RENCANA ANGGARAN BIAYA (RAB)

SHAND SHEET JALAN DESA KARYAMUKTI

Propinsi : Jawa BaratLokasi : Desa Karyamukti


Kabupaten : Ciamis Bidang : Infrastruktur
Kecamatan : BanjaranyaJenis Kegiatan : Shand sheet Jalan
Desa : KaryamuktVolume : 400 x 3 x 0,015 m

HARGA
NO URAIAN VOLUME SATUAN JUMLAH (Rp)
SATUAN (Rp)

1 2 3 4 6 7
A. Belanja Modal/Barang dan Jasa
1 Aspal 21 Drum 1,850,000 38,850,000

2 Pasir Aspal 21 M³ 275,000 5,775,000

3 Barangkal 144 M³ 165,000 23,760,000

4 Kayu bakar 42 M³ 120,000 5,040,000

Sub Total 1 73,425,000

B. Belanja Alat
1 Papan Nama Kegiatan 1 Ls 150,000 150,000

2 Prasasti 1 Ls 350,000 350,000

3 Sewa Mesin Gilas 7 Hari 400,000 2,800,000

4 Sekop 4 Buah 125,000 500,000

5 Pengki 2 Buah 27,500 55,000

6 Cangkul 3 Buah 75,000 225,000

7 Mobilisasi 1 Paket 3,000,000 3,000,000

8 Benang 2 Buah 3,500 7,000

9 Meteran 1 Buah 18,000 18,000

10 Sewa Mobil Angkutan 7 Hari 250,000 1,750,000

Sub Total 2 8,855,000

C Upah
1 Pekerja 197 Hok 80,000 15,760,000

2 Tukang 7 Hok 90,000 630,000

3 Juru Godog 7 Hok 90,000 630,000

4 Mandor 7 Hok 100,000 700,000


Sub Total 3 17,720,000
Jumlah 100,000,000

Disetujui Diverifikasi Oleh: Karyamukti,…................... 2022


Kepala Desa Karyamukti Sekretaris Desa Pelaksan Kegiatan

ANDRY SUWANDI ARMAN TARSAN SETIAWAN


Kabupaten Ciamis Jenis Prasarana Perkerasan Sand Sheet
Kecamatan Banjaranyar Take Of Sheet Lokasi Jalan Dusun
Desa Karyamukti Volume 350 X 3.00 x 0.015 m

PERKERASAN SEND SHEET TB. 2 CM SS-A

0.10 m 3.00 m 0.10

Perhirtungan Volume Bahan

1. Volume Aspal

Volume Sand Sheet V1= 350 X 3.00 = 1050.0 m²


Labur Aspal V total = 1050.0 m²
Patching / tambal 100 X 1.20 = 119.7 m³

I. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK LAPIS PEREKAT ( TEAK COAT )
Ref Analisa Dinas Binamarga
Ket 1 Drum Aspal Berat = 155 Kg
A. Bahan Koefisien
1. Aspal = 0.5000 X 1050.00 = 525.0 Kg Dibulatkan 525 Kg
2. Minyak tanah/Solar = 0.2346 X 119.70 = 28.1 Liter Dibulatkan 29 Liter
3. Kayu Bakar = 0.0019 X 1050.00 = 2.0 m3 Dibulatkan 2 m3

B. Upah
1. Pekerja = 0.0247 x 1050.00 = 25.935 HOK Dibulatkan 26 HOK

II. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK SAND SHEET


Ref Analisa Dinas Binamarga
Ket 1 Drum Aspal Berat = 155 Kg
A. Bahan Koefisien
1. Aspal 2.500 X 1050.00 = 2625.0 Kg Dibulatkan 2625 Kg
2. Pasir Aspal 0.020 X 1050.00 = 21.0 m3 Dibulatkan 21 m3
3. Kayu bakar 0.040 X 1050.00 = 42.0 m3 Dibulatkan 42 m3

B. Upah
1. Juru godog aspal 0.005 x 1050.0 = 5.25 HOK Dibulatkan 6 HOK
2. Pekerja Aspal = 0.162 x 1050.0 = 170.10 HOK Dibulatkan 171 HOK
3. Tukang Aspal = 0.008 x 1050.0 = 8.40 HOK Dibulatkan 9 HOK

III . Sewa alat


1. Mesin Gilas = 0.0020 X 1050.0 = 2.1 x 1.00 = 2.100 Dibulatkan 3 hari

II. ANALISA KEBUTUHAN BAHAN DAN UPAH UNTUK LAPIS PONDASI /PERATA PENETRASI
A. Bahan
1 Sirtu 1.200 X 119.70 = 143.6 m³ Dibulatkan 144 m³

B. Upah
1 Pekerja 0.250 x 143.6 = 35.91 HOK Dibulatkan 36 HOK
2 Mandor 0.025 x 143.6 = 3.59 HOK Dibulatkan 4 HOK

Rekap
Bahan
Aspal 21
Pasir Aspal 21
Kayu bakar 42
Sirtu 144
Minyak tanah/Solar 29
Upah
Juru godog aspal 6
Pekerja Aspal 197
Tukang Aspal 9
Mandor 4
PEK. PADAT KARYA SHAND SHAND SHEET JALAN DESA
PEMBERSIHAN / PEMBUKAAN Upah jml orang hari
JALAN 1. Pekerja 10 1.00 10.00 HOK

PEKERJAAN BEREUM JALAN volume 35.000 m3


Upah
1. Pekerja 0.5 35.00 17.50 HOK

PEKERJAAN NORMALISASI volume 112.000 m3


SALURAN Upah
1. Pekerja 0.75 0.00 HOK

PEKERJAAN PEMATOKAN Upah jml orang hari


JALAN 1. Pekerja 5 1.00 5.00 HOK
Format Kebutuhan Bahan Alat Upah Untuk RAB

Pembulata
No. Uraian/Bahan Volume Satuan Harga Sat Jumlah Harga PPN PPH Jumlah Harga + PPN+PPH n Harga Sat
Harga Sat
PPN+PPH RAB
1 Aspal 1.0 Drum 1,300,000 1,300,000 118,181.82 17,727 1,435,909 135,909 135,900 1,435,900
2 Pasir Aspal 1.0 m3 230,000 230,000 20,909.09 3,136 254,045 24,045 24,000 254,000
3 Kayu bakar 1.0 m3 75,000 75,000 6,818.18 1,023 82,841 7,841 7,800 82,800
4 Minyak tanah/Solar 1.0 ltr 6,500 6,500 590.91 89 7,180 680 600 7,100
5 Pengki 1.0 buah 25,000 25,000 2,272.73 341 27,614 2,614 2,600 27,600
6 Roda Artco 1.0 unit 500,000 500,000 45,454.55 6,818 552,273 52,273 52,200 552,200
7 Drum Bekas 1.0 bh 250,000 250,000 22,727.27 3,409 276,136 26,136 26,100 276,100
8 Sewa Mesin Gilas 1.0 ls 600,000 600,000 54,545.45 8,182 662,727 62,727 62,700 662,700
9 Mobilisasi & Demobilisas 1.0 ls 1,600,000 1,600,000 145,454.55 21,818 1,767,273 167,273 167,200 1,767,200
10 - Juru Godog Aspal 1.0 Hok 70,000 70,000 Nihil - 70,000
11 - Pekerja Aspal 1.0 Hok 75,000 75,000 Nihil - 75,000
12 - Tukang Aspal 1.0 Hok 85,000 85,000 Nihil - 85,000
Jumlah PPN + PPH Yang Harus dibayar 416,955 62,543 5,065,998 479,498 479,100 5,065,600
RENCANA ANGGARAN BIAYA

Propinsi : Jawa Barat No. RAB


Kabupaten : Ciamis RAB Untuk APBDes Program
Kecamatan : Banjaranyar Jenis Kegiatan
Desa : Karyamukti Ukuran

VOLUME Harga BIAYA


Satuan
URAIAN Satuan
Total Swadaya Dana Desa Swadaya
(Rp)

I. Bahan
1 Aspal 21 21 drum 1,850,000 -
2 Pasir Aspal 21 21 m³ 265,000 -
3 Kayu bakar 42 42 m³ 100,000 -
4 Sirtu 144 144 m³ 135,000 -

Sub Total 1) -
II. Alat
1 Mobilisasi & Demobilisasi Mesin Gilas 1 1 Ls 2,000,000 -
2 Sewa Mesin Gilas 3 3 hari 450,000 -
3 Pengki 10 10 Buah 21,500 -
4 Roda Artco 2 2 Unit 550,000 -
Sub Total 2) -
III. Upah
1 Juru Godog 6 6 HOK 70,000 -
2 Pekerja 230 230 HOK 60,000 -
3 Tukang 9 9 HOK 70,000
4 Mandor 4 4 HOK 75,000
Sub Total 3) -
IV. Lain Lain
1 Papan Proyek / Kegiatan 1 1 HOK 150,000 -
2 Prasasti 1 1 HOK 350,000 -
Sub Total 3) -
Jumlah Total -

Dari Dana Desa

SUMBER DANA Dari Swadaya

TOTAL

…………………….., ………………………
Disetujui Oleh : Dibuat Oleh :
Kepala Desa TPK

__________________________ ___________________
RENCANA ANGGARAN BIAYA

: Propinsi
: Dana Desa Kabupaten
: Semi Hotmix Kecamatan
: Panjang 600 M' ; Lebar 4 M Desa

BIAYA (Rp)

Dana Desa Total

I. Bahan
38,850,000 38,850,000 ###
5,565,000 5,565,000 ###
4,200,000 4,200,000 ###
19,440,000 19,440,000 ###

68,055,000 Sub Total 1)


68,055,000
II. Alat
2,000,000 2,000,000 ###
1,350,000 1,350,000 ###
215,000 215,000
1,100,000 1,100,000
4,665,000 Sub Total 2)
4,665,000
III. Upah
420,000 420,000 ###
13,800,000 13,800,000 ###
630,000 630,000
300,000 300,000
15,150,000 Sub Total 3)
15,150,000
III. Upah
150,000 150,000 ###
350,000 350,000 ###
500,000 Sub Total 3)
500,000
88,370,000 88,370,000
Jumlah Total

Dari Dana Desa 88,370,000

Dari Swadaya -

TOTAL 88,370,000

…………….., …………………………….2017…………………….., …………………………….2015


Dibuat Oleh : Disetujui Oleh :
TPK Kepala Desa

_____________________ __________________________