REKAPITULASI DAFTAR KUANTITAS DAN HARGA

PEKERJAAN PERENCANAAN PEMAGARAN DAN URUGAN SPBUN PTGM LUMPUR


LOKASI : LUMPUR, GRESIK
TAHUN : 2022

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp.)

A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN 8,500,000.00
TOTAL A 8,500,000.00

B PEKERJAAN BANGUNAN
I PEKERJAAN TANAH 62,471,354.00
II PEKERJAAN BETON 54,786,704.45
III PEKERJAAN PASANGAN 147,793,237.19
IV PEKERJAAN PENGECATAN 7,409,835.29
TOTAL B 272,461,130.93
C ALOKASI BIAYA RK3K
I ALOKASI BIAYA RK3K 6,417,030.00
TOTAL C 6,417,030.00

JUMLAH 287,378,160.93
PPN 11 % 31,611,597.70
TOTAL 318,989,758.64
Terbilang : ( Tiga ratus delapan belas juta sembilan ratus delapan puluh sembilan ribu tujuh ratus lima puluh delapan rupiah enam puluh sembilan sen )

Dibuat Oleh,
Konsultan Perencana
CV. MARGI UTAMA KONSULTAN

Mengetahui

NURUL SHOFIYATI, S.Sos


Direktur
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN PERENCANAAN PEMAGARAN DAN PENGURUGAN SPBUN PTGM LUMPUR
LOKASI : LUMPUR, GRESIK
TAHUN : 2023

HARGA SATUAN JUMLAH


NO. URAIAN PEKERJAAN SATUAN VOLUME
( Rp. ) ( Rp. )
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN
1 Uitzet/Pengukuran Ls. 1.00 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi Awal dan Akhir Ls. 1.00 1,000,000.00 1,000,000.00
3 Mobilisasi dan Demobilisasi Ls. 1.00 6,500,000.00 6,500,000.00
Sub Total 8,500,000.00
TOTAL A 8,500,000.00
B PEKERJAAN BANGUNAN
I PEKERJAAN TANAH
1 Bor Strouss diameter 20cm m1 43.50 76,395.00 3,323,182.50
2 Galian Tanah Biasa sedalam 1 meter m³ 6.72 122,375.00 822,360.00
3 Urugan Tanah Kembali m³ 2.24 90,750.00 203,280.00
4 Urugan Tanah Dengan Sirtu m³ 213.43 164,175.00 35,039,459.81
5 Pasir Urug Tebal 10cm m³ 5.80 121,550.00 704,990.00
6 Pemadatan Tanah Urug dengan Vibro Roller m² 900.16 24,860.12 22,378,081.69
Sub Total 62,471,354.00
II PEKERJAAN BETON
1 Strouss diameter 30cm 1,5 meter m³ 3.07 3,785,960.81 11,635,298.71
2 Poerplat 60.60.20cm m³ 2.09 4,546,948.10 9,494,027.64
3 Sloof 15/20cm m³ 1.60 4,735,112.56 7,571,444.98
4 Kolom 15/15cm m³ 2.45 6,765,943.63 16,555,418.33
5 Ringbalok 15/20cm m³ 1.52 6,253,618.63 9,530,514.80
Sub Total 54,786,704.45
III PEKERJAAN PASANGAN
1 Pasang Batu Belah 1SP : 4PP m³ 66.33 931,865.00 61,810,993.73
2 Pasang Dinding Bata Ringan tb. 10cm + Mortar m² 125.26 221,038.79 27,686,213.02
3 Plesteran 1SP : 5PP m² 250.51 45,388.75 11,370,335.76
4 Acian m² 250.51 55,137.50 13,812,495.13
5 Pekerjaan Benangan Sudut m1 638.20 16,365.80 10,444,653.56
6 Pekerjaan Pasangan Paving Block tebal 6cm Natural m² 58.00 207,207.00 12,018,006.00
Pekerjaan Pasangan Kanstine 10x20x40 m1 23.20 132,825.00 3,081,540.00
7 Cover Beton Pengaman 100x120x17cm Gandar 20 Ton Pcs 5.00 1,513,800.00 7,569,000.00
Sub Total 147,793,237.19
IV PEKERJAAN PENGECATAN
1 Pengecatan Dindng Baru m² 250.51 29,579.00 7,409,835.29
Sub Total 7,409,835.29
TOTAL B 272,461,130.93
C ALOKASI BIAYA RK3K
I ALOKASI BIAYA RK3K
1 Pembuatan Kartu Identitas Pekerja Buah 5.00 15,000.00 75,000.00
2 Spanduk Keselamatam dan Kesehatan Kerja (K3) Buah 1.00 150,000.00 150,000.00
3 Pembatas Area (Safety Line) Buah 1.00 100,000.00 100,000.00
4 Helm Proyek Buah 5.00 70,000.00 350,000.00
5 Rompi Keselamatan Baru Buah 5.00 30,000.00 150,000.00
6 Sepatu Kerja Pasang 5.00 100,000.00 500,000.00
7 Masker Box 1.00 20,000.00 20,000.00
8 Asuransi konstruksi Ls 1.00 550,000.00 550,000.00
9 Petugas Keselamatam dan Kesehatan Kerja (K3) Org/Bln 1.00 4,197,030.00 4,197,030.00
10 Peralatan P3K Buah 1.00 100,000.00 100,000.00
11 Rambu Petunjuk Buah 1.00 75,000.00 75,000.00
12 Rambu Peringatan Buah 1.00 75,000.00 75,000.00
13 Bendera Keselamatam dan Kesehatan Kerja (K3) Buah 1.00 75,000.00 75,000.00
Sub Total 6,417,030.00
TOTAL C 6,417,030.00
JUMLAH 287,378,160.93
PPN 11% 31,611,597.70
TOTAL 318,989,758.64