Anda di halaman 1dari 146

DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG
EDISI V 2018
HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 75,000 85,000

2 Pekerja tak terlatih Hr 50,000 55,000


3 Mandor Hr 100,000 110,000

4 Buruh Semi Terlatih Hr 50,000 60,000

5 T u k a n g l i s t r i k / Buruh Terlatih Hr 95,000 105,000

6 Tukang kayu Hr 95,000 105,000

7 Kep. tk. kayu Hr 110,000 120,000

8 Tukang batu Hr 95,000 105,000

9 Kep. tk. batu Hr 110,000 120,000

10 T u k a n g b e s i Hr 95,000 105,000

11 K e p . t k . b e s i Hr 110,000 120,000

12 T u k a n g c a t Hr 95,000 105,000

13 K e p . t k . c a t Hr 110,000 120,000

14 T u k a n g p l i t u r Hr 95,000 105,000

15 T u k a n g j a l a n Hr 75,000 85,000

16 T u k a n g g a l i Hr 75,000 85,000

17 Tukang masak aspal Hr 75,000 85,000

18 T k . l e i d e n g Hr 95,000 105,000

19 M a s i n i s / Operator Hr 150,000 175,000

20 P e m b . M a s i n i s Hr 100,000 125,000

21 P e n j a g a a p i Hr 75,000 85,000

22 P e n j a g a m a l a m Hr 75,000 85,000

23 Sopir Hr 140,000 150,000

24 Pembantu Sopir Hr 85,000 100,000

25 Juru Ukur Hr 150,000 175,000

26 Pembantu Juru Ukur Hr 110,000 125,000

415837801.xls 146 dup


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG
EDISI V 2018
HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000 250,000
Bulat Belah m3 260,000 335,000
Pecah 10/15 m3 260,000 300,000
Pecah 5/7 m3 300,000 350,000
Pecah 3/5 m3 330,000 360,000
2 KERIKIL Timbun m3 180,000 180,000
Sawur / Koral m3 170,000 190,000
Beton 0,5/1 m3 300,000 370,000
Beton ,1/2 m3 300,000 400,000
Beton ,2/3 m3 310,000 390,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 330,000
3 BATU BATA ex lokal bh 600 650

4 PASIR Urug m3 160,000 230,000


Pasang m3 315,000 370,000
Beton m3 350,000 380,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT

Merk I 40 kg zak 44,000 46,000


Merk I 50 kg zak 55,000 56,500
Merk II 40 kg zak 44,500 45,750
Merk II 50 kg zak 54,000 56,000
Semen Putih 40 kg zak 80,000 89,000
Semen Putih 50 kg zak 90,000 95,000
Semen warna kg 11,000 15,000

415837801.xls 146/2 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000 190,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000 7,000


Genteng Beton Warna Special bh 9,500 10,500
Genteng Beton Warna Khusus bh 14,000 15,200
Kerpus Beton Warna Standard bh 10,000 10,050
Kerpus Beton Warna Special bh 11,500 12,000
Kerpus Beton Warna Khusus bh 13,000 13,500
3 GENTENG TANAH LIAT

Vlaam bh 2,300 2,600


Kodok bh 2,500 3,100
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 ASBES GELOMBANG BESAR

. 200 cm X 102 cm X 5 mm bh 85,000 115,000


. 250 cm X 102 cm X 5 mm bh 98,000 125,000
. 225 cm X 102 cm X 5 mm bh 108,000 135,000
. 200 cm X 102 cm X 6 mm bh 120,000 145,000
. 225 cm X 102 cm X 6 mm bh 130,000 155,000
. 250 cm X 102 cm X 6 mm bh 140,000 160,000
Asbes Gelombang Kecil

. 150 cm X 105 cm X 4 mm bh 42,000 47,000


. 180 cm X 105 cm X 4 mm bh 50,000 55,000
. 210 cm X 105 cm X 4 mm bh 59,500 63,000
. 240 cm X 105 cm X 4 mm bh 65,000 72,000
. 270 cm X 105 cm X 4 mm bh 75,000 81,000
. 300 cm X 105 cm X 4 mm bh 42,000 47,000

415837801.xls 146/3 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

5 NOK Jabes nok

. Kerpus Genteng bh 35,000 40,000


. Stel Besar bh 45,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex

. Stel Besar bh 44,000 48,000


. Patent Besar bh 27,000 30,500
. Plat besar bh 51,000 55,000
6 ASBES PLAT

. 100cm X 100 cm X 3 mm bh 16,000 17,000


. 100cm X 100 cm X 4 mm bh 16,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,500 15,000
. 40 cm X 200 cm X 3 mm bh 14,000 14,500
7 FIBRE GLASS (JABES)

180 X 92 cm bh 55,000 61,000


200 X 92 cm bh 60,000 66,000
250 X 92 cm bh 68,000 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT

BJLS 0,18 lebar 55 cm m' 20,000 24,500


BJLS 0,20 lebar 55 cm m' 22,000 30,000
BJLS 0,28 lebar 55 cm m' 26,000 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG

BJLS 0,18 panjang 180 cm lbr 40,000 45,000


BJLS 0,20 panjang 180 cm lbr 42,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 72,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000 23,000,000
Balok/pesagen m3 20,000,000 20,500,000

2 KAMPER Papan m3 7,200,000 7,800,000


Balok/pesagen m3 6,100,000 7,500,000

415837801.xls 146/4 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

3 KRUING Papan m3 6,250,000 8,800,000


Balok/pesagen m3 5,200,000 6,000,000

4 MERANTI Papan m3 4,800,000 5,700,000


Balok/pesagen m3 4,500,000 5,400,000

5 LANAN Papan m3 3,290,000 3,300,000


Balok/pesagen m3 2,000,000 2,200,000

6 BENGKIRAI Papan m3 8,750,000 10,000,000


Balok/pesagen m3 9,000,000 9,850,000

7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000


Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)

PC polos 30 X 30 cm m2 35,000 38,000


20 X 20 cm m2 34,000 37,000
PC warna 30 X 30 cm m2 40,000 48,000
20 X 20 cm m2 39,500 45,000
Teraso 30 X 30 cm m2 52,000 56,000
2 UBIN PORSELIN

Lokal 11 X 11 putih dos 42,000 43,000


11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
3 MOZAIK PORSELIN

10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000

415837801.xls 146/5 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

4 Keramik 30 X 30 cm m2 56,000 78,000


20 X 20 cm m2 56,000 76,000
33 x 33 cm m2 58,000 78,000
25 x 25 cm m2 55,000 75,000
15 x 20 cm m2 57,000 75,000

V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 32,500 40,000
Ø 20 cm - 100 cm bh 42,000 50,000
Ø 30 cm - 100 cm bh 60,000 80,000
Ø 50 cm - 100 cm bh 115,000 160,000
Ø 60 cm - 100 cm bh 165,000 215,000
Ø 70 cm - 100 cm bh 240,000 265,000
U 10 cm - 100 cm bh 30,000 32,500
U 15 cm - 100 cm bh 35,000 40,000
U 20 cm - 100 cm bh 39,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 65,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,000 10,750
besi beton prestress kg 13,000 14,500
besi beton ulir kg 13,000 13,200

2 BESI PLAT Besi Strip kg 13,500 14,000

3 BESI PROFIL Besi Profil kg 14,000 14,500

4 JARING - JARING BAJA

Diameter 4 - 15 kg 13,500 14,000


Diameter 6 - 15 kg 13,500 14,500
Kawat Bronjong kg 9,500 9,500

415837801.xls 146/6 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

5 BESI SIKU L 40 X 40 X 4 btg 133,500 139,200


L 50 X 50 X 5 btg 215,500 217,500
L 60 X 60 X 6 btg 312,000 355,000

6 KAWAT - Ikat beton/bendrat kg 17,000 18,000


- Harmonika 12 X 45 mm m2 20,000 35,000
- Harmonika 12 X 24 mm m2 18,000 21,000
- Harmonika 14 X 30 mm m2 15,000 20,000
- Harmonika 14 X 35 mm m2 21,000 27,500
- Kawat Nyamuk Nylon m2 18,000 25,000
- Kawat Kasa m2 14,000 18,000
- Saringan pasir m2 18,000 20,000
- Kawat loket m2 17,000 17,500
- Kawat duri rol 110,000 135,000
- Kawat bronjong kg 25,000 27,500

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)

Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 30,000 panjang 4 m


Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 35,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 52,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 56,000 68,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 65,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 125,000 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 180,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 350,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m

415837801.xls 146/7 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

2 Pipa Medium A Galvanis - SII

Pipa Medium Galvanis 0,50" btg 150,000 155,000 panjang 6 m


Pipa Medium Galvanis 0,75" btg 190,000 195,000 panjang 6 m
Pipa Medium Galvanis 1" btg 300,000 305,000 panjang 6 m
Pipa Medium Galvanis 1,25" btg 375,000 380,000 panjang 6 m
Pipa Medium Galvanis 1,50" btg 435,000 440,000 panjang 6 m
Pipa Medium Galvanis 2" btg 585,000 590,000 panjang 6 m
Pipa Medium Galvanis 2,50" btg 735,000 740,000 panjang 6 m
Pipa Medium Galvanis 3" btg 970,000 975,000 panjang 6 m
Pipa Medium Galvanis 4" btg 1,425,000 1,430,000 panjang 6 m
Pipa Medium Galvanis 5" btg 1,900,000 1,905,000 panjang 6 m
Pipa Medium Galvanis 6" btg - - panjang 6 m
VIII . B A H A N L A N G I T - L A N G I T
1 PLY WOOD

Teak wood

90 X 210 X 3 mm lbr 55,000 75,000


. 120 X 240 X 3 mm lbr 75,000 95,000
. 90 X 210 X 4 mm lbr 65,000 80,000
. 90 X 210 X 9 mm lbr 95,000 125,000
- . 90 X 210 X 12 mm lbr 135,000 170,000
- . 90 X 210 X 15 mm lbr 165,000 240,000
. 90 X 210 X 18 mm lbr 200,000 310,000
2 Tripleks

. 120 X 240 X 3 mm lbr 52,000 65,000


. 120 X 240 X 4 mm lbr 60,000 75,000
. 120 X 240 X 6 mm lbr 75,000 86,000
3 Multipleks

. 120 X 240 X 9 mm lbr 121,000 160,000


. 120 X 240 X 12 mm lbr 142,000 185,000
. 120 X 240 X 15 mm lbr 165,000 220,000
. 120 X 240 X 18 mm lbr 210,000 265,000
4 Formika ukuran pintu lbr 68,000 75,000

415837801.xls 146/8 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

IX . B A H A N F I N I S H I N G
1 KAYU

Menie kg 23,000 30,000


Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,500 4,100
Batu Apung kg 38,000 55,000
Cat dasar kg 36,500 40,000
. Emco kg 62,000 68,000
. Yunior 66 (nippon paint) kg 60,000 71,000

. Deculux kg 63,000 75,000


. Siralax ons 15,000 20,000
. Spiritus ltr 13,000 18,000
. Plitur jadi ltr 61,000 65,000

2 TEMBOK

Kalkarium kg 4,500 5,000


Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 26,000
Sintex 5 kg 115,000 125,000
Danabride 5 kg 110,000 122,000
Catylac 5 kg 125,000 130,000
Mowilex 2,5 kg 310,000 420,000

3 BESI

Menie kg 25,000 36,000


Cat mengkilat kg 55,000 69,000
Cat kg 40,000 45,000
Thinner A ltr 15,000 20,000
Minyak cat ltr 10,000 20,000
Thinner Super ltr 17,500 35,000
Residu (teer/aspal) drum 55,000 60,000

415837801.xls 146/9 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

Fibre glass (tanki air)

kapasitas 550 liter. bh 950,000 1,100,000


kapasitas 1100 liter. bh 1,625,000 1,700,000
Lem Aica Aibon kg 55,000 65,000
X.BAHAN KACA
1 POLOS 3 mm m2 75,000 85,000
5 mm m2 90,000 95,000

2 ES KABUR 3 mm m2 75,000 85,000


5 mm m2 88,000 95,000

3 RAY BAND 3 mm m2 75,000 85,000


5 mm m2 85,000 92,000
XI . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 15,000 17,500
2 PAKU - payung kg 20,000 26,000
3 PAKU - sekrup doos 6,000 8,000
4 PAKU - beton bh 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 7,000 7,200

XII . POMPA AIR.


1 POMPA AIR TANGAN

Dragon buatan Indonesia bh 275,000 310,000


2 POMPA AIR LISTRIK

Sanyo 100 watt bh 975,000 1,050,000


Fuji 250 watt bh 1,450,000 1,500,000
Shimizu . 100 watt bh 450,000 510,000
. 90 watt bh 350,000 380,000
Dab . 125 watt bh 350,000 400,000
. 175 watt bh 425,000 450,000

415837801.xls 146/10 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

XIII. L A I N - L A I N
1 KREI 25 MM m2 45,000 50,000
2 Sliding Pintu J4 bh 180,000 235,000
3 Naco per Daun bh 12,000 12,500
4 Rolling door Besi m2 300,000 325,000
Rolling door Almunium m2 230,000 275,000
5 Awning Almunium m2 210,000 225,000
6 Kusen Almunium 4" Putih m' 80,000 85,000
7 WIDE FLANGE BEAM

150 X 75 X 5 X 7 X 12 btg 1,380,000 1,475,000

8 ASPAL.

Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,050,000

Hotmix Tebal = 4 Cm m2 65,000 70,000


Hotmix Tebal = 5 Cm m2 80,000 85,000
Hotmix Tebal = 6 Cm m2 95,000 100,000
Hotmix Tebal = 7 Cm m2 110,000 120,000
Binder Course ton 1,300,000 1,350,000
Wearing Course ton 1,300,000 1,450,000
Hot Roller Sheet ton 1,150,000 1,300,000
Sand Sheet ton 1,100,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,600,000
Cold Mix ton 1,750,000 1,850,000
Prime / Tack Coard RC liter 8,200 8,700
Prime Coat MC liter 8,200 8,700
Prime / Tack Coat Emulsi liter 8,200 8,700
10 K A C A

Cermin 5 mm m2 225,000 275,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 275,000 300,000


Pagar BRC 120 A2 /lb 350,000 375,000

415837801.xls 146/11 dhb


HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)

12 LAIN-LAIN

Minyak Beton & bekisting ltr 9,000 10,000


Pintu Lipat Besi m2 380,000 425,000
Sunscreen Allumunim m2 310,000 350,000
Allumunium Foil m2 7,500 8,000
Soda api kg 12,000 13,000
Sabun kg 11,000 13,000
Air m3 12,500 15,000
Koas Alang-alang ikat 1,250 2,000
Solar (Industri) ltr 7,000 7,200
Premium (Industri) ltr 6,200 6,800
Pelumas ltr 37,500 45,000

415837801.xls 146/12 dhb


HARGA SATUAN PEKERJAAN KONSTRUKSI
BERDASAR PERMEN NO.28/PRT/M/2016 BIDANG SUMBER DAYA AIR
SUMBER DATA : PASARAN BE BAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018

JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
A.1 PEKERJAAN TANAH

PEKERJAAN TANAH SECARA MANUAL DAN SEMI MEKANIS


A.1.1
(NORMATIF)

AHSP PEMBERSIHAN & PENGUPASAN PERMUKAAN TANAH

1 T.01.a 1 m2 PEMBERSIHAN DAN STRIPING / KOSREKAN 5,610.00 6,336.00

m2 TEBAS TEBANG BERUPA MEMOTONG & MEMBERSIHKAN LOKASI DARI


2 T.01.b 1 7,128.00 8,041.00
TANAMAN / TUMBUHAN Ø < 15 CM

CABUT TUNGGUL POHON TANAMAN KERAS Ø > 15 CM & MEMBUANG


3 T.01.c 1 bh 22,000.00 24,970.00
SISA TUNGGUL KAYU & AKAR-AKARNYA

T.02 AHSP UITZET TRASE SALURAN DAN PASANG PROFIL MELINTANG

4 T.02.a 1 m' UITZET TRASE SALURAN 2,750.00 3,146.00

PASANG 1 M' PROFIL MELINTANG GALIAN TANAH SALURAN DAN


T.02.b
PASANG BOUWPLANK

5 T.02.b.1 1 m' PASANG PROFIL MELINTANG GALIAN TANAH 26,015.00 30,360.00

6 T.02.b.2 1 m' PASANG BOUWPLANK 113,245.00 134,530.00

T.03 PENGADAAN DAN PEMASANGAN PATOK

7 T.03.a 1 m' PATOK KAYU (UKURAN 5/7) 12,892.00 15,287.25

8 T.03.b 1 bh PATOK TETAP BANTU (PBT) 93,196.61 104,018.20

9 T.03.c 1 bh PATOK UTAMA TETAP 161,493.41 180,742.31

T.06 GALIAN TANAH BIASA

T.06.a CARA MANUAL

10 T.06.a.1 1 m3 GALIAN TANAH BIASA sedalam ≤ 1 m 52,640.50 59,452.80

11 T.06.a.2 1 m3 GALIAN TANAH BIASA sedalam > 1m s/d 2 m 63,112.50 71,280.00

12 T.06.a.3 1 m3 GALIAN TANAH BIASA sedalam > 2 m s/d 3 m 71,060.00 80,256.00

GALIAN TANAH BIASA dg kedalaman > 3 m,


13 T.06.a.4 1 m3 7,012.50 7,920.00
TAMBAHAN KOEFISIEN UNT SETIAP PENAMBAHAN KEDALAMAN 1 m

T.06.b CARA SEMI MEKANIK

14 T.06.b.1 1 m3 GALIAN TANAH BIASA Sedalam ≤ 1 m 25,520.00 26,174.50

15 T.06.b.2 1 m3 GALIAN TANAH BIASA Sedalam > 1 m sd 2 m 29,260.00 30,398.50

16 T.06.b.3 1 m3 GALIAN TANAH BIASA Sedalam > 2 m sd 3 m 33,000.00 34,622.50

KEDALAMAN YANG > 3 m menggunakan AHSP T.06.b.3 + AHSP T.06.a.4


17 T.06.b.4
untuk setiap kedalaman 1 m

T.07. GALIAN TANAH BERBATU

T.07.a CARA MANUAL

18 T.07.a.1 1 m3 GALIAN TANAH BERBATU Sedalam ≤ 1 m 126,318.50 142,665.60

19 T.07.a.2 1 m3 GALIAN TANAH BERBATU Sedalam > 1 m sd 2 m 140,250.00 158,400.00

20 T.10.a 1 m3 GALIAN TANAH BERBATU Sedalam > 2 m sd 3 m 154,275.00 174,240.00

### KEDALAMAN YANG > 3 m menggunakan AHSP T.07.b.3 + AHSP T.07.a.4


21 T.07.b
untuk setiap kedalaman 1 m

415837801.xls 146/13 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
T.07.b CARA SEMI MEKANIK

22 T.07.b.1 1 m3 GALIAN TANAH BERBATU Sedalam ≤ 1 m 52,580.00 60,498.63

23 T.07.b.2 1 m3 GALIAN TANAH BERBATU Sedalam > 1 m sd 2 m 59,125.00 67,890.63

24 T.07.b.3 1 m3 GALIAN TANAH BERBATU Sedalam > 2 m sd 3 m 63,800.00 73,170.63

KEDALAMAN YANG > 3 m menggunakan AHSP T.07.b.3 + AHSP T.07.a.4


25
untuk setiap kedalaman 1 m

T.08. GALIAN BATU

T.08.a CARA MANUAL

26 T.08.a.1 1 m3 GALIAN BATU Sedalam ≤ 1 m 315,843.00 356,716.80

27 T.08.a.2 1 m3 GALIAN BATU Sedalam > 1 m sd 2 m 350,075.00 395,395.00

28 T.08.a.3 1 m3 GALIAN BATU Sedalam > 2 m sd 3 m 385,687.50 435,600.00

29 T.08.b.4 1 m3 KEDALAMAN YANG > 3 m untuk setiap penambahan kedalaman 1 m 35,062.50 39,600.00

T.08.b CARA SEMI MEKANIK

30 T.08.b.1 1 m3 GALIAN BATU Sedalam ≤ 1 m 118,250.00 161,562.50

31 T.08.b.2 1 m3 GALIAN BATU Sedalam > 1 m sd 2 m 136,950.00 182,682.50

32 T.08.b.3 1 m3 GALIAN BATU Sedalam > 2 m sd 3 m 148,170.00 195,354.50

KEDALAMAN YANG > 3 m menggunakan AHSP T.08.b.3 + AHSP T.08.a.4


33 T.08.b.4
untuk setiap kedalaman 1 m

T.09 GALIAN TANAH CADAS ATAU TANAH KERAS

T.09.a CARA MANUAL

34 T.09.a.1 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS BATU Sedalam ≤ 1 m 116,875.00 132,000.00

35 T.09.a.2 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS Sedalam > 1 m sd 2 m 130,152.00 146,995.20

GALIAN TANAH CADAS ATAU TANAH KERAS BATU Sedalam > 2 m sd 3


36 T.09.a.3 1 m3 140,250.00 158,400.00
m
GALIAN TANAH CADAS ATAU TANAH KERAS > 3 m untuk setiap
37 T.09.b.4 1 m3 9,350.00 10,560.00
penambahan kedalaman 1 m
T.09.b CARA SEMI MEKANIS

38 T.09.b.1 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS BATU Sedalam ≤ 1 m 129,250.00 147,090.63

39 T.09.b.2 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS Sedalam > 1 m sd 2 m 51,645.00 59,442.63

GALIAN TANAH CADAS ATAU TANAH KERAS BATU Sedalam > 2 m sd 3


40 T.09.b.3 1 m3 59,125.00 67,890.63
m

41 T.09.b.4 1 m3 KEDALAMAN YANG > 3 m menggunakan AHSP T.09.b.3 + AHSP T.09.a.4

T.10 GALIAN LUMPUR

T.10.a CARA MANUAL

42 T.10.a.1 1 m3 GALIAN LUMPUR SEDALAM ≤ 1 M 77,605.00 87,648.00

43 T.10.a.2 1 m3 GALIAN LUMPUR Sedalam > 1 m sd 2 m 93,500.00 105,600.00

44 T.10.a.3 1 m3 GALIAN LUMPUR Sedalam > 2 m sd 3 m 107,525.00 121,440.00

45 T.10.a.4 1 m3 GALIAN LUMPUR > 3 m untuk setiap penambahan kedalaman 1 m 14,025.00 15,840.00

T.10.b CARA SEMI MEKANIK

46 T.10.b.1 1 m3 GALIAN LUMPUR SEDALAM ≤ 1 M 33,495.00 36,531.00

47 T.10.b.2 1 m3 GALIAN LUMPUR Sedalam > 1 m sd 2 m 36,531.00 41,057.28

48 T.10.b.3 1 m3 GALIAN LUMPUR Sedalam > 2 m sd 3 m 41,376.50 48,924.48

49 T.10.b.4 1 m3 GALIAN LUMPUR > 3 m untuk setiap penambahan kedalaman 1 m 4,818.00 5,332.80

415837801.xls 146/14 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
T.11 GALIAN PASIR

T.11.a CARA MANUAL

50 T.11.a.1 1 m3 GALIAN PASIR SEDALAM ≤ 1 M 56,100.00 63,360.00

51 T.11.a.2 1 m3 GALIAN PASIR Sedalam > 1 m sd 2 m 74,800.00 84,480.00

52 T.11.a.3 1 m3 GALIAN PASIR Sedalam > 2 m sd 3 m 86,020.00 97,152.00

53 T.11.a.4 1 m3 GALIAN PASIR > 3 m untuk setiap penambahan kedalaman 1 m 9,350.00 10,560.00

T.11.b CARA SEMI MEKANIK

54 T.11.b.1 1 m3 GALIAN PASIR SEDALAM ≤ 1 M 34,870.00 39,347.00

55 T.11.b.2 1 m3 GALIAN PASIR Sedalam > 1 m sd 2 m 36,740.00 45,804.00

56 T.11.b.3 1 m3 GALIAN PASIR Sedalam > 2 m sd 3 m 44,990.00 60,456.00

57 T.11.b.4 1 m3 GALIAN PASIR > 3 m untuk setiap penambahan kedalaman 1 m 4,350.50 4,804.80

T.12.a
58 (K.3)
1 m2 PASANGAN 2 LAPIS SESEG BAMBU, JAT (JARAK ANTAR TIANG) ≤ 1,0 m' 38,087.50 42,160.25

T.12.b
59 (K.3)
1 m2 PASANGAN PAPAN 3/20, JAT ≤ 1,50 m' 61,818.90 72,631.35
T.12.c
60 (K.3)
1 m2 PASANGAN BALOK KAYU 8/12 , JAT 4 m' 185,399.50 208,102.95
T.12.d
61 1 m2 PASANGAN BALOK KAYU 8/12 , JAT ≤ 6 m' 193,539.50 217,144.95
(K.3)
T.14 TIMBUNAN DAN PEMADATAN

62 T.14.a.1 1 m3 TIMBUNAN TANAH ATAU URUGAN TANAH KEMBALI 30,855.00 34,848.00

63 T.14.b.1 1 m3 PEMADATAN TANAH 48,950.00 55,550.00

64 T.14.c.1 1 m3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI 453,200.00 530,640.00

65 T.14.d 1 m3 PEMADATAN PASIR SEBAGAI BAHAN PENGISI 13,750.00 16,060.00

T.15 ANGKUTAN MATERIAL DAN ATAU GALIAN

Koefisien pada AHSP T.15.a adalah kondisi normal, untuk hal khusus seperti
angkutan melalui sungai dengan kedalaman s/d 0,5 m dikalikan 1,2; sedang
untuk kedalaman sungai 1 m dikalikan 1,5

ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK JARAK


T.15.a.
HARIZONTAL (DATAR)

AHSP T.15.a ini berlaku pada angkutan material untuk jarak harizontal
(datar) dan termasuk juga medan dengan pelandaian menurun 1V:5H
sampai dengan pelandaian 1V:10H yang dihitung sebagai panjang
lintasannya.

MENGANGKUT MATERIAL ATAU DAN HASIL GALIAN DG JARAK


66 T.15.a.1 1 m3 21,824.00 24,688.40
ANGKUT 5 m
MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT
67 T.15.a.2 1 m3 24,183.50 27,358.10
10 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT


68 T.15.a.3 1 m3 27,725.50 31,364.30
20 m

MENGANGKUT MATERIAL DAN ATAU HASIL HASIL GALIAN DG JARAK


69 T.15.a.4 1 m3 31,328.00 35,439.80
ANGKUT 30 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK


70 T.15.a.5 1 m3 37,136.00 42,010.10
ANGKUT 50 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT


71 T.15.a.6 1 m3 52,800.00 59,730.00
100 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT


72 T.15.a.7 1 m3 83,600.00 94,572.50
200 m

415837801.xls 146/15 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT
73 T.15.a.8 1 m3 114,400.00 129,415.00
300 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK


74 T.15.a.9 1 m3 145,200.00 164,257.50
ANGKUT 400 m

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT


75 T.15.a.10 1 m3 171,600.00 194,122.50
500 m

MENGANGKUT HASIL GALIAN DG JARAK ANGKUT > 500 M UNTUK


76 T.15.a.11 1 m3 30,976.00 35,041.60
SETIAP PENAMBAHAN JARAK ANGKUT 100 M

ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK JARAK


T.15.b
VERTIKAL MENURUN

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG JARAK ANGKUT


77 T.15.a.2 1 m3 13,200.00 14,932.50
10 m
AHSP T.15.b hanya berlaku untuk pelandaian turun lebih terjal dari 1v : 5h
MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA
78 T.15.b.2 1 m3 18,480.00 20,905.50
TINGGI >1M s/d 2 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


79 T.15.b.3 1 m3 24,398.00 27,600.10
TINGGI >2M s/d 3 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


80 T.15.b.4 1 m3 30,489.25 34,491.05
TINGGI >3M s/d 4 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


81 T.15.b.5 1 m3 36,280.75 41,042.65
TINGGI >4 M s/d 5 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


82 T.15.b.6 1 m3 41,368.25 46,797.85
TINGGI >5 M s/d 6 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


83 T.15.b.7 1 m3 45,509.75 51,482.75
TINGGI >6 M s/d 7 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


84 T.15.b.8 1 m3 48,694.25 55,085.25
TINGGI >7 M s/d 8 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


85 T.15.b.9 1 m3 51,114.25 57,823.15
TINGGI >8 M s/d 9 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


86 T.15.b.10 1 m3 53,168.50 60,146.90
TINGGI >9 M s/d 10 M

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH DENGAN BEDA


87 T.15.b.11 1 m3 1,325.50 1,499.30
TINGGI >10 UNTUK SETIAP PENAMBAHAN 1 M
ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK JARAK
T.15.c
VERTIKAL NAIK
AHSP T.15.c hanya berlaku untuk pelandaian turun lebih terjal dari 1v : 10h

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


88 T.15.c.1 1 m3 26,400.00 29,865.00
TINGGI 1 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


89 T.15.c.2 1 m3 38,618.25 43,687.05
TINGGI >1M s/d 2 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


90 T.15.c.3 1 m3 53,130.00 60,104.00
TINGGI >2M s/d 3 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


91 T.15.c.4 1 m3 69,520.00 78,644.50
TINGGI >3M s/d 4 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


92 T.15.c.5 1 m3 86,322.50 97,652.50
TINGGI >4 M s/d 5 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


93 T.15.c.6 1 m3 103,015.00 116,534.00
TINGGI >5 M s/d 6 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


94 T.15.c.7 1 m3 118,250.00 133,771.00
TINGGI >6 M s/d 7 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


95 T.15.c.8 1 m3 132,412.50 149,792.50
TINGGI >7 M s/d 8 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA


96 T.15.c.9 1 m3 145,145.00 164,197.00
TINGGI >8 M s/d 9 M

415837801.xls 146/16 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH SAMPAI BEDA
97 T.15.c.10 1 m3 157,905.00 178,629.00
TINGGI >9 M s/d 10 M

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH DENGAN BEDA


98 T.15.c.11 1 m3 4,455.00 5,038.00
TINGGI >10 UNTUK SETIAP PENAMBAHAN 1 M

T.15.d Konversi berat material tanah biasa (lepas) kepada jenis material lain

JIKA BIAYA ANGKUTAN DIMASUKKAN DALAM HSD - BAHAN (DIHITUNG


T.15.d.1
TANPA OVERHEAD + KEUNTUNGAN)

99 T.15.d.1.a 1 m3 ANGKUT MATERIAL DENGAN JARAK ANGKUT 100 M' HORIZONTAL 48,000.00 54,300.00

JARAK ANGKUT VERTIKAL TURUN


100 T.15.d.1.b 1 m3 22,180.00 25,091.00
MENURUNKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3 M

JARAK ANGKUT VERTIKAL NAIK 3 M


101 T.15.d.1.c 1 m3 48,300.00 54,640.00
MENAIKKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3 M

JIKA BIAYA ANGKUTAN DIPISAH DARI HSP KOMPONEN PEKERJAAN


T.15.d.2 KONSTRUKSI (BIAYA KONSTRUKSI DAN BIAYA ANGKUT DITULIS
MASING-MASING SUDAH TERMASUK OVERHEAD + KEUNTUNGAN)

Contoh perhitungan konversi jenis material dan jarak angkut naik atau turun

JARAK ANGKUT HORIZONTAL 100 M


102 T.15.d.2.a 1 m3 52,800.00 59,730.00
JARAK ANGKUT MATERIAL DENGAN JARAK ANGKUT 100 M'

JARAK ANGKUT VERTIKAL TURUN


103 T.15.d.2.b 1 m3 24,398.00 27,600.10
MENURUNKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3 M

104 T.15.d.2.c 1 m3 JARAK ANGKUT VERTIKAL NAIK 3 M 53,130.00 60,104.00

MENAIKKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3 M

A.2 PEKERJAAN PASANGAN

P.01 PASANGAN BATU DENGAN MORTAR JENIS PC - PP

MORTAR TIPE M (MANUAL)


105 P.01.a.1 1 m3 1,150,545.00 1,327,397.50
(Mutu PP tertentu setara dg campuran 1PP : 2PP)

MORTAR TIPE M (MENGGUNAKAN MOLEN)


106 P.01.a.2 1 m3 1,141,635.00 1,312,613.50
(Mutu PP tertentu setara dg campuran 1PP : 2PP)

MORTAR TIPE S (MANUAL)


107 P.01.b.1 1 m3 1,104,950.00 1,282,806.25
(Mutu PP tertentu setara dg campuran 1PP : 3PP)

MORTAR TIPE S (Menggunakan Molen)


108 P.01.b.2 1 m3 1,096,040.00 1,268,022.25
(Mutu PP tertentu setara dg campuran 1PP : 3PP)

MORTAR TIPE N (Manual)


109 P.01.c.1 1 m3 1,069,351.25 1,247,984.38
(Mutu PP tertentu setara dg campuran 1PP : 4PP)

MORTAR TIPE N (Menggunakan Molen)


110 P.01.c.2 1 m3 1,060,441.25 1,233,200.38
(Mutu PP tertentu setara dg campuran 1PP : 4PP)

MORTAR TIPE O (Manual)


111 P.01.d.1 1 m3 1,046,867.25 1,226,594.88
(Mutu PP tertentu setara dg campuran 1PP : 5PP)

MORTAR TIPE O (Menggunakan Molen))


112 P.01.d.2 1 m3 1,037,957.25 1,211,810.88
(Mutu PP tertentu setara dg campuran 1PP : 5PP)

P.01.e BONGKAR DAN PEMANFAATAN BATU BEKAS PASANGAN

113 P.01.e.1 1 m3 BONGKAR PASANGAN BATU & PEMBERSIHAN BATU (MANUAL) 117,744.00 133,386.00

114 P.01.e.2 1 m3 BONGKAR PASANGAN BATU (MANUAL) 112,728.00 127,314.00

115 P.01.e.3 1 m3 BONGKAR PASANGAN BATU DENGAN JACK HAMMER 78,100.00 88,110.00

PEMBERSIHAN BONGKARAN PASANGAN BATU UNTUK PEMANFAATAN


116 P.01.e.4 1 m3 18,942.00 21,400.50
KEMBALI MATERIAL BATU **)

415837801.xls 146/17 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
P.02 PEKERJAAN PASANGAN BATU MERAH

P.02.a MORTAR TIPE M (SETARA CAMPURAN 1PC : 2PP)

117 P.02.a.1 1 m3 MANUAL 969,540.00 1,066,202.50

118 P.02.a.2 1 m3 MENGGUNAKAN MOLEN 1,212,090.00 1,319,642.50

P.02.b MORTAR TIPE S (SETARA CAMPURAN 1PC : 3PP)

119 P.02.b.1 1 m3 MANUAL 960,877.50 1,056,027.50

120 P.02.b.2 1 m3 MENGGUNAKAN MOLEN 876,727.50 960,987.50

P.02.c MORTAR TIPE N (SETARA CAMPURAN 1PC : 4PP)

121 P.02.c.1 1 m3 MANUAL 938,334.38 1,034,120.31

122 P.02.c.2 1 m3 MENGGUNAKAN MOLEN 953,184.38 1,044,680.31

P.02.d MORTAR TIPE O (SETARA CAMPURAN 1PC : 5PP)

123 P.02.d.1 1 m3 MANUAL 930,778.75 1,028,383.13

124 P.02.d.2 1 m3 MENGGUNAKAN MOLEN 945,628.75 1,038,943.13

P.02.e MORTAR campuran (SETARA CAMPURAN 1PC : 6PP)

125 P.02.e.1 1 m3 MANUAL 941,366.25 1,043,329.38

126 P.02.e.2 1 m3 MENGGUNAKAN MOLEN 956,216.25 1,053,889.38

P.02.f. BONGKAR PASANGAN BATA MERAH

127 P.02.f.1 1 m3 BONGKAR PASANGAN BATA MERAH (MANUAL) 56,919.50 64,295.00

128 P.02.f.2 1 m3 BONGKAR PASANGAN BATA MERAH dengan JACK HAMMER 27,500.00 31,020.00

P.03 PEKERJAAN SIARAN DG MORTAR JENIS PC-PP

129 P.03.a 1 m2 SIARAN DG MORTAR JENIS PC-PP TYPE M 57,456.58 63,845.51

130 P.03.b 1 m2 SIARAN DG MORTAR JENIS PC-PP TYPE S 57,699.95 64,400.33

P.04 PEKERJAAN PLESTERAN DG MORTAR JENIS PC-PP

TRASRAAM TEBAL 1 cm,


131 P.04.a 1 m3 59,250.95 65,791.83
DG MORTAR JENIS PC-PP TYPE M (campuran 1PC : 2PP)

PLESTERAN TEBAL 1 cm,


132 P.04.b 1 m2 58,230.70 64,844.45
DG MORTAR JENIS PC-PP TYPE S (campuran 1PC : 3PP)

1 PLESTERAN TEBAL 1 cm,


133 P.04.c m2 57,222.69 63,909.66
DG MORTAR JENIS PC-PP TYPE N (campuran 1PC : 4PP)

1 TRASRAAM TEBAL 1,5 cm,


134 P.04.d m2 77,664.62 86,189.07
DG MORTAR JENIS PC-PP TYPE M (campuran 1PC : 2PP)

PLESTERAN TEBAL 1,5 cm,


135 P.04.e 1 m2 76,043.88 84,880.18
DG MORTAR JENIS PC-PP TYPE S (campuran 1PC : 3PP)

PLESTERAN TEBAL 1,5 cm,


136 P.04.f 1 m2 72,134.15 80,556.03
DG MORTAR JENIS PC-PP TYPE N (campuran 1PC : 4PP)

137 P.04.g 1 m2 PEKERJAAN ACIAN 34,337.19 38,078.91

138 P.05 1 m3 PASANGAN BATU KOSONG * 373,560.00 476,190.00


Jika pasangan batu kosong ini dipasang untuk kontak langsung dengan
*)
tanah, maka bahan perlu ditambah koefisien pasir 0,432 m3
P.08 PASANGAN BATU MUKA DAN BATU CANDI

168 P.08.a.1 1 m2 Pasangan Batu Muka 195,588.25 222,253.63

169 P.08.b.1 1 m2 Pasangan Batu Candi 202,463.25 215,378.63

415837801.xls 146/18 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
P.09 PASANGAN GEOTEKSTIL

170 P.09.a.1 1 m2 Pemasangan Geotekstil Tipe A tipis 28,325.00 30,910.00

171 P.09.b.1 1 m2 Pemasangan Geotekstil Tipe B, tebal sedang 37,202.00 41,272.00

172 P.09.c.1 1 m2 Pemasangan Geotekstil Tipe C, tebal 49,390.00 54,032.00

173 P.10 1 bh PASANGAN BAR SCREEN / SARINGAN KASAR 471,350.00 508,893.00

PASANGAN AMBANG UKUR PADA BANGUNAN PENGUKUR DAN ATAU


174 P.11 1 bh 11,696,525.50 12,284,299.50
PENGATUR

P.12 PASANGAN LEMPENG RUMPUT

175 P.12.a 1 m2 Penanaman Rumput Lempengan 23,870.00 25,685.00

176 P.12.b.1.a 1 m2 Pembabadan Rumput secara umum dan manual 1,168.75 1,320.00

P.12.b.1.b PERHITUNGAN SECARA DETAIL


P.12.b.1.b
177 1 m2 Daerah datar sampai pelandaian naik dengan kemiringan 1V : 10H 748.00 844.80
.1
P.12.b.1.b
178 1 m2 Daerah datar sampai pelandaian naik dengan kemiringan 1V : 2,5H 1,168.75 1,320.00
.2
P.12.b.1.b
179 1 m2 Daerah datar sampai pelandaian naik dengan kemiringan 1V : 1H 1,561.45 1,763.52
.3

P.12.b.1.b Daerah datar sampai pelandaian naik dengan kemiringan 1V : 1H s/d 2,5V :
180 1 m2 2,337.50 2,640.00
.4 1H

P.12.b.1.b Daerah datar sampai pelandaian naik dengan kemiringan 2,5V : 1H Sampai
181 1 m2 4,675.00 5,280.00
.5 Tegak

P.12.b.2 Secara Semi Makanis

182 P.12.b.2.a 1 m2 Perhitungan Secara Umum (Jika medan tidak diketahui secara detail) 410.85 467.94

P.12.b.2.b Perhitungan secara detail (jika diketahui kondisi medan secara detail)

P.12.b.2.b
183 1 m2 Daerah datar sampai pelandaian naik dengan kemiringan 1V : 10H 386.65 440.11
.1

P.12.b.2.b Perhitungan secara detail (jika diketahui kondisi medan secara detail)

P.12.b.2.b Daerah datar sampai pelandaian naik dengan kemiringan 1V : 10H s/d 1V :
184 1 m2 421.99 480.81
.2 2,5H

P.12.b.2.b Daerah datar sampai pelandaian naik dengan kemiringan 1V : 2,5H s/d 1V :
185 1 m2 1,470.15 1,771.44
.3 1H

P.12.b.2.b Daerah datar sampai pelandaian naik dengan kemiringan 1V : 1H s/d 2,5V :
186 1 m2 914.10 1,041.37
.4 1H

P.12.b.2.b Daerah datar sampai pelandaian naik dengan kemiringan2,5V : 1H s/d


187 1 m2 1,659.90 1,894.20
.5 tegak.

P.13 PEKERJAAN PANTAI

188 P.13.a 1 ph Penanaman Pohon bakau 3,344.00 3,919.30

189 P.13.b 1 m2 Matras Bambu 110,550.00 144,925.00

P.14 PASANGAN ARMOR

190 P.14.a 1 bh Pembuatan Kubus ukuran 30 x 30 x 30 cm 85,342.10 93,629.20

191 P.14.b 1 bh Pembuatan Kubus ukuran 40 x 40 x 40 cm 201,041.88 220,436.05

192 P.14.c 1 bh Pembuatan 3B : Blok Beton Bergigi 309,775.38 339,548.01

193 P.14.d 1 bh Pembuatan Blok Beton Berat 0,5 Ton Quatripod, Tetrapod, Dolos Tribar 693,315.90 759,694.07

194 P.14.e 1 bh Pembuatan Blok Beton Berat 0,75 Ton Quatripod, Tetrapod, Dolos Tribar 1,037,730.68 1,137,074.44

195 P.14.f 1 bh Pembuatan Blok Beton Berat 1,00 Ton Quatripod, Tetrapod, Dolos Tribar 1,388,567.25 1,521,586.50

196 P.14.g 1 bh Pembuatan Blok Beton Berat 1,50 Ton Quatripod, Tetrapod, Dolos Tribar 2,046,314.94 2,242,302.42

197 P.14.h 1 bh Pembuatan Blok Beton Berat 2,00 Ton Quatripod, Tetrapod, Dolos Tribar 2,046,314.94 2,242,302.42

415837801.xls 146/19 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
198 P.14.i 1 bh Pembuatan Blok Beton Berat 2,50 Ton Quatripod, Tetrapod, Dolos Tribar 2,046,314.94 2,242,302.42

199 P.14.j 1 m3 Pemasangan Berbagai Jenis Armor 3,736,132.77 4,098,923.06

200 P.14.k 1 m3 Pemasangan Batu 1 kg - 3 kg, void maks 15% 441,809.50 503,558.00

201 P.14.l 1 m3 Pemasangan Batu 3 kg - 5 kg, void maks 15% 443,300.00 508,200.00

202 P.14.m 1 m3 Pemasangan Batu 5 kg - 10 kg, void maks 20% 501,710.00 570,845.00

203 P.14.n 1 m3 Pemasangan Batu 10 kg - 30 kg, void maks 20% 516,010.00 587,345.00

204 P.14.o 1 m3 Pemasangan Batu 30 kg - 50 kg, void maks 25% 527,560.00 600,325.00

205 P.14.p 1 m3 Pemasangan Batu 50 kg - 100 kg, void maks 25% 539,000.00 613,140.00

206 P.14.q 1 m3 Pemasangan Batu 100 kg - 200 kg, void maks 30% 550,440.00 626,340.00

207 P.14.r 1 bh Pembuatan Kubus ukuran 40 x 40 x 40 cm 201,041.88 220,436.05

208 P.14.s 1 m3 Pemasangan Batu 300 kg - 400 kg, void maks 30% 582,010.00 662,035.00

209 P.14.t 1 m3 Pemasangan Batu 400 kg - 500 kg, void maks 35% 582,010.00 662,035.00

210 P.14.u 1 m3 Pemasangan Batu 200 kg - 500 kg, void maks 32% 578,578.00 658,190.50

211 P.14.v 1 m3 Pemasangan Batu 500 kg - 650 kg, void maks 35% 599,170.00 681,642.50

212 P.14.w 1 m3 Pemasangan Batu 650 kg - 800 kg, void maks 35% 607,750.00 691,542.50

P.15 STRUKTUR KRIB LAUT

Buis Beton diangkut < 30 m dan dipasang untuk Konstruksi Pengaman


213 P.15.a.1 1 bh 18,700.00 21,010.00
Pantai
Pengecoran Buis Beton Ø 1 m' dengan campuran
214 P.15.b 1 bh 1,176,161.25 1,309,381.07
Pasang Pondasi Sumuran diameter 100 cm
215 P.16 1 bh Pasangan pipa suling-suling 29,232.50 39,704.50

KOEFISIEN UNTUK ANALISIS HARGA SATUAN PEKERJAAN


A.3.1
PEMBUATAN BETON

B.01 BETON UNTUK LANTAI KERJA (BEDDING)

TIPE 1 : MENGGUNAKAN CAMPURAN BETON TUMBUK fc' = 1,8 s/d 3,7


216 B.01.a 1 m3 888,734.00 1,007,325.00
(BO : K-40 s/d K-60) atau Setara 1PC : 3PB : 5Kr

TIPE 2 : MENGGUNAKAN CAMPURAN BETON TUMBUK fc' = 5,6 s/d 7,4


217 B.01.b 1 m3 902,132.00 1,014,172.50
MPa (BO : K-80 s/d K-100) atau Setara 1PC : 2PB : 3Kr

TIPE 3 : MENGGUNAKAN CAMPURAN BETON TUMBUK fc' = 7,4 MPa (K-


218 B.01.c 1 m3 918,497.25 1,030,800.38
100) atau Setara 1PC : 2PB : 3Kr

TIPE 3 : MENGGUNAKAN CAMPURAN Beton Mutu f'c = 7,4 Mpa (K100)


B.02
ATAU SETARA 1PC : 2 PB : 3Kr

219 B.02.a 1 m3 MANUAL 980,091.75 1,097,493.38

220 B.02.b 1 m3 MENGGUNAKAN MOLEN 983,614.50 1,099,352.38

B.03 BETON MUTU , fc' = 9,8 Mpa (K.125), SLUMP (12± 2) w/c = 0,78

221 B.03.a 1 m3 MANUAL 1,010,435.45 1,129,296.75

222 B.03.b 1 m3 MENGGUNAKAN MOLEN 1,011,001.95 1,127,608.25

B.04 BETON MUTU , fc' = 12,2 Mpa (K.150), SLUMP (12± 2) w/c = 0,72

223 B.04.a 1 m3 MANUAL 1,031,869.67 1,151,163.95

224 B.04.b 1 m3 MENGGUNAKAN MOLEN 1,032,436.17 1,149,475.45

B.05 BETON MUTU , fc' = 14,5 Mpa (K.175), SLUMP (12± 2) w/c = 0,66

225 B.05.a 1 m3 MANUAL 1,057,217.03 1,177,302.37

226 B.05.b 1 m3 MENGGUNAKAN MOLEN 1,057,783.53 1,175,613.87

B.06 BETON MUTU , fc' = 16,9 Mpa (K.200), SLUMP (12± 2) w/c = 0,61

227 B.06.a 1 m3 MANUAL 1,081,564.71 1,201,990.60

228 B.06.b 1 m3 MENGGUNAKAN MOLEN 1,082,131.21 1,200,302.10

415837801.xls 146/20 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
B.07 BETON MUTU , fc' = 19,3 Mpa (K.225), SLUMP (12± 2) w/c = 0,58

229 B.07.a 1 m3 MANUAL 1,099,782.44 1,221,126.57

230 B.07.b 1 m3 MENGGUNAKAN MOLEN 1,100,348.94 1,219,438.07

B.08 BETON MUTU , fc' = 21,7 Mpa (K.250), SLUMP (12± 2) w/c = 0,56

231 B.08.a 1 m3 MANUAL 1,112,020.45 1,233,148.54

232 B.08.b 1 m3 MENGGUNAKAN MOLEN 1,112,586.95 1,231,460.04

B.09 BETON MUTU , fc' = 16,9 Mpa (K.200), SLUMP (12± 2) w/c = 0,61

233 B.09.a 1 m3 MANUAL 1,133,459.25 1,254,307.61

224 B.09.b 1 m3 MENGGUNAKAN MOLEN 1,134,025.75 1,252,619.11

BETON MUTU , fc' = 26,4 Mpa (K.300), SLUMP (12± 2) w/c = 0,52 (KEDAP
B.10
AIR)

225 B.10.a 1 m3 MANUAL 1,139,937.54 1,260,629.88

226 B.10.b 1 m3 MENGGUNAKAN MOLEN 1,140,504.04 1,258,941.38


BETON MUTU , fc' = 28,8 Mpa (K.325), SLUMP (12± 2) w/c = 0,49 (KEDAP
B.11
AIR)
227 B.11.a 1 m3 MANUAL 1,164,941.15 1,285,290.18

228 B.11.b 1 m3 MENGGUNAKAN MOLEN 1,165,507.65 1,283,601.68

BETON MUTU , fc' = 31,2 Mpa (K.350), SLUMP (12± 2) w/c = 0,48 (KEDAP
B.12
AIR)

229 B.12.a 1 m3 MANUAL 1,224,373.84 1,350,917.42

230 B.12.b 1 m3 MENGGUNAKAN MOLEN 1,174,180.84 1,292,122.42

B.13 BETON MENGGUNAKAN READY MIXED DAN BAHAN AKTIF


BETON MENGGUNAKAN READY MIXED DAN BAHAN AKTIF DAN
231 B.13.a 1 m3 1,478,950.00 1,569,975.00
POMPA BETON
BAHAN ADIKTIF

232 B.13.b 1 m3 Beton Menggunakan Bahan Aditif 145,200.00 165,000.00

PENAMBAHAN KOEFISIEN TENAGA KERJA DAN ATAU PERALATAN

B.14 MENGANGKUT / MENAIKKAN CAMPURAN BETON JARAK >- 5 M

B.14.a Beton Dicorkan pada tapak berjarak <25 m

dg Ketinggian/kedalaman < 1m

233 B.14.a.1 1 m3 Manual 38,335.00 43,296.00

B.14.b Beton Dicorkan pada tapak berjarak

setiap tambahan jarak 25 m (horizontal)

Beton Dicorkan pada tapak berjarak

234 B.14.b.1 1 m3 setiap tambahan jarak 25 m (horizontal) 46,750.00 52,800.00

Manual

Beton Dicorkan pada tapak berjarak setiap tambahan 25 m


235 B.14.b.2 1 m3 78,100.00 87,120.00
Menggunakan Peralatan Pompa Beton

B.15 Pemadatan Beton pada saat Mengecor

Pemadatan Beton pada saat Mengecor


236 B.15.a 1 m3 39,875.00 44,000.00
Vibrator

237 B.15.b 1 m3 Manual (menggunakan penusuk besi beton) 46,750.00 52,800.00

415837801.xls 146/21 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
B.16 Beton Dicorkan pada tapak berjarak

Beton Dicorkan pada tapak Tiap Kenaikan 4 m (vertikal)


238 B.16.a 1 m3 23,375.00 26,400.00
Manual

Beton Dicorkan pada tapak Tiap Kenaikan 4 m (vertikal)

239 B.16.b 1 m3 Menggunakan peralatan pompa beton 78,100.00 87,120.00

KOEFISIEN UNTUK ANALISA HARGA SATUAN PEKERJAAN


PEMBESIAN BETON

B.17 PEMBESIAN BESI POLOS ATAU ULIR

240 B.17.a 100 kg Untuk Pembesian Pelat 1,330,120.00 1,435,335.00

241 B.17.b 100 kg Untuk Pembesian Kolom, Balok, Ring Balk dan Sloof 1,542,640.00 1,673,265.00

242 B.18 100 kg Pembesian dengan Jaring Kawat (wire mesh) Untuk Pelat atau Dinding 1,576,575.00 1,695,375.00

243 B.19 100 kg Pembesian Kabel presstreed polos 1,852,400.00 2,065,112.50

MENGANGKUT / MENAIKKAN TULANGAN SETIAP KENAIKAN


VERTIKAL 4 M' ATAU JARAK HORIZONTAL 25 M KE TAPAK
PEMASANGAN

244 B.20.a 4 m' Manual 38,500.00 43,230.00

10 s/d
245 B.20.b m' Mekanis (penambahan jarak horizontal) 74,442.50 77,990.00
25

246 B.20.c 25 m' Mekanis (penambahan jarak horizontal) 90,062.50 95,480.00

247 B.20.c 4 m' Mekanis (penambahan tiap 4 m' jarak vertikal) 93,500.00 100,980.00

B.21 PEKERJAAN BEKISTING


248 B.21.a 1 m2 Bekisting Lantai Beton expose dengan multipleks 18 mm 105,468.00 115,951.00

249 B.21.b 1 m2 Bekisting Lantai Beton Biasa dengan multipleks 12 mm atau 18 mm (TP) 50,353.60 60,038.00

250 B.21.c 1 m2 Bekisting Lantai Beton Biasa menggunakan papan kayu 3/20 cm (TP) 119,460.00 138,765.00

Perancah Beksiting Lantai menggunakan kaso 5/7 tinggi 4m', JAT (Jarak
251 B.21.d 1 m2 148,390.00 156,585.00
Antar Tiang) ≤ 60 cm

252 B.21.e 1 m2 Perancah Beksiting kayu dolken Ø 8 - 10 cm tinggi 4m', JAT ≤ 80 cm 86,808.70 96,053.65

Perancah Beksiting Lantai menggunakan Bambu Ø 8 - 10 cm tinggi 4m', JAT


253 B.21.f 1 m2 77,918.50 96,459.00
≤ 80 cm

B.22 FLOORDECK
254 B.22.a 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 0,60 m) 63,690.00 66,583.00

255 B.22.b 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 0,80 m) 63,129.00 65,714.00

256 B.22.c 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 1,20 m) 53,737.20 55,729.30

257 B.22.d 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 2.00 m) 49,935.60 51,665.90

B.23 BEKISTING BALOK


Bekisting balok beton expose menggunakan multipleks 18 mm JAT (Jarak
258 B.23.a 1 m2 176,957.00 189,486.00
Antar Tiang) ≤ 1,00 m

Bekisting balok beton biasa menggunakan multipleks 12 mm JAT (Jarak


259 B.23.b 1 m2 116,705.60 129,096.00
Antar Tiang) ≤ 1,00 m

260 B.23.c 1 m2 Bekisting balok beton biasa menggunakan kayu papan 3/20 cm (TP) 174,768.00 196,922.00

Perancah Beksiting balok menggunakan Kaso 5/7 tinggi 4m' dan JAT (Jarak
261 B.23.d 1 m2 112,794.00 121,066.00
Antar Tiang) ≤ 1,00 m

Perancah Beksiting balok menggunakan Dolken Ø 8 - 10 cm tinggi 4m' dan


262 B.23.e 1 m2 83,812.30 94,371.20
JAT (Jarak Antar Tiang) ≤ 1,20 m

Perancah Beksiting balok beton menggunakan Bambo Ø 8 - 10 cm tinggi 4m'


263 B.23.f 1 m2 87,807.50 103,202.00
dan JAT (Jarak Antar Tiang) ≤ 1,00 m

415837801.xls 146/22 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
B.24 BEKISTING KOLOM
264 B.24.a 1 m2 Bekisting Kolom beton EXPOSE menggunakan multipleks 18 mm 150,254.50 161,859.50

Bekisting Kolom beton biasa menggunakan multipleks 12mm atau 18 mm,


265 B.24.b 1 m2 88,919.60 100,397.00
(TP)

266 B.24.c 1 m2 Bekisting Kolom beton biasa menggunakan kayu papan 3/20 cm, (TP) 161,832.00 183,403.00

Perancah Bekisting Kolom beton menggunakan kayu uk.5/7 cm, tinggi 4m'
267 B.24.d 1 m2 109,758.00 28,900.00
JAT ≤ 1,00 M

Perancah Bekisting Kolom beton menggunakan kayu dolken Ø 8 -10 cm,


268 B.24.e 1 m2 78,658.80 88,552.20
tinggi 4m' JAT ≤ 1,20 M

Perancah Bekisting Kolom beton dengan bambu Ø 8 -10 cm, tinggi 4m' JAT
269 B.24.f 1 m2 71,450.50 84,777.00
≤ 1,00 M

B.25 Bekisting Dinding


270 B.25.a 1 m2 Bekisting Dinding beton expose dengan multipleks 18 mm 146,454.00 158,224.00

271 B.25.b 1 m2 Bekisting Dinding beton biasa dengan multipleks 12 mm atau 18 mm (TP) 86,851.60 98,560.00

272 B.25.c 1 m2 Bekisting Dinding beton biasa menggunakan Kayu Papan 3/20 cm 159,918.00 181,742.00

Perancah/Penyokong Bekisting Dinding beton menggunakan Kayu 5/7 cm,


273 B.25.d 1 m2 107,844.00 116,006.00
tinggi maksimum 2,50m

Perancah/Penyokong Bekisting Dinding beton menggunakan Balok 8/12


274 B.25.e 1 m2 163,416.00 173,404.00
cm, tinggi maksimum 4,50m

B.26 Bekisting Pondasi dan sloof


275 B.26.a 1 m2 Bekisting Pondasi dan sloof beton biasa dengan 110,308.00 117,106.00

276 B.26.b 1 m2 Bekisting Pondasi dan sloof beton biasa menggunakan papan 3/20 cm 170,610.00 191,785.00

Perancah/penyokong Bekisting Pondasi dan sloof beton biasa


277 B.26.c 1 m2 103,510.00 109,230.00
menggunakan kaso 5/7, tinggi maksimum 2,00 m

B.27 BONGKAR BEKISTING


Bongkar Bekisting secara Biasa (membersihkan dan membereskan puing-
278 B.27.a 1 m2 3,740.00 4,224.00
puing)

Bongkar Bekisting secara Biasa secara hati-ahti (dan membereskan puing-


279 B.27.b 1 m2 5,610.00 6,336.00
puing)

KOEFISIEN UNT ANALISIS HARGA SATUAN PEKERJAAN


A.3.5
PELAKSANAAN CURING
B.28 Pelaksanaan Curring Beton
ada berbagai cara pelaksanaan curing beton diantaranya :

menggenangi atau menyiram permukaan beton, dan dengan uap (steam).

Jika tidak ditentukan dapat menggunakan acuan sebagai berikut

280 B.28.a 100 m2 Menggenangi air permukaan beton 152,900.00 173,140.00

281 B.28.b 100 m2 Menyirami air permukaan beton menggunakan media terpal selama 4 hari 187,000.00 224,730.00

282 B.28.c 100 m2 Menyirami permukaan beton menggunakan media karung goni selama 4 hari 506,000.00 573,100.00

A.3.6 PEMBONGKARAN KONSTRUKSI BETON


Perhitungan praktis pembongkaran beton dan atau bertulang ditentukan oleh
tingkat mutu beton dan kemudahan pembongkarannya. Pada kondisi normal
sering dihitung pembongkaran sekitar 2,5 kali upah pembuatan beton. Jika
dibutuhkan analisa yang rinci pembongkaran beton bertulang sebagai berikut
:
283 B.29.a 1 m3 Bongkar beton secara konvensional 541,530.00 599,280.00

284 B.29.b 1 m3 Bongkar beton dengan Jack Hammer 242,825.00 272,470.00

415837801.xls 146/23 hspk (2)


JUMLAH
No. SNI VOL SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM
Rp Rp
B.30 PEMASANGAN WATERSTOP
285 B.30.a 1 m' Pasangan Water stop PVC lebar 150 mm 82,720.00 95,535.00

286 B.30.b 1 m' Pasangan Water stop PVC lebar 200 mm 57,013.00 64,069.50

287 B.30.c 1 m' Pasangan Water stop PVC lebar 230 mm - 320 mm 104,731.00 117,744.00

288 B.30.d 1 m' Pasangan Water stop Ruber lebar 150 mm - 200 mm 149,600.00 162,442.50

A.4.1 AHSP (ANALISA HARGA SATUAN PEKERJAAN)


PEMANCANGAN SECARA MANUAL / TANPA MESIN
MENGGUNAKAN TRIPOD DAN HAMMER
289 F.01 1 m' Penetrasi Tiang Pancang Kayu Gelondongan Ø 15 - 20 cm 62,700.00 71,857.50

290 F.02 1 m' Penetrasi Tiang Pancang Kayu atau Dolken Ø 8 - 10 cm 13,667.50 15,680.50

291 F.03 1 m' Penetrasi Tiang Pancang Baja Pipa Ø 30 cm atau Kotak 30 x 30 cm 57,172.50 62,672.50

F.04 TIANG PANCANG BETON BERTULANG


292 F.04.a 1 m' Penetrasi Tiang Pancang Beton Kotak 20 x 20 cm 71,335.00 79,662.00

293 F.04.b 1 m' Penetrasi Tiang Pancang Beton Kotak 25 x 25 cm 79,640.00 88,968.00

294 F.04.c 1 m' Penetrasi Tiang Pancang Beton Kotak 30 x 30 cm 136,620.00 152,064.00

295 F.04.d 1 m' Penetrasi Tiang Pancang Beton Kotak 40 x 40 cm 166,980.00 185,856.00

296 F.04.e 1 m' Penetrasi Tiang Pancang (Hollow) Beton Ø 40 cm 99,550.00 111,210.00

F.05 TURAP KAYU


297 F.05.a 1 m' Penetrasi untuk 1 m' lebar turap (10-12,5 buah) Kayu Dolken Ø 8 - 10 cm 165,000.00 186,450.00

298 F.05.b 1 m' Penetrasi untuk 1 m' lebar turap (10 buah) Papan (2-3) x 10 cm 152,625.00 171,710.00

299 F.05.c 1 m' Penetrasi untuk 1 m' lebar turap (5 buah) Papan (2-3) x 20 cm 130,212.50 146,377.00

300 F.05.d 1 m' Penetrasi untuk 1 m' lebar turap (4 buah) Papan (2-3) x 25 cm 130,350.00 146,498.00

301 F.05.e 1 m' Penetrasi untuk 1 m' lebar turap (3,33 buah) Papan (2-3) x 30 cm 106,573.50 120,241.00

302 F.05.f 1 m' Penetrasi untuk 1 m' lebar turap (4 buah) Kayu Kaso 5/7 tebal 5 cm 126,923.50 142,851.50

303 F.05.g 1 m' Penetrasi untuk 1 m' lebar turap (20 buah) Kayu Kaso 5/7 tebal 7 cm 104,511.00 117,518.50

304 F.05.h 1 m' Penetrasi untuk 1 m' lebar turap (8 buah) Kayu Balok 8/12 tebal 8 cm 152,625.00 171,710.00

305 F.05.i 1 m' Penetrasi untuk 1 m' lebar turap (12,5 buah) Kayu Balok 8/12 tebal 12 cm 130,212.50 146,377.00

F.06 TURAP BAJA


306 F.06.a 1 m' Penetrasi (1 buah) Turap Baja Profil Larsen lebar 350 mm 78,595.00 86,295.00

307 F.06.b 1 m' Penetrasi untuk 1 m' lebar Turap (7 buah) Baja Profil INP-8 + UNP-8 93,720.00 103,125.00

308 F.06.c 1 m' Penetrasi untuk 1 m' lebar Turap (5,56 buah) Baja Profil INP- 10 + UNP- 10 109,758.00 120,021.00

F.07 TURAP BETON PRE - CAST


309 F.07.a 1 m' Penetrasi 1 buah Turap Beton pre-cast 12 x 30 cm 48,400.00 55,605.00

310 F.07.b 1 m' Penetrasi 1 buah Turap Beton Precast 15 x 40 cm 77,440.00 88,968.00

311 F.07.c 1 m' Penetrasi 1 buah Turap Beton Precast 22 x 50 cm 96,800.00 111,210.00

415837801.xls 146/24 hspk (2)


[Path]

ANALISA HARGA SATUAN PEKERJAAN


BERDASAR PERMEN NO.28/PRT/M/2016 BIDANG SUMBER DAYA AIR
SUMBER DATA : PASARAN B E BAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

I A.1 PEKERJAAN TANAH


PEKERJAAN TANAH SECARA MANUAL DAN SEMI
A.1.1
MEKANIS (NORMATIF)
AHSP PEMBERSIHAN & PENGUPASAN PERMUKAAN
T.01
TANAH
1 T.01.a 1 m2 PEMBERSIHAN DAN STRIPING / KOSREKAN 5,610.00 6,336.00
A TENAGA 5,100.00 5,760.00
L.01 0.060 OH Pekerja 75,000.00 85,000.00 4,500.00 5,100.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00

B BAHAN - -
C PERALATAN
D Jumlah A + B + C 5,100.00 5,760.00
E OVERHEAD & PROFIT (CONTOH) 10% 510.00 576.00
F Harga Satuan Pekerjaan (D+E) 5,610.00 6,336.00

2 T.01.b 1 m2 TEBAS TEBANG BERUPA MEMOTONG & 7,128.00 8,041.00


MEMBERSIHKAN LOKASI DARI TANAMAN / TUMBUHAN
Ø < 15 CM

A TENAGA 6,375.00 7,200.00


L.01 0.075 OH Pekerja 75,000.00 85,000.00 5,625.00 6,375.00
L.04 0.0075 OH Mandor 100,000.00 110,000.00 750.00 825.00

B BAHAN 105.00 110.00


0.010 ltr Minyak Tanah 10,500.00 11,000.00 105.00 110.00
C PERALATAN
D Jumlah A + B + C 6,480.00 7,310.00
E OVERHEAD & PROFIT (CONTOH) 10% 648.00 731.00
F Harga Satuan Pekerjaan (D+E) 7,128.00 8,041.00

3 T.01.c 1 bh CABUT TUNGGUL POHON TANAMAN KERAS Ø > 15 CM 22,000.00 24,970.00


& MEMBUANG SISA TUNGGUL KAYU & AKAR-
AKARNYA
A TENAGA 17,000.00 19,200.00
L.01 0.200 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.04 0.020 OH Mandor 100,000.00 110,000.00 2,000.00 2,200.00

B BAHAN - -
- -
C PERALATAN 3,000 3,500
0.100 hari Chainswaw 30,000 35,000 3,000 3,500
D Jumlah A + B + C 20,000.00 22,700.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,000.00 2,270.00
F Harga Satuan Pekerjaan (D+E) 22,000.00 24,970.00

AHSP UITZET TRASE SALURAN DAN PASANG PROFIL


T.02
MELINTANG
4 T.02.a 1 m' UITZET TRASE SALURAN 2,750.00 3,146.00
A TENAGA 1,940.00 2,220.00
L.01 0.012 OH Pekerja 75,000 85,000 900.00 1,020.00
L.05 0.004 OH Juru Ukur 150,000 175,000 600.00 700.00
L.06 0.004 OH Pembantu Juru Ukur 110,000 125,000 440.00 500.00
B BAHAN - -
C PERALATAN 560.00 640.00
0.004 hr water pass 50,000 60,000 200.00 240.00
0.004 hr Theodalith 90,000 100,000 360.00 400.00
D Jumlah A + B + C 2,500.00 2,860.00
E OVERHEAD & PROFIT (CONTOH) 10% 250.00 286.00
F Harga Satuan Pekerjaan (D+E) 2,750.00 3,146.00

PASANG 1 M' PROFIL MELINTANG GALIAN TANAH


T.02.b
SALURAN DAN PASANG BOUWPLANK
5 T.02.b.1 1 m' PASANG PROFIL MELINTANG GALIAN TANAH 26,015.00 30,360.00
A TENAGA 12,200.00 13,860.00
L.01 0.0600 OH Pekerja 75,000 85,000 4,500.00 5,100.00
L.02 0.0200 OH Tukang Kayu 95,000 105,000 1,900.00 2,100.00
L.04 0.0060 OH Mandor 100,000 110,000 600.00 660.00
L.05 0.0200 OH Juru Ukur 150,000 175,000 3,000.00 3,500.00
L.06 0.0200 OH Pembantu Juru Ukur 110,000 125,000 2,200.00 2,500.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN 11,250.00 13,500.00
0.0025 m3 Kaso 4x6x4.00 cm 4,500,000 5,400,000 11,250.00 13,500.00
0.0042 m3 Papan 2x20x4.00 cm 4,800,000 5,700,000 20,160.00 23,940.00
0.2000 kg Paku 5CM & 7 CM 15,000 17,500 3,000.00 3,500.00
C PERALATAN 200.00 240.00
0.0040 hr water pass 50,000 60,000 200.00 240.00
D Jumlah A + B + C 23,650.00 27,600.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,365.00 2,760.00
F Harga Satuan Pekerjaan (D+E) 26,015.00 30,360.00

6 T.02.b.2 1 m' PASANG BOUWPLANK 113,245.00 134,530.00


A TENAGA 10,550.00 11,850.00
0.100 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
0.010 OH Tukang Kayu 95,000.00 105,000.00 950.00 1,050.00
0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

B BAHAN 92,400.00 110,450.00


0.013 m3 Kaso 4x6x4.00 cm 4,500,000.00 5,400,000.00 58,500.00 70,200.00
0.007 m3 Papan 2x20x4.00 cm 4,800,000.00 5,700,000.00 33,600.00 39,900.00
0.020 kg Paku 5CM & 7 CM 15,000.00 17,500.00 300.00 350.00
C PERALATAN

D Jumlah A + B + C 102,950.00 122,300.00


E OVERHEAD & PROFIT (CONTOH) 10% 10,295.00 12,230.00
F Harga Satuan Pekerjaan (D+E) 113,245.00 134,530.00

T.03 PENGADAAN DAN PEMASANGAN PATOK


7 T.03.a 1 m' PATOK KAYU (UKURAN 5/7) 12,892.00 15,287.25
A TENAGA 3,120.00 3,577.50
0.025 OH Pekerja 75,000.00 85,000.00 1,875.00 2,125.00
0.0083 OH Juru Ukur 150,000.00 175,000.00 1,245.00 1,452.50

B BAHAN 8,400.00 10,080.00


0.0018 m3 Patok kayu 5/7 (kayu Borneo klas 2 4,500,000.00 5,400,000.00 8,100.00 9,720.00
0.012 doos Paku Payung 25,000.00 30,000.00 300.00 360.00

C PERALATAN 200.00 240.00


0.008 bh Roll Meter 25,000.00 30,000.00 200.00 240.00

D Jumlah A + B + C 11,720.00 13,897.50


E OVERHEAD & PROFIT (CONTOH) 10% 1,172.00 1,389.75
F Harga Satuan Pekerjaan (D+E) 12,892.00 15,287.25

8 T.03.b 1 bh PATOK TETAP BANTU (PBT) 93,196.61 104,018.20


T.06a.1 0.2730 m3 Galian Tanah Biasa 64,625.00 73,150.00 17,642.63 19,969.95
T.14c 0.0030 m3 Timbunan Pasir 237,050.00 332,860.00 711.15 998.58
B.17 2.3000 kg Pembesian 13,268.20 14,317.05 30,516.86 32,929.22
B.22 0.4000 m2 Bekisting LS LS 15,000.00 16,000.00
B.05a 0.0130 m3 Beton (K.175; fc = 14,5 Mpa) 1,044,305.78 1,170,804.12 13,575.98 15,220.45
M.65 1.0500 bh Pen Kuningan untuk Titik Acu Pengukuran 5,000.00 6,000.00 5,250.00 6,300.00
M.126a 1.0500 bh Marmer Ukuran 10 x 10 cm 10,000.00 12,000.00 10,500.00 12,600.00
(tulisan graphir)

93,196.61 104,018.20

9 T.03.c 1 bh PATOK UTAMA TETAP 161,493.41 180,742.31


T.06a.1 0.3000 m3 Galian Tanah Biasa 64,625.00 73,150.00 19,387.50 21,945.00
T.14c 0.0200 m3 Timbunan Pasir 237,050.00 332,860.00 4,741.00 6,657.20
B.17 4.1000 kg Pembesian 13,268.20 14,317.05 54,399.62 58,699.91
B.22 0.8600 m2 Bekisting LS LS 15,000.00 16,000.00
B.05a 0.0500 m3 Beton (K.175; fc = 14,5 Mpa) 1,044,305.78 1,170,804.12 52,215.29 58,540.21
M.65 1.0500 bh Pen Kuningan untuk Titik Acu Pengukuran 5,000.00 6,000.00 5,250.00 6,300.00
M.126a 1.0500 bh Marmer Ukuran 10 x 10 cm 10,000.00 12,000.00 10,500.00 12,600.00
(tulisan graphir)

161,493.41 180,742.31
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
T.06 GALIAN TANAH BIASA
T.06.a CARA MANUAL
10 T.06.a.1 1 m3 GALIAN TANAH BIASA sedalam ≤ 1 m 52,640.50 59,452.80
A TENAGA 47,855.00 54,048.00
L.01 0.5630 OH Pekerja 75,000 85,000 42,225.00 47,855.00
L.04 0.0563 OH Mandor 100,000 110,000 5,630.00 6,193.00

B BAHAN - -
C PERALATAN - -
D Jumlah A + B + C 47,855.00 54,048.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,785.50 5,404.80
F Harga Satuan Pekerjaan (D+E) 52,640.50 59,452.80

11 T.06.a.2 1 m3 GALIAN TANAH BIASA sedalam > 1m s/d 2 m 63,112.50 71,280.00


A TENAGA 57,375.00 64,800.00
L.01 0.6750 OH Pekerja 75,000 85,000 50,625.00 57,375.00
L.04 0.0675 OH Mandor 100,000 110,000 6,750.00 7,425.00

B BAHAN - -
C PERALATAN - -
D Jumlah A + B + C 57,375.00 64,800.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,737.50 6,480.00
F Harga Satuan Pekerjaan (D+E) 63,112.50 71,280.00

12 T.06.a.3 1 m3 GALIAN TANAH BIASA sedalam > 2 m s/d 3 m 71,060.00 80,256.00


A TENAGA 64,600.00 72,960.00
L.01 0.7600 OH Pekerja 75,000 85,000 57,000.00 64,600.00
L.04 0.0760 OH Mandor 100,000 110,000 7,600.00 8,360.00

B BAHAN - -
C PERALATAN - -
D Jumlah A + B + C 64,600.00 72,960.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,460.00 7,296.00
F Harga Satuan Pekerjaan (D+E) 71,060.00 80,256.00

GALIAN TANAH BIASA dg kedalaman > 3 m,


13 T.06.a.4 1 m3 TAMBAHAN KOEFISIEN UNT SETIAP PENAMBAHAN 7,012.50 7,920.00
KEDALAMAN 1 m
A TENAGA 6,375.00 7,200.00
L.01 0.0750 OH Pekerja 75,000 85,000 5,625.00 6,375.00
L.04 0.0075 OH Mandor 100,000 110,000 750.00 825.00

B BAHAN - -
C PERALATAN - -
D Jumlah A + B + C 6,375.00 7,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 637.50 720.00
F Harga Satuan Pekerjaan (D+E) 7,012.50 7,920.00

T.06.b CARA SEMI MEKANIK


14 T.06.b.1 1 m3 GALIAN TANAH BIASA Sedalam ≤ 1 m 25,520.00 26,174.50
A TENAGA 18,700.00 21,120.00
L.01 0.2200 OH Pekerja 75,000 85,000 16,500.00 18,700.00
L.04 0.0220 OH Mandor 100,000 110,000 2,200.00 2,420.00

B BAHAN 3,750.00 1,875.00


0.500 ltr BBM non Subsidi 7,500.00 8,000.00 3,750.00 1,875.00

C PERALATAN 750.00 800.00


0.050 hari Jack Hammer 15,000.00 16,000.00 750.00 800.00

D Jumlah A + B + C 23,200.00 23,795.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,320.00 2,379.50
F Harga Satuan Pekerjaan (D+E) 25,520.00 26,174.50
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

15 T.06.b.2 1 m3 GALIAN TANAH BIASA Sedalam > 1 m sd 2 m 29,260.00 30,398.50


A TENAGA 22,100.00 24,960.00
L.01 0.2600 OH Pekerja 75,000 85,000 19,500.00 22,100.00
L.04 0.0260 OH Mandor 100,000 110,000 2,600.00 2,860.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN 3,750.00 1,875.00
0.500 ltr BBM non Subsidi 7,500.00 8,000.00 3,750.00 1,875.00

C PERALATAN 750.00 800.00


0.050 hari Jack Hammer 15,000.00 16,000.00 750.00 800.00

D Jumlah A + B + C 26,600.00 27,635.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,660.00 2,763.50
F Harga Satuan Pekerjaan (D+E) 29,260.00 30,398.50

16 T.06.b.3 1 m3 GALIAN TANAH BIASA Sedalam > 2 m sd 3 m 33,000.00 34,622.50


A TENAGA 25,500.00 28,800.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN 3,750.00 1,875.00


0.500 ltr BBM non Subsidi 7,500.00 8,000.00 3,750.00 1,875.00

C PERALATAN 750.00 800.00


0.050 hari Jack Hammer 15,000.00 16,000.00 750.00 800.00

D Jumlah A + B + C 30,000.00 31,475.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,000.00 3,147.50
F Harga Satuan Pekerjaan (D+E) 33,000.00 34,622.50

KEDALAMAN YANG > 3 m menggunakan AHSP T.06.b.3


17 T.06.b.4
+ AHSP T.06.a.4 untuk setiap kedalaman 1 m

T.07. GALIAN TANAH BERBATU


T.07.a CARA MANUAL
18 T.07.a.1 1 m3 GALIAN TANAH BERBATU Sedalam ≤ 1 m 126,318.50 142,665.60
A TENAGA 114,835.00 129,696.00
L.01 1.3510 OH Pekerja 75,000 85,000 101,325.00 114,835.00
L.04 0.1351 OH Mandor 100,000 110,000 13,510.00 14,861.00

B BAHAN - -
- - -

C PERALATAN - -
- -

D Jumlah A + B + C 114,835.00 129,696.00


E OVERHEAD & PROFIT (CONTOH) 10% 11,483.50 12,969.60
F Harga Satuan Pekerjaan (D+E) 126,318.50 142,665.60

19 T.07.a.2 1 m3 GALIAN TANAH BERBATU Sedalam > 1 m sd 2 m 140,250.00 158,400.00


A TENAGA 127,500.00 144,000.00
L.01 1.5000 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.04 0.1500 OH Mandor 100,000 110,000 15,000.00 16,500.00

B BAHAN - -
- - -

C PERALATAN - -
- - -

D Jumlah A + B + C 127,500.00 144,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 12,750.00 14,400.00
F Harga Satuan Pekerjaan (D+E) 140,250.00 158,400.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

20 T.07.a.3 1 m3 GALIAN TANAH BERBATU Sedalam > 2 m sd 3 m 154,275.00 174,240.00


A TENAGA 140,250.00 158,400.00
L.01 1.6500 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.04 0.1650 OH Mandor 100,000 110,000 16,500.00 18,150.00

B BAHAN - -
- -

C PERALATAN - -
- -
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
D Jumlah A + B + C 140,250.00 158,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 14,025.00 15,840.00
F Harga Satuan Pekerjaan (D+E) 154,275.00 174,240.00

KEDALAMAN YANG > 3 m menggunakan AHSP T.07.b.3


21 T.07.b
+ AHSP T.07.a.4 untuk setiap kedalaman 1 m

T.07.b CARA SEMI MEKANIK


22 T.07.b.1 1 m3 GALIAN TANAH BERBATU Sedalam ≤ 1 m 52,580.00 60,498.63
A TENAGA 36,550.00 41,280.00
L.01 0.4300 OH Pekerja 75,000 85,000 32,250.00 36,550.00
L.04 0.0430 OH Mandor 100,000 110,000 4,300.00 4,730.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 47,800.00 54,998.75


E OVERHEAD & PROFIT (CONTOH) 10% 4,780.00 5,499.88
F Harga Satuan Pekerjaan (D+E) 52,580.00 60,498.63

23 T.07.b.2 1 m3 GALIAN TANAH BERBATU Sedalam > 1 m sd 2 m 59,125.00 67,890.63


A TENAGA 42,500.00 48,000.00
L.01 0.5000 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.0500 OH Mandor 100,000 110,000 5,000.00 5,500.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 53,750.00 61,718.75


E OVERHEAD & PROFIT (CONTOH) 10% 5,375.00 6,171.88
F Harga Satuan Pekerjaan (D+E) 59,125.00 67,890.63

24 T.07.b.3 1 m3 GALIAN TANAH BERBATU Sedalam > 2 m sd 3 m 63,800.00 73,170.63


A TENAGA 46,750.00 52,800.00
L.01 0.5500 OH Pekerja 75,000 85,000 41,250.00 46,750.00
L.04 0.0550 OH Mandor 100,000 110,000 5,500.00 6,050.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 58,000.00 66,518.75


E OVERHEAD & PROFIT (CONTOH) 10% 5,800.00 6,651.88
F Harga Satuan Pekerjaan (D+E) 63,800.00 73,170.63

KEDALAMAN YANG > 3 m menggunakan AHSP T.07.b.3


25 T.07.b.4
+ AHSP T.07.a.4 untuk setiap kedalaman 1 m
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

T.08. GALIAN BATU


T.08.a CARA MANUAL
26 T.08.a.1 1 m3 GALIAN BATU Sedalam ≤ 1 m 315,843.00 356,716.80
A TENAGA 287,130.00 324,288.00
L.01 3.3780 OH Pekerja 75,000 85,000 253,350.00 287,130.00
L.04 0.3378 OH Mandor 100,000 110,000 33,780.00 37,158.00

B BAHAN - -
- - -

C PERALATAN - -
- -

D Jumlah A + B + C 287,130.00 324,288.00


[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
E OVERHEAD & PROFIT (CONTOH) 10% 28,713.00 32,428.80
F Harga Satuan Pekerjaan (D+E) 315,843.00 356,716.80

27 T.08.a.2 1 m3 GALIAN BATU Sedalam > 1 m sd 2 m 350,075.00 395,395.00


A TENAGA 318,250.00 359,450.00
L.01 3.7500 OH Pekerja 75,000 85,000 281,250.00 318,750.00
L.04 0.3700 OH Mandor 100,000 110,000 37,000.00 40,700.00

B BAHAN - -
- - -

C PERALATAN - -
- - -

D Jumlah A + B + C 318,250.00 359,450.00


E OVERHEAD & PROFIT (CONTOH) 10% 31,825.00 35,945.00
F Harga Satuan Pekerjaan (D+E) 350,075.00 395,395.00

28 T.08.a.3 1 m3 GALIAN BATU Sedalam > 2 m sd 3 m 385,687.50 435,600.00


A TENAGA 350,625.00 396,000.00
L.01 4.1250 OH Pekerja 75,000 85,000 309,375.00 350,625.00
L.04 0.4125 OH Mandor 100,000 110,000 41,250.00 45,375.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 350,625.00 396,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 35,062.50 39,600.00
F Harga Satuan Pekerjaan (D+E) 385,687.50 435,600.00

KEDALAMAN YANG > 3 m untuk setiap penambahan


29 T.08.b.4 1 m3 35,062.50 39,600.00
kedalaman 1 m
A TENAGA 31,875.00 36,000.00
L.01 0.3750 OH Pekerja 75,000 85,000 28,125.00 31,875.00
L.04 0.0375 OH Mandor 100,000 110,000 3,750.00 4,125.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 31,875.00 36,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,187.50 3,600.00
F Harga Satuan Pekerjaan (D+E) 35,062.50 39,600.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
T.08.b CARA SEMI MEKANIK
30 T.08.b.1 1 m3 GALIAN BATU Sedalam ≤ 1 m 118,250.00 161,562.50
A TENAGA 85,000.00 96,000.00
L.01 1.0000 OH Pekerja 75,000 85,000 75,000.00 85,000.00
L.04 0.1000 OH Mandor 100,000 110,000 10,000.00 11,000.00

B BAHAN 18,750.00 46,875.00


2.500 ltr BBM non Subsidi 7,500.00 8,000.00 18,750.00 46,875.00

C PERALATAN 3,750.00 4,000.00


0.250 hari Jack Hammer 15,000.00 16,000.00 3,750.00 4,000.00

D Jumlah A + B + C 107,500.00 146,875.00


E OVERHEAD & PROFIT (CONTOH) 10% 10,750.00 14,687.50
F Harga Satuan Pekerjaan (D+E) 118,250.00 161,562.50
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

31 T.08.b.2 1 m3 GALIAN BATU Sedalam > 1 m sd 2 m 136,950.00 182,682.50


A TENAGA 102,000.00 115,200.00
L.01 1.2000 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.04 0.1200 OH Mandor 100,000 110,000 12,000.00 13,200.00

B BAHAN 18,750.00 46,875.00


2.500 ltr BBM non Subsidi 7,500.00 8,000.00 18,750.00 46,875.00

C PERALATAN 3,750.00 4,000.00


0.250 hari Jack Hammer 15,000.00 16,000.00 3,750.00 4,000.00

D Jumlah A + B + C 124,500.00 166,075.00


E OVERHEAD & PROFIT (CONTOH) 10% 12,450.00 16,607.50
F Harga Satuan Pekerjaan (D+E) 136,950.00 182,682.50

32 T.08.b.3 1 m3 GALIAN BATU Sedalam > 2 m sd 3 m 148,170.00 195,354.50


A TENAGA 112,200.00 126,720.00
L.01 1.3200 OH Pekerja 75,000 85,000 99,000.00 112,200.00
L.04 0.1320 OH Mandor 100,000 110,000 13,200.00 14,520.00

B BAHAN 18,750.00 46,875.00


2.500 ltr BBM non Subsidi 7,500.00 8,000.00 18,750.00 46,875.00

C PERALATAN 3,750.00 4,000.00


0.250 hari Jack Hammer 15,000.00 16,000.00 3,750.00 4,000.00

D Jumlah A + B + C 134,700.00 177,595.00


E OVERHEAD & PROFIT (CONTOH) 10% 13,470.00 17,759.50
F Harga Satuan Pekerjaan (D+E) 148,170.00 195,354.50

KEDALAMAN YANG > 3 m menggunakan AHSP T.08.b.3


33 T.08.b.4
+ AHSP T.08.a.4 untuk setiap kedalaman 1 m

T.09 GALIAN TANAH CADAS ATAU TANAH KERAS


T.09.a CARA MANUAL

GALIAN TANAH CADAS ATAU TANAH KERAS BATU


34 T.09.a.1 1 m3 116,875.00 132,000.00
Sedalam ≤ 1 m

A TENAGA 106,250.00 120,000.00


L.01 1.2500 OH Pekerja 75,000 85,000 93,750.00 106,250.00
L.04 0.1250 OH Mandor 100,000 110,000 12,500.00 13,750.00

B BAHAN - -
- - -

C PERALATAN - -
- -

D Jumlah A + B + C 106,250.00 120,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 10,625.00 12,000.00
F Harga Satuan Pekerjaan (D+E) 116,875.00 132,000.00

GALIAN TANAH CADAS ATAU TANAH KERAS Sedalam


35 T.09.a.2 1 m3 130,152.00 146,995.20
> 1 m sd 2 m

A TENAGA 118,320.00 133,632.00


L.01 1.3920 OH Pekerja 75,000 85,000 104,400.00 118,320.00
L.04 0.1392 OH Mandor 100,000 110,000 13,920.00 15,312.00

B BAHAN - -
- - -

C PERALATAN - -
- - -

D Jumlah A + B + C 118,320.00 133,632.00


E OVERHEAD & PROFIT (CONTOH) 10% 11,832.00 13,363.20
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
F Harga Satuan Pekerjaan (D+E) 130,152.00 146,995.20

GALIAN TANAH CADAS ATAU TANAH KERAS BATU


36 T.09.a.3 1 m3 140,250.00 158,400.00
Sedalam > 2 m sd 3 m
A TENAGA 127,500.00 144,000.00
L.01 1.5000 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.04 0.1500 OH Mandor 100,000 110,000 15,000.00 16,500.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 127,500.00 144,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 12,750.00 14,400.00
F Harga Satuan Pekerjaan (D+E) 140,250.00 158,400.00

GALIAN TANAH CADAS ATAU TANAH KERAS > 3 m


37 T.09.b.4 1 m3 9,350.00 10,560.00
untuk setiap penambahan kedalaman 1 m

A TENAGA 8,500.00 9,600.00


L.01 0.1000 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.0100 OH Mandor 100,000 110,000 1,000.00 1,100.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 8,500.00 9,600.00


E OVERHEAD & PROFIT (CONTOH) 10% 850.00 960.00
F Harga Satuan Pekerjaan (D+E) 9,350.00 10,560.00

T.09.b CARA SEMI MEKANIS


GALIAN TANAH CADAS ATAU TANAH KERAS BATU
38 T.09.b.1 1 m3 129,250.00 147,090.63
Sedalam ≤ 1 m
A TENAGA 106,250.00 120,000.00
L.01 1.2500 OH Pekerja 75,000 85,000 93,750.00 106,250.00
L.04 0.1250 OH Mandor 100,000 110,000 12,500.00 13,750.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 117,500.00 133,718.75


E OVERHEAD & PROFIT (CONTOH) 10% 11,750.00 13,371.88
F Harga Satuan Pekerjaan (D+E) 129,250.00 147,090.63
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

GALIAN TANAH CADAS ATAU TANAH KERAS Sedalam


39 T.09.b.2 1 m3 51,645.00 59,442.63
> 1 m sd 2 m
A TENAGA 35,700.00 40,320.00
L.01 0.4200 OH Pekerja 75,000 85,000 31,500.00 35,700.00
L.04 0.0420 OH Mandor 100,000 110,000 4,200.00 4,620.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 46,950.00 54,038.75


E OVERHEAD & PROFIT (CONTOH) 10% 4,695.00 5,403.88
F Harga Satuan Pekerjaan (D+E) 51,645.00 59,442.63

GALIAN TANAH CADAS ATAU TANAH KERAS BATU


40 T.09.b.3 1 m3 59,125.00 67,890.63
Sedalam > 2 m sd 3 m
A TENAGA 42,500.00 48,000.00
L.01 0.5000 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.0500 OH Mandor 100,000 110,000 5,000.00 5,500.00

B BAHAN 9,375.00 11,718.75


1.250 ltr BBM non Subsidi 7,500.00 8,000.00 9,375.00 11,718.75

C PERALATAN 1,875.00 2,000.00


0.125 hari Jack Hammer 15,000.00 16,000.00 1,875.00 2,000.00

D Jumlah A + B + C 53,750.00 61,718.75


E OVERHEAD & PROFIT (CONTOH) 10% 5,375.00 6,171.88
F Harga Satuan Pekerjaan (D+E) 59,125.00 67,890.63

KEDALAMAN YANG > 3 m menggunakan AHSP T.09.b.3


41 T.09.b.4 1 m3
+ AHSP T.09.a.4

T.10 GALIAN LUMPUR


T.10.a CARA MANUAL
42 T.10.a.1 1 m3 GALIAN LUMPUR SEDALAM ≤ 1 M 77,605.00 87,648.00
A TENAGA 70,550.00 79,680.00
L.01 0.8300 OH Pekerja 75,000 85,000 62,250.00 70,550.00
L.04 0.0830 OH Mandor 100,000 110,000 8,300.00 9,130.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 70,550.00 79,680.00


E OVERHEAD & PROFIT (CONTOH) 10% 7,055.00 7,968.00
F Harga Satuan Pekerjaan (D+E) 77,605.00 87,648.00

43 T.10.a.2 1 m3 GALIAN LUMPUR Sedalam > 1 m sd 2 m 93,500.00 105,600.00


A TENAGA 85,000.00 96,000.00
L.01 1.0000 OH Pekerja 75,000 85,000 75,000.00 85,000.00
L.04 0.1000 OH Mandor 100,000 110,000 10,000.00 11,000.00

B BAHAN - -
- - -

C PERALATAN - -
- - -

D Jumlah A + B + C 85,000.00 96,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 8,500.00 9,600.00
F Harga Satuan Pekerjaan (D+E) 93,500.00 105,600.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
44 T.10.a.3 1 m3 GALIAN LUMPUR Sedalam > 2 m sd 3 m 107,525.00 121,440.00
A TENAGA 97,750.00 110,400.00
L.01 1.1500 OH Pekerja 75,000 85,000 86,250.00 97,750.00
L.04 0.1150 OH Mandor 100,000 110,000 11,500.00 12,650.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 97,750.00 110,400.00


E OVERHEAD & PROFIT (CONTOH) 10% 9,775.00 11,040.00
F Harga Satuan Pekerjaan (D+E) 107,525.00 121,440.00

GALIAN LUMPUR > 3 m untuk setiap penambahan


45 T.10.a.4 1 m3 14,025.00 15,840.00
kedalaman 1 m
A TENAGA 12,750.00 14,400.00
L.01 0.1500 OH Pekerja 75,000 85,000 11,250.00 12,750.00
L.04 0.0150 OH Mandor 100,000 110,000 1,500.00 1,650.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 12,750.00 14,400.00


E OVERHEAD & PROFIT (CONTOH) 10% 1,275.00 1,440.00
F Harga Satuan Pekerjaan (D+E) 14,025.00 15,840.00

T.10.b CARA SEMI MEKANIK


46 T.10.b.1 1 m3 GALIAN LUMPUR SEDALAM ≤ 1 M 33,495.00 36,531.00
A TENAGA 20,400.00 23,040.00
L.01 0.2400 OH Pekerja 75,000 85,000 18,000.00 20,400.00
L.04 0.0240 OH Mandor 100,000 110,000 2,400.00 2,640.00

B BAHAN 6,300.00 5,670.00


0.900 ltr Solar non Subsidi 7,000.00 7,200.00 6,300.00 5,670.00

C PERALATAN 3,750.00 4,500.00


0.150 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 3,750.00 4,500.00

D Jumlah A + B + C 30,450.00 33,210.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,045.00 3,321.00
F Harga Satuan Pekerjaan (D+E) 33,495.00 36,531.00

47 T.10.b.2 1 m3 GALIAN LUMPUR Sedalam > 1 m sd 2 m 36,531.00 41,057.28


A TENAGA 22,950.00 25,920.00
L.01 0.2700 OH Pekerja 75,000 85,000 20,250.00 22,950.00
L.04 0.0270 OH Mandor 100,000 110,000 2,700.00 2,970.00

B BAHAN 7,560.00 8,164.80


1.080 ltr Solar non Subsidi 7,000.00 7,200.00 7,560.00 8,164.80

C PERALATAN 2,700.00 3,240.00


0.108 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 2,700.00 3,240.00

D Jumlah A + B + C 33,210.00 37,324.80


E OVERHEAD & PROFIT (CONTOH) 10% 3,321.00 3,732.48
F Harga Satuan Pekerjaan (D+E) 36,531.00 41,057.28
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
48 T.10.b.3 1 m3 GALIAN LUMPUR Sedalam > 2 m sd 3 m 41,376.50 48,924.48
A TENAGA 25,075.00 28,320.00
L.01 0.2950 OH Pekerja 75,000 85,000 22,125.00 25,075.00
L.04 0.0295 OH Mandor 100,000 110,000 2,950.00 3,245.00

B BAHAN 9,240.00 12,196.80


1.320 ltr Solar non Subsidi 7,000.00 7,200.00 9,240.00 12,196.80

C PERALATAN 3,300.00 3,960.00


0.132 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 3,300.00 3,960.00

D Jumlah A + B + C 37,615.00 44,476.80


E OVERHEAD & PROFIT (CONTOH) 10% 3,761.50 4,447.68
F Harga Satuan Pekerjaan (D+E) 41,376.50 48,924.48

GALIAN LUMPUR > 3 m untuk setiap penambahan


49 T.10.b.4 1 m3 4,818.00 5,332.80
kedalaman 1 m

A TENAGA 1,700.00 1,920.00


L.01 0.0200 OH Pekerja 75,000 85,000 1,500.00 1,700.00
L.04 0.0020 OH Mandor 100,000 110,000 200.00 220.00

B BAHAN 1,680.00 1,728.00


0.240 ltr Solar non Subsidi 7,000.00 7,200.00 1,680.00 1,728.00

C PERALATAN 1,000.00 1,200.00


0.040 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 1,000.00 1,200.00

D Jumlah A + B + C 4,380.00 4,848.00


E OVERHEAD & PROFIT (CONTOH) 10% 438.00 484.80
F Harga Satuan Pekerjaan (D+E) 4,818.00 5,332.80

T.11 GALIAN PASIR


T.11.a CARA MANUAL
50 T.11.a.1 1 m3 GALIAN PASIR SEDALAM ≤ 1 M
A TENAGA 56,100.00 63,360.00
L.01 0.6600 OH Pekerja 75,000 85,000 49,500.00 56,100.00
L.04 0.0660 OH Mandor 100,000 110,000 6,600.00 7,260.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 56,100.00 63,360.00


E OVERHEAD & PROFIT (CONTOH) 10% 5,610.00 6,336.00
F Harga Satuan Pekerjaan (D+E) 61,710.00 69,696.00

51 T.11.a.2 1 m3 GALIAN PASIR Sedalam > 1 m sd 2 m 74,800.00 84,480.00


A TENAGA 68,000.00 76,800.00
L.01 0.8000 OH Pekerja 75,000 85,000 60,000.00 68,000.00
L.04 0.0800 OH Mandor 100,000 110,000 8,000.00 8,800.00

B BAHAN - -
- - -

C PERALATAN - -
- - -

D Jumlah A + B + C 68,000.00 76,800.00


E OVERHEAD & PROFIT (CONTOH) 10% 6,800.00 7,680.00
F Harga Satuan Pekerjaan (D+E) 74,800.00 84,480.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
52 T.11.a.3 1 m3 GALIAN PASIR Sedalam > 2 m sd 3 m 86,020.00 97,152.00
A TENAGA 78,200.00 88,320.00
L.01 0.9200 OH Pekerja 75,000 85,000 69,000.00 78,200.00
L.04 0.0920 OH Mandor 100,000 110,000 9,200.00 10,120.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 78,200.00 88,320.00


E OVERHEAD & PROFIT (CONTOH) 10% 7,820.00 8,832.00
F Harga Satuan Pekerjaan (D+E) 86,020.00 97,152.00

GALIAN PASIR > 3 m untuk setiap penambahan


53 T.11.a.4 1 m3 9,350.00 10,560.00
kedalaman 1 m
A TENAGA 8,500.00 9,600.00
L.01 0.1000 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.0100 OH Mandor 100,000 110,000 1,000.00 1,100.00

B BAHAN - -
- -

C PERALATAN - -
- -

D Jumlah A + B + C 8,500.00 9,600.00


E OVERHEAD & PROFIT (CONTOH) 10% 850.00 960.00
F Harga Satuan Pekerjaan (D+E) 9,350.00 10,560.00

T.11.b CARA SEMI MEKANIK


54 T.11.b.1 1 m3 GALIAN PASIR SEDALAM ≤ 1 M 34,870.00 39,347.00
A TENAGA 21,250.00 24,000.00
L.01 0.2500 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.04 0.0250 OH Mandor 100,000 110,000 2,500.00 2,750.00

B BAHAN 7,700.00 8,470.00


1.100 ltr Solar non Subsidi 7,000.00 7,200.00 7,700.00 8,470.00

C PERALATAN 2,750.00 3,300.00


0.110 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 2,750.00 3,300.00

D Jumlah A + B + C 31,700.00 35,770.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,170.00 3,577.00
F Harga Satuan Pekerjaan (D+E) 34,870.00 39,347.00

55 T.11.b.2 1 m3 GALIAN PASIR Sedalam > 1 m sd 2 m 36,740.00 45,804.00


A TENAGA 22,525.00 25,440.00
L.01 0.2650 OH Pekerja 75,000 85,000 19,875.00 22,525.00
L.04 0.0265 OH Mandor 100,000 110,000 2,650.00 2,915.00

B BAHAN 10,500.00 15,750.00


1.500 ltr Solar non Subsidi 7,000.00 7,200.00 10,500.00 15,750.00

C PERALATAN 375.00 450.00


0.015 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 375.00 450.00

D Jumlah A + B + C 33,400.00 41,640.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,340.00 4,164.00
F Harga Satuan Pekerjaan (D+E) 36,740.00 45,804.00
[Path]

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
56 T.11.b.3 1 m3 GALIAN PASIR Sedalam > 2 m sd 3 m 44,990.00 60,456.00
A TENAGA 23,800.00 26,880.00
L.01 0.2800 OH Pekerja 75,000 85,000 21,000.00 23,800.00
L.04 0.0280 OH Mandor 100,000 110,000 2,800.00 3,080.00

B BAHAN 12,600.00 22,680.00


1.800 ltr Solar non Subsidi 7,000.00 7,200.00 12,600.00 22,680.00

C PERALATAN 4,500.00 5,400.00


0.180 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 4,500.00 5,400.00

D Jumlah A + B + C 40,900.00 54,960.00


E OVERHEAD & PROFIT (CONTOH) 10% 4,090.00 5,496.00
F Harga Satuan Pekerjaan (D+E) 44,990.00 60,456.00

GALIAN PASIR > 3 m untuk setiap penambahan


57 T.11.b.4 1 m3 4,350.50 4,804.80
kedalaman 1 m

A TENAGA 1,275.00 1,440.00


L.01 0.0150 OH Pekerja 75,000 85,000 1,125.00 1,275.00
L.04 0.0015 OH Mandor 100,000 110,000 150.00 165.00

B BAHAN 1,680.00 1,728.00


0.240 ltr Solar non Subsidi 7,000.00 7,200.00 1,680.00 1,728.00

C PERALATAN 1,000.00 1,200.00


0.040 hari Pompa Lumpur Diesel 2,5 kw : 3" 25,000.00 30,000.00 1,000.00 1,200.00

D Jumlah A + B + C 3,955.00 4,368.00


E OVERHEAD & PROFIT (CONTOH) 10% 395.50 436.80
F Harga Satuan Pekerjaan (D+E) 4,350.50 4,804.80
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

PASANGAN 2 LAPIS SESEG BAMBU, JAT (JARAK ANTAR


58 T.12.a (K.3) 1 m2 38,087.50 42,160.25
TIANG) ≤ 1,0 m'

A TENAGA 3,700.00 4,110.00


L.01 0.010 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.030 OH Tukang 95,000.00 105,000.00 2,850.00 3,150.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B BAHAN * 30,425.00 33,617.50
1.127 m2 Seseg bambu 25,000.00 27,500.00 28,175.00 30,992.50
0.150 kg Paku 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN ** 500.00 600.00
0.02 hr Tripod/Tackle Handle/Crane 2 ton 25,000.00 30,000.00 500.00 600.00
D Jumlah A + B + C 34,625.00 38,327.50
E OVERHEAD & PROFIT (CONTOH) 10% 3,462.50 3,832.75
F Harga Satuan Pekerjaan (D+E) 38,087.50 42,160.25

catatan :
** coret yang tidak perlu sesuai rencana pelaksanaan di lapangan
* bahan yang digunakan berulang kali
ke - 1 ; koefisien seseg bambu 2,200
ke - 2 ; koefisien seseg bambu 1,485
ke - 3 ; koefisien seseg bambu 1,127

59 T.12.b (K.3) 1 m2 PASANGAN PAPAN 3/20, JAT ≤ 1,50 m' 61,818.90 72,631.35

A TENAGA 9,250.00 10,275.00


L.01 0.025 OH Pekerja 75,000.00 85,000.00 1,875.00 2,125.00
L.02 0.075 OH Tukang 95,000.00 105,000.00 7,125.00 7,875.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B BAHAN * 46,449.00 55,153.50
0.00963 m3 Kayu Papan klas 2 (Borneo) 4,800,000.00 5,700,000.00 46,224.00 54,891.00
0.015 kg Paku 15,000.00 17,500.00 225.00 262.50
C PERALATAN ** 500.00 600.00
0.02 hr Tripod/Tackle Handle/Crane 2 ton 25,000.00 30,000.00 500.00 600.00
D Jumlah A + B + C 56,199.00 66,028.50
E OVERHEAD & PROFIT (CONTOH) 10% 5,619.90 6,602.85
F Harga Satuan Pekerjaan (D+E) 61,818.90 72,631.35

catatan :
** coret yang tidak perlu sesuai rencana pelaksanaan di lapangan 43a
* bahan yang digunakan berulang kali
ke - 1 ; koefisien menjadi kayu papan 0,0321
ke - 2 ; koefisien menjadi kayu papan 0,01926
ke - 3 ; koefisien menjadi kayu papan 0,01284
ke - 4 ; koefisien menjadi kayu papan 0,00963

60 T.12.c (K.3) 1 m2 PASANGAN BALOK KAYU 8/12 , JAT 4 m' 185,399.50 208,102.95

A TENAGA 15,540.00 17,262.00


L.01 0.042 OH Pekerja 75,000.00 85,000.00 3,150.00 3,570.00
L.02 0.126 OH Tukang 95,000.00 105,000.00 11,970.00 13,230.00
L.04 0.0042 OH Mandor 100,000.00 110,000.00 420.00 462.00
B BAHAN * 152,505.00 171,322.50
0.01160 m3 Kayu balok klas 2 (Borneo) 4,500,000.00 5,400,000.00 52,200.00 62,640.00
0.015 kg Paku 15,000.00 17,500.00 225.00 262.50
8.34 buah Baud Ø 12 - 20 cm 12,000.00 13,000.00 100,080.00 108,420.00
C PERALATAN ** 500.00 600.00
0.02 hr Tripod/Tackle Handle/Crane 2 ton 25,000.00 30,000.00 500.00 600.00
D Jumlah A + B + C 168,545.00 189,184.50
E OVERHEAD & PROFIT (CONTOH) 10% 16,854.50 18,918.45
F Harga Satuan Pekerjaan (D+E) 185,399.50 208,102.95
catatan :
** coret yang tidak perlu sesuai rencana pelaksanaan di lapangan
* bahan yang digunakan berulang kali
ke - 1 ; koefisien menjadi kayu balok 0,084
ke - 2 ; koefisien menjadi kayu balok 0,0454
ke - 3 ; koefisien menjadi kayu balok 0,0261
ke - 4 ; koefisien menjadi kayu balok 0,0164
ke - 5 ; koefisien menjadi kayu balok 0,0116
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
44a
61 T.12.d (K.3) 1 m2 PASANGAN BALOK KAYU 8/12 , JAT ≤ 6 m' 193,539.50 217,144.95
A TENAGA 22,940.00 25,482.00
L.01 0.062 OH Pekerja 75,000.00 85,000.00 4,650.00 5,270.00
L.02 0.186 OH Tukang 95,000.00 105,000.00 17,670.00 19,530.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
L.04 0.0062 OH Mandor 100,000.00 110,000.00 620.00 682.00
B BAHAN * 152,505.00 171,322.50
0.01160 m3 Kayu balok klas 2 (Borneo) 4,500,000.00 5,400,000.00 52,200.00 62,640.00
0.015 kg Paku 15,000.00 17,500.00 225.00 262.50
8.34 buah Baud Ø 12 - 20 cm 12,000.00 13,000.00 100,080.00 108,420.00
C PERALATAN ** 500.00 600.00
0.02 hr Tripod/Tackle Handle/Crane 2 ton 25,000.00 30,000.00 500.00 600.00
D Jumlah A + B + C 175,945.00 197,404.50
E OVERHEAD & PROFIT (CONTOH) 10% 17,594.50 19,740.45
F Harga Satuan Pekerjaan (D+E) 193,539.50 217,144.95

catatan :
** coret yang tidak perlu sesuai rencana pelaksanaan di lapangan
* bahan yang digunakan berulang kali
ke - 1 ; koefisien menjadi kayu balok 0,126
ke - 2 ; koefisien menjadi kayu balok 0,0681
ke - 3 ; koefisien menjadi kayu balok 0,0391
ke - 4 ; koefisien menjadi kayu balok 0,0246
ke - 5 ; koefisien menjadi kayu balok 0,0174
T.12 PERKUATAN DINDING GALIAN

Penggunaan perkuatan dinding galian dilakukan dalam rangka sistem manajemen keselamatan dan kesehatan kerja (SMK3). Sesuai dengan Peraturan Menteri PU
No.5/PRT/M/2014 tentang SMK3.Keperluan Konstruksi perkuatan dinding disesuaikan dengan ketentuan pada spesifikasi teknis, jika tidak ditentukan perlu mempertimbangkan
hal-hal sebagai berikut :

a). perkuatan diding galian sangat tergantung pada potensi kelongsoran dinding galian tanahnya, untuk tanah cadas/keras apabila batu pada umumnya tidak diperlukan
perkuatan, Hal ini sering dilakukan pada tanah biasa, tanah berbatu atau pada galian yang mempunyai potensi longsor terutama jika kedalaman galiannya lebih dari 2 m.
Namun prakteknya galian saluran ataupun pemasangan pipa, gorong-gorong ataui box culvert untuk kedalaman galian > 1 m' saja biasa dilakukan perkuatan dinding galian.

b). Pelaksanaan perkuatan dinding galian, umumnya hanya bersifat sementara saja sehingga konstruksi perkuatan dinding galian ini setelah selesai terus dilakukan pencabutan
dan pemindahan ke ruas pekerjaan yang lainnya. Sehubungan dengan hal tersebut, beberapa jenis material sering terjadi kerusakan sehingga diperlukan penambahan material
disesuaikan dengan potensi kerusakannya.

Dengan asumsi pemakian bahan / material secara berulang, penggunaan material dihitung berdasarkan Tabel II.A.1 berikut ini :
Tabel II.A.1 Koefisien Penggunaan Berulang Bahan/Material

Penggunaan Material Keterangan


NO. PEMAKAIAN
0,4% 1% 3% 8% 10% 15% 20% 35% 0,4 % untuk baja / besi knockdown scafolding
1 Pertama 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1% untuk baja / besi profil
2 Ke - dua 0.502 0.506 0.515 0.540 0.550 0.575 0.600 0.675 3% untuk baja / besi pelat
3 Ke - tiga 0.253 0.258 0.273 0.310 0.325 0.363 0.400 0.513 8% untuk bahan kayu balok
4 Ke - empat 0.129 0.134 0.152 0.195 0.213 0.257 0.300 0.432 10% untuk bahan kayu kayu kaso atau dolken
5 Ke - lima 0.067 0.072 0.091 0.138 0.157 0.204 0.250 0.391 15% untuk bahan multipleks

20% untuk kayu papan atau bambu


35% untuk seseg bambu
TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN RANGKA & DINDING

A.2 a) TIANG RANGKA PERKUATAN DINDING


NO. BAHAN 1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m' JARAK

a) b) c) d) e) f) g) h) i) j) TIANG

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)

1 KASO 5/7 DIPAKAI 1 KALI 0.04200 m3 OH OH OH 0.125 0.0150 m3 OH OH OH 0.5

- DIPAKAI KE 2 0.02840 m3 0.860 0.430 0.086 0.0101 m3 0.800 0.300 0.080 0.120
- DIPAKAI KE 3 0.02380 m3 0.0085 m3

2 BAJA L.50.50.5 7.420 kg 4.950 kg

4.080 kg 1.000 OH 0.500 OH 0.100 OH 0.120 2.720 kg 0.72 OH 0.38 OH 0.072 OH 0.110 0.8

2.970 kg 1.980 kg

3 BAJA INP - 10 13.100 kg 4.950 kg

7.200 kg 1.200 OH 0.600 OH 0.120 OH 0.100 2.720 kg 0.86 OH 0.43 OH 0.086 OH 0.090 1
5.240 kg 1.980 kg

b) DINDING PERKUATAN

NO. BAHAN 1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m'

a) b) c) d) e) f) g) h) i) j)

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN

1 SESEG BAMBU KE-1 2.40 m2 OH OH OH 0.06 2.00 m2 OH OH OH

KE-2 1.80 m2 0.400 0.200 0.040 1.50 m2 0.300 0.150 0.030 0.050

KE-3 1.60 m2 1.33 m2

2 PAPAN 2/20 KE-1 0.048 m3 0.040 m3


KE-2 0.034 m3 0.500 OH 0.250 OH 0.050 OH 0.06 0.028 m3 0.376 OH 0.188 OH 0.0375 OH 0.070

KE-3 0.029 m3 0.024 m3

3 BALOK KAYU 8/12 KE-1 0.192 m3 0.180 m3


KE-2 0.130 m3 0.480 OH 0.230 OH 0.045 OH 0.09 0.108 m3 0.338 OH 0.169 OH 0.0338 OH 0.080

KE-3 0.109 m3 0.091 m3

TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN TURAP
A.3

NO. BAHAN 1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m' JARAK

a) b) c) d) e) f) g) h) i) j) TIANG

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)
1 KASO 5/7 DIPAKAI KE-1 0.049612 m3 OH OH OH 0.10 0.033075 m3 OH OH OH 5

KE-2 0.033488 m3 0.840 0.280 0.084 0.022326 m3 0.570 0.190 0.057 0.070
KE-3 0.028130 m3 0.018754 m3

2 BALOK KAYU 8/12 KE-1 0.090720 m3 0.080480 m3

KE-2 0.061236 m3 1.280 OH 0.420 OH 0.126 OH 0.12 0.040824 m3 0.84 OH 0.28 OH 0.064 OH 0.06 5

KE-3 0.051438 m3 0.034292 m3


3 BAJA INP - 8 37.50 kg 25.00 kg

20.62 kg 1.500 oh 0.500 OH 0.150 OH 0.15 13.75 kg 1.2 OH 0.4 OH 0.12 OH 0.11 5

15.00 kg 10.00 kg
4 BAJA INP-10 52.500 kg 35.000 kg

28.860 kg 2.100 OH 0.700 OH 0.210 OH 0.160 19.220 kg 1.5 OH 0.5 OH 0.15 OH 0.120 5

21.000 kg 14.000 kg

5 PROFIL LARSEN U-400 71.860 kg 47.910 kg


39.520 kg 3.000 OH 1.000 OH 0.300 OH 0.240 26.350 kg 2.1 OH 0.7 OH 0.21 OH 0.180 5

28.750 kg 19.160 kg
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

T.14 TIMBUNAN DAN PEMADATAN


62 T.14.a.1 1 m3 TIMBUNAN TANAH ATAU URUGAN TANAH KEMBALI 30,855.00 34,848.00
A TENAGA 28,050.00 31,680.00
L.01 0.330 OH Pekerja 75,000 85,000 24,750.00 28,050.00
L.04 0.033 OH Mandor 100,000 110,000 3,300.00 3,630.00
B BAHAN - -

C PERALATAN - -

D Jumlah A + B + C 28,050.00 31,680.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,805.00 3,168.00
F Harga Satuan Pekerjaan (D+E) 30,855.00 34,848.00

63 T.14.b.1 1 m3 PEMADATAN TANAH 48,950.00 55,550.00


A TENAGA 42,500.00 48,000.00
L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00
B BAHAN - -
- -
C PERALATAN 2,000.00 2,500.00
0.050 hr Pemadatan tanah (Stamper) 40,000 50,000 2,000.00 2,500.00
D Jumlah A + B + C 44,500.00 50,500.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,450.00 5,050.00
F Harga Satuan Pekerjaan (D+E) 48,950.00 55,550.00

64 T.14.c.1 1 m3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI 453,200.00 530,640.00


A TENAGA 34,000.00 38,400.00
L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 378,000.00 444,000.00
1.200 m3 Pasir Pasang 315,000 370,000 378,000.00 444,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 412,000.00 482,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 41,200.00 48,240.00
F Harga Satuan Pekerjaan (D+E) 453,200.00 530,640.00

65 T.14.d 1 m3 PEMADATAN PASIR SEBAGAI BAHAN PENGISI 13,750.00 16,060.00


A TENAGA 8,500.00 9,600.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
B BAHAN - -
- - -
C PERALATAN 4,000.00 5,000.00
0.100 hr Pemadatan tanah (Stamper) 40,000 50,000 4,000.00 5,000.00
D Jumlah A + B + C 12,500.00 14,600.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,250.00 1,460.00
F Harga Satuan Pekerjaan (D+E) 13,750.00 16,060.00

T.15 ANGKUTAN MATERIAL DAN ATAU GALIAN

Koefisien pada AHSP T.15.a adalah kondisi normal, untuk hal khusus seperti angkutan melalui sungai dengan kedalaman s/d 0,5 m dikalikan 1,2; sedang untuk kedalaman
sungai 1 m dikalikan 1,5

T.15.a. ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK JARAK HARIZONTAL (DATAR)
AHSP T.15.a ini berlaku pada angkutan material untuk jarak harizontal (datar) dan termasuk juga medan dengan pelandaian menurun 1V:5H sampai dengan pelandaian
1V:10H yang dihitung sebagai panjang lintasannya.
MENGANGKUT MATERIAL ATAU DAN HASIL GALIAN DG
66 T.15.a.1 1 m3 21,824.00 24,688.40
JARAK ANGKUT 5 m
A TENAGA 19,840.00 22,444.00
L.01 0.2480 OH Pekerja 75,000 85,000 18,600.00 21,080.00
L.04 0.0124 OH Mandor 100,000 110,000 1,240.00 1,364.00
B BAHAN - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -

D Jumlah A + B + C 19,840.00 22,444.00


E OVERHEAD & PROFIT (CONTOH) 10% 1,984.00 2,244.40
F Harga Satuan Pekerjaan (D+E) 21,824.00 24,688.40

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


67 T.15.a.2 1 m3 24,183.50 27,358.10
JARAK ANGKUT 10 m
A TENAGA 21,985.00 24,871.00
L.01 0.2750 OH Pekerja 75,000 85,000 20,625.00 23,375.00
L.04 0.0136 OH Mandor 100,000 110,000 1,360.00 1,496.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 21,985.00 24,871.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,198.50 2,487.10
F Harga Satuan Pekerjaan (D+E) 24,183.50 27,358.10

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


68 T.15.a.3 1 m3 27,725.50 31,364.30
JARAK ANGKUT 20 m

A TENAGA 25,205.00 28,513.00


L.01 0.3150 OH Pekerja 75,000 85,000 23,625.00 26,775.00
L.04 0.0158 OH Mandor 100,000 110,000 1,580.00 1,738.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 25,205.00 28,513.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,520.50 2,851.30
F Harga Satuan Pekerjaan (D+E) 27,725.50 31,364.30

MENGANGKUT MATERIAL DAN ATAU HASIL HASIL


69 T.15.a.4 1 m3 31,328.00 35,439.80
GALIAN DG JARAK ANGKUT 30 m
A TENAGA 28,480.00 32,218.00
L.01 0.3560 OH Pekerja 75,000 85,000 26,700.00 30,260.00
L.04 0.0178 OH Mandor 100,000 110,000 1,780.00 1,958.00
B BAHAN - -
- - -
C PERALATAN - -

D Jumlah A + B + C 28,480.00 32,218.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,848.00 3,221.80
F Harga Satuan Pekerjaan (D+E) 31,328.00 35,439.80

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


70 T.15.a.5 1 m3 37,136.00 42,010.10
JARAK ANGKUT 50 m
A TENAGA 33,760.00 38,191.00
L.01 0.4220 OH Pekerja 75,000 85,000 31,650.00 35,870.00
L.04 0.0211 OH Mandor 100,000 110,000 2,110.00 2,321.00
B BAHAN - -

C PERALATAN - -
D Jumlah A + B + C 33,760.00 38,191.00
E OVERHEAD & PROFIT (CONTOH) 10% 3,376.00 3,819.10
F Harga Satuan Pekerjaan (D+E) 37,136.00 42,010.10

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


71 T.15.a.6 1 m3 52,800.00 59,730.00
JARAK ANGKUT 100 m
A TENAGA 48,000.00 54,300.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -
- -
D Jumlah A + B + C 48,000.00 54,300.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,800.00 5,430.00
F Harga Satuan Pekerjaan (D+E) 52,800.00 59,730.00

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


72 T.15.a.7 1 m3 83,600.00 94,572.50
JARAK ANGKUT 200 m
A TENAGA 76,000.00 85,975.00
L.01 0.9500 OH Pekerja 75,000 85,000 71,250.00 80,750.00
L.04 0.0475 OH Mandor 100,000 110,000 4,750.00 5,225.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 76,000.00 85,975.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,600.00 8,597.50
F Harga Satuan Pekerjaan (D+E) 83,600.00 94,572.50

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


73 T.15.a.8 1 m3 114,400.00 129,415.00
JARAK ANGKUT 300 m
A TENAGA 104,000.00 117,650.00
L.01 1.3000 OH Pekerja 75,000 85,000 97,500.00 110,500.00
L.04 0.0650 OH Mandor 100,000 110,000 6,500.00 7,150.00
B BAHAN - -
- - -
C PERALATAN - -
- - - -
D Jumlah A + B + C 104,000.00 117,650.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,400.00 11,765.00
F Harga Satuan Pekerjaan (D+E) 114,400.00 129,415.00

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


74 T.15.a.9 1 m3 145,200.00 164,257.50
JARAK ANGKUT 400 m
A TENAGA 132,000.00 149,325.00
L.01 1.6500 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.04 0.0825 OH Mandor 100,000 110,000 8,250.00 9,075.00
B BAHAN - -

C PERALATAN - -

D Jumlah A + B + C 132,000.00 149,325.00


E OVERHEAD & PROFIT (CONTOH) 10% 13,200.00 14,932.50
F Harga Satuan Pekerjaan (D+E) 145,200.00 164,257.50

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


75 T.15.a.10 1 m3 171,600.00 194,122.50
JARAK ANGKUT 500 m
A TENAGA 156,000.00 176,475.00
L.01 1.9500 OH Pekerja 75,000 85,000 146,250.00 165,750.00
L.04 0.0975 OH Mandor 100,000 110,000 9,750.00 10,725.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 156,000.00 176,475.00
E OVERHEAD & PROFIT (CONTOH) 10% 15,600.00 17,647.50
F Harga Satuan Pekerjaan (D+E) 171,600.00 194,122.50

MENGANGKUT HASIL GALIAN DG JARAK ANGKUT > 500


76 T.15.a.11 1 m3 30,976.00 35,041.60
M UNTUK SETIAP PENAMBAHAN JARAK ANGKUT 100 M

A TENAGA 28,160.00 31,856.00


L.01 0.3520 OH Pekerja 75,000 85,000 26,400.00 29,920.00
L.04 0.0176 OH Mandor 100,000 110,000 1,760.00 1,936.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 28,160.00 31,856.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,816.00 3,185.60
F Harga Satuan Pekerjaan (D+E) 30,976.00 35,041.60

ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK


T.15.b
JARAK VERTIKAL MENURUN
AHSP T.15.b hanya berlaku untuk pelandaian turun lebih terjal dari 1v : 5h
MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH
77 T.15.b.1 1 m3 13,200.00 14,932.50
SAMPAI BEDA TINGGI 1 M

A TENAGA 12,000.00 13,575.00


L.01 0.1500 OH Pekerja 75,000 85,000 11,250.00 12,750.00
L.04 0.0075 OH Mandor 100,000 110,000 750.00 825.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 12,000.00 13,575.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,200.00 1,357.50
F Harga Satuan Pekerjaan (D+E) 13,200.00 14,932.50

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


78 T.15.b.2 1 m3 18,480.00 20,905.50
SAMPAI BEDA TINGGI >1M s/d 2 M

A TENAGA 16,800.00 19,005.00


L.01 0.2100 OH Pekerja 75,000 85,000 15,750.00 17,850.00
L.04 0.0105 OH Mandor 100,000 110,000 1,050.00 1,155.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 16,800.00 19,005.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,680.00 1,900.50
F Harga Satuan Pekerjaan (D+E) 18,480.00 20,905.50

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


79 T.15.b.3 1 m3 24,398.00 27,600.10
SAMPAI BEDA TINGGI >2M s/d 3 M

A TENAGA 22,180.00 25,091.00


L.01 0.2772 OH Pekerja 75,000 85,000 20,790.00 23,562.00
L.04 0.0139 OH Mandor 100,000 110,000 1,390.00 1,529.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 22,180.00 25,091.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,218.00 2,509.10
F Harga Satuan Pekerjaan (D+E) 24,398.00 27,600.10

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


80 T.15.b.4 1 m3 30,489.25 34,491.05
SAMPAI BEDA TINGGI >3M s/d 4 M

A TENAGA 27,717.50 31,355.50


L.01 0.3465 OH Pekerja 75,000 85,000 25,987.50 29,452.50
L.04 0.0173 OH Mandor 100,000 110,000 1,730.00 1,903.00
B BAHAN - -
- -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -
- -
D Jumlah A + B + C 27,717.50 31,355.50
E OVERHEAD & PROFIT (CONTOH) 10% 2,771.75 3,135.55
F Harga Satuan Pekerjaan (D+E) 30,489.25 34,491.05

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


81 T.15.b.5 1 m3 36,280.75 41,042.65
SAMPAI BEDA TINGGI >4 M s/d 5 M

A TENAGA 32,982.50 37,311.50


L.01 0.4123 OH Pekerja 75,000 85,000 30,922.50 35,045.50
L.04 0.0206 OH Mandor 100,000 110,000 2,060.00 2,266.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 32,982.50 37,311.50
E OVERHEAD & PROFIT (CONTOH) 10% 3,298.25 3,731.15
F Harga Satuan Pekerjaan (D+E) 36,280.75 41,042.65

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


82 T.15.b.6 1 m3 41,368.25 46,797.85
SAMPAI BEDA TINGGI >5 M s/d 6 M

A TENAGA 37,607.50 42,543.50


L.01 0.4701 OH Pekerja 75,000 85,000 35,257.50 39,958.50
L.04 0.0235 OH Mandor 100,000 110,000 2,350.00 2,585.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 37,607.50 42,543.50
E OVERHEAD & PROFIT (CONTOH) 10% 3,760.75 4,254.35
F Harga Satuan Pekerjaan (D+E) 41,368.25 46,797.85

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


83 T.15.b.7 1 m3 45,509.75 51,482.75
SAMPAI BEDA TINGGI >6 M s/d 7 M

A TENAGA 41,372.50 46,802.50


L.01 0.5171 OH Pekerja 75,000 85,000 38,782.50 43,953.50
L.04 0.0259 OH Mandor 100,000 110,000 2,590.00 2,849.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 41,372.50 46,802.50
E OVERHEAD & PROFIT (CONTOH) 10% 4,137.25 4,680.25
F Harga Satuan Pekerjaan (D+E) 45,509.75 51,482.75

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


84 T.15.b.8 1 m3 48,694.25 55,085.25
SAMPAI BEDA TINGGI >7 M s/d 8 M

A TENAGA 44,267.50 50,077.50


L.01 0.5533 OH Pekerja 75,000 85,000 41,497.50 47,030.50
L.04 0.0277 OH Mandor 100,000 110,000 2,770.00 3,047.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 44,267.50 50,077.50
E OVERHEAD & PROFIT (CONTOH) 10% 4,426.75 5,007.75
F Harga Satuan Pekerjaan (D+E) 48,694.25 55,085.25
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH
85 T.15.b.9 1 m3 51,114.25 57,823.15
SAMPAI BEDA TINGGI >8 M s/d 9 M

A TENAGA 46,467.50 52,566.50


L.01 0.5809 OH Pekerja 75,000 85,000 43,567.50 49,376.50
L.04 0.0290 OH Mandor 100,000 110,000 2,900.00 3,190.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 46,467.50 52,566.50
E OVERHEAD & PROFIT (CONTOH) 10% 4,646.75 5,256.65
F Harga Satuan Pekerjaan (D+E) 51,114.25 57,823.15

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


86 T.15.b.10 1 m3 53,168.50 60,146.90
SAMPAI BEDA TINGGI >9 M s/d 10 M

A TENAGA 48,335.00 54,679.00


L.01 0.6042 OH Pekerja 75,000 85,000 45,315.00 51,357.00
L.04 0.0302 OH Mandor 100,000 110,000 3,020.00 3,322.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,335.00 54,679.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,833.50 5,467.90
F Harga Satuan Pekerjaan (D+E) 53,168.50 60,146.90

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


87 T.15.b.11 1 m3 DENGAN BEDA TINGGI >10 UNTUK SETIAP PENAMBAHAN 1,325.50 1,499.30
1M

A TENAGA 1,205.00 1,363.00


L.01 0.0150 OH Pekerja 75,000 85,000 1,125.00 1,275.00
L.04 0.0008 OH Mandor 100,000 110,000 80.00 88.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 1,205.00 1,363.00
E OVERHEAD & PROFIT (CONTOH) 10% 120.50 136.30
F Harga Satuan Pekerjaan (D+E) 1,325.50 1,499.30

ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK


T.15.c
JARAK VERTIKAL NAIK
AHSP T.15.c hanya berlaku untuk pelandaian turun lebih terjal dari 1v : 10h
MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH
88 T.15.c.1 1 m3 26,400.00 29,865.00
SAMPAI BEDA TINGGI 1 M

A TENAGA 24,000.00 27,150.00


L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.04 0.0150 OH Mandor 100,000 110,000 1,500.00 1,650.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 24,000.00 27,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,400.00 2,715.00
F Harga Satuan Pekerjaan (D+E) 26,400.00 29,865.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH
89 T.15.c.2 1 m3 38,618.25 43,687.05
SAMPAI BEDA TINGGI >1M s/d 2 M

A TENAGA 35,107.50 39,715.50


L.01 0.4389 OH Pekerja 75,000 85,000 32,917.50 37,306.50
L.04 0.0219 OH Mandor 100,000 110,000 2,190.00 2,409.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 35,107.50 39,715.50
E OVERHEAD & PROFIT (CONTOH) 10% 3,510.75 3,971.55
F Harga Satuan Pekerjaan (D+E) 38,618.25 43,687.05

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


90 T.15.c.3 1 m3 53,130.00 60,104.00
SAMPAI BEDA TINGGI >2M s/d 3 M

A TENAGA 48,300.00 54,640.00


L.01 0.6040 OH Pekerja 75,000 85,000 45,300.00 51,340.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,300.00 54,640.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,830.00 5,464.00
F Harga Satuan Pekerjaan (D+E) 53,130.00 60,104.00

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


91 T.15.c.4 1 m3 69,520.00 78,644.50
SAMPAI BEDA TINGGI >3M s/d 4 M

A TENAGA 63,200.00 71,495.00


L.01 0.7900 OH Pekerja 75,000 85,000 59,250.00 67,150.00
L.04 0.0395 OH Mandor 100,000 110,000 3,950.00 4,345.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 63,200.00 71,495.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,320.00 7,149.50
F Harga Satuan Pekerjaan (D+E) 69,520.00 78,644.50

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


92 T.15.c.5 1 m3 86,322.50 97,652.50
SAMPAI BEDA TINGGI >4 M s/d 5 M

A TENAGA 78,475.00 88,775.00


L.01 0.9810 OH Pekerja 75,000 85,000 73,575.00 83,385.00
L.04 0.0490 OH Mandor 100,000 110,000 4,900.00 5,390.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 78,475.00 88,775.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,847.50 8,877.50
F Harga Satuan Pekerjaan (D+E) 86,322.50 97,652.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH
93 T.15.c.6 1 m3 103,015.00 116,534.00
SAMPAI BEDA TINGGI >5 M s/d 6 M

A TENAGA 93,650.00 105,940.00


L.01 1.1700 OH Pekerja 75,000 85,000 87,750.00 99,450.00
L.04 0.0590 OH Mandor 100,000 110,000 5,900.00 6,490.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 93,650.00 105,940.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,365.00 10,594.00
F Harga Satuan Pekerjaan (D+E) 103,015.00 116,534.00

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


94 T.15.c.7 1 m3 118,250.00 133,771.00
SAMPAI BEDA TINGGI >6 M s/d 7 M

A TENAGA 107,500.00 121,610.00


L.01 1.3440 OH Pekerja 75,000 85,000 100,800.00 114,240.00
L.04 0.0670 OH Mandor 100,000 110,000 6,700.00 7,370.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 107,500.00 121,610.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,750.00 12,161.00
F Harga Satuan Pekerjaan (D+E) 118,250.00 133,771.00

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


95 T.15.c.8 1 m3 132,412.50 149,792.50
SAMPAI BEDA TINGGI >7 M s/d 8 M

A TENAGA 120,375.00 136,175.00


L.01 1.5050 OH Pekerja 75,000 85,000 112,875.00 127,925.00
L.04 0.0750 OH Mandor 100,000 110,000 7,500.00 8,250.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 120,375.00 136,175.00
E OVERHEAD & PROFIT (CONTOH) 10% 12,037.50 13,617.50
F Harga Satuan Pekerjaan (D+E) 132,412.50 149,792.50

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


96 T.15.c.9 1 m3 145,145.00 164,197.00
SAMPAI BEDA TINGGI >8 M s/d 9 M

A TENAGA 131,950.00 149,270.00


L.01 1.6500 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.04 0.0820 OH Mandor 100,000 110,000 8,200.00 9,020.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 131,950.00 149,270.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,195.00 14,927.00
F Harga Satuan Pekerjaan (D+E) 145,145.00 164,197.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


97 T.15.c.10 1 m3 157,905.00 178,629.00
SAMPAI BEDA TINGGI >9 M s/d 10 M

A TENAGA 143,550.00 162,390.00


L.01 1.7940 OH Pekerja 75,000 85,000 134,550.00 152,490.00
L.04 0.0900 OH Mandor 100,000 110,000 9,000.00 9,900.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 143,550.00 162,390.00
E OVERHEAD & PROFIT (CONTOH) 10% 14,355.00 16,239.00
F Harga Satuan Pekerjaan (D+E) 157,905.00 178,629.00

MENAIKKAN MATERIAL ATAU HASIL GALIAN TANAH


98 T.15.c.11 1 m3 DENGAN BEDA TINGGI >10 UNTUK SETIAP PENAMBAHAN 4,455.00 5,038.00
1M

A TENAGA 4,050.00 4,580.00


L.01 0.0500 OH Pekerja 75,000 85,000 3,750.00 4,250.00
L.04 0.0030 OH Mandor 100,000 110,000 300.00 330.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 4,050.00 4,580.00
E OVERHEAD & PROFIT (CONTOH) 10% 405.00 458.00
F Harga Satuan Pekerjaan (D+E) 4,455.00 5,038.00

Konversi berat material tanah biasa (lepas) kepada jenis


T.15.d
material lain

TABEL II.A.2 BERAT ISI MATERIAL

BERAT ISI DALAM CONTOH TINGKAT


NO. JENIS MATERIAL BERAT ISI MATERIAL (TON/M3)
(TON/M3) KEMUDAHAN

1 * Tanah Biasa 1,00 - 1,20 1.10 1

2 * Tanah Gambut 0,60 - 0,85 0.75 1

3 * Agregat Kasar 1,236** - 1,283 1.26 1


4 * Agregat Halus 1,255 - 1,363 1.31 1

5 * Split / Koral / Kerikil 1,232 - 1,273 1.25 1

6 * Batu Kali 0,960 - 0,971 0.97 1

7 * Batu Belah 0,914 - 0,960 0.94 1

8 * Pasir Pasang 1,243 - 1,316 1.28 1

9 Pipa Beton (tidak bertulang) umum 2,10 - 2,25 2.20 0.9

10 Pipa Beton (tidak bertulang) Fc’ = 12,5 Mpa 2,25 - 2,50 2.40 0.9

11 Pipa Beton (bertulang 155 kg besi / m3) 2,35 - 2,55 2.50 0.9

12 Kayu 0,65 - 0,95 0.80 1

13 Plastik 0,60 - 0,75 0.68 1

14 PVC 0,50 - 1,20 0.85 0.9

15 HDPE 0,50 - 1,00 0.80 0.9

16 GIP 7,55 - 8,45 8.00 0.8

17 DCIP 7,50 - 8,65 8.00 0.8

18 Besi Profil 7,45 - 8,20 7.80 0.3

19 Besi Beton 7,45 - 8,20 7.80 0.7

Keterangan :

* Berat isi lepas ** Hasil pemecah batu mulai dari 1,20 ton/m3
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

JIKA BIAYA ANGKUTAN DIMASUKKAN DALAM HSD - BAHAN


T.15.d.1
(DIHITUNG TANPA OVERHEAD + KEUNTUNGAN)

Contoh perhitungan konversi jenis material dan jarak angkut naik atau turun
ANGKUT MATERIAL DENGAN JARAK ANGKUT 100 M'
99 T.15.d.1.a 1 m3 48,000.00 54,300.00
HORIZONTAL
A TENAGA 48,000.00 54,300.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,000.00 54,300.00

1 m3 KORAL/KERIKIL JARAK HORIZONTAL 100 m

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 48,000.00 = 54,981.82

50 kg SEMEN JARAK HORIZONTAL 100 m (zak)

HSP angkut 50 kg angkut jarak horizontal = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 48,000.00 = 2,181.82

100 kg BESI BETON JARAK HORIZONTAL 100 m

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 48,000.00 = 3,054.55

100 kg GIP JARAK HORIZONTAL 100 m

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 48,000.00 = 3,490.91

100 kg PIPA PVC JARAK HORIZONTAL 100 m

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 48,000.00 = 3,927.27

100 T.15.d.1.b 1 m3 JARAK ANGKUT VERTIKAL TURUN 22,180.00 25,091.00


T.15.d.1.b. MENURUNKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D
3 3M
A TENAGA 22,180.00 25,091.00
L.01 0.2772 OH Pekerja 75,000 85,000 20,790.00 23,562.00
L.04 0.0139 OH Mandor 100,000 110,000 1,390.00 1,529.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 22,180.00 25,091.00

1 m3 KORAL/KERIKIL JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 22,180.00 = 25,406.18

50 kg SEMEN JARAK VERTIKAL TURUN >2M S/D 3M (ZAK)

HSP angkut 50 kg SEMEN = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 22,180.00 = 1,008.18

100 kg BESI BETON JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 22,180.00 = 1,411.45

100 kg GIP JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 22,180.00 = 1,613.09

100 kg PIPA PVC JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 22,180.00 = 1,814.73


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
101 T.15.d.1.c 1 m3 JARAK ANGKUT VERTIKAL NAIK 3 M 48,300.00 54,640.00
T.15.d.1.c. MENAIKKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3
3 M
A TENAGA 48,300.00 54,640.00
L.01 0.6040 OH Pekerja 75,000 85,000 45,300.00 51,340.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,300.00 54,640.00

1 m3 KORAL/KERIKIL JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 48,300.00 = 55,325.45

50 kg SEMEN JARAK VERTIKAL NAIK >2M S/D 3M (ZAK)

HSP angkut 50 kg SEMEN = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 48,300.00 = 2,195.45

100 kg BESI BETON JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 48,300.00 = 3,073.64

100 kg GIP JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 48,300.00 = 3,512.73

100 kg PIPA PVC JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 48,300.00 = 3,951.82

JIKA BIAYA ANGKUTAN DIPISAH DARI HSP KOMPONEN


PEKERJAAN KONSTRUKSI (BIAYA KONSTRUKSI DAN BIAYA
T.15.d.2
ANGKUT DITULIS MASING-MASING SUDAH TERMASUK
OVERHEAD + KEUNTUNGAN)

Contoh perhitungan konversi jenis material dan jarak angkut naik atau turun
102 T.15.d.2.a 1 m3 JARAK ANGKUT HORIZONTAL 100 M 52,800.00 59,730.00
JARAK ANGKUT MATERIAL DENGAN JARAK ANGKUT 100
T.15.d.6
M'
A TENAGA 48,000.00 54,300.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,000.00 54,300.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,800.00 5,430.00
F Harga Satuan Pekerjaan (D+E) 52,800.00 59,730.00

1 m3 KORAL/KERIKIL JARAK HORIZONTAL 100 m

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 52,800.00 = 60,480.00

50 kg SEMEN JARAK HORIZONTAL 100 m (zak)

HSP angkut 50 kg angkut jarak horizontal = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 52,800.00 = 2,400.00

100 kg BESI BETON JARAK HORIZONTAL 100 m

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 52,800.00 = 3,360.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

100 kg GIP JARAK HORIZONTAL 100 m

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 52,800.00 = 3,840.00

100 kg PIPA PVC JARAK HORIZONTAL 100 m

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 52,800.00 = 4,320.00

103 T.15.d.2.b 1 m3 JARAK ANGKUT VERTIKAL TURUN 24,398.00 27,600.10

T.15.d.2.b. MENURUNKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D


3 3M

A TENAGA 22,180.00 25,091.00


L.01 0.2772 OH Pekerja 75,000 85,000 20,790.00 23,562.00
L.04 0.0139 OH Mandor 100,000 110,000 1,390.00 1,529.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 22,180.00 25,091.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,218.00 2,509.10
F Harga Satuan Pekerjaan (D+E) 24,398.00 27,600.10

1 m3 KORAL/KERIKIL JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 24,398.00 = 27,946.80

50 kg SEMEN JARAK VERTIKAL TURUN >2M S/D 3M (ZAK)

HSP angkut 50 kg SEMEN = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 24,398.00 = 1,109.00

100 kg BESI BETON JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 24,398.00 = 1,552.60

100 kg GIP JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 24,398.00 = 1,774.40

100 kg PIPA PVC JARAK VERTIKAL TURUN >2M S/D 3M

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 24,398.00 = 1,996.20

104 T.15.d.2.c 1 m3 JARAK ANGKUT VERTIKAL NAIK 3 M 53,130.00 60,104.00


T.15.d.2.c. MENAIKKAN MATERIAL SAMPAI BEDA TINGGI > 2M S/D 3
3 M
A TENAGA 48,300.00 54,640.00
L.01 0.6040 OH Pekerja 75,000 85,000 45,300.00 51,340.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 48,300.00 54,640.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,830.00 5,464.00
F Harga Satuan Pekerjaan (D+E) 53,130.00 60,104.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
1 m3 KORAL/KERIKIL JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 1m3 agregat kasar atau koral = 1,00 x 1,26/1,10 x HSP angkut 1 m3 tanah lepas

= 1.1454545455 x 53,130.00 = 60,858.00

50 kg SEMEN JARAK VERTIKAL NAIK >2M S/D 3M (ZAK)

HSP angkut 50 kg SEMEN = 1,00 x 0,05/1,10 X hps angkut 1 m3 tanah lepas

= 0.0454545455 x 53,130.00 = 2,415.00

100 kg BESI BETON JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg besi beton = 0,70 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0636363636 x 53,130.00 = 3,381.00

100 kg GIP JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg GIP = 0,80 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0727272727 x 53,130.00 = 3,864.00

100 kg PIPA PVC JARAK VERTIKAL NAIK >2M S/D 3M

HSP angkut 100 kg PIPA PVC = 0,90 x 0,1/1,10 X hps angkut 1 m3 tanah lepas

= 0.0818181818 x 53,130.00 = 4,347.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

A.2 PEKERJAAN PASANGAN


P.01 PASANGAN BATU DENGAN MORTAR JENIS PC - PP
105 P.01.a.1 1 m3 MORTAR TIPE M (MANUAL) 1,150,545.00 1,327,397.50
(Mutu PP tertentu setara dg campuran 1PP : 2PP)
A TENAGA 315,000.00 353,700.00
L.01 2.70 OH Pekerja 75,000 85,000 202,500.00 229,500.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.27 OH Mandor 100,000 110,000 27,000.00 29,700.00
B BAHAN 730,950.00 853,025.00
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.440 m3 Pasir Pasang 315,000 370,000 138,600.00 162,800.00
252 kg Portland Cement 1,113 1,144 280,350.00 288,225.00
C PERALATAN - -

D Jumlah A + B + C 1,045,950.00 1,206,725.00


E OVERHEAD & PROFIT (CONTOH) 10% 104,595.00 120,672.50
F Harga Satuan Pekerjaan (D+E) 1,150,545.00 1,327,397.50

106 P.01.a.2 1 m3 MORTAR TIPE M (MENGGUNAKAN MOLEN) 1,141,635.00 1,312,613.50


(Mutu PP tertentu setara dg campuran 1PP : 2PP)
A TENAGA 238,500.00 267,300.00
L.01 1.80 OH Pekerja 75,000 85,000 135,000.00 153,000.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.18 OH Mandor 100,000 110,000 18,000.00 19,800.00
B BAHAN 730,950.00 853,025.00
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.440 m3 Pasir Pasang 315,000 370,000 138,600.00 162,800.00
252 kg Portland Cement 1,113 1,144 280,350.00 288,225.00
C PERALATAN 68,400.00 72,960.00
0.076 hr Molen Kapasitas 0,3 m3 900,000 960,000 68,400.00 72,960.00
D Jumlah A + B + C 1,037,850.00 1,193,285.00
E OVERHEAD & PROFIT (CONTOH) 10% 103,785.00 119,328.50
F Harga Satuan Pekerjaan (D+E) 1,141,635.00 1,312,613.50

107 P.01.b.1 1 m3 MORTAR TIPE S (MANUAL) 1,104,950.00 1,282,806.25


(Mutu PP tertentu setara dg campuran 1PP : 3PP)
A TENAGA 315,000.00 353,700.00
L.01 2.70 OH Pekerja 75,000 85,000 202,500.00 229,500.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.27 OH Mandor 100,000 110,000 27,000.00 29,700.00
B BAHAN 689,500.00 812,487.50
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.485 m3 Pasir Pasang 315,000 370,000 152,775.00 179,450.00
202 kg Portland Cement 1,113 1,144 224,725.00 231,037.50
C PERALATAN - -
D Jumlah A + B + C 1,004,500.00 1,166,187.50
E OVERHEAD & PROFIT (CONTOH) 10% 100,450.00 116,618.75
F Harga Satuan Pekerjaan (D+E) 1,104,950.00 1,282,806.25

108 P.01.b.2 1 m3 MORTAR TIPE S (Menggunakan Molen) 1,096,040.00 1,268,022.25


(Mutu PP tertentu setara dg campuran 1PP : 3PP)
A TENAGA 238,500.00 267,300.00
L.01 1.80 OH Pekerja 75,000 85,000 135,000.00 153,000.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.03 - OH Kepala Tukang - - - -
L.04 0.18 OH Mandor 100,000 110,000 18,000.00 19,800.00
B BAHAN 689,500.00 812,487.50
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.485 m3 Pasir Pasang 315,000 370,000 152,775.00 179,450.00
202 kg Portland Cement 1,113 1,144 224,725.00 231,037.50
C PERALATAN 68,400.00 72,960.00
0.076 hr Molen 900,000 960,000 68,400.00 72,960.00
D Jumlah A + B + C 996,400.00 1,152,747.50
E OVERHEAD & PROFIT (CONTOH) 10% 99,640.00 115,274.75
F Harga Satuan Pekerjaan (D+E) 1,096,040.00 1,268,022.25
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
109 P.01.c.1 1 m3 MORTAR TIPE N (Manual) 1,069,351.25 1,247,984.38
(Mutu PP tertentu setara dg campuran 1PP : 4PP)
A TENAGA 315,000.00 353,700.00
L.01 2.70 OH Pekerja 75,000 85,000 202,500.00 229,500.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.27 OH Mandor 100,000 110,000 27,000.00 29,700.00
B BAHAN 657,137.50 780,831.25
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.520 m3 Pasir Pasang 315,000 370,000 163,800.00 192,400.00
163 kg Portland Cement 1,113 1,144 181,337.50 186,431.25
C PERALATAN - -
D Jumlah A + B + C 972,137.50 1,134,531.25
E OVERHEAD & PROFIT (CONTOH) 10% 97,213.75 113,453.13
F Harga Satuan Pekerjaan (D+E) 1,069,351.25 1,247,984.38

110 P.01.c.2 1 m3 MORTAR TIPE N (Menggunakan Molen) 1,060,441.25 1,233,200.38


(Mutu PP tertentu setara dg campuran 1PP : 4PP)
A TENAGA 238,500.00 267,300.00
L.01 1.80 OH Pekerja 75,000 85,000 135,000.00 153,000.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.18 OH Mandor 100,000 110,000 18,000.00 19,800.00
B BAHAN 657,137.50 780,831.25
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.520 m3 Pasir Pasang 315,000 370,000 163,800.00 192,400.00
163 kg Portland Cement 1,113 1,144 181,337.50 186,431.25
C PERALATAN 68,400.00 72,960.00
0.076 hr Molen KAPASITAS 0,3 M3 900,000 960,000 68,400.00 72,960.00
D Jumlah A + B + C 964,037.50 1,121,091.25
E OVERHEAD & PROFIT (CONTOH) 10% 96,403.75 112,109.13
F Harga Satuan Pekerjaan (D+E) 1,060,441.25 1,233,200.38

111 P.01.d.1 1 m3 MORTAR TIPE O (Manual) 1,046,867.25 1,226,594.88


(Mutu PP tertentu setara dg campuran 1PP : 5PP)
A TENAGA 315,000.00 353,700.00
L.01 2.70 OH Pekerja 75,000 85,000 202,500.00 229,500.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.27 OH Mandor 100,000 110,000 27,000.00 29,700.00
B BAHAN 636,697.50 761,386.25
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.554 m3 Pasir Pasang 315,000 370,000 174,510.00 204,980.00
135 kg Portland Cement 1,113 1,144 150,187.50 154,406.25
C PERALATAN - -
D Jumlah A + B + C 951,697.50 1,115,086.25
E OVERHEAD & PROFIT (CONTOH) 10% 95,169.75 111,508.63
F Harga Satuan Pekerjaan (D+E) 1,046,867.25 1,226,594.88

112 P.01.d.2 1 m3 MORTAR TIPE O (Menggunakan Molen)) 1,037,957.25 1,211,810.88


(Mutu PP tertentu setara dg campuran 1PP : 5PP)
A TENAGA 238,500.00 267,300.00
L.01 1.80 OH Pekerja 75,000 85,000 135,000.00 153,000.00
L.02 0.90 OH Tukang Batu 95,000 105,000 85,500.00 94,500.00
L.04 0.18 OH Mandor 100,000 110,000 18,000.00 19,800.00
B BAHAN 636,697.50 761,386.25
1.200 m3 Batu 260,000 335,000 312,000.00 402,000.00
0.554 m3 Pasir Pasang 315,000 370,000 174,510.00 204,980.00
135 kg Portland Cement 1,113 1,144 150,187.50 154,406.25
C PERALATAN 68,400.00 72,960.00
0.076 hr Molen 900,000 960,000 68,400.00 72,960.00
D Jumlah A + B + C 943,597.50 1,101,646.25
E OVERHEAD & PROFIT (CONTOH) 10% 94,359.75 110,164.63
F Harga Satuan Pekerjaan (D+E) 1,037,957.25 1,211,810.88
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
P.01.e BONGKAR DAN PEMANFAATAN BATU BEKAS PASANGAN
BONGKAR PASANGAN BATU & PEMBERSIHAN BATU
113 P.01.e.1 1 m3 117,744.00 133,386.00
(MANUAL)
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
A TENAGA 106,400.00 120,540.00
L.01 1.40 OH Pekerja 75,000 85,000 105,000.00 119,000.00
L.04 0.01 OH Mandor 100,000 110,000 1,400.00 1,540.00
B BAHAN - -
C PERALATAN 640.00 720.00
0.008 bh Palu Godam 80,000 90,000 640.00 720.00
0.012 bh Pahat Beton 20,000 25,000 240.00 300.00
0.020 bh Linggis 75,000 85,000 1,500.00 1,700.00
D Jumlah A + B + C 107,040.00 121,260.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,704.00 12,126.00
F Harga Satuan Pekerjaan (D+E) 117,744.00 133,386.00

114 P.01.e.2 1 m3 BONGKAR PASANGAN BATU (MANUAL) 112,728.00 127,314.00

A TENAGA 102,000.00 115,200.00


L.01 1.20 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.04 0.12 OH Mandor 100,000 110,000 12,000.00 13,200.00
B BAHAN - -
C PERALATAN 480.00 540.00
0.006 bh Palu Godam 80,000 90,000 480.00 540.00
0.009 bh Pahat Beton 20,000 25,000 180.00 225.00
0.020 bh Linggis 75,000 85,000 1,500.00 1,700.00
D Jumlah A + B + C 102,480.00 115,740.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,248.00 11,574.00
F Harga Satuan Pekerjaan (D+E) 112,728.00 127,314.00

115 P.01.e.3 1 m3 BONGKAR PASANGAN BATU DENGAN JACK HAMMER 78,100.00 88,110.00
A TENAGA 51,000.00 57,600.00
L.01 0.60 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.06 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
C PERALATAN 20,000.00 22,500.00
0.050 hr Jack Hammer 400,000 450,000 20,000.00 22,500.00
D Jumlah A + B + C 71,000.00 80,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,100.00 8,010.00
F Harga Satuan Pekerjaan (D+E) 78,100.00 88,110.00

PEMBERSIHAN BONGKARAN PASANGAN BATU UNTUK


116 P.01.e.4 1 m3 18,942.00 21,400.50
PEMANFAATAN KEMBALI MATERIAL BATU **)

A TENAGA 17,000.00 19,200.00


L.01 0.20 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.04 0.02 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN - -
C PERALATAN 220.00 255.00
0.002 BH Palu Godam *) BAJA KERAS 80,000 90,000 160.00 180.00
0.003 BH Pahat Beton BAJA KERAS 20,000 25,000 60.00 75.00

D Jumlah A + B + C 17,220.00 19,455.00


E OVERHEAD & PROFIT (CONTOH) 10% 1,722.00 1,945.50
F Harga Satuan Pekerjaan (D+E) 18,942.00 21,400.50
*) JIKA TIDAK PERLU MENGGUNAKAN PERELATAN KHUSUS (BAJA KERAS) MAKA HSD = 0
**) HASIL PEMBERSIHAN 1 M3 PASANGAN BATU YANG DIBONGKAR, UMUM MENGHASILKAN 0,55 - 0,65 M3 BATU
P.01.E.5 1 M3 BATU DARI BEKAS BONGKARAN PASANGAN BATU **)
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
P.02 PEKERJAAN PASANGAN BATU MERAH
P.02.a MORTAR TIPE M (SETARA CAMPURAN 1PC : 2PP)
117 P.02.a.1 1 m3 MANUAL 969,540.00 1,066,202.50
(Mutu PP tertentu setara dg campuran 1PP : 2PP)
A TENAGA 318,000.00 356,400.00
L.01 2.40 OH Pekerja 75,000 85,000 180,000.00 204,000.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.24 OH Mandor 100,000 110,000 24,000.00 26,400.00
B BAHAN 563,400.00 612,875.00
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.37 m3 Pasir Pasang 315,000 370,000 116,550.00 136,900.00
132 kg Portland Cement 1,113 1,144 146,850.00 150,975.00
C PERALATAN - -
- -
D Jumlah A + B + C 881,400.00 969,275.00
E OVERHEAD & PROFIT (CONTOH) 10% 88,140.00 96,927.50
F Harga Satuan Pekerjaan (D+E) 969,540.00 1,066,202.50

118 P.02.a.2 1 m3 MENGGUNAKAN MOLEN 1,212,090.00 1,319,642.50


(Mutu PP tertentu setara dg campuran 1PP : 2PP)
A TENAGA 241,500.00 270,000.00
L.01 1.50 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.15 OH Mandor 100,000 110,000 15,000.00 16,500.00
B BAHAN 563,400.00 612,875.00
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.37 m3 Pasir Pasang 315,000 370,000 116,550.00 136,900.00
132 kg Portland Cement 1,113 1,144 146,850.00 150,975.00
C PERALATAN 297,000.00 316,800.00
0.33 hr Molen KAPASITAS 0,3 M3 900,000 960,000 297,000.00 316,800.00
D Jumlah A + B + C 1,101,900.00 1,199,675.00
E OVERHEAD & PROFIT (CONTOH) 10% 110,190.00 119,967.50
F Harga Satuan Pekerjaan (D+E) 1,212,090.00 1,319,642.50

P.02.b MORTAR TIPE S (SETARA CAMPURAN 1PC : 3PP)


119 P.02.b.1 1 m3 MANUAL 960,877.50 1,056,027.50
(Mutu PP tertentu setara dg campuran 1PP : 3PP)
A TENAGA 318,000.00 356,400.00
L.01 2.40 OH Pekerja 75,000 85,000 180,000.00 204,000.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.24 OH Mandor 100,000 110,000 24,000.00 26,400.00
B BAHAN 555,525.00 603,625.00
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.345 m3 Pasir Pasang 315,000 370,000 108,675.00 127,650.00
132 kg Portland Cement 1,113 1,144 146,850.00 150,975.00
C PERALATAN - -
- -
D Jumlah A + B + C 873,525.00 960,025.00
E OVERHEAD & PROFIT (CONTOH) 10% 87,352.50 96,002.50
F Harga Satuan Pekerjaan (D+E) 960,877.50 1,056,027.50

120 P.02.b.2 1 m3 MENGGUNAKAN MOLEN 876,727.50 960,987.50


(Mutu PP tertentu setara dg campuran 1PP : 3PP)
A TENAGA 241,500.00 270,000.00
L.01 1.500 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 1.200 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.150 OH Mandor 100,000 110,000 15,000.00 16,500.00
B BAHAN 555,525.00 603,625.00
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.345 m3 Pasir Pasang 315,000 370,000 108,675.00 127,650.00
132 kg Portland Cement 1,113 1,144 146,850.00 150,975.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN 90,000.00 96,000.00
0.100 hr Molen KAPASITAS 0,3 M3 900,000 960,000 90,000.00 96,000.00
D Jumlah A + B + C 797,025.00 873,625.00
E OVERHEAD & PROFIT (CONTOH) 10% 79,702.50 87,362.50
F Harga Satuan Pekerjaan (D+E) 876,727.50 960,987.50

P.02.c MORTAR TIPE N (SETARA CAMPURAN 1PC : 4PP)


121 P.02.c.1 1 m3 MANUAL 938,334.38 1,034,120.31
(Mutu PP tertentu setara dg campuran 1PP : 4PP)
A TENAGA 318,000.00 356,400.00
L.01 2.40 OH Pekerja 75,000 85,000 180,000.00 204,000.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.24 OH Mandor 100,000 110,000 24,000.00 26,400.00
B BAHAN 535,031.25 583,709.38
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.370 m3 Pasir Pasang 315,000 370,000 116,550.00 136,900.00
106.50 kg Portland Cement 1,113 1,144 118,481.25 121,809.38
C PERALATAN - -
- -
D Jumlah A + B + C 853,031.25 940,109.38
E OVERHEAD & PROFIT (CONTOH) 10% 85,303.13 94,010.94
F Harga Satuan Pekerjaan (D+E) 938,334.38 1,034,120.31

122 P.02.c.2 1 m3 MENGGUNAKAN MOLEN 953,184.38 1,044,680.31


(Mutu PP tertentu setara dg campuran 1PP : 4PP)
A TENAGA 241,500.00 270,000.00
L.01 1.500 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 1.200 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.150 OH Mandor 100,000 110,000 15,000.00 16,500.00
B BAHAN 535,031.25 583,709.38
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.370 m3 Pasir Pasang 315,000 370,000 116,550.00 136,900.00
106.50 kg Portland Cement 1,113 1,144 118,481.25 121,809.38
C PERALATAN 90,000.00 96,000.00
C PERALATAN 90,000.00 96,000.00
0.100 hr Molen KAPASITAS 0,3 M3 900,000 960,000 90,000.00 96,000.00
D Jumlah A + B + C 866,531.25 949,709.38
E OVERHEAD & PROFIT (CONTOH) 10% 86,653.13 94,970.94
F Harga Satuan Pekerjaan (D+E) 953,184.38 1,044,680.31

P.02.d MORTAR TIPE O (SETARA CAMPURAN 1PC : 5PP)


123 P.02.d.1 1 m3 MANUAL 930,778.75 1,028,383.13
(Mutu PP tertentu setara dg campuran 1PP : 5PP)
A TENAGA 318,000.00 356,400.00
L.01 2.40 OH Pekerja 75,000 85,000 180,000.00 204,000.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.03 OH Kepala Tukang - - - -
L.04 0.24 OH Mandor 100,000 110,000 24,000.00 26,400.00
B BAHAN 528,162.50 578,493.75
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.410 m3 Pasir Pasang 315,000 370,000 129,150.00 151,700.00
89.00 kg Portland Cement 1,113 1,144 99,012.50 101,793.75
C PERALATAN - -
- -
D Jumlah A + B + C 846,162.50 934,893.75
E OVERHEAD & PROFIT (CONTOH) 10% 84,616.25 93,489.38
F Harga Satuan Pekerjaan (D+E) 930,778.75 1,028,383.13

124 P.02.d.2 1 m3 MENGGUNAKAN MOLEN 945,628.75 1,038,943.13


(Mutu PP tertentu setara dg campuran 1PP : 5PP)
A TENAGA 241,500.00 270,000.00
L.01 1.500 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 1.200 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.150 OH Mandor 100,000 110,000 15,000.00 16,500.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN 528,162.50 578,493.75
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.410 m3 Pasir Pasang 315,000 370,000 129,150.00 151,700.00
89.00 kg Portland Cement 1,113 1,144 99,012.50 101,793.75
C PERALATAN 90,000.00 96,000.00
C PERALATAN 90,000.00 96,000.00
0.100 hr Molen KAPASITAS 0,3 M3 900,000 960,000 90,000.00 96,000.00
D Jumlah A + B + C 859,662.50 944,493.75
E OVERHEAD & PROFIT (CONTOH) 10% 85,966.25 94,449.38
F Harga Satuan Pekerjaan (D+E) 945,628.75 1,038,943.13

P.02.e MORTAR campuran (SETARA CAMPURAN 1PC : 6PP)


125 P.02.e.1 1 m3 MANUAL 941,366.25 1,043,329.38
(Mutu PP tertentu setara dg campuran 1PP : 6PP)
A TENAGA 318,000.00 356,400.00
L.01 2.40 OH Pekerja 75,000 85,000 180,000.00 204,000.00
L.02 1.20 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.24 OH Mandor 100,000 110,000 24,000.00 26,400.00
B BAHAN 537,787.50 592,081.25
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.490 m3 Pasir Pasang 315,000 370,000 154,350.00 181,300.00
75.00 kg Portland Cement 1,113 1,144 83,437.50 85,781.25
C PERALATAN - -
- -
D Jumlah A + B + C 855,787.50 948,481.25
E OVERHEAD & PROFIT (CONTOH) 10% 85,578.75 94,848.13
F Harga Satuan Pekerjaan (D+E) 941,366.25 1,043,329.38

126 P.02.e.2 1 m3 MENGGUNAKAN MOLEN 956,216.25 1,053,889.38


(Mutu PP tertentu setara dg campuran 1PP : 6PP)
A TENAGA 241,500.00 270,000.00
L.01 1.500 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 1.200 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.04 0.150 OH Mandor 100,000 110,000 15,000.00 16,500.00
B BAHAN 537,787.50 592,081.25
500 bh Bata Merah 600 650 300,000.00 325,000.00
0.490 m3 Pasir Pasang 315,000 370,000 154,350.00 181,300.00
75.00 kg Portland Cement 1,113 1,144 83,437.50 85,781.25
C PERALATAN 90,000.00 96,000.00
C PERALATAN 90,000.00 96,000.00
0.100 hr Molen KAPASITAS 0,3 M3 900,000 960,000 90,000.00 96,000.00
D Jumlah A + B + C 869,287.50 958,081.25
E OVERHEAD & PROFIT (CONTOH) 10% 86,928.75 95,808.13
F Harga Satuan Pekerjaan (D+E) 956,216.25 1,053,889.38

P.02.f. BONGKAR PASANGAN BATA MERAH


127 P.02.f.1 1 m3 BONGKAR PASANGAN BATA MERAH (MANUAL) 56,919.50 64,295.00
A TENAGA 51,000.00 57,600.00
L.01 0.60 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.06 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
C PERALATAN 745.00 850.00
0.002 bh Palu Godam 80,000 90,000 160.00 180.00
0.003 bh Pahat Beton 20,000 25,000 60.00 75.00
0.007 bh Linggis 75,000 85,000 525.00 595.00
D Jumlah A + B + C 51,745.00 58,450.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,174.50 5,845.00
F Harga Satuan Pekerjaan (D+E) 56,919.50 64,295.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
BONGKAR PASANGAN BATA MERAH dengan JACK
128 P.02.f.2 1 m3 27,500.00 31,020.00
HAMMER
A TENAGA 17,000.00 19,200.00
L.01 0.20 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.04 0.02 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN - -
C PERALATAN 8,000.00 9,000.00
0.020 hr Jack Hammer 400,000 450,000 8,000.00 9,000.00
D Jumlah A + B + C 25,000.00 28,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,500.00 2,820.00
F Harga Satuan Pekerjaan (D+E) 27,500.00 31,020.00

P.03 PEKERJAAN SIARAN DG MORTAR JENIS PC-PP


129 P.03.a 1 m2 SIARAN DG MORTAR JENIS PC-PP TYPE M 57,456.58 63,845.51
(campuran 1PC : 2PP)
A TENAGA 41,400.00 46,350.00
L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.150 OH Tukang Batu 95,000 105,000 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 10,833.25 11,691.38
0.012 m3 Pasir Pasang 315,000 370,000 3,780.00 4,440.00
6.340 kg Portland Cement 1,113 1,144 7,053.25 7,251.38
C PERALATAN - -
- -
D Jumlah A + B + C 52,233.25 58,041.38
E OVERHEAD & PROFIT (CONTOH) 10% 5,223.33 5,804.14
F Harga Satuan Pekerjaan (D+E) 57,456.58 63,845.51

130 P.03.b 1 m2 SIARAN DG MORTAR JENIS PC-PP TYPE S 57,699.95 64,400.33


(campuran 1PC : 3PP)
A TENAGA 41,400.00 46,350.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.1500 OH Tukang Batu 95,000 105,000 14,250.00 15,750.00
L.03 0.0150 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 11,054.50 12,195.75
0.018 m3 Pasir Pasang 315,000 370,000 5,670.00 6,660.00
4.840 kg Portland Cement 1,113 1,144 5,384.50 5,535.75
C PERALATAN - -
- -
D Jumlah A + B + C 52,454.50 58,545.75
E OVERHEAD & PROFIT (CONTOH) 10% 5,245.45 5,854.58
F Harga Satuan Pekerjaan (D+E) 57,699.95 64,400.33

P.04 PEKERJAAN PLESTERAN DG MORTAR JENIS PC-PP


131 P.04.a 1 m2 TRASRAAM TEBAL 1 cm, 59,250.95 65,791.83
DG MORTAR JENIS PC-PP TYPE M (campuran 1PC : 2PP)
A TENAGA 41,400.00 46,350.00
L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.150 OH Tukang Batu 95,000 105,000 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 12,464.50 13,460.75
0.014 m3 Pasir Pasang 315,000 370,000 4,410.00 5,180.00
7.240 kg Portland Cement 1,113 1,144 8,054.50 8,280.75
C PERALATAN - -
- -
D Jumlah A + B + C 53,864.50 59,810.75

E OVERHEAD & PROFIT (CONTOH) 10% 5,386.45 5,981.08


F Harga Satuan Pekerjaan (D+E) 59,250.95 65,791.83
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
132 P.04.b 1 m2 PLESTERAN TEBAL 1 cm, 58,230.70 64,844.45
DG MORTAR JENIS PC-PP TYPE S (campuran 1PC : 3PP)
A TENAGA 41,400.00 46,350.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.1500 OH Tukang Batu 95,000 105,000 14,250.00 15,750.00
L.03 0.0150 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 11,537.00 12,599.50
0.016 m3 Pasir Pasang 315,000 370,000 5,040.00 5,920.00
5.840 kg Portland Cement 1,113 1,144 6,497.00 6,679.50
C PERALATAN - -
- -
D Jumlah A + B + C 52,937.00 58,949.50
E OVERHEAD & PROFIT (CONTOH) 10% 5,293.70 5,894.95
F Harga Satuan Pekerjaan (D+E) 58,230.70 64,844.45

133 P.04.c 1 m2 PLESTERAN TEBAL 1 cm, 57,222.69 63,909.66


DG MORTAR JENIS PC-PP TYPE N (campuran 1PC : 4PP)
A TENAGA 41,400.00 46,350.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.1500 OH Tukang Batu 95,000 105,000 14,250.00 15,750.00
L.03 0.0150 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 10,620.63 11,749.69
0.018 m3 Pasir Pasang 315,000 370,000 5,670.00 6,660.00
4.450 kg Portland Cement 1,113 1,144 4,950.63 5,089.69
C PERALATAN - -
- -
D Jumlah A + B + C 52,020.63 58,099.69
E OVERHEAD & PROFIT (CONTOH) 10% 5,202.06 5,809.97
F Harga Satuan Pekerjaan (D+E) 57,222.69 63,909.66

134 P.04.d 1 m2 TRASRAAM TEBAL 1,5 cm, 77,664.62 86,189.07


DG MORTAR JENIS PC-PP TYPE M (campuran 1PC : 2PP)
A TENAGA 52,930.00 59,260.00
L.01 0.384 OH Pekerja 75,000 85,000 28,800.00 32,640.00
L.02 0.192 OH Tukang Batu 95,000 105,000 18,240.00 20,160.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.038 OH Mandor 100,000 110,000 3,800.00 4,180.00
B BAHAN 17,674.20 19,093.70
0.020 m3 Pasir Pasang 315,000 370,000 6,300.00 7,400.00
10.224 kg Portland Cement 1,113 1,144 11,374.20 11,693.70
C PERALATAN - -
- -
D Jumlah A + B + C 70,604.20 78,353.70
E OVERHEAD & PROFIT (CONTOH) 10% 7,060.42 7,835.37
F Harga Satuan Pekerjaan (D+E) 77,664.62 86,189.07

135 P.04.e 1 m2 PLESTERAN TEBAL 1,5 cm, 76,043.88 84,880.18


DG MORTAR JENIS PC-PP TYPE S (campuran 1PC : 3PP)
A TENAGA 51,030.00 57,170.00
L.01 0.3840 OH Pekerja 75,000 85,000 28,800.00 32,640.00
L.02 0.1920 OH Tukang Batu 95,000 105,000 18,240.00 20,160.00
L.03 0.0190 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.0190 OH Mandor 100,000 110,000 1,900.00 2,090.00
B BAHAN 18,100.80 19,993.80
0.030 m3 Pasir Pasang 315,000 370,000 9,450.00 11,100.00
7.776 kg Portland Cement 1,113 1,144 8,650.80 8,893.80
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -
- -
D Jumlah A + B + C 69,130.80 77,163.80
E OVERHEAD & PROFIT (CONTOH) 10% 6,913.08 7,716.38
F Harga Satuan Pekerjaan (D+E) 76,043.88 84,880.18

136 P.04.f 1 m2 PLESTERAN TEBAL 1,5 cm, 72,134.15 80,556.03


DG MORTAR JENIS PC-PP TYPE N (campuran 1PC : 4PP)
A TENAGA 51,030.00 57,170.00
L.01 0.3840 OH Pekerja 75,000 85,000 28,800.00 32,640.00
L.02 0.1920 OH Tukang Batu 95,000 105,000 18,240.00 20,160.00
L.03 0.0190 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.0190 OH Mandor 100,000 110,000 1,900.00 2,090.00
B BAHAN 14,546.50 16,062.75
0.024 m3 Pasir Pasang 315,000 370,000 7,560.00 8,880.00
6.280 kg Portland Cement 1,113 1,144 6,986.50 7,182.75
C PERALATAN - -
- -
D Jumlah A + B + C 65,576.50 73,232.75
E OVERHEAD & PROFIT (CONTOH) 10% 6,557.65 7,323.28
F Harga Satuan Pekerjaan (D+E) 72,134.15 80,556.03

137 P.04.g 1 m2 PEKERJAAN ACIAN 34,337.19 38,078.91


A TENAGA 27,600.00 30,900.00
L.01 0.2000 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.02 0.1000 OH Tukang Batu 95,000 105,000 9,500.00 10,500.00
L.03 0.0100 OH Kepala Tukang 110,000 120,000 1,100.00 1,200.00
L.04 0.0200 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN 3,615.63 3,717.19
3.250 kg Portland Cement 1,113 1,144 3,615.63 3,717.19
C PERALATAN - -
- -
D Jumlah A + B + C 31,215.63 34,617.19
E OVERHEAD & PROFIT (CONTOH) 10% 3,121.56 3,461.72
F Harga Satuan Pekerjaan (D+E) 34,337.19 38,078.91

138 P.05 1 m3 PASANGAN BATU KOSONG * 373,560.00 476,190.00


A TENAGA 27,600.00 30,900.00
L.01 0.2000 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.02 0.1000 OH Tukang Batu 95,000 105,000 9,500.00 10,500.00
L.03 0.0100 OH Kepala Tukang 110,000 120,000 1,100.00 1,200.00
L.04 0.0200 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN 312,000.00 402,000.00
1.200 m3 Batu Belah 260,000 335,000 312,000.00 402,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 339,600.00 432,900.00
E OVERHEAD & PROFIT (CONTOH) 10% 33,960.00 43,290.00
F Harga Satuan Pekerjaan (D+E) 373,560.00 476,190.00
Catatan :
Jika pasangan batu kosong ini dipasang untuk kontak langsung dengan tanah, maka bahan perlu ditambah koefisien pasir 0,432 m3
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

P.06 PASANGAN BATU BRONJONG KAWAT (SNI 03-0009-1999)


P.06.a PASANGAN BATU BRONJONG KAWAT BENTUK I
P.06.a.1 Bentuk I, tipe A Bronjong kawat
Uk.L=2.0mxB=1.0mxT=1.0m berisi Batu (buat sendiri)
139 P.06.a.1.a 2 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,373,614.00 1,545,544.00
Uk.2,70 mm, kwat sisi 3,40 mm dan Kawat
pengikat 2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 268,800.00 299,390.00
L.01 1.635 OH Pekerja 75,000 85,000 122,625.00 138,975.00
L.02 0.545 OH Tukang Batu 95,000 105,000 51,775.00 57,225.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.229 OH Mandor 100,000 110,000 22,900.00 25,190.00
B BAHAN 979,940.00 1,105,650.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
21.71 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 303,940.00 325,650.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,248,740.00 1,405,040.00
E OVERHEAD & PROFIT (CONTOH) 10% 124,874.00 140,504.00
F Harga Satuan Pekerjaan (D+E) 1,373,614.00 1,545,544.00

140 P.06.a.1.b 2 m3 Kawat Bronjong galvanis dg kawat anyaman tiga 1,389,267.00 1,562,610.50
lilitan Uk.3,0 mm, kwat sisi 4,0 mm dan kawat
pengikat 2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 274,000.00 305,230.00
L.01 1.680 OH Pekerja 75,000 85,000 126,000.00 142,800.00
L.02 0.560 OH Tukang Batu 95,000 105,000 53,200.00 58,800.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.233 OH Mandor 100,000 110,000 23,300.00 25,630.00
B BAHAN 988,970.00 1,115,325.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
22.355 kg Kawat Bronjong Ø 3 mm 14,000 15,000 312,970.00 335,325.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,262,970.00 1,420,555.00
E OVERHEAD & PROFIT (CONTOH) 10% 126,297.00 142,055.50
F Harga Satuan Pekerjaan (D+E) 1,389,267.00 1,562,610.50

141 P.06.a.1.c 2 m3 Kawat Bronjong wire mesh 5 mm ulir dan kawat 1,824,020.00 2,037,365.00
pengikat 2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 448,100.00 499,900.00
L.01 2.865 OH Pekerja 75,000 85,000 214,875.00 243,525.00
L.02 0.955 OH Tukang Batu 95,000 105,000 90,725.00 100,275.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.710 OH Mandor 100,000 110,000 71,000.00 78,100.00
B BAHAN 1,210,100.00 1,352,250.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
38.15 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 534,100.00 572,250.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,658,200.00 1,852,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 165,820.00 185,215.00
F Harga Satuan Pekerjaan (D+E) 1,824,020.00 2,037,365.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

P.06.a.2 Bentuk I, tipe B Bronjong kawat


Uk.L=3.0m x B=1.0m x T=1.0m berisi Batu (buat sendiri)
142 P.06.a.2.a 3 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,569,613.20 2,889,051.00
Uk.2,70 mm, kwat sisi 3,40 mm dan kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 805,000.00 896,040.00
L.01 4.740 OH Pekerja 75,000 85,000 355,500.00 402,900.00
L.02 1.580 OH Tukang Batu 95,000 105,000 150,100.00 165,900.00
L.03 2.100 OH Kepala Tukang 110,000 120,000 231,000.00 252,000.00
L.04 0.684 OH Mandor 100,000 110,000 68,400.00 75,240.00
B BAHAN 1,531,012.00 1,730,370.00
4.20 m3 Batu 260,000 300,000 1,092,000.00 1,260,000.00
31.358 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 439,012.00 470,370.00
C PERALATAN - -
- -
D Jumlah A + B + C 2,336,012.00 2,626,410.00
E OVERHEAD & PROFIT (CONTOH) 10% 233,601.20 262,641.00
F Harga Satuan Pekerjaan (D+E) 2,569,613.20 2,889,051.00

143 P.06.a.2.b 3 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,053,363.40 2,310,605.00
Uk.3,0 mm, kwat sisi 4,0 mm dan kawat pengikat
2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 400,550.00 446,110.00
L.01 2.430 OH Pekerja 75,000 85,000 182,250.00 206,550.00
L.02 0.810 OH Tukang Batu 95,000 105,000 76,950.00 85,050.00
L.03 0.975 OH Kepala Tukang 110,000 120,000 107,250.00 117,000.00
L.04 0.341 OH Mandor 100,000 110,000 34,100.00 37,510.00
B BAHAN 1,466,144.00 1,654,440.00
3.90 m3 Batu 260,000 300,000 1,014,000.00 1,170,000.00
32.296 kg Kawat Bronjong Ø 3 mm 14,000 15,000 452,144.00 484,440.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,866,694.00 2,100,550.00
E OVERHEAD & PROFIT (CONTOH) 10% 186,669.40 210,055.00
F Harga Satuan Pekerjaan (D+E) 2,053,363.40 2,310,605.00

144 P.06.a.2.c 3 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat pengikat 2,622,015.00 2,931,060.00
2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 598,250.00 668,100.00
L.01 4.125 OH Pekerja 75,000 85,000 309,375.00 350,625.00
L.02 1.375 OH Tukang Batu 95,000 105,000 130,625.00 144,375.00
L.03 0.975 OH Kepala Tukang 110,000 120,000 107,250.00 117,000.00
L.04 0.510 OH Mandor 100,000 110,000 51,000.00 56,100.00
B BAHAN 1,785,400.00 1,996,500.00
3.90 m3 Batu 260,000 300,000 1,014,000.00 1,170,000.00
55.10 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 771,400.00 826,500.00
C PERALATAN - -
D Jumlah A + B + C 2,383,650.00 2,664,600.00
E OVERHEAD & PROFIT (CONTOH) 10% 238,365.00 266,460.00
F Harga Satuan Pekerjaan (D+E) 2,622,015.00 2,931,060.00

P.06.a.3 Bentuk I, tipe C Bronjong kawat


Uk.L=4.0m x B=1.0m x T=1.0m berisi Batu
145 P.06.a.3.a 4 m3 Kawat Bronjong galvanis dg kawat anyaman tiga 2,735,319.40 3,076,870.50
lilitan Uk.2,70 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 504,500.00 561,990.00
L.01 3.090 OH Pekerja 75,000 85,000 231,750.00 262,650.00
L.02 1.030 OH Tukang Batu 95,000 105,000 97,850.00 108,150.00
L.03 1.200 OH Kepala Tukang 110,000 120,000 132,000.00 144,000.00
L.04 0.429 OH Mandor 100,000 110,000 42,900.00 47,190.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B BAHAN 1,982,154.00 2,235,165.00


5.20 m3 Batu 260,000 300,000 1,352,000.00 1,560,000.00
45.011 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 630,154.00 675,165.00
C PERALATAN - -
D Jumlah A + B + C 2,486,654.00 2,797,155.00
E OVERHEAD & PROFIT (CONTOH) 10% 248,665.40 279,715.50
F Harga Satuan Pekerjaan (D+E) 2,735,319.40 3,076,870.50

146 P.06.a.3.b 4 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,704,149.80 3,044,068.50
Uk.3,0 mm, kwat sisi 4,0 mm dan kawat pengikat
2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 515,000.00 573,780.00
L.01 3.180 OH Pekerja 75,000 85,000 238,500.00 270,300.00
L.02 1.060 OH Tukang Batu 95,000 105,000 100,700.00 111,300.00
L.03 1.200 OH Kepala Tukang 110,000 120,000 132,000.00 144,000.00
L.04 0.438 OH Mandor 100,000 110,000 43,800.00 48,180.00
B BAHAN 1,943,318.00 2,193,555.00
5.20 m3 Batu 260,000 300,000 1,352,000.00 1,560,000.00
42.237 kg Kawat Bronjong Ø 3 mm 14,000 15,000 591,318.00 633,555.00
C PERALATAN - -
D Jumlah A + B + C 2,458,318.00 2,767,335.00
E OVERHEAD & PROFIT (CONTOH) 10% 245,831.80 276,733.50
F Harga Satuan Pekerjaan (D+E) 2,704,149.80 3,044,068.50

147 P.06.a.3.c 4 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat 3,462,140.00 3,871,120.00
pengikat 2,0mm uk. lobang heksagonal 100x100 mm
A TENAGA 786,000.00 877,700.00
L.01 5.400 OH Pekerja 75,000 85,000 405,000.00 459,000.00
L.02 1.800 OH Tukang Batu 95,000 105,000 171,000.00 189,000.00
L.03 1.300 OH Kepala Tukang 110,000 120,000 143,000.00 156,000.00
L.04 0.670 OH Mandor 100,000 110,000 67,000.00 73,700.00
B BAHAN 2,361,400.00 2,641,500.00
5.20 m3 Batu 260,000 300,000 1,352,000.00 1,560,000.00
72.10 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 1,009,400.00 1,081,500.00
C PERALATAN - -
- -
D Jumlah A + B + C 3,147,400.00 3,519,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 314,740.00 351,920.00
F Harga Satuan Pekerjaan (D+E) 3,462,140.00 3,871,120.00

P.06.a.4 Bentuk I, tipe D Bronjong kawat


Uk.L=2.0m x B=1.0m x T=0.5m berisi Batu
148 P.06.a.4.a 1 m3 Kawat Bronjong galvanis dg kawat anyaman tiga 810,205.00 907,588.00
lilitan Uk.2,70 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm uk. lobang heksagonal 80 x 100 mm
A TENAGA 187,150.00 208,580.00
L.01 1.140 OH Pekerja 75,000 85,000 85,500.00 96,900.00
L.02 0.380 OH Tukang Batu 95,000 105,000 36,100.00 39,900.00
L.03 0.325 OH Kepala Tukang 110,000 120,000 35,750.00 39,000.00
L.04 0.298 OH Mandor 100,000 110,000 29,800.00 32,780.00
B BAHAN 549,400.00 616,500.00
1.30 m3 Batu 260,000 300,000 338,000.00 390,000.00
15.100 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 211,400.00 226,500.00
C PERALATAN - -
- -
D Jumlah A + B + C 736,550.00 825,080.00
E OVERHEAD & PROFIT (CONTOH) 10% 73,655.00 82,508.00
F Harga Satuan Pekerjaan (D+E) 810,205.00 907,588.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

149 P.06.a.4.b 1 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 821,330.40 919,715.50
Uk.3,0 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 190,950.00 212,840.00
L.01 1.170 OH Pekerja 75,000 85,000 87,750.00 99,450.00
L.02 0.390 OH Tukang Batu 95,000 105,000 37,050.00 40,950.00
L.03 0.325 OH Kepala Tukang 110,000 120,000 35,750.00 39,000.00
L.04 0.304 OH Mandor 100,000 110,000 30,400.00 33,440.00
B BAHAN 555,714.00 623,265.00
1.30 m3 Batu 260,000 300,000 338,000.00 390,000.00
15.551 kg Kawat Bronjong Ø 3 mm 14,000 15,000 217,714.00 233,265.00
C PERALATAN - -
- -
D Jumlah A + B + C 746,664.00 836,105.00
E OVERHEAD & PROFIT (CONTOH) 10% 74,666.40 83,610.50
F Harga Satuan Pekerjaan (D+E) 821,330.40 919,715.50

150 P.06.a.4.c 1 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat pengikat 1,077,417.00 1,198,956.00
2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 270,050.00 302,010.00
L.01 1.980 OH Pekerja 75,000 85,000 148,500.00 168,300.00
L.02 0.660 OH Tukang Batu 95,000 105,000 62,700.00 69,300.00
L.03 0.325 OH Kepala Tukang 110,000 120,000 35,750.00 39,000.00
L.04 0.231 OH Mandor 100,000 110,000 23,100.00 25,410.00
B BAHAN 709,420.00 787,950.00
1.30 m3 Batu 260,000 300,000 338,000.00 390,000.00
26.53 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 371,420.00 397,950.00
C PERALATAN - -
D Jumlah A + B + C 979,470.00 1,089,960.00
E OVERHEAD & PROFIT (CONTOH) 10% 97,947.00 108,996.00
F Harga Satuan Pekerjaan (D+E) 1,077,417.00 1,198,956.00

P.06.a.5 Bentuk I, tipe E Bronjong kawat


Uk.L=3.0m x B=1.0m x T=0.5m berisi Batu
151 P.06.a.5.a 1.5 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,174,357.80 1,316,496.50
Uk.2,70 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 252,780.00 282,010.00
L.01 1.665 OH Pekerja 75,000 85,000 124,875.00 141,525.00
L.02 0.555 OH Tukang Batu 95,000 105,000 52,725.00 58,275.00
L.03 0.488 OH Kepala Tukang 110,000 120,000 53,680.00 58,560.00
L.04 0.215 OH Mandor 100,000 110,000 21,500.00 23,650.00
B BAHAN 814,818.00 914,805.00
1.95 m3 Batu 260,000 300,000 507,000.00 585,000.00
21.987 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 307,818.00 329,805.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,067,598.00 1,196,815.00
E OVERHEAD & PROFIT (CONTOH) 10% 106,759.80 119,681.50
F Harga Satuan Pekerjaan (D+E) 1,174,357.80 1,316,496.50

152 P.06.a.5.b 1.5 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,479,627.60 1,656,446.00
Uk.3,0 mm, kwat sisi 4,0 mm dan kawat pengikat
2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 521,100.00 581,200.00
L.01 3.390 OH Pekerja 75,000 85,000 254,250.00 288,150.00
L.02 1.130 OH Tukang Batu 95,000 105,000 107,350.00 118,650.00
L.03 1.050 OH Kepala Tukang 110,000 120,000 115,500.00 126,000.00
L.04 0.440 OH Mandor 100,000 110,000 44,000.00 48,400.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B BAHAN 824,016.00 924,660.00


1.95 m3 Batu 260,000 300,000 507,000.00 585,000.00
22.644 kg Kawat Bronjong Ø 3 mm 14,000 15,000 317,016.00 339,660.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,345,116.00 1,505,860.00
E OVERHEAD & PROFIT (CONTOH) 10% 134,511.60 150,586.00
F Harga Satuan Pekerjaan (D+E) 1,479,627.60 1,656,446.00

153 P.06.a.5.c 1.5 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat pengikat 1,964,798.00 2,188,560.00
2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 738,500.00 825,300.00
L.01 5.250 OH Pekerja 75,000 85,000 393,750.00 446,250.00
L.02 1.750 OH Tukang Batu 95,000 105,000 166,250.00 183,750.00
L.03 1.050 OH Kepala Tukang 110,000 120,000 115,500.00 126,000.00
L.04 0.630 OH Mandor 100,000 110,000 63,000.00 69,300.00
B BAHAN 1,047,680.00 1,164,300.00
1.95 m3 Batu 260,000 300,000 507,000.00 585,000.00
38.620 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 540,680.00 579,300.00
C PERALATAN - -
D Jumlah A + B + C 1,786,180.00 1,989,600.00
E OVERHEAD & PROFIT (CONTOH) 10% 178,618.00 198,960.00
F Harga Satuan Pekerjaan (D+E) 1,964,798.00 2,188,560.00

P.06.a.6 Bentuk I, tipe F Bronjong kawat


Uk.L=4.0m x B=1.0m x T=0.5m berisi Batu
154 P.06.a.6.a 2 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,553,213.20 1,741,542.00
Uk.2,70 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 332,000.00 370,350.00
L.01 2.175 OH Pekerja 75,000 85,000 163,125.00 184,875.00
L.02 0.725 OH Tukang Batu 95,000 105,000 68,875.00 76,125.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.285 OH Mandor 100,000 110,000 28,500.00 31,350.00
B BAHAN 1,080,012.00 1,212,870.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
28.858 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 404,012.00 432,870.00
C PERALATAN - -
D Jumlah A + B + C 1,412,012.00 1,583,220.00
E OVERHEAD & PROFIT (CONTOH) 10% 141,201.20 158,322.00
F Harga Satuan Pekerjaan (D+E) 1,553,213.20 1,741,542.00

155 P.06.a.6.b 2 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,573,983.40 1,764,185.50
Uk.3,0 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 100 x 120 mm
A TENAGA 338,800.00 377,990.00
L.01 2.235 OH Pekerja 75,000 85,000 167,625.00 189,975.00
L.02 0.745 OH Tukang Batu 95,000 105,000 70,775.00 78,225.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.289 OH Mandor 100,000 110,000 28,900.00 31,790.00
B BAHAN 1,092,094.00 1,225,815.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
29.721 kg Kawat Bronjong Ø 3 mm 14,000 15,000 416,094.00 445,815.00
C PERALATAN - -
D Jumlah A + B + C 1,430,894.00 1,603,805.00
E OVERHEAD & PROFIT (CONTOH) 10% 143,089.40 160,380.50
F Harga Satuan Pekerjaan (D+E) 1,573,983.40 1,764,185.50
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

156 P.06.a.6.c 2 m3 Kawat Bronjong wire mesh 5 mm ulir&kawat pengikat 2,047,958.00 2,279,750.00
2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 475,700.00 531,700.00
L.01 3.405 OH Pekerja 75,000 85,000 255,375.00 289,425.00
L.02 1.135 OH Tukang Batu 95,000 105,000 107,825.00 119,175.00
L.03 0.650 OH Kepala Tukang 110,000 120,000 71,500.00 78,000.00
L.04 0.410 OH Mandor 100,000 110,000 41,000.00 45,100.00
B BAHAN 1,386,080.00 1,540,800.00
2.60 m3 Batu 260,000 300,000 676,000.00 780,000.00
50.72 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 710,080.00 760,800.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,861,780.00 2,072,500.00
E OVERHEAD & PROFIT (CONTOH) 10% 186,178.00 207,250.00
F Harga Satuan Pekerjaan (D+E) 2,047,958.00 2,279,750.00

Pasang Bronjong pabrikasi (TENAGA KERJA UNT BATU


157 P.06.a.7 1 m3 670,175.00 752,400.00
BRONJONG)

A TENAGA 21,250.00 24,000.00


L.01 0.250 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN 588,000.00 660,000.00
1.30 m3 Batu 260,000 300,000 338,000.00 390,000.00
1.00 bh Kawat Bronjong 250,000 270,000 250,000.00 270,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 609,250.00 684,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 60,925.00 68,400.00
F Harga Satuan Pekerjaan (D+E) 670,175.00 752,400.00

P.06 PASANGAN BATU BRONJONG KAWAT (SNI 03-0009-1999)

P.06.b PASANGAN BATU BRONJONG KAWAT BENTUK II


P.06.b.1 Bentuk II, tipe G Bronjong kawat
Uk.L=6.0mxB=2.0mxT=0.17m berisi Batu
158 P.06.b.1 2.04 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,561,904.40 2,866,523.00
Uk.2,00 mm, kwat sisi 3,40 mm & Kawat pengikat
2,0mm, ukuran lobang heksagonal 60 x 80 mm
A TENAGA 1,063,880.00 1,189,240.00
L.01 7.650 OH Pekerja 75,000 85,000 573,750.00 650,250.00
L.02 2.550 OH Tukang Batu 95,000 105,000 242,250.00 267,750.00
L.03 1.428 OH Kepala Tukang 110,000 120,000 157,080.00 171,360.00
L.04 0.908 OH Mandor 100,000 110,000 90,800.00 99,880.00
B BAHAN 1,265,124.00 1,416,690.00
2.856 m3 Batu 260,000 300,000 742,560.00 856,800.00
37.326 kg Kawat Bronjong Ø 2,0 mm 14,000 15,000 522,564.00 559,890.00
C PERALATAN - -
D Jumlah A + B + C 2,329,004.00 2,605,930.00
E OVERHEAD & PROFIT (CONTOH) 10% 232,900.40 260,593.00
F Harga Satuan Pekerjaan (D+E) 2,561,904.40 2,866,523.00

159 P.06.b.1.b 2.04 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,030,769.40 2,260,896.00
Uk.2,7 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 447,030.00 499,470.00
L.01 3.150 OH Pekerja 75,000 85,000 236,250.00 267,750.00
L.02 1.050 OH Tukang Batu 95,000 105,000 99,750.00 110,250.00
L.03 0.663 OH Kepala Tukang 110,000 120,000 72,930.00 79,560.00
L.04 0.381 OH Mandor 100,000 110,000 38,100.00 41,910.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B BAHAN 1,399,124.00 1,555,890.00


2.652 m3 Batu 260,000 300,000 689,520.00 795,600.00
50.686 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 709,604.00 760,290.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,846,154.00 2,055,360.00
E OVERHEAD & PROFIT (CONTOH) 10% 184,615.40 205,536.00
F Harga Satuan Pekerjaan (D+E) 2,030,769.40 2,260,896.00

P.06.b.2 Bentuk II, tipe H Bronjong kawat


Uk.L=6.0m x B=2.0m x T=0.23m berisi Batu
160 P.06.b.2.a 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,265,186.00 2,540,488.50
Uk.2,00 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 60 x 80 mm
A TENAGA 576,670.00 644,160.00
L.01 4.020 OH Pekerja 75,000 85,000 301,500.00 341,700.00
L.02 1.340 OH Tukang Batu 95,000 105,000 127,300.00 140,700.00
L.03 0.897 OH Kepala Tukang 110,000 120,000 98,670.00 107,640.00
L.04 0.492 OH Mandor 100,000 110,000 49,200.00 54,120.00
B BAHAN 1,482,590.00 1,665,375.00
3.588 m3 Batu 260,000 300,000 932,880.00 1,076,400.00
39.265 kg Kawat Bronjong Ø 2,0 mm 14,000 15,000 549,710.00 588,975.00
C PERALATAN - -
D Jumlah A + B + C 2,059,260.00 2,309,535.00
E OVERHEAD & PROFIT (CONTOH) 10% 205,926.00 230,953.50
F Harga Satuan Pekerjaan (D+E) 2,265,186.00 2,540,488.50

161 P.06.b.2.b 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,427,871.60 2,712,022.50
Uk.2,7 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 527,670.00 589,140.00
L.01 3.600 OH Pekerja 75,000 85,000 270,000.00 306,000.00
L.02 1.200 OH Tukang Batu 95,000 105,000 114,000.00 126,000.00
L.03 0.897 OH Kepala Tukang 110,000 120,000 98,670.00 107,640.00
L.04 0.450 OH Mandor 100,000 110,000 45,000.00 49,500.00
B BAHAN 1,679,486.00 1,876,335.00
3.588 m3 Batu 260,000 300,000 932,880.00 1,076,400.00
53.329 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 746,606.00 799,935.00
C PERALATAN - -
D Jumlah A + B + C 2,207,156.00 2,465,475.00
E OVERHEAD & PROFIT (CONTOH) 10% 220,715.60 246,547.50
F Harga Satuan Pekerjaan (D+E) 2,427,871.60 2,712,022.50

P.06.b.3 Bentuk II, tipe I Bronjong kawat


Uk.L=6.0m x B=2.0m x T=0,30m berisi Batu
162 P.06.b.3.a 3.6 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,679,028.00 3,011,943.00
Uk.2,00 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 60 x 80 mm
A TENAGA 637,400.00 711,330.00
L.01 4.260 OH Pekerja 75,000 85,000 319,500.00 362,100.00
L.02 1.420 OH Tukang Batu 95,000 105,000 134,900.00 149,100.00
L.03 1.170 OH Kepala Tukang 110,000 120,000 128,700.00 140,400.00
L.04 0.543 OH Mandor 100,000 110,000 54,300.00 59,730.00
B BAHAN 1,798,080.00 2,026,800.00
4.68 m3 Batu 260,000 300,000 1,216,800.00 1,404,000.00
41.520 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 581,280.00 622,800.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
D Jumlah A + B + C 2,435,480.00 2,738,130.00
E OVERHEAD & PROFIT (CONTOH) 10% 243,548.00 273,813.00
F Harga Satuan Pekerjaan (D+E) 2,679,028.00 3,011,943.00

163 P.06.b.3.b 3.6 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 3,169,856.80 3,551,295.00
Uk.2,7 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 875,400.00 978,570.00
L.01 6.300 OH Pekerja 75,000 85,000 472,500.00 535,500.00
L.02 2.100 OH Tukang Batu 95,000 105,000 199,500.00 220,500.00
L.03 1.170 OH Kepala Tukang 110,000 120,000 128,700.00 140,400.00
L.04 0.747 OH Mandor 100,000 110,000 74,700.00 82,170.00
B BAHAN 2,006,288.00 2,249,880.00
4.68 m3 Batu 260,000 300,000 1,216,800.00 1,404,000.00
56.392 kg Kawat Bronjong Ø 2,7 mm 14,000 15,000 789,488.00 845,880.00
C PERALATAN - -
D Jumlah A + B + C 2,881,688.00 3,228,450.00
E OVERHEAD & PROFIT (CONTOH) 10% 288,168.80 322,845.00
F Harga Satuan Pekerjaan (D+E) 3,169,856.80 3,551,295.00

164 P.06.b.4 1 m3 Pasangan bronjong pabrikasi 415,250.00 477,180.00


(tenaga kerja untuk 1m3 batu bronjong)
A TENAGA 25,500.00 28,800.00
L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 352,000.00 405,000.00
1.30 m3 Batu 260,000 300,000 338,000.00 390,000.00
1.00 kg Kawat Bronjong 14,000 15,000 14,000.00 15,000.00
C PERALATAN - -
D Jumlah A + B + C 377,500.00 433,800.00
E OVERHEAD & PROFIT (CONTOH) 10% 37,750.00 43,380.00
F Harga Satuan Pekerjaan (D+E) 415,250.00 477,180.00

P.07. Cerucuk dan Pemasangan Modul Bronjong


P.07.a.1 1 m' Panjang Cerucuk Kayu / Dolken Ø 8 - 10 cm

Untuk pemancangan kayu atau dolken Ø 8 - 10 cm menggunakan AHSP F.02 per-m' penetrasi tiang pancang kayu dolken Ø 8 - 10 cm, Terkait
dengan asesoris sepatu adan atau sambungan kayu atau dolken Ø 8 - 10 cm harus disesuaikan, misalnya menggunakan sepatu atau tidak dan
berapa jumlah sambungan yang digunakan?, Berapa panjang kayu atau dolken yang digunakan dapat pula berbeda dengan panjang penetrasi
yang dipancangnya. Sebaiknya dibuat masing-masing secara terpisah yaitu :

a. Panjang kayu atau dolken yang digunakan sesuai dengan harga materialnya;
b. jika menggunakan sepatu pancang sesuai harga materialnya; dan

c. biaya per-m' pemancangan sesuai dengan harga penjualannya pada AHSP F.02 per - m' penetrasi tiang pancang kayu dolken Ø 8 - 10 cm

165 P.07.b 1 m' Panjang Cerucuk Bambu Ø 8 - 10 cm 22,308.00 26,823.50


A TENAGA 16,200.00 18,520.00
L.01 0.120 OH Pekerja 75,000 85,000 9,000.00 10,200.00
L.04 0.012 OH Mandor 100,000 110,000 1,200.00 1,320.00
L.05 0.040 OH M a s i n i s / Operator 150,000 175,000 6,000.00 7,000.00
B BAHAN 3,150.00 4,725.00
1.05 m' Bambu 3,000 4,500 3,150.00 4,725.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN 930.00 1,140.00


0.006 hr Tripod Tinggi 5 m' 125,000 150,000 750.00 900.00
0.006 hr Alat Pancang Hammer 0,5 ton 30,000 40,000 180.00 240.00

D Jumlah A + B + C 20,280.00 24,385.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,028.00 2,438.50
F Harga Satuan Pekerjaan (D+E) 22,308.00 26,823.50

166 P.07.c 1 m' Panjang Cerucuk Tiang Beton Ø 10 - 15 cm 102,142.41 116,492.24


A TENAGA 4,900.00 5,590.00
L.01 0.040 OH Pekerja 75,000 85,000 3,000.00 3,400.00
L.04 0.004 OH M a n d o r 100,000 110,000 400.00 440.00
L.05 0.010 OH M a s i n i s / Operator 150,000 175,000 1,500.00 1,750.00
B BAHAN 80,206.74 90,812.04
1.03 m' Tiang Beton Ø 10 - 15 cm 77,870.62 88,167.02 80,206.74 90,812.04
C PERALATAN 7,750.00 9,500.00
0.050 hr Tripod Tinggi 5 m' 125,000 150,000 6,250.00 7,500.00
0.050 hr Alat Pancang Hammer 0,5 ton 30,000 40,000 1,500.00 2,000.00
- - - -
D Jumlah A + B + C 92,856.74 105,902.04
E OVERHEAD & PROFIT (CONTOH) 10% 9,285.67 10,590.20
F Harga Satuan Pekerjaan (D+E) 102,142.41 116,492.24

167 P.07.d 1 m3 Pemasangan Modul Bronjong Kawat menjadi 52,525.00 58,465.00


Struktur Krib Sungai
A TENAGA 20,250.00 23,150.00
L.01 0.150 OH Pekerja 75,000 85,000 11,250.00 12,750.00
L.04 0.015 OH M a n d o r 100,000 110,000 1,500.00 1,650.00
L.05 0.050 OH M a s i n i s / Operator crane*) 150,000 175,000 7,500.00 8,750.00
B BAHAN - -
**) - -
C PERALATAN 27,500.00 30,000.00
0.050 hr Crane 5 ton (long arm a5 m) 550,000 600,000 27,500.00 30,000.00
D Jumlah A + B + C 47,750.00 53,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,775.00 5,315.00
F Harga Satuan Pekerjaan (D+E) 52,525.00 58,465.00
*) jika operator crane sudah tercantum dalam sewa hari crane, maka HSD operator Crane = 0
**) untuk bronjong yang menempel dengan tanah perlu ditambahkan bahan tambahan yang disesuaikan dengan fungsinya :
a. Lapisan ijuk tebal 5 cm = 1,150 m3
b. Pasir atau koral/ kerikil = 0,432 m3
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

P.08 PASANGAN BATU MUKA DAN BATU CANDI


168 P.08.a.1 1 m2 Pasangan Batu Muka 195,588.25 222,253.63
A TENAGA 33,120.00 37,080.00
L.01 0.240 OH Pekerja 75,000 85,000 18,000.00 20,400.00
L.02 0.120 OH Tukang Batu 95,000 105,000 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000 120,000 1,320.00 1,440.00
L.04 0.024 OH Mandor 100,000 110,000 2,400.00 2,640.00
B BAHAN 144,687.50 164,968.75
1.250 m2 Batu Muka 105,000 120,000 131,250.00 150,000.00
0.025 m3 Pasir Pasang 315,000 370,000 7,875.00 9,250.00
5.000 kg Portland Cemen 1,112.50 1,143.75 5,562.50 5,718.750
C PERALATAN - -
- -
D Jumlah A + B + C 177,807.50 202,048.75
E OVERHEAD & PROFIT (CONTOH) 10% 17,780.75 20,204.88
F Harga Satuan Pekerjaan (D+E) 195,588.25 222,253.63
- Pembongkaran pasangan batu candi 35% harga pasangan

- Tebal batu muka diasumsikan tebal 5 s/d 6,5 cm


- Pemasangan batu disesuaikan dengan specifikasi teknik, cara pemasangan batu dan batu muka nya harus menyatu

169 P.08.b.1 1 m2 Pasangan Batu Candi 202,463.25 215,378.63


A TENAGA 33,120.00 37,080.00
L.01 0.240 OH Pekerja 75,000 85,000 18,000.00 20,400.00
L.02 0.120 OH Tukang Batu 95,000 105,000 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000 120,000 1,320.00 1,440.00
L.04 0.024 OH Mandor 100,000 110,000 2,400.00 2,640.00
B BAHAN 150,937.50 158,718.75
1.250 m2 Batu Candi 110,000 115,000 137,500.00 143,750.00
0.025 m3 Pasir Pasang 315,000 370,000 7,875.00 9,250.00
5.000 kg Portland Cemen 1,112.50 1,143.75 5,562.50 5,718.750
C PERALATAN - -
- -
D Jumlah A + B + C 184,057.50 195,798.75
E OVERHEAD & PROFIT (CONTOH) 10% 18,405.75 19,579.88

F Harga Satuan Pekerjaan (D+E) 202,463.25 215,378.63

- Pembongkaran pasangan batu candi 35% harga pasangan


- Pemasangan batu disesuaikan dengan specifikasi teknik, cara pemasangan batu dan batu candi nya harus menyatu

P.09 PASANGAN GEOTEKSTIL


170 P.09.a.1 1 m2 Pemasangan Geotekstil Tipe A tipis 28,325.00 30,910.00
A TENAGA 10,000.00 11,300.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.02 0.020 OH Tukang Gali 75,000 85,000 1,500.00 1,700.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
B BAHAN 15,750.00 16,800.00
1.050 m2 Geotekstil 15,000 16,000 15,750.00 16,800.00
C PERALATAN - -
- -
D Jumlah A + B + C 25,750.00 28,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,575.00 2,810.00
F Harga Satuan Pekerjaan (D+E) 28,325.00 30,910.00

171 P.09.b.1 1 m2 Pemasangan Geotekstil Tipe B, tebal sedang 37,202.00 41,272.00


A TENAGA 16,000.00 18,080.00
L.01 0.160 OH Pekerja 75,000 85,000 12,000.00 13,600.00
L.02 0.032 OH Tukang Gali 75,000 85,000 2,400.00 2,720.00
L.04 0.016 OH Mandor 100,000 110,000 1,600.00 1,760.00
B BAHAN 17,820.00 19,440.00
1.080 m2 Geotekstil 16,500 18,000 17,820.00 19,440.00
C PERALATAN - -
- -

D Jumlah A + B + C 33,820.00 37,520.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,382.00 3,752.00

F Harga Satuan Pekerjaan (D+E) 37,202.00 41,272.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

172 P.09.c.1 1 m2 Pemasangan Geotekstil Tipe C, tebal 49,390.00 54,032.00

A TENAGA 24,000.00 27,120.00


L.01 0.240 OH Pekerja 75,000 85,000 18,000.00 20,400.00

L.02 0.048 OH Tukang Gali 75,000 85,000 3,600.00 4,080.00


L.04 0.024 OH Mandor 100,000 110,000 2,400.00 2,640.00

B BAHAN 20,900.00 22,000.00


1.100 m2 Geotekstil 19,000 20,000 20,900.00 22,000.00
C PERALATAN - -

- -
D Jumlah A + B + C 44,900.00 49,120.00

E OVERHEAD & PROFIT (CONTOH) 10% 4,490.00 4,912.00


F Harga Satuan Pekerjaan (D+E) 49,390.00 54,032.00

PASANGAN BAR SCREEN (SARINGAN KASAR), BANGUNAN INTAKE, PENGUKUR, DAN PENGATUR

Saringan kasar terbuat dari besi beton sesuai kebutuhan, misal menggunakan besi beton Ø 12 mm berjarak as satu sama lain 3,5
cm dihitung untuk 1 m2 saringan kasar AHSPnya sebagai berikut :

173 P.10 1 bh PASANGAN BAR SCREEN / SARINGAN KASAR 471,350.00 508,893.00


A TENAGA 90,250.00 101,250.00

L.01 0.750 OH Pekerja 75,000 85,000 56,250.00 63,750.00


L.02 0.250 OH Tukang Batu 95,000 105,000 23,750.00 26,250.00

L.03 0.025 OH Kepala Tukang Batu 110,000 120,000 2,750.00 3,000.00


L.04 0.075 OH Mandor 100,000 110,000 7,500.00 8,250.00
B BAHAN 334,300.00 356,640.00
30.000 m' Besi Beton Ø 12 mm 7,916.67 8,500.00 237,500.00 255,000.00
4.000 m' Besi Profil L.40.40.4 24,200 25,410 96,800.00 101,640.00

C PERALATAN 3,950.00 4,740.00


0.150 hr Alat Las 25,000 30,000 3,750.00 4,500.00

0.020 hr Bor Listrik 10,000 12,000 200.00 240.00


D Jumlah A + B + C 428,500.00 462,630.00
E OVERHEAD & PROFIT (CONTOH) 10% 42,850.00 46,263.00
F Harga Satuan Pekerjaan (D+E) 471,350.00 508,893.00
BANGUNAN PENGUKUR DAPAT TERBUAT DARI BETON
ATAU PASANGAN BATU KALI DIPLESTER / BATU MUKA
YANG DILENGKAPI ALAT AMBANG UKUR, AMBANG UKUR
DARI BAJA PROFIL L.40.40.4&PEMASANGAN PAKAI RAAM SET

PASANGAN AMBANG UKUR PADA BANGUNAN


174 P.11 1 bh 11,696,525.50 12,284,299.50
PENGUKUR DAN ATAU PENGATUR

PENGUKUR DAN/ATAU PENGATUR


A TENAGA 34,555.00 38,685.00
L.01 0.250 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.02 0.125 OH Tukang Batu 95,000 105,000 11,875.00 13,125.00
L.03 0.013 OH Kepala Tukang Batu 110,000 120,000 1,430.00 1,560.00
L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN 10,596,800.00 11,126,640.00
21.000 bh Dynabolt/raam set Ø 8 mm panj 4 - 5 cm *) 500,000 525,000 10,500,000.00 11,025,000.00
4.000 m' Besi Profil L.40.40.4 *) 24,200 25,410 96,800.00 101,640.00
C PERALATAN 1,850.00 2,220.00
0.050 hr Alat Las 25,000 30,000 1,250.00 1,500.00
0.060 hr Bor Listrik 10,000 12,000 600.00 720.00
D Jumlah A + B + C 10,633,205.00 11,167,545.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,063,320.50 1,116,754.50
F Harga Satuan Pekerjaan (D+E) 11,696,525.50 12,284,299.50
*) sesuai dengan spek atau kebutuhan lapangan
harga barang sebagai contoh (silahkan disesuaikan)

P.12 PASANGAN LEMPENG RUMPUT


175 P.12.a 1 m2 Penanaman Rumput Lempengan 23,870.00 25,685.00
A TENAGA 8,500.00 9,600.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN 13,200.00 13,750.00
1.100 m2 Gebalan Rumput 12,000 12,500 13,200.00 13,750.00
C PERALATAN - -
- -
D Jumlah A + B + C 21,700.00 23,350.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,170.00 2,335.00
F Harga Satuan Pekerjaan (D+E) 23,870.00 25,685.00

176 P.12.b.1.a 1 m2 Pembabadan Rumput secara umum dan manual 1,168.75 1,320.00
A TENAGA 1,062.50 1,200.00
L.01 0.01250 OH Pekerja 75,000 85,000 937.50 1,062.50
L.04 0.00125 OH Mandor 100,000 110,000 125.00 137.50
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 1,062.50 1,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 106.25 120.00
F Harga Satuan Pekerjaan (D+E) 1,168.75 1,320.00

P.12.b.1.b PERHITUNGAN SECARA DETAIL

Daerah datar sampai pelandaian naik dengan kemiringan


177 P.12.b.1.b.1 1 m2 748.00 844.80
1V : 10H

A TENAGA 680.00 768.00


L.01 0.0080 OH Pekerja 75,000 85,000 600.00 680.00
L.04 0.0008 OH Mandor 100,000 110,000 80.00 88.00
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 680.00 768.00
E OVERHEAD & PROFIT (CONTOH) 10% 68.00 76.80
F Harga Satuan Pekerjaan (D+E) 748.00 844.80

Daerah datar sampai pelandaian naik dengan kemiringan


178 P.12.b.1.b.2 1 m2 1,168.75 1,320.00
1V : 2,5H

A TENAGA 1,062.50 1,200.00


L.01 0.0125 OH Pekerja 75,000 85,000 937.50 1,062.50
L.04 0.0013 OH Mandor 100,000 110,000 125.00 137.50
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 1,062.50 1,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 106.25 120.00
F Harga Satuan Pekerjaan (D+E) 1,168.75 1,320.00

Daerah datar sampai pelandaian naik dengan kemiringan


179 P.12.b.1.b.3 1 m2 1,561.45 1,763.52
1V : 1H

A TENAGA 1,419.50 1,603.20


L.01 0.0167 OH Pekerja 75,000 85,000 1,252.50 1,419.50
L.04 0.0017 OH Mandor 100,000 110,000 167.00 183.70
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 1,419.50 1,603.20
E OVERHEAD & PROFIT (CONTOH) 10% 141.95 160.32
F Harga Satuan Pekerjaan (D+E) 1,561.45 1,763.52
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Daerah datar sampai pelandaian naik dengan kemiringan


180 P.12.b.1.b.4 1 m2 2,337.50 2,640.00
1V : 1H s/d 2,5V : 1H

A TENAGA 2,125.00 2,400.00


L.01 0.0250 OH Pekerja 75,000 85,000 1,875.00 2,125.00
L.04 0.0025 OH Mandor 100,000 110,000 250.00 275.00
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 2,125.00 2,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 212.50 240.00
F Harga Satuan Pekerjaan (D+E) 2,337.50 2,640.00

Daerah datar sampai pelandaian naik dengan kemiringan


181 P.12.b.1.b.5 1 m2 4,675.00 5,280.00
2,5V : 1H Sampai Tegak

A TENAGA 4,250.00 4,800.00


L.01 0.0500 OH Pekerja 75,000 85,000 3,750.00 4,250.00
L.04 0.0050 OH Mandor 100,000 110,000 500.00 550.00
B BAHAN - -
- - -
C PERALATAN - -
- hr Alat Potong Rumput 7,500 8,000 - -
D Jumlah A + B + C 4,250.00 4,800.00
E OVERHEAD & PROFIT (CONTOH) 10% 425.00 480.00
F Harga Satuan Pekerjaan (D+E) 4,675.00 5,280.00

P.12.b.2 Secara Semi Makanis


Perhitungan Secara Umum (Jika medan tidak diketahui
182 P.12.b.2.a 1 m2 410.85 467.94
secara detail)

A TENAGA 255.00 288.00


L.01 0.00300 OH Pekerja 75,000 85,000 225.00 255.00
L.04 0.00030 OH Mandor 100,000 110,000 30.00 33.00
B BAHAN 58.50 62.40
0.0078 ltr 7,500 8,000 58.50 62.40
C PERALATAN 60.00 75.00
0.003 hr Mesin Potong Rumput 20,000 25,000 60.00 75.00
D Jumlah A + B + C 373.50 425.40
E OVERHEAD & PROFIT (CONTOH) 10% 37.35 42.54
F Harga Satuan Pekerjaan (D+E) 410.85 467.94

Perhitungan secara detail (jika diketahui kondisi medan


P.12.b.2.b
secara detail)

Daerah datar sampai pelandaian naik dengan kemiringan


183 P.12.b.2.b.1 1 m2 386.65 440.11
1V : 10H

A TENAGA 255.00 288.00


L.01 0.00300 OH Pekerja 75,000 85,000 225.00 255.00
L.04 0.00030 OH Mandor 100,000 110,000 30.00 33.00
B BAHAN 46.50 49.60
0.0062 ltr 7,500 8,000 46.50 49.60
C PERALATAN 50.00 62.50
0.0025 hr Mesin Potong Rumput 20,000 25,000 50.00 62.50
D Jumlah A + B + C 351.50 400.10
E OVERHEAD & PROFIT (CONTOH) 10% 35.15 40.01
F Harga Satuan Pekerjaan (D+E) 386.65 440.11

Daerah datar sampai pelandaian naik dengan kemiringan


184 P.12.b.2.b.2 1 m2 421.99 480.81
1V : 10H s/d 1V : 2,5H
A TENAGA 263.50 297.60
L.01 0.00310 OH Pekerja 75,000 85,000 232.50 263.50
L.04 0.00031 OH Mandor 100,000 110,000 31.00 34.10
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN 58.13 62.00
0.0078 ltr 7,500 8,000 58.13 62.00
C PERALATAN 62.00 77.50
0.0031 hr Mesin Potong Rumput 20,000 25,000 62.00 77.50
D Jumlah A + B + C 383.63 437.10
E OVERHEAD & PROFIT (CONTOH) 10% 38.36 43.71
F Harga Satuan Pekerjaan (D+E) 421.99 480.81

Daerah datar sampai pelandaian naik dengan kemiringan


185 P.12.b.2.b.3 1 m2 1,470.15 1,771.44
1V : 2,5H s/d 1V : 1H

A TENAGA 374.00 422.40


L.01 0.00440 OH Pekerja 75,000 85,000 330.00 374.00
L.04 0.00044 OH Mandor 100,000 110,000 44.00 48.40
B BAHAN 82.50 88.00
0.0110 ltr 7,500 8,000 82.50 88.00
C PERALATAN 880.00 1,100.00
0.0440 hr Mesin Potong Rumput 20,000 25,000 880.00 1,100.00
D Jumlah A + B + C 1,336.50 1,610.40
E OVERHEAD & PROFIT (CONTOH) 10% 133.65 161.04
F Harga Satuan Pekerjaan (D+E) 1,470.15 1,771.44

Daerah datar sampai pelandaian naik dengan kemiringan


186 P.12.b.2.b.4 1 m2 914.10 1,041.37
1V : 1H s/d 2,5V : 1H

A TENAGA 569.50 643.20


L.01 0.00670 OH Pekerja 75,000 85,000 502.50 569.50
L.04 0.00067 OH Mandor 100,000 110,000 67.00 73.70
B BAHAN 127.50 136.00
0.0170 ltr 7,500 8,000 127.50 136.00
C PERALATAN 134.00 167.50
0.0067 hr Mesin Potong Rumput 20,000 25,000 134.00 167.50
D Jumlah A + B + C 831.00 946.70
E OVERHEAD & PROFIT (CONTOH) 10% 83.10 94.67
F Harga Satuan Pekerjaan (D+E) 914.10 1,041.37

Daerah datar sampai pelandaian naik dengan


187 P.12.b.2.b.5 1 m2 1,659.90 1,894.20
kemiringan2,5V : 1H s/d tegak.

A TENAGA 1,020.00 1,152.00


L.01 0.01200 OH Pekerja 75,000 85,000 900.00 1,020.00
L.04 0.00120 OH Mandor 100,000 110,000 120.00 132.00
B BAHAN 225.00 240.00
0.0300 ltr 7,500 8,000 225.00 240.00
C PERALATAN 264.00 330.00
0.0132 hr Mesin Potong Rumput 20,000 25,000 264.00 330.00
D Jumlah A + B + C 1,509.00 1,722.00
E OVERHEAD & PROFIT (CONTOH) 10% 150.90 172.20
F Harga Satuan Pekerjaan (D+E) 1,659.90 1,894.20

P.13 PEKERJAAN PANTAI


188 P.13.a 1 ph Penanaman Pohon bakau 3,344.00 3,919.30
A TENAGA 680.00 768.00
L.01 0.008 OH Pekerja 75,000 85,000 600.00 680.00
L.04 0.001 OH Mandor 100,000 110,000 80.00 88.00
B BAHAN 2,000.00 2,350.00
1.000 m3 Bibit Mangrove 1,000 1,100 1,000.00 1,100.00
1.000 kg Anjir tinggi 2 m' 1,000 1,250 1,000.00 1,250.00
C PERALATAN 360.00 445.00
0.002 hr Kendaraan Pengangkut 55,000 60,000 110.00 120.00
0.005 hr Rakit 50,000 65,000 250.00 325.00
D Jumlah A + B + C 3,040.00 3,563.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
E OVERHEAD & PROFIT (CONTOH) 10% 304.00 356.30
F Harga Satuan Pekerjaan (D+E) 3,344.00 3,919.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
189 P.13.b 1 m2 Matras Bambu 110,550.00 144,925.00
A TENAGA 42,500.00 48,000.00
L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00
B BAHAN 53,000.00 78,250.00
4.000 bh Bambu 12,000 18,000 48,000.00 72,000.00
5.000 m' Tali Pengikat 1,000 1,250 5,000.00 6,250.00
C PERALATAN 5,000.00 5,500.00
Alat Bantu ls ls 5,000.00 5,500.00
D Jumlah A + B + C 100,500.00 131,750.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,050.00 13,175.00
F Harga Satuan Pekerjaan (D+E) 110,550.00 144,925.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

P.14 PASANGAN ARMOR

Berbagai jenis armor yang terbuat dari beton diantaranya : berbentuk kubus, 3B, Quadripod, tetrapod, dolos dan
lain-lain. Untuk pembuatan dan pemasangan berbagai jenis armor sebagai berikut :

190 P.14.a 1 bh Pembuatan Kubus ukuran 30 x 30 x 30 cm 85,342.10 93,629.20


A TENAGA 5,200.00 5,850.00
L.01 0.050 OH Pekerja 75,000 85,000 3,750.00 4,250.00
L.02 0.010 OH Tukang Batu 95,000 105,000 950.00 1,050.00
L.04 0.005 OH Mandor 100,000 110,000 500.00 550.00
B BAHAN 71,485.22 78,318.95
Membuat Beton mutu f'c=14,5 MPa (K175), slum
0.027 m3 1,044,306 1,170,804 28,196.26 31,611.71
(12±2)cm, w/c = 0,66
3.240 kg Tulangan Praktis 13,268 14,317 42,988.97 46,387.24
0.002 bh Cetakan armor 150,000 160,000 300.00 320.000
C PERALATAN 898.50 948.50
0.005 hr Molen 150,000 160,000 750.00 800.00
0.0027 hr Vibrator 55,000 55,000 148.50 148.50
D Jumlah A + B + C 77,583.72 85,117.45
E OVERHEAD & PROFIT (CONTOH) 10% 7,758.37 8,511.75
F Harga Satuan Pekerjaan (D+E) 85,342.10 93,629.20

191 P.14.b 1 bh Pembuatan Kubus ukuran 40 x 40 x 40 cm 201,041.88 220,436.05


A TENAGA 10,400.00 11,700.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.02 0.020 OH Tukang Batu 95,000 105,000 1,900.00 2,100.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
B BAHAN 169,085.35 185,256.41
Membuat Beton mutu f'c=14,5 MPa (K175), slum
0.064 m3 1,044,306 1,170,804 66,835.57 74,931.46
(12±2)cm, w/c = 0,66
7.680 kg Tulangan Praktis 13,268 14,317 101,899.78 109,954.94
0.002 bh Cetakan armor 175,000 185,000 350.00 370.00
C PERALATAN 3,280.00 3,440.00
0.016 hr Molen 150,000 160,000 2,400.00 2,560.00
0.0160 hr Vibrator 55,000 55,000 880.00 880.00
D Jumlah A + B + C 182,765.35 200,396.41
E OVERHEAD & PROFIT (CONTOH) 10% 18,276.53 20,039.64
F Harga Satuan Pekerjaan (D+E) 201,041.88 220,436.05

192 P.14.c 1 bh Pembuatan 3B : Blok Beton Bergigi 309,775.38 339,548.01


A TENAGA 12,480.00 14,040.00
L.01 0.120 OH Pekerja 75,000 85,000 9,000.00 10,200.00
L.02 0.024 OH Tukang Batu 95,000 105,000 2,280.00 2,520.00
L.04 0.012 OH Mandor 100,000 110,000 1,200.00 1,320.00
B BAHAN 264,008.98 289,265.01
Membuat Beton mutu f'c=14,5 MPa (K175), slum
0.100 m3 1,044,306 1,170,804 104,430.58 117,080.41
(12±2)cm, w/c = 0,66
12.000 kg Tulangan Praktis 13,268 14,317 159,218.40 171,804.60
0.002 bh Cetakan armor 180,000 190,000 360.00 380.00
C PERALATAN 5,125.00 5,375.00
0.025 hr Molen 150,000 160,000 3,750.00 4,000.00
0.0250 hr Vibrator 55,000 55,000 1,375.00 1,375.00
D Jumlah A + B + C 281,613.98 308,680.01
E OVERHEAD & PROFIT (CONTOH) 10% 28,161.40 30,868.00
F Harga Satuan Pekerjaan (D+E) 309,775.38 339,548.01
*) Pasangan 3B akan terpasang 4,4 buah per m2

Pembuatan Blok Beton Berat 0,5 Ton Quatripod, Tetrapod,


193 P.14.d 1 bh 693,315.90 759,694.07
Dolos Tribar
A TENAGA 19,760.00 22,230.00
L.01 0.190 OH Pekerja 75,000 85,000 14,250.00 16,150.00
L.02 0.038 OH Tukang Batu 95,000 105,000 3,610.00 3,990.00
L.04 0.019 OH Mandor 100,000 110,000 1,900.00 2,090.00
B BAHAN 598,883.18 656,188.98
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


0.227 m3 1,044,306 1,170,804 237,057.41 265,772.54
w/c = 0,66
27.240 kg Tulangan Praktis 13,268 14,317 361,425.77 389,996.44
0.002 bh Cetakan armor 200,000 210,000 400.00 420.00
C PERALATAN 11,644.00 12,212.00
0.057 hr Molen 150,000 160,000 8,520.00 9,088.00
0.0568 hr Vibrator 55,000 55,000 3,124.00 3,124.00
D Jumlah A + B + C 630,287.18 690,630.98
E OVERHEAD & PROFIT (CONTOH) 10% 63,028.72 69,063.10
F Harga Satuan Pekerjaan (D+E) 693,315.90 759,694.07
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 0,5 Ton

Pembuatan Blok Beton Berat 0,75 Ton Quatripod,


194 P.14.e 1 bh 1,037,730.68 1,137,074.44
Tetrapod, Dolos Tribar
A TENAGA 29,120.00 32,760.00
L.01 0.280 OH Pekerja 75,000 85,000 21,000.00 23,800.00
L.02 0.056 OH Tukang Batu 95,000 105,000 5,320.00 5,880.00
L.04 0.028 OH Mandor 100,000 110,000 2,800.00 3,080.00
B BAHAN 896,846.52 982,669.04
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,
0.340 m3 1,044,306 1,170,804 355,063.96 398,073.40
w/c = 0,66
40.800 kg Tulangan Praktis 13,268 14,317 541,342.56 584,135.64
0.002 bh Cetakan armor 220,000 230,000 440.00 460.00
C PERALATAN 17,425.00 18,275.00
0.085 hr Molen 150,000 160,000 12,750.00 13,600.00
0.0850 hr Vibrator 55,000 55,000 4,675.00 4,675.00
D Jumlah A + B + C 943,391.52 1,033,704.04
E OVERHEAD & PROFIT (CONTOH) 10% 94,339.15 103,370.40
F Harga Satuan Pekerjaan (D+E) 1,037,730.68 1,137,074.44
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 0,75 Ton

Pembuatan Blok Beton Berat 1,00 Ton Quatripod,


195 P.14.f 1 bh 1,388,567.25 1,521,586.50
Tetrapod, Dolos Tribar
A TENAGA 41,600.00 46,800.00
L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.080 OH Tukang Batu 95,000 105,000 7,600.00 8,400.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 1,197,466.36 1,312,057.95
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,
0.454 m3 1,044,306 1,170,804 474,114.82 531,545.07
w/c = 0,66
54.480 kg Tulangan Praktis 13,268 14,317 722,851.54 779,992.88
0.002 bh Cetakan armor 250,000 260,000 500.00 520.00
C PERALATAN 23,267.50 24,402.50
0.1135 hr Molen 150,000 160,000 17,025.00 18,160.00
0.1135 hr Vibrator 55,000 55,000 6,242.50 6,242.50
D Jumlah A + B + C 1,262,333.86 1,383,260.45
E OVERHEAD & PROFIT (CONTOH) 10% 126,233.39 138,326.05
F Harga Satuan Pekerjaan (D+E) 1,388,567.25 1,521,586.50
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 1,00 Ton

Pembuatan Blok Beton Berat 1,50 Ton Quatripod,


196 P.14.g 1 bh 2,046,314.94 2,242,302.42
Tetrapod, Dolos Tribar
A TENAGA 41,600.00 46,800.00
L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.080 OH Tukang Batu 95,000 105,000 7,600.00 8,400.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 1,795,418.81 1,967,254.25
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,
0.681 m3 1,044,306 1,170,804 711,172.23 797,317.61
w/c = 0,66
81.680 kg Tulangan Praktis 13,268 14,317 1,083,746.58 1,169,416.64
0.002 bh Cetakan armor 250,000 260,000 500.00 520.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN 23,267.50 24,402.50
0.1135 hr Molen 150,000 160,000 17,025.00 18,160.00
0.1135 hr Vibrator 55,000 55,000 6,242.50 6,242.50
D Jumlah A + B + C 1,860,286.31 2,038,456.75
E OVERHEAD & PROFIT (CONTOH) 10% 186,028.63 203,845.67
F Harga Satuan Pekerjaan (D+E) 2,046,314.94 2,242,302.42
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 1,50 Ton

Pembuatan Blok Beton Berat 2,00 Ton Quatripod,


197 P.14.h 1 bh 2,046,314.94 2,242,302.42
Tetrapod, Dolos Tribar

A TENAGA 41,600.00 46,800.00


L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.080 OH Tukang Batu 95,000 105,000 7,600.00 8,400.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 1,795,418.81 1,967,254.25
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,
0.681 m3 1,044,306 1,170,804 711,172.23 797,317.61
w/c = 0,66
81.680 kg Tulangan Praktis 13,268 14,317 1,083,746.58 1,169,416.64
0.002 bh Cetakan armor 250,000 260,000 500.00 520.00
C PERALATAN 23,267.50 24,402.50
0.1135 hr Molen 150,000 160,000 17,025.00 18,160.00
0.1135 hr Vibrator 55,000 55,000 6,242.50 6,242.50
D Jumlah A + B + C 1,860,286.31 2,038,456.75
E OVERHEAD & PROFIT (CONTOH) 10% 186,028.63 203,845.67
F Harga Satuan Pekerjaan (D+E) 2,046,314.94 2,242,302.42
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 2,00 Ton

Pembuatan Blok Beton Berat 2,50 Ton Quatripod,


198 P.14.i 1 bh 2,046,314.94 2,242,302.42
Tetrapod, Dolos Tribar

A TENAGA 41,600.00 46,800.00


L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.080 OH Tukang Batu 95,000 105,000 7,600.00 8,400.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 1,795,418.81 1,967,254.25
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,
0.681 m3 1,044,306 1,170,804 711,172.23 797,317.61
w/c = 0,66
81.680 kg Tulangan Praktis 13,268 14,317 1,083,746.58 1,169,416.64
0.002 bh Cetakan armor 250,000 260,000 500.00 520.00
C PERALATAN 23,267.50 24,402.50
0.1135 hr Molen 150,000 160,000 17,025.00 18,160.00
0.1135 hr Vibrator 55,000 55,000 6,242.50 6,242.50
D Jumlah A + B + C 1,860,286.31 2,038,456.75
E OVERHEAD & PROFIT (CONTOH) 10% 186,028.63 203,845.67
F Harga Satuan Pekerjaan (D+E) 2,046,314.94 2,242,302.42
*) Harga Cetakan dapat berbeda tergantung jenis armornya,
AHSP ini dapat digunakan untuk pembuatan jenis armor lainnya untuk berat 2,50 Ton

199 P.14.j 1 m3 Pemasangan Berbagai Jenis Armor 3,736,132.77 4,098,923.06


A TENAGA 54,080.00 60,840.00
L.01 0.520 OH Pekerja 75,000 85,000 39,000.00 44,200.00
L.02 0.104 OH Tukang Batu 95,000 105,000 9,880.00 10,920.00
L.04 0.052 OH Mandor 100,000 110,000 5,200.00 5,720.00
B BAHAN 3,319,136.84 3,641,051.19
16.400 bh Armor uk 0,4 x 0,4 x 0,4 m 201,042 220,436 3,297,086.84 3,615,151.19
0.070 m3 Pasir Pasang 315,000 370,000 22,050.00 25,900.00
- -
C PERALATAN 23,267.50 24,402.50
0.1135 hr Molen 150,000 160,000 17,025.00 18,160.00
0.1135 hr Vibrator 55,000 55,000 6,242.50 6,242.50
D Jumlah A + B + C 3,396,484.34 3,726,293.69
E OVERHEAD & PROFIT (CONTOH) 10% 339,648.43 372,629.37
F Harga Satuan Pekerjaan (D+E) 3,736,132.77 4,098,923.06
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
200 P.14.k 1 m3 Pemasangan Batu 1 kg - 3 kg, void maks 15% 441,809.50 503,558.00
A TENAGA 85,000.00 96,000.00
L.01 1.000 OH Pekerja 75,000 85,000 75,000.00 85,000.00
L.04 0.100 OH Mandor 100,000 110,000 10,000.00 11,000.00
B BAHAN 286,000.00 330,000.00
1.100 m3 Batu 260,000 300,000 286,000.00 330,000.00
C PERALATAN 30,645.00 31,780.00
0.1135 jam Whell Loader / Excavator 270,000 280,000 30,645.00 31,780.00

D Jumlah A + B + C 401,645.00 457,780.00


E OVERHEAD & PROFIT (CONTOH) 10% 40,164.50 45,778.00
F Harga Satuan Pekerjaan (D+E) 441,809.50 503,558.00

201 P.14.l 1 m3 Pemasangan Batu 3 kg - 5 kg, void maks 15% 443,300.00 508,200.00
A TENAGA 94,000.00 106,000.00
L.01 1.000 OH Pekerja 75,000 85,000 75,000.00 85,000.00
L.02 0.200 OH Tukang Batu 95,000 105,000 19,000.00 21,000.00
L.04 0.100 OH Mandor 100,000 110,000 10,000.00 11,000.00
B BAHAN 299,000.00 345,000.00
1.150 m3 Batu 260,000 300,000 299,000.00 345,000.00
C PERALATAN 430,000.00 490,000.00
0.1000 jam Whell Loader / Excavator 270,000 280,000 27,000.00 28,000.00
D Jumlah A + B + C 403,000.00 462,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 40,300.00 46,200.00
F Harga Satuan Pekerjaan (D+E) 443,300.00 508,200.00

202 P.14.m 1 m3 Pemasangan Batu 5 kg - 10 kg, void maks 20% 501,710.00 570,845.00
A TENAGA 114,400.00 128,150.00
L.01 1.100 OH Pekerja 75,000 85,000 82,500.00 93,500.00
L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00
L.04 0.110 OH Mandor 100,000 105,000 11,000.00 11,550.00
B BAHAN 312,000.00 360,000.00
1.200 m3 Batu 260,000 300,000 312,000.00 360,000.00
C PERALATAN 29,700.00 30,800.00
0.110 jam Whell Loader / Excavator 270,000 280,000 29,700.00 30,800.00
D Jumlah A + B + C 456,100.00 518,950.00
E OVERHEAD & PROFIT (CONTOH) 10% 45,610.00 51,895.00
F Harga Satuan Pekerjaan (D+E) 501,710.00 570,845.00

203 P.14.n 1 m3 Pemasangan Batu 10 kg - 30 kg, void maks 20% 516,010.00 587,345.00
A TENAGA 114,400.00 128,150.00
L.01 1.100 OH Pekerja 75,000 85,000 82,500.00 93,500.00
L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00
L.04 0.110 OH Mandor 100,000 105,000 11,000.00 11,550.00
B BAHAN 325,000.00 375,000.00
1.250 m3 Batu 260,000 300,000 325,000.00 375,000.00
C PERALATAN 29,700.00 30,800.00
0.110 jam Whell Loader / Excavator 270,000 280,000 29,700.00 30,800.00
D Jumlah A + B + C 469,100.00 533,950.00
E OVERHEAD & PROFIT (CONTOH) 10% 46,910.00 53,395.00
F Harga Satuan Pekerjaan (D+E) 516,010.00 587,345.00

204 P.14.o 1 m3 Pemasangan Batu 30 kg - 50 kg, void maks 25% 527,560.00 600,325.00
A TENAGA 114,400.00 128,150.00
L.01 1.100 OH Pekerja 75,000 85,000 82,500.00 93,500.00
L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00
L.04 0.110 OH Mandor 100,000 105,000 11,000.00 11,550.00
B BAHAN 332,800.00 384,000.00
1.280 m3 Batu 260,000 300,000 332,800.00 384,000.00
C PERALATAN 32,400.00 33,600.00
0.120 jam Whell Loader / Excavator 270,000 280,000 32,400.00 33,600.00
D Jumlah A + B + C 479,600.00 545,750.00
E OVERHEAD & PROFIT (CONTOH) 10% 47,960.00 54,575.00
F Harga Satuan Pekerjaan (D+E) 527,560.00 600,325.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
205 P.14.p 1 m3 Pemasangan Batu 50 kg - 100 kg, void maks 25% 539,000.00 613,140.00
A TENAGA 124,800.00 139,800.00
L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.02 0.240 OH Tukang Batu 95,000 105,000 22,800.00 25,200.00
L.04 0.120 OH Mandor 100,000 105,000 12,000.00 12,600.00
B BAHAN 332,800.00 384,000.00
1.280 m3 Batu 260,000 300,000 332,800.00 384,000.00
C PERALATAN 32,400.00 33,600.00
0.120 jam Whell Loader / Excavator 270,000 280,000 32,400.00 33,600.00
D Jumlah A + B + C 490,000.00 557,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 49,000.00 55,740.00
F Harga Satuan Pekerjaan (D+E) 539,000.00 613,140.00

206 P.14.q 1 m3 Pemasangan Batu 100 kg - 200 kg, void maks 30% 550,440.00 626,340.00
A TENAGA 124,800.00 139,800.00
L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.02 0.240 OH Tukang Batu 95,000 105,000 22,800.00 25,200.00
L.04 0.120 OH Mandor 100,000 105,000 12,000.00 12,600.00
B BAHAN 343,200.00 396,000.00
1.320 m3 Batu 260,000 300,000 343,200.00 396,000.00
C PERALATAN 32,400.00 33,600.00
0.120 jam Whell Loader / Excavator 270,000 280,000 32,400.00 33,600.00
D Jumlah A + B + C 500,400.00 569,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 50,040.00 56,940.00
F Harga Satuan Pekerjaan (D+E) 550,440.00 626,340.00

207 P.14.r 1 m3 Pemasangan Batu 200 kg - 300 kg, void maks 30% 550,440.00 626,340.00
A TENAGA 124,800.00 139,800.00
L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.02 0.240 OH Tukang Batu 95,000 105,000 22,800.00 25,200.00
L.04 0.120 OH Mandor 100,000 105,000 12,000.00 12,600.00
B BAHAN 343,200.00 396,000.00
1.320 m3 Batu 260,000 300,000 343,200.00 396,000.00
C PERALATAN 32,400.00 33,600.00
0.120 jam Whell Loader / Excavator 270,000 280,000 32,400.00 33,600.00
D Jumlah A + B + C 500,400.00 569,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 50,040.00 56,940.00
F Harga Satuan Pekerjaan (D+E) 550,440.00 626,340.00

208 P.14.s 1 m3 Pemasangan Batu 300 kg - 400 kg, void maks 30% 582,010.00 662,035.00
A TENAGA 135,200.00 151,450.00
L.01 1.300 OH Pekerja 75,000 85,000 97,500.00 110,500.00
L.02 0.260 OH Tukang Batu 95,000 105,000 24,700.00 27,300.00
L.04 0.130 OH Mandor 100,000 105,000 13,000.00 13,650.00
B BAHAN 358,800.00 414,000.00
1.380 m3 Batu 260,000 300,000 358,800.00 414,000.00
C PERALATAN 35,100.00 36,400.00
0.130 jam Whell Loader / Excavator 270,000 280,000 35,100.00 36,400.00
D Jumlah A + B + C 529,100.00 601,850.00
E OVERHEAD & PROFIT (CONTOH) 10% 52,910.00 60,185.00
F Harga Satuan Pekerjaan (D+E) 582,010.00 662,035.00

209 P.14.t 1 m3 Pemasangan Batu 400 kg - 500 kg, void maks 35% 582,010.00 662,035.00
A TENAGA 135,200.00 151,450.00
L.01 1.300 OH Pekerja 75,000 85,000 97,500.00 110,500.00
L.02 0.260 OH Tukang Batu 95,000 105,000 24,700.00 27,300.00
L.04 0.130 OH Mandor 100,000 105,000 13,000.00 13,650.00
B BAHAN 358,800.00 414,000.00
1.380 m3 Batu 260,000 300,000 358,800.00 414,000.00
C PERALATAN 35,100.00 36,400.00
0.130 jam Whell Loader / Excavator 270,000 280,000 35,100.00 36,400.00
D Jumlah A + B + C 529,100.00 601,850.00
E OVERHEAD & PROFIT (CONTOH) 10% 52,910.00 60,185.00
F Harga Satuan Pekerjaan (D+E) 582,010.00 662,035.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
210 P.14.u 1 m3 Pemasangan Batu 200 kg - 500 kg, void maks 32% 578,578.00 658,190.50
A TENAGA 132,080.00 147,955.00
L.01 1.270 OH Pekerja 75,000 85,000 95,250.00 107,950.00
L.02 0.254 OH Tukang Batu 95,000 105,000 24,130.00 26,670.00
L.04 0.127 OH Mandor 100,000 105,000 12,700.00 13,335.00
B BAHAN 358,800.00 414,000.00
1.380 m3 Batu 260,000 300,000 358,800.00 414,000.00
C PERALATAN 35,100.00 36,400.00
0.130 jam Whell Loader / Excavator 270,000 280,000 35,100.00 36,400.00
D Jumlah A + B + C 525,980.00 598,355.00
E OVERHEAD & PROFIT (CONTOH) 10% 52,598.00 59,835.50
F Harga Satuan Pekerjaan (D+E) 578,578.00 658,190.50

211 P.14.v 1 m3 Pemasangan Batu 500 kg - 650 kg, void maks 35% 599,170.00 681,642.50
A TENAGA 140,400.00 157,275.00
L.01 1.350 OH Pekerja 75,000 85,000 101,250.00 114,750.00
L.02 0.270 OH Tukang Batu 95,000 105,000 25,650.00 28,350.00
L.04 0.135 OH Mandor 100,000 105,000 13,500.00 14,175.00
B BAHAN 369,200.00 426,000.00
1.420 m3 Batu 260,000 300,000 369,200.00 426,000.00
C PERALATAN 35,100.00 36,400.00
0.130 jam Whell Loader / Excavator 270,000 280,000 35,100.00 36,400.00
D Jumlah A + B + C 544,700.00 619,675.00
E OVERHEAD & PROFIT (CONTOH) 10% 54,470.00 61,967.50
F Harga Satuan Pekerjaan (D+E) 599,170.00 681,642.50

212 P.14.w 1 m3 Pemasangan Batu 650 kg - 800 kg, void maks 35% 607,750.00 691,542.50
A TENAGA 140,400.00 157,275.00
L.01 1.350 OH Pekerja 75,000 85,000 101,250.00 114,750.00
L.02 0.270 OH Tukang Batu 95,000 105,000 25,650.00 28,350.00
L.04 0.135 OH Mandor 100,000 105,000 13,500.00 14,175.00
B BAHAN 377,000.00 435,000.00
1.450 m3 Batu 260,000 300,000 377,000.00 435,000.00
C PERALATAN 35,100.00 36,400.00
0.130 jam Whell Loader / Excavator 270,000 280,000 35,100.00 36,400.00
D Jumlah A + B + C 552,500.00 628,675.00
E OVERHEAD & PROFIT (CONTOH) 10% 55,250.00 62,867.50
F Harga Satuan Pekerjaan (D+E) 607,750.00 691,542.50

P.15 STRUKTUR KRIB LAUT


Buis Beton diangkut < 30 m dan dipasang untuk
213 P.15.a.1 1 bh 18,700.00 21,010.00
Konstruksi Pengaman Pantai
A TENAGA 17,000.00 19,100.00
L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.04 0.020 OH Mandor 100,000 105,000 2,000.00 2,100.00
B BAHAN - -
- - -
C PERALATAN - -
- - -
D Jumlah A + B + C 17,000.00 19,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,700.00 1,910.00
F Harga Satuan Pekerjaan (D+E) 18,700.00 21,010.00

Pengecoran Buis Beton Ø 1 m' dengan campuran


214 P.15.b 1 bh 1,176,161.25 1,309,381.07
Pasang Pondasi Sumuran diameter 100 cm

A TENAGA 123,200.00 138,600.00


L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.02 0.200 OH T u k a n g b a t u 95,000 105,000 19,000.00 21,000.00
L.03 0.020 OH K e p . t k . b a t u 110,000 120,000 2,200.00 2,400.00
L.04 0.120 OH Mandor 100,000 110,000 12,000.00 13,200.00
B BAHAN 721,037.50 811,746.43
247.00 kg Portland Cement 1,100.00 1,150.00 271,700.00 284,050.00
869.00 kg Pasir Beton 250.00 271.43 217,250.00 235,871.43
999.00 kg Krikil 229.63 288.89 229,400.00 288,600.00
215.00 ltr Air 12.50 15.00 2,687.50 3,225.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN 225,000.00 240,000.00
0.250 hari Molen 0,3 m3 900,000 960,000 225,000.00 240,000.00
D Jumlah A + B + C 1,069,237.50 1,190,346.43
E OVERHEAD & PROFIT (CONTOH) 10% 106,923.75 119,034.64
F Harga Satuan Pekerjaan (D+E) 1,176,161.25 1,309,381.07

215 P.16 1 bh Pasangan pipa suling-suling 29,232.50 39,704.50


A TENAGA 8,500.00 9,600.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
B BAHAN 18,075.00 26,495.00
1.05 m' Pipa PVC Ø 2" 10,833.33 17,500.00 11,375.00 18,375.00
0.10 kg Ijuk 7,000.00 7,200.00 700.00 720.00
0.02 m3 Krikil 300,000.00 370,000.00 6,000.00 7,400.00
C PERALATAN - -

D Jumlah A + B + C 26,575.00 36,095.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,657.50 3,609.50
F Harga Satuan Pekerjaan (D+E) 29,232.50 39,704.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

TABEL A.5 KRITERIA KHUSUS CAMPURAN BETON **)

fc' = 7,4 s/d 21,7 fc' = 24 s/d 31,2


NO. Specifikasi Khusus Mpa Mpa

K.100 - K.225 K.250 - K.350


1 Perbandingan campuran beton (Volume) 1PC : 2PB : 3 Kr 1PC : 1,5PB : 2,5Kr

2 Berat isi pasir ………. Minimum (kg/m3) 1,350 1,400

3 Berat isi koral/kerikil ….. Minimum (kg/m3) 1,300 1,350

A.3.1 KOEFISIEN UNTUK ANALISIS HARGA SATUAN PEKERJAAN PEMBUATAN BETON

B.01 BETON UNTUK LANTAI KERJA (BEDDING)

TIPE 1 : MENGGUNAKAN CAMPURAN BETON TUMBUK


216 B.01.a 1 m3 fc' = 1,8 s/d 3,7 (BO : K-40 s/d K-60) atau Setara 1PC : 888,734.00 1,007,325.00
3PB : 5Kr

A TENAGA 135,520.00 152,460.00


L.01 1.320 OH Pekerja 75,000 85,000 99,000.00 112,200.00
L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00
L.03 0.022 OH Kepala Tukang 110,000 120,000 2,420.00 2,640.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 672,420.00 763,290.00
200 kg PC/Portlan Cement 1,113 1,144 222,500.00 228,750.00
0.522 m3 PB/Pasir Beton 350,000 380,000 182,700.00 198,360.00
0.862 m3 Kr/Krikil 310,000 390,000 267,220.00 336,180.00

C PERALATAN - -
- -
D Jumlah A + B + C 807,940.00 915,750.00
E OVERHEAD & PROFIT (CONTOH) 10% 80,794.00 91,575.00
F Harga Satuan Pekerjaan (D+E) 888,734.00 1,007,325.00

TIPE 2 : MENGGUNAKAN CAMPURAN BETON TUMBUK


217 B.01.b 1 m3 fc' = 5,6 s/d 7,4 MPa (BO : K-80 s/d K-100) atau Setara 902,132.00 1,014,172.50
1PC : 2PB : 3Kr

A TENAGA 135,520.00 152,460.00


L.01 1.320 OH Pekerja 75,000 85,000 99,000.00 112,200.00
L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00
L.03 0.022 OH Kepala Tukang 110,000 120,000 2,420.00 2,640.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 684,600.00 769,515.00
220 kg PC/Portlan Cement 1,113 1,144 244,750.00 251,625.00
0.588 m3 PB/Pasir Beton 350,000 380,000 205,800.00 223,440.00
0.755 m3 Kr/Krikil 310,000 390,000 234,050.00 294,450.00

- - - -
C PERALATAN - -
- -

D Jumlah A + B + C 820,120.00 921,975.00


E OVERHEAD & PROFIT (CONTOH) 10% 82,012.00 92,197.50
F Harga Satuan Pekerjaan (D+E) 902,132.00 1,014,172.50

TIPE 3 : MENGGUNAKAN CAMPURAN BETON TUMBUK


218 B.01.c 1 m3 918,497.25 1,030,800.38
fc' = 7,4 MPa (K-100) atau Setara 1PC : 2PB : 3Kr

A TENAGA 135,520.00 152,460.00

L.01 1.320 OH Pekerja 75,000 85,000 99,000.00 112,200.00

L.02 0.220 OH Tukang Batu 95,000 105,000 20,900.00 23,100.00


L.03 0.022 OH Kepala Tukang 110,000 120,000 2,420.00 2,640.00

L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00

B BAHAN 699,477.50 784,631.25


227 kg PC/Portlan Cement 1,113 1,144 252,537.50 259,631.25
0.618 m3 PB/Pasir Beton 350,000 380,000 216,300.00 234,840.00
0.744 m3 Kr/Krikil 310,000 390,000 230,640.00 290,160.00
- lt Air - - - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
hr Molen 0,35 m3 250,000 275,000 - -
D Jumlah A + B + C 834,997.50 937,091.25

E OVERHEAD & PROFIT (CONTOH) 10% 83,499.75 93,709.13


F Harga Satuan Pekerjaan (D+E) 918,497.25 1,030,800.38

TIPE 3 : MENGGUNAKAN CAMPURAN Beton Mutu f'c =


B.02 1 m3 980,091.75 1,097,493.38
7,4 Mpa (K100) ATAU SETARA 1PC : 2 PB : 3Kr

219 B.02.a MANUAL


A TENAGA 169,455.00 190,635.00

L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00


L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00

L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00


B BAHAN 721,537.50 807,086.25
247 kg PC/Portlan Cement 1,113 1,144 274,787.50 282,506.25

0.621 m3 PB/Pasir Beton 350,000 380,000 217,350.00 235,980.00


0.740 m3 Kr/Krikil 310,000 390,000 229,400.00 288,600.00
lt Air - - - -

C PERALATAN - -
- -
D Jumlah A + B + C 890,992.50 997,721.25
E OVERHEAD & PROFIT (CONTOH) 10% 89,099.25 99,772.13
F Harga Satuan Pekerjaan (D+E) 980,091.75 1,097,493.38

TIPE 3 : MENGGUNAKAN CAMPURAN Beton Mutu f'c =


B.02 1 m3 983,614.50 1,099,352.38
7,4 Mpa (K100) ATAU SETARA 1PC : 2 PB : 3Kr

220 B.02.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 724,225.00 810,311.25

247 kg PC/Portlan Cement 1,113 1,144 274,787.50 282,506.25


0.621 m3 PB/Pasir Beton 350,000 380,000 217,350.00 235,980.00

0.740 m3 Kr/Krikil 310,000 390,000 229,400.00 288,600.00

215 lt Air 12.50 15.00 2,687.50 3,225.00


C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00

D Jumlah A + B + C 894,195.00 999,411.25


E OVERHEAD & PROFIT (CONTOH) 10% 89,419.50 99,941.13

F Harga Satuan Pekerjaan (D+E) 983,614.50 1,099,352.38

BETON MUTU , fc' = 9,8 Mpa (K.125), SLUMP (12± 2) w/c =


B.03 1 m3 1,010,435.45 1,129,296.75
0,78

221 B.03.a MANUAL


A TENAGA 169,455.00 190,635.00

L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00


L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00

L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00


B BAHAN 749,122.69 835,998.41
276 kg PC/Portlan Cement 1,113 1,144 307,050.00 315,675.00

828 kg PB/Pasir Beton 250 271 207,000.00 224,742.86


1,012 kg Kr/Krikil 230 289 232,385.19 292,355.56
215 lt Air 12.50 15.00 2,687.50 3,225.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 918,577.69 1,026,633.41

E OVERHEAD & PROFIT (CONTOH) 10% 91,857.77 102,663.34


F Harga Satuan Pekerjaan (D+E) 1,010,435.45 1,129,296.75

TIPE 4 : BETON MUTU , fc' = 9,8 Mpa (K.125), SLUMP (12 ±


B.03 1 m3 1,011,001.95 1,127,608.25
2) w/c = 0,78
222 B.03.b MENGGUNAKAN MOLEN
A TENAGA 132,470.00 149,100.00

L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00


L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00

L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00


B BAHAN 749,122.69 835,998.41
276 kg PC/Portlan Cement 1,113 1,144 307,050.00 315,675.00

828 kg PB/Pasir Beton 250 271 207,000.00 224,742.86


1,012 kg Kr/Krikil 230 289 232,385.19 292,355.56
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 919,092.69 1,025,098.41
E OVERHEAD & PROFIT (CONTOH) 10% 91,909.27 102,509.84

F Harga Satuan Pekerjaan (D+E) 1,011,001.95 1,127,608.25

BETON MUTU , fc' = 12,2 Mpa (K.150), SLUMP (12± 2) w/c =


B.04 1 m3 1,031,869.67 1,151,163.95
0,72

223 B.04.a MANUAL


A TENAGA 169,455.00 190,635.00

L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00


L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00

L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00


B BAHAN 768,608.33 855,877.68
299 kg PC/Portlan Cement 1,113 1,144 332,637.50 341,981.25
799 kg PB/Pasir Beton 250 271 199,750.00 216,871.43
1,017 kg Kr/Krikil 230 289 233,533.33 293,800.00
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 938,063.33 1,046,512.68
E OVERHEAD & PROFIT (CONTOH) 10% 93,806.33 104,651.27
F Harga Satuan Pekerjaan (D+E) 1,031,869.67 1,151,163.95

BETON MUTU , fc' = 12,2 Mpa (K.150), SLUMP (12± 2) w/c =


B.04 1 m3 1,032,436.17 1,149,475.45
0,72

224 B.04.b MENGGUNAKAN MOLEN

A TENAGA 132,470.00 149,100.00


L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00

L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00


L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 768,608.33 855,877.68

299 kg PC/Portlan Cement 1,113 1,144 332,637.50 341,981.25


799 kg PB/Pasir Beton 250 271 199,750.00 216,871.43
1,017 kg Kr/Krikil 230 289 233,533.33 293,800.00
215 lt Air 12.50 15.00 2,687.50 3,225.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN 37,500.00 40,000.00


0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 938,578.33 1,044,977.68

E OVERHEAD & PROFIT (CONTOH) 10% 93,857.83 104,497.77


F Harga Satuan Pekerjaan (D+E) 1,032,436.17 1,149,475.45

BETON MUTU , fc' = 14,5 Mpa (K.175), SLUMP (12± 2) w/c =


B.05 1 m3 1,057,217.03 1,177,302.37
0,66

225 B.05.a MANUAL


A TENAGA 169,455.00 190,635.00
L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00
L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00
B BAHAN 791,651.39 879,639.88
326 kg PC/Portlan Cement 1,113 1,144 362,675.00 372,862.50
760 kg PB/Pasir Beton 250 271 190,000.00 206,285.71
1,029 kg Kr/Krikil 230 289 236,288.89 297,266.67
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
D Jumlah A + B + C 961,106.39 1,070,274.88
E OVERHEAD & PROFIT (CONTOH) 10% 96,110.64 107,027.49
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
F Harga Satuan Pekerjaan (D+E) 1,057,217.03 1,177,302.37

BETON MUTU , fc' = 14,5 Mpa (K.175), SLUMP (12± 2) w/c =


B.05 1 m3 1,057,783.53 1,175,613.87
0,66

226 B.05.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 791,651.39 879,639.88
326 kg PC/Portlan Cement 1,113 1,144 362,675.00 372,862.50
760 kg PB/Pasir Beton 250 271 190,000.00 206,285.71
1,029 kg Kr/Krikil 230 289 236,288.89 297,266.67
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 961,621.39 1,068,739.88
E OVERHEAD & PROFIT (CONTOH) 10% 96,162.14 106,873.99
F Harga Satuan Pekerjaan (D+E) 1,057,783.53 1,175,613.87

BETON MUTU , fc' = 16,9 Mpa (K.200), SLUMP (12± 2) w/c =


B.06 1 m3 1,081,564.71 1,201,990.60
0,61

227 B.06.a MANUAL


A TENAGA 169,455.00 190,635.00
L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00
L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00
B BAHAN 813,785.65 902,083.73
352 kg PC/Portlan Cement 1,113 1,144 391,600.00 402,600.00
731 kg PB/Pasir Beton 250 271 182,750.00 198,414.29
1,031 kg Kr/Krikil 230 289 236,748.15 297,844.44
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 983,240.65 1,092,718.73
E OVERHEAD & PROFIT (CONTOH) 10% 98,324.06 109,271.87
F Harga Satuan Pekerjaan (D+E) 1,081,564.71 1,201,990.60
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 16,9 Mpa (K.200), SLUMP (12± 2) w/c =


B.06 1 m3 1,082,131.21 1,200,302.10
0,61

228 B.06.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 813,785.65 902,083.73
352 kg PC/Portlan Cement 1,113 1,144 391,600.00 402,600.00
731 kg PB/Pasir Beton 250 271 182,750.00 198,414.29
1,031 kg Kr/Krikil 230 289 236,748.15 297,844.44
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 983,755.65 1,091,183.73
E OVERHEAD & PROFIT (CONTOH) 10% 98,375.56 109,118.37
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
F Harga Satuan Pekerjaan (D+E) 1,082,131.21 1,200,302.10

BETON MUTU , fc' = 19,3 Mpa (K.225), SLUMP (12± 2) w/c =


B.07 1 m3 1,099,782.44 1,221,126.57
0,58
229 B.07.a MANUAL
A TENAGA 169,455.00 190,635.00
L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00
L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00
B BAHAN 830,347.22 919,480.06
371 kg PC/Portlan Cement 1,113 1,144 412,737.50 424,331.25
698 kg PB/Pasir Beton 250 271 174,500.00 189,457.14
1,047 kg Kr/Krikil 230 289 240,422.22 302,466.67
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 999,802.22 1,110,115.06
E OVERHEAD & PROFIT (CONTOH) 10% 99,980.22 111,011.51
F Harga Satuan Pekerjaan (D+E) 1,099,782.44 1,221,126.57

BETON MUTU , fc' = 19,3 Mpa (K.225), SLUMP (12± 2) w/c =


B.07 1 m3 1,100,348.94 1,219,438.07
0,58

230 B.07.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 830,347.22 919,480.06
371 kg PC/Portlan Cement 1,113 1,144 412,737.50 424,331.25
698 kg PB/Pasir Beton 250 271 174,500.00 189,457.14
1,047 kg Kr/Krikil 230 289 240,422.22 302,466.67
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 1,000,317.22 1,108,580.06
E OVERHEAD & PROFIT (CONTOH) 10% 100,031.72 110,858.01
F Harga Satuan Pekerjaan (D+E) 1,100,348.94 1,219,438.07
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 21,7 Mpa (K.250), SLUMP (12± 2) w/c =


B.08 1 m3 1,112,020.45 1,233,148.54
0,56

231 B.08.a MANUAL


A TENAGA 169,455.00 190,635.00
L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00
L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00
B BAHAN 841,472.69 930,409.13
384 kg PC/Portlan Cement 1,113 1,144 427,200.00 439,200.00
692 kg PB/Pasir Beton 250 271 173,000.00 187,828.57
1,039 kg Kr/Krikil 230 289 238,585.19 300,155.56
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,010,927.69 1,121,044.13
E OVERHEAD & PROFIT (CONTOH) 10% 101,092.77 112,104.41
F Harga Satuan Pekerjaan (D+E) 1,112,020.45 1,233,148.54
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 21,7 Mpa (K.250), SLUMP (12± 2) w/c =


B.08 1 m3 1,112,586.95 1,231,460.04
0,56
232 B.08.b MENGGUNAKAN MOLEN
A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00
L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 841,472.69 930,409.13
384 kg PC/Portlan Cement 1,113 1,144 427,200.00 439,200.00
692 kg PB/Pasir Beton 250 271 173,000.00 187,828.57
1,039 kg Kr/Krikil 230 289 238,585.19 300,155.56
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 1,011,442.69 1,119,509.13
E OVERHEAD & PROFIT (CONTOH) 10% 101,144.27 111,950.91
F Harga Satuan Pekerjaan (D+E) 1,112,586.95 1,231,460.04

BETON MUTU , fc' = 24,0 Mpa (K.275), SLUMP (12± 2) w/c =


B.09 1 m3 1,133,459.25 1,254,307.61
0,53
233 B.09.a MANUAL
A TENAGA 169,455.00 190,635.00
L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00
L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00
B BAHAN 860,962.50 949,644.64
406 kg PC/Portlan Cement 1,113 1,144 451,675.00 464,362.50
684 kg PB/Pasir Beton 250 271 171,000.00 185,657.14
1,026 kg Kr/Krikil 230 289 235,600.00 296,400.00
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,030,417.50 1,140,279.64
E OVERHEAD & PROFIT (CONTOH) 10% 103,041.75 114,027.96
F Harga Satuan Pekerjaan (D+E) 1,133,459.25 1,254,307.61
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 24,0 Mpa (K.275), SLUMP (12± 2) w/c =


B.09 1 m3 1,134,025.75 1,252,619.11
0,53

224 B.09.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00

L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00


L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 860,962.50 949,644.64
406 kg PC/Portlan Cement 1,113 1,144 451,675.00 464,362.50

684 kg PB/Pasir Beton 250 271 171,000.00 185,657.14


1,026 kg Kr/Krikil 230 289 235,600.00 296,400.00
215 lt Air 12.50 15.00 2,687.50 3,225.00

C PERALATAN 37,500.00 40,000.00


0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 1,030,932.50 1,138,744.64

E OVERHEAD & PROFIT (CONTOH) 10% 103,093.25 113,874.46


F Harga Satuan Pekerjaan (D+E) 1,134,025.75 1,252,619.11
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 26,4 Mpa (K.300), SLUMP (12± 2) w/c =


B.10 1 m3 1,139,937.54 1,260,629.88
0,52 (KEDAP AIR)

225 B.10.a MANUAL


A TENAGA 169,455.00 190,635.00

L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00


L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00

L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00


B BAHAN 866,851.85 955,392.16
413 kg PC/Portlan Cement 1,113 1,144 459,462.50 472,368.75

681 kg PB/Pasir Beton 250 271 170,250.00 184,842.86


1,021 kg Kr/Krikil 230 289 234,451.85 294,955.56
215 lt Air 12.50 15.00 2,687.50 3,225.00

C PERALATAN - -
- -
D Jumlah A + B + C 1,036,306.85 1,146,027.16

E OVERHEAD & PROFIT (CONTOH) 10% 103,630.69 114,602.72


F Harga Satuan Pekerjaan (D+E) 1,139,937.54 1,260,629.88

BETON MUTU , fc' = 26,4 Mpa (K.300), SLUMP (12± 2) w/c =


B.10 1 m3 1,140,504.04 1,258,941.38
0,52 (KEDAP AIR)

226 B.10.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00

L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00


L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00

B BAHAN 866,851.85 955,392.16


413 kg PC/Portlan Cement 1,113 1,144 459,462.50 472,368.75
681 kg PB/Pasir Beton 250 271 170,250.00 184,842.86

1,021 kg Kr/Krikil 230 289 234,451.85 294,955.56


215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 1,036,821.85 1,144,492.16
E OVERHEAD & PROFIT (CONTOH) 10% 103,682.19 114,449.22

F Harga Satuan Pekerjaan (D+E) 1,140,504.04 1,258,941.38


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 28,8 Mpa (K.325), SLUMP (12± 2) w/c =


B.11 1 m3 1,164,941.15 1,285,290.18
0,49 (KEDAP AIR)

227 B.11.a MANUAL

A TENAGA 169,455.00 190,635.00


L.01 1.650 OH Pekerja 75,000 85,000 123,750.00 140,250.00

L.02 0.275 OH Tukang Batu 95,000 105,000 26,125.00 28,875.00

L.03 0.028 OH Kepala Tukang 110,000 120,000 3,080.00 3,360.00


L.04 0.165 OH Mandor 100,000 110,000 16,500.00 18,150.00

B BAHAN 889,582.41 977,810.62

439 kg PC/Portlan Cement 1,113 1,144 488,387.50 502,106.25


670 kg PB/Pasir Beton 250 271 167,500.00 181,857.14

1,006 kg Kr/Krikil 230 289 231,007.41 290,622.22


215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -

- -
D Jumlah A + B + C 1,059,037.41 1,168,445.62
E OVERHEAD & PROFIT (CONTOH) 10% 105,903.74 116,844.56

F Harga Satuan Pekerjaan (D+E) 1,164,941.15 1,285,290.18

BETON MUTU , fc' = 28,8 Mpa (K.325), SLUMP (12± 2) w/c =


B.11 1 m3 1,165,507.65 1,283,601.68
0,49 (KEDAP AIR)

228 B.11.b MENGGUNAKAN MOLEN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

A TENAGA 132,470.00 149,100.00


L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00
L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00

L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00


L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00
B BAHAN 889,582.41 977,810.62

439 kg PC/Portlan Cement 1,113 1,144 488,387.50 502,106.25


670 kg PB/Pasir Beton 250 271 167,500.00 181,857.14
1,006 kg Kr/Krikil 230 289 231,007.41 290,622.22

215 lt Air 12.50 15.00 2,687.50 3,225.00


C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00

D Jumlah A + B + C 1,059,552.41 1,166,910.62


E OVERHEAD & PROFIT (CONTOH) 10% 105,955.24 116,691.06
F Harga Satuan Pekerjaan (D+E) 1,165,507.65 1,283,601.68

BETON MUTU , fc' = 31,2 Mpa (K.350), SLUMP (12± 2) w/c =


B.12 1 m3 1,224,373.84 1,350,917.42
0,48 (KEDAP AIR)

229 B.12.a MANUAL


A TENAGA 215,600.00 242,550.00
L.01 2.100 OH Pekerja 75,000 85,000 157,500.00 178,500.00
L.02 0.350 OH Tukang Batu 95,000 105,000 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000 120,000 3,850.00 4,200.00
L.04 0.210 OH Mandor 100,000 110,000 21,000.00 23,100.00
B BAHAN 897,467.13 985,556.75
448 kg PC/Portlan Cement 1,113 1,144 498,400.00 512,400.00
667 kg PB/Pasir Beton 250 271 166,750.00 181,042.86
1,000 kg Kr/Krikil 230 289 229,629.63 288,888.89
215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,113,067.13 1,228,106.75
E OVERHEAD & PROFIT (CONTOH) 10% 111,306.71 122,810.67

F Harga Satuan Pekerjaan (D+E) 1,224,373.84 1,350,917.42


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

BETON MUTU , fc' = 31,2 Mpa (K.350), SLUMP (12± 2) w/c =


B.12 1 m3 1,174,180.84 1,292,122.42
0,48 (KEDAP AIR)

230 B.12.b MENGGUNAKAN MOLEN


A TENAGA 132,470.00 149,100.00
L.01 1.323 OH Pekerja 75,000 85,000 99,225.00 112,455.00

L.02 0.189 OH Tukang Batu 95,000 105,000 17,955.00 19,845.00


L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00
L.04 0.132 OH Mandor 100,000 110,000 13,200.00 14,520.00

B BAHAN 897,467.13 985,556.75


448 kg PC/Portlan Cement 1,113 1,144 498,400.00 512,400.00
667 kg PB/Pasir Beton 250 271 166,750.00 181,042.86

1,000 kg Kr/Krikil 230 289 229,629.63 288,888.89


215 lt Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN 37,500.00 40,000.00
0.25 hr Molen 0,35 m3 150,000 160,000 37,500.00 40,000.00
D Jumlah A + B + C 1,067,437.13 1,174,656.75
E OVERHEAD & PROFIT (CONTOH) 10% 106,743.71 117,465.67

F Harga Satuan Pekerjaan (D+E) 1,174,180.84 1,292,122.42

BETON MENGGUNAKAN READY MIXED DAN BAHAN


B.13 1 m3 1,478,950.00 1,569,975.00
AKTIF
BETON MENGGUNAKAN READY MIXED DAN BAHAN
231 B.13.a 1 m3 1,478,950.00 1,569,975.00
AKTIF DAN POMPA BETON

A TENAGA 111,500.00 125,250.00


L.01 1.000 OH Pekerja 75,000 85,000 75,000.00 85,000.00
L.02 0.250 OH Tukang Batu 95,000 105,000 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000 120,000 2,750.00 3,000.00
L.04 0.100 OH Mandor 100,000 110,000 10,000.00 11,000.00
B BAHAN 1,179,000.00 1,242,000.00
1.02 m3 Campuran Beton Ready Mixed 1,050,000 1,100,000 1,071,000.00 1,122,000.00

C PERALATAN 54,000.00 60,000.00


0.120 hari Pompa dan conveyor beton 450,000.00 500,000.00 54,000.00 60,000.00
- -
D Jumlah A + B + C 1,344,500.00 1,427,250.00

E OVERHEAD & PROFIT (CONTOH) 10% 134,450.00 142,725.00


F Harga Satuan Pekerjaan (D+E) 1,478,950.00 1,569,975.00

B.13.b 1 m3 BETON MENGGUNAKAN BAHAN ADITIF 165,000.00 178,200.00

232 B.13.b
A TENAGA - -
L.01 - OH Pekerja 75,000 85,000 - -
L.02 - OH Tukang Batu 95,000 105,000 - -

L.03 - OH Kepala Tukang 110,000 120,000 - -


L.04 - OH Mandor 100,000 110,000 - -
B BAHAN 150,000.00 162,000.00

1.20 Ltr Bahan Aditif**) 125,000 135,000 150,000.00 162,000.00


C PERALATAN - -
- -
D Jumlah A + B + C 150,000.00 162,000.00

E OVERHEAD & PROFIT (CONTOH) 10% 15,000.00 16,200.00


F Harga Satuan Pekerjaan (D+E) 165,000.00 178,200.00
**) dosis atau jumlah bahan aditif yang ditambahkan agar disesuaikan dengan petunjuk penggunannya
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B.13 PEKERJAAN BETON


BAHAN ADIKTIF
232 B.13.b 1 m3 Beton Menggunakan Bahan Aditif 145,200.00 165,000.00
A TENAGA - -
- -
B BAHAN 132,000.00 150,000.00
1.20 ltr Bahan Aditif *) sesuai ketentuan dosis 110,000 125,000 132,000.00 150,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 132,000.00 150,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,200.00 15,000.00
F Harga Satuan Pekerjaan (D+E) 145,200.00 165,000.00

A.3.2 PENAMBAHAN KOEFISIEN TENAGA KERJA DAN ATAU


PERALATAN
MENGANGKUT / MENAIKKAN CAMPURAN BETON
B.14 JARAK >- 5 M

B.14.a Beton Dicorkan pada tapak berjarak <25 m


dg Ketinggian/kedalaman < 1m
233 B.14.a.1 1 m3 Manual 38,335.00 43,296.00
A TENAGA 34,850.00 39,360.00
L.01 0.410 OH Pekerja 75,000 85,000 30,750.00 34,850.00
L.04 0.041 OH Mandor 100,000 110,000 4,100.00 4,510.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 34,850.00 39,360.00
E OVERHEAD & PROFIT (CONTOH) 10% 3,485.00 3,936.00
F Harga Satuan Pekerjaan (D+E) 38,335.00 43,296.00

B.14.b 1 m3 Beton Dicorkan pada tapak berjarak 46,750.00 52,800.00


setiap tambahan jarak 25 m (horizontal)
234 B.14.b.1 Manual 46,750.00 52,800.00
A TENAGA 42,500.00 48,000.00
L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00
B BAHAN - -

- -

C PERALATAN - -
- -

D Jumlah A + B + C 42,500.00 48,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 4,250.00 4,800.00
F Harga Satuan Pekerjaan (D+E) 46,750.00 52,800.00

235 1 m3 Beton Dicorkan pada tapak berjarak setiap tambahan 25 m 78,100.00 87,120.00

B.14.b.2 Menggunakan Peralatan Pompa Beton

A TENAGA 17,000.00 19,200.00


L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00

L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00

B BAHAN - -
- -

C PERALATAN 54,000.00 60,000.00

0.12 hr Pompa & Conveyor Beton 450,000 500,000 54,000.00 60,000.00


D Jumlah A + B + C 71,000.00 79,200.00

E OVERHEAD & PROFIT (CONTOH) 10% 7,100.00 7,920.00

F Harga Satuan Pekerjaan (D+E) 78,100.00 87,120.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B.15 1 m3 Pemadatan Beton pada saat Mengecor 39,875.00 44,000.00


236 B.15.a Vibrator
A TENAGA 21,250.00 24,000.00

L.01 0.250 OH Pekerja 75,000 85,000 18,750.00 21,250.00


L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN - -

- -
C PERALATAN 15,000.00 16,000.00
0.1 hr Vibrator 150,000 160,000 15,000.00 16,000.00

D Jumlah A + B + C 36,250.00 40,000.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,625.00 4,000.00
F Harga Satuan Pekerjaan (D+E) 39,875.00 44,000.00

237 B.15.b 1 m3 Manual (menggunakan penusuk besi beton) 46,750.00 52,800.00

A TENAGA 42,500.00 48,000.00


L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00

L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00

B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 42,500.00 48,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,250.00 4,800.00
F Harga Satuan Pekerjaan (D+E) 46,750.00 52,800.00

238 B.16 1 m3 Beton Dicorkan pada tapak Tiap Kenaikan 4 m (vertikal) 23,375.00 26,400.00

B.16.a Manual 23,375.00 26,400.00


A TENAGA 21,250.00 24,000.00
L.01 0.250 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN - -
- -
C PERALATAN - -

- -
D Jumlah A + B + C 21,250.00 24,000.00

E OVERHEAD & PROFIT (CONTOH) 10% 2,125.00 2,400.00

F Harga Satuan Pekerjaan (D+E) 23,375.00 26,400.00

Beton Dicorkan pada tapak Tiap Kenaikan 4 m (vertikal) 78,100.00 87,120.00

239 B.16.b 1 m3 Menggunakan peralatan pompa beton 78,100.00 87,120.00


A TENAGA 17,000.00 19,200.00

L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00


L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN - -

- -
C PERALATAN 54,000.00 60,000.00
0.12 hr Pompa & Conveyor Beton 450,000 500,000 54,000.00 60,000.00

D Jumlah A + B + C 71,000.00 79,200.00


E OVERHEAD & PROFIT (CONTOH) 10% 7,100.00 7,920.00
F Harga Satuan Pekerjaan (D+E) 78,100.00 87,120.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

KOEFISIEN UNTUK ANALISA HARGA SATUAN


A.3.3
PEKERJAAN PEMBESIAN BETON

B.17 PEMBESIAN BESI POLOS ATAU ULIR


240 B.17.a 100 kg Untuk Pembesian Pelat 1,330,120.00 1,435,335.00
A TENAGA 133,700.00 149,100.00

L.01 0.700 OH Pekerja 75,000 85,000 52,500.00 59,500.00


L.02 0.700 OH Tukang Besi 95,000 105,000 66,500.00 73,500.00
L.03 0.070 OH Kepala Tukang 110,000 120,000 7,700.00 8,400.00

L.04 0.070 OH Mandor 100,000 110,000 7,000.00 7,700.00


B BAHAN 1,075,500.00 1,155,750.00
105.0 kg Besi Beton (polos/ulir) 10,000 10,750 1,050,000.00 1,128,750.00

1.5 kg Kawat Ikat 17,000 18,000 25,500.00 27,000.00


C PERALATAN - -

- -

D Jumlah A + B + C 1,209,200.00 1,304,850.00


E OVERHEAD & PROFIT (CONTOH) 10% 120,920.00 130,485.00

F Harga Satuan Pekerjaan (D+E) 1,330,120.00 1,435,335.00

241 B.17.b 100 kg Untuk Pembesian Kolom, Balok, Ring Balk dan Sloof 1,542,640.00 1,673,265.00

A TENAGA 326,900.00 365,400.00


L.01 2.100 OH Pekerja 75,000 85,000 157,500.00 178,500.00
L.02 1.400 OH Tukang Besi 95,000 105,000 133,000.00 147,000.00
L.03 0.140 OH Kepala Tukang 110,000 120,000 15,400.00 16,800.00
L.04 0.210 OH Mandor 100,000 110,000 21,000.00 23,100.00
B BAHAN 1,075,500.00 1,155,750.00
105.0 kg Besi Beton (polos/ulir) 10,000 10,750 1,050,000.00 1,128,750.00
1.5 kg Kawat Ikat 17,000 18,000 25,500.00 27,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 1,402,400.00 1,521,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 140,240.00 152,115.00
F Harga Satuan Pekerjaan (D+E) 1,542,640.00 1,673,265.00

Pembesian dengan Jaring Kawat (wire mesh) Untuk Pelat


242 B.18 100 kg 1,576,575.00 1,695,375.00
atau Dinding

A TENAGA 47,750.00 53,250.00


L.01 0.250 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.02 0.250 OH Tukang Besi 95,000 105,000 23,750.00 26,250.00

L.03 0.025 OH Kepala Tukang 110,000 120,000 2,750.00 3,000.00


L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN 1,385,500.00 1,488,000.00

102.0 kg Wire Mesh 13,500 14,500 1,377,000.00 1,479,000.00


0.5 kg Kawat Ikat 17,000 18,000 8,500.00 9,000.00
C PERALATAN - -

- -
D Jumlah A + B + C 1,433,250.00 1,541,250.00
E OVERHEAD & PROFIT (CONTOH) 10% 143,325.00 154,125.00

F Harga Satuan Pekerjaan (D+E) 1,576,575.00 1,695,375.00

243 B.19 100 kg Pembesian Kabel presstreed polos 1,852,400.00 2,065,112.50

A TENAGA 95,500.00 106,500.00


L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.02 0.500 OH Tukang Besi 95,000 105,000 47,500.00 52,500.00
L.03 0.050 OH Kepala Tukang 110,000 120,000 5,500.00 6,000.00

L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00


B BAHAN 1,498,500.00 1,665,875.00
105.0 kg Kabel presstreed polos 13,000 14,500 1,365,000.00 1,522,500.00

12.5 kg Besi Beton (polos/ulir) 10,000 10,750 125,000.00 134,375.00


0.5 kg Kawat Ikat 17,000 18,000 8,500.00 9,000.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN 90,000.00 105,000.00


0.15 hr Jack Tension / stressing 600,000 700,000 90,000.00 105,000.00
D Jumlah A + B + C 1,684,000.00 1,877,375.00

E OVERHEAD & PROFIT (CONTOH) 10% 168,400.00 187,737.50


F Harga Satuan Pekerjaan (D+E) 1,852,400.00 2,065,112.50

244 B.20
MENGANGKUT / MENAIKKAN TULANGAN SETIAP
KENAIKAN VERTIKAL 4 M' ATAU JARAK HORIZONTAL 25
M KE TAPAK PEMASANGAN

B.20.a 4 m' Manual 38,500.00 43,230.00


A TENAGA 35,000.00 39,300.00

L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00


L.02 0.100 OH Tukang Besi 95,000 105,000 9,500.00 10,500.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN

C PERALATAN - -

D Jumlah A + B + C 35,000.00 39,300.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,500.00 3,930.00

F Harga Satuan Pekerjaan (D+E) 38,500.00 43,230.00

245 B.20.b 10 s/d 25 m' Mekanis (penambahan jarak horizontal) 74,442.50 77,990.00
A TENAGA 20,800.00 23,400.00
L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.02 0.040 OH Tukang Besi 95,000 105,000 3,800.00 4,200.00
L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN

C PERALATAN 46,875.00 47,500.00


0.025 hr Crane** 1,875,000 1,900,000 46,875.00 47,500.00
D Jumlah A + B + C 67,675.00 70,900.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,767.50 7,090.00
F Harga Satuan Pekerjaan (D+E) 74,442.50 77,990.00
** termasuk operator & bbm

246 B.20.c 25 m' Mekanis (penambahan jarak horizontal) 90,062.50 95,480.00


A TENAGA 35,000.00 39,300.00

L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00


L.02 0.100 OH Tukang Besi 95,000 105,000 9,500.00 10,500.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN

C PERALATAN 46,875.00 47,500.00


0.025 hr Crane** 1,875,000 1,900,000 46,875.00 47,500.00

D Jumlah A + B + C 81,875.00 86,800.00


E OVERHEAD & PROFIT (CONTOH) 10% 8,187.50 8,680.00
F Harga Satuan Pekerjaan (D+E) 90,062.50 95,480.00

** termasuk operator & bbm


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

247 B.20.c 4 m' Mekanis (penambahan tiap 4 m' jarak vertikal) 93,500.00 100,980.00
A TENAGA 35,000.00 39,300.00
L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00

L.02 0.100 OH Tukang Besi 95,000 105,000 9,500.00 10,500.00


L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN

C PERALATAN 50,000.00 52,500.00


0.025 hr Lift ** 2,000,000 2,100,000 50,000.00 52,500.00

D Jumlah A + B + C 85,000.00 91,800.00


E OVERHEAD & PROFIT (CONTOH) 10% 8,500.00 9,180.00
F Harga Satuan Pekerjaan (D+E) 93,500.00 100,980.00

** termasuk operator & bbm


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B.21 PEKERJAAN BEKISTING


248 B.21.a 1 m2 105,468.00 115,951.00
Bekisting Lantai Beton expose dengan multipleks 18 mm

A TENAGA 69,000.00 77,250.00


L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.02 0.250 OH Tukang kayu 95,000 105,000 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000 120,000 2,750.00 3,000.00
L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00
B BAHAN 26,880.00 28,160.00
0.128 lbr Multipleks 18 mm 210,000 220,000 26,880.00 28,160.00
0.006 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 27,000.00 27,600.00
0.280 kg Paku 14,000 16,000 3,920.00 4,480.00
0.250 ltr Minyak Beton 9,000 10,000 2,250.00 2,500.00
C PERALATAN - -
- -
D Jumlah A + B + C 95,880.00 105,410.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,588.00 10,541.00
F Harga Satuan Pekerjaan (D+E) 105,468.00 115,951.00
koef. Multipleks koef.kaso

yang ke-1 0.3500 0.0180

catatan : bahan digunakan berulang kali yang ke-2 0.2030 0.0100

yang ke-3 0.1280 0.0060

yang ke-4 0.0910 0.0040

249 B.21.b 1 m2 Bekisting Lantai Beton Biasa dengan multipleks 12 mm 50,353.60 60,038.00
atau 18 mm (TP)

A TENAGA 27,600.00 30,900.00


L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.02 0.100 OH Tukang kayu 95,000 105,000 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000 120,000 1,100.00 1,200.00
L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN 18,176.00 23,680.00
0.128 lbr Multipleks 12 mm 142,000 185,000 18,176.00 23,680.00
0.005 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 22,500.00 23,000.00
0.220 kg Paku 14,000 16,000 3,080.00 3,520.00
0.200 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 45,776.00 54,580.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,577.60 5,458.00

F Harga Satuan Pekerjaan (D+E) 50,353.60 60,038.00


koef. Multipleks koef.kaso

yang ke-1 0.3530 0.0140

catatan : bahan digunakan berulang kali yang ke-2 0.2030 0.0080

yang ke-3 0.1280 0.0050

yang ke-4 0.0910 0.0030

250 B.21.c 1 m2 Bekisting Lantai Beton Biasa menggunakan papan kayu 119,460.00 138,765.00
3/20 cm (TP)

A TENAGA 41,400.00 46,350.00


L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00

L.02 0.150 OH Tukang kayu 95,000 105,000 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00


L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN 67,200.00 79,800.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

0.014 m3 Papan 3/20 cm kayu 4,800,000 5,700,000 67,200.00 79,800.00


0.005 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 22,500.00 23,000.00
0.220 kg Paku 14,000 16,000 3,080.00 3,520.00
0.200 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 108,600.00 126,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,860.00 12,615.00

F Harga Satuan Pekerjaan (D+E) 119,460.00 138,765.00


koef. Multipleks koef.kaso

yang ke-1 0.0360 0.0080

catatan : bahan digunakan berulang kali yang ke-2 0.0220 0.0040

yang ke-3 0.0140 0.0030

yang ke-4 0.0110 0.0020

Perancah Beksiting Lantai menggunakan kaso 5/7 tinggi


251 B.21.d 1 m2 148,390.00 156,585.00
4m', JAT (Jarak Antar Tiang) ≤ 60 cm

A TENAGA 41,400.00 46,350.00


L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00

L.02 0.150 OH Tukang kayu 95,000 105,000 14,250.00 15,750.00


L.03 0.015 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00
L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN 93,500.00 96,000.00


0.0200 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 90,000.00 92,000.00
0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00

C PERALATAN - -
- -
D Jumlah A + B + C 134,900.00 142,350.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,490.00 14,235.00

F Harga Satuan Pekerjaan (D+E) 148,390.00 156,585.00


koef.kaso

yang ke-1 0.0630

yang ke-2 0.0350

yang ke-3 0.0200

yang ke-4 0.0130

Perancah Beksiting kayu dolken Ø 8 - 10 cm tinggi 4m',


252 B.21.e 1 m2 86,808.70 96,053.65
JAT ≤ 80 cm

A TENAGA 46,920.00 52,530.00


L.01 0.340 OH Pekerja 75,000 85,000 25,500.00 28,900.00

L.02 0.170 OH Tukang kayu 95,000 105,000 16,150.00 17,850.00


L.03 0.017 OH Kepala Tukang 110,000 120,000 1,870.00 2,040.00
L.04 0.034 OH Mandor 100,000 110,000 3,400.00 3,740.00

B BAHAN 31,997.00 34,791.50


1.4630 bt Kayu Dolken Ø 8 - 10 cm tinggi 4 m' 19,000 20,500 27,797.00 29,991.50

0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00

C PERALATAN - -
- -

D Jumlah A + B + C 78,917.00 87,321.50

E OVERHEAD & PROFIT (CONTOH) 10% 7,891.70 8,732.15


F Harga Satuan Pekerjaan (D+E) 86,808.70 96,053.65
dolken yg digunakan

yang ke-1 4.5000 btg

yang ke-2 2.4750 btg

yang ke-3 1.4630 btg

yang ke-4 0.9590 btg


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Perancah Beksiting Lantai menggunakan Bambu Ø 8 - 10


253 B.21.f 1 m2 77,918.50 96,459.00
cm tinggi 4m', JAT ≤ 80 cm

A TENAGA 44,160.00 49,440.00

L.01 0.320 OH Pekerja 75,000 85,000 24,000.00 27,200.00

L.02 0.160 OH Tukang kayu 95,000 105,000 15,200.00 16,800.00


L.03 0.016 OH Kepala Tukang 110,000 120,000 1,760.00 1,920.00

L.04 0.032 OH Mandor 100,000 110,000 3,200.00 3,520.00

B BAHAN 26,675.00 38,250.00


1.8000 bt Bambu Ø 8 cm - 10 cm panjang 4m' 12,000 18,000 21,600.00 32,400.00

3.500 m' Tambang ijuk atau plastik 250 300 875.00 1,050.00

0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00


C PERALATAN - -

- -
D Jumlah A + B + C 70,835.00 87,690.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,083.50 8,769.00

F Harga Satuan Pekerjaan (D+E) 77,918.50 96,459.00


dolken yg digunakan

yang ke-1 4.5000 btg

yang ke-2 2.7000 btg

yang ke-3 1.8000 btg

yang ke-4 1.3500 btg

B.22 FLOORDECK
254 B.22.a 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 0,60 m) 63,690.00 66,583.00
A TENAGA 13,800.00 15,450.00

L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00


L.02 0.050 OH Tukang kayu 95,000 105,000 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000 120,000 550.00 600.00

L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00


B BAHAN 44,100.00 45,080.00
0.0030 m3 Kaso 5/7 cm x 4.00 4,500,000 4,600,000 13,500.00 13,800.00

0.0068 m3 Balok 8/12 cm x 4.00 4,500,000 4,600,000 30,600.00 31,280.00


0.270 kg Paku 14,000 16,000 3,780.00 4,320.00
1.080 m2 Floordeck 80,000 90,000 86,400.00 97,200.00

C PERALATAN - -
- -
D Jumlah A + B + C 57,900.00 60,530.00

E OVERHEAD & PROFIT (CONTOH) 10% 5,790.00 6,053.00


F Harga Satuan Pekerjaan (D+E) 63,690.00 66,583.00
kaso balok

yang ke-1 0.0092 0.0218

catatan : bahan digunakan berulang kali yang ke-2 0.0051 0.0118

yang ke-3 0.0030 0.0068

yang ke-4 0.0020 0.0043

255 B.22.b 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 0,80 m) 63,129.00 65,714.00

A TENAGA 11,040.00 12,360.00


L.01 0.080 OH Pekerja 75,000 85,000 6,000.00 6,800.00
L.02 0.040 OH Tukang kayu 95,000 105,000 3,800.00 4,200.00

L.03 0.004 OH Kepala Tukang 110,000 120,000 440.00 480.00


L.04 0.008 OH Mandor 100,000 110,000 800.00 880.00
B BAHAN 46,350.00 47,380.00
0.0014 m3 Kaso 5/7 cm x 4.00 4,500,000 4,600,000 6,300.00 6,440.00

0.0089 m3 Balok 8/12 cm x 4.00 4,500,000 4,600,000 40,050.00 40,940.00


0.230 kg Paku 14,000 16,000 3,220.00 3,680.00
1.080 m2 Floordeck 80,000 90,000 86,400.00 97,200.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 57,390.00 59,740.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,739.00 5,974.00

F Harga Satuan Pekerjaan (D+E) 63,129.00 65,714.00


kaso balok

yang ke-1 0.0043 0.0286

catatan : bahan digunakan berulang kali yang ke-2 0.0024 0.0154

yang ke-3 0.0014 0.0089

yang ke-4 0.0009 0.0056

256 B.22.c 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 1,20 m) 53,737.20 55,729.30
A TENAGA 7,452.00 8,343.00

L.01 0.0540 OH Pekerja 75,000 85,000 4,050.00 4,590.00


L.02 0.0270 OH Tukang kayu 95,000 105,000 2,565.00 2,835.00

L.03 0.0027 OH Kepala Tukang 110,000 120,000 297.00 324.00

L.04 0.0054 OH Mandor 100,000 110,000 540.00 594.00


B BAHAN 41,400.00 42,320.00

0.0014 m3 Kaso 5/7 cm x 4.00 4,500,000 4,600,000 6,300.00 6,440.00

0.0078 m3 Balok 8/12 cm x 4.00 4,500,000 4,600,000 35,100.00 35,880.00


0.210 kg Paku 14,000 16,000 2,940.00 3,360.00

1.080 m2 Floordeck 80,000 90,000 86,400.00 97,200.00


C PERALATAN - -
- -
D Jumlah A + B + C 48,852.00 50,663.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,885.20 5,066.30
F Harga Satuan Pekerjaan (D+E) 53,737.20 55,729.30
kaso balok

yang ke-1 0.0043 0.0252

catatan : bahan digunakan berulang kali yang ke-2 0.0024 0.0136

yang ke-3 0.0014 0.0078

yang ke-4 0.0009 0.0049

257 B.22.d 1 m2 Bekisting Lantai Floordeck tipe Pelat (JAP ≤ 2.00 m) 49,935.60 51,665.90
A TENAGA 5,796.00 6,489.00
L.01 0.0420 OH Pekerja 75,000 85,000 3,150.00 3,570.00

L.02 0.0210 OH Tukang kayu 95,000 105,000 1,995.00 2,205.00


L.03 0.0021 OH Kepala Tukang 110,000 120,000 231.00 252.00
L.04 0.0042 OH Mandor 100,000 110,000 420.00 462.00

B BAHAN 39,600.00 40,480.00


0.0010 m3 Kaso 5/7 cm x 4.00 4,500,000 4,600,000 4,500.00 4,600.00
0.0078 m3 Balok 8/12 cm x 4.00 4,500,000 4,600,000 35,100.00 35,880.00
0.200 kg Paku 14,000 16,000 2,800.00 3,200.00

1.080 m2 Floordeck 80,000 90,000 86,400.00 97,200.00


C PERALATAN - -
- -

D Jumlah A + B + C 45,396.00 46,969.00


E OVERHEAD & PROFIT (CONTOH) 10% 4,539.60 4,696.90
F Harga Satuan Pekerjaan (D+E) 49,935.60 51,665.90
kaso balok

yang ke-1 0.0031 0.0252

catatan : bahan digunakan berulang kali yang ke-2 0.0017 0.0136

yang ke-3 0.0010 0.0078

yang ke-4 0.0007 0.0049


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B.23 BEKISTING BALOK


258 B.23.a 1 m2 Bekisting balok beton expose menggunakan multipleks 18 176,957.00 189,486.00
mm JAT (Jarak Antar Tiang) ≤ 1,00 m

A TENAGA 68,760.00 76,680.00

L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00


L.02 0.360 OH Tukang kayu 95,000 105,000 34,200.00 37,800.00
L.03 0.036 OH Kepala Tukang 110,000 120,000 3,960.00 4,320.00

L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00


B BAHAN 92,110.00 95,580.00
0.1280 lbr multipleks 18 mm 210,000 220,000 26,880.00 28,160.00

0.0130 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 58,500.00 59,800.00


0.3200 kg Paku 14,000 16,000 4,480.00 5,120.00
0.2500 ltr Minyak Beton 9,000 10,000 2,250.00 2,500.00

C PERALATAN - -
- -

D Jumlah A + B + C 160,870.00 172,260.00

E OVERHEAD & PROFIT (CONTOH) 10% 16,087.00 17,226.00


F Harga Satuan Pekerjaan (D+E) 176,957.00 189,486.00
koef multipleks koef.kaso

yang ke-1 0.3530 0.0410

bahan berulang kali digunakan yang ke-2 0.2030 0.0230

yang ke-3 0.1280 0.0130

yang ke-4 0.0910 0.0090

259 B.23.b 1 m2 Bekisting balok beton biasa menggunakan multipleks 12 116,705.60 129,096.00
mm JAT (Jarak Antar Tiang) ≤ 1,00 m

A TENAGA 33,120.00 37,080.00


L.01 0.240 OH Pekerja 75,000 85,000 18,000.00 20,400.00
L.02 0.120 OH Tukang kayu 95,000 105,000 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000 120,000 1,320.00 1,440.00
L.04 0.024 OH Mandor 100,000 110,000 2,400.00 2,640.00
B BAHAN 72,976.00 80,280.00
0.1280 lbr multipleks 12 mm 142,000 185,000 18,176.00 23,680.00
0.0110 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 49,500.00 50,600.00
0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00
0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00

C PERALATAN - -
- -
D Jumlah A + B + C 106,096.00 117,360.00

E OVERHEAD & PROFIT (CONTOH) 10% 10,609.60 11,736.00


F Harga Satuan Pekerjaan (D+E) 116,705.60 129,096.00
koef multipleks koef.kaso

yang ke-1 0.3530 0.0330

bahan berulang kali digunakan yang ke-2 0.2030 0.0180

yang ke-3 0.1280 0.0110

yang ke-4 0.0910 0.0070

260 B.23.c 1 m2 Bekisting balok beton biasa menggunakan kayu papan 174,768.00 196,922.00
3/20 cm (TP)

A TENAGA 49,680.00 55,620.00


L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00
L.02 0.180 OH Tukang kayu 95,000 105,000 17,100.00 18,900.00

L.03 0.018 OH Kepala Tukang 110,000 120,000 1,980.00 2,160.00


L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B BAHAN 109,200.00 123,400.00


0.0140 m3 Papan 3/20 panjang 4' m 4,800,000 5,700,000 67,200.00 79,800.00
0.0080 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 36,000.00 36,800.00
0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00

0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00


C PERALATAN - -
- -

D Jumlah A + B + C 158,880.00 179,020.00


E OVERHEAD & PROFIT (CONTOH) 10% 15,888.00 17,902.00
F Harga Satuan Pekerjaan (D+E) 174,768.00 196,922.00
koef multipleks koef.kaso

yang ke-1 0.0360 0.0240

bahan berulang kali digunakan yang ke-2 0.0220 0.0130

yang ke-3 0.0140 0.0080

yang ke-4 0.0110 0.0050

Perancah Beksiting balok menggunakan Kaso 5/7 tinggi


261 B.23.d 1 m2 112,794.00 121,066.00
4m' dan JAT (Jarak Antar Tiang) ≤ 1,00 m

A TENAGA 49,680.00 55,620.00

L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00


L.02 0.180 OH Tukang kayu 95,000 105,000 17,100.00 18,900.00
L.03 0.018 OH Kepala Tukang 110,000 120,000 1,980.00 2,160.00
L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00
B BAHAN 52,860.00 54,440.00
0.0110 m3 Kayu Kaso 5/7 panjang 4'm 4,500,000 4,600,000 49,500.00 50,600.00
0.2400 kg Paku 14,000 16,000 3,360.00 3,840.00
C PERALATAN - -
D Jumlah A + B + C 102,540.00 110,060.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,254.00 11,006.00
F Harga Satuan Pekerjaan (D+E) 112,794.00 121,066.00
dolken yg digunakan

yang ke-1 0.0350 btg

yang ke-2 0.0190 btg

yang ke-3 0.0110 btg

yang ke-4 0.0070 btg

Perancah Beksiting balok menggunakan Dolken Ø 8 - 10


262 B.23.e 1 m2 83,812.30 94,371.20
cm tinggi 4m' dan JAT (Jarak Antar Tiang) ≤ 1,20 m

A TENAGA 55,200.00 61,800.00


L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.200 OH Tukang kayu 95,000 105,000 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000 120,000 2,200.00 2,400.00


L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 20,993.00 23,992.00

0.8130 btg Dolken Ø 8-10 cm panjang 4' m 21,000 24,000 17,073.00 19,512.00
0.2800 kg Paku 14,000 16,000 3,920.00 4,480.00
C PERALATAN - -

D Jumlah A + B + C 76,193.00 85,792.00


E OVERHEAD & PROFIT (CONTOH) 10% 7,619.30 8,579.20
F Harga Satuan Pekerjaan (D+E) 83,812.30 94,371.20
dolken yg digunakan

yang ke-1 2.7000 btg

yang ke-2 1.3750 btg

yang ke-3 0.8130 btg

yang ke-4 0.5330 btg


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Perancah Beksiting balok beton menggunakan Bambo Ø 8


263 B.23.f 1 m2 87,807.50 103,202.00
- 10 cm tinggi 4m' dan JAT (Jarak Antar Tiang) ≤ 1,00 m

A TENAGA 63,030.00 70,290.00


L.01 0.330 OH Pekerja 75,000 85,000 24,750.00 28,050.00

L.02 0.330 OH Tukang kayu 95,000 105,000 31,350.00 34,650.00


L.03 0.033 OH Kepala Tukang 110,000 120,000 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000 110,000 3,300.00 3,630.00

B BAHAN 16,795.00 23,530.00


1.0000 btg Bambu Ø 8-10 cm panjang 4' m 12,000 18,000 12,000.00 18,000.00
0.2800 kg Paku 14,000 16,000 3,920.00 4,480.00

3.500 m' Tambang ijuk atau plastik 250 300 875.00 1,050.00
C PERALATAN - -
- -
D Jumlah A + B + C 79,825.00 93,820.00

E OVERHEAD & PROFIT (CONTOH) 10% 7,982.50 9,382.00


F Harga Satuan Pekerjaan (D+E) 87,807.50 103,202.00
dolken yg digunakan

yang ke-1 2.7000 btg

yang ke-2 1.5000 btg

yang ke-3 1.0000 btg

yang ke-4 0.7500 btg

B.24 BEKISTING KOLOM

Bekisting Kolom beton EXPOSE menggunakan multipleks


264 B.24.a 1 m2 150,254.50 161,859.50
18 mm

A TENAGA 72,915.00 80,785.00


L.01 0.330 OH Pekerja 75,000 85,000 24,750.00 28,050.00
L.02 0.007 OH Tukang kayu 95,000 105,000 665.00 735.00
L.03 0.250 OH Kepala Tukang 110,000 120,000 27,500.00 30,000.00
L.04 0.200 OH Mandor 100,000 110,000 20,000.00 22,000.00
B BAHAN 63,680.00 66,360.00
0.1280 lbr multipleks 18 mm 210,000 220,000 26,880.00 28,160.00
0.0070 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 31,500.00 32,200.00
0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00
0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00

C PERALATAN - -

- -
D Jumlah A + B + C 136,595.00 147,145.00

E OVERHEAD & PROFIT (CONTOH) 10% 13,659.50 14,714.50

F Harga Satuan Pekerjaan (D+E) 150,254.50 161,859.50


koef multipleks koef.kaso

yang ke-1 0.3530 0.0210

bahan digunakan beberapa kali yang ke-2 0.2030 0.0120

yang ke-3 0.1280 0.0070

yang ke-4 0.0910 0.0040

Bekisting Kolom beton biasa menggunakan multipleks


265 B.24.b 1 m2 88,919.60 100,397.00
12mm atau 18 mm, (TP)

A TENAGA 30,360.00 33,990.00


L.01 0.220 OH Pekerja 75,000 85,000 16,500.00 18,700.00

L.02 0.110 OH Tukang kayu 95,000 105,000 10,450.00 11,550.00

L.03 0.011 OH Kepala Tukang 110,000 120,000 1,210.00 1,320.00


L.04 0.022 OH Mandor 100,000 110,000 2,200.00 2,420.00

B BAHAN 50,476.00 57,280.00


0.1280 lbr multipleks 12 mm 142,000 185,000 18,176.00 23,680.00
0.0060 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 27,000.00 27,600.00

0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00


0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 80,836.00 91,270.00
E OVERHEAD & PROFIT (CONTOH) 10% 8,083.60 9,127.00

F Harga Satuan Pekerjaan (D+E) 88,919.60 100,397.00


koef multipleks koef.kaso

yang ke-1 0.3530 0.0170

bahan digunakan beberapa kali yang ke-2 0.2030 0.0090

yang ke-3 0.1280 0.0060

yang ke-4 0.0910 0.0040

Bekisting Kolom beton biasa menggunakan kayu papan


266 B.24.c 1 m2 161,832.00 183,403.00
3/20 cm, (TP)

A TENAGA 46,920.00 52,530.00


L.01 0.340 OH Pekerja 75,000 85,000 25,500.00 28,900.00
L.02 0.170 OH Tukang kayu 95,000 105,000 16,150.00 17,850.00

L.03 0.017 OH Kepala Tukang 110,000 120,000 1,870.00 2,040.00


L.04 0.034 OH Mandor 100,000 110,000 3,400.00 3,740.00
B BAHAN 100,200.00 114,200.00

0.0140 m3 Papan 3/20 kayu 4,800,000 5,700,000 67,200.00 79,800.00


0.0060 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 27,000.00 27,600.00
0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00
0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 147,120.00 166,730.00
E OVERHEAD & PROFIT (CONTOH) 10% 14,712.00 16,673.00
F Harga Satuan Pekerjaan (D+E) 161,832.00 183,403.00
koef multipleks koef.kaso

yang ke-1 0.0360 0.0170

bahan digunakan beberapa kali yang ke-2 0.0220 0.0090

yang ke-3 0.0140 0.0060

yang ke-4 0.0110 0.0040

Perancah Bekisting Kolom beton menggunakan kayu


267 B.24.d 1 m2 109,758.00 117,667.00
uk.5/7 cm, tinggi 4m' JAT ≤ 1,00 M

A TENAGA 46,920.00 52,530.00


L.01 0.340 OH Pekerja 75,000 85,000 25,500.00 28,900.00
L.02 0.170 OH Tukang kayu 95,000 105,000 16,150.00 17,850.00

L.03 0.017 OH Kepala Tukang 110,000 120,000 1,870.00 2,040.00


L.04 0.034 OH Mandor 100,000 110,000 3,400.00 3,740.00
B BAHAN 52,860.00 54,440.00
0.0110 m3 Kaso 5/7x 4.00 0.2 4,500,000 4,600,000 49,500.00 50,600.00
0.2400 kg Paku 4 14,000 16,000 3,360.00 3,840.00
0.024

C PERALATAN - -
- -
D Jumlah A + B + C 99,780.00 106,970.00

E OVERHEAD & PROFIT (CONTOH) 10% 9,978.00 10,697.00


F Harga Satuan Pekerjaan (D+E) 109,758.00 117,667.00
kaso

yang ke-1 0.0330

yang ke-2 0.0180

yang ke-3 0.0110

yang ke-4 0.0070


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Perancah Bekisting Kolom beton menggunakan kayu


268 B.24.e 1 m2 78,658.80 88,552.20
dolken Ø 8 -10 cm, tinggi 4m' JAT ≤ 1,20 M

A TENAGA 52,440.00 58,710.00

L.01 0.380 OH Pekerja 75,000 85,000 28,500.00 32,300.00


L.02 0.190 OH Tukang kayu 95,000 105,000 18,050.00 19,950.00

L.03 0.019 OH Kepala Tukang 110,000 120,000 2,090.00 2,280.00

L.04 0.038 OH Mandor 100,000 110,000 3,800.00 4,180.00


B BAHAN 19,068.00 21,792.00
0.03
0.7480 btg Dolken Ø 8 - 10 cm panjang 4 m' 0.2 21,000 24,000 15,708.00 17,952.00

0.2400 kg Paku 4 14,000 16,000 3,360.00 3,840.00


0.024
C PERALATAN - -

- -
D Jumlah A + B + C 71,508.00 80,502.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,150.80 8,050.20

F Harga Satuan Pekerjaan (D+E) 78,658.80 88,552.20


dolken

yang ke-1 2.3000

yang ke-2 1.2650

yang ke-3 0.7480

yang ke-4 0.4900

Perancah Bekisting Kolom beton dengan bambu Ø 8 -10


269 B.24.f 1 m2 71,450.50 84,777.00
cm, tinggi 4m' JAT ≤ 1,00 M

A TENAGA 49,680.00 55,620.00


L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00

L.02 0.180 OH Tukang kayu 95,000 105,000 17,100.00 18,900.00


L.03 0.018 OH Kepala Tukang 110,000 120,000 1,980.00 2,160.00
L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00
B BAHAN 15,275.00 21,450.00
0.9200 btg Bambu Ø 8 - 10 cm panjang 4 m' 0.2 12,000 18,000 11,040.00 16,560.00
0.2400 kg Paku 4 14,000 16,000 3,360.00 3,840.00
3.5000 m' Tambang Ijik / Plastik 0.024 250 300 875.00 1,050.00
C PERALATAN - -
- -
D Jumlah A + B + C 64,955.00 77,070.00

E OVERHEAD & PROFIT (CONTOH) 10% 6,495.50 7,707.00


F Harga Satuan Pekerjaan (D+E) 71,450.50 84,777.00
Bambu

yang ke-1 2.3000

yang ke-2 1.3800

yang ke-3 0.9200

yang ke-4 0.6900

B.25 Bekisting Dinding

270 B.25.a 1 m2 Bekisting Dinding beton expose dengan multipleks 18 mm 146,454.00 158,224.00

A TENAGA 68,760.00 76,680.00

L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00


L.02 0.360 OH Tukang kayu 95,000 105,000 34,200.00 37,800.00
L.03 0.036 OH Kepala Tukang 110,000 120,000 3,960.00 4,320.00

L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00


B BAHAN 64,380.00 67,160.00
0.1280 lbr Multipleks 18 cm 210,000 220,000 26,880.00 28,160.00

0.0070 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 31,500.00 32,200.00


0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00
0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 133,140.00 143,840.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,314.00 14,384.00

F Harga Satuan Pekerjaan (D+E) 146,454.00 158,224.00


multipleks koef.kaso

yang ke-1 0.3530 0.0200

Digunakan berulang kali yang ke-2 0.2030 0.0110

yang ke-3 0.1280 0.0070

yang ke-4 0.0910 0.0040

271 B.25.b 1 m2 Bekisting Dinding beton biasa dengan multipleks 12 mm 86,851.60 98,560.00
atau 18 mm (TP)

A TENAGA 33,120.00 37,080.00

L.01 0.240 OH Pekerja 75,000 85,000 18,000.00 20,400.00


L.02 0.120 OH Tukang kayu 95,000 105,000 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000 120,000 1,320.00 1,440.00

L.04 0.024 OH Mandor 100,000 110,000 2,400.00 2,640.00


B BAHAN 45,836.00 52,520.00
0.1280 lbr Multipleks 12 mm 142,000 185,000 18,176.00 23,680.00

0.0050 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 22,500.00 23,000.00


0.2400 kg Paku 14,000 16,000 3,360.00 3,840.00
0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00

C PERALATAN - -
- -
D Jumlah A + B + C 78,956.00 89,600.00

E OVERHEAD & PROFIT (CONTOH) 10% 7,895.60 8,960.00


F Harga Satuan Pekerjaan (D+E) 86,851.60 98,560.00
papan koef.kaso

yang ke-1 0.3530 0.0160

digunakan berulang kali yang ke-2 0.2030 0.0090

yang ke-3 0.1280 0.0050

yang ke-4 0.0910 0.0030

272 B.25.c 1 m2 Bekisting Dinding beton biasa menggunakan Kayu Papan 159,918.00 181,742.00
3/20 cm

A TENAGA 49,680.00 55,620.00


L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00
L.02 0.180 OH Tukang kayu 95,000 105,000 17,100.00 18,900.00

L.03 0.018 OH Kepala Tukang 110,000 120,000 1,980.00 2,160.00


L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00
B BAHAN 95,700.00 109,600.00

0.0140 m3 Papan Kayu 3/20 4,800,000 5,700,000 67,200.00 79,800.00


0.0050 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 22,500.00 23,000.00

0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00

0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00


C PERALATAN - -

- -

D Jumlah A + B + C 145,380.00 165,220.00


E OVERHEAD & PROFIT (CONTOH) 10% 14,538.00 16,522.00

F Harga Satuan Pekerjaan (D+E) 159,918.00 181,742.00


papan koef.kaso

yang ke-1 0.0360 0.0160

digunakan berulang kali yang ke-2 0.0220 0.0090

yang ke-3 0.0140 0.0050

yang ke-4 0.0110 0.0030


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

273 B.25.d 1 m2 Perancah/Penyokong Bekisting Dinding beton 107,844.00 116,006.00


menggunakan Kayu 5/7 cm, tinggi maksimum 2,50m

A TENAGA 49,680.00 55,620.00


L.01 0.360 OH Pekerja 75,000 85,000 27,000.00 30,600.00

L.02 0.180 OH Tukang kayu 95,000 105,000 17,100.00 18,900.00


L.03 0.018 OH Kepala Tukang 110,000 120,000 1,980.00 2,160.00
L.04 0.036 OH Mandor 100,000 110,000 3,600.00 3,960.00
B BAHAN 48,360.00 49,840.00
0.0100 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 45,000.00 46,000.00
0.2400 kg Paku 14,000 16,000 3,360.00 3,840.00

C PERALATAN - -
- -

D Jumlah A + B + C 98,040.00 105,460.00


E OVERHEAD & PROFIT (CONTOH) 10% 9,804.00 10,546.00
F Harga Satuan Pekerjaan (D+E) 107,844.00 116,006.00
koef.kaso

yang ke-1 0.0300

digunakan berulang kali yang ke-2 0.0170

yang ke-3 0.0100

yang ke-4 0.0060

274 B.25.e 1 m2 Perancah/Penyokong Bekisting Dinding beton 163,416.00 173,404.00


menggunakan Balok 8/12 cm, tinggi maksimum 4,50m

A TENAGA 55,200.00 61,800.00


L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.200 OH Tukang kayu 95,000 105,000 19,000.00 21,000.00
L.03 0.020 OH Kepala Tukang 110,000 120,000 2,200.00 2,400.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 93,360.00 95,840.00
0.0200 m3 Kaso 8/12cm x 4.00m' 4,500,000 4,600,000 90,000.00 92,000.00
0.2400 kg Paku 14,000 16,000 3,360.00 3,840.00

C PERALATAN - -
- -

D Jumlah A + B + C 148,560.00 157,640.00


E OVERHEAD & PROFIT (CONTOH) 10% 14,856.00 15,764.00
F Harga Satuan Pekerjaan (D+E) 163,416.00 173,404.00
koef.balok

yang ke-1 0.0660

digunakan berulang kali yang ke-2 0.0360

yang ke-3 0.0200

yang ke-4 0.0130

B.26 Bekisting Pondasi dan sloof

275 B.26.a 1 m2 Bekisting Pondasi dan sloof beton biasa dengan 110,308.00 117,106.00
Multipleks 12 cm / 18 cm (TP)
A TENAGA 27,600.00 30,900.00

L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00


L.02 0.100 OH Tukang kayu 95,000 105,000 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000 120,000 1,100.00 1,200.00

L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00


B BAHAN 72,680.00 75,560.00

0.1280 lbr Multipleks 18 cm 210,000 220,000 26,880.00 28,160.00

0.0090 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 40,500.00 41,400.00


0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00

0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

C PERALATAN - -
- -
D Jumlah A + B + C 100,280.00 106,460.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,028.00 10,646.00

F Harga Satuan Pekerjaan (D+E) 110,308.00 117,106.00


multipleks koef.kaso

yang ke-1 0.3530 0.0290

Digunakan berulang kali yang ke-2 0.2030 0.0160

yang ke-3 0.1280 0.0090

yang ke-4 0.0910 0.0060

276 B.26.b 1 m2 Bekisting Pondasi dan sloof beton biasa menggunakan 170,610.00 191,785.00
papan 3/20 cm

A TENAGA 41,400.00 46,350.00


L.01 0.300 OH Pekerja 75,000 85,000 22,500.00 25,500.00

L.02 0.150 OH Tukang kayu 95,000 105,000 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000 120,000 1,650.00 1,800.00


L.04 0.030 OH Mandor 100,000 110,000 3,000.00 3,300.00

B BAHAN 113,700.00 128,000.00

0.0140 m3 Papan 3/20 cm 4,800,000 5,700,000 67,200.00 79,800.00


0.0090 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 40,500.00 41,400.00

0.3000 kg Paku 14,000 16,000 4,200.00 4,800.00


0.2000 ltr Minyak Beton 9,000 10,000 1,800.00 2,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 155,100.00 174,350.00
E OVERHEAD & PROFIT (CONTOH) 10% 15,510.00 17,435.00
F Harga Satuan Pekerjaan (D+E) 170,610.00 191,785.00
papan koef.kaso

yang ke-1 0.0360 0.0290

digunakan berulang kali yang ke-2 0.0160 0.0160

yang ke-3 0.0090 0.0090

yang ke-4 0.0060 0.0060

277 B.26.c 1 m2 Perancah/penyokong Bekisting Pondasi dan sloof beton 103,510.00 109,230.00
biasa menggunakan kaso 5/7, tinggi maksimum 2,00 m

A TENAGA 27,600.00 30,900.00


L.01 0.200 OH Pekerja 75,000 85,000 15,000.00 17,000.00
L.02 0.100 OH Tukang kayu 95,000 105,000 9,500.00 10,500.00

L.03 0.010 OH Kepala Tukang 110,000 120,000 1,100.00 1,200.00


L.04 0.020 OH Mandor 100,000 110,000 2,000.00 2,200.00
B BAHAN 66,500.00 68,400.00
0.0140 m3 Kaso 5/7x 4.00 4,500,000 4,600,000 63,000.00 64,400.00

0.2500 kg Paku 14,000 16,000 3,500.00 4,000.00

C PERALATAN - -

- -
D Jumlah A + B + C 94,100.00 99,300.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,410.00 9,930.00

F Harga Satuan Pekerjaan (D+E) 103,510.00 109,230.00


koef.kaso

yang ke-1 0.0350

digunakan berulang kali yang ke-2 0.0190

yang ke-3 0.0140

yang ke-4 0.0110


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

B.27 BONGKAR BEKISTING


Bongkar Beksiting tiap m2 diambil untuk kondisi biasa 10% - 15% dari Upah Kerja Pemasangan
untuk pembongkaran material pakai ulang maka biaya bongkar 20% - 25% dari Upah Pemasangan
Jika tidak ditentukan lain dapat menggunakan acuan sebagai berikut :

278 B.27.a 1 m2 Bongkar Bekisting secara Biasa (membersihkan dan 3,740.00 4,224.00
membereskan puing-puing)

A TENAGA 3,400.00 3,840.00

L.01 0.040 OH Pekerja 75,000 85,000 3,000.00 3,400.00


L.04 0.004 OH Mandor 100,000 110,000 400.00 440.00
B BAHAN - -

C PERALATAN - -
D Jumlah A + B + C 3,400.00 3,840.00
E OVERHEAD & PROFIT (CONTOH) 10% 340.00 384.00

F Harga Satuan Pekerjaan (D+E) 3,740.00 4,224.00

279 B.27.b 1 m2 Bongkar Bekisting secara Biasa secara hati-ahti (dan 5,610.00 6,336.00
membereskan puing-puing)

A TENAGA 5,100.00 5,760.00


L.01 0.060 OH Pekerja 75,000 85,000 4,500.00 5,100.00

L.04 0.006 OH Mandor 100,000 110,000 600.00 660.00


B BAHAN - -
C PERALATAN - -

D Jumlah A + B + C 5,100.00 5,760.00


E OVERHEAD & PROFIT (CONTOH) 10% 510.00 576.00
F Harga Satuan Pekerjaan (D+E) 5,610.00 6,336.00

A.3.5 KOEFISIEN UNT ANALISIS HARGA SATUAN PEKERJAAN PELAKSANAAN CURING


B.28 Pelaksanaan Curring Beton
ada berbagai cara pelaksanaan curing beton diantaranya :
menggenangi atau menyiram permukaan beton, dan dengan uap (steam).
Jika tidak ditentukan dapat menggunakan acuan sebagai berikut
280 B.28.a 100 m2 Menggenangi air permukaan beton 152,900.00 173,140.00

A TENAGA 64,000.00 72,400.00


L.01 0.800 OH Pekerja 75,000 85,000 60,000.00 68,000.00

L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00


B BAHAN 75,000.00 85,000.00
5.000 m3 Air 15,000 17,000 75,000.00 85,000.00

C PERALATAN - -
D Jumlah A + B + C 139,000.00 157,400.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,900.00 15,740.00

F Harga Satuan Pekerjaan (D+E) 152,900.00 173,140.00

281 B.28.b 100 m2 Menyirami air permukaan beton menggunakan media 187,000.00 224,730.00
terpal selama 4 hari

A TENAGA 68,000.00 76,800.00

L.01 0.800 OH Pekerja 75,000 85,000 60,000.00 68,000.00


L.04 0.080 OH Mandor 100,000 110,000 8,000.00 8,800.00
B BAHAN 102,000.00 127,500.00

102.000 m2 karung goni 1,000 1,250 102,000.00 127,500.00


C PERALATAN - -
D Jumlah A + B + C 170,000.00 204,300.00
E OVERHEAD & PROFIT (CONTOH) 10% 17,000.00 20,430.00

F Harga Satuan Pekerjaan (D+E) 187,000.00 224,730.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

282 B.28.c 100 m2 Menyirami permukaan beton menggunakan media karung 506,000.00 573,100.00
goni selama 4 hari

A TENAGA 160,000.00 181,000.00


L.01 2.000 OH Pekerja 75,000 85,000 150,000.00 170,000.00

L.04 0.100 OH Mandor 100,000 110,000 10,000.00 11,000.00


B BAHAN 300,000.00 340,000.00
20.000 m3 Air 15,000 17,000 300,000.00 340,000.00

C PERALATAN - -
D Jumlah A + B + C 460,000.00 521,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 46,000.00 52,100.00

F Harga Satuan Pekerjaan (D+E) 506,000.00 573,100.00

A.3.6 PEMBONGKARAN KONSTRUKSI BETON

Perhitungan praktis pembongkaran beton dan atau bertulang ditentukan oleh tingkat mutu beton
dan kemudahan pembongkarannya. Pada kondisi normal sering dihitung pembongkaran sekitar
2,5 kali upah pembuatan beton. Jika dibutuhkan analisa yang rinci pembongkaran beton
bertulang sebagai berikut :

283 B.29.a 1 m3 Bongkar beton secara konvensional 541,530.00 599,280.00


A TENAGA 306,000.00 345,600.00

L.01 3.600 OH Pekerja 75,000 85,000 270,000.00 306,000.00

L.04 0.360 OH Mandor 100,000 110,000 36,000.00 39,600.00


B BAHAN 180,000.00 192,000.00

1.200 ltr Cuka bibit 150,000 160,000 180,000.00 192,000.00


C PERALATAN 6,300.00 7,200.00
0.020 bh Palu/Godam 80,000 90,000 1,600.00 1,800.00
0.010 bh Gergaji besi 35,000 40,000 350.00 400.00
0.030 bh Pahat beton (baja keras) 20,000 25,000 600.00 750.00
0.050 bh Linggis (baja keras0 75,000 85,000 3,750.00 4,250.00
D Jumlah A + B + C 492,300.00 544,800.00
E OVERHEAD & PROFIT (CONTOH) 10% 49,230.00 54,480.00
F Harga Satuan Pekerjaan (D+E) 541,530.00 599,280.00

284 B.29.b 1 m3 Bongkar beton dengan Jack Hammer 242,825.00 272,470.00


A TENAGA 102,000.00 115,200.00
L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.04 0.120 OH Mandor 100,000 110,000 12,000.00 13,200.00
B BAHAN 18,750.00 20,000.00
2.500 ltr BBM non Subsidi 7,500 8,000 18,750.00 20,000.00
C PERALATAN 100,000.00 112,500.00
0.250 hari Jack Hammer 400,000 450,000 100,000.00 112,500.00

D Jumlah A + B + C 220,750.00 247,700.00


E OVERHEAD & PROFIT (CONTOH) 10% 22,075.00 24,770.00
F Harga Satuan Pekerjaan (D+E) 242,825.00 272,470.00

B.30 PEMASANGAN WATERSTOP


285 B.30.a 1 m' Pasangan Water stop PVC lebar 150 mm 82,720.00 95,535.00
A TENAGA 48,780.00 55,170.00
L.01 0.600 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.02 0.030 OH Tukang Batu 95,000 105,000 2,850.00 3,150.00
L.03 0.003 OH Kepala Tukang 110,000 120,000 330.00 360.00
L.04 0.006 OH Mandor 100,000 110,000 600.00 660.00
B BAHAN 26,420.00 31,680.00
1.050 m' Water stop PVC lebar 150 mm 25,000 30,000 26,250.00 31,500.00
0.010 kg Kawat Beton / Bindrad 17,000 18,000 170.00 180.00
C PERALATAN - -

D Jumlah A + B + C 75,200.00 86,850.00


E OVERHEAD & PROFIT (CONTOH) 10% 7,520.00 8,685.00
F Harga Satuan Pekerjaan (D+E) 82,720.00 95,535.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
286 B.30.b 1 m' Pasangan Water stop PVC lebar 200 mm 57,013.00 64,069.50
A TENAGA 9,660.00 10,815.00
L.01 0.070 OH Pekerja 75,000 85,000 5,250.00 5,950.00
L.02 0.035 OH Tukang Batu 95,000 105,000 3,325.00 3,675.00
L.03 0.0035 OH Kepala Tukang 110,000 120,000 385.00 420.00
L.04 0.007 OH Mandor 100,000 110,000 700.00 770.00
B BAHAN 42,170.00 47,430.00
1.050 m' Water stop PVC lebar 200 mm 40,000 45,000 42,000.00 47,250.00
0.010 kg Kawat Beton / Bindrad 17,000 18,000 170.00 180.00
C PERALATAN - -

D Jumlah A + B + C 51,830.00 58,245.00


E OVERHEAD & PROFIT (CONTOH) 10% 5,183.00 5,824.50
F Harga Satuan Pekerjaan (D+E) 57,013.00 64,069.50

287 B.30.c 1 m' Pasangan Water stop PVC lebar 230 mm - 320 mm 104,731.00 117,744.00
A TENAGA 11,040.00 12,360.00
L.01 0.080 OH Pekerja 75,000 85,000 6,000.00 6,800.00
L.02 0.040 OH Tukang Batu 95,000 105,000 3,800.00 4,200.00
L.03 0.0040 OH Kepala Tukang 110,000 120,000 440.00 480.00
L.04 0.008 OH Mandor 100,000 110,000 800.00 880.00
B BAHAN 84,170.00 94,680.00
1.050 m' Water stop PVC lebar 230 mm- 320 mm 80,000 90,000 84,000.00 94,500.00
0.010 kg Kawat Beton / Bindrad 17,000 18,000 170.00 180.00
C PERALATAN - -

D Jumlah A + B + C 95,210.00 107,040.00


E OVERHEAD & PROFIT (CONTOH) 10% 9,521.00 10,704.00
F Harga Satuan Pekerjaan (D+E) 104,731.00 117,744.00

288 B.30.d 1 m' Pasangan Water stop Ruber lebar 150 mm - 200 mm 149,600.00 162,442.50
A TENAGA 9,660.00 10,815.00
L.01 0.070 OH Pekerja 75,000 85,000 5,250.00 5,950.00
L.02 0.035 OH Tukang Batu 95,000 105,000 3,325.00 3,675.00
L.03 0.0035 OH Kepala Tukang 110,000 120,000 385.00 420.00
L.04 0.007 OH Mandor 100,000 110,000 700.00 770.00
B BAHAN 126,340.00 136,860.00
1.050 m' Water stop Ruber lebar 150 mm- 200 mm 120,000 130,000 126,000.00 136,500.00
0.020 kg Kawat Beton / Bindrad 17,000 18,000 340.00 360.00
C PERALATAN - -

D Jumlah A + B + C 136,000.00 147,675.00


E OVERHEAD & PROFIT (CONTOH) 10% 13,600.00 14,767.50
F Harga Satuan Pekerjaan (D+E) 149,600.00 162,442.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

AHSP (ANALISA HARGA SATUAN PEKERJAAN)


A.4.1 PEMANCANGAN SECARA MANUAL / TANPA MESIN
MENGGUNAKAN TRIPOD DAN HAMMER

289 F.01 1 m' Penetrasi Tiang Pancang Kayu Gelondongan Ø 15 - 20 cm 62,700.00 71,857.50

A TENAGA 45,375.00 51,075.00


L.01 0.450 OH Pekerja 75,000 85,000 33,750.00 38,250.00
L.02 0.075 OH Tukang batu 95,000 105,000 7,125.00 7,875.00
L.04 0.045 OH Mandor 100,000 110,000 4,500.00 4,950.00
B BAHAN - -
- m' Kayu dolken Ø 15 - 20 cm 21,000 24,000 - -
C PERALATAN 11,625.00 14,250.00
0.075 hr Tripod tinggi 5 m' 125,000 150,000 9,375.00 11,250.00
0.075 hr Hammer 1 ton (manual) 30,000 40,000 2,250.00 3,000.00
- bh Alat Penyambung Tiang Pancang 10,000 15,000 - -
D Jumlah A + B + C 57,000.00 65,325.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,700.00 6,532.50
F Harga Satuan Pekerjaan (D+E) 62,700.00 71,857.50

290 F.02 1 m' Penetrasi Tiang Pancang Kayu atau Dolken Ø 8 - 10 cm 13,667.50 15,680.50
A TENAGA 8,800.00 9,880.00
L.01 0.075 OH Pekerja 75,000 85,000 5,625.00 6,375.00
L.02 0.025 OH Tukang batu 95,000 105,000 2,375.00 2,625.00
L.04 0.008 OH Mandor 100,000 110,000 800.00 880.00
B BAHAN - -
- -
- -
C PERALATAN 3,625.00 4,375.00
0.025 hr Tripod tinggi 5 m' 125,000 150,000 3,125.00 3,750.00
0.025 hr Hammer 0,5 ton (manual) 20,000 25,000 500.00 625.00
- -
D Jumlah A + B + C 12,425.00 14,255.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,242.50 1,425.50
F Harga Satuan Pekerjaan (D+E) 13,667.50 15,680.50

Penetrasi Tiang Pancang Baja Pipa Ø 30 cm atau Kotak 30


291 F.03 1 m' 57,172.50 62,672.50
x 30 cm

A TENAGA 17,095.00 19,235.00


L.01 0.168 OH Pekerja 75,000 85,000 12,600.00 14,280.00
L.02 0.021 OH Tukang batu 95,000 105,000 1,995.00 2,205.00
L.04 0.025 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN 15,680.00 17,220.00
0.150 kg Kawat Las Listrik 100,000 110,000 15,000.00 16,500.00
0.080 ltr BBM Non Subsidi 8,500 9,000 680.00 720.00
C PERALATAN 19,200.00 20,520.00
0.0400 hr Tripod tinggi 7 m' 150,000 170,000 6,000.00 6,800.00
0.0400 hr Hammer 1 ton 150,000 160,000 6,000.00 6,400.00
0.0400 hr Las Listrik 250 A Diesel 180,000 183,000 7,200.00 7,320.00
D Jumlah A + B + C 51,975.00 56,975.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,197.50 5,697.50
F Harga Satuan Pekerjaan (D+E) 57,172.50 62,672.50

F.04 TIANG PANCANG BETON BERTULANG


292 F.04.a 1 m' Penetrasi Tiang Pancang Beton Kotak 20 x 20 cm 71,335.00 79,662.00
A TENAGA 42,350.00 47,670.00
L.01 0.4200 OH Pekerja 75,000 85,000 31,500.00 35,700.00
L.02 0.0700 OH Tukang batu 95,000 105,000 6,650.00 7,350.00
L.04 0.0420 OH Mandor 100,000 110,000 4,200.00 4,620.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN - -
- m' Tiang pancang beton bertulang 40 x 40 cm 393,275 424,764 - -
- -
C PERALATAN 22,500.00 24,750.00
0.0750 hr Tripod tinggi 7 m' 150,000 170,000 11,250.00 12,750.00
0.0750 hr Alat Pancang dan Hammer 2 ton 150,000 160,000 11,250.00 12,000.00
100,000 110,000 - -
D Jumlah A + B + C 64,850.00 72,420.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,485.00 7,242.00
F Harga Satuan Pekerjaan (D+E) 71,335.00 79,662.00

293 F.04.b 1 m' Penetrasi Tiang Pancang Beton Kotak 25 x 25 cm 79,640.00 88,968.00
A TENAGA 48,400.00 54,480.00
L.01 0.4800 OH Pekerja 75,000 85,000 36,000.00 40,800.00
L.02 0.0800 OH Tukang batu 95,000 105,000 7,600.00 8,400.00
L.04 0.0480 OH Mandor 100,000 110,000 4,800.00 5,280.00
B BAHAN - -
- m' Tiang pancang beton bertulang 40 x 40 cm - - - -
- -
C PERALATAN 24,000.00 26,400.00
0.0800 hr Tripod tinggi 7 m' 150,000 170,000 12,000.00 13,600.00
0.0800 hr Alat Pancang dan Hammer 2 ton 150,000 160,000 12,000.00 12,800.00
100,000 110,000 - -
D Jumlah A + B + C 72,400.00 80,880.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,240.00 8,088.00
F Harga Satuan Pekerjaan (D+E) 79,640.00 88,968.00

294 F.04.c 1 m' Penetrasi Tiang Pancang Beton Kotak 30 x 30 cm 136,620.00 152,064.00
A TENAGA 97,200.00 108,540.00
L.01 0.5400 OH Pekerja 75,000 85,000 40,500.00 45,900.00
L.02 0.5400 OH Tukang batu 95,000 105,000 51,300.00 56,700.00
L.04 0.0540 OH Mandor 100,000 110,000 5,400.00 5,940.00
B BAHAN - -
- m' Tiang pancang beton bertulang 40 x 40 cm - - - -
- -
C PERALATAN 27,000.00 29,700.00
0.0900 hr Tripod tinggi 7 m' 150,000 170,000 13,500.00 15,300.00
0.0900 hr Alat Pancang dan Hammer 2 ton 150,000 160,000 13,500.00 14,400.00
100,000 110,000 - -
D Jumlah A + B + C 124,200.00 138,240.00
E OVERHEAD & PROFIT (CONTOH) 10% 12,420.00 13,824.00
F Harga Satuan Pekerjaan (D+E) 136,620.00 152,064.00

295 F.04.d 1 m' Penetrasi Tiang Pancang Beton Kotak 40 x 40 cm 166,980.00 185,856.00
A TENAGA 118,800.00 132,660.00
L.01 0.6600 OH Pekerja 75,000 85,000 49,500.00 56,100.00
L.02 0.6600 OH Tukang batu 95,000 105,000 62,700.00 69,300.00
L.04 0.0660 OH Mandor 100,000 110,000 6,600.00 7,260.00
B BAHAN - -
- m' Tiang pancang beton bertulang 40 x 40 cm - - - -
- -
C PERALATAN 33,000.00 36,300.00
0.1100 hr Tripod tinggi 7 m' 150,000 170,000 16,500.00 18,700.00
0.1100 hr Alat Pancang dan Hammer 2 ton 150,000 160,000 16,500.00 17,600.00
100,000 110,000 - -
D Jumlah A + B + C 151,800.00 168,960.00
E OVERHEAD & PROFIT (CONTOH) 10% 15,180.00 16,896.00
F Harga Satuan Pekerjaan (D+E) 166,980.00 185,856.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
296 F.04.e 1 m' Penetrasi Tiang Pancang (Hollow) Beton Ø 40 cm 99,550.00 111,210.00
A TENAGA 60,500.00 68,100.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.02 0.1000 OH Tukang batu 95,000 105,000 9,500.00 10,500.00
L.04 0.0600 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
- m' Tiang pancang beton bertulang 40 x 40 cm - - - -
- -
C PERALATAN 30,000.00 33,000.00
0.1000 hr Tripod tinggi 7 m' 150,000 170,000 15,000.00 17,000.00
0.1000 hr Alat Pancang dan Hammer 2 ton 150,000 160,000 15,000.00 16,000.00
100,000 110,000 - -
D Jumlah A + B + C 90,500.00 101,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,050.00 10,110.00
F Harga Satuan Pekerjaan (D+E) 99,550.00 111,210.00

F.05 TURAP KAYU

Penetrasi untuk 1 m' lebar turap (10-12,5 buah) Kayu


297 F.05.a 1 m' 165,000.00 186,450.00
Dolken Ø 8 - 10 cm

A TENAGA 87,500.00 98,250.00


L.01 0.750 OH Pekerja 75,000 85,000 56,250.00 63,750.00
L.02 0.250 OH Tukang batu 95,000 105,000 23,750.00 26,250.00
L.04 0.075 OH Mandor 100,000 110,000 7,500.00 8,250.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 21,000 24,000 - -
C PERALATAN 62,500.00 71,250.00
0.25 hr Tripod tinggi 5 m' 125,000 150,000 31,250.00 37,500.00
0.25 hr Alat Pancang dan Hammer 0,5 ton 125,000 135,000 31,250.00 33,750.00
bh Alat Penyambung Tiang Pancang 10,000 15,000 - -
D Jumlah A + B + C 150,000.00 169,500.00
E OVERHEAD & PROFIT (CONTOH) 10% 15,000.00 16,950.00
F Harga Satuan Pekerjaan (D+E) 165,000.00 186,450.00

Penetrasi untuk 1 m' lebar turap (10 buah) Papan (2-3) x 10


298 F.05.b 1 m' 152,625.00 171,710.00
cm
A TENAGA 70,000.00 78,600.00
L.01 0.600 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.02 0.200 OH Tukang batu 95,000 105,000 19,000.00 21,000.00
L.04 0.060 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 45,000 46,000 - -
C PERALATAN 68,750.00 77,500.00
0.25 hr Tripod tinggi 5 m' 125,000 150,000 31,250.00 37,500.00
0.25 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 37,500.00 40,000.00
bh Alat Penyambung Tiang Pancang 125,000 150,000 - -
D Jumlah A + B + C 138,750.00 156,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,875.00 15,610.00
F Harga Satuan Pekerjaan (D+E) 152,625.00 171,710.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Penetrasi untuk 1 m' lebar turap (5 buah) Papan (2-3) x 20


299 F.05.c 1 m' 130,212.50 146,377.00
cm
A TENAGA 84,000.00 94,320.00
L.01 0.720 OH Pekerja 75,000 85,000 54,000.00 61,200.00
L.02 0.240 OH Tukang batu 95,000 105,000 22,800.00 25,200.00
L.04 0.072 OH Mandor 100,000 110,000 7,200.00 7,920.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm - - - -
C PERALATAN 34,375.00 38,750.00
0.125 hr Tripod tinggi 5 m' 125,000 150,000 15,625.00 18,750.00
0.125 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 18,750.00 20,000.00
bh Alat Penyambung Tiang Pancang - - - -
D Jumlah A + B + C 118,375.00 133,070.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,837.50 13,307.00
F Harga Satuan Pekerjaan (D+E) 130,212.50 146,377.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Penetrasi untuk 1 m' lebar turap (4 buah) Papan (2-3) x 25


300 F.05.d 1 m' 130,350.00 146,498.00
cm
A TENAGA 91,000.00 102,180.00
L.01 0.780 OH Pekerja 75,000 85,000 58,500.00 66,300.00
L.02 0.260 OH Tukang batu 95,000 105,000 24,700.00 27,300.00
L.04 0.078 OH Mandor 100,000 110,000 7,800.00 8,580.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 13,000 14,500 - -
C PERALATAN 27,500.00 31,000.00
0.1 hr Tripod tinggi 5 m' 125,000 150,000 12,500.00 15,000.00
0.1 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 15,000.00 16,000.00
bh Alat Penyambung Tiang Pancang 393,275 424,764 - -
D Jumlah A + B + C 118,500.00 133,180.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,850.00 13,318.00
F Harga Satuan Pekerjaan (D+E) 130,350.00 146,498.00

Penetrasi untuk 1 m' lebar turap (3,33 buah) Papan (2-3) x


301 F.05.e 1 m' 106,573.50 120,241.00
30 cm

A TENAGA 74,060.00 83,580.00


L.01 0.840 OH Pekerja 75,000 85,000 63,000.00 71,400.00
L.02 0.028 OH Tukang batu 95,000 105,000 2,660.00 2,940.00
L.04 0.084 OH Mandor 100,000 110,000 8,400.00 9,240.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 17,000 18,000 - -
C PERALATAN 22,825.00 25,730.00
0.083 hr Tripod tinggi 5 m' 125,000 150,000 10,375.00 12,450.00
0.083 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 12,450.00 13,280.00
bh Alat Penyambung Tiang Pancang - - - -
D Jumlah A + B + C 96,885.00 109,310.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,688.50 10,931.00
F Harga Satuan Pekerjaan (D+E) 106,573.50 120,241.00

Penetrasi untuk 1 m' lebar turap (4 buah) Kayu Kaso 5/7


302 F.05.f 1 m' 126,923.50 142,851.50
tebal 5 cm
A TENAGA 46,635.00 52,365.00
L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.02 0.133 OH Tukang batu 95,000 105,000 12,635.00 13,965.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 34,000 35,000 - -
C PERALATAN 68,750.00 77,500.00
0.25 hr Tripod tinggi 5 m' 125,000 150,000 31,250.00 37,500.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
0.25 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 37,500.00 40,000.00
bh Alat Penyambung Tiang Pancang 100,000 110,000 - -
D Jumlah A + B + C 115,385.00 129,865.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,538.50 12,986.50
F Harga Satuan Pekerjaan (D+E) 126,923.50 142,851.50

Penetrasi untuk 1 m' lebar turap (20 buah) Kayu Kaso 5/7
303 F.05.g 1 m' 104,511.00 117,518.50
tebal 7 cm

A TENAGA 60,635.00 68,085.00


L.01 0.520 OH Pekerja 75,000 85,000 39,000.00 44,200.00
L.02 0.173 OH Tukang batu 95,000 105,000 16,435.00 18,165.00
L.04 0.052 OH Mandor 100,000 110,000 5,200.00 5,720.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 375,000 380,000 - -
C PERALATAN 34,375.00 38,750.00
0.125 hr Tripod tinggi 5 m' 125,000 150,000 15,625.00 18,750.00
0.125 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 18,750.00 20,000.00
bh Alat Penyambung Tiang Pancang 95,000 105,000 - -
D Jumlah A + B + C 95,010.00 106,835.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,501.00 10,683.50
F Harga Satuan Pekerjaan (D+E) 104,511.00 117,518.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

Penetrasi untuk 1 m' lebar turap (8 buah) Kayu Balok 8/12


304 F.05.h 1 m' 152,625.00 171,710.00
tebal 8 cm

A TENAGA 70,000.00 78,600.00


L.01 0.600 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.02 0.200 OH Tukang batu 95,000 105,000 19,000.00 21,000.00
L.04 0.060 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 135,000 170,000 - -
C PERALATAN 68,750.00 77,500.00
0.25 hr Tripod tinggi 5 m' 125,000 150,000 31,250.00 37,500.00
0.25 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 37,500.00 40,000.00
bh Alat Penyambung Tiang Pancang 75,000 85,000 - -
D Jumlah A + B + C 138,750.00 156,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 13,875.00 15,610.00
F Harga Satuan Pekerjaan (D+E) 152,625.00 171,710.00

Penetrasi untuk 1 m' lebar turap (12,5 buah) Kayu Balok


305 F.05.i 1 m' 130,212.50 146,377.00
8/12 tebal 12 cm
A TENAGA 84,000.00 94,320.00
L.01 0.720 OH Pekerja 75,000 85,000 54,000.00 61,200.00
L.02 0.240 OH Tukang batu 95,000 105,000 22,800.00 25,200.00
L.04 0.072 OH Mandor 100,000 110,000 7,200.00 7,920.00
B BAHAN - -
- m' Kayu dolken Ø 8 - 10 cm 23,000 30,000 - -
C PERALATAN 34,375.00 38,750.00
0.125 hr Tripod tinggi 5 m' 125,000 150,000 15,625.00 18,750.00
0.125 hr Alat Pancang dan Hammer 0,5 ton 150,000 160,000 18,750.00 20,000.00
bh Alat Penyambung Tiang Pancang - - - -
D Jumlah A + B + C 118,375.00 133,070.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,837.50 13,307.00
F Harga Satuan Pekerjaan (D+E) 130,212.50 146,377.00

F.06 TURAP BAJA

306 F.06.a 1 m' Penetrasi (1 buah) Turap Baja Profil Larsen lebar 350 mm 78,595.00 86,295.00

A TENAGA 30,750.00 34,500.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
L.01 0.2500 OH Pekerja 75,000 85,000 18,750.00 21,250.00
L.02 0.0500 OH Tukang batu 95,000 105,000 4,750.00 5,250.00
L.02 0.0500 OH Tukang Listrik **) 95,000 105,000 4,750.00 5,250.00
L.04 0.0250 OH Mandor 100,000 110,000 2,500.00 2,750.00
B BAHAN 16,700.00 18,300.00
0.150 kg Kawat Las Listrik 100,000 110,000 15,000.00 16,500.00
0.200 ltr BBM non Subsidi 8,500 9,000 1,700.00 1,800.00
C PERALATAN 24,000.00 25,650.00

0.0500 hr Tripod tinggi 7 m' 150,000 170,000 7,500.00 8,500.00

0.0500 hr Alat pancang & hammer 1,0 ton 150,000 160,000 7,500.00 8,000.00
0.0500 hr Las listrik diesel 250 A diesel 180,000 183,000 9,000.00 9,150.00
D Jumlah A + B + C 71,450.00 78,450.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,145.00 7,845.00
F Harga Satuan Pekerjaan (D+E) 78,595.00 86,295.00
**) Jika tidak diperlukan pengelasan, isikan HSD bahan & tukang listrik = 0

Penetrasi untuk 1 m' lebar Turap (7 buah) Baja Profil INP-8


307 F.06.b 1 m' 93,720.00 103,125.00
+ UNP-8
A TENAGA 44,500.00 49,800.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.1000 OH Tukang batu 95,000 105,000 9,500.00 10,500.00
L.02 0.1000 OH Tukang Listrik **) 95,000 105,000 9,500.00 10,500.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN 16,700.00 18,300.00
0.150 kg Kawat Las Listrik 100,000 110,000 15,000.00 16,500.00
0.200 ltr BBM non Subsidi 8,500 9,000 1,700.00 1,800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN 24,000.00 25,650.00

0.0500 hr Tripod tinggi 7 m' 150,000 170,000 7,500.00 8,500.00


0.0500 hr Alat pancang & hammer 1,0 ton 150,000 160,000 7,500.00 8,000.00
0.0500 hr Las listrik diesel 250 A diesel 180,000 183,000 9,000.00 9,150.00
D Jumlah A + B + C 85,200.00 93,750.00
E OVERHEAD & PROFIT (CONTOH) 10% 8,520.00 9,375.00
F Harga Satuan Pekerjaan (D+E) 93,720.00 103,125.00
**) Jika tidak diperlukan pengelasan, isikan HSD bahan & tukang listrik = 0

Penetrasi untuk 1 m' lebar Turap (5,56 buah) Baja Profil


308 F.06.c 1 m' 109,758.00 120,021.00
INP- 10 + UNP- 10

A TENAGA 40,050.00 44,820.00


L.01 0.2700 OH Pekerja 75,000 85,000 20,250.00 22,950.00
L.02 0.0900 OH Tukang batu 95,000 105,000 8,550.00 9,450.00
L.02 0.0900 OH Tukang Listrik **) 95,000 105,000 8,550.00 9,450.00
L.04 0.0270 OH Mandor 100,000 110,000 2,700.00 2,970.00
B BAHAN 16,530.00 18,120.00
0.150 kg Kawat Las Listrik 100,000 110,000 15,000.00 16,500.00
0.180 ltr BBM non Subsidi 8,500 9,000 1,530.00 1,620.00
C PERALATAN 43,200.00 46,170.00

0.0900 hr Tripod tinggi 7 m' 150,000 170,000 13,500.00 15,300.00

0.0900 hr Alat pancang & hammer 1,0 ton 150,000 160,000 13,500.00 14,400.00
0.0900 hr Las listrik diesel 250 A diesel 180,000 183,000 16,200.00 16,470.00
D Jumlah A + B + C 99,780.00 109,110.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,978.00 10,911.00
F Harga Satuan Pekerjaan (D+E) 109,758.00 120,021.00
**) Jika tidak diperlukan pengelasan, isikan HSD bahan & tukang listrik = 0

F.07 TURAP BETON PRE - CAST


309 F.07.a 1 m' Penetrasi 1 buah Turap Beton pre-cast 12 x 30 cm 48,400.00 55,605.00
A TENAGA 30,250.00 34,050.00
L.01 0.3000 OH Pekerja 75,000 85,000 22,500.00 25,500.00
L.02 0.0500 OH Tukang batu 95,000 105,000 4,750.00 5,250.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
- m' Beton bertulang precast 80,000 85,000 - -
C PERALATAN 13,750.00 16,500.00
0.05 hr Tripod tinggi 5 m' 125,000 170,000 6,250.00 8,500.00
0.05 hr Alat Pancang & Hammer 2 ton 150,000 160,000 7,500.00 8,000.00
- - -
D Jumlah A + B + C 44,000.00 50,550.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,400.00 5,055.00
F Harga Satuan Pekerjaan (D+E) 48,400.00 55,605.00

310 F.07.b 1 m' Penetrasi 1 buah Turap Beton Precast 15 x 40 cm 77,440.00 88,968.00
A TENAGA 48,400.00 54,480.00
L.01 0.4800 OH Pekerja 75,000 85,000 36,000.00 40,800.00
L.02 0.0800 OH Tukang batu 95,000 105,000 7,600.00 8,400.00
L.04 0.0480 OH Mandor 100,000 110,000 4,800.00 5,280.00
B BAHAN - -
m' Beton bertulang precast 135,000 145,000 - -
C PERALATAN 22,000.00 26,400.00
0.08 hr Tripod tinggi 5 m' 125,000 170,000 10,000.00 13,600.00
0.08 hr Alat Pancang & Hammer 2 ton 150,000 160,000 12,000.00 12,800.00
bh Alat Penyambung Tiang Pancang - - - -
D Jumlah A + B + C 70,400.00 80,880.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,040.00 8,088.00
F Harga Satuan Pekerjaan (D+E) 77,440.00 88,968.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
311 F.07.c 1 m' Penetrasi 1 buah Turap Beton Precast 22 x 50 cm 96,800.00 111,210.00
A TENAGA 60,500.00 68,100.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.02 0.1000 OH Tukang batu 95,000 105,000 9,500.00 10,500.00
L.04 0.0600 OH Mandor 100,000 110,000 6,000.00 6,600.00
B BAHAN - -
m' Beton bertulang precast 250,000 270,000 - -
C PERALATAN 27,500.00 33,000.00
0.1 hr Tripod tinggi 5 m' 125,000 170,000 12,500.00 17,000.00
0.1 hr Alat Pancang & Hammer 2 ton 150,000 160,000 15,000.00 16,000.00
- - - -
D Jumlah A + B + C 88,000.00 101,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 8,800.00 10,110.00
F Harga Satuan Pekerjaan (D+E) 96,800.00 111,210.00
T.12 PERKUAT DINDING GALIAN SANGAT TERGANTUNG PADA POTENSI GALIAN TANAHNYA,
- UNT TANAH BIASA & TANAH BERBATU SERING DIPERLUKAN JIKA KEDALAMAN GALIAN LEBIH DARI 2 m

- UNT TANAH CADAS / KERAS APALAGI BATU PADA UMUMNYA TIDAK DIPERLUKAN PERKUATAN

HAL INI SERING DILAKUKAN PADA GALIAN TANAH DENGAN KEDALAMAN > 1 m DALAM RANGKA PEMASANGAN
PIPA, GORONG-GORONG ATAU BOX CULVERT

TABEL A.1 ASUMSI KOEFISIEN PEMAKAIAN ULANG BAHAN / MATERIAL


PEMAKAIAN BAHAN/ PENAMBAHAN MATERIAL CATATAN
NO.
MATERIAL 5% 35% 40% 50% - 5% UNT BAHAN BAJA/BESI : SV = 50%
1 PERTAMA 0.500 1.000 1.000 1.000 - 35% UNT BAHAN KASO/BALOK KAYU : SV = 0%
2 KEDUA 0.275 0.675 0.700 0.750 - 40% UNT BAHAN MULTIPLEKS/PAPAN KAYU ; SV = 0%
3 KETIGA 0.200 0.567 0.500 0.867 - 50% UNT BAHAN SESEG BAMBU DLL; SV = 0%
4 KEEMPAT 0.165 0.513 0.550 0.625

TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN RANGKA & DINDING
A.2 a) TIANG RANGKA PERKUATAN DINDING

1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m' JARAK


NO. BAHAN a) b) c) d) e) f) g) h) i) j) TIANG

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)

1 KASO 5/7 DIPAKAI 1 KALI 0.04200 m3 0.0150 m3

- DIPAKAI KE 2 0.02840 m3 0.860 OH 0.430 OH 0.086 OH 0.125 0.0101 m3 0.800 OH 0.300 OH 0.080 OH 0.120 0.5
- DIPAKAI KE 3 0.02380 m3 0.0085 m3

2 BAJA L.50.50.5 7.420 kg 4.950 kg

4.080 kg 1.000 OH 0.500 OH 0.100 OH 0.120 2.720 kg 0.72 OH 0.38 OH 0.072 OH 0.110 0.8

2.970 kg 1.980 kg
3 BAJA INP - 10 13.100 kg 4.950 kg

7.200 kg 1.200 OH 0.600 OH 0.120 OH 0.100 2.720 kg 0.86 OH 0.43 OH 0.086 OH 0.090 1
5.240 kg 1.980 kg

b) DINDING PERKUATAN

1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m'


NO. BAHAN a) b) c) d) e) f) g) h) i) j)

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN

1 SESEG BAMBU KE-1 2.40 m2 2.00 m2

KE-2 1.80 m2 0.400 OH 0.200 OH 0.040 OH 0.06 1.50 m2 0.300 OH 0.150 OH 0.030 OH 0.050

KE-3 1.60 m2 1.33 m2

2 PAPAN 2/20 KE-1 0.048 m3 0.040 m3

KE-2 0.034 m3 0.500 OH 0.250 OH 0.050 OH 0.06 0.028 m3 0.376 OH 0.188 OH 0.0375 OH 0.070
KE-3 0.029 m3 0.024 m3

3 BALOK KAYU 8/12 KE-1 0.192 m3 0.180 m3

KE-2 0.130 m3 0.480 OH 0.230 OH 0.045 OH 0.09 0.108 m3 0.338 OH 0.169 OH 0.0338 OH 0.080

KE-3 0.109 m3 0.091 m3

TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN TURAP
A.3

1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m' JARAK

NO. BAHAN a) b) c) d) e) f) g) h) i) j) TIANG

BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)
1 KASO 5/7 DIPAKAI KE-1 0.049612 m3 0.033075 m3

KE-2 0.033488 m3 0.840 OH 0.280 OH 0.084 OH 0.10 0.022326 m3 0.570 OH 0.190 OH 0.057 OH 0.070 5

KE-3 0.028130 m3 0.018754 m3

2 BALOK KAYU 8/12 KE-1 0.090720 m3 0.080480 m3

KE-2 0.061236 m3 1.280 OH 0.420 OH 0.126 OH 0.12 0.040824 m3 0.84 OH 0.28 OH 0.064 OH 0.06 5

KE-3 0.051438 m3 0.034292 m3

3 BAJA INP - 8 37.50 kg 25.00 kg


20.62 kg 1.500 oh 0.500 OH 0.150 OH 0.15 13.75 kg 1.2 OH 0.4 OH 0.12 OH 0.11 5

15.00 kg 10.00 kg

4 BAJA INP-10 52.500 kg 35.000 kg

28.860 kg 2.100 OH 0.700 OH 0.210 OH 0.160 19.220 kg 1.5 OH 0.5 OH 0.15 OH 0.120 5
21.000 kg 14.000 kg

5 PROFIL LARSEN U-400 71.860 kg 47.910 kg


39.520 kg 3.000 OH 1.000 OH 0.300 OH 0.240 26.350 kg 2.1 OH 0.7 OH 0.21 OH 0.180 5

28.750 kg 19.160 kg
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

55 T.12.a 1 m' PERKUATAN DINDING GALIAN UNT 1 m' PALING BAWAH


A TENAGA
L.01 b) + g) OH Pekerja (tabel A.2)
L.02 c) + h) OH Tukang
L.04 d) + i) OH Mandor
B BAHAN - -
a) m3/kg Tiang rangka Perkuatan Dinding (Tabel A.2)
f) m2/m3 Dinding Perkuatan (tabel.A.2)
C PERALATAN - -
e) + j) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C - -
E OVERHEAD & PROFIT (CONTOH) 10% - -
F Harga Satuan Pekerjaan (D+E) - -

56 T.12.a 1 m' PERKUATAN DINDING GALIAN UNT 1 m' PALING BAWAH 1,062,391.00 1,263,339.00
contoh MENGGUNAKAN BAJA INP-10 & BALOK KAYU 8/12
A TENAGA 210,450.00 236,010.00
L.01 1.660 OH Pekerja 75,000 85,000 124,500.00 141,100.00
L.02 0.730 OH Tukang 95,000 105,000 69,350.00 76,650.00
L.04 0.166 OH Mandor 100,000 110,000 16,600.00 18,260.00
B BAHAN 738,260.00 893,480.00
5.240 kg Tiang perkuatan dengan INP -10 14,000 14,500 73,360.00 75,980.00
0.109 m3 Dinding perkuatan kayu 8/12 6,100,000 7,500,000 664,900.00 817,500.00
C PERALATAN 17,100.00 19,000.00
0.190 hr Crane 2 ton 90,000 100,000 17,100.00 19,000.00
D Jumlah A + B + C 965,810.00 1,148,490.00
E OVERHEAD & PROFIT (CONTOH) 10% 96,581.00 114,849.00
F Harga Satuan Pekerjaan (D+E) 1,062,391.00 1,263,339.00

43a T.12.b 1 m' PENAMBAHAN TINGGI PERKUATAN DINDING GALIAN


A TENAGA
L.01 b) + g) OH Pekerja (tabel A.2)
L.02 c) + h) OH Tukang
L.04 d) + i) OH Mandor
B BAHAN - -
a) m3/kg Tiang rangka Perkuatan Dinding (Tabel A.2)
f) m2/m3 Dinding Perkuatan (tabel.A.2)
C PERALATAN - -
e) + j) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C - -
E OVERHEAD & PROFIT (CONTOH) 10% - -
F Harga Satuan Pekerjaan (D+E) - -

43 T.12.b 1 m' PENAMBAHAN TINGGI PERKUATAN DINDING GALIAN 988,902.20 1,167,804.00


contoh MENGGUNAKAN BAJA INP-10 & BALOK KAYU
A TENAGA 256,950.00 288,260.00
L.01 2.060 OH Pekerja 75,000 85,000 154,500.00 175,100.00
L.02 0.930 OH Tukang 95,000 105,000 88,350.00 97,650.00
L.04 0.141 OH Mandor 100,000 110,000 14,100.00 15,510.00
B BAHAN 626,752.00 756,380.00
5.240 kg Tiang perkuatan dengan INP -10 14,000 14,500 73,360.00 75,980.00
0.091 m3 Dinding perkuatan kayu 8/12 6,100,000 7,500,000 553,392.00 680,400.00
C PERALATAN 15,300.00 17,000.00
0.170 hr Crane 2 ton 90,000 100,000 15,300.00 17,000.00
D Jumlah A + B + C 899,002.00 1,061,640.00
E OVERHEAD & PROFIT (CONTOH) 10% 89,900.20 106,164.00
F Harga Satuan Pekerjaan (D+E) 988,902.20 1,167,804.00

44a T.12.c 1 m' PERKUATAN DINDING GALIAN DG TURAP PALING BAWAH


A TENAGA
L.01 b) OH Pekerja (Tabel A.3)
L.02 c) OH Tukang
L.04 d) OH Mandor
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN - -
a) m3/kg Perkuatan Dinding galian dg Turap (Tabel A.3)

C PERALATAN - -
e) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C - -
E OVERHEAD & PROFIT (CONTOH) 10% - -
F Harga Satuan Pekerjaan (D+E) - -

44 T.12.c 1 m' PERKUATAN DINDING GALIAN DG TURAP PALING BAWAH 438,350.00 471,900.00
contoh MENGGUNAKAN TURAP BAJA INP-8
A TENAGA 175,000.00 196,500.00
L.01 1.500 OH Pekerja 75,000 85,000 112,500.00 127,500.00
L.02 0.500 OH Tukang 95,000 105,000 47,500.00 52,500.00
L.04 0.150 OH Mandor 100,000 110,000 15,000.00 16,500.00
B BAHAN 210,000.00 217,500.00
15.000 kg Perkuatan Dinding galian dg Turap (Tabel A.3) 14,000 14,500 210,000.00 217,500.00
- -
C PERALATAN 13,500.00 15,000.00
0.150 hr Crane 2 ton 90,000 100,000 13,500.00 15,000.00
D Jumlah A + B + C 398,500.00 429,000.00
E OVERHEAD & PROFIT (CONTOH) 10% 39,850.00 42,900.00
F Harga Satuan Pekerjaan (D+E) 438,350.00 471,900.00

45a T.12.d 1 m' PERKUATAN DINDING GALIAN DG TURAP UNTUK PENAMBAHAN TINGGI
A TENAGA
L.01 g) OH Pekerja (Tabel A.3)
L.02 h) OH Tukang
L.04 i) OH Mandor
B BAHAN - -
f) m3/kg Perkuatan Dinding galian dg Turap (Tabel A.3)

C PERALATAN - -
j) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C - -
E OVERHEAD & PROFIT (CONTOH) 10% - -
F Harga Satuan Pekerjaan (D+E) - -

45 T.12.d 1 m' PERKUATAN DINDING GALIAN DG TURAP UNTUK PENAMBAHAN TINGGI 318,890.00 344,520.00
contoh MENGGUNAKAN TURAP BAJA INP-8
A TENAGA 140,000.00 157,200.00
L.01 1.200 OH Pekerja 75,000 85,000 90,000.00 102,000.00
L.02 0.400 OH Tukang 95,000 105,000 38,000.00 42,000.00
L.04 0.120 OH Mandor 100,000 110,000 12,000.00 13,200.00
B BAHAN 140,000.00 145,000.00
10.00 kg Perkuatan Dinding galian dg Turap (Tabel A.3) 14,000 14,500 140,000.00 145,000.00
- -
C PERALATAN 9,900.00 11,000.00
0.110 hr Crane 2 ton 90,000 100,000 9,900.00 11,000.00
D Jumlah A + B + C 289,900.00 313,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 28,990.00 31,320.00
F Harga Satuan Pekerjaan (D+E) 318,890.00 344,520.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8

T.14 TIMBUNAN DAN PEMADATAN


59 T.14.a.1 1 m3 TIMBUNAN TANAH ATAU URUGAN TANAH KEMBALI 32,257.50 36,432.00
A TENAGA 28,050.00 31,680.00
L.01 0.330 OH Pekerja 75,000 85,000 24,750.00 28,050.00
L.04 0.033 OH Mandor 100,000 110,000 3,300.00 3,630.00
B BAHAN - -

C PERALATAN - -

D Jumlah A + B + C 28,050.00 31,680.00


E OVERHEAD & PROFIT (CONTOH) 15% 4,207.50 4,752.00
F Harga Satuan Pekerjaan (D+E) 32,257.50 36,432.00

60 T.14.b.1 1 m3 PEMADATAN TANAH 51,175.00 58,075.00


A TENAGA 42,500.00 48,000.00
L.01 0.500 OH Pekerja 75,000 85,000 37,500.00 42,500.00
L.04 0.050 OH Mandor 100,000 110,000 5,000.00 5,500.00
B BAHAN - -
- -
C PERALATAN 2,000.00 2,500.00
0.050 hr Pemadatan tanah (Stamper) 40,000 50,000 2,000.00 2,500.00
D Jumlah A + B + C 44,500.00 50,500.00
E OVERHEAD & PROFIT (CONTOH) 15% 6,675.00 7,575.00
F Harga Satuan Pekerjaan (D+E) 51,175.00 58,075.00

61 T.14.c.1 1 m3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI 473,800.00 554,760.00


A TENAGA 34,000.00 38,400.00
L.01 0.400 OH Pekerja 75,000 85,000 30,000.00 34,000.00
L.04 0.040 OH Mandor 100,000 110,000 4,000.00 4,400.00
B BAHAN 378,000.00 444,000.00
1.200 m3 Pasir Pasang 315,000 370,000 378,000.00 444,000.00
C PERALATAN - -
- -
D Jumlah A + B + C 412,000.00 482,400.00
E OVERHEAD & PROFIT (CONTOH) 15% 61,800.00 72,360.00
F Harga Satuan Pekerjaan (D+E) 473,800.00 554,760.00

62 T.14.d 1 m3 PEMADATAN PASIR SEBAGAI BAHAN PENGISI 12,500.00 14,600.00


A TENAGA 8,500.00 9,600.00
L.01 0.100 OH Pekerja 75,000 85,000 7,500.00 8,500.00
L.04 0.010 OH Mandor 100,000 110,000 1,000.00 1,100.00
B BAHAN - -
- - -
C PERALATAN 4,000.00 5,000.00
0.100 hr Pemadatan tanah (Stamper) 40,000 50,000 4,000.00 5,000.00
D Jumlah A + B + C 12,500.00 14,600.00
E OVERHEAD & PROFIT (CONTOH) - -
F Harga Satuan Pekerjaan (D+E) 12,500.00 14,600.00

T.15 ANGKUTAN MATERIAL DAN ATAU GALIAN

Koefisien pada AHSP T.15.a adalah kondisi normal, untuk hal khusus seperti angkutan melalui sungai dengan kedalaman s/d 0,5 m dikalikan 1,2; sedang untuk kedalaman
sungai 1 m dikalikan 1,5

T.15.a. ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK JARAK HARIZONTAL (DATAR)
AHSP T.15.a ini berlaku pada angkutan material untuk jarak harizontal (datar) dan termasuk juga medan dengan pelandaian menurun 1V:5H sampai dengan pelandaian
1V:10H yang dihitung sebagai panjang lintasannya.
MENGANGKUT MATERIAL ATAU DAN HASIL GALIAN DG
63 T.15.a.1 1 m3 21,824.00 24,688.40
JARAK ANGKUT 5 m
A TENAGA 19,840.00 22,444.00
L.01 0.2480 OH Pekerja 75,000 85,000 18,600.00 21,080.00
L.04 0.0124 OH Mandor 100,000 110,000 1,240.00 1,364.00
B BAHAN - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -

D Jumlah A + B + C 19,840.00 22,444.00


E OVERHEAD & PROFIT (CONTOH) 10% 1,984.00 2,244.40
F Harga Satuan Pekerjaan (D+E) 21,824.00 24,688.40

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


64 T.15.a.2 1 m3 24,183.50 27,358.10
JARAK ANGKUT 10 m
A TENAGA 21,985.00 24,871.00
L.01 0.2750 OH Pekerja 75,000 85,000 20,625.00 23,375.00
L.04 0.0136 OH Mandor 100,000 110,000 1,360.00 1,496.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 21,985.00 24,871.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,198.50 2,487.10
F Harga Satuan Pekerjaan (D+E) 24,183.50 27,358.10

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


65 T.15.a.3 1 m3 27,725.50 31,364.30
JARAK ANGKUT 20 m

A TENAGA 25,205.00 28,513.00


L.01 0.3150 OH Pekerja 75,000 85,000 23,625.00 26,775.00
L.04 0.0158 OH Mandor 100,000 110,000 1,580.00 1,738.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 25,205.00 28,513.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,520.50 2,851.30
F Harga Satuan Pekerjaan (D+E) 27,725.50 31,364.30

MENGANGKUT MATERIAL DAN ATAU HASIL HASIL


66 T.15.a.4 1 m3 31,328.00 35,439.80
GALIAN DG JARAK ANGKUT 30 m
A TENAGA 28,480.00 32,218.00
L.01 0.3560 OH Pekerja 75,000 85,000 26,700.00 30,260.00
L.04 0.0178 OH Mandor 100,000 110,000 1,780.00 1,958.00
B BAHAN - -
- - -
C PERALATAN - -

D Jumlah A + B + C 28,480.00 32,218.00


E OVERHEAD & PROFIT (CONTOH) 10% 2,848.00 3,221.80
F Harga Satuan Pekerjaan (D+E) 31,328.00 35,439.80

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


67 T.15.a.5 1 m3 37,136.00 42,010.10
JARAK ANGKUT 50 m
A TENAGA 33,760.00 38,191.00
L.01 0.4220 OH Pekerja 75,000 85,000 31,650.00 35,870.00
L.04 0.0211 OH Mandor 100,000 110,000 2,110.00 2,321.00
B BAHAN - -

C PERALATAN - -

D Jumlah A + B + C 33,760.00 38,191.00


E OVERHEAD & PROFIT (CONTOH) 10% 3,376.00 3,819.10
F Harga Satuan Pekerjaan (D+E) 37,136.00 42,010.10

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


68 T.15.a.6 1 m3 52,800.00 59,730.00
JARAK ANGKUT 100 m
A TENAGA 48,000.00 54,300.00
L.01 0.6000 OH Pekerja 75,000 85,000 45,000.00 51,000.00
L.04 0.0300 OH Mandor 100,000 110,000 3,000.00 3,300.00
B BAHAN - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
- -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -
- -
D Jumlah A + B + C 48,000.00 54,300.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,800.00 5,430.00
F Harga Satuan Pekerjaan (D+E) 52,800.00 59,730.00

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


69 T.15.a.7 1 m3 83,600.00 94,572.50
JARAK ANGKUT 200 m
A TENAGA 76,000.00 85,975.00
L.01 0.9500 OH Pekerja 75,000 85,000 71,250.00 80,750.00
L.04 0.0475 OH Mandor 100,000 110,000 4,750.00 5,225.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 76,000.00 85,975.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,600.00 8,597.50
F Harga Satuan Pekerjaan (D+E) 83,600.00 94,572.50

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


70 T.15.a.8 1 m3 114,400.00 129,415.00
JARAK ANGKUT 300 m
A TENAGA 104,000.00 117,650.00
L.01 1.3000 OH Pekerja 75,000 85,000 97,500.00 110,500.00
L.04 0.0650 OH Mandor 100,000 110,000 6,500.00 7,150.00
B BAHAN - -
- - -
C PERALATAN - -
- - - -
D Jumlah A + B + C 104,000.00 117,650.00
E OVERHEAD & PROFIT (CONTOH) 10% 10,400.00 11,765.00
F Harga Satuan Pekerjaan (D+E) 114,400.00 129,415.00

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


71 T.15.a.9 1 m3 145,200.00 164,257.50
JARAK ANGKUT 400 m
A TENAGA 132,000.00 149,325.00
L.01 1.6500 OH Pekerja 75,000 85,000 123,750.00 140,250.00
L.04 0.0825 OH Mandor 100,000 110,000 8,250.00 9,075.00
B BAHAN - -

C PERALATAN - -

D Jumlah A + B + C 132,000.00 149,325.00


E OVERHEAD & PROFIT (CONTOH) 10% 13,200.00 14,932.50
F Harga Satuan Pekerjaan (D+E) 145,200.00 164,257.50

MENGANGKUT MATERIAL DAN ATAU HASIL GALIAN DG


72 T.15.a.10 1 m3 171,600.00 194,122.50
JARAK ANGKUT 500 m
A TENAGA 156,000.00 176,475.00
L.01 1.9500 OH Pekerja 75,000 85,000 146,250.00 165,750.00
L.04 0.0975 OH Mandor 100,000 110,000 9,750.00 10,725.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 156,000.00 176,475.00
E OVERHEAD & PROFIT (CONTOH) 10% 15,600.00 17,647.50
F Harga Satuan Pekerjaan (D+E) 171,600.00 194,122.50

MENGANGKUT HASIL GALIAN DG JARAK ANGKUT > 500


73 T.15.a.11 1 m3 30,976.00 35,041.60
M UNTUK SETIAP PENAMBAHAN JARAK ANGKUT 100 M

A TENAGA 28,160.00 31,856.00


L.01 0.3520 OH Pekerja 75,000 85,000 26,400.00 29,920.00
L.04 0.0176 OH Mandor 100,000 110,000 1,760.00 1,936.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 28,160.00 31,856.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,816.00 3,185.60
F Harga Satuan Pekerjaan (D+E) 30,976.00 35,041.60

ANGKUTAN MATERIAL DAN ATAU HASIL GALIAN UNTUK


T.15.b
JARAK VERTIKAL MENURUN
AHSP T.15.b hanya berlaku untuk pelandaian turun lebih terjal dari 1v : 5h
MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH
74 T.15.b.1 1 m3 13,200.00 14,932.50
SAMPAI BEDA TINGGI 1 M

A TENAGA 12,000.00 13,575.00


L.01 0.1500 OH Pekerja 75,000 85,000 11,250.00 12,750.00
L.04 0.0075 OH Mandor 100,000 110,000 750.00 825.00
B BAHAN - -
- -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
1 2 3 4 5 6 7 8 9=4X7 10 = 4 X 8
C PERALATAN - -
- -
D Jumlah A + B + C 12,000.00 13,575.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,200.00 1,357.50
F Harga Satuan Pekerjaan (D+E) 13,200.00 14,932.50

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


75 T.15.b.2 1 m3 18,480.00 20,905.50
SAMPAI BEDA TINGGI >1M s/d 2 M

A TENAGA 16,800.00 19,005.00


L.01 0.2100 OH Pekerja 75,000 85,000 15,750.00 17,850.00
L.04 0.0105 OH Mandor 100,000 110,000 1,050.00 1,155.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 16,800.00 19,005.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,680.00 1,900.50
F Harga Satuan Pekerjaan (D+E) 18,480.00 20,905.50

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


76 T.15.b.3 1 m3 24,398.00 27,600.10
SAMPAI BEDA TINGGI >2M s/d 3 M

A TENAGA 22,180.00 25,091.00


L.01 0.2772 OH Pekerja 75,000 85,000 20,790.00 23,562.00
L.04 0.0139 OH Mandor 100,000 110,000 1,390.00 1,529.00
B BAHAN - -
- -
C PERALATAN - -
- -
D Jumlah A + B + C 22,180.00 25,091.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,218.00 2,509.10
F Harga Satuan Pekerjaan (D+E) 24,398.00 27,600.10

MENURUNKAN MATERIAL ATAU HASIL GALIAN TANAH


77 T.15.b.4 1 m3 30,489.25 34,491.05
SAMPAI BEDA TINGGI >3M s/d 4 M

A TENAGA 27,717.50 31,355.50


L.01 0.3465 OH Pekerja 75,000 85,000 25,987.50 29,452.50
L.04 0.0173 OH Mandor 100,000 110,000 1,730.00 1,903.00

Anda mungkin juga menyukai