Anda di halaman 1dari 249

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : Kota Semarang
EDISI II 2019
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM
(Rp) (Rp)

1 Dump Truck 3 ton Jam 85,000 100,000

2 Dump Truck 9 ton Jam 110,000 115,000

3 Truk Bak Terbuka Engkel Jam 125,000 130,000

4 Truk Bak Terbuka Double Jam 170,000 175,000

5 Truk Tanki Air Jam 280,000 290,000

6 Bulldozer 100 - 150 hp Jam 675,000 700,000


7 Motor Grader Jam 625,000 640,000

8 Wheel Loader Jam 270,000 280,000

9 Excavator Jam 650,000 660,000

10 Crane 35 ton Jam 550,000 600,000

11 Flat Bed Truck jam 430,000 440,000


12 Baby Roller / Pedestrian Jam 110,000 120,000

13 P.Tire Roller 8 - 10 ton Jam 500,000 550,000

14 Baby Roller jam 40,000 42,000

15 Vibrator Roller self 7 ton Jam 500,000 510,000

16 Pile Driver / Hammer jam 150,000 160,000

17 Water Pump Jam 40,000 42,500

18 Asphalt Sprayer Jam 135,000 140,000

19 Pick Up single cabin Jam 40,000 55,000

20 A M P Jam 5,500,000 5,600,000

21 Asphalt Finisher Jam 340,000 350,000

22 Concrete Vibrator Jam 55,000 60,000

23 Compressor Jam 310,000 320,000

24 Concrete Mixer 0,125m3 Jam 75,000 80,000

25 Concrete Cutter jam 35,000 40,000

26 Stamper Jam 40,000 45,000

27 Genset 5-25kva+bbm Jam 180,000 183,000


28 Alat Pengecat Marka Jam 300,000 310,000

29 Mesin Las jam 180,000 200,000

30 Stone Crusher jam 850,000 900,000

31 Truck Trailler trip 7,250,000 7,400,000

32 Throweel Jam 75,000 80,000


33 Plate Compactor Jam 300,000 310,000
DAFTAR SEWA P E R A L A T AN

EDISI II 2019

KET.
DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : Kota Semarang
EDISI II 2019

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 90,000 100,000

2 Mandor Hr 125,000 135,000

3 Tukang listrik Hr 120,000 130,000

4 Tukang kayu Hr 120,000 130,000

5 Kep. tk. kayu Hr 130,000 140,000

6 Tukang batu Hr 120,000 130,000

7 Kep. tk. batu Hr 130,000 140,000

8 Tukang besi Hr 120,000 130,000

9 Kep. tk. besi Hr 130,000 140,000

10 T u k a n g c a t Hr 120,000 130,000

11 K e p . t k . c a t Hr 130,000 140,000

12 T u k a n g p l i t u r Hr 120,000 130,000

13 T u k a n g j a l a n Hr 90,000 100,000

14 T u k a n g g a l i Hr 90,000 100,000

15 Tukang masak aspal Hr 90,000 100,000

16 T k . l e i d e n g Hr 130,000 140,000

17 M a s i n i s Hr 175,000 200,000

18 P e m b . M a s i n i s Hr 125,000 150,000

19 P e n j a g a a p i Hr 90,000 100,000

20 P e n j a g a m a l a m Hr 90,000 100,000

21 Sopir Hr 175,000 200,000

22 Pembantu Sopir Hr 100,000 125,000

23 Kep TK Listrik Hr 105,000 115,000

24 pekerja jalan Hr 90,000 100,000

530032289.xls 249 UPAH TENAGA KERJA


mandor jalan 125,000 135,000

530032289.xls 249 UPAH TENAGA KERJA


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : Kota Semarang
EDISI II 2

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 210,000 250,000
Bulat Belah m3 280,000 320,000
Pecah 10/15 m3 290,000 340,000
Pecah 5/7 m3 290,000 350,000
Pecah 3/5 m3 320,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 190,000 200,000
Beton 0,5/1 m3 320,000 380,000
Beton 1/2 m3 330,000 390,000
Beton 2/3 m3 340,000 380,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 320,000
3 BATU BATA ex lokal bh 580 625
4 PASIR Urug m3 160,000 220,000
Pasang m3 340,000 370,000
Beton m3 360,000 380,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT
Merk Cibinong 40 kg zak 46,000 47,000
Merk Cibinong 50 kg zak 56,000 58,000
Merk Gresik 40 kg zak 45,000 46,000
Merk Gresik 50 kg zak 56,000 58,000
Merk Holcim 40 kg zak 85,000 90,000
Merk Holcim 50 kg zak 95,000 102,000
Merk Bima 40 kg zak 11,000 15,000
Merk Bima 50 kg zak 52,000 54,000
PC 1,125 1,150
Semen Putih 40 kg zak 75,000 80,000
Semen Putih 50 kg zak 85,000 90,000
Semen warna kg 11,000 15,000
II BAHAN PENUTUP ATAP
1 SIRAP (100 lbr) pak 190,000 210,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,400 7,200


Genteng Beton Warna Special bh 9,800 10,500
Genteng Beton Warna Khusus bh 14,800 15,200
Kerpus Beton Warna Standard bh 9,900 11,000
Kerpus Beton Warna Special bh 11,250 13,000
Kerpus Beton Warna Khusus bh 13,200 15,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,300 2,600
Kodok bh 2,500 3,100
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,000 15,000
Vlaam tebal 3 mm bh 15,000 17,000
Kodok tebal 2 mm bh 14,000 15,000
Kodok tebal 3 mm bh 15,000 17,500
5 ASBES GELOMBANG BESAR

. 200 cm X 102 cm X 5 mm bh 85,000 115,000


. 225 cm X 102 cm X 5 mm bh 98,000 125,000
. 250 cm X 102 cm X 5 mm bh 108,000 135,000
. 200 cm X 102 cm X 6 mm bh 120,000 145,000
. 225 cm X 102 cm X 6 mm bh 130,000 155,000
. 250 cm X 102 cm X 6 mm bh 140,000 160,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,000 55,000
. 180 cm X 105 cm X 4 mm bh 50,500 68,000
. 210 cm X 105 cm X 4 mm bh 59,500 81,000
. 240 cm X 105 cm X 4 mm bh 67,500 96,000
. 270 cm X 105 cm X 4 mm bh 75,000 104,000
. 300 cm X 105 cm X 4 mm bh 84,500 119,000

6 ASBES PLAT
. 100cm X 100 cm X 3 mm 15,500 17,000
. 100cm X 100 cm X 4 mm 16,000 20,000
. 50 cm X 200 cm X 3 mm 14,200 15,000
. 40 cm X 200 cm X 3 mm 13,800 14,500

ONDULINE : 95 cm x 200cm x 0.3mm lbr 160,000 165,000


ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 95,000 105,000

NOK Jabes nok


. Kerpus Genteng bh 31,000 40,000
. Stel Besar bh 44,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 50,000 55,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 115,000 125,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 75,000 80,000
uk. 122cm x 244cm x 4mm lbr 77,000 85,200

GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 112,000


uk.122cm x 244cm x 6mm lbr 130,000 135,000
uk.122cm x 244cm x 8mm lbr 199,500 201,500
uk.122cm x 244cm x 10mm lbr 255,000 260,000

7 FIBRE GLASS (JABES)


180 X 92 cm bh 55,000 61,000
200 X 92 cm bh 60,000 66,000
250 X 92 cm bh 68,000 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 22,000 24,500
BJLS 0,20 lebar 55 cm m' 25,000 30,000
BJLS 0,28 lebar 55 cm m' 26,500 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 43,000 45,000
BJLS 0,20 panjang 180 cm lbr 47,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 72,000

Atap Galvalum Colorcoat 0,4 mm m2 88,000 100,000

Nok Gavalum Colorcoat m' 35,000 35,000

Atap Multiroof 0,30 mm lbr 40,000 40,000

Nok Atap Moltiroof bh 30,000 30,000

III . B A H A N K A Y U
1 JATI Papan m3 28,000,000 29,000,000
Balok/pesagen m3 25,000,000 26,000,000
2 KAMPER Papan m3 8,700,000 8,800,000
Balok/pesagen m3 8,400,000 8,600,000
3 KRUING Papan m3 8,400,000 8,800,000
Balok/pesagen m3 6,500,000 6,800,000
4 MERANTI Papan m3 5,100,000 5,700,000
Balok/pesagen m3 5,000,000 5,400,000
5 LANAN Papan m3 3,290,000 3,300,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 10,500,000 10,650,000
Balok/pesagen m3 9,500,000 9,900,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000

8 KAYU GLUGU

Balok/pesagen 6X12X400 3,500,000 3,500,000


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI

1 UBIN (TEGEL BIASA) bh 5,500 6,000


PC polos 30 X 30 cm m2 35,000 38,000
20 X 20 cm m2 34,000 37,000
PC warna 30 X 30 cm m2 40,000 48,000
20 X 20 cm m2 39,500 45,000
Teraso 30 X 30 cm m2 52,000 56,000
Ubin keramik bh 3,000 3,250
2 TEGEL PLINT

PC warna 10 X 20 cm bh 5,200 5,500


PC abu-abu 15 x 20 bh 5,100 6,000

POLIS UBIN Lantai/badan m' - -


Plint m' - -
Trap m' - -

PASANG ALDAS DECORATIVE STONE M2 110,000 110,000

3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000

Floor hardener Kg - -
4 MOZAIK PORSELIN
10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000

5 Keramik 30 X 30 cm m2 60,000 78,000


20 X 20 cm m2 60,000 76,000
33 x 33 cm m2 60,000 78,000
25 x 25 cm m2 55,000 75,000
15 x 20 cm m2 57,000 75,000
40 x 40 cm m2 55,000 55,000
60 x 60 cm m2 60,000 60,000
6 Parquet Jati m2 270,000 310,000
7 Batu Paros m2 110,000 115,000
8 Batu Tempel Hitam m2 110,000 120,000
9 GRANITILE 60 x 60 cm m2 220,000 250,000
30 x 30 cm m2 300,000 320,000
10 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 36,000 40,000
Ø 20 cm - 100 cm bh 42,000 50,000
Ø 30 cm - 100 cm bh 64,000 80,000
Ø 50 cm - 100 cm bh 125,000 160,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Ø 60 cm - 100 cm bh 175,000 215,000
Ø 70 cm - 100 cm bh 250,000 265,000
U 10 cm - 100 cm bh 30,000 32,500
U 15 cm - 100 cm bh 35,000 40,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
U 20 cm - 100 cm bh 39,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 80,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 9,000 12,000
20 X 20 cm bh 12,500 16,000
25 X 25 cm bh 16,500 20,000
30 X 30 cm bh 19,000 22,000
15 X 25 cm bh 18,000 20,000
15 X 30 cm bh 20,000 22,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,000 12,000
besi beton prestress kg 14,000 14,500
besi beton ulir kg 13,200 13,500

2 BESI PLAT Besi Strip kg 14,000 14,250

3 BESI PROFIL Besi Profil kg 14,500 14,750


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 135,000 140,000
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 105,000 115,000
lebar : 7,5cm tebal : 0,65mm btg 95,000 105,000
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 50,000 62,500
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 45,000 55,000
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 20,000 25,000
tinggi 4 cm; tebal : 0,3 mm btg 27,000 30,000
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000 14,500
Diameter 6 - 15 kg 13,500 14,700
Kawat bronjong kg - -
5 BESI SIKU L 40 X 40 X 4 btg - 135,000
L 50 X 50 X 5 btg - 217,500
L 60 X 60 X 6 btg - 355,000

6 KAWAT - Ikat beton/bendrat kg 18,000 20,000


- Harmonika 12 X 45 mm m2 20,000 35,000
- Harmonika 12 X 24 mm m2 20,000 21,000
- Harmonika 14 X 30 mm m2 20,000 21,000
- Harmonika 14 X 35 mm m2 25,000 27,500
- Kawat Nyamuk Nylon m2 20,000 25,000
- Kawat Kasa m2 15,000 18,000
- Saringan pasir m2 19,000 20,000
- Kawat loket m2 17,000 18,500
- Kawat duri rol 110,000 140,000
- Kawat bronjong kg 25,000 27,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 31,000
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 36,500
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 55,000
Pipa PVC DN 40 ( 1½" ) btg 56,000 70,000
Pipa PVC DN 63 ( 2" ) btg 70,000 105,000
Pipa PVC DN 90 ( 3" ) btg 125,000 185,000
Pipa PVC DN 110 ( 4" ) btg 270,000 280,000
Pipa PVC DN 160 ( 6" ) btg 530,000 550,000
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000
Pipa PVC DN 250 ( 10" ) btg - -
Pipa PVC DN 315 ( 12" ) btg - -

2 Pipa Medium A Galvanis - SII


Pipa Medium Galvanis 0,50" btg 155,000 160,000
Pipa Medium Galvanis 0,75" btg 195,000 200,000
Pipa Medium Galvanis 1" btg 305,000 315,000
Pipa Medium Galvanis 1,25" btg 380,000 390,000
Pipa Medium Galvanis 1,50" btg 440,000 450,000
Pipa Medium Galvanis 2" btg 590,000 602,000
Pipa Medium Galvanis 2,50" btg 740,000 752,000
Pipa Medium Galvanis 3" btg 970,000 975,000
Pipa Medium Galvanis 4" btg 1,425,000 1,430,000
Pipa Medium Galvanis 5" btg 1,900,000 1,905,000
Pipa Medium Galvanis 6" btg - -

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,500
30 X 60 lbr 13,200 14,500
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr - -
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 65,000 75,000
. 120 X 240 X 3 mm lbr 80,000 95,000
. 90 X 210 X 4 mm lbr 65,000 85,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 200,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 61,500
. 120 X 240 X 4 mm lbr 65,000 70,000
. 120 X 240 X 6 mm lbr 75,000 86,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000 160,000
. 120 X 240 X 12 mm lbr 165,000 165,000
. 120 X 240 X 15 mm lbr 190,000 190,000
. 120 X 240 X 18 mm lbr 215,000 -

Woodplank 70,000 75,000


lbr 84,000 90,000
lbr 54,000 60,000
Formika ukuran pintu lbr 70,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,500 4,100
Batu Apung kg 50,000 55,000
Cat dasar kg 40,000 42,500
. Emco kg 62,000 68,000
. Yunior 66 (nippon paint) kg 60,000 71,000
- Koas bh 7,500 15,000
. Deculux kg 63,000 75,000
. Siralax ons 15,000 21,000
. Spiritus ltr 13,000 18,000
. Plitur jadi ltr 65,000 68,000

2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 26,000
Sintex 5 kg 120,000 125,000
Danabride 5 kg 115,000 122,000
Catylac 5 kg 120,000 130,000
Mowilex 2,50 kg 280,000 350,000
Cat weathershiel kg 105,000 105,000

3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 62,000 69,000
Cat kg 40,000 45,000
Thinner A ltr 15,000 20,000
Minyak cat ltr 15,000 20,000
Thinner Super ltr 17,500 35,000
Zincrome kg 17,500 23,750
Residu (teer/aspal) drum 55,000 60,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Fibre glass (tanki air) - -
kapasitas 550 liter. bh 1,000,000 1,100,000
kapasitas 1100 liter. bh 1,600,000 1,700,000
Kuas bh - -
Roll bh - -
Lem Aica Aibon kg 55,000 65,000
Genteng (Mowilex) kg 74,000 74,000
water Profing/Coating kg 50,000 50,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 85,000 95,000
5 mm m2 95,000 105,000
2 ES KABUR 3 mm m2 95,000 110,000
5 mm m2 120,000 130,000
3 RAY BAND 3 mm m2 85,000 95,000
5 mm m2 90,000 105,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 5,000 5,500

SPLN LMK 1 X 2 1/2 mm2 m' 5,500 6,200

. 1X4 mm2 m' 6,500 7,750

1X6 mm2 m' 10,100 11,000

NYY :. 2 X 1 1/2 mm2 m' 11,000 11,500

PRIMA 2 X 2 1/2 mm2 m' 15,500 16,500

. 2X4 mm2 m' 28,000 29,500

2X6 mm2 m' 37,000 39,000

3 X 1 1/2 mm2 m' 14,500 16,700

3 X 2 1/2 mm2 m' 21,000 22,100

3X4 mm2 m' 35,600 39,000

3X6 mm2 m' 50,000 56,000

NYM :. 2 X 1 1/2 mm2 m' 8,000 8,500

PRIMA 2 X 2 1/2 mm2 m' 11,500 12,000

. 2X4 mm2 m' 22,500 24,000

3 X 1 1/2 mm2 m' 13,200 14,500

3 X 2 1/2 mm2 m' 21,050 23,400

3X4 mm2 m' 32,000 36,000

3X6 mm2 m' 45,000 49,000

2 SKAKELAR
Out bauw . Seri bh 20,000 25,000

. Engkel bh 15,000 20,000

In bauw . Seri bh 16,500 25,000

. Engkel bh 14,000 17,500

3 FUSE BOX (SEKERING KASA)


1 group bh 135,000 165,000

2 group bh 245,000 280,000

3 group bh 350,000 395,000

4 STEKER - Biasa bh 10,000 15,000

Arde bh 15,000 17,500

T Biasa bh 12,500 15,500

T dengan Arde bh 17,000 20,000


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
5 FITING Flaon bh 15,500 25,000

Gantung bh 12,500 20,000

Kap bh 12,500 20,000

Kombinasi bh 25,000 31,000

6 STOP KONTAK - Arde Outbow putih bh 22,000 30,000

Arde Outbow hitam bh 25,000 35,000

Arde IB bh 26,000 40,000

Arde Putar bh 35,000 50,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 100,000 125,000
2 X slag bh 165,000 200,000
Yale : 1 X slag bh 95,000 150,000
2 X slag bh 130,000 170,000
Kuda : 1 X slag bh 70,000 85,000
2 X slag bh 110,000 125,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 16,000 30,000
Kupu-kupu biasa bh 4,500 6,000
Nylon kupu-kupu bh 7,500 9,000
Espagnoled - dalam negeri bh 40,000 50,000
Grendel Tanam luar negeri bh 11,000 13,000
Grendel biasa bh 8,000 10,000
Kait Angin bh 17,500 20,000
Door Stop bh 275,000 350,000

Kunci Tanam bh 27,000 27,500

Kunci Tanam bh - -

Engsel Pintu bh 8,250 8,500

Engsel Jendela bh 7,500 7,500

Grendel Jendela bh 7,000 7,500

Engsel kait (Kismen) 16" bh 60,000 60,000

Engsel kait (Kismen) 18" 39,000 39,000


XIII . BAHAN SANITAIR
1 KLOSET DUDUK bh 1,600,000 1,850,000
2 KLOSET JONGKOK bh 145,000 160,000
3 WASTAFEL PEDESTAL bh 950,000 1,050,000
4 WASTAFEL MEJA OVAL bh 750,000 950,000
5 WASTAFEL GANTUNG BULAT bh 300,000 325,000
6 WASTAFEL GANTUNG SUDUT bh 250,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 240,000 275,000
8 WASTAFEL BAK CUCI bh 150,000 165,000
9 TEMPAT SABUN GANTUNG bh 45,000 55,000
10 TEMPAT SABUN TANAM bh 22,500 25,000
11 SEPTIC TANK (ETERNIT GRESIK)
5 Pemakai 500 liter Unit - -
10 Pemakai 1.000 liter Unit - -
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
12 LAIN - LAIN
Kran Air bh 27,500 45,000
Seal tape bh 4,000 4,500
Floor drain bh 35,000 42,500

Kloset Jongkok Teraso bh - -

Urinoir bh - -

Bak Mandi Teraso bh - -

Bak Mandi Fiberglass Vol. 0,3 M3 bh - -

Bak Mandi Fiberglass Vol. 1 M3 bh - -

Bak Dip bh - -

Cairan/Bubuk pembersih kg - -

Bak cuci Stainless Steel bh - -

Bak cuci Teraso bh - -

Waterdrain + Perlengkapan set - -


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 17,500 18,000
2 PAKU - payung kg 20,000 26,000
3 PAKU - sekrup kg 7,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 7,000 7,200
9 Paku skrup konektor bh 6,000 7,000

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 350,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000
. 200 watt bh 750,000 850,000
. 250 watt bh 850,000 950,000

X VI . PAVING BLOCK paving 6 cm 60,000 70,000


1 SQUARE Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
2 HOLLAND Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
3 UNIDECOR Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
4 UNI Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
5 TRIHEX Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
6 OLYMPIA HEXA Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
7 HEXAGONAL Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
8 CASTLE Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
9 TRAPEZ Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 85,000 90,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 4,800 5,500
13 KANSTEEN m' 25,000 30,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 60,000
2 Sliding Pintu J3 btg 215,000 225,000
Sliding Pintu J4 btg 200,000 235,000
Sliding Pintu J5 btg 275,000 280,000
3 Naco per Daun bh 37,500 40,000
4 Rolling door Besi m2 325,000 335,000
Rolling door Almunium m2 275,000 290,000
5 Awning Almunium m2 225,000 250,000
6 Kusen Almunium 4" Putih m' 95,000 100,000
Kusen Almunium 4" Coklat m' 100,000 110,000
Kusen Almunium 3" Putih m' 90,000 95,000
7 H.BLOM 150X150X6,5X10X12 btg - -
8 WIDE FLANGE BEAM 8,750 9,100
150 X 75 X 5 X 7 X 12 btg 1,380,000 1,528,800

9 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum - -
Aspal SPC 60/70 Ex singapura isi Net 155 kg drum 950,000 1,100,000
Aspal SPC 60/70 Ex singapura isi Net 160 kg drum 950,000 1,100,000

Hotmix Tebal = 4 Cm m2 67,500 70,000


Hotmix Tebal = 5 Cm m2 82,000 85,000
Hotmix Tebal = 6 Cm m2 97,000 100,000
Hotmix Tebal = 7 Cm m2 115,000 120,000
Binder Course ton 1,300,000 1,325,000
Wearing Course ton 1,300,000 1,400,000
Hot Roller Sheet ton 1,150,000 1,250,000
Sand Sheet ton 1,200,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,500,000
Cold Mix ton 1,800,000 1,850,000
Prime / Tack Coard RC liter 7,200 8,000
Prime Coat MC liter 7,200 8,000
Prime / Tack Coat Emulsi liter 7,200 8,000
10 K A C A
Cermin tebal 5 mm m2 275,000 325,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 310,000 325,000


Pagar BRC 120 A2 /lb 375,000 390,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 400,000 425,000
Sunscreen Allumunim m2 350,000 400,000
Allumunium Foil m2 12,000 15,000
Soda api kg 13,000 15,000
Sabun kg 12,500 15,000
Koas m3 14,000 17,500
Koas Alang-alang ikat 2,000 2,500
Air 20,000 25,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM
(Rp) (Rp)
Solar (Industri) ltr 8,200 8,600
Premium (Industri) ltr 7,050 7,800
Pelumas ltr 37,000 45,000
Vynil 30x30 cm bh 6,200 6,500
EDISI II 2019

KET
KET
KET
KET
KET
KET
KET
KET

panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m
panj : 6 m

panj : 4 m
panj : 4 m
KET

panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m

panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
panjang 6 m
KET
KET
KET
KET
KET
KET
KET
KET
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI II 2019


DAERAH : Kota Semarang

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 A.2.2.1.2 m' 705,963.50 757,501.25


Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 176,082.50 185,498.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 2,260,500.00 2,408,037.50

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,774,575.00 1,887,215.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,674,007.50 1,766,118.75

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 2,012,725.00 2,152,975.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 16,775.00 18,425.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 416,407.20 460,448.12

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 635,470.00 666,864.00

10 A.2.2.1.12 Pembuatan Jalan Sementara m2 178,337.50 202,262.50

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,411,641.00 1,565,641.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 664,570.50 738,270.50

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 59,646.40 63,002.50


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x 240
14 A.2.2.1.16 m2 296,741.50 327,822.00
cm
Pengukuran dan pemasangan Bauplank (kayu Kruing)
15 Rev SNI m' 176,082.50 185,498.50
tiap 1 m'
Pengukuran dan pemasangan Bauplank (kayu
16 HIT SNI m' 77,335.50 82,428.50
kampung/Lanan) tiap 1 m'

17 Rev SNI Bongkaran Beton Bertulang m3 1,411,641.00 1,565,641.00

18 DHAN Bongkaran plesteran tiap 1 m2 m2 5,293.75 5,871.25

19 DHAN Bongkaran atap genteng tiap 1 m2 m2 21,175.00 23,485.00

20 DHAN Bongkaran atapasbes/seng tiap 1 m2 m2 7,975.00 8,635.00

21 DHAN Bongkaran reng dan kaso tiap 1 m2 m2 14,245.00 15,702.50

LS

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 77,687.50 86,212.50
2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 95,287.50 105,682.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 113,162.50 125,449.50

530032289.xls 249/39 HARGA SATUAN PEKERJAAN


4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 103,400.00 114,752.00
5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 156,750.00 173,910.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 124,987.50 138,682.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 5,637.50 6,242.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 34,045.00 37,785.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 18,791.67 20,808.33
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 56,375.00 62,425.00

11 A.2.3.1.11 Urugan Pasir m3 242,275.00 324,885.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 456,346.00 500,577.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 63,112.50 66,247.50
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 265,787.50 295,212.50

15 DHAN Menggali dengan excavator (skala besar) tiap 1m³ m3 25,526.05 26,486.35
Mengurug tanah tiap 20 cm di padatkan (Tanah
16 HIT m3 214,775.00 260,425.00
didatangkan) tiap 1 m3
Memadatkan tanah dengan tamper/hand compactor 6
17 DHAN m3 12,724.80 14,315.40
lintasan / tebal 20cm tiap 1 m3
18 DHAN Memadatkan tanah dengan Vibrating Roller tiap 1 m³ m3 4,180.00 4,263.60

Mengurug tanah tiap 20 cm di padatkan dengan Alat


19 HIT m3 198,226.05 241,208.00
berat (tanah didatangkan) tiap 1 m3
20 HIT Cut and fill (termasuk pemadatan) tiap 1 m3 m3 32,191.50 32,938.95

21 DHAN Buang/Angkut tanah tiap 1 m3 sejauh s/d 100 m m3 51,562.50 57,227.50

530032289.xls 249/40 HARGA SATUAN PEKERJAAN


III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,088,257.50 1,202,217.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,052,012.50 1,166,055.00

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 1,026,833.50 1,140,925.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 1,009,156.50 1,123,287.00

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 984,868.50 1,099,043.00

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 871,997.50 977,487.50

7 A.3.2.1.7 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP m3 961,020.50 1,072,951.00

8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP m3 942,034.50 1,054,262.00

9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 598,471.50 706,711.50

Pasang Pondasi Siklop, 60% Beton Campuran 1PC :


10 A.3.2.1.10 m3 2,548,854.00 2,928,244.00
2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 1,007,066.50 1,091,700.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 1,054,814.36 1,131,401.07
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 1,083,503.70 1,160,667.33
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,105,781.02 1,183,284.40
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100),


4 A.4.1.1.4 m3 981,343.47 1,051,959.92
slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,132,229.04 1,210,253.17
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,157,470.26 1,235,818.86
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,176,603.56 1,255,477.58
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,189,135.12 1,268,011.61
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,211,100.79 1,290,032.86
(K275), slum (12±2)cm, w/c = 0,53

530032289.xls 249/41 HARGA SATUAN PEKERJAAN


Membuat Beton mutu f'c=26,4 MPa (K300), slum
10 A.4.1.1.10 m3 1,217,722.03 1,296,636.49
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,301,821.04 1,386,882.76
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,310,695.25 1,395,761.77
(12±2)cm, w/c = 0,48

530032289.xls 249/42 HARGA SATUAN PEKERJAAN


13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,619.10 16,128.20
14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,635.75 18,354.05

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,768.85 31,643.15

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 187,858.00 206,085.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 198,858.00 218,185.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 411,636.50 463,292.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 433,086.50 485,732.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 504,036.50 568,892.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 470,486.50 527,092.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 389,141.50 438,542.50


23 A.4.1.1.27 Memasang Jembatan Cor m2 104,445.00 114,576.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 87,780.00 98,840.50

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 113,597.00 127,311.25

Membuat Pondasi Beton Bertulang (150 kg Besi +


26 A.4.1.1. m3 4,402,788.50 4,907,435.50
Bekisting)
Membuat Sloof Beton Bertulang (200 kg Besi +
27 A.4.1.1. m3 5,386,441.50 6,020,932.50
Bekisting)

Membuat Kolom Beton Bertulang (300 kg Besi +


28 A.4.1.1. m3 7,941,136.50 8,738,867.50
Bekisting)

Membuat Balok Beton Bertulang (200 kg Besi +


29 A.4.1.1. m3 7,705,214.00 8,465,600.00
Bekisting)
Membuat Balok Beton Bertulang (150 kg Besi +
30 A.4.1.1. m3 7,084,302.50 7,755,357.50
Bekisting)

Membuat Dinding Beton Bertulang (150 kg Besi +


31 A.4.1.1. m3 6,979,582.50 7,632,157.50
Bekisting)

Membuat Tangga Beton Bertulang (200 kg Besi +


32 A.4.1.1. m3 6,949,101.50 7,681,382.50
Bekisting)
Membuat Beton Non Struktur 1Pc : 3Ps : 5Kr - untuk
33 SNI m3 1,017,995.00 1,095,765.00
rabatan/ beton tumbuk tiap 1m³
Membuat Lantai Kerja Beton 1Pc : 3Ps : 5Kr - untuk
34 SNI m2 157,003.00 172,744.00
beton rabatan/tumbuk tebal 5 cm tiap 1 m2
Membuat Beton rabatan/beton tumbuk 1 Pc : 3 Ps: 5 Kr
35 HIT SNI m2 82,381.20 90,990.90
tebal 3 cm tiap 1 m2
Membuat Beton rabatan/beton tumbuk 1 Pc : 3 Ps: 5 Kr
36 HIT SNI m2 192,222.80 212,312.10
tebal 7 cm tiap 1 m2
Membuat Beton rabatan/beton tumbuk 1 Pc : 3 Ps: 5 Kr
37 HIT SNI m2 274,604.00 303,303.00
tebal 10 cm tiap 1 m2
Membuat Kolom penguat beton bertulang (11 x 11) cm
38 SNI m' 75,075.00 144,347.50
(Kolom Praktis)
Membuat Kolom penguat beton bertulang (11 x 11) cm
39 HIT SNI m3 6,204,545.45 11,929,545.45
(Kolom Praktis)

40 SNI Membuat Ring Balok Beton Bertulang (10 x 15) cm m2 92,719.00 111,086.25

41 HIT SNI Membuat Ring Balok Beton Bertulang (10 x 15) cm m3 6,181,266.67 7,405,750.00

42 HIT Pekerjaan Floor Hardener tiap 1 m2 m2 18,645.00 20,570.00

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5


1 A.4.1.2.1 m2 90,593.50 96,836.75
Mpa, Slump (120 ± 20) mm K3

530032289.xls 249/43 HARGA SATUAN PEKERJAAN


Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =
2 A.4.1.2.2 m2 113,276.25 121,083.07
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5


3 A.4.1.2.3 m2 132,554.50 141,550.88
Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5


4 A.4.1.2.4 m2 169,897.88 181,608.10
Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 m2 126,974.18 136,379.06
Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 -


6 A.4.1.2.6 m2 52,174.10 54,975.36
12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 -


7 A.4.1.2.7 m2 45,711.60 48,210.36
12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk Komponen


8 A.4.1.2.8 bh 8,310.50 9,146.50
Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 bh 13,458.50 14,822.50
Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk Komponen


10 A.4.1.2.10 bh 10,884.50 11,984.50
Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 70,339.50 76,312.50
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 72,319.50 78,468.50
Pracetak

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 m3 65,015.50 70,537.50
Pracetak

530032289.xls 249/44 HARGA SATUAN PEKERJAAN


14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 583,559.02 609,282.96
15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 573,536.70 598,516.60

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 824,292.04 865,372.42

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 158,312.44 165,631.62

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 125,268.44 128,924.62

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 125,268.44 128,924.62

20 A.4.1.2.20 Bahan Grout Campuran m3 3,417,700.00 3,689,125.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,061,300.00 3,368,750.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 64,113.50 69,371.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 137,351.50 147,110.70

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 55,236.50 60,439.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 33,473.00 35,208.25

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 26,199.25 28,061.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 103,020.50 119,806.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 917,235.00 957,132.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,403.94 2,781.68

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 257,834.28 289,234.66


7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 652,685.00 691,471.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 550,957.00 588,863.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 510,510.00 576,114.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 554,675.00 594,825.00


Pemasangan Kusen Pintu & Jendela Allumunium warna
11 A.4.2.1.11 m' 130,736.65 138,573.05
Hijau 4"
12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 553,498.00 587,737.70

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 521,009.50 555,153.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 192,830.00 206,613.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 587,797.86 640,238.66


16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 105,222.45 118,725.71

530032289.xls 249/45 HARGA SATUAN PEKERJAAN


17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 138,572.50 151,178.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar


18 A.4.2.1.18 m' 209,838.75 232,259.50
90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 124,712.50 134,480.50
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 158,730.00 171,413.00
Modul 60x60 cm dinding plafond

530032289.xls 249/46 HARGA SATUAN PEKERJAAN


Pemasangan Atap Pelana Rangka Atap Baja Canal C
21 A.4.2.1.22 m2 248,633.28 267,087.01
dingin Profil C75

Pemasangan Atap jurai Rangka Atap Baja Canal C


22 A.4.2.1.23 m2 275,722.15 295,152.83
dingin Profil C75

23 LS Memasang rangka atap baja ringan tiap 1 m2 m2 166,929.95 177,146.48

24 HIT Memasang 1 m' Kosen Alumunium 3" YKK m' 210,893.65 232,414.05

Memasang 1 m2 pintu kaca rayband rangka allumunium


25 HIT m' 431,981.00 714,548.34
warna (Biasa)

Memasang 1 m2 pintu kaca rayband rangka allumunium


26 HIT m' 764,621.00 783,948.00
warna (YKK)

Memasang 1 m2 jendela/BV kaca, rangka allumunium


27 HIT m' 725,768.65 745,095.65
warna (Biasa)

Memasang 1 m2 jendela/BV kaca, rangka allumunium


28 HIT m' 1,072,467.00 1,091,794.00
warna (YKK)

29 HIT Memasang kawat duri tiap m' m' 7,755.00 8,937.50

30 SNI Memasang kaca nako dan tralis besi tiap 1 m2 m2 435,187.50 456,923.50

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22) cm


1 A.4.4.1.1 m2 267,052.50 287,168.75
Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


2 A.4.4.1.2 m2 257,820.75 278,009.88
Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 m2 250,472.75 270,551.88
Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 m2 248,336.00 268,592.50
Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


5 A.4.4.1.5 m2 251,135.50 271,950.25
Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 m2 238,526.20 258,438.40
Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 m2 129,236.25 139,151.38
Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 m2 124,190.55 134,045.73
Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 m2 121,682.00 131,557.25
Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 m2 120,127.70 130,018.90
Tebal 1/2 Bata Camp. 1SP : 5PP

530032289.xls 249/47 HARGA SATUAN PEKERJAAN


Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm
11 A.4.4.1.11 m2 119,903.30 129,889.10
Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 m2 117,975.00 127,943.75
Tebal 1/2 Bata Camp. 1SP : 8PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 m2 120,395.00 130,473.75
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 m2 107,684.50 116,616.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 m2 109,224.50 118,442.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

16 A.4.4.1.16 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP m2 427,776.80 462,551.10

17 A.4.4.1.17 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP m2 436,566.90 472,626.55

18 A.4.4.1.18 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP m2 337,107.10 364,396.45

530032289.xls 249/48 HARGA SATUAN PEKERJAAN


19 A.4.4.1.19 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP m2 343,332.00 371,552.50

20 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP m2 270,785.90 298,130.80

21 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP m2 275,928.95 303,982.53

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 370,397.50 475,530.00
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 370,397.50 475,530.00
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 153,070.50 163,036.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 m2 316,081.04 341,319.06
Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 m2 316,655.24 339,901.71
Mortar Siap Pakai

Memasang rollag bata merah 1 Pc : 5 Ps , tiap 1 m' (1


27 DHAN m2 218,455.00 238,325.00
lapis bata)

Memasang dinding Bataco press (40 x 19 x 9) tiap 1m²,


28 DHAN m2 164,838.30 184,036.60
spesi 1:4

29 DHAN Memasang dinding Roster beton 20 x 20 x 7 tiap 1m² m2 390,073.75 484,840.13

30 DHAN Memasang dinding Roster beton 20 x 20 x 7 tiap 1 bh bh 17,087.51 21,027.77

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 79,304.06 85,538.42

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 74,120.86 80,342.02

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 72,146.14 78,398.98

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 70,577.10 76,820.70

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 69,989.26 76,269.82

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 69,391.74 75,684.18

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 69,158.54 75,470.78

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 68,925.34 75,257.38

9 A.4.4.2.9 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm m2 68,809.40 75,039.80

530032289.xls 249/49 HARGA SATUAN PEKERJAAN


10 A.4.4.2.10 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm m2 68,596.00 75,003.50

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 63,987.00 69,993.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 65,131.00 71,313.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 99,227.48 107,555.36

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 74,088.20 80,207.40

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 94,377.80 102,724.60


16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 93,718.68 102,125.76

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 92,797.32 101,209.24

530032289.xls 249/50 HARGA SATUAN PEKERJAAN


Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 90,453.00 98,890.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 43,275.76 46,927.32

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 72,484.50 78,691.25
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 m' 109,851.50 119,707.50
mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 109,851.50 119,707.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 54,101.30 59,093.10

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 30,925.62 33,662.09
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 14,696.00 15,983.00
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 m2 66,215.60 72,065.95
2Pp

27 A.4.4.2.27 Pemasangan Acian m2 39,916.25 43,525.63

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 48,358.20 52,226.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 42,240.00 45,938.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 115,921.50 125,653.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 118,107.00 128,139.00

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 141,656.50 164,088.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 144,122.00 164,197.00


5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 60 x 60 cm m2 344,437.50 391,039.00

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 70,896.10 79,796.20

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 41,696.60 45,275.45

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 244,082.85 295,865.08

9 A.4.4.3.33 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm m2 249,527.85 303,290.08

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 245,443.18 288,601.41


530032289.xls 249/51 HARGA SATUAN PEKERJAAN
11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 244,167.50 286,213.50
12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 244,865.50 284,740.50

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 467,395.50 524,821.00
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 43,121.10 46,952.95

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 90,063.60 98,377.95

530032289.xls 249/52 HARGA SATUAN PEKERJAAN


16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 90,063.60 98,377.95
17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 714,222.85 736,943.08

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 208,488.50 222,139.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 473,467.50 538,587.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 279,250.16 310,953.57

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 271,194.00 325,635.75

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 266,013.00 312,974.75

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 271,194.00 325,635.75

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 267,223.00 314,602.75


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 820,690.26 853,427.36

26 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 286,371.25 306,219.38

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 156,534.40 169,185.50

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 126,401.00 135,905.00


29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 58,806.00 63,019.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 193,184.75 215,430.05

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 257,199.25 276,568.05

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 205,405.75 227,651.05

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 263,309.75 282,678.55

Memasang lantai keramik Km/WC (anti slip) ukuran 20


34 HIT SNI m2 230,963.70 268,247.65
x 20 cm Asia/KIA/Milan tiap 1 m²

35 HIT SNI Memasang Plint Keramik Ukuran 10x20 cm m2 55,947.10 60,070.45


Memasang dinding keramik ukuran 30 x 60 cm
36 HIT SNI m2 368,093.00 393,318.75
Asia/KIA/Milan tiap 1 m²
37 HIT SNI Memasang lantai marmer tiap 1 m² m2 723,065.75 750,712.88

38 HIT SNI Memasang dinding batu tempel palimanan tiap 1m² m2 164,628.75 181,726.88

39 HIT SNI Memasang dinding batu Candi tiap 1m² m2 271,713.75 296,126.88

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 m2 32,708.50 39,380.00
mm, 5 mm & 6 mm

2 A.4.5.1.2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm m2 107,783.50 119,889.00

3 A.4.5.1.3 Pemasangan Langit-langit Akustik Ukuran (30x60) cm m2 110,396.00 121,082.50

4 A.4.5.1.4 Pemasangan Langit-langit Akustik Ukuran (60x120) cm m2 95,480.00 104,472.50

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 52,607.50 57,051.50
Tebal 3 mm, 4 mm & 6 mm

530032289.xls 249/53 HARGA SATUAN PEKERJAAN


Memasang Langit-langit Lambriziring Kayu Jati, tebal 6
6 A.4.5.1.6 m2 663,932.50 699,358.00
mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 43,741.50 48,765.20
(120x240) tebal 9 mm

Memasang Langit-langit Akuatik Uk (60x120) cm &


8 A.4.5.1.8 m2 235,152.50 256,217.50
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 18,414.00 19,838.50

10 DHAN Memasang langit-langit GRC-board 4 mm tiap 1m² m2 44,775.50 46,656.50

11 DHAN Memasang langit-langit Calsiboard 4 mm tiap 1m² m2 44,775.50 46,656.50


Memasang List langit-langit Gypsum/GRC/Calsiboard
12 HIT m2 36,261.50 37,449.50
profil tiap 1m'
Memasang langit-langit Gypsumboard 9 mm lengkap
13 DHAN m2 176,835.39 183,589.39
dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Memasang langit-langit GRC-board 4 mm lengkap dgn
14 DHAN m2 165,397.10 182,766.10
rangka hollow tebal 0.6 mm / tiap 1 m²

15 DHAN Memasang List langit-langit PVC profil tiap 1m' m' 46,103.75 47,951.75

Memasang langit-langit PVC SHUNDA lengkap dgn


16 DHAN m2 308,077.00 314,831.00
rangka hollow tebal 0.6 mm / tiap 1 m²

Memasang langit-langit GRC-board 4 mm lengkap dgn


17 DHAN m2 165,397.10 173,691.10
rangka hollow tebal 0.6 mm / tiap 1 m²

530032289.xls 249/54 HARGA SATUAN PEKERJAAN


HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 90,172.50 101,068.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 143,869.00 149,270.00

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 127,974.00 135,575.00

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 114,598.00 123,266.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 126,973.00 136,741.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 130,823.00 139,821.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 108,130.00 120,488.50


Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5
8 A.4.5.2.8 m2 67,375.00 75,383.00
mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5


9 A.4.5.2.9 m2 69,019.50 77,357.50
mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 m2 69,349.50 78,017.50
mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 m2 76,609.50 80,855.50
mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 m2 59,642.00 75,520.50
mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4


13 A.4.5.2.13 m2 61,759.50 77,753.50
mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 m2 59,779.50 76,169.50
mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 m2 60,489.00 75,146.50
mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 m2 64,069.50 78,105.50
mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 m2 69,030.50 72,440.50
mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 m2 72,385.50 75,905.50
mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 m2 69,217.50 73,265.50
mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 m2 70,229.50 74,442.50
mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 m2 74,134.50 77,984.50
mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 113,822.50 127,039.00

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 230,576.50 256,201.00

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 95,755.00 110,605.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 120,659.00 132,308.00

530032289.xls 249/55 HARGA SATUAN PEKERJAAN


26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 136,317.50 148,973.00
27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 137,362.50 147,411.00

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 73,645.00 81,405.50

29 A.4.5.2.38 Pemasangan Nok Sirap m' 63,552.50 69,619.00

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 42,273.00 47,091.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 35,431.00 39,171.00


32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 37,125.00 42,933.00
Memasang atap genteng beton Monier Warna spesial
33 SNI m2 154,385.00 166,375.00
tiap 1m²
34 DHAN Memasang atap genteng Kodok/Vlam tiap 1m² m2 95,744.00 114,895.00
Memasang atap Bumbung genteng Kodok/Vlam tiap 1
35 SNI m' 37,114.00 39,985.00
m'
36 DHAN Pasang kerpus Genteng Beton warna spesial tiap m m2 83,710.00 95,150.00

37 HIT Memasang atap galvalum warna tiap 1 m2 m2 154,363.00 175,395.00


38 HIT Memasang nok atap galvalum warna tiap 1 m' m' 78,144.00 80,718.00
39 HIT Pasang Atap Metalroof warna m2 118,717.50 122,138.50
40 HIT Pasang Nok Atap Metalroof warna m2 85,222.50 89,380.50

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 34,101,237.50 35,655,125.00
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 14,394,462.50 14,954,500.00
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard Kayu


3 A.4.6.1.3 m2 574,502.50 595,683.00
Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 574,502.50 595,683.00
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 928,262.50 980,925.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu


6 A.4.6.1.6 m2 669,625.00 713,020.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu


7 A.4.6.1.7 m2 2,522,850.00 2,645,225.00
Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 m2 699,545.00 761,931.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 759,764.50 827,002.00
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 2,255,880.00 2,357,217.50
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood Rangkap,


11 A.4.6.1.11 m2 1,282,022.50 1,372,294.00
Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 m2 814,055.00 882,909.50
Lapis Formika, Rangka expose Kayu Klas II

530032289.xls 249/56 HARGA SATUAN PEKERJAAN


Pembuatan&Memasang Konstruksi Kuda-kuda
13 A.4.6.1.13 m3 12,681,900.00 13,122,505.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 36,988,792.50 38,636,592.50
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 11,760,210.00 12,122,825.00

Pemasangan Rangka Atap Genteng Keramik, Kayu Klas


16 A.4.6.1.16 m2 192,654.00 199,028.50
II

530032289.xls 249/57 HARGA SATUAN PEKERJAAN


17 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II m2 225,918.00 233,084.50

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 163,471.00 169,499.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 m2 215,198.50 224,801.50
Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 220,489.50 230,153.00
Klas II atau III

21 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II m' 374,412.50 389,922.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 m' 146,080.00 150,892.50
klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 343,392.50 356,818.00
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 412,582.50 449,548.00
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 421,932.50 459,305.00
Rangka Kayu Klas II

26 A.4.6.1.26 Pemasangan Dinding Lambriziring dari Papan Kelas I m2 545,545.00 582,175.00

Pemasangan Dinding Lambriziring dari Plywood ukuran


27 A.4.6.1.27 m2 43,219.00 46,645.50
(120x240) cm

28 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV m2 129,689.34 144,821.60

Pembuatan & pasang pintu panel isian multiplek 9 mm


29 BUKU m2 740,850.00 820,605.50
rangka kamper tiap 1m²

Pembuatan & pasang pintu panel isian multiplek 9 mm


30 SNI bh 1,244,628.00 1,378,617.24
rangka kamper tiap 1m²

Memasang pintu teakwood dan formika, rangka Kayu


31 SNI m2 764,797.00 826,958.00
Kamper Samarinda oven tiap 1m²

32 SNI Membuat Jalusi mati Kosen Kayu kamper tiap 1 m2 m2 341,302.50 366,272.50

Memasang Konstruksi Kuda-kuda/Gording kayu kruing


33 SNI m3 10,332,850.00 10,899,625.00
tiap 1 m3

Memasang Konstruksi rangka atap beton kayu kruing


34 SNI m2 128,205.00 132,302.50
tiap 1 m2

Memasang Konstruksi rangka atap genteng vlam/kodok


35 SNI m2 113,905.00 117,342.50
kayu kruing tiap 1 m2

36 HIT Pasang Usuk/Kaso Kayu Kruing 5/7 m2 84,513.00 88,126.50

Memasang Rangka Langit-langit (1,00x1,00) m, kayu


37 SNI m2 129,662.50 138,517.50
Klas III (meranti) tiap 1m2

38 SNI Memasang lisplank (3 x 30) cm Kayu bengkirai tiap 1m' m' 167,860.00 172,287.50

39 SNI Memasang lisplank (3 x 20) cm Kayu bengkirai tiap 1m' m' 123,970.00 127,770.50

530032289.xls 249/58 HARGA SATUAN PEKERJAAN


40 HIT Memasang lisplank Woodplank 0,9 x 30 tiap 1 m' m' 72,407.50 77,330.00

41 HIT Memasang lisplank Woodplank 0,9 x 20 tiap 1 m' m' 63,332.50 68,255.00

Memasang Papan Reuters (3x20) Kayu bengkirai tiap


42 HIT m' 132,233.75 133,454.75
1m'

Pasang dinding partisi double tripleks 6 mm rangka


43 DHAN m2 359,548.75 377,025.00
kruing tiap 1 m2

44 HIT Pek. Balok Bulat Kayu Ulin (HR) m3 27,641,460.00 27,756,300.00

HIT Pek. Papan Kayu Ulin (HR) m3 24,239,847.50 24,243,422.50

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 212,107.50 261,882.50

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 172,053.75 238,191.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 210,553.75 260,191.25


4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 32,711.25 36,423.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 21,257.50 24,282.50

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 56,828.75 75,754.25

7 A.4.6.2.9 Pemasangan Kait Angin Buah 43,780.00 48,598.00

8 A.4.6.2.10 Pasang Door Closer Buah 380,943.75 470,071.25

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 40,177.50 45,028.50

10 A.4.6.2.13 Pemasangan Door Stop Buah 318,188.75 402,014.25

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 314,132.50 360,585.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 44,728.75 50,793.05


13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 126,383.13 140,471.38

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 138,483.13 152,571.38

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 356,283.13 418,771.38

16 LS Memasang Grendel pintu Buah 9,680.00 12,100.00

17 LS Memasang Grendel Jendela Buah 8,470.00 9,075.00

18 LS Memasang Grendel Pintu tanam Buah 27,225.00 30,250.00

19 LS Memasang Grendel jendela handle Ps 32,670.00 33,275.00

20 LS Memasang Engsel kait (KISMEN) 16 " Ps 72,600.00 72,600.00

21 LS Memasang Engsel kait (KISMEN) 18 " Ps 47,190.00 47,190.00


22 SNI Memasang Kaca rayband tebal 5 mm tiap 1 m2 m2 132,433.13 152,571.38

530032289.xls 249/59 HARGA SATUAN PEKERJAAN


530032289.xls 249/60 HARGA SATUAN PEKERJAAN
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama m2 15,977.50 17,770.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 15,950.00 17,770.50
dicat

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 m2 16,637.50 18,513.00
manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 m2 45,001.00 51,887.00
dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 m2 63,327.00 72,336.00
dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 37,933.50 40,188.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 59,603.50 63,955.10

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 11,783.75 13,046.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 45,545.50 49,615.50

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2


10 A.4.7.1.10 m2 22,257.40 25,230.70
Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 15,467.10 17,306.30
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 9,824.10 10,728.30

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 17,512.55 19,488.15

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 7,757.75 8,720.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 89,883.75 101,351.25

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 32,364.75 36,154.25

17 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah m2 63,236.25 70,303.75

18 HIT Mengecat atap genteng 3 lps tiap 1 m² m2 38,247.00 39,182.00

19 DHAN Mengecat waterproofing (coating) tiap 1 m² m2 27,139.75 28,080.25

Melapis Waterproffing dak beton dengan bahan aspal


20 HIT m2 38,260.61 42,926.84
( 2 lapis aspal )

Mengecat permukaan Plafond 3 lapis (1 lapis dasar, 2


21 HIT SNI m2 20,934.65 22,846.45
lapis penutup) tiap 1 m²

22 DHAN Mengecat permukaan besi/baja 3 Lapis tiap 1 m2 m2 37,281.75 42,391.25

Mengecat pemukaan besi dengan cat zinchromate tiap


23 DHAN m2 25,786.75 33,415.25
1 m2

Mengecat pemukaan tembok luar lama dengan cat


24 HIT m2 35,366.65 36,772.45
Weathershiel 2 lapis penutup

530032289.xls 249/61 HARGA SATUAN PEKERJAAN


HARGA SATUAN PEKERJAAN SANITASI
XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,359,643.00 2,701,314.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 511,280.00 559,185.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 770,880.00 831,325.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 613,470.00 667,260.00

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,107,562.50 1,183,495.50


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,360,700.00 1,484,450.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,672,154.27 1,826,638.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,582,616.47 7,509,989.28

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 351,422.50 394,047.50

10 A.5.1.1.14 Pemasangan Floor Drain buah 54,807.50 64,432.50

530032289.xls 249/62 HARGA SATUAN PEKERJAAN


Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi
11 A.5.1.1.15 bh 494,258.12 539,627.13
35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi


12 A.5.1.1.16 bh 727,947.62 792,803.13
50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 bh 868,210.90 947,679.45
60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 66,271.33 69,672.17

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 45,229.25 114,714.88

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 77,638.00 81,038.83

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 108,896.33 113,718.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 145,696.83 151,959.50

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 2" m' 257,599.83 265,299.83

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 460,779.00 467,200.25

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 24,552.00 26,974.75


22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 27,109.50 29,319.13

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 31,798.25 37,204.75

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 34,838.83 40,533.17

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 38,817.17 50,479.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 63,840.33 83,458.83

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 89,342.00 93,327.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20


28 A.5.1.1.33 m' 83,897.00 91,173.50
cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 m' 40,221.50 45,259.50
cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 118,929.80 135,615.98

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 584,848.00 626,351.00


Membuat saluran air buis beton ½ Ø 20 cm dinding bata
32 DHAN m' 164,451.98 166,949.15
dalam 15-25 cm tiap 1 m'
Memasang pintu alumunium Km/Wc +handle+Slot (+
33 LS Unit 1,540,000.00 1,540,000.00
Kosen)
34 LS Memasang Kozyn dan pintu PVC Km/Wc Unit 495,000.00 495,000.00
Membuat tandon air Kap 5.100 m3 dengan rangka
LS Unit 25,086,866.31 23,006,242.10
beton
Membuat 1 unit tanki septik sederhana kapasitas Vol.
35 LS Unit 3,569,017.13 3,950,999.91
0,9 m3
Membuat 1 unit tanki septik sederhana kapasitas Vol. 2
36 HIT Unit 5,478,146.62 6,006,913.62
m3
Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m
37 DHAN Unit 968,543.95
(digali 1,9 m) kap. 0,5 m³
Memasang shower lengkap EX AER/WASHER unit 500,000.00 500,027.50

Memasang Jet shower lengkap EX AER/WASHER Unit 150,000.00 150,027.50

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 385,880.00 431,508.00

530032289.xls 249/63 HARGA SATUAN PEKERJAAN


2 A.8.4.6.2 Pemasangan MCB buah 488,840.00 536,448.00
Pasang instalasi lampu tiap 1 titik (termasuk fitting dan
3 LS Titik 217,387.50 249,122.50
sakelar)
Pasang instalasi stop kontak tiap 1 titik (termasuk stop
4 LS Titik 201,437.50 259,462.50
kontak)
5 LS Pasang Fuse box sekering 1 group tiap 1 unit Unit 148,500.00 181,500.00

6 LS Pasang Fuse box sekering 2 group tiap 1 unit Unit 269,500.00 308,000.00
Pasang instalasi stop AC tiap 1 titik (termasuk stop
Titik 255,461.25 288,708.75
kontak)
7 LS Pasang Fuse box sekering 3 group tiap 1 unit Unit 385,000.00 434,500.00

8 LS Pasang Arde tiap 1 unit Unit 88,000.00 88,000.00


Rehab instalasi stop kontak tiap 1 titik (termasuk Stop
9 LS Unit 93,500.00 93,500.00
kontak)
Rehab instalasi lampu tiap 1 titik (termasuk fiting dan
10 LS Unit 93,500.00 93,500.00
Saklar)

11 LS Pasang kabel NYM 3 x 4 mm tiap m' Unit 35,200.00 39,600.00

12 LS Memasang Lampu Esensial 18 Watt Buah 46,200.00 46,200.00

LS Pasang AC 1/2 PK Daikin 1 unit Unit 4,000,596.88 4,206,778.13

LS Pasang AC 1 PK Daikin 1 unit Unit 5,574,971.88 5,925,528.13


Pasang AC 1. 1/2 PK Daikin 1 unit Unit 8,000,440.94 8,113,386.88

XVI PEKERJAAN JALAN DAN LINGKUNGAN

1 Pekerjaan macadam tebal 20 cm tiap 1 m2 m2 135,685.00 162,415.00


Penyiapan badan jalan / tanah dasar (Subgrade) tiap
2 m2 4,862.00 5,226.76
1m²
3 Urugan sirtu (agregat kelas C) dipadatkan tiap 1m³ m2 246,645.30 278,361.05
Lapis Pondasi Atas (LPA / Base Course) Agregat Kelas
4 m3 474,617.00 548,586.06
A ( Batu pecah 2/3 + pasir) tiap 1m³
Lapis Pondasi Jalan Tanpa Penutup Aspal jenis
5 m3 432,377.00 523,242.06
Waterbound Macadam (batu pecah 5/7) tiap 1m³
6 Lapis Resap Ikat (Prime Coat) tiap 1 Liter / 1 m2 Ltr 13,514.92 14,333.98
7 Lapis Perekat (Tack Coat) tiap 1 Liter / 1 m2 Ltr 14,606.12 15,460.38

8 Aspal untuk Pelaburan tiap 1 Liter x 4,5 untuk 4,5 m2 Ltr 9,705.03 10,936.75

Lapisan Penetrasi (LAPEN) / Lapisan Permukaan


9 Ltr 82,711.75 96,106.45
(Surface Course) Macadam tebal 5 cm tiap 1m²

Pembuatan jalan aspal biasa (Sirtu t=10 cm, Agregat


10 m2 191,464.46 220,765.38
Kelas A t=20 cm, Permukaan Macadam t=5 cm) tiap m²

11 Pembuatan jalan aspal biasa lebar 3 m' tiap 1 m' m' 574,393.38 662,296.14

12 Pembuatan jalan aspal biasa lebar 4 m' tiap 1 m' m' 765,857.84 883,061.52

13 Pembuatan jalan aspal biasa lebar 5 m' tiap 1 m' m' 957,322.30 1,103,826.90

14 Pembuatan jalan aspal biasa lebar 6 m' tiap 1 m' m' 1,148,786.76 1,324,592.28

15 Pembuatan jalan aspal biasa lebar 8 m' tiap 1 m' m' 1,531,715.68 1,766,123.04

Membentuk badan jalan /Subgrade dengan Timbunan


16 m3 307,175.37 399,621.34
(Menggunakan alat)

530032289.xls 249/64 HARGA SATUAN PEKERJAAN


Membentuk badan jalan /didaerah galian tanah biasa
17 m3 62,427.48 66,745.30
(Menggunakan alat)
18 Pemadatan tanah dasar (Menggunakan buruh) m2 2,347.92 2,602.31

19 Pemadatan tanah dasar (Menggunakan alat) m2 1,405.26 1,465.76

20 Membentuk bahu jalan keras (Menggunakan Alat) m3 296,544.88 16,272.44


21 Membentuk bahu jalan keras (Menggunakan Buruh) m3 348,246.48 384,241.46
Konstruksi lapis Pondasi Bawah (LPB) kelas A
22 m3 350,288.90 420,376.20
(menggunakan alat)

Konstruksi lapis Pondasi Bawah (LPB) kelas B


23 m3 294,519.19 333,937.74
(menggunakan alat)

Konstruksi lapis Pondasi Bawah (LPB) kelas C


24 m3 335,422.27 352,335.50
(menggunakan alat)
Konstruksi lapis Pondasi Bawah (LPB) kelas C
25 m3 393,871.61 421,930.21
(menggunakan buruh)

Konstruksi lapis Pondasi Bawah (LPB) TELFORD


26 m3 490,670.13 582,114.50
(menggunakan buruh)

Konstruksi lapis Pondasi Atas (LPA) Kelas A


27 m3 319,564.16 343,169.43
(menggunakan Alat)

Konstruksi lapis Pondasi Atas (LPA) Kelas B


28 m3 307,941.33 323,979.33
(menggunakan Alat)

Konstruksi lapis Pondasi Atas (LPA) Kelas B


29 m3 365,478.67 388,886.67
(menggunakan Buruh)

Menghampar Lapisan Pondasi Atas Aspal beton


30 m3 1,796,002.66 1,845,345.72
(LASTON ATAS) (menggunakan Alat)

31 Laburan Aspal Pasir (BURAS) (menggunakan Alat) m3 19,905.19 21,753.75

Memasang paving blok parkir kendaraan (warna abu T-


32 16 uk. 8x10,5x21) + urugan sirtu 20 cm + urugan pasir m2 224,966.50 241,793.20
5 cm tiap m²

Memasang paving blok jalan setapak (warna abu T-16


33 uk. 8x10,5x21) + urugan sirtu 10 cm + urugan pasir 5 m2 192,736.50 207,693.20
cm tiap m2
34 Memasang kanstin beton tiap 1 m' m' 69,139.13 78,841.54

XVII PEKERJAAN JALAN DAN LINGKUNGAN

Pekerjaan Lemari Backdrop / 1 m2 m2 3,200,000.00


Pekerjaan Backdrop dinding / 1 m2 m2 1,527,400.00
Pasang skat kaca rangka stainless tiap m² m2 2,257,000.00
Pekerjaan Meja Staf Menyatu / 1 m2 m2 1,811,000.00

XVI A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA

1 A.8.4.1.1 Pemasangan Pipa PVC Ø 63 mm m' 13,215.95 14,803.25

2 A.8.4.1.2 Pemasangan Pipa PVC Ø 90 mm m' 20,685.50 22,903.10

3 A.8.4.1.3 Pemasangan Pipa PVC Ø 110 mm m' 24,266.00 26,697.00

4 A.8.4.1.4 Pemasangan Pipa PVC Ø 150 mm m' 42,179.50 48,409.90

5 A.8.4.1.5 Pemasangan Pipa PVC Ø 200 mm m' 67,045.00 73,180.80


530032289.xls 249/65 HARGA SATUAN PEKERJAAN
6 A.8.4.1.6 Pemasangan Pipa PVC Ø 250 mm m' 118,789.00 127,498.80
7 A.8.4.1.7 Pemasangan Pipa PVC Ø 300 mm m' 166,512.50 185,520.50

530032289.xls 249/66 HARGA SATUAN PEKERJAAN


8 A.8.4.1.8 Pemasangan Pipa PVC Ø 400 mm m' 338,140.00 372,636.00
9 A.8.4.1.9 Pemasangan Pipa PVC Ø 450 mm m' 503,811.00 543,312.00

10 A.8.4.1.10 Pemasangan Pipa PVC Ø 500 mm m' 418,418.00 438,431.40

11 A.8.4.1.11 Pemasangan Pipa PVC Ø 600 mm m' 487,822.50 526,960.50

12 A.8.4.1.12 Pemasangan Pipa PVC Ø 800 mm m' 688,297.50 744,826.50

13 A.8.4.1.13 Pemasangan Pipa PVC Ø 900 mm m' 918,285.50 976,127.90

14 A.8.4.1.14 Pemasangan Pipa PVC Ø 1.000 mm m' 1,061,692.50 1,117,702.30

15 A.8.4.1.15 Pemasangan Pipa PVC Ø 1.100 mm m' 1,166,500.50 1,259,168.90

16 A.8.4.1.16 Pemasangan Pipa PVC Ø 1.200 mm m' 1,249,297.50 1,345,622.30

17 A.8.4.1.17 Pemasangan Pipa HDPE Ø 63 mm m' 32,318.00 38,464.80


18 A.8.4.1.18 Pemasangan Pipa HDPE Ø 100 mm m' 44,099.00 50,344.80

19 A.8.4.1.19 Pemasangan Pipa HDPE Ø 125 mm m' 55,880.00 62,224.80

20 A.8.4.1.20 Pemasangan Pipa HDPE Ø 150 mm m' 80,041.50 86,672.30

21 A.8.4.1.21 Pemasangan Pipa HDPE Ø 200 mm m' 134,931.50 147,766.30

22 A.8.4.1.22 Pemasangan Pipa HDPE Ø 250 mm m' 166,903.00 174,838.40

23 A.8.4.1.23 Pemasangan Pipa HDPE Ø 300 mm m' 199,622.50 213,757.50

24 A.8.4.1.24 Pemasangan Pipa HDPE Ø 400 mm m' 260,749.50 277,187.90

25 A.8.4.1.25 Pemasangan Pipa HDPE Ø 450 mm m' 314,638.50 332,403.50

26 A.8.4.1.26 Pemasangan Pipa HDPE Ø 500 mm m' 391,022.50 421,186.70


27 A.8.4.1.27 Pemasangan Pipa HDPE Ø 600 mm m' 545,347.00 577,031.40

28 A.8.4.1.28 Pemasangan Pipa HDPE Ø 800 mm m' 841,549.50 886,018.10

29 A.8.4.1.29 Pemasangan Pipa HDPE Ø 900 mm m' 1,017,049.00 1,097,806.60

30 A.8.4.1.30 Pemasangan Pipa HDPE Ø 1.000 mm m' 1,225,636.50 1,284,746.10

31 A.8.4.1.31 Pemasangan Pipa HDPE Ø 1.100 mm m' 1,358,252.50 1,447,902.50

32 A.8.4.1.32 Pemasangan Pipa HDPE Ø 1.200 mm m' 1,546,781.50 1,646,978.30

33 A.8.4.1.33 Pemasangan Pipa GIP Ø 63 mm m' 76,631.50 85,442.50

34 A.8.4.1.34 Pemasangan Pipa GIP Ø 100 mm m' 91,483.33 104,940.00

35 A.8.4.1.35 Pemasangan Pipa GIP Ø 125 mm m' 118,140.00 130,610.33


36 A.8.4.1.36 Pemasangan Pipa GIP Ø 150 mm m' 139,727.50 152,304.17

37 A.8.4.1.37 Pemasangan Pipa GIP Ø 200 mm m' 189,805.00 207,485.67

38 A.8.4.1.38 Pemasangan Pipa GIP Ø 250 mm m' 236,107.67 267,483.33

39 A.8.4.1.39 Pemasangan Pipa GIP Ø 300 mm m' 265,695.83 288,975.50

40 A.8.4.1.40 Pemasangan Pipa GIP Ø 400 mm m' 347,545.00 413,790.67

41 A.8.4.1.41 Pemasangan Pipa GIP Ø 450 mm m' 303,231.50 338,035.50

42 A.8.4.1.42 Pemasangan Pipa GIP Ø 500 mm m' 352,011.00 388,872.00

43 A.8.4.1.43 Pemasangan Pipa GIP Ø 600 mm m' 354,898.50 389,262.50

44 A.8.4.1.44 Pemasangan Pipa GIP Ø 800 mm m' 533,544.00 585,497.00


45 A.8.4.1.45 Pemasangan Pipa GIP Ø 900 mm m' 606,468.50 674,635.50

530032289.xls 249/67 HARGA SATUAN PEKERJAAN


46 A.8.4.1.46 Pemasangan Pipa GIP Ø 1.000 mm m' 678,298.50 740,536.50
47 A.8.4.1.47 Pemasangan Pipa GIP Ø 1.100 mm m' 739,200.00 806,520.00

48 A.8.4.1.48 Pemasangan Pipa GIP Ø 1.200 mm m' 811,030.00 883,421.00

49 A.8.4.1.49 Pemasangan Pipa DCI Ø 100 mm m' 78,512.50 91,092.10

50 A.8.4.1.50 Pemasangan Pipa DCI Ø 125 mm m' 100,969.00 114,373.60

51 A.8.4.1.51 Pemasangan Pipa DCI Ø 150 mm m' 129,811.00 149,661.60

52 A.8.4.1.52 Pemasangan Pipa DCI Ø 200 mm m' 176,770.00 200,074.60

53 A.8.4.1.53 Pemasangan Pipa DCI Ø 250 mm m' 208,851.50 233,557.50

54 A.8.4.1.54 Pemasangan Pipa DCI Ø 300 mm m' 233,398.00 258,469.20

55 A.8.4.1.55 Pemasangan Pipa DCI Ø 400 mm m' 348,606.50 384,446.70


56 A.8.4.1.56 Pemasangan Pipa DCI Ø 450 mm m' 408,864.50 444,469.30

57 A.8.4.1.57 Pemasangan Pipa DCI Ø 500 mm m' 465,146.00 511,010.50

58 A.8.4.1.58 Pemasangan Pipa DCI Ø 600 mm m' 525,332.50 590,132.40

59 A.8.4.1.59 Pemasangan Pipa DCI Ø 800 mm m' 787,902.50 874,104.00

60 A.8.4.1.60 Pemasangan Pipa DCI Ø 900 mm m' 925,248.50 1,030,536.10

61 A.8.4.1.61 Pemasangan Pipa DCI Ø 1.000 mm m' 1,106,396.50 1,226,385.60

62 A.8.4.1.62 Pemasangan Pipa DCI Ø 1.100 mm m' 1,237,087.50 1,381,773.80

63 A.8.4.1.63 Pemasangan Pipa DCI Ø 1.200 mm m' 1,400,668.50 1,564,211.00

64 A.8.4.1.64 Pemasangan Baja PVC Ø 63 mm m' 64,872.50 73,120.30


65 A.8.4.1.65 Pemasangan Pipa Baja Ø 100 mm m' 73,694.50 84,736.30

66 A.8.4.1.66 Pemasangan Pipa Baja Ø 125 mm m' 83,611.00 95,092.80

67 A.8.4.1.67 Pemasangan Pipa Baja Ø 150 mm m' 95,315.00 110,954.80

68 A.8.4.1.68 Pemasangan Pipa Baja Ø 200 mm m' 148,137.00 169,562.80

69 A.8.4.1.69 Pemasangan Pipa Baja Ø 250 mm m' 192,104.00 222,065.80

70 A.8.4.1.70 Pemasangan Pipa Baja Ø 300 mm m' 223,300.00 249,037.80

71 A.8.4.1.71 Pemasangan Pipa Baja Ø 400 mm m' 334,235.00 371,869.30

72 A.8.4.1.72 Pemasangan Pipa Baja Ø 450 mm m' 350,355.50 393,479.90

73 A.8.4.1.73 Pemasangan Pipa Baja Ø 500 mm m' 399,767.50 462,297.00


74 A.8.4.1.74 Pemasangan Pipa Baja Ø 600 mm m' 436,452.50 490,267.80

75 A.8.4.1.75 Pemasangan Pipa Baja Ø 800 mm m' 695,464.00 779,158.60

76 A.8.4.1.76 Pemasangan Pipa Baja Ø 900 mm m' 797,714.50 882,436.50

77 A.8.4.1.77 Pemasangan Pipa Baja Ø 1.000 mm m' 913,286.00 1,011,390.60

78 A.8.4.1.78 Pemasangan Pipa Baja Ø 1.100 mm m' 1,021,537.00 1,126,752.00

79 A.8.4.1.79 Pemasangan Pipa Baja Ø 1.200 mm m' 1,131,069.50 1,243,592.90

530032289.xls 249/68 HARGA SATUAN PEKERJAAN


HARGA SATUAN PEKERJAAN PEMOTONGAN
XVII A.8.4.2
PIPA
1 A.8.4.2.1 Pemotongan Pipa PVC Ø 63 mm bh 647.90 737.00

2 A.8.4.2.2 Pemotongan Pipa PVC Ø 90 mm bh 1,868.90 2,117.50

3 A.8.4.2.3 Pemotongan Pipa PVC Ø 110 mm bh 2,968.90 3,360.50


4 A.8.4.2.4 Pemotongan Pipa PVC Ø 150 mm bh 4,140.40 4,686.00

5 A.8.4.2.5 Pemotongan Pipa PVC Ø 200 mm bh 11,001.10 12,457.50

6 A.8.4.2.6 Pemotongan Pipa PVC Ø 250 mm bh 17,534.00 19,855.00

7 A.8.4.2.7 Pemotongan Pipa PVC Ø 300 mm bh 21,104.60 23,903.00

8 A.8.4.2.8 Pemotongan Pipa PVC Ø 400 mm bh 45,400.30 51,419.50

9 A.8.4.2.9 Pemotongan Pipa PVC Ø 450 mm bh 58,080.00 65,769.00

10 A.8.4.2.10 Pemotongan Pipa PVC Ø 500 mm bh 71,720.00 81,218.50

11 A.8.4.2.11 Pemotongan Pipa PVC Ø 600 mm bh 86,229.00 97,658.00

12 A.8.4.2.12 Pemasangan Pipa PVC Ø 800 mm bh 151,206.00 171,259.00


13 A.8.4.2.13 Pemotongan Pipa PVC Ø 900 mm bh 158,411.00 179,421.00

14 A.8.4.2.14 Pemotongan Pipa PVC Ø 1.000 mm bh 178,513.50 202,191.00

15 A.8.4.2.15 Pemotongan Pipa PVC Ø 1.100 mm bh 198,478.50 224,807.00

16 A.8.4.2.16 Pemotongan Pipa PVC Ø 1.200 mm bh 218,471.00 247,456.00

17 A.8.4.2.17 Pemotongan Pipa HDPE Ø 63 mm bh 4,119.50 4,550.70

18 A.8.4.2.18 Pemotongan Pipa HDPE Ø 100 mm bh 8,800.00 9,718.50

19 A.8.4.2.19 Pemotongan Pipa HDPE Ø 125 mm bh 12,001.00 13,255.00

20 A.8.4.2.20 Pemotongan Pipa HDPE Ø 150 mm bh 15,757.50 17,424.00

21 A.8.4.2.21 Pemotongan Pipa HDPE Ø 200 mm bh 25,162.50 27,907.00


22 A.8.4.2.22 Pemotongan Pipa HDPE Ø 250 mm bh 33,951.50 37,686.00

23 A.8.4.2.23 Pemotongan Pipa HDPE Ø 300 mm bh 42,762.50 47,492.50

24 A.8.4.2.24 Pemotongan Pipa HDPE Ø 400 mm bh 66,154.00 73,650.50

25 A.8.4.2.25 Pemotongan Pipa HDPE Ø 450 mm bh 78,661.00 87,648.00

26 A.8.4.2.26 Pemotongan Pipa HDPE Ø 500 mm bh 87,983.50 97,966.00

27 A.8.4.2.27 Pemotongan Pipa HDPE Ø 600 mm bh 110,478.50 123,178.00

28 A.8.4.2.28 Pemotongan Pipa HDPE Ø 800 mm bh 170,758.50 190,806.00

29 A.8.4.2.29 Pemotongan Pipa HDPE Ø 900 mm bh 226,176.50 253,302.50

30 A.8.4.2.30 Pemotongan Pipa HDPE Ø 1.000 mm bh 267,426.50 299,722.50


31 A.8.4.2.31 Pemotongan Pipa HDPE Ø 1.100 mm bh 294,690.00 330,269.50

32 A.8.4.2.32 Pemotongan Pipa HDPE Ø 1.200 mm bh 360,046.50 404,041.00

33 A.8.4.2.33 Pemotongan Pipa GIP Ø 63 mm bh 2,623.50 2,964.50

34 A.8.4.2.34 Pemotongan Pipa GIP Ø 100 mm bh 7,837.50 8,860.50

35 A.8.4.2.35 Pemotongan Pipa GIP Ø 125 mm bh 12,375.00 13,992.00

36 A.8.4.2.36 Pemotongan Pipa GIP Ø 150 mm bh 17,693.50 20,003.50

530032289.xls 249/69 HARGA SATUAN PEKERJAAN


37 A.8.4.2.37 Pemotongan Pipa GIP Ø 200 mm bh 45,815.00 51,799.00
38 A.8.4.2.38 Pemotongan Pipa GIP Ø 250 mm bh 63,899.00 72,248.00

39 A.8.4.2.39 Pemotongan Pipa GIP Ø 300 mm bh 67,870.00 76,736.00

40 A.8.4.2.40 Pemotongan Pipa GIP Ø 400 mm bh 99,467.50 112,458.50

41 A.8.4.2.41 Pemotongan Pipa GIP Ø 450 mm bh 114,290.00 129,217.00

42 A.8.4.2.42 Pemotongan Pipa GIP Ø 500 mm bh 126,841.00 143,407.00

43 A.8.4.2.43 Pemotongan Pipa GIP Ø 600 mm bh 116,380.00 131,582.00

44 A.8.4.2.44 Pemotongan Pipa GIP Ø 800 mm bh 211,134.00 238,711.00

45 A.8.4.2.45 Pemotongan Pipa GIP Ø 900 mm bh 238,507.50 269,659.50

46 A.8.4.2.46 Pemotongan Pipa GIP Ø 1.000 mm bh 265,952.50 300,690.50


47 A.8.4.2.47 Pemotongan Pipa GIP Ø 1.100 mm bh 293,287.50 331,600.50

48 A.8.4.2.48 Pemotongan Pipa GIP Ø 1.200 mm bh 320,952.50 362,873.50

49 A.8.4.2.49 Pemotongan Pipa DCI Ø 100 mm bh 7,342.50 8,361.10

50 A.8.4.2.50 Pemotongan Pipa DCI Ø 125 mm bh 11,627.00 13,244.00

51 A.8.4.2.51 Pemotongan Pipa DCI Ø 150 mm bh 16,670.50 18,987.10

52 A.8.4.2.52 Pemotongan Pipa DCI Ø 200 mm bh 38,461.50 43,816.30

53 A.8.4.2.53 Pemotongan Pipa DCI Ø 250 mm bh 50,044.50 57,014.10

54 A.8.4.2.54 Pemotongan Pipa DCI Ø 300 mm bh 53,746.00 61,234.80

55 A.8.4.2.55 Pemotongan Pipa DCI Ø 400 mm bh 99,005.50 112,806.10


56 A.8.4.2.56 Pemotongan Pipa DCI Ø 450 mm bh 119,493.00 136,138.20

57 A.8.4.2.57 Pemotongan Pipa DCI Ø 500 mm bh 137,709.00 156,886.40

58 A.8.4.2.58 Pemotongan Pipa DCI Ø 600 mm bh 137,709.00 156,886.40

59 A.8.4.2.59 Pemotongan Pipa DCI Ø 800 mm bh 272,107.00 309,947.00

60 A.8.4.2.60 Pemotongan Pipa DCI Ø 900 mm bh 352,649.00 401,678.20

61 A.8.4.2.61 Pemotongan Pipa DCI Ø 1.000 mm bh 420,590.50 479,057.70

62 A.8.4.2.62 Pemotongan Pipa DCI Ø 1.100 mm bh 494,719.50 563,482.70

63 A.8.4.2.63 Pemotongan Pipa DCI Ø 1.200 mm bh 575,179.00 655,118.20

64 A.8.4.2.64 Pemotongan pipa Baja Ø 63 mm bh 4,180.00 4,790.50


65 A.8.4.2.65 Pemotongan Pipa Baja Ø 100 mm bh 10,054.00 11,484.00

66 A.8.4.2.66 Pemotongan Pipa Baja Ø 125 mm bh 15,147.00 17,281.00

67 A.8.4.2.67 Pemotongan Pipa Baja Ø 150 mm bh 20,487.50 23,364.00

68 A.8.4.2.68 Pemotongan Pipa Baja Ø 200 mm bh 51,221.50 58,360.50

69 A.8.4.2.69 Pemotongan Pipa Baja Ø 250 mm bh 70,807.00 80,663.00

70 A.8.4.2.70 Pemotongan Pipa Baja Ø 300 mm bh 79,354.00 90,398.00

71 A.8.4.2.71 Pemotongan Pipa Baja Ø 400 mm bh 152,361.00 173,530.50

72 A.8.4.2.72 Pemotongan Pipa Baja Ø 450 mm bh 143,929.50 163,867.00

73 A.8.4.2.73 Pemotongan Pipa Baja Ø 500 mm bh 154,682.00 176,214.50


74 A.8.4.2.74 Pemotongan Pipa Baja Ø 600 mm bh 164,890.00 187,797.50

530032289.xls 249/70 HARGA SATUAN PEKERJAAN


75 A.8.4.2.75 Pemotongan Pipa Baja Ø 800 mm bh 276,776.50 315,210.50
76 A.8.4.2.76 Pemotongan Pipa Baja Ø 900 mm bh 313,208.50 356,697.00

77 A.8.4.2.77 Pemotongan Pipa Baja Ø 1.000 mm bh 349,849.50 398,420.00

78 A.8.4.2.78 Pemotongan Pipa Baja Ø 1.100 mm bh 386,353.00 439,989.00

79 A.8.4.2.79 Pemotongan Pipa Baja Ø 1.200 mm bh 422,994.00 481,712.00

HARGA SATUAN PEKERJAAN PEMASANGAN


XVIII A.8.4.3
AKSESORIS PIPA

1 A.8.4.3.1 Pemasangan Valve Ø 150 mm bh 248,721.00 290,598.00

2 A.8.4.3.2 Pemasangan Valve Ø 200 mm bh 316,717.50 364,039.50


3 A.8.4.3.3 Pemasangan Valve Ø 250 mm m' 372,817.50 414,859.50

4 A.8.4.3.4 Pemasangan Valve Ø 300 mm bh 440,000.00 498,300.00

5 A.8.4.3.5 Pemasangan Valve Ø 400 mm bh 775,621.00 865,678.00

6 A.8.4.3.6 Pemasangan Valve Ø 450 mm bh 830,621.00 920,678.00

7 A.8.4.3.7 Pemasangan Valve Ø 500 mm bh 962,500.00 1,062,600.00

8 A.8.4.3.8 Pemasangan Valve Ø 600 mm bh 715,121.00 775,555.00

9 A.8.4.3.9 Pemasangan Valve Ø 700 mm bh 830,621.00 889,878.00

10 A.8.4.3.10 Pemasangan Valve Ø 800 mm bh 933,707.50 1,004,745.50

11 A.8.4.3.11 Pemasangan Valve Ø 900 mm bh 1,022,917.50 1,098,729.50


12 A.8.4.3.12 Pemasangan Valve Ø 1.000 mm bh 1,237,483.50 1,317,937.50

13 A.8.4.3.13 Pemasangan Valve Ø 1.100 mm bh 1,350,250.00 1,438,250.00

14 A.8.4.3.14 Pemasangan Valve Ø 1.200 mm bh 1,383,250.00 1,482,250.00

15 A.8.4.3.15 Pemasangan Tee Ø 150 mm bh 27,835.50 33,067.10

16 A.8.4.3.16 Pemasangan Tee Ø 200 mm bh 45,969.00 55,338.80

17 A.8.4.3.17 Pemasangan Tee Ø 250 mm bh 71,901.50 83,229.30

18 A.8.4.3.18 Pemasangan Tee Ø 300 mm bh 102,795.00 117,073.00

19 A.8.4.3.19 Pemasangan Tee Ø 400 mm bh 143,440.00 161,590.00

20 A.8.4.3.20 Pemasangan Tee Ø 450 mm bh 180,262.50 200,348.50


21 A.8.4.3.21 Pemasangan Tee Ø 500 mm bh 207,185.00 229,427.00

22 A.8.4.3.22 Pemasangan Tee Ø 600 mm bh 264,693.00 297,523.60

23 A.8.4.3.23 Pemasangan Tee Ø 700 mm bh 319,495.00 351,142.00

24 A.8.4.3.24 Pemasangan Tee Ø 800 mm bh 363,132.00 404,573.40

25 A.8.4.3.25 Pemasangan Tee Ø 900 mm bh 420,761.00 466,919.20

26 A.8.4.3.26 Pemasangan Tee Ø 1.000 mm bh 476,531.00 527,144.20

27 A.8.4.3.27 Pemasangan Tee Ø 1.100 mm bh 530,046.00 584,795.20

28 A.8.4.3.28 Pemasangan Tee Ø 1.200 mm bh 587,675.00 647,141.00

530032289.xls 249/71 HARGA SATUAN PEKERJAAN


HARGA SATUAN PEKERJAAN PENYAMBUNGAN
XIX A.8.4.4
PIPA BARU KE PIPA LAMA

Penyambungan Pipa Baru ke Pipa yang ada Ø 80


1 A.8.4.4.1 bh 424,242.50 500,054.50
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 100


2 A.8.4.4.2 bh 510,251.50 579,894.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 150


3 A.8.4.4.3 bh 738,116.50 826,245.20
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 200


4 A.8.4.4.4 bh 932,981.50 1,050,595.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 250


5 A.8.4.4.5 bh 1,100,346.50 1,230,946.20
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 300


6 A.8.4.4.6 bh 1,256,711.50 1,400,296.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 400


7 A.8.4.4.7 bh 1,569,441.50 1,749,997.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 450


8 A.8.4.4.8 bh 1,731,306.50 1,930,348.20
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 500


9 A.8.4.4.9 bh 1,904,171.50 2,121,698.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 600


10 A.8.4.4.10 bh 2,216,901.50 2,471,399.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 700


11 A.8.4.4.11 bh 2,562,631.50 2,854,100.70
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø 800


12 A.8.4.4.11 bh 2,864,361.50 3,203,801.70
mm

XX A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN


1 A.8.4.5.1 Pengetesan Pipa Ø 50 mm m' 1,283.98 1,417.08

2 A.8.4.5.2 Pengetesan Pipa Ø 75 mm m' 1,284.25 1,417.35

3 A.8.4.5.3 Pengetesan Pipa Ø 100 mm m' 1,284.80 1,417.90

4 A.8.4.5.4 Pengetesan Pipa Ø 150 mm m' 1,286.18 1,419.28

5 A.8.4.5.5 Pengetesan Pipa Ø 200 mm m' 1,287.96 1,421.06

6 A.8.4.5.6 Pengetesan Pipa Ø 250 mm m' 1,290.44 1,423.54

7 A.8.4.5.7 Pengetesan Pipa Ø 300 mm m' 1,293.46 1,426.56

8 A.8.4.5.8 Pengetesan Pipa Ø 400 mm m' 1,301.03 1,434.13

9 A.8.4.5.9 Pengetesan Pipa Ø 500 mm m' 1,305.43 1,438.53


10 A.8.4.5.10 Pengetesan Pipa Ø 600 mm m' 1,322.61 1,455.71

530032289.xls 249/72 HARGA SATUAN PEKERJAAN


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : Kota Semarang
EDISI II 2019

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
A.2.2.1.2 1 m' 705,963.50 757,501.25
1 2,00 m
A TENAGA 71,100.00 77,500.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.4 OH Tukang Kayu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.02 OH Mandor 125,000.00 135,000.00 2,500.00 2,700.00
B BAHAN 570,685.00 611,137.50
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portalnd Semen 1,150.00 1,175.00 2,875.00 2,937.50
1.2 Lbr Seng Gelombang 3" - 5" 47,000.00 55,000.00 56,400.00 66,000.00
0.005 m3 Pasir Beton 360,000.00 380,000.00 1,800.00 1,900.00
0.009 m3 Koral Beton 340,000.00 380,000.00 3,060.00 3,420.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 6,500,000.00 6,800,000.00 468,000.00 489,600.00
0.06 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 1,050.00 1,080.00
0.45 Kg Meni Besi 25,000.00 36,000.00 11,250.00 16,200.00
C PERALATAN
D Jumlah A + B + C 641,785.00 688,637.50
E Overhead & Profit (contah 10%) 10% 64,178.50 68,863.75
F Harga Satuan Pekerjaan (D+E) 705,963.50 757,501.25
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 176,082.50 185,498.50
A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 137,150.00 143,560.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 6,500,000.00 6,800,000.00 78,000.00 81,600.00
0.02 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 350.00 360.00
0.007 m3 Kayu Papan 3/20 Kruing 8,400,000.00 8,800,000.00 58,800.00 61,600.00
C PERALATAN
D Jumlah A + B + C 160,075.00 168,635.00
E Overhead & Profit (contah 10%) 10% 16,007.50 16,863.50
F Harga Satuan Pekerjaan (D+E) 176,082.50 185,498.50

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 2,260,500.00 2,408,037.50

A Tenaga 585,250.00 638,750.00


L.01 2 OH Pekerja 90,000.00 100,000.00 180,000.00 200,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.02 1 OH Tukang Batu 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.3 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,469,750.00 1,550,375.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 26,250.00 30,000.00
0.18 m3 Kayu 6,500,000.00 6,800,000.00 1,170,000.00 1,224,000.00
0.80 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 14,000.00 14,400.00
1.1 Kg Besi Strip 14,000.00 14,250.00 15,400.00 15,675.00
35 Kg Portland Sement 1,150.00 1,175.00 40,250.00 41,125.00
0.15 m3 Pasir pasang 340,000.00 370,000.00 51,000.00 55,500.00
0.1 m3 Pasir Beton 360,000.00 380,000.00 36,000.00 38,000.00
0.15 m3 Koral Beton 340,000.00 380,000.00 51,000.00 57,000.00
30 buah Batu bata Merah 580.00 625.00 17,400.00 18,750.00
0.25 Lbr Seng Plat 22,000.00 24,500.00 5,500.00 6,125.00
0.20 buah Jendela Naco 37,500.00 40,000.00 7,500.00 8,000.00
0.08 m2 Kaca Polos 85,000.00 95,000.00 6,800.00 7,600.00
0.15 buah Kunci Tanam 165,000.00 200,000.00 24,750.00 30,000.00
0.06 Lbr Plywood 4 mm 65,000.00 70,000.00 3,900.00 4,200.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 2,055,000.00 2,189,125.00
E Overhead & Profit (contah 10%) 10% 205,500.00 218,912.50
F Harga Satuan Pekerjaan (D+E) 2,260,500.00 2,408,037.50

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,774,575.00 1,887,215.00


A Tenaga 295,750.00 322,750.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 1.50 OH Tukang Kayu 120,000.00 130,000.00 180,000.00 195,000.00
L.03 0.15 OH Kepala Tukang 130,000.00 140,000.00 19,500.00 21,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,317,500.00 1,392,900.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
0.18 m3 Kayu 6,500,000.00 6,800,000.00 1,170,000.00 1,224,000.00
0.80 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 14,000.00 14,400.00
1.50 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,613,250.00 1,715,650.00
E Overhead & Profit (contah 10%) 10% 161,325.00 171,565.00
F Harga Satuan Pekerjaan (D+E) 1,774,575.00 1,887,215.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,674,007.50 1,766,118.75


A Tenaga 362,250.00 394,750.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.2 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,516,325.00 1,599,437.50
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.21 m3 Kayu 6,500,000.00 6,800,000.00 1,365,000.00 1,428,000.00
0.3 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 5,250.00 5,400.00
10.5 Kg Portland Semen 1,150.00 1,175.00 12,075.00 12,337.50
0.03 m3 Pasir Beton 360,000.00 380,000.00 10,800.00 11,400.00
0.05 m3 Koral Beton 340,000.00 380,000.00 17,000.00 19,000.00
1.5 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
0.25 Lbr Seng Plat 22,000.00 24,500.00 5,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,521,825.00 1,605,562.50
E Overhead & Profit (contah 10%) 10% 152,182.50 160,556.25
F Harga Satuan Pekerjaan (D+E) 1,674,007.50 1,766,118.75

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 2,012,725.00 2,152,975.00


A Tenaga 362,250.00 394,750.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.2 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,467,500.00 1,562,500.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
0.186 m3 Kayu 6,500,000.00 6,800,000.00 1,209,000.00 1,264,800.00
0.30 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 5,250.00 5,400.00
18.00 Kg Portland Semen 1,150.00 1,175.00 20,700.00 21,150.00
0.03 m3 Pasir Beton 360,000.00 380,000.00 10,800.00 11,400.00
0.05 m3 Koral Beton 340,000.00 380,000.00 17,000.00 19,000.00
1.50 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
1.35 Lbr Playwood 80,000.00 95,000.00 108,000.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,829,750.00 1,957,250.00
E Overhead & Profit (contah 10%) 10% 182,975.00 195,725.00
F Harga Satuan Pekerjaan (D+E) 2,012,725.00 2,152,975.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 16,775.00 18,425.00


A Tenaga 15,250.00 16,750.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 15,250.00 16,750.00
E Overhead & Profit (contah 10%) 10% 1,525.00 1,675.00
F Harga Satuan Pekerjaan (D+E) 16,775.00 18,425.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 416,407.20 460,448.12


A Tenaga 362,250.00 394,750.00
L.01 1.00 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 2.00 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.20 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 16,302.00 23,839.20
1.250 Btg Bambu diameter 6 - 8 / 600 cm 12,000.00 18,000.00 15,000.00 22,500.00
0.186 Kg Tali Ijuk 7,000.00 7,200.00 1,302.00 1,339.20
C PERALATAN
D Jumlah A + B + C 378,552.00 418,589.20
E Overhead & Profit (contah 10%) 10% 37,855.20 41,858.92
F Harga Satuan Pekerjaan (D+E) 416,407.20 460,448.12

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 635,470.00 666,864.00
40cmx50cmx25cm
A Tenaga 39,900.00 43,200.00
L.02 0.30 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.03 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
B Bahan 537,800.00 563,040.00
0.036 m3 Kayu Papan Kelas III 8,400,000.00 8,800,000.00 302,400.00 316,800.00
0.036 m3 Kayu Balok Kelas III 6,500,000.00 6,800,000.00 234,000.00 244,800.00
0.080 kg Paku Biasa 17,500.00 18,000.00 1,400.00 1,440.00
C PERALATAN
D Jumlah A + B + C 577,700.00 606,240.00
E Overhead & Profit (contah 10%) 10% 57,770.00 60,624.00
F Harga Satuan Pekerjaan (D+E) 635,470.00 666,864.00

10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 178,337.50 202,262.50


A Tenaga 90,625.00 100,675.00

L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00

L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00


B. Bahan 71,500.00 83,200.00

0.150 m3 Batu Belah 280,000.00 320,000.00 42,000.00 48,000.00

0.090 m3 Batu Pecah 290,000.00 350,000.00 26,100.00 31,500.00


0.010 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00

C PERALATAN
D Jumlah A + B + C 162,125.00 183,875.00
E Overhead & Profit (contah 10%) 10% 16,212.50 18,387.50
F Harga Satuan Pekerjaan (D+E) 178,337.50 202,262.50

11 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,411,641.00 1,565,641.00


A Tenaga 1,283,310.00 1,423,310.00
L.01 13.334 OH Pekerja 90,000.00 100,000.00 1,200,060.00 1,333,400.00
L.04 0.666 OH Mandor 125,000.00 135,000.00 83,250.00 89,910.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,283,310.00 1,423,310.00
E Overhead & Profit (contah 10%) 10% 128,331.00 142,331.00
F Harga Satuan Pekerjaan (D+E) 1,411,641.00 1,565,641.00

12 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 664,570.50 738,270.50


A Tenaga 604,155.00 671,155.00
L.01 6.667 OH Pekerja 90,000.00 100,000.00 600,030.00 666,700.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan
C PERALATAN
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
D Jumlah A + B + C 604,155.00 671,155.00
E Overhead & Profit (contah 10%) 10% 60,415.50 67,115.50
F Harga Satuan Pekerjaan (D+E) 664,570.50 738,270.50

13 A.2.2.1.15 1 m2 Pagar Kawat Jaring Galvanis Panjang 240 cm 59,646.40 63,002.50


A Tenaga 9,770.00 10,670.00

L.01 0.042 OH Pekerja 90,000.00 100,000.00 3,780.00 4,200.00


L.02 0.004 OH Tukang Kayu 120,000.00 130,000.00 480.00 520.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.042 OH Mandor 125,000.00 135,000.00 5,250.00 5,670.00
B Bahan 44,454.00 46,605.00

0.1434 Lbr Kawat Jaring 310,000 325,000 44,454.00 46,605.00


C PERALATAN
D Jumlah A + B + C 54,224.00 57,275.00
E Overhead & Profit (contah 10%) 10% 5,422.40 5,727.50
F Harga Satuan Pekerjaan (D+E) 59,646.40 63,002.50

Pemasangan Pagar Panel Beton Pracetak 5 x 50 x


14 A.2.2.1.16 1 m2 296,741.50 327,822.00
240 cm
A Tenaga 52,685.00 57,995.00
L.01 0.375 OH Pekerja 90,000.00 100,000.00 33,750.00 37,500.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.019 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00
B Bahan 217,080.00 240,025.00
0.986 Lbr Panel Beton Pracetak 65,000.00 75,000.00 64,090.00 73,950.00
0.525 Btg Kolom Beton Pracetak 140,000.00 160,000.00 73,500.00 84,000.00
45.000 Kg Semen (SM) 1,150.00 1,175.00 51,750.00 52,875.00
0.146 m3 Koral 190,000.00 200,000.00 27,740.00 29,200.00
C PERALATAN
D Jumlah A + B + C 269,765.00 298,020.00
E Overhead & Profit (contah 10%) 10% 26,976.50 29,802.00
F Harga Satuan Pekerjaan (D+E) 296,741.50 327,822.00

Pengukuran dan pemasangan Bauplank (kayu


15 Rev SNI 1 m' 176,082.50 185,498.50
Kruing) tiap 1 m'
A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 137,150.00 143,560.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 6,500,000.00 6,800,000.00 78,000.00 81,600.00
0.020 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 350.00 360.00
0.007 m3 Kayu Papan 3/20 Kruing 8,400,000.00 8,800,000.00 58,800.00 61,600.00
- -
C PERALATAN
D Jumlah A + B + C 160,075.00 168,635.00
E Overhead & Profit (contah 10%) 10% 16,007.50 16,863.50
F Harga Satuan Pekerjaan (D+E) 176,082.50 185,498.50

Pengukuran dan pemasangan Bauplank (kayu


16 HIT SNI 1 m' 77,335.50 82,428.50
kampung/Lanan) tiap 1 m'
A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 47,380.00 49,860.00
0.012 m3 Kayu 5/7x 4m Kayu Lanan 2,000,000.00 2,200,000.00 24,000.00 26,400.00
0.020 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 350.00 360.00
0.007 m3 Kayu Papan 3/20 Lanan 3,290,000.00 3,300,000.00 23,030.00 23,100.00
- -
C PERALATAN
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
D Jumlah A + B + C 70,305.00 74,935.00
E Overhead & Profit (contah 10%) 10% 7,030.50 7,493.50
F Harga Satuan Pekerjaan (D+E) 77,335.50 82,428.50
17 Rev SNI 1 m3 Bongkaran Beton Bertulang 1,411,641.00 1,565,641.00
A Tenaga 1,283,310.00 1,423,310.00
L.01 13.334 OH Pekerja 90,000.00 100,000.00 1,200,060.00 1,333,400.00
L.04 0.666 OH Mandor 125,000.00 135,000.00 83,250.00 89,910.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,283,310.00 1,423,310.00
E Overhead & Profit (contah 10%) 10% 128,331.00 142,331.00
F Harga Satuan Pekerjaan (D+E) 1,411,641.00 1,565,641.00
18 DHAN 1 m2 Bongkaran plesteran tiap 1 m2 5,293.75 5,871.25
A Tenaga 4,812.50 5,337.50
L.01 0.050 OH Pekerja 90,000.00 100,000.00 4,500.00 5,000.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan
C PERALATAN
D Jumlah A + B + C 4,812.50 5,337.50
E Overhead & Profit (contah 10%) 10% 481.25 533.75
F Harga Satuan Pekerjaan (D+E) 5,293.75 5,871.25
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 DHAN 1 m2 Bongkaran atap genteng tiap 1 m2 21,175.00 23,485.00
A Tenaga 19,250.00 21,350.00
L.01 0.200 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan
C PERALATAN
D Jumlah A + B + C 19,250.00 21,350.00
E Overhead & Profit (contah 10%) 10% 1,925.00 2,135.00
F Harga Satuan Pekerjaan (D+E) 21,175.00 23,485.00
20 DHAN 1 m2 Bongkaran atapasbes/seng tiap 1 m2 7,975.00 8,635.00
A Tenaga 7,250.00 7,850.00
- 0.050 OH TK Besi 120,000.00 130,000.00 6,000.00 6,500.00
- 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan
C PERALATAN
D Jumlah A + B + C 7,250.00 7,850.00
E Paku Biasa 2" - 5" 10% 725.00 785.00
F Harga Satuan Pekerjaan (D+E) 7,975.00 8,635.00
21 DHAN 1 m2 Bongkaran reng dan kaso tiap 1 m2 14,245.00 15,702.50
A Tenaga 12,950.00 14,275.00
L.02 0.025 OH Tk. Kayu 120,000.00 130,000.00 3,000.00 3,250.00
L.03 0.0025 OH Kep. Tk kayu 130,000.00 140,000.00 325.00 350.00
L.01 0.100 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00

B Bahan
C PERALATAN
D Jumlah A + B + C 12,950.00 14,275.00
E Pekerja 10% 1,295.00 1,427.50
F Harga Satuan Pekerjaan (D+E) 14,245.00 15,702.50
22 Rev SNI 1 m3 Bongkaran Rangka Kuda-kuda/Kusen kayu tiap 1 m3 159,500.00 172,700.00
A Tenaga 145,000.00 157,000.00
L.02 1.000 OH TK kayu 120,000.00 130,000.00 120,000.00 130,000.00
L.04 0.200 OH Mandor 125,000.00 135,000.00 25,000.00 27,000.00
B Bahan
C PERALATAN
D Jumlah A + B + C 145,000.00 157,000.00
E Pasir Beton 10% 14,500.00 15,700.00
F Harga Satuan Pekerjaan (D+E) 159,500.00 172,700.00
22 1 Ls Pembersihan lapangan - -

- Pembersihan lapangan
-
B Bahan
C PERALATAN
D Jumlah A + B + C - -
E PERALATAN 10% - -
F Harga Satuan Pekerjaan (D+E) - -
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

0.03
33.3
0.06

### ###
#REF! #REF!

0.2

0.2

2
0.08

###
#REF!

1075

0.05

0.5
2.4

0.06

72,666
1211100.78571 1296636.49471

72666.0471429 77798.1896825

0.15

0.4

2.2
0.132

159865.303714 171156.017302

140000 160000

140000 160000
0.06

### ###

0.06
### ###
0.06

### ###

0.06
### ###

0.06

### 8,910.00

0.06

### ###

0.06
### ###
KUANTI HARGA SAT. SUB TOTAL
NO. URAIAN SAT HSP (Rp)
TAS DASAR (Rp) (Rp)
1 2 3 4 5 6 7

1. Pekerjaan Lemari Backdrop / 1 m2


Harga bahan:
- Multiplek 18mm uk. 122 x 244cm lbr 2.10 332,500 698,250.00
- HPL 122 x 244cm lbr 4.10 185,000 758,500.00
- Engsel bh 4.00 43,150 172,600.00
- Lem Kuning Kg 1.70 53,700 91,290.00
- Lem Putih Kg 1.20 22,600 27,120.00
- Paku tembak doz 0.68 30,000 20,400.00
- Sekrup 4 cm biji 15.00 500 7,500.00
- Kertas gosok 80 lbr 0.50 2,500 1,250.00
- Kertas gosok 100 lbr 0.50 3,000 1,500.00
- Dempul kg 0.20 24,000 4,800.00
- Isolasi kertas m 1.00 1,000 1,000.00
- Stainlest m' 3.00 125,000 375,000.00
- Alat kerja 10% % 10.00 2,159,210 215,921.00

Jumlah Harga Bahan 2,375,131.00


Upah tenaga:
- Pekerja Interior Oh 1.00 140,000 140,000.00
- Tukang kayu interior Oh 2.00 150,000 300,000.00
- Kepala tukang interior Oh 0.50 160,000 80,000.00
- Mandor interior Oh 0.08 175,000 14,000.00
Jumlah Upah Tenaga 534,000.00
Jumlah Total 2,909,131.00
Jumlah Total + jasa 10% 3,200,000
2. Pekerjaan Backdrop dinding / 1 m2
Harga bahan:
- Multiplek 18mm 122 x 244cm lbr 0.42 332,500 139,650.00
- HPL 122 x 244cm lbr 0.70 185,000 129,500.00
- Lem Kuning Kg 1.50 53,700 80,550.00
- Lem Putih Kg 1.20 22,600 27,120.00
- Paku tembak doz 0.35 30,000 10,500.00
- Sekrup 4 cm biji 12.00 500 6,000.00
- Kertas gosok 80 lbr 0.50 2,500 1,250.00
- Kertas gosok 100 lbr 0.50 3,000 1,500.00
- Dempul kg 0.20 24,000 4,800.00
- Isolasi kertas m 1.00 1,000 1,000.00
- Stainlest m' 3.00 125,000 375,000.00
- Alat kerja 10% % 10.00 776,870 77,687.00

Jumlah Harga Bahan 854,557.00


Upah tenaga:
- Pekerja Interior Oh 1.00 140,000 140,000.00
- Tukang kayu interior Oh 2.00 150,000 300,000.00
- Kepala tukang interior Oh 0.50 160,000 80,000.00
- Mandor interior Oh 0.08 175,000 14,000.00
Jumlah Upah Tenaga 534,000.00
Jumlah Total 1,388,557.00
Jumlah Total + jasa 10% 1,527,400

3. Pasang skat kaca rangka stainless tiap m²


Harga bahan:
- Rangka stainless mirror tebal 1,2mm uk. 4x6 cm m' 3.00 403,000 1,209,000.00
- Kaca polos 10 mm m2 1.05 563,237 591,398.85
- Stiker Sunblast m2 1.05 150,000 157,500.00
- Paku Fisser dim. 6mm uk.7cm bh 2.00 14,750 29,500.00
- Sealant tube 0.75 35,875 26,906.25
- Sealant glass tube 0.20 56,400 11,280.00
Jumlah Harga Bahan 2,025,585.10
Upah tenaga:
- Pekerja Interior Oh 0.09 140,000 11,900.00
- Tukang kayu interior Oh 0.09 150,000 12,750.00
- Kepala tukang interior Oh 0.01 160,000 1,280.00
- Mandor interior Oh 0.00 175,000 700.00
Jumlah Upah Tenaga 26,630.00
Jumlah Total 2,052,215.10
Jumlah Total + jasa 10% 2,257,000

4. Pekerjaan Meja Staf Menyatu / 1 m2


Harga bahan:
- Multiplek 18mm 122 x 244cm lbr 0.42 362,500 152,250.00
- HPL 122 x 244cm lbr 0.70 250,000 175,000.00
- Lem Kuning Kg 1.50 53,700 80,550.00
- Lem Putih Kg 1.20 22,650 27,180.00
- Paku tembak doz 0.35 30,000 10,500.00
- Sekrup 4 cm biji 12.00 500 6,000.00
- Kertas gosok 80 lbr 0.50 2,500 1,250.00
- Kertas gosok 100 lbr 0.50 3,000 1,500.00
- Dempul kg 0.20 25,885 5,176.93
- Isolasi kertas m 1.00 1,000 1,000.00
- Stainlest m' 3.00 145,000 435,000.00
- Alat kerja 20% % 20.00 895,407 179,081.39

Jumlah Harga Bahan 1,074,488.32


Upah tenaga:
- Pekerja Interior Oh 1.00 150,000 150,000.00
- Tukang kayu interior Oh 2.00 160,000 320,000.00
- Kepala tukang interior Oh 0.50 175,000 87,500.00
- Mandor interior Oh 0.08 180,000 14,400.00
Jumlah Upah Tenaga 571,900.00
Jumlah Total 1,646,388.32
Jumlah Total + jasa 10% 1,811,000
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 77,687.50 86,212.50


A TENAGA 70,625.00 78,375.00
L.01 0.75 OH Pekerja 90,000.00 100,000.00 67,500.00 75,000.00
L.04 0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 70,625.00 78,375.00
E Overhead & Profit (contah 10%) 10% 7,062.50 7,837.50
F Harga Satuan Pekerjaan (D+E) 77,687.50 86,212.50
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 95,287.50 105,682.50
A TENAGA 86,625.00 96,075.00
L.01 0.90 OH Pekerja 90,000.00 100,000.00 81,000.00 90,000.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 86,625.00 96,075.00
E Overhead & Profit (contah 10%) 10% 8,662.50 9,607.50
F Harga Satuan Pekerjaan (D+E) 95,287.50 105,682.50

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 113,162.50 125,449.50


A TENAGA 102,875.00 114,045.00
L.01 1.05 OH Pekerja 90,000.00 100,000.00 94,500.00 105,000.00
L.04 0.067 OH Mandor 125,000.00 135,000.00 8,375.00 9,045.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 102,875.00 114,045.00
E Overhead & Profit (contah 10%) 10% 10,287.50 11,404.50
F Harga Satuan Pekerjaan (D+E) 113,162.50 125,449.50

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 103,400.00 114,752.00


TENAGA 94,000.00 104,320.00
L.01 1.000 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.04 0.032 OH Mandor 125,000.00 135,000.00 4,000.00 4,320.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 94,000.00 104,320.00
E Overhead & Profit (contah 10%) 10% 9,400.00 10,432.00
F Harga Satuan Pekerjaan (D+E) 103,400.00 114,752.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 156,750.00 173,910.00


A TENAGA 142,500.00 158,100.00
L.01 1.50 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.04 0.060 OH Mandor 125,000.00 135,000.00 7,500.00 8,100.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 142,500.00 158,100.00
E Overhead & Profit (contah 10%) 10% 14,250.00 15,810.00
F Harga Satuan Pekerjaan (D+E) 156,750.00 173,910.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 124,987.50 138,682.50


A TENAGA 113,625.00 126,075.00
L.01 1.200 OH Pekerja 90,000.00 100,000.00 108,000.00 120,000.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 113,625.00 126,075.00
E Overhead & Profit (contah 10%) 10% 11,362.50 12,607.50
F Harga Satuan Pekerjaan (D+E) 124,987.50 138,682.50

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 5,637.50 6,242.50


A TENAGA 5,125.00 5,675.00
L.01 0.05 OH Pekerja 90,000.00 100,000.00 4,500.00 5,000.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 5,125.00 5,675.00
E Overhead & Profit (contah 10%) 10% 512.50 567.50
F Harga Satuan Pekerjaan (D+E) 5,637.50 6,242.50

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 34,045.00 37,785.00


A TENAGA 30,950.00 34,350.00
L.01 0.330 OH Pekerja 90,000.00 100,000.00 29,700.00 33,000.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/86 PEK.TANAH


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 30,950.00 34,350.00
E Overhead & Profit (contah 10%) 10% 3,095.00 3,435.00
F Harga Satuan Pekerjaan (D+E) 34,045.00 37,785.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 18,791.67 20,808.33
Pekerjaan galian
A TENAGA 51,250.00 56,750.00
L.01 0.50 OH Pekerja 90,000.00 100,000.00 45,000.00 50,000.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 51,250.00 56,750.00
E Overhead & Profit (contah 10%) 10% 5,125.00 5,675.00
F Harga Satuan Pekerjaan (D+E) 56,375.00 62,425.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 56,375.00 62,425.00


A TENAGA 51,250.00 56,750.00
L.01 0.5 OH Pekerja 90,000.00 100,000.00 45,000.00 50,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 51,250.00 56,750.00
E Overhead & Profit (contah 10%) 10% 5,125.00 5,675.00
F Harga Satuan Pekerjaan (D+E) 56,375.00 62,425.00

11 A.2.3.1.11 1 m3 Urugan Pasir 242,275.00 324,885.00


A TENAGA 28,250.00 31,350.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 192,000.00 264,000.00
1.2 m3 Pasir Urug 160,000.00 220,000.00 192,000.00 264,000.00
C PERALATAN
D Jumlah A + B + C 220,250.00 295,350.00
E Overhead & Profit (contah 10%) 10% 22,025.00 29,535.00
F Harga Satuan Pekerjaan (D+E) 242,275.00 324,885.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 456,346.00 500,577.00


A TENAGA 135,200.00 148,400.00
L.01 0.800 OH Pekerja 90,000.00 100,000.00 72,000.00 80,000.00
L.02 0.400 OH Tukang Batu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.04 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00
L.04 0.080 OH Mandor 125,000.00 135,000.00 10,000.00 10,800.00
B BAHAN 279,660.00 306,670.00
0.135 m3 Pasir Pasang 340,000.00 370,000.00 45,900.00 49,950.00
0.400 m3 Kapur Padam 300,000.00 310,000.00 120,000.00 124,000.00
0.948 m3 Tanah Liat 120,000.00 140,000.00 113,760.00 132,720.00
C PERALATAN
D Jumlah A + B + C 414,860.00 455,070.00
E Overhead & Profit (contah 10%) 10% 41,486.00 45,507.00
F Harga Satuan Pekerjaan (D+E) 456,346.00 500,577.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 63,112.50 66,247.50
Resapan
A TENAGA 15,375.00 17,025.00
0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B BAHAN 42,000.00 43,200.00
6.00 kg Ijuk 7,000.00 7,200.00 42,000.00 43,200.00
C PERALATAN
D Jumlah A + B + C 57,375.00 60,225.00
E Overhead & Profit (contah 10%) 10% 5,737.50 6,022.50
F Harga Satuan Pekerjaan (D+E) 63,112.50 66,247.50

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 265,787.50 295,212.50


A TENAGA 25,625.00 28,375.00
L.01 0.25 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.04 0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B BAHAN 216,000.00 240,000.00
1.2 m3 Sirtu 180,000.00 200,000.00 216,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 241,625.00 268,375.00
E Overhead & Profit (contah 10%) 10% 24,162.50 26,837.50
F Harga Satuan Pekerjaan (D+E) 265,787.50 295,212.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/87 PEK.TANAH


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 1,088,257.50 1,202,217.50
A TENAGA 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 745,200.00 824,800.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
202 Kg Portland Sement 1,150.00 1,175.00 232,300.00 237,350.00
0.485 m3 Pasir Pasang 340,000.00 370,000.00 164,900.00 179,450.00
C PERALATAN
D Jumlah A + B + C 989,325.00 1,092,925.00
E Overhead & Profit (contoh 10%) 10% 98,932.50 109,292.50
F Harga Satuan Pekerjaan (D+E) 1,088,257.50 1,202,217.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 1,052,012.50 1,166,055.00
A TENAGA 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 712,250.00 791,925.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
163 Kg Portland Sement 1,150.00 1,175.00 187,450.00 191,525.00
0.52 m3 Pasir Pasang 340,000.00 370,000.00 176,800.00 192,400.00
C PERALATAN
D Jumlah A + B + C 956,375.00 1,060,050.00
E Overhead & Profit (contoh 10%) 10% 95,637.50 106,005.00
F Harga Satuan Pekerjaan (D+E) 1,052,012.50 1,166,055.00

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 1,026,833.50 1,140,925.50


A TENAGA 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 689,360.00 769,080.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
136 Kg Portland Sement 1,150.00 1,175.00 156,400.00 159,800.00
0.544 m3 Pasir Pasang 340,000.00 370,000.00 184,960.00 201,280.00
C PERALATAN
D Jumlah A + B + C 933,485.00 1,037,205.00
E Overhead & Profit (contoh 10%) 10% 93,348.50 103,720.50
F Harga Satuan Pekerjaan (D+E) 1,026,833.50 1,140,925.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 1,009,156.50 1,123,287.00


A TENAGA 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 673,290.00 753,045.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
117 Kg Portland Sement 1,150.00 1,175.00 134,550.00 137,475.00
0.561 m3 Pasir Pasang 340,000.00 370,000.00 190,740.00 207,570.00
C PERALATAN
D Jumlah A + B + C 917,415.00 1,021,170.00
E Overhead & Profit (contoh 10%) 10% 91,741.50 102,117.00
F Harga Satuan Pekerjaan (D+E) 1,009,156.50 1,123,287.00

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 984,868.50 1,099,043.00


A Tenaga 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 651,210.00 731,005.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
91 Kg Portland Sement 1,150.00 1,175.00 104,650.00 106,925.00
0.584 m3 Pasir Pasang 340,000.00 370,000.00 198,560.00 216,080.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/88 PEK.PONDASI


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 895,335.00 999,130.00
E Overhead & Profit (contoh 10%) 10% 89,533.50 99,913.00
F Harga Satuan Pekerjaan (D+E) 984,868.50 1,099,043.00

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 871,997.50 977,487.50
A Tenaga 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 548,600.00 620,500.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 340,000.00 370,000.00 115,600.00 125,800.00
C PERALATAN
D Jumlah A + B + C 792,725.00 888,625.00
E Overhead & Profit (contoh 10%) 10% 79,272.50 88,862.50
F Harga Satuan Pekerjaan (D+E) 871,997.50 977,487.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 961,020.50 1,072,951.00


A Tenaga 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 629,530.00 707,285.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
61 kg Portland Sement 1,150.00 1,175.00 70,150.00 71,675.00
0.147 m3 Kapur Pasang 300,000.00 310,000.00 44,100.00 45,570.00
0.492 m3 Pasir Pasang 340,000.00 370,000.00 167,280.00 182,040.00
C PERALATAN
D Jumlah A + B + C 873,655.00 975,410.00
E Overhead & Profit (contoh 10%) 10% 87,365.50 97,541.00
F Harga Satuan Pekerjaan (D+E) 961,020.50 1,072,951.00

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 942,034.50 1,054,262.00


A Tenaga 244,125.00 268,125.00
L.01 1.5 OH Pekerja 90,000.00 100,000.00 135,000.00 150,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 612,270.00 690,295.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
41 kg Portland Sement 1,150.00 1,175.00 47,150.00 48,175.00
0.131 m3 Kapur Pasang 300,000.00 310,000.00 39,300.00 40,610.00
0.523 m3 Pasir 340,000.00 370,000.00 177,820.00 193,510.00
C PERALATAN
D Jumlah A + B + C 856,395.00 958,420.00
E Overhead & Profit (contoh 10%) 10% 85,639.50 95,842.00
F Harga Satuan Pekerjaan (D+E) 942,034.50 1,054,262.00

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 598,471.50 706,711.50


A Tenaga 126,945.00 139,425.00
L.01 0.78 OH Pekerja 90,000.00 100,000.00 70,200.00 78,000.00
L.02 0.39 OH Tukang Batu 120,000.00 130,000.00 46,800.00 50,700.00
L.03 0.039 OH Kepala Tukang 130,000.00 140,000.00 5,070.00 5,460.00
L.04 0.039 OH Mandor 125,000.00 135,000.00 4,875.00 5,265.00
B Bahan 417,120.00 503,040.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
0.432 m3 Pasir Urug 160,000.00 220,000.00 69,120.00 95,040.00
C PERALATAN
D Jumlah A + B + C 544,065.00 642,465.00
E Overhead & Profit (contoh 10%) 10% 54,406.50 64,246.50
F Harga Satuan Pekerjaan (D+E) 598,471.50 706,711.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/89 PEK.PONDASI


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,548,854.00 2,928,244.00
3KR & 40% Batu Belah
A Tenaga 437,800.00 482,650.00
L.01 3.4 OH Pekerja 90,000.00 100,000.00 306,000.00 340,000.00
L.02 0.85 OH Tukang Batu 120,000.00 130,000.00 102,000.00 110,500.00
L.03 0.085 OH Kepala Tukang 130,000.00 140,000.00 11,050.00 11,900.00
L.04 0.15 OH Mandor 125,000.00 135,000.00 18,750.00 20,250.00
B Bahan 1,879,340.00 2,179,390.00
0.480 m3 Batu Belah 15/20 cm 290,000.00 340,000.00 139,200.00 163,200.00
126 Kg Besi Beton 10,000.00 12,000.00 1,260,000.00 1,512,000.00
194 Kg Portland Semen 1,150.00 1,175.00 223,100.00 227,950.00
0.312 m3 Pasir Beton 360,000.00 380,000.00 112,320.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
1.8 Kg Kawat Beton 18,000.00 20,000.00 32,400.00 36,000.00
C PERALATAN
D Jumlah A + B + C 2,317,140.00 2,662,040.00
E Overhead & Profit (contoh 10%) 10% 231,714.00 266,204.00
F Harga Satuan Pekerjaan (D+E) 2,548,854.00 2,928,244.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 1,007,066.50 1,091,700.50


A Tenaga 337,275.00 371,265.00
L.01 2.40 OH Pekerja 90,000.00 100,000.00 216,000.00 240,000.00
L.02 0.8 OH Tukang Batu 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.119 OH Mandor 125,000.00 135,000.00 14,875.00 16,065.00
B Bahan 578,240.00 621,190.00
0.45 m3 Batu Belah 15/20 cm 290,000.00 340,000.00 130,500.00 153,000.00
194 Kg Portland Semen 1,150.00 1,175.00 223,100.00 227,950.00
0.312 m3 Pasir Beton 360,000.00 380,000.00 112,320.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
C PERALATAN
D Jumlah A + B + C 915,515.00 992,455.00
E Overhead & Profit (contoh 10%) 10% 91,551.50 99,245.50
F Harga Satuan Pekerjaan (D+E) 1,007,066.50 1,091,700.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/90 PEK.PONDASI


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 1,054,814.36 1,131,401.07
= 0,87
A Tenaga 195,515.00 215,875.00
L.01 1.65 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 763,407.14 812,671.43
247 Kg Portland Semen 1,150.00 1,175.00 284,050.00 290,225.00
869 Kg Pasir Beton 257.14 271.43 223,457.14 235,871.43
999 Kg Kerikil (maksimum 30 mm) 251.85 281.48 251,600.00 281,200.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 958,922.14 1,028,546.43
E Overhead & Profit (contoh 10%) 10% 95,892.21 102,854.64
F Harga Satuan Pekerjaan (D+E) 1,054,814.36 1,131,401.07
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 1,083,503.70 1,160,667.33
= 0,78
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 789,488.36 839,277.12
276 Kg Portland Semen 1,150.00 1,175.00 317,400.00 324,300.00
828 kg Pasir Beton 257.14 271.43 212,914.29 224,742.86
1,012 kg Kerikil (maksimum 30 mm) 251.85 281.48 254,874.07 284,859.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 985,003.36 1,055,152.12
E Overhead & Profit (contoh 10%) 10% 98,500.34 105,515.21
F Harga Satuan Pekerjaan (D+E) 1,083,503.70 1,160,667.33

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 1,105,781.02 1,183,284.40
w/c = 0,72
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 809,740.48 859,838.10
299 Kg Portland Semen 1,150.00 1,175.00 343,850.00 351,325.00
799 kg Pasir Beton 257.14 271.43 205,457.14 216,871.43
1,017 kg Kerikil (maksimum 30 mm) 251.85 281.48 256,133.33 286,266.67
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,005,255.48 1,075,713.10
E Overhead & Profit (contoh 10%) 10% 100,525.55 107,571.31
F Harga Satuan Pekerjaan (D+E) 1,105,781.02 1,183,284.40

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 981,343.47 1,051,959.92
(3-6)cm, w/c = 0,87
A Tenaga 135,350.00 149,610.00
L.01 1.200 OH Pekerja 90,000.00 100,000.00 108,000.00 120,000.00
L.02 0.200 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 756,780.42 806,717.20
230 Kg Portland Semen 1,150.00 1,175.00 264,500.00 270,250.00
893 kg Pasir Beton 257.14 271.43 229,628.57 242,385.71
1,027 kg Kerikil (maksimum 30 mm) 251.85 281.48 258,651.85 289,081.48
200 ltr Air 20.00 25.00 4,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 892,130.42 956,327.20
E Overhead & Profit (contoh 10%) 10% 89,213.04 95,632.72
F Harga Satuan Pekerjaan (D+E) 981,343.47 1,051,959.92

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,132,229.04 1,210,253.17
w/c = 0,66
A Tenaga 195,515.00 215,875.00
L.01 1.65 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/91 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 833,784.13 884,355.16
326 Kg Portland Semen 1,150.00 1,175.00 374,900.00 383,050.00
760 Kg Pasir Beton 257.14 271.43 195,428.57 206,285.71
1,029 Kg Kerikil (maksimum 30 mm) 251.85 281.48 259,155.56 289,644.44
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,029,299.13 1,100,230.16
E Overhead & Profit (contoh 10%) 10% 102,929.91 110,023.02
F Harga Satuan Pekerjaan (D+E) 1,132,229.04 1,210,253.17

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,157,470.26 1,235,818.86
w/c = 0,61
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 856,730.69 907,596.69
352 Kg Portland Semen 1,150.00 1,175.00 404,800.00 413,600.00
731 Kg Pasir Beton 257.14 271.43 187,971.43 198,414.29
1,031 Kg Kerikil (maksimum 30 mm) 251.85 281.48 259,659.26 290,207.41
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,052,245.69 1,123,471.69
E Overhead & Profit (contoh 10%) 10% 105,224.57 112,347.17
F Harga Satuan Pekerjaan (D+E) 1,157,470.26 1,235,818.86

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,176,603.56 1,255,477.58
w/c = 0,58
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 874,124.60 925,468.25
371 Kg Portland Semen 1,150.00 1,175.00 426,650.00 435,925.00
698 Kg Pasir Beton 257.14 271.43 179,485.71 189,457.14
1,047 Kg Kerikil (maksimum 30 mm) 251.85 281.48 263,688.89 294,711.11
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,069,639.60 1,141,343.25
E Overhead & Profit (contoh 10%) 10% 106,963.96 114,134.33
F Harga Satuan Pekerjaan (D+E) 1,176,603.56 1,255,477.58

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,189,135.12 1,268,011.61
w/c = 0,56
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 885,516.93 936,862.83
384 Kg Portland Semen 1,150.00 1,175.00 441,600.00 451,200.00
692 Kg Pasir Beton 257.14 271.43 177,942.86 187,828.57
1,039 Kg Kerikil (maksimum 30 mm) 251.85 281.48 261,674.07 292,459.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,081,031.93 1,152,737.83
E Overhead & Profit (contoh 10%) 10% 108,103.19 115,273.78
F Harga Satuan Pekerjaan (D+E) 1,189,135.12 1,268,011.61

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,211,100.79 1,290,032.86
(12±2)cm, w/c = 0,53
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 905,485.71 956,882.14
406 Kg Portland Semen 1,150.00 1,175.00 466,900.00 477,050.00
684 kg Pasir Beton 257.14 271.43 175,885.71 185,657.14
1,026 kg Kerikil (maksimum 30 mm) 251.85 281.48 258,400.00 288,800.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,101,000.71 1,172,757.14
E Overhead & Profit (contoh 10%) 10% 110,100.07 117,275.71
F Harga Satuan Pekerjaan (D+E) 1,211,100.79 1,290,032.86

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/92 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,217,722.03 1,296,636.49
w/c = 0,52
A Tenaga 195,515.00 215,875.00
L.01 1.650 OH Pekerja 90,000.00 100,000.00 148,500.00 165,000.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 911,505.03 962,885.45
413 Kg Portland Semen 1,150.00 1,175.00 474,950.00 485,275.00
681 Kg Pasir Beton 257.14 271.43 175,114.29 184,842.86
1,021 Kg Kerikil (maksimum 30 mm) 251.85 281.48 257,140.74 287,392.59
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,107,020.03 1,178,760.45
E Overhead & Profit (contoh 10%) 10% 110,702.00 117,876.04
F Harga Satuan Pekerjaan (D+E) 1,217,722.03 1,296,636.49

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,301,821.04 1,386,882.76
w/c = 0,49
A Tenaga 248,675.00 274,575.00
L.01 2.1 OH Pekerja 90,000.00 100,000.00 189,000.00 210,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.105 OH Mandor 125,000.00 135,000.00 13,125.00 14,175.00
B Bahan 934,798.68 986,227.51
439 Kg Portland Semen 1,150.00 1,175.00 504,850.00 515,825.00
670 Kg Pasir Beton 257.14 271.43 172,285.71 181,857.14
1,006 Kg Kerikil (maksimum 30 mm) 251.85 281.48 253,362.96 283,170.37
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,183,473.68 1,260,802.51
E Overhead & Profit (contoh 10%) 10% 118,347.37 126,080.25
F Harga Satuan Pekerjaan (D+E) 1,301,821.04 1,386,882.76

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,310,695.25 1,395,761.77
w/c = 0,48
A Tenaga 248,675.00 274,575.00
L.01 2.10 OH Pekerja 90,000.00 100,000.00 189,000.00 210,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.105 OH Mandor 125,000.00 135,000.00 13,125.00 14,175.00
B Bahan 942,866.14 994,299.34
448 Kg Portland Semen 1,150.00 1,175.00 515,200.00 526,400.00
667 Kg Pasir Beton 257.14 271.43 171,514.29 181,042.86
1,000 Kg Kerikil (maksimum 30 mm) 251.85 281.48 251,851.85 281,481.48
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,191,541.14 1,268,874.34
E Overhead & Profit (contoh 10%) 10% 119,154.11 126,887.43
F Harga Satuan Pekerjaan (D+E) 1,310,695.25 1,395,761.77

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 136,191.00 161,282.00


A Tenaga 16,110.00 17,620.00
L.01 0.07 OH Pekerja 90,000.00 100,000.00 6,300.00 7,000.00
L.02 0.07 OH Tukang Besi 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 107,700.00 129,000.00
10.50 Kg Besi Beton (polos/ulir) 10,000.00 12,000.00 105,000.00 126,000.00
0.150 Kg Kawat Beton 18,000.00 20,000.00 2,700.00 3,000.00
C PERALATAN
D Jumlah A + B + C 123,810.00 146,620.00
E Overhead & Profit (contoh 10%) 10% 12,381.00 14,662.00
F Harga Satuan Pekerjaan (D+E) 136,191.00 161,282.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 176,357.50 183,540.50


A Tenaga 11,525.00 12,605.00
L.01 0.05 OH Pekerja 90,000.00 100,000.00 4,500.00 5,000.00
L.02 0.05 OH Tukang Besi 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 148,800.00 154,250.00
10.5 Kg Besi presstred polos 14,000.00 14,500.00 147,000.00 152,250.00
0.1 Kg Kawat Beton 18,000.00 20,000.00 1,800.00 2,000.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/93 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 160,325.00 166,855.00
E Overhead & Profit (contoh 10%) 10% 16,032.50 16,685.50
F Harga Satuan Pekerjaan (D+E) 176,357.50 183,540.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 287,688.50 316,431.50


A Tenaga 5,635.00 6,165.00
L.01 0.025 OH Pekerja 90,000.00 100,000.00 2,250.00 2,500.00
L.02 0.025 OH Tukang Besi 120,000.00 130,000.00 3,000.00 3,250.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 255,900.00 281,500.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 27,500.00 255,000.00 280,500.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 261,535.00 287,665.00
E Overhead & Profit (contoh 10%) 10% 26,153.50 28,766.50
F Harga Satuan Pekerjaan (D+E) 287,688.50 316,431.50

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 187,858.00 206,085.00


A Tenaga 84,630.00 92,950.00
L.01 0.52 OH Pekerja 90,000.00 100,000.00 46,800.00 52,000.00
L.02 0.26 OH Tukang Kayu 120,000.00 130,000.00 31,200.00 33,800.00
L.03 0.026 OH Kepala Tukang 130,000.00 140,000.00 3,380.00 3,640.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B Bahan 86,150.00 94,400.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 5,250.00 5,400.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 170,780.00 187,350.00
E Overhead & Profit (contoh 10%) 10% 17,078.00 18,735.00
F Harga Satuan Pekerjaan (D+E) 187,858.00 206,085.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 198,858.00 218,185.00


A Tenaga 84,630.00 92,950.00
L.01 0.52 OH Pekerja 90,000.00 100,000.00 46,800.00 52,000.00
L.02 0.26 OH Tukang Kayu 120,000.00 130,000.00 31,200.00 33,800.00
L.03 0.026 OH Kepala Tukang 130,000.00 140,000.00 3,380.00 3,640.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B Bahan 96,150.00 105,400.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 5,250.00 5,400.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 180,780.00 198,350.00
E Overhead & Profit (contoh 10%) 10% 18,078.00 19,835.00
F Harga Satuan Pekerjaan (D+E) 198,858.00 218,185.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 411,636.50 463,292.50


A Tenaga 107,415.00 117,975.00
L.01 0.66 OH Pekerja 90,000.00 100,000.00 59,400.00 66,000.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 266,800.00 303,200.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 7,000.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 374,215.00 421,175.00
E Overhead & Profit (contoh 10%) 10% 37,421.50 42,117.50
F Harga Satuan Pekerjaan (D+E) 411,636.50 463,292.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 433,086.50 485,732.50


A Tenaga 107,415.00 117,975.00
L.01 0.66 OH Pekerja 90,000.00 100,000.00 59,400.00 66,000.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/94 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 286,300.00 323,600.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 7,000.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 117,000.00 122,400.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 393,715.00 441,575.00
E Overhead & Profit (contoh 10%) 10% 39,371.50 44,157.50
F Harga Satuan Pekerjaan (D+E) 433,086.50 485,732.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 504,036.50 568,892.50


A Tenaga 107,415.00 117,975.00
L.01 0.66 OH Pekerja 90,000.00 100,000.00 59,400.00 66,000.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 350,800.00 399,200.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 7,000.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 458,215.00 517,175.00
E Overhead & Profit (contoh 10%) 10% 45,821.50 51,717.50
F Harga Satuan Pekerjaan (D+E) 504,036.50 568,892.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 470,486.50 527,092.50


A Tenaga 107,415.00 117,975.00
L.01 0.66 OH Pekerja 90,000.00 100,000.00 59,400.00 66,000.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 320,300.00 361,200.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 7,000.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 130,000.00 136,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 427,715.00 479,175.00
E Overhead & Profit (contoh 10%) 10% 42,771.50 47,917.50
F Harga Satuan Pekerjaan (D+E) 470,486.50 527,092.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 389,141.50 438,542.50


A Tenaga 107,415.00 117,975.00
L.01 0.66 OH Pekerja 90,000.00 100,000.00 59,400.00 66,000.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 246,350.00 280,700.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 7,000.00 7,200.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 353,765.00 398,675.00
E Overhead & Profit (contoh 10%) 10% 35,376.50 39,867.50
F Harga Satuan Pekerjaan (D+E) 389,141.50 438,542.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 104,445.00 114,576.00


A Tenaga 21,150.00 23,280.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 73,800.00 80,880.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 17,500.00 18,000.00 10,500.00 10,800.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/95 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 94,950.00 104,160.00
E Overhead & Profit (contoh 10%) 10% 9,495.00 10,416.00
F Harga Satuan Pekerjaan (D+E) 104,445.00 114,576.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 87,780.00 98,840.50
A Tenaga 25,305.00 27,855.00
L.01 0.180 OH Pekerja 90,000.00 100,000.00 16,200.00 18,000.00
L.02 0.020 OH Tukang batu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Kayu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Besi 120,000.00 130,000.00 2,400.00 2,600.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 54,495.00 62,000.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 175.00 180.00
3.0 Kg Besi Beton Polos 10,000.00 12,000.00 30,000.00 36,000.00
0.45 Kg Kawat Beton 18,000.00 20,000.00 8,100.00 9,000.00
4.0 Kg Portland Semen 1,150.00 1,175.00 4,600.00 4,700.00
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 360,000.00 2,880.00 3,240.00
C PERALATAN
D Jumlah A + B + C 79,800.00 89,855.00
E Overhead & Profit (contoh 10%) 10% 7,980.00 8,985.50
F Harga Satuan Pekerjaan (D+E) 87,780.00 98,840.50

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 113,597.00 127,311.25
A Tenaga 41,785.00 45,995.00
L.01 0.297 OH Pekerja 90,000.00 100,000.00 26,730.00 29,700.00
L.02 0.033 OH Tukang batu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Kayu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Besi 120,000.00 130,000.00 3,960.00 4,290.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 61,485.00 69,742.50
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 350.00 360.00
3.6 Kg Besi Beton Polos 10,000.00 12,000.00 36,000.00 43,200.00
0.05 Kg Kawat Beton 18,000.00 20,000.00 900.00 1,000.00
5.5 Kg Portland Semen 1,150.00 1,175.00 6,325.00 6,462.50
0.009 m3 Pasir Beton 360,000.00 380,000.00 3,240.00 3,420.00
0.015 m3 Kerikil 320,000.00 360,000.00 4,800.00 5,400.00
C PERALATAN
D Jumlah A + B + C 103,270.00 115,737.50
E Overhead & Profit (contoh 10%) 10% 10,327.00 11,573.75
F Harga Satuan Pekerjaan (D+E) 113,597.00 127,311.25

26 A.4.1.1. 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 4,402,788.50 4,907,435.50
A Tenaga 859,185.00 943,705.00
L.01 5.3 OH Pekerja 90,000.00 100,000.00 477,000.00 530,000.00
L.02 0.275 OH Tukang batu 120,000.00 130,000.00 33,000.00 35,750.00
L.02 1.30 OH Tukang Kayu 120,000.00 130,000.00 156,000.00 169,000.00
L.02 1.05 OH Tukang Besi 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.262 OH Kepala Tukang 130,000.00 140,000.00 34,060.00 36,680.00
L.04 0.265 OH Mandor 125,000.00 135,000.00 33,125.00 35,775.00
B Bahan 3,143,350.00 3,517,600.00
0.2 m3 Kayu Klas III 3,290,000.00 3,300,000.00 658,000.00 660,000.00
1.5 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 26,250.00 27,000.00
0.4 Ltr Minyak bekesting 9,000.00 10,000.00 3,600.00 4,000.00
157.5 Kg Besi Beton Polos 10,000.00 12,000.00 1,575,000.00 1,890,000.00
2.25 Kg Kawat Beton 18,000.00 20,000.00 40,500.00 45,000.00
336 Kg Portland Semen 1,150.00 1,175.00 386,400.00 394,800.00
0.54 m3 Pasir Beton 360,000.00 380,000.00 194,400.00 205,200.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/96 PEK.BETON


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
UNTUK PRODUKSI PRACETAK BISA DILAKUKAN DI PABRIK (COR DI PLANT) ATAU DI LAPANGAN (CAST IN PLACE). INDEKS YANG ADA DALAM PEDOMAN INI
HANYA UNTUK PEKERJAAN PRODUKSI YANG DILAKUKAN DI LAPANGAN, TERUTAMA UNTUK ANALISA CETAKAN (BEKISTING) PRACETAK BAIK UNTUK
KOMPONEN KOLOM, BALOK DAN PELAT.

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5 Mpa,


1 A.4.1.2.1 1 m2 90,593.50 96,836.75
Slump (120 ± 20) mm K3
A Tenaga 15,655.00 17,285.00
L.01 0.132 OH Pekerja 90,000.00 100,000.00 11,880.00 13,200.00
L.02 0.022 OH Tukang Batu 120,000.00 130,000.00 2,640.00 2,860.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 66,702.73 70,748.41
26.080 Kg Portland Semen 1,150.00 1,175.00 29,992.00 30,644.00
60.800 Kg Pasir Beton 257.14 271.43 15,634.29 16,502.86
82.320 Kg Kerikil (maksimum 30 mm) 251.85 281.48 20,732.44 23,171.56
17.200 ltr Air 20.00 25.00 344.00 430.00
C PERALATAN
D Jumlah A + B + C 82,357.73 88,033.41
E Overhead & Profit (contoh 10%) 10% 8,235.77 8,803.34
F Harga Satuan Pekerjaan (D+E) 90,593.50 96,836.75
10%
Overhead & Profit (contoh 10%)
Pembuatan Lahan Produksi Tebal 10 cm Beton f'c = 14,5 Mpa
2 A.4.1.2.2 1 m2 113,276.25 121,083.07
slum (120 ± 20 ) mm K3
A Tenaga 19,600.00 21,640.00
L.01 0.165 OH Pekerja 90,000.00 100,000.00 14,850.00 16,500.00
L.02 0.028 OH Tukang Batu 120,000.00 130,000.00 3,360.00 3,640.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 83,378.41 88,435.52
32.60 Kg Portland Semen 1,150.00 1,175.00 37,490.00 38,305.00
76.00 kg Pasir Beton 257.14 271.43 19,542.86 20,628.57
102.90 kg Kerikil (maksimum 30 mm) 251.85 281.48 25,915.56 28,964.44
21.50 ltr Air 20.00 25.00 430.00 537.50
C PERALATAN
D Jumlah A + B + C 102,978.41 110,075.52
E Overhead & Profit (contoh 10%) 10% 10,297.84 11,007.55
F Harga Satuan Pekerjaan (D+E) 113,276.25 121,083.07

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5 Mpa,


3 A.4.1.2.3 1 m2 132,554.50 141,550.88
slum (120±20)mm, K3
A Tenaga 20,450.00 22,560.00
L.01 0.165 OH Pekerja 90,000.00 100,000.00 14,850.00 16,500.00
L.02 0.033 OH Tukang Batu 120,000.00 130,000.00 3,960.00 4,290.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 100,054.10 106,122.62
39.120 Kg Portland Semen 1,150.00 1,175.00 44,988.00 45,966.00
91.200 kg Pasir Beton 257.14 271.43 23,451.43 24,754.29
123.480 kg Kerikil (maksimum 30 mm) 251.85 281.48 31,098.67 34,757.33
25.800 ltr Air 20.00 25.00 516.00 645.00
C PERALATAN
D Jumlah A + B + C 120,504.10 128,682.62
E Overhead & Profit (contoh 10%) 10% 12,050.41 12,868.26
F Harga Satuan Pekerjaan (D+E) 132,554.50 141,550.88

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5 Mpa,


4 A.4.1.2.4 1.00 m2 169,897.88 181,608.10
slum (120±20)mm, K3
A Tenaga 29,385.00 32,445.00
L.01 0.248 OH Pekerja 90,000.00 100,000.00 22,320.00 24,800.00
L.02 0.041 OH Tukang Batu 120,000.00 130,000.00 4,920.00 5,330.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 125,067.62 132,653.27
48.900 Kg Portland Semen 1,150.00 1,175.00 56,235.00 57,457.50
114.000 kg Pasir Beton 257.14 271.43 29,314.29 30,942.86
154.350 kg Kerikil (maksimum 30 mm) 251.85 281.48 38,873.33 43,446.67
32.250 ltr Air 20.00 25.00 645.00 806.25
C PERALATAN
D Jumlah A + B + C 154,452.62 165,098.27
E Overhead & Profit (contoh 10%) 10% 15,445.26 16,509.83
F Harga Satuan Pekerjaan (D+E) 169,897.88 181,608.10

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 1 m2 126,974.18 136,379.06
Pakai)
A Tenaga 10,915.00 11,835.00
L.01 0.007 OH Pekerja 90,000.00 100,000.00 630.00 700.00
L.02 0.076 OH Tukang Batu 120,000.00 130,000.00 9,120.00 9,880.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/97 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 104,516.07 112,145.97
0.008 m3 Lantai Kerja Tebal 10 cm 98,134.35 105,195.99 785.07 841.57
9.394 Kg Besi Hollow (50x50x3) mm 5,500.00 6,000.00 51,667.00 56,364.00
0.005 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 32,500.00 34,000.00
0.080 lbr Phenol film 12 mm 125,000.00 130,000.00 10,000.00 10,400.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
3.882 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 7,764.00 8,540.40
C PERALATAN
D Jumlah A + B + C 115,431.07 123,980.97
E Overhead & Profit (contoh 10%) 10% 11,543.11 12,398.10
F Harga Satuan Pekerjaan (D+E) 126,974.18 136,379.06

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 - 12


6 A.4.1.2.6 1 m2 52,174.10 54,975.36
kali Pakai)
A Tenaga 5,565.00 6,035.00
L.01 0.004 OH Pekerja 90,000.00 100,000.00 360.00 400.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 41,866.00 43,942.60
0.046 Kg Paku (5 s/d 7) cm 17,500.00 18,000.00 805.00 828.00
0.005 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 32,500.00 34,000.00
0.043 lbr Phenol film 12 mm 125,000.00 130,000.00 5,375.00 5,590.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 47,431.00 49,977.60
E Overhead & Profit (contoh 10%) 10% 4,743.10 4,997.76
F Harga Satuan Pekerjaan (D+E) 52,174.10 54,975.36

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 - 12


7 A.4.1.2.7 1 m2 45,711.60 48,210.36
kali Pakai)
A Tenaga 5,565.00 6,035.00
L.01 0.004 OH Pekerja 90,000.00 100,000.00 360.00 400.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 35,991.00 37,792.60
0.046 Kg Paku (5 s/d 7) cm 17,500.00 18,000.00 805.00 828.00
0.004 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 26,000.00 27,200.00
0.048 lbr Phenol film 12 mm 125,000.00 130,000.00 6,000.00 6,240.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 41,556.00 43,827.60
E Overhead & Profit (contoh 10%) 10% 4,155.60 4,382.76
F Harga Satuan Pekerjaan (D+E) 45,711.60 48,210.36

Pemasangan dan Membuka Bekisting untuk Komponen Plat


8 A.4.1.2.8 1 bh 8,310.50 9,146.50
Beton Pracetak
A Tenaga 7,555.00 8,315.00
L.01 0.053 OH Pekerja 90,000.00 100,000.00 4,770.00 5,300.00
L.02 0.018 OH Tukang Batu 120,000.00 130,000.00 2,160.00 2,340.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 7,555.00 8,315.00
E Overhead & Profit (contoh 10%) 10% 755.50 831.50
F Harga Satuan Pekerjaan (D+E) 8,310.50 9,146.50

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 1 bh 13,458.50 14,822.50
Balok Beton Pracetak
A Tenaga 12,235.00 13,475.00
L.01 0.089 OH Pekerja 90,000.00 100,000.00 8,010.00 8,900.00
L.02 0.030 OH Tukang Batu 120,000.00 130,000.00 3,600.00 3,900.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 12,235.00 13,475.00
E Overhead & Profit (contoh 10%) 10% 1,223.50 1,347.50
F Harga Satuan Pekerjaan (D+E) 13,458.50 14,822.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/98 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan dan Membuka Bekisting untuk Komponen
10 A.4.1.2.10 1 bh 10,884.50 11,984.50
Kolom Beton Pracetak
A Tenaga 9,895.00 10,895.00
L.01 0.071 OH Pekerja 90,000.00 100,000.00 6,390.00 7,100.00
L.02 0.024 OH Tukang Batu 120,000.00 130,000.00 2,880.00 3,120.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 9,895.00 10,895.00
E Overhead & Profit (contoh 10%) 10% 989.50 1,089.50
F Harga Satuan Pekerjaan (D+E) 10,884.50 11,984.50

11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 70,339.50 76,312.50

A Tenaga 63,945.00 69,375.00


L.01 0.064 OH Pekerja 90,000.00 100,000.00 5,760.00 6,400.00
L.02 0.244 OH Tukang Batu 120,000.00 130,000.00 29,280.00 31,720.00
L.02 0.128 OH Tukang Vibrator 120,000.00 130,000.00 15,360.00 16,640.00
L.03 0.034 OH Kapala Tukang 130,000.00 140,000.00 4,420.00 4,760.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 63,945.00 69,375.00
E Overhead & Profit (contoh 10%) 10% 6,394.50 6,937.50
F Harga Satuan Pekerjaan (D+E) 70,339.50 76,312.50

12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 72,319.50 78,468.50

A Tenaga 65,745.00 71,335.00


L.01 0.069 OH Pekerja 90,000.00 100,000.00 6,210.00 6,900.00
L.02 0.242 OH Tukang Batu 120,000.00 130,000.00 29,040.00 31,460.00
L.02 0.138 OH Tukang Vibrator 120,000.00 130,000.00 16,560.00 17,940.00
L.03 0.037 OH Kapala Tukang 130,000.00 140,000.00 4,810.00 5,180.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 65,745.00 71,335.00
E Overhead & Profit (contoh 10%) 10% 6,574.50 7,133.50
F Harga Satuan Pekerjaan (D+E) 72,319.50 78,468.50

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 1 m3 65,015.50 70,537.50
Pracetak
A Tenaga 59,105.00 64,125.00
L.01 0.061 OH Pekerja 90,000.00 100,000.00 5,490.00 6,100.00
L.02 0.213 OH Tukang Batu 120,000.00 130,000.00 25,560.00 27,690.00
L.02 0.122 OH Tukang Vibrator 120,000.00 130,000.00 14,640.00 15,860.00
L.03 0.033 OH Kapala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 59,105.00 64,125.00
E Overhead & Profit (contoh 10%) 10% 5,910.50 6,412.50
F Harga Satuan Pekerjaan (D+E) 65,015.50 70,537.50

14 A.4.1.2.14 1 bh Ereksi Komponen Untuk Plat Pracetak 583,559.02 609,282.96


A Tenaga 49,915.00 54,940.00
L.08 0.067 OH Operator Crane 175,000.00 200,000.00 11,725.00 13,400.00
L.09 0.067 OH Pembantu Operator Crane 120,000.00 130,000.00 8,040.00 8,710.00
L.01 0.067 OH Pekerja 90,000.00 100,000.00 6,030.00 6,700.00
L.02 0.067 OH Tukang Batu 120,000.00 130,000.00 8,040.00 8,710.00
L.02 0.134 OH Tukang Ereksi 120,000.00 130,000.00 16,080.00 17,420.00
L.03 0.067 OH Kepala Tukang 130,000.00 140,000.00 8,710.00 9,380.00
L.04 0.067 OH Mandor 125,000.00 135,000.00 8,375.00 9,045.00
B Bahan 54,743.20 57,413.60
6.676 Ltr Solar 8,200.00 8,600.00 54,743.20 57,413.60
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 530,508.20 553,893.60
E Overhead & Profit (contoh 10%) 10% 53,050.82 55,389.36
F Harga Satuan Pekerjaan (D+E) 583,559.02 609,282.96

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/99 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Plat Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Plat Ereksi Plat

1 1.0000 13 1.114
2 1.0000 14 1.134

3 1.0000 15 1.155

4 1.0000 16 1.176
5 1.0000 17 1.197

6 1.0000 18 1.219
7 1.0000 19 1.241

8 1.0180 20 1.264
9 1.0370 21 1.287

10 1.0550 22 1.310
11 1.0750 23 1.334

12 1.0940 24 1.358

15 A.4.1.2.15 1 bh Ereksi Komponen Untuk Balok Pracetak 573,536.70 598,516.60


A Tenaga 45,445.00 50,020.00
L.08 0.061 OH Operator Crane 175,000.00 200,000.00 10,675.00 12,200.00
L.09 0.061 OH Pembantu Operator Crane 120,000.00 130,000.00 7,320.00 7,930.00
L.01 0.061 OH Pekerja 90,000.00 100,000.00 5,490.00 6,100.00
L.02 0.061 OH Tukang Batu 120,000.00 130,000.00 7,320.00 7,930.00
L.02 0.122 OH Tukang Ereksi 120,000.00 130,000.00 14,640.00 15,860.00
L.03 0.061 OH Kepala Tukang 130,000.00 140,000.00 7,930.00 8,540.00
L.04 0.061 OH Mandor 125,000.00 135,000.00 7,625.00 8,235.00
B Bahan 50,102.00 52,546.00
6.110 Ltr Solar 8,200.00 8,600.00 50,102.00 52,546.00
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 521,397.00 544,106.00
E Overhead & Profit (contoh 10%) 10% 52,139.70 54,410.60
F Harga Satuan Pekerjaan (D+E) 573,536.70 598,516.60

Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak


Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok
1 1.0000 13 1.068

2 1.0000 14 1.080
3 1.0000 15 1.092

4 1.0000 16 1.104
5 1.0000 17 1.116

6 1.0000 18 1.129
7 1.0000 19 1.141

8 1.0110 20 1.154
9 1.0220 21 1.166

10 1.0340 22 1.179

11 1.0450 23 1.192
12 1.0570 24 1.206

16 A.4.1.2.16 1 bh Ereksi Komponen Untuk Kolom Pracetak 824,292.04 865,372.42


A Tenaga 61,835.00 68,060.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 120,000.00 130,000.00 9,960.00 10,790.00
L.01 0.083 OH Pekerja 90,000.00 100,000.00 7,470.00 8,300.00
L.02 0.083 OH Tukang Batu 120,000.00 130,000.00 9,960.00 10,790.00
L.02 0.166 OH Tukang Ereksi 120,000.00 130,000.00 19,920.00 21,580.00
L.03 0.083 OH Kepala Tukang 130,000.00 140,000.00 10,790.00 11,620.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 67,871.40 71,182.20
8.277 Ltr Solar 8,200.00 8,600.00 67,871.40 71,182.20
C PERALATAN 619,650.00 647,460.00
0.083 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 377,650.00 383,460.00
2.200 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 242,000.00 264,000.00
D Jumlah A + B + C 749,356.40 786,702.20
E Overhead & Profit (contoh 10%) 10% 74,935.64 78,670.22
F Harga Satuan Pekerjaan (D+E) 824,292.04 865,372.42

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/100 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok

1 1.0000 13 1.162
2 1.0000 14 1.191

3 1.0000 15 1.221

4 1.0000 16 1.252
5 1.0000 17 1.284

6 1.0000 18 1.318
7 1.0000 19 1.350

8 1.0250 20 1.384
9 1.0510 21 1.419

10 1.0780 22 1.455
11 1.1050 23 1.492

12 1.1330 24 1.530

17 A.4.1.2.17 1 bh Langsiran Komponen untuk Plat Pracetak (± 20 m) 158,312.44 165,631.62


A Tenaga 41,915.00 46,480.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 120,000.00 130,000.00 9,960.00 10,790.00
L.01 0.083 OH Pekerja 90,000.00 100,000.00 7,470.00 8,300.00
L.02 0.083 OH Tukang Batu 120,000.00 130,000.00 9,960.00 10,790.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 143,920.40 150,574.20
E Overhead & Profit (contoh 10%) 10% 14,392.04 15,057.42
F Harga Satuan Pekerjaan (D+E) 158,312.44 165,631.62

18 A.4.1.2.18 1 bh Langsiran Komponen untuk Balok Pracetak (± 20 m) 125,268.44 128,924.62


A Tenaga 11,875.00 13,110.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 120,000.00 130,000.00 2,280.00 2,470.00
L.01 0.019 OH Pekerja 90,000.00 100,000.00 1,710.00 1,900.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 113,880.40 117,204.20
E Overhead & Profit (contoh 10%) 10% 11,388.04 11,720.42
F Harga Satuan Pekerjaan (D+E) 125,268.44 128,924.62

19 A.4.1.2.19 1 bh Langsiran Komponen untuk Kolom Pracetak (± 20 m) 125,268.44 128,924.62


A Tenaga 11,875.00 13,110.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 120,000.00 130,000.00 2,280.00 2,470.00
L.01 0.019 OH Pekerja 90,000.00 100,000.00 1,710.00 1,900.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 113,880.40 117,204.20
E Overhead & Profit (contoh 10%) 10% 11,388.04 11,720.42
F Harga Satuan Pekerjaan (D+E) 125,268.44 128,924.62

20 A.4.1.2.20 1 m3 Bahan Grout Campuran 3,417,700.00 3,689,125.00


A Tenaga - -

B Bahan 3,107,000.00 3,353,750.00


1,200 Kg Semen Grout 1,500.00 1,650.00 1,800,000.00 1,980,000.00
650 kg Screening 2,000.00 2,100.00 1,300,000.00 1,365,000.00
350 Ltr Air 20.00 25.00 7,000.00 8,750.00
C PERALATAN - -
D Jumlah A + B + C 3,107,000.00 3,353,750.00
E Overhead & Profit (contoh 10%) 10% 310,700.00 335,375.00
F Harga Satuan Pekerjaan (D+E) 3,417,700.00 3,689,125.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/101 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.1.2.21 1 m3 Bahan Grout Campuran (tidak Campuran) 3,061,300.00 3,368,750.00
A Tenaga - -

B Bahan 2,783,000.00 3,062,500.00


1,850 Kg Semen Grout 1,500.00 1,650.00 2,775,000.00 3,052,500.00
400 Ltr Air 20.00 25.00 8,000.00 10,000.00
C PERALATAN - -
D Jumlah A + B + C 2,783,000.00 3,062,500.00
E Overhead & Profit (contoh 10%) 10% 278,300.00 306,250.00
F Harga Satuan Pekerjaan (D+E) 3,061,300.00 3,368,750.00

22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 64,113.50 69,371.50
A Tenaga 58,285.00 63,065.00
L.02 0.367 OH Tukang Batu 120,000.000 130,000.000 44,040.000 47,710.000
L.03 0.074 OH Kepala Tukang 130,000.000 140,000.000 9,620.000 10,360.000
L.04 0.037 OH Mandor 125,000.000 135,000.000 4,625.000 4,995.000

B Bahan - -

C PERALATAN - -
D Jumlah A + B + C 58,285.00 63,065.00
E Overhead & Profit (contoh 10%) 10% 5,828.50 6,306.50
F Harga Satuan Pekerjaan (D+E) 64,113.50 69,371.50

23 A.4.1.2.23 1 ttk Pemasangan Bekisting Joint Pra Cetak 137,351.50 147,110.70


A Tenaga 33,445.00 36,585.00
L.01 0.147 OH Pekerja 90,000.00 100,000.00 13,230.000 14,700.000
L.02 0.147 OH Tukang Batu 120,000.000 130,000.000 17,640.000 19,110.000
L.03 0.015 OH Kepala Tukang 130,000.000 140,000.000 1,950.000 2,100.000
L.04 0.005 OH Mandor 125,000.000 135,000.000 625.000 675.000
B Bahan 91,420.00 97,152.00
0.012 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 78,000.00 81,600.00
0.004 m3 Papan Cor 2,200,000.00 2,700,000.00 8,800.00 10,800.00
0.264 Kg Paku (5 s/d 7) cm 17,500.00 18,000.00 4,620.00 4,752.00
C PERALATAN - -
D Jumlah A + B + C 124,865.00 133,737.00
E Overhead & Profit (contoh 10%) 10% 12,486.50 13,373.70
F Harga Satuan Pekerjaan (D+E) 137,351.50 147,110.70

24 A.4.1.2.24 1 ttk Upah Pemasangan Joint dengan Sling 55,236.50 60,439.50


A Tenaga 50,215.00 54,945.00
L.01 0.220 OH Pekerja 90,000.00 100,000.00 19,800.000 22,000.000
L.02 0.022 OH Tukang Batu 120,000.000 130,000.000 2,640.000 2,860.000
L.02 0.220 OH Tukang Besi 120,000.000 130,000.000 26,400.000 28,600.000
L.04 0.011 OH Mandor 125,000.000 135,000.000 1,375.000 1,485.000
B Bahan

C PERALATAN - -
D Jumlah A + B + C 50,215.00 54,945.00
E Overhead & Profit (contoh 10%) 10% 5,021.50 5,494.50
F Harga Satuan Pekerjaan (D+E) 55,236.50 60,439.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/102 PEK.BETON PRA CETAK


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 33,473.00 35,208.25
A Tenaga 13,755.00 15,045.00
L.01 0.06 OH Pekerja 90,000.00 100,000.00 5,400.00 6,000.00
L.02 0.06 OH Tukang Besi 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 16,675.00 16,962.50
1.15 Kg Besi Profil 14,500.00 14,750.00 16,675.00 16,962.50
C PERALATAN
D Jumlah A + B + C 30,430.00 32,007.50
E Overhead & Profit (contoh 10%) 10% 3,043.00 3,200.75
F Harga Satuan Pekerjaan (D+E) 33,473.00 35,208.25

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 26,199.25 28,061.00


A Tenaga 13,755.00 15,045.00
L.01 0.06 OH Pekerja 90,000.00 100,000.00 5,400.00 6,000.00
L.02 0.06 OH Tukang Besi 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 10,062.50 10,465.00
1.15 kg Besi Baja IWF 8,750.00 9,100.00 10,062.50 10,465.00
C PERALATAN
D Jumlah A + B + C 23,817.50 25,510.00
E Overhead & Profit (contoh 10%) 10% 2,381.75 2,551.00
F Harga Satuan Pekerjaan (D+E) 26,199.25 28,061.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 103,020.50 119,806.50


A Tenaga 21,755.00 23,815.00
L.01 0.100 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.100 OH Tukang Besi 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.001 OH Kepala Tukang 130,000.00 140,000.00 130.00 140.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 11,900.00 13,100.00
1 ltr Solar 8,200.00 8,600.00 8,200.00 8,600.00
0.1 ltr Minyak Pelumas 37,000.00 45,000.00 3,700.00 4,500.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 93,655.00 108,915.00
E Overhead & Profit (contoh 10%) 10% 9,365.50 10,891.50
F Harga Satuan Pekerjaan (D+E) 103,020.50 119,806.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 917,235.00 957,132.00
rangka baja Siku
A Tenaga 240,650.00 263,220.00
L.01 1.05 OH Pekerja 90,000.00 100,000.00 94,500.00 105,000.00
L.02 1.05 OH Tukang Besi 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.052 OH Mandor 125,000.00 135,000.00 6,500.00 7,020.00
B Bahan 593,200.00 606,900.00
15 Kg Besi Siku L.30.30.3 8,750.00 9,100.00 131,250.00 136,500.00
32.8 Kg Besi Plat Baja 14,000.00 14,250.00 459,200.00 467,400.00
0.05 Kg Kawat Las 55,000.00 60,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 833,850.00 870,120.00
E Overhead & Profit (contoh 10%) 10% 83,385.00 87,012.00
F Harga Satuan Pekerjaan (D+E) 917,235.00 957,132.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 24,039.40 27,816.80


A Tenaga 6,510.00 7,150.00
L.01 0.04 OH Pekerja 90,000.00 100,000.00 3,600.00 4,000.00
L.02 0.02 OH Tukang Besi 120,000.00 130,000.00 2,400.00 2,600.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 2,594.00 2,838.00
0.04 kg Kawat Las 55,000.00 60,000.00 2,200.00 2,400.00
0.03 ltr Solar 8,200.00 8,600.00 246.00 258.00
0.004 ltr Minyak Pelumas 37,000.00 45,000.00 148.00 180.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/103 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 21,854.00 25,288.00
E Overhead & Profit (contoh 10%) 10% 2,185.40 2,528.80
F Harga Satuan Pekerjaan (D+E) 24,039.40 27,816.80

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 257,834.28 289,234.66


A Tenaga 148,950.00 162,920.00
L.01 0.65 OH Pekerja 90,000.00 100,000.00 58,500.00 65,000.00
L.02 0.65 OH Tukang Las Biasa 120,000.00 130,000.00 78,000.00 84,500.00
L.03 0.065 OH Kepala Tukang 130,000.00 140,000.00 8,450.00 9,100.00
L.04 0.032 OH Mandor 125,000.00 135,000.00 4,000.00 4,320.00
B Bahan 85,444.80 100,020.60
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,403.94 2,781.68 48,078.80 55,633.60
C PERALATAN
D Jumlah A + B + C 234,394.80 262,940.60
E Overhead & Profit (contoh 10%) 10% 23,439.48 26,294.06
F Harga Satuan Pekerjaan (D+E) 257,834.28 289,234.66

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 652,685.00 691,471.00


A Tenaga 268,350.00 293,610.00
L.01 1.2 OH Pekerja 90,000.00 100,000.00 108,000.00 120,000.00
L.02 1.2 OH Tukang Besi 120,000.00 130,000.00 144,000.00 156,000.00
L.03 0.12 OH Kepala Tukang 130,000.00 140,000.00 15,600.00 16,800.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 325,000.00 335,000.00
1 m2 Pintu Gulung Besi 325,000.00 335,000.00 325,000.00 335,000.00
C PERALATAN
D Jumlah A + B + C 593,350.00 628,610.00
E Overhead & Profit (contoh 10%) 10% 59,335.00 62,861.00
F Harga Satuan Pekerjaan (D+E) 652,685.00 691,471.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 550,957.00 588,863.00


A Tenaga 100,870.00 110,330.00
L.01 0.44 OH Pekerja 90,000.00 100,000.00 39,600.00 44,000.00
L.02 0.44 OH Tukang Besi 120,000.00 130,000.00 52,800.00 57,200.00
L.03 0.044 OH Kepala Tukang 130,000.00 140,000.00 5,720.00 6,160.00
L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 400,000.00 425,000.00
1 m2 Pintu Lipat 400,000.00 425,000.00 400,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 500,870.00 535,330.00
E Overhead & Profit (contoh 10%) 10% 50,087.00 53,533.00
F Harga Satuan Pekerjaan (D+E) 550,957.00 588,863.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 510,510.00 576,114.00


A Tenaga 114,100.00 123,740.00
L.01 0.08 OH Pekerja 90,000.00 100,000.00 7,200.00 8,000.00
L.02 0.8 OH Tukang Besi 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 350,000.00 400,000.00
1 m2 Sunscreen Allumunium 350,000.00 400,000.00 350,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 464,100.00 523,740.00
E Overhead & Profit (contoh 10%) 10% 46,410.00 52,374.00
F Harga Satuan Pekerjaan (D+E) 510,510.00 576,114.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 554,675.00 594,825.00


A Tenaga 229,250.00 250,750.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 1 OH Tukang Besi 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.1 OH Kepala Tukang 130,000.00 140,000.00 13,000.00 14,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/104 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 275,000.00 290,000.00


1 m2 Rolling Allumunium 275,000.00 290,000.00 275,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 504,250.00 540,750.00
E Overhead & Profit (contoh 10%) 10% 50,425.00 54,075.00
F Harga Satuan Pekerjaan (D+E) 554,675.00 594,825.00

Pemasangan Kusen Pintu & Jendela Allumunium warna


11 A.4.2.1.11 1 m' 130,736.65 138,573.05
Hijau 4"
A Tenaga 9,851.50 10,775.50
L.01 0.043 OH Pekerja 90,000.00 100,000.00 3,870.00 4,300.00
L.02 0.043 OH Tukang Besi 120,000.00 130,000.00 5,160.00 5,590.00
L.03 0.0043 OH Kepala Tukang 130,000.00 140,000.00 559.00 602.00
L.04 0.0021 OH Mandor 125,000.00 135,000.00 262.50 283.50
B Bahan 109,000.00 115,200.00
1.1 m' Profil Allumunium 95,000.00 100,000.00 104,500.00 110,000.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 118,851.50 125,975.50
E Overhead & Profit (contoh 10%) 10% 11,885.15 12,597.55
F Harga Satuan Pekerjaan (D+E) 130,736.65 138,573.05

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 553,498.00 587,737.70


A Tenaga 19,480.00 21,307.00
L.01 0.085 OH Pekerja 90,000.00 100,000.00 7,650.00 8,500.00
L.02 0.085 OH Tukang Besi 120,000.00 130,000.00 10,200.00 11,050.00
L.03 0.0085 OH Kepala Tukang 130,000.00 140,000.00 1,105.00 1,190.00
L.04 0.0042 OH Mandor 125,000.00 135,000.00 525.00 567.00
B Bahan 483,700.00 513,000.00
4.4 m' Profil Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 503,180.00 534,307.00
E Overhead & Profit (contoh 10%) 10% 50,318.00 53,430.70
F Harga Satuan Pekerjaan (D+E) 553,498.00 587,737.70

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 521,009.50 555,153.50


A Tenaga 19,645.00 21,485.00
L.01 0.085 OH Pekerja 90,000.00 100,000.00 7,650.00 8,500.00
L.02 0.085 OH Tukang Besi 120,000.00 130,000.00 10,200.00 11,050.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 454,000.00 483,200.00
4.4 m' Pintu Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 473,645.00 504,685.00
E Overhead & Profit (contoh 10%) 10% 47,364.50 50,468.50
F Harga Satuan Pekerjaan (D+E) 521,009.50 555,153.50

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 192,830.00 206,613.00


A Tenaga 80,300.00 87,830.00
L.01 0.35 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.35 OH Tukang Besi 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 175,300.00 187,830.00
E Overhead & Profit (contoh 10%) 10% 17,530.00 18,783.00
F Harga Satuan Pekerjaan (D+E) 192,830.00 206,613.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 587,797.86 640,238.66


A Tenaga 382,785.00 418,685.00
L.01 1.67 OH Pekerja 90,000.00 100,000.00 150,300.00 167,000.00
L.02 1.67 OH Tukang Las 120,000.00 130,000.00 200,400.00 217,100.00
L.03 0.167 OH Kepala Tukang 130,000.00 140,000.00 21,710.00 23,380.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/105 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/106 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 151,576.70 163,350.14


6.177 kg Besi Strip 14,000.00 14,250.00 86,478.00 88,022.25
27.08 cm Pengelasan 2,403.94 2,781.68 65,098.70 75,327.89
C PERALATAN
D Jumlah A + B + C 534,361.70 582,035.14
E Overhead & Profit (contoh 10%) 10% 53,436.17 58,203.51
F Harga Satuan Pekerjaan (D+E) 587,797.86 640,238.66

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 105,222.45 118,725.71


A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 72,731.77 82,857.46
1.1 m2 Kawat Nyamuk nylon 20,000.00 25,000.00 22,000.00 27,500.00
11.11 cm Pengelasan 2,403.94 2,781.68 26,707.77 30,904.46
1.716 kg Baja Strip (0,2x2) cm 14,000.00 14,250.00 24,024.00 24,453.00
C PERALATAN
D Jumlah A + B + C 95,656.77 107,932.46
E Overhead & Profit (contoh 10%) 10% 9,565.68 10,793.25
F Harga Satuan Pekerjaan (D+E) 105,222.45 118,725.71

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 138,572.50 151,178.50


A Tenaga 44,725.00 48,935.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 81,250.00 88,500.00
1.1 m2 Jendela Nako 37,500.00 40,000.00 41,250.00 44,000.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 125,975.00 137,435.00
E Overhead & Profit (contoh 10%) 10% 12,597.50 13,743.50
F Harga Satuan Pekerjaan (D+E) 138,572.50 151,178.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 209,838.75 232,259.50
cm
A Tenaga 70,500.00 76,850.00
L.01 0.20 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.4 OH Tukang Kayu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 120,262.50 134,295.00
1.05 Lbr Seng Plaat 22,000.00 24,500.00 23,100.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 17,500.00 18,000.00 262.50 270.00
0.019 m3 Kayu Papan Klas II atau III 5,100,000.00 5,700,000.00 96,900.00 108,300.00
C PERALATAN
D Jumlah A + B + C 190,762.50 211,145.00
E Overhead & Profit (contoh 10%) 10% 19,076.25 21,114.50
F Harga Satuan Pekerjaan (D+E) 209,838.75 232,259.50

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 82,500.00 90,161.50
BJLS 30 Lebar 45 cm
A Tenaga 44,725.00 48,935.00
L.01 0.20 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.20 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 30,275.00 33,030.00
1.05 Lbr Seng Plaat 22,000.00 24,500.00 23,100.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 17,500.00 18,000.00 175.00 180.00
0.5 Kg Besi strip 14,000.00 14,250.00 7,000.00 7,125.00
C PERALATAN
D Jumlah A + B + C 75,000.00 81,965.00
E Overhead & Profit (contoh 10%) 10% 7,500.00 8,196.50
F Harga Satuan Pekerjaan (D+E) 82,500.00 90,161.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/107 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 124,712.50 134,480.50
60x120 cm dinding partisi
A Tenaga 57,375.00 62,755.00
L.01 0.250 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.250 OH Tukang Besi 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 113,375.00 122,255.00
E Overhead & Profit (contoh 10%) 10% 11,337.50 12,225.50
F Harga Satuan Pekerjaan (D+E) 124,712.50 134,480.50

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 158,730.00 171,413.00
60x60 cm dinding plafond
A Tenaga 80,300.00 87,830.00
L.01 0.350 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.350 OH Tukang Besi 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 144,300.00 155,830.00
E Overhead & Profit (contoh 10%) 10% 14,430.00 15,583.00
F Harga Satuan Pekerjaan (D+E) 158,730.00 171,413.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 248,633.28 267,087.01
dingin Profil C75
A Tenaga 168,255.00 184,035.00
L.01 0.734 OH Pekerja 90,000.00 100,000.00 66,060.00 73,400.00
L.02 0.734 OH Tukang Besi 120,000.00 130,000.00 88,080.00 95,420.00
L.03 0.073 OH Kepala Tukang 130,000.00 140,000.00 9,490.00 10,220.00
L.04 0.037 OH Mandor 125,000.00 135,000.00 4,625.00 4,995.00
B Bahan 53,331.00 54,250.50
3.065 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 44,442.50 45,208.75
C PERALATAN 4,444.25 4,520.88
10 % Peralatan *) harga bahan 44,442.50 45,208.75 4,444.25 4,520.88
D Harga Satuan Pekerjaan (D+E) 226,030.25 242,806.38
E 0 10% 22,603.03 24,280.64
F Harga Satuan Pekerjaan (D+E) 248,633.28 267,087.01
Pemasangan Atap jurai Rangka Atap Baja Canal C dingin
22 A.4.2.1.23 1 m2 275,722.15 295,152.83
Profil C75
A Tenaga 174,314.00 190,662.00
L.01 0.7604 OH Pekerja 90,000.00 100,000.00 68,436.00 76,040.00
L.02 0.7604 OH Tukang Besi 120,000.00 130,000.00 91,248.00 98,852.00
L.03 0.0760 OH Kepala Tukang 130,000.00 140,000.00 9,880.00 10,640.00
L.04 0.0380 OH Mandor 125,000.00 135,000.00 4,750.00 5,130.00
B Bahan 70,470.00 71,685.00
4.050 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 58,725.00 59,737.50
C PERALATAN 5,872.50 5,973.75
10 % Peralatan *) harga bahan 58,725.00 59,737.50 5,872.50 5,973.75
D Jumlah A + B + C 250,656.50 268,320.75
E Overhead & Profit (contoh 10%) 10% 25,065.65 26,832.08
F Harga Satuan Pekerjaan (D+E) 275,722.15 295,152.83

23 LS 1 m2 Memasang rangka atap baja ringan tiap 1 m2 166,929.95 177,146.48

A Tenaga 87,157.00 95,331.00


L.01 0.7604 OH Pekerja 90,000.00 100,000.00 34,218.00 38,020.00
L.02 0.7604 OH Tukang Besi 120,000.00 130,000.00 45,624.00 49,426.00
L.03 0.0760 OH Kepala Tukang 130,000.00 140,000.00 4,940.00 5,320.00
L.04 0.0380 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/108 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 58,725.00 59,737.50


4.05 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 58,725.00 59,737.50
C PERALATAN 5,872.50 5,973.75
10 % Peralatan *) harga bahan 58,725.00 59,737.50 5,872.50 5,973.75
D Jumlah A + B + C 151,754.50 161,042.25
E Overhead & Profit (contoh 10%) 10% 15,175.45 16,104.23
F Harga Satuan Pekerjaan (D+E) 166,929.95 177,146.48

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/109 PEK.BESI & ALMUNIUM


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 267,052.50 287,168.75
Tebal 1 bata Camp. 1SP: 2PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 158,425.00 168,212.50
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
43.5 Kg Portland Semen (PC) 1,150.00 1,175.00 50,025.00 51,112.50
0.08 m3 Pasir Pasang (PP) 340,000.00 370,000.00 27,200.00 29,600.00
C PERALATAN
D Jumlah A + B + C 242,775.00 261,062.50
E Overhead & Profit (contoh 10%) 10% 24,277.50 26,106.25
F Harga Satuan Pekerjaan (D+E) 267,052.50 287,168.75
Overhead & Profit (contoh 10%)
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
2 A.4.4.1.2 1 m2 257,820.75 278,009.88
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 150,032.50 159,886.25
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
32.95 Kg Portland Semen (PC) 1,150.00 1,175.00 37,892.50 38,716.25
0.091 m3 Pasir Pasang (PP) 340,000.00 370,000.00 30,940.00 33,670.00
C PERALATAN
D Jumlah A + B + C 234,382.50 252,736.25
E Overhead & Profit (contoh 10%) 10% 23,438.25 25,273.63
F Harga Satuan Pekerjaan (D+E) 257,820.75 278,009.88

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 250,472.75 270,551.88
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 143,352.50 153,106.25
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
26.55 Kg Portland Semen (PC) 1,150.00 1,175.00 30,532.50 31,196.25
0.093 m3 Pasir Pasang (PP) 340,000.00 370,000.00 31,620.00 34,410.00
C PERALATAN
D Jumlah A + B + C 227,702.50 245,956.25
E Overhead & Profit (contoh 10%) 10% 22,770.25 24,595.63
F Harga Satuan Pekerjaan (D+E) 250,472.75 270,551.88

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 248,336.00 268,592.50
Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 141,410.00 151,325.00
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
22.2 Kg Portland Semen (PC) 1,150.00 1,175.00 25,530.00 26,085.00
0.102 m3 Pasir Pasang (PP) 340,000.00 370,000.00 34,680.00 37,740.00
C PERALATAN
D Jumlah A + B + C 225,760.00 244,175.00
E Overhead & Profit (contoh 10%) 10% 22,576.00 24,417.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/110 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 248,336.00 268,592.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/111 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 251,135.50 271,950.25
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 143,955.00 154,377.50
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
18.5 Kg Portland Semen (PC) 1,150.00 1,175.00 21,275.00 21,737.50
0.122 m3 Pasir Pasang (PP) 340,000.00 370,000.00 41,480.00 45,140.00
C PERALATAN
D Jumlah A + B + C 228,305.00 247,227.50
E Overhead & Profit (contoh 10%) 10% 22,830.50 24,722.75
F Harga Satuan Pekerjaan (D+E) 251,135.50 271,950.25

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 238,526.20 258,438.40
Tebal 1 Bata Camp. 1SP : 3 KP :10PP
A Tenaga 84,350.00 92,850.00
L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 132,492.00 142,094.00
140 Buah Bata Merah 580.00 625.00 81,200.00 87,500.00
10.08 Kg Portland Semen (PC) 1,150.00 1,175.00 11,592.00 11,844.00
0.0925 m3 Pasir Pasang (PP) 340,000.00 370,000.00 31,450.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 216,842.00 234,944.00
E Overhead & Profit (contoh 10%) 10% 21,684.20 23,494.40
F Harga Satuan Pekerjaan (D+E) 238,526.20 258,438.40

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 129,236.25 139,151.38
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 75,312.50 80,076.25
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
18.95 Kg Portland Semen 1,150.00 1,175.00 21,792.50 22,266.25
0.038 m3 Pasir Pasang 340,000.00 370,000.00 12,920.00 14,060.00
C PERALATAN
D Jumlah A + B + C 117,487.50 126,501.25
E Overhead & Profit (contoh 10%) 10% 11,748.75 12,650.13
F Harga Satuan Pekerjaan (D+E) 129,236.25 139,151.38

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 124,190.55 134,045.73
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 70,725.50 75,434.75
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
14.37 Kg Portland Semen 1,150.00 1,175.00 16,525.50 16,884.75
0.04 m3 Pasir Pasang 340,000.00 370,000.00 13,600.00 14,800.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/112 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 112,900.50 121,859.75
E Overhead & Profit (contoh 10%) 10% 11,290.05 12,185.98
F Harga Satuan Pekerjaan (D+E) 124,190.55 134,045.73

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 121,682.00 131,557.25
Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 68,445.00 73,172.50
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
11.50 Kg Portland Semen 1,150.00 1,175.00 13,225.00 13,512.50
0.043 m3 Pasir Pasang 340,000.00 370,000.00 14,620.00 15,910.00
C PERALATAN
D Jumlah A + B + C 110,620.00 119,597.50
E Overhead & Profit (contoh 10%) 10% 11,062.00 11,959.75
F Harga Satuan Pekerjaan (D+E) 121,682.00 131,557.25

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 120,127.70 130,018.90
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 67,032.00 71,774.00
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
9.68 Kg Portland Semen 1,150.00 1,175.00 11,132.00 11,374.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 109,207.00 118,199.00
E Overhead & Profit (contoh 10%) 10% 10,920.70 11,819.90
F Harga Satuan Pekerjaan (D+E) 120,127.70 130,018.90

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 119,903.30 129,889.10
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 66,828.00 71,656.00
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
8.32 Kg Portland Semen 1,150.00 1,175.00 9,568.00 9,776.00
0.049 m3 Pasir Pasang 340,000.00 370,000.00 16,660.00 18,130.00
C PERALATAN
D Jumlah A + B + C 109,003.00 118,081.00
E Overhead & Profit (contoh 10%) 10% 10,900.30 11,808.10
F Harga Satuan Pekerjaan (D+E) 119,903.30 129,889.10

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 117,975.00 127,943.75
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 65,075.00 69,887.50
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
6.50 Kg Portland Semen 1,150.00 1,175.00 7,475.00 7,637.50
0.05 m3 Pasir Pasang 340,000.00 370,000.00 17,000.00 18,500.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/113 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 107,250.00 116,312.50
E Overhead & Profit (contoh 10%) 10% 10,725.00 11,631.25
F Harga Satuan Pekerjaan (D+E) 117,975.00 127,943.75

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 120,395.00 130,473.75
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 67,275.00 72,187.50
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
4.5 Kg Portland Semen 1,150.00 1,175.00 5,175.00 5,287.50
0.05 m3 Pasir Pasang 340,000.00 370,000.00 17,000.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 109,450.00 118,612.50
E Overhead & Profit (contoh 10%) 10% 10,945.00 11,861.25
F Harga Satuan Pekerjaan (D+E) 120,395.00 130,473.75

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 107,684.50 116,616.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 55,720.00 59,590.00
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
0.018 m3 Semen Merah 200,000.00 200,000.00 3,600.00 3,600.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 97,895.00 106,015.00
E Overhead & Profit (contoh 10%) 10% 9,789.50 10,601.50
F Harga Satuan Pekerjaan (D+E) 107,684.50 116,616.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 109,224.50 118,442.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 57,120.00 61,250.00
70 Buah Bata Merah 5 x 11 x 22 580.00 625.00 40,600.00 43,750.00
0.014 m3 Semen Merah 200,000.00 200,000.00 2,800.00 2,800.00
0.028 m3 Pasir Pasang 340,000.00 370,000.00 9,520.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 99,295.00 107,675.00
E Overhead & Profit (contoh 10%) 10% 9,929.50 10,767.50
F Harga Satuan Pekerjaan (D+E) 109,224.50 118,442.50

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 427,776.80 462,551.10
A Tenaga 53,700.00 59,030.00
L.01 0.350 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/114 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 335,188.00 361,471.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,150.00 1,175.00 34,868.00 35,626.00
0.728 m3 Pasir Pasang 340,000.00 370,000.00 247,520.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 388,888.00 420,501.00
E Overhead & Profit (contoh 10%) 10% 38,888.80 42,050.10
F Harga Satuan Pekerjaan (D+E) 427,776.80 462,551.10

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 436,566.90 472,626.55
A Tenaga 53,700.00 59,030.00
L.01 0.350 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 343,179.00 370,630.50
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,150.00 1,175.00 27,899.00 28,505.50
0.772 m3 Pasir Pasang 340,000.00 370,000.00 262,480.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 396,879.00 429,660.50
E Overhead & Profit (contoh 10%) 10% 39,687.90 42,966.05
F Harga Satuan Pekerjaan (D+E) 436,566.90 472,626.55

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 337,107.10 364,396.45
A Tenaga 46,760.00 51,440.00
L.01 0.320 OH Pekerja 90,000.00 100,000.00 28,800.00 32,000.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 259,701.00 279,829.50
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,150.00 1,175.00 26,151.00 26,719.50
0.550 m3 Pasir Pasang 340,000.00 370,000.00 187,000.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 306,461.00 331,269.50
E Overhead & Profit (contoh 10%) 10% 30,646.10 33,126.95
F Harga Satuan Pekerjaan (D+E) 337,107.10 364,396.45

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 343,332.00 371,552.50
A Tenaga 46,760.00 51,440.00
L.01 0.320 OH Pekerja 90,000.00 100,000.00 28,800.00 32,000.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 265,360.00 286,335.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,150.00 1,175.00 20,930.00 21,385.00
0.582 m3 Pasir Pasang 340,000.00 370,000.00 197,880.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 312,120.00 337,775.00
E Overhead & Profit (contoh 10%) 10% 31,212.00 33,777.50
F Harga Satuan Pekerjaan (D+E) 343,332.00 371,552.50

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 270,785.90 298,130.80
A Tenaga 42,175.00 46,425.00
L.01 0.300 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/115 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 203,994.00 224,603.00
12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
15.160 kg PC 1,150.00 1,175.00 17,434.00 17,813.00
0.364 m3 Pasir Pasang 340,000.00 370,000.00 123,760.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 246,169.00 271,028.00
E Overhead & Profit (contoh 10%) 10% 24,616.90 27,102.80
F Harga Satuan Pekerjaan (D+E) 270,785.90 298,130.80

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 275,928.95 303,982.53
A Tenaga 42,175.00 46,425.00
L.01 0.300 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 208,669.50 229,922.75
12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
12.130 kg PC 1,150.00 1,175.00 13,949.50 14,252.75
0.388 m3 Pasir Pasang 340,000.00 370,000.00 131,920.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 250,844.50 276,347.75
E Overhead & Profit (contoh 10%) 10% 25,084.45 27,634.78
F Harga Satuan Pekerjaan (D+E) 275,928.95 303,982.53

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 370,397.50 475,530.00
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 294,550.00 385,875.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,150.00 1,175.00 12,650.00 12,925.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 336,725.00 432,300.00
E Overhead & Profit (contoh 10%) 10% 33,672.50 43,230.00
F Harga Satuan Pekerjaan (D+E) 370,397.50 475,530.00

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 370,397.50 475,530.00
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 294,550.00 385,875.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,150.00 1,175.00 12,650.00 12,925.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 336,725.00 432,300.00
E Overhead & Profit (contoh 10%) 10% 33,672.50 43,230.00
F Harga Satuan Pekerjaan (D+E) 370,397.50 475,530.00

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 153,070.50 163,036.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 42,175.00 46,425.00
L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/116 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 96,980.00 101,790.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,150.00 1,175.00 16,100.00 16,450.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 139,155.00 148,215.00
E Overhead & Profit (contoh 10%) 10% 13,915.50 14,821.50
F Harga Satuan Pekerjaan (D+E) 153,070.50 163,036.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 316,081.04 341,319.06
Mortar Siap Pakai
m2 Tenaga 0.075 233,575.00 254,605.00
L.01 0.67 OH Pekerja 0.12 725000 90,000.00 100,000.00 60,300.00 67,000.00
L.02 1.3 OH Tukang Batu 1 6525 120,000.00 130,000.00 156,000.00 169,000.00
L.03 0.13 OH Kepala Tukang 13.3333333333333 130,000.00 140,000.00 16,900.00 18,200.00
L.04 0.003 OH Mandor 111.111111111111 125,000.00 135,000.00 375.00 405.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 287,346.40 310,290.05
E Overhead & Profit (contoh 10%) 10% 28,734.64 31,029.01
F Harga Satuan Pekerjaan (D+E) 316,081.04 341,319.06

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 316,655.24 339,901.71
Mortar Siap Pakai
m2 Tenaga 0.075 218,455.00 238,325.00
L.01 0.671 OH Pekerja 0.12 700000 90,000.00 100,000.00 60,390.00 67,100.00
L.02 1.300 OH Tukang Batu 0.1 8400 120,000.00 130,000.00 156,000.00 169,000.00
L.03 0.013 OH Kepala Tukang 10 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.003 OH Mandor 83.3333333333333 125,000.00 135,000.00 375.00 405.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 287,868.40 309,001.55
E Overhead & Profit (contoh 10%) 10% 28,786.84 30,900.16
F Harga Satuan Pekerjaan (D+E) 316,655.24 339,901.71

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/117 PEK.PASANGAN DINDING


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 79,304.06 85,538.42
A Tenaga 48,825.00 53,625.00
L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 23,269.60 24,137.20
15.504 Kg Portland Semen 1,150.00 1,175.00 17,829.60 18,217.20
0.016 m3 Pasir Pasang 340,000.00 370,000.00 5,440.00 5,920.00
C PERALATAN
D Jumlah A + B + C 72,094.60 77,762.20
E Overhead & Profit (contoh 10%) 10% 7,209.46 7,776.22
F Harga Satuan Pekerjaan (D+E) 79,304.06 85,538.42
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 74,120.86 80,342.02
A Tenaga 48,825.00 53,625.00

L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00


L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 18,557.60 19,413.20
10.224 Kg Portland Semen 1,150.00 1,175.00 11,757.60 12,013.20
0.020 m3 Pasir Pasang 340,000.00 370,000.00 6,800.00 7,400.00
C PERALATAN
D Jumlah A + B + C 67,382.60 73,038.20
E Overhead & Profit (contoh 10%) 10% 6,738.26 7,303.82
F Harga Satuan Pekerjaan (D+E) 74,120.86 80,342.02

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 72,146.14 78,398.98


A Tenaga 48,825.00 53,625.00

L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 16,762.40 17,646.80
7.776 Kg Portland Semen 1,150.00 1,175.00 8,942.40 9,136.80
0.023 m3 Pasir Pasang 340,000.00 370,000.00 7,820.00 8,510.00
C PERALATAN
D Jumlah A + B + C 65,587.40 71,271.80
E Overhead & Profit (contoh 10%) 10% 6,558.74 7,127.18
F Harga Satuan Pekerjaan (D+E) 72,146.14 78,398.98

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 70,577.10 76,820.70


A Tenaga 48,825.00 53,625.00
L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 15,336.00 16,212.00
6.240 Kg Portland Semen 1,150.00 1,175.00 7,176.00 7,332.00
0.024 m3 Pasir Pasang 340,000.00 370,000.00 8,160.00 8,880.00
C PERALATAN
D Jumlah A + B + C 64,161.00 69,837.00
E Overhead & Profit (contoh 10%) 10% 6,416.10 6,983.70
F Harga Satuan Pekerjaan (D+E) 70,577.10 76,820.70

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 69,989.26 76,269.82


A Tenaga 48,825.00 53,625.00
L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 14,801.60 15,711.20
5.184 Kg Portland Semen 1,150.00 1,175.00 5,961.60 6,091.20
0.026 m3 Pasir Pasang 340,000.00 370,000.00 8,840.00 9,620.00
C PERALATAN
D Jumlah A + B + C 63,626.60 69,336.20
E Overhead & Profit (contoh 10%) 10% 6,362.66 6,933.62
F Harga Satuan Pekerjaan (D+E) 69,989.26 76,269.82

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/118 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 69,391.74 75,684.18
Tenaga 48,825.00 53,625.00

L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 14,258.40 15,178.80
4.416 Kg Portland Semen 1,150.00 1,175.00 5,078.40 5,188.80
0.027 m3 Pasir Pasang 340,000.00 370,000.00 9,180.00 9,990.00
C PERALATAN
D Jumlah A + B + C 63,083.40 68,803.80
E Overhead & Profit (contoh 10%) 10% 6,308.34 6,880.38
F Harga Satuan Pekerjaan (D+E) 69,391.74 75,684.18

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 69,158.54 75,470.78


A Tenaga 48,825.00 53,625.00

L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 14,046.40 14,984.80
3.936 Kg Portland Semen 1,150.00 1,175.00 4,526.40 4,624.80
0.028 m3 Pasir Pasang 340,000.00 370,000.00 9,520.00 10,360.00
C PERALATAN
D Jumlah A + B + C 62,871.40 68,609.80
E Overhead & Profit (contoh 10%) 10% 6,287.14 6,860.98
F Harga Satuan Pekerjaan (D+E) 69,158.54 75,470.78

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 68,925.34 75,257.38


A Tenaga 48,825.00 53,625.00

L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 13,834.40 14,790.80
3.456 Kg Portland Semen 1,150.00 1,175.00 3,974.40 4,060.80
0.029 m3 Pasir Pasang 340,000.00 370,000.00 9,860.00 10,730.00
C PERALATAN
D Jumlah A + B + C 62,659.40 68,415.80
E Overhead & Profit (contoh 10%) 10% 6,265.94 6,841.58
F Harga Satuan Pekerjaan (D+E) 68,925.34 75,257.38

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 68,809.40 75,039.80


A Tenaga 50,610.00 55,710.00

L.01 0.36 OH Pekerja 90,000.00 100,000.00 32,400.00 36,000.00

L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 11,944.00 12,508.00
5.760 Kg Portland Semen 1,150.00 1,175.00 6,624.00 6,768.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
C PERALATAN
D Jumlah A + B + C 62,554.00 68,218.00
E Overhead & Profit (contoh 10%) 10% 6,255.40 6,821.80
F Harga Satuan Pekerjaan (D+E) 68,809.40 75,039.80

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 68,596.00 75,003.50


A Tenaga 50,610.00 55,710.00

L.01 0.36 OH Pekerja 90,000.00 100,000.00 32,400.00 36,000.00


L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 11,750.00 12,475.00
3 kg Portland Semen 1,150.00 1,175.00 3,450.00 3,525.00
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 340,000.00 370,000.00 6,800.00 7,400.00
C PERALATAN
D Jumlah A + B + C 62,360.00 68,185.00
E Overhead & Profit (contoh 10%) 10% 6,236.00 6,818.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/119 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 68,596.00 75,003.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/120 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 63,987.00 69,993.00
A Tenaga 50,610.00 55,710.00

L.01 0.36 OH Pekerja 90,000.00 100,000.00 32,400.00 36,000.00

L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 7,560.00 7,920.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 340,000.00 370,000.00 3,060.00 3,330.00
C PERALATAN
D Jumlah A + B + C 58,170.00 63,630.00
E Overhead & Profit (contoh 10%) 10% 5,817.00 6,363.00
F Harga Satuan Pekerjaan (D+E) 63,987.00 69,993.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 65,131.00 71,313.00


A Tenaga 50,610.00 55,710.00

L.01 0.36 OH Pekerja 90,000.00 100,000.00 32,400.00 36,000.00

L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 8,600.00 9,120.00
0.007 m3 Semen Merah 200,000.00 200,000.00 1,400.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 340,000.00 370,000.00 5,100.00 5,550.00
C PERALATAN
D Jumlah A + B + C 59,210.00 64,830.00
E Overhead & Profit (contoh 10%) 10% 5,921.00 6,483.00
F Harga Satuan Pekerjaan (D+E) 65,131.00 71,313.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 99,227.48 107,555.36


A Tenaga 65,350.00 71,770.00

L.01 0.40 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00

L.02 0.20 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 24,856.80 26,007.60
13.632 kg Portland Semen 1,150.00 1,175.00 15,676.80 16,017.60
0.027 m3 Pasir Pasang 340,000.00 370,000.00 9,180.00 9,990.00
C PERALATAN
D Jumlah A + B + C 90,206.80 97,777.60
E Overhead & Profit (contoh 10%) 10% 9,020.68 9,777.76
F Harga Satuan Pekerjaan (D+E) 99,227.48 107,555.36

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 74,088.20 80,207.40


A Tenaga 51,625.00 56,555.00
L.01 0.26 OH Pekerja 90,000.00 100,000.00 23,400.00 26,000.00
L.02 0.2 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 22,463.20 23,652.40
10.368 Kg Portland Semen 1,150.00 1,175.00 11,923.20 12,182.40
0.031 m3 Pasir Pasang 340,000.00 370,000.00 10,540.00 11,470.00
C PERALATAN
D Jumlah A + B + C 75,713.20 81,962.40
E Overhead & Profit (contoh 10%) 10% 7,571.32 8,196.24
F Harga Satuan Pekerjaan (D+E) 83,284.52 90,158.64

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 94,377.80 102,724.60


A Tenaga 65,350.00 71,770.00

L.01 0.40 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00

L.02 0.20 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00


L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 20,448.00 21,616.00
8.320 kg Portland Semen 1,150.00 1,175.00 9,568.00 9,776.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/121 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 85,798.00 93,386.00
E Overhead & Profit (contoh 10%) 10% 8,579.80 9,338.60
F Harga Satuan Pekerjaan (D+E) 94,377.80 102,724.60

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 93,718.68 102,125.76


A Tenaga 65,350.00 71,770.00
L.01 0.400 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00

L.02 0.200 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 19,848.80 21,071.60
6.912 Kg Portland Semen 1,150.00 1,175.00 7,948.80 8,121.60
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 85,198.80 92,841.60
E Overhead & Profit (contoh 10%) 10% 8,519.88 9,284.16
F Harga Satuan Pekerjaan (D+E) 93,718.68 102,125.76

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 92,797.32 101,209.24


A Tenaga 65,350.00 71,770.00

L.01 0.40 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00

L.02 0.2 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00


L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 19,011.20 20,238.40
5.888 Kg Portland Semen 1,150.00 1,175.00 6,771.20 6,918.40
0.036 m3 Pasir Pasang 340,000.00 370,000.00 12,240.00 13,320.00
C PERALATAN
D Jumlah A + B + C 84,361.20 92,008.40
E Overhead & Profit (contoh 10%) 10% 8,436.12 9,200.84
F Harga Satuan Pekerjaan (D+E) 92,797.32 101,209.24

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 90,453.00 98,890.00


A Tenaga 71,610.00 78,650.00
L.01 0.440 OH Pekerja 90,000.00 100,000.00 39,600.00 44,000.00

L.02 0.22 OH Tukang batu 120,000.00 130,000.00 26,400.00 28,600.00


L.03 0.022 OH Kepala Tukang 130,000.00 140,000.00 2,860.00 3,080.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 10,620.00 11,250.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
C PERALATAN
D Jumlah A + B + C 82,230.00 89,900.00
E Overhead & Profit (contoh 10%) 10% 8,223.00 8,990.00
F Harga Satuan Pekerjaan (D+E) 90,453.00 98,890.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 43,275.76 46,927.32


A Tenaga 24,540.00 26,950.00

L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00

L.02 0.075 OH Tukang batu 120,000.00 130,000.00 9,000.00 9,750.00


L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00

L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00


B Bahan 14,801.60 15,711.20
5.184 Kg Portland Semen 1,150.00 1,175.00 5,961.60 6,091.20
0.026 m3 Pasir Pasang 340,000.00 370,000.00 8,840.00 9,620.00
C PERALATAN
D Jumlah A + B + C 39,341.60 42,661.20
E Overhead & Profit (contoh 10%) 10% 3,934.16 4,266.12
F Harga Satuan Pekerjaan (D+E) 43,275.76 46,927.32

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 72,484.50 78,691.25

A Tenaga 60,900.00 66,140.00

L.01 0.080 OH Pekerja 90,000.00 100,000.00 7,200.00 8,000.00

L.02 0.40 OH Tukang batu 120,000.00 130,000.00 48,000.00 52,000.00

L.03 0.040 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00

L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/122 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,995.00 5,397.50
0.5 Kg Portland Semen 1,150.00 1,175.00 575.00 587.50
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
C PERALATAN
D Jumlah A + B + C 65,895.00 71,537.50
E Overhead & Profit (contoh 10%) 10% 6,589.50 7,153.75
F Harga Satuan Pekerjaan (D+E) 72,484.50 78,691.25

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 109,851.50 119,707.50
mm
A Tenaga 73,365.00 80,575.00
L.01 0.450 OH Pekerja 90,000.00 100,000.00 40,500.00 45,000.00
L.02 0.225 OH Tukang batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.023 OH Mandor 125,000.00 135,000.00 2,875.00 3,105.00
B Bahan 26,500.00 28,250.00
10 Kg Portland Semen 1,150.00 1,175.00 11,500.00 11,750.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 99,865.00 108,825.00
E Overhead & Profit (contoh 10%) 10% 9,986.50 10,882.50
F Harga Satuan Pekerjaan (D+E) 109,851.50 119,707.50

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 109,851.50 119,707.50

A Tenaga 73,365.00 80,575.00


L.01 0.450 OH Pekerja 90,000.00 100,000.00 40,500.00 45,000.00
L.02 0.225 OH Tukang batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.023 OH Mandor 125,000.00 135,000.00 2,875.00 3,105.00
B Bahan 26,500.00 28,250.00
10 Kg Portland Semen 1,150.00 1,175.00 11,500.00 11,750.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 99,865.00 108,825.00
E Overhead & Profit (contoh 10%) 10% 9,986.50 10,882.50
F Harga Satuan Pekerjaan (D+E) 109,851.50 119,707.50

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 54,101.30 59,093.10


Tenaga 42,175.00 46,425.00

L.01 0.30 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.1 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00

L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 7,008.00 7,296.00
4.32 Kg Portland Semen 1,150.00 1,175.00 4,968.00 5,076.00
0.006 m3 Pasir Pasang 340,000.00 370,000.00 2,040.00 2,220.00
C PERALATAN
D Jumlah A + B + C 49,183.00 53,721.00
E Overhead & Profit (contoh 10%) 10% 4,918.30 5,372.10
F Harga Satuan Pekerjaan (D+E) 54,101.30 59,093.10

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 30,925.62 33,662.09
Merah
A Tenaga 24,540.00 26,950.00

L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00

L.02 0.075 OH Tukang batu 120,000.00 130,000.00 9,000.00 9,750.00

L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00

L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00


B Bahan 3,574.20 3,651.90
3.108 Kg Portland Semen 1,150.00 1,175.00 3,574.20 3,651.90
C PERALATAN
D Jumlah A + B + C 28,114.20 30,601.90
E Overhead & Profit (contoh 10%) 10% 2,811.42 3,060.19
F Harga Satuan Pekerjaan (D+E) 30,925.62 33,662.09

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/123 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 14,696.00 15,983.00
ekspose
A Tenaga 11,520.00 12,650.00
L.01 0.070 OH Pekerja 90,000.00 100,000.00 6,300.00 7,000.00

L.02 0.035 OH Tukang batu 120,000.00 130,000.00 4,200.00 4,550.00

L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00

L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00


B Bahan 1,840.00 1,880.00
1.600 Kg Portland Semen 1,150.00 1,175.00 1,840.00 1,880.00
C PERALATAN
D Jumlah A + B + C 13,360.00 14,530.00
E Overhead & Profit (contoh 10%) 10% 1,336.00 1,453.00
F Harga Satuan Pekerjaan (D+E) 14,696.00 15,983.00

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 66,215.60 72,065.95
2Pp
Tenaga 48,825.00 53,625.00

L.01 0.3 OH Pekerja 90,000.00 100,000.00 27,000.00 30,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 11,371.00 11,889.50
6.34 Kg Portland Semen 1,150.00 1,175.00 7,291.00 7,449.50
0.012 m3 Pasir Pasang 340,000.00 370,000.00 4,080.00 4,440.00
C PERALATAN
D Jumlah A + B + C 60,196.00 65,514.50
E Overhead & Profit (contoh 10%) 10% 6,019.60 6,551.45
F Harga Satuan Pekerjaan (D+E) 66,215.60 72,065.95

27 A.4.4.2.27 1 m2 Pemasangan Acian 39,916.25 43,525.63

Tenaga 32,550.00 35,750.00


L.01 0.20 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 3,737.50 3,818.75
3.25 Kg Portland Semen 1,150.00 1,175.00 3,737.50 3,818.75
C PERALATAN
D Jumlah A + B + C 36,287.50 39,568.75
E Overhead & Profit (contoh 10%) 10% 3,628.75 3,956.88
F Harga Satuan Pekerjaan (D+E) 39,916.25 43,525.63

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 48,358.20 52,226.90

Tenaga 32,550.00 35,750.00


L.01 0.20 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 43,962.00 47,479.00
E Overhead & Profit (contoh 10%) 10% 4,396.20 4,747.90
F Harga Satuan Pekerjaan (D+E) 48,358.20 52,226.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 42,240.00 45,938.75

Tenaga 32,550.00 35,750.00


L.01 0.20 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 38,400.00 41,762.50
E Overhead & Profit (contoh 10%) 10% 3,840.00 4,176.25
F Harga Satuan Pekerjaan (D+E) 42,240.00 45,938.75

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/124 PEK.PLESTERAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3
dan DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 115,921.50 125,653.50


A Tenaga 40,815.00 44,825.00
L.01 0.25 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 64,568.18 69,405.45
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,181.82 3,454.55 37,768.18 41,005.45
10.0 Kg Portland Semen 0.3 1,150.00 1,175.00 11,500.00 11,750.00
0.0450 m3 Pasir Pasang 0.09 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN

D Jumlah A + B + C 105,383.18 114,230.45


E Overhead & Profit (contoh 10%) 10% 10,538.32 11,423.05
F Harga Satuan Pekerjaan (D+E) 115,921.50 125,653.50

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 118,107.00 128,139.00


A Tenaga 44,070.00 48,400.00
L.01 0.27 OH Pekerja 90,000.00 100,000.00 24,300.00 27,000.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.014 OH Kepala Tukang 130,000.00 140,000.00 1,820.00 1,960.00
L.04 0.014 OH Mandor 125,000.00 135,000.00 1,750.00 1,890.00
B Bahan 63,300.00 68,090.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 1,480.00 36,040.00 39,220.00
10.4 Kg Portland Semen 1,150.00 1,175.00 11,960.00 12,220.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 107,370.00 116,490.00
E Overhead & Profit (contoh 10%) 10% 10,737.00 11,649.00
F Harga Satuan Pekerjaan (D+E) 118,107.00 128,139.00

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 141,656.50 164,088.50


A Tenaga 42,315.00 46,475.00
L.01 0.26 OH Pekerja 90,000.00 100,000.00 23,400.00 26,000.00
L.02 0.130 OH Tukang Batu 120,000.00 130,000.00 15,600.00 16,900.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 86,463.64 102,696.36
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,363.64 43,163.64 51,796.36
10.0 Kg Portland Semen 1,150.00 1,175.00 11,500.00 11,750.00
1.50 Kg Semen warna 11,000.00 15,000.00 16,500.00 22,500.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 128,778.64 149,171.36
E Overhead & Profit (contoh 10%) 10% 12,877.86 14,917.14
F Harga Satuan Pekerjaan (D+E) 141,656.50 164,088.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 144,122.00 164,197.00


A Tenaga 44,070.00 48,400.00
L.01 0.27 OH Pekerja 90,000.00 100,000.00 24,300.00 27,000.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.014 OH Kepala Tukang 130,000.00 140,000.00 1,820.00 1,960.00
L.04 0.014 OH Mandor 125,000.00 135,000.00 1,750.00 1,890.00
B Bahan 86,950.00 100,870.00
26.5 Buah Ubin Warna 20x20 cm 1,580.00 1,800.00 41,870.00 47,700.00
10.4 Kg Portland Semen 1,150.00 1,175.00 11,960.00 12,220.00
1.62 Kg Semen warna 11,000.00 15,000.00 17,820.00 24,300.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 131,020.00 149,270.00
E Overhead & Profit (contoh 10%) 10% 13,102.00 14,927.00

F Harga Satuan Pekerjaan (D+E) 144,122.00 164,197.00


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 60 x 60 cm 344,437.50 391,039.00
A Tenaga 40,815.00 44,825.00
L.01 0.250 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 272,310.00 310,665.00
2.63 Buah Ubin Granito60x60 cm 0.4 88,000.00 100,000.00 231,440.00 263,000.00

9.8 Kg Portland Semen 0.16 1,150.00 1,175.00 11,270.00 11,515.00


1.300 Kg Semen warna 6.25 11,000.00 15,000.00 14,300.00 19,500.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 313,125.00 355,490.00
E Overhead & Profit (contoh 10%) 10% 31,312.50 35,549.00
F Harga Satuan Pekerjaan (D+E) 344,437.50 391,039.00

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 70,896.10 79,796.20

A Tenaga 20,695.00 22,635.00


L.01 0.090 OH Pekerja 90,000.00 100,000.00 8,100.00 9,000.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 43,756.00 49,907.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,150.00 1,175.00 1,426.00 1,457.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 64,451.00 72,542.00
E Overhead & Profit (contoh 10%) 10% 6,445.10 7,254.20
F Harga Satuan Pekerjaan (D+E) 70,896.10 79,796.20

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 41,696.60 45,275.45


A Tenaga 20,695.00 22,635.00
L.01 0.090 OH Pekerja 90,000.00 100,000.00 8,100.00 9,000.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 17,211.00 18,524.50
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,150.00 1,175.00 1,311.00 1,339.50
0.100 Kg Semen Warna 11,000.00 15,000.00 1,100.00 1,500.00

0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00


C PERALATAN
D Jumlah A + B + C 37,906.00 41,159.50
E Overhead & Profit (contoh 10%) 10% 3,790.60 4,115.95
F Harga Satuan Pekerjaan (D+E) 41,696.60 45,275.45

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 244,082.85 295,865.08


A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 107,968.50 143,843.25
53.00 Buah Keramik 10 x 20 cm 1,000.00 1,440.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,150.00 1,175.00 9,418.50 9,623.25
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00

C PERALATAN
D Jumlah A + B + C 221,893.50 268,968.25
E Overhead & Profit (contoh 10%) 10% 22,189.35 26,896.83
F Harga Satuan Pekerjaan (D+E) 244,082.85 295,865.08
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 249,527.85 303,290.08
A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 112,918.50 150,593.25
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 500.00 720.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,150.00 1,175.00 9,418.50 9,623.25
3.20 Kg Semen Warna 11,000.00 15,000.00 35,200.00 48,000.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 226,843.50 275,718.25
E Overhead & Profit (contoh 10%) 10% 22,684.35 27,571.83
F Harga Satuan Pekerjaan (D+E) 249,527.85 303,290.08

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 245,443.18 288,601.41


A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 109,205.17 137,239.92
10 Buah Ubin Keramik 33 x 33 cm 6,666.67 8,666.67 66,666.67 86,666.67
8.19 Kg Portland Semen 1,150.00 1,175.00 9,418.50 9,623.25

0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00


1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
C PERALATAN
D Jumlah A + B + C 223,130.17 262,364.92
E Overhead & Profit (contoh 10%) 10% 22,313.02 26,236.49
F Harga Satuan Pekerjaan (D+E) 245,443.18 288,601.41

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 244,167.50 286,213.50


A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 108,045.45 135,069.09
11.87 Buah Ubin Keramik 30 x 30 cm 5,454.55 7,090.91 64,745.45 84,169.09
10.00 Kg Portland Semen 1,150.00 1,175.00 11,500.00 11,750.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
1.50 Kg Semen Warna 11,000.00 15,000.00 16,500.00 22,500.00
C PERALATAN
D Jumlah A + B + C 221,970.45 260,194.09
E Overhead & Profit (contoh 10%) 10% 22,197.05 26,019.41
F Harga Satuan Pekerjaan (D+E) 244,167.50 286,213.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 244,865.50 284,740.50


A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 108,680.00 133,730.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,400.00 3,040.00 63,600.00 80,560.00
10.40 Kg Portland Semen 1,150.00 1,175.00 11,960.00 12,220.00
1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 222,605.00 258,855.00
E Overhead & Profit (contoh 10%) 10% 22,260.50 25,885.50
F Harga Satuan Pekerjaan (D+E) 244,865.50 284,740.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 467,395.50 524,821.00
variasi / border
A Tenaga 168,765.00 185,395.00
L.01 1.05 OH Pekerja 90,000.00 100,000.00 94,500.00 105,000.00
L.02 0.525 OH Tukang Batu 120,000.00 130,000.00 63,000.00 68,250.00
L.03 0.053 OH Kepala Tukang 130,000.00 140,000.00 6,890.00 7,420.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 256,140.00 291,715.00
33.0 Buah Ubin Keramik 5,500.00 6,000.00 181,500.00 198,000.00
9.80 Kg Portland Semen 1,150.00 1,175.00 11,270.00 11,515.00
4.37 Kg Semen Warna 11,000.00 15,000.00 48,070.00 65,550.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 424,905.00 477,110.00
E Overhead & Profit (contoh 10%) 10% 42,490.50 47,711.00
F Harga Satuan Pekerjaan (D+E) 467,395.50 524,821.00

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 43,121.10 46,952.95


A Tenaga 20,695.00 22,635.00
L.01 0.09 OH Pekerja 90,000.00 100,000.00 8,100.00 9,000.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 18,506.00 20,049.50
5.3 Buah Ubin Keramik 3,000.00 3,250.00 15,900.00 17,225.00
1.14 Kg Portland Semen 1,150.00 1,175.00 1,311.00 1,339.50
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.025 Kg Semen Warna 11,000.00 15,000.00 275.00 375.00
C PERALATAN
D Jumlah A + B + C 39,201.00 42,684.50
E Overhead & Profit (contoh 10%) 10% 3,920.10 4,268.45
F Harga Satuan Pekerjaan (D+E) 43,121.10 46,952.95

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 90,063.60 98,377.95


A Tenaga 20,695.00 22,635.00
L.01 0.09 OH Pekerja 90,000.00 100,000.00 8,100.00 9,000.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 61,181.00 66,799.50
10.6 Buah Ubin Keramik 5,500.00 6,000.00 58,300.00 63,600.00
1.14 Kg Portland Semen 1,150.00 1,175.00 1,311.00 1,339.50
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 81,876.00 89,434.50
E Overhead & Profit (contoh 10%) 10% 8,187.60 8,943.45
F Harga Satuan Pekerjaan (D+E) 90,063.60 98,377.95

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 90,063.60 98,377.95


A Tenaga 20,695.00 22,635.00
L.01 0.09 OH Pekerja 90,000.00 100,000.00 8,100.00 9,000.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 61,181.00 66,799.50
10.6 Buah Ubin Keramik 5,500.00 6,000.00 58,300.00 63,600.00
1.14 Kg Portland Semen 1,150.00 1,175.00 1,311.00 1,339.50
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 81,876.00 89,434.50
E Overhead & Profit (contoh 10%) 10% 8,187.60 8,943.45
F Harga Satuan Pekerjaan (D+E) 90,063.60 98,377.95
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 714,222.85 736,943.08
A Tenaga 113,925.00 125,125.00
L.01 0.7 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 535,368.50 544,823.25
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,150.00 1,175.00 9,418.50 9,623.25
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 649,293.50 669,948.25
E Overhead & Profit (contoh 10%) 10% 64,929.35 66,994.83
F Harga Satuan Pekerjaan (D+E) 714,222.85 736,943.08

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 208,488.50 222,139.50


A Tenaga 39,035.00 42,695.00
L.01 0.17 OH Pekerja 90,000.00 100,000.00 15,300.00 17,000.00
L.02 0.17 OH Tukang Batu 120,000.00 130,000.00 20,400.00 22,100.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 189,535.00 201,945.00
E Overhead & Profit (contoh 10%) 10% 18,953.50 20,194.50
F Harga Satuan Pekerjaan (D+E) 208,488.50 222,139.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 473,467.50 538,587.50


A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 316,500.00 364,500.00
1.05 m2 Parquet Jati 270,000.00 310,000.00 283,500.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 430,425.00 489,625.00
E Overhead & Profit (contoh 10%) 10% 43,042.50 48,962.50
F Harga Satuan Pekerjaan (D+E) 473,467.50 538,587.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 279,250.16 310,953.57


A Tenaga 162,750.00 178,750.00
L.01 1.00 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 0.50 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.050 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 91,113.78 103,935.06
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,150.00 1,175.00 10,695.00 10,927.50

2.750 Kg Semen Warna 0.0121 11,000.00 15,000.00 30,250.00 41,250.00

0.018 m3 Pasir Pasang 0.11 340,000.00 370,000.00 6,120.00 6,660.00


C PERALATAN
D Jumlah A + B + C 253,863.78 282,685.06
E Overhead & Profit (contoh 10%) 10% 25,386.38 28,268.51
F Harga Satuan Pekerjaan (D+E) 279,250.16 310,953.57

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 271,194.00 325,635.75


A Tenaga 146,475.00 160,875.00
L.01 0.9 OH Pekerja 90,000.00 100,000.00 81,000.00 90,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 100,065.00 135,157.50
53 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,150.00 1,175.00 10,695.00 10,927.50
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 246,540.00 296,032.50
E Overhead & Profit (contoh 10%) 10% 24,654.00 29,603.25
F Harga Satuan Pekerjaan (D+E) 271,194.00 325,635.75

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 266,013.00 312,974.75


A Tenaga 146,475.00 160,875.00
L.01 0.9 OH Pekerja 90,000.00 100,000.00 81,000.00 90,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 95,355.00 123,647.50
26.0 Buah Keramik 2,200.00 2,960.00 57,200.00 76,960.00
9.3 Kg Portland Semen 1,150.00 1,175.00 10,695.00 10,927.50
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 241,830.00 284,522.50
E Overhead & Profit (contoh 10%) 10% 24,183.00 28,452.25
F Harga Satuan Pekerjaan (D+E) 266,013.00 312,974.75

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 271,194.00 325,635.75


A Tenaga 146,475.00 160,875.00
L.01 0.9 OH Pekerja 90,000.00 100,000.00 81,000.00 90,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 100,065.00 135,157.50
53.0 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,150.00 1,175.00 10,695.00 10,927.50
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 246,540.00 296,032.50
E Overhead & Profit (contoh 10%) 10% 24,654.00 29,603.25
F Harga Satuan Pekerjaan (D+E) 271,194.00 325,635.75

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 267,223.00 314,602.75


A Tenaga 146,475.00 160,875.00
L.01 0.9 OH Pekerja 90,000.00 100,000.00 81,000.00 90,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 96,455.00 125,127.50
26.5 Buah Keramik 2,200.00 2,960.00 58,300.00 78,440.00
9.3 Kg Portland Semen 1,150.00 1,175.00 10,695.00 10,927.50
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 242,930.00 286,002.50
E Overhead & Profit (contoh 10%) 10% 24,293.00 28,600.25
F Harga Satuan Pekerjaan (D+E) 267,223.00 314,602.75

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 820,690.26 853,427.36


A Tenaga 211,575.00 232,375.00
L.01 1.3 OH Pekerja 90,000.00 100,000.00 117,000.00 130,000.00
L.02 0.65 OH Tukang Batu 120,000.00 130,000.00 78,000.00 84,500.00
L.03 0.065 OH Kepala Tukang 130,000.00 140,000.00 8,450.00 9,100.00
L.04 0.065 OH Mandor 125,000.00 135,000.00 8,125.00 8,775.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 534,507.05 543,468.05
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 350.00 350.00 1,051.05 1,051.05
12.44 kg Portlan Semen 1,150.00 1,175.00 14,306.00 14,617.00
0.025 m3 Pasir Pasang 340,000.00 370,000.00 8,500.00 9,250.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 746,082.05 775,843.05
E Overhead & Profit (contoh 10%) 10% 74,608.21 77,584.31
F Harga Satuan Pekerjaan (D+E) 820,690.26 853,427.36

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 286,371.25 306,219.38
A Tenaga 113,925.00 125,125.00
L.01 0.70 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 146,412.50 153,256.25
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,150.00 1,175.00 13,512.50 13,806.25
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 260,337.50 278,381.25
E Overhead & Profit (contoh 10%) 10% 26,033.75 27,838.13
F Harga Satuan Pekerjaan (D+E) 286,371.25 306,219.38

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 156,534.40 169,185.50


A Tenaga 54,960.00 60,400.00
L.01 0.35 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.175 OH Tukang Batu 120,000.00 130,000.00 21,000.00 22,750.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 142,304.00 153,805.00
E Overhead & Profit (contoh 10%) 10% 14,230.40 15,380.50
F Harga Satuan Pekerjaan (D+E) 156,534.40 169,185.50

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 126,401.00 135,905.00


A Tenaga 54,960.00 60,400.00
L.01 0.35 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 0.175 OH Tukang Batu 120,000.00 130,000.00 21,000.00 22,750.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 59,950.00 63,150.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 11,000.00 15,000.00 2,750.00 3,750.00
C PERALATAN
D Jumlah A + B + C 114,910.00 123,550.00
E Overhead & Profit (contoh 10%) 10% 11,491.00 12,355.00
F Harga Satuan Pekerjaan (D+E) 126,401.00 135,905.00

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 58,806.00 63,019.00
Tenaga 27,510.00 30,090.00
L.01 0.12 OH Pekerja 90,000.00 100,000.00 10,800.00 12,000.00
L.02 0.12 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
Bahan 25,950.00 27,200.00
0.003 m3 Papan Kayu Klas II 8,400,000.00 8,800,000.00 25,200.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 53,460.00 57,290.00
E Overhead & Profit (contoh 10%) 10% 5,346.00 5,729.00
F Harga Satuan Pekerjaan (D+E) 58,806.00 63,019.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 193,184.75 215,430.05


Tenaga 89,162.50 97,175.50
L.01 0.25 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 78,600.00 89,700.00
1.01 m2 Paving Block Tebal 6 Cm 60,000.00 70,000.00 60,600.00 70,700.00
0.05 m3 Pasir Beton 360,000.00 380,000.00 18,000.00 19,000.00
C PERALATAN 7,860.00 8,970.00
10 % Peralatan 78,600.00 89,700.00 7,860.00 8,970.00
D Jumlah A + B + C 175,622.50 195,845.50
E Overhead & Profit (contoh 10%) 10% 17,562.25 19,584.55
F Harga Satuan Pekerjaan (D+E) 193,184.75 215,430.05

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 257,199.25 276,568.05


Tenaga 111,662.50 122,175.50
L.01 0.5 OH Pekerja 90,000.00 100,000.00 45,000.00 50,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 111,050.00 117,500.00
1.01 m2 Paving Block Tebal 8 Cm 85,000.00 90,000.00 85,850.00 90,900.00
0.07 m3 Pasir Beton 360,000.00 380,000.00 25,200.00 26,600.00
C PERALATAN 11,105.00 11,750.00
10 % Peralatan 111,050.00 117,500.00 11,105.00 11,750.00
D Jumlah A + B + C 233,817.50 251,425.50
E Overhead & Profit (contoh 10%) 10% 23,381.75 25,142.55
F Harga Satuan Pekerjaan (D+E) 257,199.25 276,568.05

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 205,405.75 227,651.05


Tenaga 89,162.50 97,175.50
L.01 0.25 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 88,700.00 99,800.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 70,000.00 80,000.00 70,700.00 80,800.00
0.05 m3 Pasir Beton 360,000.00 380,000.00 18,000.00 19,000.00
C PERALATAN 8,870.00 9,980.00
10 % Peralatan 88,700.00 99,800.00 8,870.00 9,980.00
D Jumlah A + B + C 186,732.50 206,955.50
E Overhead & Profit (contoh 10%) 10% 18,673.25 20,695.55
F Harga Satuan Pekerjaan (D+E) 205,405.75 227,651.05

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 263,309.75 282,678.55


Tenaga 111,662.50 122,175.50
L.01 0.5 OH Pekerja 90,000.00 100,000.00 45,000.00 50,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 116,100.00 122,550.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 90,000.00 95,000.00 90,900.00 95,950.00
0.07 m3 Pasir Beton 360,000.00 380,000.00 25,200.00 26,600.00
C PERALATAN 11,610.00 12,255.00
10 % Peralatan 116,100.00 122,550.00 11,610.00 12,255.00
D Jumlah A + B + C 239,372.50 256,980.50
E Overhead & Profit (contoh 10%) 10% 23,937.25 25,698.05
F Harga Satuan Pekerjaan (D+E) 263,309.75 282,678.55
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 32,708.50 39,380.00
mm, 5 mm & 6 mm

A Tenaga 12,510.00 13,620.00


L.01 0.03 OH Pekerja 90,000.00 100,000.00 2,700.00 3,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 17,225.00 22,180.00
1.1 Lbr Plat Asbes 15,500.00 20,000.00 17,050.00 22,000.00
0.01 Kg Paku 17,500.00 18,000.00 175.00 180.00
C PERALATAN
D Jumlah A + B + C 29,735.00 35,800.00
E Overhead & Profit (contoh 10%) 10% 2,973.50 3,580.00
F Harga Satuan Pekerjaan (D+E) 32,708.50 39,380.00
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 107,783.50 119,889.00
A Tenaga 27,510.00 30,090.00
L.01 0.12 OH Pekerja 90,000.00 100,000.00 10,800.00 12,000.00
L.02 0.12 OH Tukang Kayu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 70,475.00 78,900.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,500.00 69,600.00 78,000.00
0.05 Kg Paku 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 97,985.00 108,990.00
E Overhead & Profit (contoh 10%) 10% 9,798.50 10,899.00
F Harga Satuan Pekerjaan (D+E) 107,783.50 119,889.00

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 110,396.00 121,082.50


A Tenaga 22,925.00 25,075.00
L.01 0.10 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 77,435.00 85,000.00
5.80 Lbr Akustik 13,200.00 14,500.00 76,560.00 84,100.00
0.05 Kg Paku 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 100,360.00 110,075.00
E Overhead & Profit (contoh 10%) 10% 10,036.00 11,007.50
F Harga Satuan Pekerjaan (D+E) 110,396.00 121,082.50

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 95,480.00 104,472.50


A Tenaga 22,925.00 25,075.00
L.01 0.10 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 63,875.00 69,900.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 86,800.00 94,975.00
E Overhead & Profit (contoh 10%) 10% 8,680.00 9,497.50
F Harga Satuan Pekerjaan (D+E) 95,480.00 104,472.50

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 52,607.50 57,051.50
mm, 4 mm & 6 mm

A Tenaga 22,925.00 25,075.00


L.01 0.10 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/133 PEK.LANGIT-LANGIT


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 24,900.00 26,790.00
0.375 Lbr Tripleks (4 mm) 65,000.00 70,000.00 24,375.00 26,250.00
0.03 Kg Paku Tripleks 17,500.00 18,000.00 525.00 540.00
C PERALATAN
D Jumlah A + B + C 47,825.00 51,865.00
E Overhead & Profit (contoh 10%) 10% 4,782.50 5,186.50
F Harga Satuan Pekerjaan (D+E) 52,607.50 57,051.50

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 663,932.50 699,358.00


A Tenaga 183,400.00 200,600.00
L.01 0.8 OH Pekerja 90,000.00 100,000.00 72,000.00 80,000.00
L.02 0.8 OH Tukang Kayu 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.04 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 420,175.00 435,180.00
0.015 m3 Kayu Jati,Papan 28,000,000.00 29,000,000.00 420,000.00 435,000.00
0.01 Kg Paku 17,500.00 18,000.00 175.00 180.00
C PERALATAN
D Jumlah A + B + C 603,575.00 635,780.00
E Overhead & Profit (contoh 10%) 10% 60,357.50 63,578.00
F Harga Satuan Pekerjaan (D+E) 663,932.50 699,358.00

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 43,741.50 48,765.20
tebal 9 mm

A Tenaga 16,275.00 17,875.00


L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 23,490.00 26,457.00
0.364 Lbr Gypsum Board 60,000.00 68,000.00 21,840.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 39,765.00 44,332.00
E Overhead & Profit (contoh 10%) 10% 3,976.50 4,433.20
F Harga Satuan Pekerjaan (D+E) 43,741.50 48,765.20

Memasang Langit-langit Akuatik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 235,152.50 256,217.50
Rangka Allumunium

A Tenaga 114,625.00 125,375.00


L.01 0.5 OH Pekerja 90,000.00 100,000.00 45,000.00 50,000.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B Bahan 99,150.00 107,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 213,775.00 232,925.00
E Overhead & Profit (contoh 10%) 10% 21,377.50 23,292.50
F Harga Satuan Pekerjaan (D+E) 235,152.50 256,217.50

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 18,414.00 19,838.50


A Tenaga 11,525.00 12,605.00
L.01 0.05 OH Pekerja 90,000.00 100,000.00 4,500.00 5,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,215.00 5,430.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 17,500.00 18,000.00 175.00 180.00
C PERALATAN
D Jumlah A + B + C 16,740.00 18,035.00
E Overhead & Profit (contoh 10%) 10% 1,674.00 1,803.50
F Harga Satuan Pekerjaan (D+E) 18,414.00 19,838.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/134 PEK.LANGIT-LANGIT


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 90,172.50 101,068.00
A Tenaga 24,475.00 26,880.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.0075 OH Kepala Tukang 130,000.00 140,000.00 975.00 1,050.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 57,500.00 65,000.00
25 Buah Genteng Plentong 2,300.00 2,600.00 57,500.00 65,000.00
C PERALATAN
D Jumlah A + B + C 81,975.00 91,880.00
E Overhead & Profit (contoh 10%) 10% 8,197.50 9,188.00
F Harga Satuan Pekerjaan (D+E) 90,172.50 101,068.00

Overhead & Profit (contoh 10%)


2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 143,869.00 149,270.00
A Tenaga 24,540.00 26,950.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 106,250.00 108,750.00
25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00
C PERALATAN
D Jumlah A + B + C 130,790.00 135,700.00
E Overhead & Profit (contoh 10%) 10% 13,079.00 13,570.00
F Harga Satuan Pekerjaan (D+E) 143,869.00 149,270.00

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 127,974.00 135,575.00


A Tenaga 24,540.00 26,950.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 91,800.00 96,300.00
12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 116,340.00 123,250.00
E Overhead & Profit (contoh 10%) 10% 11,634.00 12,325.00
F Harga Satuan Pekerjaan (D+E) 127,974.00 135,575.00

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 114,598.00 123,266.00


A Tenaga 62,850.00 69,070.00
L.01 0.4 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 41,330.00 42,990.00
5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00
8 Kg Portland Semen 1,150.00 1,175.00 9,200.00 9,400.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 104,180.00 112,060.00
E Overhead & Profit (contoh 10%) 10% 10,418.00 11,206.00
F Harga Satuan Pekerjaan (D+E) 114,598.00 123,266.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/135 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 126,973.00 136,741.00
A Tenaga 62,850.00 69,070.00
L.01 0.4 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 52,580.00 55,240.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,150.00 1,175.00 9,200.00 9,400.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 115,430.00 124,310.00
E Overhead & Profit (contoh 10%) 10% 11,543.00 12,431.00
F Harga Satuan Pekerjaan (D+E) 126,973.00 136,741.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 130,823.00 139,821.00


A Tenaga 62,850.00 69,070.00
L.01 0.4 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 56,080.00 58,040.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,150.00 1,175.00 9,200.00 9,400.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 118,930.00 127,110.00
E Overhead & Profit (contoh 10%) 10% 11,893.00 12,711.00
F Harga Satuan Pekerjaan (D+E) 130,823.00 139,821.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 108,130.00 120,488.50


A Tenaga 22,425.00 24,635.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.067 OH Tukang Kayu 120,000.00 130,000.00 8,040.00 8,710.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 75,875.00 84,900.00
0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00
0.05 Kg Paku Biasa 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 98,300.00 109,535.00
E Overhead & Profit (contoh 10%) 10% 9,830.00 10,953.50
F Harga Satuan Pekerjaan (D+E) 108,130.00 120,488.50

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 67,375.00 75,383.00
mm

A Tenaga 23,640.00 25,950.00


L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 37,610.00 42,580.00
0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,250.00 68,530.00
E Overhead & Profit (contoh 10%) 10% 6,125.00 6,853.00
F Harga Satuan Pekerjaan (D+E) 67,375.00 75,383.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/136 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 69,019.50 77,357.50
mm

A Tenaga 22,785.00 25,025.00


L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 62,745.00 70,325.00
E Overhead & Profit (contoh 10%) 10% 6,274.50 7,032.50
F Harga Satuan Pekerjaan (D+E) 69,019.50 77,357.50

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 69,349.50 78,017.50
mm

A Tenaga 22,785.00 25,025.00


L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 40,260.00 45,900.00
0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 63,045.00 70,925.00
E Overhead & Profit (contoh 10%) 10% 6,304.50 7,092.50
F Harga Satuan Pekerjaan (D+E) 69,349.50 78,017.50

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 76,609.50 80,855.50
mm

A Tenaga 22,785.00 25,025.00


L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 46,860.00 48,480.00
0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 69,645.00 73,505.00
E Overhead & Profit (contoh 10%) 10% 6,964.50 7,350.50
F Harga Satuan Pekerjaan (D+E) 76,609.50 80,855.50

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 59,642.00 75,520.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 31,435.00 43,630.00
0.35 Lbr Asbes Gelombang 84,500.00 119,000.00 29,575.00 41,650.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,220.00 68,655.00
E Overhead & Profit (contoh 10%) 10% 5,422.00 6,865.50
F Harga Satuan Pekerjaan (D+E) 59,642.00 75,520.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/137 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 61,759.50 77,753.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 33,360.00 45,660.00
0.42 Lbr Asbes Gelombang 75,000.00 104,000.00 31,500.00 43,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,145.00 70,685.00
E Overhead & Profit (contoh 10%) 10% 5,614.50 7,068.50
F Harga Satuan Pekerjaan (D+E) 61,759.50 77,753.50

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 59,779.50 76,169.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 31,560.00 44,220.00
0.44 Lbr Asbes Gelombang 67,500.00 96,000.00 29,700.00 42,240.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,345.00 69,245.00
E Overhead & Profit (contoh 10%) 10% 5,434.50 6,924.50
F Harga Satuan Pekerjaan (D+E) 59,779.50 76,169.50

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 60,489.00 75,146.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 32,205.00 43,290.00
0.51 Lbr Asbes Gelombang 59,500.00 81,000.00 30,345.00 41,310.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,990.00 68,315.00
E Overhead & Profit (contoh 10%) 10% 5,499.00 6,831.50
F Harga Satuan Pekerjaan (D+E) 60,489.00 75,146.50

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 64,069.50 78,105.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 35,460.00 45,980.00
0.80 Lbr Asbes Gelombang 42,000.00 55,000.00 33,600.00 44,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,245.00 71,005.00
E Overhead & Profit (contoh 10%) 10% 5,824.50 7,100.50
F Harga Satuan Pekerjaan (D+E) 64,069.50 78,105.50

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 69,030.50 72,440.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/138 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/139 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 62,755.00 65,855.00
E Overhead & Profit (contoh 10%) 10% 6,275.50 6,585.50
F Harga Satuan Pekerjaan (D+E) 69,030.50 72,440.50

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 72,385.50 75,905.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 65,805.00 69,005.00
E Overhead & Profit (contoh 10%) 10% 6,580.50 6,900.50
F Harga Satuan Pekerjaan (D+E) 72,385.50 75,905.50

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 69,217.50 73,265.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 62,925.00 66,605.00
E Overhead & Profit (contoh 10%) 10% 6,292.50 6,660.50
F Harga Satuan Pekerjaan (D+E) 69,217.50 73,265.50

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 70,229.50 74,442.50
mm

A Tenaga 22,785.00 25,025.00


L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 63,845.00 67,675.00
E Overhead & Profit (contoh 10%) 10% 6,384.50 6,767.50
F Harga Satuan Pekerjaan (D+E) 70,229.50 74,442.50

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 74,134.50 77,984.50
mm
A Tenaga 22,785.00 25,025.00
L.01 0.14 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 67,395.00 70,895.00
E Overhead & Profit (contoh 10%) 10% 6,739.50 7,089.50
F Harga Satuan Pekerjaan (D+E) 74,134.50 77,984.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/140 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 113,822.50 127,039.00
A Tenaga 32,550.00 35,750.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 70,925.00 79,740.00
11 Lbr Genteng Beton Standrad 6,400.00 7,200.00 70,400.00 79,200.00
0.03 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 525.00 540.00
C PERALATAN
D Jumlah A + B + C 103,475.00 115,490.00
E Overhead & Profit (contoh 10%) 10% 10,347.50 11,549.00
F Harga Satuan Pekerjaan (D+E) 113,822.50 127,039.00

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 230,576.50 256,201.00


A Tenaga 55,640.00 60,770.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.3 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 153,975.00 172,140.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 86,000.00 26,250.00 30,100.00
0.03 kg Paku Biasa 2" - 5" 17,500.00 18,000.00 525.00 540.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 209,615.00 232,910.00
E Overhead & Profit (contoh 10%) 10% 20,961.50 23,291.00
F Harga Satuan Pekerjaan (D+E) 230,576.50 256,201.00

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 95,755.00 110,605.00


A Tenaga 32,550.00 35,750.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 54,500.00 64,800.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 17,500.00 18,000.00 3,500.00 3,600.00
C PERALATAN
D Jumlah A + B + C 87,050.00 100,550.00
E Overhead & Profit (contoh 10%) 10% 8,705.00 10,055.00
F Harga Satuan Pekerjaan (D+E) 95,755.00 110,605.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 120,659.00 132,308.00


A Tenaga 49,190.00 53,680.00
L.01 0.166 OH Pekerja 90,000.00 100,000.00 14,940.00 16,600.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 60,500.00 66,600.00
30 Lbr Genteng Sirap 1,900.00 2,100.00 57,000.00 63,000.00
0.2 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 3,500.00 3,600.00
C PERALATAN
D Jumlah A + B + C 109,690.00 120,280.00
E Overhead & Profit (contoh 10%) 10% 10,969.00 12,028.00
F Harga Satuan Pekerjaan (D+E) 120,659.00 132,308.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 136,317.50 148,973.00


A Tenaga 65,100.00 71,500.00
L.01 0.4 OH Pekerja 90,000.00 100,000.00 36,000.00 40,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.02 OH Mandor 125,000.00 135,000.00 2,500.00 2,700.00
B Bahan 58,825.00 63,930.00
3.5 Buah Nok Genteng Beton 9,900.00 11,000.00 34,650.00 38,500.00
0.05 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 875.00 900.00
10.8 Kg Portland Semen 1,150.00 1,175.00 12,420.00 12,690.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
1 Kg Semen Warna 11,000.00 15,000.00 11,000.00 15,000.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/141 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 123,925.00 135,430.00
E Overhead & Profit (contoh 10%) 10% 12,392.50 13,543.00
F Harga Satuan Pekerjaan (D+E) 136,317.50 148,973.00

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 137,362.50 147,411.00


A Tenaga 45,250.00 49,310.00
L.01 0.125 OH Pekerja 90,000.00 100,000.00 11,250.00 12,500.00
L.02 0.250 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 79,625.00 84,700.00
2.0 Buah Nok Genteng Beton 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 875.00 900.00
0.0035 m3 Balok Kayu 6,500,000.00 6,800,000.00 22,750.00 23,800.00
C PERALATAN
D Jumlah A + B + C 124,875.00 134,010.00
E Overhead & Profit (contoh 10%) 10% 12,487.50 13,401.00
F Harga Satuan Pekerjaan (D+E) 137,362.50 147,411.00

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 73,645.00 81,405.50


A Tenaga 44,075.00 48,355.00
L.01 0.250 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.150 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 22,875.00 25,650.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 875.00 900.00

C PERALATAN
D Jumlah A + B + C 66,950.00 74,005.00
E Overhead & Profit (contoh 10%) 10% 6,695.00 7,400.50
F Harga Satuan Pekerjaan (D+E) 73,645.00 81,405.50

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 63,552.50 69,619.00


A Tenaga 45,250.00 49,310.00
L.01 0.125 OH Pekerja 90,000.00 100,000.00 11,250.00 12,500.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 12,525.00 13,980.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 10,600.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 1,050.00 1,080.00
0.05 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 875.00 900.00

C PERALATAN
D Jumlah A + B + C 57,775.00 63,290.00
E Overhead & Profit (contoh 10%) 10% 5,777.50 6,329.00
F Harga Satuan Pekerjaan (D+E) 63,552.50 69,619.00

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 42,273.00 47,091.00


A Tenaga 19,530.00 21,450.00
L.01 0.12 OH Pekerja 90,000.00 100,000.00 10,800.00 12,000.00
L.02 0.06 OH Tukang Kayu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 18,900.00 21,360.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,500.00 30,000.00 18,550.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 350.00 360.00
C PERALATAN
D Jumlah A + B + C 38,430.00 42,810.00
E Overhead & Profit (contoh 10%) 10% 3,843.00 4,281.00
F Harga Satuan Pekerjaan (D+E) 42,273.00 47,091.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/142 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 35,431.00 39,171.00
A Tenaga 23,560.00 25,890.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 8,650.00 9,720.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 7,950.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 700.00 720.00
C PERALATAN
D Jumlah A + B + C 32,210.00 35,610.00
E Overhead & Profit (contoh 10%) 10% 3,221.00 3,561.00
F Harga Satuan Pekerjaan (D+E) 35,431.00 39,171.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 37,125.00 42,933.00


A Tenaga 21,150.00 23,280.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 12,600.00 15,750.00
1.05 m2 Sisalation / Allumunium Foil 12,000.00 15,000.00 12,600.00 15,750.00
C PERALATAN
D Jumlah A + B + C 33,750.00 39,030.00
E Overhead & Profit (contoh 10%) 10% 3,375.00 3,903.00
F Harga Satuan Pekerjaan (D+E) 37,125.00 42,933.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/143 PEK.PENUTUP ATAP


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 34,101,237.50 35,655,125.00
Kayu klas I
A Tenaga 3,466,750.00 3,771,250.00
L.01 7 OH Pekerja 90,000.00 100,000.00 630,000.00 700,000.00
L.02 21 OH Tukang Kayu 120,000.00 130,000.00 2,520,000.00 2,730,000.00
L.03 2.10 OH Kepala Tukang 130,000.00 140,000.00 273,000.00 294,000.00
L.04 0.35 OH Mandor 125,000.00 135,000.00 43,750.00 47,250.00
B Bahan 27,534,375.00 28,642,500.00
1.1 m3 Kayu Klas I (Jati) , Balok 25,000,000.00 26,000,000.00 27,500,000.00 28,600,000.00
1.25 kg Paku Biasa 2" - 5 " 17,500.00 18,000.00 21,875.00 22,500.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 31,001,125.00 32,413,750.00
E Overhead & Profit (contoh 10%) 10% 3,100,112.50 3,241,375.00
F Harga Satuan Pekerjaan (D+E) 34,101,237.50 35,655,125.00

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 14,394,462.50 14,954,500.00
Kayu klas II atau III
Tenaga 2,971,500.00 3,232,500.00
L.01 6.00 OH Pekerja 90,000.00 100,000.00 540,000.00 600,000.00
L.02 18.00 OH Tukang Kayu 120,000.00 130,000.00 2,160,000.00 2,340,000.00
L.03 1.80 OH Kepala Tukang 130,000.00 140,000.00 234,000.00 252,000.00
L.04 0.30 OH Mandor 125,000.00 135,000.00 37,500.00 40,500.00
Bahan 10,114,375.00 10,362,500.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 8,400,000.00 8,600,000.00 10,080,000.00 10,320,000.00
1.25 kg Paku Biasa 2" - 5 " 17,500.00 18,000.00 21,875.00 22,500.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 13,085,875.00 13,595,000.00
E Overhead & Profit (contoh 10%) 10% 1,308,587.50 1,359,500.00
F Harga Satuan Pekerjaan (D+E) 14,394,462.50 14,954,500.00

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 574,502.50 595,683.00
Kayu Klas II (Kayu Kamfer)
A Tenaga 173,400.00 188,630.00
L.01 0.35 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 1.05 OH Tukang Kayu 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 348,875.00 352,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.05 Kg Paku Biasa 2" - 5 " 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 522,275.00 541,530.00
E Overhead & Profit (contoh 10%) 10% 52,227.50 54,153.00
F Harga Satuan Pekerjaan (D+E) 574,502.50 595,683.00

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 574,502.50 595,683.00
Sederhana Kayu Klas III
Tenaga 173,400.00 188,630.00
L.01 0.35 OH Pekerja 90,000.00 100,000.00 31,500.00 35,000.00
L.02 1.05 OH Tukang Kayu 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
Bahan 348,875.00 352,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.05 Kg Paku Biasa 2" - 5 " 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 522,275.00 541,530.00
E Overhead & Profit (contoh 10%) 10% 52,227.50 54,153.00
F Harga Satuan Pekerjaan (D+E) 574,502.50 595,683.00

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 928,262.50 980,925.00
Klas I atau II
A Tenaga 495,250.00 538,750.00
L.01 1.00 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 3.00 OH Tukang Kayu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.30 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 348,625.00 353,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 843,875.00 891,750.00
E Overhead & Profit (contoh 10%) 10% 84,387.50 89,175.00
F Harga Satuan Pekerjaan (D+E) 928,262.50 980,925.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/144 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 669,625.00 713,020.00
Kayu Klas I atau II
A Tenaga 396,200.00 431,000.00
L.01 0.800 OH Pekerja 90,000.00 100,000.00 72,000.00 80,000.00
L.02 2.400 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.240 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.040 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 212,550.00 217,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 208,800.00 211,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 608,750.00 648,200.00
E Overhead & Profit (contoh 10%) 10% 60,875.00 64,820.00
F Harga Satuan Pekerjaan (D+E) 669,625.00 713,020.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 2,522,850.00 2,645,225.00
Kayu Klas I atau II (jati)
A Tenaga 495,250.00 538,750.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 3 OH Tukang Kayu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.3 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,798,250.00 1,866,000.00
0.064 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 1,792,000.00 1,856,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 2,293,500.00 2,404,750.00
E Overhead & Profit (contoh 10%) 10% 229,350.00 240,475.00
F Harga Satuan Pekerjaan (D+E) 2,522,850.00 2,645,225.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 699,545.00 761,931.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 346,675.00 377,125.00


L.01 0.700 OH Pekerja 90,000.00 100,000.00 63,000.00 70,000.00
L.02 2.100 OH Tukang Kayu 120,000.00 130,000.00 252,000.00 273,000.00
L.03 0.210 OH Kepala Tukang 130,000.00 140,000.00 27,300.00 29,400.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 289,275.00 315,540.00
0.025 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 217,500.00 220,000.00
0.030 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 525.00 540.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 635,950.00 692,665.00
E Overhead & Profit (contoh 10%) 10% 63,595.00 69,266.50
F Harga Satuan Pekerjaan (D+E) 699,545.00 761,931.50

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 759,764.50 827,002.00
rangka expose kayu klas I atau II
A Tenaga 396,200.00 431,000.00
L.01 0.800 OH Pekerja 90,000.00 100,000.00 72,000.00 80,000.00
L.02 2.400 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.240 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.040 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 294,495.00 320,820.00
0.0256 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 222,720.00 225,280.00
0.03 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 525.00 540.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 690,695.00 751,820.00
E Overhead & Profit (contoh 10%) 10% 69,069.50 75,182.00
F Harga Satuan Pekerjaan (D+E) 759,764.50 827,002.00

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 2,255,880.00 2,357,217.50
Klas I atau II
A Tenaga 368,175.00 400,225.00
L.01 0.670 OH Pekerja 90,000.00 100,000.00 60,300.00 67,000.00
L.02 2.000 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.200 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.335 OH Mandor 125,000.00 135,000.00 41,875.00 45,225.00
B Bahan 1,682,625.00 1,742,700.00
0.06 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 1,680,000.00 1,740,000.00
0.15 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 2,625.00 2,700.00
C PERALATAN
D Jumlah A + B + C 2,050,800.00 2,142,925.00
E Overhead & Profit (contoh 10%) 10% 205,080.00 214,292.50
F Harga Satuan Pekerjaan (D+E) 2,255,880.00 2,357,217.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/145 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,282,022.50 1,372,294.00
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 396,200.00 431,000.00
L.01 0.80 OH Pekerja 90,000.00 100,000.00 72,000.00 80,000.00
L.02 2.40 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.24 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.04 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 769,275.00 816,540.00
0.025 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 700,000.00 725,000.00
0.03 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 525.00 540.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 1,165,475.00 1,247,540.00
E Overhead & Profit (contoh 10%) 10% 116,547.50 124,754.00
F Harga Satuan Pekerjaan (D+E) 1,282,022.50 1,372,294.00

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 814,055.00 882,909.50
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 421,025.00 458,005.00


L.01 0.850 OH Pekerja 90,000.00 100,000.00 76,500.00 85,000.00
L.02 2.550 OH Tukang Kayu 120,000.00 130,000.00 306,000.00 331,500.00
L.03 0.255 OH Kepala Tukang 130,000.00 140,000.00 33,150.00 35,700.00
L.04 0.043 OH Mandor 125,000.00 135,000.00 5,375.00 5,805.00
B Bahan 319,025.00 344,640.00
0.025 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 217,500.00 220,000.00
0.03 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 525.00 540.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
0.5 Lbr Formika 70,000.00 75,000.00 35,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 740,050.00 802,645.00
E Overhead & Profit (contoh 10%) 10% 74,005.00 80,264.50
F Harga Satuan Pekerjaan (D+E) 814,055.00 882,909.50

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 12,681,900.00 13,122,505.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,981,000.00 2,155,000.00
L.01 4 OH Pekerja 90,000.00 100,000.00 360,000.00 400,000.00
L.02 12 OH Tukang Kayu 120,000.00 130,000.00 1,440,000.00 1,560,000.00
L.03 1.2 OH Kepala Tukang 130,000.00 140,000.00 156,000.00 168,000.00
L.04 0.2 OH Mandor 125,000.00 135,000.00 25,000.00 27,000.00
B Bahan 9,548,000.00 9,774,550.00
1.1 m3 Kayu Kamfer, balok 8,400,000.00 8,600,000.00 9,240,000.00 9,460,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 98,000.00 100,800.00
C PERALATAN
D Jumlah A + B + C 11,529,000.00 11,929,550.00
E Overhead & Profit (contoh 10%) 10% 1,152,900.00 1,192,955.00
F Harga Satuan Pekerjaan (D+E) 12,681,900.00 13,122,505.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 36,988,792.50 38,636,592.50
Expose, Kayu Klas I
A Tenaga 3,318,175.00 3,609,625.00
L.01 6.7 OH Pekerja 90,000.00 100,000.00 603,000.00 670,000.00
L.02 20.1 OH Tukang Kayu 120,000.00 130,000.00 2,412,000.00 2,613,000.00
L.03 2.01 OH Kepala Tukang 130,000.00 140,000.00 261,300.00 281,400.00
L.04 0.335 OH Mandor 125,000.00 135,000.00 41,875.00 45,225.00
B Bahan 30,308,000.00 31,514,550.00
1.2 m3 Kayu Klas I (jati), balok 25,000,000.00 26,000,000.00 30,000,000.00 31,200,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 98,000.00 100,800.00
C PERALATAN
D Jumlah A + B + C 33,626,175.00 35,124,175.00
E Overhead & Profit (contoh 10%) 10% 3,362,617.50 3,512,417.50
F Harga Satuan Pekerjaan (D+E) 36,988,792.50 38,636,592.50

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 11,760,210.00 12,122,825.00


A Tenaga 1,188,600.00 1,293,000.00
L.01 2.4 OH Pekerja 90,000.00 100,000.00 216,000.00 240,000.00
L.02 7.2 OH Tukang Kayu 120,000.00 130,000.00 864,000.00 936,000.00
L.03 0.72 OH Kepala Tukang 130,000.00 140,000.00 93,600.00 100,800.00
L.04 0.12 OH Mandor 125,000.00 135,000.00 15,000.00 16,200.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/146 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 9,502,500.00 9,727,750.00
1.1 m3 Kayu Klas I (Kamfer), balok 8,400,000.00 8,600,000.00 9,240,000.00 9,460,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
3 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 52,500.00 54,000.00
C PERALATAN
D Jumlah A + B + C 10,691,100.00 11,020,750.00
E Overhead & Profit (contoh 10%) 10% 1,069,110.00 1,102,075.00
F Harga Satuan Pekerjaan (D+E) 11,760,210.00 12,122,825.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 192,654.00 199,028.50
Klas II
A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 152,215.00 155,860.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.0036 m3 Reng (2x3) cm 8,400,000.00 8,600,000.00 30,240.00 30,960.00
0.25 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 4,375.00 4,500.00
C PERALATAN
D Jumlah A + B + C 175,140.00 180,935.00
E Overhead & Profit (contoh 10%) 10% 17,514.00 18,093.50
F Harga Satuan Pekerjaan (D+E) 192,654.00 199,028.50

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 1 m2 225,918.00 233,084.50
Klas II
A Tenaga 22,925.00 25,075.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 182,455.00 186,820.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.0072 m3 Reng (2x3) cm 8,400,000.00 8,600,000.00 60,480.00 61,920.00
0.25 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 4,375.00 4,500.00
C PERALATAN
D Jumlah A + B + C 205,380.00 211,895.00
E Overhead & Profit (contoh 10%) 10% 20,538.00 21,189.50
F Harga Satuan Pekerjaan (D+E) 225,918.00 233,084.50

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 163,471.00 169,499.00


A Tenaga 27,510.00 30,090.00
L.01 0.12 OH Pekerja 90,000.00 100,000.00 10,800.00 12,000.00
L.02 0.12 OH Tukang Kayu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 121,100.00 124,000.00
0.014 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.2 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 3,500.00 3,600.00
C PERALATAN
D Jumlah A + B + C 148,610.00 154,090.00
E Overhead & Profit (contoh 10%) 10% 14,861.00 15,409.00
F Harga Satuan Pekerjaan (D+E) 163,471.00 169,499.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 215,198.50 224,801.50
Klas II atau III
A Tenaga 62,775.00 68,325.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.30 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.030 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 132,860.00 136,040.00
0.0154 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 129,360.00 132,440.00
0.2 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 3,500.00 3,600.00
C PERALATAN
D Jumlah A + B + C 195,635.00 204,365.00
E Overhead & Profit (contoh 10%) 10% 19,563.50 20,436.50
F Harga Satuan Pekerjaan (D+E) 215,198.50 224,801.50

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 220,489.50 230,153.00
Klas II atau III
A Tenaga 59,150.00 64,550.00
L.01 0.2 OH Pekerja 90,000.00 100,000.00 18,000.00 20,000.00
L.02 0.3 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.03 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/147 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 141,295.00 144,680.00
0.0163 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 136,920.00 140,180.00
0.25 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 4,375.00 4,500.00
C PERALATAN
D Jumlah A + B + C 200,445.00 209,230.00
E Overhead & Profit (contoh 10%) 10% 20,044.50 20,923.00
F Harga Satuan Pekerjaan (D+E) 220,489.50 230,153.00

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 374,412.50 389,922.50
II
A Tenaga 36,225.00 39,475.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 304,150.00 315,000.00
0.0108 m3 Kayu klas I (Jati), papan 28,000,000.00 29,000,000.00 302,400.00 313,200.00
0.10 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 1,750.00 1,800.00
C PERALATAN
D Jumlah A + B + C 340,375.00 354,475.00
E Overhead & Profit (contoh 10%) 10% 34,037.50 35,447.50
F Harga Satuan Pekerjaan (D+E) 374,412.50 389,922.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 146,080.00 150,892.50
klas II
A Tenaga 36,225.00 39,475.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 96,575.00 97,700.00
0.011 m3 Kayu klas II (Kamfer), papan 8,700,000.00 8,800,000.00 95,700.00 96,800.00
0.05 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 132,800.00 137,175.00
E Overhead & Profit (contoh 10%) 10% 13,280.00 13,717.50
F Harga Satuan Pekerjaan (D+E) 146,080.00 150,892.50

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 343,392.50 356,818.00
Kayu klas II atau III
A Tenaga 74,350.00 80,880.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.45 OH Tukang Kayu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 237,825.00 243,500.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 2,625.00 2,700.00
C PERALATAN
D Jumlah A + B + C 312,175.00 324,380.00
E Overhead & Profit (contoh 10%) 10% 31,217.50 32,438.00
F Harga Satuan Pekerjaan (D+E) 343,392.50 356,818.00

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 412,582.50 449,548.00
Rangka Kayu Klas II
A Tenaga 74,350.00 80,880.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.45 OH Tukang Kayu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 300,725.00 327,800.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 2,625.00 2,700.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 375,075.00 408,680.00
E Overhead & Profit (contoh 10%) 10% 37,507.50 40,868.00
F Harga Satuan Pekerjaan (D+E) 412,582.50 449,548.00

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 421,932.50 459,305.00
Rangka Kayu Klas II
A Tenaga 82,850.00 89,750.00
L.01 0.020 OH Pekerja 90,000.00 100,000.00 1,800.00 2,000.00
L.02 0.600 OH Tukang Kayu 120,000.00 130,000.00 72,000.00 78,000.00
L.03 0.060 OH Kepala Tukang 130,000.00 140,000.00 7,800.00 8,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/148 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 300,725.00 327,800.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 2,625.00 2,700.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 383,575.00 417,550.00
E Overhead & Profit (contoh 10%) 10% 38,357.50 41,755.00
F Harga Satuan Pekerjaan (D+E) 421,932.50 459,305.00

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 545,545.00 582,175.00

A Tenaga 297,150.00 323,250.00


L.01 0.6 OH Pekerja 90,000.00 100,000.00 54,000.00 60,000.00
L.02 1.8 OH Tukang Kayu 120,000.00 130,000.00 216,000.00 234,000.00
L.03 0.18 OH Kepala Tukang 130,000.00 140,000.00 23,400.00 25,200.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 198,800.00 206,000.00
0.007 m3 Kayu klas I (Jati), papan 28,000,000.00 29,000,000.00 196,000.00 203,000.00
0.1 Kg Paku Biasa 2" - 5" 17,500.00 18,000.00 1,750.00 1,800.00
0.15 Kg Paku Sekrup 3,5" 7,000.00 8,000.00 1,050.00 1,200.00
C PERALATAN
D Jumlah A + B + C 495,950.00 529,250.00
E Overhead & Profit (contoh 10%) 10% 49,595.00 52,925.00
F Harga Satuan Pekerjaan (D+E) 545,545.00 582,175.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 43,219.00 46,645.50
ukuran (120x240) cm
A Tenaga 12,415.00 13,505.00
L.01 0.025 OH Pekerja 90,000.00 100,000.00 2,250.00 2,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.0080 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.0010 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 26,875.00 28,900.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 65,000.00 70,000.00 26,000.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 875.00 900.00
C PERALATAN
D Jumlah A + B + C 39,290.00 42,405.00
E Overhead & Profit (contoh 10%) 10% 3,929.00 4,240.50
F Harga Satuan Pekerjaan (D+E) 43,219.00 46,645.50

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 129,689.34 144,821.60
IV
A Tenaga 16,275.00 17,875.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 101,624.40 113,781.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 5,100,000.00 5,700,000.00 71,400.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 17,500.00 18,000.00 210.00 216.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 117,899.40 131,656.00
E Overhead & Profit (contoh 10%) 10% 11,789.94 13,165.60
F Harga Satuan Pekerjaan (D+E) 129,689.34 144,821.60

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/149 PEK.KAYU


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 212,107.50 261,882.50
A Tenaga 62,825.00 68,075.00
L.01 0.01 OH Pekerja 90,000.00 100,000.00 900.00 1,000.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 130,000.00 170,000.00
1 Buah Kunci Tanam Biasa 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 192,825.00 238,075.00
E Overhead & Profit (contoh 10%) 10% 19,282.50 23,807.50
F Harga Satuan Pekerjaan (D+E) 212,107.50 261,882.50
Overhead & Profit (contoh 10%)

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 172,053.75 238,191.25


A Tenaga 61,412.50 66,537.50
L.01 0.005 OH Pekerja 90,000.00 100,000.00 450.00 500.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 95,000.00 150,000.00
1 Buah Kunci Tanam Kamar Mandi 95,000.00 150,000.00 95,000.00 150,000.00
C PERALATAN
D Jumlah A + B + C 156,412.50 216,537.50
E Overhead & Profit (contoh 10%) 10% 15,641.25 21,653.75
F Harga Satuan Pekerjaan (D+E) 172,053.75 238,191.25

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 210,553.75 260,191.25


A Tenaga 61,412.50 66,537.50
L.01 0.005 OH Pekerja 90,000.00 100,000.00 450.00 500.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 130,000.00 170,000.00
1 Buah Kunci Selinder 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 191,412.50 236,537.50
E Overhead & Profit (contoh 10%) 10% 19,141.25 23,653.75
F Harga Satuan Pekerjaan (D+E) 210,553.75 260,191.25

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 32,711.25 36,423.75


A Tenaga 22,237.50 24,112.50
L.01 0.015 OH Pekerja 90,000.00 100,000.00 1,350.00 1,500.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.0075 OH Mandor 125,000.00 135,000.00 937.50 1,012.50
B Bahan 7,500.00 9,000.00
1 Buah Engsel pintu 7,500.00 9,000.00 7,500.00 9,000.00
C PERALATAN
D Jumlah A + B + C 29,737.50 33,112.50
E Overhead & Profit (contoh 10%) 10% 2,973.75 3,311.25
F Harga Satuan Pekerjaan (D+E) 32,711.25 36,423.75

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 21,257.50 24,282.50


A Tenaga 14,825.00 16,075.00
L.01 0.01 OH Pekerja 90,000.00 100,000.00 900.00 1,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 4,500.00 6,000.00
1 Buah Engsel Jendela 4,500.00 6,000.00 4,500.00 6,000.00
C PERALATAN
D Jumlah A + B + C 19,325.00 22,075.00
E Overhead & Profit (contoh 10%) 10% 1,932.50 2,207.50
F Harga Satuan Pekerjaan (D+E) 21,257.50 24,282.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/150 PEK.KUNCI-KACA


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 56,828.75 75,754.25
A Tenaga 35,662.50 38,867.50
L.01 0.10 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.02 0.20 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.0005 OH Mandor 125,000.00 135,000.00 62.50 67.50
B Bahan 16,000.00 30,000.00
1 Buah Engsel Angin 16,000.00 30,000.00 16,000.00 30,000.00
C PERALATAN
D Jumlah A + B + C 51,662.50 68,867.50
E Overhead & Profit (contoh 10%) 10% 5,166.25 6,886.75
F Harga Satuan Pekerjaan (D+E) 56,828.75 75,754.25

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 43,780.00 48,598.00


A Tenaga 22,300.00 24,180.00
L.01 0.015 OH Pekerja 90,000.00 100,000.00 1,350.00 1,500.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 17,500.00 20,000.00
1 Buah Kait Angin 17,500.00 20,000.00 17,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 39,800.00 44,180.00
E Overhead & Profit (contoh 10%) 10% 3,980.00 4,418.00
F Harga Satuan Pekerjaan (D+E) 43,780.00 48,598.00

8 A.4.6.2.10 1 Buah Pasang Door Closer 380,943.75 470,071.25


A Tenaga 71,312.50 77,337.50
L.01 0.05 OH Pekerja 90,000.00 100,000.00 4,500.00 5,000.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 346,312.50 427,337.50
E Overhead & Profit (contoh 10%) 10% 34,631.25 42,733.75
F Harga Satuan Pekerjaan (D+E) 380,943.75 470,071.25

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 40,177.50 45,028.50


A Tenaga 28,525.00 30,935.00
L.01 0.02 OH Pekerja 90,000.00 100,000.00 1,800.00 2,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 8,000.00 10,000.00
1 Buah Kunci Selot 8,000.00 10,000.00 8,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 36,525.00 40,935.00
E Overhead & Profit (contoh 10%) 10% 3,652.50 4,093.50
F Harga Satuan Pekerjaan (D+E) 40,177.50 45,028.50

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 318,188.75 402,014.25


A Tenaga 14,262.50 15,467.50
L.01 0.01 OH Pekerja 90,000.00 100,000.00 900.00 1,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.0005 OH Mandor 125,000.00 135,000.00 62.50 67.50
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 289,262.50 365,467.50
E Overhead & Profit (contoh 10%) 10% 28,926.25 36,546.75
F Harga Satuan Pekerjaan (D+E) 318,188.75 402,014.25

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/151 PEK.KUNCI-KACA


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 314,132.50 360,585.50
A Tenaga 85,575.00 92,805.00
L.01 0.06 OH Pekerja 90,000.00 100,000.00 5,400.00 6,000.00
L.02 0.6 OH Tukang Kayu 120,000.00 130,000.00 72,000.00 78,000.00
L.03 0.06 OH Kepala Tukang 130,000.00 140,000.00 7,800.00 8,400.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 200,000.00 235,000.00
1 Buah Rel Pintu Dorong 200,000.00 235,000.00 200,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 285,575.00 327,805.00
E Overhead & Profit (contoh 10%) 10% 28,557.50 32,780.50
F Harga Satuan Pekerjaan (D+E) 314,132.50 360,585.50

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 44,728.75 50,793.05


A Tenaga 35,662.50 38,675.50
L.01 0.025 OH Pekerja 90,000.00 100,000.00 2,250.00 2,500.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.00130 OH Mandor 125,000.00 135,000.00 162.50 175.50
B Bahan 5,000.00 7,500.00
1 Buah Kunci Lemari 5,000.00 7,500.00 5,000.00 7,500.00
C PERALATAN
D Jumlah A + B + C 40,662.50 46,175.50
E Overhead & Profit (contoh 10%) 10% 4,066.25 4,617.55
F Harga Satuan Pekerjaan (D+E) 44,728.75 50,793.05

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 126,383.13 140,471.38


A Tenaga 21,393.75 23,201.25
L.01 0.015 OH Pekerja 90,000.00 100,000.00 1,350.00 1,500.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 93,500.00 104,500.00
1.1 m2 Kaca tebal 3mm 85,000.00 95,000.00 93,500.00 104,500.00
C PERALATAN
D Jumlah A + B + C 114,893.75 127,701.25
E Overhead & Profit (contoh 10%) 10% 11,489.38 12,770.13
F Harga Satuan Pekerjaan (D+E) 126,383.13 140,471.38

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 138,483.13 152,571.38


A Tenaga 21,393.75 23,201.25
L.01 0.015 OH Pekerja 90,000.00 100,000.00 1,350.00 1,500.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 104,500.00 115,500.00
1.1 m2 Kaca tebal 5mm 95,000.00 105,000.00 104,500.00 115,500.00
C PERALATAN
D Jumlah A + B + C 125,893.75 138,701.25
E Overhead & Profit (contoh 10%) 10% 12,589.38 13,870.13
F Harga Satuan Pekerjaan (D+E) 138,483.13 152,571.38

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 356,283.13 418,771.38


A Tenaga 21,393.75 23,201.25
L.01 0.015 OH Pekerja 90,000.00 100,000.00 1,350.00 1,500.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 302,500.00 357,500.00
1.1 m2 Kaca Cermin 275,000.00 325,000.00 302,500.00 357,500.00
C PERALATAN
D Jumlah A + B + C 323,893.75 380,701.25
E Overhead & Profit (contoh 10%) 10% 32,389.38 38,070.13
F Harga Satuan Pekerjaan (D+E) 356,283.13 418,771.38

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/152 PEK.KUNCI-KACA


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 15,977.50 17,770.50
Lama
A Tenaga 13,875.00 15,405.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 650.00 750.00
0.05 Kg Soda Api 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 14,525.00 16,155.00
E Overhead & Profit (contoh 10%) 10% 1,452.50 1,615.50
F Harga Satuan Pekerjaan (D+E) 15,977.50 17,770.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 15,950.00 17,770.50
dicat
A Tenaga 13,875.00 15,405.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 14,500.00 16,155.00
E Overhead & Profit (contoh 10%) 10% 1,450.00 1,615.50
F Harga Satuan Pekerjaan (D+E) 15,950.00 17,770.50

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 16,637.50 18,513.00
manual
A Tenaga 14,500.00 16,080.00
L.01 0.15 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.04 0.0080 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 15,125.00 16,830.00
E Overhead & Profit (contoh 10%) 10% 1,512.50 1,683.00
F Harga Satuan Pekerjaan (D+E) 16,637.50 18,513.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 45,001.00 51,887.00
dasar, 2 Lp Cat Penutup)
A Tenaga 8,535.00 9,415.00
L.01 0.070 OH Pekerja 90,000.00 100,000.00 6,300.00 7,000.00
L.02 0.009 OH Tukang Cat 120,000.00 130,000.00 1,080.00 1,170.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 32,375.00 37,755.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.2600 kg Cat Penutup 60,000.00 71,000.00 15,600.00 18,460.00
0.0100 bh Kuas 7,500.00 15,000.00 75.00 150.00
0.0300 kg Pengencer 15,000.00 20,000.00 450.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 40,910.00 47,170.00
E Overhead & Profit (contoh 10%) 10% 4,091.00 4,717.00
F Harga Satuan Pekerjaan (D+E) 45,001.00 51,887.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 63,327.00 72,336.00
dasar, 3 Lp Cat Penutup)
A Tenaga 19,795.00 21,615.00
L.01 0.070 OH Pekerja 90,000.00 100,000.00 6,300.00 7,000.00
L.02 0.105 OH Tukang Cat 120,000.00 130,000.00 12,600.00 13,650.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/153 PEK.PENGECATAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 37,775.00 44,145.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.3500 kg Cat Penutup 60,000.00 71,000.00 21,000.00 24,850.00
0.0100 bh Kuas 7,500.00 15,000.00 75.00 150.00
0.0300 kg Pengencer 15,000.00 20,000.00 450.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 57,570.00 65,760.00
E Overhead & Profit (contoh 10%) 10% 5,757.00 6,576.00
F Harga Satuan Pekerjaan (D+E) 63,327.00 72,336.00

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 37,933.50 40,188.50


A Tenaga 19,725.00 21,415.00
L.01 0.04 OH Pekerja 90,000.00 100,000.00 3,600.00 4,000.00
L.02 0.063 OH Tukang Cat 120,000.00 130,000.00 7,560.00 8,190.00
L.03 0.063 OH Kepala Tukang 130,000.00 140,000.00 8,190.00 8,820.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 34,485.00 36,535.00
E Overhead & Profit (contoh 10%) 10% 3,448.50 3,653.50
F Harga Satuan Pekerjaan (D+E) 37,933.50 40,188.50

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 59,603.50 63,955.10


A Tenaga 13,255.00 14,445.00
L.01 0.04 OH Pekerja 90,000.00 100,000.00 3,600.00 4,000.00
L.02 0.06 OH Tukang Cat 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.016 OH Kepala Tukang 130,000.00 140,000.00 2,080.00 2,240.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 40,930.00 43,696.00
0.15 Ltr Politur 65,000.00 68,000.00 9,750.00 10,200.00
0.372 Ltr Politur Jadi 65,000.00 68,000.00 24,180.00 25,296.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A + B + C 54,185.00 58,141.00
E Overhead & Profit (contoh 10%) 10% 5,418.50 5,814.10
F Harga Satuan Pekerjaan (D+E) 59,603.50 63,955.10

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 11,783.75 13,046.00
A Tenaga 9,750.00 10,810.00
L.01 0.1 OH Pekerja 90,000.00 100,000.00 9,000.00 10,000.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 10,712.50 11,860.00
E Overhead & Profit (contoh 10%) 10% 1,071.25 1,186.00
F Harga Satuan Pekerjaan (D+E) 11,783.75 13,046.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 45,545.50 49,615.50


A Tenaga 36,055.00 39,445.00
L.01 0.16 OH Pekerja 90,000.00 100,000.00 14,400.00 16,000.00
L.02 0.16 OH Tukang Cat 120,000.00 130,000.00 19,200.00 20,800.00
L.03 0.016 OH Kepala Tukang 130,000.00 140,000.00 2,080.00 2,240.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,350.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 3,500.00 4,100.00 350.00 410.00
- -
C PERALATAN
D Jumlah A + B + C 41,405.00 45,105.00
E Overhead & Profit (contoh 10%) 10% 4,140.50 4,510.50
F Harga Satuan Pekerjaan (D+E) 45,545.50 49,615.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/154 PEK.PENGECATAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 22,257.40 25,230.70
Lap.Cat Penutup)
A Tenaga 10,554.00 11,477.00
L.01 0.02 OH Pekerja 90,000.00 100,000.00 1,800.00 2,000.00
L.02 0.063 OH Tukang Cat 120,000.00 130,000.00 7,560.00 8,190.00
L.03 0.0063 OH Kepala Tukang 130,000.00 140,000.00 819.00 882.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 9,680.00 11,460.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 26,000.00 5,980.00 6,760.00
C PERALATAN
D Jumlah A + B + C 20,234.00 22,937.00
E Overhead & Profit (contoh 10%) 10% 2,023.40 2,293.70
F Harga Satuan Pekerjaan (D+E) 22,257.40 25,230.70

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 15,467.10 17,306.30
Penutup)
A Tenaga 8,481.00 9,253.00
L.01 0.028 OH Pekerja 90,000.00 100,000.00 2,520.00 2,800.00
L.02 0.042 OH Tukang Cat 120,000.00 130,000.00 5,040.00 5,460.00
L.03 0.0042 OH Kepala Tukang 130,000.00 140,000.00 546.00 588.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,580.00 6,480.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 26,000.00 4,140.00 4,680.00
C PERALATAN
D Jumlah A + B + C 14,061.00 15,733.00
E Overhead & Profit (contoh 10%) 10% 1,406.10 1,573.30
F Harga Satuan Pekerjaan (D+E) 15,467.10 17,306.30

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 9,824.10 10,728.30


A Tenaga 8,481.00 9,253.00
L.01 0.028 OH Pekerja 90,000.00 100,000.00 2,520.00 2,800.00
L.02 0.042 OH Tukang Cat 120,000.00 130,000.00 5,040.00 5,460.00
L.03 0.0042 OH Kepala Tukang 130,000.00 140,000.00 546.00 588.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 450.00 500.00
0.1 Kg Kalkarium 4,500.00 5,000.00 450.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 8,931.00 9,753.00
E Overhead & Profit (contoh 10%) 10% 893.10 975.30
F Harga Satuan Pekerjaan (D+E) 9,824.10 10,728.30

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 17,512.55 19,488.15


A Tenaga 13,945.50 15,481.50
L.01 0.150 OH Pekerja 90,000.00 100,000.00 13,500.00 15,000.00
L.02 0.001 OH Tukang Cat 120,000.00 130,000.00 120.00 130.00
L.03 0.0001 OH Kepala Tukang 130,000.00 140,000.00 13.00 14.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 1,975.00 2,235.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,500.00 4,100.00 350.00 410.00
0.25 ikat Alang-alang 2,000.00 2,500.00 500.00 625.00
C PERALATAN
D Jumlah A + B + C 15,920.50 17,716.50
E Overhead & Profit (contoh 10%) 10% 1,592.05 1,771.65
F Harga Satuan Pekerjaan (D+E) 17,512.55 19,488.15

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 7,757.75 8,720.25
(pemeliharaan)
A Tenaga 4,577.50 5,057.50
L.01 0.040 OH Pekerja 90,000.00 100,000.00 3,600.00 4,000.00
L.02 0.005 OH Tukang Cat 120,000.00 130,000.00 600.00 650.00
L.03 0.0005 OH Kepala Tukang 130,000.00 140,000.00 65.00 70.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/155 PEK.PENGECATAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,475.00 2,870.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,500.00 4,100.00 700.00 820.00
0.25 ikat Alang-alang 2,000.00 2,500.00 500.00 625.00
C PERALATAN
D Jumlah A + B + C 7,052.50 7,927.50
E Overhead & Profit (contoh 10%) 10% 705.25 792.75
F Harga Satuan Pekerjaan (D+E) 7,757.75 8,720.25

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 89,883.75 101,351.25


A Tenaga 28,712.50 31,137.50
L.01 0.020 OH Pekerja 90,000.00 100,000.00 1,800.00 2,000.00
L.02 0.200 OH Tukang Cat 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.0200 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 81,712.50 92,137.50
E Overhead & Profit (contoh 10%) 10% 8,171.25 9,213.75
F Harga Satuan Pekerjaan (D+E) 89,883.75 101,351.25

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 32,364.75 36,154.25


A Tenaga 26,372.50 28,617.50
L.01 0.02 OH Pekerja 90,000.00 100,000.00 1,800.00 2,000.00
L.02 0.2 OH Tukang Cat 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 3,050.00 4,250.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 29,422.50 32,867.50
E Overhead & Profit (contoh 10%) 10% 2,942.25 3,286.75
F Harga Satuan Pekerjaan (D+E) 32,364.75 36,154.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 63,236.25 70,303.75
Perancah
A Tenaga 50,437.50 55,262.50
L.01 0.25 OH Pekerja 90,000.00 100,000.00 22,500.00 25,000.00
L.02 0.225 OH Tukang Cat 120,000.00 130,000.00 27,000.00 29,250.00
L.04 0.0075 OH Mandor 125,000.00 135,000.00 937.50 1,012.50
B Bahan 7,050.00 8,650.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 57,487.50 63,912.50
E Overhead & Profit (contoh 10%) 10% 5,748.75 6,391.25
F Harga Satuan Pekerjaan (D+E) 63,236.25 70,303.75

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/156 PEK.PENGECATAN


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,359,643.00 2,701,314.00
A Tenaga 449,130.00 494,740.00
L.01 3.3 OH Pekerja 90,000.00 100,000.00 297,000.00 330,000.00
L.02 1.1 OH Tukang Batu 120,000.00 130,000.00 132,000.00 143,000.00
L.03 0.001 OH Kepala Tukang 130,000.00 140,000.00 130.00 140.00
L.04 0.16 OH Mandor 125,000.00 135,000.00 20,000.00 21,600.00
Buah Bahan 1,696,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,600,000.00 1,850,000.00 1,600,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,600,000.00 1,850,000.00 96,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 2,145,130.00 2,455,740.00
E Overhead & Profit (contoh 10%) 10% 214,513.00 245,574.00
F Harga Satuan Pekerjaan (D+E) 2,359,643.00 2,701,314.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 511,280.00 559,185.00
A Tenaga 309,500.00 337,600.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 1.5 OH Tukang Batu 120,000.00 130,000.00 180,000.00 195,000.00
L.03 0.2 OH Kepala Tukang 130,000.00 140,000.00 19,500.00 21,000.00
L.04 0.16 OH Mandor 125,000.00 135,000.00 20,000.00 21,600.00
B Bahan 155,300.00 170,750.00
1 Buah Kloset Jongkok 145,000.00 160,000.00 145,000.00 160,000.00
6 Kg Portland Semen 1,150.00 1,175.00 6,900.00 7,050.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 464,800.00 508,350.00
E Overhead & Profit (contoh 10%) 10% 46,480.00 50,835.00
F Harga Satuan Pekerjaan (D+E) 511,280.00 559,185.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 770,880.00 831,325.00


A Tenaga 235,500.00 257,500.00
L.01 1 OH Pekerja 90,000.00 100,000.00 90,000.00 100,000.00
L.02 1 OH Tukang Batu 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.1 OH Kepala Tukang 130,000.00 140,000.00 13,000.00 14,000.00
L.04 0.1 OH Mandor 125,000.00 135,000.00 12,500.00 13,500.00
B Bahan 465,300.00 498,250.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,150.00 1,175.00 6,900.00 7,050.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 700,800.00 755,750.00
E Overhead & Profit (contoh 10%) 10% 70,080.00 75,575.00
F Harga Satuan Pekerjaan (D+E) 770,880.00 831,325.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 613,470.00 667,260.00


A Tenaga 157,400.00 173,350.00
L.01 1.2 OH Pekerja 90,000.00 100,000.00 108,000.00 120,000.00
L.02 0.145 OH Tukang Batu 120,000.00 130,000.00 17,400.00 18,850.00
L.03 0.15 OH Kepala Tukang 130,000.00 140,000.00 19,500.00 21,000.00
L.04 0.1 OH Mandor 125,000.00 135,000.00 12,500.00 13,500.00
B Bahan 400,300.00 433,250.00
1 Buah Wastafel 300,000.00 325,000.00 300,000.00 325,000.00
0.3 - Perlengkapan 30% Harga Wastafel 300,000.00 325,000.00 90,000.00 97,500.00
6 Kg Portland Semen 1,150.00 1,175.00 6,900.00 7,050.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 557,700.00 606,600.00
E Overhead & Profit (contoh 10%) 10% 55,770.00 60,660.00
F Harga Satuan Pekerjaan (D+E) 613,470.00 667,260.00

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,107,562.50 1,183,495.50


A Tenaga 106,875.00 115,905.00
L.01 0.075 OH Pekerja 90,000.00 100,000.00 6,750.00 7,500.00
L.02 0.75 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
file:///conversion/tmp/activity_task_scratch/530032289.xls 249/157 PEK.SANITASI DALAM GEDUNG
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 1,006,875.00 1,075,905.00
E Overhead & Profit (contoh 10%) 10% 100,687.50 107,590.50
F Harga Satuan Pekerjaan (D+E) 1,107,562.50 1,183,495.50

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,360,700.00 1,484,450.00


A Tenaga 929,000.00 1,013,500.00

L.01 3 OH Pekerja 90,000.00 100,000.00 270,000.00 300,000.00


L.02 4.5 OH Tukang Batu 120,000.00 130,000.00 540,000.00 585,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.9 OH Mandor 125,000.00 135,000.00 112,500.00 121,500.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,237,000.00 1,349,500.00
E Overhead & Profit (contoh 10%) 10% 123,700.00 134,950.00
F Harga Satuan Pekerjaan (D+E) 1,360,700.00 1,484,450.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,672,154.27 1,826,638.54
A Tenaga 942,750.00 1,036,050.00
L.01 6.00 OH Pekerja 90,000.00 100,000.00 540,000.00 600,000.00
L.02 3.00 OH Tukang Batu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.30 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 577,390.24 624,530.49
150.0 bh Batu Bata 580.00 625.00 87,000.00 93,750.00
120 Kg Portland Semen 0.11 1,150.00 1,175.00 138,000.00 141,000.00
0.3 m3 Pasir Pasang 0.0121 340,000.00 370,000.00 102,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,520,140.24 1,660,580.49
E Overhead & Profit (contoh 10%) 10% 152,014.02 166,058.05
F Harga Satuan Pekerjaan (D+E) 1,672,154.27 1,826,638.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,582,616.47 7,509,989.28


A Tenaga 863,750.00 944,430.00
L.01 3.50 OH Pekerja 90,000.00 100,000.00 315,000.00 350,000.00
L.02 4.50 OH Tukang Batu 120,000.00 130,000.00 540,000.00 585,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 1,230,741.59 1,335,815.04 5,120,446.79 5,882,832.98
0.9 m3 Beton K.150 1,105,781.02 1,183,284.40 995,202.92 1,064,955.96
180 Kg Baja Tulangan 0.11 13,619.10 16,128.20 2,451,438.00 2,903,076.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,341.46 1,402.44 670,731.71 701,219.51
10 % Perlengkapan 1,230,741.59 1,335,815.04 123,074.16 133,581.50
C PERALATAN
D Jumlah A + B + C 5,984,196.79 6,827,262.98
E Overhead & Profit (contoh 10%) 10% 598,419.68 682,726.30
F Harga Satuan Pekerjaan (D+E) 6,582,616.47 7,509,989.28

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 351,422.50 394,047.50
A Tenaga 44,475.00 48,225.00
L.01 0.030 OH Pekerja 90,000.00 100,000.00 2,700.00 3,000.00
L.02 0.300 OH Tukang Batu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.030 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 319,475.00 358,225.00
E Overhead & Profit (contoh 10%) 10% 31,947.50 35,822.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/158 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 351,422.50 394,047.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/159 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 54,807.50 64,432.50
A Tenaga 14,825.00 16,075.00
L.01 0.010 OH Pekerja 90,000.00 100,000.00 900.00 1,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 35,000.00 42,500.00
1 bh Floor Drain 35,000.00 42,500.00 35,000.00 42,500.00

C PERALATAN
D Jumlah A + B + C 49,825.00 58,575.00
E Overhead & Profit (contoh 10%) 10% 4,982.50 5,857.50
F Harga Satuan Pekerjaan (D+E) 54,807.50 64,432.50

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 494,258.12 539,627.13
35 cm
A Tenaga 291,535.00 321,165.00
L.01 2.160 OH Pekerja 90,000.00 100,000.00 194,400.00 216,000.00
L.02 0.720 OH Tukang Batu 120,000.00 130,000.00 86,400.00 93,600.00
L.03 0.072 OH Kepala Tukang 130,000.00 140,000.00 9,360.00 10,080.00
L.04 0.011 OH Mandor 125,000.00 135,000.00 1,375.00 1,485.00
B Bahan 157,790.56 169,405.12
40.00 bh Batu Bata 580.00 625.00 23,200.00 25,000.00
44.00 kg Semen Portland 1,150.00 1,175.00 50,600.00 51,700.00
0.07 m3 Pasir Pasang 340,000.00 370,000.00 23,800.00 25,900.00
0.06 m3 Pasir Beton 360,000.00 380,000.00 21,600.00 22,800.00
0.07 m3 Kerikil 240,000.00 260,000.00 16,800.00 18,200.00
1.60 kg Baja Tulangan 13,619.10 16,128.20 21,790.56 25,805.12
C PERALATAN
D Jumlah A + B + C 449,325.56 490,570.12
E Overhead & Profit (contoh 10%) 10% 44,932.56 49,057.01
F Harga Satuan Pekerjaan (D+E) 494,258.12 539,627.13

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 727,947.62 792,803.13
tinggi 50 cm
A Tenaga 429,430.00 473,200.00
L.01 3.200 OH Pekerja 90,000.00 100,000.00 288,000.00 320,000.00
L.02 1.150 OH Tukang Batu 120,000.00 130,000.00 138,000.00 149,500.00
L.03 0.011 OH Kepala Tukang 130,000.00 140,000.00 1,430.00 1,540.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 232,340.56 247,530.12
70.00 bh Batu Bata 580.00 625.00 40,600.00 43,750.00
77.00 kg Semen Portland 1,150.00 1,175.00 88,550.00 90,475.00
0.13 m3 Pasir Pasang 340,000.00 370,000.00 44,200.00 48,100.00
0.09 m3 Pasir Beton 360,000.00 380,000.00 32,400.00 34,200.00
0.02 m3 Kerikil 240,000.00 260,000.00 4,800.00 5,200.00
1.60 kg Baja Tulangan 13,619.10 16,128.20 21,790.56 25,805.12
C PERALATAN
D Jumlah A + B + C 661,770.56 720,730.12
E Overhead & Profit (contoh 10%) 10% 66,177.06 72,073.01
F Harga Satuan Pekerjaan (D+E) 727,947.62 792,803.13

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 868,210.90 947,679.45
60 cm
A Tenaga 429,430.00 473,200.00
L.01 3.200 OH Pekerja 90,000.00 100,000.00 288,000.00 320,000.00
L.02 1.150 OH Tukang Batu 120,000.00 130,000.00 138,000.00 149,500.00
L.03 0.011 OH Kepala Tukang 130,000.00 140,000.00 1,430.00 1,540.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 359,852.64 388,326.77
123.00 bh Batu Bata 580.00 625.00 71,340.00 76,875.00
114.00 kg Semen Portland 1,150.00 1,175.00 131,100.00 133,950.00
0.18 m3 Pasir Pasang 340,000.00 370,000.00 62,560.00 68,080.00
0.12 m3 Pasir Beton 240,000.00 260,000.00 28,800.00 31,200.00
4.85 kg Baja Tulangan 13,619.10 16,128.20 66,052.64 78,221.77
C PERALATAN
D Jumlah A + B + C 789,282.64 861,526.77
E Overhead & Profit (contoh 10%) 10% 78,928.26 86,152.68
F Harga Satuan Pekerjaan (D+E) 868,210.90 947,679.45

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/160 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 66,271.33 69,672.17
A Tenaga 20,205.00 22,005.00
L.01 0.054 OH Pekerja 90,000.00 100,000.00 4,860.00 5,400.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 40,041.67 41,333.33
1.20 m' Pipa Galvanis Ø ½" 25,833.33 26,666.67 31,000.00 32,000.00
0.35 Ls Perlengkapan 35% x pipa 25,833.33 26,666.67 9,041.67 9,333.33
C PERALATAN
D Jumlah A + B + C 60,246.67 63,338.33
E Overhead & Profit (contoh 10%) 10% 6,024.67 6,333.83
F Harga Satuan Pekerjaan (D+E) 66,271.33 69,672.17

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 90,458.50 114,714.88


A Tenaga 54,725.00 59,275.00
L.01 0.010 OH Pekerja 90,000.00 100,000.00 900.00 1,000.00
L.02 0.400 OH Tukang Batu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.040 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 27,510.00 45,011.25
1.00 bh Kran Air 27,500.00 45,000.00 27,500.00 45,000.00
0.0025 bh Sealtape 4,000.00 4,500.00 10.00 11.25
C PERALATAN
D Jumlah A + B + C 82,235.00 104,286.25
E Overhead & Profit (contoh 10%) 10% 8,223.50 10,428.63
F Harga Satuan Pekerjaan (D+E) 90,458.50 114,714.88

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 77,638.00 81,038.83


A Tenaga 20,205.00 22,005.00
L.01 0.054 OH Pekerja 90,000.00 100,000.00 4,860.00 5,400.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 50,375.00 51,666.67
1.20 m' Pipa Galvanis Ø ¾" 32,500.00 33,333.33 39,000.00 40,000.00
0.35 Ls Perlengkapan 35% x pipa 32,500.00 33,333.33 11,375.00 11,666.67
C PERALATAN
D Jumlah A + B + C 70,580.00 73,671.67
E Overhead & Profit (contoh 10%) 10% 7,058.00 7,367.17
F Harga Satuan Pekerjaan (D+E) 77,638.00 81,038.83

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 108,896.33 113,718.00


A Tenaga 20,205.00 22,005.00
L.01 0.054 OH Pekerja 90,000.00 100,000.00 4,860.00 5,400.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 78,791.67 81,375.00
1.20 m' Pipa Galvanis Ø 1" 50,833.33 52,500.00 61,000.00 63,000.00
0.35 Ls Perlengkapan 35% x pipa 50,833.33 52,500.00 17,791.67 18,375.00
C PERALATAN
D Jumlah A + B + C 98,996.67 103,380.00
E Overhead & Profit (contoh 10%) 10% 9,899.67 10,338.00
F Harga Satuan Pekerjaan (D+E) 108,896.33 113,718.00

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 145,696.83 151,959.50


A Tenaga 34,285.00 37,395.00
L.01 0.108 OH Pekerja 90,000.00 100,000.00 9,720.00 10,800.00
L.02 0.180 OH Tukang Batu 120,000.00 130,000.00 21,600.00 23,400.00
L.03 0.018 OH Kepala Tukang 130,000.00 140,000.00 2,340.00 2,520.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 98,166.67 100,750.00
1.20 m' Pipa Galvanis Ø 1½" 63,333.33 65,000.00 76,000.00 78,000.00
0.35 Ls Perlengkapan 35% x pipa 63,333.33 65,000.00 22,166.67 22,750.00
C PERALATAN
D Jumlah A + B + C 132,451.67 138,145.00
E Overhead & Profit (contoh 10%) 10% 13,245.17 13,814.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/161 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 145,696.83 151,959.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/162 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 257,599.83 265,299.83
A Tenaga 43,015.00 46,915.00
L.01 0.135 OH Pekerja 90,000.00 100,000.00 12,150.00 13,500.00
L.02 0.225 OH Tukang Batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 191,166.67 194,266.67
1.20 m' Pipa Galvanis Ø 3" 123,333.33 125,333.33 148,000.00 150,400.00
0.35 Ls Perlengkapan 35% x pipa 123,333.33 125,333.33 43,166.67 43,866.67
C PERALATAN
D Jumlah A + B + C 234,181.67 241,181.67
E Overhead & Profit (contoh 10%) 10% 23,418.17 24,118.17
F Harga Satuan Pekerjaan (D+E) 257,599.83 265,299.83

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 460,779.00 467,200.25


A Tenaga 43,015.00 46,915.00
L.01 0.135 OH Pekerja 90,000.00 100,000.00 12,150.00 13,500.00
L.02 0.225 OH Tukang Batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 375,875.00 377,812.50
1.20 m' Pipa Galvanis Ø 4" 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A + B + C 418,890.00 424,727.50
E Overhead & Profit (contoh 10%) 10% 41,889.00 42,472.75
F Harga Satuan Pekerjaan (D+E) 460,779.00 467,200.25

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 24,552.00 26,974.75


A Tenaga 11,470.00 12,510.00
L.01 0.036 OH Pekerja 90,000.00 100,000.00 3,240.00 3,600.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 10,850.00 12,012.50
1.20 m' Pipa PVC Ø ½" 7,000.00 7,750.00 8,400.00 9,300.00
0.35 Ls Perlengkapan 35% x pipa 7,000.00 7,750.00 2,450.00 2,712.50
C PERALATAN
D Jumlah A + B + C 22,320.00 24,522.50
E Overhead & Profit (contoh 10%) 10% 2,232.00 2,452.25
F Harga Satuan Pekerjaan (D+E) 24,552.00 26,974.75

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 27,109.50 29,319.13


A Tenaga 11,470.00 12,510.00
L.01 0.036 OH Pekerja 90,000.00 100,000.00 3,240.00 3,600.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 13,175.00 14,143.75
1.20 m' Pipa PVC Ø ¾" 8,500.00 9,125.00 10,200.00 10,950.00
0.35 Ls Perlengkapan 35% x pipa 8,500.00 9,125.00 2,975.00 3,193.75
C PERALATAN
D Jumlah A + B + C 24,645.00 26,653.75
E Overhead & Profit (contoh 10%) 10% 2,464.50 2,665.38
F Harga Satuan Pekerjaan (D+E) 27,109.50 29,319.13

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 31,798.25 37,204.75


A Tenaga 11,470.00 12,510.00
L.01 0.036 OH Pekerja 90,000.00 100,000.00 3,240.00 3,600.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 17,437.50 21,312.50
1.20 m' Pipa PVC Ø 1" 11,250.00 13,750.00 13,500.00 16,500.00
0.35 Ls Perlengkapan 35% x pipa 11,250.00 13,750.00 3,937.50 4,812.50
C PERALATAN
D Jumlah A + B + C 28,907.50 33,822.50
E Overhead & Profit (contoh 10%) 10% 2,890.75 3,382.25

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/163 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 31,798.25 37,204.75

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/164 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 34,838.83 40,533.17
A Tenaga 17,205.00 18,765.00
L.01 0.054 OH Pekerja 90,000.00 100,000.00 4,860.00 5,400.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 14,466.67 18,083.33
1.20 m' Pipa PVC Ø 1½" 9,333.33 11,666.67 11,200.00 14,000.00
0.35 Ls Perlengkapan 35% x pipa 9,333.33 11,666.67 3,266.67 4,083.33
C PERALATAN
D Jumlah A + B + C 31,671.67 36,848.33
E Overhead & Profit (contoh 10%) 10% 3,167.17 3,684.83
F Harga Satuan Pekerjaan (D+E) 34,838.83 40,533.17

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 38,817.17 50,479.00


A Tenaga 17,205.00 18,765.00
L.01 0.054 OH Pekerja 90,000.00 100,000.00 4,860.00 5,400.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 18,083.33 27,125.00
1.20 m' Pipa PVC Ø 2" 11,666.67 17,500.00 14,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 11,666.67 17,500.00 4,083.33 6,125.00
C PERALATAN
D Jumlah A + B + C 35,288.33 45,890.00
E Overhead & Profit (contoh 10%) 10% 3,528.83 4,589.00
F Harga Satuan Pekerjaan (D+E) 38,817.17 50,479.00

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 63,840.33 83,458.83


A Tenaga 25,745.00 28,080.00
L.01 0.081 OH Pekerja 90,000.00 100,000.00 7,290.00 8,100.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.0135 OH Kepala Tukang 130,000.00 140,000.00 1,755.00 1,890.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 32,291.67 47,791.67
1.20 m' Pipa PVC Ø 3" 20,833.33 30,833.33 25,000.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 20,833.33 30,833.33 7,291.67 10,791.67
C PERALATAN
D Jumlah A + B + C 58,036.67 75,871.67
E Overhead & Profit (contoh 10%) 10% 5,803.67 7,587.17
F Harga Satuan Pekerjaan (D+E) 63,840.33 83,458.83

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 89,342.00 93,327.67


A Tenaga 11,470.00 12,510.00
L.01 0.036 OH Pekerja 90,000.00 100,000.00 3,240.00 3,600.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 69,750.00 72,333.33
1.20 m' Pipa PVC Ø 4" 45,000.00 46,666.67 54,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 45,000.00 46,666.67 15,750.00 16,333.33
C PERALATAN
D Jumlah A + B + C 81,220.00 84,843.33
E Overhead & Profit (contoh 10%) 10% 8,122.00 8,484.33
F Harga Satuan Pekerjaan (D+E) 89,342.00 93,327.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 83,897.00 91,173.50
cm
A Tenaga 13,020.00 14,300.00
L.01 0.080 OH Pekerja 90,000.00 100,000.00 7,200.00 8,000.00
L.02 0.040 OH Tukang Batu 120,000.00 130,000.00 4,800.00 5,200.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 63,250.00 68,585.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,150.00 1,175.00 40,250.00 41,125.00
0.014 m3 Pasir Pasang 340,000.00 370,000.00 4,760.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 220,000.00 2,240.00 3,080.00
- -
file:///conversion/tmp/activity_task_scratch/530032289.xls 249/165 PEK.SANITASI DALAM GEDUNG
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 76,270.00 82,885.00
E Overhead & Profit (contoh 10%) 10% 7,627.00 8,288.50
F Harga Satuan Pekerjaan (D+E) 83,897.00 91,173.50

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 40,221.50 45,259.50
cm
A Tenaga 9,765.00 10,725.00
L.01 0.060 OH Pekerja 90,000.00 100,000.00 5,400.00 6,000.00
L.02 0.030 OH Tukang Batu 120,000.00 130,000.00 3,600.00 3,900.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 26,800.00 30,420.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,150.00 1,175.00 7,820.00 7,990.00
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 220,000.00 1,760.00 2,420.00
,
C PERALATAN
D Jumlah A + B + C 36,565.00 41,145.00
E Overhead & Profit (contoh 10%) 10% 3,656.50 4,114.50
F Harga Satuan Pekerjaan (D+E) 40,221.50 45,259.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 118,929.80 135,615.98


A Tenaga 22,785.00 25,025.00
L.01 0.140 OH Pekerja 90,000.00 100,000.00 12,600.00 14,000.00
L.02 0.070 OH Tukang Batu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 85,333.00 98,262.25
1.10 bh pipa beton 42,000.00 50,000.00 46,200.00 55,000.00
0.027 m3 Batu Bata 435,000.00 468,750.00 11,745.00 12,656.25
3.920 kg Semen Portlan 1,150.00 1,175.00 4,508.00 4,606.00
0.056 m3 Pasir Pasang 340,000.00 370,000.00 19,040.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 220,000.00 3,840.00 5,280.00
C PERALATAN
D Jumlah A + B + C 108,118.00 123,287.25
E Overhead & Profit (contoh 10%) 10% 10,811.80 12,328.73
F Harga Satuan Pekerjaan (D+E) 118,929.80 135,615.98

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 584,848.00 626,351.00


A Tenaga 61,845.00 67,925.00
L.01 0.380 OH Pekerja 90,000.00 100,000.00 34,200.00 38,000.00
L.02 0.190 OH Tukang Batu 120,000.00 130,000.00 22,800.00 24,700.00
L.03 0.019 OH Kepala Tukang 130,000.00 140,000.00 2,470.00 2,660.00
L.04 0.019 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00
B Bahan 469,835.00 501,485.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 435,000.00 468,750.00 239,250.00 257,812.50
10.300 kg Semen Portlan 1,150.00 1,175.00 11,845.00 12,102.50
0.061 m3 Pasir Pasang 340,000.00 370,000.00 20,740.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 220,000.00 11,040.00 15,180.00
C PERALATAN
D Jumlah A + B + C 531,680.00 569,410.00
E Overhead & Profit (contoh 10%) 10% 53,168.00 56,941.00
F Harga Satuan Pekerjaan (D+E) 584,848.00 626,351.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/166 PEK.SANITASI DALAM GEDUNG


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 1 Titik Pemasangan Lampu 385,880.00 431,508.00


A Tenaga 175,400.00 196,140.00
100 % Pekerja 175,400.00 196,140.00 175,400.00 196,140.00

Bahan 175,400.00 196,140.00


3.00 btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
24.00 m Kabel **) 5,500.00 6,200.00 132,000.00 148,800.00
3.00 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4.00 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3.00 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24.00 buah Klem 50.00 60.00 1,200.00 1,440.00
1.00 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1.00 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00

1.00 buah Pitting 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 350,800.00 392,280.00
E Overhead & Profit (contoh 10%) 10% 35,080.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 385,880.00 431,508.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 488,840.00 536,448.00
A Tenaga 222,200.00 243,840.00
L.01 100 % Pekerja 222,200.00 243,840.00 222,200.00 243,840.00

B Bahan 222,200.00 243,840.00


3 Kg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 5,500.00 6,200.00 82,500.00 93,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A + B + C 444,400.00 487,680.00
E Overhead & Profit (contoh 10%) 10% 44,440.00 48,768.00
F Harga Satuan Pekerjaan (D+E) 488,840.00 536,448.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/167 PEK.ELEKTRIKAL


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN

XVI A.8.4.6 Pekerjaan jalan dan lingkungan

1 1 m2 Pekerjaan macadam tebal 20 cm tiap 1 m2


A Tenaga

0.300 Oh Pekerja

0.010 Oh Mandor
B Bahan

0.140 m3 Batu belah

0.110 m3 Batu pecah 5/7

0.150 m3 Pasir urug

C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
Overhead & Profit (contoh 10%)
2 1 m2 Penyiapan badan jalan / tanah dasar (Subgrade) tiap 1m²
A Tenaga

0.025 Oh Pekerja

0.0004 Oh Mandor
B Bahan

C Peralatan
0.0033 jam VIBRATING ROLLER 6-8 TON
0.0071 jam WATER TANK TRUCK 3000-4500 L

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

3 1 m2 Urugan sirtu (agregat kelas C) dipadatkan tiap 1m³

A Tenaga

0.025 Oh Pekerja

0.0250 Oh Mandor
B Bahan
1.2 m3 sirtu

C Peralatan
0.0215 jam VIBRATING ROLLER 6-8 TON
0.0071 jam WATER TANK TRUCK 3000-4500 L

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Lapis Pondasi Atas (LPA / Base Course) Agregat Kelas A


4 1 m3 ( Batu pecah 2/3 + pasir) tiap 1m³

A Tenaga

1.000 Oh Pekerja

0.0340 Oh Mandor
B Bahan
0.768 m3 Batu pecah/split 2/3
0.432 m3 Pasir urug

C Jumlah A + B + C
0.0268 jam VIBRATING ROLLER 6-8 TON
0.0211 jam WATER TANK TRUCK 3000-4500 L

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Lapis Pondasi Jalan Tanpa Penutup Aspal jenis Waterbound


5 1 m3 Macadam (batu pecah 5/7) tiap 1m³

A Tenaga

1.000 Oh Pekerja

0.0340 Oh Mandor
B Bahan
0.768 m3 Batu pecah 5/7
0.432 m3 Pasir urug

C Peralatan
0.0268 jam VIBRATING ROLLER 6-8 TON
0.0211 jam WATER TANK TRUCK 3000-4500 L
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

6 1 Ltr Lapis Resap Ikat (Prime Coat) tiap 1 Liter / 1 m2

A Tenaga
0.0043 Oh Pekerja
0.0009 Oh Mandor
B Bahan
0.6417 kg Aspal Polimer Lokal

0.4889 Ltr Minyak Tanah

C Peralatan
0.003 jam ASPHALT SPRAYER
0.0031 jam AIR COMPRESSOR
0.003 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

7 1 Ltr Lapis Perekat (Tack Coat) tiap 1 Liter / 1 m2

A Tenaga
0.0043 Oh Pekerja
0.0009 Oh Mandor
B Bahan
0.6417 kg Aspal Polimer Lokal

0.4889 Ltr Minyak Tanah

C Peralatan
0.003 jam ASPHALT SPRAYER
0.0063 jam AIR COMPRESSOR
0.003 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

8 1 Ltr Aspal untuk Pelaburan tiap 1 Liter x 4,5 untuk 4,5 m2


A Tenaga
0.0022 Oh Pekerja
0.00022 Oh Mandor
B Bahan
1.1 kg Aspal Polimer Lokal

0.052 Ltr Minyak Tanah

C Peralatan
0.0015 jam ASPHALT SPRAYER
0.0031 jam AIR COMPRESSOR
0.0015 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Lapisan Penetrasi (LAPEN) / Lapisan Permukaan (Surface Course)


9 1 Ltr
Macadam tebal 5 cm tiap 1m²
A Tenaga
0.1415 Oh Pekerja
0.0043 Oh Tukang aspal
0.0043 Oh Mandor
B Bahan
0.04 m³ Batu pecah/split 3/5

0.022 m³ Batu pecah/split 2/3

0.011 m³ Batu pecah/split 1/2

0.0025 m³ Abu batu


4.8 kg Aspal Polimer Lokal
0.322 Ltr Minyak Tanah

C Peralatan
0.0027 jam THREE WHEEL ROLLER 8-10 TON
0.0144 jam ASPHALT SPRAYER
0.0108 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Pembuatan jalan aspal biasa (Sirtu t=10 cm, Agregat Kelas A t=20 cm,
10 1 m2
Permukaan Macadam t=5 cm) tiap m²
A Tenaga
0.3915 Oh Pekerja
0.0043 Oh Tukang aspal
0.014 Oh Mandor
B Bahan
0.12 m³ Sirtu
0.04 m³ Batu pecah/split 3/5

0.1756 m³ Batu pecah/split 2/3

0.011 m³ Batu pecah/split 1/2

0.0025 m³ Abu batu

4.8 kg Aspal Polimer Lokal

0.322 Ltr Minyak Tanah

0.0864 m³ Pasir urug

C Peralatan
0.066 jam VIBRATING ROLLER 6-8 TON
0.01352 jam WATER TANK TRUCK 3000-4500 L
0.00806 jam THREE WHEEL ROLLER 8-10 TON
0.0144 jam ASPHALT SPRAYER
0.0108 jam DUMP TRUCK 3-4 M³ / 6 TON
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

11 m' Pembuatan jalan aspal biasa lebar 3 m' tiap 1 m'


12 m' Pembuatan jalan aspal biasa lebar 4 m' tiap 1 m'
13 m' Pembuatan jalan aspal biasa lebar 5 m' tiap 1 m'
14 m' Pembuatan jalan aspal biasa lebar 6 m' tiap 1 m'

15 m' Pembuatan jalan aspal biasa lebar 8 m' tiap 1 m'

Membentuk badan jalan /Subgrade dengan


16 1 m3
Timbunan (Menggunakan alat)
A Tenaga
1 hr Pekerja
2 hr Operator
1 hr Mandor
10 hr Sopir
B Bahan
160 m³ Pasir urug

1 Set Alat bantu


C Peralatan

5.00 jam Grader 110 HP


5.00 jam Mesin gilas roda karet 8-15 T
4.00 jam Truck tangki air 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Membentuk badan jalan /didaerah galian tanah


17 1 m3
biasa (Menggunakan alat)
A Tenaga
5 hr Pekerja
3 hr Operator
1 hr Mandor
4 hr Sopir
B Bahan
1 Set Alat bantu

C Peralatan

5.00 jam Grader 110 HP


5.00 jam Buldozer 110 HP
5.00 jam Whell Loader 80 HP
20.00 jam Dump truk 5 T - 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

18 1 m2 Pemadatan tanah dasar (Menggunakan buruh)

A Tenaga
66 hr Pekerja
1 hr Tukang
2 hr Mandor
B Bahan
0.2 Set Alat bantu

C Peralatan

5.00 jam Baby Roller / Pedestrian

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

19 1 m2 Pemadatan tanah dasar (Menggunakan alat)

A Tenaga
4 hr Pekerja
1 hr Tukang
2 hr Mandor
B Bahan
0.2 Set Alat bantu

C Peralatan

6.00 jam Baby Roller / Pedestrian

6.00 jam Grader 110 HP


D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

20 1 m3 Membentuk bahu jalan keras (Menggunakan Alat)

A Tenaga
6 hr Pekerja
1 hr Tukang
1 hr Mandor
B Bahan
250.00 m3 kerikil
0.20 Set Alat bantu

C Peralatan

10.00 jam Baby Roller / Pedestrian


5.00 jam Grader 110 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

21 1 m3 Membentuk bahu jalan keras (Menggunakan Buruh)

A Tenaga
67 hr Pekerja
2 hr Mandor
B Bahan
120.00 m3 kerikil
2.30 Set Alat bantu

C Peralatan

5.00 jam Vibrator Roller self 7 ton

D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Bawah (LPB) kelas A


22 1 m3
(menggunakan alat)
A Tenaga
4 hr Pekerja
2 hr Operator
1 hr Mandor
1 hr Sopir
B Bahan

45.00 m3 Batu pecah 3-5 cm


23.00 m3 Batu pecah 2-3 cm
13.00 m3 Batu Pecah 1-2 cm
27.00 m3 Batu pecah 0,5-1 cm
72.00 m3 Pasir urug
1.00 Set Alat bantu

C Peralatan

5.00 jam Mesin gilas 3 roda 8-10 T


5.00 jam Grader 110 HP
4.00 jam Truk tangki air 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Bawah (LPB) kelas B


23 1 m3
(menggunakan alat)
A Tenaga
4 hr Pekerja
2 hr Operator
1 hr Mandor
1 hr Sopir
B Bahan
125.00 m3 Kerikil
65.00 m3 Pasir urug
0.20 Set Alat bantu

C Peralatan

10.00 jam Mesin gilas 3 roda 8-10 T


5.00 jam Grader 110 HP
5.00 jam Truk tangki air 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Bawah (LPB) kelas C


24 1 m3
(menggunakan alat)
A Tenaga
6 hr Pekerja
2 hr Operator
1 hr Mandor
1 hr Sopir
B Bahan

160.00 m3 Kerikil
0.20 Set Alat bantu

C Peralatan

10.00 jam Mesin gilas 3 roda 8-10 T


5.00 jam Grader 110 HP
5.00 jam Truk tangki air 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Bawah (LPB) kelas C


25 1 m3
(menggunakan buruh)
A Tenaga
60 hr Pekerja
1 hr Operator
3 hr Mandor
1 hr Sopir
B Bahan

75.00 m3 Kerikil
2.50 Set Alat bantu

C Peralatan

10.00 jam Mesin gilas 3 roda 8-10 T


5.00 jam Truk tangki air 68 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Bawah (LPB) TELFORD


26 1 m3
(menggunakan buruh)
A Tenaga
99 hr Pekerja
1 hr Operator
3 hr Mandor
B Bahan
50.00 m3 Batu belah 15-20 cm
20.00 m3 Batu pecah 5-7 cm
30.00 m3 Pasir urug
4.00 set Alat bantu
C Peralatan

10.00 jam Mesin gilas 3 roda 8-10 T


D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Atas (LPA) Kelas A


27 1 m3
(menggunakan Alat)
A Tenaga
4 hr Pekerja
2 hr Operator
1 hr Mandor
1 hr Sopir
B Bahan

150.00 m3 Kerikil
15.00 m3 Pasir urug
0.20 set Alat bantu
C Peralatan

5.00 jam Grader 110 HP


5.00 jam Truk tangki air 68 HP
5.00 jam Mesin gilas bergetar 1 T
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Atas (LPA) Kelas B


28 1 m3
(menggunakan Alat)
A Tenaga
4 hr Pekerja
2 hr Operator
1 hr Mandor
1 hr Sopir
B Bahan

200.00 m3 Kerikil
0.20 m3 Pasir urug
C Peralatan

5.00 jam Grader 110 HP


5.00 jam Truk tangki air 68 HP
5.00 jam Mesin gilas bergetar 1 T
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Konstruksi lapis Pondasi Atas (LPA) Kelas B


29 1 m3
(menggunakan Buruh)
A Tenaga
100 hr Pekerja
2 hr Operator
4 hr Mandor
2 hr Sopir
B Bahan

200.00 m3 Kerikil
4.00 m3 Alat bantu
C Peralatan

5.00 jam Truk tangki air 68 HP


5.00 jam Mesin gilas bergetar 1 T
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Menghampar Lapisan Pondasi Atas Aspal beton


30 1 m3
(LASTON ATAS) (menggunakan Alat)
A Tenaga
20 hr Pekerja
4 hr Operator
1 hr Mandor
B Bahan

0.60 m3 Pasir beton


135.00 kg Aspal
90.00 ltr Minyak bakar
0.50 set Alat bantu
100.00 m3 Campuran Laston atas
C Peralatan

5.00 jam Mesin gilas 3 roda 8-10 T


5.00 jam Mesin gilas roda karet 8-15 T
3.00 jam Mesin penyemprot aspal 1000 L
5.00 jam Mesin penghampar 1,28 m
4.00 jam Compresor 210 m3/jam
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

31 1 m3 Laburan Aspal Pasir (BURAS) (menggunakan Alat)

A Tenaga
14 hr Pekerja
2 hr Operator
1 hr Mandor
2 hr Sopir
B Bahan

43.00 m3 Pasir beton


2,900.00 kg Aspal
300.00 ltr Minyak bakar
0.50 set Alat bantu
C Peralatan
5.00 jam Mesin gilas roda karet 8-15 T
5.00 jam Mesin penyemprot aspal 1000 L
10.00 jam Dump truk 3,5 T / 44 HP
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Memasang paving blok parkir kendaraan (warna


32 1 m2 abu T-16 uk. 8x10,5x21) + urugan sirtu 20 cm +
urugan pasir 5 cm tiap m²
A Tenaga
0.2125 Oh Pekerja
0.12 Oh Tukang batu
0.012 Oh kepala tukang
0.01625 Oh mandor
B Bahan
0.24 m³ Sirtu

0.06 m³ Pasir urug

1.10 m² Paving abu-abu segi enam, tebal 8 cm

0.02 m³ Abu batu

C Peralatan

0.1350 jam TAMPER / HAND COMPACTOR


0.0337 jam PLATE COMPACTOR
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

Memasang paving blok jalan setapak (warna abu T-16 uk. 8x10,5x21)
33 1 m2
+ urugan sirtu 10 cm + urugan pasir 5 cm tiap m2

A Tenaga
0.1875 Oh Pekerja
0.12 Oh Tukang batu
0.012 Oh kepala tukang
0.01375 Oh mandor
B Bahan

0.12 m³ Sirtu

0.06 m³ Pasir urug


1.05 m² Paving abu-abu segi enam, tebal 8 cm

0.02 m³ Abu batu

C Peralatan

0.1350 jam TAMPER / HAND COMPACTOR


0.0337 jam PLATE COMPACTOR
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)

34 1 m' Memasang kanstin beton tiap 1 m'

A Tenaga
0.076 Oh Pekerja
0.0225 Oh Tukang batu
0.00225 Oh kepala tukang
0.005 Oh mandor
B Bahan
0.0007 m³ Kayu Meranti Palembang papan

0.0012 m³ Kayu Meranti Palembang kaso

0.002 kg Paku biasa 2"-5"

0.02 m³ Pasir urug

2.63 bh Kanstin abu-abu 15 x 25 x 40

7.08 kg Semen portland

0.02 m³ Pasir pasang

C Peralatan
D Jumlah A + B + C
E Overhead & Profit (contoh 10%)
F Harga Satuan Pekerjaan (D+E)
28 Tower Air Be Unit
Tower Air fibe bh 1.0000 ### 4,919,500.00
Galian tanah m3 2.0000 ### 174,625.00
Urugan tanah m3 0.6667 ### 19,398.50
Foot plat (0,7 m3 0.6000 ### 2,848,659.38
Kolom (0,25x0 m3 1.0000 ### 5,366,478.61
Balok +R Balk m3 0.8000 ### 4,901,479.57
Plat (2,5x2,5 m3 0.8000 ### 5,161,595.82
Cat dinding m2 32.5000 ### 988,621.21
Tangga unit 1.0000 Pekerja #VALUE!
#VALUE!
Jasa 10 % #VALUE!
#VALUE!
HARGA BAHAN/UPAH JUMLAH
AN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

135,685.00 162,415.00
28,250.00 31,350.00
90,000.00 100,000.00 27,000.00 30,000.00
125,000.00 135,000.00 1,250.00 1,350.00
95,100.00 116,300.00
280,000.00 320,000.00 39,200.00 44,800.00
290,000.00 350,000.00 31,900.00 38,500.00
160,000.00 220,000.00 24,000.00 33,000.00
- -

123,350.00 147,650.00
10% 12,335.00 14,765.00
135,685.00 162,415.00

grade) tiap 1m² 4,862.00 5,226.76


2,300.00 2,554.00
90,000.00 100,000.00 2,250.00 2,500.00
125,000.00 135,000.00 50.00 54.00
- -
- -

2,120.00 2,197.60

40,000.00 42,000.00 132.00 138.60

280,000.00 290,000.00 1,988.00 2,059.00

4,420.00 4,751.60
10% 442.00 475.16
4,862.00 5,226.76

246,645.30 278,361.05
5,375.00 6,000.00
90,000.00 100,000.00 2,250.00 2,500.00
125,000.00 140,000.00 3,125.00 3,500.00
216,000.00 240,000.00
180,000.00 200,000.00 216,000.00 240,000.00
- -

2,848.00 7,055.50

40,000.00 310,000.00 860.00 6,665.00

280,000.00 55,000.00 1,988.00 390.50

224,223.00 253,055.50
10% 22,422.30 25,305.55
246,645.30 278,361.05

Agregat Kelas A
474,617.00 548,586.06

94,250.00 104,590.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 4,250.00 4,590.00
330,240.00 386,880.00
340,000.00 380,000.00 261,120.00 291,840.00
160,000.00 220,000.00 69,120.00 95,040.00

6,980.00 7,244.60

40,000.00 42,000.00 1,072.00 1,125.60

280,000.00 290,000.00 5,908.00 6,119.00

431,470.00 498,714.60
10% 43,147.00 49,871.46
474,617.00 548,586.06

l jenis Waterbound
432,377.00 523,242.06

94,250.00 104,590.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 4,250.00 4,590.00
291,840.00 363,840.00
290,000.00 350,000.00 222,720.00 268,800.00
160,000.00 220,000.00 69,120.00 95,040.00

6,980.00 7,244.60

40,000.00 42,000.00 1,072.00 1,125.60

280,000.00 290,000.00 5,908.00 6,119.00


393,070.00 475,674.60
10% 39,307.00 47,567.46
432,377.00 523,242.06

/ 1 m2 13,514.92 14,333.98

499.50 551.50
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 112.50 121.50
10,165.79 10,767.39
5,937.50 6,875.00 3,810.09 4,411.69
13,000.00 13,000.00 6,355.70 6,355.70

1,621.00 1,712.00

135,000.00 140,000.00 405.00 420.00

310,000.00 320,000.00 961.00 992.00

85,000.00 100,000.00 255.00 300.00

12,286.29 13,030.89
10% 1,228.63 1,303.09
13,514.92 14,333.98

m2 14,606.12 15,460.38

499.50 551.50
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 112.50 121.50
10,165.79 10,767.39
5,937.50 6,875.00 3,810.09 4,411.69
13,000.00 13,000.00 6,355.70 6,355.70

2,613.00 2,736.00

135,000.00 140,000.00 405.00 420.00

310,000.00 320,000.00 1,953.00 2,016.00

85,000.00 100,000.00 255.00 300.00

13,278.29 14,054.89
10% 1,327.83 1,405.49
14,606.12 15,460.38

ntuk 4,5 m2 9,705.03 10,936.75


324.50 352.00
130,000.00 140,000.00 286.00 308.00
175,000.00 200,000.00 38.50 44.00
7,207.25 8,238.50
5,937.50 6,875.00 6,531.25 7,562.50
13,000.00 13,000.00 676.00 676.00

1,291.00 1,352.00

135,000.00 140,000.00 202.50 210.00

310,000.00 320,000.00 961.00 992.00

85,000.00 100,000.00 127.50 150.00

8,822.75 9,942.50
10% 882.28 994.25
9,705.03 10,936.75

Surface Course)
82,711.75 96,106.45

13,659.50 15,160.50
90,000.00 100,000.00 12,735.00 14,150.00
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 537.50 580.50
57,321.00 65,036.00
320,000.00 360,000.00 12,800.00 14,400.00
340,000.00 380,000.00 7,480.00 8,360.00
330,000.00 390,000.00 3,630.00 4,290.00
290,000.00 320,000.00 725.00 800.00
5,937.50 6,875.00 28,500.00 33,000.00
13,000.00 13,000.00 4,186.00 4,186.00
4,212.00 7,173.00

500,000.00 550,000.00 1,350.00 1,485.00

135,000.00 320,000.00 1,944.00 4,608.00

85,000.00 100,000.00 918.00 1,080.00

75,192.50 87,369.50
10% 7,519.25 8,736.95
82,711.75 96,106.45

at Kelas A t=20 cm,


191,464.46 220,765.38

37,372.00 41,470.00
90,000.00 100,000.00 35,235.00 39,150.00
90,000.00 100,000.00 387.00 430.00
125,000.00 135,000.00 1,750.00 1,890.00
123,369.00 142,412.00
180,000.00 200,000.00
320,000.00 360,000.00 12,800.00 14,400.00
340,000.00 380,000.00 59,704.00 66,728.00
330,000.00 390,000.00 3,630.00 4,290.00
290,000.00 320,000.00 725.00 800.00
5,937.50 6,875.00 28,500.00 33,000.00
13,000.00 13,000.00 4,186.00 4,186.00
160,000.00 220,000.00 13,824.00 19,008.00
13,317.60 16,813.80

40,000.00 42,000.00 2,640.00 2,772.00

280,000.00 290,000.00 3,785.60 3,920.80

500,000.00 550,000.00 4,030.00 4,433.00

135,000.00 320,000.00 1,944.00 4,608.00

85,000.00 100,000.00 918.00 1,080.00

174,058.60 200,695.80
10% 17,405.86 20,069.58
191,464.46 220,765.38

574,393.38 662,296.14
765,857.84 883,061.52
957,322.30 1,103,826.90
1,148,786.76 1,324,592.28

1,531,715.68 1,766,123.04

dengan
307,175.37 399,621.34

2,315,000.00 2,635,000.00
90,000.00 100,000.00 90,000.00 100,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 1,750,000.00 2,000,000.00
25,600,040.00 35,200,055.00
160,000.00 220,000.00 25,600,000.00 35,200,000.00
40.00 55.00 40.00 55.00
5,595,000.00 5,760,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

270,000.00 280,000.00 1,350,000.00 1,400,000.00

280,000.00 290,000.00 1,120,000.00 1,160,000.00

279,250.33 363,292.13
10% 27,925.03 36,329.21
307,175.37 399,621.34

galian tanah
62,427.48 66,745.30

1,800,000.00 2,035,000.00
90,000.00 100,000.00 450,000.00 500,000.00
175,000.00 200,000.00 525,000.00 600,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 700,000.00 800,000.00
450.00 508.75
450.00 508.75 450.00 508.75
9,550,000.00 10,100,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

675,000.00 700,000.00 3,375,000.00 3,500,000.00

270,000.00 280,000.00 1,350,000.00 1,400,000.00

85,000.00 100,000.00 1,700,000.00 2,000,000.00

56,752.25 60,677.54
10% 5,675.23 6,067.75
62,427.48 66,745.30

akan buruh) 2,347.92 2,602.31

6,280,000.00 6,970,000.00
90,000.00 100,000.00 5,940,000.00 6,600,000.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 250,000.00 270,000.00
314.00 348.50
1,570.00 1,742.50 314.00 348.50
550,000.00 600,000.00

110,000.00 120,000.00 550,000.00 600,000.00

2,134.47 2,365.73
10% 213.45 236.57
2,347.92 2,602.31

akan alat) 1,405.26 1,465.76

700,000.00 770,000.00
90,000.00 100,000.00 360,000.00 400,000.00
90,000.00 100,000.00 90,000.00 100,000.00
125,000.00 135,000.00 250,000.00 270,000.00
35.00 38.50
175.00 192.50 35.00 38.50
4,410,000.00 4,560,000.00

110,000.00 120,000.00 660,000.00 720,000.00

625,000.00 640,000.00 3,750,000.00 3,840,000.00

1,277.51 1,332.51
10% 127.75 133.25
1,405.26 1,465.76

ggunakan Alat) 296,544.88 16,272.44

790,000.00 870,000.00
90,000.00 100,000.00 540,000.00 600,000.00
125,000.00 135,000.00 125,000.00 135,000.00
125,000.00 135,000.00 125,000.00 135,000.00
45,002,250.00 50,002,500.00
180,000.00 200,000.00 45,000,000.00 50,000,000.00
11,250.00 12,500.00 2,250.00 2,500.00
8,125,000.00 8,300,000.00

500,000.00 510,000.00 5,000,000.00 5,100,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

269,586.25 14,793.13
10% 26,958.63 1,479.31
296,544.88 16,272.44

ggunakan Buruh) 348,246.48 384,241.46

6,280,000.00 6,970,000.00
90,000.00 100,000.00 6,030,000.00 6,700,000.00
125,000.00 135,000.00 250,000.00 270,000.00
21,612,420.00 24,013,800.00
180,000.00 200,000.00 21,600,000.00 24,000,000.00
5,400.00 6,000.00 12,420.00 13,800.00
2,500,000.00 2,550,000.00

500,000.00 510,000.00 2,500,000.00 2,550,000.00

316,587.71 349,310.42
10% 31,658.77 34,931.04
348,246.48 384,241.46

PB) kelas A
350,288.90 420,376.20

535,000.00 600,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00
125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
46,681,667.50 56,124,027.50
320,000.00 360,000.00 14,400,000.00 16,200,000.00
340,000.00 380,000.00 7,820,000.00 8,740,000.00
330,000.00 390,000.00 4,290,000.00 5,070,000.00
320,000.00 380,000.00 8,640,000.00 10,260,000.00
160,000.00 220,000.00 11,520,000.00 15,840,000.00
11,667.50 14,027.50 11,667.50 14,027.50
550,000.00 600,000.00

110,000.00 120,000.00 550,000.00 600,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

280,000.00 290,000.00 1,120,000.00 1,160,000.00

318,444.45 382,160.18
10% 31,844.45 38,216.02
350,288.90 420,376.20

PB) kelas B
294,519.19 333,937.74

1,010,000.00 1,135,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
34,151,707.50 39,301,965.00
190,000.00 200,000.00 23,750,000.00 25,000,000.00
160,000.00 220,000.00 10,400,000.00 14,300,000.00
8,537.50 9,825.00 1,707.50 1,965.00
5,000,000.00 5,100,000.00

500,000.00 510,000.00 5,000,000.00 5,100,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

280,000.00 290,000.00 1,400,000.00 1,450,000.00

267,744.72 303,579.77
10% 26,774.47 30,357.98
294,519.19 333,937.74

PB) kelas C
335,422.27 352,335.50

1,190,000.00 1,335,000.00
90,000.00 100,000.00 540,000.00 600,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00 175,000.00 200,000.00
30,401,520.00 32,001,600.00
190,000.00 200,000.00 30,400,000.00 32,000,000.00
7,600.00 8,000.00 1,520.00 1,600.00
5,000,000.00 5,100,000.00

500,000.00 510,000.00 5,000,000.00 5,100,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

280,000.00 290,000.00 1,400,000.00 1,450,000.00

304,929.33 320,305.00
10% 30,492.93 32,030.50
335,422.27 352,335.50

PB) kelas C
393,871.61 421,930.21

6,125,000.00 6,805,000.00
90,000.00 100,000.00 5,400,000.00 6,000,000.00
175,000.00 200,000.00 175,000.00 200,000.00
125,000.00 135,000.00 375,000.00 405,000.00
175,000.00 200,000.00 175,000.00 200,000.00
14,258,906.25 15,009,375.00
190,000.00 200,000.00 14,250,000.00 15,000,000.00
3,562.50 3,750.00 8,906.25 9,375.00
1,100,000.00 1,200,000.00

110,000.00 120,000.00 1,100,000.00 1,200,000.00

280,000.00 290,000.00 1,400,000.00 1,450,000.00

358,065.10 383,572.92
10% 35,806.51 38,357.29
393,871.61 421,930.21

PB) TELFORD
490,670.13 582,114.50

9,460,000.00 10,505,000.00
90,000.00 100,000.00 8,910,000.00 9,900,000.00
175,000.00 200,000.00 175,000.00 200,000.00
125,000.00 135,000.00 375,000.00 405,000.00
25,125,100.00 30,630,600.00
290,000.00 340,000.00 14,500,000.00 17,000,000.00
290,000.00 350,000.00 5,800,000.00 7,000,000.00
160,000.00 220,000.00 4,800,000.00 6,600,000.00
6,275.00 7,650.00 25,100.00 30,600.00
1,100,000.00 1,200,000.00

110,000.00 120,000.00 1,100,000.00 1,200,000.00

446,063.75 529,195.00
10% 44,606.38 52,919.50
490,670.13 582,114.50

) Kelas A
319,564.16 343,169.43

835,000.00 935,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
30,901,545.00 33,301,665.00
190,000.00 200,000.00 28,500,000.00 30,000,000.00
160,000.00 220,000.00 2,400,000.00 3,300,000.00
7,725.00 8,325.00 1,545.00 1,665.00
3,125,000.00 3,200,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00


280,000.00 290,000.00 1,400,000.00 1,450,000.00

500,000.00 510,000.00 2,500,000.00 2,550,000.00

290,512.88 311,972.21
10% 29,051.29 31,197.22
319,564.16 343,169.43

) Kelas B
307,941.33 323,979.33

835,000.00 935,000.00
90,000.00 100,000.00 360,000.00 400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
38,032,000.00 40,044,000.00
190,000.00 200,000.00 38,000,000.00 40,000,000.00
160,000.00 220,000.00 32,000.00 44,000.00
3,125,000.00 3,200,000.00

625,000.00 640,000.00 3,125,000.00 3,200,000.00

280,000.00 290,000.00 1,400,000.00 1,450,000.00

500,000.00 510,000.00 2,500,000.00 2,550,000.00

279,946.67 294,526.67
10% 27,994.67 29,452.67
307,941.33 323,979.33

) Kelas B
365,478.67 388,886.67

9,850,000.00 10,940,000.00
90,000.00 100,000.00 9,000,000.00 10,000,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 500,000.00 540,000.00
175,000.00 200,000.00
38,038,000.00 40,040,000.00
190,000.00 200,000.00 38,000,000.00 40,000,000.00
9,500.00 10,000.00 38,000.00 40,000.00
1,950,000.00 2,050,000.00

280,000.00 290,000.00 1,400,000.00 1,450,000.00

110,000.00 120,000.00 550,000.00 600,000.00

332,253.33 353,533.33
10% 33,225.33 35,353.33
365,478.67 388,886.67

s Aspal beton
1,796,002.66 1,845,345.72
at)
2,625,000.00 2,935,000.00
90,000.00 100,000.00 1,800,000.00 2,000,000.00
175,000.00 200,000.00 700,000.00 800,000.00
125,000.00 135,000.00 125,000.00 135,000.00
38,037,835.95 39,076,415.77
360,000.00 380,000.00 216,000.00 228,000.00
5,937.50 6,875.00 801,562.50 928,125.00
13,000.00 13,000.00 1,170,000.00 1,170,000.00
23,900,546.89 24,500,581.53 11,950,273.45 12,250,290.77
239,000.00 245,000.00 23,900,000.00 24,500,000.00
32,810,000.00 33,480,000.00

110,000.00 120,000.00 550,000.00 600,000.00

500,000.00 510,000.00 2,500,000.00 2,550,000.00

340,000.00 350,000.00 1,020,000.00 1,050,000.00

5,500,000.00 5,600,000.00 27,500,000.00 28,000,000.00

310,000.00 320,000.00 1,240,000.00 1,280,000.00

1,632,729.69 1,677,587.02
10% 163,272.97 167,758.70
1,796,002.66 1,845,345.72

nggunakan Alat) 19,905.19 21,753.75

1,735,000.00 1,935,000.00
90,000.00 100,000.00 1,260,000.00 1,400,000.00
175,000.00 200,000.00 350,000.00 400,000.00
125,000.00 135,000.00 125,000.00 135,000.00
175,000.00 200,000.00
36,644,498.44 40,227,721.88
360,000.00 380,000.00 15,480,000.00 16,340,000.00
5,937.50 6,875.00 17,218,750.00 19,937,500.00
13,000.00 13,000.00 3,900,000.00 3,900,000.00
91,496.88 100,443.75 45,748.44 50,221.88
5,050,000.00 5,300,000.00
500,000.00 510,000.00 2,500,000.00 2,550,000.00

340,000.00 350,000.00 1,700,000.00 1,750,000.00

85,000.00 100,000.00 850,000.00 1,000,000.00

18,095.62 19,776.13
10% 1,809.56 1,977.61
19,905.19 21,753.75

araan (warna
sirtu 20 cm + 224,966.50 241,793.20

35,085.00 38,530.00
90,000.00 100,000.00 19,125.00 21,250.00
120,000.00 130,000.00 14,400.00 15,600.00
130,000.00 140,000.00 1,560.00 1,680.00
125,000.00 135,000.00
153,920.00 164,760.00
190,000.00 200,000.00 45,600.00 48,000.00
160,000.00 200,000.00 9,600.00 12,000.00
85,000.00 90,000.00 93,500.00 99,000.00
290,000.00 320,000.00 5,220.00 5,760.00
15,510.00 16,522.00

40,000.00 45,000.00 5,400.00 6,075.00

300,000.00 310,000.00 10,110.00 10,447.00

204,515.00 219,812.00
10% 20,451.50 21,981.20
224,966.50 241,793.20

bu T-16 uk. 8x10,5x21)


192,736.50 207,693.20
m2

32,835.00 36,030.00
90,000.00 100,000.00 16,875.00 18,750.00
120,000.00 130,000.00 14,400.00 15,600.00
130,000.00 140,000.00 1,560.00 1,680.00
125,000.00 135,000.00
126,870.00 136,260.00
190,000.00 200,000.00 22,800.00 24,000.00
160,000.00 200,000.00 9,600.00 12,000.00
85,000.00 90,000.00 89,250.00 94,500.00
290,000.00 320,000.00 5,220.00 5,760.00
15,510.00 16,522.00

40,000.00 45,000.00 5,400.00 6,075.00

300,000.00 310,000.00 10,110.00 10,447.00

175,215.00 188,812.00
10% 17,521.50 18,881.20
192,736.50 207,693.20

69,139.13 78,841.54

9,832.50 10,840.00
90,000.00 100,000.00 6,840.00 7,600.00
120,000.00 130,000.00 2,700.00 2,925.00
130,000.00 140,000.00 292.50 315.00
125,000.00 135,000.00
53,021.25 60,834.13
5,100,000.00 5,700,000.00 3,570.00 3,990.00
5,000,000.00 5,400,000.00 6,000.00 6,480.00
17,500.00 18,000.00 35.00 36.00
160,000.00 220,000.00 2,400.00 3,300.00
10,000.00 12,000.00 26,250.00 31,500.00
1,150.00 1,175.00 8,136.25 8,313.13
340,000.00 370,000.00 6,630.00 7,215.00

62,853.75 71,674.13
10% 6,285.38 7,167.41
69,139.13 78,841.54
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN


XVI A.8.4.1
PIPA
1 A.8.4.1.1 1 m' Pemasangan Pipa PVC Ø 63 mm 13,215.95 14,803.25
A Tenaga 6,454.50 7,385.50
L.01 0.081 OH Pekerja 65,000.00 75,000.00 5,265.00 6,075.00
L.02 0.0041 OH Tukang Pipa 95,000.00 105,000.00 389.50 430.50
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan 5,500.00 6,000.00


1 m' Pipa PVC Ø 63 mm 5,500.00 6,000.00 5,500.00 6,000.00

C PERALATAN 60.00 72.00


0.006 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 60.00 72.00

D Jumlah A + B + C 12,014.50 13,457.50


E Overhead & Profit (contoh 10%) 10% 1,201.45 1,345.75
F Harga Satuan Pekerjaan (D+E) 13,215.95 14,803.25

2 A.8.4.1.2 1 m' Pemasangan Pipa PVC Ø 90 mm 20,685.50 22,903.10


A Tenaga 11,475.00 12,975.00
L.01 0.094 OH Pekerja 65,000.00 75,000.00 6,110.00 7,050.00
L.02 0.047 OH Tukang Pipa 95,000.00 105,000.00 4,465.00 4,935.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00

B Bahan 7,250.00 7,750.00


1 m' Pipa PVC Ø 90 mm 7,250.00 7,750.00 7,250.00 7,750.00

C PERALATAN 80.00 96.00


0.008 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 80.00 96.00

D Jumlah A + B + C 18,805.00 20,821.00


E Overhead & Profit (contoh 10%) 10% 1,880.50 2,082.10
F Harga Satuan Pekerjaan (D+E) 20,685.50 22,903.10

3 A.8.4.1.3 1 m' Pemasangan Pipa PVC Ø 110 mm 24,266.00 26,697.00


A Tenaga 12,960.00 14,650.00
L.01 0.105 OH Pekerja 65,000.00 75,000.00 6,825.00 7,875.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan 9,000.00 9,500.00


1 m' Pipa PVC Ø 110 mm 9,000.00 9,500.00 9,000.00 9,500.00

C PERALATAN 100.00 120.00


0.01 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 100.00 120.00

D Jumlah A + B + C 22,060.00 24,270.00


E Overhead & Profit (contoh 10%) 10% 2,206.00 2,427.00
F Harga Satuan Pekerjaan (D+E) 24,266.00 26,697.00

4 A.8.4.1.4 1 m' Pemasangan Pipa PVC Ø 150 mm 42,179.50 48,409.90


A Tenaga 14,475.00 16,365.00
L.01 0.118 OH Pekerja 65,000.00 75,000.00 7,670.00 8,850.00
L.02 0.059 OH Tukang Pipa 95,000.00 105,000.00 5,605.00 6,195.00
L.04 0.012 OH Mandor 100,000.00 110,000.00 1,200.00 1,320.00

B Bahan 23,750.00 27,500.00


1 m' Pipa PVC Ø 150 mm 23,750.00 27,500.00 23,750.00 27,500.00
C PERALATAN 120.00 144.00
0.012 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 120.00 144.00
D Jumlah A + B + C 38,345.00 44,009.00
E Overhead & Profit (contoh 10%) 10% 3,834.50 4,400.90
F Harga Satuan Pekerjaan (D+E) 42,179.50 48,409.90

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/197 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.8.4.1.5 1 m' Pemasangan Pipa PVC Ø 200 mm 67,045.00 73,180.80
A Tenaga 23,210.00 26,240.00
L.01 0.189 OH Pekerja 65,000.00 75,000.00 12,285.00 14,175.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.019 OH Mandor 100,000.00 110,000.00 1,900.00 2,090.00

B Bahan 37,500.00 40,000.00


1 m' Pipa PVC Ø 200 mm 37,500.00 40,000.00 37,500.00 40,000.00

C PERALATAN 240.00 288.00


0.024 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 240.00 288.00

D Jumlah A + B + C 60,950.00 66,528.00


E Overhead & Profit (contoh 10%) 10% 6,095.00 6,652.80
F Harga Satuan Pekerjaan (D+E) 67,045.00 73,180.80

6 A.8.4.1.6 1 m' Pemasangan Pipa PVC Ø 250 mm 118,789.00 127,498.80


A Tenaga 31,400.00 35,500.00
L.01 0.256 OH Pekerja 65,000.00 75,000.00 16,640.00 19,200.00
L.02 0.128 OH Tukang Pipa 95,000.00 105,000.00 12,160.00 13,440.00
L.04 0.026 OH Mandor 100,000.00 110,000.00 2,600.00 2,860.00

B Bahan 76,250.00 80,000.00


1 m' Pipa PVC Ø 250 mm 76,250.00 80,000.00 76,250.00 80,000.00

C PERALATAN 340.00 408.00


0.034 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 340.00 408.00

D Jumlah A + B + C 107,990.00 115,908.00


E Overhead & Profit (contoh 10%) 10% 10,799.00 11,590.80
F Harga Satuan Pekerjaan (D+E) 118,789.00 127,498.80

7 A.8.4.1.7 1 m' Pemasangan Pipa PVC Ø 300 mm 166,512.50 185,520.50


A Tenaga 35,975.00 40,675.00
L.01 0.294 OH Pekerja 65,000.00 75,000.00 19,110.00 22,050.00
L.02 0.147 OH Tukang Pipa 95,000.00 105,000.00 13,965.00 15,435.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00

B Bahan 115,000.00 127,500.00


1 m' Pipa PVC Ø 300 mm 115,000.00 127,500.00 115,000.00 127,500.00

C PERALATAN 400.00 480.00


0.040 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 400.00 480.00

D Jumlah A + B + C 151,375.00 168,655.00


E Overhead & Profit (contoh 10%) 10% 15,137.50 16,865.50
F Harga Satuan Pekerjaan (D+E) 166,512.50 185,520.50

8 A.8.4.1.8 1 m' Pemasangan Pipa PVC Ø 400 mm 338,140.00 372,636.00


A Tenaga 66,600.00 75,300.00
L.01 0.544 OH Pekerja 65,000.00 75,000.00 35,360.00 40,800.00
L.02 0.272 OH Tukang Pipa 95,000.00 105,000.00 25,840.00 28,560.00
L.04 0.054 OH Mandor 100,000.00 110,000.00 5,400.00 5,940.00

B Bahan 240,000.00 262,500.00


1 m' Pipa PVC Ø 400 mm 240,000.00 262,500.00 240,000.00 262,500.00

C PERALATAN 800.00 960.00


0.080 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 800.00 960.00

D Jumlah A + B + C 307,400.00 338,760.00


E Overhead & Profit (contoh 10%) 10% 30,740.00 33,876.00
F Harga Satuan Pekerjaan (D+E) 338,140.00 372,636.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/198 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.8.4.1.9 1 m' Pemasangan Pipa PVC Ø 450 mm 503,811.00 543,312.00
A Tenaga 82,010.00 92,720.00
L.01 0.669 OH Pekerja 65,000.00 75,000.00 43,485.00 50,175.00
L.02 0.335 OH Tukang Pipa 95,000.00 105,000.00 31,825.00 35,175.00
L.04 0.067 OH Mandor 100,000.00 110,000.00 6,700.00 7,370.00

B Bahan 375,000.00 400,000.00


1 m' Pipa PVC Ø 450 mm 375,000.00 400,000.00 375,000.00 400,000.00

C PERALATAN 1,000.00 1,200.00


0.100 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00

D Jumlah A + B + C 458,010.00 493,920.00


E Overhead & Profit (contoh 10%) 10% 45,801.00 49,392.00
F Harga Satuan Pekerjaan (D+E) 503,811.00 543,312.00

10 A.8.4.1.10 1 m' Pemasangan Pipa PVC Ø 500 mm 418,418.00 438,431.40


A Tenaga 99,160.00 112,110.00
L.01 0.809 OH Pekerja 65,000.00 75,000.00 52,585.00 60,675.00
L.02 0.405 OH Tukang Pipa 95,000.00 105,000.00 38,475.00 42,525.00
L.04 0.081 OH Mandor 100,000.00 110,000.00 8,100.00 8,910.00

B Bahan 280,000.00 285,000.00


1 m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 280,000.00 285,000.00

C PERALATAN 1,220.00 1,464.00


0.122 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,220.00 1,464.00

D Jumlah A + B + C 380,380.00 398,574.00


E Overhead & Profit (contoh 10%) 10% 38,038.00 39,857.40
F Harga Satuan Pekerjaan (D+E) 418,418.00 438,431.40

11 A.8.4.1.11 1 m' Pemasangan Pipa PVC Ø 600 mm 487,822.50 526,960.50


A Tenaga 117,025.00 132,315.00
L.01 0.957 OH Pekerja 65,000.00 75,000.00 62,205.00 71,775.00
L.02 0.476 OH Tukang Pipa 95,000.00 105,000.00 45,220.00 49,980.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00

B Bahan 325,000.00 345,000.00


1 m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 325,000.00 345,000.00

C PERALATAN 1,450.00 1,740.00


0.145 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,450.00 1,740.00

D Jumlah A + B + C 443,475.00 479,055.00


E Overhead & Profit (contoh 10%) 10% 44,347.50 47,905.50
F Harga Satuan Pekerjaan (D+E) 487,822.50 526,960.50

12 A.8.4.1.12 1 m' Pemasangan Pipa PVC Ø 800 mm 688,297.50 744,826.50


A Tenaga 198,225.00 224,115.00
L.01 1.618 OH Pekerja 65,000.00 75,000.00 105,170.00 121,350.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00

B Bahan 425,000.00 450,000.00


1 m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 425,000.00 450,000.00

C PERALATAN 2,500.00 3,000.00


0.250 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,500.00 3,000.00

D Jumlah A + B + C 625,725.00 677,115.00


E Overhead & Profit (contoh 10%) 10% 62,572.50 67,711.50
F Harga Satuan Pekerjaan (D+E) 688,297.50 744,826.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/199 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
13 A.8.4.1.13 1 m' Pemasangan Pipa PVC Ø 900 mm 918,285.50 976,127.90
A Tenaga 207,185.00 234,245.00
L.01 1.691 OH Pekerja 65,000.00 75,000.00 109,915.00 126,825.00
L.02 0.846 OH Tukang Pipa 95,000.00 105,000.00 80,370.00 88,830.00
L.04 0.169 OH Mandor 100,000.00 110,000.00 16,900.00 18,590.00

B Bahan 625,000.00 650,000.00


1 m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 625,000.00 650,000.00

C PERALATAN 2,620.00 3,144.00


0.262 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,620.00 3,144.00

D Jumlah A + B + C 834,805.00 887,389.00


E Overhead & Profit (contoh 10%) 10% 83,480.50 88,738.90
F Harga Satuan Pekerjaan (D+E) 918,285.50 976,127.90

14 A.8.4.1.14 1 m' Pemasangan Pipa PVC Ø 1.000 mm 1,061,692.50 1,117,702.30


A 232,235.00 262,565.00
L.01 1.895 OH Pekerja 65,000.00 75,000.00 123,175.00 142,125.00
L.02 0.948 OH Tukang Pipa 95,000.00 105,000.00 90,060.00 99,540.00
L.04 0.190 OH Mandor 100,000.00 110,000.00 19,000.00 20,900.00

B Bahan 730,000.00 750,000.00


1 m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 730,000.00 750,000.00

C PERALATAN 2,940.00 3,528.00


0.294 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,940.00 3,528.00

D Jumlah A + B + C 965,175.00 1,016,093.00


E Overhead & Profit (contoh 10%) 10% 96,517.50 101,609.30
F Harga Satuan Pekerjaan (D+E) 1,061,692.50 1,117,702.30

15 A.8.4.1.15 1 m' Pemasangan Pipa PVC Ø 1.100 mm 1,166,500.50 1,259,168.90


A Tenaga 257,185.00 290,775.00
L.01 2.099 OH Pekerja 65,000.00 75,000.00 136,435.00 157,425.00
L.02 1.050 OH Tukang Pipa 95,000.00 105,000.00 99,750.00 110,250.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00

B Bahan 800,000.00 850,000.00


1 m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 800,000.00 850,000.00

C PERALATAN 3,270.00 3,924.00


0.327 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,270.00 3,924.00

D Jumlah A + B + C 1,060,455.00 1,144,699.00


E Overhead & Profit (contoh 10%) 10% 106,045.50 114,469.90
F Harga Satuan Pekerjaan (D+E) 1,166,500.50 1,259,168.90

16 A.8.4.1.16 1 m' Pemasangan Pipa PVC Ø 1.200 mm 1,249,297.50 1,345,622.30


A Tenaga 282,135.00 318,985.00
L.01 2.303 OH Pekerja 65,000.00 75,000.00 149,695.00 172,725.00
L.02 1.152 OH Tukang Pipa 95,000.00 105,000.00 109,440.00 120,960.00
L.04 0.230 OH Mandor 100,000.00 110,000.00 23,000.00 25,300.00

B Bahan 850,000.00 900,000.00


1 m' Pipa PVC Ø 1.200 mm 850,000.00 900,000.00 850,000.00 900,000.00

C PERALATAN 3,590.00 4,308.00


0.359 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,590.00 4,308.00

D Jumlah A + B + C 1,135,725.00 1,223,293.00


E Overhead & Profit (contoh 10%) 10% 113,572.50 122,329.30
F Harga Satuan Pekerjaan (D+E) 1,249,297.50 1,345,622.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/200 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.8.4.1.17 1 m' Pemasangan Pipa HDPE Ø 63 mm 32,318.00 38,464.80
A Tenaga 4,190.00 4,740.00
L.01 0.035 OH Pekerja 65,000.00 75,000.00 2,275.00 2,625.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

B Bahan 25,000.00 30,000.00


1 m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 190.00 228.00


0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00

D Jumlah A + B + C 29,380.00 34,968.00


E Overhead & Profit (contoh 10%) 10% 2,938.00 3,496.80
F Harga Satuan Pekerjaan (D+E) 32,318.00 38,464.80

18 A.8.4.1.18 1 m' Pemasangan Pipa HDPE Ø 100 mm 44,099.00 50,344.80


A Tenaga 4,900.00 5,540.00
L.01 0.040 OH Pekerja 65,000.00 75,000.00 2,600.00 3,000.00
L.02 0.020 OH Tukang Pipa 95,000.00 105,000.00 1,900.00 2,100.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00

B Bahan 35,000.00 40,000.00


1 m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN 190.00 228.00


0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00

D Jumlah A + B + C 40,090.00 45,768.00


E Overhead & Profit (contoh 10%) 10% 4,009.00 4,576.80
F Harga Satuan Pekerjaan (D+E) 44,099.00 50,344.80

19 A.8.4.1.19 1 m' Pemasangan Pipa HDPE Ø 125 mm 55,880.00 62,224.80


A Tenaga 5,610.00 6,340.00
L.01 0.045 OH Pekerja 65,000.00 75,000.00 2,925.00 3,375.00
L.02 0.023 OH Tukang Pipa 95,000.00 105,000.00 2,185.00 2,415.00
L.04 0.005 OH Mandor 100,000.00 110,000.00 500.00 550.00

B Bahan 45,000.00 50,000.00


1 m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 45,000.00 50,000.00

C PERALATAN 190.00 228.00


0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00

D Jumlah A + B + C 50,800.00 56,568.00


E Overhead & Profit (contoh 10%) 10% 5,080.00 5,656.80
F Harga Satuan Pekerjaan (D+E) 55,880.00 62,224.80

20 A.8.4.1.20 1 m' Pemasangan Pipa HDPE Ø 150 mm 80,041.50 86,672.30


A Tenaga 7,575.00 8,565.00
L.01 0.062 OH Pekerja 65,000.00 75,000.00 4,030.00 4,650.00
L.02 0.031 OH Tukang Pipa 95,000.00 105,000.00 2,945.00 3,255.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00

B Bahan 65,000.00 70,000.00


1 m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 65,000.00 70,000.00

C PERALATAN 190.00 228.00


0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00

D Jumlah A + B + C 72,765.00 78,793.00


E Overhead & Profit (contoh 10%) 10% 7,276.50 7,879.30
F Harga Satuan Pekerjaan (D+E) 80,041.50 86,672.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/201 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.8.4.1.21 1 m' Pemasangan Pipa HDPE Ø 200 mm 134,931.50 147,766.30
A Tenaga 12,475.00 14,105.00
L.01 0.102 OH Pekerja 65,000.00 75,000.00 6,630.00 7,650.00
L.02 0.051 OH Tukang Pipa 95,000.00 105,000.00 4,845.00 5,355.00
L.04 0.010 OH Mandor 100,000.00 110,000.00 1,000.00 1,100.00

B Bahan 110,000.00 120,000.00


1 m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 110,000.00 120,000.00

C PERALATAN 190.00 228.00


0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00

D Jumlah A + B + C 122,665.00 134,333.00


E Overhead & Profit (contoh 10%) 10% 12,266.50 13,433.30
F Harga Satuan Pekerjaan (D+E) 134,931.50 147,766.30

22 A.8.4.1.22 1 m' Pemasangan Pipa HDPE Ø 250 mm 166,903.00 174,838.40


A Tenaga 16,310.00 18,440.00
L.01 0.133 OH Pekerja 65,000.00 75,000.00 8,645.00 9,975.00
L.02 0.067 OH Tukang Pipa 95,000.00 105,000.00 6,365.00 7,035.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan 135,000.00 140,000.00


1 m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 135,000.00 140,000.00

C PERALATAN 420.00 504.00


0.042 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 420.00 504.00

D Jumlah A + B + C 151,730.00 158,944.00


E Overhead & Profit (contoh 10%) 10% 15,173.00 15,894.40
F Harga Satuan Pekerjaan (D+E) 166,903.00 174,838.40

23 A.8.4.1.23 1 m' Pemasangan Pipa HDPE Ø 300 mm 199,622.50 213,757.50


A Tenaga 20,825.00 23,545.00
L.01 0.170 OH Pekerja 65,000.00 75,000.00 11,050.00 12,750.00
L.02 0.085 OH Tukang Pipa 95,000.00 105,000.00 8,075.00 8,925.00
L.04 0.017 OH Mandor 100,000.00 110,000.00 1,700.00 1,870.00

B Bahan 160,000.00 170,000.00


1 m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN 650.00 780.00


0.065 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 650.00 780.00

D Jumlah A + B + C 181,475.00 194,325.00


E Overhead & Profit (contoh 10%) 10% 18,147.50 19,432.50
F Harga Satuan Pekerjaan (D+E) 199,622.50 213,757.50

24 A.8.4.1.24 1 m' Pemasangan Pipa HDPE Ø 400 mm 260,749.50 277,187.90


A Tenaga 35,525.00 40,165.00
L.01 0.290 OH Pekerja 65,000.00 75,000.00 18,850.00 21,750.00
L.02 0.145 OH Tukang Pipa 95,000.00 105,000.00 13,775.00 15,225.00
L.04 0.029 OH Mandor 100,000.00 110,000.00 2,900.00 3,190.00

B Bahan 200,000.00 210,000.00


1 m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN 1,520.00 1,824.00


0.152 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,520.00 1,824.00

D Jumlah A + B + C 237,045.00 251,989.00


E Overhead & Profit (contoh 10%) 10% 23,704.50 25,198.90
F Harga Satuan Pekerjaan (D+E) 260,749.50 277,187.90

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/202 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
25 A.8.4.1.25 1 m' Pemasangan Pipa HDPE Ø 450 mm 314,638.50 332,403.50
A Tenaga 44,035.00 49,785.00
L.01 0.359 OH Pekerja 65,000.00 75,000.00 23,335.00 26,925.00
L.02 0.180 OH Tukang Pipa 95,000.00 105,000.00 17,100.00 18,900.00
L.04 0.036 OH Mandor 100,000.00 110,000.00 3,600.00 3,960.00

B Bahan 240,000.00 250,000.00


1 m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 240,000.00 250,000.00

C PERALATAN 2,000.00 2,400.00


0.200 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,000.00 2,400.00

D Jumlah A + B + C 286,035.00 302,185.00


E Overhead & Profit (contoh 10%) 10% 28,603.50 30,218.50
F Harga Satuan Pekerjaan (D+E) 314,638.50 332,403.50

26 A.8.4.1.26 1 m' Pemasangan Pipa HDPE Ø 500 mm 391,022.50 421,186.70


A Tenaga 52,965.00 59,885.00
L.01 0.433 OH Pekerja 65,000.00 75,000.00 28,145.00 32,475.00
L.02 0.216 OH Tukang Pipa 95,000.00 105,000.00 20,520.00 22,680.00
L.04 0.043 OH Mandor 100,000.00 110,000.00 4,300.00 4,730.00

B Bahan 300,000.00 320,000.00


1 m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 2,510.00 3,012.00


0.251 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,510.00 3,012.00

D Jumlah A + B + C 355,475.00 382,897.00


E Overhead & Profit (contoh 10%) 10% 35,547.50 38,289.70
F Harga Satuan Pekerjaan (D+E) 391,022.50 421,186.70

27 A.8.4.1.27 1 m' Pemasangan Pipa HDPE Ø 600 mm 545,347.00 577,031.40


A Tenaga 62,700.00 70,890.00
L.01 0.512 OH Pekerja 65,000.00 75,000.00 33,280.00 38,400.00
L.02 0.256 OH Tukang Pipa 95,000.00 105,000.00 24,320.00 26,880.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 430,000.00 450,000.00


1 m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 3,070.00 3,684.00


0.307 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,070.00 3,684.00

D Jumlah A + B + C 495,770.00 524,574.00


E Overhead & Profit (contoh 10%) 10% 49,577.00 52,457.40
F Harga Satuan Pekerjaan (D+E) 545,347.00 577,031.40

28 A.8.4.1.28 1 m' Pemasangan Pipa HDPE Ø 800 mm 841,549.50 886,018.10


A Tenaga 109,315.00 123,595.00
L.01 0.893 OH Pekerja 65,000.00 75,000.00 58,045.00 66,975.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.089 OH Mandor 100,000.00 110,000.00 8,900.00 9,790.00

B Bahan 650,000.00 675,000.00


1 m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 650,000.00 675,000.00

C PERALATAN 5,730.00 6,876.00


0.573 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,730.00 6,876.00

D Jumlah A + B + C 765,045.00 805,471.00


E Overhead & Profit (contoh 10%) 10% 76,504.50 80,547.10
F Harga Satuan Pekerjaan (D+E) 841,549.50 886,018.10

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/203 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
29 A.8.4.1.29 1 m' Pemasangan Pipa HDPE Ø 900 mm 1,017,049.00 1,097,806.60
A Tenaga 165,760.00 187,410.00
L.01 1.353 OH Pekerja 65,000.00 75,000.00 87,945.00 101,475.00
L.02 0.677 OH Tukang Pipa 95,000.00 105,000.00 64,315.00 71,085.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 750,000.00 800,000.00


1 m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 750,000.00 800,000.00

C PERALATAN 8,830.00 10,596.00


0.883 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,830.00 10,596.00

D Jumlah A + B + C 924,590.00 998,006.00


E Overhead & Profit (contoh 10%) 10% 92,459.00 99,800.60
F Harga Satuan Pekerjaan (D+E) 1,017,049.00 1,097,806.60

30 A.8.4.1.30 1 m' Pemasangan Pipa HDPE Ø 1.000 mm 1,225,636.50 1,284,746.10


A 203,285.00 229,835.00
L.01 1.659 OH Pekerja 65,000.00 75,000.00 107,835.00 124,425.00
L.02 0.830 OH Tukang Pipa 95,000.00 105,000.00 78,850.00 87,150.00
L.04 0.166 OH Mandor 100,000.00 110,000.00 16,600.00 18,260.00

B Bahan 900,000.00 925,000.00


1 m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 900,000.00 925,000.00

C PERALATAN 10,930.00 13,116.00


1.093 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,930.00 13,116.00

D Jumlah A + B + C 1,114,215.00 1,167,951.00


E Overhead & Profit (contoh 10%) 10% 111,421.50 116,795.10
F Harga Satuan Pekerjaan (D+E) 1,225,636.50 1,284,746.10

31 A.8.4.1.31 1 m' Pemasangan Pipa HDPE Ø 1.100 mm 1,358,252.50 1,447,902.50


A Tenaga 222,725.00 251,815.00
L.01 1.818 OH Pekerja 65,000.00 75,000.00 118,170.00 136,350.00
L.02 0.909 OH Tukang Pipa 95,000.00 105,000.00 86,355.00 95,445.00
L.04 0.182 OH Mandor 100,000.00 110,000.00 18,200.00 20,020.00

B Bahan 1,000,000.00 1,050,000.00


1 m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 1,000,000.00 1,050,000.00

C PERALATAN 12,050.00 14,460.00


1.205 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,050.00 14,460.00

D Jumlah A + B + C 1,234,775.00 1,316,275.00


E Overhead & Profit (contoh 10%) 10% 123,477.50 131,627.50
F Harga Satuan Pekerjaan (D+E) 1,358,252.50 1,447,902.50

32 A.8.4.1.32 1 m' Pemasangan Pipa HDPE Ø 1.200 mm 1,546,781.50 1,646,978.30


A Tenaga 290,325.00 328,245.00
L.01 2.370 OH Pekerja 65,000.00 75,000.00 154,050.00 177,750.00
L.02 1.185 OH Tukang Pipa 95,000.00 105,000.00 112,575.00 124,425.00
L.04 0.237 OH Mandor 100,000.00 110,000.00 23,700.00 26,070.00

B Bahan 1,100,000.00 1,150,000.00


1 m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 1,100,000.00 1,150,000.00

C PERALATAN 15,840.00 19,008.00


1.584 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 15,840.00 19,008.00

D Jumlah A + B + C 1,406,165.00 1,497,253.00


E Overhead & Profit (contoh 10%) 10% 140,616.50 149,725.30
F Harga Satuan Pekerjaan (D+E) 1,546,781.50 1,646,978.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/204 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
33 A.8.4.1.33 1 m' Pemasangan Pipa GIP Ø 63 mm 76,631.50 85,442.50
A Tenaga 42,165.00 47,675.00
L.01 0.345 OH Pekerja 65,000.00 75,000.00 22,425.00 25,875.00
L.02 0.172 OH Tukang Pipa 95,000.00 105,000.00 16,340.00 18,060.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00

B Bahan 27,500.00 30,000.00


1 m' Pipa GIP Ø 63 mm 27,500.00 30,000.00 27,500.00 30,000.00

C PERALATAN - -

hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 69,665.00 77,675.00


E Overhead & Profit (contoh 10%) 10% 6,966.50 7,767.50
F Harga Satuan Pekerjaan (D+E) 76,631.50 85,442.50

34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 91,483.33 104,940.00


A Tenaga 49,000.00 55,400.00
L.01 0.400 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00
L.02 0.200 OH Tukang Pipa 95,000.00 105,000.00 19,000.00 21,000.00
L.04 0.040 OH Mandor 100,000.00 110,000.00 4,000.00 4,400.00

B Bahan 34,166.67 40,000.00


1 m' Pipa GIP Ø 100 mm 34,166.67 40,000.00 34,166.67 40,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 83,166.67 95,400.00


E Overhead & Profit (contoh 10%) 10% 8,316.67 9,540.00
F Harga Satuan Pekerjaan (D+E) 91,483.33 104,940.00

35 A.8.4.1.35 1 m' Pemasangan Pipa GIP Ø 125 mm 118,140.00 130,610.33


A Tenaga 54,900.00 62,070.00
L.01 0.448 OH Pekerja 65,000.00 75,000.00 29,120.00 33,600.00
L.02 0.224 OH Tukang Pipa 95,000.00 105,000.00 21,280.00 23,520.00
L.04 0.045 OH Mandor 100,000.00 110,000.00 4,500.00 4,950.00

B Bahan 52,500.00 56,666.67


1 m' Pipa GIP Ø 125 mm 52,500.00 56,666.67 52,500.00 56,666.67

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 107,400.00 118,736.67


E Overhead & Profit (contoh 10%) 10% 10,740.00 11,873.67
F Harga Satuan Pekerjaan (D+E) 118,140.00 130,610.33

36 A.8.4.1.36 1 m' Pemasangan Pipa GIP Ø 150 mm 139,727.50 152,304.17


A Tenaga 62,025.00 70,125.00
L.01 0.506 OH Pekerja 65,000.00 75,000.00 32,890.00 37,950.00
L.02 0.253 OH Tukang Pipa 95,000.00 105,000.00 24,035.00 26,565.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan 65,000.00 68,333.33


1 m' Pipa GIP Ø 150 mm 65,000.00 68,333.33 65,000.00 68,333.33

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 127,025.00 138,458.33


E Overhead & Profit (contoh 10%) 10% 12,702.50 13,845.83
F Harga Satuan Pekerjaan (D+E) 139,727.50 152,304.17

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/205 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
37 A.8.4.1.37 1 m' Pemasangan Pipa GIP Ø 200 mm 189,805.00 207,485.67
A Tenaga 97,550.00 110,290.00
L.01 0.796 OH Pekerja 65,000.00 75,000.00 51,740.00 59,700.00
L.02 0.398 OH Tukang Pipa 95,000.00 105,000.00 37,810.00 41,790.00
L.04 0.080 OH Mandor 100,000.00 110,000.00 8,000.00 8,800.00

B Bahan 75,000.00 78,333.33


1 m' Pipa GIP Ø 200 mm 75,000.00 78,333.33 75,000.00 78,333.33

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 172,550.00 188,623.33


E Overhead & Profit (contoh 10%) 10% 17,255.00 18,862.33
F Harga Satuan Pekerjaan (D+E) 189,805.00 207,485.67

38 A.8.4.1.38 1 m' Pemasangan Pipa GIP Ø 250 mm 236,107.67 267,483.33


A Tenaga 116,310.00 131,500.00
L.01 0.949 OH Pekerja 65,000.00 75,000.00 61,685.00 71,175.00
L.02 0.475 OH Tukang Pipa 95,000.00 105,000.00 45,125.00 49,875.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00

B Bahan 98,333.33 111,666.67


1 m' Pipa GIP Ø 250 mm 98,333.33 111,666.67 98,333.33 111,666.67

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 214,643.33 243,166.67


E Overhead & Profit (contoh 10%) 10% 21,464.33 24,316.67
F Harga Satuan Pekerjaan (D+E) 236,107.67 267,483.33

39 A.8.4.1.39 1 m' Pemasangan Pipa GIP Ø 300 mm 265,695.83 288,975.50


A Tenaga 117,375.00 132,705.00
L.01 0.958 OH Pekerja 65,000.00 75,000.00 62,270.00 71,850.00
L.02 0.479 OH Tukang Pipa 95,000.00 105,000.00 45,505.00 50,295.00
L.04 0.096 OH Mandor 100,000.00 110,000.00 9,600.00 10,560.00

B Bahan 124,166.67 130,000.00


1 m' Pipa GIP Ø 300 mm 124,166.67 130,000.00 124,166.67 130,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 241,541.67 262,705.00


E Overhead & Profit (contoh 10%) 10% 24,154.17 26,270.50
F Harga Satuan Pekerjaan (D+E) 265,695.83 288,975.50

40 A.8.4.1.40 1 m' Pemasangan Pipa GIP Ø 400 mm 347,545.00 413,790.67


A Tenaga 148,450.00 167,840.00
L.01 1.212 OH Pekerja 65,000.00 75,000.00 78,780.00 90,900.00
L.02 0.606 OH Tukang Pipa 95,000.00 105,000.00 57,570.00 63,630.00
L.04 0.121 OH Mandor 100,000.00 110,000.00 12,100.00 13,310.00

B Bahan 167,500.00 208,333.33


1 m' Pipa GIP Ø 400 mm 167,500.00 208,333.33 167,500.00 208,333.33

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 315,950.00 376,173.33


E Overhead & Profit (contoh 10%) 10% 31,595.00 37,617.33
F Harga Satuan Pekerjaan (D+E) 347,545.00 413,790.67

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/206 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
41 A.8.4.1.41 1 m' Pemasangan Pipa GIP Ø 450 mm 303,231.50 338,035.50
A Tenaga 165,665.00 187,305.00
L.01 1.353 OH Pekerja 65,000.00 75,000.00 87,945.00 101,475.00
L.02 0.676 OH Tukang Pipa 95,000.00 105,000.00 64,220.00 70,980.00
L.04 0.135 OH Mandor 100,000.00 110,000.00 13,500.00 14,850.00

B Bahan 110,000.00 120,000.00


1 m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 110,000.00 120,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 275,665.00 307,305.00


E Overhead & Profit (contoh 10%) 10% 27,566.50 30,730.50
F Harga Satuan Pekerjaan (D+E) 303,231.50 338,035.50

42 A.8.4.1.42 1 m' Pemasangan Pipa GIP Ø 500 mm 352,011.00 388,872.00


A Tenaga 180,010.00 203,520.00
L.01 1.469 OH Pekerja 65,000.00 75,000.00 95,485.00 110,175.00
L.02 0.735 OH Tukang Pipa 95,000.00 105,000.00 69,825.00 77,175.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 140,000.00 150,000.00


1 m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 320,010.00 353,520.00


E Overhead & Profit (contoh 10%) 10% 32,001.00 35,352.00
F Harga Satuan Pekerjaan (D+E) 352,011.00 388,872.00

43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 354,898.50 389,262.50


A Tenaga 162,635.00 183,875.00
L.01 1.327 OH Pekerja 65,000.00 75,000.00 86,255.00 99,525.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 160,000.00 170,000.00


1 m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 322,635.00 353,875.00


E Overhead & Profit (contoh 10%) 10% 32,263.50 35,387.50
F Harga Satuan Pekerjaan (D+E) 354,898.50 389,262.50

44 A.8.4.1.44 1 m' Pemasangan Pipa GIP Ø 800 mm 533,544.00 585,497.00


A Tenaga 285,040.00 322,270.00
L.01 2.327 OH Pekerja 65,000.00 75,000.00 151,255.00 174,525.00
L.02 1.163 OH Tukang Pipa 95,000.00 105,000.00 110,485.00 122,115.00
L.04 0.233 OH Mandor 100,000.00 110,000.00 23,300.00 25,630.00

B Bahan 200,000.00 210,000.00


1 m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 485,040.00 532,270.00


E Overhead & Profit (contoh 10%) 10% 48,504.00 53,227.00
F Harga Satuan Pekerjaan (D+E) 533,544.00 585,497.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/207 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
45 A.8.4.1.45 1 m' Pemasangan Pipa GIP Ø 900 mm 606,468.50 674,635.50
A Tenaga 321,335.00 363,305.00
L.01 2.623 OH Pekerja 65,000.00 75,000.00 170,495.00 196,725.00
L.02 1.312 OH Tukang Pipa 95,000.00 105,000.00 124,640.00 137,760.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan 230,000.00 250,000.00


1 m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 230,000.00 250,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 551,335.00 613,305.00


E Overhead & Profit (contoh 10%) 10% 55,133.50 61,330.50
F Harga Satuan Pekerjaan (D+E) 606,468.50 674,635.50

46 A.8.4.1.46 1 m' Pemasangan Pipa GIP Ø 1.000 mm 678,298.50 740,536.50


A Tenaga 356,635.00 403,215.00
L.01 2.911 OH Pekerja 65,000.00 75,000.00 189,215.00 218,325.00
L.02 1.456 OH Tukang Pipa 95,000.00 105,000.00 138,320.00 152,880.00
L.04 0.291 OH Mandor 100,000.00 110,000.00 29,100.00 32,010.00

B Bahan 260,000.00 270,000.00


1 m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 260,000.00 270,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 616,635.00 673,215.00


E Overhead & Profit (contoh 10%) 10% 61,663.50 67,321.50
F Harga Satuan Pekerjaan (D+E) 678,298.50 740,536.50

47 A.8.4.1.47 1 m' Pemasangan Pipa GIP Ø 1.100 mm 739,200.00 806,520.00


A Tenaga 392,000.00 443,200.00
L.01 3.200 OH Pekerja 65,000.00 75,000.00 208,000.00 240,000.00
L.02 1.600 OH Tukang Pipa 95,000.00 105,000.00 152,000.00 168,000.00
L.04 0.320 OH Mandor 100,000.00 110,000.00 32,000.00 35,200.00

B Bahan 280,000.00 290,000.00


1 m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 280,000.00 290,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 672,000.00 733,200.00


E Overhead & Profit (contoh 10%) 10% 67,200.00 73,320.00
F Harga Satuan Pekerjaan (D+E) 739,200.00 806,520.00

48 A.8.4.1.48 1 m' Pemasangan Pipa GIP Ø 1.200 mm 811,030.00 883,421.00


A Tenaga 427,300.00 483,110.00
L.01 3.488 OH Pekerja 65,000.00 75,000.00 226,720.00 261,600.00
L.02 1.744 OH Tukang Pipa 95,000.00 105,000.00 165,680.00 183,120.00
L.04 0.349 OH Mandor 100,000.00 110,000.00 34,900.00 38,390.00

B Bahan 310,000.00 320,000.00


1 m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 310,000.00 320,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 737,300.00 803,110.00


E Overhead & Profit (contoh 10%) 10% 73,730.00 80,311.00
F Harga Satuan Pekerjaan (D+E) 811,030.00 883,421.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/208 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
49 A.8.4.1.49 1 m' Pemasangan Pipa DCI Ø 100 mm 78,512.50 91,092.10
A Tenaga 45,995.00 52,355.00
L.01 0.489 OH Pekerja 65,000.00 75,000.00 31,785.00 36,675.00
L.02 0.098 OH Tukang Pipa 95,000.00 105,000.00 9,310.00 10,290.00
L.04 0.049 OH Mandor 100,000.00 110,000.00 4,900.00 5,390.00

B Bahan 25,000.00 30,000.00


1 m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 380.00 456.00


0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00

D Jumlah A + B + C 71,375.00 82,811.00


E Overhead & Profit (contoh 10%) 10% 7,137.50 8,281.10
F Harga Satuan Pekerjaan (D+E) 78,512.50 91,092.10

50 A.8.4.1.50 1 m' Pemasangan Pipa DCI Ø 125 mm 100,969.00 114,373.60


A Tenaga 51,410.00 58,520.00
L.01 0.547 OH Pekerja 65,000.00 75,000.00 35,555.00 41,025.00
L.02 0.109 OH Tukang Pipa 95,000.00 105,000.00 10,355.00 11,445.00
L.04 0.055 OH Mandor 100,000.00 110,000.00 5,500.00 6,050.00

B Bahan 40,000.00 45,000.00


1 m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 40,000.00 45,000.00

C PERALATAN 380.00 456.00


0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00

D Jumlah A + B + C 91,790.00 103,976.00


E Overhead & Profit (contoh 10%) 10% 9,179.00 10,397.60
F Harga Satuan Pekerjaan (D+E) 100,969.00 114,373.60

51 A.8.4.1.51 1 m' Pemasangan Pipa DCI Ø 150 mm 129,811.00 149,661.60


A Tenaga 57,630.00 65,600.00
L.01 0.613 OH Pekerja 65,000.00 75,000.00 39,845.00 45,975.00
L.02 0.123 OH Tukang Pipa 95,000.00 105,000.00 11,685.00 12,915.00
L.04 0.061 OH Mandor 100,000.00 110,000.00 6,100.00 6,710.00

B Bahan 60,000.00 70,000.00


1 m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 60,000.00 70,000.00

C PERALATAN 380.00 456.00


0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00

D Jumlah A + B + C 118,010.00 136,056.00


E Overhead & Profit (contoh 10%) 10% 11,801.00 13,605.60
F Harga Satuan Pekerjaan (D+E) 129,811.00 149,661.60

52 A.8.4.1.52 1 m' Pemasangan Pipa DCI Ø 200 mm 176,770.00 200,074.60


A Tenaga 80,320.00 91,430.00
L.01 0.855 OH Pekerja 65,000.00 75,000.00 55,575.00 64,125.00
L.02 0.171 OH Tukang Pipa 95,000.00 105,000.00 16,245.00 17,955.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00

B Bahan 80,000.00 90,000.00


1 m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 80,000.00 90,000.00

C PERALATAN 380.00 456.00


0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00

D Jumlah A + B + C 160,700.00 181,886.00


E Overhead & Profit (contoh 10%) 10% 16,070.00 18,188.60
F Harga Satuan Pekerjaan (D+E) 176,770.00 200,074.60

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/209 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
53 A.8.4.1.53 1 m' Pemasangan Pipa DCI Ø 250 mm 208,851.50 233,557.50
A Tenaga 89,365.00 101,725.00
L.01 0.951 OH Pekerja 65,000.00 75,000.00 61,815.00 71,325.00
L.02 0.190 OH Tukang Pipa 95,000.00 105,000.00 18,050.00 19,950.00
L.04 0.095 OH Mandor 100,000.00 110,000.00 9,500.00 10,450.00

B Bahan 100,000.00 110,000.00


1 m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 500.00 600.00


0.050 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 500.00 600.00

D Jumlah A + B + C 189,865.00 212,325.00


E Overhead & Profit (contoh 10%) 10% 18,986.50 21,232.50
F Harga Satuan Pekerjaan (D+E) 208,851.50 233,557.50

54 A.8.4.1.54 1 m' Pemasangan Pipa DCI Ø 300 mm 233,398.00 258,469.20


A Tenaga 91,470.00 104,120.00
L.01 0.973 OH Pekerja 65,000.00 75,000.00 63,245.00 72,975.00
L.02 0.195 OH Tukang Pipa 95,000.00 105,000.00 18,525.00 20,475.00
L.04 0.097 OH Mandor 100,000.00 110,000.00 9,700.00 10,670.00

B Bahan 120,000.00 130,000.00


1 m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 120,000.00 130,000.00

C PERALATAN 710.00 852.00


0.071 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 710.00 852.00

D Jumlah A + B + C 212,180.00 234,972.00


E Overhead & Profit (contoh 10%) 10% 21,218.00 23,497.20
F Harga Satuan Pekerjaan (D+E) 233,398.00 258,469.20

55 A.8.4.1.55 1 m' Pemasangan Pipa DCI Ø 400 mm 348,606.50 384,446.70


A Tenaga 159,130.00 181,535.00
L.01 1.545 OH Pekerja 65,000.00 75,000.00 100,425.00 115,875.00
L.02 0.309 OH Tukang Pipa 95,000.00 105,000.00 29,355.00 32,445.00
L.08 0.093 OH Operator Alat Berat 150,000.00 175,000.00 13,950.00 16,275.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00
B Bahan 150,000.00 160,000.00
1 m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 150,000.00 160,000.00

C PERALATAN 7,785.00 7,962.00


0.023 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 7,475.00 7,590.00
0.031 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 310.00 372.00
D Jumlah A + B + C 316,915.00 349,497.00
E Overhead & Profit (contoh 10%) 10% 31,691.50 34,949.70
F Harga Satuan Pekerjaan (D+E) 348,606.50 384,446.70

56 A.8.4.1.56 1 m' Pemasangan Pipa DCI Ø 450 mm 408,864.50 444,469.30


A Tenaga 191,880.00 219,025.00
L.01 1.813 OH Pekerja 65,000.00 75,000.00 117,845.00 135,975.00
L.02 0.363 OH Tukang Pipa 95,000.00 105,000.00 34,485.00 38,115.00
L.08 0.143 OH Operator Alat Berat 150,000.00 175,000.00 21,450.00 25,025.00
L.04 0.181 OH Mandor 100,000.00 110,000.00 18,100.00 19,910.00
B Bahan 170,000.00 175,000.00
1 m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 170,000.00 175,000.00

C PERALATAN 9,815.00 10,038.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 371,695.00 404,063.00
E Overhead & Profit (contoh 10%) 10% 37,169.50 40,406.30
F Harga Satuan Pekerjaan (D+E) 408,864.50 444,469.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/210 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
57 A.8.4.1.57 1 m' Pemasangan Pipa DCI Ø 500 mm 465,146.00 511,010.50
A Tenaga 221,360.00 252,795.00
L.01 2.047 OH Pekerja 65,000.00 75,000.00 133,055.00 153,525.00
L.02 0.409 OH Tukang Pipa 95,000.00 105,000.00 38,855.00 42,945.00
L.08 0.193 OH Operator Alat Berat 150,000.00 175,000.00 28,950.00 33,775.00
L.04 0.205 OH Mandor 100,000.00 110,000.00 20,500.00 22,550.00
B Bahan 190,000.00 200,000.00
1 m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 190,000.00 200,000.00

C PERALATAN 11,500.00 11,760.00


0.034 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 11,050.00 11,220.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 422,860.00 464,555.00
E Overhead & Profit (contoh 10%) 10% 42,286.00 46,455.50
F Harga Satuan Pekerjaan (D+E) 465,146.00 511,010.50

58 A.8.4.1.58 1 m' Pemasangan Pipa DCI Ø 600 mm 525,332.50 590,132.40


A Tenaga 232,955.00 266,420.00
L.01 2.011 OH Pekerja 65,000.00 75,000.00 130,715.00 150,825.00
L.02 0.402 OH Tukang Pipa 95,000.00 105,000.00 38,190.00 42,210.00
L.08 0.293 OH Operator Alat Berat 150,000.00 175,000.00 43,950.00 51,275.00
L.04 0.201 OH Mandor 100,000.00 110,000.00 20,100.00 22,110.00
B Bahan 225,000.00 250,000.00
1 m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 225,000.00 250,000.00

C PERALATAN 19,620.00 20,064.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.077 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 770.00 924.00
D Jumlah A + B + C 477,575.00 536,484.00
E Overhead & Profit (contoh 10%) 10% 47,757.50 53,648.40
F Harga Satuan Pekerjaan (D+E) 525,332.50 590,132.40

59 A.8.4.1.59 1 m' Pemasangan Pipa DCI Ø 800 mm 787,902.50 874,104.00


A Tenaga 436,725.00 499,220.00
L.01 3.859 OH Pekerja 65,000.00 75,000.00 250,835.00 289,425.00
L.02 0.772 OH Tukang Pipa 95,000.00 105,000.00 73,340.00 81,060.00
L.08 0.493 OH Operator Alat Berat 150,000.00 175,000.00 73,950.00 86,275.00
L.04 0.386 OH Mandor 100,000.00 110,000.00 38,600.00 42,460.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 29,550.00 30,420.00


0.084 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 27,300.00 27,720.00
0.225 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,250.00 2,700.00
D Jumlah A + B + C 716,275.00 794,640.00
E Overhead & Profit (contoh 10%) 10% 71,627.50 79,464.00
F Harga Satuan Pekerjaan (D+E) 787,902.50 874,104.00

60 A.8.4.1.60 1 m' Pemasangan Pipa DCI Ø 900 mm 925,248.50 1,030,536.10


A Tenaga 558,430.00 638,185.00
L.01 4.995 OH Pekerja 65,000.00 75,000.00 324,675.00 374,625.00
L.02 0.999 OH Tukang Pipa 95,000.00 105,000.00 94,905.00 104,895.00
L.08 0.593 OH Operator Alat Berat 150,000.00 175,000.00 88,950.00 103,775.00
L.04 0.499 OH Mandor 100,000.00 110,000.00 49,900.00 54,890.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 32,705.00 33,666.00


0.093 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 30,225.00 30,690.00
0.248 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,480.00 2,976.00
D Jumlah A + B + C 841,135.00 936,851.00
E Overhead & Profit (contoh 10%) 10% 84,113.50 93,685.10
F Harga Satuan Pekerjaan (D+E) 925,248.50 1,030,536.10

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/211 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
61 A.8.4.1.61 1 m' Pemasangan Pipa DCI Ø 1.000 mm 1,106,396.50 1,226,385.60
A Tenaga 686,435.00 784,360.00
L.01 5.931 OH Pekerja 65,000.00 75,000.00 385,515.00 444,825.00
L.02 1.186 OH Tukang Pipa 95,000.00 105,000.00 112,670.00 124,530.00
L.08 0.793 OH Operator Alat Berat 150,000.00 175,000.00 118,950.00 138,775.00
L.04 0.693 OH Mandor 100,000.00 110,000.00 69,300.00 76,230.00
B Bahan 280,000.00 290,000.00
1 m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 280,000.00 290,000.00

C PERALATAN 39,380.00 40,536.00


0.112 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 36,400.00 36,960.00
0.298 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,980.00 3,576.00
D Jumlah A + B + C 1,005,815.00 1,114,896.00
E Overhead & Profit (contoh 10%) 10% 100,581.50 111,489.60
F Harga Satuan Pekerjaan (D+E) 1,106,396.50 1,226,385.60

62 A.8.4.1.62 1 m' Pemasangan Pipa DCI Ø 1.100 mm 1,237,087.50 1,381,773.80


A Tenaga 772,185.00 882,350.00
L.01 6.949 OH Pekerja 65,000.00 75,000.00 451,685.00 521,175.00
L.02 1.390 OH Tukang Pipa 95,000.00 105,000.00 132,050.00 145,950.00
L.08 0.793 OH Operator Alat Berat 150,000.00 175,000.00 118,950.00 138,775.00
L.04 0.695 OH Mandor 100,000.00 110,000.00 69,500.00 76,450.00
B Bahan 300,000.00 320,000.00
1 m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 52,440.00 53,808.00


0.152 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 49,400.00 50,160.00
0.304 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,040.00 3,648.00
D Jumlah A + B + C 1,124,625.00 1,256,158.00
E Overhead & Profit (contoh 10%) 10% 112,462.50 125,615.80
F Harga Satuan Pekerjaan (D+E) 1,237,087.50 1,381,773.80

63 A.8.4.1.63 1 m' Pemasangan Pipa DCI Ø 1.200 mm 1,400,668.50 1,564,211.00


A Tenaga 891,235.00 1,018,290.00
L.01 8.056 OH Pekerja 65,000.00 75,000.00 523,640.00 604,200.00
L.02 1.611 OH Tukang Pipa 95,000.00 105,000.00 153,045.00 169,155.00
L.08 0.893 OH Operator Alat Berat 150,000.00 175,000.00 133,950.00 156,275.00
L.04 0.806 OH Mandor 100,000.00 110,000.00 80,600.00 88,660.00
B Bahan 320,000.00 340,000.00
1 m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 320,000.00 340,000.00

C PERALATAN 62,100.00 63,720.00


0.180 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 58,500.00 59,400.00
0.360 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,600.00 4,320.00
D Jumlah A + B + C 1,273,335.00 1,422,010.00
E Overhead & Profit (contoh 10%) 10% 127,333.50 142,201.00
F Harga Satuan Pekerjaan (D+E) 1,400,668.50 1,564,211.00

64 A.8.4.1.64 1 m' Pemasangan Baja PVC Ø 63 mm 64,872.50 73,120.30


A Tenaga 46,935.00 53,425.00
L.01 0.499 OH Pekerja 65,000.00 75,000.00 32,435.00 37,425.00
L.02 0.100 OH Tukang Pipa 95,000.00 105,000.00 9,500.00 10,500.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan 12,000.00 13,000.00


1 m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 58,975.00 66,473.00


E Overhead & Profit (contoh 10%) 10% 5,897.50 6,647.30
F Harga Satuan Pekerjaan (D+E) 64,872.50 73,120.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/212 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
65 A.8.4.1.65 1 m' Pemasangan Pipa Baja Ø 100 mm 73,694.50 84,736.30
A Tenaga 54,455.00 61,985.00
L.01 0.579 OH Pekerja 65,000.00 75,000.00 37,635.00 43,425.00
L.02 0.116 OH Tukang Pipa 95,000.00 105,000.00 11,020.00 12,180.00
L.04 0.058 OH Mandor 100,000.00 110,000.00 5,800.00 6,380.00

B Bahan 12,500.00 15,000.00


1 m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 12,500.00 15,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 66,995.00 77,033.00


E Overhead & Profit (contoh 10%) 10% 6,699.50 7,703.30
F Harga Satuan Pekerjaan (D+E) 73,694.50 84,736.30

66 A.8.4.1.66 1 m' Pemasangan Pipa Baja Ø 125 mm 83,611.00 95,092.80


A Tenaga 60,970.00 69,400.00
L.01 0.648 OH Pekerja 65,000.00 75,000.00 42,120.00 48,600.00
L.02 0.130 OH Tukang Pipa 95,000.00 105,000.00 12,350.00 13,650.00
L.04 0.065 OH Mandor 100,000.00 110,000.00 6,500.00 7,150.00

B Bahan 15,000.00 17,000.00


1 m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 15,000.00 17,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 76,010.00 86,448.00


E Overhead & Profit (contoh 10%) 10% 7,601.00 8,644.80
F Harga Satuan Pekerjaan (D+E) 83,611.00 95,092.80

67 A.8.4.1.67 1 m' Pemasangan Pipa Baja Ø 150 mm 95,315.00 110,954.80


A Tenaga 66,610.00 75,820.00
L.01 0.708 OH Pekerja 65,000.00 75,000.00 46,020.00 53,100.00
L.02 0.142 OH Tukang Pipa 95,000.00 105,000.00 13,490.00 14,910.00
L.04 0.071 OH Mandor 100,000.00 110,000.00 7,100.00 7,810.00

B Bahan 20,000.00 25,000.00


1 m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 20,000.00 25,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 86,650.00 100,868.00


E Overhead & Profit (contoh 10%) 10% 8,665.00 10,086.80
F Harga Satuan Pekerjaan (D+E) 95,315.00 110,954.80

68 A.8.4.1.68 1 m' Pemasangan Pipa Baja Ø 200 mm 148,137.00 169,562.80


A Tenaga 104,630.00 119,100.00
L.01 1.113 OH Pekerja 65,000.00 75,000.00 72,345.00 83,475.00
L.02 0.223 OH Tukang Pipa 95,000.00 105,000.00 21,185.00 23,415.00
L.04 0.111 OH Mandor 100,000.00 110,000.00 11,100.00 12,210.00

B Bahan 30,000.00 35,000.00


1 m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 30,000.00 35,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 134,670.00 154,148.00


E Overhead & Profit (contoh 10%) 10% 13,467.00 15,414.80
F Harga Satuan Pekerjaan (D+E) 148,137.00 169,562.80

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/213 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
69 A.8.4.1.69 1 m' Pemasangan Pipa Baja Ø 250 mm 192,104.00 222,065.80
A Tenaga 124,600.00 141,830.00
L.01 1.325 OH Pekerja 65,000.00 75,000.00 86,125.00 99,375.00
L.02 0.265 OH Tukang Pipa 95,000.00 105,000.00 25,175.00 27,825.00
L.04 0.133 OH Mandor 100,000.00 110,000.00 13,300.00 14,630.00

B Bahan 50,000.00 60,000.00


1 m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 50,000.00 60,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 174,640.00 201,878.00


E Overhead & Profit (contoh 10%) 10% 17,464.00 20,187.80
F Harga Satuan Pekerjaan (D+E) 192,104.00 222,065.80

70 A.8.4.1.70 1 m' Pemasangan Pipa Baja Ø 300 mm 223,300.00 249,037.80


A Tenaga 132,960.00 151,350.00
L.01 1.415 OH Pekerja 65,000.00 75,000.00 91,975.00 106,125.00
L.02 0.283 OH Tukang Pipa 95,000.00 105,000.00 26,885.00 29,715.00
L.04 0.141 OH Mandor 100,000.00 110,000.00 14,100.00 15,510.00

B Bahan 70,000.00 75,000.00


1 m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 70,000.00 75,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 203,000.00 226,398.00


E Overhead & Profit (contoh 10%) 10% 20,300.00 22,639.80
F Harga Satuan Pekerjaan (D+E) 223,300.00 249,037.80

71 A.8.4.1.71 1 m' Pemasangan Pipa Baja Ø 400 mm 334,235.00 371,869.30


A Tenaga 209,685.00 238,685.00
L.01 2.231 OH Pekerja 65,000.00 75,000.00 145,015.00 167,325.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 85,000.00 90,000.00


1 m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 85,000.00 90,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 303,850.00 338,063.00
E Overhead & Profit (contoh 10%) 10% 30,385.00 33,806.30
F Harga Satuan Pekerjaan (D+E) 334,235.00 371,869.30

72 A.8.4.1.72 1 m' Pemasangan Pipa Baja Ø 450 mm 350,355.50 393,479.90


A Tenaga 209,685.00 238,685.00
L.01 2.231 OH Pekerja 65,000.00 75,000.00 145,015.00 167,325.00
L.02 0.446 OH Tukang Pipa 95,000.00 105,000.00 42,370.00 46,830.00
L.04 0.223 OH Mandor 100,000.00 110,000.00 22,300.00 24,530.00

B Bahan 100,000.00 110,000.00


1 m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 8,820.00 9,024.00


0.026 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,450.00 8,580.00
0.037 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 370.00 444.00
D Jumlah A + B + C 318,505.00 357,709.00
E Overhead & Profit (contoh 10%) 10% 31,850.50 35,770.90
F Harga Satuan Pekerjaan (D+E) 350,355.50 393,479.90

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/214 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
73 A.8.4.1.73 1 m' Pemasangan Pipa Baja Ø 500 mm 399,767.50 462,297.00
A Tenaga 228,550.00 260,160.00
L.01 2.432 OH Pekerja 65,000.00 75,000.00 158,080.00 182,400.00
L.02 0.486 OH Tukang Pipa 95,000.00 105,000.00 46,170.00 51,030.00
L.04 0.243 OH Mandor 100,000.00 110,000.00 24,300.00 26,730.00

B Bahan 125,000.00 150,000.00


1 m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 125,000.00 150,000.00

C PERALATAN 9,875.00 10,110.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 363,425.00 420,270.00
E Overhead & Profit (contoh 10%) 10% 36,342.50 42,027.00
F Harga Satuan Pekerjaan (D+E) 399,767.50 462,297.00

74 A.8.4.1.74 1 m' Pemasangan Pipa Baja Ø 600 mm 436,452.50 490,267.80


A Tenaga 207,610.00 236,320.00
L.01 2.208 OH Pekerja 65,000.00 75,000.00 143,520.00 165,600.00
L.02 0.442 OH Tukang Pipa 95,000.00 105,000.00 41,990.00 46,410.00
L.04 0.221 OH Mandor 100,000.00 110,000.00 22,100.00 24,310.00

B Bahan 180,000.00 200,000.00


1 m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 180,000.00 200,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 396,775.00 445,698.00
E Overhead & Profit (contoh 10%) 10% 39,677.50 44,569.80
F Harga Satuan Pekerjaan (D+E) 436,452.50 490,267.80

75 A.8.4.1.75 1 m' Pemasangan Pipa Baja Ø 800 mm 695,464.00 779,158.60


A Tenaga 366,310.00 416,970.00
L.01 3.897 OH Pekerja 65,000.00 75,000.00 253,305.00 292,275.00
L.02 0.779 OH Tukang Pipa 95,000.00 105,000.00 74,005.00 81,795.00
L.04 0.390 OH Mandor 100,000.00 110,000.00 39,000.00 42,900.00

B Bahan 250,000.00 275,000.00


1 m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 250,000.00 275,000.00

C PERALATAN 15,930.00 16,356.00


0.046 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 14,950.00 15,180.00
0.098 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 980.00 1,176.00
D Jumlah A + B + C 632,240.00 708,326.00
E Overhead & Profit (contoh 10%) 10% 63,224.00 70,832.60
F Harga Satuan Pekerjaan (D+E) 695,464.00 779,158.60

76 A.8.4.1.76 1 m' Pemasangan Pipa Baja Ø 900 mm 797,714.50 882,436.50


A Tenaga 407,145.00 463,675.00
L.01 4.403 OH Pekerja 65,000.00 75,000.00 286,195.00 330,225.00
L.02 0.810 OH Tukang Pipa 95,000.00 105,000.00 76,950.00 85,050.00
L.04 0.440 OH Mandor 100,000.00 110,000.00 44,000.00 48,400.00

B Bahan 300,000.00 320,000.00


1 m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 18,050.00 18,540.00


0.052 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 16,900.00 17,160.00
0.115 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,150.00 1,380.00
D Jumlah A + B + C 725,195.00 802,215.00
E Overhead & Profit (contoh 10%) 10% 72,519.50 80,221.50
F Harga Satuan Pekerjaan (D+E) 797,714.50 882,436.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/215 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
77 A.8.4.1.77 1 m' Pemasangan Pipa Baja Ø 1.000 mm 913,286.00 1,011,390.60
A Tenaga 460,080.00 523,710.00
L.01 4.895 OH Pekerja 65,000.00 75,000.00 318,175.00 367,125.00
L.02 0.979 OH Tukang Pipa 95,000.00 105,000.00 93,005.00 102,795.00
L.04 0.489 OH Mandor 100,000.00 110,000.00 48,900.00 53,790.00

B Bahan 350,000.00 375,000.00


1 m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 350,000.00 375,000.00

C PERALATAN 20,180.00 20,736.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.133 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,330.00 1,596.00
D Jumlah A + B + C 830,260.00 919,446.00
E Overhead & Profit (contoh 10%) 10% 83,026.00 91,944.60
F Harga Satuan Pekerjaan (D+E) 913,286.00 1,011,390.60

78 A.8.4.1.78 1 m' Pemasangan Pipa Baja Ø 1.100 mm 1,021,537.00 1,126,752.00


A Tenaga 506,370.00 576,400.00
L.01 5.387 OH Pekerja 65,000.00 75,000.00 350,155.00 404,025.00
L.02 1.077 OH Tukang Pipa 95,000.00 105,000.00 102,315.00 113,085.00
L.04 0.539 OH Mandor 100,000.00 110,000.00 53,900.00 59,290.00

B Bahan 400,000.00 425,000.00


1 m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 400,000.00 425,000.00

C PERALATAN 22,300.00 22,920.00


0.064 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 20,800.00 21,120.00
0.15 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,500.00 1,800.00
D Jumlah A + B + C 928,670.00 1,024,320.00
E Overhead & Profit (contoh 10%) 10% 92,867.00 102,432.00
F Harga Satuan Pekerjaan (D+E) 1,021,537.00 1,126,752.00

79 A.8.4.1.79 1 m' Pemasangan Pipa Baja Ø 1.200 mm 1,131,069.50 1,243,592.90


A Tenaga 553,825.00 630,435.00
L.01 5.897 OH Pekerja 65,000.00 75,000.00 383,305.00 442,275.00
L.02 1.176 OH Tukang Pipa 95,000.00 105,000.00 111,720.00 123,480.00
L.04 0.588 OH Mandor 100,000.00 110,000.00 58,800.00 64,680.00

B Bahan 450,000.00 475,000.00


1 m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 450,000.00 475,000.00

C PERALATAN 24,420.00 25,104.00


0.070 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 22,750.00 23,100.00
0.167 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,670.00 2,004.00
D Jumlah A + B + C 1,028,245.00 1,130,539.00
E Overhead & Profit (contoh 10%) 10% 102,824.50 113,053.90
F Harga Satuan Pekerjaan (D+E) 1,131,069.50 1,243,592.90

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/216 16-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMOTONGAN


XVII A.8.4.2
PIPA
1 A.8.4.2.1 1 bh Pemotongan Pipa PVC Ø 63 mm 647.90 737.00
A Tenaga 565.00 640.00
L.01 0.005 OH Pekerja 65,000.00 75,000.00 325.00 375.00
L.02 0.002 OH Tukang Pipa 95,000.00 105,000.00 190.00 210.00
L.04 0.0005 OH Mandor 100,000.00 110,000.00 50.00 55.00

B Bahan - -
- m' Pipa PVC Ø 63 mm 5,500.00 6,000.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 589.00 670.00


E Overhead & Profit (contoh 10%) 10% 58.90 67.00
F Harga Satuan Pekerjaan (D+E) 647.90 737.00

2 A.8.4.2.2 1 bh Pemotongan Pipa PVC Ø 90 mm 1,868.90 2,117.50


A Tenaga 1,675.00 1,895.00
L.01 0.014 OH Pekerja 65,000.00 75,000.00 910.00 1,050.00
L.02 0.007 OH Tukang Pipa 95,000.00 105,000.00 665.00 735.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00

B Bahan - -
- m' Pipa PVC Ø 90 mm 7,250.00 7,750.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 1,699.00 1,925.00


E Overhead & Profit (contoh 10%) 10% 169.90 192.50
F Harga Satuan Pekerjaan (D+E) 1,868.90 2,117.50

3 A.8.4.2.3 1 bh Pemotongan Pipa PVC Ø 110 mm 2,968.90 3,360.50


A Tenaga 2,675.00 3,025.00
L.01 0.022 OH Pekerja 65,000.00 75,000.00 1,430.00 1,650.00
L.02 0.011 OH Tukang Pipa 95,000.00 105,000.00 1,045.00 1,155.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00

B Bahan - -
- m' Pipa PVC Ø 110 mm 9,000.00 9,500.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 2,699.00 3,055.00


E Overhead & Profit (contoh 10%) 10% 269.90 305.50
F Harga Satuan Pekerjaan (D+E) 2,968.90 3,360.50

4 A.8.4.2.4 1 bh Pemotongan Pipa PVC Ø 150 mm 4,140.40 4,686.00


A Tenaga 3,740.00 4,230.00
L.01 0.031 OH Pekerja 65,000.00 75,000.00 2,015.00 2,325.00
L.02 0.015 OH Tukang Pipa 95,000.00 105,000.00 1,425.00 1,575.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

B Bahan - -
- m' Pipa PVC Ø 150 mm 23,750.00 27,500.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 3,764.00 4,260.00


E Overhead & Profit (contoh 10%) 10% 376.40 426.00
F Harga Satuan Pekerjaan (D+E) 4,140.40 4,686.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/217 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.8.4.2.5 1 bh Pemotongan Pipa PVC Ø 200 mm 11,001.10 12,457.50
A Tenaga 9,865.00 11,155.00
L.01 0.081 OH Pekerja 65,000.00 75,000.00 5,265.00 6,075.00
L.02 0.040 OH Tukang Pipa 95,000.00 105,000.00 3,800.00 4,200.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
- m' Pipa PVC Ø 200 mm 37,500.00 40,000.00 - -

C PERALATAN 136.00 170.00


0.017 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 136.00 170.00

D Jumlah A + B + C 10,001.00 11,325.00


E Overhead & Profit (contoh 10%) 10% 1,000.10 1,132.50
F Harga Satuan Pekerjaan (D+E) 11,001.10 12,457.50

6 A.8.4.2.6 1 bh Pemotongan Pipa PVC Ø 250 mm 17,534.00 19,855.00


A Tenaga 15,700.00 17,750.00
L.01 0.128 OH Pekerja 65,000.00 75,000.00 8,320.00 9,600.00
L.02 0.064 OH Tukang Pipa 95,000.00 105,000.00 6,080.00 6,720.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa PVC Ø 250 mm 76,250.00 80,000.00 - -

C PERALATAN 240.00 300.00


0.03 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 240.00 300.00

D Jumlah A + B + C 15,940.00 18,050.00


E Overhead & Profit (contoh 10%) 10% 1,594.00 1,805.00
F Harga Satuan Pekerjaan (D+E) 17,534.00 19,855.00

7 A.8.4.2.7 1 bh Pemotongan Pipa PVC Ø 300 mm 21,104.60 23,903.00


A Tenaga 18,890.00 21,360.00
L.01 0.155 OH Pekerja 65,000.00 75,000.00 10,075.00 11,625.00
L.02 0.077 OH Tukang Pipa 95,000.00 105,000.00 7,315.00 8,085.00
L.04 0.015 OH Mandor 100,000.00 110,000.00 1,500.00 1,650.00

B Bahan - -
- m' Pipa PVC Ø 300 mm 115,000.00 127,500.00 - -

C PERALATAN 296.00 370.00


0.037 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 296.00 370.00

D Jumlah A + B + C 19,186.00 21,730.00


E Overhead & Profit (contoh 10%) 10% 1,918.60 2,173.00
F Harga Satuan Pekerjaan (D+E) 21,104.60 23,903.00

8 A.8.4.2.8 1 bh Pemotongan Pipa PVC Ø 400 mm 45,400.30 51,419.50


A Tenaga 40,585.00 45,885.00
L.01 0.331 OH Pekerja 65,000.00 75,000.00 21,515.00 24,825.00
L.02 0.166 OH Tukang Pipa 95,000.00 105,000.00 15,770.00 17,430.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan - -
- m' Pipa PVC Ø 400 mm 240,000.00 262,500.00 - -

C PERALATAN 688.00 860.00


0.086 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 688.00 860.00

D Jumlah A + B + C 41,273.00 46,745.00


E Overhead & Profit (contoh 10%) 10% 4,127.30 4,674.50
F Harga Satuan Pekerjaan (D+E) 45,400.30 51,419.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/218 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.8.4.2.9 1 bh Pemotongan Pipa PVC Ø 450 mm 58,080.00 65,769.00
A Tenaga 51,450.00 58,170.00
L.01 0.420 OH Pekerja 65,000.00 75,000.00 27,300.00 31,500.00
L.02 0.210 OH Tukang Pipa 95,000.00 105,000.00 19,950.00 22,050.00
L.04 0.042 OH Mandor 100,000.00 110,000.00 4,200.00 4,620.00

B Bahan - -
- m' Pipa PVC Ø 450 mm 375,000.00 400,000.00 - -

C PERALATAN 1,350.00 1,620.00


0.054 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,350.00 1,620.00

D Jumlah A + B + C 52,800.00 59,790.00


E Overhead & Profit (contoh 10%) 10% 5,280.00 5,979.00
F Harga Satuan Pekerjaan (D+E) 58,080.00 65,769.00

10 A.8.4.2.10 1 bh Pemotongan Pipa PVC Ø 500 mm 71,720.00 81,218.50


A Tenaga 63,475.00 71,765.00
L.01 0.518 OH Pekerja 65,000.00 75,000.00 33,670.00 38,850.00
L.02 0.259 OH Tukang Pipa 95,000.00 105,000.00 24,605.00 27,195.00
L.04 0.052 OH Mandor 100,000.00 110,000.00 5,200.00 5,720.00

B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -

C PERALATAN 1,725.00 2,070.00


0.069 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,725.00 2,070.00

D Jumlah A + B + C 65,200.00 73,835.00


E Overhead & Profit (contoh 10%) 10% 6,520.00 7,383.50
F Harga Satuan Pekerjaan (D+E) 71,720.00 81,218.50

11 A.8.4.2.11 1 bh Pemotongan Pipa PVC Ø 600 mm 86,229.00 97,658.00


A Tenaga 76,240.00 86,200.00
L.01 0.623 OH Pekerja 65,000.00 75,000.00 40,495.00 46,725.00
L.02 0.311 OH Tukang Pipa 95,000.00 105,000.00 29,545.00 32,655.00
L.04 0.062 OH Mandor 100,000.00 110,000.00 6,200.00 6,820.00

B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -

C PERALATAN 2,150.00 2,580.00


0.086 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,150.00 2,580.00

D Jumlah A + B + C 78,390.00 88,780.00


E Overhead & Profit (contoh 10%) 10% 7,839.00 8,878.00
F Harga Satuan Pekerjaan (D+E) 86,229.00 97,658.00

12 A.8.4.2.12 1 bh Pemasangan Pipa PVC Ø 800 mm 151,206.00 171,259.00


A Tenaga 133,460.00 150,890.00
L.01 1.089 OH Pekerja 65,000.00 75,000.00 70,785.00 81,675.00
L.02 0.545 OH Tukang Pipa 95,000.00 105,000.00 51,775.00 57,225.00
L.04 0.109 OH Mandor 100,000.00 110,000.00 10,900.00 11,990.00

B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -

C PERALATAN 4,000.00 4,800.00


0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00

D Jumlah A + B + C 137,460.00 155,690.00


E Overhead & Profit (contoh 10%) 10% 13,746.00 15,569.00
F Harga Satuan Pekerjaan (D+E) 151,206.00 171,259.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/219 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 158,411.00 179,421.00
A Tenaga 139,810.00 158,070.00
L.01 1.141 OH Pekerja 65,000.00 75,000.00 74,165.00 85,575.00
L.02 0.571 OH Tukang Pipa 95,000.00 105,000.00 54,245.00 59,955.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00

B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -

C PERALATAN 4,200.00 5,040.00


0.168 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,200.00 5,040.00

D Jumlah A + B + C 144,010.00 163,110.00


E Overhead & Profit (contoh 10%) 10% 14,401.00 16,311.00
F Harga Satuan Pekerjaan (D+E) 158,411.00 179,421.00

14 A.8.4.2.14 1 bh Pemotongan Pipa PVC Ø 1.000 mm 178,513.50 202,191.00


A , 157,510.00 178,080.00
L.01 1.285 OH Pekerja 65,000.00 75,000.00 83,525.00 96,375.00
L.02 0.643 OH Tukang Pipa 95,000.00 105,000.00 61,085.00 67,515.00
L.04 0.129 OH Mandor 100,000.00 110,000.00 12,900.00 14,190.00

B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -

C PERALATAN 4,775.00 5,730.00


0.191 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,775.00 5,730.00

D Jumlah A + B + C 162,285.00 183,810.00


E Overhead & Profit (contoh 10%) 10% 16,228.50 18,381.00
F Harga Satuan Pekerjaan (D+E) 178,513.50 202,191.00

15 A.8.4.2.15 1 bh Pemotongan Pipa PVC Ø 1.100 mm 198,478.50 224,807.00


A Tenaga 175,110.00 197,980.00
L.01 1.429 OH Pekerja 65,000.00 75,000.00 92,885.00 107,175.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -

C PERALATAN 5,325.00 6,390.00


0.213 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,325.00 6,390.00

D Jumlah A + B + C 180,435.00 204,370.00


E Overhead & Profit (contoh 10%) 10% 18,043.50 20,437.00
F Harga Satuan Pekerjaan (D+E) 198,478.50 224,807.00

16 A.8.4.2.16 1 bh Pemotongan Pipa PVC Ø 1.200 mm 218,471.00 247,456.00


A Tenaga 192,710.00 217,880.00
L.01 1.573 OH Pekerja 65,000.00 75,000.00 102,245.00 117,975.00
L.02 0.787 OH Tukang Pipa 95,000.00 105,000.00 74,765.00 82,635.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -

C PERALATAN 5,900.00 7,080.00


0.236 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,900.00 7,080.00

D Jumlah A + B + C 198,610.00 224,960.00


E Overhead & Profit (contoh 10%) 10% 19,861.00 22,496.00
F Harga Satuan Pekerjaan (D+E) 218,471.00 247,456.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/220 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.8.4.2.17 1 bh Pemotongan Pipa HDPE Ø 63 mm 4,119.50 4,550.70
A Tenaga 3,645.00 4,017.00
L.01 0.002 OH Pekerja 65,000.00 75,000.00 130.00 150.00
L.02 0.001 OH Tukang Pipa 95,000.00 105,000.00 95.00 105.00
L.04 0.0002 OH Mandor 100,000.00 110,000.00 20.00 22.00
L.08 0.0340 OH Operator 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan - -
- m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 - -

C PERALATAN 100.00 120.00


0.004 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 100.00 120.00

D Jumlah A + B + C 3,745.00 4,137.00


E Overhead & Profit (contoh 10%) 10% 374.50 413.70
F Harga Satuan Pekerjaan (D+E) 4,119.50 4,550.70

18 A.8.4.2.18 1 bh Pemotongan Pipa HDPE Ø 100 mm 8,800.00 9,718.50


A Tenaga 7,875.00 8,685.00
L.01 0.006 OH Pekerja 65,000.00 75,000.00 390.00 450.00
L.02 0.003 OH Tukang Pipa 95,000.00 105,000.00 285.00 315.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.071 OH Operator 100,000.00 110,000.00 7,100.00 7,810.00
B Bahan - -
- m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 - -

C PERALATAN 125.00 150.00


0.005 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 125.00 150.00

D Jumlah A + B + C 8,000.00 8,835.00


E Overhead & Profit (contoh 10%) 10% 800.00 883.50
F Harga Satuan Pekerjaan (D+E) 8,800.00 9,718.50

19 A.8.4.2.19 1 bh Pemotongan Pipa HDPE Ø 125 mm 12,001.00 13,255.00


A Tenaga 10,760.00 11,870.00
L.01 0.009 OH Pekerja 65,000.00 75,000.00 585.00 675.00
L.02 0.005 OH Tukang Pipa 95,000.00 105,000.00 475.00 525.00
L.04 0.001 OH Mandor 100,000.00 110,000.00 100.00 110.00
L.08 0.096 OH Operator 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan - -
- m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 - -

C PERALATAN 150.00 180.00


0.006 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 150.00 180.00

D Jumlah A + B + C 10,910.00 12,050.00


E Overhead & Profit (contoh 10%) 10% 1,091.00 1,205.00
F Harga Satuan Pekerjaan (D+E) 12,001.00 13,255.00

20 A.8.4.2.20 1 bh Pemotongan Pipa HDPE Ø 150 mm 15,757.50 17,424.00


A Tenaga 14,100.00 15,570.00
L.01 0.016 OH Pekerja 65,000.00 75,000.00 1,040.00 1,200.00
L.02 0.008 OH Tukang Pipa 95,000.00 105,000.00 760.00 840.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00
L.08 0.121 OH Operator 100,000.00 110,000.00 12,100.00 13,310.00
B Bahan - -
- m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 - -

C PERALATAN 225.00 270.00


0.009 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 225.00 270.00

D Jumlah A + B + C 14,325.00 15,840.00


E Overhead & Profit (contoh 10%) 10% 1,432.50 1,584.00
F Harga Satuan Pekerjaan (D+E) 15,757.50 17,424.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/221 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.8.4.2.21 1 bh Pemotongan Pipa HDPE Ø 200 mm 25,162.50 27,907.00
A Tenaga 22,450.00 24,860.00
L.01 0.044 OH Pekerja 65,000.00 75,000.00 2,860.00 3,300.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.004 OH Mandor 100,000.00 110,000.00 400.00 440.00
L.08 0.171 OH Operator 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan - -
m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 - -

C PERALATAN 425.00 510.00


0.017 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 425.00 510.00

D Jumlah A + B + C 22,875.00 25,370.00


E Overhead & Profit (contoh 10%) 10% 2,287.50 2,537.00
F Harga Satuan Pekerjaan (D+E) 25,162.50 27,907.00

22 A.8.4.2.22 1 bh Pemotongan Pipa HDPE Ø 250 mm 33,951.50 37,686.00


A Tenaga 30,290.00 33,570.00
L.01 0.067 OH Pekerja 65,000.00 75,000.00 4,355.00 5,025.00
L.02 0.033 OH Tukang Pipa 95,000.00 105,000.00 3,135.00 3,465.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00
L.08 0.221 OH Operator 100,000.00 110,000.00 22,100.00 24,310.00
B Bahan - -
- m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 - -

C PERALATAN 575.00 690.00


0.023 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 575.00 690.00

D Jumlah A + B + C 30,865.00 34,260.00


E Overhead & Profit (contoh 10%) 10% 3,086.50 3,426.00
F Harga Satuan Pekerjaan (D+E) 33,951.50 37,686.00

23 A.8.4.2.23 1 bh Pemotongan Pipa HDPE Ø 300 mm 42,762.50 47,492.50


A Tenaga 38,125.00 42,275.00
L.01 0.090 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.045 OH Tukang Pipa 95,000.00 105,000.00 4,275.00 4,725.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00
L.08 0.271 OH Operator 100,000.00 110,000.00 27,100.00 29,810.00
B Bahan - -
- m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 - -

C PERALATAN 750.00 900.00


0.030 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 750.00 900.00

D Jumlah A + B + C 38,875.00 43,175.00


E Overhead & Profit (contoh 10%) 10% 3,887.50 4,317.50
F Harga Satuan Pekerjaan (D+E) 42,762.50 47,492.50

24 A.8.4.2.24 1 bh Pemotongan Pipa HDPE Ø 400 mm 66,154.00 73,650.50


A Tenaga 58,765.00 65,305.00
L.01 0.177 OH Pekerja 65,000.00 75,000.00 11,505.00 13,275.00
L.02 0.088 OH Tukang Pipa 95,000.00 105,000.00 8,360.00 9,240.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00
L.08 0.371 OH Operator 100,000.00 110,000.00 37,100.00 40,810.00
B Bahan - -
- m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 - -

C PERALATAN 1,375.00 1,650.00


0.055 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,375.00 1,650.00

D Jumlah A + B + C 60,140.00 66,955.00


E Overhead & Profit (contoh 10%) 10% 6,014.00 6,695.50
F Harga Satuan Pekerjaan (D+E) 66,154.00 73,650.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/222 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
25 A.8.4.2.25 1 bh Pemotongan Pipa HDPE Ø 450 mm 78,661.00 87,648.00
A Tenaga 69,760.00 77,580.00
L.01 0.225 OH Pekerja 65,000.00 75,000.00 14,625.00 16,875.00
L.02 0.113 OH Tukang Pipa 95,000.00 105,000.00 10,735.00 11,865.00
L.04 0.023 OH Mandor 100,000.00 110,000.00 2,300.00 2,530.00
L.08 0.421 OH Operator 100,000.00 110,000.00 42,100.00 46,310.00
B Bahan - -
- m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 - -

C PERALATAN 1,750.00 2,100.00


0.070 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,750.00 2,100.00

D Jumlah A + B + C 71,510.00 79,680.00


E Overhead & Profit (contoh 10%) 10% 7,151.00 7,968.00
F Harga Satuan Pekerjaan (D+E) 78,661.00 87,648.00

26 A.8.4.2.26 1 bh Pemotongan Pipa HDPE Ø 500 mm 87,983.50 97,966.00


A Tenaga 77,860.00 86,510.00
L.01 0.227 OH Pekerja 65,000.00 75,000.00 14,755.00 17,025.00
L.02 0.139 OH Tukang Pipa 95,000.00 105,000.00 13,205.00 14,595.00
L.04 0.028 OH Mandor 100,000.00 110,000.00 2,800.00 3,080.00
L.08 0.471 OH Operator 100,000.00 110,000.00 47,100.00 51,810.00
B Bahan - -
- m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 - -

C PERALATAN 2,125.00 2,550.00


0.085 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,125.00 2,550.00
-
D Jumlah A + B + C 79,985.00 89,060.00
E Overhead & Profit (contoh 10%) 10% 7,998.50 8,906.00
F Harga Satuan Pekerjaan (D+E) 87,983.50 97,966.00

27 A.8.4.2.27 1 bh Pemotongan Pipa HDPE Ø 600 mm 110,478.50 123,178.00


A Tenaga 97,910.00 108,950.00
L.01 0.333 OH Pekerja 65,000.00 75,000.00 21,645.00 24,975.00
L.02 0.167 OH Tukang Pipa 95,000.00 105,000.00 15,865.00 17,535.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00
L.08 0.571 OH Operator 100,000.00 110,000.00 57,100.00 62,810.00
B Bahan - -
- m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 - -

C PERALATAN 2,525.00 3,030.00


0.101 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,525.00 3,030.00

D Jumlah A + B + C 100,435.00 111,980.00


E Overhead & Profit (contoh 10%) 10% 10,043.50 11,198.00
F Harga Satuan Pekerjaan (D+E) 110,478.50 123,178.00

28 A.8.4.2.28 1 bh Pemotongan Pipa HDPE Ø 800 mm 170,758.50 190,806.00


A Tenaga 150,760.00 168,090.00
L.01 0.601 OH Pekerja 65,000.00 75,000.00 39,065.00 45,075.00
L.02 0.301 OH Tukang Pipa 95,000.00 105,000.00 28,595.00 31,605.00
L.04 0.060 OH Mandor 100,000.00 110,000.00 6,000.00 6,600.00
L.08 0.771 OH Operator 100,000.00 110,000.00 77,100.00 84,810.00
B Bahan - -
- m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 - -

C PERALATAN 4,475.00 5,370.00


0.179 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,475.00 5,370.00

D Jumlah A + B + C 155,235.00 173,460.00


E Overhead & Profit (contoh 10%) 10% 15,523.50 17,346.00
F Harga Satuan Pekerjaan (D+E) 170,758.50 190,806.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/223 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
29 A.8.4.2.29 1 bh Pemotongan Pipa HDPE Ø 900 mm 226,176.50 253,302.50
A Tenaga 198,865.00 222,175.00
L.01 0.913 OH Pekerja 65,000.00 75,000.00 59,345.00 68,475.00
L.02 0.456 OH Tukang Pipa 95,000.00 105,000.00 43,320.00 47,880.00
L.04 0.091 OH Mandor 100,000.00 110,000.00 9,100.00 10,010.00
L.08 0.871 OH Operator 100,000.00 110,000.00 87,100.00 95,810.00
B Bahan - -
- m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 - -

C PERALATAN 6,750.00 8,100.00


0.270 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 6,750.00 8,100.00

D Jumlah A + B + C 205,615.00 230,275.00


E Overhead & Profit (contoh 10%) 10% 20,561.50 23,027.50
F Harga Satuan Pekerjaan (D+E) 226,176.50 253,302.50

30 A.8.4.2.30 1 bh Pemotongan Pipa HDPE Ø 1.000 mm 267,426.50 299,722.50


A Tenaga 234,815.00 262,515.00
L.01 1.125 OH Pekerja 65,000.00 75,000.00 73,125.00 84,375.00
L.02 0.562 OH Tukang Pipa 95,000.00 105,000.00 53,390.00 59,010.00
L.04 0.112 OH Mandor 100,000.00 110,000.00 11,200.00 12,320.00
L.08 0.971 OH Operator 100,000.00 110,000.00 97,100.00 106,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 - -

C PERALATAN 8,300.00 9,960.00


0.332 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 8,300.00 9,960.00

D Jumlah A + B + C 243,115.00 272,475.00


E Overhead & Profit (contoh 10%) 10% 24,311.50 27,247.50
F Harga Satuan Pekerjaan (D+E) 267,426.50 299,722.50

31 A.8.4.2.31 1 bh Pemotongan Pipa HDPE Ø 1.100 mm 294,690.00 330,269.50


A Tenaga 258,775.00 289,295.00
L.01 1.238 OH Pekerja 65,000.00 75,000.00 80,470.00 92,850.00
L.02 0.619 OH Tukang Pipa 95,000.00 105,000.00 58,805.00 64,995.00
L.04 0.124 OH Mandor 100,000.00 110,000.00 12,400.00 13,640.00
L.08 1.071 OH Operator 100,000.00 110,000.00 107,100.00 117,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 - -

C PERALATAN 9,125.00 10,950.00


0.365 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 9,125.00 10,950.00

D Jumlah A + B + C 267,900.00 300,245.00


E Overhead & Profit (contoh 10%) 10% 26,790.00 30,024.50
F Harga Satuan Pekerjaan (D+E) 294,690.00 330,269.50

32 A.8.4.2.32 1 bh Pemotongan Pipa HDPE Ø 1.200 mm 360,046.50 404,041.00


A Tenaga 315,390.00 353,000.00
L.01 1.619 OH Pekerja 65,000.00 75,000.00 105,235.00 121,425.00
L.02 0.809 OH Tukang Pipa 95,000.00 105,000.00 76,855.00 84,945.00
L.04 0.162 OH Mandor 100,000.00 110,000.00 16,200.00 17,820.00
L.08 1.171 OH Operator 100,000.00 110,000.00 117,100.00 128,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 - -

C PERALATAN 11,925.00 14,310.00


0.477 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 11,925.00 14,310.00

D Jumlah A + B + C 327,315.00 367,310.00


E Overhead & Profit (contoh 10%) 10% 32,731.50 36,731.00
F Harga Satuan Pekerjaan (D+E) 360,046.50 404,041.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/224 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
33 A.8.4.2.33 1 bh Pemotongan Pipa GIP Ø 63 mm 2,623.50 2,964.50
A Tenaga 2,385.00 2,695.00
L.01 0.019 OH Pekerja 65,000.00 75,000.00 1,235.00 1,425.00
L.02 0.010 OH Tukang Pipa 95,000.00 105,000.00 950.00 1,050.00
L.04 0.002 OH Mandor 100,000.00 110,000.00 200.00 220.00

B Bahan - -
- m' Pipa GIP Ø 63 mm 27,500.00 30,000.00 - -

C PERALATAN - -

hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 2,385.00 2,695.00


E Overhead & Profit (contoh 10%) 10% 238.50 269.50
F Harga Satuan Pekerjaan (D+E) 2,623.50 2,964.50

34 A.8.4.2.34 1 bh Pemotongan Pipa GIP Ø 100 mm 7,837.50 8,860.50


A Tenaga 7,125.00 8,055.00
L.01 0.058 OH Pekerja 65,000.00 75,000.00 3,770.00 4,350.00
L.02 0.029 OH Tukang Pipa 95,000.00 105,000.00 2,755.00 3,045.00
L.04 0.006 OH Mandor 100,000.00 110,000.00 600.00 660.00

B Bahan - -
- m' Pipa GIP Ø 100 mm 34,166.67 40,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 7,125.00 8,055.00


E Overhead & Profit (contoh 10%) 10% 712.50 805.50
F Harga Satuan Pekerjaan (D+E) 7,837.50 8,860.50

35 A.8.4.2.35 1 bh Pemotongan Pipa GIP Ø 125 mm 12,375.00 13,992.00


A Tenaga 11,250.00 12,720.00
L.01 0.092 OH Pekerja 65,000.00 75,000.00 5,980.00 6,900.00
L.02 0.046 OH Tukang Pipa 95,000.00 105,000.00 4,370.00 4,830.00
L.04 0.009 OH Mandor 100,000.00 110,000.00 900.00 990.00

B Bahan - -
- m' Pipa GIP Ø 125 mm 52,500.00 56,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 11,250.00 12,720.00


E Overhead & Profit (contoh 10%) 10% 1,125.00 1,272.00
F Harga Satuan Pekerjaan (D+E) 12,375.00 13,992.00

36 A.8.4.2.36 1 bh Pemotongan Pipa GIP Ø 150 mm 17,693.50 20,003.50


A Tenaga 16,085.00 18,185.00
L.01 0.131 OH Pekerja 65,000.00 75,000.00 8,515.00 9,825.00
L.02 0.066 OH Tukang Pipa 95,000.00 105,000.00 6,270.00 6,930.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
- m' Pipa GIP Ø 150 mm 65,000.00 68,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 16,085.00 18,185.00


E Overhead & Profit (contoh 10%) 10% 1,608.50 1,818.50
F Harga Satuan Pekerjaan (D+E) 17,693.50 20,003.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/225 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 45,815.00 51,799.00
A Tenaga 41,650.00 47,090.00
L.01 0.340 OH Pekerja 65,000.00 75,000.00 22,100.00 25,500.00
L.02 0.170 OH Tukang Pipa 95,000.00 105,000.00 16,150.00 17,850.00
L.04 0.034 OH Mandor 100,000.00 110,000.00 3,400.00 3,740.00

B Bahan - -
- m' Pipa GIP Ø 200 mm 75,000.00 78,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 41,650.00 47,090.00


E Overhead & Profit (contoh 10%) 10% 4,165.00 4,709.00
F Harga Satuan Pekerjaan (D+E) 45,815.00 51,799.00

38 A.8.4.2.38 1 bh Pemotongan Pipa GIP Ø 250 mm 63,899.00 72,248.00


A Tenaga 58,090.00 65,680.00
L.01 0.475 OH Pekerja 65,000.00 75,000.00 30,875.00 35,625.00
L.02 0.237 OH Tukang Pipa 95,000.00 105,000.00 22,515.00 24,885.00
L.04 0.047 OH Mandor 100,000.00 110,000.00 4,700.00 5,170.00

B Bahan - -
- m' Pipa GIP Ø 250 mm 98,333.33 111,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 58,090.00 65,680.00


E Overhead & Profit (contoh 10%) 10% 5,809.00 6,568.00
F Harga Satuan Pekerjaan (D+E) 63,899.00 72,248.00

39 A.8.4.2.39 1 bh Pemotongan Pipa GIP Ø 300 mm 67,870.00 76,736.00


A Tenaga 61,700.00 69,760.00
L.01 0.504 OH Pekerja 65,000.00 75,000.00 32,760.00 37,800.00
L.02 0.252 OH Tukang Pipa 95,000.00 105,000.00 23,940.00 26,460.00
L.04 0.050 OH Mandor 100,000.00 110,000.00 5,000.00 5,500.00

B Bahan - -
- m' Pipa GIP Ø 300 mm 124,166.67 130,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 61,700.00 69,760.00


E Overhead & Profit (contoh 10%) 10% 6,170.00 6,976.00
F Harga Satuan Pekerjaan (D+E) 67,870.00 76,736.00

40 A.8.4.2.40 1 bh Pemotongan Pipa GIP Ø 400 mm 99,467.50 112,458.50


A Tenaga 90,425.00 102,235.00
L.01 0.738 OH Pekerja 65,000.00 75,000.00 47,970.00 55,350.00
L.02 0.369 OH Tukang Pipa 95,000.00 105,000.00 35,055.00 38,745.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
- m' Pipa GIP Ø 400 mm 167,500.00 208,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 90,425.00 102,235.00


E Overhead & Profit (contoh 10%) 10% 9,042.50 10,223.50
F Harga Satuan Pekerjaan (D+E) 99,467.50 112,458.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/226 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
41 A.8.4.2.41 1 bh Pemotongan Pipa GIP Ø 450 mm 114,290.00 129,217.00
A Tenaga 103,900.00 117,470.00
L.01 0.848 OH Pekerja 65,000.00 75,000.00 55,120.00 63,600.00
L.02 0.424 OH Tukang Pipa 95,000.00 105,000.00 40,280.00 44,520.00
L.04 0.085 OH Mandor 100,000.00 110,000.00 8,500.00 9,350.00

B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 103,900.00 117,470.00


E Overhead & Profit (contoh 10%) 10% 10,390.00 11,747.00
F Harga Satuan Pekerjaan (D+E) 114,290.00 129,217.00

42 A.8.4.2.42 1 bh Pemotongan Pipa GIP Ø 500 mm 126,841.00 143,407.00


A Tenaga 115,310.00 130,370.00
L.01 0.941 OH Pekerja 65,000.00 75,000.00 61,165.00 70,575.00
L.02 0.471 OH Tukang Pipa 95,000.00 105,000.00 44,745.00 49,455.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00

B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 115,310.00 130,370.00


E Overhead & Profit (contoh 10%) 10% 11,531.00 13,037.00
F Harga Satuan Pekerjaan (D+E) 126,841.00 143,407.00

43 A.8.4.2.43 1 bh Pemotongan Pipa GIP Ø 600 mm 116,380.00 131,582.00


A Tenaga 105,800.00 119,620.00
L.01 0.864 OH Pekerja 65,000.00 75,000.00 56,160.00 64,800.00
L.02 0.432 OH Tukang Pipa 95,000.00 105,000.00 41,040.00 45,360.00
L.04 0.086 OH Mandor 100,000.00 110,000.00 8,600.00 9,460.00

B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 105,800.00 119,620.00


E Overhead & Profit (contoh 10%) 10% 10,580.00 11,962.00
F Harga Satuan Pekerjaan (D+E) 116,380.00 131,582.00

44 A.8.4.2.44 1 bh Pemotongan Pipa GIP Ø 800 mm 211,134.00 238,711.00


A Tenaga 191,940.00 217,010.00
L.01 1.567 OH Pekerja 65,000.00 75,000.00 101,855.00 117,525.00
L.02 0.783 OH Tukang Pipa 95,000.00 105,000.00 74,385.00 82,215.00
L.04 0.157 OH Mandor 100,000.00 110,000.00 15,700.00 17,270.00

B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 191,940.00 217,010.00


E Overhead & Profit (contoh 10%) 10% 19,194.00 21,701.00
F Harga Satuan Pekerjaan (D+E) 211,134.00 238,711.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/227 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 238,507.50 269,659.50
A Tenaga 216,825.00 245,145.00
L.01 1.770 OH Pekerja 65,000.00 75,000.00 115,050.00 132,750.00
L.02 0.885 OH Tukang Pipa 95,000.00 105,000.00 84,075.00 92,925.00
L.04 0.177 OH Mandor 100,000.00 110,000.00 17,700.00 19,470.00

B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 216,825.00 245,145.00


E Overhead & Profit (contoh 10%) 10% 21,682.50 24,514.50
F Harga Satuan Pekerjaan (D+E) 238,507.50 269,659.50

46 A.8.4.2.46 1 bh Pemotongan Pipa GIP Ø 1.000 mm 265,952.50 300,690.50


A Tenaga 241,775.00 273,355.00
L.01 1.974 OH Pekerja 65,000.00 75,000.00 128,310.00 148,050.00
L.02 0.987 OH Tukang Pipa 95,000.00 105,000.00 93,765.00 103,635.00
L.04 0.197 OH Mandor 100,000.00 110,000.00 19,700.00 21,670.00

B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 241,775.00 273,355.00


E Overhead & Profit (contoh 10%) 10% 24,177.50 27,335.50
F Harga Satuan Pekerjaan (D+E) 265,952.50 300,690.50

47 A.8.4.2.47 1 bh Pemotongan Pipa GIP Ø 1.100 mm 293,287.50 331,600.50


A Tenaga 266,625.00 301,455.00
L.01 2.178 OH Pekerja 65,000.00 75,000.00 141,570.00 163,350.00
L.02 1.089 OH Tukang Pipa 95,000.00 105,000.00 103,455.00 114,345.00
L.04 0.216 OH Mandor 100,000.00 110,000.00 21,600.00 23,760.00

B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 266,625.00 301,455.00


E Overhead & Profit (contoh 10%) 10% 26,662.50 30,145.50
F Harga Satuan Pekerjaan (D+E) 293,287.50 331,600.50

48 A.8.4.2.48 1 bh Pemotongan Pipa GIP Ø 1.200 mm 320,952.50 362,873.50


A Tenaga 291,775.00 329,885.00
L.01 2.382 OH Pekerja 65,000.00 75,000.00 154,830.00 178,650.00
L.02 1.191 OH Tukang Pipa 95,000.00 105,000.00 113,145.00 125,055.00
L.04 0.238 OH Mandor 100,000.00 110,000.00 23,800.00 26,180.00

B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 291,775.00 329,885.00


E Overhead & Profit (contoh 10%) 10% 29,177.50 32,988.50
F Harga Satuan Pekerjaan (D+E) 320,952.50 362,873.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/228 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 7,342.50 8,361.10
A Tenaga 6,645.00 7,565.00
L.01 0.071 OH Pekerja 65,000.00 75,000.00 4,615.00 5,325.00
L.02 0.014 OH Tukang Pipa 95,000.00 105,000.00 1,330.00 1,470.00
L.04 0.007 OH Mandor 100,000.00 110,000.00 700.00 770.00

B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -

C PERALATAN 30.00 36.00


0.003 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 30.00 36.00

D Jumlah A + B + C 6,675.00 7,601.00


E Overhead & Profit (contoh 10%) 10% 667.50 760.10
F Harga Satuan Pekerjaan (D+E) 7,342.50 8,361.10

50 A.8.4.2.50 1 bh Pemotongan Pipa DCI Ø 125 mm 11,627.00 13,244.00


A Tenaga 10,470.00 11,920.00
L.01 0.112 OH Pekerja 65,000.00 75,000.00 7,280.00 8,400.00
L.02 0.022 OH Tukang Pipa 95,000.00 105,000.00 2,090.00 2,310.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -

C PERALATAN 100.00 120.00


0.010 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 100.00 120.00

D Jumlah A + B + C 10,570.00 12,040.00


E Overhead & Profit (contoh 10%) 10% 1,057.00 1,204.00
F Harga Satuan Pekerjaan (D+E) 11,627.00 13,244.00

51 A.8.4.2.51 1 bh Pemotongan Pipa DCI Ø 150 mm 16,670.50 18,987.10


A Tenaga 14,975.00 17,045.00
L.01 0.159 OH Pekerja 65,000.00 75,000.00 10,335.00 11,925.00
L.02 0.032 OH Tukang Pipa 95,000.00 105,000.00 3,040.00 3,360.00
L.04 0.016 OH Mandor 100,000.00 110,000.00 1,600.00 1,760.00

B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -

C PERALATAN 180.00 216.00


0.018 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 180.00 216.00

D Jumlah A + B + C 15,155.00 17,261.00


E Overhead & Profit (contoh 10%) 10% 1,515.50 1,726.10
F Harga Satuan Pekerjaan (D+E) 16,670.50 18,987.10

52 A.8.4.2.52 1 bh Pemotongan Pipa DCI Ø 200 mm 38,461.50 43,816.30


A Tenaga 34,425.00 39,185.00
L.01 0.366 OH Pekerja 65,000.00 75,000.00 23,790.00 27,450.00
L.02 0.073 OH Tukang Pipa 95,000.00 105,000.00 6,935.00 7,665.00
L.04 0.037 OH Mandor 100,000.00 110,000.00 3,700.00 4,070.00

B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -

C PERALATAN 540.00 648.00


0.054 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 540.00 648.00

D Jumlah A + B + C 34,965.00 39,833.00


E Overhead & Profit (contoh 10%) 10% 3,496.50 3,983.30
F Harga Satuan Pekerjaan (D+E) 38,461.50 43,816.30

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/229 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
53 A.8.4.2.53 1 bh Pemotongan Pipa DCI Ø 250 mm 50,044.50 57,014.10
A Tenaga 44,765.00 50,955.00
L.01 0.476 OH Pekerja 65,000.00 75,000.00 30,940.00 35,700.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -

C PERALATAN 730.00 876.00


0.073 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 730.00 876.00

D Jumlah A + B + C 45,495.00 51,831.00


E Overhead & Profit (contoh 10%) 10% 4,549.50 5,183.10
F Harga Satuan Pekerjaan (D+E) 50,044.50 57,014.10

54 A.8.4.2.54 1 bh Pemotongan Pipa DCI Ø 300 mm 53,746.00 61,234.80


A Tenaga 48,070.00 54,720.00
L.01 0.512 OH Pekerja 65,000.00 75,000.00 33,280.00 38,400.00
L.02 0.102 OH Tukang Pipa 95,000.00 105,000.00 9,690.00 10,710.00
L.04 0.051 OH Mandor 100,000.00 110,000.00 5,100.00 5,610.00

B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -

C PERALATAN 790.00 948.00


0.079 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 790.00 948.00

D Jumlah A + B + C 48,860.00 55,668.00


E Overhead & Profit (contoh 10%) 10% 4,886.00 5,566.80
F Harga Satuan Pekerjaan (D+E) 53,746.00 61,234.80

55 A.8.4.2.55 1 bh Pemotongan Pipa DCI Ø 400 mm 99,005.50 112,806.10


A Tenaga 88,425.00 100,655.00
L.01 0.941 OH Pekerja 65,000.00 75,000.00 61,165.00 70,575.00
L.02 0.188 OH Tukang Pipa 95,000.00 105,000.00 17,860.00 19,740.00
L.04 0.094 OH Mandor 100,000.00 110,000.00 9,400.00 10,340.00
- -
B Bahan - -
m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 - -

C PERALATAN 1,580.00 1,896.00


0.158 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,580.00 1,896.00
- -
D Jumlah A + B + C 90,005.00 102,551.00
E Overhead & Profit (contoh 10%) 10% 9,000.50 10,255.10
F Harga Satuan Pekerjaan (D+E) 99,005.50 112,806.10

56 A.8.4.2.56 1 bh Pemotongan Pipa DCI Ø 450 mm 119,493.00 136,138.20


A Tenaga 106,870.00 121,650.00
L.01 1.137 OH Pekerja 65,000.00 75,000.00 73,905.00 85,275.00
L.02 0.227 OH Tukang Pipa 95,000.00 105,000.00 21,565.00 23,835.00
L.04 0.114 OH Mandor 100,000.00 110,000.00 11,400.00 12,540.00
- -
B Bahan - -
m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 - -

C PERALATAN 1,760.00 2,112.00


0.176 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,760.00 2,112.00
- - - -
D Jumlah A + B + C 108,630.00 123,762.00
E Overhead & Profit (contoh 10%) 10% 10,863.00 12,376.20
F Harga Satuan Pekerjaan (D+E) 119,493.00 136,138.20

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/230 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
57 A.8.4.2.57 1 bh Pemotongan Pipa DCI Ø 500 mm 137,709.00 156,886.40
A Tenaga 123,270.00 140,320.00
L.01 1.312 OH Pekerja 65,000.00 75,000.00 85,280.00 98,400.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 125,190.00 142,624.00
E Overhead & Profit (contoh 10%) 10% 12,519.00 14,262.40
F Harga Satuan Pekerjaan (D+E) 137,709.00 156,886.40

58 A.8.4.2.58 1 bh Pemotongan Pipa DCI Ø 600 mm 137,709.00 156,886.40


A Tenaga 123,270.00 140,320.00
L.01 1.312 OH Pekerja 65,000.00 75,000.00 85,280.00 98,400.00
L.02 0.262 OH Tukang Pipa 95,000.00 105,000.00 24,890.00 27,510.00
L.04 0.131 OH Mandor 100,000.00 110,000.00 13,100.00 14,410.00
- -
B Bahan - -
m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 125,190.00 142,624.00
E Overhead & Profit (contoh 10%) 10% 12,519.00 14,262.40
F Harga Satuan Pekerjaan (D+E) 137,709.00 156,886.40

59 A.8.4.2.59 1 bh Pemotongan Pipa DCI Ø 800 mm 272,107.00 309,947.00


A Tenaga 244,270.00 278,050.00
L.01 2.598 OH Pekerja 65,000.00 75,000.00 168,870.00 194,850.00
L.02 0.520 OH Tukang Pipa 95,000.00 105,000.00 49,400.00 54,600.00
L.04 0.260 OH Mandor 100,000.00 110,000.00 26,000.00 28,600.00
- -
B Bahan - -
m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 - -

C PERALATAN 3,100.00 3,720.00


0.310 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,100.00 3,720.00
- - - -
D Jumlah A + B + C 247,370.00 281,770.00
E Overhead & Profit (contoh 10%) 10% 24,737.00 28,177.00
F Harga Satuan Pekerjaan (D+E) 272,107.00 309,947.00

60 A.8.4.2.60 1 bh Pemotongan Pipa DCI Ø 900 mm 352,649.00 401,678.20


A Tenaga 316,780.00 360,590.00
L.01 3.370 OH Pekerja 65,000.00 75,000.00 219,050.00 252,750.00
L.02 0.674 OH Tukang Pipa 95,000.00 105,000.00 64,030.00 70,770.00
L.04 0.337 OH Mandor 100,000.00 110,000.00 33,700.00 37,070.00
- -
B Bahan - -
m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 - -

C PERALATAN 3,810.00 4,572.00


0.381 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,810.00 4,572.00
- - - -
D Jumlah A + B + C 320,590.00 365,162.00
E Overhead & Profit (contoh 10%) 10% 32,059.00 36,516.20
F Harga Satuan Pekerjaan (D+E) 352,649.00 401,678.20

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/231 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
61 A.8.4.2.61 1 bh Pemotongan Pipa DCI Ø 1.000 mm 420,590.50 479,057.70
A Tenaga 377,945.00 430,215.00
L.01 4.021 OH Pekerja 65,000.00 75,000.00 261,365.00 301,575.00
L.02 0.804 OH Tukang Pipa 95,000.00 105,000.00 76,380.00 84,420.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00
- -
B Bahan - -
m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 - -

C PERALATAN 4,410.00 5,292.00


0.441 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 4,410.00 5,292.00
- - - -
D Jumlah A + B + C 382,355.00 435,507.00
E Overhead & Profit (contoh 10%) 10% 38,235.50 43,550.70
F Harga Satuan Pekerjaan (D+E) 420,590.50 479,057.70

62 A.8.4.2.62 1 bh Pemotongan Pipa DCI Ø 1.100 mm 494,719.50 563,482.70


A Tenaga 444,685.00 506,185.00
L.01 4.731 OH Pekerja 65,000.00 75,000.00 307,515.00 354,825.00
L.02 0.946 OH Tukang Pipa 95,000.00 105,000.00 89,870.00 99,330.00
L.04 0.473 OH Mandor 100,000.00 110,000.00 47,300.00 52,030.00
- -
B Bahan - -
m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 - -

C PERALATAN 5,060.00 6,072.00


0.506 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,060.00 6,072.00
- - - -
D Jumlah A + B + C 449,745.00 512,257.00
E Overhead & Profit (contoh 10%) 10% 44,974.50 51,225.70
F Harga Satuan Pekerjaan (D+E) 494,719.50 563,482.70

63 A.8.4.2.63 1 bh Pemotongan Pipa DCI Ø 1.200 mm 575,179.00 655,118.20


A Tenaga 517,130.00 588,650.00
L.01 5.502 OH Pekerja 65,000.00 75,000.00 357,630.00 412,650.00
L.02 1.100 OH Tukang Pipa 95,000.00 105,000.00 104,500.00 115,500.00
L.04 0.550 OH Mandor 100,000.00 110,000.00 55,000.00 60,500.00
- -
B Bahan - -
m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 - -

C PERALATAN 5,760.00 6,912.00


0.576 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,760.00 6,912.00
- - - -
D Jumlah A + B + C 522,890.00 595,562.00
E Overhead & Profit (contoh 10%) 10% 52,289.00 59,556.20
F Harga Satuan Pekerjaan (D+E) 575,179.00 655,118.20

64 A.8.4.2.64 1 bh Pemotongan pipa Baja Ø 63 mm 4,180.00 4,790.50


A Tenaga 2,690.00 3,060.00
L.01 0.028 OH Pekerja 65,000.00 75,000.00 1,820.00 2,100.00
L.02 0.006 OH Tukang Pipa 95,000.00 105,000.00 570.00 630.00
L.04 0.003 OH Mandor 100,000.00 110,000.00 300.00 330.00

B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -

C PERALATAN 1,110.00 1,295.00


0.037 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,110.00 1,295.00

D Jumlah A + B + C 3,800.00 4,355.00


E Overhead & Profit (contoh 10%) 10% 380.00 435.50
F Harga Satuan Pekerjaan (D+E) 4,180.00 4,790.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/232 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
65 A.8.4.2.65 1 bh Pemotongan Pipa Baja Ø 100 mm 10,054.00 11,484.00
A Tenaga 7,940.00 9,040.00
L.01 0.085 OH Pekerja 65,000.00 75,000.00 5,525.00 6,375.00
L.02 0.017 OH Tukang Pipa 95,000.00 105,000.00 1,615.00 1,785.00
L.04 0.008 OH Mandor 100,000.00 110,000.00 800.00 880.00

B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -

C PERALATAN 1,200.00 1,400.00


0.04 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,200.00 1,400.00

D Jumlah A + B + C 9,140.00 10,440.00


E Overhead & Profit (contoh 10%) 10% 914.00 1,044.00
F Harga Satuan Pekerjaan (D+E) 10,054.00 11,484.00

66 A.8.4.2.66 1 bh Pemotongan Pipa Baja Ø 125 mm 15,147.00 17,281.00


A Tenaga 12,510.00 14,240.00
L.01 0.133 OH Pekerja 65,000.00 75,000.00 8,645.00 9,975.00
L.02 0.027 OH Tukang Pipa 95,000.00 105,000.00 2,565.00 2,835.00
L.04 0.013 OH Mandor 100,000.00 110,000.00 1,300.00 1,430.00

B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -

C PERALATAN 1,260.00 1,470.00


0.042 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,260.00 1,470.00

D Jumlah A + B + C 13,770.00 15,710.00


E Overhead & Profit (contoh 10%) 10% 1,377.00 1,571.00
F Harga Satuan Pekerjaan (D+E) 15,147.00 17,281.00

67 A.8.4.2.67 1 bh Pemotongan Pipa Baja Ø 150 mm 20,487.50 23,364.00


A Tenaga 17,275.00 19,665.00
L.01 0.184 OH Pekerja 65,000.00 75,000.00 11,960.00 13,800.00
L.02 0.037 OH Tukang Pipa 95,000.00 105,000.00 3,515.00 3,885.00
L.04 0.018 OH Mandor 100,000.00 110,000.00 1,800.00 1,980.00

B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -

C PERALATAN 1,350.00 1,575.00


0.045 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,350.00 1,575.00

D Jumlah A + B + C 18,625.00 21,240.00


E Overhead & Profit (contoh 10%) 10% 1,862.50 2,124.00
F Harga Satuan Pekerjaan (D+E) 20,487.50 23,364.00

68 A.8.4.2.68 1 bh Pemotongan Pipa Baja Ø 200 mm 51,221.50 58,360.50


A Tenaga 44,765.00 50,955.00
L.01 0.476 OH Pekerja 65,000.00 75,000.00 30,940.00 35,700.00
L.02 0.095 OH Tukang Pipa 95,000.00 105,000.00 9,025.00 9,975.00
L.04 0.048 OH Mandor 100,000.00 110,000.00 4,800.00 5,280.00

B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -

C PERALATAN 1,800.00 2,100.00


0.06 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,800.00 2,100.00

D Jumlah A + B + C 46,565.00 53,055.00


E Overhead & Profit (contoh 10%) 10% 4,656.50 5,305.50
F Harga Satuan Pekerjaan (D+E) 51,221.50 58,360.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/233 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
69 A.8.4.2.69 1 bh Pemotongan Pipa Baja Ø 250 mm 70,807.00 80,663.00
A Tenaga 62,330.00 70,950.00
L.01 0.663 OH Pekerja 65,000.00 75,000.00 43,095.00 49,725.00
L.02 0.133 OH Tukang Pipa 95,000.00 105,000.00 12,635.00 13,965.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -

C PERALATAN 2,040.00 2,380.00


0.068 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,040.00 2,380.00

D Jumlah A + B + C 64,370.00 73,330.00


E Overhead & Profit (contoh 10%) 10% 6,437.00 7,333.00
F Harga Satuan Pekerjaan (D+E) 70,807.00 80,663.00

70 A.8.4.2.70 1 bh Pemotongan Pipa Baja Ø 300 mm 79,354.00 90,398.00


A Tenaga 69,980.00 79,660.00
L.01 0.745 OH Pekerja 65,000.00 75,000.00 48,425.00 55,875.00
L.02 0.149 OH Tukang Pipa 95,000.00 105,000.00 14,155.00 15,645.00
L.04 0.074 OH Mandor 100,000.00 110,000.00 7,400.00 8,140.00

B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -

C PERALATAN 2,160.00 2,520.00


0.072 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,160.00 2,520.00

D Jumlah A + B + C 72,140.00 82,180.00


E Overhead & Profit (contoh 10%) 10% 7,214.00 8,218.00
F Harga Satuan Pekerjaan (D+E) 79,354.00 90,398.00

71 A.8.4.2.71 1 bh Pemotongan Pipa Baja Ø 400 mm 152,361.00 173,530.50


A Tenaga 135,360.00 154,080.00
L.01 1.440 OH Pekerja 65,000.00 75,000.00 93,600.00 108,000.00
L.02 0.288 OH Tukang Pipa 95,000.00 105,000.00 27,360.00 30,240.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -

C PERALATAN 3,150.00 3,675.00


0.105 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,150.00 3,675.00
- -
D Jumlah A + B + C 138,510.00 157,755.00
E Overhead & Profit (contoh 10%) 10% 13,851.00 15,775.50
F Harga Satuan Pekerjaan (D+E) 152,361.00 173,530.50

72 A.8.4.2.72 1 bh Pemotongan Pipa Baja Ø 450 mm 143,929.50 163,867.00


A Tenaga 127,635.00 145,225.00
L.01 1.339 OH Pekerja 65,000.00 75,000.00 87,035.00 100,425.00
L.02 0.280 OH Tukang Pipa 95,000.00 105,000.00 26,600.00 29,400.00
L.04 0.140 OH Mandor 100,000.00 110,000.00 14,000.00 15,400.00

B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 130,845.00 148,970.00
E Overhead & Profit (contoh 10%) 10% 13,084.50 14,897.00
F Harga Satuan Pekerjaan (D+E) 143,929.50 163,867.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/234 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
73 A.8.4.2.73 1 bh Pemotongan Pipa Baja Ø 500 mm 154,682.00 176,214.50
A Tenaga 137,410.00 156,450.00
L.01 1.473 OH Pekerja 65,000.00 75,000.00 95,745.00 110,475.00
L.02 0.287 OH Tukang Pipa 95,000.00 105,000.00 27,265.00 30,135.00
L.04 0.144 OH Mandor 100,000.00 110,000.00 14,400.00 15,840.00

B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 140,620.00 160,195.00
E Overhead & Profit (contoh 10%) 10% 14,062.00 16,019.50
F Harga Satuan Pekerjaan (D+E) 154,682.00 176,214.50

74 A.8.4.2.74 1 bh Pemotongan Pipa Baja Ø 600 mm 164,890.00 187,797.50


A Tenaga 146,510.00 166,770.00
L.01 1.558 OH Pekerja 65,000.00 75,000.00 101,270.00 116,850.00
L.02 0.312 OH Tukang Pipa 95,000.00 105,000.00 29,640.00 32,760.00
L.04 0.156 OH Mandor 100,000.00 110,000.00 15,600.00 17,160.00

B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -

C PERALATAN 3,390.00 3,955.00


0.113 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,390.00 3,955.00
- - - -
D Jumlah A + B + C 149,900.00 170,725.00
E Overhead & Profit (contoh 10%) 10% 14,990.00 17,072.50
F Harga Satuan Pekerjaan (D+E) 164,890.00 187,797.50

75 A.8.4.2.75 1 bh Pemotongan Pipa Baja Ø 800 mm 276,776.50 315,210.50


A Tenaga 246,635.00 280,745.00
L.01 2.624 OH Pekerja 65,000.00 75,000.00 170,560.00 196,800.00
L.02 0.525 OH Tukang Pipa 95,000.00 105,000.00 49,875.00 55,125.00
L.04 0.262 OH Mandor 100,000.00 110,000.00 26,200.00 28,820.00

B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -

C PERALATAN 4,980.00 5,810.00


0.166 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 4,980.00 5,810.00
- - - -
D Jumlah A + B + C 251,615.00 286,555.00
E Overhead & Profit (contoh 10%) 10% 25,161.50 28,655.50
F Harga Satuan Pekerjaan (D+E) 276,776.50 315,210.50

76 A.8.4.2.76 1 bh Pemotongan Pipa Baja Ø 900 mm 313,208.50 356,697.00


A Tenaga 279,245.00 317,865.00
L.01 2.971 OH Pekerja 65,000.00 75,000.00 193,115.00 222,825.00
L.02 0.594 OH Tukang Pipa 95,000.00 105,000.00 56,430.00 62,370.00
L.04 0.297 OH Mandor 100,000.00 110,000.00 29,700.00 32,670.00

B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -

C PERALATAN 5,490.00 6,405.00


0.183 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 5,490.00 6,405.00
- - - -
D Jumlah A + B + C 284,735.00 324,270.00
E Overhead & Profit (contoh 10%) 10% 28,473.50 32,427.00
F Harga Satuan Pekerjaan (D+E) 313,208.50 356,697.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/235 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
77 A.8.4.2.77 1 bh Pemotongan Pipa Baja Ø 1.000 mm 349,849.50 398,420.00
A Tenaga 312,015.00 355,165.00
L.01 3.319 OH Pekerja 65,000.00 75,000.00 215,735.00 248,925.00
L.02 0.664 OH Tukang Pipa 95,000.00 105,000.00 63,080.00 69,720.00
L.04 0.332 OH Mandor 100,000.00 110,000.00 33,200.00 36,520.00

B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -

C PERALATAN 6,030.00 7,035.00


0.201 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,030.00 7,035.00
- - - -
D Jumlah A + B + C 318,045.00 362,200.00
E Overhead & Profit (contoh 10%) 10% 31,804.50 36,220.00
F Harga Satuan Pekerjaan (D+E) 349,849.50 398,420.00

78 A.8.4.2.78 1 bh Pemotongan Pipa Baja Ø 1.100 mm 386,353.00 439,989.00


A Tenaga 344,690.00 392,360.00
L.01 3.667 OH Pekerja 65,000.00 75,000.00 238,355.00 275,025.00
L.02 0.733 OH Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.367 OH Mandor 100,000.00 110,000.00 36,700.00 40,370.00

B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -

C PERALATAN 6,540.00 7,630.00


0.218 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,540.00 7,630.00
- - - -
D Jumlah A + B + C 351,230.00 399,990.00
E Overhead & Profit (contoh 10%) 10% 35,123.00 39,999.00
F Harga Satuan Pekerjaan (D+E) 386,353.00 439,989.00

79 A.8.4.2.79 1 bh Pemotongan Pipa Baja Ø 1.200 mm 422,994.00 481,712.00


A Tenaga 377,460.00 429,660.00
L.01 4.015 OH Pekerja 65,000.00 75,000.00 260,975.00 301,125.00
L.02 0.803 OH Tukang Pipa 95,000.00 105,000.00 76,285.00 84,315.00
L.04 0.402 OH Mandor 100,000.00 110,000.00 40,200.00 44,220.00

B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -

C PERALATAN 7,080.00 8,260.00


0.236 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 7,080.00 8,260.00
- - - -
D Jumlah A + B + C 384,540.00 437,920.00
E Overhead & Profit (contoh 10%) 10% 38,454.00 43,792.00
F Harga Satuan Pekerjaan (D+E) 422,994.00 481,712.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/236 17-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN


XVIII A.8.4.3
AKSESORIS PIPA
1 A.8.4.3.1 1 bh Pemasangan Valve Ø 150 mm 248,721.00 290,598.00
A Tenaga 175,110.00 197,980.00
L.01 1.429 OH Pekerja 65,000.00 75,000.00 92,885.00 107,175.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan 50,000.00 65,000.00


1 bh Valve Ø 150 mm 50,000.00 65,000.00 50,000.00 65,000.00

C PERALATAN 1,000.00 1,200.00


0.1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00

D Jumlah A + B + C 226,110.00 264,180.00


E Overhead & Profit (contoh 10%) 10% 22,611.00 26,418.00
F Harga Satuan Pekerjaan (D+E) 248,721.00 290,598.00

2 A.8.4.3.2 1 bh Pemasangan Valve Ø 200 mm 316,717.50 364,039.50


A Tenaga 209,925.00 237,345.00
L.01 1.714 OH Pekerja 65,000.00 75,000.00 111,410.00 128,550.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 75,000.00 90,000.00


1 bh Valve Ø 200 mm 75,000.00 90,000.00 75,000.00 90,000.00

C PERALATAN 3,000.00 3,600.00


0.3 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,000.00 3,600.00

D Jumlah A + B + C 287,925.00 330,945.00


E Overhead & Profit (contoh 10%) 10% 28,792.50 33,094.50
F Harga Satuan Pekerjaan (D+E) 316,717.50 364,039.50

3 A.8.4.3.3 1 m' Pemasangan Valve Ø 250 mm 372,817.50 414,859.50


A Tenaga 209,925.00 237,345.00
L.01 1.714 OH Pekerja 65,000.00 75,000.00 111,410.00 128,550.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 125,000.00 135,000.00


1 bh Valve Ø 250 mm 125,000.00 135,000.00 125,000.00 135,000.00

C PERALATAN 4,000.00 4,800.00


0.4 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,000.00 4,800.00

D Jumlah A + B + C 338,925.00 377,145.00


E Overhead & Profit (contoh 10%) 10% 33,892.50 37,714.50
F Harga Satuan Pekerjaan (D+E) 372,817.50 414,859.50

4 A.8.4.3.4 1 bh Pemasangan Valve Ø 300 mm 440,000.00 498,300.00


A Tenaga 245,000.00 277,000.00
L.01 2.000 OH Pekerja 65,000.00 75,000.00 130,000.00 150,000.00
L.02 1.000 OH Tukang Pipa 95,000.00 105,000.00 95,000.00 105,000.00
L.04 0.200 OH Mandor 100,000.00 110,000.00 20,000.00 22,000.00

B Bahan 150,000.00 170,000.00


1 bh Valve Ø 300 mm 150,000.00 170,000.00 150,000.00 170,000.00

C PERALATAN 5,000.00 6,000.00


0.5 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 400,000.00 453,000.00


E Overhead & Profit (contoh 10%) 10% 40,000.00 45,300.00
F Harga Satuan Pekerjaan (D+E) 440,000.00 498,300.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/237 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.8.4.3.5 1 bh Pemasangan Valve Ø 400 mm 775,621.00 865,678.00
A Tenaga 420,110.00 474,980.00
L.01 3.429 OH Pekerja 65,000.00 75,000.00 222,885.00 257,175.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 275,000.00 300,000.00


1 bh Valve Ø 400 mm 275,000.00 300,000.00 275,000.00 300,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 705,110.00 786,980.00


E Overhead & Profit (contoh 10%) 10% 70,511.00 78,698.00
F Harga Satuan Pekerjaan (D+E) 775,621.00 865,678.00

6 A.8.4.3.6 1 bh Pemasangan Valve Ø 450 mm 830,621.00 920,678.00


A Tenaga 420,110.00 474,980.00
L.01 3.429 OH Pekerja 65,000.00 75,000.00 222,885.00 257,175.00
L.02 1.715 OH Tukang Pipa 95,000.00 105,000.00 162,925.00 180,075.00
L.04 0.343 OH Mandor 100,000.00 110,000.00 34,300.00 37,730.00

B Bahan 325,000.00 350,000.00


1 bh Valve Ø 450 mm 325,000.00 350,000.00 325,000.00 350,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 755,110.00 836,980.00


E Overhead & Profit (contoh 10%) 10% 75,511.00 83,698.00
F Harga Satuan Pekerjaan (D+E) 830,621.00 920,678.00

7 A.8.4.3.7 1 bh Pemasangan Valve Ø 500 mm 962,500.00 1,062,600.00


A Tenaga 490,000.00 554,000.00
L.01 4.000 OH Pekerja 65,000.00 75,000.00 260,000.00 300,000.00
L.02 2.000 OH Tukang Pipa 95,000.00 105,000.00 190,000.00 210,000.00
L.04 0.400 OH Mandor 100,000.00 110,000.00 40,000.00 44,000.00

B Bahan 375,000.00 400,000.00


1 bh Valve Ø 500 mm 375,000.00 400,000.00 375,000.00 400,000.00

C PERALATAN 10,000.00 12,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 875,000.00 966,000.00


E Overhead & Profit (contoh 10%) 10% 87,500.00 96,600.00
F Harga Satuan Pekerjaan (D+E) 962,500.00 1,062,600.00

8 A.8.4.3.8 1 bh Pemasangan Valve Ø 600 mm 715,121.00 775,555.00


A Tenaga 174,110.00 196,850.00
L.01 1.421 OH Pekerja 65,000.00 75,000.00 92,365.00 106,575.00
L.02 0.711 OH Tukang Pipa 95,000.00 105,000.00 67,545.00 74,655.00
L.04 0.142 OH Mandor 100,000.00 110,000.00 14,200.00 15,620.00

B Bahan 425,000.00 450,000.00


1 bh Valve Ø 600 mm 425,000.00 450,000.00 425,000.00 450,000.00

C PERALATAN 51,000.00 58,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00
0.300 hari Mobile crane = < 3 ton 150,000.00 170,000.00 45,000.00 51,000.00
D Jumlah A + B + C 650,110.00 705,050.00
E Overhead & Profit (contoh 10%) 10% 65,011.00 70,505.00
F Harga Satuan Pekerjaan (D+E) 715,121.00 775,555.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/238 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.8.4.3.9 1 bh Pemasangan Valve Ø 700 mm 830,621.00 889,878.00
A Tenaga 175,110.00 197,980.00
L.01 1.429 OH Pekerja 65,000.00 75,000.00 92,885.00 107,175.00
L.02 0.715 OH Tukang Pipa 95,000.00 105,000.00 67,925.00 75,075.00
L.04 0.143 OH Mandor 100,000.00 110,000.00 14,300.00 15,730.00

B Bahan 500,000.00 520,000.00


1 bh Valve Ø 700 mm 500,000.00 520,000.00 500,000.00 520,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 755,110.00 808,980.00
E Overhead & Profit (contoh 10%) 10% 75,511.00 80,898.00
F Harga Satuan Pekerjaan (D+E) 830,621.00 889,878.00

10 A.8.4.3.10 1 bh Pemasangan Valve Ø 800 mm 933,707.50 1,004,745.50


A Tenaga 218,825.00 247,405.00
L.01 1.786 OH Pekerja 65,000.00 75,000.00 116,090.00 133,950.00
L.02 0.893 OH Tukang Pipa 95,000.00 105,000.00 84,835.00 93,765.00
L.04 0.179 OH Mandor 100,000.00 110,000.00 17,900.00 19,690.00

B Bahan 550,000.00 575,000.00


1 bh Valve Ø 800 mm 550,000.00 575,000.00 550,000.00 575,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 848,825.00 913,405.00
E Overhead & Profit (contoh 10%) 10% 84,882.50 91,340.50
F Harga Satuan Pekerjaan (D+E) 933,707.50 1,004,745.50

11 A.8.4.3.11 1 bh Pemasangan Valve Ø 900 mm 1,022,917.50 1,098,729.50


A Tenaga 209,925.00 237,345.00
L.01 1.714 OH Pekerja 65,000.00 75,000.00 111,410.00 128,550.00
L.02 0.857 OH Tukang Pipa 95,000.00 105,000.00 81,415.00 89,985.00
L.04 0.171 OH Mandor 100,000.00 110,000.00 17,100.00 18,810.00

B Bahan 600,000.00 625,000.00


1 bh Valve Ø 900 mm 600,000.00 625,000.00 600,000.00 625,000.00

C PERALATAN 120,000.00 136,500.00


0.750 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 7,500.00 9,000.00
0.750 hari Mobile crane = < 3 ton 150,000.00 170,000.00 112,500.00 127,500.00
D Jumlah A + B + C 929,925.00 998,845.00
E Overhead & Profit (contoh 10%) 10% 92,992.50 99,884.50
F Harga Satuan Pekerjaan (D+E) 1,022,917.50 1,098,729.50

12 A.8.4.3.12 1 bh Pemasangan Valve Ø 1.000 mm 1,237,483.50 1,317,937.50


A Tenaga 314,985.00 356,125.00
L.01 2.571 OH Pekerja 65,000.00 75,000.00 167,115.00 192,825.00
L.02 1.286 OH Tukang Pipa 95,000.00 105,000.00 122,170.00 135,030.00
L.04 0.257 OH Mandor 100,000.00 110,000.00 25,700.00 28,270.00

B Bahan 650,000.00 660,000.00


1 bh Valve Ø 1.000 mm 650,000.00 660,000.00 650,000.00 660,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,124,985.00 1,198,125.00
E Overhead & Profit (contoh 10%) 10% 112,498.50 119,812.50
F Harga Satuan Pekerjaan (D+E) 1,237,483.50 1,317,937.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/239 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
13 A.8.4.3.13 1 bh Pemasangan Valve Ø 1.100 mm 1,350,250.00 1,438,250.00
A Tenaga 367,500.00 415,500.00
L.01 3.000 OH Pekerja 65,000.00 75,000.00 195,000.00 225,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 700,000.00 710,000.00


1 bh Valve Ø 1.100 mm 700,000.00 710,000.00 700,000.00 710,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,227,500.00 1,307,500.00
E Overhead & Profit (contoh 10%) 10% 122,750.00 130,750.00
F Harga Satuan Pekerjaan (D+E) 1,350,250.00 1,438,250.00

14 A.8.4.3.14 1 bh Pemasangan Valve Ø 1.200 mm 1,383,250.00 1,482,250.00


A 367,500.00 415,500.00
L.01 3.000 OH Pekerja 65,000.00 75,000.00 195,000.00 225,000.00
L.02 1.500 OH Tukang Pipa 95,000.00 105,000.00 142,500.00 157,500.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 730,000.00 750,000.00


1 bh Valve Ø 1.200 mm 730,000.00 750,000.00 730,000.00 750,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,257,500.00 1,347,500.00
E Overhead & Profit (contoh 10%) 10% 125,750.00 134,750.00
F Harga Satuan Pekerjaan (D+E) 1,383,250.00 1,482,250.00

15 A.8.4.3.15 1 bh Pemasangan Tee Ø 150 mm 27,835.50 33,067.10


A Tenaga 13,025.00 14,725.00
L.01 0.106 OH Pekerja 65,000.00 75,000.00 6,890.00 7,950.00
L.02 0.053 OH Tukang Pipa 95,000.00 105,000.00 5,035.00 5,565.00
L.04 0.011 OH Mandor 100,000.00 110,000.00 1,100.00 1,210.00

B Bahan 12,000.00 15,000.00


1 bh Tee Ø 150 mm 12,000.00 15,000.00 12,000.00 15,000.00

C PERALATAN 280.00 336.00


0.028 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 280.00 336.00

D Jumlah A + B + C 25,305.00 30,061.00


E Overhead & Profit (contoh 10%) 10% 2,530.50 3,006.10
F Harga Satuan Pekerjaan (D+E) 27,835.50 33,067.10

16 A.8.4.3.16 1 bh Pemasangan Tee Ø 200 mm 45,969.00 55,338.80


A Tenaga 26,500.00 29,960.00
L.01 0.216 OH Pekerja 65,000.00 75,000.00 14,040.00 16,200.00
L.02 0.108 OH Tukang Pipa 95,000.00 105,000.00 10,260.00 11,340.00
L.04 0.022 OH Mandor 100,000.00 110,000.00 2,200.00 2,420.00

B Bahan 15,000.00 20,000.00


1 bh Tee Ø 200 mm 15,000.00 20,000.00 15,000.00 20,000.00

C PERALATAN 290.00 348.00


0.029 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 290.00 348.00

D Jumlah A + B + C 41,790.00 50,308.00


E Overhead & Profit (contoh 10%) 10% 4,179.00 5,030.80
F Harga Satuan Pekerjaan (D+E) 45,969.00 55,338.80

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/240 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.8.4.3.17 1 bh Pemasangan Tee Ø 250 mm 71,901.50 83,229.30
A Tenaga 39,975.00 45,195.00
L.01 0.326 OH Pekerja 65,000.00 75,000.00 21,190.00 24,450.00
L.02 0.163 OH Tukang Pipa 95,000.00 105,000.00 15,485.00 17,115.00
L.04 0.033 OH Mandor 100,000.00 110,000.00 3,300.00 3,630.00

B Bahan 25,000.00 30,000.00


1 BH Tee Ø 250 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 390.00 468.00


0.039 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 390.00 468.00

D Jumlah A + B + C 65,365.00 75,663.00


E Overhead & Profit (contoh 10%) 10% 6,536.50 7,566.30
F Harga Satuan Pekerjaan (D+E) 71,901.50 83,229.30

18 A.8.4.3.18 1 bh Pemasangan Tee Ø 300 mm 102,795.00 117,073.00


A Tenaga 53,450.00 60,430.00
L.01 0.436 OH Pekerja 65,000.00 75,000.00 28,340.00 32,700.00
L.02 0.218 OH Tukang Pipa 95,000.00 105,000.00 20,710.00 22,890.00
L.04 0.044 OH Mandor 100,000.00 110,000.00 4,400.00 4,840.00

B Bahan 35,000.00 40,000.00


1 bh Tee Ø 300 mm 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 93,450.00 106,430.00


E Overhead & Profit (contoh 10%) 10% 9,345.00 10,643.00
F Harga Satuan Pekerjaan (D+E) 102,795.00 117,073.00

19 A.8.4.3.19 1 bh Pemasangan Tee Ø 400 mm 143,440.00 161,590.00


A Tenaga 80,400.00 90,900.00
L.01 0.656 OH Pekerja 65,000.00 75,000.00 42,640.00 49,200.00
L.02 0.328 OH Tukang Pipa 95,000.00 105,000.00 31,160.00 34,440.00
L.04 0.066 OH Mandor 100,000.00 110,000.00 6,600.00 7,260.00

B Bahan 45,000.00 50,000.00


1 bh Tee Ø 400 mm 45,000.00 50,000.00 45,000.00 50,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 130,400.00 146,900.00


E Overhead & Profit (contoh 10%) 10% 13,040.00 14,690.00
F Harga Satuan Pekerjaan (D+E) 143,440.00 161,590.00

20 A.8.4.3.20 1 bh Pemasangan Tee Ø 450 mm 180,262.50 200,348.50


A Tenaga 93,875.00 106,135.00
L.01 0.766 OH Pekerja 65,000.00 75,000.00 49,790.00 57,450.00
L.02 0.383 OH Tukang Pipa 95,000.00 105,000.00 36,385.00 40,215.00
L.04 0.077 OH Mandor 100,000.00 110,000.00 7,700.00 8,470.00

B Bahan 65,000.00 70,000.00


1 bh Tee Ø 450 mm 65,000.00 70,000.00 65,000.00 70,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 163,875.00 182,135.00


E Overhead & Profit (contoh 10%) 10% 16,387.50 18,213.50
F Harga Satuan Pekerjaan (D+E) 180,262.50 200,348.50

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/241 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.8.4.3.21 1 bh Pemasangan Tee Ø 500 mm 207,185.00 229,427.00
A Tenaga 107,350.00 121,370.00
L.01 0.876 OH Pekerja 65,000.00 75,000.00 56,940.00 65,700.00
L.02 0.438 OH Tukang Pipa 95,000.00 105,000.00 41,610.00 45,990.00
L.04 0.088 OH Mandor 100,000.00 110,000.00 8,800.00 9,680.00

B Bahan 75,000.00 80,000.00


1 bh Tee Ø 500 mm 75,000.00 80,000.00 75,000.00 80,000.00

C PERALATAN 6,000.00 7,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00

D Jumlah A + B + C 188,350.00 208,570.00


E Overhead & Profit (contoh 10%) 10% 18,835.00 20,857.00
F Harga Satuan Pekerjaan (D+E) 207,185.00 229,427.00

22 A.8.4.3.22 1 bh Pemasangan Tee Ø 600 mm 264,693.00 297,523.60


A Tenaga 134,300.00 151,840.00
L.01 1.096 OH Pekerja 65,000.00 75,000.00 71,240.00 82,200.00
L.02 0.548 OH Tukang Pipa 95,000.00 105,000.00 52,060.00 57,540.00
L.04 0.110 OH Mandor 100,000.00 110,000.00 11,000.00 12,100.00

B Bahan 90,000.00 100,000.00


1 bh Tee Ø 600 mm 90,000.00 100,000.00 90,000.00 100,000.00

C PERALATAN 16,330.00 18,636.00


0.193 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,930.00 2,316.00
0.096 hari Mobile crane = < 3 ton 150,000.00 170,000.00 14,400.00 16,320.00
D Jumlah A + B + C 240,630.00 270,476.00
E Overhead & Profit (contoh 10%) 10% 24,063.00 27,047.60
F Harga Satuan Pekerjaan (D+E) 264,693.00 297,523.60

23 A.8.4.3.23 1 bh Pemasangan Tee Ø 700 mm 319,495.00 351,142.00


A Tenaga 161,250.00 182,310.00
L.01 1.316 OH Pekerja 65,000.00 75,000.00 85,540.00 98,700.00
L.02 0.658 OH Tukang Pipa 95,000.00 105,000.00 62,510.00 69,090.00
L.04 0.132 OH Mandor 100,000.00 110,000.00 13,200.00 14,520.00

B Bahan 110,000.00 115,000.00


1 bh Tee Ø 700 mm 110,000.00 115,000.00 110,000.00 115,000.00

C PERALATAN 19,200.00 21,910.00


0.225 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,250.00 2,700.00
0.113 hari Mobile crane = < 3 ton 150,000.00 170,000.00 16,950.00 19,210.00
D Jumlah A + B + C 290,450.00 319,220.00
E Overhead & Profit (contoh 10%) 10% 29,045.00 31,922.00
F Harga Satuan Pekerjaan (D+E) 319,495.00 351,142.00

24 A.8.4.3.24 1 bh Pemasangan Tee Ø 800 mm 363,132.00 404,573.40


A Tenaga 188,200.00 212,780.00
L.01 1.536 OH Pekerja 65,000.00 75,000.00 99,840.00 115,200.00
L.02 0.768 OH Tukang Pipa 95,000.00 105,000.00 72,960.00 80,640.00
L.04 0.154 OH Mandor 100,000.00 110,000.00 15,400.00 16,940.00

B Bahan 120,000.00 130,000.00


1 bh Tee Ø 800 mm 120,000.00 130,000.00 120,000.00 130,000.00

C PERALATAN 21,920.00 25,014.00


0.257 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,570.00 3,084.00
0.129 hari Mobile crane = < 3 ton 150,000.00 170,000.00 19,350.00 21,930.00
D Jumlah A + B + C 330,120.00 367,794.00
E Overhead & Profit (contoh 10%) 10% 33,012.00 36,779.40
F Harga Satuan Pekerjaan (D+E) 363,132.00 404,573.40

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/242 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
25 A.8.4.3.25 1 bh Pemasangan Tee Ø 900 mm 420,761.00 466,919.20
A Tenaga 215,150.00 243,250.00
L.01 1.756 OH Pekerja 65,000.00 75,000.00 114,140.00 131,700.00
L.02 0.878 OH Tukang Pipa 95,000.00 105,000.00 83,410.00 92,190.00
L.04 0.176 OH Mandor 100,000.00 110,000.00 17,600.00 19,360.00

B Bahan 140,000.00 150,000.00


1 bh Tee Ø 900 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN 27,360.00 31,222.00


0.321 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,210.00 3,852.00
0.161 hari Mobile crane = < 3 ton 150,000.00 170,000.00 24,150.00 27,370.00
D Jumlah A + B + C 382,510.00 424,472.00
E Overhead & Profit (contoh 10%) 10% 38,251.00 42,447.20
F Harga Satuan Pekerjaan (D+E) 420,761.00 466,919.20

26 A.8.4.3.26 1 bh Pemasangan Tee Ø 1.000 mm 476,531.00 527,144.20


A Tenaga 242,100.00 273,720.00
L.01 1.976 OH Pekerja 65,000.00 75,000.00 128,440.00 148,200.00
L.02 0.988 OH Tukang Pipa 95,000.00 105,000.00 93,860.00 103,740.00
L.04 0.198 OH Mandor 100,000.00 110,000.00 19,800.00 21,780.00

B Bahan 160,000.00 170,000.00


1 bh Tee Ø 1.000 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN 31,110.00 35,502.00


0.366 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,660.00 4,392.00
0.183 hari Mobile crane = < 3 ton 150,000.00 170,000.00 27,450.00 31,110.00
D Jumlah A + B + C 433,210.00 479,222.00
E Overhead & Profit (contoh 10%) 10% 43,321.00 47,922.20
F Harga Satuan Pekerjaan (D+E) 476,531.00 527,144.20

27 A.8.4.3.27 1 bh Pemasangan Tee Ø 1.100 mm 530,046.00 584,795.20


A Tenaga 269,050.00 304,190.00
L.01 2.196 OH Pekerja 65,000.00 75,000.00 142,740.00 164,700.00
L.02 1.098 OH Tukang Pipa 95,000.00 105,000.00 104,310.00 115,290.00
L.04 0.220 OH Mandor 100,000.00 110,000.00 22,000.00 24,200.00

B Bahan 180,000.00 190,000.00


1 bh Tee Ø 1.100 mm 180,000.00 190,000.00 180,000.00 190,000.00

C PERALATAN 32,810.00 37,442.00


0.386 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,860.00 4,632.00
0.193 hari Mobile crane = < 3 ton 150,000.00 170,000.00 28,950.00 32,810.00
D Jumlah A + B + C 481,860.00 531,632.00
E Overhead & Profit (contoh 10%) 10% 48,186.00 53,163.20
F Harga Satuan Pekerjaan (D+E) 530,046.00 584,795.20

28 A.8.4.3.28 1 bh Pemasangan Tee Ø 1.200 mm 587,675.00 647,141.00


A Tenaga 296,000.00 334,660.00
L.01 2.416 OH Pekerja 65,000.00 75,000.00 157,040.00 181,200.00
L.02 1.208 OH Tukang Pipa 95,000.00 105,000.00 114,760.00 126,840.00
L.04 0.242 OH Mandor 100,000.00 110,000.00 24,200.00 26,620.00

B Bahan 200,000.00 210,000.00


1 bh Tee Ø 1.200 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN 38,250.00 43,650.00


0.450 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,500.00 5,400.00
0.225 hari Mobile crane = < 3 ton 150,000.00 170,000.00 33,750.00 38,250.00
D Jumlah A + B + C 534,250.00 588,310.00
E Overhead & Profit (contoh 10%) 10% 53,425.00 58,831.00
F Harga Satuan Pekerjaan (D+E) 587,675.00 647,141.00

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/243 18-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA
Penyambungan Pipa Baru ke Pipa yang ada Ø
1 A.8.4.4.1 1 bh 424,242.50 500,054.50
80 mm
A Tenaga 179,625.00 203,085.00
L.01 1.466 OH Pekerja 65,000.00 75,000.00 95,290.00 109,950.00
L.02 0.733 Tukang Pipa 95,000.00 105,000.00 69,635.00 76,965.00
L.04 0.147 OH Mandor 100,000.00 110,000.00 14,700.00 16,170.00

B Bahan 50,000.00 65,000.00


1 bh Pipa Ø 80 mm 50,000.00 65,000.00 50,000.00 65,000.00

C PERALATAN 156,050.00 186,510.00


0.606 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 15,150.00 18,180.00
0.075 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 11,250.00 12,750.00
0.968 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 121,000.00 145,200.00
0.865 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,650.00 10,380.00

D Jumlah A + B + C 385,675.00 454,595.00


E Overhead & Profit (contoh 10%) 10% 38,567.50 45,459.50
F Harga Satuan Pekerjaan (D+E) 424,242.50 500,054.50

2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 510,251.50 579,894.70
100 mm
A Tenaga 209,905.00 228,015.00
L.01 1.646 OH Pekerja 70,000.00 75,000.00 115,220.00 123,450.00
L.02 0.823 OH Tukang Pipa 95,000.00 105,000.00 78,185.00 86,415.00
L.04 0.165 OH Mandor 100,000.00 110,000.00 16,500.00 18,150.00
B Bahan 70,000.00 80,000.00
1 bh Pipa Ø 100 mm 70,000.00 80,000.00 70,000.00 80,000.00
C PERALATAN 183,960.00 219,162.00
0.650 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 16,250.00 19,500.00
0.159 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 23,850.00 27,030.00
1.078 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 134,750.00 161,700.00
0.911 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 9,110.00 10,932.00
D Jumlah A + B + C 463,865.00 527,177.00
E Overhead & Profit (contoh 10%) 10% 46,386.50 52,717.70
F Harga Satuan Pekerjaan (D+E) 510,251.50 579,894.70

3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 738,116.50 826,245.20
150 mm
A Tenaga 267,280.00 290,340.00
L.01 2.096 OH Pekerja 70,000.00 75,000.00 146,720.00 157,200.00
L.02 1.048 OH Tukang Pipa 95,000.00 105,000.00 99,560.00 110,040.00
L.04 0.210 OH Mandor 100,000.00 110,000.00 21,000.00 23,100.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 671,015.00 751,132.00
E Overhead & Profit (contoh 10%) 10% 67,101.50 75,113.20
F Harga Satuan Pekerjaan (D+E) 738,116.50 826,245.20

4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 932,981.50 1,050,595.70
200 mm
A Tenaga 324,655.00 352,665.00
L.01 2.546 OH Pekerja 70,000.00 75,000.00 178,220.00 190,950.00
L.02 1.273 OH Tukang Pipa 95,000.00 105,000.00 120,935.00 133,665.00
L.04 0.255 OH Mandor 100,000.00 110,000.00 25,500.00 28,050.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 848,165.00 955,087.00
E Overhead & Profit (contoh 10%) 10% 84,816.50 95,508.70
F Harga Satuan Pekerjaan (D+E) 932,981.50 1,050,595.70

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/244 19-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,100,346.50 1,230,946.20
250 mm
A Tenaga 382,030.00 414,990.00
L.01 2.996 OH Pekerja 70,000.00 75,000.00 209,720.00 224,700.00
L.02 1.498 OH Tukang Pipa 95,000.00 105,000.00 142,310.00 157,290.00
L.04 0.300 OH Mandor 100,000.00 110,000.00 30,000.00 33,000.00

B Bahan 225,000.00 240,000.00


1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00

C PERALATAN 393,285.00 464,052.00


0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00

D Jumlah A + B + C 1,000,315.00 1,119,042.00


E Overhead & Profit (contoh 10%) 10% 100,031.50 111,904.20
F Harga Satuan Pekerjaan (D+E) 1,100,346.50 1,230,946.20

6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,256,711.50 1,400,296.70
300 mm
A Tenaga 439,405.00 477,315.00
L.01 3.446 OH Pekerja 70,000.00 75,000.00 241,220.00 258,450.00
L.02 1.723 OH Tukang Pipa 95,000.00 105,000.00 163,685.00 180,915.00
L.04 0.345 OH Mandor 100,000.00 110,000.00 34,500.00 37,950.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,142,465.00 1,272,997.00
E Overhead & Profit (contoh 10%) 10% 114,246.50 127,299.70
F Harga Satuan Pekerjaan (D+E) 1,256,711.50 1,400,296.70

7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,569,441.50 1,749,997.70
400 mm
A Tenaga 554,155.00 601,965.00
L.01 4.346 OH Pekerja 70,000.00 75,000.00 304,220.00 325,950.00
L.02 2.173 OH Tukang Pipa 95,000.00 105,000.00 206,435.00 228,165.00
L.04 0.435 OH Mandor 100,000.00 110,000.00 43,500.00 47,850.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,426,765.00 1,590,907.00
E Overhead & Profit (contoh 10%) 10% 142,676.50 159,090.70
F Harga Satuan Pekerjaan (D+E) 1,569,441.50 1,749,997.70

8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,731,306.50 1,930,348.20
450 mm
A Tenaga 611,530.00 664,290.00
L.01 4.796 OH Pekerja 70,000.00 75,000.00 335,720.00 359,700.00
L.02 2.398 OH Tukang Pipa 95,000.00 105,000.00 227,810.00 251,790.00
L.04 0.480 OH Mandor 100,000.00 110,000.00 48,000.00 52,800.00
B Bahan 290,000.00 300,000.00
1 bh Pipa Ø 450 mm 290,000.00 300,000.00 290,000.00 300,000.00
C PERALATAN 672,385.00 790,572.00
1.420 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 35,500.00 42,600.00
1.629 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 244,350.00 276,930.00
3.003 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 375,375.00 450,450.00
1.716 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 17,160.00 20,592.00
D Jumlah A + B + C 1,573,915.00 1,754,862.00
E Overhead & Profit (contoh 10%) 10% 157,391.50 175,486.20
F Harga Satuan Pekerjaan (D+E) 1,731,306.50 1,930,348.20

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/245 19-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,904,171.50 2,121,698.70
500 mm
A Tenaga 668,905.00 726,615.00
L.01 5.246 OH Pekerja 70,000.00 75,000.00 367,220.00 393,450.00
L.02 2.623 OH Tukang Pipa 95,000.00 105,000.00 249,185.00 275,415.00
L.04 0.525 OH Mandor 100,000.00 110,000.00 52,500.00 57,750.00
B Bahan 320,000.00 330,000.00
1 bh Pipa Ø 500 mm 320,000.00 330,000.00 320,000.00 330,000.00
C PERALATAN 742,160.00 872,202.00
1.530 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 38,250.00 45,900.00
1.839 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 275,850.00 312,630.00
3.278 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 409,750.00 491,700.00
1.831 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 18,310.00 21,972.00
D Jumlah A + B + C 1,731,065.00 1,928,817.00
E Overhead & Profit (contoh 10%) 10% 173,106.50 192,881.70
F Harga Satuan Pekerjaan (D+E) 1,904,171.50 2,121,698.70

10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,216,901.50 2,471,399.70
600 mm
A Tenaga 783,655.00 851,265.00
L.01 6.146 OH Pekerja 70,000.00 75,000.00 430,220.00 460,950.00
L.02 3.073 OH Tukang Pipa 95,000.00 105,000.00 291,935.00 322,665.00
L.04 0.615 OH Mandor 100,000.00 110,000.00 61,500.00 67,650.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00

D Jumlah A + B + C 2,015,365.00 2,246,727.00


E Overhead & Profit (contoh 10%) 10% 201,536.50 224,672.70
F Harga Satuan Pekerjaan (D+E) 2,216,901.50 2,471,399.70

11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,562,631.50 2,854,100.70
700 mm
A Tenaga 898,405.00 975,915.00
L.01 7.046 OH Pekerja 70,000.00 75,000.00 493,220.00 528,450.00
L.02 3.523 OH Tukang Pipa 95,000.00 105,000.00 334,685.00 369,915.00
L.04 0.705 OH Mandor 100,000.00 110,000.00 70,500.00 77,550.00

B Bahan 410,000.00 420,000.00


1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00
D Jumlah A + B + C 2,329,665.00 2,594,637.00
E Overhead & Profit (contoh 10%) 10% 232,966.50 259,463.70
F Harga Satuan Pekerjaan (D+E) 2,562,631.50 2,854,100.70

12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,864,361.50 3,203,801.70
800 mm
A Tenaga 1,013,155.00 1,100,565.00
L.01 7.946 OH Pekerja 70,000.00 75,000.00 556,220.00 595,950.00
L.02 3.973 OH Tukang Pipa 95,000.00 105,000.00 377,435.00 417,165.00
L.04 0.795 OH Mandor 100,000.00 110,000.00 79,500.00 87,450.00
B Bahan 430,000.00 450,000.00
1 bh Pipa Ø 800 mm 430,000.00 450,000.00 430,000.00 450,000.00
C PERALATAN 1,160,810.00 1,361,982.00
2.190 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 54,750.00 65,700.00
3.099 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 464,850.00 526,830.00
4.928 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 616,000.00 739,200.00
2.521 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 25,210.00 30,252.00
D Jumlah A + B + C 2,603,965.00 2,912,547.00
E Overhead & Profit (contoh 10%) 10% 260,396.50 291,254.70
F Harga Satuan Pekerjaan (D+E) 2,864,361.50 3,203,801.70

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/246 19-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XX A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN
1 A.8.4.5.1 1 m' Pengetesan Pipa Ø 50 mm 1,283.98 1,417.08
A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 567.25 600.25


0.002 m³ Air Bersih 125.00 125.00 0.25 0.25
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,167.25 1,288.25


E Overhead & Profit (contoh 10%) 10% 116.73 128.83
F Harga Satuan Pekerjaan (D+E) 1,283.98 1,417.08

2 A.8.4.5.2 1 m' Pengetesan Pipa Ø 75 mm 1,284.25 1,417.35


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 567.50 600.50


0.004 m³ Air Bersih 125.00 125.00 0.50 0.50
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,167.50 1,288.50


E Overhead & Profit (contoh 10%) 10% 116.75 128.85
F Harga Satuan Pekerjaan (D+E) 1,284.25 1,417.35

3 A.8.4.5.3 1 m' Pengetesan Pipa Ø 100 mm 1,284.80 1,417.90


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 568.00 601.00


0.008 m³ Air Bersih 125.00 125.00 1.00 1.00
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,168.00 1,289.00


E Overhead & Profit (contoh 10%) 10% 116.80 128.90
F Harga Satuan Pekerjaan (D+E) 1,284.80 1,417.90

4 A.8.4.5.4 1 m' Pengetesan Pipa Ø 150 mm 1,286.18 1,419.28


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 569.25 602.25


0.0180 m³ Air Bersih 125.00 125.00 2.25 2.25
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,169.25 1,290.25


E Overhead & Profit (contoh 10%) 10% 116.93 129.03
F Harga Satuan Pekerjaan (D+E) 1,286.18 1,419.28

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/247 20-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.8.4.5.5 1 m' Pengetesan Pipa Ø 200 mm 1,287.96 1,421.06
A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 570.88 603.88


0.031 m³ Air Bersih 125.00 125.00 3.88 3.88
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,170.88 1,291.88


E Overhead & Profit (contoh 10%) 10% 117.09 129.19
F Harga Satuan Pekerjaan (D+E) 1,287.96 1,421.06

6 A.8.4.5.6 1 m' Pengetesan Pipa Ø 250 mm 1,290.44 1,423.54


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 573.13 606.13


0.049 m³ Air Bersih 125.00 125.00 6.13 6.13
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,173.13 1,294.13


E Overhead & Profit (contoh 10%) 10% 117.31 129.41
F Harga Satuan Pekerjaan (D+E) 1,290.44 1,423.54

7 A.8.4.5.7 1 m' Pengetesan Pipa Ø 300 mm 1,293.46 1,426.56


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 575.88 608.88


0.071 m³ Air Bersih 125.00 125.00 8.88 8.88
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,175.88 1,296.88


E Overhead & Profit (contoh 10%) 10% 117.59 129.69
F Harga Satuan Pekerjaan (D+E) 1,293.46 1,426.56

8 A.8.4.5.8 1 m' Pengetesan Pipa Ø 400 mm 1,301.03 1,434.13


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 582.75 615.75


0.126 m³ Air Bersih 125.00 125.00 15.75 15.75
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,182.75 1,303.75


E Overhead & Profit (contoh 10%) 10% 118.28 130.38
F Harga Satuan Pekerjaan (D+E) 1,301.03 1,434.13

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/248 20-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.8.4.5.9 1 m' Pengetesan Pipa Ø 500 mm 1,305.43 1,438.53
A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 586.75 619.75


0.158 m³ Air Bersih 125.00 125.00 19.75 19.75
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,186.75 1,307.75


E Overhead & Profit (contoh 10%) 10% 118.68 130.78
F Harga Satuan Pekerjaan (D+E) 1,305.43 1,438.53

10 A.8.4.5.10 1 m' Pengetesan Pipa Ø 600 mm 1,322.61 1,455.71


A Tenaga 600.00 688.00
L.01 0.008 OH Pekerja 65,000.00 75,000.00 520.00 600.00
L.04 0.0008 OH Mandor 100,000.00 110,000.00 80.00 88.00

B Bahan 602.38 635.38


0.283 m³ Air Bersih 125.00 125.00 35.38 35.38
0.060 ltr Bahan Bakar 8,200.00 8,500.00 492.00 510.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,202.38 1,323.38


E Overhead & Profit (contoh 10%) 10% 120.24 132.34
F Harga Satuan Pekerjaan (D+E) 1,322.61 1,455.71

file:///conversion/tmp/activity_task_scratch/530032289.xls 249/249 20-20

Anda mungkin juga menyukai