Anda di halaman 1dari 15

RENCANA ANGGARAN BIAYA

PEKERJAAN : PUSAT RESTORASI DAN PENGEMBANGAN EKOWISATA PESISIR (PRPEP)


LOKASI : KABUPATEN GORONTALO UTARA
TAHUN ANGGARAN : 2018

NO URAIAN PEKERJAAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN 33,000,000.00

2 PEKERJAAN TRACKING MANGROVE (226 m) 190,282,599.87

3 PEKERJAAN GAZEBO ( 5 buah; 2 m x 2 m) 35,901,255.10

4 PEKERJAAN REST AREA (1 buah; 16 m x 4 m) 29,766,044.11

5 PEKERJAAN KANTIN ( 1 buah; 6 m x 6 m) 27,297,284.98

6 PEKERJAAN RUANG AULA (1 buah; 8 m x 12 m) 44,295,921.10

7 PEKERJAAN GAPURA PINTU MASUK 31,035,883.98

8 PAGAR HOLLOW DAN HURUF 41,840,040.00

9 PEKERJAAN LAIN-LAIN 4,123,518.00

Total 437,542,547.15
Pajak 10 % 43,754,254.71
Total Biaya (Termasuk Pajak) 481,296,801.86
DIBULATKAN 481,296,000.00

Terbilang : Empat Ratus Delapan Puluh Satu juta Dua ratus


Sembilan Puluh Enam Ribu Rupiah

as Makassar, 31 Mei 2018


CV. Andara Karya Abadi

Supi Batara Tungke


Direktur
RENCANA ANGGARAN BIAYA
PEKERJAAN : PUSAT RESTORASI DAN PENGEMBANGAN EKOWISATA PESISIR (PRPEP)
LOKASI : KABUPATEN GORONTALO UTARA
TAHUN ANGGARAN : 2018

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN
1 Pek. Pas. Bouwplank dan Pengukuran Ulang 1.00 ls 1,500,000.00 1,500,000.00
2 Pembuatan Papan Proyek 1.00 ls 1,500,000.00 1,500,000.00
3 Gudang Bahan dan Direksi Keet 1.00 ls 10,000,000.00 10,000,000.00
4 Penyediaan Air Kerja 1.00 ls 5,000,000.00 5,000,000.00
5 Mobilisasi 1.00 ls 15,000,000.00 15,000,000.00
Sub Total I 33,000,000.00
II PEKERJAAN TRACKING MANGROVE (226 m)
(Tracking Utama, Jalan menuju Aula Pertemuan, Jalan menuju Gazebo, Jalan menuju Kantin, dan Area Spot Foto)
1 Pekerjaan Galian Tanah 001 17.18 m3 73,975.00 1,270,890.50
PEKERJAAN BETON
1 Pekerjaan Tiang Beton 25/25 007 17.19 m2 3,568,955.06 61,350,337.48
2 Pekerjaan Telapak 50 cm x 50 cm x 20 cm 010 11.45 m3 3,186,940.46 36,490,468.27
3 Pekerjaan Balok Beton 20/25 008 5.73 m3 3,652,095.92 20,926,509.62
4 PEKERJAAN KAYU -
5 Pekerjaan Balok Gelagar Kayu 6/12 017 5.05 m3 4,323,000.00 21,831,150.00
6 Pekerjaan Lantai Papan 25/3 cm 020 359.00 m2 100,980.00 36,251,820.00
7 Pekerjaan Pengunci Lantai Papan 10/3 cm 020 46.80 m2 100,980.00 4,725,864.00
8 Pekerjaan Railing 5/5 017 1.72 m3 4,323,000.00 7,435,560.00
Sub Total II 190,282,599.87
III PEKERJAAN GAZEBO ( 5 buah; 2 m x 2 m)
1 Pekerjaan Galian Tanah 001 0.30 m3 73,975.00 22,192.50
PEKERJAAN BETON
1 Pekerjaan Tiang Beton 25/25 007 0.48 m3 3,568,955.06 1,713,098.43
2 Pekerjaan Telapak 50 cm x 50 cm x 20 cm 010 0.20 m3 3,186,940.46 637,388.09
3 PEKERJAAN KAYU
4 Pekerjaan Railing 5/5 017 0.06 m3 4,323,000.00 259,380.00
5 Tiang Balok 10/10 017 0.07 m3 4,323,000.00 302,610.00
6 Pekerjaan Balok Gelagar Kayu 6/12 017 0.17 m3 4,323,000.00 734,910.00
7 Pekerjaan Lantai Papan 25/3 cm 020 4.00 m2 100,980.00 403,920.00
PEKERJAAN ATAP
1 Pekerjaan Balok Kuda-kuda 6/12 017 0.14 m3 4,323,000.00 605,220.00
2 Atap Genteng Metal 019 18.00 m2 138,974.00 2,501,532.00
Biaya Pembangunan 1.00 buah gasebo 7,180,251.02
Biaya Pembangunan 5.00 buah gasebo Sub Total III 35,901,255.10
IV PEKERJAAN REST AREA (1 buah; 16 m x 4 m)
1 Pekerjaan Galian Tanah 001 2.03 m3 73,975.00 150,169.25
2 Pekerjaan Tiang Beton 25/25 007 3.21 m3 3,568,955.06 11,456,345.74
3 Pekerjaan Telapak 50 cm x 50 cm x 20 cm 010 1.35 m3 3,186,940.46 4,302,369.62
4 Pekerjaan Balok Beton 20/25 008 1.35 m3 3,652,095.92 4,930,329.49
5 Pekerjaan Railing 5/5 017 0.15 m3 4,323,000.00 648,450.00
6 Tiang Balok 10/10 017 0.07 m3 4,323,000.00 302,610.00
7 Pekerjaan Balok Gelagar Kayu 6/12 017 0.35 m3 4,323,000.00 1,513,050.00
8 Pekerjaan Lantai Papan 25/3 cm 020 64.00 m2 100,980.00 6,462,720.00
Sub Total IV 29,766,044.11
V PEKERJAAN KANTIN ( 1 buah; 6 m x 6 m)
1 Pekerjaan Galian Tanah 001 1.20 m3 73,975.00 88,770.00
2 Pekerjaan Tiang Beton 25/25 007 1.90 m3 3,568,955.06 6,781,014.61
3 Pekerjaan Telapak 50 cm x 50 cm x 20 cm 010 0.80 m3 3,186,940.46 2,549,552.37
4 Pekerjaan Railing 5/5 017 0.17 m3 4,323,000.00 734,910.00
5 Tiang Balok 10/10 017 0.07 m3 4,323,000.00 302,610.00
6 Kuda-kuda 5/7 017 0.14 m2 4,323,000.00 605,220.00
7 Atap Genteng Metal 019 72.00 m2 138,974.00 10,006,128.00
8 Pekerjaan Balok Gelagar Kayu 6/12 017 0.60 m3 4,323,000.00 2,593,800.00
9 Pekerjaan Lantai Papan 25/3 cm 020 36.00 m2 100,980.00 3,635,280.00
Sub Total V 27,297,284.98
VI PEKERJAAN RUANG AULA (1 buah; 8 m x 12 m)
1 Pekerjaan Galian Tanah 001 2.63 m3 73,975.00 194,554.25
2 Pekerjaan Tiang Beton 25/25 007 4.16 m3 3,568,955.06 14,846,853.05
3 Pekerjaan Telapak 50 cm x 50 cm x 20 cm 010 1.75 m3 3,186,940.46 5,577,145.81
4 Pekerjaan Railing 5/5 017 0.15 m3 4,323,000.00 648,450.00
5 Tiang Balok 10/10 017 0.40 m3 4,323,000.00 1,729,200.00
6 Kuda-kuda 5/7 017 0.29 m2 4,323,000.00 1,253,670.00
7 Atap Genteng Metal 019 72.00 m2 138,974.00 10,006,128.00
8 Pekerjaan Balok Gelagar Kayu 6/12 017 0.08 m3 4,323,000.00 345,840.00
9 Pekerjaan Lantai Papan 25/3 cm 020 96.00 m2 100,980.00 9,694,080.00
Sub Total VI 44,295,921.10
VII GAPURA PINTU MASUK
1 Pekerjaan Galian Tanah 001 0.68 m3 73,975.00 50,303.00
PEKERJAAN BETON
1 Pekerjaan Telapak 120 cm x 120 cm x 20 cm 011 0.58 m3 3,120,986.26
2 Pekerjaan Tiang 70 cm x 70 cm 009 5.29 m3 2,188,630.14 11,577,853.42
3 Plat Beton t-10 cm 012 1.33 m3 3,149,435.30 4,188,748.95
4 Dinding Bata 013 16.00 m2 112,512.40 1,800,198.40
5 Plaster 014 47.52 m2 59,685.12 2,836,236.90
6 Aci 015 47.52 m2 37,207.50 1,768,100.40
7 Batu Alam 023 16.00 m2 502,727.50 8,043,640.00
8 Finish Cat 016 47.52 m2 16,220.60 770,802.91
9 Huruf Acrilic 18.00 bh -
Sub Total VII 31,035,883.98
VIII PAGAR HOLLOW DAN HURUF
1 Pagar Hollow H 120 cm 022 18.00 m 334,620.00 6,023,160.00
2 Huruf plat besi t=1mm h 80 cm 021 16.00 Bh 2,238,555.00 35,816,880.00
Sub Total VIII 41,840,040.00
IX PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir 1.00 ls 500,000.00 500,000.00
2 Papan Informasi (di Aula Pertemuan) 024 1.00 Bh 1,123,518.00 1,123,518.00
3 Laporan, Dokumentasi (Foto, Video, dan Drone), dan As-built 1.00 ls 2,500,000.00 2,500,000.00
Sub Total IX 4,123,518.00
ANALISA HARGA SATUAN
Pekerjaan :PUSAT RESTORASI DAN PENGEMBANGAN EKOWISATA PESISIR (PRPEP)
Lokasi :KABUPATEN GORONTALO UTARA
Tahun Anggaran : 2018

NO URAIAN PEKERJAAN SAT KOEIFISIEN HARGA JUMLAH

001 1 M3 Galian Tanah


Bahan
a.
Tenaga
a.Pekerja Oh 0.75 85,000.00 63,750.00
b.M a n d o r Oh 0.025 140,000.00 3,500.00
Jumlah 67,250.00
Overhead 10 % 6,725.00
Jumlah Total 73,975.00

002 1 M3 Beton 1SP:2PB:3KR


Bahan
a Pasir Pasang m3 0.50 120,000.00 60,000.00
b Batu Kerikil m3 0.78 300,000.00 234,000.00
c Semen Kg 371 1,300.00 482,300.00
Tenaga
a.Tukang Oh 0.25 100,000.00 25,000.00
b.Kepala Tukang Oh 0.025 120,000.00 3,000.00
c. Pekerja Oh 1.65 85,000.00 140,250.00
d.Mandor Oh 0.08 140,000.00 11,200.00
Jumlah 955,750.00
Overhead 10 % 95,575.00
Jumlah Total 1,051,325.00

003 Pembesian Per 10 Kg Besi Polos / Ulir


Bahan
a Besi Beton Kg 10.5 4,500.00 47,250.00
b Kawat Beton Kg 1.05 20,000.00 21,000.00
Tenaga
a.Tukang Oh 0.07 100,000.00 7,000.00
b.Kepala Tukang Oh 0.007 120,000.00 840.00
c. Pekerja Oh 0.07 85,000.00 5,950.00
d.Mandor Oh 0.008 140,000.00 1,120.00
Jumlah 83,160.00
Overhead 10 % 8,316.00
Jumlah Total 91,476.00
004 1 M2 Membuat / Membongkar Cetakan Bekisting Sloof
Bahan
a kayu Kelas III m3 0.025 1,800,000.00 45,000.00
b Paku 5 - 10 cm Kg 0.3 25,000.00 7,500.00
c Minyak bakisting Ltr 0.1 10,000.00 1,000.00
Tenaga
a.Tukang Oh 0.16 100,000.00 16,000.00
b.Kepala Tukang Oh 0.016 120,000.00 1,920.00
c. Pekerja Oh 0.32 85,000.00 27,200.00
d.Mandor Oh 0.016 140,000.00 2,240.00
Jumlah 100,860.00
Overhead 10 % 10,086.00
Jumlah Total 110,946.00

005 1 M2 Membuat / Membongkar Cetakan Bekisting Sloof


Bahan
a kayu Kelas III m3 0.025 1,800,000.00 45,000.00
b Paku 5 - 12 cm Kg 0.3 25,000.00 7,500.00
c Minyak bakisting Ltr 0.1 10,000.00 1,000.00
d Balok Kayu Kls III m3 0.015 1,800,000.00 27,000.00
e Dolken Kayu Dia. (8-10 cm), Panjang 4 m btg 2 20,000.00 40,000.00
Tenaga
a.Tukang Oh 0.16 100,000.00 16,000.00
b.Kepala Tukang Oh 0.016 120,000.00 1,920.00
c. Pekerja Oh 0.32 85,000.00 27,200.00
d.Mandor Oh 0.016 140,000.00 2,240.00
Jumlah 167,860.00
Overhead 10 % 16,786.00
Jumlah Total 184,646.00

006 1 M2 Membuat / Membongkar Cetakan Bekisting Balok


Bahan
a kayu Kelas III m3 0.02 1,800,000.00 36,000.00
b Paku 5 - 12 cm Kg 0.4 25,000.00 10,000.00
c Minyak bakisting Ltr 0.2 10,000.00 2,000.00
d Balok Kayu Kls II m3 0.015 2,500,000.00 37,500.00
e Dolken Kayu Dia. (8-10 cm), Panjang 4 m btg 2 20,000.00 40,000.00
Tenaga
a.Tukang Oh 0.16 100,000.00 16,000.00
b.Kepala Tukang Oh 0.016 120,000.00 1,920.00
c. Pekerja Oh 0.32 85,000.00 27,200.00
d.Mandor Oh 0.016 140,000.00 2,240.00
Jumlah 172,860.00
Overhead 10 % 17,286.00
Jumlah Total 190,146.00
007 KOLOM 25/25
1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 126.6 8,316.00 1,052,805.60
c Bekesting m2 6.5 190,146.00 1,235,949.00
Jumlah 3,244,504.60
Overhead 10 % 324,450.46
Jumlah Total 3,568,955.06

008 BALOK 20/25


1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 149.2 8,316.00 1,240,747.20
c Bekesting m2 6.5 172,860.00 1,123,590.00
Jumlah 3,320,087.20
Overhead 10 % 332,008.72
Jumlah Total 3,652,095.92

009 KOLOM 70/70


1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 37.61 8,316.00 312,764.76
c Bekesting m2 6.5 110,946.00 721,149.00
Jumlah 1,989,663.76
Overhead 10 % 198,966.38
Jumlah Total 2,188,630.14

010 TELAPAK 50x50x20


1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 98.35 8,316.00 817,878.60
c Bekesting m2 6.5 172,860.00 1,123,590.00
Jumlah 2,897,218.60
Overhead 10 % 289,721.86
Jumlah Total 3,186,940.46

011 TELAPAK 120x120x20


1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 91.14 8,316.00 757,920.24
c Bekesting m2 6.5 172,860.00 1,123,590.00
Jumlah 2,837,260.24
Overhead 10 % 283,726.02
Jumlah Total 3,120,986.26
012 PLAT 10 cm
1 M3 Beton
a 1 M3 Beton 1SP:2PB:3KR m3 1 955,750.00 955,750.00
b Besi Beton kg 94.25 8,316.00 783,783.00
c Bekesting m2 6.5 172,860.00 1,123,590.00
Jumlah 2,863,123.00
Overhead 10 % 286,312.30
Jumlah Total 3,149,435.30

013 1 M2 Pasangan Dinding Batu Bata 1 : 5


Bahan
a Batu bata Bh 70.00 650.00 45,500.00
b Semen Kg 9.68 1,300.00 12,584.00
c Pasir Pasang m3 0.045 120,000.00 5,400.00
Tenaga
a.Tukang Oh 0.100 100,000.00 10,000.00
b.Kepala Tukang Oh 0.010 120,000.00 1,200.00
c. Pekerja Oh 0.300 85,000.00 25,500.00
d.Mandor Oh 0.015 140,000.00 2,100.00
Jumlah 102,284.00
Overhead 10 % 10,228.40
Jumlah Total 112,512.40

014 1 M2 Plesteran Dinding 1 : 5 (t=15mm)


a Pasir Pasang m3 0.026 120,000.00 3,120.00
b Semen Kg 5.184 1,300.00 6,739.20
Tenaga
a.Tukang Oh 0.150 100,000.00 15,000.00
b.Kepala Tukang Oh 0.015 120,000.00 1,800.00
c. Pekerja Oh 0.300 85,000.00 25,500.00
d.Mandor Oh 0.015 140,000.00 2,100.00
Jumlah 54,259.20
Overhead 10 % 5,425.92
Jumlah Total 59,685.12

015 1 M2 Acian Air Semen


Bahan
a Semen Bh 3.25 1,300.00 4,225.00
Tenaga
a.Tukang Batu Oh 0.100 100,000.00 10,000.00
b.Kepala Tukang Oh 0.010 120,000.00 1,200.00
c. Pekerja Oh 0.200 85,000.00 17,000.00
d.Mandor Oh 0.010 140,000.00 1,400.00
Jumlah 33,825.00
Overhead 10 % 3,382.50
Jumlah Total 37,207.50
016 1 M2 Pek. Cat Tembok / Plafond
Bahan
a Plamur Bh 0.10 15,000.00 1,500.00
b Cat dasar (Komilex) Kg 0.10 18,000.00 1,800.00
c Cat penutup 1X (Catylax) m3 0.13 18,000.00 2,340.00
Tenaga
a.Tukang Cat Oh 0.0630 100,000.00 6,300.00
b.Kepala Tukang Oh 0.0063 120,000.00 756.00
c. Pekerja Oh 0.0200 85,000.00 1,700.00
d.Mandor Oh 0.0025 140,000.00 350.00
Jumlah 14,746.00
Overhead 10 % 1,474.60
Jumlah Total 16,220.60

017 1 M3 Pek. Kayu Balok


Bahan
a kayu Kelas II m3 1.10 2,500,000.00 2,750,000.00
b Paku Kg 5.60 25,000.00 140,000.00
Tenaga
a.Tukang kayu Oh 6.00 100,000.00 600,000.00
b.Kepala Tukang Oh 0.60 120,000.00 72,000.00
c. Pekerja Oh 4.00 85,000.00 340,000.00
d.Mandor Oh 0.20 140,000.00 28,000.00
Jumlah 3,930,000.00
Overhead 10 % 393,000.00
Jumlah Total 4,323,000.00

018 1 M2 Pek. Gording Kelas II


Bahan
a kayu Kelas II m3 0.012 2,500,000.00 30,000.00
b Paku Kg 0.200 25,000.00 5,000.00
Tenaga
a.Tukang kayu Oh 0.100 100,000.00 10,000.00
b.Kepala Tukang Oh 0.010 120,000.00 1,200.00
c. Pekerja Oh 0.100 85,000.00 8,500.00
d.Mandor Oh 0.005 140,000.00 700.00
Jumlah 55,400.00
Overhead 10 % 5,540.00
Jumlah Total 60,940.00

019 1 M2 Pek. Atap Metal Roof


Bahan
a Metal Roof Lbr 1.3 75,000.00 97,500.00
b Paku Kg 0.02 25,000.00 500.00
Tenaga
a.Tukang kayu Oh 0.1 100,000.00 10,000.00
b.Kepala Tukang Oh 0.01 120,000.00 1,200.00
c. Pekerja Oh 0.20 85,000.00 17,000.00
d.Mandor Oh 0.001 140,000.00 140.00
Jumlah 126,340.00
Overhead 10 % 12,634.00
Jumlah Total 138,974.00
020 1 M2 Pek. Papan Kayu Kls II
Bahan
a Kayu Kls II Lbr 0.0 2,500,000.00 75,000.00
b Paku Kg 0.05 25,000.00 1,250.00
Tenaga
a.Tukang kayu Oh 0.100 100,000.00 10,000.00
b.Kepala Tukang Oh 0.005 120,000.00 600.00
c. Pekerja Oh 0.050 85,000.00 4,250.00
d.Mandor Oh 0.005 140,000.00 700.00
Jumlah 91,800.00
Overhead 10 % 9,180.00
Jumlah Total 100,980.00

021 1 M2 Pek. Huruf dari Plat Baja H 80 cm


Bahan
a Plat Baja Kg 35 55,000.00 1,925,000.00
b Kawat Las Kg 0.05 90,000.00 4,500.00
c Dudukan Huruf ls 1 75,000.00 75,000.00
d Finish Cat Minyak Kg 1 15,000.00 15,000.00
Tenaga
a.Tukang Besi Oh 0.1 100,000.00 10,000.00
b.Kepala Tukang Oh 0.005 120,000.00 600.00
c. Pekerja Oh 0.05 85,000.00 4,250.00
d.Mandor Oh 0.005 140,000.00 700.00
Jumlah 2,035,050.00
Overhead 10 % 203,505.00
Jumlah Total 2,238,555.00

022 1 M Pek. Pagar Hollow h 120 cm


Bahan
a Pagar besi m' 1 250,000.00 250,000.00
b Sement Portland Kg 25 1,300.00 32,500.00
c Pasir pasang m3 0.05 120,000.00 6,000.00
Tenaga
a.Pekerja Oh 0.1 85,000.00 8,500.00
b.Tukang Batu Oh 0.005 100,000.00 500.00
c. Kepala Tukang Oh 0.05 120,000.00 6,000.00
d.mandor Oh 0.005 140,000.00 700.00
Jumlah 304,200.00
Overhead 10 % 30,420.00
Jumlah Total 334,620.00
023 Pasangan 1 M2 L batu alam
Bahan
a Batu Alam Dos 1.1 350,000.00 385,000.00
b Semen Portland Kg 10 1,300.00 13,000.00
c Pasir Pasang M3 0.045 120,000.00 5,400.00
d Semen Warna Kg 1.5 1,500.00 2,250.00
Tenaga
a.Tukang Besi Oh 0.3 100,000.00 30,000.00
b.Kepala Tukang Oh 0.15 120,000.00 18,000.00
c. Pekerja Oh 0.015 85,000.00 1,275.00
d.Mandor Oh 0.015 140,000.00 2,100.00
Jumlah 457,025.00
Overhead 10 % 45,702.50
Jumlah Total 502,727.50

024 1 Buah Papan Informasi


Bahan
a Pintu Papan Informasi Bh 2 250,000.00 500,000.00
b Dinding Papan untuk Papan Informasi m2 4 75,000.00 300,000.00
Tenaga
a.Tukang Besi Oh 1 100,000.00 100,000.00
b.Kepala Tukang Oh 1 120,000.00 120,000.00
c. Pekerja Oh 0.015 85,000.00 1,275.00
d.Mandor Oh 0.00075 140,000.00 105.00
Jumlah 1,021,380.00
Overhead 10 % 102,138.00
Jumlah Total 1,123,518.00
HARGA BAHAN DAN UPAH

NO JENIS BAHAN SAT HARGA

1 Pasir Timbunan/Urug M3 120,000.00


2 Pasir Pasang M3 120,000.00
3 Pasir Beton M3 120,000.00
4 Batu belah/gunung M3 130,000.00
5 Batu Pecah (chipping) 2-3 M3 300,000.00
6 Bata Merah BH 650.00
7 PC (1 zak = 50 Kg) Kg 1,300.00
8 PC (1 zak = 40 Kg) warna Kg 1,500.00
9 Besi Beton Polos KG 4,500.00
10 Minyak Begisting LTR 10,000.00
11 Cat Dasar Tembok KG 18,000.00
12 Cat Kilap tembok Setara Vinilex KG 18,000.00
13 Plamir tembok KG 15,000.00
14 Kayu Kelas III ( Balok ) M3 1,800,000.00
15 Kayu Kelas II M3 2,500,000.00
16 Dolken Kayu Gelam dia. 8 - 10 cm / 4 m BTG 20,000.00
17 Multipleks t = 9 mm LBR 120,000.00
18 Paku 5 - 12 cm KG 25,000.00
19 Plat besi Kg 55,000.00
20 Pagar besi M 250,000.00
21 Kawat las Kg 90,000.00
22 Batu Alam Dos 350,000.00
23 Pintu Papan Informasi Bh 250,000.00
24 Dinding Papan untuk Papan Informasi M2 75,000.00
25 Metal Roof LBR 75,000.00
26 Dudukan Huruf ls 75,000.00
27 Minyak Cat KG 15,000.00
28 Kawat beton KG 20,000.00
29 Air LTR 150.00
NO JENIS PEKERJA SAT HARGA

1 Mandor ORG/HR 140,000.00


2 Kepala tukang ORG/HR 120,000.00
3 Tukang ORG/HR 100,000.00
4 Tukang kayu ORG/HR 100,000.00
5 Tukang batu ORG/HR 100,000.00
6 Tukang Cat ORG/HR 100,000.00
7 Tukang Listrik ORG/HR 100,000.00
8 Tukang Pipa ORG/HR 100,000.00
9 Tukang Besi ORG/HR 100,000.00
10 Pekerja ORG/HR 85,000.00
BULAN I BULAN II
NO URAIAN PEKERJAAN BBT MINGGU I MINGGU II MINGGU III MINGGU IV MINGGU V
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6

1 PEKERJAAN PERSIAPAN 7.54212 0.63 0.63 0.63 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6

2 PEKERJAAN TRACKING MANGROVE (226 m) 43.4889 0.66 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7

3 PEKERJAAN GAZEBO ( 5 buah; 2 m x 2 m) 8.2052

4 PEKERJAAN REST AREA (1 buah; 16 m x 4 m) 6.80301

5 PEKERJAAN KANTIN ( 1 buah; 6 m x 6 m) 6.23877

6 PEKERJAAN RUANG AULA (1 buah; 8 m x 12 m) 10.1238

7 PEKERJAAN GAPURA PINTU MASUK 7.09323

8 PAGAR HOLLOW DAN HURUF 9.56251

9 PEKERJAAN LAIN-LAIN 0.94243

JUMLAH 100 0.63 0.63 0.63 0.6 0.6 0.6 1.26 1.3 1.3 1.3 1.3 1.3 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7
JUMLAH AKUMULATIF 0.6 1.23 1.86 2.46 3.06 3.657 4.92 6.216 7.516 8.816 10.1 11.4 12 13 14 14 15 16 16 17 18 18 19 20 21 21 22 23 23 24
REALISASI JUMLAH
REALISASI KUMULATIF
DEVIASI(+/-)
JADWAL PELAKSANAAN KURVA "S"
PUSAT RESTORASI DAN PENGEMBANGAN EKOWISATA PESISIR (PRPEP)

BULAN II BULAN III


MINGGU VI MINGGU VII MINGGU VIII MINGGU IX MINGGU X MINGGU XI MINGGU XII
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6

0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7

0.68 0.7 0.7 0.7 0.7 0.7

0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 1.38 1.4 1.4 1.4 1.4 1.4
25 25 26 27 28 28 29 30 30 31 32 32 33 34 35 35 36 37 37 38 39 39 40.1 41 42 42 43 44 44 45 45.7 46 47 48 49 49 50.6 52 53 54.8 56.2 58
BULAN IV BULAN V
MINGGU XIII MINGGU XIV MINGGU XV MINGGU XVI MINGGU XV MINGGU XVI MINGGU XVII MINGGU XVIII
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6

0.7 0.7 0.7 0.7 0.7 0.7

0.6 0.6 0.6 0.6 0.6 0.6 0.6

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9

0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6

0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5

0.16 0.04 0.04 0.04 0.04 0.04

1.3 1.3 1.3 1.3 1.3 1.3 1.1 0.5 0.5 0.5 0.5 0.5 1.4 1.4 1.4 1.4 1.4 1.4 1.5 1.5 1.5 1.5 1.5 1.5 1.1 1.1 1.1 1.1 1.1 1.1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.16 0.04 0.04 0.04 0.04 0.04
59 60 61 63 64.1 65 66 67 67 68 68.5 69 70 72 73 75 76 77 79 80.4 81.9 83 85 86 88 89 90 91 92 93 94 94 95 95 95.5 96 97 97 98 98 99 99 99.2 99.21 99.2 99.3 99.3 100

Makassar, 31 Mei 2018


CV. ANDARA KARYA ABADI

SUFI BATARA TUNGKE


Direktur

Anda mungkin juga menyukai