PEKERJAAN BEGISTING
A.4.1.1 .20 pemasangan 1m2 begisting untuk pondasi
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
PEKERJAAN BETON
A.4.1.1 .1 Membuat 1m3 beton mutu f'c =7,4 Mpa ( k100 ) ( adukan 1pc : 3,5 pp : 4 krkl )
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.1.1 .5 Membuat 1m3 beton mutu f'c =14,5 Mpa ( k125 ) slump (12± 2)cm,w/c=0,66
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.1.1 .6 Membuat 1m3 beton mutu f'c =16,9 Mpa ( k200 ) slump (12± 2)cm,w/c=0,61 adukan 1pc : 2psr : 3kr
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.1.1 .7 Membuat 1m3 beton mutu f'c =19,3 Mpa ( k225 ) slump (12± 2)cm,w/c=0,58 adukan 1pc : 1,9psr : 2,
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.5.2.2 Pemasangan 1m2 Atap Baja Ringan + Reng Untuk Atap Genteng Metal Roof
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.6.1.5 Pembuatan dan Pemasangan 1m2 daun pintu panel ,kayu kls I atau II
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.6.1.6 Pembuatan dan Pemasangan 1m2 daun pintu dan jendela kaca ,kayu kls I atau II
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A TENAGA Pekerja
Tukang kayu 0.2000 Oh Rp 75,000.00
Kepala Tukang 0.0400 Oh Rp 80,000.00
Mandor
JUMLAH TENAGA KERJA
B Bahan Kaca Polos 5 mm 1.2000 m2 Rp 150,000.00
Bingkai nako 2.0000 m Rp 19,000.00
Bout Mur 0.0800 bh Rp 35,000.00
Besi terali Nako 2.3300 btng Rp 102,000.00
JUMLAH HARGA BAHAN
C Peralatan
JUMLAH HARGA ALAT
D Jumlah ( A + B + C )
E Overhead & Profit (Contoh 15 %) 10% X D
F Harga Satuan Pekerjaan ( D + E )
A.4.7.1.5 1M2 Pengecatan bidang kayu baru ( 1 lapis plamir,i lapis cat dasar,3 lapis cat penutup )
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.7.1.10 1M2 Pengecatan tembok baru ( 1 lapis plamir,i lapis cat dasar,2 lapis cat penutup )
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
A.4.8.1.2 1 BH Wastafel
NO URAIAN PEKERJAAN KODE KOEFISIEN SATUAN HARGA SATUAN
Rp 6,000.00
Rp 7,500.00
Rp 800.00
Rp 450.00
Rp 14,750.00
Rp 24,185.80
Rp 420.00
Rp 16,930.06
Rp 41,535.86
Rp 56,285.86
Rp 5,628.59
Rp 61,914.45
JUMLAH HARGA
Rp 3,000.00
Rp 7,500.00
Rp 800.00
Rp 450.00
Rp 11,750.00
Rp -
Rp 11,750.00
Rp 1,175.00
Rp 12,925.00
JUMLAH HARGA
Rp -
Rp 47,250.00
Rp 4,725.00
Rp 51,975.00
JUMLAH HARGA
Rp 54,000.00
Rp 4,050.00
Rp 58,050.00
Rp -
Rp 58,050.00
Rp 5,805.00
Rp 63,855.00
JUMLAH HARGA
Rp 90,000.00
Rp 5,400.00
Rp 95,400.00
Rp -
Rp 95,400.00
Rp 9,540.00
Rp 104,940.00
Rp 30,000.00
Rp 4,500.00
Rp 34,500.00
Rp -
Rp 34,500.00
Rp 3,450.00
Rp 37,950.00
JUMLAH HARGA
Rp 30,000.00
Rp 4,500.00
Rp 34,500.00
Rp -
Rp 34,500.00
Rp 3,450.00
Rp 37,950.00
JUMLAH HARGA
Rp 18,000.00
Rp 900.00
Rp 18,900.00
Rp 117,120.00
Rp 117,120.00
Rp 136,020.00
Rp 13,602.00
Rp 149,622.00
JUMLAH HARGA
Rp 18,000.00
Rp 900.00
Rp 18,900.00
Rp 69,084.00
Rp 69,084.00
Rp 87,984.00
Rp 8,798.40
Rp 96,782.40
JUMLAH HARGA
Rp 15,000.00
Rp 2,250.00
Rp 17,250.00
Rp 117,120.00
Rp 117,120.00
Rp 134,370.00
Rp 13,437.00
Rp 147,807.00
JUMLAH HARGA
Rp 90,000.00
Rp 56,250.00
Rp 6,000.00
Rp 6,750.00
Rp 159,000.00
Rp 196,776.00
Rp 296,940.00
Rp 67,463.50
Rp 561,179.50
Rp 720,179.50
Rp 72,017.95
Rp 792,197.45
JUMLAH HARGA
Rp 90,000.00
Rp 56,250.00
Rp 6,000.00
Rp 6,750.00
Rp 159,000.00
Rp 196,776.00
Rp 239,610.00
Rp 72,332.00
Rp 508,718.00
Rp 667,718.00
Rp 66,771.80
Rp 734,489.80
JUMLAH HARGA
Rp 90,000.00
Rp 56,250.00
Rp 6,000.00
Rp 6,750.00
Rp 159,000.00
Rp 196,776.00
Rp 199,920.00
Rp 75,670.40
Rp 472,366.40
Rp 631,366.40
Rp 63,136.64
Rp 694,503.04
JUMLAH HARGA
Rp 90,000.00
Rp 56,250.00
Rp 6,000.00
Rp 6,750.00
Rp 159,000.00
Rp 196,776.00
Rp 171,990.00
Rp 78,035.10
Rp 446,801.10
Rp 605,801.10
Rp 60,580.11
Rp 666,381.21
JUMLAH HARGA
Rp 46,800.00
Rp 29,250.00
Rp 3,120.00
Rp 3,510.00
Rp 82,680.00
Rp 196,776.00
Rp 42,163.20
Rp 238,939.20
Rp 321,619.20
Rp 32,161.92
Rp 353,781.12
JUMLAH HARGA
Rp 4,200.00
Rp 5,250.00
Rp 560.00
Rp 360.00
Rp 10,370.00
Rp 103,014.59
Rp 3,450.00
Rp 106,464.59
Rp 116,834.59
Rp 11,683.46
Rp 128,518.05
JUMLAH HARGA
Rp 31,200.00
Rp 19,500.00
Rp 2,080.00
Rp 2,340.00
Rp 55,120.00
Rp 96,743.20
Rp 6,300.00
Rp 3,000.00
Rp 106,043.20
Rp 161,163.20
Rp 16,116.32
Rp 177,279.52
JUMLAH HARGA
Rp 31,200.00
Rp 19,500.00
Rp 2,080.00
Rp 2,340.00
Rp 55,120.00
Rp 108,836.10 ###
Rp 6,300.00
Rp 3,000.00
Rp 118,136.10
Rp 173,256.10
Rp 17,325.61
Rp 190,581.71
JUMLAH HARGA
Rp 39,600.00
Rp 24,750.00
Rp 2,640.00
Rp 2,970.00
Rp 69,960.00
Rp 96,743.20 ###
Rp 8,400.00
Rp 6,000.00
Rp 36,278.70
Rp 49,441.00
Rp 40,000.00 Rp 236,862.90
Rp 236,862.90
Rp 306,822.90
Rp 30,682.29
Rp 337,505.19
JUMLAH HARGA
Rp 39,600.00
Rp 24,750.00
Rp 2,640.00
Rp 2,970.00
Rp 69,960.00
Rp 96,743.20
Rp 8,400.00
Rp 6,000.00
Rp 43,534.44
Rp 49,441.00
Rp 40,000.00
Rp 244,118.64
Rp 314,078.64
Rp 31,407.86
Rp 345,486.50
JUMLAH HARGA
Rp 39,600.00
Rp 24,750.00
Rp 2,640.00
Rp 2,970.00
Rp 69,960.00
Rp 96,743.20
Rp 8,400.00
Rp 6,000.00
Rp 36,278.70
Rp 49,441.00
Rp 120,000.00
Rp 316,862.90
Rp 386,822.90
Rp 38,682.29
Rp 425,505.19
pp : 4 krkl )
JUMLAH HARGA
Rp 99,000.00
Rp 20,625.00
Rp 2,240.00
Rp 7,470.00
Rp 129,335.00
Rp 363,090.00
1.2430
Rp 97,246.90
Rp 342,157.50
Rp 21,500.00
Rp 823,994.40
Rp 953,329.40
Rp 95,332.94
Rp 1,048,662.34
JUMLAH HARGA
Rp 99,000.00
Rp 20,625.00
Rp 2,240.00
Rp 7,470.00
Rp 129,335.00
Rp 479,220.00
Rp 85,049.07
Rp 352,432.50
Rp 21,500.00
Rp 938,201.57
Rp 1,067,536.57
Rp 106,753.66
Rp 1,174,290.23 ±
Rp 99,000.00
Rp 20,625.00
Rp 2,240.00
Rp 7,470.00
Rp 129,335.00
Rp 517,440.00
Rp 81,803.78
Rp 353,117.50
Rp 21,500.00
Rp 973,861.28
Rp 1,103,196.28
Rp 110,319.63
Rp 1,213,515.91
Rp 99,000.00
Rp 20,625.00
Rp 2,240.00
Rp 7,470.00
Rp 129,335.00
Rp 545,370.00
Rp 78,110.86
Rp 358,597.50
Rp 21,500.00
Rp 1,003,578.36
Rp 1,132,913.36
Rp 113,291.34
Rp 1,246,204.70
campuran 1pc : 5 pp
JUMLAH HARGA
Rp 18,000.00
Rp 7,500.00
Rp 800.00
Rp 1,350.00
Rp 27,650.00
Rp 85,400.00
Rp 14,229.60
9.6800
Rp 6,259.50
Rp 105,889.10
Rp 133,539.10
Rp 13,353.91
Rp 146,893.01
JUMLAH HARGA
Rp 21,000.00
Rp 11,250.00
Rp 1,200.00
Rp 1,620.00
Rp 35,070.00
Rp 62,500.00
Rp 10,866.24
Rp 2,503.80
Rp 75,870.04
Rp 110,940.04
Rp 11,094.00
Rp 122,034.04
JUMLAH HARGA
Rp 21,000.00
Rp 11,250.00
Rp 1,200.00
Rp 1,620.00
Rp 35,070.00
Rp 64,000.00
Rp 8,690.64
Rp 2,656.81
Rp 75,347.45
Rp 110,417.45
Rp 11,041.75
Rp 121,459.20
JUMLAH HARGA
Rp 21,000.00
Rp 11,250.00
Rp 1,200.00
Rp 1,620.00
Rp 35,070.00
Rp 62,500.00
Rp 6,209.28
Rp 2,851.55
Rp 71,560.83
Rp 106,630.83
Rp 10,663.08
Rp 117,293.91
JUMLAH HARGA
Rp 15,600.00
Rp 15,000.00
Rp 1,600.00
Rp 1,170.00
Rp 33,370.00
Rp 15,240.96
Rp 4,312.10
Rp 19,553.06
Rp 52,923.06
Rp 5,292.31
Rp 58,215.37
JUMLAH HARGA
Rp 24,000.00
Rp 15,000.00
Rp 1,600.00
Rp 1,980.00
Rp 42,580.00
Rp 12,230.40
Rp 4,451.20
Rp 16,681.60
Rp 59,261.60
Rp 5,926.16
Rp 65,187.76
JUMLAH HARGA
Rp 12,000.00
Rp 15,000.00
Rp 1,600.00
Rp 1,980.00
Rp 30,580.00
Rp 10,160.64
Rp 4,868.50
Rp 15,029.14
Rp 45,609.14
Rp 4,560.91
Rp 50,170.05
JUMLAH HARGA
Rp 18,000.00
Rp 11,250.00
Rp 1,200.00
Rp 1,350.00
Rp 31,800.00
Rp 6,491.52
Rp 3,755.70
Rp 10,247.22
Rp 42,047.22
Rp 4,204.72
Rp 46,251.94
JUMLAH HARGA
Rp 12,000.00
Rp 7,500.00
Rp 800.00
Rp 900.00
Rp 21,200.00
Rp 4,780.44
Rp 4,780.44
Rp 25,980.44
Rp 2,598.04
Rp 28,578.48
JUMLAH HARGA
Rp 12,000.00
Rp 7,500.00
Rp 800.00
Rp 900.00
Rp 21,200.00
Rp 217.56
Rp 2,920.00
Rp 217.56
Rp 21,417.56
Rp 2,141.76
Rp 23,559.32
JUMLAH HARGA
Rp 15,000.00
Rp 9,375.00
Rp 1,040.00
Rp 1,170.00
Rp 26,585.00
Rp 147,680.55
Rp 12,289.20
Rp 3,199.30
Rp 163,169.05
Rp 189,754.05
Rp 18,975.41
Rp 208,729.46
JUMLAH HARGA
Rp 15,000.00
Rp 9,375.00
Rp 1,040.00
Rp 1,170.00
Rp 26,585.00
Rp 69,187.50 6.2500
Rp 14,406.00
0.2450
Rp 6,259.50
Rp 89,853.00
Rp 116,438.00
Rp 11,643.80
Rp 128,081.80
JUMLAH HARGA
Rp 15,000.00
Rp 9,375.00
Rp 1,040.00
Rp 1,170.00
Rp 26,585.00
Rp 77,520.83
Rp 14,406.00
Rp 6,259.50
Rp 3,450.00
Rp 101,636.33
Rp 128,221.33
Rp 12,822.13
Rp 141,043.47
JUMLAH HARGA
Rp 16,200.00
Rp 10,125.00
Rp 1,120.00 20.0000
Rp 1,260.00
Rp 28,705.00
Rp 77,520.83 12.5000
0.2600
Rp 15,288.00
Rp 6,259.50
Rp 5,750.00
Rp 104,818.33
Rp 133,523.33
Rp 13,352.33
Rp 146,875.67
JUMLAH HARGA
Rp 16,200.00
Rp 10,125.00
Rp 1,120.00
Rp 1,260.00
Rp 28,705.00
Rp 66,420.00
0.2600
Rp 15,288.00
Rp 6,259.50
Rp 5,750.00
Rp 93,717.50
Rp 122,422.50
Rp 12,242.25
Rp 134,664.75
JUMLAH HARGA
Rp 5,400.00
Rp 6,750.00
Rp 720.00
Rp 450.00
Rp 13,320.00 1.6667
Rp 23,850.00
Rp 1,675.80
Rp 417.30
Rp 575.00
Rp 26,518.10
###
Rp 39,838.10
Rp 3,983.81
Rp 43,821.91
JUMLAH HARGA
Rp 3,600.00
Rp 2,400.00
Rp 256.00
Rp 225.00
Rp 6,481.00
Rp 75,000.00
1.2000
Rp 1,764.00
Rp 417.30
Rp 77,181.30 ###
Rp 83,662.30
Rp 8,366.23
Rp 92,028.53
JUMLAH HARGA
Rp 3,600.00
Rp 2,400.00
Rp 256.00
Rp 225.00
Rp 6,481.00
Rp 30,000.00
Rp 1,764.00
Rp 417.30
Rp 32,181.30
Rp 38,662.30
Rp 3,866.23
Rp 42,528.53
JUMLAH HARGA
Rp 12,000.00
Rp 7,500.00
Rp 800.00
Rp 900.00
Rp 21,200.00
Rp 72,900.00 2.1429
Rp 1,159.00 0.4667
Rp 74,059.00 0.6400
Rp 95,259.00
Rp 9,525.90
Rp 104,784.90
JUMLAH HARGA
Rp 12,000.00
Rp 33,750.00
Rp 800.00
Rp 4,500.00
Rp 51,050.00
Rp 38,440.00 0.2480
Rp 42,780.00 0.3720
Rp 19,000.00
Rp 9,600.00
Rp 67,500.00 3.7200
Rp 6,820.00 5.4000
Rp 184,140.00 ###
Rp 235,190.00
Rp 23,519.00
Rp 258,709.00
JUMLAH HARGA
Rp 6,000.00
Rp 3,750.00
Rp 9,750.00
Rp 54,000.00
Rp 1,159.00
Rp 55,159.00
Rp 64,909.00
Rp 6,490.90
Rp 71,399.90
Rp 6,520,307.00
Rp 652,030.70
Rp 7,172,337.70
JUMLAH HARGA
Rp 60,000.00
Rp 225,000.00
Rp 24,000.00
Rp 4,500.00
Rp 313,500.00
Rp 166,474.80
Rp 17,500.00
Rp 183,974.80
Rp 497,474.80
Rp 49,747.48
Rp 547,222.28
yu kls I atau II
JUMLAH HARGA
Rp 48,000.00
Rp 180,000.00
Rp 19,200.00
Rp 3,600.00
Rp 250,800.00
Rp 99,884.88
Rp 120,000.00
Rp 10,500.00
Rp 230,384.88
Rp 481,184.88
Rp 48,118.49
Rp 529,303.37
JUMLAH HARGA
Rp 60,000.00
Rp 225,000.00
Rp 24,000.00
Rp 4,500.00
Rp 313,500.00
Rp 266,359.68
Rp 17,500.00
Rp 283,859.68
Rp 597,359.68
Rp 59,735.97
Rp 657,095.65
JUMLAH HARGA
Rp 15,000.00
Rp 3,200.00
Rp 18,200.00
Rp 180,000.00
Rp 38,000.00
Rp 2,800.00
Rp 237,660.00
Rp 458,460.00
Rp 476,660.00
Rp 47,666.00
Rp 524,326.00
JUMLAH HARGA
Rp 42,000.00
Rp 157,500.00
Rp 16,800.00
Rp 3,150.00
Rp 219,450.00
Rp 104,046.75
Rp 630.00
Rp 17,500.00
Rp 54,174.69
Rp 176,351.44
Rp 395,801.44
Rp 39,580.14
Rp 435,381.58
JUMLAH HARGA
Rp 42,000.00
Rp 157,500.00
Rp 16,800.00
Rp 3,150.00
Rp 219,450.00
Rp 104,046.75
Rp 630.00
Rp 17,500.00
Rp 27,087.34
Rp 57,500.00
Rp 206,764.09
Rp 426,214.09
Rp 42,621.41
Rp 468,835.50
JUMLAH HARGA
Rp 19,200.00
Rp 72,000.00
Rp 76,800.00
Rp 1,440.00
Rp 169,440.00
Rp 150,000.00
Rp 10,500.00
Rp 160,500.00
Rp 329,940.00
Rp 32,994.00
Rp 362,934.00
JUMLAH HARGA
Rp 6,000.00
Rp 15,000.00
Rp 1,600.00
Rp 450.00
Rp 23,050.00
Rp 1,620.00
Rp 2,100.00
Rp 3,720.00
Rp 26,770.00
Rp 2,677.00
Rp 29,447.00
JUMLAH HARGA
Rp 6,000.00
Rp 15,000.00
Rp 1,600.00
Rp 450.00
Rp 23,050.00
Rp 154,561.00
Rp 1,050.00
Rp 155,611.00
Rp 178,661.00
Rp 17,866.10
Rp 196,527.10
JUMLAH HARGA
Rp 6,000.00
Rp 22,500.00
Rp 2,400.00
Rp 6,750.00
Rp 37,650.00
Rp 20,750.00
Rp 5,250.00
Rp 29,356.60
Rp 22,000.00
Rp 19,250.00
Rp 60,000.00
Rp 1,440.00
Rp 158,046.60
Rp 195,696.60
Rp 19,569.66
Rp 215,266.26
JUMLAH HARGA
Rp 175.00
Rp 403.25
Rp 550.00
Rp 525.00
Rp 1,653.25
Rp 22,000.00
Rp 210.00
Rp 22,210.00
Rp 23,863.25
Rp 2,386.33
Rp 26,249.58
JUMLAH HARGA
Rp 600.00
Rp 37,500.00
Rp 4,000.00
Rp 450.00
Rp 42,550.00
Rp 165,000.00
Rp 165,000.00
Rp 207,550.00
Rp 20,755.00
Rp 228,305.00
JUMLAH HARGA
Rp 900.00
Rp 11,250.00
Rp 1,200.00
Rp 72.00
Rp 13,422.00
Rp 25,000.00
Rp 25,000.00
Rp 38,422.00
Rp 3,842.20
Rp 42,264.20
JUMLAH HARGA
Rp 600.00
Rp 7,500.00
Rp 800.00
Rp 45.00
Rp 8,945.00
Rp 20,000.00
Rp 20,000.00
Rp 28,945.00
Rp 2,894.50
Rp 31,839.50
JUMLAH HARGA
Rp 900.00
Rp 11,250.00
Rp 1,200.00
Rp 72.00
Rp 13,422.00
Rp 6,000.00
Rp 6,000.00
Rp 19,422.00
Rp 1,942.20
Rp 21,364.20
JUMLAH HARGA
Rp 1,200.00
Rp 15,000.00
Rp 1,600.00
Rp 90.00
Rp 17,890.00
Rp 24,000.00
Rp 24,000.00
Rp 41,890.00
Rp 4,189.00
Rp 46,079.00
JUMLAH HARGA
Rp 1,200.00
Rp 15,000.00
Rp 1,600.00
Rp 90.00
Rp 17,890.00
Rp 18,000.00
Rp 18,000.00
Rp 35,890.00
Rp 3,589.00
Rp 39,479.00
JUMLAH HARGA
Rp 900.00
Rp 11,250.00
Rp 1,200.00
Rp 72.00
Rp 13,422.00
Rp 239,800.00
Rp 7,250.00
Rp 247,050.00
Rp 260,472.00
Rp 26,047.20
Rp 286,519.20
Rp 4,200.00 4200
Rp 675.00
Rp 480.00
Rp 270.00
Rp 5,625.00
Rp 11,400.00
Rp 6,000.00
Rp 9,690.00
Rp 14,820.00
Rp 170.00
Rp 1,200.00
Rp 1,000.00
Rp 44,280.00
Rp 49,905.00
Rp 4,990.50
Rp 54,895.50
Rp 4,200.00
Rp 7,875.00
Rp 320.00
Rp 270.00
Rp 12,665.00
Rp 11,400.00
Rp 6,000.00
Rp 9,690.00
Rp 19,950.00
Rp 170.00
Rp 1,200.00
Rp 1,000.00
Rp 49,410.00
Rp 62,075.00
Rp 6,207.50
Rp 68,282.50
JUMLAH HARGA
Rp 2,400.00
Rp 4,725.00
Rp 5,040.00
Rp 270.00
Rp 12,435.00
Rp 16,200.00
Rp 16,200.00
Rp 28,635.00
Rp 2,863.50
Rp 31,498.50
Rp 1,200.00
Rp 4,725.00
Rp 504.00
Rp 270.00
Rp 6,699.00
Rp 4,000.00
Rp 5,700.00
Rp 14,820.00
Rp 24,520.00
Rp 31,219.00
Rp 3,121.90
Rp 34,340.90
JUMLAH HARGA
Rp 2,400.00
Rp 4,725.00
Rp 504.00
Rp 270.00
Rp 7,899.00
Rp 18,000.00
Rp 18,000.00
Rp 25,899.00
Rp 2,589.90
Rp 28,488.90
JUMLAH HARGA
Rp 28,800.00
Rp 3,600.00
Rp 3,840.00
Rp 36,240.00
Rp 77,000.00
Rp 70,000.00 ###
Rp 147,000.00
Rp 183,240.00
Rp 18,324.00
Rp 201,564.00
JUMLAH HARGA
Rp 12,000.00
Rp 1,500.00
Rp 1,600.00
Rp 15,100.00
Rp 20,000.00
Rp 20,000.00
Rp 35,100.00
Rp 3,510.00
Rp 38,610.00
JUMLAH HARGA
Rp 12,000.00
Rp 1,500.00
Rp 1,600.00
Rp 15,100.00
Rp 60,000.00
Rp 20,000.00
Rp 80,000.00
Rp 95,100.00
Rp 9,510.00
Rp 104,610.00
JUMLAH HARGA
Rp 12,000.00
Rp 1,500.00
Rp 1,600.00
Rp 15,100.00
Rp 50,000.00
Rp 20,000.00
Rp 70,000.00
Rp 85,100.00
Rp 8,510.00
Rp 93,610.00
JUMLAH HARGA
Rp 12,000.00
Rp 1,500.00
Rp 1,600.00
Rp 15,100.00
Rp 40,000.00
Rp 20,000.00
Rp 60,000.00
Rp 75,100.00
Rp 7,510.00
Rp 82,610.00
JUMLAH HARGA
Rp 12,000.00
Rp 1,500.00
Rp 1,600.00
Rp 15,100.00
Rp 61,000.00
Rp 61,000.00
Rp 76,100.00
Rp 7,610.00
Rp 83,710.00
JUMLAH HARGA
Rp 24,000.00
Rp 3,000.00
Rp 3,200.00
Rp 30,200.00
Rp 25,000.00
Rp 25,000.00
Rp 55,200.00
Rp 5,520.00
Rp 60,720.00
JUMLAH HARGA
Rp 24,000.00
Rp 3,000.00
Rp 3,200.00
Rp 30,200.00
Rp 25,000.00
Rp 25,000.00
Rp 55,200.00
Rp 5,520.00
Rp 60,720.00
JUMLAH HARGA
Rp 60,000.00
Rp 112,500.00
Rp 120,000.00
Rp 14,400.00
Rp 306,900.00
Rp 50,000.00
Rp 8,820.00
Rp 1,391.00
Rp 60,211.00
Rp 367,111.00
Rp 36,711.10
Rp 403,822.10
JUMLAH HARGA
Rp 72,000.00
Rp 108,750.00
Rp 12,000.00
Rp 9,000.00
Rp 201,750.00
Rp 300,000.00
Rp 8,820.00
Rp 1,391.00
Rp 36,000.00
Rp 346,211.00
Rp 547,961.00
Rp 54,796.10
Rp 602,757.10
JUMLAH HARGA
Rp 22,800.00
Rp 14,250.00
Rp 1,520.00
Rp 1,710.00
Rp 40,280.00
Rp 30,500.00
Rp 15,141.00
Rp 8,485.10
Rp 6,734.40
Rp 60,860.50
Rp 101,140.50
Rp 10,114.05
Rp 111,254.55
JUMLAH HARGA
Rp 4,860.00
Rp 10,125.00
Rp 1,080.00
Rp 369.00
Rp 16,434.00
Rp 69,000.00
Rp 24,150.00
Rp 93,150.00
Rp 109,584.00
Rp 10,958.40
Rp 120,542.40
JUMLAH HARGA
Rp 4,860.00
Rp 10,125.00
Rp 1,080.00
Rp 369.00
Rp 16,434.00
Rp 30,000.00
Rp 10,500.00
Rp 40,500.00
Rp 56,934.00
Rp 5,693.40
Rp 62,627.40
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 31,200.00
Rp 10,920.00
Rp 42,120.00
Rp 53,073.00
Rp 5,307.30
Rp 58,380.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 18,000.00
Rp 6,300.00
Rp 24,300.00
Rp 35,253.00
Rp 3,525.30
Rp 38,778.30
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 48,000.00
Rp 16,800.00
Rp 64,800.00
Rp 75,753.00
Rp 7,575.30
Rp 83,328.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 22,000.00
Rp 7,700.00
Rp 29,700.00
Rp 40,653.00
Rp 4,065.30
Rp 44,718.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 30,000.00
Rp 10,500.00
Rp 40,500.00
Rp 51,453.00
Rp 5,145.30
Rp 56,598.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 12,000.00
Rp 4,200.00
Rp 16,200.00
Rp 27,153.00
Rp 2,715.30
Rp 29,868.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 25,000.00
Rp 8,750.00
Rp 33,750.00
Rp 44,703.00
Rp 4,470.30
Rp 49,173.30
JUMLAH HARGA
Rp 3,240.00
Rp 6,750.00
Rp 720.00
Rp 243.00
Rp 10,953.00
Rp 14,000.00
Rp 4,900.00
Rp 18,900.00
Rp 29,853.00
Rp 2,985.30
Rp 32,838.30
JUMLAH HARGA
Rp 600.00
Rp 7,500.00
Rp 800.00
Rp 450.00
Rp 9,350.00
Rp 40,000.00
Rp 125.00
Rp 40,125.00
Rp 49,475.00
Rp 4,947.50
Rp 54,422.50
JUMLAH HARGA
Rp 600.00
Rp 7,500.00
Rp 800.00
Rp 450.00
Rp 9,350.00
Rp 13,000.00
Rp 13,000.00
Rp 22,350.00
Rp 2,235.00
Rp 24,585.00
JUMLAH HARGA
Rp 600.00
Rp 7,500.00
Rp 800.00
Rp 450.00
Rp 9,350.00
Rp 50,000.00
Rp 50,000.00
Rp 59,350.00
Rp 5,935.00
Rp 65,285.00
JUMLAH HARGA
Rp 198,000.00
Rp 82,500.00
Rp 80.00
Rp 14,400.00
Rp 294,980.00
Rp 1,900,000.00
Rp 114,000.00
Rp 2,014,000.00
Rp 2,308,980.00
Rp 230,898.00
Rp 2,539,878.00
Jenis Pekerjaan
No Bahan / Upah Indeks Satuan PEKERJAAN TANAH DA
1 Volume Beton untuk 1 m³ campuran Beton baik k 100 maupun k 125 1
Pekerja 1.65 OH
Tukang batu 0.275 OH
Kepala Tukang 0.028 OH 2
Mandor 0.083 OH
2 Mutu beton f’c = 7,4 MPa (K 100)
Portland cement 247 kg 3
Pasir beton 869 kg
Kerikil (maksimum 30mm) 999 kg
Air 215 Liter
3 Mutu beton f’c = 9,8 MPa (K 125)
Bahan Bangunan Indeks Satuan
Portland cement 276 kg
Pasir beton 828 kg
Kerikil (maksimum 30mm) 1012 kg
Air 215 Liter
4.11 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) cm tebal
4
1/2 bata, campuran spesi 1 PC : 6 PP
Bata merah 70.000 Buah
Portland Cement 8.320 kg
Pasir Pasang 0.049 m3
Pekerja 0.300 OH
Tukang batu 0.100 OH
Kepala tukang 0.010 OH
Mandor 0.015 OH
4.12 Memasang 1 m2 dinding bata merah ukuran (5 x 11 x 22) tebal 1/2
5
bata, campuran spesi 1 PC : 8 PP
Bata merah 70.000 Buah
Portland Cement 6.500 kg
Pasir Pasang 0.050 m3
Pekerja 0.300 OH
Tukang batu 0.100 OH
Kepala tukang 0.010 OH
Mandor 0.015 OH
6 Pekerjaan Plesteran Adukan 1 : 4 tebal 2 cm / m2
Semen 0.145 sak
Pasir Pasang 0.018 m3
Alat Bantu 1 Ls
Pekerja 0.3 OH
Tukang Batu 0.15 OH
Kepala Tukang 0.02 OH
Mandor 0.01 OH
7 Pekerjaan Plesteran Adukan 1 : 5 tebal 2 cm / m2
Semen 0.12 sak
Pasir Pasang 0.02 m3
Alat Bantu 1 Ls
Pekerja 0.3 OH
Tukang Batu 0.15 OH
Kepala Tukang 0.02 OH
Mandor 0.01 OH
6.2 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela,
8
kayu kelas II atau III
Balok kayu 1.200 m3
Paku 10 cm 1.250 kg
Lem kayu 1.000 kg
Pekerja 6.000 OH
Tukang kayu 18.000 OH
Kepala Tukang 1.800 OH
Mandor 0.300 OH
6.13 Memasang 1 m3 konstruksi kuda-kuda konvensional, kayu kelas
9
I, II dan III bentang 6 meter
Balok kayu 1.100 m3
Besi strip tebal 5 mm 15.000 kg
Paku 12 cm 5.600 kg
Pekerja 4.000 OH
Tukang kayu 12.000 OH
Kepala Tukang 1.200 OH
Mandor 0.200 OH
10 6.15 Memasang 1 m konstruksi gordeng, kayu kelas II
3
Kaso-kaso (5 x 7) cm 0.014 m3
Reng (2 x 3) cm 0.036 m3
Paku 5 cm dan 10 cm 0.250 kg
Pekerja 0.100 OH
Tukang kayu 0.100 OH
Kepala Tukang 0.010 OH
Mandor 0.005 OH
a b c e
1. Balok Kayu Bayam M3 12,164,020.00
2. Papan Kayu Jati M3 10,168,580.00
3. Balok Kayu Hutan (Nara, Ledu, Mundi, Ampupu, Lui) M3 5,248,020.00
4. Papan 3 cm x 20 cm x 4 m (kelasII Nara) M3 5,252,580.00
5. Balok Kayu Hutan ( Meranti ) M3 4,161,870.00
6. Papan Kayu Hutan ( Meranti ) M3 4,168,580.00
7. Kayu bayam (papan) 3/30 M3 12,168,580.00
Balok 6/12 kelas II M3 5,120,000.00
Balok 8/12 kelas II M3 5,120,000.00
f
Lokasi Pekerjaan harga kayubayam 12,000,000
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan 1.6
Lokasi Pekerjaan
Lokasi Pekerjaan btg 147500
Lokasi Pekerjaan btg 196600
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan 28003.472
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan 11,070.00
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan 669600000
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan 58333.333
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
Lokasi Pekerjaan
RENCANA ANGGARAN BIAYA (RAB)
Nomor BNBA :
Nomor KTP :
Nama Penerima Bantuan :
Alamat :
Desa :
Kecamatan :
Kabupaten :
Ukuran Rumah : 38.5 ㎡
SUMBER DANA
VOLUME
HARGA
TOTAL HARGA
NO URAIAN PEKERJAAN SAT. SATUAN KET.
(Rp)
(Rp) BANTUAN SWADAYA
Total Swad Bantu
aya an
I PEKERJAAN PERSIAPAN
Gotong
1 Bongkar Rumah Lama 1 Ls - - -
Royong KPB
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 12.1 12.1 M3 51,975 626,818.50 - 626,818.50
2 Urugan Pasir 4 4 M3 97,600 390,400.00 - 390,400.00
3 Pasangan Pondasi 8 8 M3 - - -
Semen @ 40 kg 43 43 Zak 58,000 2,494,000.00 - 2,494,000.00
-
Pasir Beton 4 4 M3 200,000 800,000.00 - 800,000.00
-
Batu Gunung 10 10 M3 163,980 1,639,800.00 - 1,639,800.00
-
4 Urugan kembali 3.6 3.6 M3 37,950 137,303.10 - 137,303.10
III PEKERJAAN SLOOF
1 Pekerjaan bekisting 8 8.0 M2 118,136 949,814.24 - 949,814.24
2 Cor Beton Sloof, Ukuran 15/20 cm 1 1.2 M3 - - -
Besi beton Φ10 mm 14 - 14 Btg 78,000 1,092,000.00 1,092,000.00 -
-
Besi beton Φ 6 mm 16 6.0 10 Btg 36,000 576,000.00 360,000.00 216,000.00
-
Semen @ 40 kg 7 - 7 Zak 58,000 406,000.00 406,000.00 -
-
Pasir Beton 0.7 0.7 M3 200,000 149,716.29 - 149,716.29
-
Kerikil 0.7 0.7 M3 411,000 275,094.63 - 275,094.63
-
IV PEKERJAAN KOLOM
1 Pekerjaan bekisting 5.0 5.0 M2 236,863 1,193,789.02 - 1,193,789.02
Cor Beton Kolom, Ukuran 15/15 ,
2 0.8 0.8 M3
T=3m
Besi beton Φ10 mm 12 - 12 Btg 78,000 936,000.00 936,000.00 -
-
Besi beton Φ 6 mm 9 9.0 Btg 36,000 324,000.00 - 324,000.00
-
Semen @ 40 kg 5 - 5 Zak 58,000 290,000.00 290,000.00 -
-
Pasir Beton 5 5 M3 200,000 1,000,000.00 - 1,000,000.00
-
Kerikil 0.4 0.4 M3 411,000 172,447.38 - 172,447.38
-
V DINDING PERMANEN
1 Tembok 99.7 99.7 M2
Pasir Pasang 2 - 2 M3 200,000 400,000.00 400,000.00 -
-
Semen @ 40 kg 15 - 15 Zak 58,000 870,000.00 870,000.00 -
-
Batako 1,246 361 885 Bh 5,500 6,853,000.00 4,867,500.00 1,985,500.00
-
2 Pekerjaan Plester (1pc :6pp)tebal 15 mm - - -
Pasir Pasang 2.7 0.7 2 M3 200,000 538,326.00 400,000.00 138,326.00
-
Semen @ 40 kg 11 - 11 Zak 58,000 638,000.00 638,000.00 -
-
3 Papan - - - -
Papan, Ukuran……… - Lbr - - -
-
Kayu, Ukuran………. - Btg - - -
-
VI PEKERJAAN PINTU DAN JENDELA
- Kusen Pintu 4 4 Unit 350,000 1,400,000.00 - 1,400,000.00
- Kusen Jendela 5 5 Unit 300,000 1,500,000.00 - 1,500,000.00
- Daun Pintu Kayu 4 4 Unit 1,500,000 6,000,000.00 - 6,000,000.00
- Daun Jendela Kayu - Unit - - -
- Daun Jendela Kaca 5 5 Unit 400,000 2,000,000.00 - 2,000,000.00
- Handle Pintu dan Kunci Pintu 4 4 Set - - -
Handle Jendela dan Kunci
5 5 - - -
- Jendela Set
- Engsel Pintu 4 4 Set 21,000 84,000.00 - 84,000.00
- Engsel Jendela 5 5 Set 17,000 85,000.00 - 85,000.00
- Kait Angin 5 5 set 34,000 170,000.00 - 170,000.00
- Grendel Jendela 5 5 Bh 48,000 240,000.00 - 240,000.00
- Grendel Pintu 4 4 Bh 33,000 132,000.00 - 132,000.00
VII PEKERJAAN RING BALK
1 Pekerjaan Begesting 8 8 M2 244,119 1,962,713.87 - 1,962,713.87
2 Pekerjaan Cor Beton 0.9 0.9 M3 - - -
Besi beton Φ10 mm 14 - 14 Btg 78,000 1,092,000.00 1,092,000.00 -
-
Besi beton Φ 6 mm 10 - 10 Btg 36,000 360,000.00 360,000.00 -
-
Semen @ 40 kg 6 - 6 Zak 58,000 348,000.00 348,000.00 -
-
Pasir Beton 0.6 0.6 M3 200,000 112,287.21 - 112,287.21
-
Kerikil 0.5 0.5 M3 411,000 206,320.97 - 206,320.97
VII -
PEKERJAAN STRUKTUR ATAP
I
Kayu (8 cm x 12 cm x 4 m)
14 14 2,752,400.00 - 2,752,400.00
- Rangka Kuda-Kuda Btg 196,600
Kayu (6 cm x 12 cm x 4 m) /
12 12 1,770,000.00 - 1,770,000.00
- Gapit / Gording Btg 147,500
SWADAYA 50,323,400
SUMBER DANA
BANTUAN 18,000,000
-494500
-98.9
-500000
- 0
-90.9090909091
0
DAFTAR RENCANA PEMANFAATAN BANTUAN (DRPB)
(Rekapan Total Kebutuhan Material yang Dibeli dari Dana Bantuan)
Nomor BNBA : 0
Nomor KTP : 0
Nama Penerima Bantuan : 0
Alamat : 0
Desa : 0
Kecamatan : 0
Kabupaten : 0
Diajukan oleh:
Toko/Penyedia Bahan Bangunan Penerima Bantuan
.......................................................... ......................................
942
15000000
-496000
-90.1818181818
Kondisi Rumah
Luas Bangunan : 6 x 4 meter
A Bentuk Atap : Pelana
Rangka Atap : Kuda Kuda Kayu 8/12 dan 6/12
Kaso ukuran : 5/7
Usuk ukuran : 2/3
Penutup Atap : Asbes
Emperan/Teras : Konsol Kayu
Rangka Bangunan : Beton terdiri dari, Kolom praktis dan Balok Ring
B Dinding : Batu Bata Penuh tebal 1/2 bata
Plester : Sisi dalam Dinding
Pintu : 2 buah (Depan, Belakang )
Jendela : 3 buah (Depan dan 2 di Kamar)
Jalusi : 2 buah
C Lantai : Beton Rabat
Cara pengisian
a. Isilah pada alamat yg berwarna kuning
b. Catat apa yang harud diperbaiki, misal
1 Penutup Atap Asbes
2 Bubungan Asbes
3 Listplang papan (2 cm x 20 cm x 4 m)
4 Kasau / Usuk (5 cm x 7 cm)
5
6 Kuda-kuda
7 Konsol
8 Ring Balok (15 cm x 15 cm)
9 Kolom
10 Sloof
11 Dinding Permanen atau Semi Permanen
12 Plesteran
13 Pekerjaan Lantai
c. Setelah itu isi harga satuan
d. Utak utik di bahan bangunan mana yang akan diswdayakan sehingg hasinya mencapatkanpagu pekerjaa (ada yg
e. Pindahkan Sheet RAB dg Paste value ke File khusu RAB masing masing penerima bantuan
f. Atur DRPB2 agar dicapai rencana pengajuan harus bula dari setengan Nilai yg ada perahu
ncapatkanpagu pekerjaa (ada yg 7,5 jt, 10 jt dan 15 t
Ukuran rumah : 5.5 x 7= 38.5 ㎡
ukuran teras : 1.7 x 2= 3.4 ㎡
Galian
Panjang 40.2 + = 40.2 m
Lebar = 0.5 m
dalam = 0.6 m
volume = 12.06 m3
Pondasi
panjang = 40.2 m semen 42.6321 43
lebar atas = 0.2 m pasir 4.09437 4
lebar bawah = 0.5 m batu gunung 10.1304 10
tinggi = 0.6 m
volume = 8.442 m3
URUGAN
vol. Urugan tanah 3.618 m3
urugan pasir pasir urug 3.6552 4
luas lantai 30.46 m2
tebal urugan 0.1 m
volume urugan pasir 3.046 m3
begesting pondasi
sak
m3
m3
m3
Pekerjaan Rangka/Beton yg diperbaiki adalah = semua balok Ring
Pekerjaan Beton meliputi Kolom, Sloof dan Balok Ring
Memasukkan Data untuk menghitung volume Bahan
A. Kolom
Diketahui
A. Memasukkan Data untuk KOLOM
1 Jumlah Kolom = 12 buah
2 Tinggi Kolom = 2.8 meter
3 Ukuran Kolom
a. Panjang = 15 cm
b. Lebar = 15 cm
c. Kait = 5 cm
4 Diameter Tulangan Pokok = 10 mm
5 Jumlah Tulangan pokok = 4 buah
6 Diameter Beugel / Senkang = 6 mm
7 Jarak Beugel / Senkang = 20 cm
8 Panjang per beugel / sengkang = 58 cm
9 Panjang Besi Tulangan per batang = 12 meter
Berat 1 zak Semen = 40 kg
Berat jenis Pasir Pasang = 1.4 gr/cm³
Berat Kenis Kerikil = 1.8 gr/cm³
B. Sloof
1 Jumlah Sloof = 0 buah
2 Panjang Sloof = 40.2 meter
3 Ukuran Sloof
a. Panjang = 15 cm
b. Lebar = 20 cm
c. Kait / Gekuan = 5 cm
4 Diameter Tulangan Pokok = 10 mm
5 Jumlah Tulangan pokok = 4 buah
6 Diameter Beugel / Sengkang = 6 mm
7 Jarak Beugel / Sengkang = 15 cm
8 Panjang per Beugel / Sengkang = 68 cm
9 Panjang Besi Tulangan per batang = 12 meter
Berat 1 zak Semen = 40 kg
Berat jenis Pasir beton = 1.4 kg/cm³
Berat jenis Kerikil = 1.8 kg/cm³
Perhitungan Kebutuhan Besi untuk beton K100
a. Panjang Sloof (total ) = 40.20 meter
Panjang Besi Tulangan Pokok = 160.80 meter
Jumlah Besi Tulangan Φ 10 mm = 14.00 Batang
Jumlah Berat Besi Tulangan Φ 10 mm 99.160 kg
b Jumlah Sengkang = 268.00 buah
Panjang Besi Tulangan Sengkang Φ 6 mm (total) = 182.24 meter
Jumlah Besi Tulangan Φ 6 mm = 16.00 Batang
Jumlah Berat Besi Tulangan Φ 6 mm = 40.397 kg
c Volume Beton pada Sloof 1.206 M³
Perhitungan Kebutuhan Bahan untuk Sloof :
Portland cement = 7.447 Zak
Pasir beton = 0.749 M³
Kerikil (maksimum 30 mm) = 0.669 M³
Perhitungan Kebutuhan Tenaga :
Pekerja = 1.990 OH
Tukang batu = 0.332 OH
Rekapitulasi Sloof
Volume Beton pada Sloof = 1.206 M³
Besi Tulangan Φ 10 mm = 14.000 Batang
Besi Tulangan Φ 6 mm = 16.000 Batang
Portland cement = 7.000 Zak
Pasir beton = 0.749 M³
Kerikil (maksimum 30mm) = 0.669 M³
Pekerja = 1.990 OH
Tukang batu = 0.332 OH
C. Balok Ring
1 Jumlah Balok Ring = Buah
2 Panjang Balok Ring = 40.2 Meter
3 Ukuran Balok Ring
a. Panjang = 15 Cm
b. Lebar = 15 Cm
c. Kait = 5 Cm
4 Diameter Tulangan Pokok = 10 Cm
5 Jumlah Tulangan pokok = 4 Buah
6 Diameter Beugel / Sengkang = 6 Cm
7 Jarak Beugel / Sengkang = 20 Cm
8 Panjang per Beugel / Sengkang = 58 Cm
9 Panjang Besi Tulangan per batang = 12 Meter
Berat 1 zak Semen = 40 kg
Berat jenis Pasir beton = 1.4 kg/cm³
Berat jenis Kerikil = 1.8 kg/cm³
Perhitungan Kebutuhan Besi
a. Panjang Balok Ring (total ) = 40.20 meter
Panjang Besi Tulangan Pokok = 160.80 meter
Jumlah Besi Tulangan Φ 10 mm = 14.00 batang
Jumlah Berat Besi Tulangan Φ 10 mm 103.600 kg
b Jumlah Sengkang = 201.00 buah
Panjang Besi Tulangan Sengkang Φ 6 mm (total) = 116.58 meter
Jumlah Besi Tulangan Φ 6 mm = 10.00 batang
Jumlah Berat Besi Tulangan Φ 6mm = 26.600 kg
c Volume Beton pada Balok Ring 0.905 m³
Perhitungan Kebutuhan Bahan :
Portland cement = 5.585 Zak
Pasir beton = 0.561 M³
Kerikil (maksimum 30mm) = 0.502 M³
Perhitungan Kebutuhan Tenaga :
Pekerja = 1.492 OH
Tukang batu = 0.249 OH
600
0.15
0.15
400
300 300
1,400 kg/m³
1,800 kg/m³ Berat Besi Beton
Berat Berat per
Diameter Panjang
(kg) meter
app
6 mm 12 m 2.66 0.22 w
8 mm 12 m 4.47 0.37
9 mm 12 m 6.00 0.50
10 mm 12 m 7.40 0.62
12 mm 12 m 10.66 0.89
13 mm 12 m 12.48 1.04
16 mm 12 m 18.96 1.58
19 mm 12 m 26.76 2.23
22 mm 12 m 35.76 2.98
25 mm 12 m 46.20 3.85
28 mm 12 m 57.96 4.83
32 mm 12 m 75.72 6.31
36 mm 12 m 95.88 7.99
0 begesting sloof 8.04
3
0.15
0.2
5
12
4
8
15
1,400 kg/m³
1,800 kg/m³
0.749
2
4
0.15
0.15
0.6075
app
w
Kita anggap pekerjaan PK Berat akan selesai dalam =
Pasir Pasang =
Perhitungan Kebutuhan Tenaga :
Pekerja =
Tukang batu =
Perhitungan Luas Berish ( Dinding penuh - Pintu dan Jendela)
B. Pekerjaan Plesteran
Dinding A =
Jalusi (2 buah) (A) =
Dinding A (Bersih)
Dinding B =
Pintu 4 buah Ditambah Jendela B =
Dinding B (Bersih)
Dinding C =
Jendela Kamar (2 buah) (C) =
Dinding C (Bersih)
Dinding D =
Pintu Belakang (D) =
Dinding D (Bersih)
Dinding E =
Pintu E 2 buah =
Dinding E (Bersih)
Dinding F =
Penuh =
Dinding F (Bersih)
Dinding Gunungan =
Jalusi =
Dinding Gunungan (Bersih)
Luas Dinding Yang akan di plester =
Perhitungan Kebutuhan Bahan untuk Plesteran :
Portland Cement =
Pasir Pasang =
Perhitungan Kebutuhan Tenaga :
Pekerja =
Tukang batu =
C. Pekerjaan Lantai
Panjang Bangunan Rumah =
Lebar Bangunan Rumah =
Luas Lantai yang akan di Ploor =
Perhitungan Kebutuhan Bahan untuk Pluur Lantai untuk tebal 5 cm :
Portland Cement =
=
Pasir Pasang =
=
Batu pecah / Kerikil (maksimum 30mm)
Pekerjaan diding meliputi Pasangan Tembok Batu bata dan plesteran dalam
7 meter
2.8 meter D
6 meter
3 meter
6 meter
2.8 meter A C
17 meter
2.8 meter
3 meter 2.7 5.4
1.8 meter
2.5 meter 1.25
1 meter B
2.5 meter 2.25 4.5
1.8 meter
0.7 meter 1.26
1.8 meter
102.00 m²
12.41 m²
114.41 m²
0.90 meter
2.20 meter
7.92 M²
meter
meter
- M²
meter
meter
- M²
0.80 meter
1.70 meter
6.80 M²
meter
meter
- M²
meter
meter
- M²
meter
meter
- M²
14.72 M²
114.41 M²
99.69 M²
40.00 Kg
5 x 11 x 22 Cm
1/2 bata BATAKO
Perhitungan Kebutuhan Bahan untuk Dinding :
6,978.300 buah 6,978.30 batako = 1,246.000
24.125 ZAK Portland Cement = 15.000
Pasir
=
4.486 m³ Pasang 2.000
Perhitungan Kebutuhan Tenaga :
29.907 OH
9.969 OH
Pintu Jendela
19.60 M²
- M²
19.60 M² ok
18.00 M²
3.34 M²
14.66 M² ok
16.80 M² C Panjang 1.60 Jendela
3.36 M² Lebar 1.05
13.44 M² ok
5.40 M² D Panjang 0.90 Pintu
2.16 M² Lebar 2.40
3.24 M² ok
2.50 M² E Panjang 0.90 Pintu
- M² Lebar 2.40
2.50 M²
Err:520 M²
- M²
Err:520 M²
2.25 M²
- M²
2.25 M²
99.69 M²
11.000 Zak
2.692 M³
29.907 OH
14.954 OH
7.50 M
5.00 M
37.5 M²
6.000 Zak
6.000 Zak
1.000 m³
1.000 m³
2.000 m³
2.000 m³
0.078 OH
0.026 OH
99.69 M²
99.69 M²
37.50 M²
bata dan plesteran dalam
Dinding A
Dinding B
Dinding C
Dinding D
Dinding E
Dinding F
Dinding G
Dinding Gunungan
Rp 5,582,640
Rp6,379,520
buah
ZAK
m³
6
6
PNPM-Mandiri Peredesaan Ngawi 2009
Kaki Kuda-kuda
3 Tiang Kuda kuda
Sekur
I Kuda-kuda 3 buah
a Balok Tarik (8/12) 5.50 0.08 0.12
b Balok Pengunci(8/12) 0.80 0.08 0.12
c Kaki Kuda Kuda (8/12) 3.82 0.08 0.12
d Nok (8/12) 8.00 0.08 0.12
e usuk (5/7) 8.00 0.05 0.07
usuk (5/7) 7.00 0.05 0.07
f Blandar (8/12) - 0.08 0.12
g Balok Gapit (6/12) 3.00 0.06 0.12
h Sekur (6/12) 1.91 0.06 0.12
i Tiang Kuda kuda (8/12) 1.80 0.08 0.12
j Balok Angin (6/12) 24.00 0.06 0.12
II Konsol (Setengah Kuda kuda) 2 buah
a Balok 1/2 Kuda kuda (8/12) 2.50 0.08 0.12
b Tiang1/2 Kuda kuda (8/12) 1.00 0.08 0.12
c Kaki 1/2 Kuda Kuda (8/12) 2.20 0.08 0.12
d Sekur (8/12) 0.95 0.06 0.12
e usuk 5/7 2.20 0.05 0.07
Jumlah Kebutuhan Kayu Kuda Kuda Utama
Jumlah Balok 8/12 14.00
Jumlah Balok 6/12 12.00
Jumlah Balok 5/7 25.00
III Rangka Atap Genteng
Lebar Miring Panjang Tritisan
a Jumlah Kebutuhan Usuk Jarak antar Usuk (5/7) 0.50 Meter
Untuk Atap Utama - 6.00 0.50
Untuk Atap Konsol 2.20 3.00
Jumlah Usuk 5/7
b Jumlah Kebutuhan Reng Jarak antar Reng (2/3) 0.23 Meter
Untuk Atap Utama - - 0.50
Untuk Atap Konsol
Jumlah Reng 2/3
Atap Utama
Menghitung Tenaga Kerja Satuan Jumlah
Volume Rangka Kuda kuda M3 0.51
Volume Rangka Gording M3 0.42
Volume Rangka Atap M²
Volume Atap Asbes Semen M² 3.00
Jumlah Kebutuhan Tenaga Kerja
Konsol
Menghitung Tenaga Kerja Satuan Jumlah
Volume Rangka Kuda kuda M3 0.08
Volume Rangka Gording M3 0.03
Volume Rangka Atap Asbes Semen M² -
Volume Atap Asbes Semen M² -
Jumlah Kebutuhan Tenaga Kerja
P
atan
ar 10 %
1.08 m3
2.00 0.11 M3
1.00 0.01 M3
6.00 0.22 M3
1.00 0.08 M3
6.00 0.17 M3
6.00 0.15 M4
2.00 - M3
3.00 0.06 M3
6.00 0.08 M3
2.00 0.03 M3
1.00 0.17 M3
0.11
1.00 0.02 M3
1.00 0.01 M3
2.00 0.04 M3
1.00 0.01 M3
4.00 0.03 M3
Volume / Sat
14.0 Batang
12.0 Batang
- - Batang
- - Batang
- Batang
- - Batang
- Batang
- Batang
sketchup
Utama
Data Pendukung Konsol Jumlah Sat
(m)
Luas atap 2 Sisi
0.1056 Panjang Atap = 8.25 2.33 11.0 m
Lebar Atap (yg Miring) = 3.82 2.20 m
Luas atap = 62.96 10.23 73.2 m2
Tan ∂ 1.0
Sin ∂ 1/2 V2
Cos ∂ 1/2 V2
105.39054608
TERAS
Panjang Bubungan = 1.7
Lebar = 2.5
tritisan = 0.625
Panjang Datar Atap = 2.325
Lebar Kemiringan Atap = 3.60844
Luas Atap (Lebar Miring X Panjang) = 8.38962
Luas Atap Teras = 16.7792
r=? c=?
b=?
y=?
30° 45°
x=3 a=3
LEMBAR
40
40 PROPINSI JAWA TIMUR
BOGOR
Parung Panjang
DESA
BANJARJO
GAMBAR RENCANA
Kaca mati Daun jendela kaca PK RLH
5mm 105
5mm
Type Berat
200
LOKASI
Wetan
JUDUL GAMBAR
Dibuat Oleh :
Tenaga Fasilitator Lapangan
kosong b
Diperiksa Oleh :
Koordinator
Fasilitator Wilayah
90 65 65 Agus Salim
Alimudin, SE
PROPINSI JAWA TIMUR
40 BOGOR
40
Parung Panjang
DESA
BANJARJO
GAMBAR RENCANA
65 Kaca mati 5 mm Daun jendela kaca 5 mm
JENIS PRASARANA
0
LOKASI
200 0
80 80 JUDUL GAMBAR
Jendela 4 Unit
Dibuat Oleh :
Tenaga Fasilitator Lapangan
40
0
Diperiksa Oleh :
Koordinator Fasilitator Wilayah
80 80
Jalusi 1 Unit
0
90 Diketahui Oleh :
PjOK
PINTU 3 Unit
0
Perhitungan volume Bahan untuk Atap
Pekerjaan Beton meliputi Rangka Kuda kuda, Gording, Kaso, Usuk, Genteng dan Bubungan
Bubungan
1 Panjang RLH = 6 meter
2 Lebar RLH = 3 meter
3 Lebar Tritisan 0.5 meter
Perhitungan Kebutuhan Bahan dan Upah
r=? c=?
b=?
y=?
30° 45°
x=3 a=3
Harga Satuan
No Jenis Bahan / Material Satuan
(Rupiah)
Harga Satuan
No Jenis Bahan / Material Satuan
(Rupiah)
1 Kayu (8 cm x 12 cm x 4 m) Rangka Kuda-Kuda Batang 130,000.00
2 Kayu (6 cm x 12 cm x 4 m) / Gapit / Gording Batang 85,000.00
3 Kayu (5 cm x 7 cm x 400 cm) / Kaso Batang 43,000.00
4 Kayu (2 cm x 3 cm x 400 cm) / Reng Batang 20,500.00
5 Genteng Biji 900.00
6a Kerpu Bulat Biji 5,000.00
6b Kerpus Lancip Biji 3,500.00
7 Listplang papan (2 cm x 20 cm x 4 m) Batang 55,000.00
8 Besi beton Φ 12 mm SNI Batang 81,625.00
9 Besi beton Φ 8 mm SNI Batang 37,960.00
10 Semen @ 50 kg Zak 65,000.00
11 Pasir Pasang M³ 160,000.00
12 Batu Pecah M³ 190,000.00
13 Batu bata Biji 725.00
14 Kusen Pintu Depan (6 cm x 12 cm) Unit 500,000.00
15 Kusen Pintu Belakang (6 cm x 12) cm Unit 500,000.00
16 Kusen Pintu Kamar (6 cm x 12 cm) Unit 500,000.00
17 Kusen Jendela 2 lubang (6 cm x 12 cm) Unit 450,000.00
18 Kusen Jalusi 2 lubang (3 cm x 20 cm) Unit 450,000.00
19 Daun Pintu /Panel Kayu (3 cm x 20 cm) Unit 600,000.00
20 Daun Jendela Depan Kaca 5 mm Unit 700,000.00
21 Daun Jendela Kamar Kaca 5 mm Unit 250,000.00
22 Daun Jendela Ventilasi Kayu (3 cm x 30 cm) Unit 200,000.00
23 Closet Jongkok Unit 145,000.00
24 Pipa paralon 3 " M 100,000.00
25 Paku, engsel, slot pintu, kunci, kawat ikat Ls 250,000.00
26 Papan Bekisting Ls 50,000.00
27 Alat Bantu Ls 100,000.00
28 Tukang OH 70,000.00
29 Pekerja OH 50,000.00
30 Makan siang dan minum Kali 20,000.00
Volume Bahan
I
No Jenis Bahan / Material Satuan dari
BSPS
1 Kayu (8 cm x 12 cm x 4 m) Rangka Kuda-Kuda Batang #REF!
2 Kayu (6 cm x 12 cm x 4 m) / Gapit / Gording Batang #REF!
3 Kayu (5 cm x 7 cm x 400 cm) / Kaso Batang #REF!
4 Kayu (2 cm x 3 cm x 400 cm) / Reng Batang #REF!
5 Genteng Biji #REF!
6a Kerpu Bulat Biji -
6b Kerpus Lancip Biji #REF!
7 Listplang papan (2 cm x 20 cm x 4 m) Batang #REF!
8 Besi beton Φ 12 mm SNI Batang #REF!
9 Besi beton Φ 8 mm SNI Batang #REF!
10 Semen @ 50 kg Zak #REF!
11 Pasir Pasang M³ #REF!
12 Batu Pecah M³ #REF!
13 Batu bata Biji #REF!
14 Kusen Pintu Depan (6 cm x 12 cm) Unit #REF!
15 Kusen Pintu Belakang (6 cm x 12) cm Unit #REF!
16 Kusen Pintu Kamar (6 cm x 12 cm) Unit #REF!
17 Kusen Jendela 2 lubang (6 cm x 12 cm) Unit #REF!
18 Kusen Jalusi 2 lubang (3 cm x 20 cm) Unit #REF!
19 Daun Pintu /Panel Kayu (3 cm x 20 cm) Unit #REF!
20 Daun Jendela Depan Kaca 5 mm Unit #REF!
21 Daun Jendela Kamar Kaca 5 mm Unit #REF!
22 Daun Jendela Ventilasi Kayu (3 cm x 30 cm) Unit #REF!
23 Closet Jongkok Unit #REF!
24 Pipa paralon 3 " M #REF!
25 Paku, engsel, slot pintu, kunci, kawat ikat Ls #REF!
26 Papan Bekisting Ls #REF!
27 Alat Bantu Ls -
28 Tukang OH #REF!
29 Pekerja OH #REF!
30 Makan siang dan minum Kali #REF!
Jumlah
Volume Bahan
2
No Jenis Bahan / Material Satuan dari
BSPS
1 Kayu (8 cm x 12 cm x 4 m) Rangka Kuda-Kuda Batang #REF!
2 Kayu (6 cm x 12 cm x 4 m) / Gapit / Gording Batang #REF!
3 Kayu (5 cm x 7 cm x 400 cm) / Kaso Batang #REF!
4 Kayu (2 cm x 3 cm x 400 cm) / Reng Batang #REF!
5 Genteng Biji #REF!
6a Kerpu Bulat Biji -
6b Kerpus Lancip Biji #REF!
7 Listplang papan (2 cm x 20 cm x 4 m) Batang #REF!
8 Besi beton Φ 12 mm SNI Batang #REF!
9 Besi beton Φ 8 mm SNI Batang #REF!
10 Semen @ 50 kg Zak #REF!
11 Pasir Pasang M³ #REF!
12 Batu Pecah M³ #REF!
13 Batu bata Biji #REF!
14 Kusen Pintu Depan (6 cm x 12 cm) Unit #REF!
15 Kusen Pintu Belakang (6 cm x 12) cm Unit #REF!
16 Kusen Pintu Kamar (6 cm x 12 cm) Unit #REF!
17 Kusen Jendela 2 lubang (6 cm x 12 cm) Unit #REF!
18 Kusen Jalusi 2 lubang (3 cm x 20 cm) Unit #REF!
19 Daun Pintu /Panel Kayu (3 cm x 20 cm) Unit #REF!
20 Daun Jendela Depan Kaca 5 mm Unit #REF!
21 Daun Jendela Kamar Kaca 5 mm Unit #REF!
22 Daun Jendela Ventilasi Kayu (3 cm x 30 cm) Unit #REF!
23 Closet Jongkok Unit #REF!
24 Pipa paralon 3 " M #REF!
25 Paku, engsel, slot pintu, kunci, kawat ikat Ls #REF!
26 Papan Bekisting Ls #REF!
27 Alat Bantu Ls -
28 Tukang OH #REF!
29 Pekerja OH #REF!
30 Makan siang dan minum Kali #REF!
#REF!
rga Satuan Bahan
han Swadaya (BSPS)
Provinsi Lampung
017
Volume Bahan dari Harga Satuan Biaya dari
Swadaya Jumlah (Rupiah) BSPS Swadaya
#REF! #REF! 130,000.00 #REF! #REF!
#REF! #REF! 85,000.00 #REF! #REF!
#REF! #REF! 43,000.00 #REF! #REF!
#REF! #REF! 20,500.00 #REF! #REF!
#REF! #REF! 900.00 #REF! #REF!
- 5,000.00 - -
#REF! #REF! 3,500.00 #REF! #REF!
#REF! #REF! 55,000.00 #REF! #REF!
#REF! #REF! 81,625.00 #REF! #REF!
#REF! #REF! 37,960.00 #REF! #REF!
#REF! #REF! 65,000.00 #REF! #REF!
#REF! #REF! 160,000.00 #REF! #REF!
#REF! #REF! 190,000.00 #REF! #REF!
#REF! #REF! 725.00 #REF! #REF!
#REF! #REF! 500,000.00 #REF! #REF!
#REF! #REF! 500,000.00 #REF! #REF!
#REF! #REF! 500,000.00 #REF! #REF!
#REF! #REF! 450,000.00 #REF! #REF!
#REF! #REF! 450,000.00 #REF! #REF!
#REF! #REF! 600,000.00 #REF! #REF!
#REF! #REF! 700,000.00 #REF! #REF!
#REF! #REF! 250,000.00 #REF! #REF!
#REF! #REF! 200,000.00 #REF! #REF!
#REF! #REF! 145,000.00 #REF! #REF!
#REF! #REF! 100,000.00 #REF! #REF!
#REF! #REF! 250,000.00 #REF! #REF!
#REF! #REF! 50,000.00 #REF! #REF!
- 100,000.00 - -
#REF! #REF! 70,000.00 #REF! #REF!
#REF! #REF! 50,000.00 #REF! #REF!
#REF! #REF! 20,000.00 #REF! #REF!
#REF! #REF!
#REF!
daya (BSPS)
Lampung
130,000.00 #REF!
85,000.00 #REF!
43,000.00 #REF!
20,500.00 #REF!
900.00 #REF!
5,000.00 -
3,500.00 #REF!
55,000.00 #REF!
81,625.00 #REF!
37,960.00 #REF!
65,000.00 #REF!
160,000.00 #REF!
190,000.00 #REF!
725.00 #REF!
500,000.00 #REF!
500,000.00 #REF!
500,000.00 #REF!
450,000.00 #REF!
450,000.00 #REF!
600,000.00 #REF!
700,000.00 #REF!
250,000.00 #REF!
200,000.00 #REF!
145,000.00 #REF!
100,000.00 #REF!
250,000.00 #REF!
50,000.00 #REF!
100,000.00 -
70,000.00 #REF!
50,000.00 #REF!
20,000.00 #REF!
#REF!
7,500,000.00
#REF!
862.50
unan II
daya (BSPS)
Lampung
130,000.00 #REF!
85,000.00 #REF!
43,000.00 #REF!
20,500.00 #REF!
900.00 #REF!
5,000.00 -
3,500.00 #REF!
55,000.00 #REF!
81,625.00 #REF!
37,960.00 #REF!
65,000.00 #REF!
160,000.00 #REF!
190,000.00 #REF!
725.00 #REF!
500,000.00 #REF!
500,000.00 #REF!
500,000.00 #REF!
450,000.00 #REF!
450,000.00 #REF!
600,000.00 #REF!
700,000.00 #REF!
250,000.00 #REF!
200,000.00 #REF!
145,000.00 #REF!
100,000.00 #REF!
250,000.00 #REF!
50,000.00 #REF!
100,000.00 -
70,000.00 #REF!
50,000.00 #REF!
20,000.00 #REF!
#REF!
7,500,000.00
#REF!
aya dari Lihat RAB
Kontrol
Jumlah (Rupiah)
#REF!
#REF!
#REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
- 0
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
- 0
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF! #REF!
#REF!
MATRIK PERHITUNGAN CEPAT DALAM PEMBANGUNAN RUMAH
VOLUME
NO ITEM PEKERJAAN KATEGORI MATERIAL RAB KETERANGAN
SATUAN HARGA
1 ATAP Semua Jenis Tipologi Rumah BSPS Rangka Kayu M² 150,000 5,400,000 Luas Bangunan 36 M² Rumah Tembok rata-rata Rp.
600.000,-/ M²
(6 X 6) = 36 M2 Genteng M² 100,000 3,600,000
Seng M² 45,000 1,620,000
Rumah Setengah Tembok
rata-rata Rp. 630.000,-/ M²
Upah Tukang dan Tenaga (2 orang) hari 200,000 1,000,000 5 hari kerja
Rumah Kayu Panggung dan
2 LANTAI Rumah Tembok dan Setengah Tembok Lantai Rabat M² 100,000 3,600,000 Tebal 10 Cm Non Panggung rata-rata Rp.
700.000,-/ M²
(6 X 6) = 36 M2 Upah Tukang dan Tenaga (2 orang) hari 200,000 600,000 3 hari kerja
Rumah Kayu Panggung dan Non Panggung Lantai Kayu M² 150,000 5,400,000 Kayu plus Rangka
Upah Tukang dan Tenaga (2 orang) hari 200,000 1,000,000 5 hari kerja
-
3 DINDING Tembok Batu Bata M² 120,000 4,320,000 Non Plester
(6 X 6) = 36 M2 Batako M² 90,000 3,240,000 Non Plester
Asumsi Tinggi 3 M Batu Bata Ringan/ Hebel M² 150,000 5,400,000 Harus Plesteran
Upah Tukang dan Tenaga (3 orang) hari 300,000 3,000,000 10 hari kerja
CATATAN : 1. Asumsi Rumah Tembok dengan Luas Bangunan 36 M2 menghabiskan Dana Rp. 21.520.000,- (Stimulan Rp. 15.000.000,- Perlu swadaya Rp. 6.520.000,-)
2. Asumsi Rumah Setengah Tembok dengan Luas Bangunan 36 M2 menghabiskan Dana Rp. 24.800.000,- (Stimulan Rp. 15.000.000,- Perlu swadaya Rp. 9.800.000,-)
3. Asumsi Rumah Kayu dengan Luas Bangunan 36 M2 menghabiskan Dana Rp. 26.300.000,- (Stimulan Rp. 15.000.000,- Perlu swadaya Rp. 11.300.000,-)
198
MATRIK PERHITUNGAN CEPAT DALAM PEMBANGUNAN RUMAH
ASUMSI NILAI LUAS BESARAN BANTUAN
NILAI RAB BESARAN
NO ITEM PEKERJAAN (M2 BANGUNAN
(M2) SWADAYA
BANGUNAN) (M2) PKRS PBRS
1 PKRS Rumah Tembok rata-rata Rp. 600.000,-/ M² 600,000 21,600,000 6,600,000
2 PKRS Rumah Setengah Tembok rata-rata Rp. 630.000,-/ M² 630,000 22,680,000 15,000,000 7,680,000
36
3 PKRS Rumah Kayu Panggung dan Non Panggung rata-rata Rp. 700.000,-/ M² 700,000 25,200,000 10,200,000
4 PBRS Rumah Tembok rata-rata Rp. 1.500.000,-/ M² 1,500,000 54,000,000 30,000,000 24,000,000