Anda di halaman 1dari 1

TAKE OF SHEET (TOS)

DESA : HARAPAN
KECAMATAN : PONDOK KELAPA
KABUPATEN : BENGKULU TENGAH
PROPINSI : BENGKULU
TAHUN ANGGARAN : 2023
PEKERJAAN : PEMBANGUNAN JALAN PARIWISATA DESA HARAPAN
LOKASI : DUSUN III
VOLUME : 87 m' x 4 m' Meter'
KETERANGAN :
* Pekerjaan lapis penetrasi Tebal 10 cm
* Panjang Jalan : 87.0 Meter'
* Lebar Jalan : 4.0 Meter'
* Volume : 348.0 Meter2

MENGHAMPAR BATU PECAH 5/7 + 3/5 (Dipadatkan)


A. BAHAN
1 Batu Belah (7/10 cm) = 0.1200 M3 x 348.00 M2 = 41.76 M3
2 Batu pecah 3/5 = 0.0400 M3 x 348.00 M2 = 13.92 M3
B. ALAT
1 Wales 6-8 ton = 0.0267 Jam / M2 x 348.00 M2 = 9.28 Jam / M2 ~ 1.00 Hari
C. UPAH
1 Pekerja = 0.0750 Hok x 348.00 M2 = 26.10 Hok
2 Kepala Tukang = 0.0038 Hok x 348.00 M2 = 1.31 Hok
3 Operator = 0.0267 Jam x 348.00 M2 = 9.28 Jam ~ 1.00 Hok

MENGHAMPAR BATU PECAH 2/3 + 1/2 (Dipadatkan)


A. BAHAN
1 Batu pecah 2/3 = 0.0350 M3 x 348.00 M2 = 12.18 M3
2 Batu pecah 1/2 = 0.0150 M3 x 348.00 M2 = 5.22 M3
B. ALAT
1 Wales 6-8 ton = 0.0267 Jam / M2 x 348.00 M2 = 9.28 Jam / M2 ~ 1.00 Hari
C. UPAH
1 Pekerja = 0.0750 Hok x 348.00 M2 = 26.10 Hok
2 Kepala tukang = 0.0038 Hok x 348.00 M2 = 1.31 Hok
3 Operator = 0.0267 Jam x 348.00 M2 = 9.28 Jam ~ 1.00 Hok

MENGASPHALT 2X MUKA JALAN


A. BAHAN
1 Asphlat 60/70 = 5.0000 M3 x 348.00 M2 = 1,740.00 M3 ~ 11.00 Drum
2 Abu Batu / Pasir jagung = 0.0120 M3 x 348.00 M2 = 4.18 M3
B. ALAT
1 Wales 6-8 ton = 0.0013 Jam / M2 x 348.00 M2 = 0.46 Jam / M2 ~ - Hari
2 Kayu Bakar (Tempat masak asphalt) = 0.0050 Bh x 348.00 M2 = 1.74 Bh
C. UPAH
1 Pekerja = 0.1000 Hok x 348.00 M2 = 34.80 Hok
2 Kepala tukang = 0.0050 Hok x 348.00 M2 = 1.74 Hok

Urugan Base B(10 cm) 34.80 m3


A. BAHAN
1 Agregat Kelas B = 1.2000 m3 x 34.8000 m3 = 41.76 m3
B.UPAH
1 Pekerja = 0.3000 Hok x 34.8000 m3 = 10.44 Hok

REKAPITULASI BAHAN, ALAT DAN UPAH


1 Batu Belah (7/10 cm) = 41.8 M3
2 Batu pecah 3/5 = 13.9 M3
3 Batu pecah 2/3 = 12.2 M3
4 Batu pecah 1/2 = 5.2 M3
5 Agregat Kelas B = 41.8 M3
6 Asphlat 60/70 = 1,740.0 KG ~ 11.00 Drum (1 drum = 155 kg)
7 Kayu Bakar (Tempat masak asphalt) = 1.7 BH
8 Abu Batu / Pasir jagung = 4.2 M3
9 Vibrator roller 6-8 Ton = 19.0 Jam
10 Pekerja = 97.4 HOK
11 Kepala tukang = 4.4 HOK
Biaya BBM Alat Grader = 16.0 ltr/jam x 8.00 = 128 Ltr
Vibrator Roller = 10.0 ltr/jam x 19.0 = 190.24 Ltr jumlah = 318 Ltr