BULAN 1 2 3 4 5 6 7

JANUARI
FEBRUARI
MARET
APRIL
MEI
JUNI
JULI
AGUSTUS
SEPTEMBER 15 16 17 18 19 20 21
OKTOBER 45 46 47 48 49 50 51
NOPEMBER 76 77 78 79 80 81 82
DESEMBER 106 107 108 109 110 111 112

PROYEK :

NAMA PAKET
LOKASI PROYEK :
PROVINSI :
KABUPATEN :
PANJANG PENANGANAN :
KONSULTAN PERENCANA :
TEEM LEADER :
HIGHWAY ENGINEER :
KABID BINA MARGA :
KASI PEMBANGUNAN JALAN DAN JEMBATAN :
KASI PERENCANAAN TEKNIS DAN EVALUASI :
KASI PRESERVASI JALAN DAN JEMBATAN :
TIM PERENCANA :
:
:
:
KPA :
Plt. KEPALA DINAS :
NO.KONTRAK :
TGL KONTRAK :
NILAI KONTRAK :
TAHUN ANGGARAN :
TANGGAL
8 9 10 11 12 13 14 15 16

22 23 24 25 26 27 28 29 30
52 53 54 55 56 57 58 59 60
83 84 85 86 87 88 89 90 91
113 114 115 116 117 118 119 120 121

DATA PERSONIL
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO


KEC. MANIAMOLO

KEC. TANAH MASA


SUMATERA UTARA
NIAS SELATAN
10,000.00 meter
CV. POLO CONSULTANT

ARSENNIUS HALU, ST NIP. 19700513 200502 1 002


FASRI B. J. DAELI,ST Nip. 19840612 200903 1 012 MASANUDIN NDRU
RELIVAN IFADAYAZARO DACHI, ST NIP. 19800512 200804 1 002
OSARA'O TAFONAO, ST NIP. 19770227 201001 1 006
BRUCELEE F. DACHI,ST Nip. 19870618 201402 1 001
BIMAWIJAYA LAIA NIP. 19891230 201402 1 003
ASALMAN LAIA, ST NIP. 19880823 201505 1 001
ERIMAN LAIA, SE NIP. 19780114 200502 1 001

YUSUF NACHE, ST, MM NIP. 19710418 200112 1 002 Penata Utama


GAL
17 18 19 20 21 22 23 24 25

1 2 3 4 5 6 7 8
31 32 33 34 35 36 37 38 39
61 62 63 64 65 66 67 68 69
92 93 94 95 96 97 98 99 100
122 123 124 125 126 127 128 129 130

MASANUDIN NDRURU NIP. 19720914 200701 1 034

Penata Utama
26 27 28 29 30 31

9 10 11 12 13 14
40 41 42 43 44
70 71 72 73 74 75
101 102 103 104 105
Pasangan Batu Mortar
Luas Luas
KIRI Luas VOL KANAN Luas VOL
Rata2 Rata2
NO STA. Panjang STA Panjang
A
L1 L2 H1 m2 AxP L1 L2 L3 L4 L6 H1 H2 H3 H4 m m m2
=(L1+L2/2XH1)

1 2 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

PASANGAN BATU MORTAR STA. 0 + 050 S/D STA. 0 + 052

0+050 1.20 1.20 1.00 1.20


30.00 1.20 36.00
0+080 1.20 1.20 1.00 1.20

0+350 1.00 0.80 0.80 0.72


25.00 0.72 18.00
0+375 1.00 0.80 0.80 0.72
Pasangan Batu Arah Pembuangan Di Duiker Eksisting Dekat Bronjong

0+000 1.00 0.80 1.00 0.90


10.00 0.90 9.00
0+010 1.00 0.80 1.00 0.90

TOTAL VOLUME KIRI 63.00 TOTAL VOLUME KANAN 0.00


TOTAL VOLUME = 63.000 M3
VOLUME DIBULATKAN = 63.00 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 2. DRAINASE

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 2.2.(1)


KEC. MANIAMOLO
Pasangan Batu Mortar

A. Pas. Batu Drainase


Luas Luas
KIRI Luas VOL KANAN Luas VOL
Rata2 Rata2
NO STA. Panjang STA Panjang
A =(L1+L4/2xH1+H2)
L1 L2 L3 L4 H1 H2 m2 AxP L1 L2 L3 L4 L5 H1 H2 H3 H4 m m m2
- ( L2+L3/2xH1)

1 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

PASANGAN BATU MORTAR STA. 0 + 050 S/D STA. 0 + 052

0+050 1.00 0.60 0.40 0.80 0.60 0.20 0.42


30.00 0.42 12.60
0+080 1.00 0.60 0.40 0.80 0.60 0.20 0.42

0+350 1.00 0.60 0.40 0.80 0.60 0.20 0.42


25.00 0.42 10.50
0+375 1.00 0.60 0.40 0.80 0.60 0.20 0.42
Pasangan Batu Arah Pembuangan Di Duiker Eksisting Dekat Bronjong
0+000 1.00 0.60 0.40 0.80 0.80 0.20 0.50
10.00 0.50 5.00
0+010 1.00 0.60 0.40 0.80 0.80 0.20 0.50

0+378 1.00 0.60 0.40 0.80 0.80 0.20 0.50


10.00 0.50 5.00
0+388 1.00 0.60 0.40 0.80 0.80 0.20 0.50

TOTAL VOLUME KIRI 33.10 TOTAL VOLUME KANAN 0.00


TOTAL VOLUME = 33.100 M3
VOLUME DIBULATKAN = 33.10 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
DIVISI 3. PEKERJAAN TANAH DAN
Nama Pekerjaan
GEOSINTETIK
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO
3.1.(2)
KEC. MANIAMOLO
Galian Batu Lunak

Galian Batu Lunak Posisi Bronjong


Luas Luas
KIRI Luas VOL KANAN Luas VOL
NO STA. Panjang Rata2 STA Panjang Rata2
L1 L2 H1 m2 m2 m3 L1 H1 H1 x L1 m m2
1 2 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

0+359 2.00 1.00 2.00


16.00 2.00 32.00
0+375 2.00 1.00 2.00

TOTAL VOLUME KIRI 0.00 TOTAL VOLUME KANAN 32.00


TOTAL VOLUME = 32.000 M3
VOLUME DIBULATKAN = 32.00 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam

Nama Pekerjaan DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 5.3.(3)


KEC. MANIAMOLO
Lapis Fondasi Bawah Beton Kurus

KIRI Volume KANAN Volume


Luas Luas
Panjang Lebar Tebal Bidang Panjang Lebar Tebal Bidang
NO. STA. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

0 + 359 s/d 0 + 375 0 + 359 s/d 0 + 375 16.00 1.00 1.00 1.00 16.00

0.00 0.00 16.00 16.00


Volume ( Kiri + Kanan ) = 16.00 m3
Volume Dibulatkan = 16.00 m3
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 3. PEKERJAAN TANAH
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 3.3.(1)
KEC. MANIAMOLO
Penyiapan Badan Jalan

KIRI KANAN
Luas Volume Luas Volume
Panjang Lebar Bidang Panjang Lebar Tebal Bidang
NO. STA. Ket
P l A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

1 0 + 000 s/d 0 + 050 50.00 2.25 112.50 50.00 2.25 112.50


2 0 + 050 s/d 0 + 100 50.00 2.25 112.50 50.00 2.25 112.50
3 0 + 100 s/d 0 + 150 50.00 2.25 112.50 50.00 2.25 112.50
4 0 + 150 s/d 0 + 160 10.00 2.25 22.50 10.00 2.25 22.50
RENCANA DUIKER PLAT STA. 0 + 160 S/D STA. 0 + 161,7
1 0 + 162 0 + 000 0 + 200 38.30 2.25 86.18 38.30 2.25 86.18
2 0 + 200 0 + 000 0 + 250 50.00 2.25 112.50 50.00 2.25 112.50
3 0 + 250 0 + 000 0 + 300 50.00 2.25 112.50 50.00 2.25 112.50
4 0 + 300 0 + 000 0 + 358 58.00 2.25 130.50 58.00 2.25 130.50
RENCANA DUIKER PLAT STA. 0 + 358 S/D STA. 0 + 359,7
1 0 + 360 0 + 000 0 + 400 40.30 2.25 90.68 40.30 2.25 90.68
2 0 + 400 0 + 000 0 + 450 50.00 2.25 112.50 50.00 2.25 112.50
3 0 + 450 0 + 000 0 + 500 50.00 2.25 112.50 50.00 2.25 112.50
4 0 + 500 0 + 000 0 + 550 50.00 2.25 112.50 50.00 2.25 112.50
5 0 + 550 0 + 000 0 + 600 50.00 2.25 112.50 50.00 2.25 112.50
6 0 + 600 0 + 000 0 + 651 51.00 2.25 114.75 51.00 2.25 114.75
RENCANA DUIKER PLAT STA. 0 + 651 S/D STA. 0 + 652,7
1 0 + 653 0 + 000 0 + 700 47.30 2.25 106.43 47.30 2.25 106.43
2 0 + 700 0 + 000 0 + 750 50.00 2.25 112.50 50.00 2.25 112.50
3 0 + 750 0 + 000 0 + 800 50.00 2.25 112.50 50.00 2.25 112.50
4 0 + 800 0 + 000 0 + 850 50.00 2.25 112.50 50.00 2.25 112.50
5 0 + 850 0 + 000 0 + 900 50.00 2.25 112.50 50.00 2.25 112.50
RENCANA DUIKER PLAT STA. 0 + 900 S/D STA. 0 + 903
1 0 + 903 0 + 000 0 + 925 22.00 2.25 49.50 22.00 2.25 49.50
2 0 + 925 0 + 000 Err:509 Err:509 2.25 Err:509 Err:509 2.25 Err:509

Err:509 Err:509 Err:509 Err:509


Volume ( Kiri + Kanan ) = Err:509 m3
Volume Dibulatkan = Err:509 m3
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 3.4.(1)
KEC. MANIAMOLO
Pembersihan dan Pengupasan Lahan

KIRI KANAN
Volume Luas Volume
Luas Bidang
Panjang Lebar Tebal Panjang Lebar Tebal Bidang
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

0 + 000 s/d 0 + 100 100.00 2.50 250.00 250.00 100.00 2.50 250.00 250.00
0 + 100 s/d 0 + 200 100.00 2.50 250.00 250.00 100.00 2.50 250.00 250.00
0 + 200 s/d 0 + 300 100.00 2.50 250.00 250.00 100.00 2.50 250.00 250.00
0 + 300 s/d 0 + 450 150.00 2.50 375.00 375.00 150.00 2.50 375.00 375.00

450.00 1125.00 450.00 1125.00


Volume ( Kiri + Kanan ) = 2250.00 m3
Volume Dibulatkan = 2250.00 m3
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam

Nama Pekerjaan DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 3.4.(2)
KEC. MANIAMOLO
Pemotongan Pohon Pilihan diameter 15 – 30 cm

KIRI KANAN
Volume Volume
Luas Bidang Luas Bidang
Panjang Lebar Tebal Panjang Lebar Tebal
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

1 0 + 000.00 s/d 0 + 025 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
2 0 + 025 s/d 0 + 050 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
3 0 + 050 s/d 0 + 075 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
4 0 + 075 s/d 0 + 100 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
5 0 + 100 s/d 0 + 125 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
6 0 + 125 s/d 0 + 150 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
7 0 + 150 s/d 0 + 175 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5
8 0 + 175 s/d 0 + 200 25.00 2.00 0.150 0.30 7.5 25.00 2.00 0.150 0.30 7.5

9 0 + 200 s/d 0 + 225 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625
10 0 + 225 s/d 0 + 250 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625
11 0 + 250 s/d 0 + 275 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625
12 0 + 275 s/d 0 + 300 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625
13 0 + 300 s/d 0 + 325 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625
14 0 + 325 s/d 0 + 350 25.00 1.75 0.150 0.26 6.5625 25.00 1.75 0.150 0.26 6.5625

350.00 99.38 350.00 99.38


Volume ( Kiri + Kanan ) = 198.75 m3
Volume Dibulatkan = 198.75 m3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG BACK UP DATA PERE
BIDANG BINA MARGA
Nama Paket : DIVISI 7. STRUK
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.1 (7) a
KEC. MANIAMOLO
Beton mutu sedang fc’2

PANJANG (M) LEBAR ( M ) TEBAL (M) LUAS VOLUME M3


STA
P L T A=LxT PxL

PEKERJAAN BETON fc' 20 Mpa UNTUK DUIKER PLAT

0+051 1.40 5.00 0.20 1.00 1.40

JUMLAH BETON

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
BACK UP DATA PERENCANAAN

DIVISI 7. STRUKTUR

7.1 (7) a
Beton mutu sedang fc’20 Mpa

TOTAL VOLUME
KETERANGAN
(M)

1.40

1.40 M3
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG BACK UP DATA
BIDANG BINA MARGA
Nama Paket : DIVISI 7. S
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.1
KEC. MANIAMOLO
Beton, fc

PANJANG (M) LEBAR ( M ) TEBAL (M) LUAS


STA
P L T A=LxT

PEKERJAAN BETON fc' 15 Mpa UNTUK DUIKER PLAT

0+051 0.80 5.00 0.10 0.50

JUMLAH BET

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
BACK UP DATA PERENCANAAN

DIVISI 7. STRUKTUR

7.1 (8)

Beton, fc’15 Mpa

VOLUME M3 TOTAL VOLUME


KETERANGAN
(M)
PxL

0.40 0.40

JUMLAH BETON 0.40 M3


PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam

Nama Pekerjaan DIVISI 7. STRUKTUR


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.1 (8a)
KEC. MANIAMOLO
Beton strukur Campuran 1 : 2 : 3

KIRI KANAN
Volume Volume
Luas Bidang Luas Bidang
Panjang Lebar Tebal Panjang Lebar Tebal
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

1 0 + 034 s/d 0 + 050 16.00 1.50 0.15 0.23 3.60 16.00 1.50 0.15 0.23 3.60

2 0 + 052 s/d 0 + 077 25.00 1.50 0.15 0.23 5.63 25.00 1.50 0.15 0.23 5.63

3 0 + 359 s/d 0 + 375 16.00 1.50 0.15 0.23 3.60 16.00 1.50 0.15 0.23 3.60

4 0 + 378 s/d 0 + 410 32.00 1.50 0.15 0.23 7.20 32.00 1.50 0.15 0.23 7.20

89.00 20.03 89.00 20.03


Volume ( Kiri + Kanan ) = 40.05 m3
Volume Dibulatkan = 40.05 m3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BIDANG BINA MARGA
Nama Paket :
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO
KEC. MANIAMOLO

Bentuk Batang Jlh Batang Panjang/BTG TTL PANJANG

A B C D=BxC
No.
PERHITUNGAN PENULANGAN PLAT DUIKER ( STA. 0 + 050 S/D STA. 0 + 051.90 )

Tulagan melintang (A1) 13.00 5.30 68.90


1
Tulangan Melintang (A2) 13.00 5.06 65.78

Tulangan Memanjang (B1) 34.00 2.20 74.80


2
Tulangan Memanjang (B2) 34.00 1.96 66.64

3 Angkur Beton 10.00 0.54 5.40

Jumlah Kg Tiga Buah Tulangan Plat Dui

Dibuat Oleh
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
BACK UP DATA PERENCANAAN

DIVISI 7. STRUKTUR

6.6.(1)

Baja Tulangan Polos-BjTP 280

Ø Besi BERAT BESI/M' TTL BERAT(Kg)

E F G=dxf

LAT DUIKER ( STA. 0 + 050 S/D STA. 0 + 051.90 )

12 0.89 183.50

12 0.89 175.19

12 0.89 199.21

12 0.89 177.48

12 0.89 14.38

Jumlah Kg Tiga Buah Tulangan Plat Duiker 749.77 Kg


Total Berat Besi 749.77 Kg

Dibuat Oleh
ONSULTAN PERENCANA
V. POLO CONSULTANT

EMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA

Jalan Saonigeho KM. 3 Telukdalam


Nama Pekerjaan DIVISI 7. STRUKTUR
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.9.(1)
KEC. MANIAMOLO
Pasangan Batu

URAIAN

Jarak Jarak Luas Ket


Sta A Sta
(M) L.1 L.2 L.3 H.1 H.2 Luas Rata- Volume (M) L.1 L.2 L.3 H.1 H.2 Luas Rata- Volume
=(L1+L2/2xH1)+
(M) (M) (M) (M) (M) rata ( M²) (M³) (M) (M) (M) (M) (M) (M²) rata (M³)
(H2xL3)
( M²)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

PASANGAN BATU UNTUK PLAT DUIKER STA. 0 + 050 S/D STA. 0 + 051.90
0+051 3.00 0.35 0.40 0.60 0.75 0.30 0.46 0.46 2.77

0+051 2.00 0.35 0.80 1.00 2.20 0.80 2.07 2.07 8.26

Pekerjaan Loning STA. 0 + 050 S/D STA. 0 + 051.90

0+051 1.90 0.30 0.30 0.30 0.09 0.09 0.34

11.37 -
Volume ( Kiri + Kanan ) = 11.37 M3
Volume Dibulatkan = 11.37 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 7. STRUKTUR
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.9.(1)
KEC. MANIAMOLO
Pasangan Batu

URAIAN
Kiri Kanan
Jarak A Jarak A Ket
Sta L.1 L.2 L.3 H.1 H.2 Luas Rata- Volume Sta L.1 L.2 L.3 H.1 H.2 Luas Rata- Volume
(M) =(L1+L2/2xH1) (M) =(L1+L2/2xH1)
(M) (M) (M) (M) (M) rata ( M²) (M³) (M) (M) (M) (M) (M) rata ( M²) (M³)
+(H2xL3) +(H2xL3)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Rencana Pasangan Batu TPT Dekat Duiker Plat Sta. 0+050


0+000 0.30 0.80 0.80 2.00 0.80 1.74 0+000 0.30 0.80 0.80 2.00 0.80 1.74
50.00 1.74 87.00 50.00 1.74 87.00
0+050 0.30 0.80 0.80 2.00 0.80 1.74 0+050 0.30 0.80 0.80 2.00 0.80 1.74

0+378 0.30 0.80 0.80 2.00 0.80 1.74


6.00 1.74 10.44
0+384 0.30 0.80 0.80 2.00 0.80 1.74

50.00 87.00 56.00 97.44


Volume ( Kiri + Kanan ) = 184.44 M3
Volume Dibulatkan = 184.44 M3
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DEVISI.7. STRUKTUR
BIDANG BINA MARGA 7.1 (7) a
Jl. Saonigeho KM. 3 Telukdalam Beton mutu sedang fc’20 Mpa

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU


HILISIMAETANO
NAMA PAKET REKAP
KEC. MANIAMOLO

LOKASI
KECAMATAN
T.A

Total Volume
NO. ITEM PEKERJAAN Keterangan
(m³)

1 pasangan Batu Untuk Plat Duiker 11.37

2 Pasangan Batu 184.44

Total Pasangan Batu 195.81

DIBULATKAN 195.80

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam

Nama Pekerjaan DIVISI 7. STRUKTUR

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.10.(2)


KEC. MANIAMOLO
Pasangan Batu Kosong

KIRI KANAN
Volume Luas Volume
Luas Bidang
Panjang Lebar Tebal Panjang Lebar Tebal Bidang
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P

(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

1 0 + 359 s/d 0 + 375 16.00 2.25 0.20 0.45 7.20 16.00 2.25 0.20 0.45 7.20

16.00 7.20 16.00 7.20


Volume ( Kiri + Kanan ) = 14.40 m3
Volume Dibulatkan = 14.40 m3
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 3.2.(2a)
KEC. MANIAMOLO
Timbunan Pilihan dari sumber galian

300

150
? 150

KIRI KANAN
Luas Volume Luas Volume
Panjang Lebar Tebal Bidang Panjang Lebar Tebal Bidang
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m2) (m3) (m) (m) (m) (m2) (m3)

0 + 000 s/d 0 + 010 10.00 2.00 0.30 0.60 6 10.00 2.00 0.30 0.60 6
0 + 010 s/d Err:509 Err:509 2.00 0.10 0.20 Err:509 Err:509 2.00 0.10 0.20 Err:509

Err:509 Err:509 Err:509 Err:509


Volume ( Kiri + Kanan ) = Err:509 m3
Volume Dibulatkan = Err:509 m3
Diperiksa Oleh : Dibuat Oleh :
Tim Teknis Consultant Perencana
CV. Babo Consultant

Fasri b. B. J. Daeli, MT Brucelee F. Dakhi, ST Alexander Sembiring, ST


Nip. 19840612 200903 1 012 Nip. 19870618 201402 1 001 Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 6. PERKERASAN ASPAL
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO
6.1 (1)(a)
KEC. MANIAMOLO
Lapis Resap Pengikat - Aspal Cair

300
150 150

2% 2%

KIRI Volume KANAN Volume


Luas Bidang Aspal Cair Luas Bidang Aspal Cair
Panjang Lebar Panjang Lebar
NO. STA. Ket
p l A =(p*l) AC A*Ac p l A =(p*l) AC A*Ac
(m) (m) (m2) Liter/(m2) Liter (m) (m) (m2) Liter/(m2) Liter

1 0 + 000 s/d 0 + 025 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
2 0 + 025 s/d 0 + 050 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
3 0 + 050 s/d 0 + 075 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
4 0 + 075 s/d 0 + 100 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
5 0 + 100 s/d 0 + 125 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
6 0 + 125 s/d 0 + 150 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
7 0 + 150 s/d 0 + 175 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50
8 0 + 175 s/d 0 + 200 25.00 2.00 50.00 1.00 50 25.00 2.00 50.00 1.00 50

9 0 + 200 s/d 0 + 225 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75
10 0 + 225 s/d 0 + 250 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75
11 0 + 250 s/d 0 + 275 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75
12 0 + 275 s/d 0 + 300 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75
13 0 + 300 s/d 0 + 325 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75
14 0 + 325 s/d 0 + 350 25.00 1.75 43.75 1.00 43.75 25.00 1.75 43.75 1.00 43.75

350.00 662.50 350.00 662.50


Volume ( Kiri + Kanan ) = 1325.00 Liter
Volume Dibulatkan = 1325.00 Liter
Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
DINAS PEKERJAAN UMUM DAN PENATAAN
BACK UP DATA PERENCANAAN KONSULTAN PERENCANA
RUANG

PAKET : DIVISI 6. PERKERASAN ASPAL


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO 6.1 (2)(a)
MENUJU HILISIMAETANO
KEC. MANIAMOLO LAPIS PEREKAT - ASPAL CAIR

URAIAN
Kiri Kanan Total Volume
Jarak Jarak Keterangan
Sta L AC Luas Volume Sta L AC Luas Volume (Liter)
(M) (M)
(M) (Liter) (M²) (Liter) (M) (Liter) (M²) (M³)
1 2 3 5 6 7 8 9 10 12 13 14 15 16

0+000 0+000
50.00 2.00 0.35 0.70 35.00 50.00 2.00 0.35 0.70 35.00 70.00
0+050 0+050
25.00 2.00 0.35 0.70 17.50 25.00 2.00 0.35 0.70 17.50 35.00
0+075 0+075
25.00 2.00 0.35 0.70 17.50 25.00 2.00 0.35 0.70 17.50 35.00
0+100 0+100
(100.00) 2.00 0.35 0.70 (70.00) - 100.00 2.00 0.35 0.70 - 70.00 (140.00)
0+000 0+000

Jumlah 0.00 Jumlah 0.00 Total Seluruh Volume Prime Coat -


Liter
KOMULATIF -

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT
DINAS PEKERJAAN UMUM DAN PENATAAN
BACK UP DATA PERENCANAAN KONSULTAN PERENCANA
RUANG

PAKET : DIVISI 6. PERKERASAN ASPAL


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO 6.1 (2)(a)
MENUJU HILISIMAETANO
KEC. MANIAMOLO LAPIS PEREKAT - ASPAL CAIR

URAIAN
Kiri Kanan Total Volume
Jarak Jarak Keterangan
Sta L AC Luas Volume Sta L AC Luas Volume (Liter)
(M) (M)
(M) (Liter) (M²) (Liter) (M) (Liter) (M²) (M³)
1 2 3 5 6 7 8 9 10 12 13 14 15 16
HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 6. PERKERASAN ASPAL
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 6.6.(1)
KEC. MANIAMOLO
Lapis Penetrasi Permukaan Macadam

400
200 200

2% 2%

KIRI Volume KANAN Volume


Luas Bidang Luas Bidang
Panjang Lebar Tebal Panjang Lebar Tebal
NO. STA. Ket
P l t A =(l*t) A*P P l t A =(l*t) A*P
(m) (m) (m) (m )
2
(m )
3
(m) (m) (m) (m )
2
(m )
3

1 0 + 000 s/d 0 + 025 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
2 0 + 025 s/d 0 + 050 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
3 0 + 050 s/d 0 + 075 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
4 0 + 075 s/d 0 + 100 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
5 0 + 100 s/d 0 + 125 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
6 0 + 125 s/d 0 + 150 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
7 0 + 150 s/d 0 + 175 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5
8 0 + 175 s/d 0 + 200 25.00 2.00 0.05 0.10 2.5 25.00 2.00 0.05 0.10 2.5

9 0 + 200 s/d 0 + 225 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875
10 0 + 225 s/d 0 + 250 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875
11 0 + 250 s/d 0 + 275 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875
12 0 + 275 s/d 0 + 300 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875
13 0 + 300 s/d 0 + 325 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875
14 0 + 325 s/d 0 + 350 25.00 1.75 0.05 0.09 2.1875 25.00 1.75 0.05 0.09 2.1875

350.00 33.13 350.00 33.13


Volume ( Kiri + Kanan ) = 66.25 m3
Volume Dibulatkan = 66.25 m3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

NAMA PEKERJAAN DIVISI 7. STRUKTUR


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.1 (7) a
KEC. MANIAMOLO
Beton mutu sedang fc’20 MPa

L1 L2 L3 H1 H2 H3 Jlh P VOLUME
SKETSA GAMBAR Nama KETERANGAN
m' m' m' m' m' m' Sisi m' m³
L3 L2 BOX CULVERT

H1 V1 3.00 0.20 2 5.00 6.000 V1 = L1 x H1 x P x Jlh


BOX CULVERT H3

V2 0.20 2.50 2 5.00 5.000 V2 = L2 x H2 x P x Jlh


H2

V3 0.20 0.20 4 5.00 0.400 V3 = 0.5 x L3 x H3 x P x Jlh

H1

L1
DINDING PENAHAN BAWAH
DINDING PENAHAN BAWAH
15
15 V1 0.30 0.80 2 3.00 1.440 V1 = L1 x H1 x P x Jlh
10

H1 V2 0.30 0.80 2 5.00 2.400 V1 = L1 x H1 x P x Jlh


40
H1
10
DINDING SAYAP
L1
P
V1 0.20 0.50 2 5.00 1.000 V1 = L1 x H1 x P1 x Jlh

V2 0.20 2.50 4 1.00 2.000 V2 = L1 x H2 x P2 x Jlh


DINDING SAYAP
P1

H1 H 1

H 2
H2

10 TOTAL VOLUME 1 UNIT BOX CULVERT = 18.24


10 L 1
P2 Badan Box P2
Pot. C TOTAL VOLUME DIBULATKAN = 19.64
PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DIVISI 7. STRUKTUR
BIDANG BINA MARGA 7.1 (7) a
Jl. Saonigeho KM. 3 Telukdalam Beton mutu sedang fc’20 MPa

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU


HILISIMAETANO
NAMA PAKET REKAP
KEC. MANIAMOLO

LOKASI
KECAMATAN
T.A

Total Volume
NO. ITEM PEKERJAAN Keterangan
(m³)

1 pasangan Batu Untuk Plat Duiker 1.40

2 Pasangan Batu 19.64

Total Pasangan Batu 21.04

DIBULATKAN 21.04

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA
BIDANG BINA MARGA KABUPATEN NIAS SELATAN
DIVISI 7. STRUKTUR
NAMA PAKET :
7.10.(3a)

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU


HILISIMAETANO Bronjong dengan kawat yang dilapisi Galvanis
KEC. MANIAMOLO
Bronjong dengan Kawat yang Dilapisi Galvanis

Perhitungan Beronjong Volume


Panjang Lebar Tinggi Luas
NO. Posisi
p l t A=LxT PxA
(m) (m) (m) (m) (m3)

BRONJONG STA. 0 + 359 S/D STA. 0 + 375 SKET

Lapis 1 16.00 2.00 0.50 1.00 16.00


lapis 2 16.00 2.00 0.50 1.00 16.00
Lapsi 3 16.00 2.00 0.50 1.00 16.00
Lapis 4 16.00 1.00 0.50 0.50 8.00
lapis 5 16.00 1.00 0.50 0.50 8.00
Lapis 6 16.00 1.00 0.50 0.50 8.00
Lapis 7 16.00 1.00 0.50 0.50 8.00
Lapis 8 16.00 1.00 0.50 0.50 8.00
Lapis 9 16.00 1.00 0.50 0.50 8.00
Lapis 10 16.00 1.00 0.50 0.50 8.00
Lapis 11 16.00 1.00 0.50 0.50 8.00

LEMBAR PERTAMA 112.00

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DEVISI.7. STRUKTUR
BIDANG BINA MARGA 7.1 (7) a
Jl. Saonigeho KM. 3 Telukdalam Beton mutu sedang fc’20 Mpa
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU
HILISIMAETANO
NAMA PAKET
KEC. MANIAMOLO

LOKASI :- KONSULTAN PERENCANA


KECAMATAN : SIMAMBAWA
T.A : 2019 CV. POLO CONSULTANT

Total Volume
NO. ITEM PEKERJAAN Keterangan
(m³)

1 BETON MUTU SEDANG fc'10 Mpa BOX CULVERT 2.120

2 BETON MUTU SEDANG fc'10 Mpa 2 BUAH PLAT DUIKER 0.400

GRAND TOTAL BERAT BESI 2.52

DIBULATKAN 2.52
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

NAMA PEKERJAAN DIVISI 7. STRUKTUR


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.1 (8)
KEC. MANIAMOLO
Beton, fc’15 Mpa

L1 L2 L3 H1 H2 H3 Jlh P VOLUME
SKETSA GAMBAR Nama KETERANGAN
m' m' m' m' m' m' Sisi m' m³

DI BAWAH BOX CULVERT

V1 1.90 0.10 1 4.40 0.836 V1 = L1 x H1 x P x Jlh


BOX CULVERT

H1
L1

DI BAWAH DINDING PENAHAN BAWAH


DINDING PENAHAN BAWAH
V1 0.30 0.10 2 1.90 0.114 V1 = L1 x H1 x P x Jlh
15
15
10

40
DI BAWAH DINDING SAYAP
H1
10 H1
P L1
V1 0.20 0.10 4 0.50 0.040 V1 = L1 x H1 x P1 x Jlh

DINDING SAYAP

H1
H1
L1
P1 Badan Box P1

TOTAL VOLUME 1 UNIT BOX CULVERT = 0.990

Pot. C TOTAL VOLUME DIBULATKAN = 0.99


PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DIVISI 7. STRUKTUR
BIDANG BINA MARGA 7.1 (8)
Jl. Saonigeho KM. 3 Telukdalam Beton, fc’15 Mpa

PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU


HILISIMAETANO
NAMA PAKET REKAP
KEC. MANIAMOLO

LOKASI
KECAMATAN
T.A

Total Volume
NO. ITEM PEKERJAAN Keterangan
(m³)

1 pasangan Batu Untuk Plat Duiker 0.40

2 Pasangan Batu 0.99

Total Pasangan Batu 1.39

DIBULATKAN 1.39

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Nama Paket : DIVISI 7. STRUKTUR
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 7.3 (2)
KEC. MANIAMOLO
Baja Tulangan U 24 Polos

Panjang/ TTL BERAT TTL


Bentuk Batang Jlh Batang Ø Besi
BTG PANJANG BESI/M' BERAT(Kg)

STA A B C D=BxC E F G=dxf

Tulagan melintang (A1) 26.13 0.92 24.04 12 0.888 21.344

0 + 128 0 + 132

Tulangan Melintang (A2) 6.13 3.92 24.04 12 0.888 21.344

Angkur Beton 12.80 0.92 11.78 12 0.888 10.454

Jumlah Volume Tulangan Plat Duiker + 53.142 Kg


Total Berat Besi 53.142 Kg

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

NAMA PEKERJAAN DIVISI 7. STRUKTUR


PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU 7.3 (1)
HILISIMAETANO
KEC. MANIAMOLO
Baja Tulangan U 24 Polos

NAMA Panjang Batang / Potong Kait Total Panjang Space Dia. Total Berat
NO. Jumlah Batang Total Panjang Berat/ Meter Keterangan
BATANG Potongan (mm) (Kg)
a b c d e (5xØ)2 m'

1 A1 0.94 0.15 0.34 0.34 0.15 1.92 0.4 25 48 16 1.578 75.756

2 B2 2.92 0.12 2.92 0.12 0.14 6.22 0.2 50 311 12 0.888 276.093

3 B1 2.42 0.12 2.42 0.12 0.14 5.22 0.4 50 261 12 0.888 231.705

4 A2 0.94 0.15 0.34 0.34 0.15 1.92 0.4 25 48 16 1.578 75.756

5 C1 4.92 0.14 5.06 0.2 46 232.76 10 0.617 143.497

6 D1 0.64 0.14 0.78 0.4 50 39 10 0.617 24.044

7 E1 2.92 0.12 2.92 0.12 0.14 6.22 0.2 8 49.76 10 0.617 30.677

8 F1 0.92 0.15 0.92 0.14 2.13 0.2 30 63.9 12 0.888 56.728

9 G1 4.92 0.14 5.06 0.2 20 101.2 10 0.617 62.390

10 H1 0.92 0.15 0.92 0.14 2.13 0.2 50 106.5 12 0.888 94.546

8 I1 1.12 0.12 1.12 0.14 2.5 0.2 26 65 10 0.617 40.073

9 K1 2.92 0.12 2.92 0.12 0.14 6.22 0.2 10 62.2 12 0.888 55.219

10 L1 0.62 0.12 0.62 0.12 0.14 1.62 0.2 32 51.84 12 0.888 46.021

11 M1 4.92 12 4.92 12 0.14 33.98 0.2 6 203.88 10 0.617 125.692

TOTAL BERAT 1 UNIT BOX CULVERT 1,338.196

BERAT DIBULATKAN 1,338.19


PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DIVISI 7. STRUKTUR

BIDANG BINA MARGA 7.3 (1)

Jl. Saonigeho KM. 3 Telukdalam Baja Tulangan Polos-BjTP 280

PEMBANGUNAN JALAN SIMENISASI DARI DESA


EHO MENUJU HILISIMAETANO
NAMA PAKET REKAP
KEC. MANIAMOLO

Total Berat
NO. ITEM PEKERJAAN Keterangan
(Kg)

1 Jumlah Kg Tiga Buah Tulangan Plat Duiker 749.767

Total Pasangan Batu 749.77

DIBULATKAN 749.77

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG BACK UP DATA PERENCANAA
BIDANG BINA MARGA
Nama Paket : DIVISI 7. STRUKTUR
6.6.(1)
#REF!
Besi Tulangan
Bentuk Batang Jlh Batang Panjang/BTG TTL PANJANG Ø Besi BERAT BESI/M'

A B C D=BxC E F
No.
PERHITUNGAN PENULANGAN PLAT DUIKER STA. 1+088 S/D 1+090

1 Melintang A 1 58 5.3 307.4 16 1.578

2 Melintang A 2 58 4.9 284.2 16 1.578

3 Tulangan Memanjang B1 34 6.44 218.96 16 1.578

4 Tulangan Memanjang B2 34 6.04 205.36 16 1.578

5 Tulangan C 1 30 6.44 193.2 16 1.578

6 Tulangan C 2 30 6.04 181.2 16 1.578

7 Tulangan D 1 58 5.3 307.4 13 1.042

8 Tulangan D 2 58 4.9 284.2 16 1.578

10

11

12

13

14

15

16

17

18

19

20

21
Jumlah Volume Tulangan Plat Duiker + Jumlah Volume Tulangan Plat Par
Total Berat Besi
BACK UP DATA PERENCANAAN

DIVISI 7. STRUKTUR
6.6.(1)
Besi Tulangan
TTL BERAT(Kg)

G=dxf
N PLAT DUIKER STA. 1+088 S/D 1+090

485.151

448.536

345.571

324.107

304.916

285.977

320.275

448.536

2963.070 Kg
2963.070 Kg
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN BACK UP DATA RENCANA

NAMA PEKERJAAN DIVISI 7. STRUKTUR


7.3 (1) CV. POLO CONSULTANT
#REF!
Baja Tulangan U 24 Polos

Panjang Batang / Potong Kait Total Space Dia.


NAMA Jumlah Total Berat/ Total Berat
NO. Panjang Keterangan
BATANG Batang Panjang Meter (Kg)
a b c d e (5xØ)2 Potongan m' (mm)

1 A1 3.5 0.2 3.5 0.2 0.14 7.54 0.2 59 445.10 12 0.888 395.138

2 B2 1 1 1.89 0.28 0.28 4.45 0.5 23.60 105.02 16 1.578 165.747

3 B3 3.5 0.2 3.5 0.2 0.14 7.54 0.2 59 445.10 12 0.888 395.138

4 B4 1 1 1.89 0.28 0.28 4.45 0.5 23.60 105.02 16 1.578 165.747

5 B5 3.5 0.12 3.62 0.2 136 492.32 10 0.617 303.515

6 B6 0.8 0.12 0.92 0.2 118 108.56 10 0.617 66.927

7 B7 3.5 0.16 3.66 7.4 27.05 13 1.042 28.188

8 B8 0.20 0.74 0.2 0.74 0.12 2 0.2 35 70 10 0.617 43.155

9 B9 4.2 0.15 4.2 0.15 0.156 8.856 0.2 16 141.696 13 1.042 147.631

10 B10 0.7 0.15 0.7 0.15 0.156 1.856 0.2 30 55.68 13 1.042 58.012

11 B11 5.9 0.15 0.156 6.206 0.2 16 99.296 13 1.042 103.455

12 B12 0.7 0.15 0.7 0.13 1.68 0.2 68 114.24 13 1.042 119.025

TOTAL BERAT 1 UNIT BOX CULVERT 1,991.679

BERAT DIBULATKAN 1,991.67


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

NAMA PEKERJAAN DIVISI 7. STRUKTUR


7.1 (7) a
#REF!
Beton mutu sedang fc’20 MPa

L1 L2 L3 H1 H2 H3 Jlh P VOLUME
SKETSA GAMBAR Nama KETERANGAN
m' m' m' m' m' m' Sisi m' m³
L3 L2 BOX CULVERT

H1
V1 3.60 0.30 2 6.00 12.960 V1 = L1 x H1 x P x Jlh
BOX CULVERT H3

V2 0.30 3.00 2 6.00 10.800 V2 = L2 x H2 x P x Jlh


H2

V3 0.30 0.30 4 6.00 1.080 V3 = 0.5 x L3 x H3 x P x Jlh


H1

L1

DINDING PENAHAN BAWAH


DINDING PENAHAN BAWAH
15
15 V1 0.40 0.70 2 3.60 2.016 V1 = L1 x H1 x P x Jlh
10

40 H1
H1

10 DINDING SAYAP
L1
P
V1 0.30 0.50 4 1.20 0.720 V1 = L1 x H1 x P1 x Jlh

V2 0.30 4.30 4 1.20 6.192 V2 = L1 x H2 x P2 x Jlh


DINDING SAYAP
P1

H1 H 1

H2
H2

TOTAL VOLUME 1 UNIT BOX CULVERT = 33.768


10
10
L1
P2 Badan Box P2 Pot. C TOTAL VOLUME DIBULATKAN = 33.76
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN NIAS SELATAN

NAMA PEKERJAAN DIVISI 7. STRUKTUR


7.1 (10)
#REF!
Beton mutu rendah fc’10 Mpa

L1 L2 L3 H1 H2 H3 Jlh P VOLUME
SKETSA GAMBAR Nama KETERANGAN
m' m' m' m' m' m' Sisi m' m³

DI BAWAH BOX CULVERT

V1 3.60 0.10 1 5.90 2.124 V1 = L1 x H1 x P x Jlh


BOX CULVERT

H1
L1

TOTAL VOLUME 1 UNIT BOX CULVERT = 2.12

Pot. C TOTAL VOLUME DIBULATKAN = 2.12


PEMERINTAH KABUPATEN NIAS SELATAN BACK UP DATA RENCANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG DEVISI.7. STRUKTUR
BIDANG BINA MARGA 7.3 (3)
Jl. Saonigeho KM. 3 Telukdalam Baja Tulangan U 32 UlLUR

NAMA PAKET #REF!


KONSULTAN PERENCANA

LOKASI
KECAMATAN : SIMAMBAWA
T.A : 2019 CV. POLO CONSULTANT

Total Berat
NO. ITEM PEKERJAAN Keterangan
(Kg)

1 BESI TULANGAN BOX CULVERT 1,991.670

2 BESI TULANGAN 2 BUAH PLAT DUIKER 53.142

GRAND TOTAL BERAT BESI 2,044.81

DIBULATKAN 2,044.81
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 7. STRUKTUR
6.6.(1)
#REF!
Pasangan Batu

`
URAIAN
Kiri Kanan
Jarak Ket
Sta L.1 L.2 L.3 L.4 L.5 L.6 H.1 H.2 H.3 H.4 Luas Luas Rata- Volume
(M)
(M) (M) (M) (M) (M) (M) (M) (M) (M) (M) (M²) rata ( M²) (M³)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

PERHITUNGAN PASANGAN PLAT DUIKER STA. 0+006 S/D 0+007

0+358 5.00 0.30 0.50 0.70 0.80 0.30 0.53 5.30

PERHITUNGAN LONING PLAT DUIKER

0+358 2.00 0.30 0.30 0.30 0.1 0.36

TOTAL VOLUME 5.66


Volume ( Kiri + Kanan ) = 5.66 M3
Volume Dibulatkan = 5.66 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PEMERINTAH KABUPATEN NIAS SELATAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
BACK UP DATA PERENCANAAN
BIDANG BINA MARGA
Jalan Saonigeho KM. 3 Telukdalam
Nama Pekerjaan DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA
PEMBANGUNAN JALAN SIMENISASI DARI DESA EHO MENUJU HILISIMAETANO 10.1.(1)
KEC. MANIAMOLO
Galian pada Saluran Air atau Lereng untuk Pemeliharaan

Pasangan Batu Mortar


Luas Luas
KIRI Luas VOL KANAN Luas VOL
NO STA. Panjang Rata2 STA Panjang Rata2
L1 L2 H1 m 2
m2 m 3
L1 L2 L3 L4 L6 H1 H2 H3 H4 m m m2
1 2 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
0+000 0.60 0.40 0.60 0.30
25.00 0.30 7.50
0+025 0.60 0.40 0.60 0.30
0+030 0.60 0.40 0.60 0.30 0+025 0.60 0.40 0.60 0.30
20.00 0.30 6.00 25.00 0.30 7.50
0+050 0.60 0.40 0.60 0.30 0+050 0.60 0.40 0.60 0.30
0+050 0.60 0.40 0.60 0.30 0+050 0.60 0.40 0.60 0.30
25.00 0.30 7.50 25.00 0.30 7.50
0+075 0.60 0.40 0.60 0.30 0+075 0.60 0.40 0.60 0.30

TOTAL VOLUME KIRI 13.50 TOTAL VOLUME KANAN 22.50


TOTAL VOLUME = 36.000 M3
VOLUME DIBULATKAN = 36.00 M3

Dibuat Oleh:
KONSULTAN PERENCANA
CV. POLO CONSULTANT

HEMAN F H SIREGAR, ST
Cost & Quantity Engineer
PERHITUNGAN VOLUME DAN HARGA SATUAN
Volume Satuan Harga Satuan Total Harga Satuan
1. Volume Pas. Batu Arah Telukdalam Kiri
Volume : 100.80 M3
2. Volume Pas. Batu Arah Lolowau Kiri
Panjang 2 M + Bax Kontrol + Tambahan : 16.70 M3
3. Volume Pas. Tangga Pembuangan :

Panjang 3 M Lebar 2 M : 4.50

Total Pasangan Batu : 122.00 M3 1,009,853.44 123,202,119.68

3. Volume Pas. Parit Arah Telukdalam


Panjang 22 M : 6.60 M3

4. Volume Pas. Parit Arah Telukdalam


Panjang 1 M : 0.30 M3

Total Volume parit : 6.90 M3 1,009,853.44 6,967,988.74

Galian Biasa 22.00 M3 24,560.14 540,323.08

5. Volume Rabat Beton : 6.15 M3 2,771,560.40 17,045,096.46

6. Volume Lantai Kerja Panjang 22 M : 2.34 M3 2,771,560.40 6,485,451.34


8.49
7. Pasangan batu Kosong Panjang 22 M + Bak Kontrol : 4.68 M3 1,009,853.44 4,726,114.10

8. Volume Timbunan Pilihan


Volume : 40.00 262,626.89 10,505,075.60

Volume : 1.40 262,626.89 367,677.65


41.40

Total Biaya Keseluruhan 169,839,846.64