Anda di halaman 1dari 7

REKAPITULASI

KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN POS SECURITY @8 UNIT
LOKASI : HAULING ROAD PT. SSC

NO URAIAN JUMLAH

1 PEKERJAAN STRUKTUR RANGKA BAJA RINGAN 5,103,000.00


2 PEKERJAAN LANTAI 260,000.00
3 PEKERJAAN ARSITEKTUR 110,000.00
4 PEKERJAAN ATAP 1,595,000.00
5 UPAH PEKERJA PHL 4,932,000.00

JUMLAH @1 UNIT 12,000,000.00


JUMLAH @8 UNIT 96,000,000.00
TOTAL 96,000,000.00
DIBULATKAN 96,000,000.00
TERBILANG : SERATUS SATU JUTA SEMBILAN RATUS DELAPAN PULUH EMPAT RIBU RUPIAH

Kotabaru, 29 April 2022

Dibuat Oleh, Diketahui Oleh,

   

Ach Nizar Fauzi Alfun Ni'am


Engineer Prodev Manajer Prodev

Disetujui Oleh, Disetujui Oleh,

   

Luhut H. T Siregar Rendy Teguh M.


KTT PT. SSC Head of Site
REKAPITULASI

KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN PORTAL @9 UNIT
LOKASI : HAULING ROAD PT. SSC

NO URAIAN JUMLAH

1 PEKERJAAN STRUKTUR RANGKA PORTAL DAN AKSESOR 3,533,000.00


2 PEKERJAAN PONDASI 1,233,055.61
3 UPAH PEKERJA PHL 2,192,000.00

JUMLAH @1 UNIT 6,958,055.61


JUMLAH @9 UNIT 62,622,500.52
TOTAL 62,622,500.52
DIBULATKAN 62,622,000.00
TERBILANG : TUJUH PULUH JUTA DUA RATUS SEMBILAN RIBU RUPIAH

Kotabaru, 29 April 2022

Dibuat Oleh, Diketahui Oleh,

   

Alfun Ni'am
Ach Nizar Fauzi Manajer Prodev
Engineer Prodev

Disetujui Oleh, Disetujui Oleh,

   

Luhut H. T Siregar Rendy Teguh M.


KTT PT. SSC Head of Site
RENCANA ANGGARAN BIAYA
(RAB)

KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN POS SECURITY @1UNIT
LOKASI : HAULING ROAD PT. SSC

HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN

1 2 3 4 5 6
I PEKERJAAN STRUKTUR RANGKA BAJA RINGAN
1 Kolom, Balok & rangka dinding serta suai baja ringan C75.35.0,75 20.00 Btg 110,000.00 2,200,000.00
2 Dinding seng galvalum 0.8 m x 1.8 m tebal 0.20 mm 7.00 Lbr 85,000.00 595,000.00
3 Dinding kawat harmonika pvc tinggi 1 m 8.00 m2 70,000.00 560,000.00
4 Baut taso atap pakai karet 12 - 24 x 40 mm 1.00 Box 215,000.00 215,000.00
5 Baut taso putih 4.8 x 16 mm 1.00 Box 215,000.00 215,000.00
6 Baut lantai sekrub 3 cm 1.00 Box 150,000.00 150,000.00
7 Kuas cat 3'' 1.00 Bh 8,000.00 8,000.00
8 Cat minyak thiner A 1.00 Ltr 40,000.00 40,000.00
9 Cat zinc chromate 1.00 Ltr 65,000.00 65,000.00
10 Cat besi avian hitam I kg 1.00 Kg 65,000.00 65,000.00
11 Pipa Besi Hitam 3" 1.00 Btg 365,000.00 365,000.00
12 LIP Channel 120.60.20.3,2 1.00 Btg 475,000.00 475,000.00
13 Kawat Las Nikko Steel 1.00 Box 150,000.00 150,000.00
JUMLAH I 5,103,000.00
II PEKERJAAN LANTAI
1 Multipleks 12 mm 2.44 x 1.12 1.00 Lbr 150,000.00 150,000.00
2 Balok rangka baja ringan C75.35.0,75 1.00 Btg 110,000.00 110,000.00
JUMLAH II 260,000.00
III PEKERJAAN ARSITEKTUR
1 Balok rangka baja ringan C75.35.0,75 1.00 Btg 110,000.00 110,000.00
JUMLAH III 110,000.00
IV PEKERJAAN ATAP
1 Kuda-Kuda baja ringan C75.35.0,75 8.00 Btg 110,000.00 880,000.00
2 Reng taso R. 40.45 4.00 Btg 60,000.00 240,000.00
3 Atap seng galvalum 0.8 m x 1.8 m tebal 0.20 mm 4.00 Lbr 70,000.00 280,000.00
4 Nok Atap Seng plat talang Pemuung/ Wulung 60 cm tebal 0.30 mm 3.00 m 65,000.00 195,000.00
JUMLAH IV 1,595,000.00
V UPAH PEKERJA PHL
1 Upah Pekerja PHL 6 orang (Target 6 hari) 36.00 OH 137,000.00 4,932,000.00
JUMLAH V 4,932,000.00
RENCANA ANGGARAN BIAYA
(RAB)

KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN PORTAL @1 UNIT
LOKASI : HAULING ROAD PT. SSC

HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN

1 2 3 4 5 6
I PEKERJAAN STRUKTUR RANGKA PORTAL DAN AKSESORIS
1 Kuas cat 3'' 1.00 Bh 8,000.00 8,000.00
2 Cat minyak thiner A 1.00 Ltr 40,000.00 40,000.00
3 Cat zinc chromate 1.00 Ltr 65,000.00 65,000.00
4 Cat besi avian hitam I kg 1.00 Kg 65,000.00 65,000.00
5 Cat meni avian I kg 1.00 Kg 50,000.00 50,000.00
6 Cat besi avian kuning I kg 1.00 Kg 75,000.00 75,000.00
7 Pipa Besi Hitam 3" 4.00 Btg 365,000.00 1,460,000.00
8 Pipa Besi Hitam 2" 3.00 Btg 285,000.00 855,000.00
9 Besi Plat Strip 3 mm 1.00 Btg 60,000.00 60,000.00
10 Engsel Roller Besi 2" 1.00 Bh 100,000.00 100,000.00
11 Bantalan Karet Bekas 1.00 Bh 100,000.00 100,000.00
12 Tali Tampar 1.00 Roll 350,000.00 350,000.00
13 Kawat Las Nikko Steel 1.00 Dus 150,000.00 150,000.00
14 Dempul Besi 1.00 Bh 110,000.00 110,000.00
14 Mata Gerinda Poles 1.00 Bh 20,000.00 20,000.00
15 Amplas Gosok 1.00 Roll 25,000.00 25,000.00
JUMLAH I 3,533,000.00
II PEKERJAAN PONDASI
1 Beton Camp 1Pc:2Psr:3Krl 0.85 m3 938,063.19 797,353.71
2 Bekisting Multipleks Beton Pracetak 2.60 m2 143,731.50 373,701.90
3 Kaso 4/6 (include Paku) 1.00 btg 45,000.00 45,000.00
4 Plastik Cor 1.00 m2 3,000.00 3,000.00
5 Ember Cor 2.00 bh 7,000.00 14,000.00
JUMLAH II 1,233,055.61
III UPAH PEKERJA PHL
1 Upah Pekerja PHL 4 orang (Target 4 hari) 16.00 OH 137,000.00 2,192,000.00
JUMLAH III 2,192,000.00
II PEKERJAAN PONDASI

1 Tiang, balok, dinding Panjang Lebar Tinggi Jumlah Volume Satuan


Tiang Utama 3.00 x 1.00 x 1.00 x 8.00 = 24.00 m'
balok dan suai 3.00 x 1.00 x 1.00 x 4.00 = 12.00 m'
suai dinding 1.25 x 1.00 x 1.00 x 32.00 = 43.00 m'
balok dinding 9.00 x 1.00 x 1.00 x 4.00 = 36.00 m'
Total = 115.00 m'
= 19.166667 btg

2 Rangka Atap Panjang Lebar Tinggi Jumlah Volume Satuan


Kuda-kuda 9.17 x 1.00 x 1.00 x 3.00 = 27.51 m'
reng 1 2.70 x 1.00 x 1.00 x 6.00 = 16.20 m'
reng 2 0.85 x 1.00 x 1.00 x 6.00 = 5.10 m'
canopy 6.17 x 1.00 x 1.00 x 3.00 = 18.51 m'
reng canopy 1.50 x 1.00 x 1.00 x 2.00 = 3.00 m'
Total = 70.32 m'
kuda2 = 7.67 btg
reng = 4.05 btg

3 Galvalum atap Panjang Lebar Tinggi Jumlah Volume Satuan


2.7 0.9 1 2 = 4.86 m2
1.5 0.6 1 = 0.9 m2

total 5.76 m2
4 lbr

4 Lantai Panjang Lebar Tinggi Jumlah Volume Satuan


Multipleks 1.5 1.5 = 2.25 m2
Balok 6 = 6 m
total 0.8233314 lbr

5 Dinding Panjang Lebar Tinggi Jumlah Volume Satuan


Kawat 1.5 1.3 4 7.8 m2
Galvalum 1.64 1.5 4 9.84 m2

6.8333333 lbr

6 Kursi Panjang Lebar Tinggi Jumlah Volume Satuan


3 3 m'
4.5 4.5 m'
4.2 4.2 m'
11.7
1.95
II PEKERJAAN PONDASI

1 Panjang Lebar Tinggi Jumlah Volume Satuan


Besi 3" 21.00 21.00
Besi 2" 19.73 19.73

3.50
3.29
2 Beton 0.4 0.4 0.4 2 0.128

3 Pemberat 1.00 0.80 0.80 0.64

4 Bekisting 0.90 0.70 2.52 m2


BILL OF QUANTITY
KEGIATAN : HSE
PEKERJAAN : PEMBANGUNAN FASILITAS NURSERY BARU
LOKASI : NURSERY KM 07+200 PT. STC

HARGA (RP)
NO DESKRIPSI VOLUME SAT
SATUAN TOTAL

1 RUMAH TAWAS SETLINGPOUD


1.1 BAHAN MATERIAL & PEKERJAAN RANGKA BAJA
Tiang, Balok & rangka dinding serta suai baja ringan C75 30 Btg Rp. 105,000.00 Rp. 3,150,000.00
Dinding seng galvalum 0.8 x 1.8 tebal 0.20 mm 24 Lbr Rp. 65,000.00 Rp. 1,560,000.00
Baut taso atap pakai karet 12 - 24 x 40 mm 1 Ktk Rp. 215,000.00 Rp. 215,000.00
Baut taso putih 4.8 x 16 mm 2 Ktk Rp. 215,000.00 Rp. 430,000.00
Baut lantai sekrub 3 cm 1 Ktk Rp. 150,000.00 Rp. 150,000.00
Kuas cat 3'' Inc 2 Bh Rp. 8,000.00 Rp. 16,000.00
Cat minyak thiner A 2 Ltr Rp. 40,000.00 Rp. 80,000.00
Cat zinkcromat 1 Ltr Rp. 65,000.00 Rp. 65,000.00
Cat besi avian hitam I kg 2 Kg Rp. 65,000.00 Rp. 130,000.00
Rp. 5,796,000.00
1.2 PEKERJAAN LANTAI
Multiplek 12 mm 3 Lbr Rp. 150,000.00 Rp. 450,000.00
Rangka tulangan lantai baja ringan 75x75 5 Btg Rp. 105,000.00 Rp. 525,000.00
Rp. 975,000.00
1.3 PEKERJAAN PINTU
Rangka pintu baja ringan 75x75 3 Btg Rp. 105,000.00 Rp. 315,000.00
Daun pintu seng galvalum biru 2 Lbr Rp. 65,000.00 Rp. 130,000.00
Engsel pintu kupu kupu 3" x 2.5" x 2.5mm 2 Pcs Rp. 25,000.00 Rp. 50,000.00
Grendel geser 1 Pcs Rp. 25,000.00 Rp. 25,000.00
Gembok pintu 1 Pcs Rp. 25,000.00 Rp. 25,000.00
Rp. 545,000.00
1.4 PEKERJAAN ATAP
Kuda kuda baja ringan C75 5 Btg Rp. 105,000.00 Rp. 525,000.00
Ring taso R45 10 Btg Rp. 50,000.00 Rp. 500,000.00
Atap seng zinc galvalum biru 0.8 x 1.8 tebal 0.20 mm 15 Lbr Rp. 65,000.00 Rp. 975,000.00
Seng plat talang Pemuung/ Wulung 60 cm tebal 0.30 mm 3 M Rp. 65,000.00 Rp. 195,000.00
Rp. 2,195,000.00
1.5 PEKERJAAN VENTILASI
Kawat harmonika PVC Tinggi = 1m 7 M Rp. 85,000 Rp 595,000
Rp. 595,000
1.6 UPAH PEKERJA
Upah PHL ( 2 orang target kerja 15 hari ) 30 HOK Rp. 137,000 Rp. 4,110,000
Rp. 4,110,000

Total Pembulatan 14,216,000

Dibuat Oleh, Diperiksa Oleh, Diketahui Oleh,

Edward Heriady Djeki Sulistiawan Cornelius Adi T.


Drafter Spv Prodev Dept Head Prodev

Anda mungkin juga menyukai