TERBILANG : TIGA RATUS LIMA PULUH SEMBILAN JUTA DELAPAN RATUS RIBU RUPIAH
Penawar,
CV. NUMFOR YEMBURWO
A . UPAH KERJA
1 . Pekerja Org/Hr = Rp. 150,000.00
2 . Tukang Org/Hr = Rp. 185,000.00
3 . Kepala Tukang Org/Hr = Rp. 195,000.00
4 . Mandor Org/Hr = Rp. 210,000.00
B . HARGA BAHAN
I KELOMPOK TANAH PASIR DAN BATU
II KELOMPOK KAYU
1 . Balok kayu besi /M3 = Rp. 5,450,000.00
2 . Balok / papan kayu matoa /M3 = Rp. 3,150,000.00
3 . Papan kayu besi /M3 = Rp. 5,450,000.00
4 . Papan campuran /M3 = Rp. 3,000,000.00
5 . Kayu doken /btg = Rp. 22,500.00
6 Papan bekesting /M3 = Rp. 2,950,000.00
7 List plafon kayu siku 3 - 4 - 4m /M1 = Rp. 13,250.00
8 List plafon kayu lurus 3 - 4 - 4m /M1 = Rp. 9,500.00
1 M3 URUGAN TANAH
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.2500 150,000.00 37,500.00
Mandor L.04 Oh 0.0250 210,000.00 5,250.00
JUMLAH TENAGA KERJA 42,750.00
B BAHAN
Tanah Urug M3 1.0000 340,000.00 340,000.00
JUMLAH HARGA BAHAN 340,000.00
C PERALATAN
1 M2 PLESTERAN ACI
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.2000 150,000.00 30,000.00
Tukang L.02 Oh 0.1000 185,000.00 18,500.00
Kepala Tukang L.03 Oh 0.0100 195,000.00 1,950.00
Mandor L.04 Oh 0.0100 210,000.00 2,100.00
JUMLAH TENAGA KERJA 52,550.00
B BAHAN
Semen PC Kg 3.2500 2,100.00 6,825.00
JUMLAH HARGA BAHAN 6,825.00
C PERALATAN
1 M2 PASANG KACA
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 0.0150 150,000.00 2,250.00
Tukang L.02 Oh 0.1500 185,000.00 27,750.00
Kepala Tukang L.03 Oh 0.0150 195,000.00 2,925.00
Mandor L.04 Oh 0.0008 210,000.00 168.00
JUMLAH TENAGA KERJA 33,093.00
B BAHAN
Kaca tebal 5 mm lbr 1.1000 360,000.00 396,000.00
JUMLAH HARGA BAHAN 396,000.00
C PERALATAN
1 M3 Beton K.225 Setara Campuran 1Pc : 2Psr : 3Kr (Mutu f'c = 19,3 Mpa)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 Oh 1.6500 150,000.00 247,500.00
Tukang L.02 Oh 0.2750 185,000.00 50,875.00
Kepala Tukang L.03 Oh 0.0275 195,000.00 5,362.50
Mandor L.04 Oh 0.0830 210,000.00 17,430.00
JUMLAH TENAGA KERJA 321,167.50
B BAHAN
Batu Pecah 1/2 - 2/3 kg 1,047.000 742.86 777,771.43
Pasir Beton kg 698.000 428.57 299,142.86
Semen kg 371.000 2,100.00 779,100.00
Air ltr 215.000 200.00 43,000.00
JUMLAH HARGA BAHAN 1,899,014.29
C PERALATAN