Anda di halaman 1dari 95

DAFTAR HARGA BAHAN BANGUNAN

DAN UPAH KERJA

NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN


I BATA, BATU DAN PASIR
Bata Merah Buah Rp 750.00
Bata merah press Kelas I Buah Rp 1,000.00
Bata ringan tebal 10 cm Buah Rp 8,750.00
Bata ringan tebal 7.5 Buah Rp 7,500.00
Bata berongga Buah Rp 10,000.00
Bata Rosster Buah Rp 15,000.00
Batu Kali m3 Rp 250,000.00
Batu Split Pecah Mesin 1/2 m3 Rp 285,000.00
Batu Split Pecah Mesin 3/5 m3 Rp 275,000.00
Batu Split per Kg Kg Rp 158.33
Agregat Klas A m3 Rp 195,000.00
Agregat Klas B m3 Rp 185,000.00
Pasir Beton m3 Rp 250,000.00
Pasir Beton (Bj 1400 ) Kg Rp 178.57
Pasir Pasang (sedang) m3 Rp 200,000.00
Pasir Pasang (sedang) (Kg) Kg Rp 142.86
Pasir Urug m3 Rp 150,000.00
Tanah Urug m3 Rp 120,000.00
Sirtu m3 Rp 100,000.00
Tanah Liat m3 Rp 125,000.00
Air Liter Rp 150.00

II BAHAN PEREKAT
Semen (50Kg) Zak Rp 65,625.00
Semen (40Kg) Zak Rp 50,000.00
Semen PC Kg Rp 1,250.00
Semen Warna Kg Rp 5,000.00
MSP Zak Rp 150,000.00
MSP Kg Rp 5,500.00
semen grouting Kg Rp 65,000.00
Additive Ltr Rp 60,000.00
Kapur Padam m3 Rp 250,000.00
Kapur Sirih Kg Rp 2,500.00

III BAHAN BESI / BAJA :


Besi Polos/Ulir Kg Rp 10,000.00
Baja plat Kg Rp 13,000.00
Besi Tempa m2 Rp 200,000.00
Besi strip tebal 5 mm Kg Rp 13,000.00
Baja Struktur Kg Rp 13,150.00
UNP 150.75.6,5.10 Kg Rp 12,750.00
Kawat beton Kg Rp 17,500.00
Kawat Bronjong Kg Rp 20,000.00
Kawat Las Kg Rp 25,000.00
Elektroda baja kg Rp 30,000.00
Wiremesh Kg Rp 15,000.00
Kawat Jaring m Rp 30,000.00
Kawat Jaring Panjang 240 cm Lembar Rp 50,000.00
Kawat tali kg Rp 20,000.00
Kawat nyamuk m2 Rp 32,500.00
Kawat duri Barbwire Galvanize m' Rp 4,000.00
Kawat duri Razorwire 450 Strech 8 -9 m Roll Rp 350,000.00
Kawat duri Razorwire 500 Strech 9 -10 m Roll Rp 375,000.00
Besi Angkur Kg Rp 20,000.00
Baut Angkur Kg Rp 25,000.00
Mur + Baut bh Rp 7,500.00
Besi siku L30.30.3 Kg Rp 12,850.00
Besi siku L30.30.3 Lonjor Rp 30,000.00

Page 1
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
Besi Hollow (10x10x0,6)mm Lonjor Rp 30,000.00
Besi Hollow (10x10x0,6)mm m' Rp 5,000.00
Besi Hollow (20x20x1,60)mm - 6 m Lonjor Rp 80,000.00
Besi Hollow (20x20x1,60)mm - 6 m m' Rp 13,333.33
Besi Hollow (40x40 x3)mm - 6 m Lonjor Rp 210,000.00
Besi Hollow (40x40 x3)mm - 6 m m' Rp 35,000.00
Besi Hollow ( 50x50x3) mm Lonjor Rp 250,000.00
Besi Hollow ( 50x50x3) mm Kg Rp 38,000.00
Besi Hollo ( 100x50x2) mm m' Rp 68,333.33
Top Cross Rail - Heavy Dutty 0,70 mm (metal furing) m' Rp 15,000.00
Furring Channel -Fire Rated 0,50mm (metal furing) m' Rp 15,000.00
Connector Furing (metal furing) Buah Rp 1,500.00
Tutup Besi Tempa 60 x 60 cm Buah Rp 1,760,000.00
Tutup Besi Tempa 80 x 80 cm Buah Rp 2,475,000.00
Baja Ringan Profil C 75.0,75 Batang Rp 80,000.00
Baja Ringan Profil C 75.0,75 Kg Rp 15,000.00
Baja Ringan Profil C 75.0,80 Batang Rp 85,000.00
Baja Ringan Profil C 75.0,80 Kg Rp 15,000.00
Baja Ringan Profil C 75.1,00 Batang Rp 115,000.00
Baja Ringan Profil C 75.1,00 Kg Rp 15,000.00
Baja Ringan Reng 28.45 Batang Rp 30,000.00
Baja Ringan Reng 30.40 Batang Rp 32,000.00
Baja Ringan Reng 30.45 Batang Rp 34,000.00
Baja Ringan Reng 31.45 Batang Rp 35,000.00
Baja Ringan Reng 32.45 Batang Rp 36,000.00
Plat stainlessteel m2 Rp 520,833.33

IV BAHAN KAYU
Kayu Klas I (Jati ) m3 Rp 25,000,000.00
Kayu Klas II (Kamper ) m3 Rp 8,500,000.00
Kayu Klas III (Marenti, Keruing , Merbau ) m3 Rp 3,250,000.00
Kayu Klas IV (Sengon Laut, Sono ) m3 Rp 3,000,000.00
Dolken dia 8 s/d 10 cm m3 Rp 15,000.00
Papan kayu kamper m3 Rp 9,500,000.00
Kaso-kaso (5 × 7) cm kayu kamper m3 Rp 8,000,000.00
Reng (2 × 3) cm kayu kamper m3 Rp 7,500,000.00
Kaso-kaso (5 × 7) cm kayu meranti m3 Rp 2,750,000.00
Kaso-kaso (5 × 7) cm kayu meranti Btg Rp 32,500.00
Usuk (4x6) cm Kayu meranti m3 Rp 2,750,000.00
Kayu meranti (papan) m3 Rp 3,000,000.00
Balok kayu kamper m3 Rp 8,500,000.00
Bambu (P.600 cm) Btg Rp 10,000.00
Ijuk Kg Rp 6,000.00
Ijuk M3 Rp 50,000.00
Kawat Nyamuk Alumunium m2 Rp 25,000.00
Sealent Tube Rp 30,000.00

VI BAHAN PELAPIS :
Tripleks 3 mm (120x240)mm Lbr Rp 40,000.00
Tripleks 4 mm (120x240)mm Lbr Rp 60,000.00
Tripleks 6 mm (120x240)mm Lbr Rp 75,000.00
Tripleks 9 mm (120x240)mm Lbr Rp 125,000.00
Tripleks 12 mm Lbr Rp 150,000.00
Formica Lbr Rp 80,000.00
Plastik Aerator Lbr Rp 50,000.00

Page 2
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
VII BAHAN PERKERASAN , LANTAI & DINDING KERAMIK
Paving K - 500 m2 Rp 110,000.00
Stopper Uskup tebal 6 cm Buah Rp 4,000.00
Kanstin K-300 m1 Rp 50,000.00
Paving Block 6 cm natural m2 Rp 65,000.00
Paving Block 6 cm warna m2 Rp 75,000.00
Paving Block 8 cm natural m2 Rp 85,000.00
Paving Block 8 cm warna m2 Rp 100,000.00
Ubin granit tile (60x60) cm Bh Rp 80,000.00
Homogeneous Tile 60x60 ex Niro /Estilo: Elda, Carla m2 Rp 330,000.00
Keramik Lantai (11x11) cm (polos) buah Rp 12,000.00
Keramik Lantai (20x20) cm m2 Rp 55,000.00
Keramik Lantai (20x20) cm (Kasar) m2 Rp 45,000.00
Keramik Lantai (30x30) cm m2 Rp 60,000.00
Keramik Lantai (30x30) cm (warna) m2 Rp 50,000.00
Keramik Lantai (33x33) cm m2 Rp 70,000.00
Keramik Lantai (40x40) cm m2 Rp 65,000.00
Keramik Lantai (40x40) cm (warna) m2 Rp 57,000.00
Keramik Lantai (25x50) cm m2 Rp 100,000.00
Keramik Lantai (50x50) cm (warna) m2 Rp 72,000.00
Keramik Mozaik (30x30) cm m2 Rp 350,000.00
Plint Keramik (10x40) cm Buah Rp 15,000.00
Plint Keramik (10x60) cm Buah Rp 34,650.00
Plint Keramik (10x10)cm Buah Rp 13,500.00
Plint Keramik (5x20)cm Buah Rp 10,000.00
Step Nosing (10x20)cm Buah Rp 15,000.00
Step Nosing (10x30)cm Buah Rp 17,500.00
Step Nosing (10x40)cm Buah Rp 22,500.00
Plint Internal cove buah Rp 25,000.00
Keramik Rock Tile m2 Rp 100,000.00
Granite Rock Tile m2 Rp 250,000.00
Marmer (100x100) cm m2 Rp 500,000.00
Batu alam m2 Rp 120,000.00
Granit Lokal / Andesit m2 Rp 750,000.00
Tegel alur jalur tuna netra m2 Rp 200,000.00
Keramik Artistik m2 Rp 150,000.00
Teraso Polos Warna STD (30x30)cm m2 Rp 30,000.00
Teraso Polos Warna STD (30x30)cm Buah Rp 2,750.00
Teraso Polos Abu abu STD (30x30)cm m2 Rp 35,000.00
Teraso Polos Abu abu STD (30x30)cm Buah Rp 3,250.00
Teraso Polos Abu abu STD (20x20)cm m2 Rp 25,000.00
Teraso Polos Abu abu STD (20x20)cm Buah Rp 1,000.00
Teraso Motif (30x30)cm m2 Rp 32,500.00
Teraso Motif (30x30)cm Buah Rp 3,000.00
Granit (30x30)cm m2 Rp 240,000.00
Granit (30x30)cm Buah Rp 22,000.00
Granit (40x40)cm m2 Rp 280,000.00
Granit (40x40)cm Buah Rp 70,000.00
Granit (60x60)cm m2 Rp 275,000.00
Granit (60x60)cm Buah Rp 83,000.00
Marmer (60x120)cm m2 Rp 500,000.00
Marmer (60x120)cm Buah Rp 225,000.00
Marmer (60x60)cm m2 Rp 450,000.00
Marmer (60x60)cm Buah Rp 150,000.00
Marmer (40x40)cm m2 Rp 400,000.00
Marmer (40x40)cm Buah Rp 67,500.00

Page 3
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
Marmer (30x30)cm m2 Rp 400,000.00
Marmer (30x30)cm Buah Rp 65,000.00
Plint Ubin (10x20)cm bh Rp 3,500.00
Plint Ubin (10x30)cm bh Rp 5,000.00
Plint Ubin (10x40)cm bh Rp 6,000.00
Plint Ubin Warna (10x20)cm bh Rp 5,000.00
Plint Ubin Warna (10x30)cm bh Rp 6,000.00
Plint Ubin Warna (10x40)cm bh Rp 7,500.00
Plint Gnanit (10x30)cm bh Rp 15,000.00
Plint Gnanit (10x40)cm bh Rp 22,500.00
Plint Teralux Kerang (10x30)cm bh Rp 25,000.00
Plint Teralux Kerang (10x40)cm bh Rp 30,000.00
Plint Teralux Marmer (10x30)cm bh Rp 30,000.00
Plint Teralux Marmer (10x40)cm bh Rp 35,000.00
Plint Teralux Marmer (10x60)cm bh Rp 45,000.00
Lantai Vinyl Box Rp 350,000.00
Lantai Vinyl Buah Rp 7,500.00
Plint Vinyl 15x30 cm Buah Rp 4,000.00
Plint Vinyl profil 10 cm x 240 cm Batang Rp 150,000.00
Karpet Lantai m2 Rp 75,000.00
Underlayer m2 Rp 70,000.00
Parquet m2 Rp 150,000.00
Floor Hardener Kg Rp 10,000.00
Bata Keramik / Klinker m2 Rp 150,000.00

VIII BAHAN PENUTUP ATAP


Genteng Plentong Kecil 25pcs/m2 Buah Rp 1,500.00
Genteng Pelentong Besar (Murando) 18pcs/m2 Buah Rp 2,000.00
Genteng Kodok Bambe 20pcs/m2 Buah Rp 4,500.00
Genteng Kodok Glazur 20pcs/m2 Buah Rp 12,500.00
Genteng Kodok Goodyear 20pcs/m2 Buah Rp 4,750.00
Genteng Glazur Ex. KIA Buah Rp 10,000.00
Genteng Metal Ex.SAKURA Lembar Rp 99,000.00
Genteng kaca 12 mm Buah Rp 50,000.00
Genteng Beton Buah Rp 8,000.00
Genteng Aspal/Sirap Ex CTI m2 Rp 125,000.00
Genteng Aspal/Sirap Ex CTI Buah Rp 25,000.00
Bubungan Glazur Ex.KIA Buah Rp 24,000.00
Bubungan Genteng Plentong Buah Rp 15,000.00
Bubungan Genteng Kodok Buah Rp 15,000.00
Bubungan Genteng Aspal Buah Rp 25,000.00
Bubungan Genteng Beton Buah Rp 5,000.00
Seng plat 0,5 x 90 m' Rp 150,000.00
Seng Gelombang BJLS 0,25 x 80 m' Rp 30,000.00
Seng Gelombang BJLS 0,3 x 80 m' Rp 35,000.00
Seng Gelombang BJLS 0,3 x 80 x 210 lembar Rp 65,000.00
Plat Galvalum BJLS 0,4 x 120 m' Rp 100,000.00
Plat Galvalum BJLS 0,4 x 120 x 240 cm Lembar Rp 185,000.00
Bubung Stel Gelombang 0,92 m lembar Rp 35,000.00
Bubung Stel Gelombang 1,05 m lembar Rp 45,000.00
Bubung Stel Gelombang 1,08 m lembar Rp 50,000.00
Bubung Paten 0,92 m lembar Rp 39,000.00
Bubung Paten 1,05 m lembar Rp 42,000.00
Bubung Paten 1,08 m lembar Rp 49,000.00
Asbes gelombang kecil 105 x 240 Lembar Rp 75,000.00
Asbes gelombang kecil 105 x 300 Lembar Rp 100,000.00
Asbes gelombang besar 105 x 250 Lembar Rp 130,000.00
Asbes gelombang besar 105 x 300 Lembar Rp 150,000.00
Asbes Semen Gel. Kecil m2 Rp 25,000.00
Asbes Semen Gel Besar m2 Rp 35,000.00
Polycarbonate m2 Rp 121,065.38

Page 4
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
IX BAHAN KACA
Krepyak Nako Buah Rp 50,000.00
Kaca Polos 3 mm m2 Rp 85,000.00
Kaca Polos 5 mm m2 Rp 120,000.00
Kaca Polos 8 mm m2 Rp 150,000.00
Kaca Polos 10 mm m2 Rp 185,000.00
Kaca Rayban Tebal 5 mm m2 Rp 150,000.00
Kaca Wireglassed 5 mm m2 Rp 350,000.00
Kaca Tempered 12 mm m2 Rp 750,000.00

X BAHAN PAKU DAN MUR BAUT :


Paku 1 s/d 3 cm Kg Rp 17,500.00
Paku 5 s/d 10 cm Kg Rp 17,500.00
Paku 8 s/d 12 cm Kg Rp 17,500.00
Paku Skrup Bh Rp 750.00
Paku Payung /Seng 7 cm Kg Rp 20,000.00
Paku Payung /Seng 10 cm Kg Rp 25,000.00
Skrup Gypsum 3 " Bh Rp 500.00
Paku Asbes Sekrup 4 inchi Bh Rp 1,250.00
Skrup Fixer 4' Bh Rp 750.00
Ramset /Dynabolt Bh Rp 2,500.00
Angkur Bh Rp 25,000.00

XI BAHAN FINISHING :
Cat Dasar Tembok Kg Rp 40,000.00
Cat tembok (Interior) Kg Rp 60,000.00
Cat tembok (Exterior) Kg Rp 70,000.00
Cat tembok (Exterior) weathershield Kg Rp 80,000.00
Cat besi Kg Rp 65,000.00
Dempul Besi Kg Rp 35,000.00
Cat Anti Karat Kg Rp 75,000.00
Menie A kg Rp 22,500.00
Menie B kg Rp 20,000.00
Politur Liter Rp 75,000.00
Wood Filler Kg Rp 60,000.00
Vernis Liter Rp 70,000.00
Wood Stain Liter Rp 70,000.00
Sanding Sealer Liter Rp 75,000.00
Melamic Liter Rp 75,000.00
Teak Oil Liter Rp 45,000.00
Thinerr Liter Rp 25,000.00
Plamir Tembok Kg Rp 25,000.00
Minyak Begisting Liter Rp 5,000.00
Seal Tape Bh Rp 7,500.00
Amplas Lbr Rp 10,000.00
Kuwas / roll Bh Rp 25,000.00
Residu/Olie Bekas Liter Rp 5,000.00
Bensin Liter Rp 8,500.00
Solar Liter Rp 10,000.00
Minyak pelumas Liter Rp 35,000.00
Lem Kayu ex. Rajawali kg Rp 25,000.00
Lem Kayu ex. Fox kg Rp 30,000.00
Lem pipa PVC gel Tube Rp 10,000.00
Lem pipa PVC cair Kaleng Rp 30,000.00
Vertical Blind Standart m2 Rp 275,000.00
Vertical Blind Backout Deluxe m2 Rp 300,000.00
Vertical Blind Solar Screen m2 Rp 375,000.00
Wallpaper m Rp 75,000.00

Page 5
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
XII BAHAN SANITARI
Wastafel Rp 2,750,000.00
Closet jongkok Unit/Buah Rp 350,000.00
Closet duduk Tabung Ex Toto Unit/Buah Rp 2,500,000.00
Urinoir Unit/Buah Rp 2,850,000.00
Bak air fiberglas Unit/Buah Rp 450,000.00
Bak air fiberglas 1 m3 Unit/Buah Rp 750,000.00
Bak air Teraso Unit/Buah Rp 350,000.00
Jet shower Unit/Buah Rp 450,000.00
Shower Set Unit/Buah Rp 750,000.00
Floor drain PVC Buah Rp 25,000.00
Floor drain crome Buah Rp 325,000.00
Tempat Sabun Buah Rp 150,000.00
Bak Cuci Piring Teraso Buah Rp 500,000.00
Kitchenzink Unit/Buah Rp 500,000.00
Water Drain + Basket Buah Rp 150,000.00
Kran Air 1/2 " Crome Buah Rp 370,000.00
Kran Air 1/2 (besi) Buah Rp 25,000.00
Kran Air 1/2 (Plastik) Buah Rp 15,000.00
Kran Air 3/4 " Plastik Buah Rp 15,000.00
Kran Air 3/4 (besi) Buah Rp 35,000.00
Kran Angsa 1/2 " (Plastik) Buah Rp 50,000.00
Kran Angsa 1/2 " (Chrome) Buah Rp 150,000.00
Kran Air Panas/Dingin 1/2 " (Chrome) Buah Rp 250,000.00

XIII BAHAN PARTISI DINDING /PLAFOND


Gypsumboard t.9 mm Lembar Rp 60,000.00
List Profil 10 cm Gypsum m' Rp 15,000.00
Rangka plafond Metal furing m2 Rp 100,000.00
Kalsiboard 8 mm Lembar Rp 150,000.00
Kalsiboard 6 mm Lembar Rp 100,000.00
Akustik (30x30) cm 9 mm lembar Rp 50,000.00
Akustik (30x60) cm 9 mm lembar Rp 75,000.00
Akustik (60x120) cm 9 mm Lembar Rp 85,000.00
Asbes Semen 100x100 t.4 Lembar Rp 20,000.00
Asbes Semen100 x 100 t.5 Lembar Rp 22,500.00
Asbes Semen 120 x 240 t.6 Lembar Rp 30,000.00

XIV BAHAN SALURAN AIR /HIDRANT


Pipa PP Air Panas 1/2 " Ljr Rp 65,000.00
Pipa PP Air Dingin 1/2 " Ljr Rp 50,000.00
Pipa PVC 1/2" Type AW Panjang 4 m Ljr Rp 24,000.00
Pipa PVC 3/4" Type AW Panjang 4 m Ljr Rp 32,000.00
Pipa PVC 1" Type AW Panjang 4 m Ljr Rp 44,000.00
Pipa PVC 1 1/2" Type AW Panjang 4 m Ljr Rp 75,000.00
Pipa PVC 2" Type AW Panjang 4 m Ljr Rp 96,000.00
Pipa PVC 2,5" Type AW Panjang 4 m Ljr Rp 140,000.00
Pipa PVC 3" Type AW Panjang 4 m Ljr Rp 200,000.00
Pipa PVC 4" Type AW Panjang 4 m Ljr Rp 325,000.00
Pipa PVC 5" Type AW Panjang 4 m Ljr Rp 520,000.00
Pipa PVC 1 1/2" Type C Panjang 4 m Ljr Rp 46,000.00
Pipa PVC 2" Type C Panjang 4 m Ljr Rp 60,000.00
Pipa PVC 3" Type C Panjang 4 m Ljr Rp 106,000.00
Pipa PVC 4" Type C Panjang 4 m Ljr Rp 167,000.00

Page 6
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
Pipa PVC 5" Type C Panjang 4 m Ljr Rp 257,000.00
Pipa PVC 6" Type C Panjang 4 m Ljr Rp 340,000.00
Pipa PVC D dia 30 cm m1 Rp 345,000.00
Pipa GalvanisDia 1/2 " Rp 145,000.00
Pipa GalvanisDia 3/4 " Rp 183,000.00
Pipa GalvanisDia 1 " m1 Rp 47,000.00
Pipa GalvanisDia 1,5" Ljr Rp 426,000.00
Pipa GalvanisDia 1,5" m1 Rp 71,000.00
Pipa GalvanisDia 2,5" m1 Rp 123,500.00
Stop kran dia 1" bh Rp 100,000.00
Klep diameter 3/4" bh Rp 50,000.00
Tangki air 1000 liter bh Rp 1,250,000.00
Tangki air 500 liter bh Rp 800,000.00
Pelampung otomatis bh Rp 350,000.00
Roof Drain Metal Bh Rp 150,000.00
Mesin Jet Pump kap.250 watt unt Rp 8,500,000.00
Mesin Pompa tekan kap. 150 watt unt Rp 1,500,000.00
Tandon Cor 1 m3 Buah Rp 2,750,000.00
Tandon Cor 2 m3 Buah Rp 3,500,000.00
Tandon Cor 3 m3 Buah Rp 4,750,000.00
Tandon Cor 4 m3 Buah Rp 6,000,000.00
Tandon Cor 5 m3 Buah Rp 7,250,000.00
Water Stop PVC 150 m' Rp 61,000.00
Water Stop PVC 200 m' Rp 81,000.00
Water Stop PVC 250 m' Rp 110,000.00
Penjaga jarak bekisting/spacer Buah Rp 1,500.00
Panel Beton Precast m Rp 400,000.00
Strorox-100 kg Rp 45,000.00
Box Culvert 1500 x 1500 bh Rp 9,000,000.00
U-Ditch Uk. 60x60x120 bh Rp 900,000.00
Cover U-Ditch Uk. 60x60x120 bh Rp 530,000.00

XV PERALATAN ELEKTRIKAL
Box panel PVC isi 4 MCB Buah Rp 350,000.00
MCB 10 Ampere Buah Rp 100,000.00
MCB 6 Ampere Buah Rp 100,000.00
MCB 4 A Buah Rp 85,000.00
MCB 2 Ampere Buah Rp 60,000.00
Kabel NYM 2 x 2,5 mm2 Buah Rp 10,000.00
Kabel NYM 3 x 2,5 mm2 Buah Rp 13,000.00
Kabel Telepon m1 Rp 18,000.00
Kabel UTP Cat 5 e m1 Rp 15,000.00
Kabel UTP Cat 6 e m1 Rp 17,500.00
Konektor RJ 45 Set Rp 50,000.00
Isolator Buah Rp 15,000.00
Saklar Tunggal Buah Rp 25,000.00
Saklar Ganda Buah Rp 30,000.00
Stop Kontak Buah Rp 30,000.00
Outlet TV Buah Rp 45,000.00
Outlet Telephone Buah Rp 45,000.00
Down light / PLC 13 W Buah Rp 75,000.00
Fitting Plafon Buah Rp 15,000.00
Fiting Gantung EX Broco Buah Rp 10,000.00
Lampu TL 2 x 18 watt grille Buah Rp 250,000.00
Lampu TL 2 x 36 watt grille Buah Rp 350,000.00
Kabel NYA 1.5 mm m1 Rp 2,500.00
Kabel NYA 1.5 mm (50m) m1 Rp 125,000.00
Kabel NYA 1.5 mm (100m) rool Rp 250,000.00
Kabel NYA 2 x 1.5 mm m1 Rp 5,000.00
Klem Kabel pack Rp 15,000.00
Kabel NYA 500 Volt 2 x 2,5 mm2 m' Rp 7,500.00
Pipa Pralon 5/8 Lonjor Rp 12,000.00
L Bow 5/8 Buah Rp 1,500.00
T Doos Pvc Buah Rp 3,500.00

Page 7
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN

Page 8
NO NAMA/JENIS BAHAN SATUAN HARGA BAHAN 2018 URAIAN CATATAN
B SEWA PERALATAN
Scafolding Set/Hari Rp 2,500.00
Welding set ( min 5 jam ) jam Rp 75,000.00
Mini Pile 25x25 m' Rp 160,000.00
Pemancangan pile m' Rp 75,000.00
Pemotongan kepala tiang pancang ttk Rp 100,000.00

C UPAH
1 Pekerja Oh Rp 82,500.00
2 Tukang Batu Oh Rp 95,000.00
3 Tukang Las konstruksi Oh Rp 95,000.00
4 Tukang Cat Oh Rp 95,000.00
5 Tukang Las biasa Oh Rp 95,000.00
6 Tukang alumunium Oh Rp 95,000.00
7 Tukang Kayu Oh Rp 95,000.00
8 Tukang besi Oh Rp 95,000.00
9 Kepala Tukang Oh Rp 105,000.00
10 Mandor Oh Rp 110,000.00
11 Operator jam Rp 13,125.00
12 Pembantu Operator jam Rp 10,312.50
13 Sopir/Driver jam Rp 13,125.00
14 Pembantu Sopir/Driver jam Rp 10,312.50
15 Mekanik jam Rp 13,125.00
16 Pembantu Mekanik jam Rp 10,312.50
17 Juru Ukur jam Rp 13,125.00

Page 9
ANALISA HARGA SATUAN PEKERJAAN

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.200 Rp 82,500.00 Rp 16,500.00
Tukang kayu L.02 OH 0.400 Rp 95,000.00 Rp 38,000.00
Kepala tukang L.03 OH 0.020 Rp 105,000.00 Rp 2,100.00
Mandor L.04 OH 0.020 Rp 110,000.00 Rp 2,200.00
JUMLAH TENAGA KERJA Rp 58,800.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.250 Rp 15,000.00 Rp 18,750.00
Semen portland Kg 2.500 Rp 1,250.00 Rp 3,125.00
Seng gelombang Lbr 1.200 Rp 65,000.00 Rp 78,000.00
Pasir beton m3 0.005 Rp 250,000.00 Rp 1,250.00
Koral beton m3 0.009 Rp 275,000.00 Rp 2,475.00
Kayu 5/7 m3 0.072 Rp 2,750,000.00 Rp 198,000.00
Paku biasa 2” – 5” Kg 0.060 Rp 17,500.00 Rp 1,050.00
Meni besi Liter 0.450 Rp 25,000.00 Rp 11,250.00
JUMLAH HARGA BAHAN Rp 313,900.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 372,700.00

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.100 Rp 82,500.00 Rp 8,250.00
Tukang kayu L.02 OH 0.100 Rp 95,000.00 Rp 9,500.00
Kepala tukang L.03 OH 0.010 Rp 105,000.00 Rp 1,050.00
Mandor L.04 OH 0.005 Rp 110,000.00 Rp 550.00
JUMLAH TENAGA KERJA Rp 19,350.00
B BAHAN
Kayu balok 5/7 m3 0.012 Rp 2,750,000.00 Rp 33,000.00
Paku 2” – 3” Kg 0.020 Rp 17,500.00 Rp 350.00
Kayu papan 3/20 m3 0.007 Rp 3,000,000.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 54,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 73,700.00

A. 2.2.1.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 2.000 Rp 82,500.00 Rp 165,000.00
Tukang kayu L.02 OH 2.000 Rp 95,000.00 Rp 190,000.00
Tukang Batu L.02 OH 1.000 Rp 95,000.00 Rp 95,000.00
Kepala tukang L.03 OH 1.000 Rp 105,000.00 Rp 105,000.00
Mandor L.04 OH 0.050 Rp 110,000.00 Rp 5,500.00
JUMLAH TENAGA KERJA Rp 560,500.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.250 Rp 15,000.00 Rp 18,750.00
Kayu m3 0.180 Rp 2,750,000.00 Rp 495,000.00
Paku biasa Kg 0.080 Rp 17,500.00 Rp 1,400.00
Besi strip Kg 1.100 Rp 13,000.00 Rp 14,300.00
Semen portland Kg 35.000 Rp 1,250.00 Rp 43,750.00
Pasir pasang m3 0.150 Rp 200,000.00 Rp 30,000.00
Pasir beton m3 0.100 Rp 250,000.00 Rp 25,000.00
Koral beton m3 0.150 Rp 275,000.00 Rp 41,250.00
Bata merah Bh 30.000 Rp 750.00 Rp 22,500.00
Seng plat m' 0.250 Rp 150,000.00 Rp 37,500.00
Jendela naco bh 0.200 Rp 40,000.00 Rp 8,000.00
kaca polos m2 0.080 Rp 120,000.00 Rp 9,600.00
kunci tanam bh 0.150 Rp 150,000.00 Rp 22,500.00
playwood 4 mm lbr 0.060 Rp 60,000.00 Rp 3,600.00
JUMLAH HARGA BAHAN Rp 773,150.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,333,650.00

Page 10
2.2.1.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 1.000 Rp 82,500.00 Rp 82,500.00
Tukang kayu L.02 OH 2.000 Rp 95,000.00 Rp 190,000.00
Kepala tukang L.03 OH 0.200 Rp 105,000.00 Rp 21,000.00
Mandor L.04 OH 0.050 Rp 110,000.00 Rp 5,500.00
JUMLAH TENAGA KERJA Rp 299,000.00
B BAHAN
Dolken kayu Ø 8-10/400 cm Batang 1.700 Rp 15,000.00 Rp 25,500.00
Kayu m3 0.210 Rp 2,750,000.00 Rp 577,500.00
Paku biasa Kg 0.300 Rp 17,500.00 Rp 5,250.00
Semen portland Kg 10.500 Rp 1,250.00 Rp 13,125.00
Pasir beton m3 0.030 Rp 250,000.00 Rp 7,500.00
Koral beton m3 0.050 Rp 275,000.00 Rp 13,750.00
Seng gelombang Lbr 1.500 Rp 65,000.00 Rp 97,500.00
Seng plat m' 0.250 Rp 150,000.00 Rp 37,500.00
JUMLAH HARGA BAHAN Rp 777,625.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,076,625.00

2.2.1.9. (K3) Pembersihan 1 m2 lapangan


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.100 Rp 82,500.00 Rp 8,250.00
Mandor L.04 OH 0.050 Rp 110,000.00 Rp 5,500.00
JUMLAH TENAGA KERJA Rp 13,750.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 13,750.00

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.750 Rp 82,500.00 Rp 61,875.00
Mandor L.04 OH 0.025 Rp 110,000.00 Rp 2,750.00
JUMLAH TENAGA KERJA Rp 64,625.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) Rp 64,625.00

A.2.3.1.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.330 Rp 82,500.00 Rp 27,225.00
Mandor L.04 OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH TENAGA KERJA Rp 28,325.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa Dump truk 5 ton Jam 0.088 Rp 100,000.00 Rp 8,800.00
JUMLAH HARGA ALAT Rp 8,800.00
D Jumlah (A+B+C) Rp 37,125.00

Page 11
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.500 Rp 82,500.00 Rp 41,250.00
Mandor L.04 OH 0.050 Rp 110,000.00 Rp 5,500.00
JUMLAH TENAGA KERJA Rp 46,750.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa alat bantu 1 set @ 3 alat m3 8.000 Rp 1,100.00 Rp 8,800.00
JUMLAH HARGA ALAT Rp 8,800.00
D Jumlah (A+B+C) Rp 55,550.00

A.2.3.1.10. (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm)


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.500 Rp 82,500.00 Rp 41,250.00
Mandor L.04 OH 0.050 Rp 110,000.00 Rp 5,500.00
JUMLAH TENAGA KERJA Rp 46,750.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
Sewa vibrator roller min 5 jam Jam 0.012 Rp 200,000.00 Rp 2,400.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 49,150.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.300 Rp 82,500.00 Rp 24,750.00
Mandor L.04 OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH TENAGA KERJA Rp 25,850.00
B BAHAN
Pasir urug m3 1.200 Rp 150,000.00 Rp 180,000.00
JUMLAH HARGA BAHAN Rp 180,000.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) Rp 205,850.00

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerjaan L.01 OH 0.250 Rp 82,500.00 Rp 20,625.00
Mandor L.04 OH 0.025 Rp 110,000.00 Rp 2,750.00
JUMLAH TENAGA KERJA Rp 23,375.00
B BAHAN
Sirtu m3 1.200 Rp - Rp -
JUMLAH HARGA BAHAN Rp -
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) Rp 23,375.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1. Pemasangan 1 m3 pondasi batu kali campuran 1SP : 3PP
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 1.500 Rp 82,500.00 Rp 123,750.00
Tukang Batu L.02 OH 0.750 Rp 95,000.00 Rp 71,250.00
Kepala tukang L.03 OH 0.075 Rp 105,000.00 Rp 7,875.00
Mandor L.04 OH 0.075 Rp 110,000.00 Rp 8,250.00
JUMLAH TENAGA KERJA Rp 211,125.00
B BAHAN
Batu belah m3 1.200 Rp 250,000.00 Rp 300,000.00
Semen Portland kg 202.000 Rp 1,250.00 Rp 252,500.00
Pasir pasang m3 0.485 Rp 200,000.00 Rp 97,000.00
JUMLAH HARGA BAHAN Rp 649,500.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 860,625.00

Page 12
A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 1.200 Rp 82,500.00 Rp 99,000.00
Tukang Batu L.02 OH 0.200 Rp 95,000.00 Rp 19,000.00
Kepala tukang L.03 OH 0.020 Rp 105,000.00 Rp 2,100.00
Mandor L.04 OH 0.060 Rp 110,000.00 Rp 6,600.00
JUMLAH TENAGA KERJA Rp 126,700.00
B BAHAN
semen portland kg 230.000 Rp 1,250.00 Rp 287,500.00
pasir beton kg 893.000 Rp 178.57 Rp 159,464.29
kerikil (maks 30 mm) kg 1,027.000 Rp 158.33 Rp 162,608.33
air Liter 200.000 Rp 150.00 Rp 30,000.00
JUMLAH HARGA BAHAN Rp 639,572.62
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 766,272.62

A.4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 1.650 Rp 82,500.00 Rp 136,125.00
Tukang Batu L.02 OH 0.275 Rp 95,000.00 Rp 26,125.00
Kepala tukang L.03 OH 0.028 Rp 105,000.00 Rp 2,940.00
Mandor L.04 OH 0.083 Rp 110,000.00 Rp 9,130.00
JUMLAH TENAGA KERJA Rp 174,320.00
B BAHAN
semen portland kg 413.000 Rp 1,250.00 Rp 516,250.00
pasir beton kg 681.000 Rp 178.57 Rp 121,607.14
kerikil (maks 30 mm) kg 1,021.000 Rp 158.33 Rp 161,658.33
air Liter 215.000 Rp 150.00 Rp 32,250.00
JUMLAH HARGA BAHAN Rp 831,765.48
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,006,085.48

A.4.1.1.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, slump (120 ± 20) mm
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 2.100 Rp 82,500.00 Rp 173,250.00
Tukang Batu L.02 OH 0.350 Rp 95,000.00 Rp 33,250.00
Kepala tukang L.03 OH 0.035 Rp 105,000.00 Rp 3,675.00
Mandor L.04 OH 0.105 Rp 110,000.00 Rp 11,550.00
JUMLAH TENAGA KERJA Rp 221,725.00
B BAHAN
semen portland kg 448.000 Rp 1,250.00 Rp 560,000.00
pasir beton kg 667.000 Rp 178.57 Rp 119,107.14
kerikil (maks 30 mm) kg 1,000.000 Rp 158.33 Rp 158,333.33
air Liter 215.000 Rp 150.00 Rp 32,250.00
JUMLAH HARGA BAHAN Rp 869,690.48
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,091,415.48

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting batako


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.300 Rp 82,500.00 Rp 24,750.00
Tukang kayu L.02 OH 0.100 Rp 95,000.00 Rp 9,500.00
Kepala tukang L.03 OH 0.010 Rp 105,000.00 Rp 1,050.00
Mandor L.04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH TENAGA KERJA Rp 36,950.00
B BAHAN
batako bh 15.000 5,000.00 Rp 75,000.00
Pasir pasang m3 0.043 Rp 200,000.00 Rp 8,600.00
Pc kg 10.120 Rp 1,250.00 Rp 12,650.00
JUMLAH HARGA BAHAN Rp 96,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 133,200.00

Page 13
A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.520 Rp 82,500.00 Rp 42,900.00
Tukang kayu L.02 OH 0.260 Rp 95,000.00 Rp 24,700.00
Kepala tukang L.03 OH 0.026 Rp 105,000.00 Rp 2,730.00
Mandor L.04 OH 0.026 Rp 110,000.00 Rp 2,860.00
JUMLAH TENAGA KERJA Rp 73,190.00
B BAHAN
Kayu kelas III m3 0.045 Rp 3,250,000.00 Rp 146,250.00
Paku 5 – 10 cm Kg 0.300 Rp 17,500.00 Rp 5,250.00
Minyak bekisting Liter 0.100 Rp 5,000.00 Rp 500.00
JUMLAH HARGA BAHAN Rp 152,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 225,190.00

A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,663.00
JUMLAH TENAGA KERJA Rp 92,928.00
B BAHAN
Kayu kelas III m3 0.040 Rp 3,250,000.00 Rp 130,000.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.200 Rp 5,000.00 Rp 1,000.00
Balok kayu kelas III m3 0.015 Rp 2,750,000.00 Rp 41,250.00
Multiplek tebal 12 mm Lbr 0.350 Rp 150,000.00 Rp 52,500.00
Dolken kayu ᴓ 8 -10cm – 4 m Batang 2.000 Rp 15,000.00 Rp 30,000.00
JUMLAH HARGA BAHAN Rp 261,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 354,678.00

A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,630.00
JUMLAH TENAGA KERJA Rp 92,895.00
B BAHAN
Kayu kelas III m3 0.040 Rp 3,250,000.00 Rp 130,000.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.200 Rp 5,000.00 Rp 1,000.00
Balok kayu kelas III m3 0.018 Rp 2,750,000.00 Rp 49,500.00
Multiplek tebal 12 mm Lbr 0.350 Rp 150,000.00 Rp 52,500.00
Dolken kayu ᴓ 8 -10cm –panj 4 m Batang 2.000 Rp 15,000.00 Rp 30,000.00
JUMLAH HARGA BAHAN Rp 270,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 362,895.00

A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk plat lantai


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,630.00
JUMLAH TENAGA KERJA Rp 92,895.00
B BAHAN
Kayu kelas III m3 0.040 Rp 3,250,000.00 Rp 130,000.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.200 Rp 5,000.00 Rp 1,000.00
Balok kayu kelas III m3 0.015 Rp 2,750,000.00 Rp 41,250.00
Multiplek tebal 9 mm Lbr 0.350 Rp 125,000.00 Rp 43,750.00
Dolken kayu ᴓ 8 -10cm –panj 4 m Batang 6.000 Rp 15,000.00 Rp 90,000.00
JUMLAH HARGA BAHAN Rp 313,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 405,895.00

Page 14
A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk plat lantai
No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,630.00
JUMLAH TENAGA KERJA Rp 92,895.00
B BAHAN
Kayu kelas III m3 0.040 Rp 3,250,000.00 Rp 130,000.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.200 Rp 5,000.00 Rp 1,000.00
Balok kayu kelas III m3 0.015 Rp 2,750,000.00 Rp 41,250.00
Multiplek tebal 12 mm Lbr 0.350 Rp 150,000.00 Rp 52,500.00
Dolken kayu ᴓ 8 -10cm –panj 4 m Batang 6.000 Rp 15,000.00 Rp 90,000.00
JUMLAH HARGA BAHAN Rp 321,750.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 414,645.00

A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,630.00
JUMLAH TENAGA KERJA Rp 92,895.00
B BAHAN
Kayu kelas III m3 0.030 Rp 3,250,000.00 Rp 97,500.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.200 Rp 5,000.00 Rp 1,000.00
Balok kayu kelas III m3 0.020 Rp 2,750,000.00 Rp 55,000.00
Multiplek tebal 12 mm Lbr 0.350 Rp 150,000.00 Rp 52,500.00
Dolken
Penjagakayu
jarakᴓ 8 -10cm –panj 4 m Batang 3.000 Rp 15,000.00 Rp 45,000.00
bekisting/spacer Buah 0.400 Rp 1,500.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 258,600.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 351,495.00

A.4.1.1.26 (K3) Pemasangan 1 m2 bekisting untuk tangga


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.660 Rp 82,500.00 Rp 54,450.00
Tukang kayu L.02 OH 0.330 Rp 95,000.00 Rp 31,350.00
Kepala tukang L.03 OH 0.033 Rp 105,000.00 Rp 3,465.00
Mandor L.04 OH 0.033 Rp 110,000.00 Rp 3,630.00
JUMLAH TENAGA KERJA Rp 92,895.00
B BAHAN
Kayu kelas III m3 0.030 Rp 3,250,000.00 Rp 97,500.00
Paku 5 cm – 12 cm Kg 0.400 Rp 17,500.00 Rp 7,000.00
Minyak bekisting Liter 0.400 Rp 5,000.00 Rp 2,000.00
Balok kayu kelas III m3 0.015 Rp 2,750,000.00 Rp 41,250.00
Multiplek tebal 12 mm Lbr 0.350 Rp 150,000.00 Rp 52,500.00
Dolken kayu ᴓ 8 -10cm –panj 4 m Batang 2.000 Rp 15,000.00 Rp 30,000.00
JUMLAH HARGA BAHAN Rp 230,250.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 323,145.00

A.4.1.1.27 Pembesian polos/ulir


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja L.01 OH 0.007 Rp 82,500.00 Rp 577.50
Tukang besi L.02 OH 0.007 Rp 95,000.00 Rp 665.00
Kepala tukang L.03 OH 0.007 Rp 105,000.00 Rp 735.00
Mandor L.04 OH 0.007 Rp 110,000.00 Rp 770.00
JUMLAH TENAGA KERJA Rp 2,747.50
B BAHAN
Besi polos/ulir kg 1.050 Rp 10,000.00 Rp 10,500.00
Kawat beton kg 0.015 Rp 17,500.00 Rp 262.50
JUMLAH HARGA BAHAN Rp 10,762.50
C PERALATAN

JUMLAH HARGA ALAT

Page 15
D Jumlah (A+B+C) Rp 13,510.00

Page 16
ANALISA PEKERJAAN

No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)


A TENAGA
Pekerja OH 0.006 Rp 82,500.00 Rp 495.00
Tukang Baja OH 0.060 Rp 95,000.00 Rp 5,700.00
Kepala Tukang OH 0.006 Rp 105,000.00 Rp 630.00
Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH TENAGA KERJA Rp 7,155.00
B BAHAN
Baja WF Kg 1.100 Rp 13,150.00 Rp 14,465.00
Elektroda baja Kg 0.020 Rp 30,000.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 15,065.00
C PERALATAN
Sewa welding set ( min 5 jam ) Jam 0.035 Rp 75,000.00 Rp 2,625.00
JUMLAH HARGA ALAT Rp 2,625.00

D Jumlah (A+B+C) Rp 24,845.00

No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)


A TENAGA
Pekerja OH 0.006 Rp 82,500.00 Rp 495.00
Tukang Baja OH 0.060 Rp 95,000.00 Rp 5,700.00
Kepala Tukang OH 0.006 Rp 105,000.00 Rp 630.00
Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH TENAGA KERJA Rp 7,155.00
B BAHAN
UNP 75 (tebal 0.75 mm) Kg 1.100 Rp 12,750.00 Rp 14,025.00
Elektroda baja Kg 0.020 Rp 30,000.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 14,625.00
C PERALATAN
Sewa welding set ( min 5 jam ) Jam 0.035 Rp 75,000.00 Rp 2,625.00
JUMLAH HARGA ALAT Rp 2,625.00

D Jumlah (A+B+C) Rp 24,405.00

No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)


A TENAGA
Pekerja OH 0.006 Rp 82,500.00 Rp 495.00
Tukang Baja OH 0.060 Rp 95,000.00 Rp 5,700.00
Kepala Tukang OH 0.006 Rp 105,000.00 Rp 630.00
Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH TENAGA KERJA Rp 7,155.00
B BAHAN
Gording C Kg 1.100 Rp 12,500.00 Rp 13,750.00
Sewa welding set ( min 5 jam ) Kg 0.020 Rp 30,000.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 14,350.00
C PERALATAN
Sewa welding set ( min 5 jam ) Jam 0.035 Rp 75,000.00 Rp 2,625.00
JUMLAH HARGA ALAT Rp 2,625.00

D Jumlah (A+B+C) Rp 24,130.00


No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)
A TENAGA
Pekerja OH 0.006 Rp 82,500.00 Rp 495.00
Tukang Baja OH 0.060 Rp 95,000.00 Rp 5,700.00
Kepala Tukang OH 0.006 Rp 105,000.00 Rp 630.00
Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH TENAGA KERJA Rp 7,155.00
B BAHAN
Baja L siku Kg 1.100 Rp 12,850.00 Rp 14,135.00
Sewa welding set ( min 5 jam ) Kg 0.020 Rp 30,000.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 14,135.00
C PERALATAN
Sewa welding set ( min 5 jam ) Jam 0.035 Rp 75,000.00 Rp 2,625.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C) Rp 23,915.00

No Uraian Kode Satuan Koefisien Harga satuan (RP) Jumlah Harga(RP)


A TENAGA
Pekerja OH 0.006 Rp 82,500.00 Rp 495.00
Tukang Baja OH 0.060 Rp 95,000.00 Rp 5,700.00
Kepala Tukang OH 0.006 Rp 105,000.00 Rp 630.00
Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH TENAGA KERJA Rp 7,155.00
B BAHAN
Plat Sambung Kg 1.150 Rp 13,000.00 Rp 14,950.00
Sewa welding set ( min 5 jam ) Kg 0.020 Rp 30,000.00 Rp 600.00
JUMLAH HARGA BAHAN Rp 14,950.00
C PERALATAN
Sewa welding set ( min 5 jam ) Jam 0.035 Rp 75,000.00 Rp 2,625.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C) Rp 24,730.00


ANALISA HARGA SATUAN

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
PEKERJAAN BETON BERTULANG

JENIS PEKERJAAN A ,4, 1, 1, 35 : 1 m1 Pekerjaan Beton Bertulang Kolom dan balok Praktis
A TENAGA
1 Pekerja L01 OH 0.180 Rp 82,500.00 Rp 14,850.00
2 Tukang Batu L02 OH 0.020 Rp 95,000.00 Rp 1,900.00
3 Tukang kayu L02 OH 0.020 Rp 95,000.00 Rp 1,900.00
4 Tukang Besi L02 OH 0.020 Rp 95,000.00 Rp 1,900.00
5 Kepala Tukang L03 OH 0.006 Rp 105,000.00 Rp 630.00
6 Mandor L04 OH 0.009 Rp 110,000.00 Rp 990.00
JUMLAH HARGA TENAGA Rp 22,170.00
B BAHAN
1 kayu kelas III m3 0.006 Rp 3,250,000.00 Rp 19,500.00
2 paku 5 - 10cm kg 0.010 Rp 17,500.00 Rp 175.00
3 minyak bekesting liter 0.200 Rp 5,000.00 Rp 1,000.00
4 besi beton ( polos / ulir ) kg 3.000 Rp 10,000.00 Rp 30,000.00
5 kawat bendreat kg 0.045 Rp 17,500.00 Rp 787.50
6 Portland Cement (PC) kg 6.000 Rp 1,250.00 Rp 7,500.00
7 Pasir Cor m3 0.060 Rp 250,000.00 Rp 15,000.00
8 Stenslah/batu pecah tangan 2/3 m3 0.009 Rp 275,000.00 Rp 2,475.00
JUMLAH HARGA BAHAN Rp 76,437.50
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 98,607.50


Per m3 Rp 8,149,380.17

PEKERJAAN PASANGAN DINDING

JENIS PEKERJAAN A,4,4,1,10 : 1 m2 Pasangan dinding bata ringan


A TENAGA
1 Pekerja L01 OH 0.350 Rp 82,500.00 Rp 28,875.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.018 Rp 110,000.00 Rp 1,980.00
JUMLAH HARGA TENAGA Rp 46,680.00
B BAHAN
1 Bata ringan (ex citicon) bh 8.500 Rp 8,750.00 Rp 74,375.00
2 Perekat MU 380 40 Kg kg 0.080 Rp 5,500.00 Rp 440.00
3 Alat Bantu ls 1.000 Rp 5,000.00 Rp 5,000.00
JUMLAH HARGA BAHAN Rp 79,815.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 126,495.00

JENIS PEKERJAAN : 1 m2 Pasangan dinding roster


A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 Roster semen bh 26.250 Rp 15,000.00 Rp 393,750.00
2 Portland kg 5.184 Rp 1,250.00 Rp 6,480.00
3 Pasir pasang m3 1.000 Rp 200,000.00 Rp 200,000.00
JUMLAH HARGA BAHAN Rp 600,230.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 642,455.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN : 1 m2 pasangan bata merah tebal 1/2 bata, 1Pc : 3Ps
A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 Bata merah 5 x 11 x 22 cm bh 70.000 Rp 750.00 Rp 52,500.00
2 Semen portland kg 14.370 Rp 1,250.00 Rp 17,962.50
3 Pasir pasang m3 0.040 Rp 200,000.00 Rp 8,000.00
JUMLAH HARGA BAHAN Rp 78,462.50
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 120,687.50

JENIS PEKERJAAN : 1 m2 pasangan bata merah tebal 1 bata, 1Pc : 3Ps


A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 Bata merah 5 x 11 x 22 cm bh 140.000 Rp 750.00 Rp 105,000.00
2 Semen portland kg 28.500 Rp 1,250.00 Rp 35,625.00
3 Pasir pasang m3 0.080 Rp 200,000.00 Rp 16,000.00
JUMLAH HARGA BAHAN Rp 156,625.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 198,850.00

JENIS PEKERJAAN : 1 m2 pasangan bata merah tebal 1/2 bata, 1Pc : 5Ps
A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 Bata merah 5 x 11 x 22 cm bh 70.000 Rp 750.00 Rp 52,500.00
2 Semen portland kg 9.680 Rp 1,250.00 Rp 12,100.00
3 Pasir pasang m3 0.045 Rp 200,000.00 Rp 9,000.00
JUMLAH HARGA BAHAN Rp 73,600.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 115,825.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN : 1 m2 pasangan bata merah tebal 1 bata, 1Pc : 5Ps
A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 Bata merah 5 x 11 x 22 cm bh 140.000 Rp 750.00 Rp 105,000.00
2 Semen portland kg 33.000 Rp 1,250.00 Rp 41,250.00
3 Pasir pasang m3 0.080 Rp 200,000.00 Rp 16,000.00
JUMLAH HARGA BAHAN Rp 162,250.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 204,475.00

PEKERJAAN PLESTERAN

JENIS PEKERJAAN A,4,4,2,1 : 1 m2 Pekerjaan Plesteran (MU 301 &MU 201)


A TENAGA
1 Pekerja L01 OH 0.200 Rp 82,500.00 Rp 16,500.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 33,425.00
B BAHAN
1 Semen instann MU - 301 (plesteran bata ringan) kg 19.231 Rp 1,875.00 Rp 36,058.13
JUMLAH HARGA BAHAN Rp 36,058.13
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 69,483.13

JENIS PEKERJAAN A,4,4,2,1 : 1 m2 Pekerjaan Aci (MU 301 &MU 201)


A TENAGA
1 Pekerja L01 OH 0.200 Rp 82,500.00 Rp 16,500.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 33,425.00
B BAHAN
1 Semen instann MU - 301 (plesteran bata ringan) @40 kg/zak kg 2.000 Rp 3,166.67 Rp 6,333.33
JUMLAH HARGA BAHAN Rp 6,333.33
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 39,758.33

JENIS PEKERJAAN : 1 m1 Plesteran dan acian 1Pc : 3Ps


A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 semen zak 7.776 Rp 1,250.00 Rp 9,720.00
2 pasir pasang m3 0.023 Rp 200,000.00 Rp 4,600.00
JUMLAH HARGA BAHAN Rp 14,320.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 56,545.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN : 1 m1 Plesteran dan acian 1Pc : 5Ps
A TENAGA
1 Pekerja L01 OH 0.300 Rp 82,500.00 Rp 24,750.00
2 Tukang Batu L02 OH 0.150 Rp 95,000.00 Rp 14,250.00
3 Kepala Tukang L03 OH 0.015 Rp 105,000.00 Rp 1,575.00
4 Mandor L04 OH 0.015 Rp 110,000.00 Rp 1,650.00
JUMLAH HARGA TENAGA Rp 42,225.00
B BAHAN
1 semen zak 5.184 Rp 1,250.00 Rp 6,480.00
2 pasir pasang m3 0.026 Rp 200,000.00 Rp 5,200.00
JUMLAH HARGA BAHAN Rp 11,680.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 53,905.00

JENIS PEKERJAAN : 1 m1 Benangan atau Tali Air


A TENAGA
1 Pekerja L01 OH 0.075 Rp 82,500.00 Rp 6,187.50
2 Tukang Batu L02 OH 0.050 Rp 95,000.00 Rp 4,750.00
3 Kepala Tukang L03 OH 0.005 Rp 105,000.00 Rp 525.00
4 Mandor L04 OH 0.004 Rp 110,000.00 Rp 440.00
JUMLAH HARGA TENAGA Rp 11,902.50
B BAHAN
1 semen zak 0.013 Rp 65,625.00 Rp 853.13
2 pasir pasang m3 0.013 Rp 200,000.00 Rp 2,600.00
JUMLAH HARGA BAHAN Rp 3,453.13
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 15,355.63

JENIS PEKERJAAN : 1 m1 dinding partisi gypsum


A TENAGA
1 Pekerja L01 OH 0.159 Rp 82,500.00 Rp 13,117.50
2 Tukang Batu L02 OH 0.400 Rp 95,000.00 Rp 38,000.00
3 Kepala Tukang L03 OH 0.115 Rp 105,000.00 Rp 12,075.00
4 Mandor L04 OH 0.084 Rp 110,000.00 Rp 9,240.00
JUMLAH HARGA TENAGA Rp 72,432.50
B BAHAN
1 Hollow metal stud 40x40 mm m' 3.000 Rp 15,000.00 Rp 45,000.00
2 Hollow metal stud 20x40 mm m' 3.000 Rp 12,500.00 Rp 37,500.00
3 paku skrup biji 45.000 Rp 500.00 Rp 22,500.00
4 gypsumboard 12 mm lbr 0.715 Rp 100,000.00 Rp 71,500.00
5 perban gypsum rool 0.150 Rp 22,500.00 Rp 3,375.00
6 compone kg 0.250 Rp 25,000.00 Rp 6,250.00
7 alat bantu ls 1.000 Rp 5,000.00 Rp 5,000.00
JUMLAH HARGA BAHAN Rp 191,125.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 263,557.50


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN : 1 m1 dinding partisi kalsiboard


A TENAGA
1 Pekerja L01 OH 0.159 Rp 82,500.00 Rp 13,117.50
2 Tukang Batu L02 OH 0.400 Rp 95,000.00 Rp 38,000.00
3 Kepala Tukang L03 OH 0.115 Rp 105,000.00 Rp 12,075.00
4 Mandor L04 OH 0.084 Rp 110,000.00 Rp 9,240.00
JUMLAH HARGA TENAGA Rp 72,432.50
B BAHAN
1 Hollow metal stud 40x40 mm m' 3.000 Rp 15,000.00 Rp 45,000.00
2 Hollow metal stud 20x40 mm m' 3.000 Rp 12,500.00 Rp 37,500.00
3 paku skrup biji 45.000 Rp 500.00 Rp 22,500.00
4 kalsiboard 8 mm lbr 0.715 Rp 150,000.00 Rp 107,250.00
6 compone kg 0.250 Rp 25,000.00 Rp 6,250.00
7 alat bantu ls 1.000 Rp 5,000.00 Rp 5,000.00
JUMLAH HARGA BAHAN Rp 223,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 295,932.50

JENIS PEKERJAAN : 1 m1 dinding cover kalsiboard


A TENAGA
1 Pekerja L01 OH 0.159 Rp 82,500.00 Rp 13,117.50
2 Tukang Batu L02 OH 0.400 Rp 95,000.00 Rp 38,000.00
3 Kepala Tukang L03 OH 0.115 Rp 105,000.00 Rp 12,075.00
4 Mandor L04 OH 0.084 Rp 110,000.00 Rp 9,240.00
JUMLAH HARGA TENAGA Rp 72,432.50
B BAHAN
1 Hollow metal stud 40x40 mm m' 3.000 Rp 15,000.00 Rp 45,000.00
2 Hollow metal stud 20x40 mm m' 3.000 Rp 12,500.00 Rp 37,500.00
3 paku skrup biji 45.000 Rp 500.00 Rp 22,500.00
4 kalsiboard 8 mm lbr 0.350 Rp 150,000.00 Rp 52,500.00
6 compone kg 0.250 Rp 25,000.00 Rp 6,250.00
7 alat bantu ls 1.000 Rp 5,000.00 Rp 5,000.00
JUMLAH HARGA BAHAN Rp 168,750.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 241,182.50

PEKERJAAN PLAFOND

JENIS PEKERJAAN A,4,5,1,7 : 1 m2 Pemasangan Plafond Gypsum Board t. 9 mm


A TENAGA
1 Pekerja L01 OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Kayu L02 OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang L03 OH 0.050 Rp 105,000.00 Rp 5,250.00
4 Mandor L04 OH 0.025 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
1 gypsum board (uk.120x240x0.09 cm) Lmbr 0.364 Rp 60,000.00 Rp 21,840.00
2 Hollow Galvalum m 2.000 Rp 25,000.00 Rp 50,000.00
3 Gantungan m 2.000 Rp 5,000.00 Rp 10,000.00
4 paku Ramset + misiu bh 4.000 Rp 2,000.00 Rp 8,000.00
5 joint tape @75 m roll 0.143 Rp 18,000.00 Rp 2,572.20
6 Skrup bh 8.000 Rp 500.00 Rp 4,000.00
7 jointing coumpond kg 0.500 Rp 25,000.00 Rp 12,500.00
JUMLAH HARGA BAHAN Rp 108,912.20
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 136,562.20


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,4,5,1,7 : 1 m2 Pemasangan Plafond Kalsi Board t. 6 mm
A TENAGA
1 Pekerja L01 OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Kayu L02 OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang L03 OH 0.050 Rp 105,000.00 Rp 5,250.00
4 Mandor L04 OH 0.025 Rp 110,000.00 Rp 2,750.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
1 Kalsiboard 6 mm Lmbr 0.364 Rp 100,000.00 Rp 36,400.00
2 hollow galvalum kg 2.000 Rp 25,000.00 Rp 50,000.00
3 Gantungan m 2.000 Rp 5,000.00 Rp 10,000.00
4 paku Ramset + misiu bh 4.000 Rp 2,000.00 Rp 8,000.00
5 joint tape @75 m roll 0.143 Rp 18,000.00 Rp 2,572.20
6 Skrup bh 8.000 Rp 500.00 Rp 4,000.00
7 jointing coumpond kg 0.500 Rp 25,000.00 Rp 12,500.00
JUMLAH HARGA BAHAN Rp 123,472.20
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 151,122.20

JENIS PEKERJAAN A,4,5,1,9 : 1 m1 Pemasangan List Plafond Gypsum


A TENAGA
1 Pekerja L01 OH 0.050 Rp 82,500.00 Rp 4,125.00
2 Tukang Kayu L02 OH 0.050 Rp 114,000.00 Rp 5,700.00
3 Kepala Tukang L03 OH 0.005 Rp 105,000.00 Rp 525.00
4 Mandor L04 OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA Rp 10,680.00
B BAHAN
1 List Gypsumboard m1 1.050 Rp 15,000.00 Rp 15,750.00
2 Paku Gypsum kg 0.010 Rp 500.00 Rp 5.00
JUMLAH HARGA BAHAN Rp 15,755.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 26,435.00

JENIS PEKERJAAN : 1 m2 Floor Hardener


A TENAGA
1 Pekerja L01 OH 0.120 Rp 82,500.00 Rp 9,900.00
2 Tukang Batu L02 OH 0.120 Rp 114,000.00 Rp 13,680.00
3 Kepala Tukang L03 OH 0.012 Rp 105,000.00 Rp 1,260.00
4 Mandor L04 OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 25,500.00
B BAHAN
1 Floor Hardener kg 5.000 Rp 7,500.00 Rp 37,500.00
JUMLAH HARGA BAHAN Rp 37,500.00
C PERALATAN
1 Trowel hari 0.050 Rp 100,000.00 Rp 5,000.00
JUMLAH HARGA PERALATAN Rp 5,000.00

D Jumlah (A+B+C) Rp 68,000.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN : 1 m2 Pasangan Granit Lantai Uk.60x60cm
A TENAGA
1 Pekerja L01 OH 0.620 Rp 82,500.00 Rp 51,150.00
2 Tukang Batu L02 OH 0.350 Rp 114,000.00 Rp 39,900.00
3 Kepala Tukang L03 OH 0.035 Rp 105,000.00 Rp 3,675.00
4 Mandor L04 OH 0.030 Rp 110,000.00 Rp 3,300.00
JUMLAH HARGA TENAGA Rp 98,025.00
B BAHAN
1 Granit tile uk.60x60cm m2 1.050 Rp 275,000.00 Rp 288,750.00
2 semen kg 10.000 Rp 1,250.00 Rp 12,500.00
3 pasir pasang m3 0.018 Rp 200,000.00 Rp 3,600.00
4 semen warna kg 1.500 Rp 5,000.00 Rp 7,500.00
JUMLAH HARGA BAHAN Rp 312,350.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 410,375.00

JENIS PEKERJAAN A,4,4,3,54 : 1 m2 Pasangan keramik lantai Uk.40x40cm


A TENAGA
1 Pekerja L01 OH 0.620 Rp 82,500.00 Rp 51,150.00
2 Tukang Batu L02 OH 0.350 Rp 114,000.00 Rp 39,900.00
3 Kepala Tukang L03 OH 0.035 Rp 105,000.00 Rp 3,675.00
4 Mandor L04 OH 0.030 Rp 110,000.00 Rp 3,300.00
JUMLAH HARGA TENAGA Rp 98,025.00
B BAHAN
1 Keramik lantai Uk.40x40cm m2 1.050 Rp 65,000.00 Rp 68,250.00
2 semen kg 10.000 Rp 1,250.00 Rp 12,500.00
3 pasir pasang m3 0.018 Rp 200,000.00 Rp 3,600.00
4 semen warna kg 1.500 Rp 5,000.00 Rp 7,500.00
JUMLAH HARGA BAHAN Rp 91,850.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 189,875.00

JENIS PEKERJAAN A,4,4,3,35 : 1 m2 Pasangan Lantai Keramik Uk.20x20cm


A TENAGA
1 Pekerja L01 OH 0.700 Rp 82,500.00 Rp 57,750.00
2 Tukang Batu L02 OH 0.350 Rp 114,000.00 Rp 39,900.00
3 Kepala Tukang L03 OH 0.035 Rp 105,000.00 Rp 3,675.00
4 Mandor L04 OH 0.035 Rp 110,000.00 Rp 3,850.00
JUMLAH HARGA TENAGA Rp 105,175.00
B BAHAN
1 Keramik Uk.20x20cm m2 1.050 Rp 55,000.00 Rp 57,750.00
2 semen kg 10.000 Rp 1,250.00 Rp 12,500.00
3 pasir pasang m3 0.045 Rp 200,000.00 Rp 9,000.00
4 semen warna kg 1.100 Rp 5,000.00 Rp 5,500.00
JUMLAH HARGA BAHAN Rp 84,750.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 189,925.00

JENIS PEKERJAAN A,4,4,3,35 : 1 m2 Pasangan Lantai Keramik Uk.30x30cm


A TENAGA
1 Pekerja L01 OH 0.700 Rp 82,500.00 Rp 57,750.00
2 Tukang Batu L02 OH 0.350 Rp 114,000.00 Rp 39,900.00
3 Kepala Tukang L03 OH 0.035 Rp 105,000.00 Rp 3,675.00
4 Mandor L04 OH 0.035 Rp 110,000.00 Rp 3,850.00
JUMLAH HARGA TENAGA Rp 105,175.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
1 Keramik Uk.30x30cm m2 1.050 Rp 60,000.00 Rp 63,000.00
2 semen kg 10.000 Rp 1,250.00 Rp 12,500.00
3 pasir pasang m3 0.045 Rp 200,000.00 Rp 9,000.00
4 semen warna kg 1.100 Rp 5,000.00 Rp 5,500.00
JUMLAH HARGA BAHAN Rp 90,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 195,175.00

JENIS PEKERJAAN A,4,4,3,54 : 1 m2 Pasangan Dinding Keramik Uk.20x25cm


A TENAGA
1 Pekerja L01 OH 0.900 Rp 82,500.00 Rp 74,250.00
2 Tukang Batu L02 OH 0.450 Rp 114,000.00 Rp 51,300.00
3 Kepala Tukang L03 OH 0.045 Rp 105,000.00 Rp 4,725.00
4 Mandor L04 OH 0.045 Rp 110,000.00 Rp 4,950.00
JUMLAH HARGA TENAGA Rp 135,225.00
B BAHAN
1 Keramik Dinding Uk.25x50cm bh 8.000 Rp 12,500.00 Rp 100,000.00
2 semen kg 9.300 Rp 1,250.00 Rp 11,625.00
3 pasir pasang m3 0.018 Rp 200,000.00 Rp 3,600.00
4 semen warna kg 1.940 Rp 5,000.00 Rp 9,700.00
JUMLAH HARGA BAHAN Rp 124,925.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 260,150.00

JENIS PEKERJAAN A,4,4,3,54 : 1 m' Pekerjaan Pasang Plint Keramik 10X40 Cm


A TENAGA
1 Pekerja L01 OH 0.900 Rp 82,500.00 Rp 74,250.00
2 Tukang Batu L02 OH 0.450 Rp 114,000.00 Rp 51,300.00
3 Kepala Tukang L03 OH 0.045 Rp 105,000.00 Rp 4,725.00
4 Mandor L04 OH 0.045 Rp 110,000.00 Rp 4,950.00
JUMLAH HARGA TENAGA Rp 135,225.00
B BAHAN
1 Plint Keramik 10 x 40 Buah 2.500 Rp 15,000.00 Rp 37,500.00
2 semen kg 9.300 Rp 1,250.00 Rp 11,625.00
3 pasir pasang m3 0.003 Rp 200,000.00 Rp 600.00
4 semen warna Kg 0.190 Rp 5,000.00 Rp 950.00
JUMLAH HARGA BAHAN Rp 50,675.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 185,900.00

JENIS PEKERJAAN A,4,4,3,54 : 1 m' Pekerjaan Pasang Plint Keramik 10X60 Cm


A TENAGA
1 Pekerja L01 OH 0.900 Rp 82,500.00 Rp 74,250.00
2 Tukang Batu L02 OH 0.450 Rp 114,000.00 Rp 51,300.00
3 Kepala Tukang L03 OH 0.045 Rp 105,000.00 Rp 4,725.00
4 Mandor L04 OH 0.045 Rp 110,000.00 Rp 4,950.00
JUMLAH HARGA TENAGA Rp 135,225.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
B BAHAN
1 Plint Keramik 10 x 60 Buah 2.500 Rp 34,650.00 Rp 86,625.00
2 semen kg 9.300 Rp 1,250.00 Rp 11,625.00
3 pasir pasang m3 0.003 Rp 200,000.00 Rp 600.00
4 semen warna Kg 0.190 Rp 5,000.00 Rp 950.00
JUMLAH HARGA BAHAN Rp 99,800.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 235,025.00

PEKERJAAN PENGECATAN
JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Cat Tembok Interior
A TENAGA
1 Pekerja L01 OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Batu L02 OH 0.063 Rp 114,000.00 Rp 7,182.00
3 Kepala Tukang L03 OH 0.006 Rp 105,000.00 Rp 661.50
4 Mandor L04 OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA Rp 9,823.50
B BAHAN
1 plamir kg 0.100 Rp 25,000.00 Rp 2,500.00
2 cat dasar kg 0.100 Rp 40,000.00 Rp 4,000.00
3 cat penutup kg 0.260 Rp 60,000.00 Rp 15,600.00
JUMLAH HARGA BAHAN Rp 22,100.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 31,923.50

JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Cat Tembok Eksterior


A TENAGA
1 Pekerja L01 OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Batu L02 OH 0.063 Rp 114,000.00 Rp 7,182.00
3 Kepala Tukang L03 OH 0.006 Rp 105,000.00 Rp 661.50
4 Mandor L04 OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA Rp 9,823.50
B BAHAN
1 alkali kg 0.100 Rp 25,000.00 Rp 2,500.00
2 cat dasar kg 0.100 Rp 40,000.00 Rp 4,000.00
3 cat penutup kg 0.260 Rp 80,000.00 Rp 20,800.00
JUMLAH HARGA BAHAN Rp 27,300.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 37,123.50

JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Pekerjaan Pengecatan Epoxy Baja


A TENAGA
1 Pekerja OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Cat OH 0.200 Rp 114,000.00 Rp 22,800.00
3 Kepala Tukang OH 0.020 Rp 105,000.00 Rp 2,100.00
4 Mandor OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
1 Thinner Thinner B 1 Kg kg 0.125 Rp 25,000.00 Rp 3,125.00
2 Cat Epoxy kg 0.450 Rp 65,000.00 Rp 29,250.00
JUMLAH HARGA BAHAN Rp 32,375.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 60,025.00


per kg Rp 1,956.49
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Pekerjaan Pengecatan Permukaan Baja
A TENAGA
1 Pekerja OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Cat OH 0.200 Rp 114,000.00 Rp 22,800.00
3 Kepala Tukang OH 0.020 Rp 105,000.00 Rp 2,100.00
4 Mandor OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
2 Cat Besi anti karat kg 0.300 Rp 75,000.00 Rp 22,500.00
JUMLAH HARGA BAHAN Rp 22,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 50,150.00


per kg Rp 1,634.62

JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Pekerjaan Sandblasting baja


A TENAGA
1 Pekerja OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Cat OH 0.200 Rp 114,000.00 Rp 22,800.00
3 Kepala Tukang OH 0.020 Rp 105,000.00 Rp 2,100.00
4 Mandor OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
2 sandblasting baja kg 0.300 Rp 85,000.00 Rp 25,500.00
JUMLAH HARGA BAHAN Rp 25,500.00
C PERALATAN
Alat ( Compresor, semprot dll ) Ls 1.000 Rp 25,000.00 Rp 25,000.00
JUMLAH HARGA PERALATAN Rp 25,000.00

D Jumlah (A+B+C) Rp 78,150.00


per kg Rp 2,547.26

JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Pekerjaan Epoxy


A TENAGA
1 Pekerja OH 0.020 Rp 82,500.00 Rp 1,650.00
2 Tukang Cat OH 0.200 Rp 114,000.00 Rp 22,800.00
3 Kepala Tukang OH 0.020 Rp 105,000.00 Rp 2,100.00
4 Mandor OH 0.010 Rp 110,000.00 Rp 1,100.00
JUMLAH HARGA TENAGA Rp 27,650.00
B BAHAN
1 Cat epoxi dasar kg 0.150 Rp 200,000.00 Rp 30,000.00
2 Cat epoxi penutup kg 0.550 Rp 250,000.00 Rp 137,500.00
3 Roll Cat kg 0.016 Rp 25,000.00 Rp 400.00
4 Amplas kg 0.500 Rp 10,000.00 Rp 5,000.00
5 Kape kg 0.050 Rp 10,000.00 Rp 500.00
JUMLAH HARGA BAHAN Rp 173,400.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 201,050.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,4,7,1,10 : 1 m2 Pekerjaan Water Proofing
A TENAGA
1 Pekerja OH 0.200 Rp 82,500.00 Rp 16,500.00
2 Tukang Cat OH 0.600 Rp 114,000.00 Rp 68,400.00
JUMLAH HARGA TENAGA Rp 84,900.00
B BAHAN
1 Water Proofing Aquaprof kg 1.000 Rp 50,000.00 Rp 50,000.00
2 Kuas Kecil, 4" kg 0.250 Rp 10,000.00 Rp 2,500.00
JUMLAH HARGA BAHAN Rp 52,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 137,400.00

PEKERJAAN BESI DAN ALLUMINIUM

JENIS PEKERJAAN A,4,2,1,20 : 1 m2 Rangka Besi Hollow 1x40.40x2 mm


A TENAGA
1 Pekerja L01 OH 0.350 Rp 82,500.00 Rp 28,875.00
2 Tukang Besi L02 OH 0.350 Rp 114,000.00 Rp 39,900.00
3 Kepala Tukang L03 OH 0.035 Rp 105,000.00 Rp 3,675.00
4 Mandor L04 OH 0.018 Rp 110,000.00 Rp 1,980.00
JUMLAH HARGA TENAGA Rp 74,430.00
B BAHAN
1 Besi Hollow m1 4.000 Rp 35,000.00 Rp 140,000.00
2 Assesoris (Perkuatan, Las, dll) Ls 100% x rangka Rp 35,000.00 Rp 35,000.00
JUMLAH HARGA BAHAN Rp 175,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 249,430.00


Per kg Rp 17,261.59

PEKERJAAN SANITASI

JENIS PEKERJAAN A,5,1,1,1 : 1 Buah Closet Duduk


A TENAGA
1 Pekerja L01 OH 3.300 Rp 82,500.00 Rp 272,250.00
2 Tukang Batu L02 OH 1.100 Rp 114,000.00 Rp 125,400.00
3 Kepala Tukang L03 OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor L04 OH 0.160 Rp 110,000.00 Rp 17,600.00
JUMLAH HARGA TENAGA Rp 416,300.00
B BAHAN
1 Closet duduk unit 1.000 Rp 2,500,000.00 Rp 2,500,000.00
2 perlengkapan % 6.000 Rp 2,500,000.00 Rp 150,000.00
JUMLAH HARGA BAHAN Rp 2,650,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 3,066,300.00

JENIS PEKERJAAN A,5,1,1,1 : 1 Buah Closet jongkok


A TENAGA
1 Pekerja L01 OH 3.300 Rp 82,500.00 Rp 272,250.00
2 Tukang Batu L02 OH 1.100 Rp 114,000.00 Rp 125,400.00
3 Kepala Tukang L03 OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor L04 OH 0.160 Rp 110,000.00 Rp 17,600.00
JUMLAH HARGA TENAGA Rp 416,300.00
B BAHAN
1 Closet Jongkok unit 1.000 Rp 350,000.00 Rp 350,000.00
2 perlengkapan % 6.000 Rp 350,000.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 371,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 787,300.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

JENIS PEKERJAAN A,5,1,1,1 : 1 Buah Urinoir


A TENAGA
1 Pekerja L01 OH 3.300 Rp 82,500.00 Rp 272,250.00
2 Tukang Batu L02 OH 1.100 Rp 114,000.00 Rp 125,400.00
3 Kepala Tukang L03 OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor L04 OH 0.160 Rp 110,000.00 Rp 17,600.00
JUMLAH HARGA TENAGA Rp 416,300.00
B BAHAN
1 urinoir unit 1.000 Rp 2,850,000.00 Rp 2,850,000.00
2 perlengkapan % 6.000 Rp 2,850,000.00 Rp 171,000.00
JUMLAH HARGA BAHAN Rp 3,021,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 3,437,300.00

JENIS PEKERJAAN A,5,1,1,5 : 1 buah Wastafel


A TENAGA
1 Pekerja L01 OH 1.200 Rp 82,500.00 Rp 99,000.00
2 Tukang Batu L02 OH 1.450 Rp 114,000.00 Rp 165,300.00
3 Kepala Tukang L03 OH 0.150 Rp 105,000.00 Rp 15,750.00
4 Mandor L04 OH 0.060 Rp 110,000.00 Rp 6,600.00
JUMLAH HARGA TENAGA Rp 286,650.00
B BAHAN
1 wastafel unit 1.200 Rp 2,750,000.00 Rp 3,300,000.00
2 semen kg 6.000 Rp 1,250.00 Rp 7,500.00
3 pasir pasang m3 0.010 Rp 200,000.00 Rp 2,000.00
4 perlengkapan % 15.000 Rp 3,309,500.00 Rp 496,425.00
JUMLAH HARGA BAHAN Rp 3,805,925.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 4,092,575.00

JENIS PEKERJAAN A,5,1,1,14 : 1 buah Floor Drain


A TENAGA
1 Pekerja L01 OH 0.010 Rp 82,500.00 Rp 825.00
2 Tukang Batu L02 OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang L03 OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor L04 OH 0.005 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA Rp 13,825.00
B BAHAN
1 Floor Drain unit 1.000 Rp 325,000.00 Rp 325,000.00
JUMLAH HARGA BAHAN Rp 325,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 338,825.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,5,1,1,14 : 1 buah kran air
A TENAGA
1 Pekerja L01 OH 0.010 Rp 82,500.00 Rp 825.00
2 Tukang Batu L02 OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang L03 OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor L04 OH 0.005 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA Rp 13,825.00
B BAHAN
1 kran air unit 1.000 Rp 370,000.00 Rp 370,000.00
JUMLAH HARGA BAHAN Rp 370,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 383,825.00

JENIS PEKERJAAN : 1 buah jet Shower


A TENAGA
1 Pekerja L01 OH 0.010 Rp 82,500.00 Rp 825.00
2 Tukang Batu L02 OH 0.400 Rp 114,000.00 Rp 45,600.00
3 Kepala Tukang L03 OH 0.040 Rp 105,000.00 Rp 4,200.00
4 Mandor L04 OH 0.005 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA Rp 51,175.00
B BAHAN
1 jet shower m 1.000 Rp 450,000.00 Rp 450,000.00
2 sealtape bh 0.025 Rp 3,000.00 Rp 75.00
JUMLAH HARGA BAHAN Rp 450,075.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 501,250.00

JENIS PEKERJAAN : 1 M1 PEMASANGAN PIPA AIR KOTOR DIA. 4" KLAS AW


A TENAGA
1 Pekerja OH 0.034 Rp 82,500.00 Rp 2,780.25
2 Tukang Pipa OH 0.068 Rp 114,000.00 Rp 7,695.00
3 Kepala Tukang OH 0.040 Rp 105,000.00 Rp 4,200.00
4 Mandor OH 0.005 Rp 110,000.00 Rp 550.00
JUMLAH HARGA TENAGA Rp 15,225.25
B BAHAN
1 Pipa PVC dia. 4" m' 1.025 Rp 81,250.00 Rp 83,281.25
2 Lem PVC bh 1.000 Rp 10,000.00 Rp 10,000.00
JUMLAH HARGA BAHAN Rp 93,281.25
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 108,506.50


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
PEKERJAAN PAVING

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m2 Paving (K - 500)


A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Batu OH 0.150 Rp 114,000.00 Rp 17,100.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.003 Rp 110,000.00 Rp 330.00
JUMLAH HARGA TENAGA Rp 26,730.00
B BAHAN
1 Paving (K - 500) m2 1.050 Rp 110,000.00 Rp 115,500.00
2 Pasir Urug m3 0.025 Rp 150,000.00 Rp 3,750.00
JUMLAH HARGA BAHAN Rp 119,250.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 145,980.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m1 Kansten


A TENAGA
1 Pekerja OH 0.200 Rp 82,500.00 Rp 16,500.00
2 Tukang Batu OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.001 Rp 110,000.00 Rp 110.00
JUMLAH HARGA TENAGA Rp 29,060.00
B BAHAN
1 Kansten bh 2.000 Rp 50,000.00 Rp 100,000.00
2 Semen zak 0.100 Rp 1,250.00 Rp 125.00
3 Pasir Pasang m3 0.001 Rp 200,000.00 Rp 200.00
JUMLAH HARGA BAHAN Rp 100,325.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 129,385.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m2 penutup atap polycarbonat


A TENAGA
1 Pekerja OH 0.075 Rp 82,500.00 Rp 6,187.50
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 19,297.50
B BAHAN
1 Atap polycarbonat m2 1.100 Rp 175,000.00 Rp 192,500.00
3 Roof Seal m2 1.000 Rp 25,000.00 Rp 25,000.00
JUMLAH HARGA BAHAN Rp 217,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 236,797.50


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m2 Atap Kliplok Zincalume
A TENAGA
1 Pekerja OH 0.075 Rp 82,500.00 Rp 6,187.50
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 19,297.50
B BAHAN
1 Atap kliplok Zincalume 0,5 mm m2 1.100 Rp 165,000.00 Rp 181,500.00
2 Screw Cteks 12-4 x 50 Bh 6.000 Rp 3,500.00 Rp 21,000.00
3 Screw Cteks 10x16 - 16 Bh 2.000 Rp 3,000.00 Rp 6,000.00
JUMLAH HARGA BAHAN Rp 208,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 227,797.50

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan Cladding select SEAM III 0.55 BMT colourbond
A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 21,360.00
B BAHAN
1 Cladding select SEAM III 0.55 BMT colourbond m2 1.100 Rp 350,000.00 Rp 385,000.00
2 Screw Bh 6.000 Rp 3,500.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 406,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 427,360.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan Clading trimdek


A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 21,360.00
B BAHAN
1 Clading trimdek m2 1.100 Rp 165,000.00 Rp 181,500.00
2 Screw Bh 6.000 Rp 3,500.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 202,500.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 223,860.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m1 Nok Zincalume


A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 21,360.00
B BAHAN
1 Nok Zincalume 0,35 mm m1 1.100 Rp 150,000.00 Rp 165,000.00
2 Screw Cteks 10x16 - 16 Bh 6.000 Rp 3,500.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 186,000.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 207,360.00


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m1 Capping flashing
A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang Atap OH 0.100 Rp 114,000.00 Rp 11,400.00
3 Kepala Tukang OH 0.010 Rp 105,000.00 Rp 1,050.00
4 Mandor OH 0.006 Rp 110,000.00 Rp 660.00
JUMLAH HARGA TENAGA Rp 21,360.00
B BAHAN
1 Capping flashing m1 1.100 Rp 152,500.00 Rp 167,750.00
2 Screw Bh 6.000 Rp 3,500.00 Rp 21,000.00
JUMLAH HARGA BAHAN Rp 188,750.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 210,110.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan 1 m2 atap insulasi


A TENAGA
1 Pekerja OH 0.100 Rp 82,500.00 Rp 8,250.00
2 Tukang besi OH 0.150 Rp 114,000.00 Rp 17,100.00
3 Kepala Tukang OH 0.015 Rp 130,000.00 Rp 1,950.00
4 Mandor OH 0.001 Rp 135,000.00 Rp 135.00
JUMLAH HARGA TENAGA Rp 27,435.00
B BAHAN
1 Zeltech insulasi m2 1.050 Rp 75,000.00 Rp 78,750.00
JUMLAH HARGA BAHAN Rp 78,750.00
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 106,185.00

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan talang datar galvalum


A TENAGA
1 Pekerja OH 0.200 Rp 82,500.00 Rp 16,500.00
2 Tukang besi OH 0.300 Rp 114,000.00 Rp 34,200.00
3 Kepala Tukang OH 0.030 Rp 130,000.00 Rp 3,900.00
4 Mandor OH 0.010 Rp 135,000.00 Rp 1,350.00
JUMLAH HARGA TENAGA Rp 55,950.00
B BAHAN
1 Seng plat lbr 1.050 Rp 150,000.00 Rp 157,500.00
2 Paku kg 0.015 Rp 17,500.00 Rp 262.50
3 Kayu papan m3 0.019 Rp 3,000,000.00 Rp 57,000.00
JUMLAH HARGA BAHAN Rp 214,762.50
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)
C PERALATAN
JUMLAH HARGA PERALATAN Rp -

D Jumlah (A+B+C) Rp 270,712.50

JENIS PEKERJAAN A,4,6,2,17 : Pemasangan Lapisan ATB (Asphalt Treated Base)


A TENAGA
1 Pekerja OH 0.025 Rp 82,500.00 Rp 2,062.50
2 Tukang Batu OH 0.150 Rp 114,000.00 Rp 17,100.00
3 Kepala Tukang OH 0.010 Rp 130,000.00 Rp 1,300.00
4 Mandor OH 0.003 Rp 135,000.00 Rp 405.00
JUMLAH HARGA TENAGA Rp 20,867.50
B BAHAN
1 Agregat Halus m2 0.703 Rp 175,000.00 Rp 122,990.00
2 Agregat Kasar m3 0.534 Rp 170,000.00 Rp 90,797.00
3 Filter kg 139.200 Rp 1,350.00 Rp 187,920.00
4 Aspal Curah kg 157.000 Rp 7,500.00 Rp 1,177,500.00
JUMLAH HARGA BAHAN Rp 1,579,207.00

C PERALATAN
Aspatt Mixing Plant jam 0.061 Rp 3,800,000.00 Rp 232,940.00
Sewa Wheel Leader 10-15 HP jam 0.042 Rp 482,502.00 Rp 20,313.33
Sewa Dump Truck 8-10 m3 jam 0.543 Rp 65,000.00 Rp 35,288.50
Sewa Asphatt Finisher jam 0.077 Rp 856,725.00 Rp 65,710.81
Sewa Todem Roller jam 0.048 Rp 223,436.00 Rp 10,635.55
Sewa Tire Roller jam 0.036 Rp 226,360.00 Rp 8,058.42
Sewa Alat Bantu jam 1.000 Rp 1,000.00 Rp 1,000.00
JUMLAH HARGA PERALATAN Rp 373,946.61

D Jumlah (A+B+C) Rp 1,974,021.11

Jenis Pekerjaan : Pemasangan Box Culvert 1500 x 1500


A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
Box Culvert 1500 x 1500 bh 1.000 Rp 9,000,000.00 Rp 9,000,000.00
Pembersihan lahan ls 1.000 Rp 200,000.00 Rp 200,000.00
Galian tanah m3 3.375 Rp 64,625.00 Rp 218,109.38
Pemadatan tanah m3 1.200 Rp 49,150.00 Rp 58,980.00
Bedding pasir tb. 10 cm m3 0.225 Rp 205,850.00 Rp 46,316.25
Penempatan & penyetelan Box Culvert bh 1.000 Rp 450,000.00 Rp 450,000.00
Urugan tanah kembali sisi Box Culvert m3 1.200 Rp 55,550.00 Rp 66,660.00
Pemadatan tanah sisi Box Culvert m3 1.200 Rp 49,150.00 Rp 58,980.00
JUMLAH HARGA BAHAN Rp 10,099,045.63
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 10,099,045.63

Jenis Pekerjaan : Pemasangan U-Ditch Uk.60x60x120 + Cover


A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
U-Ditch Uk. 60x60x120 + Cover bh 1.000 Rp 1,430,000.00 Rp 1,430,000.00
Pembersihan lahan ls 1.000 Rp 150,000.00 Rp 150,000.00
Galian tanah m3 1.500 Rp 64,625.00 Rp 96,937.50
Pemadatan tanah m3 0.450 Rp 49,150.00 Rp 22,117.50
Bedding pasir tb. 10 cm m3 0.072 Rp 205,850.00 Rp 14,821.20
Penempatan & penyetelan U-Ditch + Cover bh 1.000 Rp 450,000.00 Rp 450,000.00
Urugan tanah kembali sisi U-Ditch m3 0.450 Rp 55,550.00 Rp 24,997.50
Pemadatan tanah sisi U-Ditch m3 0.450 Rp 49,150.00 Rp 22,117.50
JUMLAH HARGA BAHAN Rp 2,210,991.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,210,991.20
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


A PEKERJAAN PERSIAPAN
1 Pembersihan m2 5,583.39 Rp 13,750.00 Rp 76,771,612.50
2 Pagar Sementara m1 420.57 Rp 372,700.00 Rp 156,746,439.00
3 Egalisasi / Bouwplank m1 413.57 Rp 73,700.00 Rp 30,480,109.00
4 Air kerja dan listrik kerja Ls 1.00 Rp 50,000,000.00 Rp 50,000,000.00
5 Direksi keet & Gudang m2 78.00 Rp 1,333,650.00 Rp 104,024,700.00
6 Km / Wc darurat pekerja Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
7 Mob - demob Ls 1.00 Rp 50,000,000.00 Rp 50,000,000.00
8 Shop drawing & Asbuild drawing Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
9 K3 Ls 1.00 Rp 10,000,000.00 Rp 10,000,000.00

SUB TOTAL PEKERJAAN A Rp 490,522,860.50

B BANGUNAN OFFICE (AS. 1 - 3)


B-I PEKERJAAN TANAH
1 Galian tanah m3 4.45 Rp 64,625.00 Rp 287,581.25
2 Urug kembali m3 2.22 Rp 55,550.00 Rp 123,321.00
3 Buang tanah m3 0.44 Rp 37,125.00 Rp 16,335.00
4 Urugan Sirtu + Pemadatan m3 200.97 Rp 72,525.00 Rp 14,575,349.25

SUB TOTAL PEKERJAAN B-I Rp 15,002,586.50

B - II PEKERJAAN PONDASI
1 Mob- Demobilisasi Ls 1.00 Rp 45,000,000.00 Rp 45,000,000.00
2 Supply Tiang Pancang 250x250 mm m' 786.00 Rp 160,000.00 Rp 125,760,000.00
3 Pemancangan m' 786.00 Rp 75,000.00 Rp 58,950,000.00
4 Potong Kepala tiang titik 57.00 Rp 100,000.00 Rp 5,700,000.00

SUB TOTAL PEKERJAAN B-II Rp 235,410,000.00

B - III PEKERJAAN BETON


LANTAI 1 ( -0.50 )
I PILE CAP
1 PC-1B
- Lantai kerja B0 m3 0.11 Rp 766,272.62 Rp 84,289.99
- Beton f'c 25 m3 1.36 Rp 1,006,085.48 Rp 1,368,276.25
- Besi U - 24 kg 14.06 Rp 13,510.00 Rp 189,950.60
- Besi U - 40 kg 359.78 Rp 13,510.00 Rp 4,860,627.80
- Bekisting Bataco m2 8.64 Rp 133,200.00 Rp 1,150,848.00

2 PC-2
- Lantai kerja B0 m3 0.23 Rp 766,272.62 Rp 176,242.70
- Beton f'c 25 m3 2.95 Rp 1,006,085.48 Rp 2,967,952.15
- Besi U - 24 kg 9.62 Rp 13,510.00 Rp 129,966.20
- Besi U - 40 kg 2,411.19 Rp 13,510.00 Rp 32,575,176.90
- Bekisting Bataco m2 13.68 Rp 133,200.00 Rp 1,822,176.00

II SLOOF
1 SL-40
- Lantai kerja B0 m3 0.04 Rp 766,272.62 Rp 30,650.90
- Beton f'c 25 m3 0.37 Rp 1,006,085.48 Rp 372,251.63
- Besi U - 24 kg 42.30 Rp 13,510.00 Rp 571,473.00
- Besi U - 40 kg 33.57 Rp 13,510.00 Rp 453,530.70
- Bekisting Bataco m2 3.50 Rp 133,200.00 Rp 466,200.00
2 SL-55A
- Lantai kerja B0 m3 0.97 Rp 766,272.62 Rp 743,284.44
- Beton f'c 25 m3 11.17 Rp 1,006,085.48 Rp 11,237,974.77
- Besi U - 24 kg 567.80 Rp 13,510.00 Rp 7,670,978.00
- Besi U - 40 kg 824.89 Rp 13,510.00 Rp 11,144,263.90
- Bekisting Bataco m2 38.69 Rp 133,200.00 Rp 5,153,508.00
3 SL-60A
- Lantai kerja B0 m3 0.57 Rp 766,272.62 Rp 436,775.39
- Beton f'c 25 m3 7.24 Rp 1,006,085.48 Rp 7,284,058.85
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


- Besi U - 24 kg 314.33 Rp 13,510.00 Rp 4,246,598.30
- Besi U - 40 kg 767.53 Rp 13,510.00 Rp 10,369,330.30
- Bekisting Bataco m2 23.00 Rp 133,200.00 Rp 3,063,600.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


4 SL-60B
- Lantai kerja B0 m3 0.27 Rp 766,272.62 Rp 206,893.61
- Beton f'c 25 m3 3.10 Rp 1,006,085.48 Rp 3,118,864.98
- Besi U - 24 kg 141.09 Rp 13,510.00 Rp 1,906,125.90
- Besi U - 40 kg 384.78 Rp 13,510.00 Rp 5,198,377.80
- Bekisting Bataco m2 10.32 Rp 133,200.00 Rp 1,374,624.00
5 SL-105A
- Lantai kerja B0 m3 0.68 Rp 766,272.62 Rp 521,065.38
- Beton f'c 25 m3 13.55 Rp 1,006,085.48 Rp 13,632,458.20
- Besi U - 24 kg 519.73 Rp 13,510.00 Rp 7,021,552.30
- Besi U - 40 kg 715.48 Rp 13,510.00 Rp 9,666,134.80
- Bekisting Bataco m2 25.80 Rp 133,200.00 Rp 3,436,560.00

III PLAT LANTAI


PLAT LANTAI S1 (-0.05M)
- Lantai kerja Bo m3 11.82 Rp 766,272.62 Rp 9,057,342.36
- Beton f'c 25 m3 29.79 Rp 1,006,085.48 Rp 29,971,286.34
- Besi U - 40 kg 6,222.48 Rp 13,510.00 Rp 84,065,704.80
- Bekisting multiplek 12 mm m2 9.30 Rp 414,645.00 Rp 3,856,198.50

PLAT LANTAI S1 (+4,25M)


- Beton f'c 25 m3 29.79 Rp 1,006,085.48 Rp 29,971,286.34
- Besi U - 40 kg 6,222.48 Rp 13,510.00 Rp 84,065,704.80
- Shear connector kg 979.60 Rp 45,000.00 Rp 44,082,000.00
- Bekisting multiplek 9 mm ( expose ) m2 245.69 Rp 405,895.00 Rp 99,724,342.55

VI KOLOM
1 KOLOM K-450
- Beton f'c 25 m3 1.70 Rp 1,006,085.48 Rp 1,710,345.31
- Besi U - 40 kg 530.46 Rp 13,510.00 Rp 7,166,514.60
- Bekisting multiplek 12 mm ( expose ) m2 18.00 Rp 354,678.00 Rp 6,384,204.00

2 KOLOM K-500
- Beton f'c 25 m3 0.38 Rp 1,006,085.48 Rp 382,312.48
- Besi U - 40 kg 130.28 Rp 13,510.00 Rp 1,760,082.80
- Bekisting multiplek 12 mm ( expose ) m2 3.84 Rp 354,678.00 Rp 1,361,963.52
LANTAI 2 (+ 4,35 M)

V TANGGA
- Beton f'c 25 m3 2.77 Rp 1,006,085.48 Rp 2,786,856.77
- Besi U - 24 kg 250.98 Rp 13,510.00 Rp 3,390,739.80
- Besi U - 40 kg 209.98 Rp 13,510.00 Rp 2,836,829.80
- Bekisting multiplek 12 mm ( expose ) m2 19.68 Rp 323,145.00 Rp 6,359,493.60

SUB TOTAL PEKERJAAN B-III Rp 573,585,850.10

B - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 400.200.8.13 kg 536.58 Rp 24,845.00 Rp 13,331,330.10
- Kolom WF 350.175.7.11 kg 3,942.87 Rp 24,845.00 Rp 97,960,605.15
- Kolom WF 200.100.5,5.8 kg 1,457.69 Rp 24,845.00 Rp 36,216,308.05
2 RANGKA KUDA-KUDA
- Rafter + Voute WF 250.125.6.9 kg 2,121.84 Rp 24,845.00 Rp 52,717,114.80
- Konsol + Voute WF 200.100.5,5.8 kg 147.92 Rp 24,845.00 Rp 3,675,072.40
3 Balok
- Balok Castela 525.175.7.11 kg 1,019.28 Rp 24,845.00 Rp 25,324,011.60
- Balok Castela 450.150.6,5.9 kg 2,091.53 Rp 24,845.00 Rp 51,964,062.85
- Balok WF 350.175.7.11 kg 2,774.19 Rp 24,845.00 Rp 68,924,750.55
- Balok WF 300.150.6,5.9 kg 427.17 Rp 24,845.00 Rp 10,613,038.65
- Balok WF 250.125.6.9 kg 1,518.36 Rp 24,845.00 Rp 37,723,654.20
- WF 200.100.5,5.8 kg 610.99 Rp 24,845.00 Rp 15,180,046.55
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg 1,075.20 Rp 24,405.00 Rp 26,240,256.00
5 Gording C 150.65.20.2,3 kg 1,386.00 Rp 24,130.00 Rp 33,444,180.00
6 Rangka Cladding C 150.65.20.2,3 kg 1,873.62 Rp 24,130.00 Rp 45,210,450.60
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


7 Rangka Listplank C 100.50.20.2,3 kg 738.34 Rp 24,130.00 Rp 17,816,144.20
8 Rangka Listplank C 75.45.20.2,3 kg 436.29 Rp 24,130.00 Rp 10,527,677.70
9 Bracing Kolom L 60.60.6 kg 2,304.32 Rp 23,915.00 Rp 55,107,812.80
10 Penggantung Talang L 40.40.4 kg 1,016.40 Rp 23,915.00 Rp 24,307,206.00
11 Penggantung Talang Datar Plat Strip 40.4 kg 42.90 Rp 24,730.00 Rp 1,060,917.00
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg 25.26 Rp 24,730.00 Rp 624,679.80
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


13 Plat baja t= 15 mm kg 350.00 Rp 24,730.00 Rp 8,655,500.00
14 Plat baja t= 12 mm kg 280.00 Rp 24,730.00 Rp 6,924,400.00
15 Plat baja t= 10 mm kg 233.30 Rp 24,730.00 Rp 5,769,509.00
16 Plat baja t= 8 mm kg 187.00 Rp 24,730.00 Rp 4,624,510.00
17 Plat baja t= 6 mm kg 140.00 Rp 24,730.00 Rp 3,462,200.00
18 Angkur Æ 19 mm ; L= 760 - U-50 bh 48.00 Rp 45,000.00 Rp 2,160,000.00
19 Angkur Æ 16 mm ; L= 760 - U-40 bh 4.00 Rp 40,000.00 Rp 160,000.00
20 Murbaut Æ 12 mm bh 120.00 Rp 7,500.00 Rp 900,000.00
21 Murbaut Æ 16 mm - A325 bh 57.00 Rp 12,500.00 Rp 712,500.00
22 Murbaut Æ 19 mm - A325 bh 294.00 Rp 15,000.00 Rp 4,410,000.00
23 Murbaut Æ 22 mm - A325 bh 340.00 Rp 17,500.00 Rp 5,950,000.00
24 Trekstang Æ 12 mm bh 60.00 Rp 22,500.00 Rp 1,350,000.00
25 Ikatan angin Æ 16 mm bh 6.00 Rp 250,000.00 Rp 1,500,000.00
26 Jarum keras Æ 16 mm bh 12.00 Rp 25,000.00 Rp 300,000.00
27 Pekerjaan Tangga
- Balok WF 350.175.7.11 Kg 338.26 Rp 24,845.00 Rp 8,404,007.59
- WF 200.100.5,5.8 Kg 457.30 Rp 24,845.00 Rp 11,361,651.63
- Siku 40.40.4 Kg 14.52 Rp 23,915.00 Rp 347,245.80
- Plat Bordes 3,2 mm Kg 118.41 Rp 24,730.00 Rp 2,928,364.42
- Pipa Hitam 2 " Kg 182.24 Rp 24,730.00 Rp 4,506,795.20
- Plat t=12 mm Kg 5.93 Rp 24,730.00 Rp 146,738.07
- Plat t=6 mm Kg 2.97 Rp 24,730.00 Rp 73,369.03
28 Sandblasting - Standart SA 2.5 kg 27,856.68 Rp 2,547.26 Rp 70,958,270.92
29 Cat baja Epoxy t=150 mikron kg 27,856.68 Rp 1,956.49 Rp 54,501,218.32

SUB TOTAL PEKERJAAN B - IV Rp 828,075,598.98

SUB TOTAL PEKERJAAN B Rp 1,652,074,035.58

C BANGUNAN GUDANG BAHAN BAKU (AS. 3 - 13)


C-I PEKERJAAN TANAH
1 Galian tanah m3 5.62 Rp 64,625.00 Rp 363,192.50
2 Urug kembali m3 2.81 Rp 55,550.00 Rp 156,095.50
3 Buang tanah m3 0.56 Rp 37,125.00 Rp 20,790.00
4 Urugan Sirtu + Pemadatan m3 1,332.85 Rp 72,525.00 Rp 96,664,946.25

SUB TOTAL PEKERJAAN C-I Rp 97,205,024.25

C - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 632.00 Rp 160,000.00 Rp 101,120,000.00
2 Pemancangan m' 632.00 Rp 75,000.00 Rp 47,400,000.00
3 Potong Kepala tiang titik 48.00 Rp 100,000.00 Rp 4,800,000.00

SUB TOTAL PEKERJAAN C-II Rp 153,320,000.00

C - III PEKERJAAN BETON


I PILE CAP
1 PC-1B
- Lantai kerja B0 m3 0.43 Rp 766,272.62 Rp 329,497.23
- Beton f'c 25 m3 5.44 Rp 1,006,085.48 Rp 5,473,104.99
- Besi U - 24 kg 56.24 Rp 13,510.00 Rp 759,802.40
- Besi U - 40 kg 1,439.12 Rp 13,510.00 Rp 19,442,511.20
- Bekisting Bataco m2 34.56 Rp 133,200.00 Rp 4,603,392.00

II RETAINING WALL
1 RETAINING WALL 8
- Lantai kerja B0 m3 1.89 Rp 766,272.62 Rp 1,448,255.25
- Beton f'c 25 m3 11.78 Rp 1,006,085.48 Rp 11,851,686.91
- Besi U - 40 kg 1,134.03 Rp 13,510.00 Rp 15,320,745.30
- Bekisting multiplek 12 mm ( expose ) m2 141.09 Rp 351,495.00 Rp 49,592,429.55

III SLOOF
1 SL-40 A
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


- Lantai kerja B0 m3 0.71 Rp 766,272.62 Rp 544,053.56
- Beton f'c 25 m3 5.99 Rp 1,006,085.48 Rp 6,026,452.00
- Besi U - 40 kg 625.37 Rp 13,510.00 Rp 8,448,748.70
- Bekisting Bataco m2 57.00 Rp 133,200.00 Rp 7,592,400.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


2 SL-50 A
- Lantai kerja B0 m3 0.39 Rp 766,272.62 Rp 298,846.32
- Beton f'c 25 m3 4.54 Rp 1,006,085.48 Rp 4,567,628.06
- Besi U - 40 kg 786.37 Rp 13,510.00 Rp 10,623,858.70
- Bekisting Bataco m2 15.71 Rp 133,200.00 Rp 2,092,572.00
3 SL-50 B
- Lantai kerja B0 m3 0.88 Rp 766,272.62 Rp 674,319.90
- Beton f'c 25 m3 9.23 Rp 1,006,085.48 Rp 9,286,168.95
- Besi U - 40 kg 1,399.61 Rp 13,510.00 Rp 18,908,731.10
- Bekisting Bataco m2 35.15 Rp 133,200.00 Rp 4,681,980.00

III PLAT LANTAI


PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3 67.79 Rp 766,272.62 Rp 51,945,620.85
- Beton f'c 25 m3 170.82 Rp 1,006,085.48 Rp 171,859,521.04
- Besi U - 40 kg 8,740.20 Rp 13,510.00 Rp 118,080,102.00
- Bekisting multiplek 12 mm ( expose ) m2 29.39 Rp 414,645.00 Rp 12,186,416.55

IV KOLOM
1 KOLOM K-450
- Beton f'c 25 m3 3.40 Rp 1,006,085.48 Rp 3,420,690.62
- Besi U - 40 kg 530.46 Rp 13,510.00 Rp 7,166,514.60
- Bekisting multiplek 12 mm ( expose ) m2 36.00 Rp 354,678.00 Rp 12,768,408.00
SUB TOTAL PEKERJAAN C-III Rp 559,994,457.78

C - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 350.175.7.11 kg 9,725.77 Rp 24,845.00 Rp 241,636,755.65
- Kolom WF 300.150.6,5.9 kg 447.15 Rp 24,845.00 Rp 11,109,441.75
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 (WF 300.150.6,5.9) kg - Rp 24,845.00 Rp -
- Voute WF 300.150.6,5.9 kg - Rp 24,845.00 Rp -
- Rafter WF 250.125.6.9 kg 147.92 Rp 24,845.00 Rp 3,675,072.40
- Voute WF 250.125.6.9 kg 504.40 Rp 24,845.00 Rp 12,531,818.00
- Rafter WF 200.100.5,5.8 kg 512.00 Rp 24,845.00 Rp 12,720,640.00
- Voute WF 200.100.5,5.8 kg 256.00 Rp 24,845.00 Rp 6,360,320.00
3 Tiebeam WF 200.100.5,5.8 kg 5,120.00 Rp 24,845.00 Rp 127,206,400.00
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg 465.18 Rp 24,405.00 Rp 11,352,717.90
5 Gording C 150.65.20.2,3 kg 7,630.46 Rp 24,130.00 Rp 184,122,999.80
6 Rangka Cladding C 150.65.20.2,3 kg 4,349.42 Rp 24,130.00 Rp 104,951,504.60
7 Rangka Listplank C 100.50.20.2,3 kg 2,150.93 Rp 24,130.00 Rp 51,901,940.90
9 Bracing Kolom L 60.60.6 kg 865.03 Rp 23,915.00 Rp 20,687,192.45
10 Penggantung Talang L 40.40.4 kg 222.64 Rp 23,915.00 Rp 5,324,435.60
11 Penggantung Talang Datar Plat Strip 40.4 kg 205.63 Rp 24,730.00 Rp 5,085,229.90
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg 38.22 Rp 24,730.00 Rp 945,180.60
14 Plat baja t= 12 mm kg 186.10 Rp 24,730.00 Rp 4,602,253.00
15 Plat baja t= 10 mm kg 741.94 Rp 24,730.00 Rp 18,348,176.20
16 Plat baja t= 8 mm kg 415.56 Rp 24,730.00 Rp 10,276,798.80
17 Plat baja t= 6 mm kg 175.17 Rp 24,730.00 Rp 4,331,954.10
18 Angkur Æ 19 mm ; L= 760 - U-50 bh 92.00 Rp 45,000.00 Rp 4,140,000.00
19 Angkur Æ 16 mm ; L= 650 - U-50 bh 12.00 Rp 40,000.00 Rp 480,000.00
20 Murbaut Æ 12 mm bh 824.00 Rp 7,500.00 Rp 6,180,000.00
21 Murbaut Æ 16 mm - A325 bh 318.00 Rp 12,500.00 Rp 3,975,000.00
22 Murbaut Æ 19 mm - A325 bh 310.00 Rp 15,000.00 Rp 4,650,000.00
23 Trekstang Æ 12 mm bh 396.00 Rp 22,500.00 Rp 8,910,000.00
24 Ikatan angin Æ 16 mm bh 46.00 Rp 250,000.00 Rp 11,500,000.00
25 Jarum keras Æ 16 mm bh 46.00 Rp 25,000.00 Rp 1,150,000.00
26 Sandblasting - Standart SA 2.5 kg 34,159.52 Rp 2,547.26 Rp 87,013,249.28
27 Cat baja Epoxy t=150 mikron kg 34,159.52 Rp 1,956.49 Rp 66,832,633.25

SUB TOTAL PEKERJAAN C - IV Rp 1,032,001,714.18

SUB TOTAL PEKERJAAN C Rp 1,842,521,196.21


RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


D BANGUNAN GUDANG PERCETAKAN (AS. 13 - 19)
D-I PEKERJAAN TANAH
1 Galian tanah m3 14.31 Rp 64,625.00 Rp 924,783.75
2 Urug kembali m3 7.16 Rp 55,550.00 Rp 397,738.00
3 Buang tanah m3 1.43 Rp 37,125.00 Rp 53,088.75
4 Urugan Sirtu + Pemadatan m3 1,066.38 Rp 72,525.00 Rp 77,339,209.50

SUB TOTAL PEKERJAAN D-I Rp 78,714,820.00

D - II PEKERJAAN PONDASI
2 Supply Tiang Pancang 250x250 mm m' 704.00 Rp 160,000.00 Rp 112,640,000.00
3 Pemancangan m' 704.00 Rp 75,000.00 Rp 52,800,000.00
4 Potong Kepala tiang titik 52.00 Rp 100,000.00 Rp 5,200,000.00

SUB TOTAL PEKERJAAN D-II Rp 170,640,000.00

D - III PEKERJAAN BETON


I PILE CAP
1 PC-1A
- Lantai kerja B0 m3 0.25 Rp 766,272.62 Rp 191,568.15
- Beton f'c 25 m3 2.63 Rp 1,006,085.48 Rp 2,646,004.80
- Besi U - 24 kg 46.87 Rp 13,510.00 Rp 633,213.70
- Besi U - 40 kg 810.20 Rp 13,510.00 Rp 10,945,802.00
- Bekisting Bataco m2 20.00 Rp 133,200.00 Rp 2,664,000.00

2 PC-1B
- Lantai kerja B0 m3 0.04 Rp 766,272.62 Rp 30,650.90
- Beton f'c 25 m3 0.45 Rp 1,006,085.48 Rp 452,738.46
- Besi U - 24 kg 4.69 Rp 13,510.00 Rp 63,361.90
- Besi U - 40 kg 119.93 Rp 13,510.00 Rp 1,620,254.30
- Bekisting Bataco m2 2.88 Rp 133,200.00 Rp 383,616.00

3 PC-1C
- Lantai kerja B0 m3 0.50 Rp 766,272.62 Rp 383,136.31
- Beton f'c 25 m3 6.30 Rp 1,006,085.48 Rp 6,338,338.50
- Besi U - 24 kg 155.40 Rp 13,510.00 Rp 2,099,454.00
- Besi U - 40 kg 1,921.23 Rp 13,510.00 Rp 25,955,817.30
- Bekisting Bataco m2 48.00 Rp 133,200.00 Rp 6,393,600.00

4 PC-1D
- Lantai kerja B0 m3 0.32 Rp 766,272.62 Rp 245,207.24
- Beton f'c 25 m3 3.97 Rp 1,006,085.48 Rp 3,994,159.34
- Besi U - 24 kg 72.52 Rp 13,510.00 Rp 979,745.20
- Besi U - 40 kg 899.14 Rp 13,510.00 Rp 12,147,381.40
- Bekisting Bataco m2 22.68 Rp 133,200.00 Rp 3,020,976.00

II SLOOF
1 SL-40 A
- Lantai kerja B0 m3 0.43 Rp 766,272.62 Rp 329,497.23
- Beton f'c 25 m3 3.58 Rp 1,006,085.48 Rp 3,601,786.00
- Besi U - 40 kg 738.09 Rp 13,510.00 Rp 9,971,595.90
- Bekisting Bataco m2 34.05 Rp 133,200.00 Rp 4,535,460.00
2 SL-50 A
- Lantai kerja B0 m3 0.39 Rp 766,272.62 Rp 298,846.32
- Beton f'c 25 m3 4.54 Rp 1,006,085.48 Rp 4,567,628.06
- Besi U - 40 kg 786.37 Rp 13,510.00 Rp 10,623,858.70
- Bekisting Bataco m2 15.71 Rp 133,200.00 Rp 2,092,572.00
3 SL-50 B
- Lantai kerja B0 m3 0.43 Rp 766,272.62 Rp 329,497.23
- Beton f'c 25 m3 4.47 Rp 1,006,085.48 Rp 4,497,202.08
- Besi U - 40 kg 677.91 Rp 13,510.00 Rp 9,158,564.10
- Bekisting Bataco m2 17.03 Rp 133,200.00 Rp 2,268,396.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


III PLAT LANTAI
PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3 53.95 Rp 766,272.62 Rp 41,340,407.80
- Beton f'c 25 m3 135.95 Rp 1,006,085.48 Rp 136,777,320.49
- Besi U - 40 kg 6,956.06 Rp 13,510.00 Rp 93,976,370.60
- Bekisting multiplek 12 mm ( expose ) m2 19.78 Rp 414,645.00 Rp 8,201,678.10

PLAT LANTAI S2 (+4.50M)


- Lantai kerja Bo m3 3.31 Rp 766,272.62 Rp 2,536,362.37
- Beton f'c 25 m3 8.34 Rp 1,006,085.48 Rp 8,390,752.87
- Besi U - 40 kg 426.87 Rp 13,510.00 Rp 5,767,013.70
- Bekisting multiplek 12 mm ( expose ) m2 66.21 Rp 414,645.00 Rp 27,453,645.45

PLAT LANTAI S3 (+4.50M)


- Lantai kerja Bo m3 3.31 Rp 766,272.62 Rp 2,536,362.37
- Beton f'c 25 m3 8.34 Rp 1,006,085.48 Rp 8,390,752.87
- Besi U - 40 kg 426.87 Rp 13,510.00 Rp 5,767,013.70
- Bekisting multiplek 12 mm ( expose ) m2 66.21 Rp 414,645.00 Rp 27,453,645.45

DILATASI PLAT LANTAI


- Siku L 50.50.5 + angkur 8 mm kg 808.84 Rp 24,405.00 Rp 19,739,740.20
- Plat baja t=6 mm kg 1,490.68 Rp 24,730.00 Rp 36,864,516.40
- Pasir m3 0.26 Rp 205,850.00 Rp 53,521.00
- Aspalt m3 0.33 Rp 1,974,021.11 Rp 651,426.97
- Streofom m2 9.71 Rp 100,000.00 Rp 971,000.00

IV KOLOM
1 KOLOM K-400
- Beton f'c 25 m3 0.25 Rp 1,006,085.48 Rp 251,521.37
- Besi U - 40 kg 84.75 Rp 13,510.00 Rp 1,144,972.50
- Bekisting multiplek 12 mm ( expose ) m2 3.12 Rp 354,678.00 Rp 1,106,595.36
2 KOLOM K-750
- Beton f'c 25 m3 4.63 Rp 1,006,085.48 Rp 4,658,175.75
- Besi U - 40 kg 782.19 Rp 13,510.00 Rp 10,567,386.90
- Bekisting multiplek 12 mm ( expose ) m2 36.96 Rp 354,678.00 Rp 13,108,898.88
SUB TOTAL PEKERJAAN D-III Rp 591,173,010.23

D - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom CAST. 675.200.9.14 kg 12,768.00 Rp 24,845.00 Rp 317,220,960.00
- Kolom WF 400.200.8.13 kg 5,940.00 Rp 24,845.00 Rp 147,579,300.00
- Kolom HB 300.300.10.15 kg 8,460.00 Rp 24,845.00 Rp 210,188,700.00
- Kolom WF 300.150.6,5.9 kg 466.80 Rp 24,845.00 Rp 11,597,646.00
- Kolom WF 200.100.5,5.8 (gewel) kg 307.20 Rp 24,845.00 Rp 7,632,384.00
2 BALOK BAJA
- WF 400.200.8.13 kg 14,018.40 Rp 24,845.00 Rp 348,287,148.00
- HB 300.300.10.15 kg 17,474.60 Rp 24,845.00 Rp 434,156,437.00
- WF 300.150.6,5.9 kg 746.17 Rp 24,845.00 Rp 18,538,593.65
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 kg 23,104.00 Rp 24,845.00 Rp 574,018,880.00
- Voute WF 300.150.6,5.9 kg 602.80 Rp 24,845.00 Rp 14,976,566.00
- Rafter WF 250.125.6.9 kg - Rp 24,845.00 Rp -
- Voute WF 250.125.6.9 kg 347.27 Rp 24,845.00 Rp 8,627,923.15
- Rafter WF 200.100.5,5.8 kg 2,239.65 Rp 24,845.00 Rp 55,644,104.25
- Voute WF 200.100.5,5.8 kg 170.64 Rp 24,845.00 Rp 4,239,550.80
3 Tiebeam WF 200.100.5,5.8 kg 4,454.40 Rp 24,845.00 Rp 110,669,568.00
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg 1,755.60 Rp 24,405.00 Rp 42,845,418.00
5 Gording C 150.65.20.2,3 kg 5,913.60 Rp 24,130.00 Rp 142,695,168.00
6 Rangka Cladding C 150.65.20.2,3 kg 7,100.72 Rp 24,130.00 Rp 171,340,373.60
7 Rangka Listplank C 100.50.20.2,3 kg 1,880.59 Rp 24,130.00 Rp 45,378,636.70
8 Bracing Kolom L 60.60.6 kg 586.23 Rp 23,915.00 Rp 14,019,690.45
9 Penggantung Talang L 40.40.4 kg 261.75 Rp 23,915.00 Rp 6,259,751.25
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


10 Penggantung Talang Datar Plat Strip 40.4 kg 128.71 Rp 24,730.00 Rp 3,182,998.30
11 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg 417.63 Rp 24,730.00 Rp 10,327,989.90
12 Shear connector L 50.50.5 kg 150.80 Rp 23,915.00 Rp 3,606,382.00
13 Plat baja t= 18 mm kg 289.33 Rp 24,730.00 Rp 7,155,130.90
14 Plat baja t= 16 mm kg 1,059.12 Rp 24,730.00 Rp 26,192,037.60
15 Plat baja t= 12 mm kg 4.57 Rp 24,730.00 Rp 113,016.10
16 Plat baja t= 10 mm kg 95.90 Rp 24,730.00 Rp 2,371,607.00
17 Plat baja t= 8 mm kg 52.33 Rp 24,730.00 Rp 1,294,120.90
18 Plat baja t= 6 mm kg 66.18 Rp 24,730.00 Rp 1,636,631.40
19 Angkur Æ 22 mm ; L= 600- U-40 bh 40.00 Rp 60,000.00 Rp 2,400,000.00
20 Angkur Æ 19 mm ; L= 760 - U-50 bh 20.00 Rp 45,000.00 Rp 900,000.00
21 Angkur Æ 16 mm ; L= 650 - U-50 bh 20.00 Rp 40,000.00 Rp 800,000.00
22 Murbaut Æ 12 mm bh 892.00 Rp 7,500.00 Rp 6,690,000.00
23 Murbaut Æ 16 mm - A325 bh 900.00 Rp 12,500.00 Rp 11,250,000.00
24 Murbaut Æ 19 mm - A325 bh 894.00 Rp 15,000.00 Rp 13,410,000.00
25 Murbaut Æ 22 mm - A325 bh 920.00 Rp 20,000.00 Rp 18,400,000.00
26 Murbaut Æ 25 mm - A325 bh 925.00 Rp 30,000.00 Rp 27,750,000.00
27 Trekstang Æ 12 mm bh 260.00 Rp 22,500.00 Rp 5,850,000.00
28 Ikatan angin Æ 16 mm bh 24.00 Rp 250,000.00 Rp 6,000,000.00
29 Jarum keras Æ 16 mm bh 32.00 Rp 25,000.00 Rp 800,000.00
30 Sandblasting - Standart SA 2.5 kg 113,218.44 Rp 2,547.26 Rp 288,397,036.70
31 Cat baja Epoxy t=150 mikron kg 113,218.44 Rp 1,956.49 Rp 221,510,327.93
32 Tangga
- Balok WF 250.125.6.9 Kg 38.40 Rp 24,845.00 Rp 954,048.00
- UNP 200.80.7,5.11 Kg 537.73 Rp 24,405.00 Rp 13,123,300.65
- Siku 40.40.4 Kg 278.78 Rp 23,915.00 Rp 6,667,023.70
- Plat Bordes 3,2 mm Kg 368.69 Rp 24,730.00 Rp 9,117,703.70
- Pipa Hitam 2 " Kg 1,110.79 Rp 24,730.00 Rp 27,469,836.70
- Plat t=12 mm Kg 18.23 Rp 24,730.00 Rp 450,827.90
- Plat t=6 mm Kg 2.83 Rp 24,730.00 Rp 69,985.90

SUB TOTAL PEKERJAAN D - IV Rp 3,403,806,804.13

SUB TOTAL PEKERJAAN D Rp 4,244,334,634.37

E BANGUNAN GUDANG DALAM PROSES BAKU (AS. 19-22)


E-I PEKERJAAN TANAH
1 Galian tanah m3 2.34 Rp 64,625.00 Rp 151,222.50
2 Urug kembali m3 1.17 Rp 55,550.00 Rp 64,993.50
3 Buang tanah m3 0.23 Rp 37,125.00 Rp 8,538.75
4 Urugan Sirtu + Pemadatan m3 544.11 Rp 72,525.00 Rp 39,461,577.75

SUB TOTAL PEKERJAAN E-I Rp 39,686,332.50

E - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 272.00 Rp 160,000.00 Rp 43,520,000.00
2 Pemancangan m' 272.00 Rp 75,000.00 Rp 20,400,000.00
3 Potong Kepala tiang titik 21.00 Rp 100,000.00 Rp 2,100,000.00

SUB TOTAL PEKERJAAN E-II Rp 66,020,000.00

E - III PEKERJAAN BETON


I PILE CAP
1 PC-1B
- Lantai kerja B0 m3 0.18 Rp 766,272.62 Rp 137,929.07
- Beton f'c 25 m3 2.27 Rp 1,006,085.48 Rp 2,283,814.03
- Besi U - 24 kg 599.63 Rp 13,510.00 Rp 8,101,001.30
- Besi U - 40 kg 23.43 Rp 13,510.00 Rp 316,539.30
- Bekisting Bataco m2 14.40 Rp 133,200.00 Rp 1,918,080.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


II RETAINING WALL
1 RETAINING WALL 8
- Lantai kerja B0 m3 1.89 Rp 766,272.62 Rp 1,448,255.25
- Beton f'c 25 m3 11.78 Rp 1,006,085.48 Rp 11,851,686.91
- Besi U - 40 kg 1,134.03 Rp 13,510.00 Rp 15,320,745.30
- Bekisting multiplek 12 mm ( expose ) m2 141.09 Rp 351,495.00 Rp 49,592,429.55

III SLOOF
1 SL-40 A
- Lantai kerja B0 m3 0.43 Rp 766,272.62 Rp 329,497.23
- Beton f'c 25 m3 3.58 Rp 1,006,085.48 Rp 3,601,786.00
- Besi U - 40 kg 702.94 Rp 13,510.00 Rp 9,496,719.40
- Bekisting Bataco m2 17.03 Rp 133,200.00 Rp 2,268,396.00
2 SL-50 A
- Lantai kerja B0 m3 0.34 Rp 766,272.62 Rp 260,532.69
- Beton f'c 25 m3 3.91 Rp 1,006,085.48 Rp 3,933,794.21
- Besi U - 40 kg 676.89 Rp 13,510.00 Rp 9,144,783.90
- Bekisting Bataco m2 13.53 Rp 133,200.00 Rp 1,802,196.00
3 SL-50 B
- Lantai kerja B0 m3 0.21 Rp 766,272.62 Rp 160,917.25
- Beton f'c 25 m3 2.23 Rp 1,006,085.48 Rp 2,243,570.61
- Besi U - 40 kg 338.95 Rp 13,510.00 Rp 4,579,214.50
- Bekisting Bataco m2 8.51 Rp 133,200.00 Rp 1,133,532.00

III PLAT LANTAI


PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3 27.69 Rp 766,272.62 Rp 21,218,088.82
- Beton f'c 25 m3 69.78 Rp 1,006,085.48 Rp 70,204,644.53
- Besi U - 40 kg 3,570.49 Rp 13,510.00 Rp 48,237,319.90
- Bekisting multiplek 12 mm ( expose ) m2 14.55 Rp 414,645.00 Rp 6,033,084.75

IV KOLOM
1 KOLOM K-350
- Beton f'c 25 m3 0.44 Rp 1,006,085.48 Rp 442,677.61
- Besi U - 40 kg 167.43 Rp 13,510.00 Rp 2,261,979.30
- Bekisting multiplek 12 mm ( expose ) m2 5.76 Rp 354,678.00 Rp 2,042,945.28
2 KOLOM K-450
- Beton f'c 25 m3 1.02 Rp 1,006,085.48 Rp 1,026,207.19
- Besi U - 40 kg 318.91 Rp 13,510.00 Rp 4,308,474.10
- Bekisting multiplek 12 mm ( expose ) m2 10.80 Rp 354,678.00 Rp 3,830,522.40
SUB TOTAL PEKERJAAN E-III Rp 289,531,364.38

E - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 350.175.7.11 kg 2,379.00 Rp 24,845.00 Rp 59,106,255.00
- Kolom WF 250.125.6.9 kg 1,383.00 Rp 24,845.00 Rp 34,360,635.00
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 (WF 300.150.6,5.9) kg 1,034.00 Rp 24,845.00 Rp 25,689,730.00
- Voute WF 300.150.6,5.9 kg 91.67 Rp 24,845.00 Rp 2,277,541.15
- Rafter WF 250.125.6.9 kg 834.10 Rp 24,845.00 Rp 20,723,214.50
- Voute WF 250.125.6.9 kg 23.66 Rp 24,845.00 Rp 587,832.70
- Rafter WF 200.100.5,5.8 kg 160.40 Rp 24,845.00 Rp 3,985,138.00
- Voute WF 200.100.5,5.8 kg 41.80 Rp 24,845.00 Rp 1,038,521.00
3 Tiebeam WF 200.100.5,5.8 kg 767.88 Rp 24,845.00 Rp 19,077,978.60
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg 316.40 Rp 24,405.00 Rp 7,721,742.00
5 Gording C 150.65.20.2,3 kg 2,754.10 Rp 24,130.00 Rp 66,456,433.00
6 Rangka Cladding C 150.65.20.2,3 kg 1,555.40 Rp 24,130.00 Rp 37,531,802.00
7 Rangka Listplank C 100.50.20.2,3 kg 438.40 Rp 24,130.00 Rp 10,578,592.00
9 Bracing Kolom L 60.60.6 kg 642.62 Rp 23,915.00 Rp 15,368,257.30
10 Penggantung Talang L 40.40.4 kg 37.75 Rp 23,915.00 Rp 902,791.25
11 Penggantung Talang Datar Plat Strip 40.4 kg 29.86 Rp 24,730.00 Rp 738,437.80
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg 28.00 Rp 24,730.00 Rp 692,440.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


14 Plat baja t= 12 mm kg 11.40 Rp 24,730.00 Rp 281,922.00
15 Plat baja t= 10 mm kg 325.80 Rp 24,730.00 Rp 8,057,034.00
16 Plat baja t= 8 mm kg 105.00 Rp 24,730.00 Rp 2,596,650.00
17 Plat baja t= 6 mm kg 133.00 Rp 24,730.00 Rp 3,289,090.00
18 Angkur Æ 19 mm ; L= 760 - U-50 bh 32.00 Rp 45,000.00 Rp 1,440,000.00
19 Angkur Æ 16 mm ; L= 650 - U-50 bh 32.00 Rp 40,000.00 Rp 1,280,000.00
20 Murbaut Æ 12 mm bh 312.00 Rp 7,500.00 Rp 2,340,000.00
21 Murbaut Æ 16 mm - A325 bh 48.00 Rp 12,500.00 Rp 600,000.00
22 Murbaut Æ 19 mm - A325 bh 160.00 Rp 15,000.00 Rp 2,400,000.00
24 Trekstang Æ 12 mm bh 156.00 Rp 22,500.00 Rp 3,510,000.00
25 Ikatan angin Æ 16 mm bh 8.00 Rp 250,000.00 Rp 2,000,000.00
26 Jarum keras Æ 16 mm bh 16.00 Rp 25,000.00 Rp 400,000.00
27 Sandblasting - Standart SA 2.5 kg 13,093.24 Rp 2,547.26 Rp 33,351,913.49
28 Cat baja Epoxy t=150 mikron kg 13,093.24 Rp 1,956.49 Rp 25,616,744.82

SUB TOTAL PEKERJAAN E - IV Rp 394,000,695.61

SUB TOTAL PEKERJAAN E Rp 789,238,392.49

F GROUND TANK
F-I PEKERJAAN TANAH
1 Galian tanah m3 655.20 Rp 64,625.00 Rp 42,342,300.00
2 Urug kembali m3 226.20 Rp 55,550.00 Rp 12,565,410.00
3 Buang tanah m3 429.00 Rp 37,125.00 Rp 15,926,625.00
4 Urugan Sirtu + Pemadatan m3 16.50 Rp 72,525.00 Rp 1,196,662.50

SUB TOTAL PEKERJAAN F-I Rp 72,030,997.50

F - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 336.00 Rp 160,000.00 Rp 53,760,000.00
2 Pemancangan m' 336.00 Rp 75,000.00 Rp 25,200,000.00
3 Potong Kepala tiang titik 24.00 Rp 100,000.00 Rp 2,400,000.00

SUB TOTAL PEKERJAAN F-II Rp 81,360,000.00

F - III PEKERJAAN BETON


I SLOOF
1 SL-60
- Lantai kerja B0 m3 1.38 Rp 766,272.62 Rp 1,057,456.21
- Beton fc' 30 m3 20.70 Rp 1,091,415.48 Rp 22,592,300.36
- Besi U - 40 kg 2,896.33 Rp 13,510.00 Rp 39,129,418.30
- Bekisting Bataco m2 138.00 Rp 133,200.00 Rp 18,381,600.00

II BALOK
1 B-30
- Lantai kerja B0 m3 - Rp 766,272.62 Rp -
- Beton fc' 30 m3 0.32 Rp 1,091,415.48 Rp 349,252.95
- Besi U - 24 kg 12.03 Rp 13,510.00 Rp 162,525.30
- Besi U - 40 kg 22.05 Rp 13,510.00 Rp 297,895.50
- Bekisting Bataco m2 4.24 Rp 133,200.00 Rp 564,768.00

2 B-40A
- Lantai kerja B0 m3 - Rp 766,272.62 Rp -
- Beton fc' 30 m3 4.00 Rp 1,091,415.48 Rp 4,365,661.90
- Besi U - 24 kg 99.53 Rp 13,510.00 Rp 1,344,650.30
- Besi U - 40 kg 261.46 Rp 13,510.00 Rp 3,532,324.60
- Bekisting Bataco m2 42.63 Rp 133,200.00 Rp 5,678,316.00
3 B-40B
- Lantai kerja B0 m3 - Rp 766,272.62 Rp -
- Beton fc' 30 m3 1.50 Rp 1,091,415.48 Rp 1,637,123.21
- Besi U - 24 kg 36.77 Rp 13,510.00 Rp 496,762.70
- Besi U - 40 kg 112.20 Rp 13,510.00 Rp 1,515,822.00
- Bekisting Bataco m2 15.75 Rp 133,200.00 Rp 2,097,900.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


4 CL-40
- Lantai kerja B0 m3 - Rp 766,272.62 Rp -
- Beton fc' 30 m3 0.36 Rp 1,091,415.48 Rp 392,909.57
- Besi U - 24 kg 8.83 Rp 13,510.00 Rp 119,293.30
- Besi U - 40 kg 26.93 Rp 13,510.00 Rp 363,824.30
- Bekisting Bataco m2 3.78 Rp 133,200.00 Rp 503,496.00

III WALL + SLAB


- Lantai kerja Bo m3 3.57 Rp 766,272.62 Rp 2,735,593.25
- Beton fc' 30 m3 121.58 Rp 1,091,415.48 Rp 132,694,293.60
- Besi U - 40 kg 9,494.74 Rp 13,510.00 Rp 128,273,937.40
- Bekisting multiplek 12 mm ( expose ) m2 491.50 Rp 351,495.00 Rp 172,759,792.50

IV KOLOM
1 KOLOM K-30
- Beton fc' 30 m3 4.41 Rp 1,091,415.48 Rp 4,813,142.25
- Besi U - 40 kg 923.16 Rp 13,510.00 Rp 12,471,891.60
- Bekisting multiplek 12 mm ( expose ) m2 58.80 Rp 354,678.00 Rp 20,855,066.40
SUB TOTAL PEKERJAAN F-III Rp 579,187,017.51
SUB TOTAL PEKERJAAN F Rp 732,578,015.01

G R. GENSET
G- I PEKERJAAN TANAH
1 Galian tanah m3 24.00 Rp 64,625.00 Rp 1,551,000.00
2 Urug kembali m3 7.90 Rp 55,550.00 Rp 438,845.00
3 Buang tanah m3 16.10 Rp 37,125.00 Rp 597,712.50
4 Urugan Sirtu + Pemadatan m3 120.00 Rp 72,525.00 Rp 8,703,000.00

SUB TOTAL PEKERJAAN G-I Rp 11,290,557.50

G - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 336.00 Rp 160,000.00 Rp 53,760,000.00
2 Pemancangan m' 336.00 Rp 75,000.00 Rp 25,200,000.00
3 Potong Kepala tiang titik 24.00 Rp 100,000.00 Rp 2,400,000.00

SUB TOTAL PEKERJAAN G-II Rp 81,360,000.00

E - III PEKERJAAN BETON


I PC 2
- Lantai kerja B0 m3 0.13 Rp 766,272.62 Rp 99,615.44
- Beton f'c 25 m3 3.50 Rp 1,006,085.48 Rp 3,521,299.17
- Besi U - 24 kg 5.95 Rp 13,510.00 Rp 80,384.50
- Besi U - 40 kg 97.00 Rp 13,510.00 Rp 1,310,470.00
- Bekisting Bataco m2 12.00 Rp 133,200.00 Rp 1,598,400.00

II PONDASI GENSET
- Lantai kerja B0 m3 0.26 Rp 766,272.62 Rp 199,230.88
- Beton f'c 25 m3 1.58 Rp 1,006,085.48 Rp 1,589,615.05
- Besi U - 24 kg 118.17 Rp 13,510.00 Rp 1,596,476.70
- Besi U - 40 kg 4.46 Rp 13,510.00 Rp 60,254.60
- Bekisting Bataco m2 3.01 Rp 133,200.00 Rp 400,932.00

PONDASI TRAFO
- Lantai kerja B0 m3 0.12 Rp 766,272.62 Rp 91,952.71
- Beton f'c 25 m3 0.85 Rp 1,006,085.48 Rp 855,172.65
- Besi U - 24 kg 29.84 Rp 13,510.00 Rp 403,138.40
- Besi U - 40 kg 20.67 Rp 13,510.00 Rp 279,251.70
- Bekisting Bataco m2 2.24 Rp 133,200.00 Rp 298,368.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


R. GENSET
- Lantai kerja B0 m3 36.63 Rp 766,272.62 Rp 28,068,566.04
- Beton f'c 25 m3 14.65 Rp 1,006,085.48 Rp 14,739,152.23
- Besi U - 24 kg 118.17 Rp 13,510.00 Rp 1,596,476.70
- Besi U - 40 kg 4.46 Rp 13,510.00 Rp 60,254.60
- Bekisting Bataco m2 3.01 Rp 133,200.00 Rp 400,932.00

III SLOOF
1 SL-50 A
- Lantai kerja B0 m3 0.33 Rp 766,272.62 Rp 252,869.96
- Beton f'c 25 m3 5.48 Rp 1,006,085.48 Rp 5,513,348.41
- Besi U - 40 kg 428.56 Rp 13,510.00 Rp 5,789,845.60
- Bekisting Bataco m2 10.33 Rp 133,200.00 Rp 1,375,956.00
2 SL-50 B
- Lantai kerja B0 m3 0.20 Rp 766,272.62 Rp 153,254.52
- Beton f'c 25 m3 3.25 Rp 1,006,085.48 Rp 3,269,777.80
- Besi U - 40 kg 254.40 Rp 13,510.00 Rp 3,436,944.00
- Bekisting Bataco m2 26.00 Rp 133,200.00 Rp 3,463,200.00

IV BALOK
B-50A
- Lantai kerja Bo m3 - Rp 766,272.62 Rp -
- Beton f'c 25 m3 5.73 Rp 1,006,085.48 Rp 5,764,869.78
- Besi U - 40 kg 456.25 Rp 13,510.00 Rp 6,163,937.50
- Bekisting multiplek 12 mm ( expose ) m2 57.25 Rp 362,895.00 Rp 20,775,738.75

B-50B
- Lantai kerja Bo m3 - Rp 766,272.62 Rp -
- Beton f'c 25 m3 4.50 Rp 1,006,085.48 Rp 4,527,384.64
- Besi U - 40 kg 358.63 Rp 13,510.00 Rp 4,845,091.30
- Bekisting multiplek 12 mm ( expose ) m2 45.00 Rp 362,895.00 Rp 16,330,275.00

LS-40
- Lantai kerja Bo m3 - Rp 766,272.62 Rp -
- Beton f'c 25 m3 2.41 Rp 1,006,085.48 Rp 2,424,666.00
- Besi U - 40 kg 234.28 Rp 13,510.00 Rp 3,165,122.80
- Bekisting multiplek 12 mm ( expose ) m2 30.10 Rp 362,895.00 Rp 10,923,139.50

V PLAT LANTAI
LANTAI EV - 0.50
- Lantai kerja Bo m3 13.66 Rp 766,272.62 Rp 10,467,283.98
- Beton f'c 25 m3 14.65 Rp 1,006,085.48 Rp 14,739,152.23
- Besi U - 40 kg 698.14 Rp 13,510.00 Rp 9,431,871.40
- Bekisting multiplek 12 mm ( expose ) m2 6.65 Rp 414,645.00 Rp 2,757,389.25

LANTAI EV +3.25
- Lantai kerja Bo m3 - Rp 766,272.62 Rp -
- Beton f'c 25 m3 33.12 Rp 1,006,085.48 Rp 33,321,550.97
- Besi U - 40 kg 810.48 Rp 13,510.00 Rp 10,949,584.80
- Bekisting multiplek 12 mm ( expose ) m2 172.25 Rp 414,645.00 Rp 71,422,601.25

VI KOLOM
1 KOLOM K-30
- Beton f'c 25 m3 4.05 Rp 1,006,085.48 Rp 4,074,646.18
- Besi U - 40 kg 737.10 Rp 13,510.00 Rp 9,958,221.00
- Bekisting multiplek 12 mm ( expose ) m2 54.00 Rp 414,645.00 Rp 22,390,830.00
SUB TOTAL PEKERJAAN G-III Rp 344,938,495.99

SUB TOTAL PEKERJAAN G Rp 437,589,053.49


H SALURAN
H-I PEKERJAAN TANAH
1 Galian tanah m3 1,014.93 Rp 64,625.00 Rp 65,589,851.25
2 Urug kembali m3 9.22 Rp 55,550.00 Rp 512,171.00
3 Buang tanah m3 1,005.71 Rp 37,125.00 Rp 37,336,983.75
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

SUB TOTAL PEKERJAAN H-I Rp 103,439,006.00


RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


H- II PEKERJAAN BETON
1 SALURAN A
- Lantai kerja B0 m3 33.16 Rp 766,272.62 Rp 25,409,600.05
- Beton f'c 25 m3 77.26 Rp 1,006,085.48 Rp 77,730,163.89
- Besi U - 40 kg 13,360.41 Rp 13,510.00 Rp 180,499,139.10
- Bekisting m2 816.89 Rp 133,200.00 Rp 108,809,748.00
- Siku L 40.40.4 kg 843.58 Rp 23,915.00 Rp 20,174,215.70
- Penebalan pengatur level m2 107.10 Rp 49,500.00 Rp 5,301,450.00

2 SALURAN A
- Lantai kerja B0 m3 3.92 Rp 766,272.62 Rp 3,003,788.67
- Beton f'c 25 m3 79.92 Rp 1,006,085.48 Rp 80,406,351.26
- Besi U - 40 kg 4,283.05 Rp 13,510.00 Rp 57,864,005.50
- Bekisting m2 119.96 Rp 133,200.00 Rp 15,978,672.00
- Siku L 40.40.4 kg 269.68 Rp 23,915.00 Rp 6,449,397.20
- Penebalan pengatur level m2 107.10 Rp 49,500.00 Rp 5,301,450.00

SUB TOTAL PEKERJAAN H- II Rp 586,927,981.36

SUB TOTAL PEKERJAAN H Rp 690,366,987.36

I PAGAR DAN HALAMAN


I-I PEKERJAAN TANAH
1 Galian tanah m3 1,736.50 Rp 64,625.00 Rp 112,221,312.50
2 Urug kembali m3 16.90 Rp 55,550.00 Rp 938,795.00
3 Buang tanah m3 1,719.60 Rp 37,125.00 Rp 63,840,150.00
4 Urugan Sirtu + Pemadatan m3 87.86 Rp 72,525.00 Rp 6,372,046.50

SUB TOTAL PEKERJAAN I-I Rp 183,372,304.00

I - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 756.00 Rp 160,000.00 Rp 120,960,000.00
2 Pemancangan m' 756.00 Rp 75,000.00 Rp 56,700,000.00
3 Potong Kepala tiang titik 52.00 Rp 100,000.00 Rp 5,200,000.00

SUB TOTAL PEKERJAAN I-II Rp 182,860,000.00

I - III PEKERJAAN BETON


1 PAGAR
I RETAINING WALL 1-7
- Lantai kerja B0 m3 63.00 Rp 766,272.62 Rp 48,275,175.00
- Beton f'c 25 m3 207.32 Rp 1,006,085.48 Rp 208,581,640.92
- Besi U - 40 kg 22,437.62 Rp 13,510.00 Rp 303,132,246.20
- Bekisting multiplek 12 mm ( expose ) m2 1,545.20 Rp 351,495.00 Rp 543,129,019.52
- Batu kali m3 878.08 Rp 860,625.00 Rp 755,697,600.00

2 WC
I RETAINING WALL 9
- Lantai kerja B0 m3 0.32 Rp 766,272.62 Rp 245,207.24
- Beton f'c 25 m3 3.43 Rp 1,006,085.48 Rp 3,450,873.18
- Besi U - 40 kg 309.81 Rp 13,510.00 Rp 4,185,533.10
- Bekisting multiplek 12 mm ( expose ) m2 19.60 Rp 351,495.00 Rp 6,889,302.00
- Batu kali m3 14.63 Rp 860,625.00 Rp 12,590,943.75

II PLAT LANTAI
PLAT LANTAI S1 (-0.05M)
- Lantai kerja Bo m3 0.67 Rp 766,272.62 Rp 513,402.65
- Beton f'c 25 m3 1.61 Rp 1,006,085.48 Rp 1,619,797.62
- Besi U - 40 kg 309.84 Rp 13,510.00 Rp 4,185,938.40
- Bekisting multiplek 12 mm ( expose ) m2 1.17 Rp 414,645.00 Rp 485,134.65

3 TANGGA
- Lantai kerja B0 m3 0.16 Rp 766,272.62 Rp 122,603.62
- Beton f'c 25 m3 0.77 Rp 1,006,085.48 Rp 774,685.82
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


- Besi U - 40 kg 58.52 Rp 13,510.00 Rp 790,605.20
- Bekisting multiplek 12 mm ( expose ) m2 2.86 Rp 323,145.00 Rp 924,194.70
- Underla m2 17.50 Rp 250,000.00 Rp 4,375,000.00

4 RAMP
I RETAINING WALL RAMP A AS D/4-5
- Lantai kerja B0 m3 2.22 Rp 766,272.62 Rp 1,701,125.21
- Beton f'c 25 m3 14.94 Rp 1,006,085.48 Rp 15,030,917.01
- Besi U - 40 kg 1,183.70 Rp 13,510.00 Rp 15,991,787.00
- Bekisting multiplek 12 mm ( expose ) m2 76.96 Rp 351,495.00 Rp 27,051,055.20
- Batu kali m3 38.60 Rp 860,625.00 Rp 33,220,125.00

2 RETAINING WALL RAMP B AS D'/10'-11'


- Lantai kerja B0 m3 1.17 Rp 766,272.62 Rp 896,538.96
- Beton f'c 25 m3 7.56 Rp 1,006,085.48 Rp 7,606,006.20
- Besi U - 40 kg 1,183.70 Rp 13,510.00 Rp 15,991,787.00
- Bekisting multiplek 12 mm ( expose ) m2 755.38 Rp 351,495.00 Rp 265,512,293.10
- Batu kali m3 10.06 Rp 860,625.00 Rp 8,657,887.50

PLAT LANTAI S1 (RAMP 1-2)


- Lantai kerja Bo m3 2.08 Rp 766,272.62 Rp 1,593,847.05
- Beton f'c 25 m3 7.98 Rp 1,006,085.48 Rp 8,028,562.10
- Besi U - 40 kg 1,027.04 Rp 13,510.00 Rp 13,875,310.40
- Bekisting multiplek 12 mm ( expose ) m2 32.00 Rp 351,495.00 Rp 11,247,840.00

SUB TOTAL PEKERJAAN I-III Rp 2,326,373,985.31

I - IV PEKERJAAN BAJA WC
1 KOLOM BAJA
- Kolom WF 150.75.5.7 kg 448.00 Rp 24,845.00 Rp 11,130,560.00
2 RANGKA KUDA-KUDA
- WF 150.75.5.7 kg 257.60 Rp 24,845.00 Rp 6,400,072.00
- Voute WF 150.75.5.7 kg 23.66 Rp 24,845.00 Rp 587,832.70
3 Tiebeam WF 150.75.5.7 kg 168.00 Rp 24,845.00 Rp 4,173,960.00
5 Gording C 125.50.20.2,3 kg 82.53 Rp 24,130.00 Rp 1,991,448.90
7 Rangka Listplank C 75.40.20.2 kg 140.73 Rp 24,130.00 Rp 3,395,814.90
10 Penggantung Talang L 40.40.4 kg 9.08 Rp 23,915.00 Rp 217,148.20
11 Penggantung Talang Datar Plat Strip 40.4 kg 5.00 Rp 24,730.00 Rp 123,650.00
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg 1.47 Rp 24,730.00 Rp 36,353.10
16 Plat baja t= 8 mm kg 53.78 Rp 24,730.00 Rp 1,329,979.40
17 Plat baja t= 6 mm kg 8.83 Rp 24,730.00 Rp 218,365.90
19 Angkur Æ 16 mm ; L= 300 U-40 bh 40.00 Rp 40,000.00 Rp 1,600,000.00
20 Murbaut Æ 12 mm bh 15.00 Rp 7,500.00 Rp 112,500.00
21 Murbaut Æ 16 mm - A325 bh 100.00 Rp 12,500.00 Rp 1,250,000.00
24 Trekstang Æ 12 mm bh 16.80 Rp 22,500.00 Rp 378,000.00
25 Ikatan angin Æ 16 mm bh 2.00 Rp 250,000.00 Rp 500,000.00
26 Jarum keras Æ 16 mm bh 4.00 Rp 25,000.00 Rp 100,000.00
27 Sandblasting - Standart SA 2.5 kg 1,198.68 Rp 2,547.26 Rp 3,053,352.09
28 Cat baja Epoxy t=150 mikron kg 1,198.68 Rp 1,956.49 Rp 2,345,201.01

SUB TOTAL PEKERJAAN I - IV Rp 38,944,238.20


SUB TOTAL PEKERJAAN I Rp 2,731,550,527.50

J PEKERJAAN LAIN-LAIN
1 - Kolom WF 250.125.6.9 (Bangunan Office) kg 612.08 Rp 24,845.00 Rp 15,207,127.60
2 KOLOM K-400 (Bangunan Gudang Bahan Baku (AS. 3 - 13)
- Beton f'c 25 m3 0.25 Rp 1,006,085.48 Rp 251,521.37
- Besi U - 40 kg 84.75 Rp 13,510.00 Rp 1,144,972.50
- Bekisting multiplek 12 mm ( expose ) m2 3.12 Rp 414,645.00 Rp 1,293,692.40
3 - Rafter Castela 375.125.6.9 kg 13,890.74 Rp 24,845.00 Rp 345,115,345.86
PEKERJAAN BAJA WC
1 KOLOM BAJA
- Kolom WF 200.100.5,5.8 kg 505.60 Rp 24,845.00 Rp 12,561,632.00
2 RANGKA KUDA-KUDA
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


- WF 200.100.5,5.8 kg 93.87 Rp 24,845.00 Rp 2,332,200.15
- Voute WF 200.100.5,5.8 kg 45.87 Rp 24,845.00 Rp 1,139,640.15
3 Gording C 125.50.20.2,3 kg 154.00 Rp 24,130.00 Rp 3,716,020.00
4 Rangka Listplank C 75.40.20.2 kg 115.82 Rp 24,130.00 Rp 2,794,736.60
5 Penggantung Talang L 40.40.4 kg 8.47 Rp 23,915.00 Rp 202,560.05
6 Penggantung Talang Datar Plat Strip 40.4 kg 4.76 Rp 24,730.00 Rp 117,714.80
7 Plat baja t= 8 mm kg 40.53 Rp 24,730.00 Rp 1,002,306.90
8 Plat baja t= 6 mm kg 10.60 Rp 24,730.00 Rp 262,138.00
9 Angkur Æ 16 mm ; L= 300 U-40 bh 24.00 Rp 40,000.00 Rp 960,000.00
10 Murbaut Æ 12 mm bh 24.00 Rp 7,500.00 Rp 180,000.00
11 Murbaut Æ 16 mm - A325 bh 54.00 Rp 12,500.00 Rp 675,000.00
12 Trekstang Æ 12 mm bh 12.00 Rp 22,500.00 Rp 270,000.00
13 Ikatan angin Æ 16 mm bh 4.00 Rp 250,000.00 Rp 1,000,000.00
14 Jarum keras Æ 16 mm bh 4.00 Rp 25,000.00 Rp 100,000.00
15 Sandblasting - Standart SA 2.5 kg 16,531.49 Rp 2,547.26 Rp 42,110,032.18
16 Cat baja F Talit ex. Kansai kg 16,531.49 Rp 1,956.49 Rp 32,343,629.96
17 PEKERJAAN CANOPY
WF 250.125.6.9 kg 461.50 Rp 24,845.00 Rp 11,465,967.50
Gording C 150.65.20.2,3 kg 440.00 Rp 24,130.00 Rp 10,617,200.00
Trekstang Æ 12 mm bh 18.00 Rp 22,500.00 Rp 405,000.00
Ikatan angin Æ 16 mm bh 6.00 Rp 250,000.00 Rp 1,500,000.00
Murbaut Æ 12 mm bh 36.00 Rp 7,500.00 Rp 270,000.00
Murbaut Æ 16 mm - A325 bh 32.00 Rp 12,500.00 Rp 400,000.00
Jarum keras Æ 16 mm bh 6.00 Rp 250,000.00 Rp 1,500,000.00
Plat baja t= 8 mm kg 62.90 Rp 24,730.00 Rp 1,555,556.61
18 PEKERJAAN JEMBATAN
- Lantai kerja Bo m3 2.70 Rp 766,272.62 Rp 2,068,936.07
- Beton f'c 25 m3 16.20 Rp 1,006,085.48 Rp 16,298,584.71
- Besi U - 40 kg 1,841.05 Rp 13,510.00 Rp 24,872,580.10
- Bekisting multiplek 12 mm ( expose ) m2 64.80 Rp 414,645.00 Rp 26,868,996.00
19 Test tanah sandcone Ls 1.00 Rp 25,000,000.00 Rp 25,000,000.00

SUB TOTAL PEKERJAAN J Rp 587,603,091.51

JUMLAH SUB PEKERJAAN Rp 14,198,378,794.02


PROFIT 10% Rp 1,419,837,879.40
JUMLAH Rp 15,618,216,673.42
PPN 10% Rp 1,561,821,667.34
GRAND TOTAL Rp 17,180,038,340.76
PEMBULATAN Rp 17,180,038,000.00

Note :
Mohon tidak merubah Format BQ, Apabila ada pekerjaan atau item yang belum tercantum silahkan dimasukkan
dalam pekerjaan lain-lain
RENCANA ANGGARAN BIAYA
PEMILIK : PT. DHARMA NYATA PRESS
PROYEK : JL. CENDRAWASIH - JOMBANG
PEKERJAAN : FINISHING ARSITEKTUR

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA

G PEKERJAAN FINISHING ATAP & CLADDING


I OFFICE 1-3
1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMTG550 AZ 150 m2 261.12 227,797.50 59482483.2
Height Rib 41mm ex Blue Scope Lysaght
2 Cladding select SEAM III 0.55 BMT colourbond Select SEAM III Colourbond 0.55 BMT m2 434.22 427,360.00 185568259.2
ex Blue Scope Lysaght dilapisi Ecospun
3 Plat Cladding 0.4TCT Colourbond Plat Cladding Colourbond 0.40 TCT G550 AZ 150 m2 434.22 223,860.00 97204489.2
ex Blue Scope Lysaght
3 Cladding select SEAM III 0.55 BMT Natural colourbond Select SEAM III Colourbond 0.55 BMT m2 434.22 427,360.00 185568259.2
ex Blue Scope Lysaght dilapisi Ecospun
4 Nok galvalum sheet t= 0,50 mm m' 12.40 207,360.00 2571264
5 Capping Flashing Galvalum sheet t= 0,50 mm natural ex Blue Scope Lysaght m' 434.22 175000 75988500
6 Capping Flashing Clading Colourbond ex Blue Scope Lysaght m' 868.43 210110 182465827.3
7 Talang tegak PVC 4" Type AW ex Wavin, Maspion m' 115.20 108,506.50 12499948.8
8 Knee Ø 4" Type AW ex Wavin, Maspion bh 16.00 50,000.00 800000
9 Roof Drain Ø 4" Aluminium alloy bh 7.00 375,000.00 2625000
10 Insulasi Atap Zeltech ZT BF01 m2 261.12 106,185.00 27727027.2
11 Talang datar galvalum sheet t=0.5mm m 28.00 270,712.50 7579950
JUMLAH 840081008.1

II GUDANG AS. 3-13


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2 1,504.59 227,797.50 342741840.525
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 108.00 223,860.00 24176880
Height rib 41mm ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 411.60 223,860.00 92140776
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2 519.60 223,860.00 116317656
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2 300.92 236,797.50 71256630.105
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m' 60.00 207,360.00 12441600
7 Capping Flashing Galvalum sheet t= 0,50 mm m' 411.60 175,000.00 72030000
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght m' 519.60 210,110.00 109173156
9 Talang datar galvalum sheet t=0.5mm m 72.00 270,712.50 19491300
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m' 240.00 108,506.50 26041560
11 Knee 4 5" Type AW ex Wavin, Maspion bh 44.00 50,000.00 2200000
12 Roof Drain Ø 4" Aluminium alloy bh 12.00 375,000.00 4500000
13 Insulasi Atap Zeltech ZT BF01 m2 1,504.59 106,185.00 159764889.15
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- L 40.40.4 Kg 864.00 23,915.00 20662560
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000

JUMLAH 1139798573.93385

III PERCETAKAN AS. 13-19


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2 1,308.96 227,797.50 298177815.6
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 64.80 223,860.00 14506128
Height rib 41mm ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 554.40 223,860.00 124107984
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2 554.40 223,860.00 124107984
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2 261.79 236,797.50 61991691.12
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m' 36.00 207,360.00 7464960
7 Capping Flashing Galvalum sheet t= 0,50 mm m' 554.40 175,000.00 97020000
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght m' 619.20 210,110.00 130100112
9 Talang datar galvalum sheet t=0.5mm m 74.00 270,712.50 20032725
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m' 252.00 108,506.50 27343638
11 Knee 4 5" Type AW ex Wavin, Maspion bh 42.00 50,000.00 2100000
12 Roof Drain Ø 4" Aluminium alloy bh 14.00 375,000.00 5250000
13 Insulasi Atap Zeltech ZT BF01 m2 1,308.96 106,185.00 138991917.6
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- L 40.40.4 Kg 864.00 23,915.00 20662560
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000

JUMLAH 1138717241.47385
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA

IV GUDANG AS. 19-22


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2 777.14 227,797.50 177030549.15
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 62.40 223,860.00 13968864
Height rib 41mm ex Blue Scope Lysaght
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2 136.80 223,860.00 30624048
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2 136.80 223,860.00 30624048
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2 36.00 236,797.50 8524710
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m' 18.00 207,360.00 3732480
7 Capping Flashing Galvalum sheet t= 0,50 mm m' 136.80 175,000.00 23940000
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght m' 199.20 210,110.00 41853912
9 Talang datar galvalum sheet t=0.5mm m 38.00 270,712.50 10287075
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m' 72.00 108,506.50 7812468
11 Knee 4 5" Type AW ex Wavin, Maspion bh 24.00 50,000.00 1200000
12 Roof Drain Ø 4" Aluminium alloy bh 6.00 375,000.00 2250000
13 Insulasi Atap Zeltech ZT BF01 m2 777.14 106,185.00 82520610.9
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- L 40.40.4 Kg 864.00 23,915.00 20662560
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000

JUMLAH 521891051.203846

TOTAL PEK FINISHING ARSITEKTUR KESELURUHAN 3640487874.71154

H PEKERJAAN FINISHING ARSITEKTUR


I OFFICE AS.1-3
I.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 52.57 126,495.00 6649842.15
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 210.27 109,241.46 22970201.44375
- benangan m' 132.00 15,355.63 2026942.5
- kolom praktis pembesian 4D10,Ø8-150 m3 6.45 8,149,380.17 52563502.0661157
- balok praktis pembesian 4D10,Ø8-150 m3 4.83 8,149,380.17 39361506.1983471
- Partisi Gypsum 12 mm Ex Jayaboard, Knauf m2 35.82 263,557.50 9440629.65
- Cover Kolom Kalsiboard 8mm Ex Calsi m2 49.15 241,182.50 11853155.145
- Partisi Kalsiboard 8mm Ex Calsi m2 232.56 295,932.50 68822062.2

2 Pekerjaan Lantai
- Keramik Lobby Granito 60x60 Pearl White ex Granito m2 42.09 410,375.00 17272683.75
- Keramik 40x40 area Office ex Platinum m2 195.44 189,875.00 37109170
- Keramik 40x40 area Tangga Utama ex Platinum m2 10.14 189,875.00 1925332.5
- Plin Lantai 10x60 Granito ex Granito m' 26.84 235,025.00 6308071
- Plin Lantai 10x40 Platinum ex Platinum m' 156.75 185,900.00 29139825

3 Pek Cat
- Cat dinding + kolom interior ex Dulux Pentalite m2 87.62 31,923.50 2797137.07
- Cat Plafon dak interior ex Dulux Pentalite m2 221.96 31,923.50 7085740.06
- Cat exterior ex Dulux weathershield m2 49.04 37,123.50 1820536.44
- Cat Partisi Gypsum,Calsiboard ex Dulux Pentalite m2 232.56 31,923.50 7424129.16

4 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2 56.14 260,150.00 14604821
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2 8.14 189,925.00 1545989.5
- Waterprofing dinding+lantai ex Sika, Fosroc m2 64.28 137,400.00 8832072
- kran cuci T23BQ13N ex Toto bh 2.00 383,825.00 767650
- Avour TX1BV1 ex Toto bh 5.00 338,825.00 1694125
- Closet CW 660J - SW 660J ex Toto bh 2.00 3,066,300.00 6132600
- Urinoir U57 M ex Toto bh 1.00 3,437,300.00 3437300
- Wastafel LW 237V3 - kran a bh 2.00 4,092,575.00 8185150
- Jet Shower TX403SB ex Toto bh 2.00 501,250.00 1002500
- Cermin bh 2.00 500,000.00 1000000

5 Plafon
- Plafon Calsioard 6mm ex Kalsiboard m2 6.95 151,122.20 1050299.29
- Plafon Gypsum 9mm ex Jayaboard m2 215.01 136,562.20 29362238.622
- List Plafon Shadow line ex Jayaboard m' 140.37 26,435.00 3710680.95
- Cat Plafond Gypsum, Calsiboard ex Dulux Pentalite m2 221.96 31,923.50 7085740.06

JUMLAH LANTAI 1 412981632.755213

I.2 LANTAI 2
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 164.57 126,495.00 20817282.15
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 329.14 109,241.46 35955733.5958333
- benangan m' 132.00 15,355.63 2026942.5
- kolom praktis pembesian 4D10,Ø8-150 m3 6.64 8,149,380.17 54111884.2975207
- balok praktis pembesian 4D10,Ø8-150 m3 5.27 8,149,380.17 42947233.4710744
- Partisi Gypsum 12 mm Ex Jayaboard, Knauf m2 43.28 263,557.50 11406768.6
- Cover Kolom Kalsiboard 8mm Ex Calsi m2 61.70 241,182.50 14880960.25
- Partisi Kalsiboard 8mm Ex Calsi m2 268.72 295,932.50 79522981.4
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
2 Pekerjaan Lantai
- Keramik 40x40 area Office ex Platinum m2 217.55 189,875.00 41307306.25
- Keramik 40x40 area Tangga Utama ex Platinum m2 10.14 189,875.00 1925332.5
- Plin Lantai 10x40 Platinum ex Platinum m' 47.68 185,900.00 8863712
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
3 Pek Cat
- Cat dinding + kolom interior ex Dulux Pentalite m2 658.28 31,923.50 21014601.58
- Cat Plafon dak interior ex Dulux Pentalite m2 605.89 31,923.50 19342129.415
- Cat exterior ex Dulux weathershield m2 658.43 37,123.50 24443226.105
- Cat Partisi Gypsum,Calsiboard ex Dulux Pentalite m2 312.00 31,923.50 9960036.2295

4 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2 65.81 260,150.00 17120471.5
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2 7.04 189,925.00 1337072
- Waterprofing dinding+lantai ex Sika, Fosroc m2 72.85 137,400.00 10009590
- kran cuci T23BQ13N ex Toto bh 2.00 383,825.00 767650
- Avour TX1BV1 ex Toto bh 5.00 338,825.00 1694125
- Closet CW 660J - SW 660J ex Toto bh 3.00 3,066,300.00 9198900
- Urinoir U57 M ex Toto bh 2.00 3,437,300.00 6874600
- Wastafel LW 237V3 - kran ex Toto bh 1.00 4,092,575.00 4092575
- Jet Shower TX403SB ex Toto bh 3.00 501,250.00 1503750
- Cermin bh 2.00 500,000.00 1000000

5 Plafon
- Plafon Calsioard 6mm ex Kalsiboard m2 6.95 151,122.20 1050299.29
- Plafon Gypsum 9mm ex Jayaboard m2 598.93 136,562.20 81791198.446
- List Plafon Shadow line ex Jayaboard m' 143.93 26,435.00 3804789.55
- Cat Plafond Gypsum, Calsiboard ex Dulux Pentalite m2 605.89 31,923.50 19342129.415

4 Pek Railling Tangga Utama


- railling stainless pipa dia.2" stainless m' 33.50 750,000.00 25125000

JUMLAH LANTAI 2 573238280.544928

TOTAL PEK FINISHING ARSITEKTUR OFFICE AS 1-3 986219913.300141

II GUDANG AS. 3-13


II.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 445.09 126,495.00 56301659.55
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 890.18 109,241.46 97244561.3791667
- benangan m2 36.00 15,355.63 552802.5
- dinding roster rooster salip beton uk.20x40cm m2 51.20 642,455.00 32893696
- kolom praktis pembesian 4D10,Ø8-150 m3 0.49 8,149,380.17 3993196.28099174
- balok praktis pembesian 4D10,Ø8-150 m3 1.87 8,149,380.17 15239340.9090909

2 Pekerjaan Lantai
- Floorhardener 5kg/m2 natural ex Sika , Fosroc m2 1,245.50 68,000.00 84694000

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2 445.09 31,923.50 14208830.615
- Cat exterior ex Dulux weathershield m2 890.18 37,123.50 33046597.23

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- Hollow 40x40x1.4 Kg 864.00 17,261.59 14914015.2249135
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000
- Kawat nyamuk M40 aluminium m2 144.00 32,500.00 4680000

5 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2 16.09 260,150.00 4185813.5
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2 1.92 189,925.00 364656
- Waterprofing dinding+lantai ex Sika, Fosroc m2 18.00 137,400.00 2473200
- kran cuci T23BQ13N ex Toto bh 3.00 383,825.00 1151475
- Avour TX1BV1 ex Toto bh 3.00 338,825.00 1016475
- Closet Jongkok CE g ex Toto bh 1.00 787,300.00 787300
- Wastafel LW 237V3 - kran ex Toto bh 1.00 4,092,575.00 4092575
- Jet Shower TX403SB ex Toto bh 1.00 501,250.00 501250
- Cermin bh 1.00 500,000.00 500000

TOTAL PEK FINISHING ARSITEKTUR GUDANG AS.3-13 439701170.343009

III PERCETAKAN AS. 13-19


III.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 205.14 126,495.00 25949184.3
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 410.27 109,241.46 44818493.1104167
- benangan m2 205.14 15,355.63 3150052.9125
- kolom praktis pembesian 4D10,Ø8-150 m3 1.62 8,149,380.17 13201995.8677686
- balok praktis pembesian 4D10,Ø8-150 m3 3.60 8,149,380.17 29337768.5950413
- Partisi Calsiboard 8mm ex Calsi m2 102.57 295,932.50 30353796.525

2 Pekerjaan Lantai
- Floorhardener 5kg/m2 natural ex Sika , Fosroc m2 396.36 68,000.00 26952480
- Epoxy t=500 mikron ex Sika , Fosroc m2 593.03 201,050.00 119228681.5
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2 410.28 31,923.50 13097573.58
- Cat exterior ex Dulux weathershield m2 205.14 37,123.50 7615514.79
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
4 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- Hollow 40x40x1.4 Kg 864.00 17,261.59 14914015.2249135
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000
- Kawat nyamuk M40 aluminium m2 144.00 32,500.00 4680000

III.2 LANTAI 2
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 205.14 126,495.00 25949184.3
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 410.27 109,241.46 44818493.1104167
- benangan m2 205.14 15,355.63 3150052.9125
- kolom praktis pembesian 4D10,Ø8-150 m3 1.62 8,149,380.17 13201995.8677686
- balok praktis pembesian 4D10,Ø8-150 m3 3.60 8,149,380.17 29337768.5950413
- Partisi Calsiboard 8mm ex Calsi m2 175.57 295,932.50 51956869.025

2 Pekerjaan Lantai
- Epoxy t=500 mikron ex Sika , Fosroc m2 593.03 201,050.00 119228681.5

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2 410.28 31,923.50 13097573.58
- Cat exterior ex Dulux weathershield m2 593.03 37,123.50 22015349.205

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- Hollow 40x40x1.4 Kg 864.00 17,261.59 14914015.2249135
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000
- Kawat nyamuk M40 aluminium m2 144.00 32,500.00 4680000

PERCETAKAN AS.13-19 809368992.033973

II GUDANG AS. 19-22


II.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 314.59 126,495.00 39794062.05
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 629.19 109,241.46 68733633.16875
- benangan m2 314.59 15,355.63 4830726.06875
- dinding roster rooster salip beton uk.20x40cm m2 96.00 642,455.00 61675680
- kolom praktis pembesian 4D10,Ø8-150 m3 1.62 8,149,380.17 13201995.8677686
- balok praktis pembesian 4D10,Ø8-150 m3 3.60 8,149,380.17 29337768.5950413

2 Pekerjaan Lantai
- Floorhardener 5kg/m2 natural ex Sika , Fosroc m2 396.36 68,000.00 26952480

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2 314.59 31,923.50 10042813.865
- Cat exterior ex Dulux weathershield m2 943.79 37,123.50 35036602.4475

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2 72.00 50,000.00 3600000
- Hollow 40x40x1.4 Kg 864.00 17,261.59 14914015.2249135
- Plat strip 40x4 Kg 2,256.00 24,730.00 55790880
- Wirebrush dan cat finish Kg 3,468.00 1,634.62 5668846.15384615
- Murbaut dia.6mm bh 240.00 7,500.00 1800000
- Kawat nyamuk M40 aluminium m2 144.00 32,500.00 4680000

5 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2 63.18 260,150.00 16436277
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2 11.30 189,925.00 2146152.5
- Waterprofing dinding+lantai ex Sika, Fosroc m2 74.48 137,400.00 10233552
- kran cuci T23BQ13N ex Toto bh 2.00 383,825.00 767650
- Avour TX1BV1 ex Toto bh 3.00 338,825.00 1016475
- Closet Jongkok CE g ex Toto bh 2.00 787,300.00 1574600
- Wastafel LW 237V3 - kran ex Toto bh 2.00 4,092,575.00 8185150
- Jet Shower TX403SB ex Toto bh 1.00 501,250.00 501250
- Cermin bh 1.00 500,000.00 500000

TOTAL PEK FINISHING ARSITEKTUR GUDANG AS.19-22 417420609.94157

TOTAL PEK FINISHING ARSITEKTUR KESELURUHAN 2652710685.61869


HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
I PEKERJAAN ALUMUNIUM
I OFFICE AS.1-3
I.1 LANTAI 1
1 Pintu P1 Ex Atlantik unit 1.00 12,500,000.00 12500000
2 Pintu P2 Dilengkapi Door Closser unit 3.00 3,375,000.00 10125000
3 Pintu P3 Ex Atlantik unit 1.00 12,500,000.00 12500000
4 Pintu P4 Ex Atlantik unit 1.00 21,500,000.00 21500000
5 Pintu P5 Ex Atlantik unit 1.00 12,500,000.00 12500000
6 Pintu PJ1 Dilengkapi Door Closser unit 1.00 19,725,000.00 19725000
7 Pintu PJ2 Dilengkapi Door Closser unit 1.00 10,650,000.00 10650000
8 Pintu PJ3 Dilengkapi Door Closser unit 1.00 6,150,000.00 6150000
9 Pintu PJ4 Dilengkapi Door Closser unit 1.00 4,545,000.00 4545000
10 Pintu PJ5 Dilengkapi Door Closser unit 1.00 6,720,000.00 6720000
11 Jendela J1 unit 1.00 18,750,000.00 18750000
12 Jendela J2 unit 1.00 24,990,000.00 24990000
13 Jendela J3 unit 1.00 7,380,000.00 7380000
14 Jendela J4 unit 1.00 12,210,000.00 12210000
15 Jendela J5 unit 1.00 8,880,000.00 8880000
16 Jendela J6 unit 1.00 6,750,000.00 6750000
17 Jendela J7 unit 1.00 4,332,000.00 4332000
18 Jendela J8 unit 2.00 4,357,500.00 8715000
19 Jendela J9 unit 1.00 1,449,000.00 1449000
20 Jendela J10 unit 1.00 1,449,000.00 1449000
21 Jendela J11 unit 1.00 1,383,000.00 1383000
22 Jendela J12 unit 1.00 1,464,000.00 1464000
23 Jendela J13 unit 1.00 1,267,500.00 1267500
24 Jendela J14 unit 1.00 2,853,000.00 2853000
25 Jendela J15 unit 1.00 3,495,000.00 3495000
26 Jendela J16 unit 1.00 3,355,500.00 3355500

JUMLAH LANTAI 1 225638000

I.2 LANTAI 2
1 Pintu P2 Dilengkapi Door Closser unit 1.00 3,375,000.00 3375000
2 Pintu PJ6 Dilengkapi Door Closser unit 1.00 11,214,000.00 11214000
3 Pintu PJ7 Dilengkapi Door Closser unit 1.00 10,038,000.00 10038000
4 Pintu PJ8 Dilengkapi Door Closser unit 1.00 10,650,000.00 10650000
5 Jendela J22 unit 1.00 13,807,500.00 13807500
6 Jendela J23 unit 1.00 25,842,000.00 25842000
7 Jendela J24 unit 1.00 8,506,500.00 8506500
8 Jendela J25 unit 1.00 5,256,000.00 5256000
9 Jendela J26 unit 1.00 4,350,000.00 4350000
10 Jendela J26' unit 1.00 4,350,000.00 4350000
11 Jendela J27 unit 1.00 3,436,500.00 3436500
12 Jendela J28 unit 1.00 4,831,500.00 4831500
13 Jendela J29 unit 1.00 2,619,000.00 2619000
14 Jendela J30 unit 1.00 1,671,000.00 1671000
15 Jendela J31 unit 1.00 1,155,000.00 1155000
16 Jendela J32 unit 1.00 1,276,500.00 1276500
17 Jendela J33 unit 1.00 3,766,500.00 3766500

JUMLAH LANTAI 2 116145000

TOTAL PEK ALUMUNIUM OFFICE AS.1-3 341783000


II GUDANG AS. 3-13
II.1 LANTAI 1
1 Pintu P5 Ex Atlantik unit 1.00 12,500,000.00 12500000
2 Jendela J17 unit 2.00 3,100,500.00 6201000
3 Jendela J17' unit 2.00 3,100,500.00 6201000
4 Jendela J18 unit 13.00 3,100,500.00 40306500
5 Jendela J19 unit 1.00 2,245,500.00 2245500
6 Jendela J20 unit 1.00 948,000.00 948000
7 Jendela J21 unit 1.00 948,000.00 948000
8 Jendela J34 unit 14.00 6,960,000.00 97440000
9 Jendela J34' unit 2.00 6,960,000.00 13920000
10 Jendela J35 unit 4.00 5,940,000.00 23760000
11 Pintu PR1 Rolling Door Otomatis Motor unit 1 35000000 35000000
12 Pintu PR2 Rolling Door Otomatis Motor unit 2 55000000 110000000
13 Pintu PR3 Rolling Door Otomatis Motor unit 1.00 32,500,000.00 32500000

TOTAL PEK ALUMUNIUM AREA GUDANG AS.3-13 381970000


III PERCETAKAN AS. 13-19
III.1 LANTAI 1
1 Pintu PR2 Rolling Door Otomatis Motor unit 1 55000000 55000000

JUMLAH LANTAI 1 55000000

III.2 LANTAI 2
1 Jendela J34 unit 12.00 6,960,000.00 83520000

JUMLAH LANTAI 2 83520000


HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
TOTAL PEK ALUMUNIUM AREA PERCETAKAN AS 13-19 138520000
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
IV GUDANG AS. 19-22
IV.1 LANTAI 1
1 Jendela J34 unit 4.00 6,960,000.00 27840000

TOTAL PEK ALUMUNIUM AREA GUDANG AS 13-19 27840000

TOTAL PEK ALUMUNIUM SELURUH 890113000

J PEKERJAAN POWERHOUSE
1 Pasangan dinding 1/2 Bata 1PC : 3PS m2 49.20 120,687.50 5937825
2 Pasangan dinding 1/2 Bata 1PC : 5PS m2 225.40 115,825.00 26106955
1 Pasangan dinding 1 Bata 1PC : 3PS m2 28.56 198,850.00 5679156
2 Pasangan dinding 1 Bata 1PC : 5PS m2 19.04 204,475.00 3893204
3 Plesteran plester aci dinding 1PC : 3PS m2 283.60 56,545.00 16036162
4 Plesteran plester aci dinding 1PC : 5PS m2 420.00 53,905.00 22640100
5 Pekerjaan Benangan m' 330.93 15,355.63 5081636.98125
6 Pekerjaan Cat Dinding Interior Ex Catilac m2 225.40 31,923.50 7195556.9
7 Pekerjaan Cat Dinding Exterior ex Dulux weathershield m2 225.40 37,123.50 8367636.9
8 Pekerjaan Kolom dan Balok Praktis m3 2.65 8,149,380.17 21595857.4380165
9 Plesteran Balok kolom m2 32.22 56,545.00 1821879.9
10 Plesteran Plafon dak m2 162.86 53,905.00 8778968.3
11 Pekerjaan Cat Plafon Dak Beton Ex Catilac m2 162.86 31,923.50 5199061.21
12 Pekerjaan Pintu Besi P1 unit 4.00 12,500,000.00 50000000
13 Pas Keramik Lantai R Trafo, LVMD,Genset,R Pln Murano 30x30 m2 106.47 189,925.00 20221314.75

TOTAL PEK POWER HOUSE 208555314.379267

K PEKERJAAN GROUND TANK


1 Waterprofing dinding+lantai ex Sika, Fosroc m2 200.90 137,400.00 27603660
2 Pas Keramik Murano 30x30 m2 200.90 195,175.00 39210657.5
3 tangga Stainless Steel unit 3.00 3,500,000.00 10500000
4 Tutup Manhole unit 3.00 750,000.00 2250000

TOTAL PEK GROUND TANK 79564317.5

L PEKERJAAN HALAMAN
1 Pagar Panel Beton m2 592.85 450,000.00 266782500
2 Pekerjaan Pembentukan Lahan
- Pemadatan eksisting m3 304.46 49,150.00 14964209
- Onderlaag + pengunci 15/20 m1 210.75 120,000.00 25290000
- Pasang Paving K500 t=10cm Ex Focon setara m2 487.72 145,980.00 71197365.6
- Kanstin Ex Focon setara m1 123.36 129,385.00 15960933.6

TOTAL PEK HALAMAN 394195008.2

M PEKERJAAN LAIN LAIN


I OFFICE AS.1-3
I.1 LANTAI 1
4 Pek Area Toilet
Paper Holder ex Toto-TX 703 AES bh 2.00 175,000.00 350000
6 Pekerjaan Area Pantry
Kitchen zink ex Royal bh 1.00 550,000.00 550000

I.2 LANTAI 2
4 Pek Area Toilet
Paper Holder ex Toto-TX 703 AES bh 3.00 175,000.00 525000

1 Pek.Saluran bangunan
Pasang U-Ditch Uk.60x60x120 + Cover bh 84.00 2,210,991.20 185723260.8
2 Septitank Biotech Kap. 3 m3 bh 1.00 13,500,000.00 13500000
3 Septitank Biotech Kap. 1 m3 bh 2.00 6,000,000.00 12000000
4 Pek. saluran depan jalan Ex. Calvary, Focon, Lisa Concrete atau setara bh 64.00 10,099,045.63 646338920
Box Culvert Uk. 1500x1500
5 Pek.Pasang Kaca Laminnated Tempered Clear 6+6 mm m2 28.96 750,000.00 21721746.75
(Canopy As 1)
6 Pek.Canopy As A dan As F
a. Pek. Pasang Rangka Hollow 100.50.2,0 m1 352.80 85,000.00 29988000
b. Pek. Pasang Talang datar Stainlesstell SUS m1 67.20 450,000.00 30240000
304 T = 1,2mm
c. 'Capping Flashing Galvalum sheet t= 0,50 mm natural m1 360.00 175,000.00 63000000
d. Penutup Polycarbonate m2 270.00 236,797.50 63935325

TOTAL PEK LAIN-LAIN 1067872252.55

Note :
Mohon tidak merubah Format BQ, Apabila ada pekerjaan atau item yang belum tercantum pada Format BQ
silahkan dimasukkan dalam pekerjaan lain-lain.
HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME SATUAN HARGA
Segala sesuatu berkaitan dengan warna, model, dan type harus diasistensikan dahulu kepada owner.
Kontraktor berkewajiban : menambah, melengkapi,memperkuat pekerjaan yang ditawarkan (struktur & arsitektur)
sehingga hasil akhir pekerjaan dapat berfungsi dengan baik dan sempurna, walaupun di gambar dan BQ belum ada.
REKAPITULASI RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN - JOMBANG

VOLUME
No. URAIAN PEKERJAAN TOTAL HARGA BETON BESI BETON ( kg ) WIREMESH BEKISTING BAJA ATAP CLADDING
LUAS BANGUNA (m3) U - 24 U -40 (m2) (m2) (Kg) (m2) (m2)

A PEKERJAAN PERSIAPAN Rp 490,522,860.50


B BANGUNAN OFFICE AS 1-3
B.I. PEKERJAAN TANAH Rp 15,002,586.50
B.II. PEKERJAAN PONDASI Rp 235,410,000.00
B.III. PEKERJAAN BETON Rp 573,585,850.10 472.78 104.17 1859.91 18812.90 472.78 420.14
B.IV. PEKERJAAN BAJA Rp 828,075,598.98 27856.68

C BANGUNAN GUDANG BAHAN BAKU AS. 3-13


C.I. PEKERJAAN TANAH Rp 97,205,024.25
C.II. PEKERJAAN PONDASI Rp 153,320,000.00
C.III. PEKERJAAN BETON Rp 559,994,457.78 1355.7 211.20 56.24 14655.16 1355.70 348.90
C.IV. PEKERJAAN BAJA Rp 1,032,001,714.18 34159.52

D BANGUNAN GUDANG PERCETAKAN AS. 13-19


C.I. PEKERJAAN TANAH Rp 78,714,820.00
C.II. PEKERJAAN PONDASI Rp 170,640,000.00
C.III. PEKERJAAN BETON Rp 591,173,010.23 1078.96 183.45 279.48 14629.61 1078.96 352.63
C.IV. PEKERJAAN BAJA Rp 3,403,806,804.13 110862.99

E BANGUNAN GUDANG DALAM PROSES As. 19-22


C.I. PEKERJAAN TANAH Rp 39,686,332.50
C.II. PEKERJAAN PONDASI Rp 66,020,000.00
C.III. PEKERJAAN BETON Rp 289,531,364.38 553.82 95.01 599.63 6933.07 553.82 225.67
C.IV. PEKERJAAN BAJA Rp 394,000,695.61 13093.24

F GROUND TANK
F.I. PEKERJAAN TANAH Rp 72,030,997.50
F.II. PEKERJAAN PONDASI Rp 81,360,000.00
F.III. PEKERJAAN BETON Rp 579,187,017.51 152.87 157.16 13736.87 754.70

G R. GENSET
G.I. PEKERJAAN TANAH Rp 11,290,557.50
G.II. PEKERJAAN PONDASI Rp 81,360,000.00
G.III. PEKERJAAN BETON Rp 344,938,495.99 36.4 93.77 272.13 4104.43 421.84

H SALURAN
H.I. PEKERJAAN TANAH Rp 103,439,006.00
H.II. PEKERJAAN BETON Rp 586,927,981.36 157.18 0.00 17643.46 936.85

I PAGAR DAN HALAMAN


I.I. PEKERJAAN TANAH Rp 183,372,304.00
I.II. PEKERJAAN PONDASI Rp 182,860,000.00
I.III. PEKERJAAN BETON Rp 2,326,373,985.31 243.61 0.00 26510.23 2433.17
I.IV. PEKERJAAN BAJA Rp 38,944,238.20 1198.68

J PEKERJAAN LAIN-LAIN Rp 587,603,091.51 19.15 0.00 1925.80 67.92 15609.66

K PEKERJAAN FINISHING ATAP & CLADDING


G.I OFFICE AS.1-3 Rp 840,081,008.10 522.24 1302.66
G.II GUDANG AS.3-13 Rp 1,139,798,573.93 3310.10 1039.20
G.III PERCETAKAN AS.13-19 Rp 1,138,717,241.47 2879.71 1173.60
G.IV GUDANG AS 13-19 Rp 521,891,051.20 1590.28 336.00

L PEKERJAAN FINISHING ARSITEKTUR


H.I OFFICE AS.1-3 Rp 986,219,913.30 23.19
H.II GUDANG AS.3-13 Rp 439,701,170.34 2.36
H.III PERCETAKAN AS.13-19 Rp 809,368,992.03 6.84
H.IV GUDANG AS 13-19 Rp 417,420,609.94 5.22

M PEKERJAAN ALUMUNIUM
I.I OFFICE AS.1-3 Rp 341,783,000.00
I.II GUDANG AS.3-13 Rp 381,970,000.00
I.III PERCETAKAN AS.13-19 Rp 138,520,000.00
I.IV GUDANG AS 13-19 Rp 27,840,000.00

N PEKERJAAN POWER HOUSE Rp 208,555,314.38 82.68 2.65

O PEKERJAAN GROUND TANK Rp 79,564,317.50 157.29

P PEKERJAAN HALAMAN Rp 394,195,008.20

Q PEKERJAAN LAIN-LAIN Rp 1,067,872,252.55

TOTAL Rp 23,131,877,246.98 3737.63 1300.67 3224.55 118951.53 3461.26 5961.82 202780.77 8302.33 3851.46
PROFIT 10%
TOTAL II Rp 25,445,064,971.67
PPN 10% Rp 2,544,506,497.17
GRAND TOTAL Rp 27,989,571,468.84
PEMBULATAN Rp 27,989,571,000.00

Sidoarjo, 6 Maret 2019


Dibuat oleh,
Penyedia Jasa,
PT. GARUDA CATUR KENCANA

ARDY KUSTRIYONO
Direktur Utama
JADWAL PELAKSANAAN

PROYEK : PT. DHARMA NYATA PRESS


PEKERJAAN : GEDUNG PERCETAKAN - JOMBANG

JANGKA WAKTU PELAKSANAAN


BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5
No Uraian Pekerjaan Total Harga BOBOT % MG 1 MG 2 MG 3 MG 4 MG 5 MG 6 MG 7 MG 8 MG 9 MG 10 MG 11 MG 12 MG 13 MG 14 MG 15 MG 16 MG 17 MG 18 MG 19 MG 20 MG 21 MG 22
Hr 1-7 Hr 8-14 Hr 15-21 Hr 22-28 Hr 29-35 Hr 36-42 Hr 43-49 Hr 50-56 Hr 57-63 Hr 64-70 Hr 71-77 Hr 78-84 Hr 85-91 Hr 92-98 Hr 99-105 Hr 106-112 Hr 113-119 Hr 120-126 Hr 127-133 Hr 134-140 Hr 141-147 Hr 148-150 KET

A PEKERJAAN PERSIAPAN 490522860.5 2.1205492977 0.530137324 0.530137324 0.530137324 0.5301373244


B BANGUNAN OFFICE AS 1-3
B.I. PEKERJAAN TANAH 15002586.5 0.0648567617 0.032428381 0.032428381
B.II. PEKERJAAN PONDASI 235410000 1.0176865348 0.508843267 0.508843267
B.III. PEKERJAAN BETON 573585850.098571 2.4796338143 0.495926763 0.495926763 0.495926763 0.495926763 0.495926763
B.IV. PEKERJAAN BAJA 828075598.976979 3.5798028415 0.89495071 0.89495071 0.89495071 0.89495071

C BANGUNAN GUDANG BAHAN BAKU AS. 3-13


C.I. PEKERJAAN TANAH 97205024.25 0.4202210794 0.21011054 0.21011054
C.II. PEKERJAAN PONDASI 153320000 0.6628082899 0.331404145 0.331404145
C.III. PEKERJAAN BETON 559994457.778571 2.4208776996 0.48417554 0.48417554 0.48417554 0.48417554 0.48417554
C.IV. PEKERJAAN BAJA 1032001714.17934 4.4613833247 1.115345831 1.115345831 1.115345831 1.115345831

D BANGUNAN GUDANG PERCETAKAN AS. 13-19


C.I. PEKERJAAN TANAH 78714820 0.3402872113 0.170143606 0.170143606
C.II. PEKERJAAN PONDASI 170640000 0.7376833198 0.36884166 0.36884166
C.III. PEKERJAAN BETON 591173010.230539 2.5556637878 0.511132758 0.511132758 0.511132758 0.511132758 0.511132758
C.IV. PEKERJAAN BAJA 3403806804.13494 14.714788462 3.678697115 3.678697115 3.678697115 3.678697115

E BANGUNAN GUDANG DALAM PROSES As. 19-22


C.I. PEKERJAAN TANAH 39686332.5 0.1715655503 0.085782775 0.085782775
C.II. PEKERJAAN PONDASI 66020000 0.2854070134 0.142703507 0.142703507
C.III. PEKERJAAN BETON 289531364.382381 1.2516552863 0.250331057 0.250331057 0.250331057 0.250331057 0.250331057
C.IV. PEKERJAAN BAJA 394000695.611604 1.7032802457 0.425820061 0.425820061 0.425820061 0.425820061

F GROUND TANK
F.I. PEKERJAAN TANAH 72030997.5 0.3113927881 0.155696394 0.155696394
F.II. PEKERJAAN PONDASI 81360000 0.3517224267 0.175861213 0.175861213
F.III. PEKERJAAN BETON 579187017.509524 2.5038478777 0.500769576 0.500769576 0.500769576 0.500769576 0.500769576

G R. GENSET
G.I. PEKERJAAN TANAH 11290557.5 0.0488095168 0.024404758 0.024404758
G.II. PEKERJAAN PONDASI 81360000 0.3517224267 0.175861213 0.175861213
G.III. PEKERJAAN BETON 344938495.988095 1.4911824592 0.298236492 0.298236492 0.298236492 0.298236492 0.298236492

H SALURAN
H.I. PEKERJAAN TANAH 103439006 0.4471708236 0.223585412 0.223585412
H.II. PEKERJAAN BETON 586927981.361905 2.5373123638 0.507462473 0.507462473 0.507462473 0.507462473 0.507462473

I PAGAR DAN HALAMAN


I.I. PEKERJAAN TANAH 183372304 0.7927255624 0.396362781 0.396362781
I.II. PEKERJAAN PONDASI 182860000 0.7905108524 0.395255426 0.395255426
I.III. PEKERJAAN BETON 2326373985.30786 10.057004715 2.011400943 2.011400943 2.011400943 2.011400943 2.011400943
I.IV. PEKERJAAN BAJA 38944238.1964798 0.168357448 0.042089362 0.042089362 0.042089362 0.042089362

J PEKERJAAN LAIN-LAIN 587603091.508745 2.5402308911 0.84674363 0.84674363 0.84674363

K PEKERJAAN FINISHING ATAP & CLADDING


G.I OFFICE AS.1-3 840081008.1 3.6317026895 1.210567563 1.210567563 1.210567563
G.II GUDANG AS.3-13 1139798573.93385 4.9273933186 1.64246444 1.64246444 1.64246444
G.III PERCETAKAN AS.13-19 1138717241.47385 4.9227186766 1.640906226 1.640906226 1.640906226
G.IV GUDANG AS 13-19 521891051.203846 2.2561551993 0.752051733 0.752051733 0.752051733

L PEKERJAAN FINISHING ARSITEKTUR


H.I OFFICE AS.1-3 986219913.300141 4.2634668288 1.065866707 1.065866707 1.065866707 1.065866707
H.II GUDANG AS.3-13 439701170.343009 1.9008451655 0.633615055 0.633615055 0.633615055
H.III PERCETAKAN AS.13-19 809368992.033973 3.4989334562 1.166311152 1.166311152 1.166311152
H.IV GUDANG AS 13-19 417420609.94157 1.8045254412 0.60150848 0.60150848 0.60150848

M PEKERJAAN ALUMUNIUM
I.I OFFICE AS.1-3 341783000 1.477541128 0.369385282 0.369385282 0.369385282 0.369385282
I.II GUDANG AS.3-13 381970000 1.6512710833 0.412817771 0.412817771 0.412817771 0.412817771
I.III PERCETAKAN AS.13-19 138520000 0.5988273175 0.149706829 0.149706829 0.149706829 0.149706829
I.IV GUDANG AS 13-19 27840000 0.1203533968 0.030088349 0.030088349 0.030088349 0.030088349

N PEKERJAAN POWER HOUSE 208555314.379267 0.9015926903 0.225398173 0.225398173 0.225398173 0.225398173

O PEKERJAAN GROUND TANK 79564317.5 0.3439596218 0.114653207 0.114653207 0.114653207

P PEKERJAAN HALAMAN 394195008.2 1.7041202666 0.852060133 0.852060133

Q PEKERJAAN LAIN-LAIN 1067872252.55 4.6164530494 1.154113262 1.154113262 1.154113262 1.154113262

JUMLAH TOTAL Rp 23,131,877,246.98 100


RENCANA 0.530137324 0.562565705 0.751382188 1.716428321 1.936274488 2.268664155 2.639678615 4.857574364 5.409148067 9.814237205 10.9210081 12.87775469 12.75354018 7.738061239 6.498241605 5.200821372 5.111161659 3.308223007 3.082824834 0.961998231 0.530137324 0.5301373244
KOMULATIF RENCANA 0 0.530137324 1.09270303 1.844085218 3.560513538 5.496788027 7.765452181 10.4051308 15.26270516 20.67185323 30.48609043 41.40709853 54.28485322 67.0383934 74.77645464 81.27469625 86.47551762 91.58667928 94.89490229 97.97772712 98.93972535 99.46986268 100

Sidoarjo, 6 Maret 2019


Dibuat oleh,
Penyedia Jasa,
PT. GARUDA CATUR KENCANA
ARDY KUSTRIYONO
Direktur Utama
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN
1 Pembersihan m2 5,583.39
2 Pagar Sementara m1 420.57
3 Egalisasi / Bouwplank m1 413.57
4 Air kerja dan listrik kerja Ls 1.00
5 Direksi keet & Gudang m2
6 Km / Wc darurat pekerja Ls 1.00
7 Mob - demob Ls 1.00
8 Shop drawing & Asbuild drawing Ls 1.00
9 K3 Ls 1.00

SUB TOTAL PEKERJAAN A

B BANGUNAN OFFICE (AS. 1 - 3)


B-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN B-I

B - II PEKERJAAN PONDASI
1 Mob- Demobilisasi Ls 1.00
2 Supply Tiang Pancang 250x250 mm m' 786.00
3 Pemancangan m' 786.00
4 Potong Kepala tiang titik 57.00

SUB TOTAL PEKERJAAN B-II

B - III PEKERJAAN BETON


LANTAI 1 ( -0.50 )
I PILE CAP
1 PC-1B
- Lantai kerja B0 m3 0.11
- Beton f'c 25 m3 1.36
- Besi U - 24 kg 14.06
- Besi U - 40 kg 359.78
- Bekisting Bataco m2 8.64

2 PC-2
- Lantai kerja B0 m3 0.23
- Beton f'c 25 m3 2.95
- Besi U - 24 kg 9.62
- Besi U - 40 kg 2,411.19
- Bekisting Bataco m2 13.68
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

II SLOOF
1 SL-40
- Lantai kerja B0 m3 0.04
- Beton f'c 25 m3 0.37
- Besi U - 24 kg 42.30
- Besi U - 40 kg 33.57
- Bekisting Bataco m2 3.50
2 SL-55A
- Lantai kerja B0 m3 0.97
- Beton f'c 25 m3 11.17
- Besi U - 24 kg 567.80
- Besi U - 40 kg 824.89
- Bekisting Bataco m2 38.69
3 SL-60A
- Lantai kerja B0 m3 0.57
- Beton f'c 25 m3 7.24
- Besi U - 24 kg 314.33
- Besi U - 40 kg 767.53
- Bekisting Bataco m2 23.00
4 SL-60B
- Lantai kerja B0 m3 0.27
- Beton f'c 25 m3 3.10
- Besi U - 24 kg 141.09
- Besi U - 40 kg 384.78
- Bekisting Bataco m2 10.32
5 SL-105A
- Lantai kerja B0 m3 0.68
- Beton f'c 25 m3 13.55
- Besi U - 24 kg 519.73
- Besi U - 40 kg 715.48
- Bekisting Bataco m2 25.80

III PLAT LANTAI


PLAT LANTAI S1 (-0.05M)
- Lantai kerja Bo m3 11.82
- Beton f'c 25 m3 29.79
- Besi U - 40 kg 6,222.48
- Bekisting multiplek 12 mm m2 9.30

PLAT LANTAI S1 (+4,25M)


- Beton f'c 25 m3 29.79
- Besi U - 40 kg 6,222.48
- Shear connector kg
- Bekisting multiplek 9 mm ( expose ) m2 245.69

VI KOLOM
1 KOLOM K-450
- Beton f'c 25 m3 1.70
- Besi U - 40 kg 530.46
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Bekisting multiplek 12 mm ( expose ) m2 18.00

2 KOLOM K-500
- Beton f'c 25 m3 0.38
- Besi U - 40 kg 130.28
- Bekisting multiplek 12 mm ( expose ) m2 3.84
LANTAI 2 (+ 4,35 M)

V TANGGA
- Beton f'c 25 m3 2.77
- Besi U - 24 kg 250.98
- Besi U - 40 kg 209.98
- Bekisting multiplek 12 mm ( expose ) m2 19.68

SUB TOTAL PEKERJAAN B-III

B - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 400.200.8.13 kg 536.58
- Kolom WF 350.175.7.11 kg 3,942.87
- Kolom WF 200.100.5,5.8 kg 1,457.69
2 RANGKA KUDA-KUDA
- Rafter + Voute WF 250.125.6.9 kg 2,121.84
- Konsol + Voute WF 200.100.5,5.8 kg 147.92
3 Balok
- Balok Castela 525.175.7.11 kg 1,019.28
- Balok Castela 450.150.6,5.9 kg 2,091.53
- Balok WF 350.175.7.11 kg 2,774.19
- Balok WF 300.150.6,5.9 kg 427.17
- Balok WF 250.125.6.9 kg 1,518.36
- WF 200.100.5,5.8 kg 610.99
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg 1,075.20
5 Gording C 150.65.20.2,3 kg 1,386.00
6 Rangka Cladding C 150.65.20.2,3 kg 1,873.62
7 Rangka Listplank C 100.50.20.2,3 kg
8 Rangka Listplank C 75.45.20.2,3 kg
9 Bracing Kolom L 60.60.6 kg
10 Penggantung Talang L 40.40.4 kg
11 Penggantung Talang Datar Plat Strip 40.4 kg
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg
13 Plat baja t= 15 mm kg
14 Plat baja t= 12 mm kg
15 Plat baja t= 10 mm kg
16 Plat baja t= 8 mm kg
17 Plat baja t= 6 mm kg
18 Angkur Æ 19 mm ; L= 760 - U-50 bh 48.00
19 Angkur Æ 16 mm ; L= 760 - U-40 bh
20 Murbaut Æ 12 mm bh
21 Murbaut Æ 16 mm - A325 bh
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

22 Murbaut Æ 19 mm - A325 bh
23 Murbaut Æ 22 mm - A325 bh
24 Trekstang Æ 12 mm bh
25 Ikatan angin Æ 16 mm bh
26 Jarum keras Æ 16 mm bh
27 Pekerjaan Tangga
- Balok WF 350.175.7.11 Kg
- WF 200.100.5,5.8 Kg
- Siku 40.40.4 Kg
- Plat Bordes 3,2 mm Kg
- Pipa Hitam 2 " Kg
- Plat t=12 mm Kg
- Plat t=6 mm Kg
28 Sandblasting - Standart SA 2.5 kg
29 Cat baja F Talit ex. Kansai kg

SUB TOTAL PEKERJAAN B - IV

SUB TOTAL PEKERJAAN B

C BANGUNAN GUDANG BAHAN BAKU (AS. 3 - 13)


C-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN C-I

C - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m' 632.00
2 Pemancangan m' 632.00
3 Potong Kepala tiang titik 48.00

SUB TOTAL PEKERJAAN C-II

C - III PEKERJAAN BETON


I PILE CAP
1 PC-1B
- Lantai kerja B0 m3 0.43
- Beton f'c 25 m3 5.44
- Besi U - 24 kg 56.24
- Besi U - 40 kg 1,439.12
- Bekisting Bataco m2 34.56

II RETAINING WALL
1 RETAINING WALL 8
- Lantai kerja B0 m3
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

III SLOOF
1 SL-40 A
- Lantai kerja B0 m3 0.71
- Beton f'c 25 m3 5.99
- Besi U - 40 kg 625.37
- Bekisting Bataco m2 57.00
2 SL-50 A
- Lantai kerja B0 m3 0.39
- Beton f'c 25 m3 4.54
- Besi U - 40 kg 786.37
- Bekisting Bataco m2 15.71
3 SL-50 B
- Lantai kerja B0 m3 0.88
- Beton f'c 25 m3 9.23
- Besi U - 40 kg 1,399.61
- Bekisting Bataco m2 35.15

III PLAT LANTAI


PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3 67.79
- Beton f'c 25 m3 170.82
- Besi U - 40 kg 8,740.20
- Bekisting multiplek 12 mm ( expose ) m2 29.39

IV KOLOM
1 KOLOM K-450
- Beton f'c 25 m3 3.40
- Besi U - 40 kg 530.46
- Bekisting multiplek 12 mm ( expose ) m2 36.00
SUB TOTAL PEKERJAAN C-III

C - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 350.175.7.11 kg
- Kolom WF 300.150.6,5.9 kg
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 (WF 300.150.6,5.9) kg
- Voute WF 300.150.6,5.9 kg
- Rafter WF 250.125.6.9 kg
- Voute WF 250.125.6.9 kg
- Rafter WF 200.100.5,5.8 kg
- Voute WF 200.100.5,5.8 kg
3 Tiebeam WF 200.100.5,5.8 kg
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg
5 Gording C 150.65.20.2,3 kg
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

6 Rangka Cladding C 150.65.20.2,3 kg


7 Rangka Listplank C 100.50.20.2,3 kg
9 Bracing Kolom L 60.60.6 kg
10 Penggantung Talang L 40.40.4 kg
11 Penggantung Talang Datar Plat Strip 40.4 kg
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg
14 Plat baja t= 12 mm kg
15 Plat baja t= 10 mm kg
16 Plat baja t= 8 mm kg
17 Plat baja t= 6 mm kg
18 Angkur Æ 19 mm ; L= 760 - U-50 bh
19 Angkur Æ 16 mm ; L= 650 - U-50 bh
20 Murbaut Æ 12 mm bh
21 Murbaut Æ 16 mm - A325 bh
22 Murbaut Æ 19 mm - A325 bh
23 Trekstang Æ 12 mm bh
24 Ikatan angin Æ 16 mm bh
25 Jarum keras Æ 16 mm bh
26 Sandblasting - Standart SA 2.5 kg
27 Cat baja F Talit ex. Kansai kg

SUB TOTAL PEKERJAAN C - IV

SUB TOTAL PEKERJAAN C

D BANGUNAN GUDANG PERCETAKAN (AS. 13 - 19)


D-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN D-I

D - II PEKERJAAN PONDASI
2 Supply Tiang Pancang 250x250 mm m' 704.00
3 Pemancangan m' 704.00
4 Potong Kepala tiang titik 52.00

SUB TOTAL PEKERJAAN D-II

D - III PEKERJAAN BETON


I PILE CAP
1 PC-1A
- Lantai kerja B0 m3 0.25
- Beton f'c 25 m3 2.63
- Besi U - 24 kg 46.87
- Besi U - 40 kg 810.20
- Bekisting Bataco m2 20.00
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

2 PC-1B
- Lantai kerja B0 m3 0.04
- Beton f'c 25 m3 0.45
- Besi U - 24 kg 4.69
- Besi U - 40 kg 119.93
- Bekisting Bataco m2 2.88

3 PC-1C
- Lantai kerja B0 m3 0.50
- Beton f'c 25 m3 6.30
- Besi U - 24 kg 155.40
- Besi U - 40 kg 1,921.23
- Bekisting Bataco m2 48.00

4 PC-1D
- Lantai kerja B0 m3 0.32
- Beton f'c 25 m3 3.97
- Besi U - 24 kg 72.52
- Besi U - 40 kg 899.14
- Bekisting Bataco m2 22.68

II SLOOF
1 SL-40 A
- Lantai kerja B0 m3 2.54
- Beton f'c 25 m3 21.36
- Besi U - 40 kg 2,594.48
- Bekisting Bataco m2 203.40
2 SL-50 A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2
3 SL-50 B
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2

III PLAT LANTAI


PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

PLAT LANTAI S2 (+4.50M)


- Lantai kerja Bo m3
- Beton f'c 25 m3
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

PLAT LANTAI S3 (+4.50M)


- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

DILATASI PLAT LANTAI


- Siku L 50.50.5 + angkur 8 mm kg
- Plat baja t=6 mm kg
- Pasir m3
- Aspalt m3
- Streofom m2

IV KOLOM
1 KOLOM K-400
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
2 KOLOM K-750
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
SUB TOTAL PEKERJAAN D-III

D - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom CAST. 675.200.9.14 kg
- Kolom WF 400.200.8.13 kg
- Kolom HB 300.300.10.15 kg
- Kolom WF 300.150.6,5.9 kg
- Kolom WF 200.100.5,5.8 (gewel) kg
2 BALOK BAJA
- WF 400.200.8.13 kg
- HB 300.300.10.15 kg
- WF 300.150.6,5.9 kg
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 kg
- Voute WF 300.150.6,5.9 kg
- Rafter WF 250.125.6.9 kg
- Voute WF 250.125.6.9 kg
- Rafter WF 200.100.5,5.8 kg
- Voute WF 200.100.5,5.8 kg
3 Tiebeam WF 200.100.5,5.8 kg
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg
5 Gording C 150.65.20.2,3 kg
6 Rangka Cladding C 150.65.20.2,3 kg
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

7 Rangka Listplank C 100.50.20.2,3 kg


8 Bracing Kolom L 60.60.6 kg
9 Penggantung Talang L 40.40.4 kg
10 Penggantung Talang Datar Plat Strip 40.4 kg
11 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg
12 Shear connector L 50.50.5 kg
13 Plat baja t= 18 mm kg
14 Plat baja t= 16 mm kg
15 Plat baja t= 12 mm kg
16 Plat baja t= 10 mm kg
17 Plat baja t= 8 mm kg
18 Plat baja t= 6 mm kg
19 Angkur Æ 22 mm ; L= 600- U-40 bh
20 Angkur Æ 19 mm ; L= 760 - U-50 bh
21 Angkur Æ 16 mm ; L= 650 - U-50 bh
22 Murbaut Æ 12 mm bh
23 Murbaut Æ 16 mm - A325 bh
24 Murbaut Æ 19 mm - A325 bh
25 Murbaut Æ 22 mm - A325 bh
26 Murbaut Æ 25 mm - A325 bh
27 Trekstang Æ 12 mm bh
28 Ikatan angin Æ 16 mm bh
29 Jarum keras Æ 16 mm bh
30 Sandblasting - Standart SA 2.5 kg
31 Cat baja F Talit ex. Kansai kg
32 Tangga
- Balok WF 250.125.6.9 Kg
- UNP 200.80.7,5.11 Kg
- Siku 40.40.4 Kg
- Plat Bordes 3,2 mm Kg
- Pipa Hitam 2 " Kg
- Plat t=12 mm Kg
- Plat t=6 mm Kg

SUB TOTAL PEKERJAAN D - IV

SUB TOTAL PEKERJAAN D

E BANGUNAN GUDANG DALAM PROSES BAKU (AS. 19-22)


E-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN E-I

E - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m'
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

2 Pemancangan m'
3 Potong Kepala tiang titik

SUB TOTAL PEKERJAAN E-II

E - III PEKERJAAN BETON


I PILE CAP
1 PC-1B
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

II RETAINING WALL
1 RETAINING WALL 8
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

III SLOOF
1 SL-40 A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2
2 SL-50 A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2
3 SL-50 B
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2

III PLAT LANTAI


PLAT LANTAI S2 (0.00M)
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

IV KOLOM
1 KOLOM K-350
- Beton f'c 25 m3
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
2 KOLOM K-450
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
SUB TOTAL PEKERJAAN E-III

E - IV PEKERJAAN BAJA
1 KOLOM BAJA
- Kolom WF 350.175.7.11 kg
- Kolom WF 250.125.6.9 kg
2 RANGKA KUDA-KUDA
- Rafter Castela 450.150.6,5.9 (WF 300.150.6,5.9) kg
- Voute WF 300.150.6,5.9 kg
- Rafter WF 250.125.6.9 kg
- Voute WF 250.125.6.9 kg
- Rafter WF 200.100.5,5.8 kg
- Voute WF 200.100.5,5.8 kg
3 Tiebeam WF 200.100.5,5.8 kg
4 Dudukan Rangka Cladding UNP 150.75.6,5.10 kg
5 Gording C 150.65.20.2,3 kg
6 Rangka Cladding C 150.65.20.2,3 kg
7 Rangka Listplank C 100.50.20.2,3 kg
9 Bracing Kolom L 60.60.6 kg
10 Penggantung Talang L 40.40.4 kg
11 Penggantung Talang Datar Plat Strip 40.4 kg
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg
14 Plat baja t= 12 mm kg
15 Plat baja t= 10 mm kg
16 Plat baja t= 8 mm kg
17 Plat baja t= 6 mm kg
18 Angkur Æ 19 mm ; L= 760 - U-50 bh
19 Angkur Æ 16 mm ; L= 650 - U-50 bh
20 Murbaut Æ 12 mm bh
21 Murbaut Æ 16 mm - A325 bh
22 Murbaut Æ 19 mm - A325 bh
24 Trekstang Æ 12 mm bh
25 Ikatan angin Æ 16 mm bh
26 Jarum keras Æ 16 mm bh
27 Sandblasting - Standart SA 2.5 kg
28 Cat baja F Talit ex. Kansai kg

SUB TOTAL PEKERJAAN E - IV


SUB TOTAL PEKERJAAN E

F GROUND TANK
F-I PEKERJAAN TANAH
1 Galian tanah m3
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN F-I

F - II PEKERJAAN PONDASI
2 Supply Tiang Pancang 250x250 mm m'
3 Pemancangan m'
4 Potong Kepala tiang titik

SUB TOTAL PEKERJAAN F-II

F - III PEKERJAAN BETON


I SLOOF
1 SL-60
- Lantai kerja B0 m3
- Beton fc' 30 m3
- Besi U - 40 kg
- Bekisting Bataco m2

II BALOK
1 B-30
- Lantai kerja B0 m3
- Beton fc' 30 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

2 B-40A
- Lantai kerja B0 m3
- Beton fc' 30 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2
3 B-40B
- Lantai kerja B0 m3
- Beton fc' 30 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2
4 CL-40
- Lantai kerja B0 m3
- Beton fc' 30 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

III WALL + SLAB


RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Lantai kerja Bo m3
- Beton fc' 30 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

IV KOLOM
1 KOLOM K-30
- Beton fc' 30 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
SUB TOTAL PEKERJAAN F-III
SUB TOTAL PEKERJAAN F

G R. GENSET
G- I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3

SUB TOTAL PEKERJAAN G-I

G - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m'
2 Pemancangan m'
3 Potong Kepala tiang titik

SUB TOTAL PEKERJAAN G-II

E - III PEKERJAAN BETON


I PC 2
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

II PONDASI GENSET
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

PONDASI TRAFO
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 24 kg
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi U - 40 kg
- Bekisting Bataco m2

R. GENSET
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 24 kg
- Besi U - 40 kg
- Bekisting Bataco m2

III SLOOF
1 SL-50 A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2
2 SL-50 B
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting Bataco m2

IV BALOK
B-50A
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

B-50B
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

LS-40
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

V PLAT LANTAI
LANTAI EV - 0.50
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

LANTAI EV +3.25
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

VI KOLOM
1 KOLOM K-30
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
SUB TOTAL PEKERJAAN G-III

SUB TOTAL PEKERJAAN G


H SALURAN
H-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3

SUB TOTAL PEKERJAAN H-I

H- II PEKERJAAN BETON
1 SALURAN A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting m2
- Siku L 40.40.4 kg
- Penebalan pengatur level m2

2 SALURAN A
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting m2
- Siku L 40.40.4 kg
- Penebalan pengatur level m2

SUB TOTAL PEKERJAAN H- II

SUB TOTAL PEKERJAAN H

I PAGAR DAN HALAMAN


I-I PEKERJAAN TANAH
1 Galian tanah m3
2 Urug kembali m3
3 Buang tanah m3
4 Urugan Sirtu + Pemadatan m3
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

SUB TOTAL PEKERJAAN I-I

I - II PEKERJAAN PONDASI
1 Supply Tiang Pancang 250x250 mm m'
2 Pemancangan m'
3 Potong Kepala tiang titik

SUB TOTAL PEKERJAAN I-II

I - III PEKERJAAN BETON


1 PAGAR
I RETAINING WALL 1-7
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
- Batu kali m3

2 WC
I RETAINING WALL 9
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
- Batu kali m3

II PLAT LANTAI
PLAT LANTAI S1 (-0.05M)
- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

3 TANGGA
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
- Underla m3

4 RAMP
I RETAINING WALL RAMP A AS D/4-5
- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
- Batu kali m3

2 RETAINING WALL RAMP B AS D'/10'-11'


RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Lantai kerja B0 m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
- Batu kali m3

PLAT LANTAI S1 (RAMP 1-2)


- Lantai kerja Bo m3
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2

SUB TOTAL PEKERJAAN I-III

I - IV PEKERJAAN BAJA WC
1 KOLOM BAJA
- Kolom WF 150.75.5.7 kg
2 RANGKA KUDA-KUDA
- WF 150.75.5.7 kg
- Voute WF 150.75.5.7 kg
3 Tiebeam WF 150.75.5.7 kg
5 Gording C 125.50.20.2,3 kg
7 Rangka Listplank C 75.40.20.2 kg
10 Penggantung Talang L 40.40.4 kg
11 Penggantung Talang Datar Plat Strip 40.4 kg
12 Begel talang turun plat strip 3x30 mm per jarak 1.50 m kg
16 Plat baja t= 8 mm kg
17 Plat baja t= 6 mm kg
19 Angkur Æ 16 mm ; L= 300 U-40 bh
20 Murbaut Æ 12 mm bh
21 Murbaut Æ 16 mm - A325 bh
24 Trekstang Æ 12 mm bh
25 Ikatan angin Æ 16 mm bh
26 Jarum keras Æ 16 mm bh
27 Sandblasting - Standart SA 2.5 kg
28 Cat baja F Talit ex. Kansai kg

SUB TOTAL PEKERJAAN I - IV


SUB TOTAL PEKERJAAN I

J PEKERJAAN LAIN-LAIN
1 - Kolom WF 250.125.6.9 (Bangunan Office) kg 612.08
2 KOLOM K-400 (Bangunan Gudang Bahan Baku (AS. 3 - 13)
- Beton f'c 25 m3
- Besi U - 40 kg
- Bekisting multiplek 12 mm ( expose ) m2
RENCANA ANGGARAN BIAYA
PROYEK : PT. DHARMA NYATA PRESS
PEKERJAAN : GEDUNG PERCETAKAN DAN GUDANG - JOMBANG

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

SUB TOTAL PEKERJAAN J

JUMLAH SUB PEKERJAAN


PROFIT 10% Rp -
JUMLAH Rp -
PPN 10% Rp -
GRAND TOTAL Rp -
PEMBULATAN Rp -

Note :
Mohon tidak merubah Format BQ, Apabila ada pekerjaan atau item yang belum tercantum silahkan dimasukkan
dalam pekerjaan lain-lain
RENCANA ANGGARAN BIAYA
PEMILIK : PT. DHARMA NYATA PRESS
PROYEK : JL. CENDRAWASIH - JOMBANG
PEKERJAAN : FINISHING ARSITEKTUR

NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

G PEKERJAAN FINISHING ATAP & CLADDING


I OFFICE 1-3
1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMTG550 AZ 150 m2
Height Rib 41mm ex Blue Scope Lysaght
2 Cladding Trimdek 0.40 TCT colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
3 Plat Cladding 0.4TCT Colourbond Plat Cladding Colourbond 0.40 TCT G550 AZ 150 m2
ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
4 Nok galvalum sheet t= 0,50 mm m'
5 Capping Flashing Galvalum sheet t= 0,50 mm natural ex Blue Scope Lysaght m'
6 Capping Flashing Clading Colourbond ex Blue Scope Lysaght
7 Talang tegak PVC 4" Type AW ex Wavin, Maspion m'
8 Knee Ø 4" Type AW ex Wavin, Maspion bh
9 Roof Drain Ø 4" Aluminium alloy bh
10 Insulasi Atap Zeltech ZT BF01 m2
11 Talang datar galvalum sheet t=0.5mm m
JUMLAH

II GUDANG AS. 3-13


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m'
7 Capping Flashing Galvalum sheet t= 0,50 mm m'
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght
9 Talang datar galvalum sheet t=0.5mm m
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m'
11 Knee 4 5" Type AW ex Wavin, Maspion bh
12 Roof Drain Ø 4" Aluminium alloy bh
13 Insulasi Atap Zeltech ZT BF01 m2
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2
- L 40.40.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh

JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

III PERCETAKAN AS. 13-19


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m'
7 Capping Flashing Galvalum sheet t= 0,50 mm m'
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght
9 Talang datar galvalum sheet t=0.5mm m
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m'
11 Knee 4 5" Type AW ex Wavin, Maspion bh
12 Roof Drain Ø 4" Aluminium alloy bh
13 Insulasi Atap Zeltech ZT BF01 m2
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2
- L 40.40.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh

JUMLAH

IV GUDANG AS. 19-22


1 Atap Kliplok Zincalume 0.45 BMT Kliplok Zincalume 0.45 BMT m2
G550 AZ 150 Height Rib 41mm
ex. Bluescope Lysaght
2 Lisplank Cladding Trimdek 0.40 TCT Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
3 Cladding Trimdek 0.40 TCT Colourbond Trimdek Colourbond 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
4 Cladding Trimdek 0.40 TCT natural zincalume Trimdek Zincalume 0.40 TCT G550 AZ 150 m2
Height rib 41mm ex Blue Scope Lysaght
5 Atap Polycarbonat Greca t=0.8mm Polikarbonant Greca m2
tebal = 0.8mm ex. Sunloid, warna = Grey
6 Nok galvalum sheet t= 0,50 mm m'
7 Capping Flashing Galvalum sheet t= 0,50 mm m'
8 Capping Flashing Clading Colourbond ex Blue Scope Lysaght
9 Talang datar galvalum sheet t=0.5mm m
10 Talang tegak PVC 4" Type AW ex Wavin, Maspion m'
11 Knee 4 5" Type AW ex Wavin, Maspion bh
12 Roof Drain Ø 4" Aluminium alloy bh
13 Insulasi Atap Zeltech ZT BF01 m2
14 Pas. Kawat loket
- Kawat Loket uk. 3x3cm tebal 2mm m2
- L 40.40.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

JUMLAH

TOTAL PEK ATAP CLADDING

H PEKERJAAN FINISHING ARSITEKTUR


I OFFICE AS.1-3
I.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2 52.57
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2 210.27
- benangan m'
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3
- Partisi Gypsum 12 mm Ex Jayaboard, Knauf m2
- Cover Kolom Kalsiboard 8mm Ex Calsi m2
- Partisi Kalsiboard 8mm Ex Calsi m2

2 Pekerjaan Lantai
- Keramik Lobby Granito 60x60 Pearl White ex Granito m2 42.09
- Keramik 40x40 area Office ex Platinum m2 195.44
- Keramik 40x40 area Tangga Utama ex Platinum m2 20.27
- Plin Lantai 10x60 Granito ex Granito m'
- Plin Lantai 10x40 Platinum ex Platinum m'

3 Pek Cat
- Cat dinding + kolom interior ex Dulux Pentalite m2
- Cat Plafon dak interior ex Dulux Pentalite m2
- Cat exterior ex Dulux weathershield m2
- Cat Partisi Gypsum,Calsiboard ex Dulux Pentalite m2

4 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2
- Waterprofing dinding+lantai ex Sika, Fosroc m2
- kran cuci T23BQ13N ex Toto bh
- Avour TX1BV1 ex Toto bh
- Closet CW 660J - SW 660J ex Toto bh
- Urinoir U57 M ex Toto bh
- Wastafel LW 237V3 - kran ex Toto bh
- Jet Shower TX403SB ex Toto bh
- Cermin bh

5 Plafon
- Plafon Calsioard 6mm ex Kalsiboard m2
- Plafon Gypsum 9mm ex Jayaboard m2
- List Plafon Shadow line ex Jayaboard m'
- Cat Plafond Gypsum, Calsiboard ex Dulux Pentalite m2

JUMLAH LANTAI 1

I.2 LANTAI 2
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2


- benangan m'
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3
- Partisi Gypsum 12 mm Ex Jayaboard, Knauf m2
- Cover Kolom Kalsiboard 8mm Ex Calsi m2
- Partisi Kalsiboard 8mm Ex Calsi m2

2 Pekerjaan Lantai
- Keramik 40x40 area Office ex Platinum m2
- Keramik 40x40 area Tangga Utama ex Platinum m2
- Plin Lantai 10x40 Platinum ex Platinum m'

3 Pek Cat
- Cat dinding + kolom interior ex Dulux Pentalite m2
- Cat Plafon dak interior ex Dulux Pentalite m2
- Cat exterior ex Dulux weathershield m2
- Cat Partisi Gypsum,Calsiboard ex Dulux Pentalite m2

4 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2
- Waterprofing dinding+lantai ex Sika, Fosroc m2
- kran cuci T23BQ13N ex Toto bh
- Avour TX1BV1 ex Toto bh
- Closet CW 660J - SW 660J ex Toto bh
- Urinoir U57 M ex Toto bh
- Wastafel LW 237V3 - kran ex Toto bh
- Jet Shower TX403SB ex Toto bh
- Cermin bh

5 Plafon
- Plafon Calsioard 6mm ex Kalsiboard m2
- Plafon Gypsum 9mm ex Jayaboard m2
- List Plafon Shadow line ex Jayaboard m'
- Cat Plafond Gypsum, Calsiboard ex Dulux Pentalite m2

4 Pek Railling Tangga Utama


- railling stainless pipa dia.2" stainless m'

JUMLAH LANTAI 2

TOTAL PEK FINISHING ARSITEKTUR OFFICE AS 1-3

II GUDANG AS. 3-13


II.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2
- benangan m2
- dinding roster rooster salip beton uk.20x40cm m2
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3

2 Pekerjaan Lantai
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

- Floorhardener 5kg/m2 natural ex Sika , Fosroc

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2
- Cat exterior ex Dulux weathershield m2

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2
- Hollow 40x40x1.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh
- Kawat nyamuk M40 aluminium m2

5 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2
- Waterprofing dinding+lantai ex Sika, Fosroc m2
- kran cuci T23BQ13N ex Toto bh
- Avour TX1BV1 ex Toto bh
- Closet Jongkok CE g ex Toto bh
- Wastafel LW 237V3 - kran ex Toto bh
- Jet Shower TX403SB ex Toto bh
- Cermin bh

TOTAL PEK FINISHING ARSITEKTUR GUDANG AS.3-13

III PERCETAKAN AS. 13-19


III.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2
- benangan m2
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3
- Partisi Calsiboard 8mm ex Calsi m2

2 Pekerjaan Lantai
- Floorhardener 5kg/m2 natural ex Sika , Fosroc m2
- Epoxy t=500 mikron ex Sika , Fosroc m2

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2
- Cat exterior ex Dulux weathershield m2

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2
- Hollow 40x40x1.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh
- Kawat nyamuk M40 aluminium m2

III.2 LANTAI 2
1 Pekerjaan Pasangan Dinding
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

- bata ringan ex Citicon, setara m2


- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2
- benangan m2
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3
- Partisi Calsiboard 8mm ex Calsi m2

2 Pekerjaan Lantai
- Epoxy t=500 mikron ex Sika , Fosroc m2

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2
- Cat exterior ex Dulux weathershield m2

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2
- Hollow 40x40x1.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh
- Kawat nyamuk M40 aluminium m2

PERCETAKAN AS.13-19

II GUDANG AS. 19-22


II.1 LANTAI 1
1 Pekerjaan Pasangan Dinding
- bata ringan ex Citicon, setara m2
- plesteran acian PM 210+PM310 ex Prime Mortar Setara m2
- benangan m2
- dinding roster rooster salip beton uk.20x40cm m2
- kolom praktis pembesian 4D10,Ø8-150 m3
- balok praktis pembesian 4D10,Ø8-150 m3

2 Pekerjaan Lantai
- Floorhardener 5kg/m2 natural ex Sika , Fosroc

3 Pek Cat
- Cat dinding + kolom interior ex Catylac m2
- Cat exterior ex Dulux weathershield m2

4 Pas. Kawat loket


- Kawat Loket uk. 3x3cm tebal 2mm m2
- Hollow 40x40x1.4 Kg
- Plat strip 40x4 Kg
- Wirebrush dan cat finish Kg
- Murbaut dia.6mm bh
- Kawat nyamuk M40 aluminium m2

5 Pek Area Toilet


- Pas Keramik Dinding 20x25 ex Asia Tile Excel White m2
- Pas Keramik Lantai 20x20 ex Asia Tile Alpha Grey m2
- Waterprofing dinding+lantai ex Sika, Fosroc m2
- kran cuci T23BQ13N ex Toto bh
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

- Avour TX1BV1 ex Toto bh


- Closet Jongkok CE g ex Toto bh
- Wastafel LW 237V3 - kran ex Toto bh
- Jet Shower TX403SB ex Toto bh
- Cermin bh

TOTAL PEK FINISHING ARSITEKTUR GUDANG AS.19-22

TOTAL PEK FINISHING ARSITEKTUR KESELURUHAN

I PEKERJAAN ALUMUNIUM
I OFFICE AS.1-3
I.1 LANTAI 1
1 Pintu P1 Ex Atlantik unit
2 Pintu P2 Dilengkapi Door Closser unit
3 Pintu P3 Ex Atlantik unit
4 Pintu P4 Ex Atlantik unit
5 Pintu P5 Ex Atlantik unit
6 Pintu PJ1 Dilengkapi Door Closser unit
7 Pintu PJ2 Dilengkapi Door Closser unit
8 Pintu PJ3 Dilengkapi Door Closser unit
9 Pintu PJ4 Dilengkapi Door Closser unit
10 Pintu PJ5 Dilengkapi Door Closser unit
11 Jendela J1 unit
12 Jendela J2 unit
13 Jendela J3 unit
14 Jendela J4 unit
15 Jendela J5 unit
16 Jendela J6 unit
17 Jendela J7 unit
18 Jendela J8 unit
19 Jendela J9 unit
20 Jendela J10 unit
21 Jendela J11 unit
22 Jendela J12 unit
23 Jendela J13 unit
24 Jendela J14 unit
25 Jendela J15 unit
26 Jendela J16 unit

JUMLAH LANTAI 1

I.2 LANTAI 2
1 Pintu P2 Dilengkapi Door Closser unit
2 Pintu PJ6 Dilengkapi Door Closser unit
3 Pintu PJ7 Dilengkapi Door Closser unit
4 Pintu PJ8 Dilengkapi Door Closser unit
5 Jendela J22 unit
6 Jendela J23 unit
7 Jendela J24 unit
8 Jendela J25 unit
9 Jendela J26 unit
10 Jendela J26' unit
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

11 Jendela J27 unit


12 Jendela J28 unit
13 Jendela J29 unit
14 Jendela J30 unit
15 Jendela J31 unit
16 Jendela J32 unit
17 Jendela J33 unit

JUMLAH LANTAI 2

TOTAL PEK ALUMUNIUM OFFICE AS.1-3


II GUDANG AS. 3-13
II.1 LANTAI 1
1 Pintu P5 Ex Atlantik unit
2 Jendela J17 unit
3 Jendela J17' unit
4 Jendela J18 unit
5 Jendela J19 unit
6 Jendela J20 unit
7 Jendela J21 unit
8 Jendela J34 unit
9 Jendela J34' unit
10 Jendela J35 unit
8 Pintu PR1 Rolling Door Otomatis Motor unit
9 Pintu PR2 Rolling Door Otomatis Motor unit
10 Pintu PR3 Rolling Door Otomatis Motor unit

TOTAL PEK ALUMUNIUM AREA GUDANG AS.3-13


III PERCETAKAN AS. 13-19
III.1 LANTAI 1
1 Pintu PR2 Rolling Door Otomatis Motor unit

JUMLAH LANTAI 1

III.2 LANTAI 2
1 Jendela J34 unit

JUMLAH LANTAI 2

TOTAL PEK ALUMUNIUM AREA PERCETAKAN AS 13-19


IV GUDANG AS. 19-22
IV.1 LANTAI 1
1 Jendela J34 unit

TOTAL PEK ALUMUNIUM AREA PERCETAKAN AS 13-19

TOTAL PEK ALUMUNIUM SELURUH

J PEKERJAAN POWERHOUSE
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

1 Pasangan dinding 1/2 Bata 1PC : 3PS m2


2 Pasangan dinding 1/2 Bata 1PC : 5PS m2
1 Pasangan dinding 1 Bata 1PC : 3PS m2
2 Pasangan dinding 1 Bata 1PC : 5PS m2
3 Plesteran plester aci dinding 1PC : 3PS m2
4 Plesteran plester aci dinding 1PC : 5PS m2
5 Pekerjaan Benangan m'
6 Pekerjaan Cat Dinding Interior Ex Catilac m2
7 Pekerjaan Cat Dinding Exterior ex Dulux weathershield m2
8 Pekerjaan Kolom dan Balok Praktis m3
9 Plesteran Balok kolom m2
10 Plesteran Plafon dak m2
11 Pekerjaan Cat Plafon Dak Beton Ex Catilac m2
12 Pekerjaan Pintu Besi P1 unit
13 Pas Keramik Lantai R Trafo, LVMD,Genset,R Pln Murano 30x30 m2

TOTAL PEK POWER HOUSE

K PEKERJAAN GROUND TANK


1 Waterprofing dinding+lantai ex Sika, Fosroc m2
2 Pas Keramik Murano 30x30 m2
3 tangga Stainless Steel unit
4 Tutup Manhole

TOTAL PEK GROUND TANK

L PEKERJAAN HALAMAN
1 Pagar Panel Beton
2 Pekerjaan Pembentukan Lahan
- Pemadatan eksisting
- Onderlaag + pengunci 15/20
- Pasang Paving K500 t=10cm Ex Focon setara
- Kanstin Ex Focon setara
TOTAL PEK HALAMAN

M PEKERJAAN LAIN LAIN

H PEKERJAAN FINISHING ARSITEKTUR


I OFFICE AS.1-3
I.1 LANTAI 1
2 Pekerjaan Lantai
- Keramik kamar mandi 20x20 ex Asia Tile
NO URAIAN PEKERJAAN SPESIFIKASI SAT VOLUME HARGA JUMLAH

SATUAN HARGA

TOTAL PEK LAIN-LAIN

Note :
Mohon tidak merubah Format BQ, Apabila ada pekerjaan atau item yang belum tercantum pada Format BQ
silahkan dimasukkan dalam pekerjaan lain-lain.
Segala sesuatu berkaitan dengan warna, model, dan type harus diasistensikan dahulu kepada owner.
Kontraktor berkewajiban : menambah, melengkapi,memperkuat pekerjaan yang ditawarkan (struktur & arsitektur)
sehingga hasil akhir pekerjaan dapat berfungsi dengan baik dan sempurna, walaupun di gambar dan BQ belum ada.

Anda mungkin juga menyukai