REKAPITULASI

DAFTAR KUANTITAS DAN HARGA


PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE
LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

NO. JENIS KEGIATAN TOTAL

I PEKERJAAN PERSIAPAN Rp 19.454.791,30


II PEKERJAAN TANAH DAN URUGAN Rp 49.554.490,87
III PEKERJAAN STRUKTUR & BETON Rp 803.972.415,76
IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN Rp 205.718.552,55
V PEKERJAAN PASANGAN KERAMIK Rp 188.242.811,07
VI PEKERJAAN PLAFON DAN ATAP Rp 288.818.820,04
VII PEKERJAAN KUSEN, BINGKAI, & KACA Rp 144.040.000,00
VIII PEKERJAAN PENGECATAN Rp 41.975.455,81
IX PEKERJAAN WATERPROFING Rp 5.531.337,23
X PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A PEKERJAAN INSTALASI TITIK LAMPU DAN STOP KONTAK Rp 72.284.808,95
B PEKERJAAN TATA UDARA
1 PEKERJAAN EXHAUST FAN Rp 7.097.312,00
2 PEKERJAAN AIR CONDITIONER (AC) SPLIT INVERTER Rp 23.229.998,75
C PEKERJAAN PENANGKAL PETIR Rp 18.008.580,00
D PEKERJAAN CCTV Rp 29.238.580,00
XI PEKERJAAN SANITASI
A INSTALASI AIR BERSIH DAN PEMBUANGAN Rp 49.523.587,94
B PEKERJAAN SEPTIKTANK DAN PERESAPAN Rp 15.057.394,63
C PEKERJAAN GROUNDTANK (1 UNIT) Rp 30.899.198,26
XII PEKERJAAN LAIN-LAIN Rp 7.378.631,11

TOTAL PEKERJAAN Rp 2.000.026.766,25

JUMLAH TOTAL Rp 2.000.026.766,25


DIBULATKAN Rp 2.000.000.000,00
Terbilang : Dua Milyar Rupiah
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE
LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

HARGA JUMLAH
NO JENIS KEGIATAN SAT VOLUME SATUAN HARGA
( Rp ) ( Rp )
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1,00 Rp 8.000.000,00 Rp 8.000.000,00
2 Pembersihan lokasi Ls 1,00 Rp 1.000.000,00 Rp 1.000.000,00
3 Penyediaan Listrik Kerja dan Air Kerja Ls 1,00 Rp 3.000.000,00 Rp 3.000.000,00
4 Pengukuran/Pemasangan Papan Bowplank m' 100,00 Rp 74.547,91 Rp 7.454.791,30
Sub Total ( I ) Pekerjaan Persiapan Rp 19.454.791,30
II PEKERJAAN TANAH DAN URUGAN
1 Galian tanah keras pada pondasi dengan Alat berat m3 322,21 Rp 38.810,35 Rp 12.504.888,82
2 Urugan kembali tanah galian m3 107,40 Rp 48.290,00 Rp 5.186.426,48
3 Urugan pasir bawah pondasi t=5cm m3 15,72 Rp 187.118,80 Rp 2.941.507,54
4 Urugan sirtu peninggi lantai dan pemadatan m3 201,46 Rp 109.799,80 Rp 22.119.993,21
5 Urugan pasir bawah lantai t= 15 cm m3 36,35 Rp 187.118,80 Rp 6.801.674,82
Sub Total ( II) Pekerjaan Tanah dan Urugan Rp 49.554.490,87
III PEKERJAAN STRUKTUR & BETON
1 Pasangan Aanstamping Batu Karang/gunung m3 40,67 Rp 301.660,79 Rp 12.267.035,94
2 Pasangan Pondasi Menerus batu Karang/Gunung 1 pc : 5 psr m3 231,61 Rp 622.057,00 Rp 144.074.838,56
Pekerjaan Beton Mutu K-250 (Mix Design = PC 384kg, PSR 692kg, KRL 1039kg, air 215 ltr)
3 Foot Plat tebal Type 1, t=30 cm, L=150 cm beton bertulang (K250) m3 13,50 Rp 3.670.786,26 Rp 49.555.614,57
4 Foot Plat tebal Type 2, t=30 cm, L=120 cm beton bertulang (K250) m3 6,00 Rp 2.860.511,60 Rp 17.163.069,59
5 Kolom Pedestal ukuran 30x30 cm, beton bertulang (K250) m3 3,96 Rp 4.243.543,46 Rp 16.804.432,08
6 Kolom Pedestal ukuran 40x40 cm, beton bertulang (K250) m3 6,72 Rp 4.881.850,35 Rp 32.806.034,36
7 Kolom Pedestal ukuran 30x60 cm, beton bertulang (K250) m3 0,76 Rp 4.460.375,11 Rp 3.372.043,58
8 Sloof 25/35 cm beton bertulang (K250) untuk 2 lantai m3 8,40 Rp 3.468.887,88 Rp 29.138.658,19
9 Sloof 20/25 cm beton bertulang (K250) untuk 1 lantai m3 6,60 Rp 3.803.565,79 Rp 25.103.534,23
10 Plat Lantai dasar Gedung, t = 8 cm beton bertulang (K175) m3 18,48 Rp 3.407.556,14 Rp 62.971.637,48
11 Kolom Praktis 15/15 cm beton bertulang (K175) m3 2,13 Rp 6.818.288,80 Rp 14.531.137,08
12 Kolom Utama (K1) 40x40 cm beton bertulang (K250) m3 11,52 Rp 4.779.391,90 Rp 55.058.594,73
13 Kolom Utama (K2) 40x40 cm beton bertulang (K250) pada lantai 2 m3 8,18 Rp 4.315.289,47 Rp 35.281.806,74
14 Kolom utama (K3) 30x30 cm beton bertulang (K250) pada 1 lantai m3 6,66 Rp 4.243.543,46 Rp 28.261.999,41
15 Kolom Utama (K4) 30x60 cm beton bertulang (K250) m3 3,74 Rp 4.570.588,38 Rp 17.112.282,89
16 Kolom Tandon (K5) 30x30 cm beton bertulang (K250) m3 1,38 Rp 4.903.975,30 Rp 6.752.773,99
17 Kolom Teras (K6) 20x40 cm beton bertulang (K250) m3 5,32 Rp 4.315.289,47 Rp 22.957.340,00
18 Balok Induk 30x40 cm Beton bertulang (K250) m3 8,40 Rp 4.410.897,47 Rp 37.051.538,73
19 Balok Anak 20x30 cm Beton bertulang (K250) m3 1,20 Rp 5.205.524,44 Rp 6.246.629,33
20 Balok Teras 20x35 cm Beton bertulang (K250) m3 2,94 Rp 4.257.907,80 Rp 12.518.248,92
21 Balok Tangga 20x30 cm Beton bertulang (K250) m3 0,19 Rp 5.205.524,44 Rp 999.460,69
22 Anak Tangga Beton bertulang (K250) m3 0,68 Rp 6.688.051,44 Rp 4.514.434,72
23 Balok Latei 15x15 cm Beton bertulang (K175) m3 1,07 Rp 5.377.639,14 Rp 5.730.412,27
24 Ringbalk 15x20 cm Beton bertulang (K175) pada dinding KM/WC m3 0,78 Rp 4.762.667,09 Rp 3.714.880,33
25 Ringbalk 25/30 cm untuk struktur lantai 1 dan lantai 2, beton bertulang (K250) m3 16,09 Rp 4.068.032,71 Rp 65.444.476,24

26 Plat Lantai 2, t = 13 cm beton bertulang (K250) m3 14,52 Rp 4.408.168,74 Rp 64.024.242,78


27 Plat Tangga, t = 13 cm beton bertulang (K250) m3 1,40 Rp 4.408.168,74 Rp 6.160.415,81
28 Plat Konsol L=50 cm Tebal 10 cm, plat Tandon Air t = 13 cm, L=150 cm beton m3 3,80 Rp 3.822.955,31 Rp 14.527.230,19
bertulang (K250)
29 Plat Meja Beton beton bertulang (K175), Loby, wastafel dan pantry m3 0,65 Rp 3.748.903,22 Rp 2.451.782,70
30 Plat teras depan, t=13 cm beton bertulang (K250) m3 1,65 Rp 4.473.453,17 Rp 7.375.829,59
Sub Total ( III) Pekerjaan Struktur & Beton Rp 803.972.415,76
IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN
1 Pasangan dinding Batako, 1 PC: 4 Psr m2 545,48 Rp 165.716,34 Rp 90.394.163,08
2 Pasangan Batu Andesit Alur Lurus 15x30 cm pada Kaki kolom teras m2 7,80 Rp 271.390,79 Rp 2.116.848,16
3 Plesteran dinding batako t=15mm, 1 Pc : 4 Psr m2 1.090,95 Rp 55.560,52 Rp 60.613.772,71
4 Plesteran pondasi, t=15mm, 1 Pc : 4 Psr m2 41,92 Rp 55.560,52 Rp 2.329.096,83
5 Acian dinding (termasuk Seluruh Beton, dan Pondasi) m2 1.513,46 Rp 33.211,75 Rp 50.264.671,76
Sub Total ( IV) Pekerjaan Dinding dan Plesteran Rp 205.718.552,55
V PEKERJAAN PASANGAN KERAMIK
1 Lantai kerja dalam gedung t=5 cm, dan lantai kerja footplat t= 10 cm (beton K- m3 26,31 Rp 769.995,04 Rp 20.261.841,92
100) 1 pc : 3 psr : 5 krl
2 Pas. Lantai Keramik 60x60 cm Unpolish m2 61,70 Rp 222.739,88 Rp 13.743.050,60
3 Pas. Lantai Keramik 60x60 cm Polish m2 339,80 Rp 222.739,88 Rp 75.687.011,22
4 Plint Keramik 10x60 cm (rata dalam tembok) koridor dan tangga lantai 1 m1 17,50 Rp 26.999,85 Rp 472.497,41
5 Pas. Lantai GRANIT TILE 60x60 cm Polish setara Essenza (Ruangan lantai 2 dan m2 105,00 Rp 301.939,88 Rp 31.703.687,40
seluruh meja beton)
6 Plint GRANIT 10x60 cm (rata dalam tembok) warna hitam corak emas/silver m1 64,15 Rp 79.733,85 Rp 5.114.926,61
lantai 2
7 Keramik 25x40 cm Dinding Km/Wc dan Pantry (bermotif) m2 77,70 Rp 147.968,70 Rp 11.497.167,99
8 Keramik Dinding 30x60 cm pada tembok (semua ruangan Gudang Obat lantai 1) m2 139,23 Rp 142.198,82 Rp 19.798.342,11

9 Keramik List 10x30 cm pada tembok (semua ruangan Gudang Obat lantai 1) m1 77,35 Rp 29.315,35 Rp 2.267.542,48
bermotif
10 Keramik 20x20 cm wafel untuk lantai Km/Wc, (Keramik bermotif) m2 35,30 Rp 140.296,20 Rp 4.952.455,86
11 Keramik List 10x25 cm untuk Dinding Km/Wc (Keramik bermotif) m1 51,80 Rp 31.784,03 Rp 1.646.412,60
12 Pas. Step Noizing keramik 10x60 cm pada semua tangga m1 32,40 Rp 33.885,03 Rp 1.097.874,87
Sub Total ( V) Pekerjaan pasangan Keramik Rp 188.242.811,07
VI PEKERJAAN PLAFON DAN ATAP
1 Pek. Kuda2, baja ringan C 75/75 mm dan reng butten 30/0.45 (baja ringan) M2 488,86 Rp 231.229,17 Rp 113.038.458,07
2 Pek. Penutup Atap Zincalume 0.30 mm m2 488,86 Rp 85.509,82 Rp 41.802.244,68
3 Pek. Nok Bubungan Zincalume m1 54,18 Rp 33.489,94 Rp 1.814.379,37
4 Pek. Talang seng plat BJLS 0,30 mm m1 4,00 Rp 93.731,86 Rp 374.927,43
5 Pek. Kalsiplank 8 Corak Jati, uk. 0.08/20 m1 120,00 Rp 62.504,20 Rp 7.500.504,00
6 Penutup plafond Kalsiboard tb 6 mm & Rangka Hollow 4x4 cm m2 202,34 Rp 194.383,44 Rp 39.331.545,65
7 Penutup plafond Gypsum tb 9 mm & Rangka Hollow 4x4 cm m2 417,00 Rp 178.367,44 Rp 74.379.223,31
8 Pasang List Plafond Profil Gypsum (Lebar ± 15 cm) m1 552,00 Rp 19.162,21 Rp 10.577.537,52
Sub Total ( VI) Pekerjaan Plafond & Atap Rp 288.818.820,04
VII PEKERJAAN KUSEN ALUMINIUM, BINGKAI, PARTISI, KACA, PENGGANTUNG & PENGUNCI
1 Pek. Kusen dan Daun Pintu Jendela Boven Alumunium Type PJ (pintu Kaca Unit 1,00 Rp 12.690.000,00 Rp 12.690.000,00
Tempered 12 mm Lengkap aksesories, Jendela Kaca Mati Bening 5 mm)
2 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm Type P1 Unit 2,00 Rp 3.580.000,00 Rp 7.160.000,00
3 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm Type P2 Unit 1,00 Rp 4.780.000,00 Rp 4.780.000,00
4 Pek. Kusen Alumunium dan Daun Pintu Panil Kayu Jati Type P3 Unit 1,00 Rp 2.100.000,00 Rp 2.100.000,00
5 Pek. Kusen Alumunium dan Daun Pintu Kaca Es 5 mm Type P4 Unit 5,00 Rp 1.810.000,00 Rp 9.050.000,00
6 Pek. Kusen Alumunium dan Daun Pintu double Teakwood rangka papan 3cm, Unit 2,00 Rp 1.840.000,00 Rp 3.680.000,00
(pintu shaft) Type P5
7 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm Type P6 Unit 1,00 Rp 1.990.000,00 Rp 1.990.000,00
8 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm dan Partisi Kaca Unit 4,00 Rp 7.890.000,00 Rp 31.560.000,00
bening 5 mm, Kalsibaord 6 mm dobel luar dalam Type DP1
9 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm dan Partisi Kaca Unit 2,00 Rp 7.560.000,00 Rp 15.120.000,00
bening 5 mm, Kalsibaord 6 mm dobel luar dalam Type DP2
10 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm dan Partisi Kaca Unit 1,00 Rp 4.160.000,00 Rp 4.160.000,00
bening 5 mm, Kalsibaord 6 mm dobel luar dalam Type DP6
11 Pek. Kusen Alumunium dan Daun Pintu Kaca Bening 8 mm dan Partisi Kaca Unit 2,00 Rp 6.720.000,00 Rp 13.440.000,00
bening 5 mm, Type DP8
12 Pek. Kusen dan Daun Jendela Alumuinium Type J1 (Kaca Bening 5 mm) Unit 5,00 Rp 2.730.000,00 Rp 13.650.000,00
13 Pek. Kusen dan Daun Jendela Alumunium Type J2 (Kaca Bening 5 mm) Unit 2,00 Rp 4.350.000,00 Rp 8.700.000,00
14 Pek. Kusen dan Boven Alumunium Type BV (Kaca Bening 5 mm) Unit 10,00 Rp 930.000,00 Rp 9.300.000,00
15 Pek. Kusen dan Boven Alumunium Type BV2 (Daun Boven Kaca Bening 5 mm) Unit 4,00 Rp 1.460.000,00 Rp 5.840.000,00
16 Pek. Kusen dan Boven Alumunium Type BV3 (Daun Boven Kaca Bening 5 mm) Unit 1,00 Rp 820.000,00 Rp 820.000,00
Sub Total ( VII ) Pekerjaan Kusen, Bingkai dan Kaca Rp 144.040.000,00
VIII PEKERJAAN PENGECATAN
1 Pengecatan dinding baru (setara Catylac) m2 1.513,46 Rp 19.332,61 Rp 29.259.141,60
2 Pengecatan plafond dan Dinding Partisi m2 657,77 Rp 19.332,61 Rp 12.716.314,22
sub total (VIII) Pekerjaan Pengecatan Rp 41.975.455,81
IX PEKERJAAN WATERPROFING
1 Waterproofing Semen Waterbise. Plat Lantai 2 menyeluruh dan Dinding setinggi m2 87,26 Rp 63.389,15 Rp 5.531.337,23
30cm, areal Toilet Lt 2 dan Plat Teras, sebelum Plaster/Pasang keramik.
sub total (VIII) Pekerjaan Pengecatan Rp 5.531.337,23
X PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A PEKERJAAN INSTALASI TITIK LAMPU DAN STOP KONTAK
1 Pas. Lampu Philips LED Downlight inbow 18 Watt bh 31,00 Rp 211.629,00 Rp 6.560.499,00
2 Pas. Lampu SL 18 w setara philips bh 14,00 Rp 46.629,00 Rp 652.806,00
3 Pas. Lampu Downlight inbow LED Philips 3,5W Putih bh 11,00 Rp 107.129,00 Rp 1.178.419,00
4 Stop kontak 200 A, 1 ph bh 45,00 Rp 33.814,55 Rp 1.521.654,75
5 Stop kontak AC bh 3,00 Rp 48.829,55 Rp 146.488,65
6 Saklar tunggal bh 7,00 Rp 31.504,55 Rp 220.531,85
7 Saklar ganda bh 22,00 Rp 37.279,55 Rp 820.150,10
8 Instalasi titik penerangan dari PANEL ke TITIK lampu titik 81,00 Rp 145.335,30 Rp 11.772.159,30
9 Instalasi titik stop kontak dari PANEL POWER titik 51,00 Rp 145.335,30 Rp 7.412.100,30
10 Sambungan Daya PLN 10 Kva. (termasuk penambahan 3 Tiang dan seluruh Ls 1,00 Rp 30.000.000,00 Rp 30.000.000,00
instalasi Kabel Twisted SR 4x70 mm sampai ke KWH Meter dan sampai ke Panel),
sumber Sambungan Daya langsung dari Tiang Listrik PLN

11 Pas. Panel Penerangan dan Power, PANEL MDP+ PP LOBY (AMF-ATS) PANEL 1 Unit 1,00 Rp 8.000.000,00 Rp 8.000.000,00
Lantai 1
Wall mounted, tebal pelat 1,8 mm, cat bakar
Kebutuhan Komponen Panel :
1 buah x MCCB 100 A, 3 P, 36 kA
10 buah x MCB 6 A, 1 P, 6 kA
10 buah x MCB 10 A, 1 P, 6 kA
1 buah x ATS digital controller ex ASCO seri 7000
3 buah x fuse 2 A + fuse holder
3 buah x pilot lamp
2 buah lot busbar 40 A full neutral, 5 bus
1 buah lot internal wiring + aksesori
1 unit Panel 60 (L) x 20 (D) x 80 (T) cm
1 lot pentanahan
setiap Panel dilengkapi dengan papan info diagram Panel
12 Pas. Panel Penerangan dan Power, PANEL PP PANTRY (AMF-ATS) PANEL 2 Lantai 2 Unit 1,00 Rp 4.000.000,00 Rp 4.000.000,00

Wall mounted, tebal pelat 1,8 mm, cat bakar


Kebutuhan Komponen Panel :
1 buah x MCCB 16 A, 3 P, 36 kA
6 buah x MCB 6 A, 1 P, 6 kA'
5 buah x MCB 10 A, 1 P, 6 kA'
3 buah x fuse 2 A + fuse holder
3 buah x pilot lamp
1 buah lot busbar 40 A full neutral, 5 bus
1 buah lot internal wiring + aksesori
1 unit panel 50 (L) x 25 (D) x 60 (T) cm
1 lot instalasi kabel grounding
setiap Panel dilengkapi dengan papan info diagram Panel
sub total (A) Pekerjaan Instalasi Titik Lampu dan Stop Kontak Rp 72.284.808,95
B PEKERJAAN TATA UDARA
1 Pekerjaan Exhaust Fan
Pengadaan dan pemasangan Exhaust Fan c/w Accessories dan Material Bantu
a Type Axial Kap. 100 CFM, 125 w / 1P c/w EAG di Toilet Unit 4,00 Rp 552.629,00 Rp 2.210.516,00
b Type Axial Wall Kap. 300 CFM, 125 w / 1P c/w EAG di Ruangan Unit 4,00 Rp 1.102.629,00 Rp 4.410.516,00
Pekerjaan Kabel Power Exhaust Fan
Exhaust Fan Type Axial Wall Kap. 300 CFM, 125 w / 1P c/w EAG
c Kabel Power NYM 3 x 2,5 mm2 M 20,00 Rp 17.010,00 Rp 340.200,00
d Pekerjaan Kabel Power untuk semua unit Exhaust Fan di area toilet di gabung M 8,00 Rp 17.010,00 Rp 136.080,00
dengan instalasi lampu yang di toilet ( NYM 3 x 2,5 mm2 )
sub total (1) Pekerjaan Exhaust Fan Rp 7.097.312,00
2 PEKERJAAN AIR CONDITIONER (AC) SPLIT INVERTER
a Pekerjaan Peralatan Utama AC
Pengadaan dan pemasangan unit AC Inverter, Preon ramah lingkungan, lengkap
dengan penggantung dan accessories,dan berfungsi dengan baik
Tipe Indoor : Wall Mounted Splite Unit 3,00 Rp 6.014.126,25 Rp 18.042.378,75
Kapasitas Pendinginan : 9.000 BTU/H (1 PK)
Daya Listrik : 960 VA/220V/1ph/50Hz
b Pekerjaan Pipa Reffrigerant
Pengadaan dan pemasangan pipa Refrigerant, yang incluwed dengan Unit A
termasuk dalam hitungan
Pipa Tembaga sesuai dengan Kapasitas AC yang digunakan
dan terbungkus Insullation t: 25 mm (Berlaku pula untuk instalasi
dalam dinding bata) dan dilapisi perekat isolasi ( melapisi insulation )
- Pipa Liquit Ø 6,4 mm M 36,00 Rp 45.010,00 Rp 1.620.360,00
- Pipa Gas Ø 9,5 mm M 36,00 Rp 65.010,00 Rp 2.340.360,00

c Pekerjaan Pemipaan Drain dengan isolasi tebal 1", density 24 Kg/m3 c/w Fitting-
Fitting
- Pipa PVC dia 20 mm M 42,00 Rp 5.010,00 Rp 210.420,00
d Pekerjaan Kabel Power Dengan Kabel Kontrol
instalasi kabel power dan control dalam pvc conduit c/w accessories
- IU-1.2 R. Teknisi, Type Split Wall Kap. 9.000 BTUH, NYM 3 x 2,5 mm2
M 48,00 Rp 17.010,00 Rp 816.480,00
- Testing Commissioning LS 1,00 Rp 200.000,00 Rp 200.000,00
sub total (2) Pekerjaan Tata Udara Rp 23.229.998,75
C PEKERJAAN PENANGKAL PETIR
1 Pek. Penangkal Petir Electrostatik (Lighting Protection) Flash Vectron/ setara Unit 1,00 Rp 10.500.390,00 Rp 10.500.390,00
Radius 100 M
2 Instalasi Penangkal Petir (Kabel BC 50mm2 +Klem) M 20,00 Rp 150.390,00 Rp 3.007.800,00
3 Bak Kontrol Unit 1,00 Rp 500.000,00 Rp 500.000,00
4 Grounding Unit 1,00 Rp 4.000.390,00 Rp 4.000.390,00
sub total (D) Pekerjaan Penangkal Petir Rp 18.008.580,00
D PEKERJAAN CCTV
1 Monitor 32 " Full HD Unit 1,00 Rp 4.500.390,00 Rp 4.500.390,00
2 Harddisk 4 TB Unit 1,00 Rp 3.300.390,00 Rp 3.300.390,00
3 UPS (Uninterruptible Power Supply) Unit 1,00 Rp 2.000.390,00 Rp 2.000.390,00
4 Pasang DVR CCTV Hikvision Unit 1,00 Rp 5.500.390,00 Rp 5.500.390,00
5 Pasang Kamera CCTV Indoor Unit 4,00 Rp 1.100.390,00 Rp 4.401.560,00
6 Pasang Kamera CCTV Outdoor Unit 4,00 Rp 1.700.390,00 Rp 6.801.560,00
7 Pasang Adaptor Unit 8,00 Rp 60.390,00 Rp 483.120,00
8 Pasang Power Suplay Unit 2,00 Rp 400.390,00 Rp 800.780,00
9 Konektor RF LS 1,00 Rp 550.000,00 Rp 550.000,00
10 Instalasi CCTV kabel Coaxial (Kabel Data + Power) RG-59 Titik 8,00 Rp 100.000,00 Rp 800.000,00
11 Testing Commissioning Ls 1,00 Rp 100.000,00 Rp 100.000,00
sub total (B) Pekerjaan Fire Alarm Rp 29.238.580,00
XI PEKERJAAN SANITASI
A INSTALASI AIR BERSIH DAN PEMBUANGAN
1 Pasangan Bak Air Fyberglass 1 m3 Unit 5,00 Rp 815.012,22 Rp 4.075.061,10
2 Pasangan Kloset Jongkok (toto/setara) Unit 2,00 Rp 862.080,34 Rp 1.724.160,68
3 Pasangan Closet Duduk porselen putih (Toto/setara) komplet box dan jet washer Unit 3,00 Rp 4.487.612,36 Rp 13.462.837,08

4 Pasang Kran Air Ø 1/2" (type madya-vernekel) termasuk pada Tempat Cuci Tangan Bh 9,00 Rp 92.709,32 Rp 834.383,88
5 Pasang Tempat Sabun Porselen pada setiap ruang KM/WC Bh 5,00 Rp 200.000,00 Rp 1.000.000,00
6 Pasang Floor Drain Bh 9,00 Rp 28.413,00 Rp 255.717,00
7 Pasang Wastafel setara TOTO lengkap kran air Unit 5,00 Rp 2.120.922,32 Rp 10.604.611,60
8
9 Pasang Bak cuci Stainlees (Kichen Zink) single bak Unit 1,00 Rp 976.646,00 Rp 976.646,00
10 Pengadaan dan pemasangan Profil Tank Tangki Air Stainless Steel kap. 1100 liter Unit 1,00 Rp 6.000.200,00 Rp 6.000.200,00

11 Pasang Pipa GIP Ø 1/2" Med. A instalasi air bersih (lengkap ascesories) termasuk M1 60,00 Rp 50.013,70 Rp 3.000.822,00
pada areal taman
12 Pasang Pipa GIP Ø 1" Med A. instalasi air bersih (lengkap ascesories) M1 12,00 Rp 81.177,80 Rp 974.133,60
13 Pasang Pipa PVC Ø 2" instalasi air kotor ke peresapan (lengkap ascesories) M1 60,00 Rp 39.174,30 Rp 2.350.458,00
14 Pasang Pipa PVC Ø 4" instalasi Limbah Padat (lengkap ascesories) M1 60,00 Rp 71.075,95 Rp 4.264.557,00
sub total (A) Pekerjaan Sanitasi Rp 49.523.587,94
B PEKERJAAN SEPTIKTANK DAN PERESAPAN
a PEKERJAAN TANAH DAN URUGAN
1 Galian tanah M3 15,44 Rp 38.810,35 Rp 599.183,29
2 Urugan kembali tanah galian M3 5,15 Rp 48.290,00 Rp 248.512,41
3 Urugan Batu pada peresapan M3 0,73 Rp 99.890,00 Rp 72.819,81
4 Urugan Kerikil pada peresapan M3 0,55 Rp 236.440,00 Rp 129.273,57
5 Urugan Pasir pada peresapan M3 0,36 Rp 121.440,00 Rp 44.264,88
6 Urugan Ijuk pada peresapan M3 0,36 Rp 64.890,00 Rp 23.652,41
b PEKERJAAN BETON
1 Lantai kerja dan Rabat Beton t=15- 20 cm (beton K-100) 1 pc : 3 psr : 5 krl M3 0,87 Rp 769.995,04 Rp 673.360,66
2 Plat Septiktank Beton Bertulang t = 10 cm M3 0,69 Rp 3.748.903,22 Rp 2.588.242,78
3 Plat Peresapan Beton Bertulang t = 10 cm M3 0,40 Rp 3.748.903,22 Rp 1.499.561,29
4 Kolom praktis 15x15 cm beton bertulang pada Septiktank dan Peresapan M3 0,36 Rp 6.818.288,80 Rp 2.454.583,97
c PEKERJAAN PASANGAN DINDING
1 Pasangan Dinding Batako 1pc : 4 psr M2 22,89 Rp 165.716,34 Rp 3.793.661,36
2 Plesteran dinding t=15mm, 1 Pc : 4 Psr M2 26,50 Rp 55.560,52 Rp 1.472.437,01
3 Acian dinding M2 26,50 Rp 33.211,75 Rp 880.161,19
4 Susunan Bata Merah pada Peresapan M2 9,50 Rp 45.000,00 Rp 427.680,00
d PEKERJAAN PERPIPAAN
1 Pasangan Pipa Hawa BH 1,00 Rp 150.000,00 Rp 150.000,00
sub total (B) Pekerjaan Septiktank dan Peresapan Rp 15.057.394,63
C PEKERJAAN GROUNDTANK (1 UNIT)
a PEKERJAAN TANAH DAN URUGAN
1 Galian tanah dengan Alat Berat M3 18,00 Rp 38.810,35 Rp 698.586,30
2 Urugan kembali tanah galian M3 3,00 Rp 48.290,00 Rp 144.870,00
3 Urugan Pasir Bawah Lantai M3 0,90 Rp 187.118,80 Rp 168.406,92
b PEKERJAAN BETON
1 Lantai kerja dan Rabat Beton t=10 cm (beton K-100) 1 pc : 3 psr : 5 krl M3 0,90 Rp 769.995,04 Rp 692.995,53
2 Kolom 20x20 cm Groundtank Beton Bertulang M3 0,70 Rp 4.477.593,18 Rp 3.152.225,60
3 Plat Lantai Groundtank Beton Bertulang t = 20 cm M3 0,60 Rp 4.111.178,19 Rp 2.466.706,92
4 Plat Dinding dan Plat Atas Groundtank Beton Bertulang t = 15 cm M3 3,53 Rp 4.111.178,19 Rp 14.504.236,67
c PEKERJAAN PASANGAN KERAMIK
1 Pasangan Lantai dan Dinding Keramik 20x25 cm M2 24,75 Rp 147.968,70 Rp 3.662.225,33
d PEKERJAAN PERPIPAAN DAN AKSESORIES
1 Pasangan Pipa Galv. Ø 1 1/2" pipa dari groundtank ke Profil tank M 16,00 Rp 108.345,00 Rp 1.733.520,00
2 Pasangan Pipa Penguras Galv. Ø 1 1/2" M 3,00 Rp 108.345,00 Rp 325.035,00
3 Tangga pipa Galv. Dia. 1,5" Unit 1,00 Rp 400.000,00 Rp 400.000,00
4 Manholle Plat Eser 2 mm Unit 1,00 Rp 350.000,00 Rp 350.000,00
5 Filter Air BH 1,00 Rp 100.000,00 Rp 100.000,00
6 Pompa Air JetPump head 50 meter Unit 1,00 Rp 2.500.390,00 Rp 2.500.390,00
sub total (D) Pekerjaan Groundtank Rp 30.899.198,26
XII PEKERJAAN LAIN-LAIN
1 Pengadaan Cermin Rias, 70 x 120 cm (pada Wastafel ) Unit 2,00 Rp 250.280,00 Rp 500.560,00
2 Pasangan Handrill Tangga pipa Hollow 2x4 cm sekaligus Cat kilap M1 104,00 Rp 29.348,26 Rp 3.052.218,69
3 Pasangan Handrill Tangga pipa Hollow 4x4 cm sekaligus Cat kilap M1 40,68 Rp 41.300,31 Rp 1.680.096,48
4 Pasangan Handrill Pagar pada Ruang Tandon Lantai 2 pipa Hollow 2x4 cm M1 39,04 Rp 29.348,26 Rp 1.145.755,94
sekaligus Cat kilap
6 Pembersihan Kembali seluruh pekerjaan Ls 1,00 Rp 1.000.000,00 Rp 1.000.000,00
sub total (XIII) Pekerjaan Lain-lain Rp 7.378.631,11
Analisa SNI 2016

ANALISA HARGA SATUAN ITEM PEKERJAAN

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE


LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.4 Pengukuran dan pemasangan 1 m' bouwplank

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,100 78.000,00 7.800,00
Tukang Kayu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 17.840,00
B BAHAN
Kayu 5/7 m3 0,012 2.604.770,00 31.257,24
Paku 2"-3" kg 0,020 22.010,00 440,20
Kayu Papan 3/20 m3 0,007 2.604.770,00 18.233,39
JUMLAH HARGA BAHAN 49.930,83
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 67.770,83
E Overhead & Profit (10%) 10% X D 6.777,08
F Harga Satuan Pekerjaan (D+E) 74.547,91

A. 2.2.1.9 (K3) Pembersihan 1 m2 Lapangan dan Perataan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,100 78.000,00 7.800,00
Mandor L.04 OH 0,050 98.000,00 4.900,00
JUMLAH TENAGA KERJA 12.700,00
B BAHAN

JUMLAH HARGA BAHAN 0


C PERALATAN

JUMLAH HARGA ALAT 0


D Jumlah (A+B+C) 12.700,00
E Overhead & Profit (10%) 10% X D 1.270,00
F Harga Satuan Pekerjaan (D+E) 13.970,00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m 3 tanah biasa sedalam 1 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,750 78.000,00 58.500,00
Mandor L.04 OH 0,025 98.000,00 2.450,00
JUMLAH TENAGA KERJA 60.950,00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 60.950,00
E Overhead & Profit (10%) 10% X D 6.095,00
F Harga Satuan Pekerjaan (D+E) 67.045,00
Analisa SNI 2016

A.2.3.1.9 Pengurugan kembali 1 m 3 galian tanah

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,500 78.000,00 39.000,00
Mandor L.04 OH 0,050 98.000,00 4.900,00
JUMLAH TENAGA KERJA 43.900,00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 43.900,00
E Overhead & Profit (10%) 10% X D 4.390,00
F Harga Satuan Pekerjaan (D+E) 48.290,00

Pengurugan 1 m 3 dengan pasir urug

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Mandor L.04 OH 0,010 98.000,00 980,00
JUMLAH TENAGA KERJA 24.380,00
B BAHAN
Pasir urug m3 1,2 121.440,00 145.728,00
JUMLAH HARGA BAHAN 145.728,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 170.108,00
E Overhead & Profit (10%) 10% X D 17.010,80
F Harga Satuan Pekerjaan (D+E) 187.118,80

Pemasangan 1 m 2 Geotekstil Woven 200 gr

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Mandor L.04 OH 0,0025 98.000,00 245,00
JUMLAH TENAGA KERJA 2.195,00
B BAHAN
Geotekstil Woven m2 1,000 25.040,00 25.040,00
JUMLAH HARGA BAHAN 25.040,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 27.235,00
E Overhead & Profit (10%) 10% X D 2.723,50
F Harga Satuan Pekerjaan (D+E) 29.958,50

A.2.3.1.14. Pengurugan 1 m 3 dengan Sirtu padat

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,25 78.000,00 19.500,00
Mandor L.04 OH 0,025 98.000,00 2.450,00
JUMLAH TENAGA KERJA 21.950,00
B BAHAN
Sirtu m3 1,2 64.890,00 77.868,00
JUMLAH HARGA BAHAN 77.868,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 99.818,00
E Overhead & Profit (10%) 10% X D 9.981,80
F Harga Satuan Pekerjaan (D+E) 109.799,80
Analisa SNI 2016

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1. Pemasangan 1 m 3 pondasi batu Kali/Karang/Gunung campuran 1SP : 3 PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,500 78.000,00 117.000,00
Tukang Batu L.02 OH 0,750 86.000,00 64.500,00
Kepala Tukang L,03 OH 0,075 95.000,00 7.125,00
Mandor L.04 OH 0,075 98.000,00 7.350,00
JUMLAH TENAGA KERJA 195.975,00
B BAHAN
Batu Kali/Karang/Gunung m3 1,200 99.890,00 119.868,00
Semen Portland kg 202,000 1.250,00 252.500,00
Pasir pasang m3 0,485 146.440,00 71.023,40
JUMLAH HARGA BAHAN 443.391,40
C PERALATAN

JUMLAH HARGA ALAT 0


D Jumlah (A+B+C) 639.366,40
E Overhead & Profit (10%) 10% X D 63.936,64
F Harga Satuan Pekerjaan (D+E) 703.303,04

A.3.2.1.2. Pemasangan 1 m3 pondasi batu Kali/Karang/Gunung campuran 1SP : 4 PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,500 78.000,00 117.000,00
Tukang Batu L.02 OH 0,750 86.000,00 64.500,00
Kepala Tukang L,03 OH 0,075 95.000,00 7.125,00
Mandor L.04 OH 0,075 98.000,00 7.350,00
JUMLAH TENAGA KERJA 195.975,00
B BAHAN
Batu Kali/Karang/Gunung m3 1,200 99.890,00 119.868,00
Semen Portland kg 163,000 1.250,00 203.750,00
Pasir pasang m3 0,520 146.440,00 76.148,80
JUMLAH HARGA BAHAN 399.766,80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 595.741,80
E Overhead & Profit (10%) 10% X D 59.574,18
F Harga Satuan Pekerjaan (D+E) 655.315,98

A.3.2.1.3. Pemasangan 1 m3 pondasi batu Kali/Karang/Gunung campuran 1SP : 5 PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,500 78.000,00 117.000,00
Tukang Batu L.02 OH 0,750 86.000,00 64.500,00
Kepala Tukang L,03 OH 0,075 95.000,00 7.125,00
Mandor L.04 OH 0,075 98.000,00 7.350,00
JUMLAH TENAGA KERJA 195.975,00
B BAHAN
Batu Kali/Karang/Gunung m3 1,200 99.890,00 119.868,00
Semen Portland kg 136,000 1.250,00 170.000,00
Pasir pasang m3 0,544 146.440,00 79.663,36
JUMLAH HARGA BAHAN 369.531,36
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 565.506,36
E Overhead & Profit (10%) 10% X D 56.550,64
F Harga Satuan Pekerjaan (D+E) 622.057,00
Analisa SNI 2016

A.3.2.1.9. (K3) Pemasangan 1 m 3 pondasi batu kosong (anstamping)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,780 78.000,00 60.840,00
Tukang Batu L.02 OH 0,390 86.000,00 33.540,00
Kepala Tukang L,03 OH 0,039 95.000,00 3.705,00
Mandor L.04 OH 0,039 98.000,00 3.822,00
JUMLAH TENAGA KERJA 101.907,00
B BAHAN
Batu Kali/Karang/Gunung m3 1,200 99.890,00 119.868,00
3
Pasir urug m 0,432 121.440,00 52.462,08
JUMLAH HARGA BAHAN 172.330,08
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 274.237,08
E Overhead & Profit (10%) 10% X D 27.423,71
F Harga Satuan Pekerjaan (D+E) 301.660,79

A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c= 7,4 Mpa (K-100) w/c = 0.87

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,2 78000 93.600,00
Tukang Batu L.02 OH 0,2 86000 17.200,00
Kepala Tukang L,03 OH 0,02 95000 1.900,00
Mandor L.04 OH 0,06 98000 5.880,00
JUMLAH TENAGA KERJA 118.580,00
B BAHAN
Semen Portland kg 230 1.250,00 287.500,00
Pasir beton kg 893 104,60 93.407,80
Kerikil kg 1027 193,29 198.507,69
Air Liter 200 10,00 2.000,00
JUMLAH HARGA BAHAN 581.415,49
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 699.995,49
E Overhead & Profit (10%) 10% X D 69.999,55
F Harga Satuan Pekerjaan (D+E) 769.995,04

A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.21. Pemasangan 1 m2 dinding batako (10x20x40 cm) campuran 1SP : 4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Tukang Batu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 34.420,00
B BAHAN
Batako bh 12,500 3.540,00 44.250,00
Semen Portland kg 12,130 1.250,00 15.162,50
Pasir pasang m3 0,388 146.440,00 56.818,72
JUMLAH HARGA BAHAN 116.231,22
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 150.651,22
E Overhead & Profit (10%) 10% X D 15.065,12
F Harga Satuan Pekerjaan (D+E) 165.716,34
Analisa SNI 2016

A.4.4.2.3. Pemasangan 1 m2 plesteran campuran 1SP : 3PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Tukang Batu L.02 OH 0,150 86.000,00 12.900,00
Kepala Tukang L,03 OH 0,015 95.000,00 1.425,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 39.195,00
B BAHAN
Semen Portland kg 7,776 1.250,00 9.720,00
Pasir pasang m3 0,023 146.440,00 3.368,12
JUMLAH HARGA BAHAN 13.088,12
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 52.283,12
E Overhead & Profit (10%) 10% X D 5.228,31
F Harga Satuan Pekerjaan (D+E) 57.511,43

A.4.4.2.4. Pemasangan 1 m2 plesteran campuran 1SP : 4PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Tukang Batu L.02 OH 0,150 86.000,00 12.900,00
Kepala Tukang L,03 OH 0,015 95.000,00 1.425,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 39.195,00
B BAHAN
Semen Portland kg 6,240 1.250,00 7.800,00
3
Pasir pasang m 0,024 146.440,00 3.514,56
JUMLAH HARGA BAHAN 11.314,56
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 50.509,56
E Overhead & Profit (10%) 10% X D 5.050,96
F Harga Satuan Pekerjaan (D+E) 55.560,52

A.4.4.2.27. Pemasangan 1 m2 acian

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,200 78.000,00 15.600,00
Tukang Batu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,010 98.000,00 980,00
JUMLAH TENAGA KERJA 26.130,00
B BAHAN
Semen Portland kg 3,250 1.250,00 4.062,50
JUMLAH HARGA BAHAN 4.062,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 30.192,50
E Overhead & Profit (10%) 10% X D 3.019,25
F Harga Satuan Pekerjaan (D+E) 33.211,75
Analisa SNI 2016

A.4.4.3.57. Pemasangan 1 m2 dinding batu alam andesit alur lurus (15x30 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,700 78.000,00 54.600,00
Tukang Batu L.02 OH 0,350 86.000,00 30.100,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,035 98.000,00 3.430,00
JUMLAH TENAGA KERJA 91.455,00
B BAHAN
Batu alam alur lurus bh 22,220 6.030,00 133.986,60
Semen Portland kg 11,750 1.250,00 14.687,50
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 155.263,90
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 246.718,90
E Overhead & Profit (10%) 10% X D 24.671,89
F Harga Satuan Pekerjaan (D+E) 271.390,79

Pemasangan 1 M2 Batu Rooster

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Tukang Batu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 34.420,00
B BAHAN
Batu Rooster/terawang bh 30,000 10.020,00 300.600,00
Pasir pasang m3 0,035 146.440,00 5.125,40
Semen PC (Portland Cement) 40 Kg Kg 14,000 1.250,00 17.500,00

JUMLAH HARGA BAHAN 323.225,40


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 357.645,40
E Overhead & Profit (10%) 10% X D 35.764,54
F Harga Satuan Pekerjaan (D+E) 393.409,94

A.4.4.3.15. Pemasangan 1 m2 lantai Granite Tile warna krem uk. 60cm x 60cm polish

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,240 78.000,00 18.720,00
Tukang Batu L.02 OH 0,120 86.000,00 10.320,00
Kepala Tukang L,03 OH 0,012 95.000,00 1.140,00
Mandor L.04 OH 0,012 98.000,00 1.176,00
JUMLAH TENAGA KERJA 31.356,00
B BAHAN
Granite Tile 60cmx60cm (Polish) bh 4,000 70.043,33 280.173,33
Semen Portland kg 9,600 1.250,00 12.000,00
Semen warna kg 1,500 9.610,00 14.415,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 313.178,13
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 344.534,13
E Overhead & Profit (10%) 10% X D 34.453,41
F Harga Satuan Pekerjaan (D+E) 378.987,55
Analisa SNI 2016

A.4.4.3.13. Pemasangan 1 m2 lantai keramik warna uk. 60cm x 60cm teksture kasar bermotif
Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,240 78.000,00 18.720,00
Tukang Batu L.02 OH 0,120 86.000,00 10.320,00
Kepala Tukang L,03 OH 0,012 95.000,00 1.140,00
Mandor L.04 OH 0,012 98.000,00 1.176,00
JUMLAH TENAGA KERJA 31.356,00
B BAHAN
Keramik 60cmx60cm(kasar) Buah 4,000 34.532,50 138.130,00
Semen Portland kg 9,600 1.250,00 12.000,00
Semen warna kg 1,500 9.610,00 14.415,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 171.134,80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 202.490,80
E Overhead & Profit (10%) 10% X D 20.249,08
F Harga Satuan Pekerjaan (D+E) 222.739,88

A.4.4.3.14. Pemasangan 1 m2 lantai keramik warna uk. 60cm x 60cm teksture halus bermotif

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,240 78.000,00 18.720,00
Tukang Batu L.02 OH 0,120 86.000,00 10.320,00
Kepala Tukang L,03 OH 0,012 95.000,00 1.140,00
Mandor L.04 OH 0,012 98.000,00 1.176,00
JUMLAH TENAGA KERJA 31.356,00
B BAHAN
Keramik 60cmx60cm(halus) Buah 4,000 34.532,50 138.130,00
Semen Portland kg 9,600 1.250,00 12.000,00
Semen warna kg 1,500 9.610,00 14.415,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 171.134,80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 202.490,80
E Overhead & Profit (10%) 10% X D 20.249,08
F Harga Satuan Pekerjaan (D+E) 222.739,88

A.4.4.3.13.1. Pemasangan 1 m2 lantai keramik warna uk. 40cm x 40cm teksture kasar & bermotif

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,125 86.000,00 10.750,00
Kepala Tukang L,03 OH 0,013 95.000,00 1.235,00
Mandor L.04 OH 0,013 98.000,00 1.274,00
JUMLAH TENAGA KERJA 32.759,00
B BAHAN
Keramik 60cmx60cm (kasar) Buah 6,630 14.183,33 94.035,50
Semen Portland kg 9,800 1.250,00 12.250,00
Semen warna kg 0,600 9.610,00 5.766,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 118.641,30
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 151.400,30
E Overhead & Profit (10%) 10% X D 15.140,03
F Harga Satuan Pekerjaan (D+E) 166.540,33
Analisa SNI 2016

Pemasangan 1 m2 dinding keramik warna uk. 30cm x 60cm teksture halus & bermotif

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,125 86.000,00 10.750,00
Kepala Tukang L,03 OH 0,013 95.000,00 1.235,00
Mandor L.04 OH 0,013 98.000,00 1.274,00
JUMLAH TENAGA KERJA 32.759,00
B BAHAN
Keramik 30cmx60cm (halus) Buah 5,550 11.442,86 63.507,86
Semen Portland kg 9,600 1.250,00 12.000,00
Semen warna kg 1,500 9.610,00 14.415,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 96.512,66
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 129.271,66
E Overhead & Profit (10%) 10% X D 12.927,17
F Harga Satuan Pekerjaan (D+E) 142.198,82

A.4.4.3.4. Pemasangan 1 m2 lantai keramik warna uk. 40cm x 40cm teksture halus & bermotif

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,125 86.000,00 10.750,00
Kepala Tukang L,03 OH 0,013 95.000,00 1.235,00
Mandor L.04 OH 0,013 98.000,00 1.274,00
JUMLAH TENAGA KERJA 32.759,00
B BAHAN
Keramik 40cmx40cm (halus) Buah 6,630 14.016,67 92.930,50
Semen Portland kg 9,800 1.250,00 12.250,00
Semen warna kg 0,600 9.610,00 5.766,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 117.536,30
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 150.295,30
E Overhead & Profit (10%) 10% X D 15.029,53
F Harga Satuan Pekerjaan (D+E) 165.324,83

A.4.4.3.9.1 Pemasangan 1 m2 lantai Granit Tile uk. 60cm x 60cm polish

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,240 78.000,00 18.720,00
Tukang Batu L.02 OH 0,120 86.000,00 10.320,00
Kepala Tukang L,03 OH 0,012 95.000,00 1.140,00
Mandor L.04 OH 0,012 98.000,00 1.176,00
JUMLAH TENAGA KERJA 31.356,00
B BAHAN
Granit 60cmx60cm (halus) bh 4,000 52.532,50 210.130,00
Semen Portland kg 9,600 1.250,00 12.000,00
Semen warna kg 1,500 9.610,00 14.415,00
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 243.134,80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 274.490,80
E Overhead & Profit (10%) 10% X D 27.449,08
F Harga Satuan Pekerjaan (D+E) 301.939,88
Analisa SNI 2016

A.4.4.3.3. Pemasangan 1 m2 lantai wafel warna uk. 20cm x 20cm teksture kasar

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,125 86.000,00 10.750,00
Kepala Tukang L,03 OH 0,013 95.000,00 1.235,00
Mandor L.04 OH 0,013 98.000,00 1.274,00
JUMLAH TENAGA KERJA 32.759,00
B BAHAN
Keramik 20/20 cm (Wafel) Buah 26,500 2.250,00 59.625,00
Semen Portland kg 10,400 1.250,00 13.000,00
Semen warna kg 1,620 9.610,00 15.568,20
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 94.783,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 127.542,00
E Overhead & Profit (10%) 10% X D 12.754,20
F Harga Satuan Pekerjaan (D+E) 140.296,20

A.4.4.3.3. Pemasangan 1 m2 Keramik uk. 25cm x 40cm teksture halus

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,125 86.000,00 10.750,00
Kepala Tukang L,03 OH 0,013 95.000,00 1.235,00
Mandor L.04 OH 0,013 98.000,00 1.274,00
JUMLAH TENAGA KERJA 32.759,00
B BAHAN
Keramik 25/40 cm teksture halus Buah 12,000 5.550,00 66.600,00
Semen Portland kg 10,400 1.250,00 13.000,00
Semen warna kg 1,620 9.610,00 15.568,20
Pasir pasang m3 0,045 146.440,00 6.589,80
JUMLAH HARGA BAHAN 101.758,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 134.517,00
E Overhead & Profit (10%) 10% X D 13.451,70
F Harga Satuan Pekerjaan (D+E) 147.968,70

A.4.4.3.28 Pemasangan 1 m1 Plint GRANIT uk. 10cm x 60cm teksture halus

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,090 78.000,00 7.020,00
Tukang Batu L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 18.575,00
B BAHAN
Plint GRANIT 10cmx60cm Buah 1,700 30.050,00 51.085,00
Semen Portland kg 1,140 1.250,00 1.425,00
Semen warna kg 0,100 9.610,00 961,00
Pasir pasang m3 0,003 146.440,00 439,32
JUMLAH HARGA BAHAN 53.910,32
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 72.485,32
E Overhead & Profit (10%) 10% X D 7.248,53
F Harga Satuan Pekerjaan (D+E) 79.733,85
Analisa SNI 2016

A.4.4.3.28.1 Pemasangan 1 m1 Plint keramik warna uk. 10cm x 30cm teksture halus
Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,090 78.000,00 7.020,00
Tukang Batu L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 18.575,00
B BAHAN
Plint Keramik 10cmx50cm Buah 3,000 1.750,00 5.250,00
Semen Portland kg 1,140 1.250,00 1.425,00
Semen warna kg 0,100 9.610,00 961,00
Pasir pasang m3 0,003 146.440,00 439,32
JUMLAH HARGA BAHAN 8.075,32
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 26.650,32
E Overhead & Profit (10%) 10% X D 2.665,03
F Harga Satuan Pekerjaan (D+E) 29.315,35

A.4.4.3.29 Pemasangan 1 m1 Plint keramik warna uk. 10cm x 60cm teksture halus

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,090 78.000,00 7.020,00
Tukang Batu L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 18.575,00
B BAHAN
Plint Keramik 10cmx60cm Buah 1,700 1.850,00 3.145,00
Semen Portland kg 1,140 1.250,00 1.425,00
Semen warna kg 0,100 9.610,00 961,00
Pasir pasang m3 0,003 146.440,00 439,32
JUMLAH HARGA BAHAN 5.970,32
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24.545,32
E Overhead & Profit (10%) 10% X D 2.454,53
F Harga Satuan Pekerjaan (D+E) 26.999,85

A.4.4.3.39. Pemasangan 1 m1 Plint keramik warna uk. 10cm x 20cm teksture halus

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,090 78.000,00 7.020,00
Tukang Batu L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 18.575,00
B BAHAN
Plint Keramik 10cmx20cm Buah 5,300 1.550,00 8.215,00
Semen Portland kg 1,140 1.250,00 1.425,00
Semen warna kg 0,025 9.610,00 240,25
Pasir pasang m3 0,003 146.440,00 439,32
JUMLAH HARGA BAHAN 10.319,57
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 28.894,57
E Overhead & Profit (10%) 10% X D 2.889,46
F Harga Satuan Pekerjaan (D+E) 31.784,03
Analisa SNI 2016

A.4.4.3.45.1 Pemasangan 1 m1 Step Noizing uk. 8cm x 40cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,090 78.000,00 7.020,00
Tukang Batu L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 18.575,00
B BAHAN
Stepnoizing 8x40 cm Buah 2,500 4.050,00 10.125,00
Semen Portland kg 1,140 1.250,00 1.425,00
Semen warna kg 0,025 9.610,00 240,25
Pasir pasang m3 0,003 146.440,00 439,32
JUMLAH HARGA BAHAN 12.229,57
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 30.804,57
E Overhead & Profit (10%) 10% X D 3.080,46
F Harga Satuan Pekerjaan (D+E) 33.885,03

A.4.4.3.64. Pemasangan 1 m2 Paving block tebal 6 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,250 78.000,00 19.500,00
Tukang Batu L.02 OH 0,500 86.000,00 43.000,00
Kepala Tukang L,03 OH 0,050 95.000,00 4.750,00
Mandor L.04 OH 0,001 98.000,00 127,40
JUMLAH TENAGA KERJA 67.377,40
B BAHAN
Paving Block hexagon (segi enam) m2 1,010 88.000,00 88.880,00
Pasir urug m3 0,050 121.440,00 6.072,00
JUMLAH HARGA BAHAN 94.952,00
C PERALATAN
% 10,000 9.495,20
JUMLAH HARGA ALAT 9.495,20
D Jumlah (A+B+C) 171.824,60
E Overhead & Profit (10%) 10% X D 17.182,46
F Harga Satuan Pekerjaan (D+E) 189.007,06

A.4.4.3.64. Pekerjaan 1 m1 Cansteen beton cetak 10x20x40 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

Galian Tanah M3 0,012 67.045,00 804,54


Pek. Pengecooran 1:2:3 M3 0,030 936.302,69 28.089,08
Pek. Plesteran 1pc : 4psr M2 0,200 55.560,52 11.112,10
Pek. Acian M2 0,200 33.211,75 6.642,35
upah kerja pasang kansteen Ls 1,000 5.000,00 5.000,00
D Jumlah (A+B+C) 51.648,07
E Overhead & Profit (10%) 10% X D 5.164,81
F Harga Satuan Pekerjaan (D+E) 56.812,88

Pembuatan 1 m2 daun pintu panil , kayu klas I

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,80 78.000,00 62.400,00
Tukang Kayu L.02 OH 2,40 86.000,00 206.400,00
Kepala Tukang L,03 OH 0,24 95.000,00 22.800,00
Mandor L.04 OH 0,04 98.000,00 3.920,00
JUMLAH TENAGA KERJA 295520
B BAHAN
Papan Kayu m3 0,024 3.504.770,00 84.114,48
Lem kayu Kg 0,300 15.010,00 4.503,00
JUMLAH HARGA BAHAN 88.617,48
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 384.137,48
E Overhead & Profit (10%) 10% X D 38.413,75
F Harga Satuan Pekerjaan (D+E) 422.551,23
Analisa SNI 2016

Pembuatan dan Pemasangan 1 m2 pintu teakwood lapis alumunium foil , kayu klas I

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,800 78.000,00 62.400,00
Tukang Kayu L.02 OH 2,400 86.000,00 206.400,00
Kepala Tukang L,03 OH 0,240 95.000,00 22.800,00
Mandor L.04 OH 0,040 98.000,00 3.920,00
JUMLAH TENAGA KERJA 295.520,00
B BAHAN
Papan Kayu m3 0,024 3.504.770,00 84.114,48
Lem kayu Kg 0,300 15.010,00 4.503,00
Paku Kg 0,030 22.010,00 660,30
Teakwood lapis alumunium foil lbr 0,800 80.100,00 64.080,00
JUMLAH HARGA BAHAN 153.357,78
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 448.877,78
E Overhead & Profit (10%) 10% X D 44.887,78
F Harga Satuan Pekerjaan (D+E) 493.765,56

PEKERJAAN ATAP
Pemasangan 1 m2 konstruksi kuda-kuda Baja Ringan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,200 78.000,00 15.600,00
Tukang Besi L.02 OH 0,450 86.000,00 38.700,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,050 98.000,00 4.900,00
JUMLAH TENAGA KERJA 60.150,00
B BAHAN
Kanal C 75-75 m1 2,800 16.673,33 46.685,33
Reng Butten R.30-45 m1 5,400 9.171,67 49.527,00
Drilling screw R20 bh 25,000 910,00 22.750,00
Drilling screw R14 bh 35,000 760,00 26.600,00
Dynabold 12x 120 mm bh 1,600 2.810,00 4.496,00
JUMLAH HARGA BAHAN 150.058,33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 210.208,33
E Overhead & Profit (10%) 10% X D 21.020,83
F Harga Satuan Pekerjaan (D+E) 231.229,17

Pemasangan 1 m2 Atap Genteng Multiroof

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,200 78.000,00 15.600,00
Tukang Kayu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,010 98.000,00 980,00
JUMLAH TENAGA KERJA 26.130,00
B BAHAN
Genteng metal MULTI ROOF lbr 1,020 65.040,00 66.340,80
Paku genteng metalroof kg 0,200 25.010,00 5.002,00
JUMLAH HARGA BAHAN 71.342,80
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 97.472,80
E Overhead & Profit (10%) 10% X D 9.747,28
F Harga Satuan Pekerjaan (D+E) 107.220,08
Analisa SNI 2016

Pemasangan 1 m1 Bubungan Atap Genteng Multiroof

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,200 78.000,00 15.600,00
Tukang Kayu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,010 98.000,00 980,00
JUMLAH TENAGA KERJA 26.130,00
B BAHAN
Bubungan Genteng Metal bh 3,500 20.040,00 70.140,00
Paku genteng metalroof kg 0,050 25.010,00 1.250,50
JUMLAH HARGA BAHAN 71.390,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 97.520,50
E Overhead & Profit (10%) 10% X D 9.752,05
F Harga Satuan Pekerjaan (D+E) 107.272,55

Pemasangan 1 m2 Atap Genteng Multiroof dengan Rangka Hollow 4x4 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,200 78.000,00 15.600,00
Tukang Kayu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,010 98.000,00 980,00
JUMLAH TENAGA KERJA 26.130,00
B BAHAN
Genteng metal MULTI ROOF lbr 1,020 65.040,00 66.340,80
Paku genteng metalroof kg 0,200 25.010,00 5.002,00
Besi Hollow 4x4 cm M1 4,000 19.171,67 76.686,67
JUMLAH HARGA BAHAN 148.029,47
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 174.159,47
E Overhead & Profit (10%) 10% X D 17.415,95
F Harga Satuan Pekerjaan (D+E) 191.575,41
Analisa SNI 2016

Pemasangan 1 m2 Atap Seng Zincalume (100 cm x 0,4 mm x 6 m)


Harga Satuan (Rp.) Jumlah Harga (Rp.)
No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0,120 78.000,00 9.360,00
Tukang Kayu L.02 OH 0,060 86.000,00 5.160,00
Kepala Tukang L,03 OH 0,006 95.000,00 570,00
Mandor L.04 OH 0,006 98.000,00 588,00
JUMLAH TENAGA KERJA 15.678,00
B BAHAN
Seng Zincalume 0.40 mm M2 1,000 62.040,00 62.040,00
Skrup mata baja bh 0,020 910,00 18,20
JUMLAH HARGA BAHAN 62.058,20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 77.736,20
E Overhead & Profit (10%) 10% X D 7.773,62
F Harga Satuan Pekerjaan (D+E) 85.509,82

Pemasangan 1 m1 Nok Zincalume


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,150 78.000,00 11.700,00
Tukang Kayu L.02 OH 0,070 86.000,00 6.020,00
Kepala Tukang L,03 OH 0,007 95.000,00 665,00
Mandor L.04 OH 0,006 98.000,00 588,00
JUMLAH TENAGA KERJA 18.973,00
B BAHAN
Nok Zincalume lbr 0,300 35.040,00 10.512,00
Paku Seng kg 0,040 24.010,00 960,40
JUMLAH HARGA BAHAN 11.472,40
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 30.445,40
E Overhead & Profit (10%) 10% X D 3.044,54
F Harga Satuan Pekerjaan (D+E) 33.489,94

Pemasangan 1 m1 Talang seng Licin BJLS 0.30 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,100 78.000,00 7.800,00
Tukang Kayu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 17.840,00
B BAHAN
Papan Kayu kelas II m3 0,019 2.604.770,00 49.490,63
Seng Licin BJLS 0.30 mm Lbr 0,500 35.040,00 17.520,00
Paku Kg 0,015 24.010,00 360,15

JUMLAH HARGA BAHAN 67.370,78


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 85.210,78
E Overhead & Profit (10%) 10% X D 8.521,08
F Harga Satuan Pekerjaan (D+E) 93.731,86
Analisa SNI 2016

Pemasangan 1 m2 Seng Licin BJLS 0.30 mm pada bagian dalam Lisplank Beton
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,120 70.100,00 8.412,00
Tukang Kayu L.02 OH 0,060 910,00 54,60
Kepala Tukang L,03 OH 0,006 2.510,00 15,06
Mandor L.04 OH 0,006 15.220,00 91,32
JUMLAH TENAGA KERJA 8.572,98
B BAHAN
Seng Licin/Bubungan seng plat BJLS 0.30 lbr 1,000 35.040,00 35.040,00
Skrup mata baja bh 0,200 910,00 182,00

Pipa Hollow Galvanis Pagar/ Kotak 4x4 cm tebalM1 mm 4,000 19.171,67 76.686,67
JUMLAH HARGA BAHAN 111.908,67
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 120.481,65
E Overhead & Profit (10%) 10% X D 12.048,16
F Harga Satuan Pekerjaan (D+E) 132.529,81

Pemasangan 1 m2 langit-langit Kalsiboard uk.(120x240), tebal 6 mm + Rangka Pipa Hollow 4x4 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,500 78.000,00 39.000,00
Tukang Kayu L.02 OH 0,500 86.000,00 43.000,00
Kepala Tukang L,03 OH 0,050 95.000,00 4.750,00
Mandor L.04 OH 0,025 98.000,00 2.450,00
JUMLAH TENAGA KERJA 89.200,00
B BAHAN
Kalsiboard 6 mm Lbr 0,364 120.100,00 43.716,40
Paku Skrup bh 15,000 910,00 13.650,00
Cotton Plaster bh 0,072 2.510,00 180,72
Coumpond Zak 0,125 15.220,00 1.902,50
Hollow 4x4 cm sincromate Btg 0,415 42.040,00 17.446,60
Hollow 2x4 cm sincromate Btg 0,150 30.030,00 4.504,50
Kawat Ø 4 mm kg 0,150 22.010,00 3.301,50
Dinabolt bh 1,000 2.810,00 2.810,00

JUMLAH HARGA BAHAN 87.512,22


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 176.712,22
E Overhead & Profit (10%) 10% X D 17.671,22
F Harga Satuan Pekerjaan (D+E) 194.383,44

Pemasangan 1 m2 langit-langit Gypsum Board uk.(120x240), tebal 9 mm + Rangka Pipa Hollow 4x4 cm
Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,500 78.000,00 39.000,00
Tukang Kayu L.02 OH 0,500 86.000,00 43.000,00
Kepala Tukang L,03 OH 0,050 95.000,00 4.750,00
Mandor L.04 OH 0,025 98.000,00 2.450,00
JUMLAH TENAGA KERJA 89.200,00
B BAHAN
Gypsum 9 mm Lbr 0,364 80.100,00 29.156,40
Paku Skrup bh 15,000 910,00 13.650,00
Cotton Plaster bh 0,072 2.510,00 180,72
Coumpond Zak 0,125 15.220,00 1.902,50
Hollow 4x4 cm sincromate Btg 0,415 42.040,00 17.446,60
Hollow 2x4 cm sincromate Btg 0,150 30.030,00 4.504,50
Kawat Ø 4 mm kg 0,150 22.010,00 3.301,50
Dinabolt bh 1,000 2.810,00 2.810,00

JUMLAH HARGA BAHAN 72.952,22


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 162.152,22
E Overhead & Profit (10%) 10% X D 16.215,22
F Harga Satuan Pekerjaan (D+E) 178.367,44
Analisa SNI 2016

Pemasangan 1 m2 Dinding Partisi Kalsiboard uk.(120x240), tebal 6 mm + Rangka Kanal C 75/75

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,150 78.000,00 11.700,00
Tukang Kayu L.02 OH 0,050 86.000,00 4.300,00
Kepala Tukang L,03 OH 0,005 95.000,00 475,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 16.965,00
B BAHAN
Kalsiboard 6 mm Lbr 0,364 120.100,00 43.716,40
Paku Skrup bh 15,000 910,00 13.650,00
Cotton Plaster bh 0,072 2.510,00 180,72
Coumpond Zak 0,125 15.220,00 1.902,50
Kanal C. 75/75 m1 4,000 16.673,33 66.693,33
Drilling screw R20 bh 10,000 910,00 9.100,00
Drilling screw R14 bh 10,000 760,00 7.600,00
Dynabold 12x 120 mm bh 1,600 2.810,00 4.496,00

JUMLAH HARGA BAHAN 147.338,95


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 164.303,95
E Overhead & Profit (10%) 10% X D 16.430,40
F Harga Satuan Pekerjaan (D+E) 180.734,35

Pemasangan 1 m1 Kalsiplank 8 corak jati uk.(0.8x20) cm, kayu klas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,100 78.000,00 7.800,00
Tukang Kayu L.02 OH 0,200 86.000,00 17.200,00
Kepala Tukang L,03 OH 0,020 95.000,00 1.900,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 27.390,00
B BAHAN
Kalsiplank 8 corak jati uk. 0.8/20 cm M1 1,000 25.030,00 25.030,00
Paku Skrup kg 0,200 22.010,00 4.402,00
JUMLAH HARGA BAHAN 29.432,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 56.822,00
E Overhead & Profit (10%) 10% X D 5.682,20
F Harga Satuan Pekerjaan (D+E) 62.504,20

Pemasangan 1 m1 List Gypsum uk.(10-15) cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,050 78.000,00 3.900,00
Tukang Kayu L.02 OH 0,050 86.000,00 4.300,00
Kepala Tukang L,03 OH 0,005 95.000,00 475,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 8.969,00
B BAHAN
List Gypsum M1 1,050 7.839,13 8.231,09
Paku Skrup kg 0,010 22.010,00 220,10
JUMLAH HARGA BAHAN 8.451,19
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 17.420,19
E Overhead & Profit (10%) 10% X D 1.742,02
F Harga Satuan Pekerjaan (D+E) 19.162,21
Analisa SNI 2016

PEKERJAAN SANITASI
Pemasangan 1 buah Closed duduk komplet box

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 3,300 78.000,00 257.400,00
Tukang Batu L.02 OH 1,100 86.000,00 94.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,160 98.000,00 15.680,00
JUMLAH TENAGA KERJA 368.630,00
B BAHAN
Closet duduk porselen putih setara Toto kompletUnit 1,000 3.500.960,00 3.500.960,00
Perlengkapan Ls 6%xClosed 210.057,60
JUMLAH HARGA BAHAN 3.711.017,60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.079.647,60
E Overhead & Profit (10%) 10% X D 407.964,76
F Harga Satuan Pekerjaan (D+E) 4.487.612,36

Pemasangan 1 buah Closed jongkok porslen


Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,000 78.000,00 78.000,00
Tukang Batu L.02 OH 1,500 86.000,00 129.000,00
Kepala Tukang L,03 OH 0,015 95.000,00 1.425,00
Mandor L.04 OH 0,160 98.000,00 15.680,00
JUMLAH TENAGA KERJA 224.105,00
B BAHAN
Closet jongkok porselin setara Toto Unit 1,000 550.640,00 550.640,00
semen portland Kg 6,000 1.250,00 7.500,00
Pasir Pasang M3 0,010 146.440,00 1.464,40
JUMLAH HARGA BAHAN 559.604,40
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 783.709,40
E Overhead & Profit (10%) 10% X D 78.370,94
F Harga Satuan Pekerjaan (D+E) 862.080,34

Pemasangan 1 buah Urinoir

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,000 78.000,00 78.000,00
Tukang Batu L.02 OH 1,000 86.000,00 86.000,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,050 98.000,00 4.900,00
JUMLAH TENAGA KERJA 169.850,00
B BAHAN
Urinoir Unit 1,000 1.700.640,00 1.700.640,00
semen portland Kg 6,000 1.250,00 7.500,00
Pasir Pasang M3 0,010 146.440,00 1.464,40
Perlengkapan % 30,000 510.192,00
JUMLAH HARGA BAHAN 2.219.796,40
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.389.646,40
E Overhead & Profit (10%) 10% X D 238.964,64
F Harga Satuan Pekerjaan (D+E) 2.628.611,04
Analisa SNI 2016

Pemasangan 1 buah Wastafel

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,200 78.000,00 93.600,00
Tukang Batu L.02 OH 1,450 86.000,00 124.700,00
Kepala Tukang L,03 OH 0,150 95.000,00 14.250,00
Mandor L.04 OH 0,060 98.000,00 5.880,00
JUMLAH TENAGA KERJA 238.430,00
B BAHAN
Wastafel Komplet Unit 1,000 1.500.640,00 1.500.640,00
semen portland Kg 6,000 1.250,00 7.500,00
Pasir Pasang M3 0,010 146.440,00 1.464,40
Perlengkapan Ls 12,000 180.076,80
JUMLAH HARGA BAHAN 1.689.681,20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1.928.111,20
E Overhead & Profit (10%) 10% X D 192.811,12
F Harga Satuan Pekerjaan (D+E) 2.120.922,32

Pemasangan 1 buah bak air Fiberglass vol 1m3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,300 78.000,00 23.400,00
Tukang Batu L.02 OH 0,450 86.000,00 38.700,00
Kepala Tukang L,03 OH 0,045 95.000,00 4.275,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 67.845,00
B BAHAN
Bak Fiberglass Unit 1,000 600.960,00 600.960,00
Perlengkapan Ls 12%xbak 72.115,20
JUMLAH HARGA BAHAN 673.075,20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 740.920,20
E Overhead & Profit (10%) 10% X D 74.092,02
F Harga Satuan Pekerjaan (D+E) 815.012,22

Pemasangan 1 Unit Spoel Hoek

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,030 78.000,00 2.340,00
Tukang Batu L.02 OH 0,300 86.000,00 25.800,00
Kepala Tukang L,03 OH 0,030 95.000,00 2.850,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 32.460,00
B BAHAN
Spoel Hoek setara toto Unit 1,000 6.500.960,00 6.500.960,00
Perlengkapan % 0,100 650.096,00
JUMLAH HARGA BAHAN 7.151.056,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 7.183.516,00
E Overhead & Profit (10%) 10% X D 718.351,60
F Harga Satuan Pekerjaan (D+E) 7.901.867,60
Analisa SNI 2016

Pemasangan 1 buah bak Cuci stainlessteel(Kichen Sink) single bak

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,030 78.000,00 2.340,00
Tukang Batu L.02 OH 0,300 86.000,00 25.800,00
Kepala Tukang L,03 OH 0,030 95.000,00 2.850,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 32.460,00
B BAHAN
Bak cuci Stainlesstel(Kichen Sink) single bak Unit 1,000 850.390,00 850.390,00
waterdrain bh 1,000 5.010,00 5.010,00
JUMLAH HARGA BAHAN 855.400,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 887.860,00
E Overhead & Profit (10%) 10% X D 88.786,00
F Harga Satuan Pekerjaan (D+E) 976.646,00

Pemasangan 1 buah bak Cuci stainlessteel(Kichen Sink) double bak

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,030 78.000,00 2.340,00
Tukang Batu L.02 OH 0,300 86.000,00 25.800,00
Kepala Tukang L,03 OH 0,030 95.000,00 2.850,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 32.460,00
B BAHAN
Bak cuci Stainlesstel(Kichen Sink) double bak Unit 1,000 1.000.390,00 1.000.390,00
waterdrain bh 1,000 85.010,00 85.010,00
JUMLAH HARGA BAHAN 1.085.400,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1.117.860,00
E Overhead & Profit (10%) 10% X D 111.786,00
F Harga Satuan Pekerjaan (D+E) 1.229.646,00

Pemasangan 1 buah floor drain

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang Batu L.02 OH 0,100 86.000,00 8.600,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 10.820,00
B BAHAN
Floor drain Unit 1,000 15.010,00 15.010,00
JUMLAH HARGA BAHAN 15.010,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 25.830,00
E Overhead & Profit (10%) 10% X D 2.583,00
F Harga Satuan Pekerjaan (D+E) 28.413,00
Analisa SNI 2016

Pemasangan 1 M1 pipa Galvanis diameter 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,054 78.000,00 4.212,00
Tukang Pipa L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,009 95.000,00 855,00
Mandor L.04 OH 0,027 98.000,00 2.646,00
JUMLAH TENAGA KERJA 15.453,00
B BAHAN
Pipa Galv. 1/2" M 1,200 25.011,67 30.014,00
Perlengkapan Ls 35%xpipa 3.601,68
JUMLAH HARGA BAHAN 30.014,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 45.467,00
E Overhead & Profit (10%) 10% X D 4.546,70
F Harga Satuan Pekerjaan (D+E) 50.013,70

Pemasangan 1 M1 pipa Kran Air diameter 1/2" atau 3/4"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang Pipa L.02 OH 0,400 86.000,00 34.400,00
Kepala Tukang L,03 OH 0,040 95.000,00 3.800,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 39.470,00
B BAHAN
Pipa Galv. 1/2" M 1,000 40.010,00 40.010,00
Sealtape Bh 0,025 5.010,00 4.801,20
JUMLAH HARGA BAHAN 44.811,20
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 84.281,20
E Overhead & Profit (10%) 10% X D 8.428,12
F Harga Satuan Pekerjaan (D+E) 92.709,32

Pemasangan 1 M1 pipa Galvanis diameter 3/4"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,054 78.000,00 4.212,00
Tukang Pipa L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,009 95.000,00 855,00
Mandor L.04 OH 0,027 98.000,00 2.646,00
JUMLAH TENAGA KERJA 15.453,00
B BAHAN
Pipa Galv. 3/4" M 1,000 58.345,00 58.345,00
Perlengkapan Ls 35%xpipa 7.001,40
JUMLAH HARGA BAHAN 58.345,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 73.798,00
E Overhead & Profit (10%) 10% X D 7.379,80
F Harga Satuan Pekerjaan (D+E) 81.177,80
Analisa SNI 2016

Pemasangan 1 M1 pipa Galvanis diameter 2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,054 78.000,00 4.212,00
Tukang Pipa L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,009 95.000,00 855,00
Mandor L.04 OH 0,027 98.000,00 2.646,00
JUMLAH TENAGA KERJA 15.453,00
B BAHAN
Pipa Galv. 2" M 1,200 208.366,67 250.040,00
Perlengkapan Ls 35%xpipa 30.004,80
JUMLAH HARGA BAHAN 250.040,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 265.493,00
E Overhead & Profit (10%) 10% X D 26.549,30
F Harga Satuan Pekerjaan (D+E) 292.042,30

Pemasangan 1 M1 pipa Galvanis diameter 1 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,108 78.000,00 8.424,00
Tukang Pipa L.02 OH 0,180 86.000,00 15.480,00
Kepala Tukang L,03 OH 0,018 95.000,00 1.710,00
Mandor L.04 OH 0,005 98.000,00 490,00
JUMLAH TENAGA KERJA 26.104,00
B BAHAN
Pipa Galv. 1 1/2" M 1,200 108.345,00 130.014,00
Perlengkapan Ls 35%xpipa 15.601,68
JUMLAH HARGA BAHAN 130.014,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 156.118,00
E Overhead & Profit (10%) 10% X D 15.611,80
F Harga Satuan Pekerjaan (D+E) 171.729,80

Pemasangan 1 M1 pipa PVC tipe AW diameter 1/2"


Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,036 78.000,00 2.808,00
Tukang Pipa L.02 OH 0,060 86.000,00 5.160,00
Kepala Tukang L,03 OH 0,006 95.000,00 570,00
Mandor L.04 OH 0,002 98.000,00 196,00
JUMLAH TENAGA KERJA 8.734,00
B BAHAN
Pipa PVC 1/2" M 1,200 6.510,00 7.812,00
Perlengkapan Ls 35%xpipa 937,44
JUMLAH HARGA BAHAN 7.812,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 16.546,00
E Overhead & Profit (10%) 10% X D 1.654,60
F Harga Satuan Pekerjaan (D+E) 18.200,60
Analisa SNI 2016

Pemasangan 1 M1 pipa PVC tipe AW diameter 3/4"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,04 78.000,00 2.808,00
Tukang Pipa L.02 OH 0,06 86.000,00 5.160,00
Kepala Tukang L,03 OH 0,01 95.000,00 570,00
Mandor L.04 OH 0,00 98.000,00 196,00
JUMLAH TENAGA KERJA 8.734,00
B BAHAN
Pipa PVC 3/4" M 1,20 8.510,00 10.212,00
Perlengkapan Ls 35%xpipa 1.225,44
JUMLAH HARGA BAHAN 10.212,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 18.946,00
E Overhead & Profit (10%) 10% X D 1.894,60
F Harga Satuan Pekerjaan (D+E) 20.840,60

Pemasangan 1 M1 pipa PVC tipe AW diameter 1"


Harga Satuan (Rp.)
No Uraian Kode Satuan Koefisien
Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,036 78.000,00 2.808,00
Tukang Pipa L.02 OH 0,060 86.000,00 5.160,00
Kepala Tukang L,03 OH 0,006 95.000,00 570,00
Mandor L.04 OH 0,002 98.000,00 196,00
JUMLAH TENAGA KERJA 8.734,00
B BAHAN
Pipa PVC 1" M 1,200 20.010,00 24.012,00
Perlengkapan Ls 35%xpipa 2.881,44
JUMLAH HARGA BAHAN 24.012,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 32.746,00
E Overhead & Profit (10%) 10% X D 3.274,60
F Harga Satuan Pekerjaan (D+E) 36.020,60

Pemasangan 1 M1 pipa PVC tipe AW diameter 1 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,054 78.000,00 4.212,00
Tukang Pipa L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,009 95.000,00 855,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 13.101,00
B BAHAN
Pipa PVC 1 1/2" M 1,200 16.260,00 19.512,00
Perlengkapan Ls 35%xpipa 2.341,44
JUMLAH HARGA BAHAN 19.512,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 32.613,00
E Overhead & Profit (10%) 10% X D 3.261,30
F Harga Satuan Pekerjaan (D+E) 35.874,30
Analisa SNI 2016

Pemasangan 1 M1 pipa PVC tipe AW diameter 2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,054 78.000,00 4.212,00
Tukang Pipa L.02 OH 0,090 86.000,00 7.740,00
Kepala Tukang L,03 OH 0,009 95.000,00 855,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 13.101,00
B BAHAN
Pipa PVC 2" M 1,200 18.760,00 22.512,00
Perlengkapan Ls 35%xpipa 2.701,44
JUMLAH HARGA BAHAN 22.512,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 35.613,00
E Overhead & Profit (10%) 10% X D 3.561,30
F Harga Satuan Pekerjaan (D+E) 39.174,30

Pemasangan 1 M1 pipa PVC tipe AW diameter 2 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,081 78.000,00 6.318,00
Tukang Pipa L.02 OH 0,135 86.000,00 11.610,00
Kepala Tukang L,03 OH 0,014 95.000,00 1.282,50
Mandor L.04 OH 0,004 98.000,00 392,00
JUMLAH TENAGA KERJA 19.602,50
B BAHAN
Pipa PVC 2 1/2" M 1,200 21.260,00 25.512,00
Perlengkapan Ls 35%xpipa 3.061,44
JUMLAH HARGA BAHAN 25.512,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 45.114,50
E Overhead & Profit (10%) 10% X D 4.511,45
F Harga Satuan Pekerjaan (D+E) 49.625,95

Pemasangan 1 M1 pipa PVC tipe AW diameter 3"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,081 78.000,00 6.318,00
Tukang Pipa L.02 OH 0,135 86.000,00 11.610,00
Kepala Tukang L,03 OH 0,014 95.000,00 1.282,50
Mandor L.04 OH 0,004 98.000,00 392,00
JUMLAH TENAGA KERJA 19.602,50
B BAHAN
Pipa PVC 3" M 1,200 27.510,00 33.012,00
Perlengkapan Ls 35%xpipa 3.961,44
JUMLAH HARGA BAHAN 33.012,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 52.614,50
E Overhead & Profit (10%) 10% X D 5.261,45
F Harga Satuan Pekerjaan (D+E) 57.875,95
Analisa SNI 2016

Pemasangan 1 M1 pipa PVC tipe AW diameter 4"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,081 78.000,00 6.318,00
Tukang Pipa L.02 OH 0,135 86.000,00 11.610,00
Kepala Tukang L,03 OH 0,014 95.000,00 1.282,50
Mandor L.04 OH 0,004 98.000,00 392,00
JUMLAH TENAGA KERJA 19.602,50
B BAHAN
Pipa PVC 4" M 1,200 37.510,00 45.012,00
Perlengkapan Ls 35%xpipa 5.401,44
JUMLAH HARGA BAHAN 45.012,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 64.614,50
E Overhead & Profit (10%) 10% X D 6.461,45
F Harga Satuan Pekerjaan (D+E) 71.075,95

PEKERJAAN PENGECATAN
Pengecatan 1m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,070 78.000,00 5.460,00
Tukang Cat L.02 OH 0,009 86.000,00 774,00
Kepala Tukang L,03 OH 0,006 95.000,00 570,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 7.098,00
B BAHAN
Cat Menie Kg 0,200 19.260,00 3.852,00
Plamur Kg 0,150 12.010,00 1.801,50
Cat Dasar Kg 0,170 20.010,00 3.401,70
Cat Penutup Kg 0,260 25.010,00 6.502,60
Kuas bh 0,010 14.860,00 148,60
Pengencer Kg 0,030 20.010,00 600,30
Ampelas lbr 0,200 3.510,00 702,00
JUMLAH HARGA BAHAN 17.008,70
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24.106,70
E Overhead & Profit (10%) 10% X D 2.410,67
F Harga Satuan Pekerjaan (D+E) 26.517,37

Pelaburan 1 m2 bidang kayu dengan teak oil

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,040 78.000,00 3.120,00
Tukang Cat L.02 OH 0,063 86.000,00 5.418,00
Kepala Tukang L,03 OH 0,063 95.000,00 5.985,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 14.817,00
B BAHAN
Teak oil Liter 0,360 27.510,00 9.903,60
JUMLAH HARGA BAHAN 9.903,60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 24.720,60
E Overhead & Profit (10%) 10% X D 2.472,06
F Harga Satuan Pekerjaan (D+E) 27.192,66
Analisa SNI 2016

Pelaburan 1 m2 bidang kayu Politur

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,040 78.000,00 3.120,00
Tukang Cat L.02 OH 0,063 86.000,00 5.418,00
Kepala Tukang L,03 OH 0,063 95.000,00 5.985,00
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 14.817,00
B BAHAN
Politur Liter 0,150 7.510,00 1.126,50
Politur Jadi Liter 0,372 10.010,00 3.723,72
Ampelas lbr 2,000 3.510,00 7.020,00
JUMLAH HARGA BAHAN 11.870,22
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 26.687,22
E Overhead & Profit (10%) 10% X D 2.668,72
F Harga Satuan Pekerjaan (D+E) 29.355,94

Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,020 78.000,00 1.560,00
Tukang cat L.02 OH 0,063 86.000,00 5.418,00
Kepala Tukang L,03 OH 0,006 95.000,00 598,50
Mandor L.04 OH 0,003 98.000,00 294,00
JUMLAH TENAGA KERJA 7.870,50
B BAHAN
Plamuur kg 0,100 12.010,00 1.201,00
Cat dasar kg 0,100 20.010,00 2.001,00
Cat penutup kg 0,260 25.010,00 6.502,60
JUMLAH HARGA BAHAN 9.704,60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 17.575,10
E Overhead & Profit (10%) 10% X D 1.757,51
F Harga Satuan Pekerjaan (D+E) 19.332,61

Pengecatan 1 m2 Waterproofing

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang cat L.02 OH 0,083 86.000,00 7.138,00
Kepala Tukang L,03 OH 0,008 95.000,00 788,50
Mandor L.04 OH 0,003 98.000,00 245,00
JUMLAH TENAGA KERJA 10.121,50
B BAHAN
Waterproffing (ex-Sika) kg 0,500 95.010,00 47.505,00

JUMLAH HARGA BAHAN 47.505,00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 57.626,50
E Overhead & Profit (10%) 10% X D 5.762,65
F Harga Satuan Pekerjaan (D+E) 63.389,15
Analisa SNI 2016

PEKERJAAN MEKANIKAL & ELEKTRIKAL


Pemasangan 1 buah Saklar Ganda

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
saklar ganda bh 1,000 30.010,00 30.010,00
Perlengkapan Ls 5% x saklar 1.500,50 1.500,50
JUMLAH HARGA BAHAN 31.510,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 33.890,50
E Overhead & Profit (10%) 10% X D 3.389,05
F Harga Satuan Pekerjaan (D+E) 37.279,55

Pemasangan 1 buah Saklar Triple

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Saklar triple merk broco bh 1,000 35.010,00 35.010,00
Perlengkapan Ls 5% x saklar 1.750,50 1.750,50
JUMLAH HARGA BAHAN 36.760,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 39.140,50
E Overhead & Profit (10%) 10% X D 3.914,05
F Harga Satuan Pekerjaan (D+E) 43.054,55

Pemasangan 1 buah saklar Tunggal

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
saklar tunggal bh 1,000 25.010,00 25.010,00
Perlengkapan Ls 5% x saklar 1.250,50 1.250,50
JUMLAH HARGA BAHAN 26.260,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 28.640,50
E Overhead & Profit (10%) 10% X D 2.864,05
F Harga Satuan Pekerjaan (D+E) 31.504,55

Pemasangan 1 buah Stop Kontak AC

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Stop Kontak AC, 1 ph bh 1,000 40.010,00 40.010,00
Perlengkapan Ls 5% x saklar 2.000,50 2.000,50
JUMLAH HARGA BAHAN 42.010,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 44.390,50
E Overhead & Profit (10%) 10% X D 4.439,05
F Harga Satuan Pekerjaan (D+E) 48.829,55
Analisa SNI 2016

Pemasangan 1 buah Stop Kontak

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Stop Kontak 200 A, 1ph bh 1,000 27.010,00 27.010,00
Perlengkapan Ls 5% x saklar 1.350,50 1.350,50
JUMLAH HARGA BAHAN 28.360,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 30.740,50
E Overhead & Profit (10%) 10% X D 3.074,05
F Harga Satuan Pekerjaan (D+E) 33.814,55

Pemasangan 1 buah Lampu Downlight Theme LED 12 watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu Downlight LED 12 watt bh 1,000 190.010,00 190.010,00

JUMLAH HARGA BAHAN 190.010,00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 192.390,00
E Overhead & Profit (10%) 10% X D 19.239,00
F Harga Satuan Pekerjaan (D+E) 211.629,00

Pemasangan 1 buah Lampu SL 18 Watt setara Phillips

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu SL 18 W lengkap fitting bh 1,000 40.010,00 40.010,00
JUMLAH HARGA BAHAN 40.010,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 42.390,00
E Overhead & Profit (10%) 10% X D 4.239,00
F Harga Satuan Pekerjaan (D+E) 46.629,00
Analisa SNI 2016

Pemasangan 1 buah Lampu Downlight Theme LED 3 watt

No Uraian Kode Satuan Koefisien


Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu Downlight LED 3 watt bh 1,000 95.010,00 95.010,00

JUMLAH HARGA BAHAN 95.010,00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 97.390,00
E Overhead & Profit (10%) 10% X D 9.739,00
F Harga Satuan Pekerjaan (D+E) 107.129,00

Pemasangan 1 Unit Lampu Sorot LED 50 watt lengkap kap lampu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu Sorot LED 50 watt lengkap kap lampu Unit 1,000 325.010,00 325.010,00
Perlengkapan Ls 5% x Lampu 16.250,50 16.250,50
JUMLAH HARGA BAHAN 341.260,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 343.640,50
E Overhead & Profit (10%) 10% X D 34.364,05
F Harga Satuan Pekerjaan (D+E) 378.004,55

Pemasangan 1 buah Lampu Neon Box/TL 2x18 watt

No Uraian Kode Satuan Koefisien


Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu Neon Box/TL 2x18 watt bh 1,000 250.010,00 250.010,00
lengkap kap lampu
JUMLAH HARGA BAHAN 250.010,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 252.390,00
E Overhead & Profit (10%) 10% X D 25.239,00
F Harga Satuan Pekerjaan (D+E) 277.629,00
Analisa SNI 2016

Pemasangan Lampu LED pada Logo dan Huruf

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Lampu Led pada huruf, Motif Daerah unit 1,000 2.000.010,00 2.000.010,00
dan logo
JUMLAH HARGA BAHAN 2.000.010,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.002.390,00
E Overhead & Profit (10%) 10% X D 200.239,00
F Harga Satuan Pekerjaan (D+E) 2.202.629,00

Pemasangan 1 buah Exhaust Fan Type Axial Wall Kap. 100 CFM, 125 w / 1P c/w EAG di Toilet

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Exhaust Fan Type Axial Wall Kap. 100 CFM bh 1,000 500.010,00 500.010,00

JUMLAH HARGA BAHAN 500.010,00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 502.390,00
E Overhead & Profit (10%) 10% X D 50.239,00
F Harga Satuan Pekerjaan (D+E) 552.629,00

Pemasangan 1 buah Exhaust Fan Type Axial Wall Kap. 300 CFM, 125 w / 1P c/w EAG di ruangan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Exhaust Fan Type Axial Wall Kap. 300 CFM bh 1,000 1.000.010,00 1.000.010,00
JUMLAH HARGA BAHAN 1.000.010,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1.002.390,00
E Overhead & Profit (10%) 10% X D 100.239,00
F Harga Satuan Pekerjaan (D+E) 1.102.629,00
Analisa SNI 2016

Pemasangan 1 Unit Sekring Box + MCB 3 Phase

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Sekring box Unit 1,000 85.010,00 85.010,00
MCB 3 Phase bh 1,000 350.010,00 350.010,00
JUMLAH HARGA BAHAN 435.020,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 437.400,00
E Overhead & Profit (10%) 10% X D 43.740,00
F Harga Satuan Pekerjaan (D+E) 481.140,00

Pemasangan 1 titik instalasi listrik

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,020 78.000,00 1.560,00
Tukang listrik L.02 OH 0,063 86.000,00 5.418,00
JUMLAH TENAGA KERJA 6.978,00
B BAHAN
Kabel NYA 3x2.5 mm2 m' 10,000 10.010,00 100.100,00
Conduit Pipa dia. 20 m' 4,000 5.010,00 20.040,00
Perlengkapan Ls 0,050 5.005,00
JUMLAH HARGA BAHAN 125.145,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 132.123,00
E Overhead & Profit (10%) 10% X D 13.212,30
F Harga Satuan Pekerjaan (D+E) 145.335,30

Pemasangan 1 buah Portable extinguisher 3.5 NAF PIV

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,025 78.000,00 1.950,00
Tukang listrik L.02 OH 0,005 86.000,00 430,00
JUMLAH TENAGA KERJA 2.380,00
B BAHAN
Portable extinguisher 3.5 NAF PIV bh 1,000 2.500.390,00 2.500.390,00
JUMLAH HARGA BAHAN 2.500.390,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.502.770,00
E Overhead & Profit (10%) 10% X D 250.277,00
F Harga Satuan Pekerjaan (D+E) 2.753.047,00
Analisa SNI 2016

Pemasangan 1 Unit AC wall Mounted 9000 BTU/H

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,020 78.000,00 1.560,00
Tukang listrik L.02 OH 0,063 86.000,00 5.418,00
JUMLAH TENAGA KERJA 6.978,00
B BAHAN
AC Split wall Mounted 9000 BTU/H Unit 1,000 5.200.390,00 5.200.390,00

JUMLAH HARGA BAHAN 5.200.390,00


C UPAH & PERALATAN
Material bantu 2.5 % x bahan 130.009,75
Pemasangan 2.5% x bahan 130.009,75

JUMLAH HARGA ALAT 260.019,50


D Jumlah (A+B+C) 5.467.387,50
E Overhead & Profit (10%) 10% X D 546.738,75
F Harga Satuan Pekerjaan (D+E) 6.014.126,25

Pembuatan dan Pemasangan Pagar 1 m'Rangka besi hollow galvanis 4 x 4 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang cat L.02 OH 0,002 86.000,00 172,00
Tukang las L.02 OH 0,002 95.000,00 190,00
Kepala Tukang L,03 OH 0,006 98.000,00 617,40
JUMLAH TENAGA KERJA 1.759,40
B BAHAN
Besi hollow galvanis m' 1,000 19.171,67 19.171,67
Kawat las buah 0,900 210,00 189,00
cat besi kg 0,200 37.510,00 7.502,00
dumpul kg 0,150 35.010,00 5.251,50
Amplas Lembar 0,500 3.510,00 1.755,00
Perlengkapan Ls 10% x besi holow 1.917,17
JUMLAH HARGA BAHAN 35.786,33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 37.545,73
E Overhead & Profit (10%) 10% X D 3.754,57
F Harga Satuan Pekerjaan (D+E) 41.300,31

Pembuatan dan Pemasangan Pagar 1 m' Rangka besi hollow galvanis 2 x 4 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang cat L.02 OH 0,002 86.000,00 172,00
Tukang las L.02 OH 0,002 95.000,00 190,00
Kepala Tukang L,03 OH 0,006 98.000,00 617,40
JUMLAH TENAGA KERJA 1.759,40
B BAHAN
Besi hollow galvanis m' 1,000 11.671,67 11.671,67
Kawat las buah 0,600 210,00 126,00
cat besi kg 0,160 37.510,00 6.001,60
dumpul kg 0,140 35.010,00 4.901,40
Amplas Lembar 0,300 3.510,00 1.053,00
Perlengkapan Ls 10% x besi holow 1.167,17
JUMLAH HARGA BAHAN 24.920,83
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 26.680,23
E Overhead & Profit (10%) 10% X D 2.668,02
F Harga Satuan Pekerjaan (D+E) 29.348,26
Analisa SNI 2016

Pemasangan 1 M2 Marmer Hitam

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,700 78.000,00 54.600,00
Tukang Batu L.02 OH 0,350 86.000,00 30.100,00
Kepala Tukang L,03 OH 0,035 95.000,00 3.325,00
Mandor L.04 OH 0,035 98.000,00 3.430,00
JUMLAH TENAGA KERJA 91.455,00
B BAHAN
Marmer 60x90 cm poles m2 1,850 1.450.000,00 2.682.500,00
Semen Portland Kg 10,400 1.250,00 13.000,00
Pasir Pasang M3 0,045 146.440,00 6.589,80
Semen warna Kg 1,620 9.610,00 15.568,20
JUMLAH HARGA BAHAN 2.717.658,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.809.113,00
E Overhead & Profit (10%) 10% X D 280.911,30
F Harga Satuan Pekerjaan (D+E) 3.090.024,30

Pembuatan dan Pemasangan 1 Kg Ram-ram Saluran Besi Siku kombinasi Plat Strip

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang cat L.02 OH 0,002 86.000,00 172,00
Tukang las L.02 OH 0,002 86.000,00 172,00
Kepala Tukang L,03 OH 0,006 98.000,00 617,40
JUMLAH TENAGA KERJA 1.741,40
B BAHAN
Besi Siku 30.30.3 kg 1,050 12.010,00 12.610,50
Besi Strip kg 0,670 12.010,00 8.046,70
Kawat las buah 0,600 210,00 126,00
cat besi kg 0,160 37.510,00 6.001,60
Amplas Lembar 0,300 3.510,00 1.053,00

JUMLAH HARGA BAHAN 27.837,80


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 29.579,20
E Overhead & Profit (10%) 10% X D 2.957,92
F Harga Satuan Pekerjaan (D+E) 32.537,12
Analisa SNI 2016

Pembuatan dan Pemasangan 1 M2 Aluminium Composite Panel + Rangka Hollow Galvanis 40.40.1,2 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,150 78.000,00 11.700,00
Tukang Besi L.02 OH 0,075 86.000,00 6.450,00
Kepala Tukang L,03 OH 0,008 95.000,00 760,00
Mandor L.04 OH 0,008 98.000,00 784,00
JUMLAH TENAGA KERJA 19.694,00
B BAHAN
Alumunium Composite Panel m2 1,000 805.070,00 805.070,00
finishing PVDF (setara seven)
Screw buah 20,000 510,00 10.200,00
Sealant tube 0,270 2.510,00 677,70
Pipa Hollow Galvanis Pagar/ Kotak m' 4,000 19.171,67 76.686,67
4x4 cm tebal 1 mm
Kawat las buah 0,600 210,00 126,00
Amplas Lembar 0,300 3.510,00 1.053,00

JUMLAH HARGA BAHAN 893.813,37


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 913.507,37
E Overhead & Profit (10%) 10% X D 91.350,74
F Harga Satuan Pekerjaan (D+E) 1.004.858,10

Pemasangan 1 M2 ACRYLIC Putih Susu tebal 3 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,150 78.000,00 11.700,00
Tukang Besi L.02 OH 0,075 86.000,00 6.450,00
Kepala Tukang L,03 OH 0,008 95.000,00 760,00
Mandor L.04 OH 0,008 98.000,00 784,00
JUMLAH TENAGA KERJA 19.694,00
B BAHAN
ACRYLIC putih susu tebal 3 mm m2 1,000 800.100,00 800.100,00
lem Acrylic Kg 0,050 15.010,00 750,50
JUMLAH HARGA BAHAN 800.850,50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 820.544,50
E Overhead & Profit (10%) 10% X D 82.054,45
F Harga Satuan Pekerjaan (D+E) 902.598,95

Pembuatan dan Pemasangan 1 Kg Papan Info/Reklame besi UNP 200

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,010 78.000,00 780,00
Tukang cat L.02 OH 0,002 86.000,00 172,00
Tukang las L.02 OH 0,002 86.000,00 172,00
Kepala Tukang L,03 OH 0,006 98.000,00 617,40
JUMLAH TENAGA KERJA 1.741,40
B BAHAN
Besi Kanal UNP, U200, (200x807.5 mm) kg 1,050 19.760,00 20.748,00
Kawat las buah 0,600 15.010,00 9.006,00

JUMLAH HARGA BAHAN 29.754,00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 31.495,40
E Overhead & Profit (10%) 10% X D 3.149,54
F Harga Satuan Pekerjaan (D+E) 34.644,94
Analisa SNI 2016

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Membuat 1 m3 Sloof 20x25 cm beton bertulang (besi + bekisting) K250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 160,023 12.010,00 1.921.873,83
Kawat Beton kg 3,000 22.010,00 66.030,00
Kayu kelas III m3 0,270 1.604.770,00 433.287,90
Paku 5-10 cm Kg 2,000 22.010,00 44.020,00
Minyak begisting Liter 0,600 5.510,00 3.306,00
JUMLAH HARGA BAHAN 3.223.878,08
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.457.787,08
E Overhead & Profit (10%) 10% X D 345.778,71
F Harga Satuan Pekerjaan (D+E) 3.803.565,79

Membuat 1 m3 Sloof 25x35 cm beton bertulang (besi + bekisting) K250, w/c = 0,56

No Uraian Kode Satuan Koefisien


Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 134,690 12.010,00 1.617.621,18
Kawat Beton kg 3,000 22.010,00 66.030,00
Kayu kelas III m3 0,270 1.604.770,00 433.287,90
Paku 5-10 cm Kg 2,000 22.010,00 44.020,00
Minyak begisting Liter 0,600 5.510,00 3.306,00
JUMLAH HARGA BAHAN 2.919.625,44
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.153.534,44
E Overhead & Profit (10%) 10% X D 315.353,44
F Harga Satuan Pekerjaan (D+E) 3.468.887,88
Analisa SNI 2016

Membuat 1 m3 Balok Latei 15x15 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien


Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 211,472 12.010,00 2.539.781,39
Kawat Beton kg 3,000 22.010,00 66.030,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.654.853,86
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.888.762,86
E Overhead & Profit (10%) 10% X D 488.876,29
F Harga Satuan Pekerjaan (D+E) 5.377.639,14

Membuat 1 m3 Ringbalk 15x20 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 164,922 12.010,00 1.980.715,89
Kawat Beton kg 3,000 22.010,00 66.030,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.095.788,36
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.329.697,36
E Overhead & Profit (10%) 10% X D 432.969,74
F Harga Satuan Pekerjaan (D+E) 4.762.667,09
Analisa SNI 2016

Membuat 1 m3 Ringbalk 25x30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien


Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 112,342 12.010,00 1.349.230,09
Kawat Beton kg 3,000 22.010,00 66.030,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.464.302,56
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.698.211,56
E Overhead & Profit (10%) 10% X D 369.821,16
F Harga Satuan Pekerjaan (D+E) 4.068.032,71

Membuat 1 m3 Balok Induk 30x40 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 132,323 12.010,00 1.589.203,23
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.775.997,79
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.009.906,79
E Overhead & Profit (10%) 10% X D 400.990,68
F Harga Satuan Pekerjaan (D+E) 4.410.897,47
Analisa SNI 2016

Membuat 1 m3 Balok Anak 20x30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 192,472 12.010,00 2.311.591,39
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.498.385,94
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.732.294,94
E Overhead & Profit (10%) 10% X D 473.229,49
F Harga Satuan Pekerjaan (D+E) 5.205.524,44

Membuat 1 m3 Balok Teras 20x35 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 120,743 12.010,00 1.450.121,71
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.636.916,27
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.870.825,27
E Overhead & Profit (10%) 10% X D 387.082,53
F Harga Satuan Pekerjaan (D+E) 4.257.907,80
Analisa SNI 2016

Membuat 1 m3 Anak Tangga beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 304,691 12.010,00 3.659.343,21
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 5.846.137,77
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6.080.046,77
E Overhead & Profit (10%) 10% X D 608.004,68
F Harga Satuan Pekerjaan (D+E) 6.688.051,44

Membuat 1 m3 Kolom Pedestal (K1) 40x40 cm beton bertulang (besi+bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 167,972 12.010,00 2.017.342,22
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.204.136,77
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.438.045,77
E Overhead & Profit (10%) 10% X D 443.804,58
F Harga Satuan Pekerjaan (D+E) 4.881.850,35
Analisa SNI 2016

Membuat 1 m3 Kolom Pedestal (K3) 30x30 cm beton bertulang (besi+bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 119,656 12.010,00 1.437.063,22
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.623.857,78
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.857.766,78
E Overhead & Profit (10%) 10% X D 385.776,68
F Harga Satuan Pekerjaan (D+E) 4.243.543,46

Membuat 1 m3 Kolom Pedestal (K4) 30x60 cm beton bertulang (besi+bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 136,069 12.010,00 1.634.182,91
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.820.977,46
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.054.886,46
E Overhead & Profit (10%) 10% X D 405.488,65
F Harga Satuan Pekerjaan (D+E) 4.460.375,11
Analisa SNI 2016

Membuat 1 m3 Kolom (K3) 30x30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 119,656 12.010,00 1.437.063,22
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.623.857,78
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.857.766,78
E Overhead & Profit (10%) 10% X D 385.776,68
F Harga Satuan Pekerjaan (D+E) 4.243.543,46

Membuat 1 m3 Kolom Teras (K6) 20x40 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 79,321 12.010,00 952.643,21
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,140 2.604.770,00 364.667,80
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.139.437,76
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.373.346,76
E Overhead & Profit (10%) 10% X D 337.334,68
F Harga Satuan Pekerjaan (D+E) 3.710.681,44
Analisa SNI 2016

Membuat 1 m3 Kolom (KP) 15x15 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 317,986 12.010,00 3.819.013,19
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 5.964.535,36
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6.198.444,36
E Overhead & Profit (10%) 10% X D 619.844,44
F Harga Satuan Pekerjaan (D+E) 6.818.288,80

Membuat 1 m3 Kolom Utama (K1) 40x40 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 158,048 12.010,00 1.898.150,48
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.110.992,73
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.344.901,73
E Overhead & Profit (10%) 10% X D 434.490,17
F Harga Satuan Pekerjaan (D+E) 4.779.391,90
Analisa SNI 2016

Membuat 1 m3 Kolom Utama(K2) 40x40 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 122,918 12.010,00 1.476.239,18
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.689.081,43
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.922.990,43
E Overhead & Profit (10%) 10% X D 392.299,04
F Harga Satuan Pekerjaan (D+E) 4.315.289,47

Membuat 1 m3 Kolom Utama(K4) 30x60 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 142,242 12.010,00 1.708.329,09
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.921.171,34
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.155.080,34
E Overhead & Profit (10%) 10% X D 415.508,03
F Harga Satuan Pekerjaan (D+E) 4.570.588,38
Analisa SNI 2016

Membuat 1 m3 Kolom Utama(K5) 30x30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 167,478 12.010,00 2.011.408,11
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.224.250,37
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.458.159,37
E Overhead & Profit (10%) 10% X D 445.815,94
F Harga Satuan Pekerjaan (D+E) 4.903.975,30

Membuat 1 m3 Plat Lisplank Beton t=12 cm, K250, w/c = 0,56


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 164,533 12.010,00 1.976.045,33
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 4.229.527,59
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4.463.436,59
E Overhead & Profit (10%) 10% X D 446.343,66
F Harga Satuan Pekerjaan (D+E) 4.909.780,25
Analisa SNI 2016

Membuat 1 m3 Plat Talang T=12 cm, K250, w/c = 0,56


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 205,667 12.010,00 2.470.056,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 4.723.538,92
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4.957.447,92
E Overhead & Profit (10%) 10% X D 495.744,79
F Harga Satuan Pekerjaan (D+E) 5.453.192,71
Membuat 1 m3 Plat Lantai 2, T=13 cm, K250
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 126,564 12.010,00 1.520.034,87
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.773.517,13
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4.007.426,13
E Overhead & Profit (10%) 10% X D 400.742,61
F Harga Satuan Pekerjaan (D+E) 4.408.168,74
Analisa SNI 2016

Membuat 1 m3 Plat Tangga, T=13 cm, K250

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 126,564 12.010,00 1.520.034,87
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.773.517,13
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.007.426,13
E Overhead & Profit (10%) 10% X D 400.742,61
F Harga Satuan Pekerjaan (D+E) 4.408.168,74

Membuat 1 m3 Plat Konsol, T=12 cm, K250

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 82,267 12.010,00 988.022,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.241.504,92
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.475.413,92
E Overhead & Profit (10%) 10% X D 347.541,39
F Harga Satuan Pekerjaan (D+E) 3.822.955,31
Analisa SNI 2016

Membuat 1 m3 Plat 10 cm (Meja Beton R. steril, R. Alat, Gudang Obat, Lab, Meja & Dapur)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 82,267 12.010,00 988.022,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.174.184,83
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.408.093,83
E Overhead & Profit (10%) 10% X D 340.809,38
F Harga Satuan Pekerjaan (D+E) 3.748.903,22

Membuat 1 m3 Plat 10 cm (Lantai dasar gedung)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 56,429 12.010,00 677.707,14
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 2.863.869,31
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.097.778,31
E Overhead & Profit (10%) 10% X D 309.777,83
F Harga Satuan Pekerjaan (D+E) 3.407.556,14
Analisa SNI 2016

Membuat 1 m3 Plat 12 cm (Teras Depan & samping)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 137,111 12.010,00 1.646.704,44
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.832.866,61
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.066.775,61
E Overhead & Profit (10%) 10% X D 406.677,56
F Harga Satuan Pekerjaan (D+E) 4.473.453,17

Membuat 1 m3 Footplat Type 1, tebal 30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 140,267 12.010,00 1.684.602,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
JUMLAH HARGA BAHAN 3.103.169,42
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.337.078,42
E Overhead & Profit (10%) 10% X D 333.707,84
F Harga Satuan Pekerjaan (D+E) 3.670.786,26
Analisa SNI 2016

Membuat 1 m3 Footplat Type 2, tebal 30 cm beton bertulang (besi + bekisting) K.250, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 384,000 1.250,00 480.000,00
Pasir beton kg 692,000 104,60 72.383,20
Kerikil kg 1.039,000 193,29 200.827,16
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 78,933 12.010,00 947.989,33
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
JUMLAH HARGA BAHAN 2.366.556,09
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.600.465,09
E Overhead & Profit (10%) 10% X D 260.046,51
F Harga Satuan Pekerjaan (D+E) 2.860.511,60

Membuat 1 m3 Kolom 25x25 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 140,808 12.010,00 1.691.108,08
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.836.630,25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.070.539,25
E Overhead & Profit (10%) 10% X D 407.053,93
F Harga Satuan Pekerjaan (D+E) 4.477.593,18
Analisa SNI 2016

Membuat 1 m3 Plat 20 cm (Lantai Groundtank)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 109,689 12.010,00 1.317.363,56
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.503.525,72
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.737.434,72
E Overhead & Profit (10%) 10% X D 373.743,47
F Harga Satuan Pekerjaan (D+E) 4.111.178,19

Membuat 1 m3 Plat 15 cm (Dinding Groundtank dan Plat atas Groundtank)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 109,689 12.010,00 1.317.363,56
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 24,000 5.080,00 121.920,00
JUMLAH HARGA BAHAN 3.503.525,72
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 3.737.434,72
E Overhead & Profit (10%) 10% X D 373.743,47
F Harga Satuan Pekerjaan (D+E) 4.111.178,19
Analisa SNI 2016

Membuat sloof beton bertulang (10x15 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0,297 78.000,00 23.166,00
Tukang Batu L.02 OH 0,033 86.000,00 2.838,00
Tukang Kayu L.02 OH 0,033 86.000,00 2.838,00
Tukang Besi L.02 OH 0,033 86.000,00 2.838,00
Kepala Tukang L,03 OH 0,010 95.000,00 950,00
Mandor L.04 OH 0,015 98.000,00 1.470,00
JUMLAH TENAGA KERJA 34.100,00
B BAHAN
Kayu klas III m3 0,270 1.604.770,00 433.287,90
Paku 5 - 12 cm kg 2,000 22.010,00 44.020,00
Besi beton polos kg 331,600 12.010,00 3.982.516,00
Kawat beton kg 3,000 22.010,00 66.030,00
Semen portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Batu kerikil kg 1029,000 193,29 198.894,27
JUMLAH HARGA BAHAN 5.211.744,17
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5.245.844,17
E Overhead & Profit (10%) 10% X D 524.584,42
F Harga Satuan Pekerjaan (D+E) 5.770.428,58

Membuat 1 m3 Kolom 20x20 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 140,808 12.010,00 1.691.108,08
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 3.836.630,25
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.070.539,25
E Overhead & Profit (10%) 10% X D 407.053,93
F Harga Satuan Pekerjaan (D+E) 4.477.593,18
Analisa SNI 2016

Membuat 1 m3 Kolom 20x40 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 173,138 12.010,00 2.079.381,38
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.224.903,54
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.458.812,54
E Overhead & Profit (10%) 10% X D 445.881,25
F Harga Satuan Pekerjaan (D+E) 4.904.693,80

Membuat 1 m3 Kolom 10x30 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 178,967 12.010,00 2.149.389,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.294.911,83
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.528.820,83
E Overhead & Profit (10%) 10% X D 452.882,08
F Harga Satuan Pekerjaan (D+E) 4.981.702,92
Analisa SNI 2016

Membuat 1 m3 Kolom 15x30 cm beton bertulang (besi + bekisting) K.175, slump (12 ± 2) cm, w/c = 0,66

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 186,496 12.010,00 2.239.820,52
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
Balok kayu kelas II m3 0,150 2.604.770,00 390.715,50
Plywood t= 9 mm Lembar 2,800 115.100,00 322.280,00
Dolken kayu dia. 8-10 cm batang 16,000 5.080,00 81.280,00
JUMLAH HARGA BAHAN 4.385.342,69
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4.619.251,69
E Overhead & Profit (10%) 10% X D 461.925,17
F Harga Satuan Pekerjaan (D+E) 5.081.176,85

Membuat 1 m3 Footplat kolom 20/40 cm, tebal 25 cm beton bertulang (besi + bekisting) K.175, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 80,267 12.010,00 964.002,67
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
JUMLAH HARGA BAHAN 2.315.249,33
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.549.158,33
E Overhead & Profit (10%) 10% X D 254.915,83
F Harga Satuan Pekerjaan (D+E) 2.804.074,17
Analisa SNI 2016

Membuat 1 m3 Footplat kolom 15/30 cm, tebal 20 cm beton bertulang (besi + bekisting) K.175, w/c = 0,56

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 1,650 78.000,00 128.700,00
Tukang Batu L.02 OH 0,275 86.000,00 23.650,00
Tukang Kayu L.02 OH 0,275 86.000,00 23.650,00
Tukang Besi L.02 OH 0,275 86.000,00 23.650,00
Kepala Tukang L,03 OH 0,275 95.000,00 26.125,00
Mandor L.04 OH 0,083 98.000,00 8.134,00
JUMLAH TENAGA KERJA 233.909,00
B BAHAN
Semen Portland kg 326,000 1.250,00 407.500,00
Pasir beton kg 760,000 104,60 79.496,00
Kerikil kg 1.029,000 193,29 198.894,27
Air Liter 215,000 10,00 2.150,00
Besi Beton (Polos/Ulir) kg 100,333 12.010,00 1.205.003,33
Kawat Beton kg 3,200 22.010,00 70.432,00
Kayu kelas III m3 0,320 1.604.770,00 513.526,40
Paku 5-10 cm Kg 3,200 22.010,00 70.432,00
Minyak begisting Liter 1,600 5.510,00 8.816,00
JUMLAH HARGA BAHAN 2.556.250,00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 2.790.159,00
E Overhead & Profit (10%) 10% X D 279.015,90
F Harga Satuan Pekerjaan (D+E) 3.069.174,90
ANALISA HARGA SATUAN KUSEN PINTU JENDELA ALUMINIUM
NO TYPE SAT. VOL. HARGA SAT. JUMLAH HARGA

1 Kusen Type PJ (pintu Double) dan Jendela kaca mati


a Bahan
Kusen Aluminium 4" m' 19,20 112.030,00 2.150.976,00
Daun Pintu Kaca Tempered 12 mm Lengkap Asesories (Engsel unit 1,00 7.000.000,00 7.000.000,00
pach Fitting top bottom, overpanel, floor hinges & Bottom
patch lock +cylinder)

ACP +rangka hollow galvanis 4x4 cm m2 2,22 1.004.858,10 2.230.784,99


Kaca Bening 5 mm m2 4,25 135.100,00 573.958,84
Sealant m' 19,20 2.510,00 48.192,00
Sanblast Stiker silver m2 1,42 60.010,00 85.214,20
Pull Handle besar psg 2,00 180.010,00 360.020,00

b Upah
Upah Pasang Kusen m' 19,20 5.000,00 96.000,00
Upah Pasang Pintu, Jendela & kaca unit 1,00 150.000,00 150.000,00
12.695.146,03
Pembulatan 12.690.000,00
3 Kusen Type P1
a Bahan
Kusen Aluminium 4" m' 6,60 112.030,00 739.398,00
Daun Pintu Kaca Bening 8 mm m2 2,40 250.100,00 600.240,00
Bingkai Daun Pintu rangka aluminium m1 14,72 90.030,00 1.325.241,60
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 2,00 45.010,00 90.020,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Door Closer unit 1,00 270.010,00 270.010,00
Sealant m' 6,60 2.510,00 16.566,00
Sanblast Stiker silver m2 1,20 60.010,00 72.012,00

b Upah
Upah Pasang Kusen m' 6,60 5.000,00 33.000,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
3.589.567,60
Pembulatan 3.580.000,00
3 Kusen Type P2
a Bahan
Kusen Aluminium 4" m' 14,72 112.030,00 1.649.081,60
Daun Pintu Kaca Bening 8 mm m2 2,40 250.100,00 600.240,00
Bingkai Daun Pintu rangka aluminium m1 14,72 90.030,00 1.325.241,60
Kaca bening 5 mm m2 1,67 135.100,00 225.508,92
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 2,00 45.010,00 90.020,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Door Closer unit 1,00 270.010,00 270.010,00
Sealant m' 14,72 2.510,00 36.947,20
Sanblast Stiker silver m2 1,20 60.010,00 72.012,00

b Upah
Upah Pasang Kusen m' 14,72 5.000,00 73.600,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
4.785.741,32
Pembulatan 4.780.000,00
3 Kusen Type P3 (pintu Panil)
a Bahan
Kusen Aluminium 4" m' 5,88 112.030,00 658.736,40
Daun Pintu Panil Kayu Jati m2 2,16 422.551,23 912.710,65
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 1,00 45.010,00 45.010,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Sealant m' 5,88 2.510,00 14.758,80

b Upah
Upah Pasang Kusen m' 5,88 5.000,00 29.400,00
Upah Pasang Pintu unit 1,00 150.000,00 150.000,00
2.103.695,85
Pembulatan 2.100.000,00
4 Kusen Type P4 (Pintu KM/WC)
a Bahan
Kusen Aluminium 4" m' 5,00 112.030,00 560.150,00
Daun Pintu Kaca ES 5 mm m2 1,00 200.200,00 201.080,88
Bingkai Daun Pintu dan Boven rangka aluminium m1 6,30 90.030,00 567.189,00
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 1,00 45.010,00 45.010,00
Double Cylinder bulat u/ KM bh 1,00 145.010,00 145.010,00
Sealant m' 5,00 2.510,00 12.550,00

b Upah
Upah Pasang Kusen m' 5,00 5.000,00 25.000,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
1.814.049,88
Pembulatan 1.810.000,00
6 Kusen Type P5 (Shaft)
a Bahan
Kusen Aluminium 4" m' 4,20 112.030,00 470.526,00
Teakwood 3 mm lapis alumunium foil m2 1,54 493.765,56 760.398,96
Engsel Pintu 4" (3 bh tiap daun) bh 3,00 18.010,00 54.030,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Papan Kayu klas II m3 0,13 2.604.770,00 328.201,02
Paku 5 cm Kg 0,25 22.010,00 5.502,50

b Upah
Upah Pasang Kusen m' 4,20 5.000,00 21.000,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
1.844.668,48
Pembulatan 1.840.000,00
3 Kusen Type P6
a Bahan
Kusen Aluminium 4" m' 5,30 112.030,00 593.759,00
Daun Pintu Kaca Bening 8 mm m2 1,30 250.100,00 325.630,20
Bingkai Daun Pintu rangka aluminium m1 6,30 90.030,00 567.189,00
Engsel Pintu 4" (3 bh tiap daun) bh 3,00 18.010,00 54.030,00
Pull Handle psg 1,00 45.010,00 45.010,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Sealant m' 5,30 2.510,00 13.303,00
Sanblast Stiker silver m2 0,63 60.010,00 37.806,30

b Upah
Upah Pasang Kusen m' 5,30 5.000,00 26.500,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
1.998.247,50
Pembulatan 1.990.000,00
2 Kusen Type DP1(Pintu Double) dan Partisi Kaca + Kalsiboard 6 mm
a Bahan
Kusen Aluminium 4" m' 24,98 112.030,00 2.798.509,40
Daun Pintu Kaca Bening 8 mm m2 2,40 250.100,00 600.240,00
Bingkai Daun Pintu rangka aluminium m1 14,40 90.030,00 1.296.432,00
Kaca bening 5 mm m2 6,91 135.100,00 933.243,78
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 2,00 45.010,00 90.020,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Door Closer unit 2,00 270.010,00 540.020,00
Sealant m' 24,98 2.510,00 62.699,80
Sanblast Stiker silver m2 2,42 60.010,00 145.224,20
Kalsiboard 6 mm (double luar dalam) m2 5,53 120.100,00 663.552,50
Baja Ringan 0.75/75 m 9,42 16.673,33 157.062,80
Paku Skrup bh 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00

b Upah
Upah Pasang Kusen m' 24,98 5.000,00 124.900,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
7.898.657,70
Pembulatan 7.890.000,00
2 Kusen Type DP2(Pintu Double) dan Partisi Kaca + Kalsiboard 6 mm
a Bahan
Kusen Aluminium 4" m' 24,48 112.030,00 2.742.494,40
Daun Pintu Kaca Bening 8 mm m2 2,40 250.100,00 600.240,00
Bingkai Daun Pintu rangka aluminium m1 14,40 90.030,00 1.296.432,00
Kaca bening 5 mm m2 5,59 135.100,00 755.641,32
Engsel Pintu 4" (3 bh tiap daun) bh 6,00 18.010,00 108.060,00
Pull Handle psg 2,00 45.010,00 90.020,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Door Closer unit 2,00 270.010,00 540.020,00
Sealant m' 24,48 2.510,00 61.444,80
Sanblast Stiker silver m2 2,25 60.010,00 135.022,50
Kalsiboard 6 mm (double luar dalam) m2 4,90 120.100,00 588.490,00
Baja Ringan 0.75/75 m 8,92 16.673,33 148.726,13
Paku Skrup bh 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00

b Upah
Upah Pasang Kusen m' 24,48 5.000,00 122.400,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
7.567.684,37
Pembulatan 7.560.000,00
13 Partisi Type DP3
a Bahan
Kusen Aluminium 4" m' 23,05 112.030,00 2.582.291,50
Kaca Bening 5 mm m2 7,85 135.100,00 1.060.264,80
Kalsiboard 6 mm (double luar dalam) m' 9,63 120.100,00 1.155.962,50
Baja Ringan 0.75/75 m2 13,95 16.673,33 232.593,00
Paku Skrup m1 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00
Sealant m' 23,05 2.510,00 57.855,50
Sanblast Stiker silver m2 2,20 60.010,00 132.022,00
b Upah
Upah Pasang Kusen m' 23,05 5.000,00 115.250,00
Upah Pasang Kaca Mati unit 1,00 100.000,00 100.000,00
5.479.912,52
Pembulatan 5.470.000,00
13 Partisi Type DP4
a Bahan
Kusen Aluminium 4" m' 22,30 112.030,00 2.498.269,00
Kaca Bening 5 mm m2 7,32 135.100,00 989.580,48
Kalsiboard 6 mm (double luar dalam) m2 9,00 120.100,00 1.080.900,00
Baja Ringan 0.75/75 m' 13,45 16.673,33 224.256,33
Paku Skrup bh 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00
Sealant m' 22,30 2.510,00 55.973,00
Sanblast Stiker silver m2 2,03 60.010,00 121.820,30
b Upah
Upah Pasang Kusen m' 22,30 5.000,00 111.500,00
Upah Pasang Kaca Mati unit 1,00 100.000,00 100.000,00
5.225.972,33
Pembulatan 5.220.000,00
13 Partisi Type DP5
a Bahan
Kusen Aluminium 4" m' 8,26 112.030,00 925.367,80
Kaca Bening 5 mm m2 2,46 135.100,00 332.805,34
Kalsiboard 6 mm (double luar dalam) m2 3,05 120.100,00 366.305,00
Baja Ringan 0.75/75 m1 4,94 16.673,33 82.366,27
Paku Skrup bh 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00
Sealant m' 8,26 2.510,00 20.732,60
Sanblast Stiker silver m2 0,68 60.010,00 40.806,80
b Upah
Upah Pasang Kusen m' 8,26 5.000,00 41.300,00
Upah Pasang Kaca Mati unit 1,00 100.000,00 100.000,00
1.953.357,03
Pembulatan 1.950.000,00
2 Kusen Type DP6 (Pintu) dan Partisi Kaca + Kalsiboard 6 mm
a Bahan
Kusen Aluminium 4" m' 13,71 112.030,00 1.535.931,30
Daun Pintu Kaca Bening 8 mm m2 1,48 250.100,00 370.148,00
Bingkai Daun Pintu rangka aluminium m1 7,76 90.030,00 698.632,80
Kaca bening 5 mm m2 2,60 135.100,00 350.989,80
Engsel Pintu 4" (3 bh tiap daun) bh 3,00 18.010,00 54.030,00
Pull Handle psg 1,00 45.010,00 45.010,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Door Closer unit 1,00 270.010,00 270.010,00
Sealant m' 13,71 2.510,00 34.412,10
Sanblast Stiker silver m2 1,15 60.010,00 69.011,50
Kalsiboard 6 mm (double luar dalam) m2 1,88 120.100,00 225.187,50
Baja Ringan 0.75/75 m 4,00 16.673,33 66.693,33
Paku Skrup bh 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00

b Upah
Upah Pasang Kusen m' 13,71 5.000,00 68.550,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
4.167.299,55
Pembulatan 4.160.000,00
13 Partisi Type DP7
a Bahan
Kusen Aluminium 4" m' 12,24 112.030,00 1.371.247,20
Kaca Bening 5 mm m2 3,58 135.100,00 483.009,52
Kalsiboard 6 mm (double luar dalam) m2 4,45 120.100,00 534.445,00
Baja Ringan 0.75/75 m' 7,31 16.673,33 121.882,07
Paku Skrup m2 15,00 910,00 13.650,00
Cotton Plaster bh 0,07 2.510,00 180,72
Coumpond Zak 0,13 15.220,00 1.902,50
Drilling screw R20 bh 10,00 910,00 9.100,00
Drilling screw R14 bh 10,00 760,00 7.600,00
Dynabold 12x 120 mm bh 4,00 2.810,00 11.240,00
Sealant m' 12,24 2.510,00 30.722,40
Sanblast Stiker silver m2 1,00 60.010,00 60.010,00
b Upah
Upah Pasang Kusen m' 12,24 5.000,00 61.200,00
Upah Pasang Kaca Mati unit 1,00 100.000,00 100.000,00
2.806.189,41
Pembulatan 2.800.000,00
2 Kusen Type DP8 (Pintu) dan Partisi Kaca 5 mm
a Bahan
Kusen Aluminium 4" m' 34,00 112.030,00 3.809.020,00
Daun Pintu Kaca Bening 8 mm m2 1,26 250.100,00 315.126,00
Bingkai Daun Pintu rangka aluminium m1 6,42 90.030,00 577.992,60
Kaca bening 5 mm m2 8,45 135.100,00 1.141.595,00
Engsel Pintu 4" (3 bh tiap daun) bh 3,00 18.010,00 54.030,00
Pull Handle psg 1,00 45.010,00 45.010,00
Lockcase bh 1,00 130.010,00 130.010,00
Double Cylinder bh 1,00 55.010,00 55.010,00
Sealant m' 34,00 2.510,00 85.340,00
Sanblast Stiker silver m2 3,13 60.010,00 187.831,30

b Upah
Upah Pasang Kusen m' 34,00 5.000,00 170.000,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
6.720.964,90
Pembulatan 6.720.000,00
2 Kusen Type DP9 Partisi Kaca 5 mm
a Bahan
Kusen Aluminium 4" m' 17,57 112.030,00 1.968.367,10
Kaca bening 5 mm m2 5,41 135.100,00 730.620,80
Sealant m' 17,57 2.510,00 44.100,70
Sanblast Stiker silver m2 1,60 60.010,00 96.016,00

b Upah
Upah Pasang Kusen m' 17,57 5.000,00 87.850,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
3.076.954,60
Pembulatan 3.070.000,00
2 Kusen Type DP10 Partisi Kaca 5 mm
a Bahan
Kusen Aluminium 4" m' 18,05 112.030,00 2.022.141,50
Kaca bening 5 mm m2 5,81 135.100,00 785.417,36
Sealant m' 18,05 2.510,00 45.305,50
Sanblast Stiker silver m2 1,70 60.010,00 102.017,00

b Upah
Upah Pasang Kusen m' 18,05 5.000,00 90.250,00
Upah Pasang Pintu & Boven unit 1,00 150.000,00 150.000,00
3.195.131,36
Pembulatan 3.190.000,00
7 Kusen Type J1
a Bahan
Kusen Aluminium 4" m' 11,61 112.030,00 1.300.668,30
Kaca Bening 5 mm m2 2,55 135.100,00 344.126,72
Bingkai Daun jendela rangka aluminium m1 8,16 90.030,00 734.644,80
Engsel casement 12" pada Jendela psg 2,00 35.010,00 70.020,00
Rambuncis bh 2,00 25.010,00 50.020,00
Sealant m' 11,61 2.510,00 29.141,10
Sanblast Stiker silver m2 0,75 60.010,00 45.007,50

b Upah
Upah Pasang Kusen m' 11,61 5.000,00 58.050,00
Upah Pasang Jendela & Boven unit 1,00 100.000,00 100.000,00
2.731.678,42
Pembulatan 2.730.000,00
8 Kusen Type J2
a Bahan
Kusen Aluminium 4" m' 21,20 112.030,00 2.375.036,00
Kaca Bening 5 mm m2 5,95 135.100,00 803.250,56
Bingkai Daun jendela rangka aluminium m1 7,68 90.030,00 691.430,40
Engsel casement 12" pada Jendela psg 2,00 35.010,00 70.020,00
Rambuncis bh 2,00 25.010,00 50.020,00
Sealant m' 21,20 2.510,00 53.212,00
Sanblast Stiker silver m2 1,73 60.010,00 103.817,30

b Upah
Upah Pasang Kusen m' 21,20 5.000,00 106.000,00
Upah Pasang Jendela & Boven unit 1,00 100.000,00 100.000,00
4.352.786,26
4.350.000,00
8 Kusen Type J3
a Bahan
Kusen Aluminium 4" m' 21,20 112.030,00 2.375.036,00
Kaca Bening 5 mm m2 5,96 135.100,00 805.412,16
Bingkai Daun jendela & Boven rangka aluminium m1 8,48 90.030,00 763.454,40
Engsel casement 12" pada Jendela psg 2,00 35.010,00 70.020,00
Rambuncis bh 2,00 25.010,00 50.020,00
Sealant m' 21,20 2.510,00 53.212,00
Sanblast Stiker silver m2 1,75 60.010,00 105.017,50

b Upah
Upah Pasang Kusen m' 21,20 5.000,00 106.000,00
Upah Pasang Jendela & Boven unit 1,00 100.000,00 100.000,00
4.428.172,06
4.420.000,00
8 Kusen Type J4
a Bahan
Kusen Aluminium 4" m' 44,29 112.030,00 4.961.808,70
Kaca Bening 5 mm m2 8,88 135.100,00 1.199.688,00
Bingkai Daun jendela & Boven rangka aluminium m1 7,88 90.030,00 709.436,40
Engsel casement 12" pada Jendela psg 2,00 35.010,00 70.020,00
Rambuncis bh 2,00 25.010,00 50.020,00
Sealant m' 44,29 2.510,00 111.167,90
Sanblast Stiker silver m2 1,98 60.010,00 118.819,80

b Upah
Upah Pasang Kusen m' 44,29 5.000,00 221.450,00
Upah Pasang Jendela & Boven unit 1,00 100.000,00 100.000,00
7.542.410,80
7.540.000,00
15 Kusen Type BV
a Bahan
Kusen Aluminium 4" m' 5,66 112.030,00 634.089,80
Kaca Bening 5 mm m2 0,98 135.100,00 132.938,40
Sealant m' 5,66 2.510,00 14.206,60
Sanblast Stiker silver m2 0,50 60.010,00 30.005,00
b Upah
Upah Pasang Kusen m' 5,66 5.000,00 28.300,00
Upah Pasang Boven Unit 1,00 100.000,00 100.000,00
939.539,80
Pembulatan 930.000,00
15 Kusen Type BV2
a Bahan
Kusen Aluminium 4" m' 5,64 112.030,00 631.849,20
Kaca Bening 5 mm m2 0,98 135.100,00 132.938,40
Bingkai Daun Boven rangka aluminium m1 5,04 90.030,00 453.751,20
Engsel casement 8" pada Boven psg 2,00 25.010,00 50.020,00
Rambuncis bh 2,00 25.010,00 50.020,00
Sealant m' 5,64 2.510,00 14.156,40
b Upah
Upah Pasang Kusen m' 5,64 5.000,00 28.200,00
Upah Pasang Boven Unit 1,00 100.000,00 100.000,00
1.460.935,20
Pembulatan 1.460.000,00
16 Kusen Type BV3
a Bahan
Kusen Aluminium 4" m' 3,22 112.030,00 360.736,60
Kaca Bening 5 mm m2 0,49 135.100,00 66.469,20
Bingkai Daun Boven rangka aluminium m1 2,52 90.030,00 226.875,60
Engsel casement 8" pada Boven psg 1,00 25.010,00 25.010,00
Rambuncis bh 1,00 25.010,00 25.010,00
Sealant m' 3,22 2.510,00 8.082,20
b Upah
Upah Pasang Kusen m' 3,22 5.000,00 16.100,00
Upah Pasang Boven Unit 1,00 100.000,00 100.000,00
828.283,60
Pembulatan 820.000,00
DAFTAR HARGA SATUAN BAHAN

PEKERJAAN PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE

LOKASI KOTA SOE - KAB. TIMOR TENGAH SELATAN

HARGA DASAR ONGKOS ANGKUT HARGA SATUAN


NO. NAMA / JENIS BAHAN SATUAN

(Rp) (Rp) (Rp)

PASIR - SIRTU
1 Pasir Urug m³ 95.000,00 26.440,00 121.440,00

2 Pasir Pasang m³ 120.000,00 26.440,00 146.440,00


3 Pasir Cor m³ 120.000,00 26.440,00 146.440,00

4 Sirtu m³ 60.000,00 4.890,00 64.890,00


BATU
1 Batu Karang/Gunung 15/20 m³ 95.000,00 4.890,00 99.890,00

2 Koral Beton 1/2, 2/3 (pecah mesin) m³ 234.500,00 26.440,00 260.940,00


3 Koral Beton 3/5 (koral biasa) m³ 210.000,00 26.440,00 236.440,00

4 Batu batako Bh 3.500,00 40,00 3.540,00


5 Batu alam andesit alur lurus 15x30 cm Bh 6.000,00 30,00 6.030,00

6 Bata Merah uk. 5x11x22 cm Bh 700,00 10,00 710,00


7 Batu Rooster/terawang Bh 10.000,00 20,00 10.020,00
8 Batu Paving tebal 6 cm Bh 3.500,00 20,00 3.520,00

SEMEN / P.C.
1 Semen Pc 40 kg zak 49.500,00 220,00 49.720,00

2 Semen Pc 1kg 1Kg 1.237,50 12,50 1.250,00

3 Semen warna 5 Kg zak 48.000,00 160,00 48.160,00


4 Semen warna 1Kg 9.600,00 10,00 9.610,00

KAYU
1 Kayu klas I papan 3/20 (Jati/kayu merah) m³ 3.500.000,00 4.770,00 3.504.770,00

2 Kayu klas I papan 3/20 (Bayam) m³ 14.500.000,00 4.770,00 14.504.770,00

3 Kayu klas II papan 3/20 Lokal m³ 2.600.000,00 4.770,00 2.604.770,00


4 Kayu klas II usuk 5/7 m³ 2.600.000,00 4.770,00 2.604.770,00

5 Kayu / Papan begesting Kls III lokal m³ 1.600.000,00 4.770,00 1.604.770,00


6 Kayu klas II 6/12 cm lokal m³ 2.600.000,00 4.770,00 2.604.770,00

7 Kayu klas II 5/11 cm lokal m³ 2.600.000,00 4.770,00 2.604.770,00


8 Kayu klas I lokal (jati / Kayu Merah) m³ 3.500.000,00 4.770,00 3.504.770,00

9 Kayu klas I lokal (Bayam) m³ 14.000.000,00 4.770,00 14.004.770,00


10 Kayu klas II 4/6 cm lokal m³ 2.600.000,00 4.770,00 2.604.770,00

11 Kayu klas II 2/3 cm lokal m³ 2.600.000,00 4.770,00 2.604.770,00


12 Kayu Bulat Btg 5.000,00 80,00 5.080,00
TRIPLEKS / KAYU LAPIS.

1 Teakwood lbr 75.000,00 100,00 75.100,00


2 Plywood 9 mm lbr 115.000,00 100,00 115.100,00

3 Kalciboard 4 mm Lbr 70.000,00 100,00 70.100,00

4 Kalciboard 6 mm Lbr 120.000,00 100,00 120.100,00

5 Gypsum Board 9 mm Lbr 80.000,00 100,00 80.100,00

6 Teakwood lapis alumunium lbr 80.000,00 100,00 80.100,00


7 Papan Woodplank lbr 105.000,00 40,00 105.040,00
8 Lem kayu Kg 15.000,00 10,00 15.010,00
BESI
1 Besi beton polos Kg 12.000,00 10,00 12.010,00
2 Kawat bendrat Kg 22.000,00 10,00 22.010,00

3 Besi Siku 70.70.7 mm Kg 12.000,00 10,00 12.010,00


4 Kawat Las bh 200,00 10,00 210,00
5 Besi Plat Baja Kg 15.000,00 10,00 15.010,00
6 Paku > 5cm Kg 22.000,00 10,00 22.010,00
7 Paku < 5cm Kg 22.000,00 10,00 22.010,00

8 Paku calsiboard Kg 23.000,00 10,00 23.010,00


9 Paku seng Kg 24.000,00 10,00 24.010,00

10 Paku genteng metalroof kg 25.000,00 10,00 25.010,00


11 Skrup Mata Baja bh 900,00 10,00 910,00
12 Factory Applied Structural Adhesive bh 1.500,00 10,00 1.510,00

13 Sillicone Weatherseal m1 2.000,00 10,00 2.010,00


14 Paku gypsum kg 27.000,00 10,00 27.010,00

15 Besi Kanal UNP, U200, (200x807.5 mm) kg 19.750,00 10,00 19.760,00


15 Besi strip kg 12.000,00 10,00 12.010,00
16 Pipa galvanis ø 4" Medium A lnjr 1.855.000,00 200,00 1.855.200,00

17 Pipa galvanis ø 2.5" Medium A lnjr 1.250.000,00 200,00 1.250.200,00


18 Pipa galvanis ø 1 1/2" Medium A lnjr 650.000,00 70,00 650.070,00

19 Pipa galvanis ø 1" Medium A lnjr 450.000,00 70,00 450.070,00


20 Pipa galvanis ø 3/4" Medium A lnjr 350.000,00 70,00 350.070,00

21 Pipa galvanis ø 1/2" Medium A lnjr 150.000,00 70,00 150.070,00

PIPA P.V.C..
1 Pipa PVC AW dia 4" 4m ljr 150.000,00 40,00 150.040,00

2 Pipa PVC AW dia 3" 4m ljr 110.000,00 40,00 110.040,00


3 Pipa PVC AW dia 2 1/2" 4 m ljr 85.000,00 40,00 85.040,00

4 Pipa PVC AW dia 2" 4 m ljr 75.000,00 40,00 75.040,00

5 Pipa PVC AW dia 1 1/2" 4 m ljr 65.000,00 40,00 65.040,00


6 Pipa PVC AW dia 1" 4m ljr 80.000,00 40,00 80.040,00

7 Pipa PVC AW dia 3/4" 4 m ljr 34.000,00 40,00 34.040,00


8 Pipa PVC AW dia 1/2" 4 m ljr 26.000,00 40,00 26.040,00

9 Klem PVC bh 3.000,00 10,00 3.010,00

10 Lem PVC bh 10.000,00 10,00 10.010,00


11 Avour/floor drain bh 15.000,00 10,00 15.010,00

12 Penguras Bak bh 10.000,00 10,00 10.010,00


BAHAN PENUTUP ATAP & PLAFOND

1 Seng gelombang BJLS 0.30 lbr 73.000,00 40,00 73.040,00


2 Seng Licin/Bubungan seng plat BJLS 0.30 lbr 35.000,00 40,00 35.040,00

3 Seng gelombang BJLS 0.20 lbr 45.000,00 40,00 45.040,00


4 Nok Zincalume lbr 25.000,00 40,00 25.040,00

5 Seng Zincalume 0.40 mm M2 62.000,00 40,00 62.040,00


6 Laminated Glass Clear 99x99 cm, 12 mm M2 375.000,00 390,00 375.390,00

7 Genteng metal MULTI ROOF lbr 65.000,00 40,00 65.040,00

8 Bubungan Genteng Metal m1 20.000,00 40,00 20.040,00


9 Kalsiplank 8 corak jati uk. 0.8/20 cm m1 25.000,00 30,00 25.030,00
10 Lis plafon profil (gypsum 10-15 cm) ml 18.000,00 30,00 18.030,00
PENGECATAN + POLITUR
1 Kertas gosok lbr 3.500,00 10,00 3.510,00
2 Plamur Kg 12.000,00 10,00 12.010,00

3 Cat besi Kg 37.500,00 10,00 37.510,00


4 Cat kayu Kg 37.500,00 10,00 37.510,00
5 Cat tembok putih Kw.II (Matex/Avian) Kg 25.000,00 10,00 25.010,00
6 Cat tembok putih Kw.III (Aries-Colombus) Kg 20.000,00 10,00 20.010,00
7 Cotton plaster bh 2.500,00 10,00 2.510,00

8 Coumpond Zak 15.000,00 220,00 15.220,00


9 Cat meni Kg 19.250,00 10,00 19.260,00

10 waterproofing (ex-Sika) Kg 95.000,00 10,00 95.010,00


11 Teak Oil / Plitur Ltr 27.500,00 10,00 27.510,00
12 Minyak cat / thiner B Ltr 20.000,00 10,00 20.010,00

13 Minyak cat / afduner Ltr 20.000,00 10,00 20.010,00


14 Minyak cat untuk meni Ltr 16.500,00 10,00 16.510,00

15 Teer kg 33.522,50 7,50 33.530,00


16 Politur Ltr 7.500,00 10,00 7.510,00
17 Politur Jadi Ltr 10.000,00 10,00 10.010,00

18 Dumpul kg 35.000,00 10,00 35.010,00


19 Minyak begesting Ltr 5.500,00 10,00 5.510,00

20 Kuas kecil/roll 4" Bh 14.850,00 10,00 14.860,00


LANTAI

1 Keramik 40/40 cm (teksture halus & bermotif) m2 84.000,00 100,00 84.100,00

2 Keramik 40/40 cm (teksture kasar/anti slip & bermotif) m2 85.000,00 100,00 85.100,00
3 Keramik Mozaik Venus m2 800.000,00 130,00 800.130,00

4 Granit 50/50 cm warna Krem m2 165.000,00 130,00 165.130,00


5 Granit 60/60 cm warna Krem m2 210.000,00 130,00 210.130,00

6 Keramik 60/60 cm (teksture kasar/anti slip & bermotif) m2 138.000,00 130,00 138.130,00

8 Keramik 25/40 cm teksture halus bh 5.500,00 50,00 5.550,00


9 Keramik 20/20 cm (Wafel) bh 2.200,00 50,00 2.250,00

10 Keramik 20/25 cm (Motif) bh 3.000,00 50,00 3.050,00


11 Keramik List 10/20 cm (Motif) bh 1.500,00 50,00 1.550,00

12 Plint keramik 10/50 cm (Motif) bh 1.700,00 50,00 1.750,00

13 Plint keramik 10/40 cm (Motif) bh 1.800,00 50,00 1.850,00


14 Plint Keramik 10/60 cm (Motif) bh 30.000,00 50,00 30.050,00

15 Stepnoizing 8x40 cm bh 4.000,00 50,00 4.050,00


PENGGANTUNG & PENGUNCI

1 Krepyak Nako bh 55.000,00 40,00 55.040,00


2 Engsel Pintu 4" bh 18.000,00 10,00 18.010,00

3 Engsel jendela bh 15.000,00 10,00 15.010,00


4 Engsel Casement 8" bh 25.000,00 10,00 25.010,00

5 Grendel 3" bh 7.500,00 10,00 7.510,00


6 Grendel pintu bh 12.500,00 10,00 12.510,00

7 Kunci tanam pintu bh 175.000,00 10,00 175.010,00

8 Pull Handle Sedang Bh 45.000,00 10,00 45.010,00


9 Pull Handle Besar Bh 180.000,00 10,00 180.010,00

10 Engsel Casement 12" bh 35.000,00 10,00 35.010,00

11 Double Cylinder bh 55.000,00 10,00 55.010,00

12 Double Cylinder bulat u/ KM bh 145.000,00 10,00 145.010,00


13 Lockcase Psg 130.000,00 10,00 130.010,00
14 Rambuncis Psg 25.000,00 10,00 25.010,00
15 Kaca Panasap Biru Muda 5 mm m2 203.000,00 100,00 203.100,00
16 Kaca Panasap Biru Muda 8 mm m2 550.000,00 130,00 550.130,00

17 Kaca Es 5 mm m2 200.000,00 200,00 200.200,00


18 Gembok Besar Bh 15.000,00 10,00 15.010,00
19 Kait Angin Bh 9.000,00 10,00 9.010,00
20 Door Holder magnet Bh 55.000,00 10,00 55.010,00
21 Door Closer Bh 270.000,00 10,00 270.010,00

23 Kaca Bening/polos 8 mm m2 250.000,00 100,00 250.100,00


24 Kaca Bening/polos 5 mm m2 135.000,00 100,00 135.100,00

SANITASI
1 Kran air type Vernekel bh 40.000,00 10,00 40.010,00
2 Closet duduk porselen putih setara Toto komplet bh 3.500.000,00 960,00 3.500.960,00

3 Closet jongkok porselin setara Toto bh 550.000,00 640,00 550.640,00


4 Buis Beton Ø 50 cm m' 750.000,00 80,00 750.080,00

5 Bak cuci Stainlesstel(Kichen Sink) single bak unit 850.000,00 390,00 850.390,00
5 Bak cuci Stainlesstel(Kichen Sink) double bak unit 1.000.000,00 390,00 1.000.390,00
6 Wastafel Komplet unit 1.500.000,00 640,00 1.500.640,00

7 Urinoir Komplet unit 1.700.000,00 640,00 1.700.640,00


8 Bak air Fiber 1 M3 unit 600.000,00 960,00 600.960,00
9 Grab bar Disability safety/pegangan kamar mandi Toilet stainles unit 650.000,00 960,00 650.960,00
lipat

10 Spoel Hoek setara toto unit 6.500.000,00 960,00 6.500.960,00


11 Waterdrain bh 5.000,00 10,00 5.010,00

12 Sealtape bh 5.000,00 10,00 5.010,00

13 Glass Block bh 45.000,00 40,00 45.040,00


14 Knee PVC 2" bh 7.500,00 10,00 7.510,00

15 Knee PVC 4" bh 15.000,00 10,00 15.010,00

16 Tee GIP 1/2" bh 7.500,00 10,00 7.510,00


17 Tee PVC 2" bh 7.500,00 10,00 7.510,00

18 Tee PVC 4" bh 15.000,00 10,00 15.010,00


19 Shock GIP 1/2" bh 7.500,00 10,00 7.510,00

20 Shock PVC 2" bh 10.000,00 10,00 10.010,00

21 Shock PVC 4" bh 15.000,00 10,00 15.010,00


22 Pintu PVC Km/Wc unit 850.000,00 200,00 850.200,00

ELEKTRIKAL
1 Stop kontak merk broco bh 27.000,00 10,00 27.010,00

2 Stop kontak AC bh 40.000,00 10,00 40.010,00

3 Saklar ganda merk broco bh 30.000,00 10,00 30.010,00


4 Saklar tunggal merk broco bh 25.000,00 10,00 25.010,00

5 Saklar triple merk broco bh 35.000,00 10,00 35.010,00

6 MCB 1 fase bh 80.000,00 10,00 80.010,00


7 MCB 3 fase bh 350.000,00 10,00 350.010,00

8 Pipa conduit dia.20 m 5.000,00 10,00 5.010,00


9 Sekring box unit 85.000,00 10,00 85.010,00

10 Kabel NYA 3x 2,5 mm2 m1 10.000,00 10,00 10.010,00

11 Kabel NYM 3x 2,5 mm2 m1 17.000,00 10,00 17.010,00


12 ITC 2 Pairs, 0.6 mm m1 12.000,00 10,00 12.010,00
13 Lampu Sorot LED 50 watt lengkap kap lampu Unit 325.000,00 10,00 325.010,00
14 Lampu Philips LED Downlight Outbow DN027C 18 Watt bh 190.000,00 10,00 190.010,00
15 Lampu Downlight LED Philips 3,5W Meson Gen 3 Putih bh 95.000,00 10,00 95.010,00

16 Lampu SL 18 watt setara philps bh 40.000,00 10,00 40.010,00


17 Lampu Led pada huruf, Motif Daerah dan logo unit 2.000.000,00 10,00 2.000.010,00
18 Lampu Neon Box/ TL 2x18 Watt bh 250.000,00 10,00 250.010,00
19 Batang Arde bh 500.000,00 10,00 500.010,00

20 Kawat Arde bh 50.000,00 10,00 50.010,00

21 MCCB 400 A, 4 P, 50 kA (adjustable trip unit) bh 6.500.000,00 10,00 6.500.010,00

22 MCCB 250 A, 3 P, 36 kA Bh 2.500.000,00 10,00 2.500.010,00


23 MCCB 200 A, 3 P, 36 kA Bh 2.000.000,00 10,00 2.000.010,00

24 MCCB 160 A, 3 P, 36 kA Bh 1.500.000,00 10,00 1.500.010,00


25 MCCB 125 A, 3 P, 36 kA Bh 1.300.000,00 10,00 1.300.010,00
26 MCCB 60 A, 3 P, 18 kA Bh 1.000.000,00 10,00 1.000.010,00

27 MCCB 50 A, 3 P, 36 kA Bh 800.000,00 10,00 800.010,00


28 MCCB 25 A, 3 P, 10 kA Bh 500.000,00 10,00 500.010,00

29 MCCB 15 A, 3 P, 10 kA Bh 450.000,00 10,00 450.010,00


30 MCB 10 A, 1 P, 6 kA Bh 200.000,00 10,00 200.010,00

31 MCB 6 A, 1 P, 6 kA Bh 100.000,00 10,00 100.010,00

29 Contactor 400 A + electric - mech. Interlock ex ASCO seri 7000 Bh 4.000.000,00 10,00 4.000.010,00
30 ATS digital controller ex ASCO seri 7000 Bh 2.150.000,00 10,00 2.150.010,00

31 CT 400/5A Bh 350.000,00 10,00 350.010,00


32 CT 200/5A Bh 150.000,00 10,00 150.010,00

33 Cosphi-meter Bh 500.000,00 10,00 500.010,00


34 Aux relay 220 VAC Bh 450.000,00 10,00 450.010,00
35 Fuse 2 A + fuse holder Bh 80.000,00 10,00 80.010,00

36 Pilot lamp Bh 45.000,00 10,00 45.010,00

37 Push button ON (metal) Bh 150.000,00 10,00 150.010,00


38 Push button OFF (metal) Bh 150.000,00 10,00 150.010,00

39 Busbar 600 A full neutral, 5 bus Bh 450.000,00 10,00 450.010,00


40 Busbar 250 A full neutral, 5 bus Bh 250.000,00 10,00 250.010,00

41 Busbar 40 A full neutral, 5 bus Bh 80.000,00 10,00 80.010,00

42 Control wiring + aksesori Bh 400.000,00 10,00 400.010,00


43 Y-D starter 5 kW Bh 150.000,00 10,00 150.010,00

44 Y-D starter 37 kW Bh 400.000,00 10,00 400.010,00


45 Direct on Line Starter 1,5 kW Bh 500.000,00 10,00 500.010,00
46 A-meter 0 - 150 A Bh 500.000,00 10,00 500.010,00
47 A/O/M selector switch Bh 250.000,00 10,00 250.010,00
48 Exhaust Fan Type Axial Wall Kap. 100 CFM Unit 500.000,00 10,00 500.010,00
49 Exhaust Fan Type Axial Wall Kap. 300 CFM Unit 1.000.000,00 10,00 1.000.010,00

50 Panel 160 (L) x 60 (D) x 220 (T) cm Bh 3.500.000,00 10,00 3.500.010,00

51 Panel 70 (L) x 30 (d) x 100 (T) cm Bh 1.500.000,00 10,00 1.500.010,00


52 Panel 50 (L) x 25 (D) x 60 (T) cm Bh 750.000,00 10,00 750.010,00
BAJA RINGAN & ALUMUNIUM
1 Kanal C 75-75 ljr 100.000,00 40,00 100.040,00
2 Reng Butten R.30-45 ljr 55.000,00 30,00 55.030,00

3 Drilling screw R20 bh 900,00 10,00 910,00


4 Drilling screw R14 bh 750,00 10,00 760,00
5 Dynabold 12x 120 mm bh 2.800,00 10,00 2.810,00
6 Aluminium profil natural 4" M1 112.000,00 40,00 112.040,00
7 Profil Alumunium T M1 10.000,00 30,00 10.030,00

8 Alumunium Frame 4" untuk bingkai pintu M1 112.000,00 30,00 112.030,00


9 Alumunium Frame 3" untuk bingkai jendela M1 90.000,00 30,00 90.030,00

10 Besi Plat Hitam tebal 1.2 mm uk. 1.2x2.4 m M2 160.000,00 70,00 160.070,00
11 Alumunium Composite Panel finishing PVDF (setara seven) M2 805.000,00 70,00 805.070,00
12 List Kaca karet m' 4.000,00 30,00 4.030,00

13 Skrup Fixcer buah 500,00 10,00 510,00


14 Sealant m' 2.500,00 10,00 2.510,00
FIRE ALARM

1 Master Control Fire Alarm Konventional 10 Zone Unit 7.000.000,00 10,00 7.000.010,00
2 Alarm Bell Unit 450.000,00 10,00 450.010,00

3 Annunciator panel 5 zone Unit 5.000.000,00 200,00 5.000.200,00


4 Smoke Detector ( Konventional ) bh 800.000,00 200,00 800.200,00

5 Portable extinguisher 3.5 NAF PIV unit 2.500.000,00 390,00 2.500.390,00

6 Heat Detector ( ROR ) Konvetional unit 750.000,00 10,00 750.010,00


7 Manual break glass unit 575.000,00 10,00 575.010,00

8 Indicator Lamp unit 350.000,00 10,00 350.010,00


9 Hidrant Luar (Hydrant + Box Hidrant Lengkap Selang) unit 5.000.000,00 390,00 5.000.390,00

PENANGKAL PETIR
1 Penangkal Petir Electrostatik (Lighting Protection) Flash Vectron/ setara
unit 10.500.000,00 390,00 10.500.390,00

2 Instalasi Penangkal Petir (Kabel BC 70mm2 +Klem) M 150.000,00 390,00 150.390,00

3 Grounding unit 4.000.000,00 390,00 4.000.390,00

CCTV

1 Kamera CCTV Outdoor 1000 TVL IR Kamera Unit 1.700.000,00 390,00 1.700.390,00
2 Kamera CCTV Indoor Unit 1.100.000,00 390,00 1.100.390,00

3 Adaptor Unit 60.000,00 390,00 60.390,00


4 Monitor 32 " Full HD Unit 4.500.000,00 390,00 4.500.390,00
5 DVR 32 Channel (HDMI) Unit 5.500.000,00 390,00 5.500.390,00

6 UPS + Stabilizer (AVR) 1200 VA - 800 W unit 2.000.000,00 390,00 2.000.390,00

7 Hardisk 4 TB unit 3.300.000,00 390,00 3.300.390,00

8 Power suplay unit 400.000,00 390,00 400.390,00


AC

1 AC Split wall Mounted 9000 BTU/H unit 5.200.000,00 390,00 5.200.390,00


2 Pipa Liquit Ø 6.4 mm M 45.000,00 10,00 45.010,00

3 Pipa Gas Ø 9.5 mm M 65.000,00 10,00 65.010,00


LAIN - LAIN

1 Pompa Air Jet Pump head 30 M bh 2.500.000,00 390,00 2.500.390,00


2 Pipa Hollow/ Kotak 4x4 cm (untuk Plafond) lnjr 42.000,00 40,00 42.040,00
3 Pipa Hollow/ Kotak 2x4 cm (untuk Plafond) lnjr 30.000,00 30,00 30.030,00

4 Pipa Hollow Galvanis Pagar/ Kotak 2x4 cm tebal 1 mm lnjr 70.000,00 30,00 70.030,00
5 Pipa Hollow Galvanis Pagar/ Kotak 4x4 cm tebal 1 mm lnjr 115.000,00 30,00 115.030,00
6 Acrylic Putih Susu t= 3 mm m2 800.000,00 100,00 800.100,00

7 Cermin 125x180 cm unit 400.000,00 390,00 400.390,00


8 Cermin 70x100 cm unit 250.000,00 280,00 250.280,00

9 Sanblast Stiker silver m2 60.000,00 10,00 60.010,00


11 Profil tank Tangki Air Stainless Stel 1100 liter unit 6.000.000,00 200,00 6.000.200,00
12 Geotekstil Woven 200 gr m2 25.000,00 40,00 25.040,00
21 Mesin IPAL Paket Rp 381.000.000,00 381.000.000,00
ANALISA HARGA MATERIAL ON SITE
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE
LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

BIAYA WAKTU SIRKULS Produksi Per Hari Ongkos Angkut


Biaya Bahan
Kapasitas Kec. Rata- Jarak Angkut Waktu Jalan Waktu Sirklus Sesuai Bhn Bahan
HARGA SATUAN Jarak Angkut
NO. MATERIAL SAT Dump Truck rata ke lokasi(JA) Sewa Truck Waktu Bongkar Ke.lokasi Pek, Ke.lokasi Pek. Ke Lokasi Pek. Ke.lokasi Pek. KET.
DASAR DITEMPAT PP = 2 x JA Ke. Lokasi Pek.
(Q) (Km/Jam) (KM) (Rp./Hari) Muat (jam) (WJ) = (9/6+10) (WS) = 7/WJ WS x Q (10)/(13)
(KM) (14 ) + (3) (Rp)
(Menit) (Menit) (Sat.Sesuai Bahan ) (Rp)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
BAHAN PASIR & TANAH
1 Pasir Urug 95.000,00 m³ 4 65 18 1.226.000 36 0,05 0,60 11,59 46,37 26.439,84 121.440
2 Pasir Pasang 120.000,00 m³ 4 65 18 1.226.000 36 0,05 0,60 11,59 46,37 26.439,84 146.440
3 Pasir Cor 120.000,00 m³ 4 65 18 1.226.000 36 0,05 0,60 11,59 46,37 26.439,84 146.440
4 Sirtu 60.000,00 m³ 4 65 2 1.226.000 4 0,05 0,11 62,76 251,03 4.883,79 64.890
BATU
1 Batu Karang/Gunung 15/20 95.000,00 m³ 4 65 2 1.226.000 4 0,05 0,11 62,76 251,03 4.883,79 99.890
2 Koral Beton 1/2, 2/3 (pecah mesin) 234.500,00 m³ 4 65 18 1.226.000 36 0,05 0,60 11,59 46,37 26.439,84 260.940
3 Koral Beton 3/5 (koral biasa) 210.000,00 m³ 4 65 18 1.226.000 36 0,05 0,60 11,59 46,37 26.439,84 236.440
4 Batu batako 3.500,00 Bh 500 65 2 1.226.000 4 0,05 0,11 62,76 31.379,31 39,07 3.540
5 Batu alam andesit alur lurus 15x30 cm 6.000,00 Bh 700 65 2 1.226.000 4 0,05 0,11 62,76 43.931,03 27,91 6.030
6 Bata Merah uk. 5x11x22 cm 700,00 Bh 2000 65 2 1.226.000 4 0,05 0,11 62,76 125.517,24 9,77 710
7 Batu Rooster/terawang 10.000,00 Bh 1000 65 2 1.226.000 4 0,05 0,11 62,76 62.758,62 19,54 10.020
8 Batu Paving tebal 6 cm 3.500,00 Bh 1000 65 2 1.226.000 4 0,05 0,11 62,76 62.758,62 19,54 3.520
SEMEN / P.C.
1 Semen Pc 40 kg 49.500,00 zak 88 68 2 1.226.000 4 0,05 0,11 64,32 5.660,54 216,59 49.720
2 Semen Pc 1kg 1.237,50 1Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 1.250
3 Semen warna 5 Kg 48.000,00 zak 120 68 2 1.226.000 4 0,05 0,11 64,32 7.718,92 158,83 48.160
4 Semen warna 9.600,00 1Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 9.610
KAYU
1 Kayu klas I papan 3/20 (Jati/kayu merah) 3.500.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 3.504.770
2 Kayu klas I papan 3/20 (Bayam) 14.500.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 14.504.770
3 Kayu klas II papan 3/20 Lokal 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
4 Kayu klas II usuk 5/7 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
4 Kayu / Papan begesting Kls III lokal 1.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 1.604.770
5 Kayu klas II 6/12 cm lokal 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
6 Kayu klas II 5/11 cm lokal 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
7 Kayu klas I lokal (jati / Kayu Merah) 3.500.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 3.504.770
9 Kayu klas I lokal (Bayam) 14.000.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 14.004.770
8 Kayu klas II 4/6 cm lokal 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
9 Kayu klas II 2/3 cm lokal 2.600.000,00 m³ 4 68 2 1.226.000 4 0,05 0,11 64,32 257,30 4.764,92 2.604.770
10 Kayu Bulat 5.000,00 Btg 250 68 2 1.226.000 4 0,05 0,11 64,32 16.081,08 76,24 5.080
TRIPLEKS / KAYU LAPIS.
1 Teakwood 75.000,00 lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 75.100
2 Plywood 9 mm 115.000,00 lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 115.100
3 Kalciboard 4 mm 70.000,00 Lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 70.100
4 Kalciboard 6 mm 120.000,00 Lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 120.100
5 Gypsum Board 9 mm 80.000,00 Lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 80.100
6 Teakwood lapis alumunium 80.000,00 lbr 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 80.100
7 Papan Woodplank 105.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 105.040
8 Lem kayu 15.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 15.010
BESI
1 Besi beton polos 12.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 12.010
2 Kawat bendrat 22.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 22.010
3 Besi Siku 70.70.7 mm 12.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 12.010
4 Kawat Las 200,00 bh 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 210
5 Besi Plat Baja 15.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 15.010
6 Paku > 5cm 22.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 22.010
7 Paku < 5cm 22.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 22.010
8 Paku calsiboard 23.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 23.010
9 Paku seng 24.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 24.010
10 Paku genteng metalroof 25.000,00 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 25.010
11 Skrup Mata Baja 900,00 bh 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 910
12 Factory Applied Structural Adhesive 1.500,00 bh 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 1.510
13 Sillicone Weatherseal 2.000,00 m1 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 2.010
14 Paku gypsum 27.000,00 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 27.010
15 Besi Kanal UNP, U200, (200x807.5 mm) 19.750,00 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 19.760
15 Besi strip 12.000,00 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 12.010
16 Pipa galvanis ø 4" Medium A 1.855.000,00 lnjr 100 68 2 1.226.000 4 0,05 0,11 64,32 6.432,43 190,60 1.855.200
17 Pipa galvanis ø 2.5" Medium A 1.250.000,00 lnjr 100 68 2 1.226.000 4 0,05 0,11 64,32 6.432,43 190,60 1.250.200
18 Pipa galvanis ø 1 1/2" Medium A 650.000,00 lnjr 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 650.070
19 Pipa galvanis ø 1" Medium A 450.000,00 lnjr 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 450.070
20 Pipa galvanis ø 3/4" Medium A 350.000,00 lnjr 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 350.070
21 Pipa galvanis ø 1/2" Medium A 150.000,00 lnjr 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 150.070

PIPA P.V.C..
1 Pipa PVC AW dia 4" 4 m 150.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 150.040
2 Pipa PVC AW dia 3" 4 m 110.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 110.040
3 Pipa PVC AW dia 2 1/2" 4 m 85.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 85.040
4 Pipa PVC AW dia 2" 4 m 75.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 75.040
5 Pipa PVC AW dia 1 1/2" 4 m 65.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 65.040
6 Pipa PVC AW dia 1" 4 m 80.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 80.040
7 Pipa PVC AW dia 3/4" 4 m 34.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 34.040
8 Pipa PVC AW dia 1/2" 4 m 26.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 26.040
9 Klem PVC 3.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 3.010
10 Lem PVC 10.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 10.010
11 Avour/floor drain 15.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
12 Penguras Bak 10.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 10.010
BAHAN PENUTUP ATAP & PLAFOND
1 Seng gelombang BJLS 0.30 73.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 73.040
2 Seng Licin/Bubungan seng plat BJLS 0.30 35.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 35.040
3 Seng gelombang BJLS 0.20 45.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 45.040
4 Nok Zincalume 25.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 25.040
5 Seng Zincalume 0.40 mm 62.000,00 M2 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 62.040
6 Laminated Glass Clear 99x99 cm, 12 mm 375.000,00 M2 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 375.390
7 Genteng metal MULTI ROOF 65.000,00 lbr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 65.040
8 Bubungan Genteng Metal 20.000,00 m1 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 20.040
9 Kalsiplank 8 corak jati uk. 0.8/20 cm 25.000,00 m1 700 68 2 1.226.000 4 0,05 0,11 64,32 45.027,03 27,23 25.030
10 Lis plafon profil (gypsum 10-15 cm) 18.000,00 ml 700 68 2 1.226.000 4 0,05 0,11 64,32 45.027,03 27,23 18.030
PENGECATAN + POLITUR
1 Kertas gosok 3.500,00 lbr 25000 68 2 1.226.000 4 0,05 0,11 64,32 1.608.108,11 0,76 3.510
2 Plamur 12.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 12.010
3 Cat besi 37.500,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 37.510
4 Cat kayu 37.500,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 37.510
5 Cat tembok putih Kw.II (Matex/Avian) 25.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 25.010
6 Cat tembok putih Kw.III (Aries-Colombus) 20.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 20.010
7 Cotton plaster 2.500,00 bh 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 2.510
8 Coumpond 15.000,00 Zak 88 68 2 1.226.000 4 0,05 0,11 64,32 5.660,54 216,59 15.220
9 Cat meni 19.250,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 19.260
10 waterproofing (ex-Sika) 95.000,00 Kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 95.010
11 Teak Oil / Plitur 27.500,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 27.510
12 Minyak cat / thiner B 20.000,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 20.010
13 Minyak cat / afduner 20.000,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 20.010
14 Minyak cat untuk meni 16.500,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 16.510
15 Teer 33.522,50 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 33.530
16 Politur 7.500,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 7.510
17 Politur Jadi 10.000,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 10.010
18 Dumpul 35.000,00 kg 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 35.010
19 Minyak begesting 5.500,00 Ltr 4000 68 2 1.226.000 4 0,05 0,11 64,32 257.297,30 4,76 5.510
20 Kuas kecil/roll 4" 14.850,00 Bh 15000 68 2 1.226.000 4 0,05 0,11 64,32 964.864,86 1,27 14.860
LANTAI
1 Keramik 40/40 cm (teksture halus & bermotif) 84.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 84.100
2 Keramik 40/40 cm (teksture kasar/anti slip & bermotif) 85.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 85.100
3 Keramik Mozaik Venus 800.000,00 m2 150 68 2 1.226.000 4 0,05 0,11 64,32 9.648,65 127,06 800.130
4 Granit 50/50 cm warna Krem 165.000,00 m2 150 68 2 1.226.000 4 0,05 0,11 64,32 9.648,65 127,06 165.130
5 Granit 60/60 cm warna Krem 210.000,00 m2 150 68 2 1.226.000 4 0,05 0,11 64,32 9.648,65 127,06 210.130
6 Keramik 60/60 cm (teksture kasar/anti slip & bermotif) 138.000,00 m2 150 68 2 1.226.000 4 0,05 0,11 64,32 9.648,65 127,06 138.130
7 Keramik 20/40 cm (teksture halus & bermotif) 80.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 80.100
8 Keramik 25/40 cm teksture halus 5.500,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 5.550
9 Keramik 20/20 cm (Wafel) 2.200,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 2.250
10 Keramik 20/25 cm (Motif) 3.000,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 3.050
11 Keramik List 10/20 cm (Motif) 1.500,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 1.550
12 Plint keramik 10/50 cm (Motif) 1.700,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 1.750
13 Plint keramik 10/40 cm (Motif) 1.800,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 1.850
14 Plint Keramik 10/60 cm (Motif) 30.000,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 30.050
15 Stepnoizing 8x40 cm 4.000,00 bh 400 68 2 1.226.000 4 0,05 0,11 64,32 25.729,73 47,65 4.050
PENGGANTUNG & PENGUNCI
1 Krepyak Nako 55.000,00 bh 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 55.040
2 Engsel Pintu 4" 18.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 18.010
3 Engsel jendela 15.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
4 Engsel Casement 8" 25.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 25.010
5 Grendel 3" 7.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 7.510
6 Grendel pintu 12.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 12.510
7 Kunci tanam pintu 175.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 175.010
8 Pull Handle Sedang 45.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 45.010
9 Pull Handle Besar 180.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 180.010
10 Engsel Casement 12" 35.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 35.010
11 Double Cylinder 55.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 55.010
12 Double Cylinder bulat u/ KM 145.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 145.010
13 Lockcase 130.000,00 Psg 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 130.010
14 Rambuncis 25.000,00 Psg 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 25.010
15 Kaca Panasap Biru Muda 5 mm 203.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 203.100
16 Kaca Panasap Biru Muda 8 mm 550.000,00 m2 150 68 2 1.226.000 4 0,05 0,11 64,32 9.648,65 127,06 550.130
17 Kaca Es 5 mm 200.000,00 m2 100 68 2 1.226.000 4 0,05 0,11 64,32 6.432,43 190,60 200.200
18 Gembok Besar 15.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
19 Kait Angin 9.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 9.010
20 Door Holder magnet 55.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 55.010
21 Door Closer 270.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 270.010
22 Kaca Tempered 12 mm 750.000,00 m2 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 750.010
23 Kaca Bening/polos 8 mm 250.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 250.100
24 Kaca Bening/polos 5 mm 135.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 135.100
SANITASI
1 Kran air type Vernekel 40.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 40.010
2 Closet duduk porselen putih setara Toto komplet 3.500.000,00 bh 20 68 2 1.226.000 4 0,05 0,11 64,32 1.286,49 952,98 3.500.960
3 Closet jongkok porselin setara Toto 550.000,00 bh 30 68 2 1.226.000 4 0,05 0,11 64,32 1.929,73 635,32 550.640
4 Buis Beton Ø 50 cm 750.000,00 m' 250 68 2 1.226.000 4 0,05 0,11 64,32 16.081,08 76,24 750.080
5 Bak cuci Stainlesstel(Kichen Sink) single bak 850.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 850.390
5 Bak cuci Stainlesstel(Kichen Sink) double bak 1.000.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 1.000.390
6 Wastafel Komplet 1.500.000,00 unit 30 68 2 1.226.000 4 0,05 0,11 64,32 1.929,73 635,32 1.500.640
7 Urinoir Komplet 1.700.000,00 unit 30 68 2 1.226.000 4 0,05 0,11 64,32 1.929,73 635,32 1.700.640
8 Bak air Fiber 1 M3 600.000,00 unit 20 68 2 1.226.000 4 0,05 0,11 64,32 1.286,49 952,98 600.960
9 Grab bar Disability safety/pegangan kamar mandi Toilet stainles lipat 650.000,00 unit 20 68 2 1.226.000 4 0,05 0,11 64,32 1.286,49 952,98 650.960
10 Spoel Hoek setara toto 6.500.000,00 unit 20 68 2 1.226.000 4 0,05 0,11 64,32 1.286,49 952,98 6.500.960
11 Waterdrain 5.000,00 bh 2500 68 2 1.226.000 4 0,05 0,11 64,32 160.810,81 7,62 5.010
12 Sealtape 5.000,00 bh 2500 68 2 1.226.000 4 0,05 0,11 64,32 160.810,81 7,62 5.010
13 Glass Block 45.000,00 bh 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 45.040
14 Knee PVC 2" 7.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 7.510
15 Knee PVC 4" 15.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
16 Tee GIP 1/2" 7.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 7.510
17 Tee PVC 2" 7.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 7.510
18 Tee PVC 4" 15.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
19 Shock GIP 1/2" 7.500,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 7.510
20 Shock PVC 2" 10.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 10.010
21 Shock PVC 4" 15.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 15.010
ELEKTRIKAL
1 Stop kontak merk broco 27.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 27.010
2 Stop kontak AC 40.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 40.010
3 Saklar ganda merk broco 30.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 30.010
4 Saklar tunggal merk broco 25.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 25.010
5 Saklar triple merk broco 35.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 35.010
6 MCB 1 fase 80.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 80.010
7 MCB 3 fase 350.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 350.010
8 Pipa conduit dia.20 5.000,00 m 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 5.010
9 Sekring box 85.000,00 unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 85.010
10 Kabel NYA 3x 2,5 mm2 10.000,00 m1 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 10.010
11 Kabel NYM 3x 2,5 mm2 17.000,00 m1 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 17.010
12 ITC 2 Pairs, 0.6 mm 12.000,00 m1 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 12.010
13 Lampu Sorot LED 50 watt lengkap kap lampu 325.000,00 Unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 325.010
14 Lampu Philips LED Downlight Outbow DN027C 18 Watt 190.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 190.010
15 Lampu Downlight LED Philips 3,5W Meson Gen 3 Putih 95.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 95.010
16 Lampu SL 18 watt setara philps 40.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 40.010
17 Lampu Led pada huruf, Motif Daerah dan logo 2.000.000,00 unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.000.010
18 Lampu Neon Box/ TL 2x18 Watt 250.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 250.010
19 Batang Arde 500.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
20 Kawat Arde 50.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 50.010
21 MCCB 400 A, 4 P, 50 kA (adjustable trip unit) 6.500.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 6.500.010
22 MCCB 250 A, 3 P, 36 kA 2.500.000,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.500.010
23 MCCB 200 A, 3 P, 36 kA 2.000.000,00 unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.000.010
24 MCCB 160 A, 3 P, 36 kA 1.500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 1.500.010
25 MCCB 125 A, 3 P, 36 kA 1.300.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 1.300.010
26 MCCB 60 A, 3 P, 18 kA 1.000.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 1.000.010
27 MCCB 50 A, 3 P, 36 kA 800.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 800.010
28 MCCB 25 A, 3 P, 10 kA 500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
29 MCCB 15 A, 3 P, 10 kA 450.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 450.010
30 MCB 10 A, 1 P, 6 kA 200.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 200.010
31 MCB 6 A, 1 P, 6 kA 100.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 100.010
29 Contactor 400 A + electric - mech. Interlock ex ASCO seri 7000 4.000.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 4.000.010
30 ATS digital controller ex ASCO seri 7000 2.150.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.150.010
31 CT 400/5A 350.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 350.010
32 CT 200/5A 150.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 150.010
33 Cosphi-meter 500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
34 Aux relay 220 VAC 450.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 450.010
35 Fuse 2 A + fuse holder 80.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 80.010
36 Pilot lamp 45.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 45.010
37 Push button ON (metal) 150.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 150.010
38 Push button OFF (metal) 150.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 150.010
39 Busbar 600 A full neutral, 5 bus 450.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 450.010
40 Busbar 250 A full neutral, 5 bus 250.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 250.010
41 Busbar 40 A full neutral, 5 bus 80.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 80.010
42 Control wiring + aksesori 400.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 400.010
43 Y-D starter 5 kW 150.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 150.010
44 Y-D starter 37 kW 400.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 400.010
45 Direct on Line Starter 1,5 kW 500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
46 A-meter 0 - 150 A 500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
47 A/O/M selector switch 250.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 250.010
48 Exhaust Fan Type Axial Wall Kap. 100 CFM 500.000,00 Unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 500.010
49 Exhaust Fan Type Axial Wall Kap. 300 CFM 1.000.000,00 Unit 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 1.000.010
50 Panel 160 (L) x 60 (D) x 220 (T) cm 3.500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 3.500.010
51 Panel 70 (L) x 30 (d) x 100 (T) cm 1.500.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 1.500.010
52 Panel 50 (L) x 25 (D) x 60 (T) cm 750.000,00 Bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 750.010
BAJA RINGAN & ALUMUNIUM
1 Kanal C 75-75 100.000,00 ljr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 100.040
2 Reng Butten R.30-45 55.000,00 ljr 750 68 2 1.226.000 4 0,05 0,11 64,32 48.243,24 25,41 55.030
3 Drilling screw R20 900,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 910
4 Drilling screw R14 750,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 760
5 Dynabold 12x 120 mm 2.800,00 bh 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.810
6 Aluminium profil natural 4" 112.000,00 M1 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 112.040
7 Profil Alumunium T 10.000,00 M1 750 68 2 1.226.000 4 0,05 0,11 64,32 48.243,24 25,41 10.030
8 Alumunium Frame 4" untuk bingkai pintu 112.000,00 M1 750 68 2 1.226.000 4 0,05 0,11 64,32 48.243,24 25,41 112.030
9 Alumunium Frame 3" untuk bingkai jendela 90.000,00 M1 750 68 2 1.226.000 4 0,05 0,11 64,32 48.243,24 25,41 90.030
10 Besi Plat Hitam tebal 1.2 mm uk. 1.2x2.4 m 160.000,00 M2 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 160.070
11 Alumunium Composite Panel finishing PVDF (setara seven) 805.000,00 M2 300 68 2 1.226.000 4 0,05 0,11 64,32 19.297,30 63,53 805.070
12 List Kaca karet 4.000,00 m' 750 68 2 1.226.000 4 0,05 0,11 64,32 48.243,24 25,41 4.030
13 Skrup Fixcer 500,00 buah 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 510
14 Sealant 2.500,00 m' 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 2.510
FIRE ALARM
5 Portable extinguisher 3.5 NAF PIV 2.500.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 2.500.390
9 Hidrant Luar (Hydrant + Box Hidrant Lengkap Selang) 5.000.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 5.000.390
PENANGKAL PETIR
1 Penangkal Petir Electrostatik (Lighting Protection) Flash Vectron/ setara
10.500.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 10.500.390
2 Instalasi Penangkal Petir (Kabel BC 70mm2 +Klem) 150.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 150.390
3 Grounding 4.000.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 4.000.390

CCTV
1 Kamera CCTV Outdoor 1000 TVL IR Kamera 1.700.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 1.700.390
2 Kamera CCTV Indoor 1.100.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 1.100.390
3 Adaptor 60.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 60.390
4 Monitor 32 " Full HD 4.500.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 4.500.390
5 DVR 32 Channel (HDMI) 5.500.000,00 Unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 5.500.390
6 UPS + Stabilizer (AVR) 1200 VA - 800 W 2.000.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 2.000.390
7 Hardisk 4 TB 3.300.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 3.300.390
8 Power suplay 400.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 400.390

AC
1 AC Split wall Mounted 9000 BTU/H 5.200.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 5.200.390
2 Pipa Liquit Ø 6.4 mm 45.000,00 M 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 45.010
3 Pipa Gas Ø 9.5 mm 65.000,00 M 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 65.010
LAIN - LAIN
1 Pompa Air Jet Pump head 30 M 2.500.000,00 bh 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 2.500.390
2 Pipa Hollow/ Kotak 4x4 cm (untuk Plafond) 42.000,00 lnjr 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 42.040
3 Pipa Hollow/ Kotak 2x4 cm (untuk Plafond) 30.000,00 lnjr 700 68 2 1.226.000 4 0,05 0,11 64,32 45.027,03 27,23 30.030
4 Pipa Hollow Galvanis Pagar/ Kotak 2x4 cm tebal 1 mm 70.000,00 lnjr 700 68 2 1.226.000 4 0,05 0,11 64,32 45.027,03 27,23 70.030
5 Pipa Hollow Galvanis Pagar/ Kotak 4x4 cm tebal 1 mm 115.000,00 lnjr 700 68 2 1.226.000 4 0,05 0,11 64,32 45.027,03 27,23 115.030
6 Acrylic Putih Susu t= 3 mm 800.000,00 m2 200 68 2 1.226.000 4 0,05 0,11 64,32 12.864,86 95,30 800.100
7 Cermin 125x180 cm 400.000,00 unit 50 68 2 1.226.000 4 0,05 0,11 64,32 3.216,22 381,19 400.390
8 Cermin 70x100 cm 250.000,00 unit 70 68 2 1.226.000 4 0,05 0,11 64,32 4.502,70 272,28 250.280
9 Sanblast Stiker silver 60.000,00 m2 5000 68 2 1.226.000 4 0,05 0,11 64,32 321.621,62 3,81 60.010
11 Profil tank Tangki Air Stainless Stel 1100 liter 6.000.000,00 unit 100 68 2 1.226.000 4 0,05 0,11 64,32 6.432,43 190,60 6.000.200
12 Geotekstil Woven 200 gr 25.000,00 m2 500 68 2 1.226.000 4 0,05 0,11 64,32 32.162,16 38,12 25.040
21 Mesin IPAL 381.000.000,00 Paket 1 381.000.000
JENIS PEKERJAAN : Galian Utk Cutting Permukaan tapak bangunan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : Area Cutting + Pondasi
3 Kondisi Lahan : sedang / berbatu
4 Jam kerja efektif per-hari Tk 7 jam
5 Faktor pengembangan bahan Fk 1,2 -
6 Berat volume bahan D 1,4 Ton/M3

II. URUTAN KERJA


1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
Ke dalam bidang urugan untuk tapak bangunan
3 Pekerja membuang material hasil galian keluar
lokasi jalan sejauh L 2 Km
4 Sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0,9 M3
Faktor Bucket Fb 0,9 -
Faktor Efisiensi alat Fa 0,8 -

Waktu siklus Ts1 menit


- Menggali / memuat T1 1 menit
- Lain-lain T2 0,3 menit
Ts1 1,3 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 24,92 M3 / jam


Ts1 x Fh

Koefisien Alat / M3 = 1 : Q1 - 0,040 Jam

2.b. DUMP TRUCK (E08)


Kaasitas bak V M3
Faktor efisiensi alat Fa -
Kecepatan rata-rata bermuatan v1 Km/Jam
Kecepatan rata-rata kosong v2 Km/Jam
Waktu siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 menit
- Muat = (V : Q1) x 60 T3 menit
- Lain-lain T4 menit
Ts2 0 menit
Berlanjut ke halaman berikut
JENIS PEKERJAAN : Galian Utk Cutting Permukaan tapak bangunan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

Kapasitas Produksi / Jam = V x Fa x 60 Q2 M3 / Jam


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 - Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Keranjang + Sapu

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 24,92307692 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 174,4615385 M3
Kebutuhan tenaga :
- Pekerja P 4 orang
- Mandor M 1 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0,160 Jam
- Mandor = (Tk x M) : Qt (L03) 0,040 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 38.810,35 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : ............ bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0 M3
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE


LOKASI KOTA SOE - KAB. TIMOR TENGAH SELATAN
ITEM PEMBAYARAN NO. PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Galian Utk Cutting Permukaan tapak bangunan
TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0,160 11.142,86 1.788,36


2. Mandor (L03) jam 0,040 14.000,00 561,73

JUMLAH HARGA TENAGA 2.350,09

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Excavator (E10) jam 0,040 696.152,59 27.932,05

2 Alat Bantu Ls 1 5.000,00 5.000,00


(sekop, kereta dorong)

JUMLAH HARGA PERALATAN 32.932,05

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 35.282,14


E. OVERHEAD & PROFIT 10 % x D 3.528,21
F. HARGA SATUAN PEKERJAAN ( D + E ) 38.810,35
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.2.2 Analisa EI-322
JENIS PEKERJAAN : TIMBUNAN MATERIAL DARI HASIL GALIAN/CUTTING
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KET.

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7 Jam
5 Faktor pengembangan bahan Fk 1,1 -
6 Tebal hamparan padat t 0,08 M
7 Berat volume bahan (lepas) D 1,51 Ton/M3

II. URUTAN KERJA


1 Whell Loader memuat ke dalam Dump Truck
2 Dump Truck mengangkut ke lapangan dengan jarak
quari ke lapangan L 0 Km
3 Material dihampar dengan menggunakan Tenaga Kerja
4 Hamparan material disiram air dengan Watertank Truck
(sebelum pelaksanaan pemadatan) dan dipadatkan
dengan menggunakan Vibrator Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Bahan pilihan = 1 x Fk (M09) 1,1 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas Bucket V 1,5 M3
Faktor Bucket Fb 0,9 -
Faktor Efisiensi Alat Fa 0,83 -
Waktu sklus Ts1
- Muat T1 1 menit
Ts1 1 menit

Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 61,12 M3


Fk x Ts1

Koefisienalat /=M3
1 : Q1
= 1 / Q1 (E15) 0,016 Jam

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.2.2 Analisa EI-322
JENIS PEKERJAAN : TIMBUNAN MATERIAL DARI HASIL GALIAN/CUTTING
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan
No. URAIAN KODE KOEF. SATUAN
KETERANGAN

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 1 Km / Jam
Lebar efektif pemadatan b 1,6 M
Jumlah lintasan n 12 lintasan
Lajur lintasan N 3
Lebar Overlap bo 0,2 M
Faktor efisiensi alat Fa 0,85 -

Kapasitas Prod./Jam
(v x 1000)= x (N(b-bo)+bo) x t x Fa Q4 24,93 M3
n

Koefisien Alat=/ 1M3: Q4 (E19) 0,040 Jam

2.e. WATER TANK TRUCK (E23)


Volume tangki air V 4 M3
Kebutuhan air / M3 material padat Wc 0,1 M3
Kapasitas pompa air pa 100 liter/menit
Faktor efisiensi alat Fa 0,7 -

Kapasitas Produksi / Jam =pa x Fa x 60 Q5 42 M3


1000 x Wc

Koefisien Alat=/ 1m3: Q5 (E23) 0,02 Jam

2.f. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Sekop = 3 buah

3. TENAGA
Produksi menentukan : vibro Q2 24,93 M3/Jam
Produksi Timbunan / hari = Tk x Q2 Qt 174,53 M3
Kebutuhan tenaga :
- Pekerja P 5 orang
- Mandor M 1 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0,201 Jam
- Mandor = (Tk x M) : Qt (L03) 0,040 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 115.649,56 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0 M3
Analisa EI-322

ANALISA HARGA SATUAN PEKERJAAN

PAKET KEGIATAN PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE


LOKASI KOTA SOE - KAB. TIMOR TENGAH SELATAN

ITEM PEMBAYARAN NO. : 3.2.2 PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : TIMBUNAN MATERIAL DARI HASIL GALIAN/CUTTING
TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Jam 0,201 11.142,86 2.234,53


2. Mandor Jam 0,040 14.000,00 561,50

JUMLAH HARGA TENAGA 2.796,03

B. BAHAN

Sirtu M3 1,100 64.890,00 71.379,00

JUMLAH HARGA BAHAN 71.379,00

C. PERALATAN

1 VIBRATORY ROLLER Jam 0,040 450.673,15 18.075,13


2 Water Tanker Jam 0,024 331.204,00 7.885,81
3 Alat Bantu Ls 1,000 5.000,00 5.000,00

JUMLAH HARGA PERALATAN 30.960,94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 105.135,96


E. OVERHEAD & PROFIT 10 % x D 10.513,60
F. HARGA SATUAN PEKERJAAN ( D + E ) 115.649,56
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ANALISA BIAYA PERALATAN PER JAM KERJA

ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJA TOTAL
TENAGA KAPASITAS HARGA JAM SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP SPAREPART UPAH TOTAL BIAYA
ALAT ALAT ALAT UMUR KERJA HARGA ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK OPERATOR PEMBANTU BIAYA SEWA ALAT
( BARU ) ALAT 1 TAHUN ALAT MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
MODAL / SOPIR / JAM JAM KERJA
(HP) (Rp.) (Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) % % % - (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
No. JENIS PERALATAN KODE f1 x HP x 1 Orang 1 Orang
ALAT 12 2,5 Harga BBM 0,0625 0,125 Per Per

(10% X B) i(1+i)^A (B' - C) x D 0.002 x B' (e1 + e2) s/d s/d + s/d (g1 x B') s/d (h1 x B') Jam Kerja Jam Kerja F+G+H+I+J E+K
(1+i)^A-1 W W 15 3 f2 x HP x 0,0875 W 0,175 W = =
Harga Olie 13571,4286 11142,8571

HP Cp B A W B' C D e1 e2 E f1 f2 F g1 G h1 H I J K L M
1 2 2a 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 EXCAVATOR 80-140 HP E10 133 0,9 M3 1.500.000.000,00 5 2000 1.500.000.000 150.000.000 0,264 178.063,30 1500 179.563,30 0,12 0,025 332.500 0,0875 65.625,0 0,125 93.750 13.571,43 11.142,86 516.589,29 696.152,59 Pek.Berat

2 VIBRATORY ROLLER E19 80 5-8 Ton 1.000.000.000,00 5 2000 1.000.000.000 100.000.000 0,264 118.708,87 1000 119.708,87 0,12 0,025 200.000 0,0875 43.750,0 0,125 62.500 13.571,43 11.142,86 330.964,29 450.673,15 Pek.Berat

3 WATER TANKER 3000-4500 L. E23 100 4000 Liter 250.000.000,00 5 2000 250.000.000 25.000.000 0,264 29.677,22 250 29.927,22 0,12 0,025 250.000 0,0875 10.937,5 0,125 15.625 13.571,43 11.142,86 301.276,79 331.204,00 Pek.Berat
4 ROCK DRILL BREAKER E37 3 0 1.160.000.000,00 6 1500 1.160.000.000,00 116.000.000 0,230 159.806,74 1546,6667 161353,4034 0,15 0,03 9225 0,0875 67666,6667 0,175 135.333 13571,4286 11142,8571 236939,2857 398.292,69 Pek.Ringan

KETERANGAN :

1 TINGKAT SUKU BUNGA = 10 % per-tahun

2 UPAH OPERATOR/SOPIR/MEKANIK = 13.571 Rupiah per-orang/jam

3 PEMBANTU OPERATOR/SOPIR/MEKANIK = 11.143 Rupiah per-orang/jam

5 HARGA BAHAN BAKAR SOLAR = 12500 Rupiah per-liter

6 MINYAK PELUMAS = 40000 Rupiah per-liter


ANALISA PERALATAN
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE
LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

No. URAIAN KODE KOEFISIEN SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3 - 4 TON
2. Tenaga Pw 100 HP
3. Kapasitas Cp 4 Ton
4. Umur Ekonomis A 5 Tahun
5. Jam Operasi/Setahun W 2000 Jam/Thn
6. Harga Setempat B 300.000.000,00 Rupiah
7. Harga Ban b 9.000.000,00 Rupiah
8. Nilai Sisa = 10% x (B - b) c 29.100.000,00 Rupiah
9. Harga Penyusutan = B-b-c d 261.900.000,00 Rupiah

B. BIAYA KERJA ALAT


I. Biaya Langsung/Biaya Pasti
1.1. Biaya Pemilikan Alat
a. Penyusutan d D 26.190,00 Rp./Jam
= AxW

b. Bunga, Pajak, Biaya Gudang (A + 1) B E 18.000,00 Rp./Jam


dan Asuransi = 0,2 2A x W

1.2. Biaya Operasi


a. Bahan Bakar = ( 5 Ltr/Jam x Ms) F 62.500,00 Rp./Jam
b. Pelumas Mesin = ( 0,14 Ltr/Jam x Mp) G 5.600,00 Rp./Jam
c. Pelumas Hidrolik = ( 0,1 Ltr/Jam x Mp) H 4.000,00
d. Pelumas Transmisi = ( 0,08 Ltr/Jam x Mp) I 3.200,00 Rp./Jam
e. Grease = ( 0,01 Kg/Jam x Gs) J 100,00
f. Perlengkapan/Work Shop B K 9.375,00 Rp./Jam
= (6,25% - 8,75%) x W
Ban = b/Umur Ban L 4.500,00
Sopir = 1 org/jam x U1 M 13.571,43 Rp./Jam
Pembantu Sopir = 1 org/jam x U2 n 11.142,86 Rp./Jam

1.3. Biaya Perbaikan/Spare Part (B - b) O 8730 Rp./Jam


= (6% - 30%) x W

Jumlah Biaya Langsung P 166.909,29 Rp./Jam

II. Biaya Tidak Langsung


Biaya Tidak Langsung = 0,05 x Biaya Langsung Q 8.345,46 Rp./Jam

Total Biaya Sewa Alat per Jam = (P + Q + R + S) T 175.254,75 Rp./Jam


Total Biaya Sewa Alat per Hari = (T x 7) V 1.226.783,25 Rp./Hari
Dibulatkan 1.226.000,00 Rp./Hari

IV. Lain-Lain
- Tingkat Suku Bunga N 20 %/Tahun
- Upah Sopir U1 13.571,43 Rp./Jam
- Upah Pembantu Sopir U2 11.142,86 Rp./Jam
- Bahan Bakar Solar Ms 12.500,00 Rp./Liter
- Minyak Pelumas Mp 40.000,00 Rp./Liter
- Grease Gs 10.000,00 Rp./Kg
DAFTAR HARGA UPAH
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL dr.EIRENE INA DEIKA ATE
LOKASI : KOTA SOE - KAB. TIMOR TENGAH SELATAN

NO. URAIAN TENAGA SATUAN UPAH


1 2 3 4

1 MANDOR Org / hr 98.000,00


2 KEPALA TUKANG BATU Org / hr 95.000,00
3 KEPALA TUKANG KAYU Org / hr 95.000,00
4 KEPALA TUKANG BESI Org / hr 95.000,00
5 KEPALA TUKANG CAT Org / hr 95.000,00
6 KEPALA TUKANG LISTRIK Org / hr 95.000,00
7 KEPALA TUKANG PIPA Org / hr 95.000,00
8 TUKANG BATU (TUKANG TERAMPIL) Org / hr 86.000,00
9 TUKANG KAYU (TUKANG TERAMPIL) Org / hr 86.000,00
10 TUKANG BESI (TUKANG TERAMPIL) Org / hr 86.000,00
11 TUKANG CAT (TUKANG TERAMPIL) Org / hr 86.000,00
12 TUKANG LISTRIK (TUKANG TERAMPIL) Org / hr 86.000,00
13 TUKANG LAS (TUKANG TERAMPIL) Org / hr 86.000,00
14 TUKANG PIPA (TUKANG TERAMPIL) Org / hr 86.000,00
15 PEKERJA Org / hr 78.000,00
16 SOPIR Org / hr 95.000,00
17 PEMBANTU SOPIR Org / hr 78.000,00
18 MEKANIK Org / hr 95.000,00
19 PEMBANTU MEKANIK Org / hr 78.000,00
20 OPERATOR Org / hr 95.000,00
21 PEMBANTU OPERATOR Org / hr 78.000,00