Harga Satuan
No. Uraian Satuan Ket.
(Rp.)
1 2 3 4 5
II HARGA BAHAN
A. BAHAN PASANGAN
1 Pasir beton M3 77,000.00
2 Pasir pasang M3 77,000.00
3 Pasir urug M3 75,000.00
4 Kerikil M3 330,000.00
5 Tanah urug biasa M3 50,000.00
6 Tanah urug pilihan M3 60,000.00
7 Semen PC ( 50 Kg ) Zak 72,000.00
8 Semen putih Zak 104,000.00
9 Semen warna Kg 12,000.00
10 Air Ltr 52.50
B. BAHAN PONDASI
1 Batu kali/batu belah/batu gunung M3 287,000.00
2 Split 2/3 & 3/4 M3 300,000.00
C. BAHAN LANTAI
1 Keramik 30x30 cm polos Ktk 46,000.00
2 Keramik 30x30 cm motif/warna Ktk 55,000.00
3 Keramik 30x30 cm anti slip / motif kulit jeruk Ktk 57,000.00
4 Keramik 10x20 cm warna Ktk 52,000.00
5 Keramik 20x20 cm polos Ktk 54,000.00
6 Keramik 20x20 cm warna Ktk 57,000.00
7 Keramik 20x25 cm polos Ktk 54,000.00
8 Keramik 20x25 cm warna Ktk 65,000.00
9 Keramik 40x40 cm motif Ktk 97,000.00
10 Keramik 40x40 cm polos Ktk 79,000.00
11 Keramik 10 x 40 cm polos Bh 3,000.00
12 Cincin Keramik M1 8,000.00
D. BAHAN DINDING
1 Batu bata kecil Bh 600.00
2 Batu bata kecil M3 441,000.00
3 Batu bata bolong besar Bh 740.00
4 Batu Tempel Andesit M2 175,000.00
G. BAHAN KAYU
1 Kayu balok klas I M3 6,000,000.00
2 Kayu balok klas II M3 1,800,000.00
3 Kayu reng klas II M3 1,800,000.00
4 Kayu balok klas III M3 1,600,000.00
5 Kayu papan klas I ( lisplank ) M3 8,400,000.00
6 Kayu papan klas I M3 5,750,000.00
7 Kayu papan tembesu M3 12,000,000.00
8 Kayu papan lambesering klas II M3 2,400,000.00
9 Kayu papan klas II M3 1,950,000.00
10 Kayu papan klas III M3 1,600,000.00
11 Kayu papan klas IV M3 1,500,000.00
12 Dolken kayu Ø 8-10/400 Cm Btg 8,000.00
13 Kayu gelam Ø 12/400 Cm Btg 20,000.00
14 Formtie/penjaga jarak bekisting/spacer Btg 5,750.00
15 Lis propil M1 4,500.00
K BAHAN FINISHING
1 Cat besi Kg 54,000.00
2 Cat genteng Kg 31,000.00
3 Cat tembok Kg 25,000.00
4 Cat kayu Kg 44,800.00
5 Cat dasar tembok Kg 22,000.00
6 Cat dasar kayu Kg 34,000.00
7 Minyak cat Ltr 12,000.00
8 Minyak bekisting Ltr 12,500.00
9 Dempul kayu Kg 20,000.00
10 Meni Kg 52,000.00
11 Plamir tembok Kg 8,200.00
12 Ter/residu Ltr 6,900.00
13 Plitur Ltr 55,000.00
14 Tiner Ltr 23,000.00
15 Lem aibon Kg 38,000.00
16 Lem vinyl Kg 38,000.00
Harga Satuan
No. Uraian Satuan Ket.
(Rp.)
1 2 3 4 5
17 Amplas Lbr 6,000.00
18 Lem kayu ( fox ) Kg 18,000.00
19 Sabun Kg 25,000.00
20 Kuas Bh 28,000.00
L BAHAN LAIN-LAIN
1 Kaca bening 5 mm M2 138,000.00
2 Kaca rayban 5 mm M2 90,000.00
3 Kaca biru 5 mm M2 110,000.00
4 Kaca Cermin, Tebal 5 mm M2 85,000.00
5 Kaca "Wireglass", Tebal 5 mm M2 98,000.00
6 Pintu kamar mandi PVC Bh 240,000.00
7 Kunci pintu 2 slaag kualitas Bh 190,000.00
8 Kunci pintu 2 slaag biasa Bh 95,000.00
9 Kunci Silinder Bh 52,000.00
10 Kunci selot Bh 42,000.00
11 Engsel pintu Bh 14,300.00
12 Engsel jendela Bh 9,000.00
13 Tarikan pintu Bh 115,000.00
14 Hak angin Bh 7,000.00
15 Tarikan jendela Bh 6,000.00
16 Grendel pintu Bh 11,500.00
17 Grendel jendela Bh 6,000.00
18 Kunci lemari Bh 11,500.00
19 Sealent Kg 15,500.00
20 Pompa air Bh 400,000.00
21 Papan nama proyek Unit 200,000.00
22 Barak kerja Unit 3,000,000.00
23 Sewa barak kerja Unit 750,000.00
24 Huruf Stainless Tinggi 20 cm Hrf 198,000.00
25 Logo Fiber Uk. 70 x 70 cm M2 780,000.00
Jambi, 2014
Konsultan Perencana
PT. MULT STRUKTUR AROYA
ILKI REPELITA, ST
Team Leader
sdn 150 - - -
sdn 26 -
1,800.00
- -
- -
630.00 550.00 82.50 630.00 632.50 660.00
441,000.00 - 441,000.00 - 463,000.00
740.00 650.00 97.50 740.00 747.50 775.00
- -
- -
66,000.00 58,000.00 8,700.00 66,000.00 66,700.00 69,000.00
51,000.00 43,000.00 6,450.00 51,000.00 49,450.00 53,500.00
110,000.00 80,000.00 12,000.00 110,000.00 92,000.00 115,000.00
150,000.00 120,000.00 18,000.00 150,000.00 138,000.00 157,000.00
64,000.00 58,000.00 8,700.00 66,000.00 66,700.00 69,000.00
132,000.00 50,000.00 7,500.00 58,000.00 57,500.00 61,000.00
280,000.00 65,000.00 9,750.00 75,000.00 74,750.00 79,000.00
95,000.00 77,000.00 11,550.00 95,000.00 88,550.00 99,000.00
17,250.00 15,000.00 2,250.00 17,250.00 17,250.00 18,100.00
2012 Rata-2 TOKO 15% dekat final DEKAT
- -
65,000.00 54,000.00 8,100.00 65,000.00 62,100.00 68,250.00
82,000.00 71,300.00 10,695.00 82,000.00 81,995.00 86,100.00
5,500.00 - 5,500.00 - 5,750.00
5,750.00 5,000.00 750.00 5,750.00 5,750.00 6,000.00
60,000.00 42,000.00 6,300.00 48,000.00 48,300.00 50,000.00
18,000.00 - 18,000.00 - 18,900.00
750,000.00 630,000.00 94,500.00 750,000.00 724,500.00 787,000.00
870,000.00 730,000.00 109,500.00 870,000.00 839,500.00 913,000.00
1,150,000.00 960,000.00 144,000.00 1,150,000.00 1,104,000.00 1,207,000.00
- -
- -
5,750,000.00 5,500,000.00 825,000.00 6,300,000.00 6,325,000.00 6,600,000.00
1,950,000.00 1,700,000.00 255,000.00 1,950,000.00 1,955,000.00 2,000,000.00
2,500,000.00 - 2,500,000.00 - 2,625,000.00
1,600,000.00 1,400,000.00 210,000.00 1,600,000.00 1,610,000.00 1,680,000.00
8,400,000.00 7,200,000.00 1,080,000.00 8,400,000.00 8,280,000.00 8,820,000.00
5,750,000.00 5,500,000.00 825,000.00 5,750,000.00 6,325,000.00 6,025,000.00
5,290,000.00 4,600,000.00 690,000.00 5,290,000.00 5,290,000.00 5,550,000.00
2,400,000.00 - 2,400,000.00 - 2,520,000.00
1,950,000.00 1,700,000.00 255,000.00 1,950,000.00 1,955,000.00 2,000,000.00
1,600,000.00 1,400,000.00 210,000.00 1,600,000.00 1,610,000.00 1,680,000.00
1,500,000.00 1,300,000.00 195,000.00 1,500,000.00 1,495,000.00 1,575,000.00
5,750.00 5,000.00 750.00 5,750.00 5,750.00 6,000.00
20,000.00 18,000.00 2,700.00 20,000.00 20,700.00 21,000.00
5,750.00 5,000.00 750.00 5,750.00 5,750.00 6,000.00
4,500.00 4,000.00 600.00 4,500.00 4,600.00 4,700.00
- -
14,375.00 12,500.00 1,875.00 14,375.00 14,375.00 15,100.00
13,800.00 12,000.00 1,800.00 13,800.00 13,800.00 14,500.00
18,500.00 16,000.00 2,400.00 18,500.00 18,400.00 19,425.00
18,000.00 - 18,000.00 - 18,900.00
18,000.00 - 18,000.00 - 18,900.00
5,750.00 6,000.00 900.00 6,900.00 6,900.00 7,250.00
11,500.00 - 11,500.00 - 12,075.00
18,000.00 - 18,000.00 - 18,900.00
184,000.00 145,000.00 21,750.00 165,000.00 166,750.00 173,000.00
16,750.00 14,500.00 2,175.00 16,750.00 16,675.00 17,550.00
21,500.00 18,000.00 2,700.00 21,500.00 20,700.00 22,500.00
23,000.00 - 23,000.00 - 24,150.00
23,000.00 20,000.00 3,000.00 23,000.00 23,000.00 24,000.00
22,000.00 20,000.00 3,000.00 23,000.00 23,000.00 24,000.00
23,000.00 20,000.00 3,000.00 23,000.00 23,000.00 24,150.00
23,000.00 - 23,000.00 - 24,150.00
23,000.00 20,000.00 3,000.00 23,000.00 23,000.00 24,150.00
4,800.00 5,000.00 750.00 5,700.00 5,750.00 6,000.00
7,200.00 6,500.00 975.00 7,500.00 7,475.00 7,900.00
132,000.00 - 13,800.00 - 14,500.00
13,800.00 - 13,800.00 - 14,500.00
575,000.00 500,000.00 75,000.00 575,000.00 575,000.00 603,000.00
175,000.00 150,000.00 22,500.00 175,000.00 172,500.00 183,000.00
- -
- -
- -
- -
75,000.00 - 75,000.00 - 78,500.00
115,000.00 - 115,000.00 - 120,000.00
18,000.00 15,000.00 2,250.00 18,000.00 17,250.00 18,900.00
20,000.00 18,000.00 2,700.00 20,000.00 20,700.00 21,000.00
26,000.00 22,000.00 3,300.00 26,000.00 25,300.00 27,700.00
19,000.00 16,000.00 2,400.00 19,000.00 18,400.00 20,150.00
50,000.00 45,000.00 6,750.00 50,000.00 51,750.00 52,500.00
55,000.00 50,000.00 7,500.00 55,000.00 57,500.00 57,500.00
- -
- -
45,000.00 47,000.00 7,050.00 54,000.00 54,050.00 57,000.00
31,000.00 26,000.00 3,900.00 31,000.00 29,900.00 32,500.00
17,800.00 20,000.00 3,000.00 23,000.00 23,000.00 24,000.00
45,000.00 47,000.00 7,050.00 54,000.00 54,050.00 56,000.00
19,000.00 16,000.00 2,400.00 19,000.00 18,400.00 20,000.00
19,000.00 30,000.00 4,500.00 34,000.00 34,500.00 35,500.00
11,500.00 10,000.00 1,500.00 11,500.00 11,500.00 12,000.00
8,600.00 - 8,600.00 - 9,000.00
18,400.00 17,000.00 2,550.00 19,000.00 19,550.00 20,000.00
18,400.00 16,000.00 2,400.00 19,000.00 18,400.00 19,300.00
8,200.00 7,000.00 1,050.00 8,200.00 8,050.00 8,600.00
10,300.00 9,000.00 1,350.00 10,300.00 10,350.00 10,800.00
42,000.00 48,000.00 7,200.00 55,000.00 55,200.00 57,000.00
18,400.00 20,000.00 3,000.00 23,000.00 23,000.00 24,000.00
38,000.00 31,000.00 4,650.00 38,000.00 35,650.00 39,900.00
38,000.00 - 38,000.00 - 39,900.00
2012 Rata-2 TOKO 15% dekat final DEKAT
- -
97,000.00 - 97,000.00 - 101,800.00
90,000.00 - 90,000.00 - 94,500.00
110,000.00 - 110,000.00 - 115,500.00
85,000.00 71,000.00 10,650.00 85,000.00 81,650.00 89,250.00
98,000.00 82,000.00 12,300.00 98,000.00 94,300.00 102,500.00
240,000.00 210,000.00 31,500.00 240,000.00 241,500.00 252,000.00
190,000.00 160,000.00 24,000.00 190,000.00 184,000.00 200,000.00
90,000.00 80,000.00 12,000.00 95,000.00 92,000.00 100,000.00
42,000.00 45,000.00 6,750.00 52,000.00 51,750.00 54,500.00
42,000.00 35,000.00 5,250.00 42,000.00 40,250.00 44,100.00
12,000.00 12,500.00 1,875.00 14,300.00 14,375.00 15,000.00
9,000.00 7,500.00 1,125.00 9,000.00 8,625.00 9,450.00
9,000.00 100,000.00 15,000.00 115,000.00 115,000.00 120,000.00
5,000.00 6,000.00 900.00 7,000.00 6,900.00 7,350.00
6,000.00 5,000.00 750.00 6,000.00 5,750.00 6,300.00
9,000.00 10,000.00 1,500.00 11,500.00 11,500.00 12,000.00
6,000.00 5,000.00 750.00 6,000.00 5,750.00 6,300.00
9,500.00 10,000.00 1,500.00 11,500.00 11,500.00 12,000.00
15,500.00 13,000.00 1,950.00 15,500.00 14,950.00 16,000.00
400,000.00 335,000.00 50,250.00 400,000.00 385,250.00 420,000.00
200,000.00 - 200,000.00 - 210,000.00
1,500,000.00 - 1,500,000.00 - 1,575,000.00
750,000.00 - 750,000.00 - 800,000.00
0.16
4,687,500.00
750,000.00
120,000.00
0.24
750,000.00
0.6864 1.45687645688
SEDANG JAUH
0.16
6.25
79062.5
0.16
94,500.00 99,000.00 99,000.00 6.25 79062.5
94,500.00 99,000.00 99,000.00
84,000.00 88,000.00 88,000.00
330,750.00 347,000.00 346,500.00
48,300.00 51,000.00 50,600.00
59,850.00 63,000.00 62,700.00
77,700.00 82,000.00 81,400.00
109,200.00 115,000.00 114,400.00
12,600.00 13,200.00 13,200.00
55.13 57.50 57.75
- -
- -
301,350.00 316,000.00 315,700.00
315,000.00 330,000.00 330,000.00
- -
- -
48,300.00 51,000.00 50,600.00
57,750.00 60,000.00 60,500.00
59,850.00 63,000.00 62,700.00
54,600.00 58,000.00 57,200.00
56,700.00 60,000.00 59,400.00
59,850.00 63,000.00 62,700.00
56,700.00 60,000.00 59,400.00
59,850.00 63,000.00 62,700.00
66,150.00 70,000.00 69,300.00
59,850.00 63,000.00 62,700.00
- -
- -
661.50 700.00 693.00
463,050.00 485,000.00 485,100.00
777.00 815.00 814.00
- -
- -
69,300.00 73,000.00 72,600.00
53,550.00 56,500.00 56,100.00
115,500.00 121,000.00 121,000.00
157,500.00 165,000.00 165,000.00
69,300.00 73,000.00 72,600.00
60,900.00 64,000.00 63,800.00
78,750.00 83,000.00 82,500.00
99,750.00 105,000.00 104,500.00
18,112.50 19,000.00 18,975.00
SEDANG JAUH
- -
68,250.00 72,000.00 71,500.00
86,100.00 90,500.00 90,200.00
5,775.00 6,100.00 6,050.00
6,037.50 6,400.00 6,325.00
50,400.00 53,000.00 52,800.00
18,900.00 20,000.00 19,800.00
787,500.00 825,000.00 825,000.00
913,500.00 960,000.00 957,000.00
1,207,500.00 1,265,000.00 1,265,000.00 897000
- -
- -
6,615,000.00 6,930,000.00 6,930,000.00
2,047,500.00 2,145,000.00 2,145,000.00
2,625,000.00 2,750,000.00 2,750,000.00
1,680,000.00 1,760,000.00 1,760,000.00
8,820,000.00 9,240,000.00 9,240,000.00
6,037,500.00 6,325,000.00 6,325,000.00
5,554,500.00 5,820,000.00 5,819,000.00
2,520,000.00 2,640,000.00 2,640,000.00
2,047,500.00 2,145,000.00 2,145,000.00
1,680,000.00 1,760,000.00 1,760,000.00
1,575,000.00 1,650,000.00 1,650,000.00
6,037.50 6,500.00 6,325.00
21,000.00 22,000.00 22,000.00
6,037.50 6,350.00 6,325.00
4,725.00 4,950.00 4,950.00
- -
15,093.75 15,850.00 15,812.50
14,490.00 15,200.00 15,180.00
19,425.00 20,350.00 20,350.00
18,900.00 19,800.00 19,800.00
18,900.00 19,800.00 19,800.00
7,245.00 7,590.00 7,590.00
12,075.00 12,650.00 12,650.00
18,900.00 19,800.00 19,800.00
173,250.00 181,500.00 181,500.00
17,587.50 18,500.00 18,425.00
22,575.00 24,000.00 23,650.00
24,150.00 25,500.00 25,300.00
24,150.00 25,500.00 25,300.00
24,150.00 25,500.00 25,300.00
24,150.00 25,500.00 25,300.00
24,150.00 25,500.00 25,300.00
24,150.00 25,500.00 25,300.00
5,985.00 6,300.00 6,270.00
7,875.00 8,250.00 8,250.00
14,490.00 15,200.00 15,180.00
14,490.00 15,200.00 15,180.00
603,750.00 633,000.00 632,500.00
183,750.00 193,000.00 192,500.00
- -
- -
- -
- -
78,750.00 83,000.00 82,500.00
120,750.00 127,000.00 126,500.00
18,900.00 20,000.00 19,800.00
21,000.00 22,000.00 22,000.00
27,300.00 29,000.00 28,600.00
19,950.00 21,000.00 20,900.00
52,500.00 55,000.00 55,000.00
57,750.00 61,000.00 60,500.00
- -
- -
56,700.00 60,000.00 59,400.00
32,550.00 34,000.00 34,100.00
24,150.00 25,300.00 25,300.00
56,700.00 60,000.00 59,400.00
19,950.00 21,000.00 20,900.00
35,700.00 37,500.00 37,400.00
12,075.00 12,700.00 12,650.00
9,030.00 9,500.00 9,460.00
19,950.00 21,000.00 20,900.00
19,950.00 21,000.00 20,900.00
8,610.00 9,050.00 9,020.00
10,815.00 11,350.00 11,330.00
57,750.00 60,500.00 60,500.00
24,150.00 25,300.00 25,300.00
39,900.00 42,000.00 41,800.00
39,900.00 42,000.00 41,800.00
SEDANG JAUH
- -
101,850.00 107,000.00 106,700.00
94,500.00 99,000.00 99,000.00
115,500.00 121,000.00 121,000.00
89,250.00 94,000.00 93,500.00
102,900.00 108,000.00 107,800.00
252,000.00 264,000.00 264,000.00
199,500.00 210,000.00 209,000.00
99,750.00 105,000.00 104,500.00
54,600.00 58,000.00 57,200.00
44,100.00 56,500.00 46,200.00
15,015.00 15,750.00 15,730.00
9,450.00 9,900.00 9,900.00
120,750.00 127,000.00 126,500.00
7,350.00 7,700.00 7,700.00
6,300.00 6,600.00 6,600.00
12,075.00 12,650.00 12,650.00
6,300.00 6,600.00 6,600.00
12,075.00 12,650.00 12,650.00
16,275.00 17,050.00 17,050.00
420,000.00 440,000.00 440,000.00
210,000.00 220,000.00 220,000.00
1,575,000.00 1,650,000.00 1,650,000.00
787,500.00 825,000.00 825,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN : 2014
L O K A S I : KOTA JAMBI
Harga Satuan
Kebutuhan Satuan Indeks Bahan/Upah Jumlah (Rp)
(Rp)
2 3 4 5 6
PEKERJAAN PERSIAPAN
PEKERJAAN TANAH
PEKERJAAN PONDASI
PEKERJAAN BETON
PEKERJAAN DINDING
PEKERJAAN PLESTERAN
PEKERJAAN KAYU
PEKERJAAN LANGIT-LANGIT
PEKERJAAN SANITAIR
PEKERJAAN PENGECATAN
JUMLAH
NO SATUAN NAMA ANALISA
HARGA
HARGA SATUAN PEKERJAAN PERSIAPAN
1 1M3 MEMBUAT BETON MUTU f'c = 7,4 Mpa (K 100), SLUMP (12 + 2) cm, w/c = 0,87 Rp 1,172,990.50
2 1M3 MEMBUAT BETON MUTU f'c = 9,8 Mpa (K 125), SLUMP (12 + 2) cm, w/c = 0,78 Rp 1,222,747.17
3 1M3 MEMBUAT BETON MUTU f'c = 12,2 Mpa (K 150), SLUMP (12 + 2) cm, w/c = 0,72 Rp 1,260,770.50
4 1M3 MEMBUAT LANTAI KERJA BETON MUTU f'c = 7,4 MPa, SLUMP (3 - 6) cm, w/c = 0,87 Rp 1,083,839.17
5 1M3 MEMBUAT BETON MUTU f'c = 14,5 MPa, SLUMP (12 + 2) cm, w/c = 0,66 Rp 1,306,956.75
6 1M3 MEMBUAT BETON MUTU f'c = 16,9 Mpa (K 200), SLUMP (12 + 2) cm, w/c = 0,61 Rp 1,827,466.67
7 1M3 MEMBUAT BETON MUTU f'c = 19,3 Mpa (K 225), SLUMP (12 + 2) cm, w/c = 0,58 Rp 1,861,947.09
8 1M3 MEMBUAT BETON MUTU f'c = 21,7 Mpa (K 250), SLUMP (12 + 2) cm, w/c = 0,56 (Ready Mix Mobile) Rp 1,402,555.92
9 1M3 MEMBUAT 1 M3 BETON MUTU fc' 26,4 MPa (K-300) Rp 1,995,084.67
10 1M3 MEMBUAT BETON MUTU f'c = 26,4 Mpa (K 300), SLUMP (12 + 2) cm, w/c = 0,52 Rp 1,555,084.67
11 1M3 MEMBUAT BETON MUTU f'c = 28,8 Mpa (K 325), SLUMP (12 + 2) cm, w/c = 0,49 Rp 1,553,896.67
12 1M3 MEMBUAT BETON MUTU f'c = 30 MPa, SLUMP (12 + 2) cm, w/c = 0,48 Rp 2,117,000.42
13 Err:509 Err:509 Err:509
14 Err:509 Err:509 Err:509
15 Err:509 Err:509 Err:509
16 Err:509 Err:509 Err:509
17 Err:509 Err:509 Err:509
18 Err:509 Err:509 Err:509
19 10 Kg MEMASANG JARING KAWAT BAJA / WIRE MESH Rp 137,086.66
20 1M2 MEMASANG BEKISTING UNTUK PONDASI Rp 208,369.33
21 1M2 MEMASANG BEKISTING UNTUK SLOOF Rp 219,369.33
22 1M2 PASANG BEKISTING UNTUK KOLOM Rp 352,482.17
23 1M2 PASANG BEKISTING UNTUK BALOK Rp 362,382.17
24 1M2 PASANG BEKISTING UNTUK LANTAI Rp 378,882.17
25 1M2 PASANG BEKISTING UNTUK DINDING Rp 379,982.17
26 1M2 PASANG BEKISTING UNTUK TANGGA Rp 328,823.00
27 1M2 PASANG JEMBATAN COR Rp 101,123.00
28 1M3 MEMBUAT PONDASI BETON BERTULANG (150 Kg BESI + BEGISTING) Rp 5,428,219.14
29 1M3 MEMBUAT SLOOF BETON BERTULANG (136 Kg BESI + BEGISTING) Rp 5,282,209.93
30 Err:509 Err:509 Err:509
31 1M3 MEMBUAT KOLOM BETON BERTULANG (130 Kg BESI + BEGISTING) Rp 7,162,228.27
32 Err:509 Err:509 Err:509
33 Err:509 Err:509 Err:509
34 1M3 MEMBUAT BALOK BETON BERTULANG (160 Kg BESI + BEGISTING) Rp 7,104,013.52
35 Err:509 Err:509 Err:509
36 Err:509 Err:509 Err:509
37 Err:509 Err:509 Err:509
38 Err:509 Err:509 Err:509
39 Err:509 Err:509 Err:509
40 Err:509 Err:509 Err:509
41 1M3 MEMBUAT DINDING BETON BERTULANG (150 Kg BESI + BEGISTING) Rp 6,633,923.86
42 Err:509 Err:509 Err:509
43 1M' MEMBUAT KOLOM PRAKTIS BETON BERTULANG (11 X 11) CM Rp 110,999.58
44 1M' MEMBUAT RING BALOK BETON BERTULANG (13 X 20) CM Rp 143,135.25
45 1M3 MEMBUAT PLAT BETON BERTULANG ( 150 Kg BESI + BEKISTING ) Rp 6,722,974.14
Err:509
1 1M3 Membuat dan Memasang Kusen Pintu dan Jendela, Kayu Kelas I Rp 11,183,865.00
2 1M3 Membuat dan Memasang Kusen Pintu dan Kusen Jendela, Kayu Kelas II atau III Rp 7,848,940.00
3 1M2 Membuat dan Memasang Pintu Klamp Standar, Kayu Kelas II Rp 357,038.00
4 1M2 Membuat dan Memasang Pintu Klamp Sederhana, Kayu Kelas III Rp 313,038.00
5 1M2 Membuat dan memasang Daun Pintu Panel, Kayu Kelas I atau II Rp 784,245.00
6 1M2 Membuat dan Memasang Pintu dan Jendela Kaca, Kayu Kelas I atau II Rp 664,532.00
7 1M2 Membuat dan Memasang Pintu dan Jendela Jalusi, Kayu Kelas I atau II Rp 1,039,445.00
8 1M2 Membuat daun Pintu Plywood rangkap, rangka tertutup Kayu kelas II (lebar s/d 90 cm) Rp 616,951.50
9 1M2 Membuat Pintu Plywood rangkap, rangka Ekspose Kayu kelas I atau II Rp 753,324.00
10 1M2 Memasang Jalusi Kusen, Kayu Kelas I atau II Rp 837,787.50
11 1M2 Memasang Teakwood rangkap, rangka Ekspose Kayu kelas I Rp 783,266.00
12 1M2 Memasang Pintu Teakwood rangkap Lapis Formika, Rangka Ekspose Kayu kelas II Rp 842,066.50
13 1M3 Memasang Konstruksi Kuda - Kuda Konvensional, Kayu Kelas I, II dan III bentang 6 m Rp 10,414,580.00
14 1M3 Memasang Konstruksi Kuda - Kuda Ekspose, Kayu Kelas I Rp 12,747,377.50
15 1M3 Memasang Konstruksi Gordeng, Kayu Kelas II Rp 6,314,220.00
16 1M2 Memasang Rangka Atap Genteng Keramik Kayu Kelas II Rp 92,922.50
17 1M2 Memasang Rangka Atap Genteng Beton, Kayu Kelas II Rp 104,802.50
18 1M2 Memasang Rangka Atap Sirap, Kayu Kelas II Rp 584,331.00
19 1M2 Memasang Rangka Langit - langit (50 x 100) cm, Kayu Kelas II atau III Rp 135,217.50
20 1M2 Memasang Rangka Langit - langit (60 x 60) cm, Kayu Kelas II atau III Rp 135,575.00
21 1M' Memasang Lisplank Ukuran (3 x 20) cm, Kayu Kelas I atau II Rp 114,262.50
22 1M' Memasang Lisplank Ukuran (3 x 30) cm, Kayu Kelas I atau II Rp 114,482.50
23 1M' Memasang Lisplank GRC Lebar 20 cm Rp 126,934.50
24 1M' Memasang Lisplank GRC Lebar 8 mm Rp 98,582.00
25 1M2 Memasang Rangka Dinding Pemisah (60 x 120) cm, Kayu Kelas II atau III Rp 191,433.00
26 1M2 Memasang Dinding pemisah Teakwood Rangkap, Rangka Kayu Kelas II Rp 294,439.20
27 1M2 Memasang Dinding pemisah Plywood Rangkap, Rangka Kayu Kelas II Rp 300,440.80
28 1M2 Memasang Dinding Lambriziring dari Papan Kayu kelas I Rp 438,630.50
29 1M2 Memasang Dinding Lambriziring dari Plywood ukuran (120 x 240) cm Rp 46,689.50
Err:509
1 Err:509 Err:509
Err:509
2 Err:509 Err:509 Err:509
Err:509
3 Err:509 Err:509
Err:509
4 Err:509 Err:509 Err:509
Err:509
5 Err:509 Err:509
Err:509
6 Err:509 Err:509 Err:509
DAFTAR REKAPITULASI
NO URAIAN HARGA
1 2 3
TERBILANG ENAM RATUS DELAPAN PULUH TUJUH JUTA TIGA RATUS RIBU RUPIAH
Dibuat Oleh
II DAFTAR 2
MATA PEMBAYARAN PENYELENGGARAAN KEAMANAN DAN
KESEHATAN KERJA SERTA KESELAMATAN KONSTRUKSI
1 PENYIAPAN RKK
a Pembuatan Dokumen Rencana Keselamatan Konstruksi
b Pembuatan Prosedur dan Instruksi Kerja SET 1 300,000
c Penyiapan Formulir
SUB TOTAL PENYIAPAN RKK 300,000
5 Personel K3 Konstruksi
a Ahli K3 Konstruksi OB
b Petugas K3 Konstruksi OB
E Sub Total Personel K3
### ### #REF!
### ### #REF!
### ### #REF!
### ### #REF!
### ### #REF!
### ### #REF!
### ### #REF!
II DAFTAR 2
MATA PEMBAYARAN PENYELENGGARAAN KEAMANAN DAN
KESEHATAN KERJA SERTA KESELAMATAN KONSTRUKSI
Item Pekerjaan K3
Total Daftar 2 5,225,000.00 Disesuaikan dgn
(pindahkan nilai total ke Daftar Rekapitulasi) item dan jln pek
dilapangan
PEKERJAAN: ### PEMBANGUNAN JEMBATAN LINTASAN PIPA GAS
LOKASI : ### DESA MENDIS KECAMATAN BAYUNG LENCIR MUSI BANYUASIN SUMATERA SELATAN
TA. : ### 2023
I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran dan Pemasangan Bowplank 52.00 M1 72,088.50 3,748,602.00
2 Pek. Pembuatan Barak Kerja 1.00 Ls 3,000,000.00 3,000,000.00
3 Pek. Papan Nama Proyek 1.00 Ls 150,000.00 150,000.00
4 Pek. Dokumentasi dan Pelaporan 1.00 Ls 1,000,000.00 1,000,000.00
5 APD dan Kelengkapan HSE 10.00 Pax 1,500,000.00 15,000,000.00
6 Mob-Demob Material dan Tenaga Kerja 1.00 Ls 20,000,000.00 20,000,000.00
TOTAL PEKERJAAN PERSIAPAN (I) 42,898,602.00
II PEKERJAAN STRUKTUR
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Pondasi 103.40 M3 94,462.50 9,767,422.50
2 Pek. Urugan Tanah Kembali 34.47 M3 34,636.25 1,193,796.08
3 Pek. Urugan Pasir Bawah Pondasi T = 5 cm 6.75 M3 245,685.00 1,658,373.75
4 Pek. Lantai Kerja Bawah Pondasi T = 5 cm 6.75 M3 1,083,839.17 7,315,914.37
5 Pek. Timbunan Tanah dipadatkan 48.00 M3 164,175.00 7,880,400.00
6 Pek. Buis Beton Pondasi Sumuran Dia. 100 cm uk. 100x50 70.00 Bh 450,000.00 31,500,000.00
[ 7 Pek. Adukan Isi Dasar Pondasi Sumuran K-300 Tbl=50 cm 2.51 M3 1,995,084.67 5,011,652.68
8 Pek. Beton Bertulang K-300 Isi Pondasi Sumuran 15.07 M3 4,567,572.19 68,842,448.01
9 Pek. Beton Bertulang K-300 Pile Cap uk. 1,5 x 4,0 m x 0,6 m 6.75 M3 5,048,524.46 34,077,540.10
10 Pek. Pasangan Elastomer 40x20x3 cm 10.00 bh 400,000.00 4,000,000.00
11 Pek. Pondasi Batu Kali Pelat Injak 5.18 M3 1,322,928.75 6,852,770.93
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 72,088.50
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 94,462.50
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 136,999.50
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 34,636.25
DAFTAR ANALISA BAHAN DAN UPAH
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 42,380.25
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 245,685.00
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 127,985.00
1M3 Memasang PONDASI BATU KALI, Campuran 1 Pc : 3 PP
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 1,322,928.75
DAFTAR ANALISA BAHAN DAN UPAH
PEKERJAAN BETON
1M3 MEMBUAT LANTAI KERJA BETON MUTU f'c = 7,4 MPa, SLUMP (3 - 6) cm, w/c = 0,87
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 1,083,839.17
1M3 MEMBUAT BETON MUTU f'c = 14,5 MPa, SLUMP (12 + 2) cm, w/c = 0,66
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 1,306,956.75
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 1,995,084.67
1M3 MEMBUAT BETON MUTU f'c = 30 MPa, SLUMP (12 + 2) cm, w/c = 0,48
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 2,117,000.42
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 208,369.33
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 219,369.33
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 378,882.17
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 110,999.58
100 kg Pembesian dengan besi polos atau ulir untuk pembesian pelat
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 1,978,836.55
100 kg Pembesian dengan besi polos atau ulir untuk pembesian kolom / balok
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 2,301,576.55
1M3 Membuat 1 M3 Beton Bertulang Pile Cap Beton K-300, Besi 135 Kg
DAFTAR ANALISA BAHAN DAN UPAH
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 5,048,524.46
1M3 Membuat 1 M3 Beton Bertulang Balok Girder Beton K-300, Besi 268 Kg
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 8,756,188.71
1M3 Membuat 1 M3 Beton Bertulang Balok Diafragma Beton K-300, Besi 253 Kg
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 8,807,408.71
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 5,672,843.80
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 3,598,613.33
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 4,567,572.19
137,728.75
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 262,656.63
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 90,823.81
1M2 PENGECATAN TEMBOK BARU ( 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
Harga Satuan Pekerjaan (Jumlah Bahan + Upah + Overhead + Profit 10%Total >>> Rp. 35,717.00
BULAN Ke- 1 BULAN Ke-2 BULAN Ke-3 BULAN Ke-4 BULAN Ke-5 BULAN Ke-6
Bobot (%)
Minggu ke-10
Minggu ke-11
Minggu ke-12
Minggu ke-13
Minggu ke-14
Minggu ke-15
Minggu ke-16
Minggu ke-17
Minggu ke-18
Minggu ke-19
Minggu ke-20
Minggu ke-21
Minggu ke-22
Minggu ke-23
Minggu ke-24
Minggu ke-1
Minggu ke-2
Minggu ke-3
Minggu ke-4
Minggu ke-5
Minggu ke-6
Minggu ke-7
Minggu ke-8
Minggu ke-9
SKALA
Renc./
No. Uraian Kegiatan Real.
0
Rencana Bobot (%) 88.98 0.72 2.22 2.56 2.74 4.25 5.00 4.38 5.95 6.87 6.80 6.76 6.34 6.54 6.84 5.65 5.15 4.51 4.01 4.11 2.55 1.01 1.01 0.61 0.19
Akumulasi Bobot Rencana (%) 0 0.72 2.94 5.49 8.24 12.49 17.49 21.88 27.82 34.69 41.49 48.25 54.59 61.12 67.96 73.60 78.75 83.26 87.27 91.37 93.92 94.93 95.93 96.54 96.73
Bobot Realisasi (%)
Akumulasi Bobot Realisasi (%) 0 0
Deviasi (%)
JADWAL PELAKSANAAN PEKERJAAN
NAMA PEKERJAAN : PEMBANGUNAN JEMBATAN LINTASAN PIPA GAS
DURASI PEKERJAAN : 168 HARI KALENDER
BULAN Ke- 1 BULAN Ke-2 BULAN Ke-3
Bobot (%)
Minggu ke-10
Minggu ke-11
Minggu ke-12
Minggu ke-1
Minggu ke-2
Minggu ke-3
Minggu ke-4
Minggu ke-5
Minggu ke-6
Minggu ke-7
Minggu ke-8
Minggu ke-9
SKALA
Renc./
No. Uraian Kegiatan Real.
0
Rencana Bobot (%) 100.00 4.39 8.19 9.54 6.74 7.99 12.50 11.59 6.86 10.11 8.35 11.34 2.38
Akumulasi Bobot Rencana (%) 0 4.39 12.58 22.12 28.87 36.85 49.36 60.95 67.80 77.92 86.27 97.62 100.00
Bobot Realisasi (%)
Akumulasi Bobot Realisasi (%) 0 0
Deviasi (%)
DAFTAR STANDAR HARGA BARANG DAN JASA
B. BAHAN KAYU
1 Kayu Balok Kelas I Rp. 5,500,000.00 / M³
2 Kayu Balok Kelas II Rp. 3,000,000.00 / M³
3 Kayu Balok Kelas III Rp. 2,000,000.00 / M³
4 Papan Bekisting Rp. 1,800,000.00 / M³
5 Papan Kelas I Rp. 5,500,000.00 / M³
6 Papan Kelass II Rp. 3,000,000.00 / M³
7 Papan Kelass III Rp. 2,000,000.00 / M³
8 Multiplek t = 2 cm Rp. 190,600.00 / Lbr
9 Papan Mal Rp. 1,800,000.00 / M³
10 Plywood 4 mm Rp. 66,900.00 / Lbr
11 Plywood 9 mm Rp. 120,000.00 / Lbr
12 Kayu Bulat (Dolken) Rp. 6,000.00 / Btg
C. BAHAN BESI
1 Besi Beton Rp. 14,990.40 / Kg
2 Besi Strip (3/4 x 4) mm Rp. 6,600.00 / Btg
Sling Baja Dia. 16 mm Rp. 100,000.00 / M
3 Kawat beton Rp. 20,000.00 / Kg
4 Paku Beton Rp. 25,000.00 / Kg
5 Paku Biasa Rp. 18,000.00 / Kg
6 Paku GRC Rp. 28,800.00 / Kg
DAFTAR STANDAR HARGA BARANG DAN JASA
D. BAHAN FINISHING
1 Amplas Rp. 7,400.00 / Lbr
2 Cat Dasar Rp. 40,000.00 / Kg
3 Cat Kilat Rp. 65,000.00 / Kg
4 Cat Tembok (avitek-Vinilex) Rp. 40,000.00 / Kg
5 Cat Tembok Rp. 30,000.00 / Kg
6 Cat Meni Besi Rp. 68,666.67 / Kg
7 Cat Meni Kayu Rp. 36,000.00 / Kg
8 Dempul Rp. 24,500.00 / Kg
9 Lem Fox Rp. 18,300.00 / Kg
10 Lem Aibon Rp. 33,900.00 / Kg
11 Lem Kayu Rp. 22,400.00 / Kg
12 Minyak Bekisting Rp. 15,000.00 / Ltr
13 Thiner (Minyak Cat) Rp. 30,166.67 / Btl
14 Minyak Tanah (Non Subsidi) Rp. 12,700.00 / Ltr
15 Plamir @ 25 Kg Rp. / Pl
16 Plamir Rp. 20,000.00 / Kg
17 Cat Pilox Rp. 22,300.00 / Bh
18 Sirlak Rp. 165,000.00 / Kg
19 Spritus Rp. 11,500.00 / Btl
20 Kuas Rp. 16,600.00 / Bh
21 HPL - High Pressure Laminate - FORMIKA Rp. 151,200.00 / Lbr
22 Cat Propane Rp. 60,000.00 / Lbr
Pile Cap 8.1 7.95 42 bh 2 163.8
2.1 1.95 12 bh 2 190.8
8.1 7.95 1 2 15.9
371.5 408.65
6.75
223.2895 245.6184
0.38
2.631579
0.15 9 13
6.666667 22 11
229.3173 253
1.990446
129.379
4.320988
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100.00 HP
3. Kapasitas Cp 4,000.00 Liter
4. Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 185,000,000.00 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 15,860.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,290.00 Rp./Jam
4. Bahan Bakar Bensin Mb 5,500.00 Liter
5. Bahan Bakar Solar Ms 9,700.00 Liter
6. Minyak Pelumas Mp 31,600.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
No. URAIAN KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PUMP E28
2. Pw 100.00 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 185,000,000.00 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 15,860.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,290.00 Rp./Jam
4. Bahan Bakar Bensin Mb 5,500.00 Liter
5. Bahan Bakar Solar Ms 9,700.00 Liter
6. Minyak Pelumas Mp 31,600.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
No. URAIAN KODE SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PAN MIXER E43
2. Tenaga Pw 134.00 HP
3. Kapasitas Cp 600.00 Liter
4. Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.00 Jam
c. Harga Alat B 1,000,000,000.00 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 15,860.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,290.00 Rp./Jam
4. Bahan Bakar Bensin Mb 5,500.00 Liter
5. Bahan Bakar Solar Ms 9,700.00 Liter
6. Minyak Pelumas Mp 31,600.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TRUK MIXER (AGITATOR) E49
2. Tenaga Pw 220.00 HP
3. Kapasitas Cp 5.00 M3
4. Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,500.00 Jam
c. Harga Alat B 750,000,000.00 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 75,000,000.00 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 15,860.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,290.00 Rp./Jam
4. Bahan Bakar Bensin Mb 5,500.00 Liter
5. Bahan Bakar Solar Ms 9,700.00 Liter
6. Minyak Pelumas Mp 31,600.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
pembesian sloof 20/30
Pondasi
jlh dlm 1 m3 uk 60/60 11.11
160.00 8 168.00
160.00 8 168.00