REKAPITULASI RENCANA ANGGARAN BIAYA

PEMBANGUNAN TEMPAT WUDHU PRIA & WANITA MASJID SAFIINATUN NAJAH

NO URAIAN PEKERJAAN SUB JUMLAH JUMLAH

I PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN Rp 2,305,040.00
Rp 2,305,040.00
SUB TOTAL PEKERJAAN STRUKTUR Rp 2,305,040.00

II PEKERJAAN STRUKTUR
A LANTAI 1
I PEKERJAAN TANAH Rp 3,692,354.40
II PEKERJAAN PONDASI Rp 14,543,348.00
III PEKERJAAN BETON Rp 65,556,968.34
Rp 83,792,670.74
SUB TOTAL PEKERJAAN STRUKTUR Rp 83,792,670.74

III ARSITEKTUR
A LANTAI 1
I PEKERJAAN PASANGAN & PLESTERAN Rp 38,650,894.00
II PEKERJAAN LANTAI & DINDING KERAMIK Rp 61,338,348.00
III PEKERJAAN PENGECATAN Rp 5,066,714.20
IV PEKERJAAN PINTU DAN JENDELA Rp 9,595,800.00
V PEKERJAAN SANITASI Rp 11,698,000.00
VI PEKERJAAN LAIN LAIN Rp 52,326,840.00
Rp 178,676,596.20
SUB TOTAL PEKERJAAN ARSITEKTUR Rp 178,676,596.20

IV MEKANIKAL DAN ELEKTRIKAL


A LANTAI 1
I PEKERJAAN MEKANIKAL PLUMBING Rp 3,097,000.00
II PEKERJAAN ELEKTRIKAL Rp 6,469,200.00
Rp 9,566,200.00
SUB TOTAL MEP Rp 9,566,200.00

JUMLAH TOTAL Rp 274,340,506.94


DIBULATKAN Rp 274,340,000.00

Terbilang : Dua Ratus Tujuh Puluh Empat Juta Tiga Ratus Empat Puluh Ribu Rupiah.

Surabaya, Agustus 2022


KONSULTAN PERENCANA

Fahrizal Ardiansyah
RENCANA ANGGARAN BIAYA
PEMBANGUNAN TEMPAT WUDHU PRIA & WANITA MASJID SAFIINATUN NAJAH

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PENDAHULUAN
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan dan Perataan Lapangan 102.40 m2 8,100.00 829,440.00
2 Pek. Pengukuran dan Pemasangan Bouwplank 34.00 m1 43,400.00 1,475,600.00
2,305,040.00
II PEKERJAAN STRUKTUR
A LANTAI 1
I PEKERJAAN TANAH
1 Galian tanah pondasi 15.80 m³ 36,600.00 578,294.64
2 Urugan Pasir bawah Lt. Kerja Plat Lt. t = 5 cm 1.80 m³ 130,000.00 234,000.00
3 Urugan Tanah Kembali 3.92 m³ 29,400.00 115,259.76
4 Urugan Sirtu t. 30 cm (Peninggian Site Bangunan) 30.72 m³ 90,000.00 2,764,800.00
3,692,354.40
II PEKERJAAN PONDASI
1 Pondasi batu kali 11.88 m³ 434,000.00 5,155,920.00
2 Beton K-225 Pilecap 60 x 60 x 20 (PC) 0.72 m³ 1,778,600.00 1,280,592.00
3 Beton K-225 Sloof 15 x 20 (S) 2.28 m³ 2,316,100.00 5,280,708.00
4 Beton K-225 Lantai Kerja bawah pondasi t: 5 cm 1.80 m³ 408,400.00 735,120.00
5 Beton Rabat Lt. 1, t: 5 cm 5.12 m³ 408,400.00 2,091,008.00
14,543,348.00
III PEKERJAAN BETON
1 Beton K-225 Kolom 15 x 30 cm (K1) 2.79 m³ 4,859,600.00 13,569,218.10
2 Beton K-225 Balok 15 x 25 (B1) 3.41 m³ 4,859,600.00 16,583,385.00
3 Beton K-225 Balok latei 15 x 15 (B2) 0.88 m³ 2,859,600.00 2,509,299.00
4 Beton K-225 Plat, t: 12 cm 11.53 m³ 2,852,800.00 32,895,066.24
65,556,968.34

III ARSITEKTUR
A LANTAI 1
I PEKERJAAN PASANGAN & PLESTERAN
1 Pek. Dinding Bata ringan 180.85 m2 130,000.00 23,510,500.00
2 Pek. Plesteran 361.70 m2 32,400.00 11,719,080.00
3 Pek. Acian 162.77 m2 15,600.00 2,539,134.00
4 Pek. Benangan 101.40 m' 8,700.00 882,180.00
38,650,894.00
II PEKERJAAN LANTAI & DINDING KERAMIK
1 Pek. Granit Lantai UK. 60 x 60 99.23 m2 311,600.00 30,918,510.00
3 Pek. Granit dinding UK. 60 x 60 91.87 m2 311,600.00 28,625,913.00
4 Pek. Dinding Keramik UK. 20 x 40 15.75 m2 113,900.00 1,793,925.00
61,338,348.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

III PEKERJAAN PENGECATAN


1 Pek. Pengecatan Dinding 113.86 m2 20,600.00 2,345,516.00
2 Pek. Pengecatan Plafond dan list plafond 132.10 m2 20,600.00 2,721,198.20
5,066,714.20
IV PEKERJAAN PINTU DAN JENDELA
1 Kusen Type P1 6.00 bh 996,000.00 5,976,000.00
2 Kusen Type P2 3.00 bh 462,600.00 1,387,800.00
3 Kusen Type BV 6.00 bh 372,000.00 2,232,000.00
9,595,800.00
V PEKERJAAN SANITASI
1 Pas. Septictank bio 1.00 unit 2,480,000.00 2,480,000.00
2 Pas. Resapan 1.00 unit 1,240,000.00 1,240,000.00
3 Pas. Closet jongkok 6.00 bh 503,000.00 3,018,000.00
4 Pas. Kran air dinding 27.00 m1 124,000.00 3,348,000.00
5 Pas. Floor drain 13.00 m1 124,000.00 1,612,000.00
11,698,000.00
VI PEKERJAAN LAIN LAIN
1 Pek. Kanopi 50.00 m2 330,000.00 16,500,000.00
2 Pek. Ram pipa trainless steel 1" 20.31 m2 1,764,000.00 35,826,840.00
52,326,840.00
IV MEKANIKAL DAN ELEKTRIKAL
A LANTAI 1
I PEKERJAAN MEKANIKAL PLUMBING
1 Pas. Saluran air bersih Pipa PVC 3/4" 30.00 m1 15,200.00 456,000.00
2 Pas. Saluran air bersih Pipa PVC 1" 20.00 m1 17,600.00 352,000.00
3 Pas. Saluran air kotor Pipa PVC 4" 30.00 m1 76,300.00 2,289,000.00
3,097,000.00
II PEKERJAAN ELEKTRIKAL
1 Pas. Instalasi titik lampu 23.00 titik 127,600.00 2,934,800.00
2 Pas. Instalasi titik stop kontak biasa 2.00 titik 102,600.00 205,200.00
3 Pas. Saklar tunggal - bh 26,000.00 -
4 Pas. Saklar ganda 3.00 bh 30,600.00 91,800.00
5 DL LED Panel 12W 16.00 bh 150,800.00 2,412,800.00
6 DL LED Panel 3W - Toilet 7.00 bh 117,800.00 824,600.00
6,469,200.00