1 2 3 4
PEKERJAAN PEMBORONGAN
PEKERJAAN PERSIAPAN
1 1 m2 Pembersihan Lapangan dan Peralatan
Upah An. SNI ( Revisi ) 6.8.1
0.1000 Oh Pekerja @ Rp. 100,000.00 = Rp 10,000.00
0.0500 Oh Mandor @ Rp. 0.00 = Rp 0.00
= Rp 10,000.00
Harga 1 m2 = Rp 10,000.00
-3-
Upah An. SNI ( Revisi ) 6.3.2
0.2000 Oh Tukang Kayu @ Rp. 120,000.00 = Rp 24,000.00
0.3000 Oh Pekerja @ Rp. 100,000.00 = Rp 30,000.00
0.0200 Oh Kepala Tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0200 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 56,500.00
Total Upah dan Bahan = Rp #REF!
-4-
0.7000 kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 9,940.00
1.5000 Lbr Seng gelombang bljs 32 @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
-5-
11 1 m2 Pembuatan jalan sementara
Bahan An. SNI ( Revisi ) 6.12.1
0.1500 m3 Batu belah 15/20 @ Rp. #REF! = Rp #REF!
0.0900 m3 Batu pecah 5/7 @ Rp. #REF! = Rp #REF!
0.0100 m3 Pasir pasang @ Rp. 165,000.00 = Rp 1,650.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.12.2
1.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 100,000.00
0.0500 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 100,000.00
Total Upah dan Bahan = Rp #REF!
-6-
Sub total : = Rp 9,740.00
Total Upah dan Bahan = Rp #REF!
-7-
1.2000 Oh Pekerja @ Rp. 100,000.00 = Rp. 120,000.00
0.0450 Oh Mandor @ Rp. 0.00 = Rp. 0.00
= Rp. 120,000.00
Total Upah = Rp 120,000.00
-8-
0.0800 Oh Mandor @ Rp. 0.00 = Rp. 0.00
Sub total : = Rp. 133,000.00
Total Upah + bahan = Rp #REF!
16 1 m3 Urugan sirtu
Bahan An. SNI ( Revisi ) 6.15.1
1.2000 m3 Sirtu @ Rp. 102,000.00 = Rp. 122,400.00
Sub total : = Rp. 122,400.00
-9-
1 - Menguruk sirtu per M3 (An- SNI -revisi 6.15.)
(Jarak dengan penggambilan sirtu +/- 10 Km)
Bahan
An. SNI ( Revisi ) 6.15.1 = Rp. 122,400.00
Upah
An. SNI ( Revisi ) 6.15.2 = Rp. 30,000.00
Sub total : = Rp. 152,400.00
### Biaya transportasi. 1,500.00 = Rp. 1,500.00
Total Biaya / M3 = Rp 153,900.00
- 10 -
Sub total : = Rp. 152,400.00
### Biaya transportasi. 1,500.00 = Rp. 2,013.00
Total Biaya / M3 = Rp 154,413.00
PEKERJAAN PONDASI
1 1 m3 Pasang pondasi batu kosong (Aanstamping)
Bahan An. SNI ( Revisi ) 6.14.1
1.2000 m3 Batu belah ( 15/20 ) @ Rp. 200,000.00 = Rp 240,000.00
0.4320 m3 Pasir urug @ Rp. 175,000.00 = Rp 75,600.00
Sub total : = Rp 315,600.00
Upah An. SNI ( Revisi ) 6.14.2
0.7800 Oh Pekerja @ Rp. 100,000.00 = Rp 78,000.00
0.3900 Oh Tukang batu @ Rp. 120,000.00 = Rp 46,800.00
0.0390 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,875.00
0.0390 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 129,675.00
- 11 -
Total upah+bahan : = Rp 445,275.00
- 12 -
6 1 m3 Pasang pondasi batu kali 1 Pc : 4 Ps
Bahan An. SNI ( Revisi ) 6.5.1
1.2000 m3 Batu belah ( 15/20 ) @ Rp. #REF! = Rp #REF!
163.0000 kg Semen porland @ Rp. 1,675.00 = Rp 273,025.00
0.5200 m3 Pasir pasang @ Rp. 165,000.00 = Rp 85,800.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.5.2
1.5000 Oh Pekerja @ Rp. 100,000.00 = Rp 150,000.00
0.6000 Oh Tukang batu @ Rp. 120,000.00 = Rp 72,000.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 229,500.00
Total upah+bahan : = Rp #REF!
- 13 -
10 1 m3 Pasang pondasi batu kali 1 Kp : 1 Sm : 1 Ps
Bahan An. SNI ( Revisi ) 6.9.1
1.2000 m3 Batu belah ( 15/20 ) @ Rp. #REF! = Rp #REF!
0.1700 m3 Kapur pasang @ Rp. 544,000.00 = Rp 92,480.00
0.1700 m3 Semen merah @ Rp. #REF! = Rp #REF!
0.3400 m3 Pasir pasang @ Rp. 165,000.00 = Rp 56,100.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.9.2
1.5000 Oh Pekerja @ Rp. 100,000.00 = Rp 150,000.00
0.7500 Oh Tukang batu @ Rp. 120,000.00 = Rp 90,000.00
0.0750 Oh Kepala tukang @ Rp. 125,000.00 = Rp 9,375.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 249,375.00
Total upah+bahan : = Rp #REF!
- 14 -
Sub total : = Rp 196,875.00
Total upah+bahan : = Rp 700,198.00
- 15 -
0.0320 m3 Kayu meranti 5/7 @ Rp. #REF! = Rp #REF!
0.1200 Kg Paku @ Rp. 14,200.00 = Rp 1,704.00
0.0900 Lt Minyak bekisting @ Rp. 11,550.00 = Rp 1,039.50
0.2400 Kg Plamuur tembok @ Rp. 17,050.00 = Rp 4,092.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.17.2
1.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 100,000.00
0.6700 Oh Tukang batu @ Rp. 120,000.00 = Rp 80,400.00
0.0670 Oh Kepala tukang @ Rp. 125,000.00 = Rp 8,375.00
0.0500 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 188,775.00
Total upah+bahan : = Rp #REF!
Jadi harga 1 Meter Tiang pancang ukuran 40 x 40 Cm2 = Rp #REF!
PEKERJAAN PASANGAN
1 1 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps
Bahan An. SNI ( Revisi ) 6.1.1
140.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 91,000.00
55.6000 kg Semen portland @ Rp. 1,675.00 = Rp 93,130.00
0.0560 m3 Pasir pasang @ Rp. 165,000.00 = Rp 9,240.00
Sub total : = Rp 193,370.00
Upah An. SNI ( Revisi ) 6.1.2
0.6000 Oh Pekerja @ Rp. 100,000.00 = Rp 60,000.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0300 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 86,500.00
Total upah+bahan /m = Rp 279,870.00
Total per : M3 = Rp 916,627.31
- 16 -
Sub total : = Rp 177,062.50
Upah An. SNI ( Revisi ) 6.2.2
0.6000 Oh Pekerja @ Rp. 100,000.00 = Rp 60,000.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0300 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 86,500.00
Total upah+bahan : = Rp 263,562.50
Total per : M3 = Rp 867,030.29
- 17 -
140.0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 91,000.00
19.5000 kg Semen portland @ Rp. 1,675.00 = Rp 32,662.50
0.1220 m3 Pasir pasang @ Rp. 165,000.00 = Rp 20,130.00
Sub total : = Rp 143,792.50
Upah An. SNI ( Revisi ) 6.6.2
0.6000 Oh Pekerja @ Rp. 100,000.00 = Rp 60,000.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0300 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 86,500.00
Total upah+bahan : = Rp 230,292.50
Total per : M3 = Rp 764,130.29
- 18 -
Total per : M3 = Rp 831,874.13
- 19 -
0.0150 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 43,250.00
Total upah+bahan : = Rp 110,771.00
Total per : M3 = Rp 728,440.92
- 20 -
0.0140 m3 Kapur padam @ Rp. 544,000.00 = Rp 7,616.00
Sub total : = Rp 57,759.45
Upah An. SNI ( Revisi ) 6.17.2
0.3000 Oh Pekerja @ Rp. 100,000.00 = Rp 30,000.00
0.1000 Oh Tukang batu @ Rp. 120,000.00 = Rp 12,000.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0150 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 43,250.00
Total upah+bahan : = Rp 101,009.45
Total per : M3 = Rp 658,398.09
- 21 -
0.0150 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 49,875.00
Total upah+bahan : = Rp 78,605.00
Total per : M3 = Rp 261,714.58
PEKERJAAN PLESTERAN
1 1 m2 Plesteran, 1 Pc : 1 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.1.1
15.5040 kg Semen portland @ Rp. 1,675.00 = Rp 25,969.20
0.0160 m3 Pasir pasang @ Rp. 165,000.00 = Rp 2,640.00
Sub total : = Rp 28,609.20
Upah An. SNI ( Revisi ) 6.1.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.1500 Oh Tukang batu @ Rp. 120,000.00 = Rp 18,000.00
0.0150 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,875.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 39,875.00
Total upah+bahan : = Rp 68,484.20
- 22 -
Sub total : = Rp 39,875.00
Total upah+bahan : = Rp 53,864.00
- 23 -
5.7600 kg Semen portland @ Rp. 1,675.00 = Rp 9,648.00
0.0030 m3 Kapur Padam @ Rp. 544,000.00 = Rp 1,632.00
0.0130 m3 Pasir pasang @ Rp. 165,000.00 = Rp 2,145.00
Sub total : = Rp 13,425.00
Upah An. SNI ( Revisi ) 6.8.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.1500 Oh Tukang batu @ Rp. 120,000.00 = Rp 18,000.00
0.0150 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,875.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 39,875.00
Total upah+bahan : = Rp 53,300.00
- 24 -
0.0022 m3 Kapur Padam @ Rp. 544,000.00 = Rp 1,196.80
0.0190 m3 Pasir pasang @ Rp. 165,000.00 = Rp 3,135.00
Sub total : = Rp 7,556.18
Upah An. SNI ( Revisi ) 6.10.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.1500 Oh Tukang batu @ Rp. 120,000.00 = Rp 18,000.00
0.0150 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,875.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 39,875.00
Total upah+bahan : = Rp 47,431.18
- 25 -
Upah An. SNI ( Revisi ) 6.14.2
0.2500 Oh Pekerja @ Rp. 100,000.00 = Rp 25,000.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,500.00
Total upah+bahan : = Rp 70,152.00
- 26 -
0.0133 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 53,166.67
Total upah+bahan : = Rp #REF!
- 27 -
23 1 m2 Plesteran, 1 Pc : 2 Ps, tebal 30 mm
Bahan An. SNI ( Revisi ) 6.23.1
17.0400 kg Semen portland @ Rp. 1,675.00 = Rp 28,542.00
0.0340 m3 Pasir pasang @ Rp. 165,000.00 = Rp 5,610.00
Sub total : = Rp 34,152.00
Upah An. SNI ( Revisi ) 6.23.2
0.3200 Oh Pekerja @ Rp. 100,000.00 = Rp 32,000.00
0.2500 Oh Tukang batu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0150 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 65,125.00
Total upah+bahan : = Rp 99,277.00
- 28 -
7.0700 kg Semen portland @ Rp. 1,675.00 = Rp 11,842.25
0.0210 m3 Pasir pasang @ Rp. 165,000.00 = Rp 3,465.00
Sub total : = Rp 15,307.25
1 m2 Berapen, 1 Pc : 5 Ps, tebal 30 mm
Upah An. SNI ( Revisi ) 6.27.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.0700 Oh Tukang batu @ Rp. 120,000.00 = Rp 8,400.00
0.0070 Oh Kepala tukang @ Rp. 125,000.00 = Rp 875.00
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 24,275.00
Total upah+bahan : = Rp 39,582.25
31 1 m2 Plesteran skoning, 1 Pc : 2 Ps
Bahan An. SNI ( Revisi ) 6.31.1
0.5000 kg Semen portland @ Rp. 1,675.00 = Rp 837.50
0.0020 m3 Pasir pasang @ Rp. 165,000.00 = Rp 330.00
- 29 -
Sub total : = Rp 1,167.50
Upah An. SNI ( Revisi ) 6.31.2
0.0570 Oh Pekerja @ Rp. 100,000.00 = Rp 5,700.00
0.0380 Oh Tukang batu @ Rp. 120,000.00 = Rp 4,560.00
0.0380 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,750.00
0.0020 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 15,010.00
Total upah+bahan : = Rp 16,177.50
- 30 -
1 m2 Plesteran siar / setrikan adukan, 1 Pc : 2 Ps
Upah An. SNI ( Revisi ) 6.35.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.0700 Oh Tukang batu @ Rp. 120,000.00 = Rp 8,400.00
0.0070 Oh Kepala tukang @ Rp. 125,000.00 = Rp 875.00
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 24,275.00
Total upah+bahan : = Rp 34,151.00
36 1 m' Benangan
Bahan 2.2500 kg Semen portland @ Rp. 1,675.00 = Rp 3,768.75
Sub total : = Rp 3,768.75
BETON TUMBUK
- 31 -
1.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 165,000.00
0.2500 Oh Tukang batu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0800 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 198,125.00
Total upah+bahan : = Rp 838,000.00
BETON BERTULANG
- 32 -
Upah An. SNI ( Revisi ) 6.7.2
1.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 165,000.00
0.2500 Oh Tukang batu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0800 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 198,125.00
Total upah+bahan : = Rp ###
- 33 -
Upah An. SNI ( Revisi ) 6.11.2
1.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 165,000.00
0.2500 Oh Tukang batu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0800 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 198,125.00
Total upah+bahan : = Rp ###
- 34 -
247.0000 kg PC @ Rp. 1,675.00 = Rp 413,725.00
869.0000 Kg Pasir Cor @ Rp. #REF! = Rp #REF!
999.0000 Kg Krikil (maksimum 30 mm) @ Rp. #REF! = Rp #REF!
215.0000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.18.2
1.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 165,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
0.0280 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,500.00
0.0830 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 201,500.00
Total upah+bahan : = Rp #REF!
4 Membuat 1 M3 LANTAI KERJA beton mutu f'c=7,4 Mpa (K100), slump 3-6 cm / W/c = 0,87.
- 35 -
0.0830 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 201,500.00
Total upah+bahan : = Rp #REF!
- 36 -
### Kg Krikil (maksimum 30 mm) @ Rp. #REF! = Rp #REF!
215.0000 Ltr Air. @ Rp. 2.50 = Rp 537.50
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.18.2
1.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 165,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
0.0280 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,500.00
0.0830 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 201,500.00
Total upah+bahan : = Rp #REF!
- 37 -
Total upah+bahan : = Rp #REF!
PEMBESIAN
- 38 -
0.0070 Oh Pekerja @ Rp. 100,000.00 = Rp 700.00
0.0070 Oh Tukang besi @ Rp. 120,000.00 = Rp 840.00
0.0007 Oh Kepala tukang @ Rp. 125,000.00 = Rp 87.50
0.0003 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 1,627.50
Total upah+bahan : = Rp #REF!
BEGESTING
- 39 -
0.2600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 31,200.00
0.0260 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,250.00
0.0260 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 86,450.00
Total upah+bahan : = Rp 227,990.00
- 40 -
23 1 m2 Pasang bekisting untuk dinding ( shear wall )
Bahan An. SNI ( Revisi ) 6.33.1
0.0300 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 90,750.00
0.4000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 5,680.00
0.2000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 2,310.00
0.0200 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 87,266.66
0.3500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.0000 Btg Dolken kayu galam Ø 8-10 / @ Rp. 56,000.00 = Rp 168,000.00
4.0000 Bh Formtie/penjaga jarak bkstn @ Rp. 35,000.00 = Rp 140,000.00
Sub total : = Rp 346,500.00
Upah An. SNI ( Revisi ) 6.33.2
0.6600 Oh Pekerja @ Rp. 100,000.00 = Rp 66,000.00
0.3300 Oh Tukang kayu @ Rp. 120,000.00 = Rp 39,600.00
0.0330 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,125.00
0.0330 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 109,725.00
Total upah+bahan : = Rp 456,225.00
PONDASI BETON
26 1 m3 Membuat pondasi beton bertulang ( 150 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.38.1
0.2000 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 605,000.00
1.5000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 21,300.00
0.4000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 4,620.00
157.5000 Kg Besi beton polos @ Rp. 11,500.00 = Rp 1,811,250.00
- 41 -
2.2500 Kg Kawat beton @ Rp. 16,500.00 = Rp 37,125.00
336.0000 kg Semen portland @ Rp. 1,675.00 = Rp 562,800.00
0.5400 m3 Pasir beton @ Rp. 225,000.00 = Rp 121,500.00
0.8100 m3 Koral beton @ Rp. 255,000.00 = Rp 206,550.00
Sub total : = Rp 3,370,145.00
Upah An. SNI ( Revisi ) 6.38.2
5.3000 Oh Pekerja @ Rp. 100,000.00 = Rp 530,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
1.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 156,000.00
1.0500 Oh Tukang besi @ Rp. 120,000.00 = Rp 126,000.00
0.2620 Oh Kepala tukang @ Rp. 125,000.00 = Rp 32,750.00
0.2650 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 877,750.00
Total upah+bahan : = Rp ###
Sloof
27 1 m3 Membuat sloof beton bertulang ( 200 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.39.1
0.2700 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 816,750.00
2.0000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 28,400.00
0.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 6,930.00
210.0000 Kg Besi beton polos @ Rp. 11,500.00 = Rp 2,415,000.00
3.0000 Kg Kawat beton @ Rp. 16,500.00 = Rp 49,500.00
336.0000 kg Semen portland @ Rp. 1,675.00 = Rp 562,800.00
0.5400 m3 Pasir beton @ Rp. 225,000.00 = Rp 121,500.00
0.8100 m3 Koral beton @ Rp. 255,000.00 = Rp 206,550.00
Sub total : = Rp 4,207,430.00
Upah An. SNI ( Revisi ) 6.39.2
5.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 565,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
1.5600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 187,200.00
1.4000 Oh Tukang besi @ Rp. 120,000.00 = Rp 168,000.00
0.3230 Oh Kepala tukang @ Rp. 125,000.00 = Rp 40,375.00
0.2830 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 993,575.00
Total upah+bahan : = Rp ###
28 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 5 dia 19 mm + beugel dia
Bahan An. SNI ( Revisi ) 6.39.1
0.2700 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 816,750.00
2.0000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 28,400.00
0.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 6,930.00
179.8590 Kg Besi beton polos dia 16 mm @ Rp. 11,500.00 = Rp 2,068,378.50
### 81.6563 Kg Besi begel polos dia 6 mm @ Rp. 11,500.00 = Rp 939,047.68
3.0000 Kg Kawat beton @ Rp. 16,500.00 = Rp 49,500.00
323.0000 kg Semen portland @ Rp. 1,675.00 = Rp 541,025.00
0.5200 m3 Pasir beton @ Rp. 225,000.00 = Rp 117,000.00
0.7800 m3 Koral beton @ Rp. 255,000.00 = Rp 198,900.00
Sub total : = Rp 4,765,931.18
Upah An. SNI ( Revisi ) 6.39.2
4.8500 Oh Pekerja @ Rp. 100,000.00 = Rp 485,000.00
0.3500 Oh Tukang batu @ Rp. 120,000.00 = Rp 42,000.00
1.5600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 187,200.00
1.3500 Oh Tukang besi @ Rp. 120,000.00 = Rp 162,000.00
0.3310 Oh Kepala tukang @ Rp. 125,000.00 = Rp 41,375.00
0.1700 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 917,575.00
- 42 -
Total upah+bahan : = Rp ###
29 1 m3 Membuat sloof beton bertulang ukuran 20 x 30 Cm dengan besi 5 dia 16 mm + beugel dia 6 mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.2700 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 816,750.00
2.0000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 28,400.00
0.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 6,930.00
127.5045 Kg Besi beton polos dia 16 mm @ Rp. 11,500.00 = Rp 1,466,301.75
45.7446 Kg Besi begel polos dia 6 mm @ Rp. 11,500.00 = Rp 526,063.36
3.0000 Kg Kawat beton @ Rp. 16,500.00 = Rp 49,500.00
323.0000 kg Semen portland @ Rp. 1,675.00 = Rp 541,025.00
0.5200 m3 Pasir beton @ Rp. 225,000.00 = Rp 117,000.00
0.7800 m3 Koral beton @ Rp. 255,000.00 = Rp 198,900.00
Sub total : = Rp 3,750,870.11
Upah An. SNI ( Revisi ) 6.39.2
4.8500 Oh Pekerja @ Rp. 100,000.00 = Rp 485,000.00
0.3500 Oh Tukang batu @ Rp. 120,000.00 = Rp 42,000.00
1.5600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 187,200.00
1.3500 Oh Tukang besi @ Rp. 120,000.00 = Rp 162,000.00
0.3310 Oh Kepala tukang @ Rp. 125,000.00 = Rp 41,375.00
0.1700 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 917,575.00
Total upah+bahan : = Rp ###
30 1 m3 Membuat sloof beton bertulang ukuran 15 x 20 Cm dengan besi 4 dia 12 mm + beugel dia 6mm .
Bahan An. SNI ( Revisi ) 6.39.1
0.2700 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 816,750.00
2.0000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 28,400.00
0.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 6,930.00
114.4188 Kg Besi beton polos dia 12 mm @ Rp. 11,500.00 = Rp 1,315,816.20
35.6310 Kg Besi begel polos dia 6 mm @ Rp. 11,500.00 = Rp 409,756.50
3.0000 Kg Kawat beton @ Rp. 16,500.00 = Rp 49,500.00
323.0000 kg Semen portland @ Rp. 1,675.00 = Rp 541,025.00
0.5200 m3 Pasir beton @ Rp. 225,000.00 = Rp 117,000.00
0.7800 m3 Koral beton @ Rp. 255,000.00 = Rp 198,900.00
Sub total : = Rp 3,484,077.70
Upah An. SNI ( Revisi ) 6.39.2
4.8500 Oh Pekerja @ Rp. 100,000.00 = Rp 485,000.00
0.3500 Oh Tukang batu @ Rp. 120,000.00 = Rp 42,000.00
1.5600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 187,200.00
1.3500 Oh Tukang besi @ Rp. 120,000.00 = Rp 162,000.00
0.3310 Oh Kepala tukang @ Rp. 125,000.00 = Rp 41,375.00
0.1700 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 917,575.00
Total upah+bahan : = Rp ###
- 43 -
Sub total : = Rp 3,081,214.30
Upah An. SNI ( Revisi ) 6.39.2
4.8500 Oh Pekerja @ Rp. 100,000.00 = Rp 485,000.00
0.3500 Oh Tukang batu @ Rp. 120,000.00 = Rp 42,000.00
1.5600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 187,200.00
1.3000 Oh Tukang besi @ Rp. 120,000.00 = Rp 156,000.00
0.3310 Oh Kepala tukang @ Rp. 125,000.00 = Rp 41,375.00
0.1700 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 911,575.00
Total upah+bahan : = Rp ###
Kolom
32 1 m3 Membuat kolom beton bertulang ( 300 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.40.1
0.4000 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 1,210,000.00
4.0000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 56,800.00
2.0000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 23,100.00
315.0000 Kg Besi beton polos @ Rp. 11,500.00 = Rp 3,622,500.00
4.5000 Kg Kawat beton @ Rp. 16,500.00 = Rp 74,250.00
336.0000 kg Semen portland @ Rp. 1,675.00 = Rp 562,800.00
0.5400 m3 Pasir beton @ Rp. 225,000.00 = Rp 121,500.00
0.8100 m3 Koral beton @ Rp. 255,000.00 = Rp 206,550.00
0.1500 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 654,499.95
3.5000 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 385,000.00
20.0000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 1,120,000.00
Sub total : = Rp 8,036,999.95
Upah An. SNI ( Revisi ) 6.40.2
7.0500 Oh Pekerja @ Rp. 100,000.00 = Rp 705,000.00
0.2700 Oh Tukang batu @ Rp. 120,000.00 = Rp 32,400.00
1.6500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 198,000.00
2.1000 Oh Tukang besi @ Rp. 120,000.00 = Rp 252,000.00
0.4030 Oh Kepala tukang @ Rp. 125,000.00 = Rp 50,375.00
0.3530 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 1,237,775.00
Total upah+bahan : = Rp ###
- 44 -
Biaya kolom praktis dengan besi polos 4 diameter 12 mm = Rp 82,369.50
Analog biaya / M3 = 82,369.50 x 60.61 = Rp 4,992,415.40
Balok
35 1 m3 Membuat balok beton bertulang ( 200 Kg besi + bekisting )
Bahan An. SNI ( Revisi ) 6.41.1
0.3200 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 968,000.00
3.2000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 45,440.00
1.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 18,480.00
210.0000 Kg Besi beton polos @ Rp. 11,500.00 = Rp 2,415,000.00
3.0000 Kg Kawat beton @ Rp. 16,500.00 = Rp 49,500.00
336.0000 kg Semen portland @ Rp. 1,675.00 = Rp 562,800.00
0.5400 m3 Pasir beton @ Rp. 225,000.00 = Rp 121,500.00
0.8100 m3 Koral beton @ Rp. 255,000.00 = Rp 206,550.00
0.1400 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 610,866.62
2.8000 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
16.0000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 896,000.00
Sub total : = Rp 6,202,136.62
Upah An. SNI ( Revisi ) 6.41.2
6.3500 Oh Pekerja @ Rp. 100,000.00 = Rp 635,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
1.6500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 198,000.00
1.4000 Oh Tukang besi @ Rp. 120,000.00 = Rp 168,000.00
0.3330 Oh Kepala tukang @ Rp. 125,000.00 = Rp 41,625.00
0.3180 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 1,075,625.00
Total upah+bahan : = Rp ###
- 45 -
Bahan An. SNI ( Revisi ) 6.42.1
0.3200 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 968,000.00
3.2000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 45,440.00
1.6000 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 18,480.00
157.5000 Kg Besi beton polos @ Rp. 11,500.00 = Rp 1,811,250.00
2.2500 Kg Kawat beton @ Rp. 16,500.00 = Rp 37,125.00
336.0000 kg Semen portland @ Rp. 1,675.00 = Rp 562,800.00
0.5400 m3 Pasir beton @ Rp. 225,000.00 = Rp 121,500.00
0.8100 m3 Koral beton @ Rp. 255,000.00 = Rp 206,550.00
0.1200 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 523,599.96
2.8000 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 308,000.00
32.0000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 1,792,000.00
Sub total : = Rp 6,394,744.96
Upah An. SNI ( Revisi ) 6.42.2
5.3000 Oh Pekerja @ Rp. 100,000.00 = Rp 530,000.00
0.2750 Oh Tukang batu @ Rp. 120,000.00 = Rp 33,000.00
1.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 156,000.00
1.0500 Oh Tukang besi @ Rp. 120,000.00 = Rp 126,000.00
0.2650 Oh Kepala tukang @ Rp. 125,000.00 = Rp 33,125.00
0.2650 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 878,125.00
Total upah+bahan : = Rp ###
- 46 -
5.5000 kg Semen portland @ Rp. 1,675.00 = Rp 9,212.50
0.0090 m3 Pasir beton @ Rp. 225,000.00 = Rp 2,025.00
0.0150 m3 Koral beton @ Rp. 255,000.00 = Rp 3,825.00
Sub total : = Rp 55,882.50
Upah An. SNI ( Revisi ) 6.46.2
0.1000 Oh Pekerja @ Rp. 100,000.00 = Rp 10,000.00
0.0330 Oh Tukang batu @ Rp. 120,000.00 = Rp 3,960.00
0.0330 Oh Tukang kayu @ Rp. 120,000.00 = Rp 3,960.00
0.0330 Oh Tukang besi @ Rp. 120,000.00 = Rp 3,960.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0050 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 23,130.00
Total upah+bahan : = Rp 79,012.50
- 47 -
5.6000 Oh Pekerja @ Rp. 100,000.00 = Rp 560,000.00
0.3500 Oh Tukang batu @ Rp. 120,000.00 = Rp 42,000.00
2.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 276,000.00
1.4000 Oh Tukang besi @ Rp. 120,000.00 = Rp 168,000.00
0.4050 Oh Kepala tukang @ Rp. 125,000.00 = Rp 50,625.00
0.2020 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 1,096,625.00
Total upah+bahan : = Rp ###
Plat Lantai
41 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm , pembagi 8 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 116,160.00
- Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 0.00
0.1920 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 2,217.60
5.6900 Kg Besi beton polos 10 mm & 8 m @ Rp. 11,500.00 = Rp 65,435.00
0.2250 Kg Kawat beton @ Rp. 16,500.00 = Rp 3,712.50
38.7600 kg Semen portland @ Rp. 1,675.00 = Rp 64,923.00
0.0624 m3 Pasir beton @ Rp. 225,000.00 = Rp 14,040.00
0.0936 m3 Koral beton @ Rp. 255,000.00 = Rp 23,868.00
0.0144 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 62,832.00
0.3500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.5000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 196,000.00
Sub total : = Rp 587,688.10
Upah An. SNI ( Revisi ) 6.42.2
0.6960 Oh Pekerja @ Rp. 100,000.00 = Rp 69,600.00
0.0420 Oh Tukang batu @ Rp. 120,000.00 = Rp 5,040.00
0.3360 Oh Tukang kayu @ Rp. 120,000.00 = Rp 40,320.00
0.1260 Oh Tukang besi @ Rp. 120,000.00 = Rp 15,120.00
0.0504 Oh Kepala tukang @ Rp. 125,000.00 = Rp 6,300.00
0.0222 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 136,380.00
Total upah+bahan : = Rp 724,068.10
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 10 - 12
dan besi polos dia 8 - 15 = Rp 724,068.10
Analog biaya / M3 = 724,068.10 x 8.33 = Rp ###
42 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 12 mm , pembagi 10 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 116,160.00
0.2500 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 3,550.00
0.1920 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 2,217.60
9.7000 Kg Besi beton polos 10 mm & 8 m @ Rp. 11,500.00 = Rp 111,550.00
0.2250 Kg Kawat beton @ Rp. 16,500.00 = Rp 3,712.50
38.7600 kg Semen portland @ Rp. 1,675.00 = Rp 64,923.00
0.0624 m3 Pasir beton @ Rp. 225,000.00 = Rp 14,040.00
0.0936 m3 Koral beton @ Rp. 255,000.00 = Rp 23,868.00
0.0144 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 62,832.00
0.3500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.5000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 196,000.00
Sub total : = Rp 637,353.10
Upah An. SNI ( Revisi ) 6.42.2
0.6960 Oh Pekerja @ Rp. 100,000.00 = Rp 69,600.00
0.0420 Oh Tukang batu @ Rp. 120,000.00 = Rp 5,040.00
0.3360 Oh Tukang kayu @ Rp. 120,000.00 = Rp 40,320.00
- 48 -
0.1260 Oh Tukang besi @ Rp. 120,000.00 = Rp 15,120.00
0.0504 Oh Kepala tukang @ Rp. 125,000.00 = Rp 6,300.00
0.0222 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 136,380.00
Total upah+bahan : = Rp 773,733.10
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 12 - 15
dan besi polos dia 10 - 15 = Rp 773,733.10
Analog biaya / M3 = 773,733.10 x 8.33 = Rp ###
43 1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm jarak 15 , pembagi 10 mm.
arak 15 rangkap atas bawah ( doble wappening)
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC @ Rp. 3,025,000.00 = Rp 116,160.00
0.2500 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 3,550.00
0.1920 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 2,217.60
15.8930 Kg Besi beton polos 10 mm @ Rp. 11,500.00 = Rp 182,769.50
0.2250 Kg Kawat beton @ Rp. 16,500.00 = Rp 3,712.50
38.7600 kg Semen portland @ Rp. 1,675.00 = Rp 64,923.00
0.0624 m3 Pasir beton @ Rp. 225,000.00 = Rp 14,040.00
0.0936 m3 Koral beton @ Rp. 255,000.00 = Rp 23,868.00
0.0144 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 62,832.00
0.3500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.5000 Btg Dolken kayu galam Ø 8 / 4 @ Rp. 56,000.00 = Rp 196,000.00
Sub total : = Rp 708,572.60
Upah An. SNI ( Revisi ) 6.42.2
0.6960 Oh Pekerja @ Rp. 100,000.00 = Rp 69,600.00
0.0420 Oh Tukang batu @ Rp. 120,000.00 = Rp 5,040.00
0.3360 Oh Tukang kayu @ Rp. 120,000.00 = Rp 40,320.00
0.1260 Oh Tukang besi @ Rp. 120,000.00 = Rp 15,120.00
0.0504 Oh Kepala tukang @ Rp. 125,000.00 = Rp 6,300.00
0.0222 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 136,380.00
Total upah+bahan : = Rp 844,952.60
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm penulangan rangkap dengan besi dia 10 - 15
dan besi polos dia 8 - 15 (doble wappening) atas bawah. = Rp 844,952.60
Analog biaya / M3 = 844,952.60 x 8.33 = Rp ###
PEKERJAAN KAYU
- 49 -
2 1 m3 Pasang kusen pintu & jendela kayu kamper (Kayu klas II )
Bahan An. SNI ( Revisi ) 6.2.1
1.2000 m3 Kayu kamper, balok @ Rp. #REF! = Rp #REF!
1.2000 Kg Paku 10Cm @ Rp. 14,200.00 = Rp 17,040.00
1.0000 Kg Lem kayu @ Rp. 40,150.00 = Rp 40,150.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.2.2
6.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 600,000.00
18.0000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 2,160,000.00
2.0000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 250,000.00
0.3000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 3,010,000.00
Total upah+bahan : = Rp #REF!
3 1 m3 Pasang kusen pintu & jendela kayu borneo ( Kruwing , kempas , Meranti batu )
Bahan An. SNI ( Revisi ) 6.3.1
1.2000 m3 Kayu borneo, balok @ Rp. #REF! = Rp #REF!
1.2000 Kg Paku 10Cm @ Rp. 14,200.00 = Rp 17,040.00
1.0000 Kg Lem kayu @ Rp. 40,150.00 = Rp 40,150.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.3.2
6.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 600,000.00
18.0000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 2,160,000.00
2.0000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 250,000.00
0.3000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 3,010,000.00
Total upah+bahan : = Rp #REF!
PEKERJAAN PINTU
4 1 m2 Pasang pintu klamp kayu kamper
Bahan An. SNI ( Revisi ) 6.5.1
0.0400 m3 Kayu kamper papan @ Rp. 9,070,000.00 = Rp 362,800.00
0.0500 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 710.00
Sub total : = Rp 363,510.00
Upah An. SNI ( Revisi ) 6.5.2
0.3500 Oh Pekerja @ Rp. 100,000.00 = Rp 35,000.00
1.0500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 126,000.00
0.1050 Oh Kepala tukang @ Rp. 125,000.00 = Rp 13,125.00
0.0180 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 174,125.00
Total upah+bahan : = Rp 537,635.00
- 50 -
Bahan An. SNI ( Revisi ) 6.7.1
0.0400 m3 Kayu jati, papan @ Rp. #REF! = Rp #REF!
0.5000 kg Lem kayu @ Rp. 40,150.00 = Rp 20,075.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.7.2
1.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 100,000.00
3.0000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 360,000.00
0.3000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 37,500.00
0.0500 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 497,500.00
Total upah+bahan : = Rp #REF!
- 51 -
0.8000 Oh Pekerja @ Rp. 100,000.00 = Rp 80,000.00
2.4000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 288,000.00
0.2400 Oh Kepala tukang @ Rp. 125,000.00 = Rp 30,000.00
0.0400 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 398,000.00
Total upah+bahan : = Rp #REF!
- 52 -
2.1000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 252,000.00
0.2100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 26,250.00
0.0350 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 338,250.00
Total upah+bahan : = Rp 613,363.00
- 53 -
2.0000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 240,000.00
0.2000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 25,000.00
0.0300 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 325,000.00
Total upah+bahan : = Rp #REF!
- 54 -
0.8000 Kg Lem kayu @ Rp. 10,750.00 = Rp 8,600.00
1.0000 Lbr Teakwood 4' x 8' x 4 mm @ Rp. 93,690.00 = Rp 93,690.00
0.5000 Lbr Formica 4' x 8' @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.21.2
0.8500 Oh Pekerja @ Rp. 100,000.00 = Rp 85,000.00
2.5500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 306,000.00
0.2550 Oh Kepala tukang @ Rp. 125,000.00 = Rp 31,875.00
0.0430 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 422,875.00
Total upah+bahan : = Rp #REF!
- 55 -
Total upah+bahan : = Rp #REF!
KUDA KUDA
27 1 m3 Pasang konstruksi kuda-kuda kayu jati
Bahan An. SNI ( Revisi ) 6.27.1
1.1000 m3 Kayu jati, balok @ Rp. #REF! = Rp #REF!
15.0000 Kg Besi strip @ Rp. #REF! = Rp #REF!
5.6000 Kg Paku biasa 12 Cm. @ Rp. 14,200.00 = Rp 79,520.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.27.2
4.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 400,000.00
12.0000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 1,440,000.00
1.2000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 150,000.00
0.2000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 1,990,000.00
Total upah+bahan : = Rp #REF!
- 56 -
Total upah+bahan : = Rp #REF!
PASANG USUK.
31 1 m2 Pasang kaso + reng genteng kodok kayu kamper
Bahan An. SNI ( Revisi ) 6.31.1
0.0077 m3 Kayu kamper, usuk 5/7. @ Rp. #REF! = Rp #REF!
0.0046 m3 Reng 2/3 cm kayu kamper @ Rp. #REF! = Rp #REF!
0.2500 Kg Paku biasa 5 Cm dan 10 Cm @ Rp. 14,200.00 = Rp 3,550.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.31.2
0.1000 Oh Pekerja @ Rp. 100,000.00 = Rp 10,000.00
0.1000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 12,000.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0050 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 23,250.00
Total upah+bahan : = Rp #REF!
- 57 -
Total upah+bahan : = Rp #REF!
- 58 -
39 1 m2 Pasang kaso + reng atap sirap kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.37.1
0.1650 m3 Ky. kruw/beng/kempas, usuk@ Rp. #REF! = Rp #REF!
0.2000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 2,840.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.37.2
0.1200 Oh Pekerja @ Rp. 100,000.00 = Rp 12,000.00
0.1200 Oh Tukang kayu @ Rp. 120,000.00 = Rp 14,400.00
0.0120 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,500.00
0.0060 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 27,900.00
Total upah+bahan : = Rp #REF!
42 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu kamper potongan 5/7 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0120 m3 Kayu kamper 5/7 - 2 mtr. @ Rp. #REF! = Rp #REF!
0.1000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 1,420.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.39.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.2500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 48,125.00
Total upah+bahan : = Rp #REF!
- 59 -
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.40.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.2500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 48,125.00
Total upah+bahan : = Rp #REF!
45 1 m2 Pasang rangka langit-langit ( 1.00 x 1.00 ) m, kayu meranti potongan 5/7 - 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0120 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. #REF! = Rp #REF!
0.1000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 1,420.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.39.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.2500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 48,125.00
Total upah+bahan : = Rp #REF!
- 60 -
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 54,750.00
Total upah+bahan : = Rp #REF!
48 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu kamper potongan 5/7 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu kamper 5/7 - 2 mtr. @ Rp. #REF! = Rp #REF!
0.2000 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,840.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.38.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 54,750.00
Total upah+bahan : = Rp #REF!
51 1 m2 Pasang rangka langit-langit ( 50 x 100 ) Cm, kayu meranti potongan 5/7 - 2 meter.
Bahan An. SNI ( Revisi ) 6.39.1
0.0154 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. #REF! = Rp #REF!
0.2000 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,840.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.38.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 54,750.00
Total upah+bahan : = Rp #REF!
- 61 -
Bahan An. SNI ( Revisi ) 6.41.1
0.0163 m3 Kayu jati, usuk 5/7. @ Rp. #REF! = Rp #REF!
0.2500 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 3,550.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.41.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
Total upah+bahan : = Rp #REF!
54 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu kamper potongan panjang 2 mtr.- 5/7
Bahan An. SNI ( Revisi ) 6.42.1
0.0163 m3 Kayu kamper, potongan 2 m@ Rp. #REF! = Rp #REF!
0.2500 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 3,550.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.41.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
Total upah+bahan : = Rp #REF!
- 62 -
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
Total upah+bahan : = Rp #REF!
57 1 m2 Pasang rangka langit-langit ( 60 x 60 ) cm, kayu Meranti potongan panjang 2 meter - 5/7.
Bahan An. SNI ( Revisi ) 6.43.1
0.0163 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 231.46
0.2500 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 3,550.00
Sub total : = Rp 3,781.46
Upah An. SNI ( Revisi ) 6.41.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
Total upah+bahan : = Rp 63,531.46
60 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu kamper potongan panjang 2 mtr.- 5/7
Bahan An. SNI ( Revisi ) 6.42.1
0.0230 m3 Kayu kamper, potongan 2 m@ Rp. #REF! = Rp #REF!
0.1500 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,130.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.42.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
- 63 -
Total upah+bahan : = Rp #REF!
63 1 m2 Pasang rangka langit-langit ( 30 x 60 ) cm, kayu Meranti potongan panjang 2 meter - 5/7.
Bahan An. SNI ( Revisi ) 6.43.1
0.0230 m3 Kayu meranti 5/7 - 2 mtr. @ Rp. #REF! = Rp #REF!
0.1500 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,130.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.43.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.3000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 36,000.00
0.0300 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 59,750.00
Total upah+bahan : = Rp #REF!
- 64 -
0.2000 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,840.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.45.2
0.2500 Oh Pekerja @ Rp. 100,000.00 = Rp 25,000.00
0.3500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 42,000.00
0.0350 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,375.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 71,375.00
Total upah+bahan : = Rp #REF!
66 1 m2 Pasang rangka langit-langit ( 30 x 30 ) cm, kayu kamper potongan panjang 2 mtr Uk.5/7
Bahan An. SNI ( Revisi ) 6.45.1
0.0270 m3 Kayu kamper, usuk 5/7 @ Rp. #REF! = Rp #REF!
0.2000 Kg Paku biasa 7 - 10 cm @ Rp. 14,200.00 = Rp 2,840.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.45.2
0.2500 Oh Pekerja @ Rp. 100,000.00 = Rp 25,000.00
0.3500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 42,000.00
0.0350 Oh Kepala tukang @ Rp. 125,000.00 = Rp 4,375.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 71,375.00
Total upah+bahan : = Rp #REF!
PASANG LISPLANG
68 1 m' Pasang lisplang ukuran ( 3 x 20 ) cm, kayu jati
Bahan An. SNI ( Revisi ) 6.47.1
0.0108 m3 Kayu jati, papan @ Rp. #REF! = Rp #REF!
0.1000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 1,420.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.47.2
0.1000 Oh Pekerja @ Rp. 100,000.00 = Rp 10,000.00
0.2000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0050 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 36,500.00
Total upah+bahan : = Rp #REF!
- 65 -
0.2000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0050 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 36,500.00
Total upah+bahan : = Rp 135,876.00
- 66 -
74 1 m' Pasang lisplang ukuran 2 x ( 3 x 20 ) cm, kayu kamper
Bahan An. SNI ( Revisi ) 6.51.1
0.0145 m3 Kayu kamper, papan @ Rp. 9,070,000.00 = Rp 131,515.00
0.0600 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 852.00
Sub total : = Rp 132,367.00
Upah An. SNI ( Revisi ) 6.51.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.2500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 48,125.00
Total upah+bahan : = Rp 180,492.00
- 67 -
Sub total : = Rp 37,352.00
Upah An. SNI ( Revisi ) 6.53.2
0.0500 Oh Pekerja @ Rp. 100,000.00 = Rp 5,000.00
0.0500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 6,000.00
0.0060 Oh Kepala tukang @ Rp. 125,000.00 = Rp 750.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 11,750.00
Total upah+bahan : = Rp 49,102.00
80 1 m2 Pasang rangka dan dinding pemisah (60 x 120) Cm kayu kruwing / bengkirai / kempas.
Bahan An. SNI ( Revisi ) 6.55.1
0.0195 m3 Kayu , balok @ Rp. #REF! = Rp #REF!
0.0070 m3 Kayu , papan @ Rp. #REF! = Rp #REF!
0.1000 Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 1,420.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.55.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.4500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 54,000.00
0.0450 Oh Kepala tukang @ Rp. 125,000.00 = Rp 5,625.00
0.0750 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 74,625.00
Total upah+bahan : = Rp #REF!
- 68 -
0.8600 Lbr Tripleks 120 x 240 Cm x 5 @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.56.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.6000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 72,000.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 99,500.00
Total upah+bahan : = Rp #REF!
- 69 -
1.0500 m' Kayu profil @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.60.2
0.0210 Oh Pekerja @ Rp. 100,000.00 = Rp 2,100.00
0.0210 Oh Tukang kayu @ Rp. 120,000.00 = Rp 2,520.00
0.0020 Oh Kepala tukang @ Rp. 125,000.00 = Rp 250.00
0.0010 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 4,870.00
Total upah+bahan : = Rp #REF!
- 70 -
0.0700 Oh Tukang kayu @ Rp. 120,000.00 = Rp 8,400.00
0.0070 Oh Kepala tukang @ Rp. 125,000.00 = Rp 875.00
0.0040 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 12,275.00
Total upah+bahan : = Rp #REF!
- 71 -
8 1 m2 Pasang langit-langit plywood ( 30 x 60 ) cm, tebal 4 mm
Bahan An. SNI ( Revisi ) 6.8.1
0.3600 Lbr Plywood 4' x 8' x 4 mm @ Rp. #REF! = Rp #REF!
0.0300 Kg Paku @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.8.2
0.0700 Oh Pekerja @ Rp. 100,000.00 = Rp 7,000.00
0.1000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 12,000.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0035 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 20,250.00
Total upah+bahan : = Rp #REF!
- 72 -
0.0500 Kg Paku sekrup @ Rp. 24,000.00 = Rp 1,200.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.14.2
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.6000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 72,000.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 99,500.00
Total upah+bahan : = Rp #REF!
- 73 -
Upah An. SNI ( Revisi ) 6.18.2
0.0750 Oh Pekerja @ Rp. 100,000.00 = Rp 7,500.00
0.2500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 30,000.00
0.0250 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,125.00
0.0035 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 40,625.00
Total upah+bahan : = Rp 60,305.00
- 74 -
Sub total : = Rp 25,000.00
Total upah+bahan : = Rp 78,750.00
- 75 -
0.0600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 7,200.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 29,700.00
Total upah+bahan : = Rp 76,175.00
- 76 -
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0020 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 66,500.00
Total upah+bahan : = Rp 128,930.00
- 77 -
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 24,000.00
Total upah+bahan : = Rp #REF!
- 78 -
20 1 m2 Pasang atap seng Galvalum type DJLS 45 Warna
Bahan An. SNI
1.3700 M2 1 M! SENG GALVALUM warna
( Lebar efektif 73 Cm.) @ Rp. #REF! = Rp #REF!
4.0000 Bh Paku rifet @ Rp. 300.00 = Rp 1,200.00
Sub total : = Rp #REF!
Upah An. SNI
0.0210 Oh Pekerja @ Rp. 100,000.00 = Rp 2,100.00
0.0110 Oh Tukang kayu @ Rp. 120,000.00 = Rp 1,320.00
0.0040 Oh Mandor @ Rp. 0.00 = Rp 0.00
1.0000 Ls Biaya mekanik/peralatan @ Rp. 2,650.00 Rp 2,650.00
Sub total : = Rp 6,070.00
Total upah+bahan : = Rp #REF!
- 79 -
Bahan An. SNI ( Revisi ) 6.38.1
0.7000 Lbr Seng glmbg 3" x 6" bjls 28 @ Rp. #REF! = Rp #REF!
0.0200 Kg Paku biasa 1/2" - 1" @ Rp. 14,200.00 = Rp 284.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.38.2
0.1200 Oh Pekerja @ Rp. 100,000.00 = Rp 12,000.00
0.0600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 7,200.00
0.0060 Oh Kepala tukang @ Rp. 125,000.00 = Rp 750.00
0.0060 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 19,950.00
Total upah+bahan : = Rp #REF!
- 80 -
Sub total : = Rp 15,283.00
Upah An. SNI ( Revisi ) 6.1.2
0.0060 Oh Pekerja @ Rp. 100,000.00 = Rp 600.00
0.0600 Oh Tukang besi @ Rp. 120,000.00 = Rp 7,200.00
0.0060 Oh Kepala tukang @ Rp. 125,000.00 = Rp 750.00
0.0003 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 8,550.00
Total upah+bahan : = Rp 23,833.00
2 1 m2 Pasang pintu besi plat baja tabal 2mm rangkap, rangka baja siku 30.30.3.
Bahan An. SNI ( Revisi ) 6.2.1
15.0000 Kg Besi siku 30.30.3 @ Rp. #REF! = Rp #REF!
32.8000 Kg Besi plat baja tebal 2mm. @ Rp. #REF! = Rp #REF!
0.0500 Kg Kawat las. @ Rp. 37,500.00 = Rp 1,875.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.2.2
0.6500 Oh Tukang besi @ Rp. 120,000.00 = Rp 78,000.00
0.6500 Oh Pekerja @ Rp. 100,000.00 = Rp 65,000.00
0.0650 Oh Kepala tukang @ Rp. 125,000.00 = Rp 8,125.00
0.0320 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 151,125.00
Total upah+bahan : = Rp #REF!
- 81 -
0.0005 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 23,250.00
Total upah+bahan : = Rp #REF!
8 1 m2 Pasang pagar kawat dari besi siku tinggi 1,5 m dan panjang 3m tidak termasuk pondasi setempat.
Bahan
11.6000 m1 m' besi L 40 . 40 . 5 @ Rp. #VALUE! = Rp #VALUE!
34.0000 m1 m'kawat duri @ Rp. #REF! = Rp #REF!
Sub total : = Rp #VALUE!
- 82 -
Bahan
1.1500 m2 Pintu dari aluminium @ Rp. 255,000.00 = Rp 293,250.00
Sub total : = Rp 293,250.00
Upah Biaya pasang / Upah diperhitungkan. Rp 52,500.00
Sub total : = Rp 52,500.00
Total upah+bahan : = Rp 345,750.00
- 83 -
Sub total : = Rp 82,500.00
19 1 Bh. Pasang pintu aluminium 2,75" putih ( Silver) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Bahan An. SNI ( Revisi ) 6.9.1
6.2500 m1 Slimar Aluminium putih 2.75@ Rp. #REF! = Rp #REF!
15.0000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 47,850.00
1.0000 set Engsel. @ Rp. 25,000.00 Rp 25,000.00
1.0000 Bh Kunci @ Rp. 195,000.00 Rp 195,000.00
0.6400 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 70,400.00
1.2400 m2 Multipleks 9 mm @ Rp. 110,000.00 = Rp 136,400.00
1.0000 Ls Paku Skrup @ Rp. 7,500.00 Rp 7,500.00
Sub total : = Rp #REF!
koefisen tenaga ditambah 35 % dari anlisa untuk 1 M2 pembuatan pintu aluminium.
Upah 1.4175 Oh Pekerja @ Rp. 100,000.00 = Rp 141,750.00
1.4175 Oh Tukang besi @ Rp. 120,000.00 = Rp 170,100.00
0.1418 Oh Kepala tukang besi @ Rp. 125,000.00 = Rp 17,718.75
0.0070 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 329,568.75
Total upah+bahan : = Rp #REF!
20 1 Bh. Pasang pintu aluminium 2,75" coklat ( Brown) UKURAN 0.80 X 2.00 Mtr.
( pintu isian kaca bening 5mm dan multipleks 9 mm).
Bahan An. SNI ( Revisi ) 6.9.1
- 84 -
6.2500 m1 Slimar Aluminium coklat 2.7 @
Rp. 68,200.00 = Rp 426,250.00
15.0000 m1 Karet penjepit kaca/ tripleks @
Rp. 3,190.00 Rp 47,850.00
1.0000 set Engsel. Rp. @ 25,000.00 Rp 25,000.00
1.0000 Bh Kunci Rp. @ 195,000.00 Rp 195,000.00
0.6400 m2 Kaca bening 5 mm Rp. @ 110,000.00 = Rp 70,400.00
1.2400 m2 Multipleks 9 mm Rp. @ 110,000.00 = Rp 136,400.00
1.0000 Ls Paku Skrup Rp. @ 7,500.00 Rp 7,500.00
Sub total : = Rp 908,400.00
koefisen tenaga ditambah 30 % dari anlisa untuk 1 M2 pembuatan pintu aluminium karena
pintu ini ukuran 80 x 200 Cm.dan ada ambang tengah.
Upah 1.4175 Oh Pekerja @ Rp. 100,000.00 = Rp 141,750.00
1.4175 Oh Tukang besi @ Rp. 120,000.00 = Rp 170,100.00
0.1418 Oh Kepala tukang besi @ Rp. 125,000.00 = Rp 17,718.75
0.0070 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 329,568.75
Total upah+bahan : = Rp ###
21 1M2 Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
4.8000 m1 Slimar Aluminium putih 2" @ Rp. 65,000.00 = Rp 312,000.00
8.5000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 27,115.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.9025 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 99,275.00
Sub total : = Rp 503,390.00
22 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.60 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2.2000 m1 Slimar Aluminium putih 2" @ Rp. #REF! = Rp #REF!
4.4000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 14,036.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.3000 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 33,000.00
Sub total : = Rp #REF!
23 1Bh Pasang daun jendela aluminium 2" putih ( Silver) UKURAN 0.50 X 0.50 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2.0000 m1 Slimar Aluminium putih 2" @ Rp. #REF! = Rp #REF!
4.0000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 12,760.00
- 85 -
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.2500 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 27,500.00
Sub total : = Rp #REF!
24 1M2 Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 1.00 X 1.00 Mtr.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
4.8000 m1 Slimar Aluminium coklat 2" @ Rp. 68,200.00 = Rp 327,360.00
8.5000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 27,115.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.9025 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 99,275.00
Sub total : = Rp 518,750.00
25 1Bh Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 60 Cm.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2.2000 m1 Slimar Aluminium coklat 2" @ Rp. 68,200.00 = Rp 150,040.00
4.4000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 14,036.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.3000 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 33,000.00
Sub total : = Rp 262,076.00
26 1Bh. Pasang daun jendela aluminium 2" coklat (Brown) UKURAN 50 X 50 Cm.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
2.0000 m1 Slimar Aluminium coklat 2" @ Rp. 68,200.00 = Rp 136,400.00
4.0000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 Rp 12,760.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 Rp 45,000.00
0.2500 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 27,500.00
Sub total : = Rp 241,660.00
- 86 -
Upah 1.0500 Oh Pekerja @ Rp. 100,000.00 = Rp 105,000.00
1.0500 Oh Tukang besi @ Rp. 120,000.00 = Rp 126,000.00
0.1050 Oh Kepala tukang besi @ Rp. 125,000.00 = Rp 13,125.00
0.0052 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 244,125.00
Total upah+bahan : = Rp 485,785.00
- 87 -
0.5000 Bh
Knie 3" @ Rp. #REF! = Rp #REF!
0.3500 Bh
tube lem pvc @ Rp. 3,750.00 = Rp 1,312.50
0.7500 buah klem + 2 paku beton @ Rp.
Bh 2,750.00 = Rp 2,062.50
Sub total : = Rp #REF!
Upah LUMSUM Rp 4,500.00
Total upah+bahan : = Rp #REF!
PEKERJAAN PENGECATAN
Pemersihan Cat
1 1 m2 Mengikis/mengerok permukaan cat tembok lama
Bahan An. SNI ( Revisi ) 6.1.1
0.0500 Kg Soda api @ Rp. 7,500.00 = Rp 375.00
Sub total : = Rp 375.00
Upah An. SNI ( Revisi ) 6.1.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
- Oh Tukang cat @ Rp. 120,000.00 = Rp 0.00
- Oh Kepala tukang @ Rp. 125,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 15,000.00
Total upah+bahan : = Rp 15,375.00
- 88 -
0.0500 Kg Sabun @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.4.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
- Oh Tukang cat @ Rp. 120,000.00 = Rp 0.00
- Oh Kepala tukang @ Rp. 125,000.00 = Rp 0.00
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 15,000.00
Total upah+bahan : = Rp #REF!
5 1 m2 Mengerok karat atau cat lama permukaan baja dengan pancar pasir ( sanblasting )
dengan tingkat kebersihan Sa 2.5%
Bahan UNTUK 10 m2 'An. SNI ( Revisi ) 6.5.1
40.0000 Kg Pasir silika @ Rp. 25.00 = Rp 1,000.00
10.0000 Ltr B B M @ Rp. 3,250.00 = Rp 32,500.00
Sub total : = Rp 33,500.00
Alat An. SNI ( Revisi ) 6.5.2 PER 10 M2.
Sewa / hari Kompressor, blasting pot, @ Rp. 250,000.00 = Rp 250,000.00
selang dan nozle
Sub total : = Rp 250,000.00
Upah An. SNI ( Revisi ) 6.5.3
1.6000 Oh Pekerja @ Rp. 100,000.00 = Rp 160,000.00
1.6000 Oh Tukang cat @ Rp. 120,000.00 = Rp 192,000.00
0.8000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 100,000.00
0.5000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 452,000.00
Untuk 10 M2 Total upah+bahan : = Rp 702,000.00
Untuk 1 M2 = Rp 70,200.00
Cat KAYU
- 89 -
. Sub total : = Rp 16,937.50
Total upah+bahan : = Rp #REF!
- 90 -
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 9,200.00
Total upah+bahan : = Rp #REF!
Cat TEMBOK
Cat BARU.
- 91 -
14 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Cat Paragon /Decolith
Bahan An. SNI ( Revisi ) 6.14.1
0.1000 Kg Plamir @ Rp. 17,050.00 = Rp 1,705.00
0.2500 Lbr Ampelas @ Rp. 5,500.00 = Rp 1,375.00
0.0200 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 130.00
0.1000 Kg Cat dasar @ Rp. #REF! = Rp #REF!
0.2600 Kg Cat penutup 2x @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.14.2
0.0200 Oh Pekerja @ Rp. 100,000.00 = Rp 2,000.00
0.0630 Oh Tukang cat @ Rp. 120,000.00 = Rp 7,560.00
0.0063 Oh Kepala tukang @ Rp. 125,000.00 = Rp 787.50
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 10,347.50
Total upah+bahan : = Rp #REF!
15 1 m2 Pengecatan tembok baru ( 1x plamir , 1x cat dasar, 2x cat penutup ) Cat I.C.I. Catilac
Bahan An. SNI ( Revisi ) 6.14.1
0.1000 Kg Plamir @ Rp. 17,050.00 = Rp 1,705.00
0.2500 Lbr Ampelas @ Rp. 5,500.00 = Rp 1,375.00
0.0200 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 130.00
0.1000 Kg Cat dasar @ Rp. 30,000.00 = Rp 3,000.00
0.2600 Kg Cat penutup 2x @ Rp. 30,000.00 = Rp 7,800.00
Sub total : = Rp 14,010.00
Upah An. SNI ( Revisi ) 6.14.2
0.0200 Oh Pekerja @ Rp. 100,000.00 = Rp 2,000.00
0.0630 Oh Tukang cat @ Rp. 120,000.00 = Rp 7,560.00
0.0063 Oh Kepala tukang @ Rp. 125,000.00 = Rp 787.50
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 10,347.50
Total upah+bahan : = Rp 24,357.50
Cat LAMA.
17 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat penutup )Cat Paragon /Decolith
Bahan An. SNI ( Revisi ) 6.14.1
0.0100 Kg Plamir @ Rp. 17,050.00 = Rp 170.50
0.1200 Lbr Ampelas @ Rp. 5,500.00 = Rp 660.00
0.0333 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 216.67
0.1100 Kg Cat dasar @ Rp. #REF! = Rp #REF!
0.2200 Kg Cat penutup 2x @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
- 92 -
Upah An. SNI ( Revisi ) 6.14.2
0.0280 Oh Pekerja @ Rp. 100,000.00 = Rp 2,800.00
0.0420 Oh Tukang cat @ Rp. 120,000.00 = Rp 5,040.00
0.0042 Oh Kepala tukang @ Rp. 125,000.00 = Rp 525.00
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 8,365.00
Total upah+bahan : = Rp #REF!
18 1 m2 Pengecatan tembok lama ( Ngamplas, 1x cat dasar, 2x cat penutup )Cat I.C.I. Catilac
Bahan An. SNI ( Revisi ) 6.14.1
0.0100 Kg Plamir @ Rp. 17,050.00 = Rp 170.50
0.1200 Lbr Ampelas @ Rp. 5,500.00 = Rp 660.00
0.0333 Bh Kuwas / roll @ Rp. 6,500.00 = Rp 216.67
0.1100 Kg Cat dasar @ Rp. 30,000.00 = Rp 3,300.00
0.2200 Kg Cat penutup 2x @ Rp. 30,000.00 = Rp 6,600.00
Sub total : = Rp 10,947.17
Upah An. SNI ( Revisi ) 6.14.2
0.0280 Oh Pekerja @ Rp. 100,000.00 = Rp 2,800.00
0.0420 Oh Tukang cat @ Rp. 120,000.00 = Rp 5,040.00
0.0042 Oh Kepala tukang @ Rp. 125,000.00 = Rp 525.00
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 8,365.00
Total upah+bahan : = Rp 19,312.17
- 93 -
0.0020 m3 Andang andang @ Rp. 300,000.00 = Rp 600.00
0.3000 Kg Kapur sirih @ Rp. 2,750.00 = Rp 825.00
Sub total : = Rp 1,425.00
Upah An. SNI ( Revisi ) 6.18.2
0.0400 Oh Pekerja @ Rp. 100,000.00 = Rp 4,000.00
0.0050 Oh Tukang cat @ Rp. 120,000.00 = Rp 600.00
0.0005 Oh Kepala tukang @ Rp. 125,000.00 = Rp 62.50
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 4,662.50
Total upah+bahan : = Rp 6,087.50
22 1 m2 Pemasangan wallpaper
Bahan An. SNI ( Revisi ) 6.19.1
1.2000 m2 Wall paper @ Rp. 45,000.00 = Rp 54,000.00
0.2000 Kg Perekat @ Rp. 10,750.00 = Rp 2,150.00
Sub total : = Rp 56,150.00
Upah An. SNI ( Revisi ) 6.19.2
0.0200 Oh Pekerja @ Rp. 100,000.00 = Rp 2,000.00
0.2000 Oh Tukang cat @ Rp. 120,000.00 = Rp 24,000.00
0.0020 Oh Kepala tukang @ Rp. 125,000.00 = Rp 250.00
0.0025 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 26,250.00
Total upah+bahan : = Rp 82,400.00
- 94 -
0.0400 Kg Alluminium C @ Rp. 22,500.00 = Rp 900.00
0.0400 Kg Alluminium B @ Rp. 26,250.00 = Rp 1,050.00
0.0100 Ltr Pengencer @ Rp. 11,550.00 = Rp 115.50
0.0020 m3 Andang andang @ Rp. 300,000.00 = Rp 600.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.22.2
0.0400 Oh Pekerja @ Rp. 100,000.00 = Rp 4,000.00
0.5000 Oh Tukang cat @ Rp. 120,000.00 = Rp 60,000.00
0.0500 Oh Kepala tukang @ Rp. 125,000.00 = Rp 6,250.00
0.0250 Oh Mandor @ Rp. 0.00 = Rp 0.00
. Sub total : = Rp 70,250.00
Total upah+bahan : = Rp #REF!
28 1 m2 Pengecatan permukaan baja lapis seng ( galbani ) secara semprot ( airless spray )
sistem 1 lapis cat mutakhir dengan tebal 200 um
Bahan An. SNI ( Revisi ) 6.25.1
0.3000 Kg Cat dasar @ Rp. 45,000.00 = Rp 13,500.00
Peralatan Lumsum = Rp 3,000.00
Sub total : = Rp 16,500.00
- 95 -
PEKERJAAN PENUTUP LANTAI
1 1 m2 Pasang lantai ubin warna akuran 40 x 40 cm
Bahan An. SNI ( Revisi ) 6.4.1
6.6300 Bh Ubin warna 40 x 40 cm @ Rp. #REF! = Rp #REF!
9.8000 kg Semen portland @ Rp. 1,675.00 = Rp 16,415.00
0.0230 m3 Pasir pasang @ Rp. 165,000.00 = Rp 3,795.00
0.3000 Kg Semen warna @ Rp. 8,250.00 = Rp 2,475.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.4.2
0.2500 Oh Pekerja @ Rp. 100,000.00 = Rp 25,000.00
0.1200 Oh Tukang batu @ Rp. 120,000.00 = Rp 14,400.00
0.0120 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,500.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 40,900.00
Total upah+bahan : = Rp #REF!
- 96 -
0.2600 Oh Pekerja @ Rp. 100,000.00 = Rp 26,000.00
0.1250 Oh Tukang batu @ Rp. 120,000.00 = Rp 15,000.00
0.0125 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,562.50
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Biaya poles. Lumsum = Rp 1,750.00
Sub total : = Rp 44,312.50
Total upah+bahan : = Rp #REF!
- 97 -
8.1900 kg Semen portland @ Rp. 1,675.00 = Rp 13,718.25
0.0450 m3 Pasir pasang @ Rp. 165,000.00 = Rp 7,425.00
0.2500 Kg Semen warna @ Rp. 8,250.00 = Rp 2,062.50
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.13.2
0.2500 Oh Pekerja @ Rp. 100,000.00 = Rp 25,000.00
0.1200 Oh Tukang batu @ Rp. 120,000.00 = Rp 14,400.00
0.0120 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,500.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Biaya poles. @ Rp. = Rp 1,750.00
Sub total : = Rp 42,650.00
Total upah+bahan : = Rp #REF!
- 98 -
0.0900 Oh Tukang batu @ Rp. 120,000.00 = Rp 10,800.00
0.0090 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,125.00
0.0450 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 20,925.00
Total upah+bahan : = Rp #REF!
- 99 -
3.9261 kg Kapur bubuk @ Rp. 2,750.00 = Rp 10,796.78
0.0420 m3 Pasir pasang @ Rp. 165,000.00 = Rp 6,930.00
0.2000 Kg Semen warna @ Rp. 8,250.00 = Rp 1,650.00
Sub total : = Rp 97,487.06
Upah An. SNI ( Revisi ) 6.47.2
0.2200 Oh Pekerja @ Rp. 100,000.00 = Rp 22,000.00
0.1000 Oh Tukang batu @ Rp. 120,000.00 = Rp 12,000.00
0.0120 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,500.00
0.0125 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 35,500.00
Total upah+bahan : = Rp 132,987.06
- 100 -
18 1 m2 Pasang lantai karpet 80% wool, 20% nylon
Bahan An. SNI ( Revisi ) 6.53.1
1.0500 m2 Carpet 80% wool, 20% nylo @ Rp. 155,000.00 = Rp 162,750.00
0.3500 Kg Lem vinyl @ Rp. 40,150.00 = Rp 14,052.50
Sub total : = Rp 176,802.50
Upah An. SNI ( Revisi ) 6.53.2
0.1700 Oh Pekerja @ Rp. 100,000.00 = Rp 17,000.00
0.1700 Oh Tukang @ Rp. 120,000.00 = Rp 20,400.00
0.0170 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,125.00
0.0085 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 39,525.00
Total upah+bahan : = Rp 216,327.50
- 101 -
22 1 m2 Pasang dinding keramik 20 x 25 cm
Bahan An. SNI ( Revisi ) 6.69.1
1.0500 m2 Keramik 20 x 25 cm @ Rp. #REF! = Rp #REF!
6.9285 kg Semen portland @ Rp. 1,675.00 = Rp 11,605.24
2.3715 kg Kapur bubuk @ Rp. 2,750.00 = Rp 6,521.63
0.0180 m3 Pasir pasang @ Rp. 165,000.00 = Rp 2,970.00
0.4000 Kg Semen warna @ Rp. 8,250.00 = Rp 3,300.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.69.2
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
- 102 -
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0130 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 48,500.00
Total upah+bahan : = Rp #REF!
- 103 -
0.0075 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 34,875.00
Total upah+bahan : = Rp #VALUE!
1 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm.
Bahan An. SNI ( Revisi )
36.0000 Bj Paving type "S" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
2 1 m2 Pasang PAVING STONE Abu abu TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm.
Bahan An. SNI ( Revisi )
36.0000 Bj Paving type "S" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
- 104 -
3 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
36.0000 Bj Paving type "S" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
4 1 m2 Pasang PAVING STONE warna merah TYPE S.( DT -1 ) EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
36.0000 Bj Paving type "S" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
5 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35.0000 Bj Paving type "Tiga berlian" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
6 1 m2 Pasang PAVING STONE Abu abu TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35.0000 Bj Paving type "Tiga berlian" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
7 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
35.0000 Bj Paving type "Tiga berlian" @ Rp. #REF! = Rp #REF!
- 105 -
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
8 1 m2 Pasang PAVING STONE Warna Merah TYPE tiga berlian EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
35.0000 Bj Paving type "Tiga berlian" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
9 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
46.0000 Bj Paving type "Segi empat" @ Rp. 1,280.00 = Rp 58,880.00
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp 80,055.00
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp 131,355.00
10 1 m2 Pasang PAVING STONE Abu abu TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46.0000 Bj Paving type "Segi empat" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
11 1 m2 Pasang PAVING STONE warna merah TYPE segi empat EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
46.0000 Bj Paving type "Segi empat" @ Rp. 1,250.00 = Rp 57,500.00
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp 78,675.00
Upah An. SNI ( Revisi )
- 106 -
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp 129,975.00
12 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 6 Cm
Bahan An. SNI ( Revisi )
26.0000 Bj Paving type "Segi ENAM" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
13 1 m2 Pasang PAVING STONE Warna merah TYPE segi enam EX Dinoyo / UPS. tebal 8 Cm
Bahan An. SNI ( Revisi )
26.0000 Bj Paving type "Segi ENAM" @ Rp. #REF! = Rp #REF!
0.1210 m3 Pasir urug 10 Cm. @ Rp. 175,000.00 = Rp 21,175.00
Sub total : = Rp #REF!
Upah An. SNI ( Revisi )
0.2480 Oh Pekerja @ Rp. 100,000.00 = Rp 24,800.00
0.2000 Oh Tukang batu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0100 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 51,300.00
Total upah+bahan : = Rp #REF!
- 107 -
0.2000 Oh Pekerja @ Rp. 100,000.00 = Rp 20,000.00
0.1500 Oh Tukang batu @ Rp. 120,000.00 = Rp 18,000.00
0.0150 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,875.00
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 39,875.00
Total upah+bahan : = Rp 54,825.00
- 108 -
Sub total : = Rp 85,500.00
Total upah+bahan : = Rp #REF!
- 109 -
0.1000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 12,000.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0005 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 14,250.00
Total upah+bahan : = Rp 34,250.00
- 110 -
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.11.2
0.0200 Oh Pekerja @ Rp. 100,000.00 = Rp 2,000.00
0.2000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 24,000.00
0.0200 Oh Kepala tukang @ Rp. 125,000.00 = Rp 2,500.00
0.0010 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 28,500.00
Total upah+bahan : = Rp #REF!
- 111 -
16 1 buah pasang rel pintu dorong
Bahan An. SNI ( Revisi ) 6.14.1
1.0000 Bh Rel pintu dorong @ Rp. #REF! = Rp #REF!
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.14.2
0.0600 Oh Pekerja @ Rp. 100,000.00 = Rp 6,000.00
0.6000 Oh Tukang kayu @ Rp. 120,000.00 = Rp 72,000.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0030 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 85,500.00
Total upah+bahan : = Rp #REF!
- 112 -
Sub total : = Rp 21,375.00
Total upah+bahan : = Rp #REF!
- 113 -
0.1500 Oh Tukang kayu @ Rp. 120,000.00 = Rp 18,000.00
0.0150 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,875.00
0.0008 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 21,375.00
Total upah+bahan : = Rp #REF!
PEKERJAAN SANITAIR
- 114 -
Upah An. SNI ( Revisi ) 6.4.2
1.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 100,000.00
1.0000 Oh Tukang batu @ Rp. 120,000.00 = Rp 120,000.00
0.1000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 12,500.00
0.1000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 232,500.00
Total upah+bahan : = Rp #REF!
- 115 -
Sub total : = Rp #REF!
Upah An. SNI ( Revisi ) 6.8.2
6.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 600,000.00
3.0000 Oh Tukang batu @ Rp. 120,000.00 = Rp 360,000.00
0.3000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 37,500.00
0.3000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 997,500.00
Total upah+bahan : = Rp #REF!
- 116 -
3.0000 Oh Pekerja @ Rp. 100,000.00 = Rp 300,000.00
4.5000 Oh Tukang batu @ Rp. 120,000.00 = Rp 540,000.00
0.9000 Oh Kepala tukang @ Rp. 125,000.00 = Rp 112,500.00
0.9000 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 952,500.00
Total upah+bahan : = Rp #REF!
16 Memasang 1 buah bak kontrol pas. batu bata ( 30x30 ) cm, tinggi 35 cm
Bahan An. SNI ( Revisi ) 6.16.1
0.1450 Bh Batu bata @ Rp. 650.00 = Rp 94.25
44.0000 kg Semen portland @ Rp. 1,675.00 = Rp 73,700.00
0.0700 m3 Pasir pasang @ Rp. 165,000.00 = Rp 11,550.00
0.0700 m3 Batu kerikil @ Rp. 255,000.00 = Rp 17,850.00
1.6000 Kg Besi beton @ Rp. 11,500.00 = Rp 18,400.00
0.0600 m3 Pasir beton @ Rp. 225,000.00 = Rp 13,500.00
Sub total : = Rp 135,094.25
Upah An. SNI ( Revisi ) 6.16.2
0.1667 Oh Pekerja @ Rp. 100,000.00 = Rp 16,666.67
1.0150 Oh Tukang batu @ Rp. 120,000.00 = Rp 121,800.00
0.0015 Oh Kepala tukang @ Rp. 125,000.00 = Rp 187.50
0.0160 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 138,654.17
Total upah+bahan : = Rp 273,748.42
17 Memasang 1 buah bak kontrol pas. batu bata ( 45x45 ) cm, tinggi 50 cm
- 117 -
Bahan An. SNI ( Revisi ) 6.17.1
0.2500 Bh Batu bata @ Rp. 650.00 = Rp 162.50
77.0000 kg Semen portland @ Rp. 1,675.00 = Rp 128,975.00
0.1300 m3 Pasir pasang @ Rp. 165,000.00 = Rp 21,450.00
0.0200 m3 Batu kerikil @ Rp. 255,000.00 = Rp 5,100.00
2.6000 Kg Besi beton @ Rp. 11,500.00 = Rp 29,900.00
0.0900 m3 Pasir beton @ Rp. 225,000.00 = Rp 20,250.00
Sub total : = Rp 205,837.50
Upah An. SNI ( Revisi ) 6.17.2
1.4200 Oh Pekerja @ Rp. 100,000.00 = Rp 142,000.00
0.4700 Oh Tukang batu @ Rp. 120,000.00 = Rp 56,400.00
0.0470 Oh Kepala tukang @ Rp. 125,000.00 = Rp 5,875.00
0.0710 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 204,275.00
Total upah+bahan : = Rp 410,112.50
18 Memasang 1 buah bak kontrol pas. batu bata ( 60x60 ) cm, tinggi 65 cm
Bahan An. SNI ( Revisi ) 6.18.1
0.3710 Bh Batu bata @ Rp. 650.00 = Rp 241.15
114.0000 kg Semen portland @ Rp. 1,675.00 = Rp 190,950.00
0.1840 m3 Pasir pasang @ Rp. 165,000.00 = Rp 30,360.00
0.0330 m3 Batu kerikil @ Rp. 255,000.00 = Rp 8,415.00
4.8500 Kg Besi beton @ Rp. 11,500.00 = Rp 55,775.00
0.1200 m3 Pasir beton @ Rp. 225,000.00 = Rp 27,000.00
Sub total : = Rp 312,741.15
Upah An. SNI ( Revisi ) 6.18.2
2.1600 Oh Pekerja @ Rp. 100,000.00 = Rp 216,000.00
0.7200 Oh Tukang batu @ Rp. 120,000.00 = Rp 86,400.00
0.0720 Oh Kepala tukang @ Rp. 125,000.00 = Rp 9,000.00
0.1080 Oh Mandor @ Rp. 0.00 = Rp 0.00
0.1000 Oh Tukang gali @ Rp. 120,000.00 = Rp 12,000.00
Sub total : = Rp 323,400.00
Total upah+bahan : = Rp 636,141.15
- 118 -
Sub total : = Rp 17,325.00
Total upah+bahan : = Rp #VALUE!
- 119 -
Bahan An. SNI ( Revisi ) 6.25.1
1.2000 m' Pipa PVC @ Rp. #VALUE! = Rp #VALUE!
35.0000 % Perlengkapan = Rp #VALUE!
Sub total : = Rp #VALUE!
Upah An. SNI ( Revisi ) 6.25.2
0.0360 Oh Pekerja @ Rp. 100,000.00 = Rp 3,600.00
0.0600 Oh Tukang batu @ Rp. 120,000.00 = Rp 7,200.00
0.0060 Oh Kepala tukang @ Rp. 125,000.00 = Rp 750.00
0.0018 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 11,550.00
Total upah+bahan : = Rp #VALUE!
- 120 -
0.0360 Oh Pekerja @ Rp. 100,000.00 = Rp 3,600.00
0.0600 Oh Tukang batu @ Rp. 120,000.00 = Rp 7,200.00
0.0060 Oh Kepala tukang @ Rp. 125,000.00 = Rp 750.00
0.0018 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 11,550.00
Total upah+bahan : = Rp 52,237.50
- 121 -
0.0050 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 14,250.00
Total upah+bahan : = Rp 49,312.50
.
1 1 m2 Pemasangan Plafond Gypsum Rangka Plafon Metal Furing
Upah 0.0750 Oh Mandor @ Rp. - = Rp -
0.0250 Oh Kepala Tukang Kayu @ Rp. 125,000.00 = Rp 3,125.00
0.2500 Oh Pembantu Tukang @ Rp. 100,000.00 = Rp 25,000.00
0.1500 Oh Tukang Kayu @ Rp. 120,000.00 = Rp 18,000.00
Sub total : = Rp 46,125.00
- 122 -
0.0010 Oh Pekerja Terampil @ Rp. 100,000.00 = Rp 100.00
Sub total : = Rp 30,350.00
Bahan
Bahan 1.0000 Buah Stop Kontak (broco) @ Rp. 40,000.00 = Rp 40,000.00
10.0000 m1 Kabel NYA 500 Volt 2 x 2,5 @ Rp. 9,500.00 = Rp 95,000.00
1.0000 Lonjor Pipa Pralon 5/8 @ Rp. 8,000.00 = Rp 8,000.00
1.0000 Buah T Doos Pvc @ Rp. 1,500.00 = Rp 1,500.00
Sub total : = Rp 144,500.00
Total upah+bahan : = Rp 174,850.00
- 123 -
0.0600 tube Sealent @ Rp. 50,000.00 = Rp 3,000.00
2.0000 Buah Skrup/Ripet @ Rp. 3,700.00 = Rp 7,400.00
Sub total : = Rp 87,400.00
Total upah+bahan : = Rp 97,397.50
Bahan 1.2000 Jam Sewa Alat Bantu Strouss Pile@ Rp. 10,000.00 = Rp 12,000.00
Sub total : = Rp 12,000.00
Total upah+bahan : = Rp 132,000.00
- 124 -
35.0000 % Perlengkapan = Rp 40,320.00
Sub total : = Rp 155,520.00
Upah An. SNI ( Revisi ) 6.24.2
0.1620 Oh Pekerja @ Rp. 100,000.00 = Rp 16,200.00
0.2700 Oh Tukang besi @ Rp. 120,000.00 = Rp 32,400.00
0.0270 Oh Kepala tukang @ Rp. 125,000.00 = Rp 3,375.00
0.0239 Oh Mandor @ Rp. - = Rp -
Sub total : = Rp 51,975.00
Total upah+bahan : = Rp 207,495.00
13 1Bh. Pasang daun jendela Bowven aluminium 2" coklat (Brown) UKURAN 40 X 40 Cm.
( Jendela isian kaca 5mm).
Bahan An. SNI ( Revisi ) 6.3.1
1.6000 m1 Slimar Aluminium coklat 2" @ Rp. 68,200.00 = Rp 109,120.00
4.0000 m1 Karet penjepit kaca/ tripleks @ Rp. 3,190.00 = Rp 12,760.00
1.0000 set Engsel jendela. @ Rp. 20,000.00 = Rp 20,000.00
1.0000 Bh Hak window . @ Rp. 45,000.00 = Rp 45,000.00
0.2500 m2 Kaca bening 5 mm @ Rp. 110,000.00 = Rp 27,500.00
Sub total : = Rp 214,380.00
- 125 -
0.0250 Oh Kepala Tukang Kayu @ Rp. 125,000.00 = Rp 3,125.00
0.1500 Oh Tukang Kayu @ Rp. 120,000.00 = Rp 18,000.00
0.2500 Oh Pekerja/Buruh Tak Terampil @ Rp. 100,000.00 = Rp 25,000.00
Sub total : = Rp 46,125.00
Bahan :
Bahan 0.7500 m1 Besi Hollow 40/40 @ Rp. 23,000.00 = Rp 17,250.00
2.0000 m1 Besi Hollow 20/20 @ Rp. 17,500.00 = Rp 35,000.00
4.0000 Buah Skrup @ Rp. 3,700.00 = Rp 14,800.00
Sub total : = Rp 67,050.00
Total upah+bahan : = Rp 113,175.00
- 126 -
21 1 m1 Pemasangan List Kayu
- 127 -
27 1 m2 Pemasangan Pelapis Vinyl HPL hitam "arborite"
0.0013 Oh Mandor @ Rp. - = Rp -
0.0075 Oh Kepala Tukang Kayu @ Rp. 125,000.00 = Rp 937.50
0.0750 Oh Tukang Kayu @ Rp. 125,000.00 = Rp 9,375.00
0.0250 Oh Pekerja/Buruh Tak Terampil @ Rp. 100,000.00 = Rp 2,500.00
0.4000 lembaVinyl HPL hitam "arborite" , @ Rp. 300,000.00 = Rp 120,000.00
0.0500 kg Paku biasa 1/2" - 1" - -
Total : = Rp 132,812.50
- 128 -
0.5000 Kg Shanding @ Rp. 72,737.50 = Rp 36,368.75
0.2000 Kg Clear Doof @ Rp. 64,471.88 = Rp 12,894.38
0.8370 Liter Thinner A @ Rp. 28,566.00 = Rp 23,909.74
0.2000 Kalen Coumpond @ Rp. 39,542.75 = Rp 7,908.55
1.0000 Set Sewa Alat Bantu ( 1 Set @ 3 @ Rp. 1,000.00 = Rp 1,000.00
0.6250 Jam Sewa Compresor @ Rp. 35,000.00 = Rp 21,875.00
Total : = Rp 142,557.67
- 129 -
ANALISA HARGA BAHAN
1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps
Bahan An. SNI ( Revisi ) 6.13.1
### Bh Bata merah 5 x 11 x 22 cm @ Rp. 650.00 = Rp 45,500.00
8.3200 kg Semen portland @ Rp. 1,675.00 = Rp 13,936.00
0.0490 m3 Pasir pasang @ Rp. 165,000.00 = Rp 8,085.00
Sub total : = Rp 67,521.00
Upah An. SNI ( Revisi ) 6.13.2
0.3000 Oh Pekerja @ Rp. 100,000.00 = Rp 30,000.00
0.1000 Oh Tukang batu @ Rp. 120,000.00 = Rp 12,000.00
0.0100 Oh Kepala tukang @ Rp. 125,000.00 = Rp 1,250.00
0.0150 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 43,250.00
Total upah+bahan : = Rp 110,771.00
Total per : M3 = Rp 728,440.92
1 m2 acian
Bahan An. SNI ( Revisi ) 6.35.1
4.3200 kg Semen portland @ Rp. 1,675.00 = Rp 7,236.00
Sub total : = Rp 7,236.00
1 m2 Plesteran siar / setrikan adukan, 1 Pc : 2 Ps
Upah An. SNI ( Revisi ) 6.35.2
0.1000 Oh Pekerja @ Rp. 100,000.00 = Rp 10,000.00
0.0400 Oh Tukang batu @ Rp. 120,000.00 = Rp 4,800.00
0.0040 Oh Kepala tukang @ Rp. 125,000.00 = Rp 500.00
0.0060 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 15,300.00
Total upah+bahan : = Rp 22,536.00
1 m' Benangan
Bahan 2.2500 kg Semen portland @ Rp. 1,675.00 = Rp 3,768.75
Sub total : = Rp 3,768.75
1 m2 Membuat plat lantai tebal 12 Cm dengan besi polos diameter 10 mm , pembagi 8 mm.
Bahan An. SNI ( Revisi ) 6.42.1
0.0384 m3 Kayu terentang/Meranti (MC) @ Rp. 3,025,000.00 = Rp 116,160.00
- Kg Paku biasa 2" - 5 " @ Rp. 14,200.00 = Rp 0.00
0.1920 Ltr Minyak bekisting @ Rp. 11,550.00 = Rp 2,217.60
5.6900 Kg Besi beton polos 10 mm & 8 mm @ Rp. 11,500.00 = Rp 65,435.00
0.2250 Kg Kawat beton @ Rp. 16,500.00 = Rp 3,712.50
### kg Semen portland @ Rp. 1,675.00 = Rp 64,923.00
0.0624 m3 Pasir beton @ Rp. 225,000.00 = Rp 14,040.00
0.0936 m3 Koral beton @ Rp. 255,000.00 = Rp 23,868.00
0.0144 m3 Balok kayu borneo @ Rp. 4,363,333.00 = Rp 62,832.00
0.3500 Lbr Plywood tebal 9 mm @ Rp. 110,000.00 = Rp 38,500.00
3.5000 Btg Dolken kayu galam Ø 8 / 4 m @ Rp. 56,000.00 = Rp 196,000.00
Sub total : = Rp 587,688.10
Upah An. SNI ( Revisi ) 6.42.2
0.6960 Oh Pekerja @ Rp. 100,000.00 = Rp 69,600.00
0.0420 Oh Tukang batu @ Rp. 120,000.00 = Rp 5,040.00
0.3360 Oh Tukang kayu @ Rp. 120,000.00 = Rp 40,320.00
0.1260 Oh Tukang besi @ Rp. 120,000.00 = Rp 15,120.00
0.0504 Oh Kepala tukang @ Rp. 125,000.00 = Rp 6,300.00
0.0222 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 136,380.00
Total upah+bahan : = Rp 724,068.10
Biaya pembuatan plat lantai per 1 M2 tebal 12 Cm dengan besi dia 10 - 12
dan besi polos dia 8 - 15 = Rp 724,068.10
Analog biaya / = 724,068.10 x 8.33 = Rp 6,031,487.23
1 m2 Pasang atap genteng bambe / good year / Jatiwangi type Alto.Kw 1.
Bahan An. SNI ( Revisi ) 6.3.1
### Bh Genteng plenthong super @ Rp. 3,900.00 = Rp 81,900.00
Sub total : = Rp 81,900.00
Upah An. SNI ( Revisi ) 6.3.2
0.1500 Oh Pekerja @ Rp. 100,000.00 = Rp 15,000.00
0.0600 Oh Tukang kayu @ Rp. 120,000.00 = Rp 7,200.00
0.0600 Oh Kepala tukang @ Rp. 125,000.00 = Rp 7,500.00
0.0080 Oh Mandor @ Rp. 0.00 = Rp 0.00
Sub total : = Rp 29,700.00
Total upah+bahan : = Rp 111,600.00
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan lokasi 1.000 Ls 500,000.00 500,000.00
2 Pek. Pembong. Bangunan lama 154.000 m2 #REF! #REF!
3 Pek. Uitset & pengkuran 38.000 M1 81,009.00 3,078,342.00
Jumlah #REF!
II PEKERJAAN TANAH
1 Pek. Galian tanah 34.000 m3 #REF! #REF!
3 Pek. Pengeboran strous Ø 25 m 96.000 m1 45,000.00 4,320,000.00
3 Pek. Urugan kembali 20.400 m3 #REF! #REF!
4 Pek. Urugan sirtu peninggian lantai 75.000 m3 #REF! #REF!
5 Pek. Urugan bawah pondasi 9.900 m3 #REF! #REF!
Jumlah #REF!
III PEKERJAAN PASANGAN
1 Pek. Pas. Rollag bata 1 Pc : 6 Psr 2.858 m3 728,440.92 2,081,519.94
2 Pek. Pas. Bata 1 Pc : 6 Psr 492.450 m2 110,771.00 54,549,178.95
3 Pek. Plesteran dinding (1 : 6 ) 984.900 m2 49,834.00 49,081,506.60
4 Pek. Acian dinding 984.900 m2 22,536.00 22,195,706.40
5 Pek. Benangan 246.225 m2 15,768.75 3,882,660.47
6 Pek. Pas. Batu alam 24.000 m2 #REF! #REF!
Jumlah #REF!
IV PEKERJAAN BETON
1 Pek. Rabatan bawah pondasi 1.650 m3 #REF! #REF!
2 Pek. Pengecoran Strous 6.720 m3 4,401,652.70 29,579,106.14
3 Pek. Beton plat beton setempat 100x100x20 cm 5.800 m3 #REF! #REF!
4 Pek. Beton plat beton setempat 80x80x15 cm 0.576 m3 #REF! #REF!
5 Pek. Beton sloof 15/20 1.028 m3 #REF! #REF!
6 Pek. Beton sloof 20/30 7.380 m3 4,401,652.70 32,484,196.93
7 Pek. Beton kolom praktis 15/12 0.738 m3 4,971,504.95 3,668,970.65
8 Pek. Kolom Ø 27 cm 0.461 m3 4,971,504.95 2,289,875.18
9 Pek. Beton kolom 25/25 10.413 m3 4,971,504.95 51,765,795.24
10 Pek. Balok 20/40 3.422 m3 6,809,624.42 23,305,258.60
11 Pek. Balok 20/30 4.464 m3 6,809,624.42 30,398,163.39
12 Pek. Balok latei 12/20 0.864 m3 4,788,947.63 4,137,650.75
13 Pek. Ring balk 12/20 1.008 m3 4,788,947.63 4,827,259.21
14 Pek. Plat Lantai penutup saluran t = 12 cm 2.100 m3 6,031,487.23 12,666,123.19
15 Pek. Plat Lantai t = 12 cm 26.400 m3 6,031,487.23 159,231,262.95
Jumlah #REF!
V PEKERJAAN ATAP & PLAFOND
1 Pek. Penutup atap zincalume t = 0,3 mm 96.950 m2 #REF! #REF!
2 Pek. Kuda-kuda WF. 200.100 362.100 Kg 23,833.00 8,629,929.30
3 Pek. Gording canal C 100.50 349.566 Kg 23,833.00 8,331,206.48
4 Pek. Ikatan angin 34.957 Kg 23,833.00 833,120.65
5 Pek. Baut Ø 16 36.000 Bh 16,500.00 594,000.00
6 Pek. Lisplank kalsiplank 1/30 37.300 m1 44,702.00 1,667,384.60
7 Pek. Talang galvalume + papan talang 12.500 m1 #REF! #REF!
8 Pek. Canopi rangka canal C penutup kaca 8 mm 6.000 m2 1,000,000.00 6,000,000.00
9 Pek. Rangka plafond hollow galvalume 40.40 96.950 m2 #REF! #REF!
10 Pek. Penutup plafond gipsum 9 mm 96.950 m2 #REF! #REF!
11 Pek. List plafond gipsum 8 cm 189.000 m1 #REF! #REF!
Jumlah #REF!
VI PEK. PENGECATAN
1 Pek. Pengecatan dinding ex. Dulux 984.900 m2 22,612.17 22,270,722.95
2 Pek. Pengecatan plafond ex. Catylac / setara 96.950 m2 #REF! #REF!
3 Pek. Pengecatan lisplank 11.190 m2 #REF! #REF!
#REF!
HARGA STN JUMLAH HRG TOTAL
NO URAIAN PEKERJAAN VOLUME STN
(Rp.) (Rp.) (Rp.)
VII PEKERJAAN KERAMIK LANTAI
1 Pas. keramik 50 x 50 ex. Platinum 242.000 m2 #REF! #REF!
2 Pas. Keramik dinding 20/25 t = 1,5 25.500 m2 #REF! #REF!
3 Pas. Keramik lantai 20/20 4.500 m2 #REF! #REF!
Jumlah #REF!
VIII PEKERJAAN KUSEN, PINTU & JENDELA
1 Pek. Kusen alumunium 4" 134.600 m1 #REF! #REF!
2 Pek. Kusen alumunium 3" 146.640 m1 #REF! #REF!
3 Pek. Pintu alumunium + kaca 1.000 bh #REF! #REF!
4 Pek. Pintu double teakwood 4.000 bh #REF! #REF!
5 Pek. Jendela alumunium + kaca uk. 0,7x2,10m 10.000 bh #REF! #REF!
6 Pek. Pintu kaca frameless 12 mm tempred + acc 2.000 bh 4,750,000.00 9,500,000.00
7 Kaca 5 mm 57.300 m2 110,000.00 6,303,000.00
8 Pek. Pas. Dinding partisi kalsiboard rangka alumunium 26.900 m2 #REF! #REF!
9 Pek. Pintu PVC 1.000 bh 550,000.00 550,000.00
Jumlah #REF!
IX PEKERJAAN SANITASI
1 Pek. Titik lampu 28.000 Bh 135,000.00 3,780,000.00
2 Pek. Titik stop kontak 11.000 Bh 135,000.00 1,485,000.00
3 Pek. Inst. Jack Atene TV 2.000 Titik 225,000.00 450,000.00
4 Pek. Inst. Jack telepon 2.000 Titik 225,000.00 450,000.00
5 Pek. Lampu DL 18 watt 28.000 Bh 155,000.00 4,340,000.00
6 Pek. Box MCB 5 panel 1.000 Ls 750,000.00 750,000.00
7 Pek. Saklar 10.000 Bh 45,000.00 450,000.00
8 Pek. Stop kontak 11.000 Bh 40,000.00 440,000.00
9 Pek. Saluran air kotor pipa PVC 4 " 15.000 m1 #REF! #REF!
10 Pek. Saluran air pembuangan pipa PVC 3 " 65.000 m1 #REF! #REF!
11 Pek. Saluran air bersih 3/4" 45.000 m1 #REF! #REF!
12 Pek. Closed duduk ex. INA + acc 1.000 Unit #REF! #REF!
13 Pek. Wastafel 2.000 Bh #REF! #REF!
14 Pek. Kran air 4.000 Bh 75,000.00 300,000.00
Jumlah #REF!
REKAPITULASI
RENCANA ANGGARAN BIAYA
JML TOTAL
NO URAIAN PEKERJAAN
(RP)
Terbilang : TUJUH RATUS DUA BELAS JUTA DELAPAN RATUS RIBU RUPIAH
Konsultant Perencana
CV. LAVINA CIPTA PERSADA
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 1.00 Ls 500,000.00 500,000.00
2 Pek. Pengeboran strous 6.00 m1 55,000.00 330,000.00
3 Pek. Galian tanah 4.00 m3 75,000.00 300,000.00
4 Pek. Urugan tanah kembali 1.40 m3 19,200.00 26,880.00
, 1,156,880.00
II PEKERJAAN PASANGAN
1 Pasang bata 1Pc : 6 Ps 22.75 m2 110,771.00 2,520,040.25
2 Plesteran 1Pc : 6Ps 45.50 m2 49,834.00 2,267,447.00
3 Acian 45.50 m2 16,500.00 750,750.00
4 Benangan 73.00 m' 15,768.75 1,151,118.75
6,689,356.00
III PEKERJAAN BETON
1 Pek. Rabatan bawah pondasi 0.120 m3 902,125.00 108,255.00
2 Pek. Beton strous Ø 30 cm 0.424 m3 4,668,445.11 1,978,953.88
3 Pek. Pondasi Plat setempat 100 x 130 x 25 0.650 m3 4,247,895.00 2,761,131.75
4 Kolom 50/50 2.500 m3 4,971,504.95 12,428,762.36
5 Balok gantung 15/45 0.371 m3 6,809,624.42 2,528,073.06
6 Balok ring 15/15 0.165 m3 4,788,947.63 790,176.36
7 Plat = 12 cm 0.330 m3 6,031,487.23 1,990,390.79
22,585,743.20
IV PEK. LETTER TULISAN
1 Pek. Letter tulisan stenlistell 1.00 Ls 4,500,000.00 4,500,000.00
4,500,000.00
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 182.00 m2 22,612.17 4,115,414.33
4,115,414.33
VIII PEKERJAAN INST. LISTRIK & AIR
1 Instalasi Lampu 2.00 titik 225,000.00 450,000.00
2 Pasang lampu SL 25 Watt LED 2.00 bh 325,000.00 650,000.00
3 Pas. Saklar ex. Broco 1.00 bh 45,000.00 45,000.00
1,145,000.00
REKAPITULASI ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN GAPURA DESA
LOKASI : DESA KESAMBI, KEC. PORONG
Sidoarjo, 2016
KONSULTANT PERENCANA
CV. LAVINA CIPTA PERSADA
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5.00 6
I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi 1.00 Ls 595,000.00 595,000.00
2 Pek. Pengurukan lantai peninggian 26.00 m1 157,037.50 4,082,975.00
3 Pek. Galian tanah 13.00 m3 75,000.00 975,000.00
4 Pek. Urugan tanah kembali 7.80 m3 19,200.00 149,760.00
, 5,802,735.00
II PEKERJAAN PASANGAN
1 Pasangan batu kosong aanstampeng 3.12 m3 445,275.00 1,389,258.00
2 Pasangan pondasi batu kali 7.02 m3 700,198.00 4,915,389.96
3 Pasang bata 1Pc : 6 Ps 92.69 m2 110,771.00 10,267,363.99
4 Plesteran 1Pc : 6Ps 185.38 m2 49,834.00 9,238,226.92
5 Acian 185.38 m2 16,500.00 3,058,770.00
6 Benangan 103.40 m' 15,768.75 1,630,488.75
7 Pek.pasang keramik lantai 30 x 30 52.00 m2 132,987.06 6,915,326.99
8 Pek. Paving stone 46.00 m2 131,355.00 6,042,330.00
43,457,154.61
III PEKERJAAN BETON
1 Pek. Rabatan bawah pondasi 0.120 m3 902,125.00 108,255.00
2 Sloof 15/20 0.780 m3 4,401,652.70 3,433,289.11
3 Kolom 15/20 0.960 m3 4,971,504.95 4,772,644.75
4 Balok gantung 15/25 0.270 m3 6,809,624.42 1,838,598.59
5 Balok latei & ring 15/15 1.193 m3 4,788,947.63 5,710,820.04
15,863,607.49
IV PEK. ATAP & PLAFOND
1 Pek. Rangka atap galvalume 67.50 m2 160,000.00 10,800,000.00
2 Pek. Genteng karang pilang 94.50 m2 130,900.00 12,370,050.00
3 Pek. Bumbungan 9.00 m1 128,930.00 1,160,370.00
4 Pek. Lisplank kalsiplank 34.00 m1 65,000.00 2,210,000.00
5 Pek. Rangka plafond hollow 68.00 m2 113,175.00 7,695,900.00
6 Pek. Plafond gipsum 68.00 m2 37,843.00 2,573,324.00
36,809,644.00
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 185.38 m2 22,612.17 4,191,843.46
2 Pek. Pengecatan plafond 58.50 m2 22,612.17 1,322,811.75
5,514,655.21
VIII PEKERJAAN PENGECATAN
1 Pek. Kusen alumunium 4 " 59.00 m1 105,000.00 6,195,000.00
2 Pek. Pintu alumunium + acc 2.00 Bh 1,150,000.00 2,300,000.00
3 Pek.. Jemdela alumunium + acc 4.00 Bh 750,000.00 3,000,000.00
4 Pek. Kaca 5 mm 6.20 m2 215,000.00 1,333,000.00
12,828,000.00
IX PEKERJAAN INST. LISTRIK & AIR
1 Instalasi Lampu 5.00 titik 225,000.00 1,125,000.00
2 Instalasi stop kontak 4.00 titik 174,850.00 699,400.00
3 Pasang lampu SL 25 Watt LED 5.00 bh 325,000.00 1,625,000.00
4 Pas. Saklar ex. Broco 2.00 bh 45,000.00 90,000.00
3,539,400.00
REKAPITULASI ANGGARAN BIAYA
Terbilang : SERATUS EMPAT PULUH SEMBILAN JUTA EMPAT RATUS ENAM BELAS RIBU RUPIAH
Sidoarjo, 2016
KONSULTANT PERENCANA
CV. LAVINA CIPTA PERSADA
II PEKERJAAN TANAH
1 Galian tanah biasa 0.38 m3 75,000.00
2 Urugan tanah kembali 0.13 m3 19,200.00
3 Urugan pasir bawah pondasi 0.04 m3 240,000.00
IV PEKERJAAN BETON
1 Pek. Rabatan bawah pondasi 0.10 m3 902,125.00
2 Pek. Plat setempat 50 x 50 x 15 0.15 m3 4,247,895.00
3 Pek. Sloof 15/20 0.15 m3 4,401,652.70
4 Pek. Kolom 20/20 0.28 m3 4,971,504.95
,
V PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding pagar 5.60 m2 22,612.17
JUMLAH TOTAL
JUMLAH
HARGA
( Rp )
6
150,000.00
150,000.00
28,125.00
2,520.00
9,000.00
39,645.00
780,935.55
279,070.40
92,400.00
176,610.00
1,329,015.95
90,212.50
637,184.25
647,042.95
1,392,021.38
2,766,461.08
126,628.13
126,628.13
4,680,000.00
3,042,000.00
7,722,000.00
12,133,750.16
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5.00 6
I PEKERJAAN PERSIAPAN
1 Pek. Pengurukan lantai peninggian 15.60 m1 157,037.50 2,449,785.00
2 Pek. Galian tanah 15.60 m3 75,000.00 1,170,000.00
3 Pek. Urugan tanah kembali 4.68 m3 19,200.00 89,856.00
, 3,709,641.00
II PEKERJAAN PASANGAN
1 Pasangan batu kosong aanstampeng 3.12 m3 445,275.00 1,389,258.00
2 Pasangan pondasi batu kali 7.02 m3 700,198.00 4,915,389.96
3 Pasang bata 1Pc : 6 Ps 96.64 m2 110,771.00 10,704,909.44
4 Plesteran 1Pc : 6Ps 193.28 m2 49,834.00 9,631,915.52
5 Acian 193.28 m2 17,500.00 3,382,400.00
6 Pek.pasang keramik lantai 30 x 30 52.00 m2 132,987.06 6,915,326.99
36,939,199.91
III PEKERJAAN BETON
1 Sloof 15/20 0.780 m3 4,401,652.70 3,433,289.11
2 Kolom 15/15 0.720 m3 4,971,504.95 3,579,483.56
3 Balok gantung 15/25 0.225 m3 6,809,624.42 1,532,165.49
4 Balok latei & ring 15/15 0.945 m3 4,788,947.63 4,525,555.51
13,070,493.67
IV PEK. ATAP & PLAFOND
1 Pek. Rangka atap galvalume 67.50 m2 170,000.00 11,475,000.00
2 Pek. Genteng karang pilang 67.50 m2 130,900.00 8,835,750.00
3 Pek. Bumbungan 9.00 m1 128,930.00 1,160,370.00
4 Pek. Lisplank kalsiplank 34.00 m1 75,000.00 2,550,000.00
5 Pek. Rangka plafond hollow 68.00 m2 113,175.00 7,695,900.00
6 Pek. Plafond gipsum 68.00 m2 37,843.00 2,573,324.00
34,290,344.00
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding 193.28 m2 22,612.17 4,370,479.57
2 Pek. Pengecatan plafond 58.50 m2 22,612.17 1,322,811.75
5,693,291.32
VIII PEKERJAAN PENGECATAN
1 Pek. Kusen alumunium 4 " 55.57 m1 125,000.00 6,946,600.00
2 Pek. Pintu alumunium + acc 2.00 Bh 1,150,000.00 2,300,000.00
3 Pek.. Jemdela alumunium + acc 4.00 Bh 650,000.00 2,600,000.00
4 Pek. Kaca 5 mm 6.20 m2 270,000.00 1,674,000.00
13,520,600.00
IX PEKERJAAN INST. LISTRIK
1 Instalasi Lampu 5.00 titik 275,000.00 1,375,000.00
2 Instalasi stop kontak 4.00 titik 174,850.00 699,400.00
3 Pasang lampu SL 25 Watt LED 5.00 bh 355,000.00 1,775,000.00
4 Pas. Saklar ex. Broco 2.00 bh 45,000.00 90,000.00
3,939,400.00
REKAPITULASI ANGGARAN BIAYA
Terbilang : SERATUS EMPAT PULUH SEMBILAN JUTA EMPAT RATUS ENAM BELAS RIBU RUPIAH
Sidoarjo, 2016
KONSULTANT PERENCANA
CV. LAVINA CIPTA PERSADA
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SATU- SATUAN HARGA
AN ( Rp ) ( Rp )
1 2 3 4 5.00 6
I PEKERJAAN PERSIAPAN
, 886,801.34
II PEK. PASANGAN DAN PLESTERAN
1 Pasangan batu kumbung penahan 1.08 m3 617,035.26 666,398.08
2 Pasang kanstin 25.00 m1 0.00
3 Pasang pavingstone T=6 cm 59.00 m2 170,830.00 10,078,970.00
4
5
6
10,745,368.08
III PEKERJAAN BETON
1 Sloof 15/20 0.204 m3 4,573,131.00
2 Kolom 15/15 0.648 m3 4,813,235.40
3 Ring balk 12/15 0.108 m3 4,813,235.40
Terbilang : SEMBILAN PULUH SEMBILAN JUTA SEMBILAN RATUS SEMBILAN PULUH SEMBILAN RIBU RUPIAH
Sidoarjo, 2018
ANALISA PERHITUNGAN PEKERJAAN
6,833,941.44
48,959.12
28,202.62
kayu Usuk 4/6 0.571 Btg 4.290 2.45 45,993.60 112,750.03 112,750.03
Tripleks 9 mm 0.728 Lembar 4.290 3.12 144,500.00 451,290.84 451,290.84
Paku 5 cm - 10 cm 0.110 kg 4.290 0.47 15,000.00 7,078.50 7,078.50
Plamur 0.100 kg 4.290 0.43 10,500.00 4,504.50 4,504.50
Cat dasar 0.100 kg 4.290 0.43 22,300.00 9,566.70 9,566.70
Cat penutup 0.260 kg 4.290 1.12 22,300.00 24,873.42 24,873.42
702,835.24
3,714,774.25
Harga Satuan Bahan Upah
No Uraian Analisa Satuan Volume Kebutuhan Total (Rp)
(Rp) (Rp) (Rp)
8 Pek. Pintu alumunium + kaca
Pek. Pintu alumunium + kaca & acc 1.000 bh 5.000 5.00 1,250,000.00 6,250,000.00 6,250,000.00
6,250,000.00
Pek. Jendela alumunium + kaca & Acc 1.000 bh 6.000 6.00 700,000.00 4,200,000.00 4,200,000.00
4,200,000.00
Rangka hollow galvalum 40.40 0.750 m1 103.250 77.44 8,000.00 619,500.00 619,500.00
Assesoris (perkuatan bahan hollow 40.20) 2.000 m1 103.250 206.50 5,750.00 1,187,375.00 1,187,375.00
7,550,156.25
3,883,480.30
5,557,130.78
1,985,032.88
1,500,000.00
83.00
Panjang Lebar tinggi
Pek. Kusen
PJ1 10.24
P1 6.80
p km 4.80
j 7.32
bv 2.32
jumlah item Luas volume (0)
0.45
-
4.29
13,000,000
1.08
13.00
46.00
Total 59.00
25.00
1.50 0.43
2.00 1.15
2.00 1.25
2.00 1.25
2.00 1.25
2.00 0.75
2.00 0.80
2.00 0.95
2.00 0.95
2.00 1.00
2.00 1.05
2.00 1.90
12.30
4.23
0.25
-
0.25
0.50
-
0.50
1.63
-
1.63
1.80
92.25
1.00 2.22
1.00 1.01
1.00 2.09
5.31
86.94
10.97
5.27
16.25
6.27
0.20
12.00 0.65
0.17
0.11
25.50
8.50
27.00
10.24
2.00
2.00
1.00 7.32
6.00
17.56
ANALISA PERHITUNGAN PEKERJAAN
10,178,675.30
532,132.20
1,105,587.50
RENCANA ANGGARAN BIAYA
KEGIATAN :
PEKERJAAN : PEMBANGUNAN JALAN PAVING GANG MUSTAHAL
SUMBER DANA : APBDes
TAHUN ANGGARAN : 2019
LOKASI : DESA WADUNGASIH, KEC. BUDURAN - KAB. SIDOARJO
Wadungasih , 2019
............................................................ ............................................................
REKAPITULASI RENCANA ANGGARAN BIAYA
KEGIATAN :
PEKERJAAN : PEMBANGUNAN JALAN PAVING GANG MUSTAHAL
SUMBER DANA : APBDes
TAHUN ANGGARAN : 2019
LOKASI : DESA WADUNGASIH, KEC. BUDURAN - KAB. SIDOARJO
Wadungasih , 2019
Dibuat Oleh :
Diketahui Oleh : Tim Pelaksana Kegiatan Desa
Kepala Desa
............................................................ ............................................................
9. Memasang 1 m3 Pondasi batu kumbung 1:4
Analisa SNI 6897:2008
A. Bahan Sat. Vol.
m3 27.000
zak 0.550
m3 0.217
C. Peralatan
D. Jumlah (A+B+C)
E. Overhead & Profit 15%
F. Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA KERJA
1 Pekerja L.01
2 Tukang besi L.02
3 Kepala tukang L.03
4 Mandor L.04
B BAHAN
1 Zincalume 0,4mm
2 Paku Skrup 1/2 - 1"
C PERALATAN
Perlengkapan
4 1 m2 Pasang rangka atap Galvalum type U 75.30 - 0,75 mm. Jarank antar kuda2 1 Meter
B TENAGA
Pekerja OH
Tukang alumunium OH
Kepala Tukang OH
Mandor OH
C Jumlah (a+b)
D Overhead & Profit (Contoh 15 %)
E Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01
Tukang batu L.02
Kepala tukang L.03
Mandor L.04
B BAHAN
Ubin abu-abu
Semen Portland
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
No Uraian Kode
A TENAGA
Pekerja L.01
Tukang batu L.02
Kepala tukang L.03
Mandor L.04
B BAHAN
Ubin abu-abu
Semen Portland
Pasir pasang
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Pipa PVC 3/4" M1
Perlengkapan %
C PERALATAN
Peralatan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01 OH
Tukang batu L.03 OH
Kepala tukang L.03 OH
Mandor L.04 OH
B BAHAN
Pipa Pvc 3" M
Perlengkapan %
C PERALATAN
Peralatan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01 OH
Tukang batu L.03 OH
Kepala tukang L.03 OH
Mandor L.04 OH
B BAHAN
Kran air 3/4" Bh
Seal tape Bh
C PERALATAN
Peralatan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
B BAHAN
Floor drain unit
C PERALATAN
Peralatan
D Jumlah (A+B+C)
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01 OH
Tukang alluminium/kaca L.03 OH
Kepala tukang L.03 OH
Mandor L.04 OH
B BAHAN
Jendela alluminium casement m
3 profil
Spigot m
Skrup bh
Karet m
Sealant Tube
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E)
Uraian Harga Satuan
Batu kumbung 30x30x60 @ Rp. 10,000.00 = 270,000.00
Semen portland @ Rp. #REF! = #REF!
Pasir pasang @ Rp. #REF! = #REF!
#REF!
Harga Jumlah
Satuan Koefisien Satuan Harga
(Rp) (Rp)
ls 1.000 2,500.000 -
Jumlah Harga Peralatan -
JA , BAHAN DAN PERALATAN ( A+B+C ) #REF!
10% x D o
RJAAN PER M2 ( D+ E ) #REF!
% 10 #REF!
JUMLAH HARGA ALAT -
#REF!
0% x D (maksimum)
#REF!
% 10 #REF!
JUMLAH HARGA ALAT -
#REF!
0% x D (maksimum)
#REF!
Harga Satuan
Koefisien Jumlah Harga (Rp)
(Rp)
24,967.50
10% x D 2,496.75
27,464.25
57,570.00
10% x D 5,757.00
63,327.00
Harga Satuan
Koefisien Jumlah Harga (Rp)
(Rp)
65,550.00
10% x D 6,555.00
72,105.00
Harga Satuan
Koefisien Jumlah Harga (Rp)
(Rp)
m casement 3 profil
Harga satuan
Koefisien Jumlah Harga(RP)
(RP)
543,060.53
15% x D (maksimum)
543,060.53
DAFTAR HARGA BAHAN BANGUNAN
DAN UPAH KERJA DI WILAYAH KAB. SIDOARJO
DAFTAR HARGA BAHAN BANGUNAN TERTINGGI PERIODE SEMESTER I TAHUN 2019
SEBELUM PPN
II BAHAN PEREKAT
Semen (50Kg) Zak 64,000.00
Semen (40Kg) Zak 57,500.00
Semen PC Kg 1,437.50
Semen Warna Kg 12,100.00
MSP Zak 152,500.00
MSP Kg 6,100.00
semen grouting Kg 65,000.00
Additive Ltr 64,500.00
Kapur Padam m3 270,000.00
Kapur Sirih Kg 2,500.00
Stro Rox Kg 24,000.00
Page 166
Tutup Besi Tempa 60 x 60 cm Buah 1,760,000.00
Tutup Besi Tempa 80 x 80 cm Buah 2,475,000.00
Baja Ringan Profil C 75.0,75 Batang 81,000
Baja Ringan Profil C 75.0,75 Kg 18,828
Baja Ringan Profil C 75.0,80 Batang 95,000
Baja Ringan Profil C 75.0,80 Kg 16,009
Baja Ringan Profil C 75.1,00 Batang 128,000
Baja Ringan Profil C 75.1,00 Kg 16,474
Baja Ringan Reng 28.45 Batang 28,000
Baja Ringan Reng 30.40 Batang 29,000
Baja Ringan Reng 30.45 Batang 33,000
Baja Ringan Reng 31.45 Batang 34,000
Baja Ringan Reng 32.45 Batang 35,000
IV BAHAN KAYU
Kayu Klas I (Jati ) m3 15,750,000
Kayu Klas II (Kamper ) m3 8,140,000
Kayu Klas III (Marenti, Keruing , Merbau ) m3 5,275,000
Kayu Klas IV (Sengon Laut, Sono ) m3 3,564,000
Dolken dia 8 s/d 10 cm m3 27,000
Papan kayu kamper m3 8,625,000.00
Kaso-kaso (5 × 7) cm kayu kamper m3 5,175,000.00
Reng (2 × 3) cm kayu kamper m3 6,708,333.33
Kaso-kaso (5 × 7) cm kayu meranti m3 3,500,000.00
Kaso-kaso (5 × 7) cm kayu meranti Btg 75,000.00
Usuk (4x6) cm Kayu meranti m3 3,387,500.00
Kayu meranti (balok) m3 4,861,111.11
Balok kayu kamper m3 5,789,930.56
Bambu (P.600 cm) Btg 35,000.00
Ijuk Kg 5,500
Ijuk M3 80,000
Page 167
Pintu gulung besi/ rolling door besi m2 810,000
Pintu Harmonika Ex. m2 1,350,000
Folding Door PVC m2 550,000.00
Jendela Nako ( Rangka + Kaca 5 mm) m2
Sealent Tube 36,000
VI BAHAN PELAPIS :
Tripleks 3 mm (120x240)mm Lbr 68,000
Tripleks 4 mm (120x240)mm Lbr 103,000
Tripleks 6 mm (120x240)mm Lbr 113,000
Tripleks 9 mm (120x240)mm Lbr 175,000
Tripleks 12 mm Phenolic Film Lbr 199,000
Formica Lbr 45,000
Plastik Aerator Lbr 12,000
Page 168
Plint Ubin (10x30)cm bh 3,427.00
Plint Ubin (10x40)cm bh 4,640.00
Plint Ubin Warna (10x20)cm bh 2,100.00
Plint Ubin Warna (10x30)cm bh 3,727.00
Plint Ubin Warna (10x40)cm bh 4,940.00
Plint Gnanit (10x30)cm bh 45,333.33
Plint Gnanit (10x40)cm bh 49,250.00
Plint Teralux Kerang (10x30)cm bh 5,550.00
Plint Teralux Kerang (10x40)cm bh 7,600.00
Plint Teralux Marmer (10x30)cm bh 5,550.00
Plint Teralux Marmer (10x40)cm bh 7,600.00
Plint Teralux Marmer (10x60)cm bh 14,400.00
Lantai Vinyl Box 700,000.00
Lantai Vinyl Buah 21,000.00
Plint Vinyl 15x30 cm Buah 18,750.00
Plint Vinyl profil 10 cm x 240 cm Batang 110,000.00
Karpet Lantai m2 160,000.00
Underlayer m2 7,250.00
Parquet m2 196,000.00
Floor Hardener Kg 17,600.00
Bata Keramik / Klinker m2 243,569.00
IX BAHAN KACA
Krepyak Nako Buah 16,000
Kaca Polos 3 mm m2 89,500
Kaca Polos 5 mm m2 97,000
Kaca Polos 8 mm m2 207,000
Kaca Polos 10 mm m2 210,000
Kaca Rayban Tebal 5 mm m2 125,000
Kaca Wireglassed 5 mm m2 99,000
Kaca Tempered 12 mm m2 450,000
Page 169
Paku 8 s/d 12 cm Kg 21,500
Paku Skrup Bh 1,500
Paku Payung /Seng 7 cm Kg 28,500.00
Paku Payung /Seng 10 cm Kg 35,000.00
Skrup Gypsum 3 " Bh 300.00
Paku Asbes Sekrup 4 inchi Bh 900.00
Skrup Fixer 4' Bh 950.00
Ramset /Dynabolt Bh 1,800.00
Angkur Bh
XI BAHAN FINISHING :
Cat Dasar Tembok Kg 20,000
Cat tembok (Interior) Kg 25,000
Cat tembok (Exterior) Kg 32,500
Cat tembok (Exterior) weathershield Kg 62,000
Cat Meni Kayu/besi Kg 62,500
Cat Besi/Kayu Kg 57,500
Dempul Besi Kg 50,000
Cat Anti Karat Kg 32,800
Menie A kg 31,500.00
Menie B kg 24,500.00
Politur Liter 71,000.00
Wood Filler Kg 50,000
Vernis Liter 35,800
Wood Stain Liter 70,000
Sanding Sealer Liter 65,000
Melamic Liter 74,600
Teak Oil Liter 80,000
Thinerr Liter 24,500
Plamir Tembok Kg 45,000
Minyak Begisting Liter 30,000
Seal Tape Bh 7,000
Amplas Lbr 8,000.00
Kuwas / roll Bh 25,000.00
Residu/Olie Bekas Liter 2,900.00
Bensin Liter 7,350.00
Solar Liter 12,700.00
Minyak pelumas Liter 45,000.00
Lem Kayu ex. Rajawali kg 12,500.00
Lem Kayu ex. Fox kg 46,800.00
Lem pipa PVC gel Tube 9,000.00
Lem pipa PVC cair Kaleng 46,000.00
Vertical Blind Standart m2 225,000.00
Vertical Blind Backout Deluxe m2 380,000.00
Vertical Blind Solar Screen m2 525,000.00
Wallpaper m 89,000.00
Page 170
Rangka plafond Metal furing m2 135,000.00
Kalsiboard 1200x2400x35mm Lembar 67,900.00
Kalsiboard 1200x2400x35mm m2 23,579.00
Akustik (30x30) cm 9 mm lembar 17,000.00
Akustik (30x60) cm 9 mm lembar 19,500.00
Akustik (60x120) cm 9 mm Lembar 34,500.00
Asbes Semen 100x100 t.4 Lembar
Asbes Semen100 x 100 t.5 Lembar
Asbes Semen 120 x 240 t.6 Lembar
Page 171
U Ditch 200.100-120 cm+Cover (G.20 Ton ) Buah 7,533,460
U Ditch 200.150-120 cm+Cover (G.20 Ton ) Buah 8,941,900
U Ditch 300.100-120 cm+Cover (G.20 Ton ) Buah 13,610,080
U Ditch 300.150-120 cm+Cover (G.20 Ton ) Buah 14,880,580
U Ditch 60.60-120 cm (G.10 Ton ) tanpa cover Buah 655,600
U Ditch 60.80-120 cm (G.10 Ton ) tanpa cover Buah 941,600
DUB 400.300-120 cm (G.20 Ton ) (Top+Bottom) Buah 27,571,060
U Ditch 40.50-120 cm (G.10 Ton ) tanpa cover Buah 484,000
Sheet Pile (FPC 320.500) (Mcr min 13,00 ton.m) m1 758,670
U-ditch 100.100 - 120 cm + cover (G. 10 TON) Buah 2,701,710
DUB 500.200 - 200 cm (G. 20 TON) (TOP + Bottom) Buah 42,075,330
U-ditch 500.150 - 120 cm + Cover (G. 20 TON) Buah 28,666,110
U-ditch 600.150 - 120 cm + Cover (G. 20 TON) Buah 37,667,300.00
U-ditch 50.70 - 120 cm + Cover (G.20 TON) Buah 1,965,040.00
DUB 200.200 - 120 cm (G. 20 TON) ( TOP+Bottom) Buah 10,219,660.00
DUB 300.200 - 120 cm (G. 20 TON) ( TOP+Bottom) Buah 17,399,800.00
Buis beton dia 20 cm m1 77,000.00
Buis beton dia 30 cm m1 104,500.00
Buis beton dia 50 cm m1 126,500.00
Buis beton dia 60 cm m1 181,500.00
Buis beton dia 90 cm m1 231,000.00
Buis beton U dia 20 cm m1 55,000.00
Buis beton U dia 30 cm m1 71,500.00
Tandon Cor 1 m3 Buah 2,695,000.00
Tandon Cor 2 m3 Buah 4,070,000.00
Tandon Cor 3 m3 Buah 4,620,000.00
Tandon Cor 4 m3 Buah 7,260,000.00
Tandon Cor 5 m3 Buah 9,570,000.00
Water Stop PVC 150 m' 55,000.00
Water Stop PVC 200 m' 72,000.00
Water Stop PVC 250 m' 90,000.00
Penjaga jarak bekisting/spacer Buah 1,300.00
XV PERALATAN ELEKTRIKAL
Box panel PVC isi 4 MCB Buah 150,000
MCB 10 Ampere Buah 80,000
MCB 6 Ampere Buah 50,000
MCB 4 A Buah 45,000
MCB 2 Ampere Buah 29,000
Kabel NYM 2 x 2,5 mm2 Buah 14,025
Kabel NYM 3 x 2,5 mm2 Buah 18,900
Kabel Telepon m1 15,000
Kabel UTP Cat 5 e m1 9,754.00
Kabel UTP Cat 6 e m1 11,978.00
Konektor RJ 45 Set 3,125.00
Isolator Buah 7,000
Saklar Tunggal Buah 14,700
Saklar Ganda Buah 14,700
Stop Kontak Buah 24,500
Outlet TV Buah 43,575
Outlet Telephone Buah 43,575
Down light / PLC 13 W Buah 173,460
Fitting Plafon Buah 20,000
Fiting Gantung EX Broco Buah 12,000.00
Lampu TL 2 x 18 watt grille Buah 80,850
Lampu TL 2 x 36 watt grille Buah 110,513
Kabel NYA 1.5 mm m1 3,500.00
Kabel NYA 1.5 mm (50m) m1 97,500.00
Kabel NYA 1.5 mm (100m) rool 300,000.00
Kabel NYA 2 x 1.5 mm m1 6,000.00
Klem Kabel pack 13,000.00
Kabel NYA 500 Volt 2 x 2,5 mm2 m' 9,000.00
Pipa Pralon 5/8 Lonjor 11,500.00
L Bow 5/8 Buah 1,000.00
T Doos Pvc Buah 3,450.00
Page 172
B SEWA PERALATAN
1 ASPHALT MIXING PLANT E01 5,300,000.00
2 ASPHALT FINISHER E02 300,000.00
3 ASPHALT SPRAYER E03 150,000.00
4 BULLDOZER 100-150 HP E04 362,895.00
5 COMPRESSOR 4000-6500 L/M E05 150,000.00
6 CONCRETE MIXER 0.3-0.6 M3 E06 60,000.00
7 CRANE 10-15 TON E07 814,165.00
8 DUMP TRUCK 3.5 TON E08 210,000.00
9 DUMP TRUCK 10 TON E09 210,000.00
10 EXCAVATOR 80-140 HP E10 442,915.00
11 FLAT BED TRUCK 3-4M3 E11 90,000.00
12 GENERATOR SET E12 63,000.00
13 MOTOR GRADER >100 HP E13 477,080.00
14 WHEEL LOADER 1.0-1.6 M3 E15 150,000.00
15 THREE WHEEL ROLLER 6-8 T E16 170,000.00
16 TANDEM ROLLER 6-8 T E17 150,000.00
17 TIRE ROLLER 6-8T E18 150,000.00
18 VIBRATORY ROLLER 5-8T E19 362,895.00
19 CONCRETE VIBRATOR E20 35,000.00
20 WATER TANKER 3000-4500 L. E23 103,000.00
21 PEDESTRIAN ROLLER E24 75,000.00
22 STAMPER E25 30,000.00
23 JACK HAMMER E26 196,000.00
24 CONCRETE PUMP E28 125,000.00
25 TRAILER 20 TON E29 200,000.00
26 PILE DRIVER + HAMMER E30 75,000.00
27 CRANE ON TRACK 35 TON E31 175,000.00
28 WELDING SET E32 155,000.00
29 BORE PILE MACHINE E33 20,000.00
30 TRONTON E35 200,000.00
31 COLD MILLING E36 2,000,000.00
32 AGGREGAT (CHIP) SPREADER E40 584,000.00
33 ASPHALT DISTRIBUTOR E41 150,000.00
34 TRUCK MIXER (AGITATOR) E49 210,000.00
35 BORE PILE MACHINE E50 110,000.00
36 CRANE ON TRACK 75-100 TON E51 175,000.00
37 ASPHALT LIQUID MIXER E34a 150,000.00
38 MESIN LAS E58 150,000.00
39 PILE DRIVER LEADER, 75 kw E59 95,000.00
40 WELDING MACHINE, 300 A E63 150,000.00
41 CHAIN SAW 65,000.00
42 BATCHING PLANT 2,020,000.00
43 PALU/GODAM (BAJA KERAS) 79,000.00
44 PAHAT/BETON (BAJA KERAS) 61,667.00
45 LINGGIS (BAJA KERAS) 73,000.00
46 ALAT UKUR 122,667.00
47 POMPA AIR 201,667.00
48 PONTON 1,750,000.00
49 TRIPOT & TRIMBIS 593,333.00
50 THEODOLITE / WATERPASS 57,500.00
51 Scafolding Set/Hari 27,000
Page 173
C UPAH
1 Pekerja Oh 100,000.00
2 Tukang Batu Oh 120,000.00
3 Tukang Las konstruksi Oh 120,000.00
4 Tukang Cat Oh 120,000.00
5 Tukang Las biasa Oh 120,000.00
6 Tukang alumunium Oh 120,000.00
7 Tukang Kayu Oh 120,000.00
8 Tukang besi Oh 120,000.00
9 Kepala Tukang Oh 125,000.00
10 Mandor Oh 150,000.00
11 Operator jam 20,874.00 166,992.00
12 Pembantu Operator jam 17,874.00 142,992.00
13 Sopir/Driver jam 17,875.00 143,000.00
14 Pembantu Sopir/Driver jam 14,125.00 113,000.00
15 Mekanik jam 19,437.00 155,496.00
16 Pembantu Mekanik jam 17,874.00 142,992.00
17 Juru Ukur jam 19,333.00 154,664.00
Menyetujui : Dibuat :
KABID TATA BANGUNAN DINAS KASI PERENCANAAN TEKNIS BIDANG TATA
PERUMAHAN ,PERMUKIMAN,CIPTA KARYA BANGUNAN BANGUNAN DINAS PERUMAHAN
DAN TATA RUANG KABUPATEN SIDOARJO ,PERMUKIMAN,CIPTA KARYA DAN TATA RUANG
KABUPATEN SIDOARJO
Mengetahui :
KEPALA DINAS DINAS PERUMAHAN ,PERMUKIMAN,CIPTA
KARYA DAN TATA RUANG KABUPATEN SIDOARJO
Ir. SULAKSONO.
Pembina Utama Muda
NIP. 19620129 198903 1 005
Page 174
A.4.2.1.21. Pemasangan 1 m2 rangka hollow galvalum 1x3,5.3,5, modul 60 x 60 cm, untuk pla
A TENAGA
Pekerja L.01 OH 0.250
Tukang aluminium L.02 OH 0.250
Kepala tukang L.03 OH 0.025
Mandor L.04 OH 0.013
JUMLAH TENAGA KERJA
B BAHAN
Rangka hollow galvalum 40.40 M1 4.00
Assesoris (perkuatan dll) % 100.000
JUMLAH HARGA BAHAN
C PERALATAN
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
A TENAGA
Pekerja L.01 OH 0.250 122,992.00
Tukang
L.03 OH 136,992.00
Batu 0.500
Kepala tuk L.03 OH 0.050 147,992.00
Mandor L.04 OH 0.0013 157,992.00
JUMLAH TENAGA KERJA
B BAHAN
Paving block 6 cm m2 1.010 60,000.00
Pasir beton m3 0.050 365,000.00
JUMLAH HARGA BAHAN
C PERALATAN
% 10.000 78,850.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (10 %) 10% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batucampuran 1SP :5PP
A TENAGA
Pekerja L.01 OH 0.300 122,992.00
Tukang
L.03 OH 0.100 136,992.00
Batu
Kepala tuk L.03 OH 0.010 147,992.00
Mandor L.04 OH 0.015 157,992.00
JUMLAH TENAGA KERJA
B BAHAN
Bata merah Buah 70.000 770.00
Semen Portland Kg 9.680 1,312.50
Pasir pasang m3 0.045 300,000.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (10 %) 10% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87
A TENAGA
Pekerja L.01 OH 1.200 122,992.00
Tukang Ba L.02 OH 0.200 136,992.00
Kepala tuk L.03 OH 0.020 147,992.00
Mandor L.04 OH 0.060 157,992.00
JUMLAH TENAGA KERJA
B BAHAN
semen portland kg 230.000 1,312.50
pasir beton kg 893.000 365.00
kerikil (maks 30 mm) kg 1,027.000 163.70
air Liter 200.000 6.50
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (10 %) 10% x D (maksimum)
F Harga Satuan Pekerjaan (D+E)
modul 60 x 60 cm, untuk plafon
Harga Jumlah
Satuan Harga
(Rp) (Rp)
100,000.00 25,000.00
120,000.00 30,000.00
125,000.00 3,125.00
13,500.00 54,000.00
54,000.00 54,000.00
AH HARGA BAHAN 108,000.00
AH HARGA ALAT
166,125.00
D (maksimum)
166,125.00
Jumlah Harga(RP)
30,748.00
68,496.00
7,399.60
205.39
106,848.99
60,600.00
18,250.00
78,850.00
7,885.00
193,583.99
19,358.40
212,942.39
mpuran 1SP :5PP
Jumlah Harga(RP)
36,897.60
13,699.20
1,479.92
2,369.88
54,446.60
53,900.00
12,705.00
13,500.00
80,105.00
134,551.60
13,455.16
148,006.76
m, w/c = 0,87
Jumlah Harga(RP)
147,590.40
27,398.40
2,959.84
9,479.52
187,428.16
301,875.00
325,945.00
168,123.70
1,300.00
797,243.70
984,671.86
98,467.19
1,083,139.05