HARGA SATUAN
No. JENIS PERALATAN SATUAN SEWA PERALATAN
(Rp.)
1,069,200.00 90.60
11,801.32 1.00
A. TENAGA
1 Pekerja L.01 OH 0.4000 90,000.00 36,000.00
2 Tukang Kayu L.02 OH 0.2000 110,000.00 22,000.00
3 Kepala Tukang Kayu L.03 OH 0.0200 120,000.00 2,400.00
4 Mandor L.04 OH 0.0200 130,000.00 2,600.00
B. BAHAN
Dolken Kayu
1 Batang 1.2500 -
8-10/400 cm
2 Semen Portland KG 5.0000 1,200.00 6,000.00
3 Pasir Beton M3 0.0050 250,000.00 1,250.00
4 Koral Beton M3 0.0090 395,000.00 3,555.00
5 Kayu 5/7 M3 0.0720 -
6 Paku biasa 2"-5" KG 0.0600 15,000.00 900.00
7 Residu Liter 0.4000 13,400.00 5,360.00
-
JUMLAH HARGA BAHAN 17,065.00
C. ALAT
JENIS PEKERJAAN : Pembuatan Pagar Sementara dari Seng Gelombang Tinggi 2 Meter
SATUAN PEKERJAAN : M2
HARGA SATUAN : Rp 83,270.00
A. TENAGA
1 Pekerja L.01 OH 0.2000 90,000.00 18,000.00
2 Tukang Kayu L.02 OH 0.4000 110,000.00 44,000.00
3 Kepala Tukang L.03 OH 0.0200 120,000.00 2,400.00
4 Mandor L.04 OH 0.0200 130,000.00 2,600.00
B. BAHAN
Dolken Kayu
1 Batang 1.2500 -
8-10/400 cm
2 Semen Portland KG 2.5000 1,200.00 3,000.00
3 Seng Gelombang Lbr 1.2000 -
4 Pasir Beton M3 0.0050 250,000.00 1,250.00
5 Koral Beton M3 0.0090 395,000.00 3,555.00
6 Kayu 5/7 M3 0.0720 -
7 Paku biasa 2"-5" KG 0.0600 15,000.00 900.00
8 Meni Besi Liter 0.4500
-
JUMLAH HARGA BAHAN 8,705.00
C. ALAT
JENIS PEKERJAAN : Pembuatan Pagar Sementara dari Kawat Duri Tinggi 1.8 Meter
SATUAN PEKERJAAN : M2
HARGA SATUAN : Rp 70,510.00
A. TENAGA
1 Pekerja L.01 OH 0.2000 90,000.00 18,000.00
2 Tukang Kayu L.02 OH 0.3000 110,000.00 33,000.00
3 Kepala Tukang L.03 OH 0.0200 120,000.00 2,400.00
4 Mandor L.04 OH 0.0200 130,000.00 2,600.00
B. BAHAN
Dolken Kayu
1 Batang 1.0000 -
8-10/400 cm
2 Semen Portland KG 2.0000 1,200.00 2,400.00
3 Kawat Duri M' 25.0000 -
4 Pasir Beton M3 0.0050 250,000.00 1,250.00
5 Koral Beton M3 0.0090 395,000.00 3,555.00
6 Paku biasa 2"-5" KG 0.0600 15,000.00 900.00
-
JUMLAH HARGA BAHAN 8,105.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 0.1000 90,000.00 9,000.00
2 Tukang Kayu L.02 OH 0.1000 110,000.00 11,000.00
3 Kepala Tukang Kayu L.03 OH 0.0100 120,000.00 1,200.00
4 Mandor L.04 OH 0.0050 130,000.00 650.00
B. BAHAN
1 Kayu Balok 5/7 Batang 0.1200 -
2 Paku 2"-3" KG 0.0200 15,000.00 300.00
3 Kayu Papan 3/20 M3 0.0070 -
-
JUMLAH HARGA BAHAN 300.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 2.0000 90,000.00 180,000.00
2 Tukang Kayu L.02 OH 2.0000 110,000.00 220,000.00
3 Tukang Batu L.02 OH 1.0000 110,000.00 110,000.00
4 Kepala Tukang L.03 OH 0.3000 120,000.00 36,000.00
5 Mandor L.04 OH 0.0500 130,000.00 6,500.00
B. BAHAN
Dolken Kayu
1 Batang 1.2500 -
8-10/400 cm
2 Kayu M3 0.1800 -
3 Paku Biasa KG 0.0800 15,000.00 1,200.00
4 Besi Strip KG 1.1000 -
5 Semen Portland KG 35.0000 1,200.00 42,000.00
6 Pasir Pasang M3 0.1500 250,000.00 37,500.00
7 Pasir Beton M3 0.1000 250,000.00 25,000.00
8 Koral Beton M3 0.1500 395,000.00 59,250.00
9 Bata Merah Bh 30.0000 -
10 Seng Plat Lbr 0.2500 -
11 Jendela Naco Bh 0.2000 -
12 Kaca Polos M2 0.0800 -
13 Kunci Tanam Bh 0.1500 -
14 Pywood 4mm Lbr 0.0600 -
-
JUMLAH HARGA BAHAN 164,950.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 1.0000 90,000.00 90,000.00
2 Tukang Kayu L.02 OH 1.5000 110,000.00 165,000.00
3 Kepala Tukang Kayu L.03 OH 0.1500 120,000.00 18,000.00
4 Mandor L.04 OH 0.0500 130,000.00 6,500.00
B. BAHAN
Dolken Kayu
1 Batang 3.0000 3,250,000.00 9,750,000.00
8-10/400 cm
2 Kayu 5/7 M3 0.2760 3,250,000.00 897,000.00
3 Paku biasa 2"-5" KG 0.7000 15,000.00 10,500.00
4 Seng Gelombang Lbr 1.5000 395,000.00 592,500.00
-
JUMLAH HARGA BAHAN 11,250,000.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 1.0000 90,000.00 90,000.00
2 Tukang Kayu L.02 OH 2.0000 110,000.00 220,000.00
3 Kepala Tukang L.03 OH 0.2000 120,000.00 24,000.00
4 Mandor L.04 OH 0.0050 130,000.00 650.00
B. BAHAN
Dolken Kayu
1 Batang 1.7000 3,250,000.00 5,525,000.00
8-10/400 cm
2 Kayu M3 0.2100 3,250,000.00 682,500.00
3 Paku biasa KG 0.3000 15,000.00 4,500.00
4 Semen Portland KG 10.5000 1,200.00 12,600.00
5 Pasir Beton M3 0.0300 250,000.00 7,500.00
6 Koral Beton M3 0.0500 395,000.00 19,750.00
7 Seng Gelombang Lbr 1.5000 15,000.00 22,500.00
8 Seng Plat Lbr 0.2500 -
-
JUMLAH HARGA BAHAN 6,274,350.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 1.0000 90,000.00 90,000.00
2 Tukang Kayu L.02 OH 2.0000 110,000.00 220,000.00
3 Kepala Tukang L.03 OH 0.2000 120,000.00 24,000.00
4 Mandor L.04 OH 0.0500 130,000.00 6,500.00
B. BAHAN
Dolken Kayu
1 Batang 1.2500 -
8-10/400 cm
2 Kayu M3 0.1860 -
3 Paku Biasa KG 0.3000 15,000.00 4,500.00
4 Semen Portland KG 18.0000 1,200.00
5 Pasir Beton M3 0.0300 250,000.00
6 Koral Beton M3 0.0500 395,000.00
7 Seng Gelombang Lbr 1.5000 -
8 Plywood 4mm Lbr 1.3500 -
-
JUMLAH HARGA BAHAN 4,500.00
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 0.1000 90,000.00 9,000.00
2 Mandor L.04 OH 0.0500 130,000.00 6,500.00
B. BAHAN
-
JUMLAH HARGA BAHAN -
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 1.0000 90,000.00 90,000.00
2 Tukang Kayu L.02 OH 2.0000 110,000.00 220,000.00
3 Kepala Tukang L.03 OH 0.2000 120,000.00 24,000.00
4 Mandor L.04 OH 0.0500 130,000.00 6,500.00
B. BAHAN
Bambu Dia 6-
1 Batang 1.2500 -
8/600 cm
2 Tali Ijuk M3 0.1860 -
-
JUMLAH HARGA BAHAN -
C. ALAT
A. TENAGA
1 Tukang Kayu L.02 OH 0.3000 110,000.00 33,000.00
2 Kepala Tukang L.03 OH 0.0300 120,000.00 3,600.00
B. BAHAN
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 1.0000 90,000.00 90,000.00
2 Mandor L.04 OH 0.0050 130,000.00 650.00
B. BAHAN
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 13.3340 90,000.00 1,200,060.00
2 Mandor L.04 OH 0.6660 130,000.00 86,580.00
B. BAHAN
-
JUMLAH HARGA BAHAN -
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 6.6670 90,000.00 600,030.00
2 Mandor L.04 OH 0.3330 130,000.00 43,290.00
B. BAHAN
-
JUMLAH HARGA BAHAN -
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 0.0420 90,000.00 3,780.00
2 Tukang L.02 OH 0.0040 110,000.00 440.00
3 Kepala Tukang L.03 OH 0.0020 120,000.00 240.00
4 Mandor L.04 OH 0.0420 130,000.00 5,460.00
B. BAHAN
1 Kawat Jaring Lbr 0.1434 -
C. ALAT
A. TENAGA
1 Pekerja L.01 OH 0.3750 90,000.00 33,750.00
2 Tukang L.02 OH 0.1250 110,000.00 13,750.00
###
### 3 Kepala Tukang L.03 OH 0.0120 120,000.00 1,440.00
4 Mandor L.04 OH 0.0190 130,000.00 2,470.00
B. BAHAN
1 Panel Beton Pracetak Lbr 0.9860 -
2 Kolom Beton Pracetak Batang 0.5250 -
3 Semen PC KG 45.0000 1,200.00 54,000.00
4 Pasir Beton M3 0.0740 250,000.00 18,500.00
5 Koral M3 0.1460 395,000.00 57,670.00
C. ALAT