SUMMARY

I PEKERJAAN PERSIAPAN Rp 693,600.00


II PEKERJAAN TANAH DAN PONDASI Rp 5,308,913.04
III PEKERJAAN BETON Rp 21,974,658.30
IV PEKERJAAN ATAP Rp 2,840,640.00
V PEKERJAAN PASANGAN DINDING, LANTAI, PLESTERAN DAN ACIAN Rp 6,191,991.84
VI PEKERJAAN KUSEN, JENDELA DAN PINTU Rp 12,571,700.00
VII PEKERJAAN PENGGANTUNG DAN KUNCI Rp 1,242,792.00
VIII PEKERJAAN PLAFOND Rp 2,669,184.00
IX PEKERJAAN FINISHING Rp 1,837,440.00
X PEKERJAAN SANITAIR Rp 13,992,936.00
XI PEKERJAAN M & E Rp 2,381,280.00
TOTAL : 71,705,135
DIBULATKAN 71,705,000

Diajukan Oleh
PT. Andromeda Putra Nusantara

( Bayu )
Project Manager
BILL OF QUANTITY
Pekerjaan : POS JAGA
Lokasi : KAWASAN SAINS DAN TEKNOLOG CIBINONG, BOGOR JAWA BARAT
Tahun : 2023

HARGA SATUAN TOTAL HARGA


NO URAIAN PEKERJAAN SAT VOL KET
(RP) (RP)

I PEKERJAAN PERSIAPAN Rp 693,600.00


1 Pemasangan Bowplank m1 10.80 Rp 42,000.00 Rp 453,600.00
2 Air Kerja unit 1 Rp 120,000.00 Rp 120,000.00
3 Listrik Kerja unit 1 Rp 120,000.00 Rp 120,000.00

II PEKERJAAN TANAH DAN PONDASI Rp 5,308,913.04


1 Pekerjaan Galian Pondasi Batu Kali m3 8.91 Rp 108,240.00 Rp 964,418.40
2 Pekerjaan Galian Pondasi Footplat 160 X 160 cm m3 7.68 Rp 108,240.00 Rp 831,283.20
3 Pekerjaan Urugan Pasir Bawah Pondasi m3 4.18 Rp 312,576.00 Rp 1,306,567.68
4 Pekerjaan Pasang Batu Kali m3 1.89 Rp 1,020,000.00 Rp 1,927,800.00
5 Urugan Tanah Kembali Bekas Galian m3 5.53 Rp 34,200.00 Rp 189,126.00
6 Pemadatan Tanah m2 1.15 Rp 77,880.00 Rp 89,717.76

III PEKERJAAN BETON Rp 21,974,658.30


1 Pekerjaan Footplat
Beton K250 m3 1.173 Rp 1,265,000.00 Rp 1,484,351.00
Besi Tulangan Ulir kg 212.284 Rp 17,500.00 Rp 3,714,978.50

2 Pekerjaan Kolom (K1)


Beton K250 m3 0.540 Rp 1,265,000.00 Rp 683,100.00
Besi Tulangan Ulir kg 64.687 Rp 17,500.00 Rp 1,132,024.61

3 Pekerjaan Sloof 20x30


Beton K250 m3 0.612 Rp 1,265,000.00 Rp 774,180.00
Besi Tulangan Ulir kg 89.492 Rp 17,500.00 Rp 1,566,104.04

4 Pekerjaan Kolom Praktis


Beton K250 m3 0.135 Rp 1,265,000.00 Rp 170,775.00
Besi Tulangan kg 32.282 Rp 17,500.00 Rp 564,933.36

5 Pekerjaan Balok
Beton K250 m3 0.608 Rp 1,265,000.00 Rp 768,487.50
Besi Tulangan Ulir kg 87.272 Rp 17,500.00 Rp 1,527,262.18

6 Pekerjaan Balok Intel +0.80


Beton K250 m3 0.177 Rp 1,265,000.00 Rp 223,430.63
Besi Tulangan Ulir kg 52.223 Rp 17,500.00 Rp 913,905.95

7 Pekerjaan Balok Intel +2.40


Beton K250 m3 0.199 Rp 1,265,000.00 Rp 251,893.13
Besi Tulangan Ulir kg 92.972 Rp 17,500.00 Rp 1,627,008.09

8 Pekerjaan Pelat Lantai T 7 cm


Beton K250 m3 0.403 Rp 1,265,000.00 Rp 510,048.00
Besi Tulangan Ulir kg 41.763 Rp 17,500.00 Rp 730,848.55

9 Pekerjaan DAK T 10 cm
Beton K250 m3 1.764 Rp 1,265,000.00 Rp 2,231,460.00
Besi Tulangan Kg 162.563 Rp 17,500.00 Rp 2,844,843.75

10 Pekerjaan Meja Beton


Beton K250 m3 0.202 Rp 1,265,000.00 Rp 255,024.00

IV PEKERJAAN ATAP Rp 2,840,640.00


1 Dak Expose (Skim Coat) m2 18.920 Rp 102,000.00 Rp 1,929,840.00
2 List Profil m2 13.800 Rp 66,000.00 Rp 910,800.00

V PEKERJAAN PASANGAN DINDING, LANTAI, PLESTERAN DAN ACIAN Rp 6,191,991.84


1 Pekerjaan Pasangan Dinding Hebel m2 9.88 Rp 210,000.00 Rp 2,074,800.00
2 Pekerjaan Pleseteran Dinding m2 0.38 Rp 96,000.00 Rp 36,172.80
3 Pekerjaan Acian Dinding m2 0.04 Rp 78,000.00 Rp 2,939.04
4 Keramik Lantai 60 x 60 cm m2 5.76 Rp 558,000.00 Rp 3,214,080.00
5 Plint skriting Granit Tile 10 x 60 cm m2 5.76 Rp 150,000.00 Rp 864,000.00

VI PEKERJAAN KUSEN, JENDELA DAN PINTU Rp 12,571,700.00


1 Kusen Pintu 80 x 220 (aluminium) m1 5.20 Rp 222,000.00 Rp 1,154,400.00
2 Daun Pintu Kaca bh 1.00 Rp 3,500,000.00 Rp 3,500,000.00
3 Kaca + Silent m2 13.89 Rp 570,000.00 Rp 7,917,300.00

VII PEKERJAAN PENGGANTUNG DAN KUNCI Rp 1,242,792.00


1 Handle pintu Solid unit 1 Rp 342,000.00 Rp 342,000.00
2 Kunci pintu Solid unit 1 Rp 264,792.00 Rp 264,792.00
3 Engsel pintu uk. 5" Solid unit 3 Rp 72,000.00 Rp 216,000.00
4 Door Stoper Solid unit 1 Rp 420,000.00 Rp 420,000.00

VIII PEKERJAAN PLAFOND Rp 2,669,184.00


1 Pasang plafond Gypsum rangka hollow m2 5.76 Rp 323,400.00 Rp 1,862,784.00
2 Pasang list plafon m1 19.20 Rp 42,000.00 Rp 806,400.00

IX PEKERJAAN FINISHING Rp 1,837,440.00


1 Cat plafond ex. Vinilex m2 5.76 Rp 72,000.00 Rp 414,720.00
2 Cat dinding dalam ex. dulux m2 9.88 Rp 78,000.00 Rp 770,640.00
3 Cat dinding luar ex. dulux weathersield m2 9.88 Rp 66,000.00 Rp 652,080.00

X PEKERJAAN SANITAIR Rp 13,992,936.00


1 Piapa 3" m1 9.5 Rp 450,000.00 Rp 4,275,000.00
2 Sambungan Pipa 3" bh 4.0 Rp 68,400.00 Rp 273,600.00
3 Pekerjaan Pasangan Roof Drain Toto o2'' bh 3.00 Rp 68,112.00 Rp 204,336.00
4 Bak Kontrol bh 2.00 Rp 1,020,000.00 Rp 2,040,000.00
5 Pipa Saluran Bak Kontrol m1 16.00 Rp 450,000.00 Rp 7,200,000.00

XI PEKERJAAN M & E Rp 2,381,280.00


1 Stop Kontak Ls 1 Rp 66,000.00 Rp 66,000.00
2 Pekerjaan Pasangan Lampu Gantung LED Ls 5 Rp 463,056.00 Rp 2,315,280.00