Anda di halaman 1dari 98

HARGA PERKIRAAN SENDIRI (HPS)

INSTANSI : DINAS PERUMAHAN DAN KAWASAN PEMUKIMAN KABUPATEN M


NAMA PEKERJAAN : PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURME
LOKASI : BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAMBE
PROVINSI : PAPUA
TAHUN : 2019
NO. JENIS PEKERJAAN JUMLAH

1 2
I. PEKERJAAN PERSIAPAN
II. PEKERJAAN TANAH
III. PEKERJAAN PONDASI
IV. PEKERJAAN PASANGAN DINDING
V. PEKERJAAN PLESTERAN
VI. PEKERJAAN KAYU
VII. PEKERJAAN BETON
VIII. PEKERJAAN BETON
IX. PEKERJAAN PENUTUP ATAP
X. PEKERJAAN LANGIT - LANGIT ( PLAFOND )
XI. PEKERJAAN INSTALASI LISTRIK
XII. PEKERJAAN SANITASI DALAM GEDUNG
XIII. PEKERJAAN SANITASI
XIV. PEKERJAAN KUNCI DAN KACA
XV. PEKERJAAN PENUTUP LANTAI DAN DINDING
XVI. PEKERJAAN PENGECATAN
XVII. PEKERJAAN FINSHING
Real Cost
PPN 10%
Total Cost Fisik
Dibulatkan Total 1 Unit Rumah
Total 8 Unit Rumah
Terbilang : Dua Milliyar Sembilan Ratus Dua Puluh Juta Rupiah,-
MUKIMAN KABUPATEN MAMBERAMO RAYA
36 DI KAMPUNG BURMESO (8 UNIT)
GAH KABUPATEN MAMBERAMO RAYA

JUMLAH
( Rp )
3
Rp 6,200,720.00
Rp 15,726,678.00
Rp 35,368,815.24
Rp 43,803,072.50
Rp 35,985,002.33
Rp 36,412,880.09
Rp 33,834,002.32
Rp 5,070,487.50
Rp 13,544,643.20
Rp 6,891,335.00
Rp 5,880,081.16
Rp 7,389,719.50
Rp 18,137,415.32
Rp 4,751,765.66
Rp 22,726,416.56
Rp 14,110,581.13
Rp 450,000.00
Rp. 306,283,615.51
Rp. 30,628,361.55
Rp. 336,911,977.06
Rp. 336,911,000.00
Rp. 2,695,288,000.00
FORMULIR REKAPITU

NAMA PEKERJAAN : PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURMESO (8 U


LOKASI : BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAMBERAMO

Nilai Penawaran Tanpa PPN 10% (Rp)


Uraian Pekerjaan LN DN

Barang
I. Material Langsung (Bahan Jadi) 0.00 1,886,701,600.00
II. Peralatan (Barang Jadi) 0.00 404,293,200.00
A. Sub Total Barang 2,290,994,800.00
Jasa
III. Manajemen Proyek dan Perekayasaan 0.00 53,905,760.00
IV. Alat Kerja/ Fasilitas Kerja 0.00 53,905,760.00
V. Konstruksi dan Fabrikasi 0.00 269,528,800.00
VI. Jasa Umum 0.00 26,952,880.00
B. Jasa Umum 404,293,200.00
C. TOTAL Biaya (A+B) 2,695,288,000.00
Capaian diatas dinyatakan sendiri oleh
Nilai penawaran diluar PPN 10%
RMULIR REKAPITULASI TKDN

MPUNG BURMESO (8 UNIT)


UPATEN MAMBERAMO RAYA

2,695,288,000.00 TKDN Gabungan


TOTAL % TKDN RP
RP % KDN
Barang
1,886,701,600.00 70.00%
404,293,200.00 15.00%
2,290,994,800.00 85.00% 85.00% 2,290,994,800.00
Jasa
53,905,760.00 2.00%
53,905,760.00 2.00%
269,528,800.00 10.00%
26,952,880.00 1.00%
404,293,200.00 15.00% 15.00% 404,293,200.00
2,695,288,000.00 100.00% 2,695,288,000.00

Jayapura,
TKDN Gabungan
%

85.00%

15.00%
100.00%

a,
RENCANA ANGGARAN BI
INSTANSI :
NAMA PEKERJAAN :
LOKASI :
PROVINSI :
TAHUN :
NO.
NOMOR JENIS PEKERJAAN
ANALISA
1 2 3
I. PEKERJAAN PERSIAPAN
1 A.2.2.1.4 Mengerjakan 1 m² pengukuran dan pemasangan bouwplank
2 A.2.2.1.7 Membuat 1 m² gudang semen dan alat-alat
3 A.2.2.1.9 Membersihkan 1 m² lapangan dan perataan
4 Penyediaan Air dan Listrik Kerja
5 Pembuatan papan nama proyek

II. PEKERJAAN TANAH


1 A.2.3.1.1 Menggali 1 m³ tanah biasa sedalam 1 meter
2 A.2.3.1.9 Mengurug kembali 1 m³ galian sedalam 1 m
3 A.2.3.1.11 Urugan pasir bawah pondasi
4 A.2.3.1.11 Urugan pasir bawah lantai
5 A.2.3.1.11.a Mengurug 1 m³ tanah urug

III. PEKERJAAN PONDASI


1 A.3.2.1.2 Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP
2 A.3.2.1.9 Memasang 1 m³ batu kosong (aanstampeeng)

IV. PEKERJAAN PASANGAN DINDING


1 A.4.4.1.9 Memasang 1 m² dinding batu tela; tebal ½ bata; campuran 1 PC : 4 PP

V. PEKERJAAN PLESTERAN
1 A.44.2.4 Memasang 1 m² plesteran 1 PC : 4 PP; tebal 15 mm
2 A.44.2.20 Memasang 1 m' plesteran skoning 1 Pc : 2 PP; lebar 10 mm
3 A.44.2.27 Memasang 1 m² acian dinding

VI. PEKERJAAN KAYU


1 A.4.6.1.1 Membuat dan memasang 1 m³ kusen pintu dan kusen jendela, kayu kelas I
2 A.4.6.1.5 Membuat dan memasang 1 m² daun pintu panel, kayu kelas I
3 A.4.6.1.6 Membuat dan memasang 1 m² pintu dan jendela kaca 5 mm, kayu kelas I
4 A.4.6.1.8 Membuat 1 m² daun pintu plywood rangkap, rangka tertutup kayu kelas II
5 A.4.6.1.14 Memasang 1 m³ kontruksi kuda-kuda expose, kayu kelas I ( kayu besi )
6 A.4.6.1.15 Memasang 1 m³ kontruksi gording, kayu kelas II
7 A.4.6.1.20 Memasang 1 m² rangka langit-langit (60 x 60) cm, kayu kelas II
8 A.4.6.1.22 Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I ( kayu besi )
VII. PEKERJAAN BETON
1 A.4.1.1.29 Membuat 1 m³ sloof beton bertulang 15/20 (200 kg besi + bekisting)
2 A.4.1.1.32 Membuat 1 m³ kolom beton bertulang 12/12 (150 kg besi + bekisting)
3 A.4.1.1.33 Membuat 1 m³ dak beton bertulang (150 kg besi + bekisting)
4 A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10 x 15 cm)

VIII. PEKERJAAN BETON


1 G.042 Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR

IX. PEKERJAAN PENUTUP ATAP


1 A.4.5.2.40 Memasang 1 m² penutup atap spandek warna ( zingkalume ), BJLS 0.30
2 A.4.5.2.41 Memasang 1 m' nok bubung spandek warna BJLS 0.30

X. PEKERJAAN LANGIT - LANGIT ( PLAFOND )


1 A.4.5.1.5 Memasang 1 m² langit-langit tripleks ukuran (120 x 240 ) cm; tbl. 4 mm
2 A.4.5.1.9 Memasang 1 m' list langit-langit kayu profil

XI. PEKERJAAN INSTALASI LISTRIK


1 A.4.5.3.1 Memasang 1 ttk lampu SL 18 watt
2 A.4.5.3.2 Memasang 1 ttk saklar tunggal
3 A.4.5.3.3 Memasang 1 ttk saklar ganda
4 A.4.5.3.4 Memasang 1 ttk stop kontak
5 A.4.5.3.5 Memasang 1 bh box sekring

XII. PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.2 Memasang 1 buah closet jongkok porselen INA warna tua
2 A.5.1.1.7 Memasang 1 buah bak mandi fibreglass volume 1,00 m³
3 A.5.1.1.14 Memasang 1 buah floor drain
4 A.5.1.1.18 Memasang 1 m' pipa galvanis Ø ½"
5 A.5.1.1.19.a Memasang 1 buah kran Ø ¾" atau ½" kualitas baik
6 A.5.1.1.29 Memasang 1 m' pipa PVC tipe AW Ø 2"
7 A.5.1.1.32 Memasang 1 m' pipa PVC tipe AW Ø 4"

XIII. PEKERJAAN SANITASI


1 J.041 Membuat 1 unit septic tank ukuran 1,5 x 1 x 1,5 m + rembesan
2 K.015 Memasang 1 m' talang ½ lingkaran Ø 10 cm, seng BJLS 30, 90 cm
3 Pengadaan dan pemasangan Tangki 1100 L + ACC
4 Membuat menara air konstruksi kayu

XIV. PEKERJAAN KUNCI DAN KACA


1 A.4.6.2.2 Memasang 1 buah kunci tanam biasa
2 A.4.6.2.5 Memasang 1 buah engsel pintu
3 A.4.6.2.6 Memasang 1 buah engsel jendela kupu - kupu
4 A.4.6.2.9 Memasang 1 buah kait angin
5 A.4.6.2.17 Memasang 1 m² kaca bening tebal 5 mm
L. PEKERJAAN KUNCI DAN KACA
1 L.011 Memasang 1 buah gerendel (pendek) pintu
2 L.013 Memasang 1 buah gerendel jendela

XV. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 A.4.4.3.35.c Memasang 1 m² lantai keramik polos (40 x 40) cm
2 A.4.4.3.36 Memasang 1 m² lantai keramik polos (20 x 20) cm
3 A.4.4.3.54.b Memasang 1 m² dinding keramik polos ukuran 20 x 25 cm, tinggi 1,5 m
4 A.4.4.3.60 Memasang 1 m² lapis seng plat BJLS 0.30 pada pintu km/wc

XVI. PEKERJAAN PENGECATAN


1 A.4.7.1.5 1 m² mengecat bidang kayu baru
2 A.4.7.1.10 1 m² pengecetan tembok baru
3 A.4.7.1.10.a 1 m² pengecetan plafond baru menggunakan perancah

XVII. PEKERJAAN FINSHING


1 Pembersihan Lokasi
2 Dokumentasi & Pelaporan
RENCANA ANGGARAN BIAYA ( RAB )
DINAS PERUMAHAN DAN KAWASAN PEMUKIMAN KABUPATEN MAMBERAMO RAYA
PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURMESO (8 UNIT)
BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAMBERAMO RAYA
PAPUA
2019

JENIS PEKERJAAN SAT.

Mengerjakan 1 m² pengukuran dan pemasangan bouwplank m²


Membuat 1 m² gudang semen dan alat-alat ls
Membersihkan 1 m² lapangan dan perataan ls
Penyediaan Air dan Listrik Kerja ls
Pembuatan papan nama proyek ls

Menggali 1 m³ tanah biasa sedalam 1 meter m³


Mengurug kembali 1 m³ galian sedalam 1 m m³
Urugan pasir bawah pondasi m³
Urugan pasir bawah lantai m³
Mengurug 1 m³ tanah urug m³

Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP m³


Memasang 1 m³ batu kosong (aanstampeeng) m³

ANGAN DINDING
Memasang 1 m² dinding batu tela; tebal ½ bata; campuran 1 PC : 4 PP m²

Memasang 1 m² plesteran 1 PC : 4 PP; tebal 15 mm m²


Memasang 1 m' plesteran skoning 1 Pc : 2 PP; lebar 10 mm m'
Memasang 1 m² acian dinding m²

Membuat dan memasang 1 m³ kusen pintu dan kusen jendela, kayu kelas I m³
Membuat dan memasang 1 m² daun pintu panel, kayu kelas I m²
Membuat dan memasang 1 m² pintu dan jendela kaca 5 mm, kayu kelas I m²
Membuat 1 m² daun pintu plywood rangkap, rangka tertutup kayu kelas II m²
Memasang 1 m³ kontruksi kuda-kuda expose, kayu kelas I ( kayu besi ) m³
Memasang 1 m³ kontruksi gording, kayu kelas II m²
Memasang 1 m² rangka langit-langit (60 x 60) cm, kayu kelas II m²
Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I ( kayu besi ) m'
Membuat 1 m³ sloof beton bertulang 15/20 (200 kg besi + bekisting) m³
Membuat 1 m³ kolom beton bertulang 12/12 (150 kg besi + bekisting) m³
Membuat 1 m³ dak beton bertulang (150 kg besi + bekisting) m³
Membuat 1 m' ring balok beton bertulang (10 x 15 cm) m'

Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR m³

UTUP ATAP
Memasang 1 m² penutup atap spandek warna ( zingkalume ), BJLS 0.30 m²
Memasang 1 m' nok bubung spandek warna BJLS 0.30 m²

GIT - LANGIT ( PLAFOND )


Memasang 1 m² langit-langit tripleks ukuran (120 x 240 ) cm; tbl. 4 mm m²
Memasang 1 m' list langit-langit kayu profil m'

TALASI LISTRIK
Memasang 1 ttk lampu SL 18 watt ttk
Memasang 1 ttk saklar tunggal ttk
Memasang 1 ttk saklar ganda ttk
Memasang 1 ttk stop kontak ttk
Memasang 1 bh box sekring bh

ITASI DALAM GEDUNG


Memasang 1 buah closet jongkok porselen INA warna tua bh
Memasang 1 buah bak mandi fibreglass volume 1,00 m³ bh
Memasang 1 buah floor drain bh
Memasang 1 m' pipa galvanis Ø ½" m'
Memasang 1 buah kran Ø ¾" atau ½" kualitas baik bh
Memasang 1 m' pipa PVC tipe AW Ø 2" m'
Memasang 1 m' pipa PVC tipe AW Ø 4" m'

Membuat 1 unit septic tank ukuran 1,5 x 1 x 1,5 m + rembesan unit


Memasang 1 m' talang ½ lingkaran Ø 10 cm, seng BJLS 30, 90 cm m'
Pengadaan dan pemasangan Tangki 1100 L + ACC unit
Membuat menara air konstruksi kayu ls

CI DAN KACA
Memasang 1 buah kunci tanam biasa bh
Memasang 1 buah engsel pintu bh
Memasang 1 buah engsel jendela kupu - kupu bh
Memasang 1 buah kait angin bh
Memasang 1 m² kaca bening tebal 5 mm m²
PEKERJAAN KUNCI DAN KACA
Memasang 1 buah gerendel (pendek) pintu bh
Memasang 1 buah gerendel jendela bh

UTUP LANTAI DAN DINDING


Memasang 1 m² lantai keramik polos (40 x 40) cm m²
Memasang 1 m² lantai keramik polos (20 x 20) cm m²
Memasang 1 m² dinding keramik polos ukuran 20 x 25 cm, tinggi 1,5 m m²
Memasang 1 m² lapis seng plat BJLS 0.30 pada pintu km/wc m²

GECATAN
1 m² mengecat bidang kayu baru m²
1 m² pengecetan tembok baru m²
1 m² pengecetan plafond baru menggunakan perancah m²

Pembersihan Lokasi ls
Dokumentasi & Pelaporan ls
A ( RAB )

HARGA SATUAN JUMLAH


VOLUME
( Rp ) ( Rp )
5 6

32.00 51,585.00 1,650,720.00


1.00 1,500,000.00 1,500,000.00
1.00 2,500,000.00 2,500,000.00
1.00 500,000.00 500,000.00
1.00 50,000.00 50,000.00
JUMLAH 6,200,720.00
-
11.52 115,500.00 1,330,560.00
3.84 88,000.00 337,920.00
1.44 1,102,200.00 1,587,168.00
3.90 1,102,200.00 4,298,580.00
9.75 838,200.00 8,172,450.00
JUMLAH 15,726,678.00
-
9.72 2,906,475.00 28,250,937.00
4.32 1,647,657.00 7,117,878.24
JUMLAH 35,368,815.24
-
105.50 415,195.00 43,803,072.50
JUMLAH 43,803,072.50
-
211.00 100,217.00 21,145,787.00
3.00 116,545.00 349,635.00
196.09 73,892.50 14,489,580.330
JUMLAH 35,985,002.33
-
0.30 7,033,800.00 2,120,690.70
6.72 1,021,900.00 6,867,168.00
2.22 990,220.00 2,198,288.40
1.47 837,650.00 1,231,345.50
0.43 9,320,880.00 4,030,115.49
0.56 8,161,480.00 4,570,428.80
67.20 172,161.00 11,569,219.20
34.40 111,210.00 3,825,624.00
JUMLAH 36,412,880.09
-
1.08 11,892,319.00 12,843,704.52
0.65 11,890,900.00 7,705,303.20
0.32 12,654,741.00 4,074,826.60
36.00 255,838.00 9,210,168.00
JUMLAH 33,834,002.32
RSNI-T-13-2002
1.95 2,600,250.00 5,070,487.50
JUMLAH 5,070,487.50
-
76.80 162,459.00 12,476,851.20
8.00 133,474.00 1,067,792.00
JUMLAH 13,544,643.20
-
67.20 56,644.27 3,806,495.00
72.00 42,845.00 3,084,840.00
JUMLAH 6,891,335.00
-
7.00 392,150.00 2,745,050.00
3.00 327,855.00 983,565.00
2.00 330,825.00 661,650.00
3.00 325,921.54 977,764.62
1.00 512,051.54 512,051.54
JUMLAH 5,880,081.16
-
1.00 1,465,850.00 1,465,850.00
1.00 1,448,085.00 1,448,085.00
1.00 74,910.00 74,910.00
6.00 99,814.00 598,884.00
1.00 273,900.00 273,900.00
8.00 93,599.00 748,792.00
11.00 252,663.50 2,779,298.50
JUMLAH 7,389,719.50
-
1.00 10,410,815.32 10,410,815.32
8.00 209,575.00 1,676,600.00
1.00 3,500,000.00 3,500,000.00
1.00 2,550,000.00 2,550,000.00
JUMLAH 18,137,415.32
-
5.00 245,730.00 1,228,650.00
15.00 101,904.00 1,528,560.00
8.00 78,925.00 631,400.00
8.00 71,280.00 570,240.00
1.50 227,569.00 340,215.66
Pt. T - 30 - 2002 C
5.00 50,300.00 251,500.00
4.00 50,300.00 201,200.00
JUMLAH 4,751,765.66
-
35.25 514,254.60 18,127,474.65
2.25 426,031.00 958,569.75
7.80 429,562.00 3,350,583.60
1.47 197,135.07 289,788.56
JUMLAH 22,726,416.56
-
40.98 98,318.00 4,029,071.64
196.09 35,357.90 6,933,330.61
67.20 46,847.90 3,148,178.88
JUMLAH 14,110,581.13
-
1.00 200,000.00 200,000.00
1.00 250,000.00 250,000.00
JUMLAH 450,000.00
TIME SKECDHULE
INSTANSI : DINAS PERUMAHAN DAN KAWASAN PEMUKIMAN KABUPATEN MAMBERAMO RAYA
NAMA PEKERJAAN : PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURMESO (8 UNIT)
LOKASI : BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAMBERAMO RAYA
PROVINSI : PAPUA
TAHUN : 2019
NOMOR WAKT
NO. JENIS PEKERJAAN SAT. VOLUME BOBOT
ANALISA BULAN KE I

1 2 3 4

I. PEKERJAAN PERSIAPAN
100.00
1 A.2.2.1.4 Mengerjakan 1 m² pengukuran dan pemasangan bouwplank m² 32.00 2.24 2.239
2 A.2.2.1.7 Membuat 1 m² gudang semen dan alat-alat ls 1.00 0.07 0.070
3 A.2.2.1.9 Membersihkan 1 m² lapangan dan perataan ls 1.00 0.07 0.070
4 Penyediaan Air dan Listrik Kerja ls 1.00 0.07 0.070
5 Pembuatan papan nama proyek ls 1.00 0.07 0.070

II. PEKERJAAN TANAH


1 A.2.3.1.1 Menggali 1 m³ tanah biasa sedalam 1 meter m³ 11.52 0.81 0.806
2 A.2.3.1.9 Mengurug kembali 1 m³ galian sedalam 1 m m³ 3.84 0.27 0.269
3 A.2.3.1.11 Urugan pasir bawah pondasi m³ 1.44 0.10 0.050 0.050
90.00
4 A.2.3.1.11 Urugan pasir bawah lantai m³ 3.90 0.27 0.273
5 A.2.3.1.11.a Mengurug 1 m³ tanah urug m³ 9.75 0.68 0.682

III. PEKERJAAN PONDASI


1 A.3.2.1.2 Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP m³ 9.72 0.68 0.227 0.227 0.227
2 A.3.2.1.9 Memasang 1 m³ batu kosong (aanstampeeng) m³ 4.32 0.30 0.302

IV. PEKERJAAN PASANGAN DINDING


1 A.4.4.1.9 Memasang 1 m² dinding batu tela; tebal ½ bata; campuran 1 PC : 4 PP m² 105.50 7.38 2.461

80.00
V. PEKERJAAN PLESTERAN
1 A.44.2.4 Memasang 1 m² plesteran 1 PC : 4 PP; tebal 15 mm m² 211.00 14.77
2 A.44.2.20 Memasang 1 m' plesteran skoning 1 Pc : 2 PP; lebar 10 mm m' 3.00 0.21
3 A.44.2.27 Memasang 1 m² acian dinding m² 196.09 13.72

VI. PEKERJAAN KAYU


1 A.4.6.1.1 Membuat dan memasang 1 m³ kusen pintu dan kusen jendela, kayu kelas I m³ 0.30 0.02 0.021
2 A.4.6.1.5 Membuat dan memasang 1 m² daun pintu panel, kayu kelas I m² 6.72 0.47 0.470
3 A.4.6.1.6 Membuat dan memasang 1 m² pintu dan jendela kaca 5 mm, kayu kelas I m² 2.22 0.16 0.155
4 A.4.6.1.8 Membuat 1 m² daun pintu plywood rangkap, rangka tertutup kayu kelas II m² 1.47 0.10 0.103
70.00
5 A.4.6.1.14 Memasang 1 m³ kontruksi kuda-kuda expose, kayu kelas I ( kayu besi ) m³ 0.43 0.03
6 A.4.6.1.15 Memasang 1 m³ kontruksi gording, kayu kelas II m² 0.56 0.04
7 A.4.6.1.20 Memasang 1 m² rangka langit-langit (60 x 60) cm, kayu kelas II m² 67.20 4.70
8 A.4.6.1.22 Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I ( kayu besi ) m' 34.40 2.41

VII. PEKERJAAN BETON


1 A.4.1.1.29 Membuat 1 m³ sloof beton bertulang 15/20 (200 kg besi + bekisting) m³ 1.08 0.08 0.076

60.00
2 A.4.1.1.32 Membuat 1 m³ kolom beton bertulang 12/12 (150 kg besi + bekisting) m³ 0.65 0.05 0.045
3 A.4.1.1.33 Membuat 1 m³ dak beton bertulang (150 kg besi + bekisting) m³ 0.32 0.02
4 A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10 x 15 cm) m' 36.00 2.52
60.00

VIII. PEKERJAAN BETON


1 G.042 Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR m³ 1.95 0.14

IX. PEKERJAAN PENUTUP ATAP


1 A.4.5.2.40 Memasang 1 m² penutup atap spandek warna ( zingkalume ), BJLS 0.30 m² 76.80 5.37
2 A.4.5.2.41 Memasang 1 m' nok bubung spandek warna BJLS 0.30 m² 8.00 0.56

X. PEKERJAAN LANGIT - LANGIT ( PLAFOND )


1 A.4.5.1.5 Memasang 1 m² langit-langit tripleks ukuran (120 x 240 ) cm; tbl. 4 mm m² 67.20 4.70 50.00
2 A.4.5.1.9 Memasang 1 m' list langit-langit kayu profil m' 72.00 5.04

XI. PEKERJAAN INSTALASI LISTRIK


1 A.4.5.3.1 Memasang 1 ttk lampu SL 18 watt ttk 7.00 0.49
2 A.4.5.3.2 Memasang 1 ttk saklar tunggal ttk 3.00 0.21
3 A.4.5.3.3 Memasang 1 ttk saklar ganda ttk 2.00 0.14
4 A.4.5.3.4 Memasang 1 ttk stop kontak ttk 3.00 0.21
5 A.4.5.3.5 Memasang 1 bh box sekring bh 1.00 0.07

XII. PEKERJAAN SANITASI DALAM GEDUNG 40.00


1 A.5.1.1.2 Memasang 1 buah closet jongkok porselen INA warna tua bh 1.00 0.07
2 A.5.1.1.7 Memasang 1 buah bak mandi fibreglass volume 1,00 m³ bh 1.00 0.07
3 A.5.1.1.14 Memasang 1 buah floor drain bh 1.00 0.07
4 A.5.1.1.18 Memasang 1 m' pipa galvanis Ø ½" m' 6.00 0.42
5 A.5.1.1.19.a Memasang 1 buah kran Ø ¾" atau ½" kualitas baik bh 1.00 0.07
6 A.5.1.1.29 Memasang 1 m' pipa PVC tipe AW Ø 2" m' 8.00 0.56
7 A.5.1.1.32 Memasang 1 m' pipa PVC tipe AW Ø 4" m' 11.00 0.77

XIII. PEKERJAAN SANITASI


1 J.041 Membuat 1 unit septic tank ukuran 1,5 x 1 x 1,5 m + rembesan unit 1.00 0.07 30.00
2 K.015 Memasang 1 m' talang ½ lingkaran Ø 10 cm, seng BJLS 30, 90 cm m' 8.00 0.56
3 Pengadaan dan pemasangan Tangki 1100 L + ACC unit 1.00 0.07
4 Membuat menara air konstruksi kayu ls 1.00 0.07

XIV. PEKERJAAN KUNCI DAN KACA


1 A.4.6.2.2 Memasang 1 buah kunci tanam biasa bh 5.00 0.35
2 A.4.6.2.5 Memasang 1 buah engsel pintu bh 15.00 1.05
3 A.4.6.2.6 Memasang 1 buah engsel jendela kupu - kupu bh 8.00 0.56
4 A.4.6.2.9 Memasang 1 buah kait angin bh 8.00 0.56
5 A.4.6.2.17 Memasang 1 m² kaca bening tebal 5 mm m² 1.50 0.10 20.00
L. PEKERJAAN KUNCI DAN KACA Pt. T - 30 - 2002 C
1 L.011 Memasang 1 buah gerendel (pendek) pintu bh 5.00 0.35
2 L.013 Memasang 1 buah gerendel jendela bh 4.00 0.28

XV. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 A.4.4.3.35.c Memasang 1 m² lantai keramik polos (40 x 40) cm m² 35.25 2.47
2 A.4.4.3.36 Memasang 1 m² lantai keramik polos (20 x 20) cm m² 2.25 0.16

10.00
3 A.4.4.3.54.b Memasang 1 m² dinding keramik polos ukuran 20 x 25 cm, tinggi 1,5 m m² 7.80 0.55
4 A.4.4.3.60 Memasang 1 m² lapis seng plat BJLS 0.30 pada pintu km/wc m² 1.47 0.10
10.00
XVI. PEKERJAAN PENGECATAN
1 A.4.7.1.5 1 m² mengecat bidang kayu baru m² 40.98 2.87
2 A.4.7.1.10 1 m² pengecetan tembok baru m² 196.09 13.72
3 A.4.7.1.10.a 1 m² pengecetan plafond baru menggunakan perancah m² 67.20 4.70

XVII. PEKERJAAN FINSHING


1 Pembersihan Lokasi ls 1.00 0.07
2 Dokumentasi & Pelaporan ls 1.00 0.07
1428.92 100.00
100 0.00 2.52 1.34 0.37 4.74
RENCANA KOMULATIF
2.52 3.85 4.23 8.96
WAKTU PELAKSANAAN
BULAN KE II BULAN KE III
KETERANGAN
5 6 7 8 9 10 11 12

3 Bulan x 30 hari
= 90 Hari
1 Minggu = 7 Hari

2.461 2.461

4.922 4.922 4.922


0.105 0.105
13.723

0.030
0.039
4.703
2.407
0.023
1.260 1.260

0.136

5.375
0.560

2.351 2.351
5.039

0.490
0.210
0.140
0.210
0.070

0.070
0.070
0.070
0.420
0.070
0.560
0.770

0.070
0.560
0.070
0.070

0.350
1.050
0.560
0.560
0.105

0.350
0.280

2.467
0.157
0.546
0.103

2.868
13.723
4.703

0.070
0.070

15.40 10.18 12.99 16.77 12.49 0.65 22.41 0.14


24.36 34.54 47.53 64.31 76.80 77.45 99.86 100.00
REKAPITULASI PERHITUNGAN TKDN
PEKERJAAN : PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BU
: BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN M
TAHUN ANGGARAN : 2019

Uraian Pekerjaan Nilai Penawaran Tanpa PPN 10% (Rp)

KDN

Barang
I. Material Langsung (Bahan Baku) 183,770,169.31
II. Tenaga Kerja Langsung 76,570,903.88
III. Biaya Tidak Langsung Pabrik 45,942,542.33
(Factory Overhead)
TOTAL 306,283,615.51
PERHITUNGAN TKDN
RAKYAT TYPE 36 DI KAMPUNG BURMESO (8 UNIT)
MBERAMO TENGAH KABUPATEN MAMBERAMO RAYA

aran Tanpa PPN 10% (Rp) 306,283,615.51

KLN TOTAL
RP % KDN

0.00 183,770,169.31 60.00


0.00 76,570,903.88 25.00
0.00 45,942,542.33 15.00

0.00 306,283,615.51 100.00


NO. URAIAN

1 2
UPAH TENAGA :
1 Pekerja
2 Tukang gali
3 Mandor Lapangan
4 Tukang cat / plitur / batu
5 Kepala tukang cat / plitur / batu
6 Tukang kayu
7 Kepala tukang kayu
8 Tukang Besi
9 Kepala Tukang besi
10 Tukang Besi Profil
11 Kepala Tukang Besi Profil
12 Tukang las biasa
13 Tukang las konstruksi
14 Tukang khusus allumunium
15 Tukang allumunium / kaca
16 Tukang Instalasi
17 Mekanik terlatih
18 Mekanik Pembantu
19 Operator terlatih / masinis
20 Operator kurang terlatih
21 Pembantu operator / pemb. Masinis
22 Sopir Material / Truck
23 Sopir personil
24 Pembantu Sopir / Kenek
25 Buruh lapangan tak terlatih
26 Buruh lapangan kurang terlatih
27 Buruh lapangan terlatih
28 Tukang masak aspal
29 Penjaga malam
30 Sewa Bekisting jalan
31 Sewa Skafolding

Kelompok Material Alam :


32 Air
33 Tanah urug
34 Tanah urug Pilihan
35 Pasir urug
36 Pasir batu (sirtu)
37 Pasir pasang
38 Pasir pasang Muntilan ( ditempat )
39 Batu belah 10/15
40 Batu pecah tangan 5-7 cm
41 Batu pecah tangan 3-5 cm
42 Batu pecah tangan 3-4 cm
43 Batu pecah tangan 2-3 cm (split)
44 Batu pecah mesin 2-3 cm
45 Batu pecah mesin 3-4 cm
46 Batu pecah mesin 1-2 cm
47 Batu pecah mesin 0,5-1 cm
48 Abu batu
49 Kerikil sungai (tidak disaring) royalti
50 Batu kali besar royalti
51 Pasir ( Quary )
52 Batu kali ( Quary )
53 Batu tela
54 Batu bata ringan ( Hebel )
55 Batako (conblock)
56 Kapur

Kelompok Kayu
57 a. Kayu Kelas 1 : Balok 8/15 ( Kayu Besi )
b. Kayu Besi Klas I : Balok 8/15 ( Kayu Besi )
c. Papan kayu Kelas I ( kayu besi )
58 a. Kayu Kelas II : Balok 8/15 ( Kayu Matoa dan Sejenisnya )
b. Kayu Kelas II : 5/7 & 4/6 ( Kayu Matoa dan Sejenisnya )
c. Kayu Kelas II : 3/4 & 3/5 ( Kayu Matoa dan Sejenisnya )
d. Kayu Kelas II : 2/3 ( Kayu Matoa dan Sejenisnya )
e. Papan Kayu Kelas II ( Kayu Matoa dan Sejenisnya )
59 a. Kayu Kelas III : Balok
b. Kayu Kelas III : 5/7 & 4/6
c. Kayu Kelas III : 3/4 & 3/5
d. Kayu Kelas III : 2/3
e. Kayu Kelas III ( 2 x 20 x 400 )
60 a. Kayu Kelas IV ( Meranti Batu ) : Balok 8/15
b. Kayu Kelas IV, 5/7 & 4/6 (ikat)
Kayu Kelas IV 5/7 & 4/6 (lepas)
c. Kayu Kelas IV : 3/4 & 3/5
d. Kayu Kelas IV : 2/3
e. Papan Kayu Kelas IV ( 2 x 20 x 400 )
Papan Kayu Kelas IV ( 2 x 25 x 400 )
61 Balok Bekisting
62 Papan Cetak ( kayu putih ) uk 2 x 20 x 200
63 Kayu Putih
64 Kayu tahun
65 Kayu bakar
66 Kayu stoot
67 Alat - alat bantu ( @ 3 alat )
68 Kayu untuk perancah
69 Kayu Struktural ( Kayu Besi )
70 Tripleks tebal 3 mm uk. 120 x 240 cm
71 Tripleks tebal 4 mm uk. 120 x 240 cm
72 Tripleks tebal 6 mm uk. 120 x 240 cm
73 Tripleks tebal 8 mm uk. 120 x 240 cm
74 Tripleks tebal 3 mm uk. 90 x210 cm (uk. Pintu)
75 Tripleks tebal 4 mm uk. 90 x 210 cm (uk. Pintu)
76 Tripleks melaminto tebal 3 mm uk. 120 x 240 cm putih
77 Teakwood tebal 3 mm uk. 90 x 120 cm
78 Teakwood tebal 4 mm uk. 90 x 210 cm
79 Teakwood tebal 3 mm uk. 120 x240 cm
80 Teakwood tebal 4 mm uk. 120 x240 cm
81 Multipleks 9 mm
82 Multipleks 12 mm
83 Multipleks 15 mm
84 Multipleks 18 mm
85 Plywood 3 mm uk. 90 x 220 cm
86 Plywood 4 mm uk. 120 x 240 mm
87 Plywood 9 mm uk. 120 x 240 mm
88 Formika uk. Pintu
89 Ijuk
90 Dolken Ø 5
91 Dolken Ø 8 - 10
92 Dolken Ø 12
93 List Kayu Profil
94 Bambu Ø 7 - 10
95 Bambu Ø10 - 12

Kelompok Besi / Baja :


96 Paku
97 Paku skrup ( utk Gypsum)
98 Skrup vixer
99 Paku asbes gelombang
100 Paku sumbat
101 Paku Pancing
102 Besi beton/baja tulangan beton
103 Folding door tb. 1 cm bahan plastik / PVC
104 Rolling Door Aluminium
105 Rolling Door Besi
106 Vertical Blind
107 Profil allumunium
108 Atap Spandek Warna ( zingkalume ) BJLS 0.30
109 Nok Bubung Spandek BJLS 0,30
109 Bondex ( plat beton )
110 Besi beton U-24
111 Besi beton U-29
112 Besi Strip ( tebal 5 mm, lebar 5 Cm )
113 Besi Hollow
114 Kawat beton (bindrad)
115 Kawat Las
116 Kawat Las Listrik RD 26
117 Kawat Las Listrik RB 26
118 Baja plat
119 Baja baud - baud/ baud beugel
120 Rangka atap baja ringan type UK 75 terpasang jarak Kuda2 1,00M
121 Rangka atap baja ringan type C. 75 dan Z.75 terpasang Jarak Kuda2 1,00M
122 Baja ringan C.75, 0.8
123 Baja ringan C.75, 0.6
124 Reng R30 / 0,45
125 Besi kanal C
126 Besi siku L
127 Besi IWF
128 Kawat kasa / nyamuk
129 Kawat galvanis Q 1 mm
130 Baut 15 mm
131 Kawat Harmonika
132 Kawat duri
133 Kawat baja
134 Kran air standar

135 Kran air kualitas baik kuningan


136 Bak cuci almunium standart
137 Kunci tanam 2 X Slog
138 Kunci tanam kwalitas baik kuningan
139 Kunci Slot
140 Kunci Silinder
141 Kunci Lemari
142 Engsel pintu Nylon
143 Engsel pintu kuningan
144 Engsel jendela Nylon
145 Engsel jendela kuningan
146 Kait angin 6"
147 Kait angin 8"
148 Kait angin 10"
149 Hak angin
150 Hak angin kuningan
151 Spring knip
152 Door closer
153 Door holder
154 Door stop
155 Grendel jendela
156 Grendel pintu ( pendek )
157 Grendel pintu ( panjang )
158 Rel pintu dorong
159 Tangki air fiberglas Isi : 250 ltr
160 Tangki air fiberglas Isi : 500 ltr
161 Tangki air fiberglas Isi : 700 ltr
162 Tangki air fiberglas Isi : 1100 ltr
163 Pintu PVC biasa/polos (lengkap; kusen + daun)
164 Pintu PVC motif (lengkap; kusen + daun)
165 Kosen Almunium 4" Coklat
166 Kosen Almunium 4" Putih
167 Formite / penjaga jarak bekisting / spacer
168 Mur Baut Panjang
169 Mur Baut Pendek

Kelompok Lantai :
170 Keramik polos kw.1 ukuran 20 x 20 cm (antislip)
171 Keramik motif kw.1 ukuran 20 x 20 cm (antislip)
172 Keramik motif kw.1 ukuran 25 x 25 cm (antislip)
173 Keramik motif kw.1 ukuran 25 x 25 cm (antislip) Ex. Roman
174 Keramik Dinding motif kw.1 ukuran 25 x 40 cm
175 Keramik Dinding motif kw.1 ukuran 25 x 60 cm
176 Keramik polos kw.1 ukuran 30 x 30 cm
177 Keramik motif kw.1 ukuran 30 x 30 cm
178 Keramik granit kw.1 ukuran 30 x 30 cm
179 Keramik motif kw.1 ukuran 30 x 60 cm
180 Keramik motif kw.1 ukuran 30 x 60 cm Ex. Roman
181 Keramik polos kw.1 ukuran 40 x 40 cm
182 Keramik motif kw.1 ukuran 40 x 40 cm
183 Keramik granit kw.1 ukuran 40 x 40 cm
184 Keramik polos kw.1 ukuran 60 x 60 cm
185 Keramik motif kw.1 ukuran 60 x 60 cm
186 Keramik granit kw.1 ukuran 60 x 60 cm
187 Granite Tile Uk. 60 x 60 cm single loading
188 Granite Tile Uk. 60 x 60 cm double loading ex. Platinum
189 Keramik interlock
190 Keramik dinding polos kw.1 ukuran 20 x 25 cm
191 Keramik dinding motif kw.1 ukuran 20 x 25 cm
192 Keramik dinding granit kw.1 ukuran 20 x 25 cm
193 Keramik dinding kw.1 ukuran 30 x 60 cm
194 Keramik Artistik 10/20
195 Keramik Artistik 10/30
196 List keramik motif 5 x 20 cm
197 List keramik motif 5 x 25 cm
198 Plint keramik motif 10 x 40 cm
199 Plint keramik motif 10 x 60 cm
200 Porselen (11 x 11) cm
201 Karpet talang
202 Wallpaper standart ( vynil waterproof ex. lokal/china )
203 Paving segi 4 natural tb. 6 cm (Lokal)
204 Paving segi 6 natural tb. 6 cm (Lokal)
205 Paving segi 4 warna tb. 6 cm
206 Paving segi 6 warna tb. 6 cm
207 Paving blok natural tb. 6 cm (Magelang) / (K.175)
208 Paving blok natural tb. 8 cm (Magelang) / (K.175)
209 Kansteen beton cetak 10 x 20 x 50 cm
210 Kansteen beton cetak 10 x 20 x 40 cm
211 Kansteen beton cetak 15 x 30 x 60 cm
212 Roster bata (10x20)
213 Roster beton (10x20)
214 Roster keramik (20x20)

Kelompok Atap :
215 Genteng metal / multiroof berserabut barpasir
216 Genteng metal / multiroof polos
217 Kerpus genteng metal polos
218 Kerpus genteng metal ( Berpasir )
219 Atap galvalume / Zincalum 0,30 mm
220 Seng gelombang (210 x 80 x 0.3 cm)
221 Seng gelombang 3'-6' (90 x 180 x 0.3 cm)
222 Seng Plat BJLS 30 lebar 90 cm ; panjang 180 cm
223 Seng Plat BJLS 30 lebar 60 cm ; panjang 180 cm
224 Seng Plat BJLS 30 lebar 30 cm ; panjang 180 cm
225 Eternit
226 Kalsibot 4 mm 120 x 240 cm
227 Gypsum board 120 x 240 x 9 mm
228 List Gipsum Profil 15 cm Pj. 2.00 m'
229 List Gipsum profil 10 cm Pj. 2.00 m'
230 Kompon board ( 1 zak = 20 kg )
231 Fiberglass gelombang uk. 180 x 80 cm
Kelompok Cat / Minyak :
232 Cat Warna ( Kayu ).
233 Cat Warna ( besi ).
234 Cat dasar ( meni kayu )
235 Cat dasar ( meni besi )
236 Cat jembatan ( besi )
237 Cat genteng ( 1 Klg = 4 kg )
238 Cat tembok / cat dasar
239 Cat Tembok Luar ( Wheather Shield )
240 Cat Tembok pelapis anti bocor
241 Cat brown
242 Vernis
243 Plamur Kayu
244 Plamur Tembok
245 Flincote
246 Minyak cat
247 Minyak Terpentin
248 Minyak Bekisting ( olie bekas )
249 Politur
250 Politur jadi
251 Dempul
252 Amplas
253 Aspal bitumen (kemasan )
254 Aspal curah
255 Kerosine / minyak aspal
256 Ol ie
257 Solar
258 Solar industri
259 Minyak tanah
260 Minyak pelumas
261 Plastik
262 Minyak Transmisi
263 Bensin / premium
264 Shear Connector
265 Melamik
266 Kuas cat 2"
267 Kuas cat 3"
268 Kuas cat 4"
269 Sikat Baja
270 Kapek
271 Roll Cat
272 Residu / Soligium
273 Soda Api
274 Sabun
275 Sealant
276 Lem Kayu
277 Lem Kuning
278 Wood Filler

Kelompok Cement, Kaca dan Lain-lain :


279 Portland Cement ( PC ) 50 kg
280 Portland Cement ( PC )
281 Cement warna
282 Cement putih
283 Kaca bening tebal 3 mm
284 Kaca bening tebal 5 mm
285 Kaca bening tebal 8 mm
286 Kaca bening tebal 10 mm
287 Kaca rayban tebal 5 mm
288 Kaca buram tebal 5 mm
289 Jendelan naco
290 Profil kaca
291 Glassblock
292 Bak Mandi Fiberglass, volume 120 ltrr (sudut)
293 Closet Jongkok KIA
294 Closet duduk standart - 1 ( monoblock manual )
295 Closet duduk standart - 2 ( Monoblok single flush dimensi bowl)
296 Closet duduk monoblock
297 Kloset duduk / Monoblok " INA ", Putih
298 Kloset duduk / Monoblok " INA ", Warna Tua
299 Kloset jongkok INA, warna tua
300 Kloset jongkok INA, warna muda
301 Urinoir Otomatis
302 Floordrain (saringan buangan air KM/WC)
303 Floordrain Stainless Steel (saringan buangan air KM/WC)
304 Floordrain Stainless Steel (+ waste filter)
305 Wastafel Kw.1 pedes steel
306 Wastafel standart - 1 ( model gantung marble )
307 Bak Cuci Stainless Steel lengkap

KELOMPOK AIR BERSIH


308 Pipa GIP SNI
Ukuran ½"
Ukuran ¾"
Ukuran 1"
Ukuran 1½"
Ukuran 2"
Ukuran 2½"
Ukuran 3"
Ukuran 4"
309 Pipa PVC
Ukuran Ø ½" ( AW ) ex Wavin
Ukuran Ø ¾" ( AW ) ex Wavin
Ukuran Ø 1" ( AW ) ex Wavin
Ukuran Ø 1¼" ( AW ) ex Wavin
Ukuran Ø 1½" ( AW ) ex Wavin
Ukuran Ø 2" ( AW ) ex Wavin
Ukuran Ø 2½" ( AW ) ex Wavin
Ukuran Ø 3" ( AW ) ex Wavin
Ukuran Ø 4" ( AW ) ex Wavin
Ukuran Ø 5" ( AW ) ex Wavin
Ukuran Ø 6" ( AW ) ex Wavin
Ukuran Ø 10" ( AW ) ex Wavin
Ukuran Ø 12" ( AW ) ex Wavin
318 Seal Tape
319 Lem Isarplas
KELOMPOK LAMPU - LAMPU
310 Lampu Pijar 25 Wat
311 Lampu SL 18 Wat ( CFL )
312 Lampu TL 20 Wat ( Lengkap )
313 Lampu TL 20 Wat Double ( Lengkap )
314 Lampu TL 40 Wat ( Lengkap )
315 Lampu TL 40 Wat Double ( Lengkap )
316 Stop Kontak
317 Stop Kontak AC
318 Sakelar Tunggal
319 Sakelar Ganda
320 Downlight
321 Box Panel
322 Box Sekering
323 MCB 6 - 10 A

KELOMPOK LAMPU - LAMPU


Peralatan Jaringan Listrik
324 Pipa Kabel
325 Fitting Plafon Broco
326 Isolasi Besar
327 Kabel NYM 2 x 1,5 mm
328 Kabel NYM 2 x 4 mm
329 Kabel NYM 3 x 1,5 mm
330 Kabel NYM 3 x 2,5 mm
331 Kabel NYY 2 x 1,5 mm
332 Kabel NYY 2 x 2,5 mm
333 Kabel NYY 2 x 4 mm
334 Ignitor SN 58
335 Capasitor 30 UF CP 30 ET 28
336 MCB. 6 A
337 MCB. 10 A
338 MCB. 40 A
339 BOX MCB isi 1
340 Kabel twested 2 x 10 mm
341 Kabel twested 2 x 16 mm
342 Fitting Gantung 5 W
343 Kaki TL + Tempat stater
344 Tiang Lampu Poligonal 7 meter Type CN1
345 Tiang Lampu Poligonal 9 meter Type CN1
Lampu Slang
346 Klem lampu slang 12 mm
347 Contactor 50 A
348 Saklar Engkel Broco
349 Saklar seri Broco
350 Stop kontak Broco
351 Stop Kontak AC Broco
HARGA
SATUAN BAHAN
( Rp. )
3 4

hari 130,000.00
hari 130,000.00
hari 300,000.00
hari 180,000.00
hari 230,000.00
hari 180,000.00
hari 230,000.00
hari 180,000.00
hari 230,000.00
hari 180,000.00
hari 230,000.00
hari 180,000.00
hari 200,000.00
hari 180,000.00
hari 180,000.00
hari 180,000.00
hari 230,000.00
hari 180,000.00
hari 250,000.00
hari 200,000.00
hari 180,000.00
hari 180,000.00
hari 180,000.00
hari 140,000.00
hari 120,000.00
hari 125,000.00
hari 130,000.00
hari 130,000.00
hari 125,000.00
m² 150,000.00
set/hari 15,000.00

liter 91.00
m³ 600,000.00
m³ 700,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 1,500,000.00
m³ 1,400,000.00
m³ 1,600,000.00
m³ 1,600,000.00
m³ 1,000,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
m³ 800,000.00
buah 12,000.00
buah 30,000.00
buah 20,000.00
m³ 605,000.00

m³ 4,000,000.00
m³ 4,000,000.00
m³ 4,000,000.00
m³ 3,500,000.00
m³ 3,500,000.00
m³ 3,500,000.00
m³ 3,500,000.00
m³ 3,500,000.00
m³ 3,000,000.00
m³ 3,000,000.00
m³ 3,000,000.00
m³ 3,000,000.00
m³ 3,000,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 2,950,000.00
m³ 815,000.00
btg 25,000.00
set 100,000.00
m3 2,950,000.00
m3 4,000,000.00
lbr 119,000.00
lbr 119,000.00
lbr 220,000.00
lbr 280,000.00
lbr 70,000.00
lbr 80,000.00
lbr 170,000.00
lbr 110,000.00
lbr 120,000.00
lbr 150,000.00
lbr 160,000.00
lbr 290,000.00
lbr 400,000.00
lbr 445,000.00
lbr 500,000.00
lbr 130,000.00
lbr 170,000.00
lbr 300,000.00
lbr 190,000.00
kg 50,000.00
m' 2,000.00
m' 3,000.00
m' 4,000.00
m' 20,000.00
Btg 15,000.00
Btg 25,000.00

kg 40,000.00
kg 44,000.00
bh 2,800.00
kg 64,000.00
kg 46,000.00
kg 41,000.00
kg 30,000.00
m² 2,100,000.00
m² 1,700,000.00
m² 680,000.00
m² 290,000.00
m' 110,000.00
m² 105,000.00
m² 70,000.00
kg 301,000.00
kg 29,000.00
kg 29,000.00
kg 75,000.00
kg 30,000.00
kg 45,000.00
kg 50,000.00
kg 54,000.00
kg 55,000.00
kg 33,000.00
kg 60,000.00
m2 461,593.00
m2 461,593.00
m' 30,000.00
m' 30,000.00
m' 23,000.00
kg 40,000.00
kg 40,000.00
kg 40,000.00
m² 33,000.00
m' 45,000.00
bh 19,000.00
m² 140,000.00
rol 330,000.00
kg 46,000.00
buah 105,000.00

buah 150,000.00
unit 1,100,000.00
buah 210,000.00
buah 390,000.00
buah 250,000.00
buah 170,000.00
buah 63,000.00
buah 50,000.00
buah 60,000.00
buah 50,000.00
buah 65,000.00
psg 30,000.00
psg 40,000.00
psg 45,000.00
psg 40,000.00
psg 45,000.00
buah 24,000.00
unit 1,300,000.00
unit 570,000.00
unit 200,000.00
buah 30,000.00
buah 35,000.00
buah 40,000.00
unit 330,000.00
unit 3,000,000.00
unit 4,000,000.00
unit 4,500,000.00
unit 5,000,000.00
unit 670,000.00
unit 820,000.00
m' 250,000.00
m' 230,000.00
buah 15,000.00
buah 22,000.00
buah 14,000.00

m² 150,000.00
m² 160,000.00
m² 165,000.00
m² 170,000.00
m² 155,000.00
m² 190,000.00
m² 160,000.00
m² 175,000.00
m² 310,000.00
m² 290,000.00
m² 390,000.00
m² 170,000.00
m² 190,000.00
m² 310,000.00
m² 360,000.00
m² 350,000.00
m² 395,000.00
m² 395,000.00
m² 540,000.00
m² 560,000.00
m² 130,000.00
m² 140,000.00
m² 225,000.00
m² 220,000.00
buah 12,000.00
buah 22,000.00
buah 6,000.00
buah 12,000.00
buah 17,000.00
buah 26,000.00
m² 40,000.00
m² 50,000.00
m² 63,000.00
m² 420,000.00
m² 420,000.00
m² 448,000.00
m² 448,000.00
m² 476,000.00
m² 476,000.00
buah 65,000.00
buah 86,000.00
buah 110,000.00
buah 20,000.00
buah 20,000.00
buah 110,000.00

m² 290,000.00
m² 180,000.00
m' 150,000.00
m' 160,000.00
m² 170,000.00
lbr 138,000.00
lbr 138,000.00
lbr 138,000.00
lbr 135,000.00
lbr 132,000.00
m² 64,000.00
lbr 135,000.00
lbr 155,000.00
m' 41,000.00
m' 37,000.00
kg 15,000.00
lbr 91,000.00
kg 91,000.00
kg 91,000.00
kg 45,000.00
kg 45,000.00
kg 91,000.00
kg 150,000.00
kg 40,000.00
kg 220,000.00
kg 80,000.00
kg 81,000.00
ltr 175,000.00
kg 60,000.00
kg 60,000.00
kg 91,000.00
kg 42,000.00
kg 21,000.00
ltr 8,000.00
kg 175,000.00
kg 190,000.00
kg 50,000.00
lbr 7,000.00
kg 22,000.00
kg 22,000.00
ltr 24,000.00
ltr 56,000.00
ltr 10,000.00
ltr 20,000.00
ltr 15,000.00
ltr 56,000.00
m² 21,000.00
ltr 77,000.00
ltr 20,000.00
ls 33,000.00
kg 155,000.00
buah 20,000.00
buah 25,000.00
buah 35,000.00
buah 35,000.00
buah 10,000.00
buah 50,000.00
ltr 20,000.00
kg 32,000.00
kg 12,000.00
tube 23,000.00
kg 30,000.00
kg 125,000.00
kg 42,000.00

zak 275,000.00
kg 5,500.00
kg 33,000.00
kg 20,000.00
m² 180,000.00
m² 240,000.00
m² 340,000.00
m² 470,000.00
m² 280,000.00
m² 280,000.00
buah 50,000.00
m' 80,000.00
buah 65,000.00
buah 1,100,000.00
buah 900,000.00
unit 2,300,000.00
unit 2,300,000.00
buah 3,800,000.00
Buah 3,800,000.00
Buah 3,800,000.00
Buah 900,000.00
Buah 900,000.00
buah 2,700,000.00
buah 45,000.00
buah 85,000.00
buah 390,000.00
unit 3,200,000.00
unit 3,200,000.00
Buah 1,100,000.00

m' 37,000.00
m' 47,000.00
m' 61,000.00
m' 88,000.00
m' 110,000.00
m' 120,000.00
m' 170,000.00
m' 230,000.00

m' 15,000.00
m' 17,000.00
m' 19,000.00
m' 23,000.00
m' 27,000.00
m' 38,000.00
m' 51,000.00
m' 79,000.00
m' 123,000.00
m' 183,000.00
m' 240,000.00
m' 570,000.00
m' 800,000.00
buah 15,000.00
tube 15,000.00

buah 40,000.00
buah 80,000.00
buah 160,000.00
buah 290,000.00
buah 190,000.00
buah 750,000.00
buah 52,000.00
buah 120,000.00
buah 53,000.00
buah 55,000.00
buah 170,000.00
unit 93,000.00
unit 110,000.00
unit 130,000.00

btg 42,000.00
buah 50,000.00
buah 22,000.00
m 15,000.00
m 27,000.00
m 27,000.00
m 46,000.00
m 15,000.00
m 25,000.00
m 27,000.00
buah 250,000.00
buah 250,000.00
buah 100,000.00
buah 100,000.00
buah 130,000.00
buah 30,000.00
m 12,000.00
m 17,000.00
buah 20,000.00
buah 25,000.00
buah 5,400,000.00
buah 7,020,000.00

buah 16,000.00
buah 2,500,000.00
buah 53,000.00
buah 58,000.00
buah 52,000.00
buah 123,000.00
JADW
LOKASI : FOKRI / FONA III, DISTRIK ROUFAER KABUPATEN MAMBERAMO RAYA
0.00

HARGA
NO. URAIAN PEKERJAAN SATUAN
SATUAN VOLUME

(Rp.)

Mengerjakan 1 m2 Pengukuran dan Pemasangan Bouwplank


1 Membuat 1 m2 Gudang Semen dan alat-alat m2 2.00 ###
2 Membersihkan 1 m2 Lapangan dan Perataan m2 168.00 ###
3 Penyediaan Air dan Listrik Kerja Ls 1.00 ###
4 Pembautan Papan Nama Proyek Ls 1.00 ###
5 0.00 0.00 0.00 0.00

Menggali 1 m3 tanah biasa sedalam 1 meter


1 Mengurug kembali 1 m3 galian sedalam 1 m m3 2.08 ###
2 0.00 0.00 0.00 0.00

Membuat dan memasang 1 m3 Cerucuk Pondasi, Kayu Kelas I


1 Membuat dan memasang 1 m3 balok gelagar/sloof kay m3 0.36 ###
2 Membuat dan memasang 1 m3 kolom kayu kelas I m3 0.42 ###
3 Membuat dan memasang 1 m3 ring balok kayu kelas m3 0.18 ###
4 Membuat dan memasang 1 m3 balok lantai kayu kelas m3 0.55 ###
5 Membuat dan memasang 1 m2 lantai papan kayu kela m2 42.00 ###
6 0.00 0.00 0.00 0.00

Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I
1 Membuat dan memasang 1 m3 Ralling Kayu Kelas I m3 0.23 ###
2 Membuat dan memasang 1 m2 daun pintu panel, kayu m2 6.72 ###
3 Membuat dan memasang 1 m2 pintu dan jendela kaca m2 5.74 ###
4 Membuat 1 m2 daun pintu plywood rangkap, rangka te m2 1.47 ###
5 Memasang 1 m2 jalusi kusen, kayu kelas II m2 2.08 ###
6 Memasang 1 m3 konstruksi kuda-kuda expose, kayu ke m2 0.40 ###
7 Memasang 1 m3 Konstruksi gording, kayu kelas II m2 0.56 ###
8 Memasang 1 m2rangka langit-langit (60 x 60) cm, kay m2 66.80 ###
9 Memasang 1 m' Lisplank Ukuran (3x30) cm, kayu kelas m' 35.00 ###
10 Memasang 1 m' Lisplank penutup lantai ukuran (3x30) m' 28.00 ###
11 Memasang 1 m2 rangka dinding pemisah (60 x 120) cm m2 95.26 ###
12 Memasang 1 m2 dinding lambrizing dari papan kayu k m2 63.26 ###
13 Memasang 1 m2 dinding lambrizing dari plywood uku m2 127.26 ###
14 0.00 0.00 0.00 0.00

Membuat 1 m3 beton tumbuk 1 Pc : 3 Pb : 5 Kr


1 0.00 0.00 0.00 0.00

Memasang 1 m2 Penutup atap spandek warna (Zingkalume) , BJLS 0.30


1 Memasang 1 m' nok bubung Spandek Warna BJLS0.3 m2 8.00 ###
2 0.00 0.00 0.00 0.00

Memasang 1 m2 Langit - langit tripleks ukuran (120 x 240) cm; tbl 4 mm


1 Memasang 1 m' List Langit - langit Kayu Profil m' 72.00 ###
2 0.00 0.00 0.00 0.00

Memasang 1 ttk lampu SL 18 Watt


1 Memasang 1 ttk saklar tunggal Bh 2.00 ###
2 Memasang 1 ttk saklar ganda Bh 2.00 ###
3 Memasang 1 ttk Stop Kontak Bh 3.00 ###
4 Memasang 1 bh BoX Sekring Bh 1.00 ###
5 0.00 0.00 0.00 0.00

Memasang 1 buah closet jongkok porselen INA Warna Tua


1 Memasang 1 buah bak mandi fiberglas volume 1,00 bh 1.00 ###
2 Memasang 1 buah floor drain bh 1.00 ###
3 Memasang 1 m' pipa galvanis Ø 1/2 " m' 6.00 ###
4 Memasang 1 buah kran Ø 3/4 " atau 1/2 " Kualitas ba bh 1.00 ###
5 Memasang 1 m' Pipa PVC tipe AW Ø 2" m' 8.00 ###
6 Memasang 1 m' pipa PVC Tipe AW Ø 4" m' 8.00 ###
7 0.00 0.00 0.00 0.00

Membuat 1 unit Septick Tank Ukuran 1.5 x 1 x 1.5 m + rembesan


1 Memasang 1 m' talang 1/2 lingkaran Ø 10 cm, seng B m 8.00 ###
2 Pengadaan dan pemasangan tangki 1100 L + ACC Unit 1.00 ###
3 Membuat menara air konstruksi kayu Ls 1.00 ###
4 0.00 0.00 0.00 0.00

Memasang 1 buah Kunci Tanam Biasa


1 Memasang 1 buah engsel pintu bh 15.00 ###
2 Memasang 1 buah engsel jendela Kupu-kupu bh 12.00 ###
3 Memasang 1 buah kait angin bh 12.00 ###
4 Memasang 1 buah gerendel (Pendek) Pintu bh 5.00 ###
5 Memasang 1 buah gerendel Jendela bh 6.00 ###
6 0.00 0.00 0.00 0.00

1 Memasang 1 m2 lantai keramik polos (20x20) cm


2 Memasang 1 m2 lapis seng plat bjls 0.30 dinding & m2 9.27 ###
3 0.00 0.00 0.00 0.00

1 m2 mengecat bidang kayu baru


1 1 m2 Pengecetan tembok baru m2 190.52 ###
2 1 m2 pengecetan plafond baru menggunakan peranc m2 66.80 ###
3 0.00 0.00 0.00 0.00

Pembersihan lokasi
1 Dokumnetasi & Pelaporan ls 1.00 ###
2 0.00 0.00 0.00 0.00

RENCANA Rp.
KOMULATIF RENCANA
JADWAL PELAKSANAAN
TEN MAMBERAMO RAYA

JUMLAH WAKTU PELAKSANAAN


HARGA BULAN KE I BULAN KE II
BOBOT
1 2 3 4 5 6
(Rp.)

11,773,443.00
4,038,243.00 #DIV/0! #DIV/0!
4,435,200.00 #DIV/0! #DIV/0!
1,500,000.00 #DIV/0! #DIV/0!
1,800,000.00 #DIV/0! #DIV/0!
- #DIV/0! #DIV/0!

178,464.00
178,464.00 #DIV/0! #DIV/0!
- #DIV/0! #DIV/0!

35,742,846.97
2,605,272.63 #DIV/0! #DIV/0! #DIV/0! 1.597
3,164,047.23 #DIV/0! #DIV/0!
723,803.73 #DIV/0! #DIV/0!
5,475,232.13 #DIV/0! #DIV/0!
23,774,491.25 #DIV/0! #DIV/0! #DIV/0!
- #DIV/0! #DIV/0!

110,795,159.42
1,691,298.53 #DIV/0!
6,259,631.13 #DIV/0!
6,260,879.95 #DIV/0!
1,065,000.66 #DIV/0!
1,615,613.93 #DIV/0!
4,194,309.22 #DIV/0!
5,279,273.62 #DIV/0!
10,388,599.35 #DIV/0!
3,143,324.41 #DIV/0!
2,514,659.53 #DIV/0!
19,689,810.07 #DIV/0!
31,946,235.30 #DIV/0!
16,746,523.73 #DIV/0!
- #DIV/0!

-
- #DIV/0! #DIV/0!

1,940,000.00
1,940,000.00 #DIV/0!
- #DIV/0!

4,279,176.00
4,279,176.00 #DIV/0!
- #DIV/0!

2,433,750.00
599,225.00 #DIV/0!
632,225.00 #DIV/0!
915,337.50 #DIV/0!
286,962.50 #DIV/0!
- #DIV/0!

9,100,069.80
2,715,000.00 #DIV/0!
56,430.00 #DIV/0!
925,500.00 #DIV/0!
431,450.00 #DIV/0!
629,607.00 #DIV/0!
4,342,082.80 #DIV/0!
- #DIV/0!

13,986,467.36
1,271,467.36 #DIV/0! #DIV/0!
9,500,000.00 #DIV/0!
3,215,000.00 #DIV/0!
- #DIV/0!

9,899,303.50
2,782,500.00 #DIV/0!
2,358,660.00 #DIV/0!
2,389,629.00 #DIV/0!
1,041,700.00 #DIV/0!
1,326,814.50 #DIV/0!
- #DIV/0!

1,935,102.02
1,935,102.02 #DIV/0!
- #DIV/0!

8,131,744.51
6,241,682.88 #DIV/0!
1,890,061.63 #DIV/0!
- #DIV/0!

2,200,000.00
2,200,000.00 #DIV/0!
- #DIV/0!

212,395,526.59 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!


0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
WAKTU PELAKSANAAN
BULAN KE II BULAN KE III
KETERANGAN
7 8 9 10 11 12

3 Bulan x 30 hari
= 90 Hari
1 Minggu = 7 Hari

#DIV/0! #DIV/0! 1.268

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0! #DIV/0! #DIV/0! 0.373
#DIV/0! #DIV/0! #DIV/0! 0.534
#DIV/0! #DIV/0! 1.680

#DIV/0! #DIV/0! 1.560


#DIV/0!

#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!
#DIV/0!

#DIV/0!
#DIV/0!

#DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!


#DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KABUPATEN MAMBERAMO RAYA

ANALISA HARGA SATUAN PEKERJAAN


TAHUN ANGGARAN 2019

NO URAIAN PEKERJAAN KOEF


1 2 3
A.2.2.1 PEKERJAAN PERSIAPAN
A.2.2.1.4 Mengerjakan 1 m² pengukuran dan pemasangan bouwplank
A. Bahan
Kayu Meranti Batu 5/7 (ikat) 0,012
Paku Biasa 2" - 5" 0,020
Kayu Papan Meranti Batu (2 x 20 x 400) 0,007
Jumlah harga bahan
B. Tenaga
Pekerja 0,100
Tukang Kayu 0,100
Kepala Tukang 0,010
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.2.3.1 PEKERJAAN TANAH


A.2.3.1.1 Menggali 1 m³ tanah biasa sedalam 1 meter
A. Bahan
Jumlah harga bahan
B. Tenaga
Pekerja 0,750
Mandor 0,025
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.2.3.1.9 Mengurug kembali 1 m³ galian sedalam 1 m


A. Bahan
Jumlah harga bahan
B. Tenaga
Pekerja 0,500
Mandor 0,050
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.2.3.1.11 Mengurug 1 m³ pasir urug


A. Bahan
Pasir Urug 1,200
Jumlah harga bahan
B. Tenaga
Pekerja 0,300
Mandor 0,010
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.2.3.1.11.a Mengurug 1 m³ tanah urug


A. Bahan
Tanah Urug 1,200
Jumlah harga bahan
B. Tenaga
Pekerja 0,300
Mandor 0,010
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.3.2.1 PEKERJAAN PONDASI


A.3.2.1.2 Memasang 1 m³ pondasi batu belah; campuran 1 PC : 4 PP
A. Bahan
Batu Belah 15/20 cm 1,200
Portland Cement (PC) 163,000
Pasir Pasang (PP) 0,520
Jumlah harga bahan
B. Tenaga
Pekerja 1,500
Tukang Batu 0,750
Kepala Tukang 0,075
Mandor 0,075
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.3.2.1.9 Memasang 1 m³ batu kosong (aanstampeeng)


A. Bahan
Batu Belah 15/20 1,200
Pasir Urug 0,432
Jumlah harga bahan
B. Tenaga
Pekerja 0,780
Tukang Batu 0,390
Kepala Tukang 0,039
Mandor 0,039
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.4.1 PEKERJAAN PASANGAN DINDING


A.4.4.1.9 Memasang 1 m² dinding batu tela; tebal ½ bata; campuran 1 PC : 4 PP
A. Bahan
Batu Tela 18,000
Portland Cement (PC) 11,500
Pasir Pasang (PP) 0,043
Jumlah harga bahan
B. Tenaga
Pekerja 0,300
Tukang Batu 0,100
Kepala Tukang 0,010
Mandor 0,015
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.44.2 PEKERJAAN PLESTERAN


A.44.2.4 Memasang 1 m² plesteran 1 PC : 4 PP; tebal 15 mm
A. Bahan
Portland Cement (PC) 6,240
Pasir Pasang 0,024
Jumlah harga bahan
B. Tenaga
Pekerja 0,300
Tukang Batu 0,150
Kepala Tukang 0,015
Mandor 0,015
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.44.2.20 Memasang 1 m' plesteran skoning 1 Pc : 2 PP; lebar 10 mm


A. Bahan
Portland Cement (PC) 0,500
Pasir Pasang (PP) 0,013
Jumlah harga bahan
B. Tenaga
Pekerja 0,080
Tukang Batu 0,400
Kepala Tukang 0,040
Mandor 0,004
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.44.2.27 Memasang 1 m² acian


A. Bahan
Portland Cement (PC) 3,250
Jumlah harga bahan
B. Tenaga
Pekerja 0,200
Tukang Batu 0,100
Kepala Tukang 0,010
Mandor 0,010
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1 PEKERJAAN KAYU


A.4.6.1.1 Membuat dan memasang 1 m³ kusen pintu dan kusen jendela, kayu kelas I
A. Bahan
Balok Kayu kelas I 1,100
Paku 10 cm 1,250
Lem kayu 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 7,000
Tukang Kayu 21,000
Kepala Tukang 2,100
Mandor 0,350
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.5 Membuat dan memasang 1 m² daun pintu panel, kayu kelas I


A. Bahan
Papan kayu Besi 0,040
Lem kayu 0,500
Jumlah harga bahan
B. Tenaga
Pekerja 1,000
Tukang Kayu 3,000
Kepala Tukang 0,300
Mandor 0,050
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.6 Membuat dan memasang 1 m² pintu dan jendela kaca 5 mm, kayu kelas I
A. Bahan
Papan kayu Jati 0,024
Kaca Bening 5 mm 0,800
Lem kayu 0,300
Jumlah harga bahan
B. Tenaga
Pekerja 0,800
Tukang Kayu 2,400
Kepala Tukang 0,240
Mandor 0,040
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.8 Membuat 1 m² daun pintu plywood rangkap, rangka tertutup kayu kelas II
A. Bahan
Papan Kayu Kamper 0,025
Paku 1 cm - 2,5 cm 0,030
Lem Kayu 0,500
plywood tebal 3 mm ukuran (90 x 220) cm 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,700
Tukang Kayu 2,100
Kepala Tukang 0,210
Mandor 0,035
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.14 Memasang 1 m³ kontruksi kuda-kuda expose, kayu kelas I ( kayu besi )


A. Bahan
Balok Kayu Jati 1,200
Besi strip tebal 5 mm 15,000
Paku 12 cm 5,600
Jumlah harga bahan
B. Tenaga
Pekerja 6,700
Tukang Kayu 20,100
Kepala Tukang 2,010
Mandor 0,335
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.15 Memasang 1 m³ kontruksi gording, kayu kelas II


A. Bahan
Balok Kayu Kamper 1,100
Besi Strip 5 mm 15,000
Paku 12 cm 3,000
Jumlah harga bahan
B. Tenaga
Pekerja 6,700
Tukang Kayu 20,100
Kepala Tukang 2,010
Mandor 0,335
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.20 Memasang 1 m² rangka langit-langit (60 x 60) cm, kayu kelas II


A. Bahan
Kaso-kaso (5 x 7) cm kayu Kamper 0,0163
Paku 5 cm & 10 cm 0,250
Jumlah harga bahan
B. Tenaga
Pekerja 0,200
Tukang Kayu 0,300
Kepala Tukang 0,030
Mandor 0,010
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.1.22 Memasang 1 m' lisplank ukuran (3 x 30) cm, kayu kelas I ( kayu besi )
A. Bahan
Papan kayu Jati 0,011
Paku 5 cm - 7 cm 0,050
Jumlah harga bahan
B. Tenaga
Pekerja 0,100
Tukang Kayu 0,200
Kepala Tukang 0,020
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.1.1 PEKERJAAN BETON


A.4.1.1.29 Membuat 1 m³ sloof beton bertulang (200 kg besi + bekisting) menggunakan batu pecah tangan
A. Bahan
Kayu kelas III 0,270
Paku 5 cm - 12 cm 2,000
Minyak Bekisting 0,600
Besi Beton (polos/ulir) 210,000
Kawat Beton 3,000
Portland Cement (PC) 336,000
Pasir Beton (PB) 0,540
Koral Beton (maksimum 30 mm) pecah tangan 0,810
Jumlah harga bahan
B. Tenaga
Pekerja 5,650
Tukang Batu 0,275
Tukang Kayu 1,560
Tukang Besi 1,400
Kepala Tukang 0,323
Mandor 0,283
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.1.1.32 Membuat 1 m³ kolom beton bertulang (150 kg besi + bekisting) menggunakan batu pecah tangan
A. Bahan
Kayu kelas III 0,320
Paku 5 cm - 12 cm 3,200
Minyak Bekisting 1,600
Besi Beton (polos/ulir) 157,500
Kawat Beton 2,250
Portland Cement (PC) 336,000
Pasir Beton (PB) 0,540
Koral Beton (maksimum 30 mm) pecah tangan 0,810
Balok kayu kelas II 0,120
Plywood tebal 9 mm 2,800
Dolken Ø (8-10) cm panjang 4 m 32,000
Jumlah harga bahan
B. Tenaga
Pekerja 5,300
Tukang Batu 0,275
Tukang Kayu 1,300
Tukang Besi 1,050
Kepala Tukang 0,265
Mandor 0,265
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.1.1.33 Membuat 1 m³ dinding beton bertulang (150 kg besi + bekisting) menggunakan batu pecah tangan
A. Bahan
Kayu kelas III 0,240
Paku 5 cm - 12 cm 3,200
Minyak Bekisting 1,600
Besi Beton (polos/ulir) 157,500
Kawat Beton 2,250
Portland Cement (PC) 336,000
Pasir Beton (PB) 0,540
Koral Beton (maksimum 30 mm) pecah tangan 0,810
Balok Kayu Meranti Batu 5/7 0,160
Plywood tebal 9 mm 2,800
Dolken Ø (8-10) cm panjang 4 m 24,000
Jumlah harga bahan
B. Tenaga
Pekerja 5,300
Tukang Batu 0,275
Tukang Kayu 1,300
Tukang Besi 1,050
Kepala Tukang 0,262
Mandor 0,265
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10 x 15 cm) menggunakan batu pecah tangan
A. Bahan
Kayu Pinus / Kayu Rawa 0,003
Paku 5 cm - 12 cm 0,020
Besi Beton (polos/ulir) 3,600
Kawat Beton 0,050
Portland Cement (PC) 5,500
Pasir Beton (PB) 0,009
Koral Beton (maksimum 30 mm) pecah tangan 0,015
Jumlah harga bahan
B. Tenaga
Pekerja 0,297
Tukang Batu 0,033
Tukang Kayu 0,033
Tukang Besi 0,033
Kepala Tukang 0,010
Mandor 0,015
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

G.1 PEKERJAAN BETON


G.042 Membuat 1 m³ beton tumbuk 1 PC : 3 PB : 5 KR menggunakan batu split pecah tangan
Bahan
Portland Cement (PC) 2,180,000
Pasir Beton (PB) 0,5200
Koral Beton (maksimum 30 mm) pecah tangan 0,8700

Tenaga
Pekerja 16,500
Tukang Batu 0,2500
Kepala Tukang 0,0250
Mandor 0,0800

Jumlah (1) + (2)

A.4.5.2 PEKERJAAN PENUTUP ATAP


A.4.5.2.40 Memasang 1 m² penutup atap spandek warna ( zingkalume ), BJLS 0.30
A. Bahan
Atap Spandek bjls 0.30 1,050
Paku hak pj. 15 cm 0,020
Jumlah harga bahan
B. Tenaga
Pekerja 0,150
Tukang Kayu 0,075
Kepala Tukang 0,008
Mandor 0,006
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.2.41 Memasang 1 m' nok bubung spandek warna BJLS 0.30


A. Bahan
Bubungan Spandek Warna Bjls 0.30 1,200
Angker baut 0,040
Jumlah harga bahan
B. Tenaga
Pekerja 0,150
Tukang Kayu 0,070
Kepala Tukang 0,008
Mandor 0,006
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.1 PEKERJAAN LANGIT - LANGIT ( PLAFOND )


A.4.5.1.5 Memasang 1 m² langit-langit tripleks ukuran (120 x 240 ) cm; tbl. 3 mm, 4 mm, 6 mm
A. Bahan
Triplek tebal 3 mm ( 120 x 240 ) 0,375
Paku Triplek 0,030
Jumlah harga bahan
B. Tenaga
Pekerja 0,100
Tukang Kayu 0,100
Kepala Tukang 0,010
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.1.9 Memasang 1 m' list langit-langit kayu profil


A. Bahan
List Kayu Profil 1,050
Paku Triplek 0,010
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Kayu 0,050
Kepala Tukang 0,005
Mandor 0,003
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.3 PEKERJAAN INSTALASI LISTRIK


A.4.5.3.1 Memasang 1 ttk lampu SL 18 watt
A. Bahan
Lampu SL 18 watt 1,000
Kabel NYM 2x2,5 5,000
Fitting lampu 1,000
Pipa Kabel 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Listrik 0,250
Kepala Tukang 0,025
Mandor 0,008
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.3.2 Memasang 1 ttk saklar tunggal


A. Bahan
saklar tunggal 1,000
Kabel NYM 2x2,5 5,000
Pipa Kabel 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Listrik 0,250
Kepala Tukang 0,025
Mandor 0,008
Jumlah harga tenaga
C. Peralatan 0,3500
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.3.3 Memasang 1 ttk saklar ganda


A. Bahan
saklar ganda 1,000
Kabel NYM 2x2,5 5,000
Pipa Kabel 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Listrik 0,250
Kepala Tukang 0,025
Mandor 0,008
Jumlah harga tenaga
C. Peralatan 0,3500
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.3.4 Memasang 1 ttk stop kontak


A. Bahan
stop kontak 1,000
Kabel NYM 2x2,5 7,500
Pipa Kabel 1,667
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Listrik 0,250
Kepala Tukang 0,025
Mandor 0,008
Jumlah harga tenaga
C. Peralatan 0,3500
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.5.3.5 Memasang 1 bh box sekring


A. Bahan
box sekring 1,000
Kabel NYM 2x2,5 7,500
Pipa Kabel 1,667
Jumlah harga bahan
B. Tenaga
Pekerja 0,050
Tukang Listrik 0,250
Kepala Tukang 0,025
Mandor 0,008
Jumlah harga tenaga
C. Peralatan 0,3500
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.2 Memasang 1 buah closet jongkok porselen INA warna tua
A. Bahan
Closet Jongkok INA warna tua 1,000
Portland Cement (PC) 6,000
Pasir Pasang 0,010
Jumlah harga bahan
B. Tenaga
Pekerja 1,000
Tukang Batu 1,500
Kepala Tukang 0,150
Mandor 0,160
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.7 Memasang 1 buah bak mandi fibreglass volume 1,00 m³


A. Bahan
Bak Fibreglass 1,000
Perlengkapan 12% harga bak
Jumlah harga bahan
B. Tenaga
Pekerja 0,300
Tukang Batu 0,450
Kepala Tukang 0,045
Mandor 0,150
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.14 Memasang 1 buah floor drain


A. Bahan
Floordrain 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,010
Tukang Batu 0,100
Kepala Tukang 0,010
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.18 Memasang 1 m' pipa galvanis Ø ½"


A. Bahan
Pipa Galvanis 1,200
Perlengkapan 35% harga pipa
Jumlah harga bahan
B. Tenaga
Pekerja 0,054
Tukang Batu 0,090
Kepala Tukang 0,009
Mandor 0,027
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.19.a Memasang 1 buah kran Ø ¾" atau ½" kualitas baik


A. Bahan
Kran Air kualitas baik 1,000
Seal Tape 0,025
Jumlah harga bahan
B. Tenaga
Pekerja 0,010
Tukang Batu 0,400
Kepala Tukang 0,040
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.29 Memasang 1 m' pipa PVC tipe AW Ø 2"


A. Bahan
Pipa PVC 1,200
Perlengkapan 35% harga pipa
Jumlah harga bahan
B. Tenaga
Pekerja 0,054
Tukang Batu 0,090
Kepala Tukang 0,009
Mandor 0,003
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.5.1.1.32 Memasang 1 m' pipa PVC tipe AW Ø 4"


A. Bahan
Pipa PVC 1,200
Perlengkapan 35% harga pipa
Jumlah harga bahan
B. Tenaga
Pekerja 0,081
Tukang Batu 0,135
Kepala Tukang 0,0135
Mandor 0,004
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

J.1 PEKERJAAN SANITASI


J.041 Membuat 1 unit septic tank ukuran 1,5 x 1 x 1,5 m + rembesan (rumah tipe kecil)
Galian Tanah ( B.001) 22,500
Urugan Pasir urug (B.012) 0,1071
Lantai kerja beton 1:3:5 (G.035) 11,250
Pas. Batu bata 1 PC : 2 PS + Plesteran (D.002) 75,000
Plat beton bertulang 1:2:3 penutup dan balok (G.023) 0,1500
Pipa PVC 4" jenis AW + sambungan (J.029) 90,000
Pipa GIP 1 1/2" (j.019) 0,6000
Galian tanah untuk rembesan (B.001) 16,875
Pasang Ijuk (B.015) 27,000
Urugan kerikil 3-5 cm. (B.016) 0,5250
Pipa PVC 4" berlobang jenis AW (J.029) 90,000
Urugan kembali perataan tanah (B.010) 0,5625
Tambahan upah 0,0650

K. PEKERJAAN TALANG DAN JURAI SENG PLAT


K.015 Memasang 1 m' talang ½ lingkaran Ø 10 cm, seng BJLS 30, 90 cm
Bahan
Seng Plat 3' x 6 ' BJLS 30, lebar 90 cm 0,300
Paku Biasa ½" - 1" atau sekrup 0,100
Kayu Papan Cetak 0,019
Besi Strip 0,500

Tenaga
Pekerja 0,150
Tukang Kayu 0,250
Kepala Tukang 0,025
Mandor 0,00125

Jumlah (1) + (2)

A.4.6.2 PEKERJAAN KUNCI DAN KACA


A.4.6.2.2 Memasang 1 buah kunci tanam biasa
A. Bahan
Kunci Tanam Biasa 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,010
Tukang Kayu 0,500
Kepala Tukang 0,050
Mandor 0,005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.2.5 Memasang 1 buah engsel pintu


A. Bahan
Engsel Pintu kuningan 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,015
Tukang Kayu 0,150
Kepala Tukang 0,015
Mandor 0,0008
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.2.6 Memasang 1 buah engsel jendela kupu - kupu


A. Bahan
Engsel kupu - kupu 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,010
Tukang Kayu 0,100
Kepala Tukang 0,010
Mandor 0,0005
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.2.9 Memasang 1 buah kait angin


A. Bahan
Kait Angin Ø 6" 1,000
Jumlah harga bahan
B. Tenaga
Pekerja 0,015
Tukang Kayu 0,150
Kepala Tukang 0,015
Mandor 0,008
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.6.2.17 Memasang 1 m² kaca bening tebal 5 mm


A. Bahan
Kaca bening 5 mm 1,100
Sealant 0,050
Jumlah harga bahan
B. Tenaga
Pekerja 0,015
Tukang Kayu 0,150
Kepala Tukang 0,015
Mandor 0,0008
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

L. PEKERJAAN KUNCI DAN KACA


L.011 Memasang 1 buah gerendel (pendek) pintu
Bahan
Gerendel pendek pintu 1,000

Tenaga
Pekerja 0,000
Tukang Kayu 0,100
Kepala Tukang 0,010
Mandor 0,000

Jumlah (1) + (2)

L.013 Memasang 1 buah gerendel jendela


Bahan
Gerendel jendela 1,000

Tenaga
Pekerja 0,000
Tukang Kayu 0,100
Kepala Tukang 0,010
Mandor 0,000

Jumlah (1) + (2)

A.4.4.3.1 PEKERJAAN PENUTUP LANTAI DAN DINDING


A.4.4.3.35.c Memasang 1 m² lantai keramik polos (40 x 40) cm
A. Bahan
keramik 40 x 40 cm polos 6,630
Portland Cement (PC) 9,800
Pasir Pasang (PP) 0,045
Semen Warna 1,300
Jumlah harga bahan
B. Tenaga
Pekerja 0,700
Tukang Batu 0,350
Kepala Tukang 0,035
Mandor 0,035
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.4.3.36 Memasang 1 m² lantai keramik polos (20 x 20) cm


A. Bahan
keramik 20 x 20 cm polos 26,500
Portland Cement (PC) 10,400
Pasir Pasang (PP) 0,045
Semen Warna 1,620
Jumlah harga bahan
B. Tenaga
Pekerja 0,700
Tukang Batu 0,350
Kepala Tukang 0,035
Mandor 0,035
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.4.3.54.b Memasang 1 m² dinding keramik polos ukuran 20 x 25 cm


A. Bahan
Keramik 20 x 25 cm polos 20,000
Portland Cement (PC) 9,300
Pasir Pasang (PP) 0,018
Semen Warna 1,940
Jumlah harga bahan
B. Tenaga
Pekerja 0,900
Tukang Batu 0,450
Kepala Tukang 0,045
Mandor 0,045
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.4.3.60 Memasang 1 m² lapis seng plat BJLS 0.30


A. Bahan
seng plat bjls 0.30 0,679
paku 0,100
Jumlah harga bahan
B. Tenaga
Pekerja 0,350
Tukang Batu 0,175
Kepala Tukang 0,017
Mandor 0,002
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.7.1 PEKERJAAN PENGECATAN


A.4.7.1.5 1 m² mengecat bidang kayu baru ( 1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup )
A. Bahan
Cat menie 0,200
Plamur 0,150
Cat dasar 0,170
Cat penutup 0,350
kuas cat 3' 0,010
minyak cat ( pengencer ) 0,030
Ampelas 0,200
Jumlah harga bahan
B. Tenaga
Pekerja 0,070
Tukang Cat 0,105
Kepala Tukang 0,004
Mandor 0,003
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.7.1.10 1 m² pengecetan tembok baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup )
A. Bahan
plamir tembok 0,100
cat dasar 0,100
cat tembok 0,260
Jumlah harga bahan
B. Tenaga
Pekerja 0,020
Tukang Cat 0,063
Kepala Tukang 0,0063
Mandor 0,003
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )

A.4.7.1.10.a 1 m² pengecetan plafond baru menggunakan perancah (1lapis plamur, 1lapis cat dasar, 2lapis cat penutup)
A. Bahan
plamir tembok 0,100
cat dasar 0,100
cat tembok 0,260
Perancah kayu 0,002
Jumlah harga bahan
B. Tenaga
Pekerja 0,020
Tukang Cat 0,063
Kepala Tukang 0,0063
Mandor 0,003
Jumlah harga tenaga
C. Peralatan
Jumlah harga peralatan
D. Jumlah ( A + B + C )
E. Overhead and profit 10 %
F. Harga satuan pekerjaan ( D + E )
N RUANG
A

HARGA SAT JUMLAH


SAT
Rp. Rp.
4 5 6

m³ 2.950.000,00 35.400,00
kg 40.000,00 800,00
m³ 2.950.000,00 20.650,00
lah harga bahan 56.850,00

OH 130.000,00 13.000,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 1.500,00
lah harga tenaga 34.800,00
-
lah harga peralatan -
91.650,00
9.165,00
100.815,00

-
lah harga bahan -

OH 130.000,00 97.500,00
OH 300.000,00 7.500,00
lah harga tenaga 105.000,00
-
lah harga peralatan -
105.000,00
10.500,00
115.500,00

-
lah harga bahan -

OH 130.000,00 65.000,00
OH 300.000,00 15.000,00
lah harga tenaga 80.000,00
-
lah harga peralatan -
80.000,00
8.000,00
88.000,00

m³ 800.000,00 960.000,00
lah harga bahan 960.000,00

OH 130.000,00 39.000,00
OH 300.000,00 3.000,00
lah harga tenaga 42.000,00
-
lah harga peralatan -
1.002.000,00
100.200,00
1.102.200,00

m³ 600.000,00 720.000,00
lah harga bahan 720.000,00

OH 130.000,00 39.000,00
OH 300.000,00 3.000,00
lah harga tenaga 42.000,00
-
lah harga peralatan -
762.000,00
76.200,00
838.200,00

m³ 800.000,00 960.000,00
kg 5.500,00 896.500,00
m³ 800.000,00 416.000,00
lah harga bahan 2.272.500,00

OH 130.000,00 195.000,00
OH 180.000,00 135.000,00
OH 230.000,00 17.250,00
OH 300.000,00 22.500,00
lah harga tenaga 369.750,00
-
Jumlah harga peralatan -
2.642.250,00
264.225,00
2.906.475,00

m³ 800.000,00 960.000,00
m³ 800.000,00 345.600,00
lah harga bahan 1.305.600,00

OH 130.000,00 101.400,00
OH 180.000,00 70.200,00
OH 230.000,00 8.970,00
OH 300.000,00 11.700,00
lah harga tenaga 192.270,00
-
Jumlah harga peralatan -
1.497.870,00
149.787,00
1.647.657,00

buah 12.000,00 216.000,00


kg 5.500,00 63.250,00
m³ 800.000,00 34.400,00
lah harga bahan 313.650,00

OH 130.000,00 39.000,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 4.500,00
lah harga tenaga 63.800,00
-
Jumlah harga peralatan -
377.450,00
37.745,00
415.195,00

kg 5.500,00 34.320,00
m³ 800.000,00 19.200,00
lah harga bahan 53.520,00

OH 130.000,00 39.000,00
OH 180.000,00 27.000,00
OH 230.000,00 3.450,00
OH 300.000,00 4.500,00
lah harga tenaga 73.950,00
-
lah harga peralatan -
127.470,00
12.747,00
140.217,00

kg 5.500,00 2.750,00
m³ 800.000,00 10.400,00
lah harga bahan 13.150,00

OH 130.000,00 10.400,00
OH 180.000,00 72.000,00
OH 230.000,00 9.200,00
OH 300.000,00 1.200,00
lah harga tenaga 92.800,00
-
lah harga peralatan -
105.950,00
10.595,00
116.545,00

kg 5.500,00 17.875,00
lah harga bahan 17.875,00

OH 130.000,00 26.000,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 3.000,00
lah harga tenaga 49.300,00
-
lah harga peralatan -
67.175,00
6.717,50
73.892,50

m³ 4.000.000,00 4.400.000,00
kg 40.000,00 50.000,00
kg 30.000,00 30.000,00
lah harga bahan 4.480.000,00

OH 130.000,00 910.000,00
OH 180.000,00 3.780.000,00
OH 230.000,00 483.000,00
OH 300.000,00 105.000,00
lah harga tenaga 5.278.000,00
-
Jumlah harga peralatan -
9.758.000,00
975.800,00
10.733.800,00

m³ 4.000.000,00 160.000,00
kg 30.000,00 15.000,00
lah harga bahan 175.000,00

OH 130.000,00 130.000,00
OH 180.000,00 540.000,00
OH 230.000,00 69.000,00
OH 300.000,00 15.000,00
lah harga tenaga 754.000,00
-
Jumlah harga peralatan -
929.000,00
92.900,00
1.021.900,00

m³ 4.000.000,00 96.000,00
m2 240.000,00 192.000,00
kg 30.000,00 9.000,00
lah harga bahan 297.000,00

OH 130.000,00 104.000,00
OH 180.000,00 432.000,00
OH 230.000,00 55.200,00
OH 300.000,00 12.000,00
lah harga tenaga 603.200,00
-
Jumlah harga peralatan -
900.200,00
90.020,00
990.220,00

m³ 3.500.000,00 87.500,00
kg 40.000,00 1.200,00
kg 30.000,00 15.000,00
lembar 130.000,00 130.000,00
lah harga bahan 233.700,00

OH 130.000,00 91.000,00
OH 180.000,00 378.000,00
OH 230.000,00 48.300,00
OH 300.000,00 10.500,00
lah harga tenaga 527.800,00
-
Jumlah harga peralatan -
761.500,00
76.150,00
837.650,00

m³ 4.000.000,00 4.800.000,00
kg 75.000,00 1.125.000,00
kg 40.000,00 224.000,00
lah harga bahan 6.149.000,00

OH 130.000,00 871.000,00
OH 180.000,00 3.618.000,00
OH 230.000,00 462.300,00
OH 300.000,00 100.500,00
lah harga tenaga 5.051.800,00
-
Jumlah harga peralatan -
11.200.800,00
1.120.080,00
12.320.880,00

m³ 3.500.000,00 3.850.000,00
kg 75.000,00 1.125.000,00
kg 40.000,00 120.000,00
lah harga bahan 5.095.000,00

OH 130.000,00 871.000,00
OH 180.000,00 3.618.000,00
OH 230.000,00 462.300,00
OH 300.000,00 100.500,00
lah harga tenaga 5.051.800,00
-
Jumlah harga peralatan -
10.146.800,00
1.014.680,00
11.161.480,00

m³ 3.500.000,00 57.050,00
kg 40.000,00 10.000,00
lah harga bahan 67.050,00

OH 130.000,00 26.000,00
OH 180.000,00 54.000,00
OH 230.000,00 6.900,00
OH 300.000,00 3.000,00
lah harga tenaga 89.900,00
-
lah harga peralatan -
156.950,00
15.695,00
172.645,00

m³ 4.000.000,00 44.000,00
kg 40.000,00 2.000,00
lah harga bahan 46.000,00

OH 130.000,00 13.000,00
OH 180.000,00 36.000,00
OH 230.000,00 4.600,00
OH 300.000,00 1.500,00
lah harga tenaga 55.100,00
-
lah harga peralatan -
101.100,00
10.110,00
111.210,00

m³ 2.950.000,00 796.500,00
kg 40.000,00 80.000,00
liter 8.000,00 4.800,00
kg 30.000,00 6.300.000,00
kg 45.000,00 135.000,00
kg 5.500,00 1.848.000,00
m³ 800.000,00 432.000,00
m³ 800.000,00 648.000,00
lah harga bahan 10.244.300,00

OH 130.000,00 734.500,00
OH 180.000,00 49.500,00
OH 180.000,00 280.800,00
OH 180.000,00 252.000,00
OH 230.000,00 74.290,00
OH 300.000,00 84.900,00
lah harga tenaga 1.475.990,00
-
Jumlah harga peralatan -
11.720.290,00
1.172.029,00
12.892.319,00

m³ 2.950.000,00 944.000,00
kg 40.000,00 128.000,00
liter 8.000,00 12.800,00
kg 30.000,00 4.725.000,00
kg 45.000,00 101.250,00
kg 5.500,00 1.848.000,00
m³ 800.000,00 432.000,00
m³ 800.000,00 648.000,00
m³ 2.950.000,00 354.000,00
lembar 300.000,00 840.000,00
batang 12.000,00 384.000,00
lah harga bahan 10.417.050,00

OH 130.000,00 689.000,00
OH 180.000,00 49.500,00
OH 180.000,00 234.000,00
OH 180.000,00 189.000,00
OH 230.000,00 60.950,00
OH 300.000,00 79.500,00
lah harga tenaga 1.301.950,00
-
Jumlah harga peralatan -
11.719.000,00
1.171.900,00
12.890.900,00

m³ 2.950.000,00 708.000,00
kg 40.000,00 128.000,00
liter 8.000,00 12.800,00
kg 30.000,00 4.725.000,00
kg 45.000,00 101.250,00
kg 5.500,00 1.848.000,00
m³ 800.000,00 432.000,00
m³ 800.000,00 648.000,00
m³ 2.950.000,00 472.000,00
lembar 300.000,00 840.000,00
batang 12.000,00 288.000,00
lah harga bahan 10.203.050,00

OH 130.000,00 689.000,00
OH 180.000,00 49.500,00
OH 180.000,00 234.000,00
OH 180.000,00 189.000,00
OH 230.000,00 60.260,00
OH 300.000,00 79.500,00
lah harga tenaga 1.301.260,00
-
Jumlah harga peralatan -
11.504.310,00
1.150.431,00
12.654.741,00

m³ 2.950.000,00 8.850,00
kg 40.000,00 800,00
kg 30.000,00 108.000,00
kg 45.000,00 2.250,00
kg 5.500,00 30.250,00
m³ 800.000,00 7.200,00
m³ 800.000,00 12.000,00
lah harga bahan 169.350,00
OH 130.000,00 38.610,00
OH 180.000,00 5.940,00
OH 180.000,00 5.940,00
OH 180.000,00 5.940,00
OH 230.000,00 2.300,00
OH 300.000,00 4.500,00
lah harga tenaga 63.230,00
-
Jumlah harga peralatan -
232.580,00
23.258,00
255.838,00

RSNI-T-13-2002

kg 5.500,00 1.199.000,00
m³ 800.000,00 416.000,00
m³ 800.000,00 696.000,00
Jumlah (1) 2.311.000,00

OH 130.000,00 214.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 24.000,00
Jumlah (2) 289.250,00
2.600.250,00

m2 105.000,00 110.250,00
kg 40.000,00 800,00
lah harga bahan 111.050,00

OH 130.000,00 19.500,00
OH 180.000,00 13.500,00
OH 230.000,00 1.840,00
OH 300.000,00 1.800,00
lah harga tenaga 36.640,00
-
Jumlah harga peralatan -
147.690,00
14.769,00
162.459,00

bh 70.000,00 84.000,00
kg 40.000,00 1.600,00
lah harga bahan 85.600,00
OH 130.000,00 19.500,00
OH 180.000,00 12.600,00
OH 230.000,00 1.840,00
OH 300.000,00 1.800,00
lah harga tenaga 35.740,00
-
Jumlah harga peralatan -
121.340,00
12.134,00
133.474,00

lbr 41.319,44 15.494,79


kg 40.000,00 1.200,00
lah harga bahan 16.694,79

OH 130.000,00 13.000,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 1.500,00
lah harga tenaga 34.800,00
-
lah harga peralatan -
51.494,79
5.149,48
56.644,27

m' 20.000,00 21.000,00


kg 40.000,00 400,00
lah harga bahan 21.400,00

OH 130.000,00 6.500,00
OH 180.000,00 9.000,00
OH 230.000,00 1.150,00
OH 300.000,00 900,00
lah harga tenaga 17.550,00
-
lah harga peralatan -
38.950,00
3.895,00
42.845,00

bh 80.000,00 80.000,00
m 25.000,00 125.000,00
bh 50.000,00 50.000,00
btg 42.000,00 42.000,00
lah harga bahan 297.000,00

OH 130.000,00 6.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 2.250,00
lah harga tenaga 59.500,00
-
lah harga peralatan -
356.500,00
35.650,00
392.150,00

bh 53.000,00 53.000,00
m 25.000,00 125.000,00
btg 42.000,00 42.000,00
lah harga bahan 220.000,00

OH 130.000,00 6.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 2.250,00
lah harga tenaga 59.500,00
set 53.000,00 18.550,00
lah harga peralatan 18.550,00
298.050,00
29.805,00
327.855,00

bh 55.000,00 55.000,00
m 25.000,00 125.000,00
btg 42.000,00 42.000,00
lah harga bahan 222.000,00

OH 130.000,00 6.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 2.250,00
lah harga tenaga 59.500,00
set 55.000,00 19.250,00
lah harga peralatan 19.250,00
300.750,00
30.075,00
330.825,00

bh 52.000,00 52.000,00
m 25.000,00 187.500,00
btg 42.000,00 70.001,40
lah harga bahan 309.501,40

OH 130.000,00 6.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 2.250,00
lah harga tenaga 59.500,00
set 52.000,00 18.200,00
lah harga peralatan 18.200,00
387.201,40
38.720,14
425.921,54

bh 110.000,00 110.000,00
m 25.000,00 187.500,00
btg 42.000,00 70.001,40
lah harga bahan 367.501,40

OH 130.000,00 6.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 2.250,00
lah harga tenaga 59.500,00
set 110.000,00 38.500,00
lah harga peralatan 38.500,00
465.501,40
46.550,14
512.051,54

bh 900.000,00 900.000,00
kg 5.500,00 33.000,00
m³ 800.000,00 8.000,00
lah harga bahan 941.000,00

OH 130.000,00 130.000,00
OH 180.000,00 270.000,00
OH 230.000,00 34.500,00
OH 300.000,00 48.000,00
lah harga tenaga 482.500,00
-
lah harga peralatan -
1.423.500,00
142.350,00
1.565.850,00
bh 1.100.000,00 1.100.000,00
132.000,00 132.000,00
lah harga bahan 1.232.000,00

OH 130.000,00 39.000,00
OH 180.000,00 81.000,00
OH 230.000,00 10.350,00
OH 300.000,00 45.000,00
lah harga tenaga 175.350,00
-
lah harga peralatan -
1.407.350,00
140.735,00
1.548.085,00

bh 45.000,00 45.000,00
lah harga bahan 45.000,00

OH 130.000,00 1.300,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 1.500,00
lah harga tenaga 23.100,00
-
lah harga peralatan -
68.100,00
6.810,00
74.910,00

m' 37.000,00 44.400,00


12.950,00 12.950,00
lah harga bahan 57.350,00

OH 130.000,00 7.020,00
OH 180.000,00 16.200,00
OH 230.000,00 2.070,00
OH 300.000,00 8.100,00
lah harga tenaga 33.390,00
-
lah harga peralatan -
90.740,00
9.074,00
99.814,00

bh 150.000,00 150.000,00
bh 15.000,00 15.000,00
lah harga bahan 165.000,00
OH 130.000,00 1.300,00
OH 180.000,00 72.000,00
OH 230.000,00 9.200,00
OH 300.000,00 1.500,00
lah harga tenaga 84.000,00
-
lah harga peralatan -
249.000,00
24.900,00
273.900,00

m' 38.000,00 45.600,00


13.300,00 13.300,00
lah harga bahan 58.900,00

OH 130.000,00 7.020,00
OH 180.000,00 16.200,00
OH 230.000,00 2.070,00
OH 300.000,00 900,00
lah harga tenaga 26.190,00
-
lah harga peralatan -
85.090,00
8.509,00
93.599,00

m' 123.000,00 147.600,00


43.050,00 43.050,00
lah harga bahan 190.650,00

OH 130.000,00 10.530,00
OH 180.000,00 24.300,00
OH 230.000,00 3.105,00
OH 300.000,00 1.200,00
lah harga tenaga 39.135,00
-
lah harga peralatan -
229.785,00
22.978,50
252.763,50

m³ 115.500,00 259.875,00
m³ 1.102.200,00 118.045,62
m² 266.360,00 299.655,00
m² 616.667,70 4.625.007,75
m³ 10.679.581,00 1.601.937,15
m' 252.763,50 2.274.871,50
m' 207.328,00 124.396,80
m³ 115.500,00 194.906,25
kg 356.400,00 962.280,00
m³ 1.100.000,00 577.500,00
m' 252.763,50 2.274.871,50
m³ 115.500,00 64.968,75
ls 500.000,00 32.500,00
Jumlah 13.410.815,32

SNI 7393 : 2008

lbr 138.000,00 41.400,00


kg 40.000,00 4.000,00
m³ 2.950.000,00 56.050,00
kg 75.000,00 37.500,00
Jumlah (1) 138.950,00

OH 130.000,00 19.500,00
OH 180.000,00 45.000,00
OH 230.000,00 5.750,00
OH 300.000,00 375,00
Jumlah (2) 70.625,00
209.575,00

bh 210.000,00 210.000,00
lah harga bahan 210.000,00

OH 130.000,00 1.300,00
OH 180.000,00 90.000,00
OH 230.000,00 11.500,00
OH 300.000,00 1.500,00
lah harga tenaga 104.300,00
-
lah harga peralatan -
314.300,00
31.430,00
345.730,00

bh 60.000,00 60.000,00
lah harga bahan 60.000,00

OH 130.000,00 1.950,00
OH 180.000,00 27.000,00
OH 230.000,00 3.450,00
OH 300.000,00 240,00
lah harga tenaga 32.640,00
-
lah harga peralatan -
92.640,00
9.264,00
101.904,00

bh 50.000,00 50.000,00
lah harga bahan 50.000,00

OH 130.000,00 1.300,00
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 150,00
lah harga tenaga 21.750,00
-
lah harga peralatan -
71.750,00
7.175,00
78.925,00

bh 30.000,00 30.000,00
lah harga bahan 30.000,00

OH 130.000,00 1.950,00
OH 180.000,00 27.000,00
OH 230.000,00 3.450,00
OH 300.000,00 2.400,00
lah harga tenaga 34.800,00
-
Jumlah harga peralatan -
64.800,00
6.480,00
71.280,00

m² 240.000,00 264.000,00
kg 23.000,00 1.150,00
lah harga bahan 265.150,00

OH 130.000,00 1.950,00
OH 180.000,00 27.000,00
OH 230.000,00 3.450,00
OH 300.000,00 240,00
lah harga tenaga 32.640,00
-
Jumlah harga peralatan -
297.790,00
29.779,00
327.569,00

Pt. T - 30 - 2002 C

bh 35.000,00 35.000,00
Jumlah (1) 35.000,00

OH 130.000,00 -
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 -
Jumlah (2) 20.300,00
55.300,00

bh 30.000,00 30.000,00
Jumlah (1) 30.000,00

OH 130.000,00 -
OH 180.000,00 18.000,00
OH 230.000,00 2.300,00
OH 300.000,00 -
Jumlah (2) 20.300,00
50.300,00

Buah 27.200,00 180.336,00


kg 5.500,00 53.900,00
m³ 800.000,00 36.000,00
kg 33.000,00 42.900,00
lah harga bahan 313.136,00

OH 130.000,00 91.000,00
OH 180.000,00 63.000,00
OH 230.000,00 8.050,00
OH 300.000,00 10.500,00
lah harga tenaga 172.550,00
-
lah harga peralatan -
485.686,00
48.568,60
534.254,60

Buah 6.000,00 159.000,00


kg 5.500,00 57.200,00
m³ 800.000,00 36.000,00
kg 33.000,00 53.460,00
lah harga bahan 305.660,00

OH 130.000,00 91.000,00
OH 180.000,00 63.000,00
OH 230.000,00 8.050,00
OH 300.000,00 10.500,00
lah harga tenaga 172.550,00
-
lah harga peralatan -
478.210,00
47.821,00
526.031,00

Buah 6.500,00 130.000,00


kg 5.500,00 51.150,00
m³ 800.000,00 14.400,00
kg 33.000,00 64.020,00
lah harga bahan 259.570,00

OH 130.000,00 117.000,00
OH 180.000,00 81.000,00
OH 230.000,00 10.350,00
OH 300.000,00 13.500,00
lah harga tenaga 221.850,00
-
Jumlah harga peralatan -
481.420,00
48.142,00
529.562,00

lbr 138.000,00 93.703,70


kg 40.000,00 4.000,00
lah harga bahan 97.703,70

OH 130.000,00 45.500,00
OH 180.000,00 31.500,00
OH 230.000,00 3.910,00
OH 300.000,00 600,00
lah harga tenaga 81.510,00
-
Jumlah harga peralatan -
179.213,70
17.921,37
197.135,07

kg 45.000,00 9.000,00
kg 60.000,00 9.000,00
kg 40.000,00 6.800,00
kg 91.000,00 31.850,00
bh 25.000,00 250,00
kg 42.000,00 1.260,00
lbr 7.000,00 1.400,00
lah harga bahan 59.560,00

OH 130.000,00 9.100,00
OH 180.000,00 18.900,00
OH 230.000,00 920,00
OH 300.000,00 900,00
lah harga tenaga 29.820,00
-
lah harga peralatan -
89.380,00
8.938,00
98.318,00

kg 60.000,00 6.000,00
kg 40.000,00 4.000,00
kg 40.000,00 10.400,00
lah harga bahan 20.400,00

OH 130.000,00 2.600,00
OH 180.000,00 11.340,00
OH 230.000,00 1.449,00
OH 300.000,00 900,00
lah harga tenaga 16.289,00
-
lah harga peralatan -
36.689,00
3.668,90
40.357,90

2lapis cat penutup)

kg 60.000,00 6.000,00
kg 40.000,00 4.000,00
kg 40.000,00 10.400,00
3m 2.950.000,00 5.900,00
lah harga bahan 26.300,00

OH 130.000,00 2.600,00
OH 180.000,00 11.340,00
OH 230.000,00 1.449,00
OH 300.000,00 900,00
lah harga tenaga 16.289,00
-
lah harga peralatan -
42.589,00
4.258,90
46.847,90
JADWAL PENG
NAMA PEKERJAAN : PEMBANGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURM
LOKASI : BURMESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAM

NO. URAIAN PEKERJAAN

I. PEKERJAAN PERSIAPAN
II. PEKERJAAN TANAH
III. PEKERJAAN PONDASI
IV. PEKERJAAN PASANGAN DINDING
V. PEKERJAAN PLESTERAN
VI. PEKERJAAN KAYU
VII. PEKERJAAN BETON
VIII. PEKERJAAN BETON
IX. PEKERJAAN PENUTUP ATAP
X. PEKERJAAN LANGIT - LANGIT ( PLAFOND )
XI. PEKERJAAN INSTALASI LISTRIK
XII. PEKERJAAN SANITASI DALAM GEDUNG
XIII. PEKERJAAN SANITASI
XIV. PEKERJAAN KUNCI DAN KACA
XV. PEKERJAAN PENUTUP LANTAI DAN DINDING
XVI. PEKERJAAN PENGECATAN
XVII. PEKERJAAN FINSHING
JADWAL PENGIRIMAN BAHAN
NGUNAN RUMAH RAKYAT TYPE 36 DI KAMPUNG BURMESO (8 UNIT)
ESO, DISTRIK MAMBERAMO TENGAH KABUPATEN MAMBERAMO RAYA

WAKTU PELAKSANAA
URAIAN PEKERJAAN BULAN KE I BULAN KE II
1 2 3 4 5
AHAN

WAKTU PELAKSANAAN
BULAN KE II BULAN KE III KETERANGA
N
6 7 8 9 10 11 12

3 Bulan x 30
hari
Metode Mobilisasi Personil

Mobilisasi tenaga mencakup tenaga kerja yang didatangkan dari luar lokasi maupun berasal dari sekitar proyek.
Tenaga kerja yang dominan adalah tenaga kerja konstruksi Tenaga kerja yang tidak memerlukan keahlian khusus
akan diambil sebanyak mungkin dari penduduk lokal. Jika tenaga kerja lokal yang ada belum mencukupi, baru
akan diambil tenaga kerja dari luar lokasi.

PERSONIL INTI JUMLAH PERSIONIL

Project Manager 1 Orang


Site Manager 1 Orang
Pelaksana 1 Orang
K3 Konstruksi 1 Orang
Surveyor / Juru Ukur 1 Orang
Tenaga Laboratorium Beton 1 Orang
Tenaga Laboratorium Aspal 1 Orang
Mandor Besi / Pembesia / Penulangan Beton 1 Orang
Tukang Cor Beton / Concretor / Concrete Operation 1 Orang
Juru Gambar 1 Orang
Tenaga Logistik 1 Orang
Tenaga Administrasi 1 Orang
Tenaga Keuangan 1 Orang

Jakarta, 2019
PT.RATU KARYA

Cheppy Sapari
Direktur
Metode Mobilisasi Bahan / Material

Mobiliasi bahan yang dilakukan meliputi material : split, semen, besi, batu kal, belah, pasir pasang / beton, semen, kayu
dan papan begisting, serta bahan–bahan pendukung lainnya. Pada mobilisasi material, Kontraktor juga memperhitungkan
dan merencanakan akses jalan masuk, serta tetap menjaga kelancaran lalulintas sekitar proyek, dan keamanan proyek.
Dropping material ditempatkan pada lokasi yang mudah dijangkau dalam pelaksanaan pekerjaan, dalam pekerjaan ini
material juga dilangsir menuju masing- masing item pekerjaan, adapun bahan material yang di pakai dalam pelaksaan
sesuai jadwal pelaksaan sebagai berikut :

Bahan / Material
Bambu cerucuk Ø 10 cm panjang 600 cm
Batu belah (quarry - lokasi pekerjaan)
Portland cement
Pasir pasang muntilan (quarry-lokasi pekerjaan)
Produksi LPA (lapis pondasi agregat kelas A)
Minyak tanah
Kayu 10x10 Kls 1,2
Kayu 5X10 Kls 1,2
Kayu bekisting
Minyak bekisting
Plastik cor/Polytene 125 mikron
Baja tulangan polos
Kawat beton
Cat besi
Pipa PVC tipe AW Ø 1" panjang 4 m
Plywood 12 mm (120x240)
Paku
Thinner
atap spandek warna (Zingkalume) , BJLS 0.30
Spandek Warna BJLS0.30
tripleks ukuran (120 x 240) cm; tbl 4 mm
Kayu Profil
lampu SL 18 Wat
saklar tunggal
saklar ganda
Stop Kontak
BoX Sekring
closet jongkok porselen INA Warna Tua
bak mandi fiberglas volume 1,00 m3
floor drain
pipa galvanis Ø 1/2 "
kran Ø 3/4 " atau 1/2 " Kualitas baik
Pipa PVC tipe AW Ø 2"
pipa PVC Tipe AW Ø 4"
talang 1/2 lingkaran Ø 10 cm, seng BJLS 30
tangki 1100 L + ACC
Kunci Tanam Biasa
engsel pintu
engsel jendela Kupu-kupu
kait angin
gerendel (Pendek) Pintu
gerendel Jendela
keramik polos (20x20) cm
seng plat bjls 0.30
cat kayu
cetembok
Dokumnetasi & Pelaporan

MEMBERAMO, 2019
PT.RATU KARYA

Cheppy Sapari
Direktur
asang / beton, semen, kayu
aktor juga memperhitungkan
ek, dan keamanan proyek.
aan, dalam pekerjaan ini
di pakai dalam pelaksaan

Anda mungkin juga menyukai