EDISI II 2019
KET.
DAFTAR UPAH PEKERJA
HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 90,000 100,000
10 T u k a n g c a t Hr 120,000 130,000
11 K e p . t k . c a t Hr 130,000 140,000
12 T u k a n g p l i t u r Hr 120,000 130,000
13 T u k a n g j a l a n Hr 90,000 100,000
14 T u k a n g g a l i Hr 90,000 100,000
16 T k . l e i d e n g Hr 130,000 140,000
17 M a s i n i s Hr 175,000 200,000
18 P e m b . M a s i n i s Hr 125,000 150,000
19 P e n j a g a a p i Hr 90,000 100,000
20 P e n j a g a m a l a m Hr 90,000 100,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 210,000 250,000
Bulat Belah m3 280,000 320,000
Pecah 10/15 m3 290,000 340,000
Pecah 5/7 m3 290,000 350,000
Pecah 3/5 m3 320,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 190,000 200,000
Beton 0,5/1 m3 320,000 380,000
Beton 1/2 m3 330,000 390,000
Beton 2/3 m3 340,000 380,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 320,000
3 BATU BATA ex lokal bh 580 625
4 PASIR Urug m3 160,000 220,000
Pasang m3 340,000 370,000
Beton m3 360,000 380,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT
Merk Cibinong 40 kg zak 46,000 47,000
Merk Cibinong 50 kg zak 56,000 58,000
Merk Gresik 40 kg zak 45,000 46,000
Merk Gresik 50 kg zak 56,000 58,000
Merk Holcim 40 kg zak 85,000 90,000
Merk Holcim 50 kg zak 95,000 102,000
Merk Bima 40 kg zak 11,000 15,000
Merk Bima 50 kg zak 52,000 54,000
PC 1,125 1,150
Semen Putih 40 kg zak 75,000 80,000
Semen Putih 50 kg zak 85,000 90,000
Semen warna kg 11,000 15,000
II BAHAN PENUTUP ATAP
1 SIRAP (100 lbr) pak 190,000 210,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm 15,500 17,000
. 100cm X 100 cm X 4 mm 16,000 20,000
. 50 cm X 200 cm X 3 mm 14,200 15,000
. 40 cm X 200 cm X 3 mm 13,800 14,500
III . B A H A N K A Y U
1 JATI Papan m3 28,000,000 29,000,000
Balok/pesagen m3 25,000,000 26,000,000
2 KAMPER Papan m3 8,700,000 8,800,000
Balok/pesagen m3 8,400,000 8,600,000
3 KRUING Papan m3 8,400,000 8,800,000
Balok/pesagen m3 6,500,000 6,800,000
4 MERANTI Papan m3 5,100,000 5,700,000
Balok/pesagen m3 5,000,000 5,400,000
5 LANAN Papan m3 3,290,000 3,300,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 10,500,000 10,650,000
Balok/pesagen m3 9,500,000 9,900,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000
8 KAYU GLUGU
3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
Floor hardener Kg - -
4 MOZAIK PORSELIN
10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 31,000
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 36,500
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 55,000
Pipa PVC DN 40 ( 1½" ) btg 56,000 70,000
Pipa PVC DN 63 ( 2" ) btg 70,000 105,000
Pipa PVC DN 90 ( 3" ) btg 125,000 185,000
Pipa PVC DN 110 ( 4" ) btg 270,000 280,000
Pipa PVC DN 160 ( 6" ) btg 530,000 550,000
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000
Pipa PVC DN 250 ( 10" ) btg - -
Pipa PVC DN 315 ( 12" ) btg - -
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,500
30 X 60 lbr 13,200 14,500
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr - -
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 65,000 75,000
. 120 X 240 X 3 mm lbr 80,000 95,000
. 90 X 210 X 4 mm lbr 65,000 85,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 200,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 61,500
. 120 X 240 X 4 mm lbr 65,000 70,000
. 120 X 240 X 6 mm lbr 75,000 86,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000 160,000
. 120 X 240 X 12 mm lbr 165,000 165,000
. 120 X 240 X 15 mm lbr 190,000 190,000
. 120 X 240 X 18 mm lbr 215,000 -
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,500 4,100
Batu Apung kg 50,000 55,000
Cat dasar kg 40,000 42,500
. Emco kg 62,000 68,000
. Yunior 66 (nippon paint) kg 60,000 71,000
- Koas bh 7,500 15,000
. Deculux kg 63,000 75,000
. Siralax ons 15,000 21,000
. Spiritus ltr 13,000 18,000
. Plitur jadi ltr 65,000 68,000
2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 26,000
Sintex 5 kg 120,000 125,000
Danabride 5 kg 115,000 122,000
Catylac 5 kg 120,000 130,000
Mowilex 2,50 kg 280,000 350,000
Cat weathershiel kg 105,000 105,000
3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 62,000 69,000
Cat kg 40,000 45,000
Thinner A ltr 15,000 20,000
Minyak cat ltr 15,000 20,000
Thinner Super ltr 17,500 35,000
Zincrome kg 17,500 23,750
Residu (teer/aspal) drum 55,000 60,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Fibre glass (tanki air) - -
kapasitas 550 liter. bh 1,000,000 1,100,000
kapasitas 1100 liter. bh 1,600,000 1,700,000
Kuas bh - -
Roll bh - -
Lem Aica Aibon kg 55,000 65,000
Genteng (Mowilex) kg 74,000 74,000
water Profing/Coating kg 50,000 50,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 85,000 95,000
5 mm m2 95,000 105,000
2 ES KABUR 3 mm m2 95,000 110,000
5 mm m2 120,000 130,000
3 RAY BAND 3 mm m2 85,000 95,000
5 mm m2 90,000 105,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 5,000 5,500
2 SKAKELAR
Out bauw . Seri bh 20,000 25,000
Kunci Tanam bh - -
Urinoir bh - -
Bak Dip bh - -
Cairan/Bubuk pembersih kg - -
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 350,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000
. 200 watt bh 750,000 850,000
. 250 watt bh 850,000 950,000
9 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum - -
Aspal SPC 60/70 Ex singapura isi Net 155 kg drum 950,000 1,100,000
Aspal SPC 60/70 Ex singapura isi Net 160 kg drum 950,000 1,100,000
KET
KET
KET
KET
KET
KET
KET
KET
panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m
panj : 4 m
panj : 4 m
KET
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
KET
KET
KET
KET
KET
KET
KET
KET
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016
LS
15 DHAN Menggali dengan excavator (skala besar) tiap 1m³ m3 25,526.05 26,486.35
Mengurug tanah tiap 20 cm di padatkan (Tanah
16 HIT m3 214,775.00 260,425.00
didatangkan) tiap 1 m3
Memadatkan tanah dengan tamper/hand compactor 6
17 DHAN m3 12,724.80 14,315.40
lintasan / tebal 20cm tiap 1 m3
18 DHAN Memadatkan tanah dengan Vibrating Roller tiap 1 m³ m3 4,180.00 4,263.60
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 871,997.50 977,487.50
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 87,780.00 98,840.50
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 113,597.00 127,311.25
40 SNI Membuat Ring Balok Beton Bertulang (10 x 15) cm m2 92,719.00 111,086.25
41 HIT SNI Membuat Ring Balok Beton Bertulang (10 x 15) cm m3 6,181,266.67 7,405,750.00
22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 64,113.50 69,371.50
24 HIT Memasang 1 m' Kosen Alumunium 3" YKK m' 210,893.65 232,414.05
30 SNI Memasang kaca nako dan tralis besi tiap 1 m2 m2 435,187.50 456,923.50
16 A.4.4.1.16 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP m2 427,776.80 462,551.10
17 A.4.4.1.17 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP m2 436,566.90 472,626.55
18 A.4.4.1.18 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP m2 337,107.10 364,396.45
20 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP m2 270,785.90 298,130.80
21 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP m2 275,928.95 303,982.53
26 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 286,371.25 306,219.38
38 HIT SNI Memasang dinding batu tempel palimanan tiap 1m² m2 164,628.75 181,726.88
39 HIT SNI Memasang dinding batu Candi tiap 1m² m2 271,713.75 296,126.88
15 DHAN Memasang List langit-langit PVC profil tiap 1m' m' 46,103.75 47,951.75
21 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II m' 374,412.50 389,922.50
28 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV m2 129,689.34 144,821.60
32 SNI Membuat Jalusi mati Kosen Kayu kamper tiap 1 m2 m2 341,302.50 366,272.50
38 SNI Memasang lisplank (3 x 30) cm Kayu bengkirai tiap 1m' m' 167,860.00 172,287.50
39 SNI Memasang lisplank (3 x 20) cm Kayu bengkirai tiap 1m' m' 123,970.00 127,770.50
41 HIT Memasang lisplank Woodplank 0,9 x 20 tiap 1 m' m' 63,332.50 68,255.00
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 11,783.75 13,046.00
17 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah m2 63,236.25 70,303.75
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,672,154.27 1,826,638.54
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 351,422.50 394,047.50
6 LS Pasang Fuse box sekering 2 group tiap 1 unit Unit 269,500.00 308,000.00
Pasang instalasi stop AC tiap 1 titik (termasuk stop
Titik 255,461.25 288,708.75
kontak)
7 LS Pasang Fuse box sekering 3 group tiap 1 unit Unit 385,000.00 434,500.00
8 Aspal untuk Pelaburan tiap 1 Liter x 4,5 untuk 4,5 m2 Ltr 9,705.03 10,936.75
11 Pembuatan jalan aspal biasa lebar 3 m' tiap 1 m' m' 574,393.38 662,296.14
12 Pembuatan jalan aspal biasa lebar 4 m' tiap 1 m' m' 765,857.84 883,061.52
13 Pembuatan jalan aspal biasa lebar 5 m' tiap 1 m' m' 957,322.30 1,103,826.90
14 Pembuatan jalan aspal biasa lebar 6 m' tiap 1 m' m' 1,148,786.76 1,324,592.28
15 Pembuatan jalan aspal biasa lebar 8 m' tiap 1 m' m' 1,531,715.68 1,766,123.04
C PERALATAN
D Jumlah A + B + C 162,125.00 183,875.00
E Overhead & Profit (contah 10%) 10% 16,212.50 18,387.50
F Harga Satuan Pekerjaan (D+E) 178,337.50 202,262.50
B Bahan
C PERALATAN
D Jumlah A + B + C 12,950.00 14,275.00
E Pekerja 10% 1,295.00 1,427.50
F Harga Satuan Pekerjaan (D+E) 14,245.00 15,702.50
22 Rev SNI 1 m3 Bongkaran Rangka Kuda-kuda/Kusen kayu tiap 1 m3 159,500.00 172,700.00
A Tenaga 145,000.00 157,000.00
L.02 1.000 OH TK kayu 120,000.00 130,000.00 120,000.00 130,000.00
L.04 0.200 OH Mandor 125,000.00 135,000.00 25,000.00 27,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C 145,000.00 157,000.00
E Pasir Beton 10% 14,500.00 15,700.00
F Harga Satuan Pekerjaan (D+E) 159,500.00 172,700.00
22 1 Ls Pembersihan lapangan - -
- Pembersihan lapangan
-
B Bahan
C PERALATAN
D Jumlah A + B + C - -
E PERALATAN 10% - -
F Harga Satuan Pekerjaan (D+E) - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
0.03
33.3
0.06
### ###
#REF! #REF!
0.2
0.2
2
0.08
###
#REF!
1075
0.05
0.5
2.4
0.06
72,666
1211100.78571 1296636.49471
72666.0471429 77798.1896825
0.15
0.4
2.2
0.132
159865.303714 171156.017302
140000 160000
140000 160000
0.06
### ###
0.06
### ###
0.06
### ###
0.06
### ###
0.06
### 8,910.00
0.06
### ###
0.06
### ###
KUANTI HARGA SAT. SUB TOTAL
NO. URAIAN SAT HSP (Rp)
TAS DASAR (Rp) (Rp)
1 2 3 4 5 6 7
6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 871,997.50 977,487.50
A Tenaga 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 548,600.00 620,500.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 340,000.00 370,000.00 115,600.00 125,800.00
C PERALATAN
D Jumlah A + B + C 792,725.00 888,625.00
E Overhead & Profit (contoh 10%) 10% 79,272.50 88,862.50
F Harga Satuan Pekerjaan (D+E) 871,997.50 977,487.50
24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 87,780.00 98,840.50
A Tenaga 25,305.00 27,855.00
L.01 0.180 OH Pekerja 90,000.00 100,000.00 16,200.00 18,000.00
L.02 0.020 OH Tukang batu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Kayu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Besi 120,000.00 130,000.00 2,400.00 2,600.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 54,495.00 62,000.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 175.00 180.00
3.0 Kg Besi Beton Polos 10,000.00 12,000.00 30,000.00 36,000.00
0.45 Kg Kawat Beton 18,000.00 20,000.00 8,100.00 9,000.00
4.0 Kg Portland Semen 1,150.00 1,175.00 4,600.00 4,700.00
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 360,000.00 2,880.00 3,240.00
C PERALATAN
D Jumlah A + B + C 79,800.00 89,855.00
E Overhead & Profit (contoh 10%) 10% 7,980.00 8,985.50
F Harga Satuan Pekerjaan (D+E) 87,780.00 98,840.50
25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 113,597.00 127,311.25
A Tenaga 41,785.00 45,995.00
L.01 0.297 OH Pekerja 90,000.00 100,000.00 26,730.00 29,700.00
L.02 0.033 OH Tukang batu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Kayu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Besi 120,000.00 130,000.00 3,960.00 4,290.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 61,485.00 69,742.50
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 350.00 360.00
3.6 Kg Besi Beton Polos 10,000.00 12,000.00 36,000.00 43,200.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
5.5 Kg Portland Semen 1,150.00 1,175.00 6,325.00 6,462.50
0.009 m3 Pasir Beton 360,000.00 380,000.00 3,240.00 3,420.00
0.015 m3 Kerikil 320,000.00 360,000.00 4,800.00 5,400.00
C PERALATAN
D Jumlah A + B + C 103,270.00 115,737.50
E Overhead & Profit (contoh 10%) 10% 10,327.00 11,573.75
F Harga Satuan Pekerjaan (D+E) 113,597.00 127,311.25
26 A.4.1.1. 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 4,402,788.50 4,907,435.50
A Tenaga 859,185.00 943,705.00
L.01 5.3 OH Pekerja 90,000.00 100,000.00 477,000.00 530,000.00
L.02 0.275 OH Tukang batu 120,000.00 130,000.00 33,000.00 35,750.00
L.02 1.30 OH Tukang Kayu 120,000.00 130,000.00 156,000.00 169,000.00
L.02 1.05 OH Tukang Besi 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.262 OH Kepala Tukang 130,000.00 140,000.00 34,060.00 36,680.00
L.04 0.265 OH Mandor 125,000.00 135,000.00 33,125.00 35,775.00
B Bahan 3,143,350.00 3,517,600.00
0.2 m3 Kayu Klas III 3,290,000.00 3,300,000.00 658,000.00 660,000.00
1.5 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 26,250.00 27,000.00
0.4 Ltr Minyak bekesting 9,000.00 10,000.00 3,600.00 4,000.00
157.5 Kg Besi Beton Polos 10,000.00 12,000.00 1,575,000.00 1,890,000.00
2.25 Kg Kawat Beton 18,000.00 20,000.00 40,500.00 45,000.00
336 Kg Portland Semen 1,150.00 1,175.00 386,400.00 394,800.00
0.54 m3 Pasir Beton 360,000.00 380,000.00 194,400.00 205,200.00
11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 70,339.50 76,312.50
12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 72,319.50 78,468.50
1 1.0000 13 1.114
2 1.0000 14 1.134
3 1.0000 15 1.155
4 1.0000 16 1.176
5 1.0000 17 1.197
6 1.0000 18 1.219
7 1.0000 19 1.241
8 1.0180 20 1.264
9 1.0370 21 1.287
10 1.0550 22 1.310
11 1.0750 23 1.334
12 1.0940 24 1.358
2 1.0000 14 1.080
3 1.0000 15 1.092
4 1.0000 16 1.104
5 1.0000 17 1.116
6 1.0000 18 1.129
7 1.0000 19 1.141
8 1.0110 20 1.154
9 1.0220 21 1.166
10 1.0340 22 1.179
11 1.0450 23 1.192
12 1.0570 24 1.206
1 1.0000 13 1.162
2 1.0000 14 1.191
3 1.0000 15 1.221
4 1.0000 16 1.252
5 1.0000 17 1.284
6 1.0000 18 1.318
7 1.0000 19 1.350
8 1.0250 20 1.384
9 1.0510 21 1.419
10 1.0780 22 1.455
11 1.1050 23 1.492
12 1.1330 24 1.530
22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 64,113.50 69,371.50
A Tenaga 58,285.00 63,065.00
L.02 0.367 OH Tukang Batu 120,000.000 130,000.000 44,040.000 47,710.000
L.03 0.074 OH Kepala Tukang 130,000.000 140,000.000 9,620.000 10,360.000
L.04 0.037 OH Mandor 125,000.000 135,000.000 4,625.000 4,995.000
B Bahan - -
C PERALATAN - -
D Jumlah A + B + C 58,285.00 63,065.00
E Overhead & Profit (contoh 10%) 10% 5,828.50 6,306.50
F Harga Satuan Pekerjaan (D+E) 64,113.50 69,371.50
C PERALATAN - -
D Jumlah A + B + C 50,215.00 54,945.00
E Overhead & Profit (contoh 10%) 10% 5,021.50 5,494.50
F Harga Satuan Pekerjaan (D+E) 55,236.50 60,439.50
16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 427,776.80 462,551.10
A Tenaga 53,700.00 59,030.00
L.01 0.350 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 436,566.90 472,626.55
A Tenaga 53,700.00 59,030.00
L.01 0.350 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 343,179.00 370,630.50
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,150.00 1,175.00 27,899.00 28,505.50
0.772 m3 Pasir Pasang 340,000.00 370,000.00 262,480.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 396,879.00 429,660.50
E Overhead & Profit (contoh 10%) 10% 39,687.90 42,966.05
F Harga Satuan Pekerjaan (D+E) 436,566.90 472,626.55
18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 337,107.10 364,396.45
A Tenaga 46,760.00 51,440.00
L.01 0.320 OH Pekerja 90,000.00 100,000.00 28,800.00 32,000.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 259,701.00 279,829.50
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,150.00 1,175.00 26,151.00 26,719.50
0.550 m3 Pasir Pasang 340,000.00 370,000.00 187,000.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 306,461.00 331,269.50
E Overhead & Profit (contoh 10%) 10% 30,646.10 33,126.95
F Harga Satuan Pekerjaan (D+E) 337,107.10 364,396.45
19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 343,332.00 371,552.50
A Tenaga 46,760.00 51,440.00
L.01 0.320 OH Pekerja 90,000.00 100,000.00 28,800.00 32,000.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 265,360.00 286,335.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,150.00 1,175.00 20,930.00 21,385.00
0.582 m3 Pasir Pasang 340,000.00 370,000.00 197,880.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 312,120.00 337,775.00
E Overhead & Profit (contoh 10%) 10% 31,212.00 33,777.50
F Harga Satuan Pekerjaan (D+E) 343,332.00 371,552.50
20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 270,785.90 298,130.80
A Tenaga 42,175.00 46,425.00
L.01 0.300 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 275,928.95 303,982.53
A Tenaga 42,175.00 46,425.00
L.01 0.300 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 208,669.50 229,922.75
12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
12.130 kg PC 1,150.00 1,175.00 13,949.50 14,252.75
0.388 m3 Pasir Pasang 340,000.00 370,000.00 131,920.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 250,844.50 276,347.75
E Overhead & Profit (contoh 10%) 10% 25,084.45 27,634.78
F Harga Satuan Pekerjaan (D+E) 275,928.95 303,982.53
C PERALATAN
D Jumlah A + B + C 287,346.40 310,290.05
E Overhead & Profit (contoh 10%) 10% 28,734.64 31,029.01
F Harga Satuan Pekerjaan (D+E) 316,081.04 341,319.06
C PERALATAN
D Jumlah A + B + C 287,868.40 309,001.55
E Overhead & Profit (contoh 10%) 10% 28,786.84 30,900.16
F Harga Satuan Pekerjaan (D+E) 316,655.24 339,901.71
22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 109,851.50 119,707.50
C PERALATAN
D Jumlah A + B + C 221,893.50 268,968.25
E Overhead & Profit (contoh 10%) 10% 22,189.35 26,896.83
F Harga Satuan Pekerjaan (D+E) 244,082.85 295,865.08
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 249,527.85 303,290.08
A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 112,918.50 150,593.25
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 500.00 720.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,150.00 1,175.00 9,418.50 9,623.25
3.20 Kg Semen Warna 11,000.00 15,000.00 35,200.00 48,000.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 226,843.50 275,718.25
E Overhead & Profit (contoh 10%) 10% 22,684.35 27,571.83
F Harga Satuan Pekerjaan (D+E) 249,527.85 303,290.08
26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 286,371.25 306,219.38
A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 146,412.50 153,256.25
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,150.00 1,175.00 13,512.50 13,806.25
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 260,337.50 278,381.25
E Overhead & Profit (contoh 10%) 10% 26,033.75 27,838.13
F Harga Satuan Pekerjaan (D+E) 286,371.25 306,219.38
C PERALATAN
D Jumlah A + B + C 142,304.00 153,805.00
E Overhead & Profit (contoh 10%) 10% 14,230.40 15,380.50
F Harga Satuan Pekerjaan (D+E) 156,534.40 169,185.50
29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 58,806.00 63,019.00
Tenaga 27,510.00 30,090.00
L.01 0.12 OH Pekerja 90,000.00 100,000.00 10,800.00 12,000.00
L.02 0.12 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
Bahan 25,950.00 27,200.00
0.003 m3 Papan Kayu Klas II 8,400,000.00 8,800,000.00 25,200.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 53,460.00 57,290.00
E Overhead & Profit (contoh 10%) 10% 5,346.00 5,729.00
F Harga Satuan Pekerjaan (D+E) 58,806.00 63,019.00
C PERALATAN
D Jumlah A + B + C 66,950.00 74,005.00
E Overhead & Profit (contoh 10%) 10% 6,695.00 7,400.50
F Harga Satuan Pekerjaan (D+E) 73,645.00 81,405.50
C PERALATAN
D Jumlah A + B + C 57,775.00 63,290.00
E Overhead & Profit (contoh 10%) 10% 5,777.50 6,329.00
F Harga Satuan Pekerjaan (D+E) 63,552.50 69,619.00
8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 11,783.75 13,046.00
A Tenaga 9,750.00 10,810.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 10,712.50 11,860.00
E Overhead & Profit (contoh 10%) 10% 1,071.25 1,186.00
F Harga Satuan Pekerjaan (D+E) 11,783.75 13,046.00
C PERALATAN
D Jumlah A + B + C 81,712.50 92,137.50
E Overhead & Profit (contoh 10%) 10% 8,171.25 9,213.75
F Harga Satuan Pekerjaan (D+E) 89,883.75 101,351.25
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,672,154.27 1,826,638.54
A Tenaga 942,750.00 1,036,050.00
L.01 6.00 OH Pekerja 90,000.00 100,000.00 540,000.00 600,000.00
L.02 3.00 OH Tukang Batu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.30 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 577,390.24 624,530.49
150.0 bh Batu Bata 580.00 625.00 87,000.00 93,750.00
120 Kg Portland Semen 0.11 1,150.00 1,175.00 138,000.00 141,000.00
0.3 m3 Pasir Pasang 0.0121 340,000.00 370,000.00 102,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,520,140.24 1,660,580.49
E Overhead & Profit (contoh 10%) 10% 152,014.02 166,058.05
F Harga Satuan Pekerjaan (D+E) 1,672,154.27 1,826,638.54
9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 351,422.50 394,047.50
A Tenaga 44,475.00 48,225.00
L.01 0.030 OH Pekerja 90,000.00 100,000.00 2,700.00 3,000.00
L.02 0.300 OH Tukang Batu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.030 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 319,475.00 358,225.00
E Overhead & Profit (contoh 10%) 10% 31,947.50 35,822.50
C PERALATAN
D Jumlah A + B + C 49,825.00 58,575.00
E Overhead & Profit (contoh 10%) 10% 4,982.50 5,857.50
F Harga Satuan Pekerjaan (D+E) 54,807.50 64,432.50
28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 83,897.00 91,173.50
cm
A Tenaga 13,020.00 14,300.00
L.01 0.080 OH Pekerja 90,000.00 100,000.00 7,200.00 8,000.00
L.02 0.040 OH Tukang Batu 120,000.00 130,000.00 4,800.00 5,200.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 63,250.00 68,585.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,150.00 1,175.00 40,250.00 41,125.00
0.014 m3 Pasir Pasang 340,000.00 370,000.00 4,760.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 220,000.00 2,240.00 3,080.00
- -
file:///conversion/tmp/activity_task_scratch/530032289.xls 249/165 PEK.SANITASI DALAM GEDUNG
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 76,270.00 82,885.00
E Overhead & Profit (contoh 10%) 10% 7,627.00 8,288.50
F Harga Satuan Pekerjaan (D+E) 83,897.00 91,173.50
C PERALATAN
D Jumlah A + B + C 350,800.00 392,280.00
E Overhead & Profit (contoh 10%) 10% 35,080.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 385,880.00 431,508.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 488,840.00 536,448.00
A Tenaga 222,200.00 243,840.00
L.01 100 % Pekerja 222,200.00 243,840.00 222,200.00 243,840.00
0.300 Oh Pekerja
0.010 Oh Mandor
B Bahan
C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 1 m2 Penyiapan badan jalan / tanah dasar (Subgrade) tiap 1m²
A Tenaga
0.025 Oh Pekerja
0.0004 Oh Mandor
B Bahan
C Peralatan
0.0033 jam VIBRATING ROLLER 6-8 TON
0.0071 jam WATER TANK TRUCK 3000-4500 L
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
0.025 Oh Pekerja
0.0250 Oh Mandor
B Bahan
1.2 m3 sirtu
C Peralatan
0.0215 jam VIBRATING ROLLER 6-8 TON
0.0071 jam WATER TANK TRUCK 3000-4500 L
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
1.000 Oh Pekerja
0.0340 Oh Mandor
B Bahan
0.768 m3 Batu pecah/split 2/3
0.432 m3 Pasir urug
C Jumlah A + B + C
0.0268 jam VIBRATING ROLLER 6-8 TON
0.0211 jam WATER TANK TRUCK 3000-4500 L
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
1.000 Oh Pekerja
0.0340 Oh Mandor
B Bahan
0.768 m3 Batu pecah 5/7
0.432 m3 Pasir urug
C Peralatan
0.0268 jam VIBRATING ROLLER 6-8 TON
0.0211 jam WATER TANK TRUCK 3000-4500 L
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
0.0043 Oh Pekerja
0.0009 Oh Mandor
B Bahan
0.6417 kg Aspal Polimer Lokal
C Peralatan
0.003 jam ASPHALT SPRAYER
0.0031 jam AIR COMPRESSOR
0.003 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
0.0043 Oh Pekerja
0.0009 Oh Mandor
B Bahan
0.6417 kg Aspal Polimer Lokal
C Peralatan
0.003 jam ASPHALT SPRAYER
0.0063 jam AIR COMPRESSOR
0.003 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
C Peralatan
0.0015 jam ASPHALT SPRAYER
0.0031 jam AIR COMPRESSOR
0.0015 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
C Peralatan
0.0027 jam THREE WHEEL ROLLER 8-10 TON
0.0144 jam ASPHALT SPRAYER
0.0108 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Pembuatan jalan aspal biasa (Sirtu t=10 cm, Agregat Kelas A t=20 cm,
10 1 m2
Permukaan Macadam t=5 cm) tiap m²
A Tenaga
0.3915 Oh Pekerja
0.0043 Oh Tukang aspal
0.014 Oh Mandor
B Bahan
0.12 m³ Sirtu
0.04 m³ Batu pecah/split 3/5
C Peralatan
0.066 jam VIBRATING ROLLER 6-8 TON
0.01352 jam WATER TANK TRUCK 3000-4500 L
0.00806 jam THREE WHEEL ROLLER 8-10 TON
0.0144 jam ASPHALT SPRAYER
0.0108 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
C Peralatan
A Tenaga
66 hr Pekerja
1 hr Tukang
2 hr Mandor
B Bahan
0.2 Set Alat bantu
C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
A Tenaga
4 hr Pekerja
1 hr Tukang
2 hr Mandor
B Bahan
0.2 Set Alat bantu
C Peralatan
A Tenaga
6 hr Pekerja
1 hr Tukang
1 hr Mandor
B Bahan
250.00 m3 kerikil
0.20 Set Alat bantu
C Peralatan
A Tenaga
67 hr Pekerja
2 hr Mandor
B Bahan
120.00 m3 kerikil
2.30 Set Alat bantu
C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
C Peralatan
C Peralatan
160.00 m3 Kerikil
0.20 Set Alat bantu
C Peralatan
75.00 m3 Kerikil
2.50 Set Alat bantu
C Peralatan
150.00 m3 Kerikil
15.00 m3 Pasir urug
0.20 set Alat bantu
C Peralatan
200.00 m3 Kerikil
0.20 m3 Pasir urug
C Peralatan
200.00 m3 Kerikil
4.00 m3 Alat bantu
C Peralatan
A Tenaga
14 hr Pekerja
2 hr Operator
1 hr Mandor
2 hr Sopir
B Bahan
C Peralatan
Memasang paving blok jalan setapak (warna abu T-16 uk. 8x10,5x21)
33 1 m2
+ urugan sirtu 10 cm + urugan pasir 5 cm tiap m2
A Tenaga
0.1875 Oh Pekerja
0.12 Oh Tukang batu
0.012 Oh kepala tukang
0.01375 Oh mandor
B Bahan
0.12 m³ Sirtu
C Peralatan
A Tenaga
0.076 Oh Pekerja
0.0225 Oh Tukang batu
0.00225 Oh kepala tukang
0.005 Oh mandor
B Bahan
0.0007 m³ Kayu Meranti Palembang papan
C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
28 Tower Air Be Unit
Tower Air fibe bh 1.0000 ### 4,919,500.00
Galian tanah m3 2.0000 ### 174,625.00
Urugan tanah m3 0.6667 ### 19,398.50
Foot plat (0,7 m3 0.6000 ### 2,848,659.38
Kolom (0,25x0 m3 1.0000 ### 5,366,478.61
Balok +R Balk m3 0.8000 ### 4,901,479.57
Plat (2,5x2,5 m3 0.8000 ### 5,161,595.82
Cat dinding m2 32.5000 ### 988,621.21
Tangga unit 1.0000 Pekerja #VALUE!
#VALUE!
Jasa 10 % #VALUE!
#VALUE!
HARGA BAHAN/UPAH JUMLAH
AN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
135,685.00 162,415.00
28,250.00 31,350.00
90,000.00 100,000.00 27,000.00 30,000.00
125,000.00 135,000.00 1,250.00 1,350.00
95,100.00 116,300.00
280,000.00 320,000.00 39,200.00 44,800.00
290,000.00 350,000.00 31,900.00 38,500.00
160,000.00 220,000.00 24,000.00 33,000.00
- -
123,350.00 147,650.00
10% 12,335.00 14,765.00
135,685.00 162,415.00
2,120.00 2,197.60
4,420.00 4,751.60
10% 442.00 475.16
4,862.00 5,226.76
246,645.30 278,361.05
5,375.00 6,000.00
90,000.00 100,000.00 2,250.00 2,500.00
125,000.00 140,000.00 3,125.00 3,500.00
216,000.00 240,000.00
180,000.00 200,000.00 216,000.00 240,000.00
- -
2,848.00 7,055.50
224,223.00 253,055.50
10% 22,422.30 25,305.55
246,645.30 278,361.05
Agregat Kelas A
474,617.00 548,586.06
94,250.00 104,590.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 4,250.00 4,590.00
330,240.00 386,880.00
340,000.00 380,000.00 261,120.00 291,840.00
160,000.00 220,000.00 69,120.00 95,040.00
6,980.00 7,244.60
431,470.00 498,714.60
10% 43,147.00 49,871.46
474,617.00 548,586.06
l jenis Waterbound
432,377.00 523,242.06
94,250.00 104,590.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 4,250.00 4,590.00
291,840.00 363,840.00
290,000.00 350,000.00 222,720.00 268,800.00
160,000.00 220,000.00 69,120.00 95,040.00
6,980.00 7,244.60
/ 1 m2 13,514.92 14,333.98
499.50 551.50
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 112.50 121.50
10,165.79 10,767.39
5,937.50 6,875.00 3,810.09 4,411.69
13,000.00 13,000.00 6,355.70 6,355.70
1,621.00 1,712.00
12,286.29 13,030.89
10% 1,228.63 1,303.09
13,514.92 14,333.98
m2 14,606.12 15,460.38
499.50 551.50
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 112.50 121.50
10,165.79 10,767.39
5,937.50 6,875.00 3,810.09 4,411.69
13,000.00 13,000.00 6,355.70 6,355.70
2,613.00 2,736.00
13,278.29 14,054.89
10% 1,327.83 1,405.49
14,606.12 15,460.38
1,291.00 1,352.00
8,822.75 9,942.50
10% 882.28 994.25
9,705.03 10,936.75
Surface Course)
82,711.75 96,106.45
13,659.50 15,160.50
90,000.00 100,000.00 12,735.00 14,150.00
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 537.50 580.50
57,321.00 65,036.00
320,000.00 360,000.00 12,800.00 14,400.00
340,000.00 380,000.00 7,480.00 8,360.00
330,000.00 390,000.00 3,630.00 4,290.00
290,000.00 320,000.00 725.00 800.00
5,937.50 6,875.00 28,500.00 33,000.00
13,000.00 13,000.00 4,186.00 4,186.00
4,212.00 7,173.00
75,192.50 87,369.50
10% 7,519.25 8,736.95
82,711.75 96,106.45
37,372.00 41,470.00
90,000.00 100,000.00 35,235.00 39,150.00
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 1,750.00 1,890.00
123,369.00 142,412.00
180,000.00 200,000.00
320,000.00 360,000.00 12,800.00 14,400.00
340,000.00 380,000.00 59,704.00 66,728.00
330,000.00 390,000.00 3,630.00 4,290.00
290,000.00 320,000.00 725.00 800.00
5,937.50 6,875.00 28,500.00 33,000.00
13,000.00 13,000.00 4,186.00 4,186.00
160,000.00 220,000.00 13,824.00 19,008.00
13,317.60 16,813.80
174,058.60 200,695.80
10% 17,405.86 20,069.58
191,464.46 220,765.38
574,393.38 662,296.14
765,857.84 883,061.52
957,322.30 1,103,826.90
1,148,786.76 1,324,592.28
1,531,715.68 1,766,123.04
dengan
307,175.37 399,621.34
2,315,000.00 2,635,000.00
90,000.00 100,000.00 90,000.00 100,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 1,750,000.00 2,000,000.00
25,600,040.00 35,200,055.00
160,000.00 220,000.00 25,600,000.00 35,200,000.00
40.00 55.00 40.00 55.00
5,595,000.00 5,760,000.00
279,250.33 363,292.13
10% 27,925.03 36,329.21
307,175.37 399,621.34
galian tanah
62,427.48 66,745.30
1,800,000.00 2,035,000.00
90,000.00 100,000.00 450,000.00 500,000.00
175,000.00 200,000.00 525,000.00 600,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 700,000.00 800,000.00
450.00 508.75
450.00 508.75 450.00 508.75
9,550,000.00 10,100,000.00
56,752.25 60,677.54
10% 5,675.23 6,067.75
62,427.48 66,745.30
6,280,000.00 6,970,000.00
90,000.00 100,000.00 5,940,000.00 6,600,000.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 250,000.00 270,000.00
314.00 348.50
1,570.00 1,742.50 314.00 348.50
550,000.00 600,000.00
2,134.47 2,365.73
10% 213.45 236.57
2,347.92 2,602.31
700,000.00 770,000.00
90,000.00 100,000.00 360,000.00 400,000.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 250,000.00 270,000.00
35.00 38.50
175.00 192.50 35.00 38.50
4,410,000.00 4,560,000.00
1,277.51 1,332.51
10% 127.75 133.25
1,405.26 1,465.76
790,000.00 870,000.00
90,000.00 100,000.00 540,000.00 600,000.00
125,000.00 135,000.00 125,000.00 135,000.00
125,000.00 135,000.00 125,000.00 135,000.00
45,002,250.00 50,002,500.00
180,000.00 200,000.00 45,000,000.00 50,000,000.00
11,250.00 12,500.00 2,250.00 2,500.00
8,125,000.00 8,300,000.00
269,586.25 14,793.13
10% 26,958.63 1,479.31
296,544.88 16,272.44
6,280,000.00 6,970,000.00
90,000.00 100,000.00 6,030,000.00 6,700,000.00
125,000.00 135,000.00 250,000.00 270,000.00
21,612,420.00 24,013,800.00
180,000.00 200,000.00 21,600,000.00 24,000,000.00
5,400.00 6,000.00 12,420.00 13,800.00
2,500,000.00 2,550,000.00
316,587.71 349,310.42
10% 31,658.77 34,931.04
348,246.48 384,241.46
PB) kelas A
350,288.90 420,376.20
535,000.00 600,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00
125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
46,681,667.50 56,124,027.50
320,000.00 360,000.00 14,400,000.00 16,200,000.00
340,000.00 380,000.00 7,820,000.00 8,740,000.00
330,000.00 390,000.00 4,290,000.00 5,070,000.00
320,000.00 380,000.00 8,640,000.00 10,260,000.00
160,000.00 220,000.00 11,520,000.00 15,840,000.00
11,667.50 14,027.50 11,667.50 14,027.50
550,000.00 600,000.00
318,444.45 382,160.18
10% 31,844.45 38,216.02
350,288.90 420,376.20
PB) kelas B
294,519.19 333,937.74
1,010,000.00 1,135,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
34,151,707.50 39,301,965.00
190,000.00 200,000.00 23,750,000.00 25,000,000.00
160,000.00 220,000.00 10,400,000.00 14,300,000.00
8,537.50 9,825.00 1,707.50 1,965.00
5,000,000.00 5,100,000.00
267,744.72 303,579.77
10% 26,774.47 30,357.98
294,519.19 333,937.74
PB) kelas C
335,422.27 352,335.50
1,190,000.00 1,335,000.00
90,000.00 100,000.00 540,000.00 600,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
30,401,520.00 32,001,600.00
190,000.00 200,000.00 30,400,000.00 32,000,000.00
7,600.00 8,000.00 1,520.00 1,600.00
5,000,000.00 5,100,000.00
304,929.33 320,305.00
10% 30,492.93 32,030.50
335,422.27 352,335.50
PB) kelas C
393,871.61 421,930.21
6,125,000.00 6,805,000.00
90,000.00 100,000.00 5,400,000.00 6,000,000.00
175,000.00 200,000.00 175,000.00 200,000.00
125,000.00 135,000.00 375,000.00 405,000.00
175,000.00 200,000.00 175,000.00 200,000.00
14,258,906.25 15,009,375.00
190,000.00 200,000.00 14,250,000.00 15,000,000.00
3,562.50 3,750.00 8,906.25 9,375.00
1,100,000.00 1,200,000.00
358,065.10 383,572.92
10% 35,806.51 38,357.29
393,871.61 421,930.21
PB) TELFORD
490,670.13 582,114.50
9,460,000.00 10,505,000.00
90,000.00 100,000.00 8,910,000.00 9,900,000.00
175,000.00 200,000.00 175,000.00 200,000.00
125,000.00 135,000.00 375,000.00 405,000.00
25,125,100.00 30,630,600.00
290,000.00 340,000.00 14,500,000.00 17,000,000.00
290,000.00 350,000.00 5,800,000.00 7,000,000.00
160,000.00 220,000.00 4,800,000.00 6,600,000.00
6,275.00 7,650.00 25,100.00 30,600.00
1,100,000.00 1,200,000.00
446,063.75 529,195.00
10% 44,606.38 52,919.50
490,670.13 582,114.50
) Kelas A
319,564.16 343,169.43
835,000.00 935,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
30,901,545.00 33,301,665.00
190,000.00 200,000.00 28,500,000.00 30,000,000.00
160,000.00 220,000.00 2,400,000.00 3,300,000.00
7,725.00 8,325.00 1,545.00 1,665.00
3,125,000.00 3,200,000.00
290,512.88 311,972.21
10% 29,051.29 31,197.22
319,564.16 343,169.43
) Kelas B
307,941.33 323,979.33
835,000.00 935,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
38,032,000.00 40,044,000.00
190,000.00 200,000.00 38,000,000.00 40,000,000.00
160,000.00 220,000.00 32,000.00 44,000.00
3,125,000.00 3,200,000.00
279,946.67 294,526.67
10% 27,994.67 29,452.67
307,941.33 323,979.33
) Kelas B
365,478.67 388,886.67
9,850,000.00 10,940,000.00
90,000.00 100,000.00 9,000,000.00 10,000,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 500,000.00 540,000.00
175,000.00 200,000.00
38,038,000.00 40,040,000.00
190,000.00 200,000.00 38,000,000.00 40,000,000.00
9,500.00 10,000.00 38,000.00 40,000.00
1,950,000.00 2,050,000.00
332,253.33 353,533.33
10% 33,225.33 35,353.33
365,478.67 388,886.67
s Aspal beton
1,796,002.66 1,845,345.72
at)
2,625,000.00 2,935,000.00
90,000.00 100,000.00 1,800,000.00 2,000,000.00
175,000.00 200,000.00 700,000.00 800,000.00
125,000.00 135,000.00 125,000.00 135,000.00
38,037,835.95 39,076,415.77
360,000.00 380,000.00 216,000.00 228,000.00
5,937.50 6,875.00 801,562.50 928,125.00
13,000.00 13,000.00 1,170,000.00 1,170,000.00
23,900,546.89 24,500,581.53 11,950,273.45 12,250,290.77
239,000.00 245,000.00 23,900,000.00 24,500,000.00
32,810,000.00 33,480,000.00
1,632,729.69 1,677,587.02
10% 163,272.97 167,758.70
1,796,002.66 1,845,345.72
1,735,000.00 1,935,000.00
90,000.00 100,000.00 1,260,000.00 1,400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
36,644,498.44 40,227,721.88
360,000.00 380,000.00 15,480,000.00 16,340,000.00
5,937.50 6,875.00 17,218,750.00 19,937,500.00
13,000.00 13,000.00 3,900,000.00 3,900,000.00
91,496.88 100,443.75 45,748.44 50,221.88
5,050,000.00 5,300,000.00
500,000.00 510,000.00 2,500,000.00 2,550,000.00
18,095.62 19,776.13
10% 1,809.56 1,977.61
19,905.19 21,753.75
araan (warna
sirtu 20 cm + 224,966.50 241,793.20
35,085.00 38,530.00
90,000.00 100,000.00 19,125.00 21,250.00
120,000.00 130,000.00 14,400.00 15,600.00
130,000.00 140,000.00 1,560.00 1,680.00
125,000.00 135,000.00
153,920.00 164,760.00
190,000.00 200,000.00 45,600.00 48,000.00
160,000.00 200,000.00 9,600.00 12,000.00
85,000.00 90,000.00 93,500.00 99,000.00
290,000.00 320,000.00 5,220.00 5,760.00
15,510.00 16,522.00
204,515.00 219,812.00
10% 20,451.50 21,981.20
224,966.50 241,793.20
32,835.00 36,030.00
90,000.00 100,000.00 16,875.00 18,750.00
120,000.00 130,000.00 14,400.00 15,600.00
130,000.00 140,000.00 1,560.00 1,680.00
125,000.00 135,000.00
126,870.00 136,260.00
190,000.00 200,000.00 22,800.00 24,000.00
160,000.00 200,000.00 9,600.00 12,000.00
85,000.00 90,000.00 89,250.00 94,500.00
290,000.00 320,000.00 5,220.00 5,760.00
15,510.00 16,522.00
175,215.00 188,812.00
10% 17,521.50 18,881.20
192,736.50 207,693.20
69,139.13 78,841.54
9,832.50 10,840.00
90,000.00 100,000.00 6,840.00 7,600.00
120,000.00 130,000.00 2,700.00 2,925.00
130,000.00 140,000.00 292.50 315.00
125,000.00 135,000.00
53,021.25 60,834.13
5,100,000.00 5,700,000.00 3,570.00 3,990.00
5,000,000.00 5,400,000.00 6,000.00 6,480.00
17,500.00 18,000.00 35.00 36.00
160,000.00 220,000.00 2,400.00 3,300.00
10,000.00 12,000.00 26,250.00 31,500.00
1,150.00 1,175.00 8,136.25 8,313.13
340,000.00 370,000.00 6,630.00 7,215.00
62,853.75 71,674.13
10% 6,285.38 7,167.41
69,139.13 78,841.54
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN - -
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 63 mm 5,500.00 6,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 90 mm 7,250.00 7,750.00 - -
B Bahan - -
- m' Pipa PVC Ø 110 mm 9,000.00 9,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 150 mm 23,750.00 27,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 200 mm 37,500.00 40,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 250 mm 76,250.00 80,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 300 mm 115,000.00 127,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 400 mm 240,000.00 262,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 450 mm 375,000.00 400,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 63 mm 27,500.00 30,000.00 - -
C PERALATAN - -
B Bahan - -
- m' Pipa GIP Ø 100 mm 34,166.67 40,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 125 mm 52,500.00 56,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 150 mm 65,000.00 68,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 200 mm 75,000.00 78,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 250 mm 98,333.33 111,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 300 mm 124,166.67 130,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 400 mm 167,500.00 208,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -
B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -
B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -
B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -
B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -
B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -
B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -
B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -
B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -
B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -
B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -
B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -
B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -
2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 510,251.50 579,894.70
100 mm
A Tenaga 209,905.00 228,015.00
L.01 1.646 OH Pekerja 70,000.00 75,000.00 115,220.00 123,450.00
L.02 0.823 OH Tukang Pipa 95,000.00 105,000.00 78,185.00 86,415.00
L.04 0.165 OH Mandor 100,000.00 110,000.00 16,500.00 18,150.00
B Bahan 70,000.00 80,000.00
1 bh Pipa Ø 100 mm 70,000.00 80,000.00 70,000.00 80,000.00
C PERALATAN 183,960.00 219,162.00
0.650 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 16,250.00 19,500.00
0.159 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 23,850.00 27,030.00
1.078 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 134,750.00 161,700.00
0.911 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 9,110.00 10,932.00
D Jumlah A + B + C 463,865.00 527,177.00
E Overhead & Profit (contoh 10%) 10% 46,386.50 52,717.70
F Harga Satuan Pekerjaan (D+E) 510,251.50 579,894.70
3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 738,116.50 826,245.20
150 mm
A Tenaga 267,280.00 290,340.00
L.01 2.096 OH Pekerja 70,000.00 75,000.00 146,720.00 157,200.00
L.02 1.048 OH Tukang Pipa 95,000.00 105,000.00 99,560.00 110,040.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 671,015.00 751,132.00
E Overhead & Profit (contoh 10%) 10% 67,101.50 75,113.20
F Harga Satuan Pekerjaan (D+E) 738,116.50 826,245.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 932,981.50 1,050,595.70
200 mm
A Tenaga 324,655.00 352,665.00
L.01 2.546 OH Pekerja 70,000.00 75,000.00 178,220.00 190,950.00
L.02 1.273 OH Tukang Pipa 95,000.00 105,000.00 120,935.00 133,665.00
L.04 0.255 OH Mandor 100,000.00 110,000.00 25,500.00 28,050.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 848,165.00 955,087.00
E Overhead & Profit (contoh 10%) 10% 84,816.50 95,508.70
F Harga Satuan Pekerjaan (D+E) 932,981.50 1,050,595.70
5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,100,346.50 1,230,946.20
250 mm
A Tenaga 382,030.00 414,990.00
L.01 2.996 OH Pekerja 70,000.00 75,000.00 209,720.00 224,700.00
L.02 1.498 OH Tukang Pipa 95,000.00 105,000.00 142,310.00 157,290.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00
6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,256,711.50 1,400,296.70
300 mm
A Tenaga 439,405.00 477,315.00
L.01 3.446 OH Pekerja 70,000.00 75,000.00 241,220.00 258,450.00
L.02 1.723 OH Tukang Pipa 95,000.00 105,000.00 163,685.00 180,915.00
L.04 0.345 OH Mandor 100,000.00 110,000.00 34,500.00 37,950.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,142,465.00 1,272,997.00
E Overhead & Profit (contoh 10%) 10% 114,246.50 127,299.70
F Harga Satuan Pekerjaan (D+E) 1,256,711.50 1,400,296.70
7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,569,441.50 1,749,997.70
400 mm
A Tenaga 554,155.00 601,965.00
L.01 4.346 OH Pekerja 70,000.00 75,000.00 304,220.00 325,950.00
L.02 2.173 OH Tukang Pipa 95,000.00 105,000.00 206,435.00 228,165.00
L.04 0.435 OH Mandor 100,000.00 110,000.00 43,500.00 47,850.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,426,765.00 1,590,907.00
E Overhead & Profit (contoh 10%) 10% 142,676.50 159,090.70
F Harga Satuan Pekerjaan (D+E) 1,569,441.50 1,749,997.70
8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,731,306.50 1,930,348.20
450 mm
A Tenaga 611,530.00 664,290.00
L.01 4.796 OH Pekerja 70,000.00 75,000.00 335,720.00 359,700.00
L.02 2.398 OH Tukang Pipa 95,000.00 105,000.00 227,810.00 251,790.00
L.04 0.480 OH Mandor 100,000.00 110,000.00 48,000.00 52,800.00
B Bahan 290,000.00 300,000.00
1 bh Pipa Ø 450 mm 290,000.00 300,000.00 290,000.00 300,000.00
C PERALATAN 672,385.00 790,572.00
1.420 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 35,500.00 42,600.00
1.629 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 244,350.00 276,930.00
3.003 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 375,375.00 450,450.00
1.716 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 17,160.00 20,592.00
D Jumlah A + B + C 1,573,915.00 1,754,862.00
E Overhead & Profit (contoh 10%) 10% 157,391.50 175,486.20
F Harga Satuan Pekerjaan (D+E) 1,731,306.50 1,930,348.20
10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,216,901.50 2,471,399.70
600 mm
A Tenaga 783,655.00 851,265.00
L.01 6.146 OH Pekerja 70,000.00 75,000.00 430,220.00 460,950.00
L.02 3.073 OH Tukang Pipa 95,000.00 105,000.00 291,935.00 322,665.00
L.04 0.615 OH Mandor 100,000.00 110,000.00 61,500.00 67,650.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,562,631.50 2,854,100.70
700 mm
A Tenaga 898,405.00 975,915.00
L.01 7.046 OH Pekerja 70,000.00 75,000.00 493,220.00 528,450.00
L.02 3.523 OH Tukang Pipa 95,000.00 105,000.00 334,685.00 369,915.00
L.04 0.705 OH Mandor 100,000.00 110,000.00 70,500.00 77,550.00
12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,864,361.50 3,203,801.70
800 mm
A Tenaga 1,013,155.00 1,100,565.00
L.01 7.946 OH Pekerja 70,000.00 75,000.00 556,220.00 595,950.00
L.02 3.973 OH Tukang Pipa 95,000.00 105,000.00 377,435.00 417,165.00
L.04 0.795 OH Mandor 100,000.00 110,000.00 79,500.00 87,450.00
B Bahan 430,000.00 450,000.00
1 bh Pipa Ø 800 mm 430,000.00 450,000.00 430,000.00 450,000.00
C PERALATAN 1,160,810.00 1,361,982.00
2.190 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 54,750.00 65,700.00
3.099 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 464,850.00 526,830.00
4.928 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 616,000.00 739,200.00
2.521 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 25,210.00 30,252.00
D Jumlah A + B + C 2,603,965.00 2,912,547.00
E Overhead & Profit (contoh 10%) 10% 260,396.50 291,254.70
F Harga Satuan Pekerjaan (D+E) 2,864,361.50 3,203,801.70