Tahun :
2021
Lokasi :
Bontang Lestari
Kota Bontang Kalimantan Timur
RENCANA ANGGARAN BIAYA
REKAPITULASI BIAYA
Pekerjaan : Perencanaan Pembangunan Mesjid dan Kantor Pesantren Hidayatullah
Lokasi : Bontang Lestari - Kota Bontang
Tahun : 2021
JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp.)
I TAHAP 1
I PEKERJAAN PENDAHULUAN 41,020,000.00
II PEKERJAAN TANAH 20,491,400.00
III PEKERJAAN PONDASI PAS. BATU GUNUNG 113,357,160.00
IV PEKERJAAN STRUKTUR BETON 2,123,043,885.80
V PEKERJAAN LANTAI DAN DAK BETON 1,775,485,615.68
VI PEKERJAAN PASANGAN DINDING LT I,II,III 494,348,386.00
VII PEKERJAAN KUSEN PINTU, JENDELA & ASSESORIES 219,909,000.00
VIII PEKERJAAN LANTAI I,II,III 450,488,691.43
IX PEKERJAAN CAT - CATAN 132,703,540.00
X PEK. INSTALASI LISTRIK 58,750,000.00
XI PEKERJAAN SANITASI & LAINNYA 66,640,000.00
A JUMLAH 5,496,237,678.91
B. PPN (10% x A) 549,623,767.89
C. JUMLAH TOTAL (A + B) 6,045,861,446.80
B DIBULATKAN 6,045,861,000.00
Terbilang : Enam Milyar Empat Puluh Lima Juta Delapan Ratus Enam Puluh Satu Ribu Rupiah
DI Buat Oleh :
Konsultan Perencana
Team Leader
DAFTAR KUANTITAS DAN HARGA
Pekerjaan : Perencanaan Pembangunan Mesjid dan Kantor Pesantren Hidayatullah
Lokasi : Bontang Lestari - Kota Bontang
Tahun : 2021
I PEKERJAAN PENDAHULUAN
1 Pemasangan Bouwplank M1 96.00 120,000.00 11,520,000.00
2 LandClearing & Pembentukan Lahan Ls 1.00 17,500,000.00 17,500,000.00
3 Mobilisasi/Demobilisasi Ls 1.00 3,000,000.00 3,000,000.00
4 K3 dan Keselamatan Kerja Ls 1.00 6,000,000.00 6,000,000.00
5 Listrik Dan Air Kerja Ls 1.00 3,000,000.00 3,000,000.00
SUB TOTAL 41,020,000.00
II PEKERJAAN TANAH
1 Galian Tanah Biasa M3 98.00 86,750.00 8,501,500.00
2 Urugan Tanah M3 26.00 103,750.00 2,697,500.00
3 Urugan Pasir Bawah Lantai M3 52.00 178,700.00 9,292,400.00
SUB TOTAL 20,491,400.00
III PEKERJAAN PONDASI PAS. BATU GUNUNG
1 Pas. Batu Kosong M3 28.00 520,170.00 14,564,760.00
2 Pas. Batu Gunung camp. 1pc : 4 ps M3 112.00 882,075.00 98,792,400.00
SUB TOTAL 113,357,160.00
IV PEKERJAAN STRUKTUR BETON
1 Pemancangan Tiang Pancang Beton 20 x 20cm M1 2,016.00 199,200.00 401,587,200.00
2 Foot Plat Beton M3 27.30 7,178,610.00 195,976,053.00
3 Sloof Beton 20/35 cm M3 22.40 6,659,660.00 149,176,384.00
4 Kolom Beton 35/35 cm Lt. I,II,III M3 64.68 9,898,060.00 640,206,520.80
5 Balok Beton 20/40, 20/35 cm LT II, III M3 51.20 9,898,060.00 506,780,672.00
6 Balok Dak Beton 20/35 cm M3 19.20 9,898,060.00 190,042,752.00
7 Kolom Praktis 12/12 M1 144.00 92,291.00 13,289,904.00
8 Lantai Kerja Camp. 1pc:3ps:5kr M3 26.00 999,400.00 25,984,400.00
SUB TOTAL 2,123,043,885.80
V PEKERJAAN LANTAI DAN DAK BETON
1 Plat Lantai II,III Beton t = 12 cm, Beton Camp. 1pc : 1,5pc : 2,5kr + Tulangan + Bekisting m3 114.05 10,610,810.00 1,210,141,658.88
2 Tangga Beton m3 7.20 10,610,810.00 76,397,832.00
3 Plat Dak Beton t = 10 cm, Beton Camp. 1pc : 1,5pc : 2,5kr + Baja Tulangan + Bekisting m3 46.08 10,610,810.00 488,946,124.80
SUB TOTAL 1,775,485,615.68
VI PEKERJAAN PASANGAN DINDING LT I,II,III
1 Pas. Dinding Batu Bata, 1/2 Bata camp. 1pc : 2ps M2 1,120.00 165,625.00 185,500,000.00
2 Pas. Dinding Batu Bata, 1/2 Bata camp. 1pc : 4ps M2 126.00 145,075.00 18,279,450.00
3 Plesteran Dinding camp. 1pc : 2ps M2 2,240.00 79,763.60 178,670,464.00
4 Plesteran Dinding dan Kolom camp. 1pc : 4ps M2 252.00 75,186.00 18,946,872.00
5 Acian M2 2,492.00 37,300.00 92,951,600.00
SUB TOTAL 494,348,386.00
VII PEKERJAAN KUSEN PINTU, JENDELA & ASSESORIES
1 Kusen Pintu P1 Unit 18.00 800,000.00 14,400,000.00
2 Kusen Pintu P2 KM/WC Unit 18.00 800,000.00 14,400,000.00
3 Daun Pintu P1 lengkap Unit 18.00 1,800,000.00 32,400,000.00
4 Daun Pintu P2 KM/WC lengkap Unit 18.00 1,200,000.00 21,600,000.00
5 Kusen Jendela Unit 36.00 700,000.00 25,200,000.00
6 Daun Jendela lengkap Unit 36.00 1,200,000.00 43,200,000.00
7 Bouvenlight Unit 144.00 400,000.00 57,600,000.00
8 Pas. Roster M2 19.32 575,000.00 11,109,000.00
SUB TOTAL 219,909,000.00
VIII PEKERJAAN LANTAI I,II,III
1 Cor Beton Camp. 1pc : 2pc : 3kr dalam dan Luar Bangunan M3 26.00 1,239,660.00 32,231,160.00
2 Pasangan Granit Lantai 60/60 cm (Polish) M2 780.00 436,123.14 340,176,051.43
3 Pasangan Keramik Lantai KM/WC 40/40 cm M2 72.00 235,240.00 16,937,280.00
4 Pasangan Keramik Dinding KM/WC 40/40 cm M2 180.00 339,690.00 61,144,200.00
SUB TOTAL 450,488,691.43
IX PEKERJAAN CAT - CATAN
1 Pengecatan Dinding dan Kolom M2 2,492.00 39,170.00 97,611,640.00
2 Pengecatan Balok & Dak M2 520.00 39,170.00 20,368,400.00
3 Pengecatan Cat Minyak M2 220.00 66,925.00 14,723,500.00
SUB TOTAL 132,703,540.00
X PEK. INSTALASI LISTRIK
2 Lampu DownLight + SL 18+ Watt, complete Bh 48.00 250,000.00 12,000,000.00
3 Sakelar Tunggal Bh 27.00 60,000.00 1,620,000.00
4 Sakelar Ganda Bh 18.00 60,000.00 1,080,000.00
5 Stop Kontak Bh 36.00 60,000.00 2,160,000.00
6 Instalasi Titik Lampu (Supreme NYM 3 x 2.5 mm)+asesoris, komplit Ttk 48.00 485,000.00 23,280,000.00
7 Instalasi Titik Stop Kontak (Supreme NYM 3 x 2.5 mm)+asesoris, komplit Ttk 36.00 485,000.00 17,460,000.00
8 MMCB 16 A Bh 1.00 400,000.00 400,000.00
9 Panel Box lengkap Unit 1.00 750,000.00 750,000.00
SUB TOTAL 58,750,000.00
XI PEKERJAAN SANITASI & LAINNYA
1 Pagar Pengaman Teras & Railing Tangga M2 95.20 700,000.00 66,640,000.00
SUB TOTAL 66,640,000.00
DAFTAR ANALISA HARGA SATUAN
1 M³ Urugan Tanah
1.2000 M³ Tanah Urug 60,000.00 72,000.00
0.2500 OH Pekerja Biasa 110,000.00 27,500.00
0.0250 OH Mandor 170,000.00 4,250.00
Jumlah 72,000.00 31,750.00 103,750.00
Total 103,750.00
B PEKERJAAN STRUKTUR
C PEKERJAAN PASANGAN
1 M³ Pasangan Batu Kosong (Aanstamping)
1.2000 M³ Batu Belah 15/20 cm 240,000.00 288,000.00
0.3000 M³ Pasir Pasang 250,000.00 75,000.00
0.7800 OH Pekerja 110,000.00 85,800.00
0.3900 OH Tukang Batu 150,000.00 58,500.00
0.0390 OH Kepala Tukang 160,000.00 6,240.00
0.0390 OH Mandor 170,000.00 6,630.00
Jumlah 363,000.00 157,170.00 520,170.00
Total 520,170.00
1 M³ Pasangan Batu Gunung; Camp. 1 pc : 4 ps
1.2000 M³ Batu Belah 15/20 cm 240,000.00 288,000.00
163.00 Kg Portland Cement 1,400.00 228,200.00
0.5200 M³ Pasir Pasang 250,000.00 130,000.00
1.1500 OH Pekerja 110,000.00 126,500.00
0.6000 OH Tukang Batu 150,000.00 90,000.00
0.0600 OH Kepala Tukang 160,000.00 9,600.00
0.0575 OH Mandor 170,000.00 9,775.00
Jumlah 646,200.00 235,875.00 882,075.00
Total 882,075.00
1 M² Acian Semen
3.7500 Kg Semen 1,400.00 5,250.00
0.1000 OH Tukang Batu 150,000.00 15,000.00
0.0100 OH Kepala Tukang Batu 160,000.00 1,600.00
0.1250 OH Pekerja Biasa 110,000.00 13,750.00
0.0100 OH Mandor 170,000.00 1,700.00
Jumlah 5,250.00 32,050.00 37,300.00
Total 37,300.00
D PEKERJAAN CAT-CATAN
1 M² Mengecat Tembok Baru ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup). ( SNI Rev.2002)
0.1500 Kg Cat Dasar 70,000.00 10,500.00
0.2000 Kg Cat Penutup 2 x setara Jotun Weathershie 90,000.00 18,000.00
0.0500 OH Tukang Cat 150,000.00 7,500.00
0.0050 OH Kepala Tukang Cat 160,000.00 800.00
0.0200 OH Pekerja Biasa 110,000.00 2,200.00
0.0010 OH Mandor 170,000.00 170.00
Jumlah 28,500.00 10,670.00 39,170.00
Total 39,170.00
HARGA UPAH
No. PEKERJA SAT
(Rp)
1 2 3 4
1 Pekerja Biasa Hari 110,000.00
2 Mandor Hari 170,000.00
3 Tukang Kayu Hari 150,000.00
4 Kepala Tukang Kayu Hari 160,000.00
5 Tukang Batu Hari 150,000.00
6 Kepala Tukang Batu Hari 160,000.00
7 Tukang Besi Hari 150,000.00
8 Kepala Tukang Besi Hari 160,000.00
9 Tukang Cat Hari 150,000.00
10 Kepala Tukang Cat Hari 160,000.00
11 Tukang Listrik Hari 150,000.00
12 Kepala Tukang Listrik Hari 160,000.00
DAFTAR SATUAN BAHAN BANGUNAN
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SATUAN KETERANGAN
( Rp)
1 2 3 4 5
BAHAN
1 Batu Gunung M3 240,000.00
2 Koral Beton/Cor M3 400,000.00
3 Pasir Pasangan Ex. Sambera M3 250,000.00
4 Pasir Beton/Cor (ex. palu) M3 390,000.00
5 Pasir Urug (lokal) M3 120,000.00
6 Tanah Urug/Timbunan M3 60,000.00
7 Bata Merah Bh 1,200.00
8 Semen PC 50 Kg Kg 1,400.00
9 Semen warna kg 3,000.00
10 Plywood 4 mm Lbr 60,000.00
11 Plywood 9 mm Lbr 125,000.00
12 Plywood 12 mm Lbr 185,000.00
13 Besi Beton Polos Kg 14,000.00
14 Besi Beton Ulir Kg 14,000.00
15 Kawat Beton (Bendrat) Kg 20,000.00
16 Granit 60 x 60 cm (polish) M2 267,857.14
17 Granit 60 x 60 cm (unpolish) M2 267,857.14
18 Keramik 40/40 cm (polished) M2 135,000.00
19 Keramik 40/40 cm (unpolish) M2 150,000.00
20 Kloset Jongkok (Toto) Bh 1,400,000.00 Terpasang
21 Bak Cuci piring Stanless Stell Bh 700,000.00
22 Floor Drain Bh 100,000.00
23 Kran Air Bh 175,000.00
24 Asesories Bh 100,000.00
25 Seal Tape Bh 10,000.00
26 Paku Kayu 0.5"-1.5"/1-2.5 cm Kg 20,000.00
27 Paku Kayu 2"-6"/5-7 cm Kg 20,000.00
28 Paku Beton Kg 25,000.00
29 Paku Ulin Kg 25,000.00
30 Paku Plywood Kg 20,000.00
31 Paku 12 cm Kg 20,000.00
32 Paku 10 cm Kg 20,000.00
33 Beton Pile 20 x 20 cm M1 150,000.00
34 Balok Meranti M3 3,000,000.00
35 Papan Meranti M3 3,200,000.00
36 Papan/Kayu Bouwplank M3 2,500,000.00
37 Papan Bekisting M3 2,650,000.00
38 Kayu Bekisting M3 2,500,000.00
39 Kayu Terentang (meranti) M3 2,750,000.00
40 Dolken Kayu Galam Btg 9,000.00
41 Cat Dasar/Alkali Tembok Kg 70,000.00
42 Cat Minyak setara alftlak Kg 135,000.00
43 Cat Tembok Kg 90,000.00
44 Minyak Bekisting Ltr 10,000.00
ALAT
1 Mesin Pancang Jam 200,000.00
2 Concrete Mixer Jam 50,000.00
JADWAL PELAKSANAAN PEKERJAAN
Pekerjaan : Perencanaan Pembangunan Mesjid dan Kantor Pesantren Hidayatullah
Lokasi : Bontang Lestari - Kota Bontang
Tahun : 2021
Bobot 1 2 3 4 5 6 7 8 9 10 11 12
No. Uraian Pekerjaan KET (%)
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
100%
I PEKERJAAN PENDAHULUAN 0.75 0.19 0.19 0.19 0.19
II PEKERJAAN TANAH 0.37 0.06 0.06 0.06 0.06 0.06 0.06
III PEKERJAAN PONDASI PAS. BATU GUNUNG 2.06 0.34 0.34 0.34 0.34 0.34 0.34
IV PEKERJAAN STRUKTUR BETON 38.63 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41
V PEKERJAAN LANTAI DAN DAK BETON 32.30 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69 2.69
50%
VI PEKERJAAN PASANGAN DINDING LT I,II,III 8.99 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
VII PEKERJAAN KUSEN PINTU, JENDELA & ASSESORIES 4.00 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33
VIII PEKERJAAN LANTAI I,II,III 8.20 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68 0.68
IX PEKERJAAN CAT - CATAN 2.41 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
X PEK. INSTALASI LISTRIK 1.07 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
XI PEKERJAAN SANITASI & LAINNYA 1.21 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
0%
Jumlah Bobot Pekerjaan ( % ) 100.00
Kemajuan Mingguan (%) 0.2 0.2 0.4 0.4 0.4 0.4 0.3 0.3 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.7 2.7 2.7 3.4 3.7 3.7 3.7 3.7 3.7 3.7 3.7 3.7 4.2 4.2 4.2 3.6 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 0.3 0.3 0.5 0.4 Waktu
Komulatif Kemajuan (%) 0 0.2 0.5 0.9 1.3 1.7 2.1 2.5 2.8 5.2 7.6 10.1 12.5 14.9 17.3 19.7 22.1 24.5 27.0 29.4 31.8 34.5 37.3 40.0 43.5 47.2 50.9 54.6 58.3 62.0 65.7 69.4 73.1 77.3 81.5 85.8 89.4 90.5 91.7 92.8 94.0 95.1 96.2 97.4 98.5 98.8 99.1 99.6 100 Pelaksanaan
Realisasi Mingguan (%) 360 Hari
Komulatif Realisasi (%) 0 Kalender
Deviasi (+/-) (%)
Di Buat Oleh :
Konsultan Perencana