KEGIATAN : CSR
PEKERJAAN : PEMBANGUNAN SERAMBI + PLAFOND + PENGECATAN DINDING MASJID DESA BETUNG
LOKASI : MASJID DESA BETUNG
NO URAIAN JUMLAH
JUMLAH 309,644,724.86
PPN 11 % 34,060,919.73
TOTAL 343,705,644.59
DIBULATKAN 343,705,000.00
TERBILANG : TIGA RATUS EMPAT PULUH TIGA JUTA TUJUH RATUS LIMA RIBU RUPIAH
KEGIATAN : CSR
PEKERJAAN : PEMBANGUNAN SERAMBI + PLAFOND + PENGECATAN DINDING MASJID DESA BETUNG
LOKASI : MASJID DESA BETUNG
HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
2 Pemasangan Bowplank 1.00 Ls 750,000.00 750,000.00
3 Air Kerja dan Listrik Kerja 1.00 Ls 500,000.00 500,000.00
JUMLAH I 2,250,000.00
II PEKERJAAN PONDASI
1 Galian Pondasi Batu Kali 21.18 m3 89,100.00 1,887,138.00
2 Urugan Pasir Bawah Batu Kali, t=5 cm 2.12 m3 184,360.00 390,474.48
3 Urugan Tanah Kembali 3.65 m3 49,280.00 179,970.56
4 Pondasi Menerus Pas Batu, Camp 1:4 30.83 m3 862,824.29 26,596,558.61
5 Urugan Tanah Peninggian Lantai dan Isi sisi pondasi 77.52 m3 126,720.00 9,822,700.80
6 Urugan Pasir Bawah Lantai, t=5 cm 7.75 m3 184,360.00 1,429,066.54
JUMLAH II 40,305,908.99
III PEKERJAAN STRUKTUR
1 Sloof 15/20 Beton fc' 9,8 Mpa
a. Beton fc 9,8 Mpa 2.06 m3 938,063.19 1,927,719.86
b. Bekisting Mulitipleks 27.40 m2 143,731.50 3,938,243.10
c. Pembesian Polos D12 (Tul. Pokok) 262.49 kg 17,140.20 4,499,179.09
d. Pembesian Polos D10 (Tul. Sengkang) 98.53 kg 17,140.20 1,688,830.76
2 Kolom 20/20 Beton fc' 9,8 Mpa
a. Beton fc' 9,8 Mpa 2.77 m3 938,063.19 2,600,311.17
b. Bekisting Mulitipleks 55.44 m2 154,152.63 8,546,221.53
c. Pembesian Polos D12 (Tul. Pokok) 246.71 kg 17,140.20 4,228,624.46
d. Pembesian Polos D10 (Tul. Sengkang) 99.68 kg 17,140.20 1,708,554.33
3 Plat Lantai, t=8 cm, fc' 9,8 Mpa
a. Beton fc' 9,8 Mpa 12.40 m3 938,063.19 11,634,234.93
b. Plastik Cor 155.03 m2 3,000.00 465,090.00
4 Ringbalk R1 15/20, Beton fc' 9,8 Mpa
a. Beton fc' 9,8 Mpa 2.06 m3 938,063.19 1,927,719.86
b. Bekisting Mulitipleks 27.40 m2 143,731.50 3,938,243.10
c. Pembesian Polos D12 (Tul. Pokok) 266.04 kg 17,140.20 4,560,061.08
d. Pembesian Polos D10 (Tul. Sengkang) 98.53 kg 17,140.20 1,688,830.76
5 Balok Praktis Fasad 15/15, Beton fc' 9,8 Mpa
a. Beton fc' 9,8 Mpa 1.86 m3 938,063.19 1,748,878.11
b. Bekisting Mulitipleks 24.86 m2 143,731.50 3,572,877.63
c. Pembesian Polos D12 (Tul. Pokok) 313.50 kg 17,140.20 5,373,444.47
d. Pembesian Polos D10 (Tul. Sengkang) 119.19 kg 17,140.20 2,042,868.86
JUMLAH III 66,089,933.11
IV PEKERJAAN DINDING/ PASANGAN
1 Pas. Dinding 1/2 Bata Camp 1:4 62.19 m2 252,206.35 15,684,965.11
2 Plesteran Camp 1:4 124.38 m2 70,791.60 8,805,200.79
3 Acian 124.38 m2 41,923.75 5,214,559.87
4 Cat-catan Interior 332.28 m2 37,567.00 12,482,837.89
5 Cat-catan Eksterior 332.28 m2 52,300.60 17,378,547.97
6 Keramik 30x30 (Unpolished) 155.03 m2 63,039.90 9,773,075.70
7 Roster Beton Minimalis Motif 30x30x10 428.04 bh 16,000.00 6,848,640.00
JUMLAH IV 76,187,827.34
V PEKERJAAN ATAP/ PENGGANTUNG
1 Plafond PVC Shunda (Rangka + Pemasangan) 252.03 m2 250,000.00 63,007,500.00
2 Kasau & Reng Baja Ringan Atap 118.00 m2 105,000.00 12,390,000.00
3 Kuda-Kuda Baja Ringan 33.20 m2 145,000.00 4,814,000.00
4 Penutup Atap Multi Roof 155.03 m2 129,514.00 20,078,555.42
5 Nok Atap Multiroof 13.60 m' 70,000.00 952,000.00
6 Talang Air PVC Segi Empat 68.50 m' 90,000.00 6,165,000.00
7 Pipa PVC 4'' (Termasuk Aksesoris) Type AW 59.20 m' 95,000.00 5,624,000.00
JUMLAH V 113,031,055.42
VI PEKERJAAN ELEKTRIKAL
1 Instalasi Listrik
a. Instalasi Stop Kontak 8.00 titik 185,000.00 1,480,000.00
b. Instalasi Lampu LED 18 Watt 18.00 titik 130,000.00 2,340,000.00
c. Instalasi Saklar 8.00 titik 165,000.00 1,320,000.00
2 Instalasi Lampu Hias Gantung 1.00 unit 4,500,000.00 4,500,000.00
3 Saklar Tunggal 4.00 unit 45,000.00 180,000.00
4 Saklar Ganda 4.00 unit 65,000.00 260,000.00
5 Stop Kontak 8.00 unit 55,000.00 440,000.00
6 Lampu LED 18 Watt 18.00 bh 70,000.00 1,260,000.00
JUMLAH VI 11,780,000.00
Selaru, 01 April 2022
Total = 262.49 kg
d. Pembesian Polos D10 (Tul. Sengkang) Diameter Berat/m Panjang Jmlh tul Volume Satuan
As - 1 Tul.sengkang Ø10-300 0.62 x 0.60 x 70.33 = 26.16 kg
bengkokan Ø10 x 2 0.62 x 0.10 x 70.33 = 4.19 kg
Total = 98.53 kg
2 Kolom 20/20 Beton fc' 9,8 Mpa
c. Pembesian Polos D12 (Tul. Pokok) Diameter Berat/m Panjang Jmlh tul Jmlh kolom Volume Satuan
0.00-4.00 Tul.utama 4Ø12 0.89 x 3.85 x 4.00 x 18.00 = 246.71 kg
sengkang Ø10-300 0.62 x 0.60 x 12.83 x 18.00 = 85.93 kg
bengkokan sengkang Ø10 x 2 0.62 x 0.10 x 12.83 x 18.00 = 13.75 kg
Jumlah Tul. Sengkang = 99.68 kg
Total = 346.39 kg
Total = 266.04 kg
d. Pembesian Polos D10 (Tul. Sengkang) Diameter Berat/m Panjang Jmlh tul Volume Satuan
As - 1 Tul.sengkang Ø10-300 0.62 x 0.60 x 70.33 = 26.16 kg
bengkokan Ø10 x 2 0.62 x 0.10 x 70.33 = 4.19 kg
Total = 98.53 kg
Total = 313.50 kg
d. Pembesian Polos D10 (Tul. Sengkang) Diameter Berat/m Panjang Jmlh tul Volume Satuan
As - 1 Tul.sengkang Ø10-300 0.62 x 0.60 x 82.00 = 30.50 kg
bengkokan Ø10 x 2 0.62 x 0.10 x 82.00 = 4.88 kg
Total = 119.19 kg
I PEKERJAAN PERSIAPAN
1 Galian Pondasi Batu Kali Panjang Lebar Tinggi Jumlah Volume Satuan
70.60 x 0.60 x 0.50 x 1.00 = 21.18 m3
Total = 21.18 m3
2 Urugan Pasir Bawah Batu Kali, t=5 cm Panjang Lebar Tinggi Jumlah Volume Satuan
70.60 x 0.60 x 0.05 x 1.00 = 2.12 m3
Total = 2.12 m3
Total = 3.65 m3
4 Pondasi Menerus Pas Batu, Camp 1:4 Panjang lbr atas lbr bawah Tinggi Volume Satuan
As 1 21.10 x 0.30 + 0.60 x 1.00 = 9.50 m3
As 2 21.20 x 0.30 + 0.60 x 1.00 = 9.54 m3
Total = 30.83 m3
5 Urugan Tanah Peninggian Lantai dan Isi sisi pondasi Area Tinggi Volume Satuan
155.03 x 0.5 = 77.52 m3
Total = 77.52 m3
Total = 7.75 m3
III PEKERJAAN STRUKTUR
Total = 2.06 m3
Total = 27.40 m2
2 Kolom 20/20 Beton fc' 9,8 Mpa Panjang Lebar Tinggi Jumlah Volume Satuan
a. Beton fc' 9,8 Mpa 0.2 x 0.2 x 3.85 x 18.00 = 2.77 m3
Total = 2.77 m3
Total = 55.44 m2
Total = 12.40 m3
Total = 155.03 m2
Total = 2.06 m3
Total = 1.86 m3
Total = 24.86 m2
IV PEKERJAAN DINDING/ PASANGAN
1 Pas. Dinding 1/2 Bata Camp 1:4 Panjang Tinggi Volume Satuan
Total = 62.19 m2
Total = 124.382 m2
3 Acian
Panjang Tinggi Sisi Volume Satuan
As 1 20.00 x 0.85 x 2.00 = 34.00 m2
As 2 20.00 x 0.85 x 2.00 = 34.00 m2
Total = 124.382 m2
4 Cat-catan Interior
Panjang Tinggi Sisi Volume Satuan
As 1 20.00 x 0.85 x 2.00 = 34.00 m2
As 2 20.00 x 0.85 x 2.00 = 34.00 m2
Total = 332.282 m2
5 Cat-catan Eksterior
Panjang Tinggi Sisi Volume Satuan
As 1 20.00 x 0.85 x 2.00 = 34.00 m2
As 2 20.00 x 0.85 x 2.00 = 34.00 m2
Total = 332.282 m2
Total = 155.03 m2
Total = 428.04 bh
V PEKERJAAN ATAP/ PENGGANTUNG
2 Kasau & Reng Baja Ringan Atap Panjang Lebar Jumlah Volume Satuan
Depan belakang 23.00 x 2.2 x 1.00 = 50.60 m2
Kiri kanan 17.00 x 2.2 x 1.00 = 37.40 m2
5.00 x 6.0 x 1.00 = 30.00 m2
total = 118.00 m2
total = 155.03 m2
7 Pipa PVC 4'' (Termasuk Aksesoris) Type AW Panjang Jumlah Volume Satuan
3.70 x 16.00 59.2 m'
1 Instalasi Listrik
a. Instalasi Stop Kontak Jumlah Volume Satuan
Lampu LED 18.00 = 18.00 titik
Stop kontak 8.00 = 8.00 titik
Saklar 8.00 = 8.00 titik
Pengurugan Kembali 1 m3 Galian Dihitung dari 1/3 kali Koefisien Pekerjaan Galian
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 Rp. 100,000.00 Rp. 40,000.00
Tukang L.02 OH - Rp. 110,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 120,000.00 Rp -
Mandor L.04 OH 0.040 Rp. 120,000.00 Rp. 4,800.00
Jumlah Tenaga Kerja (A) Rp. 44,800.00
B BAHAN
Analisa : A. 4.5.2.32
Item : Pek. Atap Galvalum
Satuan : m2
Analisa :
Item : Pemasangan 1 m2 paving blok
Satuan : m2