REKAPITULASI

RENCANA ANGGARAN BIAYA


(RAB)
PEKERJAAN : PEMBANGUNAN PAGAR, ATAP DAN R. ISTIRAHAT
LOKASI : KLATEN, JAWA TENGAH
TAHUN : 2023

JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)

A PEKERJAAN PERSIAPAN Rp 2,150,000.00


B BANGUNAN PAGAR DAN ATAP
I PEKERJAAN TANAH Rp 12,261,814.29
II PEKERJAAN PASANGAN DAN PLESTERAN Rp 26,705,134.50
III PEKERJAAN BETON Rp 22,767,286.52
C BANGUNAN TEMPAT ISTIRAHAT, WC DAN GUDANG PAKAN
I PEKERJAAN TANAH Rp 623,952.00
II PEKERJAAN PASANGAN DAN PLESTERAN Rp 12,492,363.18
III PEKERJAAN BETON Rp 9,638,088.07
IV PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 4,071,000.00
VI PEKERJAAN PINTU DAN JENDELA Rp 16,285,000.00
V PEKERJAAN CAT - CATAN Rp 1,800,691.20
VI PEKERJAAN SANITASI Rp 19,017,187.25
VII PEKERJAAN LISTRIK Rp 3,935,261.45
VIII PEKERJAAN ATAP Rp 12,716,000.00

JUMLAH Rp 144,463,778.46
JUMLAH TOTAL Rp 144,463,778.46
DIBULATKAN Rp 144,463,000.00

Terbilang : Seratus Empat Puluh Empat Juta Empat Ratus Enam Puluh Tiga Ribu Rupiah

Klaten, 25 Mei 2023

Di Buat

ROHMAT TOHWANI, ST
RENCANA ANGGARAN BIAYA
(RAB)

PEKERJAAN : PEMBANGUNAN PAGAR, ATAP DAN R. ISTIRAHAT


LOKASI : KLATEN
TAHUN : 2023
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN VOL SAT
(Rp.) (Rp.)
A PEKERJAAN PERSIAPAN
1 Uitzet dan Bouwplank 180.00 m' 10,000.00 1,800,000.00
2 Pembersihan Lokasi 1.00 Ls 350,000.00 350,000.00
JUMLAH 2,150,000.00
B BANGUNAN PAGAR DAN ATAP
I PEKERJAAN TANAH
1 Galian tanah pondasi batu kali 21.06 m3 45,870.00 966,022.20
2 Urugan tanah kembali 7.24 m3 22,275.00 161,262.09
3 Urugan pasir bawah pondasi batu kali 1.62 m3 206,500.00 334,530.00
4 Peninggian Tanah Urugan dan pemadatan rata 18.00 m3 600,000.00 10,800,000.00
JUMLAH 12,261,814.29
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasang pondasi batu kali campuran 1 Pc : 8 Psr 12.96 m3 662,265.00 8,582,954.40
2 Pasang Batako Campuran 1:8 141.00 m2 103,000.00 14,523,000.00
3 Plesteran dinding 1 Pc : 8 Pp Tebal 15 mm 42.30 m2 52,200.00 2,208,060.00
4 Pekerjaan Acian 42.30 m2 32,887.00 1,391,120.10
JUMLAH 26,705,134.50
III PEKERJAAN BETON
1 Beton Bertulang Sloof 15/20
a. Beton K-225 1.89 m3 840,824.00 1,589,157.36
b. Pasang Bekisting 22.68 m2 143,475.00 3,254,013.00
c. Pembesian 222.14 kg 17,586.00 3,906,506.56
2 Beton Bertulang Kolom Struktural 15x20
a. Beton K-225 1.44 m3 840,824.00 1,210,786.56
b. Pasang Bekisting 18.00 m2 143,475.00 2,582,550.00
c. Pembesian 174.24 kg 17,586.00 3,064,237.40
3 Beton Bertulang Ringbalk Struktural 15x20
a. Beton K-225 1.62 m3 840,824.00 1,362,134.88
b. Pasang Bekisting 21.60 m2 143,475.00 3,099,060.00
c. Pembesian 153.47 kg 17,586.00 2,698,840.77
JUMLAH 22,767,286.52
C BANGUNAN TEMPAT ISTIRAHAT, WC DAN GUDANG PAKAN
I PEKERJAAN TANAH
1 Galian tanah pondasi batu kali 4.80 m3 45,870.00 220,176.00
2 Urugan tanah kembali 1.44 m3 22,275.00 32,076.00
3 Urugan pasir bawah pondasi batu kali 1.80 m3 206,500.00 371,700.00
JUMLAH 623,952.00
II PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasang pondasi batu kali campuran 1 Pc : 8 Psr 2.98 m3 662,265.00 1,970,238.38
2 Pasang Batako Campuran 1:8 44.00 m2 103,000.00 4,532,000.00
3 Plesteran dinding 1 Pc : 8 Pp Tebal 15 mm 70.40 m2 52,200.00 3,674,880.00
4 Pekerjaan Acian 70.40 m2 32,887.00 2,315,244.80
JUMLAH 12,492,363.18
III PEKERJAAN BETON
1 Beton Bertulang Sloof 15/20
a. Beton K-225 0.51 m3 840,824.00 428,820.24
b. Pasang Bekisting 7.40 m2 143,475.00 1,061,715.00
c. Pembesian 81.25 kg 17,586.00 1,428,862.50
2 Beton Bertulang Kolom Struktural 15x15
a. Beton K-225 0.62 m3 840,824.00 521,310.88
b. Pasang Bekisting 7.20 m2 143,475.00 1,033,020.00
c. Pembesian 89.85 kg 17,586.00 1,580,102.10

1
HARGA SATUAN JUMLAH HARGA
No URAIAN PEKERJAAN VOL SAT
(Rp.) (Rp.)
3 Beton Bertulang Ringbalk Struktural 15x15
a. Beton K-225 0.98 m3 840,824.00 819,803.40
b. Pasang Bekisting 7.17 m2 143,475.00 1,028,715.75
c. Pembesian 98.70 kg 17,586.00 1,735,738.20
JUMLAH 9,638,088.07
IV PEKERJAAN PENUTUP LANTAI DAN DINDING
1 Pasang Keramik lantai 40x40cm 9.00 m2 170,000.00 1,530,000.00
2 Pasang Keramik tile KM/WC 25 x 25cm 3.00 m2 160,000.00 480,000.00
3 Pasang dinding Keramik tile KM/WC 20 x 40 cm 9.00 m2 170,000.00 1,530,000.00
4 Plester dan aci lantai gudang pakan 9.00 m2 59,000.00 531,000.00
JUMLAH 4,071,000.00
VI PEKERJAAN PINTU DAN JENDELA
1 Kusen Dan Pintu Kayu Finishing Cat 1.00 bh 1,900,000.00 1,900,000.00
2 Kusen Dan Pintu Kamar Mandi 1.00 bh 1,250,000.00 1,250,000.00
3 Kusen Dan Jendela Kayu Kaca 1.00 bh 895,000.00 895,000.00
4 Kusen Dan Boven Kayu kaca 1.00 bh 495,000.00 495,000.00
5 Pintu Besi Kandang depan plat 13.50 m2 450,000.00 6,075,000.00
6 Pintu Besi Kandang belakang plat 12.60 m2 450,000.00 5,670,000.00
JUMLAH 16,285,000.00
VII PEKERJAAN CAT - CATAN
1 Pengecatan dinding Weathershield Décor Primer (NoDrop) 70.40 m2 25,578.00 1,800,691.20
JUMLAH 1,800,691.20
VIII PEKERJAAN SANITASI
1 Pasang closet jongkok "kia" CW637J 1.00 unit 450,000.00 450,000.00
2 Pasang kran air Ø 1/2 " Ex. Taho 3.00 bh 61,459.75 184,379.25
3 Pasang floordrain Ø 3 " stainless 2.00 bh 59,875.00 119,750.00
4 Pasang pipa air bersih PVC Ø 1 " Type AW 41.00 m' 25,000.00 1,025,000.00
5 Pasang pipa air kotoran PVC Ø 4 " Type D 13.00 m' 80,000.00 1,040,000.00
6 Pasang pipa air bekas PVC Ø 3 " Type D 21.00 m' 70,000.00 1,470,000.00
7 Pasang Jet Pump – PC-375 BIT Ex. Shimizu 1.00 unit 1,350,000.00 1,350,000.00
8 Pasang sumur Bor 1.00 bh 3,500,000.00 3,500,000.00
9 Pasang tandon air 750 liter Penguin lengkap dengan pelampung dan otomatis 1.00 bh 1,800,000.00 1,800,000.00
9 Pasang dudukan tandon air luar 750 liter 1.00 ls 4,100,000.00 4,100,000.00
10 Pasang saptictank dan resapan 1.00 unit 3,978,058.00 3,978,058.00
JUMLAH 19,017,187.25
IX PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik baru 900 kVA 900.00 kVA 2,000.00 1,800,000.00
2 Pasang Instalasi Titik Lampu & stop kontak NYA 3x1x2,5mm dalam conduit high impact PVC
7.00
20 mm titik 224,827.35 1,573,791.45
3 Pasang saklar tunggal Broco 5.00 bh 28,490.00 142,450.00
4 Pasang saklar Ganda Broco 1.00 bh 32,230.00 32,230.00
5 Pasang stop kontak dinding Broco 3.00 bh 28,930.00 86,790.00
6 Pasang LAMPU LED BULP-8 W Philips 6.00 bh 50,000.00 300,000.00

JUMLAH 3,935,261.45
IX PEKERJAAN ATAP
1 Rangka atap baja ringan (Reng Dan Usuk) 64.00 m2 95,000.00 6,080,000.00
2 Genteng Press sokka 64.00 m2 74,500.00 4,768,000.00
3 Kerpus Genteng press sokka 9.00 m 92,000.00 828,000.00
4 Lisplank Kayu finishing 16.00 m 65,000.00 1,040,000.00
JUMLAH 12,716,000.00