1 2 3 4
I BAHAN KACA
1 Kaca Polos 3 mm (ASAHI) Rp. 109,800 m2
2 Kaca Polos 5 mm (ASAHI) Rp. 164,700 m2
3 Kaca Polos 8 mm (ASAHI) Rp. 163,300 m2
4 Kaca Raybend 3 mm ( ASAHI ) Rp. 160,200 m2
5 Kaca Raybend 5 mm ( ASAHI ) Rp. 269,300 m2
6 Kaca Cermin 5 mm Rp. 241,400 m2
7 Glass Block DN 20 x 20 Rp. 38,600 bh
8 List Kaca 1x2/1x3 Rp. 7,500 m1
R ALAT TUKANG
1 Palu 0,5 Kg Rp. 49,300 bh
2 Cangkul Rp. 71,700 bh
3 Singkup Rp. 58,900 bh
4 Linggis Rp. 56,300 bh
5 Rol meter 30 meter Rp. 169,000 bh
6 Rol meter 5 meter Rp. 56,300 bh
7 Slang Plastik Untuk Waterpass dia. 0,5 cm Rp. 2,000 m1
8 Waterpass alumunium Panjang 60 cm Rp. 140,800 bh
9 Roda dorong Rp. 350,000 bh
9 1 m3 MENGURUG KEMBALI dan DIPADATKAN (Dihitung 1/3 Index Galian) SNI-2835 T-2008
Pekerja 0.1920 Oh 100,000.00 - 19,200.00 19,200.00
Mandor 0.0190 Oh 180,000.00 - 3,420.00 3,420.00
Jumlah Harga Satuan - 22,620.00 22,620.00
Dibulatkan - 22,620.00 22,620.00
10 1 m3 PEMADATAN TANAH (per-20 cm) SNI-2835 T-2008
Pekerja 0.5000 Oh 100,000.00 - 50,000.00 50,000.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan - 59,000.00 59,000.00
Dibulatkan - 59,000.00 59,000.00
13 1 m3 URUGAN DENGAN SIRTU PADAT (Untuk Peninggian Lantai Bangunan) SNI-2835 T-2008
Bahan :
Sirtu 1.2000 m3 281,400.00 337,680.00 - 337,680.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Mandor 0.0250 Oh 180,000.00 - 4,500.00 4,500.00
Jumlah Harga Satuan 337,680.00 29,500.00 367,180.00
Dibulatkan 337,680.00 29,500.00 367,180.00
7 1 m3 PASANGAN BATU BELAH 1 : 4 PAKAI MUKA BATU SEGI ENAM + SIARAN SK.SNI T-02-1991-03
Bahan :
Batu Belah 1.5000 m3 286,000.00 429,000.00 - 429,000.00
Semen Portland ( PC TYPE I ) 62.5000 kg 1,544.00 96,500.00 - 96,500.00
Pasir Pasang 0.3480 m3 359,200.00 125,001.60 - 125,001.60
Tenaga Kerja :
Pekerja 1.2500 Oh 100,000.00 - 125,000.00 125,000.00
Tukang batu 1.1250 Oh 140,000.00 - 157,500.00 157,500.00
Kepala tukang batu 0.0169 Oh 150,000.00 - 2,535.00 2,535.00
Mandor 0.0338 Oh 180,000.00 - 6,084.00 6,084.00
Jumlah Harga Satuan 650,501.60 291,119.00 941,620.60
Dibulatkan 650,500.00 291,115.00 941,615.00
8 1 m3 PASANGAN PONDASI SIKLOP, 60% beton Campuran 1PC ; 2 PS ; 3 Kr dan 40% BATU BELAH SNI-2836 T-2008
Bahan :
Batu Belah 15 - 20 cm 0.4800 m3 286,000.00 137,280.00 - 137,280.00
Semen Portland ( PC TYPE I ) 194.0000 kg 1,544.00 299,536.00 - 299,536.00
Pasir Beton 0.3120 m3 368,400.00 114,940.80 - 114,940.80
Kerikil 2/3 0.4680 m3 250,000.00 117,000.00 - 117,000.00
Besi Beton 126.0000 kg 12,500.00 1,575,000.00 - 1,575,000.00
Kawat Beton 1.8000 kg 36,600.00 65,880.00 - 65,880.00
Tenaga Kerja :
Pekerja 3.4000 Oh 100,000.00 - 340,000.00 340,000.00
Tukang Batu 0.8500 Oh 140,000.00 - 119,000.00 119,000.00
Kepala Tukang 0.0850 Oh 150,000.00 - 12,750.00 12,750.00
Mandor 0.1700 Oh 180,000.00 - 30,600.00 30,600.00
Jumlah Harga Satuan 2,309,636.80 502,350.00 2,811,986.80
Dibulatkan 2,309,635.00 502,350.00 2,811,985.00
2 1 m3 COR BETON SITE MIK K-125/ f1c = 7,4 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 276.0000 Kg 1,544.00 426,144.00 - 426,144.00
Pasir Beton 0.5914 m3 368,400.00 217,882.29 - 217,882.29
Split/Kerikil Uk. 2/3 0.7496 m3 250,000.00 187,407.41 - 187,407.41
Air 215.0000 Ltr - - - -
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 831,433.69 222,640.00 1,054,073.69
Dibulatkan 831,430.00 222,640.00 1,054,070.00
3 1 m3 COR BETON SITE MIK K-175 / f1c = 16,9 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 326.0000 Kg 1,544.00 503,344.00 - 503,344.00
Pasir Beton 0.5429 m3 368,400.00 199,988.57 - 199,988.57
Split/Kerikil Uk. 2/3 0.7496 m3 250,000.00 187,407.41 - 187,407.41
Air 215.0000 Ltr 100.00 21,500.00 - 21,500.00
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 912,239.98 222,640.00 1,134,879.98
Dibulatkan 912,235.00 222,640.00 1,134,875.00
4 1 m3 COR BETON SITE MIK K-225/ f1c = 19,3 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 371.0000 Kg 1,544.00 572,824.00 - 572,824.00
Pasir Beton 0.4986 m3 368,400.00 183,673.71 - 183,673.71
Split/Kerikil Uk. 2/3 0.7756 m3 250,000.00 193,888.89 - 193,888.89
Air 215.0000 Ltr 100.00 21,500.00 - 21,500.00
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 971,886.60 222,640.00 1,194,526.60
Dibulatkan 971,885.00 222,640.00 1,194,525.00
CATATAN : Bobot isi pasir = 1.400 kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Bukling factor pasir = 20 %
5 1 m3 PASANGAN PONDASI TELAPAK / PLAT BETON K.175 (150 Kg besi + Bekisting) SNI - 7394 -T-2008
Bahan :
Kayu Klas III 0.2000 m3 2,450,000.00 490,000.00 - 490,000.00
Minyak Bekisting 0.4000 Ltr 1,500.00 600.00 - 600.00
Paku 5 - 12 cm 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Besi Beton polos 157.5000 kg 12,500.00 1,968,750.00 - 1,968,750.00
Kawat Beton 3.0000 kg 36,600.00 109,800.00 - 109,800.00
Semen Portland ( PC TYPE I ) 336.0000 kg 1,544.00 518,784.00 - 518,784.00
Pasir Beton 0.5400 m3 368,400.00 198,936.00 - 198,936.00
Split 2/3 0.8100 m3 250,000.00 202,500.00 - 202,500.00
Tenaga Kerja :
Pekerja 3.9000 Oh 100,000.00 - 390,000.00 390,000.00
Tukang 2.4400 Oh 140,000.00 - 341,600.00 341,600.00
Kepala Tukang 0.2620 Oh 150,000.00 - 39,300.00 39,300.00
Mandor 0.2650 Oh 180,000.00 - 47,700.00 47,700.00
Jumlah Harga Satuan 3,508,870.00 818,600.00 4,327,470.00
Dibulatkan 3,508,870.00 818,600.00 4,327,470.00
8 1 m2 PASANGAN DINDING BATA EKSPOSED Uk. (5x11x24) cm Campuran 1PC ; 4 Psr SNI : 6897 T-2008
Bahan :
Bata berongga ekspose 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 14.0000 Kg 1,544.00 21,616.00 - 21,616.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 93,310.40 55,950.00 149,260.40
Dibulatkan 93,310.00 55,950.00 149,260.00
9 1 m2 PASANGAN BATA TERAWANG (ROSTER Uk. 12x11x24 cm) 1PC ; 3 Psr SNI : 6897 T-2008
Bahan :
Bata Terawang (Rooster) 30.0000 bh 4,500.00 135,000.00 - 135,000.00
Semen Portland ( PC TYPE I ) 14.0000 Kg 1,544.00 21,616.00 - 21,616.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 168,110.40 48,200.00 216,310.40
Dibulatkan 168,110.00 48,200.00 216,310.00
10 1 m2 PASANGAN BATA TERAWANG (ROOSTER Uk. 12x11x24 cm) 1PC ; 4 Psr SNI : 6897 T-2008
Bahan :
Bata Terawang (Rooster) 30.0000 bh 4,500.00 135,000.00 - 135,000.00
Semen Portland ( PC TYPE I ) 11.0000 Kg 1,544.00 16,984.00 - 16,984.00
Pasir Pasang 0.0350 m3 359,200.00 12,572.00 - 12,572.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 164,556.00 48,200.00 212,756.00
Dibulatkan 164,555.00 48,200.00 212,755.00
11 1 Bh PASANGAN GLASSBLOCK DN (Uk. 11,5 x 18,5 x 18,5 cm) 1PC ; 5 Psr SNI : 6897 T-2008
Bahan :
Glassblock DN 1.0000 bh 38,600.00 38,600.00 - 38,600.00
Semen Portland ( PC TYPE I ) 0.4400 Kg 1,544.00 679.36 - 679.36
Pasir Pasang 0.0014 m3 359,200.00 502.88 - 502.88
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.0040 Oh 140,000.00 - 560.00 560.00
Kepala tukang batu 0.0004 Oh 150,000.00 - 60.00 60.00
Mandor 0.0006 Oh 180,000.00 - 108.00 108.00
Jumlah Harga Satuan 39,782.24 1,728.00 41,510.24
Dibulatkan 39,780.00 1,725.00 41,505.00
VII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan PELAPIS DINDING
2 1 m2 PENGECATAN DINDING TEMBOK LAMA ( 1 CAT DASAR dan 2 CAT PENUTUP) 2x SK.SNI T-03-2407-1991
Bahan :
Cat Dasar 0.1200 kg 70,000.00 8,400.00 - 8,400.00
Cat Penutup 2x 0.1800 kg 41,000.00 7,380.00 - 7,380.00
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 500.00 500.00 - 500.00
Amplas 0.5000 lbr 4,000.00 2,000.00 - 2,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0420 Oh. 140,000.00 - 5,880.00 5,880.00
Kepala tukang cat 0.0042 Oh. 150,000.00 - 630.00 630.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 18,479.00 8,960.00 27,439.00
Dibulatkan 18,475.00 8,960.00 27,435.00
3 1 m2 PENGECATAN DINDING EXTERIOR SK.SNI T-03-2410-1991
Bahan :
Cat tembok exterior 0.2500 kg 50,000.00 12,500.00 - 12,500.00
Alkali ICI sebelum pengecatan 0.1250 lt 7,500.00 937.50 - 937.50
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Amplas 0.5000 lbr 4,000.00 2,000.00 - 2,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0630 Oh. 140,000.00 - 8,820.00 8,820.00
Kepala tukang cat 0.0140 Oh. 150,000.00 - 2,100.00 2,100.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 15,886.50 13,370.00 29,256.50
Dibulatkan 15,885.00 13,370.00 29,255.00
8 1 m2 PELABURAN BIDANG KAYU DENGAN RESIDU / SULIGNEM DAN TER (WOOD TREATMENT) SK.SNI T-2001
Bahan :
Residu 0.3500 ltr 60,000.00 21,000.00 - 21,000.00
Kwas 3" 0.0500 bh 1,900.00 95.00 - 95.00
Steiger werk 0.5000 ls 250.00 125.00 - 125.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Mandor 0.0060 Oh. 180,000.00 - 1,080.00 1,080.00
Jumlah Harga Satuan 21,220.00 11,080.00 32,300.00
Dibulatkan 21,220.00 11,080.00 32,300.00
10 1 m2 POLITURAN BIASA ( UNTUK PEKERJAAN KUSEN PINTU dan JENDELA) SK.SNI T-2001
Bahan :
Dempul plitur (dempul kasar) 0.0300 kg 52,000.00 1,560.00 - 1,560.00
Wood Filer (INFRA) 0.2000 kg 45,000.00 9,000.00 - 9,000.00
Oker putih 0.0200 kg 12,500.00 250.00 - 250.00
Oker warna 0.0100 bks 50,000.00 500.00 - 500.00
Batu Apung (gosok) 0.1000 kg 8,300.00 830.00 - 830.00
Sirlak ex India 0.2000 kg 34,999.00 6,999.80 - 6,999.80
Kwas 3" 0.0100 bh 1,900.00 19.00 - 19.00
Spirtus 0.2000 ltr 15,000.00 3,000.00 - 3,000.00
Ampelas kayu 0.1000 lbr 4,000.00 400.00 - 400.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang cat/politur 0.2850 Oh 140,000.00 - 39,900.00 39,900.00
Kepala tukang cat/politur 0.0400 Oh 150,000.00 - 6,000.00 6,000.00
Mandor 0.0200 Oh 180,000.00 - 3,600.00 3,600.00
Jumlah Harga Satuan 22,558.80 74,500.00 97,058.80
Dibulatkan 22,555.00 74,500.00 97,055.00
2 1 m3 KONSTRUKSI KUDA-KUDA KONVESIONAL, KAYU LAMA (KELAS II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 0.0000 m3 3,684,900.00 - - -
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 312,250.00 2,296,000.00 2,608,250.00
Dibulatkan 312,250.00 2,296,000.00 2,608,250.00
3 1 m3 KONSTRUKSI GORDENG dan KOMPONEN ATAP (BAHAN KAYU KLS.II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 1.1000 m3 3,684,900.00 4,053,390.00 - 4,053,390.00
Paku 08 - 12 cm 3.0000 kg 25,000.00 75,000.00 - 75,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 2.4000 Oh. 100,000.00 - 240,000.00 240,000.00
Tukang kayu 7.2000 Oh. 140,000.00 - 1,008,000.00 1,008,000.00
Kepala tukang kayu 0.7200 Oh. 150,000.00 - 108,000.00 108,000.00
Mandor 0.1200 Oh. 180,000.00 - 21,600.00 21,600.00
Jumlah Harga Satuan 4,295,640.00 1,377,600.00 5,673,240.00
Dibulatkan 4,295,640.00 1,377,600.00 5,673,240.00
4 1 m3 KONSTRUKSI GORDENG dan KOMPONEN ATAP (BAHAN KAYU KLS.II) KAYU LAMA SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 0.0000 m3 3,684,900.00 - - -
Paku 08 - 12 cm 3.0000 kg 25,000.00 75,000.00 - 75,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 2.4000 Oh. 100,000.00 - 240,000.00 240,000.00
Tukang kayu 7.2000 Oh. 140,000.00 - 1,008,000.00 1,008,000.00
Kepala tukang kayu 0.7200 Oh. 150,000.00 - 108,000.00 108,000.00
Mandor 0.1200 Oh. 180,000.00 - 21,600.00 21,600.00
Jumlah Harga Satuan 242,250.00 1,377,600.00 1,619,850.00
Dibulatkan 242,250.00 1,377,600.00 1,619,850.00
6 1 m3 KUDA-KUDA KAYU OVERSTEK / KONSOL (EKSPOSE) KAYU LOKAL KLS.II SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 1.2000 m3 3,684,900.00 4,421,880.00 - 4,421,880.00
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 4,734,130.00 2,296,000.00 7,030,130.00
Dibulatkan 4,734,130.00 2,296,000.00 7,030,130.00
7 1 m2 RANGKA ATAP BARU (KAYU BORNEO) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso 5/7 Kayu Borneo super 0.0140 m3 1,530,000.00 21,420.00 - 21,420.00
Reng Kayu 2/3 Borneo super 0.0036 m3 1,530,000.00 5,508.00 - 5,508.00
Paku 04 - 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 30,678.00 26,400.00 57,078.00
Dibulatkan 30,675.00 26,400.00 57,075.00
8 1 m2 RANGKA ATAP BARU (KAYU lokal KLS.II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso-kaso (5x7) cm 0.0140 m3 3,684,900.00 51,588.60 - 51,588.60
Reng (2x3) cm 0.0036 m3 3,684,900.00 13,265.64 - 13,265.64
Paku 5 cm dan 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 68,604.24 26,400.00 95,004.24
Dibulatkan 68,600.00 26,400.00 95,000.00
9 1 m2 RANGKA ATAP RENG 2/3 BARU (KASO KAYU LAMA ) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso-kaso (5x7) cm 0.0000 m3 3,684,900.00 - - -
Reng (2x3) cm 0.0036 m3 3,684,900.00 13,265.64 - 13,265.64
Paku 5 cm dan 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 17,015.64 26,400.00 43,415.64
Dibulatkan 17,015.00 26,400.00 43,415.00
11 1 m1 PEKERJAAN LISPLANK KAYU 3/30 BORNEO SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Borneo 3/30 0.0099 m3 7,380,500.00 73,066.95 - 73,066.95
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 73,716.95 46,000.00 119,716.95
Dibulatkan 73,715.00 46,000.00 119,715.00
12 1 m1 PEKERJAAN LISPLANK KAYU 3/20 BORNEO SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Kls. II 3/20 0.0066 m3 7,380,500.00 48,711.30 - 48,711.30
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 49,361.30 46,000.00 95,361.30
Dibulatkan 49,360.00 46,000.00 95,360.00
13 1 m1 PEKERJAAN LISPLANK KAYU 3/20 KAYU LOKAL KLS. II SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Kls. II 3/20 0.0066 m3 3,684,900.00 24,320.34 - 24,320.34
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 24,970.34 46,000.00 70,970.34
Dibulatkan 24,970.00 46,000.00 70,970.00
2 1 m2 PEKERJAAN RANGKA PLAFOND (GRID 100 x 100) KAYU ALBA SK SNI T-11-1993-03
Bahan :
Balok Kayu 5/10 dan 5/7 Kayu Alba 0.0120 m1 2,600,000.00 31,200.00 - 31,200.00
Paku 0.1000 m3 25,000.00 2,500.00 - 2,500.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.2500 Oh 140,000.00 - 35,000.00 35,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 33,700.00 67,250.00 100,950.00
Dibulatkan 33,700.00 67,250.00 100,950.00
7 1 m2 PENUTUP RANGKA PLAFOND (GRC BOARD EX. JAYA BOARD 120 x 240 TEBAL 4 MM) SK SNI T-11-1993-03
Bahan :
GRC 120x240 0.3640 lbr 45,000.00 16,380.00 - 16,380.00
Paku Skrup/GRC 0.1100 kg 13,000.00 1,430.00 - 1,430.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 17,810.00 19,520.00 37,330.00
Dibulatkan 17,810.00 19,520.00 37,330.00
3 1 m3 PAKERJAAN KUSEN PINTU / JENDELA BAHAN KAYU LOKAL KLS.II SK.SNI T-2002
Bahan :
Balok Kayu Lokal Kls. II Uk. 6/15 cm at 1.2000 M3 3,684,900.00 4,421,880.00 - 4,421,880.00
Paku 7 s/d 12 cm 2.5000 kg 25,000.00 62,500.00 - 62,500.00
Lem Kayu 1.0000 kg 40,000.00 40,000.00 - 40,000.00
Tenaga Kerja :
Pekerja 6.0000 Oh 100,000.00 - 600,000.00 600,000.00
Tukang kayu 18.0000 Oh 140,000.00 - 2,520,000.00 2,520,000.00
Kepala tukang kayu 2.0000 Oh 150,000.00 - 300,000.00 300,000.00
Mandor 0.3000 Oh 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 4,524,380.00 3,474,000.00 7,998,380.00
Dibulatkan 4,524,380.00 3,474,000.00 7,998,380.00
4 1 m1 PAKERJAAN KUSEN ALUMUNIUM UK. 4" NATURAL SEK. ALEXINDO SK.SNI T-2002
Bahan :
Profil allumunium 1.1000 m1 13,000.00 14,300.00 - 14,300.00
Skrup fixer 2.0000 Bh 300.00 600.00 - 600.00
Sealant 0.0600 Tube 22,000.00 1,320.00 - 1,320.00
Tenaga Kerja :
Pekerja 0.0430 Oh 100,000.00 - 4,300.00 4,300.00
Tukang khusus allumunium 0.0430 Oh 140,000.00 - 6,020.00 6,020.00
Kepala Tukang 0.0043 Oh 150,000.00 - 645.00 645.00
Mandor 0.0021 Oh 180,000.00 - 378.00 378.00
Jumlah Harga Satuan 16,220.00 11,343.00 27,563.00
Dibulatkan 16,220.00 11,340.00 27,560.00
5 1 m1 PAKERJAAN KUSEN ALUMUNIUM UK. 4" WARNA SEK. ALEXINDO SK.SNI T-2002
Bahan :
Profil allumunium 1.1000 m1 125,000.00 137,500.00 - 137,500.00
Skrup fixer 2.0000 Bh 300.00 600.00 - 600.00
Sealant 0.0600 Tube 22,000.00 1,320.00 - 1,320.00
Tenaga Kerja :
Pekerja 0.0430 Oh 100,000.00 - 4,300.00 4,300.00
Tukang khusus allumunium 0.0430 Oh 140,000.00 - 6,020.00 6,020.00
Kepala Tukang 0.0043 Oh 150,000.00 - 645.00 645.00
Mandor 0.0021 Oh 180,000.00 - 378.00 378.00
Jumlah Harga Satuan 139,420.00 11,343.00 150,763.00
Dibulatkan 139,420.00 11,340.00 150,760.00
10 1 m2 PAKERJAAN DAUN PINTU DOUBLE FORMIKA dan TEAKWOOD 4 MM RANGKA KAYU SK.SNI T-2002
Bahan :
Papan kayu Lokal Kls.II 0.0196 M3 3,684,900.00 72,224.04 - 72,224.04
Paku 1 s/d 3 cm 0.0300 kg 13,000.00 390.00 - 390.00
Lem Kayu 0.1500 kg 40,000.00 6,000.00 - 6,000.00
Formika T. 4 mm 0.4000 lbr 275,000.00 110,000.00 - 110,000.00
Teakwood T. 4 mm 0.4000 lbr 93,000.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 225,814.04 375,400.00 601,214.04
Dibulatkan 225,810.00 375,400.00 601,210.00
12 1 m2 Pek. JALUSI KAYU Uk. 2/15 (KAYU LOKAL KLS. II) SK.SNI T-2002
Bahan :
Kayu Lokal Setara Kls. II, Papan 0.0300 m3 3,684,900.00 110,547.00 - 110,547.00
Paku 1- 3 cm 0.0075 kg 13,000.00 97.50 - 97.50
Tenaga Kerja :
Pekerja 0.5000 Oh 100,000.00 - 50,000.00 50,000.00
Tukang kayu 1.0000 Oh 140,000.00 - 140,000.00 140,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 110,644.50 229,000.00 339,644.50
Dibulatkan 110,640.00 229,000.00 339,640.00
17 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara SEIS STANDARD UK. BESAR SK.SNI T-2002
Bahan :
Kunci 2 Slaag Silinder SEIS STANDARD 1.0000 bh 217,560.00 217,560.00 - 217,560.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 217,560.00 73,400.00 290,960.00
Dibulatkan 217,560.00 73,400.00 290,960.00
18 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara SEIS STANDARD UK. KECIL SK.SNI T-2002
Bahan :
Kunci 2 Slaag Silinder SEIS STANDARD 1.0000 bh 206,460.00 206,460.00 - 206,460.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 206,460.00 73,400.00 279,860.00
Dibulatkan 206,460.00 73,400.00 279,860.00
19 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara UNION TERBANG UK. KECIL SK.SNI T-2002
Bahan :
Kunci Bulat 2slaag UNION 1.0000 bh 65,000.00 65,000.00 - 65,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 65,000.00 73,400.00 138,400.00
Dibulatkan 65,000.00 73,400.00 138,400.00
8 MEMASANG 1 BUAH KRAN DINDING LEHER ANGSA (STAINLESS) dia-1/2" SK.SNI T-2001
Bahan :
Kran Dinding Leher Angsa stainless 1.0000 bh 47,500.00 47,500.00 - 47,500.00
Seal tape 1.0000 bh 4,500.00 4,500.00 - 4,500.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 52,000.00 16,590.00 68,590.00
Dibulatkan 52,000.00 16,590.00 68,590.00
10 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS STEEL LOKAL 1 LUBANG SK.SNI T-2001
Bahan :
Bak cuci stainless steel 1.0000 bh 216,200.00 216,200.00 - 216,200.00
Water drain+ asesories 1.0000 bh 27,500.00 27,500.00 - 27,500.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang batu 0.3000 Oh 140,000.00 - 42,000.00 42,000.00
Kepala tukang batu 0.0300 Oh 150,000.00 - 4,500.00 4,500.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 243,700.00 49,770.00 293,470.00
Dibulatkan 243,700.00 49,770.00 293,470.00
2 PEMBUATAN 1 Unit SEPTICTANK DAN REMBESAN UKURAN SEDANG (1,25x1,75 Tinggi 1,75m)SK.SNI T-2001 & SNI 03-29/398-1991
Bahan / Upah :
a. Galian tanah septictank 9.0000 m3 79,195.00 712,755.00 - 712,755.00
b. Galian tanah rembesan 4.2375 m3 66,825.00 283,170.94 - 283,170.94
c. Pasangan bata (1PC ; 4 Psr) 18.7500 m2 104,365.00 1,956,843.75 - 1,956,843.75
d. Plesteran Kedap Air 1 Pc ; 3 Psr 18.7500 m2 57,305.00 1,074,468.75 - 1,074,468.75
e. Beton Praktis K-175 0.3750 m3 3,565,955.00 1,337,233.13 - 1,337,233.13
f. Pasir Urug 0.2678 m3 282,600.00 75,666.15 - 75,666.15
g. Lapisan Injuk Untuk Rembesan 6.7500 kg 11,000.00 74,250.00 - 74,250.00
h. Batu Pecah / Split Ukuran 0,5 - 2 cm 1.3125 m3 408,400.00 536,025.00 - 536,025.00
i. Urugan tanah Kembali dipadatkan 2.6250 m3 15,055.00 39,519.38 - 39,519.38
j. Pasang Pipa Galvanis Ø 3/4" 1.0000 Btg 175,000.00 175,000.00 - 175,000.00
Jumlah Harga Satuan 6,264,932.09 - 6,264,932.09
Dibulatkan 6,264,930.00 - 6,264,930.00
3 PEMBUATAN 1 Unit SEPTICTANK DAN REMBESAN UKURAN KECIL (1,0x1,5 Tinggi 1,75m) SK.SNI T-2001 & SNI 03-29/398-1991
Bahan / Upah :
a. Galian tanah septictank 3.6000 m3 79,195.00 285,102.00 - 285,102.00
b. Galian tanah rembesan 1.6950 m3 66,825.00 113,268.38 - 113,268.38
c. Pasangan bata (1PC ; 4 Psr) 8.7500 m2 104,365.00 913,193.75 - 913,193.75
d. Plesteran Kedap Air 1 Pc ; 3 Psr 7.5000 m2 57,305.00 429,787.50 - 429,787.50
e. Beton Praktis K-175 0.1500 m3 3,565,955.00 534,893.25 - 534,893.25
f. Pasir Urug 0.1071 m3 282,600.00 30,266.46 - 30,266.46
g. Lapisan Injuk Untuk Rembesan 2.7000 kg 11,000.00 29,700.00 - 29,700.00
h. Batu Pecah / Split Ukuran 0,5 - 2 cm 0.5250 m3 408,400.00 214,410.00 - 214,410.00
i. Urugan tanah Kembali dipadatkan 1.0500 m3 15,055.00 15,807.75 - 15,807.75
j. Pasang Pipa Galvanis Ø 3/4" 1.0000 Btg 175,000.00 175,000.00 - 175,000.00
Jumlah Harga Satuan 2,741,429.09 - 2,741,429.09
Dibulatkan 2,741,425.00 - 2,741,425.00
5 1 m1 PASANGAN PAGAR TEMBOK TINGGI 1,20 Cm (Sdh Termasuk PASANGAN Pondasi Pagar) SK.SNI T-2001
Bahan / Upah :
a. Bata Merah Bakar (Kw. 2) 100.0000 bh 860.00 86,000.00 - 86,000.00
b. Batu Belah Pondasi 0.2500 m3 286,000.00 71,500.00 - 71,500.00
c. Beton praktis 1.3300 m3 1,134,879.98 1,509,390.37 - 1,509,390.37
Jumlah Harga Satuan 1,666,890.37 - 1,666,890.37
Dibulatkan 1,666,890.00 - 1,666,890.00
2 PEMASANGAN 1 BUAH TITIK INSTALASI PENERANGAN/LAMPU SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Kabel, NYM 3 x 2,5 mm2 8.0000 m1 260.00 2,080.00 - 2,080.00
Pipa Conduit 8.0000 m1 3,697.50 29,580.00 - 29,580.00
Socket Pipa 1.0000 bh 548.00 548.00 - 548.00
Tee Doos 2.0000 bh 990.00 1,980.00 - 1,980.00
Klem Pipa 3.0000 bh 4,400.00 13,200.00 - 13,200.00
Fhiser 6.0000 bh 600.00 3,600.00 - 3,600.00
Las Doop 2.0000 bh 22,000.00 44,000.00 - 44,000.00
Isolasi ban 0.2500 bh 7,000.00 1,750.00 - 1,750.00
Tenaga Kerja :
Pekerja 0.1667 Oh 100,000.00 - 16,666.67 16,666.67
Tukang M/E 0.3000 Oh 140,000.00 - 42,000.00 42,000.00
Mandor 0.3000 Oh. 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 96,738.00 112,666.67 209,404.67
Dibulatkan 96,735.00 112,665.00 209,400.00
3 PEMASANGAN 1 UNIT PEMASANGAN LAMPU TL 40 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu TL 40 Watt Philips + Arm 1.0000 bh 135,000.00 135,000.00 - 135,000.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 135,000.00 24,677.00 159,677.00
Dibulatkan 135,000.00 24,675.00 159,675.00
4 PEMASANGAN 1 UNIT PEMASANGAN LAMPU TL 20 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu TL 40 Watt Philips + Arm 1.0000 bh 87,500.00 87,500.00 - 87,500.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 87,500.00 24,677.00 112,177.00
Dibulatkan 87,500.00 24,675.00 112,175.00
5 PEMASANGAN 1 UNIT LAMPU PIJAR + FITTING PLAFOND SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu Pijar 15 - 60 Watt 1.0000 bh 15,000.00 15,000.00 - 15,000.00
Fitting Plafond Brocco 1.0000 bh 8,000.00 8,000.00 - 8,000.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 23,000.00 24,677.00 47,677.00
Dibulatkan 23,000.00 24,675.00 47,675.00
6 PEMASANGAN 1 BUAH STOP KONTAK Daya 10A/16A SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Stop Kontak Brocco 1.0000 bh 19,500.00 19,500.00 - 19,500.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 19,500.00 24,677.00 44,177.00
Dibulatkan 19,500.00 24,675.00 44,175.00
7 PEMASANGAN 1 BUAH SAKLAR GANDA/DOUBLE SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Saklar Ganda 1.0000 bh 26,000.00 26,000.00 - 26,000.00
Tenaga Kerja :
Pekerja 0.0250 Oh 100,000.00 - 2,500.00 2,500.00
Tukang M/E 0.0500 Oh 140,000.00 - 7,000.00 7,000.00
Mandor 0.0500 Oh. 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 26,000.00 18,500.00 44,500.00
Dibulatkan 26,000.00 18,500.00 44,500.00
8 PEMASANGAN 1 BUAH SAKLAR TUNGGAL/ENGKEL SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Saklar Tunggal 10A 1.0000 bh 18,600.00 18,600.00 - 18,600.00
Tenaga Kerja :
Pekerja 0.0250 Oh 100,000.00 - 2,500.00 2,500.00
Tukang M/E 0.0500 Oh 140,000.00 - 7,000.00 7,000.00
Mandor 0.0500 Oh. 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 18,600.00 18,500.00 37,100.00
Dibulatkan 18,600.00 18,500.00 37,100.00
VOLUME
### m2
46,859.20
26,400.00
PEK. TIANG PANCANG PER METER DAN TITIK
harga material tiang pancang m3 Rp 185,000
harga upah total oh Rp 100,000
harga joint & welding m3 Rp 390,000
Rp 675,000
6.12009
58.7529
117.506
2.9768
5.1963
0.4608
1 PEMASANGAN 1 UNIT PEMASANGAN Pas. Lampu SL 10 watt SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 10 Watt Philips + Arm ### bh 47,000.00 47,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 47,000.00 24,677.00
Dibulatkan 47,000.00 24,675.00
1 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 14 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 14 Watt Philips + Arm ### bh 49,000.00 49,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 49,000.00 24,677.00
Dibulatkan 49,000.00 24,675.00
1 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 18 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 18 Watt Philips + Arm ### bh 52,700.00 52,700.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 52,700.00 24,677.00
Dibulatkan 52,700.00 24,675.00
2 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 23 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 23 Watt Philips + Arm ### bh 62,000.00 62,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 62,000.00 24,677.00
Dibulatkan 62,000.00 24,675.00
T-2001 & PUIL SNI 04-0225-1987
47,000.00
3,333.00
9,338.00
12,006.00
71,677.00
71,675.00
49,000.00
3,333.00
9,338.00
12,006.00
73,677.00
73,675.00
52,700.00
3,333.00
9,338.00
12,006.00
77,377.00
77,375.00
3,333.00
9,338.00
12,006.00
86,677.00
86,675.00
Pri-
Perencana,
Pri-
B)
Total Biaya
(Rp.)
4,798,950.00
30,932,750.29
15,124,918.54
174,241,572.48
30,082,037.30
Pri-
54,930,407.37
18,543,555.70
29,939,509.25
7,230,750.00
4,163,170.00
10,909,042.50
-
380,896,663.42
380,897,000.00
A Rumah Tinggal
I PEKERJAAN PERSIAPAN Rp 4,798,950
II PEKERJAAN TANAH Rp 30,932,750
III PEKERJAAN BETON Rp 15,124,919
IV PEKERJAAN PASANGAN & PLESTERAN Rp 174,241,572
V PEKERJAAN KUSEN, DAUN PINTU & JENDELA Rp 30,082,037
VI PEKERJAAN ATAP Rp 54,930,407
VII PEKERJAAN LANGIT-LANGIT Rp 18,543,556
VIII PEKERJAAN CAT Rp 29,939,509
IX PEKERJAAN LISTRIK Rp 7,230,750
X PEKERJAAN KUNCI & PENGGANTUNG Rp 4,163,170
XI PASANGAN PENUTUP (PAS. KERAMIK) Rp 10,909,043
XII PEKERJAAN LAIN-LAIN Rp -
Pembulatan Rp 380,897,000
A PEKERJAAN FISIK
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan Bouwplank m2 62.00
2 Steger dan Alat Bantu Ls 1.00
3 Pembersihan Area Kembali Ls 1.00
4 Mobilisasi Ls 1.00
5 Papan Proyek Ls 1.00
Jumlah :
II PEKERJAAN TANAH
1 Galian tanah pondasi batu kali m3 74.58
2 Galian tanah utk pondasi kolom teras m3 1.96
3 Urugan tanah bekas galian pondasi m3 25.49
4 Urugan pasir bawah pondasi dan lantai t=10 cm m3 60.00
5 Galian Tanah Biasa Kedalaman 3m m3 10.73
6 Urugan tanah bawah lantai m3 33.60
Jumlah :
IV PEKERJAAN BETON
1 Pek. Sloof Beton (15/20) cm
a. Beton m3 5.11
b. Bekisting m2 67.2
c. Pembesian kg 629.02
Jumlah :
2 Pek. Kolom Beton (15/15) cm
a. Beton m3 2.76
b. Bekisting m2 39.7
c. Pembesian kg 447.11
Jumlah :
3 Pek. Kolom Teras (20/20) cm
a. Beton m3 0.21
b. Bekisting m2 15.17
c. Pembesian kg 100.06
Jumlah :
4 Pek. Ring Balok (15/20) cm
a. Beton m3 2.23
b. Bekisting m2 29.8
c. Pembesian kg 266.11
Jumlah :
5 Balok Teras
a. Beton m3 3.15
b. Bekisting m2 22.97
c. Pembesian kg 337.9
Jumlah :
IX PEKERJAAN CAT
1 Pengecatan dinding m2 651.00
2 Pengecatan Plafon m2 163.25
3 Pengecatan Kayu kusen m2 24.85
Jumlah :
X PEKERJAAN LISTRIK
1 Pas. Instalasi titik lampu ttk 23.00
2 Pas. Instalasi stop kontak ttk 7.00
3 Pas. Sakelar ganda bh 8.00
4 Pas. Lampu SL 10 watt bh 6.00
5 Pas. Lampu SL 14 watt bh 9.00
6 Pas. Lampu SL 18 watt bh 4.00
7 Pas. Lampu SL 23 watt bh 4.00
Jumlah :
- - 0.000%
-
1,355,000.00 2,710,000.00 0.345%
310,000.00 930,000.00 0.118%
2,500,000.00 5,000,000.00 0.636%
3,250,000.00 9,750,000.00 1.240%
1,950,000.00 1,950,000.00 0.248%
379,000.00 1,137,000.00 0.145%
2,500,000.00 7,500,000.00 0.954%
2,500,000.00 2,500,000.00 0.318%
50,000,000.00 50,000,000.00 6.358%
81,477,000.00
0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012%
0.223%
0.064%
0.544%
0.199% 0.199%
0.789% 0.789%
0.015% 0.015%
0.301% 0.301%
0.161% 0.161%
0.151% 0.151%
0.227% 0.227%
0.262% 0.262%
3.034% 3.034%
3.981% 3.981%
3.711% 3.711%
0.089% 0.089%
0.214% 0.214%
0.000% 0.000%
0.074% 0.074%
0.132%
0.639% 0.639%
0.002% 0.002%
0.002% 0.002%
1.045% 1.045%
1.600% 1.600%
1.775%
0.636%
0.980%
0.040%
0.009%
0.036%
0.056%
0.082%
1.907% 1.907%
0.042%
0.123%
0.757%
4.064%
1.880%
5.396% 9.680% 8.504% 3.812% 2.977% 2.888% 3.492% 9.961% 2.141% 2.148%
31.408% 41.088% 49.592% 53.403% 56.380% 59.268% 62.760% 72.721% 74.863% 77.010%
Sep-29
14 15 16
0.132%
0.128%
0.136%
0.020%
0.044%
0.056%
0.042%
0.123%
0.775%
0.752%
0.092%
0.395%
0.037%
0.031%
0.000%
0.000%
0.345%
0.118%
0.636%
1.240%
0.248%
0.145%
0.954%
0.318%
6.358%
0.045%
0.235%
0.356%
0.245%
0.151%
0.562%
0.528%
0.102%
0.870%
0.996%
1.540% 1.540%
1.023%
3.603% 3.559%
96.441% 100.000%