HARGA UPAH TENAGA KERJA DAN BAHAN

HARGA
NO TENAGA KERJA / MATERIAL SATUAN (Rp)

A. UPAH
1 Mandor Org/hari 95,000.00
2 Kepala Tukang Org/hari 83,800.00
3 Tukang Org/hari 64,800.00
4 Pekerja Org/hari 62,400.00
-
B. BAHAN PENGISI -
1 Pasir Urug M 187,700.00
4 Batu pecah 15/20 cm M 386,200.00
6 Batu pecah 1/2 cm M 683,600.00
7 Pasir M 238,700.00
8 Semen PC Zak 78,700.00
9 Semen PC Kg 1,500.00
10 Semen Warna Kg 2,500.00
10 Bataco 20 x 40 x 7 cm Bh 2,000.00
11 Keramik 20 x 20 cm Kotak 49,000.00
12 Keramik 30 x 30 cm Kotak 59,000.00
C. BAHAN KAYU -
1 Ky. klas I M 3,746,600.00
2 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M 2,479,700.00
3 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam ) M 2,479,700.00
4 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) M 1,954,400.00
5 Ky klas III uk. 4/6 - 4 M ( tdk ketam) M 1,954,400.00
6 Papan kayu klas II (mabang) tdk ketam M 2,556,900.00
7 Papan kayu klas II (mabang) ketam M 2,634,200.00
8 Papan kayu klas I tdk ketam M 3,553,500.00
9 Papan kayu klas I ketam M 3,630,700.00
10 Papan mal klas III M 1,492,400.00
11 Kayu cerucuk /dolken 6 - 8 - Pj. 4 M Btg 7,600.00
12 Kayu cerucuk /dolken 10 - Pj. 4 M Btg 9,200.00
-
D. BAHAN CAT -
1 Amplas Lbr 1,900.00
2 Cat dasar kayu Kg 21,700.00
3 Cat dasar tembok Kg 21,700.00
4 Cat kilat Kg 46,600.00
5 Cat tembok Kg 14,600.00
6 Dempul kayu Kg 14,200.00
7 Dempul tembok Kg 14,200.00
8 Plamur Kg 12,400.00
9 Thiner Ltr 6,300.00
10 Meni Kg 21,700.00
11 Kuas 4" Bh 9,200.00
-
E. BAHAN KAWAT DAN PAKU -
1 Besi Tulangan Beton Kg 15,200.00
2 Kawat baja/bendrat Kg 15,200.00
7 Besi Strip T.5mm Kg 15,200.00
4 Paku Seng Kg 21,600.00
5 Paku campuran 1" - 5 " Kg 15,800.00
7 Paku Atap Seng Kg 19,300.00
8 Paku triplek Kg 16,900.00
9 Paku GRC Kg 19,300.00
-
F. BAHAN ATAP -
1 Genteng Metal 0.25 Lbr 37,400.00
2 Metal Plat 0.30 Lbr 45,100.00
-
G. BAHAN TRIPLEK -
1 Panel GRC 120 x 240 x 4mm Lbr 61,000.00
2 Multiplek 9 mm Lbr 137,600.00
ANALISA HARGA SATUAN PEKERJAAN

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.750 62,400.00 46,800.00
2 Mandor L.04 OH 0.025 95,000.00 2,375.00
JUMLAH TENAGA KERJA 49,175.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 49,175.00
E Overhead & Profit (Contoh 15 %) 15% x D 7,376.25
F Harga Satuan Pekerjaan (D+E) 56,551.25

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


Pengurugan kembali 1 m galian dihitung dari 1/3 kali dari koefisien pekerjaan galian

Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.250 62,400.00 15,600.00
2 Mandor L.04 OH 0.008 95,000.00 760.00
JUMLAH TENAGA KERJA 16,360.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 16,360.00
E Overhead & Profit (Contoh 15 %) 15% x D 2,454.00
F Harga Satuan Pekerjaan (D+E) 18,814.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.300 62,400.00 18,720.00
2 Mandor L.04 OH 0.001 95,000.00 95.00
JUMLAH TENAGA KERJA 18,815.00
B BAHAN
Pasir 1.250 187,700.00 234,625.00
JUMLAH HARGA BAHAN 234,625.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 253,440.00
E Overhead & Profit (Contoh 15 %) 15% x D 38,016.00
F Harga Satuan Pekerjaan (D+E) 291,456.00

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 1.500 62,400.00 93,600.00
2 Tukang L.02 OH 0.750 64,800.00 48,600.00
3 Kepala Tukang L.03 OH 0.075 83,800.00 6,285.00
4 Mandor L.04 OH 0.075 95,000.00 7,125.00
JUMLAH TENAGA KERJA 155,610.00
B BAHAN
1 Batu belah M3 1.200 386,200.00 463,440.00
2 Semen Portlan Kg 202.000 1,500.00 303,000.00
3 Pasir Pasang M3 0.485 238,700.00 115,769.50
JUMLAH HARGA BAHAN 882,209.50
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,037,819.50
E Overhead & Profit (Contoh 15 %) 15% x D 155,672.93
F Harga Satuan Pekerjaan (D+E) 1,193,492.43
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 1.200 62,400.00 74,880.00
2 Tukang Kayu L.02 OH 0.200 64,800.00 12,960.00
3 Kepala Tukang L.03 OH 0.020 83,800.00 1,676.00
4 Mandor L.04 OH 0.060 95,000.00 5,700.00
JUMLAH TENAGA KERJA 95,216.00
B BAHAN
1 Semen Portland Kg 230.000 1,500.00 345,000.00
2 Pasir Beton Kg 893.000 170.50 152,256.50
3 Kerikil (Maks 30mm) Kg 1,027.000 506.37 520,042.37
4 Air Liter 200.000 - -
JUMLAH HARGA BAHAN 1,017,298.87
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,112,514.87
E Overhead & Profit (Contoh 15 %) 15% x D 166,877.23
F Harga Satuan Pekerjaan (D+E) 1,279,392.10
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %

A.4.1.1.5. Membuat 1 m3 beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 1.650 62,400.00 102,960.00
2 Tukang Kayu L.02 OH 0.275 64,800.00 17,820.00
3 Kepala Tukang L.03 OH 0.028 83,800.00 2,346.40
4 Mandor L.04 OH 0.083 95,000.00 7,885.00
JUMLAH TENAGA KERJA 131,011.40
B BAHAN
1 Semen Portland Kg 326.000 1,500.00 489,000.00
2 Pasir Beton Kg 760.000 170.50 129,580.00
3 Kerikil (Maks 30mm) Kg 1,029.000 506.37 521,055.11
4 Air Liter 215.000 - -
JUMLAH HARGA BAHAN 1,139,635.11
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,270,646.51
E Overhead & Profit (Contoh 15 %) 15% x D 190,596.98
F Harga Satuan Pekerjaan (D+E) 1,461,243.49

A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.070 62,400.00 4,368.00
2 Tukang Kayu L.02 OH 0.070 64,800.00 4,536.00
3 Kepala Tukang L.03 OH 0.007 83,800.00 586.60
4 Mandor L.04 OH 0.004 95,000.00 380.00
JUMLAH TENAGA KERJA 9,870.60
B BAHAN
1 Besi beton (polos/ulir) Kg 10.500 15,200.00 159,600.00
2 Kawat beton Kg 0.150 15,200.00 2,280.00
JUMLAH HARGA BAHAN 161,880.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 171,750.60
E Overhead & Profit (Contoh 15 %) 15% x D 25,762.59
F Harga Satuan Pekerjaan (D+E)/10 19,751.32

A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.520 62,400.00 32,448.00
2 Tukang Kayu L.02 OH 0.260 64,800.00 16,848.00
3 Kepala Tukang L.03 OH 0.026 83,800.00 2,178.80
4 Mandor L.04 OH 0.026 95,000.00 2,470.00
JUMLAH TENAGA KERJA 53,944.80
B BAHAN
1 Kayu kelas III M3 0.045 1,492,400.00 67,158.00
2 Paku 5 10 cm Kg 0.300 15,800.00 4,740.00
3 Minyak bekisting Liter 0.100 8,000.00 800.00
JUMLAH HARGA BAHAN 72,698.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 126,642.80
E Overhead & Profit (Contoh 15 %) 15% x D 18,996.42
F Harga Satuan Pekerjaan (D+E) 145,639.22
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.1 1 M2 Pasangan Dinding Batako 7 X 20 X 40 CM Spesi 1PC : 4 PS (SNI DT 91-0009-2007)


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.300 62,400.00 18,720.00
2 Tukang Semen L.02 OH 0.100 64,800.00 6,480.00
3 Kepala Tukang L.03 OH 0.010 83,800.00 838.00
4 Mandor L.04 OH 0.015 95,000.00 1,425.00
JUMLAH TENAGA KERJA 27,463.00
B BAHAN
1 Batako Bh 12.500 2,000.00 25,000.00
2 Pasir M3 0.039 238,700.00 9,261.56
3 Semen Kg 12.130 1,500.00 18,195.00
JUMLAH HARGA BAHAN 52,456.56
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 79,919.56


E Overhead & Profit (Contoh 15 %) 15% x D 11,987.93
F Harga Satuan Pekerjaan (D+E) 91,907.49

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.300 62,400.00 18,720.00
2 Tukang Semen L.03 OH 0.150 64,800.00 9,720.00
3 Kepala Tukang L.03 OH 0.015 83,800.00 1,257.00
4 Mandor L.04 OH 0.015 95,000.00 1,425.00
JUMLAH TENAGA KERJA 31,122.00
B BAHAN
1 Semen Portland Kg 7.776 1,500.00 11,664.00
2 Pasir M3 0.023 238,700.00 5,490.10
JUMLAH HARGA BAHAN 17,154.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,276.10


E Overhead & Profit (Contoh 15 %) 15% x D 7,241.42
F Harga Satuan Pekerjaan (D+E) 55,517.52

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.35.Pemasangan 1m lantai keramik ukuran 30cm x 30cm


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.700 62,400.00 43,680.00
2 Tukang Semen L.02 OH 0.350 64,800.00 22,680.00
3 Kepala Tukang L.03 OH 0.035 83,800.00 2,933.00
4 Mandor L.04 OH 0.035 95,000.00 3,325.00
JUMLAH TENAGA KERJA 72,618.00
B BAHAN
1 Ubin keramik Bh 11.870 5,363.64 63,666.36
2 Semen Portlan Kg 10.000 1,500.00 15,000.00
3 Pasir pasang M3 0.045 238,700.00 10,741.50
4 Semen warna Kg 1.500 2,500.00 3,750.00
JUMLAH HARGA BAHAN 93,157.86
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 165,775.86


E Overhead & Profit (Contoh 15 %) 15% x D 24,866.38
F Harga Satuan Pekerjaan (D+E) 190,642.24

A.4.4.3.50.Pemasangan 1 m2 dinding porslen 20cm x 20cm


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.900 62,400.00 56,160.00
2 Tukang Semen L.02 OH 0.450 64,800.00 29,160.00
3 Kepala Tukang L.03 OH 0.045 83,800.00 3,771.00
4 Mandor L.04 OH 0.045 95,000.00 4,275.00
JUMLAH TENAGA KERJA 93,366.00
B BAHAN
1 Porslen Bh 26.000 1,960.00 50,960.00
2 Semen Portlan Kg 9.300 1,500.00 13,950.00
3 Pasir pasang M3 0.018 238,700.00 4,296.60
4 Semen warna Kg 1.940 2,500.00 4,850.00
JUMLAH HARGA BAHAN 74,056.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 167,422.60


E Overhead & Profit (Contoh 15 %) 15% x D 25,113.39
F Harga Satuan Pekerjaan (D+E) 192,535.99
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7. Pemasangan 1 m2 langit-langit GRC board ukuran (120x240x9) mm, tebal 4 mm


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.100 62,400.00 6,240.00
2 Tukang Kayu L.02 OH 0.050 64,800.00 3,240.00
3 Kepala Tukang L.03 OH 0.005 83,800.00 419.00
4 Mandor L.04 OH 0.005 95,000.00 475.00
JUMLAH TENAGA KERJA 10,374.00
B BAHAN
1 GRC board Lembar 0.364 61,000.00 22,204.00
2 Paku tripleks Kg 0.110 16,900.00 1,859.00
JUMLAH HARGA BAHAN 24,063.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 34,437.00


E Overhead & Profit (Contoh 15 %) 15% x D 5,165.55
F Harga Satuan Pekerjaan (D+E) 39,602.55

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

1m3 Pekerjaan Rangka Badan Kayu Kelas I Uk. 7/7 (P.K. 07)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 8.000 62,400.00 499,200.00
2 Tukang Kayu L.02 OH 24.000 64,800.00 1,555,200.00
3 Kepala Tukang L.03 OH 2.400 83,800.00 201,120.00
4 Mandor L.04 OH 0.400 95,000.00 38,000.00
JUMLAH TENAGA KERJA 2,293,520.00
B BAHAN
1 Balok kayu Klas I M3 1.100 3,746,600.00 4,121,260.00
2 Paku Kg 6.000 15,800.00 94,800.00
JUMLAH HARGA BAHAN 4,216,060.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,509,580.00


E Overhead & Profit (Contoh 15 %) 15% x D 976,437.00
F Harga Satuan Pekerjaan (D+E) 7,486,017.00
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - F.27.a

A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 4.000 62,400.00 249,600.00
2 Tukang Kayu L.02 OH 12.000 64,800.00 777,600.00
3 Kepala Tukang L.03 OH 1.200 83,800.00 100,560.00
4 Mandor L.04 OH 0.120 95,000.00 11,400.00
JUMLAH TENAGA KERJA 1,139,160.00
B BAHAN
1 Balok kayu Klas II M3 1.100 2,479,700.00 2,727,670.00
2 Besi strip tebal 5mm Kg 15.000 15,200.00 228,000.00
3 Paku 12 cm Kg 5.600 15,800.00 88,480.00
JUMLAH HARGA BAHAN 3,044,150.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 4,183,310.00


E Overhead & Profit (Contoh 15 %) 15% x D 627,496.50
F Harga Satuan Pekerjaan (D+E) 4,810,806.50

1m2 Pasang Kasau + Reng Atap Genteng Metal Kayu Kelas II (P.K. 28)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.100 62,400.00 6,240.00
2 Tukang Kayu L.02 OH 0.100 64,800.00 6,480.00
3 Kepala Tukang L.03 OH 0.010 83,800.00 838.00
4 Mandor L.04 OH 0.005 95,000.00 475.00
JUMLAH TENAGA KERJA 14,033.00
B BAHAN
1 Kayu Klas II M3 0.014 1,954,400.00 27,361.60
2 Paku 5 dan 10 cm Kg 0.150 15,800.00 2,370.00
JUMLAH HARGA BAHAN 29,731.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 43,764.60


E Overhead & Profit (Contoh 15 %) 15% x D 6,564.69
F Harga Satuan Pekerjaan (D+E) 50,329.29
Acuan : ABK Bangunan Gedung dan Perumahan - 6.35
A.4.6.1.20.Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.200 62,400.00 12,480.00
2 Tukang Kayu L.02 OH 0.300 64,800.00 19,440.00
3 Kepala Tukang L.03 OH 0.030 83,800.00 2,514.00
4 Mandor L.04 OH 0.010 95,000.00 950.00
JUMLAH TENAGA KERJA 35,384.00
B BAHAN
1 Kaso-kaso 5 x 7cm M3 0.016 1,954,400.00 31,856.72
2 Paku 7 dan 10 cm Kg 0.250 15,800.00 3,950.00
JUMLAH HARGA BAHAN 35,806.72
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 71,190.72


E Overhead & Profit (Contoh 15 %) 15% x D 10,678.61
F Harga Satuan Pekerjaan (D+E) 81,869.33

A.4.6.1.21. Pemasangan 1 m lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.100 62,400.00 6,240.00
2 Tukang Kayu L.02 OH 0.200 64,800.00 12,960.00
3 Kepala Tukang L.03 OH 0.020 83,800.00 1,676.00
4 Mandor L.04 OH 0.005 95,000.00 475.00
JUMLAH TENAGA KERJA 21,351.00
B BAHAN
1 Papan kayu M3 0.011 2,634,200.00 28,449.36
2 Paku 5 dan 10 cm Kg 0.100 15,800.00 1,580.00
JUMLAH HARGA BAHAN 30,029.36
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,380.36


E Overhead & Profit (Contoh 15 %) 15% x D 7,707.05
F Harga Satuan Pekerjaan (D+E) 59,087.41

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.32. Pemasangan 1 m2 genteng metal


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.200 62,400.00 12,480.00
2 Tukang Kayu L.02 OH 0.100 64,800.00 6,480.00
3 Kepala Tukang L.03 OH 0.010 83,800.00 838.00
4 Mandor L.04 OH 0.001 95,000.00 95.00
JUMLAH TENAGA KERJA 19,893.00
B BAHAN
1 Genteng metal Lembar 1.020 37,400.00 38,148.00
2 Paku biasa "-1 Kg 0.200 15,800.00 3,160.00
JUMLAH HARGA BAHAN 41,308.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 61,201.00


E Overhead & Profit (Contoh 15 %) 15% x D 9,180.15
F Harga Satuan Pekerjaan (D+E) 70,381.15

1m1 Pekerjaan Bubungan Atap Metal 0.30 / 10m 1 (P.PA. 13.a)


Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.250 62,400.00 15,600.00
2 Tukang Kayu L.02 OH 0.250 64,800.00 16,200.00
3 Kepala Tukang L.03 OH 0.025 83,800.00 2,095.00
JUMLAH TENAGA KERJA 33,895.00
B BAHAN
1 Metal datar Lembar 6.000 45,100.00 270,600.00
2 Paku biasa "-1 Kg 0.100 15,800.00 1,580.00
3 Papan Kayu Klas II M3 0.072 2,556,900.00 184,096.80

JUMLAH HARGA BAHAN 272,180.00


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 306,075.00


E Overhead & Profit (Contoh 15 %) 15% x D 45,911.25
F Harga Satuan Pekerjaan (D+E)/10 35,198.63
Acuan : Harga Satuan Bahan, Upah dan Analisa Biaya Pekerjaan BOW - H.10
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.070 62,400.00 4,368.00
2 Tukang Cat L.02 OH 0.009 64,800.00 583.20
3 Kepala Tukang L.03 OH 0.060 83,800.00 5,028.00
4 Mandor L.04 OH 0.030 95,000.00 2,850.00
JUMLAH TENAGA KERJA 12,829.20
B BAHAN
1 Cat menie Kg 0.200 21,700.00 4,340.00
2 Plamur Kg 0.150 12,400.00 1,860.00
3 Cat dasar Kg 0.170 21,700.00 3,689.00
4 Cat penutup Kg 0.260 46,600.00 12,116.00
5 Kuas Buah 0.010 9,200.00 92.00
6 Pengencer Kg 0.020 6,300.00 126.00
7 Ampelas Lembar 0.200 1,900.00 380.00
JUMLAH HARGA BAHAN 22,603.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,432.20


E Overhead & Profit (Contoh 15 %) 15% x D 5,314.83
F Harga Satuan Pekerjaan (D+E) 40,747.03

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.020 62,400.00 1,248.00
2 Tukang Cat L.02 OH 0.063 64,800.00 4,082.40
3 Kepala Tukang L.03 OH 0.006 83,800.00 527.94
4 Mandor L.04 OH 0.003 95,000.00 285.00
JUMLAH TENAGA KERJA 6,143.34
B BAHAN
1 Plamur Kg 0.100 12,400.00 1,240.00
2 Cat dasar Kg 0.100 21,700.00 2,170.00
3 Cat penutup Kg 0.260 14,600.00 3,796.00
JUMLAH HARGA BAHAN 7,206.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,349.34


E Overhead & Profit (Contoh 15 %) 15% x D 2,002.40
F Harga Satuan Pekerjaan (D+E) 15,351.74

A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.028 62,400.00 1,747.20
2 Tukang Cat L.02 OH 0.042 64,800.00 2,721.60
3 Kepala Tukang L.03 OH 0.004 83,800.00 351.96
4 Mandor L.04 OH 0.003 95,000.00 285.00
JUMLAH TENAGA KERJA 5,105.76
B BAHAN
1 Cat dasar Kg 0.120 21,700.00 2,604.00
2 Cat penutup Kg 0.180 14,600.00 2,628.00
JUMLAH HARGA BAHAN 5,232.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 10,337.76


E Overhead & Profit (Contoh 15 %) 15% x D 1,550.66
F Harga Satuan Pekerjaan (D+E) 11,888.42

A.4.7.1.4. A .1 m2 Pengecatan bidang kayu lama ( 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No. Uraian Kode Satuan Koefesien Jumlah Harga (Rp)
(Rp)
1 2 3 4 5.000 6.00 7.00
A TENAGA
1 Pekerja L.01 OH 0.070 62,400.00 4,368.00
2 Tukang Cat L.02 OH 0.009 64,800.00 583.20
3 Kepala Tukang L.03 OH 0.060 83,800.00 5,028.00
4 Mandor L.04 OH 0.030 95,000.00 2,850.00
JUMLAH TENAGA KERJA 12,829.20
B BAHAN
1 Cat menie Kg 0.200 - -
2 Plamur Kg 0.150 - -
3 Cat dasar Kg 0.170 21,700.00 3,689.00
4 Cat penutup Kg 0.260 46,600.00 12,116.00
5 Kuas Buah 0.010 9,200.00 92.00
6 Pengencer Kg 0.020 6,300.00 126.00
7 Ampelas Lembar 0.200 1,900.00 380.00
JUMLAH HARGA BAHAN 16,403.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,232.20


E Overhead & Profit (Contoh 15 %) 15% x D 4,384.83
F Harga Satuan Pekerjaan (D+E) 33,617.03
Kontrak Awal Volume Jumlah Harga (Rp)
NO URAIAN PEKERJAAN KODE SAT Harga Satuan Kontrak Kontrak Tambah Kurang Kontrak Awal Kontrak ADD Tambah Kurang
ANALISA ( Rp. ) Awal ADD
1 2 3 4 10 6 7 8 9 10 11 12 13

XII PEKERJAAN LAIN-LAIN


1 Pasangan Batako Tutup Kolong SNI 4.4.1.1 m2 91,903.03 12.00 12.00 1,102,836.36 1,102,836.36
2 Plasteran Tutup Kolong A.4.4.2.3 m2 55,514.87 12.00 12.00 666,178.44 666,178.44
3 Gororng- Gororng Jalan Masuk + Pemasangan - Bh 748,000.00 4.00 4.00 2,992,000.00 2,992,000.00
4 Lantai Teras Belakang Cor Beton Fc 7.4 Mpa t 10 cm A.4.1.1.4 m3 1,279,187.52 0.80 0.80 1,023,350.02 1,023,350.02
5 Pekerjaan Jalan Rabat -
Galian tanah A.2.3.1.1 m3 56,551.25 1.04 1.04 58,813.32 58,813.32
Dinding penahan pasir cor beton Fc.7.4 Mpa A.4.1.1.4 m3 1,279,187.52 1.56 1.56 1,995,532.53 1,995,532.53
Bakesting A.4.1.1.21 m2 145,290.77 7.80 7.80 1,133,268.01 1,133,268.01
Urug pasir bawah Lantai A.2.3.1.11 m3 291,312.25 5.20 5.20 1,514,823.70 1,514,823.70
Cor Lantai Beton Fc. 7.4 Mpa A.4.1.1.4 m3 1,279,187.52 5.20 5.20 6,651,775.10 6,651,775.10
Plesteran camp. 1:3 , tbl = 1,5 cm A.4.4.2.3 m2 55,514.87 52.00 52.00 2,886,773.24 2,886,773.24
20,025,350.72 20,025,350.72 26,266,619.1 26,260,826.91

JUMLAH BIAYA 179.160.271.1779.160.271.17


PPN 10 % 17.916.027.1217.916.027.12
TOTAL BIAYA 197.076.298.2897.076.298.28
DIBULATKAN 197.076.000.0097.076.000.00

Menyetujui Konsultan Pengawas Pelaksana Kegiatan


Pejabat Pembuat Komitmen (PPK) CV.CITRA MULTI DIMENSI CV. BHINEKA JAYA MAKMUR

H. EKO SUSANTO, SKM.M.Kes DOSO EKO SUWANDI


NIP. 19650312 198603 1 022 Pengawas Direktur
Estimate Engineer (EE)

REKAPITULASI
RENCANA ANGGARAN BIAYA

Kegiatan : Pengadaan Sarana dan Prasarana Puskesmas


Pekerjaan : Rehabilitasi Puskesmas Pembantu
Lokasi : Ds. Sebagu Kec Teluk Keramat
Tahun Anggaran : 2015

JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp)

1 2 3

I PEKERJAAN PENDAHULUAN 1,483,000.00

II PEKERJAAN PONDASI 10,545,212.32

III PEKERJAAN STRUKTUR 15,120,000.78

IV PEKERJAAN LANTAI, DINDING DAN PLASTERAN 40,765,044.44

V PEKERJAAN RANGKA ATAP 39,116,552.82

VI PEKERJAAN PLAFOND 18,576,907.32

VII PEKERJAAN PINTU, JENDELA DAN VENTILASI 6,758,300.00

VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI 1,774,200.00

IX PEKERJAAN SANITASI 8,594,000.00

X PEKERJAAN INSTALASI LISTRIK 2,574,500.00

XI PEKERJAAN PENGECATAN 13,827,202.77

XII PEKERJAAN LAIN-LAIN 20,025,350.72

JUMLAH BIAYA 179,160,271.16


PPN 10 % 17,916,027.12
TOTAL BIAYA 197,076,298.27
DIBULATKAN 197,076,000.00

TERBILANG : Seratus Sembilan Puluh Delapan Juta Rupiah

Dibuat
Diperiksa Konsultan Perencana
Pengelola Teknis CV. SKETSA MULTIGUNA

YOELYANTO, ST ASWANDI, ST
Nip.19720124 200312 1 002 Perencana

Mengetahui Menyetujui
Kepala Dinas Kesehatan Pejabat Pembuat Komitmen (PPK)
Kabupaten Sambas

dr. I. KETUT SUKARJA H. EKO SUSANTO, SKM.M.Kes


NIP. 19651010199509.1.001 NIP. 19650312 198603 1 022
LEMBAR PERHITUNGAN
Customer : Tanggal
Project : Rehabilitasi Puskesmas Pembantu Revisi
Location : Ds. Sebagu Kec Teluk Keramat

NO Dimensi Volume Volume


Uraian Unit Satuan
ITEM Pjg Lbr Tgg / unit Total

A PEK. PENDAHULUAN
1 Pembersihan lokasi 1 30 35 1050 1050 M2
2 Pengukuran & pemasangan Bouwplank 1 25 25 50 50 M'
3 Direksi keet & gudang 1 1 Lsm

B PEK. PONDASI
1 Galian Tanah
Pondasi P1 LAJUR 1 295.00 0.80 0.50 118.00 118.00 M3
Pondasi P2 1 8.70 0.20 0.50 0.87 0.87 M3
Sub galian tanah 118.87 M3

2 Pemancangan Cerucuk dia. 8/10 - 4 M BARIS BANYAK/ BARIS


Pondasi P1 1 295.00 590.00 2.00 1180.00 1180.00 Btg
Pondasi P2 1 8.70 18.00 2.00 36.00 36.00 Btg

Sub pemancangan cerucuk dia.12-12 m 1216.00 M3

3 Urugan Pasir bawah pondasi


Pondasi P1 1 295.00 0.80 0.10 23.60 23.60 M3
Pondasi P2 1 8.70 0.20 0.10 0.17 0.17 M3

Sub Urugan pasir bwh pondasi 23.77 M3

4 Cor Lantai Kerja camp. 1:3:5 tbl= 5 cm


Pondasi P1 1 295.00 0.80 0.05 11.80 11.80 M3
Pondasi P2 1 8.70 0.20 0.05 0.09 0.09 M3
Sub cor lt kerja camp 1:3:5 11.89 M3

5 Tapak Pondasi Pas Batu


Pondasi P1
- Pas Batu Kali 1 295.00 0.55 0.80 129.80 129.80 M3

- Plasteran 1 92.00 1.00 0.50 93.00 93.00 M2


Pondasi P2
- Pas Batu Kali 1 8.70 0.20 0.50 0.87 0.87 M3

- Plasteran 1 8.70 1.00 0.25 4.85 4.85 M2

Sub Batu Kali 130.67 M3

Sub Plaster pondasi 97.85 M2

I Pek. Struktur Utama


1 Balok Sloof Lt. dasar 15/15 cm
- Cor beton camp 1:2:3 1 295.00 0.15 0.15 6.64 6.64 M3
- Tulangan Pokok dia. 12 mm - 4 btg 1 295.00 4 0.89 1047.56 1047.56 Kg
- Tulangan Sengkang dia.8 mm - 15 cm 1 0.60 1968.00 0.39 465.90 465.90 Kg
Sub pembesian sloof lt dsr 30/50 1513.46 Kg
- Bekesting 1 295.00 0.15 0.15 132.75 132.75 M2
- Plaster 1 92.00 0.08 0.15 0.23 20.7 M2

2 Kolom Lt. dasar 15/15 cm


- Cor beton camp 1:2:3 63 0.15 0.15 3.85 0.09 5.67 M3
- Tulangan Pokok dia. 12 mm - 4 btg 63 4.15 4 0.89 14.74 928.62 Kg
- Tulangan Sengkang dia. 8 mm - 15 cm 63 0.60 27.00 0.39 6.39 402.57 Kg
Sub pembesian kolom lt dasar 1331.19 Kg
- Bekesting 63 0.15 0.15 3.85 2.31 145.53 M2
- Plasteran 63 0.15 0.15 3.85 2.02 127.26 M2

Kolom Praktis 10 x 10 cm
- Cor beton camp 1:2:3 19 0.10 0.10 3.85 0.04 0.76 M3
- Tulangan Pokok dia. 10 mm -4 btg 19 4.15 4 0.62 10.23 194.37 Kg
- Tulangan Sengkang dia.6 mm - 15 cm 19 0.40 29.00 0.22 2.57 48.83 Kg
Sub pembesian kolom pondasi 243.20 Kg
- Bekesting 19 0.10 0.10 3.85 1.54 29.26 M2
- Plasteran 19 0.10 0.10 3.85 0.77 14.63 M2

3 Balok Ring 15 /15 cm


- Cor beton camp 1:2:3 1 295.00 0.15 0.15 6.64 6.64 M3
- Tulangan Pokok dia. 12 mm - 4 btg 1 295.00 4 0.89 1047.56 1047.56 Kg
- Tulangan Sengkang dia.8 mm - 15 cm 1 0.60 1968.00 0.39 465.90 465.90 Kg
Sub pembesian balok lt dsr 25/45 1513.46 Kg
- Bekesting 1 295.00 0.15 0.15 132.75 132.75 M2
- Plasteran 1 295.00 0.15 0.15 0.30 88.5 M2

II Pek. Lantai, dinding dan plesteran


1 Urugan Pasir Bawah Lantai tebal Luas
Segmen 1 1 0.55 320.00 176.00 M3
Segmen 2 1 0.55 35.50 19.53 M3
Segmen 3 1 0.55 38.50 21.18 M3
Segmen 4 1 0.55 10.00 5.50 M3

Segmen Teras 1 Un Polysed 0.50 13.50 6.75 M3


Segmen Tangga 1 Un Polysed 0.20 1.00 0.20 M3
Sub urugan pasir bwh lantai 418.50 229.15 M3

2 Cor Lantai Dasar Beton Bertulang


- Cor beton camp 1:2:3 1 418.50 - 0.10 41.85 41.85 M3
- Pembesian Wiremesh M-8 1 418.50 16.00 0.39 2641.97 2641.97 Kg

3 Pas. Batako uk. 7x15x30 cm


Segmen Vertikal 1 1 290.00 - 3.85 1116.50 1116.50 M2
Segmen Vertikal 1 0.5 7.00 - 2.50 17.50 8.75 M2
Segmen Dpn Teras keliling 1 44.50 - 0.80 35.60 35.60 M2
Luas pintu, jendela + ventilasi -1 142.29 -142.29 M2
Sub pas. Batako lt dasar 1018.56 M2

4 Plasteran Dinding camp. 1:3 tbl = 1,5 cm


Segmen 1 B"(2-5) - R(2-5) 2 - - - 1116.50 2233.00 M2
Segmen 2 R(1-2) - O(1-3) 2 - - - 8.75 17.50 M2
Segmen 3 O(1-3) - A(1-3) 2 - - - 35.60 71.20 M2
Segmen 4 A(3-7) - C(4-7) 2 - - - -142.29 -284.58 M2
Sub plasteran dinding 2037.12 M2

5 Pemasangan Keramik Lt dasar


a. Keramik lantai uk. 30x30 Polysed 1 383.50 383.50 383.50 M2
b. Keramik tangga uk. 30x30 Un polysed
- Tangga Utama 1 14.50 16.32 4.32 35.14 35.14 M2

Sub keramik tangga 35.14 M2


c. Keramik lantai uk. 20x20
- Keramik lantai km/wc 1 20.50 20.50 M2

Sub keramik lantai uk. 20x20 20.50 M2


d. Keramik dinding uk. 20x20
- Keramik dinding km/wc (bag. Dalam) 0 0.00 M2
- Keramik dinding km/wc (bag. luar) 0 0.00 M2
- Keramik dinding kamar ganti 0 0.00 M2
- Keramik dinding tempat wudhu 0 M2
Sub keramik dinding uk. 20x20 0.00 0

III Pek. Plafond


1 - Rangka Plafond
Segmen 1 1 320.00 320.00 M2
Segmen 2 1 35.50 35.50 M2
Segmen 3 1 38.50 38.50 M2
Segmen 4 1 10.00 10.00 M2
Segmen Teras Depan 1 13.50 13.50 M2
Segmen Kaki Atap 1
Sub rangka plafond 417.50 M2
2 - Penutup Plafond Gypsum board
Sub plafond gypsum 417.50 M2
3 - List Plafond cornise gypsum R. kelas Selasar
Segmen 1 B"(2-6) - R(2-6) 0 172.00 94.50 - 266.50 0.00 M'
Segmen 2 R(1-6) - O(1-6) 0 127.00 48.00 - 175.00 0.00 M'
Segmen 3 O(1-6) - A(1-7) 0 256.00 141.50 - 397.50 M'
Sub list gypsum 0.00 M'

IV Pek. Pintu, Jendela & Ventilasi


P 0 Pintu Ruang Tindakan 1 Unit
- Kusen kayu klas I 1 21.50 0.05 0.10 0.108 0.11 M3
- Pintu panel klas I ( 2 daun ) 1 Buah 1.30 2.00 2.60 2.60 M2
- Daun Jendela + kaca mati 4 Buah 1.15 0.70 0.81 3.24 M2
- Ventilasi Jalusi 6 Buah 0.70 0.60 0.42 2.52 M2
Sub Luas PJ1 8.36 M2
P U PINTU DEPAN 1 Unit
- Kusen kayu klas I 1 17.50 0.05 0.10 0.088 0.09 M3
- Pintu panel klas I ( 2 daun ) 1 Buah 1.30 2.00 2.60 2.60 M2
- Daun Jendela + kaca mati 2 Buah 1.35 0.70 0.95 1.90 M2
- Ventilasi Jalusi 1 Buah 2.90 0.60 1.74 1.74 M2
Sub Luas P1 6.24 M2
P 1 Pintu wc n ruang 4 Unit
- Kusen kayu klas I 4 8.00 0.05 0.10 0.040 0.16 M3
- Pintu panel klas I ( 1 daun ) 4 Buah 1.30 2.00 2.60 10.40 M2
- Ventilasi Jalusi 4 Buah 1.30 0.60 0.78 3.12 M2
Sub Luas P2 13.52 M2
P 2 3 Unit
- Kusen kayu klas I 3 10.00 0.05 0.10 0.050 0.15 M3
- Pintu panel klas I ( Locker ) 3 Buah 1.30 2.00 2.60 7.80 M2
- Ventilasi Jalusi 3 Buah 2.14 0.60 1.28 3.84 M2
Sub Luas P3 11.64 M2
P 3 3 Unit
- Kusen kayu klas I 3 8.50 0.05 0.10 0.043 0.13 M3
- Pintu panel klas I ( Locker ) 3 Buah 0.81 2.00 1.62 4.86 M2
- Ventilasi Jalusi 3 Buah 1.65 0.60 0.99 2.97 M2
Sub Luas P3 7.83 M2
P 4 2 Unit
- Kusen kayu klas I 2 10.50 0.05 0.10 0.053 0.11 M3
- Pintu panel klas I ( Locker ) 2 Buah 0.81 2.00 1.62 3.24 M2
- Ventilasi Jalusi 2 Buah 2.40 0.60 1.44 2.88 M2
Sub Luas P3 6.12 M2
P 5 1 Unit
- Kusen kayu klas I 1 12.50 0.05 0.10 0.063 0.06 M3
- Pintu panel klas I ( Locker ) 1 Buah 0.81 2.00 1.62 1.62 M2
- Ventilasi Jalusi 1 Buah 3.15 0.60 1.89 1.89 M2
Sub Luas P3 3.51 M2
P 6 4 Unit
- Kusen kayu klas I 4 7.00 0.05 0.10 0.035 0.14 M3
- Pintu panel klas I ( Locker ) 4 Buah 0.81 2.00 1.62 6.48 M2
- Ventilasi Jalusi 4 Buah 0.81 0.60 0.49 1.96 M2
Sub Luas P3 8.44 M2
P 7 6 Unit
- Kusen kayu klas I 6 5.00 0.05 0.10 0.025 0.15 M3
- Pintu panel klas I ( Locker ) 6 Buah 0.76 2.00 1.52 9.12 M2
- Ventilasi Jalusi 6 Buah 0.76 0.60 0.46 2.76 M2
Sub Luas P3 11.88 M2
J1 11 Unit
- Kusen kayu klas I 11 15.50 0.05 0.10 0.078 0.85 M3
- Daun Jendela + kaca 33 Buah 1.15 0.70 0.81 26.73 M2
- Ventilasi Jalusi 11 Buah 2.30 0.60 1.38 15.18 M2
Sub Luas J1 41.91 M2
J2 Jendela Kaca Mati 4 Unit
- Kusen kayu klas I 4 11.00 0.05 0.10 0.055 0.22 M3
- Daun Jendela + kaca 8 Buah 1.15 0.70 0.81 6.48 M2
- Ventilasi Jalusi 4 Buah 1.55 0.60 0.93 3.72 M2
Sub Luas J2 10.20 M2
J3 Jendela Kaca Mati 1 Unit
- Kusen kayu klas I 1 12.00 0.05 0.10 0.060 0.06 M3
Kaca mati 2 Buah 0.60 0.60 0.36 0.72 M2
- Ventilasi Jalusi 1 Buah 1.55 0.60 0.93 0.93 M2
Sub Luas J2 1.65 M2
V1 8 Unit
- Kusen kayu klas I 8 3.50 0.05 0.10 0.018 0.14 M3
- Jalusi Kayu 8 Buah 0.80 0.60 0.48 3.84 M2
Sub Luas V1 3.84 M2
V2 6 Unit
- Kusen kayu klas I 6 5.50 0.05 0.10 0.028 0.17 M3
- Ventilasi Jalusi 12 Buah 0.80 0.60 0.48 5.76 M2
Sub Luas V2 5.76 M2

V3 4 Unit
- Kusen kayu klas I 4 7.50 0.05 0.10 0.038 0.15 M3
- Ventilasi Jalusi 8 Buah 0.80 0.60 0.48 3.84 M2
Sub Luas V2 3.84 M2

Total kusen kayu klas I 2.69 M3


Total pintu panel kayu klas I 9 Buah 48.72 M2
Total Jendela Kaca Mati 4 Buah 33.93 M2
Total jendela + kaca 11 Buah M2
Total ventilasi jalusi 21 Buah 56.95 M2
142.29
V Pek. Pengunci & Penggantung
1 Engsel Pintu 4" 14 4 56.00 bh
2 Engsel Jendela 3" 44 2 88.00 bh
3 Kunci 2 slaag :
- PJ1 ( 2 daun ) 1 1 1.00 bh
- P1 ( 2 daun ) 1 1 1.00 bh
- P2 ( 1 daun ) 4 1 4.00 bh
- P3 (Pintu locker) 3 1 3.00 bh
Sub Kunci 2 slaag 9.00 bh
4 Kunci 1 slaag ( P3 km/wc ) 3 1 3.00 bh
5 Slot Pintu besar ( PJ1 + P1 ) 2 2 4.00 bh
6 Slot Pintu kecil ( P3 km/wc ) 3 1 3.00 bh
7 Slot Jendela 44 2 88.00 bh
8 Tarikan jendela 44 1 44.00 bh
9 Kait angin jendela 44 2 88.00 bh
RENCANA JADWAL KEGIATAN / S
KURVA "S"
Kegiatan : Pengadaan Sarana dan Prasarana Puskesmas
Pekerjaaan : Rehabilitasi Puskesmas Pembantu
Lokasi : Ds. Sebagu Kec Teluk Keramat
Thn Anggaran : 2015

NO. ITEM PEKERJAAN BOBOT BULAN KE-1


1 2

1 PEKERJAAN PENDAHULUAN 0.83 0.83

2 PEKERJAAN PONDASI 5.89 2.94

3 PEKERJAAN STRUKTUR 8.44 2.11

4 PEKERJAAN LANTAI, DINDING DAN PLASTERAN 22.75

5 PEKERJAAN RANGKA ATAP 21.83

6 PEKERJAAN PLAFOND 10.37

7 PEKERJAAN PINTU, JENDELA DAN VENTILASI 3.77

8 PEKERJAAN PENGGANTUNG DAN PENGUNCI 0.99

9 PEKERJAAN SANITASI 4.80

10 PEKERJAAN INSTALASI LISTRIK 1.44

11 PEKERJAAN PENGECATAN 7.72

12 PEKERJAAN LAIN-LAIN 11.18

TOTAL 100.00
Bobot Rencana Mingguan 0.83 5.05
Bobot Rencana Kumulatif 0 0.83 5.88
Bobot Realisai Kumulatif 0.00 0.00
Deviasi -0.83 -5.88
WAL KEGIATAN / SHCEDULE KERJA
KURVA "S"

BULAN KE-1 BULAN KE-2 BULAN KE-3


KETERANGAN
3 4 5 6 7 8 9 10 11 12
100%

2.94

2.11 2.11 2.11

3.79 3.79 3.79 3.79 3.79 3.79

7.28 7.27776 7.28

3.46 3.46 3.46

1.26 1.26 1.26 50%

0.99

1.60 1.60 1.60

1.44

2.57 2.57 2.57

3.73 3.73 3.73


0%

5.05 5.90 13.18 14.53 17.38 11.54 11.36 6.30 6.30 2.57
10.93 16.84 30.02 44.54 61.92 73.47 84.83 91.13 97.43 100.00
0.00 0.00 1.30 11.59 18.64 27.65 47.92 70.97 84.36 100.00
-10.93 -16.84 -28.72 -32.95 -43.28 -45.82 -36.92 -20.16 -13.07 0.00

Dibuat Oleh :
Konsultan Perencana
CV. SKETSA MULTIGUNA

ASWANDI, ST
Perencana
REKAPITULASI AHSP PERMEN No 11-PRT-M-2013
KODE ANALISA JENIS PEKERJAAN
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m
A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m galian dihitung dari 1/3 kali dari koefisien pekerjaan gali
A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu fc = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
A.4.1.1.5 Membuat 1 m3 beton mutu fc = 14,5 MPa (K 175), slump (12 2) cm, w/c = 0,66
A.4.1.1.17 Pembesian 1 kg dengan besi polos atau besi ulir
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


SNI 4.4.1.1 1 M2 Pasangan Dinding Batako 7 X 20 X 40 CM Spesi 1PC : 4 PS

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.3 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


A.4.4.3.35 Pemasangan 1m lantai keramik ukuran 30cm x 30cm
A.4.4.3.50 Pemasangan 1 m2 dinding porslen 20cm x 20cm

A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


A.4.5.1.7 Pemasangan 1 m2 langit-langit GRC board ukuran (120x240x9) mm, tebal 4 mm

A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.32 Pemasangan 1 m2 genteng metal
P.PA (13.a) Pemasangan Bumbung Metal Datar

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU


PK.07 Pembuatan Rangka Badan 1 m3 kayu kelas I
A.4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter
PK .2.8 Pemasangan 1 m2 rangka atap genteng Metal, kayu kelas II
A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
A.4.6.1.21 Pemasangan 1 m lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup
A.4.7.1.10 Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
-PRT-M-2013
HARGA SATUAN

56,551.25
18,814.00
koefisien pekerjaan galian
291,456.00

1,193,492.43

1,279,392.10
1,461,243.49
19,751.32
145,639.22
263,074.46
269,817.14

91,907.49

55,517.52

PENUTUP DINDING
190,642.24
192,535.99

39,602.55

70,381.15
35,198.63

7,486,017.00
7,087,266.00
4,810,806.50
50,329.29
81,869.33
59,087.41

40,747.03
15,351.74
11888.424
VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Engsel Pintu buah 15.00 ###
2 Engsel Jendela buah 14.00 ###
3 Kunci Pintu 2 slaag buah 8.00 ###
4 Slot Pintu Besar buah 8.00 ###
5 Slot Jendela buah 30.00 ###
6 Tarikan Jendela buah 15.00 ###
7 Kait angin jendela buah 30.00 ###

IX PEKERJAAN SANITASI
1 Instalasi Air Bersih Lsm 1.00 ###
2 Instalasi Air Kotor Lsm 1.00 ###
3 Kloset Jongkok dan Pemasangan buah 1.00 ###
7 Kran Air buah 2.00 ###
8 Floordrain buah 2.00 ###
9 Bak Air (finishing keramik) uk. 70 x 70 T 80 cm buah 1.00 ###
10 Berfoot Gorong -gorong Dia. 1 M. 2 bh Unit 1.00 ###
11 Talang Horizontal dan Pembuangan Pipa PVC dia. 4 " m 16.00 ###
12 Talang Vertikal dan Pembuangan Pipa PVC 2" m 8.00 ###
13 Bak Air Viber 1000 m3 + pipa PVC 3/4 " Bh 1.00 ###
14 Steling bak Viber Ky Belian Unit 1.00 ### Berkurang

X PEKERJAAN INSTALASI LISTRIK


1 Lampu SL 35 watt + Fitting buah 9.00 ###
2 Lampu SL 18 watt + Fitting buah 3.00 ### Berkurang
3 Saklar Double buah 3.00 ###
4 Saklar Tunggal buah 3.00 ###
5 Saklar Treple buah 1.00 ###
6 Stopkontak buah 7.00 ###
7 Instalasi Listrik + Kabel + upah + aksesoris Titik 26.00 ###

XI PEKERJAAN PENGECATAN
1 Cat Tembok Baru m2 363.10 363.10
2 Cat Tembok Lama m2 133.53 ###
3 Cat Kilat Baru m2 43.90 ### Berkurang
4 Cat Kilat Lama m2 146.85 ### Berkurang

XII PEKERJAAN LAIN-LAIN


1 Pasangan Batako Tutup Kolong m2 12.00 ###
2 Plasteran Tutup Kolong m2 12.00 ###
3 Gororng- Gororng Jalan Masuk + Pemasangan Bh 4.00 ###
4 Lantai Teras Belakang Cor Beton Fc 7.4 Mpa t 10 cm m3 0.80 ###
5 Pekerjaan Jalan Rabat
Galian tanah m3 1.04 1.04
Dinding penahan pasir cor beton Fc.7.4 Mpa m3 1.56 ###
Bakesting m2 7.80 ###
Urug pasir bawah Lantai m3 5.20 ###
Cor Lantai Beton Fc. 7.4 Mpa m3 5.20 5.20
Plesteran camp. 1:3 , tbl = 1,5 cm m2 52.00 ###