Anda di halaman 1dari 2

REKAPITULASI RENCANA ANGGARAN BIAYA

Program : REHABILITASI / PEMELIHARAAN JALAN DAN JEMBATAN


Kegiatan : PEMELIHARAAN JEMBATAN DALAM KOTA (TERSEBAR)
Paket : PENGGANTIAN JEMBATAN GG. SUKA DAMAI TAHAP 2
Lokasi : JL. SUKA DAMAI LOA BAHU
Sumber Dana : APBD KOTA SAMARINDA
Tahun Anggaran : 2014

NO URAIAN PEKERJAAN JUMLAH


(RP)

I. PEKERJAAN PENDAHULUAN 32.750.000,00

II. PEKERJAAN TANAH 11.781.165,79

III. PEKERJAAN PONDASI 46.628.325,00

IV. PEKERJAAN JALAN BETON 320.798.485,33

V. PEKERJAAN BAJA 850.526.767,06

VI. PEKERJAAN LAINNYA 10.000.000,00

JUMLAH 1.272.484.743,18
PPN 10 % 127.248.474,32
JUMLAH 1.399.733.217,50
PEMBULATAN 1.399.733.000,00

Terbilang :

Pejabat Pembuat Komitmen

Ir. H. EKO RESTU MINTO, MMT


Nip. 19591009 199303 1 001
RENCANA ANGGARAN BIAYA
Program : REHABILITASI / PEMELIHARAAN JALAN DAN JEMBATAN
Kegiatan : PEMELIHARAAN JEMBATAN DALAM KOTA (TERSEBAR)
Paket : PENGGANTIAN JEMBATAN GG. SUKA DAMAI TAHAP 2
Lokasi : JL. SUKA DAMAI LOA BAHU
Sumber Dana : APBD KOTA SAMARINDA
Tahun Anggaran : 2014

HARGA SATUAN JUMLAH


NO. URAIAN
SAT VOL. HARGA
(Rp) (Rp)
I PEKERJAAN PENDAHULUAN
1 Papan Nama Proyek Ls 1,000 750.000,00 750.000,00
2 Mobilisasi dan Demobilisasi Ls 1,000 15.000.000,00 15.000.000,00
3 Bongkaran Jembatan Lama Ls 1,000 15.000.000,00 15.000.000,00
4 Administrasi dan Dokumentasi Proyek Ls 1,000 2.000.000,00 2.000.000,00
Sub Total 32.750.000,00
II PEKERJAAN TANAH
1 Galian Tanah Konstruksi M3 97,620 70.586,13 6.890.618,11
2 Urugan Kembali Tanah Eks. Galian M3 29,280 24.705,15 723.366,67
3 Urugan Tanah Dengan Pemadatan M3 3,993 78.722,55 314.339,16
4 Leveling ( Timbunan Agregat B ) M3 6,630 503.109,83 3.335.618,15
5 Urugan Pasir Bawah Pondasi t = 10 Cm M3 3,360 153.935,63 517.223,70
Sub Total 11.781.165,79
III PEKERJAAN PONDASI
1 Pemotongan Tiang Pancang & Menghancurkan Isian Beton Bh 36,000 1.000.000,00 36.000.000,00
2 Pancang Kayu Ulin 10/10 - 400 m Ttk 50,000 212.566,50 10.628.325,00
Sub Total 46.628.325,00
IV PEKERJAAN JALAN BETON
1 Lantai Kerja Pondasi Beton Fc 10 MPa t = 5 Cm M3 2,680 1.334.979,72 3.577.745,64
2 Abutment
- Beton Fc 20 Mpa M3 43,800 2.126.674,74 93.148.353,81
- Baja Tulangan Ø19, Ø16, Ø12 mm Kg 9.204,154 19.703,15 181.350.780,86
- Bekisting M2 67,760 357.568,25 24.228.824,62
3 Lantai Jembatan t = 20 Cm dan Trotoar t = 25 Cm
- Beton Fc 20 Mpa M3 2.126.674,74 -
- Baja Tulangan Ø16, Ø12 mm Kg 19.703,15 -
- Floor Dack M2 250.000,00 -
- Bekisting M2 357.568,25 -
9 Elastomeric Bearing (450x450x39) Bh 6,000 2.615.463,40 15.692.780,40
10 Anchor Bolt Ø 1" L=50cm Bh 32,000 75.000,00 2.400.000,00
11 Mortar t=3,0 cm Bh 8,000 50.000,00 400.000,00
Sub Total 320.798.485,33
V PEKERJAAN BAJA
1 Stud/Shear Conector Ø 1" Kg 132,651 37.045,61 4.914.137,24
2 Girder Baja H Beam 900 x 300 x 18 Kg 15.718,560 37.045,61 582.303.583,79
3 Diafragma Baja INP 300 x 125 x 10,8 x 16,2 Kg 1.283,456 37.045,61 47.546.405,55
4 Closs Plate
- 1000 x 700 x 16 mm Kg 1.955,172 37.045,61 72.430.547,29
- 1000 x 300 x 16 mm Kg 558,621 37.045,61 20.694.453,58
- 2000 x 300 x 16 mm Kg 1.117,241 37.045,61 41.388.870,12
- 2000 x 130 x 16 mm Kg 726,207 37.045,61 26.902.774,71
- 400 x 200 x 12 mm Kg 228,414 37.045,61 8.461.727,43
5 Torsion Plate 860 x 100 x 16 mm Kg 384,331 37.045,61 14.237.776,15
6 Baut Ø 1" Bh 2.508,000 11.395,68 28.580.370,00
Sub Total 850.526.767,06
VI PEKERJAAN LAINNYA
1 Pemindahan Sementara dan Pengembalian Jaringan Pipa Ls 1,000 10.000.000,00 10.000.000,00
-
Sub Total 10.000.000,00
Jumlah Keseluruhan 1.272.484.743,18