Anda di halaman 1dari 9

PROGRAM HIBAH KHUSUS PAMSIMAS

DAFTAR HARGA SATUAN UPAH DAN BAHAN


TAHUN ANGGARAN 2018

HARGA
NO URAIAN SATUAN SATUAN KET.
( Rp )
1 2 3 4 5
I UPAH TENAGA KERJA
1 Pekerja OH 85,000
2 Tukang Batu OH 120,000
3 Tukang Kayu OH 120,000
4 Tukang Besi OH 120,000
5 Tukang Cat OH 120,000
6 Tukang OH 120,000
II BAHAN
A. Bahan Batu, Semen, Tanah dan Pasir
1 Batu Belah/Gunung M3 150,000
2 Batu Bata Bh 800
3 Batu Pecah 5/7 M3 175,000
4 Batu Pecah 3/5 M3 175,000
5 Batu Pecah 1/3 M3 175,000
6 Batu Kali M3 150,000
7 Split M3 150,000
8 Kerikil M3 170,000
9 Kerikil Halus M3 175,000
10 Pasir Pasangan M3 120,000
11 Pasir Urug M3 120,000
12 Semen Tonasa @ 50 Kg Kg 1,640 84,000.00
13 Semen Tiga Roda @ 50 Kg Kg 1,640 84,000.00
14 Semen Bosowa @ 50 Kg Kg 1,400
15 Semen Warna Kg 15,000
16 Domato Timbunan Pilihan M3 90,000
17 Tanah Urug M3 80,000
18 Buis Beton m 150,000

B. Bahan Kayu
1 Kayu Lingua Balok Klas I M3 4,485,000
2 Kayu Lingua Papan Klas I M3 4,485,000
3 Kayu Papan Klas II M3 3,622,500
4 Kayu Balok Klas II M3 3,622,500
5 Kayu Balok Kls III M3 3,335,000
6 Kayu Papan Kls III M3 3,335,000
7 Kayu Papan Kls IV M3 2,750,000
8 Kayu Lis Profil 3 cm Btg 15,000
9 Seng Plat Lembar 55,000
C. Bahan Logam
1 Besi Beton Polos Kg 11,000
2 Besi Ulir Dia. 13" Kg 18,065
2 Besi Beton Dia 6" Ujung 35,000
3 Besi Beton Dia 8" Ujung 60,000
4 Besi Beton Dia 10" Ujung 85,000
5 Besi Beton Dia 12" Ujung 120,000
6 Besi Beton Dia 16" Ujung 230,000
7 Kawat Beton Kg 34,500
8 Paku Biasa Kg 20,000
9 Paku Biasa 3 cm - 7 cm Kg 32,200
10 Paku Seng Kg 25,000
11 Paku Triplek Kg 23,000
12 Seng Gelombang BJLS 20 Kl Lbr 55,000
13 Seng Plat BJLS 20 Kl Lbr 50,000

D. Perlengkapan Pintu dan Jendela


1 Daun Pintu Seng Plat Set 600,000
2 Batu Karawang 12 x 24 cm Bh 5,000

E. Bahan Lantai
1 Keramik Lantai 30 x 30 cm bh 6,000
2 Keramik Lantai 20 x 20 cm bh 2,680
3 Keramik Dinding 20 x 25 cm Dos 65,000
4 Plint Warna 30 x 30 cm Dos 60,000

F. Bahan Cat
1 Amplas Lbr 5,000
2 Cat Dasar Kg 13,000
3 Cat Tembok ( Metrolite ) Kg 70,000
4 Cat Kayu Kg 66,125
5 Dempul Kayu Kg 20,000
6 Meni Kayu Kg 50,000
7 Plamer / Dempul Tembok ( Setara Wallputty ) Kg 10,000

G. Bahan Instalasi Listrik


1 Biaya Penyambungan ( BP ) Watt 900 Ls 1,300,000
2 Biaya Penyambungan ( BP ) Watt 1300 Ls 4,500,000
3 Biaya Penyambungan ( BP ) Watt 2200 Ls 5,000,000
4 Instalasi Listrik ( Titik lampu ) Ttk 135,000
5 Kabel Eterna 2 x 2.5 mm M 12,000
6 Stop Kontak bh 7,500
7 Lampu Pijar 15 Watt bh 31,000
8 Lampu TL 20 Watt bh 20,000
9 Saklar Tunggal bh 7,500
10 Saklar Ganda bh 8,000
11 Rumah Saklar bh 2,500
12 Pelampung Otomat bh 100,000
13 Klep saringan bh 50,000
14 MCB bh 100,000

H. Perlengkapan Sanitair
1 1 M' Pipa GIP Diameter 1/2 " Ujung 96,000 16,000.00
2 1 M' Pipa GIP Diameter 3/4 " Ujung 110,000 18,333.33
3 1 M' Pipa GIP Diameter 1 1/2" Ujung 205,000 35,800.00
1 M' Pipa GIP Diameter 1" Ujung 157,500 26,258.33
4 1 M' Pipa GIP Diameter 2 " Ujung 306,600 51,100.00
5 1 M' Pipa GIP Diameter 3 " Ujung 350,000 58,400.00
6 1 M' Pipa PVC Diameter 1/2 " Ujung 25,000
7 1 M' Pipa PVC Diameter 1 " Ujung 35,000
8 1 M' Pipa PVC Diameter 1,5 " Ujung 80,000
9 1 M' Pipa PVC Diameter 2 " Ujung 110,000
10 1 M' Pipa PVC Diameter 3 " Ujung 175,000
11 Pipa PVC SNI Diameter 3 " M' 55,000 330,000.00
12 Pipa PVC SNI Diameter 2 " M' 34,000 204,000.00
13 Pipa PVC SNI Diameter 1,5 " M' 25,000 150,000.00
14 Pipa PVC SNI Diameter 1 " M' 16,000
15 Pipa PVC SNI Diameter 3/4 " M' 9,000
16 Pipa PE Diameter 1/2 " M' 8,000
17 Asesoris Ukuran 1/2" Bh 5,000
18 Asesoris Ukuran 3/4" Bh 7,000
19 Asesoris Ukuran 1" Bh 8,000
20 Asesoris Ukuran 1 1/4" Bh 15,000
21 Asesoris Ukuran 1 1/2" Bh 17,500
22 Asesoris Ukuran 2" Bh 20,000
23 Asesoris Ukuran 2 1/2" Bh 25,000
24 Asesoris Ukuran 3" Bh 27,500
25 Beugel Ø 2" x 1/2" Bh 40,000
26 Doble Niple GIP 1/2" Bh 7,000
27 Doble Niple GIP 3" Bh 35,000
28 Knee GIP Ø 1/2" Bh 6,000
29 Kloset Jongkok Bh 150,000
30 Kran Air Bh 30,000
31 Meter Air Bh 100,000
32 Gate Valve 1.5 inch Bh 650,000
33 Gate Valve 2 inch Bh 750,000
34 Selang Air M' 15,000
35 Profil Tank 1100 ltr bh 1,500,000
36 Seal Tape Bh 5,000
37 Pompa Air Jet Pump 40/40 Unit 5,000,000
38 Pompa Sumersible Unit 8,500,000
39 Bak Reservoir Figre Glass Kap. 1000 Liter Unit 1,300,000
I. ALAT
1 Cangkul Bh 50,000
2 Sekop Bh 50,000
3 Linggis Bh 75,000
4 Ember Bh 15,000
5 Tali Bh 10,000
6 Timba Bh 7,000
7 Paku Wely Bh 75,000
8 Gergaji Pipa Bh 35,000

Dibuat Oleh
Satlak Pamsimas

……………………………………………………………
PROGRAM PAMSIMAS (PENYEDIAAN AIR MINUM & SANITASI BERBASIS MASYARAKAT)
HIBAH INSETIF DESA (HID)
TAHUN ANGGARAN 2019

RENCANA ANGGARAN BIAYA (RAB)

Dusun : Dusun Saribaru, Dusun 5 SP1, Dusun Tangga & dusun Tangga II Pekerjaan / Kegiatan : Sarana Air Minum
Desa : UPT SP1 No. RAB : 02
Kecamatan : Wonosari Sub Pekerjaan : Rehab Bak
Kabupaten : Boalemo Volume : 1 unit

VOLUME Biaya (Rp)


Kontribusi Harga Satuan
NO URAIAN SAT Kontribusi Masyarakat
Total Masyarakat APBN (Rp.) Total APBN
In Cash In Kind In Cash In Kind
1 2 3 4 5 7 8 9 10 (3x9) 11 (4x9) 12 (5x9) 14 (7x9)
I BAHAN
1 Tangga Bak 1.00 - - 1.00 Ls 2,000,000 2,000,000 - - 2,000,000
2 Cat Tembok 1.00 - - 1.00 Kaleng 100,000 100,000 - - 100,000
3 Semen Portland 2.00 - - 2.00 Zak 84,000 168,000 - - 168,000
4 Pasir Pasang 1.00 - - 1.00 M³ 120,000 120,000 - - 120,000
5 Masker 2.00 - - 2.00 Buah 10,000 20,000 - - 20,000
6 Handscoon 1.00 - - 1.00 Buah 15,000 15,000 - - 15,000
Sub total I : 2,423,000 - - 2,423,000
II ALAT

Sub Total II : - - - -
III UPAH
1 Pekerja 1.00 - - 1.00 Hok 85,000 85,000 - - 85,000
- - - - - - - - - -
Sub Total III : 85,000 - - 85,000
Jumlah Total : 2,508,000 - - 2,508,000

UPT SP1, 2020

Mengetahui Disetujui Diperiksa Oleh Dibuat Oleh


Ketua DPMU Koordinator Kabupaten Fasilitator Masyarakat Satlak Pamsimas

Azlan Ayub Triono Saido, ST. Andalucia Nurdin Chatriani Asta Pauweni, ST ………………………………….
NIP. 19800727 200604 1 023 DC FM - WSS KETUA SATLAK