REKAPITULASI

PEKERJAAN : Pembangunan Caffetaria


LOKASI : Purworejo, Jawa Tengah
TAHUN ANGGARAN : 2020
HARGA SATUAN (Rp.) JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp.)
I PEKERJAAN PERSIAPAN 7,645,820.00
II PEKERJAAN TANAH DAN PASIR 13,211,362.05
III PEKERJAAN PASANGAN DAN PLESTERAN 82,483,204.77
Lantai satu rumah : 67,137,798.44
Lantai atap rumah : 15,345,406.33
IV PEKERJAAN STRUKTUR / BETON 114,740,850.15
Lantai satu rumah : 82,005,146.84
Lantai atap rumah : 32,735,703.31
V PEKERJAAN RANGKA DAN PENUTUP ATAP 33,363,873.68
VI PEKERJAAN PINTU DAN JENDELA 34,416,678.88
VII RENCANA LANTAI DAN PLAFON 51,855,476.25
VIII PEKERJAAN SANITAIR 24,792,000.00
IX PEKERJAAN FINISHING 25,246,227.08
Lantai satu rumah : 18,159,682.33
Lantai atap rumah : 7,086,544.75
X PEKERJAAN MEKANIKAL 11,347,750.50
Pekerjaan Sistem Suplai Air Bersih 5,896,888.83
Pekerjaan Sistem Air Limbah 5,450,861.67
XI PEKERJAAN ELEKTRIKAL 5,126,000.00
Pekerjaan Instalasi Penerangan 5,126,000.00
TOTAL : 404,229,243.35
DIBULATKAN :
TERBILANG :

Purworejo, Desember 2020


Penyedia jasa,
PT. ACELINE ADHINATHA

DIBUAT

Indra Gunawan, S.T,


Team Leader
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : Pembangunan Caffetaria


LOKASI : Purworejo, Jawa Tengah
TAHUN ANGGARAN : 2020

Kode Analisa Harga Satuan Sub Jumlah Total


No. URAIAN PEKERJAAN Volume Sat.
Harga Satuan (Rp.) (Rp.) (Rp.)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank 52.00 m' A.2.2.1.04. 124,535.00 6,475,820.00
2 Pembersihan Lokasi 120.00 m³ A. 2.2.1.09. 9,750.00 1,170,000.00
7,645,820.00
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah utk pondasi footplat 15.46 m³ A.2.3.1.02. 53,325.00 824,191.20
2 Galian tanah utk pondasi batu kali 34.06 m³ A.2.3.1.01. 43,375.00 1,477,309.13
3 Urugan tanah kembali bekas galian 23.23 m³ A.2.3.1.09. 15,904.17 369,493.55
4 Urugan tanah bawah lantai 71.52 m³ A.2.3.1.14. 136,262.50 9,745,017.08
5 Urugan pasir bawah pondasi 2.95 m³ A.2.3.1.11. 269,885.00 795,351.10
13,211,362.05
III PEKERJAAN PASANGAN dan PLESTERAN
Lantai satu :
1 Pas. Pondasi Batu belah 1 pc : 6psr 12.44 m³ A.3.2.1.04. 623,670.00 7,760,013.98
2 Pas. Pondasi Batu kosong/anstamping 6.64 m³ A.3.2.1.09. 388,860.00 2,580,474.96
3 Pas. Dinding bata merah spesi camp. 1pc:3psr 64.24 m² A.4.4.1.08 99,044.60 6,362,823.19
4 Pas. Dinding bata merah spesi camp. 1pc:5psr 185.62 m² A.4.4.1.10 95,029.40 17,639,357.23
5 Plesteran dinding spesi 1pc:3psr 128.48 m² A.4.4.2.03. 43,528.08 5,592,661.83
6 Plesteran dinding spesi 1pc:5psr 371.24 m² A.4.4.2.05. 41,358.72 15,354,011.21
7 Acian 499.72 m² A.4.4.2.27. 23,710.00 11,848,456.04
67,137,798.44
lantai atap :
1 Pas. Dinding bata merah spesi camp. 1pc:3psr 63.66 m² A.4.4.1.08 99,044.60 6,305,179.24
2 Plesteran dinding spesi 1pc:3psr 134.45 m² A.4.4.2.03. 43,528.08 5,852,393.88
3 Acian 134.45 m² A.4.4.2.27. 23,710.00 3,187,833.21
15,345,406.33
IV PEKERJAAN STRUKTUR / BETON
lantai satu :
1 Beton lantai kerja bawah footplat (Camp 1:3:5) mutu K100 0.64 m³ A.4.1.1.04 657,529.95 423,449.29
2 Beton lantai kerja bawah lantai (Camp 1:3:5) mutu K100 11.68 m³ A.4.1.1.04 657,529.95 7,680,081.29
3 Footplat type : FP1
• Beton 2.63 m³ A.4.1.1.07. 835,681.03 2,199,512.48
• Besi penulangan 291.51 kg A.4.1.1.17 9,636.00 2,809,003.46
• Bekisting pondasi 15.04 m² A.4.1.1.20 83,885.00 1,261,630.40
4 Footplat type : FP2
• Beton 1.33 m³ A.4.1.1.07. 835,681.03 1,113,127.13
• Besi penulangan 147.95 kg A.4.1.1.17 9,636.00 1,425,659.30
• Bekisting pondasi 8.64 m² A.4.1.1.20 83,885.00 724,766.40
5 Sloof 20/30
• Beton 4.67 m³ A.4.1.1.07. 835,681.03 3,898,452.01
• Besi penulangan 527.92 kg A.4.1.1.17 9,636.00 5,087,011.81
• Bekisting Sloof 50.29 m² A.4.1.1.21 87,322.50 4,391,448.53
6 Sloof 15/30
• Beton 0.46 m³ A.4.1.1.07. 835,681.03 386,836.75
• Besi penulangan 81.91 kg A.4.1.1.17 9,636.00 789,310.58
• Bekisting Sloof 6.17 m² A.4.1.1.21 87,322.50 538,954.47
7 Kolom 20/20
• Beton 1.66 m³ A.4.1.1.07. 835,681.03 1,387,899.06
• Besi penulangan 338.22 kg A.4.1.1.17 9,636.00 3,259,049.07
• Bekisting kolom 116.26 m² A.4.1.1.22 144,473.75 16,795,940.28
8 Kolom 15/20
• Beton 0.12 m³ A.4.1.1.07. 835,681.03 101,785.95
• Besi penulangan 33.62 kg A.4.1.1.17 9,636.00 324,005.16
• Bekisting kolom 2.84 m² A.4.1.1.22 144,473.75 410,594.40
10 Balok (B1) 15/40
• Beton 1.39 m³ A.4.1.1.07. 835,681.03 1,163,268.00
• Besi penulangan 305.55 kg A.4.1.1.17 9,636.00 2,944,315.74
• Bekisting balok 22.04 m² A.4.1.1.23 144,473.75 3,184,201.45
11 Balok (B2) 15/20
• Beton 2.66 m³ A.4.1.1.07. 835,681.03 2,223,747.23
• Besi penulangan 333.15 kg A.4.1.1.17 9,636.00 3,210,232.19
• Bekisting balok 38.07 m² A.4.1.1.23 144,473.75 5,499,971.19
13 Balok (BK 1)
• Beton 1.32 m³ A.4.1.1.07. 835,681.03 1,102,597.55
• Besi penulangan 244.61 kg A.4.1.1.17 9,636.00 2,357,057.33
• Bekisting balok 26.39 m² A.4.1.1.23 144,473.75 3,812,373.32
14 Balok (BK 2)
• Beton 0.15 m³ A.4.1.1.07. 835,681.03 126,956.66
• Besi penulangan 85.43 kg A.4.1.1.17 9,636.00 823,197.06
Kode Analisa Harga Satuan Sub Jumlah Total
No. URAIAN PEKERJAAN Volume Sat.
Harga Satuan (Rp.) (Rp.) (Rp.)
• Bekisting balok 3.80 m² A.4.1.1.23 144,473.75 548,711.30
82,005,146.84
lantai atap : `
1 Plat lantai
• Beton 8.53 m³ A.4.1.1.07. 835,681.03 7,128,192.06
• Besi penulangan/Wermes 852.62 kg A.4.1.1.17 9,636.00 8,215,816.45
• Bekisting 100.19 m² A.4.1.1.24 144,473.75 14,474,825.01
2 Kolom 15/15
• Beton 0.28 m³ A.4.1.1.07. 835,681.03 235,862.61
• Besi penulangan 137.17 kg A.4.1.1.17 9,636.00 1,321,798.13
• Bekisting kolom 9.41 m² A.4.1.1.22 144,473.75 1,359,209.04
32,735,703.31
V PEKERJAAN RANGKA DAN PENUTUP ATAP
1 Kuda - Kuda Baja Ringan Profil C.75 Tebal 0,75 109.76 m² 120,000.00 13,170,600.00
2 Pas. Atap Genteng Metal 109.76 m² A.4.5.2.2. 183,985.00 20,193,273.68
33,363,873.68
VI PEKERJAAN PINTU DAN JENDELA
1 TYPE PJ1 2 unit 4,635,861.18 9,271,722.35
• Kusen Alumunium A.4.2.1.11
• Frame daun pintu alumunium warna hitam A.4.2.1.13.
• Kaca bening 5mm Ex. Asahimas A.4.6.2.17
• Karet
• Hardware pintu :
• door closer
• Pull handle FINO P.45.07FB (45cm) US32
• Lockcase swing AL FINO FB8535-30 US32D
• Double Cylinder FINO DC.FB1001-60 US14
• Hinges FINO SEL FB08 4x3x3 4BB US32D

2 TYPE P1 2 unit 2,891,889.40 5,783,778.81


• Kusen Alumunium A.4.2.1.11
• Frame daun pintu alumunium warna hitam A.4.2.1.13.
• Frame daun jendela alumunium warna hitam A.4.2.1.13.
• Teakwood tebal 3mm rangkap
• Finishing teakwood polituran A.4.7.1.7.
• Kaca bening 5mm Ex. Asahimas A.4.6.2.17
• Karet
• Hardware pintu :
• Lever handle FINO HREO.85.01FB US32D
• Lockcase swing AL FINO FB8535-30 US32D
• Double Cylinder FINO DC.FB1001-60 US14
• Hinges FINO SEL FB08 4x3x3 4BB US32D

3 TYPE P2 1 unit 1,984,744.37 1,984,744.37


• Kusen Alumunium A.4.2.1.11
• Frame daun pintu alumunium warna hitam A.4.2.1.13.
• Teakwood tebal 3mm rangkap
• Finishing teakwood polituran A.4.7.1.7.
• Hardware pintu :
• Lever handle FINO HREO.85.01FB US32D
• Lockcase swing AL FINO FB8535-30 US32D
• Double Cylinder FINO DC.FB1001-60 US14
• Hinges FINO SEL FB08 4x3x3 4BB US32D

4 TYPE P3 3 unit 1,475,000.00 4,425,000.00


• Pintu UPVC 1 Set A.4.2.1.11
Kode Analisa Harga Satuan Sub Jumlah Total
No. URAIAN PEKERJAAN Volume Sat.
Harga Satuan (Rp.) (Rp.) (Rp.)
5 TYPE P4 1 unit 1,906,798.36 1,906,798.36
• Kusen Alumunium Warna Hitam A.4.2.1.11
• Frame daun pintu alumunium warna hitam A.4.2.1.13.
• Kaca bening 5mm Ex. Asahimas A.4.6.2.17
• Karet
• Hardware pintu :
• Lever handle FINO HREO.85.01FB US32D
• Lockcase swing AL FINO FB8535-30 US32D
• Double Cylinder FINO DC.FB1001-60 US14
• Hinges FINO SEL FB08 4x3x3 4BB US32D

6 TYPE J1 4 unit 2,515,091.18 10,060,364.72


• Kusen Alumunium Warna Hitam A.4.2.1.11
• Kaca bening 5mm Ex. Asahimas A.4.6.2.17
• Karet

7 J BV 1 unit 984,270.27 984,270.27


• Kusen Alumunium Warna Hitam A.4.2.1.11
• Kaca bening 5mm Ex. Asahimas A.4.6.2.17
• Karet
34,416,678.88
VII RENCANA LANTAI DAN PLAFON
lantai satu :
1 Pas. Keramik 40X40 130.01 m² A.4.4.3.36. 158,507.00 20,607,495.07
2 Pas. Keramik 30x30 Lavatory 14.22 m² A.4.4.3.35. 147,684.00 2,100,066.48
3 Pas. Dinding keramik 30x60 Lavatory 11.52 m² A.4.4.3.53. 215,487.89 2,482,420.48
4 Pas. Plint keramik 10x40 88.75 m' A.4.4.3.40. 36,336.20 3,224,910.42
5 Plafond Gypsum tebal 9
A.4.5.1.07 +
mm + rangka hollow 141.92 m² 149,505.00 21,217,749.60
A.4.2.1.21.
galvalum
6 List gypsum 8 cm 96.94 m' A.4.5.1.09. 22,930.00 2,222,834.20
51,855,476.25
VIII PEKERJAAN SANITAIR
lantai satu :
1 Kloset jongkok 2.00 unit 275,000.00 550,000.00
2 Meja pantry beton lapis keramik 6.90 m' 2,650,000.00 18,285,000.00
3 Kitchen sink stainless type SB 45 ex. Royal 2.00 bh 316,000.00 632,000.00
4 Kran dapur ø ½" type TX 603 KM ex. TOTO 4.00 bh 560,000.00 2,240,000.00
5 Floor Drain type TX 1 BN ex. TOTO 2.00 bh 390,000.00 780,000.00
6 Kran ø ½" type T30ARQ13N ex. TOTO 3.00 bh 475,000.00 1,425,000.00
7 Wastafel 1.00 bh 880,000.00 880,000.00
24,792,000.00

IX PEKERJAAN FINISHING
lantai satu :
1 Cat dinding eksterior weathershield 185.29 m² A.4.7.1.10.a 35,625.50 6,601,048.90
2 Cat dinding interior satin 446.74 m² A.4.7.1.10.c 19,635.50 8,771,963.27
3 Cat plafond/langit-langit satin 141.92 m² A.4.7.1.10.c 19,635.50 2,786,670.16
18,159,682.33
lantai atap :
1 Cat dinding eksterior weathershield 70.79 m² A.4.7.1.10.a 35,625.50 2,521,964.77
2 Water Proofing Dag Atap 109.16 m² A.4.7.1.10.b 41,815.50 4,564,579.98
7,086,544.75

Purworejo, Desember 2020


Penyedia jasa,
PT. ACELINE ADHINATHA

DIBUAT

Indra Gunawan, S.T,


Team Leader
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : Pembangunan Caffetaria


LOKASI : Purworejo, Jawa Tengah
TAHUN ANGGARAN : 2020

Kode Harga Satuan Sub Jumlah Total


No. URAIAN PEKERJAAN Volume Sat.
analisa (Rp.) (Rp.) (Rp.)
A PEKERJAAN SISTEM SUPLAI AIR BERSIH
Pengadaan dan pemasangan peralatan utama sistem suplai Air Bersih, lengkap
terpasang dengan asesoris yang diperlukan sesuai dengan gambar perencanaan
dan spesifikasi teknis.
PERALATAN UTAMA
1 Rooftank stainless steel kap. 500 liter. 1.00 unit 4,800,000.00 4,800,000.00
Pemipaan area rooftank
1 Pipa Pipa PVC AW dia. 1,5" 4.00 m' PL.1-5 28,011.50 112,046.00
2 Pipa PVC AW dia. 2" 4.00 m' PL.1-6 34,547.33 138,189.33
3 Gate valve dia. 2" 1.00 bh PL.6-6 405,000.00 405,000.00
SUPLAI AIR BERSIH
Pengadaan dan pemasangan sistem perpipaan Air Bersih Dingin, pemipaan
dengan bahan pipa PVC AW , lengkap terpasang dengan asesoris yang
diperlukan sesuai dengan gambar perencanaan dan spesifikasi teknis.
PIPA DISTRIBUSI AIR BERSIH
1 Pipa PVC AW Ø 0.5" 20.00 m' PL.1-1 13,417.25 268,345.00
2 Pipa PVC AW Ø 1" 6.00 m' PL.1-3 19,384.75 116,308.50
3 elbow 20mm 9.00 bh 3,000.00 27,000.00
4 tee 20mm 5.00 bh 6,000.00 30,000.00
5,896,888.83
B PEKERJAAN SISTEM AIR LIMBAH
Pengadaan dan pemasangan pipa Air Bekas, dan Air Kotor, bahan pipa PVC
AW , lengkap terpasang dengan asesoris yang diperlukan sesuai dengan
gambar perencanaan dan spesifikasi teknis.
UNIT PENAMPUNGAN & POMPA
1 Bak kontrol air bekas 3.00 unit 155,000.00 465,000.00
PIPA DISTRIBUSI AIR BEKAS & KOTOR
1 PVC AW Air Bekas dia.75mm " 20.00 m' PL.1-7 57,457.58 1,149,151.67
2 PVC AW Air Kotor dia.100" 8.00 m' PL.1-8 91,421.00 731,368.00
3 PVC AW Vent dia. 65mm" 4.00 m' PL.1-3 41,651.50 166,606.00
4 Large radius elbow 100'' 1.00 bh 45,000.00 45,000.00
5 Elbow Ø100'' 2.00 bh 26,000.00 52,000.00
6 Elbow Ø75mm'' 6.00 bh 15,000.00 90,000.00
7 Bend 45° 4'' 1.00 bh 15,000.00 15,000.00
8 Ty 4'' 1.00 bh 55,000.00 55,000.00
9 Tee 3'' 5.00 bh 23,000.00 115,000.00
2,884,125.67
C PEKERJAAN DRAINASE DAN AIR HUJAN
Pengadaan dan pemasangan sistem drainase air hujan, lengkap terpasang
dengan asesoris yang diperlukan sesuai dengan gambar perencanaan dan
spesifikasi teknis.
1 Pipa drainase air hujan vertical , PVC AW dia. 4" 16.00 m' PL.1-8 91,421.00 1,462,736.00
2 Roofdrain (cast iron tipe meshroom) dia. 4" 4.00 bh 250,000.00 1,000,000.00
3 Elbow Ø100'' 4.00 bh 26,000.00 104,000.00
2,566,736.00
TOTAL PEKERJAAN MEKANIKAL 11,347,750.50

Purworejo, Desember 2020


Penyedia jasa,
PT. ACELINE ADHINATHA

DIBUAT

Indra Gunawan, S.T,


Team Leader
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : Pembangunan Caffetaria


LOKASI : Purworejo, Jawa Tengah
TAHUN ANGGARAN : 2020

Kode Harga Satuan Sub Jumlah Total


No. URAIAN PEKERJAAN Volume Sat.
Analisa (Rp.) (Rp.) (Rp.)
PEKERJAAN INSTALASI PENERANGAN
Pengadaan dan pemasangan instalasi Penerangan,
lengkap terpasang dengan saklar, alat bantu dan
asesoris lain yang diperlukan sesuai gambar dan
spesifikasi&teknis.
FIXTURE INSTALASI
LED Bulb 11W 6500K/CDL, E-27
1 9.00 unit A.EL.3. 4 40,000.00 360,000.00
Instalasi penerangan, menggunakan kabel NYM
9.00 titik 220,000.00 1,980,000.00
3x2,5mm² dalam pipa conduit Ø 20mm.
Instalasi stop kontak dinding, menggunakan kabel NYM
7 7.00 titik A.EL.3. 48 250,000.00 1,750,000.00
3x2,5mm² dalam pipa conduit Ø 20mm.
Instalasi stop kontak AC, menggunakan kabel NYM
8 1.00 titik A.EL.3. 49 500,000.00 500,000.00
3x2,5mm² dalam pipa conduit Ø 20mm.
7 Saklar tunggal inbow 5.00 unit A.EL.3. 29 23,000.00 115,000.00
8 Saklar ganda inbow 2.00 unit A.EL.3. 30 25,000.00 50,000.00
9 Normal Stop Kontak 250VA 3.00 unit A.EL.3. 42 62,000.00 186,000.00
10 Normal Stop Kontak 2x250 VA 4.00 unit A.EL.3. 39 30,000.00 120,000.00
11 Normal Stop Kontak AC 1.00 unit A.EL.3. 40 65,000.00 65,000.00

5,126,000.00
TOTAL PEKERJAAN ELEKTRIKAL 5,126,000.00

Purworejo, Desember 2020


Penyedia jasa,
PT. ACELINE ADHINATHA

DIBUAT

Indra Gunawan, S.T,


Team Leader