DAFTAR HARGA SEWA PERALATAN

KABUPATEN JEPARA TAHUN 2016

HARGA SEWA
NO. PERALATAN SATUAN ALAT KET.
(Rp)

1 Dump Truck 3 ton Jam 71,500

2 Dump Truck Jam 240,571

3 Truck Bak Terbuka Hari 250,000

4 Truk Tanki Air Jam 240,571


5 Motor Grader Jam 316,434

6 Wheel Loader Jam 192,500

7 Wheel Loader 1.0-1.6 M3 Jam 367,477

8 Tandem Roller 6-8 T Jam 201,556

9 3-Wheel Roller Jam 143,034

10 Asp. Sprayer Jam 41,841

11 Asp. Distributor Jam 296,191

12 Compressor Jam 153,871

13 Vibro roller 1 ton Jam 30,200

14 Water Pump Jam 20,000

15 Molen hr 250,000

Jepara, Februari 2016

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR UPAH TENAGA KERJA
KABUPATEN JEPARA TAHUN 2016

NO. JENIS BAHAN SATUAN HARGA SATUAN KET.


(Rp)
1 Pekerja Hr 65,000

2 Mandor Hr 80,000

3 Tukang listrik Hr 75,000

4 Tukang kayu Hr 75,000

5 Kep. tk. kayu Hr 80,000

6 Tukang batu Hr 75,000

7 Kep. tk. batu Hr 80,000

8 Tukang besi Hr 75,000

9 Kep. tk. besi Hr 80,000

10 T u k a n g c a t Hr 75,000

11 K e p . t k . c a t Hr 80,000

12 T u k a n g p l i t u r Hr 75,000

13 T u k a n g g a l i Hr 75,000

14 M a n d o r P i p a Hr 75,000

15 T k . P i p a Hr 65,000

16 P e k e r j a . P i p a Hr 55,000

17 T k . l e i d e n g Hr 70,000

18 Site manager Hr 75,000

19 Geologist Hr 60,000

20 Administrasi Hr 50,000

21 Logistik Hr 50,000

22 Operator pemboran Hr 50,000

23 Mekanik Hr 60,000

24 C r e w Hr 50,000

25 Pengemudi Hr 40,000

26 Buruh lokal Hr 40,000

27 P e n j a g a m a l a m Hr 40,000

Jepara, Februari 2016

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN

KABUPATEN JEPARA
Ir. ASHAR EKANTO
NIP. 19620921 199503 1 001
DAFTAR HARGA SATUAN BAHAN BANGUNAN
KABUPATEN JEPARA TAHUN 2016

HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

I. B A H A N DASAR
1 BATU KALI
Pecah 15/20 m3 149,400
Pecah 5/7 m3 191,900
Pecah 3/5 m3 191,900
2 KERIKIL Timbun/Sirtu m3 106,100
Beton/Ciping 0,5/1 m3 189,400
Beton ,1/2 m3 217,100
Beton ,2/3 m3 215,900
Abu batu m3 172,700
AGREGAT (ANALISA SARINGAN)
Agr.Base Kelas A m3 173,000
Agr.Base Kelas B m3 167,800
Lolos screen2 ukuran ( 0 - 5) m3 178,300
Lolos screen2 ukuran ( 5 - 9,5) m3 157,800
Lolos screen2 ukuran ( 9.5 - 19,0) m3 141,400
3 BATU BATA Kudus bh 760
Kalipucang/Clering bh 530
4 PASIR Urug m3 82,000
Pasang lokal m3 177,400
Beton/Muntilan m3 385,000
5 TANAH Padas m3 60,600
Liat/tanah merah m3 45,400
6 KAPUR Pasang m3 402,800
Semen Merah m3 172,500
7 PORTLAND CEMENT
Semen PC kg 1,410
Semen Putih kg 2,180
Semen warna kg 12,000

II. B A H A N PENUTUP ATAP

1 GENTENG BETON Genteng Beton Warna standard bh 6,000


Kerpus Beton Warna Standard bh 13,500
2 GENTENG TANAH LIAT
Jatiwangi kecil tak berwarna bh 3,130
Jatiwangi besar tak berwarna bh 6,000
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Genteng Pres Lokal bh 1,130


Nok kerpus Jatiwangi bh 13,500
Nok kerpus Lokal bh 5,600

3 ASBES GELOMBANG
Asbes Gelombang Besar bh 83,000
Asbes Gelombang Kecil bh 36,200
NOK Jabes nok bh 28,000
. Stel Asbes bh 30,000

4 ASBES PLAT
. 100cm X 100 cm X 4 mm bh 25,700

5 FIBRE GLASS (JABES)


Fiber Glass Plat bh 29,800
Fiber Glass Gelombang bh 51,600
6 SENG PLAT
BJLS 0,18 lebar 55 cm m' 20,300
BJLS 0,28 lebar 55 cm m' 28,000
7 SENG GELOMBANG
BJLS 0,20 panjang 180 cm lbr 40,700
III . B A H A N K A Y U
1 JATI m3 16,875,000
2 KAMPER m3 8,116,300
3 KRUING m3 6,582,500
4 MERANTI m3 4,500,000
5 SENGON/HUTAN m3 2,750,000
6 BENGKIRAI m3 8,946,200
7 KAYU KELAPA/GLUGU m3 3,464,400
8 DOLKEN
Kayu cetakan/Randu m3 945,300
Kayu bakar m3 403,500
Bambu bt 13,500
9 UKIRAN
Gebyok m2 5,500,000
Kleweran m1 1,250,000
Kleweran Ukiran + Bingkai m1 2,000,000
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm bh 3,400
20 X 20 cm bh 1,500
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

PC warna 30 X 30 cm bh 3,700
20 X 20 cm bh 1,900
Teraso 30 X 30 cm bh 3,800

2 KERAMIK 40 X 40 cm warna bh 8,300


40 X 40 cm putih bh 7,800
30 X 30 cm warna bh 4,100
30 X 30 cm putih bh 3,800
20 X 20 cm bh 2,000
20 X 25 cm bh 2,700
3 Parquet Jati m2 210,000
4 Batu Paras/alam m2 105,000
5 Batu Tempel Hitam m2 111,600
6 GRANITO 40 x 40 cm bh 32,800

60 x 60 cm bh 55,800
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

V.BAHAN CETAK
1 BUIS BETON
Ø 20 cm - 100 cm bh 56,100
Ø 30 cm - 100 cm bh 81,100
Ø 60 cm - 100 cm bh 179,100
Ø 80 cm - 100 cm bh 275,000
Ø 100 cm - 100 cm bh 383,300
U 15 cm - 100 cm bh 38,700
U 20 cm - 100 cm bh 46,200
U 30 cm - 100 cm bh 60,000

2 LUBANG ANGIN (ROSTER)


Roster Tanah Merah bh 3,800
Roster Beton bh 10,500
Roster Kayu bh 18,400

VI . B A H A N B E S I
1 BESI BETON besi beton polos/Ulir kg 8,700
besi beton prestress kg 16,000

2 BESI PLAT Besi Strip kg 20,200

3 BESI PROFIL Besi Profil kg 14,000

4 JARING - JARING BAJA


Kawat Bronjong/wiremesh kg 17,000
5 BESI SIKU L
L 50 X 50 X 5 m' 35,800
6 KAWAT - Ikat beton/bendrat kg 15,300
- Kawat Kasa m2 21,800
- Saringan pasir m2 15,000
- Kawat bronjong kg 17,300

VII . B A H A N P I P A
1 Pipa PVC AW
Pipa PVC DN 20 ( ½" ) AW m' 5,400
Pipa PVC DN 25 ( ¾" ) AW m' 6,900
Pipa PVC DN 32 ( 1" ) AW m' 8,700
Pipa PVC DN 40 ( 1½" ) AW m' 13,700
Pipa PVC DN 63 ( 2" ) AW m' 20,000
Pipa PVC DN 90 ( 3" ) AW m' 38,700
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Pipa PVC DN 110 ( 4" ) AW m' 59,100


Pipa PVC DN 160 ( 6" ) AW m' 109,900
Pipa PVC DN 200 ( 8" ) AW m' 173,700
Pipa PVC DN 250 ( 10" ) AW m' 350,000
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

VIII . B A H A N L A N G I T - L A N G I T
1 List Kayu Profil m' 3,900
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 64,300
Liat Gypsum m' 25,000
3 PLY WOOD
Teak wood
. 90 X 210 X 4 mm lbr 80,000
Tripleks
. 120 X 240 X 3 mm lbr 47,500
. 120 X 240 X 4 mm lbr 58,000
. 120 X 240 X 6 mm lbr 71,300
. 120 X 240 X 9 mm lbr 105,400
Multipleks
. 120 X 240 X 9 mm lbr 102,000
4 KalsiBoard
. 120 X 240 X 3,5 mm lbr 53,400
. 120 X 240 X 4,5 mm lbr 61,300
5 Formika ukuran pintu lbr 58,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 29,000
Dempul plamur kg 32,800
Ambril/amplas lbr 6,400
Cat dasar kg 33,500
cat kayu kg 51,700
Kuas bh 13,200
Sirlak ons 16,900
Spiritus ltr 12,000
Vernish ltr 27,900

2 TEMBOK
Kalkarium kg 6,900
Kapur sirih kg 6,600
Plamur kg 17,500
Undercoat/cat dasar kg 19,000
Cat Tembok Decolite kg 20,200
Mowilex Dalam Ruangan kg 54,500
Mowilex Luar Ruangan kg 83,600
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

3 BESI
Menie kg 30,600
Cat besi kg 57,600
Minyak cat/Afduner ltr 20,000
Residu (teer/aspal) drum 68,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 855,700
kapasitas 1100 liter. bh 1,506,400
Lem Aica Aibon kg 35,000

X.BAHAN KACA
1 POLOS 3 mm m2 71,200
5 mm m2 85,000
8 mm m3 140,000

XI . BAHAN INSTALASI LISTRIK


Stop kontak Broco bh 15,200
Saklar tunggal Broco bh 14,200
Saklar ganda Broco bh 17,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM
Biasa 2 X slag bh 77,200
Kamar mandi 1 X slag bh 46,400

2 ENGSEL DAN GERENDEL


Engsel Angin bh 19,800
Engsel Jendela bh 18,500
Engsel Pintu kuningan bh 26,100
Espagnoled - bh 32,000
Grendel biasa bh 8,900
Kait Angin bh 6,900
Door Stop bh 35,000
Door Closer bh 118,400

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,192,800
2 KLOSET JONGKOK bh 137,600
3 WASTAFEL GANTUNG BULAT bh 355,700
4 TEMPAT SABUN TANAM bh 41,200
5 URINOIR bh 367,500
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

6 BAK MANDI FIBER bh 280,000


7 BAK CUCI PIRING STAINLES bh 176,100

8 LAIN - LAIN
Kran Air bh 25,700
Seal tape bh 4,100
Floor drain bh 23,100
Water drain bh 60,000
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 5" kg 12,800
2 PAKU - sekrup kg 13,000
3 PAKU - sekrup fizzer bh 1,600
4 PAKU - sumbat / kait kg 7,500
5 MUR BAUT (kuda-kuda) kg 16,000
6 ANGKUR BAUT bh 14,000
7 LEM KAYU bh 12,800
8 Tali Ijuk kg 23,600

X V . PAVING BLOCK
1 Blok pafing tebal 6 cm lokal m2 55,300
2 Blok pafing tebal 8 cm lokal m2 75,000
3 Blok pafing warna tebal 6 cm lokal m2 51,000
4 Blok pafing warna tebal 8 cm lokal m2 57,500
5 Blok pafing blok tebal 6 cm K.225 Holand m2 85,000
Blok pafing blok tebal 6 cm K.225 Hexagonal m2 87,000
6 Blok pafing blok tebal 8 cm K.300 Holland m2 125,000
Blok pafing blok tebal 8 cm K.300 Unipave/Hexagonal m2 127,000
Blok pafing blok tebal 8 cm K.300 Grassblock m2 140,000
7 Blok pafing blok tebal 8 cm K.400 Holland m2 140,000
Blok pafing blok tebal 8 cm K.400 Unipave/Hexagonal m2 142,000
8 KANSTEEN 15/20x30x50 bh 50,000
9 BATACO bh 4,500
10 Glass blox bh 22,600
XVI. L A I N - L A I N
1 Rel Pintu dorong bh 216,200
2 Naco per Daun bh 11,500
3 Rolling door Besi m2 350,000
4 Rolling door Almunium m2 364,000
5 Awning Almunium m2 190,000
6 Profil Alumunium m' 103,200
7 Alumunium strip m' 34,300
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

8 Besi Hollow 40x40x2 m' 11,300


9 ASPAL.
Aspal Ex Pertamina kg 13,500
10 K A C A
Cermin tebal 5 mm m2 170,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 198,300


Pagar BRC 120 A2 /lb 272,500
12 LAIN-LAIN
Minyak Beton & bekisting ltr 10,000
Pintu Lipat Besi m2 434,000
Sealent tube 22,500
Soda api kg 23,200
Sabun kg 8,000
Air ltr 20
Premium ltr 7,050
Minyak Tanah/Kerosen ltr 13,500
Vynil 30x30 cm bh 6,500

XVII. INSTALASI AIR BERSIH PERDESAAN/PERKOTAAN


1 " Pipa PVC "SII, S 10
Diameter nominal 1/2" m' 3,400
Diameter nominal 3/4" m' 5,000
Diameter nominal 1" m' 8,450
Diameter nominal 1 1/2" m' 19,100
2 " Pipa PVC "SII, S 12.5
Diameter nominal 2" m' 24,350
Diameter nominal 3" m' 50,900
Diameter nominal 4" m' 73,900
3 " Pipa Galvanis " medium
Diameter nominal 1/2" m' 19,900
Diameter nominal 3/4" m' 26,000
Diameter nominal 1" m' 40,000
Diameter nominal 1 1/2" m' 60,100
Diameter nominal 2" m' 80,100
Diameter nominal 3" m' 130,200
Diameter nominal 4" m' 190,300
Diameter nominal 6" m' 310,500
4 " Pipa HDPE " SDR 171(PN10)
Diameter nominal OD 40mm m' 20,400
Diameter nominal OD 50mm m' 31,650
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Diameter nominal OD 63mm m' 50,050


Diameter nominal OD 75mm m' 69,900
Diameter nominal OD 90mm m' 101,300
5 " Stop valve "
Diameter nominal 3/4" Bh 35,100
Diameter nominal 1" Bh 58,500
Diameter nominal 1 1/2" Bh 101,600
Diameter nominal 2" Bh 171,900
6 " Gate valve "
Diameter nominal 3" Bh 445,400
Diameter nominal 4" Bh 570,400
Diameter nominal 6" Bh 1,015,100
7 " Reduser " SC/SC
Diameter nominal 160 x 110 mm Bh 164,200
Diameter nominal 110 x 90 mm Bh 76,200
Diameter nominal 63 x 50 mm Bh 26,050
Diameter nominal 50 x 40 mm Bh 10,850
Diameter nominal 40 x 25 mm Bh 8,150
Diameter nominal 25 x 20 mm Bh 3,050
8 " Tee all socket " PVC
Diameter nominal 100 x 100 mm Bh 179,100
Diameter nominal 75 x 75 mm Bh 110,800
Diameter nominal 50 x 50 mm Bh 18,050
Diameter nominal 40 x 40 mm Bh 10,500
Diameter nominal 25 x 25 mm Bh 3,850
9 " Bend all socket " PVC
Diameter nominal 75 mm RRJ Bh 36,500
Diameter nominal 50 mm RRJ Bh 27,000
Diameter nominal 40 mm Bh 5,400
Diameter nominal 25 mm Bh 3,400
Diameter nominal 20 mm Bh 2,100
10 " Bend all socket " GI
Diameter nominal 2" Bh 10,400
Diameter nominal 1 1/2" Bh 8,300
Diameter nominal 1" Bh 5,400
Diameter nominal 3/4" Bh 3,100
11 " Clamp sadle " GI
Diameter nominal 3" x 3/4" Bh 23,400
Diameter nominal 2" x 3/4" Bh 15,600
Diameter nominal 1 1/2" x 3/4" Bh 12,400
Diameter nominal 1" x 3/4" Bh 12,400
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

12 " Valve socket " PVC


Diameter nominal 50 mm Bh 23,550
Diameter nominal 40 mm Bh 13,400
Diameter nominal 25 mm Bh 8,700
Diameter nominal 20 mm Bh 8,050
13 " Flange socket " PVC
Diameter nominal 50 mm Bh 143,200
Diameter nominal 63 mm Bh 179,400
Diameter nominal 110 mm Bh 448,400
Diameter nominal 160 mm Bh 691,200
14 " Faucet socket " PVC
Diameter nominal 50 mm Bh 47,850
Diameter nominal 40 mm Bh 35,750
Diameter nominal 25 mm Bh 20,050
Diameter nominal 20 mm Bh 15,900
15 " D o f " PVC
Diameter nominal 100 mm Bh 24,300
Diameter nominal 75 mm Bh 14,200
Diameter nominal 50 mm Bh 12,250
Diameter nominal 40 mm Bh 8,050
Diameter nominal 25 mm Bh 4,050
Diameter nominal 20 mm Bh 3,050
16 " Water meter "
Diameter nominal 3" Bh 1,218,500
Diameter nominal 2" Bh 927,800
Diameter nominal 1" Bh 345,300
Diameter nominal 1/2" Bh 108,100
17 " Chek valve "
Diameter nominal 3" Bh 473,300
Diameter nominal 4" Bh 609,300
Diameter nominal 6" Bh 1,048,800
18 " Bend all flange " CI - 45'
Diameter nominal 3" Bh 89,700
Diameter nominal 4" Bh 124,100
Diameter nominal 6" Bh 199,900
19 " Air valve " CI
Diameter nominal 1" Bh 115,100
Diameter nominal 3/4" Bh 108,100
20 " Stred boox "
Diameter nominal 3" Bh 25,200
Diameter nominal 4" Bh 30,600
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

21 "Accessories"
Float Valve 2" Bh 950,000
Doble neple GI dia 3/4" Bh 1,800
Tee all socket GI dia 3/4" Bh 4,600
Valve socket GI dia 3/4" Bh 2,600
Kran stainless steel Bh 18,600
Verlop ring 1 " x 3/4" Bh 8,300
Sock GIP dia 1" Bh 3,300
Sock GIP dia 3/4" Bh 2,600
Tee faucet dia 20 mm PVC Bh 5,400
Bend faucet dia 20 mm PVC Bh 3,400
Submersible pump 5.5 KW/1 Phase Unit 29,508,000
Submersible pump 11 KW/3 Phase Unit 53,655,900
Panel submersible pump 5.5 KW Unit 2,864,600
Panel submersible pump 11 KW Unit 4,688,400
Submersible pump 2.2 KW/1 Phase Unit 22,325,600
Panel submersible pump 2.2 KW Unit 2,232,600
Bend all sock GIP diameter 3" Bh 21,400
Tee all sock GIP diameter 3" Bh 17,900
Pasang tangga bahan pipa GIP dn 1" Bh 198,500
Tutup man hole & tutup pengaman lengkap 3 mm Unit 297,700
Speed Kran DN 20 mm Bh 18,600
Gate Valev DN 50 mm Bh 168,700
Flends diameter 150 mm Bh 99,200
Pelurus / Centering tiap 30 mm set 36,000
Reduser DN 100 x 150 mm set 509,300
Filter Grevel m3 180,000
Grouting m 480,300
Tangki fiberglas kapasitas 1 m3 m' 3,959,100
Tangki fiberglas kapasitas 2 m3 m' 4,688,400
22 "Pembuatan Sumur Produksi"
Solar ltr 5,900
Olie ltr 35,300
Bentonite kg 11,400
Veet/grease kg 33,100
Gravel pack m3 173,900
Kawat las btg 900
Pipa jambang diameter 8" ( GI) m' 578,400
Pipa jambang diameter 6" (GI) m' 323,200
Pipa buta diamter 6" ( GI ) m' 310,000
Pipa buta diamter 4" (GI ) m' 283,500
HARGA
BAHAN
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)

Pipa saringan stainless steel diameter 6" m' 1,719,900


Pipa saringan stainless steel diameter 4" m' 1,181,300

Jepara, Februari 2016

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR HARGA SATUAN PEKERJAAN KONSTRUKSI
KABUPATEN JEPARA
TAHUN ANGGARAN 2016
(Ket : Harga belum termasuk PPN 10%)

HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)

I HARGA SATUAN PEKERJAAN PERSIAPAN A. 2.2.1


1 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m m' A.2.2.1.2 373,326.86
2 Pengukuran dan Pemasangan Bouwplank m' A.2.2.1.4 61,957.24
3 Membersihkan Lapangan dan Perataan m2 A.2.2.1.9 11,812.50
4 Bongkaran Beton Bertulang m3 A.2.2.1.13 1,034,988.75
5 Bongkaran Dinding Tembok Bata Merah m3 A.2.2.1.14 517,494.38
6 Bongkaran 1 m3 Pasangan Batu m3 A.2.2.1.17 151,931.25
7 Pembuatan Steger/Perancah dari Bambu m2 A.2.2.1.18 112,753.13
tebas tebang berupa memotong dan membersihkan lokasi dari tanaman diameter < 15cm
8 m2 A.2.2.1.19 6,311.25

II HARGA SATUAN PEKERJAAN TANAH A.2.3.1


1 Menggali Tanah Biasa Sedalam 1 m m3 A.2.3.1.1 57,093.75
2 Menggali Tanah Biasa Sedalam 2 m m3 A.2.3.1.2 69,862.50
3 Menggali Tanah Biasa Sedalam 3 m m3 A.2.3.1.3 82,811.25
4 Menggali Tanah Keras Sedalam 1 m m3 A.2.3.1.4 76,005.00
5 Menggali Tanah Cadas Sedalam 1 m m3 A.2.3.1.5 115,087.50
6 Menggali Tanah Lumpur Sedalam 1 m m3 A.2.3.1.6 91,800.00
7 Mengerjakan Striping Tebing Setinggi 1 m m2 A.2.3.1.7 4,106.25
8 MembuangTanah sejauh 30 m' m3 A.2.3.1.8 25,031.25
9 Pengurugan Kembali m3 A.2.3.1.9 13,687.50
10 Pemadatan Tanah (per 20 cm) m3 A.2.3.1.10 41,062.50
11 Urugan Pasir hurug m3 A.2.3.1.11 133,537.50
12 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan m2 A.2.3.1.13 171,618.75
13 Mengurug Sirtu Padat m3 A.2.3.1.14 163,766.25
14 Urugan tanah biasa dan dipadatkan m3 A.2.3.1.15 96,473.36
15 Urugan tanah biasa dan dipadatkan dengan buruh m3 A.2.3.1.16 69,800.63
16 Urugan tanah padas dan dipadatkan m3 A.2.3.1.17 116,993.36
17 Urugan tanah padas dan dipadatkan dengan buruh m3 A.2.3.1.18 90,320.63
18 Pemasangan trucuk bambu Ø 10 cm panjang 6 m (SNI) ttk A.2.3.1.19 26,470.27

III HARGA SATUAN PEKERJAAN PONDASI A.3.2.1.


1 Pemasangan Pondasi Batu Belah 1SP : 3 PP lokal m3 A.3.2.1.1 805,375.13
2 Pemasangan Pondasi Batu Belah 1SP : 3 PP muntilan m3 A.3.2.1.1.1 918,646.88
3 Pemasangan Pondasi Batu Belah 1SP : 4 PP lokal m3 A.3.2.1.2 750,496.50
4 Pemasangan Pondasi Batu Belah 1SP : 4 PP muntilan m3 A.3.2.1.2.1 871,942.50
5 Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal m3 A.3.2.1.3 712,457.55
6 Pemasangan Pondasi Batu Belah 1SP : 5 PP muntilan m3 A.3.2.1.3.1 839,508.75
7 Pemasangan Pondasi Batu Belah 1SP : 6 PP lokal m3 A.3.2.1.4 685,711.58
8 Pemasangan Pondasi Batu Belah 1SP : 6 PP muntilan m3 A.3.2.1.4.1 816,733.13
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
9 Pemasangan Pondasi Batu Belah 1SP : 8 PP lokal m3 A.3.2.1.5 649,059.30
10 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan m3 A.3.2.1.5.1 785,452.50
11 Pemasang Batu Kosong/Anstamping m3 A.3.2.1.9 338,505.75
12 Pasang Pondasi Sumuran diameter 100 cm m3 A.3.2.1.11 850,355.10
13 Pasang Pondasi Rolag Trashraam Bata Merah 1 Pc : 3 Ps (SNI) m3 A.3.2.1.12 1,177,886.25
14 Pasang suling-suling m' A.3.2.1.13 9,168.75
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
IV HARGA SATUAN PEKERJAAN PASANGAN DINDING A.4.4.1
Dinding dengan bata merah kudus
1 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.2 276,631.31
2 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.3 267,345.56
3 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.4 264,343.50
4 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.5 267,136.88
5 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.8 132,594.41
6 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.9 129,341.25
7 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.10 127,320.53
8 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.11 126,895.73
9 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 8PP Muntilan m2 A.4.4.1.12 124,441.88
10 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP Muntilan m2 A.4.4.1.23 193,483.13
11 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.2.1 255,378.26
12 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.3.1 245,625.41
13 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.4.1 240,521.40
14 Pemasangan Dinding Bata Merah Kudus Tebal 1 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.5.1 238,643.78
15 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.8.1 123,252.41
16 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.9.1 119,298.60
17 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.10.1 116,810.78
18 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.11.1 115,451.78
19 Pemasangan Dinding Bata Merah Kudus Tebal 1/2 Bata Camp. 1SP : 8PP Lokal m2 A.4.4.1.12.1 112,764.38
20 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP Lokal m2 A.4.4.1.23.1 185,308.88
Dinding dengan bata merah Kalipucang
21 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.2.2 246,368.81
22 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.3.2 237,083.06
23 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.4.2 247,072.00
24 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.5.2 236,874.38
25 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP Muntilan m2 A.4.4.1.8.2 117,463.16
26 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP Muntilan m2 A.4.4.1.9.2 114,210.00
27 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP Muntilan m2 A.4.4.1.10.2 112,189.28
28 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP Muntilan m2 A.4.4.1.11.2 111,764.48
29 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP Muntilan m2 A.4.4.1.12.2 109,310.63
30 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.3.3 225,115.76
31 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.3.3 215,362.91
32 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.4.3 225,896.80
33 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.5.3 208,381.28
34 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP Lokal m2 A.4.4.1.8.3 108,121.16
35 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP Lokal m2 A.4.4.1.9.3 104,167.35
36 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP Lokal m2 A.4.4.1.10.3 101,679.53
37 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP Lokal m2 A.4.4.1.11.3 100,320.53
38 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP Lokal m2 A.4.4.1.12.3 97,633.13

V HARGA SATUAN PEKERJAAN PLESTERAN A.4.4.2


1 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.3 59,590.31
2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.3.1 54,218.66
3 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.4 57,586.95
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.4.1 51,981.75
5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.5 56,778.12
6 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.5.1 50,705.82
7 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.6 55,993.01
8 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.6.1 49,687.16
9 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.7 55,664.73
10 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.7.1 49,125.33
11 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.8 55,336.46
12 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.8.1 48,563.51
13 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm Pasir Muntilan m2 A.4.4.2.19 38,221.25
14 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm Pasir Lokal m2 A.4.4.2.19.1 32,148.95
15 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm Pasir Muntilan m' A.4.4.2.20 49,983.75
16 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm Pasir Lokal m' A.4.4.2.20.1 46,947.60
17 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Muntilan m2 A.4.4.2.23 42,076.35
18 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Lokal m2 A.4.4.2.23.1 40,675.05
19 Pemasangan Finishing Siar Pasangan Dinding Bata Merah m2 A.4.4.2.24 23,666.94
20 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp Muntilan m2 A.4.4.2.26 52,548.08
21 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp Lokal m2 A.4.4.2.26.1 49,745.48
22 Pemasangan Acian m2 A.4.4.2.27 30,017.81

VI HARGA SATUAN PEKERJAAN K A Y U A.4.6.1


1 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu bengkirai m3 A.4.6.1.1 13,607,572.50
2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu Kamfer m3 A.4.6.1.2 13,135,905.00
3 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Jati m2 A.4.6.1.5 1,117,845.00
4 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Kamfer m2 A.4.6.1.5.1 723,703.50
5 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati m2 A.4.6.1.6 746,145.00
6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer m2 A.4.6.1.6.1 509,660.10
7 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Kamfer m2 A.4.6.1.8 576,327.94
8 Pembuatan&Pemasangan 1 m2 Pintu Plywood rangkap, rangka expose kayu Kamfer m2 A.4.6.1.9 617,581.44
9 Pembuatan & Pemasangan 1 m2 Jalusi mati Kosen Kayu Bengkirai m2 A.4.6.1.10 871,922.25
10 Pembuatan & Pemasangan 1 m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Bengkirai m2 A.4.6.1.11 632,563.88
11 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu kamfer m2 A.4.6.1.12 656,612.44
12 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu bengkirai m3 A.4.6.1.13 12,923,437.50
13 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing m3 A.4.6.1.13.1 9,998,358.75
14 Pemasangan 1 m3 konstruksi Gording, Kayu bengkirai m3 A.4.6.1.15 13,851,922.50
15 Pemasangan konstruksi 1 m3 Gording, Kayu Kruing m3 A.4.6.1.15.1 10,926,843.75
16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu bengkirai m2 A.4.6.1.16 197,834.76
17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu bengkirai m2 A.4.6.1.17 234,066.87
18 Pemasangan 1 m2 Rangka Langit-langit (50x1,00) m, kayu Kruing m2 A.4.6.1.19 162,653.06
19 Pemasangan 1 m2 Rangka Langit-langit (60x60) cm, kayu Kruing m2 A.4.6.1.20 167,844.09
20 Pemasangan 1 m' Listplank Uk. (3x20)cm Kayu Bengkirai m' A.4.6.1.21 136,573.83
21 Pemasangan 1 m' Listplank Uk. (3x30)cm Kayu Bengkirai m' A.4.6.1.22 137,866.73
22 Pemasangan 1 m2 Rangka Dinding Pemisah (60x120) cm Kayu Kruing m2 A.4.6.1.23 263,216.25
23 Pemasangan 1 m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Kruing m2 A.4.6.1.24 348,680.25
24 Pemasangan 1 m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kruing m2 A.4.6.1.25 353,360.25
25 Pemasangan 1 m2 Dinding Lambriziring dari Papan Kayu Jati m2 A.4.6.1.26 351,174.38
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
26 Pasang Kasau & Reng Kayu Bengkirai (SNI) m2 A.4.6.1.29 140,033.70
27 Pasang Kasau & Reng Kayu Kruing (SNI) m2 A.4.6.1.30 108,123.75
28 Pasang Papan sirip (SNI) m' A.4.6.1.31 58,896.56

VII HARGA SATUAN PEKERJAAN BETON A.4.1.1


1 Membuat Beton mutu f'c=7,4 Mpa (K100) m3 A.4.1.1.1 999,074.25
2 Membuat Beton mutu f'c=9,8 Mpa (K125) m3 A.4.1.1.2 1,034,730.04
3 Membuat Beton mutu f'c=12,2 Mpa (K150) m3 A.4.1.1.3 1,063,141.50
4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K100) m3 A.4.1.1.4 942,208.79
5 Membuat Beton mutu f'c=14,5 MPa (K175) m3 A.4.1.1.5 1,096,063.63
6 Membuat Beton mutu f'c=16,9 MPa (K200) m3 A.4.1.1.6 1,128,694.08
7 Membuat Beton mutu f'c=19,3 MPa (K225) m3 A.4.1.1.7 1,151,502.13
8 Membuat Beton mutu f'c=21,7 MPa (K250) m3 A.4.1.1.8 1,168,827.79
9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275) m3 A.4.1.1.9 1,198,911.38
10 Membuat Beton mutu f'c=26,4 MPa (K300) m3 A.4.1.1.10 1,208,187.42
11 Pembesian dg Besi Polos atau Besi Ulir 1 kg A.4.1.1.17 11,736.56
12 Jaring Kawat baja/Wire Mesh 1 kg A.4.1.1.19 20,014.31
13 Memasang Bekisting untuk Pondasi m2 A.4.1.1.20 111,501.00
14 Memasang Bekisting untuk Sloof m2 A.4.1.1.21 116,818.31
15 Memasang Bekisting untuk Kolom m2 A.4.1.1.22 216,834.19
16 Memasang Bekisting untuk Balok m2 A.4.1.1.23 220,024.58
17 Memasang Bekisting untuk Lantai m2 A.4.1.1.24 260,259.19
18 Memasang Bekisting untuk Tangga m2 A.4.1.1.26 188,874.56
19 Membuat Kolom Penguat Beton Bertulang/kolom praktis (11 x 11) cm m' A.4.1.1.35 63,112.73
20 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' A.4.1.1.36 88,161.08
21 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm m2 A.4.1.1.37 91,368.68

VIII HARGA SATUAN PEKERJAAN PENUTUP ATAP A.4.5.2


1 Pemasangan Atap Genteng Jatiwangi Kecil m2 A.4.5.2.1 106,723.13
2 Pemasangan Atap Genteng Kodok / lokal m2 A.4.5.2.2 50,518.13
3 Pemasangan Atap Genteng Jatiwangi Super / Besar m2 A.4.5.2.3 140,236.88
4 Pemasangan Genteng Bubung jatiwangi kecil m' A.4.5.2.4 143,118.90
5 Pemasangan Genteng Bubung Kodok / lokal m' A.4.5.2.5 98,681.40
6 Pemasangan Genteng Bubung Jatiwangi Besar m' A.4.5.2.6 127,931.40
7 Pemasangan Atap Asbes Gelombang Besar m2 A.4.5.2.9 75,043.13
8 Pemasangan Atap Asbes Gelombang Kecil m2 A.4.5.2.12 32,670.00
9 Pemasangan 1 m’ bubung Asbes m' A.4.5.2.22 59,169.38
10 Pemasangan Atap Genteng Beton m2 A.4.5.2.30 99,544.50
11 Pemasangan Nok Genteng Beton m' A.4.5.2.34 140,619.15
12 Pemasangan Atap Seng Gelombang m2 A.4.5.2.38 47,137.50
13 Pemasangan Atap Nok Seng m' A.4.5.2.39 32,357.25

IX HARGA SATUAN PEKERJAAN LANGIT-LANGIT A.4.5.1


1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm m2 A.4.5.1.1 41,037.75
2 Memasang Langit-langit Tripleks Uk (120x240) cm, m2 A.4.5.1.5 42,000.75
3 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm m2 A.4.5.1.6 421,709.63
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
4 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm m2 A.4.5.1.7 40,370.85
5 Memasang Langit-langit Kalsiboard, Uk (120x240) tebal 3,5 mm m2 A.4.5.1.8 34,855.43
6 List Langit-Langit Kayu Profil m1 A.4.5.1.10 13,345.88

X HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG A.5.1.1


1 Memasang Closet Duduk / Mono Blok Unit A.5.1.1.1 1,771,839.00
2 Memasang Closet Jongkok Porselen Unit A.5.1.1.2 393,900.75
3 Memasang Urinoir Unit A.5.1.1.4 719,982.00
4 Memasang Wastafel Unit A.5.1.1.5 578,579.63
5 Pemasangan Bak Fibreglass vol.1 m3 Unit A.5.1.1.7 1,037,362.50
6 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit A.5.1.1.8 1,430,797.50
7 Pemasangan Bak Cuci Piring Stainless stell buah A.5.1.1.12 297,168.75
8 Pemasangan Floor Drain buah A.5.1.1.14 36,506.25
9 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm bh A.5.1.1.15 402,784.88
10 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm bh A.5.1.1.16 610,683.75
11 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm bh A.5.1.1.17 763,640.21
12 Pemasangan Pipa Galvanis Ø ½" m' A.5.1.1.18 49,483.13
13 Pemasangan Kran Ø ½" atau Ø ¾" bh A.5.1.1.19 67,559.06
14 Pemasangan Pipa Galvanis Ø ¾" m' A.5.1.1.20 60,120.00
15 Pemasangan Pipa Galvanis Ø 1" m' A.5.1.1.21 84,532.50

16 Pemasangan Pipa Galvanis Ø 1½ " m' A.5.1.1.22 129,954.38

17 Pemasangan Pipa Galvanis Ø 3" m' A.5.1.1.23 258,592.50

18 Pemasangan Pipa Galvanis Ø 4" m' A.5.1.1.24 363,391.88

19 Pemasangan Pipa PVC tipe AW Ø ½" m' A.5.1.1.25 17,831.25

20 Pemasangan Pipa PVC tipe AW Ø ¾" m' A.5.1.1.26 20,446.88

21 Pemasangan Pipa PVC tipe AW Ø 1" m' A.5.1.1.27 23,585.63

22 Pemasangan Pipa PVC tipe AW Ø 1½" m' A.5.1.1.28 36,511.88

23 Pemasangan Pipa PVC tipe AW Ø 2" m' A.5.1.1.29 47,497.50

24 Pemasangan Pipa PVC tipe AW Ø 3" m' A.5.1.1.31 86,371.88

25 Pemasangan Pipa PVC tipe AW Ø 4" m' A.5.1.1.32 121,944.38

26 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' A.5.1.1.33 382,209.30

27 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' A.5.1.1.34 219,674.48

28 Pemasangan Pipa Beton Ø 20 cm m' A.5.1.1.35 123,749.55

29 Pemasangan Pipa Beton Ø 100 cm m' A.5.1.1.36 434,803.95

XI HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM A.4.2.1


1 Pemasangan Besi Profil Kg A.4.2.1.1 30,438.00
2 Pemasangan Rangka Kuda-kuda Baja IWF kg A.4.2.1.2 28,372.50
3 Pemasangan Pintu Rolling Door Besi m2 A.4.2.1.7 594,090.00
4 Pemasangan Pintu Lipat (Folding Door) m2 A.4.2.1.8 563,490.00
5 Pemasangan Rolling Door Allumunium m2 A.4.2.1.10 580,500.00
6 Pemasangan Kusen Pintu Allumunium m' A.4.2.1.11 140,177.25
7 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 A.4.2.1.12 1,088,748.00
8 Pemasangan Pintu Kaca Rangka Allumunium m2 A.4.2.1.13 962,634.38
9 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m' A.4.2.1.18 153,772.88
10 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m' A.4.2.1.19 75,187.13
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
11 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon m2 A.4.2.1.21 113,923.13

XII HARGA SATUAN PEKERJAAN KUNCI dan KACA A.4.6.2


1 Pemasangan Kunci Tanam Biasa Buah A.4.6.2.2 134,718.75
2 Pemasangan Kunci Kamar Mandi Buah A.4.6.2.3 99,478.13
3 Pemasangan Kunci Selinder Buah A.4.6.2.4 134,128.13
4 Pemasangan Engsel Pintu Buah A.4.6.2.5 44,537.63
5 Pemasangan Engsel Jendela Kupu-kupu Buah A.4.6.2.6 30,926.25
6 Pemasangan Engsel Angin Buah A.4.6.2.7 48,307.50
7 Pemasangan Kait Angin Buah A.4.6.2.9 23,585.63
8 Pasang Door Closer Buah A.4.6.2.10 183,768.75
9 Pemasangan Kunci Selot Buah A.4.6.2.11 30,240.00
10 Pemasangan Door Stop Buah A.4.6.2.13 49,488.75
11 Pemasangan Rel Pintu Dorong Buah A.4.6.2.14 303,907.50
12 Pemasangan Kaca tebal 3 mm m2 A.4.6.2.16 103,280.63
13 Pemasangan Kaca tebal 5 mm m2 A.4.6.2.17 120,358.13
14 Pemasangan Kaca Cermin tebal 5 mm m2 A.4.6.2.18 225,545.63

XIII HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING A.4.4.3


1 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 A.4.4.3.2 101,414.25
2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 A.4.4.3.3 103,851.00
3 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 A.4.4.3.5 126,823.50
4 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 A.4.4.3.6 137,646.00
5 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 A.4.4.3.9 317,891.25
6 Pemasangan Lantai Keramik 30 x 30 cm warna m2 A.4.4.3.35 186,862.50
7 Pemasangan Lantai Keramik 30 x 30 cm putih m2 A.4.4.3.35.1 182,856.38
8 Pemasangan Lantai Keramik 40 x 40 cm warna m2 A.4.4.3.35.2 191,002.50
9 Pemasangan Lantai Keramik 40 x 40 cm putih m2 A.4.4.3.35.3 187,273.13
10 Pemasangan Lantai Keramik 20 x 20 cm m2 A.4.4.3.36 193,991.63
11 Pemasangan Lantai Parquet Jati m2 A.4.4.3.46 358,706.25
12 Pemasangan Dinding Keramik 10x20 cm, m2 A.4.4.3.53 226,975.73
13 Pemasangan Dinding Keramik 20x20 cm, m2 A.4.4.3.54 216,040.73
14 Pemasangan Dinding Keramik 20x25 cm, m2 A.4.4.3.55 217,165.73
15 Pemasangan Dinding Batu Paras / Batu Tempel Hitam m2 A.4.4.3.58 242,579.81
16 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' A.4.4.3.63 43,467.19
14 Pasang blok pafing tebal 6 cm K.125 (SNI) m2 A.4.4.3.64 117,196.88
15 Blok paving tebal 6 cm dengan paving mutu K 225 (SNI) m2 A.4.4.3.65 150,609.38
16 Blok paving tebal 8 cm dengan paving mutu K 300 (SNI) m2 A.4.4.3.66 195,609.38
17 Blok paving tebal 8 cm dengan paving mutu K 400 (SNI) m2 A.4.4.3.67 212,484.38
18 Blok paving warna tebal 6 cm K.125 (SNI) m2 A.4.4.3.68 112,359.38
19 Blok paving warna tebal 8 cm K.125 (SNI) m2 A.4.4.3.69 119,671.88
20 pasang saluran U-20 cm (+ Plester Aci) m' A.4.4.3.70 232,830.40
21 pasang saluran U-30 cm (+ Plester Aci) m' A.4.4.3.71 248,355.40

XIV HARGA SATUAN PEKERJAAN PENGECATAN A.4.7.1


1 Pengikisan / pengerokan Permukaan Cat Tembok Lama m2 A.4.7.1.1 12,543.75
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
2 Pencucian Bidang Permukaan Tembok yang Pernah dicat m2 A.4.7.1.2 11,688.75
3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual m2 A.4.7.1.3 12,138.75
4 Pengecatan Bidang Kayu Baru 2x cat m2 A.4.7.1.4 42,540.75
5 Pengecatan Bidang Kayu Baru 3x cat m2 A.4.7.1.5 55,695.38
6 Pelaburan Bidang Kayu dg Teak Oil m2 A.4.7.1.6 31,190.63
7 Pelaburan Bidang Kayu dg Politur m2 A.4.7.1.7 31,971.38
8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 A.4.7.1.8 9,191.25
9 Pelaburan Bidang Kayu dg Vernis m2 A.4.7.1.9 34,183.13
10 Pengecat Tembok Baru dengan Decolite m2 A.4.7.1.10 17,629.88
11 Pengecat Tembok Baru dengan Mowilex dalam ruangan m2 A.4.7.1.10.1 27,662.63
12 Pengecat Tembok Baru dengan Mowilex luar ruangan m2 A.4.7.1.10.2 36,174.38
13 Pengecatan Tembok Lama dengan Decolite m2 A.4.7.1.11 12,894.75
14 Pengecatan Tembok Lama dengan Mowilex dalam ruangan m2 A.4.7.1.11.1 19,840.50
15 Pengecatan Tembok Lama dengan Mowilex luar ruangan m2 A.4.7.1.11.2 25,733.25
16 Pengecatan Permukaan Baja dg Meni Besi m2 A.4.7.1.16 24,198.75
17 Pengecatan 1 m2 permukaan Besi 3x (SNI) m2 A.4.7.1.22 35,669.25
18 Pengecatan 1 m2 permukaan Trotoir 3x (SNI) m2 A.4.7.1.23 33,087.38

XV HARGA SATUAN PEKERJAAN PEMASANGAN PIPA A.8.4.1


1 Pemasangan 1 m pipa PVC Ø 50 mm (2") m' A.8.4.1.1 36,078.75
2 Pemasangan 1 m pipa PVC Ø 25 mm (1") m' A.8.4.1.1.1 16,683.94
3 Pemasangan 1 m pipa PVC Ø 40 mm (1½") m' A.8.4.1.1.2 29,382.95
4 Pemasangan 1 m pipa PVC Ø 75 mm (3") m' A.8.4.1.2 67,275.00
5 Pemasangan 1 m pipa PVC Ø 90 mm (4") m' A.8.4.1.3 94,438.13
6 Pemasangan 1 m pipa HDPE OD 63 mm m' A.8.4.1.17 59,968.13
7 Pemasangan 1 m pipa HDPE OD 75 mm m' A.8.4.1.17.1 82,665.56
8 Pemasangan 1 m pipa HDPE OD 90 mm m' A.8.4.1.17.2 118,237.50
9 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan) m' A.8.4.1.80 23,524.31
10 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan) m' A.8.4.1.81 38,579.08
11 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan) m' A.8.4.1.82 47,630.63
12 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan) m' A.8.4.1.83 81,069.19
13 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan) m' A.8.4.1.84 121,742.91
14 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan) m' A.8.4.1.85 71,520.00
15 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan) m' A.8.4.1.86 96,459.75
16 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan) m' A.8.4.1.87 134,330.72
HARGA
NO. URAIAN PEKERJAAN SAT KODE SATUAN
(Rp)
XVI HARGA SATUAN PEKERJAAN PENGETESAN PIPA A.8.4.5
1 Pengetesan 1 m pipa Ø 50 mm m' A.8.4.5.1 1,089.68
2 Pengetesan 1 m pipa Ø 75 mm m' A.8.4.5.2 1,134.68
3 Pengetesan 1 m pipa Ø 100 mm m' A.8.4.5.3 1,224.68
4 Pengetesan 1 m pipa Ø 150 mm m' A.8.4.5.4 1,449.68
5 Pengetesan 1 m pipa Ø 200 mm m' A.8.4.5.5 1,742.18

XVII HARGA SATUAN PEKERJAAN PEMBUATAN SUMUR PRODUKSI A.8.4.1


1 Mobilisasi/demobilisasi driling rig dan peralatan pemboran Ls An.1 1,485,000.00
2 Pemboran pilot hole diameter 6 ", 0 -- 50 m m' An.2 203,670.00
3 Pemboran pilot hole diameter 6 ", 50 -- 100 m m' An.3 215,520.00
4 Pemboran pilot hole diameter 6 ", 100 -- 150 m m' An.4 239,660.00
5 Pekerjaan raming 0 -- 65 m m' An.5 191,740.00
6 Pekerjaan raming 65 -- 130 m m' An.6 228,060.00
7 Pekerjaan electric logging m' An.7 23,400.00
8 Pekerjaan pengadaan dan pemasangan pipa jambang diameter 8" m' An.8 608,000.00
9 Pekerjaan pengadaan dan pemasangan pipa buta diameter 6" m' An.9 349,000.00
10 Pekerjaan pengadaan dan pemasangan pipa saringan stainless steel 6" m' An.10 1,759,000.00
11 Pekerjaan pengadaan dan pemasangan pipa jambang diameter 6" (GIP) m' An.8' 353,000.00
12 Pekerjaan pengadaan dan pemasangan pipa buta diameter 4" (GIP) m' An.9' 323,000.00
13 Pekerjaan pengadaan dan pemasangan pipa saringan stainless steel 4" m' An.10' 1,220,000.00

XVIII HARGA SATUAN PEKERJAAN PERKERASAN JALAN ASPAL


1 Lapis Pondasi Agregat Kelas A m3 EI-421 341,246.41
2 Lapis Pondasi Agregat Kelas B m3 EI-422a 333,624.52
3 Lapis Pondasi Agregat Kelas S m3 EI-422c 240,257.42
4 Lapis Perekat - Aspal Cair liter EI-612a 16,151.52
5 Lapis Permukaan Penetrasi Macadam m3 EI-661 1,887,092.12
6 Penetrasi Macadam untuk Pekerjaan Minor (Petching Lapen) m3 EI-817 1,862,949.32
7 Latasir Manual dengan buruh ton EI-816a 2,507,173.00

Jepara, Februari 2016

KEPALA DINAS CIPTA KARYA TATA RUANG DAN KEBERSIHAN


KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
CONTOH RENCANA ANGGARAN BIAYA
KEGIATAN : PEMELIHARAAN PRASARANA FISIK BIDANG CIPTA KARYA
TERSEBAR DI KECAMATAN SE KABUPATEN JEPARA
PEKERJAAN : REHABILITASI RUMAH DINAS
LOKASI : KECAMATAN JEPARA
TAHUN ANGGARAN : 2016
VOLUME : 1 UNIT

HARGA SATUAN JUMLAH HARGA JUMLAH


NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
A PEKERJAAN PERSIAPAN
1 Pekerjaan Bongkaran 1 LS 2,000,000.00 2,000,000.00
2,000,000.00
B PEKERJAAN REHAB
I PEKERJAAN BETON DAN PLESTERAN
1 Pekerjaan Ringbalk 1 m' A.4.1.1.36 88,161.08 88,161.08
2 Plester Aci Dinding Tambal Sulam 1 m2 A.4.4.2.3 59,590.31 59,590.31
147,751.38
II PEKERJAAN PENUTUP ATAP DAN KAYU
1 Pasang Konstruksi Kuda-Kuda Bengkirai 1.000 m2 A.4.6.1.13 12,923,437.50 12,923,437.50
2 Pemasangan 1 m' Listplank Uk. (3x20)cm Kayu Bengkirai 1.000 m1 A.4.6.1.21 136,573.83 136,573.83
3 Pas atap genteng Jatiwangi tak berwarna kecil baru 1.000 m2 A.4.5.2.1 106,723.13 106,723.13
4 Pas krepus Jatiwangi tak berwarna 1.000 m2 A.4.5.2.4 143,118.90 143,118.90
5 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 1.000 m2 A.4.5.1.5 42,000.75 42,000.75
6 Pekerjaan Kusen Kayu Bengkirai baru (2 kusen) 1.000 m3 A.4.6.1.2 13,135,905.00 13,135,905.00
7 Pasang Jalusi mati Kosen Kayu Bengkirai 1.000 m3 A.4.6.1.10 871,922.25 871,922.25
8 Pembuatan & Pemasangan 1 m2 Pintu panil kayu kamfer 1.000 m2 A.4.6.1.5.1 723,703.50 723,703.50
9 Pas. kunci pintu 2x putar 1.000 bh A.4.6.2.2 134,718.75 134,718.75
10 Pas. engsel pintu 1.000 bh A.4.6.2.5 44,537.63 44,537.63
11 Pasang dan rehab Jendela Lama 1.000 bh Taksir 130,000.00 130,000.00
12 Pas. Engsel jendela 1.000 set A.4.6.2.6 30,926.25 30,926.25
13 Pas. Grendel jendela 1.000 bh A.4.6.2.11 30,240.00 30,240.00
14 Pas. Kait angin 1.000 bh A.4.6.2.9 23,585.63 23,585.63
15 Pasang Ukir Kleweran 1.000 bh Ls 3,000,000.00 3,000,000.00
31,477,393.11
III PEKERJAAN LANTAI
1 Pasang Lantai Keramik uk. 40x40 Warna Pola 1.000 m2 A.4.4.3.35.1 182,856.38 182,856.38
2 Pasang keramik kamar mandi 1.000 m2 A.4.4.3.54 216,040.73 216,040.73
3 Pasang Paving K 225 1.000 m2 A.4.4.3.65 150,609.38 150,609.38
4 Hurugan Pasir Bawah Paving 1.000 m3 A.2.3.1.11 133,537.50 133,537.50
5 Cor Beton Kanstin K 100 1.000 m3 A.4.1.1.1 999,074.25 999,074.25
1,682,118.23
IV PEKERJAAN PENGECATAN
1 Mengecat kayu 3 kali 1.000 m2 A.4.7.1.4 42,540.75 42,540.75
2 Mengecat Besi Tralis 1.000 m2 A.4.7.1.22 35,669.25 35,669.25
3 Mengecat tembok dg Decolit 1.000 m2 A.4.7.1.11 12,894.75 12,894.75
4 Mengecat plafon dg Decolit 1.000 m2 A.4.7.1.11 12,894.75 12,894.75
103,999.50
TOTAL 35,411,262.21
PPN 10 % 3,541,126.22
JUMLAH TOTAL 38,952,388.43
DIBULATKAN 38,950,000.00
TERBILANG
Err:511

Jepara, 2016

KEPALA DINAS CIPTA KARYA, TATA RUANG


HARGA SATUAN JUMLAH HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME ANALISA
Rp Rp Rp
DAN KEBERSIHAN KABUPATEN JEPARA

Ir. ASHAR EKANTO


NIP. 19620921 199503 1 001
DAFTAR ANALISIS HARGA SATUAN PEKERJAAN
(AHSP)
KABUPATEN JEPARA
TAHUN 2016

HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m


A TENAGA
Pekerja L.01 OH 0.2 65,000.00 13,000.00
Tukang Kayu L.02 OH 0.4 75,000.00 30,000.00
Kepala Tukang L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.02 80,000.00 1,600.00
46,200.00
B BAHAN
Bambu Btg 1.25 13,500.00 16,875.00
Portalnd Semen Kg 2.5 1,410.00 3,525.00
Seng Gelombang 3" - 5" Lbr 1.2 40,700.00 48,840.00
Pasir Beton m3 0.005 385,000.00 1,925.00
Koral Beton m3 0.009 215,900.00 1,943.10
Kayu 5/7X4m Kayu Hutan m3 0.072 2,750,000.00 198,000.00
Paku Biasa 2" - 5" Kg 0.06 12,800.00 768.00
Meni Besi Kg 0.45 30,600.00 13,770.00
285,646.10
C PERALATAN
D Jumlah A + B + C 331,846.10
E Overhead & Profit 12.5% 41,480.76
F Harga Satuan Pekerjaan (D+E) 373,326.86
Overhead & Profit
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank
A Tenaga
Pekerja L.01 OH 0.1 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.005 80,000.00 400.00
15,200.00
B Bahan
Kayu 5/7x 4m Kayu Hutan m3 0.012 2,750,000.00 33,000.00
Paku Biasa 2" - 5" Kg 0.02 12,800.00 256.00
Kayu Papan 3/20 randu m3 0.007 945,300.00 6,617.10
39,873.10
C PERALATAN
D Jumlah A + B + C 55,073.10
E Overhead & Profit 12.5% 6,884.14
F Harga Satuan Pekerjaan (D+E) 61,957.24

3 A.2.2.1.9 Membersihkan Lapangan dan Perataan


A Tenaga
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Pekerja L.01 OH 0.1 65,000.00 6,500.00
Mandor L.04 OH 0.05 80,000.00 4,000.00
10,500.00
B Bahan
C PERALATAN
D Jumlah A + B + C 10,500.00
E Overhead & Profit 12.5% 1,312.50
F Harga Satuan Pekerjaan (D+E) 11,812.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.2.2.1.13 Bongkaran Beton Bertulang


A Tenaga
Pekerja L.01 OH 13.334 65,000.00 866,710.00
Mandor L.04 OH 0.666 80,000.00 53,280.00
919,990.00
B Bahan
C PERALATAN
D Jumlah A + B + C 919,990.00
E Overhead & Profit 12.5% 114,998.75
F Harga Satuan Pekerjaan (D+E) 1,034,988.75

5 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah


A Tenaga
Pekerja L.01 OH 6.667 65,000.00 433,355.00
Mandor L.04 OH 0.333 80,000.00 26,640.00
459,995.00
B Bahan
C PERALATAN
D Jumlah A + B + C 459,995.00
E Overhead & Profit 12.5% 57,499.38
F Harga Satuan Pekerjaan (D+E) 517,494.38

6 A.2.2.1.17 Bongkaran 1 m3 Pasangan Batu


A Tenaga
AHSP-SDA Pekerja L.01 OH 1.850 65,000.00 120,250.00
Mandor L.04 OH 0.185 80,000.00 14,800.00
135,050.00
B Bahan
C PERALATAN
D Jumlah A + B + C 135,050.00
E Overhead & Profit 12.5% 16,881.25
F Harga Satuan Pekerjaan (D+E) 151,931.25

7 A.2.2.1.18 Pembuatan Steger/Perancah dari Bambu


A Tenaga
AHSP-SDA Pekerja L.01 OH 0.33 65,000.00 21,450.00
Tukang Kayu L.02 OH 0.66 75,000.00 49,500.00
Kepala Tukang L.03 OH 0.066 80,000.00 5,280.00
Mandor L.04 OH 0.0330 80,000.00 2,640.00
78,870.00
B Bahan
Bambu diameter 6 - 8 / 600 cm Btg 1.250 13,500.00 16,875.00
Paku 5 - 7 cm Kg 0.350 12,800.00 4,480.00
21,355.00
C PERALATAN
D Jumlah A + B + C 100,225.00
E Overhead & Profit 12.5% 12,528.13
F Harga Satuan Pekerjaan (D+E) 112,753.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
1m2 tebas tebang berupa memotong dan membersihkan lokasi dari tanaman/
8 A.2.2.1.19 tumbuhan diameter < 15cm

A Tenaga
AHSP-SDA Pekerja L.01 OH 0.0750 65,000.00 4,875.00
Mandor L.04 OH 0.0075 80,000.00 600.00
5,475.00
B Bahan
Minyak tanah ltr 0.010 13,500.00 135.00
135.00
C PERALATAN
D Jumlah A + B + C 5,610.00
E Overhead & Profit 12.5% 701.25
F Harga Satuan Pekerjaan (D+E) 6,311.25
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m


A TENAGA
Pekerja L.01 OH 0.7500 65,000.00 48,750.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
50,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 50,750.00
E Overhead & Profit 12.5% 6,343.75
F Harga Satuan Pekerjaan (D+E) 57,093.75
Overhead & Profit
2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m
A TENAGA
Pekerja L.01 OH 0.9000 65,000.00 58,500.00
Mandor L.04 OH 0.0450 80,000.00 3,600.00
62,100.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,100.00
E Overhead & Profit 12.5% 7,762.50
F Harga Satuan Pekerjaan (D+E) 69,862.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m


A TENAGA
Pekerja L.01 OH 1.0500 65,000.00 68,250.00
Mandor L.04 OH 0.0670 80,000.00 5,360.00
73,610.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 73,610.00
E Overhead & Profit 12.5% 9,201.25
F Harga Satuan Pekerjaan (D+E) 82,811.25

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m


A TENAGA
Pekerja L.01 OH 1.0000 65,000.00 65,000.00
Mandor L.04 OH 0.0320 80,000.00 2,560.00
67,560.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 67,560.00
E Overhead & Profit 12.5% 8,445.00
F Harga Satuan Pekerjaan (D+E) 76,005.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m


A TENAGA
Pekerja L.01 OH 1.5000 65,000.00 97,500.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Mandor L.04 OH 0.0600 80,000.00 4,800.00
102,300.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 102,300.00
E Overhead & Profit 12.5% 12,787.50
F Harga Satuan Pekerjaan (D+E) 115,087.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m
A TENAGA
Pekerja L.01 OH 1.2000 65,000.00 78,000.00
Mandor L.04 OH 0.0450 80,000.00 3,600.00
81,600.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 81,600.00
E Overhead & Profit 12.5% 10,200.00
F Harga Satuan Pekerjaan (D+E) 91,800.00

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m


A TENAGA
Pekerja L.01 OH 0.0500 65,000.00 3,250.00
Mandor L.04 OH 0.0050 80,000.00 400.00
3,650.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 3,650.00
E Overhead & Profit 12.5% 456.25
F Harga Satuan Pekerjaan (D+E) 4,106.25

8 A.2.3.1.8 MembuangTanah sejauh 30 m'


A TENAGA
Pekerja L.01 OH 0.3300 65,000.00 21,450.00
Mandor L.04 OH 0.0100 80,000.00 800.00
22,250.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 22,250.00
E Overhead & Profit 12.5% 2,781.25
F Harga Satuan Pekerjaan (D+E) 25,031.25

9 A.2.3.1.9 Pengurugan Kembali


Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian
A TENAGA
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
36,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 36,500.00
E Overhead & Profit 12.5% 4,562.50
F Harga Satuan Pekerjaan (D+E) 13,687.50

10 A.2.3.1.10 Pemadatan Tanah (per 20 cm)


A TENAGA
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
36,500.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 36,500.00
E Overhead & Profit 12.5% 4,562.50
F Harga Satuan Pekerjaan (D+E) 41,062.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
11 A.2.3.1.11 Urugan Pasir
A TENAGA
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Mandor L.04 OH 0.0100 80,000.00 800.00
20,300.00
B BAHAN
Pasir Urug m3 1.2000 82,000.00 98,400.00
98,400.00
C PERALATAN
D Jumlah A + B + C 118,700.00
E Overhead & Profit 12.5% 14,837.50
F Harga Satuan Pekerjaan (D+E) 133,537.50

12 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan


A TENAGA
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
10,950.00
B BAHAN
Ijuk kg 6.0000 23,600.00 141,600.00
141,600.00
C PERALATAN
D Jumlah A + B + C 152,550.00
E Overhead & Profit 12.5% 19,068.75
F Harga Satuan Pekerjaan (D+E) 171,618.75

13 A.2.3.1.14 Mengurug Sirtu Padat


A TENAGA
Pekerja L.01 OH 0.2500 65,000.00 16,250.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
18,250.00
B BAHAN
Sirtu m3 1.2000 106,100.00 127,320.00
127,320.00
C PERALATAN
D Jumlah A + B + C 145,570.00
E Overhead & Profit 12.5% 18,196.25
F Harga Satuan Pekerjaan (D+E) 163,766.25

14 A.2.3.1.15 Urugan tanah biasa dan dipadatkan


SNI A TENAGA
Pekerja L.01 OH 0.0714 65,000.00 4,641.00
Mandor L.04 OH 0.0178 80,000.00 1,424.00
6,065.00
B BAHAN
Tanah biasa m3 1.2000 45,400.00 54,480.00
54,480.00
C PERALATAN
whell loader jam 0.0178 192,500.00 3,426.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
dump truck jam 0.2289 71,500.00 16,366.35
motor grader jam 0.0061 316,433.95 1,930.25
vibro roller jam 0.0100 30,200.00 302.00
water tangker jam 0.0070 240,571.45 1,684.00
alat bantu ls 1.0000 1,500.00 1,500.00
25,209.10
D Jumlah A + B + C 85,754.10
E Overhead & Profit 12.5% 10,719.26
F Harga Satuan Pekerjaan (D+E) 96,473.36
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
15 A.2.3.1.16 Urugan tanah biasa dan dipadatkan dengan buruh
SNI A TENAGA
Pekerja L.01 OH 0.0714 65,000.00 4,641.00
Mandor L.04 OH 0.0178 80,000.00 1,424.00
6,065.00
B BAHAN
Tanah biasa m3 1.2000 45,400.00 54,480.00
54,480.00
C PERALATAN
alat bantu ls 1.0000 1,500.00 1,500.00
1,500.00
D Jumlah A + B + C 62,045.00
E Overhead & Profit 12.5% 7,755.63
F Harga Satuan Pekerjaan (D+E) 69,800.63

16 A.2.3.1.17 Urugan tanah padas dan dipadatkan


SNI A PERALATAN
Pekerja L.01 OH 0.0714 65,000.00 4,641.00
Mandor L.04 OH 0.0178 80,000.00 1,424.00
6,065.00
B BAHAN
Tanah padas m3 1.2000 60,600.00 72,720.00
72,720.00
C PERALATAN
whell loader jam 0.0178 192,500.00 3,426.50
dump truck jam 0.2289 71,500.00 16,366.35
motor grader jam 0.0061 316,433.95 1,930.25
vibro roller jam 0.0100 30,200.00 302.00
water tangker jam 0.0070 240,571.45 1,684.00
alat bantu ls 1.0000 1,500.00 1,500.00
25,209.10
D Jumlah A + B + C 103,994.10
E Overhead & Profit 12.5% 12,999.26
F Harga Satuan Pekerjaan (D+E) 116,993.36

17 A.2.3.1.18 Urugan tanah padas dan dipadatkan dengan buruh


SNI A PERALATAN
Pekerja L.01 OH 0.0714 65,000.00 4,641.00
Mandor L.04 OH 0.0178 80,000.00 1,424.00
6,065.00
B BAHAN
Tanah padas m3 1.2000 60,600.00 72,720.00
72,720.00
C PERALATAN
alat bantu ls 1.0000 1,500.00 1,500.00
1,500.00
D Jumlah A + B + C 80,285.00
E Overhead & Profit 12.5% 10,035.63
F Harga Satuan Pekerjaan (D+E) 90,320.63
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

18 A.2.3.1.19 Pemasangan trucuk bambu Ø 10 cm panjang 6 m


SNI A PERALATAN
Pekerja L.01 OH 0.1250 65,000.00 8,125.00
Mandor L.04 OH 0.0125 80,000.00 1,000.00
9,125.00
B BAHAN
Bambu btg 1.0000 13,500.00 13,500.00
alat pancang jam 0.1000 9,000.00 900.00
alat bantu jam 0.0165 250.00 4.13
14,404.13
C PERALATAN
D Jumlah A + B + C 23,529.13
E Overhead & Profit 12.5% 2,941.14
F Harga Satuan Pekerjaan (D+E) 26,470.27
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP Lokal
A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 202 1,410.00 284,820.00
Pasir Pasang m3 0.485 177,400.00 86,039.00
550,139.00
C PERALATAN
D Jumlah A + B + C 715,889.00
E Overhead & Profit 12.5% 89,486.13
F Harga Satuan Pekerjaan (D+E) 805,375.13

2 A.3.2.1.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP Muntilan


A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 202 1,410.00 284,820.00
Pasir muntilan m3 0.485 385,000.00 186,725.00
650,825.00
C PERALATAN
D Jumlah A + B + C 816,575.00
E Overhead & Profit 12.5% 102,071.88
F Harga Satuan Pekerjaan (D+E) 918,646.88
Overhead & Profit
3 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP lokal
A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 163 1,410.00 229,830.00
Pasir Pasang m3 0.52 177,400.00 92,248.00
501,358.00
C PERALATAN
D Jumlah A + B + C 667,108.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 83,388.50
F Harga Satuan Pekerjaan (D+E) 750,496.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.3.2.1.2.1 Pemasangan Pondasi Batu Belah 1SP : 4 PP Muntilan
A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 163 1,410.00 229,830.00
Pasir Muntilan m3 0.52 385,000.00 200,200.00
609,310.00
C PERALATAN
D Jumlah A + B + C 775,060.00
E Overhead & Profit 12.5% 96,882.50
F Harga Satuan Pekerjaan (D+E) 871,942.50

5 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP lokal


A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 136 1,410.00 191,760.00
Pasir Pasang m3 0.544 177,400.00 96,505.60
467,545.60
C PERALATAN
D Jumlah A + B + C 633,295.60
E Overhead & Profit 12.5% 79,161.95
F Harga Satuan Pekerjaan (D+E) 712,457.55

6 A.3.2.1.3.1 Pemasangan Pondasi Batu Belah 1SP : 5 PP muntilan


A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 136 1,410.00 191,760.00
Pasir muntilan m3 0.544 385,000.00 209,440.00
580,480.00
C PERALATAN
D Jumlah A + B + C 746,230.00
E Overhead & Profit 12.5% 93,278.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 839,508.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP lokal
A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 117 1,410.00 164,970.00
Pasir Pasang m3 0.561 177,400.00 99,521.40
443,771.40
C PERALATAN
D Jumlah A + B + C 609,521.40
E Overhead & Profit 12.5% 76,190.18
F Harga Satuan Pekerjaan (D+E) 685,711.58

8 A.3.2.1.4.1 Pemasangan Pondasi Batu Belah 1SP : 6 PP muntilan


A TENAGA
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B BAHAN
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 117 1,410.00 164,970.00
Pasir Muntilan m3 0.561 385,000.00 215,985.00
560,235.00
C PERALATAN
D Jumlah A + B + C 725,985.00
E Overhead & Profit 12.5% 90,748.13
F Harga Satuan Pekerjaan (D+E) 816,733.13

9 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP lokal


A Tenaga
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B Bahan
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 91 1,410.00 128,310.00
Pasir Pasang m3 0.584 177,400.00 103,601.60
411,191.60
C PERALATAN
D Jumlah A + B + C 576,941.60
E Overhead & Profit 12.5% 72,117.70
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 649,059.30
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.3.2.1.5.1 Pemasangan Pondasi Batu Belah 1SP : 8 PP muntilan
A Tenaga
Pekerja L.01 OH 1.5 65,000.00 97,500.00
Tukang Batu L.02 OH 0.750 75,000.00 56,250.00
Kepala Tukang L.03 OH 0.075 80,000.00 6,000.00
Mandor L.04 OH 0.075 80,000.00 6,000.00
165,750.00
B Bahan
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Portland Sement Kg 91 1,410.00 128,310.00
Pasir muntilan m3 0.584 385,000.00 224,840.00
532,430.00
C PERALATAN
D Jumlah A + B + C 698,180.00
E Overhead & Profit 12.5% 87,272.50
F Harga Satuan Pekerjaan (D+E) 785,452.50

11 A.3.2.1.9 Pemasang Batu Kosong/Anstamping


A Tenaga
Pekerja L.01 OH 0.78 65,000.00 50,700.00
Tukang Batu L.02 OH 0.39 75,000.00 29,250.00
Kepala Tukang L.03 OH 0.039 80,000.00 3,120.00
Mandor L.04 OH 0.039 80,000.00 3,120.00
86,190.00
B Bahan
Batu Belah 15/20 m3 1.2 149,400.00 179,280.00
Pasir Urug m3 0.432 82,000.00 35,424.00
214,704.00
C PERALATAN
D Jumlah A + B + C 300,894.00
E Overhead & Profit 12.5% 37,611.75
F Harga Satuan Pekerjaan (D+E) 338,505.75

12 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm


A Tenaga
Pekerja L.01 OH 2.40 65,000.00 156,000.00
Tukang Batu L.02 OH 0.8 75,000.00 60,000.00
Kepala Tukang L.03 OH 0.08 80,000.00 6,400.00
Mandor L.04 OH 0.119 80,000.00 9,520.00
231,920.00
B Bahan
Batu Belah 15/20 cm m3 0.45 65,000.00 29,250.00
Portland Semen Kg 194 1,410.00 273,540.00
Pasir Beton m3 0.312 385,000.00 120,120.00
Koral Beton m3 0.468 215,900.00 101,041.20
523,951.20
C PERALATAN
D Jumlah A + B + C 755,871.20
E Overhead & Profit 12.5% 94,483.90
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 850,355.10
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.3.2.1.12 Pasang Pondasi Rolag Trashraam Bata Merah 1 Pc : 3 Ps


SNI A Tenaga
Pekerja L.01 OH 4.50 65,000.00 292,500.00
Tukang Batu L.02 OH 1.5 75,000.00 112,500.00
Kepala Tukang L.03 OH 0.15 80,000.00 12,000.00
Mandor L.04 OH 0.225 80,000.00 18,000.00
435,000.00
B Bahan
bata merah m3 500.00 530.00 265,000.00
semen / PC Kg 156 1,410.00 219,960.00
pasir beton m3 0.330 385,000.00 127,050.00
612,010.00
C PERALATAN
D Jumlah A + B + C 1,047,010.00
E Overhead & Profit 12.5% 130,876.25
F Harga Satuan Pekerjaan (D+E) 1,177,886.25

14 A.3.2.1.13 Pasang suling-suling


SDA A Tenaga
Pekerja L.01 OH 0.018 65,000.00 1,170.00
Mandor L.04 OH 0.002 80,000.00 160.00
1,330.00
B Bahan
Pipa PVC 2" m' 0.341 20,000.00 6,820.00
6,820.00
C PERALATAN
D Jumlah A + B + C 8,150.00
E Overhead & Profit 12.5% 1,018.75
F Harga Satuan Pekerjaan (D+E) 9,168.75
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp
IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Muntilan m3 0.091 385,000.00 35,035.00
187,894.50
C PERALATAN
D Jumlah A + B + C 245,894.50
E Overhead & Profit 12.5% 30,736.81
F Harga Satuan Pekerjaan (D+E) 276,631.31

2 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 385,000.00 35,805.00
179,640.50
C PERALATAN
D Jumlah A + B + C 237,640.50
E Overhead & Profit 12.5% 29,705.06
F Harga Satuan Pekerjaan (D+E) 267,345.56

3 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 385,000.00 39,270.00
176,972.00
C PERALATAN
D Jumlah A + B + C 234,972.00
E Overhead & Profit 12.5% 29,371.50
F Harga Satuan Pekerjaan (D+E) 264,343.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

4 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 385,000.00 46,970.00
179,455.00
C PERALATAN
D Jumlah A + B + C 237,455.00
E Overhead & Profit 12.5% 29,681.88
F Harga Satuan Pekerjaan (D+E) 267,136.88

5 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 385,000.00 15,400.00
88,861.70
C PERALATAN
D Jumlah A + B + C 117,861.70
E Overhead & Profit 12.5% 14,732.71
F Harga Satuan Pekerjaan (D+E) 132,594.41

6 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Muntilan m3 0.043 385,000.00 16,555.00
85,970.00
C PERALATAN
D Jumlah A + B + C 114,970.00
E Overhead & Profit 12.5% 14,371.25
F Harga Satuan Pekerjaan (D+E) 129,341.25
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
7 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 385,000.00 17,325.00
84,173.80
C PERALATAN
D Jumlah A + B + C 113,173.80
E Overhead & Profit 12.5% 14,146.73
F Harga Satuan Pekerjaan (D+E) 127,320.53

8 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 385,000.00 18,865.00
83,796.20
C PERALATAN
D Jumlah A + B + C 112,796.20
E Overhead & Profit 12.5% 14,099.53
F Harga Satuan Pekerjaan (D+E) 126,895.73

9 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 385,000.00 19,250.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
81,615.00
C PERALATAN
D Jumlah A + B + C 110,615.00
E Overhead & Profit 12.5% 13,826.88
F Harga Satuan Pekerjaan (D+E) 124,441.88
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
10 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Terawang / Roster Buah 30 3,800.00 114,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Muntilan m3 0.035 385,000.00 13,475.00
142,985.00
C PERALATAN
D Jumlah A + B + C 171,985.00
E Overhead & Profit 12.5% 21,498.13
F Harga Satuan Pekerjaan (D+E) 193,483.13

11 A.4.4.1.2.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Pasang lokal m3 0.091 177,400.00 16,143.40
169,002.90
C PERALATAN
D Jumlah A + B + C 227,002.90
E Overhead & Profit 12.5% 28,375.36
F Harga Satuan Pekerjaan (D+E) 255,378.26

12 A.4.4.1.3.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang lokal m3 0.093 177,400.00 16,498.20
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
160,333.70
C PERALATAN
D Jumlah A + B + C 218,333.70
E Overhead & Profit 12.5% 27,291.71
F Harga Satuan Pekerjaan (D+E) 245,625.41
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
13 A.4.4.1.4.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang lokal m3 0.102 177,400.00 18,094.80
155,796.80
C PERALATAN
D Jumlah A + B + C 213,796.80
E Overhead & Profit 12.5% 26,724.60
F Harga Satuan Pekerjaan (D+E) 240,521.40

14 A.4.4.1.5.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 140 760.00 106,400.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Pasang lokal m3 0.122 177,400.00 21,642.80
154,127.80
C PERALATAN
D Jumlah A + B + C 212,127.80
E Overhead & Profit 12.5% 26,515.98
F Harga Satuan Pekerjaan (D+E) 238,643.78

15 A.4.4.1.8.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang lokal m3 0.04 177,400.00 7,096.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
80,557.70
C PERALATAN
D Jumlah A + B + C 109,557.70
E Overhead & Profit 12.5% 13,694.71
F Harga Satuan Pekerjaan (D+E) 123,252.41
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
16 A.4.4.1.9.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang lokal m3 0.043 177,400.00 7,628.20
77,043.20
C PERALATAN
D Jumlah A + B + C 106,043.20
E Overhead & Profit 12.5% 13,255.40
F Harga Satuan Pekerjaan (D+E) 119,298.60

17 A.4.4.1.10.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Pasang lokal m3 0.045 177,400.00 7,983.00
74,831.80
C PERALATAN
D Jumlah A + B + C 103,831.80
E Overhead & Profit 12.5% 12,978.98
F Harga Satuan Pekerjaan (D+E) 116,810.78

18 A.4.4.1.11.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang lokal m3 0.049 177,400.00 8,692.60
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
73,623.80
C PERALATAN
D Jumlah A + B + C 102,623.80
E Overhead & Profit 12.5% 12,827.98
F Harga Satuan Pekerjaan (D+E) 115,451.78
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
19 A.4.4.1.12.1 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah 5 x 11 x 22 Buah 70 760.00 53,200.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang lokal m3 0.05 177,400.00 8,870.00
71,235.00
C PERALATAN
D Jumlah A + B + C 100,235.00
E Overhead & Profit 12.5% 12,529.38
F Harga Satuan Pekerjaan (D+E) 112,764.38

20 A.4.4.1.23.1 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Terawang / Roster Buah 30 3,800.00 114,000.00
Portland Semen kg 11 1,410.00 15,510.00
Pasir Pasang lokal m3 0.035 177,400.00 6,209.00
135,719.00
C PERALATAN
D Jumlah A + B + C 164,719.00
E Overhead & Profit 12.5% 20,589.88
F Harga Satuan Pekerjaan (D+E) 185,308.88

21 A.4.4.1.2.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
Pasir Muntilan m3 0.091 385,000.00 35,035.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
160,994.50
C PERALATAN
D Jumlah A + B + C 218,994.50
E Overhead & Profit 12.5% 27,374.31
F Harga Satuan Pekerjaan (D+E) 246,368.81
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
22 A.4.4.1.3.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Muntilan m3 0.093 385,000.00 35,805.00
152,740.50
C PERALATAN
D Jumlah A + B + C 210,740.50
E Overhead & Profit 12.5% 26,342.56
F Harga Satuan Pekerjaan (D+E) 237,083.06

23 A.4.4.1.4.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Muntilan m3 0.102 385,000.00 39,270.00
150,072.00
C PERALATAN
D Jumlah A + B + C 208,072.00
E Overhead & Profit 12.5% 26,009.00
F Harga Satuan Pekerjaan (D+E) 247,072.00

24 A.4.4.1.5.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
Pasir Muntilan m3 0.122 385,000.00 46,970.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
152,555.00
C PERALATAN
D Jumlah A + B + C 210,555.00
E Overhead & Profit 12.5% 26,319.38
F Harga Satuan Pekerjaan (D+E) 236,874.38
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
25 A.4.4.1.8.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Muntilan m3 0.04 385,000.00 15,400.00
75,411.70
C PERALATAN
D Jumlah A + B + C 104,411.70
E Overhead & Profit 12.5% 13,051.46
F Harga Satuan Pekerjaan (D+E) 117,463.16

26 A.4.4.1.9.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Muntilan m3 0.043 385,000.00 16,555.00
72,520.00
C PERALATAN
D Jumlah A + B + C 101,520.00
E Overhead & Profit 12.5% 12,690.00
F Harga Satuan Pekerjaan (D+E) 114,210.00

27 A.4.4.1.10.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
Pasir Muntilan m3 0.045 385,000.00 17,325.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
70,723.80
C PERALATAN
D Jumlah A + B + C 99,723.80
E Overhead & Profit 12.5% 12,465.48
F Harga Satuan Pekerjaan (D+E) 112,189.28
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

28 A.4.4.1.11.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Muntilan m3 0.049 385,000.00 18,865.00
70,346.20
C PERALATAN
D Jumlah A + B + C 99,346.20
E Overhead & Profit 12.5% 12,418.28
F Harga Satuan Pekerjaan (D+E) 111,764.48

29 A.4.4.1.12.2 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Muntilan m3 0.05 385,000.00 19,250.00
68,165.00
C PERALATAN
D Jumlah A + B + C 97,165.00
E Overhead & Profit 12.5% 12,145.63
F Harga Satuan Pekerjaan (D+E) 109,310.63

30 A.4.4.1.2.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 32.95 1,410.00 46,459.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.091 177,400.00 16,143.40
142,102.90
C PERALATAN
D Jumlah A + B + C 200,102.90
E Overhead & Profit 12.5% 25,012.86
F Harga Satuan Pekerjaan (D+E) 225,115.76
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

31 A.4.4.1.3.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 26.55 1,410.00 37,435.50
Pasir Pasang Lokal m3 0.093 177,400.00 16,498.20
133,433.70
C PERALATAN
D Jumlah A + B + C 191,433.70
E Overhead & Profit 12.5% 23,929.21
F Harga Satuan Pekerjaan (D+E) 215,362.91

32 A.4.4.1.4.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 22.2 1,410.00 31,302.00
Pasir Pasang Lokal m3 0.102 177,400.00 18,094.80
128,896.80
C PERALATAN
D Jumlah A + B + C 186,896.80
E Overhead & Profit 12.5% 23,362.10
F Harga Satuan Pekerjaan (D+E) 225,896.80

33 A.4.4.1.5.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.6 65,000.00 39,000.00
Tukang Batu L.02 OH 0.2 75,000.00 15,000.00
Kepala Tukang Batu L.03 OH 0.02 80,000.00 1,600.00
Mandor L.04 OH 0.03 80,000.00 2,400.00
58,000.00
B Bahan
Bata Merah Buah 150 530.00 79,500.00
Portland Semen (PC) Kg 18.5 1,410.00 26,085.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.122 177,400.00 21,642.80
127,227.80
C PERALATAN
D Jumlah A + B + C 185,227.80
E Overhead & Profit 12.5% 23,153.48
F Harga Satuan Pekerjaan (D+E) 208,381.28
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

34 A.4.4.1.8.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 14.37 1,410.00 20,261.70
Pasir Pasang Lokal m3 0.04 177,400.00 7,096.00
67,107.70
C PERALATAN
D Jumlah A + B + C 96,107.70
E Overhead & Profit 12.5% 12,013.46
F Harga Satuan Pekerjaan (D+E) 108,121.16

35 A.4.4.1.9.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 11.50 1,410.00 16,215.00
Pasir Pasang Lokal m3 0.043 177,400.00 7,628.20
63,593.20
C PERALATAN
D Jumlah A + B + C 92,593.20
E Overhead & Profit 12.5% 11,574.15
F Harga Satuan Pekerjaan (D+E) 104,167.35

36 A.4.4.1.10.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 9.68 1,410.00 13,648.80
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Pasir Pasang Lokal m3 0.045 177,400.00 7,983.00
61,381.80
C PERALATAN
D Jumlah A + B + C 90,381.80
E Overhead & Profit 12.5% 11,297.73
F Harga Satuan Pekerjaan (D+E) 101,679.53
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF

37 A.4.4.1.11.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 8.32 1,410.00 11,731.20
Pasir Pasang Lokal m3 0.049 177,400.00 8,692.60
60,173.80
C PERALATAN
D Jumlah A + B + C 89,173.80
E Overhead & Profit 12.5% 11,146.73
F Harga Satuan Pekerjaan (D+E) 100,320.53

38 A.4.4.1.12.3 Pemasangan Dinding Bata Merah Kalipucang Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga
Pekerja L.01 OH 0.30 65,000.00 19,500.00
Tukang Batu L.02 OH 0.1 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.01 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
29,000.00
B Bahan
Bata Merah Buah 75 530.00 39,750.00
Portland Semen Kg 6.50 1,410.00 9,165.00
Pasir Pasang Lokal m3 0.05 177,400.00 8,870.00
57,785.00
C PERALATAN
D Jumlah A + B + C 86,785.00
E Overhead & Profit 12.5% 10,848.13
F Harga Satuan Pekerjaan (D+E) 97,633.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 7.7760 1,410.00 10,964.16
Pasir Muntilan m3 0.0230 385,000.00 8,855.00
19,819.16
C PERALATAN
D Jumlah A + B + C 52,969.16
E Overhead & Profit 12.5% 6,621.15
F Harga Satuan Pekerjaan (D+E) 59,590.31

2 A.4.4.2.3.1 Pemasangan Plesteran 1 Pc : 3 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 7.7760 1,410.00 10,964.16
Pasir lokal m3 0.0230 177,400.00 4,080.20
15,044.36
C PERALATAN
D Jumlah A + B + C 48,194.36
E Overhead & Profit 12.5% 6,024.30
F Harga Satuan Pekerjaan (D+E) 54,218.66

3 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 6.2400 1,410.00 8,798.40
Pasir Muntilan m3 0.0240 385,000.00 9,240.00
18,038.40
C PERALATAN
D Jumlah A + B + C 51,188.40
E Overhead & Profit 12.5% 6,398.55
F Harga Satuan Pekerjaan (D+E) 57,586.95

4 A.4.4.2.4.1 Pemasangan Plesteran 1 Pc : 4 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B Bahan
Portland Semen Kg 6.2400 1,410.00 8,798.40
Pasir lokal m3 0.0240 177,400.00 4,257.60
13,056.00
C PERALATAN
D Jumlah A + B + C 46,206.00
E Overhead & Profit 12.5% 5,775.75
F Harga Satuan Pekerjaan (D+E) 51,981.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir Muntilan m3 0.0260 385,000.00 10,010.00
17,319.44
C PERALATAN
D Jumlah A + B + C 50,469.44
E Overhead & Profit 12.5% 6,308.68
F Harga Satuan Pekerjaan (D+E) 56,778.12

6 A.4.4.2.5.1 Pemasangan Plesteran 1 Pc : 5 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir lokal m3 0.0260 177,400.00 4,612.40
11,921.84
C PERALATAN
D Jumlah A + B + C 45,071.84
E Overhead & Profit 12.5% 5,633.98
F Harga Satuan Pekerjaan (D+E) 50,705.82

7 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 4.4160 1,410.00 6,226.56
Pasir Muntilan m3 0.0270 385,000.00 10,395.00
16,621.56
C PERALATAN
D Jumlah A + B + C 49,771.56
E Overhead & Profit 12.5% 6,221.45
F Harga Satuan Pekerjaan (D+E) 55,993.01

8 A.4.4.2.6.1 Pemasangan Plesteran 1 Pc : 6 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 4.4160 1,410.00 6,226.56
Pasir lokal m3 0.0270 177,400.00 4,789.80
11,016.36
C PERALATAN
D Jumlah A + B + C 44,166.36
E Overhead & Profit 12.5% 5,520.80
F Harga Satuan Pekerjaan (D+E) 49,687.16
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
9 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 3.9360 1,410.00 5,549.76
Pasir Muntilan m3 0.0280 385,000.00 10,780.00
16,329.76
C PERALATAN
D Jumlah A + B + C 49,479.76
E Overhead & Profit 12.5% 6,184.97
F Harga Satuan Pekerjaan (D+E) 55,664.73

10 A.4.4.2.7.1 Pemasangan Plesteran 1 Pc : 7 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 3.9360 1,410.00 5,549.76
Pasir lokal m3 0.0280 177,400.00 4,967.20
10,516.96
C PERALATAN
D Jumlah A + B + C 43,666.96
E Overhead & Profit 12.5% 5,458.37
F Harga Satuan Pekerjaan (D+E) 49,125.33

11 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp muntilan Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Portland Semen Kg 3.4560 1,410.00 4,872.96
Pasir Muntilan m3 0.0290 385,000.00 11,165.00
16,037.96
C PERALATAN
D Jumlah A + B + C 49,187.96
E Overhead & Profit 12.5% 6,148.50
F Harga Satuan Pekerjaan (D+E) 55,336.46

12 A.4.4.2.8.1 Pemasangan Plesteran 1 Pc : 8 Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 3.4560 1,410.00 4,872.96
Pasir lokal m3 0.0290 177,400.00 5,144.60
10,017.56
C PERALATAN
D Jumlah A + B + C 43,167.56
E Overhead & Profit 12.5% 5,395.95
F Harga Satuan Pekerjaan (D+E) 48,563.51
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp muntilan Tebal 15 mm
A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang batu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,655.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir Muntilan m3 0.0260 385,000.00 10,010.00
17,319.44
C PERALATAN
D Jumlah A + B + C 33,974.44
E Overhead & Profit 12.5% 4,246.81
F Harga Satuan Pekerjaan (D+E) 38,221.25

14 A.4.4.2.19.1 Pemasangan Berapen 1 Pc : 5Pp lokal Tebal 15 mm


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang batu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,655.00
B Bahan
Portland Semen Kg 5.1840 1,410.00 7,309.44
Pasir lokal m3 0.0260 177,400.00 4,612.40
11,921.84
C PERALATAN
D Jumlah A + B + C 28,576.84
E Overhead & Profit 12.5% 3,572.11
F Harga Satuan Pekerjaan (D+E) 32,148.95

15 A.4.4.2.20 Pemasangan Plesteran Skoning 1 Pc : 2Pp muntilan


A Tenaga
Pekerja L.01 OH 0.0800 65,000.00 5,200.00
Tukang batu L.02 OH 0.4000 75,000.00 30,000.00
Kepala Tukang L.03 OH 0.0400 80,000.00 3,200.00
Mandor L.04 OH 0.0040 80,000.00 320.00
38,720.00
B Bahan
Portland Semen Kg 0.5000 1,410.00 705.00
Pasir Muntilan m3 0.0130 385,000.00 5,005.00
5,710.00
C PERALATAN
D Jumlah A + B + C 44,430.00
E Overhead & Profit 12.5% 5,553.75
F Harga Satuan Pekerjaan (D+E) 49,983.75

16 A.4.4.2.20.1 Pemasangan Plesteran Skoning 1 Pc : 2Pp lokal


A Tenaga
Pekerja L.01 OH 0.0800 65,000.00 5,200.00
Tukang batu L.02 OH 0.4000 75,000.00 30,000.00
Kepala Tukang L.03 OH 0.0400 80,000.00 3,200.00
Mandor L.04 OH 0.0040 80,000.00 320.00
38,720.00
B Bahan
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Portland Semen Kg 0.5000 1,410.00 705.00
Pasir lokal m3 0.0130 177,400.00 2,306.20
3,011.20
C PERALATAN
D Jumlah A + B + C 41,731.20
E Overhead & Profit 12.5% 5,216.40
F Harga Satuan Pekerjaan (D+E) 46,947.60
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
17 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
29,000.00
B Bahan
Portland Semen Kg 4.3200 1,410.00 6,091.20
Pasir Muntilan m3 0.0060 385,000.00 2,310.00
8,401.20
C PERALATAN
D Jumlah A + B + C 37,401.20
E Overhead & Profit 12.5% 4,675.15
F Harga Satuan Pekerjaan (D+E) 42,076.35

18 A.4.4.2.23.1 Pemasangan Plesteran Ciprat 1Pc : 2 Pp Lokal


A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
29,000.00
B Bahan
Portland Semen Kg 4.3200 1,410.00 6,091.20
Pasir Lokal m3 0.0060 177,400.00 1,064.40
7,155.60
C PERALATAN
D Jumlah A + B + C 36,155.60
E Overhead & Profit 12.5% 4,519.45
F Harga Satuan Pekerjaan (D+E) 40,675.05

19 A.4.4.2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m')
A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang batu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,655.00
B Bahan
Portland Semen Kg 3.1080 1,410.00 4,382.28
4,382.28
C PERALATAN
D Jumlah A + B + C 21,037.28
E Overhead & Profit 12.5% 2,629.66
F Harga Satuan Pekerjaan (D+E) 23,666.94

20 A.4.4.2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Muntilan
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
PP Muntilan m3 0.0120 385,000.00 4,620.00
13,559.40
C PERALATAN
D Jumlah A + B + C 46,709.40
E Overhead & Profit 12.5% 5,838.68
F Harga Satuan Pekerjaan (D+E) 52,548.08
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

21 A.4.4.2.26.1 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2PP Lokal
A Tenaga
Pekerja L.01 OH 0.3000 65,000.00 19,500.00
Tukang batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
33,150.00
B Bahan
Pc Kg 6.3400 1,410.00 8,939.40
PP Lokal m3 0.0120 177,400.00 2,128.80
11,068.20
C PERALATAN
D Jumlah A + B + C 44,218.20
E Overhead & Profit 12.5% 5,527.28
F Harga Satuan Pekerjaan (D+E) 49,745.48

22 A.4.4.2.27 Pemasangan Acian


A Tenaga
Pekerja L.01 OH 0.2000 65,000.00 13,000.00
Tukang batu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0100 80,000.00 800.00
22,100.00
B Bahan
Portland Semen Kg 3.2500 1,410.00 4,582.50
4,582.50
C PERALATAN
D Jumlah A + B + C 26,682.50
E Overhead & Profit 12.5% 3,335.31
F Harga Satuan Pekerjaan (D+E) 30,017.81
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
1 A.4.6.1.1 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu Bengkirai
A Tenaga
Pekerja L.01 OH 7.0000 65,000.00 455,000.00
Tukang Kayu L.02 OH 21.0000 75,000.00 1,575,000.00
Kepala Tukang L.03 OH 2.1000 80,000.00 168,000.00
Mandor L.04 OH 0.3500 80,000.00 28,000.00
2,226,000.00
B Bahan B
Kayu Klas I (bengkirai) m3 1.1000 8,946,200.00 9,840,820.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
9,869,620.00
C PERALATAN
D Jumlah A + B + C 12,095,620.00
E Overhead & Profit 12.5% 1,511,952.50
F Harga Satuan Pekerjaan (D+E) 13,607,572.50

2 A.4.6.1.2 Pembuatan & Pemasangan 1 m3 Kosen Pintu & Jendela Kayu kamfer
A Tenaga
Pekerja L.01 OH 6.0000 65,000.00 390,000.00
Tukang Kayu L.02 OH 18.0000 75,000.00 1,350,000.00
Kepala Tukang L.03 OH 1.8000 80,000.00 144,000.00
Mandor L.04 OH 0.3000 80,000.00 24,000.00
1,908,000.00
B Bahan
Kayu Klas II (kamfer) m3 1.2000 8,116,300.00 9,739,560.00
Paku Biasa 2" - 5 " kg 1.2500 12,800.00 16,000.00
Lem Kayu kg 1.0000 12,800.00 12,800.00
9,768,360.00
C PERALATAN
D Jumlah A + B + C 11,676,360.00
E Overhead & Profit 12.5% 1,459,545.00
F Harga Satuan Pekerjaan (D+E) 13,135,905.00

3 A.4.6.1.5 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Jati


A Tenaga
Pekerja L.01 OH 1.0000 65,000.00 65,000.00
Tukang Kayu L.02 OH 3.0000 75,000.00 225,000.00
Kepala Tukang L.03 OH 0.3000 80,000.00 24,000.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
318,000.00
B Bahan
Kayu jati m3 0.0400 16,875,000.00 675,000.00
Lem Kayu kg 0.0500 12,800.00 640.00
675,640.00
C PERALATAN
D Jumlah A + B + C 993,640.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 124,205.00
F Harga Satuan Pekerjaan (D+E) 1,117,845.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.6.1.5.1 Pembuatan & Pemasangan 1 m2 Daun Pintu Panel, Kayu Kamfer
A Tenaga
Pekerja L.01 OH 1.0000 65,000.00 65,000.00
Tukang Kayu L.02 OH 3.0000 75,000.00 225,000.00
Kepala Tukang L.03 OH 0.3000 80,000.00 24,000.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
318,000.00
B Bahan
Kayu kamfer m3 0.0400 8,116,300.00 324,652.00
Lem Kayu kg 0.0500 12,800.00 640.00
325,292.00
C PERALATAN
D Jumlah A + B + C 643,292.00
E Overhead & Profit 12.5% 80,411.50
F Harga Satuan Pekerjaan (D+E) 723,703.50

5 A.4.6.1.6 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu Jati
A Tenaga
Pekerja L.01 OH 0.8000 65,000.00 52,000.00
Tukang Kayu L.02 OH 2.4000 75,000.00 180,000.00
Kepala Tukang L.03 OH 0.2400 80,000.00 19,200.00
Mandor L.04 OH 0.0400 80,000.00 3,200.00
254,400.00
B Bahan
Kayu jati, papan m3 0.0240 16,875,000.00 405,000.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
408,840.00
C PERALATAN
D Jumlah A + B + C 663,240.00
E Overhead & Profit 12.5% 82,905.00
F Harga Satuan Pekerjaan (D+E) 746,145.00

6 A.4.6.1.6.1 Pembuatan & Pemasangan 1 m2 Pintu & Jendela Kaca Kayu kamfer
A Tenaga
Pekerja L.01 OH 0.8000 65,000.00 52,000.00
Tukang Kayu L.02 OH 2.4000 75,000.00 180,000.00
Kepala Tukang L.03 OH 0.2400 80,000.00 19,200.00
Mandor L.04 OH 0.0400 80,000.00 3,200.00
254,400.00
B Bahan
Kayu kamfer m3 0.0240 8,116,300.00 194,791.20
Lem Kayu kg 0.3000 12,800.00 3,840.00
198,631.20
C PERALATAN
D Jumlah A + B + C 453,031.20
E Overhead & Profit 12.5% 56,628.90
F Harga Satuan Pekerjaan (D+E) 509,660.10
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.6.1.8 Pembuatan&Pemasangan 1 m2 Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm)
A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Kayu L.02 OH 2.1000 75,000.00 157,500.00
Kepala Tukang L.03 OH 0.2100 80,000.00 16,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
222,600.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 80,000.00 80,000.00
289,691.50
C PERALATAN
D Jumlah A + B + C 512,291.50
E Overhead & Profit 12.5% 64,036.44
F Harga Satuan Pekerjaan (D+E) 576,327.94

8 A.4.6.1.9 Pembuatan&Pemasangan 1 m2 Pintu Plywood rangkap, rangka expose kayu klas I atau II
A Tenaga
Pekerja L.01 OH 0.8000 65,000.00 52,000.00
Tukang Kayu L.02 OH 2.4000 75,000.00 180,000.00
Kepala Tukang L.03 OH 0.2400 80,000.00 19,200.00
Mandor L.04 OH 0.0400 80,000.00 3,200.00
254,400.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0256 8,116,300.00 207,777.28
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu Ltr 0.5000 12,800.00 6,400.00
Plywood tebal 4 mm uk.90x220cm Lbr 1.0000 80,000.00 80,000.00
294,561.28
C PERALATAN
D Jumlah A + B + C 548,961.28
E Overhead & Profit 12.5% 68,620.16
F Harga Satuan Pekerjaan (D+E) 617,581.44

9 A.4.6.1.10 Pembuatan & Pemasangan 1 m2 Jalusi mati Kosen Kayu Klas I atau II
A Tenaga
Pekerja L.01 OH 0.6700 65,000.00 43,550.00
Tukang Kayu L.02 OH 2.0000 75,000.00 150,000.00
Kepala Tukang L.03 OH 0.2000 80,000.00 16,000.00
Mandor L.04 OH 0.3350 80,000.00 26,800.00
236,350.00
B Bahan
Kayu Klas I Bengkirai) m3 0.0600 8,946,200.00 536,772.00
Paku Biasa 1/2" - 1" Kg 0.1500 12,800.00 1,920.00
538,692.00
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 775,042.00
E Overhead & Profit 12.5% 96,880.25
F Harga Satuan Pekerjaan (D+E) 871,922.25
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.4.6.1.11 Pembuatan & Pemasangan 1 m2 Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I
A Tenaga
Pekerja L.01 OH 0.8000 65,000.00 52,000.00
Tukang Kayu L.02 OH 2.4000 75,000.00 180,000.00
Kepala Tukang L.03 OH 0.2400 80,000.00 19,200.00
Mandor L.04 OH 0.0400 80,000.00 3,200.00
254,400.00
B Bahan
Kayu Klas I (Bengkirai) m3 0.0250 8,946,200.00 223,655.00
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.3000 12,800.00 3,840.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 80,000.00 80,000.00
307,879.00
C PERALATAN
D Jumlah A + B + C 562,279.00
E Overhead & Profit 12.5% 70,284.88
F Harga Satuan Pekerjaan (D+E) 632,563.88

11 A.4.6.1.12 Pembuatan&Pemasangan 1 m2 Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II
A Tenaga
Pekerja L.01 OH 0.8500 65,000.00 55,250.00
Tukang Kayu L.02 OH 2.5500 75,000.00 191,250.00
Kepala Tukang L.03 OH 0.2550 80,000.00 20,400.00
Mandor L.04 OH 0.0430 80,000.00 3,440.00
270,340.00
B Bahan
Kayu Klas II (Kamfer) m3 0.0250 8,116,300.00 202,907.50
Paku Biasa 1/2" - 1" Kg 0.0300 12,800.00 384.00
Lem Kayu kg 0.0800 12,800.00 1,024.00
Teakwood (90 x 220) cm x 4 mm Lbr 1.0000 80,000.00 80,000.00
Formika Lbr 0.5000 58,000.00 29,000.00
313,315.50
C PERALATAN
D Jumlah A + B + C 583,655.50
E Overhead & Profit 12.5% 72,956.94
F Harga Satuan Pekerjaan (D+E) 656,612.44

12 A.4.6.1.13 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Bengkirai


A Tenaga
Pekerja L.01 OH 4.0000 65,000.00 260,000.00
Tukang Kayu L.02 OH 12.0000 75,000.00 900,000.00
Kepala Tukang L.03 OH 1.2000 80,000.00 96,000.00
Mandor L.04 OH 0.2000 80,000.00 16,000.00
1,272,000.00
B Bahan
Kayu Bengkirai m3 1.1000 8,946,200.00 9,840,820.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Paku Biasa 2" - 5" Kg 5.6000 12,800.00 71,680.00
10,215,500.00
C PERALATAN
D Jumlah A + B + C 11,487,500.00
E Overhead & Profit 12.5% 1,435,937.50
F Harga Satuan Pekerjaan (D+E) 12,923,437.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.4.6.1.13.1 Pembuatan&Memasang 1 m3 Konstruksi Kuda-kuda Konvensional Kayu Kruing


A Tenaga
Pekerja L.01 OH 4.0000 65,000.00 260,000.00
Tukang Kayu L.02 OH 12.0000 75,000.00 900,000.00
Kepala Tukang L.03 OH 1.2000 80,000.00 96,000.00
Mandor L.04 OH 0.2000 80,000.00 16,000.00
1,272,000.00
B Bahan
Kayu Kruing m3 1.1000 6,582,500.00 7,240,750.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 5.6000 12,800.00 71,680.00
7,615,430.00
C PERALATAN
D Jumlah A + B + C 8,887,430.00
E Overhead & Profit 12.5% 1,110,928.75
F Harga Satuan Pekerjaan (D+E) 9,998,358.75

14 A.4.6.1.15 Pemasangan konstruksi 1 m3 Gording, Kayu bengkirai


A Tenaga
Pekerja L.01 OH 6.7000 65,000.00 435,500.00
Tukang Kayu L.02 OH 20.1000 75,000.00 1,507,500.00
Kepala Tukang L.03 OH 2.0100 80,000.00 160,800.00
Mandor L.04 OH 0.3350 80,000.00 26,800.00
2,130,600.00
B Bahan
Kayu Klas I (Bengkirai) m3 1.1000 8,946,200.00 9,840,820.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 3.0000 12,800.00 38,400.00
10,182,220.00
C PERALATAN
D Jumlah A + B + C 12,312,820.00
E Overhead & Profit 12.5% 1,539,102.50
F Harga Satuan Pekerjaan (D+E) 13,851,922.50

15 A.4.6.1.15.1 Pemasangan konstruksi 1 m3 Gording, Kayu Kruing


A Tenaga
Pekerja L.01 OH 6.7000 65,000.00 435,500.00
Tukang Kayu L.02 OH 20.1000 75,000.00 1,507,500.00
Kepala Tukang L.03 OH 2.0100 80,000.00 160,800.00
Mandor L.04 OH 0.3350 80,000.00 26,800.00
2,130,600.00
B Bahan
Kayu Klas Kruing m3 1.1000 6,582,500.00 7,240,750.00
Besi Strip Kg 15.0000 20,200.00 303,000.00
Paku Biasa 2" - 5" Kg 3.0000 12,800.00 38,400.00
7,582,150.00
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 9,712,750.00
E Overhead & Profit 12.5% 1,214,093.75
F Harga Satuan Pekerjaan (D+E) 10,926,843.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.4.6.1.16 Pemasangan 1 m2 Rangka Atap Genteng Keramik, Kayu Klas II
A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0050 80,000.00 400.00
15,200.00
B Bahan
Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm m3 0.0140 8,946,200.00 125,246.80
Reng (2x3) cm bengkirai m3 0.0036 8,946,200.00 32,206.32
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
160,653.12
C PERALATAN
D Jumlah A + B + C 175,853.12
E Overhead & Profit 12.5% 21,981.64
F Harga Satuan Pekerjaan (D+E) 197,834.76

17 A.4.6.1.17 Pemasangan 1 m2 Rangka Atap Genteng Beton, Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0050 80,000.00 400.00
15,200.00
B Bahan
Kayu Klas II (Bengkirai), Kaso-kaso (5x7) cm m3 0.0140 8,946,200.00 125,246.80
Reng (2x3) cm bengkirai m3 0.0072 8,946,200.00 64,412.64
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
192,859.44
C PERALATAN
D Jumlah A + B + C 208,059.44
E Overhead & Profit 12.5% 26,007.43
F Harga Satuan Pekerjaan (D+E) 234,066.87

18 A.4.6.1.19 Pemasangan 1 m2 Rangka Langit-langit (50x1,00) m, kayu Klas II atau III


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.3000 75,000.00 22,500.00
Kepala Tukang L.03 OH 0.0300 80,000.00 2,400.00
Mandor L.04 OH 0.0750 80,000.00 6,000.00
40,650.00
B Bahan
Kayu Klas II (Kruing) m3 0.0154 6,582,500.00 101,370.50
Paku Biasa 2" - 5" Kg 0.2000 12,800.00 2,560.00
103,930.50
C PERALATAN
D Jumlah A + B + C 144,580.50
E Overhead & Profit 12.5% 18,072.56
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 162,653.06
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

19 A.4.6.1.20 Pemasangan 1 m2 Rangka Langit-langit (60x60) cm, kayu Klas II atau III
A Tenaga
Pekerja L.01 OH 0.2000 65,000.00 13,000.00
Tukang Kayu L.02 OH 0.3000 75,000.00 22,500.00
Kepala Tukang L.03 OH 0.0300 80,000.00 2,400.00
Mandor L.04 OH 0.0100 80,000.00 800.00
38,700.00
B Bahan
Kayu Klas II (Kruing) m3 0.0163 6,582,500.00 107,294.75
Paku Biasa 2" - 5" Kg 0.2500 12,800.00 3,200.00
110,494.75
C PERALATAN
D Jumlah A + B + C 149,194.75
E Overhead & Profit 12.5% 18,649.34
F Harga Satuan Pekerjaan (D+E) 167,844.09

20 A.4.6.1.21 Pemasangan 1 m' Listplank Uk. (3x20)cm Kayu klas I atau II


A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0050 80,000.00 400.00
23,500.00
B Bahan
Kayu klas I Bengkirai) m3 0.0108 8,946,200.00 96,618.96
Paku Biasa 2" - 5" Kg 0.1000 12,800.00 1,280.00
97,898.96
C PERALATAN
D Jumlah A + B + C 121,398.96
E Overhead & Profit 12.5% 15,174.87
F Harga Satuan Pekerjaan (D+E) 136,573.83

21 A.4.6.1.22 Pemasangan 1 m' Listplank Uk. (3x30)cm Kayu klas I atau klas II
A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0050 80,000.00 400.00
23,500.00
B Bahan
Kayu klas I Bengkirai) m3 0.0110 8,946,200.00 98,408.20
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
99,048.20
C PERALATAN
D Jumlah A + B + C 122,548.20
E Overhead & Profit 12.5% 15,318.53
F Harga Satuan Pekerjaan (D+E) 137,866.73
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

22 A.4.6.1.23 Pemasangan 1 m2 Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III
A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.4500 75,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 80,000.00 3,600.00
Mandor L.04 OH 0.0080 80,000.00 640.00
47,740.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
186,230.00
C PERALATAN
D Jumlah A + B + C 233,970.00
E Overhead & Profit 12.5% 29,246.25
F Harga Satuan Pekerjaan (D+E) 263,216.25

23 A.4.6.1.24 Pemasangan 1 m2 Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.4500 75,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 80,000.00 3,600.00
Mandor L.04 OH 0.0080 80,000.00 640.00
47,740.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
Teakwood 120 x 240 cm tebal 4mm Lbr 0.8600 80,000.00 68,800.00
Lem Ltr 0.5600 12,800.00 7,168.00
262,198.00
C PERALATAN
D Jumlah A + B + C 309,938.00
E Overhead & Profit 12.5% 38,742.25
F Harga Satuan Pekerjaan (D+E) 348,680.25

24 A.4.6.1.25 Pemasangan 1 m2 Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II


A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Kayu L.02 OH 0.6000 75,000.00 45,000.00
Kepala Tukang L.03 OH 0.0600 80,000.00 4,800.00
Mandor L.04 OH 0.0100 80,000.00 800.00
51,900.00
B Bahan
Kayu klas II (Kruing) m3 0.0280 6,582,500.00 184,310.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
Plywood 120 x 240 cm tebal 4mm Lbr 0.8600 80,000.00 68,800.00
Lem Ltr 0.5600 12,800.00 7,168.00
262,198.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 314,098.00
E Overhead & Profit 12.5% 39,262.25
F Harga Satuan Pekerjaan (D+E) 353,360.25
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

25 A.4.6.1.26 Pemasangan 1 m2 Dinding Lambriziring dari Papan klas I


A Tenaga
Pekerja L.01 OH 0.6000 65,000.00 39,000.00
Tukang Kayu L.02 OH 1.8000 75,000.00 135,000.00
Kepala Tukang L.03 OH 0.1800 80,000.00 14,400.00
Mandor L.04 OH 0.0300 80,000.00 2,400.00
190,800.00
B Bahan
Kayu klas I (Jati) m3 0.0070 16,875,000.00 118,125.00
Paku Biasa 2" - 5" Kg 0.1000 12,800.00 1,280.00
Paku Sekrup 3,5" Kg 0.1500 13,000.00 1,950.00
121,355.00
C PERALATAN
D Jumlah A + B + C 312,155.00
E Overhead & Profit 12.5% 39,019.38
F Harga Satuan Pekerjaan (D+E) 351,174.38

26 A.4.6.1.29 Pasang Kasau & Reng Kayu Bengkirai


A Tenaga
SNI Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0050 80,000.00 400.00
15,200.00
B Bahan
Kayu Bengkirai m3 0.0120 8,946,200.00 107,354.40
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
109,274.40
C PERALATAN
D Jumlah A + B + C 124,474.40
E Overhead & Profit 12.5% 15,559.30
F Harga Satuan Pekerjaan (D+E) 140,033.70

27 A.4.6.1.30 Pasang Kasau & Reng Kayu Kruing


A Tenaga
SNI Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0050 80,000.00 400.00
15,200.00
B Bahan
Kayu Kruing m3 0.0120 6,582,500.00 78,990.00
Paku Biasa 2" - 5" Kg 0.1500 12,800.00 1,920.00
80,910.00
C PERALATAN
D Jumlah A + B + C 96,110.00
E Overhead & Profit 12.5% 12,013.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 108,123.75
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
28 A.4.6.1.31 Pasang Papan sirip
A Tenaga
SNI Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
18,800.00
B Bahan
Kayu Kruing m3 0.0050 6,582,500.00 32,912.50
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
33,552.50
C PERALATAN
D Jumlah A + B + C 52,352.50
E Overhead & Profit 12.5% 6,544.06
F Harga Satuan Pekerjaan (D+E) 58,896.56
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 247.000 1,410.00 348,270.00
Pasir Beton Kg 869.000 275.00 238,975.00
Kerikil (maksimum 30 mm) Kg 999.000 159.93 159,766.00
Air ltr 215.000 20.00 4,300.00
751,311.00
C PERALATAN
D Jumlah A + B + C 888,066.00
E Overhead & Profit 12.5% 111,008.25
F Harga Satuan Pekerjaan (D+E) 999,074.25
Overhead & Profit 12.5%
2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 276.000 1,410.00 389,160.00
Pasir Beton kg 828.000 275.00 227,700.00
Kerikil (maksimum 30 mm) kg 1012.000 159.93 161,845.04
Air ltr 215.000 20.00 4,300.00
783,005.04
C PERALATAN
D Jumlah A + B + C 919,760.04
E Overhead & Profit 12.5% 114,970.00
F Harga Satuan Pekerjaan (D+E) 1,034,730.04

3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 299.000 1,410.00 421,590.00
Pasir Beton kg 799.000 275.00 219,725.00
Kerikil (maksimum 30 mm) kg 1017.000 159.93 162,644.67
Air ltr 215.000 20.00 4,300.00
808,259.67
C PERALATAN
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
D Jumlah A + B + C 945,014.67
E Overhead & Profit 12.5% 118,126.83
F Harga Satuan Pekerjaan (D+E) 1,063,141.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A Tenaga
Pekerja L.01 OH 1.200 65,000.00 78,000.00
Tukang Batu L.02 OH 0.200 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.020 80,000.00 1,600.00
Mandor L.04 OH 0.060 80,000.00 4,800.00
99,400.00
B Bahan
Portland Semen Kg 230.000 1,410.00 324,300.00
Pasir Beton Kg 893.000 275.00 245,575.00
Kerikil (maksimum 30 mm) Kg 1027.000 159.93 164,243.93
Air ltr 200.000 20.00 4,000.00
738,118.93
C PERALATAN
D Jumlah A + B + C 837,518.93
E Overhead & Profit 12.5% 104,689.87
F Harga Satuan Pekerjaan (D+E) 942,208.79

5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 326.000 1,410.00 459,660.00
Pasir Beton Kg 760.000 275.00 209,000.00
Kerikil (maksimum 30 mm) Kg 1029.000 159.93 164,563.78
Air ltr 215.000 20.00 4,300.00
837,523.78
C PERALATAN
D Jumlah A + B + C 974,278.78
E Overhead & Profit 12.5% 121,784.85
F Harga Satuan Pekerjaan (D+E) 1,096,063.63

6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 352.000 1,410.00 496,320.00
Pasir Beton Kg 731.000 275.00 201,025.00
Kerikil (maksimum 30 mm) Kg 1031.000 159.93 164,883.63
Air ltr 215.000 20.00 4,300.00
866,528.63
C PERALATAN
D Jumlah A + B + C 1,003,283.63
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 125,410.45
F Harga Satuan Pekerjaan (D+E) 1,128,694.08
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 371.000 1,410.00 523,110.00
Pasir Beton Kg 698.000 275.00 191,950.00
Kerikil (maksimum 30 mm) Kg 1047.000 159.93 167,442.44
Air ltr 215.000 20.00 4,300.00
886,802.44
C PERALATAN
D Jumlah A + B + C 1,023,557.44
E Overhead & Profit 12.5% 127,944.68
F Harga Satuan Pekerjaan (D+E) 1,151,502.13

8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 384.000 1,410.00 541,440.00
Pasir Beton Kg 692.000 275.00 190,300.00
Kerikil (maksimum 30 mm) Kg 1039.000 159.93 166,163.04
Air ltr 215.000 20.00 4,300.00
902,203.04
C PERALATAN
D Jumlah A + B + C 1,038,958.04
E Overhead & Profit 12.5% 129,869.75
F Harga Satuan Pekerjaan (D+E) 1,168,827.79

9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 406.000 1,410.00 572,460.00
Pasir Beton kg 684.000 275.00 188,100.00
Kerikil (maksimum 30 mm) kg 1026.000 159.93 164,084.00
Air ltr 215.000 20.00 4,300.00
928,944.00
C PERALATAN
D Jumlah A + B + C 1,065,699.00
E Overhead & Profit 12.5% 133,212.38
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,198,911.38
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52
A Tenaga
Pekerja L.01 OH 1.650 65,000.00 107,250.00
Tukang Batu L.02 OH 0.275 75,000.00 20,625.00
Kepala Tukang L.03 OH 0.028 80,000.00 2,240.00
Mandor L.04 OH 0.083 80,000.00 6,640.00
136,755.00
B Bahan
Portland Semen Kg 413.000 1,410.00 582,330.00
Pasir Beton Kg 681.000 275.00 187,275.00
Kerikil (maksimum 30 mm) Kg 1021.000 159.93 163,284.37
Air ltr 215.000 20.00 4,300.00
937,189.37
C PERALATAN
D Jumlah A + B + C 1,073,944.37
E Overhead & Profit 12.5% 134,243.05
F Harga Satuan Pekerjaan (D+E) 1,208,187.42

11 A.4.1.1.17 Pembesian 10 kg dg Besi Polos atau Besi Ulir


A Tenaga
Pekerja L.01 OH 0.070 65,000.00 4,550.00
Tukang Besi L.02 OH 0.070 75,000.00 5,250.00
Kepala Tukang L.03 OH 0.007 80,000.00 560.00
Mandor L.04 OH 0.004 80,000.00 320.00
10,680.00
B Bahan
Besi Beton (polos/ulir) Kg 10.500 8,700.00 91,350.00
Kawat Beton Kg 0.150 15,300.00 2,295.00
93,645.00
C PERALATAN
D Jumlah A + B + C 104,325.00
E Overhead & Profit 12.5% 13,040.63
F Harga Satuan Pekerjaan (D+E) 117,365.63
Jadi untuk pembesian 1 kg dibagi 10 11,736.56

12 A.4.1.1.19 Jaring Kawat baja/Wire Mesh / 10 kg


A Tenaga
Pekerja L.01 OH 0.025 65,000.00 1,625.00
Tukang Besi L.02 OH 0.025 75,000.00 1,875.00
Kepala Tukang L.03 OH 0.002 80,000.00 160.00
Mandor L.04 OH 0.001 80,000.00 80.00
3,740.00
B Bahan
Jaring Kawat Baja dilas/wiremesh Kg 10.200 17,000.00 173,400.00
Kawat Beton Kg 0.050 15,300.00 765.00
174,165.00
C PERALATAN
D Jumlah A + B + C 177,905.00
E Overhead & Profit 12.5% 22,238.13
F Harga Satuan Pekerjaan (D+E) 200,143.13
Jadi untuk pembesian 1 kg dibagi 10 20,014.31
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.1.1.20 Memasang Bekisting untuk Pondasi
A Tenaga
Pekerja L.01 OH 0.520 65,000.00 33,800.00
Tukang Kayu L.02 OH 0.260 75,000.00 19,500.00
Kepala Tukang L.03 OH 0.026 80,000.00 2,080.00
Mandor L.04 OH 0.026 80,000.00 2,080.00
57,460.00
B Bahan
Kayu Klas III (Randu) m3 0.040 945,300.00 37,812.00
Paku Biasa 2" - 5" Kg 0.300 12,800.00 3,840.00
Minyak Bekisting Ltr 0.100 -
41,652.00
C PERALATAN
D Jumlah A + B + C 99,112.00
E Overhead & Profit 12.5% 12,389.00
F Harga Satuan Pekerjaan (D+E) 111,501.00

14 A.4.1.1.21 Memasang Bekisting untuk Sloof


A Tenaga
Pekerja L.01 OH 0.520 65,000.00 33,800.00
Tukang Kayu L.02 OH 0.260 75,000.00 19,500.00
Kepala Tukang L.03 OH 0.026 80,000.00 2,080.00
Mandor L.04 OH 0.026 80,000.00 2,080.00
57,460.00
B Bahan
Kayu Klas III (Randu) m3 0.045 945,300.00 42,538.50
Paku Biasa 2" - 5" Kg 0.300 12,800.00 3,840.00
Minyak Bekisting Ltr 0.100 0.00 -
46,378.50
C PERALATAN
D Jumlah A + B + C 103,838.50
E Overhead & Profit 12.5% 12,979.81
F Harga Satuan Pekerjaan (D+E) 116,818.31

15 A.4.1.1.22 Memasang Bekisting untuk Kolom


A Tenaga
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang Kayu L.02 OH 0.330 75,000.00 24,750.00
Kepala Tukang L.03 OH 0.033 80,000.00 2,640.00
Mandor L.04 OH 0.033 80,000.00 2,640.00
72,930.00
B Bahan
Kayu Klas III (Randu) m3 0.040 945,300.00 37,812.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 0.00 -
Balok Kayu m3 0.015 945,300.00 14,179.50
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 2.000 13,500.00 27,000.00
119,811.50
C PERALATAN
D Jumlah A + B + C 192,741.50
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 24,092.69
F Harga Satuan Pekerjaan (D+E) 216,834.19
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.4.1.1.23 Memasang Bekisting untuk Balok
A Tenaga
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang Kayu L.02 OH 0.330 75,000.00 24,750.00
Kepala Tukang L.03 OH 0.033 80,000.00 2,640.00
Mandor L.04 OH 0.033 80,000.00 2,640.00
72,930.00
B Bahan
Kayu Klas III (Randu) m3 0.040 945,300.00 37,812.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 0.00 -
Balok Kayu m3 0.018 945,300.00 17,015.40
Plywood tebal 9mm Lbr 0.350 102,000.00 35,700.00
Bambu Btg 2.000 13,500.00 27,000.00
122,647.40
C PERALATAN
D Jumlah A + B + C 195,577.40
E Overhead & Profit 12.5% 24,447.18
F Harga Satuan Pekerjaan (D+E) 220,024.58

17 A.4.1.1.24 Memasang Bekisting untuk Lantai


A Tenaga
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang Kayu L.02 OH 0.330 75,000.00 24,750.00
Kepala Tukang L.03 OH 0.033 80,000.00 2,640.00
Mandor L.04 OH 0.033 80,000.00 2,640.00
72,930.00
B Bahan
Kayu Klas III (Randu) m3 0.040 945,300.00 37,812.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.200 0.00 -
Balok Kayu m3 0.015 945,300.00 14,179.50
Triplek 4 mm Lbr 0.350 58,000.00 20,300.00
Bambu Btg 6.000 13,500.00 81,000.00
158,411.50
C PERALATAN
D Jumlah A + B + C 231,341.50
E Overhead & Profit 12.5% 28,917.69
F Harga Satuan Pekerjaan (D+E) 260,259.19

18 A.4.1.1.26 Memasang Bekisting untuk Tangga


A Tenaga
Pekerja L.01 OH 0.660 65,000.00 42,900.00
Tukang Kayu L.02 OH 0.330 75,000.00 24,750.00
Kepala Tukang L.03 OH 0.033 80,000.00 2,640.00
Mandor L.04 OH 0.033 80,000.00 2,640.00
72,930.00
B Bahan
Kayu Klas III (Randu) m3 0.030 945,300.00 28,359.00
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
Minyak Bekisting Ltr 0.150 0.00 -
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Balok Kayu m3 0.015 945,300.00 14,179.50
Triplek 4 mm Lbr 0.350 58,000.00 20,300.00
Bambu Btg 2.000 13,500.00 27,000.00
94,958.50
C PERALATAN
D Jumlah A + B + C 167,888.50
E Overhead & Profit 12.5% 20,986.06
F Harga Satuan Pekerjaan (D+E) 188,874.56
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
19 A.4.1.1.35 Membuat Kolom Praktis Beton Bertulang (11 x 11) cm
A Tenaga
Pekerja L.01 OH 0.180 65,000.00 11,700.00
Tukang batu L.02 OH 0.020 75,000.00 1,500.00
Tukang Kayu L.02 OH 0.020 75,000.00 1,500.00
Tukang Besi L.02 OH 0.020 75,000.00 1,500.00
Kepala Tukang L.03 OH 0.006 80,000.00 480.00
Mandor L.04 OH 0.009 80,000.00 720.00
17,400.00
B Bahan
Kayu Klas III (Randu) m3 0.002 945,300.00 1,890.60
Paku Biasa 2" - 5" Kg 0.010 12,800.00 128.00
Besi Beton Polos Kg 3.000 8,700.00 26,100.00
Kawat Beton Kg 0.045 15,300.00 688.50
Portland Semen Kg 4.000 1,410.00 5,640.00
Pasir Beton m3 0.006 385,000.00 2,310.00
Kerikil Beton m3 0.009 215,900.00 1,943.10
38,700.20
C PERALATAN
D Jumlah A + B + C 56,100.20
E Overhead & Profit 12.5% 7,012.53
F Harga Satuan Pekerjaan (D+E) 63,112.73

20 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm


A Tenaga
Pekerja L.01 OH 0.297 65,000.00 19,305.00
Tukang batu L.02 OH 0.033 75,000.00 2,475.00
Tukang Kayu L.02 OH 0.033 75,000.00 2,475.00
Tukang Besi L.02 OH 0.033 75,000.00 2,475.00
Kepala Tukang L.03 OH 0.010 80,000.00 800.00
Mandor L.04 OH 0.015 80,000.00 1,200.00
28,730.00
B Bahan
Kayu Klas III (Randu) m3 0.003 945,300.00 2,835.90
Paku Biasa 2" - 5" Kg 0.020 12,800.00 256.00
Besi Beton Polos Kg 3.600 8,700.00 31,320.00
Kawat Beton Kg 0.050 15,300.00 765.00
Portland Semen Kg 5.500 1,410.00 7,755.00
Pasir Beton m3 0.009 385,000.00 3,465.00
Kerikil Beton m3 0.015 215,900.00 3,238.50
49,635.40
C PERALATAN
D Jumlah A + B + C 78,365.40
E Overhead & Profit 12.5% 9,795.68
F Harga Satuan Pekerjaan (D+E) 88,161.08

21 A.4.1.1.37 1 m² bekisting untuk permukaan beton biasa dengan kayu randu tebal 2 cm
A Tenaga
Pekerja L.01 OH 0.200 65,000.00 13,000.00
Tukang Kayu L.02 OH 0.500 75,000.00 37,500.00
Kepala Tukang L.03 OH 0.050 80,000.00 4,000.00
Mandor L.04 OH 0.010 80,000.00 800.00
55,300.00
B Bahan
kayu randu tebal 2 cm m3 0.022 945,300.00 20,796.60
Paku Biasa 2" - 5" Kg 0.400 12,800.00 5,120.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
25,916.60
C PERALATAN
D Jumlah A + B + C 81,216.60
E Overhead & Profit 12.5% 10,152.08
F Harga Satuan Pekerjaan (D+E) 91,368.68
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil
A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0075 80,000.00 600.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,615.00
B Bahan
Genteng Plentong Buah 25.0000 3,130.00 78,250.00
78,250.00
C PERALATAN
D Jumlah A + B + C 94,865.00
E Overhead & Profit 12.5% 11,858.13
F Harga Satuan Pekerjaan (D+E) 106,723.13

Overhead & Profit


2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur
A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,655.00
B Bahan
Genteng Kodok / Glasur Buah 25.0000 1,130.00 28,250.00
28,250.00
C PERALATAN
D Jumlah A + B + C 44,905.00
E Overhead & Profit 12.5% 5,613.13
F Harga Satuan Pekerjaan (D+E) 50,518.13

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,655.00
B Bahan
Genteng Plentong Super / Besar Buah 18.0000 6,000.00 108,000.00
108,000.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

C PERALATAN
D Jumlah A + B + C 124,655.00
E Overhead & Profit 12.5% 15,581.88
F Harga Satuan Pekerjaan (D+E) 140,236.88
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong


A Tenaga
Pekerja L.01 OH 0.4000 65,000.00 26,000.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0020 80,000.00 160.00
42,760.00
B Bahan
Genteng Bubung Plentong Buah 5.0000 13,500.00 67,500.00
Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 177,400.00 5,676.80
84,456.80
C PERALATAN
D Jumlah A + B + C 127,216.80
E Overhead & Profit 12.5% 15,902.10
F Harga Satuan Pekerjaan (D+E) 143,118.90

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur


A Tenaga
Pekerja L.01 OH 0.4000 65,000.00 26,000.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0020 80,000.00 160.00
42,760.00
B Bahan
Genteng Bubung Kodok / Glasur Buah 5.0000 5,600.00 28,000.00
Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 177,400.00 5,676.80
44,956.80
C PERALATAN
D Jumlah A + B + C 87,716.80
E Overhead & Profit 12.5% 10,964.60
F Harga Satuan Pekerjaan (D+E) 98,681.40

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar


A Tenaga
Pekerja L.01 OH 0.4000 65,000.00 26,000.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0020 80,000.00 160.00
42,760.00
B Bahan
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

Genteng Bubung Plentong Besar Buah 4.0000 13,500.00 54,000.00


Portland Semen Kg 8.0000 1,410.00 11,280.00
Pasir Pasang m3 0.0320 177,400.00 5,676.80
70,956.80
C PERALATAN
D Jumlah A + B + C 113,716.80
E Overhead & Profit 12.5% 14,214.60
F Harga Satuan Pekerjaan (D+E) 127,931.40
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

7 A.4.5.2.9 Pemasangan Atap Asbes Gelombang Besar(2,25x0,92 m) x 5 mm


A Tenaga
Pekerja L.01 OH 0.1400 65,000.00 9,100.00
Tukang Kayu L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0080 80,000.00 640.00
Mandor L.04 OH 0.0080 80,000.00 640.00
16,005.00
B Bahan
Asbes Gelombang Lbr 0.6000 83,000.00 49,800.00
Paku Pancing 60 x 230 Kg 0.1200 7,500.00 900.00
50,700.00
C PERALATAN
D Jumlah A + B + C 66,705.00
E Overhead & Profit 12.5% 8,338.13
F Harga Satuan Pekerjaan (D+E) 75,043.13

8 A.4.5.2.12 Pemasangan Atap Asbes Gelombang Kecil


A Tenaga
Pekerja L.01 OH 0.1400 65,000.00 9,100.00
Tukang Kayu L.02 OH 0.0700 75,000.00 5,250.00
Kepala Tukang L.03 OH 0.0070 80,000.00 560.00
Mandor L.04 OH 0.0070 80,000.00 560.00
15,470.00
B Bahan
Asbes Gelombang Lbr 0.3500 36,200.00 12,670.00
Paku Pancing 60 x 230 Kg 0.1200 7,500.00 900.00
13,570.00
C PERALATAN
D Jumlah A + B + C 29,040.00
E Overhead & Profit 12.5% 3,630.00
F Harga Satuan Pekerjaan (D+E) 32,670.00

9 A.4.5.2.22 Pemasangan 1 m’ bubung stel gelombang


A Tenaga
Pekerja L.01 OH 0.0840 65,000.00 5,460.00
Tukang Kayu L.02 OH 0.1250 75,000.00 9,375.00
Kepala Tukang L.03 OH 0.0130 80,000.00 1,040.00
Mandor L.04 OH 0.0040 80,000.00 320.00
16,195.00
B Bahan
Bubung stel gelombang Lbr 1.0000 30,000.00 30,000.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

Paku skrup 3,5” bj 4.0000 1,600.00 6,400.00


36,400.00
C PERALATAN
D Jumlah A + B + C 52,595.00
E Overhead & Profit 12.5% 6,574.38
F Harga Satuan Pekerjaan (D+E) 59,169.38
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

10 A.4.5.2.30 Pemasangan Atap Genteng Beton


A Tenaga
Pekerja L.01 OH 0.2000 65,000.00 13,000.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0100 80,000.00 800.00
22,100.00
B Bahan
Genteng Beton Standrad Lbr 11.0000 6,000.00 66,000.00
Paku Biasa 2" - 5" Kg 0.0300 12,800.00 384.00
66,384.00
C PERALATAN
D Jumlah A + B + C 88,484.00
E Overhead & Profit 12.5% 11,060.50
F Harga Satuan Pekerjaan (D+E) 99,544.50

11 A.4.5.2.34 Pemasangan Nok Genteng Beton


A Tenaga
Pekerja L.01 OH 0.4000 65,000.00 26,000.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0200 80,000.00 1,600.00
44,200.00
B Bahan
Nok Genteng Beton Buah 3.5000 13,500.00 47,250.00
Paku Biasa 2" - 5" Kg 0.0500 12,800.00 640.00
Portland Semen Kg 10.8000 1,410.00 15,228.00
Pasir Pasang m3 0.0320 177,400.00 5,676.80
Semen Warna Kg 1.0000 12,000.00 12,000.00
80,794.80
C PERALATAN
D Jumlah A + B + C 124,994.80
E Overhead & Profit 12.5% 15,624.35
F Harga Satuan Pekerjaan (D+E) 140,619.15

12 A.4.5.2.38 Pemasangan Atap Seng Gelombang


A Tenaga
Pekerja L.01 OH 0.1200 65,000.00 7,800.00
Tukang Kayu L.02 OH 0.0600 75,000.00 4,500.00
Kepala Tukang L.03 OH 0.0060 80,000.00 480.00
Mandor L.04 OH 0.0060 80,000.00 480.00
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

13,260.00
B Bahan
Seng Gelombang 3" x 6" BJLS 28 Lbr 0.7000 40,700.00 28,490.00
Paku Pancing Kg 0.0200 7,500.00 150.00
28,640.00
C PERALATAN
D Jumlah A + B + C 41,900.00
E Overhead & Profit 12.5% 5,237.50
F Harga Satuan Pekerjaan (D+E) 47,137.50
HARGA
JUMLAH HARGA
SATUAN
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF
Rp Rp

13 A.4.5.2.39 Pemasangan Atap Nok Seng


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Tukang Kayu L.02 OH 0.0700 75,000.00 5,250.00
Kepala Tukang L.03 OH 0.0070 80,000.00 560.00
Mandor L.04 OH 0.0060 80,000.00 480.00
16,040.00
B Bahan
Seng Plaat 3" x 6" BJLS 28 Lbr 0.3000 40,700.00 12,210.00
Paku Biasa 1/2" - 1" Kg 0.0400 12,800.00 512.00
12,722.00
C PERALATAN
D Jumlah A + B + C 28,762.00
E Overhead & Profit 12.5% 3,595.25
F Harga Satuan Pekerjaan (D+E) 32,357.25
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm

A Tenaga
Pekerja L.01 OH 0.030 65,000.00 1,950.00

Tukang Kayu L.02 OH 0.070 75,000.00 5,250.00


Kepala Tukang L.03 OH 0.007 80,000.00 560.00

Mandor L.04 OH 0.004 80,000.00 320.00

8,080.00

B Bahan

Plat Asbes Lbr 1.100 25,700.00 28,270.00


Paku Kg 0.010 12,800.00 128.00

28,398.00

C PERALATAN

D Jumlah A + B + C 36,478.00
E Overhead & Profit 12.5% 4,559.75

F Harga Satuan Pekerjaan (D+E) 41,037.75


Overhead & Profit (contoh 15%)

2 A.4.5.1.5 Memasang Langit-langit Tripleks Uk (120x240) cm, T 4 mm

A Tenaga
Pekerja L.01 OH 0.100 65,000.00 6,500.00

Tukang Kayu L.02 OH 0.100 75,000.00 7,500.00

Kepala Tukang L.03 OH 0.010 80,000.00 800.00

Mandor L.04 OH 0.005 80,000.00 400.00


15,200.00

B Bahan

Tripleks (4 mm) Lbr 0.375 58,000.00 21,750.00

Paku Tripleks Kg 0.030 12,800.00 384.00

22,134.00
C PERALATAN

D Jumlah A + B + C 37,334.00
E Overhead & Profit 12.5% 4,666.75

F Harga Satuan Pekerjaan (D+E) 42,000.75

3 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm


A Tenaga

Pekerja L.01 OH 0.800 65,000.00 52,000.00

Tukang Kayu L.02 OH 0.800 75,000.00 60,000.00


Kepala Tukang L.03 OH 0.080 80,000.00 6,400.00

Mandor L.04 OH 0.040 80,000.00 3,200.00


121,600.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
B Bahan

Kayu Jati,Papan m3 0.015 16,875,000.00 253,125.00


Paku Kg 0.010 12,800.00 128.00

253,253.00
C PERALATAN

D Jumlah A + B + C 374,853.00

E Overhead & Profit 12.5% 46,856.63

F Harga Satuan Pekerjaan (D+E) 421,709.63


HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.5.1.7 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm


A Tenaga

Pekerja L.01 OH 0.100 65,000.00 6,500.00


Tukang Kayu L.02 OH 0.050 75,000.00 3,750.00

Kepala Tukang L.03 OH 0.005 80,000.00 400.00

Mandor L.04 OH 0.005 80,000.00 400.00

11,050.00

B Bahan
Gypsum Board Lbr 0.364 64,300.00 23,405.20

Paku Sekrup Kg 0.110 13,000.00 1,430.00


24,835.20

C PERALATAN
D Jumlah A + B + C 35,885.20

E Overhead & Profit 12.5% 4,485.65

F Harga Satuan Pekerjaan (D+E) 40,370.85

5 A.4.5.1.8 Memasang Langit-langit Kalsiboard, Uk (120x240) tebal 3,5 mm


A Tenaga
Pekerja L.01 OH 0.100 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.050 75,000.00 3,750.00
Kepala Tukang L.03 OH 0.005 80,000.00 400.00
Mandor L.04 OH 0.005 80,000.00 400.00
11,050.00
B Bahan
Kalsiboard Lbr 0.364 53,400.00 19,437.60
Paku Sekrup Kg 0.110 4,500.00 495.00
19,932.60
C PERALATAN
D Jumlah A + B + C 30,982.60
E Overhead & Profit 12.5% 3,872.83
F Harga Satuan Pekerjaan (D+E) 34,855.43

6 A.4.5.1.10 List Langit-Langit Kayu Profil


A Tenaga
Pekerja L.01 OH 0.050 65,000.00 3,250.00
Tukang Kayu L.02 OH 0.050 75,000.00 3,750.00
Kepala Tukang L.03 OH 0.005 80,000.00 400.00
Mandor L.04 OH 0.003 80,000.00 240.00
7,640.00
B Bahan
List Kayu Profil m1 1.050 3,900.00 4,095.00
Paku Kg 0.010 12,800.00 128.00
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4,223.00
C PERALATAN
D Jumlah A + B + C 11,863.00
E Overhead & Profit 12.5% 1,482.88
F Harga Satuan Pekerjaan (D+E) 13,345.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok
A Tenaga
Pekerja L.01 OH 3.3000 65,000.00 214,500.00
Tukang Batu L.02 OH 1.1000 75,000.00 82,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.1600 80,000.00 12,800.00
310,600.00
B Bahan
Kloset Duduk / Monoblok Buah 1.0000 1,192,800.00 1,192,800.00
Kelengkapan 6% dari harga Kloset 0.0600 1,192,800.00 71,568.00
1,264,368.00
C PERALATAN
D Jumlah A + B + C 1,574,968.00
E Overhead & Profit 12.5% 196,871.00
F Harga Satuan Pekerjaan (D+E) 1,771,839.00
Overhead & Profit (contoh 15%)
2 A.5.1.1.2 Memasang Closet Jongkok Porselen
A Tenaga
Pekerja L.01 OH 1.0000 65,000.00 65,000.00
Tukang Batu L.02 OH 1.5000 75,000.00 112,500.00
Kepala Tukang L.03 OH 0.1500 80,000.00 12,000.00
Mandor L.04 OH 0.1600 80,000.00 12,800.00
202,300.00
B Bahan
Kloset Jongkok Buah 1.0000 137,600.00 137,600.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 177,400.00 1,774.00
147,834.00
C PERALATAN
D Jumlah A + B + C 350,134.00
E Overhead & Profit 12.5% 43,766.75
F Harga Satuan Pekerjaan (D+E) 393,900.75

3 A.5.1.1.4 Memasang Urinoir


A Tenaga
Pekerja L.01 OH 1.0000 65,000.00 65,000.00
Tukang Batu L.02 OH 1.0000 75,000.00 75,000.00
Kepala Tukang L.03 OH 0.1000 80,000.00 8,000.00
Mandor L.04 OH 0.0500 80,000.00 4,000.00
152,000.00
B Bahan
Urinoir Buah 1.0000 367,500.00 367,500.00
Perlengkapan 30% Harga Urinoir Ls 0.3000 367,500.00 110,250.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 177,400.00 1,774.00
487,984.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 639,984.00
E Overhead & Profit 12.5% 79,998.00
F Harga Satuan Pekerjaan (D+E) 719,982.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.5.1.1.5 Memasang Wastafel


A Tenaga
Pekerja L.01 OH 1.2000 65,000.00 78,000.00
Tukang Batu L.02 OH 0.1450 75,000.00 10,875.00
Kepala Tukang L.03 OH 0.1500 80,000.00 12,000.00
Mandor L.04 OH 0.0600 80,000.00 4,800.00
105,675.00
B Bahan
Wastafel Buah 1.0000 355,700.00 355,700.00
Perlengkapan 12% Harga Wastafel Ls 0.1200 355,700.00 42,684.00
Portland Semen Kg 6.0000 1,410.00 8,460.00
Pasir Pasang m3 0.0100 177,400.00 1,774.00
408,618.00
C PERALATAN
D Jumlah A + B + C 514,293.00
E Overhead & Profit 12.5% 64,286.63
F Harga Satuan Pekerjaan (D+E) 578,579.63

5 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3


A Tenaga
Pekerja L.01 OH 3.0000 65,000.00 195,000.00
Tukang Batu L.02 OH 4.5000 75,000.00 337,500.00
Kepala Tukang L.03 OH 0.0500 80,000.00 4,000.00
Mandor L.04 OH 0.9000 80,000.00 72,000.00
608,500.00
B Bahan
Bak Fibreglass Buah 1.0000 280,000.00 280,000.00
Perlengkapan 12% Bak Fibreglass Ls 0.1200 280,000.00 33,600.00
313,600.00
C PERALATAN
D Jumlah A + B + C 922,100.00
E Overhead & Profit 12.5% 115,262.50
F Harga Satuan Pekerjaan (D+E) 1,037,362.50

6 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3


A Tenaga
Pekerja L.01 OH 6.0000 65,000.00 390,000.00
Tukang Batu L.02 OH 3.0000 75,000.00 225,000.00
Kepala Tukang L.03 OH 0.3000 80,000.00 24,000.00
Mandor L.04 OH 0.0300 80,000.00 2,400.00
641,400.00
B Bahan
Batu Bata bh 150.00 760.00 114,000.00
Portland Semen Kg 120.00 1,410.00 169,200.00
Pasir Pasang m3 0.3000 177,400.00 53,220.00
Keramik 20 x 20 buah 111.00 2,000.00 222,000.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Semen Nat Kg 6.0000 12,000.00 72,000.00
630,420.00
C PERALATAN
D Jumlah A + B + C 1,271,820.00
E Overhead & Profit 12.5% 158,977.50
F Harga Satuan Pekerjaan (D+E) 1,430,797.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell


A Tenaga
Pekerja L.01 OH 0.0300 65,000.00 1,950.00
Tukang Batu L.02 OH 0.3000 75,000.00 22,500.00
Kepala Tukang L.03 OH 0.0300 80,000.00 2,400.00
Mandor L.04 OH 0.0150 80,000.00 1,200.00
28,050.00
B Bahan
Bak Cuci Piring unit 1.0000 176,100.00 176,100.00
Water drain bh 1.0000 60,000.00 60,000.00
236,100.00
C PERALATAN
D Jumlah A + B + C 264,150.00
E Overhead & Profit 12.5% 33,018.75
F Harga Satuan Pekerjaan (D+E) 297,168.75

8 A.5.1.1.14 Pemasangan Floor Drain


A Tenaga
Pekerja L.01 OH 0.0100 65,000.00 650.00
Tukang Batu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0050 80,000.00 400.00
9,350.00
B Bahan
Floor Drain bh 1.0000 23,100.00 23,100.00
23,100.00
C PERALATAN
D Jumlah A + B + C 32,450.00
E Overhead & Profit 12.5% 4,056.25
F Harga Satuan Pekerjaan (D+E) 36,506.25

9 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm


A Tenaga
Pekerja L.01 OH 2.1600 65,000.00 140,400.00
Tukang Batu L.02 OH 0.7200 75,000.00 54,000.00
Kepala Tukang L.03 OH 0.0720 80,000.00 5,760.00
Mandor L.04 OH 0.0110 80,000.00 880.00
201,040.00
B Bahan
Batu Bata bh 40.0000 760.00 30,400.00
Semen Portland kg 44.0000 1,410.00 62,040.00
Pasir Pasang m3 0.0700 177,400.00 12,418.00
Pasir Beton m3 0.0600 385,000.00 23,100.00
Kerikil m3 0.0700 215,900.00 15,113.00
Baja Tulangan kg 1.6000 8,700.00 13,920.00
156,991.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 358,031.00
E Overhead & Profit 12.5% 44,753.88
F Harga Satuan Pekerjaan (D+E) 402,784.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.5.1.1.16 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm


A Tenaga
Pekerja L.01 OH 3.2000 65,000.00 208,000.00
Tukang Batu L.02 OH 1.1500 75,000.00 86,250.00
Kepala Tukang L.03 OH 0.0110 80,000.00 880.00
Mandor L.04 OH 0.0160 80,000.00 1,280.00
296,410.00
B Bahan
Batu Bata bh 70.0000 760.00 53,200.00
Semen Portland kg 77.0000 1,410.00 108,570.00
Pasir Pasang m3 0.1300 177,400.00 23,062.00
Pasir Beton m3 0.0900 385,000.00 34,650.00
Kerikil m3 0.0200 215,900.00 4,318.00
Baja Tulangan kg 2.6000 8,700.00 22,620.00
246,420.00
C PERALATAN
D Jumlah A + B + C 542,830.00
E Overhead & Profit 12.5% 67,853.75
F Harga Satuan Pekerjaan (D+E) 610,683.75

11 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm


A Tenaga
Pekerja L.01 OH 3.2000 65,000.00 208,000.00
Tukang Batu L.02 OH 1.1500 75,000.00 86,250.00
Kepala Tukang L.03 OH 0.0110 80,000.00 880.00
Mandor L.04 OH 0.0160 80,000.00 1,280.00
296,410.00
B Bahan
Batu Bata bh 123.0000 760.00 93,480.00
Semen Portland kg 114.0000 1,410.00 160,740.00
Pasir Pasang m3 0.1840 177,400.00 32,641.60
Pasir Beton m3 0.1200 385,000.00 46,200.00
Kerikil m3 0.0330 215,900.00 7,124.70
Baja Tulangan kg 4.8500 8,700.00 42,195.00
382,381.30
C PERALATAN
D Jumlah A + B + C 678,791.30
E Overhead & Profit 12.5% 84,848.91
F Harga Satuan Pekerjaan (D+E) 763,640.21

12 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½"


A Tenaga
Pekerja L.01 OH 0.0540 65,000.00 3,510.00
Tukang Batu L.02 OH 0.0900 75,000.00 6,750.00
Kepala Tukang L.03 OH 0.0090 80,000.00 720.00
Mandor L.04 OH 0.0270 80,000.00 2,160.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13,140.00
B Bahan
Pipa Galvanis Ø ½" m' 1.2000 19,900.00 23,880.00
Perlengkapan 35% x pipa Ls 0.3500 19,900.00 6,965.00
30,845.00
C PERALATAN
D Jumlah A + B + C 43,985.00
E Overhead & Profit 12.5% 5,498.13
F Harga Satuan Pekerjaan (D+E) 49,483.13
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0100 65,000.00 650.00
Tukang Batu L.02 OH 0.4000 75,000.00 30,000.00
Kepala Tukang L.03 OH 0.0400 80,000.00 3,200.00
Mandor L.04 OH 0.0050 80,000.00 400.00
34,250.00
B Bahan
Kran Air bh 1.0000 25,700.00 25,700.00
Sealtape bh 0.0250 4,100.00 102.50
25,802.50
C PERALATAN
D Jumlah A + B + C 60,052.50
E Overhead & Profit 12.5% 7,506.56
F Harga Satuan Pekerjaan (D+E) 67,559.06

14 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0540 65,000.00 3,510.00
Tukang Batu L.02 OH 0.0900 75,000.00 6,750.00
Kepala Tukang L.03 OH 0.0090 80,000.00 720.00
Mandor L.04 OH 0.0270 80,000.00 2,160.00
13,140.00
B Bahan
Pipa Galvanis Ø ¾" m' 1.2000 26,000.00 31,200.00
Perlengkapan 35% x pipa Ls 0.3500 26,000.00 9,100.00
40,300.00
C PERALATAN
D Jumlah A + B + C 53,440.00
E Overhead & Profit 12.5% 6,680.00
F Harga Satuan Pekerjaan (D+E) 60,120.00

15 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1"


A Tenaga
Pekerja L.01 OH 0.0540 65,000.00 3,510.00
Tukang Batu L.02 OH 0.0900 75,000.00 6,750.00
Kepala Tukang L.03 OH 0.0090 80,000.00 720.00
Mandor L.04 OH 0.0270 80,000.00 2,160.00
13,140.00
B Bahan
Pipa Galvanis Ø 1" m' 1.2000 40,000.00 48,000.00
Perlengkapan 35% x pipa Ls 0.3500 40,000.00 14,000.00
62,000.00
C PERALATAN
D Jumlah A + B + C 75,140.00
E Overhead & Profit 12.5% 9,392.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 84,532.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
16 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ "
A Tenaga
Pekerja L.01 OH 0.1080 65,000.00 7,020.00
Tukang Batu L.02 OH 0.1800 75,000.00 13,500.00
Kepala Tukang L.03 OH 0.0180 80,000.00 1,440.00
Mandor L.04 OH 0.0050 80,000.00 400.00
22,360.00
B Bahan
Pipa Galvanis Ø 1½" m' 1.2000 60,100.00 72,120.00
Perlengkapan 35% x pipa Ls 0.3500 60,100.00 21,035.00
93,155.00
C PERALATAN
D Jumlah A + B + C 115,515.00
E Overhead & Profit 12.5% 14,439.38
F Harga Satuan Pekerjaan (D+E) 129,954.38

17 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3"


A Tenaga
Pekerja L.01 OH 0.1350 65,000.00 8,775.00
Tukang Batu L.02 OH 0.2250 75,000.00 16,875.00
Kepala Tukang L.03 OH 0.0230 80,000.00 1,840.00
Mandor L.04 OH 0.0070 80,000.00 560.00
28,050.00
B Bahan
Pipa Galvanis Ø 3" m' 1.2000 130,200.00 156,240.00
Perlengkapan 35% x pipa Ls 0.3500 130,200.00 45,570.00
201,810.00
C PERALATAN
D Jumlah A + B + C 229,860.00
E Overhead & Profit 12.5% 28,732.50
F Harga Satuan Pekerjaan (D+E) 258,592.50

18 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4"


A Tenaga
Pekerja L.01 OH 0.1350 65,000.00 8,775.00
Tukang Batu L.02 OH 0.2250 75,000.00 16,875.00
Kepala Tukang L.03 OH 0.0230 80,000.00 1,840.00
Mandor L.04 OH 0.0070 80,000.00 560.00
28,050.00
B Bahan
Pipa Galvanis Ø 4" m' 1.2000 190,300.00 228,360.00
Perlengkapan 35% x pipa Ls 0.3500 190,300.00 66,605.00
294,965.00
C PERALATAN
D Jumlah A + B + C 323,015.00
E Overhead & Profit 12.5% 40,376.88
F Harga Satuan Pekerjaan (D+E) 363,391.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

19 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½"


A Tenaga
Pekerja L.01 OH 0.0360 65,000.00 2,340.00
Tukang Batu L.02 OH 0.0600 75,000.00 4,500.00
Kepala Tukang L.03 OH 0.0060 80,000.00 480.00
Mandor L.04 OH 0.0020 80,000.00 160.00
7,480.00
B Bahan
Pipa PVC Ø ½" m' 1.2000 5,400.00 6,480.00
Perlengkapan 35% x pipa Ls 0.3500 5,400.00 1,890.00
8,370.00
C PERALATAN
D Jumlah A + B + C 15,850.00
E Overhead & Profit 12.5% 1,981.25
F Harga Satuan Pekerjaan (D+E) 17,831.25

20 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾"


A Tenaga
Pekerja L.01 OH 0.0360 65,000.00 2,340.00
Tukang Batu L.02 OH 0.0600 75,000.00 4,500.00
Kepala Tukang L.03 OH 0.0060 80,000.00 480.00
Mandor L.04 OH 0.0020 80,000.00 160.00
7,480.00
B Bahan
Pipa PVC Ø ¾" m' 1.2000 6,900.00 8,280.00
Perlengkapan 35% x pipa Ls 0.3500 6,900.00 2,415.00
10,695.00
C PERALATAN
D Jumlah A + B + C 18,175.00
E Overhead & Profit 12.5% 2,271.88
F Harga Satuan Pekerjaan (D+E) 20,446.88

21 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1"


A Tenaga
Pekerja L.01 OH 0.0360 65,000.00 2,340.00
Tukang Batu L.02 OH 0.0600 75,000.00 4,500.00
Kepala Tukang L.03 OH 0.0060 80,000.00 480.00
Mandor L.04 OH 0.0020 80,000.00 160.00
7,480.00
B Bahan
Pipa PVC Ø 1" m' 1.2000 8,700.00 10,440.00
Perlengkapan 35% x pipa Ls 0.3500 8,700.00 3,045.00
13,485.00
C PERALATAN
D Jumlah A + B + C 20,965.00
E Overhead & Profit 12.5% 2,620.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 23,585.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
22 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½"
A Tenaga
Pekerja L.01 OH 0.0540 65,000.00 3,510.00
Tukang Batu L.02 OH 0.0900 75,000.00 6,750.00
Kepala Tukang L.03 OH 0.0090 80,000.00 720.00
Mandor L.04 OH 0.0030 80,000.00 240.00
11,220.00
B Bahan
Pipa PVC Ø 1½" m' 1.2000 13,700.00 16,440.00
Perlengkapan 35% x pipa Ls 0.3500 13,700.00 4,795.00
21,235.00
C PERALATAN
D Jumlah A + B + C 32,455.00
E Overhead & Profit 12.5% 4,056.88
F Harga Satuan Pekerjaan (D+E) 36,511.88

23 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2"


A Tenaga
Pekerja L.01 OH 0.0540 65,000.00 3,510.00
Tukang Batu L.02 OH 0.0900 75,000.00 6,750.00
Kepala Tukang L.03 OH 0.0090 80,000.00 720.00
Mandor L.04 OH 0.0030 80,000.00 240.00
11,220.00
B Bahan
Pipa PVC Ø 2" m' 1.2000 20,000.00 24,000.00
Perlengkapan 35% x pipa Ls 0.3500 20,000.00 7,000.00
31,000.00
C PERALATAN
D Jumlah A + B + C 42,220.00
E Overhead & Profit 12.5% 5,277.50
F Harga Satuan Pekerjaan (D+E) 47,497.50

24 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3"


A Tenaga
Pekerja L.01 OH 0.0810 65,000.00 5,265.00
Tukang Batu L.02 OH 0.1350 75,000.00 10,125.00
Kepala Tukang L.03 OH 0.0135 80,000.00 1,080.00
Mandor L.04 OH 0.0040 80,000.00 320.00
16,790.00
B Bahan
Pipa PVC Ø 3" m' 1.2000 38,700.00 46,440.00
Perlengkapan 35% x pipa Ls 0.3500 38,700.00 13,545.00
59,985.00
C PERALATAN
D Jumlah A + B + C 76,775.00
E Overhead & Profit 12.5% 9,596.88
F Harga Satuan Pekerjaan (D+E) 86,371.88
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
25 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4"
A Tenaga
Pekerja L.01 OH 0.0810 65,000.00 5,265.00
Tukang Batu L.02 OH 0.1350 75,000.00 10,125.00
Kepala Tukang L.03 OH 0.0135 80,000.00 1,080.00
Mandor L.04 OH 0.0040 80,000.00 320.00
16,790.00
B Bahan
Pipa PVC Ø 4" m' 1.2000 59,100.00 70,920.00
Perlengkapan 35% x pipa Ls 0.3500 59,100.00 20,685.00
91,605.00
C PERALATAN
D Jumlah A + B + C 108,395.00
E Overhead & Profit 12.5% 13,549.38
F Harga Satuan Pekerjaan (D+E) 121,944.38

26 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm


A Tenaga
Pekerja L.01 OH 0.0800 65,000.00 5,200.00
Tukang Batu L.02 OH 0.0400 75,000.00 3,000.00
Kepala Tukang L.03 OH 0.0040 80,000.00 320.00
Mandor L.04 OH 0.0040 80,000.00 320.00
8,840.00
B Bahan
pipa tanah bh 1.6000 173,700.00 277,920.00
Semen Portlan kg 35.0000 1,410.00 49,350.00
Pasir Pasang m3 0.0140 177,400.00 2,483.60
Pasir Urug m3 0.0140 82,000.00 1,148.00
330,901.60
C PERALATAN
D Jumlah A + B + C 339,741.60
E Overhead & Profit 12.5% 42,467.70
F Harga Satuan Pekerjaan (D+E) 382,209.30

27 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm


A Tenaga
Pekerja L.01 OH 0.0600 65,000.00 3,900.00
Tukang Batu L.02 OH 0.0300 75,000.00 2,250.00
Kepala Tukang L.03 OH 0.0030 80,000.00 240.00
Mandor L.04 OH 0.0030 80,000.00 240.00
6,630.00
B Bahan
pipa tanah bh 1.6000 109,900.00 175,840.00
Semen Portlan kg 6.8000 1,410.00 9,588.00
Pasir Pasang m3 0.0130 177,400.00 2,306.20
Pasir Urug m3 0.0110 82,000.00 902.00
188,636.20
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN
D Jumlah A + B + C 195,266.20
E Overhead & Profit 12.5% 24,408.28
F Harga Satuan Pekerjaan (D+E) 219,674.48
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
28 A.5.1.1.35 Pemasangan Pipa Beton Ø 20 cm
A Tenaga
Pekerja L.01 OH 0.1400 65,000.00 9,100.00
Tukang Batu L.02 OH 0.0700 75,000.00 5,250.00
Kepala Tukang L.03 OH 0.0070 80,000.00 560.00
Mandor L.04 OH 0.0070 80,000.00 560.00
15,470.00
B Bahan
pipa beton bh 1.1000 56,100.00 61,710.00
Batu Bata m3 0.0270 570,000.00 15,390.00
Semen Portlan kg 3.9200 1,410.00 5,527.20
Pasir Pasang m3 0.0560 177,400.00 9,934.40
Pasir Urug m3 0.0240 82,000.00 1,968.00
94,529.60
C PERALATAN
D Jumlah A + B + C 109,999.60
E Overhead & Profit 12.5% 13,749.95
F Harga Satuan Pekerjaan (D+E) 123,749.55

29 A.5.1.1.36 Pemasangan Pipa Beton Ø 100 cm


A Tenaga
Pekerja L.01 OH 0.3800 65,000.00 24,700.00
Tukang Batu L.02 OH 0.1900 75,000.00 14,250.00
Kepala Tukang L.03 OH 0.0190 80,000.00 1,520.00
Mandor L.04 OH 0.0190 80,000.00 1,520.00
41,990.00
B Bahan
pipa beton bh 1.1000 0.00 -
Batu Bata m3 0.5500 570,000.00 313,500.00
Semen Portlan kg 10.3000 1,410.00 14,523.00
Pasir Pasang m3 0.0610 177,400.00 10,821.40
Pasir Urug m3 0.0690 82,000.00 5,658.00
344,502.40
C PERALATAN
D Jumlah A + B + C 386,492.40
E Overhead & Profit 12.5% 48,311.55
F Harga Satuan Pekerjaan (D+E) 434,803.95
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM

1 A.4.2.1.1 Pemasangan Besi Profil

A Tenaga

Pekerja L.01 OH 0.0600 65,000.00 3,900.00

Tukang Besi L.02 OH 0.0600 75,000.00 4,500.00

Kepala Tukang L.03 OH 0.0060 80,000.00 480.00

Mandor L.04 OH 0.0030 80,000.00 240.00

9,120.00

B Bahan

Besi Profil Kg 1.1500 14,000.00 16,100.00

Meni Besi Kg 0.0600 30,600.00 1,836.00

17,936.00

C PERALATAN

D Jumlah A + B + C 27,056.00

E Overhead & Profit 12.5% 3,382.00

F Harga Satuan Pekerjaan (D+E) 30,438.00

Overhead & Profit

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF

A Tenaga

Pekerja L.01 OH 0.0600 65,000.00 3,900.00

Tukang Besi L.02 OH 0.0600 75,000.00 4,500.00

Kepala Tukang L.03 OH 0.0060 80,000.00 480.00

Mandor L.04 OH 0.0030 80,000.00 240.00

9,120.00

B Bahan

Besi Baja IWF kg 1.1500 14,000.00 16,100.00

16,100.00

C PERALATAN

D Jumlah A + B + C 25,220.00
E Overhead & Profit 12.5% 3,152.50

F Harga Satuan Pekerjaan (D+E) 28,372.50

3 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi

A Tenaga
Pekerja L.01 OH 1.2000 65,000.00 78,000.00

Tukang Besi L.02 OH 1.2000 75,000.00 90,000.00

Kepala Tukang L.03 OH 0.1200 80,000.00 9,600.00

Mandor L.04 OH 0.0060 80,000.00 480.00

178,080.00

B Bahan

Pintu Gulung Besi m2 1.0000 350,000.00 350,000.00

350,000.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
C PERALATAN

D Jumlah A + B + C 528,080.00

E Overhead & Profit 12.5% 66,010.00

F Harga Satuan Pekerjaan (D+E) 594,090.00


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door)

A Tenaga

Pekerja L.01 OH 0.4400 65,000.00 28,600.00

Tukang Besi L.02 OH 0.4400 75,000.00 33,000.00

Kepala Tukang L.03 OH 0.0440 80,000.00 3,520.00

Mandor L.04 OH 0.0220 80,000.00 1,760.00

66,880.00
B Bahan

Pintu Lipat m2 1.0000 434,000.00 434,000.00

434,000.00

C PERALATAN

D Jumlah A + B + C 500,880.00

E Overhead & Profit 12.5% 62,610.00

F Harga Satuan Pekerjaan (D+E) 563,490.00

5 A.4.2.1.10 Pemasangan Rolling Door Allumunium

A Tenaga
Pekerja L.01 OH 1.0000 65,000.00 65,000.00

Tukang Besi L.02 OH 1.0000 75,000.00 75,000.00

Kepala Tukang L.03 OH 0.1000 80,000.00 8,000.00

Mandor L.04 OH 0.0500 80,000.00 4,000.00

152,000.00

B Bahan

Rolling Allumunium m2 1.0000 364,000.00 364,000.00

364,000.00

C PERALATAN

D Jumlah A + B + C 516,000.00

E Overhead & Profit 12.5% 64,500.00

F Harga Satuan Pekerjaan (D+E) 580,500.00

6 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium

A Tenaga

Pekerja L.01 OH 0.0430 65,000.00 2,795.00

Tukang Besi L.02 OH 0.0430 75,000.00 3,225.00

Kepala Tukang L.03 OH 0.0043 80,000.00 344.00

Mandor L.04 OH 0.0021 80,000.00 168.00

6,532.00

B Bahan

Profil Allumunium m' 1.1000 103,200.00 113,520.00


Skrup Fixer buah 2.0000 1,600.00 3,200.00

Sealant Tube 0.0600 22,500.00 1,350.00


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
118,070.00

C PERALATAN

D Jumlah A + B + C 124,602.00

E Overhead & Profit 12.5% 15,575.25

F Harga Satuan Pekerjaan (D+E) 140,177.25


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm

A Tenaga

Pekerja L.01 OH 0.0850 65,000.00 5,525.00

Tukang Besi L.02 OH 0.0850 75,000.00 6,375.00

Kepala Tukang L.03 OH 0.0085 80,000.00 680.00

Mandor L.04 OH 0.0042 80,000.00 336.00

12,916.00
B Bahan

Profil Allumunium m' 4.4000 103,200.00 454,080.00

Allumunium Strip m' 14.6000 34,300.00 500,780.00

954,860.00

C PERALATAN

D Jumlah A + B + C 967,776.00

E Overhead & Profit 12.5% 120,972.00

F Harga Satuan Pekerjaan (D+E) 1,088,748.00

8 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium


A Tenaga

Pekerja L.01 OH 0.0850 65,000.00 5,525.00

Tukang Besi L.02 OH 0.0850 75,000.00 6,375.00

Kepala Tukang L.03 OH 0.0090 80,000.00 720.00

Mandor L.04 OH 0.0050 80,000.00 400.00

13,020.00

B Bahan

Pintu Allumunium m' 4.4000 103,200.00 454,080.00

Profil Kaca m' 4.5000 85,000.00 382,500.00

Sealant tube 0.2700 22,500.00 6,075.00

842,655.00

C PERALATAN

D Jumlah A + B + C 855,675.00

E Overhead & Profit 12.5% 106,959.38

F Harga Satuan Pekerjaan (D+E) 962,634.38

9 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm

A Tenaga

Pekerja L.01 OH 0.2000 65,000.00 13,000.00

Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00

Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00

Mandor L.04 OH 0.0010 80,000.00 80.00


29,680.00

B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Seng Plaat Lbr 1.0500 20,300.00 21,315.00

Paku Biasa 1 - 2,5 cm Kg 0.0150 12,800.00 192.00

Kayu Papan Klas II atau III m3 0.0190 4,500,000.00 85,500.00

107,007.00

C PERALATAN

D Jumlah A + B + C 136,687.00

E Overhead & Profit 12.5% 17,085.88

F Harga Satuan Pekerjaan (D+E) 153,772.88


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm

A Tenaga

Pekerja L.01 OH 0.1500 65,000.00 9,750.00

Tukang Kayu L.02 OH 0.3000 75,000.00 22,500.00

Kepala Tukang L.03 OH 0.0300 80,000.00 2,400.00

Mandor L.04 OH 0.0080 80,000.00 640.00

35,290.00
B Bahan

Seng Plaat Lbr 1.0500 20,300.00 21,315.00

Paku Biasa 1 - 2,5 cm Kg 0.0100 12,800.00 128.00

Besi strip Kg 0.5000 20,200.00 10,100.00

31,543.00

C PERALATAN

D Jumlah A + B + C 66,833.00

E Overhead & Profit 12.5% 8,354.13

F Harga Satuan Pekerjaan (D+E) 75,187.13

11 A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon

A Tenaga

Pekerja L.01 OH 0.3500 65,000.00 22,750.00

Tukang Kayu L.02 OH 0.3500 75,000.00 26,250.00

Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00

Mandor L.04 OH 0.0180 80,000.00 1,440.00

53,240.00

B Bahan

Rangka metal hollow 40.40.2 mm M1 4.0000 11,300.00 45,200.00

Assesoris (perkuatan, las dll) Ls 0.5000 5,650.00 2,825.00

48,025.00

C PERALATAN

D Jumlah A + B + C 101,265.00

E Overhead & Profit 12.5% 12,658.13

F Harga Satuan Pekerjaan (D+E) 113,923.13


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa
A Tenaga
Pekerja L.01 OH 0.0100 65,000.00 650.00
Tukang Kayu L.02 OH 0.5000 75,000.00 37,500.00
Kepala Tukang L.03 OH 0.0500 80,000.00 4,000.00
Mandor L.04 OH 0.0050 80,000.00 400.00
42,550.00
B Bahan
Kunci Tanam Biasa Buah 1.0000 77,200.00 77,200.00
77,200.00
C PERALATAN
D Jumlah A + B + C 119,750.00
E Overhead & Profit 12.5% 14,968.75
F Harga Satuan Pekerjaan (D+E) 134,718.75
Overhead & Profit

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi


A Tenaga
Pekerja L.01 OH 0.0050 65,000.00 325.00
Tukang Kayu L.02 OH 0.5000 75,000.00 37,500.00
Kepala Tukang L.03 OH 0.0500 80,000.00 4,000.00
Mandor L.04 OH 0.0025 80,000.00 200.00
42,025.00
B Bahan
Kunci Tanam Kamar Mandi Buah 1.0000 46,400.00 46,400.00
46,400.00
C PERALATAN
D Jumlah A + B + C 88,425.00
E Overhead & Profit 12.5% 11,053.13
F Harga Satuan Pekerjaan (D+E) 99,478.13

3 A.4.6.2.4 Pemasangan Kunci Selinder


A Tenaga
Pekerja L.01 OH 0.0050 65,000.00 325.00
Tukang Kayu L.02 OH 0.5000 75,000.00 37,500.00
Kepala Tukang L.03 OH 0.0500 80,000.00 4,000.00
Mandor L.04 OH 0.0025 80,000.00 200.00
42,025.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Kunci Selinder Buah 1.0000 77,200.00 77,200.00
77,200.00
C PERALATAN
D Jumlah A + B + C 119,225.00
E Overhead & Profit 12.5% 14,903.13
F Harga Satuan Pekerjaan (D+E) 134,128.13
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.6.2.5 Pemasangan Engsel Pintu
A Tenaga
Pekerja L.01 OH 0.0150 65,000.00 975.00
Tukang Kayu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0008 80,000.00 64.00
13,489.00
B Bahan
Engsel pintu Buah 1.0000 26,100.00 26,100.00
26,100.00
C PERALATAN
D Jumlah A + B + C 39,589.00
E Overhead & Profit 12.5% 4,948.63
F Harga Satuan Pekerjaan (D+E) 44,537.63

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu


A Tenaga
Pekerja L.01 OH 0.0100 65,000.00 650.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0005 80,000.00 40.00
8,990.00
B Bahan
Engsel Jendela Buah 1.0000 18,500.00 18,500.00
18,500.00
C PERALATAN
D Jumlah A + B + C 27,490.00
E Overhead & Profit 12.5% 3,436.25
F Harga Satuan Pekerjaan (D+E) 30,926.25

6 A.4.6.2.7 Pemasangan Engsel Angin


A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0005 80,000.00 40.00
23,140.00
B Bahan
Engsel Angin Buah 1.0000 19,800.00 19,800.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
19,800.00
C PERALATAN
D Jumlah A + B + C 42,940.00
E Overhead & Profit 12.5% 5,367.50
F Harga Satuan Pekerjaan (D+E) 48,307.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.4.6.2.9 Pemasangan Kait Angin
A Tenaga
Pekerja L.01 OH 0.0150 65,000.00 975.00
Tukang Kayu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0080 80,000.00 640.00
14,065.00
B Bahan
Kait Angin Buah 1.0000 6,900.00 6,900.00
6,900.00
C PERALATAN
D Jumlah A + B + C 20,965.00
E Overhead & Profit 12.5% 2,620.63
F Harga Satuan Pekerjaan (D+E) 23,585.63

8 A.4.6.2.10 Pasang Door Closer


A Tenaga
Pekerja L.01 OH 0.0500 65,000.00 3,250.00
Tukang Kayu L.02 OH 0.5000 75,000.00 37,500.00
Kepala Tukang L.03 OH 0.0500 80,000.00 4,000.00
Mandor L.04 OH 0.0025 80,000.00 200.00
44,950.00
B Bahan
Door Closer Buah 1.0000 118,400.00 118,400.00
118,400.00
C PERALATAN
D Jumlah A + B + C 163,350.00
E Overhead & Profit 12.5% 20,418.75
F Harga Satuan Pekerjaan (D+E) 183,768.75

9 A.4.6.2.11 Pemasangan Kunci Selot


A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Kayu L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0010 80,000.00 80.00
17,980.00
B Bahan
Kunci Selot Buah 1.0000 8,900.00 8,900.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
8,900.00
C PERALATAN
D Jumlah A + B + C 26,880.00
E Overhead & Profit 12.5% 3,360.00
F Harga Satuan Pekerjaan (D+E) 30,240.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
10 A.4.6.2.13 Pemasangan Door Stop
A Tenaga
Pekerja L.01 OH 0.0100 65,000.00 650.00
Tukang Kayu L.02 OH 0.1000 75,000.00 7,500.00
Kepala Tukang L.03 OH 0.0100 80,000.00 800.00
Mandor L.04 OH 0.0005 80,000.00 40.00
8,990.00
B Bahan
Door Stop Buah 1.0000 35,000.00 35,000.00
35,000.00
C PERALATAN
D Jumlah A + B + C 43,990.00
E Overhead & Profit 12.5% 5,498.75
F Harga Satuan Pekerjaan (D+E) 49,488.75

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong


A Tenaga
Pekerja L.01 OH 0.0600 65,000.00 3,900.00
Tukang Kayu L.02 OH 0.6000 75,000.00 45,000.00
Kepala Tukang L.03 OH 0.0600 80,000.00 4,800.00
Mandor L.04 OH 0.0030 80,000.00 240.00
53,940.00
B Bahan
Rel Pintu Dorong Buah 1.0000 216,200.00 216,200.00
216,200.00
C PERALATAN
D Jumlah A + B + C 270,140.00
E Overhead & Profit 12.5% 33,767.50
F Harga Satuan Pekerjaan (D+E) 303,907.50

12 A.4.6.2.16 Pemasangan Kaca tebal 3 mm


A Tenaga
Pekerja L.01 OH 0.0150 65,000.00 975.00
Tukang Kayu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0008 80,000.00 60.00
13,485.00
B Bahan
Kaca tebal 3mm m2 1.1000 71,200.00 78,320.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
78,320.00
C PERALATAN
D Jumlah A + B + C 91,805.00
E Overhead & Profit 12.5% 11,475.63
F Harga Satuan Pekerjaan (D+E) 103,280.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
13 A.4.6.2.17 Pemasangan Kaca tebal 5 mm
A Tenaga
Pekerja L.01 OH 0.0150 65,000.00 975.00
Tukang Kayu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0008 80,000.00 60.00
13,485.00
B Bahan
Kaca tebal 5mm m2 1.1000 85,000.00 93,500.00
93,500.00
C PERALATAN
D Jumlah A + B + C 106,985.00
E Overhead & Profit 12.5% 13,373.13
F Harga Satuan Pekerjaan (D+E) 120,358.13

14 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm


A Tenaga
Pekerja L.01 OH 0.0150 65,000.00 975.00
Tukang Kayu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0008 80,000.00 60.00
13,485.00
B Bahan
Kaca Cermin m2 1.1000 170,000.00 187,000.00
187,000.00
C PERALATAN
D Jumlah A + B + C 200,485.00
E Overhead & Profit 12.5% 25,060.63
F Harga Satuan Pekerjaan (D+E) 225,545.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm
A Tenaga
Pekerja L.01 OH 0.2500 65,000.00 16,250.00
Tukang Batu L.02 OH 0.1250 75,000.00 9,375.00
Kepala Tukang L.03 OH 0.0130 80,000.00 1,040.00
Mandor L.04 OH 0.0130 80,000.00 1,040.00
27,705.00
B Bahan
Ubin Abu-abu 30x30 cm Buah 11.8700 3,400.00 40,358.00
Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
62,441.00
C PERALATAN
D Jumlah A + B + C 90,146.00
E Overhead & Profit 12.5% 11,268.25
F Harga Satuan Pekerjaan (D+E) 101,414.25

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.2700 65,000.00 17,550.00
Tukang Batu L.02 OH 0.1350 75,000.00 10,125.00
Kepala Tukang L.03 OH 0.0140 80,000.00 1,120.00
Mandor L.04 OH 0.0140 80,000.00 1,120.00
29,915.00
B Bahan
Ubin Abu-abu 20x20 cm Buah 26.5000 1,500.00 39,750.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
62,397.00
C PERALATAN
D Jumlah A + B + C 92,312.00
E Overhead & Profit 12.5% 11,539.00
F Harga Satuan Pekerjaan (D+E) 103,851.00

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm


A Tenaga
Pekerja L.01 OH 0.2600 65,000.00 16,900.00
Tukang Batu L.02 OH 0.1300 75,000.00 9,750.00
Kepala Tukang L.03 OH 0.0130 80,000.00 1,040.00
Mandor L.04 OH 0.0130 80,000.00 1,040.00
28,730.00
B Bahan
Ubin Warna 30x30 cm Buah 11.8700 3,700.00 43,919.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Portland Semen Kg 10.0000 1,410.00 14,100.00


Semen warna Kg 1.5000 12,000.00 18,000.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
84,002.00
C PERALATAN
D Jumlah A + B + C 112,732.00
E Overhead & Profit 12.5% 14,091.50
F Harga Satuan Pekerjaan (D+E) 126,823.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.2700 65,000.00 17,550.00
Tukang Batu L.02 OH 0.1350 75,000.00 10,125.00
Kepala Tukang L.03 OH 0.0140 80,000.00 1,120.00
Mandor L.04 OH 0.0140 80,000.00 1,120.00
29,915.00
B Bahan
Ubin Warna 20x20 cm Buah 26.5000 1,900.00 50,350.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Semen warna Kg 1.6200 12,000.00 19,440.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
92,437.00
C PERALATAN
D Jumlah A + B + C 122,352.00
E Overhead & Profit 12.5% 15,294.00
F Harga Satuan Pekerjaan (D+E) 137,646.00

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm


A Tenaga
Pekerja L.01 OH 0.2500 65,000.00 16,250.00
Tukang Batu L.02 OH 0.1250 75,000.00 9,375.00
Kepala Tukang L.03 OH 0.0130 80,000.00 1,040.00
Mandor L.04 OH 0.0130 80,000.00 1,040.00
27,705.00
B Bahan
Ubin Granito 40x40 cm Buah 6.6300 32,800.00 217,464.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen warna Kg 1.3000 12,000.00 15,600.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
254,865.00
C PERALATAN
D Jumlah A + B + C 282,570.00
E Overhead & Profit 12.5% 35,321.25
F Harga Satuan Pekerjaan (D+E) 317,891.25

6 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm warna


A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Ubin Keramik 30 x 30 cm warna Buah 11.8700 4,100.00 48,667.00


Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
Semen Warna Kg 1.5000 12,000.00 18,000.00
88,750.00
C PERALATAN
D Jumlah A + B + C 166,100.00
E Overhead & Profit 12.5% 20,762.50
F Harga Satuan Pekerjaan (D+E) 186,862.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

7 A.4.4.3.35.1 Pemasangan Lantai Keramik 30 x 30 cm putih


A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
Ubin Keramik 30 x 30 cm putih Buah 11.8700 3,800.00 45,106.00
Portland Semen Kg 10.0000 1,410.00 14,100.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
Semen Warna Kg 1.5000 12,000.00 18,000.00
85,189.00
C PERALATAN
D Jumlah A + B + C 162,539.00
E Overhead & Profit 12.5% 20,317.38
F Harga Satuan Pekerjaan (D+E) 182,856.38

8 A.4.4.3.35.2 Pemasangan Lantai Keramik 40 x 40 cm warna

SNI A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
Ubin Keramik 40 x 40 cm Buah 6.6300 8,300.00 55,029.00
Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 12,000.00 15,600.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
92,430.00
C PERALATAN
D Jumlah A + B + C 169,780.00
E Overhead & Profit 12.5% 21,222.50
F Harga Satuan Pekerjaan (D+E) 191,002.50

9 A.4.4.3.35.3 Pemasangan Lantai Keramik 40 x 40 cm putih

SNI A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Ubin Keramik 40 x 40 cm putih Buah 6.6300 7,800.00 51,714.00


Portland Semen Kg 9.8000 1,410.00 13,818.00
Semen Warna Kg 1.3000 12,000.00 15,600.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
89,115.00
C PERALATAN
D Jumlah A + B + C 166,465.00
E Overhead & Profit 12.5% 20,808.13
F Harga Satuan Pekerjaan (D+E) 187,273.13
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

10 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm


A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
Ubin Keramik 20 x 20 cm Buah 26.5000 2,000.00 53,000.00
Portland Semen Kg 10.4000 1,410.00 14,664.00
Semen Warna Kg 1.6200 12,000.00 19,440.00
Pasir Pasang m3 0.0450 177,400.00 7,983.00
95,087.00
C PERALATAN
D Jumlah A + B + C 172,437.00
E Overhead & Profit 12.5% 21,554.63
F Harga Satuan Pekerjaan (D+E) 193,991.63

11 A.4.4.3.46 Pemasangan Lantai Parquet Jati


A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
Parquet Jati m2 1.0500 210,000.00 220,500.00
Lem Vynil Kg 0.6000 35,000.00 21,000.00
241,500.00
C PERALATAN
D Jumlah A + B + C 318,850.00
E Overhead & Profit 12.5% 39,856.25
F Harga Satuan Pekerjaan (D+E) 358,706.25

12 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm,


A Tenaga
Pekerja L.01 OH 0.9000 65,000.00 58,500.00
Tukang Batu L.02 OH 0.4500 75,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 80,000.00 3,600.00
Mandor L.04 OH 0.0450 80,000.00 3,600.00
99,450.00
B Bahan
Keramik Buah 53.0000 1,000.00 53,000.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Portland Semen Kg 9.3000 1,410.00 13,113.00


Pasir Pasang m3 0.0180 177,400.00 3,193.20
Semen Warna Kg 2.7500 12,000.00 33,000.00
102,306.20
C PERALATAN
D Jumlah A + B + C 201,756.20
E Overhead & Profit 12.5% 25,219.53
F Harga Satuan Pekerjaan (D+E) 226,975.73
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm,


A Tenaga
Pekerja L.01 OH 0.9000 65,000.00 58,500.00
Tukang Batu L.02 OH 0.4500 75,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 80,000.00 3,600.00
Mandor L.04 OH 0.0450 80,000.00 3,600.00
99,450.00
B Bahan
Keramik Buah 26.5000 2,000.00 53,000.00
Portland Semen Kg 9.3000 1,410.00 13,113.00
Pasir Pasang m3 0.0180 177,400.00 3,193.20
Semen Warna Kg 1.9400 12,000.00 23,280.00
92,586.20
C PERALATAN
D Jumlah A + B + C 192,036.20
E Overhead & Profit 12.5% 24,004.53
F Harga Satuan Pekerjaan (D+E) 216,040.73

14 A.4.4.3.55 Pemasangan Dinding Keramik 20x25 cm,


A Tenaga
Pekerja L.01 OH 0.9000 65,000.00 58,500.00
Tukang Batu L.02 OH 0.4500 75,000.00 33,750.00
Kepala Tukang L.03 OH 0.0450 80,000.00 3,600.00
Mandor L.04 OH 0.0450 80,000.00 3,600.00
99,450.00
B Bahan
Keramik Buah 20.0000 2,700.00 54,000.00
Portland Semen Kg 9.3000 1,410.00 13,113.00
Pasir Pasang m3 0.0180 177,400.00 3,193.20
Semen Warna Kg 1.9400 12,000.00 23,280.00
93,586.20
C PERALATAN
D Jumlah A + B + C 193,036.20
E Overhead & Profit 12.5% 24,129.53
F Harga Satuan Pekerjaan (D+E) 217,165.73

15 A.4.4.3.58 Pemasangan Dinding Batu Paras / Batu Tempel Hitam


A Tenaga
Pekerja L.01 OH 0.7000 65,000.00 45,500.00
Tukang Batu L.02 OH 0.3500 75,000.00 26,250.00
Kepala Tukang L.03 OH 0.0350 80,000.00 2,800.00
Mandor L.04 OH 0.0350 80,000.00 2,800.00
77,350.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

Batu Paras/batu tempel m2 1.1000 105,000.00 115,500.00


Portland Semen Kg 11.7500 1,410.00 16,567.50
Pasir Pasang m3 0.0350 177,400.00 6,209.00
138,276.50
C PERALATAN
D Jumlah A + B + C 215,626.50
E Overhead & Profit 12.5% 26,953.31
F Harga Satuan Pekerjaan (D+E) 242,579.81
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

16 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm


A Tenaga
Pekerja L.01 OH 0.1200 65,000.00 7,800.00
Tukang Batu L.02 OH 0.1200 75,000.00 9,000.00
Kepala Tukang L.03 OH 0.0120 80,000.00 960.00
Mandor L.04 OH 0.0060 80,000.00 480.00
18,240.00
B Bahan
Papan Kayu Klas II m3 0.0030 6,582,500.00 19,747.50
Paku Sekrup 5 cm kg 0.0500 13,000.00 650.00
20,397.50
C PERALATAN
D Jumlah A + B + C 38,637.50
E Overhead & Profit 12.5% 4,829.69
F Harga Satuan Pekerjaan (D+E) 43,467.19

17 A.4.4.3.64 Pasang blok pafing tebal 6 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 55,300.00 55,300.00
57,225.00
C PERALATAN
D Jumlah A + B + C 104,175.00
E Overhead & Profit 12.5% 13,021.88
F Harga Satuan Pekerjaan (D+E) 117,196.88

18 A.4.4.3.65 Blok paving tebal 6 cm dengan paving mutu K 225


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 85,000.00 85,000.00
86,925.00
C PERALATAN
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

D Jumlah A + B + C 133,875.00
E Overhead & Profit 12.5% 16,734.38
F Harga Satuan Pekerjaan (D+E) 150,609.38
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

19 A.4.4.3.66 Blok paving tebal 8 cm dengan paving mutu K 300


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 125,000.00 125,000.00
126,925.00
C PERALATAN
D Jumlah A + B + C 173,875.00
E Overhead & Profit 12.5% 21,734.38
F Harga Satuan Pekerjaan (D+E) 195,609.38

20 A.4.4.3.67 Blok paving tebal 8 cm dengan paving mutu K 400


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 140,000.00 140,000.00
141,925.00
C PERALATAN
D Jumlah A + B + C 188,875.00
E Overhead & Profit 12.5% 23,609.38
F Harga Satuan Pekerjaan (D+E) 212,484.38

21 A.4.4.3.68 Blok paving warna tebal 6 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 51,000.00 51,000.00
52,925.00
C PERALATAN
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

D Jumlah A + B + C 99,875.00
E Overhead & Profit 12.5% 12,484.38
F Harga Satuan Pekerjaan (D+E) 112,359.38
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

22 A.4.4.3.69 Blok paving warna tebal 8 cm K.125


SNI A Tenaga
Pekerja L.01 OH 0.5000 65,000.00 32,500.00
Tukang Batu L.02 OH 0.1500 75,000.00 11,250.00
Kepala Tukang L.03 OH 0.0150 80,000.00 1,200.00
Mandor L.04 OH 0.0250 80,000.00 2,000.00
46,950.00
B Bahan
pasir muntilan utk nat m3 0.0050 385,000.00 1,925.00
paving m2 1.0000 57,500.00 57,500.00
59,425.00
C PERALATAN
D Jumlah A + B + C 106,375.00
E Overhead & Profit 12.5% 13,296.88
F Harga Satuan Pekerjaan (D+E) 119,671.88

23 A.4.4.3.70 pasang saluran U-20 cm


SNI A Tenaga
B Bahan
Buis beton U-20 cm m' 1.0000 46,200.00 46,200.00
Pasang 1/2 batu bata 1:4 m2 0.8000 114,970.00 91,976.00
Plesteran 1:3 m2 0.7400 52,969.16 39,197.18
Acian m2 0.7400 30,017.81 22,213.18
Hurugan pasir m3 0.0200 118,700.00 2,374.00
Ongkos pasang Buis U-20 1.0000 5,000.00 5,000.00
206,960.36
C PERALATAN
D Jumlah A + B + C 206,960.36
E Overhead & Profit 12.5% 25,870.04
F Harga Satuan Pekerjaan (D+E) 232,830.40

24 A.4.4.3.71 pasang saluran U-30 cm


SNI A Tenaga
B Bahan
Buis beton U-30 cm m' 1.0000 60,000.00 60,000.00
Pasang 1/2 batu bata 1:4 m2 0.8000 114,970.00 91,976.00
Plesteran 1:3 m2 0.7400 52,969.16 39,197.18
Acian m2 0.7400 30,017.81 22,213.18
Hurugan pasir m3 0.0200 118,700.00 2,374.00
Ongkos pasang Buis U-30 1.0000 5,000.00 5,000.00
220,760.36
C PERALATAN
D Jumlah A + B + C 220,760.36
E Overhead & Profit 12.5% 27,595.04
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

F Harga Satuan Pekerjaan (D+E) 248,355.40


HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Mandor L.04 OH 0.0030 80,000.00 240.00
9,990.00
B Bahan
Soda Api Kg 0.0500 23,200.00 1,160.00
1,160.00
C PERALATAN
D Jumlah A + B + C 11,150.00
E Overhead & Profit 12.5% 1,393.75
F Harga Satuan Pekerjaan (D+E) 12,543.75

2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Mandor L.04 OH 0.0030 80,000.00 240.00
9,990.00
B Bahan
Sabun Kg 0.0500 8,000.00 400.00
400.00
C PERALATAN
D Jumlah A + B + C 10,390.00
E Overhead & Profit 12.5% 1,298.75
F Harga Satuan Pekerjaan (D+E) 11,688.75

3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual


A Tenaga
Pekerja L.01 OH 0.1500 65,000.00 9,750.00
Mandor L.04 OH 0.0080 80,000.00 640.00
10,390.00
B Bahan
Sabun Kg 0.0500 8,000.00 400.00
400.00
C PERALATAN
D Jumlah A + B + C 10,790.00
E Overhead & Profit 12.5% 1,348.75
F Harga Satuan Pekerjaan (D+E) 12,138.75
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 65,000.00 4,550.00
Tukang Cat L.02 OH 0.0090 75,000.00 675.00
Kepala Tukang L.03 OH 0.0060 80,000.00 480.00
Mandor L.04 OH 0.0030 80,000.00 240.00
5,945.00
B Bahan
Cat Menie kg 0.2000 29,000.00 5,800.00
Plamuur kg 0.1500 32,800.00 4,920.00
Cat Dasar kg 0.1700 33,500.00 5,695.00
Cat Penutup kg 0.2600 51,700.00 13,442.00
Kuas bh 0.0100 13,200.00 132.00
Pengencer kg 0.0300 20,000.00 600.00
Amplas lbr 0.2000 6,400.00 1,280.00
31,869.00
C PERALATAN
D Jumlah A + B + C 37,814.00
E Overhead & Profit 12.5% 4,726.75
F Harga Satuan Pekerjaan (D+E) 42,540.75

5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup)
A Tenaga
Pekerja L.01 OH 0.0700 65,000.00 4,550.00
Tukang Cat L.02 OH 0.1050 75,000.00 7,875.00
Kepala Tukang L.03 OH 0.0040 80,000.00 320.00
Mandor L.04 OH 0.0030 80,000.00 240.00
12,985.00
B Bahan
Cat Menie kg 0.2000 29,000.00 5,800.00
Plamuur kg 0.1500 32,800.00 4,920.00
Cat Dasar kg 0.1700 33,500.00 5,695.00
Cat Penutup kg 0.3500 51,700.00 18,095.00
Kuas bh 0.0100 13,200.00 132.00
Pengencer kg 0.0300 20,000.00 600.00
Amplas lbr 0.2000 6,400.00 1,280.00
36,522.00
C PERALATAN
D Jumlah A + B + C 49,507.00
E Overhead & Profit 12.5% 6,188.38
F Harga Satuan Pekerjaan (D+E) 55,695.38
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil


A Tenaga
Pekerja L.01 OH 0.0400 65,000.00 2,600.00
Tukang Cat L.02 OH 0.0630 75,000.00 4,725.00
Kepala Tukang L.03 OH 0.0630 80,000.00 5,040.00
Mandor L.04 OH 0.0030 80,000.00 240.00
12,605.00
B Bahan
Teak Oil Ltr 0.3600 42,000.00 15,120.00
15,120.00
C PERALATAN
D Jumlah A + B + C 27,725.00
E Overhead & Profit 12.5% 3,465.63
F Harga Satuan Pekerjaan (D+E) 31,190.63

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur


A Tenaga
Pekerja L.01 OH 0.0400 65,000.00 2,600.00
Tukang Cat L.02 OH 0.0600 75,000.00 4,500.00
Kepala Tukang L.03 OH 0.0160 80,000.00 1,280.00
Mandor L.04 OH 0.0030 80,000.00 240.00
8,620.00
B Bahan
Politur Ltr 0.1500 16,900.00 2,535.00
Spiritus Ltr 0.3720 12,000.00 4,464.00
Ampelas Lbr 2.0000 6,400.00 12,800.00
19,799.00
C PERALATAN
D Jumlah A + B + C 28,419.00
E Overhead & Profit 12.5% 3,552.38
F Harga Satuan Pekerjaan (D+E) 31,971.38

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter


A Tenaga
Pekerja L.01 OH 0.1000 65,000.00 6,500.00
Mandor L.04 OH 0.0060 80,000.00 480.00
6,980.00
B Bahan
Residu atau Ter Ltr 0.3500 3,400.00 1,190.00
1,190.00
C PERALATAN
D Jumlah A + B + C 8,170.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 1,021.25
F Harga Satuan Pekerjaan (D+E) 9,191.25
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis
A Tenaga
Pekerja L.01 OH 0.1600 65,000.00 10,400.00
Tukang Cat L.02 OH 0.1600 75,000.00 12,000.00
Kepala Tukang L.03 OH 0.0160 80,000.00 1,280.00
Mandor L.04 OH 0.0030 80,000.00 240.00
23,920.00
B Bahan
Vernis Ltr 0.1500 27,900.00 4,185.00
Dempul Ltr 0.0500 32,800.00 1,640.00
Ampelas Lbr 0.1000 6,400.00 640.00
6,465.00
C PERALATAN
D Jumlah A + B + C 30,385.00
E Overhead & Profit 12.5% 3,798.13
F Harga Satuan Pekerjaan (D+E) 34,183.13

10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Decolite
A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Cat L.02 OH 0.0630 75,000.00 4,725.00
Kepala Tukang L.03 OH 0.0063 80,000.00 504.00
Mandor L.04 OH 0.0030 80,000.00 240.00
6,769.00
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 19,000.00 1,900.00
Cat Penutup 2 kali Kg 0.2600 20,200.00 5,252.00
8,902.00
C PERALATAN
D Jumlah A + B + C 15,671.00
E Overhead & Profit 12.5% 1,958.88
F Harga Satuan Pekerjaan (D+E) 17,629.88

11 A.4.7.1.10.1 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Cat L.02 OH 0.0630 75,000.00 4,725.00
Kepala Tukang L.03 OH 0.0063 80,000.00 504.00
Mandor L.04 OH 0.0030 80,000.00 240.00
6,769.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 19,000.00 1,900.00
Cat Penutup 2 kali Kg 0.2600 54,500.00 14,170.00
17,820.00
C PERALATAN
D Jumlah A + B + C 24,589.00
E Overhead & Profit 12.5% 3,073.63
F Harga Satuan Pekerjaan (D+E) 27,662.63
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

12 A.4.7.1.10.2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Cat L.02 OH 0.0630 75,000.00 4,725.00
Kepala Tukang L.03 OH 0.0063 80,000.00 504.00
Mandor L.04 OH 0.0030 80,000.00 240.00
6,769.00
B Bahan
Plamir Kg 0.1000 17,500.00 1,750.00
Cat Dasar Kg 0.1000 19,000.00 1,900.00
Cat Penutup 2 kali Kg 0.2600 83,600.00 21,736.00
25,386.00
C PERALATAN
D Jumlah A + B + C 32,155.00
E Overhead & Profit 12.5% 4,019.38
F Harga Satuan Pekerjaan (D+E) 36,174.38

13 A.4.7.1.11 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Decolite


A Tenaga
Pekerja L.01 OH 0.0280 65,000.00 1,820.00
Tukang Cat L.02 OH 0.0420 75,000.00 3,150.00
Kepala Tukang L.03 OH 0.0042 80,000.00 336.00
Mandor L.04 OH 0.0030 80,000.00 240.00
5,546.00
B Bahan
Cat Dasar Kg 0.1200 19,000.00 2,280.00
Cat Penutup 2 kali Kg 0.1800 20,200.00 3,636.00
5,916.00
C PERALATAN
D Jumlah A + B + C 11,462.00
E Overhead & Profit 12.5% 1,432.75
F Harga Satuan Pekerjaan (D+E) 12,894.75

14 A.4.7.1.11.1 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex dalam ruangan
A Tenaga
Pekerja L.01 OH 0.0280 65,000.00 1,820.00
Tukang Cat L.02 OH 0.0420 75,000.00 3,150.00
Kepala Tukang L.03 OH 0.0042 80,000.00 336.00
Mandor L.04 OH 0.0030 80,000.00 240.00
5,546.00
B Bahan
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Cat Dasar Kg 0.1200 19,000.00 2,280.00
Cat Penutup 2 kali Kg 0.1800 54,500.00 9,810.00
12,090.00
C PERALATAN
D Jumlah A + B + C 17,636.00
E Overhead & Profit 12.5% 2,204.50
F Harga Satuan Pekerjaan (D+E) 19,840.50
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
15 A.4.7.1.11.2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup)Mowilex luar ruangan
A Tenaga
Pekerja L.01 OH 0.0280 65,000.00 1,820.00
Tukang Cat L.02 OH 0.0420 75,000.00 3,150.00
Kepala Tukang L.03 OH 0.0042 80,000.00 336.00
Mandor L.04 OH 0.0030 80,000.00 240.00
5,546.00
B Bahan
Cat Dasar Kg 0.1200 19,000.00 2,280.00
Cat Penutup 2 kali Kg 0.1800 83,600.00 15,048.00
17,328.00
C PERALATAN
D Jumlah A + B + C 22,874.00
E Overhead & Profit 12.5% 2,859.25
F Harga Satuan Pekerjaan (D+E) 25,733.25

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi


A Tenaga
Pekerja L.01 OH 0.0200 65,000.00 1,300.00
Tukang Cat L.02 OH 0.2000 75,000.00 15,000.00
Kepala Tukang L.03 OH 0.0200 80,000.00 1,600.00
Mandor L.04 OH 0.0025 80,000.00 200.00
18,100.00
B Bahan
Meni Besi Kg 0.1000 30,600.00 3,060.00
Perekat / Lem Kg 0.0100 35,000.00 350.00
3,410.00
C PERALATAN
D Jumlah A + B + C 21,510.00
E Overhead & Profit 12.5% 2,688.75
F Harga Satuan Pekerjaan (D+E) 24,198.75

17 A.4.7.1.22 Pengecatan 1 m2 permukaan Besi 3x


SNI A Tenaga
Pekerja L.01 OH 0.0500 65,000.00 3,250.00
Tukang Cat L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0075 80,000.00 600.00
Mandor L.04 OH 0.0025 80,000.00 200.00
9,675.00
B Bahan
Cat Kg 0.2600 57,600.00 14,976.00
Pengencer L 0.1740 20,000.00 3,480.00
Meni Kg 0.0750 30,600.00 2,295.00
Amplas Bh 0.2000 6,400.00 1,280.00
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
22,031.00
C PERALATAN
D Jumlah A + B + C 31,706.00
E Overhead & Profit 12.5% 3,963.25
F Harga Satuan Pekerjaan (D+E) 35,669.25
HARGA JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
18 A.4.7.1.23 Pengecatan 1 m2 permukaan Trotoir 3x
SNI A Tenaga
Pekerja L.01 OH 0.0500 65,000.00 3,250.00
Tukang Cat L.02 OH 0.0750 75,000.00 5,625.00
Kepala Tukang L.03 OH 0.0075 80,000.00 600.00
Mandor L.04 OH 0.0025 80,000.00 200.00
9,675.00
B Bahan
Cat Kg 0.2600 57,600.00 14,976.00
Pengencer L 0.1740 20,000.00 3,480.00
Amplas Bh 0.2000 6,400.00 1,280.00
19,736.00
C PERALATAN
D Jumlah A + B + C 29,411.00
E Overhead & Profit 12.5% 3,676.38
F Harga Satuan Pekerjaan (D+E) 33,087.38
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
XV A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
1 A.8.4.1.1 Pemasangan 1 m pipa PVC Ø 50 mm (2")
A TENAGA
Pekerja L.01 OH 0.081 55,000.00 4,455.00
Tukang pipa L.02 OH 0.041 65,000.00 2,665.00
Mandor L.04 OH 0.008 75,000.00 600.00
7,720.00
B BAHAN
Pipa PVC Ø 50 mm m 1.000 24,350.00 24,350.00
24,350.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 32,070.00
E Overhead & Profit 12.5% 4,008.75
F Harga Satuan Pekerjaan (D+E) 36,078.75

2 A.8.4.1.1.1 Pemasangan 1 m pipa PVC Ø 25 mm (1")


A TENAGA
Pekerja L.01 OH 0.067 55,000.00 3,681.82
Tukang pipa L.02 OH 0.034 65,000.00 2,202.48
Mandor L.04 OH 0.007 75,000.00 495.87
6,380.17
B BAHAN
Pipa PVC Ø 25 mm m 1.000 8,450.00 8,450.00
8,450.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 14,830.17
E Overhead & Profit 12.5% 1,853.77
F Harga Satuan Pekerjaan (D+E) 16,683.94

3 A.8.4.1.1.2 Pemasangan 1 m pipa PVC Ø 40 mm (1½")


A TENAGA
Pekerja L.01 OH 0.074 55,000.00 4,050.00
Tukang pipa L.02 OH 0.037 65,000.00 2,422.73
Mandor L.04 OH 0.007 75,000.00 545.45
7,018.18
B BAHAN
Pipa PVC Ø 40 mm m 1.000 19,100.00 19,100.00
19,100.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.006 -
-
D Jumlah A + B + C 26,118.18
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
E Overhead & Profit 12.5% 3,264.77
F Harga Satuan Pekerjaan (D+E) 29,382.95
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
4 A.8.4.1.2 Pemasangan 1 m pipa PVC Ø 75 mm (3")
A TENAGA
Pekerja L.01 OH 0.094 55,000.00 5,170.00
Tukang pipa L.02 OH 0.047 65,000.00 3,055.00
Mandor L.04 OH 0.009 75,000.00 675.00
8,900.00
B BAHAN
Pipa PVC Ø 75 mm m 1.000 50,900.00 50,900.00
50,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.009 -
-
D Jumlah A + B + C 59,800.00
E Overhead & Profit 12.5% 7,475.00
F Harga Satuan Pekerjaan (D+E) 67,275.00

5 A.8.4.1.3 Pemasangan 1 m pipa PVC Ø 90 mm (4")


A TENAGA
Pekerja L.01 OH 0.105 55,000.00 5,775.00
Tukang pipa L.02 OH 0.053 65,000.00 3,445.00
Mandor L.04 OH 0.011 75,000.00 825.00
10,045.00
B BAHAN
Pipa PVC Ø 90 mm m 1.000 73,900.00 73,900.00
73,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.009 -
-
D Jumlah A + B + C 83,945.00
E Overhead & Profit 12.5% 10,493.13
F Harga Satuan Pekerjaan (D+E) 94,438.13

6 A.8.4.1.17 Pemasangan 1 m pipa HDPE OD 63 mm


A TENAGA
Pekerja L.01 OH 0.035 55,000.00 1,925.00
Tukang pipa L.02 OH 0.017 65,000.00 1,105.00
Mandor L.04 OH 0.003 75,000.00 225.00
3,255.00
B BAHAN
Pipa HDPE OD 63 mm m 1.000 50,050.00 50,050.00
50,050.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 53,305.00
E Overhead & Profit 12.5% 6,663.13
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
F Harga Satuan Pekerjaan (D+E) 59,968.13
Overhead & Profit
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
7 A.8.4.1.17.1 Pemasangan 1 m pipa HDPE OD 75 mm
A TENAGA
Pekerja L.01 OH 0.039 55,000.00 2,117.50
Tukang pipa L.02 OH 0.019 65,000.00 1,215.50
Mandor L.04 OH 0.003 75,000.00 247.50
3,580.50
B BAHAN
Pipa HDPE OD 75 mm m 1.000 69,900.00 69,900.00
69,900.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 73,480.50
E Overhead & Profit 12.5% 9,185.06
F Harga Satuan Pekerjaan (D+E) 82,665.56

8 A.8.4.1.17.2 Pemasangan 1 m pipa HDPE OD 90 mm


A TENAGA
Pekerja L.01 OH 0.040 55,000.00 2,200.00
Tukang pipa L.02 OH 0.020 65,000.00 1,300.00
Mandor L.04 OH 0.004 75,000.00 300.00
3,800.00
B BAHAN
Pipa HDPE OD 90 mm m 1.000 101,300.00 101,300.00
101,300.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 -
-
D Jumlah A + B + C 105,100.00
E Overhead & Profit 12.5% 13,137.50
F Harga Satuan Pekerjaan (D+E) 118,237.50

9 A.8.4.1.80 Biaya 1 m' pemasangan pipa PVC Ø 25 mm (galian 0,25m x 0,3m + Bahan)
Galian tanah keras m3 0.075 76,005.00 5,700.38
Urugan tanah kembali m3 0.065 13,687.50 889.69
Buangan sisa galian m3 0.010 25,031.25 250.31
Pemasangan Pipa 1.000 16,683.94 16,683.94
Harga Satuan Pekerjaan 23,524.31

10 A.8.4.1.81 Biaya 1 m' pemasangan pipa PVC Ø 40 mm (galian 0,25m x 0,4m + Bahan)
Galian tanah keras m3 0.100 76,005.00 7,600.50
Urugan tanah kembali m3 0.080 13,687.50 1,095.00
Buangan sisa galian m3 0.020 25,031.25 500.63
Pemasangan Pipa 1.000 29,382.95 29,382.95
Harga Satuan Pekerjaan 38,579.08

11 A.8.4.1.82 Biaya 1 m' pemasangan pipa PVC Ø 50 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 76,005.00 9,500.63
Urugan tanah kembali m3 0.095 13,687.50 1,300.31
Buangan sisa galian m3 0.030 25,031.25 750.94
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
Pemasangan Pipa 1.000 36,078.75 36,078.75
Harga Satuan Pekerjaan 47,630.63

12 A.8.4.1.83 Biaya 1 m' pemasangan pipa PVC Ø 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 76,005.00 11,400.75
Urugan tanah kembali m3 0.120 13,687.50 1,642.50
Buangan sisa galian m3 0.030 25,031.25 750.94
Pemasangan Pipa 1.000 67,275.00 67,275.00
Harga Satuan Pekerjaan 81,069.19
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp

13 A.8.4.1.84 Biaya 1 m' pemasangan pipa PVC Ø 100 mm (galian 0,30m x 1,00m + Bahan)
Galian tanah keras m3 0.300 76,005.00 22,801.50
Urugan tanah kembali m3 0.265 13,687.50 3,627.19
Buangan sisa galian m3 0.035 25,031.25 876.09
Pemasangan Pipa 1.000 94,438.13 94,438.13
Harga Satuan Pekerjaan 121,742.91

14 A.8.4.1.85 Biaya 1 m' pemasangan pipa HDPE OD 63 mm (galian 0,25m x 0,5m + Bahan)
Galian tanah keras m3 0.125 76,005.00 9,500.63
Urugan tanah kembali m3 0.095 13,687.50 1,300.31
Buangan sisa galian m3 0.030 25,031.25 750.94
Pemasangan Pipa 1.000 59,968.13 59,968.13
Harga Satuan Pekerjaan 71,520.00

15 A.8.4.1.86 Biaya 1 m' pemasangan pipa HDPE OD 75 mm (galian 0,25m x 0,6m + Bahan)
Galian tanah keras m3 0.150 76,005.00 11,400.75
Urugan tanah kembali m3 0.120 13,687.50 1,642.50
Buangan sisa galian m3 0.030 25,031.25 750.94
Pemasangan Pipa 1.000 82,665.56 82,665.56
Harga Satuan Pekerjaan 96,459.75

16 A.8.4.1.87 Biaya 1 m' pemasangan pipa HDPE OD 90 mm (galian 0,25m x 0,70m + Bahan)
Galian tanah keras m3 0.175 76,005.00 13,300.88
Urugan tanah kembali m3 0.140 13,687.50 1,916.25
Buangan sisa galian m3 0.035 25,031.25 876.09
Pemasangan Pipa 1.000 118,237.50 118,237.50
Harga Satuan Pekerjaan 134,330.72

XVI A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA

1 A.8.4.5.1 Pengetesan 1 m pipa Ø 50 mm


A TENAGA
Pekerja L.01 OH 0.0080 55,000.00 440.00
Mandor L.04 OH 0.0008 80,000.00 64.00
504.00
B BAHAN
Air test (air bersih) m3 0.002 20,000.00 40.00
Bahan bakar liter 0.060 5,900.00 354.00
Oli liter 0.002 35,300.00 70.60
464.60
C PERALATAN
D Jumlah A + B + C 968.60
E Overhead & Profit 12.5% 121.08
F Harga Satuan Pekerjaan (D+E) 1,089.68

2 A.8.4.5.2 Pengetesan 1 m pipa Ø 75 mm


A TENAGA
Pekerja L.01 OH 0.0080 55,000.00 440.00
Mandor L.04 OH 0.0008 80,000.00 64.00
504.00
B BAHAN
Air test (air bersih) m3 0.004 20,000.00 80.00
Bahan bakar liter 0.060 5,900.00 354.00
Oli liter 0.002 35,300.00 70.60
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
504.60
C PERALATAN
D Jumlah A + B + C 1,008.60
E Overhead & Profit 12.5% 126.08
F Harga Satuan Pekerjaan (D+E) 1,134.68
HARGA
JUMLAH HARGA
No. AHSP URAIAN PEKERJAAN KODE SAT. KOEF SATUAN
Rp Rp
3 A.8.4.5.3 Pengetesan 1 m pipa Ø 100 mm
A TENAGA
Pekerja L.01 OH 0.0080 55,000.00 440.00
Mandor L.04 OH 0.0008 80,000.00 64.00
504.00
B BAHAN
Air test (air bersih) m3 0.008 20,000.00 160.00
Bahan bakar liter 0.060 5,900.00 354.00
Oli liter 0.002 35,300.00 70.60
584.60
C PERALATAN
D Jumlah A + B + C 1,088.60
E Overhead & Profit 12.5% 136.08
F Harga Satuan Pekerjaan (D+E) 1,224.68

4 A.8.4.5.4 Pengetesan 1 m pipa Ø 150 mm


A TENAGA
Pekerja L.01 OH 0.0080 55,000.00 440.00
Mandor L.04 OH 0.0008 80,000.00 64.00
504.00
B BAHAN
Air test (air bersih) m3 0.018 20,000.00 360.00
Bahan bakar liter 0.060 5,900.00 354.00
Oli liter 0.002 35,300.00 70.60
784.60
C PERALATAN
D Jumlah A + B + C 1,288.60
E Overhead & Profit 12.5% 161.08
F Harga Satuan Pekerjaan (D+E) 1,449.68

5 A.8.4.5.5 Pengetesan 1 m pipa Ø 200 mm


A TENAGA
Pekerja L.01 OH 0.0080 55,000.00 440.00
Mandor L.04 OH 0.0008 80,000.00 64.00
504.00
B BAHAN
Air test (air bersih) m3 0.031 20,000.00 620.00
Bahan bakar liter 0.060 5,900.00 354.00
Oli liter 0.002 35,300.00 70.60
1,044.60
C PERALATAN
D Jumlah A + B + C 1,548.60
E Overhead & Profit 12.5% 193.58
F Harga Satuan Pekerjaan (D+E) 1,742.18
PEKERJAAN : PEMBUATAN SUMUR PRODUKSI

An.1 Jenis pekerjaan : Mobilisasi/demobilisasi driling rig & peralatan pemboran

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3
Crew pengeboran Hari 4.00 x 1.00 50,000.00 200,000.00
4
Pengemudi Hari 2.00 x 2.00 40,000.00 160,000.00
II. PERALATAN
1 Sewa kendaraan Hari 2.00 x 2.00 250,000.00 1,000,000.00
angkut ( truk )

JUMLAH 1,485,000.00

An.2 Jenis pekerjaan :Pemboran pilot hole diameter 6", 0 -- 50 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 70.00 x 1.00 5,900.00 413,000.00
2 Olie mesin Ltr 5.00 x 1.00 35,300.00 176,500.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 400,000.00 400,000.00

JUMLAH 2,036,700.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 203,670.00
An.3 Jenis pekerjaan :Pemboran pilot hole diameter 6", 50 -- 100 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 5,900.00 442,500.00
2 Olie mesin Ltr 5.00 x 1.00 35,300.00 176,500.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 50.00 x 1.00 11,400.00 570,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,155,200.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 215,520.00

An.4 Jenis pekerjaan :Pemboran pilot hole diameter 6", 100 -- 150 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 85.00 x 1.00 5,900.00 501,500.00
2 Olie mesin Ltr 6.00 x 1.00 35,300.00 211,800.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 60.00 x 1.00 11,400.00 684,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,396,600.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 239,660.00
An.5 Jenis pekerjaan : Pekerjaan reaming, 0 -- 65 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 60.00 x 1.00 5,900.00 354,000.00
2 Olie mesin Ltr 4.00 x 1.00 35,300.00 141,200.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Bentonite Kg 40.00 x 1.00 11,400.00 456,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 1,917,400.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 191,740.00

An.6 Jenis pekerjaan : Pekerjaan reaming ,65 -- 130 m

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3 Keuangan Hari 1.00 x 1.00 50,000.00 50,000.00
4 Logistik Hari 1.00 x 1.00 50,000.00 50,000.00
5 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
6 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
7 Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
8 Buruh lokal Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 75.00 x 1.00 5,900.00 442,500.00
2 Olie mesin Ltr 6.00 x 1.00 35,300.00 211,800.00
3 Veet Kg 3.00 x 1.00 33,100.00 99,300.00
4 Bentonite Kg 55.00 x 1.00 11,400.00 627,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00

JUMLAH 2,280,600.00
1 HARI RATA-RATA 10 M' ----> JADI PER METER 228,060.00
An.7 Jenis pekerjaan : Electric logging

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1
Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2
Geologist Hari 1.00 x 1.00 60,000.00 60,000.00
3
Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
4
Crew pengeboran Hari 2.00 x 1.00 50,000.00 100,000.00
II. PERALATAN
1 Recorder paper Unit 1.00 x 1.00 20,000.00 20,000.00
2 Alat tulis Unit 1.00 x 1.00 15,000.00 15,000.00
III. PERALATAN
Mesin peralatan logging Unit 1.00 x 1.00 700,000.00 700,000.00
Tranportasi peralatan logging Unit 1.00 x 1.00 150,000.00 150,000.00

JUMLAH 1,170,000.00
1 HARI RATA-RATA 50 M' ----> JADI PER METER 23,400.00

An.8 Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 8"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 5,900.00 708,000.00
2 Olie mesin Ltr 3.00 x 1.00 35,300.00 105,900.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
Pipa jambang diameter 8" Mtr 60.00 x 578,400.00 34,704,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 36,532,100.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 608,868.33
DIBULATKAN 608,000.00
An.9 Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 6"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00 236,000.00
2 Olie mesin Ltr 1.00 x 35,300.00 35,300.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 6" Mtr 30.00 x 310,000.00 9,300,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 10,485,160.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 349,505.33
DIBULATKAN 349,000.00

An.10 Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 6"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00 236,000.00
2 Olie mesin Ltr 1.00 x 35,300.00 35,300.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 6 : Mtr 30.00 x 1,719,900.00 51,597,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 52,782,160.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,759,405.33
DIBULATKAN 1,759,000.00
An.8' Jenis pekerjaan : Pengadaan dan pemasangan pipa jambang diametr 6" (GIP)

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 120.00 x 1.00 5,900.00 708,000.00
2 Olie mesin Ltr 3.00 x 1.00 35,300.00 105,900.00
3 Veet Kg 2.00 x 1.00 33,100.00 66,200.00
4 Kawat las Btg 120.00 x 1.00 900.00 108,000.00
5 Pipa jambang diameter 6" Mtr 60.00 x 323,200.00 19,392,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 21,220,100.00
1 HARI RATA-RATA 60 M' ----> JADI PER METER 353,668.33
DIBULATKAN 353,000.00

An.9' Jenis pekerjaan : Pengadaan dan pemasangan pipa buta diametr 4" (GIP)

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00 236,000.00
2 Olie mesin Ltr 1.00 x 35,300.00 35,300.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Pipa buta diameter 4" Mtr 30.00 x 283,500.00 8,505,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 9,690,160.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 323,005.33
DIBULATKAN 323,000.00
An.10' Jenis pekerjaan : Pengad. dan pemasangan screen stainless steel diametr 4"

NO URAIAN SATUAN KUANTITAS HARGA SAT. JUML. HARGA

I UPAH
1 Site manager Hari 1.00 x 1.00 75,000.00 75,000.00
2 Operator pemboran Hari 1.00 x 1.00 50,000.00 50,000.00
3 Mekanik Hari 1.00 x 1.00 60,000.00 60,000.00
4 Crew pengeboran Hari 3.00 x 1.00 50,000.00 150,000.00
5 Penjaga malam Hari 2.00 x 1.00 40,000.00 80,000.00
II. PERALATAN
1 Solar Ltr 40.00 x 5,900.00 236,000.00
2 Olie mesin Ltr 1.00 x 35,300.00 35,300.00
3 Veet Kg 0.60 x 33,100.00 19,860.00
4 Kawat las Btg 60.00 x 900.00 54,000.00
5 Screen stainless steel dia 4" : Mtr 30.00 x 1,181,300.00 35,439,000.00
III. PERALATAN
Peralatan pemboran Unit 1.00 x 1.00 375,000.00 375,000.00
Sewa mesin las Unit 1.00 x 1.00 50,000.00 50,000.00

JUMLAH 36,624,160.00
1 HARI RATA-RATA 30 M' ----> JADI PER METER 1,220,805.33
DIBULATKAN 1,220,000.00
Analisa EI-421
KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 4.2.(1) PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0595 9,410.71 559.62


2. Mandor (L03) Jam 0.0085 11,553.57 98.15

JUMLAH HARGA TENAGA 657.77

B. BAHAN

1. Agregat A (M26) M3 1.2586 173,000.00 217,739.40

JUMLAH HARGA BAHAN 217,739.40

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 367,476.75 3,121.80


2 Dump Truck E08 Jam 0.3036 240,571.45 73,042.69
3 Motor Grader E13 Jam 0.0094 316,433.95 2,965.24
4 Tandem Roller E17 Jam 0.0119 201,556.45 2,388.82
5 Water Tanker E23 Jam 0.0141 240,571.45 3,381.53
6 Alat Bantu Ls 1.0000 32.89 32.89

JUMLAH HARGA PERALATAN 84,932.97

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 303,330.14


E. OVERHEAD & PROFIT 12.5 % x D 37,916.27
F. HARGA SATUAN PEKERJAAN ( D + E ) 341,246.41
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-422a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 4.2.(2a) PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0595 9,410.71 559.62


2. Mandor (L03) Jam 0.0085 11,553.57 98.15

JUMLAH HARGA TENAGA 657.77

B. BAHAN

1. Agregat B (M27) M3 1.2586 167,800.00 211,194.64

JUMLAH HARGA BAHAN 211,194.64

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 367,476.75 3,121.80


2 Dump Truck E08 Jam 0.3036 240,571.45 73,042.69
3 Motor Grader E13 Jam 0.0094 316,433.95 2,965.24
4 Tandem Roller E17 Jam 0.0107 201,556.45 2,158.57
5 Water Tanker E23 Jam 0.0141 240,571.45 3,381.53
6 Alat Bantu Ls 1.0000 32.89 32.89

JUMLAH HARGA PERALATAN 84,702.72

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 296,555.13


E. OVERHEAD & PROFIT 12.5 % x D 37,069.39
F. HARGA SATUAN PEKERJAAN ( D + E ) 333,624.52
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-427

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 4.2.(7) PERKIRAAN VOL. PEK. : 0


JENIS PEKERJAAN : Lapis Resap Pengikat TOTAL HARGA (Rp.) : 0
SATUAN PEMBAYARAN : Liter

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.00208333333333333 9410.71428571429 19.6056547619


2. Mandor (L03) Jam 0.00041666666666667 12267.8571428571 5.111607142857

JUMLAH HARGA TENAGA 24.71726190476

B. BAHAN

1. Aspal (M10) Kg 0.63448 13400 8502.032


2. Kerosene (M11) liter 0.484 18000 8712

JUMLAH HARGA BAHAN 17214.032

C. PERALATAN

1. Asp. Distributor E41 Jam 0.00020833333333333 296191.094024458 61.70647792176


2. Air Compresor (E05) Jam 0.00020833333333333 153871.451167315 32.05655232652

JUMLAH HARGA PERALATAN 93.76303024829

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 17332.51229215


E. OVERHEAD & PROFIT 15 % x D 2599.876843823
F. HARGA SATUAN PEKERJAAN ( D + E ) 19932.38913598
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-422c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

LISA HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 4.2.(2c) PERKIRAAN VOL. PEK. :


JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas S TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0595 9,410.71 559.62


2. Mandor (L03) Jam 0.0085 11,553.57 98.15

JUMLAH HARGA TENAGA 657.77

B. BAHAN

1. Agregat S (Sirtu) (M27) M3 1.2586 106,100.00 133,538.44

JUMLAH HARGA BAHAN 133,538.44

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 367,476.75 3,121.80


2 Dump Truck E08 Jam 0.2926 240,571.45 70,402.60
3 Motor Grader E13 Jam 0.0043 316,433.95 1,347.84
4 Tandem Roller E17 Jam 0.0054 201,556.45 1,079.28
5 Water Tanker E23 Jam 0.0141 240,571.45 3,381.53
6 Alat Bantu Ls 1.0000 32.89 32.89

JUMLAH HARGA PERALATAN 79,365.93

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 213,562.15


E. OVERHEAD & PROFIT 12.5 % x D 26,695.27
F. HARGA SATUAN PEKERJAAN ( D + E ) 240,257.42
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-611a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.1 (1)(a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Liter

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.002083333333333 9410.71428571429 19.61


2. Mandor (L03) Jam 0.000416666666667 12267.8571428571 5.11

JUMLAH HARGA TENAGA 24.72

B. BAHAN

1. Aspal (M10) Kg 0.678976 13400 9,098.28


2. Kerosene (M11) liter 0.3708 18000 6,674.40

JUMLAH HARGA BAHAN 15,772.68

C. PERALATAN

1. Asp. Distributor E41 Jam 0.000208333333333 296191.094024458 61.71


2. Compressor E05 Jam 0.000208333333333 153871.451167315 32.06

JUMLAH HARGA PERALATAN 93.76

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 15,891.16


E. OVERHEAD & PROFIT 15 % x D 2,383.67
F. HARGA SATUAN PEKERJAAN ( D + E ) 18,274.83
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-612a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 6.1 (2)(a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Lapis Perekat - Aspal Cair TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Liter

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 9,410.71 19.61


2. Mandor (L03) Jam 0.0004 11,553.57 4.81

JUMLAH HARGA TENAGA 24.42

B. BAHAN

1. Aspal (M10) Kg 0.8487 13,500.00 11,457.72


2. Kerosene (M11) liter 0.2060 13,500.00 2,781.00

JUMLAH HARGA BAHAN 14,238.72

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 296,191.09 61.71


2. Compressor E05 Jam 0.0002 153,871.45 32.06

JUMLAH HARGA PERALATAN 93.76

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 14,356.90


E. OVERHEAD & PROFIT 12.5 % x D 1,794.61
F. HARGA SATUAN PEKERJAAN ( D + E ) 16,151.52
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-621

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.2 (1) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Agregat Penutup BURTU TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.212615166548547 9410.71428571429 2,000.86


2. Mandor (L02) Jam 0.010630758327427 12267.8571428571 130.42

JUMLAH HARGA TENAGA 2,131.28

B. BAHAN

1. Chipping (M41) Kg 23 102.13285229202 2,349.06

JUMLAH HARGA BAHAN 2,349.06

C. PERALATAN

1. Wheel Loader E15 Jam 0.010630758327427 367476.74838601 3,906.56


2. Dump Truck E08 Jam 0.018924866871376 240571.451167315 4,552.78
3. P. Tyre Roller E18 Jam 0.000538466716026 241655.201167315 130.12
4. Alat Bantu Ls 1 10 10.00

JUMLAH HARGA PERALATAN 8,599.46

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 13,079.80


E. OVERHEAD & PROFIT 15 % x D 1,961.97
F. HARGA SATUAN PEKERJAAN ( D + E ) 15,041.76
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-622

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.2 (2) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Agregat Penutup BURDA TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.354358610914245 9410.71428571429 3,334.77


2. Mandor (L03) Jam 0.017717930545712 12267.8571428571 217.36

JUMLAH HARGA TENAGA 3,552.13

B. BAHAN

1. Chipping (M41) Kg 35 102.13285229202 3,574.65

JUMLAH HARGA BAHAN 3,574.65

C. PERALATAN

1. Wheel Loader E15 Jam 0.017717930545712 367476.74838601 6,510.93


2. Dump Truck E08 Jam 0.02805366318214 240571.451167315 6,748.91
3. P. Tyre Roller E18 Jam 0.001076933432052 241655.201167315 260.25
4. Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 13,520.08

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 20,646.86


E. OVERHEAD & PROFIT 15 % x D 3,097.03
F. HARGA SATUAN PEKERJAAN ( D + E ) 23,743.89
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-631

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3 (1) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Latasir Kelas A (SS-A) TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.140562248995984 9410.71428571429 1,322.79


2. Mandor (L03) Jam 0.020080321285141 12267.8571428571 246.34

JUMLAH HARGA TENAGA 1,569.13

B. BAHAN

1. Pasir Kasar M01a M3 0.208561643835616 339000 70,702.40


2. Pasir Halus M01c M3 0.417123287671233 339000 141,404.79
3 Semen (M05) Kg 31.5 2070 65,205.00
4 Aspal (M10) Kg 103 13400 1,380,200.00

JUMLAH HARGA BAHAN 1,657,512.19

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.008544642857143 240571.451167315 2,055.60
5. Asphalt Finisher E02 Jam 0.038634576787187 216912.260439046 8,380.31
6. Tandem Roller E17 Jam 0.031727445526287 201556.451167315 6,394.87
7 P. Tyre Roller E18 Jam 0.010871558528578 241655.201167315 2,627.17
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 165,926.98

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,825,008.30


E. OVERHEAD & PROFIT 15 % x D 273,751.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,098,759.55
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-632

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3 (2) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Latasir Kelas B (SS-B) TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.140562248995984 9410.71428571429 1,322.79


2. Mandor (L03) Jam 0.020080321285141 12267.8571428571 246.34

JUMLAH HARGA TENAGA 1,569.13

B. BAHAN

1. Pasir Kasar (M01a) M3 0.013923287671233 339000 4,719.99


2. Pasir Halus (M01c) M3 0.013923287671233 339000 4,719.99
3 Semen (M05) Kg 31.5 2070 65,205.00
4 Aspal (M10) Kg 92.7 13400 1,242,180.00

JUMLAH HARGA BAHAN 1,316,824.99

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.011392857142857 240571.451167315 2,740.80
5. Asphalt Finisher E02 Jam 0.028975932590391 216912.260439046 6,285.24
6. Tandem Roller E17 Jam 0.023795584144716 201556.451167315 4,796.15
7 P. Tyre Roller E18 Jam 0.008158586606456 241655.201167315 1,971.56
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 162,262.78

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,480,656.90


E. OVERHEAD & PROFIT 15 % x D 222,098.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,702,755.44
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-633a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3(3a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Lataston Lapis Aus (HRS-WC) (gradasi senjanTOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.133401901910916 9410.71428571429 1,255.41


2. Mandor (L03) Jam 0.019057414558702 12267.8571428571 233.79

JUMLAH HARGA TENAGA 1,489.20

B. BAHAN

1. Agr 5-10 & 10-15 M3 0.244014084507042 150307.015735308 36,677.03


2. Lolos screen2 ukuran ( 0 - 5) M3 0.153821656050955 169855.523602961 26,127.46
3 Pasir Halus (M01c) M3 0.248116438356164 339000 84,111.47
4 Semen (M05) Kg 23.1 2070 47,817.00
5 Aspal (M10) Kg 75.19 13400 1,007,546.00

JUMLAH HARGA BAHAN 1,202,278.96

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.258928571428571 240571.451167315 62,290.82
5. Asphalt Finisher E02 Jam 0.019057414558702 216912.260439046 4,133.79
6. Tandem Roller E17 Jam 0.015650309452429 201556.451167315 3,154.42
7 P. Tyre Roller E18 Jam 0.004308434631094 241655.201167315 1,041.16
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 217,089.21

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,420,857.37


E. OVERHEAD & PROFIT 15 % x D 213,128.61
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,633,985.98
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-634a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 6.3.(4a) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Lataston Lapis Pondasi (HRS-Base) (gradasi TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.028586121838053 9410.71428571429 269.02


2. Mandor (L03) Jam 0.00408373169115 12267.8571428571 50.10

JUMLAH HARGA TENAGA 319.11

B. BAHAN

1. Agr 5-10 & 10-15 (M92) M3 0.295774647887324 150307.015735308 44,457.00


2. Lolos screen2 ukuran ( 0 - 5(M91) M3 0.140445859872611 169855.523602961 23,855.51
3 Pasir Halus (M01c) M3 0.226541095890411 339000 76,797.43
4 Semen (M05) Kg 15.75 2070 32,602.50
5 Aspal (M10) Kg 61.8 13400 828,120.00

JUMLAH HARGA BAHAN 1,005,832.44

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.258928571428571 240571.451167315 62,290.82
5. Asphalt Finisher E02 Jam 0.00408373169115 216912.260439046 885.81
6. Tandem Roller E17 Jam 0.015751536523009 201556.451167315 3,174.82
7 P. Tyre Roller E18 Jam 0.004923925292679 241655.201167315 1,189.89
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 214,010.38

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,220,161.93


E. OVERHEAD & PROFIT 15 % x D 183,024.29
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,403,186.22
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-635a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3(5a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.200803212851406 9410.71428571429 1,889.70


2. Mandor (L03) Jam 0.020080321285141 12267.8571428571 246.34

JUMLAH HARGA TENAGA 2,136.04

B. BAHAN

1. Lolos screen2 ukuran ( 9.5 - 19,0) M3 0.297845070422535 150307.015735308 44,768.20


2. Lolos screen2 ukuran ( 0 - 5) M3 0.35231847133758 169855.523602961 59,843.24
3 Semen (M05) Kg 9.87 2070 20,430.90
4 Aspal (M10) Kg 62.83 13400 841,922.00

JUMLAH HARGA BAHAN 966,964.34

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.258928571428571 240571.451167315 62,290.82
5. Asp. Finisher E02 Jam 0.013738588728202 216912.260439046 2,980.07
6. Tandem Roller E17 Jam 0.013523923279324 201556.451167315 2,725.83
7 P. Tyre Roller E18 Jam 0.005802443060626 241655.201167315 1,402.19
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 215,867.94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,184,968.33


E. OVERHEAD & PROFIT 15 % x D 177,745.25
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,362,713.58
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-636a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3(6a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Laston Lapis Antara (AC-BC) TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.200803212851406 9410.71428571429 1,889.70


2. Mandor (L03) Jam 0.020080321285141 12267.8571428571 246.34

JUMLAH HARGA TENAGA 2,136.04

B. BAHAN

1. Lolos screen2 ukuran ( 9.5 - 19,0) M3 0.34813829787234 150307.015735308 52,327.63


2. Lolos screen2 ukuran ( 0 - 5) M3 0.31265923566879 169855.523602961 53,106.90
3 Semen (M05) Kg 9.45 2070 19,561.50
4 Aspal (M10) Kg 57.68 13400 772,912.00

JUMLAH HARGA BAHAN 897,908.03

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.258928571428571 240571.451167315 62,290.82
5. Asphalt Finisher E02 Jam 0.010990870982562 216912.260439046 2,384.05
6. Tandem Roller E17 Jam 0.010819138623459 201556.451167315 2,180.67
7 P. Tyre Roller E18 Jam 0.004641954448501 241655.201167315 1,121.75
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 214,446.32

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,114,490.40


E. OVERHEAD & PROFIT 15 % x D 167,173.56
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,281,663.95
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-637a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 6.3(7a) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Laston Lapis Pondasi (AC-Base) TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.200803212851406 9410.71428571429 1,889.70


2. Mandor (L03) Jam 0.020080321285141 12267.8571428571 246.34

JUMLAH HARGA TENAGA 2,136.04

B. BAHAN

1 Lolos screen2 ukuran ( 9.5 - 19,0) M3 0.131619718309859 134668.209441185 17,724.99


2 Lolos screen2 ukuran ( 5 - 9,5) M3 0.298140845070422 150307.015735308 44,812.66
3 Lolos screen2 ukuran ( 0 - 5) M3 0.241633757961783 169855.523602961 41,042.83
3 Semen (M05) Kg 9.975 2070 20,648.25
4 Aspal (M10) Kg 49.44 13400 662,496.00

JUMLAH HARGA BAHAN 786,724.73

C. PERALATAN
1. Wheel Loader E15 Jam 0.00957138052807 367476.74838601 3,517.26
2. AMP E01 Jam 0.020080321285141 6705026.59882663 134,639.09
3. Genset E12 Jam 0.020080321285141 413971.451167315 8,312.68
4. Dump Truck E08 Jam 0.258928571428571 240571.451167315 62,290.82
5. Asphalt Finisher E02 Jam 0.009159059152135 216912.260439046 1,986.71
6. Tandem Roller E17 Jam 0.009015948852883 201556.451167315 1,817.22
7 P. Tyre Roller E18 Jam 0.005157727165001 241655.201167315 1,246.39
8 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 213,810.18

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,002,670.95


E. OVERHEAD & PROFIT 15 % x D 150,400.64
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,153,071.59
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-661

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 6.6.(1) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Lapis Permukaan Penetrasi Macadam TOTAL HARGA : -
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1417 9,410.71 1,333.91


2. Mandor (L03) Jam 0.0142 11,553.57 163.76

JUMLAH HARGA TENAGA 1,497.67

B. BAHAN

1. Agregat Kasar (M03) M3 1.6690 157,800.00 263,370.42


2. Agregat Halus (M04) M3 0.1479 178,300.00 26,368.31
3 Aspal (M10) Kg 98.5857 13,500.00 1,330,907.14

JUMLAH HARGA BAHAN 1,620,645.88

C. PERALATAN

1. Wheel Loader E15 Jam 0.0071 367,476.75 2,604.37


2. Dump Truck E09 Jam 0.1272 240,571.45 30,598.84
3. 3-Wheel Roller E16 Jam 0.0435 143,033.95 6,219.43
4. Asp. Sprayer E03 Jam 0.3788 41,841.45 15,849.03
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 55,271.67

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,677,415.22


E. OVERHEAD & PROFIT 12.5 % x D 209,676.90
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,887,092.12
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-811

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
MATA PEMBAYARAN NO. : 8.1 (1) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Pondasi Agregat Kls. A Untuk - Pek. Minor TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 0.177179305457123 9410.71428571429 1,667.38


2. Mandor (L03) jam 0.0070871722182849 12267.8571428571 86.94

JUMLAH HARGA TENAGA 1,754.33

B. BAHAN

1. Agregat Pecah Kasar M3 1.25860927152318 140532.761801481 176,875.84

JUMLAH HARGA BAHAN 176,875.84

C. PERALATAN

1. Wheel Loader E15 jam 0.0070871722182849 367476.74838601 2,604.37


2. Dump Truck E08 jam 0.290613861919466 240571.451167315 69,913.40
3. Pedestrian Roller E24 jam 0.0526696951741392 42895.4573915947 2,259.29
4. Water Tanker E23 jam 0.0140562248995984 240571.451167315 3,381.53
5. Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 78,158.59

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 256,788.75


E. OVERHEAD & PROFIT 15 % x D 38,518.31
F. HARGA SATUAN PEKERJAAN ( D + E ) 295,307.06
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-812

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
MATA PEMBAYARAN NO. : 8.1 (2) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Pondasi Agregat Kls. B Untuk - Pek. Minor TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 0.106307583274274 9410.71428571429 1,000.43


2. Mandor (L03) jam 0.0070871722182849 12267.8571428571 86.94

JUMLAH HARGA TENAGA 1,087.37

B. BAHAN

1. Agregat Kasar (M03) M3 1.25860927152318 150307.015735308 189,177.80

JUMLAH HARGA BAHAN 189,177.80

C. PERALATAN

1. Wheel Loader E15 jam 0.0070871722182849 367476.74838601 2,604.37


2. Dump Truck E08 jam 0.290613861919466 240571.451167315 69,913.40
3. Pedestrian Roller E24 jam 0.0526696951741392 42895.4573915947 2,259.29
4. Water Tanker E23 jam 0.0140562248995984 240571.451167315 3,381.53
5. Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 78,158.59

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 268,423.76


E. OVERHEAD & PROFIT 15 % x D 40,263.56
F. HARGA SATUAN PEKERJAAN ( D + E ) 308,687.33
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-813

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (3) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : TOTAL HARGA (Rp.) : -
Agregat Utk. Lapis Pond. Jalan - Tanpa Penutup As
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 0.12742829518307 9410.71428571429 1,199.19


2. Mandor (L03) Jam 0.0084952196788713 12267.8571428571 104.22

JUMLAH HARGA TENAGA 1,303.41

B. BAHAN

1. Agregat Kelas C (M28) M3 1.2 158777 190,532.40

JUMLAH HARGA BAHAN 190,532.40

C. PERALATAN

1 Wheel Loader E15 Jam 0.0084952196788713 367476.74838601 3,121.80


2 Dump Truck E09 Jam 0.0923692212569891 435646.451167315 40,240.32
3 Pedestrian Roller E24 Jam 0.0526696951741392 42895.4573915947 2,259.29
4 Water Tanker E23 Jam 0.0140562248995984 240571.451167315 3,381.53
5 Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 49,002.94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 240,838.75


E. OVERHEAD & PROFIT 15 % x D 36,125.81
F. HARGA SATUAN PEKERJAAN ( D + E ) 276,964.56
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-815

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.1 (5) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Camp. Aspal Panas Utk.Pek.Minor TOTAL HARGA (Rp.) : -
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 1.10843373493976 9410.71428571429 10,431.15


2. Mandor (L03) Jam 0.110843373493976 12267.8571428571 1,359.81

JUMLAH HARGA TENAGA 11,790.96

B. BAHAN

1. Agregat Kasar (M03) M3 0.773055555555555 150307.015735308 116,195.67


2. Agregat Halus (M04) M3 0.527083333333333 169855.523602961 89,528.02
3 Filler (M05) Kg 25.3 2070 52,371.00
4 Aspal (M10) Kg 156.975 13400 2,103,465.00

JUMLAH HARGA BAHAN 2,361,559.69

C. PERALATAN
1. Wheel Loader E15 Jam 0.0301441058351051 367476.74838601 11,077.26
2. AMP E01 Jam 0.055421686746988 6705026.59882663 371,603.88
3. Genset E12 Jam 0.055421686746988 413971.451167315 22,943.00
4. Dump Truck E09 Jam 0.332530120481928 435646.451167315 144,865.57
5. Pedestrian Roller E24 Jam 0.197511356903022 42895.4573915947 8,472.34
6. Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 547,884.79

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,921,235.44


E. OVERHEAD & PROFIT 15 % x D 438,185.32
F. HARGA SATUAN PEKERJAAN ( D + E ) 3,359,420.76
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-817

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :
ITEM PEMBAYARAN NO. : 8.1 (7) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Penetrasi Macadam Utk.Pek.Minor TOTAL HARGA : -
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 0.1701 9,410.71 1,600.69


2. Mandor (L03) Jam 0.0170 11,553.57 196.52

JUMLAH HARGA TENAGA 1,797.21

B. BAHAN

1. Agregat Kasar (M03) M3 1.7556 157,800.00 277,026.67


2. Aspal (M10) Kg 99.2727 13,500.00 1,340,181.82

JUMLAH HARGA BAHAN 1,617,208.48

C. PERALATAN

1. Wheel Loader E15 Jam 0.0085 367,476.75 3,125.25


2. Dump Truck E09 Jam 0.1274 240,571.45 30,637.96
3. 3-Wheel Roller E16 Jam 0.0118 143,033.95 1,684.56
4. Asp. Sprayer E03 Jam 0.0359 41,841.45 1,501.49
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 36,949.26

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,655,954.95


E. OVERHEAD & PROFIT 12.5 % x D 206,994.37
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,862,949.32
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-821

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.2 (1) PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : Galian untuk Bahu Jalan & Pek. Minor Lain TOTAL HARGA (Rp.) : 56,781.88
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 1 9410.71428571429 9,410.71


2. Mandor (L03) Jam 0.1 10839.2857142857 1,083.93

JUMLAH HARGA TENAGA 10,494.64

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

1. Excavator E10 Jam 0 312098.951167315 -


2. Dump Truck E08 Jam 0.159437751004016 240571.451167315 38,356.17
3. Alat Bantu Ls 1 524.732142857143 524.73

JUMLAH HARGA PERALATAN 38,880.90

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 49,375.55


E. OVERHEAD & PROFIT 15 % x D 7,406.33
F. HARGA SATUAN PEKERJAAN ( D + E ) 56,781.88
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-814

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0

ITEM PEMBAYARAN NO. : 8.1.(4) PERKIRAAN VOL. PEK. : -


JENIS PEKERJAAN : Waterbound Macadam untuk Pekerjaan Minor TOTAL HARGA : 322,324.42
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0594665377520992 9410.71428571429 559.62


2. Mandor (L03) jam 0.0084952196788713 12267.8571428571 104.22

JUMLAH HARGA TENAGA 663.84

B. BAHAN

1. Aggregat S M27 M3 1.25860927152318 159132.169233203 200,285.22

JUMLAH HARGA BAHAN 200,285.22

C. PERALATAN
1. Wheel Loader (E15) jam 0.0084952196788713 367476.74838601 3,121.80
2. Dump Truck (E08) jam 0.292647346243779 240571.451167315 70,402.60
3. Motor Grader (E13) jam 0.0042594620907874 316433.951167315 1,347.84
4. Tandem Roller (E17) jam 0.0053547523427042 201556.451167315 1,079.28
5. Water Tanker (E23) jam 0.0140562248995984 240571.451167315 3,381.53
6. Alat Bantu Ls 1 0 -

JUMLAH HARGA PERALATAN 79,333.04

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 280,282.11


E. OVERHEAD & PROFIT 15 % x D 42,042.32
F. HARGA SATUAN PEKERJAAN ( D + E ) 322,324.42
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-842

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.4.(2).a PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : TOTAL HARGA (Rp.) : 21,159.81
Marka Jalan Bukan Termoplastic (Cat trotoar
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 0.1 9410.71428571429 941.07


2. Tukang (L02) jam 0.033333333333 10839.2857142857 361.31
3. Mandor (L03) jam 0.016666666667 12267.8571428571 204.46

JUMLAH HARGA TENAGA 1,506.85

B. BAHAN

1. Cat Minyak (M95) Kg 0.1625 68750 11,171.88


2. Thinner (M33) Liter 0.0875 18700 1,636.25

JUMLAH HARGA BAHAN 12,808.13

C. PERALATAN

2. Dump Truck E08 Jam 0.016666666667 240571.451167315 4,009.52


3. Alat Bantu Ls 1 75.3422619047619 75.34

JUMLAH HARGA PERALATAN 4,084.87

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18,399.84


E. OVERHEAD & PROFIT 15 % x D 2,759.98
F. HARGA SATUAN PEKERJAAN ( D + E ) 21,159.81
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-842

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN : 0
PEKERJAAN : 0
LOKASI : 0
ITEM PEMBAYARAN NO. : 8.4.(2).b PERKIRAAN VOL. PEK. : -
JENIS PEKERJAAN : TOTAL HARGA (Rp.) : 19,054.00
Marka Jalan Bukan Termoplastic ( Cat tembok
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 0.05 9410.71428571429 470.54


2. Tukang (L02) jam 0.016666666667 10839.2857142857 180.65
3. Mandor (L03) jam 0.008333333333 12267.8571428571 102.23

JUMLAH HARGA TENAGA 753.42

B. BAHAN

1. Cat Tembok Mowilex luar ruangan Kg 0.1125 102500 11,531.25


2. Air Liter 0.0125 27.5 0.34
3 Amplas lbr 0.125 17930 2,241.25

JUMLAH HARGA BAHAN 13,772.84

C. PERALATAN

2. Dump Truck E08 Jam 0.008333333333 240571.451167315 2,004.76


3. Alat Bantu Ls 1 37.671130952381 37.67

JUMLAH HARGA PERALATAN 2,042.43

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 16,568.70


E. OVERHEAD & PROFIT 15 % x D 2,485.30
F. HARGA SATUAN PEKERJAAN ( D + E ) 19,054.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-816a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KEGIATAN :
PEKERJAAN :
LOKASI :

ITEM PEMBAYARAN NO. : 8.1 (6)a PERKIRAAN VOL. PEK. : 1.00


JENIS PEKERJAAN : Latasir Manual dengan buruh TOTAL HARGA (Rp.) : 2,507,173.00
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 11.8644 9,410.71 111,652.54


2. Tukang (L02) Jam 1.6949 10,839.29 18,371.67
3. Kepala Tukang (L10) Jam 1.6949 11,553.57 19,582.32
4. Mandor (L03) Jam 1.6949 11,553.57 19,582.32
JUMLAH HARGA TENAGA 169,188.86

B. BAHAN

1. Pasir Kasar (Pst. Muntilan) (M01a) M3 0.2445 385,000.00 94,140.41


2. Pasir Halus (Abu batu) (M01c) M3 0.4027 172,700.00 69,553.15
3. Aspal (M10) Kg 103.0000 13,500.00 1,390,500.00
4. Lapis Perekat (EI-612a) Liter 6.0606 16,151.52 97,887.97
5. Kayu Bakar M3 0.9685 403,500.00 390,799.03

JUMLAH HARGA BAHAN 2,042,880.57

C. PERALATAN
1. Dump Truck E08 Jam 0.0041 240,571.45 992.36
2. Tandem Roller E17 Jam 0.0351 201,556.45 7,076.99
3. Alat Bantu Ls 1.0000 8,459.44 8,459.44
4.
5.
6.
7
8

JUMLAH HARGA PERALATAN 16,528.79

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,228,598.22


E. OVERHEAD & PROFIT 12.5 % x D 278,574.78
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,507,173.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.