Anda di halaman 1dari 37

DAFTAR HARGA SATUAN UPAH DAN BAHAN

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

Harga Satuan
No. Jenis Upah dan Bahan Sat. Keterangan
(Rp)

A. Upah
1 Pekerja OH Rp 120,000
2 Tukang OH Rp 149,000
3 Kepala tukang OH Rp 165,000
4 Mandor OH Rp 180,000

B. Bahan / Material
1 Atap genteng metal berwarna (88 x 77 cm) Kpg Rp 32,200
2 Atap genteng bitumen (Onduline 200 x 95 x 0.3 cm) lbr Rp 156,400
3 Atap genteng metal zcl berpasir biasa Kpg Rp 65,500
4 Alluminium composite panel (ACP) T. 3 mm M2 Rp 348,174
5 Batu bata lobang (9x9x18 cm) Bh Rp 610
6 Batu koral beton (split) M3 Rp 475,000
7 Besi dia. 6 mm KS Btg Rp 32,200 2,66 kg/12 m'
8 Besi dia. 8 mm KS Btg Rp 48,400 4,74 kg/12 m'
9 Besi dia. 10 mm KS Btg Rp 75,600 7.40 kg/12 m'
10 Besi dia. 12 mm KS Btg Rp 100,900 10,66 kg/12 m'
11 Besi dia. 16 mm KS Btg Rp 185,600 18,96 kg/12 m'
12 Besi beton polos Kg Rp 18,100
13 Besi hollow 1x40.40.2mm (plafond) M' Rp 4,000
14 Bubungan / nok genteng metal / alumunium Bh Rp 29,200
15 Bubungan (Onduline 90 x 50 x 0.3 cm) Bh Rp 88,800
16 Cat dasar tembok Kg Rp 45,400
17 Cat kayu dan besi (cat minyak mutu B) Kg Rp 58,500
18 Cat meni besi / kayu / flincote Kg Rp 46,400
19 Cat tembok mutu B luar (catylac, vinilex dan sejenis) Kg Rp 36,300
20 Cat tembok mutu B (exterior) Kg Rp 60,500
21 Closet jongkok porselin (biasa) Bh Rp 158,400
22 Engsel jendela 3" Bh Rp 16,100
23 Engsel kuningan 4" Bh Rp 21,100
24 Eternit 100x100 t. 3,5 mm M2 Rp 30,200
25 Ijuk Kg Rp 15,100
26 Kalsiboard 3,5 mm (120x240 cm) Lbr Rp 69,000
27 Gypsum board 9 mm (120x240 cm) Lbr Rp 75,000
28 Cornis Kg Rp 5,000
29 Lakban gypsum Roll Rp 15,000
30 List gypsum sedang M' Rp 10,000
31 Kaca bening 5 mm M2 Rp 114,000
32 Kaca bening 8 mm M2 Rp 342,100
33 Alumunium Profil kusen M' Rp 47,400
34 Alumuniun Profil daun pintu kaca M' Rp 80,700
35 Alumuniun Profil daun jendela kaca M' Rp 60,500
36 Sealant Tube Rp 25,200
37 Skrup fixer Bh Rp 7,000
38 Kait angin jendela Set Rp 16,100
39 Kawat beton Kg Rp 20,000
40 Kayu gelam dia. 6-8 cm Btg Rp 9,000
41 Kayu gelam dia. 10-12 cm Btg Rp 12,000
Harga Satuan
No. Jenis Upah dan Bahan Sat. Keterangan
(Rp)

42 Kayu lis 1/4 cm M' Rp 2,800


43 Kayu kelas II M3 Rp 5,500,000
44 Kayu kelas III M3 Rp 4,800,000
45 Kayu balok kelas IV M3 Rp 1,600,000
46 Kayu papan kelas IV M3 Rp 1,400,000
47 Keramik lantai uk. 20x20 cm (warna) Kotak Rp 80,700
48 Keramik dinding uk. 20x25 cm (warna) Kotak Rp 57,500
49 Keramik lantai uk. 30x30 cm (polos putih) Kotak Rp 65,000
50 Keramik lantai uk. 40x40 cm (polos putih) Kotak Rp 75,000
51 Lantai uk. 60x60 cm (warana) Kotak Rp 234,336
49 Kran air Bh Rp 30,200
50 Kunci slot Bh Rp 20,100
51 Kunci tanam 2 slaag mutu B Bh Rp 160,400
52 Lem kayu Kg Rp 28,200
53 Lisplank GRC uk. 20 cm (kalsiplank) M' Rp 18,100
54 Paku biasa macam-macam uk. 2"-5" Kg Rp 20,100
55 Paku biasa 1/2" - 1" Kg Rp 21,100
56 Paku beton Kotak Rp 40,300
57 Paku seng / asbes Kg Rp 35,300
58 Paku sekrup Kg Rp 37,300
59 Paku sekrup atap bh Rp 1,300
60 Pasir pasang / beton M3 Rp 125,000
61 Pasir urug M3 Rp 111,000
62 Pintu PVC lengkap + pemasangan Bh Rp 353,200
63 Pipa PVC dia. 3/4" M' Rp 8,000
64 Pipa PVC dia. 3" M' Rp 43,300
65 Plafond PVC motif glosy M2 Rp 100,920
66 List Plafond PVC M' Rp 20,184
67 Plamir tembok (kingkong) Kg Rp 7,000
68 Plamir kayu RJ Kg Rp 25,200
69 Plywood 4 mm Lbr Rp 75,600
70 Plywood 12 mm Lbr Rp 180,000
Rangka atap baja ringan utk atap seng, metal, asbes, Rp 290,000
71 M2
alumunium termasuk pemasangan Rp -
70 Roster terawang uk. 12x11x24 cm Bh Rp 8,500
71 Seal tape Bh Rp 5,800
72 Semen @ 50 kg Zak Rp 67,000
73 Semen portland (PC) Kg Rp 1,340
74 Semen putih @ 40 kg Zak Rp 124,100
75 Semen putih Kg Rp 3,100
76 Semen nat (supergrout) Kg Rp 13,600
77 Seng gelombang, lebar 70 cm Kaki Rp 8,000
78 Seng plat 120x240 cm Lbr Rp 359,200
79 Seng datar lebar 55 cm M' Rp 30,200
80 Alumunium Magnesium Rp -
- zingalium (baja ringan) C. 75.75 M' Rp 16,500 19,500
- reng u ts. 32.45 M' Rp 8,000 8,000
- screw Bh Rp 200
- dynabolt Bh Rp 3,200
- valery gutter talang jurai M' Rp 60,500
- Aluminium foil M2 Rp 46,900
81 Tanah timbunan biasa M3 Rp 131,100
82 Wastafel biasa (lengkap aksesoris) Unit Rp 807,300
83 Batu alam (palimanan hitam) M2 Rp 353,200
84 Vernis batu Ltr Rp 81,700
85 Handle jendela Bh Rp 15,100
86 Floor drain Bh Rp 30,200
87 Penguras bak (saringan air) Bh Rp 15,100
Harga Satuan
No. Jenis Upah dan Bahan Sat. Keterangan
(Rp)

88 Instalasi + Titik Lampu + Kabel Ttk Rp 282,500


89 Instalasi + Stop Kontak + Kabel Ttk Rp 292,600
90 Saklar Tunggal Bh Rp 27,200
91 Saklar Ganda Bh Rp 32,200
92 Bola Lampu SL 20 W Bh Rp 50,400
93 MCB 2A Bh Rp 55,500
94 Stop Kontak BH Rp 22,200
95 Stop Kontak AC BH Rp 46,400
96 Kabel Biasa NYM 2 x 1,5 mm M' Rp 6,200
97 Kabel Biasa NYM 2 x 2,5 mm M' Rp 9,500
98 Kabel Biasa NYM 3 x 2,5 mm M' Rp 13,100
ANALISA HARGA SATUAN PEKERJAAN

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

I. Pekerjaan persiapan
1 1 M2 Pembersihan lapangan dan perataan
2 a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Mandor 0.0500 OH 180,000.00 9,000.00
1 M2 pembersihan lapangan dan perataan 21,000.00
Overhead & Profit (10%) 2,100.00
Jumlah 23,100.00
1 1 M1 Pemasangan bouplank
a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala Tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0050 OH 180,000.00 900.00
29,450.00
b. Bahan
kayu kls IV papan 0.0070 M3 1,400,000.00 9,800.00
paku biasa 0.0200 Kg 20,100.00 402.00
kayu gelam dia. 10-12 cm 0.4000 Btg 12,000.00 4,800.00
15,002.00
1 M1 pemasangan bouplank 44,452.00
Overhead & Profit (15%) 6,667.80
Jumlah 51,119.80
II. Pekerjaan pembongkaran dan penahan
1 1 M3 Pembongkaran dinding tembok bata
a. Upah
Pekerja 6.6670 OH 120,000.00 800,040.00
Mandor 0.3330 OH 180,000.00 59,940.00
1 M3 Pembongkaran dinding tembok bata 859,980.00
Overhead & Profit (10%) 85,998.00
Jumlah 945,978.00
2 1 M2 Pembongkaran dinding tembok bata 0.1200 Tebal Jumlah 113,517.36
3 1 M2 Pasang cerucuk gelam
a. Upah
Pekerja 0.3000 OH 120,000.00 36,000.00
Kepala Tukang 0.0300 OH 180,000.00 5,400.00
41,400.00
b. Bahan
gelam dia. 6-8 cm 6.0000 Btg 9,000.00 54,000.00
1 M2 pas. cerucuk gelam dia. 6-8 cm 95,400.00
Overhead & Profit (15%) 14,310.00
Jumlah 109,710.00
III. Pekerjaan tanah dan pasir
1 1 M3 Galian tanah biasa sedalam 1 m
a. Upah
Pekerja 0.7500 OH 120,000.00 90,000.00
Mandor 0.0250 OH 180,000.00 4,500.00
1 M3 galian tanah biasa sedalam 1 m 94,500.00

4
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Overhead & Profit (10%) 9,450.00


Jumlah 103,950.00
2 1 M3 Urugan kembali
Upah
Pekerja 0.2500 OH 120,000.00 30,000.00
Mandor 0.0083 OH 180,000.00 1,494.00
1 M3 urugan kembali 31,494.00
Overhead & Profit (10%) 3,149.40
Jumlah 34,643.40
3 1 M3 Pekerjaan urugan pasir
a. Upah
Pekerja 0.3000 OH 120,000.00 36,000.00
Mandor 0.0100 OH 180,000.00 1,800.00
37,800.00
b. Bahan
pasir urug 1.2000 M3 111,000.00 133,200.00
133,200.00
1 M3 pekerjaan urugan pasir 171,000.00
Overhead & Profit (15%) 25,650.00
Jumlah 196,650.00
4 1 M3 Urugan tanah pilihan
a. Upah
Pekerja 0.2500 OH 120,000.00 30,000.00
Mandor 0.0250 OH 180,000.00 4,500.00
34,500.00
b. Bahan
tanah timbunan biasa 1.2000 M3 131,100.00 157,320.00
157,320.00
1 M3 urugan tanah pilihan 191,820.00
Overhead & Profit (15%) 28,773.00
Jumlah 220,593.00
IV Pekerjaan pondasi
1 1 M3 Pas. pondasi batu bata ad. 1:4
a. Upah
Pekerja 2.0250 OH 120,000.00 243,000.00
Tukang 0.6750 OH 149,000.00 100,575.00
Kepala tukang 0.0680 OH 165,000.00 11,220.00
Mandor 0.1010 OH 180,000.00 18,180.00
372,975.00
b. Bahan
Batu bata lobang (9x9x18 cm) 686.0000 Bh 610.00 418,460.00
semen pc 136.9980 Kg 1,340.00 183,577.32
pasir pasang 0.4800 M3 125,000.00 60,000.00
662,037.32
1 M3 pas. pondasi batu bata ad. 1:4 1,035,012.32
Overhead & Profit (15%) 155,251.85
Jumlah 1,190,264.17
V Pekerjaan beton
1 1 M3 Membuat lantai kerja beton tumbuk, 1 pc : 3 ps : 5 kr
a. Upah
Pekerja 1.2000 OH 120,000.00 144,000.00
Tukang 0.2000 OH 149,000.00 29,800.00
Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0600 OH 180,000.00 10,800.00
187,900.00
b. Bahan
semen portland 230.0000 Kg 1,340.00 308,200.00
pasir beton 0.6379 M3 125,000.00 79,737.50

5
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

koral beton 0.7607 M3 475,000.00 361,332.50


749,270.00
1 M3 membuat beton tumbuk, 1 pc : 3 ps : 5 kr 937,170.00
Overhead & Profit (15%) 140,575.50
Jumlah 1,077,745.50
2 1 M3 Membuat beton ad 1 pc : 2 ps : 3 kr (mutu K175)
a. Upah
Pekerja 1.6500 OH 120,000.00 198,000.00
Tukang 0.2750 OH 149,000.00 40,975.00
Kepala tukang 0.0280 OH 165,000.00 4,620.00
Mandor 0.0830 OH 180,000.00 14,940.00
258,535.00
b. Bahan
semen portland 326.0000 Kg 1,340.00 436,840.00
pasir beton 0.5429 M3 125,000.00 67,862.50
koral beton 0.7622 M3 475,000.00 362,045.00
866,747.50
1 M3 membuat beton ad 1 pc : 2 ps : 3 kr 1,125,282.50
Overhead & Profit (15%) 168,792.38
Jumlah 1,294,074.88
3 1 M3 Membuat pondasi beton bertulang (200 Kg besi+bekisting)
a. Upah
Pekerja 5.3000 OH 120,000.00 636,000.00
Tukang batu 0.2750 OH 149,000.00 40,975.00
Tukang kayu 1.3000 OH 149,000.00 193,700.00
Tukang besi 1.0500 OH 149,000.00 156,450.00
Kepala tukang 0.2620 OH 165,000.00 43,230.00
Mandor 0.2650 OH 180,000.00 47,700.00
1,118,055.00
b. Bahan
kayu papan kelas. IV 0.2000 M3 1,400,000.00 280,000.00
paku biasa 2"-5" 1.5000 Kg 20,100.00 30,150.00
besi beton polos 200.0000 Kg 18,100.00 3,620,000.00
kawat beton 2.2500 Kg 20,000.00 45,000.00
semen portland 336.0000 Kg 1,340.00 450,240.00
pasir beton 0.5400 M3 125,000.00 67,500.00
koral beton 0.8100 M3 475,000.00 384,750.00
4,877,640.00
1 M3 pondasi beton bertulang (120 Kg besi+bekisting) 5,995,695.00
Overhead & Profit (15%) 899,354.25
Jumlah 6,895,049.25
4 1 M3 Membuat sloof beton bertulang (200 Kg besi+bekisting)
a. Upah
Pekerja 5.6500 OH 120,000.00 678,000.00
Tukang batu 0.2750 OH 149,000.00 40,975.00
Tukang kayu 1.5600 OH 149,000.00 232,440.00
Tukang besi 1.4000 OH 149,000.00 208,600.00
Kepala tukang 0.3230 OH 165,000.00 53,295.00
Mandor 0.2830 OH 180,000.00 50,940.00
1,264,250.00
b. Bahan
kayu papan kelas. IV 0.2700 M3 1,400,000.00 378,000.00
paku biasa 2"-5" 2.0000 Kg 20,100.00 40,200.00
besi beton polos 200.0000 Kg 18,100.00 3,620,000.00
kawat beton 3.0000 Kg 20,000.00 60,000.00
semen portland 336.0000 Kg 1,340.00 450,240.00
pasir beton 0.5400 M3 125,000.00 67,500.00
koral beton 0.8100 M3 475,000.00 384,750.00

6
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

5,000,690.00
1 M3 sloof beton bertulang (120 Kg besi+bekisting) 6,264,940.00
Overhead & Profit (15%) 939,741.00
Jumlah 7,204,681.00
5 1 M3 Membuat kolom beton praktis bertulang (100 Kg besi+bekisting)
a. Upah
Pekerja 3.9000 OH 120,000.00 468,000.00
Tukang batu 0.3500 OH 149,000.00 52,150.00
Tukang kayu 1.0400 OH 149,000.00 154,960.00
Tukang besi 1.0500 OH 149,000.00 156,450.00
Kepala tukang 0.2450 OH 165,000.00 40,425.00
Mandor 0.1650 OH 180,000.00 29,700.00
901,685.00
b. Bahan
kayu papan kelas. IV 0.2000 M3 1,400,000.00 280,000.00
besi beton polos 100.0000 Kg 18,100.00 1,810,000.00
kawat beton 2.2250 Kg 20,000.00 44,500.00
semen portland 232.0000 Kg 1,340.00 310,880.00
pasir beton 0.5200 M3 125,000.00 65,000.00
koral beton 0.7800 M3 475,000.00 370,500.00
2,880,880.00
1 M3 kolom beton praktis bertulang (100 Kg besi+bekisting) 3,782,565.00
Overhead & Profit (15%) 567,384.75
Jumlah 4,349,949.75
6 1 M3 Membuat kolom beton bertulang (200 Kg besi+bekisting)
a. Upah
Pekerja 5.3000 OH 120,000.00 636,000.00
Tukang batu 0.2750 OH 149,000.00 40,975.00
Tukang kayu 1.3000 OH 149,000.00 193,700.00
Tukang besi 1.0500 OH 149,000.00 156,450.00
Kepala tukang 0.2650 OH 165,000.00 43,725.00
Mandor 0.2650 OH 180,000.00 47,700.00
1,118,550.00
b. Bahan
kayu papan kelas. IV 0.3200 M3 1,400,000.00 448,000.00
paku biasa 2"-5" 3.2000 Kg 20,100.00 64,320.00
besi beton polos 200.0000 Kg 18,100.00 3,620,000.00
kawat beton 2.2500 Kg 20,000.00 45,000.00
semen portland 336.0000 Kg 1,340.00 450,240.00
pasir beton 0.5400 M3 125,000.00 67,500.00
koral beton 0.8100 M3 475,000.00 384,750.00
kayu balok kls. IV 0.1200 M3 1,600,000.00 192,000.00
kayu gelam dia.6-8 cm 32.0000 Btg 9,000.00 288,000.00
5,559,810.00
1 M3 kolom beton bertulang (120 Kg besi+bekisting) 6,678,360.00
Overhead & Profit (15%) 1,001,754.00
Jumlah 7,680,114.00
7 1 M3 Membuat balok beton bertulang (200 Kg besi+bekisting)
a. Upah
Pekerja 6.3500 OH 120,000.00 762,000.00
Tukang batu 0.2750 OH 149,000.00 40,975.00
Tukang kayu 1.6500 OH 149,000.00 245,850.00
Tukang besi 1.4000 OH 149,000.00 208,600.00
Kepala tukang 0.3330 OH 165,000.00 54,945.00
Mandor 0.3180 OH 180,000.00 57,240.00
1,369,610.00
b. Bahan
kayu papan kelas. IV 0.3200 M3 1,400,000.00 448,000.00

7
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

paku biasa 2"-5" 3.2000 Kg 20,100.00 64,320.00


besi beton polos 200.0000 Kg 18,100.00 3,620,000.00
kawat beton 3.0000 Kg 20,000.00 60,000.00
semen portland 336.0000 Kg 1,340.00 450,240.00
pasir beton 0.5400 M3 125,000.00 67,500.00
koral beton 0.8100 M3 475,000.00 384,750.00
kayu balok kls. IV 0.1400 M3 1,600,000.00 224,000.00
kayu gelam dia.6-8 cm 16.0000 Btg 9,000.00 144,000.00
5,462,810.00
1 M3 membuat balok beton bertulang (120 Kg besi+bekisting) 6,832,420.00
Overhead & Profit (15%) 1,024,863.00
Jumlah 7,857,283.00
8 1 M3 Membuat ring balok beton bertulang (100 Kg besi+bekisting)
a. Upah
Pekerja 3.9000 OH 120,000.00 468,000.00
Tukang batu 0.3500 OH 149,000.00 52,150.00
Tukang kayu 1.0400 OH 149,000.00 154,960.00
Tukang besi 1.0500 OH 149,000.00 156,450.00
Kepala tukang 0.2450 OH 165,000.00 40,425.00
Mandor 0.1650 OH 180,000.00 29,700.00
901,685.00
b. Bahan
kayu papan kelas. IV 0.3200 M3 1,400,000.00 448,000.00
paku biasa 2"-5" 3.2000 Kg 20,100.00 64,320.00
besi beton polos 100.0000 Kg 18,100.00 1,810,000.00
kawat beton 2.2500 Kg 20,000.00 45,000.00
semen portland 232.0000 Kg 1,340.00 310,880.00
pasir beton 0.5200 M3 125,000.00 65,000.00
koral beton 0.7800 M3 475,000.00 370,500.00
3,113,700.00
1 M3 membuat ring balok beton bertulang (100 Kg besi+bekisting) 4,015,385.00
Overhead & Profit (15%) 602,307.75
Jumlah 4,617,692.75
VI. Pekerjaan dinding
1 1 M2 Pas. dinding batu bata lobang t. 1/2 bata ad. 1 : 4
a. Upah
Pekerja 0.3000 OH 120,000.00 36,000.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0150 OH 180,000.00 2,700.00
55,250.00
b. Bahan
batu bata 9x9x18 cm 62.0000 Bh 610.00 37,820.00
semen pc 6.2680 Kg 1,340.00 8,399.12
pasir pasang 0.0230 M3 125,000.00 2,875.00
49,094.12
1 M2 pas. dinding batu bata lobang t. 1/2 bata ad. 1 : 4 104,344.12
Overhead & Profit (15%) 15,651.62
Jumlah 119,995.74
2 1 M2 Pas. dinding roster terawang 12x11x24cm
a. Upah
Pekerja 0.3000 OH 120,000.00 36,000.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0150 OH 180,000.00 2,700.00
55,250.00
b. Bahan
roster terawang 12x11x24 cm 45.0000 Bh 8,500.00 382,500.00

8
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

semen pc 11.0000 Kg 1,340.00 14,740.00


pasir pasang 0.0350 M3 125,000.00 4,375.00
401,615.00
1 M2 pas. dinding roster terawang 12x11x24cm 456,865.00
Overhead & Profit (15%) 68,529.75
Jumlah 525,394.75
VII. Pekerjaan plesteran
1 1 M2 Plesteran ad. 1:4 t. 15 mm
a. Upah
Pekerja 0.3000 OH 120,000.00 36,000.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0150 OH 180,000.00 2,700.00
63,525.00
b. Bahan
semen pc 6.2400 Kg 1,340.00 8,361.60
pasir pasang 0.0240 M3 125,000.00 3,000.00
11,361.60
1 M2 plesteran ad. 1:4 t. 15 mm 74,886.60
Overhead & Profit (15%) 11,232.99
Jumlah 86,119.59
VIII. Pekerjaan kayu
1 1 M3 Pembuatan & pasang kusen pintu dan jendela kayu kls. II
a. Upah
Pekerja 6.0000 OH 120,000.00 720,000.00
Tukang 18.0000 OH 149,000.00 2,682,000.00
Kepala tukang 1.8000 OH 165,000.00 297,000.00
Mandor 0.3000 OH 180,000.00 54,000.00
3,753,000.00
b. Bahan
kayu balok kelas II 1.2000 M3 5,500,000.00 6,600,000.00
Paku biasa uk. 2"-5" 1.2500 Kg 20,100.00 25,125.00
Lem kayu 1.0000 Kg 28,200.00 28,200.00
6,653,325.00
1 M3 Pembuatan & pasang kusen pintu dan jendela kayu kls. II 10,406,325.00
Overhead & Profit (15%) 1,560,948.75
Jumlah 11,967,273.75
2 1 M2 Pembutan & pasang pintu panil kayu kls. II
a. Upah
Pekerja 1.0000 OH 120,000.00 120,000.00
Tukang 3.0000 OH 149,000.00 447,000.00
Kepala tukang 0.3000 OH 165,000.00 49,500.00
Mandor 0.0500 OH 180,000.00 9,000.00
625,500.00
b. Bahan
kayu papan kelas II 0.0400 M3 5,500,000.00 220,000.00
Lem kayu 0.5000 Kg 28,200.00 14,100.00
234,100.00
1 M2 Pembutan & pasang pintu panil kayu kls. II 859,600.00
Overhead & Profit (15%) 128,940.00
Jumlah 988,540.00
3 1 M2 Pembuatan & pasang pintu dan jendela kaca kayu kls. II
a. Upah
Pekerja 0.8000 OH 120,000.00 96,000.00
Tukang 2.4000 OH 149,000.00 357,600.00
Kepala tukang 0.2400 OH 165,000.00 39,600.00
Mandor 0.0400 OH 180,000.00 7,200.00
500,400.00

9
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

b. Bahan
kayu papan kelas II 0.0240 M3 5,500,000.00 132,000.00
Lem kayu 0.3000 Kg 28,200.00 8,460.00
kaca tebal 5 mm 1.0000 M2 114,000.00 114,000.00
254,460.00
1 M2 Pembuatan & pasang pintu dan jendela kaca kayu kls. II 754,860.00
Overhead & Profit (15%) 113,229.00
Jumlah 868,089.00
4 1 M3 Pasang kuda-kuda kayu kelas II
a. Upah
Pekerja 4.0000 OH 120,000.00 480,000.00
Tukang 12.0000 OH 149,000.00 1,788,000.00
Kepala tukang 1.2000 OH 165,000.00 198,000.00
Mandor 0.2000 OH 180,000.00 36,000.00
2,502,000.00
b. Bahan
kayu kelas II 1.1000 M3 5,500,000.00 6,050,000.00
besi besi 15.0000 Kg 18,100.00 271,500.00
paku biasa uk. 2-5" 5.6000 Kg 20,100.00 112,560.00
6,434,060.00
1 M3 pasang kuda-kuda kayu kelas II 8,936,060.00
Overhead & Profit (15%) 1,340,409.00
Jumlah 10,276,469.00
5 1 M1 pasang lisplank uk. 3 x 20 cm kayu kls. II
a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.2000 OH 149,000.00 29,800.00
Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0050 OH 180,000.00 900.00
46,000.00
b. Bahan
kayu kls. II 0.0108 M3 5,500,000.00 59,400.00
paku biasa 2-5" 0.1000 Kg 20,100.00 2,010.00
61,410.00
1 M1 pasang lisplank uk. 3 x 20 cm kayu kls. II 107,410.00
Overhead & Profit (15%) 16,111.50
Jumlah 123,521.50
6 1 M2 Pas. rangka dinding pemisah + plywood rangkap kayu kls. II
a. Upah
Pekerja 0.0280 OH 120,000.00 3,360.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.8600 OH 165,000.00 141,900.00
Mandor 0.5600 OH 180,000.00 100,800.00
268,410.00
b. Bahan
kayu balok kls. II 0.0280 M3 5,500,000.00 154,000.00
plywood t. 4 mm 0.8600 Lbr 75,600.00 65,016.00
lem kayu 0.5600 Kg 28,200.00 15,792.00
paku biasa 2-5" 0.1500 Kg 20,100.00 3,015.00
237,823.00
1 M2 pas. rangka dinding pemisah + plykwood rangkap kayu kls. II 506,233.00
Overhead & Profit (15%) 75,934.95
Jumlah 582,167.95
7 1 M3 Gording, sako, kitau, blandar kayu kelas II
a. Upah
Pekerja 4.0000 OH 120,000.00 480,000.00
Tukang 12.0000 OH 149,000.00 1,788,000.00
Kepala tukang 1.5000 OH 165,000.00 247,500.00

10
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Mandor 0.2500 OH 180,000.00 45,000.00


2,560,500.00
b. Bahan
kayu kelas II 1.1000 M1 5,500,000.00 6,050,000.00
paku 3.0000 Kg 20,100.00 60,300.00
6,110,300.00
1 M3 gording, sako, kitau, blandar kayu kelas II 8,670,800.00
Overhead & Profit (15%) 1,300,620.00
Jumlah 9,971,420.00
8 1 M2 Lantai papan kayu kelas II
a. Upah
Pekerja 0.2000 OH 120,000.00 24,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.5000 OH 165,000.00 82,500.00
Mandor 0.0100 OH 180,000.00 1,800.00
115,750.00
b. Bahan
kayu papan kelas II 0.0300 M3 5,500,000.00 165,000.00
paku 0.2000 Kg 20,100.00 4,020.00
169,020.00
1 M2 lantai papan kayu kelas II 284,770.00
Overhead & Profit (15%) 42,715.50
Jumlah 327,485.50
IX. Pekerjaan penutup lantai dan dinding
1 1 M2 lantai granite tile ukuran 60cm x 60cm
a. Upah
Pekerja 0.2500 OH 120,000.00 30,000.00
Tukang 0.1250 OH 149,000.00 18,625.00
Kepala tukang 0.0130 OH 165,000.00 2,145.00
Mandor 0.0130 OH 180,000.00 2,340.00
53,110.00
b. Bahan
Granite tile 3.0500 bh 78,112.13 238,242.00
Semen Portland 8.1900 kg 1,340.00 10,974.60
Pasir pasang 0.0450 M3 125,000.00 5,625.00
Semen warna 1.6200 kg 13,600.00 22,032.00
276,873.60
1 M2 lantai granite tile ukuran 60cm x 60cm 329,983.60
Overhead & Profit (15%) 49,497.54
Jumlah 379,481.14
2 1 M2 Pasang lantai keramik putih uk. 40x40 cm
a. Upah
Pekerja 0.2500 OH 120,000.00 30,000.00
Tukang 0.1250 OH 149,000.00 18,625.00
Kepala tukang 0.0130 OH 165,000.00 2,145.00
Mandor 0.0130 OH 180,000.00 2,340.00
53,110.00
b. Bahan
keramik putih uk. 40 x 40 cm 1.0000 M2 75,000.00 75,000.00
semen pc 10.0000 Kg 1,340.00 13,400.00
pasir pasang 0.0450 M3 125,000.00 5,625.00
Semen nat (supergrout) 1.5000 Kg 13,600.00 20,400.00
114,425.00
1 M2 pasang lantai keramik putih uk. 40x40 cm 167,535.00
Overhead & Profit (15%) 25,130.25
Jumlah 192,665.25
3 1 M2 Pasang lantai keramik putih uk. 30x30 cm
a. Upah

11
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Pekerja 0.2500 OH 120,000.00 30,000.00


Tukang 0.1250 OH 149,000.00 18,625.00
Kepala tukang 0.0130 OH 165,000.00 2,145.00
Mandor 0.0130 OH 180,000.00 2,340.00
53,110.00
b. Bahan
keramik putih uk. 30 x 30 cm 1.0000 M2 65,000.00 65,000.00
semen pc 10.0000 Kg 1,340.00 13,400.00
pasir pasang 0.0450 M3 125,000.00 5,625.00
Semen nat (supergrout) 1.5000 Kg 13,600.00 20,400.00
104,425.00
1 M2 pasang lantai keramik putih uk. 30x30 cm 157,535.00
Overhead & Profit (15%) 23,630.25
Jumlah 181,165.25
4 1 M2 Pasang lantai keramik uk. 20x20 cm (km/wc)
a. Upah
Pekerja 0.2700 OH 120,000.00 32,400.00
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0140 OH 165,000.00 2,310.00
Mandor 0.0140 OH 180,000.00 2,520.00
57,345.00
b. Bahan
keramik uk. 20 x 20 cm 1.0000 M2 80,700.00 80,700.00
semen pc 10.4000 Kg 1,340.00 13,936.00
pasir pasang 0.0450 M3 125,000.00 5,625.00
Semen nat (supergrout) 1.6200 Kg 13,600.00 22,032.00
122,293.00
1 M2 pasang lantai keramik uk. 20x20 cm (km/wc) 179,638.00
Overhead & Profit (15%) 26,945.70
Jumlah 206,583.70
5 1 M2 Pasang dinding keramik uk. 20x25 cm
b. Upah
Pekerja 0.1875 OH 120,000.00 22,500.00
Tukang 0.3750 OH 149,000.00 55,875.00
Kepala tukang 0.0450 OH 165,000.00 7,425.00
Mandor 0.0188 OH 180,000.00 3,384.00
89,184.00
a. Bahan
keramik uk. 20 x 25 cm 1.0000 M2 57,500.00 57,500.00
semen pc 9.3000 Kg 1,340.00 12,462.00
pasir pasang 0.0180 M3 125,000.00 2,250.00
Semen nat (supergrout) 1.9400 Kg 13,600.00 26,384.00
98,596.00
1 M2 pasang dinding keramik uk. 20x25 cm 187,780.00
Overhead & Profit (15%) 28,167.00
Jumlah 215,947.00
6 1 M1 Pasang plin lantai keramik
a. Upah
Pekerja 0.0900 OH 120,000.00 10,800.00
Tukang 0.0900 OH 149,000.00 13,410.00
Kepala tukang 0.0350 OH 165,000.00 5,775.00
Mandor 0.0050 OH 180,000.00 900.00
30,885.00
b. Bahan
plin keramik putih uk. 10 x 30 cm 0.1000 M2 65,000.00 6,500.00
semen pc 1.1400 Kg 1,340.00 1,527.60
pasir pasang 0.0030 M3 125,000.00 375.00
Semen nat (supergrout) 0.0500 Kg 13,600.00 680.00

12
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

9,082.60
1 M1 pasang plin lantai keramik putih uk. 10 x 30 cm 39,967.60
Overhead & Profit (15%) 5,995.14
Jumlah 45,962.74
7 1 M2 Pasang dinding batu tempel hitam (batu kali) + anti lumut (vernis)
a. Upah
Pekerja 0.7000 OH 120,000.00 84,000.00
Tukang 0.3500 OH 149,000.00 52,150.00
Kepala tukang 0.0350 OH 165,000.00 5,775.00
Mandor 0.0350 OH 180,000.00 6,300.00
148,225.00
b. Bahan
batu tempel hitam 1.1000 M2 353,200.00 388,520.00
anti lumut / vernis / propan 0.1000 Kg 81,700.00 8,170.00
semen pc 11.7500 Kg 1,340.00 15,745.00
pasir pasang 0.0350 M3 125,000.00 4,375.00
416,810.00
1 M2 pasang dinding batu tempel hitam (batu kali) + anti lumut (vernis) 565,035.00
Overhead & Profit (15%) 84,755.25
Jumlah 649,790.25
8 1 M1 Saluran keliling bangunan uk. 20 x 20 cm

Galian tanah 0.2400 M3 34,643.40 8,314.42


Urug pasir 0.0600 M3 196,650.00 11,799.00
Pas. batu bata ad. 1:4 0.0900 M3 1,190,264.17 107,123.78
Plesteran ad. 1:4 0.9000 M2 86,119.59 77,507.63
204,744.82
1 M1 saluran keliling banguanan uk. 20 x 20 cm 204,744.82
X. Pekerjaan penutup atap
1 1 M2 Rangka atap baja ringan zinggalium (untuk atap, asbes, metal, seng)
a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.2500 OH 149,000.00 37,250.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0500 OH 180,000.00 9,000.00
59,900.00
b. Bahan
type C.75.75 2.3200 M1 16,500.00 38,280.000
reng u ts.40/32 5.4000 M1 8,000.00 43,200.000
scruw 38.0000 Bh 200.00 7,600.000
dinabolt 1.6000 Bh 3,200.00 5,120.000
94,200.000
1 M2 rangka atap baja ringan zinggalium (untuk atap, asbes, metal, seng) 154,100.00
Overhead & Profit (15%) 23,115.00
Jumlah 177,215.00
2 1 M2 Pasang atap genteng metal warna (88 cm x 77 cm)
a. Upah
Pekerja 0.2000 OH 120,000.00 24,000.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0010 OH 180,000.00 180.00
40,730.00
b. Bahan
genteng metal 1.6200 Kpg 32,200.00 52,164.00
Paku biasa 1/2" - 1" 0.2000 Kg 21,100.00 4,220.00
56,384.00
1 M2 pasang atap genteng metal warna (88 cm x 77 cm) 97,114.00
Overhead & Profit (15%) 14,567.10

13
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Jumlah 111,681.10
3 1 M2 Pasang atap genteng metal berpasir
a. Upah
Pekerja 0.2000 OH 120,000.00 24,000.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0010 OH 180,000.00 180.00
40,730.00
b. Bahan
Atap genteng metal zcl berpasir biasa 1.6200 Kpg 65,500.00 106,110.00
Paku biasa 1/2" - 1" 0.2000 Kg 21,100.00 4,220.00
110,330.00
1 M2 Pasang atap genteng metal berpasir 151,060.00
Overhead & Profit (15%) 22,659.00
Jumlah 173,719.00
4 1 M1 Pasang nok genteng metal
a. Upah
Pekerja 0.2500 OH 120,000.00 30,000.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0130 OH 180,000.00 2,340.00
57,165.00
b. Bahan
nok genteng metal 1.1000 Bh 29,200.00 32,120.00
paku biasa 1/2"-1" 0.0500 Kg 21,100.00 1,055.00
33,175.00
1 M1 pasang nok genteng metal 90,340.00
Overhead & Profit (15%) 13,551.00
Jumlah 103,891.00
5 1 M2 Pasang atap seng gelombang
a. Upah
Pekerja 0.1200 OH 120,000.00 14,400.00
Tukang 0.0600 OH 149,000.00 8,940.00
Kepala tukang 0.0060 OH 165,000.00 990.00
Mandor 0.0060 OH 180,000.00 1,080.00
25,410.00
b. Bahan
Seng gelombang, lebar 70 cm 4.6870 Kaki 8,000.00 37,496.00
paku seng 0.0200 Kg 35,300.00 706.00
38,202.00
1 M2 pasang atap seng gelombang 63,612.00
Overhead & Profit (15%) 9,541.80
Jumlah 73,153.80
6 1 M1 Pasang atap nok seng
a. Upah
Pekerja 0.1500 OH 120,000.00 18,000.00
Tukang 0.0700 OH 149,000.00 10,430.00
Kepala tukang 0.0070 OH 165,000.00 1,155.00
Mandor 0.0060 OH 180,000.00 1,080.00
30,665.00
b. Bahan
seng datar 55 cm 1.0100 M1 30,200.00 30,502.00
paku seng 0.0400 Kg 35,300.00 1,412.00
31,914.00
1 M1 pasang atap nok seng 62,579.00
Overhead & Profit (15%) 9,386.85
Jumlah 71,965.85
7 1 M2 Pasang atap genteng bitumen bergelombang (Onduline 200 x 95 x 0.3 cm)

14
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0050 OH 180,000.00 900.00
21,175.00
b. Bahan
Genteng Bitumen 0.7520 lbr 156,400.00 117,612.80
Paku Skrup 10.5230 bh 1,300.00 13,679.90
131,292.70
1 M2 Pasang atap genteng bitumen bergelombang (Onduline 200 x 95 x 0.3 cm) 152,467.70
Overhead & Profit (15%) 22,870.16
Jumlah 175,337.86
8 1 M1 Pasang bubungan genteng bitumen (Onduline 90 x 50 x 0.3 cm)
a. Upah
Pekerja 0.0840 OH 120,000.00 10,080.00
Tukang 0.1250 OH 149,000.00 18,625.00
Kepala tukang 0.0130 OH 165,000.00 2,145.00
Mandor 0.0040 OH 180,000.00 720.00
31,570.00
b. Bahan
genteng bubungan bitumen 1.2500 bh 88,800.00 111,000.00
paku skrup 10.0000 bh 1,300.00 13,000.00
124,000.00
1 M1 Pasang bubungan genteng bitumen (Onduline 90 x 50 x 0.3 cm) 155,570.00
Overhead & Profit (15%) 23,335.50
Jumlah 178,905.50
9 1 M1 Pasang lisplank GRC (kalsiplank)
a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.2000 OH 149,000.00 29,800.00
Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0050 OH 180,000.00 900.00
46,000.00
b. Bahan
Lisplank GRC UK. 20 cm (kalsiplank) 1.0500 M1 18,100.00 19,005.00
paku biasa 2-5" 0.1000 Kg 20,100.00 2,010.00
21,015.00
1 M1 Pasang lisplank GRC (kalsiplank) 67,015.00
Overhead & Profit (15%) 10,052.25
Jumlah 77,067.25
10 1 M1 Pemasangan Alumunium foil
a. Upah
Pekerja 0.1500 OH 120,000.00 18,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0080 OH 180,000.00 1,440.00
27,715.00
b. Bahan
Alumunium foil 1.0500 M2 10,000.00 10,500.00
10,500.00
1 M1 Pemasangan Aluminium foil 38,215.00
Overhead & Profit (15%) 5,732.25
Jumlah 43,947.25
XI. Pekerjaan langit-langit / plafond
1 1 M2 Pasang rangka langit-langit / plafond (1 m x 1 m) kayu kls. III
a. Upah
Pekerja 0.1500 OH 120,000.00 18,000.00

15
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Tukang 0.3000 OH 149,000.00 44,700.00


Kepala tukang 0.0300 OH 165,000.00 4,950.00
Mandor 0.0750 OH 180,000.00 13,500.00
81,150.00
b. Bahan
kayu kls. III 0.0154 M3 4,800,000.00 73,920.00
paku biasa 2-5" 0.2000 Kg 12,000.00 2,400.00
76,320.00
1 M2 pasang rangka plafon (1 m x 1 m) kayu kls. III 157,470.00
Overhead & Profit (15%) 23,620.50
Jumlah 181,090.50
2 1 M2 Rangka besi hollow uk. 1x40.40.2mm, modul 60x60cm, plafon
a. Upah
Pekerja 0.1500 OH 120,000.00 18,000.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0350 OH 165,000.00 5,775.00
Mandor 0.0180 OH 180,000.00 3,240.00
49,365.00
b. Bahan
Rangka metal hollow 40.20.2 mm 4.000 M1 4,000.00 16,000.00
Assesoris (perkuatan, las dll) x 100% rangka 1.000 Ls 4,000.00 4,000.00
20,000.00
1 M2 Rangka besi hollow 1x40.40.2mm, modul 60x60cm, plafon 69,365.00
Overhead & Profit (15%) 10,404.75
Jumlah 79,769.75
3 1 M2 Langit-langit asbes/eternit (1 x 1 m), tebal 3,4 mm
a. Upah
Pekerja 0.0300 OH 120,000.00 3,600.00
Tukang 0.0700 OH 149,000.00 10,430.00
Kepala tukang 0.0070 OH 165,000.00 1,155.00
Mandor 0.0040 OH 180,000.00 720.00
15,905.00
b. Bahan
Eternit tebal 3,4 mm 1.1000 Lbr 30,200.00 33,220.000
paku 0.0100 Kg 21,100.00 211.000
33,431.000
1 M2 langit-langit asbes/eternit (1 x 1 m), tebal 3,4 mm 49,336.00
Overhead & Profit (15%) 7,400.40
Jumlah 56,736.40

4 1 M2 Langit-langit eternit + rangka kayu kls. III


1 M2 langit-langit asbes/eternit (1 x 1 m) 1.0000 M2 56,736.40 56,736.40
1 M2 pasang rangka plafon (1 m x 1 m) kayu kls. III 1.0000 M2 181,090.50 181,090.50
Jumlah 237,826.90

5 1 M2 Langit-langit kalsiboard uk. 120 x 240 cm (tebal 3,5 mm)


a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0050 OH 180,000.00 900.00
21,175.00
b. Bahan
Kalsiboard t. 3,5 mm (120x240 cm) 0.3640 Lbr 69,000.00 25,116.000
paku skrup 0.1100 Kg 37,300.00 4,103.000
29,219.000
1 M2 Langit-langit kalsiboard ukuran 120 x 240 cm (tebal 3,5 mm) 50,394.00
Overhead & Profit (15%) 7,559.10

16
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Jumlah 57,953.10

6 1 M2 Langit-langit kalsiboard ukuran 120 x 240 cm (tebal 3,5 mm) + rangka kayu kls. III
1 M2 Langit-langit kalsiboard 1.0000 M2 57,953.10 57,953.10
1 M2 pasang rangka plafon (1 m x 1 m) kayu kls. III 1.0000 M2 181,090.50 181,090.50
Jumlah 239,043.60

7 1 M2 Langit-langit gypsum board uk. 120 x 240 cm (tebal 9 mm)


a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0050 OH 180,000.00 900.00
21,175.00
b. Bahan
Gypsum board uk. 120x240 0.3640 Lbr 75,000.00 27,300.000
Paku skrup 0.1100 Kg 37,300.00 4,103.000
Cornis 0.3000 kg 5,000.00 1,500.000
Lakban gypsum 0.0700 roll 15,000.00 1,050.000
33,953.000
1 M2 Langit-langit gypsum board ukuran 120 x 240 cm (tebal 9 mm) 55,128.00
Overhead & Profit (15%) 8,269.20
Jumlah 63,397.20

8 1 M2 Langit-langit gypsum board uk. 120 x 240 cm (tbl 9 mm) + Rangka besi hollow 1x40.40.2mm
1 M2 Langit-langit gypsum board, 1.0000 M2 63,397.20 63,397.20
1 M2 Rangka besi hollow 1x40.40.2mm, 1.0000 M2 79,769.75 79,769.75
Jumlah 143,166.95
9 1 M2 Pasangan Plafond Pvc
a. Upah
Pekerja 0.1500 OH 120,000.00 18,000.00
Tukang 0.2500 OH 149,000.00 37,250.00
Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0750 OH 180,000.00 13,500.00
72,050.00
b. Bahan
Plafond Pvc Motif 1.0500 M2 100,920.06 105,966.068
screw 18.0000 Bh 200.00 3,600.000
109,566.068
1 M2 Pasangan Plafond Pvc 181,616.07
Overhead & Profit (15%) 27,242.41
Jumlah 208,858.48
10 1 M2 Pasangan List Plafond Pvc
a. Upah
Pekerja 0.1000 OH 120,000.00 12,000.00
Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0050 OH 180,000.00 900.00
21,175.00
b. Bahan
List Pvc 1.0500 M1 20,184.01 21,193.214
screw 6.0000 Bh 200.00 1,200.000
22,393.214
1 M2 Pasangan List Plafond Pvc 43,568.21
Overhead & Profit (15%) 6,535.23
Jumlah 50,103.45
11 1 M1 List langit-langit gypsum profil
a. Upah

17
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Pekerja 0.0500 OH 120,000.00 6,000.00


Tukang 0.0500 OH 149,000.00 7,450.00
Kepala tukang 0.0050 OH 165,000.00 825.00
Mandor 0.0030 OH 180,000.00 540.00
14,815.00
b. Bahan
List gypsum sedang 1.0500 M' 10,000.00 10,500.000
Paku skrup 0.0100 Kg 37,300.00 373.000
Cornis 0.1000 kg 5,000.00 500.000
11,373.000
1 M1 List langit-langit gypsum profil 26,188.00
Overhead & Profit (15%) 3,928.20
Jumlah 30,116.20
12 1 M1 Pasang list plafond kayu 1/4 cm
a. Upah
Pekerja 0.0210 OH 120,000.00 2,520.00
Tukang 0.0210 OH 149,000.00 3,129.00
Kepala tukang 0.0021 OH 165,000.00 346.50
Mandor 0.0010 OH 180,000.00 180.00
6,175.50
b. Bahan
kayu lis 1/4 1.0500 M1 2,800.00 2,940.00
Paku biasa 1/2" - 1" 0.0100 Kg 21,100.00 211.00
3,151.00
1 M1 pasang list plafond kayu 1/4 9,326.50
Overhead & Profit (15%) 1,398.98
Jumlah 10,725.48
XII. Pekerjaan kunci dan kaca
1 1 Bh Pasang kunci tanam mutu B
a. Upah
Pekerja 0.0100 OH 120,000.00 1,200.00
Tukang 0.5000 OH 149,000.00 74,500.00
Kepala tukang 0.0500 OH 165,000.00 8,250.00
Mandor 0.0050 OH 180,000.00 900.00
84,850.00
b. Bahan
kunci tanam mutu B 1.0000 Bh 160,400.00 160,400.00
160,400.00
1 Bh pasang kunci tanam mutu B 245,250.00
Overhead & Profit (15%) 36,787.50
Jumlah 282,037.50
2 1 Bh Pasang engsel pintu
a. Upah
Pekerja 0.0150 OH 120,000.00 1,800.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0008 OH 180,000.00 135.00
26,760.00
b. Bahan
engsel pintu 4" 1.0000 Bh 21,100.00 21,100.00
21,100.00
1 Bh pasang engsel pintu 47,860.00
Overhead & Profit (15%) 7,179.00
Jumlah 55,039.00
3 1 Bh Pasang engsel jendela
a. Upah
Pekerja 0.0100 OH 120,000.00 1,200.00
Tukang 0.1000 OH 149,000.00 14,900.00

18
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Kepala tukang 0.0100 OH 165,000.00 1,650.00


Mandor 0.0005 OH 180,000.00 90.00
17,840.00
b. Bahan
engsel jendela 3" 1.0000 Bh 16,100.00 16,100.00
16,100.00
1 Bh pasang engsel jendela 33,940.00
Overhead & Profit (15%) 5,091.00
Jumlah 39,031.00
4 1 Bh Pasang kunci slot/gerendel
a. Upah
Pekerja 0.0200 OH 120,000.00 2,400.00
Tukang 0.2000 OH 149,000.00 29,800.00
Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0010 OH 180,000.00 180.00
35,680.00
b. Bahan
kunci slot/gerendel 1.0000 Bh 20,100.00 20,100.00
20,100.00
1 Bh pasang kunci slot/gerendel 55,780.00
Overhead & Profit (15%) 8,367.00
Jumlah 64,147.00
5 1 Bh Pasang kait angin jendela
a. Upah
Pekerja 0.0150 OH 120,000.00 1,800.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0080 OH 180,000.00 1,440.00
28,065.00
b. Bahan
kait angin 1.0000 Bh 16,100.00 16,100.00
16,100.00
1 Bh pasang kait angin jendela 44,165.00
Overhead & Profit (15%) 6,624.75
Jumlah 50,789.75
6 1 Bh Pasang handle jendela
a. Upah
Pekerja 0.0150 OH 120,000.00 1,800.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0008 OH 180,000.00 135.00
26,760.00
b. Bahan
handle jendela 1.0000 Bh 15,100.00 15,100.00
15,100.00
1 Bh pasang handle jendela 41,860.00
Overhead & Profit (15%) 6,279.00
Jumlah 48,139.00
7 1 M2 Pasang kaca, tebal 5 mm
a. Upah
Pekerja 0.0150 OH 120,000.00 1,800.00
Tukang 0.1500 OH 149,000.00 22,350.00
Kepala tukang 0.0150 OH 165,000.00 2,475.00
Mandor 0.0008 OH 180,000.00 144.00
26,769.00
b. Bahan
kaca tebal 5 mm 1.1000 M2 114,000.00 125,400.00
125,400.00

19
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

1 M2 pasang kaca, tebal 5 mm 152,169.00


Overhead & Profit (15%) 22,825.35
Jumlah 174,994.35
XIII. Pekerjaan pengecatan
1 1 M2 Pengecatan tembok baru (1 lps plamir, 1 lps cat dasar, 2 lps cat penutup)
a. Upah
Pekerja 0.0200 OH 120,000.00 2,400.00
Tukang 0.0630 OH 149,000.00 9,387.00
Kepala tukang 0.0063 OH 165,000.00 1,039.50
Mandor 0.0030 OH 180,000.00 540.00
13,366.50
b. Bahan
plamir tembok 0.1000 Kg 7,000.00 700.00
cat dasar 0.1000 Kg 45,400.00 4,540.00
cat penutup 2 kali, mutu B anti lumut/jamur 0.2600 Kg 60,500.00 15,730.00
20,970.00
1 M2 pengecatan tembok baru mutu B anti lumut/jamur 34,336.50
Overhead & Profit (15%) 5,150.48
Jumlah 39,486.98
2 1 M2 Pekerjaan pengecatan plafond
a. Upah
Pekerja 0.0280 OH 120,000.00 3,360.00
Tukang 0.0420 OH 149,000.00 6,258.00
Kepala tukang 0.0042 OH 165,000.00 693.00
Mandor 0.0030 OH 180,000.00 540.00
10,851.00
b. Bahan
cat tembok mutu B 0.1800 Kg 36,300.00 6,534.00
6,534.00
1 M2 pekerjaan pengecatan plafond 17,385.00
Overhead & Profit (15%) 2,607.75
Jumlah 19,992.75
3 1 M2 Pengecatan bidang kayu baru (1 lps plamir, 1 lapis cat dasar, 2 lapis cat penutup)
a. Upah
Pekerja 0.0700 OH 120,000.00 8,400.00
Tukang 0.0090 OH 149,000.00 1,341.00
Kepala tukang 0.0060 OH 165,000.00 990.00
Mandor 0.0030 OH 180,000.00 540.00
11,271.00
b. Bahan
cat meni kayu 0.2000 Kg 46,400.00 9,280.00
plamir kayu 0.1500 Kg 25,200.00 3,780.00
cat dasar 0.1700 Kg 45,400.00 7,718.00
Cat kayu dan besi (cat minyak mutu B) 0.2600 Kg 58,500.00 15,210.00
35,988.00
1 M2 pengecatan bidang kayu baru (1 lps plamir, 1 lapis cat dasar, 2 lapis cat penutup) 47,259.00
Overhead & Profit (15%) 7,088.85
Jumlah 54,347.85
4 Pemasangan Alumunium Composite Panel Flat + Rangka
a. Upah
Pekerja 0.6000 OH 120,000.00 72,000.00
Tukang 0.5000 OH 149,000.00 74,500.00
Kepala tukang 0.0650 OH 165,000.00 10,725.00
Mandor 0.0430 OH 180,000.00 7,740.00
164,965.00
b. Bahan
ACP 1.2000 m2 348,174.22 417,809.07
Rangka hollow 1.0000 Ls 100,000.00 100,000.00

20
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Sealant/Lem Alluminium 1.0000 Ls 35,000.00 35,000.00


Aksesoris 1.0000 Ls 25,000.00 25,000.00
Besi siku - Bracket 1.0000 Ls 25,000.00 25,000.00
Alat Bantu 1.0000 Ls 20,000.00 20,000.00
622,809.07
Pemasangan Alumunium Composite Panel Flat + Rangka 787,774.07
Overhead & Profit (15%) 118,166.11
Jumlah 905,940.18
XIV. Pekerjaan sanitasi
1 1 Bh Pasang closet jongkok porselin
a. Upah
Pekerja 1.0000 OH 120,000.00 120,000.00
Tukang 0.3000 OH 149,000.00 44,700.00
Kepala tukang 0.1500 OH 165,000.00 24,750.00
Mandor 0.0500 OH 180,000.00 9,000.00
198,450.00
b. Bahan
closet jongkok porselin 1.0000 Bh 158,400.00 158,400.00
semen portand 6.0000 Kg 1,340.00 8,040.00
pasir pasang 0.0100 M3 125,000.00 1,250.00
batu bata 7.0000 Bh 610.00 4,270.00
171,960.00
1 Bh pasang closet jongkok porselin 370,410.00
Overhead & Profit (15%) 55,561.50
Jumlah 425,971.50
2 1 Bh Pemasangan bak mandi batu bata volume 0,3 M3
a. Upah
Pekerja 4.0000 OH 120,000.00 480,000.00
Tukang 3.0000 OH 149,000.00 447,000.00
Kepala tukang 0.3000 OH 165,000.00 49,500.00
Mandor 0.0300 OH 180,000.00 5,400.00
981,900.00
b. Bahan
batu bata 200.0000 Bh 610.00 122,000.00
semen pc 120.0000 Kg 1,340.00 160,800.00
pasir pasang 0.3000 M3 125,000.00 37,500.00
320,300.00
1 Bh pemasangan bak mandi batu bata volume 0,3 M3 1,302,200.00
Overhead & Profit (15%) 195,330.00
Jumlah 1,497,530.00
3 1 Bh Floor drain & 1 Bh penguras bak air
a. Upah
Pekerja 0.0100 OH 120,000.00 1,200.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0050 OH 180,000.00 900.00
18,650.00
b. Bahan
Floor drain 1.0000 Bh 30,200.00 30,200.00
Penguras bak (saringan air) 1.0000 Bh 15,100.00 15,100.00
45,300.00
1 Bh Kran dia. 1/2" atau 3/4" 63,950.00
Overhead & Profit (15%) 9,592.50
Jumlah 73,542.50
4 1 M1 Pemasangan pipa air limbah dia. 3"
a. Upah
Pekerja 0.0810 OH 120,000.00 9,720.00
Tukang 0.1350 OH 149,000.00 20,115.00

21
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Kepala tukang 0.0135 OH 165,000.00 2,227.50


Mandor 0.0040 OH 180,000.00 720.00
32,782.50
b. Bahan
pipa paralon dia. 3" 1.2000 M1 43,300.00 51,960.00
perlengkapan (35% harga pipa) 15,155.00 15,155.00
67,115.00
1 M1 pemasangan pipa air limbah dia. 3" 99,897.50
Overhead & Profit (15%) 14,984.63
Jumlah 114,882.13
5 1 M1 Pemasangan pipa pvc aw dia. 3/4"
a. Upah
Pekerja 0.0360 OH 120,000.00 4,320.00
Tukang 0.0600 OH 149,000.00 8,940.00
Kepala tukang 0.0060 OH 165,000.00 990.00
Mandor 0.0020 OH 180,000.00 360.00
14,610.00
b. Bahan
pipa pvc aw. dia. 3/4" 1.2000 M1 8,000.00 9,600.00
perlengkapan (35% harga pipa) 2,800.00 2,800.00
12,400.00
1 M1 pemasangan pipa pvc aw dia. 3/4" 27,010.00
Overhead & Profit (15%) 4,051.50
Jumlah 31,061.50
6 1 Bh Kran air dia. 1/2" atau 3/4"
a. Upah
Pekerja 0.0100 OH 120,000.00 1,200.00
Tukang 0.1000 OH 149,000.00 14,900.00
Kepala tukang 0.0100 OH 165,000.00 1,650.00
Mandor 0.0050 OH 180,000.00 900.00
18,650.00
b. Bahan
Kran air 1.0000 Bh 30,200.00 30,200.00
Seal tape 0.0250 Bh 5,800.00 5,800.00
36,000.00
1 Bh Kran dia. 1/2" atau 3/4" 54,650.00
Overhead & Profit (15%) 8,197.50
Jumlah 62,847.50
7 1 Bh Septictank uk. 1,2 x 2 x 1 m dan resapan
septictank
galian tanah 5.2500 M3 103,950.00 545,737.50
urugan kembali 1.3125 M3 34,643.40 45,469.46
pas. batu bata ad. 1:4 4.2000 M2 119,995.74 503,982.10
beton tumbuk ad. 1:3:5 0.1500 M3 1,077,745.50 161,661.83
plesteran ad. 1:4 6.7500 M2 86,119.59 581,307.23
plat beton bertulang ad. 1:2:3 0.1000 M3 4,349,949.75 434,994.98
pipa hawa 2" 0.5000 Bh 20,000.00 20,000.00
2,293,153.09
peresapan
batu koral beton 0.3750 M3 475,000.00 178,125.00
pasir pasang 0.5000 M3 125,000.00 62,500.00
ijuk 5.0000 ikat 15,100.00 75,500.00
316,125.00
1 Bh septictank uk. 1,2 x 2 x 1 m dan resapan 2,609,278.09
XV. Pekerjaan besi dan alumunium
1 1 M1 Pasang talang miring/jurai seng bjls
a. Upah
Pekerja 0.2000 OH 120,000.00 24,000.00

22
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

Tukang 0.2000 OH 149,000.00 29,800.00


Kepala tukang 0.0200 OH 165,000.00 3,300.00
Mandor 0.0010 OH 180,000.00 180.00
57,280.00
b. Bahan
Seng datar lebar 55 cm 1.0500 M1 30,200.00 31,710.00
paku uk. 1/2 - 1" 0.0150 Kg 21,100.00 316.50
kayu papan kls. III 0.0190 M3 4,800,000.00 91,200.00
123,226.50
1 M1 pasang talang miring seng bjls 180,506.50
Overhead & Profit (15%) 27,075.98
Jumlah 207,582.48
2 1 M2 pasang terali besi + cat besi
a. Upah
Pekerja 1.6700 OH 120,000.00 200,400.00
Tukang 1.6700 OH 149,000.00 248,830.00
Kepala tukang 0.1670 OH 165,000.00 27,555.00
Mandor 0.0830 OH 180,000.00 14,940.00
491,725.00
b. Bahan
Besi dia. 8 mm 11.5000 M' 4,033.33 46,383.33
Besi siku 4.2500 M' 12,100.00 51,425.00
Pengelasan 27.0800 cm 3,025.00 81,917.00
Cat minyak 0.7500 m2 47,259.00 35,444.25
215,169.58
1 M2 pasang terali besi + cat besi 706,894.58
Overhead & Profit (15%) 106,034.19
Jumlah 812,928.77
3 1 M1 kusen pintu alluminium
a. Upah
Pekerja 0.0430 OH 120,000.00 5,160.00
Tukang khusus aluminium 0.0430 OH 149,000.00 6,407.00
Kepala Tukang 0.0043 OH 165,000.00 709.50
Mandor 0.0021 OH 180,000.00 378.00
12,654.50
b. Bahan
Profil alluminium kusen 1.1000 M' 47,400.00 52,140.00
Skrup fixer 2.0000 Bh 7,000.00 14,000.00
Sealeant 0.0600 tube 25,200.00 1,512.00
67,652.00
1 M1 kusen pintu alluminium 80,306.50
Overhead & Profit (15%) 12,045.98
Jumlah 92,352.48
4 1 M2 pintu kaca 8mm rangka aluminium
a. Upah
Pekerja 0.0850 OH 120,000.00 10,200.00
Tukang aluminium/kaca 0.0850 OH 149,000.00 12,665.00
Kepala Tukang 0.0090 OH 165,000.00 1,485.00
Mandor 0.0050 OH 180,000.00 900.00
25,250.00
b. Bahan
Profil aluminium pintu 5.4000 M' 80,700.00 435,780.00
Kaca 8mm 1.2000 M2 342,100.00 410,520.00
Sealant 0.2700 tube 25,200.00 6,804.00
853,104.00
1 M2 pintu kaca 8mm rangka aluminium 878,354.00
Overhead & Profit (15%) 131,753.10
Jumlah 1,010,107.10
5 1 M2 Jendela kaca 5mm rangka aluminium
a. Upah
Pekerja 0.0850 OH 120,000.00 10,200.00
Tukang aluminium/kaca 0.0850 OH 149,000.00 12,665.00
Kepala Tukang 0.0090 OH 165,000.00 1,485.00
Mandor 0.0050 OH 180,000.00 900.00
23
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

25,250.00
b. Bahan
Profil aluminium jendela 4.4000 M' 60,500.00 266,200.00
Kaca 5mm 1.2000 M2 114,000.00 136,800.00
Sealant 0.2700 tube 25,200.00 6,804.00
409,804.00
1 M2 Jendela kaca 6 mm rangka aluminium 435,054.00
Overhead & Profit (15%) 65,258.10
Jumlah 500,312.10
XVI. Pekerjaan Listrik
1 Pemasangan 1 titik nyala Lampu
a. Upah
Pekerja OH 120,000.00 -
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0135 OH 165,000.00 2,227.50
Mandor 0.0050 OH 180,000.00 900.00
23,242.50
b. Bahan
NYM 2 x 2,5 mm2 15.0000 M1 9,500.00 142,500.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 49,875.00
192,375.00
Pemasangan 1 titik nyala Lampu 215,617.50
Overhead & Profit (15%) 32,342.63
Jumlah 247,960.13
2 Pemasangan 1 titik nyala stop kontak
a. Upah
Pekerja OH 120,000.00 -
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0135 OH 165,000.00 2,227.50
Mandor 0.0050 OH 180,000.00 900.00
23,242.50
b. Bahan
NYM 3 x 2,5 mm2 15.0000 M1 13,100.00 196,500.00
Stop Kontak 1.0000 Bh 22,200.00 22,200.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 68,775.00
287,475.00
Pemasangan 1 titik nyala stop kontak 310,717.50
Overhead & Profit (15%) 46,607.63
Jumlah 357,325.13
3 Pemasangan 1 titik nyala stop kontak AC
a. Upah
Pekerja OH 120,000.00 -
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0135 OH 165,000.00 2,227.50
Mandor 0.0050 OH 180,000.00 900.00
23,242.50
b. Bahan
NYM 3 x 2,5 mm2 15.0000 M1 13,100.00 196,500.00
Stop Kontak AC 1.0000 Bh 46,400.00 46,400.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 68,775.00
311,675.00
Pemasangan 1 titik nyala stop kontak AC 334,917.50
Overhead & Profit (15%) 50,237.63
Jumlah 385,155.13
4 Pemasangan 1 titik nyala saklar tunggal
a. Upah
Pekerja OH 120,000.00 -
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0135 OH 165,000.00 2,227.50
Mandor 0.0050 OH 180,000.00 900.00
24
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga

23,242.50
b. Bahan
NYM 2 x 2,5 mm2 15.0000 M1 13,100.00 196,500.00
Saklar tunggal 1.0000 Bh 27,200.00 27,200.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 68,775.00
292,475.00
Pemasangan 1 titik nyala saklar tunggal 315,717.50
Overhead & Profit (15%) 47,357.63
Jumlah 363,075.13
5 Pemasangan 1 titik nyala saklar double
a. Upah
Pekerja OH 120,000.00 -
Tukang 0.1350 OH 149,000.00 20,115.00
Kepala tukang 0.0135 OH 165,000.00 2,227.50
Mandor 0.0050 OH 180,000.00 900.00
23,242.50
b. Bahan
NYM 2 x 2,5 mm2 15.0000 M1 13,100.00 196,500.00
Saklar dauble 1.0000 Bh 32,200.00 32,200.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 68,775.00
297,475.00
Pemasangan 1 titik nyala saklar double 320,717.50
Overhead & Profit (15%) 48,107.63
Jumlah 368,825.13

25
DAFTAR HARGA SATUAN PEKERJAAN

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

No. Jenis pekerjaan Jumlah Harga (Rp)

I. Pekerjaan persiapan
1 1 M2 Pembersihan lapangan dan perataan 23,100.00
2 1 M1 Pemasangan bouplank 51,119.80
II. Pekerjaan pembongkaran dan penahan
1 1 M3 Pembongkaran dinding tembok bata 945,978.00
2 1 M2 Pembongkaran dinding tembok bata 113,517.36
3 1 M2 Pasang cerucuk gelam 109,710.00
III. Pekerjaan tanah dan pasir
1 1 M3 Galian tanah biasa sedalam 1 m 103,950.00
2 1 M3 Urugan kembali 34,643.40
3 1 M3 Pekerjaan urugan pasir 196,650.00
4 1 M3 Urugan tanah pilihan 220,593.00
IV. Pekerjaan pondasi
1 1 M3 Pas. pondasi batu bata ad. 1:4 1,190,264.17
V. Pekerjaan beton
1 1 M3 Membuat lantai kerja beton tumbuk, 1 pc : 3 ps : 5 kr 1,077,745.50
2 1 M3 Membuat beton ad 1 pc : 2 ps : 3 kr (mutu K175) 1,294,074.88
3 1 M3 Membuat pondasi beton bertulang (200 Kg besi+bekisting) 6,895,049.25
4 1 M3 Membuat sloof beton bertulang (200 Kg besi+bekisting) 7,204,681.00
5 1 M3 Membuat kolom beton praktis bertulang (100 Kg besi+bekisting) 4,349,949.75
6 1 M3 Membuat kolom beton bertulang (200 Kg besi+bekisting) 7,680,114.00
7 1 M3 Membuat balok beton bertulang (200 Kg besi+bekisting) 7,857,283.00
8 1 M3 Membuat ring balok beton bertulang (100 Kg besi+bekisting) 4,617,692.75
VI. Pekerjaan dinding
1 1 M2 Pas. dinding batu bata lobang t. 1/2 bata ad. 1 : 4 119,995.74
2 1 M2 Pas. dinding roster terawang 12x11x24cm 525,394.75
VII. Pekerjaan plesteran
1 1 M2 Plesteran ad. 1:4 t. 15 mm 86,119.59
VIII. Pekerjaan kayu
1 1 M3 Pembuatan & pasang kusen pintu dan jendela kayu kls. II 11,967,273.75
2 1 M2 Pembutan & pasang pintu panil kayu kls. II 988,540.00
3 1 M2 Pembuatan & pasang pintu dan jendela kaca kayu kls. II 868,089.00
4 1 M3 Pasang kuda-kuda kayu kelas II 10,276,469.00
5 1 M1 pasang lisplank uk. 3 x 20 cm kayu kls. II 123,521.50
6 1 M2 Pas. rangka dinding pemisah + plywood rangkap kayu kls. II 582,167.95
7 1 M3 Gording, sako, kitau, blandar kayu kelas II 9,971,420.00
8 1 M2 Lantai papan kayu kelas II 327,485.50
IX. Pekerjaan penutup lantai dan dinding
1 1 M2 lantai granite tile ukuran 60cm x 60cm 379,481.14
2 1 M2 Pasang lantai keramik putih uk. 40x40 cm 192,665.25
3 1 M2 Pasang lantai keramik putih uk. 30x30 cm 181,165.25
4 1 M2 Pasang lantai keramik uk. 20x20 cm (km/wc) 206,583.70
5 1 M2 Pasang dinding keramik uk. 20x25 cm 215,947.00
6 1 M1 Pasang plin lantai keramik 45,962.74
7 1 M2 Pasang dinding batu tempel hitam (batu kali) + anti lumut (vernis) 649,790.25
8 1 M1 Saluran keliling bangunan uk. 20 x 20 cm 204,744.82
X. Pekerjaan penutup atap
1 1 M2 Rangka atap baja ringan zinggalium (untuk atap, asbes, metal, seng) 177,215.00
2 1 M2 Pasang atap genteng metal warna (77 cm x 88 cm) 111,681.10

26
No. Jenis pekerjaan Jumlah Harga (Rp)

3 1 M2 Pasang atap genteng metal berpasir 173,719.00


4 1 M1 Pasang nok genteng metal 103,891.00
5 1 M2 Pasang atap seng gelombang 73,153.80
6 1 M1 Pasang atap nok seng 71,965.85
7 1 M2 Pasang atap genteng bitumen bergelombang (Onduline 200 x 95 x 0.3 cm) 175,337.86
8 1 M1 Pasang bubungan genteng bitumen (Onduline 90 x 50 x 0.3 cm) 178,905.50
9 1 M1 Pasang lisplank GRC (kalsiplank) 77,067.25
10 1 M1 Pemasangan Alumunium foil 43,947.25
XI. Pekerjaan langit-langit
1 1 M2 Pasang rangka langit-langit / plafond (1 m x 1 m) kayu kls. III 181,090.50
2 1 M2 Rangka besi hollow uk. 1x40.40.2mm, modul 60x60cm, plafon 79,769.75
3 1 M2 Langit-langit asbes/eternit (1 x 1 m), tebal 3,4 mm 56,736.40
4 1 M2 Langit-langit eternit + rangka kayu kls. III 237,826.90
5 1 M2 Langit-langit kalsiboard uk. 120 x 240 cm (tebal 3,5 mm) 57,953.10
6 1 M2 Langit-langit kalsiboard uk. 120 x 240 cm (tbl 3,5 mm) + rangka kayu kls. III 239,043.60
7 1 M2 Langit-langit gypsum board uk. 120 x 240 cm (tebal 9 mm) 63,397.20
8 1 M2 Langit-langit gypsum board (tbl 9 mm) + Rangka besi hollow 1x40.40.2mm, 143,166.95
9 1 M2 Pasangan Plafond Pvc 208,858.48
10 1 M2 Pasangan List Plafond Pvc 50,103.45
11 1 M1 List langit-langit gypsum profil 30,116.20
12 1 M1 Pasang list plafond kayu 1/4 cm 10,725.48
XII. Pekerjaan kunci dan kaca
1 1 Bh Pasang kunci tanam mutu B 282,037.50
2 1 Bh Pasang engsel pintu 55,039.00
3 1 Bh Pasang engsel jendela 39,031.00
4 1 Bh Pasang kunci slot/gerendel 64,147.00
5 1 Bh Pasang kait angin jendela 50,789.75
6 1 Bh Pasang handle jendela 48,139.00
7 1 M2 Pasang kaca, tebal 5 mm 174,994.35
XIII. Pekerjaan pengecatan
1 1 M2 Pengecatan tembok baru (1 lps plamir, 1 lps cat dasar, 2 lps cat penutup) 39,486.98
2 1 M2 Pekerjaan pengecatan plafond 19,992.75
3 1 M2 Pengecatan bidang kayu baru (1 lps plamir, 1 lapis cat dasar, 2 lapis cat penutup) 54,347.85
4 Pemasangan Alumunium Composite Panel Flat + Rangka 905,940.18
XIV. Pekerjaan sanitasi
1 1 Bh Pasang closet jongkok porselin 425,971.50
2 1 Bh Pemasangan bak mandi batu bata volume 0,3 M3 1,497,530.00
3 1 Bh Floor drain & 1 Bh penguras bak air 73,542.50
4 1 M1 Pemasangan pipa air limbah dia. 3" 114,882.13
5 1 M1 Pemasangan pipa pvc aw dia. 3/4" 31,061.50
6 1 Bh Kran air dia. 1/2" atau 3/4" 62,847.50
7 1 Bh Septictank uk. 1,2 x 2 x 1 m dan resapan 2,609,278.09
XV. Pekerjaan besi dan alumunium
1 1 M1 Pasang talang miring/jurai seng bjls 207,582.48
2 1 M2 pasang terali besi + cat besi 812,928.77
3 1 M1 kusen pintu alluminium 92,352.48
4 1 M2 pintu kaca 8mm rangka aluminium 1,010,107.10
5 1 M2 Jendela kaca 5mm rangka aluminium 500,312.10
XVI. Pekerjaan Instalasi Listrik
1 Pemasangan 1 titik nyala Lampu 247,960.13
2 Pemasangan 1 titik nyala stop kontak 357,325.13
3 Pemasangan 1 titik nyala stop kontak AC 385,155.13
4 Pemasangan 1 titik nyala saklar tunggal 363,075.13
5 Pemasangan 1 titik nyala saklar double 368,825.13
6 Bola Lampu SL 20 W / Bh 50,400.00
7 MCB 2A / Bh 55,500.00

27
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

NO. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA (RP)
(RP)

1 2 3 4 5 6
A. REHAB. GEDUNG AUDITORIUM
I. PEKERJAAN PERSIAPAN
1 Kesehatan & Keselamatan Kerja (K3) 1.00 Ls 15,000,000.00 15,000,000.00
2 Pembutan Papan Nama Kegiatan 1.00 Bh 250,000.00 250,000.00
3 Biaya Sewa/Pembutan Direksiket & Gudang 1.00 Ls 1,800,000.00 1,800,000.00
4 Pek. Pembersihan Lokasi/Pengukuran 105.10 M1 51,119.80 5,372,690.98
22,422,690.98
II. PEKERJAAN BONGKARAN
1 Pek. Bongkaran Rangka Atap dan Atap lama 415.09 M2 15,400.00 6,392,436.05
2 Pek. Bongkaran Rangka Plafond dan plafond lama 687.40 M2 11,550.00 7,939,470.00
3 Pek. Bongkaran Instalasi listrik lama + Pasang 1.00 Ls 2,500,000.00 2,500,000.00
16,831,906.05
III. PEKERJAAN ATAP
1 Pek. Kerangka atap baja ringan (trust) 455.69 M2 177,215.00 80,754,660.31
2 Pek. Pas Atap Onduline 455.69 M2 175,337.86 79,899,268.80
3 Pek. Bubungan atap onduline 70.24 M1 178,905.50 12,566,322.32
4 Pek. Lisplank GRC uk. 20 cm (kalsiplank) 94.54 M1 77,067.25 7,285,937.82
5 Pek. Waterproofing DAK atap 206.20 M2 95,000.00 19,589,000.00
200,095,189.25
IV. PEKERJAAN PLAFOND
1 Pek. Rangka Plafond besi holow 574.54 M2 79,769.75 45,830,912.17
2 Pek. Pasangan Plafond PVC Motif 574.54 M2 208,858.48 119,997,550.07
3 Pek. Pasangan List Plafond PVC 1,378.90 M1 50,103.45 69,087,440.78
234,915,903.02
V. PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 398.55 M2 39,486.98 15,737,533.89
2 Pek. Pengecatan plafond expose beton dgn cat tembok 84.00 M2 39,486.98 3,316,905.90
3 Pek. Pengecatan Listplank dengan cat minyak 18.91 M2 54,347.85 1,027,609.15
20,082,048.93
VI. PEKERJAAN LAIN - LAIN
1 Biaya Administrasi 1.00 Ls 1,500,000.00 1,500,000.00
2 Biaya Pelaporan dan Dokumentasi 1.00 Ls 1,000,000.00 1,000,000.00
3 Biaya Pembersihan akhir 1.00 Ls 1,500,000.00 1,500,000.00
4,000,000.00
JUMLAH TOTAL 498,347,738.23
BACK UP DATA

PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN


LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
T. ANGGARAN : 2021

Ukuran Keterangan
No Uraian Pekerjaan Luas Satuan
Panjang Lebar Tinggi Banyak Berat/M
Volume (M3, M2, M1)

A. REHAB. GEDUNG AUDITORIUM


PEKERJAAN PERSIAPAN
Kesehatan & Keselamatan Kerja (K3)
Pembutan Papan Nama Kegiatan
Biaya Sewa/Pembutan Direksiket & Gudang
Pek. Pembersihan Lokasi/Pengukuran 52.55 2.00 105.10 M2

PEKERJAAN BONGKARAN
Pek. Bongkaran Rangka Atap dan Atap lama 415.09 M2
t depan dan belakang 0.50 19.05 7.45 2.00 141.89
t samping 0.50 15.04 7.45 2.00 112.05
atas 9.48 17.00 1.00 161.16

Pek. Bongkaran Rangka Plafond dan plafond lama 24.55 28.00 1.00 687.40 M2
Pek. Bongkaran Instalasi listrik lama + Pasang 1.00 LS

PEKERJAAN ATAP
Pek. Kerangka atap baja ringan (trust) 455.69 M2
t depan dan belakang 0.50 14.82 12.50 2.00 185.19
t samping 0.50 21.64 12.50 2.00 270.50

Pek. Pas Atap Onduline 455.69 M2


Pek. Bubungan atap onduline 70.24 M1
16.56 4.00 66.24
4.00 1.00 4.00
Pek. Lisplank GRC uk. 20 cm (kalsiplank) 94.54 M1
21.64 2.00 43.28
25.63 2.00 51.26

Pek. Waterproofing DAK atap 206.20 M2


24.00 2.00 1.00 48.00
24.00 2.50 1.00 60.00
24.55 4.00 1.00 98.20
PEKERJAAN PLAFOND
Pek. Rangka Plafond besi holow 574.54 M2
GEDUNG 20.00 24.00 1.00 480.00
OVRSTEK 94.54 1.00 1.00 94.54
Pek. Pasangan Plafond PVC Motif 574.54 M2
Pek. Pasangan List Plafond PVC 574.54 2.40 1,378.90 M1

PEKERJAAN PENGECATAN
Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 398.55 M2
dinding bwh 50.00 3.50 1.00 175.00
dinding atas 88.00 3.00 1.00 264.00
lisplank beton atas 28.00 1.00 1.00 28.00

PENGURANGAN 68.45 M2
dinding bwh
J4 3.70 2.25 2.00 16.65
PJ1 3.70 2.80 5.00 51.80

Pek. Pengecatan plafond expose beton dgn cat tembok 3.00 28.00 1.00 84.00 M2
Pek. Pengecatan Listplank dengan cat minyak 94.54 0.20 1.00 18.91 M2

PEKERJAAN LAIN - LAIN


Biaya Administrasi
Biaya Pelaporan dan Dokumentasi
Biaya Pembersihan akhir 24.55 28.00 1.00 687.40 M2
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

NO. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA (RP)
(RP)

1 2 3 4 5 6
B. REHAB. GEDUNG ASRAMA ANGGREK
I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi/Pengukuran 97.00 M1 51,119.80 4,958,620.60
4,958,620.60
II. PEKERJAAN BONGKARAN
1 Pek. Bongkaran Rangka Atap dan Atap lama 678.48 M2 15,400.00 10,448,592.00
2 Pek. Bongkaran Rangka Plafond dan plafond lama 665.28 M2 11,550.00 7,683,984.00
3 Pek. Bongkaran Instalasi listrik lama + Pasang 1.00 Ls 2,500,000.00 2,500,000.00
20,632,576.00
III. PEKERJAAN BETON DAN DINDING
1 Pek. Pasangan dinding batu bata ad 1.4 6.00 M2 119,995.74 719,974.43
2 Pek. Beton bertulang ring balok 12/15 cm 0.22 M3 4,617,692.75 997,421.63
1,717,396.06
IV. PEKERJAAN ATAP
1 Pek. Kerangka atap baja ringan (trust) 905.94 M2 177,215.00 160,546,865.96
2 Pek. Pas Atap Onduline 905.94 M2 175,337.86 158,846,277.71
3 Pek. Bubungan atap onduline 36.80 M1 178,905.50 6,583,722.40
4 Pek. Lisplank GRC uk. 20 cm (kalsiplank) 133.28 M1 77,067.25 10,271,523.08
5 Pek. Waterproofing DAK atap 96.00 M2 95,000.00 9,120,000.00
345,368,389.15
V. PEKERJAAN PLAFOND
1 Pek. Rangka Plafond besi holow 779.00 M2 79,769.75 62,140,635.25
2 Pek. Pasangan Plafond PVC Motif 779.00 M2 208,858.48 162,700,754.53
3 Pek. Pasangan List Plafond PVC 1,869.60 M1 50,103.45 93,673,401.97
318,514,791.75
VI. PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 260.20 M2 39,486.98 10,274,352.95
2 Pek. Pengecatan Listplank dengan cat minyak 26.66 M2 54,347.85 1,448,696.29
11,723,049.24
VII. PEKERJAAN FASADE
1 Pas. Alumunium Composite Panel 319.23 M2 905,940.178 289,205,548.00
- Alluminium Composite Panel (Ex.SEVEN PVDF Tebal.3 mm )
2 Pas. Sirip Fasad Alumunium Composite Panel 239.03 M2 905,940.178 216,546,880.84
- Alluminium Composite Panel (Ex.SEVEN PVDF Tebal.3 mm )
3 Pek. Pasangan Huruf stainless Tinggi 60 cm 8.00 Bh 120,000.00 960,000.00
4 Pek. Pasangan Huruf stainless Tinggi 40 cm 46.00 Bh 80,000.00 3,680,000.00
510,392,428.83
VII. PEKERJAAN LAIN - LAIN
1 Biaya Pembersihan akhir 1.00 Ls 1,500,000.00 1,500,000.00
1,500,000.00
JUMLAH TOTAL 1,214,807,251.63
BACK UP DATA

PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN


LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
T. ANGGARAN : 2021

Ukuran Keterangan
No Uraian Pekerjaan Luas Satuan
Panjang Lebar Tinggi Banyak Berat/M
Volume (M3, M2, M1)

REHAB. GEDUNG ASRAMA ANGGREK


PEKERJAAN PERSIAPAN
#REF!
Pek. Pembersihan Lokasi/Pengukuran 161.00 M1
GEDUNG ANGGREK 48.50 2.00 97.00
GEDUNG BLKNG 32.00 2.00 64.00

PEKERJAAN BONGKARAN
Pek. Bongkaran Rangka Atap dan Atap lama 678.48 M2
GEDUNG ANGGREK 12.00 32.60 1.00 391.20
GEDUNG BLKNG 13.30 21.60 1.00 287.28
Pek. Bongkaran Rangka Plafond dan plafond lama 665.28 M2
GEDUNG ANGGREK 12.00 31.50 1.00 378.00
GEDUNG BLKNG 13.30 21.60 1.00 287.28

PEKERJAAN BETON DAN DINDING


Pek. Pasangan dinding batu bata ad 1.4 12.00 0.50 1.00 6.00 M2
Pek. Beton bertulang ring balok 12/15 cm 12.00 0.12 0.15 1.00 0.22 M3

PEKERJAAN ATAP
Pek. Kerangka atap baja ringan (trust) 905.94 M2
GEDUNG ANGGEREK 13.00 37.56 1.00 488.28
TERAS 0.50 6.10 4.60 8.00 112.24
GEDUNG BELAKANG 14.14 21.60 1.00 305.42
Pek. Pas Atap Onduline 905.94 M2
Pek. Bubungan atap onduline 4.60 8.00 36.80 M1
Pek. Lisplank GRC uk. 20 cm (kalsiplank) 133.28 M1
GEDUNG ANGGEREK 13.00 1.00 13.00
TERAS 6.10 8.00 48.80
GEDUNG BELAKANG 14.14 2.00 28.28
21.60 2.00 43.20

Pek. Waterproofing DAK atap 12.00 4.00 2.00 96.00 M2

PEKERJAAN PLAFOND
Pek. Rangka Plafond besi holow 779.00 M2
GEDUNG ANGGEREK 12.00 36.50 1.00 438.00
TERAS 2.50 4.00 1.00 10.00
6.00 4.50 1.00 27.00
GEDUNG BELAKANG 12.00 20.00 1.00 240.00
OVRSTEK 64.00 1.00 1.00 64.00

Pek. Pasangan Plafond PVC Motif 779.00 M2


Pek. Pasangan List Plafond PVC 779.00 2.40 1,869.60 M1

PEKERJAAN PENGECATAN
Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 55.50 8.10 1.00 260.20 M2

PENGURANGAN 189.35 M2
J2 2.70 3.15 6.00 51.03
J2' 2.70 4.10 2.00 22.14
J1' 2.70 2.10 4.00 22.68
J1 0.82 3.00 8.00 19.68
PJ1 UTAMA 3.60 3.50 1.00 12.60
PJ1 UTAMA' 4.10 3.50 1.00 14.35
J4 2.77 2.30 4.00 25.48
J22 1.55 2.30 6.00 21.39

Pek. Pengecatan Listplank dengan cat minyak 133.28 0.20 1.00 26.66 M2

PEKERJAAN FASADE
Pas. Alumunium Composite Panel 319.23 M2
- Alluminium Composite Panel (Ex.SEVEN PVDF Tebal.3 mm )
DEPAN 1 6.60 8.30 1.00 54.78
DEPAN 2 37.95 5.15 1.00 195.44
SAMPING 1 13.40 5.15 1.00 69.01

Pas. Sirip Fasad Alumunium Composite Panel 108.65 2.20 1.00 239.03 M2
- Alluminium Composite Panel (Ex.SEVEN PVDF Tebal.3 mm )

PEKERJAAN LAIN - LAIN


Biaya Pembersihan akhir 12.00 36.50 1.00 438.00 M2
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

NO. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN JUMLAH HARGA (RP)
(RP)

1 2 3 4 5 6
C. REHAB. GEDUNG PELATIHAN
I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi/Pengukuran 104.00 M1 51,119.80 5,316,459.20
5,316,459.20
II. PEKERJAAN BONGKARAN
1 Pek. Bongkaran Rangka Atap dan Atap lama 576.00 M2 15,400.00 8,870,400.00
2 Pek. Bongkaran Rangka Plafond dan plafond lama 628.00 M2 11,550.00 7,253,400.00
3 Pek. Bongkaran Instalasi listrik lama + Pasang 1.00 Ls 2,500,000.00 2,500,000.00
18,623,800.00
III. PEKERJAAN BETON DAN DINDING
1 Pek. Pasangan dinding batu bata ad 1.4 57.60 M2 119,995.74 6,911,754.51
2 Pek. Beton bertulang ring balok 12/15 cm 0.58 M3 4,617,692.75 2,659,791.02
9,571,545.53
IV. PEKERJAAN ATAP
1 Pek. Kerangka atap baja ringan (trust) 845.32 M2 177,215.00 149,803,383.80
2 Pek. Pas Atap Onduline 845.32 M2 175,337.86 148,216,595.59
3 Pek. Bubungan atap onduline 72.00 M1 178,905.50 12,881,196.00
4 Pek. Lisplank GRC uk. 20 cm (kalsiplank) 124.92 M1 77,067.25 9,627,240.87
320,528,416.26
V. PEKERJAAN PLAFOND
1 Pek. Rangka Plafond besi holow 663.44 M2 79,769.75 52,922,762.02
2 Pek. Pasangan Plafond PVC Motif 663.44 M2 208,858.48 138,565,904.22
3 Pek. Pasangan List Plafond PVC 1,592.27 M1 50,103.45 79,777,992.94
271,266,659.18
VI. PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 909.17 M2 39,486.98 35,900,262.50
2 Pek. Pengecatan Listplank dengan cat minyak 24.98 M2 54,347.85 1,357,826.68
37,258,089.18
VII. PEKERJAAN LAIN - LAIN
1 Biaya Pembersihan akhir 1.00 Ls 766,500.00 766,500.00
766,500.00
JUMLAH TOTAL 663,331,469.35
BACK UP DATA

PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN


LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
T. ANGGARAN : 2021

Ukuran Keterangan
No Uraian Pekerjaan Luas Satuan
Panjang Lebar Tinggi Banyak Berat/M
Volume (M3, M2, M1)

REHAB. GEDUNG PELATIHAN


PEKERJAAN PERSIAPAN
#REF! 1.00
Pek. Pembersihan Lokasi/Pengukuran 52.00 2.00 104.00 M2

PEKERJAAN BONGKARAN
Pek. Bongkaran Rangka Atap dan Atap lama 36.00 16.00 1.00 576.00 M2
Pek. Bongkaran Rangka Plafond dan plafond lama 628.00 M2
104.00 0.50 1.00 52.00
16.00 36.00 1.00 576.00
PEKERJAAN BETON DAN DINDING
Pek. Pasangan dinding batu bata ad 1.4 57.60 M2
TUTUP DPN BLKNG 16.00 1.80 2.00 57.60

Pek. Beton bertulang ring balok 12/15 cm 16.00 0.12 0.15 2.00 0.58 M3

PEKERJAAN ATAP
Pek. Kerangka atap baja ringan (trust) 845.32 M2
GEDUNG 0.50 17.80 11.00 2.00 195.80
0.50 57.80 11.00 2.00 635.80
TERAS 0.50 3.43 2.00 4.00 13.72

Pek. Pas Atap Onduline 845.32 M2


Pek. Bubungan atap onduline 72.00 M1
20.00 1.00 20.00
11.00 4.00 44.00
2.00 4.00 8.00
Pek. Lisplank GRC uk. 20 cm (kalsiplank) 124.92 M1
17.80 2.00 35.60
37.80 2.00 75.60
3.43 4.00 13.72

PEKERJAAN PLAFOND
Pek. Rangka Plafond besi holow 663.44 M2
OVRSTEK 124.92 0.70 1.00 87.44
DALAM 16.00 36.00 1.00 576.00
Pek. Pasangan Plafond PVC Motif 663.44 M2
Pek. Pasangan List Plafond PVC
663.44 2.40 1,592.27 M1
PEKERJAAN PENGECATAN
Pek. Pengecatan dinding dgn cat tembok (EXTERIOR) 909.17 M2
104.00 8.00 1.00 832.00
104.00 2.80 1.00 291.20

PENGURANGAN 214.03 M2
PJ1 1.70 2.90 2.00 9.86
P1 0.94 2.16 2.00 4.06
V1 1.38 0.60 5.00 4.14
J2 1.58 1.88 60.00 178.22
J3 2.90 3.06 2.00 17.75

Pek. Pengecatan Listplank dengan cat minyak 124.92 0.20 1.00 24.98 M2

PEKERJAAN LAIN - LAIN


Biaya Pembersihan akhir 16.00 36.00 1.00 576.00 M2
RENCANA ANGGARAN BIAYA
(R.A.B)

SATUAN KERJA : DINAS PU BINA MARGA DAN TATA RUANG PROV. SUMATERA SELATAN
KEGIATAN : PENGAMANAN ASET (PEMBUATAN PAGAR/DRAINASE)
PEKERJAAN : PEMBUATAN PAGAR/DRAINASE KANTOR UPTD PROVINSI SUMATERA SELATAN
LOKASI : EX GUDANG TALANG BURUK PALEMBANG
TAHUN : 2021

HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT. (RP) JUMLAH HARGA (RP)

1 2 3 4 5 6
D. PEKERJAAN PEMBANGUNAN PAGAR
I. PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lokasi 150.00 M2 23,100.00 3,465,000.00
2 Pekerjaan Pengukuran / Pas. bouplank 155.00 M' 51,119.80 7,923,569.00
11,388,569.00
II. PEKERJAAN PAGAR (PANJANG 135,00 M)
1 Pek. Galian tanah pondasi 105.00 M3 103,950.00 10,914,750.00
2 Pek. Urugan kembali 35.00 M3 34,643.40 1,212,519.00
3 Pek. Urugan Pasir bawah pondasi 12.50 M3 196,650.00 2,458,125.00
4 Pek. Cor Lantai kerja pondasi ad. 1.3.5 2.50 M3 1,077,745.50 2,694,363.75
5 Pek. Pondasi bt. bata ad. 1.4 27.00 M3 1,190,264.17 32,137,132.54
6 Pek. Pondasi beton bertulang ad. 1.2.3 6.40 M3 6,895,049.25 44,128,315.20
7 Pek. Beton bertulang sloof 15/25 ad. 1.2.3 5.63 M3 7,204,681.00 40,526,330.63
8 Pek. Beton bertulang kolom pagar 20/20 ad. 1:2:3 3.90 M3 7,680,114.00 29,952,444.60
9 Pek. Beton bertulang ring balok 15/20 ad. 1:2:3 4.50 M3 4,617,692.75 20,779,617.38
10 Pas. Dinding batu bata ad. 1:4 213.13 M2 119,995.74 25,574,091.66
11 Pek. Plesteran dinding ad. 1:4 426.25 M2 86,119.59 36,708,475.24
12 Pek. Pengecatan dinding dengan cat tembok 426.25 M2 39,486.98 16,831,323.09
263,917,488.08
III. PEKERJAAN DRAINASE/SALURAN AIR HUJAN
1 Pek. Galian tanah Saluran 52.50 M3 103,950.00 5,457,375.00
2 Pek. Urugan kembali 17.50 M3 34,643.40 606,259.50
3 Pek. Urugan Pasir bawah Saluran 10.50 M3 196,650.00 2,064,825.00
4 Pek. Pas bt bata saluran ad. 1:4 25.20 M3 1,190,264.17 29,994,657.03
5 Pek. Plesteran dinding saluran ad. 1:4 231.00 M2 86,119.59 19,893,625.29
6 Pas. Pipa Rembes 1" 12.00 BTG 114,882.13 1,378,585.50
59,395,327.32
IV. PEKERJAAN PENGECATAN
1 Pek. Pengecatan pagar dgn cat tembok (EXTERIOR) 253.44 M2 39,486.98 10,007,578.94
2 Pek. Pengecatan Realing Besi pagar dengan cat minyak 78.71 M2 54,347.85 4,277,447.53
14,285,026.48
V. PEKERJAAN LAIN - LAIN
1 Biaya Pembersihan akhir 1.00 Ls 1,800,000.00 1,800,000.00
1,800,000.00
JUMLAH TOTAL 350,786,410.88
BACK UP DATA

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

Ukuran Keterangan
No Uraian Pekerjaan Luas Satuan
Panjang Lebar Tinggi Banyak Berat/M
Volume (M3, M2, M1)

PEKERJAAN PERSIAPAN
Pek. Pembersihan Lokasi 150.00 1.00 1.00 150.00 M2

Pekerjaan Pengukuran / Pas. bouplank 155.00 M1


153.00 1.00 2.00 155.00

PEKERJAAN PAGAR (PANJANG 135,00 M)


Pek. Galian tanah pondasi 105.00 M3
P1 KOLOM 1.00 1.00 1.05 50.00 52.50
P2 BT BATA 150.00 0.50 0.70 1.00 52.50
0.00
Pek. Urugan kembali 35.00 M3
Pek. Urugan Pasir bawah pondasi 12.50 M3
1.00 1.00 0.10 50.00 5.00
150.00 0.50 0.10 1.00 7.50
0.00
Pek. Cor Lantai kerja pondasi ad. 1.3.5 1.00 1.00 0.05 50.00 2.50 M3
Pek. Pondasi bt. bata ad. 1.4 150.00 0.30 0.60 1.00 27.00 M3
Pek. Pondasi beton bertulang ad. 1.2.3 6.40 M3
0.80 0.80 0.20 50.00 6.40
0.00
Pek. Beton bertulang sloof 15/25 ad. 1.2.3 150.00 0.15 0.25 1.00 5.63 M3
Pek. Beton bertulang kolom pagar 20/20 ad. 1:2:3 1.95 0.20 0.20 50.00 3.90 M3

Pek. Beton bertulang ring balok 15/20 ad. 1:2:3 150.00 0.15 0.20 1.00 4.50 M3
Pas. Dinding batu bata ad. 1:4 2.75 1.55 50.00 213.13 M2
Pek. Plesteran dinding ad. 1:4 213.13 2.00 426.25 M2
Pek. Pengecatan dinding dengan cat tembok 426.25 M2

PEKERJAAN DRAINASE/SALURAN AIR HUJAN


Pek. Galian tanah Saluran 150.00 0.70 0.50 1.00 52.50 M3
Pek. Urugan kembali 17.50 M3
Pek. Urugan Pasir bawah Saluran 150.00 0.70 0.10 1.00 10.50 M3
Pek. Pas bt bata saluran ad. 1:4 150.00 1.40 0.12 1.00 25.20 M3
Pek. Plesteran dinding saluran ad. 1:4 150.00 1.54 1.00 231.00 M2
Pas. Pipa Rembes 1" 60.00 0.20 12.00 BTG

PEKERJAAN PENGECATAN
Pek. Pengecatan pagar dgn cat tembok (EXTERIOR) 253.44 M2
DINDING 2.70 0.80 44.00 95.04
KOLOM 1.20 2.50 44.00 132.00
KOLOM PINTU 4.40 3.00 2.00 26.40
Pek. Pengecatan Realing Besi pagar dengan cat minyak 78.71 M2
realing 2.70 1.20 44.00 142.56
pintu 9.90 1.50 1.00 14.85

PEKERJAAN LAIN - LAIN


Biaya Pembersihan akhir 150.00 1.00 1.00 150.00 M2
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : BADAN PELATIHAN KESEHATAN PALEMBANG


KEGIATAN : REHABILITASI SEDANG / BERAT GEDUNG KANTOR BAPELKES PALEMBANG
PEKERJAAN : REHABILITASI KAWASAN GEDUNG BAPELKES PROV. SUMATERA SELATAN
LOKASI : KOMPLEK BAPELKES JALAN LEBONG SIARANG PALEMBANG
TAHUN : 2021

N0. URAIAN PEKERJAAN JUMLAH HARGA (Rp)

A. REHAB. GEDUNG AUDITORIUM Rp. 498,347,738.23

B. REHAB. GEDUNG ASRAMA ANGGREK Rp. 1,214,807,251.63

C. REHAB. GEDUNG PELATIHAN Rp. 663,331,469.35

D. PEKERJAAN PEMBANGUNAN PAGAR Rp. 350,786,410.88

JUMLAH Rp. 2,727,272,870.10


PAJAK PPN 10% Rp. 272,727,287.01
JUMLAH TOTAL Rp. 3,000,000,157.11
DIBULATKAN Rp. 3,000,000,000.00
TERBILANG, " TIGA MILYAR RUPIAH "

Mengetahui, Dihitung Oleh,


PENGELOLA TEKNIS KEGIATAN KONSULTAN PERENCANA
DINAS PERUMAHAN & KAWASAN PEMUKIMAN CV. PLATINUM CONSULTAN
PROVINSI SUMATERA SELATAN

SUKO DJATI, ST
Ir.IMAM SANTOSO Direktur
NIP. 19630923 199903 1 001

Disetujui, Diperiksa,
PEJABAT PEMBUAT KOMITMEN PEJABAT PELAKSANA TEKNIS KEGIATAN
(PPK) (PPTK)

Dra.LESTY NURAINY,Apt.M.Kes EDWIN YULIUS,SKM.M.Si


NIP. 19620703 198903 2002 NIP. 19690723 199303 1003

Anda mungkin juga menyukai