Kabupaten Ciamis Jenis Prasarana Perkerasan Sand Sheet

Kecamatan Cikoneng Take Of Sheet Lokasi Jalan Desa Pasar Sabtu


Desa Cikoneng Volume 420 m² 0.020

PERKERASAN SEND SHEET TB. 2 CM SS-A

0.10 m 2,8 - 4 m 0.10

Perhirtungan Volume Bahan

1. Volume Aspal

Volume Sand Sheet V1 = ( 9.30 + 5.20 ) X 5.50 = 39.9 M²


2.0
V2 = 15.00 x 5.20 = 78.0 M²
V3 = 10.15 x 4.00 = 40.6 M²
V4 = 24.30 x 4.00 = 97.2 M²
V5 = 25.40 x 2.80 = 71.1 M²
V6 = 20.70 x 4.00 = 82.8 M²
V7 = 0.50 x 4.00 X 5.7 = 11.4 M²
421.00 M²
Bak Kontrol = 0.60 x 0.60 = 0.36 M²
= 420.6 M²
Labur Aspal V total = 420.6 M²

I. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK LAPIS PEREKAT ( TEAK COAT )
Ref Analisa Dinas Binamarga
Ket 1 Drum Aspal Berat = 155 Kg
A. Bahan Koefisien
1. Aspal = 0.5000 X 420.64 = 210.3 Kg Dibulatkan 210
2. Minyak tanah/Solar = 0.2346 X 420.64 = 98.7 Liter Dibulatkan 99
3. Kayu Bakar = 0.0019 X 420.64 = 0.8 m3 Dibulatkan 1

B. Upah
1. Pekerja = 0.0247 x 420.64 = 10.39 HOK Dibulatkan 10

II. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK SAND SHEET


Ref Analisa Dinas Binamarga
Ket 1 Drum Aspal Berat = 155 Kg
A. Bahan Koefisien
1. Aspal 2.500 X 420.64 = 1051.6 Kg Dibulatkan 1052
2. Pasir Aspal 0.020 X 420.64 = 8.4 m3 Dibulatkan 8
3. Kayu bakar 0.018 X 420.64 = 7.6 m3 Dibulatkan 8

B. Upah
1. Juru godog aspal 0.005 x 420.64 = 2.10 HOK Dibulatkan 2
2. Pekerja Aspal = 0.162 x 420.64 = 68.14 HOK Dibulatkan 68
3. Tukang Aspal = 0.008 x 420.64 = 3.37 HOK Dibulatkan 3

III . Sewa alat


1. Mesin Gilas = 0.0020 X 420.64 = 0.84127 x 1.00 = 0.841 Dibulatkan 2

III. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK LPB Agregat Kelas B
Ref Analisa Dinas Binamarga
A. Bahan Koefisien
1. Agregat Kelas B 1.200 X 42.06 = 50.5 M³ Dibulatkan 50

B. Upah
1. Pekerja = 0.040 x 42.06 = 1.68 HOK Dibulatkan 2
2. Mandor = 0.007 x 42.06 = 0.28 HOK Dibulatkan 0

III . Sewa alat


1. Mesin Gilas = 0.0333 X 42.06 = 1.4007146 x 1.00 = 1.401 Dibulatkan 2

III. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK LAPIS PONDASI / PERATA PENETRASI MAKADAM
Ref Analisa Dinas Binamarga
Ket 1 Drum Aspal Berat = 155 Kg
A. Bahan Koefisien
1. Aspal 62.500 X 16.83 = 1051.6 Kg Dibulatkan 1052
2. Batu Pecah 3-5 0.9904 X 16.83 = 16.7 m3 Dibulatkan 17
3. Batu Pecah 1-2 0.3096 X 16.83 = 5.2 m3 Dibulatkan 5
2. Pasir Aspal 0.1587 X 16.83 = 2.7 m3 Dibulatkan 3
3. Kayu bakar 0.1009 X 16.83 = 1.7 m3 Dibulatkan 2

B. Upah
1. Pekerja = 2.914 x 16.83 = 49.03 HOK Dibulatkan 49
2. Mandor = 0.043 x 16.83 = 0.72 HOK Dibulatkan 1

III . Sewa alat


1. Mesin Gilas = 0.0020 X 16.83 = 0.0336508 x 1.00 = 0.034 Dibulatkan 1
Sand Sheet
u
0.020 m

116.65

20

Kg 0.84872
Liter 0.206
m3

3.125 3.75 2.5


HOK 10.51588 0.025 0.03 0.02
15.77381 0.0225 0.027 0.018
0.00625 0.0075 0.005
0.2025 0.243 0.162
0.066666667 0.01 0.012 0.008

Kg
m3
m3

0.983935743 0.140562249
HOK
HOK 0.0200803213
HOK

hari

HOK
HOK

hari

ASI MAKADAM

Kg
m3
m3
m3
m3

HOK
HOK

hari
kg Aspal
m3 Pasair pasang
m3 Kayu bakar
org Juru godog aspal
org Pekerja
org Mandor
Format Kebutuhan Bahan Alat Upah Untuk RAB

No. Uraian/Bahan Volume Satuan Harga Sat Jumlah Harga PPN PPH

1 Aspal 1.0 Drum 1,400,000 1,400,000 127,272.73 19,091


2 Pasir Aspal 1.0 m3 230,000 230,000 20,909.09 3,136
3 Batu Pecah 3-5 1.0 m3 220,000 220,000 20,000.00 3,000
4 Batu Pecah 1-2 1.0 m3 220,000 220,000 20,000.00 3,000
5 Agregat Kelas B 1.0 Buah 110,000 110,000 10,000.00 1,500
7 Kayu bakar 1.0 m3 75,000 75,000 6,818.18 1,023
8 Minyak tanah/Solar 1.0 ltr 6,500 6,500 590.91 89
9 Pengki 1.0 buah 25,000 25,000 2,272.73 341
10 Roda Artco 1.0 unit 500,000 500,000 45,454.55 6,818
11 Drum Bekas 1.0 bh 250,000 250,000 22,727.27 3,409
12 Sewa Mesin Gilas 1.0 ls 600,000 600,000 54,545.45 8,182
13 Mobilisasi & Demobilisa 1.0 ls 1,600,000 1,600,000 145,454.55 21,818
14 - Juru Godog Aspal 1.0 Hok 70,000 70,000 Nihil
15 - Pekerja Aspal 1.0 Hok 75,000 75,000 Nihil
16 - Tukang Aspal 1.0 Hok 85,000 85,000 Nihil
17 -Mandor 1.0 Hok 90,000 90,000 Nihil
Jumlah PPN + PPH Yang Harus dibayar 476,045 71,407
Pembulata
Jumlah Harga + PPN+PPH n Harga Sat
Harga Sat
PPN+PPH RAB
1,546,364 146,364 146,300 1,546,300
254,045 24,045 24,000 254,000
243,000 23,000 23,000 243,000
243,000 23,000 23,000 243,000
121,500 11,500 11,500 121,500
82,841 7,841 7,800 82,800
7,180 680 600 7,100
27,614 2,614 2,600 27,600
552,273 52,273 52,200 552,200
276,136 26,136 26,100 276,100
662,727 62,727 62,700 662,700
1,767,273 167,273 167,200 1,767,200
Nihil - 70,000
Nihil - 75,000
Nihil - 85,000
Nihil - 90,000
5,783,952 547,452 547,000 5,783,500
RENCANA ANGGARAN BIAYA

Propinsi : Jawa Barat No. RAB


Kabupaten : Ciamis RAB Untuk APBDes Program
Kecamatan : Cikoneng Jenis Kegiatan
Desa : Cikoneng Ukuran

VOLUME Harga BIAYA (


Satuan
URAIAN Dana Satuan
Total Swadaya Swadaya
Desa (Rp)

I. Bahan
1 Aspal 15 15 drum 1,546,300 -
2 Pasir Aspal 11 11 m³ 254,000 -
3 Kayu bakar 9 9 m³ 82,800 -
4 Batu Pecah 3-5 17 17 m³ 243,000 -
5 Batu Pecah 1-2 5 5 m³ 243,000 -
6 Agregat Kelas B 50 50 m³ 121,500 -
7 Minyak tanah/Solar 99 99 m³ 7,100 -
Sub Total 1) -
II. Alat
1 Mobilisasi & Demobilisasi Mesin Gilas 1 1 Ls 1,767,200 -
2 Sewa Mesin Gilas 5 5 hari 662,700 -
3 Pengki 10 10 Buah 27,600 -
4 Roda Artco 2 2 Unit 552,200 -
5 Drum Bekas 3.00 3 Buah 276,100 -
Sub Total 2) -
III. Upah
1 Juru Godog 2 2 HOK 70,000 -
2 Pekerja 119 119 HOK 75,000 -
3 Tukang 3 3 HOK 85,000 -
4 Mandor 1 1 HOK 90,000 -
Sub Total 3) -
IV. Lain Lain
1 Papan Proyek / Kegiatan 1 1 HOK 100,000 -
2 Prasasti 1 1 HOK 350,000 -
Sub Total 3) -
Jumlah Total -

Dari Dana Desa

SUMBER DANA Dari Swadaya

TOTAL

…………………….., …………………………
Disetujui Oleh : Dibuat Oleh :
Kepala Desa TPK

__________________________ _____________________
RENCANA ANGGARAN BIAYA

: Propinsi
: Dana Desa Kabupaten
: Peningkatan Jalan Desa Pasar Saptu Kecamatan
: Panjang 116 M' ; Lebar 2,8 - 4 M Desa

BIAYA (Rp)

Dana Desa Total

I. Bahan
23,194,500 23,194,500 ###
2,794,000 2,794,000 ###
745,200 745,200 ###
4,131,000 4,131,000
1,215,000 1,215,000
6,075,000 6,075,000
702,900 702,900 ###
38,857,600 Sub Total 1)
38,857,600
II. Alat
1,767,200 1,767,200 ###
3,313,500 3,313,500 ###
276,000 276,000
1,104,400 1,104,400
828,300 828,300
7,289,400 Sub Total 2)
7,289,400
III. Upah
140,000 140,000 ###
8,925,000 8,925,000 ###
255,000 255,000
90,000 90,000
9,410,000 Sub Total 3)
9,410,000
III. Upah
100,000 100,000 ###
350,000 350,000 ###
450,000 Sub450,000
Total 3)
56,007,000 56,007,000
Jumlah Total

Dari Dana Desa 56,007,000

Dari Swadaya -

TOTAL 56,007,000

…………….., …………………………….2017…………………….., …………………………….2015


Dibuat Oleh : Disetujui Oleh :
TPK Kepala Desa

_____________________ __________________________