Anda di halaman 1dari 90

REKAPITULASI

RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN SALURAN DRAINASE / GORONG-GORONG


PEKERJAAN : PEMBANGUNAN SALURAN DRAINASE DS. BALENREJO KEC. BALEN
SUMBER DANA : APBD 2018
LOKASI : KEC. BALEN
PANJANG TOTAL : CROSSING JALAN : 6.00 M
SALURAN (A) : 94.80 M
SALURAN (B) : 24.00 M

NO. URAIAN PEKERJAAN JUMLAH HARGA

1 PEKERJAAN PERSIAPAN Rp 1,500,000.00


2 PEKERJAAN TANAH Rp 5,762,430.50
3 PEKERJAAN STRUKTUR Rp 166,337,861.00

TOTAL BIAYA ( TANPA PPN ) Rp 173,600,291.50


PPN ( 10% ) = A x 10 % Rp 17,360,029.15
TOTAL BIAYA PEKERJAAN = A + B Rp 190,960,320.65
DIBULATKAN Rp 190,960,000.00

TERBILANG : #NAME?

Bojonegoro, 2018

Dibuat Oleh :
Konsultan Perencana
CV. ALVIN CONSULTANT

LELI DARMAYANTI, ST.


Direktur
RENCANA ANGGARAN BIAYA ( RAB )

KEGIATAN : PEMBANGUNAN SALURAN DRAINASE / GORONG-GORONG


PEKERJAAN : PEMBANGUNAN SALURAN DRAINASE DS. BALENREJO KEC. BALEN
SUMBER DANA : APBD 2018
LOKASI : KEC. BALEN
PANJANG TOTAL : CROSSING JALAN : 6.00 M

RINCIAN SATUAN PEKERJAAN


Harga Satuan
No. Uraian Pekerjaan Kode Sat Volume (Rp.) Jumlah Harga (Rp.)

a b c d e f g=(exf)

A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Pekerjaan - Ls 1.000 500,000.00 Rp 500,000.00
2 Pengukuran dan Pasang Profil/Bouwplank - Ls 1.000 500,000.00 Rp 500,000.00
3 Buat dan Pasang Papan Nama Pekerjaan, dan Dokumentasi - Ls 1.000 500,000.00 Rp 500,000.00
Pengadaan U Ditch Unit 1.00 Harga Bahan
Total Biaya Pekerjaan Persiapan Rp 1,500,000.00

B PEKERJAAN TANAH DAN URUGAN


1 Galian Tanah - M3 60.860 47,950.00 Rp 2,918,237.00
2 Urugan Pedel Dipadatkan Bawah U-Ditch Tebal 15 cm - M3 14.450 196,830.00 Rp 2,844,193.50

Total Biaya Pekerjaan Tanah dan Urugan Rp 5,762,430.50

C PEKERJAAN STRUKTUR
I Pekerjaan Crossing Jalan
1 Pengadaan dan Pemasangan U-DICTH 80.80.120 t 10 cm K. 350 - Unit 5.000 2,376,130.00 Rp 11,880,650.00
2 Pengadaan dan Pemasangan CU 80.120 t 12 cm K. 350 - Unit 5.000 920,710.00 Rp 4,603,550.00

II Pekerjaan Saluran (A)


1 Pengadaan dan Pemasangan U-DICTH 60.60.120 t 8 cm K. 350 - Unit 79.000 1,265,130.00 Rp 99,945,270.00
2 Pengadaan dan Pemasangan CU 60.120 t 12 cm K. 350 - Unit 26.000 693,460.00 Rp 18,029,960.00
3 Plesteran Perekat U-dicht - M2 5.610 47,950.00 Rp 268,999.50

III Pekerjaan Saluran (B)


1 Pengadaan dan Pemasangan U-DICTH 60.60.120 t 8 cm K. 350 - Unit 20.000 1,265,130.00 Rp 25,302,600.00
2 Pengadaan dan Pemasangan CU 60.120 t 12 cm K. 350 - Unit 9.000 693,460.00 Rp 6,241,140.00
3 Plesteran Perekat U-dicht - M2 1.370 47,950.00 Rp 65,691.50

Total Biaya Pekerjaan Struktur Rp 166,337,861.00


ANALISA HARGA SATUAN
1. Galian tanah biasa
1 m3 Galian tanah biasa pada saluran sedalam lebih kecil sama dengan 1 m dan
membuang hasil galian ketempat pembuangan dengan jarak angkut lebih kecil
atau sama dengan 3 m termasuk perataan dan perapihan.
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 0.5630 70,000.00 39,410.00
2 Mandor L.04 OH 0.0563 95,000.00 5,348.50
JUMLAH TENAGA KERJA 44,758.50
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 44,758.50


E DIBULATKAN Rp 44,758.00

2. Galian tanah berbatu


1 m3 Galian tanah berbatu sedalam ˂ 1 m
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 1.3510 70,000.00 94,570.00
2 Mandor L.04 OH 0.1351 95,000.00 12,834.50
JUMLAH TENAGA KERJA 107,404.50
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
1 Jack Hammer Sewa-hari 0.150 125,000.00 18,750.00
JUMLAH HARGA PERALATAN 18,750.00

D Harga satuan pekerjaan ( A + B + C ) 126,154.50


E DIBULATKAN Rp 126,154.00

3. Timbunan
1 m3 Timbunan tanah atau Urugan tanah kembali
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 0.3300 70,000.00 23,100.00
2 Mandor L.04 OH 0.0330 95,000.00 3,135.00
JUMLAH TENAGA KERJA 26,235.00
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 26,235.00


E DIBULATKAN Rp 26,235.00

4. 1 m3 Timbunan Tanah
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.4000 70,000.00 28,000.00
2 Mandor L.04 OH 0.0400 95,000.00 3,800.00
JUMLAH TENAGA KERJA 31,800.00
B. BAHAN
1 Tanah Urug m3 1.200 160,000.00 192,000.00
JUMLAH HARGA BAHAN 192,000.00
C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 223,800.00


E DIBULATKAN Rp 223,800.00
5. 1 m3 Timbunan Pedel
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.4000 70,000.00 28,000.00
2 Mandor L.04 OH 0.0400 95,000.00 3,800.00
JUMLAH TENAGA KERJA 31,800.00
B. BAHAN
1 Pedel m3 1.200 160,000.00 192,000.00
JUMLAH HARGA BAHAN 192,000.00
C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 223,800.00


E DIBULATKAN Rp 223,800.00

6. B.01 1 m3 beton untuk lantai kerja (bedding)


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA Molen
1 Pekerja L.01 OH 1.320 70,000.00 92,400.00
2 Tukang L.02 OH 0.220 80,000.00 17,600.00
3 Kepala Tukang L.03 OH 0.022 85,000.00 1,870.00
4 Mandor L.04 OH 0.132 95,000.00 12,540.00
JUMLAH TENAGA KERJA 124,410.00
B. BAHAN
1 Portlan Cement (40 Kg) kg 247.000 1,575.00 389,025.00
2 Pasir Beton kg 0.621 339.29 210.70
3 Batu Koral 1 - 2 cm kg 0.740 259.26 191.85
4 Air L 215.000 350.00 75,250.00
JUMLAH HARGA BAHAN 464,677.55
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 589,087.55


E DIBULATKAN Rp 589,087.00
CATATAN: *) perbandingan volume
Berat isi pb (pasir beton) = 1,4 ton/m3; Berat isi kr (kerikil/split) = 1,35 ton/m3

7. B.02 1 m3 beton mutu, f’c = 7,4 MPa (K100), slump (12±2) cm, w/c = 0,87
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA Molen
1 Pekerja L.01 OH 1.323 70,000.00 92,610.00
2 Tukang L.02 OH 0.189 80,000.00 15,120.00
3 Kepala Tukang L.03 OH 0.019 85,000.00 1,615.00
4 Mandor L.04 OH 0.132 95,000.00 12,540.00
JUMLAH TENAGA KERJA 121,885.00
B. BAHAN
1 Portlan Cement (40 Kg) kg 247.000 1,575.00 389,025.00
2 Pasir Beton kg 0.621 339.29 210.70
3 Batu Koral 1 - 2 cm kg 0.740 259.26 191.85
4 Air L 215.000 350.00 75,250.00
JUMLAH HARGA BAHAN 464,677.55
C PERALATAN
1 Molen 0,35 m3 Hari 0.250 330,000.00 82,500.00
JUMLAH HARGA PERALATAN 82,500.00

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 669,062.55


E DIBULATKAN Rp 669,062.00
CATATAN: *) perbandingan volume
Berat isi pb (pasir beton) = 1,4 ton/m3; Berat isi kr (kerikil/split) = 1,35 ton/m3
8. B.05 1 m3 beton mutu, f’c = 14,5 MPa (K175), slump (12±2) cm, w/c = 0,66
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA Molen
1 Pekerja L.01 OH 1.323 70,000.00 92,610.00
2 Tukang L.02 OH 0.189 80,000.00 15,120.00
3 Kepala Tukang L.03 OH 0.019 85,000.00 1,615.00
4 Mandor L.04 OH 0.132 95,000.00 12,540.00
JUMLAH TENAGA KERJA 121,885.00
B. BAHAN
1 Portlan Cement (40 Kg) kg 326.000 1,575.00 513,450.00
2 Pasir Beton kg 760.000 339.29 257,857.14
3 Batu Koral 1 - 2 cm kg 1,029.000 259.26 266,777.78
4 Air L 215.000 350.00 75,250.00
JUMLAH HARGA BAHAN 1,113,334.92
C PERALATAN
1 Molen 0,35 m3 Hari 0.250 330,000.00 82,500.00
JUMLAH HARGA PERALATAN 82,500.00

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 1,317,719.92


E DIBULATKAN Rp 1,317,719.00
CATATAN: *) perbandingan volume
Berat isi pb (pasir beton) = 1,4 ton/m3; Berat isi kr (kerikil/split) = 1,35 ton/m3

9. B.13 1 m3 beton menggunakan Ready mixed


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA Molen
1 Pekerja L.01 OH 1.000 70,000.00 70,000.00
2 Tukang L.02 OH 0.200 80,000.00 16,000.00
3 Kepala Tukang L.03 OH 0.025 85,000.00 2,125.00
4 Mandor L.04 OH 0.100 95,000.00 9,500.00
JUMLAH TENAGA KERJA 97,625.00
B. BAHAN
1 Beton Ready Mix K-175 M3 1.020 1,075,500.00 1,097,010.00

JUMLAH HARGA BAHAN 1,097,010.00


C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 1,194,635.00


E DIBULATKAN Rp 1,194,635.00

10. 1 m3 beton dicorkan pada tapak berjarak setiap tambahan jarak 25 m ( Horizontal )
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA Molen
1 Pekerja L.01 OH 0.500 70,000.00 35,000.00
2 Mandor L.02 OH 0.050 95,000.00 4,750.00
JUMLAH TENAGA KERJA 39,750.00
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 39,750.00


E DIBULATKAN Rp 39,750.00
11. Besi Tulangan Untuk Besi Struktur
B.17 Pembesian 100 kg dengan besi polos atau ulir
Harga Satuan Jumlah Harga(Rp)
No. Uraian Kode Satuan Koefisien (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.700 70,000.00 49,000.00
2 Tukang L.02 OH 0.700 80,000.00 56,000.00
3 Kepala Tukang L.03 OH 0.070 85,000.00 5,950.00
4 Mandor L.04 OH 0.070 95,000.00 6,650.00
JUMLAH TENAGA KERJA 117,600.00
B. BAHAN
1 Besi beton polos kg 105.000 19,000.00 1,995,000.00
2 Kawat beton kg 1.500 29,000.00 43,500.00
JUMLAH HARGA BAHAN 2,038,500.00
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 2,156,100.00


E Harga Satuan Pekerjaan / kg 21,561.00
F DIBULATKAN Rp 21,561.00
* digunakan besi polos

12 Bekisting Dengan Multiflek 8 mm


B.21 1 m2 Bekisting untuk permukaan beton biasa dengan multiflex 8 mm (tanpa perancah)
Tiga kali pakai
Harga Satuan Jumlah Harga (Rp)
No. Uraian Kode Satuan Koefisien (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.660 70,000.00 46,200.00
2 Tukang L.02 OH 0.330 80,000.00 26,400.00
3 Kepala Tukang L.03 OH 0.033 85,000.00 2,805.00
4 Mandor L.04 OH 0.033 95,000.00 3,135.00
JUMLAH TENAGA KERJA 78,540.00
B. BAHAN
1 Triplek tbl 8 mm lbr 0.350 155,000.00 54,250.00
2 Kayu Usuk m3 0.030 5,300,000.00 159,000.00
3 Paku 5 cm dan 7 cm kg 0.400 20,000.00 8,000.00
4 Minyak Begesting Ltr 0.200 1,500.00 300.00
JUMLAH HARGA BAHAN 221,550.00
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 300,090.00


E Harga Pekerjaan Bekisting 3 x Pakai 100,030.00
F DIBULATKAN Rp 100,030.00
CATATAN: *Dapat digunakan lebih dari 1 (satu) kali misal 2 kali maka koefisien menjadi 0,20
13. Pembongkaran Bekisting Biasa
B.35 Bongkar 1 m2 bekisting secara biasa

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga (Rp)
(Rp)
A. TENAGA
1 Pekerja L.01 OH 0.0400 70,000.00 2,800.00
2 Mandor L.15 OH 0.0040 95,000.00 380.00
JUMLAH TENAGA KERJA 3,180.00
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 3,180.00


E DIBULATKAN Rp 3,180.00
14 Pasangan batu dengan mortar tipe N ( untuk mutu PP tertentu setara dengan campuran 1 Pc:4 Pp
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 2.700 70,000.00 189,000.00
2 Tukang L.04 OH 0.900 80,000.00 72,000.00
3 Kepala Tukang L.03 OH 0.090 85,000.00 7,650.00
4 Mandor L.15 OH 0.270 95,000.00 25,650.00
JUMLAH TENAGA KERJA 294,300.00
B. BAHAN
1 Batu m3 1.200 170,000.00 204,000.00
2 Pasir Pasang m3 0.520 425,000.00 221,000.00
3 Portlan Cement (40 Kg) kg 163.000 1,575.00 256,725.00
JUMLAH HARGA BAHAN 681,725.00
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 976,025.00


E DIBULATKAN Rp 976,025.00

15 Bongkar 1 m3 pasangan batu ( Manual )


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 1.800 70,000.00 126,000.00
2 Mandor L.04 OH 0.180 95,000.00 17,100.00

JUMLAH TENAGA KERJA 143,100.00


B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 143,100.00


E DIBULATKAN Rp 143,100.00

16 Plesteran tebal 1 cm, dengan mortal jenis PC-PP tipe N ( untuk mutu PP tertentu setara dengan
campuran 1 PC : 4 PP )
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.400 70,000.00 28,000.00
2 Mandor L.15 OH 0.040 95,000.00 3,800.00
JUMLAH TENAGA KERJA 31,800.00
B. BAHAN
1 Pasir Pasang m3 0.018 425,000.00 7,650.00
2 Portlan Cement (40 Kg) kg 4.450 1,575.00 7,008.75
JUMLAH HARGA BAHAN 14,658.75
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 46,458.75


E DIBULATKAN Rp 46,458.00
17 Pasangan 1/2 Bata merah spesi 1 Pc : 6 Ps

Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.300 70,000.00 21,000.00
2 Tukang L.02 OH 0.100 80,000.00 8,000.00
Kepala Tukang L.03 OH 0.010 85,000.00 850.00
Mandor L.04 OH 0.015 95,000.00 1,425.00
JUMLAH TENAGA KERJA 31,275.00
B. BAHAN
Portlan Cement (40 Kg) zak 0.208 1,575.00 327.60
Pasir Pasang m3 0.049 425,000.00 20,825.00
Bata Merah bh 70.000 850.00 59,500.00
JUMLAH HARGA BAHAN 80,652.60
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 111,927.60


E DIBULATKAN Rp 111,927.00

18 PEMASANGAN 1 M2 ACIAN
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.200 70,000.00 14,000.00
2 Tukang L.02 OH 0.100 80,000.00 8,000.00
3 Kepala Tukang L.03 OH 0.010 85,000.00 850.00
4 Mandor L.04 OH 0.010 95,000.00 950.00
JUMLAH TENAGA KERJA 23,800.00
B. BAHAN
1 Portlan Cement (40 Kg) kg 3.250 1,575.00 5,118.75
JUMLAH HARGA BAHAN 5,118.75
C PERALATAN

JUMLAH HARGA PERALATAN

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 28,918.75


E DIBULATKAN Rp 28,918.00

19 1M1 Pasang Bambu Crucuk Ø 8 - 10 cm


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.01 OH 0.036 70,000.00 2,520.00
2 Mandor L.04 OH 0.004 95,000.00 380.00
JUMLAH TENAGA KERJA 2,900.00
B. BAHAN
1 Bambu Ø 8 - 10 cm m1 1.050 19,800.00 20,790.00
JUMLAH HARGA BAHAN 20,790.00
C PERALATAN
1 Bodem 5 kg ls 0.006 75,000.00 450.00
JUMLAH HARGA PERALATAN 450.00

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 24,140.00


E DIBULATKAN Rp 24,140.00

20 Pasangan Benangan
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)

A. TENAGA
1 Tukang L.03 OH 0.120 80,000.00 9,600.00
JUMLAH TENAGA KERJA 9,600.00
B. BAHAN
1 Portlan Cement (40 Kg) zak 0.003 1,575.00 4.73
2 Pasir Pasang m3 0.009 425,000.00 3,825.00
JUMLAH HARGA BAHAN 3,829.73

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 13,429.73


D DIBULATKAN Rp 13,429.00
21 Pengecatan kanstin baru ( 2x lapis )
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.004 95,000.00 380.00
2 Kepala Tukang L.02 OH 0.008 85,000.00 637.50
3 Tukang L.03 OH 0.075 80,000.00 6,000.00
4 Pekerja L.04 OH 0.075 70,000.00 5,250.00
JUMLAH TENAGA KERJA 12,267.50
B. BAHAN
1 Cat dasar dan penutup Kg 0.300 70,000.00 21,000.00
2 Kuas Bh 0.010 21,000.00 210.00
3 Minyak Cat Lt 0.100 25,000.00 2,500.00
JUMLAH HARGA BAHAN 23,710.00

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 35,977.50


D DIBULATKAN Rp 35,977.00

22 Pasang 1 m2 L.Keramik Uk. (20x20)cm Kasar Motif/Warna


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.035 95,000.00 3,325.00
2 Kepala Tukang L.02 OH 0.035 85,000.00 2,975.00
3 Tukang L.03 OH 0.350 80,000.00 28,000.00
4 Pekerja L.04 OH 0.700 70,000.00 49,000.00
JUMLAH TENAGA KERJA 83,300.00
B. BAHAN
1 Keramik Uk. (20x20) cm Kasar Motif/Warna Bh 26.500 2,160.00 57,240.00
2 Portlan Cement (40 Kg) zak 0.260 1,575.00 409.50
3 Pasir Pasang m3 0.045 425,000.00 19,125.00
4 Semen Warna Kg 1.620 21,000.00 34,020.00
JUMLAH HARGA BAHAN 110,794.50

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 194,094.50


D DIBULATKAN Rp 194,094.00

23 Pemasangan batu ampyang motif


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.025 95,000.00 2,375.00
2 Kepala Tukang L.02 OH 0.050 85,000.00 4,250.00
3 Tukang L.03 OH 0.800 80,000.00 64,000.00
4 Pekerja L.04 OH 1.000 70,000.00 70,000.00
JUMLAH TENAGA KERJA 140,625.00
B. BAHAN
1 Portlan Cement (40 Kg) zak 0.294 1,575.00 462.66
2 Pasir pasang m3 0.035 425,000.00 14,875.00
3 Batu Ampyang m2 1.100 42,000.00 46,200.00
4 Foam m2 0.500 8,000.00 4,000.00
JUMLAH HARGA BAHAN 65,537.66

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 206,162.66


D DIBULATKAN Rp 206,162.00

24 Pasangan Buis Beton


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor OH 0.004 95,000.00 361.00
2 Pekerja OH 0.038 70,000.00 2,667.00
JUMLAH TENAGA KERJA 3,028.00
B. BAHAN
1 Buis Beton Bulat Ukuran 80 x 100 cm Bh 2.000 233,000.00 466,000.00
JUMLAH HARGA BAHAN 466,000.00
C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 469,028.00
D DIBULATKAN Rp 469,028.00
25 Pemasangan Tegel Plint
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0050 95,000.00 475.00
2 Kepala Tukang L.02 OH 0.0090 85,000.00 765.00
3 Tukang L.03 OH 0.0800 80,000.00 6,400.00
4 Pekerja L.04 OH 0.0800 70,000.00 5,600.00
JUMLAH TENAGA KERJA 13,240.00
B. BAHAN
1 Portlan Cement (40 Kg) zak 0.0285 63,000.00 1,795.50
2 Semen Warna kg 0.0250 21,000.00 525.00
3 Pasir Pasang m3 0.0030 425,000.00 1,275.00
4 Tegel Plint Keramik Warna/Motif 7.5x20 Bh 5.3000 2,500.00 13,250.00
JUMLAH HARGA BAHAN 16,845.50

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 30,085.50


D DIBULATKAN Rp 30,085.00

26 Pasang Kanstin Beton 10x20x40


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0010 95,000.00 95.00
2 Kepala Tukang L.02 OH 0.0100 85,000.00 850.00
3 Tukang L.03 OH 0.0500 80,000.00 4,000.00
4 Pekerja L.04 OH 0.0500 70,000.00 3,500.00
JUMLAH TENAGA KERJA 8,445.00
B. BAHAN
1 Kanstin Beton 10x20x40 K-225 Bh 2.500 40,500.00 101,250.00
2 Portlan Cement (40 Kg) zak 0.0260 63,000.00 1,638.00
3 Pasir Pasang m3 0.0019 425,000.00 807.50
JUMLAH HARGA BAHAN 103,695.50

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 112,140.50


D DIBULATKAN Rp 112,140.00

27 Pasang Kanstin Beton 18x30x60


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0010 95,000.00 95.00
2 Kepala Tukang L.02 OH 0.0100 85,000.00 850.00
3 Tukang L.03 OH 0.0500 80,000.00 4,000.00
4 Pekerja L.04 OH 0.0500 70,000.00 3,500.00
JUMLAH TENAGA KERJA 8,445.00
B. BAHAN
1 Kanstin Beton 18x30x60 K-225 Bh 1.6670 58,000.00 96,686.00
2 Portlan Cement (40 Kg) zak 1.0400 63,000.00 65,520.00
3 Pasir Pasang m3 0.0019 425,000.00 807.50
JUMLAH HARGA BAHAN 163,013.50

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 171,458.50


D DIBULATKAN Rp 171,458.00

28 Pekerjaan Pengecatan Besi


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0100 95,000.00 950.00
2 Kepala Tukang L.02 OH 0.0200 85,000.00 1,700.00
3 Tukang L.03 OH 0.2000 80,000.00 16,000.00
4 Pekerja L.04 OH 0.0200 70,000.00 1,400.00
JUMLAH TENAGA KERJA 20,050.00
B. BAHAN
1 Cat Besi/Baja Kg 0.1000 72,000.00 7,200.00
2 Kuas Bh 0.0100 21,000.00 210.00
JUMLAH HARGA BAHAN 7,410.00

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 27,460.00


D DIBULATKAN Rp 27,460.00
29 Pekerjaan Pembesian dengan Besi Siku
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0030 95,000.00 285.00
2 Kepala Tukang L.02 OH 0.0060 85,000.00 510.00
3 Tukang L.03 OH 0.0600 80,000.00 4,800.00
4 Pekerja L.04 OH 0.0600 70,000.00 4,200.00
JUMLAH TENAGA KERJA 9,795.00
B. BAHAN
1 Besi Siku Kg 1.1500 19,000.00 21,850.00
2 Pengelasan/febrikasi Kg 0.1150 7,464.00 858.36
JUMLAH HARGA BAHAN 22,708.36

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 32,503.36


D DIBULATKAN Rp 32,503.00

30 Pekerjaan Pembesian dengan Besi Strip


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0030 95,000.00 285.00
2 Kepala Tukang L.02 OH 0.0060 85,000.00 510.00
3 Tukang L.03 OH 0.0600 80,000.00 4,800.00
4 Pekerja L.04 OH 0.0600 70,000.00 4,200.00
JUMLAH TENAGA KERJA 9,795.00
B. BAHAN
1 Besi Siku Kg 1.1500 19,000.00 21,850.00
2 Pengelasan/febrikasi Kg 0.1150 7,464.00 858.36
JUMLAH HARGA BAHAN 22,708.36

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 32,503.36


D DIBULATKAN Rp 32,503.00

31 Pemasangan Pipa PVC 2'' (AW)


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.001 95,000.00 95.00
2 Kepala Tukang L.02 OH 0.010 85,000.00 850.00
3 Tukang L.03 OH 0.050 80,000.00 4,000.00
4 Pekerja L.04 OH 0.050 70,000.00 3,500.00
JUMLAH TENAGA KERJA 8,445.00
B. BAHAN
1 Pipa PVC 2'' (AW) btg 0.200 122,000.00 24,400.00
2 Perlengkapan 35% harga pipa m3 0.350 42,700.00 14,945.00
JUMLAH HARGA BAHAN 39,345.00

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 47,790.00


D DIBULATKAN Rp 47,790.00

32 Pekerjaan Pengelasan dangan las listrik


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.0002 95,000.00 19.00
2 Kepala Tukang L.02 OH 0.0002 85,000.00 17.00
3 Tukang L.03 OH 0.0020 80,000.00 160.00
4 Pekerja L.04 OH 0.0040 70,000.00 280.00
JUMLAH TENAGA KERJA 476.00
B. BAHAN
1 Electrode Las Kg 0.0400 60,000.00 2,400.00
2 Solar liter 0.0300 5,150.00 154.50
3 Minyak Pelumas liter 0.0040 46,000.00 184.00
JUMLAH HARGA BAHAN 2,738.50
C PERALATAN
1 Sewa Alat Las jam 0.1700 25,000.00 4,250.00
JUMLAH HARGA PERALATAN 4,250.00

D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 7,464.50


E DIBULATKAN Rp 7,464.00
33 Pemasangan Pipa PVC 3'' (AW)
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.001 95,000.00 95.00
2 Kepala Tukang L.02 OH 0.010 85,000.00 850.00
3 Tukang L.03 OH 0.050 80,000.00 4,000.00
4 Pekerja L.04 OH 0.050 70,000.00 3,500.00
JUMLAH TENAGA KERJA 8,445.00
B. BAHAN
1 Pipa PVC 3'' (AW) btg 0.200 218,000.00 43,600.00
2 Perlengkapan 35% harga pipa m3 0.350 76,300.00 26,705.00
JUMLAH HARGA BAHAN 70,305.00

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 78,750.00


D DIBULATKAN Rp 78,750.00

34 Pemasangan Pipa PVC 4'' (AW)


Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor L.01 OH 0.001 95,000.00 95.00
2 Kepala Tukang L.02 OH 0.010 85,000.00 850.00
3 Tukang L.03 OH 0.050 80,000.00 4,000.00
4 Pekerja L.04 OH 0.050 70,000.00 3,500.00
JUMLAH TENAGA KERJA 8,445.00
B. BAHAN
1 Pipa PVC 4'' (AW) btg 0.200 312,000.00 62,400.00
2 Perlengkapan 35% harga pipa m3 0.350 109,200.00 38,220.00
JUMLAH HARGA BAHAN 100,620.00

C Jumlah harga tenaga, bahan dan peralatan ( A + B ) 109,065.00


D DIBULATKAN Rp 109,065.00

35 #REF!
Harga Satuan
No. Uraian Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Mandor Oh 0.033 95,000.00 3,135.00
2 Pekerja Oh 0.067 70,000.00 4,690.00
JUMLAH TENAGA KERJA 3,135.00
B. BAHAN
1 #REF! Unit 1.000 #REF! #REF!
JUMLAH HARGA BAHAN #REF!
C PERALATAN
1 #REF! Unit 1.000 #REF! #REF!
JUMLAH HARGA PERALATAN #REF!

D JUMLAH TENAGA, BAHAN DAN PERALATAN ( A+B+C ) #REF!


E DIBULATKAN #REF!
DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN ANGGARAN 2016

PROPINSI : JAWA TIMUR KABUPATEN : BOJONEGORO


WILAYAH : 3 ( Tiga )

NO URAIAN SATUAN HARGA UPAH / BAHAN KET.

1 2 4 5 6

I UPAH
1 Mandor Orang/Hari Rp. 95,000.00
2 Kepala Tukang Orang/Hari Rp. 85,000.00
3 Tukang Orang/Hari Rp. 80,000.00
4 Pekerja Orang/Hari Rp. 70,000.00
5 Operator Terlatih Orang/Hari Rp. 175,000.00
6 Pembantu Operator Orang/Hari Rp. 125,000.00
7 Biaya Pemasangan U-DITCH 30x50x120x6 cm K-350 BH Rp. 60,000.00
8 Biaya Pemasangan U-DITCH 40x40x120x6 cm K-350 Bh Rp. 60,000.00
9 Biaya Pemasangan U- DICTH 40x50x120x6 cm K-350 Bh Rp. 60,000.00
10 Biaya Pemasangan U-DITCH 50x50x120x6 cm K-350 Bh Rp. 60,000.00
11 Biaya Pemasangan U-DITCH 50x60x120x6 cm K-350 Bh Rp. 60,000.00
12 Biaya Pemasangan U-DITCH 50x70x120x6 cm K-350 Bh Rp. 60,000.00
13 Biaya Pemasangan U-DITCH 50x70x120x10 cm K-350 Bh Rp. 60,000.00
14 Biaya Pemasangan U-DITCH 60x60x120x6 cm K-350 Bh Rp. 60,000.00
15 Biaya Pemasangan U-DITCH 60x60x120x8 cm K-350 Bh Rp. 60,000.00
16 Biaya Pemasangan U-DITCH 60x60x120x10 cm K-350 Bh Rp. 60,000.00
17 Biaya Pemasangan U-DITCH 60x70x120x6 cm K-350 Bh Rp. 60,000.00
18 Biaya Pemasangan U-DITCH 60x70x120x9 cm K-350 Bh Rp. 60,000.00
19 Biaya Pemasangan U-DITCH 60x70x120x10 cm K-350 Bh Rp. 60,000.00
20 Biaya Pemasangan U-DITCH 60x80x120x10 cm K-350 Bh Rp. 75,000.00
21 Biaya Pemasangan U-DITCH 60x90x120x10 cm K-350 Bh Rp. 75,000.00
22 Biaya Pemasangan U-DITCH 60x100x120x10 cm K-350 Bh Rp. 75,000.00
23 Biaya Pemasangan U-DITCH 70x80x120x10 cm K-350 Bh Rp. 75,000.00
24 Biaya Pemasangan U-DITCH 80x80x120x8 cm K-350 Bh Rp. 75,000.00
25 Biaya Pemasangan U-DITCH 80x80x120x10 cm K-350 Bh Rp. 75,000.00
26 Biaya Pemasangan U-DITCH 80x90x120x12 cm K-350 Bh Rp. 90,000.00
27 Biaya Pemasangan U-DITCH 80x100x120x12 cm K-350 Bh Rp. 90,000.00
28 Biaya Pemasangan U-DITCH 100x100x120x10 cm K-350 Bh Rp. 90,000.00
-
II BAHAN -
1 Batu m3 Rp. 170,000.00
2 Batu koral 1/2 - 1 cm m3 Rp. 365,000.00
3 Batu Koral 1 - 2 cm m3 Rp. 350,000.00
4 Batu koral 2 - 3 cm m3 Rp. 350,000.00
5 Bata Merah BH Rp. 850.00
6 Pasir Beton Kg Rp. 475,000.00
7 Pasir Pasang m3 Rp. 425,000.00
8 Pasir Urug / Timbun m3 Rp. 250,000.00
9 Pedel m3 Rp. 160,000.00
10 Tanah Urug m3 Rp. 160,000.00
11 Beton Ready Mix K-175 m3 Rp. 1,075,500.00
12 Beton Ready Mix K-200 m3 Rp. 1,106,000.00
13 Portlan Cement (40 Kg) Zak Rp. 63,000.00
14 Semen Warna Kg Rp. 21,000.00
15 Besi beton polos Kg Rp. 19,000.00
16 Paku 5 cm dan 7 cm Kg Rp. 20,000.00
17 Besi Siku Kg Rp. 19,000.00
NO URAIAN SATUAN HARGA UPAH / BAHAN KET.

1 2 4 5 6
18 Besi Strip Kg Rp. 20,000.00
19 Besi Plat Tebal 10mm m2 Rp. 2,210,000.00
20 Besi Pipa Galvanis medium 3'' 6m Ljr Rp. 1,253,000.00
21 Kawat beton Kg Rp. 29,000.00
22 Engsel bh Rp. 15,000.00
NO URAIAN SATUAN HARGA UPAH / BAHAN KET.

1 2 4 5 6
23 Minyak Begesting ltr Rp. 1,500.00
24 Kayu Usuk m3 Rp. 5,300,000.00
25 Triplek tbl 8 mm LBR Rp. 155,000.00
26 Keramik Uk. (20x20) cm Kasar Motif/Warna Bh Rp. 2,160.00
27 Batu Ampyang m2 Rp. 42,000.00
28 Foam m2 Rp. 8,000.00
29 Tegel Plint Keramik Warna/Motif 7.5x20 Bh Rp. 2,500.00
30 Alat Bantu Set Rp. 150,000.00
31 Molen 0,35 m3 /hari Rp. 330,000.00
32 Bodem 5 kg Bh Rp. 75,000.00
33 Jack Hammer /hari Rp. 125,000.00
34 Sewa alat bantu strouss pile Jam Rp. 8,000.00
35 Sewa Concrete Vibrator Jam Rp. 26,000.00
36 Sewa Pick Up Truck Hari Rp. 200,000.00
37 Sewa Alat Las Jam Rp. 25,000.00
38 Bambu Ø 8 - 10 cm Btg Rp. 19,800.00
39 Kayu Dolken D18 / 300cm Btg Rp. 45,000.00
40 Glangsing 25 kg (isi 150 kg sedimen) Bh Rp. 2,000.00
41 Air Liter Rp. 350.00
42 Cat Besi/Baja Kg Rp. 72,000.00
43 Cat Tembok Kg Rp. 70,000.00
44 Kertas Gosok Lbr Rp. 13,000.00
45 Kuas Bh Rp. 21,000.00
46 kapek Bh Rp. 1,000.00
47 Minyak Cat ltr Rp. 25,000.00
48 Plamir Kg Rp. 32,000.00
49 U-DITCH 30x50x120x6 cm K-350 Bh Rp.
### 602,000.00
50 U-DITCH 40x40x120x6 cm K-350 Bh Rp.
### 669,000.00
51 U- DICTH 40x50x120x6 cm K-350 Bh Rp. 787,000.00
52 U-DITCH 50x50x120x6 cm K-350 Bh Rp. 832,000.00
53 U-DITCH 50x60x120x6 cm K-350 Bh Rp. 867,000.00
54 U-DITCH 50x70x120x6 cm K-350 Bh Rp. 1,030,000.00
55 U-DITCH 50x70x120x10 cm K-350 Bh Rp. 1,582,000.00
56 U-DITCH 60x60x120x6 cm K-350 Bh Rp. 955,000.00
57 U-DITCH 60x60x120x8 cm K-350 Bh Rp. 1,076,000.00
58 U-DITCH 60x60x120x10 cm K-350 Bh Rp. 1,518,000.00
59 U-DITCH 60x70x120x6 cm K-350 Bh Rp. 1,072,000.00
60 U-DITCH 60x70x120x8 cm K-350 Bh Rp. 1,385,000.00
61 U-DITCH 60x70x120x10 cm K-350 Bh Rp. 1,562,000.00
62 U-DITCH 60x80x120x10 cm K-350 Bh Rp. 1,703,000.00
63 U-DITCH 60x90x120x10 cm K-350 Bh Rp. 1,845,000.00
64 U-DITCH 70x80x120x10 cm K-350 Bh Rp. 1,775,000.00
65 U-DITCH 80x80x120x8 cm K-350 Bh Rp. 1,454,000.00
66 U-DITCH 80x80x120x10 cm K-350 Bh Rp. 2,199,000.00
67 U-DITCH 80x90x120x12 cm K-350 Bh Rp. 2,657,000.00
68 U-DITCH 80x100x120x12 cm K-350 Bh Rp. 2,980,000.00
69 U-DITCH 100x100x120x10 cm K-350 Bh Rp. 2,954,000.00
70 Box Culvert BC - 1000x1000x1200 Bh Rp. 6,000,000.00
71 Box Culvert BC - 800x800x1200 Bh Rp. 4,000,000.00
72 Kanstin Beton 10x20x40 K-225 Bh Rp. 40,500.00
73 Kanstin Beton 18x30x60 K-225 Bh Rp. 58,000.00
74 Pipa PVC 4'' (AW) Btg Rp. 312,000.00
75 Pipa PVC 3'' (AW) Btg Rp. 218,000.00
76 Buis Beton Bulat Ukuran 80 x 100 cm bh Rp. 233,000.00
77 Pipa PVC 2'' (AW) Btg Rp. 122,000.00
78 Electrode Las kg Rp. 60,000.00
NO URAIAN SATUAN HARGA UPAH / BAHAN KET.

1 2 4 5 6
79 Solar liter Rp. 5,150.00
80 Three Wheel Roller 6 - 8 ton jam Rp. 131,585.00
81 Aspal (Drum) Kg Rp. 30,000.00
82 Minyak Pelumas liter Rp. 46,000.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN ANGGARAN 2017
PROPINSI : JAWA TIMUR KABUPATEN : BOJONEGORO

NO URAIAN SATUAN HARGA UPAH / BAHAN KET.


1 2 4 5 6

I UPAH
1 Mandor Orang/Hari Rp. 95,000.000
2 Kepala Tukang Orang/Hari Rp. 85,000.000
3 Tukang Orang/Hari Rp. 80,000.000
4 Pekerja Orang/Hari Rp. 70,000.000
5 Operator Terlatih Orang/Hari Rp. 175,000.000
6 Pembantu Operator Orang/Hari Rp. 125,000.000
II BAHAN
1 Batu kali pecah 1/2 - 1 cm m3 Rp. 365,000.000
2 Batu kali pecah 1 - 2 cm m3 Rp. 345,000.000
3 Batu kali pecah 2 - 3 cm m3 Rp. 330,000.000
4 Batu kali m3 Rp. 145,000.000
5 U-DICTH 30.40.120 t 6 cm K. 350 bh Rp. 379,000.000
6 U-DICTH 40.40.120 t 6 cm K. 350 bh Rp. 522,000.000
7 U-DICTH 40.50.120 t 6 cm K. 350 bh Rp. 585,000.000
8 U-DICTH 50.50.120 t 6 cm K. 350 bh Rp. 659,000.000
9 U-DICTH 50.60.120 t 6 cm K. 350 bh Rp. 710,000.000
10 U-DICTH 60.60.120 t 8 cm K. 350 bh Rp. 860,000.000
11 U-DICTH 60.70.120 t 10 cm K. 350 bh Rp. 1,250,000.000
12 U-DICTH 80.80.120 t 10 cm K. 350 bh Rp. 1,435,000.000
13 U-DICTH 80.90.120 t 10 cm K. 350 bh Rp. 1,316,000.000
14 U-DICTH 100.100.120 t 10 cm K. 350 bh Rp. 1,889,000.000
15 Cu 30.120 t 12 cm K. 350 bh Rp. 270,000.000
16 Cu 40.120 t 12 cm K. 350 bh Rp. 340,000.000
17 Cu 50.120 t 12 cm K. 350 bh Rp. 405,000.000
18 Cu 60.120 t 12 cm K. 350 bh Rp. 435,000.000
19 Cu 80.120 t 12 cm K. 350 bh Rp. 549,000.000
20 Cu 100.120 t 15 cm K. 350 bh Rp. 752,000.000
21 BC 80.80.120 t 11 cm, 20 ton, K. 350 bh Rp. 2,798,000.000
22 BC 100.100.120 t 12,5 cm, 20 ton, K. 350 bh Rp. 3,669,000.000
23 Beton Ready Mix K-175 m3 Rp. 1,035,000.000
24 Beton Ready Mix K-225 m3 Rp. 1,093,000.000
25 Pasir Urug / Timbun m3 Rp. 250,000.000
26 Tanah Urug m3 Rp. 145,000.000
27 Semen ( PC ) 40 Kg zak Rp. 60,000.000
28 Pasir Pasang m3 Rp. 425,000.000
29 Paku Kg Rp. 16,500.000
30 Pasir cor m3 Rp. 475,000.000
31 Pudel m3 Rp. 150,000.000
32 Besi beton Kg Rp. 15,000.000
33 Kawat beton Kg Rp. 13,500.000
34 Kayu bekisting m3 Rp. 530,000.000
35 Tripleks 9 mm 120 x 240 cm Lbr Rp. 170,000.000
36 Alat Bantu Set Rp. 100,000.000
37 Pipa PVC 3'' (AW) Btg Rp. 200,000.000
37 Pipa PVC 4'' (AW) Btg Rp. 312,000.000
38 Air tawar Liter Rp. 250.000
39 Bambu m Rp. 20,000.000
40 Keramik 20x20 kw 1 m2 Rp. 52,000.000
NO URAIAN SATUAN HARGA UPAH / BAHAN KET.
1 2 4 5 6
41 Semen Warna kg Rp. 21,000.000
42 Sewa alat untuk Pemasangan U ditch ukuran.100,80,60 bh Rp. 75,000.000
43 Sewa alat untuk Pemasangan U ditch ukuran.50,40,30 bh Rp. 60,000.000
44 Sewa alat untuk Pemasangan CU ukuran. 100.80.60 bh Rp. 25,000.000
45 Sewa Alat untuk Pemasangan CU ukuran. 50.40.30 bh Rp. 20,000.000
46 Sewa Alat untuk Pemasangan BC bh Rp. 250,000.000
47 Kerb Beton Pracetak 0,18x0,30x0,60 K 225 bh Rp. 56,000.000
48 Kerb Beton Pracetak 0,10x0,20x0,40 K 225 bh Rp. 40,000.000
49 Kuas 4 " bh Rp. 18,000.000
50 Cat Tembok kg Rp. 35,000.000
51 Palu bh Rp. 25,000.000
52 Linggis bh Rp. 45,000.000
53 Aspal kg Rp. 25,000.000
54 Manhole 60.60 (Besi Cor Pabrikasi) bh Rp. 1,500,000.000
55 Grill Tangkapan Air 50.30 (Besi Cor Pabrikasi) bh Rp. 1,050,000.000
43 HRS - WC Ton Rp. 1,250,000.000
44 Asphalt Finisher jam Rp. 68,000.000
45 Tandem Roller jam Rp. 88,000.000
46 P. Tyre Roller jam Rp. 98,000.000

III SEWA ALAT

1 Stamper jam Rp. 57,514.000


2 Jack Hammer jam Rp. 43,552.000
3 Three Wheel Roller 6-8 ton jam Rp. 427,350.000
4 Exavator jam Rp. 429,439.000

KETERANGAN :

Harga tersebut di atas tidak termasuk PPN

Wil I Bojonegoro
Wil II Balen, Kapas, Dander, Sukosewu, Temayang
Wil III Kanor, Sumberrejo, Kepobaru, Kedungadem, Sugihwaras, Baureno
Wil IV Kalitidu,Trucuk, Malo,Kasiman, Kedewan, Padangan, Purwosari
Wil V Bubulan, Gondang, Ngambon, Ngraho, Margomulyo, Tambakrejo, Ngasem, Gayan
Wil VI Sekar
ANALISA HARGA SATUAN PEKERJAAN

T.07 1 m3 Galian Tanah Biasa sedalam lebih kecil sama dengan 1 m


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 3.3333 10,714.286 35,714.286
2 Mandor L.15 Jam 0.6667 14,285.714 9,523.810
JUMLAH HARGA TENAGA KERJA 45,238.095
B Peralatan
1 alat bantu ls 1.0000 2,714.286 2,714.286
JUMLAH HARGA PERALATAN 2,714.286
Jumlah 47,952.381
B PEMBULATAN 47,950.000

1 m3 Galian Lumpur
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 OH 1.2000 75,000.000 90,000.000
2 Mandor L.15 OH 0.0450 100,000.000 4,500.000
JUMLAH HARGA TENAGA KERJA 94,500.000
Jumlah 94,500.000
B PEMBULATAN 94,500.000

1 m3 Galian tanah menggunakan Alat


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 0.0727 10,714.286 778.845
2 Mandor L.15 Jam 0.0363 14,285.714 519.230
JUMLAH HARGA TENAGA KERJA 1,298.075
B Bahan

JUMLAH HARGA BAHAN -


C Peralatan
1 Exavator jam 0.0363 429,439.000 15,608.433
JUMLAH HARGA PERALATAN 15,608.433

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 16,906.508

E PEMBULATAN 16,900.000

1 m3 Urugan Pedel pemadatan menggunakan stamper


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 jam 1.0258 10,714.286 10,990.780
2 Mandor L.15 jam 0.1465 14,285.714 2,093.482
JUMLAH HARGA TENAGA KERJA 13,084.262
B Bahan
Pedel Pilihan M3 1.1100 160,000.000 177,600.000
JUMLAH HARGA BAHAN 177,600.000
C Peralatan
1 Stamper jam 0.1070 57,514.000 6,153.305
JUMLAH HARGA PERALATAN 6,153.305

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 196,837.567

E PEMBULATAN 196,830.000
1 m3 Timbunan tanah atau Urugan tanah kembali
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 0.33 75,000.000 24,750.000
2 Mandor L.04 OH 0.033 100,000.000 3,300.000
JUMLAH TENAGA KERJA 28,050.000
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 28,050.000


E DIBULATKAN 28,050.000
1 m³ Beton mutu, f'c = 14,5 Mpa (K175), slump (12±2) cm, w/c = 0,66
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.6500 75,000.000 123,750.000
2 Tukang batu L.04 OH 0.2750 85,000.000 23,375.000
3 Kepala tukang L.03 OH 0.0280 90,000.000 2,520.000
4 Mandor L.15 OH 0.0830 100,000.000 8,300.000
JUMLAH HARGA TENAGA KERJA 157,945.000
B Bahan
1 PC M.18 Kg 326.0000 1,550.000 505,300.000
2 PB M.09 Kg 760.0000 339.286 257,857.143
3 KR - Kg 1,029.0000 277.778 285,833.333
4 Air M.01 Ltr 215.0000 400.000 86,000.000
JUMLAH HARGA BAHAN 1,134,990.476
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,292,935.476

Jumlah 1,292,935.476
F PEMBULATAN 1,292,930.000

1 m3 Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3-6) cm, w/c = 0,87
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.2000 75,000.000 90,000.000
2 Tukang batu L.04 OH 0.2000 85,000.000 17,000.000
3 Kepala tukang L.03 OH 0.0200 90,000.000 1,800.000
4 Mandor L.15 OH 0.0600 100,000.000 6,000.000
JUMLAH HARGA TENAGA KERJA 114,800.000
B Bahan
1 PC M.18 Kg 230.0000 1,550.000 356,500.000
2 PB M.09 M3 893.0000 339.286 302,982.143
3 KR - M3 1,027.0000 277.778 285,277.778
4 Air M.01 Ltr 200.0000 400.000 80,000.000
JUMLAH HARGA BAHAN 1,024,759.921

C Jumlah Harga Tenaga, Bahan dan Peralatan (A + B ) 1,139,559.921


E PEMBULATAN 1,139,550.000
1 kg Pembesian dengan besi polos atau ulir
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0700 75,000.000 5,250.000
2 Tukang besi L.04 OH 0.0700 85,000.000 5,950.000
3 Kepala tukang L.03 OH 0.0070 90,000.000 630.000
4 Mandor L.15 OH 0.0040 100,000.000 400.000
JUMLAH HARGA TENAGA KERJA 12,230.000
B Bahan
1 Besi beton (polos/ulir) Kg 10.5000 20,000.000 210,000.000
2 Kawat beton M.75 Kg 0.1500 20,000.000 3,000.000
JUMLAH HARGA BAHAN 213,000.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 225,230.000

Harga Satuan Pekejaan /kg 22,523.000


Jumlah 22,523.000
E PEMBULATAN 22,520.000

1 m² Begisting untuk Dinding


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6600 75,000.000 49,500.000
2 Tukang kayu L.04 OH 0.3300 85,000.000 28,050.000
3 Kepala tukang L.03 OH 0.0330 90,000.000 2,970.000
4 Mandor L.15 OH 0.0330 100,000.000 3,300.000
JUMLAH HARGA TENAGA KERJA 83,820.000
B Bahan
1 M.61/ Lbr
0.3500
Multiflex 9 mm atau 12 mm M.17 186,000.000 65,100.000
2 Kaso 5/7 M.54 m³ 0.0300 5,300,000.000 159,000.000
3 Paku 5 cm dan 7 cm M.77 Kg 0.4000 20,000.000 8,000.000
JUMLAH HARGA BAHAN 232,100.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 315,920.000

Asumsi dipakai 3 kali 0.3333 X D 105,306.667


Jumlah 105,306.667
PEMBULATAN 105,300.000
1 BH Pengadaan dan Pemasangan BC 80.80.120 t 11 cm, 20 ton, K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.2500 100,000.000 25,000.000
JUMLAH HARGA TENAGA KERJA 25,000.000
B Bahan
1 BH 1.0000
BC 80.80.120 t 11 cm, 20 ton, K. 350 2,844,780.000 2,844,780.000
JUMLAH HARGA BAHAN 2,844,780.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 250,000.000 250,000.000
JUMLAH HARGA PERALATAN 250,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,119,780.000


PEMBULATAN 3,119,780.000

1 BH Pengadaan dan Pemasangan U-DICTH 30.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 30.40.120 t 6 cm K. 350 BH 1.0000 513,080.000 513,080.000
JUMLAH HARGA BAHAN 513,080.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 576,413.333


PEMBULATAN 576,410.000

1 BH Pengadaan dan Pemasangan U-DICTH 40.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 40.40.120 t 6 cm K. 350 BH 1.0000 664,580.000 664,580.000
JUMLAH HARGA BAHAN 664,580.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 727,913.333


PEMBULATAN 727,910.000
1 BH Pengadaan dan Pemasangan U-DICTH 50.50.120 t 6 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 50.50.120 t 6 cm K. 350 BH 1.0000 830,220.000 830,220.000
JUMLAH HARGA BAHAN 830,220.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 893,553.333


PEMBULATAN 893,550.000

1 BH Pengadaan dan Pemasangan U-DICTH 60.60.120 t 8 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 60.60.120 t 8 cm K. 350 BH 1.0000 1,073,630.000 1,073,630.000
JUMLAH HARGA BAHAN 1,073,630.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,151,963.333


PEMBULATAN 1,151,960.000

1 BH Pengadaan dan Pemasangan U-DICTH 60.70.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 60.70.120 t 10 cm K. 350 Unit 1.0000 1,561,460.000 1,561,460.000
JUMLAH HARGA BAHAN 1,561,460.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,639,793.333


PEMBULATAN 1,639,790.000

1 BH Pengadaan dan Pemasangan U-DICTH 100.100.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 100,000.000 3,333.333
JUMLAH HARGA TENAGA KERJA 3,333.333
B Bahan
1 U-DICTH 100.100.120 t 10 cm K. 350 Unit 1.0000 2,729,020.000 2,729,020.000
JUMLAH HARGA BAHAN 2,729,020.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 2,807,353.333


PEMBULATAN 2,807,350.000
1 BH Pengadaan dan Pemasangan Cu 30.120 t 12 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 100,000.000 2,500.000
JUMLAH HARGA TENAGA KERJA 2,500.000
B Bahan
1 Cu 30.120 t 12 cm K. 350 Unit 1.0000 370,670.000 370,670.000
JUMLAH HARGA BAHAN 370,670.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 393,170.000


PEMBULATAN 393,170.000

1 BH Pengadaan dan Pemasangan Cu 40.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 100,000.000 2,500.000
JUMLAH HARGA TENAGA KERJA 2,500.000
B Bahan
1 Cu 40.120 t 12 cm K. 350 Unit 1.0000 430,260.000 430,260.000
JUMLAH HARGA BAHAN 430,260.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 452,760.000


PEMBULATAN 452,760.000

1 BH Pengadaan dan Pemasangan Cu 50.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 100,000.000 2,500.000
JUMLAH HARGA TENAGA KERJA 2,500.000
B Bahan
1 Cu 50.120 t 12 cm K. 350 Unit 1.0000 495,910.000 495,910.000
JUMLAH HARGA BAHAN 495,910.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 518,410.000


PEMBULATAN 518,410.000

1 BH Pengadaan dan Pemasangan Cu 60.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 100,000.000 2,500.000
JUMLAH HARGA TENAGA KERJA 2,500.000
B Bahan
1 Cu 60.120 t 12 cm K. 350 Unit 1.0000 528,230.000 528,230.000
JUMLAH HARGA BAHAN 528,230.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 555,730.000


PEMBULATAN 555,730.000
1 BH Pengadaan dan Pemasangan Cu 80.120 t 12 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 100,000.000 2,500.000
JUMLAH HARGA TENAGA KERJA 2,500.000
B Bahan
1 Cu 80.120 t 12 cm K. 350 Unit 1.0000 564,060.000 564,060.000
JUMLAH HARGA BAHAN 564,060.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 591,560.000


PEMBULATAN 591,560.000

1 BH Pengadaan dan Pemasangan Cu 100.120 t 15 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 100.120 t 15 cm K. 350 Unit 1.0000 957,480.000 957,480.000
JUMLAH HARGA BAHAN 957,480.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 984,855.000


PEMBULATAN 984,850.000

1 M' Pekerjaan Acian


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2000 75,000.000 15,000.000
2 Tukang batu L.04 OH 0.1000 85,000.000 8,500.000
3 Kepala tukang L.03 OH 0.0100 90,000.000 900.000
4 Mandor L.15 OH 0.0100 100,000.000 1,000.000
JUMLAH HARGA TENAGA KERJA 25,400.000
B Bahan
1 Portland Cement M.18 kg 3.2500 1,550.000 5,037.500
JUMLAH HARGA BAHAN 5,037.500
C Peralatan
JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 30,437.500

F PEMBULATAN 30,430.000
1 m2 Plesteran tebal 15mm Campuran 1:5
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja OH 0.3000 75,000.000 22,500.000
2 Tukang OH 0.1500 85,000.000 12,750.000
3 Kepala tukang OH 0.0150 90,000.000 1,350.000
4 Mandor OH 0.0300 100,000.000 3,000.000
JUMLAH HARGA TENAGA KERJA 39,600.000
B Bahan
1 Pasir Pasang m3 0.0160 425,000.000 6,800.000
2 Portland cement kg 5.1840 1,550.000 1,550.000
JUMLAH HARGA BAHAN 8,350.000
C Peralatan
JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 47,950.000

E Jumlah 47,950.000
PEMBULATAN 47,950.000

1 m3 Pembongkaran Pasangan batu (Mekanis)/Jack Hammer


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 9.6386 10,714.286 103,270.224
2 Mandor jam 1.2048 14,285.714 17,211.704
JUMLAH HARGA TENAGA KERJA 120,481.928
B Peralatan
1 Jack Hammrer jam 1.2048 43,552.000 52,472.289
JUMLAH HARGA PERALATAN 52,472.289

C Jumlah Harga Tenaga dan Peralatan (A + B + C) 172,954.217


PEMBULATAN 172,950.000

1 m2 Pemasangan Keramik Ukuran 20x20


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 75,000.000 52,500.000
2 Tukang batu L.04 OH 0.3500 85,000.000 29,750.000
3 Kepala tukang L.03 OH 0.0350 90,000.000 3,150.000
4 Mandor L.15 OH 0.0350 100,000.000 3,500.000
JUMLAH HARGA TENAGA KERJA 88,900.000
B Bahan
1 Keramik - bh 26.5000 2,150.943 57,000.000
2 Portland Cement - kg 10.4000 1,550.000 16,120.000
3 Pasir Pasang - m3 0.0450 425,000.000 19,125.000
4 Semen warna - kg 1.6200 2,200.000 3,564.000
JUMLAH HARGA BAHAN 95,809.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 184,709.000

E PEMBULATAN 184,700.000
1 m³ Beton mutu K - 175 ( Ready Mix)
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 1.0000 75,000.000 75,000.000
2 Tukang L.04 OH 0.2500 85,000.000 21,250.000
3 Kepala tukang L.03 OH 0.0250 90,000.000 2,250.000
4 Mandor L.15 OH 0.1000 100,000.000 10,000.000
JUMLAH HARGA TENAGA KERJA 108,500.000
B Bahan
1 Ready Mix K - 175 - m3 1.0200 1,010,000.000 1,030,200.000
JUMLAH HARGA BAHAN 1,030,200.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,138,700.000

Jumlah 1,138,700.000
F PEMBULATAN 1,138,700.000

1 m' Memasang Beton Pracetak 0,18x0,30x0,60


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.5833 75,000.000 43,747.500
2 Tukang batu L.04 OH 0.3500 85,000.000 29,750.000
3 Mandor L.15 OH 0.1167 100,000.000 11,670.000
JUMLAH HARGA TENAGA KERJA 85,167.500
B Bahan
1 Kerb Pracetak (0,18x0,30x0,60) - bh 1.6667 58,500.000 97,501.950
JUMLAH HARGA BAHAN 97,501.950
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 182,669.450

Jumlah 182,669.450
F PEMBULATAN 182,660.000

1 m' Memasang Beton Pracetak 0,10x0,20x0,40


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6667 75,000.000 50,002.500
2 Tukang batu L.04 OH 0.4000 85,000.000 34,000.000
3 Mandor L.15 OH 0.1333 100,000.000 13,330.000
JUMLAH HARGA TENAGA KERJA 97,332.500
B Bahan
1 Kerb Pracetak (0,10x0,20x0,40) - bh 2.5000 41,000.000 102,500.000
JUMLAH HARGA BAHAN 102,500.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 199,832.500

Jumlah 199,832.500
F PEMBULATAN 199,830.000
1 m2 Pengecatan Tembok
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0200 75,000.000 1,500.000
2 Tukang L.04 OH 0.0630 85,000.000 5,355.000
3 Kepala Tukang L.03 OH 0.0063 90,000.000 567.000
4 Mandor L.15 OH 0.0030 100,000.000 300.000
JUMLAH HARGA TENAGA KERJA 7,722.000
B Bahan
1 Cat tembok - kg 0.3600 47,000.000 16,920.000
JUMLAH HARGA BAHAN 16,920.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 24,642.000

Jumlah 24,642.000
F PEMBULATAN 24,640.000

1 m' Pemasangan Pipa Air Kotor 3" PVC AW


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0810 75,000.000 6,075.000
2 Tukang batu L.04 OH 0.1350 85,000.000 11,475.000
3 Kepala Tukang L.15 OH 0.0135 90,000.000 1,215.000
4 Mandor L.15 OH 0.0040 100,000.000 400.000
JUMLAH HARGA TENAGA KERJA 19,165.000
B Bahan
1 Pipa PVC 3" - btg 1.2000 55,000.000 66,000.000
Perlengkapan 35% % 0.3500 23,100.000 23,100.000
JUMLAH HARGA BAHAN 89,100.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 108,265.000

Jumlah 108,265.000
F PEMBULATAN 108,260.000
1 m3 Lapis Penetrasi t 5 cm (Lapen)
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 1.3880 9,375.000 13,012.500
3 Mandor L.15 Jam 0.1542 12,500.000 1,927.500
JUMLAH HARGA TENAGA KERJA 14,940.000
B Bahan
1 Batu Pecah2-3 m3 0.9429 350,000.000 330,015.000
2 Batu Pecah 1-2 m3 0.3929 375,000.000 147,337.500
3 Batu Pecah 1/2 - 1 m3 0.2200 375,000.000 82,500.000
4 Aspal Drum - kg 105.0000 25,000.000 2,625,000.000
JUMLAH HARGA BAHAN 3,184,852.500
C Peralatan
1 Three Wheel Roller 6-8 ton Jam 0.0771 126,093.000 9,721.770
JUMLAH HARGA PERALATAN 9,721.770

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,209,514.270

Jumlah 3,209,514.270
F PEMBULATAN 3,209,510.000

1 m2 Pasang Paving Block abu abu


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 0.8750 9,375.000 8,203.125
2 Tukang - Jam 0.3500 10,625.000 3,718.750
3 Mandor L.15 Jam 0.0875 12,500.000 1,093.750
JUMLAH HARGA TENAGA KERJA 13,015.625
B Bahan
1 Paving m2 1.0000 -
2 Pasir Urug m3 0.0629 250,000.000 15,725.000

JUMLAH HARGA BAHAN 15,725.000


C Peralatan

JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 28,740.625

Jumlah 28,740.625
F PEMBULATAN 28,740.000
ANALISA HARGA SATUAN PEKERJAAN

1 m3 Galian Tanah Biasa sedalam lebih kecil sama dengan 1 m


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 3.3333 10,714.29 35,714.286
2 Mandor L.15 Jam 0.6667 14,285.71 9,523.810
JUMLAH HARGA TENAGA KERJA 45,238.095
B Peralatan
1 alat bantu ls 1.0000 2,714.29 2,714.286
JUMLAH HARGA PERALATAN 2,714.286
Jumlah 47,952.381
B PEMBULATAN 47,950.000

1 m3 Galian Lumpur
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 OH 1.2000 75,000.00 90,000.000
2 Mandor L.15 OH 0.0450 100,000.00 4,500.000
JUMLAH HARGA TENAGA KERJA 94,500.000
Jumlah 94,500.000
B PEMBULATAN 94,500.000

1 m3 Galian tanah menggunakan Alat


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 0.0727 10,714.29 778.845
2 Mandor L.15 Jam 0.0363 14,285.71 519.230
JUMLAH HARGA TENAGA KERJA 1,298.075
B Bahan

JUMLAH HARGA BAHAN -


C Peralatan
1 Exavator jam 0.0363 429,439.00 15,608.433
JUMLAH HARGA PERALATAN 15,608.433

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 16,906.508

E PEMBULATAN 16,900.000

1 m3 Urugan Pedel pemadatan menggunakan stamper


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 jam 1.0258 10,714.29 10,990.780
2 Mandor L.15 jam 0.1465 14,285.71 2,093.482
JUMLAH HARGA TENAGA KERJA 13,084.262
B Bahan
Pedel Pilihan M3 1.1100 160,000.00 177,600.000
JUMLAH HARGA BAHAN 177,600.000
C Peralatan
1 Stamper jam 0.1070 57,514.00 6,153.305
JUMLAH HARGA PERALATAN 6,153.305

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 196,837.567

E PEMBULATAN 196,830.000
1 m3 Timbunan tanah atau Urugan tanah kembali
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 0.33 75,000.00 24,750.000
2 Mandor L.04 OH 0.033 100,000.00 3,300.000
JUMLAH TENAGA KERJA 28,050.000
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 28,050.000


E DIBULATKAN 28,050.000

1 m³ Beton mutu, f'c = 14,5 Mpa (K175), slump (12±2) cm, w/c = 0,66
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.6500 75,000.00 123,750.000
2 Tukang batu L.04 OH 0.2750 85,000.00 23,375.000
3 Kepala tukang L.03 OH 0.0280 90,000.00 2,520.000
4 Mandor L.15 OH 0.0830 100,000.00 8,300.000
JUMLAH HARGA TENAGA KERJA 157,945.000
B Bahan
1 PC M.18 Kg 326.0000 1,550.00 505,300.000
2 PB M.09 Kg 760.0000 339.29 257,857.143
3 KR - Kg 1,029.0000 277.78 285,833.333
4 Air M.01 Ltr 215.0000 400.00 86,000.000
JUMLAH HARGA BAHAN 1,134,990.476
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,292,935.476

Jumlah 1,292,935.476
F PEMBULATAN 1,292,930.000
CATATAN: *) perbandingan volume
Berat isi pb (pasir beton) = 1,4 ton/m3; Berat isi kr (kerikil/split) = 1,35 ton/m3

1 m3 Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3-6) cm, w/c = 0,87
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.2000 75,000.00 90,000.000
2 Tukang batu L.04 OH 0.2000 85,000.00 17,000.000
3 Kepala tukang L.03 OH 0.0200 90,000.00 1,800.000
4 Mandor L.15 OH 0.0600 100,000.00 6,000.000
JUMLAH HARGA TENAGA KERJA 114,800.000
B Bahan
1 PC M.18 Kg 230.0000 1,550.00 356,500.000
2 PB M.09 M3 893.0000 339.29 302,982.143
3 KR - M3 1,027.0000 277.78 285,277.778
4 Air M.01 Ltr 200.0000 400.00 80,000.000
JUMLAH HARGA BAHAN 1,024,759.921

C Jumlah Harga Tenaga, Bahan dan Peralatan (A + B ) 1,139,559.921


E PEMBULATAN 1,139,550.000
CATATAN: *) perbandingan volume
Berat isi pb (pasir beton) = 1,4 ton/m3; Berat isi kr (kerikil/split) = 1,35 ton/m3
1 kg Pembesian dengan besi polos atau ulir
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0700 75,000.00 5,250.000
2 Tukang besi L.04 OH 0.0700 85,000.00 5,950.000
3 Kepala tukang L.03 OH 0.0070 90,000.00 630.000
4 Mandor L.15 OH 0.0040 100,000.00 400.000
JUMLAH HARGA TENAGA KERJA 12,230.000
B Bahan
1 Besi beton (polos/ulir) Kg 10.5000 20,000.00 210,000.000
2 Kawat beton M.75 Kg 0.1500 20,000.00 3,000.000
JUMLAH HARGA BAHAN 213,000.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 225,230.000

Harga Satuan Pekejaan /kg 22,523.000


Jumlah 22,523.000
E PEMBULATAN 22,520.000

1 m² Begisting untuk Dinding


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6600 75,000.00 49,500.000
2 Tukang kayu L.04 OH 0.3300 85,000.00 28,050.000
3 Kepala tukang L.03 OH 0.0330 90,000.00 2,970.000
4 Mandor L.15 OH 0.0330 100,000.00 3,300.000
JUMLAH HARGA TENAGA KERJA 83,820.000
B Bahan
1 M.61/ Lbr
0.3500
Multiflex 9 mm atau 12 mm M.17 186,000.00 65,100.000
2 Kaso 5/7 M.54 m³ 0.0300 5,300,000.00 159,000.000
3 Paku 5 cm dan 7 cm M.77 Kg 0.4000 20,000.00 8,000.000
JUMLAH HARGA BAHAN 232,100.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 315,920.000

Asumsi dipakai 3 kali 0.3333 X D 105,306.667


Jumlah 105,306.667
PEMBULATAN 105,300.000

1 BH Pengadaan dan Pemasangan BC 80.80.120 t 11 cm, 20 ton, K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
M100 unit 1.0000
1 Boxculvert 3,090,600.00 3,090,600.000
JUMLAH HARGA BAHAN 3,090,600.000
C Peralatan
1 Crane (E31) jam 0.5857 373,843.00 218,950.887
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 224,479.458
D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,407,222.315
PEMBULATAN 3,407,220.000
D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,499,365.173
PEMBULATAN 3,499,360.000
1 BH Pengadaan dan Pemasangan BC 100.100.120 t 12,5 cm, 20 ton, K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Boxculvert M100 unit 1.0000 3,505,200.00 3,505,200.000
JUMLAH HARGA BAHAN 3,505,200.000
C Peralatan
1 Crane (E31) jam 0.5857 373,843.00 218,950.887
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 224,479.458

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,821,822.315


PEMBULATAN 3,821,820.000

1 BH Pengadaan dan Pemasangan U-DICTH 30.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 513,080.00 513,080.000
U-DICTH 30.40.120 t 6 cm K. 350
JUMLAH HARGA BAHAN 513,080.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 704,587.523


PEMBULATAN 704,580.000

1 BH Pengadaan dan Pemasangan U-DICTH 40.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 664,580.00 664,580.000
U-DICTH 40.40.120 t 6 cm K. 350
JUMLAH HARGA BAHAN 664,580.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 856,087.523


PEMBULATAN 856,080.000
1 BH Pengadaan dan Pemasangan U-DICTH 40.50.120 t 6 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 61,465.71 307,328.571
2 Tukang (L02) jam 2.0000 52,952.86 105,905.714
3 Mandor (L03) jam 1.0000 306,895.71 306,895.714
JUMLAH HARGA TENAGA KERJA 720,130.000
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 145,000.00 145,000.000
U-DICTH 40.50.120 t 6 cm K. 350
JUMLAH HARGA BAHAN 145,000.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 43,207.80 43,207.800
JUMLAH HARGA PERALATAN 137,043.894

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,002,173.894


PEMBULATAN 1,002,170.000

1 BH Pengadaan dan Pemasangan U-DICTH 50.50.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 830,220.00 830,220.000
U-DICTH 50.50.120 t 6 cm K. 350
JUMLAH HARGA BAHAN 830,220.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,021,727.523


PEMBULATAN 1,021,720.000

1 BH Pengadaan dan Pemasangan U-DICTH 60.60.120 t 8 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 1,073,630.00 1,073,630.000
U-DICTH 60.60.120 t 8 cm K. 350
JUMLAH HARGA BAHAN 1,073,630.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,265,137.523


PEMBULATAN 1,265,130.000
1 BH Pengadaan dan Pemasangan U-DICTH 60.70.120 t 10 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor 1.00 jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 1,561,460.00 1,561,460.000
U-DICTH 60.70.120 t 10 cm K. 350
JUMLAH HARGA BAHAN 1,561,460.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,752,967.523


PEMBULATAN 1,752,960.000

1 BH Pengadaan dan Pemasangan U-DICTH 80.80.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 2,184,630.00 2,184,630.000
U-DICTH 80.80.120 t 10 cm K. 350
JUMLAH HARGA BAHAN 2,184,630.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 2,376,137.523


PEMBULATAN 2,376,130.000

1 BH Pengadaan dan Pemasangan U-DICTH 80.90.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 2,148,270.00 2,148,270.000
U-DICTH 80.90.120 t 10 cm K. 350
JUMLAH HARGA BAHAN 2,148,270.000
C Peralatan
1 Crane Tb jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 2,339,777.523


PEMBULATAN 2,339,770.000
1 BH Pengadaan dan Pemasangan U-DICTH 100.100.120 t 10 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 U-DITCH Lebar 30 - 100 unit 1.0000 2,729,020.00 2,729,020.000
U-DICTH 100.100.120 t 10 cm K. 350
JUMLAH HARGA BAHAN 2,729,020.000
C Peralatan
1 Crane (E31) jam 0.2510 373,843.00 93,836.094
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 99,364.666

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 2,920,527.523


PEMBULATAN 2,920,520.000

1 BH Pengadaan dan Pemasangan CU 30.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 370,670.00 370,670.000
CU 30.120 t 12 cm K. 350
JUMLAH HARGA BAHAN 370,670.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 535,903.417


PEMBULATAN 535,900.000

1 BH Pengadaan dan Pemasangan CU 40.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 430,260.00 430,260.000
CU 40.120 t 12 cm K. 350
JUMLAH HARGA BAHAN 430,260.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 595,493.417


PEMBULATAN 595,490.000
1 BH Pengadaan dan Pemasangan CU 50.120 t 12 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 495,910.00 495,910.000
CU 50.120 t 12 cm K. 350
JUMLAH HARGA BAHAN 495,910.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 661,143.417


PEMBULATAN 661,140.000

1 BH Pengadaan dan Pemasangan CU 60.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 528,230.00 528,230.000
CU 60.120 t 12 cm K. 350
JUMLAH HARGA BAHAN 528,230.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 693,463.417


PEMBULATAN 693,460.000

1 BH Pengadaan dan Pemasangan CU 80.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 755,480.00 755,480.000
CU 80.120 t 12 cm K. 350
JUMLAH HARGA BAHAN 755,480.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 920,713.417


PEMBULATAN 920,710.000
1 BH Pengadaan dan Pemasangan CU 100.120 t 15 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja (L01) jam 5.0000 10,714.29 53,571.429
2 Tukang (L02) jam 2.0000 12,142.86 24,285.714
3 Mandor (L03) jam 1.0000 14,285.71 14,285.714
JUMLAH HARGA TENAGA KERJA 92,142.857
B Bahan
1 Cover U-ditch L 30-100 Unit 1.0000 957,480.00 957,480.000
CU 100.120 t 15 cm K. 350
JUMLAH HARGA BAHAN 957,480.000
C Peralatan
1 Crane (E31) jam 0.1807 373,843.00 67,561.988
2 Alat Bantu ls 1.0000 5,528.57 5,528.571
JUMLAH HARGA PERALATAN 73,090.559

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,122,713.417


PEMBULATAN 1,122,710.000

1 M' Pekerjaan Acian


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2000 75,000.00 15,000.000
2 Tukang batu L.04 OH 0.1000 85,000.00 8,500.000
3 Kepala tukang L.03 OH 0.0100 90,000.00 900.000
4 Mandor L.15 OH 0.0100 100,000.00 1,000.000
JUMLAH HARGA TENAGA KERJA 25,400.000
B Bahan
1 Portland Cement M.18 kg 3.2500 1,550.00 5,037.500
JUMLAH HARGA BAHAN 5,037.500
C Peralatan
JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 30,437.500

F PEMBULATAN 30,430.000

1 m2 Plesteran tebal 15mm Campuran 1:5


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja OH 0.3000 75,000.00 22,500.000
2 Tukang OH 0.1500 85,000.00 12,750.000
3 Kepala tukang OH 0.0150 90,000.00 1,350.000
4 Mandor OH 0.0300 100,000.00 3,000.000
JUMLAH HARGA TENAGA KERJA 39,600.000
B Bahan
1 Pasir Pasang m3 0.0160 425,000.00 6,800.000
2 Portland cement kg 5.1840 1,550.00 1,550.000
JUMLAH HARGA BAHAN 8,350.000
C Peralatan
JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 47,950.000

E Jumlah 47,950.000
PEMBULATAN 47,950.000
1 m3 Pembongkaran Pasangan batu (Mekanis)/Jack Hammer
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 9.6386 10,714.29 103,270.224
2 Mandor jam 1.2048 14,285.71 17,211.704
JUMLAH HARGA TENAGA KERJA 120,481.928
B Peralatan
1 Jack Hammrer jam 1.2048 43,552.00 52,472.289
JUMLAH HARGA PERALATAN 52,472.289

C Jumlah Harga Tenaga dan Peralatan (A + B + C) 172,954.217


PEMBULATAN 172,950.000

1 m2 Pemasangan Keramik Ukuran 20x20


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 75,000.00 52,500.000
2 Tukang batu L.04 OH 0.3500 85,000.00 29,750.000
3 Kepala tukang L.03 OH 0.0350 90,000.00 3,150.000
4 Mandor L.15 OH 0.0350 100,000.00 3,500.000
JUMLAH HARGA TENAGA KERJA 88,900.000
B Bahan
1 Keramik - bh 26.5000 2,150.94 57,000.000
2 Portland Cement - kg 10.4000 1,550.00 16,120.000
3 Pasir Pasang - m3 0.0450 425,000.00 19,125.000
4 Semen warna - kg 1.6200 2,200.00 3,564.000
JUMLAH HARGA BAHAN 95,809.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 184,709.000

E PEMBULATAN 184,700.000

1 m³ Beton mutu K - 175 ( Ready Mix)


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 1.0000 75,000.00 75,000.000
2 Tukang L.04 OH 0.2500 85,000.00 21,250.000
3 Kepala tukang L.03 OH 0.0250 90,000.00 2,250.000
4 Mandor L.15 OH 0.1000 100,000.00 10,000.000
JUMLAH HARGA TENAGA KERJA 108,500.000
B Bahan
1 Ready Mix K - 175 - m3 1.0200 1,010,000.00 1,030,200.000
JUMLAH HARGA BAHAN 1,030,200.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,138,700.000

Jumlah 1,138,700.000
F PEMBULATAN 1,138,700.000
1 m' Memasang Beton Pracetak 0,18x0,30x0,60
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.5833 75,000.00 43,747.500
2 Tukang batu L.04 OH 0.3500 85,000.00 29,750.000
3 Mandor L.15 OH 0.1167 100,000.00 11,670.000
JUMLAH HARGA TENAGA KERJA 85,167.500
B Bahan
1 Kerb Pracetak (0,18x0,30x0,60) - bh 1.6667 58,500.00 97,501.950
JUMLAH HARGA BAHAN 97,501.950
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 182,669.450

Jumlah 182,669.450
F PEMBULATAN 182,660.000

1 m' Memasang Beton Pracetak 0,10x0,20x0,40


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6667 75,000.00 50,002.500
2 Tukang batu L.04 OH 0.4000 85,000.00 34,000.000
3 Mandor L.15 OH 0.1333 100,000.00 13,330.000
JUMLAH HARGA TENAGA KERJA 97,332.500
B Bahan
1 Kerb Pracetak (0,10x0,20x0,40) - bh 2.5000 41,000.00 102,500.000
JUMLAH HARGA BAHAN 102,500.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 199,832.500

Jumlah 199,832.500
F PEMBULATAN 199,830.000

1 m2 Pengecatan Tembok
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0200 75,000.00 1,500.000
2 Tukang L.04 OH 0.0630 85,000.00 5,355.000
3 Kepala Tukang L.03 OH 0.0063 90,000.00 567.000
4 Mandor L.15 OH 0.0030 100,000.00 300.000
JUMLAH HARGA TENAGA KERJA 7,722.000
B Bahan
1 Cat tembok - kg 0.3600 47,000.00 16,920.000
JUMLAH HARGA BAHAN 16,920.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 24,642.000

Jumlah 24,642.000
F PEMBULATAN 24,640.000
1 m' Pemasangan Pipa Air Kotor 3" PVC AW
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0810 75,000.00 6,075.000
2 Tukang batu L.04 OH 0.1350 85,000.00 11,475.000
3 Kepala Tukang L.15 OH 0.0135 90,000.00 1,215.000
4 Mandor L.15 OH 0.0040 100,000.00 400.000
JUMLAH HARGA TENAGA KERJA 19,165.000
B Bahan
1 Pipa PVC 3" - btg 1.2000 55,000.00 66,000.000
Perlengkapan 35% % 0.3500 23,100.00 23,100.000
JUMLAH HARGA BAHAN 89,100.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 108,265.000

Jumlah 108,265.000
F PEMBULATAN 108,260.000

1 m3 Lapis Penetrasi t 5 cm (Lapen)


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 1.3880 9,375.00 13,012.500
3 Mandor L.15 Jam 0.1542 12,500.00 1,927.500
JUMLAH HARGA TENAGA KERJA 14,940.000
B Bahan
1 Batu Pecah2-3 m3 0.9429 350,000.00 330,015.000
2 Batu Pecah 1-2 m3 0.3929 375,000.00 147,337.500
3 Batu Pecah 1/2 - 1 m3 0.2200 375,000.00 82,500.000
4 Aspal Drum - kg 105.0000 25,000.00 2,625,000.000
JUMLAH HARGA BAHAN 3,184,852.500
C Peralatan
1 Three Wheel Roller 6-8 ton Jam 0.0771 126,093.00 9,721.770
JUMLAH HARGA PERALATAN 9,721.770

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,209,514.270

Jumlah 3,209,514.270
F PEMBULATAN 3,209,510.000

1 m2 Pasang Paving Block abu abu


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 0.8750 9,375.00 8,203.125
2 Tukang - Jam 0.3500 10,625.00 3,718.750
3 Mandor L.15 Jam 0.0875 12,500.00 1,093.750
JUMLAH HARGA TENAGA KERJA 13,015.625
B Bahan
1 Paving m2 1.0000 -
2 Pasir Urug m3 0.0629 275,000.00 17,297.500

JUMLAH HARGA BAHAN 17,297.500


C Peralatan

JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 30,313.125

Jumlah 30,313.125
F PEMBULATAN 30,310.000
DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN ANGGARAN 2017
PROPINSI : JAWA TIMUR KABUPATEN : BOJONEGORO

NO URAIAN SATUAN HARGA UPAH / BAHAN KET.


1 2 4 5 6

I UPAH
1 Mandor Orang/Hari Rp. 100,000.00 ###
2 Kepala Tukang Orang/Hari Rp. 90,000.00 ###
3 Tukang Orang/Hari Rp. 85,000.00 ###
4 Pekerja Orang/Hari Rp. 75,000.00 ###
5 Operator Terlatih Orang/Hari Rp. 175,000.00 ###
6 Pembantu Operator Orang/Hari Rp. 125,000.00 ###
II BAHAN
1 Batu kali pecah 1/2 - 1 cm m3 Rp. 375,000.00
2 Batu kali pecah 1 - 2 cm m3 Rp. 375,000.00 ###
3 Batu kali pecah 2 - 3 cm m3 Rp. 350,000.00 ###
4 Batu kali m3 Rp. 160,000.00 ###
5 U-DICTH 30.40.120 t 6 cm K. 350 bh Rp. 513,080.00 ###
6 U-DICTH 40.40.120 t 6 cm K. 350 bh Rp. 664,580.00 ###
7 U-DICTH 40.50.120 t 6 cm K. 350 bh Rp. 782,750.00 ###
8 U-DICTH 50.50.120 t 6 cm K. 350 bh Rp. 830,220.00 ###
9 U-DICTH 50.60.120 t 6 cm K. 350 bh Rp. 864,560.00 ###
10 U-DICTH 60.60.120 t 8 cm K. 350 bh Rp. 1,073,630.00 ###
11 U-DICTH 60.70.120 t 10 cm K. 350 bh Rp. 1,561,460.00 ###
12 U-DICTH 80.80.120 t 10 cm K. 350 bh Rp. 2,184,630.00 ###
13 U-DICTH 80.90.120 t 10 cm K. 350 bh Rp. 2,148,270.00 ###
14 U-DICTH 100.100.120 t 10 cm K. 350 bh Rp. 2,729,020.00 ###
15 CU 30.120 t 12 cm K. 350 bh Rp. 370,670.00 ###
16 CU 40.120 t 12 cm K. 350 bh Rp. 430,260.00 ###
17 CU 50.120 t 12 cm K. 350 bh Rp. 495,910.00 ###
18 CU 60.120 t 12 cm K. 350 bh Rp. 528,230.00 ###
19 CU 80.120 t 12 cm K. 350 bh Rp. 755,480.00 ###
20 CU 100.120 t 15 cm K. 350 bh Rp. 957,480.00 ###
21 BC 80.80.120 t 11 cm, 20 ton, K. 350 bh Rp. 3,090,600.00 ###
22 BC 100.100.120 t 12,5 cm, 20 ton, K. 350 bh Rp. 3,505,200.00 ###
23 Beton Ready Mix K-175 m3 Rp. 1,010,000.00 ###
24 Beton Ready Mix K-225 m3 Rp. 1,083,000.00 ###
25 Pasir Urug / Timbun m3 Rp. 275,000.00 ###
26 Tanah Urug m3 Rp. 145,000.00 ###
27 Semen ( PC ) 40 Kg zak Rp. 62,000.00 ###
28 Pasir Pasang m3 Rp. 425,000.00 ###
29 Paku Kg Rp. 20,000.00 ###
30 Pasir cor m3 Rp. 475,000.00 ###
31 Pudel m3 Rp. 160,000.00 ###
32 Besi beton Kg Rp. 20,000.00 ###
33 Kawat beton Kg Rp. 20,000.00 ###
34 Kayu bekisting m3 Rp. 5,300,000.00 ###
35 Tripleks 9 mm 120 x 240 cm Lbr Rp. 186,000.00 ###
36 Alat Bantu Set Rp. 100,000.00 ###
37 Pipa PVC 3'' (AW) Btg Rp. 220,000.00 ###
38 Air tawar Liter Rp. 400.00 ###
39 Bambu m Rp. 21,000.00 ###
40 Keramik 20x20 kw 1 m2 Rp. 57,000.00 ###
41 Semen Warna kg Rp. 22,000.00 ###
42 Sewa alat untuk Pemasangan U ditch ukuran.100,80,60 bh Rp. 75,000.00 ###
43 Sewa alat untuk Pemasangan U ditch ukuran.50,40,30 bh Rp. 60,000.00 ###
44 Sewa alat untuk Pemasangan CU ukuran. 100.80.60 bh Rp. 25,000.00 ###
45 Sewa Alat untuk Pemasangan CU ukuran. 50.40.30 bh Rp. 20,000.00 ###
46 Sewa Alat untuk Pemasangan BC bh Rp. 250,000.00 ###
47 Kerb Beton Pracetak 0,18x0,30x0,60 K 225 bh Rp. 58,500.00 ###
48 Kerb Beton Pracetak 0,10x0,20x0,40 K 225 bh Rp. 41,000.00 ###
49 Kuas 4 " bh Rp. 21,000.00 ###
50 Cat Tembok kg Rp. 47,000.00 ###
51 Palu bh Rp. 25,000.00
52 Linggis bh Rp. 45,000.00
53 Aspal kg Rp. 25,000.00

III SEWA ALAT

1 Stamper jam Rp. 57,514.00


2 Jack Hammer jam Rp. 43,552.00
3 Three Wheel Roller 6-8 ton jam Rp. 126,093.00
4 Exavator jam Rp. 429,439.00
5 Crane on track35 TON jam Rp. 373,843.00
ANALISA HARGA SATUAN PEKERJAAN

T.07 1 m3 Galian Tanah Biasa sedalam lebih kecil sama dengan 1 m


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 3.3333 10,000.000 33,333.333
2 Mandor L.15 Jam 0.6667 13,571.429 9,047.619
JUMLAH HARGA TENAGA KERJA 42,380.952
B Peralatan
1 alat bantu ls 1.0000 2,542.857 2,542.857
JUMLAH HARGA PERALATAN 2,542.857
Jumlah 44,923.810
B PEMBULATAN 44,920.000

1 m3 Galian Lumpur
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 OH 1.2000 70,000.000 84,000.000
2 Mandor L.15 OH 0.0450 95,000.000 4,275.000
JUMLAH HARGA TENAGA KERJA 88,275.000
Jumlah 88,275.000
B PEMBULATAN 88,270.000

1 m3 Galian tanah menggunakan Alat


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 Jam 0.0727 10,000.000 726.922
2 Mandor L.15 Jam 0.0363 13,571.429 493.269
JUMLAH HARGA TENAGA KERJA 1,220.191
B Bahan

JUMLAH HARGA BAHAN -


C Peralatan
1 Exavator jam 0.0363 429,439.000 15,608.433
JUMLAH HARGA PERALATAN 15,608.433

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 16,828.624

E PEMBULATAN 16,820.000

Timbunan
1 m3 Timbunan tanah atau Urugan tanah kembali
Harga Satuan
No. Uraian Kode Satuan Koefisien (Rp) Jumlah Harga (Rp)
A. TENAGA
1 Pekerja L.02 OH 0.3300 70,000.00 23,100.00
2 Mandor L.04 OH 0.0330 95,000.00 3,135.00
JUMLAH TENAGA KERJA 26,235.00
B. BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA PERALATAN

D Harga satuan pekerjaan ( A + B + C ) 26,235.00


E DIBULATKAN Rp 26,235.00
1 m3 Urugan Pedel pemadatan menggunakan stamper
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 jam 1.0258 10,000.000 10,258.061
2 Mandor L.15 jam 0.1465 13,571.429 1,988.808
JUMLAH HARGA TENAGA KERJA 12,246.869
B Bahan
Pedel Pilihan M3 1.1100 150,000.000 166,500.000
JUMLAH HARGA BAHAN 166,500.000
C Peralatan
1 Stamper jam 0.1070 57,514.000 6,153.305
JUMLAH HARGA PERALATAN 6,153.305

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 184,900.174

E PEMBULATAN 184,900.000
1 m³ Beton mutu, f'c = 14,5 Mpa (K175), slump (12±2) cm, w/c = 0,66
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.6500 70,000.000 115,500.000
2 Tukang batu L.04 OH 0.2750 80,000.000 22,000.000
3 Kepala tukang L.03 OH 0.0280 85,000.000 2,380.000
4 Mandor L.15 OH 0.0830 95,000.000 7,885.000
JUMLAH HARGA TENAGA KERJA 147,765.000
B Bahan
1 PC M.18 Kg 326.0000 1,500.000 489,000.000
2 PB M.09 Kg 760.0000 339.286 257,857.143
3 KR - Kg 1,029.0000 255.556 262,966.667
4 Air M.01 Ltr 215.0000 250.000 53,750.000
JUMLAH HARGA BAHAN 1,063,573.810
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,211,338.810

Jumlah 1,211,338.810
F PEMBULATAN 1,211,330.000

1 m3 Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3-6) cm, w/c = 0,87
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.2000 70,000.000 84,000.000
2 Tukang batu L.04 OH 0.2000 80,000.000 16,000.000
3 Kepala tukang L.03 OH 0.0200 85,000.000 1,700.000
4 Mandor L.15 OH 0.0600 95,000.000 5,700.000
JUMLAH HARGA TENAGA KERJA 107,400.000
B Bahan
1 PC M.18 Kg 230.0000 1,500.000 345,000.000
2 PB M.09 M3 893.0000 339.286 302,982.143
3 KR - M3 1,027.0000 255.556 262,455.556
4 Air M.01 Ltr 200.0000 250.000 50,000.000
JUMLAH HARGA BAHAN 960,437.698

C Jumlah Harga Tenaga, Bahan dan Peralatan (A + B ) 1,067,837.698


E PEMBULATAN 1,067,830.000
1 kg Pembesian dengan besi polos atau ulir
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0700 70,000.000 4,900.000
2 Tukang besi L.04 OH 0.0700 80,000.000 5,600.000
3 Kepala tukang L.03 OH 0.0070 85,000.000 595.000
4 Mandor L.15 OH 0.0040 95,000.000 380.000
JUMLAH HARGA TENAGA KERJA 11,475.000
B Bahan
1 Besi beton (polos/ulir) Kg 10.5000 15,000.000 157,500.000
2 Kawat beton M.75 Kg 0.1500 13,500.000 2,025.000
JUMLAH HARGA BAHAN 159,525.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 171,000.000

Harga Satuan Pekejaan /kg 17,100.000


Jumlah 17,100.000
E PEMBULATAN 17,100.000

1 m² Begisting untuk Dinding


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6600 70,000.000 46,200.000
2 Tukang kayu L.04 OH 0.3300 80,000.000 26,400.000
3 Kepala tukang L.03 OH 0.0330 85,000.000 2,805.000
4 Mandor L.15 OH 0.0330 95,000.000 3,135.000
JUMLAH HARGA TENAGA KERJA 78,540.000
B Bahan
1 M.61/ Lbr
0.3500
Multiflex 9 mm atau 12 mm M.17 170,000.000 59,500.000
2 Kaso 5/7 M.54 m³ 0.0300 530,000.000 15,900.000
3 Paku 5 cm dan 7 cm M.77 Kg 0.4000 16,500.000 6,600.000
JUMLAH HARGA BAHAN 82,000.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 160,540.000

Asumsi dipakai 3 kali 0.3333 X D 53,513.333


Jumlah 53,513.333
PEMBULATAN 53,510.000
1 BH Pengadaan dan Pemasangan BC 80.80.120 t 11 cm, 20 ton, K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.2500 95,000.000 23,750.000
JUMLAH HARGA TENAGA KERJA 23,750.000
B Bahan
1 BH 1.0000
BC 80.80.120 t 11 cm, 20 ton, K. 350 2,798,000.000 2,798,000.000
JUMLAH HARGA BAHAN 2,798,000.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 250,000.000 250,000.000
JUMLAH HARGA PERALATAN 250,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,071,750.000


PEMBULATAN 3,071,750.000

1 BH Pengadaan dan Pemasangan U-DICTH 30.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 30.40.120 t 6 cm K. 350 BH 1.0000 379,000.000 379,000.000
JUMLAH HARGA BAHAN 379,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 442,166.667


PEMBULATAN 442,160.000

1 BH Pengadaan dan Pemasangan U-DICTH 40.40.120 t 6 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 40.40.120 t 6 cm K. 350 BH 1.0000 522,000.000 522,000.000
JUMLAH HARGA BAHAN 522,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 585,166.667


PEMBULATAN 585,160.000
1 BH Pengadaan dan Pemasangan U-DICTH 50.50.120 t 6 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 50.50.120 t 6 cm K. 350 BH 1.0000 659,000.000 659,000.000
JUMLAH HARGA BAHAN 659,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 60,000.000 60,000.000
JUMLAH HARGA PERALATAN 60,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 722,166.667


PEMBULATAN 722,160.000

1 BH Pengadaan dan Pemasangan U-DICTH 60.60.120 t 8 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 60.60.120 t 8 cm K. 350 BH 1.0000 860,000.000 860,000.000
JUMLAH HARGA BAHAN 860,000.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 938,166.667


PEMBULATAN 938,160.000

1 BH Pengadaan dan Pemasangan U-DICTH 60.70.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 60.70.120 t 10 cm K. 350 Unit 1.0000 1,250,000.000 1,250,000.000
JUMLAH HARGA BAHAN 1,250,000.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,328,166.667


PEMBULATAN 1,328,160.000

1 BH Pengadaan dan Pemasangan U-DICTH 100.100.120 t 10 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0333 95,000.000 3,166.667
JUMLAH HARGA TENAGA KERJA 3,166.667
B Bahan
1 U-DICTH 100.100.120 t 10 cm K. 350 Unit 1.0000 1,889,000.000 1,889,000.000
JUMLAH HARGA BAHAN 1,889,000.000
C Lain - lain
1 Sewa Alat / Crane BH 1.0000 75,000.000 75,000.000
JUMLAH HARGA PERALATAN 75,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,967,166.667


PEMBULATAN 1,967,160.000
1 BH Pengadaan dan Pemasangan Cu 30.120 t 12 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 30.120 t 12 cm K. 350 Unit 1.0000 270,000.000 270,000.000
JUMLAH HARGA BAHAN 270,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 292,375.000


PEMBULATAN 292,370.000

1 BH Pengadaan dan Pemasangan Cu 40.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 40.120 t 12 cm K. 350 Unit 1.0000 340,000.000 340,000.000
JUMLAH HARGA BAHAN 340,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 362,375.000


PEMBULATAN 362,370.000

1 BH Pengadaan dan Pemasangan Cu 50.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 50.120 t 12 cm K. 350 Unit 1.0000 405,000.000 405,000.000
JUMLAH HARGA BAHAN 405,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 20,000.000 20,000.000
JUMLAH HARGA PERALATAN 20,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 427,375.000


PEMBULATAN 427,370.000

1 BH Pengadaan dan Pemasangan Cu 60.120 t 12 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 60.120 t 12 cm K. 350 Unit 1.0000 435,000.000 435,000.000
JUMLAH HARGA BAHAN 435,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 462,375.000


PEMBULATAN 462,370.000
1 BH Pengadaan dan Pemasangan Cu 80.120 t 12 cm K. 350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 80.120 t 12 cm K. 350 Unit 1.0000 549,000.000 549,000.000
JUMLAH HARGA BAHAN 549,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 576,375.000


PEMBULATAN 576,370.000

1 BH Pengadaan dan Pemasangan Cu 100.120 t 15 cm K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Mandor OH 0.0250 95,000.000 2,375.000
JUMLAH HARGA TENAGA KERJA 2,375.000
B Bahan
1 Cu 100.120 t 15 cm K. 350 Unit 1.0000 752,000.000 752,000.000
JUMLAH HARGA BAHAN 752,000.000
C Peralatan
1 Sewa Alat / Crane BH 1.0000 25,000.000 25,000.000
JUMLAH HARGA PERALATAN 25,000.000

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 779,375.000


PEMBULATAN 779,370.000

1 M' Pekerjaan Acian


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.2000 70,000.000 14,000.000
2 Tukang batu L.04 OH 0.1000 80,000.000 8,000.000
3 Kepala tukang L.03 OH 0.0100 85,000.000 850.000
4 Mandor L.15 OH 0.0100 95,000.000 950.000
JUMLAH HARGA TENAGA KERJA 23,800.000
B Bahan
1 Portland Cement M.18 kg 3.2500 1,500.000 4,875.000
JUMLAH HARGA BAHAN 4,875.000
C Peralatan
JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 28,675.000

F PEMBULATAN 28,670.000
1 m2 Plesteran tebal 15mm Campuran 1:5
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja OH 0.3000 70,000.000 21,000.000
2 Tukang OH 0.1500 80,000.000 12,000.000
3 Kepala tukang OH 0.0150 85,000.000 1,275.000
4 Mandor OH 0.0300 95,000.000 2,850.000
JUMLAH HARGA TENAGA KERJA 37,125.000
B Bahan
1 Pasir Pasang m3 0.0160 425,000.000 6,800.000
2 Portland cement kg 5.1840 1,500.000 1,500.000
JUMLAH HARGA BAHAN 8,300.000
C Peralatan
JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 45,425.000

E Jumlah 45,425.000
PEMBULATAN 45,420.000

1 m3 Pembongkaran Pasangan batu (Mekanis)/Jack Hammer


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 9.6386 10,000.000 96,385.542
2 Mandor jam 1.2048 11,428.571 13,769.363
JUMLAH HARGA TENAGA KERJA 110,154.905
B Peralatan
1 Jack Hammrer jam 1.2048 43,552.000 52,472.289
JUMLAH HARGA PERALATAN 52,472.289

C Jumlah Harga Tenaga dan Peralatan (A + B + C) 162,627.194


PEMBULATAN 162,620.000

1 m2 Pemasangan Keramik Ukuran 20x20


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.7000 70,000.000 49,000.000
2 Tukang batu L.04 OH 0.3500 80,000.000 28,000.000
3 Kepala tukang L.03 OH 0.0350 85,000.000 2,975.000
4 Mandor L.15 OH 0.0350 95,000.000 3,325.000
JUMLAH HARGA TENAGA KERJA 83,300.000
B Bahan
1 Keramik - bh 26.5000 1,962.264 52,000.000
2 Portland Cement - kg 10.4000 1,500.000 15,600.000
3 Pasir Pasang - m3 0.0450 425,000.000 19,125.000
4 Semen warna - kg 1.6200 2,100.000 3,402.000
JUMLAH HARGA BAHAN 90,127.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 173,427.000

E PEMBULATAN 173,420.000
1 m³ Beton mutu K - 175 ( Ready Mix)
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 1.0000 70,000.000 70,000.000
2 Tukang L.04 OH 0.2500 80,000.000 20,000.000
3 Kepala tukang L.03 OH 0.0250 85,000.000 2,125.000
4 Mandor L.15 OH 0.1000 95,000.000 9,500.000
JUMLAH HARGA TENAGA KERJA 101,625.000
B Bahan
1 Ready Mix K - 175 - m3 1.0200 1,035,000.000 1,055,700.000
JUMLAH HARGA BAHAN 1,055,700.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,157,325.000

Jumlah 1,157,325.000
F PEMBULATAN 1,157,320.000

1 m' Memasang Beton Pracetak 0,18x0,30x0,60


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.5833 70,000.000 40,831.000
2 Tukang batu L.04 OH 0.3500 80,000.000 28,000.000
3 Mandor L.15 OH 0.1167 95,000.000 11,086.500
JUMLAH HARGA TENAGA KERJA 79,917.500
B Bahan
1 Kerb Pracetak (0,18x0,30x0,60) - bh 1.6667 56,000.000 93,335.200
JUMLAH HARGA BAHAN 93,335.200
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 173,252.700

Jumlah 173,252.700
F PEMBULATAN 173,250.000

1 m' Memasang Beton Pracetak 0,10x0,20x0,40


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6667 70,000.000 46,669.000
2 Tukang batu L.04 OH 0.4000 80,000.000 32,000.000
3 Mandor L.15 OH 0.1333 95,000.000 12,663.500
JUMLAH HARGA TENAGA KERJA 91,332.500
B Bahan
1 Kerb Pracetak (0,10x0,20x0,40) - bh 2.5000 40,000.000 100,000.000
JUMLAH HARGA BAHAN 100,000.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 191,332.500

Jumlah 191,332.500
F PEMBULATAN 191,330.000
1 m2 Pengecatan Tembok
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0200 70,000.000 1,400.000
2 Tukang L.04 OH 0.0630 80,000.000 5,040.000
3 Kepala Tukang L.03 OH 0.0063 85,000.000 535.500
4 Mandor L.15 OH 0.0030 95,000.000 285.000
JUMLAH HARGA TENAGA KERJA 7,260.500
B Bahan
1 Cat tembok - kg 0.3600 21,000.000 7,560.000
JUMLAH HARGA BAHAN 7,560.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 14,820.500

Jumlah 14,820.500
F PEMBULATAN 14,820.000

1 m' Pemasangan Pipa Air Kotor 4" PVC AW


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0810 70,000.000 5,670.000
2 Tukang batu L.04 OH 0.1350 80,000.000 10,800.000
3 Kepala Tukang L.15 OH 0.0135 85,000.000 1,147.500
4 Mandor L.15 OH 0.0040 95,000.000 380.000
JUMLAH HARGA TENAGA KERJA 17,997.500
B Bahan
1 Pipa PVC 4'' - btg 1.2000 312,000.000 374,400.000
Perlengkapan 35% % 0.3500 131,040.000 131,040.000
JUMLAH HARGA BAHAN 505,440.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 523,437.500

Jumlah 523,437.500
F PEMBULATAN 523,430.000
1 m3 Lapis Penetrasi t 5 cm (Lapen)
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 1.3880 8,750.000 12,145.000
3 Mandor L.15 Jam 0.1542 11,875.000 1,831.125
JUMLAH HARGA TENAGA KERJA 13,976.125
B Bahan
1 Batu Pecah2-3 m3 0.9429 330,000.000 311,157.000
2 Batu Pecah 1-2 m3 0.3929 345,000.000 135,550.500
3 Batu Pecah 1/2 - 1 m3 0.2200 365,000.000 80,300.000
4 Aspal Drum - kg 105.0000 25,000.000 2,625,000.000
JUMLAH HARGA BAHAN 3,152,007.500
C Peralatan
1 Three Wheel Roller 6-8 ton Jam 0.0771 427,350.000 32,948.685
JUMLAH HARGA PERALATAN 32,948.685

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 3,198,932.310

Jumlah 3,198,932.310
F PEMBULATAN 3,198,930.000

1 m2 Pasang Paving Block abu abu


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 0.8750 8,750.000 7,656.250
2 Tukang - Jam 0.3500 10,000.000 3,500.000
3 Mandor L.15 Jam 0.0875 11,875.000 1,039.063
JUMLAH HARGA TENAGA KERJA 12,195.313
B Bahan
1 Paving m2 1.0000 -
2 Pasir Urug m3 0.0629 250,000.000 15,725.000

JUMLAH HARGA BAHAN 15,725.000


C Peralatan

JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 27,920.313

Jumlah 27,920.313
F PEMBULATAN 27,920.000
BACK UP PERHITUNGAN VOLUME ( BOQ )
KEGIATAN = PEMBANGUNAN SALURAN DRAINASE / GORONG-GORONG
PEKERJAAN = PEMBANGUNAN SALURAN DRAINASE DS. BALENREJO KEC. BALEN CROSSING JALAN
SUMBER DANA = APBD 2018
LOKASI = KEC. BALEN
UKURAN POKOK = PANJANG : 6.00 M
LEBAR : 0.80 M Jumlah CU : 5.00 BH
TINGGI : 0.80 M Jumlah Plat Dpn R : BH
TEBAL : 0.10 M

VOLUME
No. URAIAN PEKERJAAN HITUNGAN
V1 V2 ∑
P L T J
1 Galian Tanah P0-P1 6.00 x 1.00 x 0.17 x 1.00 m3 1.020

m3 1.020

V.gal x 30%
2 Urugan Tanah Kembali 0.000 x 0.3 m3 0.000
m3 -

3 Urugan Pedel Bawah Uditch 6.00 x 1.00 x 0.15 x 1.00 m3 0.900


m3 0.900

4 Urugan Pedel Tepi Saluran 0.00 x 0.50 x 0.12 x 1.00 m3 0.000


m3 -

JML L T
5 Plesteran 4.00 x 0.80 x 0.05 x 1.00 m2 0.160
4.00 x 0.05 x 0.80 x 2.00 m2 0.320
jml m2 0.480

6 U-DICTH 80.80.120 t 10 cm K. 350 bh 5.000

7 CU 80.120 t 12 cm K. 350 bh 5.000

KEGIATAN = PEMBANGUNAN SALURAN DRAINASE / GORONG-GORONG SALURAN (A)


PEKERJAAN = PEMBANGUNAN SALURAN DRAINASE DS. BALENREJO KEC. BALEN
SUMBER DANA = APBD 2018
LOKASI = KEC. BALEN
UKURAN POKOK = PANJANG : 94.80 M
LEBAR : 0.60 M Jumlah CU : 26.00 BH
TINGGI : 0.60 M Jumlah Plat Dpn R : BH 5.00
TEBAL : 0.08 M 4.00
4.00

VOLUME
No. URAIAN PEKERJAAN HITUNGAN
V1 V2 ∑
P L T J
1 Galian Tanah P0-P1 50.00 x 0.76 x 0.63 x 1.00 m3 23.940
P1-P2 44.80 x 0.76 x 0.68 x 1.00 m3 23.150
m3 47.090

V.gal x 30%
2 Urugan Tanah Kembali 0.000 x 0.3 m3 0.000
m3 -

3 Urugan Pedel Bawah Uditch 94.80 x 0.76 x 0.15 x 1.00 m3 10.810


m3 10.810
JML L T
4 Plesteran 78.00 x 0.60 x 0.04 x 1.00 m2 1.870
78.00 x 0.04 x 0.60 x 2.00 m2 3.740
jml m2 5.610

5 U-DITCH 50x50x120x6 cm K-350 bh 79.000

6 CU 50x120x12 cm K-350 bh 26.000


KEGIATAN = PEMBANGUNAN SALURAN DRAINASE / GORONG-GORONG SALURAN (B)
PEKERJAAN = PEMBANGUNAN SALURAN DRAINASE DS. BALENREJO KEC. BALEN
SUMBER DANA = APBD 2018
LOKASI = KEC. BALEN
UKURAN POKOK = PANJANG : 24.00 M
LEBAR : 0.60 M Jumlah CU : 9.00 BH
TINGGI : 0.60 M Jumlah Plat Dpn R : BH 5.00
TEBAL : 0.08 M 4.00
4.00

VOLUME
No. URAIAN PEKERJAAN HITUNGAN
V1 V2 ∑
P L T J
1 Galian Tanah P0-P1 24.00 x 0.76 x 0.70 x 1.00 m3 12.750
m3 12.750

V.gal x 30%
2 Urugan Tanah Kembali 0.000 x 0.3 m3 0.000
m3 -

3 Urugan Pedel Bawah Uditch 24.00 x 0.76 x 0.15 x 1.00 m3 2.740


m3 2.740
JML L T
4 Plesteran 19.00 x 0.60 x 0.04 x 1.00 m2 0.460
19.00 x 0.04 x 0.60 x 2.00 m2 0.910
jml m2 1.370

5 U-DITCH 50x50x120x6 cm K-350 bh 20.000

6 CU 50x120x12 cm K-350 bh 9.000


DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
BIAYA
No. URAIAN KODE HP KAP. HARGA SEWA KET.
ALAT ALAT/JAM
(di luar PPN)

1 COMPRESSOR 4000-6500 L\M E05 60.00 5,000.00 CPM/(L/m) 240,450,000.00 161,027.82


2 CONCRETE MIXER 0.3-0.6 M3 E06 20.00 500.00 Liter 23,625,000.00 74,416.04
3 DUMP TRUCK 3.5 TON E08 100.00 3.50 Ton 323,400,000.00 225,290.25
4 EXCAVATOR 80-140 HP E10 133.00 0.93 M3 1,083,600,000.00 429,439.77
5 TANDEM ROLLER 6-8 T. E17 82.00 8.10 Ton 512,400,000.00 245,818.85
6 VIBRATORY ROLLER 5-8 T. E19 82.00 7.05 Ton 806,400,000.00 310,050.25
7 CONCRETE VIBRATOR E20 5.50 25.00 - 13,125,000.00 52,300.23
8 WATER TANKER 3000-4500 L. E23 100.00 4,000.00 Liter 303,450,000.00 220,931.69
9 TAMPER E25 4.70 121.00 Ton 25,200,000.00 57,514.08
10 JACK HAMMER E26 - 1,330.00 - 19,530,000.00 43,552.51
11 CRANE ON TRACK 35 TON E31 125.00 35.00 Ton 1,005,900,000.00 387,791.82
12 BORE PILE (MANUAL) E33a - - 5,000,000.00 10,000.00
Pengadaan dan Pemasangan
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (a)


JENIS PEKERJAAN Pengadaan dan Pemasangan Boxculvert (Precast) ukuran 80x80x1.20.11
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 10,714.29 53,571.43


2. Tukang (L02) jam 2.0000 12,142.86 24,285.71
3. Mandor (L03) jam 1.0000 14,285.71 14,285.71

JUMLAH HARGA TENAGA 92,142.86

B. BAHAN

1. Boxculvert M100 unit 1.0000 3,090,600.00 3,090,600.00

JUMLAH HARGA BAHAN 3,090,600.00

C. PERALATAN
1. Crane 1 (E31) 0.5857 387,791.82 227,120.38
2 Alat Bantu LS 1.0000 5,528.57 5,528.57

JUMLAH HARGA PERALATAN 232,648.95

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,415,391.81


E. HARGA SATUAN PEKERJAAN (Pembulatan) 3,415,390.00
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (a)1


JENIS PEKERJAAN Pengadaan dan Pemasangan Boxculvert (Precast) ukuran 1.00x1.00x1.20.12,5
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 10,714.29 53,571.43


2. Tukang (L02) jam 2.0000 12,142.86 24,285.71
3. Mandor (L03) jam 1.0000 14,285.71 14,285.71

JUMLAH HARGA TENAGA 92,142.86

B. BAHAN

1. Boxculvert M100a unit 1.0000 3,505,200.00 3,505,200.00

JUMLAH HARGA BAHAN 3,505,200.00


C. PERALATAN
1. Crane 1 (E31) 0.7028 387,791.82 272,544.45
2 Alat Bantu LS 1.0000 5,528.57 5,528.57

JUMLAH HARGA PERALATAN 278,073.03

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,875,415.88


E. HARGA SATUAN PEKERJAAN (Pembulatan) 3,875,410.00
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (a)2


JENIS PEKERJAAN Pengadaan dan Pemasangan Boxculvert (Precast) ukuran 1.50x1.50x1.20.20
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 9,600.00 48,000.00


2. Tukang (L02) jam 2.0000 10,300.00 20,600.00
3. Mandor (L03) jam 1.0000 11,400.00 11,400.00

JUMLAH HARGA TENAGA 80,000.00

B. BAHAN

1. Boxculvert M100b unit 1.0000 9,660,000.00 9,660,000.00

JUMLAH HARGA BAHAN 9,660,000.00

C. PERALATAN
1. Crane 1 (E31) 0.7028 387,791.82 272,544.45
2 Alat Bantu LS 1.0000 4,800.00 4,800.00

JUMLAH HARGA PERALATAN 277,344.45

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 10,017,344.45


E. HARGA SATUAN PEKERJAAN (Pembulatan) 10,017,340.00
Analisa EI-721b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK Err:509
NAMA PAKET Err:509
Err:509
PROP / KAB / KODYA Err:509
ITEM PEMBAYARAN NO. 7.2 (1)b PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN Penyediaan Unit Pracetak Gelagar Tipe I : Bentang TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN Buah % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 20.5714 6,875.00 141,428.57


2. Tukang (L02) jam 5.7143 8,750.00 50,000.00
3. Mandor (L03) jam 1.1429 10,000.00 11,428.57

JUMLAH HARGA TENAGA 202,857.14

B. BAHAN

1. Beton K500 M3 6.6406 #REF! #REF!


2 Kabel prategang kg 443.6250 20,000.00 8,872,500.00
3 Tulangan baja (M39b) kg 884.3906 13,000.00 11,497,078.13
4 Anchorage kg 9.0000 480,000.00 4,320,000.00
5 Ducting M 225.0000 50,000.00 11,250,000.00

JUMLAH HARGA BAHAN #REF!


C. PERALATAN
1. Crane 1 (E31) 0.9036 411,918.54 372,215.55

3 Alat Bantu LS 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 0.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
0 0
0
0 0
0
0
0 0
0 0
0

ITEM PEMBAYARAN NO. 7.2 (2).b


JENIS PEKERJAAN Pemasangan Unit Pracetak Gelagar Tipe I : Bentang 25 meter
SATUAN PEMBAYARAN Buah

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

2 Crane 2 (E31) 0.9036 411,918.54 372,215.55

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 372,215.55


OVERHEAD & PROFIT 0.0 % x D 0.00
HARGA SATUAN PEKERJAAN ( D + E ) 372,215.55
Analisa EI-721c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK Err:509
NAMA PAKET Err:509
Err:509
PROP / KAB / KODYA Err:509
ITEM PEMBAYARAN NO. 7.2 (1)c PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN Penyediaan Unit Pracetak Gelagar Tipe I : Bentang TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN Buah 00 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 20.5714 6,875.00 141,428.57


2. Tukang (L02) jam 5.7143 8,750.00 50,000.00
3. Mandor (L03) jam 1.1429 10,000.00 11,428.57

JUMLAH HARGA TENAGA 202,857.14

B. BAHAN

1. Beton K500 M3 9.2969 #REF! #REF!


2 Kabel prategang kg 621.0750 20,000.00 12,421,500.00
3 Tulangan baja (M39b) kg 1,238.1469 13,000.00 16,095,909.38
4 Anchorage kg 12.0000 480,000.00 5,760,000.00
5 Ducting M 0.0000 50,000.00 0.00

JUMLAH HARGA BAHAN #REF!

C. PERALATAN
1. Crane 1 (E31) 0.9036 411,918.54 372,215.55
3 Alat Bantu LS 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 0.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
0 0
0
0 0
0
0
0 0
0 0
0

ITEM PEMBAYARAN NO. 7.2 (2)c : #REF!


JENIS PEKERJAAN Pemasangan Unit Pracetak Gelagar Tipe I : Bentang 35 m : #REF!
SATUAN PEMBAYARAN Buah : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

2 Crane 2 (E31) 0.9036 411,918.54 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 372,215.55


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 372,215.55
Analisa EI-721d

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK Err:509
NAMA PAKET Err:509
Err:509
PROP / KAB / KODYA Err:509
ITEM PEMBAYARAN NO. 7.2 (1).c PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN Penyediaan Unit Pracetak Gelagar Tipe I : Bentang .......
TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN Buah 00 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0000 6,875.00 0.00


2. Tukang (L02) jam 0.0000 8,750.00 0.00
3. Mandor (L03) jam 0.0000 10,000.00 0.00

JUMLAH HARGA TENAGA 0.00

B. BAHAN

1. Beton K500 M3 0.0000 #REF! #REF!


2 Kabel prategang kg 0.0000 20,000.00 0.00
3 Tulangan baja (M39b) kg 0.0000 13,000.00 0.00
4 Anchorage kg 0.0000 480,000.00 0.00
5 Ducting M 0.0000 50,000.00 0.00

JUMLAH HARGA BAHAN #REF!

C. PERALATAN
1. Crane 1 (E31) 0.9036 411,918.54 372,215.55

3 Alat Bantu LS 1.0000 0.00 0.00


JUMLAH HARGA PERALATAN 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 0.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
0 0
0
0 0
0
0
0 0
0 0
0

ITEM PEMBAYARAN NO. 7.2 (2).c


JENIS PEKERJAAN Pemasangan Unit Pracetak Gelagar Tipe I : Bentang .................... m
SATUAN PEMBAYARAN Buah

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

2 Crane 2 (E31) 0.9036 411,918.54 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 372,215.55


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 372,215.55
Analisa EI-722a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK Err:509
NAMA PAKET Err:509
Err:509
PROP / KAB / KODYA Err:509
ITEM PEMBAYARAN NO. 7.2 (3)a PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN Penyediaan Unit Pracetak Gelagar Tipe U : BentangTOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN Buah 00 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 20.5714 6,875.00 141,428.57


2. Tukang (L02) jam 5.7143 8,750.00 50,000.00
3. Mandor (L03) jam 1.1429 10,000.00 11,428.57

JUMLAH HARGA TENAGA 202,857.14

B. BAHAN

1. Beton K500 M3 4.2500 #REF! #REF!


2 Kabel prategang kg 283.9200 20,000.00 5,678,400.00
3 Tulangan baja (M39b) kg 566.0100 13,000.00 7,358,130.00
4 Anchorage kg 6.0000 480,000.00 2,880,000.00
5 Ducting M 0.0000 50,000.00 0.00

JUMLAH HARGA BAHAN #REF!

C. PERALATAN
1. Crane 1 (E31) 0.9036 411,918.54 372,215.55

3 Alat Bantu LS 1.0000 0.00 0.00


JUMLAH HARGA PERALATAN 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 0.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
0 0
0
0 0
0
0
0 0
0 0
0

ITEM PEMBAYARAN NO. 7.2 (4).a


JENIS PEKERJAAN Pemasangan Unit Pracetak Gelagar Tipe U : Bentang 16 meter
SATUAN PEMBAYARAN Buah

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

2 Crane 2 (E31) 0.9036 411,918.54 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 372,215.55


E. OVERHEAD & PROFIT 0.0 % x D 0.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 372,215.55
Analisa EI-722b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK Err:509
NAMA PAKET Err:509
Err:509
PROP / KAB / KODYA Err:509
ITEM PEMBAYARAN NO. 7.2 (3)b PERKIRAAN VOL. PEK. : #REF!
JENIS PEKERJAAN Penyediaan Unit Pracetak Gelagar Tipe U : Bentan TOTAL HARGA (Rp.) : #REF!
SATUAN PEMBAYARAN Buah 00 % THD. BIAYA PROYEK : #REF!

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 20.5714 6,875.00 141,428.57


2. Tukang (L02) jam 5.7143 8,750.00 50,000.00
3. Mandor (L03) jam 1.1429 10,000.00 11,428.57

JUMLAH HARGA TENAGA 202,857.14

B. BAHAN

1. Beton K500 M3 6.6406 #REF! #REF!


2 Kabel prategang kg 443.6250 20,000.00 8,872,500.00
3 Tulangan baja (M39b) kg 884.3906 13,000.00 11,497,078.13
4 Anchorage kg 9.0000 480,000.00 4,320,000.00
5 Ducting M 0.0000 50,000.00 0.00

JUMLAH HARGA BAHAN #REF!

C. PERALATAN
1. Crane 1 (E31) 0.9036 411,918.54 372,215.55

3 Alat Bantu LS 1.0000 0.00 0.00


JUMLAH HARGA PERALATAN 372,215.55

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) #REF!


E. OVERHEAD & PROFIT 0.0 % x D #REF!
F. HARGA SATUAN PEKERJAAN ( D + E ) #REF!
0 0
0
0 0
0
0
0 0
0 0
0

ITEM PEMBAYARAN NO. 7.2 (4).b


JENIS PEKERJAAN Pemasangan Unit Pracetak Gelagar Tipe U : Bentang 25 m
SATUAN PEMBAYARAN Buah

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

2 Crane 2 (E31) 0.9036 411,918.54 372,215.55


Pengadaan dan Pemasangan
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (b)


JENIS PEKERJAAN Pengadaan dan Pemasangan Uditch (Precast) lebar 30 - 100 cm
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 10,714.29 53,571.43


2. Tukang (L02) jam 2.0000 12,142.86 24,285.71
3. Mandor (L03) jam 1.0000 14,285.71 14,285.71

JUMLAH HARGA TENAGA 92,142.86

B. BAHAN

1. Uditch lebar 30 - 100 cm M101p unit 1.0000 1,463,700.00 1,463,700.00


U-Ditch 80 x 80 x 120 t;10 mesh 8

JUMLAH HARGA BAHAN 1,463,700.00

C. PERALATAN
1. Crane 1 (E31) 0.2510 387,791.82 97,337.31
2 Alat Bantu LS 1.0000 5,528.57 5,528.57

JUMLAH HARGA PERALATAN 102,865.88

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,658,708.73


E. HARGA SATUAN PEKERJAAN (Pembulatan) 1,658,700.00
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (b)1


JENIS PEKERJAAN Pengadaan dan Pemasangan Uditch (Precast) lebar > 100 cm
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 7,500.00 37,500.00


2. Tukang (L02) jam 2.0000 8,750.00 17,500.00
3. Mandor (L03) jam 1.0000 10,625.00 10,625.00

JUMLAH HARGA TENAGA 65,625.00

B. BAHAN

1. Uditch lebar > 100 cm M101w unit 1.0000 3,412,920.00 3,412,920.00

JUMLAH HARGA BAHAN 3,412,920.00

C. PERALATAN
1. Crane 1 (E31) 0.3012 387,791.82 116,804.77
2 Alat Bantu LS 1.0000 3,937.50 3,937.50

JUMLAH HARGA PERALATAN 120,742.27


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 3,599,287.27
E. HARGA SATUAN PEKERJAAN (Pembulatan) 3,599,280.00
Analisa EI-729

ANALISA HARGA SATUAN PEKERJAAN

ITEM PEMBAYARAN NO. 2.3 (c)


JENIS PEKERJAAN Pengadaan dan Pemasangan Cover Uditch (Precast)
SATUAN PEMBAYARAN unit

PERKIRAAN HARGA JUMLAH

NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 5.0000 9,600.00 48,000.00


2. Tukang (L02) jam 2.0000 10,300.00 20,600.00
3. Mandor (L03) jam 1.0000 11,400.00 11,400.00

JUMLAH HARGA TENAGA 80,000.00

B. BAHAN

1. Cover Uditch M106e unit 1.0000 559,980.00 559,980.00


Cover U-Ditch 80 x 120 x 12 mesh 10

JUMLAH HARGA BAHAN 559,980.00

C. PERALATAN
1. Crane 1 (E31) 0.1807 387,791.82 70,082.86
2 Alat Bantu LS 1.0000 4,800.00 4,800.00

JUMLAH HARGA PERALATAN 74,882.86

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 714,862.86


E. HARGA SATUAN PEKERJAAN (Pembulatan) 714,860.00

Anda mungkin juga menyukai