I PEKERJAAN PERSIAPAN Rp 14,688,277.00 II PEKERJAAN TANAH Rp 2,564,044.55 III PEKERJAAN PONDASI Rp 50,580,530.00 IV PEKERJAAN DINDING Rp 60,064,322.99 V PEKERJAAN KAYU Rp 50,804,205.00 VI PEKERJAAN PENUTUP ATAP Rp 1,468,880.00 VII PEKERJAAN PLAFON Rp 745,333.33 VIII PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 8,954,391.20 IX PEKERJAAN KUNCI DAN KACA Rp 5,378,266.25 X PEKERJAAN PENGECATAN Rp 7,829,792.43 XI PEKERJAAN INSTALASI LISTRIK Rp 3,826,000.00 XII PEKERJAAN SANITASI Rp 14,176,570.00 TOTAL JUMLAH Rp 206,904,042.75 dibulatkan Rp 206,904,000.00 Rencanana Anggaran Biaya Pekerjaan : Lokasi : Tahun :
Harga Satuan Jumlah Harga
No Jenis Pekerjaan Satuan Volume Total Harga (Rp) (Rp) (Rp)
A PEKERJAAN PERSIAPAN 14,688,277.00
1 Pembersihan Lahan m² 308.120 20,000.00 6,162,400.00 3 Memasang Bouwplank m¹ 38.000 99,200.00 3,769,600.00 4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 756,277.00 756,277.00 6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00 7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
B PEKERJAAN TANAH 2,564,044.55
1 Galian Tanah Biasa sedalam 1 m m³ 43.680 40,000.00 1,747,200.00 2 Urugan Kembali m³ 13.197 19,150.00 252,722.55 3 Urugan Pasir Bawah Pondasi m³ 3.338 169,000.00 564,122.00
C PEKERJAAN PONDASI 50,580,530.00
1 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m³ 22.400 656,890.00 14,714,336.00 2 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m³ 54.600 656,890.00 35,866,194.00
D PEKERJAAN DINDING 60,064,322.99
1 Pasangan Kayu 7x12x400 Btg 33.000 594,500.00 19,618,500.00 2 Pasangan Kayu Papan m² 74.200 360,591.95 26,755,922.99 3 Pasangan Plywood 9 mm m² 74.200 184,500.00 13,689,900.00
E PEKERJAAN KAYU 50,804,205.00
1 Pasang Kusen Dan Pintu Geser m³ 1.123 19,325,000.00 21,701,975.00 2 Pasang Pintu Panel Kayu Jati m² 2.356 1,095,000.00 2,579,820.00 3 Pasang Nook, Gording, Murplat, Nook Kayu Bengkirai m³ 1.327 10,530,000.00 13,973,310.00 4 Pasang Usuk+Reng Genteng Beton Kayu Bengkirai m² 74.200 141,500.00 10,499,300.00 5 Pasang Listplank, Reuter 2X (2X20) cm, kayu bengkirai m³ 1.000 102,800.00 102,800.00 6 Pasang Rangka Langit-langit 1X1 m Kayu Borneo m² 12.000 162,250.00 1,947,000.00 F PEKERJAAN PENUTUP ATAP 1,468,880.00 1 Pasang Genteng Zinc Roof m¹ 14.000 104,920.00 1,468,880.00
G PEKERJAAN PLAFON 745,333.33
1 Pasang List Plafon Kayu Profil m¹ 14.000 13,916.67 194,833.33 2 Langit-langit Asbes m² 12.000 45,875.00 550,500.00
H PEKERJAAN PENUTUP LANTAI DAN DINDING 8,954,391.20
1 Pekerjaan Urug Pasir Bawah Lantai m³ 21.500 169,000.00 3,633,500.00 2 Pasang Lantai Keramik 33X33 cm m² 21.500 173,111.20 3,721,890.80 3 Pasang Lantai Keramik 20X20 cm m² 4.500 355,333.42 1,599,000.40