LOKASI :
MENARA SUAR PULAU SELARU, KAB. KEPULAUAN
TANIMBAR - PROPINSI MALUKU
a b c
JUMLAH 533.780.176,86
PPN ( 11 %) 58.715.819,46
JUMLAH 592.495.996,32
DIBULATKAN 592.495.000,00
Terbilang :
LIMA RATUS DELAPAN PULUH TUJUH JUTA EMPAT RATUS TUJUH PULUH DELAPAN RIBU RUPIH
HARGA SATUAN
NO. URAIAN JENIS PEKERJAAN
(Rp)
a b c
1 1 M2 BONGKAR LANTAI KERAMIK / RABAT/DINDING KERAMIK: 16.920,00
2 1 M3 URUGAN PASIR DENGAN PASIR URUG : 562.480,00
3 1 M2 LAPIS PONDASI AGREGAT KELAS A 943.740,00
4 1 M2 LAPIS PONDASI AGREGAT KELAS B 868.660,00
5 1 LITER LAPIS RESAP PENGIKAT 85.480,00
6 1 LITER LAPIS PEREKAT 34.150,00
7 1 M2 LASTON LAPIS AUS AC - BW ( T= 5 CM ) 1.081.570,00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO URAIAN BAHAN DAN UPAH KODE SATUAN
(Rp)
a b c d
III PERALATAN
1 Whell Loader 1,0 - 1,6 m3 M4 616.346,55 Jam
2 Dump Truck 3 - 4 m3 M5 880.218,17 Jam
3 Motor Grader > 100 HP M6 139.100,98 Jam
4 Vibratory Roller 5 - 8 T M7 102.256,64 Jam
5 Pneumatic Tire Roller M8 105.772,88 Jam
6 Water Tanker 3000 - 4500 L M9 78.227,72 Jam
7 Air Compressor M10 47.079,12 Jam
8 Asphalt Spayer M11 55.567,30 Jam
9 Asphalt Mixing Plant (AMP) M12 8.459.968,13 Jam
10 Generator Set M13 64.344,34 Jam
11 Asphalt Finisher M14 503.643,32 Jam
12 Tandem Roller 6-8 T M15 240.276,08 Jam