Bahan Cat
1 Cat Dasar Kg Rp. 20,000.00
2 Cat Kayu Kg Rp. 75,000.00
3 Cat Menie Kg Rp. 30,750.00
4 Cat Penutup Setara Jotun/Lenkote Kg Rp. 100,000.00
5 Cat Penutup Setara Avian Kg Rp. 30,000.00
6 Minyak Cat Liter Rp. 10,000.00
7 Minyak Bekesting Liter Rp. 6,500.00
8 Plamur Kg Rp. 25,000.00
9 Sealant Tube Rp. 40,000.00
10 Amplas Lembar Rp. 8,000.00
11 Kuas Cat 2" Bh Rp. 10,000.00
12 Kuas Cat 4" Bh Rp. 15,000.00
13 Roll cat Bh Rp. 25,000.00
Bahan Kaca
1 Kaca Polos tebal 5 mm m2 Rp. 160,000.00
Bahan Elektrikal
1 Lampu (LED) 19 WATT Bh Rp. 110,000.00
2 Lampu (LED) 11 WATT Bh Rp. 50,000.00
3 Saklar Ganda bh Rp. 30,000.00
4 Saklar Tunggal bh Rp. 25,000.00
5 Stop Kontak Tunggal bh Rp. 25,000.00
6 Pipa listrik 5/8” btg Rp. 10,000.00
7 Kabel NYA 1x2,5 mm2 m Rp. 3,500.00
8 Tee Doos bh Rp. 2,000.00
9 L.Bow bh Rp. 750.00
10 Las Dop bh Rp. 1,000.00
11 Klem Pipa Listrik bh Rp. 500.00
12 Mongkok (Listrik) bh Rp. 5,000.00
13 Fitting lampu bh Rp. 20,000.00
14 MCB 1 group unit Rp. 30,000.00
15 MCB 2 group unit Rp. 50,000.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang Kayu L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.005 Rp. 160,000.00 Rp. 800.00
Jumlah Tenaga Kerja (A) Rp. 29,900.00
B BAHAN
Kayu 4/6 M3 0.012 Rp. 3,300,000.00 Rp. 39,600.00
Paku Kayu 2" - 3" Kg 0.020 Rp. 20,000.00 Rp. 400.00
Papan Kayu Kelas IV m3 0.007 Rp. 2,700,000.00 Rp. 18,900.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.750 Rp. 125,000.00 Rp. 93,750.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.025 Rp. 160,000.00 Rp. 4,000.00
Jumlah Tenaga Kerja (A) Rp. 97,750.00
B BAHAN
Pengurugan Kembali 1 m3 Galian Dihitung dari 1/3 kali Koefisien Pekerjaan Galian
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 Rp. 125,000.00 Rp. 62,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.050 Rp. 160,000.00 Rp. 8,000.00
Jumlah Tenaga Kerja (A) Rp. 70,500.00
B BAHAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 39,100.00
B BAHAN
Pasir Urug m3 1.200 Rp. 200,000.00 Rp. 240,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 39,100.00
B BAHAN
Tanah Urug m3 1.200 Rp. 100,000.00 Rp. 120,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.500 Rp. 125,000.00 Rp. 187,500.00
Tukang L.02 OH 0.750 Rp. 150,000.00 Rp. 112,500.00
Kepala Tukang L.03 OH 0.075 Rp. 160,000.00 Rp. 12,000.00
Mandor L.04 OH 0.075 Rp. 160,000.00 Rp. 12,000.00
Jumlah Tenaga Kerja (A) Rp. 324,000.00
B BAHAN
Batu Kali / Batu Belah m3 1.200 Rp. 250,000.00 Rp. 300,000.00
Semen Kg 163.000 Rp. 1,500.00 Rp. 244,500.00
Pasir Pasang m3 0.520 Rp. 220,000.00 Rp. 114,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.780 Rp. 125,000.00 Rp. 97,500.00
Tukang Batu L.02 OH 0.390 Rp. 150,000.00 Rp. 58,500.00
Kepala Tukang L.03 OH 0.039 Rp. 160,000.00 Rp. 6,240.00
Mandor L.04 OH 0.039 Rp. 160,000.00 Rp. 6,240.00
Jumlah Tenaga Kerja (A) Rp. 168,480.00
B BAHAN
Batu Kali / Batu Belah m3 1.200 Rp. 250,000.00 Rp. 300,000.00
Pasir Urug m3 0.432 Rp. 200,000.00 Rp. 86,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.200 Rp. 125,000.00 Rp. 150,000.00
Tukang L.02 OH 0.200 Rp. 150,000.00 Rp. 30,000.00
Kepala Tukang L.03 OH 0.020 Rp. 160,000.00 Rp. 3,200.00
Mandor L.04 OH 0.060 Rp. 160,000.00 Rp. 9,600.00
Jumlah Tenaga Kerja (A) Rp. 192,800.00
B BAHAN
Semen Kg 230.000 Rp. 1,500.00 Rp. 345,000.00
Pasir pasang Kg 893.000 Rp. 157.14 Rp. 140,328.57
Koral Beton Kg 1,027.000 Rp. 177.78 Rp. 182,577.78
Air Liter 200.000 Rp - Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 Rp. 125,000.00 Rp. 206,250.00
Tukang L.02 OH 0.275 Rp. 150,000.00 Rp. 41,250.00
Kepala Tukang L.03 OH 0.028 Rp. 160,000.00 Rp. 4,480.00
Mandor L.04 OH 0.083 Rp. 160,000.00 Rp. 13,280.00
Jumlah Tenaga Kerja (A) Rp. 265,260.00
B BAHAN
Semen Kg 326.000 Rp. 1,500.00 Rp. 489,000.00
Pasir Pasang kg 760.000 Rp. 157.14 Rp. 119,428.57
Batu pecah 1-2 cm Kg 1,029.000 Rp. 300.00 Rp. 308,700.00
Air Liter 215.000 Rp - Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.070 Rp. 125,000.00 Rp. 8,750.00
Tukang L.02 OH 0.070 Rp. 150,000.00 Rp. 10,500.00
Kepala Tukang L.03 OH 0.007 Rp. 160,000.00 Rp. 1,120.00
Mandor L.04 OH 0.004 Rp. 160,000.00 Rp. 640.00
Jumlah Tenaga Kerja (A) Rp. 21,010.00
B BAHAN
Besi Beton Polos Kg 10.500 Rp. 14,000.00 Rp. 147,000.00
Kawat Beton Kg 0.150 Rp. 25,000.00 Rp. 3,750.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.520 Rp. 125,000.00 Rp. 65,000.00
Tukang L.02 OH 0.260 Rp. 150,000.00 Rp. 39,000.00
Kepala Tukang L.03 OH 0.026 Rp. 160,000.00 Rp. 4,160.00
Mandor L.04 OH 0.026 Rp. 160,000.00 Rp. 4,160.00
Jumlah Tenaga Kerja (A) Rp. 112,320.00
B BAHAN
Kayu Kelas IV M3 0.045 Rp. 2,700,000.00 Rp. 121,500.00
Paku Biasa 5 cm - 10 cm Kg 0.300 Rp. 20,000.00 Rp. 6,000.00
Minyak Bekesting Liter 0.100 Rp. 6,500.00 Rp. 650.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 Rp. 125,000.00 Rp. 82,500.00
Tukang L.02 OH 0.330 Rp. 150,000.00 Rp. 49,500.00
Kepala Tukang L.03 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Mandor L.04 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Jumlah Tenaga Kerja (A) Rp. 142,560.00
B BAHAN
Kayu Kelas IV M3 0.040 Rp. 2,700,000.00 Rp. 108,000.00
Paku Biasa 5 cm - 10 cm Kg 0.400 Rp. 20,000.00 Rp. 8,000.00
Minyak Bekesting Liter 0.200 Rp. 6,500.00 Rp. 1,300.00
Kayu Kelas II M3 0.015 Rp. 3,300,000.00 Rp. 49,500.00
Multipleks 9 mm Lembar 0.350 Rp. 140,000.00 Rp. 49,000.00
Kayu Dolken Ø 8-10/400 cm Batang 2.000 Rp. 15,000.00 Rp. 30,000.00
Jumlah Harga Bahan (B) Rp. 245,800.00
C PERALATAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 Rp. 125,000.00 Rp. 82,500.00
Tukang L.02 OH 0.330 Rp. 150,000.00 Rp. 49,500.00
Kepala Tukang L.03 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Mandor L.04 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Jumlah Tenaga Kerja (A) Rp. 142,560.00
B BAHAN
Kayu Kelas IV M3 0.040 Rp. 2,700,000.00 Rp. 108,000.00
Paku Biasa 5 cm - 10 cm Kg 0.400 Rp. 20,000.00 Rp. 8,000.00
Minyak Bekesting Liter 0.200 Rp. 6,500.00 Rp. 1,300.00
Kayu Kelas II M3 0.018 Rp. 3,300,000.00 Rp. 59,400.00
Multipleks 9 mm Lembar 0.350 Rp. 140,000.00 Rp. 49,000.00
Kayu Dolken Ø 8-10/400 cm Batang 2.000 Rp. 15,000.00 Rp. 30,000.00
Jumlah Harga Bahan (B) Rp. 255,700.00
C PERALATAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang L.02 OH 0.225 Rp. 150,000.00 Rp. 33,750.00
Kepala Tukang L.03 OH 0.005 Rp. 160,000.00 Rp. 800.00
Mandor L.04 OH 0.025 Rp. 160,000.00 Rp. 4,000.00
Jumlah Tenaga Kerja (A) Rp. 51,050.00
B BAHAN
Baja Ringan C75 Btg 0.675 Rp. 130,000.00 Rp. 87,750.00
Baut (Skrup baja) Bh 28.000 Rp. 300.00 Rp. 8,400.00
Dynabolt Bh 1.600 Rp. 3,500.00 Rp. 5,600.00
Reng m' 1.850 Rp. 11,000.00 Rp. 20,350.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Jumlah Tenaga Kerja (A) Rp. 56,500.00
B BAHAN
Batu Bata Buah 70.000 Rp. 900.00 Rp. 63,000.00
Semen Kg 11.500 Rp. 1,500.00 Rp. 17,250.00
Pasir Pasang m3 0.0430 Rp. 220,000.00 Rp. 9,460.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH 0.150 Rp. 150,000.00 Rp. 22,500.00
Kepala Tukang L.03 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Mandor L.04 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Jumlah Tenaga Kerja (A) Rp. 64,800.00
B BAHAN
Semen Kg 6.240 Rp. 1,500.00 Rp. 9,360.00
Pasir Pasang m3 0.024 Rp. 220,000.00 Rp. 5,280.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 Rp. 125,000.00 Rp. 25,000.00
Tukang L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 43,200.00
B BAHAN
Semen Kg 3.250 Rp. 1,500.00 Rp. 4,875.00
AHSP A.4.4.3. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 Rp. 125,000.00 Rp. 87,500.00
Tukang Batu L.02 OH 0.350 Rp. 150,000.00 Rp. 52,500.00
Kepala Tukang L.03 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Mandor L.04 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Jumlah Tenaga Kerja (A) Rp. 151,200.00
B BAHAN
Keramik Uk. 40 x 40 cm bh 6.563 Rp. 13,000.00 Rp. 85,312.50
Semen Kg 8.190 Rp. 1,500.00 Rp. 12,285.00
Semen Warna Kg 0.500 Rp. 4,000.00 Rp. 2,000.00
Pasir Pasang m3 0.045 Rp. 220,000.00 Rp. 9,900.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.090 Rp. 125,000.00 Rp. 11,250.00
Tukang Batu L.02 OH 0.090 Rp. 150,000.00 Rp. 13,500.00
Kepala Tukang L.03 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Mandor L.04 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Jumlah Tenaga Kerja (A) Rp. 35,950.00
B BAHAN
Plint Keramik Uk. 10 x 40 cm bh 2.650 Rp. 4,000.00 Rp. 10,600.00
Semen Kg 1.140 Rp. 1,500.00 Rp. 1,710.00
Semen Warna Kg 0.003 Rp. 4,000.00 Rp. 12.00
Pasir Pasang m3 0.025 Rp. 220,000.00 Rp. 5,500.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang Kayu L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.005 Rp. 160,000.00 Rp. 800.00
Jumlah Tenaga Kerja (A) Rp. 29,900.00
B BAHAN
Multipleks 4 mm Lembar 0.375 Rp. 90,000.00 Rp. 33,750.00
Paku Tripleks Kg 0.030 Rp. 25,000.00 Rp. 750.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 Rp. 125,000.00 Rp. 6,250.00
Tukang Kayu L.02 OH 0.050 Rp. 150,000.00 Rp. 7,500.00
Kepala Tukang L.03 OH 0.005 Rp. 160,000.00 Rp. 800.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 400.00
Jumlah Tenaga Kerja (A) Rp. 14,950.00
B BAHAN
Lis Plafon Kayu Profil m 1.050 Rp. 5,000.00 Rp. 5,250.00
Paku Tripleks Kg 0.010 Rp. 25,000.00 Rp. 250.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 Rp. 125,000.00 Rp. 15,000.00
Tukang Kayu L.02 OH 0.060 Rp. 150,000.00 Rp. 9,000.00
Kepala Tukang L.03 OH 0.006 Rp. 160,000.00 Rp. 960.00
Mandor L.04 OH 0.006 Rp. 160,000.00 Rp. 960.00
Jumlah Tenaga Kerja (A) Rp. 25,920.00
B BAHAN
Seng Gelombang BJLS 20 Lembar 0.700 Rp. 90,000.00 Rp. 63,000.00
Baut (roofing) Bh 6.000 Rp. 600.00 Rp. 3,600.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 Rp. 125,000.00 Rp. 18,750.00
Tukang Kayu L.02 OH 0.070 Rp. 150,000.00 Rp. 10,500.00
Kepala Tukang L.03 OH 0.007 Rp. 160,000.00 Rp. 1,120.00
Mandor L.04 OH 0.008 Rp. 160,000.00 Rp. 1,200.00
Jumlah Tenaga Kerja (A) Rp. 31,570.00
B BAHAN
Nok Seng Plat Lembar 0.300 Rp. 35,000.00 Rp. 10,500.00
Baut (roofing) Bh 4.000 Rp. 600.00 Rp. 2,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.070 Rp. 125,000.00 Rp. 8,750.00
Tukang Cat / Pelitur L.02 OH 0.090 Rp. 150,000.00 Rp. 13,500.00
Kepala Tukang L.03 OH 0.006 Rp. 160,000.00 Rp. 960.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 480.00
Jumlah Tenaga Kerja (A) Rp. 23,690.00
B BAHAN
Cat Menie Kg 0.200 Rp. 30,750.00 Rp. 6,150.00
Plamur Kg 0.150 Rp. 25,000.00 Rp. 3,750.00
Cat Dasar Kg 0.170 Rp. 20,000.00 Rp. 3,400.00
Cat Kayu Kg 0.350 Rp. 75,000.00 Rp. 26,250.00
Minyak Cat Liter 0.030 Rp. 10,000.00 Rp. 300.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.028 Rp. 125,000.00 Rp. 3,500.00
Tukang Kayu L.02 OH 0.042 Rp. 150,000.00 Rp. 6,300.00
Kepala Tukang L.03 OH 0.0042 Rp. 160,000.00 Rp. 672.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 480.00
Jumlah Tenaga Kerja (A) Rp. 10,952.00
B BAHAN
Cat Dasar Kg 0.060 Rp. 20,000.00 Rp. 1,200.00
Cat Penutup Setara Avian Kg 0.090 Rp. 30,000.00 Rp. 2,700.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Upah - % 1.000 Rp. 71,500.00 Rp. 71,500.00
Jumlah Tenaga Kerja (A) Rp. 71,500.00
B BAHAN
Pipa listrik 5/8” btg 3.000 Rp. 10,000.00 Rp. 30,000.00
Kabel NYA 1x2,5 mm2 m 24.000 Rp. 3,500.00 Rp. 84,000.00
Tee Doos bh 3.000 Rp. 2,000.00 Rp. 6,000.00
L.Bow bh 4.000 Rp. 750.00 Rp. 3,000.00
Las Dop bh 3.000 Rp. 1,000.00 Rp. 3,000.00
Klem Pipa Listrik bh 24.000 Rp. 500.00 Rp. 12,000.00
Mongkok (Listrik) bh 1.000 Rp. 5,000.00 Rp. 5,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang Kayu L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.005 Rp. 160,000.00 Rp. 800.00
Jumlah Tenaga Kerja (A) Rp. 29,900.00
B BAHAN
Kayu 4/6 m3 0.012 Rp. 3,300,000.00 Rp. 39,600.00
Paku Kayu 2" - 3" Kg 0.020 Rp. 20,000.00 Rp. 400.00
Papan Kayu Kelas IV m3 0.007 Rp. 2,700,000.00 Rp. 18,900.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.750 Rp. 125,000.00 Rp. 93,750.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.025 Rp. 160,000.00 Rp. 4,000.00
Jumlah Tenaga Kerja (A) Rp. 97,750.00
B BAHAN
Pengurugan Kembali 1 m3 Galian Dihitung dari 1/3 kali Koefisien Pekerjaan Galian
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.500 Rp. 125,000.00 Rp. 62,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.050 Rp. 160,000.00 Rp. 8,000.00
Jumlah Tenaga Kerja (A) Rp. 70,500.00
B BAHAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 39,100.00
B BAHAN
Pasir Urug m3 1.200 Rp. 200,000.00 Rp. 240,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 39,100.00
B BAHAN
Tanah Urug m3 1.200 Rp. 100,000.00 Rp. 120,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.500 Rp. 125,000.00 Rp. 187,500.00
Tukang L.02 OH 0.750 Rp. 150,000.00 Rp. 112,500.00
Kepala Tukang L.03 OH 0.075 Rp. 160,000.00 Rp. 12,000.00
Mandor L.04 OH 0.075 Rp. 160,000.00 Rp. 12,000.00
Jumlah Tenaga Kerja (A) Rp. 324,000.00
B BAHAN
Batu Kali / Batu Belah m3 1.200 Rp. 250,000.00 Rp. 300,000.00
Semen Kg 163.000 Rp. 1,500.00 Rp. 244,500.00
Pasir Pasang m3 0.520 Rp. 220,000.00 Rp. 114,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.780 Rp. 125,000.00 Rp. 97,500.00
Tukang Batu L.02 OH 0.390 Rp. 150,000.00 Rp. 58,500.00
Kepala Tukang L.03 OH 0.039 Rp. 160,000.00 Rp. 6,240.00
Mandor L.04 OH 0.039 Rp. 160,000.00 Rp. 6,240.00
Jumlah Tenaga Kerja (A) Rp. 168,480.00
B BAHAN
Batu Kali / Batu Belah m3 1.200 Rp. 250,000.00 Rp. 300,000.00
Pasir Urug m3 0.432 Rp. 200,000.00 Rp. 86,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.200 Rp. 125,000.00 Rp. 150,000.00
Tukang L.02 OH 0.200 Rp. 150,000.00 Rp. 30,000.00
Kepala Tukang L.03 OH 0.020 Rp. 160,000.00 Rp. 3,200.00
Mandor L.04 OH 0.060 Rp. 160,000.00 Rp. 9,600.00
Jumlah Tenaga Kerja (A) Rp. 192,800.00
B BAHAN
Semen Kg 230.000 Rp. 1,500.00 Rp. 345,000.00
Pasir pasang Kg 893.000 Rp. 157.14 Rp. 140,328.57
Koral Beton Kg 1,027.000 Rp. 177.78 Rp. 182,577.78
Air Liter 200.000 Rp - Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 Rp. 125,000.00 Rp. 206,250.00
Tukang L.02 OH 0.275 Rp. 150,000.00 Rp. 41,250.00
Kepala Tukang L.03 OH 0.028 Rp. 160,000.00 Rp. 4,480.00
Mandor L.04 OH 0.083 Rp. 160,000.00 Rp. 13,280.00
Jumlah Tenaga Kerja (A) Rp. 265,260.00
B BAHAN
Semen Kg 326.000 Rp. 1,500.00 Rp. 489,000.00
Pasir Pasang kg 760.000 Rp. 157.14 Rp. 119,428.57
Batu pecah 1-2 cm Kg 1,029.000 Rp. 300.00 Rp. 308,700.00
Air Liter 215.000 Rp - Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.070 Rp. 125,000.00 Rp. 8,750.00
Tukang L.02 OH 0.070 Rp. 150,000.00 Rp. 10,500.00
Kepala Tukang L.03 OH 0.007 Rp. 160,000.00 Rp. 1,120.00
Mandor L.04 OH 0.004 Rp. 160,000.00 Rp. 640.00
Jumlah Tenaga Kerja (A) Rp. 21,010.00
B BAHAN
Besi Beton Polos Kg 10.500 Rp. 14,000.00 Rp. 147,000.00
Kawat Beton Kg 0.150 Rp. 25,000.00 Rp. 3,750.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.520 Rp. 125,000.00 Rp. 65,000.00
Tukang L.02 OH 0.260 Rp. 150,000.00 Rp. 39,000.00
Kepala Tukang L.03 OH 0.026 Rp. 160,000.00 Rp. 4,160.00
Mandor L.04 OH 0.026 Rp. 160,000.00 Rp. 4,160.00
Jumlah Tenaga Kerja (A) Rp. 112,320.00
B BAHAN
Kayu Kelas IV M3 0.045 Rp. 2,700,000.00 Rp. 121,500.00
Paku Biasa 5 cm - 10 cm Kg 0.300 Rp. 20,000.00 Rp. 6,000.00
Minyak Bekesting Liter 0.100 Rp. 6,500.00 Rp. 650.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 Rp. 125,000.00 Rp. 82,500.00
Tukang L.02 OH 0.330 Rp. 150,000.00 Rp. 49,500.00
Kepala Tukang L.03 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Mandor L.04 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Jumlah Tenaga Kerja (A) Rp. 142,560.00
B BAHAN
Kayu Kelas IV M3 0.040 Rp. 2,700,000.00 Rp. 108,000.00
Paku Biasa 5 cm - 10 cm Kg 0.400 Rp. 20,000.00 Rp. 8,000.00
Minyak Bekesting Liter 0.200 Rp. 6,500.00 Rp. 1,300.00
Kayu Kelas II M3 0.015 Rp. 3,300,000.00 Rp. 49,500.00
Multipleks 9 mm Lembar 0.350 Rp. 140,000.00 Rp. 49,000.00
Kayu Dolken Ø 8-10/400 cm Batang 2.000 Rp. 15,000.00 Rp. 30,000.00
Jumlah Harga Bahan (B) Rp. 245,800.00
C PERALATAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.660 Rp. 125,000.00 Rp. 82,500.00
Tukang L.02 OH 0.330 Rp. 150,000.00 Rp. 49,500.00
Kepala Tukang L.03 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Mandor L.04 OH 0.033 Rp. 160,000.00 Rp. 5,280.00
Jumlah Tenaga Kerja (A) Rp. 142,560.00
B BAHAN
Kayu Kelas IV M3 0.040 Rp. 2,700,000.00 Rp. 108,000.00
Paku Biasa 5 cm - 10 cm Kg 0.400 Rp. 20,000.00 Rp. 8,000.00
Minyak Bekesting Liter 0.200 Rp. 6,500.00 Rp. 1,300.00
Kayu Kelas II M3 0.018 Rp. 3,300,000.00 Rp. 59,400.00
Multipleks 9 mm Lembar 0.350 Rp. 140,000.00 Rp. 49,000.00
Kayu Dolken Ø 8-10/400 cm Batang 2.000 Rp. 15,000.00 Rp. 30,000.00
Jumlah Harga Bahan (B) Rp. 255,700.00
C PERALATAN
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang L.02 OH 0.225 Rp. 150,000.00 Rp. 33,750.00
Kepala Tukang L.03 OH 0.005 Rp. 160,000.00 Rp. 800.00
Mandor L.04 OH 0.025 Rp. 160,000.00 Rp. 4,000.00
Jumlah Tenaga Kerja (A) Rp. 51,050.00
B BAHAN
Baja Ringan C75 Btg 0.675 Rp. 130,000.00 Rp. 87,750.00
Baut (Skrup baja) Bh 28.000 Rp. 300.00 Rp. 8,400.00
Dynabolt Bh 1.600 Rp. 3,500.00 Rp. 5,600.00
Reng m' 1.850 Rp. 11,000.00 Rp. 20,350.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Jumlah Tenaga Kerja (A) Rp. 56,500.00
B BAHAN
Batu Bata Buah 70.000 Rp. 900.00 Rp. 63,000.00
Semen Kg 11.500 Rp. 1,500.00 Rp. 17,250.00
Pasir Pasang m3 0.0430 Rp. 220,000.00 Rp. 9,460.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 Rp. 125,000.00 Rp. 37,500.00
Tukang L.02 OH 0.150 Rp. 150,000.00 Rp. 22,500.00
Kepala Tukang L.03 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Mandor L.04 OH 0.015 Rp. 160,000.00 Rp. 2,400.00
Jumlah Tenaga Kerja (A) Rp. 64,800.00
B BAHAN
Semen Kg 6.240 Rp. 1,500.00 Rp. 9,360.00
Pasir Pasang m3 0.024 Rp. 220,000.00 Rp. 5,280.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 Rp. 125,000.00 Rp. 25,000.00
Tukang L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Jumlah Tenaga Kerja (A) Rp. 43,200.00
B BAHAN
Semen Kg 3.250 Rp. 1,500.00 Rp. 4,875.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.700 Rp. 125,000.00 Rp. 87,500.00
Tukang Batu L.02 OH 0.350 Rp. 150,000.00 Rp. 52,500.00
Kepala Tukang L.03 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Mandor L.04 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Jumlah Tenaga Kerja (A) Rp. 151,200.00
B BAHAN
Keramik Uk. 40 x 40 cm bh 6.563 Rp. 13,000.00 Rp. 85,312.50
Semen Kg 8.190 Rp. 1,500.00 Rp. 12,285.00
Semen Warna Kg 0.500 Rp. 4,000.00 Rp. 2,000.00
Pasir Pasang m3 0.045 Rp. 220,000.00 Rp. 9,900.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.090 Rp. 125,000.00 Rp. 11,250.00
Tukang Batu L.02 OH 0.090 Rp. 150,000.00 Rp. 13,500.00
Kepala Tukang L.03 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Mandor L.04 OH 0.035 Rp. 160,000.00 Rp. 5,600.00
Jumlah Tenaga Kerja (A) Rp. 35,950.00
B BAHAN
Plint Keramik Uk. 10 x 40 cm bh 2.650 Rp. 4,000.00 Rp. 10,600.00
Semen Kg 1.140 Rp. 1,500.00 Rp. 1,710.00
Semen Warna Kg 0.003 Rp. 4,000.00 Rp. 12.00
Pasir Pasang m3 0.025 Rp. 220,000.00 Rp. 5,500.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang Kayu L.02 OH 0.100 Rp. 150,000.00 Rp. 15,000.00
Kepala Tukang L.03 OH 0.010 Rp. 160,000.00 Rp. 1,600.00
Mandor L.04 OH 0.005 Rp. 160,000.00 Rp. 800.00
Jumlah Tenaga Kerja (A) Rp. 29,900.00
B BAHAN
Multipleks 4 mm Lembar 0.375 Rp. 90,000.00 Rp. 33,750.00
Paku Tripleks Kg 0.030 Rp. 25,000.00 Rp. 750.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.050 Rp. 125,000.00 Rp. 6,250.00
Tukang Kayu L.02 OH 0.050 Rp. 150,000.00 Rp. 7,500.00
Kepala Tukang L.03 OH 0.005 Rp. 160,000.00 Rp. 800.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 400.00
Jumlah Tenaga Kerja (A) Rp. 14,950.00
B BAHAN
Lis Plafon Kayu Profil m 1.050 Rp. 5,000.00 Rp. 5,250.00
Paku Tripleks Kg 0.010 Rp. 25,000.00 Rp. 250.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.120 Rp. 125,000.00 Rp. 15,000.00
Tukang Kayu L.02 OH 0.060 Rp. 150,000.00 Rp. 9,000.00
Kepala Tukang L.03 OH 0.006 Rp. 160,000.00 Rp. 960.00
Mandor L.04 OH 0.006 Rp. 160,000.00 Rp. 960.00
Jumlah Tenaga Kerja (A) Rp. 25,920.00
B BAHAN
Seng Gelombang BJLS 20 Lembar 0.700 Rp. 90,000.00 Rp. 63,000.00
Baut (roofing) Bh 6.000 Rp. 600.00 Rp. 3,600.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.150 Rp. 125,000.00 Rp. 18,750.00
Tukang Kayu L.02 OH 0.070 Rp. 150,000.00 Rp. 10,500.00
Kepala Tukang L.03 OH 0.007 Rp. 160,000.00 Rp. 1,120.00
Mandor L.04 OH 0.008 Rp. 160,000.00 Rp. 1,200.00
Jumlah Tenaga Kerja (A) Rp. 31,570.00
B BAHAN
Nok Seng Plat Lembar 0.300 Rp. 35,000.00 Rp. 10,500.00
Baut (roofing) Bh 4.000 Rp. 600.00 Rp. 2,400.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.070 Rp. 125,000.00 Rp. 8,750.00
Tukang Cat / Pelitur L.02 OH 0.090 Rp. 150,000.00 Rp. 13,500.00
Kepala Tukang L.03 OH 0.006 Rp. 160,000.00 Rp. 960.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 480.00
Jumlah Tenaga Kerja (A) Rp. 23,690.00
B BAHAN
Cat Menie Kg 0.200 Rp. 30,750.00 Rp. 6,150.00
Plamur Kg 0.150 Rp. 25,000.00 Rp. 3,750.00
Cat Dasar Kg 0.170 Rp. 20,000.00 Rp. 3,400.00
Cat Kayu Kg 0.350 Rp. 75,000.00 Rp. 26,250.00
Minyak Cat Liter 0.030 Rp. 10,000.00 Rp. 300.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.020 Rp. 125,000.00 Rp. 2,500.00
Tukang Cat / Pelitur L.02 OH 0.063 Rp. 150,000.00 Rp. 9,450.00
Kepala Tukang L.03 OH 0.0063 Rp. 160,000.00 Rp. 1,008.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 480.00
Jumlah Tenaga Kerja (A) Rp. 13,438.00
B BAHAN
Plamur Kg 0.100 Rp. 25,000.00 Rp. 2,500.00
Cat Dasar Kg 0.100 Rp. 20,000.00 Rp. 2,000.00
Cat Penutup Setara Jotun/Lenkote Kg 0.260 Rp. 100,000.00 Rp. 26,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Pekerja L.01 OH 0.028 Rp. 125,000.00 Rp. 3,500.00
Tukang Kayu L.02 OH 0.042 Rp. 150,000.00 Rp. 6,300.00
Kepala Tukang L.03 OH 0.0042 Rp. 160,000.00 Rp. 672.00
Mandor L.04 OH 0.003 Rp. 160,000.00 Rp. 480.00
Jumlah Tenaga Kerja (A) Rp. 10,952.00
B BAHAN
Cat Dasar Kg 0.060 Rp. 20,000.00 Rp. 1,200.00
Cat Penutup Setara Avian Kg 0.090 Rp. 30,000.00 Rp. 2,700.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A TENAGA
Upah - % 1.000 Rp. 71,500.00 Rp. 71,500.00
Jumlah Tenaga Kerja (A) Rp. 71,500.00
B BAHAN
Pipa listrik 5/8” btg 3.000 Rp. 10,000.00 Rp. 30,000.00
Kabel NYA 1x2,5 mm2 m 24.000 Rp. 3,500.00 Rp. 84,000.00
Tee Doos bh 3.000 Rp. 2,000.00 Rp. 6,000.00
L.Bow bh 4.000 Rp. 750.00 Rp. 3,000.00
Las Dop bh 3.000 Rp. 1,000.00 Rp. 3,000.00
Klem Pipa Listrik bh 24.000 Rp. 500.00 Rp. 12,000.00
Mongkok (Listrik) bh 1.000 Rp. 5,000.00 Rp. 5,000.00
I PEKERJAAN PERSIAPAN
1. 1 Pek. Direksi Keet / Barak Kerja / Gudang Ls 1.00 Unit 2,000,000.00 2,000,000.00
1. 2 Pek. Papan Nama Kegiatan Ls 1.00 Bh 350,000.00 350,000.00
1. 3 Pek. Pembersihan dan persiapan lahan Ls 1.00 Unit 1,000,000.00 1,000,000.00
1. 4 Pek. Pengukuran dan Pemasangan Bouwplank A.2.2.1.4 42.00 M' 102,120.00 4,289,040.00
1. 5 Pek. K3 konstruksi Ls 1.00 Unit 7,150,000.00 7,150,000.00
1. 6 Pek. Administrasi dan dokumentasi Ls 1.00 Unit 3,500,000.00 3,500,000.00
18,289,040.00
II PEKERJAAN TANAH
7,743,546.91
3. 1 Pek. Pemasangan Pondasi Batu Belah Campuran 1 SP : 4 PP A.3.2.1.2. 11.17 M3 1,130,335.00 12,625,841.95
3. 2 Pek. Pemasangan Batu Kosong ( Aanstamping ) A.3.2.1.9. 6.62 M3 638,112.00 4,224,301.44
16,850,143.39
IV PEKERJAAN BETON
37,762,747.80
42,248,073.00
23,128,029.00
7. 1 Pek. Pemasangan plafon tripleks tebal 4mm A.4.5.1.5. 100.31 M2 74,060.00 7,428,958.60
7. 2 Pek. Pemasangan rangka plafon A.4.6.1.19a. 100.31 M2 155,670.00 15,615,257.70
7. 3 Pek. Pemasangan list plafon kayu profil A.4.5.1.9. 105.60 M 23,517.00 2,483,395.20
25,527,611.50
VIII PEKERJAAN PENUTUP ATAP
8. 1 Pek. Pemasangan rangka atap baja ringan (Taso) A.4.2.1.22 131.92 M2 200,117.00 26,399,434.64
8. 2 Pek. Pemasangan atap seng gelombang A.4.5.2.39. 131.92 M2 106,398.00 14,036,024.16
8. 3 Pek. Pemasangan nok atap A.4.5.2.40. 34.25 M' 51,140.00 1,751,545.00
8. 4 Pek. Pemasangan lisplank GRC 9x200 mm Ls 41.20 M' 25,000.00 1,030,000.00
43,217,003.80
IX PEKERJAAN KAYU
9. 1 Pek. Pembuatan dan pemasangan kusen pintu dan kusen jendela A.4.6.1.2. 0.43 M3 8,568,650.00 3,684,519.50
9. 2 Pek. Pembuatan dan pemasangan daun pintu panel kayu A.4.6.1.5. 1.89 M2 883,200.00 1,669,248.00
9. 3 Pek. Pembuatan dan pemasangan daun jendela kaca hidup A.4.6.1.6. 3.90 M2 675,050.00 2,632,695.00
7,986,462.50
10. 1 Pek. Pemasangan 1 set kunci pintu A.4.6.2.4. 1.00 Set 516,370.00 516,370.00
10. 2 Pek. Pemasangan 1 buah engsel pintu A.4.6.2.5. 3.00 Bh 66,670.00 200,010.00
10. 4 Pek. Pemasangan 1 buah engsel jendela A.4.6.2.6. 20.00 Bh 49,360.00 987,200.00
10. 5 Pek. Pemasangan 1 buah tarikan jendela A.4.6.2.8a. 10.00 Bh 55,170.00 551,700.00
10. 6 Pek. Pemasangan 1 buah kait angin A.4.6.2.9. 20.00 Bh 78,170.00 1,563,400.00
10. 7 Pek. Pemasangan 1 buah kunci slot jendela A.4.6.2.11. 20.00 Bh 58,480.00 1,169,600.00
10. 8 Pek. Pemasangan kaca tebal 5 mm A.4.6.2.17. 4.42 M2 235,620.00 1,041,440.40
10. 9 Pek. Pengadaan dan Pemasangan teralis besi pintu Ls 1.89 M2 875,000.00 1,653,750.00
10. 10 Pek. Pengadaan dan Pemasangan teralis besi jendela Ls 5.85 M2 600,000.00 3,510,000.00
11,193,470.40
XI PEKERJAAN PENGECATAN
12,001,806.85
12. 1 Pek. Pemasangan instalasi titik api A.8.4.6.2 21.00 Titik 246,675.00 5,180,175.00
12. 2 Pek. Pemasangan Lampu (LED) 19 WATT Ls 3.00 Bh 110,000.00 330,000.00
12. 3 Pek. Pemasangan Lampu (LED) 11 WATT Ls 4.00 Bh 50,000.00 200,000.00
12. 4 Pek. Pemasangan Fitting Lampu Ls 7.00 Bh 20,000.00 140,000.00
12. 5 Pek. Pemasangan Saklar Ganda Ls 1.00 Bh 30,000.00 30,000.00
12. 6 Pek. Pemasangan Saklar tunggal Ls 1.00 Bh 25,000.00 25,000.00
12. 7 Pek. Pemasangan Stop Kontak Tunggal Ls 9.00 Bh 25,000.00 225,000.00
12. 8 Pek. Pemasangan MCB 1 group Ls 2.00 Bh 30,000.00 60,000.00
12. 9 Pek. Pemasangan MCB 2 group Ls 1.00 Bh 50,000.00 50,000.00
12. 10 Pek. Biaya Pasang Baru Listrik (Daya 2.200 watt) (baru) + SLO Ls 1.00 Unit 3,500,000.00 3,500,000.00
9,740,175.00
9,627,640.00
47,500,000.00
XV PEKERJAAN LAIN-LAIN
2,500,000.00
REKAPITULASI
JUMLAH 315,315,750.146
PPN 11% 34,684,732.516
JUMLAH TOTAL 350,000,482.662
DIBULATKAN 350,000,000.000
2 Galian tanah
total
di bawah pondasi
teras
ruang lab
total
rabat keliling
bawah saluran
bawah teras
bawah ruang lab
total
beton 1:2:3
8 Beton sloof 15/20
9 pembesian
dikurangi jendela
dikurangi ventilasi
dikurangi pintu
total
15 Plesteran
16 Acian
ruang lab
teras
total
ruang lab
teras
total
19 Pemasangan plafon tripleks tebal 4mm
ruang lab
terasdepan
teras belakang
teras samping
total
kusen pintu
kusen jendela
ventilasi
total
total
total
cat lisplank
subtot
dikurangi luasan jendela
dikurangi luasan pintu
dikurangi luasan vent
total
21 Pengecatan plafon
11 10
41.4 0.8
42.8 0.46
41.4 0.8
7.85 1.85
7.85 6.85
41.4 0.45
41.4 0.8
38 0.9
42.8 0.46
7.85 1.85
7.85 6.85
39.4 0.15
3.6 0.1
3.8 0.2
41.87 0.13
39.4 0.2
3.6 0.1
3.8 0.2
41.87 0.15
29.2 3.6
2.04 0.77
0.46 0.21
2.18 1.02
7.85 6.8
8.2 2
0.2 0.2
29.3
7.18
7.85 6.85
9.75 2.8
9.75 0.8
7.15 0.8
cad
11.2 10.2
8.314088
1
5.06 0.12
6.68 0.12
1.22 0.12
2.1 0.9
0.65 0.6
0.51 0.46
0.67 0.62
2.1 0.9
0.65 0.6
6.68 0.06
2.5 0.12
2.18 0.08
5.06 0.06
4.94 0.12
2.1 0.9
41.2 0.2
105.6 0.03
29.3 3.3
8.2 3.05
7.2 3.3
8.2 3.3
3.15 0.8
2.04 0.77
2.18 1.02
0.46 0.21
43.8
t j v satuan
42 m
0.85 1 28.152 m3
0.2 1 3.9376 m3
32.0896 m3
0.05 1 1.656 m3
0.18 1 2.61405 m3
0.23 1 12.36767 m3
14.98172 m3
0.6 1 11.178 m3
0.2 1 6.624 m3
0.1 1 3.42 m3
0.05 1 0.9844 m3
0.05 1 0.726125 m3
0.05 1 2.688625 m3
7.81915 m3
0.2 1 1.182 m3
0.1 4 0.144 m3
0.2 12 1.824 m3
0.15 1 0.816465 m3
2 15.76 m2
16 5.76 m2
48 36.48 m2
2 12.561 m2
105.12 m2
5 7.854 m2
36 3.4776 m2
1 2.2236 m2
91.5648 m2
183.1296 m2
183.1296 m2
53.38 m2
16.4 m2
4 0.16 m2
69.62 m2
29.3 m
7.18 m
36.48 m
53.7725 m2
27.3 m2
7.8 m2
2 11.44 m2
100.3125 m2
100.3125 m2
105.6 m
131.9169 m2
131.9169 m2
4 33.25635 m
1m
34.25635 m
41.2 m
0.06 1 0.036432 m3
0.06 5 0.24048 m3
0.03 36 0.158112 m3
0.435024 m3
1 1.89 m2
10 3.9 m2
1 bh
3 bh
20 bh
10 bh
20 bh
20 bh
10 2.346 m2
5 2.077 m2
4.423 m2
1 1.89 m2
15 5.85 m2
7.74 m2
10 4.008 m2
15 4.5 m2
20 3.488 m2
2 0.6072 m2
1 0.5928 m2
2 3.78 m2
1 8.24 m2
1 3.168 m2
28.384 m2
96.69 m2
25.01 m2
23.76 m2
27.06 m2
2.52 m2
175.04 m2
5 7.854 m2
1 2.2236 m2
36 3.4776 m2
161.4848 m2
100.3125 m2
19 titik
5 bh
5 bh
1 bh
1 bh
9 Bh
3 bh
43.8 m
No Bentuk Pot dia
1 sloof 15/20 10
sengkang 8
total
2 kolom 10/10 8
sengkang 6
total
3 kolom 20/20 10
sengkang 8
total
sengkang 8
total
total
Jarak P.Pot J.Pot J.Pnjng Berat/m J.Berat Sat
151.12 kg
27.03 kg
189.47 kg
147.44 kg
515.06 kg
RINCIAN BIAYA K3
NAMA PEKERJAAN : Pembangunan Laboratorium Komputer Beserta Perabotnya SDN 07 Penarik, SDN 06 Penarik, SDN 08 Penarik,
SDN 09 Penarik, SDN 04 Penarik
JENIS PEKERJAAN : Penyelenggaraan Keamanan dan Kesehatan Kerja serta Keselamatan Konstruksi
LOKASI : KABUPATEN MUKOMUKO
TAHUN ANGGARAN : 2021 ###
HARGA JUMLAH
SATUAN KUANTITAS
NO URAIAN PEKERJAAN KODE SATUAN HARGA
1 2.1 APD : - -
1 - Topi pelindung (Safety Helmet) Ls Bh 8.00 50,000.00 400,000.00
1 - Pelindung pernafasan dan mulut (Masker) Ls Box 1.00 50,000.00 50,000.00
1 - Sarung tangan (Safety Gloves) Ls Psg 50.00 5,000.00 250,000.00
1 - Sepatu keselamatan (Safety Shoes) Ls Psg 8.00 100,000.00 800,000.00
1 - Rompi keselamatan (Safety Vest) Ls Bh 8.00 50,000.00 400,000.00
3 PERSONIL K3 KONSTRUKSI
1 4.1 Peralatan P3K (Kotak P3K, Tandu, Obat Luka, Perban,dll) Ls set 1.00 200,000.00 200,000.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH 6.667 Rp. 125,000.00 Rp. 833,375.00
Tukang Kayu L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.333 Rp. 160,000.00 Rp. 53,280.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH 0.01 Rp. 125,000.00 Rp. 1,250.00
Tukang Kayu L.02 OH 0.050 Rp. 150,000.00 Rp. 7,500.00
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH - Rp. 160,000.00 Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH 0.100 Rp. 125,000.00 Rp. 12,500.00
Tukang Kayu L.02 OH 0.025 Rp. 150,000.00 Rp. 3,750.00
Kepala Tukang L.03 OH 0.003 Rp. 160,000.00 Rp. 400.00
Mandor L.04 OH 0.005 Rp. 160,000.00 Rp. 800.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH 0.040 Rp. 125,000.00 Rp. 5,000.00
Tukang Kayu L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.020 Rp. 160,000.00 Rp. 3,200.00
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH - Rp. 125,000.00 Rp -
Tukang Kayu L.02 OH 1.000 Rp. 150,000.00 Rp. 150,000.00
Kepala Tukang L.03 OH 0.100 Rp. 160,000.00 Rp. 16,000.00
Mandor L.04 OH - Rp. 160,000.00 Rp -
Jumlah Harga
Harga Satuan
No. Uraian Kode Satuan Koefisien
(Rp.)
(Rp.)
A
Pekerja L.01 OH 0.020 Rp. 125,000.00 Rp. 2,500.00
Tukang Kayu L.02 OH - Rp. 150,000.00 Rp -
Kepala Tukang L.03 OH - Rp. 160,000.00 Rp -
Mandor L.04 OH 0.001 Rp. 160,000.00 Rp. 160.00