A. DAFTAR UPAH
1 Pekerja Org/hr Rp 65,000
2 Tukang batu Org/hr Rp 80,000
3 Tukang kayu Org/hr Rp 80,000
4 Tukang besi Org/hr Rp 85,000
5 Tukang Cat Org/hr Rp 75,000
6 Tukang Las Org/hr Rp 85,000
7 Tukang Pipa Org/hr Rp 80,000
8 Tukang Listrik Org/hr Rp 100,000
8 Kepala tukang Org/hr Rp 90,000
9 Mandor Org/hr Rp 100,000
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
TOTAL Rp 919,920.00
OVERHEAD (10%) Rp 91,992.00
SUB TOTAL Rp 1,011,912.00
A-05 1 M2 PEMBUATAN JALAN SEMENTARA
1 Batu Belah 15 / 20 M3 0.15 Rp 225,000.00 Rp 33,750.00
2 Sirtu 5/7 ( Pasir Koral ) M3 0.05 Rp 165,000.00 Rp 8,250.00
3 Pasir Pasang M3 0.01 Rp 225,000.00 Rp 2,250.00
4 Pekerja Oh 1 Rp 65,000.00 Rp 65,000.00
5 Mandor Oh 0.05 Rp 100,000.00 Rp 5,000.00
TOTAL Rp 114,250.00
OVERHEAD (10%) Rp 11,425.00
SUB TOTAL Rp 125,675.00
A-06 1 M2 MEMBERSIHKAN LOKASI PROYEK
1 Pekerja Oh 0.1 Rp 65,000.00 Rp 6,500.00
2 Mandor Oh 0.01 Rp 100,000.00 Rp 1,000.00
TOTAL Rp 7,500.00
OVERHEAD (10%) Rp 750.00
SUB TOTAL Rp 8,250.00
A-06 1 M2 MEMBERSIHKAN PUING-PUING
1 Pekerja Oh 0.2 Rp 65,000.00 Rp 13,000.00
2 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 15,000.00
OVERHEAD (10%) Rp 1,500.00
SUB TOTAL Rp 16,500.00
II AHS PEKERJAAN TANAH ( GALIAN & URUGAN )
B-01 1 M3 GALIAN TANAH SEDALAM 1 M
1 Pekerja Oh 0.4 Rp 65,000.00 Rp 26,000.00
2 Mandor Oh 0.04 Rp 100,000.00 Rp 4,000.00
TOTAL Rp 30,000.00
OVERHEAD (10%) Rp 3,000.00
SUB TOTAL Rp 33,000.00
B-02 1 M3 GALIAN TANAH KERAS SEDALAM 1 M
1 Pekerja Oh 0.4 Rp 65,000.00 Rp 26,000.00
2 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 28,000.00
OVERHEAD (10%) Rp 2,800.00
SUB TOTAL Rp 30,800.00
B-03 1 M3 GALIAN TANAH SEDALAM 2 M
1 Pekerja Oh 0.53 Rp 65,000.00 Rp 34,450.00
2 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 36,450.00
OVERHEAD (10%) Rp 3,645.00
SUB TOTAL Rp 40,095.00
B-04 1 M3 GALIAN TANAH SEDALAM 3 M
1 Pekerja Oh 0.75 Rp 65,000.00 Rp 48,750.00
2 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 50,750.00
OVERHEAD (10%) Rp 5,075.00
SUB TOTAL Rp 55,825.00
B-05 1 M3 URUGAN TANAH
1 Tanah Urug M3 1.2 Rp 175,000.00 Rp 210,000.00
2 Pekerja Oh 0.3 Rp 65,000.00 Rp 19,500.00
3 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 21,500.00
OVERHEAD (10%) Rp 2,150.00
SUB TOTAL Rp 23,650.00
B-06 1 M3 URUGAN TANAH KEMBALI
1 Pekerja Oh 0.19 Rp 65,000.00 Rp 12,350.00
2 Mandor Oh 0.02 Rp 100,000.00 Rp 2,000.00
TOTAL Rp 14,350.00
OVERHEAD (10%) Rp 1,435.00
SUB TOTAL Rp 15,785.00
B-05 1 M3 URUGAN PASIR
ANALISIS HARGA SATUAN (SNI-2011) 18/12/2019
Project : RUMAH TINGGAL RUDY WONOWIDJAJA
: JL. BUKIT GADING BOULEVARD, KELAPA GADING, JAKARTA
Prepared by : NIZAR ARMAN HARJAKUSUMA - 133.16.002
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
TOTAL Rp 581,815.00
OVERHEAD (10%) Rp 58,181.50
SUB TOTAL Rp 639,996.50
K-BB 1 BUAH JENDELA
1 Door Holder Bh 1 Rp 864,000.00 Rp 864,000.00
2 Kaca Clear - 5mm M2 0.55 Rp 105,000.00 Rp 57,750.00
2 Pekerja Oh 0.065 Rp 65,000.00 Rp 4,225.00
3 Tukang Kayu Oh 0.65 Rp 80,000.00 Rp 52,000.00
4 Kepala Tukang Oh 0.065 Rp 90,000.00 Rp 5,850.00
5 Mandor Oh 0.00325 Rp 100,000.00 Rp 325.00
TOTAL Rp 984,150.00
OVERHEAD (10%) Rp 98,415.00
SUB TOTAL Rp 1,082,565.00
K-02 1 UNIT JENDELA
1 Kusen Jendela Rangka Allumunium M2 1 Rp 639,996.50 Rp 639,996.50
2 Jendela Bh 1 Rp 1,082,565.00 Rp 1,082,565.00
TOTAL Rp 1,722,561.50
OVERHEAD (10%) Rp 172,256.15
SUB TOTAL Rp 1,894,817.65
XIV AHS ATAP
L-01 1 M3 PLAT LANTAI H = 10 CM / BETON BERTULANG (100 KG BESI + BEKISTING)
1 Papan Kayu Terentang M3 0.4 Rp 2,400,000 Rp 960,000
2 Paku 2" - 5" Kg 4 Rp 15,000 Rp 60,000
3 Pelumas Bekisting ( Oli / Minyak ) Ltr 2 Rp 12,000 Rp 24,000
4 Besi U-39 Kg 90 Rp 9,200 Rp 828,000
5 Bendrat / Kawat Beton Kg 3 Rp 15,000 Rp 45,000
6 Balok Kayu Borneo Super M3 0.105 Rp 3,600,000 Rp 378,000
7 Multiplex ( 120 X 240 X 9 MM ) Lbr 3.5 Rp 105,000 Rp 367,500
8 Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m Btg 60 Rp 28,000 Rp 1,680,000
9 Semen Portland Sak 6.4 Rp 62,000 Rp 396,800
10 Pasir Beton M3 0.52 Rp 250,000 Rp 130,000
11 Batu Pecah ( Splitz ) M3 0.78 Rp 178,000 Rp 138,840
12 Pekerja Oh 5.2 Rp 65,000 Rp 338,000
13 Tukang Batu Oh 0.35 Rp 80,000 Rp 28,000
14 Tukang Kayu Oh 3.3 Rp 80,000 Rp 264,000
15 Kepala Tukang Oh 0.365 Rp 90,000 Rp 32,850
16 Mandor Oh 1.06 Rp 100,000 Rp 106,000
TOTAL Rp 5,776,990.00
OVERHEAD (10%) Rp 577,699.00
SUB TOTAL Rp 6,354,689.00
H-03 1 BUAH FLOOR DRAIN ATAP
1 Floor Drain Bh 1 Rp 421,000.00 Rp 421,000.00
2 Pekerja Oh 0.01 Rp 65,000.00 Rp 650.00
3 Tukang Batu Oh 0.1 Rp 80,000.00 Rp 8,000.00
4 Kepala Tukang Oh 0.01 Rp 90,000.00 Rp 900.00
5 Mandor Oh 0.005 Rp 100,000.00 Rp 500.00
TOTAL Rp 431,050.00
OVERHEAD (10%) Rp 43,105.00
SUB TOTAL Rp 474,155.00
XV AHS PIPA & POMPA
M-01 1 M' INSTALASI AIR BERSIH
1 Pipa PVC dia. 3/4" M' 1.2 Rp 5,000.00 Rp 6,000.00
2 Perlengkapan Bh 1 Rp 1,500.00 Rp 1,500.00
3 Pekerja Oh 0.054 Rp 65,000.00 Rp 3,510.00
4 Tukang Pipia Oh 0.09 Rp 80,000.00 Rp 7,200.00
5 Kepala Tukang Oh 0.009 Rp 90,000.00 Rp 810.00
6 Mandor Oh 0.0027 Rp 100,000.00 Rp 270.00
TOTAL Rp 19,290.00
OVERHEAD (10%) Rp 1,929.00
SUB TOTAL Rp 21,219.00
M-02 1 M' INSTALASI AIR KOTOR
1 Pipa PVC dia. 4" M' 1.2 Rp 17,000.00 Rp 20,400.00
2 Perlengkapan Bh 1 Rp 5,100.00 Rp 5,100.00
ANALISIS HARGA SATUAN (SNI-2011) 18/12/2019
Project : RUMAH TINGGAL RUDY WONOWIDJAJA
: JL. BUKIT GADING BOULEVARD, KELAPA GADING, JAKARTA
Prepared by : NIZAR ARMAN HARJAKUSUMA - 133.16.002
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
HARGA (Rp)
NO URAIAN PEKERJAAN SAT. VOLUME
SATUAN JUMLAH
XI AHS PENGECATAN
J-01 PENGECATAN TEMBOK EXTERIOR SETARA VINILEX 1M2 Rp 93,030
J-02 PENGECATAN PLAFOND SETARA VINILEX 1M2 Rp 92,131
Lantai : Keramik tile 300 x 300 / HT 600 x 600mm Niro granite / roman
Dinding : Keramik tile 300 x 300 / HT 600 x 600mm Niro granite / roman
Plafond : Gypsum board dry/wet type 12 mm Jayaboard
SANITARY EX
Security Toilet A 01 A 02 B 01 + B 02
CERAMIC TILE
SIZE 300 x 300
A 01 THICKNESS 8 mm ROMAN FLOOR
FINISH MATT
COLOUR
CERAMIC TILE
SIZE 300 x 600
A 02 THICKNESS 8 mm ROMAN WALL
FINISH MATT
COLOUR
CONCRETE EXOSED
SIZE -
B 01 THICKNESS - LOCAL DRYMIX SERVICE CEILING
FINISH SKIMCOAT BY DRYMIX
COLOUR GREY