Anda di halaman 1dari 175

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)

1 Dump Truck 3 ton Jam 85,000 100,000

2 Dump Truck 9 ton Jam 110,000 115,000


3 Truk Bak Terbuka Engkel Jam 125,000 130,000

4 Truk Tanki Air Jam 280,000 290,000

5 Bulldozer 100 - 150 hp Jam 675,000 700,000

6 Motor Grader Jam 625,000 640,000

7 Wheel Loader Jam 270,000 280,000


8 Excavator Jam 650,000 660,000

9 Crane 35 ton Jam 550,000 600,000

10 Flat Bed Truck jam 430,000 440,000

11 Baby Roller / Pedestrian Jam 110,000 120,000

12 P.Tire Roller 8 - 10 ton Jam 500,000 550,000


13 Baby Roller jam 40,000 42,000

14 Vibrator Roller self 7 ton Jam 500,000 510,000

15 Pile Driver / Hammer jam 150,000 160,000

16 Water Pump Jam 40,000 42,500


17 Asphalt Sprayer Jam 135,000 140,000

18 Pick Up single cabin Jam 40,000 55,000

19 A M P Jam 5,500,000 5,600,000

20 Asphalt Finisher Jam 340,000 350,000

21 Concrete Vibrator Jam 55,000 60,000

22 Compressor Jam 310,000 320,000

23 Concrete Mixer 0,125m3 Jam 75,000 80,000

24 Concrete Cutter jam 35,000 40,000

25 Stamper Jam 40,000 45,000

26 Genset 5-25kva+bbm Jam 180,000 183,000

27 Alat Pengecat Marka Jam 300,000 310,000

28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 850,000 900,000

30 Truck Trailler trip 7,250,000 7,400,000


DAFTAR U PAH PE K E R JA

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 75,000 85,000

2 Mandor Hr 100,000 110,000

3 Tukang listrik Hr 95,000 105,000

4 Tukang kayu Hr 95,000 105,000

5 Kep. tk. kayu Hr 110,000 120,000

6 Tukang batu Hr 95,000 105,000

7 Kep. tk. batu Hr 110,000 120,000

8 Tukang besi Hr 95,000 105,000

9 Kep. tk. besi Hr 110,000 120,000

10 T u k a n g c a t Hr 95,000 105,000

11 K e p . t k . c a t Hr 110,000 120,000

12 T u k a n g p l i t u r Hr 95,000 105,000

13 T u k a n g j a l a n Hr 75,000 85,000

14 T u k a n g g a l i Hr 75,000 85,000

15 Tukang masak aspal Hr 75,000 85,000

16 T k . l e i d e n g Hr 95,000 105,000

17 M a s i n i s Hr 150,000 175,000

18 P e m b . M a s i n i s Hr 100,000 125,000

19 P e n j a g a a p i Hr 75,000 85,000

20 P e n j a g a m a l a m Hr 75,000 85,000

21 Sopir Hr 140,000 150,000

22 Pembantu Sopir Hr 85,000 100,000

415837925.xls 175 utk


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000 250,000
Bulat Belah m3 260,000 335,000
Pecah 10/15 m3 260,000 300,000
Pecah 5/7 m3 300,000 350,000
Pecah 3/5 m3 330,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 170,000 190,000
Beton 0,5/1 m3 300,000 370,000
Beton 1/2 m3 300,000 400,000
Beton 2/3 m3 310,000 390,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 330,000
3 BATU BATA ex lokal bh 600 650

4 PASIR Urug m3 160,000 230,000


Pasang m3 315,000 370,000
Beton m3 350,000 380,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 44,000 46,000
Merk I 50 kg zak 55,000 56,500
Merk II 40 kg zak 44,500 45,750
Merk II 50 kg zak 54,000 56,000
Semen Putih 40 kg zak 80,000 89,000
Semen Putih 50 kg zak 90,000 95,000
Semen warna kg 11,000 15,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000 190,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000 7,000


Genteng Beton Warna Special bh 9,500 10,500
Genteng Beton Warna Khusus bh 14,000 15,200
Kerpus Beton Warna Standard bh 10,000 10,050
Kerpus Beton Warna Special bh 11,500 12,000
Kerpus Beton Warna Khusus bh 13,000 13,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,300 2,600
Kodok bh 2,500 3,100
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 12,500 15,000
Vlaam tebal 3 mm bh 13,500 17,000
Kodok tebal 2 mm bh 12,500 15,000
Kodok tebal 3 mm bh 14,500 17,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 85,000 115,000
. 225 cm X 102 cm X 5 mm bh 98,000 125,000
. 250 cm X 102 cm X 5 mm bh 108,000 135,000
. 200 cm X 102 cm X 6 mm bh 120,000 145,000
. 225 cm X 102 cm X 6 mm bh 130,000 155,000
. 250 cm X 102 cm X 6 mm bh 140,000 160,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,000 47,000
. 180 cm X 105 cm X 4 mm bh 50,000 55,000
. 210 cm X 105 cm X 4 mm bh 59,500 63,000
. 240 cm X 105 cm X 4 mm bh 65,000 72,000
. 270 cm X 105 cm X 4 mm bh 75,000 81,000
. 300 cm X 105 cm X 4 mm bh 84,500 87,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 160,000 165,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 95,000 105,000
NOK Jabes nok
. Kerpus Genteng bh 31,000 40,000
. Stel Besar bh 45,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 51,000 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 115,000 125,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 16,000 17,000
. 100cm X 100 cm X 4 mm bh 16,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,500 15,000
. 40 cm X 200 cm X 3 mm bh 14,000 14,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 75,000 80,000
uk. 122cm x 244cm x 4mm lbr 77,000 85,200
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 112,000
uk.122cm x 244cm x 6mm lbr 130,000 135,000
uk.122cm x 244cm x 8mm lbr 199,500 201,500
uk.122cm x 244cm x 10mm lbr 255,000 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 55,000 61,000
200 X 92 cm bh 60,000 66,000
250 X 92 cm bh 68,000 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 20,000 24,500
BJLS 0,20 lebar 55 cm m' 22,000 30,000
BJLS 0,28 lebar 55 cm m' 26,000 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 40,000 45,000
BJLS 0,20 panjang 180 cm lbr 42,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 72,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000 23,000,000
Balok/pesagen m3 20,000,000 20,500,000
2 KAMPER Papan m3 7,200,000 7,800,000
Balok/pesagen m3 6,100,000 7,500,000
3 KRUING Papan m3 6,250,000 8,800,000
Balok/pesagen m3 5,200,000 6,000,000
4 MERANTI Papan m3 4,800,000 5,700,000
Balok/pesagen m3 4,500,000 5,400,000
5 LANAN Papan m3 3,290,000 3,300,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 8,750,000 10,000,000
Balok/pesagen m3 9,000,000 9,850,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 35,000 38,000
20 X 20 cm m2 34,000 37,000
PC warna 30 X 30 cm m2 40,000 48,000
20 X 20 cm m2 39,500 45,000
Teraso 30 X 30 cm m2 52,000 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200 5,500
PC abu-abu 15 x 20 bh 5,100 6,000
3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
4 MOZAIK PORSELIN
10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000

5 Keramik 30 X 30 cm m2 56,000 78,000


20 X 20 cm m2 56,000 76,000
33 x 33 cm m2 58,000 78,000
25 x 25 cm m2 55,000 75,000
15 x 20 cm m2 57,000 75,000
2,250 2,500
6 Parquet Jati m2 210,000 310,000
7 Batu Paros m2 110,000 115,000
8 Batu Tempel Hitam m2 105,000 120,000
9 GRANITO 40 x 40 cm m2 220,000 250,000
30 x 30 cm m2 300,000 320,000
10 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 32,500 40,000
Ø 20 cm - 100 cm bh 42,000 50,000
Ø 30 cm - 100 cm bh 60,000 80,000
Ø 50 cm - 100 cm bh 115,000 160,000
Ø 60 cm - 100 cm bh 165,000 215,000
Ø 70 cm - 100 cm bh 240,000 265,000
U 10 cm - 100 cm bh 30,000 32,500
U 15 cm - 100 cm bh 35,000 40,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 20 cm - 100 cm bh 39,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 80,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 7,500 12,000
20 X 20 cm bh 12,500 16,000
25 X 25 cm bh 16,500 20,000
30 X 30 cm bh 19,000 22,000
15 X 25 cm bh 18,000 20,000
15 X 30 cm bh 20,000 22,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,000 10,750
besi beton prestress kg 13,000 14,500
besi beton ulir kg 13,000 13,200

2 BESI PLAT Besi Strip kg 13,500 14,000

3 BESI PROFIL Besi Profil kg 14,000 14,500


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 135,000 140,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 105,000 115,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 95,000 105,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 50,000 62,500 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 45,000 55,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 20,000 25,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 27,000 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000 15,000
Diameter 6 - 15 kg 14,000 16,000
Kawat Bronjong kg 12,500 14,000
5 BESI SIKU L 40 X 40 X 4 btg 133,500 139,200
L 50 X 50 X 5 btg 215,500 217,500
L 60 X 60 X 6 btg 312,000 355,000

6 KAWAT - Ikat beton/bendrat kg 17,000 18,000


- Harmonika 12 X 45 mm m2 20,000 35,000
- Harmonika 12 X 24 mm m2 18,000 21,000
- Harmonika 14 X 30 mm m2 15,000 20,000
- Harmonika 14 X 35 mm m2 21,000 27,500
- Kawat Nyamuk Nylon m2 18,000 25,000
- Kawat Kasa m2 14,000 18,000
- Saringan pasir m2 18,000 20,000
- Kawat loket m2 17,000 17,500
- Kawat duri rol 110,000 135,000
- Kawat bronjong kg 25,000 27,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 30,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 35,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 52,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 56,000 68,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 65,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 125,000 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 180,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 350,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m

2 Pipa Medium A Galvanis - SII


Pipa Medium Galvanis 0,50" btg 150,000 155,000 panjang 6 m
Pipa Medium Galvanis 0,75" btg 190,000 195,000 panjang 6 m
Pipa Medium Galvanis 1" btg 300,000 305,000 panjang 6 m
Pipa Medium Galvanis 1,25" btg 375,000 380,000 panjang 6 m
Pipa Medium Galvanis 1,50" btg 435,000 440,000 panjang 6 m
Pipa Medium Galvanis 2" btg 585,000 590,000 panjang 6 m
Pipa Medium Galvanis 2,50" btg 735,000 740,000 panjang 6 m
Pipa Medium Galvanis 3" btg 970,000 975,000 panjang 6 m
Pipa Medium Galvanis 4" btg 1,425,000 1,430,000 panjang 6 m
Pipa Medium Galvanis 5" btg 1,900,000 1,905,000 panjang 6 m
Pipa Medium Galvanis 6" btg - - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,200
30 X 60 lbr 13,200 14,200
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr 60,000 65,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 55,000 75,000
. 120 X 240 X 3 mm lbr 75,000 95,000
. 90 X 210 X 4 mm lbr 65,000 80,000
. 90 X 210 X 9 mm lbr 95,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 165,000 240,000
. 90 X 210 X 18 mm lbr 200,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 52,000 65,000
. 120 X 240 X 4 mm lbr 60,000 75,000
. 120 X 240 X 6 mm lbr 75,000 86,000
Multipleks
. 120 X 240 X 9 mm lbr 121,000 160,000
. 120 X 240 X 12 mm lbr 142,000 185,000
. 120 X 240 X 15 mm lbr 165,000 220,000
. 120 X 240 X 18 mm lbr 210,000 265,000
Formika ukuran pintu lbr 68,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 23,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,500 4,100
Batu Apung kg 38,000 55,000
Cat dasar kg 36,500 40,000
. Emco kg 62,000 68,000
. Yunior 66 (nippon paint) kg 60,000 71,000
- Koas bh 14,000 17,500
. Deculux kg 63,000 75,000
. Siralax ons 15,000 20,000
. Spiritus ltr 13,000 18,000
. Plitur jadi ltr 61,000 65,000

2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 26,000
Sintex 5 kg 115,000 125,000
Danabride 5 kg 110,000 122,000
Catylac 5 kg 125,000 130,000
Mowilex 2,50 kg 310,000 420,000

3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 55,000 69,000
Cat kg 40,000 45,000
Thinner A ltr 15,000 20,000
Minyak cat ltr 10,000 20,000
Thinner Super ltr 17,500 35,000
Residu (teer/aspal) drum 55,000 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 950,000 1,100,000
kapasitas 1100 liter. bh 1,625,000 1,700,000
Lem Aica Aibon kg 55,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 75,000 85,000
5 mm m2 90,000 95,000
2 ES KABUR 3 mm m2 75,000 85,000
5 mm m2 88,000 95,000
3 RAY BAND 3 mm m2 75,000 85,000
5 mm m2 85,000 92,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 4,200 5,000

SPLN LMK 1 X 2 1/2 mm2 m' 4,600 5,200

. 1X4 mm2 m' 6,250 6,600

1X6 mm2 m' 9,100 10,100

NYY :. 2 X 1 1/2 mm2 m' 9,450 9,600

PRIMA 2 X 2 1/2 mm2 m' 15,200 15,500

. 2X4 mm2 m' 27,500 28,000

2X6 mm2 m' 36,000 37,000

3 X 1 1/2 mm2 m' 13,500 14,000

3 X 2 1/2 mm2 m' 20,000 21,000

3X4 mm2 m' 34,500 36,500

3X6 mm2 m' 50,000 53,000

NYM :. 2 X 1 1/2 mm2 m' 7,000 8,000

PRIMA 2 X 2 1/2 mm2 m' 10,900 11,500

. 2X4 mm2 m' 21,000 23,000

3 X 1 1/2 mm2 m' 12,500 14,000

3 X 2 1/2 mm2 m' 19,000 22,000

3X4 mm2 m' 30,000 35,000

3X6 mm2 m' 43,000 48,000

2 SKAKELAR
Out bauw . Seri bh 17,500 21,000

. Engkel bh 15,000 16,000

In bauw . Seri bh 15,000 16,500

. Engkel bh 11,000 15,000

3 FUSE BOX (SEKERING KASA)


1 group bh 125,000 135,000

2 group bh 230,000 245,000

3 group bh 350,000 360,000

4 STEKER - Biasa bh 10,000 12,000

Arde bh 15,000 16,000

T Biasa bh 12,500 13,000

T dengan Arde bh 17,000 17,500


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
5 FITING Flaon bh 15,500 17,000

Gantung bh 12,500 15,000

Kap bh 12,500 16,000

Kombinasi bh 25,000 27,500

6 STOP KONTAK - Arde Outbow putih bh 12,500 15,000

Arde Outbow hitam bh 20,000 25,000

Arde IB bh 21,000 26,000

Arde Putar bh 31,000 42,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 100,000 115,000
2 X slag bh 165,000 175,000
Yale : 1 X slag bh 90,000 95,000
2 X slag bh 110,000 155,000
Kuda : 1 X slag bh 70,000 85,000
2 X slag bh 110,000 125,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 15,000 25,000
Kupu-kupu biasa bh 4,000 6,000
Nylon kupu-kupu bh 6,000 9,000
Espagnoled - dalam negeri bh 40,000 50,000
Grendel Tanam luar negeri bh 11,000 13,000
Grendel biasa bh 8,000 10,000
Kait Angin bh 15,000 20,000
Door Stop bh 275,000 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,600,000 1,850,000
2 KLOSET JONGKOK bh 140,000 150,000
3 WASTAFEL PEDESTAL bh 950,000 1,050,000
4 WASTAFEL MEJA OVAL bh 750,000 950,000
5 WASTAFEL GANTUNG BULAT bh 300,000 325,000
6 WASTAFEL GANTUNG SUDUT bh 250,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 240,000 275,000
8 WASTAFEL BAK CUCI bh 150,000 165,000
9 TEMPAT SABUN GANTUNG bh 45,000 55,000
10 TEMPAT SABUN TANAM bh 22,500 25,000
11 LAIN - LAIN
Kran Air bh 25,000 45,000
Seal tape bh 3,500 4,500
Floor drain bh 35,000 40,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 15,000 17,500
2 PAKU - payung kg 20,000 26,000
3 PAKU - sekrup kg 6,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 7,000 7,200

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 310,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 80,000 85,000
Merah/hitam m2 85,000 90,000
2 HOLLAND Abu-abu m2 80,000 85,000
Merah/hitam m2 85,000 90,000
3 UNIDECOR Abu-abu m2 80,000 85,000
Merah/hitam m2 85,000 90,000
4 UNI Abu-abu m2 80,000 85,000
Merah/hitam m2 85,000 90,000
5 TRIHEX Abu-abu m2 80,000 85,000
Merah/hitam m2 85,000 90,000
6 OLYMPIA HEXA Abu-abu m2 80,000 85,000
7 HEXAGONAL Abu-abu m2 85,000 90,000
Merah/hitam m2 80,000 85,000
8 CASTLE Abu-abu m2 85,000 90,000
9 TRAPEZ Abu-abu m2 80,000 85,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 80,000 85,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 4,800 5,500
13 KANSTEEN m' 25,000 30,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 60,000
2 Sliding Pintu J4 bh 200,000 235,000
3 Naco per Daun bh 35,000 37,500
4 Rolling door Besi m2 325,000 335,000
Rolling door Almunium m2 275,000 290,000
5 Awning Almunium m2 225,000 250,000
6 Kusen Almunium 4" Putih m' 85,000 95,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,380,000 1,475,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,050,000

Hotmix Tebal = 4 Cm m2 65,000 67,500


Hotmix Tebal = 5 Cm m2 80,000 82,000
Hotmix Tebal = 6 Cm m2 95,000 97,000
Hotmix Tebal = 7 Cm m2 110,000 115,000
Binder Course ton 1,300,000 1,325,000
Wearing Course ton 1,300,000 1,400,000
Hot Roller Sheet ton 1,150,000 1,250,000
Sand Sheet ton 1,200,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,500,000
Cold Mix ton 1,800,000 1,850,000
Prime / Tack Coard RC liter 7,200 8,000
Prime Coat MC liter 7,200 8,000
Prime / Tack Coat Emulsi liter 7,200 8,000
10 K A C A
Cermin tebal 5 mm m2 275,000 300,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 275,000 300,000


Pagar BRC 120 A2 /lb 350,000 375,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 400,000 425,000
Sunscreen Allumunim m2 350,000 400,000
Allumunium Foil m2 12,000 15,000
Soda api kg 13,000 15,000
Sabun kg 12,500 15,000
Air m3 15,000 20,000
Koas Alang-alang ikat 1,250 2,000
Solar (Industri) ltr 8,500 8,800
Premium (Industri) ltr 7,800 8,100
Pelumas ltr 39,500 47,000
Vynil 30x30 cm bh 6,200 6,500
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI V 2018


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 580,459.00 678,848.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 137,555.00 170,170.00

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,863,070.00 2,121,707.50

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,444,300.00 1,665,950.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,361,525.00 1,581,415.00

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,650,000.00 1,911,910.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 13,750.00 15,400.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 339,132.20 383,173.12

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 489,720.00 626,230.00

10 A.2.2.1.12 Pembuatan Jalan Sementara m2 159,115.00 188,100.00

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,173,315.00 1,327,315.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 553,657.50 627,357.50

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 52,123.50 57,057.00


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 300,393.50 333,676.75
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 64,625.00 73,150.00

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 79,200.00 89,595.00

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 93,995.00 106,282.00

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 86,020.00 97,372.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 130,350.00 147,510.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 103,950.00 117,645.00

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 4,675.00 5,280.00

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 28,325.00 32,065.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 15,583.33 17,600.00
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 46,750.00 52,800.00

11 A.2.3.1.11 Urugan Pasir m3 237,050.00 332,860.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 425,353.50 473,297.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 60,225.00 63,360.00
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 260,975.00 290,400.00

415837925.xls 175/14 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 975,122.50 1,094,775.00

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 940,060.00 1,059,685.00

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 915,706.00 1,035,298.00

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 898,606.50 1,018,182.00

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 875,116.00 994,653.00

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 773,960.00 875,600.00
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 855,448.00 969,386.00
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 836,709.50 951,247.00
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 533,346.00 633,138.00

Pasang Pondasi Siklop, 60% Beton Campuran 1PC :


10 A.3.2.1.10 m3 2,431,462.00 2,639,109.00
2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 911,482.00 999,933.00

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 971,113.00 1,093,880.07
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 998,211.70 1,122,454.75
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,019,329.67 1,144,480.07
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 909,567.59 1,026,998.06
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,044,305.78 1,170,804.12
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,068,295.96 1,195,671.10
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,086,252.44 1,214,937.69
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,098,311.70 1,227,049.04
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,119,448.00 1,248,359.36
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,125,830.04 1,254,729.75
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,198,705.65 1,333,892.30
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,207,255.09 1,342,474.92
(12±2)cm, w/c = 0,48

415837925.xls 175/15 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,268.20 14,317.05

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 16,230.50 18,092.80

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,646.20 31,515.00

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 170,016.00 188,903.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 181,016.00 201,003.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 371,723.00 428,274.00

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 388,883.00 448,074.00

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 464,123.00 533,874.00

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 423,423.00 487,674.00

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 349,228.00 403,524.00

23 A.4.1.1.27 Memasang Jembatan Cor m2 98,615.00 110,066.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 82,071.00 88,610.50

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 104,995.00 113,833.50

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 83,555.02 93,676.21
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 104,474.03 117,128.26
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 122,555.03 137,368.31
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 156,697.29 175,678.64
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 117,352.02 129,548.10
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 39,701.00 44,839.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 35,126.00 39,489.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 6,185.00 6,945.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 10,025.00 11,265.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 8,105.00 9,105.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 56,298.00 56,610.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 57,909.50 58,235.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 52,063.00 52,350.00
Kolom Pracetak

415837925.xls 175/16 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 575,444.10 600,433.68

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 566,159.00 590,466.80

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 814,241.45 854,411.36

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 150,721.45 157,831.96

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 123,490.95 126,938.46

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 123,490.95 126,938.46

20 A.4.1.2.20 Bahan Grout Campuran m3 3,415,775.00 3,687,200.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,059,100.00 3,366,550.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 51,375.50 56,633.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 112,530.00 129,470.00

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 44,649.00 49,852.00

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 29,986.00 32,037.50

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 24,546.50 25,839.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 99,066.00 115,687.00

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 864,930.00 906,422.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,275.13 2,652.32

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 224,090.46 255,478.74

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 597,080.00 635,866.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 530,024.00 567,930.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 485,320.00 550,924.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 507,100.00 547,250.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 116,592.30 130,478.70

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 501,055.50 559,495.20

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 468,534.00 526,878.00

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 176,165.00 189,948.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 501,127.02 555,250.11

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 95,526.96 111,915.40

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 126,280.00 138,886.00

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 186,092.50 217,126.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 112,805.00 122,573.00
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 142,065.00 154,748.00
Modul 60x60 cm dinding plafond

415837925.xls 175/17 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 211,522.30 231,071.78
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 236,651.80 257,530.35
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 248,875.00 273,157.50
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 239,921.00 264,288.75
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 232,870.00 257,006.75
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 230,725.00 255,167.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 233,178.00 258,626.50
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 221,843.05 245,346.20
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 120,356.50 132,222.75
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 115,507.70 127,243.05
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 113,074.50 124,833.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 111,565.30 123,345.20
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 111,305.70 123,252.80
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 109,450.00 121,357.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 111,980.00 123,942.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 100,397.00 110,209.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran


15 A.4.4.1.15 m2 101,662.00 112,035.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


16 A.4.4.1.16 m2 395,364.20 450,607.30
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 403,277.60 460,849.40
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 311,447.40 354,102.10
3PP

415837925.xls 175/18 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 317,042.00 361,383.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 251,609.60 288,996.40
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 256,259.30 294,931.45
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 143,088.00 154,319.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 266,333.54 291,571.56
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 269,465.24 292,711.71
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 68,193.84 75,294.56

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 63,191.04 70,243.36

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 61,268.46 68,367.64

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 59,756.40 66,831.60

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 59,171.64 66,309.76

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 58,588.86 65,745.24

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 58,354.56 65,545.04

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 58,120.26 65,344.84

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 58,136.10 64,882.40
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 57,882.00 64,922.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 53,740.50 59,994.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 54,719.50 61,314.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 84,590.22 94,035.48

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 63,169.80 70,323.20

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 79,895.20 89,350.80

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 79,231.02 88,790.68

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 78,338.48 87,902.32

415837925.xls 175/19 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 75,559.00 84,491.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 37,342.14 41,851.26

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 58,789.50 65,367.50
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 94,550.50 104,681.50
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 94,550.50 104,681.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 45,366.20 50,641.80

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 25,821.18 28,643.12
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 12,292.50 13,623.50
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 55,719.40 62,074.10
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 33,192.50 36,891.25

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 41,813.20 45,681.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 35,695.00 39,393.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 105,928.00 117,172.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 107,437.00 118,992.50

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 131,360.50 155,305.00

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 133,452.00 155,050.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 347,281.00 397,138.50

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 65,294.90 75,466.60

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 37,255.90 40,948.60

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 219,487.40 272,732.35

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 224,932.40 280,157.35
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 218,403.29 265,468.68

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 214,724.50 263,031.00

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 215,484.50 261,547.00

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 413,578.00 461,620.50
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 35,765.40 41,168.60

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 82,124.90 88,221.10

415837925.xls 175/20 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 79,792.90 87,055.10

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 689,627.40 713,810.35

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 200,387.00 214,038.00

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 381,260.00 515,680.00

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 245,518.66 277,972.82

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 240,735.00 295,927.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 235,554.00 283,266.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 240,735.00 295,927.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 236,764.00 284,894.50


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 775,735.52 809,502.22

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 261,855.00 282,988.75
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 145,517.90 158,169.00

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 115,384.50 124,888.50

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 46,002.00 57,310.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 167,458.50 184,198.30

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 227,106.00 247,321.80


32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 179,679.50 196,419.30

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 233,216.50 253,432.30

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 30,602.00 33,060.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 101,937.00 110,192.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 105,501.00 114,383.50
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 90,585.00 99,687.50
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 45,705.00 54,340.00
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati, tebal


6 A.4.5.1.6 m2 526,845.00 562,292.50
6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 40,469.00 45,492.70
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 211,365.00 232,430.00
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 15,994.00 17,440.50

415837925.xls 175/21 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 85,250.00 96,145.50

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 138,935.50 144,336.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 123,040.50 130,641.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 100,683.00 110,451.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 113,058.00 123,926.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 116,908.00 127,006.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 103,493.50 115,962.00


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 62,606.50 70,614.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 64,438.00 72,776.00
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 64,768.00 73,436.00
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 72,028.00 76,274.00
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 55,060.50 58,619.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 57,178.00 62,546.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 53,988.00 59,972.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 55,907.50 60,467.00
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 59,488.00 66,484.00
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 64,449.00 67,859.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 67,804.00 71,324.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 64,636.00 68,684.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 65,648.00 69,861.00
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 69,553.00 73,403.00
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 102,355.00 118,057.50

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 218,603.00 244,293.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 88,660.00 103,950.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 108,075.00 115,214.00

415837925.xls 175/22 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 122,001.00 131,901.00

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 122,567.50 134,651.00

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 64,570.00 72,440.50

29 A.4.5.2.38 Pemasangan Nok Sirap m' 53,377.50 59,906.00

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 37,906.00 43,153.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 30,437.00 34,430.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 32,945.00 38,753.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 27,298,975.00 28,250,612.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 10,713,175.00 12,859,962.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 470,910.00 514,200.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 470,910.00 514,200.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 755,287.50 829,950.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 544,445.00 601,040.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 1,993,475.00 2,115,850.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 583,330.00 654,032.50
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 631,862.00 707,745.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 1,779,800.00 1,881,467.50
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,031,360.00 1,116,197.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 680,680.00 758,950.50
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 9,447,350.00 11,356,400.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 29,648,410.00 30,652,655.00
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 8,703,970.00 10,529,310.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 142,681.00 172,837.50
Klas II

415837925.xls 175/23 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 166,837.00 202,537.50
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 121,792.00 146,740.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 162,239.00 192,610.00
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 166,078.00 197,807.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 295,130.00 310,860.00
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 120,065.00 131,037.50
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 256,080.00 306,795.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 325,270.00 394,795.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 332,255.00 402,187.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 434,720.00 471,735.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 38,203.00 46,139.50
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 121,763.84 141,542.50
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 175,835.00 231,110.00

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 152,542.50 163,680.00

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 174,542.50 229,680.00

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 26,152.50 31,515.00

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 17,435.00 21,010.00

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 48,125.00 62,650.50

7 A.4.6.2.9 Pemasangan Kait Angin Buah 36,107.50 43,675.50

8 A.4.6.2.10 Pasang Door Closer Buah 365,200.00 454,327.50

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 33,880.00 38,731.00

10 A.4.6.2.13 Pemasangan Door Stop Buah 315,040.00 398,865.50

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 295,240.00 341,693.00

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 45,105.50 51,169.80

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 109,560.00 123,648.25

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 127,710.00 135,748.25


15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 351,560.00 383,798.25

415837925.xls 175/24 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp

XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 13,420.00 15,213.00
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 13,392.50 15,213.00
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 13,942.50 15,818.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 42,196.00 49,830.00
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 57,926.00 67,683.00
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 34,072.50 36,327.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 54,562.20 59,488.00

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 9,968.75 11,231.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 38,071.00 42,141.00

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 19,973.80 22,947.10
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 13,675.20 15,514.40
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 8,032.20 8,936.40

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 14,732.85 16,777.20

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 6,674.25 7,705.50
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 83,545.00 95,012.50

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 26,422.00 30,211.50

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 52,717.50 59,785.00
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,270,521.00 2,612,192.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 603,075.00 660,770.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 721,325.00 782,210.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 583,027.50 637,257.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,083,967.50 1,159,900.50


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,161,600.00 1,285,350.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,471,679.27 1,638,538.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,234,908.17 6,925,402.59

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 341,605.00 384,230.00

10 A.5.1.1.14 Pemasangan Floor Drain buah 51,535.00 58,410.00

415837925.xls 175/25 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 432,189.03 479,003.01
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 634,963.03 704,316.01
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 772,607.85 853,157.46
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 60,544.00 63,944.83

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 75,524.63 102,532.38

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 71,910.67 75,311.50

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 103,169.00 106,569.83

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 137,010.50 141,852.33

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 247,065.50 252,776.33

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 451,665.50 458,086.75

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 22,121.00 24,117.50

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 24,678.50 26,248.75

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 29,367.25 33,495.00

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 31,192.33 36,318.33


25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 33,749.83 46,832.50

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 58,384.33 78,002.83

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 61,336.00 90,896.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 78,969.00 87,747.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 37,526.50 43,230.00
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 113,038.20 131,747.55

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 579,243.50 624,976.00

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 338,360.00 378,708.00

2 A.8.4.6.2 Pemasangan MCB buah 459,140.00 503,448.00

415837925.xls 175/26 hspk


DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI V 2018


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 580,459.00 678,848.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 137,555.00 170,170.00

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,863,070.00 2,121,707.50

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,444,300.00 1,665,950.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,361,525.00 1,581,415.00

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,650,000.00 1,911,910.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 13,750.00 15,400.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 339,132.20 383,173.12

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 489,720.00 626,230.00

10 A.2.2.1.12 Pembuatan Jalan Sementara m2 159,115.00 188,100.00

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,173,315.00 1,327,315.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 553,657.50 627,357.50

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 52,123.50 57,057.00


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 300,393.50 333,676.75
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 64,625.00 73,150.00

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 79,200.00 89,595.00

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 93,995.00 106,282.00

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 86,020.00 97,372.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 130,350.00 147,510.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 103,950.00 117,645.00

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 4,675.00 5,280.00

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 28,325.00 32,065.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 15,583.33 17,600.00
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 46,750.00 52,800.00

11 A.2.3.1.11 Urugan Pasir m3 237,050.00 332,860.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 425,353.50 473,297.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 60,225.00 63,360.00
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 260,975.00 290,400.00

415837925.xls 175/27 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 975,122.50 1,094,775.00

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 940,060.00 1,059,685.00

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 915,706.00 1,035,298.00

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 898,606.50 1,018,182.00

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 875,116.00 994,653.00

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 773,960.00 875,600.00
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 855,448.00 969,386.00
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 836,709.50 951,247.00
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 533,346.00 633,138.00

Pasang Pondasi Siklop, 60% Beton Campuran 1PC :


10 A.3.2.1.10 m3 2,431,462.00 2,639,109.00
2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 911,482.00 999,933.00

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 971,113.00 1,093,880.07
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 998,211.70 1,122,454.75
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,019,329.67 1,144,480.07
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 909,567.59 1,026,998.06
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,044,305.78 1,170,804.12
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,068,295.96 1,195,671.10
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,086,252.44 1,214,937.69
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,098,311.70 1,227,049.04
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,119,448.00 1,248,359.36
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,125,830.04 1,254,729.75
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,198,705.65 1,333,892.30
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,207,255.09 1,342,474.92
(12±2)cm, w/c = 0,48

415837925.xls 175/28 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,268.20 14,317.05

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 16,230.50 18,092.80

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,646.20 31,515.00

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 170,016.00 188,903.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 181,016.00 201,003.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 371,723.00 428,274.00

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 388,883.00 448,074.00

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 464,123.00 533,874.00

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 423,423.00 487,674.00

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 349,228.00 403,524.00

23 A.4.1.1.27 Memasang Jembatan Cor m2 98,615.00 110,066.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 82,071.00 88,610.50

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 104,995.00 113,833.50

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 83,555.02 93,676.21
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 104,474.03 117,128.26
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 122,555.03 137,368.31
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 156,697.29 175,678.64
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 117,352.02 129,548.10
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 39,701.00 44,839.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 35,126.00 39,489.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 6,185.00 6,945.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 10,025.00 11,265.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 8,105.00 9,105.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 56,298.00 56,610.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 57,909.50 58,235.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 52,063.00 52,350.00
Kolom Pracetak

415837925.xls 175/29 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 575,444.10 600,433.68

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 566,159.00 590,466.80

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 814,241.45 854,411.36

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 150,721.45 157,831.96

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 123,490.95 126,938.46

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 123,490.95 126,938.46

20 A.4.1.2.20 Bahan Grout Campuran m3 3,415,775.00 3,687,200.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,059,100.00 3,366,550.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 51,375.50 56,633.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 112,530.00 129,470.00

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 44,649.00 49,852.00

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 29,986.00 32,037.50

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 24,546.50 25,839.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 99,066.00 115,687.00

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 864,930.00 906,422.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,275.13 2,652.32

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 224,090.46 255,478.74

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 597,080.00 635,866.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 530,024.00 567,930.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 485,320.00 550,924.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 507,100.00 547,250.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 116,592.30 130,478.70

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 501,055.50 559,495.20

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 468,534.00 526,878.00

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 176,165.00 189,948.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 501,127.02 555,250.11

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 95,526.96 111,915.40

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 126,280.00 138,886.00

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 186,092.50 217,126.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 112,805.00 122,573.00
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 142,065.00 154,748.00
Modul 60x60 cm dinding plafond

415837925.xls 175/30 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 211,522.30 231,071.78
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 236,651.80 257,530.35
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 248,875.00 273,157.50
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 239,921.00 264,288.75
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 232,870.00 257,006.75
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 230,725.00 255,167.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 233,178.00 258,626.50
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 221,843.05 245,346.20
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 120,356.50 132,222.75
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 115,507.70 127,243.05
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 113,074.50 124,833.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 111,565.30 123,345.20
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 111,305.70 123,252.80
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 109,450.00 121,357.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 111,980.00 123,942.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 100,397.00 110,209.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran


15 A.4.4.1.15 m2 101,662.00 112,035.00
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


16 A.4.4.1.16 m2 395,364.20 450,607.30
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 403,277.60 460,849.40
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 311,447.40 354,102.10
3PP

415837925.xls 175/31 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 317,042.00 361,383.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 251,609.60 288,996.40
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 256,259.30 294,931.45
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 143,088.00 154,319.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 266,333.54 291,571.56
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 269,465.24 292,711.71
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 68,193.84 75,294.56

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 63,191.04 70,243.36

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 61,268.46 68,367.64

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 59,756.40 66,831.60

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 59,171.64 66,309.76

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 58,588.86 65,745.24

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 58,354.56 65,545.04

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 58,120.26 65,344.84

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 58,136.10 64,882.40
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 57,882.00 64,922.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 53,740.50 59,994.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 54,719.50 61,314.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 84,590.22 94,035.48

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 63,169.80 70,323.20

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 79,895.20 89,350.80

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 79,231.02 88,790.68

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 78,338.48 87,902.32

415837925.xls 175/32 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 75,559.00 84,491.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 37,342.14 41,851.26

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 58,789.50 65,367.50
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 94,550.50 104,681.50
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 94,550.50 104,681.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 45,366.20 50,641.80

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 25,821.18 28,643.12
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 12,292.50 13,623.50
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 55,719.40 62,074.10
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 33,192.50 36,891.25

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 41,813.20 45,681.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 35,695.00 39,393.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 105,928.00 117,172.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 107,437.00 118,992.50

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 131,360.50 155,305.00

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 133,452.00 155,050.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 347,281.00 397,138.50

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 65,294.90 75,466.60

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 37,255.90 40,948.60

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 219,487.40 272,732.35

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 224,932.40 280,157.35
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 218,403.29 265,468.68

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 214,724.50 263,031.00

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 215,484.50 261,547.00

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 413,578.00 461,620.50
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 35,765.40 41,168.60

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 82,124.90 88,221.10

415837925.xls 175/33 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 79,792.90 87,055.10

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 689,627.40 713,810.35

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 200,387.00 214,038.00

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 381,260.00 515,680.00

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 245,518.66 277,972.82

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 240,735.00 295,927.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 235,554.00 283,266.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 240,735.00 295,927.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 236,764.00 284,894.50


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 775,735.52 809,502.22

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 261,855.00 282,988.75
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 145,517.90 158,169.00

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 115,384.50 124,888.50

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 46,002.00 57,310.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 167,458.50 184,198.30

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 227,106.00 247,321.80


32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 179,679.50 196,419.30

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 233,216.50 253,432.30

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 30,602.00 33,060.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 101,937.00 110,192.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 105,501.00 114,383.50
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 90,585.00 99,687.50
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 45,705.00 54,340.00
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati, tebal


6 A.4.5.1.6 m2 526,845.00 562,292.50
6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 40,469.00 45,492.70
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 211,365.00 232,430.00
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 15,994.00 17,440.50

415837925.xls 175/34 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 85,250.00 96,145.50

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 138,935.50 144,336.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 123,040.50 130,641.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 100,683.00 110,451.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 113,058.00 123,926.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 116,908.00 127,006.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 103,493.50 115,962.00


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 62,606.50 70,614.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 64,438.00 72,776.00
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 64,768.00 73,436.00
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 72,028.00 76,274.00
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 55,060.50 58,619.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 57,178.00 62,546.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 53,988.00 59,972.00
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 55,907.50 60,467.00
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 59,488.00 66,484.00
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 64,449.00 67,859.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 67,804.00 71,324.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 64,636.00 68,684.00
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 65,648.00 69,861.00
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 69,553.00 73,403.00
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 102,355.00 118,057.50

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 218,603.00 244,293.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 88,660.00 103,950.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 108,075.00 115,214.00

415837925.xls 175/35 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 122,001.00 131,901.00

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 122,567.50 134,651.00

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 64,570.00 72,440.50

29 A.4.5.2.38 Pemasangan Nok Sirap m' 53,377.50 59,906.00

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 37,906.00 43,153.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 30,437.00 34,430.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 32,945.00 38,753.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 27,298,975.00 28,250,612.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 10,713,175.00 12,859,962.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 470,910.00 514,200.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 470,910.00 514,200.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 755,287.50 829,950.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 544,445.00 601,040.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 1,993,475.00 2,115,850.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 583,330.00 654,032.50
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 631,862.00 707,745.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 1,779,800.00 1,881,467.50
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,031,360.00 1,116,197.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 680,680.00 758,950.50
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 9,447,350.00 11,356,400.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 29,648,410.00 30,652,655.00
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 8,703,970.00 10,529,310.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 142,681.00 172,837.50
Klas II

415837925.xls 175/36 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 166,837.00 202,537.50
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 121,792.00 146,740.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 162,239.00 192,610.00
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 166,078.00 197,807.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 295,130.00 310,860.00
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 120,065.00 131,037.50
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 256,080.00 306,795.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 325,270.00 394,795.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 332,255.00 402,187.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 434,720.00 471,735.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 38,203.00 46,139.50
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 121,763.84 141,542.50
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 175,835.00 231,110.00

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 152,542.50 163,680.00

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 174,542.50 229,680.00

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 26,152.50 31,515.00

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 17,435.00 21,010.00

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 48,125.00 62,650.50

7 A.4.6.2.9 Pemasangan Kait Angin Buah 36,107.50 43,675.50

8 A.4.6.2.10 Pasang Door Closer Buah 365,200.00 454,327.50

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 33,880.00 38,731.00

10 A.4.6.2.13 Pemasangan Door Stop Buah 315,040.00 398,865.50

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 295,240.00 341,693.00

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 45,105.50 51,169.80

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 109,560.00 123,648.25

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 127,710.00 135,748.25


15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 351,560.00 383,798.25

415837925.xls 175/37 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp

XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 13,420.00 15,213.00
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 13,392.50 15,213.00
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 13,942.50 15,818.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 42,196.00 49,830.00
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 57,926.00 67,683.00
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 34,072.50 36,327.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 54,562.20 59,488.00

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 9,968.75 11,231.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 38,071.00 42,141.00

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 19,973.80 22,947.10
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 13,675.20 15,514.40
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 8,032.20 8,936.40

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 14,732.85 16,777.20

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 6,674.25 7,705.50
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 83,545.00 95,012.50

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 26,422.00 30,211.50

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 52,717.50 59,785.00
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,270,521.00 2,612,192.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 603,075.00 660,770.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 721,325.00 782,210.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 583,027.50 637,257.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,083,967.50 1,159,900.50


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,161,600.00 1,285,350.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,471,679.27 1,638,538.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,234,908.17 6,925,402.59

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 341,605.00 384,230.00

10 A.5.1.1.14 Pemasangan Floor Drain buah 51,535.00 58,410.00

415837925.xls 175/38 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 432,189.03 479,003.01
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 634,963.03 704,316.01
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 772,607.85 853,157.46
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 60,544.00 63,944.83

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 75,524.63 102,532.38

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 71,910.67 75,311.50

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 103,169.00 106,569.83

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 137,010.50 141,852.33

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 247,065.50 252,776.33

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 451,665.50 458,086.75

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 22,121.00 24,117.50

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 24,678.50 26,248.75

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 29,367.25 33,495.00

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 31,192.33 36,318.33


25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 33,749.83 46,832.50

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 58,384.33 78,002.83

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 61,336.00 90,896.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 78,969.00 87,747.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 37,526.50 43,230.00
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 113,038.20 131,747.55

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 579,243.50 624,976.00

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 338,360.00 378,708.00

2 A.8.4.6.2 Pemasangan MCB buah 459,140.00 503,448.00

HARGA SATUAN PEKERJAAN


XVI A.8.4.1
PEMASANGAN PIPA

1 A.8.4.1.1 Pemasangan Pipa PVC Ø 63 mm m' 14,931.95 17,344.25

2 A.8.4.1.2 Pemasangan Pipa PVC Ø 90 mm m' 21,994.50 25,037.10

3 A.8.4.1.3 Pemasangan Pipa PVC Ø 110 mm m' 25,696.00 31,702.00

4 A.8.4.1.4 Pemasangan Pipa PVC Ø 150 mm m' 30,002.50 38,157.90

5 A.8.4.1.5 Pemasangan Pipa PVC Ø 200 mm m' 44,374.00 60,134.80

6 A.8.4.1.6 Pemasangan Pipa PVC Ø 250 mm m' 59,730.00 93,189.80

7 A.8.4.1.7 Pemasangan Pipa PVC Ø 300 mm m' 92,746.50 125,504.50

415837925.xls 175/39 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
8 A.8.4.1.8 Pemasangan Pipa PVC Ø 400 mm m' 176,374.00 241,120.00

9 A.8.4.1.9 Pemasangan Pipa PVC Ø 450 mm m' 346,170.00 399,421.00

10 A.8.4.1.10 Pemasangan Pipa PVC Ø 500 mm m' 427,317.00 447,330.40

11 A.8.4.1.11 Pemasangan Pipa PVC Ø 600 mm m' 498,349.50 537,487.50

12 A.8.4.1.12 Pemasangan Pipa PVC Ø 800 mm m' 706,095.50 762,624.50

13 A.8.4.1.13 Pemasangan Pipa PVC Ø 900 mm m' 936,886.50 994,728.90

14 A.8.4.1.14 Pemasangan Pipa PVC Ø 1.000 mm m' 1,082,537.50 1,138,547.30

15 A.8.4.1.15 Pemasangan Pipa PVC Ø 1.100 mm m' 1,189,589.50 1,282,257.90

16 A.8.4.1.16 Pemasangan Pipa PVC Ø 1.200 mm m' 1,274,630.50 1,370,955.30

17 A.8.4.1.17 Pemasangan Pipa HDPE Ø 63 mm m' 32,703.00 38,849.80

18 A.8.4.1.18 Pemasangan Pipa HDPE Ø 100 mm m' 44,539.00 50,784.80

19 A.8.4.1.19 Pemasangan Pipa HDPE Ø 125 mm m' 56,375.00 62,719.80

20 A.8.4.1.20 Pemasangan Pipa HDPE Ø 150 mm m' 80,723.50 87,354.30

21 A.8.4.1.21 Pemasangan Pipa HDPE Ø 200 mm m' 136,053.50 148,888.30

22 A.8.4.1.22 Pemasangan Pipa HDPE Ø 250 mm m' 168,366.00 176,301.40

23 A.8.4.1.23 Pemasangan Pipa HDPE Ø 300 mm m' 201,492.50 215,627.50

24 A.8.4.1.24 Pemasangan Pipa HDPE Ø 400 mm m' 263,939.50 280,377.90

25 A.8.4.1.25 Pemasangan Pipa HDPE Ø 450 mm m' 318,587.50 336,352.50

26 A.8.4.1.26 Pemasangan Pipa HDPE Ø 500 mm m' 395,785.50 425,949.70

27 A.8.4.1.27 Pemasangan Pipa HDPE Ø 600 mm m' 550,979.00 582,663.40

28 A.8.4.1.28 Pemasangan Pipa HDPE Ø 800 mm m' 851,372.50 895,841.10

29 A.8.4.1.29 Pemasangan Pipa HDPE Ø 900 mm m' 1,031,932.00 1,112,689.60

30 A.8.4.1.30 Pemasangan Pipa HDPE Ø 1.000 mm m' 1,243,885.50 1,302,995.10

31 A.8.4.1.31 Pemasangan Pipa HDPE Ø 1.100 mm m' 1,378,250.50 1,467,900.50

32 A.8.4.1.32 Pemasangan Pipa HDPE Ø 1.200 mm m' 1,572,851.50 1,673,048.30

33 A.8.4.1.33 Pemasangan Pipa GIP Ø 63 mm m' 66,676.50 75,487.50

34 A.8.4.1.34 Pemasangan Pipa GIP Ø 100 mm m' 79,383.33 92,840.00

35 A.8.4.1.35 Pemasangan Pipa GIP Ø 125 mm m' 90,068.00 106,205.00

36 A.8.4.1.36 Pemasangan Pipa GIP Ø 150 mm m' 104,960.17 123,036.83

37 A.8.4.1.37 Pemasangan Pipa GIP Ø 200 mm m' 157,311.00 183,241.67

38 A.8.4.1.38 Pemasangan Pipa GIP Ø 250 mm m' 187,880.00 219,255.67

39 A.8.4.1.39 Pemasangan Pipa GIP Ø 300 mm m' 216,650.50 246,346.83

40 A.8.4.1.40 Pemasangan Pipa GIP Ø 400 mm m' 279,293.67 304,289.33

41 A.8.4.1.41 Pemasangan Pipa GIP Ø 450 mm m' 318,114.50 352,918.50

42 A.8.4.1.42 Pemasangan Pipa GIP Ø 500 mm m' 368,170.00 405,031.00

43 A.8.4.1.43 Pemasangan Pipa GIP Ø 600 mm m' 369,495.50 403,859.50

415837925.xls 175/40 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
44 A.8.4.1.44 Pemasangan Pipa GIP Ø 800 mm m' 559,141.00 611,094.00

45 A.8.4.1.45 Pemasangan Pipa GIP Ø 900 mm m' 635,321.50 703,488.50

46 A.8.4.1.46 Pemasangan Pipa GIP Ø 1.000 mm m' 710,319.50 772,557.50

47 A.8.4.1.47 Pemasangan Pipa GIP Ø 1.100 mm m' 774,400.00 841,720.00

48 A.8.4.1.48 Pemasangan Pipa GIP Ø 1.200 mm m' 849,398.00 921,789.00

49 A.8.4.1.49 Pemasangan Pipa DCI Ø 100 mm m' 83,891.50 96,471.10

50 A.8.4.1.50 Pemasangan Pipa DCI Ø 125 mm m' 106,986.00 120,390.60

51 A.8.4.1.51 Pemasangan Pipa DCI Ø 150 mm m' 136,554.00 156,404.60

52 A.8.4.1.52 Pemasangan Pipa DCI Ø 200 mm m' 186,175.00 209,479.60

53 A.8.4.1.53 Pemasangan Pipa DCI Ø 250 mm m' 219,312.50 244,018.50

54 A.8.4.1.54 Pemasangan Pipa DCI Ø 300 mm m' 244,101.00 269,172.20

55 A.8.4.1.55 Pemasangan Pipa DCI Ø 400 mm m' 366,624.50 401,441.70

56 A.8.4.1.56 Pemasangan Pipa DCI Ø 450 mm m' 430,380.50 464,412.30

57 A.8.4.1.57 Pemasangan Pipa DCI Ø 500 mm m' 489,786.00 533,527.50

58 A.8.4.1.58 Pemasangan Pipa DCI Ø 600 mm m' 550,676.50 612,253.40

59 A.8.4.1.59 Pemasangan Pipa DCI Ø 800 mm m' 835,774.50 916,553.00

60 A.8.4.1.60 Pemasangan Pipa DCI Ø 900 mm m' 986,716.50 1,085,481.10

61 A.8.4.1.61 Pemasangan Pipa DCI Ø 1.000 mm m' 1,180,360.50 1,291,626.60

62 A.8.4.1.62 Pemasangan Pipa DCI Ø 1.100 mm m' 1,322,249.50 1,458,212.80

63 A.8.4.1.63 Pemasangan Pipa DCI Ø 1.200 mm m' 1,499,107.50 1,652,827.00

64 A.8.4.1.64 Pemasangan Baja PVC Ø 63 mm m' 70,361.50 78,609.30

65 A.8.4.1.65 Pemasangan Pipa Baja Ø 100 mm m' 80,063.50 91,105.30

66 A.8.4.1.66 Pemasangan Pipa Baja Ø 125 mm m' 90,739.00 102,220.80

67 A.8.4.1.67 Pemasangan Pipa Baja Ø 150 mm m' 103,103.00 118,742.80

68 A.8.4.1.68 Pemasangan Pipa Baja Ø 200 mm m' 160,380.00 181,805.80

69 A.8.4.1.69 Pemasangan Pipa Baja Ø 250 mm m' 206,679.00 236,640.80

70 A.8.4.1.70 Pemasangan Pipa Baja Ø 300 mm m' 238,865.00 264,602.80

71 A.8.4.1.71 Pemasangan Pipa Baja Ø 400 mm m' 358,776.00 396,410.30

72 A.8.4.1.72 Pemasangan Pipa Baja Ø 450 mm m' 374,896.50 418,020.90

73 A.8.4.1.73 Pemasangan Pipa Baja Ø 500 mm m' 426,519.50 489,049.00

74 A.8.4.1.74 Pemasangan Pipa Baja Ø 600 mm m' 460,740.50 514,555.80

75 A.8.4.1.75 Pemasangan Pipa Baja Ø 800 mm m' 738,331.00 822,025.60

76 A.8.4.1.76 Pemasangan Pipa Baja Ø 900 mm m' 846,147.50 930,869.50

77 A.8.4.1.77 Pemasangan Pipa Baja Ø 1.000 mm m' 967,131.00 1,065,235.60

78 A.8.4.1.78 Pemasangan Pipa Baja Ø 1.100 mm m' 1,080,794.00 1,186,009.00

79 A.8.4.1.79 Pemasangan Pipa Baja Ø 1.200 mm m' 1,195,936.50 1,308,459.90

415837925.xls 175/41 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA

1 A.8.4.2.1 Pemotongan Pipa PVC Ø 63 mm bh 702.90 792.00

2 A.8.4.2.2 Pemotongan Pipa PVC Ø 90 mm bh 2,022.90 2,271.50

3 A.8.4.2.3 Pemotongan Pipa PVC Ø 110 mm bh 3,210.90 3,602.50

4 A.8.4.2.4 Pemotongan Pipa PVC Ø 150 mm bh 4,481.40 5,027.00

5 A.8.4.2.5 Pemotongan Pipa PVC Ø 200 mm bh 11,892.10 13,348.50

6 A.8.4.2.6 Pemotongan Pipa PVC Ø 250 mm bh 18,942.00 21,263.00

7 A.8.4.2.7 Pemotongan Pipa PVC Ø 300 mm bh 22,809.60 25,608.00

8 A.8.4.2.8 Pemotongan Pipa PVC Ø 400 mm bh 49,041.30 55,060.50

9 A.8.4.2.9 Pemotongan Pipa PVC Ø 450 mm bh 62,700.00 70,389.00

10 A.8.4.2.10 Pemotongan Pipa PVC Ø 500 mm bh 77,418.00 86,916.50

11 A.8.4.2.11 Pemotongan Pipa PVC Ø 600 mm bh 93,082.00 104,511.00

12 A.8.4.2.12 Pemasangan Pipa PVC Ø 800 mm bh 163,185.00 183,238.00

13 A.8.4.2.13 Pemotongan Pipa PVC Ø 900 mm bh 170,962.00 191,972.00

14 A.8.4.2.14 Pemotongan Pipa PVC Ø 1.000 mm bh 192,648.50 216,326.00

15 A.8.4.2.15 Pemotongan Pipa PVC Ø 1.100 mm bh 214,197.50 240,526.00

16 A.8.4.2.16 Pemotongan Pipa PVC Ø 1.200 mm bh 235,774.00 264,759.00

17 A.8.4.2.17 Pemotongan Pipa HDPE Ø 63 mm bh 4,141.50 4,572.70

18 A.8.4.2.18 Pemotongan Pipa HDPE Ø 100 mm bh 8,866.00 9,784.50

19 A.8.4.2.19 Pemotongan Pipa HDPE Ø 125 mm bh 12,100.00 13,354.00

20 A.8.4.2.20 Pemotongan Pipa HDPE Ø 150 mm bh 15,933.50 17,600.00

21 A.8.4.2.21 Pemotongan Pipa HDPE Ø 200 mm bh 25,646.50 28,391.00

22 A.8.4.2.22 Pemotongan Pipa HDPE Ø 250 mm bh 34,688.50 38,423.00

23 A.8.4.2.23 Pemotongan Pipa HDPE Ø 300 mm bh 43,752.50 48,482.50

24 A.8.4.2.24 Pemotongan Pipa HDPE Ø 400 mm bh 68,101.00 75,597.50

25 A.8.4.2.25 Pemotongan Pipa HDPE Ø 450 mm bh 81,136.00 90,123.00

26 A.8.4.2.26 Pemotongan Pipa HDPE Ø 500 mm bh 90,480.50 100,463.00

27 A.8.4.2.27 Pemotongan Pipa HDPE Ø 600 mm bh 114,141.50 126,841.00

28 A.8.4.2.28 Pemotongan Pipa HDPE Ø 800 mm bh 177,369.50 197,417.00

29 A.8.4.2.29 Pemotongan Pipa HDPE Ø 900 mm bh 236,219.50 263,345.50

30 A.8.4.2.30 Pemotongan Pipa HDPE Ø 1.000 mm bh 279,801.50 312,097.50

31 A.8.4.2.31 Pemotongan Pipa HDPE Ø 1.100 mm bh 308,308.00 343,887.50

32 A.8.4.2.32 Pemotongan Pipa HDPE Ø 1.200 mm bh 377,855.50 421,850.00

33 A.8.4.2.33 Pemotongan Pipa GIP Ø 63 mm bh 2,832.50 3,173.50

34 A.8.4.2.34 Pemotongan Pipa GIP Ø 100 mm bh 8,475.50 9,498.50

415837925.xls 175/42 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
35 A.8.4.2.35 Pemotongan Pipa GIP Ø 125 mm bh 13,387.00 15,004.00

36 A.8.4.2.36 Pemotongan Pipa GIP Ø 150 mm bh 19,134.50 21,444.50

37 A.8.4.2.37 Pemotongan Pipa GIP Ø 200 mm bh 49,555.00 55,539.00

38 A.8.4.2.38 Pemotongan Pipa GIP Ø 250 mm bh 69,124.00 77,473.00

39 A.8.4.2.39 Pemotongan Pipa GIP Ø 300 mm bh 73,414.00 82,280.00

40 A.8.4.2.40 Pemotongan Pipa GIP Ø 400 mm bh 107,585.50 120,576.50

41 A.8.4.2.41 Pemotongan Pipa GIP Ø 450 mm bh 123,618.00 138,545.00

42 A.8.4.2.42 Pemotongan Pipa GIP Ø 500 mm bh 125,884.00 141,086.00

43 A.8.4.2.43 Pemotongan Pipa GIP Ø 600 mm bh 137,192.00 153,758.00

44 A.8.4.2.44 Pemotongan Pipa GIP Ø 800 mm bh 228,371.00 255,948.00

45 A.8.4.2.45 Pemotongan Pipa GIP Ø 900 mm bh 257,977.50 289,129.50

46 A.8.4.2.46 Pemotongan Pipa GIP Ø 1.000 mm bh 287,666.50 322,404.50

47 A.8.4.2.47 Pemotongan Pipa GIP Ø 1.100 mm bh 317,245.50 355,558.50

48 A.8.4.2.48 Pemotongan Pipa GIP Ø 1.200 mm bh 347,154.50 389,075.50

49 A.8.4.2.49 Pemotongan Pipa DCI Ø 100 mm bh 8,123.50 9,142.10

50 A.8.4.2.50 Pemotongan Pipa DCI Ø 125 mm bh 12,859.00 14,476.00

51 A.8.4.2.51 Pemotongan Pipa DCI Ø 150 mm bh 18,419.50 20,736.10

52 A.8.4.2.52 Pemotongan Pipa DCI Ø 200 mm bh 42,487.50 47,842.30

53 A.8.4.2.53 Pemotongan Pipa DCI Ø 250 mm bh 55,280.50 62,250.10

54 A.8.4.2.54 Pemotongan Pipa DCI Ø 300 mm bh 59,378.00 66,866.80

55 A.8.4.2.55 Pemotongan Pipa DCI Ø 400 mm bh 109,356.50 123,157.10

56 A.8.4.2.56 Pemotongan Pipa DCI Ø 450 mm bh 132,000.00 148,645.20

57 A.8.4.2.57 Pemotongan Pipa DCI Ø 500 mm bh 152,141.00 171,318.40

58 A.8.4.2.58 Pemotongan Pipa DCI Ø 600 mm bh 152,141.00 171,318.40

59 A.8.4.2.59 Pemotongan Pipa DCI Ø 800 mm bh 300,685.00 338,525.00

60 A.8.4.2.60 Pemotongan Pipa DCI Ø 900 mm bh 389,719.00 438,748.20

61 A.8.4.2.61 Pemotongan Pipa DCI Ø 1.000 mm bh 464,821.50 523,288.70

62 A.8.4.2.62 Pemotongan Pipa DCI Ø 1.100 mm bh 546,760.50 615,523.70

63 A.8.4.2.63 Pemotongan Pipa DCI Ø 1.200 mm bh 635,701.00 715,640.20

64 A.8.4.2.64 Pemotongan pipa Baja Ø 63 mm bh 4,488.00 5,098.50

65 A.8.4.2.65 Pemotongan Pipa Baja Ø 100 mm bh 10,989.00 12,419.00

66 A.8.4.2.66 Pemotongan Pipa Baja Ø 125 mm bh 16,610.00 18,744.00

67 A.8.4.2.67 Pemotongan Pipa Baja Ø 150 mm bh 22,511.50 25,388.00

68 A.8.4.2.68 Pemotongan Pipa Baja Ø 200 mm bh 56,457.50 63,596.50

69 A.8.4.2.69 Pemotongan Pipa Baja Ø 250 mm bh 78,100.00 87,956.00

70 A.8.4.2.70 Pemotongan Pipa Baja Ø 300 mm bh 87,549.00 98,593.00

415837925.xls 175/43 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
71 A.8.4.2.71 Pemotongan Pipa Baja Ø 400 mm bh 168,201.00 189,370.50

72 A.8.4.2.72 Pemotongan Pipa Baja Ø 450 mm bh 158,658.50 178,596.00

73 A.8.4.2.73 Pemotongan Pipa Baja Ø 500 mm bh 170,885.00 192,417.50

74 A.8.4.2.74 Pemotongan Pipa Baja Ø 600 mm bh 182,028.00 204,935.50

75 A.8.4.2.75 Pemotongan Pipa Baja Ø 800 mm bh 305,640.50 344,074.50

76 A.8.4.2.76 Pemotongan Pipa Baja Ø 900 mm bh 345,889.50 389,378.00

77 A.8.4.2.77 Pemotongan Pipa Baja Ø 1.000 mm bh 386,358.50 434,929.00

78 A.8.4.2.78 Pemotongan Pipa Baja Ø 1.100 mm bh 426,690.00 480,326.00

79 A.8.4.2.79 Pemotongan Pipa Baja Ø 1.200 mm bh 467,159.00 525,877.00

HARGA SATUAN PEKERJAAN


XVIII A.8.4.3
PEMASANGAN AKSESORIS PIPA

1 A.8.4.3.1 Pemasangan Valve Ø 150 mm bh 264,440.00 306,317.00

2 A.8.4.3.2 Pemasangan Valve Ø 200 mm bh 335,571.50 382,893.50

3 A.8.4.3.3 Pemasangan Valve Ø 250 mm bh 391,671.50 433,713.50

4 A.8.4.3.4 Pemasangan Valve Ø 300 mm bh 462,000.00 520,300.00

5 A.8.4.3.5 Pemasangan Valve Ø 400 mm bh 813,340.00 903,397.00

6 A.8.4.3.6 Pemasangan Valve Ø 450 mm bh 868,340.00 958,397.00

7 A.8.4.3.7 Pemasangan Valve Ø 500 mm bh 1,006,500.00 1,106,600.00

8 A.8.4.3.8 Pemasangan Valve Ø 600 mm bh 730,752.00 791,186.00

9 A.8.4.3.9 Pemasangan Valve Ø 700 mm bh 846,340.00 905,597.00

10 A.8.4.3.10 Pemasangan Valve Ø 800 mm bh 953,353.50 1,024,391.50

11 A.8.4.3.11 Pemasangan Valve Ø 900 mm bh 1,041,771.50 1,117,583.50

12 A.8.4.3.12 Pemasangan Valve Ø 1.000 mm bh 1,265,764.50 1,346,218.50

13 A.8.4.3.13 Pemasangan Valve Ø 1.100 mm bh 1,383,250.00 1,471,250.00

14 A.8.4.3.14 Pemasangan Valve Ø 1.200 mm bh 1,416,250.00 1,515,250.00

15 A.8.4.3.15 Pemasangan Tee Ø 150 mm bh 29,001.50 34,233.10

16 A.8.4.3.16 Pemasangan Tee Ø 200 mm bh 48,345.00 57,714.80

17 A.8.4.3.17 Pemasangan Tee Ø 250 mm bh 75,487.50 86,815.30

18 A.8.4.3.18 Pemasangan Tee Ø 300 mm bh 107,591.00 121,869.00

19 A.8.4.3.19 Pemasangan Tee Ø 400 mm bh 150,656.00 168,806.00

20 A.8.4.3.20 Pemasangan Tee Ø 450 mm bh 188,688.50 208,774.50

21 A.8.4.3.21 Pemasangan Tee Ø 500 mm bh 216,821.00 239,063.00

22 A.8.4.3.22 Pemasangan Tee Ø 600 mm bh 276,749.00 309,579.60

23 A.8.4.3.23 Pemasangan Tee Ø 700 mm bh 333,971.00 365,618.00

24 A.8.4.3.24 Pemasangan Tee Ø 800 mm bh 380,028.00 421,469.40

25 A.8.4.3.25 Pemasangan Tee Ø 900 mm bh 440,077.00 486,235.20

415837925.xls 175/44 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.8.4.3.26 Pemasangan Tee Ø 1.000 mm bh 498,267.00 548,880.20

27 A.8.4.3.27 Pemasangan Tee Ø 1.100 mm bh 554,202.00 608,951.20

28 A.8.4.3.28 Pemasangan Tee Ø 1.200 mm bh 614,251.00 673,717.00

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

Penyambungan Pipa Baru ke Pipa yang ada Ø 80


1 A.8.4.4.1 bh 440,368.50 516,180.50
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


2 A.8.4.4.2 bh 519,304.50 598,000.70
100 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


3 A.8.4.4.3 bh 749,644.50 849,301.20
150 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


4 A.8.4.4.4 bh 946,984.50 1,078,601.70
200 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


5 A.8.4.4.5 bh 1,116,824.50 1,263,902.20
250 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


6 A.8.4.4.6 bh 1,275,664.50 1,438,202.70
300 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


7 A.8.4.4.7 bh 1,593,344.50 1,797,803.70
400 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


8 A.8.4.4.8 bh 1,757,684.50 1,983,104.20
450 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


9 A.8.4.4.9 bh 1,933,024.50 2,179,404.70
500 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


10 A.8.4.4.10 bh 2,250,704.50 2,539,005.70
600 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


11 A.8.4.4.11 bh 2,601,384.50 2,931,606.70
700 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


12 A.8.4.4.11 bh 2,908,064.50 3,291,207.70
800 mm

XX A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN

1 A.8.4.5.1 Pengetesan Pipa Ø 50 mm m' 1,292.83 1,419.44

2 A.8.4.5.2 Pengetesan Pipa Ø 75 mm m' 1,293.16 1,419.88

3 A.8.4.5.3 Pengetesan Pipa Ø 100 mm m' 1,293.82 1,420.76

4 A.8.4.5.4 Pengetesan Pipa Ø 150 mm m' 1,295.47 1,422.96

5 A.8.4.5.5 Pengetesan Pipa Ø 200 mm m' 1,297.62 1,425.82

6 A.8.4.5.6 Pengetesan Pipa Ø 250 mm m' 1,300.59 1,429.78

7 A.8.4.5.7 Pengetesan Pipa Ø 300 mm m' 1,304.22 1,434.62

8 A.8.4.5.8 Pengetesan Pipa Ø 400 mm m' 1,313.29 1,446.72

9 A.8.4.5.9 Pengetesan Pipa Ø 500 mm m' 1,318.57 1,453.76

10 A.8.4.5.10 Pengetesan Pipa Ø 600 mm m' 1,339.20 1,481.26

415837925.xls 175/45 hspk ok


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN B E BAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI V 2018

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
1 A.2.2.1.2 1 m' 580,459.00 678,848.50
2,00 m
A TENAGA 57,200.00 63,600.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.4 OH Tukang Kayu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.02 OH Mandor 100,000.00 110,000.00 2,000.00 2,200.00
B BAHAN 470,490.00 553,535.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portalnd Semen 1,100.00 1,150.00 2,750.00 2,875.00
1.2 Lbr Seng Gelombang 3" - 5" 42,000.00 55,000.00 50,400.00 66,000.00
0.005 m3 Pasir Beton 350,000.00 380,000.00 1,750.00 1,900.00
0.009 m3 Koral Beton 310,000.00 390,000.00 2,790.00 3,510.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 5,200,000.00 6,000,000.00 374,400.00 432,000.00
0.06 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 900.00 1,050.00
0.45 Kg Meni Besi 25,000.00 36,000.00 11,250.00 16,200.00
C PERALATAN
D Jumlah A + B + C 527,690.00 617,135.00
E Overhead & Profit (contah 10%) 10% 52,769.00 61,713.50
F Harga Satuan Pekerjaan (D+E) 580,459.00 678,848.50
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 137,555.00 170,170.00
A Tenaga 18,600.00 20,750.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 106,450.00 133,950.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 5,200,000.00 6,000,000.00 62,400.00 72,000.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
0.007 m3 Kayu Papan 3/20 Kruing 6,250,000.00 8,800,000.00 43,750.00 61,600.00
C PERALATAN
D Jumlah A + B + C 125,050.00 154,700.00
E Overhead & Profit (contah 10%) 10% 12,505.00 15,470.00
F Harga Satuan Pekerjaan (D+E) 137,555.00 170,170.00

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,863,070.00 2,121,707.50

A Tenaga 473,000.00 526,500.00


L.01 2 OH Pekerja 75,000.00 85,000.00 150,000.00 170,000.00
L.02 2 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.02 1 OH Tukang Batu 95,000.00 105,000.00 95,000.00 105,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,220,700.00 1,402,325.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 26,250.00 30,000.00
0.18 m3 Kayu 5,200,000.00 6,000,000.00 936,000.00 1,080,000.00
0.80 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 12,000.00 14,000.00
1.1 Kg Besi Strip 13,500.00 14,000.00 14,850.00 15,400.00
35 Kg Portland Sement 1,100.00 1,150.00 38,500.00 40,250.00
0.15 m3 Pasir pasang 315,000.00 370,000.00 47,250.00 55,500.00
0.1 m3 Pasir Beton 350,000.00 380,000.00 35,000.00 38,000.00
0.15 m3 Koral Beton 310,000.00 390,000.00 46,500.00 58,500.00
30 buah Batu bata Merah 600.00 650.00 18,000.00 19,500.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
0.20 buah Jendela Naco 35,000.00 37,500.00 7,000.00 7,500.00
0.08 m2 Kaca Polos 75,000.00 85,000.00 6,000.00 6,800.00
0.15 buah Kunci Tanam 165,000.00 175,000.00 24,750.00 26,250.00
0.06 Lbr Plywood 4 mm 60,000.00 75,000.00 3,600.00 4,500.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 1,693,700.00 1,928,825.00
E Overhead & Profit (contah 10%) 10% 169,370.00 192,882.50
F Harga Satuan Pekerjaan (D+E) 1,863,070.00 2,121,707.50

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,444,300.00 1,665,950.00


A Tenaga 239,000.00 266,000.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 1.50 OH Tukang Kayu 95,000.00 105,000.00 142,500.00 157,500.00
L.03 0.15 OH Kepala Tukang 110,000.00 120,000.00 16,500.00 18,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,074,000.00 1,248,500.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
0.18 m3 Kayu 5,200,000.00 6,000,000.00 936,000.00 1,080,000.00
0.80 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 12,000.00 14,000.00
1.50 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,313,000.00 1,514,500.00
E Overhead & Profit (contah 10%) 10% 131,300.00 151,450.00
F Harga Satuan Pekerjaan (D+E) 1,444,300.00 1,665,950.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,361,525.00 1,581,415.00


A Tenaga 292,000.00 324,500.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 2 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.03 0.2 OH Kepala Tukang 110,000.00 120,000.00 22,000.00 24,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,232,750.00 1,431,525.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.21 m3 Kayu 5,200,000.00 6,000,000.00 1,092,000.00 1,260,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
10.5 Kg Portland Semen 1,100.00 1,150.00 11,550.00 12,075.00
0.03 m3 Pasir Beton 350,000.00 380,000.00 10,500.00 11,400.00
0.05 m3 Koral Beton 310,000.00 390,000.00 15,500.00 19,500.00
1.5 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,237,750.00 1,437,650.00
E Overhead & Profit (contah 10%) 10% 123,775.00 143,765.00
F Harga Satuan Pekerjaan (D+E) 1,361,525.00 1,581,415.00

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 1,650,000.00 1,911,910.00


A Tenaga 292,000.00 324,500.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 2 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.03 0.2 OH Kepala Tukang 110,000.00 120,000.00 22,000.00 24,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,208,000.00 1,413,600.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
0.186 m3 Kayu 5,200,000.00 6,000,000.00 967,200.00 1,116,000.00
0.30 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
18.00 Kg Portland Semen 1,100.00 1,150.00 19,800.00 20,700.00
0.03 m3 Pasir Beton 350,000.00 380,000.00 10,500.00 11,400.00
0.05 m3 Koral Beton 310,000.00 390,000.00 15,500.00 19,500.00
1.50 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
1.35 Lbr Playwood 75,000.00 95,000.00 101,250.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,500,000.00 1,738,100.00
E Overhead & Profit (contah 10%) 10% 150,000.00 173,810.00
F Harga Satuan Pekerjaan (D+E) 1,650,000.00 1,911,910.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 13,750.00 15,400.00


A Tenaga 12,500.00 14,000.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 12,500.00 14,000.00
E Overhead & Profit (contah 10%) 10% 1,250.00 1,400.00
F Harga Satuan Pekerjaan (D+E) 13,750.00 15,400.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 339,132.20 383,173.12


A Tenaga 292,000.00 324,500.00
L.01 1.00 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 2.00 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.03 0.20 OH Kepala Tukang 110,000.00 120,000.00 22,000.00 24,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 16,302.00 23,839.20
1.250 Btg Bambu diameter 6 - 8 / 600 cm 12,000.00 18,000.00 15,000.00 22,500.00
0.186 Kg Tali Ijuk 7,000.00 7,200.00 1,302.00 1,339.20
C PERALATAN
D Jumlah A + B + C 308,302.00 348,339.20
E Overhead & Profit (contah 10%) 10% 30,830.20 34,833.92
F Harga Satuan Pekerjaan (D+E) 339,132.20 383,173.12

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 489,720.00 626,230.00
40cmx50cmx25cm
A Tenaga 31,800.00 35,100.00
L.02 0.30 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
B Bahan 413,400.00 534,200.00
0.036 m3 Kayu Papan Kelas III 6,250,000.00 8,800,000.00 225,000.00 316,800.00
0.036 m3 Kayu Balok Kelas III 5,200,000.00 6,000,000.00 187,200.00 216,000.00
0.080 kg Paku Biasa 15,000.00 17,500.00 1,200.00 1,400.00
C PERALATAN
D Jumlah A + B + C 445,200.00 569,300.00
E Overhead & Profit (contah 10%) 10% 44,520.00 56,930.00
F Harga Satuan Pekerjaan (D+E) 489,720.00 626,230.00

10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 159,115.00 188,100.00


A Tenaga 75,500.00 85,550.00

L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00

L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00

B. Bahan 69,150.00 85,450.00

0.150 m3 Batu Belah 260,000.00 335,000.00 39,000.00 50,250.00

0.090 m3 Batu Pecah 300,000.00 350,000.00 27,000.00 31,500.00

0.010 m3 Pasir Pasang 315,000.00 370,000.00 3,150.00 3,700.00

C PERALATAN
D Jumlah A + B + C 144,650.00 171,000.00
E Overhead & Profit (contah 10%) 10% 14,465.00 17,100.00
F Harga Satuan Pekerjaan (D+E) 159,115.00 188,100.00

11 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,173,315.00 1,327,315.00


A Tenaga 1,066,650.00 1,206,650.00
L.01 13.334 OH Pekerja 75,000.00 85,000.00 1,000,050.00 1,133,390.00
L.04 0.666 OH Mandor 100,000.00 110,000.00 66,600.00 73,260.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,066,650.00 1,206,650.00
E Overhead & Profit (contah 10%) 10% 106,665.00 120,665.00
F Harga Satuan Pekerjaan (D+E) 1,173,315.00 1,327,315.00

12 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 553,657.50 627,357.50


A Tenaga 503,325.00 570,325.00
L.01 6.667 OH Pekerja 75,000.00 85,000.00 500,025.00 566,695.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan
C PERALATAN
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
D Jumlah A + B + C 503,325.00 570,325.00
E Overhead & Profit (contah 10%) 10% 50,332.50 57,032.50
F Harga Satuan Pekerjaan (D+E) 553,657.50 627,357.50

13 A.2.2.1.15 1 m2 Pagar Kawat Jaring Galvanis Panjang 240 cm 52,123.50 57,057.00


A Tenaga 7,950.00 8,850.00

L.01 0.042 OH Pekerja 75,000.00 85,000.00 3,150.00 3,570.00


L.02 0.004 OH Tukang 95,000.00 105,000.00 380.00 420.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.042 OH Mandor 100,000.00 110,000.00 4,200.00 4,620.00
B Bahan 39,435.00 43,020.00

0.1434 Lbr Kawat Jaring 275,000 300,000 39,435.00 43,020.00


C PERALATAN
D Jumlah A + B + C 47,385.00 51,870.00
E Overhead & Profit (contah 10%) 10% 4,738.50 5,187.00
F Harga Satuan Pekerjaan (D+E) 52,123.50 57,057.00

Pemasangan Pagar Panel Beton Pracetak 5 x 50 x


14 A.2.2.1.16 1 m2 300,393.50 333,676.75
240 cm

A Tenaga 43,220.00 48,530.00


L.01 0.375 OH Pekerja 75,000.00 85,000.00 28,125.00 31,875.00
L.02 0.125 OH Tukang Batu 95,000.00 105,000.00 11,875.00 13,125.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00
B Bahan 229,865.00 254,812.50
0.986 Lbr Panel Beton Pracetak 65,000.00 75,000.00 64,090.00 73,950.00
0.525 Btg Kolom Beton Pracetak 145,000.00 162,500.00 76,125.00 85,312.50
45.000 Kg Semen (SM) 1,100.00 1,150.00 49,500.00 51,750.00
0.146 m3 Koral 275,000.00 300,000.00 40,150.00 43,800.00
C PERALATAN
D Jumlah A + B + C 273,085.00 303,342.50
E Overhead & Profit (contah 10%) 10% 27,308.50 30,334.25
F Harga Satuan Pekerjaan (D+E) 300,393.50 333,676.75
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 64,625.00 73,150.00


A TENAGA 58,750.00 66,500.00
L.01 0.75 OH Pekerja 75,000.00 85,000.00 56,250.00 63,750.00
L.04 0.025 OH Mandor 100,000.00 110,000.00 2,500.00 2,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 58,750.00 66,500.00
E Overhead & Profit (contah 10%) 10% 5,875.00 6,650.00
F Harga Satuan Pekerjaan (D+E) 64,625.00 73,150.00
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 79,200.00 89,595.00
A TENAGA 72,000.00 81,450.00
L.01 0.90 OH Pekerja 75,000.00 85,000.00 67,500.00 76,500.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 72,000.00 81,450.00
E Overhead & Profit (contah 10%) 10% 7,200.00 8,145.00
F Harga Satuan Pekerjaan (D+E) 79,200.00 89,595.00

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 93,995.00 106,282.00


A TENAGA 85,450.00 96,620.00
L.01 1.05 OH Pekerja 75,000.00 85,000.00 78,750.00 89,250.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 85,450.00 96,620.00
E Overhead & Profit (contah 10%) 10% 8,545.00 9,662.00
F Harga Satuan Pekerjaan (D+E) 93,995.00 106,282.00

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 86,020.00 97,372.00


TENAGA 78,200.00 88,520.00
L.01 1.000 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.04 0.032 OH Mandor 100,000.00 110,000.00 3,200.00 3,520.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 78,200.00 88,520.00
E Overhead & Profit (contah 10%) 10% 7,820.00 8,852.00
F Harga Satuan Pekerjaan (D+E) 86,020.00 97,372.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 130,350.00 147,510.00


A TENAGA 118,500.00 134,100.00
L.01 1.50 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.04 0.060 OH Mandor 100,000.00 110,000.00 6,000.00 6,600.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 118,500.00 134,100.00
E Overhead & Profit (contah 10%) 10% 11,850.00 13,410.00
F Harga Satuan Pekerjaan (D+E) 130,350.00 147,510.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 103,950.00 117,645.00


A TENAGA 94,500.00 106,950.00
L.01 1.200 OH Pekerja 75,000.00 85,000.00 90,000.00 102,000.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 94,500.00 106,950.00
E Overhead & Profit (contah 10%) 10% 9,450.00 10,695.00
F Harga Satuan Pekerjaan (D+E) 103,950.00 117,645.00

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 4,675.00 5,280.00


A TENAGA 4,250.00 4,800.00
L.01 0.05 OH Pekerja 75,000.00 85,000.00 3,750.00 4,250.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 4,250.00 4,800.00
E Overhead & Profit (contah 10%) 10% 425.00 480.00
F Harga Satuan Pekerjaan (D+E) 4,675.00 5,280.00

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 28,325.00 32,065.00


A TENAGA 25,750.00 29,150.00
L.01 0.330 OH Pekerja 75,000.00 85,000.00 24,750.00 28,050.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

file:///conversion/tmp/scratch/415837925.xls 175/50 2-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 25,750.00 29,150.00
E Overhead & Profit (contah 10%) 10% 2,575.00 2,915.00
F Harga Satuan Pekerjaan (D+E) 28,325.00 32,065.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 15,583.33 17,600.00
Pekerjaan galian
A TENAGA 42,500.00 48,000.00
L.01 0.50 OH Pekerja 75,000.00 85,000.00 37,500.00 42,500.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 42,500.00 48,000.00
E Overhead & Profit (contah 10%) 10% 4,250.00 4,800.00
F Harga Satuan Pekerjaan (D+E) 46,750.00 52,800.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 46,750.00 52,800.00


A TENAGA 42,500.00 48,000.00
L.01 0.5 OH Pekerja 75,000.00 85,000.00 37,500.00 42,500.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 42,500.00 48,000.00
E Overhead & Profit (contah 10%) 10% 4,250.00 4,800.00
F Harga Satuan Pekerjaan (D+E) 46,750.00 52,800.00

11 A.2.3.1.11 1 m3 Urugan Pasir 237,050.00 332,860.00


A TENAGA 23,500.00 26,600.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B BAHAN 192,000.00 276,000.00
1.2 m3 Pasir Urug 160,000.00 230,000.00 192,000.00 276,000.00
C PERALATAN
D Jumlah A + B + C 215,500.00 302,600.00
E Overhead & Profit (contah 10%) 10% 21,550.00 30,260.00
F Harga Satuan Pekerjaan (D+E) 237,050.00 332,860.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 425,353.50 473,297.00


A TENAGA 110,400.00 123,600.00
L.01 0.800 OH Pekerja 75,000.00 85,000.00 60,000.00 68,000.00
L.02 0.400 OH Tukang Batu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.04 OH Kepala Tukang 110,000.00 120,000.00 4,400.00 4,800.00
L.04 0.080 OH Mandor 100,000.00 110,000.00 8,000.00 8,800.00
B BAHAN 276,285.00 306,670.00
0.135 m3 Pasir Pasang 315,000.00 370,000.00 42,525.00 49,950.00
0.400 m3 Kapur Padam 300,000.00 310,000.00 120,000.00 124,000.00
0.948 m3 Tanah Liat 120,000.00 140,000.00 113,760.00 132,720.00
C PERALATAN
D Jumlah A + B + C 386,685.00 430,270.00
E Overhead & Profit (contah 10%) 10% 38,668.50 43,027.00
F Harga Satuan Pekerjaan (D+E) 425,353.50 473,297.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 60,225.00 63,360.00
Resapan
A TENAGA 12,750.00 14,400.00
0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B BAHAN 42,000.00 43,200.00
6.00 kg Ijuk 7,000.00 7,200.00 42,000.00 43,200.00
C PERALATAN
D Jumlah A + B + C 54,750.00 57,600.00
E Overhead & Profit (contah 10%) 10% 5,475.00 5,760.00
F Harga Satuan Pekerjaan (D+E) 60,225.00 63,360.00

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 260,975.00 290,400.00


A TENAGA 21,250.00 24,000.00
0.25 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
0.025 OH Mandor 100,000.00 110,000.00 2,500.00 2,750.00
B BAHAN 216,000.00 240,000.00
1.2 m3 Sirtu 180,000.00 200,000.00 216,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 237,250.00 264,000.00
E Overhead & Profit (contah 10%) 10% 23,725.00 26,400.00
F Harga Satuan Pekerjaan (D+E) 260,975.00 290,400.00

file:///conversion/tmp/scratch/415837925.xls 175/51 2-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 975,122.50 1,094,775.00
A TENAGA 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B BAHAN 686,975.00 771,750.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
202 Kg Portland Sement 1,100.00 1,150.00 222,200.00 232,300.00
0.485 m3 Pasir Pasang 315,000.00 370,000.00 152,775.00 179,450.00
C PERALATAN
D Jumlah A + B + C 886,475.00 995,250.00
E Overhead & Profit (contoh 10%) 10% 88,647.50 99,525.00
F Harga Satuan Pekerjaan (D+E) 975,122.50 1,094,775.00
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 940,060.00 1,059,685.00
A TENAGA 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B BAHAN 655,100.00 739,850.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
163 Kg Portland Sement 1,100.00 1,150.00 179,300.00 187,450.00
0.52 m3 Pasir Pasang 315,000.00 370,000.00 163,800.00 192,400.00
C PERALATAN
D Jumlah A + B + C 854,600.00 963,350.00
E Overhead & Profit (contoh 10%) 10% 85,460.00 96,335.00
F Harga Satuan Pekerjaan (D+E) 940,060.00 1,059,685.00

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 915,706.00 1,035,298.00


A TENAGA 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B BAHAN 632,960.00 717,680.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
136 Kg Portland Sement 1,100.00 1,150.00 149,600.00 156,400.00
0.544 m3 Pasir Pasang 315,000.00 370,000.00 171,360.00 201,280.00
C PERALATAN
D Jumlah A + B + C 832,460.00 941,180.00
E Overhead & Profit (contoh 10%) 10% 83,246.00 94,118.00
F Harga Satuan Pekerjaan (D+E) 915,706.00 1,035,298.00

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 898,606.50 1,018,182.00


A TENAGA 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B BAHAN 617,415.00 702,120.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
117 Kg Portland Sement 1,100.00 1,150.00 128,700.00 134,550.00
0.561 m3 Pasir Pasang 315,000.00 370,000.00 176,715.00 207,570.00
C PERALATAN
D Jumlah A + B + C 816,915.00 925,620.00
E Overhead & Profit (contoh 10%) 10% 81,691.50 92,562.00
F Harga Satuan Pekerjaan (D+E) 898,606.50 1,018,182.00

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 875,116.00 994,653.00


A Tenaga 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 596,060.00 680,730.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
91 Kg Portland Sement 1,100.00 1,150.00 100,100.00 104,650.00
0.584 m3 Pasir Pasang 315,000.00 370,000.00 183,960.00 216,080.00

file:///conversion/tmp/scratch/415837925.xls 175/52 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 795,560.00 904,230.00
E Overhead & Profit (contoh 10%) 10% 79,556.00 90,423.00
F Harga Satuan Pekerjaan (D+E) 875,116.00 994,653.00

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 773,960.00 875,600.00
A Tenaga 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 504,100.00 572,500.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 315,000.00 370,000.00 107,100.00 125,800.00
C PERALATAN
D Jumlah A + B + C 703,600.00 796,000.00
E Overhead & Profit (contoh 10%) 10% 70,360.00 79,600.00
F Harga Satuan Pekerjaan (D+E) 773,960.00 875,600.00

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 855,448.00 969,386.00


A Tenaga 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 578,180.00 657,760.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
61 kg Portland Sement 1,100.00 1,150.00 67,100.00 70,150.00
0.147 m3 Kapur Pasang 300,000.00 310,000.00 44,100.00 45,570.00
0.492 m3 Pasir Pasang 315,000.00 370,000.00 154,980.00 182,040.00
C PERALATAN
D Jumlah A + B + C 777,680.00 881,260.00
E Overhead & Profit (contoh 10%) 10% 77,768.00 88,126.00
F Harga Satuan Pekerjaan (D+E) 855,448.00 969,386.00

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 836,709.50 951,247.00


A Tenaga 199,500.00 223,500.00
L.01 1.5 OH Pekerja 75,000.00 85,000.00 112,500.00 127,500.00
L.02 0.750 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 561,145.00 641,270.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
41 kg Portland Sement 1,100.00 1,150.00 45,100.00 47,150.00
0.131 m3 Kapur Pasang 300,000.00 310,000.00 39,300.00 40,610.00
0.523 m3 Pasir 315,000.00 370,000.00 164,745.00 193,510.00
C PERALATAN
D Jumlah A + B + C 760,645.00 864,770.00
E Overhead & Profit (contoh 10%) 10% 76,064.50 86,477.00
F Harga Satuan Pekerjaan (D+E) 836,709.50 951,247.00

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 533,346.00 633,138.00


A Tenaga 103,740.00 116,220.00
L.01 0.78 OH Pekerja 75,000.00 85,000.00 58,500.00 66,300.00
L.02 0.39 OH Tukang Batu 95,000.00 105,000.00 37,050.00 40,950.00
L.03 0.039 OH Kepala Tukang 110,000.00 120,000.00 4,290.00 4,680.00
L.04 0.039 OH Mandor 100,000.00 110,000.00 3,900.00 4,290.00
B Bahan 381,120.00 459,360.00
1.2 m3 Batu Belah 15/20 260,000.00 300,000.00 312,000.00 360,000.00
0.432 m3 Pasir Urug 160,000.00 230,000.00 69,120.00 99,360.00
C PERALATAN
D Jumlah A + B + C 484,860.00 575,580.00
E Overhead & Profit (contoh 10%) 10% 48,486.00 57,558.00
F Harga Satuan Pekerjaan (D+E) 533,346.00 633,138.00

file:///conversion/tmp/scratch/415837925.xls 175/53 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,431,462.00 2,639,109.00
3KR & 40% Batu Belah
A Tenaga 360,100.00 404,950.00
L.01 3.4 OH Pekerja 75,000.00 85,000.00 255,000.00 289,000.00
L.02 0.85 OH Tukang Batu 95,000.00 105,000.00 80,750.00 89,250.00
L.03 0.085 OH Kepala Tukang 110,000.00 120,000.00 9,350.00 10,200.00
L.04 0.15 OH Mandor 100,000.00 110,000.00 15,000.00 16,500.00
B Bahan 1,850,320.00 1,994,240.00
0.480 m3 Batu Belah 15/20 cm 260,000.00 300,000.00 124,800.00 144,000.00
126 Kg Besi Beton 10,000.00 10,750.00 1,260,000.00 1,354,500.00
194 Kg Portland Semen 1,100.00 1,150.00 213,400.00 223,100.00
0.312 m3 Pasir Beton 350,000.00 380,000.00 109,200.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
1.8 Kg Kawat Beton 17,000.00 18,000.00 30,600.00 32,400.00
C PERALATAN
D Jumlah A + B + C 2,210,420.00 2,399,190.00
E Overhead & Profit (contoh 10%) 10% 221,042.00 239,919.00
F Harga Satuan Pekerjaan (D+E) 2,431,462.00 2,639,109.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 911,482.00 999,933.00


A Tenaga 276,700.00 310,690.00
L.01 2.40 OH Pekerja 75,000.00 85,000.00 180,000.00 204,000.00
L.02 0.8 OH Tukang Batu 95,000.00 105,000.00 76,000.00 84,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 120,000.00 8,800.00 9,600.00
L.04 0.119 OH Mandor 100,000.00 110,000.00 11,900.00 13,090.00
B Bahan 551,920.00 598,340.00
0.45 m3 Batu Belah 15/20 cm 260,000.00 300,000.00 117,000.00 135,000.00
194 Kg Portland Semen 1,100.00 1,150.00 213,400.00 223,100.00
0.312 m3 Pasir Beton 350,000.00 380,000.00 109,200.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
C PERALATAN
D Jumlah A + B + C 828,620.00 909,030.00
E Overhead & Profit (contoh 10%) 10% 82,862.00 90,903.00
F Harga Satuan Pekerjaan (D+E) 911,482.00 999,933.00

file:///conversion/tmp/scratch/415837925.xls 175/54 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 971,113.00 1,093,880.07
= 0,87
A Tenaga 161,255.00 181,615.00
L.01 1.65 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 721,575.00 812,821.43
247 Kg Portland Semen 1,100.00 1,150.00 271,700.00 284,050.00
869 Kg Pasir Beton 250.00 271.43 217,250.00 235,871.43
999 Kg Kerikil (maksimum 30 mm) 229.63 288.89 229,400.00 288,600.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 882,830.00 994,436.43
E Overhead & Profit (contoh 10%) 10% 88,283.00 99,443.64
F Harga Satuan Pekerjaan (D+E) 971,113.00 1,093,880.07
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 998,211.70 1,122,454.75
= 0,78
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 746,210.19 838,798.41
276 Kg Portland Semen 1,100.00 1,150.00 303,600.00 317,400.00
828 kg Pasir Beton 250.00 271.43 207,000.00 224,742.86
1,012 kg Kerikil (maksimum 30 mm) 229.63 288.89 232,385.19 292,355.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 907,465.19 1,020,413.41
E Overhead & Profit (contoh 10%) 10% 90,746.52 102,041.34
F Harga Satuan Pekerjaan (D+E) 998,211.70 1,122,454.75

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 1,019,329.67 1,144,480.07
w/c = 0,72
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 765,408.33 858,821.43
299 Kg Portland Semen 1,100.00 1,150.00 328,900.00 343,850.00
799 kg Pasir Beton 250.00 271.43 199,750.00 216,871.43
1,017 kg Kerikil (maksimum 30 mm) 229.63 288.89 233,533.33 293,800.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 926,663.33 1,040,436.43
E Overhead & Profit (contoh 10%) 10% 92,666.33 104,043.64
F Harga Satuan Pekerjaan (D+E) 1,019,329.67 1,144,480.07

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 909,567.59 1,026,998.06
(3-6)cm, w/c = 0,87
A Tenaga 111,800.00 126,060.00
L.01 1.200 OH Pekerja 75,000.00 85,000.00 90,000.00 102,000.00
L.02 0.200 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 715,079.63 807,574.60
230 Kg Portland Semen 1,100.00 1,150.00 253,000.00 264,500.00
893 kg Pasir Beton 250.00 271.43 223,250.00 242,385.71
1,027 kg Kerikil (maksimum 30 mm) 229.63 288.89 235,829.63 296,688.89
200 ltr Air 15.00 20.00 3,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 826,879.63 933,634.60
E Overhead & Profit (contoh 10%) 10% 82,687.96 93,363.46
F Harga Satuan Pekerjaan (D+E) 909,567.59 1,026,998.06

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,044,305.78 1,170,804.12
w/c = 0,66
A Tenaga 161,255.00 181,615.00
L.01 1.65 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00

file:///conversion/tmp/scratch/415837925.xls 175/55 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 788,113.89 882,752.38
326 Kg Portland Semen 1,100.00 1,150.00 358,600.00 374,900.00
760 Kg Pasir Beton 250.00 271.43 190,000.00 206,285.71
1,029 Kg Kerikil (maksimum 30 mm) 229.63 288.89 236,288.89 297,266.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 949,368.89 1,064,367.38
E Overhead & Profit (contoh 10%) 10% 94,936.89 106,436.74
F Harga Satuan Pekerjaan (D+E) 1,044,305.78 1,170,804.12

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,068,295.96 1,195,671.10
w/c = 0,61
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 809,923.15 905,358.73
352 Kg Portland Semen 1,100.00 1,150.00 387,200.00 404,800.00
731 Kg Pasir Beton 250.00 271.43 182,750.00 198,414.29
1,031 Kg Kerikil (maksimum 30 mm) 229.63 288.89 236,748.15 297,844.44
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 971,178.15 1,086,973.73
E Overhead & Profit (contoh 10%) 10% 97,117.81 108,697.37
F Harga Satuan Pekerjaan (D+E) 1,068,295.96 1,195,671.10

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,086,252.44 1,214,937.69
w/c = 0,58
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 826,247.22 922,873.81
371 Kg Portland Semen 1,100.00 1,150.00 408,100.00 426,650.00
698 Kg Pasir Beton 250.00 271.43 174,500.00 189,457.14
1,047 Kg Kerikil (maksimum 30 mm) 229.63 288.89 240,422.22 302,466.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 987,502.22 1,104,488.81
E Overhead & Profit (contoh 10%) 10% 98,750.22 110,448.88
F Harga Satuan Pekerjaan (D+E) 1,086,252.44 1,214,937.69

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,098,311.70 1,227,049.04
w/c = 0,56
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 837,210.19 933,884.13
384 Kg Portland Semen 1,100.00 1,150.00 422,400.00 441,600.00
692 Kg Pasir Beton 250.00 271.43 173,000.00 187,828.57
1,039 Kg Kerikil (maksimum 30 mm) 229.63 288.89 238,585.19 300,155.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 998,465.19 1,115,499.13
E Overhead & Profit (contoh 10%) 10% 99,846.52 111,549.91
F Harga Satuan Pekerjaan (D+E) 1,098,311.70 1,227,049.04

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,119,448.00 1,248,359.36
(12±2)cm, w/c = 0,53
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 856,425.00 953,257.14
406 Kg Portland Semen 1,100.00 1,150.00 446,600.00 466,900.00
684 kg Pasir Beton 250.00 271.43 171,000.00 185,657.14
1,026 kg Kerikil (maksimum 30 mm) 229.63 288.89 235,600.00 296,400.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,017,680.00 1,134,872.14
E Overhead & Profit (contoh 10%) 10% 101,768.00 113,487.21
F Harga Satuan Pekerjaan (D+E) 1,119,448.00 1,248,359.36

file:///conversion/tmp/scratch/415837925.xls 175/56 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,125,830.04 1,254,729.75
w/c = 0,52
A Tenaga 161,255.00 181,615.00
L.01 1.650 OH Pekerja 75,000.00 85,000.00 123,750.00 140,250.00
L.02 0.275 OH Tukang Batu 95,000.00 105,000.00 26,125.00 28,875.00
L.03 0.028 OH Kepala Tukang 110,000.00 120,000.00 3,080.00 3,360.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 862,226.85 959,048.41
413 Kg Portland Semen 1,100.00 1,150.00 454,300.00 474,950.00
681 Kg Pasir Beton 250.00 271.43 170,250.00 184,842.86
1,021 Kg Kerikil (maksimum 30 mm) 229.63 288.89 234,451.85 294,955.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,023,481.85 1,140,663.41
E Overhead & Profit (contoh 10%) 10% 102,348.19 114,066.34
F Harga Satuan Pekerjaan (D+E) 1,125,830.04 1,254,729.75

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,198,705.65 1,333,892.30
w/c = 0,49
A Tenaga 205,100.00 231,000.00
L.01 2.1 OH Pekerja 75,000.00 85,000.00 157,500.00 178,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.105 OH Mandor 100,000.00 110,000.00 10,500.00 11,550.00
B Bahan 884,632.41 981,629.37
439 Kg Portland Semen 1,100.00 1,150.00 482,900.00 504,850.00
670 Kg Pasir Beton 250.00 271.43 167,500.00 181,857.14
1,006 Kg Kerikil (maksimum 30 mm) 229.63 288.89 231,007.41 290,622.22
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,089,732.41 1,212,629.37
E Overhead & Profit (contoh 10%) 10% 108,973.24 121,262.94
F Harga Satuan Pekerjaan (D+E) 1,198,705.65 1,333,892.30

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,207,255.09 1,342,474.92
w/c = 0,48
A Tenaga 205,100.00 231,000.00
L.01 2.10 OH Pekerja 75,000.00 85,000.00 157,500.00 178,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.105 OH Mandor 100,000.00 110,000.00 10,500.00 11,550.00
B Bahan 892,404.63 989,431.75
448 Kg Portland Semen 1,100.00 1,150.00 492,800.00 515,200.00
667 Kg Pasir Beton 250.00 271.43 166,750.00 181,042.86
1,000 Kg Kerikil (maksimum 30 mm) 229.63 288.89 229,629.63 288,888.89
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,097,504.63 1,220,431.75
E Overhead & Profit (contoh 10%) 10% 109,750.46 122,043.17
F Harga Satuan Pekerjaan (D+E) 1,207,255.09 1,342,474.92

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 132,682.00 143,170.50


A Tenaga 13,070.00 14,580.00
L.01 0.07 OH Pekerja 75,000.00 85,000.00 5,250.00 5,950.00
L.02 0.07 OH Tukang Besi 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 107,550.00 115,575.00
10.50 Kg Besi Beton (polos/ulir) 10,000.00 10,750.00 105,000.00 112,875.00
0.150 Kg Kawat Beton 17,000.00 18,000.00 2,550.00 2,700.00
C PERALATAN
D Jumlah A + B + C 120,620.00 130,155.00
E Overhead & Profit (contoh 10%) 10% 12,062.00 13,015.50
F Harga Satuan Pekerjaan (D+E) 132,682.00 143,170.50

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 162,305.00 180,928.00


A Tenaga 9,350.00 10,430.00
L.01 0.05 OH Pekerja 75,000.00 85,000.00 3,750.00 4,250.00
L.02 0.05 OH Tukang Besi 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 138,200.00 154,050.00
10.5 Kg Besi presstred polos 13,000.00 14,500.00 136,500.00 152,250.00
0.1 Kg Kawat Beton 17,000.00 18,000.00 1,700.00 1,800.00

file:///conversion/tmp/scratch/415837925.xls 175/57 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 147,550.00 164,480.00
E Overhead & Profit (contoh 10%) 10% 14,755.00 16,448.00
F Harga Satuan Pekerjaan (D+E) 162,305.00 180,928.00

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 286,462.00 315,150.00


A Tenaga 4,570.00 5,100.00
L.01 0.025 OH Pekerja 75,000.00 85,000.00 1,875.00 2,125.00
L.02 0.025 OH Tukang Besi 95,000.00 105,000.00 2,375.00 2,625.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 255,850.00 281,400.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 27,500.00 255,000.00 280,500.00
0.05 Kg Kawat Beton 17,000.00 18,000.00 850.00 900.00
C PERALATAN
D Jumlah A + B + C 260,420.00 286,500.00
E Overhead & Profit (contoh 10%) 10% 26,042.00 28,650.00
F Harga Satuan Pekerjaan (D+E) 286,462.00 315,150.00

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 170,016.00 188,903.00


A Tenaga 69,160.00 77,480.00
L.01 0.52 OH Pekerja 75,000.00 85,000.00 39,000.00 44,200.00
L.02 0.26 OH Tukang Kayu 95,000.00 105,000.00 24,700.00 27,300.00
L.03 0.026 OH Kepala Tukang 110,000.00 120,000.00 2,860.00 3,120.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 85,400.00 94,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 154,560.00 171,730.00
E Overhead & Profit (contoh 10%) 10% 15,456.00 17,173.00
F Harga Satuan Pekerjaan (D+E) 170,016.00 188,903.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 181,016.00 201,003.00


A Tenaga 69,160.00 77,480.00
L.01 0.52 OH Pekerja 75,000.00 85,000.00 39,000.00 44,200.00
L.02 0.26 OH Tukang Kayu 95,000.00 105,000.00 24,700.00 27,300.00
L.03 0.026 OH Kepala Tukang 110,000.00 120,000.00 2,860.00 3,120.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 95,400.00 105,250.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 164,560.00 182,730.00
E Overhead & Profit (contoh 10%) 10% 16,456.00 18,273.00
F Harga Satuan Pekerjaan (D+E) 181,016.00 201,003.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 371,723.00 428,274.00


A Tenaga 87,780.00 98,340.00
L.01 0.66 OH Pekerja 75,000.00 85,000.00 49,500.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 250,150.00 291,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 337,930.00 389,340.00
E Overhead & Profit (contoh 10%) 10% 33,793.00 38,934.00
F Harga Satuan Pekerjaan (D+E) 371,723.00 428,274.00

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 388,883.00 448,074.00


A Tenaga 87,780.00 98,340.00
L.01 0.66 OH Pekerja 75,000.00 85,000.00 49,500.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

file:///conversion/tmp/scratch/415837925.xls 175/58 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 265,750.00 309,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 93,600.00 108,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 353,530.00 407,340.00
E Overhead & Profit (contoh 10%) 10% 35,353.00 40,734.00
F Harga Satuan Pekerjaan (D+E) 388,883.00 448,074.00

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 464,123.00 533,874.00


A Tenaga 87,780.00 98,340.00
L.01 0.66 OH Pekerja 75,000.00 85,000.00 49,500.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 334,150.00 387,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 421,930.00 485,340.00
E Overhead & Profit (contoh 10%) 10% 42,193.00 48,534.00
F Harga Satuan Pekerjaan (D+E) 464,123.00 533,874.00

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 423,423.00 487,674.00


A Tenaga 87,780.00 98,340.00
L.01 0.66 OH Pekerja 75,000.00 85,000.00 49,500.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 297,150.00 345,000.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 104,000.00 120,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 384,930.00 443,340.00
E Overhead & Profit (contoh 10%) 10% 38,493.00 44,334.00
F Harga Satuan Pekerjaan (D+E) 423,423.00 487,674.00

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 349,228.00 403,524.00


A Tenaga 87,780.00 98,340.00
L.01 0.66 OH Pekerja 75,000.00 85,000.00 49,500.00 56,100.00
L.02 0.33 OH Tukang Kayu 95,000.00 105,000.00 31,350.00 34,650.00
L.03 0.033 OH Kepala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
B Bahan 229,700.00 268,500.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 121,000.00 160,000.00 42,350.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 317,480.00 366,840.00
E Overhead & Profit (contoh 10%) 10% 31,748.00 36,684.00
F Harga Satuan Pekerjaan (D+E) 349,228.00 403,524.00

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 98,615.00 110,066.00


A Tenaga 17,350.00 19,480.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 72,300.00 80,580.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 9,000.00 10,500.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/scratch/415837925.xls 175/59 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 89,650.00 100,060.00
E Overhead & Profit (contoh 10%) 10% 8,965.00 10,006.00
F Harga Satuan Pekerjaan (D+E) 98,615.00 110,066.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 82,071.00 88,610.50
A Tenaga 20,760.00 23,310.00
L.01 0.180 OH Pekerja 75,000.00 85,000.00 13,500.00 15,300.00
L.02 0.020 OH Tukang batu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Kayu 95,000.00 105,000.00 1,900.00 2,100.00
L.02 0.020 OH Tukang Besi 95,000.00 105,000.00 1,900.00 2,100.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 53,850.00 57,245.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 150.00 175.00
3.0 Kg Besi Beton Polos 10,000.00 10,750.00 30,000.00 32,250.00
0.45 Kg Kawat Beton 17,000.00 18,000.00 7,650.00 8,100.00
4.0 Kg Portland Semen 1,100.00 1,150.00 4,400.00 4,600.00
0.006 m3 Pasir Beton 350,000.00 380,000.00 2,100.00 2,280.00
0.009 m3 Kerikil 330,000.00 360,000.00 2,970.00 3,240.00
C PERALATAN
D Jumlah A + B + C 74,610.00 80,555.00
E Overhead & Profit (contoh 10%) 10% 7,461.00 8,055.50
F Harga Satuan Pekerjaan (D+E) 82,071.00 88,610.50

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 104,995.00 113,833.50
A Tenaga 34,280.00 38,490.00
L.01 0.297 OH Pekerja 75,000.00 85,000.00 22,275.00 25,245.00
L.02 0.033 OH Tukang batu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Kayu 95,000.00 105,000.00 3,135.00 3,465.00
L.02 0.033 OH Tukang Besi 95,000.00 105,000.00 3,135.00 3,465.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 61,170.00 64,995.00
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
3.6 Kg Besi Beton Polos 10,000.00 10,750.00 36,000.00 38,700.00
0.05 Kg Kawat Beton 17,000.00 18,000.00 850.00 900.00
5.5 Kg Portland Semen 1,100.00 1,150.00 6,050.00 6,325.00
0.009 m3 Pasir Beton 350,000.00 380,000.00 3,150.00 3,420.00
0.015 m3 Kerikil 330,000.00 360,000.00 4,950.00 5,400.00
C PERALATAN
D Jumlah A + B + C 95,450.00 103,485.00
E Overhead & Profit (contoh 10%) 10% 9,545.00 10,348.50
F Harga Satuan Pekerjaan (D+E) 104,995.00 113,833.50

file:///conversion/tmp/scratch/415837925.xls 175/60 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
UNTUK PRODUKSI PRACETAK BISA DILAKUKAN DI PABRIK (COR DI PLANT) ATAU DI LAPANGAN (CAST IN PLACE). INDEKS YANG ADA DALAM PEDOMAN INI
HANYA UNTUK PEKERJAAN PRODUKSI YANG DILAKUKAN DI LAPANGAN, TERUTAMA UNTUK ANALISA CETAKAN (BEKISTING) PRACETAK BAIK UNTUK
KOMPONEN KOLOM, BALOK DAN PELAT.

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5 Mpa,


1 A.4.1.2.1 1 m2 83,555.02 93,676.21
Slump (120 ± 20) mm K3
A Tenaga 12,910.00 14,540.00
L.01 0.132 OH Pekerja 75,000.00 85,000.00 9,900.00 11,220.00
L.02 0.022 OH Tukang Batu 95,000.00 105,000.00 2,090.00 2,310.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 63,049.11 70,620.19
26.080 Kg Portland Semen 1,100.00 1,150.00 28,688.00 29,992.00
60.800 Kg Pasir Beton 250.00 271.43 15,200.00 16,502.86
82.320 Kg Kerikil (maksimum 30 mm) 229.63 288.89 18,903.11 23,781.33
17.200 ltr Air 15.00 20.00 258.00 344.00
C PERALATAN
D Jumlah A + B + C 75,959.11 85,160.19
E Overhead & Profit (contoh 10%) 10% 7,595.91 8,516.02
F Harga Satuan Pekerjaan (D+E) 83,555.02 93,676.21
10%
Overhead & Profit (contoh 10%)
Pembuatan Lahan Produksi Tebal 10 cm Beton f'c = 14,5 Mpa
2 A.4.1.2.2 1 m2 104,474.03 117,128.26
slum (120 ± 20 ) mm K3
A Tenaga 16,165.00 18,205.00
L.01 0.165 OH Pekerja 75,000.00 85,000.00 12,375.00 14,025.00
L.02 0.028 OH Tukang Batu 95,000.00 105,000.00 2,660.00 2,940.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 78,811.39 88,275.24
32.60 Kg Portland Semen 1,100.00 1,150.00 35,860.00 37,490.00
76.00 kg Pasir Beton 250.00 271.43 19,000.00 20,628.57
102.90 kg Kerikil (maksimum 30 mm) 229.63 288.89 23,628.89 29,726.67
21.50 ltr Air 15.00 20.00 322.50 430.00
C PERALATAN
D Jumlah A + B + C 94,976.39 106,480.24
E Overhead & Profit (contoh 10%) 10% 9,497.64 10,648.02
F Harga Satuan Pekerjaan (D+E) 104,474.03 117,128.26

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5 Mpa,


3 A.4.1.2.3 1 m2 122,555.03 137,368.31
slum (120±20)mm, K3
A Tenaga 16,840.00 18,950.00
L.01 0.165 OH Pekerja 75,000.00 85,000.00 12,375.00 14,025.00
L.02 0.033 OH Tukang Batu 95,000.00 105,000.00 3,135.00 3,465.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 94,573.67 105,930.29
39.120 Kg Portland Semen 1,100.00 1,150.00 43,032.00 44,988.00
91.200 kg Pasir Beton 250.00 271.43 22,800.00 24,754.29
123.480 kg Kerikil (maksimum 30 mm) 229.63 288.89 28,354.67 35,672.00
25.800 ltr Air 15.00 20.00 387.00 516.00
C PERALATAN
D Jumlah A + B + C 111,413.67 124,880.29
E Overhead & Profit (contoh 10%) 10% 11,141.37 12,488.03
F Harga Satuan Pekerjaan (D+E) 122,555.03 137,368.31

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5 Mpa,


4 A.4.1.2.4 1.00 m2 156,697.29 175,678.64
slum (120±20)mm, K3
A Tenaga 24,235.00 27,295.00
L.01 0.248 OH Pekerja 75,000.00 85,000.00 18,600.00 21,080.00
L.02 0.041 OH Tukang Batu 95,000.00 105,000.00 3,895.00 4,305.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 118,217.08 132,412.86
48.900 Kg Portland Semen 1,100.00 1,150.00 53,790.00 56,235.00
114.000 kg Pasir Beton 250.00 271.43 28,500.00 30,942.86
154.350 kg Kerikil (maksimum 30 mm) 229.63 288.89 35,443.33 44,590.00
32.250 ltr Air 15.00 20.00 483.75 645.00
C PERALATAN
D Jumlah A + B + C 142,452.08 159,707.86
E Overhead & Profit (contoh 10%) 10% 14,245.21 15,970.79
F Harga Satuan Pekerjaan (D+E) 156,697.29 175,678.64

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 1 m2 117,352.02 129,548.10
Pakai)
A Tenaga 8,725.00 9,645.00
L.01 0.007 OH Pekerja 75,000.00 85,000.00 525.00 595.00
L.02 0.076 OH Tukang Batu 95,000.00 105,000.00 7,220.00 7,980.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00

file:///conversion/tmp/scratch/415837925.xls 175/61 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 97,958.65 108,126.00
0.008 m3 Lantai Kerja Tebal 10 cm 90,956.76 102,699.81 727.65 821.60
9.394 Kg Besi Hollow (50x50x3) mm 5,500.00 6,000.00 51,667.00 56,364.00
0.005 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 26,000.00 30,000.00
0.080 lbr Phenol film 12 mm 125,000.00 130,000.00 10,000.00 10,400.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
3.882 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 7,764.00 8,540.40
C PERALATAN
D Jumlah A + B + C 106,683.65 117,771.00
E Overhead & Profit (contoh 10%) 10% 10,668.37 11,777.10
F Harga Satuan Pekerjaan (D+E) 117,352.02 129,548.10

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 - 12


6 A.4.1.2.6 1 m2 39,701.00 44,839.60
kali Pakai)
A Tenaga 4,450.00 4,920.00
L.01 0.004 OH Pekerja 75,000.00 85,000.00 300.00 340.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 35,251.00 39,919.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.005 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 26,000.00 30,000.00
0.043 lbr Phenol film 12 mm 125,000.00 130,000.00 5,375.00 5,590.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 39,701.00 44,839.60
E Overhead & Profit (contoh 10%) 10% 3,970.10 4,483.96
F Harga Satuan Pekerjaan (D+E) 43,671.10 49,323.56

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 - 12


7 A.4.1.2.7 1 m2 35,126.00 39,489.60
kali Pakai)
A Tenaga 4,450.00 4,920.00
L.01 0.004 OH Pekerja 75,000.00 85,000.00 300.00 340.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 30,676.00 34,569.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.004 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 20,800.00 24,000.00
0.048 lbr Phenol film 12 mm 125,000.00 130,000.00 6,000.00 6,240.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 35,126.00 39,489.60
E Overhead & Profit (contoh 10%) 10% 3,512.60 3,948.96
F Harga Satuan Pekerjaan (D+E) 38,638.60 43,438.56

Pemasangan dan Membuka Bekisting untuk Komponen Plat


8 A.4.1.2.8 1 bh 6,185.00 6,945.00
Beton Pracetak
A Tenaga 6,185.00 6,945.00
L.01 0.053 OH Pekerja 75,000.00 85,000.00 3,975.00 4,505.00
L.02 0.018 OH Tukang Batu 95,000.00 105,000.00 1,710.00 1,890.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 6,185.00 6,945.00
E Overhead & Profit (contoh 10%) 10% 618.50 694.50
F Harga Satuan Pekerjaan (D+E) 6,803.50 7,639.50

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 1 bh 10,025.00 11,265.00
Balok Beton Pracetak
A Tenaga 10,025.00 11,265.00
L.01 0.089 OH Pekerja 75,000.00 85,000.00 6,675.00 7,565.00
L.02 0.030 OH Tukang Batu 95,000.00 105,000.00 2,850.00 3,150.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 10,025.00 11,265.00
E Overhead & Profit (contoh 10%) 10% 1,002.50 1,126.50
F Harga Satuan Pekerjaan (D+E) 11,027.50 12,391.50

file:///conversion/tmp/scratch/415837925.xls 175/62 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan dan Membuka Bekisting untuk Komponen
10 A.4.1.2.10 1 bh 8,105.00 9,105.00
Kolom Beton Pracetak
A Tenaga 8,105.00 9,105.00
L.01 0.071 OH Pekerja 75,000.00 85,000.00 5,325.00 6,035.00
L.02 0.024 OH Tukang Batu 95,000.00 105,000.00 2,280.00 2,520.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan
C PERALATAN
D Jumlah A + B + C 8,105.00 9,105.00
E Overhead & Profit (contoh 10%) 10% 810.50 910.50
F Harga Satuan Pekerjaan (D+E) 8,915.50 10,015.50

11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 56,298.00 56,610.00

A Tenaga 51,180.00 56,610.00


L.01 0.064 OH Pekerja 75,000.00 85,000.00 4,800.00 5,440.00
L.02 0.244 OH Tukang Batu 95,000.00 105,000.00 23,180.00 25,620.00
L.02 0.128 OH Tukang Vibrator 95,000.00 105,000.00 12,160.00 13,440.00
L.03 0.034 OH Kapala Tukang 110,000.00 120,000.00 3,740.00 4,080.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 51,180.00 56,610.00
E Overhead & Profit (contoh 10%) 10% 5,118.00 5,661.00
F Harga Satuan Pekerjaan (D+E) 56,298.00 62,271.00

12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 57,909.50 58,235.00

A Tenaga 52,645.00 58,235.00


L.01 0.069 OH Pekerja 75,000.00 85,000.00 5,175.00 5,865.00
L.02 0.242 OH Tukang Batu 95,000.00 105,000.00 22,990.00 25,410.00
L.02 0.138 OH Tukang Vibrator 95,000.00 105,000.00 13,110.00 14,490.00
L.03 0.037 OH Kapala Tukang 110,000.00 120,000.00 4,070.00 4,440.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 52,645.00 58,235.00
E Overhead & Profit (contoh 10%) 10% 5,264.50 5,823.50
F Harga Satuan Pekerjaan (D+E) 57,909.50 64,058.50

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 1 m3 52,063.00 52,350.00
Pracetak
A Tenaga 47,330.00 52,350.00
L.01 0.061 OH Pekerja 75,000.00 85,000.00 4,575.00 5,185.00
L.02 0.213 OH Tukang Batu 95,000.00 105,000.00 20,235.00 22,365.00
L.02 0.122 OH Tukang Vibrator 95,000.00 105,000.00 11,590.00 12,810.00
L.03 0.033 OH Kapala Tukang 110,000.00 120,000.00 3,630.00 3,960.00
L.04 0.073 OH Mandor 100,000.00 110,000.00 7,300.00 8,030.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 47,330.00 52,350.00
E Overhead & Profit (contoh 10%) 10% 4,733.00 5,235.00
F Harga Satuan Pekerjaan (D+E) 52,063.00 57,585.00

14 A.4.1.2.14 1 bh Ereksi Komponen Untuk Plat Pracetak 575,444.10 600,433.68


A Tenaga 40,535.00 45,560.00
L.08 0.067 OH Operator Crane 150,000.00 175,000.00 10,050.00 11,725.00
L.09 0.067 OH Pembantu Operator Crane 95,000.00 105,000.00 6,365.00 7,035.00
L.01 0.067 OH Pekerja 75,000.00 85,000.00 5,025.00 5,695.00
L.02 0.067 OH Tukang Batu 95,000.00 105,000.00 6,365.00 7,035.00
L.02 0.134 OH Tukang Ereksi 95,000.00 105,000.00 12,730.00 14,070.00
L.03 0.067 OH Kepala Tukang 110,000.00 120,000.00 7,370.00 8,040.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00
B Bahan 56,746.00 58,748.80
6.676 Ltr Solar 8,500.00 8,800.00 56,746.00 58,748.80
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 523,131.00 545,848.80
E Overhead & Profit (contoh 10%) 10% 52,313.10 54,584.88
F Harga Satuan Pekerjaan (D+E) 575,444.10 600,433.68

file:///conversion/tmp/scratch/415837925.xls 175/63 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Plat Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Plat Ereksi Plat

1 1.0000 13 1.114
2 1.0000 14 1.134

3 1.0000 15 1.155

4 1.0000 16 1.176

5 1.0000 17 1.197

6 1.0000 18 1.219

7 1.0000 19 1.241

8 1.0180 20 1.264

9 1.0370 21 1.287

10 1.0550 22 1.310

11 1.0750 23 1.334

12 1.0940 24 1.358

15 A.4.1.2.15 1 bh Ereksi Komponen Untuk Balok Pracetak 566,159.00 590,466.80


A Tenaga 36,905.00 41,480.00
L.08 0.061 OH Operator Crane 150,000.00 175,000.00 9,150.00 10,675.00
L.09 0.061 OH Pembantu Operator Crane 95,000.00 105,000.00 5,795.00 6,405.00
L.01 0.061 OH Pekerja 75,000.00 85,000.00 4,575.00 5,185.00
L.02 0.061 OH Tukang Batu 95,000.00 105,000.00 5,795.00 6,405.00
L.02 0.122 OH Tukang Ereksi 95,000.00 105,000.00 11,590.00 12,810.00
L.03 0.061 OH Kepala Tukang 110,000.00 120,000.00 6,710.00 7,320.00
L.04 0.061 OH Mandor 100,000.00 110,000.00 6,100.00 6,710.00
B Bahan 51,935.00 53,768.00
6.110 Ltr Solar 8,500.00 8,800.00 51,935.00 53,768.00
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 514,690.00 536,788.00
E Overhead & Profit (contoh 10%) 10% 51,469.00 53,678.80
F Harga Satuan Pekerjaan (D+E) 566,159.00 590,466.80

Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak


Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok
1 1.0000 13 1.068

2 1.0000 14 1.080
3 1.0000 15 1.092

4 1.0000 16 1.104
5 1.0000 17 1.116

6 1.0000 18 1.129
7 1.0000 19 1.141

8 1.0110 20 1.154
9 1.0220 21 1.166

10 1.0340 22 1.179

11 1.0450 23 1.192

12 1.0570 24 1.206

16 A.4.1.2.16 1 bh Ereksi Komponen Untuk Kolom Pracetak 814,241.45 854,411.36


A Tenaga 50,215.00 56,440.00
L.08 0.083 OH Operator Crane 150,000.00 175,000.00 12,450.00 14,525.00
L.09 0.083 OH Pembantu Operator Crane 95,000.00 105,000.00 7,885.00 8,715.00
L.01 0.083 OH Pekerja 75,000.00 85,000.00 6,225.00 7,055.00
L.02 0.083 OH Tukang Batu 95,000.00 105,000.00 7,885.00 8,715.00
L.02 0.166 OH Tukang Ereksi 95,000.00 105,000.00 15,770.00 17,430.00
L.03 0.083 OH Kepala Tukang 110,000.00 120,000.00 9,130.00 9,960.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00
B Bahan 70,354.50 72,837.60
8.277 Ltr Solar 8,500.00 8,800.00 70,354.50 72,837.60
C PERALATAN 619,650.00 647,460.00
0.083 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 377,650.00 383,460.00
2.200 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 242,000.00 264,000.00
D Jumlah A + B + C 740,219.50 776,737.60
E Overhead & Profit (contoh 10%) 10% 74,021.95 77,673.76
F Harga Satuan Pekerjaan (D+E) 814,241.45 854,411.36

file:///conversion/tmp/scratch/415837925.xls 175/64 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok

1 1.0000 13 1.162
2 1.0000 14 1.191

3 1.0000 15 1.221

4 1.0000 16 1.252

5 1.0000 17 1.284

6 1.0000 18 1.318

7 1.0000 19 1.350

8 1.0250 20 1.384

9 1.0510 21 1.419

10 1.0780 22 1.455

11 1.1050 23 1.492

12 1.1330 24 1.530

17 A.4.1.2.17 1 bh Langsiran Komponen untuk Plat Pracetak (± 20 m) 150,721.45 157,831.96


A Tenaga 34,445.00 39,010.00
L.08 0.083 OH Operator Crane 150,000.00 175,000.00 12,450.00 14,525.00
L.09 0.083 OH Pembantu Operator Crane 95,000.00 105,000.00 7,885.00 8,715.00
L.01 0.083 OH Pekerja 75,000.00 85,000.00 6,225.00 7,055.00
L.02 0.083 OH Tukang Batu 95,000.00 105,000.00 7,885.00 8,715.00
B Bahan 16,124.50 16,693.60
1.897 Ltr Solar 8,500.00 8,800.00 16,124.50 16,693.60
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 137,019.50 143,483.60
E Overhead & Profit (contoh 10%) 10% 13,701.95 14,348.36
F Harga Satuan Pekerjaan (D+E) 150,721.45 157,831.96

18 A.4.1.2.18 1 bh Langsiran Komponen untuk Balok Pracetak (± 20 m) 123,490.95 126,938.46


A Tenaga 9,690.00 10,925.00
L.08 0.019 OH Operator Crane 150,000.00 175,000.00 2,850.00 3,325.00
L.09 0.019 OH Pembantu Operator Crane 95,000.00 105,000.00 1,805.00 1,995.00
L.01 0.019 OH Pekerja 75,000.00 85,000.00 1,425.00 1,615.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
B Bahan 16,124.50 16,693.60
1.897 Ltr Solar 8,500.00 8,800.00 16,124.50 16,693.60
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 112,264.50 115,398.60
E Overhead & Profit (contoh 10%) 10% 11,226.45 11,539.86
F Harga Satuan Pekerjaan (D+E) 123,490.95 126,938.46

19 A.4.1.2.19 1 bh Langsiran Komponen untuk Kolom Pracetak (± 20 m) 123,490.95 126,938.46


A Tenaga 9,690.00 10,925.00
L.08 0.019 OH Operator Crane 150,000.00 175,000.00 2,850.00 3,325.00
L.09 0.019 OH Pembantu Operator Crane 95,000.00 105,000.00 1,805.00 1,995.00
L.01 0.019 OH Pekerja 75,000.00 85,000.00 1,425.00 1,615.00
L.02 0.038 OH Tukang Batu 95,000.00 105,000.00 3,610.00 3,990.00
B Bahan 16,124.50 16,693.60
1.897 Ltr Solar 8,500.00 8,800.00 16,124.50 16,693.60
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 112,264.50 115,398.60
E Overhead & Profit (contoh 10%) 10% 11,226.45 11,539.86
F Harga Satuan Pekerjaan (D+E) 123,490.95 126,938.46

20 A.4.1.2.20 1 m3 Bahan Grout Campuran 3,415,775.00 3,687,200.00


A Tenaga - -

B Bahan 3,105,250.00 3,352,000.00


1,200 Kg Semen Grout 1,500.00 1,650.00 1,800,000.00 1,980,000.00
650 kg Screening 2,000.00 2,100.00 1,300,000.00 1,365,000.00
350 Ltr Air 15.00 20.00 5,250.00 7,000.00
C PERALATAN - -
D Jumlah A + B + C 3,105,250.00 3,352,000.00
E Overhead & Profit (contoh 10%) 10% 310,525.00 335,200.00
F Harga Satuan Pekerjaan (D+E) 3,415,775.00 3,687,200.00

file:///conversion/tmp/scratch/415837925.xls 175/65 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.1.2.21 1 m3 Bahan Grout Campuran (tidak Campuran) 3,059,100.00 3,366,550.00
A Tenaga - -

B Bahan 2,781,000.00 3,060,500.00


1,850 Kg Semen Grout 1,500.00 1,650.00 2,775,000.00 3,052,500.00
400 Ltr Air 15.00 20.00 6,000.00 8,000.00
C PERALATAN - -
D Jumlah A + B + C 2,781,000.00 3,060,500.00
E Overhead & Profit (contoh 10%) 10% 278,100.00 306,050.00
F Harga Satuan Pekerjaan (D+E) 3,059,100.00 3,366,550.00

22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 51,375.50 56,633.50
A Tenaga 46,705.00 51,485.00
L.02 0.367 OH Tukang Batu 95,000.000 105,000.000 34,865.000 38,535.000
L.03 0.074 OH Kepala Tukang 110,000.000 120,000.000 8,140.000 8,880.000
L.04 0.037 OH Mandor 100,000.000 110,000.000 3,700.000 4,070.000

B Bahan - -

C PERALATAN - -
D Jumlah A + B + C 46,705.00 51,485.00
E Overhead & Profit (contoh 10%) 10% 4,670.50 5,148.50
F Harga Satuan Pekerjaan (D+E) 51,375.50 56,633.50

23 A.4.1.2.23 1 ttk Pemasangan Bekisting Joint Pra Cetak 112,530.00 129,470.00


A Tenaga 27,140.00 30,280.00
L.01 0.147 OH Pekerja 75,000.00 85,000.00 11,025.000 12,495.000
L.02 0.147 OH Tukang Batu 95,000.000 105,000.000 13,965.000 15,435.000
L.03 0.015 OH Kepala Tukang 110,000.000 120,000.000 1,650.000 1,800.000
L.04 0.005 OH Mandor 100,000.000 110,000.000 500.000 550.000
B Bahan 75,160.00 87,420.00
0.012 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 62,400.00 72,000.00
0.004 m3 Papan Cor 2,200,000.00 2,700,000.00 8,800.00 10,800.00
0.264 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 3,960.00 4,620.00
C PERALATAN - -
D Jumlah A + B + C 102,300.00 117,700.00
E Overhead & Profit (contoh 10%) 10% 10,230.00 11,770.00
F Harga Satuan Pekerjaan (D+E) 112,530.00 129,470.00

24 A.4.1.2.24 1 ttk Upah Pemasangan Joint dengan Sling 44,649.00 49,852.00


A Tenaga 40,590.00 45,320.00
L.01 0.220 OH Pekerja 75,000.00 85,000.00 16,500.000 18,700.000
L.02 0.022 OH Tukang Batu 95,000.000 105,000.000 2,090.000 2,310.000
L.02 0.220 OH Tukang Besi 95,000.000 105,000.000 20,900.000 23,100.000
L.04 0.011 OH Mandor 100,000.000 110,000.000 1,100.000 1,210.000
B Bahan

C PERALATAN - -
D Jumlah A + B + C 40,590.00 45,320.00
E Overhead & Profit (contoh 10%) 10% 4,059.00 4,532.00
F Harga Satuan Pekerjaan (D+E) 44,649.00 49,852.00

file:///conversion/tmp/scratch/415837925.xls 175/66 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 29,986.00 32,037.50
A Tenaga 11,160.00 12,450.00
L.01 0.06 OH Pekerja 75,000.00 85,000.00 4,500.00 5,100.00
L.02 0.06 OH Tukang Besi 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 16,100.00 16,675.00
1.15 Kg Besi Profil 14,000.00 14,500.00 16,100.00 16,675.00
C PERALATAN
D Jumlah A + B + C 27,260.00 29,125.00
E Overhead & Profit (contoh 10%) 10% 2,726.00 2,912.50
F Harga Satuan Pekerjaan (D+E) 29,986.00 32,037.50

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 24,546.50 25,839.00


A Tenaga 11,160.00 12,450.00
L.01 0.06 OH Pekerja 75,000.00 85,000.00 4,500.00 5,100.00
L.02 0.06 OH Tukang Besi 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 11,155.00 11,040.00
1.15 kg Besi Baja IWF 9,700.00 9,600.00 11,155.00 11,040.00
C PERALATAN
D Jumlah A + B + C 22,315.00 23,490.00
E Overhead & Profit (contoh 10%) 10% 2,231.50 2,349.00
F Harga Satuan Pekerjaan (D+E) 24,546.50 25,839.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 99,066.00 115,687.00


A Tenaga 17,610.00 19,670.00
L.01 0.100 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.100 OH Tukang Besi 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 120,000.00 110.00 120.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 12,450.00 13,500.00
1 ltr Solar 8,500.00 8,800.00 8,500.00 8,800.00
0.1 ltr Minyak Pelumas 39,500.00 47,000.00 3,950.00 4,700.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 90,060.00 105,170.00
E Overhead & Profit (contoh 10%) 10% 9,006.00 10,517.00
F Harga Satuan Pekerjaan (D+E) 99,066.00 115,687.00

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 864,930.00 906,422.00
rangka baja Siku
A Tenaga 195,250.00 217,820.00
L.01 1.05 OH Pekerja 75,000.00 85,000.00 78,750.00 89,250.00
L.02 1.05 OH Tukang Besi 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.052 OH Mandor 100,000.00 110,000.00 5,200.00 5,720.00
B Bahan 591,050.00 606,200.00
15 Kg Besi Siku L.30.30.3 9,700.00 9,600.00 145,500.00 144,000.00
32.8 Kg Besi Plat Baja 13,500.00 14,000.00 442,800.00 459,200.00
0.05 Kg Kawat Las 55,000.00 60,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 786,300.00 824,020.00
E Overhead & Profit (contoh 10%) 10% 78,630.00 82,402.00
F Harga Satuan Pekerjaan (D+E) 864,930.00 906,422.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 22,751.30 26,523.20


A Tenaga 5,320.00 5,960.00
L.01 0.04 OH Pekerja 75,000.00 85,000.00 3,000.00 3,400.00
L.02 0.02 OH Tukang Besi 95,000.00 105,000.00 1,900.00 2,100.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 2,613.00 2,852.00
0.04 kg Kawat Las 55,000.00 60,000.00 2,200.00 2,400.00
0.03 ltr Solar 8,500.00 8,800.00 255.00 264.00
0.004 ltr Minyak Pelumas 39,500.00 47,000.00 158.00 188.00

file:///conversion/tmp/scratch/415837925.xls 175/67 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 20,683.00 24,112.00
E Overhead & Profit (contoh 10%) 10% 2,068.30 2,411.20
F Harga Satuan Pekerjaan (D+E) 22,751.30 26,523.20

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 224,090.46 255,478.74


A Tenaga 120,850.00 134,820.00
L.01 0.65 OH Pekerja 75,000.00 85,000.00 48,750.00 55,250.00
L.02 0.65 OH Tukang Las Biasa 95,000.00 105,000.00 61,750.00 68,250.00
L.03 0.065 OH Kepala Tukang 110,000.00 120,000.00 7,150.00 7,800.00
L.04 0.032 OH Mandor 100,000.00 110,000.00 3,200.00 3,520.00
B Bahan 82,868.60 97,433.40
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,275.13 2,652.32 45,502.60 53,046.40
C PERALATAN
D Jumlah A + B + C 203,718.60 232,253.40
E Overhead & Profit (contoh 10%) 10% 20,371.86 23,225.34
F Harga Satuan Pekerjaan (D+E) 224,090.46 255,478.74

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 597,080.00 635,866.00


A Tenaga 217,800.00 243,060.00
L.01 1.2 OH Pekerja 75,000.00 85,000.00 90,000.00 102,000.00
L.02 1.2 OH Tukang Besi 95,000.00 105,000.00 114,000.00 126,000.00
L.03 0.12 OH Kepala Tukang 110,000.00 120,000.00 13,200.00 14,400.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 325,000.00 335,000.00
1 m2 Pintu Gulung Besi 325,000.00 335,000.00 325,000.00 335,000.00
C PERALATAN
D Jumlah A + B + C 542,800.00 578,060.00
E Overhead & Profit (contoh 10%) 10% 54,280.00 57,806.00
F Harga Satuan Pekerjaan (D+E) 597,080.00 635,866.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 530,024.00 567,930.00


A Tenaga 81,840.00 91,300.00
L.01 0.44 OH Pekerja 75,000.00 85,000.00 33,000.00 37,400.00
L.02 0.44 OH Tukang Besi 95,000.00 105,000.00 41,800.00 46,200.00
L.03 0.044 OH Kepala Tukang 110,000.00 120,000.00 4,840.00 5,280.00
L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00
B Bahan 400,000.00 425,000.00
1 m2 Pintu Lipat 400,000.00 425,000.00 400,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 481,840.00 516,300.00
E Overhead & Profit (contoh 10%) 10% 48,184.00 51,630.00
F Harga Satuan Pekerjaan (D+E) 530,024.00 567,930.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 485,320.00 550,924.00


A Tenaga 91,200.00 100,840.00
L.01 0.08 OH Pekerja 75,000.00 85,000.00 6,000.00 6,800.00
L.02 0.8 OH Tukang Besi 95,000.00 105,000.00 76,000.00 84,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 120,000.00 8,800.00 9,600.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 350,000.00 400,000.00
1 m2 Sunscreen Allumunium 350,000.00 400,000.00 350,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 441,200.00 500,840.00
E Overhead & Profit (contoh 10%) 10% 44,120.00 50,084.00
F Harga Satuan Pekerjaan (D+E) 485,320.00 550,924.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 507,100.00 547,250.00


A Tenaga 186,000.00 207,500.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 1 OH Tukang Besi 95,000.00 105,000.00 95,000.00 105,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 120,000.00 11,000.00 12,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

file:///conversion/tmp/scratch/415837925.xls 175/68 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 275,000.00 290,000.00


1 m2 Rolling Allumunium 275,000.00 290,000.00 275,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 461,000.00 497,500.00
E Overhead & Profit (contoh 10%) 10% 46,100.00 49,750.00
F Harga Satuan Pekerjaan (D+E) 507,100.00 547,250.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 116,592.30 130,478.70


A Tenaga 7,993.00 8,917.00
L.01 0.043 OH Pekerja 75,000.00 85,000.00 3,225.00 3,655.00
L.02 0.043 OH Tukang Besi 95,000.00 105,000.00 4,085.00 4,515.00
L.03 0.0043 OH Kepala Tukang 110,000.00 120,000.00 473.00 516.00
L.04 0.0021 OH Mandor 100,000.00 110,000.00 210.00 231.00
B Bahan 98,000.00 109,700.00
1.1 m' Profil Allumunium 85,000.00 95,000.00 93,500.00 104,500.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 105,993.00 118,617.00
E Overhead & Profit (contoh 10%) 10% 10,599.30 11,861.70
F Harga Satuan Pekerjaan (D+E) 116,592.30 130,478.70

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 501,055.50 559,495.20


A Tenaga 15,805.00 17,632.00
L.01 0.085 OH Pekerja 75,000.00 85,000.00 6,375.00 7,225.00
L.02 0.085 OH Tukang Besi 95,000.00 105,000.00 8,075.00 8,925.00
L.03 0.0085 OH Kepala Tukang 110,000.00 120,000.00 935.00 1,020.00
L.04 0.0042 OH Mandor 100,000.00 110,000.00 420.00 462.00
B Bahan 439,700.00 491,000.00
4.4 m' Profil Allumunium 85,000.00 95,000.00 374,000.00 418,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 455,505.00 508,632.00
E Overhead & Profit (contoh 10%) 10% 45,550.50 50,863.20
F Harga Satuan Pekerjaan (D+E) 501,055.50 559,495.20

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 468,534.00 526,878.00


A Tenaga 15,940.00 17,780.00
L.01 0.085 OH Pekerja 75,000.00 85,000.00 6,375.00 7,225.00
L.02 0.085 OH Tukang Besi 95,000.00 105,000.00 8,075.00 8,925.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 410,000.00 461,200.00
4.4 m' Pintu Allumunium 85,000.00 95,000.00 374,000.00 418,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 425,940.00 478,980.00
E Overhead & Profit (contoh 10%) 10% 42,594.00 47,898.00
F Harga Satuan Pekerjaan (D+E) 468,534.00 526,878.00

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 176,165.00 189,948.00


A Tenaga 65,150.00 72,680.00
L.01 0.35 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.35 OH Tukang Besi 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 160,150.00 172,680.00
E Overhead & Profit (contoh 10%) 10% 16,015.00 17,268.00
F Harga Satuan Pekerjaan (D+E) 176,165.00 189,948.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 501,127.02 555,250.11


A Tenaga 310,570.00 346,470.00
L.01 1.67 OH Pekerja 75,000.00 85,000.00 125,250.00 141,950.00
L.02 1.67 OH Tukang Las 95,000.00 105,000.00 158,650.00 175,350.00
L.03 0.167 OH Kepala Tukang 110,000.00 120,000.00 18,370.00 20,040.00
L.04 0.083 OH Mandor 100,000.00 110,000.00 8,300.00 9,130.00

file:///conversion/tmp/scratch/415837925.xls 175/69 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 145,000.02 158,302.83


6.177 kg Besi Strip 13,500.00 14,000.00 83,389.50 86,478.00
27.08 cm Pengelasan 2,275.13 2,652.32 61,610.52 71,824.83
C PERALATAN
D Jumlah A + B + C 455,570.02 504,772.83
E Overhead & Profit (contoh 10%) 10% 45,557.00 50,477.28
F Harga Satuan Pekerjaan (D+E) 501,127.02 555,250.11

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 95,526.96 111,915.40


A Tenaga 18,600.00 20,750.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.1 OH Tukang 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 68,242.69 80,991.28
1.1 m2 Kawat Nyamuk nylon 18,000.00 25,000.00 19,800.00 27,500.00
11.11 cm Pengelasan 2,275.13 2,652.32 25,276.69 29,467.28
1.716 kg Baja Strip (0,2x2) cm 13,500.00 14,000.00 23,166.00 24,024.00
C PERALATAN
D Jumlah A + B + C 86,842.69 101,741.28
E Overhead & Profit (contoh 10%) 10% 8,684.27 10,174.13
F Harga Satuan Pekerjaan (D+E) 95,526.96 111,915.40

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 126,280.00 138,886.00


A Tenaga 36,300.00 40,510.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 78,500.00 85,750.00
1.1 m2 Jendela Nako 35,000.00 37,500.00 38,500.00 41,250.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 114,800.00 126,260.00
E Overhead & Profit (contoh 10%) 10% 11,480.00 12,626.00
F Harga Satuan Pekerjaan (D+E) 126,280.00 138,886.00

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 186,092.50 217,126.25
cm
A Tenaga 56,750.00 63,100.00
L.01 0.20 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.4 OH Tukang Kayu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 112,425.00 134,287.50
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 225.00 262.50
0.019 m3 Kayu Papan Klas II atau III 4,800,000.00 5,700,000.00 91,200.00 108,300.00
C PERALATAN
D Jumlah A + B + C 169,175.00 197,387.50
E Overhead & Profit (contoh 10%) 10% 16,917.50 19,738.75
F Harga Satuan Pekerjaan (D+E) 186,092.50 217,126.25

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 70,620.00 80,751.00
BJLS 30 Lebar 45 cm
A Tenaga 36,300.00 40,510.00
L.01 0.20 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.20 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 27,900.00 32,900.00
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 150.00 175.00
0.5 Kg Besi strip 13,500.00 14,000.00 6,750.00 7,000.00
C PERALATAN
D Jumlah A + B + C 64,200.00 73,410.00
E Overhead & Profit (contoh 10%) 10% 6,420.00 7,341.00
F Harga Satuan Pekerjaan (D+E) 70,620.00 80,751.00

file:///conversion/tmp/scratch/415837925.xls 175/70 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 112,805.00 122,573.00
60x120 cm dinding partisi
A Tenaga 46,550.00 51,930.00
L.01 0.250 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.250 OH Tukang Besi 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 102,550.00 111,430.00
E Overhead & Profit (contoh 10%) 10% 10,255.00 11,143.00
F Harga Satuan Pekerjaan (D+E) 112,805.00 122,573.00

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 142,065.00 154,748.00
60x60 cm dinding plafond
A Tenaga 65,150.00 72,680.00
L.01 0.350 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.350 OH Tukang Besi 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 129,150.00 140,680.00
E Overhead & Profit (contoh 10%) 10% 12,915.00 14,068.00
F Harga Satuan Pekerjaan (D+E) 142,065.00 154,748.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 211,522.30 231,071.78
dingin Profil C75
A Tenaga 136,510.00 152,290.00
L.01 0.734 OH Pekerja 75,000.00 85,000.00 55,050.00 62,390.00
L.02 0.734 OH Tukang Besi 95,000.00 105,000.00 69,730.00 77,070.00
L.03 0.073 OH Kepala Tukang 110,000.00 120,000.00 8,030.00 8,760.00
L.04 0.037 OH Mandor 100,000.00 110,000.00 3,700.00 4,070.00
B Bahan 51,492.00 53,331.00
3.065 kg Baja Ringan Canal Dingin C75 14,000.00 14,500.00 42,910.00 44,442.50
C PERALATAN 4,291.00 4,444.25
10 % Peralatan *) harga bahan 42,910.00 44,442.50 4,291.00 4,444.25
D Jumlah A + B + C 192,293.00 210,065.25
E Overhead & Profit (contoh 10%) 10% 19,229.30 21,006.53
F Harga Satuan Pekerjaan (D+E) 211,522.30 231,071.78

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 236,651.80 257,530.35
Profil C75
A Tenaga 141,428.00 157,776.00
L.01 0.7604 OH Pekerja 75,000.00 85,000.00 57,030.00 64,634.00
L.02 0.7604 OH Tukang Besi 95,000.00 105,000.00 72,238.00 79,842.00
L.03 0.0760 OH Kepala Tukang 110,000.00 120,000.00 8,360.00 9,120.00
L.04 0.0380 OH Mandor 100,000.00 110,000.00 3,800.00 4,180.00
B Bahan 68,040.00 70,470.00
4.05 kg Baja Ringan Canal Dingin C75 14,000.00 14,500.00 56,700.00 58,725.00
C PERALATAN 5,670.00 5,872.50
10 % Peralatan *) harga bahan 56,700.00 58,725.00 5,670.00 5,872.50
D Jumlah A + B + C 215,138.00 234,118.50
E Overhead & Profit (contoh 10%) 10% 21,513.80 23,411.85
F Harga Satuan Pekerjaan (D+E) 236,651.80 257,530.35

file:///conversion/tmp/scratch/415837925.xls 175/71 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 248,875.00 273,157.50
Tebal 1 bata Camp. 1SP: 2PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 157,050.00 170,625.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
43.5 Kg Portland Semen (PC) 1,100.00 1,150.00 47,850.00 50,025.00
0.08 m3 Pasir Pasang (PP) 315,000.00 370,000.00 25,200.00 29,600.00
C PERALATAN
D Jumlah A + B + C 226,250.00 248,325.00
E Overhead & Profit (contoh 10%) 10% 22,625.00 24,832.50
F Harga Satuan Pekerjaan (D+E) 248,875.00 273,157.50
Overhead & Profit (contoh 10%)
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
2 A.4.4.1.2 1 m2 239,921.00 264,288.75
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 148,910.00 162,562.50
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
32.95 Kg Portland Semen (PC) 1,100.00 1,150.00 36,245.00 37,892.50
0.091 m3 Pasir Pasang (PP) 315,000.00 370,000.00 28,665.00 33,670.00
C PERALATAN
D Jumlah A + B + C 218,110.00 240,262.50
E Overhead & Profit (contoh 10%) 10% 21,811.00 24,026.25
F Harga Satuan Pekerjaan (D+E) 239,921.00 264,288.75

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 232,870.00 257,006.75
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 142,500.00 155,942.50
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
26.55 Kg Portland Semen (PC) 1,100.00 1,150.00 29,205.00 30,532.50
0.093 m3 Pasir Pasang (PP) 315,000.00 370,000.00 29,295.00 34,410.00
C PERALATAN
D Jumlah A + B + C 211,700.00 233,642.50
E Overhead & Profit (contoh 10%) 10% 21,170.00 23,364.25
F Harga Satuan Pekerjaan (D+E) 232,870.00 257,006.75

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 230,725.00 255,167.00
Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 140,550.00 154,270.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
22.2 Kg Portland Semen (PC) 1,100.00 1,150.00 24,420.00 25,530.00
0.102 m3 Pasir Pasang (PP) 315,000.00 370,000.00 32,130.00 37,740.00
C PERALATAN
D Jumlah A + B + C 209,750.00 231,970.00
E Overhead & Profit (contoh 10%) 10% 20,975.00 23,197.00
F Harga Satuan Pekerjaan (D+E) 230,725.00 255,167.00

file:///conversion/tmp/scratch/415837925.xls 175/72 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 233,178.00 258,626.50
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 142,780.00 157,415.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
18.5 Kg Portland Semen (PC) 1,100.00 1,150.00 20,350.00 21,275.00
0.122 m3 Pasir Pasang (PP) 315,000.00 370,000.00 38,430.00 45,140.00
C PERALATAN
D Jumlah A + B + C 211,980.00 235,115.00
E Overhead & Profit (contoh 10%) 10% 21,198.00 23,511.50
F Harga Satuan Pekerjaan (D+E) 233,178.00 258,626.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 221,843.05 245,346.20
Tebal 1 Bata Camp. 1SP : 3 KP :10PP
A Tenaga 69,200.00 77,700.00
L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 0.2 OH Tukang Batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 132,475.50 145,342.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
10.08 Kg Portland Semen (PC) 1,100.00 1,150.00 11,088.00 11,592.00
0.0925 m3 Pasir Pasang (PP) 315,000.00 370,000.00 29,137.50 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 201,675.50 223,042.00
E Overhead & Profit (contoh 10%) 10% 20,167.55 22,304.20
F Harga Satuan Pekerjaan (D+E) 221,843.05 245,346.20

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 120,356.50 132,222.75
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 74,815.00 81,352.50
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
18.95 Kg Portland Semen 1,100.00 1,150.00 20,845.00 21,792.50
0.038 m3 Pasir Pasang 315,000.00 370,000.00 11,970.00 14,060.00
C PERALATAN
D Jumlah A + B + C 109,415.00 120,202.50
E Overhead & Profit (contoh 10%) 10% 10,941.50 12,020.25
F Harga Satuan Pekerjaan (D+E) 120,356.50 132,222.75

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 115,507.70 127,243.05
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 70,407.00 76,825.50
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
14.37 Kg Portland Semen 1,100.00 1,150.00 15,807.00 16,525.50
0.04 m3 Pasir Pasang 315,000.00 370,000.00 12,600.00 14,800.00

file:///conversion/tmp/scratch/415837925.xls 175/73 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 105,007.00 115,675.50
E Overhead & Profit (contoh 10%) 10% 10,500.70 11,567.55
F Harga Satuan Pekerjaan (D+E) 115,507.70 127,243.05

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 113,074.50 124,833.50
Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 68,195.00 74,635.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
11.50 Kg Portland Semen 1,100.00 1,150.00 12,650.00 13,225.00
0.043 m3 Pasir Pasang 315,000.00 370,000.00 13,545.00 15,910.00
C PERALATAN
D Jumlah A + B + C 102,795.00 113,485.00
E Overhead & Profit (contoh 10%) 10% 10,279.50 11,348.50
F Harga Satuan Pekerjaan (D+E) 113,074.50 124,833.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 111,565.30 123,345.20
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 66,823.00 73,282.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
9.68 Kg Portland Semen 1,100.00 1,150.00 10,648.00 11,132.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 101,423.00 112,132.00
E Overhead & Profit (contoh 10%) 10% 10,142.30 11,213.20
F Harga Satuan Pekerjaan (D+E) 111,565.30 123,345.20

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 111,305.70 123,252.80
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 66,587.00 73,198.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
8.32 Kg Portland Semen 1,100.00 1,150.00 9,152.00 9,568.00
0.049 m3 Pasir Pasang 315,000.00 370,000.00 15,435.00 18,130.00
C PERALATAN
D Jumlah A + B + C 101,187.00 112,048.00
E Overhead & Profit (contoh 10%) 10% 10,118.70 11,204.80
F Harga Satuan Pekerjaan (D+E) 111,305.70 123,252.80

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 109,450.00 121,357.50
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 64,900.00 71,475.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
6.50 Kg Portland Semen 1,100.00 1,150.00 7,150.00 7,475.00
0.05 m3 Pasir Pasang 315,000.00 370,000.00 15,750.00 18,500.00

file:///conversion/tmp/scratch/415837925.xls 175/74 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 99,500.00 110,325.00
E Overhead & Profit (contoh 10%) 10% 9,950.00 11,032.50
F Harga Satuan Pekerjaan (D+E) 109,450.00 121,357.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 111,980.00 123,942.50
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 67,200.00 73,825.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
4.5 Kg Portland Semen 1,100.00 1,150.00 4,950.00 5,175.00
0.05 m3 Pasir Pasang 315,000.00 370,000.00 15,750.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 101,800.00 112,675.00
E Overhead & Profit (contoh 10%) 10% 10,180.00 11,267.50
F Harga Satuan Pekerjaan (D+E) 111,980.00 123,942.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 100,397.00 110,209.00
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 56,670.00 61,340.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.018 m3 Semen Merah 200,000.00 200,000.00 3,600.00 3,600.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 91,270.00 100,190.00
E Overhead & Profit (contoh 10%) 10% 9,127.00 10,019.00
F Harga Satuan Pekerjaan (D+E) 100,397.00 110,209.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 101,662.00 112,035.00
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 57,820.00 63,000.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.014 m3 Semen Merah 200,000.00 200,000.00 2,800.00 2,800.00
0.028 m3 Pasir Pasang 315,000.00 370,000.00 8,820.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 92,420.00 101,850.00
E Overhead & Profit (contoh 10%) 10% 9,242.00 10,185.00
F Harga Satuan Pekerjaan (D+E) 101,662.00 112,035.00

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 395,364.20 450,607.30
A Tenaga 43,950.00 49,280.00
L.01 0.350 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

file:///conversion/tmp/scratch/415837925.xls 175/75 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 315,472.00 360,363.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,100.00 1,150.00 33,352.00 34,868.00
0.728 m3 Pasir Pasang 315,000.00 370,000.00 229,320.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 359,422.00 409,643.00
E Overhead & Profit (contoh 10%) 10% 35,942.20 40,964.30
F Harga Satuan Pekerjaan (D+E) 395,364.20 450,607.30

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 403,277.60 460,849.40
A Tenaga 43,950.00 49,280.00
L.01 0.350 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.150 OH Tukang Batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

B Bahan 322,666.00 369,674.00


12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,100.00 1,150.00 26,686.00 27,899.00
0.772 m3 Pasir Pasang 315,000.00 370,000.00 243,180.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 366,616.00 418,954.00
E Overhead & Profit (contoh 10%) 10% 36,661.60 41,895.40
F Harga Satuan Pekerjaan (D+E) 403,277.60 460,849.40

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 311,447.40 354,102.10
A Tenaga 38,320.00 43,000.00
L.01 0.320 OH Pekerja 75,000.00 85,000.00 24,000.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 244,814.00 278,911.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,100.00 1,150.00 25,014.00 26,151.00
0.550 m3 Pasir Pasang 315,000.00 370,000.00 173,250.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 283,134.00 321,911.00
E Overhead & Profit (contoh 10%) 10% 28,313.40 32,191.10
F Harga Satuan Pekerjaan (D+E) 311,447.40 354,102.10

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 317,042.00 361,383.00
A Tenaga 38,320.00 43,000.00
L.01 0.320 OH Pekerja 75,000.00 85,000.00 24,000.00 27,200.00
L.02 0.120 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 249,900.00 285,530.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,100.00 1,150.00 20,020.00 20,930.00
0.582 m3 Pasir Pasang 315,000.00 370,000.00 183,330.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 288,220.00 328,530.00
E Overhead & Profit (contoh 10%) 10% 28,822.00 32,853.00
F Harga Satuan Pekerjaan (D+E) 317,042.00 361,383.00

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 251,609.60 288,996.40
A Tenaga 34,600.00 38,850.00
L.01 0.300 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

file:///conversion/tmp/scratch/415837925.xls 175/76 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 194,136.00 223,874.00
12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
15.160 kg PC 1,100.00 1,150.00 16,676.00 17,434.00
0.364 m3 Pasir Pasang 315,000.00 370,000.00 114,660.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 228,736.00 262,724.00
E Overhead & Profit (contoh 10%) 10% 22,873.60 26,272.40
F Harga Satuan Pekerjaan (D+E) 251,609.60 288,996.40

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 256,259.30 294,931.45
A Tenaga 34,600.00 38,850.00
L.01 0.300 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

B Bahan 198,363.00 229,269.50


12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
12.130 kg PC 1,100.00 1,150.00 13,343.00 13,949.50
0.388 m3 Pasir Pasang 315,000.00 370,000.00 122,220.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 10,750.00 2,800.00 3,010.00
C PERALATAN
D Jumlah A + B + C 232,963.00 268,119.50
E Overhead & Profit (contoh 10%) 10% 23,296.30 26,811.95
F Harga Satuan Pekerjaan (D+E) 256,259.30 294,931.45

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 248,125.00 385,600.00
30 Buah Terawang / Roster 7,500.00 12,000.00 225,000.00 360,000.00
11 kg Portland Semen 1,100.00 1,150.00 12,100.00 12,650.00
0.035 m3 Pasir Pasang 315,000.00 370,000.00 11,025.00 12,950.00
C PERALATAN
D Jumlah A + B + C 282,725.00 424,450.00
E Overhead & Profit (contoh 10%) 10% 28,272.50 42,445.00
F Harga Satuan Pekerjaan (D+E) 310,997.50 466,895.00

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 310,997.50 466,895.00
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 248,125.00 385,600.00
30 Buah Terawang / Roster 7,500.00 12,000.00 225,000.00 360,000.00
11 kg Portland Semen 1,100.00 1,150.00 12,100.00 12,650.00
0.035 m3 Pasir Pasang 315,000.00 370,000.00 11,025.00 12,950.00
C PERALATAN
D Jumlah A + B + C 282,725.00 424,450.00
E Overhead & Profit (contoh 10%) 10% 28,272.50 42,445.00
F Harga Satuan Pekerjaan (D+E) 310,997.50 466,895.00

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 143,088.00 154,319.00
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 34,600.00 38,850.00
L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.1 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

file:///conversion/tmp/scratch/415837925.xls 175/77 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 95,480.00 101,440.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,100.00 1,150.00 15,400.00 16,100.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00
C PERALATAN
D Jumlah A + B + C 130,080.00 140,290.00
E Overhead & Profit (contoh 10%) 10% 13,008.00 14,029.00
F Harga Satuan Pekerjaan (D+E) 143,088.00 154,319.00

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 266,333.54 291,571.56
Mortar Siap Pakai
m2 Tenaga 0.075 188,350.00 209,380.00
L.01 0.67 OH Pekerja 0.12 725000 75,000.00 85,000.00 50,250.00 56,950.00
L.02 1.3 OH Tukang Batu 1 6525 95,000.00 105,000.00 123,500.00 136,500.00
L.03 0.13 OH Kepala Tukang 13.3333333333 110,000.00 120,000.00 14,300.00 15,600.00
L.04 0.003 OH Mandor 111.1111111111 100,000.00 110,000.00 300.00 330.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 242,121.40 265,065.05
E Overhead & Profit (contoh 10%) 10% 24,212.14 26,506.51
F Harga Satuan Pekerjaan (D+E) 266,333.54 291,571.56

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 269,465.24 292,711.71
Mortar Siap Pakai
m2 Tenaga 0.075 175,555.00 195,425.00
L.01 0.671 OH Pekerja 0.12 700000 75,000.00 85,000.00 50,325.00 57,035.00
L.02 1.300 OH Tukang Batu 0.1 8400 95,000.00 105,000.00 123,500.00 136,500.00
L.03 0.013 OH Kepala Tukang 10 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.003 OH Mandor 83.3333333333 100,000.00 110,000.00 300.00 330.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 244,968.40 266,101.55
E Overhead & Profit (contoh 10%) 10% 24,496.84 26,610.16
F Harga Satuan Pekerjaan (D+E) 269,465.24 292,711.71

file:///conversion/tmp/scratch/415837925.xls 175/78 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 68,193.84 75,294.56
A Tenaga 39,900.00 44,700.00

L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 22,094.40 23,749.60
15.504 Kg Portland Semen 1,100.00 1,150.00 17,054.40 17,829.60
0.016 m3 Pasir Pasang 315,000.00 370,000.00 5,040.00 5,920.00
C PERALATAN
D Jumlah A + B + C 61,994.40 68,449.60
E Overhead & Profit (contoh 10%) 10% 6,199.44 6,844.96
F Harga Satuan Pekerjaan (D+E) 68,193.84 75,294.56
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 63,191.04 70,243.36
A Tenaga 39,900.00 44,700.00
L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 17,546.40 19,157.60
10.224 Kg Portland Semen 1,100.00 1,150.00 11,246.40 11,757.60
0.020 m3 Pasir Pasang 315,000.00 370,000.00 6,300.00 7,400.00
C PERALATAN
D Jumlah A + B + C 57,446.40 63,857.60
E Overhead & Profit (contoh 10%) 10% 5,744.64 6,385.76
F Harga Satuan Pekerjaan (D+E) 63,191.04 70,243.36

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 61,268.46 68,367.64


A Tenaga 39,900.00 44,700.00

L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 15,798.60 17,452.40
7.776 Kg Portland Semen 1,100.00 1,150.00 8,553.60 8,942.40
0.023 m3 Pasir Pasang 315,000.00 370,000.00 7,245.00 8,510.00
C PERALATAN
D Jumlah A + B + C 55,698.60 62,152.40
E Overhead & Profit (contoh 10%) 10% 5,569.86 6,215.24
F Harga Satuan Pekerjaan (D+E) 61,268.46 68,367.64

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 59,756.40 66,831.60


A Tenaga 39,900.00 44,700.00

L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 14,424.00 16,056.00
6.240 Kg Portland Semen 1,100.00 1,150.00 6,864.00 7,176.00
0.024 m3 Pasir Pasang 315,000.00 370,000.00 7,560.00 8,880.00
C PERALATAN
D Jumlah A + B + C 54,324.00 60,756.00
E Overhead & Profit (contoh 10%) 10% 5,432.40 6,075.60
F Harga Satuan Pekerjaan (D+E) 59,756.40 66,831.60

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 59,171.64 66,309.76


A Tenaga 39,900.00 44,700.00
L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00
L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 13,892.40 15,581.60
5.184 Kg Portland Semen 1,100.00 1,150.00 5,702.40 5,961.60
0.026 m3 Pasir Pasang 315,000.00 370,000.00 8,190.00 9,620.00
C PERALATAN
D Jumlah A + B + C 53,792.40 60,281.60
E Overhead & Profit (contoh 10%) 10% 5,379.24 6,028.16
F Harga Satuan Pekerjaan (D+E) 59,171.64 66,309.76

file:///conversion/tmp/scratch/415837925.xls 175/79 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 58,588.86 65,745.24
Tenaga 39,900.00 44,700.00

L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00


L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 13,362.60 15,068.40
4.416 Kg Portland Semen 1,100.00 1,150.00 4,857.60 5,078.40
0.027 m3 Pasir Pasang 315,000.00 370,000.00 8,505.00 9,990.00
C PERALATAN
D Jumlah A + B + C 53,262.60 59,768.40
E Overhead & Profit (contoh 10%) 10% 5,326.26 5,976.84
F Harga Satuan Pekerjaan (D+E) 58,588.86 65,745.24

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 58,354.56 65,545.04


A Tenaga 39,900.00 44,700.00
L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 13,149.60 14,886.40
3.936 Kg Portland Semen 1,100.00 1,150.00 4,329.60 4,526.40
0.028 m3 Pasir Pasang 315,000.00 370,000.00 8,820.00 10,360.00
C PERALATAN
D Jumlah A + B + C 53,049.60 59,586.40
E Overhead & Profit (contoh 10%) 10% 5,304.96 5,958.64
F Harga Satuan Pekerjaan (D+E) 58,354.56 65,545.04

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 58,120.26 65,344.84


A Tenaga 39,900.00 44,700.00

L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


B Bahan 12,936.60 14,704.40
3.456 Kg Portland Semen 1,100.00 1,150.00 3,801.60 3,974.40
0.029 m3 Pasir Pasang 315,000.00 370,000.00 9,135.00 10,730.00
C PERALATAN
D Jumlah A + B + C 52,836.60 59,404.40
E Overhead & Profit (contoh 10%) 10% 5,283.66 5,940.44
F Harga Satuan Pekerjaan (D+E) 58,120.26 65,344.84

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 58,136.10 64,882.40


A Tenaga 41,520.00 46,620.00

L.01 0.36 OH Pekerja 75,000.00 85,000.00 27,000.00 30,600.00

L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00


L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 11,331.00 12,364.00
5.760 Kg Portland Semen 1,100.00 1,150.00 6,336.00 6,624.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 315,000.00 370,000.00 4,095.00 4,810.00
C PERALATAN
D Jumlah A + B + C 52,851.00 58,984.00
E Overhead & Profit (contoh 10%) 10% 5,285.10 5,898.40
F Harga Satuan Pekerjaan (D+E) 58,136.10 64,882.40

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 57,882.00 64,922.00


A Tenaga 41,520.00 46,620.00
L.01 0.36 OH Pekerja 75,000.00 85,000.00 27,000.00 30,600.00
L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 11,100.00 12,400.00
3 kg Portland Semen 1,100.00 1,150.00 3,300.00 3,450.00
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 315,000.00 370,000.00 6,300.00 7,400.00
C PERALATAN
D Jumlah A + B + C 52,620.00 59,020.00
E Overhead & Profit (contoh 10%) 10% 5,262.00 5,902.00
F Harga Satuan Pekerjaan (D+E) 57,882.00 64,922.00

file:///conversion/tmp/scratch/415837925.xls 175/80 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 53,740.50 59,994.00
A Tenaga 41,520.00 46,620.00
L.01 0.36 OH Pekerja 75,000.00 85,000.00 27,000.00 30,600.00
L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00

L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00


B Bahan 7,335.00 7,920.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 315,000.00 370,000.00 2,835.00 3,330.00
C PERALATAN
D Jumlah A + B + C 48,855.00 54,540.00
E Overhead & Profit (contoh 10%) 10% 4,885.50 5,454.00
F Harga Satuan Pekerjaan (D+E) 53,740.50 59,994.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 54,719.50 61,314.00


A Tenaga 41,520.00 46,620.00

L.01 0.36 OH Pekerja 75,000.00 85,000.00 27,000.00 30,600.00

L.02 0.12 OH Tukang batu 95,000.00 105,000.00 11,400.00 12,600.00

L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00

L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00


B Bahan 8,225.00 9,120.00
0.007 m3 Semen Merah 200,000.00 200,000.00 1,400.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 315,000.00 370,000.00 4,725.00 5,550.00
C PERALATAN
D Jumlah A + B + C 49,745.00 55,740.00
E Overhead & Profit (contoh 10%) 10% 4,974.50 5,574.00
F Harga Satuan Pekerjaan (D+E) 54,719.50 61,314.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 84,590.22 94,035.48


A Tenaga 53,400.00 59,820.00

L.01 0.40 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00

L.02 0.20 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 23,500.20 25,666.80
13.632 kg Portland Semen 1,100.00 1,150.00 14,995.20 15,676.80
0.027 m3 Pasir Pasang 315,000.00 370,000.00 8,505.00 9,990.00
C PERALATAN
D Jumlah A + B + C 76,900.20 85,486.80
E Overhead & Profit (contoh 10%) 10% 7,690.02 8,548.68
F Harga Satuan Pekerjaan (D+E) 84,590.22 94,035.48

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 63,169.80 70,323.20


A Tenaga 42,000.00 46,930.00
L.01 0.26 OH Pekerja 75,000.00 85,000.00 19,500.00 22,100.00
L.02 0.2 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 21,169.80 23,393.20
10.368 Kg Portland Semen 1,100.00 1,150.00 11,404.80 11,923.20
0.031 m3 Pasir Pasang 315,000.00 370,000.00 9,765.00 11,470.00
C PERALATAN
D Jumlah A + B + C 64,469.80 71,753.20
E Overhead & Profit (contoh 10%) 10% 6,446.98 7,175.32
F Harga Satuan Pekerjaan (D+E) 70,916.78 78,928.52

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 79,895.20 89,350.80


A Tenaga 53,400.00 59,820.00

L.01 0.40 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00

L.02 0.20 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 19,232.00 21,408.00
8.320 kg Portland Semen 1,100.00 1,150.00 9,152.00 9,568.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00

file:///conversion/tmp/scratch/415837925.xls 175/81 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 72,632.00 81,228.00
E Overhead & Profit (contoh 10%) 10% 7,263.20 8,122.80
F Harga Satuan Pekerjaan (D+E) 79,895.20 89,350.80

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 79,231.02 88,790.68


A Tenaga 53,400.00 59,820.00

L.01 0.400 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00

L.02 0.200 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 18,628.20 20,898.80
6.912 Kg Portland Semen 1,100.00 1,150.00 7,603.20 7,948.80
0.035 m3 Pasir Pasang 315,000.00 370,000.00 11,025.00 12,950.00
C PERALATAN
D Jumlah A + B + C 72,028.20 80,718.80
E Overhead & Profit (contoh 10%) 10% 7,202.82 8,071.88
F Harga Satuan Pekerjaan (D+E) 79,231.02 88,790.68

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 78,338.48 87,902.32


A Tenaga 53,400.00 59,820.00

L.01 0.40 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00


L.02 0.2 OH Tukang batu 95,000.00 105,000.00 19,000.00 21,000.00

L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 17,816.80 20,091.20
5.888 Kg Portland Semen 1,100.00 1,150.00 6,476.80 6,771.20
0.036 m3 Pasir Pasang 315,000.00 370,000.00 11,340.00 13,320.00
C PERALATAN
D Jumlah A + B + C 71,216.80 79,911.20
E Overhead & Profit (contoh 10%) 10% 7,121.68 7,991.12
F Harga Satuan Pekerjaan (D+E) 78,338.48 87,902.32

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 75,559.00 84,491.00


A Tenaga 58,520.00 65,560.00

L.01 0.440 OH Pekerja 75,000.00 85,000.00 33,000.00 37,400.00

L.02 0.22 OH Tukang batu 95,000.00 105,000.00 20,900.00 23,100.00

L.03 0.022 OH Kepala Tukang 110,000.00 120,000.00 2,420.00 2,640.00

L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00


B Bahan 10,170.00 11,250.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
C PERALATAN
D Jumlah A + B + C 68,690.00 76,810.00
E Overhead & Profit (contoh 10%) 10% 6,869.00 7,681.00
F Harga Satuan Pekerjaan (D+E) 75,559.00 84,491.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 37,342.14 41,851.26


A Tenaga 20,055.00 22,465.00

L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00

L.02 0.075 OH Tukang batu 95,000.00 105,000.00 7,125.00 7,875.00

L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00


L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 13,892.40 15,581.60
5.184 Kg Portland Semen 1,100.00 1,150.00 5,702.40 5,961.60
0.026 m3 Pasir Pasang 315,000.00 370,000.00 8,190.00 9,620.00
C PERALATAN
D Jumlah A + B + C 33,947.40 38,046.60
E Overhead & Profit (contoh 10%) 10% 3,394.74 3,804.66
F Harga Satuan Pekerjaan (D+E) 37,342.14 41,851.26

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 58,789.50 65,367.50

A Tenaga 48,800.00 54,040.00

L.01 0.080 OH Pekerja 75,000.00 85,000.00 6,000.00 6,800.00


L.02 0.40 OH Tukang batu 95,000.00 105,000.00 38,000.00 42,000.00

L.03 0.040 OH Kepala Tukang 110,000.00 120,000.00 4,400.00 4,800.00

L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00

file:///conversion/tmp/scratch/415837925.xls 175/82 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,645.00 5,385.00
0.5 Kg Portland Semen 1,100.00 1,150.00 550.00 575.00
0.013 m3 Pasir Pasang 315,000.00 370,000.00 4,095.00 4,810.00
C PERALATAN
D Jumlah A + B + C 53,445.00 59,425.00
E Overhead & Profit (contoh 10%) 10% 5,344.50 5,942.50
F Harga Satuan Pekerjaan (D+E) 58,789.50 65,367.50

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 94,550.50 104,681.50
mm
A Tenaga 59,955.00 67,165.00
L.01 0.450 OH Pekerja 75,000.00 85,000.00 33,750.00 38,250.00
L.02 0.225 OH Tukang batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
B Bahan 26,000.00 28,000.00
10 Kg Portland Semen 1,100.00 1,150.00 11,000.00 11,500.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 85,955.00 95,165.00
E Overhead & Profit (contoh 10%) 10% 8,595.50 9,516.50
F Harga Satuan Pekerjaan (D+E) 94,550.50 104,681.50

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 94,550.50 104,681.50

A Tenaga 59,955.00 67,165.00


L.01 0.450 OH Pekerja 75,000.00 85,000.00 33,750.00 38,250.00
L.02 0.225 OH Tukang batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
B Bahan 26,000.00 28,000.00
10 Kg Portland Semen 1,100.00 1,150.00 11,000.00 11,500.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 85,955.00 95,165.00
E Overhead & Profit (contoh 10%) 10% 8,595.50 9,516.50
F Harga Satuan Pekerjaan (D+E) 94,550.50 104,681.50

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 45,366.20 50,641.80


Tenaga 34,600.00 38,850.00

L.01 0.30 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.1 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00

L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 6,642.00 7,188.00
4.32 Kg Portland Semen 1,100.00 1,150.00 4,752.00 4,968.00
0.006 m3 Pasir Pasang 315,000.00 370,000.00 1,890.00 2,220.00
C PERALATAN
D Jumlah A + B + C 41,242.00 46,038.00
E Overhead & Profit (contoh 10%) 10% 4,124.20 4,603.80
F Harga Satuan Pekerjaan (D+E) 45,366.20 50,641.80

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 25,821.18 28,643.12
Merah
A Tenaga 20,055.00 22,465.00

L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00

L.02 0.075 OH Tukang batu 95,000.00 105,000.00 7,125.00 7,875.00

L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00


L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 3,418.80 3,574.20
3.108 Kg Portland Semen 1,100.00 1,150.00 3,418.80 3,574.20
C PERALATAN
D Jumlah A + B + C 23,473.80 26,039.20
E Overhead & Profit (contoh 10%) 10% 2,347.38 2,603.92
F Harga Satuan Pekerjaan (D+E) 25,821.18 28,643.12

file:///conversion/tmp/scratch/415837925.xls 175/83 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 12,292.50 13,623.50
ekspose
A Tenaga 9,415.00 10,545.00

L.01 0.070 OH Pekerja 75,000.00 85,000.00 5,250.00 5,950.00

L.02 0.035 OH Tukang batu 95,000.00 105,000.00 3,325.00 3,675.00


L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00

L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00


B Bahan 1,760.00 1,840.00
1.600 Kg Portland Semen 1,100.00 1,150.00 1,760.00 1,840.00
C PERALATAN
D Jumlah A + B + C 11,175.00 12,385.00
E Overhead & Profit (contoh 10%) 10% 1,117.50 1,238.50
F Harga Satuan Pekerjaan (D+E) 12,292.50 13,623.50

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 55,719.40 62,074.10
2Pp
Tenaga 39,900.00 44,700.00

L.01 0.3 OH Pekerja 75,000.00 85,000.00 22,500.00 25,500.00

L.02 0.15 OH Tukang batu 95,000.00 105,000.00 14,250.00 15,750.00

L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00

L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00


Bahan 10,754.00 11,731.00
6.34 Kg Portland Semen 1,100.00 1,150.00 6,974.00 7,291.00
0.012 m3 Pasir Pasang 315,000.00 370,000.00 3,780.00 4,440.00
C PERALATAN
D Jumlah A + B + C 50,654.00 56,431.00
E Overhead & Profit (contoh 10%) 10% 5,065.40 5,643.10
F Harga Satuan Pekerjaan (D+E) 55,719.40 62,074.10

27 A.4.4.2.27 1 m2 Pemasangan Acian 33,192.50 36,891.25

Tenaga 26,600.00 29,800.00


L.01 0.20 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 3,575.00 3,737.50
3.25 Kg Portland Semen 1,100.00 1,150.00 3,575.00 3,737.50
C PERALATAN
D Jumlah A + B + C 30,175.00 33,537.50
E Overhead & Profit (contoh 10%) 10% 3,017.50 3,353.75
F Harga Satuan Pekerjaan (D+E) 33,192.50 36,891.25

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 41,813.20 45,681.90

Tenaga 26,600.00 29,800.00


L.01 0.20 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 38,012.00 41,529.00
E Overhead & Profit (contoh 10%) 10% 3,801.20 4,152.90
F Harga Satuan Pekerjaan (D+E) 41,813.20 45,681.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 35,695.00 39,393.75


Tenaga 26,600.00 29,800.00
L.01 0.20 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.10 OH Tukang batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 32,450.00 35,812.50
E Overhead & Profit (contoh 10%) 10% 3,245.00 3,581.25
F Harga Satuan Pekerjaan (D+E) 35,695.00 39,393.75

file:///conversion/tmp/scratch/415837925.xls 175/84 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan


VIII A.4.4.3
DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 105,928.00 117,172.50


A Tenaga 33,355.00 37,365.00
L.01 0.25 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.125 OH Tukang Batu 95,000.00 105,000.00 11,875.00 13,125.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 62,943.18 69,155.45
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,181.82 3,454.55 37,768.18 41,005.45
10.0 Kg Portland Semen 0.3 1,100.00 1,150.00 11,000.00 11,500.00
0.0450 m3 Pasir Pasang 0.09 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 96,298.18 106,520.45
E Overhead & Profit (contoh 10%) 10% 9,629.82 10,652.05
F Harga Satuan Pekerjaan (D+E) 105,928.00 117,172.50

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 107,437.00 118,992.50


A Tenaga 36,015.00 40,345.00
L.01 0.27 OH Pekerja 75,000.00 85,000.00 20,250.00 22,950.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.014 OH Kepala Tukang 110,000.00 120,000.00 1,540.00 1,680.00
L.04 0.014 OH Mandor 100,000.00 110,000.00 1,400.00 1,540.00
B Bahan 61,655.00 67,830.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 1,480.00 36,040.00 39,220.00
10.4 Kg Portland Semen 1,100.00 1,150.00 11,440.00 11,960.00
0.0450 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 97,670.00 108,175.00
E Overhead & Profit (contoh 10%) 10% 9,767.00 10,817.50
F Harga Satuan Pekerjaan (D+E) 107,437.00 118,992.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 131,360.50 155,305.00


A Tenaga 34,580.00 38,740.00
L.01 0.26 OH Pekerja 75,000.00 85,000.00 19,500.00 22,100.00
L.02 0.130 OH Tukang Batu 95,000.00 105,000.00 12,350.00 13,650.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 84,838.64 102,446.36
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,363.64 43,163.64 51,796.36
10.0 Kg Portland Semen 1,100.00 1,150.00 11,000.00 11,500.00
1.50 Kg Semen warna 11,000.00 15,000.00 16,500.00 22,500.00
0.0450 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 119,418.64 141,186.36
E Overhead & Profit (contoh 10%) 10% 11,941.86 14,118.64

F Harga Satuan Pekerjaan (D+E) 131,360.50 155,305.00

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 133,452.00 155,050.50


A Tenaga 36,015.00 40,345.00
L.01 0.27 OH Pekerja 75,000.00 85,000.00 20,250.00 22,950.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.014 OH Kepala Tukang 110,000.00 120,000.00 1,540.00 1,680.00
L.04 0.014 OH Mandor 100,000.00 110,000.00 1,400.00 1,540.00
B Bahan 85,305.00 100,610.00
26.5 Buah Ubin Warna 20x20 cm 1,580.00 1,800.00 41,870.00 47,700.00
10.4 Kg Portland Semen 1,100.00 1,150.00 11,440.00 11,960.00
1.62 Kg Semen warna 11,000.00 15,000.00 17,820.00 24,300.00
0.0450 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 121,320.00 140,955.00
E Overhead & Profit (contoh 10%) 10% 12,132.00 14,095.50
F Harga Satuan Pekerjaan (D+E) 133,452.00 155,050.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 347,281.00 397,138.50
A Tenaga 33,355.00 37,365.00
L.01 0.250 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.125 OH Tukang Batu 95,000.00 105,000.00 11,875.00 13,125.00
L.03 0.013 OH Kepala Tukang 110,000.00 120,000.00 1,430.00 1,560.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 282,355.00 323,670.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 41,666.67 243,100.00 276,250.00
9.8 Kg Portland Semen 0.16 1,100.00 1,150.00 10,780.00 11,270.00
1.300 Kg Semen warna 6.25 11,000.00 15,000.00 14,300.00 19,500.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 315,710.00 361,035.00
E Overhead & Profit (contoh 10%) 10% 31,571.00 36,103.50
F Harga Satuan Pekerjaan (D+E) 347,281.00 397,138.50

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 65,294.90 75,466.60

A Tenaga 16,790.00 18,730.00


L.01 0.090 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 42,569.00 49,876.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,100.00 1,150.00 1,364.00 1,426.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 59,359.00 68,606.00
E Overhead & Profit (contoh 10%) 10% 5,935.90 6,860.60
F Harga Satuan Pekerjaan (D+E) 65,294.90 75,466.60

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 37,255.90 40,948.60


A Tenaga 16,790.00 18,730.00
L.01 0.090 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 17,079.00 18,496.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,100.00 1,150.00 1,254.00 1,311.00
0.100 Kg Semen Warna 11,000.00 15,000.00 1,100.00 1,500.00
0.003 m3 Pasir Pasang 315,000.00 370,000.00 945.00 1,110.00
C PERALATAN
D Jumlah A + B + C 33,869.00 37,226.00
E Overhead & Profit (contoh 10%) 10% 3,386.90 3,722.60
F Harga Satuan Pekerjaan (D+E) 37,255.90 40,948.60

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 219,487.40 272,732.35


A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 106,434.00 143,638.50
53.00 Buah Keramik 10 x 20 cm 1,000.00 1,440.00 53,000.00 76,320.00

8.19 Kg Portland Semen 1,100.00 1,150.00 9,009.00 9,418.50


2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
0.0450 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 199,534.00 247,938.50
E Overhead & Profit (contoh 10%) 10% 19,953.40 24,793.85
F Harga Satuan Pekerjaan (D+E) 219,487.40 272,732.35
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 224,932.40 280,157.35
A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.350 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 111,384.00 150,388.50
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 500.00 720.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,100.00 1,150.00 9,009.00 9,418.50
3.20 Kg Semen Warna 11,000.00 15,000.00 35,200.00 48,000.00
0.0450 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 204,484.00 254,688.50
E Overhead & Profit (contoh 10%) 10% 20,448.40 25,468.85
F Harga Satuan Pekerjaan (D+E) 224,932.40 280,157.35

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 218,403.29 265,468.68


A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 105,448.44 137,035.17
10 Buah Ubin Keramik 33 x 33 cm 6,444.44 8,666.67 64,444.44 86,666.67
8.19 Kg Portland Semen 1,100.00 1,150.00 9,009.00 9,418.50

0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00


1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
C PERALATAN
D Jumlah A + B + C 198,548.44 241,335.17
E Overhead & Profit (contoh 10%) 10% 19,854.84 24,133.52
F Harga Satuan Pekerjaan (D+E) 218,403.29 265,468.68

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 214,724.50 263,031.00


A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 102,104.09 134,819.09
11.87 Buah Ubin Keramik 30 x 30 cm 5,090.91 7,090.91 60,429.09 84,169.09
10.00 Kg Portland Semen 1,100.00 1,150.00 11,000.00 11,500.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
1.50 Kg Semen Warna 11,000.00 15,000.00 16,500.00 22,500.00
C PERALATAN
D Jumlah A + B + C 195,204.09 239,119.09
E Overhead & Profit (contoh 10%) 10% 19,520.41 23,911.91
F Harga Satuan Pekerjaan (D+E) 214,724.50 263,031.00

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 215,484.50 261,547.00


A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 102,795.00 133,470.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,240.00 3,040.00 59,360.00 80,560.00
10.40 Kg Portland Semen 1,100.00 1,150.00 11,440.00 11,960.00
1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 195,895.00 237,770.00
E Overhead & Profit (contoh 10%) 10% 19,589.50 23,777.00
F Harga Satuan Pekerjaan (D+E) 215,484.50 261,547.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 413,578.00 461,620.50
variasi / border
A Tenaga 137,955.00 154,585.00
L.01 1.05 OH Pekerja 75,000.00 85,000.00 78,750.00 89,250.00
L.02 0.525 OH Tukang Batu 95,000.00 105,000.00 49,875.00 55,125.00
L.03 0.053 OH Kepala Tukang 110,000.00 120,000.00 5,830.00 6,360.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 238,025.00 265,070.00
33.0 Buah Ubin Keramik 5,000.00 5,200.00 165,000.00 171,600.00
9.80 Kg Portland Semen 1,100.00 1,150.00 10,780.00 11,270.00
4.37 Kg Semen Warna 11,000.00 15,000.00 48,070.00 65,550.00
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
C PERALATAN
D Jumlah A + B + C 375,980.00 419,655.00
E Overhead & Profit (contoh 10%) 10% 37,598.00 41,965.50
F Harga Satuan Pekerjaan (D+E) 413,578.00 461,620.50

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 35,765.40 41,168.60


A Tenaga 16,790.00 18,730.00
L.01 0.09 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 15,724.00 18,696.00
5.3 Buah Ubin Keramik 2,500.00 3,000.00 13,250.00 15,900.00
1.14 Kg Portland Semen 1,100.00 1,150.00 1,254.00 1,311.00
0.003 m3 Pasir Pasang 315,000.00 370,000.00 945.00 1,110.00
0.025 Kg Semen Warna 11,000.00 15,000.00 275.00 375.00
C PERALATAN
D Jumlah A + B + C 32,514.00 37,426.00
E Overhead & Profit (contoh 10%) 10% 3,251.40 3,742.60
F Harga Satuan Pekerjaan (D+E) 35,765.40 41,168.60

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 82,124.90 88,221.10


A Tenaga 16,790.00 18,730.00
L.01 0.09 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 57,869.00 61,471.00
10.6 Buah Ubin Keramik 5,200.00 5,500.00 55,120.00 58,300.00
1.14 Kg Portland Semen 1,100.00 1,150.00 1,254.00 1,311.00
0.003 m3 Pasir Pasang 315,000.00 370,000.00 945.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 74,659.00 80,201.00
E Overhead & Profit (contoh 10%) 10% 7,465.90 8,020.10
F Harga Satuan Pekerjaan (D+E) 82,124.90 88,221.10

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 79,792.90 87,055.10


A Tenaga 16,790.00 18,730.00
L.01 0.09 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.09 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 55,749.00 60,411.00
10.6 Buah Ubin Keramik 5,000.00 5,400.00 53,000.00 57,240.00
1.14 Kg Portland Semen 1,100.00 1,150.00 1,254.00 1,311.00
0.003 m3 Pasir Pasang 315,000.00 370,000.00 945.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 72,539.00 79,141.00
E Overhead & Profit (contoh 10%) 10% 7,253.90 7,914.10
F Harga Satuan Pekerjaan (D+E) 79,792.90 87,055.10
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 689,627.40 713,810.35
A Tenaga 93,100.00 104,300.00
L.01 0.7 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 533,834.00 544,618.50
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,100.00 1,150.00 9,009.00 9,418.50
0.045 m3 Pasir Pasang 315,000.00 370,000.00 14,175.00 16,650.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 626,934.00 648,918.50
E Overhead & Profit (contoh 10%) 10% 62,693.40 64,891.85
F Harga Satuan Pekerjaan (D+E) 689,627.40 713,810.35

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 200,387.00 214,038.00


A Tenaga 31,670.00 35,330.00
L.01 0.17 OH Pekerja 75,000.00 85,000.00 12,750.00 14,450.00
L.02 0.17 OH Tukang Batu 95,000.00 105,000.00 16,150.00 17,850.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 182,170.00 194,580.00
E Overhead & Profit (contoh 10%) 10% 18,217.00 19,458.00
F Harga Satuan Pekerjaan (D+E) 200,387.00 214,038.00

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 381,260.00 515,680.00


A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 253,500.00 364,500.00
1.05 m2 Parquet Jati 210,000.00 310,000.00 220,500.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 346,600.00 468,800.00
E Overhead & Profit (contoh 10%) 10% 34,660.00 46,880.00
F Harga Satuan Pekerjaan (D+E) 381,260.00 515,680.00

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 245,518.66 277,972.82


A Tenaga 133,000.00 149,000.00
L.01 1.00 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 0.50 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.050 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 90,198.78 103,702.56
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,100.00 1,150.00 10,230.00 10,695.00

2.750 Kg Semen Warna 0.0121 11,000.00 15,000.00 30,250.00 41,250.00

0.018 m3 Pasir Pasang 0.11 315,000.00 370,000.00 5,670.00 6,660.00


C PERALATAN
D Jumlah A + B + C 223,198.78 252,702.56
E Overhead & Profit (contoh 10%) 10% 22,319.88 25,270.26
F Harga Satuan Pekerjaan (D+E) 245,518.66 277,972.82

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 240,735.00 295,927.50


A Tenaga 119,700.00 134,100.00
L.01 0.9 OH Pekerja 75,000.00 85,000.00 67,500.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 99,150.00 134,925.00
53 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,100.00 1,150.00 10,230.00 10,695.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 218,850.00 269,025.00
E Overhead & Profit (contoh 10%) 10% 21,885.00 26,902.50
F Harga Satuan Pekerjaan (D+E) 240,735.00 295,927.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 235,554.00 283,266.50


A Tenaga 119,700.00 134,100.00
L.01 0.9 OH Pekerja 75,000.00 85,000.00 67,500.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 94,440.00 123,415.00
26.0 Buah Keramik 2,200.00 2,960.00 57,200.00 76,960.00
9.3 Kg Portland Semen 1,100.00 1,150.00 10,230.00 10,695.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 214,140.00 257,515.00
E Overhead & Profit (contoh 10%) 10% 21,414.00 25,751.50
F Harga Satuan Pekerjaan (D+E) 235,554.00 283,266.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 240,735.00 295,927.50


A Tenaga 119,700.00 134,100.00
L.01 0.9 OH Pekerja 75,000.00 85,000.00 67,500.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 99,150.00 134,925.00
53.0 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,100.00 1,150.00 10,230.00 10,695.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 218,850.00 269,025.00
E Overhead & Profit (contoh 10%) 10% 21,885.00 26,902.50
F Harga Satuan Pekerjaan (D+E) 240,735.00 295,927.50

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 236,764.00 284,894.50


A Tenaga 119,700.00 134,100.00
L.01 0.9 OH Pekerja 75,000.00 85,000.00 67,500.00 76,500.00
L.02 0.45 OH Tukang Batu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00
B Bahan 95,540.00 124,895.00
26.5 Buah Keramik 2,200.00 2,960.00 58,300.00 78,440.00
9.3 Kg Portland Semen 1,100.00 1,150.00 10,230.00 10,695.00
0.018 m3 Pasir Pasang 315,000.00 370,000.00 5,670.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 215,240.00 258,995.00
E Overhead & Profit (contoh 10%) 10% 21,524.00 25,899.50
F Harga Satuan Pekerjaan (D+E) 236,764.00 284,894.50

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 775,735.52 809,502.22


A Tenaga 172,900.00 193,700.00
L.01 1.3 OH Pekerja 75,000.00 85,000.00 97,500.00 110,500.00
L.02 0.65 OH Tukang Batu 95,000.00 105,000.00 61,750.00 68,250.00
L.03 0.065 OH Kepala Tukang 110,000.00 120,000.00 7,150.00 7,800.00
L.04 0.065 OH Mandor 100,000.00 110,000.00 6,500.00 7,150.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 532,314.11 542,211.11
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 35.00 35.00 105.11 105.11
12.44 kg Portlan Semen 1,100.00 1,150.00 13,684.00 14,306.00
0.025 m3 Pasir Pasang 315,000.00 370,000.00 7,875.00 9,250.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 705,214.11 735,911.11
E Overhead & Profit (contoh 10%) 10% 70,521.41 73,591.11
F Harga Satuan Pekerjaan (D+E) 775,735.52 809,502.22

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 261,855.00 282,988.75
A Tenaga 93,100.00 104,300.00
L.01 0.70 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 0.35 OH Tukang Batu 95,000.00 105,000.00 33,250.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 120,000.00 3,850.00 4,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 144,950.00 152,962.50
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,100.00 1,150.00 12,925.00 13,512.50
0.035 m3 Pasir Pasang 315,000.00 370,000.00 11,025.00 12,950.00
C PERALATAN
D Jumlah A + B + C 238,050.00 257,262.50
E Overhead & Profit (contoh 10%) 10% 23,805.00 25,726.25
F Harga Satuan Pekerjaan (D+E) 261,855.00 282,988.75

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 145,517.90 158,169.00


A Tenaga 44,945.00 50,385.00
L.01 0.35 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.175 OH Tukang Batu 95,000.00 105,000.00 16,625.00 18,375.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 132,289.00 143,790.00
E Overhead & Profit (contoh 10%) 10% 13,228.90 14,379.00
F Harga Satuan Pekerjaan (D+E) 145,517.90 158,169.00

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 115,384.50 124,888.50


A Tenaga 44,945.00 50,385.00
L.01 0.35 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 0.175 OH Tukang Batu 95,000.00 105,000.00 16,625.00 18,375.00
L.03 0.017 OH Kepala Tukang 110,000.00 120,000.00 1,870.00 2,040.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 59,950.00 63,150.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 11,000.00 15,000.00 2,750.00 3,750.00
C PERALATAN
D Jumlah A + B + C 104,895.00 113,535.00
E Overhead & Profit (contoh 10%) 10% 10,489.50 11,353.50
F Harga Satuan Pekerjaan (D+E) 115,384.50 124,888.50

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 46,002.00 57,310.00
Tenaga 22,320.00 24,900.00
L.01 0.12 OH Pekerja 75,000.00 85,000.00 9,000.00 10,200.00
L.02 0.12 OH Tukang Batu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
Bahan 19,500.00 27,200.00
0.003 m3 Papan Kayu Klas II 6,250,000.00 8,800,000.00 18,750.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 41,820.00 52,100.00
E Overhead & Profit (contoh 10%) 10% 4,182.00 5,210.00
F Harga Satuan Pekerjaan (D+E) 46,002.00 57,310.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 167,458.50 184,198.30


Tenaga 71,880.00 79,893.00
L.01 0.25 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 73,050.00 79,600.00
1.01 m2 Paving Block Tebal 6 Cm 55,000.00 60,000.00 55,550.00 60,600.00
0.05 m3 Pasir Beton 350,000.00 380,000.00 17,500.00 19,000.00
C PERALATAN 7,305.00 7,960.00
10 % Peralatan 73,050.00 79,600.00 7,305.00 7,960.00
D Jumlah A + B + C 152,235.00 167,453.00
E Overhead & Profit (contoh 10%) 10% 15,223.50 16,745.30
F Harga Satuan Pekerjaan (D+E) 167,458.50 184,198.30

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 227,106.00 247,321.80


Tenaga 90,630.00 101,143.00
L.01 0.5 OH Pekerja 75,000.00 85,000.00 37,500.00 42,500.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 105,300.00 112,450.00
1.01 m2 Paving Block Tebal 8 Cm 80,000.00 85,000.00 80,800.00 85,850.00
0.07 m3 Pasir Beton 350,000.00 380,000.00 24,500.00 26,600.00
C PERALATAN 10,530.00 11,245.00
10 % Peralatan 105,300.00 112,450.00 10,530.00 11,245.00
D Jumlah A + B + C 206,460.00 224,838.00
E Overhead & Profit (contoh 10%) 10% 20,646.00 22,483.80
F Harga Satuan Pekerjaan (D+E) 227,106.00 247,321.80

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 179,679.50 196,419.30


Tenaga 71,880.00 79,893.00
L.01 0.25 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 83,150.00 89,700.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 65,000.00 70,000.00 65,650.00 70,700.00
0.05 m3 Pasir Beton 350,000.00 380,000.00 17,500.00 19,000.00
C PERALATAN 8,315.00 8,970.00
10 % Peralatan 83,150.00 89,700.00 8,315.00 8,970.00
D Jumlah A + B + C 163,345.00 178,563.00
E Overhead & Profit (contoh 10%) 10% 16,334.50 17,856.30
F Harga Satuan Pekerjaan (D+E) 179,679.50 196,419.30

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 233,216.50 253,432.30


Tenaga 90,630.00 101,143.00
L.01 0.5 OH Pekerja 75,000.00 85,000.00 37,500.00 42,500.00
L.02 0.5 OH Tukang Batu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0013 OH Mandor 100,000.00 110,000.00 130.00 143.00
Bahan 110,350.00 117,500.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 85,000.00 90,000.00 85,850.00 90,900.00
0.07 m3 Pasir Beton 350,000.00 380,000.00 24,500.00 26,600.00
C PERALATAN 11,035.00 11,750.00
10 % Peralatan 110,350.00 117,500.00 11,035.00 11,750.00
D Jumlah A + B + C 212,015.00 230,393.00
E Overhead & Profit (contoh 10%) 10% 21,201.50 23,039.30
F Harga Satuan Pekerjaan (D+E) 233,216.50 253,432.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 30,602.00 33,060.50
mm, 5 mm & 6 mm

A Tenaga 10,070.00 11,180.00


L.01 0.03 OH Pekerja 75,000.00 85,000.00 2,250.00 2,550.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 17,750.00 18,875.00
1.1 Lbr Plat Asbes 16,000.00 17,000.00 17,600.00 18,700.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 27,820.00 30,055.00
E Overhead & Profit (contoh 10%) 10% 2,782.00 3,005.50
F Harga Satuan Pekerjaan (D+E) 30,602.00 33,060.50
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 101,937.00 110,192.50
A Tenaga 22,320.00 24,900.00
L.01 0.12 OH Pekerja 75,000.00 85,000.00 9,000.00 10,200.00
L.02 0.12 OH Tukang Kayu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 70,350.00 75,275.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,200.00 69,600.00 74,400.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 92,670.00 100,175.00
E Overhead & Profit (contoh 10%) 10% 9,267.00 10,017.50
F Harga Satuan Pekerjaan (D+E) 101,937.00 110,192.50

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 105,501.00 114,383.50


A Tenaga 18,600.00 20,750.00
L.01 0.10 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 77,310.00 83,235.00
5.80 Lbr Akustik 13,200.00 14,200.00 76,560.00 82,360.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 95,910.00 103,985.00
E Overhead & Profit (contoh 10%) 10% 9,591.00 10,398.50
F Harga Satuan Pekerjaan (D+E) 105,501.00 114,383.50

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 90,585.00 99,687.50


A Tenaga 18,600.00 20,750.00
L.01 0.10 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 63,750.00 69,875.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 82,350.00 90,625.00
E Overhead & Profit (contoh 10%) 10% 8,235.00 9,062.50
F Harga Satuan Pekerjaan (D+E) 90,585.00 99,687.50

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 45,705.00 54,340.00
mm, 4 mm & 6 mm

A Tenaga 18,600.00 20,750.00


L.01 0.10 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.10 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00

file:///conversion/tmp/scratch/415837925.xls 175/93 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 22,950.00 28,650.00
0.375 Lbr Tripleks (4 mm) 60,000.00 75,000.00 22,500.00 28,125.00
0.03 Kg Paku Tripleks 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 41,550.00 49,400.00
E Overhead & Profit (contoh 10%) 10% 4,155.00 4,940.00
F Harga Satuan Pekerjaan (D+E) 45,705.00 54,340.00

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 526,845.00 562,292.50


A Tenaga 148,800.00 166,000.00
L.01 0.8 OH Pekerja 75,000.00 85,000.00 60,000.00 68,000.00
L.02 0.8 OH Tukang Kayu 95,000.00 105,000.00 76,000.00 84,000.00
L.03 0.08 OH Kepala Tukang 110,000.00 120,000.00 8,800.00 9,600.00
L.04 0.04 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 330,150.00 345,175.00
0.015 m3 Kayu Jati,Papan 22,000,000.00 23,000,000.00 330,000.00 345,000.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 478,950.00 511,175.00
E Overhead & Profit (contoh 10%) 10% 47,895.00 51,117.50
F Harga Satuan Pekerjaan (D+E) 526,845.00 562,292.50

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 40,469.00 45,492.70
tebal 9 mm

A Tenaga 13,300.00 14,900.00


L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 23,490.00 26,457.00
0.364 Lbr Gypsum Board 60,000.00 68,000.00 21,840.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 36,790.00 41,357.00
E Overhead & Profit (contoh 10%) 10% 3,679.00 4,135.70
F Harga Satuan Pekerjaan (D+E) 40,469.00 45,492.70

Memasang Langit-langit Akustik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 211,365.00 232,430.00
Rangka Allumunium

A Tenaga 93,000.00 103,750.00


L.01 0.5 OH Pekerja 75,000.00 85,000.00 37,500.00 42,500.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.025 OH Mandor 100,000.00 110,000.00 2,500.00 2,750.00
B Bahan 99,150.00 107,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 192,150.00 211,300.00
E Overhead & Profit (contoh 10%) 10% 19,215.00 21,130.00
F Harga Satuan Pekerjaan (D+E) 211,365.00 232,430.00

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 15,994.00 17,440.50


A Tenaga 9,350.00 10,430.00
L.01 0.05 OH Pekerja 75,000.00 85,000.00 3,750.00 4,250.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 5,190.00 5,425.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 14,540.00 15,855.00
E Overhead & Profit (contoh 10%) 10% 1,454.00 1,585.50
F Harga Satuan Pekerjaan (D+E) 15,994.00 17,440.50

file:///conversion/tmp/scratch/415837925.xls 175/94 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 85,250.00 96,145.50
A Tenaga 20,000.00 22,405.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.0075 OH Kepala Tukang 110,000.00 120,000.00 825.00 900.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 57,500.00 65,000.00
25 Buah Genteng Plentong 2,300.00 2,600.00 57,500.00 65,000.00
C PERALATAN
D Jumlah A + B + C 77,500.00 87,405.00
E Overhead & Profit (contoh 10%) 10% 7,750.00 8,740.50
F Harga Satuan Pekerjaan (D+E) 85,250.00 96,145.50
Overhead & Profit (contoh 10%)
2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 138,935.50 144,336.50
A Tenaga 20,055.00 22,465.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 106,250.00 108,750.00
25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00
C PERALATAN
D Jumlah A + B + C 126,305.00 131,215.00
E Overhead & Profit (contoh 10%) 10% 12,630.50 13,121.50
F Harga Satuan Pekerjaan (D+E) 138,935.50 144,336.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 123,040.50 130,641.50


A Tenaga 20,055.00 22,465.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 91,800.00 96,300.00
12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 111,855.00 118,765.00
E Overhead & Profit (contoh 10%) 10% 11,185.50 11,876.50
F Harga Satuan Pekerjaan (D+E) 123,040.50 130,641.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 100,683.00 110,451.00


A Tenaga 51,400.00 57,620.00
L.01 0.4 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 40,130.00 42,790.00
5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00
8 Kg Portland Semen 1,100.00 1,150.00 8,800.00 9,200.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00
C PERALATAN
D Jumlah A + B + C 91,530.00 100,410.00
E Overhead & Profit (contoh 10%) 10% 9,153.00 10,041.00
F Harga Satuan Pekerjaan (D+E) 100,683.00 110,451.00

file:///conversion/tmp/scratch/415837925.xls 175/95 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 113,058.00 123,926.00
A Tenaga 51,400.00 57,620.00
L.01 0.4 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 51,380.00 55,040.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,100.00 1,150.00 8,800.00 9,200.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00
C PERALATAN
D Jumlah A + B + C 102,780.00 112,660.00
E Overhead & Profit (contoh 10%) 10% 10,278.00 11,266.00
F Harga Satuan Pekerjaan (D+E) 113,058.00 123,926.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 116,908.00 127,006.00


A Tenaga 51,400.00 57,620.00
L.01 0.4 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 54,880.00 57,840.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,100.00 1,150.00 8,800.00 9,200.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00
C PERALATAN
D Jumlah A + B + C 106,280.00 115,460.00
E Overhead & Profit (contoh 10%) 10% 10,628.00 11,546.00
F Harga Satuan Pekerjaan (D+E) 116,908.00 127,006.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 103,493.50 115,962.00


A Tenaga 18,335.00 20,545.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.067 OH Tukang Kayu 95,000.00 105,000.00 6,365.00 7,035.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 75,750.00 84,875.00
0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00
0.05 Kg Paku Biasa 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 94,085.00 105,420.00
E Overhead & Profit (contoh 10%) 10% 9,408.50 10,542.00
F Harga Satuan Pekerjaan (D+E) 103,493.50 115,962.00

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 62,606.50 70,614.50
mm

A Tenaga 19,305.00 21,615.00


L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 37,610.00 42,580.00
0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,915.00 64,195.00
E Overhead & Profit (contoh 10%) 10% 5,691.50 6,419.50
F Harga Satuan Pekerjaan (D+E) 62,606.50 70,614.50

file:///conversion/tmp/scratch/415837925.xls 175/96 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 64,438.00 72,776.00
mm

A Tenaga 18,620.00 20,860.00


L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,580.00 66,160.00
E Overhead & Profit (contoh 10%) 10% 5,858.00 6,616.00
F Harga Satuan Pekerjaan (D+E) 64,438.00 72,776.00

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 64,768.00 73,436.00
mm

A Tenaga 18,620.00 20,860.00


L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 40,260.00 45,900.00
0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,880.00 66,760.00
E Overhead & Profit (contoh 10%) 10% 5,888.00 6,676.00
F Harga Satuan Pekerjaan (D+E) 64,768.00 73,436.00

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 72,028.00 76,274.00
mm

A Tenaga 18,620.00 20,860.00


L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 46,860.00 48,480.00
0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 65,480.00 69,340.00
E Overhead & Profit (contoh 10%) 10% 6,548.00 6,934.00
F Harga Satuan Pekerjaan (D+E) 72,028.00 76,274.00

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 55,060.50 58,619.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 31,435.00 32,430.00
0.35 Lbr Asbes Gelombang 84,500.00 87,000.00 29,575.00 30,450.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 50,055.00 53,290.00
E Overhead & Profit (contoh 10%) 10% 5,005.50 5,329.00
F Harga Satuan Pekerjaan (D+E) 55,060.50 58,619.00

file:///conversion/tmp/scratch/415837925.xls 175/97 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 57,178.00 62,546.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 33,360.00 36,000.00
0.42 Lbr Asbes Gelombang 75,000.00 81,000.00 31,500.00 34,020.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 51,980.00 56,860.00
E Overhead & Profit (contoh 10%) 10% 5,198.00 5,686.00
F Harga Satuan Pekerjaan (D+E) 57,178.00 62,546.00

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 53,988.00 59,972.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 30,460.00 33,660.00
0.44 Lbr Asbes Gelombang 65,000.00 72,000.00 28,600.00 31,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 49,080.00 54,520.00
E Overhead & Profit (contoh 10%) 10% 4,908.00 5,452.00
F Harga Satuan Pekerjaan (D+E) 53,988.00 59,972.00

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 55,907.50 60,467.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 32,205.00 34,110.00
0.51 Lbr Asbes Gelombang 59,500.00 63,000.00 30,345.00 32,130.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 50,825.00 54,970.00
E Overhead & Profit (contoh 10%) 10% 5,082.50 5,497.00
F Harga Satuan Pekerjaan (D+E) 55,907.50 60,467.00

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 59,488.00 66,484.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 35,460.00 39,580.00
0.80 Lbr Asbes Gelombang 42,000.00 47,000.00 33,600.00 37,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,080.00 60,440.00
E Overhead & Profit (contoh 10%) 10% 5,408.00 6,044.00
F Harga Satuan Pekerjaan (D+E) 59,488.00 66,484.00

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 64,449.00 67,859.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/scratch/415837925.xls 175/98 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 58,590.00 61,690.00
E Overhead & Profit (contoh 10%) 10% 5,859.00 6,169.00
F Harga Satuan Pekerjaan (D+E) 64,449.00 67,859.00

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 67,804.00 71,324.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,640.00 64,840.00
E Overhead & Profit (contoh 10%) 10% 6,164.00 6,484.00
F Harga Satuan Pekerjaan (D+E) 67,804.00 71,324.00

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 64,636.00 68,684.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,760.00 62,440.00
E Overhead & Profit (contoh 10%) 10% 5,876.00 6,244.00
F Harga Satuan Pekerjaan (D+E) 64,636.00 68,684.00

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 65,648.00 69,861.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 59,680.00 63,510.00
E Overhead & Profit (contoh 10%) 10% 5,968.00 6,351.00
F Harga Satuan Pekerjaan (D+E) 65,648.00 69,861.00

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 69,553.00 73,403.00
mm
A Tenaga 18,620.00 20,860.00
L.01 0.14 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 63,230.00 66,730.00
E Overhead & Profit (contoh 10%) 10% 6,323.00 6,673.00
F Harga Satuan Pekerjaan (D+E) 69,553.00 73,403.00

file:///conversion/tmp/scratch/415837925.xls 175/99 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 102,355.00 118,057.50
A Tenaga 26,600.00 29,800.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 66,450.00 77,525.00
11 Lbr Genteng Beton Standrad 6,000.00 7,000.00 66,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 93,050.00 107,325.00
E Overhead & Profit (contoh 10%) 10% 9,305.00 10,732.50
F Harga Satuan Pekerjaan (D+E) 102,355.00 118,057.50

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 218,603.00 244,293.50


A Tenaga 44,830.00 49,960.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 153,900.00 172,125.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 86,000.00 26,250.00 30,100.00
0.03 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 198,730.00 222,085.00
E Overhead & Profit (contoh 10%) 10% 19,873.00 22,208.50
F Harga Satuan Pekerjaan (D+E) 218,603.00 244,293.50

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 88,660.00 103,950.00


A Tenaga 26,600.00 29,800.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 54,000.00 64,700.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 80,600.00 94,500.00
E Overhead & Profit (contoh 10%) 10% 8,060.00 9,450.00
F Harga Satuan Pekerjaan (D+E) 88,660.00 103,950.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 108,075.00 115,214.00


A Tenaga 39,750.00 44,240.00
L.01 0.166 OH Pekerja 75,000.00 85,000.00 12,450.00 14,110.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 58,500.00 60,500.00
30 Lbr Genteng Sirap 1,850.00 1,900.00 55,500.00 57,000.00
0.2 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 98,250.00 104,740.00
E Overhead & Profit (contoh 10%) 10% 9,825.00 10,474.00
F Harga Satuan Pekerjaan (D+E) 108,075.00 115,214.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 122,001.00 131,901.00


A Tenaga 53,200.00 59,600.00
L.01 0.4 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.02 OH Mandor 100,000.00 110,000.00 2,000.00 2,200.00
B Bahan 57,710.00 60,310.00
3.5 Buah Nok Genteng Beton 10,000.00 10,050.00 35,000.00 35,175.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
10.8 Kg Portland Semen 1,100.00 1,150.00 11,880.00 12,420.00
0.032 m3 Pasir Pasang 315,000.00 370,000.00 10,080.00 11,840.00
1 Kg Semen Warna 11,000.00 15,000.00 11,000.00 15,000.00

file:///conversion/tmp/scratch/415837925.xls 175/100 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 110,910.00 119,910.00
E Overhead & Profit (contoh 10%) 10% 11,091.00 11,991.00
F Harga Satuan Pekerjaan (D+E) 122,001.00 131,901.00

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 122,567.50 134,651.00


A Tenaga 36,475.00 40,535.00
L.01 0.125 OH Pekerja 75,000.00 85,000.00 9,375.00 10,625.00
L.02 0.250 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 74,950.00 81,875.00
2.0 Buah Nok Genteng Beton 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
0.0035 m3 Balok Kayu 5,200,000.00 6,000,000.00 18,200.00 21,000.00
C PERALATAN
D Jumlah A + B + C 111,425.00 122,410.00
E Overhead & Profit (contoh 10%) 10% 11,142.50 12,241.00
F Harga Satuan Pekerjaan (D+E) 122,567.50 134,651.00

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 64,570.00 72,440.50


A Tenaga 35,950.00 40,230.00
L.01 0.250 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.150 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 22,750.00 25,625.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 58,700.00 65,855.00
E Overhead & Profit (contoh 10%) 10% 5,870.00 6,585.50
F Harga Satuan Pekerjaan (D+E) 64,570.00 72,440.50

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 53,377.50 59,906.00


A Tenaga 36,475.00 40,535.00
L.01 0.125 OH Pekerja 75,000.00 85,000.00 9,375.00 10,625.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 12,050.00 13,925.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 10,400.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 900.00 1,050.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 48,525.00 54,460.00
E Overhead & Profit (contoh 10%) 10% 4,852.50 5,446.00
F Harga Satuan Pekerjaan (D+E) 53,377.50 59,906.00

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 37,906.00 43,153.00


A Tenaga 15,960.00 17,880.00
L.01 0.12 OH Pekerja 75,000.00 85,000.00 9,000.00 10,200.00
L.02 0.06 OH Tukang Kayu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 18,500.00 21,350.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,000.00 30,000.00 18,200.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 300.00 350.00
C PERALATAN
D Jumlah A + B + C 34,460.00 39,230.00
E Overhead & Profit (contoh 10%) 10% 3,446.00 3,923.00
F Harga Satuan Pekerjaan (D+E) 37,906.00 43,153.00

file:///conversion/tmp/scratch/415837925.xls 175/101 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 30,437.00 34,430.00
A Tenaga 19,270.00 21,600.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.07 OH Tukang Kayu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 8,400.00 9,700.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 7,800.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 600.00 700.00
C PERALATAN
D Jumlah A + B + C 27,670.00 31,300.00
E Overhead & Profit (contoh 10%) 10% 2,767.00 3,130.00
F Harga Satuan Pekerjaan (D+E) 30,437.00 34,430.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 32,945.00 38,753.00


A Tenaga 17,350.00 19,480.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 12,600.00 15,750.00
1.05 m2 Sisalation / Allumunium Foil 12,000.00 15,000.00 12,600.00 15,750.00
C PERALATAN
D Jumlah A + B + C 29,950.00 35,230.00
E Overhead & Profit (contoh 10%) 10% 2,995.00 3,523.00
F Harga Satuan Pekerjaan (D+E) 32,945.00 38,753.00

file:///conversion/tmp/scratch/415837925.xls 175/102 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 27,298,975.00 28,250,612.50
Kayu klas I
A Tenaga 2,786,000.00 3,090,500.00
L.01 7 OH Pekerja 75,000.00 85,000.00 525,000.00 595,000.00
L.02 21 OH Tukang Kayu 95,000.00 105,000.00 1,995,000.00 2,205,000.00
L.03 2.10 OH Kepala Tukang 110,000.00 120,000.00 231,000.00 252,000.00
L.04 0.35 OH Mandor 100,000.00 110,000.00 35,000.00 38,500.00
B Bahan 22,031,250.00 22,591,875.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,000,000.00 20,500,000.00 22,000,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 24,817,250.00 25,682,375.00
E Overhead & Profit (contoh 10%) 10% 2,481,725.00 2,568,237.50
F Harga Satuan Pekerjaan (D+E) 27,298,975.00 28,250,612.50

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 10,713,175.00 12,859,962.50
Kayu klas II atau III
Tenaga 2,388,000.00 2,649,000.00
L.01 6.00 OH Pekerja 75,000.00 85,000.00 450,000.00 510,000.00
L.02 18.00 OH Tukang Kayu 95,000.00 105,000.00 1,710,000.00 1,890,000.00
L.03 1.80 OH Kepala Tukang 110,000.00 120,000.00 198,000.00 216,000.00
L.04 0.30 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
Bahan 7,351,250.00 9,041,875.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,100,000.00 7,500,000.00 7,320,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 9,739,250.00 11,690,875.00
E Overhead & Profit (contoh 10%) 10% 973,925.00 1,169,087.50
F Harga Satuan Pekerjaan (D+E) 10,713,175.00 12,859,962.50

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 470,910.00 514,200.50
Kayu Klas II (Kayu Kamfer)
A Tenaga 139,350.00 154,580.00
L.01 0.35 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 1.05 OH Tukang Kayu 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 428,100.00 467,455.00
E Overhead & Profit (contoh 10%) 10% 42,810.00 46,745.50
F Harga Satuan Pekerjaan (D+E) 470,910.00 514,200.50

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 470,910.00 514,200.50
Sederhana Kayu Klas III
Tenaga 139,350.00 154,580.00
L.01 0.35 OH Pekerja 75,000.00 85,000.00 26,250.00 29,750.00
L.02 1.05 OH Tukang Kayu 95,000.00 105,000.00 99,750.00 110,250.00
L.03 0.105 OH Kepala Tukang 110,000.00 120,000.00 11,550.00 12,600.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 428,100.00 467,455.00
E Overhead & Profit (contoh 10%) 10% 42,810.00 46,745.50
F Harga Satuan Pekerjaan (D+E) 470,910.00 514,200.50

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 755,287.50 829,950.00
Klas I atau II
A Tenaga 398,000.00 441,500.00
L.01 1.00 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 3.00 OH Tukang Kayu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 288,625.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 686,625.00 754,500.00
E Overhead & Profit (contoh 10%) 10% 68,662.50 75,450.00
F Harga Satuan Pekerjaan (D+E) 755,287.50 829,950.00

file:///conversion/tmp/scratch/415837925.xls 175/103 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 544,445.00 601,040.00
Kayu Klas I atau II
A Tenaga 318,400.00 353,200.00
L.01 0.800 OH Pekerja 75,000.00 85,000.00 60,000.00 68,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 176,550.00 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 172,800.00 187,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 494,950.00 546,400.00
E Overhead & Profit (contoh 10%) 10% 49,495.00 54,640.00
F Harga Satuan Pekerjaan (D+E) 544,445.00 601,040.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 1,993,475.00 2,115,850.00
Kayu Klas I atau II (jati)
A Tenaga 398,000.00 441,500.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 3 OH Tukang Kayu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.05 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00
B Bahan 1,414,250.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,812,250.00 1,923,500.00
E Overhead & Profit (contoh 10%) 10% 181,225.00 192,350.00
F Harga Satuan Pekerjaan (D+E) 1,993,475.00 2,115,850.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 583,330.00 654,032.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 278,600.00 309,050.00


L.01 0.700 OH Pekerja 75,000.00 85,000.00 52,500.00 59,500.00
L.02 2.100 OH Tukang Kayu 95,000.00 105,000.00 199,500.00 220,500.00
L.03 0.210 OH Kepala Tukang 110,000.00 120,000.00 23,100.00 25,200.00
L.04 0.035 OH Mandor 100,000.00 110,000.00 3,500.00 3,850.00
B Bahan 251,700.00 285,525.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 530,300.00 594,575.00
E Overhead & Profit (contoh 10%) 10% 53,030.00 59,457.50
F Harga Satuan Pekerjaan (D+E) 583,330.00 654,032.50

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 631,862.00 707,745.50
rangka expose kayu klas I atau II
A Tenaga 318,400.00 353,200.00
L.01 0.800 OH Pekerja 75,000.00 85,000.00 60,000.00 68,000.00
L.02 2.400 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.240 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 256,020.00 290,205.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 184,320.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 574,420.00 643,405.00
E Overhead & Profit (contoh 10%) 10% 57,442.00 64,340.50
F Harga Satuan Pekerjaan (D+E) 631,862.00 707,745.50

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 1,779,800.00 1,881,467.50
Klas I atau II
A Tenaga 295,750.00 327,800.00
L.01 0.670 OH Pekerja 75,000.00 85,000.00 50,250.00 56,950.00
L.02 2.000 OH Tukang Kayu 95,000.00 105,000.00 190,000.00 210,000.00
L.03 0.200 OH Kepala Tukang 110,000.00 120,000.00 22,000.00 24,000.00
L.04 0.335 OH Mandor 100,000.00 110,000.00 33,500.00 36,850.00
B Bahan 1,322,250.00 1,382,625.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 1,618,000.00 1,710,425.00
E Overhead & Profit (contoh 10%) 10% 161,800.00 171,042.50
F Harga Satuan Pekerjaan (D+E) 1,779,800.00 1,881,467.50

file:///conversion/tmp/scratch/415837925.xls 175/104 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,031,360.00 1,116,197.50
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 318,400.00 353,200.00
L.01 0.80 OH Pekerja 75,000.00 85,000.00 60,000.00 68,000.00
L.02 2.40 OH Tukang Kayu 95,000.00 105,000.00 228,000.00 252,000.00
L.03 0.24 OH Kepala Tukang 110,000.00 120,000.00 26,400.00 28,800.00
L.04 0.04 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00
B Bahan 619,200.00 661,525.00
0.025 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 550,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 937,600.00 1,014,725.00
E Overhead & Profit (contoh 10%) 10% 93,760.00 101,472.50
F Harga Satuan Pekerjaan (D+E) 1,031,360.00 1,116,197.50

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 680,680.00 758,950.50
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 338,350.00 375,330.00


L.01 0.850 OH Pekerja 75,000.00 85,000.00 63,750.00 72,250.00
L.02 2.550 OH Tukang Kayu 95,000.00 105,000.00 242,250.00 267,750.00
L.03 0.255 OH Kepala Tukang 110,000.00 120,000.00 28,050.00 30,600.00
L.04 0.043 OH Mandor 100,000.00 110,000.00 4,300.00 4,730.00
B Bahan 280,450.00 314,625.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
0.5 Lbr Formika 68,000.00 75,000.00 34,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 618,800.00 689,955.00
E Overhead & Profit (contoh 10%) 10% 61,880.00 68,995.50
F Harga Satuan Pekerjaan (D+E) 680,680.00 758,950.50

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 9,447,350.00 11,356,400.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,592,000.00 1,766,000.00
L.01 4 OH Pekerja 75,000.00 85,000.00 300,000.00 340,000.00
L.02 12 OH Tukang Kayu 95,000.00 105,000.00 1,140,000.00 1,260,000.00
L.03 1.2 OH Kepala Tukang 110,000.00 120,000.00 132,000.00 144,000.00
L.04 0.2 OH Mandor 100,000.00 110,000.00 20,000.00 22,000.00
B Bahan 6,996,500.00 8,558,000.00
1.1 m3 Kayu Kamfer, balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 8,588,500.00 10,324,000.00
E Overhead & Profit (contoh 10%) 10% 858,850.00 1,032,400.00
F Harga Satuan Pekerjaan (D+E) 9,447,350.00 11,356,400.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 29,648,410.00 30,652,655.00
Expose, Kayu Klas I
A Tenaga 2,666,600.00 2,958,050.00
L.01 6.7 OH Pekerja 75,000.00 85,000.00 502,500.00 569,500.00
L.02 20.1 OH Tukang Kayu 95,000.00 105,000.00 1,909,500.00 2,110,500.00
L.03 2.01 OH Kepala Tukang 110,000.00 120,000.00 221,100.00 241,200.00
L.04 0.335 OH Mandor 100,000.00 110,000.00 33,500.00 36,850.00
B Bahan 24,286,500.00 24,908,000.00
1.2 m3 Kayu Klas I (jati), balok 20,000,000.00 20,500,000.00 24,000,000.00 24,600,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 26,953,100.00 27,866,050.00
E Overhead & Profit (contoh 10%) 10% 2,695,310.00 2,786,605.00
F Harga Satuan Pekerjaan (D+E) 29,648,410.00 30,652,655.00

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 8,703,970.00 10,529,310.00


A Tenaga 955,200.00 1,059,600.00
L.01 2.4 OH Pekerja 75,000.00 85,000.00 180,000.00 204,000.00
L.02 7.2 OH Tukang Kayu 95,000.00 105,000.00 684,000.00 756,000.00
L.03 0.72 OH Kepala Tukang 110,000.00 120,000.00 79,200.00 86,400.00
L.04 0.12 OH Mandor 100,000.00 110,000.00 12,000.00 13,200.00

file:///conversion/tmp/scratch/415837925.xls 175/105 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 6,957,500.00 8,512,500.00
1.1 m3 Kayu Klas I (Kamfer), balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 45,000.00 52,500.00
C PERALATAN
D Jumlah A + B + C 7,912,700.00 9,572,100.00
E Overhead & Profit (contoh 10%) 10% 791,270.00 957,210.00
F Harga Satuan Pekerjaan (D+E) 8,703,970.00 10,529,310.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 142,681.00 172,837.50
Klas II
A Tenaga 18,600.00 20,750.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 111,110.00 136,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0036 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 21,960.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 129,710.00 157,125.00
E Overhead & Profit (contoh 10%) 10% 12,971.00 15,712.50
F Harga Satuan Pekerjaan (D+E) 142,681.00 172,837.50

Pemasangan Rangka Atap Genteng Beton, Kayu Klas


17 A.4.6.1.17 1 m2 166,837.00 202,537.50
II
A Tenaga 18,600.00 20,750.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 133,070.00 163,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 43,920.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 151,670.00 184,125.00
E Overhead & Profit (contoh 10%) 10% 15,167.00 18,412.50
F Harga Satuan Pekerjaan (D+E) 166,837.00 202,537.50

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 121,792.00 146,740.00


A Tenaga 22,320.00 24,900.00
L.01 0.12 OH Pekerja 75,000.00 85,000.00 9,000.00 10,200.00
L.02 0.12 OH Tukang Kayu 95,000.00 105,000.00 11,400.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 120,000.00 1,320.00 1,440.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 88,400.00 108,500.00
0.014 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 110,720.00 133,400.00
E Overhead & Profit (contoh 10%) 10% 11,072.00 13,340.00
F Harga Satuan Pekerjaan (D+E) 121,792.00 146,740.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 162,239.00 192,610.00
Klas II atau III
A Tenaga 50,550.00 56,100.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.30 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.075 OH Mandor 100,000.00 110,000.00 7,500.00 8,250.00
B Bahan 96,940.00 119,000.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 93,940.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 147,490.00 175,100.00
E Overhead & Profit (contoh 10%) 10% 14,749.00 17,510.00
F Harga Satuan Pekerjaan (D+E) 162,239.00 192,610.00

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 166,078.00 197,807.50
Klas II atau III
A Tenaga 47,800.00 53,200.00
L.01 0.2 OH Pekerja 75,000.00 85,000.00 15,000.00 17,000.00
L.02 0.3 OH Tukang Kayu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.03 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.01 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

file:///conversion/tmp/scratch/415837925.xls 175/106 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 103,180.00 126,625.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 99,430.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 150,980.00 179,825.00
E Overhead & Profit (contoh 10%) 10% 15,098.00 17,982.50
F Harga Satuan Pekerjaan (D+E) 166,078.00 197,807.50

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 295,130.00 310,860.00
II
A Tenaga 29,200.00 32,450.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.020 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 239,100.00 250,150.00
0.0108 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 237,600.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
C PERALATAN
D Jumlah A + B + C 268,300.00 282,600.00
E Overhead & Profit (contoh 10%) 10% 26,830.00 28,260.00
F Harga Satuan Pekerjaan (D+E) 295,130.00 310,860.00

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 120,065.00 131,037.50
klas II
A Tenaga 29,200.00 32,450.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 79,950.00 86,675.00
0.011 m3 Kayu klas II (Kamfer), papan 7,200,000.00 7,800,000.00 79,200.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 109,150.00 119,125.00
E Overhead & Profit (contoh 10%) 10% 10,915.00 11,912.50
F Harga Satuan Pekerjaan (D+E) 120,065.00 131,037.50

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 256,080.00 306,795.50
Kayu klas II atau III
A Tenaga 59,750.00 66,280.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.45 OH Tukang Kayu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 173,050.00 212,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 232,800.00 278,905.00
E Overhead & Profit (contoh 10%) 10% 23,280.00 27,890.50
F Harga Satuan Pekerjaan (D+E) 256,080.00 306,795.50

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 325,270.00 394,795.50
Rangka Kayu Klas II
A Tenaga 59,750.00 66,280.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.45 OH Tukang Kayu 95,000.00 105,000.00 42,750.00 47,250.00
L.03 0.045 OH Kepala Tukang 110,000.00 120,000.00 4,950.00 5,400.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 235,950.00 292,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 295,700.00 358,905.00
E Overhead & Profit (contoh 10%) 10% 29,570.00 35,890.50
F Harga Satuan Pekerjaan (D+E) 325,270.00 394,795.50

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 332,255.00 402,187.50
Rangka Kayu Klas II
A Tenaga 66,100.00 73,000.00
L.01 0.020 OH Pekerja 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.600 OH Tukang Kayu 95,000.00 105,000.00 57,000.00 63,000.00
L.03 0.060 OH Kepala Tukang 110,000.00 120,000.00 6,600.00 7,200.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

file:///conversion/tmp/scratch/415837925.xls 175/107 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 235,950.00 292,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 302,050.00 365,625.00
E Overhead & Profit (contoh 10%) 10% 30,205.00 36,562.50
F Harga Satuan Pekerjaan (D+E) 332,255.00 402,187.50

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 434,720.00 471,735.00

A Tenaga 238,800.00 264,900.00


L.01 0.6 OH Pekerja 75,000.00 85,000.00 45,000.00 51,000.00
L.02 1.8 OH Tukang Kayu 95,000.00 105,000.00 171,000.00 189,000.00
L.03 0.18 OH Kepala Tukang 110,000.00 120,000.00 19,800.00 21,600.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 156,400.00 163,950.00
0.007 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 154,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
0.15 Kg Paku Sekrup 3,5" 6,000.00 8,000.00 900.00 1,200.00
C PERALATAN
D Jumlah A + B + C 395,200.00 428,850.00
E Overhead & Profit (contoh 10%) 10% 39,520.00 42,885.00
F Harga Satuan Pekerjaan (D+E) 434,720.00 471,735.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 38,203.00 46,139.50
ukuran (120x240) cm
A Tenaga 9,980.00 11,070.00
L.01 0.025 OH Pekerja 75,000.00 85,000.00 1,875.00 2,125.00
L.02 0.075 OH Tukang Kayu 95,000.00 105,000.00 7,125.00 7,875.00
L.03 0.0080 OH Kepala Tukang 110,000.00 120,000.00 880.00 960.00
L.04 0.0010 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 24,750.00 30,875.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 60,000.00 75,000.00 24,000.00 30,000.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 34,730.00 41,945.00
E Overhead & Profit (contoh 10%) 10% 3,473.00 4,194.50
F Harga Satuan Pekerjaan (D+E) 38,203.00 46,139.50

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 121,763.84 141,542.50
IV
A Tenaga 13,300.00 14,900.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.05 OH Tukang Kayu 95,000.00 105,000.00 4,750.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 97,394.40 113,775.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,700,000.00 67,200.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 180.00 210.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 110,694.40 128,675.00
E Overhead & Profit (contoh 10%) 10% 11,069.44 12,867.50
F Harga Satuan Pekerjaan (D+E) 121,763.84 141,542.50

file:///conversion/tmp/scratch/415837925.xls 175/108 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 175,835.00 231,110.00
A Tenaga 49,850.00 55,100.00
L.01 0.01 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 110,000.00 155,000.00
1 Buah Kunci Tanam Biasa 110,000.00 155,000.00 110,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 159,850.00 210,100.00
E Overhead & Profit (contoh 10%) 10% 15,985.00 21,010.00
F Harga Satuan Pekerjaan (D+E) 175,835.00 231,110.00
Overhead & Profit (contoh 10%)
2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 152,542.50 163,680.00
A Tenaga 48,675.00 53,800.00
L.01 0.005 OH Pekerja 75,000.00 85,000.00 375.00 425.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 90,000.00 95,000.00
1 Buah Kunci Tanam Kamar Mandi 90,000.00 95,000.00 90,000.00 95,000.00
C PERALATAN
D Jumlah A + B + C 138,675.00 148,800.00
E Overhead & Profit (contoh 10%) 10% 13,867.50 14,880.00
F Harga Satuan Pekerjaan (D+E) 152,542.50 163,680.00

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 174,542.50 229,680.00


A Tenaga 48,675.00 53,800.00
L.01 0.005 OH Pekerja 75,000.00 85,000.00 375.00 425.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.005 OH Kepala Tukang 110,000.00 120,000.00 550.00 600.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 110,000.00 155,000.00
1 Buah Kunci Selinder 110,000.00 155,000.00 110,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 158,675.00 208,800.00
E Overhead & Profit (contoh 10%) 10% 15,867.50 20,880.00
F Harga Satuan Pekerjaan (D+E) 174,542.50 229,680.00

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 26,152.50 31,515.00


A Tenaga 17,775.00 19,650.00
L.01 0.015 OH Pekerja 75,000.00 85,000.00 1,125.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.0075 OH Mandor 100,000.00 110,000.00 750.00 825.00
B Bahan 6,000.00 9,000.00
1 Buah Engsel pintu 6,000.00 9,000.00 6,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 23,775.00 28,650.00
E Overhead & Profit (contoh 10%) 10% 2,377.50 2,865.00
F Harga Satuan Pekerjaan (D+E) 26,152.50 31,515.00

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 17,435.00 21,010.00


A Tenaga 11,850.00 13,100.00
L.01 0.01 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 4,000.00 6,000.00
1 Buah Engsel Jendela 4,000.00 6,000.00 4,000.00 6,000.00
C PERALATAN
D Jumlah A + B + C 15,850.00 19,100.00
E Overhead & Profit (contoh 10%) 10% 1,585.00 1,910.00
F Harga Satuan Pekerjaan (D+E) 17,435.00 21,010.00

file:///conversion/tmp/scratch/415837925.xls 175/109 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 48,125.00 62,650.50
A Tenaga 28,750.00 31,955.00
L.01 0.10 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.02 0.20 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00
B Bahan 15,000.00 25,000.00
1 Buah Engsel Angin 15,000.00 25,000.00 15,000.00 25,000.00
C PERALATAN
D Jumlah A + B + C 43,750.00 56,955.00
E Overhead & Profit (contoh 10%) 10% 4,375.00 5,695.50
F Harga Satuan Pekerjaan (D+E) 48,125.00 62,650.50

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 36,107.50 43,675.50


A Tenaga 17,825.00 19,705.00
L.01 0.015 OH Pekerja 75,000.00 85,000.00 1,125.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 15,000.00 20,000.00
1 Buah Kait Angin 15,000.00 20,000.00 15,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 32,825.00 39,705.00
E Overhead & Profit (contoh 10%) 10% 3,282.50 3,970.50
F Harga Satuan Pekerjaan (D+E) 36,107.50 43,675.50

8 A.4.6.2.10 1 Buah Pasang Door Closer 365,200.00 454,327.50


A Tenaga 57,000.00 63,025.00
L.01 0.05 OH Pekerja 75,000.00 85,000.00 3,750.00 4,250.00
L.02 0.5 OH Tukang Kayu 95,000.00 105,000.00 47,500.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 332,000.00 413,025.00
E Overhead & Profit (contoh 10%) 10% 33,200.00 41,302.50
F Harga Satuan Pekerjaan (D+E) 365,200.00 454,327.50

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 33,880.00 38,731.00


A Tenaga 22,800.00 25,210.00
L.01 0.02 OH Pekerja 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.2 OH Tukang Kayu 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
B Bahan 8,000.00 10,000.00
1 Buah Kunci Selot 8,000.00 10,000.00 8,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 30,800.00 35,210.00
E Overhead & Profit (contoh 10%) 10% 3,080.00 3,521.00
F Harga Satuan Pekerjaan (D+E) 33,880.00 38,731.00

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 315,040.00 398,865.50


A Tenaga 11,400.00 12,605.00
L.01 0.01 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.1 OH Tukang Kayu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 286,400.00 362,605.00
E Overhead & Profit (contoh 10%) 10% 28,640.00 36,260.50
F Harga Satuan Pekerjaan (D+E) 315,040.00 398,865.50

file:///conversion/tmp/scratch/415837925.xls 175/110 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 295,240.00 341,693.00
A Tenaga 68,400.00 75,630.00
L.01 0.06 OH Pekerja 75,000.00 85,000.00 4,500.00 5,100.00
L.02 0.6 OH Tukang Kayu 95,000.00 105,000.00 57,000.00 63,000.00
L.03 0.06 OH Kepala Tukang 110,000.00 120,000.00 6,600.00 7,200.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 200,000.00 235,000.00
1 Buah Rel Pintu Dorong 200,000.00 235,000.00 200,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 268,400.00 310,630.00
E Overhead & Profit (contoh 10%) 10% 26,840.00 31,063.00
F Harga Satuan Pekerjaan (D+E) 295,240.00 341,693.00

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 45,105.50 51,169.80


A Tenaga 28,505.00 31,518.00
L.01 0.025 OH Pekerja 75,000.00 85,000.00 1,875.00 2,125.00
L.02 0.25 OH Tukang Kayu 95,000.00 105,000.00 23,750.00 26,250.00
L.03 0.025 OH Kepala Tukang 110,000.00 120,000.00 2,750.00 3,000.00
L.04 0.00130 OH Mandor 100,000.00 110,000.00 130.00 143.00
B Bahan 12,500.00 15,000.00
1 Buah Kunci Lemari 12,500.00 15,000.00 12,500.00 15,000.00
C PERALATAN
D Jumlah A + B + C 41,005.00 46,518.00
E Overhead & Profit (contoh 10%) 10% 4,100.50 4,651.80
F Harga Satuan Pekerjaan (D+E) 45,105.50 51,169.80

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 109,560.00 123,648.25


A Tenaga 17,100.00 18,907.50
L.01 0.015 OH Pekerja 75,000.00 85,000.00 1,125.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 82,500.00 93,500.00
1.1 m2 Kaca tebal 3mm 75,000.00 85,000.00 82,500.00 93,500.00
C PERALATAN
D Jumlah A + B + C 99,600.00 112,407.50
E Overhead & Profit (contoh 10%) 10% 9,960.00 11,240.75
F Harga Satuan Pekerjaan (D+E) 109,560.00 123,648.25

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 127,710.00 135,748.25


A Tenaga 17,100.00 18,907.50
L.01 0.015 OH Pekerja 75,000.00 85,000.00 1,125.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 99,000.00 104,500.00
1.1 m2 Kaca tebal 5mm 90,000.00 95,000.00 99,000.00 104,500.00
C PERALATAN
D Jumlah A + B + C 116,100.00 123,407.50
E Overhead & Profit (contoh 10%) 10% 11,610.00 12,340.75
F Harga Satuan Pekerjaan (D+E) 127,710.00 135,748.25

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 351,560.00 383,798.25


A Tenaga 17,100.00 18,907.50
L.01 0.015 OH Pekerja 75,000.00 85,000.00 1,125.00 1,275.00
L.02 0.15 OH Tukang Kayu 95,000.00 105,000.00 14,250.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 120,000.00 1,650.00 1,800.00
L.04 0.00075 OH Mandor 100,000.00 110,000.00 75.00 82.50
B Bahan 302,500.00 330,000.00
1.1 m2 Kaca Cermin 275,000.00 300,000.00 302,500.00 330,000.00
C PERALATAN
D Jumlah A + B + C 319,600.00 348,907.50
E Overhead & Profit (contoh 10%) 10% 31,960.00 34,890.75
F Harga Satuan Pekerjaan (D+E) 351,560.00 383,798.25

file:///conversion/tmp/scratch/415837925.xls 175/111 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 13,420.00 15,213.00
Lama
A Tenaga 11,550.00 13,080.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 650.00 750.00
0.05 Kg Soda Api 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 12,200.00 13,830.00
E Overhead & Profit (contoh 10%) 10% 1,220.00 1,383.00
F Harga Satuan Pekerjaan (D+E) 13,420.00 15,213.00

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 13,392.50 15,213.00
dicat
A Tenaga 11,550.00 13,080.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 12,175.00 13,830.00
E Overhead & Profit (contoh 10%) 10% 1,217.50 1,383.00
F Harga Satuan Pekerjaan (D+E) 13,392.50 15,213.00

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 13,942.50 15,818.00
manual
A Tenaga 12,050.00 13,630.00
L.01 0.15 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.04 0.0080 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 12,675.00 14,380.00
E Overhead & Profit (contoh 10%) 10% 1,267.50 1,438.00
F Harga Satuan Pekerjaan (D+E) 13,942.50 15,818.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 42,196.00 49,830.00
dasar, 2 Lp Cat Penutup)
A Tenaga 7,065.00 7,945.00
L.01 0.070 OH Pekerja 75,000.00 85,000.00 5,250.00 5,950.00
L.02 0.009 OH Tukang Cat 95,000.00 105,000.00 855.00 945.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 31,295.00 37,355.00
0.2000 kg Cat Menie 23,000.00 30,000.00 4,600.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 36,500.00 40,000.00 6,205.00 6,800.00
0.2600 kg Cat Penutup 60,000.00 71,000.00 15,600.00 18,460.00
0.0100 bh Kuas 14,000.00 17,500.00 140.00 175.00
0.0300 kg Pengencer 10,000.00 20,000.00 300.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 38,360.00 45,300.00
E Overhead & Profit (contoh 10%) 10% 3,836.00 4,530.00
F Harga Satuan Pekerjaan (D+E) 42,196.00 49,830.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 57,926.00 67,683.00
dasar, 3 Lp Cat Penutup)
A Tenaga 15,965.00 17,785.00
L.01 0.070 OH Pekerja 75,000.00 85,000.00 5,250.00 5,950.00
L.02 0.105 OH Tukang Cat 95,000.00 105,000.00 9,975.00 11,025.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

file:///conversion/tmp/scratch/415837925.xls 175/112 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 36,695.00 43,745.00
0.2000 kg Cat Menie 23,000.00 30,000.00 4,600.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 36,500.00 40,000.00 6,205.00 6,800.00
0.3500 kg Cat Penutup 60,000.00 71,000.00 21,000.00 24,850.00
0.0100 bh Kuas 14,000.00 17,500.00 140.00 175.00
0.0300 kg Pengencer 10,000.00 20,000.00 300.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 52,660.00 61,530.00
E Overhead & Profit (contoh 10%) 10% 5,266.00 6,153.00
F Harga Satuan Pekerjaan (D+E) 57,926.00 67,683.00

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 34,072.50 36,327.50


A Tenaga 16,215.00 17,905.00
L.01 0.04 OH Pekerja 75,000.00 85,000.00 3,000.00 3,400.00
L.02 0.063 OH Tukang Cat 95,000.00 105,000.00 5,985.00 6,615.00
L.03 0.063 OH Kepala Tukang 110,000.00 120,000.00 6,930.00 7,560.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 30,975.00 33,025.00
E Overhead & Profit (contoh 10%) 10% 3,097.50 3,302.50
F Harga Satuan Pekerjaan (D+E) 34,072.50 36,327.50

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 54,562.20 59,488.00


A Tenaga 10,760.00 11,950.00
L.01 0.04 OH Pekerja 75,000.00 85,000.00 3,000.00 3,400.00
L.02 0.06 OH Tukang Cat 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.016 OH Kepala Tukang 110,000.00 120,000.00 1,760.00 1,920.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 38,842.00 42,130.00
0.15 Ltr Politur 61,000.00 65,000.00 9,150.00 9,750.00
0.372 Ltr Politur Jadi 61,000.00 65,000.00 22,692.00 24,180.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A + B + C 49,602.00 54,080.00
E Overhead & Profit (contoh 10%) 10% 4,960.20 5,408.00
F Harga Satuan Pekerjaan (D+E) 54,562.20 59,488.00

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 9,968.75 11,231.00
A Tenaga 8,100.00 9,160.00
L.01 0.1 OH Pekerja 75,000.00 85,000.00 7,500.00 8,500.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 9,062.50 10,210.00
E Overhead & Profit (contoh 10%) 10% 906.25 1,021.00
F Harga Satuan Pekerjaan (D+E) 9,968.75 11,231.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 38,071.00 42,141.00


A Tenaga 29,260.00 32,650.00
L.01 0.16 OH Pekerja 75,000.00 85,000.00 12,000.00 13,600.00
L.02 0.16 OH Tukang Cat 95,000.00 105,000.00 15,200.00 16,800.00
L.03 0.016 OH Kepala Tukang 110,000.00 120,000.00 1,760.00 1,920.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 5,350.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 3,500.00 4,100.00 350.00 410.00
C PERALATAN
D Jumlah A + B + C 34,610.00 38,310.00
E Overhead & Profit (contoh 10%) 10% 3,461.00 3,831.00
F Harga Satuan Pekerjaan (D+E) 38,071.00 42,141.00

file:///conversion/tmp/scratch/415837925.xls 175/113 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 19,973.80 22,947.10
Lap.Cat Penutup)
A Tenaga 8,478.00 9,401.00
L.01 0.02 OH Pekerja 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.063 OH Tukang Cat 95,000.00 105,000.00 5,985.00 6,615.00
L.03 0.0063 OH Kepala Tukang 110,000.00 120,000.00 693.00 756.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 9,680.00 11,460.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 26,000.00 5,980.00 6,760.00
C PERALATAN
D Jumlah A + B + C 18,158.00 20,861.00
E Overhead & Profit (contoh 10%) 10% 1,815.80 2,086.10
F Harga Satuan Pekerjaan (D+E) 19,973.80 22,947.10

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 13,675.20 15,514.40
Penutup)
A Tenaga 6,852.00 7,624.00
L.01 0.028 OH Pekerja 75,000.00 85,000.00 2,100.00 2,380.00
L.02 0.042 OH Tukang Cat 95,000.00 105,000.00 3,990.00 4,410.00
L.03 0.0042 OH Kepala Tukang 110,000.00 120,000.00 462.00 504.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 5,580.00 6,480.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 26,000.00 4,140.00 4,680.00
C PERALATAN
D Jumlah A + B + C 12,432.00 14,104.00
E Overhead & Profit (contoh 10%) 10% 1,243.20 1,410.40
F Harga Satuan Pekerjaan (D+E) 13,675.20 15,514.40

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 8,032.20 8,936.40


A Tenaga 6,852.00 7,624.00
L.01 0.028 OH Pekerja 75,000.00 85,000.00 2,100.00 2,380.00
L.02 0.042 OH Tukang Cat 95,000.00 105,000.00 3,990.00 4,410.00
L.03 0.0042 OH Kepala Tukang 110,000.00 120,000.00 462.00 504.00
L.04 0.0030 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 450.00 500.00
0.1 Kg Kalkarium 4,500.00 5,000.00 450.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 7,302.00 8,124.00
E Overhead & Profit (contoh 10%) 10% 730.20 812.40
F Harga Satuan Pekerjaan (D+E) 8,032.20 8,936.40

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 14,732.85 16,777.20


A Tenaga 11,606.00 13,142.00
L.01 0.150 OH Pekerja 75,000.00 85,000.00 11,250.00 12,750.00
L.02 0.001 OH Tukang Cat 95,000.00 105,000.00 95.00 105.00
L.03 0.0001 OH Kepala Tukang 110,000.00 120,000.00 11.00 12.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 1,787.50 2,110.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,500.00 4,100.00 350.00 410.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 13,393.50 15,252.00
E Overhead & Profit (contoh 10%) 10% 1,339.35 1,525.20
F Harga Satuan Pekerjaan (D+E) 14,732.85 16,777.20

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 6,674.25 7,705.50
(pemeliharaan)
A Tenaga 3,780.00 4,260.00
L.01 0.040 OH Pekerja 75,000.00 85,000.00 3,000.00 3,400.00
L.02 0.005 OH Tukang Cat 95,000.00 105,000.00 475.00 525.00
L.03 0.0005 OH Kepala Tukang 110,000.00 120,000.00 55.00 60.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00

file:///conversion/tmp/scratch/415837925.xls 175/114 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,287.50 2,745.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,500.00 4,100.00 700.00 820.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 6,067.50 7,005.00
E Overhead & Profit (contoh 10%) 10% 606.75 700.50
F Harga Satuan Pekerjaan (D+E) 6,674.25 7,705.50

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 83,545.00 95,012.50


A Tenaga 22,950.00 25,375.00
L.01 0.020 OH Pekerja 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.200 OH Tukang Cat 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.0200 OH Kepala Tukang 110,000.00 120,000.00 2,200.00 2,400.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 75,950.00 86,375.00
E Overhead & Profit (contoh 10%) 10% 7,595.00 8,637.50
F Harga Satuan Pekerjaan (D+E) 83,545.00 95,012.50

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 26,422.00 30,211.50


A Tenaga 20,970.00 23,215.00
L.01 0.02 OH Pekerja 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.2 OH Tukang Cat 95,000.00 105,000.00 19,000.00 21,000.00
L.03 0.002 OH Kepala Tukang 110,000.00 120,000.00 220.00 240.00
L.04 0.0025 OH Mandor 100,000.00 110,000.00 250.00 275.00
B Bahan 3,050.00 4,250.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 24,020.00 27,465.00
E Overhead & Profit (contoh 10%) 10% 2,402.00 2,746.50
F Harga Satuan Pekerjaan (D+E) 26,422.00 30,211.50

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 52,717.50 59,785.00
Perancah
A Tenaga 40,875.00 45,700.00
L.01 0.25 OH Pekerja 75,000.00 85,000.00 18,750.00 21,250.00
L.02 0.225 OH Tukang Cat 95,000.00 105,000.00 21,375.00 23,625.00
L.04 0.0075 OH Mandor 100,000.00 110,000.00 750.00 825.00
B Bahan 7,050.00 8,650.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 47,925.00 54,350.00
E Overhead & Profit (contoh 10%) 10% 4,792.50 5,435.00
F Harga Satuan Pekerjaan (D+E) 52,717.50 59,785.00

file:///conversion/tmp/scratch/415837925.xls 175/115 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,270,521.00 2,612,192.00
A Tenaga 368,110.00 413,720.00
L.01 3.3 OH Pekerja 75,000.00 85,000.00 247,500.00 280,500.00
L.02 1.1 OH Tukang Batu 95,000.00 105,000.00 104,500.00 115,500.00
L.03 0.001 OH Kepala Tukang 110,000.00 120,000.00 110.00 120.00
L.04 0.16 OH Mandor 100,000.00 110,000.00 16,000.00 17,600.00
Buah Bahan 1,696,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,600,000.00 1,850,000.00 1,600,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,600,000.00 1,850,000.00 96,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 2,064,110.00 2,374,720.00
E Overhead & Profit (contoh 10%) 10% 206,411.00 237,472.00
F Harga Satuan Pekerjaan (D+E) 2,270,521.00 2,612,192.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 603,075.00 660,770.00
A Tenaga 398,500.00 440,100.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 1.5 OH Tukang Batu 95,000.00 105,000.00 142,500.00 157,500.00
L.03 1.5 OH Kepala Tukang 110,000.00 120,000.00 165,000.00 180,000.00
L.04 0.16 OH Mandor 100,000.00 110,000.00 16,000.00 17,600.00
B Bahan 149,750.00 160,600.00
1 Buah Kloset Jongkok 140,000.00 150,000.00 140,000.00 150,000.00
6 Kg Portland Semen 1,100.00 1,150.00 6,600.00 6,900.00
0.01 m3 Pasir Pasang 315,000.00 370,000.00 3,150.00 3,700.00
C PERALATAN
D Jumlah A + B + C 548,250.00 600,700.00
E Overhead & Profit (contoh 10%) 10% 54,825.00 60,070.00
F Harga Satuan Pekerjaan (D+E) 603,075.00 660,770.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 721,325.00 782,210.00


A Tenaga 191,000.00 213,000.00
L.01 1 OH Pekerja 75,000.00 85,000.00 75,000.00 85,000.00
L.02 1 OH Tukang Batu 95,000.00 105,000.00 95,000.00 105,000.00
L.03 0.1 OH Kepala Tukang 110,000.00 120,000.00 11,000.00 12,000.00
L.04 0.1 OH Mandor 100,000.00 110,000.00 10,000.00 11,000.00
B Bahan 464,750.00 498,100.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,100.00 1,150.00 6,600.00 6,900.00
0.01 m3 Pasir Pasang 315,000.00 370,000.00 3,150.00 3,700.00
C PERALATAN
D Jumlah A + B + C 655,750.00 711,100.00
E Overhead & Profit (contoh 10%) 10% 65,575.00 71,110.00
F Harga Satuan Pekerjaan (D+E) 721,325.00 782,210.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 583,027.50 637,257.50


A Tenaga 130,275.00 146,225.00
L.01 1.2 OH Pekerja 75,000.00 85,000.00 90,000.00 102,000.00
L.02 0.145 OH Tukang Batu 95,000.00 105,000.00 13,775.00 15,225.00
L.03 0.15 OH Kepala Tukang 110,000.00 120,000.00 16,500.00 18,000.00
L.04 0.1 OH Mandor 100,000.00 110,000.00 10,000.00 11,000.00
B Bahan 399,750.00 433,100.00
1 Buah Wastafel 300,000.00 325,000.00 300,000.00 325,000.00
0.3 - Perlengkapan 30% Harga Wastafel 300,000.00 325,000.00 90,000.00 97,500.00
6 Kg Portland Semen 1,100.00 1,150.00 6,600.00 6,900.00
0.01 m3 Pasir Pasang 315,000.00 370,000.00 3,150.00 3,700.00
C PERALATAN
D Jumlah A + B + C 530,025.00 579,325.00
E Overhead & Profit (contoh 10%) 10% 53,002.50 57,932.50
F Harga Satuan Pekerjaan (D+E) 583,027.50 637,257.50

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,083,967.50 1,159,900.50


A Tenaga 85,425.00 94,455.00
L.01 0.075 OH Pekerja 75,000.00 85,000.00 5,625.00 6,375.00
L.02 0.75 OH Tukang Batu 95,000.00 105,000.00 71,250.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 120,000.00 8,250.00 9,000.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

file:///conversion/tmp/scratch/415837925.xls 175/116 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 985,425.00 1,054,455.00
E Overhead & Profit (contoh 10%) 10% 98,542.50 105,445.50
F Harga Satuan Pekerjaan (D+E) 1,083,967.50 1,159,900.50

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,161,600.00 1,285,350.00


A Tenaga 748,000.00 832,500.00

L.01 3 OH Pekerja 75,000.00 85,000.00 225,000.00 255,000.00


L.02 4.5 OH Tukang Batu 95,000.00 105,000.00 427,500.00 472,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.9 OH Mandor 100,000.00 110,000.00 90,000.00 99,000.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,056,000.00 1,168,500.00
E Overhead & Profit (contoh 10%) 10% 105,600.00 116,850.00
F Harga Satuan Pekerjaan (D+E) 1,161,600.00 1,285,350.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,471,679.27 1,638,538.54
A Tenaga 771,000.00 864,300.00
L.01 6.00 OH Pekerja 75,000.00 85,000.00 450,000.00 510,000.00
L.02 3.00 OH Tukang Batu 95,000.00 105,000.00 285,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 120,000.00 33,000.00 36,000.00
L.04 0.03 OH Mandor 100,000.00 110,000.00 3,000.00 3,300.00
B Bahan 566,890.24 625,280.49
150.0 bh Batu Bata 600.00 650.00 90,000.00 97,500.00
120 Kg Portland Semen 0.11 1,100.00 1,150.00 132,000.00 138,000.00
0.3 m3 Pasir Pasang 0.0121 315,000.00 370,000.00 94,500.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,337,890.24 1,489,580.49
E Overhead & Profit (contoh 10%) 10% 133,789.02 148,958.05
F Harga Satuan Pekerjaan (D+E) 1,471,679.27 1,638,538.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,234,908.17 6,925,402.59


A Tenaga 697,300.00 777,980.00
L.01 3.50 OH Pekerja 75,000.00 85,000.00 262,500.00 297,500.00
L.02 4.50 OH Tukang Batu 95,000.00 105,000.00 427,500.00 472,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 120,000.00 5,500.00 6,000.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
B Bahan 1,143,939.33 1,295,199.56 4,970,798.34 5,517,840.53
0.9 m3 Beton K.150 1,019,329.67 1,144,480.07 917,396.70 1,030,032.06
180 Kg Baja Tulangan 0.11 13,268.20 14,317.05 2,388,276.00 2,577,069.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,341.46 1,402.44 670,731.71 701,219.51
10 % Perlengkapan 1,143,939.33 1,295,199.56 114,393.93 129,519.96
C PERALATAN
D Jumlah A + B + C 5,668,098.34 6,295,820.53
E Overhead & Profit (contoh 10%) 10% 566,809.83 629,582.05
F Harga Satuan Pekerjaan (D+E) 6,234,908.17 6,925,402.59

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 341,605.00 384,230.00
A Tenaga 35,550.00 39,300.00
L.01 0.030 OH Pekerja 75,000.00 85,000.00 2,250.00 2,550.00
L.02 0.300 OH Tukang Batu 95,000.00 105,000.00 28,500.00 31,500.00
L.03 0.030 OH Kepala Tukang 110,000.00 120,000.00 3,300.00 3,600.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 310,550.00 349,300.00
E Overhead & Profit (contoh 10%) 10% 31,055.00 34,930.00
F Harga Satuan Pekerjaan (D+E) 341,605.00 384,230.00

file:///conversion/tmp/scratch/415837925.xls 175/117 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 51,535.00 58,410.00
A Tenaga 11,850.00 13,100.00
L.01 0.010 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.100 OH Tukang Batu 95,000.00 105,000.00 9,500.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 120,000.00 1,100.00 1,200.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 35,000.00 40,000.00
1 bh Floor Drain 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN
D Jumlah A + B + C 46,850.00 53,100.00
E Overhead & Profit (contoh 10%) 10% 4,685.00 5,310.00
F Harga Satuan Pekerjaan (D+E) 51,535.00 58,410.00

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 432,189.03 479,003.01
35 cm
A Tenaga 239,420.00 269,050.00
L.01 2.160 OH Pekerja 75,000.00 85,000.00 162,000.00 183,600.00
L.02 0.720 OH Tukang Batu 95,000.00 105,000.00 68,400.00 75,600.00
L.03 0.072 OH Kepala Tukang 110,000.00 120,000.00 7,920.00 8,640.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00
B Bahan 153,479.12 166,407.28
40.00 bh Batu Bata 600.00 650.00 24,000.00 26,000.00
44.00 kg Semen Portland 1,100.00 1,150.00 48,400.00 50,600.00
0.07 m3 Pasir Pasang 315,000.00 370,000.00 22,050.00 25,900.00
0.06 m3 Pasir Beton 350,000.00 380,000.00 21,000.00 22,800.00
0.07 m3 Kerikil 240,000.00 260,000.00 16,800.00 18,200.00
1.60 kg Baja Tulangan 13,268.20 14,317.05 21,229.12 22,907.28
C PERALATAN
D Jumlah A + B + C 392,899.12 435,457.28
E Overhead & Profit (contoh 10%) 10% 39,289.91 43,545.73
F Harga Satuan Pekerjaan (D+E) 432,189.03 479,003.01

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 634,963.03 704,316.01
tinggi 50 cm
A Tenaga 352,060.00 395,830.00
L.01 3.200 OH Pekerja 75,000.00 85,000.00 240,000.00 272,000.00
L.02 1.150 OH Tukang Batu 95,000.00 105,000.00 109,250.00 120,750.00
L.03 0.011 OH Kepala Tukang 110,000.00 120,000.00 1,210.00 1,320.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 225,179.12 244,457.28
70.00 bh Batu Bata 600.00 650.00 42,000.00 45,500.00
77.00 kg Semen Portland 1,100.00 1,150.00 84,700.00 88,550.00
0.13 m3 Pasir Pasang 315,000.00 370,000.00 40,950.00 48,100.00
0.09 m3 Pasir Beton 350,000.00 380,000.00 31,500.00 34,200.00
0.02 m3 Kerikil 240,000.00 260,000.00 4,800.00 5,200.00
1.60 kg Baja Tulangan 13,268.20 14,317.05 21,229.12 22,907.28
C PERALATAN
D Jumlah A + B + C 577,239.12 640,287.28
E Overhead & Profit (contoh 10%) 10% 57,723.91 64,028.73
F Harga Satuan Pekerjaan (D+E) 634,963.03 704,316.01

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 772,607.85 853,157.46
60 cm
A Tenaga 352,060.00 395,830.00
L.01 3.200 OH Pekerja 75,000.00 85,000.00 240,000.00 272,000.00
L.02 1.150 OH Tukang Batu 95,000.00 105,000.00 109,250.00 120,750.00
L.03 0.011 OH Kepala Tukang 110,000.00 120,000.00 1,210.00 1,320.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00
B Bahan 350,310.77 379,767.69
123.00 bh Batu Bata 600.00 650.00 73,800.00 79,950.00
114.00 kg Semen Portland 1,100.00 1,150.00 125,400.00 131,100.00
0.18 m3 Pasir Pasang 315,000.00 370,000.00 57,960.00 68,080.00
0.12 m3 Pasir Beton 240,000.00 260,000.00 28,800.00 31,200.00
4.85 kg Baja Tulangan 13,268.20 14,317.05 64,350.77 69,437.69
C PERALATAN
D Jumlah A + B + C 702,370.77 775,597.69
E Overhead & Profit (contoh 10%) 10% 70,237.08 77,559.77
F Harga Satuan Pekerjaan (D+E) 772,607.85 853,157.46

file:///conversion/tmp/scratch/415837925.xls 175/118 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 60,544.00 63,944.83
A Tenaga 16,290.00 18,090.00
L.01 0.054 OH Pekerja 75,000.00 85,000.00 4,050.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 38,750.00 40,041.67
1.20 m' Pipa Galvanis Ø ½" 25,000.00 25,833.33 30,000.00 31,000.00
0.35 Ls Perlengkapan 35% x pipa 25,000.00 25,833.33 8,750.00 9,041.67
C PERALATAN
D Jumlah A + B + C 55,040.00 58,131.67
E Overhead & Profit (contoh 10%) 10% 5,504.00 5,813.17
F Harga Satuan Pekerjaan (D+E) 60,544.00 63,944.83

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 75,524.63 102,532.38


A Tenaga 43,650.00 48,200.00
L.01 0.010 OH Pekerja 75,000.00 85,000.00 750.00 850.00
L.02 0.400 OH Tukang Batu 95,000.00 105,000.00 38,000.00 42,000.00
L.03 0.040 OH Kepala Tukang 110,000.00 120,000.00 4,400.00 4,800.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 25,008.75 45,011.25
1.00 bh Kran Air 25,000.00 45,000.00 25,000.00 45,000.00
0.0025 bh Sealtape 3,500.00 4,500.00 8.75 11.25
C PERALATAN
D Jumlah A + B + C 68,658.75 93,211.25
E Overhead & Profit (contoh 10%) 10% 6,865.88 9,321.13
F Harga Satuan Pekerjaan (D+E) 75,524.63 102,532.38

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 71,910.67 75,311.50


A Tenaga 16,290.00 18,090.00
L.01 0.054 OH Pekerja 75,000.00 85,000.00 4,050.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 49,083.33 50,375.00
1.20 m' Pipa Galvanis Ø ¾" 31,666.67 32,500.00 38,000.00 39,000.00
0.35 Ls Perlengkapan 35% x pipa 31,666.67 32,500.00 11,083.33 11,375.00
C PERALATAN
D Jumlah A + B + C 65,373.33 68,465.00
E Overhead & Profit (contoh 10%) 10% 6,537.33 6,846.50
F Harga Satuan Pekerjaan (D+E) 71,910.67 75,311.50

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 103,169.00 106,569.83


A Tenaga 16,290.00 18,090.00
L.01 0.054 OH Pekerja 75,000.00 85,000.00 4,050.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.027 OH Mandor 100,000.00 110,000.00 2,700.00 2,970.00
B Bahan 77,500.00 78,791.67
1.20 m' Pipa Galvanis Ø 1" 50,000.00 50,833.33 60,000.00 61,000.00
0.35 Ls Perlengkapan 35% x pipa 50,000.00 50,833.33 17,500.00 17,791.67
C PERALATAN
D Jumlah A + B + C 93,790.00 96,881.67
E Overhead & Profit (contoh 10%) 10% 9,379.00 9,688.17
F Harga Satuan Pekerjaan (D+E) 103,169.00 106,569.83

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 137,010.50 141,852.33


A Tenaga 27,680.00 30,790.00
L.01 0.108 OH Pekerja 75,000.00 85,000.00 8,100.00 9,180.00
L.02 0.180 OH Tukang Batu 95,000.00 105,000.00 17,100.00 18,900.00
L.03 0.018 OH Kepala Tukang 110,000.00 120,000.00 1,980.00 2,160.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 96,875.00 98,166.67
1.20 m' Pipa Galvanis Ø 1½" 62,500.00 63,333.33 75,000.00 76,000.00
0.35 Ls Perlengkapan 35% x pipa 62,500.00 63,333.33 21,875.00 22,166.67
C PERALATAN
D Jumlah A + B + C 124,555.00 128,956.67
E Overhead & Profit (contoh 10%) 10% 12,455.50 12,895.67
F Harga Satuan Pekerjaan (D+E) 137,010.50 141,852.33

file:///conversion/tmp/scratch/415837925.xls 175/119 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 247,065.50 252,776.33
A Tenaga 34,730.00 38,630.00
L.01 0.135 OH Pekerja 75,000.00 85,000.00 10,125.00 11,475.00
L.02 0.225 OH Tukang Batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 189,875.00 191,166.67
1.20 m' Pipa Galvanis Ø 3" 122,500.00 123,333.33 147,000.00 148,000.00
0.35 Ls Perlengkapan 35% x pipa 122,500.00 123,333.33 42,875.00 43,166.67
C PERALATAN
D Jumlah A + B + C 224,605.00 229,796.67
E Overhead & Profit (contoh 10%) 10% 22,460.50 22,979.67
F Harga Satuan Pekerjaan (D+E) 247,065.50 252,776.33

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 451,665.50 458,086.75


A Tenaga 34,730.00 38,630.00
L.01 0.135 OH Pekerja 75,000.00 85,000.00 10,125.00 11,475.00
L.02 0.225 OH Tukang Batu 95,000.00 105,000.00 21,375.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 120,000.00 2,530.00 2,760.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 375,875.00 377,812.50
1.20 m' Pipa Galvanis Ø 4" 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A + B + C 410,605.00 416,442.50
E Overhead & Profit (contoh 10%) 10% 41,060.50 41,644.25
F Harga Satuan Pekerjaan (D+E) 451,665.50 458,086.75

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 22,121.00 24,117.50


A Tenaga 9,260.00 10,300.00
L.01 0.036 OH Pekerja 75,000.00 85,000.00 2,700.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 10,850.00 11,625.00
1.20 m' Pipa PVC Ø ½" 7,000.00 7,500.00 8,400.00 9,000.00
0.35 Ls Perlengkapan 35% x pipa 7,000.00 7,500.00 2,450.00 2,625.00
C PERALATAN
D Jumlah A + B + C 20,110.00 21,925.00
E Overhead & Profit (contoh 10%) 10% 2,011.00 2,192.50
F Harga Satuan Pekerjaan (D+E) 22,121.00 24,117.50

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 24,678.50 26,248.75


A Tenaga 9,260.00 10,300.00
L.01 0.036 OH Pekerja 75,000.00 85,000.00 2,700.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 13,175.00 13,562.50
1.20 m' Pipa PVC Ø ¾" 8,500.00 8,750.00 10,200.00 10,500.00
0.35 Ls Perlengkapan 35% x pipa 8,500.00 8,750.00 2,975.00 3,062.50
C PERALATAN
D Jumlah A + B + C 22,435.00 23,862.50
E Overhead & Profit (contoh 10%) 10% 2,243.50 2,386.25
F Harga Satuan Pekerjaan (D+E) 24,678.50 26,248.75

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 29,367.25 33,495.00


A Tenaga 9,260.00 10,300.00
L.01 0.036 OH Pekerja 75,000.00 85,000.00 2,700.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 17,437.50 20,150.00
1.20 m' Pipa PVC Ø 1" 11,250.00 13,000.00 13,500.00 15,600.00
0.35 Ls Perlengkapan 35% x pipa 11,250.00 13,000.00 3,937.50 4,550.00
C PERALATAN
D Jumlah A + B + C 26,697.50 30,450.00
E Overhead & Profit (contoh 10%) 10% 2,669.75 3,045.00
F Harga Satuan Pekerjaan (D+E) 29,367.25 33,495.00

file:///conversion/tmp/scratch/415837925.xls 175/120 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 31,192.33 36,318.33
A Tenaga 13,890.00 15,450.00
L.01 0.054 OH Pekerja 75,000.00 85,000.00 4,050.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 14,466.67 17,566.67
1.20 m' Pipa PVC Ø 1½" 9,333.33 11,333.33 11,200.00 13,600.00
0.35 Ls Perlengkapan 35% x pipa 9,333.33 11,333.33 3,266.67 3,966.67
C PERALATAN
D Jumlah A + B + C 28,356.67 33,016.67
E Overhead & Profit (contoh 10%) 10% 2,835.67 3,301.67
F Harga Satuan Pekerjaan (D+E) 31,192.33 36,318.33

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 33,749.83 46,832.50


A Tenaga 13,890.00 15,450.00
L.01 0.054 OH Pekerja 75,000.00 85,000.00 4,050.00 4,590.00
L.02 0.090 OH Tukang Batu 95,000.00 105,000.00 8,550.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 120,000.00 990.00 1,080.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 16,791.67 27,125.00
1.20 m' Pipa PVC Ø 2" 10,833.33 17,500.00 13,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 10,833.33 17,500.00 3,791.67 6,125.00
C PERALATAN
D Jumlah A + B + C 30,681.67 42,575.00
E Overhead & Profit (contoh 10%) 10% 3,068.17 4,257.50
F Harga Satuan Pekerjaan (D+E) 33,749.83 46,832.50

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 58,384.33 78,002.83


A Tenaga 20,785.00 23,120.00
L.01 0.081 OH Pekerja 75,000.00 85,000.00 6,075.00 6,885.00
L.02 0.135 OH Tukang Batu 95,000.00 105,000.00 12,825.00 14,175.00
L.03 0.0135 OH Kepala Tukang 110,000.00 120,000.00 1,485.00 1,620.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 32,291.67 47,791.67
1.20 m' Pipa PVC Ø 3" 20,833.33 30,833.33 25,000.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 20,833.33 30,833.33 7,291.67 10,791.67
C PERALATAN
D Jumlah A + B + C 53,076.67 70,911.67
E Overhead & Profit (contoh 10%) 10% 5,307.67 7,091.17
F Harga Satuan Pekerjaan (D+E) 58,384.33 78,002.83

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 61,336.00 90,896.67


A Tenaga 9,260.00 10,300.00
L.01 0.036 OH Pekerja 75,000.00 85,000.00 2,700.00 3,060.00
L.02 0.060 OH Tukang Batu 95,000.00 105,000.00 5,700.00 6,300.00
L.03 0.006 OH Kepala Tukang 110,000.00 120,000.00 660.00 720.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan 46,500.00 72,333.33
1.20 m' Pipa PVC Ø 4" 30,000.00 46,666.67 36,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 30,000.00 46,666.67 10,500.00 16,333.33
C PERALATAN
D Jumlah A + B + C 55,760.00 82,633.33
E Overhead & Profit (contoh 10%) 10% 5,576.00 8,263.33
F Harga Satuan Pekerjaan (D+E) 61,336.00 90,896.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 78,969.00 87,747.00
cm
A Tenaga 10,640.00 11,920.00
L.01 0.080 OH Pekerja 75,000.00 85,000.00 6,000.00 6,800.00
L.02 0.040 OH Tukang Batu 95,000.00 105,000.00 3,800.00 4,200.00
L.03 0.004 OH Kepala Tukang 110,000.00 120,000.00 440.00 480.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 61,150.00 67,850.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,100.00 1,150.00 38,500.00 40,250.00
0.014 m3 Pasir Pasang 315,000.00 370,000.00 4,410.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 230,000.00 2,240.00 3,220.00
- -

file:///conversion/tmp/scratch/415837925.xls 175/121 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 71,790.00 79,770.00
E Overhead & Profit (contoh 10%) 10% 7,179.00 7,977.00
F Harga Satuan Pekerjaan (D+E) 78,969.00 87,747.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 37,526.50 43,230.00
cm
A Tenaga 7,980.00 8,940.00
L.01 0.060 OH Pekerja 75,000.00 85,000.00 4,500.00 5,100.00
L.02 0.030 OH Tukang Batu 95,000.00 105,000.00 2,850.00 3,150.00
L.03 0.003 OH Kepala Tukang 110,000.00 120,000.00 330.00 360.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 26,135.00 30,360.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,100.00 1,150.00 7,480.00 7,820.00
0.013 m3 Pasir Pasang 315,000.00 370,000.00 4,095.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 230,000.00 1,760.00 2,530.00
,
C PERALATAN
D Jumlah A + B + C 34,115.00 39,300.00
E Overhead & Profit (contoh 10%) 10% 3,411.50 3,930.00
F Harga Satuan Pekerjaan (D+E) 37,526.50 43,230.00

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 113,038.20 131,747.55


A Tenaga 18,620.00 20,860.00
L.01 0.140 OH Pekerja 75,000.00 85,000.00 10,500.00 11,900.00
L.02 0.070 OH Tukang Batu 95,000.00 105,000.00 6,650.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 120,000.00 770.00 840.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
B Bahan 84,142.00 98,910.50
1.10 bh pipa beton 42,000.00 50,000.00 46,200.00 55,000.00
0.027 m3 Batu Bata 450,000.00 487,500.00 12,150.00 13,162.50
3.920 kg Semen Portlan 1,100.00 1,150.00 4,312.00 4,508.00
0.056 m3 Pasir Pasang 315,000.00 370,000.00 17,640.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 230,000.00 3,840.00 5,520.00
C PERALATAN
D Jumlah A + B + C 102,762.00 119,770.50
E Overhead & Profit (contoh 10%) 10% 10,276.20 11,977.05
F Harga Satuan Pekerjaan (D+E) 113,038.20 131,747.55

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 579,243.50 624,976.00


A Tenaga 50,540.00 56,620.00
L.01 0.380 OH Pekerja 75,000.00 85,000.00 28,500.00 32,300.00
L.02 0.190 OH Tukang Batu 95,000.00 105,000.00 18,050.00 19,950.00
L.03 0.019 OH Kepala Tukang 110,000.00 120,000.00 2,090.00 2,280.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00
B Bahan 476,045.00 511,540.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 450,000.00 487,500.00 247,500.00 268,125.00
10.300 kg Semen Portlan 1,100.00 1,150.00 11,330.00 11,845.00
0.061 m3 Pasir Pasang 315,000.00 370,000.00 19,215.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 230,000.00 11,040.00 15,870.00
C PERALATAN
D Jumlah A + B + C 526,585.00 568,160.00
E Overhead & Profit (contoh 10%) 10% 52,658.50 56,816.00
F Harga Satuan Pekerjaan (D+E) 579,243.50 624,976.00

file:///conversion/tmp/scratch/415837925.xls 175/122 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 1 Titik Pemasangan Lampu 338,360.00 378,708.00


A Tenaga 153,800.00 172,140.00
100 % Pekerja 153,800.00 172,140.00 153,800.00 172,140.00

Bahan 153,800.00 172,140.00


3.00 btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
24.00 m Kabel **) 4,600.00 5,200.00 110,400.00 124,800.00
3.00 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4.00 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3.00 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24.00 buah Klem 50.00 60.00 1,200.00 1,440.00
1.00 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1.00 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00

1.00 buah Pitting 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 307,600.00 344,280.00
E Overhead & Profit (contoh 10%) 10% 30,760.00 34,428.00
F Harga Satuan Pekerjaan (D+E) 338,360.00 378,708.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 459,140.00 503,448.00
A Tenaga 208,700.00 228,840.00
L.01 100 % Pekerja 208,700.00 228,840.00 208,700.00 228,840.00

B Bahan 208,700.00 228,840.00


3 Kg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 4,600.00 5,200.00 69,000.00 78,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A + B + C 417,400.00 457,680.00
E Overhead & Profit (contoh 10%) 10% 41,740.00 45,768.00
F Harga Satuan Pekerjaan (D+E) 459,140.00 503,448.00

file:///conversion/tmp/scratch/415837925.xls 175/123 15-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN PEMASANGAN
XVI A.8.4.1
PIPA
1 A.8.4.1.1 1 m' Pemasangan Pipa PVC Ø 63 mm 14,931.95 17,344.25
A Tenaga 7,264.50 8,195.50
L.01 0.081 OH Pekerja 75,000.00 85,000.00 6,075.00 6,885.00
L.02 0.0041 OH Tukang Pipa 95,000.00 105,000.00 389.50 430.50
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00
B Bahan 6,250.00 7,500.00
1 m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 6,250.00 7,500.00
C PERALATAN 60.00 72.00
0.006 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 60.00 72.00
D Jumlah A + B + C 13,574.50 15,767.50
E Overhead & Profit (contoh 10%) 10% 1,357.45 1,576.75
F Harga Satuan Pekerjaan (D+E) 14,931.95 17,344.25

2 A.8.4.1.2 1 m' Pemasangan Pipa PVC Ø 90 mm 21,994.50 25,037.10


A Tenaga 12,415.00 13,915.00
L.01 0.094 OH Pekerja 75,000.00 85,000.00 7,050.00 7,990.00
L.02 0.047 OH Tukang Pipa 95,000.00 105,000.00 4,465.00 4,935.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
B Bahan 7,500.00 8,750.00
1 m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 7,500.00 8,750.00
C PERALATAN 80.00 96.00
0.008 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 80.00 96.00
D Jumlah A + B + C 19,995.00 22,761.00
E Overhead & Profit (contoh 10%) 10% 1,999.50 2,276.10
F Harga Satuan Pekerjaan (D+E) 21,994.50 25,037.10

3 A.8.4.1.3 1 m' Pemasangan Pipa PVC Ø 110 mm 25,696.00 31,702.00


A Tenaga 14,010.00 15,700.00
L.01 0.105 OH Pekerja 75,000.00 85,000.00 7,875.00 8,925.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00
B Bahan 9,250.00 13,000.00
1 m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 9,250.00 13,000.00
C PERALATAN 100.00 120.00
0.01 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 100.00 120.00
D Jumlah A + B + C 23,360.00 28,820.00
E Overhead & Profit (contoh 10%) 10% 2,336.00 2,882.00
F Harga Satuan Pekerjaan (D+E) 25,696.00 31,702.00

4 A.8.4.1.4 1 m' Pemasangan Pipa PVC Ø 150 mm 30,002.50 38,157.90


A Tenaga 15,655.00 17,545.00
L.01 0.118 OH Pekerja 75,000.00 85,000.00 8,850.00 10,030.00
L.02 0.059 OH Tukang Pipa 95,000.00 105,000.00 5,605.00 6,195.00
L.04 0.012 OH Mandor 100,000.00 110,000.00 1,200.00 1,320.00
B Bahan 11,500.00 17,000.00
1 m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 11,500.00 17,000.00
C PERALATAN 120.00 144.00
0.012 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 120.00 144.00
D Jumlah A + B + C 27,275.00 34,689.00
E Overhead & Profit (contoh 10%) 10% 2,727.50 3,468.90
F Harga Satuan Pekerjaan (D+E) 30,002.50 38,157.90

5 A.8.4.1.5 1 m' Pemasangan Pipa PVC Ø 200 mm 44,374.00 60,134.80


A Tenaga 25,100.00 28,130.00
L.01 0.189 OH Pekerja 75,000.00 85,000.00 14,175.00 16,065.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00
B Bahan 15,000.00 26,250.00
1 m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 15,000.00 26,250.00
C PERALATAN 240.00 288.00
0.024 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 240.00 288.00
D Jumlah A + B + C 40,340.00 54,668.00
E Overhead & Profit (contoh 10%) 10% 4,034.00 5,466.80
F Harga Satuan Pekerjaan (D+E) 44,374.00 60,134.80

6 A.8.4.1.6 1 m' Pemasangan Pipa PVC Ø 250 mm 59,730.00 93,189.80


A Tenaga 33,960.00 38,060.00
L.01 0.256 OH Pekerja 75,000.00 85,000.00 19,200.00 21,760.00
L.02 0.128 OH Tukang Pipa 95,000.00 105,000.00 12,160.00 13,440.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00
B Bahan 20,000.00 46,250.00
1 m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 20,000.00 46,250.00
C PERALATAN 340.00 408.00
0.034 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 340.00 408.00
D Jumlah A + B + C 54,300.00 84,718.00
E Overhead & Profit (contoh 10%) 10% 5,430.00 8,471.80
F Harga Satuan Pekerjaan (D+E) 59,730.00 93,189.80

7 A.8.4.1.7 1 m' Pemasangan Pipa PVC Ø 300 mm 92,746.50 125,504.50


A Tenaga 38,915.00 43,615.00
L.01 0.294 OH Pekerja 75,000.00 85,000.00 22,050.00 24,990.00
L.02 0.147 OH Tukang Pipa 95,000.00 105,000.00 13,965.00 15,435.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00
B Bahan 45,000.00 70,000.00
1 m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 45,000.00 70,000.00
C PERALATAN 400.00 480.00
0.040 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 400.00 480.00
D Jumlah A + B + C 84,315.00 114,095.00
E Overhead & Profit (contoh 10%) 10% 8,431.50 11,409.50
F Harga Satuan Pekerjaan (D+E) 92,746.50 125,504.50

8 A.8.4.1.8 1 m' Pemasangan Pipa PVC Ø 400 mm 176,374.00 241,120.00


A Tenaga 72,040.00 80,740.00
L.01 0.544 OH Pekerja 75,000.00 85,000.00 40,800.00 46,240.00
L.02 0.272 OH Tukang Pipa 95,000.00 105,000.00 25,840.00 28,560.00
L.04 0.054 OH Mandor 100,000.00 110,000.00 5,400.00 5,940.00
B Bahan 87,500.00 137,500.00
1 m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 87,500.00 137,500.00
C PERALATAN 800.00 960.00
0.080 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 800.00 960.00
D Jumlah A + B + C 160,340.00 219,200.00
E Overhead & Profit (contoh 10%) 10% 16,034.00 21,920.00
F Harga Satuan Pekerjaan (D+E) 176,374.00 241,120.00

9 A.8.4.1.9 1 m' Pemasangan Pipa PVC Ø 450 mm 346,170.00 399,421.00


A Tenaga 88,700.00 99,410.00
L.01 0.669 OH Pekerja 75,000.00 85,000.00 50,175.00 56,865.00
L.02 0.335 OH Tukang Pipa 95,000.00 105,000.00 31,825.00 35,175.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00
B Bahan 225,000.00 262,500.00
1 m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 225,000.00 262,500.00
C PERALATAN 1,000.00 1,200.00
0.100 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00
D Jumlah A + B + C 314,700.00 363,110.00
E Overhead & Profit (contoh 10%) 10% 31,470.00 36,311.00
F Harga Satuan Pekerjaan (D+E) 346,170.00 399,421.00

10 A.8.4.1.10 1 m' Pemasangan Pipa PVC Ø 500 mm 427,317.00 447,330.40


A Tenaga 107,250.00 120,200.00
L.01 0.809 OH Pekerja 75,000.00 85,000.00 60,675.00 68,765.00
L.02 0.405 OH Tukang Pipa 95,000.00 105,000.00 38,475.00 42,525.00
L.04 0.081 OH Mandor 100,000.00 110,000.00 8,100.00 8,910.00
B Bahan 280,000.00 285,000.00
1 m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 280,000.00 285,000.00
C PERALATAN 1,220.00 1,464.00
0.122 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,220.00 1,464.00
D Jumlah A + B + C 388,470.00 406,664.00
E Overhead & Profit (contoh 10%) 10% 38,847.00 40,666.40
F Harga Satuan Pekerjaan (D+E) 427,317.00 447,330.40

11 A.8.4.1.11 1 m' Pemasangan Pipa PVC Ø 600 mm 498,349.50 537,487.50


A Tenaga 126,595.00 141,885.00
L.01 0.957 OH Pekerja 75,000.00 85,000.00 71,775.00 81,345.00
L.02 0.476 OH Tukang Pipa 95,000.00 105,000.00 45,220.00 49,980.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan 325,000.00 345,000.00
1 m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 325,000.00 345,000.00
C PERALATAN 1,450.00 1,740.00
0.145 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,450.00 1,740.00
D Jumlah A + B + C 453,045.00 488,625.00
E Overhead & Profit (contoh 10%) 10% 45,304.50 48,862.50
F Harga Satuan Pekerjaan (D+E) 498,349.50 537,487.50

12 A.8.4.1.12 1 m' Pemasangan Pipa PVC Ø 800 mm 706,095.50 762,624.50


A Tenaga 214,405.00 240,295.00
L.01 1.618 OH Pekerja 75,000.00 85,000.00 121,350.00 137,530.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00
B Bahan 425,000.00 450,000.00
1 m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 425,000.00 450,000.00
C PERALATAN 2,500.00 3,000.00
0.250 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,500.00 3,000.00
D Jumlah A + B + C 641,905.00 693,295.00
E Overhead & Profit (contoh 10%) 10% 64,190.50 69,329.50
F Harga Satuan Pekerjaan (D+E) 706,095.50 762,624.50

13 A.8.4.1.13 1 m' Pemasangan Pipa PVC Ø 900 mm 936,886.50 994,728.90


A Tenaga 224,095.00 251,155.00
L.01 1.691 OH Pekerja 75,000.00 85,000.00 126,825.00 143,735.00
L.02 0.846 OH Tukang Pipa 95,000.00 105,000.00 80,370.00 88,830.00
L.04 0.169 OH Mandor 100,000.00 110,000.00 16,900.00 18,590.00
B Bahan 625,000.00 650,000.00
1 m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 625,000.00 650,000.00
C PERALATAN 2,620.00 3,144.00
0.262 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,620.00 3,144.00
D Jumlah A + B + C 851,715.00 904,299.00
E Overhead & Profit (contoh 10%) 10% 85,171.50 90,429.90
F Harga Satuan Pekerjaan (D+E) 936,886.50 994,728.90

14 A.8.4.1.14 1 m' Pemasangan Pipa PVC Ø 1.000 mm 1,082,537.50 1,138,547.30


A Tenaga 251,185.00 281,515.00
L.01 1.895 OH Pekerja 75,000.00 85,000.00 142,125.00 161,075.00
L.02 0.948 OH Tukang Pipa 95,000.00 105,000.00 90,060.00 99,540.00
L.04 0.190 OH Mandor 100,000.00 110,000.00 19,000.00 20,900.00
B Bahan 730,000.00 750,000.00
1 m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 730,000.00 750,000.00
C PERALATAN 2,940.00 3,528.00
0.294 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,940.00 3,528.00
D Jumlah A + B + C 984,125.00 1,035,043.00
E Overhead & Profit (contoh 10%) 10% 98,412.50 103,504.30
F Harga Satuan Pekerjaan (D+E) 1,082,537.50 1,138,547.30

15 A.8.4.1.15 1 m' Pemasangan Pipa PVC Ø 1.100 mm 1,189,589.50 1,282,257.90


A Tenaga 278,175.00 311,765.00
L.01 2.099 OH Pekerja 75,000.00 85,000.00 157,425.00 178,415.00
L.02 1.050 OH Tukang Pipa 95,000.00 105,000.00 99,750.00 110,250.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 800,000.00 850,000.00
1 m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 800,000.00 850,000.00
C PERALATAN 3,270.00 3,924.00
0.327 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,270.00 3,924.00
D Jumlah A + B + C 1,081,445.00 1,165,689.00
E Overhead & Profit (contoh 10%) 10% 108,144.50 116,568.90
F Harga Satuan Pekerjaan (D+E) 1,189,589.50 1,282,257.90

16 A.8.4.1.16 1 m' Pemasangan Pipa PVC Ø 1.200 mm 1,274,630.50 1,370,955.30


A Tenaga 305,165.00 342,015.00
L.01 2.303 OH Pekerja 75,000.00 85,000.00 172,725.00 195,755.00
L.02 1.152 OH Tukang Pipa 95,000.00 105,000.00 109,440.00 120,960.00
L.04 0.230 OH Mandor 100,000.00 110,000.00 23,000.00 25,300.00
B Bahan 850,000.00 900,000.00
1 m' Pipa PVC Ø 1.200 mm 850,000.00 900,000.00 850,000.00 900,000.00
C PERALATAN 3,590.00 4,308.00
0.359 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,590.00 4,308.00
D Jumlah A + B + C 1,158,755.00 1,246,323.00
E Overhead & Profit (contoh 10%) 10% 115,875.50 124,632.30
F Harga Satuan Pekerjaan (D+E) 1,274,630.50 1,370,955.30

17 A.8.4.1.17 1 m' Pemasangan Pipa HDPE Ø 63 mm 32,703.00 38,849.80


A Tenaga 4,540.00 5,090.00
L.01 0.035 OH Pekerja 75,000.00 85,000.00 2,625.00 2,975.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan 25,000.00 30,000.00
1 m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 29,730.00 35,318.00
E Overhead & Profit (contoh 10%) 10% 2,973.00 3,531.80
F Harga Satuan Pekerjaan (D+E) 32,703.00 38,849.80

18 A.8.4.1.18 1 m' Pemasangan Pipa HDPE Ø 100 mm 44,539.00 50,784.80


A Tenaga 5,300.00 5,940.00
L.01 0.040 OH Pekerja 75,000.00 85,000.00 3,000.00 3,400.00
L.02 0.020 OH Tukang Pipa 95,000.00 105,000.00 1,900.00 2,100.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
B Bahan 35,000.00 40,000.00
1 m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 35,000.00 40,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 40,490.00 46,168.00
E Overhead & Profit (contoh 10%) 10% 4,049.00 4,616.80
F Harga Satuan Pekerjaan (D+E) 44,539.00 50,784.80

19 A.8.4.1.19 1 m' Pemasangan Pipa HDPE Ø 125 mm 56,375.00 62,719.80


A Tenaga 6,060.00 6,790.00
L.01 0.045 OH Pekerja 75,000.00 85,000.00 3,375.00 3,825.00
L.02 0.023 OH Tukang Pipa 95,000.00 105,000.00 2,185.00 2,415.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00
B Bahan 45,000.00 50,000.00
1 m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 51,250.00 57,018.00
E Overhead & Profit (contoh 10%) 10% 5,125.00 5,701.80
F Harga Satuan Pekerjaan (D+E) 56,375.00 62,719.80

20 A.8.4.1.20 1 m' Pemasangan Pipa HDPE Ø 150 mm 80,723.50 87,354.30


A Tenaga 8,195.00 9,185.00
L.01 0.062 OH Pekerja 75,000.00 85,000.00 4,650.00 5,270.00
L.02 0.031 OH Tukang Pipa 95,000.00 105,000.00 2,945.00 3,255.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00
B Bahan 65,000.00 70,000.00
1 m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 73,385.00 79,413.00
E Overhead & Profit (contoh 10%) 10% 7,338.50 7,941.30
F Harga Satuan Pekerjaan (D+E) 80,723.50 87,354.30

21 A.8.4.1.21 1 m' Pemasangan Pipa HDPE Ø 200 mm 136,053.50 148,888.30


A Tenaga 13,495.00 15,125.00
L.01 0.102 OH Pekerja 75,000.00 85,000.00 7,650.00 8,670.00
L.02 0.051 OH Tukang Pipa 95,000.00 105,000.00 4,845.00 5,355.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00
B Bahan 110,000.00 120,000.00
1 m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 110,000.00 120,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 123,685.00 135,353.00
E Overhead & Profit (contoh 10%) 10% 12,368.50 13,535.30
F Harga Satuan Pekerjaan (D+E) 136,053.50 148,888.30

22 A.8.4.1.22 1 m' Pemasangan Pipa HDPE Ø 250 mm 168,366.00 176,301.40


A Tenaga 17,640.00 19,770.00
L.01 0.133 OH Pekerja 75,000.00 85,000.00 9,975.00 11,305.00
L.02 0.067 OH Tukang Pipa 95,000.00 105,000.00 6,365.00 7,035.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00
B Bahan 135,000.00 140,000.00
1 m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 135,000.00 140,000.00
C PERALATAN 420.00 504.00
0.042 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 420.00 504.00
D Jumlah A + B + C 153,060.00 160,274.00
E Overhead & Profit (contoh 10%) 10% 15,306.00 16,027.40
F Harga Satuan Pekerjaan (D+E) 168,366.00 176,301.40

23 A.8.4.1.23 1 m' Pemasangan Pipa HDPE Ø 300 mm 201,492.50 215,627.50


A Tenaga 22,525.00 25,245.00
L.01 0.170 OH Pekerja 75,000.00 85,000.00 12,750.00 14,450.00
L.02 0.085 OH Tukang Pipa 95,000.00 105,000.00 8,075.00 8,925.00
L.04 0.017 OH Mandor 100,000.00 110,000.00 1,700.00 1,870.00
B Bahan 160,000.00 170,000.00
1 m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 160,000.00 170,000.00
C PERALATAN 650.00 780.00
0.065 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 650.00 780.00
D Jumlah A + B + C 183,175.00 196,025.00
E Overhead & Profit (contoh 10%) 10% 18,317.50 19,602.50
F Harga Satuan Pekerjaan (D+E) 201,492.50 215,627.50

24 A.8.4.1.24 1 m' Pemasangan Pipa HDPE Ø 400 mm 263,939.50 280,377.90


A Tenaga 38,425.00 43,065.00
L.01 0.290 OH Pekerja 75,000.00 85,000.00 21,750.00 24,650.00
L.02 0.145 OH Tukang Pipa 95,000.00 105,000.00 13,775.00 15,225.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00
B Bahan 200,000.00 210,000.00
1 m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 1,520.00 1,824.00
0.152 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,520.00 1,824.00
D Jumlah A + B + C 239,945.00 254,889.00
E Overhead & Profit (contoh 10%) 10% 23,994.50 25,488.90
F Harga Satuan Pekerjaan (D+E) 263,939.50 280,377.90

25 A.8.4.1.25 1 m' Pemasangan Pipa HDPE Ø 450 mm 318,587.50 336,352.50


A Tenaga 47,625.00 53,375.00
L.01 0.359 OH Pekerja 75,000.00 85,000.00 26,925.00 30,515.00
L.02 0.180 OH Tukang Pipa 95,000.00 105,000.00 17,100.00 18,900.00
L.04 0.036 OH Mandor 100,000.00 110,000.00 3,600.00 3,960.00
B Bahan 240,000.00 250,000.00
1 m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 2,000.00 2,400.00
0.200 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,000.00 2,400.00
D Jumlah A + B + C 289,625.00 305,775.00
E Overhead & Profit (contoh 10%) 10% 28,962.50 30,577.50
F Harga Satuan Pekerjaan (D+E) 318,587.50 336,352.50

26 A.8.4.1.26 1 m' Pemasangan Pipa HDPE Ø 500 mm 395,785.50 425,949.70


A Tenaga 57,295.00 64,215.00
L.01 0.433 OH Pekerja 75,000.00 85,000.00 32,475.00 36,805.00
L.02 0.216 OH Tukang Pipa 95,000.00 105,000.00 20,520.00 22,680.00
L.04 0.043 OH Mandor 100,000.00 110,000.00 4,300.00 4,730.00

B Bahan 300,000.00 320,000.00


1 m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 2,510.00 3,012.00


0.251 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,510.00 3,012.00

D Jumlah A + B + C 359,805.00 387,227.00


E Overhead & Profit (contoh 10%) 10% 35,980.50 38,722.70
F Harga Satuan Pekerjaan (D+E) 395,785.50 425,949.70

27 A.8.4.1.27 1 m' Pemasangan Pipa HDPE Ø 600 mm 550,979.00 582,663.40


A Tenaga 67,820.00 76,010.00
L.01 0.512 OH Pekerja 75,000.00 85,000.00 38,400.00 43,520.00
L.02 0.256 OH Tukang Pipa 95,000.00 105,000.00 24,320.00 26,880.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 430,000.00 450,000.00


1 m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 3,070.00 3,684.00


0.307 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,070.00 3,684.00

D Jumlah A + B + C 500,890.00 529,694.00


E Overhead & Profit (contoh 10%) 10% 50,089.00 52,969.40
F Harga Satuan Pekerjaan (D+E) 550,979.00 582,663.40

28 A.8.4.1.28 1 m' Pemasangan Pipa HDPE Ø 800 mm 851,372.50 895,841.10


A Tenaga 118,245.00 132,525.00
L.01 0.893 OH Pekerja 75,000.00 85,000.00 66,975.00 75,905.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.089 OH Mandor 100,000.00 110,000.00 8,900.00 9,790.00

B Bahan 650,000.00 675,000.00


1 m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 650,000.00 675,000.00

C PERALATAN 5,730.00 6,876.00


0.573 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,730.00 6,876.00

D Jumlah A + B + C 773,975.00 814,401.00


E Overhead & Profit (contoh 10%) 10% 77,397.50 81,440.10
F Harga Satuan Pekerjaan (D+E) 851,372.50 895,841.10

29 A.8.4.1.29 1 m' Pemasangan Pipa HDPE Ø 900 mm 1,031,932.00 1,112,689.60


A Tenaga 179,290.00 200,940.00
L.01 1.353 OH Pekerja 75,000.00 85,000.00 101,475.00 115,005.00
L.02 0.677 OH Tukang Pipa 95,000.00 105,000.00 64,315.00 71,085.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 750,000.00 800,000.00


1 m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 750,000.00 800,000.00
C PERALATAN 8,830.00 10,596.00
0.883 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,830.00 10,596.00

D Jumlah A + B + C 938,120.00 1,011,536.00


E Overhead & Profit (contoh 10%) 10% 93,812.00 101,153.60
F Harga Satuan Pekerjaan (D+E) 1,031,932.00 1,112,689.60

30 A.8.4.1.30 1 m' Pemasangan Pipa HDPE Ø 1.000 mm 1,243,885.50 1,302,995.10


A 219,875.00 246,425.00
L.01 1.659 OH Pekerja 75,000.00 85,000.00 124,425.00 141,015.00
L.02 0.830 OH Tukang Pipa 95,000.00 105,000.00 78,850.00 87,150.00
L.04 0.166 OH Mandor 100,000.00 110,000.00 16,600.00 18,260.00

B Bahan 900,000.00 925,000.00


1 m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 900,000.00 925,000.00

C PERALATAN 10,930.00 13,116.00


1.093 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,930.00 13,116.00

D Jumlah A + B + C 1,130,805.00 1,184,541.00


E Overhead & Profit (contoh 10%) 10% 113,080.50 118,454.10
F Harga Satuan Pekerjaan (D+E) 1,243,885.50 1,302,995.10

31 A.8.4.1.31 1 m' Pemasangan Pipa HDPE Ø 1.100 mm 1,378,250.50 1,467,900.50


A Tenaga 240,905.00 269,995.00
L.01 1.818 OH Pekerja 75,000.00 85,000.00 136,350.00 154,530.00
L.02 0.909 OH Tukang Pipa 95,000.00 105,000.00 86,355.00 95,445.00
L.04 0.182 OH Mandor 100,000.00 110,000.00 18,200.00 20,020.00

B Bahan 1,000,000.00 1,050,000.00


1 m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 1,000,000.00 1,050,000.00

C PERALATAN 12,050.00 14,460.00


1.205 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,050.00 14,460.00

D Jumlah A + B + C 1,252,955.00 1,334,455.00


E Overhead & Profit (contoh 10%) 10% 125,295.50 133,445.50
F Harga Satuan Pekerjaan (D+E) 1,378,250.50 1,467,900.50

32 A.8.4.1.32 1 m' Pemasangan Pipa HDPE Ø 1.200 mm 1,572,851.50 1,673,048.30


A Tenaga 314,025.00 351,945.00
L.01 2.370 OH Pekerja 75,000.00 85,000.00 177,750.00 201,450.00
L.02 1.185 OH Tukang Pipa 95,000.00 105,000.00 112,575.00 124,425.00
L.04 0.237 OH Mandor 100,000.00 110,000.00 23,700.00 26,070.00

B Bahan 1,100,000.00 1,150,000.00


1 m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 1,100,000.00 1,150,000.00
C PERALATAN 15,840.00 19,008.00
1.584 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 15,840.00 19,008.00
D Jumlah A + B + C 1,429,865.00 1,520,953.00
E Overhead & Profit (contoh 10%) 10% 142,986.50 152,095.30
F Harga Satuan Pekerjaan (D+E) 1,572,851.50 1,673,048.30

33 A.8.4.1.33 1 m' Pemasangan Pipa GIP Ø 63 mm 66,676.50 75,487.50


A Tenaga 45,615.00 51,125.00
L.01 0.345 OH Pekerja 75,000.00 85,000.00 25,875.00 29,325.00
L.02 0.172 OH Tukang Pipa 95,000.00 105,000.00 16,340.00 18,060.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan 15,000.00 17,500.00
1 m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 15,000.00 17,500.00
C PERALATAN - -

hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
D Jumlah A + B + C 60,615.00 68,625.00
E Overhead & Profit (contoh 10%) 10% 6,061.50 6,862.50
F Harga Satuan Pekerjaan (D+E) 66,676.50 75,487.50
34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 79,383.33 92,840.00
A Tenaga 53,000.00 59,400.00
L.01 0.400 OH Pekerja 75,000.00 85,000.00 30,000.00 34,000.00
L.02 0.200 OH Tukang Pipa 95,000.00 105,000.00 19,000.00 21,000.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00

B Bahan 19,166.67 25,000.00


1 m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 19,166.67 25,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 72,166.67 84,400.00


E Overhead & Profit (contoh 10%) 10% 7,216.67 8,440.00
F Harga Satuan Pekerjaan (D+E) 79,383.33 92,840.00

35 A.8.4.1.35 1 m' Pemasangan Pipa GIP Ø 125 mm 90,068.00 106,205.00


A Tenaga 59,380.00 66,550.00
L.01 0.448 OH Pekerja 75,000.00 85,000.00 33,600.00 38,080.00
L.02 0.224 OH Tukang Pipa 95,000.00 105,000.00 21,280.00 23,520.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00

B Bahan 22,500.00 30,000.00


1 m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 22,500.00 30,000.00

C PERALATAN
D Jumlah A + B + C 81,880.00 96,550.00
E Overhead & Profit (contoh 10%) 10% 8,188.00 9,655.00
F Harga Satuan Pekerjaan (D+E) 90,068.00 106,205.00

36 A.8.4.1.36 1 m' Pemasangan Pipa GIP Ø 150 mm 104,960.17 123,036.83


A Tenaga 67,085.00 75,185.00
L.01 0.506 OH Pekerja 75,000.00 85,000.00 37,950.00 43,010.00
L.02 0.253 OH Tukang Pipa 95,000.00 105,000.00 24,035.00 26,565.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 28,333.33 36,666.67


1 m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 28,333.33 36,666.67

C PERALATAN
D Jumlah A + B + C 95,418.33 111,851.67
E Overhead & Profit (contoh 10%) 10% 9,541.83 11,185.17
F Harga Satuan Pekerjaan (D+E) 104,960.17 123,036.83

37 A.8.4.1.37 1 m' Pemasangan Pipa GIP Ø 200 mm 157,311.00 183,241.67


A Tenaga 105,510.00 118,250.00
L.01 0.796 OH Pekerja 75,000.00 85,000.00 59,700.00 67,660.00
L.02 0.398 OH Tukang Pipa 95,000.00 105,000.00 37,810.00 41,790.00
L.04 0.080 OH Mandor 100,000.00 110,000.00 8,000.00 8,800.00

B Bahan 37,500.00 48,333.33


1 m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 37,500.00 48,333.33

C PERALATAN
D Jumlah A + B + C 143,010.00 166,583.33
E Overhead & Profit (contoh 10%) 10% 14,301.00 16,658.33
F Harga Satuan Pekerjaan (D+E) 157,311.00 183,241.67

38 A.8.4.1.38 1 m' Pemasangan Pipa GIP Ø 250 mm 187,880.00 219,255.67


A Tenaga 125,800.00 140,990.00
L.01 0.949 OH Pekerja 75,000.00 85,000.00 71,175.00 80,665.00
L.02 0.475 OH Tukang Pipa 95,000.00 105,000.00 45,125.00 49,875.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00
B Bahan 45,000.00 58,333.33
1 m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 45,000.00 58,333.33

C PERALATAN
D Jumlah A + B + C 170,800.00 199,323.33
E Overhead & Profit (contoh 10%) 10% 17,080.00 19,932.33
F Harga Satuan Pekerjaan (D+E) 187,880.00 219,255.67

39 A.8.4.1.39 1 m' Pemasangan Pipa GIP Ø 300 mm 216,650.50 246,346.83


A Tenaga 126,955.00 142,285.00
L.01 0.958 OH Pekerja 75,000.00 85,000.00 71,850.00 81,430.00
L.02 0.479 OH Tukang Pipa 95,000.00 105,000.00 45,505.00 50,295.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00

B Bahan 70,000.00 81,666.67


1 m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 70,000.00 81,666.67

C PERALATAN
D Jumlah A + B + C 196,955.00 223,951.67
E Overhead & Profit (contoh 10%) 10% 19,695.50 22,395.17
F Harga Satuan Pekerjaan (D+E) 216,650.50 246,346.83

40 A.8.4.1.40 1 m' Pemasangan Pipa GIP Ø 400 mm 279,293.67 304,289.33


A Tenaga 160,570.00 179,960.00
L.01 1.212 OH Pekerja 75,000.00 85,000.00 90,900.00 103,020.00
L.02 0.606 OH Tukang Pipa 95,000.00 105,000.00 57,570.00 63,630.00
L.04 0.121 OH Mandor 100,000.00 110,000.00 12,100.00 13,310.00

B Bahan 93,333.33 96,666.67


1 m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 93,333.33 96,666.67

C PERALATAN
D Jumlah A + B + C 253,903.33 276,626.67
E Overhead & Profit (contoh 10%) 10% 25,390.33 27,662.67
F Harga Satuan Pekerjaan (D+E) 279,293.67 304,289.33

41 A.8.4.1.41 1 m' Pemasangan Pipa GIP Ø 450 mm 318,114.50 352,918.50


A Tenaga 179,195.00 200,835.00
L.01 1.353 OH Pekerja 75,000.00 85,000.00 101,475.00 115,005.00
L.02 0.676 OH Tukang Pipa 95,000.00 105,000.00 64,220.00 70,980.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 110,000.00 120,000.00


1 m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 110,000.00 120,000.00

C PERALATAN
D Jumlah A + B + C 289,195.00 320,835.00
E Overhead & Profit (contoh 10%) 10% 28,919.50 32,083.50
F Harga Satuan Pekerjaan (D+E) 318,114.50 352,918.50

42 A.8.4.1.42 1 m' Pemasangan Pipa GIP Ø 500 mm 368,170.00 405,031.00


A Tenaga 194,700.00 218,210.00
L.01 1.469 OH Pekerja 75,000.00 85,000.00 110,175.00 124,865.00
L.02 0.735 OH Tukang Pipa 95,000.00 105,000.00 69,825.00 77,175.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 140,000.00 150,000.00


1 m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN
D Jumlah A + B + C 334,700.00 368,210.00
E Overhead & Profit (contoh 10%) 10% 33,470.00 36,821.00
F Harga Satuan Pekerjaan (D+E) 368,170.00 405,031.00
43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 369,495.50 403,859.50
A Tenaga 175,905.00 197,145.00
L.01 1.327 OH Pekerja 75,000.00 85,000.00 99,525.00 112,795.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 160,000.00 170,000.00


1 m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN
D Jumlah A + B + C 335,905.00 367,145.00
E Overhead & Profit (contoh 10%) 10% 33,590.50 36,714.50
F Harga Satuan Pekerjaan (D+E) 369,495.50 403,859.50

44 A.8.4.1.44 1 m' Pemasangan Pipa GIP Ø 800 mm 559,141.00 611,094.00


A Tenaga 308,310.00 345,540.00
L.01 2.327 OH Pekerja 75,000.00 85,000.00 174,525.00 197,795.00
L.02 1.163 OH Tukang Pipa 95,000.00 105,000.00 110,485.00 122,115.00
L.04 0.233 OH Mandor 100,000.00 110,000.00 23,300.00 25,630.00

B Bahan 200,000.00 210,000.00


1 m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN
D Jumlah A + B + C 508,310.00 555,540.00
E Overhead & Profit (contoh 10%) 10% 50,831.00 55,554.00
F Harga Satuan Pekerjaan (D+E) 559,141.00 611,094.00

45 A.8.4.1.45 1 m' Pemasangan Pipa GIP Ø 900 mm 635,321.50 703,488.50


A Tenaga 347,565.00 389,535.00
L.01 2.623 OH Pekerja 75,000.00 85,000.00 196,725.00 222,955.00
L.02 1.312 OH Tukang Pipa 95,000.00 105,000.00 124,640.00 137,760.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan 230,000.00 250,000.00


1 m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 230,000.00 250,000.00

C PERALATAN
D Jumlah A + B + C 577,565.00 639,535.00
E Overhead & Profit (contoh 10%) 10% 57,756.50 63,953.50
F Harga Satuan Pekerjaan (D+E) 635,321.50 703,488.50

46 A.8.4.1.46 1 m' Pemasangan Pipa GIP Ø 1.000 mm 710,319.50 772,557.50


A Tenaga 385,745.00 432,325.00
L.01 2.911 OH Pekerja 75,000.00 85,000.00 218,325.00 247,435.00
L.02 1.456 OH Tukang Pipa 95,000.00 105,000.00 138,320.00 152,880.00
L.04 0.291 OH Mandor 100,000.00 110,000.00 29,100.00 32,010.00
B Bahan 260,000.00 270,000.00
1 m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 260,000.00 270,000.00
C PERALATAN
D Jumlah A + B + C 645,745.00 702,325.00
E Overhead & Profit (contoh 10%) 10% 64,574.50 70,232.50
F Harga Satuan Pekerjaan (D+E) 710,319.50 772,557.50

47 A.8.4.1.47 1 m' Pemasangan Pipa GIP Ø 1.100 mm 774,400.00 841,720.00


A Tenaga 424,000.00 475,200.00
L.01 3.200 OH Pekerja 75,000.00 85,000.00 240,000.00 272,000.00
L.02 1.600 OH Tukang Pipa 95,000.00 105,000.00 152,000.00 168,000.00
L.04 0.320 OH Mandor 100,000.00 110,000.00 32,000.00 35,200.00
B Bahan 280,000.00 290,000.00
1 m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 280,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 704,000.00 765,200.00
E Overhead & Profit (contoh 10%) 10% 70,400.00 76,520.00
F Harga Satuan Pekerjaan (D+E) 774,400.00 841,720.00
48 A.8.4.1.48 1 m' Pemasangan Pipa GIP Ø 1.200 mm 849,398.00 921,789.00
A Tenaga 462,180.00 517,990.00
L.01 3.488 OH Pekerja 75,000.00 85,000.00 261,600.00 296,480.00
L.02 1.744 OH Tukang Pipa 95,000.00 105,000.00 165,680.00 183,120.00
L.04 0.349 OH Mandor 100,000.00 110,000.00 34,900.00 38,390.00

B Bahan 310,000.00 320,000.00


1 m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 310,000.00 320,000.00
C PERALATAN
D Jumlah A + B + C 772,180.00 837,990.00
E Overhead & Profit (contoh 10%) 10% 77,218.00 83,799.00
F Harga Satuan Pekerjaan (D+E) 849,398.00 921,789.00

49 A.8.4.1.49 1 m' Pemasangan Pipa DCI Ø 100 mm 83,891.50 96,471.10


A Tenaga 50,885.00 57,245.00
L.01 0.489 OH Pekerja 75,000.00 85,000.00 36,675.00 41,565.00
L.02 0.098 OH Tukang Pipa 95,000.00 105,000.00 9,310.00 10,290.00
L.04 0.049 OH Mandor 100,000.00 110,000.00 4,900.00 5,390.00
B Bahan 25,000.00 30,000.00
1 m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 76,265.00 87,701.00
E Overhead & Profit (contoh 10%) 10% 7,626.50 8,770.10
F Harga Satuan Pekerjaan (D+E) 83,891.50 96,471.10

50 A.8.4.1.50 1 m' Pemasangan Pipa DCI Ø 125 mm 106,986.00 120,390.60


A Tenaga 56,880.00 63,990.00
L.01 0.547 OH Pekerja 75,000.00 85,000.00 41,025.00 46,495.00
L.02 0.109 OH Tukang Pipa 95,000.00 105,000.00 10,355.00 11,445.00
L.04 0.055 OH Mandor 100,000.00 110,000.00 5,500.00 6,050.00
B Bahan 40,000.00 45,000.00
1 m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 40,000.00 45,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 97,260.00 109,446.00
E Overhead & Profit (contoh 10%) 10% 9,726.00 10,944.60
F Harga Satuan Pekerjaan (D+E) 106,986.00 120,390.60

51 A.8.4.1.51 1 m' Pemasangan Pipa DCI Ø 150 mm 136,554.00 156,404.60


A Tenaga 63,760.00 71,730.00
L.01 0.613 OH Pekerja 75,000.00 85,000.00 45,975.00 52,105.00
L.02 0.123 OH Tukang Pipa 95,000.00 105,000.00 11,685.00 12,915.00
L.04 0.061 OH Mandor 100,000.00 110,000.00 6,100.00 6,710.00
B Bahan 60,000.00 70,000.00
1 m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 60,000.00 70,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 124,140.00 142,186.00
E Overhead & Profit (contoh 10%) 10% 12,414.00 14,218.60
F Harga Satuan Pekerjaan (D+E) 136,554.00 156,404.60

52 A.8.4.1.52 1 m' Pemasangan Pipa DCI Ø 200 mm 186,175.00 209,479.60


A Tenaga 88,870.00 99,980.00
L.01 0.855 OH Pekerja 75,000.00 85,000.00 64,125.00 72,675.00
L.02 0.171 OH Tukang Pipa 95,000.00 105,000.00 16,245.00 17,955.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00
B Bahan 80,000.00 90,000.00
1 m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 80,000.00 90,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 169,250.00 190,436.00
E Overhead & Profit (contoh 10%) 10% 16,925.00 19,043.60
F Harga Satuan Pekerjaan (D+E) 186,175.00 209,479.60
53 A.8.4.1.53 1 m' Pemasangan Pipa DCI Ø 250 mm 219,312.50 244,018.50
A Tenaga 98,875.00 111,235.00
L.01 0.951 OH Pekerja 75,000.00 85,000.00 71,325.00 80,835.00
L.02 0.190 OH Tukang Pipa 95,000.00 105,000.00 18,050.00 19,950.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00

B Bahan 100,000.00 110,000.00


1 m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 500.00 600.00


0.050 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 500.00 600.00

D Jumlah A + B + C 199,375.00 221,835.00


E Overhead & Profit (contoh 10%) 10% 19,937.50 22,183.50
F Harga Satuan Pekerjaan (D+E) 219,312.50 244,018.50

54 A.8.4.1.54 1 m' Pemasangan Pipa DCI Ø 300 mm 244,101.00 269,172.20


A Tenaga 101,200.00 113,850.00
L.01 0.973 OH Pekerja 75,000.00 85,000.00 72,975.00 82,705.00
L.02 0.195 OH Tukang Pipa 95,000.00 105,000.00 18,525.00 20,475.00
L.04 0.097 OH Mandor 100,000.00 110,000.00 9,700.00 10,670.00

B Bahan 120,000.00 130,000.00


1 m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 120,000.00 130,000.00

C PERALATAN 710.00 852.00


0.071 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 710.00 852.00

D Jumlah A + B + C 221,910.00 244,702.00


E Overhead & Profit (contoh 10%) 10% 22,191.00 24,470.20
F Harga Satuan Pekerjaan (D+E) 244,101.00 269,172.20

55 A.8.4.1.55 1 m' Pemasangan Pipa DCI Ø 400 mm 366,624.50 401,441.70


A Tenaga 175,510.00 196,985.00
L.01 1.545 OH Pekerja 75,000.00 85,000.00 115,875.00 131,325.00
L.02 0.309 OH Tukang Pipa 95,000.00 105,000.00 29,355.00 32,445.00
L.08 0.093 OH Operator Alat Berat 160,000.00 175,000.00 14,880.00 16,275.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00
B Bahan 150,000.00 160,000.00
1 m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 150,000.00 160,000.00

C PERALATAN 7,785.00 7,962.00


0.023 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 7,475.00 7,590.00
0.031 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 310.00 372.00
D Jumlah A + B + C 333,295.00 364,947.00
E Overhead & Profit (contoh 10%) 10% 33,329.50 36,494.70
F Harga Satuan Pekerjaan (D+E) 366,624.50 401,441.70

56 A.8.4.1.56 1 m' Pemasangan Pipa DCI Ø 450 mm 430,380.50 464,412.30


A Tenaga 211,440.00 237,155.00
L.01 1.813 OH Pekerja 75,000.00 85,000.00 135,975.00 154,105.00
L.02 0.363 OH Tukang Pipa 95,000.00 105,000.00 34,485.00 38,115.00
L.08 0.143 OH Operator Alat Berat 160,000.00 175,000.00 22,880.00 25,025.00
L.04 0.181 OH Mandor 100,000.00 110,000.00 18,100.00 19,910.00
B Bahan 170,000.00 175,000.00
1 m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 170,000.00 175,000.00

C PERALATAN 9,815.00 10,038.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 391,255.00 422,193.00
E Overhead & Profit (contoh 10%) 10% 39,125.50 42,219.30
F Harga Satuan Pekerjaan (D+E) 430,380.50 464,412.30
57 A.8.4.1.57 1 m' Pemasangan Pipa DCI Ø 500 mm 489,786.00 533,527.50
A Tenaga 243,760.00 273,265.00
L.01 2.047 OH Pekerja 75,000.00 85,000.00 153,525.00 173,995.00
L.02 0.409 OH Tukang Pipa 95,000.00 105,000.00 38,855.00 42,945.00
L.08 0.193 OH Operator Alat Berat 160,000.00 175,000.00 30,880.00 33,775.00
L.04 0.205 OH Mandor 100,000.00 110,000.00 20,500.00 22,550.00
B Bahan 190,000.00 200,000.00
1 m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 190,000.00 200,000.00

C PERALATAN 11,500.00 11,760.00


0.034 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 11,050.00 11,220.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 445,260.00 485,025.00
E Overhead & Profit (contoh 10%) 10% 44,526.00 48,502.50
F Harga Satuan Pekerjaan (D+E) 489,786.00 533,527.50

58 A.8.4.1.58 1 m' Pemasangan Pipa DCI Ø 600 mm 550,676.50 612,253.40


A Tenaga 255,995.00 286,530.00
L.01 2.011 OH Pekerja 75,000.00 85,000.00 150,825.00 170,935.00
L.02 0.402 OH Tukang Pipa 95,000.00 105,000.00 38,190.00 42,210.00
L.08 0.293 OH Operator Alat Berat 160,000.00 175,000.00 46,880.00 51,275.00
L.04 0.201 OH Mandor 100,000.00 110,000.00 20,100.00 22,110.00
B Bahan 225,000.00 250,000.00
1 m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 225,000.00 250,000.00

C PERALATAN 19,620.00 20,064.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.077 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 770.00 924.00
D Jumlah A + B + C 500,615.00 556,594.00
E Overhead & Profit (contoh 10%) 10% 50,061.50 55,659.40
F Harga Satuan Pekerjaan (D+E) 550,676.50 612,253.40

59 A.8.4.1.59 1 m' Pemasangan Pipa DCI Ø 800 mm 835,774.50 916,553.00


A Tenaga 480,245.00 537,810.00
L.01 3.859 OH Pekerja 75,000.00 85,000.00 289,425.00 328,015.00
L.02 0.772 OH Tukang Pipa 95,000.00 105,000.00 73,340.00 81,060.00
L.08 0.493 OH Operator Alat Berat 160,000.00 175,000.00 78,880.00 86,275.00
L.04 0.386 OH Mandor 100,000.00 110,000.00 38,600.00 42,460.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 29,550.00 30,420.00


0.084 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 27,300.00 27,720.00
0.225 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,250.00 2,700.00
D Jumlah A + B + C 759,795.00 833,230.00
E Overhead & Profit (contoh 10%) 10% 75,979.50 83,323.00
F Harga Satuan Pekerjaan (D+E) 835,774.50 916,553.00

60 A.8.4.1.60 1 m' Pemasangan Pipa DCI Ø 900 mm 986,716.50 1,085,481.10


A Tenaga 614,310.00 688,135.00
L.01 4.995 OH Pekerja 75,000.00 85,000.00 374,625.00 424,575.00
L.02 0.999 OH Tukang Pipa 95,000.00 105,000.00 94,905.00 104,895.00
L.08 0.593 OH Operator Alat Berat 160,000.00 175,000.00 94,880.00 103,775.00
L.04 0.499 OH Mandor 100,000.00 110,000.00 49,900.00 54,890.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 32,705.00 33,666.00


0.093 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 30,225.00 30,690.00
0.248 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,480.00 2,976.00
D Jumlah A + B + C 897,015.00 986,801.00
E Overhead & Profit (contoh 10%) 10% 89,701.50 98,680.10
F Harga Satuan Pekerjaan (D+E) 986,716.50 1,085,481.10
61 A.8.4.1.61 1 m' Pemasangan Pipa DCI Ø 1.000 mm 1,180,360.50 1,291,626.60
A Tenaga 753,675.00 843,670.00
L.01 5.931 OH Pekerja 75,000.00 85,000.00 444,825.00 504,135.00
L.02 1.186 OH Tukang Pipa 95,000.00 105,000.00 112,670.00 124,530.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.693 OH Mandor 100,000.00 110,000.00 69,300.00 76,230.00
B Bahan 280,000.00 290,000.00
1 m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 280,000.00 290,000.00

C PERALATAN 39,380.00 40,536.00


0.112 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 36,400.00 36,960.00
0.298 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,980.00 3,576.00
D Jumlah A + B + C 1,073,055.00 1,174,206.00
E Overhead & Profit (contoh 10%) 10% 107,305.50 117,420.60
F Harga Satuan Pekerjaan (D+E) 1,180,360.50 1,291,626.60

62 A.8.4.1.62 1 m' Pemasangan Pipa DCI Ø 1.100 mm 1,322,249.50 1,458,212.80


A Tenaga 849,605.00 951,840.00
L.01 6.949 OH Pekerja 75,000.00 85,000.00 521,175.00 590,665.00
L.02 1.390 OH Tukang Pipa 95,000.00 105,000.00 132,050.00 145,950.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.695 OH Mandor 100,000.00 110,000.00 69,500.00 76,450.00
B Bahan 300,000.00 320,000.00
1 m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 52,440.00 53,808.00


0.152 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 49,400.00 50,160.00
0.304 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,040.00 3,648.00
D Jumlah A + B + C 1,202,045.00 1,325,648.00
E Overhead & Profit (contoh 10%) 10% 120,204.50 132,564.80
F Harga Satuan Pekerjaan (D+E) 1,322,249.50 1,458,212.80

63 A.8.4.1.63 1 m' Pemasangan Pipa DCI Ø 1.200 mm 1,499,107.50 1,652,827.00


A Tenaga 980,725.00 1,098,850.00
L.01 8.056 OH Pekerja 75,000.00 85,000.00 604,200.00 684,760.00
L.02 1.611 OH Tukang Pipa 95,000.00 105,000.00 153,045.00 169,155.00
L.08 0.893 OH Operator Alat Berat 160,000.00 175,000.00 142,880.00 156,275.00
L.04 0.806 OH Mandor 100,000.00 110,000.00 80,600.00 88,660.00
B Bahan 320,000.00 340,000.00
1 m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 320,000.00 340,000.00

C PERALATAN 62,100.00 63,720.00


0.180 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 58,500.00 59,400.00
0.360 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,600.00 4,320.00
D Jumlah A + B + C 1,362,825.00 1,502,570.00
E Overhead & Profit (contoh 10%) 10% 136,282.50 150,257.00
F Harga Satuan Pekerjaan (D+E) 1,499,107.50 1,652,827.00

64 A.8.4.1.64 1 m' Pemasangan Baja PVC Ø 63 mm 70,361.50 78,609.30


A Tenaga 51,925.00 58,415.00
L.01 0.499 OH Pekerja 75,000.00 85,000.00 37,425.00 42,415.00
L.02 0.100 OH Tukang Pipa 95,000.00 105,000.00 9,500.00 10,500.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan 12,000.00 13,000.00


1 m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 63,965.00 71,463.00


E Overhead & Profit (contoh 10%) 10% 6,396.50 7,146.30
F Harga Satuan Pekerjaan (D+E) 70,361.50 78,609.30
65 A.8.4.1.65 1 m' Pemasangan Pipa Baja Ø 100 mm 80,063.50 91,105.30
A Tenaga 60,245.00 67,775.00
L.01 0.579 OH Pekerja 75,000.00 85,000.00 43,425.00 49,215.00
L.02 0.116 OH Tukang Pipa 95,000.00 105,000.00 11,020.00 12,180.00
L.04 0.058 OH Mandor 100,000.00 110,000.00 5,800.00 6,380.00

B Bahan 12,500.00 15,000.00


1 m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 12,500.00 15,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 72,785.00 82,823.00


E Overhead & Profit (contoh 10%) 10% 7,278.50 8,282.30
F Harga Satuan Pekerjaan (D+E) 80,063.50 91,105.30

66 A.8.4.1.66 1 m' Pemasangan Pipa Baja Ø 125 mm 90,739.00 102,220.80


A Tenaga 67,450.00 75,880.00
L.01 0.648 OH Pekerja 75,000.00 85,000.00 48,600.00 55,080.00
L.02 0.130 OH Tukang Pipa 95,000.00 105,000.00 12,350.00 13,650.00
L.04 0.065 OH Mandor 100,000.00 110,000.00 6,500.00 7,150.00

B Bahan 15,000.00 17,000.00


1 m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 15,000.00 17,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 82,490.00 92,928.00


E Overhead & Profit (contoh 10%) 10% 8,249.00 9,292.80
F Harga Satuan Pekerjaan (D+E) 90,739.00 102,220.80

67 A.8.4.1.67 1 m' Pemasangan Pipa Baja Ø 150 mm 103,103.00 118,742.80


A Tenaga 73,690.00 82,900.00
L.01 0.708 OH Pekerja 75,000.00 85,000.00 53,100.00 60,180.00
L.02 0.142 OH Tukang Pipa 95,000.00 105,000.00 13,490.00 14,910.00
L.04 0.071 OH Mandor 100,000.00 110,000.00 7,100.00 7,810.00

B Bahan 20,000.00 25,000.00


1 m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 20,000.00 25,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 93,730.00 107,948.00


E Overhead & Profit (contoh 10%) 10% 9,373.00 10,794.80
F Harga Satuan Pekerjaan (D+E) 103,103.00 118,742.80

68 A.8.4.1.68 1 m' Pemasangan Pipa Baja Ø 200 mm 160,380.00 181,805.80


A Tenaga 115,760.00 130,230.00
L.01 1.113 OH Pekerja 75,000.00 85,000.00 83,475.00 94,605.00
L.02 0.223 OH Tukang Pipa 95,000.00 105,000.00 21,185.00 23,415.00
L.04 0.111 OH Mandor 100,000.00 110,000.00 11,100.00 12,210.00

B Bahan 30,000.00 35,000.00


1 m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 30,000.00 35,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 145,800.00 165,278.00


E Overhead & Profit (contoh 10%) 10% 14,580.00 16,527.80
F Harga Satuan Pekerjaan (D+E) 160,380.00 181,805.80
69 A.8.4.1.69 1 m' Pemasangan Pipa Baja Ø 250 mm 206,679.00 236,640.80
A Tenaga 137,850.00 155,080.00
L.01 1.325 OH Pekerja 75,000.00 85,000.00 99,375.00 112,625.00
L.02 0.265 OH Tukang Pipa 95,000.00 105,000.00 25,175.00 27,825.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 50,000.00 60,000.00


1 m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 50,000.00 60,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 187,890.00 215,128.00


E Overhead & Profit (contoh 10%) 10% 18,789.00 21,512.80
F Harga Satuan Pekerjaan (D+E) 206,679.00 236,640.80

70 A.8.4.1.70 1 m' Pemasangan Pipa Baja Ø 300 mm 238,865.00 264,602.80


A Tenaga 147,110.00 165,500.00
L.01 1.415 OH Pekerja 75,000.00 85,000.00 106,125.00 120,275.00
L.02 0.283 OH Tukang Pipa 95,000.00 105,000.00 26,885.00 29,715.00
L.04 0.141 OH Mandor 100,000.00 110,000.00 14,100.00 15,510.00

B Bahan 70,000.00 75,000.00


1 m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 70,000.00 75,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 217,150.00 240,548.00


E Overhead & Profit (contoh 10%) 10% 21,715.00 24,054.80
F Harga Satuan Pekerjaan (D+E) 238,865.00 264,602.80

71 A.8.4.1.71 1 m' Pemasangan Pipa Baja Ø 400 mm 358,776.00 396,410.30


A Tenaga 231,995.00 260,995.00
L.01 2.231 OH Pekerja 75,000.00 85,000.00 167,325.00 189,635.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 85,000.00 90,000.00


1 m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 85,000.00 90,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 326,160.00 360,373.00
E Overhead & Profit (contoh 10%) 10% 32,616.00 36,037.30
F Harga Satuan Pekerjaan (D+E) 358,776.00 396,410.30

72 A.8.4.1.72 1 m' Pemasangan Pipa Baja Ø 450 mm 374,896.50 418,020.90


A Tenaga 231,995.00 260,995.00
L.01 2.231 OH Pekerja 75,000.00 85,000.00 167,325.00 189,635.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 100,000.00 110,000.00


1 m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 8,820.00 9,024.00


0.026 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,450.00 8,580.00
0.037 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 370.00 444.00
D Jumlah A + B + C 340,815.00 380,019.00
E Overhead & Profit (contoh 10%) 10% 34,081.50 38,001.90
F Harga Satuan Pekerjaan (D+E) 374,896.50 418,020.90
73 A.8.4.1.73 1 m' Pemasangan Pipa Baja Ø 500 mm 426,519.50 489,049.00
A Tenaga 252,870.00 284,480.00
L.01 2.432 OH Pekerja 75,000.00 85,000.00 182,400.00 206,720.00
L.02 0.486 OH Tukang Pipa 95,000.00 105,000.00 46,170.00 51,030.00
L.04 0.243 OH Mandor 100,000.00 110,000.00 24,300.00 26,730.00

B Bahan 125,000.00 150,000.00


1 m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 125,000.00 150,000.00

C PERALATAN 9,875.00 10,110.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 387,745.00 444,590.00
E Overhead & Profit (contoh 10%) 10% 38,774.50 44,459.00
F Harga Satuan Pekerjaan (D+E) 426,519.50 489,049.00

74 A.8.4.1.74 1 m' Pemasangan Pipa Baja Ø 600 mm 460,740.50 514,555.80


A Tenaga 229,690.00 258,400.00
L.01 2.208 OH Pekerja 75,000.00 85,000.00 165,600.00 187,680.00
L.02 0.442 OH Tukang Pipa 95,000.00 105,000.00 41,990.00 46,410.00
L.04 0.221 OH Mandor 100,000.00 110,000.00 22,100.00 24,310.00

B Bahan 180,000.00 200,000.00


1 m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 180,000.00 200,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 418,855.00 467,778.00
E Overhead & Profit (contoh 10%) 10% 41,885.50 46,777.80
F Harga Satuan Pekerjaan (D+E) 460,740.50 514,555.80

75 A.8.4.1.75 1 m' Pemasangan Pipa Baja Ø 800 mm 738,331.00 822,025.60


A Tenaga 405,280.00 455,940.00
L.01 3.897 OH Pekerja 75,000.00 85,000.00 292,275.00 331,245.00
L.02 0.779 OH Tukang Pipa 95,000.00 105,000.00 74,005.00 81,795.00
L.04 0.390 OH Mandor 100,000.00 110,000.00 39,000.00 42,900.00

B Bahan 250,000.00 275,000.00


1 m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 250,000.00 275,000.00

C PERALATAN 15,930.00 16,356.00


0.046 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 14,950.00 15,180.00
0.098 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 980.00 1,176.00
D Jumlah A + B + C 671,210.00 747,296.00
E Overhead & Profit (contoh 10%) 10% 67,121.00 74,729.60
F Harga Satuan Pekerjaan (D+E) 738,331.00 822,025.60

76 A.8.4.1.76 1 m' Pemasangan Pipa Baja Ø 900 mm 846,147.50 930,869.50


A Tenaga 451,175.00 507,705.00
L.01 4.403 OH Pekerja 75,000.00 85,000.00 330,225.00 374,255.00
L.02 0.810 OH Tukang Pipa 95,000.00 105,000.00 76,950.00 85,050.00
L.04 0.440 OH Mandor 100,000.00 110,000.00 44,000.00 48,400.00

B Bahan 300,000.00 320,000.00


1 m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 18,050.00 18,540.00


0.052 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 16,900.00 17,160.00
0.115 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,150.00 1,380.00
D Jumlah A + B + C 769,225.00 846,245.00
E Overhead & Profit (contoh 10%) 10% 76,922.50 84,624.50
F Harga Satuan Pekerjaan (D+E) 846,147.50 930,869.50
77 A.8.4.1.77 1 m' Pemasangan Pipa Baja Ø 1.000 mm 967,131.00 1,065,235.60
A Tenaga 509,030.00 572,660.00
L.01 4.895 OH Pekerja 75,000.00 85,000.00 367,125.00 416,075.00
L.02 0.979 OH Tukang Pipa 95,000.00 105,000.00 93,005.00 102,795.00
L.04 0.489 OH Mandor 100,000.00 110,000.00 48,900.00 53,790.00

B Bahan 350,000.00 375,000.00


1 m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 350,000.00 375,000.00

C PERALATAN 20,180.00 20,736.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.133 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,330.00 1,596.00
D Jumlah A + B + C 879,210.00 968,396.00
E Overhead & Profit (contoh 10%) 10% 87,921.00 96,839.60
F Harga Satuan Pekerjaan (D+E) 967,131.00 1,065,235.60

78 A.8.4.1.78 1 m' Pemasangan Pipa Baja Ø 1.100 mm 1,080,794.00 1,186,009.00


A Tenaga 560,240.00 630,270.00
L.01 5.387 OH Pekerja 75,000.00 85,000.00 404,025.00 457,895.00
L.02 1.077 OH Tukang Pipa 95,000.00 105,000.00 102,315.00 113,085.00
L.04 0.539 OH Mandor 100,000.00 110,000.00 53,900.00 59,290.00

B Bahan 400,000.00 425,000.00


1 m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 400,000.00 425,000.00

C PERALATAN 22,300.00 22,920.00


0.064 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 20,800.00 21,120.00
0.15 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,500.00 1,800.00
D Jumlah A + B + C 982,540.00 1,078,190.00
E Overhead & Profit (contoh 10%) 10% 98,254.00 107,819.00
F Harga Satuan Pekerjaan (D+E) 1,080,794.00 1,186,009.00

79 A.8.4.1.79 1 m' Pemasangan Pipa Baja Ø 1.200 mm 1,195,936.50 1,308,459.90


A Tenaga 612,795.00 689,405.00
L.01 5.897 OH Pekerja 75,000.00 85,000.00 442,275.00 501,245.00
L.02 1.176 OH Tukang Pipa 95,000.00 105,000.00 111,720.00 123,480.00
L.04 0.588 OH Mandor 100,000.00 110,000.00 58,800.00 64,680.00

B Bahan 450,000.00 475,000.00


1 m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 450,000.00 475,000.00

C PERALATAN 24,420.00 25,104.00


0.070 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 22,750.00 23,100.00
0.167 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,670.00 2,004.00
D Jumlah A + B + C 1,087,215.00 1,189,509.00
E Overhead & Profit (contoh 10%) 10% 108,721.50 118,950.90
F Harga Satuan Pekerjaan (D+E) 1,195,936.50 1,308,459.90
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA
1 A.8.4.2.1 1 bh Pemotongan Pipa PVC Ø 63 mm 702.90 792.00
A Tenaga 615.00 690.00
L.01 0.005 OH Pekerja 75,000.00 85,000.00 375.00 425.00
L.02 0.002 OH Tukang Pipa 95,000.00 105,000.00 190.00 210.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00

B Bahan - -
- m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 639.00 720.00


E Overhead & Profit (contoh 10%) 10% 63.90 72.00
F Harga Satuan Pekerjaan (D+E) 702.90 792.00

2 A.8.4.2.2 1 bh Pemotongan Pipa PVC Ø 90 mm 2,022.90 2,271.50


A Tenaga 1,815.00 2,035.00
L.01 0.014 OH Pekerja 75,000.00 85,000.00 1,050.00 1,190.00
L.02 0.007 OH Tukang Pipa 95,000.00 105,000.00 665.00 735.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00

B Bahan - -
- m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 1,839.00 2,065.00


E Overhead & Profit (contoh 10%) 10% 183.90 206.50
F Harga Satuan Pekerjaan (D+E) 2,022.90 2,271.50

3 A.8.4.2.3 1 bh Pemotongan Pipa PVC Ø 110 mm 3,210.90 3,602.50


A Tenaga 2,895.00 3,245.00
L.01 0.022 OH Pekerja 75,000.00 85,000.00 1,650.00 1,870.00
L.02 0.011 OH Tukang Pipa 95,000.00 105,000.00 1,045.00 1,155.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
B Bahan - -
- m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 2,919.00 3,275.00
E Overhead & Profit (contoh 10%) 10% 291.90 327.50
F Harga Satuan Pekerjaan (D+E) 3,210.90 3,602.50

4 A.8.4.2.4 1 bh Pemotongan Pipa PVC Ø 150 mm 4,481.40 5,027.00


A Tenaga 4,050.00 4,540.00
L.01 0.031 OH Pekerja 75,000.00 85,000.00 2,325.00 2,635.00
L.02 0.015 OH Tukang Pipa 95,000.00 105,000.00 1,425.00 1,575.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00
B Bahan - -
- m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 - -
C PERALATAN 24.00 30.00
0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 4,074.00 4,570.00
E Overhead & Profit (contoh 10%) 10% 407.40 457.00
F Harga Satuan Pekerjaan (D+E) 4,481.40 5,027.00
5 A.8.4.2.5 1 bh Pemotongan Pipa PVC Ø 200 mm 11,892.10 13,348.50
A Tenaga 10,675.00 11,965.00
L.01 0.081 OH Pekerja 75,000.00 85,000.00 6,075.00 6,885.00
L.02 0.040 OH Tukang Pipa 95,000.00 105,000.00 3,800.00 4,200.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
- m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 - -

C PERALATAN 136.00 170.00


0.017 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 136.00 170.00

D Jumlah A + B + C 10,811.00 12,135.00


E Overhead & Profit (contoh 10%) 10% 1,081.10 1,213.50
F Harga Satuan Pekerjaan (D+E) 11,892.10 13,348.50

6 A.8.4.2.6 1 bh Pemotongan Pipa PVC Ø 250 mm 18,942.00 21,263.00


A Tenaga 16,980.00 19,030.00
L.01 0.128 OH Pekerja 75,000.00 85,000.00 9,600.00 10,880.00
L.02 0.064 OH Tukang Pipa 95,000.00 105,000.00 6,080.00 6,720.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 - -

C PERALATAN 240.00 300.00


0.03 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 240.00 300.00

D Jumlah A + B + C 17,220.00 19,330.00


E Overhead & Profit (contoh 10%) 10% 1,722.00 1,933.00
F Harga Satuan Pekerjaan (D+E) 18,942.00 21,263.00

7 A.8.4.2.7 1 bh Pemotongan Pipa PVC Ø 300 mm 22,809.60 25,608.00


A Tenaga 20,440.00 22,910.00
L.01 0.155 OH Pekerja 75,000.00 85,000.00 11,625.00 13,175.00
L.02 0.077 OH Tukang Pipa 95,000.00 105,000.00 7,315.00 8,085.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

B Bahan - -
- m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 - -

C PERALATAN 296.00 370.00


0.037 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 296.00 370.00

D Jumlah A + B + C 20,736.00 23,280.00


E Overhead & Profit (contoh 10%) 10% 2,073.60 2,328.00
F Harga Satuan Pekerjaan (D+E) 22,809.60 25,608.00

8 A.8.4.2.8 1 bh Pemotongan Pipa PVC Ø 400 mm 49,041.30 55,060.50


A Tenaga 43,895.00 49,195.00
L.01 0.331 OH Pekerja 75,000.00 85,000.00 24,825.00 28,135.00
L.02 0.166 OH Tukang Pipa 95,000.00 105,000.00 15,770.00 17,430.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan - -
- m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 - -

C PERALATAN 688.00 860.00


0.086 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 688.00 860.00

D Jumlah A + B + C 44,583.00 50,055.00


E Overhead & Profit (contoh 10%) 10% 4,458.30 5,005.50
F Harga Satuan Pekerjaan (D+E) 49,041.30 55,060.50
9 A.8.4.2.9 1 bh Pemotongan Pipa PVC Ø 450 mm 62,700.00 70,389.00
A Tenaga 55,650.00 62,370.00
L.01 0.420 OH Pekerja 75,000.00 85,000.00 31,500.00 35,700.00
L.02 0.210 OH Tukang Pipa 95,000.00 105,000.00 19,950.00 22,050.00
L.04 0.042 OH Mandor 100,000.00 110,000.00 4,200.00 4,620.00

B Bahan - -
- m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 - -

C PERALATAN 1,350.00 1,620.00


0.054 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,350.00 1,620.00

D Jumlah A + B + C 57,000.00 63,990.00


E Overhead & Profit (contoh 10%) 10% 5,700.00 6,399.00
F Harga Satuan Pekerjaan (D+E) 62,700.00 70,389.00

10 A.8.4.2.10 1 bh Pemotongan Pipa PVC Ø 500 mm 77,418.00 86,916.50


A Tenaga 68,655.00 76,945.00
L.01 0.518 OH Pekerja 75,000.00 85,000.00 38,850.00 44,030.00
L.02 0.259 OH Tukang Pipa 95,000.00 105,000.00 24,605.00 27,195.00
L.04 0.052 OH Mandor 100,000.00 110,000.00 5,200.00 5,720.00

B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -

C PERALATAN 1,725.00 2,070.00


0.069 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,725.00 2,070.00

D Jumlah A + B + C 70,380.00 79,015.00


E Overhead & Profit (contoh 10%) 10% 7,038.00 7,901.50
F Harga Satuan Pekerjaan (D+E) 77,418.00 86,916.50

11 A.8.4.2.11 1 bh Pemotongan Pipa PVC Ø 600 mm 93,082.00 104,511.00


A Tenaga 82,470.00 92,430.00
L.01 0.623 OH Pekerja 75,000.00 85,000.00 46,725.00 52,955.00
L.02 0.311 OH Tukang Pipa 95,000.00 105,000.00 29,545.00 32,655.00
L.04 0.062 OH Mandor 100,000.00 110,000.00 6,200.00 6,820.00

B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -

C PERALATAN 2,150.00 2,580.00


0.086 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,150.00 2,580.00

D Jumlah A + B + C 84,620.00 95,010.00


E Overhead & Profit (contoh 10%) 10% 8,462.00 9,501.00
F Harga Satuan Pekerjaan (D+E) 93,082.00 104,511.00

12 A.8.4.2.12 1 bh Pemasangan Pipa PVC Ø 800 mm 163,185.00 183,238.00


A Tenaga 144,350.00 161,780.00
L.01 1.089 OH Pekerja 75,000.00 85,000.00 81,675.00 92,565.00
L.02 0.545 OH Tukang Pipa 95,000.00 105,000.00 51,775.00 57,225.00
L.04 0.109 OH Mandor 100,000.00 110,000.00 10,900.00 11,990.00

B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
C PERALATAN 4,000.00 4,800.00
0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00
D Jumlah A + B + C 148,350.00 166,580.00
E Overhead & Profit (contoh 10%) 10% 14,835.00 16,658.00
F Harga Satuan Pekerjaan (D+E) 163,185.00 183,238.00
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 170,962.00 191,972.00
A Tenaga 151,220.00 169,480.00
L.01 1.141 OH Pekerja 75,000.00 85,000.00 85,575.00 96,985.00
L.02 0.571 OH Tukang Pipa 95,000.00 105,000.00 54,245.00 59,955.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00

B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -

C PERALATAN 4,200.00 5,040.00


0.168 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,200.00 5,040.00

D Jumlah A + B + C 155,420.00 174,520.00


E Overhead & Profit (contoh 10%) 10% 15,542.00 17,452.00
F Harga Satuan Pekerjaan (D+E) 170,962.00 191,972.00

14 A.8.4.2.14 1 bh Pemotongan Pipa PVC Ø 1.000 mm 192,648.50 216,326.00


A , 170,360.00 190,930.00
L.01 1.285 OH Pekerja 75,000.00 85,000.00 96,375.00 109,225.00
L.02 0.643 OH Tukang Pipa 95,000.00 105,000.00 61,085.00 67,515.00
L.04 0.129 OH Mandor 100,000.00 110,000.00 12,900.00 14,190.00

B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -

C PERALATAN 4,775.00 5,730.00


0.191 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,775.00 5,730.00

D Jumlah A + B + C 175,135.00 196,660.00


E Overhead & Profit (contoh 10%) 10% 17,513.50 19,666.00
F Harga Satuan Pekerjaan (D+E) 192,648.50 216,326.00

15 A.8.4.2.15 1 bh Pemotongan Pipa PVC Ø 1.100 mm 214,197.50 240,526.00


A Tenaga 189,400.00 212,270.00
L.01 1.429 OH Pekerja 75,000.00 85,000.00 107,175.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -

C PERALATAN 5,325.00 6,390.00


0.213 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,325.00 6,390.00

D Jumlah A + B + C 194,725.00 218,660.00


E Overhead & Profit (contoh 10%) 10% 19,472.50 21,866.00
F Harga Satuan Pekerjaan (D+E) 214,197.50 240,526.00

16 A.8.4.2.16 1 bh Pemotongan Pipa PVC Ø 1.200 mm 235,774.00 264,759.00


A Tenaga 208,440.00 233,610.00
L.01 1.573 OH Pekerja 75,000.00 85,000.00 117,975.00 133,705.00
L.02 0.787 OH Tukang Pipa 95,000.00 105,000.00 74,765.00 82,635.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -

C PERALATAN 5,900.00 7,080.00


0.236 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,900.00 7,080.00
D Jumlah A + B + C 214,340.00 240,690.00
E Overhead & Profit (contoh 10%) 10% 21,434.00 24,069.00
F Harga Satuan Pekerjaan (D+E) 235,774.00 264,759.00
17 A.8.4.2.17 1 bh Pemotongan Pipa HDPE Ø 63 mm 4,141.50 4,572.70
A Tenaga 3,665.00 4,037.00
L.01 0.002 OH Pekerja 75,000.00 85,000.00 150.00 170.00
L.02 0.001 OH Tukang Pipa 95,000.00 105,000.00 95.00 105.00
L.04 0.0002 OH Mandor 100,000.00 110,000.00 20.00 22.00
L.08 0.0340 OH Operator 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan - -
- m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 - -

C PERALATAN 100.00 120.00


0.004 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 100.00 120.00

D Jumlah A + B + C 3,765.00 4,157.00


E Overhead & Profit (contoh 10%) 10% 376.50 415.70
F Harga Satuan Pekerjaan (D+E) 4,141.50 4,572.70

18 A.8.4.2.18 1 bh Pemotongan Pipa HDPE Ø 100 mm 8,866.00 9,784.50


A Tenaga 7,935.00 8,745.00
L.01 0.006 OH Pekerja 75,000.00 85,000.00 450.00 510.00
L.02 0.003 OH Tukang Pipa 95,000.00 105,000.00 285.00 315.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.071 OH Operator 100,000.00 110,000.00 7,100.00 7,810.00
B Bahan - -
- m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 - -

C PERALATAN 125.00 150.00


0.005 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 125.00 150.00

D Jumlah A + B + C 8,060.00 8,895.00


E Overhead & Profit (contoh 10%) 10% 806.00 889.50
F Harga Satuan Pekerjaan (D+E) 8,866.00 9,784.50

19 A.8.4.2.19 1 bh Pemotongan Pipa HDPE Ø 125 mm 12,100.00 13,354.00


A Tenaga 10,850.00 11,960.00
L.01 0.009 OH Pekerja 75,000.00 85,000.00 675.00 765.00
L.02 0.005 OH Tukang Pipa 95,000.00 105,000.00 475.00 525.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.096 OH Operator 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan - -
- m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 - -

C PERALATAN 150.00 180.00


0.006 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 150.00 180.00

D Jumlah A + B + C 11,000.00 12,140.00


E Overhead & Profit (contoh 10%) 10% 1,100.00 1,214.00
F Harga Satuan Pekerjaan (D+E) 12,100.00 13,354.00

20 A.8.4.2.20 1 bh Pemotongan Pipa HDPE Ø 150 mm 15,933.50 17,600.00


A Tenaga 14,260.00 15,730.00
L.01 0.016 OH Pekerja 75,000.00 85,000.00 1,200.00 1,360.00
L.02 0.008 OH Tukang Pipa 95,000.00 105,000.00 760.00 840.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
L.08 0.121 OH Operator 100,000.00 110,000.00 12,100.00 13,310.00
B Bahan - -
- m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 - -

C PERALATAN 225.00 270.00


0.009 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 225.00 270.00
D Jumlah A + B + C 14,485.00 16,000.00
E Overhead & Profit (contoh 10%) 10% 1,448.50 1,600.00
F Harga Satuan Pekerjaan (D+E) 15,933.50 17,600.00
21 A.8.4.2.21 1 bh Pemotongan Pipa HDPE Ø 200 mm 25,646.50 28,391.00
A Tenaga 22,890.00 25,300.00
L.01 0.044 OH Pekerja 75,000.00 85,000.00 3,300.00 3,740.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
L.08 0.171 OH Operator 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan - -
m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 - -

C PERALATAN 425.00 510.00


0.017 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 425.00 510.00

D Jumlah A + B + C 23,315.00 25,810.00


E Overhead & Profit (contoh 10%) 10% 2,331.50 2,581.00
F Harga Satuan Pekerjaan (D+E) 25,646.50 28,391.00

22 A.8.4.2.22 1 bh Pemotongan Pipa HDPE Ø 250 mm 34,688.50 38,423.00


A Tenaga 30,960.00 34,240.00
L.01 0.067 OH Pekerja 75,000.00 85,000.00 5,025.00 5,695.00
L.02 0.033 OH Tukang Pipa 95,000.00 105,000.00 3,135.00 3,465.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
L.08 0.221 OH Operator 100,000.00 110,000.00 22,100.00 24,310.00
B Bahan - -
- m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 - -

C PERALATAN 575.00 690.00


0.023 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 575.00 690.00

D Jumlah A + B + C 31,535.00 34,930.00


E Overhead & Profit (contoh 10%) 10% 3,153.50 3,493.00
F Harga Satuan Pekerjaan (D+E) 34,688.50 38,423.00

23 A.8.4.2.23 1 bh Pemotongan Pipa HDPE Ø 300 mm 43,752.50 48,482.50


A Tenaga 39,025.00 43,175.00
L.01 0.090 OH Pekerja 75,000.00 85,000.00 6,750.00 7,650.00
L.02 0.045 OH Tukang Pipa 95,000.00 105,000.00 4,275.00 4,725.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
L.08 0.271 OH Operator 100,000.00 110,000.00 27,100.00 29,810.00
B Bahan - -
- m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 - -

C PERALATAN 750.00 900.00


0.030 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 750.00 900.00

D Jumlah A + B + C 39,775.00 44,075.00


E Overhead & Profit (contoh 10%) 10% 3,977.50 4,407.50
F Harga Satuan Pekerjaan (D+E) 43,752.50 48,482.50

24 A.8.4.2.24 1 bh Pemotongan Pipa HDPE Ø 400 mm 68,101.00 75,597.50


A Tenaga 60,535.00 67,075.00
L.01 0.177 OH Pekerja 75,000.00 85,000.00 13,275.00 15,045.00
L.02 0.088 OH Tukang Pipa 95,000.00 105,000.00 8,360.00 9,240.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
L.08 0.371 OH Operator 100,000.00 110,000.00 37,100.00 40,810.00
B Bahan - -
- m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 - -
C PERALATAN 1,375.00 1,650.00
0.055 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,375.00 1,650.00

D Jumlah A + B + C 61,910.00 68,725.00


E Overhead & Profit (contoh 10%) 10% 6,191.00 6,872.50
F Harga Satuan Pekerjaan (D+E) 68,101.00 75,597.50
25 A.8.4.2.25 1 bh Pemotongan Pipa HDPE Ø 450 mm 81,136.00 90,123.00
A Tenaga 72,010.00 79,830.00
L.01 0.225 OH Pekerja 75,000.00 85,000.00 16,875.00 19,125.00
L.02 0.113 OH Tukang Pipa 95,000.00 105,000.00 10,735.00 11,865.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
L.08 0.421 OH Operator 100,000.00 110,000.00 42,100.00 46,310.00
B Bahan - -
- m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 - -

C PERALATAN 1,750.00 2,100.00


0.070 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,750.00 2,100.00

D Jumlah A + B + C 73,760.00 81,930.00


E Overhead & Profit (contoh 10%) 10% 7,376.00 8,193.00
F Harga Satuan Pekerjaan (D+E) 81,136.00 90,123.00

26 A.8.4.2.26 1 bh Pemotongan Pipa HDPE Ø 500 mm 90,480.50 100,463.00


A Tenaga 80,130.00 88,780.00
L.01 0.227 OH Pekerja 75,000.00 85,000.00 17,025.00 19,295.00
L.02 0.139 OH Tukang Pipa 95,000.00 105,000.00 13,205.00 14,595.00
L.04 0.028 OH Mandor 100,000.00 110,000.00 2,800.00 3,080.00
L.08 0.471 OH Operator 100,000.00 110,000.00 47,100.00 51,810.00
B Bahan - -
- m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 - -

C PERALATAN 2,125.00 2,550.00


0.085 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,125.00 2,550.00
-
D Jumlah A + B + C 82,255.00 91,330.00
E Overhead & Profit (contoh 10%) 10% 8,225.50 9,133.00
F Harga Satuan Pekerjaan (D+E) 90,480.50 100,463.00

27 A.8.4.2.27 1 bh Pemotongan Pipa HDPE Ø 600 mm 114,141.50 126,841.00


A Tenaga 101,240.00 112,280.00
L.01 0.333 OH Pekerja 75,000.00 85,000.00 24,975.00 28,305.00
L.02 0.167 OH Tukang Pipa 95,000.00 105,000.00 15,865.00 17,535.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
L.08 0.571 OH Operator 100,000.00 110,000.00 57,100.00 62,810.00
B Bahan - -
- m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 - -

C PERALATAN 2,525.00 3,030.00


0.101 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,525.00 3,030.00

D Jumlah A + B + C 103,765.00 115,310.00


E Overhead & Profit (contoh 10%) 10% 10,376.50 11,531.00
F Harga Satuan Pekerjaan (D+E) 114,141.50 126,841.00

28 A.8.4.2.28 1 bh Pemotongan Pipa HDPE Ø 800 mm 177,369.50 197,417.00


A Tenaga 156,770.00 174,100.00
L.01 0.601 OH Pekerja 75,000.00 85,000.00 45,075.00 51,085.00
L.02 0.301 OH Tukang Pipa 95,000.00 105,000.00 28,595.00 31,605.00
L.04 0.060 OH Mandor 100,000.00 110,000.00 6,000.00 6,600.00
L.08 0.771 OH Operator 100,000.00 110,000.00 77,100.00 84,810.00
B Bahan - -
- m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 - -

C PERALATAN 4,475.00 5,370.00


0.179 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,475.00 5,370.00
D Jumlah A + B + C 161,245.00 179,470.00
E Overhead & Profit (contoh 10%) 10% 16,124.50 17,947.00
F Harga Satuan Pekerjaan (D+E) 177,369.50 197,417.00
29 A.8.4.2.29 1 bh Pemotongan Pipa HDPE Ø 900 mm 236,219.50 263,345.50
A Tenaga 207,995.00 231,305.00
L.01 0.913 OH Pekerja 75,000.00 85,000.00 68,475.00 77,605.00
L.02 0.456 OH Tukang Pipa 95,000.00 105,000.00 43,320.00 47,880.00
L.04 0.091 OH Mandor 100,000.00 110,000.00 9,100.00 10,010.00
L.08 0.871 OH Operator 100,000.00 110,000.00 87,100.00 95,810.00
B Bahan - -
- m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 - -

C PERALATAN 6,750.00 8,100.00


0.270 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 6,750.00 8,100.00

D Jumlah A + B + C 214,745.00 239,405.00


E Overhead & Profit (contoh 10%) 10% 21,474.50 23,940.50
F Harga Satuan Pekerjaan (D+E) 236,219.50 263,345.50

30 A.8.4.2.30 1 bh Pemotongan Pipa HDPE Ø 1.000 mm 279,801.50 312,097.50


A Tenaga 246,065.00 273,765.00
L.01 1.125 OH Pekerja 75,000.00 85,000.00 84,375.00 95,625.00
L.02 0.562 OH Tukang Pipa 95,000.00 105,000.00 53,390.00 59,010.00
L.04 0.112 OH Mandor 100,000.00 110,000.00 11,200.00 12,320.00
L.08 0.971 OH Operator 100,000.00 110,000.00 97,100.00 106,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 - -

C PERALATAN 8,300.00 9,960.00


0.332 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 8,300.00 9,960.00

D Jumlah A + B + C 254,365.00 283,725.00


E Overhead & Profit (contoh 10%) 10% 25,436.50 28,372.50
F Harga Satuan Pekerjaan (D+E) 279,801.50 312,097.50

31 A.8.4.2.31 1 bh Pemotongan Pipa HDPE Ø 1.100 mm 308,308.00 343,887.50


A Tenaga 271,155.00 301,675.00
L.01 1.238 OH Pekerja 75,000.00 85,000.00 92,850.00 105,230.00
L.02 0.619 OH Tukang Pipa 95,000.00 105,000.00 58,805.00 64,995.00
L.04 0.124 OH Mandor 100,000.00 110,000.00 12,400.00 13,640.00
L.08 1.071 OH Operator 100,000.00 110,000.00 107,100.00 117,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 - -

C PERALATAN 9,125.00 10,950.00


0.365 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 9,125.00 10,950.00

D Jumlah A + B + C 280,280.00 312,625.00


E Overhead & Profit (contoh 10%) 10% 28,028.00 31,262.50
F Harga Satuan Pekerjaan (D+E) 308,308.00 343,887.50

32 A.8.4.2.32 1 bh Pemotongan Pipa HDPE Ø 1.200 mm 377,855.50 421,850.00


A Tenaga 331,580.00 369,190.00
L.01 1.619 OH Pekerja 75,000.00 85,000.00 121,425.00 137,615.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00
L.08 1.171 OH Operator 100,000.00 110,000.00 117,100.00 128,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 - -

C PERALATAN 11,925.00 14,310.00


0.477 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 11,925.00 14,310.00
D Jumlah A + B + C 343,505.00 383,500.00
E Overhead & Profit (contoh 10%) 10% 34,350.50 38,350.00
F Harga Satuan Pekerjaan (D+E) 377,855.50 421,850.00
33 A.8.4.2.33 1 bh Pemotongan Pipa GIP Ø 63 mm 2,832.50 3,173.50
A Tenaga 2,575.00 2,885.00
L.01 0.019 OH Pekerja 75,000.00 85,000.00 1,425.00 1,615.00
L.02 0.010 OH Tukang Pipa 95,000.00 105,000.00 950.00 1,050.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00

B Bahan - -
- m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 - -

C PERALATAN - -

hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 2,575.00 2,885.00


E Overhead & Profit (contoh 10%) 10% 257.50 288.50
F Harga Satuan Pekerjaan (D+E) 2,832.50 3,173.50

34 A.8.4.2.34 1 bh Pemotongan Pipa GIP Ø 100 mm 8,475.50 9,498.50


A Tenaga 7,705.00 8,635.00
L.01 0.058 OH Pekerja 75,000.00 85,000.00 4,350.00 4,930.00
L.02 0.029 OH Tukang Pipa 95,000.00 105,000.00 2,755.00 3,045.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00

B Bahan - -
- m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 7,705.00 8,635.00


E Overhead & Profit (contoh 10%) 10% 770.50 863.50
F Harga Satuan Pekerjaan (D+E) 8,475.50 9,498.50

35 A.8.4.2.35 1 bh Pemotongan Pipa GIP Ø 125 mm 13,387.00 15,004.00


A Tenaga 12,170.00 13,640.00
L.01 0.092 OH Pekerja 75,000.00 85,000.00 6,900.00 7,820.00
L.02 0.046 OH Tukang Pipa 95,000.00 105,000.00 4,370.00 4,830.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00

B Bahan - -
- m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 12,170.00 13,640.00


E Overhead & Profit (contoh 10%) 10% 1,217.00 1,364.00
F Harga Satuan Pekerjaan (D+E) 13,387.00 15,004.00

36 A.8.4.2.36 1 bh Pemotongan Pipa GIP Ø 150 mm 19,134.50 21,444.50


A Tenaga 17,395.00 19,495.00
L.01 0.131 OH Pekerja 75,000.00 85,000.00 9,825.00 11,135.00
L.02 0.066 OH Tukang Pipa 95,000.00 105,000.00 6,270.00 6,930.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 17,395.00 19,495.00
E Overhead & Profit (contoh 10%) 10% 1,739.50 1,949.50
F Harga Satuan Pekerjaan (D+E) 19,134.50 21,444.50
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 49,555.00 55,539.00
A Tenaga 45,050.00 50,490.00
L.01 0.340 OH Pekerja 75,000.00 85,000.00 25,500.00 28,900.00
L.02 0.170 OH Tukang Pipa 95,000.00 105,000.00 16,150.00 17,850.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00

B Bahan - -
- m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 45,050.00 50,490.00


E Overhead & Profit (contoh 10%) 10% 4,505.00 5,049.00
F Harga Satuan Pekerjaan (D+E) 49,555.00 55,539.00

38 A.8.4.2.38 1 bh Pemotongan Pipa GIP Ø 250 mm 69,124.00 77,473.00


A Tenaga 62,840.00 70,430.00
L.01 0.475 OH Pekerja 75,000.00 85,000.00 35,625.00 40,375.00
L.02 0.237 OH Tukang Pipa 95,000.00 105,000.00 22,515.00 24,885.00
L.04 0.047 OH Mandor 100,000.00 110,000.00 4,700.00 5,170.00

B Bahan - -
- m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 62,840.00 70,430.00


E Overhead & Profit (contoh 10%) 10% 6,284.00 7,043.00
F Harga Satuan Pekerjaan (D+E) 69,124.00 77,473.00

39 A.8.4.2.39 1 bh Pemotongan Pipa GIP Ø 300 mm 73,414.00 82,280.00


A Tenaga 66,740.00 74,800.00
L.01 0.504 OH Pekerja 75,000.00 85,000.00 37,800.00 42,840.00
L.02 0.252 OH Tukang Pipa 95,000.00 105,000.00 23,940.00 26,460.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan - -
- m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 66,740.00 74,800.00


E Overhead & Profit (contoh 10%) 10% 6,674.00 7,480.00
F Harga Satuan Pekerjaan (D+E) 73,414.00 82,280.00

40 A.8.4.2.40 1 bh Pemotongan Pipa GIP Ø 400 mm 107,585.50 120,576.50


A Tenaga 97,805.00 109,615.00
L.01 0.738 OH Pekerja 75,000.00 85,000.00 55,350.00 62,730.00
L.02 0.369 OH Tukang Pipa 95,000.00 105,000.00 35,055.00 38,745.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
- m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 97,805.00 109,615.00


E Overhead & Profit (contoh 10%) 10% 9,780.50 10,961.50
F Harga Satuan Pekerjaan (D+E) 107,585.50 120,576.50
41 A.8.4.2.41 1 bh Pemotongan Pipa GIP Ø 450 mm 123,618.00 138,545.00
A Tenaga 112,380.00 125,950.00
L.01 0.848 OH Pekerja 75,000.00 85,000.00 63,600.00 72,080.00
L.02 0.424 OH Tukang Pipa 95,000.00 105,000.00 40,280.00 44,520.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00

B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 112,380.00 125,950.00


E Overhead & Profit (contoh 10%) 10% 11,238.00 12,595.00
F Harga Satuan Pekerjaan (D+E) 123,618.00 138,545.00

42 A.8.4.2.42 1 bh Pemotongan Pipa GIP Ø 500 mm 125,884.00 141,086.00


A Tenaga 114,440.00 128,260.00
L.01 0.864 OH Pekerja 75,000.00 85,000.00 64,800.00 73,440.00
L.02 0.432 OH Tukang Pipa 95,000.00 105,000.00 41,040.00 45,360.00
L.04 0.086 OH Mandor 100,000.00 110,000.00 8,600.00 9,460.00

B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 114,440.00 128,260.00


E Overhead & Profit (contoh 10%) 10% 11,444.00 12,826.00
F Harga Satuan Pekerjaan (D+E) 125,884.00 141,086.00

43 A.8.4.2.43 1 bh Pemotongan Pipa GIP Ø 600 mm 137,192.00 153,758.00


A Tenaga 124,720.00 139,780.00
L.01 0.941 OH Pekerja 75,000.00 85,000.00 70,575.00 79,985.00
L.02 0.471 OH Tukang Pipa 95,000.00 105,000.00 44,745.00 49,455.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00

B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 124,720.00 139,780.00


E Overhead & Profit (contoh 10%) 10% 12,472.00 13,978.00
F Harga Satuan Pekerjaan (D+E) 137,192.00 153,758.00

44 A.8.4.2.44 1 bh Pemotongan Pipa GIP Ø 800 mm 228,371.00 255,948.00


A Tenaga 207,610.00 232,680.00
L.01 1.567 OH Pekerja 75,000.00 85,000.00 117,525.00 133,195.00
L.02 0.783 OH Tukang Pipa 95,000.00 105,000.00 74,385.00 82,215.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 207,610.00 232,680.00
E Overhead & Profit (contoh 10%) 10% 20,761.00 23,268.00
F Harga Satuan Pekerjaan (D+E) 228,371.00 255,948.00
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 257,977.50 289,129.50
A Tenaga 234,525.00 262,845.00
L.01 1.770 OH Pekerja 75,000.00 85,000.00 132,750.00 150,450.00
L.02 0.885 OH Tukang Pipa 95,000.00 105,000.00 84,075.00 92,925.00
L.04 0.177 OH Mandor 100,000.00 110,000.00 17,700.00 19,470.00

B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 234,525.00 262,845.00


E Overhead & Profit (contoh 10%) 10% 23,452.50 26,284.50
F Harga Satuan Pekerjaan (D+E) 257,977.50 289,129.50

46 A.8.4.2.46 1 bh Pemotongan Pipa GIP Ø 1.000 mm 287,666.50 322,404.50


A Tenaga 261,515.00 293,095.00
L.01 1.974 OH Pekerja 75,000.00 85,000.00 148,050.00 167,790.00
L.02 0.987 OH Tukang Pipa 95,000.00 105,000.00 93,765.00 103,635.00
L.04 0.197 OH Mandor 100,000.00 110,000.00 19,700.00 21,670.00

B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 261,515.00 293,095.00


E Overhead & Profit (contoh 10%) 10% 26,151.50 29,309.50
F Harga Satuan Pekerjaan (D+E) 287,666.50 322,404.50

47 A.8.4.2.47 1 bh Pemotongan Pipa GIP Ø 1.100 mm 317,245.50 355,558.50


A Tenaga 288,405.00 323,235.00
L.01 2.178 OH Pekerja 75,000.00 85,000.00 163,350.00 185,130.00
L.02 1.089 OH Tukang Pipa 95,000.00 105,000.00 103,455.00 114,345.00
L.04 0.216 OH Mandor 100,000.00 110,000.00 21,600.00 23,760.00

B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 288,405.00 323,235.00


E Overhead & Profit (contoh 10%) 10% 28,840.50 32,323.50
F Harga Satuan Pekerjaan (D+E) 317,245.50 355,558.50

48 A.8.4.2.48 1 bh Pemotongan Pipa GIP Ø 1.200 mm 347,154.50 389,075.50


A Tenaga 315,595.00 353,705.00
L.01 2.382 OH Pekerja 75,000.00 85,000.00 178,650.00 202,470.00
L.02 1.191 OH Tukang Pipa 95,000.00 105,000.00 113,145.00 125,055.00
L.04 0.238 OH Mandor 100,000.00 110,000.00 23,800.00 26,180.00

B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 315,595.00 353,705.00
E Overhead & Profit (contoh 10%) 10% 31,559.50 35,370.50
F Harga Satuan Pekerjaan (D+E) 347,154.50 389,075.50
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 8,123.50 9,142.10
A Tenaga 7,355.00 8,275.00
L.01 0.071 OH Pekerja 75,000.00 85,000.00 5,325.00 6,035.00
L.02 0.014 OH Tukang Pipa 95,000.00 105,000.00 1,330.00 1,470.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00

B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -

C PERALATAN 30.00 36.00


0.003 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 30.00 36.00

D Jumlah A + B + C 7,385.00 8,311.00


E Overhead & Profit (contoh 10%) 10% 738.50 831.10
F Harga Satuan Pekerjaan (D+E) 8,123.50 9,142.10

50 A.8.4.2.50 1 bh Pemotongan Pipa DCI Ø 125 mm 12,859.00 14,476.00


A Tenaga 11,590.00 13,040.00
L.01 0.112 OH Pekerja 75,000.00 85,000.00 8,400.00 9,520.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -

C PERALATAN 100.00 120.00


0.010 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 100.00 120.00

D Jumlah A + B + C 11,690.00 13,160.00


E Overhead & Profit (contoh 10%) 10% 1,169.00 1,316.00
F Harga Satuan Pekerjaan (D+E) 12,859.00 14,476.00

51 A.8.4.2.51 1 bh Pemotongan Pipa DCI Ø 150 mm 18,419.50 20,736.10


A Tenaga 16,565.00 18,635.00
L.01 0.159 OH Pekerja 75,000.00 85,000.00 11,925.00 13,515.00
L.02 0.032 OH Tukang Pipa 95,000.00 105,000.00 3,040.00 3,360.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00

B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -

C PERALATAN 180.00 216.00


0.018 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 180.00 216.00

D Jumlah A + B + C 16,745.00 18,851.00


E Overhead & Profit (contoh 10%) 10% 1,674.50 1,885.10
F Harga Satuan Pekerjaan (D+E) 18,419.50 20,736.10

52 A.8.4.2.52 1 bh Pemotongan Pipa DCI Ø 200 mm 42,487.50 47,842.30


A Tenaga 38,085.00 42,845.00
L.01 0.366 OH Pekerja 75,000.00 85,000.00 27,450.00 31,110.00
L.02 0.073 OH Tukang Pipa 95,000.00 105,000.00 6,935.00 7,665.00
L.04 0.037 OH Mandor 100,000.00 110,000.00 3,700.00 4,070.00

B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -

C PERALATAN 540.00 648.00


0.054 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 540.00 648.00

D Jumlah A + B + C 38,625.00 43,493.00


E Overhead & Profit (contoh 10%) 10% 3,862.50 4,349.30
F Harga Satuan Pekerjaan (D+E) 42,487.50 47,842.30
53 A.8.4.2.53 1 bh Pemotongan Pipa DCI Ø 250 mm 55,280.50 62,250.10
A Tenaga 49,525.00 55,715.00
L.01 0.476 OH Pekerja 75,000.00 85,000.00 35,700.00 40,460.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -

C PERALATAN 730.00 876.00


0.073 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 730.00 876.00

D Jumlah A + B + C 50,255.00 56,591.00


E Overhead & Profit (contoh 10%) 10% 5,025.50 5,659.10
F Harga Satuan Pekerjaan (D+E) 55,280.50 62,250.10

54 A.8.4.2.54 1 bh Pemotongan Pipa DCI Ø 300 mm 59,378.00 66,866.80


A Tenaga 53,190.00 59,840.00
L.01 0.512 OH Pekerja 75,000.00 85,000.00 38,400.00 43,520.00
L.02 0.102 OH Tukang Pipa 95,000.00 105,000.00 9,690.00 10,710.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -

C PERALATAN 790.00 948.00


0.079 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 790.00 948.00

D Jumlah A + B + C 53,980.00 60,788.00


E Overhead & Profit (contoh 10%) 10% 5,398.00 6,078.80
F Harga Satuan Pekerjaan (D+E) 59,378.00 66,866.80

55 A.8.4.2.55 1 bh Pemotongan Pipa DCI Ø 400 mm 109,356.50 123,157.10


A Tenaga 97,835.00 110,065.00
L.01 0.941 OH Pekerja 75,000.00 85,000.00 70,575.00 79,985.00
L.02 0.188 OH Tukang Pipa 95,000.00 105,000.00 17,860.00 19,740.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00
- -
B Bahan - -
m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 - -

C PERALATAN 1,580.00 1,896.00


0.158 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,580.00 1,896.00
- -
D Jumlah A + B + C 99,415.00 111,961.00
E Overhead & Profit (contoh 10%) 10% 9,941.50 11,196.10
F Harga Satuan Pekerjaan (D+E) 109,356.50 123,157.10

56 A.8.4.2.56 1 bh Pemotongan Pipa DCI Ø 450 mm 132,000.00 148,645.20


A Tenaga 118,240.00 133,020.00
L.01 1.137 OH Pekerja 75,000.00 85,000.00 85,275.00 96,645.00
L.02 0.227 OH Tukang Pipa 95,000.00 105,000.00 21,565.00 23,835.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00
- -
B Bahan - -
m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 - -

C PERALATAN 1,760.00 2,112.00


0.176 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,760.00 2,112.00
- - - -
D Jumlah A + B + C 120,000.00 135,132.00
E Overhead & Profit (contoh 10%) 10% 12,000.00 13,513.20
F Harga Satuan Pekerjaan (D+E) 132,000.00 148,645.20
57 A.8.4.2.57 1 bh Pemotongan Pipa DCI Ø 500 mm 152,141.00 171,318.40
A Tenaga 136,390.00 153,440.00
L.01 1.312 OH Pekerja 75,000.00 85,000.00 98,400.00 111,520.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 138,310.00 155,744.00
E Overhead & Profit (contoh 10%) 10% 13,831.00 15,574.40
F Harga Satuan Pekerjaan (D+E) 152,141.00 171,318.40

58 A.8.4.2.58 1 bh Pemotongan Pipa DCI Ø 600 mm 152,141.00 171,318.40


A Tenaga 136,390.00 153,440.00
L.01 1.312 OH Pekerja 75,000.00 85,000.00 98,400.00 111,520.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 138,310.00 155,744.00
E Overhead & Profit (contoh 10%) 10% 13,831.00 15,574.40
F Harga Satuan Pekerjaan (D+E) 152,141.00 171,318.40

59 A.8.4.2.59 1 bh Pemotongan Pipa DCI Ø 800 mm 300,685.00 338,525.00


A Tenaga 270,250.00 304,030.00
L.01 2.598 OH Pekerja 75,000.00 85,000.00 194,850.00 220,830.00
L.02 0.520 OH Tukang Pipa 95,000.00 105,000.00 49,400.00 54,600.00
L.04 0.260 OH Mandor 100,000.00 110,000.00 26,000.00 28,600.00
- -
B Bahan - -
m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 - -

C PERALATAN 3,100.00 3,720.00


0.310 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,100.00 3,720.00
- - - -
D Jumlah A + B + C 273,350.00 307,750.00
E Overhead & Profit (contoh 10%) 10% 27,335.00 30,775.00
F Harga Satuan Pekerjaan (D+E) 300,685.00 338,525.00

60 A.8.4.2.60 1 bh Pemotongan Pipa DCI Ø 900 mm 389,719.00 438,748.20


A Tenaga 350,480.00 394,290.00
L.01 3.370 OH Pekerja 75,000.00 85,000.00 252,750.00 286,450.00
L.02 0.674 OH Tukang Pipa 95,000.00 105,000.00 64,030.00 70,770.00
L.04 0.337 OH Mandor 100,000.00 110,000.00 33,700.00 37,070.00
- -
B Bahan - -
m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 - -

C PERALATAN 3,810.00 4,572.00


0.381 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,810.00 4,572.00
- - - -
D Jumlah A + B + C 354,290.00 398,862.00
E Overhead & Profit (contoh 10%) 10% 35,429.00 39,886.20
F Harga Satuan Pekerjaan (D+E) 389,719.00 438,748.20
61 A.8.4.2.61 1 bh Pemotongan Pipa DCI Ø 1.000 mm 464,821.50 523,288.70
A Tenaga 418,155.00 470,425.00
L.01 4.021 OH Pekerja 75,000.00 85,000.00 301,575.00 341,785.00
L.02 0.804 OH Tukang Pipa 95,000.00 105,000.00 76,380.00 84,420.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00
- -
B Bahan - -
m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 - -

C PERALATAN 4,410.00 5,292.00


0.441 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 4,410.00 5,292.00
- - - -
D Jumlah A + B + C 422,565.00 475,717.00
E Overhead & Profit (contoh 10%) 10% 42,256.50 47,571.70
F Harga Satuan Pekerjaan (D+E) 464,821.50 523,288.70

62 A.8.4.2.62 1 bh Pemotongan Pipa DCI Ø 1.100 mm 546,760.50 615,523.70


A Tenaga 491,995.00 553,495.00
L.01 4.731 OH Pekerja 75,000.00 85,000.00 354,825.00 402,135.00
L.02 0.946 OH Tukang Pipa 95,000.00 105,000.00 89,870.00 99,330.00
L.04 0.473 OH Mandor 100,000.00 110,000.00 47,300.00 52,030.00
- -
B Bahan - -
m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 - -

C PERALATAN 5,060.00 6,072.00


0.506 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,060.00 6,072.00
- - - -
D Jumlah A + B + C 497,055.00 559,567.00
E Overhead & Profit (contoh 10%) 10% 49,705.50 55,956.70
F Harga Satuan Pekerjaan (D+E) 546,760.50 615,523.70

63 A.8.4.2.63 1 bh Pemotongan Pipa DCI Ø 1.200 mm 635,701.00 715,640.20


A Tenaga 572,150.00 643,670.00
L.01 5.502 OH Pekerja 75,000.00 85,000.00 412,650.00 467,670.00
L.02 1.100 OH Tukang Pipa 95,000.00 105,000.00 104,500.00 115,500.00
L.04 0.550 OH Mandor 100,000.00 110,000.00 55,000.00 60,500.00
- -
B Bahan - -
m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 - -

C PERALATAN 5,760.00 6,912.00


0.576 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,760.00 6,912.00
- - - -
D Jumlah A + B + C 577,910.00 650,582.00
E Overhead & Profit (contoh 10%) 10% 57,791.00 65,058.20
F Harga Satuan Pekerjaan (D+E) 635,701.00 715,640.20

64 A.8.4.2.64 1 bh Pemotongan pipa Baja Ø 63 mm 4,488.00 5,098.50


A Tenaga 2,970.00 3,340.00
L.01 0.028 OH Pekerja 75,000.00 85,000.00 2,100.00 2,380.00
L.02 0.006 OH Tukang Pipa 95,000.00 105,000.00 570.00 630.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -

C PERALATAN 1,110.00 1,295.00


0.037 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,110.00 1,295.00

D Jumlah A + B + C 4,080.00 4,635.00


E Overhead & Profit (contoh 10%) 10% 408.00 463.50
F Harga Satuan Pekerjaan (D+E) 4,488.00 5,098.50
65 A.8.4.2.65 1 bh Pemotongan Pipa Baja Ø 100 mm 10,989.00 12,419.00
A Tenaga 8,790.00 9,890.00
L.01 0.085 OH Pekerja 75,000.00 85,000.00 6,375.00 7,225.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -

C PERALATAN 1,200.00 1,400.00


0.04 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,200.00 1,400.00

D Jumlah A + B + C 9,990.00 11,290.00


E Overhead & Profit (contoh 10%) 10% 999.00 1,129.00
F Harga Satuan Pekerjaan (D+E) 10,989.00 12,419.00

66 A.8.4.2.66 1 bh Pemotongan Pipa Baja Ø 125 mm 16,610.00 18,744.00


A Tenaga 13,840.00 15,570.00
L.01 0.133 OH Pekerja 75,000.00 85,000.00 9,975.00 11,305.00
L.02 0.027 OH Tukang Pipa 95,000.00 105,000.00 2,565.00 2,835.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -

C PERALATAN 1,260.00 1,470.00


0.042 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,260.00 1,470.00

D Jumlah A + B + C 15,100.00 17,040.00


E Overhead & Profit (contoh 10%) 10% 1,510.00 1,704.00
F Harga Satuan Pekerjaan (D+E) 16,610.00 18,744.00

67 A.8.4.2.67 1 bh Pemotongan Pipa Baja Ø 150 mm 22,511.50 25,388.00


A Tenaga 19,115.00 21,505.00
L.01 0.184 OH Pekerja 75,000.00 85,000.00 13,800.00 15,640.00
L.02 0.037 OH Tukang Pipa 95,000.00 105,000.00 3,515.00 3,885.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -

C PERALATAN 1,350.00 1,575.00


0.045 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,350.00 1,575.00

D Jumlah A + B + C 20,465.00 23,080.00


E Overhead & Profit (contoh 10%) 10% 2,046.50 2,308.00
F Harga Satuan Pekerjaan (D+E) 22,511.50 25,388.00

68 A.8.4.2.68 1 bh Pemotongan Pipa Baja Ø 200 mm 56,457.50 63,596.50


A Tenaga 49,525.00 55,715.00
L.01 0.476 OH Pekerja 75,000.00 85,000.00 35,700.00 40,460.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -

C PERALATAN 1,800.00 2,100.00


0.06 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,800.00 2,100.00

D Jumlah A + B + C 51,325.00 57,815.00


E Overhead & Profit (contoh 10%) 10% 5,132.50 5,781.50
F Harga Satuan Pekerjaan (D+E) 56,457.50 63,596.50
69 A.8.4.2.69 1 bh Pemotongan Pipa Baja Ø 250 mm 78,100.00 87,956.00
A Tenaga 68,960.00 77,580.00
L.01 0.663 OH Pekerja 75,000.00 85,000.00 49,725.00 56,355.00
L.02 0.133 OH Tukang Pipa 95,000.00 105,000.00 12,635.00 13,965.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -

C PERALATAN 2,040.00 2,380.00


0.068 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,040.00 2,380.00

D Jumlah A + B + C 71,000.00 79,960.00


E Overhead & Profit (contoh 10%) 10% 7,100.00 7,996.00
F Harga Satuan Pekerjaan (D+E) 78,100.00 87,956.00

70 A.8.4.2.70 1 bh Pemotongan Pipa Baja Ø 300 mm 87,549.00 98,593.00


A Tenaga 77,430.00 87,110.00
L.01 0.745 OH Pekerja 75,000.00 85,000.00 55,875.00 63,325.00
L.02 0.149 OH Tukang Pipa 95,000.00 105,000.00 14,155.00 15,645.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -

C PERALATAN 2,160.00 2,520.00


0.072 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,160.00 2,520.00

D Jumlah A + B + C 79,590.00 89,630.00


E Overhead & Profit (contoh 10%) 10% 7,959.00 8,963.00
F Harga Satuan Pekerjaan (D+E) 87,549.00 98,593.00

71 A.8.4.2.71 1 bh Pemotongan Pipa Baja Ø 400 mm 168,201.00 189,370.50


A Tenaga 149,760.00 168,480.00
L.01 1.440 OH Pekerja 75,000.00 85,000.00 108,000.00 122,400.00
L.02 0.288 OH Tukang Pipa 95,000.00 105,000.00 27,360.00 30,240.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -

C PERALATAN 3,150.00 3,675.00


0.105 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,150.00 3,675.00
- -
D Jumlah A + B + C 152,910.00 172,155.00
E Overhead & Profit (contoh 10%) 10% 15,291.00 17,215.50
F Harga Satuan Pekerjaan (D+E) 168,201.00 189,370.50

72 A.8.4.2.72 1 bh Pemotongan Pipa Baja Ø 450 mm 158,658.50 178,596.00


A Tenaga 141,025.00 158,615.00
L.01 1.339 OH Pekerja 75,000.00 85,000.00 100,425.00 113,815.00
L.02 0.280 OH Tukang Pipa 95,000.00 105,000.00 26,600.00 29,400.00
L.04 0.140 OH Mandor 100,000.00 110,000.00 14,000.00 15,400.00

B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 144,235.00 162,360.00
E Overhead & Profit (contoh 10%) 10% 14,423.50 16,236.00
F Harga Satuan Pekerjaan (D+E) 158,658.50 178,596.00
73 A.8.4.2.73 1 bh Pemotongan Pipa Baja Ø 500 mm 170,885.00 192,417.50
A Tenaga 152,140.00 171,180.00
L.01 1.473 OH Pekerja 75,000.00 85,000.00 110,475.00 125,205.00
L.02 0.287 OH Tukang Pipa 95,000.00 105,000.00 27,265.00 30,135.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 155,350.00 174,925.00
E Overhead & Profit (contoh 10%) 10% 15,535.00 17,492.50
F Harga Satuan Pekerjaan (D+E) 170,885.00 192,417.50

74 A.8.4.2.74 1 bh Pemotongan Pipa Baja Ø 600 mm 182,028.00 204,935.50


A Tenaga 162,090.00 182,350.00
L.01 1.558 OH Pekerja 75,000.00 85,000.00 116,850.00 132,430.00
L.02 0.312 OH Tukang Pipa 95,000.00 105,000.00 29,640.00 32,760.00
L.04 0.156 OH Mandor 100,000.00 110,000.00 15,600.00 17,160.00

B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -

C PERALATAN 3,390.00 3,955.00


0.113 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,390.00 3,955.00
- - - -
D Jumlah A + B + C 165,480.00 186,305.00
E Overhead & Profit (contoh 10%) 10% 16,548.00 18,630.50
F Harga Satuan Pekerjaan (D+E) 182,028.00 204,935.50

75 A.8.4.2.75 1 bh Pemotongan Pipa Baja Ø 800 mm 305,640.50 344,074.50


A Tenaga 272,875.00 306,985.00
L.01 2.624 OH Pekerja 75,000.00 85,000.00 196,800.00 223,040.00
L.02 0.525 OH Tukang Pipa 95,000.00 105,000.00 49,875.00 55,125.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -

C PERALATAN 4,980.00 5,810.00


0.166 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 4,980.00 5,810.00
- - - -
D Jumlah A + B + C 277,855.00 312,795.00
E Overhead & Profit (contoh 10%) 10% 27,785.50 31,279.50
F Harga Satuan Pekerjaan (D+E) 305,640.50 344,074.50

76 A.8.4.2.76 1 bh Pemotongan Pipa Baja Ø 900 mm 345,889.50 389,378.00


A Tenaga 308,955.00 347,575.00
L.01 2.971 OH Pekerja 75,000.00 85,000.00 222,825.00 252,535.00
L.02 0.594 OH Tukang Pipa 95,000.00 105,000.00 56,430.00 62,370.00
L.04 0.297 OH Mandor 100,000.00 110,000.00 29,700.00 32,670.00

B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -

C PERALATAN 5,490.00 6,405.00


0.183 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 5,490.00 6,405.00
- - - -
D Jumlah A + B + C 314,445.00 353,980.00
E Overhead & Profit (contoh 10%) 10% 31,444.50 35,398.00
F Harga Satuan Pekerjaan (D+E) 345,889.50 389,378.00
77 A.8.4.2.77 1 bh Pemotongan Pipa Baja Ø 1.000 mm 386,358.50 434,929.00
A Tenaga 345,205.00 388,355.00
L.01 3.319 OH Pekerja 75,000.00 85,000.00 248,925.00 282,115.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.332 OH Mandor 100,000.00 110,000.00 33,200.00 36,520.00

B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -

C PERALATAN 6,030.00 7,035.00


0.201 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,030.00 7,035.00
- - - -
D Jumlah A + B + C 351,235.00 395,390.00
E Overhead & Profit (contoh 10%) 10% 35,123.50 39,539.00
F Harga Satuan Pekerjaan (D+E) 386,358.50 434,929.00

78 A.8.4.2.78 1 bh Pemotongan Pipa Baja Ø 1.100 mm 426,690.00 480,326.00


A Tenaga 381,360.00 429,030.00
L.01 3.667 OH Pekerja 75,000.00 85,000.00 275,025.00 311,695.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.367 OH Mandor 100,000.00 110,000.00 36,700.00 40,370.00

B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -

C PERALATAN 6,540.00 7,630.00


0.218 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,540.00 7,630.00
- - - -
D Jumlah A + B + C 387,900.00 436,660.00
E Overhead & Profit (contoh 10%) 10% 38,790.00 43,666.00
F Harga Satuan Pekerjaan (D+E) 426,690.00 480,326.00

79 A.8.4.2.79 1 bh Pemotongan Pipa Baja Ø 1.200 mm 467,159.00 525,877.00


A Tenaga 417,610.00 469,810.00
L.01 4.015 OH Pekerja 75,000.00 85,000.00 301,125.00 341,275.00
L.02 0.803 OH Tukang Pipa 95,000.00 105,000.00 76,285.00 84,315.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00

B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -

C PERALATAN 7,080.00 8,260.00


0.236 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 7,080.00 8,260.00
- - - -
D Jumlah A + B + C 424,690.00 478,070.00
E Overhead & Profit (contoh 10%) 10% 42,469.00 47,807.00
F Harga Satuan Pekerjaan (D+E) 467,159.00 525,877.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN


XVIII A.8.4.3
AKSESORIS PIPA
1 A.8.4.3.1 1 bh Pemasangan Valve Ø 150 mm 264,440.00 306,317.00
A Tenaga 189,400.00 212,270.00
L.01 1.429 OH Pekerja 75,000.00 85,000.00 107,175.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00
B Bahan 50,000.00 65,000.00
1 bh Valve Ø 150 mm 50,000.00 65,000.00 50,000.00 65,000.00
C PERALATAN 1,000.00 1,200.00
0.1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00

D Jumlah A + B + C 240,400.00 278,470.00


E Overhead & Profit (contoh 10%) 10% 24,040.00 27,847.00
F Harga Satuan Pekerjaan (D+E) 264,440.00 306,317.00

2 A.8.4.3.2 1 bh Pemasangan Valve Ø 200 mm 335,571.50 382,893.50


A Tenaga 227,065.00 254,485.00
L.01 1.714 OH Pekerja 75,000.00 85,000.00 128,550.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 75,000.00 90,000.00


1 bh Valve Ø 200 mm 75,000.00 90,000.00 75,000.00 90,000.00

C PERALATAN 3,000.00 3,600.00


0.3 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,000.00 3,600.00

D Jumlah A + B + C 305,065.00 348,085.00


E Overhead & Profit (contoh 10%) 10% 30,506.50 34,808.50
F Harga Satuan Pekerjaan (D+E) 335,571.50 382,893.50

3 A.8.4.3.3 1 bh Pemasangan Valve Ø 250 mm 391,671.50 433,713.50


A Tenaga 227,065.00 254,485.00
L.01 1.714 OH Pekerja 75,000.00 85,000.00 128,550.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 125,000.00 135,000.00


1 bh Valve Ø 250 mm 125,000.00 135,000.00 125,000.00 135,000.00

C PERALATAN 4,000.00 4,800.00


0.4 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,000.00 4,800.00

D Jumlah A + B + C 356,065.00 394,285.00


E Overhead & Profit (contoh 10%) 10% 35,606.50 39,428.50
F Harga Satuan Pekerjaan (D+E) 391,671.50 433,713.50

4 A.8.4.3.4 1 bh Pemasangan Valve Ø 300 mm 462,000.00 520,300.00


A Tenaga 265,000.00 297,000.00
L.01 2.000 OH Pekerja 75,000.00 85,000.00 150,000.00 170,000.00
L.02 1.000 OH Tukang Pipa 95,000.00 105,000.00 95,000.00 105,000.00
L.04 0.200 OH Mandor 100,000.00 110,000.00 20,000.00 22,000.00

B Bahan 150,000.00 170,000.00


1 bh Valve Ø 300 mm 150,000.00 170,000.00 150,000.00 170,000.00

C PERALATAN 5,000.00 6,000.00


0.5 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
D Jumlah A + B + C 420,000.00 473,000.00
E Overhead & Profit (contoh 10%) 10% 42,000.00 47,300.00
F Harga Satuan Pekerjaan (D+E) 462,000.00 520,300.00
5 A.8.4.3.5 1 bh Pemasangan Valve Ø 400 mm 813,340.00 903,397.00
A Tenaga 454,400.00 509,270.00
L.01 3.429 OH Pekerja 75,000.00 85,000.00 257,175.00 291,465.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 275,000.00 300,000.00


1 bh Valve Ø 400 mm 275,000.00 300,000.00 275,000.00 300,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 739,400.00 821,270.00


E Overhead & Profit (contoh 10%) 10% 73,940.00 82,127.00
F Harga Satuan Pekerjaan (D+E) 813,340.00 903,397.00

6 A.8.4.3.6 1 bh Pemasangan Valve Ø 450 mm 868,340.00 958,397.00


A Tenaga 454,400.00 509,270.00
L.01 3.429 OH Pekerja 75,000.00 85,000.00 257,175.00 291,465.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 325,000.00 350,000.00


1 bh Valve Ø 450 mm 325,000.00 350,000.00 325,000.00 350,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 789,400.00 871,270.00


E Overhead & Profit (contoh 10%) 10% 78,940.00 87,127.00
F Harga Satuan Pekerjaan (D+E) 868,340.00 958,397.00

7 A.8.4.3.7 1 bh Pemasangan Valve Ø 500 mm 1,006,500.00 1,106,600.00


A Tenaga 530,000.00 594,000.00
L.01 4.000 OH Pekerja 75,000.00 85,000.00 300,000.00 340,000.00
L.02 2.000 OH Tukang Pipa 95,000.00 105,000.00 190,000.00 210,000.00
L.04 0.400 OH Mandor 100,000.00 110,000.00 40,000.00 44,000.00

B Bahan 375,000.00 400,000.00


1 bh Valve Ø 500 mm 375,000.00 400,000.00 375,000.00 400,000.00

C PERALATAN 10,000.00 12,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 915,000.00 1,006,000.00


E Overhead & Profit (contoh 10%) 10% 91,500.00 100,600.00
F Harga Satuan Pekerjaan (D+E) 1,006,500.00 1,106,600.00

8 A.8.4.3.8 1 bh Pemasangan Valve Ø 600 mm 730,752.00 791,186.00


A Tenaga 188,320.00 211,060.00
L.01 1.421 OH Pekerja 75,000.00 85,000.00 106,575.00 120,785.00
L.02 0.711 OH Tukang Pipa 95,000.00 105,000.00 67,545.00 74,655.00
L.04 0.142 OH Mandor 100,000.00 110,000.00 14,200.00 15,620.00

B Bahan 425,000.00 450,000.00


1 bh Valve Ø 600 mm 425,000.00 450,000.00 425,000.00 450,000.00

C PERALATAN 51,000.00 58,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00
0.300 hari Mobile crane = < 3 ton 150,000.00 170,000.00 45,000.00 51,000.00
D Jumlah A + B + C 664,320.00 719,260.00
E Overhead & Profit (contoh 10%) 10% 66,432.00 71,926.00
F Harga Satuan Pekerjaan (D+E) 730,752.00 791,186.00
9 A.8.4.3.9 1 bh Pemasangan Valve Ø 700 mm 846,340.00 905,597.00
A Tenaga 189,400.00 212,270.00
L.01 1.429 OH Pekerja 75,000.00 85,000.00 107,175.00 121,465.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan 500,000.00 520,000.00


1 bh Valve Ø 700 mm 500,000.00 520,000.00 500,000.00 520,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 769,400.00 823,270.00
E Overhead & Profit (contoh 10%) 10% 76,940.00 82,327.00
F Harga Satuan Pekerjaan (D+E) 846,340.00 905,597.00

10 A.8.4.3.10 1 bh Pemasangan Valve Ø 800 mm 953,353.50 1,024,391.50


A Tenaga 236,685.00 265,265.00
L.01 1.786 OH Pekerja 75,000.00 85,000.00 133,950.00 151,810.00
L.02 0.893 OH Tukang Pipa 95,000.00 105,000.00 84,835.00 93,765.00
L.04 0.179 OH Mandor 100,000.00 110,000.00 17,900.00 19,690.00

B Bahan 550,000.00 575,000.00


1 bh Valve Ø 800 mm 550,000.00 575,000.00 550,000.00 575,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 866,685.00 931,265.00
E Overhead & Profit (contoh 10%) 10% 86,668.50 93,126.50
F Harga Satuan Pekerjaan (D+E) 953,353.50 1,024,391.50

11 A.8.4.3.11 1 bh Pemasangan Valve Ø 900 mm 1,041,771.50 1,117,583.50


A Tenaga 227,065.00 254,485.00
L.01 1.714 OH Pekerja 75,000.00 85,000.00 128,550.00 145,690.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan 600,000.00 625,000.00
1 bh Valve Ø 900 mm 600,000.00 625,000.00 600,000.00 625,000.00
C PERALATAN 120,000.00 136,500.00
0.750 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 7,500.00 9,000.00
0.750 hari Mobile crane = < 3 ton 150,000.00 170,000.00 112,500.00 127,500.00
D Jumlah A + B + C 947,065.00 1,015,985.00
E Overhead & Profit (contoh 10%) 10% 94,706.50 101,598.50
F Harga Satuan Pekerjaan (D+E) 1,041,771.50 1,117,583.50

12 A.8.4.3.12 1 bh Pemasangan Valve Ø 1.000 mm 1,265,764.50 1,346,218.50


A Tenaga 340,695.00 381,835.00
L.01 2.571 OH Pekerja 75,000.00 85,000.00 192,825.00 218,535.00
L.02 1.286 OH Tukang Pipa 95,000.00 105,000.00 122,170.00 135,030.00
L.04 0.257 OH Mandor 100,000.00 110,000.00 25,700.00 28,270.00

B Bahan 650,000.00 660,000.00


1 bh Valve Ø 1.000 mm 650,000.00 660,000.00 650,000.00 660,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,150,695.00 1,223,835.00
E Overhead & Profit (contoh 10%) 10% 115,069.50 122,383.50
F Harga Satuan Pekerjaan (D+E) 1,265,764.50 1,346,218.50
13 A.8.4.3.13 1 bh Pemasangan Valve Ø 1.100 mm 1,383,250.00 1,471,250.00
A Tenaga 397,500.00 445,500.00
L.01 3.000 OH Pekerja 75,000.00 85,000.00 225,000.00 255,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 700,000.00 710,000.00


1 bh Valve Ø 1.100 mm 700,000.00 710,000.00 700,000.00 710,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,257,500.00 1,337,500.00
E Overhead & Profit (contoh 10%) 10% 125,750.00 133,750.00
F Harga Satuan Pekerjaan (D+E) 1,383,250.00 1,471,250.00

14 A.8.4.3.14 1 bh Pemasangan Valve Ø 1.200 mm 1,416,250.00 1,515,250.00


A 397,500.00 445,500.00
L.01 3.000 OH Pekerja 75,000.00 85,000.00 225,000.00 255,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 730,000.00 750,000.00


1 bh Valve Ø 1.200 mm 730,000.00 750,000.00 730,000.00 750,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,287,500.00 1,377,500.00
E Overhead & Profit (contoh 10%) 10% 128,750.00 137,750.00
F Harga Satuan Pekerjaan (D+E) 1,416,250.00 1,515,250.00

15 A.8.4.3.15 1 bh Pemasangan Tee Ø 150 mm 29,001.50 34,233.10


A Tenaga 14,085.00 15,785.00
L.01 0.106 OH Pekerja 75,000.00 85,000.00 7,950.00 9,010.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan 12,000.00 15,000.00


1 bh Tee Ø 150 mm 12,000.00 15,000.00 12,000.00 15,000.00

C PERALATAN 280.00 336.00


0.028 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 280.00 336.00

D Jumlah A + B + C 26,365.00 31,121.00


E Overhead & Profit (contoh 10%) 10% 2,636.50 3,112.10
F Harga Satuan Pekerjaan (D+E) 29,001.50 34,233.10

16 A.8.4.3.16 1 bh Pemasangan Tee Ø 200 mm 48,345.00 57,714.80


A Tenaga 28,660.00 32,120.00
L.01 0.216 OH Pekerja 75,000.00 85,000.00 16,200.00 18,360.00
L.02 0.108 OH Tukang Pipa 95,000.00 105,000.00 10,260.00 11,340.00
L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00
B Bahan 15,000.00 20,000.00
1 bh Tee Ø 200 mm 15,000.00 20,000.00 15,000.00 20,000.00

C PERALATAN 290.00 348.00


0.029 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 290.00 348.00
D Jumlah A + B + C 43,950.00 52,468.00
E Overhead & Profit (contoh 10%) 10% 4,395.00 5,246.80
F Harga Satuan Pekerjaan (D+E) 48,345.00 57,714.80
17 A.8.4.3.17 1 bh Pemasangan Tee Ø 250 mm 75,487.50 86,815.30
A Tenaga 43,235.00 48,455.00
L.01 0.326 OH Pekerja 75,000.00 85,000.00 24,450.00 27,710.00
L.02 0.163 OH Tukang Pipa 95,000.00 105,000.00 15,485.00 17,115.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan 25,000.00 30,000.00


1 BH Tee Ø 250 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 390.00 468.00


0.039 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 390.00 468.00

D Jumlah A + B + C 68,625.00 78,923.00


E Overhead & Profit (contoh 10%) 10% 6,862.50 7,892.30
F Harga Satuan Pekerjaan (D+E) 75,487.50 86,815.30

18 A.8.4.3.18 1 bh Pemasangan Tee Ø 300 mm 107,591.00 121,869.00


A Tenaga 57,810.00 64,790.00
L.01 0.436 OH Pekerja 75,000.00 85,000.00 32,700.00 37,060.00
L.02 0.218 OH Tukang Pipa 95,000.00 105,000.00 20,710.00 22,890.00
L.04 0.044 OH Mandor 100,000.00 110,000.00 4,400.00 4,840.00

B Bahan 35,000.00 40,000.00


1 bh Tee Ø 300 mm 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 97,810.00 110,790.00


E Overhead & Profit (contoh 10%) 10% 9,781.00 11,079.00
F Harga Satuan Pekerjaan (D+E) 107,591.00 121,869.00

19 A.8.4.3.19 1 bh Pemasangan Tee Ø 400 mm 150,656.00 168,806.00


A Tenaga 86,960.00 97,460.00
L.01 0.656 OH Pekerja 75,000.00 85,000.00 49,200.00 55,760.00
L.02 0.328 OH Tukang Pipa 95,000.00 105,000.00 31,160.00 34,440.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan 45,000.00 50,000.00


1 bh Tee Ø 400 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 5,000.00 6,000.00
0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 136,960.00 153,460.00


E Overhead & Profit (contoh 10%) 10% 13,696.00 15,346.00
F Harga Satuan Pekerjaan (D+E) 150,656.00 168,806.00

20 A.8.4.3.20 1 bh Pemasangan Tee Ø 450 mm 188,688.50 208,774.50


A Tenaga 101,535.00 113,795.00
L.01 0.766 OH Pekerja 75,000.00 85,000.00 57,450.00 65,110.00
L.02 0.383 OH Tukang Pipa 95,000.00 105,000.00 36,385.00 40,215.00
L.04 0.077 OH Mandor 100,000.00 110,000.00 7,700.00 8,470.00

B Bahan 65,000.00 70,000.00


1 bh Tee Ø 450 mm 65,000.00 70,000.00 65,000.00 70,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 171,535.00 189,795.00


E Overhead & Profit (contoh 10%) 10% 17,153.50 18,979.50
F Harga Satuan Pekerjaan (D+E) 188,688.50 208,774.50
21 A.8.4.3.21 1 bh Pemasangan Tee Ø 500 mm 216,821.00 239,063.00
A Tenaga 116,110.00 130,130.00
L.01 0.876 OH Pekerja 75,000.00 85,000.00 65,700.00 74,460.00
L.02 0.438 OH Tukang Pipa 95,000.00 105,000.00 41,610.00 45,990.00
L.04 0.088 OH Mandor 100,000.00 110,000.00 8,800.00 9,680.00

B Bahan 75,000.00 80,000.00


1 bh Tee Ø 500 mm 75,000.00 80,000.00 75,000.00 80,000.00

C PERALATAN 6,000.00 7,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00

D Jumlah A + B + C 197,110.00 217,330.00


E Overhead & Profit (contoh 10%) 10% 19,711.00 21,733.00
F Harga Satuan Pekerjaan (D+E) 216,821.00 239,063.00

22 A.8.4.3.22 1 bh Pemasangan Tee Ø 600 mm 276,749.00 309,579.60


A Tenaga 145,260.00 162,800.00
L.01 1.096 OH Pekerja 75,000.00 85,000.00 82,200.00 93,160.00
L.02 0.548 OH Tukang Pipa 95,000.00 105,000.00 52,060.00 57,540.00
L.04 0.110 OH Mandor 100,000.00 110,000.00 11,000.00 12,100.00

B Bahan 90,000.00 100,000.00


1 bh Tee Ø 600 mm 90,000.00 100,000.00 90,000.00 100,000.00

C PERALATAN 16,330.00 18,636.00


0.193 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,930.00 2,316.00
0.096 hari Mobile crane = < 3 ton 150,000.00 170,000.00 14,400.00 16,320.00
D Jumlah A + B + C 251,590.00 281,436.00
E Overhead & Profit (contoh 10%) 10% 25,159.00 28,143.60
F Harga Satuan Pekerjaan (D+E) 276,749.00 309,579.60

23 A.8.4.3.23 1 bh Pemasangan Tee Ø 700 mm 333,971.00 365,618.00


A Tenaga 174,410.00 195,470.00
L.01 1.316 OH Pekerja 75,000.00 85,000.00 98,700.00 111,860.00
L.02 0.658 OH Tukang Pipa 95,000.00 105,000.00 62,510.00 69,090.00
L.04 0.132 OH Mandor 100,000.00 110,000.00 13,200.00 14,520.00

B Bahan 110,000.00 115,000.00


1 bh Tee Ø 700 mm 110,000.00 115,000.00 110,000.00 115,000.00

C PERALATAN 19,200.00 21,910.00


0.225 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,250.00 2,700.00
0.113 hari Mobile crane = < 3 ton 150,000.00 170,000.00 16,950.00 19,210.00
D Jumlah A + B + C 303,610.00 332,380.00
E Overhead & Profit (contoh 10%) 10% 30,361.00 33,238.00
F Harga Satuan Pekerjaan (D+E) 333,971.00 365,618.00

24 A.8.4.3.24 1 bh Pemasangan Tee Ø 800 mm 380,028.00 421,469.40


A Tenaga 203,560.00 228,140.00
L.01 1.536 OH Pekerja 75,000.00 85,000.00 115,200.00 130,560.00
L.02 0.768 OH Tukang Pipa 95,000.00 105,000.00 72,960.00 80,640.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00
B Bahan 120,000.00 130,000.00
1 bh Tee Ø 800 mm 120,000.00 130,000.00 120,000.00 130,000.00
C PERALATAN 21,920.00 25,014.00
0.257 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,570.00 3,084.00
0.129 hari Mobile crane = < 3 ton 150,000.00 170,000.00 19,350.00 21,930.00
D Jumlah A + B + C 345,480.00 383,154.00
E Overhead & Profit (contoh 10%) 10% 34,548.00 38,315.40
F Harga Satuan Pekerjaan (D+E) 380,028.00 421,469.40
25 A.8.4.3.25 1 bh Pemasangan Tee Ø 900 mm 440,077.00 486,235.20
A Tenaga 232,710.00 260,810.00
L.01 1.756 OH Pekerja 75,000.00 85,000.00 131,700.00 149,260.00
L.02 0.878 OH Tukang Pipa 95,000.00 105,000.00 83,410.00 92,190.00
L.04 0.176 OH Mandor 100,000.00 110,000.00 17,600.00 19,360.00

B Bahan 140,000.00 150,000.00


1 bh Tee Ø 900 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN 27,360.00 31,222.00


0.321 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,210.00 3,852.00
0.161 hari Mobile crane = < 3 ton 150,000.00 170,000.00 24,150.00 27,370.00
D Jumlah A + B + C 400,070.00 442,032.00
E Overhead & Profit (contoh 10%) 10% 40,007.00 44,203.20
F Harga Satuan Pekerjaan (D+E) 440,077.00 486,235.20

26 A.8.4.3.26 1 bh Pemasangan Tee Ø 1.000 mm 498,267.00 548,880.20


A Tenaga 261,860.00 293,480.00
L.01 1.976 OH Pekerja 75,000.00 85,000.00 148,200.00 167,960.00
L.02 0.988 OH Tukang Pipa 95,000.00 105,000.00 93,860.00 103,740.00
L.04 0.198 OH Mandor 100,000.00 110,000.00 19,800.00 21,780.00

B Bahan 160,000.00 170,000.00


1 bh Tee Ø 1.000 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN 31,110.00 35,502.00


0.366 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,660.00 4,392.00
0.183 hari Mobile crane = < 3 ton 150,000.00 170,000.00 27,450.00 31,110.00
D Jumlah A + B + C 452,970.00 498,982.00
E Overhead & Profit (contoh 10%) 10% 45,297.00 49,898.20
F Harga Satuan Pekerjaan (D+E) 498,267.00 548,880.20

27 A.8.4.3.27 1 bh Pemasangan Tee Ø 1.100 mm 554,202.00 608,951.20


A Tenaga 291,010.00 326,150.00
L.01 2.196 OH Pekerja 75,000.00 85,000.00 164,700.00 186,660.00
L.02 1.098 OH Tukang Pipa 95,000.00 105,000.00 104,310.00 115,290.00
L.04 0.220 OH Mandor 100,000.00 110,000.00 22,000.00 24,200.00

B Bahan 180,000.00 190,000.00


1 bh Tee Ø 1.100 mm 180,000.00 190,000.00 180,000.00 190,000.00

C PERALATAN 32,810.00 37,442.00


0.386 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,860.00 4,632.00
0.193 hari Mobile crane = < 3 ton 150,000.00 170,000.00 28,950.00 32,810.00
D Jumlah A + B + C 503,820.00 553,592.00
E Overhead & Profit (contoh 10%) 10% 50,382.00 55,359.20
F Harga Satuan Pekerjaan (D+E) 554,202.00 608,951.20

28 A.8.4.3.28 1 bh Pemasangan Tee Ø 1.200 mm 614,251.00 673,717.00


A Tenaga 320,160.00 358,820.00
L.01 2.416 OH Pekerja 75,000.00 85,000.00 181,200.00 205,360.00
L.02 1.208 OH Tukang Pipa 95,000.00 105,000.00 114,760.00 126,840.00
L.04 0.242 OH Mandor 100,000.00 110,000.00 24,200.00 26,620.00
B Bahan 200,000.00 210,000.00
1 bh Tee Ø 1.200 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 38,250.00 43,650.00
0.450 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,500.00 5,400.00
0.225 hari Mobile crane = < 3 ton 150,000.00 170,000.00 33,750.00 38,250.00
D Jumlah A + B + C 558,410.00 612,470.00
E Overhead & Profit (contoh 10%) 10% 55,841.00 61,247.00
F Harga Satuan Pekerjaan (D+E) 614,251.00 673,717.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

1 A.8.4.4.1 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 440,368.50 516,180.50
80 mm
A Tenaga 194,285.00 217,745.00
L.01 1.466 OH Pekerja 75,000.00 85,000.00 109,950.00 124,610.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 50,000.00 65,000.00


1 bh Pipa Ø 80 mm 50,000.00 65,000.00 50,000.00 65,000.00

C PERALATAN 156,050.00 186,510.00


0.606 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 15,150.00 18,180.00
0.075 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 11,250.00 12,750.00
0.968 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 121,000.00 145,200.00
0.865 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,650.00 10,380.00

D Jumlah A + B + C 400,335.00 469,255.00


E Overhead & Profit (contoh 10%) 10% 40,033.50 46,925.50
F Harga Satuan Pekerjaan (D+E) 440,368.50 516,180.50

2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 519,304.50 598,000.70
100 mm
A Tenaga 218,135.00 244,475.00
L.01 1.646 OH Pekerja 75,000.00 85,000.00 123,450.00 139,910.00
L.02 0.823 OH Tukang Pipa 95,000.00 105,000.00 78,185.00 86,415.00
L.04 0.165 OH Mandor 100,000.00 110,000.00 16,500.00 18,150.00

B Bahan 70,000.00 80,000.00


1 bh Pipa Ø 100 mm 70,000.00 80,000.00 70,000.00 80,000.00

C PERALATAN 183,960.00 219,162.00


0.650 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 16,250.00 19,500.00
0.159 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 23,850.00 27,030.00
1.078 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 134,750.00 161,700.00
0.911 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 9,110.00 10,932.00

D Jumlah A + B + C 472,095.00 543,637.00


E Overhead & Profit (contoh 10%) 10% 47,209.50 54,363.70
F Harga Satuan Pekerjaan (D+E) 519,304.50 598,000.70

3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 749,644.50 849,301.20
150 mm
A Tenaga 277,760.00 311,300.00
L.01 2.096 OH Pekerja 75,000.00 85,000.00 157,200.00 178,160.00
L.02 1.048 OH Tukang Pipa 95,000.00 105,000.00 99,560.00 110,040.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 681,495.00 772,092.00
E Overhead & Profit (contoh 10%) 10% 68,149.50 77,209.20
F Harga Satuan Pekerjaan (D+E) 749,644.50 849,301.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 946,984.50 1,078,601.70
200 mm
A Tenaga 337,385.00 378,125.00
L.01 2.546 OH Pekerja 75,000.00 85,000.00 190,950.00 216,410.00
L.02 1.273 OH Tukang Pipa 95,000.00 105,000.00 120,935.00 133,665.00
L.04 0.255 OH Mandor 100,000.00 110,000.00 25,500.00 28,050.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 860,895.00 980,547.00
E Overhead & Profit (contoh 10%) 10% 86,089.50 98,054.70
F Harga Satuan Pekerjaan (D+E) 946,984.50 1,078,601.70

5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,116,824.50 1,263,902.20
250 mm
A Tenaga 397,010.00 444,950.00
L.01 2.996 OH Pekerja 75,000.00 85,000.00 224,700.00 254,660.00
L.02 1.498 OH Tukang Pipa 95,000.00 105,000.00 142,310.00 157,290.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
B Bahan 225,000.00 240,000.00
1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00
C PERALATAN 393,285.00 464,052.00
0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00
D Jumlah A + B + C 1,015,295.00 1,149,002.00
E Overhead & Profit (contoh 10%) 10% 101,529.50 114,900.20
F Harga Satuan Pekerjaan (D+E) 1,116,824.50 1,263,902.20

6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,275,664.50 1,438,202.70
300 mm
A Tenaga 456,635.00 511,775.00
L.01 3.446 OH Pekerja 75,000.00 85,000.00 258,450.00 292,910.00
L.02 1.723 OH Tukang Pipa 95,000.00 105,000.00 163,685.00 180,915.00
L.04 0.345 OH Mandor 100,000.00 110,000.00 34,500.00 37,950.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,159,695.00 1,307,457.00
E Overhead & Profit (contoh 10%) 10% 115,969.50 130,745.70
F Harga Satuan Pekerjaan (D+E) 1,275,664.50 1,438,202.70

7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,593,344.50 1,797,803.70
400 mm
A Tenaga 575,885.00 645,425.00
L.01 4.346 OH Pekerja 75,000.00 85,000.00 325,950.00 369,410.00
L.02 2.173 OH Tukang Pipa 95,000.00 105,000.00 206,435.00 228,165.00
L.04 0.435 OH Mandor 100,000.00 110,000.00 43,500.00 47,850.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,448,495.00 1,634,367.00
E Overhead & Profit (contoh 10%) 10% 144,849.50 163,436.70
F Harga Satuan Pekerjaan (D+E) 1,593,344.50 1,797,803.70

8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,757,684.50 1,983,104.20
450 mm
A Tenaga 635,510.00 712,250.00
L.01 4.796 OH Pekerja 75,000.00 85,000.00 359,700.00 407,660.00
L.02 2.398 OH Tukang Pipa 95,000.00 105,000.00 227,810.00 251,790.00
L.04 0.480 OH Mandor 100,000.00 110,000.00 48,000.00 52,800.00

B Bahan 290,000.00 300,000.00


1 bh Pipa Ø 450 mm 290,000.00 300,000.00 290,000.00 300,000.00

C PERALATAN 672,385.00 790,572.00


1.420 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 35,500.00 42,600.00
1.629 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 244,350.00 276,930.00
3.003 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 375,375.00 450,450.00
1.716 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 17,160.00 20,592.00

D Jumlah A + B + C 1,597,895.00 1,802,822.00


E Overhead & Profit (contoh 10%) 10% 159,789.50 180,282.20
F Harga Satuan Pekerjaan (D+E) 1,757,684.50 1,983,104.20

9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,933,024.50 2,179,404.70
500 mm
A Tenaga 695,135.00 779,075.00
L.01 5.246 OH Pekerja 75,000.00 85,000.00 393,450.00 445,910.00
L.02 2.623 OH Tukang Pipa 95,000.00 105,000.00 249,185.00 275,415.00
L.04 0.525 OH Mandor 100,000.00 110,000.00 52,500.00 57,750.00

B Bahan 320,000.00 330,000.00


1 bh Pipa Ø 500 mm 320,000.00 330,000.00 320,000.00 330,000.00

C PERALATAN 742,160.00 872,202.00


1.530 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 38,250.00 45,900.00
1.839 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 275,850.00 312,630.00
3.278 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 409,750.00 491,700.00
1.831 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 18,310.00 21,972.00

D Jumlah A + B + C 1,757,295.00 1,981,277.00


E Overhead & Profit (contoh 10%) 10% 175,729.50 198,127.70
F Harga Satuan Pekerjaan (D+E) 1,933,024.50 2,179,404.70

10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,250,704.50 2,539,005.70
600 mm
A Tenaga 814,385.00 912,725.00
L.01 6.146 OH Pekerja 75,000.00 85,000.00 460,950.00 522,410.00
L.02 3.073 OH Tukang Pipa 95,000.00 105,000.00 291,935.00 322,665.00
L.04 0.615 OH Mandor 100,000.00 110,000.00 61,500.00 67,650.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
D Jumlah A + B + C 2,046,095.00 2,308,187.00
E Overhead & Profit (contoh 10%) 10% 204,609.50 230,818.70
F Harga Satuan Pekerjaan (D+E) 2,250,704.50 2,539,005.70
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,601,384.50 2,931,606.70
700 mm
A Tenaga 933,635.00 1,046,375.00
L.01 7.046 OH Pekerja 75,000.00 85,000.00 528,450.00 598,910.00
L.02 3.523 OH Tukang Pipa 95,000.00 105,000.00 334,685.00 369,915.00
L.04 0.705 OH Mandor 100,000.00 110,000.00 70,500.00 77,550.00
B Bahan 410,000.00 420,000.00
1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00

D Jumlah A + B + C 2,364,895.00 2,665,097.00


E Overhead & Profit (contoh 10%) 10% 236,489.50 266,509.70
F Harga Satuan Pekerjaan (D+E) 2,601,384.50 2,931,606.70

12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,908,064.50 3,291,207.70
800 mm
A Tenaga 1,052,885.00 1,180,025.00
L.01 7.946 OH Pekerja 75,000.00 85,000.00 595,950.00 675,410.00
L.02 3.973 OH Tukang Pipa 95,000.00 105,000.00 377,435.00 417,165.00
L.04 0.795 OH Mandor 100,000.00 110,000.00 79,500.00 87,450.00

B Bahan 430,000.00 450,000.00


1 bh Pipa Ø 800 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 1,160,810.00 1,361,982.00


2.190 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 54,750.00 65,700.00
3.099 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 464,850.00 526,830.00
4.928 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 616,000.00 739,200.00
2.521 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 25,210.00 30,252.00

D Jumlah A + B + C 2,643,695.00 2,992,007.00


E Overhead & Profit (contoh 10%) 10% 264,369.50 299,200.70
F Harga Satuan Pekerjaan (D+E) 2,908,064.50 3,291,207.70
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XX A.8.4.5
PENGETESAN
1 A.8.4.5.1 1 m' Pengetesan Pipa Ø 50 mm 1,292.83 1,419.44
A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 495.30 522.40


0.002 m³ Air Bersih 150.00 200.00 0.30 0.40
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,175.30 1,290.40
E Overhead & Profit (contoh 10%) 10% 117.53 129.04
F Harga Satuan Pekerjaan (D+E) 1,292.83 1,419.44

2 A.8.4.5.2 1 m' Pengetesan Pipa Ø 75 mm 1,293.16 1,419.88


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 495.60 522.80


0.004 m³ Air Bersih 150.00 200.00 0.60 0.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,175.60 1,290.80
E Overhead & Profit (contoh 10%) 10% 117.56 129.08
F Harga Satuan Pekerjaan (D+E) 1,293.16 1,419.88

3 A.8.4.5.3 1 m' Pengetesan Pipa Ø 100 mm 1,293.82 1,420.76


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 496.20 523.60


0.008 m³ Air Bersih 150.00 200.00 1.20 1.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,176.20 1,291.60
E Overhead & Profit (contoh 10%) 10% 117.62 129.16
F Harga Satuan Pekerjaan (D+E) 1,293.82 1,420.76

4 A.8.4.5.4 1 m' Pengetesan Pipa Ø 150 mm 1,295.47 1,422.96


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 497.70 525.60


0.0180 m³ Air Bersih 150.00 200.00 2.70 3.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,177.70 1,293.60
E Overhead & Profit (contoh 10%) 10% 117.77 129.36
F Harga Satuan Pekerjaan (D+E) 1,295.47 1,422.96
5 A.8.4.5.5 1 m' Pengetesan Pipa Ø 200 mm 1,297.62 1,425.82
A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 499.65 528.20
0.031 m³ Air Bersih 150.00 200.00 4.65 6.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,179.65 1,296.20
E Overhead & Profit (contoh 10%) 10% 117.97 129.62
F Harga Satuan Pekerjaan (D+E) 1,297.62 1,425.82

6 A.8.4.5.6 1 m' Pengetesan Pipa Ø 250 mm 1,300.59 1,429.78


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 502.35 531.80
0.049 m³ Air Bersih 150.00 200.00 7.35 9.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,182.35 1,299.80
E Overhead & Profit (contoh 10%) 10% 118.24 129.98
F Harga Satuan Pekerjaan (D+E) 1,300.59 1,429.78

7 A.8.4.5.7 1 m' Pengetesan Pipa Ø 300 mm 1,304.22 1,434.62


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 505.65 536.20
0.071 m³ Air Bersih 150.00 200.00 10.65 14.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,185.65 1,304.20
E Overhead & Profit (contoh 10%) 10% 118.57 130.42
F Harga Satuan Pekerjaan (D+E) 1,304.22 1,434.62

8 A.8.4.5.8 1 m' Pengetesan Pipa Ø 400 mm 1,313.29 1,446.72


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 513.90 547.20
0.126 m³ Air Bersih 150.00 200.00 18.90 25.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,193.90 1,315.20
E Overhead & Profit (contoh 10%) 10% 119.39 131.52
F Harga Satuan Pekerjaan (D+E) 1,313.29 1,446.72

9 A.8.4.5.9 1 m' Pengetesan Pipa Ø 500 mm 1,318.57 1,453.76


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 518.70 553.60
0.158 m³ Air Bersih 150.00 200.00 23.70 31.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,198.70 1,321.60
E Overhead & Profit (contoh 10%) 10% 119.87 132.16
F Harga Satuan Pekerjaan (D+E) 1,318.57 1,453.76

10 A.8.4.5.10 1 m' Pengetesan Pipa Ø 600 mm 1,339.20 1,481.26


A Tenaga 680.00 768.00
L.01 0.008 OH Pekerja 75,000.00 85,000.00 600.00 680.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00
B Bahan 537.45 578.60
0.283 m³ Air Bersih 150.00 200.00 42.45 56.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,217.45 1,346.60


E Overhead & Profit (contoh 10%) 10% 121.75 134.66
F Harga Satuan Pekerjaan (D+E) 1,339.20 1,481.26

Anda mungkin juga menyukai