RENCANA ANGGARAN BIAYA PELAKSANAAN (RAP)
PEKERJAAN PEMBANGUNAN RUMAH PAK AGUS
I PEKERJAAN PERSIAPAN
1 Membersihkan Lapangan dan Perataan 237.000 m2 Rp 1,777,500.00 0.2566 0.2566
2 Pengukuran dan Pasangan Bouplang 66.000 m1 Rp 2,729,100.00 0.3939 0.3939
II PEKERJAAN TANAH DAN PASIR
1 Galian tnh Pondasi Batu Kali 77.400 m3 Rp 2,658,690.00 0.3838 0.1919 0.1919
2 Galian Tanah footplate 7.000 m3 Rp 240,450.00 0.0347 0.0347
3 Urug tanah kembali 21.100 m3 Rp 222,605.00 0.0321
4 Urug pasir bwh lantai 11.850 m3 Rp 1,921,675.00 0.2774
5 Urug peninggian level bangunan 50 cm 118.500 m3 Rp 12,294,375.00 1.7746
III PEKERJAAN PASANGAN
1 Pas Pondasi bt kali 1:3:10 77.400 m3 Rp 39,978,562.00 5.7706 1.9235 1.9235
2 Pas Rollag Bata 1:3:10 20.000 m' Rp 167,680.80 0.0242
3 Rabat beton 11.850 m3 Rp 7,153,792.33 1.0326
4 Pas Dinding 1/2 bata 1:3:10 671.920 m2 Rp 56,334,041.57 8.1314
5 Pek Plesteran dan Acian dinding 1,343.840 m2 Rp 59,836,865.05 8.6370
6 Pas Bak Kontrol Saluran 4.000 unit Rp 1,255,235.56 0.1812
7 Pas Lis Beton
Lis beton keliling lebar 30 cm 48.000 m1 Rp 7,200,000.00 1.0393
Lis beton ujung topi2 beton 45.000 m1 Rp 2,700,000.00 0.3897
Lis beton keliling jendela (6 jendela) 36.000 m1 Rp 1,800,000.00 0.2598
Teras Depan, Teras samping
* Mahkota 2.000 bh Rp 200,000.00 0.0289
* Lis beton lebar 12 cm 60.000 m1 Rp 3,000,000.00 0.4330
IV PEKERJAAN BETON
1 Pek Footplat 2.450 m3 Rp 2,001,846.00 0.2890 0.2890
- Pembesian 490.000 kg Rp 7,775,810.00 1.1224 1.1224
IV PEKERJAAN KERAMIK
1 Pas Lantai Granit Teras 16.00 m2 Rp 3,684,064.00 0.5318
2 Pas Lantai Granit Cina 60x60 145.340 m2 Rp 33,465,116.36 4.8304
IX PEKERJAAN PENGECATAN
1 Pek Cat Dinding Catylac 1,343.840 m2 Rp 36,100,245.84 5.2108
2 Pek Cat Plafond Kalsiboard 294.000 m2 Rp 7,897,869.00 1.1400
3 Pek Cat Genteng 332.500 m2 Rp 8,932,113.75 1.2893
4 Pek Melamin Doff Kayu
Kusen 146.600 m1 Rp 5,131,000.00 0.7406
Daun Pintu (17 daun) 34.000 m2 Rp 3,060,000.00 0.4417
Daun jendela jendela besar = 15 bh 60.000 m1 Rp 1,200,000.00 0.1732
jendela kecil = 24 bh 48.000 m1 Rp 960,000.00 0.1386
100
JUMLAH Rp 692,799,261.41
###
MINGGU KE
5 6 7 8 9 10 11 12 13 14 15 16
0.0161 0.0161
0.2774
0.8873 0.8873
1.9235
0.0242
0.5163 0.5163
2.7105 2.7105 2.7105
2.8790 2.8790 2.8790
0.1812
0.5196 0.5196
0.1949 0.1949
0.1299 0.1299
0.0144 0.0144
0.2165 0.2165
0.3804 0.3804
1.2927 1.2927
0.6670 0.6670
0.0938
0.3642
0.3244
0.0730 0.0730
0.2835 0.2835
0.2104 0.2104
0.3043 0.3043
1.1819 1.1819
1.4036 1.4036
0.2165 0.2165
0.8411 0.8411
0.2104 0.2104
0.0619 0.0619
0.2405 0.2405
0.1530 0.1530
0.0967 0.0967
1.2731 1.2731
0.8487
0.1443
0.2165
0.2979
0.1949
0.0808
0.0533
0.0302
0.0325
0.1083
0.0325
0.2165 0.2165
0.2887
0.0577
0.0325
0.0994
0.2189
0.0117
0.0325
0.0361
0.0217
0.2864 0.2864 0.2864
0.1443 0.1443
0.4605
0.3703 0.3703
0.2208 0.2208
0.0866 0.0866
0.0693 0.0693
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
HARGA SATUAN UPAH (Rp)
NO. SATUAN KODE JENIS UPAH PEK. SWAKELOLA PEK. DIBORONGKAN
Rp / OH Rp / OH Rp / Jam
A. UPAH
1 OH L.001 Tukang Batu - 65,000.00 9,285.71
2 OH L.002 Tukang Kayu - 65,000.00 9,285.71
3 OH L.003 Tukang Besi - 65,000.00 9,285.71
4 OH L.004 Tukang Cat - 65,000.00 9,285.71
5 OH L.005 Tukang Dempul - 65,000.00 9,285.71
6 OH L.006 Tukang Plistur - 65,000.00 9,285.71
7 OH L.007 Kepala Tukang - 70,000.00 10,000.00
8 OH L.008 Pekerja - 50,000.00 7,142.86
9 OH L.009 Pekerja Bongkar / Siram - 50,000.00 7,142.86
10 OH L.010 Mandor - 50,000.00 7,142.86
11 OH L.011 Tukang Batu Ahli - 70,000.00 10,000.00
12 OH L.012 Operator Mesin Poles - 80,000.00 10,000.00
11 OH L.021 Operator Alat Berat - 100,000.00 14,285.71
12 OH L.022 Pembantu Operator - 50,000.00 7,142.86
13 OH L.023 Sopir - 50,000.00 7,142.86
14 OH L.024 Pembantu Sopir - 45,000.00 6,428.57
halaman 13 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
002 Zak M.002 Portland Cement 50 Kg 64,000.00 65,000.00
Kg M.002a Portland Cement 1,280.00 1,300.00
Kg M.002b PC Warna 6,000.00 10,000.00
halaman 14 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
Kg M.006b Paku Kait 23,000.00 28,000.00
Kg M.006c Paku Seng ( 1/2" - 1") 23,000.00 23,750.00
Bj M.006d Paku Payung 450.00 450.00
halaman 15 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
Bj M.006e Paku Sumbat 350.00 350.00
Btg M.006f Bambu 7,500.00 8,000.00
Bj M.006g Skrup 3.5" 550.00 550.00
Kg M.006h Skrup 36,000.00 36,000.00
Kg M.006i Paku beton 5 cm 25,000.00 5,000.00
halaman 16 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN
KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
Kg M.012b Plamir Kayu 13,000.00 13,500.00
Lbr M.012c Amplas 2,000.00 2,000.00
Kg M.012d Dempul Lilin 7,000.00 7,500.00
Kg M.012e Dempul Kayu 11,000.00 11,500.00
Kg M.012f Kapur sirih / Labur / Gamping 1,800.00 2,000.00
Kg M.012g Lem Kayu 11,000.00 11,500.00
Kg M.012h Politur 25,000.00 25,000.00
Ikat M.012i Alang-alang 2,000.00 2,200.00
ltr M.012j Tir Kayu 3,000.00 3,000.00
ltr M.012k OlI 37,000.00 37,000.00
Kg M.012l Soda api 15,000.00 16,000.00
M3 M.012m Perancah kayu hapus 950,000.00 950,000.00
Bh M.012n Kuas 3,800.00 4,000.00
Ltr M.012o Resin warna 47,000.00 47,000.00
Ltr M.012p Cairan coating 19,000.00 19,000.00
set M.012q Batu grenda poles 380,000.00 380,000.00
Kg M.012r Obat poles 120,000.00 120,000.00
Glg M.012s Kain poles 4,000.00 4,000.00
Bh M.012t Kain pel 4,500.00 4,500.00
Kg M.012u Semir lantai sek. MAA 17,000.00 17,000.00
013 M2 M.013 Paving Blok Natural 6 cm 60,000.00 32,000.00
M2 M.013a Paving Blok Warna 6 cm 60,000.00 36,000.00
M2 M.013b Paving Blok Aldas t : 10 cm K - 400 80,000.00 128,000.00
M2 M.013c Paving Blok Aldas t : 6 cm K - 300 80,000.00 65,000.00
014 Bh M.014 Kunci tanam antik 300,000.00 300,000.00
Bh M.014a Kunci tanam biasa sek. Yalle 85,000.00 85,000.00
Bh M.014b Kunci tanam kamar mandi 32,000.00 32,000.00
Bh M.014c Engsel pintu 7,000.00 7,000.00
Bh M.014d Engsel jendela kupu-kupu 4,500.00 4,500.00
Bh M.014e Engsel angin 20,000.00 20,000.00
Bh M.014f Kait Angin model lipat 5,000.00 5,000.00
Bh M.014f.1 Kait Angin model antik 16,500.00 16,500.00
Bh M.014g Door Closer 200,000.00 200,000.00
Bh M.014h Kunci slot 85,000.00 85,000.00
Bh M.014i Pegangan Pintu / Door Holder 175,500.00 175,500.00
Bh M.014j Door Stop 25,000.00 25,000.00
Bh M.014k Rel Pintu Dorong 300,000.00 310,000.00
015 Bh M.015 Kloset duduk sek. Toto 1,400,000.00 1,425,000.00
Bh M.015a Kloset jongkok sek. Toto 150,000.00 155,000.00
Bh M.015b U r i n o i r sek. Toto 400,000.00 420,000.00
Bh M.015c W a s t a f e l sek. Toto 475,000.00 480,000.00
Bh M.015d Bak Mandi Fiberglass 150,000.00 157,000.00
Bh M.015d.1 Bak Fiberglass 340,000.00 340,000.00
Bh M.015e Bathkip 3,861,000.00 4,000,000.00
Bh M.015f Bak Cuci Piring Stainless 1 ruang 206,000.00 215,000.00
Bh M.015g Water drain + asesories 29,000.00 29,000.00
Bh M.015h Kran air 3/4" 60,000.00 20,000.00
Bh M.015h.1 Kran air 1/2" 60,000.00 15,000.00
Bh M.015i Seal tape 2,000.00 2,000.00
Bh M.015j Floor Drain 19,000.00 20,000.00
016 M' M.016 Pipa Galvanis 1/2" med. B 13,000.00 13,500.00
M' M.016a Pipa Galvanis 3/4" med. B 16,000.00 16,500.00
M' M.016b Pipa Galvanis 1" med. B 21,000.00 22,000.00
M' M.016c Pipa Galvanis 1 1/2" med. B 29,000.00 31,000.00
M' M.016d Pipa Galvanis 2" med. B 48,000.00 50,000.00
M' M.016e Pipa Galvanis 3" med. B 76,000.00 78,000.00
M' M.016f Pipa Galvanis 4" med. B 101,000.00 105,000.00
M' M.016g Pipa PVC 1/2" type AW 2,800.00 3,000.00
M' M.016h Pipa PVC 3/4" type AW 4,000.00 4,500.00
M' M.016i Pipa PVC 1" type AW 5,000.00 6,000.00
M' M.016j Pipa PVC 1 1/2" type AW 10,000.00 11,000.00
M' M.016k Pipa PVC 2" type AW 13,000.00 14,000.00
halaman 17 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS DAFTAR HARGA SATUAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2015
M' M.016l Pipa PVC 3" type AW 27,000.00 28,000.00
M' M.016m Pipa PVC 4" type AW 45,000.00 46,000.00
halaman 18 / 51
19 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
A. PEKERJAAN PERSIAPAN
Pengukuran dan Pemasangan Bouwplank (Kayu
SNI - A.6.4a M' 41,350.00 35,430.00 28,900.00
Tahun)
M.005a Usuk 5/7 kayu Tahun 0.0120 M3 1,500,000.00 18,000.00 1,200,000.00 14,400.00 1,500,000.00 18,000.00
M.006 Paku Biasa ( 2" - 5" ) 0.0200 Kg 20,000.00 400.00 9,000.00 180.00 20,000.00 400.00
M.005a Papan kayu Tahun 3/20 0.0070 M3 1,500,000.00 10,500.00 1,200,000.00 8,400.00 1,500,000.00 10,500.00
L.008 Pekerja 0.1000 OH 50,000.00 5,000.00 50,000.00 5,000.00 - -
L.002 Tukang Kayu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
Pembuatan Gudang Semen dan Alat-alat (Kayu
SNI - A.6.6a M2 650,106.67 594,750.00 453,606.67
Tahun )
M.005s Dolken kayu diam. 8-10 / 4 m 1.7000 Btg 30,000.00 51,000.00 35,000.00 59,500.00 30,000.00 51,000.00
M.005a Papan kayu Tahun 3/20 0.2100 M3 1,500,000.00 315,000.00 1,200,000.00 252,000.00 1,500,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5" ) 0.3000 Kg 20,000.00 6,000.00 9,000.00 2,700.00 20,000.00 6,000.00
M.002a Portland Cement 10.5000 Kg 1,280.00 13,440.00 1,300.00 13,650.00 1,280.00 13,440.00
M.001 Pasir Beton 0.0300 M3 122,222.22 3,666.67 130,000.00 3,900.00 122,222.22 3,666.67
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0500 M3 180,000.00 9,000.00 190,000.00 9,500.00 180,000.00 9,000.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 37,000.00 55,500.00 38,000.00 57,000.00 37,000.00 55,500.00
L.008 Pekerja 1.0000 OH 50,000.00 50,000.00 50,000.00 50,000.00 - -
L.002 Tukang Kayu 2.0000 OH 65,000.00 130,000.00 65,000.00 130,000.00 - -
L.007 Kepala Tukang 0.2000 OH 70,000.00 14,000.00 70,000.00 14,000.00 - -
L.010 Mandor 0.0500 OH 50,000.00 2,500.00 50,000.00 2,500.00 - -
SNI - A.6.8 Membersihkan Lapangan dan Perataan M2 SNIA.6.8 7,500.00 SN2A.6.8 7,500.00 SNSA.6.8 -
L.008 Pekerja 0.1000 OH 50,000.00 5,000.00 50,000.00 5,000.00 - -
L.010 Mandor 0.0500 OH 50,000.00 2,500.00 50,000.00 2,500.00 - -
B. PEKERJAAN TANAH
SNI - B.6.3 Galian Tanah Biasa Sedalam 3 meter M3 SNIB.6.3 40,400.00 SN2B.6.3 40,400.00 SNSB.6.3 -
L.008 Pekerja 0.7350 OH 50,000.00 36,750.00 50,000.00 36,750.00 - -
L.010 Mandor 0.0730 OH 50,000.00 3,650.00 50,000.00 3,650.00 - -
20 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - B.6.4 Galian Tanah Keras Sedalam 1 meter M3 SNIB.6.4 34,350.00 SN2B.6.4 34,350.00 SNSB.6.4 -
L.008 Pekerja 0.6250 OH 50,000.00 31,250.00 50,000.00 31,250.00 - -
L.010 Mandor 0.0620 OH 50,000.00 3,100.00 50,000.00 3,100.00 - -
SNI - B.6.9 Urugan Kembali M3 SNIB.6.9 10,550.00 SN2B.6.9 10,550.00 SNSB.6.9 -
L.008 Pekerja 0.1920 OH 50,000.00 9,600.00 50,000.00 9,600.00 - -
L.010 Mandor 0.0190 OH 50,000.00 950.00 50,000.00 950.00 - -
SNI - B.6.11 Urugan Pasir M3 SNIB.6.11 162,166.67 SN2B.6.11 171,500.00 SNSB.6.11 146,666.67
M.001b Pasir urug 1.2000 M3 122,222.22 146,666.67 130,000.00 156,000.00 122,222.22 146,666.67
L.008 Pekerja 0.3000 OH 50,000.00 15,000.00 50,000.00 15,000.00 - -
L.010 Mandor 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
SNI - B.6.15 Urugan Sirtu M3 SNIB.6.15 103,750.00 SN2B.6.15 109,750.00 SNSB.6.15 90,000.00
M.001e Sirtu 1.2000 M3 75,000.00 90,000.00 80,000.00 96,000.00 75,000.00 90,000.00
L.008 Pekerja 0.2500 OH 50,000.00 12,500.00 50,000.00 12,500.00 - -
L.010 Mandor 0.0250 OH 50,000.00 1,250.00 50,000.00 1,250.00 - -
C. PEKERJAAN PONDASI BATU KALI
SNI - C.6.6 Pas. Pondasi Batu Kali 1 PC : 5 Psr M3 SNIC.6.6 516,518.89 SN2C.6.6 534,470.00 SNSC.6.6 394,568.89
M.001f1 Batu Belah 15/20 cm 1.1000 M3 140,000.00 154,000.00 150,000.00 165,000.00 140,000.00 154,000.00
M.002a Portland Cement 136.00 Kg 1,280.00 174,080.00 1,300.00 176,800.00 1,280.00 174,080.00
M.001a Pasir Pasang 0.5440 M3 122,222.22 66,488.89 130,000.00 70,720.00 122,222.22 66,488.89
L.008 Pekerja 1.5000 OH 50,000.00 75,000.00 50,000.00 75,000.00 - -
L.001 Tukang Batu 0.6000 OH 65,000.00 39,000.00 65,000.00 39,000.00 - -
L.007 Kepala Tukang 0.0600 OH 70,000.00 4,200.00 70,000.00 4,200.00 - -
L.010 Mandor 0.0750 OH 50,000.00 3,750.00 50,000.00 3,750.00 - -
D. PEKERJAAN DINDING
SNI - D.6.12 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 Psr M2 SNID.6.12 83,840.40 SN2D.6.12 71,084.00 SNSD.6.12 49,390.40
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 600.00 42,000.00 410.00 28,700.00 450.00 31,500.00
21 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.002a Portland Cement 9.6800 Kg 1,280.00 12,390.40 1,300.00 12,584.00 1,280.00 12,390.40
M.001a Pasir Pasang 0.0450 M3 122,222.22 5,500.00 130,000.00 5,850.00 122,222.22 5,500.00
L.008 Pekerja 0.3200 OH 50,000.00 16,000.00 50,000.00 16,000.00 - -
L.001 Tukang Batu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0150 OH 50,000.00 750.00 50,000.00 750.00 - -
E. PEKERJAAN PLESTERAN
SNI - E.6.3 Plesteran 1 PC : 3 Psr tb. 1,5 cm M2 SNIE.6.3 31,916.62 SN2E.6.3 32,194.00 SNSE.6.3 10,616.62
M.002a Portland Cement 6.4800 Kg 1,280.00 8,294.40 1,300.00 8,424.00 1,280.00 8,294.40
M.001a Pasir Pasang 0.0190 M3 122,222.22 2,322.22 130,000.00 2,470.00 122,222.22 2,322.22
L.008 Pekerja 0.2000 OH 50,000.00 10,000.00 50,000.00 10,000.00 - -
L.001 Tukang Batu 0.1500 OH 65,000.00 9,750.00 65,000.00 9,750.00 - -
L.007 Kepala Tukang 0.0150 OH 70,000.00 1,050.00 70,000.00 1,050.00 - -
L.010 Mandor 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
SNI - E.6.5 Plesteran 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.5 29,518.49 SN2E.6.5 29,776.00 SNSE.6.5 8,218.49
M.002a Portland Cement 4.3200 Kg 1,280.00 5,529.60 1,300.00 5,616.00 1,280.00 5,529.60
M.001a Pasir Pasang 0.0220 M3 122,222.22 2,688.89 130,000.00 2,860.00 122,222.22 2,688.89
L.008 Pekerja 0.2000 OH 50,000.00 10,000.00 50,000.00 10,000.00 - -
L.001 Tukang Batu 0.1500 OH 65,000.00 9,750.00 65,000.00 9,750.00 - -
L.007 Kepala Tukang 0.0150 OH 70,000.00 1,050.00 70,000.00 1,050.00 - -
L.010 Mandor 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
SNI - E.6.9 Plesteran 1 PC : 3 Kp : 10 Psr tb. 1,5 cm M2 SNIE.6.9 26,866.31 SN2E.6.9 27,312.00 SNSE.6.9 5,566.31
M.002a Portland Cement 1.8400 Kg 1,280.00 2,355.20 1,300.00 2,392.00 1,280.00 2,355.20
M.001d Kapur Padam 0.0060 M3 250,000.00 1,500.00 300,000.00 1,800.00 250,000.00 1,500.00
M.001a Pasir Pasang 0.0140 M3 122,222.22 1,711.11 130,000.00 1,820.00 122,222.22 1,711.11
L.008 Pekerja 0.2000 OH 50,000.00 10,000.00 50,000.00 10,000.00 - -
L.001 Tukang Batu 0.1500 OH 65,000.00 9,750.00 65,000.00 9,750.00 - -
L.007 Kepala Tukang 0.0150 OH 70,000.00 1,050.00 70,000.00 1,050.00 - -
L.010 Mandor 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
22 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - E.6.14 Plesteran 1 PC : 3 Psr tb. 2 cm M2 SNIE.6.14 44,526.78 SN2E.6.14 44,945.00 SNSE.6.14 17,001.78
M.002a Portland Cement 10.8000 Kg 1,280.00 13,824.00 1,300.00 14,040.00 1,280.00 13,824.00
M.001a Pasir Pasang 0.0260 M3 122,222.22 3,177.78 130,000.00 3,380.00 122,222.22 3,177.78
L.008 Pekerja 0.2500 OH 50,000.00 12,500.00 50,000.00 12,500.00 - -
L.001 Tukang Batu 0.2000 OH 65,000.00 13,000.00 65,000.00 13,000.00 - -
L.007 Kepala Tukang 0.0200 OH 70,000.00 1,400.00 70,000.00 1,400.00 - -
L.010 Mandor 0.0125 OH 50,000.00 625.00 50,000.00 625.00 - -
SNI - E.6.16 Plesteran 1 PC : 5 Psr tb. 2 cm M2 SNIE.6.16 40,278.42 SN2E.6.16 40,642.00 SNSE.6.16 12,753.42
M.002a Portland Cement 7.2900 Kg 1,280.00 9,331.20 1,300.00 9,477.00 1,280.00 9,331.20
M.001a Pasir Pasang 0.0280 M3 122,222.22 3,422.22 130,000.00 3,640.00 122,222.22 3,422.22
L.008 Pekerja 0.2500 OH 50,000.00 12,500.00 50,000.00 12,500.00 - -
L.001 Tukang Batu 0.2000 OH 65,000.00 13,000.00 65,000.00 13,000.00 - -
L.007 Kepala Tukang 0.0200 OH 70,000.00 1,400.00 70,000.00 1,400.00 - -
L.010 Mandor 0.0125 OH 50,000.00 625.00 50,000.00 625.00 - -
SNI - E.6.30 Plesteran Beton 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.30 39,666.27 SN2E.6.30 39,971.00 SNSE.6.30 11,616.27
M.002a Portland Cement 7.0700 Kg 1,280.00 9,049.60 1,300.00 9,191.00 1,280.00 9,049.60
M.001a Pasir Pasang 0.0210 M3 122,222.22 2,566.67 130,000.00 2,730.00 122,222.22 2,566.67
L.008 Pekerja 0.2600 OH 50,000.00 13,000.00 50,000.00 13,000.00 - -
L.001 Tukang Batu 0.2000 OH 65,000.00 13,000.00 65,000.00 13,000.00 - -
L.007 Kepala Tukang 0.0200 OH 70,000.00 1,400.00 70,000.00 1,400.00 - -
L.010 Mandor 0.0130 OH 50,000.00 650.00 50,000.00 650.00 - -
SNI - E.6.31 Plesteran Skoning 1 PC : 2 Psr M1 SNIE.6.31 8,964.44 SN2E.6.31 8,990.00 SNSE.6.31 884.44
M.002a Portland Cement 0.5000 Kg 1,280.00 640.00 1,300.00 650.00 1,280.00 640.00
M.001a Pasir Pasang 0.0020 M3 122,222.22 244.44 130,000.00 260.00 122,222.22 244.44
L.008 Pekerja 0.0570 OH 50,000.00 2,850.00 50,000.00 2,850.00 - -
L.001 Tukang Batu 0.0380 OH 65,000.00 2,470.00 65,000.00 2,470.00 - -
L.007 Kepala Tukang 0.0380 OH 70,000.00 2,660.00 70,000.00 2,660.00 - -
L.010 Mandor 0.0020 OH 50,000.00 100.00 50,000.00 100.00 - -
SNI - E.6.35 Plesteran Siar Adukan 1 PC : 2 Psr M2 SNIE.6.35 20,425.16 SN2E.6.35 20,636.00 SNSE.6.35 7,485.16
23 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.002a Portland Cement 4.3200 Kg 1,280.00 5,529.60 1,300.00 5,616.00 1,280.00 5,529.60
M.001a Pasir Pasang 0.0160 M3 122,222.22 1,955.56 130,000.00 2,080.00 122,222.22 1,955.56
L.008 Pekerja 0.1500 OH 50,000.00 7,500.00 50,000.00 7,500.00 - -
L.001 Tukang Batu 0.0700 OH 65,000.00 4,550.00 65,000.00 4,550.00 - -
L.007 Kepala Tukang 0.0070 OH 70,000.00 490.00 70,000.00 490.00 - -
L.010 Mandor 0.0080 OH 50,000.00 400.00 50,000.00 400.00 - -
F. PEKERJAAN KAYU
SNI - F.6.8a Pas. Pintu Panil Kayu Bangkir M2 SNIF.6.8a 540,500.00 SN2F.6.8a 541,500.00 SNSF.6.8a 298,000.00
M.005n Papan Bangkir 0.0400 M3 7,700,000.00 308,000.00 7,725,000.00 309,000.00 7,700,000.00 308,000.00
L.008 Pekerja 1.0000 OH 50,000.00 50,000.00 50,000.00 50,000.00 - -
L.002 Tukang Kayu 2.5000 OH 65,000.00 162,500.00 65,000.00 162,500.00 - -
L.007 Kepala Tukang 0.2500 OH 70,000.00 17,500.00 70,000.00 17,500.00 - -
L.010 Mandor 0.0500 OH 50,000.00 2,500.00 50,000.00 2,500.00 - -
Pas. Kaso dan Reng genteng glasur Kayu
M2 SNIF.6.31d 92,250.00 SN2F.6.31d 90,600.00 SNSF.6.31d 79,800.00
Bangkir uk. Khusus
M.005i1 Usuk Bangkir 5/7 (uk. khusus) 0.0120 M3 6,400,000.00 76,800.00 6,400,000.00 76,800.00 6,400,000.00 76,800.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 20,000.00 3,000.00 9,000.00 1,350.00 20,000.00 3,000.00
L.008 Pekerja 0.1000 OH 50,000.00 5,000.00 50,000.00 5,000.00 - -
L.002 Tukang Kayu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
G. PEKERJAAN BETON
SNI - G.6.1 Membuat Beton Tumbuk 1 PC : 3 Ps : 5 Kr M3 SNIG.6.1 603,695.56 SN2G.6.1 620,800.00 SNSG.6.1 499,195.56
M.002a Portland Cement 218.00 Kg 1,280.00 279,040.00 1,300.00 283,400.00 1,280.00 279,040.00
M.001 Pasir Beton 0.5200 M3 122,222.22 63,555.56 130,000.00 67,600.00 122,222.22 63,555.56
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8700 M3 180,000.00 156,600.00 190,000.00 165,300.00 180,000.00 156,600.00
L.008 Pekerja 1.6500 OH 50,000.00 82,500.00 50,000.00 82,500.00 - -
L.001 Tukang Batu 0.2500 OH 65,000.00 16,250.00 65,000.00 16,250.00 - -
L.007 Kepala Tukang 0.0250 OH 70,000.00 1,750.00 70,000.00 1,750.00 - -
24 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0800 OH 50,000.00 4,000.00 50,000.00 4,000.00 - -
Membuat Lantai Kerja Beton Tumbuk 1 PC : 3
SNI - G.6.4 M3 SNIG.6.4 83,137.78 SN2G.6.4 83,980.00 SNSG.6.4 23,897.78
Ps : 5 Kr tb. 5 cm
M.002a Portland Cement 10.0000 Kg 1,280.00 12,800.00 1,300.00 13,000.00 1,280.00 12,800.00
M.001 Pasir Beton 0.0260 M3 122,222.22 3,177.78 130,000.00 3,380.00 122,222.22 3,177.78
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.0440 M3 180,000.00 7,920.00 190,000.00 8,360.00 180,000.00 7,920.00
L.008 Pekerja 1.1500 OH 50,000.00 57,500.00 50,000.00 57,500.00 - -
L.001 Tukang Batu 0.0200 OH 65,000.00 1,300.00 65,000.00 1,300.00 - -
L.007 Kepala Tukang 0.0020 OH 70,000.00 140.00 70,000.00 140.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
SNI - G.6.13 Membuat Beton Cor 1 PC : 2 Ps : 3 Kr M3 SNIG.6.13 817,080.00 SN2G.6.13 836,100.00 SNSG.6.13 641,880.00
M.002a Portland Cement 336.00 Kg 1,280.00 430,080.00 1,300.00 436,800.00 1,280.00 430,080.00
M.001 Pasir Beton 0.5400 M3 122,222.22 66,000.00 130,000.00 70,200.00 122,222.22 66,000.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8100 M3 180,000.00 145,800.00 190,000.00 153,900.00 180,000.00 145,800.00
L.008 Pekerja 2.0000 OH 50,000.00 100,000.00 50,000.00 100,000.00 - -
L.001 Tukang Batu 0.3500 OH 65,000.00 22,750.00 65,000.00 22,750.00 - -
L.007 Kepala Tukang 0.0350 OH 70,000.00 2,450.00 70,000.00 2,450.00 - -
L.010 Mandor 1.0000 OH 50,000.00 50,000.00 50,000.00 50,000.00 - -
SNI - G.6.25 Pembesian dengan Besi Beton Polos Kg SNIG.6.25 13,769.00 SN2G.6.25 14,819.00 SNSG.6.25 12,900.00
M.003 Besi Beton Polos 1.0500 Kg 12,000.00 12,600.00 13,000.00 13,650.00 12,000.00 12,600.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 20,000.00 300.00 20,000.00 300.00 20,000.00 300.00
L.008 Pekerja 0.0070 OH 50,000.00 350.00 50,000.00 350.00 - -
L.003 Tukang Besi 0.0070 OH 65,000.00 455.00 65,000.00 455.00 - -
L.007 Kepala Tukang 0.0007 OH 70,000.00 49.00 70,000.00 49.00 - -
L.010 Mandor 0.0003 OH 50,000.00 15.00 50,000.00 15.00 - -
SNI - G.6.25a Pembesian dengan Besi Beton Ulir Kg SNIG.6.25a 14,819.00 SN2G.6.25a 15,869.00 SNSG.6.25a 13,950.00
M.003c Besi Beton Ulir 1.0500 Kg 13,000.00 13,650.00 14,000.00 14,700.00 13,000.00 13,650.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 20,000.00 300.00 20,000.00 300.00 20,000.00 300.00
L.008 Pekerja 0.0070 OH 50,000.00 350.00 50,000.00 350.00 - -
L.003 Tukang Besi 0.0070 OH 65,000.00 455.00 65,000.00 455.00 - -
L.007 Kepala Tukang 0.0007 OH 70,000.00 49.00 70,000.00 49.00 - -
25 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0003 OH 50,000.00 15.00 50,000.00 15.00 - -
SNI - G.6.28 Pas. Bekisting untuk Pondasi M2 SNIG.6.28 99,970.00 SN2G.6.28 84,670.00 SNSG.6.28 66,000.00
M.005a Kayu Tahun 0.0400 M3 1,500,000.00 60,000.00 1,200,000.00 48,000.00 1,500,000.00 60,000.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 20,000.00 6,000.00 9,000.00 2,700.00 20,000.00 6,000.00
L.008 Pekerja 0.3000 OH 50,000.00 15,000.00 50,000.00 15,000.00 - -
L.002 Tukang Kayu 0.2600 OH 65,000.00 16,900.00 65,000.00 16,900.00 - -
L.007 Kepala Tukang 0.0260 OH 70,000.00 1,820.00 70,000.00 1,820.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
SNI - G.6.29 Pas. Bekisting untuk Sloof M2 SNIG.6.29 107,470.00 SN2G.6.29 90,670.00 SNSG.6.29 73,500.00
M.005a Kayu Tahun 0.0450 M3 1,500,000.00 67,500.00 1,200,000.00 54,000.00 1,500,000.00 67,500.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 20,000.00 6,000.00 9,000.00 2,700.00 20,000.00 6,000.00
L.008 Pekerja 0.3000 OH 50,000.00 15,000.00 50,000.00 15,000.00 - -
L.002 Tukang Kayu 0.2600 OH 65,000.00 16,900.00 65,000.00 16,900.00 - -
L.007 Kepala Tukang 0.0260 OH 70,000.00 1,820.00 70,000.00 1,820.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
SNI - G.6.30 Pas. Bekisting untuk Kolom (pakai 2x) M2 SNIG.6.30 135,367.50 SN2G.6.30 265,760.00 SNSG.6.30 231,675.00
M.005a Kayu Tahun 0.0400 M3 1,500,000.00 60,000.00 1,200,000.00 48,000.00 1,500,000.00 60,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 20,000.00 8,000.00 9,000.00 3,600.00 20,000.00 8,000.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,645,000.00 54,675.00 3,670,000.00 55,050.00 3,645,000.00 54,675.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3000 OH 50,000.00 15,000.00 50,000.00 15,000.00 - -
L.002 Tukang Kayu 0.3300 OH 65,000.00 21,450.00 65,000.00 21,450.00 - -
L.007 Kepala Tukang 0.0330 OH 70,000.00 2,310.00 70,000.00 2,310.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
SNI - G.6.31 Pas. Bekisting untuk Balok (pakai 2x) M2 SNIG.6.31 141,335.00 SN2G.6.31 277,770.00 SNSG.6.31 242,610.00
M.005a Kayu Tahun 0.0400 M3 1,500,000.00 60,000.00 1,200,000.00 48,000.00 1,500,000.00 60,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 20,000.00 8,000.00 9,000.00 3,600.00 20,000.00 8,000.00
M.005g Usuk Meranti 5/7 0.0180 M3 3,645,000.00 65,610.00 3,670,000.00 66,060.00 3,645,000.00 65,610.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
26 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 50,000.00 16,000.00 50,000.00 16,000.00 - -
L.002 Tukang Kayu 0.3300 OH 65,000.00 21,450.00 65,000.00 21,450.00 - -
L.007 Kepala Tukang 0.0330 OH 70,000.00 2,310.00 70,000.00 2,310.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
SNI - G.6.32 Pas. Bekisting untuk Lantai (pakai 2x) M2 SNIG.6.32 195,867.50 SN2G.6.32 406,760.00 SNSG.6.32 351,675.00
M.005a Kayu Tahun 0.0400 M3 1,500,000.00 60,000.00 1,200,000.00 48,000.00 1,500,000.00 60,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 20,000.00 8,000.00 9,000.00 3,600.00 20,000.00 8,000.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,645,000.00 54,675.00 3,670,000.00 55,050.00 3,645,000.00 54,675.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 6.0000 Btg 30,000.00 180,000.00 35,000.00 210,000.00 30,000.00 180,000.00
L.008 Pekerja 0.3200 OH 50,000.00 16,000.00 50,000.00 16,000.00 - -
L.002 Tukang Kayu 0.3300 OH 65,000.00 21,450.00 65,000.00 21,450.00 - -
L.007 Kepala Tukang 0.0330 OH 70,000.00 2,310.00 70,000.00 2,310.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
SNI - G.6.33 Pas. Bekisting untuk Dinding M2 SNIG.6.33 374,960.00 SN2G.6.33 380,110.00 SNSG.6.33 334,900.00
M.005a Kayu Tahun 0.0300 M3 1,500,000.00 45,000.00 1,200,000.00 36,000.00 1,500,000.00 45,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 20,000.00 8,000.00 9,000.00 3,600.00 20,000.00 8,000.00
M.005g Usuk Meranti 5/7 0.0200 M3 3,645,000.00 72,900.00 3,670,000.00 73,400.00 3,645,000.00 72,900.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005t Formite/Penjaga Jarak Bekisting/Spacer 4.0000 Btg 17,500.00 70,000.00 18,000.00 72,000.00 17,500.00 70,000.00
L.008 Pekerja 0.3200 OH 50,000.00 16,000.00 50,000.00 16,000.00 - -
L.002 Tukang Kayu 0.3300 OH 65,000.00 21,450.00 65,000.00 21,450.00 - -
L.007 Kepala Tukang 0.0330 OH 70,000.00 2,310.00 70,000.00 2,310.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
SNI - G.6.34 Pas. Bekisting untuk Tangga M2 SNIG.6.34 256,735.00 SN2G.6.34 254,760.00 SNSG.6.34 216,675.00
M.005a Kayu Tahun 0.0300 M3 1,500,000.00 45,000.00 1,200,000.00 36,000.00 1,500,000.00 45,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 20,000.00 8,000.00 9,000.00 3,600.00 20,000.00 8,000.00
M.005g Kayu Meranti ( Balok ) 0.0150 M3 3,645,000.00 54,675.00 3,670,000.00 55,050.00 3,645,000.00 54,675.00
M.009c Plywood 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
27 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 50,000.00 16,000.00 50,000.00 16,000.00 - -
L.002 Tukang Kayu 0.3300 OH 65,000.00 21,450.00 65,000.00 21,450.00 - -
L.007 Kepala Tukang 0.0330 OH 70,000.00 2,310.00 70,000.00 2,310.00 - -
L.010 Mandor 0.0060 OH 50,000.00 300.00 50,000.00 300.00 - -
H. PEKERJAAN ATAP
SNI - H.6.30a 1 M2 Pas. Atap Genteng Morando kebumen M2 SNIH.6.30a 90,300.00 SN2H.6.30a 67,470.00 SNSH.6.30a 50,100.00
M.010e Genteng Glasur Natural Morando 18.0000 Bh 4,000.00 72,000.00 2,750.00 49,500.00 2,750.00 49,500.00
M.006 Paku Biasa ( 2" - 5") 0.0300 Kg 20,000.00 600.00 9,000.00 270.00 20,000.00 600.00
L.008 Pekerja 0.2000 OH 50,000.00 10,000.00 50,000.00 10,000.00 - -
L.002 Tukang Kayu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
SNI - H.6.34a Pas. Atap Nok Genteng Glasur Natural M' SNIH.6.34a 123,135.11 SN2H.6.34a 77,175.00 SNSH.6.34a 37,860.11
M.010f Genteng Nok 3.5000 Bh 18,000.00 63,000.00 3,750.00 13,125.00 3,750.00 13,125.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 20,000.00 1,000.00 9,000.00 450.00 20,000.00 1,000.00
M.002a Portland Cement 10.8000 Kg 1,280.00 13,824.00 1,300.00 14,040.00 1,280.00 13,824.00
M.001a Pasir Pasang 0.0320 M3 122,222.22 3,911.11 130,000.00 4,160.00 122,222.22 3,911.11
M.002b PC Warna 1.0000 Kg 6,000.00 6,000.00 10,000.00 10,000.00 6,000.00 6,000.00
L.008 Pekerja 0.4000 OH 50,000.00 20,000.00 50,000.00 20,000.00 - -
L.002 Tukang Kayu 0.2000 OH 65,000.00 13,000.00 65,000.00 13,000.00 - -
L.007 Kepala Tukang 0.0200 OH 70,000.00 1,400.00 70,000.00 1,400.00 - -
L.010 Mandor 0.0200 OH 50,000.00 1,000.00 50,000.00 1,000.00 - -
J. PEKERJAAN SANITASI
SNI - J.6.1 Pasang Kloset Duduk / Monoblok BH SNIJ.6.1 1,516,570.00 SN2J.6.1 1,755,070.00 SNSJ.6.1 1,484,000.00
M.015 Kloset duduk / Monoblok 1.0000 Bh 1,200,000.00 1,200,000.00 1,425,000.00 1,425,000.00 1,400,000.00 1,400,000.00
- Perlengkapan 6% x hrg kloset 72,000.00 72,000.00 85,500.00 85,500.00 84,000.00 84,000.00
28 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.008 Pekerja 3.3000 OH 50,000.00 165,000.00 50,000.00 165,000.00 - -
L.001 Tukang Batu 1.1000 OH 65,000.00 71,500.00 65,000.00 71,500.00 - -
L.007 Kepala Tukang 0.0010 OH 70,000.00 70.00 70,000.00 70.00 - -
L.010 Mandor 0.1600 OH 50,000.00 8,000.00 50,000.00 8,000.00 - -
SNI - J.6.2 Pasang Kloset Jongkok Porselen BH SNIJ.6.2 344,402.22 SN2J.6.2 424,600.00 SNSJ.6.2 158,902.22
M.015a Kloset Jongkok Porselen 1.0000 Bh 75,000.00 75,000.00 155,000.00 155,000.00 150,000.00 150,000.00
M.002a Portland Cement 6.0000 Kg 1,280.00 7,680.00 1,300.00 7,800.00 1,280.00 7,680.00
M.001a Pasir Pasang 0.0100 M3 122,222.22 1,222.22 130,000.00 1,300.00 122,222.22 1,222.22
L.008 Pekerja 1.0000 OH 50,000.00 50,000.00 50,000.00 50,000.00 - -
L.001 Tukang Batu 1.5000 OH 65,000.00 97,500.00 65,000.00 97,500.00 - -
L.007 Kepala Tukang 1.5000 OH 70,000.00 105,000.00 70,000.00 105,000.00 - -
L.010 Mandor 0.1600 OH 50,000.00 8,000.00 50,000.00 8,000.00 - -
SNI - J.6.5 Pasang Wastafel BH SNIJ.6.5 402,652.22 SN2J.6.5 716,450.00 SNSJ.6.5 540,902.22
M.015c Wastafel 1.0000 Bh 200,000.00 200,000.00 480,000.00 480,000.00 475,000.00 475,000.00
- Perlengkapan 12% x hrg Wastafel 24,000.00 24,000.00 57,600.00 57,600.00 57,000.00 57,000.00
M.002a Portland Cement 6.0000 Kg 1,280.00 7,680.00 1,300.00 7,800.00 1,280.00 7,680.00
M.001a Pasir Pasang 0.0100 M3 122,222.22 1,222.22 130,000.00 1,300.00 122,222.22 1,222.22
L.008 Pekerja 1.2000 OH 50,000.00 60,000.00 50,000.00 60,000.00 - -
L.001 Tukang Batu 1.4500 OH 65,000.00 94,250.00 65,000.00 94,250.00 - -
L.007 Kepala Tukang 0.1500 OH 70,000.00 10,500.00 70,000.00 10,500.00 - -
L.010 Mandor 0.1000 OH 50,000.00 5,000.00 50,000.00 5,000.00 - -
Pasang Bak Kontrol Pasang Batu Bata Uk.
SNI - J.6.17 BH SNIJ.6.17 313,808.89 SN2J.6.17 327,822.50 SNSJ.6.17 205,223.89
(45x45) cm tinggi 50 cm
M.001m Batu Bata 0.2500 M3 191,100.00 47,775.00 222,950.00 55,737.50 191,100.00 47,775.00
M.002a Portland Cement 77.00 Kg 1,280.00 98,560.00 1,300.00 100,100.00 1,280.00 98,560.00
M.001a Pasir Pasang 0.1300 M3 122,222.22 15,888.89 130,000.00 16,900.00 122,222.22 15,888.89
M.001n Batu Kerikil 0.0200 M3 40,000.00 800.00 50,000.00 1,000.00 40,000.00 800.00
M.003 Besi Beton 2.6000 Kg 12,000.00 31,200.00 13,000.00 33,800.00 12,000.00 31,200.00
M.001 Pasir Beton 0.0900 M3 122,222.22 11,000.00 130,000.00 11,700.00 122,222.22 11,000.00
L.008 Pekerja 1.4200 OH 50,000.00 71,000.00 50,000.00 71,000.00 - -
L.001 Tukang Batu 0.4730 OH 65,000.00 30,745.00 65,000.00 30,745.00 - -
L.007 Kepala Tukang 0.0470 OH 70,000.00 3,290.00 70,000.00 3,290.00 - -
29 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0710 OH 50,000.00 3,550.00 50,000.00 3,550.00 - -
SNI - J.6.25 Pasang Pipa PVC diameter 1/2" type AW M' SNIJ.6.25 10,550.00 SN2J.6.25 10,860.00 SNSJ.6.25 4,340.00
M.016g Pipa PVC 1/2" 1.2000 M' 2,800.00 3,360.00 3,000.00 3,600.00 2,800.00 3,360.00
- Perlengkapan 35% x hrg pipa 980.00 980.00 1,050.00 1,050.00 980.00 980.00
L.008 Pekerja 0.0360 OH 50,000.00 1,800.00 50,000.00 1,800.00 - -
L.001 Tukang Batu 0.0600 OH 65,000.00 3,900.00 65,000.00 3,900.00 - -
L.007 Kepala Tukang 0.0060 OH 70,000.00 420.00 70,000.00 420.00 - -
L.010 Mandor 0.0018 OH 50,000.00 90.00 50,000.00 90.00 - -
SNI - J.6.26 Pasang Pipa PVC diameter 3/4" type AW M' SNIJ.6.26 12,410.00 SN2J.6.26 13,185.00 SNSJ.6.26 6,200.00
M.016h Pipa PVC diam. 3/4" 1.2000 M' 4,000.00 4,800.00 4,500.00 5,400.00 4,000.00 4,800.00
- Perlengkapan 35% x hrg pipa 1,400.00 1,400.00 1,575.00 1,575.00 1,400.00 1,400.00
L.008 Pekerja 0.0360 OH 50,000.00 1,800.00 50,000.00 1,800.00 - -
L.001 Tukang Batu 0.0600 OH 65,000.00 3,900.00 65,000.00 3,900.00 - -
L.007 Kepala Tukang 0.0060 OH 70,000.00 420.00 70,000.00 420.00 - -
L.010 Mandor 0.0018 OH 50,000.00 90.00 50,000.00 90.00 - -
SNI - J.6.27 Pasang Pipa PVC diameter 1" type AW M' SNIJ.6.27 13,960.00 SN2J.6.27 15,510.00 SNSJ.6.27 7,750.00
M.016i Pipa PVC diam. 1" 1.2000 M' 5,000.00 6,000.00 6,000.00 7,200.00 5,000.00 6,000.00
- Perlengkapan 35% x hrg pipa 1,750.00 1,750.00 2,100.00 2,100.00 1,750.00 1,750.00
L.008 Pekerja 0.0360 OH 50,000.00 1,800.00 50,000.00 1,800.00 - -
L.001 Tukang Batu 0.0600 OH 65,000.00 3,900.00 65,000.00 3,900.00 - -
L.007 Kepala Tukang 0.0060 OH 70,000.00 420.00 70,000.00 420.00 - -
L.010 Mandor 0.0018 OH 50,000.00 90.00 50,000.00 90.00 - -
SNI - J.6.29 Pasang Pipa PVC diameter 2" type AW M' SNIJ.6.29 29,465.00 SN2J.6.29 31,015.00 SNSJ.6.29 20,150.00
M.016k Pipa PVC diam. 2" 1.2000 M' 13,000.00 15,600.00 14,000.00 16,800.00 13,000.00 15,600.00
- Perlengkapan 35% x hrg pipa 4,550.00 4,550.00 4,900.00 4,900.00 4,550.00 4,550.00
L.008 Pekerja 0.0540 OH 50,000.00 2,700.00 50,000.00 2,700.00 - -
L.001 Tukang Batu 0.0900 OH 65,000.00 5,850.00 65,000.00 5,850.00 - -
L.007 Kepala Tukang 0.0090 OH 70,000.00 630.00 70,000.00 630.00 - -
L.010 Mandor 0.0027 OH 50,000.00 135.00 50,000.00 135.00 - -
30 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.31 Pasang Pipa PVC diameter 3" type AW M' SNIJ.6.31 51,165.00 SN2J.6.31 52,715.00 SNSJ.6.31 41,850.00
M.016l Pipa PVC diam. 3" 1.2000 M' 27,000.00 32,400.00 28,000.00 33,600.00 27,000.00 32,400.00
- Perlengkapan 35% x hrg pipa 9,450.00 9,450.00 9,800.00 9,800.00 9,450.00 9,450.00
L.008 Pekerja 0.0540 OH 50,000.00 2,700.00 50,000.00 2,700.00 - -
L.001 Tukang Batu 0.0900 OH 65,000.00 5,850.00 65,000.00 5,850.00 - -
L.007 Kepala Tukang 0.0090 OH 70,000.00 630.00 70,000.00 630.00 - -
L.010 Mandor 0.0027 OH 50,000.00 135.00 50,000.00 135.00 - -
SNI - J.6.32 Memasang 1 m' Pipa PVC diameter 4" type AW M' SNIJ.6.32 83,725.00 SN2J.6.32 85,275.00 SNSJ.6.32 69,750.00
M.016m Pipa PVC diam. 4" 1.2000 M' 45,000.00 54,000.00 46,000.00 55,200.00 45,000.00 54,000.00
- Perlengkapan 35% x hrg pipa 15,750.00 15,750.00 16,100.00 16,100.00 15,750.00 15,750.00
L.008 Pekerja 0.0810 OH 50,000.00 4,050.00 50,000.00 4,050.00 - -
L.001 Tukang Batu 0.1350 OH 65,000.00 8,775.00 65,000.00 8,775.00 - -
L.007 Kepala Tukang 0.0135 OH 70,000.00 945.00 70,000.00 945.00 - -
L.010 Mandor 0.0041 OH 50,000.00 205.00 50,000.00 205.00 - -
Memasang 1 Buah Bak Cuci Piring Stainless
SNI - J.6.33 BH SNIJ.6.33 258,175.00 SN2J.6.33 267,175.00 SNSJ.6.33 235,000.00
Steel
M.015f Bak Cuci piring Stainless stell 1.0000 Bh 206,000.00 206,000.00 215,000.00 215,000.00 206,000.00 206,000.00
M.015g Water drain + Asesories 1.0000 Set 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00
L.008 Pekerja 0.0300 OH 50,000.00 1,500.00 50,000.00 1,500.00 - -
L.001 Tukang Batu 0.3000 OH 65,000.00 19,500.00 65,000.00 19,500.00 - -
L.007 Kepala Tukang 0.0300 OH 70,000.00 2,100.00 70,000.00 2,100.00 - -
L.010 Mandor 0.0015 OH 50,000.00 75.00 50,000.00 75.00 - -
SNI - J.6.35a Memasang 1 Buah Kran diameter 1/2" BH SNIJ.6.35a 68,000.00 SN2J.6.35a 23,000.00 SNSJ.6.35a 60,050.00
M.015h.1 Kran air 1/2" 1.0000 Bh 60,000.00 60,000.00 15,000.00 15,000.00 60,000.00 60,000.00
M.015i Seal tape 0.0250 Bh 2,000.00 50.00 2,000.00 50.00 2,000.00 50.00
L.008 Pekerja 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
L.001 Tukang Batu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
SNI - J.6.36 Memasang 1 Buah Floor Drain BH SNIJ.6.36 26,950.00 SN2J.6.36 27,950.00 SNSJ.6.36 19,000.00
31 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.015j Floor Drain 1.0000 Bh 19,000.00 19,000.00 20,000.00 20,000.00 19,000.00 19,000.00
L.008 Pekerja 0.0100 OH 50,000.00 500.00 50,000.00 500.00 - -
L.001 Tukang Batu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
L.007 Kepala Tukang 0.0100 OH 70,000.00 700.00 70,000.00 700.00 - -
L.010 Mandor 0.0050 OH 50,000.00 250.00 50,000.00 250.00 - -
L. PEKERJAAN LANTAI
SNI - L.6.47b Pas. Lantai Keramik uk. ( 40 x 40 ) cm KW.I M2 SNIL.6.47b 138,899.73 SN2L.6.47b 144,516.50 SNSL.6.47b 66,199.73
M.004d Ubin Keramik 40 x 40 cm KW.I 6.2500 Bh 8,400.00 52,500.00 8,250.00 51,562.50 6,000.00 37,500.00
M.002a Portland Cement 11.3800 Kg 1,280.00 14,566.40 1,300.00 14,794.00 1,280.00 14,566.40
M.001a Pasir Pasang 0.0420 M3 122,222.22 5,133.33 130,000.00 5,460.00 122,222.22 5,133.33
M.002b Semen Warna 1.5000 Kg 6,000.00 9,000.00 10,000.00 15,000.00 6,000.00 9,000.00
L.008 Pekerja 0.6200 OH 50,000.00 31,000.00 50,000.00 31,000.00 - -
L.001 Tukang Batu 0.3500 OH 65,000.00 22,750.00 65,000.00 22,750.00 - -
L.007 Kepala Tukang 0.0350 OH 70,000.00 2,450.00 70,000.00 2,450.00 - -
L.010 Mandor 0.0300 OH 50,000.00 1,500.00 50,000.00 1,500.00 - -
Pas. Lantai Keramik Anti Slip uk. ( 40 x 40 ) cm
SNI - L.6.48b M2 SNIL.6.48b 143,399.73 SN2L.6.48b 181,754.00 SNSL.6.48b 95,299.73
KW.I
M.004j Keramik Lantai 30x30 cm Anti Slip KW.I 11.1000 Bh 5,135.14 57,000.00 8,000.00 88,800.00 6,000.00 66,600.00
M.002a Portland Cement 11.3800 Kg 1,280.00 14,566.40 1,300.00 14,794.00 1,280.00 14,566.40
M.001a Pasir Pasang 0.0420 M3 122,222.22 5,133.33 130,000.00 5,460.00 122,222.22 5,133.33
M.002b Semen Warna 1.5000 Kg 6,000.00 9,000.00 10,000.00 15,000.00 6,000.00 9,000.00
L.008 Pekerja 0.6200 OH 50,000.00 31,000.00 50,000.00 31,000.00 - -
L.001 Tukang Batu 0.3500 OH 65,000.00 22,750.00 65,000.00 22,750.00 - -
L.007 Kepala Tukang 0.0350 OH 70,000.00 2,450.00 70,000.00 2,450.00 - -
L.010 Mandor 0.0300 OH 50,000.00 1,500.00 50,000.00 1,500.00 - -
SNI - L.6.68 Pas. Dinding Keramik uk. ( 20 x 40 ) cm KW.I M2 SNIL.6.68 130,254.00 SN2L.6.68 81,580.00 SNSL.6.68 32,729.00
M.004n Dinding Keramik 20 x 40 cm KW.I 5.5000 Bh 12,000.00 66,000.00 2,000.00 11,000.00 1,750.00 9,625.00
M.002a Portland Cement 9.3000 Kg 1,280.00 11,904.00 1,300.00 12,090.00 1,280.00 11,904.00
M.001a Pasir Pasang 0.0180 M3 122,222.22 2,200.00 130,000.00 2,340.00 122,222.22 2,200.00
M.002b Semen Warna 1.5000 Kg 6,000.00 9,000.00 10,000.00 15,000.00 6,000.00 9,000.00
L.008 Pekerja 0.6000 OH 50,000.00 30,000.00 50,000.00 30,000.00 - -
L.001 Tukang Batu 0.1000 OH 65,000.00 6,500.00 65,000.00 6,500.00 - -
32 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.007 Kepala Tukang 0.0450 OH 70,000.00 3,150.00 70,000.00 3,150.00 - -
L.010 Mandor 0.0300 OH 50,000.00 1,500.00 50,000.00 1,500.00 - -
M. PEKERJAAN PENGECATAN
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14a dasar, 2 lps cat penutup ) Sek. Dulux untuk M2 SNIM.6.14a 38,811.00 SN2M.6.14a 27,651.00 SNSM.6.14a 33,150.00
Exterior
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011a.1 Cat dasar ( sek. Dulux ) 0.1000 Kg 90,000.00 9,000.00 59,000.00 5,900.00 90,000.00 9,000.00
M.011a.1 Cat Penutup 2 kali ( sek. Dulux ) 0.2600 Kg 90,000.00 23,400.00 59,000.00 15,340.00 90,000.00 23,400.00
L.008 Pekerja 0.0200 OH 50,000.00 1,000.00 50,000.00 1,000.00 - -
L.004 Tukang Cat 0.0630 OH 65,000.00 4,095.00 65,000.00 4,095.00 - -
L.007 Kepala Tukang 0.0063 OH 70,000.00 441.00 70,000.00 441.00 - -
L.010 Mandor 0.0025 OH 50,000.00 125.00 50,000.00 125.00 - -
ANALISA BOW
A. PEKERJAAN PAVING
BOW - KPU.
Pasang Paving Blok Natural M2 BKPU. IVa 122,622.22 KPU2.4a 80,400.00 KPUS.4a 72,222.22
IVa
M.013 Paving Blok Natural 6 cm 1.0000 M2 75,000.00 75,000.00 32,000.00 32,000.00 60,000.00 60,000.00
M.001a Pasir Pasang 0.1000 M3 122,222.22 12,222.22 130,000.00 13,000.00 122,222.22 12,222.22
L.001 Tukang Batu 0.2000 OH 65,000.00 13,000.00 65,000.00 13,000.00 - -
L.007 Kepala Tukang 0.0200 OH 70,000.00 1,400.00 70,000.00 1,400.00 - -
L.008 Pekerja 0.4000 OH 50,000.00 20,000.00 50,000.00 20,000.00 - -
L.010 Mandor 0.0200 OH 50,000.00 1,000.00 50,000.00 1,000.00 - -
B. PEKERJAAN KAP BESI
BOW - I.a Pekerjaan Kap Besi Kg BOW.Ia 24,550.00 BOW2.Ia 23,450.00 BOWS.Ia 12,100.00
M.003b Besi Siku/Propil 1.1000 Kg 11,000.00 12,100.00 10,000.00 11,000.00 11,000.00 12,100.00
L.003 Tukang Besi 0.0900 OH 65,000.00 5,850.00 65,000.00 5,850.00 - -
L.007 Kepala Tukang 0.0300 OH 70,000.00 2,100.00 70,000.00 2,100.00 - -
L.008 Pekerja 0.0900 OH 50,000.00 4,500.00 50,000.00 4,500.00 - -
33 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
D. PEKERJAAN PENGECATAN
BOW -
Pengecatan plapond 3x ( sek. Catylac ) M2 BOWK.623 26,863.50 BOW2K.623 25,663.50 BOWSK.623 6,800.00
K.6+23
M.011b Cat Tembok ( sek. Catylac ) 0.4000 Kg 17,000.00 6,800.00 14,000.00 5,600.00 17,000.00 6,800.00
L.004 Tukang Cat 0.1875 OH 65,000.00 12,187.50 65,000.00 12,187.50 - -
L.007 Kepala Tukang 0.0188 OH 70,000.00 1,316.00 70,000.00 1,316.00 - -
L.008 Pekerja 0.1250 OH 50,000.00 6,250.00 50,000.00 6,250.00 - -
L.010 Mandor 0.0062 OH 50,000.00 310.00 50,000.00 310.00 - -
E. PEKERJAAN BETON
BOW-
Pasang Tegel Batu Candi M2 B.Sup.4h 220,008.05 B2.Sup.4h 225,696.05 BS.Sup.4h 164,695.55
Supl.IV.h
120,000.00 Batu Candi 1.0000 M2 120,000.00 120,000.00 125,000.00 125,000.00 120,000.00 120,000.00
BOW-G.13 Perekat G.13 0.0300 M3 1,204,851.56 36,145.55 1,227,785.00 36,833.55 1,204,851.56 36,145.55
19,000.00 Cairan coating 0.4500 Ltr 19,000.00 8,550.00 19,000.00 8,550.00 19,000.00 8,550.00
BOW-G.69 Upah Pasang G.69 1.2500 M3 44,250.00 55,312.50 44,250.00 55,312.50 - -
Pembuatan Septictank 1 x 1 x 2 m
Ls.08 UNIT Ls.08 5,952,064.18 Ls2.08 6,105,154.00 LsS.08 4,391,336.18
+ Peresapan
SNI-B.6.2 Galian Tanah Biasa Sedalam 2 M 10.00 m3 28,900.00 289,000.00 28,900.00 289,000.00 - -
SNI-B.6.9 Urugan Kembali 2.50 m3 10,550.00 26,375.00 10,550.00 26,375.00 - -
SNI-B.6.11 Urugan Pasir 1.50 m3 162,166.67 243,250.00 171,500.00 257,250.00 146,666.67 220,000.00
SNI-C.6.14 Pas. Pondasi Batu Kosong 0.60 m3 273,696.67 164,218.00 288,030.00 172,818.00 204,666.67 122,800.00
SNI-D.6.3 Pas. Batu Merah tb.1 bata 1Pc:3Ps 6.00 m2 185,698.22 1,114,189.33 194,065.00 1,164,390.00 137,298.22 823,789.33
SNI-D.6.10 Pas. Batu Merah tb.1/2 bata 1Pc:3Ps 3.00 m2 89,232.49 267,697.47 93,331.00 279,993.00 65,282.49 195,847.47
SNI-E.6.3 Plesteran 1Pc:3Ps tb.1,5 cm 10.00 m2 31,916.62 319,166.22 32,194.00 321,940.00 10,616.62 106,166.22
SNI-G.6.13 Membuat Beton Cor 1Pc:2Ps:3Kr 0.22 m3 817,080.00 179,757.60 836,100.00 183,942.00 641,880.00 141,213.60
SNI-G.6.25 Pembesian dengan Besi Beton Polos 16.50 kg 13,769.00 227,188.50 14,819.00 244,513.50 12,900.00 212,850.00
BOW-F.8 Cetakan Kayu Tahun 4.00 m2 134,500.00 538,000.00 118,100.00 472,400.00 68,000.00 272,000.00
SNI-J.6.32 Pasang Pipa PVC diam. 4" type AW 8.00 m' 83,725.00 669,800.00 85,275.00 682,200.00 69,750.00 558,000.00
SNI-J.6.31 Pasang Pipa PVC diam. 3" type AW 10.00 m' 51,165.00 511,650.00 52,715.00 527,150.00 41,850.00 418,500.00
SNI-J.6.22 Pasang Pipa Galvanis diam. 1 1/2" med. B 3.00 m' 63,580.00 190,740.00 66,680.00 200,040.00 44,950.00 134,850.00
Ls Kenie T 1.00 bh 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00
M.001f3 Batu pecah 5/7 cm 2.60 m3 160,000.00 416,000.00 170,000.00 442,000.00 160,000.00 416,000.00
34 / 51
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2015
KODE KOEFISIE SATU KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN
ANALISA N AN HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Ls Krosok 2.50 m3 45,000.00 112,500.00 45,000.00 112,500.00 45,000.00 112,500.00
SNI-B.6.14 Pemasangan Lapisan Ijuk 1.85 m3 332,250.00 614,662.50 356,250.00 659,062.50 324,000.00 599,400.00
SNI-G.6.1 Membuat Beton Tumbuk 1Pc:3Ps:5Kr 0.10 m3 603,695.56 60,369.56 620,800.00 62,080.00 499,195.56 49,919.56
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
A. PEKERJAAN PERSIAPAN
1 SNI - A.6.4 M' Pengukuran & Pas.Bouwplank Kayu Meranti 86,515.00 86,815.00 74,065.00
2 SNI - A.6.4a M' Pengukuran & Pas.Bouwplank Kayu Tahun 41,350.00 35,430.00 28,900.00
3 SNI - A.6.6 M2 Pemb.Gudang Semen & Alat-alat Ky.Meranti 1,232,856.67 1,245,750.00 1,036,356.67
4 SNI - A.6.6a M2 Pemb.Gudang Semen & Alat-alat Ky.Tahun 650,106.67 594,750.00 453,606.67
5 SNI - A.6.7 M2 Pemb. Rumah Jaga / Konstruksi Kayu Meranti 1,499,900.00 1,515,600.00 1,339,400.00
6 SNI - A.6.7a M2 Pemb. Rumah Jaga / Konstruksi Kayu Tahun 734,000.00 660,000.00 573,500.00
7 SNI - A.6.8 M2 Membersihkan Lapangan dan Perataan 7,500.00 7,500.00 -
8 SNI - A.6.10 Bh Pemb. Bak Adukan Uk.(40x50x20)cm Ky.Tahun 92,675.00 81,495.00 73,100.00
9 SNI - A.6.11 M2 Pembuatan Steger dari Bambu 23,270.00 23,895.00 8,875.00
10 SNI - A.6.13 M3 Bongkaran Beton Bertulang 350,000.00 350,000.00 -
11 SNI - A.6.14 M3 Bongkaran Dinding Tembok Bt.Merah 335,000.00 335,000.00 -
B. PEKERJAAN TANAH
1 SNI - B.6.1 M3 Galian Tanah Biasa Sedalam 1 M 22,000.00 22,000.00 -
2 SNI - B.6.2 M3 Galian Tanah Biasa Sedalam 2 M 28,900.00 28,900.00 -
3 SNI - B.6.3 M3 Galian Tanah Biasa Sedalam 3 M 40,400.00 40,400.00 -
4 SNI - B.6.4 M3 Galian Tanah Keras Sedalam 1 M 34,350.00 34,350.00 -
5 SNI - B.6.7 M2 Pekerjaan Striping Setinggi 1 M 2,750.00 2,750.00 -
6 SNI - B.6.8 M3 Pembuangan Tanah Sejauh 150 M 28,300.00 28,300.00 -
7 SNI - B.6.9 M3 Urugan Kembali 10,550.00 10,550.00 -
8 SNI - B.6.10 M3 Pemadatan Tanah 27,500.00 27,500.00 -
9 SNI - B.6.11 M3 Urugan Pasir 162,166.67 171,500.00 146,666.67
10 SNI - B.6.14 M3 Pemasangan Lapisan Ijuk 332,250.00 356,250.00 324,000.00
11 SNI - B.6.15 M3 Urugan Sirtu 103,750.00 109,750.00 90,000.00
D. PEKERJAAN DINDING
1 SNI - D.6.3 M2 Pas. Batu Merah tb.1 bata 1Pc:3Ps 185,698.22 194,065.00 137,298.22
2 SNI - D.6.5 M2 Pas. Batu Merah tb.1 bata 1Pc:5Ps 173,282.67 181,520.00 124,882.67
3 SNI - D.6.7 M2 Pas. Batu Merah tb.1 bata 1Pc:3Kp:10Ps 163,482.96 172,779.00 115,082.96
4 SNI - D.6.10 M2 Pas. Batu Merah tb.1/2 bata 1Pc:3Ps 89,232.49 93,331.00 65,282.49
5 SNI - D.6.12 M2 Pas. Batu Merah tb.1/2 bata 1Pc:5Ps 83,840.40 71,084.00 49,390.40
6 SNI - D.6.15 M2 Pas. Batu Merah tb.1/2 bata 1Pc:3Kp:10Ps 81,571.11 86,300.00 57,621.11
E. PEKERJAAN PLESTERAN
1 SNI - E.6.3 M2 Plesteran 1Pc:3Ps tb.1,5 cm 31,916.62 32,194.00 10,616.62
2 SNI - E.6.5 M2 Plesteran 1PC:5Ps tb.1,5 cm 29,518.49 29,776.00 8,218.49
3 SNI - E.6.9 M2 Plesteran 1Pc:3Kp:10Ps tb.1,5 cm 26,866.31 27,312.00 5,566.31
4 SNI - E.6.14 M2 Plesteran 1Pc:3Ps tb.2 cm 44,526.78 44,945.00 17,001.78
5 SNI - E.6.16 M2 Plesteran 1Pc:5Ps tb.2 cm 40,278.42 40,642.00 12,753.42
6 SNI - E.6.28 M2 Berapen 1Pc:5Ps tb.1,5 cm 23,008.71 23,301.00 10,068.71
7 SNI - E.6.30 M2 Plesteran Beton 1Pc:3 Ps tb.1,5 cm 39,666.27 39,971.00 11,616.27
8 SNI - E.6.31 M2 Plesteran Skoning 1Pc:2Ps 8,964.44 8,990.00 884.44
9 SNI - E.6.35 M2 Plesteran Siar Adukan 1Pc:2Ps 20,425.16 20,636.00 7,485.16
F. PEKERJAAN KAYU
1 SNI - F.6.1 M3 Pas. Kusen pintu dan Jendela Ky.Jati 13,855,000.00 13,965,000.00 12,100,000.00
2 SNI - F.6.2 M3 Pas. Kusen pintu dan Jendela Ky.Kamper 9,789,800.00 9,819,800.00 8,164,800.00
3 SNI - F.6.2a M3 Pas. Kusen pintu dan Jendela Ky.Bangkir 9,965,000.00 9,995,000.00 8,340,000.00
35 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
4 SNI - F.6.2b M3 Pas. Kusen pintu dan Jendela Ky.Kruing 7,889,000.00 7,919,000.00 6,264,000.00
5 SNI - F.6.2c M3 Pas. Kusen Pintu dan Jendela Ky Jati (lokal) 13,725,000.00 13,835,000.00 12,100,000.00
6 SNI - F.6.2d M3 Pas. Kusen Pintu dan Jendela Ky Jati Kls I 40,125,000.00 40,125,000.00 38,500,000.00
7 SNI - F.6.2e M3 Pas. Kusen Pintu dan Jendela Ky Bangkir 9,965,000.00 9,995,000.00 8,340,000.00
8 SNI - F.6.7 M2 Pas. Pintu Panil Kayu Jati 692,500.00 696,500.00 460,000.00
9 SNI - F.6.8 M2 Pas. Pintu Panil Kayu Kamper 530,500.00 531,500.00 298,000.00
10 SNI - F.6.8a M2 Pas. Pintu Panil Kayu Bangkir 540,500.00 541,500.00 298,000.00
11 SNI - F.6.8b M2 Pas. Pintu Panil Kayu Kruing 456,500.00 457,500.00 308,000.00
12 SNI - F.6.9 M2 Pas. Pintu dan Jendela Kaca Ky. Jati 588,500.00 592,000.00 402,500.00
13 SNI - F.6.10 M2 Pas. Pintu dan Jendela Kaca Ky.Kamper 446,750.00 447,625.00 260,750.00
14 SNI - F.6.10a M2 Pas. Pintu dan Jendela Kaca Ky.Bangkir 455,500.00 456,375.00 269,500.00
15 SNI - F.6.10b M2 Pas. Pintu dan Jendela Kaca Ky. Kruing 382,000.00 382,875.00 196,000.00
16 SNI - F.6.12 M2 Pas. Pintu dan Jendela Jalusi Ky. Jati 1,017,000.00 1,023,400.00 736,000.00
17 SNI - F.6.13 M2 Pas. Pintu dan Jendela Jalusi Ky. Kamper 767,800.00 769,400.00 476,800.00
18 SNI - F.6.13a M2 Pas. Pintu dan Jendela Jalusi Ky. Bangkir 783,800.00 785,400.00 492,800.00
19 SNI - F.6.13b M2 Pas. Pintu dan Jendela Jalusi Ky. Kruing 649,400.00 651,000.00 358,400.00
20 SNI - F.6.16 M2 Pas. Jalusi Mati Kusen Kayu Jati 863,700.00 867,900.00 693,450.00
21 SNI - F.6.17 M2 Pas. Jalusi Mati Kusen Kayu Kamper 620,700.00 620,400.00 450,450.00
22 SNI - F.6.17a M2 Pas. Jalusi Mati Kusen Kayu Bangkir 635,700.00 635,400.00 465,450.00
23 SNI - F.6.17b M2 Pas. Jalusi Mati Kusen Kayu Kruing 509,700.00 509,400.00 339,450.00
24 SNI - F.6.19 M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Jati 471,100.00 469,610.00 295,600.00
25 SNI - F.6.20 M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Kamper 391,720.00 388,760.00 216,220.00
26 SNI - F.6.20a M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Bangkir 396,620.00 393,660.00 221,120.00
27 SNI - F.6.20b M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Kruing 355,460.00 352,500.00 179,960.00
28 SNI - F.6.20c M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Kamper 377,720.00 376,260.00 202,220.00
29 SNI - F.6.20d M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Bangkir 382,620.00 381,160.00 207,120.00
30 SNI - F.6.20e M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Kruing 341,460.00 340,000.00 165,960.00
31 SNI - F.6.27 M3 Pas. Konstruksi Kuda-kuda Kayu Jati 13,490,000.00 13,388,700.00 12,416,000.00
32 SNI - F.6.28 M3 Pas. Konstruksi Kuda-kuda Kayu Kamper 8,874,400.00 8,690,600.00 7,800,400.00
33 SNI - F.6.28a M3 Pas. Konstruksi Kuda-kuda Kayu Bangkir 9,035,000.00 8,851,200.00 7,961,000.00
34 SNI - F.6.28b M3 Pas. Konstruksi Kuda-kuda Kayu Bangkir (Uk. Khusus) 9,640,000.00 9,428,700.00 8,566,000.00
35 SNI - F.6.30 M3 Pas. Konstruksi Kuda-kuda Kayu Kruing 7,132,000.00 6,948,200.00 6,058,000.00
Pas. Kaso dan Reng genteng (kodok, plentong, vlams
36 SNI - F.6.31 M2 85,650.00 84,300.00 73,200.00
dan sejenisnya) Kayu Kamper
Pas. Kaso dan Reng genteng (kodok, plentong, vlams
37 SNI - F.6.31a M2 88,650.00 87,300.00 76,200.00
dan sejenisnya) Kayu Bangkir
Pas. Kaso dan Reng genteng (kodok, plentong, vlams
38 SNI - F.6.31b M2 74,250.00 72,900.00 61,800.00
dan sejenisnya) Kayu Kruing
Pas. Kaso dan Reng genteng (kodok, plentong, vlams
39 SNI - F.6.31c M2 59,190.00 57,840.00 46,740.00
dan sejenisnya) Kayu Meranti
Pas. Kaso dan Reng genteng (kodok, plentong, vlams
40 SNI - F.6.31d M2 92,250.00 90,600.00 79,800.00
dan sejenisnya) Kayu Bangkir uk. Khusus
Pas. Kaso dan Reng genteng (monier dan sejenisnya)
41 SNI - F.6.35 M2 97,350.00 96,050.00 84,900.00
Kayu Kamper
Pas. Kaso dan Reng genteng (monier dan sejenisnya)
42 SNI - F.6.35a M2 100,850.00 99,550.00 88,400.00
Kayu Bangkir
Pas. Kaso dan Reng genteng (monier dan sejenisnya)
43 SNI - F.6.35b M2 84,050.00 82,750.00 71,600.00
Kayu Kruing
44 SNI - F.6.35c M2 Pas. Usuk 6/12 p .6-8 m' Kayu Bangkir 193,955.00 194,480.00 150,180.00
45 SNI - F.6.35d M3 Pas. Usuk 5/10 kayu Bangkir uk. Khusus #REF! #REF! #REF!
46 SNI - F.6.38 M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Jati 145,250.00 145,350.00 116,000.00
47 SNI - F.6.39 M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Kamper 101,450.00 100,650.00 72,200.00
48 SNI - F.6.39a M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Bangkir 104,450.00 103,650.00 75,200.00
49 SNI - F.6.39b M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Kruing 90,050.00 89,250.00 60,800.00
50 SNI - F.6.39c M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Meranti 74,990.00 74,190.00 45,740.00
36 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
51 SNI - F.6.44 M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Kamper 200,275.00 198,750.00 161,950.00
52 SNI - F.6.44a M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Bangkir 207,025.00 205,500.00 168,700.00
53 SNI - F.6.44b M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Kruing 174,625.00 173,100.00 136,300.00
54 SNI - F.6.44c M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Meranti 140,740.00 139,215.00 102,415.00
55 SNI - F.6.47 M' Pas. Lisplank Uk. (3 x 20) cm Kayu Jati 103,800.00 103,970.00 83,800.00
56 SNI - F.6.48 M' Pas. Lisplank Uk. (3 x 20) cm Kayu Kamper 74,290.00 73,920.00 54,640.00
57 SNI - F.6.48a M' Pas. Lisplank Uk. (3 x 20) cm Kayu Bangkir 76,090.00 75,720.00 56,440.00
58 SNI - F.6.48b M' Pas. Lisplank Uk. (3 x 20) cm Kayu Kruing 60,970.00 60,600.00 41,320.00
59 SNI - F.6.52 M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Jati 114,800.00 115,000.00 100,100.00
60 SNI - F.6.52a M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Kamper 79,970.00 79,525.00 65,270.00
61 SNI - F.6.52b M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Bangkir 82,120.00 81,675.00 67,420.00
62 SNI - F.6.52c M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Kruing 64,060.00 63,615.00 49,360.00
G. PEKERJAAN BETON
1 SNI - G.6.1 M3 Membuat Beton Tumbuk 1Pc:3Ps:5Kr 603,695.56 620,800.00 499,195.56
2 SNI - G.6.4 M3 Lantai Kerja Beton Tumbuk 1Pc:3Ps:5Kr tb.5cm 83,137.78 83,980.00 23,897.78
3 SNI - G.6.7 M3 Membuat Beton Cor 1Pc:2Ps:2,5Kr 749,504.44 767,900.00 645,004.44
4 SNI - G.6.13 M3 Membuat Beton Cor 1Pc:2Ps:3Kr 817,080.00 836,100.00 641,880.00
5 SNI - G.6.25 Kg Pembesian dengan Besi Beton Polos 13,769.00 14,819.00 12,900.00
6 SNI - G.6.25a Kg Pembesian dengan Besi Beton Ulir 14,819.00 15,869.00 13,950.00
7 SNI - G.6.28 M2 Pas. Bekisting untuk Pondasi 99,970.00 84,670.00 66,000.00
8 SNI - G.6.29 M2 Pas. Bekisting untuk Sloof 107,470.00 90,670.00 73,500.00
9 SNI - G.6.30 M2 Pas. Bekisting untuk Kolom 135,367.50 265,760.00 231,675.00
10 SNI - G.6.31 M2 Pas. Bekisting untuk Balok 141,335.00 277,770.00 242,610.00
11 SNI - G.6.32 M2 Pas. Bekisting untuk Lantai 195,867.50 406,760.00 351,675.00
12 SNI - G.6.33 M2 Pas. Bekisting untuk Dinding 374,960.00 380,110.00 334,900.00
13 SNI - G.6.34 M2 Pas. Bekisting untuk Tangga 256,735.00 254,760.00 216,675.00
14 SNI - G.6.45 M' Memb. Kolom Penguat Beton Bertulang (11x11)cm 63,143.33 65,650.00 55,673.33
15 SNI - G.6.46 M' Membuat Ring Balok Beton Bertulang (10x15)cm 72,325.00 75,135.00 59,940.00
H. PEKERJAAN ATAP
1 SNI - H.6.1 M2 Pas. Atap Genteng Plentong Kecil 35,335.00 36,460.00 22,000.00
2 SNI - H.6.2 M2 Pas. Atap Genteng Kodok 43,335.00 43,585.00 30,000.00
3 SNI - H.6.4 M' Pas. Atap Genteng Bubung Plentong 62,401.11 63,060.00 27,901.11
4 SNI - H.6.12 M2 Pas. Asbes Gelombang Uk.(3,00x1,05m)x4mm 42,450.00 43,750.00 30,060.00
5 SNI - H.6.13 M2 Pas. Asbes Gelombang Uk.(2,70x1,05m)x4mm 44,550.00 45,990.00 32,160.00
6 SNI - H.6.14 M2 Pas. Asbes Gelombang Uk.(2,40x1,05m)x4mm 42,235.00 43,715.00 30,040.00
7 SNI - H.6.15 M2 Pas. Asbes Gelombang Uk.(2,10x1,05m)x4mm 43,005.00 44,625.00 30,810.00
8 SNI - H.6.16 M2 Pas. Asbes Gelombang Uk.(1,50x1,05m)x4mm 46,555.00 48,755.00 34,360.00
9 SNI - H.6.16.a M2 Pas. Atap seng Galvalum 84,555.00 87,555.00 72,360.00
10 SNI - H.6.23 M' Pas. Nok Stel Asbes Gelombang Uk. 1,05m 74,485.00 75,535.00 61,050.00
11 SNI - H.6.30 M2 Pas. Atap Genteng Beton 60,100.00 59,770.00 42,400.00
12 SNI - H.6.30a M2 Pas. Atap Genteng Morando 90,300.00 67,470.00 50,100.00
13 SNI - H.6.34 M' Pas. Atap Nok Genteng Beton 666,138.22 87,530.00 71,138.22
14 SNI - H.6.34a M' Pas. Atap Nok Genteng Morando 123,135.11 77,175.00 37,860.11
15 SNI - H.6.38 M2 Pas. Atap Seng Gelombang BJLS 20 36,980.00 37,695.00 26,360.00
16 SNI - H.6.39 M2 Pas. Atap Nok Seng 21,030.00 21,360.00 8,120.00
17 SNI - H.6.40 M' Pas. Talang Datar Seng BJS 30 Ky.Meranti 91,447.50 92,448.75 56,135.00
18 SNI - H.6.40a M' Pas. Talang Datar Seng BJS 30 Ky.Kruing 151,857.50 153,143.75 122,045.00
19 SNI - H.6.41 M' Pas. Talang Miring Seng BJS 30 Ky.Meranti 126,682.50 127,968.75 96,870.00
20 SNI - H.6.41a M' Pas. Talang Miring Seng BJS 30 Ky.Kruing 151,857.50 153,143.75 122,045.00
21 SNI - H.6.42 M2 Pas. Aluminium Foil / Sisalation 25,150.00 25,675.00 13,650.00
22 SNI - H.6.43 M2 Pas. Kawat Burung Kayu Meranti 35,780.00 36,685.00 23,555.00
23 SNI - H.6.43a M2 Pas. Kawat Burung Kayu Kruing 38,165.00 39,070.00 25,940.00
37 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
1 SNI - I.6.19 M' Lis Langit-langit Kayu Propil Kayu Kruing 12,530.00 12,960.00 6,280.00
2 SNI - I.6.19a M' Lis Langit-langgit Kayu Kruing 10,330.00 10,760.00 4,080.00
3 SNI - I.6.20 M2 Langit-langit Eternit Rk.Ky.Kamper Uk.(1x1)m 110,670.00 110,250.00 78,180.00
4 SNI - I.6.20a M2 Langit-langit Eternit Rk.Ky.Bangkir Uk. (1x1)m 113,670.00 113,250.00 81,180.00
5 SNI - I.6.20b M2 Langit-langit Eternit Rk.Ky.Kruing Uk. (1x1)m 99,270.00 98,850.00 66,780.00
6 SNI - I.6.20c M2 Langit-langit Eternit Rk.Ky.Meranti Uk. (1x1)m 83,760.00 83,340.00 51,720.00
7 SNI - I.6.20d M2 Langit-langit Harplek 4mm Rk.Ky.Kruing Uk. (1x1)m 115,210.00 114,790.00 82,720.00
8 SNI - I.6.20e M2 Langit-langit Harplek 4mm Rk.Ky.Meranti Uk. (1x1)m 100,690.00 100,270.00 68,200.00
9 SNI - I.6.24 M2 Langit-langit Gypsum board tb.9mm 25,732.00 25,823.00 16,882.00
J. PEKERJAAN SANITASI
1 SNI - J.6.1 Bh Pasang Kloset Duduk / Monoblok 1,516,570.00 1,755,070.00 1,484,000.00
2 SNI - J.6.2 Bh Pasang Kloset Jongkok Porselen 344,402.22 424,600.00 158,902.22
3 SNI - J.6.4 Bh Pasang Urinoir 655,902.22 682,100.00 528,902.22
4 SNI - J.6.5 Bh Pasang Wastafel 402,652.22 716,450.00 540,902.22
5 SNI - J.6.7 Bh Pasang Bak Mandi Fiberglass vol. 0,30 m3 air 485,800.00 494,060.00 177,000.00
6 SNI - J.6.8 Bh Pasang Bak Mandi Batu Bata vol. 0,30 m3 air. 997,206.67 1,049,580.00 466,206.67
7 SNI - J.6.9 Bh Pasang Bath tubh Porselen 4,703,075.00 4,869,875.00 4,633,200.00
8 SNI - J.6.11 Bh Pasang Bak Fiberglass vol. 1 m3 air 931,300.00 931,300.00 380,800.00
9 SNI - J.6.16 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(35x35)cm T:35 cm 348,798.39 357,607.75 357,607.75
10 SNI - J.6.17 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(45x45)cm T:50 cm 313,808.89 327,822.50 205,223.89
11 SNI - J.6.18 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(60x60)cm T:65 cm 483,733.66 505,374.45 313,493.66
12 SNI - J.6.19 M' Pasang Pipa Galvanis diam. 1/2" med. B 30,680.00 31,455.00 20,150.00
13 SNI - J.6.20 M' Pasang Pipa Galvanis diam. 3/4" med. B 35,330.00 36,105.00 24,800.00
14 SNI - J.6.21 M' Pasang Pipa Galvanis diam. 1" med. B 43,080.00 44,630.00 32,550.00
15 SNI - J.6.22 M' Pasang Pipa Galvanis diam. 1 1/2" med. B 63,580.00 66,680.00 44,950.00
16 SNI - J.6.22a M' Pasang Pipa Galvanis diam. 2" med. B 93,030.00 96,130.00 74,400.00
17 SNI - J.6.23 M' Pasang Pipa Galvanis diam. 3" med. B 136,430.00 139,530.00 117,800.00
18 SNI - J.6.24 M' Pasang Pipa Galvanis diam. 4" med. B 179,840.00 186,040.00 156,550.00
19 SNI - J.6.25 M' Pasang Pipa PVC diam. 1/2" type AW 10,550.00 10,860.00 4,340.00
20 SNI - J.6.26 M' Pasang Pipa PVC diam. 3/4" type AW 12,410.00 13,185.00 6,200.00
21 SNI - J.6.27 M' Pasang Pipa PVC diam. 1" type AW 13,960.00 15,510.00 7,750.00
22 SNI - J.6.28 M' Pasang Pipa PVC diam. 1 1/2" type AW 21,710.00 23,260.00 15,500.00
23 SNI - J.6.29 M' Pasang Pipa PVC diam. 2" type AW 29,465.00 31,015.00 20,150.00
24 SNI - J.6.31 M' Pasang Pipa PVC diam. 3" type AW 51,165.00 52,715.00 41,850.00
25 SNI - J.6.32 M' Pasang Pipa PVC diam. 4" type AW 83,725.00 85,275.00 69,750.00
26 SNI - J.6.33 Bh Pasang Bak Cuci Piring Stainless Steel 258,175.00 267,175.00 235,000.00
27 SNI - J.6.35 Bh Pasang Kran diameter 3/4". 68,000.00 28,000.00 60,050.00
28 SNI - J.6.35a Bh Pasang Kran diameter 1/2" 68,000.00 23,000.00 60,050.00
29 SNI - J.6.36 Bh Pasang Floor Drain 26,950.00 27,950.00 27,950.00
K. PEKERJAAN KUNCI DAN KACA
1 SNI - K.6.1 Bh Pasang Kunci tanam antik 346,350.00 346,350.00 300,000.00
2 SNI - K.6.2 Bh Pasang Kunci Tanam Biasa 118,950.00 118,950.00 85,000.00
3 SNI - K.6.3 Bh Pasang Kunci Tanam Kamar Mandi 65,950.00 65,950.00 32,000.00
4 SNI - K.6.5 Bh Pasang Engsel Pintu 18,587.50 18,587.50 7,000.00
5 SNI - K.6.6 Bh Pasang Engsel Jendela Kupu-kupu 16,087.50 16,087.50 4,500.00
6 SNI - K.6.7 Bh Pasang Engsel Angin 35,900.00 35,900.00 20,000.00
7 SNI - K.6.9 Bh Pasang Kait Angin model lipat 16,587.50 16,587.50 5,000.00
8 SNI - K.6.9.a Bh Pasang Kait Angin model antik 28,087.50 28,087.50 16,500.00
9 SNI - K.6.10 Bh Pasang Door Closer 238,625.00 238,625.00 200,000.00
10 SNI - K.6.11 Bh Pasang Kunci Selot 100,450.00 100,450.00 85,000.00
11 SNI - K.6.12 Bh Pasang Pegangan pintu/Door Holder 214,125.00 214,125.00 175,500.00
12 SNI - K.6.13 Bh Pasang Door Stop 32,725.00 32,725.00 25,000.00
13 SNI - K.6.14 Bh Pasang Rel Pintu Dorong 346,350.00 356,350.00 300,000.00
14 SNI - K.6.16 Bh Pasang Kaca tb. 3mm 64,387.50 67,687.50 52,800.00
15 SNI - K.6.17 Bh Pasang Kaca tb. 5mm 83,087.50 84,187.50 71,500.00
16 SNI - K.6.18 Bh Pasang Kaca tb. 8mm 183,245.00 187,645.00 170,500.00
17 SNI - K.6.20 Bh Pasang Kaca Cermin tb. 5mm 176,587.50 177,687.50 165,000.00
38 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
L. PEKERJAAN LANTAI
1 SNI - L.6.2 M2 Pas. Lantai Ubin PC Abu-abu 30 x 30 cm 61,817.78 64,985.28 39,167.78
2 SNI - L.6.3 M2 Pas. Lantai Ubin PC Abu-abu 20 x 20 cm 57,047.00 60,010.00 33,512.00
3 SNI - L.6.44 M2 Pas. Lantai Keramik 20 x 20 cm KW.I 128,899.73 137,954.00 71,199.73
4 SNI - L.6.44a M2 Pas. Lantai Keramik 20 x 20 cm KW.II 123,899.73 132,954.00 66,199.73
5 SNI - L.6.47 M2 Pas. Lantai Keramik 33 x 33 cm KW.I 136,399.73 147,954.00 78,699.73
6 SNI - L.6.47a M2 Pas. Lantai Keramik 33 x 33 cm KW.II 133,899.73 145,454.00 76,199.73
7 SNI - L.6.47b M2 Pas. Lantai Keramik 40 x 40 cm KW.I 138,899.73 144,516.50 66,199.73
8 SNI - L.6.47c M2 Pas. Lantai Keramik 40 x 40 cm KW.II 135,399.73 145,454.00 77,699.73
9 SNI - L.6.47d M2 Pas. Lantai Keramik 30 x 30 cm KW.I 128,399.73 137,954.00 70,699.73
10 SNI - L.6.47e M2 Pas. Lantai Keramik 30 x 30 cm KW.II 122,399.73 131,954.00 64,699.73
11 SNI - L.6.48 M2 Pas. Lt. Keramik Anti Slip 33x33 cm KW.I 131,399.73 140,454.00 73,699.73
12 SNI - L.6.48a M2 Pas. Lt.Keramik Anti Slip 33x33 cm KW.II 123,899.73 132,954.00 66,199.73
13 SNI - L.6.48b M2 Pas. Lt.Keramik Anti Slip 40x40 cm KW.I 143,399.73 181,754.00 95,299.73
14 SNI - L.6.48c M2 Pas. Lt.Keramik Anti Slip 40x40 cm KW.II 135,399.73 145,454.00 77,699.73
15 SNI - L.6.48d M2 Pas. Lt.Keramik Anti Slip 30x30 cm KW.I 128,399.73 137,954.00 70,699.73
16 SNI - L.6.48e M2 Pas. Lt.Keramik Anti Slip 30x30 cm KW.II 125,399.73 134,954.00 67,699.73
17 SNI - L.6.68 M2 Pas. Dinding Keramik 20x20 cm KW.I 130,254.00 81,580.00 32,729.00
Pas. Dinding Keramik 20x25 cm KW.I 130,254.00 81,580.00 32,729.00
18 SNI - L.6.68a M2 Pas. Dinding Keramik 20x20 cm KW.II 104,254.00 116,830.00 63,104.00
Pas. Dinding Keramik 20x25 cm KW.II 104,254.00 116,830.00 63,104.00
M. PEKERJAAN PENGECATAN
1 SNI - M.6.1 M2 Mengerok Permukaan Cat Tembok Lama 8,375.00 8,425.00 750.00
2 SNI - M.6.6 M2 Mendempul dan Menggosok Kayu 6,047.75 6,110.00 1,042.75
3 SNI - M.6.7 M2 Mengecat kayu Lama 22,025.00 22,270.00 13,000.00
4 SNI - M.6.8 M2 Mengecat kayu 2 x jadi (Sek. Avian) 22,755.00 23,245.00 18,125.00
5 SNI - M.6.9 M2 Mengecat kayu 3 x jadi (Sek. Avian) 31,780.00 32,315.00 21,050.00
6 SNI - M.6.11 M2 Pelaburan Kayu dgn Politur 22,195.00 22,195.00 17,050.00
7 SNI - M.6.12 M2 Pelaburan Kayu dgn Cat Residu dan Ter 6,350.00 6,350.00 1,050.00
8 SNI - M.6.14 M2 Mengecat Tembok 2x utk interior(sek.Mowilex) 38,811.00 19,551.00 33,150.00
9 SNI - M.6.14a M2 Mengecat Tembok 4x utk exterior (sek.Mowilex) 38,811.00 27,651.00 33,150.00
10 SNI - M.6.14b M2 Mengecat Tembok 4x (sek.Catylac) 12,531.00 11,451.00 6,870.00
11 SNI - M.6.14c M2 Mengecat Tembok 4x (sek.Decolith) 12,531.00 10,911.00 6,870.00
12 SNI - M.6.14d M2 Mengecat Tembok 4x (sek.Molex) 38,811.00 8,571.00 33,150.00
13 SNI - M.6.15 M2 Mengecat Tembok lama 2x utk interior(sek.Mowilex) 31,549.00 15,499.00 27,000.00
14 SNI - M.6.15a M2 Mengecat Tembok lama 2x utk exterior(sek.Mowilex) 31,549.00 22,249.00 27,000.00
15 SNI - M.6.15b M2 Mengecat Tembok lama 2x (sek.Catylac) 9,649.00 8,749.00 5,100.00
16 SNI - M.6.15c M2 Mengecat Tembok lama 2x (sek.Decolith) 9,649.00 8,299.00 5,100.00
17 SNI - M.6.15d M2 Mengecat Tembok lama 2x (sek.Mollex) 31,549.00 6,349.00 27,000.00
18 SNI - M.6.17 M2 Melabur Tembok dengan Kapur Sirih 10,567.00 10,647.00 2,870.00
19 SNI - M.6.18 M2 Melabur Tembok Lama dgn Kapur Sirih 4,925.00 4,985.00 2,440.00
20 SNI - M.6.20 M2 Mengecat Baja dengan Meni Besi 17,038.00 17,140.00 1,138.00
21 SNI - M.6.21 M2 Mengecat Baja dgn Meni Besi & Perancah 32,113.00 32,215.00 3,038.00
22 SNI - M.6.24 M2 Mengecat Baja 3x cat konvensional 119,700.00 119,880.00 11,700.00
ANALISA BOW
A. PEKERJAAN PAVING
1 BOW - KPU.IVa M2 Pas. Paving Blok Natural 6 cm 122,622.22 80,400.00 72,222.22
2 BOW - KPU.IVb M2 Pas. Paving Blok Warna 6 cm 107,622.22 84,400.00 72,222.22
3 BOW - KPU.IVc M2 Pas. Paving Blok T = 8cm K-400 127,622.22 176,400.00 92,222.22
4 BOW - KPU.IVd M2 Pas. Paving Blok T = 6cm K-300 127,622.22 113,400.00 92,222.22
39 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
C. PEKERJAAN KAYU
1 BOW - F.16 M2 Pas. Kembali Usuk dan Reng Bekas 17,450.00 14,700.00 5,000.00
2 BOW - F.16a M2 Pas. Reng Kayu Kruing 27,637.50 25,732.50 18,300.00
3 BOW - F.16b M2 Usuk Diketam Halus dan Reng Ky.Kruing 88,700.00 86,250.00 63,800.00
4 BOW - F.16c M2 Usuk Diketam Halus dan Reng Ky.Bangkir 103,100.00 100,650.00 78,200.00
5 BOW - F.16d M2 Usuk Diketam Halus dan Reng Ky.Kamper 100,100.00 97,650.00 75,200.00
6 BOW - F.16e M2 Usuk Diketam Halus dan Reng Ky.Jati 143,900.00 142,350.00 119,000.00
7 BOW - F.16f M2 Pas. Usuk Kayu Kruing 71,887.50 70,125.00 62,550.00
8 BOW - F.16g M2 Pas. Usuk Kayu Bangkir 86,287.50 84,525.00 76,950.00
9 BOW - Supl.VIIIa M2 Plafond Harplek Diatas Usuk 29,160.00 28,920.00 19,160.00
10 BOW - Supl.VIIIb M2 PlaFond Eternit Diatas Usuk 18,060.00 17,820.00 7,060.00
11 BOW - F.36a M2 Pintu Kaca Kayu Kruing tebal 3,5 cm 683,760.00 684,670.00 146,760.00
12 BOW - F.36b M2 Pintu Kaca Kayu Kruing Sederhana tebal 3,5 cm 493,060.00 493,920.00 135,560.00
13 BOW - F.36c M2 Pintu Kaca Kayu Bangkir tebal 3,5 cm 721,560.00 722,470.00 184,560.00
14 BOW - F.36d M2 Pintu Kaca Kayu Kamper tebal 3,5 cm 717,060.00 717,970.00 180,060.00
15 BOW - F.36e M2 Pintu Kaca Kayu Jati tebal 3,5 cm 778,060.00 781,720.00 241,060.00
16 BOW - F.36f M2 Jendela Kaca Kayu Kruing tebal 2,5 cm 504,010.00 506,170.00 101,260.00
17 BOW - F.36g M2 Jendela Kaca Kayu Kruing Sederhana tebal 3 cm 369,760.00 371,920.00 101,260.00
18 BOW - F.36h M2 Jendela Kaca Kayu Bangkir tebal 2,5 cm 529,210.00 531,370.00 126,460.00
19 BOW - F.36i M2 Jendela Kaca Kayu Kamper tebal 2,5 cm 526,210.00 528,370.00 123,460.00
20 BOW - F.36j M2 Jendela Kaca Kayu Jati tebal 2,5 cm 574,810.00 577,870.00 172,060.00
21 BOW - F.36k M2 Pintu Panil Multiplek 9 mm Rangka Kayu Jati tebal 3,5 c 616,600.00 619,520.00 258,800.00
22 BOW - F.36l M2 Pintu Panil Multiplek 9 mm Rangka Kayu Kruing 510,400.00 511,970.00 152,600.00
23 BOW - F.36m M2 Pintu Panil Multiplek 9 mm Rangka Kayu Bangkir 548,200.00 549,770.00 190,400.00
24 BOW - F.36n M2 Pintu Panil Multiplek 9 mm Rangka Kayu Kamper 588,800.00 589,920.00 51,800.00
D. PEKERJAAN ATAP
1 BOW - K.6+23 M2 Mengecat Plapond 3x jadi ( Sek. Catylac ) 26,863.50 25,663.50 6,800.00
2 BOW - K.6+23a M2 Mengecat Plapond 3x jadi ( Sek. Decolith ) 26,860.00 25,060.00 6,800.00
3 BOW - K.6+23b M2 Mengecat Plapond 3x jadi ( Sek. Mollex ) 56,060.00 22,460.00 36,000.00
4 BOW - K.6+23c M2 Mengecat Genteng 3x jadi (Sek. Tamitex) 26,660.00 26,660.00 6,600.00
PEKERJAAN BETON
E. PEKERJAAN BETON
1 BOW - F.8 M2 Cetakan Kayu Tahun 134,500.00 118,100.00 68,000.00
PEKERJAAN PASANGAN BATU GRANIT
F. PEKERJAAN PEMASANGAN BATU GRANIT
1 BOW-G.14 M3 Perekat camp. 1 Pc : 2 Psr 867,727.11 886,860.00 867,727.11
2 BOW-G.13 M3 Perekat camp. 1 Pc : 1 Psr 1,204,851.56 1,227,785.00 1,204,851.56
3 BOW-G.77 M2 Upah Pasang Lembaran Batu Granit 623,000.00 623,000.00 -
4 BOW-Supl.IVa M2 Pasang lantai Batu Granit 908,901.81 909,475.80 285,901.81
5 BOW-Supl.IVb M2 Pasang Pelapis Dinding Batu Granit 1,407,807.03 1,458,335.70 784,807.03
6 BOW-Supl.IVc M2 Pelapisan Coating 3x ( sebelum dipasang ) 13,800.00 13,800.00 8,550.00
7 BOW-Supl.IVd M2 Pelapisan Coating 1x ( setelah dipasang ) 8,300.00 8,300.00 5,700.00
8 BOW-Supl.IVe M2 Pemolesan Lantai Batu Granit ( sampai mengkilap ) 151,300.00 151,300.00 130,800.00
9 BOW-Supl.IVf M2 Pemolesan Lembaran Batu Granit ( Rata, Halus tidak men 33,300.00 33,300.00 18,700.00
10 BOW-Supl.IVg M2 Penyemiran Lantai 11,325.00 11,325.00 4,825.00
11 BOW-G.69 M3 Upah Pasang Tegel 44,250.00 44,250.00 -
12 BOW-Supl.IVh M2 Pasang Tegel Batu Candi 220,008.05 225,696.05 164,695.55
13 BOW-Supl.IVi M2 Pasang Koral Sikat 237,470.55 255,658.55 148,970.55
14 BOW-Supl.IVj M2 Pasang Pelapis Dinding Batu Granit Import 2,530,807.03 2,131,335.70 1,284,807.03
PEKERJAAN LAIN - LAIN
1 Up.SNI-H.6.1 M2 Upah Pas. Genteng lama 13,335.00 13,335.00 0.00
2 Ls.01 Bh Pas. Grendel pintu 6,000.00 6,000.00 6,000.00
40 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
3 Ls.02 Bh Pas. Grendel jendela 4,000.00 4,000.00 4,000.00
4 Ls.03 Bh Pas. Tarikan jendela 4,500.00 4,500.00 4,500.00
5 Ls.04 Daun Pas. Kaca Nako 5 mm + Tralis 20,000.00 20,000.00 20,000.00
6 Ls.05 Kg Pas. Besi, Doog, Angkur 7,000.00 7,000.00 7,000.00
7 Ls.06 Kg Pas. Begel 7,000.00 7,000.00 7,000.00
8 Ls.07 M' Pas. Tutup Lisplank Kayu Kruing Lapis Seng 15,000.00 15,000.00 15,000.00
9 Ls.08 Unit Pembuatan Septictank 1 x 1 x 2 m + Peresapan 5,952,064.18 6,105,154.00 4,391,336.18
10 Ls.09 Unit Pembuatan Septictank 1.5 x 2 x 2 m + Peresapan 8,306,249.09 8,545,682.95 5,729,112.34
11 Ls.11 Titik Pas. Instalasi Titik Cahaya / Lampu 150,000.00 150,000.00 150,000.00
12 Ls.12 Titik Pas. Instalasi Stop Kontak 150,000.00 150,000.00 150,000.00
13 Ls.13 Titik Pas. A r d e 150,000.00 150,000.00 150,000.00
14 Ls.14 Unit Biaya Sambungan Listrik ( PLN ) 900 watt 388,410.00 388,410.00 388,410.00
15 Ls.15 Unit Biaya Sambungan Listrik ( PLN ) 450 watt 226,050.00 226,050.00 226,050.00
16 Ls.16 Unit Biaya Sambungan Listrik ( PLN ) 1300 watt 559,570.00 559,570.00 559,570.00
17 Ls.16.a Unit Biaya Sambungan Listrik ( PLN ) 2200 watt 944,680.00 944,680.00 944,680.00
18 Ls.17 Bh Pas. Shock 1/2" PVC 1,250.00 1,250.00 1,250.00
19 Ls.18 Bh Pas. Shock 3/4" PVC 1,750.00 1,750.00 1,750.00
20 Ls.19 Bh Pas. Shock 2" PVC 4,000.00 4,000.00 4,000.00
21 Ls.20 Bh Pas. Shock 3" PVC 7,000.00 7,000.00 7,000.00
22 Ls.21 Bh Pas. Shock 4" PVC 12,500.00 12,500.00 12,500.00
23 Ls.22 Bh Pas. Kenie 1/2" PVC 2,000.00 2,000.00 2,000.00
24 Ls.23 Bh Pas. Kenie 3/4" PVC 2,500.00 2,500.00 2,500.00
25 Ls.24 Bh Pas. Kenie 2" PVC 5,000.00 5,000.00 5,000.00
26 Ls.25 Bh Pas. Kenie 3" PVC 12,500.00 12,500.00 12,500.00
27 Ls.26 Bh Pas. Kenie 4" PVC 25,000.00 25,000.00 25,000.00
28 Ls.27 M' Pas. Saluran U 20x25 dengan buis beton 58,000.00 58,000.00 58,000.00
29 Ls.31 M' Pas. Papan Sanggan Talang 2 x 20 cm kayu kruing 40,000.00 40,000.00 40,000.00
30 Ls.32 M' Pas. Papan Suri - suri 2 x 20 cm Kayu Kruing 25,000.00 25,000.00 25,000.00
31 Ls.33 M' Pas. Papan Suri - suri 2 / 20 cm Kayu Jati 47,000.00 47,000.00 47,000.00
32 Ls.34 M' Pas. Kawat Duri 3,000.00 3,000.00 3,000.00
33 Ls.35 M2 Pengrosokan Halaman tebal 7 cm 3,250.00 3,250.00 3,250.00
34 Ls.36 Unit Pas. Lampu TL 20 watt 50,000.00 50,000.00 50,000.00
35 Ls.37 Unit Pas. Lampu TL 40 watt 60,000.00 60,000.00 60,000.00
36 Ls.38 Bh Pas. Lampu Pijar 4,000.00 4,000.00 4,000.00
37 Ls.39 Bh Pas. Lampu SL 18 watt 60,000.00 60,000.00 60,000.00
38 Ls.40 Btg Pas. Talang PVC U 75,000.00 75,000.00 75,000.00
39 Ls.41 Bh Pas. Tutup Talang PVC U 3,000.00 3,000.00 3,000.00
40 Ls.42 Bh Pas. Hak Talang PVC U 6,500.00 6,500.00 6,500.00
41 Ls.43 Bh Pas. Kenie Talang PVC U 13,000.00 13,000.00 13,000.00
42 Ls.44 Bh Pas. Corong Talang PVC U 13,000.00 13,000.00 13,000.00
43 Ls.45 Bh Pas. Sarangan Stainless steel 25,000.00 25,000.00 25,000.00
44 Ls.46 Bh Step nosing/ plint tangga 12,000.00 12,000.00 12,000.00
45 Ls.47 m2 Pas. folding gate besi 450,000.00 450,000.00 450,000.00
46 Ls.48 set Pas. pintu aluminium uk. 70 cm lengkap 276,000.00 276,000.00 276,000.00
47 Ls.49 set Pas. pintu PVC uk. 70 cm lengkap 325,000.00 325,000.00 325,000.00
41 / 51
PEMERINTAH KABUPATEN BANYUMAS
DINAS PEKERJAAN UMUM KAB. BANYUMAS
DAFTAR HARGA SATUAN PEKERJAAN
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038
PURWOKERTO HSP
TAHUN 2007
HRG SATUAN (Rp)
NO KODE ANALIS SATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
SWAKELOLA
(Mudah) (Sulit)
7 E1.322 M3 URUGAN SIRTU #REF! #REF!
8 E1.321 M3 URUGAN TANAH BIASA #REF! #REF!
9 E1.511 M3 LAPIS PONDASI AGREGAT KELAS A #REF! #REF!
10 E1.512 M3 LAPIS PONDASI AGREGAT KELAS B #REF! #REF!
11 E1.521 M3 LAPIS PONDASI AGREGAT KELAS C #REF! #REF!
12 E1.611 LITER LAPIS RESAP PENGIKAT #REF! #REF!
13 E1.612 LITER LAPIS PEREKAT #REF! #REF!
14 E1.817a M3 LAPIS PENETRASI MACADAM (Leveling) #REF! #REF!
15 E1.631 M2 LATASIR ( SAND SHEET ) #REF! #REF!
16 E1.817b M2 LAPIS PENETRASI MACADAM SHEET #REF! #REF!
17 E1.635 M3 ASPHALT TREATED BASE (ATB) #REF! #REF!
18 E1.635a TON ASPHALT TREATED BASE LEVELING (ATBL) #REF! #REF!
19 E1.633 M2 LATASTON (HRS) #REF! #REF!
20 E1.716 M3 BETON K-125 #REF! #REF!
21 E1.711 M3 BETON K-250 #REF! #REF!
22 E1.714b M3 BETON K-350 #REF! #REF!
23 E1.712a M3 BETON CYCLOP #REF! #REF!
24 E1.713a M3 BETON STRUKTUR K-225 KANSTIN ( EKSPOS ) #REF! #REF!
25 E1.72 Kg. PENULANGAN / PEMBESIAN 15,125.00 16,225.00
26 E1.710 M2 ACUAN (Begisting) utk Jbt / gorong-gorong 67,900.00 66,450.00
27 E1.813 M2 PENGECATAN KAYU / BESI 28,973.00 29,141.00
28 E1.753 M3 BRONJONG (GABIONS) 353,625.00 372,125.00
29 E1.79 M3 PASANGAN BATU (MEKANIK) #REF! #REF!
30 E1.841 M2 MARKA JALAN THERMOPLASTIC 75,000.00 75,000.00
31 E1.715 M2 GROOVING 7,244.57 7,244.57
32 E1.847 BH PATOK KILOMETER #REF! #REF!
33 E1.846 BH PATOK HEKTOMETER #REF! #REF!
34 E1.723.4 M' TIANG PANCANG BETON #REF! #REF!
35 W.2 M2 Memasang Onderlaag tebal 15 cm 58,916.11 61,305.00
36 A.18 M3 Urugan pasir pasang 162,166.67 171,500.00
37 W.3 M2 Memasang Stenslaag tebal 6 cm 19,385.83 20,340.14
38 KPU.IVa M2 Pasang Paving Blok Natural 107,622.22 80,400.00
39 KPU.IVb M2 Pasang Paving Blok Warna 107,622.22 84,400.00
40 W.3.a M2 Memasang Stenslaag tebal 6 - 8 cm 28,394.44 29,550.00
41 A.19 M3 Urugan pasir Urug 162,166.67 171,500.00
42 W.3.a M2 Sokongon Jembatan (Bekisting)
42 / 51
BESI BETON / Mild Steel Round Bars
SIZE WEIGHT WEIGHT/m1
6 mm - 12 M 2.66 Kg 0.22167 Kg
6.5 mm - 12 M 3.2 Kg 0.26667 Kg
7.5 mm - 12 M 4.4 Kg 0.36667 Kg
8 mm - 12 M 4.74 Kg 0.395 Kg
9 mm - 12 M 6 Kg 0.5 Kg
10 mm - 12 M 7.4 Kg 0.61667 Kg
11 mm - 12 M 8.95 Kg 0.74583 Kg
12 mm - 12 M 10.7 Kg 0.89167 Kg
13 mm - 12 M 12.6 Kg 1.05 Kg
14 mm - 12 M 14.5 Kg 1.20833 Kg
15 mm - 12 M 16.6 Kg 1.38333 Kg
16 mm - 12 M 19 Kg 1.58333 Kg
18 mm - 12 M 24 Kg 2 Kg
19 mm - 12 M 26.8 Kg 2.23333 Kg
21 mm - 12 M 32.6 Kg 2.71667 Kg
22 mm - 12 M 36.8 Kg 3.06667 Kg
24 mm - 12 M 42.6 Kg 3.55 Kg
25 mm - 12 M 46.24 Kg 3.85333 Kg
29 mm - 12 M 62.22 Kg 5.185 Kg
32 mm - 12 M 75.77 Kg 6.31417 Kg
35 mm - 12 M 90.63 Kg 7.5525 Kg
36 mm - 12 M 95.88 Kg 7.99 Kg
Prankuta. Doc
BESI BETONSPIRAL / Deformed Bars
.= Rp 130,000,000.00 X 100%
Rp 700,684,261.41
.= 18.553 %
.= 5 jt x 7 minggu
.= 35 jt
REALISASI .= Rp 35,000,000.00
RAB RENCANA TENAGA Rp 15,552,655.22 (-)
PEKERJAAN TAMBAH .= Rp 19,447,344.78
.= Rp 130,000,000.00 X 100%
Rp 700,684,261.41
.= 18.553 %
.= Rp 130,000,000.00 X 100%
Rp 700,684,261.41
.= 18.553 %
2 Penggantian Atap Jurai Pojok Utara-Timur, Penggantian Kayu, Sudah jadi, Bongkar Pasang
* Tukang , 2 orang 3 hari 3 Hari Rp 140,000.00 Rp 420,000.00
9 Pas Plafon Dak Luar Kamr mandi dan 4 Hari Rp 70,000.00 Rp 280,000.00
Teras Ruang Tamu.
Gambar Expose
Rp 3,035,000.00 Rp 3,035,000.00
URAIAN
PEKERJAAN TAMBAH KURANG KEDUA RUMAH PAK AGUS
2 Penggantian Atap Jurai Pojok Utara-Timur, Penggantian Kayu, Sudah jadi, Bongkar Pasang
* Tukang , 2 orang 3 hari
9 Pas Plafon Dak Luar Kamr mandi dan Digambar Tidak Ada
Teras Ruang Tamu.
Gambar Expose
KETERANGAN
Sudah