HARGA
NO. J E N I S B A H A N SATUAN KET.
(Rp)
1 Pekerja Hr 68,000
2 Mandor Hr 84,000
3 Tukang listrik Hr 74,000
4 Tukang kayu Hr 74,000
5 Kep. tk. kayu Hr 80,000
6 Tukang batu Hr 74,000
7 Kep. tk. batu Hr 80,000
8 Tukang besi Hr 74,000
9 Kep. tk. besi Hr 80,000
10 T u k a n g c a t Hr 74,000
11 K e p . t k . c a t Hr 80,000
12 T u k a n g p l i t u r Hr 74,000
13 T u k a n g j a l a n Hr 68,000
14 T u k a n g g a l i Hr 68,000
15 Tukang masak aspal Hr 68,000
16 T k . l e i d e n g Hr 74,000
17 M a s i n i s / Operator Hr 74,000
18 P e m b . M a s i n i s Hr 68,000
19 P e n j a g a a p i Hr 68,000
20 P e n j a g a m a l a m Hr 68,000
21 Sopir Hr 74,000
22 Pembantu Sopir Hr 68,000
23 Juru Ukur Hr 74,000
24 Pembantu Juru Ukur Hr 68,000
25 Operator Alat Berat Hr 220,000
Tim Survey
3 Eko Prayitno, ST 3
4 Teguh Achmad Sumarsono, ST 4
5 Iksanudin, S.ST, MT
5
6 Bachtiar Achmad, ST, Mec, Dev 6
7 Agus Muslim, ST 7
8 Suparno 8
Kebumen,
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 210,000
Bulat Belah m3 210,000
Pecah 10/15 m3 225,000
Pecah 5/7 m3 250,000
Pecah 3/5 m3 300,000
2 KERIKIL Timbun/Sirtu m3 180,000
Sawur / Koral m3 180,000
Beton 0,5/1 m3 270,000
Beton ,1/2 m3 310,000
Beton ,2/3 m3 325,000
Biasa m3 210,000
Tras Giling m3 160,000
3 BATU BATA ex lokal bh 800
Vlaam bh 1,800
Kodok bh 2,000
Kodok Glasur bh 3,500
Nok kerpus Kodok bh 3,500
Nok kerpus Kodok Glasur bh 6,000
Plentong super besar 18 bh/m2 bh 2,700
Nok kerpus plentong super bh 3,500
Genteng Magase bh 2,000
Genteng Magaze glazur bh 4,800
Genteng Morando biasa bh 2,700
Genteng Morando glazur bh 5,600
4 ASBES GELOMBANG BESAR
180 X 92 cm bh 47,500
200 X 92 cm bh 57,250
250 X 92 cm bh 66,000
180 X 105 cm bh 66,500
210 X 105 cm bh 66,800
250 X 105 cm bh 75,000
8 SENG PLAT
Balok/pesagen m3 9,500,000
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
PC polos 30 X 30 cm m2 55,000
20 X 20 cm m2 60,000
PC warna 30 X 30 cm m2 65,000
20 X 20 cm m2 63,000
Teraso 30 X 30 cm m2 70,000
2 UBIN PORSELIN
10 X 20 cm m2 75,000
15 X 15 cm m2 80,000
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
20 X 20 cm m2 83,000
20 X 25 cm m2 85,000
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
4 Keramik 30 X 30 cm m2 60,000
20 X 20 cm m2 70,000
33 x 33 cm m2 85,000
40 x 40 cm m2 100,000
25 x 25 cm m2 83,000
15 x 20 cm m2 80,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 75,000
Ø 20 cm - 100 cm bh 80,000
Ø 30 cm - 100 cm bh 85,000
Ø 50 cm - 100 cm bh 132,000
Ø 60 cm - 100 cm bh 220,000
Ø 70 cm - 100 cm bh 285,000
U 10 cm - 100 cm bh 50,000
U 15 cm - 100 cm bh 70,000
U 20 cm - 100 cm bh 85,000
U 30 cm - 100 cm bh 105,000
U 50 cm - 100 cm bh 135,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 12,500
besi beton prestress kg 12,500
besi beton ulir kg 12,500
Diameter 4 - 15 kg 12,900
Diameter 6 - 15 kg 12,900
Kawat bronjong Φ 3 mm kg 20,000
Kawat bronjong Φ 4 mm kg 20,000
5 BESI SIKU L 40 X 40 X 4 btg 75,000
L 50 X 50 X 5 btg 105,000
L 60 X 60 X 6 btg 235,000
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
3 Pipa PVC AW
4 Pipa HDPE
VIII . B A H A N L A N G I T - L A N G I T
1 PLY WOOD
Teak wood
Menie kg 28,000
Dempul plamur kg 30,000
Ambril/amplas lbr 3,000
Batu Apung kg 27,500
Cat dasar kg 52,500
. Emco kg 50,000
. Yunior 66 (nippon paint) kg 52,500
. Kuas bh 9,500
. Deculux kg 52,500
. Siralax ons 9,500
. Spiritus ltr 14,250
. Plitur jadi ltr 54,500
2 TEMBOK
Kalkarium kg 5,700
Kapur sirih kg 2,900
Plamur kg 28,500
Cat Tembok kg 23,500
Sintex 5 kg 21,000
Danabride 5 kg 21,000
Catylac 5 kg 32,000
Mowilex 2,5 kg 38,000
3 BESI
Menie kg 38,000
Cat mengkilat kg 57,000
Cat kg 57,000
Thinner A ltr 21,000
Minyak cat ltr 23,500
Thinner Super ltr 28,500
Residu (teer/aspal) drum 14,500
Fibre glass (tanki air)
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
2 ES KABUR 3 mm m2 71,500
5 mm m2 89,000
10 K A C A
Cermin 5 mm m2 140,000
Cangkul Bh 124,000
Sabit Bh 70,000
Cakar (tanpa gagang) Bh 85,000
Karung plastik Lbr 6,900
Mesin Potong Rumput Gendong (Honda ) Bh 4,000,000
Seal tape Bh 7,500
HARGA
NO. J E N I S B A H A N SATUAN KETERANGAN
(Rp)
XIV PERALATAN
Tim Survey
3 Eko Prayitno, ST 3
5 Iksanudin, S.ST, MT 5
7 Agus Muslim, ST 7
8 Suparno 8
Kebumen,
JUMLAH
No. SNI KODE SAT. URAIAN PEKERJAAN
Rp
I A.1 HARGA SATUAN PEKERJAAN TANAH
A.1.1 PEKERJAAN TANAH SECARA MANUAL
19 T.09.a.2 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 2 m 116,983.68
20 T.09.a.3 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 3 m 126,060.00
21 T.09.a.4 m3 GALIAN TANAH CADAS ATAU TANAH KERAS dg kedalaman > 3 m, 8,404.00
39 T.09.b.2 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 2 m 37,771.80
40 T.09.b.3 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 3 m 44,495.00
41 T.09.d m3 GALIAN TANAH CADAS ATAU TANAH KERAS dg kedalaman > 3 m, 10,879.00
42 T.12.a m' PERKUATAN DINDING GALIAN UNT 1 m' PALING BAWAH 1,431,720.40
45 T.12.d m' PERKUATAN DINDING GALIAN DG TURAP UNTUK PENAMBAHAN TINGGI 287,298.00
50 T.15.a.1 m3 MENGANGKUT HASIL GALIAN DG JARAK ANGKUT > 3m S/D < 5 m 19,696.16
P.06.a.1
98 c) 1.5 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat pengikat 2,004,167.00
102 P.06.a.7 1 m3 Pasangan bronjong pabrikasi (tenaga kerja untuk 1m3 batu bronjong) 727,760.00
JUMLAH
No. SNI KODE SAT. URAIAN PEKERJAAN
Rp
P.06 PASANGAN BATU BRONJONG KAWAT (SNI 03-0009-1999)
103 a) 2.04 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,498,535.60
104 b) 2.04 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,177,568.80
105 a) 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,274,188.40
106 b) 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,536,903.60
107 a) 3.6 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,643,665.20
108 b) 3.6 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 3,197,642.80
109 P.06.b.4) 1 m3 Pasangan bronjong pabrikasi (tenaga kerja untuk 1m3 batu 786,962.00
bronjong)
PEKERJAAN BETON
B.02 1 m3 Beton Mutu f'c=7,4 Mpa (K100), slump (12±2) cm, w/c =0,87
2 a) Manual 964,290.25
B.03 1 m3 Beton Mutu f'c=9,8 Mpa (K125), slump (12±2) cm, w/c =0,78
4 a) Manual 993,364.41
B.04 1 m3 Beton Mutu f'c=12,2 Mpa (K150), slump (12±2) cm, w/c =0,72
6 Manual 1,016,011.20
B.05 1 m3 Beton Mutu f'c=14,5 Mpa (K175), slump (12±2) cm, w/c =0,66
8 Manual 1,042,934.84
B.06 1 m3 Beton Mutu f'c=16,9 Mpa (K200), slump (12±2) cm, w/c =0,61
10 a) Manual 1,068,549.18
B.07 1 m3 Beton Mutu f'c=19,3 Mpa (K225), slump (12±2) cm, w/c =0,58
12 a) Manual 1,088,055.79
14 a) Manual 1,100,683.56
16 a) Manual 1,122,754.68
18 a) Manual 1,129,430.75
20 a) Manual 1,199,749.38
22 a) Manual 1,208,668.64
PEKERJAAN BETON
a) dg Ketinggian/kedalaman < 1m
Manual 34,456.40
Manual 42,020.00
a) Vibrator 37,510.00
a) Manual 21,010.00
12 B.20
PEKERJAAN BEKISTING
Tanpa perancah
7 B.23.d 1 m2 Perancah Beksiting balok dengan kaso 5/7 tinggi 4m' 79,041.60
Multipleks 12 cm / 18 cm
Papan 3/20 cm
Multipleks 12 cm / 18 cm
Papan 3/20 cm
BONGKAR BEKISTING
Bongkar Beksiting tiap m2 diambil untuk kondisi biasa 10% - 15% dari Upah Kerja Pemasangan
untuk pembongkaran material pakai ulang maka biaya bongkar 20% - 25% dari Upah Pemasangan
dengan hati-hati
2 F.03 1 m' Tiang pancang baja pipa atau kotak Ø 30cm 773,300.00
11 F.11 1 m' Tiang pancang baja pipa atau kotak Ø 30cm 745,991.95
Tim Survey
3 Eko Prayitno, ST 3
5 Iksanudin, S.ST, MT 5
7 Agus Muslim, ST 7
8 Suparno 8
Kebumen,
KABUPATEN KEBUMEN
JUMLAH
No. SNI KODE SAT. URAIAN PEKERJAAN
Rp
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
A.1 HARGA SATUAN PEKERJAAN TANAH
A.1.1 PEKERJAAN TANAH SECARA MANUAL
a AHSP PEMBERSIHAN & PENGUPASAN PERMUKAAN TANAH
1 T.01.a 1 m2 PEMBERSIHAN DAN STRIPING / KOSREKAN 5,042.40
A TENAGA 4,584.00
L.01 0.060 OH Pekerja 68,000.00 4,080.00
L.04 0.006 OH Mandor 84,000.00 504.00
B BAHAN -
C PERALATAN
D Jumlah A + B + C 4,584.00
E OVERHEAD & PROFIT (CONTOH) 10% 458.40
F Harga Satuan Pekerjaan (D+E) 5,042.40
B BAHAN 128.70
0.010 ltr Minyak Tanah 12,870.00 128.70
C PERALATAN
D Jumlah A + B + C 5,858.70
E OVERHEAD & PROFIT (CONTOH) 10% 585.87
F Harga Satuan Pekerjaan (D+E) 6,444.57
B BAHAN -
-
C PERALATAN 3,000
0.100 hari Chainswaw 30,000 3,000
D Jumlah A + B + C 18,280.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,828.00
F Harga Satuan Pekerjaan (D+E) 20,108.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 43,013.20
E OVERHEAD & PROFIT (CONTOH) 10% 4,301.32
F Harga Satuan Pekerjaan (D+E) 47,314.52
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 51,570.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,157.00
F Harga Satuan Pekerjaan (D+E) 56,727.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
8 T.06.a.3 1 m3 GALIAN TANAH BIASA sedalam s/d 3 m 63,870.40
A TENAGA 58,064.00
L.01 0.7600 OH Pekerja 68,000 51,680.00
L.04 0.0760 OH Mandor 84,000 6,384.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 58,064.00
E OVERHEAD & PROFIT (CONTOH) 10% 5,806.40
F Harga Satuan Pekerjaan (D+E) 63,870.40
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 5,730.00
E OVERHEAD & PROFIT (CONTOH) 10% 573.00
F Harga Satuan Pekerjaan (D+E) 6,303.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 103,216.40
E OVERHEAD & PROFIT (CONTOH) 10% 10,321.64
F Harga Satuan Pekerjaan (D+E) 113,538.04
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 10,696.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,069.60
F Harga Satuan Pekerjaan (D+E) 11,765.60
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 286,500.00
E OVERHEAD & PROFIT (CONTOH) 10% 28,650.00
F Harga Satuan Pekerjaan (D+E) 315,150.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 315,192.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
E OVERHEAD & PROFIT (CONTOH) 10% 31,519.20
F Harga Satuan Pekerjaan (D+E) 346,711.20
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 95,500.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,550.00
F Harga Satuan Pekerjaan (D+E) 105,050.00
19 T.09.a.2 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 2 m 116,983.68
A TENAGA 106,348.80
L.01 1.3920 OH Pekerja 68,000 94,656.00
L.04 0.1392 OH Mandor 84,000 11,692.80
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 106,348.80
E OVERHEAD & PROFIT (CONTOH) 10% 10,634.88
F Harga Satuan Pekerjaan (D+E) 116,983.68
20 T.09.a.3 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 3 m 126,060.00
A TENAGA 114,600.00
L.01 1.5000 OH Pekerja 68,000 102,000.00
L.04 0.1500 OH Mandor 84,000 12,600.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 114,600.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,460.00
F Harga Satuan Pekerjaan (D+E) 126,060.00
21 T.09.a.4 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS dg kedalaman > 3 m, 8,404.00
TAMBAHAN KOEFISIEN UNT SETIAP PENAMBAHAN KEDALAMAN 1 m
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
A TENAGA 7,640.00
L.01 0.1000 OH Pekerja 68,000 6,800.00
L.04 0.0100 OH Mandor 84,000 840.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 7,640.00
E OVERHEAD & PROFIT (CONTOH) 10% 764.00
F Harga Satuan Pekerjaan (D+E) 8,404.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 63,412.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,341.20
F Harga Satuan Pekerjaan (D+E) 69,753.20
B BAHAN -
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
C PERALATAN -
D Jumlah A + B + C 11,460.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,146.00
F Harga Satuan Pekerjaan (D+E) 12,606.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 61,120.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,112.00
F Harga Satuan Pekerjaan (D+E) 67,232.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 70,288.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,028.80
F Harga Satuan Pekerjaan (D+E) 77,316.80
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 40,450.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,045.00
F Harga Satuan Pekerjaan (D+E) 44,495.00
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 44,270.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,427.00
F Harga Satuan Pekerjaan (D+E) 48,697.00
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 14,474.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,447.40
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
F Harga Satuan Pekerjaan (D+E) 15,921.40
B BAHAN -
C PERALATAN 4,500.00
0.2500 hr Jack hammer 18,000 4,500.00
D Jumlah A + B + C 80,900.00
E OVERHEAD & PROFIT (CONTOH) 10% 8,090.00
F Harga Satuan Pekerjaan (D+E) 88,990.00
B BAHAN -
C PERALATAN 4,500.00
0.2500 hr Jack hammer 18,000 4,500.00
D Jumlah A + B + C 96,180.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,618.00
F Harga Satuan Pekerjaan (D+E) 105,798.00
B BAHAN -
C PERALATAN 4,500.00
0.2500 hr Jack hammer 18,000 4,500.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
D Jumlah A + B + C 33,150.00
E OVERHEAD & PROFIT (CONTOH) 10% 3,315.00
F Harga Satuan Pekerjaan (D+E) 36,465.00
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 26,698.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,669.80
F Harga Satuan Pekerjaan (D+E) 29,367.80
39 T.09.b.2 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 2 m 37,771.80
A TENAGA 32,088.00
L.01 0.4200 OH Pekerja 68,000 28,560.00
L.04 0.0420 OH Mandor 84,000 3,528.00
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 34,338.00
E OVERHEAD & PROFIT (CONTOH) 10% 3,433.80
F Harga Satuan Pekerjaan (D+E) 37,771.80
40 T.09.b.3 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS sedalam s/d 3 m 44,495.00
A TENAGA 38,200.00
L.01 0.5000 OH Pekerja 68,000 34,000.00
L.04 0.0500 OH Mandor 84,000 4,200.00
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 40,450.00
E OVERHEAD & PROFIT (CONTOH) 10% 4,045.00
F Harga Satuan Pekerjaan (D+E) 44,495.00
41 T.09.d 1 m3 GALIAN TANAH CADAS ATAU TANAH KERAS dg kedalaman > 3 m, 10,879.00
TAMBAHAN KOEFISIEN UNT SETIAP PENAMBAHAN KEDALAMAN 1 m
A TENAGA 7,640.00
L.01 0.1000 OH Pekerja 68,000 6,800.00
L.04 0.0100 OH Mandor 84,000 840.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
B BAHAN -
C PERALATAN 2,250.00
0.1250 hr Jack hammer 18,000 2,250.00
D Jumlah A + B + C 9,890.00
E OVERHEAD & PROFIT (CONTOH) 10% 989.00
F Harga Satuan Pekerjaan (D+E) 10,879.00
T.12 PERKUAT DINDING GALIAN SANGAT TERGANTUNG PADA POTENSI GALIAN TANAHNYA,
- UNT TANAH BIASA & TANAH BERBATU SERING DIPERLUKAN JIKA KEDALAMAN GALIAN LEBIH DARI 2 m
- UNT TANAH CADAS / KERAS APALAGI BATU PADA UMUMNYA TIDAK DIPERLUKAN PERKUATAN
HAL INI SERING DILAKUKAN PADA GALIAN TANAH DENGAN KEDALAMAN > 1 m DALAM RANGKA PEMASANGAN
PIPA, GORONG-GORONG ATAU BOX CULVERT
TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN RANGKA & DINDING
A.2 a) TIANG RANGKA PERKUATAN DINDING
BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)
1 KASO 5/7 DIPAKAI 1 KALI 0.04200 m3 0.0150 m3
- DIPAKAI KE 2 0.02840 m3 0.860 OH 0.430 OH 0.086 OH 0.125 0.0101 m3 0.800 OH 0.300 OH 0.080 OH 0.120 0.5
4.080 kg 1.000 OH 0.500 OH 0.100 OH 0.120 2.720 kg 0.72 OH 0.38 OH 0.072 OH 0.110 0.8
2.970 kg 1.980 kg
5.240 kg 1.980 kg
b) DINDING PERKUATAN
1 m' PALING BAWAH SETIAP PENAMBAHAN TINGGI 1 m'
NO. BAHAN a) b) c) d) e) f) g) h) i) j)
BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN
1 SESEG BAMBU KE-1 2.40 m2 2.00 m2
KE-2 1.80 m2 0.400 OH 0.200 OH 0.040 OH 0.06 1.50 m2 0.300 OH 0.150 OH 0.030 OH 0.050
KE-3 1.60 m2 1.33 m2
KE-2 0.130 m3 0.480 OH 0.230 OH 0.045 OH 0.09 0.108 m3 0.338 OH 0.169 OH 0.0338 OH 0.080
KE-3 0.109 m3 0.091 m3
TABEL KOEFISIEN PEKERJAAN & BAHAN PERKUATAN DINDING GALIAN DENGAN TURAP
A.3
BAHAN PEKERJA TUKANG MANDOR PERALATAN BAHAN PEKERJA TUKANG MANDOR PERALATAN (m)
1 KASO 5/7 DIPAKAI KE-1 0.049612 m3 0.033075 m3
KE-2 0.033488 m3 0.840 OH 0.280 OH 0.084 OH 0.10 0.022326 m3 0.570 OH 0.190 OH 0.057 OH 0.070 5
KE-3 0.028130 m3 0.018754 m3
15.00 kg 10.00 kg
4 BAJA INP-10 52.500 kg 35.000 kg
28.860 kg 2.100 OH 0.700 OH 0.210 OH 0.160 19.220 kg 1.5 OH 0.5 OH 0.15 OH 0.120 5
21.000 kg 14.000 kg
28.750 kg 19.160 kg
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8= 4 X 7
42a T.12.a 1 m' PERKUATAN DINDING GALIAN UNT 1 m' PALING BAWAH
A TENAGA
L.01 b) + g) OH Pekerja (tabel A.2)
L.02 c) + h) OH Tukang
L.04 d) + i) OH Mandor
B BAHAN -
a) m3/kg Tiang rangka Perkuatan Dinding (Tabel A.2)
f) m2/m3 Dinding Perkuatan (tabel.A.2)
C PERALATAN -
e) + j) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C -
E OVERHEAD & PROFIT (CONTOH) 10% -
F Harga Satuan Pekerjaan (D+E) -
42 T.12.a 1 m' PERKUATAN DINDING GALIAN UNT 1 m' PALING BAWAH 1,431,720.40
contoh MENGGUNAKAN BAJA INP-10 & BALOK KAYU 8/12
A TENAGA 180,844.00
L.01 1.660 OH Pekerja 68,000 112,880.00
L.02 0.730 OH Tukang 74,000 54,020.00
L.04 0.166 OH Mandor 84,000 13,944.00
B BAHAN 1,103,620.00
5.240 kg Tiang perkuatan dengan INP -10 13,000 68,120.00
0.109 m3 Dinding perkuatan kayu 8/12 9,500,000 1,035,500.00
C PERALATAN 17,100.00
0.190 hr Crane 2 ton 90,000 17,100.00
D Jumlah A + B + C 1,301,564.00
E OVERHEAD & PROFIT (CONTOH) 10% 130,156.40
F Harga Satuan Pekerjaan (D+E) 1,431,720.40
C PERALATAN -
e) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C -
E OVERHEAD & PROFIT (CONTOH) 10% -
F Harga Satuan Pekerjaan (D+E) -
45a T.12.d 1 m' PERKUATAN DINDING GALIAN DG TURAP UNTUK PENAMBAHAN TINGGI
A TENAGA
L.01 g) OH Pekerja (Tabel A.3)
L.02 h) OH Tukang
L.04 i) OH Mandor
B BAHAN -
f) m3/kg Perkuatan Dinding galian dg Turap (Tabel A.3)
C PERALATAN -
j) hr Tripod/Tackle Handle/Crane 2 ton
D Jumlah A + B + C -
E OVERHEAD & PROFIT (CONTOH) 10% -
F Harga Satuan Pekerjaan (D+E) -
45 T.12.d 1 m' PERKUATAN DINDING GALIAN DG TURAP UNTUK PENAMBAHAN TINGGI 287,298.00
contoh MENGGUNAKAN TURAP BAJA INP-8
A TENAGA 121,280.00
L.01 1.200 OH Pekerja 68,000 81,600.00
L.02 0.400 OH Tukang 74,000 29,600.00
L.04 0.120 OH Mandor 84,000 10,080.00
B BAHAN 130,000.00
10.00 kg Perkuatan Dinding galian dg Turap (Tabel A.3) 13,000 130,000.00
-
C PERALATAN 9,900.00
0.110 hr Crane 2 ton 90,000 9,900.00
D Jumlah A + B + C 261,180.00
E OVERHEAD & PROFIT (CONTOH) 10% 26,118.00
F Harga Satuan Pekerjaan (D+E) 287,298.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
C PERALATAN -
D Jumlah A + B + C 25,212.00
E OVERHEAD & PROFIT (CONTOH) 10% 2,521.20
F Harga Satuan Pekerjaan (D+E) 27,733.20
C PERALATAN -
D Jumlah A + B + C 17,905.60
E OVERHEAD & PROFIT (CONTOH) 10% 1,790.56
F Harga Satuan Pekerjaan (D+E) 19,696.16
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 8=4X7
D Jumlah A + B + C 25,703.20
E OVERHEAD & PROFIT (CONTOH) 10% 2,570.32
F Harga Satuan Pekerjaan (D+E) 28,273.52
C PERALATAN -
D Jumlah A + B + C 30,468.40
E OVERHEAD & PROFIT (CONTOH) 10% 3,046.84
F Harga Satuan Pekerjaan (D+E) 33,515.24
C PERALATAN -
D Jumlah A + B + C 119,130.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,913.00
F Harga Satuan Pekerjaan (D+E) 131,043.00
98 c) 1.5 m3 Kawat Bronjong wire mesh 5 mm ulir & kawat pengikat 2,004,167.00
2,0mm, ukuran lobang heksagonal 100 x 100 mm
A TENAGA 610,820.00
L.01 5.250 OH Pekerja Penganyam 68,000 357,000.00
L.02 1.750 OH Tukang Penganyam 74,000 129,500.00
L.01 1.050 OH Pekerja Pengisi Batu 68,000 71,400.00
L.04 0.630 OH Mandor 84,000 52,920.00
B BAHAN 1,211,150.00
1.95 m3 Batu 225,000 438,750.00
38.62 kg Kawat Bronjong Ø 2,7 mm 20,000 772,400.00
C PERALATAN -
-
D Jumlah A + B + C 1,821,970.00
E OVERHEAD & PROFIT (CONTOH) 10% 182,197.00
F Harga Satuan Pekerjaan (D+E) 2,004,167.00
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
P.06.a.6 Bentuk I, tipe F Bronjong kawat
Uk.L=4.0m x B=1.0m x T=0.5m berisi Batu (buat sendiri)
99 a) 2 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 1,575,035.00
Uk.2,70 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 269,690.00
L.01 2.175 OH Pekerja Penganyam 68,000 147,900.00
L.02 0.725 OH Tukang Penganyam 74,000 53,650.00
L.01 0.650 OH Pekerja Pengisi Batu 68,000 44,200.00
L.04 0.285 OH Mandor 84,000 23,940.00
B BAHAN 1,162,160.00
2.60 m3 Batu 225,000 585,000.00
28.858 kg Kawat Bronjong Ø 2,7 mm 20,000 577,160.00
C PERALATAN -
-
D Jumlah A + B + C 1,431,850.00
E OVERHEAD & PROFIT (CONTOH) 10% 143,185.00
F Harga Satuan Pekerjaan (D+E) 1,575,035.00
104 b) 2.04 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,177,568.80
Uk.2,7 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 368,988.00
L.01 3.150 OH Pekerja Penganyam 68,000 214,200.00
L.02 1.050 OH Tukang Penganyam 74,000 77,700.00
L.01 0.663 OH Pekerja Pengisi Batu 68,000 45,084.00
L.04 0.381 OH Mandor 84,000 32,004.00
B BAHAN 1,610,620.00
2.652 m3 Batu 225,000 596,700.00
50.696 kg Kawat Bronjong Ø 2,7 mm 20,000 1,013,920.00
C PERALATAN -
-
D Jumlah A + B + C 1,979,608.00
E OVERHEAD & PROFIT (CONTOH) 10% 197,960.80
F Harga Satuan Pekerjaan (D+E) 2,177,568.80
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
P.06.b.2 Bentuk II, tipe H Bronjong kawat
Uk.L=6.0m x B=2.0m x T=0.23m berisi Batu (buat sendiri)
105 a) 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,274,188.40
Uk.2,00 mm, kwat sisi 3,40 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 60 x 80 mm
A TENAGA 474,844.00
L.01 4.020 OH Pekerja Penganyam 68,000 273,360.00
L.02 1.340 OH Tukang Penganyam 74,000 99,160.00
L.01 0.897 OH Pekerja Pengisi Batu 68,000 60,996.00
L.04 0.492 OH Mandor 84,000 41,328.00
B BAHAN 1,592,600.00
3.588 m3 Batu 225,000 807,300.00
39.265 kg Kawat Bronjong Ø 2,0 mm 20,000 785,300.00
C PERALATAN -
-
D Jumlah A + B + C 2,067,444.00
E OVERHEAD & PROFIT (CONTOH) 10% 206,744.40
F Harga Satuan Pekerjaan (D+E) 2,274,188.40
106 b) 2.76 m3 Kawat Bronjong galvanis dg kawat anyaman tiga lilitan 2,536,903.60
Uk.2,7 mm, kwat sisi 4,0 mm & kawat pengikat
2,0mm, ukuran lobang heksagonal 80 x 100 mm
A TENAGA 432,396.00
L.01 3.600 OH Pekerja Penganyam 68,000 244,800.00
L.02 1.200 OH Tukang Penganyam 74,000 88,800.00
L.01 0.897 OH Pekerja Pengisi Batu 68,000 60,996.00
L.04 0.450 OH Mandor 84,000 37,800.00
B BAHAN 1,873,880.00
3.588 m3 Batu 225,000 807,300.00
53.329 kg Kawat Bronjong Ø 2,7 mm 20,000 1,066,580.00
C PERALATAN -
-
D Jumlah A + B + C 2,306,276.00
E OVERHEAD & PROFIT (CONTOH) 10% 230,627.60
F Harga Satuan Pekerjaan (D+E) 2,536,903.60
109 P.06.b.4) 1 m3 Pasangan bronjong pabrikasi (tenaga kerja untuk 1m3 batu 786,962.00
bronjong)
A TENAGA 22,920.00
L.01 0.300 OH Pekerja 68,000 20,400.00
L.04 0.030 OH Mandor 84,000 2,520.00
B BAHAN 692,500.00
1.30 m3 Batu 225,000 292,500.00
1.00 bh Kawat Bronjong Pabrikasi dia,3,0 400,000 400,000.00
C PERALATAN -
-
D Jumlah A + B + C 715,420.00
E OVERHEAD & PROFIT (CONTOH) 10% 71,542.00
F Harga Satuan Pekerjaan (D+E) 786,962.00
A TENAGA 21,600.00
L.01 0.240 OH Pekerja 68,000 16,320.00
B BAHAN 14,190.00
C PERALATAN -
-
D Jumlah A + B + C 35,790.00
A TENAGA 77,500.00
C PERALATAN 9,950.00
D Jumlah A + B + C 421,250.00
E OVERHEAD & PROFIT (CONTOH) 10% 42,125.00
2 B.02 1 m3 Beton Mutu f'c=7,4 Mpa (K100), slump (12±2) cm, w/c =0,87 964,290.25
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
B BAHAN 727,977.50
247 kg PC/Portlan Cement 1,140 281,580.00
0.621 m3 PB/Pasir Beton 330,000 204,930.00
0.740 m3 Kr/Krikil 325,000 240,500.00
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 876,627.50
E OVERHEAD & PROFIT (CONTOH) 10% 87,662.75
F Harga Satuan Pekerjaan (D+E) 964,290.25
3 B.02 1 m3 Beton Mutu f'c=7,4 Mpa (K100), slump (12±2) cm, w/c =0,87 949,201.55
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 727,977.50
247 kg PC/Portlan Cement 1,140 281,580.00
0.621 m3 PB/Pasir Beton 330,000 204,930.00
0.740 m3 Kr/Krikil 325,000 240,500.00
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 862,910.50
E OVERHEAD & PROFIT (CONTOH) 10% 86,291.05
F Harga Satuan Pekerjaan (D+E) 949,201.55
4 B.03 1 m3 Beton Mutu f'c=9,8 Mpa (K125), slump (12±2) cm, w/c =0,78 993,364.41
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
B BAHAN 754,408.56
276 kg PC/Portlan Cement 1,140 314,640.00
828 kg PB/Pasir Beton 236 195,171.43
1,012 kg Kr/Krikil 241 243,629.63
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 903,058.56
E OVERHEAD & PROFIT (CONTOH) 10% 90,305.86
F Harga Satuan Pekerjaan (D+E) 993,364.41
5 B.03 1 m3 Beton Mutu f'c=9,8 Mpa (K125), slump (12±2) cm, w/c =0,78 978,275.71
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 754,408.56
276 kg PC/Portlan Cement 1,140 314,640.00
828 kg PB/Pasir Beton 236 195,171.43
1,012 kg Kr/Krikil 241 243,629.63
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 889,341.56
E OVERHEAD & PROFIT (CONTOH) 10% 88,934.16
F Harga Satuan Pekerjaan (D+E) 978,275.71
6 B.04 1 m3 Beton Mutu f'c=12,2 Mpa (K150), slump (12±2) cm, w/c =0,72 1,016,011.20
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
B BAHAN 774,996.55
299 kg PC/Portlan Cement 1,140 340,860.00
799 kg PB/Pasir Beton 236 188,335.71
1,017 kg Kr/Krikil 241 244,833.33
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 923,646.55
E OVERHEAD & PROFIT (CONTOH) 10% 92,364.65
F Harga Satuan Pekerjaan (D+E) 1,016,011.20
7 B.04 1 m3 Beton Mutu f'c=12,2 Mpa (K150), slump (12±2) cm, w/c =0,72 1,000,922.50
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 774,996.55
299 kg PC/Portlan Cement 1,140 340,860.00
799 kg PB/Pasir Beton 236 188,335.71
1,017 kg Kr/Krikil 241 244,833.33
215 lt Air 4.50 967.50
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 909,929.55
E OVERHEAD & PROFIT (CONTOH) 10% 90,992.95
F Harga Satuan Pekerjaan (D+E) 1,000,922.50
8 B.05 1 m3 Beton Mutu f'c=14,5 Mpa (K175), slump (12±2) cm, w/c =0,66 1,042,934.84
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
B BAHAN 799,472.58
326 kg PC/Portlan Cement 1,140 371,640.00
760 kg PB/Pasir Beton 236 179,142.86
1,029 kg Kr/Krikil 241 247,722.22
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 948,122.58
E OVERHEAD & PROFIT (CONTOH) 10% 94,812.26
F Harga Satuan Pekerjaan (D+E) 1,042,934.84
9 B.05 1 m3 Beton Mutu f'c=14,5 Mpa (K175), slump (12±2) cm, w/c =0,66 1,027,846.14
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 799,472.58
326 kg PC/Portlan Cement 1,140 371,640.00
760 kg PB/Pasir Beton 236 179,142.86
1,029 kg Kr/Krikil 241 247,722.22
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 934,405.58
E OVERHEAD & PROFIT (CONTOH) 10% 93,440.56
F Harga Satuan Pekerjaan (D+E) 1,027,846.14
10 B.06 1 m3 Beton Mutu f'c=16,9 Mpa (K200), slump (12±2) cm, w/c =0,61 1,068,549.18
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
B BAHAN 822,758.35
352 kg PC/Portlan Cement 1,140 401,280.00
731 kg PB/Pasir Beton 236 172,307.14
1,031 kg Kr/Krikil 241 248,203.70
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 971,408.35
E OVERHEAD & PROFIT (CONTOH) 10% 97,140.83
F Harga Satuan Pekerjaan (D+E) 1,068,549.18
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
11 B.06 1 m3 Beton Mutu f'c=16,9 Mpa (K200), slump (12±2) cm, w/c =0,61 1,053,460.48
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 822,758.35
352 kg PC/Portlan Cement 1,140 401,280.00
731 kg PB/Pasir Beton 236 172,307.14
1,031 kg Kr/Krikil 241 248,203.70
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 957,691.35
E OVERHEAD & PROFIT (CONTOH) 10% 95,769.13
F Harga Satuan Pekerjaan (D+E) 1,053,460.48
12 B.07 1 m3 Beton Mutu f'c=19,3 Mpa (K225), slump (12±2) cm, w/c =0,58 1,088,055.79
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
B BAHAN 840,491.63
371 kg PC/Portlan Cement 1,140 422,940.00
698 kg PB/Pasir Beton 236 164,528.57
1,047 kg Kr/Krikil 241 252,055.56
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 989,141.63
E OVERHEAD & PROFIT (CONTOH) 10% 98,914.16
F Harga Satuan Pekerjaan (D+E) 1,088,055.79
13 B.07 1 m3 Beton Mutu f'c=19,3 Mpa (K225), slump (12±2) cm, w/c =0,58 1,072,967.09
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 840,491.63
371 kg PC/Portlan Cement 1,140 422,940.00
698 kg PB/Pasir Beton 236 164,528.57
1,047 kg Kr/Krikil 241 252,055.56
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 975,424.63
E OVERHEAD & PROFIT (CONTOH) 10% 97,542.46
F Harga Satuan Pekerjaan (D+E) 1,072,967.09
14 B.08 1 m3 Beton Mutu f'c=21,7 Mpa (K250), slump (12±2) cm, w/c =0,56 1,100,683.56
a) Manual
A TENAGA 148,650.00
L.01 1.650 OH Pekerja 68,000 112,200.00
L.02 0.275 OH Tukang Batu 74,000 20,350.00
L.03 0.028 OH Kepala Tukang 80,000 2,240.00
L.04 0.165 OH Mandor 84,000 13,860.00
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
B BAHAN 851,971.42
384 kg PC/Portlan Cement 1,140 437,760.00
692 kg PB/Pasir Beton 236 163,114.29
1,039 kg Kr/Krikil 241 250,129.63
215 lt Air 4.50 967.50
C PERALATAN -
-
D Jumlah A + B + C 1,000,621.42
E OVERHEAD & PROFIT (CONTOH) 10% 100,062.14
F Harga Satuan Pekerjaan (D+E) 1,100,683.56
15 B.08 1 m3 Beton Mutu f'c=21,7 Mpa (K250), slump (12±2) cm, w/c =0,56 1,085,594.86
b) Menggunakan Molen
A TENAGA 116,558.00
L.01 1.323 OH Pekerja 68,000 89,964.00
L.02 0.189 OH Tukang Batu 74,000 13,986.00
L.03 0.019 OH Kepala Tukang 80,000 1,520.00
L.04 0.132 OH Mandor 84,000 11,088.00
B BAHAN 851,971.42
384 kg PC/Portlan Cement 1,140 437,760.00
692 kg PB/Pasir Beton 236 163,114.29
1,039 kg Kr/Krikil 241 250,129.63
215 lt Air 4.50 967.50
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 986,904.42
E OVERHEAD & PROFIT (CONTOH) 10% 98,690.44
F Harga Satuan Pekerjaan (D+E) 1,085,594.86
C PERALATAN 18,375.00
0.25 hr Molen 0,35 m3 73,500 18,375.00
D Jumlah A + B + C 1,006,969.07
E OVERHEAD & PROFIT (CONTOH) 10% 100,696.91
F Harga Satuan Pekerjaan (D+E) 1,107,665.98
b) Manual
A TENAGA 38,200.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 38,200.00
E OVERHEAD & PROFIT (CONTOH) 10% 3,820.00
F Harga Satuan Pekerjaan (D+E) 42,020.00
A TENAGA 15,280.00
B BAHAN -
-
C PERALATAN 54,000.00
D Jumlah A + B + C 69,280.00
a) Vibrator
A TENAGA 19,100.00
B BAHAN -
-
C PERALATAN 15,000.00
D Jumlah A + B + C 34,100.00
A TENAGA 38,200.00
C PERALATAN 15,000.00
D Jumlah A + B + C 53,200.00
a) Manual
A TENAGA 19,100.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 19,100.00
E OVERHEAD & PROFIT (CONTOH) 10% 1,910.00
A TENAGA 15,280.00
B BAHAN -
C PERALATAN 54,000.00
D Jumlah A + B + C 69,280.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,928.00
A TENAGA 110,880.00
B BAHAN 1,341,000.00
C PERALATAN -
-
D Jumlah A + B + C 1,451,880.00
A TENAGA 39,600.00
L.01 0.250 OH Pekerja 68,000 17,000.00
B BAHAN 1,325,300.00
C PERALATAN -
D Jumlah A + B + C 1,364,900.00
A TENAGA 79,200.00
B BAHAN 1,552,500.00
C PERALATAN 90,000.00
0.15 hr Jack Tension / stressing 600,000 90,000.00
D Jumlah A + B + C 1,721,700.00
A TENAGA 30,320.00
B BAHAN
C PERALATAN -
D Jumlah A + B + C 30,320.00
A TENAGA 18,240.00
L.01 0.200 OH Pekerja 68,000 13,600.00
B BAHAN
C PERALATAN 2,250.00
0.025 hr Crane 90,000 2,250.00
D Jumlah A + B + C 20,490.00
B BAHAN
C PERALATAN 2,250.00
D Jumlah A + B + C 32,570.00
A TENAGA 30,320.00
B BAHAN
C PERALATAN 2,250.00
D Jumlah A + B + C 32,570.00
PEKERJAAN BEKISTING
1 B.21.b 1 m2 Bekisting untuk permukaan beton biasa 76,214.60
dg multipleks 12 mm atau 18 mm (tanpa perancah)
A TENAGA 23,480.00
L.01 0.200 OH Pekerja 68,000 13,600.00
L.02 0.100 OH Tukang kayu 74,000 7,400.00
L.03 0.010 OH Kepala Tukang 80,000 800.00
L.04 0.020 OH Mandor 84,000 1,680.00
B BAHAN 45,806.00
0.128 lbr Multipleks 18 mm 210,000 26,880.00
0.005 m3 Kaso 5/7x 4.00 2,400,000 12,000.00
0.220 kg Paku 13,300 2,926.00
0.200 ltr Minyak Beton 20,000 4,000.00
C PERALATAN -
-
D Jumlah A + B + C 69,286.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,928.60
F Harga Satuan Pekerjaan (D+E) 76,214.60
koef. Multipleks
0.3500
catatan : bahan digunakan lebih dari satu kali,
0.2450
0.2100
B BAHAN 33,600.00
0.0140 m3 Papan 2/30 2,400,000 33,600.00
C PERALATAN -
-
D Jumlah A + B + C 68,820.00
E OVERHEAD & PROFIT (CONTOH) 10% 6,882.00
0.0400
0.0280
0.0240
C PERALATAN -
-
D Jumlah A + B + C 97,524.00
0.3500
0.2450
0.2100
A TENAGA 35,220.00
L.01 0.300 OH Pekerja 68,000 20,400.00
B BAHAN 51,325.00
C PERALATAN -
-
D Jumlah A + B + C 86,545.00
A TENAGA 39,916.00
L.01 0.340 OH Pekerja 68,000 23,120.00
B BAHAN 16,425.50
C PERALATAN -
D Jumlah A + B + C 56,341.50
8.0000
4.0000
3.0000
Tanpa perancah
A TENAGA 28,176.00
B BAHAN 60,605.00
C PERALATAN -
-
D Jumlah A + B + C 88,781.00
0.3500
0.2450
0.2100
7 B.23.d 1 m2 Perancah Beksiting balok dengan kaso 5/7 tinggi 4m' 79,041.60
A TENAGA 42,264.00
L.01 0.360 OH Pekerja 68,000 24,480.00
B BAHAN 29,592.00
C PERALATAN -
-
D Jumlah A + B + C 71,856.00
A TENAGA 46,960.00
L.01 0.400 OH Pekerja 68,000 27,200.00
B BAHAN 10,634.50
C PERALATAN -
D Jumlah A + B + C 57,594.50
8.0000
4.0000
3.0000
A TENAGA 25,828.00
B BAHAN 48,605.00
C PERALATAN -
-
D Jumlah A + B + C 74,433.00
0.3500
0.2450
0.2100
A TENAGA 39,916.00
B BAHAN 55,990.00
C PERALATAN -
D Jumlah A + B + C 95,906.00
0.0400
0.0280
0.0240
Multipleks 12 cm / 18 cm
A TENAGA 28,176.00
B BAHAN 46,072.00
D Jumlah A + B + C 74,248.00
0.3500
0.2450
0.2100
Papan 3/20 cm
A TENAGA 42,264.00
B BAHAN 53,590.00
0.0140 lbr Papan 3/20 cm 2,400,000 33,600.00
D Jumlah A + B + C 95,854.00
E OVERHEAD & PROFIT (CONTOH) 10% 9,585.40
0.0400
0.0280
0.0240
Multipleks 12 cm / 18 cm
A TENAGA 23,480.00
B BAHAN 55,805.00
C PERALATAN -
D Jumlah A + B + C 79,285.00
E OVERHEAD & PROFIT (CONTOH) 10% 7,928.50
0.3500
0.2450
0.2100
Papan 3/20 cm
A TENAGA 35,220.00
B BAHAN 63,190.00
0.0140 lbr Papan 3/20 cm 2,400,000 33,600.00
0.0090 m3 Kaso 5/7x 4.00 2,400,000 21,600.00
C PERALATAN -
D Jumlah A + B + C 98,410.00
0.0400
0.0280
0.0240
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
BONGKAR BEKISTING
Bongkar Beksiting tiap m2 diambil untuk kondisi biasa 10% - 15% dari Upah Kerja Pemasangan
untuk pembongkaran material pakai ulang maka biaya bongkar 20% - 25% dari Upah Pemasangan
A TENAGA 3,056.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 3,056.00
dengan hati-hati
A TENAGA 4,584.00
B BAHAN -
C PERALATAN -
D Jumlah A + B + C 4,584.00
A TENAGA 57,760.00
B BAHAN 22,500.00
C PERALATAN -
D Jumlah A + B + C 80,260.00
B BAHAN 51,000.00
C PERALATAN -
D Jumlah A + B + C 112,120.00
E OVERHEAD & PROFIT (CONTOH) 10% 11,212.00
A TENAGA 144,400.00
B BAHAN 90,000.00
D Jumlah A + B + C 234,400.00
2 F.03 1 m' Tiang pancang baja pipa atau kotak Ø 30cm 773,300.00
A TENAGA 21,200.00
L.01 0.200 OH Pekerja 68,000 13,600.00
L.02 0.040 OH Tukang batu 74,000 2,960.00
A TENAGA 47,916.00
C PERALATAN 27,000.00
B BAHAN 440,021.78
1.030 m' Tiang pancang beton bertulang 40 x 40 cm 427,206 440,021.78
-
C PERALATAN 33,000.00
A TENAGA 26,500.00
L.01 0.2500 OH Pekerja 68,000 17,000.00
L.02 0.0500 OH Tukang batu 74,000 3,700.00
C PERALATAN 17,500.00
A TENAGA 26,620.00
L.01 0.3000 OH Pekerja 68,000 20,400.00
L.02 0.0500 OH Tukang batu 74,000 3,700.00
L.04 0.0300 OH Mandor 84,000 2,520.00
B BAHAN 82,400.00
1.0300 m' Beton bertulang precast 80,000 82,400.00
C PERALATAN 15,000.00
A TENAGA 42,592.00
L.01 0.4800 OH Pekerja 68,000 32,640.00
L.02 0.0800 OH Tukang batu 74,000 5,920.00
L.04 0.0480 OH Mandor 84,000 4,032.00
B BAHAN 139,050.00
1.0300 m' Beton bertulang precast 135,000 139,050.00
C PERALATAN 24,000.00
A TENAGA 53,240.00
L.01 0.6000 OH Pekerja 68,000 40,800.00
D Jumlah A + B + C 340,740.00
E OVERHEAD & PROFIT (CONTOH) 10% 34,074.00
F Harga Satuan Pekerjaan (D+E) 374,814.00
C PERALATAN 14,560.00
11 F.11 1 m' Tiang pancang baja pipa atau kotak Ø 30cm 745,991.95
A TENAGA 4,675.00
L.01 0.0345 OH Pekerja 68,000 2,346.00
B BAHAN 660,700.00
1.010 m' Tiang pancang baja pipa Ø 30 cm 650,000 656,500.00
-
C PERALATAN 20,020.00
A TENAGA 11,306.40
L.01 0.0945 OH Pekerja 68,000 6,426.00
L.02 0.0189 OH Tukang 74,000 1,398.60
L.04 0.0095 OH Mandor 84,000 798.00
L.05 0.0189 Oh Operator Crane 74,000 1,398.60
B BAHAN 440,021.78
1.030 m' Tiang pancang beton bertulang 40 x 40 cm 427,206 440,021.78
-
C PERALATAN 32,147.50
-
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
1 2 3 4 5 6 7 9=4X7
C PERALATAN 32,147.50
1.050 m' Turap Baja Profil Larsen lebar 350 mm 55,000 57,750.00
-
C PERALATAN 6,240.00
C PERALATAN 10,505.00
C PERALATAN 6,875.00
C PERALATAN 26,950.00