Anda di halaman 1dari 86

DAFTAR SATUAN UPAH

LOKASI PEKERJAAN : KABUPATEN SUMEDANG - PROVINSI JAWA BARAT

No. MACAM PEKERJA HARGA SATUAN


(a) (b) (c) (d)
1 Pekerja Rp. 100,000 Org/ hr
2 Tukang Rp. 140,000 Org/ hr
3 Kepala Tukang Rp. 150,000 Org/ hr
Kepala Tukang Kayu Rp. 150,000 Org/ hr
Tukang Kayu Rp. 140,000 Org/ hr
Kepala Tukang Besi Rp. 150,000 Org/ hr
Tukang Besi Rp. 140,000 Org/ hr
Kepala Tukang Cat/politur Rp. 150,000 Org/ hr
Tukang Cat/Politur Rp. 140,000 Org/ hr
Kepala Tukang Gali Rp. 150,000 Org/ hr
Tukang Gali Rp. 140,000 Org/ hr
Kepala Tukang Instalasai Rp. 150,000 Org/ hr
Tukang Instalasi M/E Rp. 140,000 Org/ hr
Kepala Tukang Pipa Rp. 150,000 Org/ hr
Tukang Pipa Rp. 140,000 Org/ hr
4 Mandor Rp. 180,000 Org/ hr
5 Sopir/Operator Rp. 170,000 Org/ hr
6 Pembantu Sopir/Operator Rp. 120,000 Org/ hr

Untuk Pekerjaan Secara Swakelola Melalui DAK "Mandor" Ditiadakan.


DAFTAR HARGA SATUAN BAHAN
LOKASI PEKERJAAN : KABUPATEN SUMEDANG - PROVINSI JAWA BARAT

No. JENIS BAHAN / MATERIAL HARGA SAT

1 2 3 4

A BAHAN AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA


1 Pasir urug Rp. 282,600 m3
2 Pasir pasang Rp. 359,200 m3
3 Pasir beton Rp. 368,400 m3
4 Abu batu Rp. 200,000 m3
5 Pasir batu (Sirtu) tersaring Rp. 281,400 m3
6 Batu pecah mesin ukuran 1/2 Rp. 408,400 m3
7 Batu pecah mesin ukuran 2/3 Rp. 250,000 m3
8 Batu pecah mesin ukuran 3/5 Rp. 225,000 m3
9 Batu Belah Pondasi Rp. 286,000 m3
10 Batu Templek Hitam Rp. 155,500 m2
11 Batu Templek Hijau Rp. 95,000 m2
12 Batu Candi Rp. 150,000 m2
13 Batu Pahat Dekoratif Rp. 180,000 m2
14 Batu Granit Rp. 22,300 kg
15 Batu Gosok (Apung) Rp. 8,300 kg
16 Bata Merah Bakar (Kw. 1) Rp. 860 bh
17 Bata Rooster 20x20 Rp. 4,500 bh
18 Bata Krawang Rp. 6,000 bh
19 Paving Block Natural 6 Cm Rp. 51,300 m2
20 Paving Block Warna 6 Cm Rp. 65,000 m2
21 Semen Portland ( PC TYPE I ) @50Kg/zak Rp. 77,200 zak
22 Semen Putih Rp. 3,000 kg
23 Semen Warna Sekualitas Mitsubishi Rp. 13,000 kg
24 Beton Ready Mix K-175, termasuk pompa/slang dll Rp. 912,500 m3
25 Beton Ready Mix K-225, termasuk pompa/slang dll Rp. 975,000 m3
26 Beton Ready Mix K-250, termasuk pompa/slang dll Rp. 1,045,000 m3

B BAHAN FINISHING : LABURAN, PENGISI DAN ALATNYA


1 Dempul/Plamir Tembok Sek. Sanlex Rp. 21,000 kg
2 Plamir Kayu Sek. Cap Kucing Rp. 33,750 kg
3 Cat Tembok Dasar Tembok Eksterior 5100 SEALER Rp. 70,000 kg
4 Cat Tembok Interior Sekualitas Sanlex Std Rp. 41,000 kg
5 Cat Tembok Interior Sekualitas Sanlex Wonder Rp. 25,500 kg
6 Cat Tembok Eksterior Sek. Kemstore Rp. 113,000 kg
7 Cat Penutup Vinilex Rp. 50,000 kg
8 Cat Genteng Rp. 33,200 kg
9 Solignem ( 1 blek = 10 liter ) Rp. 60,000 ltr
10 Plintcoat Rp. 41,600 kg
11 Sealant Rp. 22,000 Tube
12 Terpentin (Minyak cat) Rp. 68,600 botol
13 Thinner B Rp. 26,600 ltr
14 Menie Kayu Rp. 22,900 kg
15 Menie Besi Rp. 36,600 kg
16 Cat Kayu Sekualitas SEIV Rp. 73,200 kg
17 Cat Besi sekualitas AVIAN Rp. 78,900 kg
18 Zinkcromate Rp. 41,500 kg
19 Plitur Jadi DX Rp. 66,400 ltr
20 Plitur Jadi Ultran Rp. 75,500 Ltr
21 Water Profing Emulsion Rp. 45,500 Kg
22 Water Profing Membrance Rp. 156,000 Kg
23 Oker Putih Rp. 12,500 kg
24 Oker Warna Rp. 50,000 kg
25 Spirtus Rp. 15,000 ltr
26 Sirlak India Rp. 34,999 kg
27 Dempul Lilin Rp. 42,100 kg
28 Dempul Plitur Rp. 52,000 kg
29 Wood Filler Ex. IMPRA Rp. 45,000 kg
30 ML 131 Clear Danagloss Rp. 57,300 kg
31 Woodstain Ex. IMPRA Rp. 86,400 kg
32 Sending Siller MSS 123 Rp. 43,200 kg
33 Lem Aibond Ex. FOX Rp. 42,000 kg
34 Lem Kayu Ex. FOX Rp. 40,000 kg
35 Roll Cat Tembok ex. ETERNA Rp. 19,900 bh
36 Kwass Ukuran 1 - 2 " Rp. 2,500 bh
37 Kwass Ukuran 3 - 4 " Rp. 1,900 bh
38 Kape Dempul (4 inch 10 cm) Rp. 7,000 bh
39 Amplas Kayu Rp. 4,000 lbr

C BAHAN KAYU DAN BAHAN JADINYA


1 Bambu Ø 5 s.d 7 Rp. 24,000 btg
2 Bambu Ø 7 s.d 10 Rp. 22,900 Btg
3 Bambu Gombong Rp. 26,400 Btg
4 Dolken 5 s/d 7 Rp. 45,500 Btg
5 Dolken 8 s/d 10 Rp. 57,200 Btg
6 Kayu Terentang Rp. 12,000 m1
7 Kayu Balok Albasia Kelas II Rp. 2,600,000 m3
8 Kayu Papan Albasia Rp. 2,165,600 m3
9 Kayu Lokal / Hutan Kelas Kuat II Rp. 3,684,900 m3
10 Kayu Kelas III Rp. 2,650,000 m3
11 Kayu Kaso Albasia / Hutan Kelas II Rp. 2,450,000 m3
12 Kayu Jati Jabar Tua Lepas Mata dari dia. 80 cm keatas Rp. 12,822,000 m3
13 Kayu Jati Jabar dia. 40 cm keatas Rp. 12,822,000 m3
14 Balok Kayu Jati Uk. 6/15 cm Rp. 1,530,000 m3
15 Balok Kayu Borneo Super Rp. 7,380,500 m3
16 Reng Kayu 2/3 Borneo Super Rp. 3,750,000 m3
17 Papan Kayu Borneo Super Rp. 7,603,400 m3
18 Kaso Kayu Borneo Super Rp. 1,430,000 m3
19 Balok Kayu Kamper Banjar Rp. 9,295,800 m3
20 List profil kamper 2 x 2 cm Rp. 17,700 btg
21 List profil kamper 1 x 3 cm Rp. 9,300 btg
22 List profil kamper 1 x 5 cm Rp. 22,600 btg
23 List profil kamper 1 x 4 cm Rp. 17,200 btg
24 List profil kamper 2 x 4 cm Rp. 38,400 btg
25 List Plafond Gypsum L. 6 cm Rp. 11,400 m1
26 List Plafond Gypsum L. 7 cm Rp. 14,000 m1
27 List Plafond Gypsum L. 10 cm Rp. 20,400 m1
28 List Plafond Gypsum L. 14cm Rp. 21,700 m1
29 Lem Gypsum Rp. 6,000 bh
30 Penggantung dan Ramset Rp. 1,000 m1

D BAHAN PENUTUP RANGKA PLAFOND


1 Bahan Plafond Hardplek T. 5mm Ukuran 100x100 cm Rp. 15,000 lbr
2 Bahan plafond Enternit 4 mm Ukuran 50x100 cm Polos Rp. 5,000 lbr
3 Bahan plafond Enternit 4 mm Ukuran 50x100 cm Corak Rp. 7,500 lbr
4 Bahan Plafond GRC Board 4 mm 120 x 240 cm Rp. 45,000 lbr
5 Gypsum 120 x 240 t = 9 mm ex JAYABOARD Rp. 107,600 lbr
6 Lisplang GRC 12mm 120 x 240 cm (super panel) Rp. 230,000 lbr

E BAHAN KAYU LAPIS


1 Triplek 3 mm Ukuran 120 x 240 cm Rp. 52,728 lbr
2 Triplek 4 mm Ukuran 120 x 240 cm Rp. 66,358 lbr
3 Multipleks 6 mm Ukuran 120 x 240 cm Rp. 144,400 lbr
4 Multipleks 9 mm Ukuran 120 x 240 cm Rp. 156,700 lbr
5 Multipleks 12 mm Ukuran 120 x 240 cm Rp. 212,800 lbr
6 Multipleks 15 mm Ukuran 120 x 240 cm Rp. 259,700 lbr
7 Multipleks 18 mm Ukuran 120 x 240 cm Rp. 287,100 lbr
8 Bilik Bambu ( Hinis ) Rp. 29,200 m2
9 Teak Wood 3 mm 120 x 240 Rp. 102,100 lbr
10 Teak Wood 4 mm 120 x 240 Rp. 93,000 lbr
11 Melamin 4 mm 120 x 240 Rp. 62,000 lbr
12 Formika Putih Polos 122 x 244 Rp. 275,000 lbr
13 Formika Motif 120 x 240 cm Rp. 270,000
14 HPL Warna Solid Uk. 120x240 Rp. 145,000 lbr
15 HPL Warna Kayu Uk. 120x240 Rp. 210,000 lbr
16 HPL Alumunium Brush Uk. 120x240 Rp. 630,000 lbr

F BAHAN PENUTUP BIDANG LANTAI DAN PELAPIS DINDING


1 Lantai Granit 40x40 Rp. 95,000 m2
2 Keramik Lantai 40x40, Putih Polos sek. Roman Rp. 47,000 m2
3 Keramik Lantai 40x40, Warna/corak sek. Roman Rp. 65,500 m2
4 Keramik Lantai 30x30, Putih Polos sek. Mulya Rp. 49,400 m2
5 Keramik Lantai 30x30, Warna/corak sek. Roman Rp. 49,100 m2
6 Keramik Lantai 20x20, Putih polos sek. Mulya Rp. 68,600 m2
7 Keramik lantai 30x30, Anti slip sek. Asia tile Rp. 89,200 m2
8 Keramik lantai 25x25, Anti slip sek. Asia tile Rp. 61,900 m2
9 Keramik lantai 20x20, Anti slip sek. Asia tile Rp. 53,000 m2
10 Keramik Dinding 20x25, Putih Polos sek. Roman Rp. 131,000 m2
11 Keramik Dinding 20x25, Warna/corak sek. Roman Rp. 144,600 m2
12 Keramik Dinding 20x40, Warna/corak sek. Roman Rp. 70,000 m2
13 Keramik 30x30, Warna/corak sek. Roman Rp. 42,000 m2
14 Stair Nozing 10x30 Rp. 7,500 bh
15 Border Keramik 5x20 Motif/Corak Rp. 12,500 bh
16 Alat Potong Keramik Rp. 1,000 ls

G BAHAN SALURAN AIR KOTOR (RIOLERING)


1 Gravel U 20 cm Panjang 1 meter Rp. 51,800 bh
2 Gravel U 30 cm Panjang 1 meter Rp. 48,700 bh
3 Buis beton Ø 20 cm Panjang 1 meter Rp. 75,000 bh
4 Buis beton Ø 30 cm Panjang 1 meter Rp. 100,000 bh

H BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton Rata-rata Rp. 12,500 kg
2 Besi Beton U.32 Ø 16 mm (polos) Standard KS Rata-rata Rp. 175,000 btg
3 Besi Beton U.24 Ø 13 mm (ulir) Standard KS Rata-rata Rp. 123,500 btg
4 Besi Beton U.24 Ø 12 mm Standard KS Rata-rata Rp. 105,000 btg
5 Besi Beton U.24 Ø 10 mm Standard KS Rata-rata Rp. 68,500 btg
6 Besi Beton U.24 Ø 8 mm Standard KS Rata-rata Rp. 45,000 btg
7 Besi Beton U.24 Ø 6 mm Standard KS Rata-rata Rp. 32,500 btg
8 Besi Strip Rp. 19,500 kg
9 Besi Angkur Ø 10 mm Panjang 15mm Rp. 15,000 bh
10 Besi Begel Rp. 1,800 bh
11 Wiremesh ø8 mm (ulir) Rp. 668,500 lbr
12 Wiremesh ø6 mm (ulir) Rp. 406,700 lbr
13 IWF Ex DN SII Rp. 20,000 Kg
14 Kawat Beton Rp. 36,600 kg
15 Kawat Las Listrik Rp. 45,800 Kg
16 Kawat Ram 1x1 cm Rp. 23,400 m2
17 Pagar BRC T. 90 mm Rp. 39,500 lbr
18 Pagar BRC T. 60 mm Rp. 28,000 lbr
19 Kawat berduri ( 1 rol = 33 m = 4,5 kg )
1
Rp. 95,000 roll
20 Plat Bondex CD-35 Ex. DN SII Rp. 132,000 m2
21 Spandex t=0,35 mm Rp. 85,000 m2
22 Main Truss Z 75x100 sek. PRYDA Rp. 26,300 btg
23 Main Truss Z 75x75 sek. PRYDA Rp. 24,000 btg
24 Main Truss Z 75x100 sek. Blooscope Rp. 21,700 btg
25 Main Truss Z 75x75 sek. Blooscope Rp. 19,200 btg
26 Reng U Type 0,6 TCT Ek. PRYDA Rp. 47,600 btg
27 Talang air (Zyncalume) tebal 0,35 mm Rp. 196,800 lbr
28 Seng BJLS 0,20 lebar 55cm (1 rol 50 m' ) Rp. 24,000 m1
29 Seng BJLS 0,30 lebar 90cm (1 rol 50 m' ) Rp. 34,300 m1
30 Besi Hollow 40x40mm u/Rangka Plafond Rp. 34,100 btg
31 Besi Hollow 20x40mm u/Rangka Plafond Rp. 23,800 btg
32 Besi Hollow 40x40mm u/Rangka Pagar Rp. 83,300 btg
33 Besi Hollow 20x40mm u/Rangka Pagar Rp. 59,900 btg
34 Kusen Alumunium Natural 1.3 mm t=1,3 mm ( 4 " ) Rp. 13,000 m1
35 Kusen Alumunium Warna 1.3 mm t=1,3 mm ( 4 " ) Rp. 125,000 m1

I BAHAN KACA
1 Kaca Polos 3 mm (ASAHI) Rp. 109,800 m2
2 Kaca Polos 5 mm (ASAHI) Rp. 164,700 m2
3 Kaca Polos 8 mm (ASAHI) Rp. 163,300 m2
4 Kaca Raybend 3 mm ( ASAHI ) Rp. 160,200 m2
5 Kaca Raybend 5 mm ( ASAHI ) Rp. 269,300 m2
6 Kaca Cermin 5 mm Rp. 241,400 m2
7 Glass Block DN 20 x 20 Rp. 38,600 bh
8 List Kaca 1x2/1x3 Rp. 7,500 m1

J BAHAN PAKU DAN MUR BAUT


1 Paku 1 Cm s/d 3 Cm Rp. 28,000 kg
2 Paku 4 Cm s/d 7 Cm Rp. 13,000 kg
3 Paku 5 Cm s/d 10 Cm Rp. 20,000 kg
4 Paku 8 Cm s/d 12 Cm Rp. 25,000 kg
5 Paku beton 2" - 5" Rp. 20,000 kg
6 Paku Ramset/Dina Bolt Rp. 85,800 box
7 Paku Gypsum (20,00 m2/kg) Rp. 60,000 kg
8 Sekrup Gypsum Rp. 460 bh
9 Sekrup Genteng Metal 1/2"-1" Rp. 300 bh
10 Paku Beton 2cm - 5cm Rp. 12,200 box
11 Paku Kait Lengkap Rp. 42,200 kg
12 Paku Sekrup/Sekrup Fixer Rp. 690 bh
13 Paranet Rp. 32,500 m2
14 Silent/Plyurethan Rp. 43,700 kg
15 Baut Rp. 500 bh

K BAHAN SANITAIR DAN PERPIPAAN


1 Pipa GIP Medium B Ø 1 1/2" Rp. 784,500 btg
2 Pipa PVC (AW) Ø 1/2" Sek. Maspion Rp. 30,900 btg
3 Pipa PVC (AW) Ø 3/4" Sek. Maspion Rp. 42,300 btg
4 Pipa PVC (AW) Ø 1" Sek. Maspion Rp. 54,900 btg
5 Pipa PVC (AW) Ø 1 1/4" Sek. Maspion Rp. 78,900 btg
6 Pipa PVC (AW) Ø 1 1/2" Sek. Maspion Rp. 96,100 btg
7 Pipa PVC (AW) Ø 2" Sek. Maspion Rp. 165,900 btg
8 Pipa PVC (AW) Ø 2 1/2" Sek. Maspion Rp. 188,800 btg
9 Pipa PVC (AW) Ø 3" Sek. Maspion Rp. 203,600 btg
10 Pipa PVC (AW) Ø 4" Sek. Maspion Rp. 251,700 btg
11 Pipa PVC (AW) Ø 5" Sek. Maspion Rp. 601,700 btg
12 Pipa PVC (AW) Ø 6" Sek. Maspion Rp. 830,500 btg
13 Pasang Pipa Galvanis Ø 3/4" 175,000 btg
14 Stop Kran Ø 1/2 " KIT Rp. 81,200 bh
15 Stop Kran Ø 3/4 " KIT Rp. 120,900 bh
16 Stop Kran Ø 1 " KIT Rp. 196,000 bh
17 Check Valve Ø 1/2 " Rp. 51,450 bh
18 Double Neple Ø 1/2 " Rp. 16,500 bh
19 Water Mur 1/2 " Rp. 28,600 bh
20 Gate Walve 1/2 " Rp. 26,250 bh
21 Floor Drain Ex. SUN-EI Rp. 271,800 bh
22 Floor Drain Lt KM Stainless Steel (lokal) Rp. 27,500 bh
23 Kran Dinding Sun-Eui dia. 1/2 " Rp. 40,000 bh
24 Kran Dinding Lokal dia. 1/2 " Rp. 14,300 bh
25 Kran Dinding Sun-Ei Leher Angsa dia. 1/2 " Rp. 47,500 bh
26 Jet Washer Sek. TOTO Rp. 11,550 bh
27 Sealtape Rp. 4,500 bh
28 Wastafel Lengkap TOTO L.38vi Rp. 2,002,000 bh
29 Wastafel Lengkap INA LW.230 Rp. 577,000 unit
30 Kloset Duduk Porselen TOTO Standard lengkap, Putih Rp. 2,312,500 bh
31 Kloset Duduk Porselen TOTO Standard lengkap, Warna Tua Rp. 2,437,500 bh
32 Kloset Duduk Porselen INA Standard lengkap, Warna Tua Rp. 1,361,200 bh
33 Kloset Jongkok Porselen TOTO Standar Lengkap, Putih Rp. 218,700 bh
34 Kloset Jongkok Porselen INA Standar Lengkap, Putih Rp. 137,500 bh
35 Urinoir Lengkap lengkap Standard Ex. TOTO Rp. 606,200 bh
36 Penyekat Urinoir Ex. TOTO Rp. 237,500 bh
37 Bak Mandi Fiber glass Ukuran Besar Rp. 200,000 bh
38 Bak Mandi Fiber glass Ukuran Kecil Rp. 162,500 bh
39 Kitchen Zink Stainless Non Standard SAKURA ( 1 Lobang ) Rp. 216,200 bh
40 Kitchen Zink Stainless Non Standard MAJESTIC ( 2 Lobang ) Rp. 588,700 bh
41 Tangki Air Fiber Glass 500 ltr ( PINGUIN ) Rp. 1,001,200 bh
42 Menara Air Tinggi ±6,00m Untuk Kav. 500 ltr Rp. 31,964,500 bh
43 Tanki Saptic Biotech Rp. 33,962,000 bh
44 Pompa Air Kav. 100sek National Rp. 35,959,500 bh
44 Pompa Air Kav. 150sek National Rp. 37,957,000 bh
45 Jet Pump, 200 Watt (Pompa Dorong) sek. Groundfos Rp. 39,954,500 bh
45 Bio Septic Uk. 1,43x1,00x1,5 Rp. 41,952,000 bh
46 Glassbloock BN Rp. 23,000 bh

M BAHAN PENUTUP BIDANG ATAP


1 Atap Asbes Gelombang Kecil T. 4 mm (105x180 cm) Rp. 47,100 lbr
2 Atap Asbes Gelombang Kecil T. 4 mm (105x210 cm) Rp. 53,800 lbr
3 Atap Asbes Gelombang Kecil T. 4 mm (105x240 cm) Rp. 60,500 lbr
4 Genteng Beton Natural (14,4 bh/m2) Type "RENGGANIS" Rp. 11,400 bh
5 Genteng Beton Warna (14,4 bh/m2) Type "RENGGANIS" Rp. 4,000 bh
6 Genteng Murando Natural 18 bh/M2 Rp. 3,400 bh
7 Genteng Murando Glazur 18 bh/M2 Rp. 5,500 bh
8 Genteng Plentong Natural, Ex. Jatiwangi Rp. 2,300 bh
9 Genteng Plentong Glazuur, Ex. Jatiwangi Rp. 5,500 bh
10 Genteng Plentong Super/Besar Natural Ex. Jatiwangi Rp. 3,000 bh
11 Genteng Palentong Super/Besar Glazur Ex. Jatiwangi Rp. 3,500 bh
12 Genteng Bubung Segitiga/bulat Natural Ex. Jatiwangi Rp. 3,000 bh
13 Genteng Bubung Segitiga/bulat Glazur Ex. Jatiwangi Rp. 3,250 bh
14 Genteng Bubung Beton Natural RENGGANIS Rp. 6,250 bh
15 Genteng Metal Sand t = 0,35 Rp. 32,000 lbr
16 Genteng Metal Rainbow t = 0,35 Rp. 96,000 lbr
17 Genteng Metal Sakura t = 0,35 Rp. 73,000 lbr
18 Bubung Genteng Metal Sand Rp. 36,000 lbr
19 Bubung Genteng Metal Rainbow Rp. 45,000 lbr
20 Bubung Genteng Metal Sakura Rp. 55,000 bh
21 Alumunium Foil uk.lebar 1,25 m x 60.00m Rp. 12,500 m2
22 Alumunium Foil uk.lebar 2,50 m x 60.00m Rp. 17,500 m2
23 Seng gelombang BJLS 25 uk. 0.90 x 1.80 m Rp. 84,000 lbr
24 Seng gelombang BJLS 30 uk. 0.90 x 1.80 m Rp. 59,000 Lbr
25 Seng BJLS 0.20, l = 55 cm ( 1 rol = 50 m' ) Rp. 22,150 m1
26 Seng BJLS 0.30, l = 55 cm ( 1 rol = 50 m' ) Rp. 35,000 m1
25 Nok Stel 0,92 m Rp. 24,375 Lbr

N BAHAN MEKANIKAL DAN ELEKTRIKAL


1 MCB Domae 1 Kutub 20 A ( Kap. < 4.5 KA ) Rp. 47,500 unit
2 Skring Kas 2 grop biasa Rp. 47,500 bh
3 Box Panel MCB Sek. Prestro Rp. 37,000 bh
4 Kabel NYM 2 x 2,5 mm Rp. 10,000 m1
5 Kabel NYM 3 x 1,5 mm Rp. 9,000 m1
6 Kabel NYM 3 x 2,5 mm Rp. 13,000 m1
7 Kabel NYM 2 x 1,5 mm Rp. 7,000 m1
8 Pipa Conduit Ex. EGA 12mm Rp. 14,790 m1
9 Socket pipa 1/2 Rp. 548 pcs
10 Tee Doos Rp. 990 pcs
11 Klem Kabel 12mm Rp. 4,400 pck
12 Klem Pipa 450 pcs
13 Fhiser Rp. 600 pcs
14 Las doop Rp. 22,000 pck
15 Stop Kontak sek. Philips Rp. 19,500 pcs
16 Saklar Tunggal sek. Philips Rp. 18,600 pcs
17 Saklar Ganda sek. Philips Rp. 26,000 pcs
18 Fitting Lampu Plafond sek. Brocco Rp. 8,000 bh
19 Lampu Pijar 60 watt sek. Philips Rp. 15,000 bh
20 Lampu SL 8 watt sek. Philips Rp. 24,000 bh
21 Lampu SL 10 watt sek. Philips Rp. 47,000 bh
22 Lampu SL 14 watt sek. Philips Rp. 49,000 bh
23 Lampu SL 18 watt sek. Philips Rp. 52,700 bh
24 Lampu SL 23 watt sek. Philips Rp. 62,000 bh
25 Lampu Neon TL 20 watt sek. Philips + Armateur Rp. 87,500 bh
26 Lampu Neon TL 40 watt sek. Philips + Armateur Rp. 135,000 bh
27 Armatur Down Light Philips Uk. 4" Rp. 48,599 bh
28 Travo Philips 20 watt sekualitas Philips Rp. 56,000 bh
29 Isolasiban Rp. 7,000 bh
30 Lampu Sportlight Rp. 26,000 pcs
31 Jarum penangkal petir d-16 Rp. 332,000 bh
32 Kawat BC (tembaga) Rp. 3,500 pcs
33 Pek. Grounding instalasi penangkal petir Rp. 120,000 titik
34 Pek. Grounding instalasi panel Rp. 84,000 tiitik

O BAHAN ALAT PENGGANTUNG DAN KUNCI


1 Kunci KM/Wc Pintu Alumunium "ALPHA" Uk. Standar Rp. 29,000 pcs
2 Kunci KM Bulat Kualitas Biasa Rp. 9,900 pcs
3 Kunci Pintu 2 Slaag Ex-SEIS Ukuran Besar Rp. 217,560 pcs
4 Kunci Pintu 2 Slaag Ex-SEIS Ukuran Kecil Rp. 206,460 pcs
5 Kunci Pintu 2 Slaag Ex-UNION Besar Rp. 72,500 pcs
6 Kunci Pintu 2 Slaag Ex-UNION Kecil Rp. 65,000 pcs
7 Kunci Pintu Lemari Rp. 9,999 pcs
8 Rel Pintu Dorong 1 Pintu Ex-MARATON Lengkap Rp. 190,000 pcs
9 Kunci Gembok Besar Rp. 31,500 pcs
10 Grendel Tanam Pintu Ganda "ESPAGNOLET" Rp. 300,000 pcs
11 Grendel Pintu 15 cm (Slot Biasa) Rp. 15,000 pcs
12 Grendel Jendela (Spring Knip) Rp. 11,000 pcs
13 Grendel Jendela Biasa Rp. 3,000 pcs
14 Hak Angin Kait Jendela Biasa Rp. 10,000 pcs
15 Hak Angin Sendok Stainless / Kuningan Rp. 45,510 pcs
16 Tarikan Jendela Biasa Rp. 5,000 pcs
17 Sloot Pintu berikut Rantai Rp. 45,000 bh
18 Engsel Pintu Nylon Besar 3" Rp. 20,900 pcs
19 Engsel Pintu Nylon Kecil 4" Rp. 12,500 pcs
20 Engsel Pintu Alumunium (Floor Hinge) Ex "AKN" Standard Rp. 22,000 pcs
21 Engsel Jendela Nylon Rp. 23,000 pcs
22 Door Closer Kelas Standard ( Kelas Sedang ) Rp. 79,900 bh
23 Daun Pintu PVC Kwalitas Baik Lengkap Kunci Rp. 322,822 bh
24 Hendle (Tarikan Pintu) Alumunium Type GOLD Rp. 113,500 Pcs

P BAHAN JADI PENAMPUNG TINJA


1 Tali Injuk Rp. 11,000 kg

Q BAHAN BAKAR DAN MINYAK PELUMAS


1 Minyak Solar Rp. 6,800 ltr
2 Minyak Tanah/Korosin Rp. 12,000 ltr
3 Minyak Bekisting Rp. 1,500 ltr
4 Bensin Premium Rp. 74,000 ltr
5 Pelumas Rp. 55,600 ltr

R ALAT TUKANG
1 Palu 0,5 Kg Rp. 49,300 bh
2 Cangkul Rp. 71,700 bh
3 Singkup Rp. 58,900 bh
4 Linggis Rp. 56,300 bh
5 Rol meter 30 meter Rp. 169,000 bh
6 Rol meter 5 meter Rp. 56,300 bh
7 Slang Plastik Untuk Waterpass dia. 0,5 cm Rp. 2,000 m1
8 Waterpass alumunium Panjang 60 cm Rp. 140,800 bh
9 Roda dorong Rp. 350,000 bh

O SEWA ALAT BANTU


1 Concrete Pump + Slang Rp. 123,550 /Jam
2 Concrete Viberator Rp. 24,500 / Jam
3 Concrete Mixer Kav. 0,125 m3 Rp. 26,500 / Jam
4 Concrete Mixer Kav. 0,3 - 0,6 m3 Rp. 40,350 / Jam

Catatan : Harga belum termasuk pajak-pajak


ANALISA HARGA SATUAN PEKERJAAN
PELAKSANAAN PEMBANGUNAN / REHABILITASI GEDUNG
MELALUI DANA APBN TAHUN ANGGARAN 2016
LOKASI PEKERJAAN : KABUPATEN SUMEDANG - PROVINSI JAWA BARAT

HARGA SATUAN HARGA SATUAN


JUMLAH
NO. URAIAN dan JENIS PEKERJAAN KOEF. BAHAN/UPAH BAHAN UPAH
(Rp) (Rp) (Rp) (Rp)
a b c d e = (c x d) f = (c x d) g = (e + f )

A. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PERSIAPAN

Bongkaran 1 Ls 550,000 550,000.00 550,000.00


Perbersihan akhir lokasi 1 Ls 450,000 450,000.00 450,000.00
Pembersihan bongkaran 1 Ls 450,000 450,000.00 450,000.00

1 1 m2 PEMBUATAN LOS BAHAN / GUDANG SEMEN & ALAT PERMEN PU 11/PRT/M/2013


Bahan :
Dolken Kayu Ø 8-10 (Panjang 400 cm) 1.7000 m3 57,200.00 97,240.00 - 97,240.00
Kayu Lokal / biasa Kls. III 0.2100 m3 2,600,000.00 546,000.00 - 546,000.00
Paku berbagai ukuran 0.3000 kg 25,000.00 7,500.00 - 7,500.00
Semen Portland ( PC TYPE I ) 10.5000 kg 1,544.00 16,212.00 - 16,212.00
Pasir Beton 0.0300 m3 368,400.00 11,052.00 - 11,052.00
Koral beton 0.0500 m3 250,000.00 12,500.00 - 12,500.00
Seng Gelombang BJLS 32 1.5000 lbr 84,000.00 126,000.00 - 126,000.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 816,504.00 419,000.00 1,235,504.00
Dibulatkan 816,500.00 419,000.00 1,235,500.00

2 1 Bh PEMBUATAN PAPAN PROYEK SK SNI-T-2001


Bahan :
Triplek T.4 mm 0.3333 lbr 66,358.00 22,119.33 - 22,119.33
Kayu Kaso 5/7 Kls. II 0.0315 m3 3,684,900.00 116,074.35 - 116,074.35
Cat Minyak 1.0000 Kg 73,200.00 73,200.00 - 73,200.00
Paku 5 - 7 0.2500 Kg 13,000.00 3,250.00 - 3,250.00
Tenaga Kerja :
Upah Penulisan 1.0000 ls 35,000.00 - 35,000.00 35,000.00
Upah pasang 1.0000 ls 7,500.00 - 7,500.00 7,500.00
Jumlah Harga Satuan 214,643.68 42,500.00 257,143.68
Dibulatkan 214,640.00 42,500.00 257,140.00

3 1 m1 PENGUKURAN DAN PASANG BOUWPLANK SK SNI-T-2001


Bahan :
Kayu Kaso Albasia 5/7 0.0120 m3 2,600,000.00 31,200.00 - 31,200.00
Paku 2" - 5" 0.0200 kg 25,000.00 500.00 - 500.00
Kayu Papan Albasia 0.0070 m3 2,165,600.00 15,159.20 - 15,159.20
Tenaga Kerja :
Pekerja 0.1000 Oh 100,000.00 - 10,000.00 10,000.00
Tukang Kayu/batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala Tukang Kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 46,859.20 26,400.00 73,259.20
Dibulatkan ### 46,855.00 26,400.00 73,255.00

II. PENETAPAN INDEK HARGA SATUAN PEKERJAAN GALIAN dan URUGAN


1 1 m3 GALIAN TANAH BIASA KEDALAMAN 1 meter SNI-2835 T-2008
Pekerja 0.7500 Oh 100,000.00 - 75,000.00 75,000.00
Mandor 0.0250 Oh 180,000.00 - 4,500.00 4,500.00
Jumlah Harga Satuan - 79,500.00 79,500.00
Dibulatkan - 79,500.00 79,500.00

2 1 m3 GALIAN TANAH BIASA KEDALAMAN 2 meter SNI-2835 T-2008


Pekerja 0.9000 Oh 100,000.00 - 90,000.00 90,000.00
Mandor 0.0450 Oh 180,000.00 - 8,100.00 8,100.00
Jumlah Harga Satuan - 98,100.00 98,100.00
Dibulatkan - 98,100.00 98,100.00

3 1 m3 GALIAN TANAH BIASA KEDALAMAN 3 meter SNI-2835 T-2008


Pekerja 1.0500 Oh 100,000.00 - 105,000.00 105,000.00
Mandor 0.0670 Oh 180,000.00 - 12,060.00 12,060.00
Jumlah Harga Satuan - 117,060.00 117,060.00
Dibulatkan - 117,060.00 117,060.00

4 1 m3 GALIAN TANAH BERBATU/KERAS KEDALAMAN 1 meter SNI-2835 T-2008


Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Mandor 0.0320 Oh 180,000.00 - 5,760.00 5,760.00
Jumlah Harga Satuan - 105,760.00 105,760.00
Dibulatkan - 105,760.00 105,760.00

5 1 m3 GALIAN TANAH CADAS KEDALAMAN 1 meter SNI-2835 T-2008


Pekerja 1.5000 Oh 100,000.00 - 150,000.00 150,000.00
Mandor 0.0600 Oh 180,000.00 - 10,800.00 10,800.00
Jumlah Harga Satuan - 160,800.00 160,800.00
Dibulatkan - 160,800.00 160,800.00

6 1 m3 GALIAN TANAH LUMPUR KEDALAMAN 1 meter SNI-2835 T-2008


Pekerja 1.2000 Oh 100,000.00 - 120,000.00 120,000.00
Mandor 0.0450 Oh 180,000.00 - 8,100.00 8,100.00
Jumlah Harga Satuan - 128,100.00 128,100.00
Dibulatkan - 128,100.00 128,100.00

7 1 m2 STRIPING TEBING SETINGGI 1 meter SNI-2835 T-2008


Pekerja 0.0500 Oh 100,000.00 - 5,000.00 5,000.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan - 5,900.00 5,900.00
Dibulatkan - 5,900.00 5,900.00

8 1 m3 MEMBUANG TANAH SEJAUH 150 meter SNI-2835 T-2008


Pekerja 0.3300 Oh 100,000.00 - 33,000.00 33,000.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan - 34,800.00 34,800.00
Dibulatkan - 34,800.00 34,800.00

9 1 m3 MENGURUG KEMBALI dan DIPADATKAN (Dihitung 1/3 Index Galian) SNI-2835 T-2008
Pekerja 0.1920 Oh 100,000.00 - 19,200.00 19,200.00
Mandor 0.0190 Oh 180,000.00 - 3,420.00 3,420.00
Jumlah Harga Satuan - 22,620.00 22,620.00
Dibulatkan - 22,620.00 22,620.00
10 1 m3 PEMADATAN TANAH (per-20 cm) SNI-2835 T-2008
Pekerja 0.5000 Oh 100,000.00 - 50,000.00 50,000.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan - 59,000.00 59,000.00
Dibulatkan - 59,000.00 59,000.00

11 1 m2 PEMASANGAN LAPISAN IJUK TEBAL 10 cm (Untuk Bidang Resapan) SNI-2835 T-2008


Bahan :
Injuk 6.0000 kg 11,000.00 66,000.00 - 66,000.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 66,000.00 17,700.00 83,700.00
Dibulatkan 66,000.00 17,700.00 83,700.00

12 1 m3 URUGAN DENGAN PASIR URUG DIPADTKAN SNI-2835 T-2008


Bahan :
Pasir Urug 1.2000 m3 282,600.00 339,120.00 - 339,120.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan 339,120.00 31,800.00 370,920.00
Dibulatkan 339,120.00 31,800.00 370,920.00

13 1 m3 URUGAN DENGAN SIRTU PADAT (Untuk Peninggian Lantai Bangunan) SNI-2835 T-2008
Bahan :
Sirtu 1.2000 m3 281,400.00 337,680.00 - 337,680.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Mandor 0.0250 Oh 180,000.00 - 4,500.00 4,500.00
Jumlah Harga Satuan 337,680.00 29,500.00 367,180.00
Dibulatkan 337,680.00 29,500.00 367,180.00

III. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PONDASI


1 1 m3 PASANGAN BATU KOSONG/ AANSTAMPING SNI-2836 T-2008
Bahan :
Batu Belah 15/20 cm 1.2000 m3 286,000.00 343,200.00 - 343,200.00
Pasir Urug 0.4320 m3 282,600.00 122,083.20 - 122,083.20
Tenaga Kerja :
Pekerja 0.7800 Oh 100,000.00 - 78,000.00 78,000.00
Tukang Batu 0.3900 Oh 140,000.00 - 54,600.00 54,600.00
Kepala tukang batu 0.0390 Oh 150,000.00 - 5,850.00 5,850.00
Mandor 0.0390 Oh 180,000.00 - 7,020.00 7,020.00
Jumlah Harga Satuan 465,283.20 145,470.00 610,753.20
Dibulatkan 465,280.00 145,470.00 610,750.00

2 1 m3 PASANGAN PONDASI LAJUR BELAH ( 1 PC ; 6 PSR ) SNI-2836 T-2008


Bahan :
Batu Belah 15/20 cm 1.2000 m3 286,000.00 343,200.00 - 343,200.00
Semen Portland ( PC TYPE I ) 117.0000 Kg 1,544.00 180,648.00 - 180,648.00
Pasir Pasang 0.5610 m3 359,200.00 201,511.20 - 201,511.20
Tenaga Kerja :
Pekerja 1.5000 Oh 100,000.00 - 150,000.00 150,000.00
Tukang Batu 0.7500 Oh 140,000.00 - 105,000.00 105,000.00
Kepala Tukang 0.0750 Oh 150,000.00 - 11,250.00 11,250.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 725,359.20 279,750.00 1,005,109.20
Dibulatkan 725,355.00 279,750.00 1,005,105.00

3 1 m3 PASANGAN PONDASI LAJUR BELAH ( 1 PC ; 5 PSR ) SNI-2836 T-2008


Bahan :
Batu Belah 15/20 cm 1.2000 m3 286,000.00 343,200.00 - 343,200.00
Semen Portland ( PC TYPE I ) 136.0000 Kg 1,544.00 209,984.00 - 209,984.00
Pasir Pasang 0.5440 m3 359,200.00 195,404.80 - 195,404.80
Tenaga Kerja :
Pekerja 1.5000 Oh 100,000.00 - 150,000.00 150,000.00
Tukang Batu 0.7500 Oh 140,000.00 - 105,000.00 105,000.00
Kepala Tukang 0.0750 Oh 150,000.00 - 11,250.00 11,250.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 748,588.80 279,750.00 1,028,338.80
Dibulatkan 748,585.00 279,750.00 1,028,335.00

4 1 m3 PASANGAN PONDASI LAJUR BATU KALI ( 1 PC ; 4 PSR ) SNI-2836 T-2008


Bahan :
Batu Belah 15/20 cm 1.2000 m3 286,000.00 343,200.00 - 343,200.00
Semen Portland ( PC TYPE I ) 163.0000 Kg 1,544.00 251,672.00 - 251,672.00
Pasir Pasang 0.5200 m3 359,200.00 186,784.00 - 186,784.00
Tenaga Kerja :
Pekerja 1.5000 Oh 100,000.00 - 150,000.00 150,000.00
Tukang batu 0.7500 Oh 140,000.00 - 105,000.00 105,000.00
Kepala tukang batu 0.0750 Oh 150,000.00 - 11,250.00 11,250.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 781,656.00 279,750.00 1,061,406.00
Dibulatkan 781,655.00 279,750.00 1,061,405.00

5 1 m3 PASANGAN PONDASI LAJUR BATU KALI ( 1 PC ; 3 PSR ) SNI-2836 T-2008


Bahan :
Batu Belah 15/20 cm 1.2000 m3 286,000.00 343,200.00 - 343,200.00
Semen Portland ( PC TYPE I ) 202.0000 Kg 1,544.00 311,888.00 - 311,888.00
Pasir Pasang 0.4850 m3 359,200.00 174,212.00 - 174,212.00
Tenaga Kerja :
Pekerja 1.5000 Oh 100,000.00 - 150,000.00 150,000.00
Tukang batu 0.7500 Oh 140,000.00 - 105,000.00 105,000.00
Kepala tukang batu 0.0750 Oh 150,000.00 - 11,250.00 11,250.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 829,300.00 279,750.00 1,109,050.00
Dibulatkan 829,300.00 279,750.00 1,109,050.00

6 1 m2 PASANGAN BATU TEMPEL + SIARAN SK.SNI T-02-1991-03


Bahan :
Batu Tempel Hitam 1.1000 m2 155,500.00 171,050.00 - 171,050.00
Semen Portland ( PC TYPE I ) 6.0000 kg 1,544.00 9,264.00 - 9,264.00
Pasir Pasang 0.0310 m3 359,200.00 11,135.20 - 11,135.20
Tenaga Kerja :
Pekerja 0.1875 Oh 100,000.00 - 18,750.00 18,750.00
Tukang batu 0.2250 Oh 140,000.00 - 31,500.00 31,500.00
Mandor 0.0338 Oh 180,000.00 - 6,084.00 6,084.00
Jumlah Harga Satuan 191,449.20 56,334.00 247,783.20
Dibulatkan 191,445.00 56,330.00 247,775.00

7 1 m3 PASANGAN BATU BELAH 1 : 4 PAKAI MUKA BATU SEGI ENAM + SIARAN SK.SNI T-02-1991-03
Bahan :
Batu Belah 1.5000 m3 286,000.00 429,000.00 - 429,000.00
Semen Portland ( PC TYPE I ) 62.5000 kg 1,544.00 96,500.00 - 96,500.00
Pasir Pasang 0.3480 m3 359,200.00 125,001.60 - 125,001.60
Tenaga Kerja :
Pekerja 1.2500 Oh 100,000.00 - 125,000.00 125,000.00
Tukang batu 1.1250 Oh 140,000.00 - 157,500.00 157,500.00
Kepala tukang batu 0.0169 Oh 150,000.00 - 2,535.00 2,535.00
Mandor 0.0338 Oh 180,000.00 - 6,084.00 6,084.00
Jumlah Harga Satuan 650,501.60 291,119.00 941,620.60
Dibulatkan 650,500.00 291,115.00 941,615.00

8 1 m3 PASANGAN PONDASI SIKLOP, 60% beton Campuran 1PC ; 2 PS ; 3 Kr dan 40% BATU BELAH SNI-2836 T-2008
Bahan :
Batu Belah 15 - 20 cm 0.4800 m3 286,000.00 137,280.00 - 137,280.00
Semen Portland ( PC TYPE I ) 194.0000 kg 1,544.00 299,536.00 - 299,536.00
Pasir Beton 0.3120 m3 368,400.00 114,940.80 - 114,940.80
Kerikil 2/3 0.4680 m3 250,000.00 117,000.00 - 117,000.00
Besi Beton 126.0000 kg 12,500.00 1,575,000.00 - 1,575,000.00
Kawat Beton 1.8000 kg 36,600.00 65,880.00 - 65,880.00
Tenaga Kerja :
Pekerja 3.4000 Oh 100,000.00 - 340,000.00 340,000.00
Tukang Batu 0.8500 Oh 140,000.00 - 119,000.00 119,000.00
Kepala Tukang 0.0850 Oh 150,000.00 - 12,750.00 12,750.00
Mandor 0.1700 Oh 180,000.00 - 30,600.00 30,600.00
Jumlah Harga Satuan 2,309,636.80 502,350.00 2,811,986.80
Dibulatkan 2,309,635.00 502,350.00 2,811,985.00

9 1 m3 PASANGAN PONDASI SUMURAN (diameter 100 cm) SNI-2836 T-2008


Bahan :
Batu Belah 15 - 20 cm 0.4500 m3 286,000.00 128,700.00 - 128,700.00
Semen Portland ( PC TYPE I ) 194.0000 kg 1,544.00 299,536.00 - 299,536.00
Pasir Beton 0.3120 m3 368,400.00 114,940.80 - 114,940.80
Kerikil 2/3 0.4680 m3 250,000.00 117,000.00 - 117,000.00
Tenaga Kerja :
Pekerja 2.4000 Oh 100,000.00 - 240,000.00 240,000.00
Tukang Batu 0.8000 Oh 140,000.00 - 112,000.00 112,000.00
Kepala Tukang 0.0800 Oh 150,000.00 - 12,000.00 12,000.00
Mandor 0.1190 Oh 180,000.00 - 21,420.00 21,420.00
Jumlah Harga Satuan 660,176.80 385,420.00 1,045,596.80
Dibulatkan 660,175.00 385,420.00 1,045,595.00

IV. PENETAPAN INDEK HARGA SATUAN PEKERJAAN BETON


1 1 m2 LANTAI KERJA ( 1 PC ; 3 PSR ; 5 KR) TEBAL 5cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 13.8000 Kg 1,544.00 21,307.20 - 21,307.20
Pasir Beton 0.0296 m3 368,400.00 10,894.11 - 10,894.11
Split/Kerikil Uk. 2/3 0.0375 m3 250,000.00 9,370.37 - 9,370.37
Air 10.7500 Ltr - - - -
Tenaga Kerja :
Pekerja 0.0825 Oh 100,000.00 - 8,250.00 8,250.00
Tukang Batu 0.0138 Oh 140,000.00 - 1,925.00 1,925.00
Kepala Tukang 0.0014 Oh 150,000.00 - 210.00 210.00
Mandor 0.0042 Oh 180,000.00 - 747.00 747.00
Jumlah Harga Satuan 41,571.68 11,132.00 52,703.68
Dibulatkan 41,570.00 11,130.00 52,700.00

2 1 m3 COR BETON SITE MIK K-125/ f1c = 7,4 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 276.0000 Kg 1,544.00 426,144.00 - 426,144.00
Pasir Beton 0.5914 m3 368,400.00 217,882.29 - 217,882.29
Split/Kerikil Uk. 2/3 0.7496 m3 250,000.00 187,407.41 - 187,407.41
Air 215.0000 Ltr - - - -
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 831,433.69 222,640.00 1,054,073.69
Dibulatkan 831,430.00 222,640.00 1,054,070.00

3 1 m3 COR BETON SITE MIK K-175 / f1c = 16,9 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 326.0000 Kg 1,544.00 503,344.00 - 503,344.00
Pasir Beton 0.5429 m3 368,400.00 199,988.57 - 199,988.57
Split/Kerikil Uk. 2/3 0.7496 m3 250,000.00 187,407.41 - 187,407.41
Air 215.0000 Ltr 100.00 21,500.00 - 21,500.00
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 912,239.98 222,640.00 1,134,879.98
Dibulatkan 912,235.00 222,640.00 1,134,875.00

4 1 m3 COR BETON SITE MIK K-225/ f1c = 19,3 MPa, Slumptest (12 ± 2) cm SNI - 7394 -T-2008
Bahan :
Semen Portland ( PC TYPE I ) 371.0000 Kg 1,544.00 572,824.00 - 572,824.00
Pasir Beton 0.4986 m3 368,400.00 183,673.71 - 183,673.71
Split/Kerikil Uk. 2/3 0.7756 m3 250,000.00 193,888.89 - 193,888.89
Air 215.0000 Ltr 100.00 21,500.00 - 21,500.00
Tenaga Kerja :
Pekerja 1.6500 Oh 100,000.00 - 165,000.00 165,000.00
Tukang Batu 0.2750 Oh 140,000.00 - 38,500.00 38,500.00
Kepala Tukang 0.0280 Oh 150,000.00 - 4,200.00 4,200.00
Mandor 0.0830 Oh 180,000.00 - 14,940.00 14,940.00
Jumlah Harga Satuan 971,886.60 222,640.00 1,194,526.60
Dibulatkan 971,885.00 222,640.00 1,194,525.00
CATATAN : Bobot isi pasir = 1.400 kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Bukling factor pasir = 20 %

5 1 m3 PASANGAN PONDASI TELAPAK / PLAT BETON K.175 (150 Kg besi + Bekisting) SNI - 7394 -T-2008
Bahan :
Kayu Klas III 0.2000 m3 2,450,000.00 490,000.00 - 490,000.00
Minyak Bekisting 0.4000 Ltr 1,500.00 600.00 - 600.00
Paku 5 - 12 cm 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Besi Beton polos 157.5000 kg 12,500.00 1,968,750.00 - 1,968,750.00
Kawat Beton 3.0000 kg 36,600.00 109,800.00 - 109,800.00
Semen Portland ( PC TYPE I ) 336.0000 kg 1,544.00 518,784.00 - 518,784.00
Pasir Beton 0.5400 m3 368,400.00 198,936.00 - 198,936.00
Split 2/3 0.8100 m3 250,000.00 202,500.00 - 202,500.00
Tenaga Kerja :
Pekerja 3.9000 Oh 100,000.00 - 390,000.00 390,000.00
Tukang 2.4400 Oh 140,000.00 - 341,600.00 341,600.00
Kepala Tukang 0.2620 Oh 150,000.00 - 39,300.00 39,300.00
Mandor 0.2650 Oh 180,000.00 - 47,700.00 47,700.00
Jumlah Harga Satuan 3,508,870.00 818,600.00 4,327,470.00
Dibulatkan 3,508,870.00 818,600.00 4,327,470.00

6 1 Kg BESI BETON POLOS/ULIR SNI - 7394 -T-2008


Bahan :
Besi Beton Rata-rata 1.0500 kg 12,500.00 13,125.00 - 13,125.00
Kawat Beton 0.0150 kg 36,600.00 549.00 - 549.00
Tenaga Kerja :
Pekerja 0.0070 Oh 100,000.00 - 700.00 700.00
Tukang besi 0.0070 Oh 140,000.00 - 980.00 980.00
Kepala tukang besi 0.0007 Oh 150,000.00 - 105.00 105.00
Mandor 0.0004 Oh 180,000.00 - 72.00 72.00
Jumlah Harga Satuan 13,674.00 1,857.00 15,531.00
Dibulatkan 13,670.00 1,855.00 15,525.00

7 1 m2 PEK. WIREMESH M8 SNI - 7394 -T-2008


Bahan :
Wiremesh M8 1.0100 m² 668,500.00 675,185.00 - 675,185.00
Kawat las 0.1000 kg 45,800.00 4,580.00 - 4,580.00
Tenaga Kerja :
Pekerja terampil 0.1000 Oh 100,000.00 - 10,000.00 10,000.00
Tukang besi profil 0.0750 Oh 140,000.00 - 10,500.00 10,500.00
Kepala Tukang 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan 679,765.00 23,800.00 703,565.00
Dibulatkan 679,765.00 23,800.00 703,565.00

8 1 m2 BEKISTING DENGAN PAPAN SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0240 m3 2,165,600.00 51,974.40 - 51,974.40
Kayu Kaso 5/7 Lokal Alba 0.0170 m3 2,600,000.00 44,200.00 - 44,200.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.1200 Oh 100,000.00 - 12,000.00 12,000.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0500 Oh 150,000.00 - 7,500.00 7,500.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan 101,674.40 42,300.00 143,974.40
Dibulatkan 101,670.00 42,300.00 143,970.00

9 1 m2 PASANG BEKISTING UNTUK PONDASI SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0400 m3 2,165,600.00 86,624.00 - 86,624.00
Paku 0.3000 kg 13,000.00 3,900.00 - 3,900.00
Minyak bekisting 0.1000 ltr 1,500.00 150.00 - 150.00
Tenaga Kerja :
Pekerja 0.5200 Oh 100,000.00 - 52,000.00 52,000.00
Tukang kayu 0.2600 Oh 140,000.00 - 36,400.00 36,400.00
Kepala tukang kayu 0.0260 Oh 150,000.00 - 3,900.00 3,900.00
Mandor 0.0260 Oh 180,000.00 - 4,680.00 4,680.00
Jumlah Harga Satuan 90,674.00 96,980.00 187,654.00
Dibulatkan 90,670.00 96,980.00 187,650.00

10 1 m2 PASANG BEKISTING UNTUK SLOOF SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0450 m3 2,165,600.00 97,452.00 - 97,452.00
Paku 0.3000 kg 13,000.00 3,900.00 - 3,900.00
Minyak bekisting 0.1000 ltr 1,500.00 150.00 - 150.00
Tenaga Kerja :
Pekerja 0.5200 Oh 100,000.00 - 52,000.00 52,000.00
Tukang kayu 0.2600 Oh 140,000.00 - 36,400.00 36,400.00
Kepala tukang kayu 0.0260 Oh 150,000.00 - 3,900.00 3,900.00
Mandor 0.0260 Oh 180,000.00 - 4,680.00 4,680.00
Jumlah Harga Satuan 101,502.00 96,980.00 198,482.00
Dibulatkan 101,500.00 96,980.00 198,480.00

11 1 m2 PASANG BEKISTING UNTUK KOLOM SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0400 m3 2,165,600.00 86,624.00 - 86,624.00
Kayu Kaso 5/7 Lokal Kls.III 0.0170 m3 2,450,000.00 41,650.00 - 41,650.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.6600 Oh 100,000.00 - 66,000.00 66,000.00
Tukang kayu 0.3300 Oh 140,000.00 - 46,200.00 46,200.00
Kepala tukang kayu 0.0330 Oh 150,000.00 - 4,950.00 4,950.00
Mandor 0.0330 Oh 180,000.00 - 5,940.00 5,940.00
Jumlah Harga Satuan 133,774.00 123,090.00 256,864.00
Dibulatkan 133,770.00 123,090.00 256,860.00

12 1 m2 PASANG BEKISTING UNTUK BALOK SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0400 m3 2,165,600.00 86,624.00 - 86,624.00
Kayu Kaso 5/7 Lokal Kls.III 0.0180 m3 2,450,000.00 44,100.00 - 44,100.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.6600 Oh 100,000.00 - 66,000.00 66,000.00
Tukang kayu 0.3300 Oh 140,000.00 - 46,200.00 46,200.00
Kepala tukang kayu 0.0330 Oh 150,000.00 - 4,950.00 4,950.00
Mandor 0.0330 Oh 180,000.00 - 5,940.00 5,940.00
Jumlah Harga Satuan 136,224.00 123,090.00 259,314.00
Dibulatkan 136,220.00 123,090.00 259,310.00

13 1 m2 PASANG BEKISTING UNTUK LANTAI SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0400 m3 2,165,600.00 86,624.00 - 86,624.00
Kayu Kaso 5/7 Lokal Kls.III 0.0180 m3 2,650,000.00 47,700.00 - 47,700.00
Dolken Kayu Ø 8 - 10 P. 4m 6.0000 btg 45,500.00 273,000.00 - 273,000.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.6600 Oh 100,000.00 - 66,000.00 66,000.00
Tukang kayu 0.3300 Oh 140,000.00 - 46,200.00 46,200.00
Kepala tukang kayu 0.0330 Oh 150,000.00 - 4,950.00 4,950.00
Mandor 0.0330 Oh 180,000.00 - 5,940.00 5,940.00
Jumlah Harga Satuan 412,824.00 123,090.00 535,914.00
Dibulatkan 412,820.00 123,090.00 535,910.00

14 1 m2 PASANG BEKISTING UNTUK DINDING SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0300 m3 2,165,600.00 64,968.00 - 64,968.00
Kayu Kaso 5/7 Lokal Kls.III 0.0200 m3 2,450,000.00 49,000.00 - 49,000.00
Dolken Kayu Ø 8 - 10 P. 4m 3.0000 btg 45,500.00 136,500.00 - 136,500.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.6600 Oh 100,000.00 - 66,000.00 66,000.00
Tukang kayu 0.3300 Oh 140,000.00 - 46,200.00 46,200.00
Kepala tukang kayu 0.0330 Oh 150,000.00 - 4,950.00 4,950.00
Mandor 0.0330 Oh 180,000.00 - 5,940.00 5,940.00
Jumlah Harga Satuan 255,968.00 123,090.00 379,058.00
Dibulatkan 255,965.00 123,090.00 379,055.00

15 1 m2 PASANG BEKISTING UNTUK TANGGA SK.SNI-T-2001


Bahan :
Kayu Papan Kls. IV / Albasia (2xpakai) 0.0300 m3 2,165,600.00 64,968.00 - 64,968.00
Kayu Kaso 5/7 Lokal Kls.III 0.0150 m3 2,450,000.00 36,750.00 - 36,750.00
Dolken Kayu Ø 8 - 10 P. 4m 2.0000 btg 45,500.00 91,000.00 - 91,000.00
Paku 0.4000 kg 13,000.00 5,200.00 - 5,200.00
Minyak bekisting 0.1500 ltr 1,500.00 225.00 - 225.00
Tenaga Kerja :
Pekerja 0.6600 Oh 100,000.00 - 66,000.00 66,000.00
Tukang kayu 0.3300 Oh 140,000.00 - 46,200.00 46,200.00
Kepala tukang kayu 0.0330 Oh 150,000.00 - 4,950.00 4,950.00
Mandor 0.0330 Oh 180,000.00 - 5,940.00 5,940.00
Jumlah Harga Satuan 198,143.00 123,090.00 321,233.00
Dibulatkan 198,140.00 123,090.00 321,230.00

16 1 m2 BEKISTING DENGAN MULTIPLEK 9 MM SK.SNI-T-2001


Bahan :
Multiplek 9 mm ( 2 x pakai ) 0.3470 lbr 156,700.00 54,374.90 - 54,374.90
Kaso 5/7 Kls.II (2 x pakai) 0.0170 m3 2,450,000.00 41,650.00 - 41,650.00
Paku 0.5000 kg 13,000.00 6,500.00 - 6,500.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.1200 Oh 100,000.00 - 12,000.00 12,000.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0500 Oh 150,000.00 - 7,500.00 7,500.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Upah Bongkar Cetakan 1.0000 ls 1,000.00 - 1,000.00 1,000.00
Jumlah Harga Satuan 102,824.90 43,300.00 146,124.90
Dibulatkan 102,820.00 43,300.00 146,120.00

17 1 m2 BEKISTING DENGAN MULTIPLEK 12 MM SK.SNI-T-2001


Bahan :
Multiplek 12 mm (2 x pakai) 0.3470 lbr 212,800.00 73,841.60 - 73,841.60
Kaso 5/7 Kls.III (2 x pakai) 0.0170 m3 2,450,000.00 41,650.00 - 41,650.00
Paku 0.5000 kg 13,000.00 6,500.00 - 6,500.00
Minyak bekisting 0.2000 ltr 1,500.00 300.00 - 300.00
Tenaga Kerja :
Pekerja 0.1200 Oh 100,000.00 - 12,000.00 12,000.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0500 Oh 150,000.00 - 7,500.00 7,500.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Upah Bongkar Cetakan 1.0000 ls 1,250.00 - 1,250.00 1,250.00
Jumlah Harga Satuan 122,291.60 43,550.00 165,841.60
Dibulatkan 122,290.00 43,550.00 165,840.00
18 1 m2 BEKISTING LANTAI BETON DENGAN FLOOR DECK SK.SNI-T-2001
Bahan :
Floor DECK CD-45 Standard 1.0100 m² 132,000.00 133,320.00 - 133,320.00
Kawat las 0.1000 kg 45,800.00 4,580.00 - 4,580.00
Shear Connector 1.0000 ls 10,000.00 - 10,000.00 10,000.00
Tenaga Kerja :
Pekerja terampil 0.0500 Oh 100,000.00 - 5,000.00 5,000.00
Tukang besi profil 0.0300 Oh 140,000.00 - 4,200.00 4,200.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan 137,900.00 21,000.00 158,900.00
Dibulatkan 137,900.00 21,000.00 158,900.00

19 1 m3 BETON BERTULANG K-175 SITE MIX (1 PC ; 2 PS ; 3 KR ) SK.SNI-T-2001


Bahan :
Semen Portland ( PC TYPE I ) 6.8000 zak 77,200.00 524,960.00 - 524,960.00
Pasir Beton I 0.5000 m3 368,400.00 184,200.00 - 184,200.00
Batu Pecah / Split Ukuran 0,5 - 2 cm 0.9000 m3 250,000.00 225,000.00 - 225,000.00
Besi Beton U. 24 Rata-rata 132.0000 kg 12,500.00 1,650,000.00 - 1,650,000.00
Kawat Beton 3.0000 kg 36,600.00 109,800.00 - 109,800.00
Kayu Papan Kls. IV / Albasia (2xpakai) 0.1800 m3 2,165,600.00 389,808.00 - 389,808.00
Kaso 5/7 Kls.III (2 x pakai) 0.0600 m3 2,450,000.00 147,000.00 - 147,000.00
Paku 2.4000 kg 25,000.00 60,000.00 - 60,000.00
Alat bantu 1.0000 ls 15,000.00 15,000.00 - 15,000.00
Tenaga Kerja :
Pekerja 2.9000 Oh. 100,000.00 - 290,000.00 290,000.00
Tukang batu 0.5000 Oh. 140,000.00 - 70,000.00 70,000.00
Tukang besi 2.1600 Oh. 140,000.00 - 302,400.00 302,400.00
Tukang kayu 0.6300 Oh. 140,000.00 - 88,200.00 88,200.00
Kepala tukang 0.4370 Oh. 150,000.00 - 65,550.00 65,550.00
Mandor 0.0437 Oh 180,000.00 - 7,866.00 7,866.00
Jumlah Harga Satuan 3,305,768.00 824,016.00 4,129,784.00
Dibulatkan 3,305,765.00 824,015.00 4,129,780.00

20 1 m2 PASANGAN STOOT WERK SK.SNI-T-2001


Bahan :
Kayu stoot ( dinding 2x pakai ) 50% 9.0000 btg 45,500.00 409,500.00 - 409,500.00
Kayu Papan albasia ( 2X pakai ) 0.0160 m3 2,165,600.00 34,649.60 - 34,649.60
Paku 5 - 7 cm 0.5000 kg 13,000.00 6,500.00 - 6,500.00
Tenaga Kerja :
Pekerja 0.3500 Oh 100,000.00 - 35,000.00 35,000.00
Tukang kayu 1.0000 Oh 140,000.00 - 140,000.00 140,000.00
Kepala tukang kayu 0.1020 Oh 150,000.00 - 15,300.00 15,300.00
Mandor 0.0180 Oh 180,000.00 - 3,240.00 3,240.00
Jumlah Harga Satuan 450,649.60 193,540.00 644,189.60
Dibulatkan 450,645.00 193,540.00 644,185.00

V. PENETAPAN INDEK HARGA SATUAN PEKERJAAN DINDING dan PENGISI


1 1 m2 PASANGAN DINDING 1/2 BATA ( 1PC ; 6 Psr) SNI : 6897 T-2008
Bahan :
Bata Merah Bakar 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 8.3200 Kg 1,544.00 12,846.08 - 12,846.08
Pasir Pasang 0.0490 m3 359,200.00 17,600.80 - 17,600.80
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 90,646.88 48,200.00 138,846.88
Dibulatkan 90,645.00 48,200.00 138,845.00

2 1 m2 PASANGAN DINDING 1/2 BATA ( 1PC ; 5 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 9.6800 Kg 1,544.00 14,945.92 - 14,945.92
Pasir Pasang 0.0450 m3 359,200.00 16,164.00 - 16,164.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 91,309.92 48,200.00 139,509.92
Dibulatkan 91,305.00 48,200.00 139,505.00

3 1 m2 PASANGAN DINDING 1/2 BATA ( 1PC ; 4 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 11.5000 Kg 1,544.00 17,756.00 - 17,756.00
Pasir Pasang 0.0430 m3 359,200.00 15,445.60 - 15,445.60
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 93,401.60 48,200.00 141,601.60
Dibulatkan 93,400.00 48,200.00 141,600.00

4 1 m2 PASANGAN DINDING 1/2 BATA ( 1PC ; 3 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 14.3700 Kg 1,544.00 22,187.28 - 22,187.28
Pasir Pasang 0.0400 m3 359,200.00 14,368.00 - 14,368.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 96,755.28 48,200.00 144,955.28
Dibulatkan 96,755.00 48,200.00 144,955.00

5 1 m2 PASANGAN DINDING 1 BATA ( 1PC ; 6 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 140.0000 bh 860.00 120,400.00 - 120,400.00
Semen Portland ( PC TYPE I ) 18.5000 Kg 1,544.00 28,564.00 - 28,564.00
Pasir Pasang 0.1220 m3 359,200.00 43,822.40 - 43,822.40
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 192,786.40 96,400.00 289,186.40
Dibulatkan 192,785.00 96,400.00 289,185.00

6 1 m2 PASANGAN DINDING 1 BATA ( 1PC ; 5 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 140.0000 bh 860.00 120,400.00 - 120,400.00
Semen Portland ( PC TYPE I ) 22.2000 Kg 1,544.00 34,276.80 - 34,276.80
Pasir Pasang 0.1020 m3 359,200.00 36,638.40 - 36,638.40
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 191,315.20 96,400.00 287,715.20
Dibulatkan 191,315.00 96,400.00 287,715.00

7 1 m2 PASANGAN DINDING 1 BATA ( 1PC ; 4 Psr) SNI : 6897 T-2008


Bahan :
Bata Merah Bakar 140.0000 bh 860.00 120,400.00 - 120,400.00
Semen Portland ( PC TYPE I ) 26.5500 Kg 1,544.00 40,993.20 - 40,993.20
Pasir Pasang 0.0930 m3 359,200.00 33,405.60 - 33,405.60
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 194,798.80 96,400.00 291,198.80
Dibulatkan 194,795.00 96,400.00 291,195.00

8 1 m2 PASANGAN DINDING BATA EKSPOSED Uk. (5x11x24) cm Campuran 1PC ; 4 Psr SNI : 6897 T-2008
Bahan :
Bata berongga ekspose 70.0000 bh 860.00 60,200.00 - 60,200.00
Semen Portland ( PC TYPE I ) 14.0000 Kg 1,544.00 21,616.00 - 21,616.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 93,310.40 55,950.00 149,260.40
Dibulatkan 93,310.00 55,950.00 149,260.00

9 1 m2 PASANGAN BATA TERAWANG (ROSTER Uk. 12x11x24 cm) 1PC ; 3 Psr SNI : 6897 T-2008
Bahan :
Bata Terawang (Rooster) 30.0000 bh 4,500.00 135,000.00 - 135,000.00
Semen Portland ( PC TYPE I ) 14.0000 Kg 1,544.00 21,616.00 - 21,616.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 168,110.40 48,200.00 216,310.40
Dibulatkan 168,110.00 48,200.00 216,310.00

10 1 m2 PASANGAN BATA TERAWANG (ROOSTER Uk. 12x11x24 cm) 1PC ; 4 Psr SNI : 6897 T-2008
Bahan :
Bata Terawang (Rooster) 30.0000 bh 4,500.00 135,000.00 - 135,000.00
Semen Portland ( PC TYPE I ) 11.0000 Kg 1,544.00 16,984.00 - 16,984.00
Pasir Pasang 0.0350 m3 359,200.00 12,572.00 - 12,572.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 164,556.00 48,200.00 212,756.00
Dibulatkan 164,555.00 48,200.00 212,755.00

11 1 Bh PASANGAN GLASSBLOCK DN (Uk. 11,5 x 18,5 x 18,5 cm) 1PC ; 5 Psr SNI : 6897 T-2008
Bahan :
Glassblock DN 1.0000 bh 38,600.00 38,600.00 - 38,600.00
Semen Portland ( PC TYPE I ) 0.4400 Kg 1,544.00 679.36 - 679.36
Pasir Pasang 0.0014 m3 359,200.00 502.88 - 502.88
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.0040 Oh 140,000.00 - 560.00 560.00
Kepala tukang batu 0.0004 Oh 150,000.00 - 60.00 60.00
Mandor 0.0006 Oh 180,000.00 - 108.00 108.00
Jumlah Harga Satuan 39,782.24 1,728.00 41,510.24
Dibulatkan 39,780.00 1,725.00 41,505.00

VI. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PLESTERAN dan ACIAN


1 1 m2 PLESTERAN DINDING T. 20 mm ( 1 PC ; 2 PSR ) SK.SNI T-03-1991-03
Bahan :
Semen Portland ( PC TYPE I ) 13.6320 Kg 1,544.00 21,047.81 - 21,047.81
Pasir Pasang 0.0270 m3 359,200.00 9,698.40 - 9,698.40
Tenaga Kerja :
Pekerja 0.4000 Oh 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0220 Oh 180,000.00 - 3,960.00 3,960.00
Jumlah Harga Satuan 30,746.21 74,960.00 105,706.21
Dibulatkan 30,745.00 74,960.00 105,705.00

2 1 m2 PLESTERAN DINDING T. 20 mm ( 1 PC ; 3 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 10.3680 Kg 1,544.00 16,008.19 - 16,008.19
Pasir Pasang 0.0310 m3 359,200.00 11,135.20 - 11,135.20
Tenaga Kerja :
Pekerja 0.2600 Oh 100,000.00 - 26,000.00 26,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0130 Oh 180,000.00 - 2,340.00 2,340.00
Jumlah Harga Satuan 27,143.39 59,340.00 86,483.39
Dibulatkan 27,140.00 59,340.00 86,480.00

3 1 m2 PLESTERAN DINDING T. 20 mm ( 1 PC ; 4 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 8.3200 Kg 1,544.00 12,846.08 - 12,846.08
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Tenaga Kerja :
Pekerja 0.4000 Oh 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0220 Oh 180,000.00 - 3,960.00 3,960.00
Jumlah Harga Satuan 24,340.48 74,960.00 99,300.48
Dibulatkan 24,340.00 74,960.00 99,300.00
4 1 m2 PLESTERAN DINDING T. 20 mm ( 1 PC ; 5 PSR ) SK.SNI T-03-1991-03
Bahan :
Semen Portland ( PC TYPE I ) 6.9120 Kg 1,544.00 10,672.13 - 10,672.13
Pasir Pasang 0.0350 m3 359,200.00 12,572.00 - 12,572.00
Tenaga Kerja :
Pekerja 0.4000 Oh 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0220 Oh 180,000.00 - 3,960.00 3,960.00
Jumlah Harga Satuan 23,244.13 74,960.00 98,204.13
Dibulatkan 23,240.00 74,960.00 98,200.00

5 1 m2 PLESTERAN DINDING T. 20 mm ( 1 PC ; 6 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 5.8880 Kg 1,544.00 9,091.07 - 9,091.07
Pasir Pasang 0.0360 m3 359,200.00 12,931.20 - 12,931.20
Tenaga Kerja :
Pekerja 0.4000 Oh 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0220 Oh 180,000.00 - 3,960.00 3,960.00
Jumlah Harga Satuan 22,022.27 74,960.00 96,982.27
Dibulatkan 22,020.00 74,960.00 96,980.00

6 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 1 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 15.5040 Kg 1,544.00 23,938.18 - 23,938.18
Pasir Pasang 0.0160 m3 359,200.00 5,747.20 - 5,747.20
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 29,685.38 55,950.00 85,635.38
Dibulatkan 29,685.00 55,950.00 85,635.00

7 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 2 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 10.2240 Kg 1,544.00 15,785.86 - 15,785.86
Pasir Pasang 0.0200 m3 359,200.00 7,184.00 - 7,184.00
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 22,969.86 55,950.00 78,919.86
Dibulatkan 22,965.00 55,950.00 78,915.00

8 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 3 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 7.7760 Kg 1,544.00 12,006.14 - 12,006.14
Pasir Pasang 0.0230 m3 359,200.00 8,261.60 - 8,261.60
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 20,267.74 55,950.00 76,217.74
Dibulatkan 20,265.00 55,950.00 76,215.00

9 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 4 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 6.2400 Kg 1,544.00 9,634.56 - 9,634.56
Pasir Pasang 0.0240 m3 359,200.00 8,620.80 - 8,620.80
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 18,255.36 55,950.00 74,205.36
Dibulatkan 18,255.00 55,950.00 74,205.00

10 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 5 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 5.1840 Kg 1,544.00 8,004.10 - 8,004.10
Pasir Pasang 0.0260 m3 359,200.00 9,339.20 - 9,339.20
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 17,343.30 55,950.00 73,293.30
Dibulatkan 17,340.00 55,950.00 73,290.00

11 1 m2 PLESTERAN DINDING T. 15 mm ( 1 PC ; 6 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 4.4160 Kg 1,544.00 6,818.30 - 6,818.30
Pasir Pasang 0.0270 m3 359,200.00 9,698.40 - 9,698.40
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 16,516.70 55,950.00 72,466.70
Dibulatkan 16,515.00 55,950.00 72,465.00

12 1 m2 PLESTERAN T. 15 MM ( 1 PC ; 7 PSR ) SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 3.9360 Kg 1,544.00 6,077.18 - 6,077.18
Pasir Pasang 0.0280 m3 359,200.00 10,057.60 - 10,057.60
Tenaga Kerja :
Pekerja 0.3000 Oh 100,000.00 - 30,000.00 30,000.00
Tukang batu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang batu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0150 Oh 180,000.00 - 2,700.00 2,700.00
Jumlah Harga Satuan 16,134.78 55,950.00 72,084.78
Dibulatkan 16,130.00 55,950.00 72,080.00

13 1 m2 ACIAN DINDING BATA SK.SNI T-03-1991-03


Bahan :
Semen Portland ( PC TYPE I ) 3.2500 Kg 1,544.00 5,018.00 - 5,018.00
Tenaga Kerja :
Pekerja 0.2000 Oh 100,000.00 - 20,000.00 20,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0100 Oh 180,000.00 - 1,800.00 1,800.00
Jumlah Harga Satuan 5,018.00 37,300.00 42,318.00
Dibulatkan 5,015.00 37,300.00 42,315.00

VII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan PELAPIS DINDING

1 1 m2 PASANGAN KERAMIK LANTAI 40x40, PUTIH/POLOS SK.SNI T-03-3976-1995


Bahan :
Keramik lantai 40x40 1.0100 m2 61,900.00 62,519.00 - 62,519.00
Pasir Pasang 0.0420 m3 359,200.00 15,086.40 - 15,086.40
Semen Portland ( PC TYPE I ) 11.3800 kg 1,544.00 17,570.72 - 17,570.72
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0125 Oh 180,000.00 - 2,250.00 2,250.00
Jumlah Harga Satuan 115,176.12 46,625.00 161,801.12
Dibulatkan 115,175.00 46,625.00 161,800.00

2 1 m2 PASANGAN KERAMIK LANTAI 40x40, WARNA/CORAK SK.SNI T-03-3976-1995


Bahan :
Keramik lantai 40x40 Warna/Corak 1.0100 m2 53,000.00 53,530.00 - 53,530.00
Pasir Pasang 0.0420 m3 359,200.00 15,086.40 - 15,086.40
Semen Portland ( PC TYPE I ) 11.3800 kg 1,544.00 17,570.72 - 17,570.72
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0125 Oh 180,000.00 - 2,250.00 2,250.00
Jumlah Harga Satuan 106,187.12 46,625.00 152,812.12
Dibulatkan 106,185.00 46,625.00 152,810.00

3 1 m2 PASANGAN KERAMIK LANTAI 30x30, PUTIH/POLOS SK.SNI T-03-3976-1995


Bahan :
Keramik lantai 30x30 1.0100 m2 49,100.00 49,591.00 - 49,591.00
Pasir Pasang 0.0420 m3 359,200.00 15,086.40 - 15,086.40
Semen Portland ( PC TYPE I ) 11.3800 kg 1,544.00 17,570.72 - 17,570.72
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0125 Oh 180,000.00 - 2,250.00 2,250.00
Jumlah Harga Satuan 102,248.12 46,625.00 148,873.12
Dibulatkan 102,245.00 46,625.00 148,870.00

4 1 m2 PASANGAN KERAMIK LANTAI 30x30, WARNA/CORAK SK.SNI T-03-3976-1995


Bahan :
Keramik lantai 30x30, Warna/ Corak 1.0100 m2 89,200.00 90,092.00 - 90,092.00
Pasir Pasang 0.0420 m3 359,200.00 15,086.40 - 15,086.40
Semen Portland ( PC TYPE I ) 11.3800 kg 1,544.00 17,570.72 - 17,570.72
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0125 Oh 180,000.00 - 2,250.00 2,250.00
Jumlah Harga Satuan 142,749.12 46,625.00 189,374.12
Dibulatkan 142,745.00 46,625.00 189,370.00

5 1 m2 PASANGAN KERAMIK LANTAI 20x20, CORAK / ANTI SLIP SK.SNI T-03-3976-1995


Bahan :
Keramik 20x20 Warna / Corak 1.0100 m2 47,000.00 47,470.00 - 47,470.00
Pasir Pasang 0.0420 m3 359,200.00 15,086.40 - 15,086.40
Semen Portland ( PC TYPE I ) 11.3800 kg 1,544.00 17,570.72 - 17,570.72
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0125 Oh 180,000.00 - 2,250.00 2,250.00
Jumlah Harga Satuan 100,127.12 46,625.00 146,752.12
Dibulatkan 100,125.00 46,625.00 146,750.00

6 1 m2 PASANGAN KERAMIK DINDING 20x25 WARNA/CORAK KW.I DN SK.SNI T-03-3976-1995


Bahan :
Keramik 20/25 KW.I DN Warna / Corak 1.0100 m2 49,400.00 49,894.00 - 49,894.00
Pasir Pasang 0.0180 m3 359,200.00 6,465.60 - 6,465.60
Semen Portland ( PC TYPE I ) 9.3000 kg 1,544.00 14,359.20 - 14,359.20
Semen Warna untuk Grouting 1.5000 kg 13,000.00 19,500.00 - 19,500.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang batu 0.1250 Oh 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0125 Oh 150,000.00 - 1,875.00 1,875.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 90,718.80 84,775.00 175,493.80
Dibulatkan 90,715.00 84,775.00 175,490.00

7 1 m1 PASANGAN PLINT KERAMIK 10x30 PUTIH/POLOS SK.SNI T-03-3976-1995


Bahan :
Keramik 10 x 30 cm 4.0000 m1 1,487.88 5,951.52 - 5,951.52
Semen portland 1.1380 Kg 1,544.00 1,757.07 - 1,757.07
Pasir pasang 0.0042 m3 1,544.00 6.48 - 6.48
Semen warna 0.1500 Kg 13,000.00 1,950.00 - 1,950.00
Alat ( potong keramik ) 1.0000 ls 500.00 500.00 - 500.00
Tenaga Kerja :
Pekerja 0.0620 Oh 100,000.00 - 6,200.00 6,200.00
Tukang batu 0.0350 Oh 140,000.00 - 4,900.00 4,900.00
Kepala tukang batu 0.0035 Oh 150,000.00 - 525.00 525.00
Mandor 0.0030 Oh 180,000.00 - 540.00 540.00
Jumlah Harga Satuan 10,165.07 12,165.00 22,330.07
Dibulatkan 10,165.00 12,165.00 22,330.00

8 1 m1 PASANGAN STAIR NOZING 5 x 30 cm SK.SNI T-03-3976-1995


Bahan :
Stair Nozing 5 x 30 cm 3.3333 m1 7,500.00 25,000.00 - 25,000.00
Semen portland 0.5690 Kg 1,544.00 878.54 - 878.54
Pasir pasang 0.0021 m3 1,544.00 3.24 - 3.24
Semen warna 0.0750 Kg 13,000.00 975.00 - 975.00
Tenaga Kerja :
Pekerja 0.0310 Oh 100,000.00 - 3,100.00 3,100.00
Tukang batu 0.0175 Oh 140,000.00 - 2,450.00 2,450.00
Kepala tukang batu 0.0018 Oh 150,000.00 - 262.50 262.50
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 26,856.78 6,082.50 32,939.28
Dibulatkan 26,855.00 6,080.00 32,935.00

9 1 m1 PAS, BORDER DINDING KERAMIK/LIST 5 x 20 cm SK.SNI T-03-3976-1995


Bahan :
List Keramik 5 x 20 cm 5.0000 bh 12,500.00 62,500.00 - 62,500.00
Semen portland 0.7966 Kg 1,544.00 1,229.95 - 1,229.95
Pasir pasang 0.0029 m3 1,544.00 4.54 - 4.54
Semen warna 0.1050 Kg 13,000.00 1,365.00 - 1,365.00
Tenaga Kerja :
Pekerja 0.0434 Oh 100,000.00 - 4,340.00 4,340.00
Tukang batu 0.0245 Oh 140,000.00 - 3,430.00 3,430.00
Kepala tukang batu 0.0025 Oh 150,000.00 - 367.50 367.50
Mandor 0.0021 Oh 180,000.00 - 378.00 378.00
Jumlah Harga Satuan 65,099.49 8,515.50 73,614.99
Dibulatkan 65,095.00 8,515.00 73,610.00

VIII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PENGECATAN dan LABURAN


1 1 m2 PENGECATAN DINDING BARU ( 1 PLAMIR, 1 CAT DASAR dan 2 CAT PENUTUP) 3x SK.SNI T-03-2407-1991
Bahan :
Plamir Tembok 0.1000 kg 21,000.00 2,100.00 - 2,100.00
Cat Dasar 0.1000 kg 70,000.00 7,000.00 - 7,000.00
Cat Penutup 0.2600 kg 41,000.00 10,660.00 - 10,660.00
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 500.00 500.00 - 500.00
Amplas 0.5000 lbr 4,000.00 2,000.00 - 2,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0630 Oh. 140,000.00 - 8,820.00 8,820.00
Kepala tukang cat 0.0140 Oh. 150,000.00 - 2,100.00 2,100.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 22,459.00 13,370.00 35,829.00
Dibulatkan 22,455.00 13,370.00 35,825.00

2 1 m2 PENGECATAN DINDING TEMBOK LAMA ( 1 CAT DASAR dan 2 CAT PENUTUP) 2x SK.SNI T-03-2407-1991
Bahan :
Cat Dasar 0.1200 kg 70,000.00 8,400.00 - 8,400.00
Cat Penutup 2x 0.1800 kg 41,000.00 7,380.00 - 7,380.00
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 500.00 500.00 - 500.00
Amplas 0.5000 lbr 4,000.00 2,000.00 - 2,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0420 Oh. 140,000.00 - 5,880.00 5,880.00
Kepala tukang cat 0.0042 Oh. 150,000.00 - 630.00 630.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 18,479.00 8,960.00 27,439.00
Dibulatkan 18,475.00 8,960.00 27,435.00
3 1 m2 PENGECATAN DINDING EXTERIOR SK.SNI T-03-2410-1991
Bahan :
Cat tembok exterior 0.2500 kg 50,000.00 12,500.00 - 12,500.00
Alkali ICI sebelum pengecatan 0.1250 lt 7,500.00 937.50 - 937.50
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Amplas 0.5000 lbr 4,000.00 2,000.00 - 2,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0630 Oh. 140,000.00 - 8,820.00 8,820.00
Kepala tukang cat 0.0140 Oh. 150,000.00 - 2,100.00 2,100.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 15,886.50 13,370.00 29,256.50
Dibulatkan 15,885.00 13,370.00 29,255.00

4 1 m2 PENGECATAN BIDANG PLAFOND BARU 3 x PELAKSANAAN SK.SNI T-03-2407-1991


Bahan :
Plamir tembok 0.1600 kg 21,000.00 3,360.00 - 3,360.00
Cat Dasar 0.1000 kg 70,000.00 7,000.00 - 7,000.00
Cat Penutup 0.2600 kg 41,000.00 10,660.00 - 10,660.00
Roll cat 0.0100 bh 19,900.00 199.00 - 199.00
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Amplas 0.0000 lbr 4,000.00 - - -
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0420 Oh. 140,000.00 - 5,880.00 5,880.00
Kepala tukang cat 0.0042 Oh. 150,000.00 - 630.00 630.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 21,469.00 8,960.00 30,429.00
Dibulatkan 21,465.00 8,960.00 30,425.00

5 1 m2 PENGECATAN BIDANG PLAFOND BARU 2 x PELAKSANAAN SK.SNI T-03-2407-1991


Bahan :
Plamir tembok 0.0000 kg 21,000.00 - - -
Cat Dasar 0.1000 kg 70,000.00 7,000.00 - 7,000.00
Cat Penutup 0.1333 kg 41,000.00 5,465.30 - 5,465.30
Roll cat 0.0067 bh 19,900.00 133.33 - 133.33
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Amplas 0.0000 lbr 4,000.00 - - -
Tenaga Kerja :
Pekerja 0.0200 Oh. 100,000.00 - 2,000.00 2,000.00
Tukang cat 0.0420 Oh. 140,000.00 - 5,880.00 5,880.00
Kepala tukang cat 0.0042 Oh. 150,000.00 - 630.00 630.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 12,848.63 8,960.00 21,808.63
Dibulatkan 12,845.00 8,960.00 21,805.00

6 1 m2 PENGECATAN KAYU (3X) BERIKUT MENI SK.SNI T-2001


Bahan :
Meni kayu 0.1670 kg 22,900.00 3,824.30 - 3,824.30
Plamir kayu 0.0830 kg 33,750.00 2,801.25 - 2,801.25
Cat Kayu AVIAN 0.3500 kg 73,200.00 25,620.00 - 25,620.00
Amplas kayu 0.2000 lbr 4,000.00 800.00 - 800.00
Minyak cat terpentin 0.1500 ltr 68,600.00 10,290.00 - 10,290.00
Kwas 3" 0.0500 bh 1,900.00 95.00 - 95.00
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Tenaga Kerja :
Pekerja 0.0700 Oh. 100,000.00 - 7,000.00 7,000.00
Tukang cat 0.1050 Oh. 140,000.00 - 14,700.00 14,700.00
Kepala tukang cat 0.0040 Oh. 150,000.00 - 600.00 600.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 43,680.55 22,750.00 66,430.55
Dibulatkan 43,680.00 22,750.00 66,430.00

7 1 m2 PENGECATAN BIDANG BESI / LOGAM (3X) BERIKUT MENI SK.SNI T-2001


Bahan :
Meni Besi 0.1670 kg 36,600.00 6,112.20 - 6,112.20
Cat Besi merk SEIV 0.2000 kg 78,900.00 15,780.00 - 15,780.00
Amplas kayu 0.2500 lbr 4,000.00 1,000.00 - 1,000.00
Thinner 0.1500 ltr 26,600.00 3,990.00 - 3,990.00
Kwas 3" 0.0500 bh 1,900.00 95.00 - 95.00
Seiger werk 1.0000 ls 250.00 250.00 - 250.00
Tenaga Kerja :
Pekerja 0.0700 Oh. 100,000.00 - 7,000.00 7,000.00
Tukang cat 0.1050 Oh. 140,000.00 - 14,700.00 14,700.00
Kepala tukang cat 0.0040 Oh. 150,000.00 - 600.00 600.00
Mandor 0.0025 Oh. 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 27,227.20 22,750.00 49,977.20
Dibulatkan 27,225.00 22,750.00 49,975.00

8 1 m2 PELABURAN BIDANG KAYU DENGAN RESIDU / SULIGNEM DAN TER (WOOD TREATMENT) SK.SNI T-2001
Bahan :
Residu 0.3500 ltr 60,000.00 21,000.00 - 21,000.00
Kwas 3" 0.0500 bh 1,900.00 95.00 - 95.00
Steiger werk 0.5000 ls 250.00 125.00 - 125.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Mandor 0.0060 Oh. 180,000.00 - 1,080.00 1,080.00
Jumlah Harga Satuan 21,220.00 11,080.00 32,300.00
Dibulatkan 21,220.00 11,080.00 32,300.00

9 1 m2 PELABURAN KAYU BARU DENGAN MELAMIC SK.SNI T-2001


Bahan :
Wood Filler 0.2800 Kg 45,000.00 12,600.00 - 12,600.00
Wood Stain 0.1333 Kg 86,400.00 11,520.00 - 11,520.00
Melamin Sending Siller MSS 123 0.2200 Kg 43,200.00 9,504.00 - 9,504.00
ML 131 Clear Danagloss 0.2200 Kg 57,300.00 12,606.00 - 12,606.00
Tiner 1.3000 Ltr 26,600.00 34,580.00 - 34,580.00
Ampelas 4.0000 Lbr 4,000.00 16,000.00 - 16,000.00
Kwas 3" 0.5000 Bh 1,900.00 950.00 - 950.00
Alat Bantu dll 1.0000 Ls 5,000.00 5,000.00 - 5,000.00
Tenaga Kerja :
Pekerja 0.4200 Oh 100,000.00 - 42,000.00 42,000.00
Tukang cat/Politur 0.3600 Oh 140,000.00 - 50,400.00 50,400.00
Kepala tukang cat 0.0360 Oh 150,000.00 - 5,400.00 5,400.00
Mandor 0.0210 Oh 180,000.00 - 3,780.00 3,780.00
Jumlah Harga Satuan 102,760.00 101,580.00 204,340.00
Dibulatkan 102,760.00 101,580.00 204,340.00

10 1 m2 POLITURAN BIASA ( UNTUK PEKERJAAN KUSEN PINTU dan JENDELA) SK.SNI T-2001
Bahan :
Dempul plitur (dempul kasar) 0.0300 kg 52,000.00 1,560.00 - 1,560.00
Wood Filer (INFRA) 0.2000 kg 45,000.00 9,000.00 - 9,000.00
Oker putih 0.0200 kg 12,500.00 250.00 - 250.00
Oker warna 0.0100 bks 50,000.00 500.00 - 500.00
Batu Apung (gosok) 0.1000 kg 8,300.00 830.00 - 830.00
Sirlak ex India 0.2000 kg 34,999.00 6,999.80 - 6,999.80
Kwas 3" 0.0100 bh 1,900.00 19.00 - 19.00
Spirtus 0.2000 ltr 15,000.00 3,000.00 - 3,000.00
Ampelas kayu 0.1000 lbr 4,000.00 400.00 - 400.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang cat/politur 0.2850 Oh 140,000.00 - 39,900.00 39,900.00
Kepala tukang cat/politur 0.0400 Oh 150,000.00 - 6,000.00 6,000.00
Mandor 0.0200 Oh 180,000.00 - 3,600.00 3,600.00
Jumlah Harga Satuan 22,558.80 74,500.00 97,058.80
Dibulatkan 22,555.00 74,500.00 97,055.00

11 1 m2 POLITURAN BIASA (UNTUK MEBEULAIR) SK.SNI T-2001


Bahan :
Dempul plitur (dempul kasar) 0.0300 kg 52,000.00 1,560.00 - 1,560.00
Wood Filer (INFRA) 0.0750 kg 45,000.00 3,375.00 - 3,375.00
Oker putih 0.0200 kg 12,500.00 250.00 - 250.00
Oker warna 0.0100 bks 50,000.00 500.00 - 500.00
Batu Apung (gosok) 0.0500 kg 8,300.00 415.00 - 415.00
Sirlak ex India 0.1500 kg 34,999.00 5,249.85 - 5,249.85
Kwas 3" 0.0100 bh 1,900.00 19.00 - 19.00
Spirtus 0.1500 ltr 15,000.00 2,250.00 - 2,250.00
Ampelas kayu 0.1000 lbr 4,000.00 400.00 - 400.00
Tenaga Kerja :
Pekerja 0.2500 Oh 100,000.00 - 25,000.00 25,000.00
Tukang cat/politur 0.2850 Oh 140,000.00 - 39,900.00 39,900.00
Kepala tukang cat/politur 0.0400 Oh 150,000.00 - 6,000.00 6,000.00
Mandor 0.0200 Oh 180,000.00 - 3,600.00 3,600.00
Jumlah Harga Satuan 14,018.85 74,500.00 88,518.85
Dibulatkan 14,015.00 74,500.00 88,515.00

IX. PENETAPAN INDEK HARGA SATUAN PEKERJAAN STRUKTUR ATAP


1 1 m3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II (BARU) SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 1.1000 m3 3,684,900.00 4,053,390.00 - 4,053,390.00
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 4,365,640.00 2,296,000.00 6,661,640.00
Dibulatkan 4,365,640.00 2,296,000.00 6,661,640.00

2 1 m3 KONSTRUKSI KUDA-KUDA KONVESIONAL, KAYU LAMA (KELAS II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 0.0000 m3 3,684,900.00 - - -
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 312,250.00 2,296,000.00 2,608,250.00
Dibulatkan 312,250.00 2,296,000.00 2,608,250.00

3 1 m3 KONSTRUKSI GORDENG dan KOMPONEN ATAP (BAHAN KAYU KLS.II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 1.1000 m3 3,684,900.00 4,053,390.00 - 4,053,390.00
Paku 08 - 12 cm 3.0000 kg 25,000.00 75,000.00 - 75,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 2.4000 Oh. 100,000.00 - 240,000.00 240,000.00
Tukang kayu 7.2000 Oh. 140,000.00 - 1,008,000.00 1,008,000.00
Kepala tukang kayu 0.7200 Oh. 150,000.00 - 108,000.00 108,000.00
Mandor 0.1200 Oh. 180,000.00 - 21,600.00 21,600.00
Jumlah Harga Satuan 4,295,640.00 1,377,600.00 5,673,240.00
Dibulatkan 4,295,640.00 1,377,600.00 5,673,240.00

4 1 m3 KONSTRUKSI GORDENG dan KOMPONEN ATAP (BAHAN KAYU KLS.II) KAYU LAMA SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 0.0000 m3 3,684,900.00 - - -
Paku 08 - 12 cm 3.0000 kg 25,000.00 75,000.00 - 75,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 2.4000 Oh. 100,000.00 - 240,000.00 240,000.00
Tukang kayu 7.2000 Oh. 140,000.00 - 1,008,000.00 1,008,000.00
Kepala tukang kayu 0.7200 Oh. 150,000.00 - 108,000.00 108,000.00
Mandor 0.1200 Oh. 180,000.00 - 21,600.00 21,600.00
Jumlah Harga Satuan 242,250.00 1,377,600.00 1,619,850.00
Dibulatkan 242,250.00 1,377,600.00 1,619,850.00

5 1 m3 KUDA-KUDA KAYU BORNEO SUPER SK.SNI T-2001 & PKKI NI-5


Bahan :
Balok kayu Borneo Super 1.1000 m3 1,530,000.00 1,683,000.00 - 1,683,000.00
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 1,995,250.00 2,296,000.00 4,291,250.00
Dibulatkan 1,995,250.00 2,296,000.00 4,291,250.00

6 1 m3 KUDA-KUDA KAYU OVERSTEK / KONSOL (EKSPOSE) KAYU LOKAL KLS.II SK.SNI T-2001 & PKKI NI-5
Bahan :
Balok kayu Kls II 1.2000 m3 3,684,900.00 4,421,880.00 - 4,421,880.00
Paku 08 - 12 cm 5.8000 kg 25,000.00 145,000.00 - 145,000.00
Besi strip 15.0000 kg 11,150.00 167,250.00 - 167,250.00
Tenaga Kerja :
Pekerja 4.0000 Oh. 100,000.00 - 400,000.00 400,000.00
Tukang kayu 12.0000 Oh. 140,000.00 - 1,680,000.00 1,680,000.00
Kepala tukang kayu 1.2000 Oh. 150,000.00 - 180,000.00 180,000.00
Mandor 0.2000 Oh. 180,000.00 - 36,000.00 36,000.00
Jumlah Harga Satuan 4,734,130.00 2,296,000.00 7,030,130.00
Dibulatkan 4,734,130.00 2,296,000.00 7,030,130.00

7 1 m2 RANGKA ATAP BARU (KAYU BORNEO) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso 5/7 Kayu Borneo super 0.0140 m3 1,530,000.00 21,420.00 - 21,420.00
Reng Kayu 2/3 Borneo super 0.0036 m3 1,530,000.00 5,508.00 - 5,508.00
Paku 04 - 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 30,678.00 26,400.00 57,078.00
Dibulatkan 30,675.00 26,400.00 57,075.00

8 1 m2 RANGKA ATAP BARU (KAYU lokal KLS.II) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso-kaso (5x7) cm 0.0140 m3 3,684,900.00 51,588.60 - 51,588.60
Reng (2x3) cm 0.0036 m3 3,684,900.00 13,265.64 - 13,265.64
Paku 5 cm dan 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 68,604.24 26,400.00 95,004.24
Dibulatkan 68,600.00 26,400.00 95,000.00

9 1 m2 RANGKA ATAP RENG 2/3 BARU (KASO KAYU LAMA ) SK.SNI T-2001 & PKKI NI-5
Bahan :
Kaso-kaso (5x7) cm 0.0000 m3 3,684,900.00 - - -
Reng (2x3) cm 0.0036 m3 3,684,900.00 13,265.64 - 13,265.64
Paku 5 cm dan 10 cm 0.1500 kg 25,000.00 3,750.00 - 3,750.00
Tenaga Kerja :
Pekerja 0.1000 Oh. 100,000.00 - 10,000.00 10,000.00
Tukang kayu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh. 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 17,015.64 26,400.00 43,415.64
Dibulatkan 17,015.00 26,400.00 43,415.00

10 1 m2 KONSTRUKSI KAP BAJA RINGAN


Bahan / Alat / Upah :
Rangka & Kuda-kuda Atap Baja Ringan ( 1.0000 m2 120,000.00 120,000.00 - 120,000.00

Jumlah Harga Satuan 120,000.00 - 120,000.00


PPn 10% 12,000.00 - 12,000.00
Jumlah + Pajak (PPn) 132,000.00 - 132,000.00
Dibulatkan 132,000.00 - 132,000.00

11 1 m1 PEKERJAAN LISPLANK KAYU 3/30 BORNEO SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Borneo 3/30 0.0099 m3 7,380,500.00 73,066.95 - 73,066.95
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 73,716.95 46,000.00 119,716.95
Dibulatkan 73,715.00 46,000.00 119,715.00
12 1 m1 PEKERJAAN LISPLANK KAYU 3/20 BORNEO SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Kls. II 3/20 0.0066 m3 7,380,500.00 48,711.30 - 48,711.30
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 49,361.30 46,000.00 95,361.30
Dibulatkan 49,360.00 46,000.00 95,360.00

13 1 m1 PEKERJAAN LISPLANK KAYU 3/20 KAYU LOKAL KLS. II SK.SNI T-2001 & PKKI NI-5
Bahan :
Papan Kayu Kls. II 3/20 0.0066 m3 3,684,900.00 24,320.34 - 24,320.34
Paku 3 - 7 cm 0.0500 m3 13,000.00 650.00 - 650.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 24,970.34 46,000.00 70,970.34
Dibulatkan 24,970.00 46,000.00 70,970.00

14 1 m1 PEKERJAAN LISPLANK GRC 1/20 SK.SNI T-2001 & PKKI NI-5


Bahan :
Lisplang GRC Tebal 1/20 x400 cm 1.0000 m1 57,500.00 57,500.00 - 57,500.00
Paku Skrup 6.0000 bh 300.00 1,800.00 - 1,800.00
Tenaga Kerja :
Pekerja 0.1100 Oh. 100,000.00 - 11,000.00 11,000.00
Tukang kayu 0.2200 Oh. 140,000.00 - 30,800.00 30,800.00
Kepala tukang kayu 0.0220 Oh. 150,000.00 - 3,300.00 3,300.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 59,300.00 46,000.00 105,300.00
Dibulatkan 59,300.00 46,000.00 105,300.00

15 1 m1 PEKERJAAN FLASHING SENG BJLS SK.SNI T-2001 & PKKI NI-5


Bahan :
Seng Plat BJLS 30 0.3500 m1 24,000.00 8,400.00 - 8,400.00
Paku 0.0150 m3 13,000.00 195.00 - 195.00
Tenaga Kerja :
Pekerja 0.0200 Oh 100,000.00 - 2,000.00 2,000.00
Tukang kayu 0.0400 Oh 140,000.00 - 5,600.00 5,600.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0050 Oh. 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 8,595.00 12,250.00 20,845.00
Dibulatkan 8,595.00 12,250.00 20,845.00

16 1 m1 PEKERJAAN TALANG MIRING (SENG BJLS 28) SK.SNI T-2001


Bahan :
Seng Plat BJLS 28 0.5000 Lbr 24,000.00 12,000.00 - 12,000.00
Papan Kayu 3/30 0.0190 m3 3,684,900.00 70,013.10 - 70,013.10
Paku 0.0150 m3 13,000.00 195.00 - 195.00
Meni besi / Flincoote 0.1500 Kg 41,600.00 6,240.00 - 6,240.00
Tenaga Kerja :
Pekerja 0.0400 Oh 100,000.00 - 4,000.00 4,000.00
Tukang kayu 0.4000 Oh 140,000.00 - 56,000.00 56,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0013 Oh. 180,000.00 - 225.00 225.00
Jumlah Harga Satuan 88,448.10 63,975.00 152,423.10
Dibulatkan 88,445.00 63,975.00 152,420.00

17 1 m1 PEKERJAAN TALANG DATAR (SENG BJLS 28) SK.SNI T-2001


Bahan :
Seng Plat BJLS 28 0.5000 Lbr 24,000.00 12,000.00 - 12,000.00
Papan Kayu 3/30 0.0096 m3 3,684,900.00 35,375.04 - 35,375.04
Paku 0.0150 m3 13,000.00 195.00 - 195.00
Meni besi / Flincoote 0.1500 Kg 41,600.00 6,240.00 - 6,240.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.4000 Oh 140,000.00 - 56,000.00 56,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0013 Oh. 180,000.00 - 225.00 225.00
Jumlah Harga Satuan 53,810.04 74,975.00 128,785.04
Dibulatkan 53,810.00 74,975.00 128,785.00

X. PENETAPAN INDEK HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 1 m2 PASANGAN GENTENG METAL ROOF t = 0,35 SK SNI T-11-1993-03
Bahan :
Genteng Metal t = 0,3 1.0000 lbr 76,000.00 76,000.00 - 76,000.00
Assesories 1.0000 ls 3,800.00 3,800.00 - 3,800.00
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 79,800.00 28,140.00 107,940.00
Dibulatkan 79,800.00 28,140.00 107,940.00

2 1 m1 PASANGAN NOK GENTENG METAL ROOF t = 0,35 SK SNI T-11-1993-03


Bahan :
Nok genteng Metal t = 0,3 1.0000 m1 36,000.00 36,000.00 - 36,000.00
Assesories 1.0000 ls 1,800.00 1,800.00 - 1,800.00
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 37,800.00 28,140.00 65,940.00
Dibulatkan 37,800.00 28,140.00 65,940.00

3 1 m2 PASANGAN GENTENG PALENTONG JATIWANGI (KECIL) SK SNI T-11-1993-03


Bahan :
Genteng Plentong Press Ex. Jatiwangi 25.0000 bh 2,300.00 57,500.00 - 57,500.00
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 57,500.00 28,140.00 85,640.00
Dibulatkan 57,500.00 28,140.00 85,640.00
4 1 m2 PASANGAN GENTENG MURANDO NATURAL SK SNI T-11-1993-03
Bahan :
Genteng Plentong Press Ex. Jatiwangi 18.0000 bh 3,400.00 61,200.00 - 61,200.00
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 61,200.00 28,140.00 89,340.00
Dibulatkan 61,200.00 28,140.00 89,340.00

5 1 m2 PASANGAN GENTENG MURANDO GLAZUUR SK SNI T-11-1993-03


Bahan :
Genteng Plentong Press Ex. Jatiwangi 18.0000 bh 5,500.00 99,000.00 - 99,000.00
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 99,000.00 28,140.00 127,140.00
Dibulatkan 99,000.00 28,140.00 127,140.00

6 1 m2 PASANGAN GENTENG LAMA SK SNI T-11-1993-03


Bahan :
Genteng Plentong Press Ex. Jatiwangi 25.0000 bh - - - -
Tenaga Kerja :
Pekerja 0.1500 Oh. 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.0750 Oh. 140,000.00 - 10,500.00 10,500.00
Kepala tukang kayu 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan - 28,140.00 28,140.00
Dibulatkan - 28,140.00 28,140.00

7 1 m2 PEK. PENGECATAN GENTENG SK.SNI T-2001


Bahan :
Cat Genteng 0.2200 kg 33,200.00 7,304.00 - 7,304.00
Kwass 3-4" 0.0500 bh 1,900.00 95.00 - 95.00
Tenaga Kerja :
Pekerja 0.0750 Oh. 100,000.00 - 7,500.00 7,500.00
Tukang cat 0.1500 Oh. 140,000.00 - 21,000.00 21,000.00
Kepala tukang cat 0.0080 Oh. 150,000.00 - 1,200.00 1,200.00
Mandor 0.0080 Oh. 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 7,399.00 31,140.00 38,539.00
Dibulatkan 7,395.00 31,140.00 38,535.00

8 1 m1 PASANGAN GENTENG BUBUNGAN JATIWANGI SK SNI T-11-1993-03


Bahan :
Genteng Bubung Ex. Jatiwangi 5.0000 bh 3,000.00 15,000.00 - 15,000.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Semen Portland ( PC TYPE I ) 8.0000 kg 1,544.00 12,352.00 - 12,352.00
Tenaga Kerja :
Pekerja 0.4000 Oh. 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh. 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh. 150,000.00 - 3,000.00 3,000.00
Mandor 0.0020 Oh. 180,000.00 - 360.00 360.00
Jumlah Harga Satuan 38,846.40 71,360.00 110,206.40
Dibulatkan 38,845.00 71,360.00 110,205.00
9 1 m1 PASANGAN GENTENG BUBUNGAN MURANDO NATURAL SK SNI T-11-1993-03
Bahan :
Genteng Bubung Ex. Jatiwangi 4.0000 bh 3,250.00 13,000.00 - 13,000.00
Pasir Pasang 0.0320 m3 359,200.00 11,494.40 - 11,494.40
Semen Portland ( PC TYPE I ) 8.0000 kg 2,260.00 18,080.00 - 18,080.00
Tenaga Kerja :
Pekerja 0.4000 Oh. 100,000.00 - 40,000.00 40,000.00
Tukang batu 0.2000 Oh. 140,000.00 - 28,000.00 28,000.00
Kepala tukang batu 0.0200 Oh. 150,000.00 - 3,000.00 3,000.00
Mandor 0.0020 Oh. 180,000.00 - 360.00 360.00
Jumlah Harga Satuan 42,574.40 71,360.00 113,934.40
Dibulatkan 42,570.00 71,360.00 113,930.00

XI. PENETAPAN INDEK HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 1 m2 PEKERJAAN RANGKA PLAFOND (GRID 60 x 60)cm KAYU BARU SK SNI T-11-1993-03
Bahan :
Kayu Klas II/II (Kaso 5/7 dan 5/10 Utk. 0.0120 m1 3,684,900.00 44,218.80 - 44,218.80
Paku 7 - 12 cm 0.1000 m3 25,000.00 2,500.00 - 2,500.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.2500 Oh 140,000.00 - 35,000.00 35,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 46,718.80 67,250.00 113,968.80
Dibulatkan 46,715.00 67,250.00 113,965.00

2 1 m2 PEKERJAAN RANGKA PLAFOND (GRID 100 x 100) KAYU ALBA SK SNI T-11-1993-03
Bahan :
Balok Kayu 5/10 dan 5/7 Kayu Alba 0.0120 m1 2,600,000.00 31,200.00 - 31,200.00
Paku 0.1000 m3 25,000.00 2,500.00 - 2,500.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.2500 Oh 140,000.00 - 35,000.00 35,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 33,700.00 67,250.00 100,950.00
Dibulatkan 33,700.00 67,250.00 100,950.00

3 1 m2 PEKERJAAN RANGKA PLAFOND (TANPA PENUTUP) KAYU LAMA SK SNI T-11-1993-03


Bahan :
Balok Kayu 5/10 dan 5/7 0.0000 m1 3,684,900.00 - -
Paku 0.1000 m3 25,000.00 2,500.00 - 2,500.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang kayu 0.2500 Oh 140,000.00 - 35,000.00 35,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0750 Oh 180,000.00 - 13,500.00 13,500.00
Jumlah Harga Satuan 2,500.00 67,250.00 69,750.00
Dibulatkan 2,500.00 67,250.00 69,750.00

4 1 m2 PASANG RANGKA PLAFOND (60 X 60) cm BESI HOLLO SK SNI T-11-1993-03


Bahan :
Besi Hollo 4 x 4 1.2000 m1 8,525.00 10,230.00 - 10,230.00
Besi Hollo 2 x 4 2.4000 m1 5,950.00 14,280.00 - 14,280.00
Gantungan Besi dia 6 0.2750 kg 12,500.00 3,437.50 - 3,437.50
Assesories dan Alat Bantu 1.0000 ls 1,000.00 1,000.00 - 1,000.00
Tenaga Kerja :
Pekerja 0.1500 Oh 100,000.00 - 15,000.00 15,000.00
Tukang Kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala Tukang Kayu 0.0500 Oh 150,000.00 - 7,500.00 7,500.00
Mandor 0.0080 Oh 180,000.00 - 1,440.00 1,440.00
Jumlah Harga Satuan 18,717.50 93,940.00 112,657.50
Dibulatkan 18,715.00 93,940.00 112,655.00

5 1 m2 PENUTUP RANGKA PLAFOND TRIPLEK 4 MM, Uk. 120x240 cm SK SNI T-11-1993-03


Bahan :
Triplek 4 mm Ukuran 120 x 240 cm 0.3750 lbr 66,358.00 24,884.25 - 24,884.25
Paku triplek 0.0300 kg 28,000.00 840.00 - 840.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 25,724.25 19,520.00 45,244.25
Dibulatkan 25,720.00 19,520.00 45,240.00

6 1 m2 PENUTUP RANGKA PLAFOND (HARDPLEK 1X1 TEBAL 5 MM) SK SNI T-11-1993-03


Bahan :
Hardplek 1 x 1 m 1.1000 lbr 15,000.00 16,500.00 - 16,500.00
Paku triplek 0.0250 kg 28,000.00 700.00 - 700.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 17,200.00 19,520.00 36,720.00
Dibulatkan 17,200.00 19,520.00 36,720.00

7 1 m2 PENUTUP RANGKA PLAFOND (GRC BOARD EX. JAYA BOARD 120 x 240 TEBAL 4 MM) SK SNI T-11-1993-03
Bahan :
GRC 120x240 0.3640 lbr 45,000.00 16,380.00 - 16,380.00
Paku Skrup/GRC 0.1100 kg 13,000.00 1,430.00 - 1,430.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 17,810.00 19,520.00 37,330.00
Dibulatkan 17,810.00 19,520.00 37,330.00

8 1 m2 MEMASANG LANGIT-LANGIT GYPSUMBOARD 9 mm SK SNI T-11-1993-03


Bahan :
Pelat Gypsum Board 0.3470 Lbr 107,600.00 37,337.20 - 37,337.20
Plaster Board 1.0000 Ls 3,000.00 3,000.00 - 3,000.00
Paku Skrup 12.0000 bh 500.00 6,000.00 - 6,000.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang kayu 0.0700 Oh 140,000.00 - 9,800.00 9,800.00
Kepala tukang kayu 0.0070 Oh 150,000.00 - 1,050.00 1,050.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 46,337.20 14,120.00 60,457.20
Dibulatkan 46,335.00 14,120.00 60,455.00
9 1 m1 PAKERJAAN LIST PROFIL U/ PLAFOND Uk. 3/3 SK SNI T-11-1993-03
Bahan :
List Profil Kayu 1.1000 m1 9,600.00 10,560.00 - 10,560.00
Paku 3 s.d 5 0.0100 kg 13,000.00 130.00 - 130.00
Tenaga Kerja :
Pekerja 0.0250 Oh 100,000.00 - 2,500.00 2,500.00
Tukang kayu 0.0500 Oh 140,000.00 - 7,000.00 7,000.00
Kepala tukang kayu 0.0050 Oh 150,000.00 - 750.00 750.00
Mandor 0.0030 Oh 180,000.00 - 540.00 540.00
Jumlah Harga Satuan 10,690.00 10,790.00 21,480.00
Dibulatkan 10,690.00 10,790.00 21,480.00

XII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN KUSEN dan JENDELA


1 1 m3 PAKERJAAN KUSEN PINTU / JENDELA BAHAN JATI LOKAL SK.SNI T-2002
Bahan :
Balok Kayu Jati Ukuran 6/15 cm 1.2000 M3 12,822,000.00 15,386,400.00 - 15,386,400.00
Paku 7 s/d 12 cm 2.5000 kg 25,000.00 62,500.00 - 62,500.00
Lem Kayu 1.0000 kg 40,000.00 40,000.00 - 40,000.00
Tenaga Kerja :
Pekerja 6.0000 Oh 100,000.00 - 600,000.00 600,000.00
Tukang kayu 18.0000 Oh 140,000.00 - 2,520,000.00 2,520,000.00
Kepala tukang kayu 2.0000 Oh 150,000.00 - 300,000.00 300,000.00
Mandor 0.3000 Oh 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 15,488,900.00 3,474,000.00 18,962,900.00
Dibulatkan 15,488,900.00 3,474,000.00 18,962,900.00

2 1 m3 PAKERJAAN KUSEN PINTU / JENDELA BAHAN KAMPER BANJAR SK.SNI T-2002


Bahan :
Balok Kayu Kamper Banjar Ukuran 6/15 1.2000 M3 3,750,000.00 4,500,000.00 - 4,500,000.00
Paku 7 s/d 12 cm 2.5000 kg 25,000.00 62,500.00 - 62,500.00
Lem Kayu 1.0000 kg 40,000.00 40,000.00 - 40,000.00
Tenaga Kerja :
Pekerja 6.0000 Oh 100,000.00 - 600,000.00 600,000.00
Tukang kayu 18.0000 Oh 140,000.00 - 2,520,000.00 2,520,000.00
Kepala tukang kayu 2.0000 Oh 150,000.00 - 300,000.00 300,000.00
Mandor 0.3000 Oh 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 4,602,500.00 3,474,000.00 8,076,500.00
Dibulatkan 4,602,500.00 3,474,000.00 8,076,500.00

3 1 m3 PAKERJAAN KUSEN PINTU / JENDELA BAHAN KAYU LOKAL KLS.II SK.SNI T-2002
Bahan :
Balok Kayu Lokal Kls. II Uk. 6/15 cm at 1.2000 M3 3,684,900.00 4,421,880.00 - 4,421,880.00
Paku 7 s/d 12 cm 2.5000 kg 25,000.00 62,500.00 - 62,500.00
Lem Kayu 1.0000 kg 40,000.00 40,000.00 - 40,000.00
Tenaga Kerja :
Pekerja 6.0000 Oh 100,000.00 - 600,000.00 600,000.00
Tukang kayu 18.0000 Oh 140,000.00 - 2,520,000.00 2,520,000.00
Kepala tukang kayu 2.0000 Oh 150,000.00 - 300,000.00 300,000.00
Mandor 0.3000 Oh 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 4,524,380.00 3,474,000.00 7,998,380.00
Dibulatkan 4,524,380.00 3,474,000.00 7,998,380.00

4 1 m1 PAKERJAAN KUSEN ALUMUNIUM UK. 4" NATURAL SEK. ALEXINDO SK.SNI T-2002
Bahan :
Profil allumunium 1.1000 m1 13,000.00 14,300.00 - 14,300.00
Skrup fixer 2.0000 Bh 300.00 600.00 - 600.00
Sealant 0.0600 Tube 22,000.00 1,320.00 - 1,320.00
Tenaga Kerja :
Pekerja 0.0430 Oh 100,000.00 - 4,300.00 4,300.00
Tukang khusus allumunium 0.0430 Oh 140,000.00 - 6,020.00 6,020.00
Kepala Tukang 0.0043 Oh 150,000.00 - 645.00 645.00
Mandor 0.0021 Oh 180,000.00 - 378.00 378.00
Jumlah Harga Satuan 16,220.00 11,343.00 27,563.00
Dibulatkan 16,220.00 11,340.00 27,560.00

5 1 m1 PAKERJAAN KUSEN ALUMUNIUM UK. 4" WARNA SEK. ALEXINDO SK.SNI T-2002
Bahan :
Profil allumunium 1.1000 m1 125,000.00 137,500.00 - 137,500.00
Skrup fixer 2.0000 Bh 300.00 600.00 - 600.00
Sealant 0.0600 Tube 22,000.00 1,320.00 - 1,320.00
Tenaga Kerja :
Pekerja 0.0430 Oh 100,000.00 - 4,300.00 4,300.00
Tukang khusus allumunium 0.0430 Oh 140,000.00 - 6,020.00 6,020.00
Kepala Tukang 0.0043 Oh 150,000.00 - 645.00 645.00
Mandor 0.0021 Oh 180,000.00 - 378.00 378.00
Jumlah Harga Satuan 139,420.00 11,343.00 150,763.00
Dibulatkan 139,420.00 11,340.00 150,760.00

6 1 m2 PAKERJAAN DAUN PINTU PANEL KAYU KAMPER BANJAR SK.SNI T-2002


Bahan :
Papan kayu kamper 0.0400 M3 7,603,400.00 304,136.00 - 304,136.00
Lem Kayu 1.0000 kg 40,000.00 40,000.00 - 40,000.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang kayu 2.5000 Oh 140,000.00 - 350,000.00 350,000.00
Kepala tukang kayu 0.2500 Oh 150,000.00 - 37,500.00 37,500.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 344,136.00 496,500.00 840,636.00
Dibulatkan 344,135.00 496,500.00 840,635.00

7 1 m2 PAKERJAAN DAUN PINTU PANEL KAYU LOKAL KLS. II SK.SNI T-2002


Bahan :
Papan kayu Lokal Kls.II 0.0400 M3 3,684,900.00 147,396.00 - 147,396.00
Lem Kayu 0.3500 kg 40,000.00 14,000.00 - 14,000.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang kayu 2.5000 Oh 140,000.00 - 350,000.00 350,000.00
Kepala tukang kayu 0.2500 Oh 150,000.00 - 37,500.00 37,500.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 161,396.00 496,500.00 657,896.00
Dibulatkan 161,395.00 496,500.00 657,895.00

8 1 m2 PAKERJAAN DAUN PINTU DOUBLE TRIPLEK 4 MM RANGKA KAYU SK.SNI T-2002


Bahan :
Papan kayu Lokal Kls.II 0.0196 M3 3,684,900.00 72,224.04 - 72,224.04
Paku 1 s/d 3 cm 0.0300 kg 13,000.00 390.00 - 390.00
Lem Kayu 0.1500 kg 40,000.00 6,000.00 - 6,000.00
Triplek T. 4 mm 0.4000 lbr 66,358.00 26,543.20 - 26,543.20
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 105,157.24 375,400.00 480,557.24
Dibulatkan 105,155.00 375,400.00 480,555.00

9 1 m2 PAKERJAAN DAUN PINTU DOUBLE TEAKWOOD 4 MM RANGKA KAYU SK.SNI T-2002


Bahan :
Papan kayu Lokal Kls.II 0.0196 M3 3,684,900.00 72,224.04 - 72,224.04
Paku 1 s/d 3 cm 0.0300 kg 13,000.00 390.00 - 390.00
Lem Kayu 0.1500 kg 40,000.00 6,000.00 - 6,000.00
Teakwood T. 4 mm 0.4000 lbr 93,000.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 115,814.04 375,400.00 491,214.04
Dibulatkan 115,810.00 375,400.00 491,210.00

10 1 m2 PAKERJAAN DAUN PINTU DOUBLE FORMIKA dan TEAKWOOD 4 MM RANGKA KAYU SK.SNI T-2002
Bahan :
Papan kayu Lokal Kls.II 0.0196 M3 3,684,900.00 72,224.04 - 72,224.04
Paku 1 s/d 3 cm 0.0300 kg 13,000.00 390.00 - 390.00
Lem Kayu 0.1500 kg 40,000.00 6,000.00 - 6,000.00
Formika T. 4 mm 0.4000 lbr 275,000.00 110,000.00 - 110,000.00
Teakwood T. 4 mm 0.4000 lbr 93,000.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.6000 Oh 100,000.00 - 60,000.00 60,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0300 Oh 180,000.00 - 5,400.00 5,400.00
Jumlah Harga Satuan 225,814.04 375,400.00 601,214.04
Dibulatkan 225,810.00 375,400.00 601,210.00

11 1 m2 PEKERJAAN RANGKA JENDELA KAYU Kls. I SK.SNI T-2002


Bahan :
Kayu Papan Kls. II 0.0350 m3 3,684,900.00 128,971.50 - 128,971.50
Paku 1 - 3 cm 0.0075 kg 25,000.00 187.50 - 187.50
Tenaga Kerja :
Pekerja 0.8000 Oh 100,000.00 - 80,000.00 80,000.00
Tukang kayu 2.0000 Oh 140,000.00 - 280,000.00 280,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0400 Oh 180,000.00 - 7,200.00 7,200.00
Jumlah Harga Satuan 129,159.00 397,200.00 526,359.00
Dibulatkan 129,155.00 397,200.00 526,355.00

12 1 m2 Pek. JALUSI KAYU Uk. 2/15 (KAYU LOKAL KLS. II) SK.SNI T-2002
Bahan :
Kayu Lokal Setara Kls. II, Papan 0.0300 m3 3,684,900.00 110,547.00 - 110,547.00
Paku 1- 3 cm 0.0075 kg 13,000.00 97.50 - 97.50
Tenaga Kerja :
Pekerja 0.5000 Oh 100,000.00 - 50,000.00 50,000.00
Tukang kayu 1.0000 Oh 140,000.00 - 140,000.00 140,000.00
Kepala tukang kayu 0.2000 Oh 150,000.00 - 30,000.00 30,000.00
Mandor 0.0500 Oh 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 110,644.50 229,000.00 339,644.50
Dibulatkan 110,640.00 229,000.00 339,640.00

13 1 m2 PARTISI DOUBLE TRIPLEK 4 MM


Bahan :
Kayu untuk Rangka Kls II 0.0175 m3 3,684,900.00 64,485.75 - 64,485.75
Triplek 4 mm Ukuran 120 x 240 cm 1.0000 lbr 66,358.00 66,358.00 - 66,358.00
Paku 0.0300 kg 25,000.00 750.00 - 750.00
Tenaga Kerja :
Pekerja 0.0800 Oh 100,000.00 - 8,000.00 8,000.00
Tukang kayu 1.5000 Oh 140,000.00 - 210,000.00 210,000.00
Kepala tukang kayu 0.0250 Oh 150,000.00 - 3,750.00 3,750.00
Mandor 0.0400 Oh 180,000.00 - 7,200.00 7,200.00
Jumlah Harga Satuan 131,593.75 228,950.00 360,543.75
Dibulatkan 131,590.00 228,950.00 360,540.00

14 1 m2 PASANG KACA POLOS T. 5 MM + LIST KACA SK.SNI T-2002


Bahan :
Kaca Polos 5 mm (ASAHI) 1.0000 m2 164,700.00 164,700.00 - 164,700.00
Paku 1 - 3 cm 0.0100 kg 28,000.00 280.00 - 280.00
List Kaca 1x2 / 1x3 4.0000 m1 9,300.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 135.00 135.00
Jumlah Harga Satuan 202,180.00 24,885.00 227,065.00
Dibulatkan 202,180.00 24,885.00 227,065.00

15 1 m2 PASANG KACA POLOS T. 3 MM + LIST KACA SK.SNI T-2002


Bahan :
Kaca Polos 3 mm (ASAHI) 1.0000 m2 109,800.00 109,800.00 - 109,800.00
Paku 1 - 3 cm 0.0100 kg 28,000.00 280.00 - 280.00
List Kaca 1x2 / 1x3 4.0000 m1 9,300.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 135.00 135.00
Jumlah Harga Satuan 147,280.00 24,885.00 172,165.00
Dibulatkan 147,280.00 24,885.00 172,165.00

16 1 m2 PASANG KACA POLOS T. 5 atau 3 mm (LAMA) SK.SNI T-2002


Bahan :
Kaca Polos 3 mm (ASAHI) 1.0000 m2 - - - -
Paku 1 - 3 cm 0.0100 kg 28,000.00 280.00 - 280.00
List Kaca 1x2 / 1x3 4.0000 m1 9,300.00 37,200.00 - 37,200.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 135.00 135.00
Jumlah Harga Satuan 37,480.00 24,885.00 62,365.00
Dibulatkan 37,480.00 24,885.00 62,365.00

17 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara SEIS STANDARD UK. BESAR SK.SNI T-2002
Bahan :
Kunci 2 Slaag Silinder SEIS STANDARD 1.0000 bh 217,560.00 217,560.00 - 217,560.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 217,560.00 73,400.00 290,960.00
Dibulatkan 217,560.00 73,400.00 290,960.00

18 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara SEIS STANDARD UK. KECIL SK.SNI T-2002
Bahan :
Kunci 2 Slaag Silinder SEIS STANDARD 1.0000 bh 206,460.00 206,460.00 - 206,460.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 206,460.00 73,400.00 279,860.00
Dibulatkan 206,460.00 73,400.00 279,860.00

19 1 Bh PASANG KUNCI PINTU TANAM DOUBLE SLAAG Setara UNION TERBANG UK. KECIL SK.SNI T-2002
Bahan :
Kunci Bulat 2slaag UNION 1.0000 bh 65,000.00 65,000.00 - 65,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.5000 Oh 140,000.00 - 70,000.00 70,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0050 Oh 180,000.00 - 900.00 900.00
Jumlah Harga Satuan 65,000.00 73,400.00 138,400.00
Dibulatkan 65,000.00 73,400.00 138,400.00

20 1 Bh PASANG KUNCI BULAT 2 SLAAG (KM/WC) ALFA STANDARD SK.SNI T-2002


Bahan :
Kunci Bulat 2slaag SEIS Standard 1.0000 bh 9,900.00 9,900.00 - 9,900.00
Tenaga Kerja :
Pekerja 0.0600 Oh 100,000.00 - 6,000.00 6,000.00
Tukang kayu 0.6000 Oh 140,000.00 - 84,000.00 84,000.00
Kepala tukang kayu 0.0600 Oh 150,000.00 - 9,000.00 9,000.00
Mandor 0.0025 Oh 180,000.00 - 450.00 450.00
Jumlah Harga Satuan 9,900.00 99,450.00 109,350.00
Dibulatkan 9,900.00 99,450.00 109,350.00

21 1 Pcs PASANG ENGSEL PINTU UNION BESAR SK.SNI T-2002


Bahan :
Engsel Pintu Unilon 1.0000 Pcs 20,900.00 20,900.00 - 20,900.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 135.00 135.00
Jumlah Harga Satuan 20,900.00 24,885.00 45,785.00
Dibulatkan 20,900.00 24,885.00 45,785.00

22 1 Pcs PASANG ENGSEL JENDELA KUPU-KUPU SK.SNI T-2002


Bahan :
Engsel Jendela 1.0000 Pcs 23,000.00 23,000.00 - 23,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 23,000.00 16,590.00 39,590.00
Dibulatkan 23,000.00 16,590.00 39,590.00
23 1 Pcs SLOT PINTU TANAM ATAS BAWAH (ESPAGNOLET) SK.SNI T-2002
Bahan :
Slot Pintu Tanam (Espagnolet) 1.0000 Pcs 300,000.00 300,000.00 - 300,000.00
Tenaga Kerja :
Pekerja 0.0200 Oh 100,000.00 - 2,000.00 2,000.00
Tukang kayu 0.2000 Oh 140,000.00 - 28,000.00 28,000.00
Kepala tukang kayu 0.0200 Oh 150,000.00 - 3,000.00 3,000.00
Mandor 0.0010 Oh 180,000.00 - 180.00 180.00
Jumlah Harga Satuan 300,000.00 33,180.00 333,180.00
Dibulatkan 300,000.00 33,180.00 333,180.00

24 1 Bh SLOT PINTU BIASA SK.SNI T-2002


Bahan :
Grendel Pintu 1.0000 bh 15,000.00 15,000.00 - 15,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 15,000.00 16,590.00 31,590.00
Dibulatkan 15,000.00 16,590.00 31,590.00

25 1 Bh SLOT JENDELA BIASA SK.SNI T-2002


Bahan :
Grendel Jendela 1.0000 bh 3,000.00 3,000.00 - 3,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 3,000.00 16,590.00 19,590.00
Dibulatkan 3,000.00 16,590.00 19,590.00

26 1 Bh SPRING KNIP SK.SNI T-2002


Bahan :
Spring Knip 1.0000 bh 11,000.00 11,000.00 - 11,000.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 135.00 135.00
Jumlah Harga Satuan 11,000.00 24,885.00 35,885.00
Dibulatkan 11,000.00 24,885.00 35,885.00

27 1 Pcs PASANG KAIT ANGIN JENDELA BIASA SK.SNI T-2002


Bahan :
Hak Angin Kait Biasa 1.0000 bh 10,000.00 10,000.00 - 10,000.00
Tenaga Kerja :
Pekerja 0.0150 Oh 100,000.00 - 1,500.00 1,500.00
Tukang kayu 0.1500 Oh 140,000.00 - 21,000.00 21,000.00
Kepala tukang kayu 0.0150 Oh 150,000.00 - 2,250.00 2,250.00
Mandor 0.0008 Oh 180,000.00 - 144.00 144.00
Jumlah Harga Satuan 10,000.00 24,894.00 34,894.00
Dibulatkan 10,000.00 24,890.00 34,890.00

28 1 Bh PASANG TARIKAN JENDELA SK.SNI T-2002


Bahan :
Tarikan Jendela Biasa 1.0000 bh 5,000.00 5,000.00 - 5,000.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang kayu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang kayu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 5,000.00 16,590.00 21,590.00
Dibulatkan 5,000.00 16,590.00 21,590.00

XIII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN SANITARY


1 MEMASANG 1 Bh KLOSET DUDUK/MONOBLOK SEKUALITAS "INA" STANDARD SK.SNI T-2001
Bahan :
Kloset duduk monoblok 1.0000 bh 1,361,200.00 1,361,200.00 - 1,361,200.00
Perlengkapan 35% dari harga bahan 1.0000 ls 476,420.00 476,420.00 - 476,420.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang batu 1.5000 Oh 140,000.00 - 210,000.00 210,000.00
Kepala tukang batu 1.5000 Oh 150,000.00 - 225,000.00 225,000.00
Mandor 0.1600 Oh 180,000.00 - 28,800.00 28,800.00
Jumlah Harga Satuan 1,837,620.00 563,800.00 2,401,420.00
Dibulatkan 1,837,620.00 563,800.00 2,401,420.00

2 MEMASANG 1 BUAH CLOSET JONGKOK SK.SNI T-2001


Bahan :
Kloset Jongkok Keramik Standar Putih 1.0000 bh 137,500.00 137,500.00 - 137,500.00
Semen Portland ( PC TYPE I ) 6.0000 kg 1,544.00 9,264.00 - 9,264.00
Pasir Pasang 0.0500 m2 359,200.00 17,960.00 - 17,960.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang batu 1.5000 Oh 140,000.00 - 210,000.00 210,000.00
Kepala tukang batu 1.5000 Oh 150,000.00 - 225,000.00 225,000.00
Mandor 0.1600 Oh 180,000.00 - 28,800.00 28,800.00
Jumlah Harga Satuan 164,724.00 563,800.00 728,524.00
Dibulatkan 164,720.00 563,800.00 728,520.00

3 MEMASANG 1 BUAH BAK MANDI FIBER Uk. Sedang SK.SNI T-2001


Bahan :
Bak Mandi Fiber 1.0000 bh 162,500.00 162,500.00 - 162,500.00
Semen Portland ( PC TYPE I ) 60.0000 kg 1,544.00 92,640.00 - 92,640.00
Pasir Pasang 0.2500 m2 359,200.00 89,800.00 - 89,800.00
Semen Warna Setara Mitsubishi 1.0000 kg 13,000.00 13,000.00 - 13,000.00
Bata Merah Bakar (Kw. 1) 70.0000 bh 860.00 60,200.00 - 60,200.00
Perlengkapan 0.1800 % 162,500.00 29,250.00 - 29,250.00
Tenaga Kerja :
Pekerja 0.5600 Oh 100,000.00 - 56,000.00 56,000.00
Tukang batu 1.2000 Oh 140,000.00 - 168,000.00 168,000.00
Kepala tukang batu 0.2100 Oh 150,000.00 - 31,500.00 31,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 447,390.00 255,590.00 702,980.00
Dibulatkan 447,390.00 255,590.00 702,980.00

4 MEMASANG 1 BUAH WASHTAFEL MEJA/GANTUNG Sek. INA SK.SNI T-2001


Bahan :
Washtafel Lengkap Ex. INA 1.0000 bh 577,000.00 577,000.00 - 577,000.00
Perlengkapan 35% dari harga bahan 1.0000 ls 201,950.00 201,950.00 - 201,950.00
Tenaga Kerja :
Pekerja 1.2000 Oh 100,000.00 - 120,000.00 120,000.00
Tukang batu 1.4500 Oh 140,000.00 - 203,000.00 203,000.00
Kepala tukang batu 0.1500 Oh 150,000.00 - 22,500.00 22,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 778,950.00 345,590.00 1,124,540.00
Dibulatkan 778,950.00 345,590.00 1,124,540.00

5 MEMASANG 1 BUAH PASANG URINOIR SK.SNI T-2001


Bahan :
Urinoir lengkap Ex. TOTO 1.0000 bh 606,200.00 606,200.00 - 606,200.00
Perlengkapan 35% dari harga bahan 1.0000 ls 212,170.00 212,170.00 - 212,170.00
Tenaga Kerja :
Pekerja 1.0000 Oh 100,000.00 - 100,000.00 100,000.00
Tukang batu 1.0000 Oh 140,000.00 - 140,000.00 140,000.00
Kepala tukang batu 0.1000 Oh 150,000.00 - 15,000.00 15,000.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 818,370.00 255,090.00 1,073,460.00
Dibulatkan 818,370.00 255,090.00 1,073,460.00

6 MEMASANG 1 BUAH FLOOR DRAIN SK.SNI T-2001


Bahan :
Floor Drain SUN-EI 1.0000 bh 27,500.00 27,500.00 - 27,500.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 27,500.00 16,590.00 44,090.00
Dibulatkan 27,500.00 16,590.00 44,090.00

7 MEMASANG 1 BUAH KRAN DINDING SK.SNI T-2001


Bahan :
Kran Tembok/Dinding Biasa 1.0000 bh 14,300.00 14,300.00 - 14,300.00
Seal tape 1.0000 bh 4,500.00 4,500.00 - 4,500.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 18,800.00 16,590.00 35,390.00
Dibulatkan 18,800.00 16,590.00 35,390.00

8 MEMASANG 1 BUAH KRAN DINDING LEHER ANGSA (STAINLESS) dia-1/2" SK.SNI T-2001
Bahan :
Kran Dinding Leher Angsa stainless 1.0000 bh 47,500.00 47,500.00 - 47,500.00
Seal tape 1.0000 bh 4,500.00 4,500.00 - 4,500.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 52,000.00 16,590.00 68,590.00
Dibulatkan 52,000.00 16,590.00 68,590.00

9 MEMASANG 1 BUAH FIXED JET WASHER Sek. TOTO SK.SNI T-2001


Bahan :
Kran air 1.0000 bh 11,550.00 11,550.00 - 11,550.00
Seal tape 1.0000 bh 4,500.00 4,500.00 - 4,500.00
Tenaga Kerja :
Pekerja 0.0100 Oh 100,000.00 - 1,000.00 1,000.00
Tukang batu 0.1000 Oh 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0100 Oh 150,000.00 - 1,500.00 1,500.00
Mandor 0.0005 Oh 180,000.00 - 90.00 90.00
Jumlah Harga Satuan 16,050.00 16,590.00 32,640.00
Dibulatkan 16,050.00 16,590.00 32,640.00

10 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS STEEL LOKAL 1 LUBANG SK.SNI T-2001
Bahan :
Bak cuci stainless steel 1.0000 bh 216,200.00 216,200.00 - 216,200.00
Water drain+ asesories 1.0000 bh 27,500.00 27,500.00 - 27,500.00
Tenaga Kerja :
Pekerja 0.0300 Oh 100,000.00 - 3,000.00 3,000.00
Tukang batu 0.3000 Oh 140,000.00 - 42,000.00 42,000.00
Kepala tukang batu 0.0300 Oh 150,000.00 - 4,500.00 4,500.00
Mandor 0.0015 Oh 180,000.00 - 270.00 270.00
Jumlah Harga Satuan 243,700.00 49,770.00 293,470.00
Dibulatkan 243,700.00 49,770.00 293,470.00

XIV. PENETAPAN INDEK HARGA SATUAN PEKERJAAN INSTALASI PIPA


1 MEMASANG 1 m1 PIPA PVC Ø 1/2" Tipe AW SK.SNI T-2001
Bahan :
Pipa PVC 1.2000 m1 7,725.00 9,270.00 - 9,270.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 7,725.00 2,703.75 - 2,703.75
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang plumbing 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 11,973.75 12,900.00 24,873.75
Dibulatkan 11,970.00 12,900.00 24,870.00

2 MEMASANG 1 m1 PIPA PVC Ø 3/4" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 10,575.00 12,690.00 - 12,690.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 10,575.00 3,701.25 - 3,701.25
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 16,391.25 13,224.00 29,615.25
Dibulatkan 16,390.00 13,220.00 29,610.00

3 MEMASANG 1 m1 PIPA PVC Ø 1" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 13,725.00 16,470.00 - 16,470.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 13,725.00 4,803.75 - 4,803.75
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 21,273.75 13,224.00 34,497.75
Dibulatkan 21,270.00 13,220.00 34,490.00

4 MEMASANG 1 m1 PIPA PVC Ø 1 1/2" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 24,025.00 28,830.00 - 28,830.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 24,025.00 8,408.75 - 8,408.75
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 37,238.75 13,224.00 50,462.75
Dibulatkan 37,235.00 13,220.00 50,455.00

5 MEMASANG 1 m1 PIPA PVC Ø 2" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 41,475.00 49,770.00 - 49,770.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 41,475.00 14,516.25 - 14,516.25
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 64,286.25 13,224.00 77,510.25
Dibulatkan 64,285.00 13,220.00 77,505.00

6 MEMASANG 1 m1 PIPA PVC Ø 2 1/2" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 47,200.00 56,640.00 - 56,640.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 47,200.00 16,520.00 - 16,520.00
Tenaga Kerja :
Pekerja 0.0360 Oh 100,000.00 - 3,600.00 3,600.00
Tukang Pipa 0.0600 Oh 140,000.00 - 8,400.00 8,400.00
Kepala tukang 0.0060 Oh 150,000.00 - 900.00 900.00
Mandor 0.0018 Oh 180,000.00 - 324.00 324.00
Jumlah Harga Satuan 73,160.00 13,224.00 86,384.00
Dibulatkan 73,160.00 13,220.00 86,380.00

7 MEMASANG 1 m1 PIPA PVC Ø 3" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 33,933.33 40,720.00 - 40,720.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 33,933.33 11,876.67 - 11,876.67
Tenaga Kerja :
Pekerja 0.0810 Oh 100,000.00 - 8,100.00 8,100.00
Tukang Pipa 0.1350 Oh 140,000.00 - 18,900.00 18,900.00
Kepala tukang plumbing 0.0135 Oh 150,000.00 - 2,025.00 2,025.00
Mandor 0.0041 Oh 180,000.00 - 738.00 738.00
Jumlah Harga Satuan 52,596.67 29,763.00 82,359.67
Dibulatkan 52,595.00 29,760.00 82,355.00

8 MEMASANG 1 m1 PIPA PVC Ø 4" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 41,950.00 50,340.00 - 50,340.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 41,950.00 14,682.50 - 14,682.50
Tenaga Kerja :
Pekerja 0.0810 Oh 100,000.00 - 8,100.00 8,100.00
Tukang Pipa 0.1350 Oh 140,000.00 - 18,900.00 18,900.00
Kepala tukang plumbing 0.0135 Oh 150,000.00 - 2,025.00 2,025.00
Mandor 0.0041 Oh 180,000.00 - 738.00 738.00
Jumlah Harga Satuan 65,022.50 29,763.00 94,785.50
Dibulatkan 65,020.00 29,760.00 94,780.00

9 MEMASANG 1 m1 PIPA PVC Ø 5" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 150,425.00 180,510.00 - 180,510.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 150,425.00 52,648.75 - 52,648.75
Tenaga Kerja :
Pekerja 0.0810 Oh 100,000.00 - 8,100.00 8,100.00
Tukang Pipa 0.1350 Oh 140,000.00 - 18,900.00 18,900.00
Kepala tukang plumbing 0.0135 Oh 150,000.00 - 2,025.00 2,025.00
Mandor 0.0041 Oh 180,000.00 - 738.00 738.00
Jumlah Harga Satuan 233,158.75 29,763.00 262,921.75
Dibulatkan 233,155.00 29,760.00 262,915.00

10 MEMASANG 1 m1 PIPA PVC Ø 6" Tipe AW SK.SNI T-2001


Bahan :
Pipa PVC 1.2000 m1 207,625.00 249,150.00 - 249,150.00
Perlengkapan (35% x Harga Pipa) 35.0000 % 207,625.00 72,668.75 - 72,668.75
Tenaga Kerja :
Pekerja 0.0810 Oh 100,000.00 - 8,100.00 8,100.00
Tukang Pipa 0.1350 Oh 140,000.00 - 18,900.00 18,900.00
Kepala tukang plumbing 0.0135 Oh 150,000.00 - 2,025.00 2,025.00
Mandor 0.0041 Oh 180,000.00 - 738.00 738.00
Jumlah Harga Satuan 321,818.75 29,763.00 351,581.75
Dibulatkan 321,815.00 29,760.00 351,575.00

XV. PENETAPAN INDEK HARGA SATUAN PEKERJAAN SEPTICTANK dan REMBESAN


1 PEMBUATAN 1 Unit SEPTICTANK DAN REMBESAN UKURAN BESAR (1,5x2,5 Tinggi 1,75m) SK.SNI T-2001 & SNI 03-29/398-1991
Bahan / Upah :
a. Galian tanah septictank 12.0000 m3 79,195.00 950,340.00 - 950,340.00
b. Galian tanah rembesan 5.6500 m3 66,825.00 377,561.25 - 377,561.25
c. Pasangan bata (1PC ; 4 Psr) 25.0000 m2 104,365.00 2,609,125.00 - 2,609,125.00
d. Plesteran Kedap Air 1 Pc ; 3 Psr 25.0000 m2 57,305.00 1,432,625.00 - 1,432,625.00
e. Beton Praktis K-175 0.5000 m3 3,565,955.00 1,782,977.50 - 1,782,977.50
f. Pasir Urug 0.3570 m3 282,600.00 100,888.20 - 100,888.20
g. Lapisan Injuk Untuk Rembesan 9.0000 m2 11,000.00 99,000.00 - 99,000.00
h. Batu Pecah / Split Ukuran 0,5 - 2 cm 1.7500 m3 408,400.00 714,700.00 - 714,700.00
i. Urugan tanah Kembali dipadatkan 3.5000 m3 15,055.00 52,692.50 - 52,692.50
j. Pasang Pipa Galvanis Ø 3/4" 1.0000 Btg 175,000.00 175,000.00 - 175,000.00
Jumlah Harga Satuan 8,294,909.45 - 8,294,909.45
Dibulatkan 8,294,905.00 - 8,294,905.00

2 PEMBUATAN 1 Unit SEPTICTANK DAN REMBESAN UKURAN SEDANG (1,25x1,75 Tinggi 1,75m)SK.SNI T-2001 & SNI 03-29/398-1991
Bahan / Upah :
a. Galian tanah septictank 9.0000 m3 79,195.00 712,755.00 - 712,755.00
b. Galian tanah rembesan 4.2375 m3 66,825.00 283,170.94 - 283,170.94
c. Pasangan bata (1PC ; 4 Psr) 18.7500 m2 104,365.00 1,956,843.75 - 1,956,843.75
d. Plesteran Kedap Air 1 Pc ; 3 Psr 18.7500 m2 57,305.00 1,074,468.75 - 1,074,468.75
e. Beton Praktis K-175 0.3750 m3 3,565,955.00 1,337,233.13 - 1,337,233.13
f. Pasir Urug 0.2678 m3 282,600.00 75,666.15 - 75,666.15
g. Lapisan Injuk Untuk Rembesan 6.7500 kg 11,000.00 74,250.00 - 74,250.00
h. Batu Pecah / Split Ukuran 0,5 - 2 cm 1.3125 m3 408,400.00 536,025.00 - 536,025.00
i. Urugan tanah Kembali dipadatkan 2.6250 m3 15,055.00 39,519.38 - 39,519.38
j. Pasang Pipa Galvanis Ø 3/4" 1.0000 Btg 175,000.00 175,000.00 - 175,000.00
Jumlah Harga Satuan 6,264,932.09 - 6,264,932.09
Dibulatkan 6,264,930.00 - 6,264,930.00

3 PEMBUATAN 1 Unit SEPTICTANK DAN REMBESAN UKURAN KECIL (1,0x1,5 Tinggi 1,75m) SK.SNI T-2001 & SNI 03-29/398-1991
Bahan / Upah :
a. Galian tanah septictank 3.6000 m3 79,195.00 285,102.00 - 285,102.00
b. Galian tanah rembesan 1.6950 m3 66,825.00 113,268.38 - 113,268.38
c. Pasangan bata (1PC ; 4 Psr) 8.7500 m2 104,365.00 913,193.75 - 913,193.75
d. Plesteran Kedap Air 1 Pc ; 3 Psr 7.5000 m2 57,305.00 429,787.50 - 429,787.50
e. Beton Praktis K-175 0.1500 m3 3,565,955.00 534,893.25 - 534,893.25
f. Pasir Urug 0.1071 m3 282,600.00 30,266.46 - 30,266.46
g. Lapisan Injuk Untuk Rembesan 2.7000 kg 11,000.00 29,700.00 - 29,700.00
h. Batu Pecah / Split Ukuran 0,5 - 2 cm 0.5250 m3 408,400.00 214,410.00 - 214,410.00
i. Urugan tanah Kembali dipadatkan 1.0500 m3 15,055.00 15,807.75 - 15,807.75
j. Pasang Pipa Galvanis Ø 3/4" 1.0000 Btg 175,000.00 175,000.00 - 175,000.00
Jumlah Harga Satuan 2,741,429.09 - 2,741,429.09
Dibulatkan 2,741,425.00 - 2,741,425.00

XVI. PENETAPAN INDEK HARGA SATUAN PEKERJAAN INFRA STRUKTUR


1 1 m1 SALURAN GRAVEL U 1/2 dia-20 cm SK.SNI T-2001
Bahan / Upah :
a. Pasangan 1/2 bata (1;5) 0.6000 m2 139,509.92 83,705.95 - 83,705.95
b. Gravel Uk. 1/2 diameter 20 cm panjang 1.0500 bh 51,800.00 54,390.00 - 54,390.00
c. Semen Portland ( PC TYPE I ) 10.0000 kg 1,544.00 15,440.00 - 15,440.00
d. Pasir Pasang 0.0500 m3 359,200.00 17,960.00 - 17,960.00
Tenaga Kerja :
Pekerja 0.0720 Oh. 100,000.00 - 7,200.00 7,200.00
Tukang batu 0.1250 Oh. 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0195 Oh. 150,000.00 - 2,925.00 2,925.00
Mandor 0.0195 Oh. 180,000.00 - 3,510.00 3,510.00
Jumlah Harga Satuan 171,495.95 31,135.00 202,630.95
Dibulatkan 171,495.00 31,135.00 202,630.00

2 1 m1 SALURAN GRAVEL U 1/2 dia-30 cm SK.SNI T-2001


Bahan / Upah :
a. Pasangan 1/2 bata (1;5) 0.6000 m2 139,509.92 83,705.95 - 83,705.95
b. Gravel Uk. 1/2 diameter 30 cm panjang 1.0500 bh 48,700.00 51,135.00 - 51,135.00
c. Semen Portland ( PC TYPE I ) 10.0000 kg 1,000.00 10,000.00 - 10,000.00
d. Pasir Pasang 0.0500 m3 4,500.00 225.00 - 225.00
Tenaga Kerja :
Pekerja 0.0720 Oh. 100,000.00 - 7,200.00 7,200.00
Tukang batu 0.1250 Oh. 140,000.00 - 17,500.00 17,500.00
Kepala tukang batu 0.0195 Oh. 150,000.00 - 2,925.00 2,925.00
Mandor 0.0195 Oh. 180,000.00 - 3,510.00 3,510.00
Jumlah Harga Satuan 145,065.95 31,135.00 176,200.95
Dibulatkan 145,065.00 31,135.00 176,200.00

3 1 m1 SALURAN PINGGIR BANGUNAN (Pas 1/2 Bata) SK.SNI T-2001


Bahan / Upah :
a. Pasangan 1/2 bata (1;5) 0.6000 m2 139,505.00 83,703.00 - 83,703.00
b. Plesteran dan Acian (1;5) 0.8000 m2 105,705.00 84,564.00 - 84,564.00
Jumlah Harga Satuan 168,267.00 - 168,267.00
Dibulatkan 168,265.00 - 168,265.00
4 1 m1 PASANGAN PAGAR BRC (Termasuk Pondasi + Pas Bata T. 40 Cm) SK.SNI T-2001
Bahan / Upah :
a. Pagar BRC T. 90 mm 1.1000 m1 39,500.00 43,450.00 - 43,450.00
b. Batu Belah Pondasi 0.2500 m3 286,000.00 71,500.00 - 71,500.00
c. Bata Merah Bakar (Kw. 2) 100.0000 bh 860.00 86,000.00 - 86,000.00
d. Beton praktis 0.2500 m3 1,134,875.00 283,718.75 - 283,718.75
Jumlah Harga Satuan 484,668.75 - 484,668.75
Dibulatkan 484,665.00 - 484,665.00

5 1 m1 PASANGAN PAGAR TEMBOK TINGGI 1,20 Cm (Sdh Termasuk PASANGAN Pondasi Pagar) SK.SNI T-2001
Bahan / Upah :
a. Bata Merah Bakar (Kw. 2) 100.0000 bh 860.00 86,000.00 - 86,000.00
b. Batu Belah Pondasi 0.2500 m3 286,000.00 71,500.00 - 71,500.00
c. Beton praktis 1.3300 m3 1,134,879.98 1,509,390.37 - 1,509,390.37
Jumlah Harga Satuan 1,666,890.37 - 1,666,890.37
Dibulatkan 1,666,890.00 - 1,666,890.00

6 1 m2 PEREKERASAN HALAMAN DENGAN PAVING BLOCK NATURAL Tebal 6 cm SK.SNI T-2001


Bahan :
Paving Block Natural 6 Cm 1.1000 m2 51,300.00 56,430.00 - 56,430.00
Pasir Pasang 0.1300 m3 359,200.00 46,696.00 - 46,696.00
Tenaga Kerja :
Pekerja 0.1400 Oh. 100,000.00 - 14,000.00 14,000.00
Tukang batu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0250 Oh. 150,000.00 - 3,750.00 3,750.00
Mandor 0.0195 Oh. 180,000.00 - 3,510.00 3,510.00
Jumlah Harga Satuan 103,126.00 35,260.00 138,386.00
Dibulatkan 103,125.00 35,260.00 138,385.00

7 1 m2 PEREKERASAN HALAMAN DENGAN PAVING BLOCK WARNA Tebal 6 cm SK.SNI T-2001


Bahan :
Paving Block Natural 6 Cm 1.1000 m2 65,000.00 71,500.00 - 71,500.00
Pasir Pasang 0.1300 m3 359,200.00 46,696.00 - 46,696.00
Tenaga Kerja :
Pekerja 0.1400 Oh. 100,000.00 - 14,000.00 14,000.00
Tukang batu 0.1000 Oh. 140,000.00 - 14,000.00 14,000.00
Kepala tukang batu 0.0250 Oh. 150,000.00 - 3,750.00 3,750.00
Mandor 0.0195 Oh. 180,000.00 - 3,510.00 3,510.00
Jumlah Harga Satuan 118,196.00 35,260.00 153,456.00
Dibulatkan 118,195.00 35,260.00 153,455.00

XVII. PENETAPAN INDEK HARGA SATUAN PEKERJAAN ELEKTRIKAL


1 PEMASANGAN 1 BUAH TITIK STOP KONTAK/DAYA 1 PHASE SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Kabel, NYM 3 x 2,5 mm2 7.0000 m1 260.00 1,820.00 - 1,820.00
Pipa Conduit 7.0000 m1 3,697.50 25,882.50 - 25,882.50
Socket Pipa 1.0000 bh 548.00 548.00 - 548.00
Tee Doos 2.0000 bh 990.00 1,980.00 - 1,980.00
Klem Pipa 3.0000 bh 4,400.00 13,200.00 - 13,200.00
Fhiser 6.0000 bh 600.00 3,600.00 - 3,600.00
Las Doop 2.0000 bh 22,000.00 44,000.00 - 44,000.00
Isolasi ban 0.2500 bh 7,000.00 1,750.00 - 1,750.00
Tenaga Kerja :
Pekerja 0.1667 Oh 100,000.00 - 16,666.67 16,666.67
Tukang instalatur M/E 0.3000 Oh 140,000.00 - 42,000.00 42,000.00
Mandor 0.3000 Oh. 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 92,780.50 112,666.67 205,447.17
Dibulatkan 92,780.00 112,665.00 205,445.00

2 PEMASANGAN 1 BUAH TITIK INSTALASI PENERANGAN/LAMPU SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Kabel, NYM 3 x 2,5 mm2 8.0000 m1 260.00 2,080.00 - 2,080.00
Pipa Conduit 8.0000 m1 3,697.50 29,580.00 - 29,580.00
Socket Pipa 1.0000 bh 548.00 548.00 - 548.00
Tee Doos 2.0000 bh 990.00 1,980.00 - 1,980.00
Klem Pipa 3.0000 bh 4,400.00 13,200.00 - 13,200.00
Fhiser 6.0000 bh 600.00 3,600.00 - 3,600.00
Las Doop 2.0000 bh 22,000.00 44,000.00 - 44,000.00
Isolasi ban 0.2500 bh 7,000.00 1,750.00 - 1,750.00
Tenaga Kerja :
Pekerja 0.1667 Oh 100,000.00 - 16,666.67 16,666.67
Tukang M/E 0.3000 Oh 140,000.00 - 42,000.00 42,000.00
Mandor 0.3000 Oh. 180,000.00 - 54,000.00 54,000.00
Jumlah Harga Satuan 96,738.00 112,666.67 209,404.67
Dibulatkan 96,735.00 112,665.00 209,400.00

3 PEMASANGAN 1 UNIT PEMASANGAN LAMPU TL 40 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu TL 40 Watt Philips + Arm 1.0000 bh 135,000.00 135,000.00 - 135,000.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 135,000.00 24,677.00 159,677.00
Dibulatkan 135,000.00 24,675.00 159,675.00

4 PEMASANGAN 1 UNIT PEMASANGAN LAMPU TL 20 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu TL 40 Watt Philips + Arm 1.0000 bh 87,500.00 87,500.00 - 87,500.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 87,500.00 24,677.00 112,177.00
Dibulatkan 87,500.00 24,675.00 112,175.00

5 PEMASANGAN 1 UNIT LAMPU PIJAR + FITTING PLAFOND SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu Pijar 15 - 60 Watt 1.0000 bh 15,000.00 15,000.00 - 15,000.00
Fitting Plafond Brocco 1.0000 bh 8,000.00 8,000.00 - 8,000.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 23,000.00 24,677.00 47,677.00
Dibulatkan 23,000.00 24,675.00 47,675.00

6 PEMASANGAN 1 BUAH STOP KONTAK Daya 10A/16A SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Stop Kontak Brocco 1.0000 bh 19,500.00 19,500.00 - 19,500.00
Tenaga Kerja :
Pekerja 0.0333 Oh 100,000.00 - 3,333.00 3,333.00
Tukang M/E 0.0667 Oh 140,000.00 - 9,338.00 9,338.00
Mandor 0.0667 Oh. 180,000.00 - 12,006.00 12,006.00
Jumlah Harga Satuan 19,500.00 24,677.00 44,177.00
Dibulatkan 19,500.00 24,675.00 44,175.00

7 PEMASANGAN 1 BUAH SAKLAR GANDA/DOUBLE SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Saklar Ganda 1.0000 bh 26,000.00 26,000.00 - 26,000.00
Tenaga Kerja :
Pekerja 0.0250 Oh 100,000.00 - 2,500.00 2,500.00
Tukang M/E 0.0500 Oh 140,000.00 - 7,000.00 7,000.00
Mandor 0.0500 Oh. 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 26,000.00 18,500.00 44,500.00
Dibulatkan 26,000.00 18,500.00 44,500.00

8 PEMASANGAN 1 BUAH SAKLAR TUNGGAL/ENGKEL SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Saklar Tunggal 10A 1.0000 bh 18,600.00 18,600.00 - 18,600.00
Tenaga Kerja :
Pekerja 0.0250 Oh 100,000.00 - 2,500.00 2,500.00
Tukang M/E 0.0500 Oh 140,000.00 - 7,000.00 7,000.00
Mandor 0.0500 Oh. 180,000.00 - 9,000.00 9,000.00
Jumlah Harga Satuan 18,600.00 18,500.00 37,100.00
Dibulatkan 18,600.00 18,500.00 37,100.00
VOLUME
### m2

46,859.20

26,400.00
PEK. TIANG PANCANG PER METER DAN TITIK
harga material tiang pancang m3 Rp 185,000
harga upah total oh Rp 100,000
harga joint & welding m3 Rp 390,000
Rp 675,000
6.12009
58.7529
117.506
2.9768
5.1963
0.4608
1 PEMASANGAN 1 UNIT PEMASANGAN Pas. Lampu SL 10 watt SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 10 Watt Philips + Arm ### bh 47,000.00 47,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 47,000.00 24,677.00
Dibulatkan 47,000.00 24,675.00

1 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 14 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 14 Watt Philips + Arm ### bh 49,000.00 49,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 49,000.00 24,677.00
Dibulatkan 49,000.00 24,675.00

1 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 18 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 18 Watt Philips + Arm ### bh 52,700.00 52,700.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 52,700.00 24,677.00
Dibulatkan 52,700.00 24,675.00

2 PEMASANGAN 1 UNIT PEMASANGAN LAMPU SL 23 WATT SK.SNI T-2001 & PUIL SNI 04-0225-1987
Bahan :
Lampu SL 23 Watt Philips + Arm ### bh 62,000.00 62,000.00 -
Tenaga Kerja :
Pekerja ### Oh 100,000.00 - 3,333.00
Tukang M/E ### Oh 140,000.00 - 9,338.00
Mandor ### Oh. 180,000.00 - 12,006.00
Jumlah Harga Satuan 62,000.00 24,677.00
Dibulatkan 62,000.00 24,675.00
T-2001 & PUIL SNI 04-0225-1987

47,000.00

3,333.00
9,338.00
12,006.00
71,677.00
71,675.00

T-2001 & PUIL SNI 04-0225-1987

49,000.00

3,333.00
9,338.00
12,006.00
73,677.00
73,675.00

T-2001 & PUIL SNI 04-0225-1987

52,700.00

3,333.00
9,338.00
12,006.00
77,377.00
77,375.00

T-2001 & PUIL SNI 04-0225-1987


62,000.00

3,333.00
9,338.00
12,006.00
86,677.00
86,675.00
Pri-

RENCANA ANGGARAN BIAYA (RAB )


Pekerjaan : Rumah Tinggal
Alamat : Cimalaka
Kabupaten : Sumedang

No. Jenis Pekerjaan Sat. Volume Harga Satuan Jumlah Harga


(Rp.) (Rp.)
A Rumah Tinggal
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan bouwplank m2 62.00 73,255.00 4,541,810.00
2 Mobilisasi Ls 1.00 -
3 Papan Proyek Ls 1.00 257,140.00 257,140.00
Jumlah :
II PEKERJAAN TANAH
1 Galian tanah pondasi batu kali m3 74.58 79,500.00 5,929,110.00
2 Galian tanah utk pondasi kolom teras m3 1.96 79,500.00 155,820.00
3 Urugan tanah bekas galian pondasi m3 25.49 22,620.00 576,534.49
4 Urugan pasir bawah pondasi dan lantai t=10 cm m3 60.00 370,920.00 22,255,200.00
5 Galian Tanah Biasa Kedalaman 3m m3 10.73 117,060.00 1,256,053.80
6 Urugan tanah bawah lantai m3 33.60 22,620.00 760,032.00
Jumlah :
III PEKERJAAN BETON
1 Pek.Sloof Beton (15/20)cm 2.53
a. Beton m3 0.08 1,134,875.00 86,051.90
b. Bekisting m2 1.01 198,480.00 200,663.28
c. Pembesian kg 9.10 15,525.00 141,261.97
2 Pek.Kolom Beton (15/20)cm h=3.5 4.85
a. Beton m3 0.51 1,134,875.00 577,920.20
b. Bekisting m2 13.58 35,000.00 475,287.75
c. Pembesian kg 56.02 15,525.00 869,649.27
3 Pek. Balok ring (20/20) cm 2.65
a. Beton m3 2.65 1,134,875.00 3,007,418.75
b. Bekisting m2 1.06 198,480.00 210,388.80
c. Pembesian kg 291.50 15,525.00 4,525,537.50
4. Pek. Tangga Beton 1.40
a. Beton m3 1.40 1,134,875.00 1,590,130.11
b. Bekisting m2 0.56 198,480.00 111,240.10
c. Pembesian Kg 154.13 15,525.00 2,392,813.91
5. Pek. Balok teras (20/40) cm 3.00
a. Beton m3 0.12 1,134,875.00 136,185.00
b. Bekisting m2 3.00 198,480.00 595,440.00
c. Pembesian kg 13.20 15,525.00 204,930.00
Jumlah :
IV PEKERJAAN PASANGAN & PLESTERAN
1 Pas. pondasi batu kali 1:5 m3 29.49 1,028,335.00 30,323,028.31
2 Pas. anstamping m3 14.63 610,750.00 8,932,218.75
3 Pas. dinding 1/2 bata m2 270.06 139,505.00 37,674,441.29
4 Plesteran 1:5 dan acian m2 699.00 128,795.00 90,027,705.00
5 Pas. Rabat beton 80cm t=5cm m2 0.85 52,700.00 45,026.88
6. Pas. Pondasi Pour & Strous m3 10.72 675,000.00 7,239,152.25
Jumlah :
V PEKERJAAN KUSEN, DAUN PINTU & JENDELA
1 Kusen Kayu Bahan 6/15, Kayu Lokal Kls. II m3 1.00 7,998,380.00 7,998,380.00
2 Pas. Pintu panil m2 5.69 657,895.00 3,746,251.50
3 Pas. Jendela tanpa kaca m2 15.84 526,355.00 8,337,463.20
4 Pas. Kaca Polos T. 5mm + List Kaca m2 44.04 227,065.00 9,999,942.60
5 Besi Angker Ø 10 mm Panjang 15 cm bh 30.00 -
6 Neut Beton (sepatu) bh 26.00 -
Jumlah :
VI PEKERJAAN ATAP
1 Rangka atap kayu m2 196.00 95,000.00 18,620,000.00
2 Genteng tanah liat m2 103.50 107,940.00 11,171,790.00
3 Pasang listplank 2/20 terpasang m' 236.54 105,300.00 24,907,827.37
Pri-

4 Nok Bubungan terpasang m' 3.50 65,940.00 230,790.00


Jumlah :
VII PEKERJAAN LANGIT-LANGIT
1 Pas. Rangka plafon m2 104.48 113,965.00 11,907,063.20
2 Pas. Plafon GRC m2 163.25 37,330.00 6,094,122.50
3 Pas. List plafon m1 25.25 21,480.00 542,370.00
Jumlah :
VIII PEKERJAAN CAT
1 Pengecatan dinding m2 651.00 35,825.00 23,322,075.00
2 Pengecatan Plafon m2 163.25 30,425.00 4,966,881.25
3 Pengecatan Kayu kusen m2 24.85 66,430.00 1,650,552.99
Jumlah :
IX PEKERJAAN LISTRIK
1 Pas. Instalasi titik lampu ttk 23.00 209,400.00 4,816,200.00
2 Pas. Instalasi stop kontak ttk 7.00 44,175.00 309,225.00
3 Pas. Sakelar ganda bh 8.00 44,500.00 356,000.00
4 Pas. Lampu SL 10 watt bh 6.00 71,675.00 430,050.00
5 Pas. Lampu SL 14 watt bh 9.00 73,675.00 663,075.00
6 Pas. Lampu SL 18 watt bh 4.00 77,375.00 309,500.00
7 Pas. Lampu SL 23 watt bh 4.00 86,675.00 346,700.00
Jumlah :
X PEKERJAAN KUNCI & PENGGANTUNG
1 Pas. Kunci tanam 2x putar bh 5.00 290,960.00 1,454,800.00
2 Pas. Engsel jendela 3" bh 48.00 39,590.00 1,900,320.00
3 Pas. Engsel pintu 4" bh 6.00 45,785.00 274,710.00
4 Pas. Grendel pintu bh 2.00 31,590.00 63,180.00
5 Pas. Grendel jendela bh 24.00 19,590.00 470,160.00
6 Pas. Hak Angin bh 24.00 -
Jumlah :
XI PASANGAN PENUTUP (PAS. KERAMIK)
1 Pas. Keramik Lantai 20/20 m2 6.00 146,750.00 880,500.00
2 Pas. Keramik Lantai 30/30 m2 12.75 148,870.00 1,898,092.50
3 Pas. Keramik Lantai 40/40 m2 50.25 161,800.00 8,130,450.00
Jumlah :
XII PEKERJAAN LAIN-LAIN
1 Pembuatan Plank Proyek Ls 1.00 -
Jumlah :
Total Rumah Tinggal
Dibulatkan :
Terbilang : ( )

Sumedang, September 2023

Perencana,
Pri-

B)

Total Biaya
(Rp.)

4,798,950.00

30,932,750.29

v. pondasi pour & stous 10.72

15,124,918.54

174,241,572.48

30,082,037.30
Pri-

54,930,407.37

18,543,555.70

29,939,509.25

7,230,750.00

4,163,170.00

10,909,042.50

-
380,896,663.42
380,897,000.00

umedang, September 2023


Pri-

REKAPITULASI RENCANA ANGGARAN BIAYA

Pekerjaan : Rumah Tinggal


Alamat : Cimalaka
Kabupaten : Sumedang

NO URAIAN PEKERJAAN JUMLAH HARGA

A Rumah Tinggal
I PEKERJAAN PERSIAPAN Rp 4,798,950
II PEKERJAAN TANAH Rp 30,932,750
III PEKERJAAN BETON Rp 15,124,919
IV PEKERJAAN PASANGAN & PLESTERAN Rp 174,241,572
V PEKERJAAN KUSEN, DAUN PINTU & JENDELA Rp 30,082,037
VI PEKERJAAN ATAP Rp 54,930,407
VII PEKERJAAN LANGIT-LANGIT Rp 18,543,556
VIII PEKERJAAN CAT Rp 29,939,509
IX PEKERJAAN LISTRIK Rp 7,230,750
X PEKERJAAN KUNCI & PENGGANTUNG Rp 4,163,170
XI PASANGAN PENUTUP (PAS. KERAMIK) Rp 10,909,043
XII PEKERJAAN LAIN-LAIN Rp -

Total Rumah Tinggal Rp 380,896,663

Pembulatan Rp 380,897,000

Sumedang, September 2023


Pri-
RENCANA ANGGARAN BIAYA (RAB)

No. Jenis Pekerjaan Sat. Volume

A PEKERJAAN FISIK
I PEKERJAAN PERSIAPAN
1 Pengukuran dan pemasangan Bouwplank m2 62.00
2 Steger dan Alat Bantu Ls 1.00
3 Pembersihan Area Kembali Ls 1.00
4 Mobilisasi Ls 1.00
5 Papan Proyek Ls 1.00
Jumlah :

II PEKERJAAN TANAH
1 Galian tanah pondasi batu kali m3 74.58
2 Galian tanah utk pondasi kolom teras m3 1.96
3 Urugan tanah bekas galian pondasi m3 25.49
4 Urugan pasir bawah pondasi dan lantai t=10 cm m3 60.00
5 Galian Tanah Biasa Kedalaman 3m m3 10.73
6 Urugan tanah bawah lantai m3 33.60
Jumlah :

III PEKERJAAN PONDASI


Pas. Aanstamping m3 23.38
Pas. Pondasi Batu Kali 1:5 m3 63.03
Jumlah :

IV PEKERJAAN BETON
1 Pek. Sloof Beton (15/20) cm
a. Beton m3 5.11
b. Bekisting m2 67.2
c. Pembesian kg 629.02
Jumlah :
2 Pek. Kolom Beton (15/15) cm
a. Beton m3 2.76
b. Bekisting m2 39.7
c. Pembesian kg 447.11
Jumlah :
3 Pek. Kolom Teras (20/20) cm
a. Beton m3 0.21
b. Bekisting m2 15.17
c. Pembesian kg 100.06
Jumlah :
4 Pek. Ring Balok (15/20) cm
a. Beton m3 2.23
b. Bekisting m2 29.8
c. Pembesian kg 266.11
Jumlah :
5 Balok Teras
a. Beton m3 3.15
b. Bekisting m2 22.97
c. Pembesian kg 337.9
Jumlah :

V PASANGAN & PLESTERAN


1 Pas. pondasi batu kali 1:5 m3 29.49
2 Pas. anstamping m3 14.63
3 Pas. dinding 1/2 bata m2 270.06
4 Plesteran 1:5 dan acian m2 699.00
5 Pas. Rabat beton 80cm t=5cm m2 0.85
6 Pas. Pondasi Pour & Strous m3 10.72
Jumlah :

VI PEKERJAAN KUSEN, DAUN PINTU & JENDELA


1 Kusen Kayu Bahan 6/15, Kayu Lokal Kls. II m3 1.00
2 Pas. Pintu panil m2 5.69
3 Pas. Jendela tanpa kaca m2 15.84
4 Pas. Kaca Polos T. 5mm + List Kaca m2 44.04
5 Besi Angker Ø 10 mm Panjang 15 cm bh 30.00
6 Neut Beton (sepatu) bh 26.00063
Jumlah :

VII PEKERJAAN ATAP


1 Rangka atap kayu m2 196.0
2 Genteng tanah liat m2 103.50
3 Pasang listplank 2/20 terpasang m' 236.54
4 Nok Bubungan terpasang m' 3.50
Jumlah :

VII PEKERJAAN LANGIT-LANGIT


1 Pas. Rangka plafon m2 104.48
2 Pas. Plafon GRC m2 163.25
3 Pas. List plafon m1 25.25
Jumlah :

IX PEKERJAAN CAT
1 Pengecatan dinding m2 651.00
2 Pengecatan Plafon m2 163.25
3 Pengecatan Kayu kusen m2 24.85
Jumlah :

X PEKERJAAN LISTRIK
1 Pas. Instalasi titik lampu ttk 23.00
2 Pas. Instalasi stop kontak ttk 7.00
3 Pas. Sakelar ganda bh 8.00
4 Pas. Lampu SL 10 watt bh 6.00
5 Pas. Lampu SL 14 watt bh 9.00
6 Pas. Lampu SL 18 watt bh 4.00
7 Pas. Lampu SL 23 watt bh 4.00
Jumlah :

XI PEKERJAAN KUNCI & PENGGANTUNG


1 Pas. Kunci tanam 2x putar bh 5.00
2 Pas. Engsel jendela 3" bh 48.00
3 Pas. Engsel pintu 4" bh 6.00
4 Pas. Grendel pintu bh 2.00
5 Pas. Grendel jendela bh 24.00
6 Pas. Hak Angin bh 24.00
Jumlah :

XII PAS. PENUTUP (PAS. KERAMIK)


1 Pas. Keramik Lantai 20/20 m2 120.21
2 Pas. Keramik Lantai 30/30 m2 5.2
3 Pas. Keramik Lantai 40/40 m2 23.08
Jumlah :

XII PEKERJAAN INSTALASI PLUMBING


1 Pas. Wastafel bh 2.00
2 Pas. Kloset duduk Lengkap bh 2.00
3 Pas, Jet Wasser bh 2.00
4 Pas. Bak Fiber bh 2.00
5 Pas. Kithen Zeng bh 1.00
6 Pas. Keran Air bh 4.00
7 Pas. Intalasi Fipa PVC 3/4" m1 37.06
8 Pas. Intalasi Fipa PVC 4" m1 66.10
9 Pek. Septictank dan Rembesan bh 2.00
Jumlah :

XII PEKERJAAN LAIN - LAIN


1 Pembuatan Plank Proyek Ls 1.00
Jumlah :
B PEKERJAAN NON FISIK
I PEKERJAAN FURNITUR RUANG
1 Sofa bh 2.00
2 Kursi bh 3.00
3 Lemari bh 2.00
4 Tempat Tidur bh 3.00
5 TV bh 1.00
6 Meja Kerja bh 3.00
7 Lemari Pakaian bh 3.00
8 Lemari TV bh 1.00
9 Piano bh 1.00
Jumlah :

II PEKERJAAN FURNITUR RUANG DAPUR


1 Kompor Portable bh 1.00
2 Kitchen Set bh 1.00
3 Kulkas bh 1.00
4 Mesin Cuci bh 1.00
5 Meja Makan bh 1.00
Jumlah :
Total Rumah Tinggal
Total
PROGRES RENCANA
RAN BIAYA (RAB)

Harga Satuan Jumlah Harga Total Biaya


(Rp.) (Rp.) (Rp.) Sep-26
BOBOT
1 2 3
73,255.00 4,541,810.00 0.578% 0.127%
1,500,000.00 1,500,000.00 0.191% 0.012% 0.012% 0.012%
1,750,000.00 1,750,000.00 0.223%
1,000,000.00 1,000,000.00 0.127% 0.064%
257,140.00 257,140.00 0.033%
9,048,950.00

79,500.00 5,929,110.00 0.754% 0.884% 0.884%


79,500.00 155,820.00 0.020%
22,620.00 576,534.49 0.073% 0.274%
370,920.00 22,255,200.00
117,060.00 1,256,053.80
22,620.00 760,032.00
30,932,750.29

607,516.20 14,203,728.76 1.806% 0.903% 0.903%


1,022,113.80 64,423,832.81 8.192% 4.096% 4.096%
78,627,561.57

1,134,639.35 5,798,007.07 0.737% 0.737%


66,066.60 4,439,675.52 0.565% 0.565%
54,974.00 34,579,745.48 4.397% 4.397%
44,817,428.07

1,134,639.35 3,131,604.60 0.398%


312,597.30 12,416,364.76 1.579%
54,974.00 24,579,425.14 3.125% 3.125%
40,127,394.50

1,134,639.35 238,274.26 0.030%


312,597.30 4,742,101.04 0.603%
54,974.00 5,500,698.44 0.699% 0.699%
10,481,073.74

1,134,639.35 2,530,245.75 0.322%


79,582.50 2,371,558.50 0.302%
54,974.00 14,629,131.14 1.860% 1.860%
19,530,935.39

1,134,639.35 3,574,113.95 0.454%


179,242.50 4,117,200.22 0.524%
54,974.00 18,576,264.34 2.362% 2.362%
26,267,578.52

1,028,335.00 30,323,028.31 3.856%


610,750.00 8,932,218.75 1.136%
139,505.00 37,674,441.29 4.790%
128,795.00 90,027,705.00 11.447%
52,700.00 45,026.88
675,000.00 7,239,152.25
174,241,572.48

7,998,380.00 7,998,380.00 1.017%


657,895.00 3,746,251.50 0.476%
526,355.00 8,337,463.20 1.060%
227,065.00 9,999,942.60 1.272%
- - 1.045%
- - 0.132%
30,082,037.30

95,000.00 18,620,000.00 2.368%


107,940.00 11,171,790.00 1.421%
105,300.00 24,907,827.37 3.167%
65,940.00 230,790.00 0.029%
54,930,407.37

113,965.00 11,907,063.20 1.514%


37,330.00 6,094,122.50 0.775%
21,480.00 542,370.00 0.069%
18,543,555.70
35,825.00 23,322,075.00 2.965%
30,425.00 4,966,881.25 0.632%
66,430.00 1,650,552.99 0.210%
29,939,509.25

209,400.00 4,816,200.00 0.612%


44,175.00 309,225.00 0.039%
44,500.00 356,000.00 0.045%
71,675.00 430,050.00 0.055%
73,675.00 663,075.00 0.084%
77,375.00 309,500.00 0.039%
86,675.00 346,700.00
7,230,750.00

290,960.00 1,454,800.00 0.185%


39,590.00 1,900,320.00 0.242%
45,785.00 274,710.00 0.035%
31,590.00 63,180.00 0.008%
19,590.00 470,160.00 0.060%
0.00 - 0.056%
4,163,170.00

249,529.36 29,995,924.37 3.814%


127,645.00 663,754.00 0.084%
83,737.50 1,932,661.50 0.246%
32,592,339.87

3,047,000.00 6,094,000.00 0.775%


2,955,720.00 5,911,440.00 0.752%
360,350.00 720,700.00 0.092%
1,553,126.00 3,106,252.00 0.395%
287,560.00 287,560.00 0.037%
60,260.00 241,040.00 0.031%
160,712.00 5,955,986.72 0.757%
483,512.00 31,960,143.20 4.064%
7,393,478.45 14,786,956.90 1.880%
69,064,078.82

- - 0.000%
-
1,355,000.00 2,710,000.00 0.345%
310,000.00 930,000.00 0.118%
2,500,000.00 5,000,000.00 0.636%
3,250,000.00 9,750,000.00 1.240%
1,950,000.00 1,950,000.00 0.248%
379,000.00 1,137,000.00 0.145%
2,500,000.00 7,500,000.00 0.954%
2,500,000.00 2,500,000.00 0.318%
50,000,000.00 50,000,000.00 6.358%
81,477,000.00

350,000.00 350,000.00 0.045%


1,849,999.00 1,849,999.00 0.235%
2,798,000.00 2,798,000.00 0.356%
1,929,000.00 1,929,000.00 0.245%
1,190,000.00 1,190,000.00 0.151%
8,116,999.00
786,451,036.02 100%
1.087% 6.169% 18.756%
RENCANA 1.087% 7.256% 26.012%
p-26 Sep-27 Sep-28 Sep-29
MINGGU KE
4 5 6 7 8 9 10 11 12 13

0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012% 0.012%
0.223%
0.064%

0.544%

0.199% 0.199%
0.789% 0.789%

0.015% 0.015%
0.301% 0.301%
0.161% 0.161%
0.151% 0.151%

0.227% 0.227%
0.262% 0.262%

3.034% 3.034%
3.981% 3.981%
3.711% 3.711%
0.089% 0.089%

0.214% 0.214%
0.000% 0.000%
0.074% 0.074%

0.132%

0.639% 0.639%
0.002% 0.002%
0.002% 0.002%
1.045% 1.045%

1.600% 1.600%
1.775%
0.636%
0.980%
0.040%
0.009%
0.036%
0.056%
0.082%

1.907% 1.907%
0.042%
0.123%

0.757%
4.064%
1.880%
5.396% 9.680% 8.504% 3.812% 2.977% 2.888% 3.492% 9.961% 2.141% 2.148%
31.408% 41.088% 49.592% 53.403% 56.380% 59.268% 62.760% 72.721% 74.863% 77.010%
Sep-29

14 15 16

0.012% 0.012% 0.012%


1.315%
1.045%
1.499% 1.499%
1.583%
0.004%

0.132%
0.128%
0.136%
0.020%
0.044%
0.056%

0.042%
0.123%

0.775%
0.752%
0.092%
0.395%
0.037%
0.031%

0.000%

0.000%
0.345%
0.118%
0.636%
1.240%
0.248%
0.145%
0.954%
0.318%
6.358%

0.045%
0.235%
0.356%
0.245%
0.151%

6.631% 4.820% 11.404%


83.641% 88.460% 99.865%
NO URAIAN PEKERJAAN MINGGU 1 MINGGU 2 MINGGU 3
BOBOT
A Rumah Tinggal
I PEKERJAAN PERSIAPAN 0.662% 0.132% 0.331% 0.198%
II PEKERJAAN TANAH 2.564% 0.513% 1.03%
III PEKERJAAN PONDASI 9.909% 0.991%
IV PEKERJAAN BETON 17.799%
V PASANGAN & PLESTERAN 21.437%
VI PEKERJAAN KUSEN, DAUN PINTU & JENDELA 3.521%
VII PEKERJAAN ATAP 5.701%
VIII PEKERJAAN LANGIT-LANGIT 5.560%
IX PEKERJAAN CAT 5.618%
X PEKERJAAN LISTRIK 1.056%
XI PEKERJAAN KUNCI & PENGGANTUNG 0.510%
XII PAS. PENUTUP ( PAS. KERAMIK ) 4.671%
XIII PEKERJAAN INSTALASI PLUMBING 8.704%
XIV PEKERJAAN LAIN-LAIN 0.996%
B PEKERJAAN NON FISIK
I PEKERJAAN FURNITUR RUANG 10.269%
II PEKERJAAN FURNITUR RUANG DAPUR 1.023%
Total 100%
Progres Rencana 0.132% 0.844% 2.215%
0.132% 0.976% 3.191%
MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9MINGGU 10MINGGU 11MINGGU 12
Chart Title
0.77% 0.256%
1.982% 3.964% 2.973%
3.560% 5.340% 5.340% 3.560%
4.287% 8.575% 8.575%
1.408% 2.113%
3.421% 2.281%
4.448% 1.112%
2.809% 2.247%
0.528%
0.408%
2.335% 2.335%
3.482% 3.482% 0.870%

0.513% 1.540% 1.540% 1.027% 2.567%

6.311% 9.560% 12.600% 13.543% 14.622% 10.605% 8.469% 7.318% 6.621%


9.502% 19.061% 31.661% 45.204% 59.826% 70.430% 78.899% 86.217% 92.838%
MINGGU 13MINGGU 14

0.562%
0.528%
0.102%

0.870%
0.996%

1.540% 1.540%
1.023%

3.603% 3.559%
96.441% 100.000%

Anda mungkin juga menyukai