( HARGA PERKIRAAN SENDIRI )

DAFTAR KUANTITAS DAN HARGA


NAMA PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN PANJANG RUAS : 1.000.00 M
NAMA KEGIATAN : PEMBANGUNAN JALAN PANJ. PROYEK : 427.00 M
PAKET PEKERJAAN : PENINGKATAN JALAN DESA KALUMPANG LEBAR : 4,0 M'
LOKASI : KECAMATAN PADARINCANG KONSTRUKSI : BETON
SUMBER DANA/TA. : DAU - APBD KABUPATEN SERANG / 2016 WILAYAH : (II) DUA

HARGA JUMLAH TOTAL


NO. MATA
JENIS PEKERJAAN SAT. VOLUME SATUAN HARGA HARGA
PEMBAYARAN
(Rp.) (Rp.) (Rp.)

Sta. 0+000 s/d Sta.0+128 (P=128 m' : L= 4,0 m')


Sta. 0+236 s/d Sta.0+535 (P=299 m' : L= 4,0 m')

I PEKERJAAN UMUM
1.2 Mobilisasi Ls 1,00 17.102.058,87 17.102.058,87 17.102.058,87
- Pembuatan papan nama proyek
- Pengujian Laboratorium
- Direksikeet
- Dokumentasi dan Rekaman Proyek
- Pengukuran dan Pematokan
- Mobilisasi dan Demobilisasi Alat

III PEKERJAAN TANAH


3.1.(10) Galian Tanah Untuk Pelebaran M3 106,75 90.850,00 9.698.237,50 12.100.600,84
3.4.6 Pembersihan semak - semak M2 598,00 4.017,33 2.402.363,34

IV PELEB. PERKERASAN & BAHU JALAN


4.2.1 Lapis Pondasi Agregat Kelas A M3 42,70 280.102,44 11.960.374,19 29.709.835,89
4.2.(2a) Lapis Pondasi Agregat Kelas B M3 64,05 277.118,84 17.749.461,70

V PEK. PERKERASAN BERBUTIR & BETON SEMEN


5.1.1 Perbaikan Lapis Pondasi Agregat Kelas A M3 103,50 277.289,68 28.699.481,88 334.373.966,99
5.1.2 Perbaikan Lapis Pondasi Agregat Kelas B M3 45,92 270.518,69 12.422.218,24
7.1 (7a) Perkerasan Beton Semen (K-250) P= 427 M' M3 256,20 1.063.401,14 272.443.372,07
- Polytene 125 mikron Kg 112,09 25.000,00 2.802.250,00
7.1 (11) Acuan Untuk Perkerasan Beton M2 107,60 167.348,00 18.006.644,80

VII PEKERJAAN STRUKTUR


Tembok Penahan Tanah :
(P=200m : T=-0,5m)
3.1.(10) Galian untuk pondasi TPT M3 22,00 90.850,00 1.998.700,00 61.259.366,40
7.9.(1) Pasangan Batu untuk TPT M3 60,00 827.045,36 49.622.721,60
7.9 (2) Plesteran untuk TPT M2 80,00 91.669,26 7.333.540,80
3.2.4 Timbunan untuk TPT M3 50,00 46.088,08 2.304.404,00
( HARGA PERKIRAAN SENDIRI )
REKAPITULASI HARGA
PROVINSI : BANTEN PANJANG RUAS : 1.000.00 M
KABUPATEN : SERANG PANJ. PROYEK : 427.00 M
NAMA PROGRAM : PEMBANGUNAN JALAN DAN JEMBATAN LEBAR : 4,0 M'
NAMA KEGIATAN : PEMBANGUNAN JALAN KONSTRUKSI : BETON
PAKET PEKERJAAN : PENINGKATAN JALAN DESA KALUMPANG WILAYAH : (II) DUA
LOKASI : KECAMATAN PADARINCANG
SUMBER DANA/TA. : DAU - APBD KABUPATEN SERANG / 2016

NO. MATA JUMLAH


JENIS URAIAN PEKERJAAN
PEMBAYARAN BIAYA

I PEKERJAAN UMUM Rp. 17.102.058,87


III PEKERJAAN TANAH Rp. 12.100.600,84
IV PELEB. PERKERASAN & BAHU JALAN Rp. 29.709.835,89
V PEK. PERKERASAN BERBUTIR & BETON SEMEN Rp. 334.373.966,99
VII PEKERJAAN STRUKTUR
Tembok Penahan Tanah : Rp. 61.259.366,40
(P=200m : T=-0,5m)

JUMLAH Rp. 454.545.828,99


PPN 10% Rp. 45.454.582,90
JUMLAH TOTAL Rp. 500.000.411,89
DIBULATKAN Rp. 500.000.000,00

TERBILANG : LIMA RATUS JUTA RUPIAH,--

Serang, Februari 2016

Ditetapkan oleh : Dibuat oleh :


Kepala Bidang Bina Marga Kepala Seksi Perencanaan
Selaku Pejabat Pembuat Komitmen Bidang Bina Marga DPU Kab. Serang
DPU Kab. Serang

JATNIKA, ST YADI PRIYADI ROCHDIAN,ST.MM.


NIP. 19691123 200701 1 008 NIP. 19810622 200801 1 004
3,7624499

2,1336105
0,5285195

2,6312802
3,9048784

6,3138808
2,7328858
59,937492
0,6164945
3,9614586

0,4397136
10,91699
1,6133776
0,5069685
100
DAFTAR HARGA SATUAN
WILAYAH 2

Harga
No. Mata
Uraian Satuan Satuan
Pembayaran
(Rupiah)

a b c d

DIVISI 3. PEKERJAAN TANAH


3.1.(10) Galian Tanah Untuk Konstruksi M3 90.850,00
3.2.(4) Timbunan Kembali M3 46.088,08
3.4.(6) Pembersihan Semak-Semak Pada Bahu M2 4.017,33

DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN


4.2.(1) Lapis Pondasi Agregat Kelas A (untuk pelebaran) M3 280.102,44
4.2.(2a) Lapis Pondasi Agregat Kelas B (untuk pelebaran) M3 277.118,84

DIVISI 5. PERKERASAN BERBUTIR & BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M3 277.289,68
5.1.(2) Lapis Pondasi Agregat Kelas B M3 270.518,69

DIVISI 7. STRUKTUR
7.1 (7a) Beton mutu sedang fc= 20 MPa (K-250) (Site Mix) M3 1.063.401,14
7.1 (11) Acuan Untuk Beton M2 167.348,00
7.9.(1) Pasangan Batu M3 827.045,36
7.9.(2) Plesteran M2 91.669,26
90.850,00
46.088,08
4.017,33

280.102,44
277.118,84

277.289,68
270.518,69

1.063.401,14
167.348,00
827.045,36
91.669,26
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA
No. URAIAN KODE HP SEWA KET.
ALAT/JAM (Harga 2011)
(di luar PPN)

1 ASPHALT MIXING PLANT E01 294,0 6.821.489,09 1.936.000,00


2 ASPHALT FINISHER E02 72,4 925.245,53 260.150,00
3 ASPHALT SPRAYER E03 4,0 67.854,99 78.650,00
4 BULLDOZER 100-150 HP E04 155,0 568.351,55 780.450,00
5 COMPRESSOR 4000-6500 L\M E05 60,0 185.404,05 157.300,00
6 CONCRETE MIXER 0.3-0.6 M3 E06 20,0 175.847,93 121.000,00
7 CRANE 10-15 TON E07 138,0 664.631,36 0,00
8 DUMP TRUCK 3.5 TON E08 100,0 327.973,76 0,00
9 DUMP TRUCK 10 TON E09 190,0 535.211,30 350.900,00
10 EXCAVATOR 80-140 HP E10 133,0 528.690,15 719.950,00
11 FLAT BED TRUCK 3-4 M3 E11 190,0 515.055,76 272.250,00
12 GENERATOR SET E12 180,0 465.562,06 42.350,00
13 MOTOR GRADER >100 HP E13 135,0 474.696,77 568.700,00
14 TRACK LOADER 75-100 HP E14 70,0 304.538,28 0,00
15 WHEEL LOADER 1.0-1.6 M3 E15 96,0 365.461,37 453.750,00
16 THREE WHEEL ROLLER 6-8 T E16 55,0 228.874,17 199.650,00
17 TANDEM ROLLER 6-8 T. E17 82,0 478.009,45 290.400,00
18 TIRE ROLLER 8-10 T. E18 100,5 451.067,55 441.650,00
19 VIBRATORY ROLLER 5-8 T. E19 82,0 415.500,75 108.900,00
20 CONCRETE VIBRATOR E20 5,5 48.042,27 26.620,00
21 STONE CRUSHER E21 220,0 747.596,37 943.800,00
22 WATER PUMP 70-100 mm E22 6,0 45.781,58 26.015,00
23 WATER TANKER 3000-4500 L. E23 100,0 270.354,25 363.000,00
24 PEDESTRIAN ROLLER E24 8,8 93.596,42 0,00
25 TAMPER E25 4,7 52.734,77 29.040,00
26 JACK HAMMER E26 0,0 39.337,13 0,00
27 FULVI MIXER E27 345,0 1.413.309,92 0,00
28 CONCRETE PUMP E28 100,0 270.318,07 226.875,00
29 TRAILER 20 TON E29 175,0 534.372,56
30 PILE DRIVER + HAMMER E30 25,0 282.942,58
31 CRANE ON TRACK 35 TON E31 125,0 479.415,89
32 WELDING SET E32 40,0 121.462,85
33 BORE PILE MACHINE E33 150,0 828.018,54
34 ASPHALT LIQUID MIXER E34 5,0 45.926,75
35 TRONTON E35 150,0 579.291,26
36 COLD MILLING E36 248,0 1.711.062,59
37 ROCK DRILL BREAKER E37 3,0 314.502,51
38 COLD RECYCLER E38 900,0 4.075.621,57
39 HOT RECYCLER E39 400,0 7.530.096,84
40 AGGREGAT (CHIP) SPREADER E40 115,0 570.352,37
41 ASPHALT DISTRIBUTOR E41 115,0 396.733,75
42 SLIP FORM PAVER E42 105,0 567.526,61
43 CONCRETE PAN MIXER E43 134,0 687.740,57
44 CONCRETE BREAKER E44 290,0 887.442,98
45 ASPAHLT TANKER E45 190,0 583.995,23
46 CEMENT TANKER E46 190,0 545.595,23
47 CONDRETE MIXER (350) E47 20,0 87.297,32
48 VIBRATING RAMMER E48 4,2 52.985,05
49 TRUK MIXER (AGITATOR) E49 220,0 674.337,72
50 BORE PILE MACHINE E50 125,0 681.985,84
51 CRANE ON TRACK 75-100 TON E51 200,0 665.191,55
52 BLENDING EQUIPMENT E52 50,0 163.428,57
53 ASPHALT LIQUID MIXER E34a 40,0 121.246,75
HARGA DASAR SATUAN UPAH
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1. Pekerja (L01) Jam 14.285,71


2. Tukang (L02) Jam 15.000,00
3. Mandor (L03) Jam 17.142,86
4. Operator (L04) Jam 17.142,86
5. Pembantu Operator (L05) Jam 14.285,71
6. Sopir / Driver (L06) Jam 17.142,86
7. Pembantu Sopir / Driver (L07) Jam 14.285,71
8. Mekanik (L08) Jam 17.142,86
9. Pembantu Mekanik (L09) Jam 17.142,86
10. Kepala Tukang (L10) Jam 14.285,71
DAFTAR
HARGA DASAR SATUAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

1 Pasir Pasang (Sedang) M01b M3 190.000,00


2 Pasir Beton (Kasar) M01a M3 190.000,00
3 Pasir Urug (ada unsur lempung) M01d M3 105.000,00
4 Batu Kali M02 M3 140.000,00
5 Agregat Kasar M03 M3 198.843,73
6 Agregat Halus M04 M3 198.843,73
7 Batu Belah / Kerakal M06 M3 140.000,00
8 Bahan Tanah Timbunan M08 M3 100.000,00
9 Aspal M10 KG 11.612,90
10 Kerosen / Minyak Tanah M11 LITER 12.100,00
11 Semen / PC (50kg) M12 Zak 64.500,00
12 Semen / PC (kg) M12 Kg 1.290,00
13 Kawat Beton M14 Kg 17.800,00
15 Paku M18 Kg 12.600,00
16 Kayu Perancah M19 M3 2.700.000,00
17 Bensin M20 LITER 9.400,00
18 Solar M21 LITER 9.600,00
19 Minyak Pelumas / Olie M22 LITER 40.000,00
20 Bahan Agr.Base Kelas A M26 M3 180.630,01
21 Bahan Agr.Base Kelas B M27 M3 179.002,51
22 Geotextile M30 M2 5.800,00
23 Thinner M33 LITER 16.500,00
24 Beton K-250 M37 M3 885.039,00
25 Baja Tulangan (Polos) U24 M39a Kg 9.420,00
26 Baja Tulangan (Ulir) D32 M39b Kg 9.485,00
27 Cat M42 Kg 55.000,00
28 Pasir Urug M44 M3 105.000,00
29 Beton K-125 M47 M3 818.591,00
30 Baja Tulangan (Polos) U32 M57a Kg 9.420,00
31 Baja Tulangan (Ulir) D39 M39c Kg 9.485,00
32 Baja Tulangan (Ulir) D48 M39d Kg 9.485,00
33 Beton K-300 M59 M3 915.262,50
34 Beton K-175 M60 M3 841.732,50
35 Beton K-500 M68 M3 1.020.566,50
36 Beton K-400 M69 M3 965.352,00
37 Beton K-350 M72 M3 931.784,50
38 Agregat Pecah Mesin 0-5 mm M91 M3 165.000,00
39 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 172.500,00
40 Agregat Pecah Mesin 20-30 mm M93 M3 182.500,00
41 Joint Sealent M94 Kg 35.000,00
42 Polytene 125 mikron M97 Kg 25.000,00
43 Curing Compound M98 Ltr 10.500,00
44 Kayu Acuan M99 M3 2.700.000,00
45 Hotmix HRS-WC Ton 1.492.350,00
46 Hotmix AC-WC Ton 1.358.050,00