Tahun 2020
Provinsi Jawa Tengah
Kota Salatiga
( dalam Rupiah)
GEDUNG NEGARA
TIDAK SEDERHANA SEDERHANA
6,530,000 4,720,000
RUMAH NEGARA
TIPE A TIPE B TIPE C,D,E
6,050,000 5,610,000 5,170,000
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM KET.
(Rp)
1 Pekerja Hr 90,000 80,000.00
2 Mandor Hr 120,000 110,000.00
3 Tukang listrik Hr 105,000 100,000.00
4 Tukang kayu Hr 105,000 ###
5 Kep. tk. kayu Hr 110,000 ###
6 Tukang batu Hr 105,000 ###
7 Kep. tk. batu Hr 110,000 ###
8 Tukang besi Hr 105,000 ###
9 Kep. tk. besi Hr 110,000 ###
10 T u k a n g c a t Hr 105,000 ###
11 K e p . t k . c a t Hr 110,000 105,000.00
12 T u k a n g p l i t u r Hr 105,000 ###
13 T u k a n g j a l a n Hr 105,000 ###
14 T u k a n g g a l i Hr 105,000 ###
HARGA
NO. J E N I S B A H A N SAT MINIMUM KET
(Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 350,000
Bulat Belah m3 350,000
Pecah 10/15 m3 350,000
Pecah 5/7 m3 350,000
Pecah 3/5 m3 350,000
2 KERIKIL Timbun m3
Sawur / Koral m3
Beton 0,5/1 m3 350,000
Beton ,1/2 m3 350,000
Beton ,2/3 m3 350,000
Biasa m3
Tras Giling m3
3 BATU BATA ex lokal bh 850
BATA RINGAN 0,6 x 0,2 x 0,1 bh 10,000
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 942,820.78
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 201,849.56
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 100,369.06
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 123,083.84
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,672,673.41
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
A.2.2.1.2 1 m' 942,820.78
1 2,00 m
A TENAGA 64,600.00
L.01 0.2 OH Pekerja 90,000.00 18,000.00
L.02 0.4 OH Tukang Kayu 105,000.00 42,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
L.04 0.02 OH Mandor 120,000.00 2,400.00
B BAHAN 792,509.80
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 61,600.00 77,000.00
2.5 Kg Portalnd Semen 1,200.00 3,000.00
1.2 Lbr Seng Gelombang 3" - 5" 66,000.00 79,200.00
0.005 m3 Pasir Beton 325,000.00 1,625.00
0.009 m3 Koral Beton 350,000.00 3,150.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 8,518,400.00 613,324.80
0.06 Kg Paku Biasa 2" - 5" 22,500.00 1,350.00
0.45 Kg Meni Besi 30,800.00 13,860.00
C PERALATAN
D Jumlah A + B + C 857,109.80
E Overhead & Profit (contah 10%) 10% 85,710.98
F Harga Satuan Pekerjaan (D+E) 942,820.78
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 201,849.56
A Tenaga 21,200.00
L.01 0.1 OH Pekerja 90,000.00 9,000.00
L.02 0.1 OH Tukang Kayu 105,000.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 120,000.00 600.00
B Bahan 162,299.60
0.012 m3 Kayu 5/7x 4m Kayu Kruing 8,518,400.00 102,220.80
0.02 Kg Paku Biasa 2" - 5" 22,500.00 450.00
0.007 m3 Kayu Papan 3/20 Kruing 8,518,400.00 59,628.80
C PERALATAN
D Jumlah A + B + C 183,499.60
E Overhead & Profit (contah 10%) 10% 18,349.96
F Harga Satuan Pekerjaan (D+E) 201,849.56
A Tenaga 534,000.00
L.01 2 OH Pekerja 90,000.00 180,000.00
L.02 2 OH Tukang Kayu 105,000.00 210,000.00
L.02 1 OH Tukang Batu 105,000.00 105,000.00
L.03 0.3 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.05 OH Mandor 120,000.00 6,000.00
B Bahan 1,888,876.50
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 61,600.00 77,000.00
0.18 m3 Kayu 8,518,400.00 1,533,312.00
0.80 Kg Paku Biasa 2" - 5" 22,500.00 18,000.00
1.1 Kg Besi Strip 16,000.00 17,600.00
35 Kg Portland Sement 1,200.00 42,000.00
0.15 m3 Pasir pasang 300,000.00 45,000.00
0.1 m3 Pasir Beton 325,000.00 32,500.00
0.15 m3 Koral Beton 350,000.00 52,500.00
30 buah Batu bata Merah 850.00 25,500.00
0.25 Lbr Seng Plat 43,890.00 10,972.50
0.20 buah Jendela Naco 46,750.00 9,350.00
0.08 m2 Kaca Polos 106,150.00 8,492.00
0.15 buah Kunci Tanam 77,000.00 11,550.00
0.06 Lbr Plywood 4 mm 85,000.00 5,100.00
HARGA JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
C PERALATAN
D Jumlah A + B + C 2,422,876.50
E Overhead & Profit (contah 10%) 10% 242,287.65
F Harga Satuan Pekerjaan (D+E) 2,665,164.15
24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 100,369.06
A Tenaga 24,240.00
L.01 0.180 OH Pekerja 90,000.00 16,200.00
L.02 0.020 OH Tukang batu 105,000.00 2,100.00
L.02 0.020 OH Tukang Kayu 105,000.00 2,100.00
L.02 0.020 OH Tukang Besi 105,000.00 2,100.00
L.03 0.006 OH Kepala Tukang 110,000.00 660.00
L.04 0.009 OH Mandor 120,000.00 1,080.00
B Bahan 67,004.60
0.002 m3 Kayu Terentang 1,064,800.00 2,129.60
0.01 Kg Paku Biasa 2" - 5" 22,500.00 225.00
3.0 Kg Besi Beton Polos 14,500.00 43,500.00
0.45 Kg Kawat Beton 25,000.00 11,250.00
4.0 Kg Portland Semen 1,200.00 4,800.00
0.006 m3 Pasir Beton 325,000.00 1,950.00
0.009 m3 Kerikil 350,000.00 3,150.00
C PERALATAN
D Jumlah A + B + C 91,244.60
E Overhead & Profit (contoh 10%) 10% 9,124.46
F Harga Satuan Pekerjaan (D+E) 100,369.06
25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 123,083.84
A Tenaga 40,025.00
L.01 0.297 OH Pekerja 90,000.00 26,730.00
L.02 0.033 OH Tukang batu 105,000.00 3,465.00
L.02 0.033 OH Tukang Kayu 105,000.00 3,465.00
L.02 0.033 OH Tukang Besi 105,000.00 3,465.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B Bahan 71,869.40
0.003 m3 Kayu Terentang 1,064,800.00 3,194.40
0.02 Kg Paku Biasa 2" - 5" 22,500.00 450.00
3.6 Kg Besi Beton Polos 14,500.00 52,200.00
0.05 Kg Kawat Beton 25,000.00 1,250.00
5.5 Kg Portland Semen 1,200.00 6,600.00
0.009 m3 Pasir Beton 325,000.00 2,925.00
0.015 m3 Kerikil 350,000.00 5,250.00
C PERALATAN
D Jumlah A + B + C 111,894.40
E Overhead & Profit (contoh 10%) 10% 11,189.44
F Harga Satuan Pekerjaan (D+E) 123,083.84
C PERALATAN 12,750
0.170 jam Sewa Alat 75,000 12,750
D Jumlah A + B + C 21,545.60
E Overhead & Profit (contoh 10%) 10% 2,154.56
F Harga Satuan Pekerjaan (D+E) 23,700.16
B Bahan 302,500.00
1 m2 Rolling Allumunium 302,500.00 302,500.00
C PERALATAN
D Jumlah A + B + C 514,500.00
E Overhead & Profit (contoh 10%) 10% 51,450.00
F Harga Satuan Pekerjaan (D+E) 565,950.00
B Bahan 163,012.03
6.177 kg Besi Strip 16,000.00 98,832.00
27.08 cm Pengelasan 2,370.02 64,180.03
C PERALATAN
D Jumlah A + B + C 516,992.03
E Overhead & Profit (contoh 10%) 10% 51,699.20
F Harga Satuan Pekerjaan (D+E) 568,691.24
A Tenaga 80,800.00
L.01 0.6 OH Pekerja 90,000.00 54,000.00
L.02 0.2 OH Tukang Batu 105,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 195,200.00
140 Buah Bata Merah 850.00 119,000.00
43.5 Kg Portland Semen (PC) 1,200.00 52,200.00
0.08 m3 Pasir Pasang (PP) 300,000.00 24,000.00
C PERALATAN
D Jumlah A + B + C 276,000.00
E Overhead & Profit (contoh 10%) 10% 27,600.00
F Harga Satuan Pekerjaan (D+E) 303,600.00
Overhead & Profit (contoh 10%)
A Tenaga 80,800.00
L.01 0.6 OH Pekerja 90,000.00 54,000.00
L.02 0.2 OH Tukang Batu 105,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 185,840.00
140 Buah Bata Merah 850.00 119,000.00
32.95 Kg Portland Semen (PC) 1,200.00 39,540.00
0.091 m3 Pasir Pasang (PP) 300,000.00 27,300.00
C PERALATAN
D Jumlah A + B + C 266,640.00
E Overhead & Profit (contoh 10%) 10% 26,664.00
F Harga Satuan Pekerjaan (D+E) 293,304.00
A Tenaga 80,800.00
L.01 0.6 OH Pekerja 90,000.00 54,000.00
L.02 0.2 OH Tukang Batu 105,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 176,240.00
140 Buah Bata Merah 850.00 119,000.00
22.2 Kg Portland Semen (PC) 1,200.00 26,640.00
0.102 m3 Pasir Pasang (PP) 300,000.00 30,600.00
C PERALATAN
D Jumlah A + B + C 257,040.00
E Overhead & Profit (contoh 10%) 10% 25,704.00
F Harga Satuan Pekerjaan (D+E) 282,744.00
A Tenaga 80,800.00
L.01 0.6 OH Pekerja 90,000.00 54,000.00
L.02 0.2 OH Tukang Batu 105,000.00 21,000.00
L.03 0.02 OH Kepala Tukang Batu 110,000.00 2,200.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 159,066.00
140 Buah Bata Merah 850.00 119,000.00
10.08 Kg Portland Semen (PC) 1,200.00 12,096.00
0.0925 m3 Pasir Pasang (PP) 300,000.00 27,750.00
0.0275 m3 Kapur Pasang (KP) 8,000.00 220.00
C PERALATAN
D Jumlah A + B + C 239,866.00
E Overhead & Profit (contoh 10%) 10% 23,986.60
F Harga Satuan Pekerjaan (D+E) 263,852.60
A Tenaga 40,400.00
L.01 0.30 OH Pekerja 90,000.00 27,000.00
L.02 0.1 OH Tukang Batu 105,000.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B Bahan 86,200.00
70 Buah Bata Merah 5 x 11 x 22 850.00 59,500.00
11.50 Kg Portland Semen 1,200.00 13,800.00
0.043 m3 Pasir Pasang 300,000.00 12,900.00
C PERALATAN
D Jumlah A + B + C 126,600.00
E Overhead & Profit (contoh 10%) 10% 12,660.00
F Harga Satuan Pekerjaan (D+E) 139,260.00
A Tenaga 40,400.00
L.01 0.30 OH Pekerja 90,000.00 27,000.00
L.02 0.1 OH Tukang Batu 105,000.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B Bahan 80,020.00
70 Buah Bata Merah 5 x 11 x 22 850.00 59,500.00
4.5 Kg Portland Semen 1,200.00 5,400.00
0.05 m3 Pasir Pasang 300,000.00 15,000.00
0.015 m3 Kapur Padam 8,000.00 120.00
C PERALATAN
D Jumlah A + B + C 120,420.00
E Overhead & Profit (contoh 10%) 10% 12,042.00
F Harga Satuan Pekerjaan (D+E) 132,462.00
A Tenaga 40,400.00
L.01 0.30 OH Pekerja 90,000.00 27,000.00
L.02 0.1 OH Tukang Batu 105,000.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B Bahan 65,044.00
70 Buah Bata Merah 5 x 11 x 22 850.00 59,500.00
0.018 m3 Semen Merah - -
0.018 m3 Pasir Pasang 300,000.00 5,400.00
0.018 m3 Kapur Padam 8,000.00 144.00
C PERALATAN
D Jumlah A + B + C 105,444.00
E Overhead & Profit (contoh 10%) 10% 10,544.40
F Harga Satuan Pekerjaan (D+E) 115,988.40
16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 395,894.40
A Tenaga 51,060.00
L.01 0.350 OH Pekerja 90,000.00 31,500.00
L.02 0.150 OH Tukang Batu 105,000.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.018 OH Mandor 120,000.00 2,160.00
17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 402,415.20
A Tenaga 51,060.00
L.01 0.350 OH Pekerja 90,000.00 31,500.00
L.02 0.150 OH Tukang Batu 105,000.00 15,750.00
L.03 0.015 OH Kepala Tukang 110,000.00 1,650.00
L.04 0.018 OH Mandor 120,000.00 2,160.00
B Bahan 314,772.00
12.500 buah Batako 4,000.00 50,000.00
24.260 kg PC 1,200.00 29,112.00
0.772 m3 Pasir Pasang 300,000.00 231,600.00
0.280 kg Besi Angkur Ø 8 mm 14,500.00 4,060.00
C PERALATAN
D Jumlah A + B + C 365,832.00
E Overhead & Profit (contoh 10%) 10% 36,583.20
F Harga Satuan Pekerjaan (D+E) 402,415.20
18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 313,211.80
A Tenaga 44,640.00
L.01 0.320 OH Pekerja 90,000.00 28,800.00
L.02 0.120 OH Tukang Batu 105,000.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.016 OH Mandor 120,000.00 1,920.00
B Bahan 240,098.00
12.500 buah Batako 3,500.00 43,750.00
22.740 kg PC 1,200.00 27,288.00
0.550 m3 Pasir Pasang 300,000.00 165,000.00
0.280 kg Besi Angkur Ø 8 mm 14,500.00 4,060.00
C PERALATAN
D Jumlah A + B + C 284,738.00
E Overhead & Profit (contoh 10%) 10% 28,473.80
F Harga Satuan Pekerjaan (D+E) 313,211.80
19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 317,779.00
A Tenaga 44,640.00
L.01 0.320 OH Pekerja 90,000.00 28,800.00
L.02 0.120 OH Tukang Batu 105,000.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.016 OH Mandor 120,000.00 1,920.00
B Bahan 244,250.00
12.500 buah Batako 3,500.00 43,750.00
18.200 kg PC 1,200.00 21,840.00
0.582 m3 Pasir Pasang 300,000.00 174,600.00
0.280 kg Besi Angkur Ø 8 mm 14,500.00 4,060.00
C PERALATAN
D Jumlah A + B + C 288,890.00
E Overhead & Profit (contoh 10%) 10% 28,889.00
F Harga Satuan Pekerjaan (D+E) 317,779.00
20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 253,318.45
A Tenaga 40,400.00
L.01 0.300 OH Pekerja 90,000.00 27,000.00
L.02 0.100 OH Tukang Batu 105,000.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 257,238.85
A Tenaga 40,400.00
L.01 0.300 OH Pekerja 90,000.00 27,000.00
L.02 0.100 OH Tukang Batu 105,000.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.015 OH Mandor 120,000.00 1,800.00
B Bahan 193,453.50
12.500 buah Batako 4,675.00 58,437.50
12.130 kg PC 1,200.00 14,556.00
0.388 m3 Pasir Pasang 300,000.00 116,400.00
0.280 kg Besi Angkur Ø 8 mm 14,500.00 4,060.00
C PERALATAN
D Jumlah A + B + C 233,853.50
E Overhead & Profit (contoh 10%) 10% 23,385.35
F Harga Satuan Pekerjaan (D+E) 257,238.85
C PERALATAN
D Jumlah A + B + C 265,231.40
E Overhead & Profit (contoh 10%) 10% 26,523.14
F Harga Satuan Pekerjaan (D+E) 291,754.54
C PERALATAN
D Jumlah A + B + C 268,093.40
E Overhead & Profit (contoh 10%) 10% 26,809.34
F Harga Satuan Pekerjaan (D+E) 294,902.74
A Tenaga 54,080.00
A Tenaga 69,415.00
L.01 0.450 OH Pekerja 90,000.00 40,500.00
L.02 0.225 OH Tukang batu 105,000.00 23,625.00
L.03 0.023 OH Kepala Tukang 110,000.00 2,530.00
L.04 0.023 OH Mandor 120,000.00 2,760.00
B Bahan 27,000.00
10 Kg Portland Semen 1,200.00 12,000.00
15 m3 Batu Traso 1,000.00 15,000.00
C PERALATAN
D Jumlah A + B + C 96,415.00
E Overhead & Profit (contoh 10%) 10% 9,641.50
F Harga Satuan Pekerjaan (D+E) 106,056.50
Tenaga 46,200.00
Tenaga 30,800.00
L.01 0.20 OH Pekerja 90,000.00 18,000.00
L.02 0.10 OH Tukang batu 105,000.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
Bahan 3,900.00
3.25 Kg Portland Semen 1,200.00 3,900.00
C PERALATAN
D Jumlah A + B + C 34,700.00
E Overhead & Profit (contoh 10%) 10% 3,470.00
F Harga Satuan Pekerjaan (D+E) 38,170.00
Tenaga 30,800.00
L.01 0.20 OH Pekerja 90,000.00 18,000.00
L.02 0.10 OH Tukang batu 105,000.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
Bahan 11,412.00
6.34 Kg Portland Semen 1,800.00 11,412.00
C PERALATAN
D Jumlah A + B + C 42,212.00
E Overhead & Profit (contoh 10%) 10% 4,221.20
F Harga Satuan Pekerjaan (D+E) 46,433.20
Tenaga 30,800.00
L.01 0.20 OH Pekerja 90,000.00 18,000.00
L.02 0.10 OH Tukang batu 105,000.00 10,500.00
L.03 0.010 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.010 OH Mandor 120,000.00 1,200.00
Bahan 5,850.00
3.25 Kg Mortar Siap Pakai 1,800.00 5,850.00
C PERALATAN
D Jumlah A + B + C 36,650.00
E Overhead & Profit (contoh 10%) 10% 3,665.00
F Harga Satuan Pekerjaan (D+E) 40,315.00
D Jumlah A + B + C 105,660.00
E Overhead & Profit (contoh 10%) 10% 10,566.00
F Harga Satuan Pekerjaan (D+E) 116,226.00
A Tenaga 19,140.00
L.01 0.090 OH Pekerja 90,000.00 8,100.00
L.02 0.090 OH Tukang Batu 105,000.00 9,450.00
L.03 0.009 OH Kepala Tukang 110,000.00 990.00
L.04 0.005 OH Mandor 120,000.00 600.00
B Bahan 49,968.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 6,600.00 34,980.00
1.2 Kg Portland Semen 1,200.00 1,488.00
0.045 m3 Pasir Pasang 300,000.00 13,500.00
C PERALATAN
D Jumlah A + B + C 69,108.00
E Overhead & Profit (contoh 10%) 10% 6,910.80
F Harga Satuan Pekerjaan (D+E) 76,018.80
C PERALATAN
D Jumlah A + B + C 169,628.00
E Overhead & Profit (contoh 10%) 10% 16,962.80
F Harga Satuan Pekerjaan (D+E) 186,590.80
HARGA
BAHAN/UPA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN H
Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 193,520.80
A Tenaga 107,800.00
L.01 0.70 OH Pekerja 90,000.00 63,000.00
L.02 0.350 OH Tukang Batu 105,000.00 36,750.00
L.03 0.035 OH Kepala Tukang 110,000.00 3,850.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B Bahan 68,128.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm - -
8.19 Kg Portland Semen 1,200.00 9,828.00
3.20 Kg Semen Warna 14,000.00 44,800.00
0.0450 m3 Pasir Pasang 300,000.00 13,500.00
C PERALATAN
D Jumlah A + B + C 175,928.00
E Overhead & Profit (contoh 10%) 10% 17,592.80
F Harga Satuan Pekerjaan (D+E) 193,520.80
C PERALATAN
D Jumlah A + B + C 146,480.50
E Overhead & Profit (contoh 10%) 10% 14,648.05
F Harga Satuan Pekerjaan (D+E) 161,128.55
A Tenaga 11,300.00
L.01 0.03 OH Pekerja 90,000.00 2,700.00
L.02 0.07 OH Tukang Kayu 105,000.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.004 OH Mandor 120,000.00 480.00
B Bahan 21,823.50
1.1 Lbr Plat Asbes 19,635.00 21,598.50
0.01 Kg Paku 22,500.00 225.00
C PERALATAN
D Jumlah A + B + C 33,123.50
E Overhead & Profit (contoh 10%) 10% 3,312.35
F Harga Satuan Pekerjaan (D+E) 36,435.85
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 113,437.50
A Tenaga 25,440.00
L.01 0.12 OH Pekerja 90,000.00 10,800.00
L.02 0.12 OH Tukang Kayu 105,000.00 12,600.00
L.03 0.012 OH Kepala Tukang 110,000.00 1,320.00
L.04 0.006 OH Mandor 120,000.00 720.00
B Bahan 77,685.00
12.0 Lbr Akustik Uk.30 x 30 cm 6,380.00 76,560.00
0.05 Kg Paku 22,500.00 1,125.00
C PERALATAN
D Jumlah A + B + C 103,125.00
E Overhead & Profit (contoh 10%) 10% 10,312.50
F Harga Satuan Pekerjaan (D+E) 113,437.50
A Tenaga 21,200.00
L.01 0.10 OH Pekerja 90,000.00 9,000.00
L.02 0.10 OH Tukang Kayu 105,000.00 10,500.00
L.03 0.01 OH Kepala Tukang 110,000.00 1,100.00
L.04 0.005 OH Mandor 120,000.00 600.00
A Tenaga 15,400.00
L.01 0.1 OH Pekerja 90,000.00 9,000.00
L.02 0.05 OH Tukang Kayu 105,000.00 5,250.00
L.03 0.005 OH Kepala Tukang 110,000.00 550.00
L.04 0.005 OH Mandor 120,000.00 600.00
B Bahan 27,275.60
0.364 Lbr Gypsum Board 70,400.00 25,625.60
0.11 Kg Paku Sekrup 15,000.00 1,650.00
C PERALATAN
D Jumlah A + B + C 42,675.60
E Overhead & Profit (contoh 10%) 10% 4,267.56
F Harga Satuan Pekerjaan (D+E) 46,943.16
A Tenaga 106,000.00
L.01 0.5 OH Pekerja 90,000.00 45,000.00
L.02 0.5 OH Tukang Kayu 105,000.00 52,500.00
L.03 0.05 OH Kepala Tukang 110,000.00 5,500.00
L.04 0.025 OH Mandor 120,000.00 3,000.00
B Bahan 103,800.00
3.6 m' Profil Allumunium "T" 3,500.00 12,600.00
0.15 kg Kawat Ø 4 mm 6,500.00 975.00
1.05 bh Ramset 21,500.00 22,575.00
1.5 lmb Akuatik 60 x 120 cm 45,100.00 67,650.00
C PERALATAN
D Jumlah A + B + C 209,800.00
E Overhead & Profit (contoh 10%) 10% 20,980.00
F Harga Satuan Pekerjaan (D+E) 230,780.00
A Tenaga 23,160.00
L.01 0.15 OH Pekerja 90,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 105,000.00 7,875.00
B Bahan 105,000.00
C PERALATAN
D Jumlah A + B + C 128,160.00
A Tenaga 23,215.00
L.01 0.15 OH Pekerja 90,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 105,000.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 880.00
L.04 0.008 OH Mandor 120,000.00 960.00
B Bahan 210,000.00
C PERALATAN
D Jumlah A + B + C 233,215.00
A Tenaga 23,215.00
L.01 0.15 OH Pekerja 90,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 105,000.00 7,875.00
L.03 0.008 OH Kepala Tukang 110,000.00 880.00
L.04 0.008 OH Mandor 120,000.00 960.00
B Bahan 97,200.00
D Jumlah A + B + C 120,415.00
A Tenaga 59,440.00
L.01 0.4 OH Pekerja 90,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 105,000.00 21,000.00
L.03 0.02 OH Kepala Tukang 110,000.00 2,200.00
B Bahan 44,500.00
D Jumlah A + B + C 103,940.00
A Tenaga 59,440.00
L.01 0.4 OH Pekerja 90,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 105,000.00 21,000.00
B Bahan 66,775.00
C PERALATAN
D Jumlah A + B + C 126,215.00
A Tenaga 59,440.00
L.01 0.4 OH Pekerja 90,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 105,000.00 21,000.00
B Bahan 59,020.00
C PERALATAN
D Jumlah A + B + C 118,460.00
B Bahan 76,125.00
0.6 Lbr Rooflight 90 x 180 125,000.00 75,000.00
C PERALATAN
D Jumlah A + B + C 97,370.00
A Tenaga 22,315.00
L.01 0.14 OH Pekerja 90,000.00 12,600.00
L.02 0.075 OH Tukang Kayu 105,000.00 7,875.00
C PERALATAN
D Jumlah A + B + C 59,925.00
A Tenaga 21,560.00
B Bahan 39,960.00
C PERALATAN
D Jumlah A + B + C 61,520.00
A Tenaga 21,560.00
L.01 0.14 OH Pekerja 90,000.00 12,600.00
L.02 0.07 OH Tukang Kayu 105,000.00 7,350.00
B Bahan 39,960.00
C PERALATAN
D Jumlah A + B + C 61,520.00
A Tenaga 21,560.00
L.01 0.14 OH Pekerja 90,000.00 12,600.00
B Bahan 46,860.00
C PERALATAN
D Jumlah A + B + C 68,420.00
E Overhead & Profit (contoh 10%) 10% 6,842.00
A Tenaga 21,560.00
L.01 0.14 OH Pekerja 90,000.00 12,600.00
L.02 0.070 OH Tukang Kayu 105,000.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 120,000.00 840.00
B Bahan 41,060.00
0.49 Lbr Asbes Gelombang 80,000.00 39,200.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 1,860.00
C PERALATAN
D Jumlah A + B + C 62,620.00
E Overhead & Profit (contoh 10%) 10% 6,262.00
F Harga Satuan Pekerjaan (D+E) 68,882.00
A Tenaga 21,560.00
L.01 0.14 OH Pekerja 90,000.00 12,600.00
L.02 0.070 OH Tukang Kayu 105,000.00 7,350.00
L.03 0.007 OH Kepala Tukang 110,000.00 770.00
L.04 0.007 OH Mandor 120,000.00 840.00
B Bahan 44,610.00
0.57 Lbr Asbes Gelombang 75,000.00 42,750.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 1,860.00
C PERALATAN
D Jumlah A + B + C 66,170.00
E Overhead & Profit (contoh 10%) 10% 6,617.00
F Harga Satuan Pekerjaan (D+E) 72,787.00
C PERALATAN
D Jumlah A + B + C 64,585.00
E Overhead & Profit (contoh 10%) 10% 6,458.50
F Harga Satuan Pekerjaan (D+E) 71,043.50
C PERALATAN
D Jumlah A + B + C 62,756.60
E Overhead & Profit (contoh 10%) 10% 6,275.66
F Harga Satuan Pekerjaan (D+E) 69,032.26
A Tenaga 310,800.00
L.01 0.700 OH Pekerja 90,000.00 63,000.00
L.02 2.100 OH Tukang Kayu 105,000.00 220,500.00
L.03 0.210 OH Kepala Tukang 110,000.00 23,100.00
L.04 0.035 OH Mandor 120,000.00 4,200.00
B Bahan 451,950.00
0.025 m3 Kayu Klas II (Kamfer), papan 14,641,000.00 366,025.00
0.030 Kg Paku Biasa 1/2" - 1" 22,500.00 675.00
0.500 Ltr Lem Kayu 23,100.00 11,550.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 73,700.00 73,700.00
C PERALATAN
D Jumlah A + B + C 762,750.00
E Overhead & Profit (contoh 10%) 10% 76,275.00
F Harga Satuan Pekerjaan (D+E) 839,025.00
A Tenaga 377,460.00
L.01 0.850 OH Pekerja 90,000.00 76,500.00
L.02 2.550 OH Tukang Kayu 105,000.00 267,750.00
L.03 0.255 OH Kepala Tukang 110,000.00 28,050.00
L.04 0.043 OH Mandor 120,000.00 5,160.00
B Bahan 476,348.00
0.025 m3 Kayu Klas II (Kamfer), papan 14,641,000.00 366,025.00
0.03 Kg Paku Biasa 1/2" - 1" 22,500.00 675.00
0.08 kg Lem Kayu 23,100.00 1,848.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 73,700.00 73,700.00
0.5 Lbr Formika 68,200.00 34,100.00
C PERALATAN
D Jumlah A + B + C 853,808.00
E Overhead & Profit (contoh 10%) 10% 85,380.80
F Harga Satuan Pekerjaan (D+E) 939,188.80
A Tenaga 266,400.00
L.01 0.6 OH Pekerja 90,000.00 54,000.00
L.02 1.8 OH Tukang Kayu 105,000.00 189,000.00
L.03 0.18 OH Kepala Tukang 110,000.00 19,800.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 297,407.50
0.007 m3 Kayu klas I (Jati), papan 41,800,000.00 292,600.00
0.1 Kg Paku Biasa 2" - 5" 22,500.00 2,250.00
0.15 Kg Paku Sekrup 3,5" 17,050.00 2,557.50
C PERALATAN
D Jumlah A + B + C 563,807.50
E Overhead & Profit (contoh 10%) 10% 56,380.75
F Harga Satuan Pekerjaan (D+E) 620,188.25
B Bahan 715.00
0.05 Kg Soda Api 14,300.00 715.00
C PERALATAN
D Jumlah A + B + C 14,575.00
E Overhead & Profit (contoh 10%) 10% 1,457.50
B Bahan 715.00
C PERALATAN
D Jumlah A + B + C 14,575.00
C PERALATAN
D Jumlah A + B + C 75,000.00
E Overhead & Profit (contoh 10%) 10% 7,500.00
F Harga Satuan Pekerjaan (D+E) 82,500.00
A Tenaga 94,110.00
L.01 0.075 OH Pekerja 90,000.00 6,750.00
L.02 0.75 OH Tukang Batu 105,000.00 78,750.00
L.03 0.075 OH Kepala Tukang 110,000.00 8,250.00
L.04 0.003 OH Mandor 120,000.00 360.00
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,672,673.41
A Tenaga 891,600.00
L.01 6.00 OH Pekerja 90,000.00 540,000.00
L.02 3.00 OH Tukang Batu 105,000.00 315,000.00
L.03 0.30 OH Kepala Tukang 110,000.00 33,000.00
L.04 0.03 OH Mandor 120,000.00 3,600.00
B Bahan 629,012.20
150.0 bh Batu Bata 850.00 127,500.00
120 Kg Portland Semen 0.11 1,200.00 144,000.00
0.3 m3 Pasir Pasang 0.0121 300,000.00 90,000.00
360 buah Porselen 11 x 11 cm 82.6446 509.76 183,512.20
6 Kg Semen Nat 14,000.00 84,000.00
C PERALATAN
D Jumlah A + B + C 1,520,612.20
E Overhead & Profit (contoh 10%) 10% 152,061.22
F Harga Satuan Pekerjaan (D+E) 1,672,673.41
C PERALATAN
D Jumlah A + B + C 54,350.00
E Overhead & Profit (contoh 10%) 10% 5,435.00
F Harga Satuan Pekerjaan (D+E) 59,785.00
28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 85,437.00
cm
A Tenaga 12,320.00
L.01 0.080 OH Pekerja 90,000.00 7,200.00
L.02 0.040 OH Tukang Batu 105,000.00 4,200.00
L.03 0.004 OH Kepala Tukang 110,000.00 440.00
L.04 0.004 OH Mandor 120,000.00 480.00
B Bahan 65,350.00
1.60 bh pipa tanah 10,000.00 16,000.00
35.00 kg Semen Portlan 1,200.00 42,000.00
0.014 m3 Pasir Pasang 300,000.00 4,200.00
0.014 m3 Pasir Urug 225,000.00 3,150.00
-