HARGA SATUAN
NO. JENIS BAHAN SAT. KETERANGAN
(Rp)
A BAHAN DASAR
1 Batu Kali M3 150,000.00
2 Kerikil Beton M3 130,000.00
3 Split 1-2 M3 285,000.00
4 Pasir Pasang M3 120,000.00
5 Pasir Beton M3 120,000.00
6 Pasir Urug M3 95,000.00
7 Porland Cement 50 Kg Zak 62,500.00
8 Batu Bata Bh 950.00
10 Bahan Bakar Solar Ltr 6,450.00
11 Pelumas / Oil Ltr 45,000.00
C BAHAN BESI
1 Besi Beton Kg 13,650.00
2 Kawat Ikat/ Kawat Beton Kg 21,850.00
3 Sekrup Kg 19,500.00
4 PAKU - ukuran 1" s/d 4" Kg 21,000.00
5 Paku Triplek Kg 18,500.00
6 Paku Atap Kg 22,500.00
7 Kunci Tanam Bh 185,000.00
8 Engsel Pintu Bh 15,000.00
9 Grendel Pintu Bh 14,500.00
10 Engsel Jendela Type Casement Solid 701 12" Bh 18,500.00
11 Handle / Tarikan Jendela ( Rambucis ) Bh 12,500.00
D SANITAIR
1 Pipa PVC type AW ø 3" M1 35,100.00
2 Pipa PVC type AW ø 2.5" M1 28,100.00
3 Pipa PVC type AW ø 3/4" M1 9,800.00
4 Kran Air 3/4 " Bh 30,000.00
5 Stopkran Kuningan 3" Bh 1,525,000.00
6 Seal Tape Bh 3,500.00
DAFTAR UPAH PEKERJA
HARGA SATUAN
NO. JENIS TENAGA SATUAN KET.
(Rp)
1 Pekerja Hr 105,000.00
2 Mandor Hr 130,000.00
3 Tukang listrik Hr 125,000.00
4 Tukang kayu Hr 125,000.00
5 Kep. tk. kayu Hr 130,200.00
6 Tukang batu Hr 125,000.00
7 Kep. tk. batu Hr 130,200.00
8 Tukang besi Hr 125,000.00
9 Kep. tk. besi Hr 130,200.00
10 Tukang cat Hr 125,000.00
11 Kep. tk. cat Hr 130,200.00
12 Operator Hr 125,000.00
TTD
HARMAIZEN
Direktur