KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN POS SECURITY @8 UNIT
LOKASI : HAULING ROAD PT. SSC
NO URAIAN JUMLAH
KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN PORTAL @9 UNIT
LOKASI : HAULING ROAD PT. SSC
NO URAIAN JUMLAH
Alfun Ni'am
Ach Nizar Fauzi Manajer Prodev
Engineer Prodev
KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN POS SECURITY @1UNIT
LOKASI : HAULING ROAD PT. SSC
HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN
1 2 3 4 5 6
I PEKERJAAN STRUKTUR RANGKA BAJA RINGAN
1 Kolom, Balok & rangka dinding serta suai baja ringan C75.35.0,75 20.00 Btg 110,000.00 2,200,000.00
2 Dinding seng galvalum 0.8 m x 1.8 m tebal 0.20 mm 7.00 Lbr 85,000.00 595,000.00
3 Dinding kawat harmonika pvc tinggi 1 m 8.00 m2 70,000.00 560,000.00
4 Baut taso atap pakai karet 12 - 24 x 40 mm 1.00 Box 215,000.00 215,000.00
5 Baut taso putih 4.8 x 16 mm 1.00 Box 215,000.00 215,000.00
6 Baut lantai sekrub 3 cm 1.00 Box 150,000.00 150,000.00
7 Kuas cat 3'' 1.00 Bh 8,000.00 8,000.00
8 Cat minyak thiner A 1.00 Ltr 40,000.00 40,000.00
9 Cat zinc chromate 1.00 Ltr 65,000.00 65,000.00
10 Cat besi avian hitam I kg 1.00 Kg 65,000.00 65,000.00
11 Pipa Besi Hitam 3" 1.00 Btg 365,000.00 365,000.00
12 LIP Channel 120.60.20.3,2 1.00 Btg 475,000.00 475,000.00
13 Kawat Las Nikko Steel 1.00 Box 150,000.00 150,000.00
JUMLAH I 5,103,000.00
II PEKERJAAN LANTAI
1 Multipleks 12 mm 2.44 x 1.12 1.00 Lbr 150,000.00 150,000.00
2 Balok rangka baja ringan C75.35.0,75 1.00 Btg 110,000.00 110,000.00
JUMLAH II 260,000.00
III PEKERJAAN ARSITEKTUR
1 Balok rangka baja ringan C75.35.0,75 1.00 Btg 110,000.00 110,000.00
JUMLAH III 110,000.00
IV PEKERJAAN ATAP
1 Kuda-Kuda baja ringan C75.35.0,75 8.00 Btg 110,000.00 880,000.00
2 Reng taso R. 40.45 4.00 Btg 60,000.00 240,000.00
3 Atap seng galvalum 0.8 m x 1.8 m tebal 0.20 mm 4.00 Lbr 70,000.00 280,000.00
4 Nok Atap Seng plat talang Pemuung/ Wulung 60 cm tebal 0.30 mm 3.00 m 65,000.00 195,000.00
JUMLAH IV 1,595,000.00
V UPAH PEKERJA PHL
1 Upah Pekerja PHL 6 orang (Target 6 hari) 36.00 OH 137,000.00 4,932,000.00
JUMLAH V 4,932,000.00
RENCANA ANGGARAN BIAYA
(RAB)
KEGIATAN : PENGAMANAN
PEKERJAAN : PEMBANGUNAN PORTAL @1 UNIT
LOKASI : HAULING ROAD PT. SSC
HARGA
NO URAIAN PEKERJAAN VOLUME SATUAN JUMLAH
SATUAN
1 2 3 4 5 6
I PEKERJAAN STRUKTUR RANGKA PORTAL DAN AKSESORIS
1 Kuas cat 3'' 1.00 Bh 8,000.00 8,000.00
2 Cat minyak thiner A 1.00 Ltr 40,000.00 40,000.00
3 Cat zinc chromate 1.00 Ltr 65,000.00 65,000.00
4 Cat besi avian hitam I kg 1.00 Kg 65,000.00 65,000.00
5 Cat meni avian I kg 1.00 Kg 50,000.00 50,000.00
6 Cat besi avian kuning I kg 1.00 Kg 75,000.00 75,000.00
7 Pipa Besi Hitam 3" 4.00 Btg 365,000.00 1,460,000.00
8 Pipa Besi Hitam 2" 3.00 Btg 285,000.00 855,000.00
9 Besi Plat Strip 3 mm 1.00 Btg 60,000.00 60,000.00
10 Engsel Roller Besi 2" 1.00 Bh 100,000.00 100,000.00
11 Bantalan Karet Bekas 1.00 Bh 100,000.00 100,000.00
12 Tali Tampar 1.00 Roll 350,000.00 350,000.00
13 Kawat Las Nikko Steel 1.00 Dus 150,000.00 150,000.00
14 Dempul Besi 1.00 Bh 110,000.00 110,000.00
14 Mata Gerinda Poles 1.00 Bh 20,000.00 20,000.00
15 Amplas Gosok 1.00 Roll 25,000.00 25,000.00
JUMLAH I 3,533,000.00
II PEKERJAAN PONDASI
1 Beton Camp 1Pc:2Psr:3Krl 0.85 m3 938,063.19 797,353.71
2 Bekisting Multipleks Beton Pracetak 2.60 m2 143,731.50 373,701.90
3 Kaso 4/6 (include Paku) 1.00 btg 45,000.00 45,000.00
4 Plastik Cor 1.00 m2 3,000.00 3,000.00
5 Ember Cor 2.00 bh 7,000.00 14,000.00
JUMLAH II 1,233,055.61
III UPAH PEKERJA PHL
1 Upah Pekerja PHL 4 orang (Target 4 hari) 16.00 OH 137,000.00 2,192,000.00
JUMLAH III 2,192,000.00
II PEKERJAAN PONDASI
total 5.76 m2
4 lbr
6.8333333 lbr
3.50
3.29
2 Beton 0.4 0.4 0.4 2 0.128
HARGA (RP)
NO DESKRIPSI VOLUME SAT
SATUAN TOTAL