REKAPITULASI RENCANA ANGGARAN BIAYA

PEMBANGUNAN MENARA DAN SELASAR MASJID SAFIINATUN NAJAH

NO URAIAN PEKERJAAN SUB JUMLAH JUMLAH

I PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN Rp 5,608,400.00
Rp 5,608,400.00
SUB TOTAL PEKERJAAN STRUKTUR Rp 5,608,400.00

II PEKERJAAN STRUKTUR
I PEKERJAAN TANAH Rp 3,963,028.20
II PEKERJAAN PONDASI Rp 76,934,399.60
III PEKERJAAN BETON Rp 298,199,074.58
Rp 379,096,502.38
SUB TOTAL PEKERJAAN STRUKTUR Rp 379,096,502.38

III ARSITEKTUR
I PEKERJAAN PASANGAN & PLESTERAN Rp 22,043,845.56
II PEKERJAAN LANTAI & DINDING KERAMIK Rp 92,810,492.00
III PEKERJAAN PENGECATAN Rp 9,483,210.00
IV PEKERJAAN PINTU DAN JENDELA Rp 5,000,000.00
V PEKERJAAN SANITASI Rp 992,000.00
VI PEKERJAAN LAIN LAIN Rp 2,200,000.00
Rp 132,529,547.56
SUB TOTAL PEKERJAAN ARSITEKTUR Rp 132,529,547.56

IV MEKANIKAL DAN ELEKTRIKAL


I PEKERJAAN MEKANIKAL PLUMBING Rp 4,400,000.00
II PEKERJAAN ELEKTRIKAL Rp 9,502,000.00
Rp 13,902,000.00
SUB TOTAL MEP Rp 13,902,000.00

JUMLAH TOTAL Rp 531,136,449.94


DIBULATKAN Rp 531,130,000.00

Terbilang : Lima Ratus Tiga Puluh Satu Juta Seratus Tiga Puluh Ribu Rupiah.

Surabaya, Agustus 2022


KONSULTAN PERENCANA

MIFTAHUR ROHIM
RENCANA ANGGARAN BIAYA
PEMBANGUNAN MENARA DAN SELASAR MASJID SAFIINATUN NAJAH

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan dan Perataan Lapangan 56.00 m2 8,100.00 453,600.00
2 Pek. Pengukuran dan Pemasangan Bouwplank 22.00 m1 43,400.00 954,800.00
3 Pek. Bongkaran dinding 42.00 m2 100,000.00 4,200,000.00
5,608,400.00
II PEKERJAAN STRUKTUR
I PEKERJAAN TANAH
1 Galian tanah pondasi 22.20 m³ 36,600.00 812,520.00
2 Urugan Pasir bawah Lt. Kerja Plat Lt. t = 5 cm 10.50 m³ 130,000.00 1,365,000.00
3 Urugan Tanah Kembali 9.30 m³ 29,400.00 273,508.20
4 Urugan Sirtu t. 30 cm (Peninggian Site Bangunan) 16.80 m³ 90,000.00 1,512,000.00
3,963,028.20
II PEKERJAAN PONDASI
1 Pondasi batu kali 8.91 m³ 700,000.00 6,237,000.00
2 Beton K-250 Pilecap 100 x 100 x 40 PC Menara masjid 1.60 m³ 7,226,700.00 11,562,720.00
3 Beton K-250 Pilecap 60 x 60 x 20 (PC) 0.72 m³ 7,226,700.00 5,203,224.00
4 Pondasi Straus D :30 T:3 10.00 Titik 1,266,375.00 12,663,750.00
5 Pondasi Straus D :30 T:8 8.00 Titik 2,776,000.00 22,208,000.00
6 Beton K-225 Sloof 20 x 40 (S) 3.36 m³ 4,916,100.00 16,518,096.00
7 Beton K-225 Lantai Kerja bawah pondasi t: 5 cm 0.34 m³ 808,400.00 278,089.60
8 Beton Rabat Lt. 1, t: 5 cm 2.80 m³ 808,400.00 2,263,520.00
76,934,399.60
III PEKERJAAN BETON
1 Beton K-225 Kolom 40 x 40 cm (K1) 3.20 m³ 7,291,000.00 23,331,200.00
2 Beton K-225 Kolom 20 x 20 cm (K2) 0.90 m³ 5,817,000.00 5,212,032.00
3 Beton K-225 Kolom 15 x 15 cm (K3) 1.14 m³ 5,259,600.00 6,021,190.08
4 Beton K-225 Balok 15 x 15 (B1) 0.40 m³ 5,875,300.00 2,337,194.34
5 Beton K-225 Balok 20 x 35 (B2) 3.90 m³ 5,859,600.00 22,879,394.16
6 Beton K-225 Plat, t: 12 cm 49.13 m³ 4,852,800.00 238,418,064.00
7 Beton Listplank beton bertulang 4.22 m³ 1,786,850.00 7,547,654.40
298,199,074.58
III ARSITEKTUR
I PEKERJAAN PASANGAN & PLESTERAN
1 Pek. Dinding Bata ringan 98.79 m2 130,000.00 12,842,700.00
2 Pek. Plesteran 177.82 m2 32,400.00 5,761,432.80
3 Pek. Acian 97.80 m2 15,600.00 1,525,712.76
4 Pek. Benangan 220.00 m' 8,700.00 1,914,000.00
22,043,845.56
II PEKERJAAN LANTAI & DINDING KERAMIK
1 Pek. Granit Lantai UK. 60 x 60 126.00 m2 311,600.00 39,261,600.00
2 Pek. Keramik menara UK. 20 x 40 37.68 m2 213,900.00 8,059,752.00
3 Pek. Batu alam candi 105.04 m2 170,000.00 17,857,140.00
4 Pek. Batu alam andesit 125.60 m2 220,000.00 27,632,000.00
92,810,492.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

III PEKERJAAN PENGECATAN


1 Pek. Pengecatan Dinding 350.35 m2 20,600.00 7,217,210.00
2 Pek. Pengecatan Plafond dan list plafond 110.00 m2 20,600.00 2,266,000.00
9,483,210.00
IV PEKERJAAN PINTU DAN JENDELA
1 Kusen kaca mati 4.00 bh 1,250,000.00 5,000,000.00
5,000,000.00
V PEKERJAAN SANITASI
1 Pas. Floor drain 8.00 Titik 124,000.00 992,000.00
992,000.00
VI PEKERJAAN LAIN LAIN
1 Pek. Kubah menara 1.00 bh 2,200,000.00 2,200,000.00
2,200,000.00
IV MEKANIKAL DAN ELEKTRIKAL
I PEKERJAAN MEKANIKAL PLUMBING
1 Pas. Saluran air kotor Pipa PVC 4" 40.00 m1 110,000.00 4,400,000.00
4,400,000.00
II PEKERJAAN ELEKTRIKAL
1 Pas. Instalasi titik lampu 30.00 titik 127,600.00 3,828,000.00
2 Pas. Instalasi titik stop kontak biasa 5.00 titik 102,600.00 513,000.00
3 Pas. Saklar tunggal 3.00 bh 26,000.00 78,000.00
4 Pas. Saklar ganda 5.00 bh 30,600.00 153,000.00
5 DL LED Panel 12W 11.00 bh 200,000.00 2,200,000.00
6 UL LED Panel 5W - outdoor 8.00 bh 135,000.00 1,080,000.00
7 LED lampu taman 5 W - outdoor 11.00 bh 150,000.00 1,650,000.00
9,502,000.00