WAKTU PELAKSANAAN / TIME SCHEDUL

PEKERJAAN : PEMBANGUNAN PINTU AIR SETTLING POND

LOKASI : PIT STC

PELAKSANA : CV. ZAHRA PRATAMA

THN ANGGARAN : 2021

WAKTU PELAKSANAAN 15 (LIMA BELAS) HARI KERJA


TOTAL HARGA BOBOT
NO. URAIAN PEKERJAAN KET.
( Rp ) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

100
A. PEKERJAAN PERSIAPAN 13,941,800.00 16.65 16.65

80
B. PEKERJAAN TANAH 19,663,800.00 23.48 11.74 11.74
60
C. PEKERJAAN BETON BERTULANG 21,703,528.00 25.92 4.32 4.32 4.32 4.32 4.32 4.32
40
D. PEKERJAAN PINTU AIR 16,642,800.00 19.87 9.94 9.94
20
E. PEKERJAAN DINDING PENAHAN TANAH & PAS. BATU KOSONG 11,786,400.00 14.08 3.52 3.52 3.52 3.52
0

TOTAL 83,738,328.00 100.00

RENCANA PROGRES (%) 16.65 11.74 11.74 4.32 4.32 4.32 4.32 4.32 4.32 9.94 9.94 3.52 3.52 3.52 3.52

RENCANA AKUMULATIF (%) 16.65 28.39 40.13 44.45 48.77 53.09 57.41 61.73 66.05 75.99 85.92 89.44 92.96 96.48 100.00

N/B :
- Time Schedul ini untuk kegiatan 1 (satu) unit pembangunan pintu air settling pond Kota Baru, 03 September 2021
CV. ZAHRA PRATAMA

Wardana Kesuma, ST
Direktur