Anda di halaman 1dari 73

DAFTAR HARGA SATUAN UPAH DAN BAHAN

TAHUN ANGGARAN 2020


KATEGORI WILAYAH III BERAT

NO URAIAN SATUAN HARGA SATUAN (Rp.)


1 2 3 4

I UPAH
1 Pekerja Hari 101,000.00
2 Mandor Hari 141,000.00
3 Kepala Tukang Hari 161,000.00
4 Tukang Kayu Hari 131,000.00
5 Tukang Batu Hari 131,000.00
6 Tukang Cat Hari 131,000.00
7 Tukang Listrik Hari 131,000.00
8 Tukang Besi Hari 131,000.00
9 Tukang Masak Aspal Hari 131,000.00
10 Tukang Lebur Aspal Hari 131,000.00
11 Pekerja Bongkar Siram Hari 101,000.00
12 Penjaga Malam Hari 101,000.00
13 Sopir Hari 176,000.00
14 Pembantu Sopir Hari 101,000.00
15 Operator Terlatih Hari 201,000.00
16 Pembantu Operator Hari 126,000.00
17 Mekanik Hari 171,000.00

II BAHAN
A BAHAN BATU - BATUAN
1 Batu Kali / Gunung / Belah M3 163,400.00
2 Batu Pecah Alam ukr 5/10 M3 210,900.00
3 Batu Pecah Alam ukr 5/7 M3 210,900.00
4 Batu Pecah mesin ukr 3/4 M3 286,900.00
5 Batu Pecah mesin ukr 2/3 M3 286,900.00
6 Batu Pecah mesin ukr 1/2 M3 286,900.00

B BAHAN KERIKIL / KORAL


1 Kerikil Beton ( Alam ) M3 210,900.00
2 Split (Batu pecah 0,5-1 cm/mesin) M3 272,650.00
3 Krekel Timbunan (Sirtu) M3 149,150.00
4 Agregat Kasar ( Stone Cruiser ) M3 272,650.00
5 Agregat halus ( Stone Cruiser ) M3 277,400.00

C BAHAN PASIR
1 Pasir Pasang M3 168,150.00
2 Pasir Beton M3 182,400.00
3 Pasir Urug M3 87,400.00
4 Tanah Cadas ( Timbunan Pilihan ) M3 87,400.00
5 Tanah Urug / timbunan M3 73,150.00
6 Sirtu M3 149,150.00
7 Tanah Bunga (humus) M3 191,900.00
8 Abu Batu / Filler M3 286,900.00
9 Rumput Lempeng M2 31,036.50
10 Rumput Gajah Mini M2 42,531.50

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 1 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)
D BAHAN DINDING
1 Bata Merah Bakar Klas I Bh 1,520.00
2 Bata Merah Bakar Klas II Bh 1,045.00
3 Hollowbrick (HB) 20 Bh 3,800.00
4 Hollowbrick (HB) 10 Bh 4,275.00
5 Batako Bh 4,294.00

E BAHAN SEMEN
1 Semen Portland / PC Kg 1,529.50
2 Semen Warna (Tepung Alfa) Kg 15,675.00

F BAHAN KAYU
1 Kayu Banio (Papan) Klas I M3 3,597,887.50
2 Kayu Banio (Balok) Klas I M3 3,341,031.25
3 Kayu Marsawa (Papan) Klas II M3 3,089,400.00
4 Kayu Marsawa (Balok) Klas II M3 2,953,550.00
5 Kayu Merantih (Papan) Klas III M3 2,880,685.00
6 Kayu Merantih (Balok) Klas III M3 2,456,605.00
7 Kayu untuk perancah M3 1,840,720.00
8 Kayu Bekisting (Papan) Klas IV M3 1,949,400.00
9 Kayu Bekisting (Balok) Klas IV M3 1,901,900.00
10 Papan Lamberzering Btg 44,507.50
11 List Kayu 1/ 4 cm Btg 16,245.00
12 List Profil uk 3x3 Btg 16,340.00
13 List Profil uk 3,5x3,5 Btg 15,105.00
14 Kayu Pancang Buah 10,421.50
15 Dolken Kayu Galam dia. 8-10/3 m Btg 54,245.00
16 Penjaga jarak Bekisting / Spancer Bh 712.50
17 Lem Kayu Kg 15,152.50

G BAHAN PAKU
1 Paku Biasa 1/2"-5" Kg 15,675.00
2 Paku Triplek Kg 21,850.00
3 Paku Seng Gelombang Kg 27,550.00
4 Paku Atap Anti Karat Kg 29,450.00
5 Paku Beton 2" - 3" Kotak 15,200.00

H BAHAN PIPA
PIPA GIP SNI Medium
1 GIP Ø 1/2" M' 38,475.00
2 GIP Ø 3/4" M' 47,975.00
3 GIP Ø 1" M' 66,975.00
4 GIP Ø 1 1/2" M' 105,450.00
5 GIP Ø 2" M' 138,700.00
6 GIP Ø 3" M' 228,950.00
7 GIP Ø 4" M' 328,700.00
PIPA PVC Tipe AW
8 PVC Ø 1/2" M' 6,650.00
9 PVC Ø 3/4" M' 8,550.00
10 PVC Ø 1" M' 12,350.00

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 2 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)
11 PVC Ø 1 1/4" M' 17,100.00
12 PVC Ø 1 1/2" M' 19,475.00
13 PVC Ø 2" M' 24,225.00
14 PVC Ø 3" M' 47,975.00
15 PVC Ø 4" M' 85,975.00
16 PVC Ø 6" M' 190,950.00
17 PVC Ø 8" M' 309,700.00
PIPA PVC SNI
18 PVC Ø 1 1/4" Btg 101,887.50
19 PVC Ø 1 1/2" Btg 129,437.50
20 PVC Ø 2" Btg 247,427.50
21 PVC Ø 2 1/2" Btg 297,255.00
22 PVC Ø 3" Btg 360,620.00
23 PVC Ø 4" Btg 444,505.00
24 PVC Ø 6" Btg 809,827.50
25 PVC Ø 8" Btg 1,244,310.00
26 Kran 1/2" stainless steel Bh 57,950.00
27 Kran 3/4" BC Onda Bh 60,325.00
28 TBA Bh 5,225.00
29 Lem Pipa Tube 9,975.00
30 Plastik Hitam M2 10,450.00
31 Knee 1/2 " Bh 9,025.00

I BAHAN PLAFOND
1 Multiplek Tebal 12 mm Lbr 163,780.00
2 Multiplek Tebal 9 mm Lbr 129,200.00
3 Triplek Tebal 6 mm Lbr 105,450.00
4 Triplek Tebal 4 mm Lbr 95,950.00
5 Triplek Jati tbl 3 mm Lbr 145,350.00
6 Triplek Jati tbl 4 mm Lbr 190,950.00
7 Triplek Jati tbl 6 mm Lbr 285,950.00
8 Teak Wood Tebal 3 mm Lbr 206,340.00
9 Plywood 4 mm Lbr 78,850.00
10 Plywood 9 mm Lbr 141,550.00
11 Gypsum Board tebal 9 mm Lbr 110,200.00
12 Gypsum Board tebal 6 mm Lbr 66,975.00
13 Formika Lbr 109,725.00
14 GRC Board tebal 4 mm Lbr 71,725.00
15 GRC Board tebal 6 mm Lbr 133,950.00
16 GRC Board tebal 8 mm Lbr 186,200.00
17 GRC Board tebal 10 mm Lbr 247,950.00
18 List Profil Gypsum M' 19,475.00
19 Compound Gypsum Kg 7,125.00
20 Compound GRC Kg 7,125.00
22 Plafond PVC Board 6 mm (putih) L= 20cm M' 24,225.00
23 Plafond PVC Board 8 mm (putih) L=20cm M' 26,125.00
24 Plafond PVC Board 8 mm (motif) L= 20cm M' 30,875.00
25 Kalsi Board tebal 4 mm Lbr 66,975.00
26 Kalsi Board tebal 8 mm Lbr 171,475.00
27 Papan Listplank GRC M' 28,975.00
28 ACP (Almunium Composit Panel) Merk Seven t=3mm (luar) Lbr 736,725.00
29 ACP (Almunium Composit Panel) Merk Seven t=3mm (dalam) Lbr 603,725.00

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 3 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)

J BAHAN BESI DAN ALUMINIUM


1 Kawat Berduri rol (50M) 145,350.00
2 Kawat Beton Kg 16,150.00
3 Besi Beton Polos Kg 14,915.00
4 Besi Beton Ulir KS Kg 15,912.50
5 Besi Profil IWF Kg 16,625.00
6 Besi L 70.70.7 Batang 409,925.00
7 Besi L 50.50.5 Batang 72,200.00
8 Besi L 40.40.4 Batang 67,450.00
9 Besi L 30.30.3 Batang 41,800.00
10 Besi Wiremesh kg 15,295.00
11 Kabel Prestress kg 261,345.00
12 Kawat Nyamuk M2 24,700.00
13 Kawat Harmonika M2 34,200.00
14 Kawat Ayak M2 24,700.00
15 Besi Plat Baja tbl 2 mm M2 449,350.00
16 Pagar BRC (tinggi 0,90 m) Lbr 199,500.00
17 Pagar BRC (tinggi 1,20 m) Lbr 230,850.00
18 Truss C-75, 0.75 M' 21,850.00
19 Truss C-75, 0.60 M' 19,760.00
20 Reng R.33-0.45 M' 11,400.00
21 Baut (Screw Driver) Canal dan Reng Bh 475.00
22 Baut (Screw Driver) Atap 45 Bh 617.50
23 Baut (Screw Driver) Atap 40 Bh 522.50
24 Baut (Screw Driver) Atap 35 Bh 437.00
25 Dynabolt dia 8 pjg 4-5 cm Bh 29,735.00
26 Profil Aluminium 4" (Ex. Alexindo) warna Silver M' 123,500.00
27 Profil Aluminium 3" (Ex. Alexindo) warna Silver M' 90,250.00
28 Profil Aluminium 4" (Ex. Alexindo) warna Hitam/Coklat M' 135,850.00
29 Profil Aluminium 3" (Ex. Alexindo) warna Hitam/Coklat M' 99,275.00
30 Profil Aluminium 4" (Ex. Alexindo) warna Coating Powder M' 176,605.00
31 Profil Aluminium 3" (Ex. Alexindo) warna Coating Powder M' 129,057.50
32 Rangka Pintu Aluminium M' 229,900.00
33 Rangka Jendela Aluminium M' 86,212.50
32 Skrup Fixer Bh 9,975.00
33 Sealant Tube 37,050.00
34 Karet Kaca M' 5,225.00
35 Sandblash M2 95,950.00
36 Furing Channel Zincalume M' 4,138.20
37 Hollow Zincalume 40x40x400 Btg 37,050.00
38 Hollow Zincalume 20x40x400 Btg 24,700.00
39 Hollow Zincalume 30x30x400 Btg 33,250.00
40 Besi Hollow 1,6x20x40x600 Btg 96,558.00
41 Besi Hollow 1,8x20x40x600 Btg 111,815.00
42 Besi Hollow 1,6x40x40x600 Btg 169,290.00
43 Besi Hollow 2x40x40x600 Btg 178,600.00
44 Kawat Las Listrik Kg 33,725.00
45 Sewa Alat Las Listrik (Diesel) Jam 39,187.50
46 Pintu Folding Gate tebal 1 mm M2 905,350.00
47 Rolling door aluminium M2 430,350.00
48 Pintu aluminium M2 335,350.00
49 Baut diameter. 3/4" x 4" Bh 14,915.00

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 4 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)

K BAHAN ATAP
1 Atap Seng BJLS 20 K bd 11 Biasa (Angsa Mas) Lbr 58,900.00
2 Atap Seng BJLS 20 K bd 11 Warna Lbr 69,350.00
3 Genteng Metal sakura 0,3 cm Lbr 55,100.00
4 Genteng Metal Multiroof 0,3 cm Lbr 92,150.00
5 Atap Plastik Warna Putih Acrylic Lbr 110,200.00
6 Atap Plastik Fiber Glass Lbr 142,500.00
7 Perabung Seng Plat BJLS 20 biasa Lbr 23,275.00
8 Perabung Seng Plat BJLS 20 warna Lbr 25,650.00
9 Perabung Atap Genteng Metal Lbr 43,367.50
10 Perabung Atap Genteng Metal Multiroof persegi Bh 28,025.00
11 Perabung Atap Genteng Metal Multiroof bulat Bh 29,640.00
12 Bola-bola Atap Genteng Metal Bh 24,225.00
13 Bola-bola Atap Seng Lbr 20,900.00
14 Talang Air PVC Btg 58,900.00
15 Seng plat lebar 0,9 M' t-0,03 M1 59,850.00

L BAHAN PELAPIS LANTAI DAN DINDING


1 Keramik uk. 40 x 40 cm (biasa) Kotak 78,375.00
2 Keramik uk. 40 x 40 cm (bermotif) Kotak 83,837.50
3 Keramik uk. 30 x 30 cm (biasa) Kotak 78,375.00
4 Keramik uk. 30 x 30 cm (bermotif) Kotak 83,837.50
5 Keramik uk. 20 x 20 cm (biasa) Kotak 75,050.00
6 Keramik uk. 20 x 20 cm (bermotif) Kotak 80,275.00
7 Keramik uk. 25 x 25 cm (bermotif) Kotak 76,950.00
8 Keramik uk. 20 x 25 cm (biasa) Kotak 76,950.00
9 Keramik uk. 20 x 25 cm (bermotif) Kotak 78,137.50
10 Keramik uk. 25 x 40 cm (biasa) Kotak 101,175.00
11 Keramik uk. 20 x 40 cm (biasa) Kotak 71,487.50
12 Keramik uk. 60 x 60 cm (biasa) Kotak 181,450.00
13 Keramik uk. 60 x 60 cm (bermotif) Kotak 181,450.00
14 Granit uk. 80 x 80 cm polos Bh 89,616.35
15 Granit uk. 60 x 60 cm polos Bh 46,017.05
16 Granit uk. 40 x 40 cm Bh 27,550.00
17 Granit uk. 30 x 30 cm Bh 23,750.00
18 Plint kramik 10 x 20 Bh 5,225.00
19 Plint kramik 10 x 10 Bh 3,135.00
20 Plint kramik 5 x 20 Bh 7,125.00
21 Bon-bon keramik M1 5,225.00
22 Batu Andesit Bintik Bakar M2 197,505.00
23 Paving Blok Tebal 6 Natural Bh 4,275.00
24 Paving Blok Tebal 6 Warna Bh 5,225.00
25 Paving Blok Tebal 8 Natural Bh 4,750.00
26 Paving Blok Tebal 8 Warna Bh 5,225.00
27 Paving Blok Tebal 6 Hexagon K-225 Bh 11,875.00
28 Paving Blok Tebal 6 balok K-225 Bh 11,637.50
29 Paving Blok Tebal 8 Hexagon K-225 Bh 12,587.50
30 Paving Blok Tebal 8 balok K-225 Bh 12,350.00
31 Paving Blok Tebal 6 Natural K-400 pabrikan halfpave 10x10 Bh 5,462.50
32 Paving Blok Tebal 6 Warna Hexagon K-400 Bh 8,550.00
33 Paving Blok Tebal 8 Natural K-400 pabrikan halfpave 10x10 Bh 5,937.50
34 Kanstein L (pabrikasi) Bh 38,950.00
35 Kanstein I (pabrikasi) Bh 38,950.00

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 5 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)

M BAHAN KACA
1 Kaca Polos Tebal 3 mm M2 94,050.00
2 Kaca Polos Tebal 5 mm M2 114,950.00
3 Kaca Polos Tebal 8 mm M2 304,950.00
4 Rayben Tebal 3 mm M2 113,050.00
5 Rayben Tebal 5 mm M2 129,200.00
6 Rayben Tebal 8 mm M2 399,950.00
7 Kaca Tebal 12 mm Biru M2 1,045,950.00
8 Kaca Tempered Tebal 8 mm M2 760,950.00
9 Kaca Tempered Tebal 12 mm M2 1,045,950.00

N BAHAN PENGGANTUNG DAN PENGUNCI


1 Grendel Jendela Bh 9,975.00
2 Grendel Pintu Bh 15,200.00
3 Tangan-Tangan Jendela (kuningan) Bh 14,725.00
4 Engsel Pintu 4" Bh 16,625.00
5 Engsel Jendela 3" Bh 14,725.00
6 Kunci tanam Merk SES Asli Bh 333,450.00
7 Kunci Tanam Antika/Cltali/Seiss Bh 218,215.00
8 Hak angin Bh 11,875.00
9 Kunci Pintu Aluminium Bh 218,215.00
10 Engsel tanam Set 564,537.50
11 Tarikan Pintu Alumunium Pasang 156,750.00
12 Door Closer Bh 261,250.00

O BAHAN CAT
1 Cat Dasar Kayu Kg 33,250.00
2 Dempul Kayu Kg 38,000.00
3 Cat kayu/besi platoon Kg 51,300.00
4 Cat kayu/besi avian Kg 58,900.00
5 Menie Kayu Kg 33,250.00
6 Menie Besi Kg 33,568.25
7 Cat Dasar Tembok Kg 33,250.00
8 Cat Tembok Matex Kg 19,000.00
9 Cat Tembok Dulux/Catylac Kg 23,750.00
10 Plamer Tembok Alkali Kg 24,700.00
11 Cat Tembok Weathershield Exterior (dulux) Kg 106,400.00
12 Cat impra Kg 70,300.00
13 Cat residu Ltr 9,500.00
14 Cat Ultran Politur Kg 61,655.00
15 Cat Melanin (Clear) Kg 68,970.00
16 Dempul/Plamir Tembok Kg 23,750.00
17 Vernis Ltr 22,325.00
18 Wood Filler Ltr 47,025.00
19 Sanding Siller Ltr 65,835.00
20 Wood Stain Ltr 63,745.00
21 Dempul Impra Kg 38,000.00
22 Thinner Ltr 18,715.00
23 Minyak Bekisting ltr 12,540.00
24 Amplas Lbr 7,942.00
25 Kuas Bh 21,422.50
26 Waterproofing / aqua proof Kg 64,790.00

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 6 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)
27 Soda Api ltr 70,553.18
28 Sabun Kg 50,540.00

P BAHAN MINYAK DAN PELUMAS


1 Solar ( Non Subsidi) Ltr 9,927.50
2 Bensin/Premium ( Non Subsidi) Ltr 9,497.15
3 Pelumas Ltr 36,100.00
4 Aspal 60/70 drum Kg 19,427.50
5 Air Ltr 95.00

Q BAHAN SANITAIR
1 Kloset Jongkok (American Standart) Bh 153,900.00
2 Kloset Jongkok KIA Bh 248,900.00
3 Kloset Duduk komplit pakai tangki siram + shower (KIA) Set 1,714,750.00
4 Kloset Duduk standar (KIA) Set 669,750.00
5 Urinoir Bh 3,753,450.00
6 Wastafel merk KIA 1 Set + kaca Set 828,115.00
7 Bak Mandi Fibreglass 65x65 Bh 460,940.00
8 Tangki Air Kap. 2 m3 Bh 3,448,500.00
9 Tangki Air Kap. 1000 L (Tedmond) Bh 1,789,325.00
10 Tangki Air Kap. 3 m3 Bh 5,367,975.00
11 Pelampung Otomatis 1/2 Bh 104,500.00
12 Pompa Air Otomatis Bh 574,750.00
13 Floor drain Bh 9,975.00
14 Bak cuci piring Bh 386,840.00

R INSTALASI LISTRIK
1 Biaya Penyambungan ( BP ) Watt 900 Ls 855,000.00
2 Biaya Penyambungan ( BP ) Watt 1300 Ls 1,235,000.00
3 Biaya Penyambungan ( BP ) Watt 2200 Ls 2,090,000.00
4 Pas. Instalasi Listrik dan Jaringan Ttk 190,000.00

S GORONG-GORONG / BUIS BETON


GORONG-GORONG BETON BERTULANG
1 DIA 100 cm M1 561,592.50
2 DIA 80 cm M1 457,852.50
3 DIA 60 cm M1 353,115.00
4 DIA 40 cm M1 248,377.50
5 DIA 30 cm M1 196,507.50
GORONG-GORONG BETON TANPA TULANGAN
6 DIA 100 cm M1 227,729.25
7 DIA 80 cm M1 188,926.50
8 DIA 60 cm M1 144,637.50
9 DIA 40 cm M1 94,563.00
10 DIA 30 cm M1 75,610.50

T BETON READY MIX


1 Beton Ready Mix K-125 M3 837,330.00
2 Beton Ready Mix K-150 M3 907,231.00
3 Beton Ready Mix K-175 M3 1,154,012.50
4 Beton Ready Mix K-200 M3 1,176,456.25

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 7 dari 73
NO URAIAN SATUAN HARGA SATUAN (Rp.)
5 Beton Ready Mix K-225 M3 1,198,900.00
6 Beton Ready Mix K-250 M3 1,243,550.00
7 Beton Ready Mix K-275 M3 1,313,612.50
8 Beton Ready Mix K-300 M3 1,383,437.50
9 Beton Ready Mix K-350 M3 1,567,975.00
10 Concrete Pump / Pengecoran < 40 M3 3,657,500.00
11 Concrete Pump / Pengecoran (Penambahan /jam) > 40 M3 71,250.00
12 Sewa Concrete Mixer / Molen Hari 285,000.00
13 Upah Angkut Beton Ready Mix / Km ≥ 30 Km 9,927.50

Arosuka, Januari 2020


Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kabupaten Solok

SYAIFUL. SY, ST, MT


NIP. 19650110 199403 1 006

Daftar Harga Satuan Upah dan Bahan Wil III Bdang CK T.A. 2020 Hal. 8 dari 73
ANALISA HARGA SATUAN PEKERJAAN (AHSP) WILAYAH III BERAT
PEKERJAAN KECIPTAKARYAAN
TAHUN ANGGARAN 2020

No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f

I PEKERJAAN PERSIAPAN

1 A. 2.2.1.9. 1 M2 PEMBERSIHAN LAPANGAN DAN PERATAAN


0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 17,150.00 Rp. 17,150.00
Overhead 10% Rp. 1,715.00
Jumlah Rp. 18,865.00
Dibulatkan Rp. 18,865.00

2 A. 2.2.1.13. 1 M3 PEMBONGKARAN BETON BERTULANG


13.3340 Pekerja Rp. 101,000.00 Rp. 1,346,734.00
0.6660 Mandor Rp. 141,000.00 Rp. 93,906.00
Rp. 1,440,640.00 Rp. 1,440,640.00
Overhead 10% Rp. 144,064.00
Jumlah Rp. 1,584,704.00
Dibulatkan Rp. 1,584,704.00

3 A. 2.2.1.14. 1 M3 PEMBONGKARAN DINDING TEMBOK BATA


6.6670 Pekerja Rp. 101,000.00 Rp. 673,367.00
0.0333 Mandor Rp. 141,000.00 Rp. 4,695.30
Rp. 678,062.30 Rp. 678,062.30
Overhead 10% Rp. 67,806.23
Jumlah Rp. 745,868.53
Dibulatkan Rp. 745,868.00

4 A. 2.2.1.4. 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00
0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00

0.0070 M3 Kayu Papan 3/20 Rp. 1,949,400.00 Rp. 13,645.80


0.0120 M3 Kayu 5/7 / Kayu Pancang Rp. 744,392.86 Rp. 8,932.71
0.0200 Kg Paku Biasa (2" - 5") Rp. 15,675.00 Rp. 313.50
Rp. 25,515.00 Rp. 22,892.01 Rp. 48,407.01
Overhead 10% Rp. 4,840.70
Jumlah Rp. 53,247.72
Dibulatkan Rp. 53,247.00

5 A. 2.2.1.2 1 M' PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M


0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00
0.4000 Tukang Kayu Rp. 131,000.00 Rp. 52,400.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0200 Mandor Rp. 141,000.00 Rp. 2,820.00

1.250 Btg Dolken Kayu dia. 8-10/400 cm Rp. 54,245.00 Rp. 67,806.25
2.500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 3,823.75
1.200 Lbr Seng Gelombang 3"-5" Rp. 58,900.00 Rp. 70,680.00
0.005 M3 Pasir Beton Rp. 182,400.00 Rp. 912.00
0.009 M3 Koral Beton Rp. 210,900.00 Rp. 1,898.10
0.072 M3 Kayu 5/7 Rp. 744,392.86 Rp. 53,596.29
0.060 Kg Paku Biasa 2"-5" Rp. 15,675.00 Rp. 940.50
0.450 Kg Menie Besi Rp. 33,568.25 Rp. 15,105.71
Rp. 78,640.00 Rp. 214,762.60 Rp. 293,402.60
Overhead 10% Rp. 29,340.26
Jumlah Rp. 322,742.86
Dibulatkan Rp. 322,742.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 9 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
6 A. 2.2.1.15. PEMASANGAN 1 M2 PAGAR KAWAT JARING GALVANIS
0.0420 Pekerja Rp. 101,000.00 Rp. 4,242.00
0.0040 Tukang Rp. 131,000.00 Rp. 524.00
0.0020 Kepala Tukang Rp. 161,000.00 Rp. 322.00
0.0420 Mandor Rp. 141,000.00 Rp. 5,922.00

1.2000 M2 Kawat jaring Rp. 34,200.00 Rp. 41,040.00


1.3500 M' Besi diameter 10 mm Rp. 9,202.56 Rp. 12,423.45
3.0000 Cm Pengelasan Rp. 3,502.00 Rp. 10,506.00
Rp. 11,010.00 Rp. 63,969.45 Rp. 74,979.45
Overhead 10% Rp. 7,497.94
Jumlah Rp. 82,477.39
Dibulatkan Rp. 82,477.00

II PEKERJAAN TANAH

1 A.2.3.1.1. 1 M3 PENGGALIAN TANAH BIASA SEDALAM 1 METER


0.7500 Pekerja Rp. 101,000.00 Rp. 75,750.00
0.0250 Mandor Rp. 141,000.00 Rp. 3,525.00
Rp. 79,275.00 Rp. 79,275.00
Overhead 10% Rp. 7,927.50
Jumlah Rp. 87,202.50
Dibulatkan Rp. 87,202.00

2 A.2.3.1.2 1 M3 PENGGALIAN TANAH BIASA SEDALAM 2 METER


0.9000 Pekerja Rp. 101,000.00 Rp. 90,900.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 97,245.00 Rp. 97,245.00
Overhead 10% Rp. 9,724.50
Jumlah Rp. 106,969.50
Dibulatkan Rp. 106,969.00

3 A.2.3.1.3 1 M3 PENGGALIAN TANAH BIASA SEDALAM 3 METER


1.0500 Pekerja Rp. 101,000.00 Rp. 106,050.00
0.0670 Mandor Rp. 141,000.00 Rp. 9,447.00
Rp. 115,497.00 Rp. 115,497.00
Overhead 10% Rp. 11,549.70
Jumlah Rp. 127,046.70
Dibulatkan Rp. 127,046.00

4 A.2.3.1.4. 1 M3 PENGGALIAN TANAH KERAS SEDALAM 1 METER


1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00
0.0320 Mandor Rp. 141,000.00 Rp. 4,512.00
Rp. 105,512.00 Rp. 105,512.00
Overhead 10% Rp. 10,551.20
Jumlah Rp. 116,063.20
Dibulatkan Rp. 116,063.00

5 A.2.3.1.5. 1 M3 PENGGALIAN TANAH CADAS SEDALAM 1 METER


1.5000 Pekerja Rp. 101,000.00 Rp. 151,500.00
0.0600 Mandor Rp. 141,000.00 Rp. 8,460.00
Rp. 159,960.00 Rp. 159,960.00
Overhead 10% Rp. 15,996.00
Jumlah Rp. 175,956.00
Dibulatkan Rp. 175,956.00

6 A.2.3.1.61 M3 PENGGALIAN TANAH LUMPUR SEDALAM 1 METER


1.2000 Pekerja Rp. 101,000.00 Rp. 121,200.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 127,545.00 Rp. 127,545.00
Overhead 10% Rp. 12,754.50
Jumlah Rp. 140,299.50
Dibulatkan Rp. 140,299.00

7 1 M3 PENGGALIAN TANAH BERBATU SEDALAM ≤ 1 METER


1.3510 Pekerja Rp. 101,000.00 Rp. 136,451.00
0.1351 Mandor Rp. 141,000.00 Rp. 19,049.10
Rp. 155,500.10 Rp. 155,500.10
Overhead 10% Rp. 15,550.01
Jumlah Rp. 171,050.11
Dibulatkan Rp. 171,050.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 10 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f

8 1 M3 PENGGALIAN TANAH BERBATU SEDALAM > 1 S.D 2 METER


1.5000 Pekerja Rp. 101,000.00 Rp. 151,500.00
0.1500 Mandor Rp. 141,000.00 Rp. 21,150.00
Rp. 172,650.00 Rp. 172,650.00
Overhead 10% Rp. 17,265.00
Jumlah Rp. 189,915.00
Dibulatkan Rp. 189,915.00

9 1 M3 PENGGALIAN TANAH BERBATU SEDALAM > 2 S.D 3 METER


1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00
0.1650 Mandor Rp. 141,000.00 Rp. 23,265.00
Rp. 189,915.00 Rp. 189,915.00
Overhead 10% Rp. 18,991.50
Jumlah Rp. 208,906.50
Dibulatkan Rp. 208,906.00

10 A.2.3.1.7. 1 M2 PENGERJAAN STRIPPING TEBING SETINGGI 1 METER


0.0500 Pekerja Rp. 101,000.00 Rp. 5,050.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 5,755.00 Rp. 5,755.00
Overhead 10% Rp. 575.50
Jumlah Rp. 6,330.50
Dibulatkan Rp. 6,330.00

11 A.2.3.1.8. 1 M3 PEMBUANGAN TANAH SEJAUH 30 M'


0.3300 Pekerja Rp. 101,000.00 Rp. 33,330.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00
Rp. 34,740.00 Rp. 34,740.00
Overhead 10% Rp. 3,474.00
Jumlah Rp. 38,214.00
Dibulatkan Rp. 38,214.00

12 A.2.3.1.9. 1 M3 PENGURUGAN KEMBALI GALIAN TANAH


0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 57,550.00 Rp. 57,550.00
Overhead 10% Rp. 5,755.00
Jumlah Rp. 63,305.00
Dibulatkan Rp. 63,305.00

13 A.2.3.1.10. 1 M3 PEMADATAN TANAH (PER 20 CM)


0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 57,550.00 Rp. 57,550.00
Overhead 10% Rp. 5,755.00
Jumlah Rp. 63,305.00
Dibulatkan Rp. 63,305.00

14 A.2.3.1.11 1 M3 PENGURUGAN DENGAN PASIR URUG


0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00

1.2000 M3 Pasir Urug Rp. 87,400.00 Rp. 104,880.00


Rp. 31,710.00 Rp. 104,880.00 Rp. 136,590.00
Overhead 10% Rp. 13,659.00
Jumlah Rp. 150,249.00
Dibulatkan Rp. 150,249.00

15 A.2.3.1.14 1 M3 PENGURUGAN SIRTU PADAT


0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00
0.0250 Mandor Rp. 141,000.00 Rp. 3,525.00

1.2000 M3 Sirtu Rp. 149,150.00 Rp. 178,980.00


Rp. 28,775.00 Rp. 178,980.00 Rp. 207,755.00
Overhead 10% Rp. 20,775.50
Jumlah Rp. 228,530.50
Dibulatkan Rp. 228,530.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 11 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
16 A.2.3.1.14 1 M3 PENGURUGAN CADAS PADAT
0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00
0.0250 Mandor Rp. 141,000.00 Rp. 3,525.00

1.2000 M3 Cadas Rp. 87,400.00 Rp. 104,880.00


Rp. 28,775.00 Rp. 104,880.00 Rp. 133,655.00
Overhead 10% Rp. 13,365.50
Jumlah Rp. 147,020.50
Dibulatkan Rp. 147,020.00

17 1 M3 PENGURUGAN TANAH TIMBUNAN


0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00
0.0250 Mandor Rp. 141,000.00 Rp. 3,525.00

1.2000 M3 Tanah timbunan Rp. 73,150.00 Rp. 87,780.00


Rp. 28,775.00 Rp. 87,780.00 Rp. 116,555.00
Overhead 10% Rp. 11,655.50
Jumlah Rp. 128,210.50
Dibulatkan Rp. 128,210.00

18 PEMASANGAN RUMPUT LEMPENG / 1 M2


0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00

1.1000 M2 Rumput Lempeng Rp. 31,036.50 Rp. 34,140.15


0.050 M3 Tanah Bunga ( Humus ) Rp. 191,900.00 Rp. 9,595.00
Rp. 16,560.00 Rp. 43,735.15 Rp. 60,295.15
Overhead 10% Rp. 6,029.52
Jumlah Rp. 66,324.67
Dibulatkan Rp. 66,324.00

19 PEMASANGAN RUMPUT GAJAH MINI / 1 M2


0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00

1.1000 M2 Rumput Gajah Mini Rp. 42,531.50 Rp. 46,784.65


0.050 M3 Tanah Bunga ( Humus ) Rp. 191,900.00 Rp. 9,595.00
Rp. 16,560.00 Rp. 56,379.65 Rp. 72,939.65
Overhead 10% Rp. 7,293.97
Jumlah Rp. 80,233.62
Dibulatkan Rp. 80,233.00

III PEKERJAAN PONDASI

1 A.3.2.1.1 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 3 PP


1.5000 Pekerja Rp. 101,000.00 Rp. 151,500.00
0.7500 Tukang Batu Rp. 131,000.00 Rp. 98,250.00
0.0750 Kepala Tukang Rp. 161,000.00 Rp. 12,075.00
0.0750 Mandor Rp. 141,000.00 Rp. 10,575.00

1.2000 M3 Batu Belah 15 cm/20 cm Rp. 163,400.00 Rp. 196,080.00


0.4850 M3 Pasir Pasang Rp. 168,150.00 Rp. 81,552.75
202.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 308,959.00
Rp. 272,400.00 Rp. 586,591.75 Rp. 858,991.75
Overhead 10% Rp. 85,899.18
Jumlah Rp. 944,890.93
Dibulatkan Rp. 944,890.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 12 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
2 A.3.2.1.2 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 4 PP
1.5000 Pekerja Rp. 101,000.00 Rp. 151,500.00
0.7500 Tukang Batu Rp. 131,000.00 Rp. 98,250.00
0.0750 Kepala Tukang Rp. 161,000.00 Rp. 12,075.00
0.0750 Mandor Rp. 141,000.00 Rp. 10,575.00

1.2000 M3 Batu Belah 15 cm/20 cm Rp. 163,400.00 Rp. 196,080.00


0.5200 M3 Pasir Pasang Rp. 168,150.00 Rp. 87,438.00
163.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 249,308.50
Rp. 272,400.00 Rp. 532,826.50 Rp. 805,226.50
Overhead 10% Rp. 80,522.65
Jumlah Rp. 885,749.15
Dibulatkan Rp. 885,749.00

3 A.3.2.1.3. 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 5 PP


1.5000 Pekerja Rp. 101,000.00 Rp. 151,500.00
0.7500 Tukang Batu Rp. 131,000.00 Rp. 98,250.00
0.0750 Kepala Tukang Rp. 161,000.00 Rp. 12,075.00
0.0750 Mandor Rp. 141,000.00 Rp. 10,575.00

1.2000 M3 Batu Belah 15 cm/20 cm Rp. 163,400.00 Rp. 196,080.00


0.5440 M3 Pasir Pasang Rp. 168,150.00 Rp. 91,473.60
136.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 208,012.00
Rp. 272,400.00 Rp. 495,565.60 Rp. 767,965.60
Overhead 10% Rp. 76,796.56
Jumlah Rp. 844,762.16
Dibulatkan Rp. 844,762.00

4 A.3.2.1.9. 1 M3 PEMASANGAN BATU KOSONG (ANSTAMPING)


0.7800 Pekerja Rp. 101,000.00 Rp. 78,780.00
0.3900 Tukang Batu Rp. 131,000.00 Rp. 51,090.00
0.0390 Kepala Tukang Rp. 161,000.00 Rp. 6,279.00
0.0390 Mandor Rp. 141,000.00 Rp. 5,499.00

1.2000 M3 Batu Belah 15/20 cm Rp. 163,400.00 Rp. 196,080.00


0.4320 M3 Pasir Urug Rp. 87,400.00 Rp. 37,756.80
Rp. 141,648.00 Rp. 233,836.80 Rp. 375,484.80
Overhead 10% Rp. 37,548.48
Jumlah Rp. 413,033.28
Dibulatkan Rp. 413,033.00

5 A.3.2.1.10. 1 M3 PEMASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR


DAN 40% BATU BELAH
3.4000 Pekerja Rp. 101,000.00 Rp. 343,400.00
0.8500 Tukang Batu Rp. 131,000.00 Rp. 111,350.00
0.0850 Kepala Tukang Rp. 161,000.00 Rp. 13,685.00
0.1700 Mandor Rp. 141,000.00 Rp. 23,970.00

194.000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 296,723.00


0.3120 M3 Pasir Beton Rp. 182,400.00 Rp. 56,908.80
0.4680 M3 Koral Beton Rp. 210,900.00 Rp. 98,701.20
0.4800 M3 Batu Belah 15cm/20 cm Rp. 163,400.00 Rp. 78,432.00
Rp. 492,405.00 Rp. 530,765.00 Rp. 1,023,170.00
Overhead 10% Rp. 102,317.00
Jumlah Rp. 1,125,487.00
Dibulatkan Rp. 1,125,487.00

6 A.3.2.1.11. 1 M3 PEMASANGAN PONDASI SUMURAN DIAMETER 100 CM


2.4000 Pekerja Rp. 101,000.00 Rp. 242,400.00
0.8000 Tukang Batu Rp. 131,000.00 Rp. 104,800.00
0.0800 Kepala Tukang Rp. 161,000.00 Rp. 12,880.00
0.1190 Mandor Rp. 141,000.00 Rp. 16,779.00

0.4500 M3 Batu Belah 15/20 cm Rp. 163,400.00 Rp. 73,530.00


0.3120 M3 Pasir Beton Rp. 182,400.00 Rp. 56,908.80
0.4680 M3 Kerekel beton Rp. 210,900.00 Rp. 98,701.20
194.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 296,723.00
Rp. 376,859.00 Rp. 525,863.00 Rp. 902,722.00
Overhead 10% Rp. 90,272.20
Jumlah Rp. 992,994.20
Dibulatkan Rp. 992,994.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 13 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f

7 1 M2 MEMASANG CETAKAN CINCIN SUMURAN


0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00
0.0100 Tukang Kayu Rp. 131,000.00 Rp. 1,310.00
0.5000 Kepala Tukang Rp. 161,000.00 Rp. 80,500.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00

0.0400 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40


0.4000 Kg Paku 5 cm - 10 cm Rp. 15,675.00 Rp. 6,270.00
0.0150 Ltr Minyak Bekisting Rp. 12,540.00 Rp. 188.10
0.6170 Lbr Seng Plat Rp. 59,850.00 Rp. 36,927.45
Rp. 109,060.00 Rp. 158,612.95 Rp. 267,672.95
Overhead 10% Rp. 26,767.30
Jumlah Rp. 294,440.25
Dibulatkan Rp. 294,440.00

8 A.3.2.1.11. PEMANSANGAN 1 M3 PONDASI SUMURAN, DIAMETER 100 cm

2.4000 Pekerja Rp. 101,000.00 Rp. 242,400.00


0.8000 Tukang Batu Rp. 131,000.00 Rp. 104,800.00
0.0800 Kepala Tukang Rp. 161,000.00 Rp. 12,880.00
0.1190 Mandor Rp. 141,000.00 Rp. 16,779.00

0.4500 Batu belah Rp. 163,400.00 Rp. 73,530.00


194.0000 Semen Portland Rp. 1,529.50 Rp. 296,723.00
0.3120 Pasir beton Rp. 182,400.00 Rp. 56,908.80
0.4680 Kerikil Rp. 210,900.00 Rp. 98,701.20
376,859.00 Rp. 525,863.00 Rp. 902,722.00
Overhead 10% Rp. 90,272.20
Jumlah Rp. 992,994.20
Dibulatkan Rp. 992,994.00

IV PEKERJAAN PASANGAN DINDING

1 A. 4.4.1.1. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU


CAMPURAN SPESI 1 PC : 2 PP
0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00
0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00

140.000 Bh Bata Merah Rp. 1,045.00 Rp. 146,300.00


0.0800 M3 Pasir Pasang Rp. 168,150.00 Rp. 13,452.00
43.5000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 66,533.25
Rp. 94,250.00 Rp. 226,285.25 Rp. 320,535.25
Overhead 10% Rp. 32,053.53
Jumlah Rp. 352,588.78
Dibulatkan Rp. 352,588.00

2 A. 4.4.1.2. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU


CAMPURAN SPESI 1 PC : 3 PP
0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00
0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00

140.000 Bh Bata Merah Rp. 1,045.00 Rp. 146,300.00


0.0910 M3 Pasir Pasang Rp. 168,150.00 Rp. 15,301.65
32.9500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 50,397.03
Rp. 94,250.00 Rp. 211,998.68 Rp. 306,248.68
Overhead 10% Rp. 30,624.87
Jumlah Rp. 336,873.54
Dibulatkan Rp. 336,873.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 14 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
3 A. 4.4.1.3. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU
CAMPURAN SPESI 1 PC : 4 PP
0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00
0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00

140.000 Bh Bata Merah Rp. 1,045.00 Rp. 146,300.00


0.0930 M3 Pasir Pasang Rp. 168,150.00 Rp. 15,637.95
26.5500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 40,608.23
Rp. 94,250.00 Rp. 202,546.18 Rp. 296,796.18
Overhead 10% Rp. 29,679.62
Jumlah Rp. 326,475.79
Dibulatkan Rp. 326,475.00

4 A. 4.4.1.4. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU


CAMPURAN SPESI 1 PC : 5 PP
0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00
0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00

140.000 Bh Bata Merah Rp. 1,045.00 Rp. 146,300.00


0.1020 M3 Pasir Pasang Rp. 168,150.00 Rp. 17,151.30
22.2000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 33,954.90
Rp. 94,250.00 Rp. 197,406.20 Rp. 291,656.20
Overhead 10% Rp. 29,165.62
Jumlah Rp. 320,821.82
Dibulatkan Rp. 320,821.00

5 A. 4.4.1.5 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU


CAMPURAN SPESI 1 PC : 6 PP
0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00
0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00

140.000 Bh Bata Merah Rp. 1,045.00 Rp. 146,300.00


0.1220 M3 Pasir Pasang Rp. 168,150.00 Rp. 20,514.30
18.5000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 28,295.75
Rp. 94,250.00 Rp. 195,110.05 Rp. 289,360.05
Overhead 10% Rp. 28,936.01
Jumlah Rp. 318,296.06
Dibulatkan Rp. 318,296.00

6 A. 4.4.1.7 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU


CAMPURAN SPESI 1 PC : 2 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

70.000 Bh Bata Merah Rp. 1,045.00 Rp. 73,150.00


0.0380 M3 Pasir Pasang Rp. 168,150.00 Rp. 6,389.70
18.9500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 28,984.03
Rp. 47,125.00 Rp. 108,523.73 Rp. 155,648.73
Overhead 10% Rp. 15,564.87
Jumlah Rp. 171,213.60
Dibulatkan Rp. 171,213.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 15 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
7 A. 4.4.1.8 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU
CAMPURAN SPESI 1 PC : 3 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

70.000 Bh Bata Merah Rp. 1,045.00 Rp. 73,150.00


0.0400 M3 Pasir Pasang Rp. 168,150.00 Rp. 6,726.00
14.3700 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 21,978.92
Rp. 47,125.00 Rp. 101,854.92 Rp. 148,979.92
Overhead 10% Rp. 14,897.99
Jumlah Rp. 163,877.91
Dibulatkan Rp. 163,877.00

8 A.4.4.1.9 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU


CAMPURAN SPESI 1 PC : 4 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

70.000 Bh Bata Merah Rp. 1,045.00 Rp. 73,150.00


0.0430 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,230.45
11.5000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 17,589.25
Rp. 47,125.00 Rp. 97,969.70 Rp. 145,094.70
Overhead 10% Rp. 14,509.47
Jumlah Rp. 159,604.17
Dibulatkan Rp. 159,604.00

9 A. 4.4.1.10 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU


CAMPURAN SPESI 1 PC : 5 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

70.000 Bh Bata Merah Rp. 1,045.00 Rp. 73,150.00


0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
9.6800 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,805.56
Rp. 47,125.00 Rp. 95,522.31 Rp. 142,647.31
Overhead 10% Rp. 14,264.73
Jumlah Rp. 156,912.04
Dibulatkan Rp. 156,912.00

10 A. 4.4.1.11 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU


CAMPURAN SPESI 1 PC : 6 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

70.000 Bh Bata Merah Rp. 1,045.00 Rp. 73,150.00


0.0490 M3 Pasir Pasang Rp. 168,150.00 Rp. 8,239.35
8.3200 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 12,725.44
Rp. 47,125.00 Rp. 94,114.79 Rp. 141,239.79
Overhead 10% Rp. 14,123.98
Jumlah Rp. 155,363.77
Dibulatkan Rp. 155,363.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 16 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
11 A. 4.4.1.8 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 20, CAMPURAN SPESI 1 PC : 3 PP
0.3200 Pekerja Rp. 101,000.00 Rp. 32,320.00
0.1200 Tukang Batu Rp. 131,000.00 Rp. 15,720.00
0.0120 Kepala Tukang Rp. 161,000.00 Rp. 1,932.00
0.0160 Mandor Rp. 141,000.00 Rp. 2,256.00

12.500 Bh Hollow block (HB.20) Rp. 3,800.00 Rp. 47,500.00


22.7400 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 34,780.83
0.5500 M3 Pasir Pasang Rp. 168,150.00 Rp. 92,482.50
0.2800 Kg Besi Angkur dia. 8 mm Rp. 14,915.00 Rp. 4,176.20
Rp. 52,228.00 Rp. 178,939.53 Rp. 231,167.53
Overhead 10% Rp. 23,116.75
Jumlah Rp. 254,284.28
Dibulatkan Rp. 254,284.00

12 A. 4.4.1.19 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 20, CAMPURAN SPESI 1 PC : 4 PP


0.3200 Pekerja Rp. 101,000.00 Rp. 32,320.00
0.1200 Tukang Batu Rp. 131,000.00 Rp. 15,720.00
0.0120 Kepala Tukang Rp. 161,000.00 Rp. 1,932.00
0.0160 Mandor Rp. 141,000.00 Rp. 2,256.00

12.500 Bh Hollow block (HB.20) Rp. 3,800.00 Rp. 47,500.00


18.2000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 27,836.90
0.5820 M3 Pasir Pasang Rp. 168,150.00 Rp. 97,863.30
0.2800 Kg Besi Angkur dia. 8 mm Rp. 14,915.00 Rp. 4,176.20
Rp. 52,228.00 Rp. 177,376.40 Rp. 229,604.40
Overhead 10% Rp. 22,960.44
Jumlah Rp. 252,564.84
Dibulatkan Rp. 252,564.00

13 A. 4.4.1.20 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 10, CAMPURAN SPESI 1 PC : 3 PP


0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

12.500 Bh Hollow block (HB.10) Rp. 4,275.00 Rp. 53,437.50


15.1600 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 23,187.22
0.3640 M3 Pasir Pasang Rp. 168,150.00 Rp. 61,206.60
0.2800 Kg Besi Angkur dia. 8 mm Rp. 14,915.00 Rp. 4,176.20
Rp. 47,125.00 Rp. 142,007.52 Rp. 189,132.52
Overhead 10% Rp. 18,913.25
Jumlah Rp. 208,045.77
Dibulatkan Rp. 208,045.00

14 A. 4.4.1.21 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 10, CAMPURAN SPESI 1 PC : 4 PP


0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

12.500 Bh Hollow block (HB.10) Rp. 4,275.00 Rp. 53,437.50


12.1300 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 18,552.84
0.3880 M3 Pasir Pasang Rp. 168,150.00 Rp. 65,242.20
0.2800 Kg Besi Angkur dia. 8 mm Rp. 14,915.00 Rp. 4,176.20
Rp. 47,125.00 Rp. 141,408.74 Rp. 188,533.74
Overhead 10% Rp. 18,853.37
Jumlah Rp. 207,387.11
Dibulatkan Rp. 207,387.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 17 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
15 A. 4.4.1.22 1 M2 PEMASANGAN DINDING TERAWANG (ROOSTER) 12X11X24 CM
CAMPURAN SPESI 1 PC : 3 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

30.0000 Bh Bata Rooster Rp. 1,045.00 Rp. 31,350.00


11.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 16,824.50
0.0350 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,885.25
Rp. 47,125.00 Rp. 54,059.75 Rp. 101,184.75
Overhead 10% Rp. 10,118.48
Jumlah Rp. 111,303.23
Dibulatkan Rp. 111,303.00

16 A. 4.4.1.23 1 M2 PEMASANGAN DINDING TERAWANG (ROOSTER) 12X11X24 CM


CAMPURAN SPESI 1 PC : 4 PP
0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

30.0000 Bh Roster/Terawang Rp. 1,045.00 Rp. 31,350.00


11.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 16,824.50
0.0350 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,885.25
Rp. 47,125.00 Rp. 54,059.75 Rp. 101,184.75
Overhead 10% Rp. 10,118.48
Jumlah Rp. 111,303.23
Dibulatkan Rp. 111,303.00

17 1 M2 PEMASANGAN DINDING BATAKO, CAMPURAN SPESI 1 PC : 4 PP


0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00
0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00

12.500 Bh Batako Rp. 4,294.00 Rp. 53,675.00


12.1300 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 18,552.84
0.0388 M3 Pasir Pasang Rp. 168,150.00 Rp. 6,524.22
0.2800 Kg Besi Angkur dia. 8 mm Rp. 14,915.00 Rp. 4,176.20
Rp. 47,125.00 Rp. 82,928.26 Rp. 130,053.26
Overhead 10% Rp. 13,005.33
Jumlah Rp. 143,058.58
Dibulatkan Rp. 143,058.00

V PEKERJAAN PLESTERAN

1 A.4.4.2.1 1 M2 PEMASANGAN PLESTERAN 1 PC : 1 PP, TEBAL 15 mm


15.5040 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 23,713.37
0.0160 M3 Pasir Pasang Rp. 168,150.00 Rp. 2,690.40

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 26,403.77 Rp. 80,883.77
Overhead 10% Rp. 8,088.38
Jumlah Rp. 88,972.14
Dibulatkan Rp. 88,972.00

2 A.4.4.2.2. 1 M2 PEMASANGAN PLESTERAN 1 PC : 2 PP, TEBAL 15 mm


10.2240 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,637.61
0.0200 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,363.00

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 19,000.61 Rp. 73,480.61
Overhead 10% Rp. 7,348.06

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 18 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
Jumlah Rp. 80,828.67
Dibulatkan Rp. 80,828.00

3 A.4.4.2.3. 1 M2 PEMASANGAN PLESTERAN 1 PC : 3 PP, TEBAL 15 mm


7.7760 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 11,893.39
0.0230 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,867.45

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 15,760.84 Rp. 70,240.84
Overhead 10% Rp. 7,024.08
Jumlah Rp. 77,264.93
Dibulatkan Rp. 77,264.00

4 A.4.4.2.4. 1 M2 PEMASANGAN PLESTERAN 1 PC : 4 PP, TEBAL 15 mm


6.2400 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,544.08
0.0240 M3 Pasir Pasang Rp. 168,150.00 Rp. 4,035.60

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 13,579.68 Rp. 68,059.68
Overhead 10% Rp. 6,805.97
Jumlah Rp. 74,865.65
Dibulatkan Rp. 74,865.00

5 A.4.4.2.5. 1 M2 PEMASANGAN PLESTERAN 1 PC : 5 PP, TEBAL 15 mm


5.1840 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 7,928.93
0.0260 M3 Pasir Pasang Rp. 168,150.00 Rp. 4,371.90

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 12,300.83 Rp. 66,780.83
Overhead 10% Rp. 6,678.08
Jumlah Rp. 73,458.91
Dibulatkan Rp. 73,458.00

6 A.4.4.2.6. 1 M2 PEMASANGAN PLESTERAN 1 PC : 6 PP, TEBAL 15 mm


4.4160 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 6,754.27
0.0270 M3 Pasir Pasang Rp. 168,150.00 Rp. 4,540.05

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 11,294.32 Rp. 65,774.32
Overhead 10% Rp. 6,577.43
Jumlah Rp. 72,351.75
Dibulatkan Rp. 72,351.00

7 A.4.4.2.13. 1 M2 PEMASANGAN PLESTERAN 1 PC : 1 PP, TEBAL 20 mm


13.6320 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 20,850.14
0.0270 M3 Pasir Pasang Rp. 168,150.00 Rp. 4,540.05

0.4000 Pekerja Rp. 101,000.00 Rp. 40,400.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0220 Mandor Rp. 141,000.00 Rp. 3,102.00
Rp. 72,922.00 Rp. 25,390.19 Rp. 98,312.19
Overhead 10% Rp. 9,831.22
Jumlah Rp. 108,143.41
Dibulatkan Rp. 108,143.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 19 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
8 A.4.4.2.14. 1 M2 PEMASANGAN PLESTERAN 1 PC : 3 PP, TEBAL 20 mm
10.3680 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,857.86
0.0310 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,212.65

0.4000 Pekerja Rp. 101,000.00 Rp. 40,400.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0130 Mandor Rp. 141,000.00 Rp. 1,833.00
Rp. 71,653.00 Rp. 21,070.51 Rp. 92,723.51
Overhead 10% Rp. 9,272.35
Jumlah Rp. 101,995.86
Dibulatkan Rp. 101,995.00

9 A.4.4.2.15. 1 M2 PEMASANGAN PLESTERAN 1 PC : 4 PP, TEBAL 20 mm


8.3200 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 12,725.44
0.0320 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,380.80

0.4000 Pekerja Rp. 101,000.00 Rp. 40,400.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0220 Mandor Rp. 141,000.00 Rp. 3,102.00
Rp. 72,922.00 Rp. 18,106.24 Rp. 91,028.24
Overhead 10% Rp. 9,102.82
Jumlah Rp. 100,131.06
Dibulatkan Rp. 100,131.00

10 A.4.4.2.16. 1 M2 PEMASANGAN PLESTERAN 1 PC : 5 PP, TEBAL 20 mm


6.9120 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 10,571.90
0.0350 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,885.25

0.4000 Pekerja Rp. 101,000.00 Rp. 40,400.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0220 Mandor Rp. 141,000.00 Rp. 3,102.00
Rp. 72,922.00 Rp. 16,457.15 Rp. 89,379.15
Overhead 10% Rp. 8,937.92
Jumlah Rp. 98,317.07
Dibulatkan Rp. 98,317.00

11 A.4.4.2.17. 1 M2 PEMASANGAN PLESTERAN 1 PC : 6 PP, TEBAL 20 mm


5.8880 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,005.70
0.0360 M3 Pasir Pasang Rp. 168,150.00 Rp. 6,053.40

0.4000 Pekerja Rp. 101,000.00 Rp. 40,400.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0220 Mandor Rp. 141,000.00 Rp. 3,102.00
Rp. 72,922.00 Rp. 15,059.10 Rp. 87,981.10
Overhead 10% Rp. 8,798.11
Jumlah Rp. 96,779.21
Dibulatkan Rp. 96,779.00

12 A.4.4.2.19. 1 M2 PEMASANGAN BERAPEN 1 PC : 5 PP, TEBAL 15 mm


5.1840 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 7,928.93
0.0260 M3 Pasir Pasang Rp. 168,150.00 Rp. 4,371.90

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0750 Tukang Batu Rp. 131,000.00 Rp. 9,825.00
0.0080 Kepala Tukang Rp. 161,000.00 Rp. 1,288.00
0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 27,391.00 Rp. 12,300.83 Rp. 39,691.83
Overhead 10% Rp. 3,969.18
Jumlah Rp. 43,661.01
Dibulatkan Rp. 43,661.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 20 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
13 A.4.4.2.20. 1 M PEMASANGAN PLESTERAN SKONING 1 PC : 3 PP, LEBAR 10 mm
0.5000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 764.75
0.0130 M3 Pasir Pasang Rp. 168,150.00 Rp. 2,185.95

0.0800 Pekerja Rp. 101,000.00 Rp. 8,080.00


0.4000 Tukang Batu Rp. 131,000.00 Rp. 52,400.00
0.0400 Kepala Tukang Rp. 161,000.00 Rp. 6,440.00
0.0040 Mandor Rp. 141,000.00 Rp. 564.00
Rp. 67,484.00 Rp. 2,950.70 Rp. 70,434.70
Overhead 10% Rp. 7,043.47
Jumlah Rp. 77,478.17
Dibulatkan Rp. 77,478.00

14 A.4.4.2.23. 1 M2 PEMASANGAN PLESTERAN CIPRAT 1 PC : 2 PP


4.3200 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 6,607.44
0.0060 M3 Pasir Pasang Rp. 168,150.00 Rp. 1,008.90

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 47,125.00 Rp. 7,616.34 Rp. 54,741.34
Overhead 10% Rp. 5,474.13
Jumlah Rp. 60,215.47
Dibulatkan Rp. 60,215.00

15 A.4.4.2.24 1 M2 PEMASANGAN FINISHING SIAR PASANGAN BATA MERAH


3.1080 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 4,753.69

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0750 Tukang Batu Rp. 131,000.00 Rp. 9,825.00
0.0080 Kepala Tukang Rp. 161,000.00 Rp. 1,288.00
0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 27,391.00 Rp. 4,753.69 Rp. 32,144.69
Overhead 10% Rp. 3,214.47
Jumlah Rp. 35,359.15
Dibulatkan Rp. 35,359.00

16 A.4.4.2.25 1 M2 PEMASANGAN FINISHING SIAR PASANGAN CONBLOCK EKSPOSE


1.6000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 2,447.20

0.0700 Pekerja Rp. 101,000.00 Rp. 7,070.00


0.0350 Tukang Batu Rp. 131,000.00 Rp. 4,585.00
0.0040 Kepala Tukang Rp. 161,000.00 Rp. 644.00
0.0040 Mandor Rp. 141,000.00 Rp. 564.00
Rp. 12,863.00 Rp. 2,447.20 Rp. 15,310.20
Overhead 10% Rp. 1,531.02
Jumlah Rp. 16,841.22
Dibulatkan Rp. 16,841.00

17 A.4.4.2.26. 1 M2 PEMASANGAN FINISHING SIAR PASANGAN BATU KALI ADUKAN 1 PC : 2 PP


6.3400 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,697.03
0.0120 M3 Pasir Pasang Rp. 168,150.00 Rp. 2,017.80

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.1500 Tukang Batu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 54,480.00 Rp. 11,714.83 Rp. 66,194.83
Overhead 10% Rp. 6,619.48
Jumlah Rp. 72,814.31
Dibulatkan Rp. 72,814.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 21 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
18 A.4.4.2.27. 1 M2 PEMASANGAN ACIAN
3.2500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 4,970.88

0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00


0.1000 Tukang Batu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00
Rp. 36,320.00 Rp. 4,970.88 Rp. 41,290.88
Overhead 10% Rp. 4,129.09
Jumlah Rp. 45,419.96
Dibulatkan Rp. 45,419.00

VI PEKERJAAN KAYU

1 A.4.6.1.1. 1 M3 PEMBUATAN DAN PEMASANGAN KUSEN PINTU DAN JENDELA, KAYU KLAS I
1.1000 M3 Balok Kayu Klas I Rp. 3,341,031.25 Rp. 3,675,134.38
1.2500 Kg Paku 10 cm Rp. 15,675.00 Rp. 19,593.75
1.0000 Kg Lem Kayu Rp. 15,152.50 Rp. 15,152.50

7.0000 Pekerja Rp. 101,000.00 Rp. 707,000.00


21.0000 Tukang Kayu Rp. 131,000.00 Rp. 2,751,000.00
2.1000 Kepala Tukang Rp. 161,000.00 Rp. 338,100.00
0.3500 Mandor Rp. 141,000.00 Rp. 49,350.00
Rp. 3,845,450.00 Rp. 3,709,880.63 Rp. 7,555,330.63
Overhead 10% Rp. 755,533.06
Jumlah Rp. 8,310,863.69
Dibulatkan Rp. 8,310,863.00

2 A.4.6.1.2 1 M3 PEMBUATAN DAN PEMASANGAN KUSEN PINTU DAN JENDELA, KAYU KLAS II
1.2000 M3 Balok Kayu Klas II Rp. 2,953,550.00 Rp. 3,544,260.00
1.2500 Kg Paku 10 cm Rp. 15,675.00 Rp. 19,593.75
1.0000 Kg Lem Kayu Rp. 15,152.50 Rp. 15,152.50

6.0000 Pekerja Rp. 101,000.00 Rp. 606,000.00


18.0000 Tukang Kayu Rp. 131,000.00 Rp. 2,358,000.00
1.8000 Kepala Tukang Rp. 161,000.00 Rp. 289,800.00
0.3000 Mandor Rp. 141,000.00 Rp. 42,300.00
Rp. 3,296,100.00 Rp. 3,579,006.25 Rp. 6,875,106.25
Overhead 10% Rp. 687,510.63
Jumlah Rp. 7,562,616.88
Dibulatkan Rp. 7,562,616.00

3 A.4.6.1.3. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU KLAMP STANDAR, KAYU KLAS II


0.0400 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 123,576.00
0.0500 Kg Paku 5 - 7 cm Rp. 15,675.00 Rp. 783.75

0.3500 Pekerja Rp. 101,000.00 Rp. 35,350.00


1.0500 Tukang Kayu Rp. 131,000.00 Rp. 137,550.00
0.1050 Kepala Tukang Rp. 161,000.00 Rp. 16,905.00
0.0180 Mandor Rp. 141,000.00 Rp. 2,538.00
Rp. 192,343.00 Rp. 124,359.75 Rp. 316,702.75
Overhead 10% Rp. 31,670.28
Jumlah Rp. 348,373.03
Dibulatkan Rp. 348,373.00

4 A.4.6.1.4. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU KLAMP SEDERHANA, KAYU KLAS III
0.0400 M3 Papan Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40
0.0500 Kg Paku 5 - 7 cm Rp. 15,675.00 Rp. 783.75

0.3500 Pekerja Rp. 101,000.00 Rp. 35,350.00


1.0500 Tukang Kayu Rp. 131,000.00 Rp. 137,550.00
0.1050 Kepala Tukang Rp. 161,000.00 Rp. 16,905.00
0.0180 Mandor Rp. 141,000.00 Rp. 2,538.00
Rp. 192,343.00 Rp. 116,011.15 Rp. 308,354.15
Overhead 10% Rp. 30,835.42
Jumlah Rp. 339,189.57
Dibulatkan Rp. 339,189.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 22 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
5 A.4.6.1.5. 1 M2 PEMBUATAN DAN PEMASANGAN DAUN PINTU PANEL KAYU KLAS I
0.0400 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 143,915.50
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


3.0000 Tukang Kayu Rp. 131,000.00 Rp. 393,000.00
0.3000 Kepala Tukang Rp. 161,000.00 Rp. 48,300.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 549,350.00 Rp. 151,491.75 Rp. 700,841.75
Overhead 10% Rp. 70,084.18
Jumlah Rp. 770,925.93
Dibulatkan Rp. 770,925.00

6 A.4.6.1.5. 1 M2 PEMBUATAN DAN PEMASANGAN DAUN PINTU PANEL KAYU KLAS II


0.0400 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 123,576.00
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


3.0000 Tukang Kayu Rp. 131,000.00 Rp. 393,000.00
0.3000 Kepala Tukang Rp. 161,000.00 Rp. 48,300.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 549,350.00 Rp. 131,152.25 Rp. 680,502.25
Overhead 10% Rp. 68,050.23
Jumlah Rp. 748,552.48
Dibulatkan Rp. 748,552.00

7 A.4.6.1.6. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA KACA, KAYU KLAS I
0.0240 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 86,349.30
0.3000 Kg Lem Kayu Rp. 15,152.50 Rp. 4,545.75

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


2.4000 Tukang Kayu Rp. 131,000.00 Rp. 314,400.00
0.2400 Kepala Tukang Rp. 161,000.00 Rp. 38,640.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 439,480.00 Rp. 90,895.05 Rp. 530,375.05
Overhead 10% Rp. 53,037.51
Jumlah Rp. 583,412.56
Dibulatkan Rp. 583,412.00

8 A.4.6.1.6. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA KACA, KAYU KLAS II
0.0240 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 74,145.60
0.3000 Kg Lem Kayu Rp. 15,152.50 Rp. 4,545.75

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


2.4000 Tukang Kayu Rp. 131,000.00 Rp. 314,400.00
0.2400 Kepala Tukang Rp. 161,000.00 Rp. 38,640.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 439,480.00 Rp. 78,691.35 Rp. 518,171.35
Overhead 10% Rp. 51,817.14
Jumlah Rp. 569,988.49
Dibulatkan Rp. 569,988.00

9 A.4.6.1.7. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA JALUSI KAYU KLAS I
0.0640 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 230,264.80
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


3.0000 Tukang Kayu Rp. 131,000.00 Rp. 393,000.00
0.3000 Kepala Tukang Rp. 161,000.00 Rp. 48,300.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 549,350.00 Rp. 237,841.05 Rp. 787,191.05
Overhead 10% Rp. 78,719.11
Jumlah Rp. 865,910.16
Dibulatkan Rp. 865,910.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 23 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
10 A.4.6.1.7. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA JALUSI KAYU KLAS II
0.0640 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 197,721.60
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


3.0000 Tukang Kayu Rp. 131,000.00 Rp. 393,000.00
0.3000 Kepala Tukang Rp. 161,000.00 Rp. 48,300.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 549,350.00 Rp. 205,297.85 Rp. 754,647.85
Overhead 10% Rp. 75,464.79
Jumlah Rp. 830,112.64
Dibulatkan Rp. 830,112.00

11 A.4.6.1.8. 1 M2 PEMBUATAN DAUN PINTU KAYU LAPIS (PLYWOOD) RANGKAP,


RANGKA TERTUTUP KAYU KLAS II (LEBAR SAMPAI 90 CM)
0.0250 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 77,235.00
0.0300 Kg Paku 1 cm - 2,5 cm Rp. 15,675.00 Rp. 470.25
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25
1.0000 Lbr Plywood tebal 4 mm Ukuran (90x220) cm Rp. 78,850.00 Rp. 78,850.00

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


2.1000 Tukang Kayu Rp. 131,000.00 Rp. 275,100.00
0.2100 Kepala Tukang Rp. 161,000.00 Rp. 33,810.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 384,545.00 Rp. 164,131.50 Rp. 548,676.50
Overhead 10% Rp. 54,867.65
Jumlah Rp. 603,544.15
Dibulatkan Rp. 603,544.00

12 A.4.6.1.9. 1 M2 PEMBUATAN PINTU PLYWOOD RANGKAP,


RANGKA EXPOSE KAYU KLAS I
0.0256 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 92,105.92
0.0300 Kg Paku 1 cm - 2,5 cm Rp. 15,675.00 Rp. 470.25
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25
1.0000 Lbr Plywood tebal 4 mm Ukuran (90x220) cm Rp. 78,850.00 Rp. 78,850.00

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


2.4000 Tukang Kayu Rp. 131,000.00 Rp. 314,400.00
0.2400 Kepala Tukang Rp. 161,000.00 Rp. 38,640.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 439,480.00 Rp. 179,002.42 Rp. 618,482.42
Overhead 10% Rp. 61,848.24
Jumlah Rp. 680,330.66
Dibulatkan Rp. 680,330.00

13 A.4.6.1.9. 1 M2 PEMBUATAN PINTU PLYWOOD RANGKAP,


RANGKA EXPOSE KAYU KLAS II
0.0256 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 79,088.64
0.0300 Kg Paku 1 cm - 2,5 cm Rp. 15,675.00 Rp. 470.25
0.5000 Kg Lem Kayu Rp. 15,152.50 Rp. 7,576.25
1.0000 Lbr Plywood tebal 4 mm Ukuran (90x220) cm Rp. 78,850.00 Rp. 78,850.00

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


2.4000 Tukang Kayu Rp. 131,000.00 Rp. 314,400.00
0.2400 Kepala Tukang Rp. 161,000.00 Rp. 38,640.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 439,480.00 Rp. 165,985.14 Rp. 605,465.14
Overhead 10% Rp. 60,546.51
Jumlah Rp. 666,011.65
Dibulatkan Rp. 666,011.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 24 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
14 A.4.6.1.10. 1 M2 PEMASANGAN JALUSI KUSEN, KAYU KLAS I
0.0600 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 215,873.25
0.1500 Kg Paku Biasa 1/2" - 1" Rp. 15,675.00 Rp. 2,351.25

0.6700 Pekerja Rp. 101,000.00 Rp. 67,670.00


2.0000 Tukang Kayu Rp. 131,000.00 Rp. 262,000.00
0.2000 Kepala Tukang Rp. 161,000.00 Rp. 32,200.00
0.3350 Mandor Rp. 141,000.00 Rp. 47,235.00
Rp. 409,105.00 Rp. 218,224.50 Rp. 627,329.50
Overhead 10% Rp. 62,732.95
Jumlah Rp. 690,062.45
Dibulatkan Rp. 690,062.00

15 A.4.6.1.10. 1 M2 PEMASANGAN JALUSI KUSEN, KAYU KLAS II


0.0600 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 185,364.00
0.1500 Kg Paku Biasa 1/2" - 1" Rp. 15,675.00 Rp. 2,351.25

0.6700 Pekerja Rp. 101,000.00 Rp. 67,670.00


2.0000 Tukang Kayu Rp. 131,000.00 Rp. 262,000.00
0.2000 Kepala Tukang Rp. 161,000.00 Rp. 32,200.00
0.3350 Mandor Rp. 141,000.00 Rp. 47,235.00
Rp. 409,105.00 Rp. 187,715.25 Rp. 596,820.25
Overhead 10% Rp. 59,682.03
Jumlah Rp. 656,502.28
Dibulatkan Rp. 656,502.00

16 A.4.6.1.11. 1 M2 PEMASANGAN TEAKWOOD RANGKAP, RANGKA EXPOSE KAYU KLAS I


0.0250 M3 Papan Kayu Klas I Rp. 3,597,887.50 Rp. 89,947.19
0.0300 Kg Paku 1 cm - 2,5 cm Rp. 15,675.00 Rp. 470.25
0.3000 Kg Lem Kayu Rp. 15,152.50 Rp. 4,545.75
1.0000 Lbr Teakwood tebal 4 mm Ukuran (90x220) cm Rp. 206,340.00 Rp. 206,340.00

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


2.4000 Tukang Kayu Rp. 131,000.00 Rp. 314,400.00
0.2400 Kepala Tukang Rp. 161,000.00 Rp. 38,640.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 439,480.00 Rp. 301,303.19 Rp. 740,783.19
Overhead 10% Rp. 74,078.32
Jumlah Rp. 814,861.51
Dibulatkan Rp. 814,861.00

17 A.4.6.1.12. 1 M2 PEMASANGAN TEAKWOOD RANGKAP LAPIS FORMIKA, RANGKA EXPOSE KAYU KLAS II
0.0250 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 77,235.00
0.0300 Kg Paku 1 cm - 2,5 cm Rp. 15,675.00 Rp. 470.25
0.8000 Kg Lem Kayu Rp. 15,152.50 Rp. 12,122.00
1.0000 Lbr Teakwood tebal 4 mm Ukuran (90x220) cm Rp. 206,340.00 Rp. 206,340.00
0.5000 Lbr Formika Rp. 109,725.00 Rp. 54,862.50

0.8500 Pekerja Rp. 101,000.00 Rp. 85,850.00


2.5500 Tukang Kayu Rp. 131,000.00 Rp. 334,050.00
0.2550 Kepala Tukang Rp. 161,000.00 Rp. 41,055.00
0.0430 Mandor Rp. 141,000.00 Rp. 6,063.00
Rp. 467,018.00 Rp. 351,029.75 Rp. 818,047.75
Overhead 10% Rp. 81,804.78
Jumlah Rp. 899,852.53
Dibulatkan Rp. 899,852.00

18 A.4.6.1.13. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KLAS I BENTANG 6 METER


1.1000 M3 Balok Kayu Klas I Rp. 3,341,031.25 Rp. 3,675,134.38
15.0000 Kg Besi Strip tebal 5 mm Rp. 14,915.00 Rp. 223,725.00
5.6000 Kg Paku 12 cm Rp. 15,675.00 Rp. 87,780.00

4.0000 Pekerja Rp. 101,000.00 Rp. 404,000.00


12.0000 Tukang Kayu Rp. 131,000.00 Rp. 1,572,000.00
1.2000 Kepala Tukang Rp. 161,000.00 Rp. 193,200.00
0.2000 Mandor Rp. 141,000.00 Rp. 28,200.00
Rp. 2,197,400.00 Rp. 3,986,639.38 Rp. 6,184,039.38
Overhead 10% Rp. 618,403.94
Jumlah Rp. 6,802,443.31
Dibulatkan Rp. 6,802,443.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 25 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
19 A.4.6.1.13. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KLAS II BENTANG 6 METER
1.1000 M3 Balok Kayu Klas II Rp. 2,953,550.00 Rp. 3,248,905.00
15.0000 Kg Besi Strip tebal 5 mm Rp. 14,915.00 Rp. 223,725.00
5.6000 Kg Paku 12 cm Rp. 15,675.00 Rp. 87,780.00

4.0000 Pekerja Rp. 101,000.00 Rp. 404,000.00


12.0000 Tukang Kayu Rp. 131,000.00 Rp. 1,572,000.00
1.2000 Kepala Tukang Rp. 161,000.00 Rp. 193,200.00
0.2000 Mandor Rp. 141,000.00 Rp. 28,200.00
Rp. 2,197,400.00 Rp. 3,560,410.00 Rp. 5,757,810.00
Overhead 10% Rp. 575,781.00
Jumlah Rp. 6,333,591.00
Dibulatkan Rp. 6,333,591.00

20 A.4.6.1.14. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KLAS I


1.2000 M3 Balok Kayu Klas I Rp. 3,341,031.25 Rp. 4,009,237.50
15.0000 Kg Besi Strip tebal 5 mm Rp. 14,915.00 Rp. 223,725.00
5.6000 Kg Paku 12 cm Rp. 15,675.00 Rp. 87,780.00

6.7000 Pekerja Rp. 101,000.00 Rp. 676,700.00


20.1000 Tukang Kayu Rp. 131,000.00 Rp. 2,633,100.00
2.0100 Kepala Tukang Rp. 161,000.00 Rp. 323,610.00
0.3350 Mandor Rp. 141,000.00 Rp. 47,235.00
Rp. 3,680,645.00 Rp. 4,320,742.50 Rp. 8,001,387.50
Overhead 10% Rp. 800,138.75
Jumlah Rp. 8,801,526.25
Dibulatkan Rp. 8,801,526.00

21 A.4.6.1.14. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KLAS II


1.2000 M3 Balok Kayu Klas II Rp. 2,953,550.00 Rp. 3,544,260.00
15.0000 Kg Besi Strip tebal 5 mm Rp. 14,915.00 Rp. 223,725.00
5.6000 Kg Paku 12 cm Rp. 15,675.00 Rp. 87,780.00

6.7000 Pekerja Rp. 101,000.00 Rp. 676,700.00


20.1000 Tukang Kayu Rp. 131,000.00 Rp. 2,633,100.00
2.0100 Kepala Tukang Rp. 161,000.00 Rp. 323,610.00
0.3350 Mandor Rp. 141,000.00 Rp. 47,235.00
Rp. 3,680,645.00 Rp. 3,855,765.00 Rp. 7,536,410.00
Overhead 10% Rp. 753,641.00
Jumlah Rp. 8,290,051.00
Dibulatkan Rp. 8,290,051.00

22 A.4.6.1.15. 1 M3 PEMASANGAN KONSTRUKSI GORDENG, KAYU KLAS II


1.1000 M3 Balok Kayu Klas II Rp. 2,953,550.00 Rp. 3,248,905.00
15.0000 Kg Besi Strip tebal 5 mm Rp. 14,915.00 Rp. 223,725.00
3.0000 Kg Paku 12 cm Rp. 15,675.00 Rp. 47,025.00

6.7000 Pekerja Rp. 101,000.00 Rp. 676,700.00


20.1000 Tukang Kayu Rp. 131,000.00 Rp. 2,633,100.00
2.0100 Kepala Tukang Rp. 161,000.00 Rp. 323,610.00
0.3350 Mandor Rp. 141,000.00 Rp. 47,235.00
Rp. 3,680,645.00 Rp. 3,519,655.00 Rp. 7,200,300.00
Overhead 10% Rp. 720,030.00
Jumlah Rp. 7,920,330.00
Dibulatkan Rp. 7,920,330.00

23 A.4.6.1.16. 1 M2 PEMASANGAN RANGKA ATAP GENTENG KERAMIK, KAYU KLAS II


0.0140 M3 Kaso-Kaso (5x7) cm Rp. 2,953,550.00 Rp. 41,349.70
0.0360 M3 Reng (2x3) cm Rp. 2,953,550.00 Rp. 106,327.80
0.2500 Kg Paku 5 cm dan 10 cm Rp. 15,675.00 Rp. 3,918.75

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 25,515.00 Rp. 151,596.25 Rp. 177,111.25
Overhead 10% Rp. 17,711.13
Jumlah Rp. 194,822.38
Dibulatkan Rp. 194,822.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 26 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
24 A.4.6.1.17. 1 M2 PEMASANGAN RANGKA ATAP GENTENG BETON, KAYU KLAS II
0.0140 M3 Kaso-Kaso (5x7) cm Rp. 2,953,550.00 Rp. 41,349.70
0.0570 M3 Reng (3x4) cm Rp. 2,953,550.00 Rp. 168,352.35
0.2500 Kg Paku 5 cm dan 10 cm Rp. 15,675.00 Rp. 3,918.75

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 25,515.00 Rp. 213,620.80 Rp. 239,135.80
Overhead 10% Rp. 23,913.58
Jumlah Rp. 263,049.38
Dibulatkan Rp. 263,049.00

25 A.4.6.1.18. 1 M2 PEMASANGAN RANGKA ATAP SIRAP, KAYU KLAS II


0.0140 M3 Kayu Klas II Rp. 2,953,550.00 Rp. 41,349.70
0.0570 Kg Paku 5 cm - 10 cm Rp. 15,675.00 Rp. 893.48

0.1200 Pekerja Rp. 101,000.00 Rp. 12,120.00


0.1200 Tukang Kayu Rp. 131,000.00 Rp. 15,720.00
0.0120 Kepala Tukang Rp. 161,000.00 Rp. 1,932.00
0.0060 Mandor Rp. 141,000.00 Rp. 846.00
Rp. 30,618.00 Rp. 42,243.18 Rp. 72,861.18
Overhead 10% Rp. 7,286.12
Jumlah Rp. 80,147.29
Dibulatkan Rp. 80,147.00

26 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (60X120) CM, KAYU KLAS II


0.0131 M3 Kaso-Kaso (5x7) cm Rp. 2,953,550.00 Rp. 38,691.51
0.1750 Kg Paku 7 cm - 10 cm Rp. 15,675.00 Rp. 2,743.13

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.3000 Tukang Kayu Rp. 131,000.00 Rp. 39,300.00
0.0300 Kepala Tukang Rp. 161,000.00 Rp. 4,830.00
0.0750 Mandor Rp. 141,000.00 Rp. 10,575.00
Rp. 69,855.00 Rp. 41,434.63 Rp. 111,289.63
Overhead 10% Rp. 11,128.96
Jumlah Rp. 122,418.59
Dibulatkan Rp. 122,418.00

27 A.4.6.1.19. 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (50X100) CM, KAYU KLAS II


0.0154 M3 Kaso-Kaso (5x7) cm Rp. 2,953,550.00 Rp. 45,484.67
0.2000 Kg Paku 7 cm - 10 cm Rp. 15,675.00 Rp. 3,135.00

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.3000 Tukang Kayu Rp. 131,000.00 Rp. 39,300.00
0.0300 Kepala Tukang Rp. 161,000.00 Rp. 4,830.00
0.0750 Mandor Rp. 141,000.00 Rp. 10,575.00
Rp. 69,855.00 Rp. 48,619.67 Rp. 118,474.67
Overhead 10% Rp. 11,847.47
Jumlah Rp. 130,322.14
Dibulatkan Rp. 130,322.00

28 A.4.6.1.20. 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (60x60) CM, KAYU KLAS II


0.0163 M3 Kaso-Kaso (5x7) cm Rp. 2,953,550.00 Rp. 48,142.87
0.2500 Kg Paku 7 cm - 10 cm Rp. 15,675.00 Rp. 3,918.75

0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00


0.3000 Tukang Kayu Rp. 131,000.00 Rp. 39,300.00
0.0300 Kepala Tukang Rp. 161,000.00 Rp. 4,830.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00
Rp. 65,740.00 Rp. 52,061.62 Rp. 117,801.62
Overhead 10% Rp. 11,780.16
Jumlah Rp. 129,581.78
Dibulatkan Rp. 129,581.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 27 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
29 A.4.6.1.21. 1 M PEMASANGAN LISTPLANK UKURAN (3x20) CM, KAYU KLAS II
0.0108 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 33,365.52
0.1000 Kg Paku 5 cm dan 7 cm Rp. 15,675.00 Rp. 1,567.50

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.2000 Tukang Kayu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 40,225.00 Rp. 34,933.02 Rp. 75,158.02
Overhead 10% Rp. 7,515.80
Jumlah Rp. 82,673.82
Dibulatkan Rp. 82,673.00

30 A.4.6.1.22. 1 M PEMASANGAN LISTPLANK UKURAN (3x30) CM, KAYU KLAS II


0.0110 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 33,983.40
0.0500 Kg Paku 5 cm dan 7 cm Rp. 15,675.00 Rp. 783.75

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.2000 Tukang Kayu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 40,225.00 Rp. 34,767.15 Rp. 74,992.15
Overhead 10% Rp. 7,499.22
Jumlah Rp. 82,491.37
Dibulatkan Rp. 82,491.00

31 A.4.6.1.23. 1 M2 PEMASANGAN RANGKA DINDING PEMISAH (60x120) CM, KAYU KLAS II


0.0280 M3 Balok Kayu Klas II Rp. 2,953,550.00 Rp. 82,699.40
0.1500 Kg Paku 5 cm dan 7 cm Rp. 15,675.00 Rp. 2,351.25

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.4500 Tukang Kayu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 82,473.00 Rp. 85,050.65 Rp. 167,523.65
Overhead 10% Rp. 16,752.37
Jumlah Rp. 184,276.02
Dibulatkan Rp. 184,276.00

32 1 M2 PEMASANGAN DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KLAS II


0.0280 M3 Balok Kayu Ukuran (6x12) cm Rp. 2,953,550.00 Rp. 82,699.40
0.1500 Kg Paku 5 cm dan 10 cm Rp. 15,675.00 Rp. 2,351.25
0.5600 Kg Lem Kayu Rp. 15,152.50 Rp. 8,485.40
0.8600 Lbr Teakwood tebal 4 mm Ukuran (120x240) cm Rp. 206,340.00 Rp. 177,452.40

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.4500 Tukang Kayu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 82,473.00 Rp. 270,988.45 Rp. 353,461.45
Overhead 10% Rp. 35,346.15
Jumlah Rp. 388,807.60
Dibulatkan Rp. 388,807.00

33 A.4.6.1.25. 1 M2 PEMASANGAN DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KLAS II


0.0280 M3 Balok Kayu Ukuran (6x12) cm Rp. 2,953,550.00 Rp. 82,699.40
0.1500 Kg Paku 5 cm dan 10 cm Rp. 15,675.00 Rp. 2,351.25
0.5600 Kg Lem Kayu Rp. 15,152.50 Rp. 8,485.40
0.8600 Lbr Plywood tebal 4 mm Ukuran (120x240) cm Rp. 78,850.00 Rp. 67,811.00

0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00


0.6000 Tukang Kayu Rp. 131,000.00 Rp. 78,600.00
0.0600 Kepala Tukang Rp. 161,000.00 Rp. 9,660.00
0.0100 Mandor Rp. 141,000.00 Rp. 1,410.00
Rp. 109,870.00 Rp. 161,347.05 Rp. 271,217.05
Overhead 10% Rp. 27,121.71
Jumlah Rp. 298,338.76
Dibulatkan Rp. 298,338.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 28 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
34 A.4.6.1.26. 1 M2 PEMASANGAN DINDING LAMBRIZIRING DARI PAPAN KAYU KLAS II
0.0070 M3 Papan Kayu Klas II Rp. 3,089,400.00 Rp. 21,625.80
0.1000 Kg Paku 5 cm dan 10 cm Rp. 15,675.00 Rp. 1,567.50
0.1500 Kg Paku Triplek Rp. 21,850.00 Rp. 3,277.50

0.6000 Pekerja Rp. 101,000.00 Rp. 60,600.00


1.8000 Tukang Kayu Rp. 131,000.00 Rp. 235,800.00
0.1800 Kepala Tukang Rp. 161,000.00 Rp. 28,980.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00
Rp. 329,610.00 Rp. 26,470.80 Rp. 356,080.80
Overhead 10% Rp. 35,608.08
Jumlah Rp. 391,688.88
Dibulatkan Rp. 391,688.00

VII PEKERJAAN BETON

1 A.4.1.1.1 1 M3 MEMBUAT BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (12 + 2) CM, W/C = 0,87
247.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 377,786.50
0.6207 M3 Pasir Beton Rp. 182,400.00 Rp. 113,218.29
0.7400 M3 Kerikil Beton Rp. 210,900.00 Rp. 156,066.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. 667,495.79 Rp. 886,381.79
Overhead 10% Rp. 88,638.18
Jumlah Rp. 975,019.96
Dibulatkan Rp. 975,019.00

2 A.4.1.1.2 1 M3 MEMBUAT BETON MUTU fc' = 9,8 MPa (K 125), SLUMP (12 + 2) CM, W/C = 0,78
276.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 422,142.00
0.5914 M3 Pasir Beton Rp. 182,400.00 Rp. 107,876.57
0.7496 M3 Kerikil Beton Rp. 210,900.00 Rp. 158,096.89
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. 708,540.46 Rp. 927,426.46
Overhead 10% Rp. 92,742.65
Jumlah Rp. 1,020,169.11
Dibulatkan Rp. 1,020,169.00

3 A.4.1.1.3 1 M3 MEMBUAT BETON MUTU fc' = 12,2 MPa (K 150), SLUMP (12 + 2) CM, W/C = 0,72
299.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 457,320.50
0.5707 M3 Pasir Beton Rp. 182,400.00 Rp. 104,098.29
0.7533 M3 Kerikil Beton Rp. 210,900.00 Rp. 158,878.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. 740,721.79 Rp. 959,607.79
Overhead 10% Rp. 95,960.78
Jumlah Rp. 1,055,568.56
Dibulatkan Rp. 1,055,568.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 29 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
4 A.A.4.1.1.4 1 M3 MEMBUAT LANTAI KERJA BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (3-6) CM, W/C = 0,87
230.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 351,785.00
0.6379 M3 Pasir Beton Rp. 182,400.00 Rp. 116,345.14
0.7607 M3 Kerikil Beton Rp. 210,900.00 Rp. 160,440.22
200.0000 Ltr Air Rp. 95.00 Rp. 19,000.00

1.2000 Pekerja Rp. 101,000.00 Rp. 121,200.00


0.2000 Tukang Batu Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0600 Mandor Rp. 141,000.00 Rp. 8,460.00
Rp. 159,080.00 Rp. 647,570.37 Rp. 806,650.37
Overhead 10% Rp. 80,665.04
Jumlah Rp. 887,315.40
Dibulatkan Rp. 887,315.00

5 A. A.4.1.1.5 1 M3 MEMBUAT BETON MUTU fc' = 14,5 MPa (K 175), SLUMP (12 + 2) CM, W/C = 0,66
326.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 498,617.00
0.5429 M3 Pasir Beton Rp. 182,400.00 Rp. 99,017.14
0.7622 M3 Kerikil Beton Rp. 210,900.00 Rp. 160,752.67
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. 778,811.81 Rp. 997,697.81
Overhead 10% Rp. 99,769.78
Jumlah Rp. 1,097,467.59
Dibulatkan Rp. 1,097,467.00

6 A.4.1.1.6 1 M3 MEMBUAT BETON MUTU fc' = 16,9 MPa (K 200), SLUMP (12 + 2) CM, W/C = 0,61
352.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 538,384.00
0.5221 M3 Pasir Beton Rp. 182,400.00 Rp. 95,238.86
0.7637 M3 Kerikil Beton Rp. 210,900.00 Rp. 161,065.11
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. 815,112.97 Rp. 1,033,998.97
Overhead 10% Rp. 103,399.90
Jumlah Rp. 1,137,398.87
Dibulatkan Rp. 1,137,398.00

7 A.4.1.1.7. 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58
371.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 567,444.50
0.4986 M3 Pasir Beton Rp. 182,400.00 Rp. 90,939.43
0.7756 M3 Kerikil Beton Rp. 210,900.00 Rp. 163,564.67
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 913,623.60 Rp. 1,132,509.60
Overhead 10% Rp. 113,250.96
Jumlah Rp. 1,245,760.55
Dibulatkan Rp. 1,245,760.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 30 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
8 A.4.1.1.8. 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56
384.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 587,328.00
0.4943 M3 Pasir Beton Rp. 182,400.00 Rp. 90,157.71
0.7696 M3 Kerikil Beton Rp. 210,900.00 Rp. 162,314.89
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 931,475.60 Rp. 1,150,361.60
Overhead 10% Rp. 115,036.16
Jumlah Rp. 1,265,397.76
Dibulatkan Rp. 1,265,397.00

9 A.4.1.1.9 1 M3 MEMBUAT BETON MUTU fc' = 24,0 MPa (K 275), SLUMP (12 + 2) CM, W/C = 0,53
406.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 620,977.00
0.4886 M3 Pasir Beton Rp. 182,400.00 Rp. 89,115.43
0.7600 M3 Kerikil Beton Rp. 210,900.00 Rp. 160,284.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 962,051.43 Rp. 1,180,937.43
Overhead 10% Rp. 118,093.74
Jumlah Rp. 1,299,031.17
Dibulatkan Rp. 1,299,031.00

10 A.4.1.1.10. 1 M3 MEMBUAT BETON MUTU fc' = 26,4 MPa (K 300), SLUMP (12 + 2) CM, W/C = 0,52
413.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 631,683.50
0.4864 M3 Pasir Beton Rp. 182,400.00 Rp. 88,724.57
0.7563 M3 Kerikil Beton Rp. 210,900.00 Rp. 159,502.89
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 971,585.96 Rp. 1,190,471.96
Overhead 10% Rp. 119,047.20
Jumlah Rp. 1,309,519.16
Dibulatkan Rp. 1,309,519.00

11 A.4.1.1.11. 1 M3 MEMBUAT BETON MUTU fc' = 28,8 MPa (K 325), SLUMP (12 + 2) CM, W/C = 0,49
439.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 671,450.50
0.4786 M3 Pasir Beton Rp. 182,400.00 Rp. 87,291.43
0.7452 M3 Kerikil Beton Rp. 210,900.00 Rp. 157,159.56
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

2.1000 Pekerja Rp. 101,000.00 Rp. 212,100.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.1050 Mandor Rp. 141,000.00 Rp. 14,805.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 278,390.00 Rp. 1,007,576.48 Rp. 1,285,966.48
Overhead 10% Rp. 128,596.65
Jumlah Rp. 1,414,563.13
Dibulatkan Rp. 1,414,563.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 31 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
12 A.4.1.1.12. 1 M3 MEMBUAT BETON MUTU fc' = 31,2 MPa (K 350), SLUMP (12 + 2) CM, W/C = 0,48
448.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 685,216.00
0.4764 M3 Pasir Beton Rp. 182,400.00 Rp. 86,900.57
0.7407 M3 Kerikil Beton Rp. 210,900.00 Rp. 156,222.22
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

2.1000 Pekerja Rp. 101,000.00 Rp. 212,100.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.1050 Mandor Rp. 141,000.00 Rp. 14,805.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 278,390.00 Rp. 1,020,013.79 Rp. 1,298,403.79
Overhead 10% Rp. 129,840.38
Jumlah Rp. 1,428,244.17
Dibulatkan Rp. 1,428,244.00

13 A.4.1.1.7. 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58 ( Stone Cruiser )
371.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 567,444.50
0.4986 M3 Pasir Beton Rp. 182,400.00 Rp. 90,939.43
0.7756 M3 Kerikil Beton Stone Cruiser Rp. 272,650.00 Rp. 211,455.22
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 961,514.15 Rp. 1,180,400.15
Overhead 10% Rp. 118,040.02
Jumlah Rp. 1,298,440.17
Dibulatkan Rp. 1,298,440.00

14 A.4.1.1.8. 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56 ( Stone Cruiser )
384.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 587,328.00
0.4943 M3 Pasir Beton Rp. 182,400.00 Rp. 90,157.71
0.7696 M3 Kerikil Beton Stone Cruiser Rp. 272,650.00 Rp. 209,839.52
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00

0.2500 Hari Sewa Molen Rp. 285,000.00 Rp. 71,250.00


Rp. 218,886.00 Rp. 979,000.23 Rp. 1,197,886.23
Overhead 10% Rp. 119,788.62
Jumlah Rp. 1,317,674.86
Dibulatkan Rp. 1,317,674.00

15 1 M3 MENGGUNAKAN READY MIXED K-225


1.0200 M3 Campuran Beton Ready Mixed K-225 Rp. 1,198,900.00 Rp. 1,222,878.00

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


0.2500 Tukang Batu Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.1000 Mandor Rp. 141,000.00 Rp. 14,100.00
Rp. 151,875.00 Rp. 1,222,878.00 Rp. 1,374,753.00
Overhead 10% Rp. 137,475.30
Jumlah Rp. 1,512,228.30
Dibulatkan Rp. 1,512,228.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 32 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
16 1 M3 MENGGUNAKAN READY MIXED K-250
1.0200 M3 Campuran Beton Ready Mixed K-250 Rp. 1,243,550.00 Rp. 1,268,421.00

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


0.2500 Tukang Batu Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.1000 Mandor Rp. 141,000.00 Rp. 14,100.00
Rp. 151,875.00 Rp. 1,268,421.00 Rp. 1,420,296.00
Overhead 10% Rp. 142,029.60
Jumlah Rp. 1,562,325.60
Dibulatkan Rp. 1,562,325.00

17 1 M3 MENGGUNAKAN READY MIXED K-300


1.0200 M3 Campuran Beton Ready Mixed K-300 Rp. 1,383,437.50 Rp. 1,411,106.25

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


0.2500 Tukang Batu Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.1000 Mandor Rp. 141,000.00 Rp. 14,100.00
Rp. 151,875.00 Rp. 1,411,106.25 Rp. 1,562,981.25
Overhead 10% Rp. 156,298.13
Jumlah Rp. 1,719,279.38
Dibulatkan Rp. 1,719,279.00

18 MEMASANG GORONG - GORONG PIPA BETON BERTULANG, Ø 60 cm / M1

4.9000 Jam Pekerja Rp. 14,428.57 Rp. 70,700.00


1.4000 Jam Tukang Rp. 18,714.29 Rp. 26,200.00
0.7000 Jam Mandor Rp. 20,142.86 Rp. 14,100.00
1.0000 Bh Gorong - Gorong Ø 60 cm Rp. 353,115.00 Rp. 353,115.00
0.1588 M3 Timbunan Porus Rp. 87,400.00 Rp. 13,875.62
1.1416 M3 Mat. Pilihan Rp. 87,400.00 Rp. 99,772.34

1.4136 Jam Stamper Rp. 21,428.57 30,291.43


1.0000 Ls Alat Bantu Rp. 1,000.00 Rp. 1,000.00
Rp. 466,762.97 Rp. 142,291.43 Rp. 609,054.40
Overhead 10% Rp. 60,905.44
Jumlah Rp. 669,959.84
Dibulatkan Rp. 669,959.00

19 MEMASANG GORONG - GORONG PIPA BETON BERTULANG, Ø 30 cm / M1

1.7500 Jam Pekerja Rp. 14,428.57 Rp. 25,250.00


0.3500 Jam Mandor Rp. 20,142.86 Rp. 7,050.00

1.0000 Bh Gorong - Gorong Ø 30 cm Rp. 196,507.50 Rp. 196,507.50


0.0767 M3 Urugan Porus Rp. 87,400.00 Rp. 6,699.21
0.2920 M3 Mat. Pilihan Rp. 87,400.00 Rp. 25,523.20

0.3518 Jam Stamper Rp. 21,428.57 7,539.44


1.0000 Ls Alat Bantu Rp. 1,000.00 Rp. 1,000.00
Rp. 228,729.91 Rp. 40,839.44 Rp. 269,569.35
Overhead 10% Rp. 26,956.93
Jumlah Rp. 296,526.28
Dibulatkan Rp. 296,526.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 33 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
20 MEMASANG GORONG - GORONG PIPA BETON TANPA TULANGAN, Ø 60 cm / M1

4.9000 Jam Pekerja Rp. 14,428.57 Rp. 70,700.00


1.4000 Jam Tukang Rp. 18,714.29 Rp. 26,200.00
0.7000 Jam Mandor Rp. 20,142.86 Rp. 14,100.00

1.0000 Bh Gorong - Gorong Ø 60 cm Rp. 144,637.50 Rp. 144,637.50


0.1588 M3 Timbunan Porus Rp. 87,400.00 Rp. 13,875.62
1.1416 M3 Mat. Pilihan Rp. 87,400.00 Rp. 99,772.34

1.4136 Jam Stamper Rp. 21,428.57 30,291.43


1.0000 Ls Alat Bantu Rp. 1,000.00 Rp. 1,000.00
Rp. 258,285.47 Rp. 142,291.43 Rp. 400,576.90
Overhead 10% Rp. 40,057.69
Jumlah Rp. 440,634.59
Dibulatkan Rp. 440,634.00

21 MEMASANG GORONG - GORONG PIPA BETON TANPA TULANGAN, Ø 30 cm / M1

1.7500 Jam Pekerja Rp. 14,428.57 Rp. 25,250.00


0.3500 Jam Mandor Rp. 20,142.86 Rp. 7,050.00

1.0000 Bh Gorong - Gorong Ø 30 cm Rp. 75,610.50 Rp. 75,610.50


0.0767 M3 Urugan Porus Rp. 87,400.00 Rp. 6,699.21
0.2920 M3 Mat. Pilihan Rp. 87,400.00 Rp. 25,523.20

0.3518 Jam Stamper Rp. 21,428.57 7,539.44


1.0000 Ls Alat Bantu Rp. 1,000.00 Rp. 1,000.00
Rp. 107,832.91 Rp. 40,839.44 Rp. 148,672.35
Overhead 10% Rp. 14,867.23
Jumlah Rp. 163,539.58
Dibulatkan Rp. 163,539.00

22 A.4.1.1.17 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR


1.0500 Kg Besi Beton (polos/ulir) Rp. 14,915.00 Rp. 15,660.75
0.0150 Kg Kawat Beton Rp. 16,150.00 Rp. 242.25

0.0070 Pekerja Rp. 101,000.00 Rp. 707.00


0.0070 Tukang Besi Rp. 131,000.00 Rp. 917.00
0.0007 Kepala Tukang Rp. 161,000.00 Rp. 112.70
0.0004 Mandor Rp. 141,000.00 Rp. 56.40
Rp. 1,793.10 Rp. 15,903.00 Rp. 17,696.10
Overhead 10% Rp. 1,769.61
Jumlah Rp. 19,465.71
Dibulatkan Rp. 19,465.00

23 A.4.1.1.18 1 Kg PEMASANGAN KABEL PRESSTRESSED POLOS/STRANDS


1.0500 Kg Besi Beton (polos/ulir) Rp. 261,345.00 Rp. 274,412.25
0.0100 Kg Kawat Beton Rp. 16,150.00 Rp. 161.50

0.0050 Pekerja Rp. 101,000.00 Rp. 505.00


0.0050 Tukang Besi Rp. 131,000.00 Rp. 655.00
0.0005 Kepala Tukang Rp. 161,000.00 Rp. 80.50
0.0003 Mandor Rp. 141,000.00 Rp. 42.30
Rp. 1,282.80 Rp. 274,573.75 Rp. 275,856.55
Overhead 10% Rp. 27,585.66
Jumlah Rp. 303,442.21
Dibulatkan Rp. 303,442.00

24 A.4.1.1.19 1 Kg PEMASANGAN JARING KAWAT BAJA/WIRE MESH


1.0200 Kg Jaring Kawat Baja dilas Rp. 15,295.00 Rp. 15,600.90
0.0050 Kg Kawat Beton Rp. 16,150.00 Rp. 80.75

0.0025 Pekerja Rp. 101,000.00 Rp. 252.50


0.0025 Tukang Besi Rp. 131,000.00 Rp. 327.50
0.0025 Kepala Tukang Rp. 161,000.00 Rp. 402.50
0.0001 Mandor Rp. 141,000.00 Rp. 14.10
Rp. 996.60 Rp. 15,681.65 Rp. 16,678.25
Overhead 10% Rp. 1,667.83
Jumlah Rp. 18,346.08
Dibulatkan Rp. 18,346.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 34 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
25 A.4.1.1.20 1 M2 PEMASANGAN BEKISTING UNTUK PONDASI
0.0400 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40
0.3000 Kg Paku 5 cm - 10 cm Rp. 15,675.00 Rp. 4,702.50
0.1000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 1,254.00

0.5200 Pekerja Rp. 101,000.00 Rp. 52,520.00


0.2600 Tukang Kayu Rp. 131,000.00 Rp. 34,060.00
0.0260 Kepala Tukang Rp. 161,000.00 Rp. 4,186.00
0.0260 Mandor Rp. 141,000.00 Rp. 3,666.00
Rp. 94,432.00 Rp. 121,183.90
Untuk 2x Pemakaian Bahan Rp. 94,432.00 Rp. 60,591.95 Rp. 155,023.95
Overhead 10% Rp. 15,502.40
Jumlah Rp. 170,526.35
Dibulatkan Rp. 170,526.00

26 A.4.1.1.21 1 M2 PEMASANGAN BEKISTING UNTUK SLOOF, KOLOM PRAKTIS, BALOK PRAKTIS, PET BETON
0.0450 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 129,630.83
0.3000 Kg Paku 5 cm - 10 cm Rp. 15,675.00 Rp. 4,702.50
0.1000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 1,254.00

0.5200 Pekerja Rp. 101,000.00 Rp. 52,520.00


0.2600 Tukang Kayu Rp. 131,000.00 Rp. 34,060.00
0.0260 Kepala Tukang Rp. 161,000.00 Rp. 4,186.00
0.0260 Mandor Rp. 141,000.00 Rp. 3,666.00
Rp. 94,432.00 Rp. 135,587.33
Untuk 2x Pemakaian Bahan Rp. 94,432.00 Rp. 67,793.66 Rp. 162,225.66
Overhead 10% Rp. 16,222.57
Jumlah Rp. 178,448.23
Dibulatkan Rp. 178,448.00

27 A.4.1.1.22 1 M2 PEMASANGAN BEKISTING UNTUK KOLOM


0.0400 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40
0.4000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 6,270.00
0.2000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 2,508.00
0.0150 m3 Balok Kayu Klas III Rp. 2,456,605.00 Rp. 36,849.08
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00
2.0000 Btg Dolken Kayu Galam dia. 8-10 cm,panjang 4 m Rp. 54,245.00 Rp. 108,490.00

0.6600 Pekerja Rp. 101,000.00 Rp. 66,660.00


0.3300 Tukang Kayu Rp. 131,000.00 Rp. 43,230.00
0.0330 Kepala Tukang Rp. 161,000.00 Rp. 5,313.00
0.0330 Mandor Rp. 141,000.00 Rp. 4,653.00
Rp. 119,856.00 Rp. 314,564.48
Untuk 2x Pemakaian Bahan Rp. 119,856.00 Rp. 157,282.24 Rp. 277,138.24
Overhead 10% Rp. 27,713.82
Jumlah Rp. 304,852.06
Dibulatkan Rp. 304,852.00

28 A.4.1.1.23 1 M2 PEMASANGAN BEKISTING UNTUK BALOK


0.0400 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40
0.4000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 6,270.00
0.2000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 2,508.00
0.0180 m3 Balok Kayu Klas III Rp. 2,456,605.00 Rp. 44,218.89
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00
2.0000 Btg Dolken Kayu Galam dia. 8-10 cm,panjang 4 m Rp. 54,245.00 Rp. 108,490.00

0.6600 Pekerja Rp. 101,000.00 Rp. 66,660.00


0.3300 Tukang Kayu Rp. 131,000.00 Rp. 43,230.00
0.0330 Kepala Tukang Rp. 161,000.00 Rp. 5,313.00
0.0330 Mandor Rp. 141,000.00 Rp. 4,653.00
Rp. 119,856.00 Rp. 321,934.29
Untuk 2x Pemakaian Bahan Rp. 119,856.00 Rp. 160,967.15 Rp. 280,823.15
Overhead 10% Rp. 28,082.31
Jumlah Rp. 308,905.46
Dibulatkan Rp. 308,905.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 35 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
29 A.4.1.1.24 1 M2 PEMASANGAN BEKISTING UNTUK LANTAI
0.0400 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 115,227.40
0.4000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 6,270.00
0.2000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 2,508.00
0.0150 m3 Balok Kayu Klas III Rp. 2,456,605.00 Rp. 36,849.08
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00
6.0000 Btg Dolken Kayu Galam dia. 8-10 cm,panjang 4 m Rp. 54,245.00 Rp. 325,470.00

0.6600 Pekerja Rp. 101,000.00 Rp. 66,660.00


0.3300 Tukang Kayu Rp. 131,000.00 Rp. 43,230.00
0.0330 Kepala Tukang Rp. 161,000.00 Rp. 5,313.00
0.0330 Mandor Rp. 141,000.00 Rp. 4,653.00
Rp. 119,856.00 Rp. 531,544.48
Untuk 2x Pemakaian Bahan Rp. 119,856.00 Rp. 265,772.24 Rp. 385,628.24
Overhead 10% Rp. 38,562.82
Jumlah Rp. 424,191.06
Dibulatkan Rp. 424,191.00

30 1 M2 PEMASANGAN BEKISTING UNTUK LANTAI PLAT DUIKER


0.0100 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 28,806.85
0.4000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 6,270.00
0.2000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 2,508.00
0.0038 m3 Balok Kayu Klas III Rp. 2,456,605.00 Rp. 9,212.27
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00
1.5000 Btg Dolken Kayu Galam dia. 8-10 cm,panjang 4 m Rp. 54,245.00 Rp. 81,367.50

0.6600 Pekerja Rp. 101,000.00 Rp. 66,660.00


0.3300 Tukang Kayu Rp. 131,000.00 Rp. 43,230.00
0.0330 Kepala Tukang Rp. 161,000.00 Rp. 5,313.00
0.0330 Mandor Rp. 141,000.00 Rp. 4,653.00
Rp. 119,856.00 Rp. 173,384.62
Untuk 2x Pemakaian Bahan Rp. 119,856.00 Rp. 86,692.31 Rp. 206,548.31
Overhead 10% Rp. 20,654.83
Jumlah Rp. 227,203.14
Dibulatkan Rp. 227,203.00

32 A.4.1.1.26 1 M2 PEMASANGAN BEKISTING UNTUK TANGGA


0.0300 M3 Kayu Klas III Rp. 2,880,685.00 Rp. 86,420.55
0.4000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 6,270.00
0.1500 Lt Minyak Bekisting Rp. 12,540.00 Rp. 1,881.00
0.0150 m3 Balok Kayu Klas III Rp. 2,456,605.00 Rp. 36,849.08
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00
2.0000 Btg Dolken Kayu Galam dia. 8-10 cm,panjang 4 m Rp. 54,245.00 Rp. 108,490.00

0.6600 Pekerja Rp. 101,000.00 Rp. 66,660.00


0.3300 Tukang Kayu Rp. 131,000.00 Rp. 43,230.00
0.0330 Kepala Tukang Rp. 161,000.00 Rp. 5,313.00
0.0330 Mandor Rp. 141,000.00 Rp. 4,653.00
Rp. 119,856.00 Rp. 285,130.63
Untuk 2x Pemakaian Bahan Rp. 119,856.00 Rp. 142,565.31 Rp. 262,421.31
Overhead 10% Rp. 26,242.13
Jumlah Rp. 288,663.44
Dibulatkan Rp. 288,663.00

33 1 M2 PEMASANGAN BEKISTING COR BETON JALAN


0.3000 Kg Paku 5 cm - 12 cm Rp. 15,675.00 Rp. 4,702.50
0.1000 Lt Minyak Bekisting Rp. 12,540.00 Rp. 1,254.00
0.3500 Lbr Multiplek tebal 9 mm Rp. 129,200.00 Rp. 45,220.00

0.5200 Pekerja Rp. 101,000.00 Rp. 52,520.00


0.2600 Tukang Kayu Rp. 131,000.00 Rp. 34,060.00
0.0260 Mandor Rp. 141,000.00 Rp. 3,666.00
Rp. 90,246.00 Rp. 51,176.50
Untuk 2x Pemakaian Bahan Rp. 90,246.00 Rp. 25,588.25 Rp. 115,834.25
Overhead 10% Rp. 11,583.43
Jumlah Rp. 127,417.68
Dibulatkan Rp. 127,417.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 36 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
VIII PEKERJAAN PENUTUP ATAP

1 A.4.5.2.32. 1 M2 PEMASANGAN ATAP GENTENG METAL


1.3000 Lbr Genteng Metal Rp. 55,100.00 Rp. 71,630.00
0.2000 Kg Paku atap Rp. 29,450.00 Rp. 5,890.00

0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0010 Mandor Rp. 141,000.00 Rp. 141.00
Rp. 35,051.00 Rp. 77,520.00 Rp. 112,571.00
Overhead 10% Rp. 11,257.10
Jumlah Rp. 123,828.10
Dibulatkan Rp. 123,828.00

2 A.4.5.2.37. 1 M' PEMASANGAN NOK GENTENG METAL


1.1000 Bh Nok Genteng Metal Rp. 43,367.50 Rp. 47,704.25
0.0500 Kg Paku atap Rp. 29,450.00 Rp. 1,472.50

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.0060 Mandor Rp. 141,000.00 Rp. 846.00
Rp. 26,096.00 Rp. 49,176.75 Rp. 75,272.75
Overhead 10% Rp. 7,527.28
Jumlah Rp. 82,800.03
Dibulatkan Rp. 82,800.00

4 A.4.5.2.39 1 M2 PEMASANGAN ATAP SENG GELOMBANG WARNA


0.7000 Lbr Seng Gelombang Warna bjls 20 Rp. 69,350.00 Rp. 48,545.00
0.0200 Kg Paku atap Rp. 27,550.00 Rp. 551.00

0.1200 Pekerja Rp. 101,000.00 Rp. 12,120.00


0.0600 Tukang Kayu Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0060 Mandor Rp. 141,000.00 Rp. 846.00
Rp. 21,792.00 Rp. 49,096.00 Rp. 70,888.00
Overhead 10% Rp. 7,088.80
Jumlah Rp. 77,976.80
Dibulatkan Rp. 77,976.00

5 A.4.5.2.40. 1 M' PEMASANGAN ATAP NOK SENG


0.3000 Lbr Seng Plat bjls 20 Rp. 23,275.00 Rp. 6,982.50
0.0400 Kg Paku atap Rp. 27,550.00 Rp. 1,102.00

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0700 Tukang Kayu Rp. 131,000.00 Rp. 9,170.00
0.0070 Kepala Tukang Rp. 161,000.00 Rp. 1,127.00
0.0060 Mandor Rp. 141,000.00 Rp. 846.00
Rp. 26,293.00 Rp. 8,084.50 Rp. 34,377.50
Overhead 10% Rp. 3,437.75
Jumlah Rp. 37,815.25
Dibulatkan Rp. 37,815.00

6 1 M' PASANG TALANG 1/2 LINGKARAN D-10 cm, SENG BJLS 28


0.3000 Lbr Seng Plat bjls 28 Rp. 59,850.00 Rp. 17,955.00
0.1000 Kg Paku Biasa 1/2" - 1" Rp. 15,675.00 Rp. 1,567.50
0.0190 M3 Kayu Klas III Papan Rp. 2,880,685.00 Rp. 54,733.02
0.5000 Kg Besi Strip Rp. 14,915.00 Rp. 7,457.50

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.2500 Tukang Kayu Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.0013 Mandor Rp. 141,000.00 Rp. 176.25
Rp. 52,101.25 Rp. 81,713.02 Rp. 133,814.27
Overhead 10% Rp. 13,381.43
Jumlah Rp. 147,195.69
Dibulatkan Rp. 147,195.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 37 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
IX PEKERJAAN LANGIT-LANGIT (FLAFOND)

1 A.4.5.1.5. 1 M2 PEMASANGAN LANGIT-LANGIT TRIPLEKS UKURAN (120x240) cm, tebal 3 mm


0.3750 Lbr Tripleks tebal 3 mm Rp. 145,350.00 Rp. 54,506.25
0.0300 Kg Paku Triplek Rp. 21,850.00 Rp. 655.50

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 12,415.00 Rp. 55,161.75 Rp. 67,576.75
Overhead 10% Rp. 6,757.68
Jumlah Rp. 74,334.43
Dibulatkan Rp. 74,334.00

3 A.4.5.1.6. 1 M2 PEMASANGAN LANGIT-LANGIT LAMBRIZIRING KAYU, TEBAL 9 MM


0.0150 M3 Kayu Papan kls II Rp. 3,089,400.00 Rp. 46,341.00
0.0100 Kg Paku Triplek Rp. 21,850.00 Rp. 218.50

0.8000 Pekerja Rp. 101,000.00 Rp. 80,800.00


0.8000 Tukang Kayu Rp. 131,000.00 Rp. 104,800.00
0.0800 Kepala Tukang Rp. 161,000.00 Rp. 12,880.00
0.0400 Mandor Rp. 141,000.00 Rp. 5,640.00
Rp. 204,120.00 Rp. 46,559.50 Rp. 250,679.50
Overhead 10% Rp. 25,067.95
Jumlah Rp. 275,747.45
Dibulatkan Rp. 275,747.00

4 A.4.5.1.9. 1 M' PEMASANGAN LIST LANGIT-LANGIT KAYU PROFIL


1.0500 M' List Kayu Profil Rp. 16,245.00 Rp. 17,057.25
0.0100 Kg Paku Rp. 15,675.00 Rp. 156.75

0.0500 Pekerja Rp. 101,000.00 Rp. 5,050.00


0.0500 Tukang Kayu Rp. 131,000.00 Rp. 6,550.00
0.0050 Kepala Tukang Rp. 161,000.00 Rp. 805.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 12,828.00 Rp. 17,214.00 Rp. 30,042.00
Overhead 10% Rp. 3,004.20
Jumlah Rp. 33,046.20
Dibulatkan Rp. 33,046.00

5 1 M2 PEMASANGAN LANGIT-LANGIT GYPSUM BOARD UKURAN (120X240X9) MM, TEBAL 9 mm, RANGKA HOLLOW ZINCALUME
0.3640 Lbr Gypsum Board (120x240x9) mm Rp. 110,200.00 Rp. 40,112.80
5.7500 M' Hollow Zincalume 40x40x400 Rp. 9,262.50 Rp. 53,259.38
0.1100 Kg Paku Sekrup Rp. 47,500.00 Rp. 5,225.00

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.5000 Tukang Kayu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 89,405.00 Rp. 98,597.18 Rp. 188,002.18
Overhead 10% Rp. 18,800.22
Jumlah Rp. 206,802.39
Dibulatkan Rp. 206,802.00

5 A.4.5.1.7. 1 M2 PEMASANGAN LANGIT-LANGIT GYPSUM BOARD UKURAN (120X240X9) MM


0.3640 Lbr Gypsum Board (120x240x9) mm Rp. 110,200.00 Rp. 40,112.80
0.1100 Kg Paku Sekrup Rp. 47,500.00 Rp. 5,225.00

0.1000 Pekerja Rp. 101,000.00 Rp. 10,100.00


0.0500 Tukang Kayu Rp. 131,000.00 Rp. 6,550.00
0.0050 Kepala Tukang Rp. 161,000.00 Rp. 805.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 18,160.00 Rp. 45,337.80 Rp. 63,497.80
Overhead 10% Rp. 6,349.78
Jumlah Rp. 69,847.58
Dibulatkan Rp. 69,847.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 38 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
6 1 M2 PEMASANGAN LIST PLAFOND GYPSUM PROFIL
1.0500 M' List Gypsum Profil Rp. 19,475.00 Rp. 20,448.75
0.1500 Kg Tepung Gypsum Rp. 7,125.00 Rp. 1,068.75

0.0600 Pekerja Rp. 101,000.00 Rp. 6,060.00


0.0600 Tukang Kayu Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 15,309.00 Rp. 21,517.50 Rp. 36,826.50
Overhead 10% Rp. 3,682.65
Jumlah Rp. 40,509.15
Dibulatkan Rp. 40,509.00

7 1 M2 PEMASANGAN LANGIT-LANGIT PLAFOND PVC, RANGKA FURING CHANNEL ZINCALUME


5.0000 M' Plafond PVC tebal 8 mm Rp. 26,125.00 Rp. 130,625.00
3.6000 M' Furing Channel Zincalume Rp. 4,138.20 Rp. 14,897.52
6.0000 bh Screw Rp. 475.00 Rp. 2,850.00
0.1100 Kg Paku Sekrup Rp. 47,500.00 Rp. 5,225.00

0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00


0.5000 Tukang Kayu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0250 Mandor Rp. 141,000.00 Rp. 3,525.00
Rp. 127,575.00 Rp. 153,597.52 Rp. 281,172.52
Overhead 10% Rp. 28,117.25
Jumlah Rp. 309,289.77
Dibulatkan Rp. 309,289.00

X PEKERJAAN SANITASI GEDUNG

1 A.5.1.1 2. PEMASANGAN 1 BUAH CLOSET JONGKOK PORSLEN


1.0000 Unit Closet Jongkok Rp. 153,900.00 Rp. 153,900.00
6.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,177.00
0.0100 M3 Pasir Pasang Rp. 168,150.00 Rp. 1,681.50

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


1.5000 Tukang Batu Rp. 131,000.00 Rp. 196,500.00
0.1500 Kepala Tukang Rp. 161,000.00 Rp. 24,150.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 328,700.00 Rp. 164,758.50 Rp. 493,458.50
Overhead 10% Rp. 49,345.85
Jumlah Rp. 542,804.35
Dibulatkan Rp. 542,804.00

2 A.5.1.1.1. PEMASANGAN 1 BUAH CLOSET DUDUK/MONOBLOK


1.0000 Unit Closet Duduk/Monoblok Rp. 1,714,750.00 Rp. 1,714,750.00
0.0600 Perlengkapan (6% Harga Kloset) Rp. 1,714,750.00 Rp. 102,885.00

3.3000 Pekerja Rp. 101,000.00 Rp. 333,300.00


1.1000 Tukang Batu Rp. 131,000.00 Rp. 144,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.1600 Mandor Rp. 141,000.00 Rp. 22,560.00
Rp. 501,570.00 Rp. 1,817,635.00 Rp. 2,319,205.00
Overhead 10% Rp. 231,920.50
Jumlah Rp. 2,551,125.50
Dibulatkan Rp. 2,551,125.00

3 A.5.1.1 4. PEMASANGAN 1 BUAH URINOIR


1.0000 Unit Urinoir Rp. 3,753,450.00 Rp. 3,753,450.00
0.3000 Perlengkapan (30% Harga Urinoir) Rp. 3,753,450.00 Rp. 1,126,035.00
6.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,177.00
0.0100 M3 Pasir Pasang Rp. 168,150.00 Rp. 1,681.50

1.0000 Pekerja Rp. 101,000.00 Rp. 101,000.00


1.0000 Tukang Batu Rp. 131,000.00 Rp. 131,000.00
0.1000 Kepala Tukang Rp. 161,000.00 Rp. 16,100.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 255,150.00 Rp. 4,890,343.50 Rp. 5,145,493.50
Overhead 10% Rp. 514,549.35
Jumlah Rp. 5,660,042.85
Dibulatkan Rp. 5,660,042.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 39 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
4 A.5.1.1 5. PEMASANGAN 1 BUAH WASTAFEL
1.2000 Unit Wastafel Rp. 828,115.00 Rp. 993,738.00
0.1200 Perlengkapan (12% Harga Urinoir) Rp. 828,115.00 Rp. 99,373.80
6.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 9,177.00
0.0100 M3 Pasir Pasang Rp. 168,150.00 Rp. 1,681.50

1.2000 Pekerja Rp. 101,000.00 Rp. 121,200.00


1.4500 Tukang Batu Rp. 131,000.00 Rp. 189,950.00
0.1500 Kepala Tukang Rp. 161,000.00 Rp. 24,150.00
0.0600 Mandor Rp. 141,000.00 Rp. 8,460.00
Rp. 343,760.00 Rp. 1,103,970.30 Rp. 1,447,730.30
Overhead 10% Rp. 144,773.03
Jumlah Rp. 1,592,503.33
Dibulatkan Rp. 1,592,503.00

5 A.5.1.1 7. PEMASANGAN 1 BUAH BAK AIR FIBREGLASS VOLUME 1 M3


1.0000 Bh Bak Air Fibreglass Rp. 460,940.00 Rp. 460,940.00
0.1200 Perlengkapan (12% Harga Bak) Rp. 460,940.00 Rp. 55,312.80

0.3000 Pekerja Rp. 101,000.00 Rp. 30,300.00


0.4500 Tukang Batu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0150 Mandor Rp. 141,000.00 Rp. 2,115.00
Rp. 98,610.00 Rp. 516,252.80 Rp. 614,862.80
Overhead 10% Rp. 61,486.28
Jumlah Rp. 676,349.08
Dibulatkan Rp. 676,349.00

6 A.5.1.1 15. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 30X30 CM TINGGI 35 CM
40.0000 Bh Batu Bata Rp. 1,045.00 Rp. 41,800.00
44.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 67,298.00
0.0700 M3 Pasir Pasang Rp. 168,150.00 Rp. 11,770.50
0.0700 M3 Kerikil Rp. 210,900.00 Rp. 14,763.00
1.6000 Kg Besi Beton Rp. 14,915.00 Rp. 23,864.00
0.0600 M3 Pasir Beton Rp. 182,400.00 Rp. 10,944.00

2.1600 Pekerja Rp. 101,000.00 Rp. 218,160.00


0.7200 Tukang Batu Rp. 131,000.00 Rp. 94,320.00
0.0720 Kepala Tukang Rp. 161,000.00 Rp. 11,592.00
0.0110 Mandor Rp. 141,000.00 Rp. 1,551.00
Rp. 325,623.00 Rp. 170,439.50 Rp. 496,062.50
Overhead 10% Rp. 49,606.25
Jumlah Rp. 545,668.75
Dibulatkan Rp. 545,668.00

7 A.5.1.1 16. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 45x45 CM TINGGI 50 CM
70.0000 Bh Batu Bata Rp. 1,045.00 Rp. 73,150.00
77.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 117,771.50
0.1300 M3 Pasir Pasang Rp. 168,150.00 Rp. 21,859.50
0.0200 M3 Kerikil Rp. 210,900.00 Rp. 4,218.00
2.6000 Kg Besi Beton Rp. 14,915.00 Rp. 38,779.00
0.0900 M3 Pasir Beton Rp. 182,400.00 Rp. 16,416.00

3.2000 Pekerja Rp. 101,000.00 Rp. 323,200.00


1.1500 Tukang Batu Rp. 131,000.00 Rp. 150,650.00
0.0110 Kepala Tukang Rp. 161,000.00 Rp. 1,771.00
0.0160 Mandor Rp. 141,000.00 Rp. 2,256.00
Rp. 477,877.00 Rp. 272,194.00 Rp. 750,071.00
Overhead 10% Rp. 75,007.10
Jumlah Rp. 825,078.10
Dibulatkan Rp. 825,078.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 40 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
8 A.5.1.1 17. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 60x60 CM TINGGI 65 CM
123.0000 Bh Batu Bata Rp. 1,045.00 Rp. 128,535.00
114.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 174,363.00
0.1840 M3 Pasir Pasang Rp. 168,150.00 Rp. 30,939.60
0.0330 M3 Kerikil Rp. 210,900.00 Rp. 6,959.70
4.8500 Kg Besi Beton Rp. 14,915.00 Rp. 72,337.75
0.1200 M3 Pasir Beton Rp. 182,400.00 Rp. 21,888.00

3.2000 Pekerja Rp. 101,000.00 Rp. 323,200.00


1.1500 Tukang Batu Rp. 131,000.00 Rp. 150,650.00
0.0110 Kepala Tukang Rp. 161,000.00 Rp. 1,771.00
0.0160 Mandor Rp. 141,000.00 Rp. 2,256.00
0.1000 Tukang Gali Rp. 131,000.00 Rp. 13,100.00
Rp. 490,977.00 Rp. 435,023.05 Rp. 926,000.05
Overhead 10% Rp. 92,600.01
Jumlah Rp. 1,018,600.06
Dibulatkan Rp. 1,018,600.00

9 A.5.1.1 18. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1/2"


1.2000 M' Pipa Galvanis Rp. 38,475.00 Rp. 46,170.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 38,475.00 Rp. 13,466.25

0.0540 Pekerja Rp. 101,000.00 Rp. 5,454.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0090 Kepala Tukang Rp. 161,000.00 Rp. 1,449.00
0.0270 Mandor Rp. 141,000.00 Rp. 3,807.00
Rp. 22,500.00 Rp. 59,636.25 Rp. 82,136.25
Overhead 10% Rp. 8,213.63
Jumlah Rp. 90,349.88
Dibulatkan Rp. 90,349.00

10 A.5.1.1 20. PEMASANGAN 1 M' PIPA GALVANIS DIA. 3/4"


1.2000 M' Pipa Galvanis Rp. 47,975.00 Rp. 57,570.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 47,975.00 Rp. 16,791.25

0.0540 Pekerja Rp. 101,000.00 Rp. 5,454.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0090 Kepala Tukang Rp. 161,000.00 Rp. 1,449.00
0.0270 Mandor Rp. 141,000.00 Rp. 3,807.00
Rp. 22,500.00 Rp. 74,361.25 Rp. 96,861.25
Overhead 10% Rp. 9,686.13
Jumlah Rp. 106,547.38
Dibulatkan Rp. 106,547.00

11 A.5.1.1 21. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1"


1.2000 M' Pipa Galvanis Rp. 66,975.00 Rp. 80,370.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 66,975.00 Rp. 23,441.25

0.0540 Pekerja Rp. 101,000.00 Rp. 5,454.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0090 Kepala Tukang Rp. 161,000.00 Rp. 1,449.00
0.0270 Mandor Rp. 141,000.00 Rp. 3,807.00
Rp. 22,500.00 Rp. 103,811.25 Rp. 126,311.25
Overhead 10% Rp. 12,631.13
Jumlah Rp. 138,942.38
Dibulatkan Rp. 138,942.00

12 A.5.1.1 22. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1 1/2"


1.2000 M' Pipa Galvanis Rp. 105,450.00 Rp. 126,540.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 105,450.00 Rp. 36,907.50

0.1080 Pekerja Rp. 101,000.00 Rp. 10,908.00


0.1800 Tukang Batu Rp. 131,000.00 Rp. 23,580.00
0.0180 Kepala Tukang Rp. 161,000.00 Rp. 2,898.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 38,091.00 Rp. 163,447.50 Rp. 201,538.50
Overhead 10% Rp. 20,153.85
Jumlah Rp. 221,692.35
Dibulatkan Rp. 221,692.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 41 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
13 A.5.1.1 23. PEMASANGAN 1 M' PIPA GALVANIS DIA. 3"
1.2000 M' Pipa Galvanis Rp. 228,950.00 Rp. 274,740.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 228,950.00 Rp. 80,132.50

0.1350 Pekerja Rp. 101,000.00 Rp. 13,635.00


0.2250 Tukang Batu Rp. 131,000.00 Rp. 29,475.00
0.0230 Kepala Tukang Rp. 161,000.00 Rp. 3,703.00
0.0070 Mandor Rp. 141,000.00 Rp. 987.00
Rp. 47,800.00 Rp. 354,872.50 Rp. 402,672.50
Overhead 10% Rp. 40,267.25
Jumlah Rp. 442,939.75
Dibulatkan Rp. 442,939.00

14 A.5.1.1 24. PEMASANGAN 1 M' PIPA GALVANIS DIA. 4"


1.2000 M' Pipa Galvanis Rp. 328,700.00 Rp. 394,440.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 328,700.00 Rp. 115,045.00

0.1350 Pekerja Rp. 101,000.00 Rp. 13,635.00


0.2250 Tukang Batu Rp. 131,000.00 Rp. 29,475.00
0.0230 Kepala Tukang Rp. 161,000.00 Rp. 3,703.00
0.0070 Mandor Rp. 141,000.00 Rp. 987.00
Rp. 47,800.00 Rp. 509,485.00 Rp. 557,285.00
Overhead 10% Rp. 55,728.50
Jumlah Rp. 613,013.50
Dibulatkan Rp. 613,013.00

15 A.5.1.1 25. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 1/2"


1.2000 M' Pipa PVC Rp. 6,650.00 Rp. 7,980.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 6,650.00 Rp. 2,327.50

0.0360 Pekerja Rp. 101,000.00 Rp. 3,636.00


0.0600 Tukang Batu Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0020 Mandor Rp. 141,000.00 Rp. 282.00
Rp. 12,744.00 Rp. 10,307.50 Rp. 23,051.50
Overhead 10% Rp. 2,305.15
Jumlah Rp. 25,356.65
Dibulatkan Rp. 25,356.00

16 A.5.1.1 26. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 3/4"


1.2000 M' Pipa PVC Rp. 8,550.00 Rp. 10,260.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 8,550.00 Rp. 2,992.50

0.0360 Pekerja Rp. 101,000.00 Rp. 3,636.00


0.0600 Tukang Batu Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0020 Mandor Rp. 141,000.00 Rp. 282.00
Rp. 12,744.00 Rp. 13,252.50 Rp. 25,996.50
Overhead 10% Rp. 2,599.65
Jumlah Rp. 28,596.15
Dibulatkan Rp. 28,596.00

17 A.5.1.1 27. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 1"


1.2000 M' Pipa PVC Rp. 12,350.00 Rp. 14,820.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 12,350.00 Rp. 4,322.50

0.0360 Pekerja Rp. 101,000.00 Rp. 3,636.00


0.0600 Tukang Batu Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0020 Mandor Rp. 141,000.00 Rp. 282.00
Rp. 12,744.00 Rp. 19,142.50 Rp. 31,886.50
Overhead 10% Rp. 3,188.65
Jumlah Rp. 35,075.15
Dibulatkan Rp. 35,075.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 42 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
18 A.5.1.1 29. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 2"
1.2000 M' Pipa PVC Rp. 24,225.00 Rp. 29,070.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 24,225.00 Rp. 8,478.75

0.0540 Pekerja Rp. 101,000.00 Rp. 5,454.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0090 Kepala Tukang Rp. 161,000.00 Rp. 1,449.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 19,116.00 Rp. 37,548.75 Rp. 56,664.75
Overhead 10% Rp. 5,666.48
Jumlah Rp. 62,331.23
Dibulatkan Rp. 62,331.00

19 A.5.1.1 31. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 3'


1.2000 M' Pipa PVC Rp. 47,975.00 Rp. 57,570.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 47,975.00 Rp. 16,791.25

0.0810 Pekerja Rp. 101,000.00 Rp. 8,181.00


0.1350 Tukang Batu Rp. 131,000.00 Rp. 17,685.00
0.0135 Kepala Tukang Rp. 161,000.00 Rp. 2,173.50
0.0040 Mandor Rp. 141,000.00 Rp. 564.00
Rp. 28,603.50 Rp. 74,361.25 Rp. 102,964.75
Overhead 10% Rp. 10,296.48
Jumlah Rp. 113,261.23
Dibulatkan Rp. 113,261.00

20 A.5.1.1 32. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 4'


1.2000 M' Pipa PVC Rp. 85,975.00 Rp. 103,170.00
0.3500 Perlengkapan (35% Harga Pipa) Rp. 85,975.00 Rp. 30,091.25

0.0810 Pekerja Rp. 101,000.00 Rp. 8,181.00


0.1350 Tukang Batu Rp. 131,000.00 Rp. 17,685.00
0.0135 Kepala Tukang Rp. 161,000.00 Rp. 2,173.50
0.0040 Mandor Rp. 141,000.00 Rp. 564.00
Rp. 28,603.50 Rp. 133,261.25 Rp. 161,864.75
Overhead 10% Rp. 16,186.48
Jumlah Rp. 178,051.23
Dibulatkan Rp. 178,051.00

21 A.5.1.1 19 PEMASANGAN 1 BUAH KRAN DIA. 3/4" ATAU 1/2"


1.0000 Bh Kran Air Rp. 57,950.00 Rp. 57,950.00
0.0250 Bh Seal Tape Rp. 5,225.00 Rp. 130.63

0.0100 Pekerja Rp. 101,000.00 Rp. 1,010.00


0.4000 Tukang Batu Rp. 131,000.00 Rp. 52,400.00
0.0400 Kepala Tukang Rp. 161,000.00 Rp. 6,440.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 60,555.00 Rp. 58,080.63 Rp. 118,635.63
Overhead 10% Rp. 11,863.56
Jumlah Rp. 130,499.19
Dibulatkan Rp. 130,499.00

22 MEMBUAT 1 UNIT SEPTICK TANK KAP. 15 ORG LENGKAP DENGAN RESAPAN (Uk.1.00M x 2.00M x 1.40 M)
4.8000 M3 Galian Tanah Rp. 87,202.00 418,569.60
2.7000 M3 Urugan kembali bekas Galian Rp. 63,305.00 170,923.50
1.1000 M3 Pas. Bata 1 : 2 Rp. 171,213.00 188,334.30
8.5000 M2 Plesteran 1 : 2 tbl 20 cm Rp. 80,828.00 687,038.00
0.1600 M3 Beton mutu K.100 (f'c = 7,4 MPa) Rp. 975,019.00 156,003.04
Beton plat lantai t = 10 cm/ m3
0.3000 M3 Beton Mutu K.225 ( fc = 19,3 Mpa ) Rp. 1,245,760.00 373,728.00
2.6400 M2 Bekisting Plat Rp. 227,203.00 599,815.92
30.6666 Kg Pembesian Rp. 19,465.00 596,925.37

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 43 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
1.0000 M3 Kerikil Saringan Rp. 210,900.00 210,900.00
2.0000 M3 Pasir Saringan Rp. 210,900.00 421,800.00
5.0000 M1 Pipa PVC dia 4" Rp. 85,975.00 429,875.00
1.5000 Bh Pipa GIP 2 " Rp. 138,700.00 208,050.00
2.0000 Bh Knee Rp. 9,025.00 18,050.00
6.0000 M2 Plastik Hitam Rp. 10,450.00 62,700.00
20.0000 Kg Ijuk Rp. 23,000.00 460,000.00

Rp. 5,002,712.73 Rp. Rp. 5,002,712.73


Jumlah Rp. 5,002,712.73
Dibulatkan Rp. 5,002,712.00

XI PEKERJAAN BESI DAN ALUMUNIUM

1 A.4.2.1.1. 1 Kg PEMASANGAN BESI PROFIL


1.1500 Kg Besi Profil Rp. 16,625.00 Rp. 19,118.75

0.0600 Pekerja Rp. 101,000.00 Rp. 6,060.00


0.0600 Tukang Las Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 15,309.00 Rp. 19,118.75 Rp. 34,427.75
Overhead 10% Rp. 3,442.78
Jumlah Rp. 37,870.53
Dibulatkan Rp. 37,870.00

2 A.4.2.1.2 . 1 Kg PEMASANGAN RANGKA KUDA-KUDA BAJA IWF


1.1500 Kg Besi Profil WF Rp. 16,625.00 Rp. 19,118.75

0.0600 Pekerja Rp. 101,000.00 Rp. 6,060.00


0.0600 Tukang Las Rp. 131,000.00 Rp. 7,860.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 15,309.00 Rp. 19,118.75 Rp. 34,427.75
Overhead 10% Rp. 3,442.78
Jumlah Rp. 37,870.53
Dibulatkan Rp. 37,870.00

3 A.4.2.1.3. 1 Kg PENGERJAAN PEKERJAAN PERAKITAN


0.0100 Ltr Solar Rp. 9,927.50 Rp. 99.28
0.0010 Ltr Minyak Pelumas Rp. 36,100.00 Rp. 36.10
0.0080 Jam Sewa Alat Rp. 39,187.50 Rp. 313.50

0.0010 Pekerja Rp. 101,000.00 Rp. 101.00


0.0010 Tukang Besi Konstruksi Rp. 131,000.00 Rp. 131.00
0.0000 Kepala Tukang Rp. 161,000.00 Rp. 1.61
0.0001 Mandor Rp. 141,000.00 Rp. 7.05
Rp. 240.66 Rp. 448.88 Rp. 689.54
Overhead 10% Rp. 68.95
Jumlah Rp. 758.49
Dibulatkan Rp. 758.00

4 A.4.2.1.5. 1 Cm PENGERJAAN PENGELASAN DENGAN LAS LISTRIK


0.0400 Kg Kawat Las Listrik Rp. 33,725.00 Rp. 1,349.00
0.0300 Ltr Solar Rp. 9,927.50 Rp. 297.83
0.0040 Ltr Minyak Pelumas Rp. 36,100.00 Rp. 144.40
0.0170 Jam Sewa Alat Rp. 39,187.50 Rp. 666.19

0.0040 Pekerja Rp. 101,000.00 Rp. 404.00


0.0020 Tukang Besi Konstruksi Rp. 131,000.00 Rp. 262.00
0.0002 Kepala Tukang Rp. 161,000.00 Rp. 32.20
0.0002 Mandor Rp. 141,000.00 Rp. 28.20
Rp. 726.40 Rp. 2,457.41 Rp. 3,183.81
Overhead 10% Rp. 318.38
Jumlah Rp. 3,502.19
Dibulatkan Rp. 3,502.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 44 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
5 A.4.2.1.15. 1 M2 PEMASANGAN TERALI BESI STRIP (2x3) mm
6.1770 Kg Besi Strip Rp. 14,915.00 Rp. 92,129.96
27.0800 Cm Pengelasan Rp. 3,502.00 Rp. 94,834.16

1.6700 Pekerja Rp. 101,000.00 Rp. 168,670.00


1.6700 Tukang Las Rp. 131,000.00 Rp. 218,770.00
0.1670 Kepala Tukang Rp. 161,000.00 Rp. 26,887.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 426,030.00 Rp. 186,964.12 Rp. 612,994.12
Overhead 10% Rp. 61,299.41
Jumlah Rp. 674,293.53
Dibulatkan Rp. 674,293.00

6 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (SILVER)


1.1000 M' Profil Alluminium 4" (Ex. Alexindo) warna Silver Rp. 123,500.00 Rp. 135,850.00
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 158,023.00 Rp. 168,987.40
Overhead 10% Rp. 16,898.74
Jumlah Rp. 185,886.14
Dibulatkan Rp. 185,886.00

7 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (HITAM/COKLAT)


1.1000 M' Profil Alluminium 4" (Ex. Alexindo) warna Hitam/Coklat Rp. 135,850.00 Rp. 149,435.00
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 171,608.00 Rp. 182,572.40
Overhead 10% Rp. 18,257.24
Jumlah Rp. 200,829.64
Dibulatkan Rp. 200,829.00

8 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (COATING POWDER)


1.1000 M' Profil Alluminium 4" (Ex. Alexindo) warna Coating Powder Rp. 176,605.00 Rp. 194,265.50
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 216,438.50 Rp. 227,402.90
Overhead 10% Rp. 22,740.29
Jumlah Rp. 250,143.19
Dibulatkan Rp. 250,143.00

9 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (SILVER)


1.1000 M' Profil Alluminium 3" (Ex. Alexindo) warna Silver Rp. 90,250.00 Rp. 99,275.00
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 121,448.00 Rp. 132,412.40
Overhead 10% Rp. 13,241.24
Jumlah Rp. 145,653.64
Dibulatkan Rp. 145,653.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 45 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
10 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (HITAM/COKLAT)
1.1000 M' Profil Alluminium 3" (Ex. Alexindo) warna Hitam/Coklat Rp. 99,275.00 Rp. 109,202.50
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 131,375.50 Rp. 142,339.90
Overhead 10% Rp. 14,233.99
Jumlah Rp. 156,573.89
Dibulatkan Rp. 156,573.00

11 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (COATING POWDER)


1.1000 M' Profil Alluminium 3" (Ex. Alexindo) warna Coating Powder Rp. 129,057.50 Rp. 141,963.25
2.0000 Bh Skrup Fixer Rp. 9,975.00 Rp. 19,950.00
0.0600 TubeSealant Rp. 37,050.00 Rp. 2,223.00

0.0430 Pekerja Rp. 101,000.00 Rp. 4,343.00


0.0430 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 5,633.00
0.0043 Kepala Tukang Rp. 161,000.00 Rp. 692.30
0.0021 Mandor Rp. 141,000.00 Rp. 296.10
Rp. 10,964.40 Rp. 164,136.25 Rp. 175,100.65
Overhead 10% Rp. 17,510.07
Jumlah Rp. 192,610.72
Dibulatkan Rp. 192,610.00

12 A.4.2.1.20 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1x40x40x2 MM, MODUL 60x120 CM, DINDING PARTISI
3.5000 M' Rangka Metal Hollow 40x40x2 mm Rp. 28,215.00 Rp. 98,752.50
1.0000 Assesories (Perkuatan, Las dll, 100% x Rangka) Rp. 28,215.00 Rp. 28,215.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.2500 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.0130 Mandor Rp. 141,000.00 Rp. 1,833.00
Rp. 63,858.00 Rp. 126,967.50 Rp. 190,825.50
Overhead 10% Rp. 19,082.55
Jumlah Rp. 209,908.05
Dibulatkan Rp. 209,908.00

13 A.4.2.1.21. 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1x40x40x2 MM, MODUL 60x60 CM, FLAFON
4.0000 M' Rangka Metal Hollow 40x40x2 mm Rp. 28,215.00 Rp. 112,860.00
1.0000 Assesories (Perkuatan, Las dll, 100% x Rangka) Rp. 28,215.00 Rp. 28,215.00

0.3500 Pekerja Rp. 101,000.00 Rp. 35,350.00


0.3500 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0180 Mandor Rp. 141,000.00 Rp. 2,538.00
Rp. 89,373.00 Rp. 141,075.00 Rp. 230,448.00
Overhead 10% Rp. 23,044.80
Jumlah Rp. 253,492.80
Dibulatkan Rp. 253,492.00

14 1 M2 PEKERJAAN KUDA-KUDA BAJA RINGAN


2.8000 M' Truss C-75, 0.75 Rp. 21,850.00 Rp. 61,180.00
25.0000 bh Baut (screw driver) Rp. 475.00 Rp. 11,875.00
1.0000 bh Dynabolt Rp. 29,735.00 Rp. 29,735.00
5.1000 M' Reng R.33-0.45 Rp. 11,400.00 Rp. 58,140.00

0.2000 Pekerja Rp. 101,000.00 Rp. 20,200.00


0.4500 Tukang Besi Rp. 131,000.00 Rp. 58,950.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0500 Mandor Rp. 141,000.00 Rp. 7,050.00
Rp. 87,810.00 Rp. 160,930.00 Rp. 248,740.00
Overhead 10% Rp. 24,874.00
Jumlah Rp. 273,614.00
Dibulatkan Rp. 273,614.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 46 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
15 A.4.2.1.8. 1 M2 PEMASANGAN PINTU FOLDING GATE
1.0000 M2 Pintu Folding Gate Rp. 905,350.00 Rp. 905,350.00

0.4400 Pekerja Rp. 101,000.00 Rp. 44,440.00


0.4400 Tukang Besi Rp. 131,000.00 Rp. 57,640.00
0.0440 Kepala Tukang Rp. 161,000.00 Rp. 7,084.00
0.0220 Mandor Rp. 141,000.00 Rp. 3,102.00
Rp. 112,266.00 Rp. 905,350.00 Rp. 1,017,616.00
Overhead 10% Rp. 101,761.60
Jumlah Rp. 1,119,377.60
Dibulatkan Rp. 1,119,377.00

16 A.4.2.1.13. PEMASANGAN 1 M2 PINTU KACA RANGKA ALUMUNIUM


4.4000 M' Rangka Pintu Alumunium Rp. 229,900.00 Rp. 1,011,560.00
0.2700 TubeSealant Rp. 37,050.00 Rp. 10,003.50

0.0850 Pekerja Rp. 101,000.00 Rp. 8,585.00


0.0850 Tukang Besi/Alluminium Rp. 131,000.00 Rp. 11,135.00
0.0090 Kepala Tukang Rp. 161,000.00 Rp. 1,449.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 21,874.00 Rp. 1,021,563.50 Rp. 1,043,437.50
Overhead 10% Rp. 104,343.75
Jumlah Rp. 1,147,781.25
Dibulatkan Rp. 1,147,781.00

XII PEKERJAAN KUNCI DAN KACA

1 A.4.6.2.1. 1 BUAH PEMASANGAN KUNCI TANAM SES ASLI


1.0000 Bh Kunci Tanam SES Rp. 333,450.00 Rp. 333,450.00

0.0600 Pekerja Rp. 101,000.00 Rp. 6,060.00


0.6000 Tukang Kayu Rp. 131,000.00 Rp. 78,600.00
0.0600 Kepala Tukang Rp. 161,000.00 Rp. 9,660.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 94,743.00 Rp. 333,450.00 Rp. 428,193.00
Overhead 10% Rp. 42,819.30
Jumlah Rp. 471,012.30
Dibulatkan Rp. 471,012.00

2 A.4.6.2.2. 1 BUAH PEMASANGAN KUNCI TANAM BIASA


1.0000 Bh Kunci Tanam Biasa Rp. 218,215.00 Rp. 218,215.00

0.0100 Pekerja Rp. 101,000.00 Rp. 1,010.00


0.5000 Tukang Kayu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 75,265.00 Rp. 218,215.00 Rp. 293,480.00
Overhead 10% Rp. 29,348.00
Jumlah Rp. 322,828.00
Dibulatkan Rp. 322,828.00

3 A.4.6.2.5. 1 BUAH PEMASANGAN ENGSEL PINTU


1.0000 Bh Engsel Pintu Rp. 16,625.00 Rp. 16,625.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00080 Mandor Rp. 141,000.00 Rp. 112.80
Rp. 23,692.80 Rp. 16,625.00 Rp. 40,317.80
Overhead 10% Rp. 4,031.78
Jumlah Rp. 44,349.58
Dibulatkan Rp. 44,349.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 47 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
4 A.4.6.2.5. 1 BUAH PEMASANGAN ENGSEL JENDELA
1.0000 Bh Engsel Jendela Rp. 14,725.00 Rp. 14,725.00

0.0100 Pekerja Rp. 101,000.00 Rp. 1,010.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.00050 Mandor Rp. 141,000.00 Rp. 70.50
Rp. 15,790.50 Rp. 14,725.00 Rp. 30,515.50
Overhead 10% Rp. 3,051.55
Jumlah Rp. 33,567.05
Dibulatkan Rp. 33,567.00

5 1 BUAH PEMASANGAN GRENDEL JENDELA


1.0000 Bh Grendel Jendela Rp. 9,975.00 Rp. 9,975.00

0.0100 Pekerja Rp. 101,000.00 Rp. 1,010.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.00050 Mandor Rp. 141,000.00 Rp. 70.50
Rp. 15,790.50 Rp. 9,975.00 Rp. 25,765.50
Overhead 10% Rp. 2,576.55
Jumlah Rp. 28,342.05
Dibulatkan Rp. 28,342.00

6 A.4.6.2.9. PEMASANGAN 1 BH KAIT ANGIN


1.0000 Bh Kait Angin Rp. 11,875.00 Rp. 11,875.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 24,708.00 Rp. 11,875.00 Rp. 36,583.00
Overhead 10% Rp. 3,658.30
Jumlah Rp. 40,241.30
Dibulatkan Rp. 40,241.00

7 1 BH TANGAN - TANGAN JENDELA


1.0000 Bh Tangan - Tangan Jendela Rp. 14,725.00 Rp. 14,725.00

0.0100 Pekerja Rp. 101,000.00 Rp. 1,010.00


0.1000 Tukang Kayu Rp. 131,000.00 Rp. 13,100.00
0.0100 Kepala Tukang Rp. 161,000.00 Rp. 1,610.00
0.0005 Mandor Rp. 141,000.00 Rp. 70.50
Rp. 15,790.50 Rp. 14,725.00 Rp. 30,515.50
Overhead 10% Rp. 3,051.55
Jumlah Rp. 33,567.05
Dibulatkan Rp. 33,567.00

8 A.4.6.2.19. 1 M2 PEMASANGAN KACA, TEBAL 12 mm ( Biru )


1.1000 M2 Kaca Rp. 1,045,950.00 Rp. 1,150,545.00

0.0250 Pekerja Rp. 101,000.00 Rp. 2,525.00


0.2500 Tukang Kayu Rp. 131,000.00 Rp. 32,750.00
0.0250 Kepala Tukang Rp. 161,000.00 Rp. 4,025.00
0.00130 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 39,483.30 Rp. 1,150,545.00 Rp. 1,190,028.30
Overhead 10% Rp. 119,002.83
Jumlah Rp. 1,309,031.13
Dibulatkan Rp. 1,309,031.00

9 A.4.6.2.18.. 1 M2 PEMASANGAN KACA, TEBAL 8 mm


1.1000 M2 Kaca Rp. 304,950.00 Rp. 335,445.00

0.0170 Pekerja Rp. 101,000.00 Rp. 1,717.00


0.1700 Tukang Kayu Rp. 131,000.00 Rp. 22,270.00
0.0170 Kepala Tukang Rp. 161,000.00 Rp. 2,737.00
0.00009 Mandor Rp. 141,000.00 Rp. 12.69
Rp. 26,736.69 Rp. 335,445.00 Rp. 362,181.69
Overhead 10% Rp. 36,218.17
Jumlah Rp. 398,399.86
Dibulatkan Rp. 398,399.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 48 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
10 A.4.6.2.17. 1 M2 PEMASANGAN KACA, TEBAL 5 mm
1.1000 M2 Kaca Rp. 114,950.00 Rp. 126,445.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00080 Mandor Rp. 141,000.00 Rp. 112.80
Rp. 23,692.80 Rp. 126,445.00 Rp. 150,137.80
Overhead 10% Rp. 15,013.78
Jumlah Rp. 165,151.58
Dibulatkan Rp. 165,151.00

11 A.4.6.2.16. 1 M2 PEMASANGAN KACA, TEBAL 3 mm


1.1000 M2 Kaca Rp. 94,050.00 Rp. 103,455.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00075 Mandor Rp. 141,000.00 Rp. 105.75
Rp. 23,685.75 Rp. 103,455.00 Rp. 127,140.75
Overhead 10% Rp. 12,714.08
Jumlah Rp. 139,854.83
Dibulatkan Rp. 139,854.00

12 A.4.6.2.18. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 8 mm


1.1000 M2 Kaca Rayban Rp. 399,950.00 Rp. 439,945.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00075 Mandor Rp. 141,000.00 Rp. 105.75
Rp. 23,685.75 Rp. 439,945.00 Rp. 463,630.75
Overhead 10% Rp. 46,363.08
Jumlah Rp. 509,993.83
Dibulatkan Rp. 509,993.00

13 A.4.6.2.17. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 5 mm


1.1000 M2 Kaca Rayban Rp. 129,200.00 Rp. 142,120.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00075 Mandor Rp. 141,000.00 Rp. 105.75
Rp. 23,685.75 Rp. 142,120.00 Rp. 165,805.75
Overhead 10% Rp. 16,580.58
Jumlah Rp. 182,386.33
Dibulatkan Rp. 182,386.00

14 A.4.6.2.16. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 3 mm


1.1000 M2 Kaca Rayban Rp. 113,050.00 Rp. 124,355.00

0.0150 Pekerja Rp. 101,000.00 Rp. 1,515.00


0.1500 Tukang Kayu Rp. 131,000.00 Rp. 19,650.00
0.0150 Kepala Tukang Rp. 161,000.00 Rp. 2,415.00
0.00075 Mandor Rp. 141,000.00 Rp. 105.75
Rp. 23,685.75 Rp. 124,355.00 Rp. 148,040.75
Overhead 10% Rp. 14,804.08
Jumlah Rp. 162,844.83
Dibulatkan Rp. 162,844.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 49 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
XIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

1 A.4.4.3.34. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (40X40) CM


6.7000 Bh Ubin Keramik Rp. 13,062.50 Rp. 87,518.75
10.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,295.00
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00
Rp. 126,415.00 Rp. 118,218.00 Rp. 244,633.00
Overhead 10% Rp. 24,463.30
Jumlah Rp. 269,096.30
Dibulatkan Rp. 269,096.00

2 A.4.4.3.34. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (40X40) CM


6.7000 Bh Ubin Keramik Rp. 13,972.92 Rp. 93,618.54
10.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,295.00
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0300 Mandor Rp. 141,000.00 Rp. 4,230.00
Rp. 126,415.00 Rp. 124,317.79 Rp. 250,732.79
Overhead 10% Rp. 25,073.28
Jumlah Rp. 275,806.07
Dibulatkan Rp. 275,806.00

3 A.4.4.3.35. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (30X30) CM


11.8700 Bh Ubin Keramik Rp. 7,125.00 Rp. 84,573.75
10.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,295.00
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 115,273.00 Rp. 242,393.00
Overhead 10% Rp. 24,239.30
Jumlah Rp. 266,632.30
Dibulatkan Rp. 266,632.00

4 A.4.4.3.35. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (30X30) CM


11.8700 Bh Ubin Keramik Rp. 7,621.59 Rp. 90,468.28
10.0000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,295.00
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 121,167.53 Rp. 248,287.53
Overhead 10% Rp. 24,828.75
Jumlah Rp. 273,116.29
Dibulatkan Rp. 273,116.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 50 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
5 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (20X20) CM
26.5000 Bh Ubin Keramik Rp. 3,002.00 Rp. 79,553.00
10.4000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,906.80
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 110,864.05 Rp. 237,984.05
Overhead 10% Rp. 23,798.41
Jumlah Rp. 261,782.46
Dibulatkan Rp. 261,782.00

6 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (20X20) CM


26.5000 Bh Ubin Keramik Rp. 3,211.00 Rp. 85,091.50
10.4000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,906.80
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 116,402.55 Rp. 243,522.55
Overhead 10% Rp. 24,352.26
Jumlah Rp. 267,874.81
Dibulatkan Rp. 267,874.00

7 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (20X25) CM


21.0000 Bh Ubin Keramik Rp. 3,847.50 Rp. 80,797.50
10.4000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,906.80
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 112,108.55 Rp. 239,228.55
Overhead 10% Rp. 23,922.86
Jumlah Rp. 263,151.41
Dibulatkan Rp. 263,151.00

8 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (25X25) CM


16.8000 Bh Ubin Keramik Rp. 4,809.38 Rp. 80,797.50
10.4000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 15,906.80
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
0.5000 Kg Semen Warna Rp. 15,675.00 Rp. 7,837.50

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 112,108.55 Rp. 239,228.55
Overhead 10% Rp. 23,922.86
Jumlah Rp. 263,151.41
Dibulatkan Rp. 263,151.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 51 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
9 A.4.4.3.13. 1 M2 PEMASANGAN LANTAI GRANITE UKURAN (60X60) CM
3.1000 Bh Granite Rp. 46,017.05 Rp. 142,652.86
9.6000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,683.20
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
1.5000 Kg Semen Warna Rp. 15,675.00 Rp. 23,512.50

0.2400 Pekerja Rp. 101,000.00 Rp. 24,240.00


0.1200 Tukang Batu Rp. 131,000.00 Rp. 15,720.00
0.0120 Kepala Tukang Rp. 161,000.00 Rp. 1,932.00
0.0120 Mandor Rp. 141,000.00 Rp. 1,692.00
Rp. 43,584.00 Rp. 188,415.31 Rp. 231,999.31
Overhead 10% Rp. 23,199.93
Jumlah Rp. 255,199.24
Dibulatkan Rp. 255,199.00

10 A.4.4.3.9. PEMASANGAN 1 M2 LANTAI UBIN GRANIT UKURAN 40 X 40 CM


6.6300 Bh Granite Rp. 27,550.00 Rp. 182,656.50
9.8000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,989.10
0.0450 M3 Pasir Pasang Rp. 168,150.00 Rp. 7,566.75
1.3000 Kg Semen Warna Rp. 15,675.00 Rp. 20,377.50

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.1250 Tukang Batu Rp. 131,000.00 Rp. 16,375.00
0.0130 Kepala Tukang Rp. 161,000.00 Rp. 2,093.00
0.0130 Mandor Rp. 141,000.00 Rp. 1,833.00
Rp. 45,551.00 Rp. 225,589.85 Rp. 271,140.85
Overhead 10% Rp. 27,114.09
Jumlah Rp. 298,254.94
Dibulatkan Rp. 298,254.00

11 A.4.4.3.39. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (10X20) CM


5.3000 Bh Plint Keramik Rp. 5,225.00 Rp. 27,692.50
1.1400 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 1,743.63
0.0030 M3 Pasir Pasang Rp. 168,150.00 Rp. 504.45
0.0250 Kg Semen Warna Rp. 15,675.00 Rp. 391.88

0.0900 Pekerja Rp. 101,000.00 Rp. 9,090.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 27,220.00 Rp. 30,332.46 Rp. 57,552.46
Overhead 10% Rp. 5,755.25
Jumlah Rp. 63,307.70
Dibulatkan Rp. 63,307.00

12 A.4.4.3.40. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (10X10) CM


10.6000 Bh Plint Keramik Rp. 3,135.00 Rp. 33,231.00
1.1400 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 1,743.63
0.0030 M3 Pasir Pasang Rp. 168,150.00 Rp. 504.45
0.0500 Kg Semen Warna Rp. 15,675.00 Rp. 783.75

0.0900 Pekerja Rp. 101,000.00 Rp. 9,090.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 27,220.00 Rp. 36,262.83 Rp. 63,482.83
Overhead 10% Rp. 6,348.28
Jumlah Rp. 69,831.11
Dibulatkan Rp. 69,831.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 52 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
13 A.4.4.3.41. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (5x20) CM
5.3000 Bh Plint Keramik Rp. 7,125.00 Rp. 37,762.50
0.5700 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 871.82
0.0015 M3 Pasir Pasang Rp. 168,150.00 Rp. 252.23
0.0130 Kg Semen Warna Rp. 15,675.00 Rp. 203.78

0.0900 Pekerja Rp. 101,000.00 Rp. 9,090.00


0.0900 Tukang Batu Rp. 131,000.00 Rp. 11,790.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0050 Mandor Rp. 141,000.00 Rp. 705.00
Rp. 27,220.00 Rp. 39,090.32 Rp. 66,310.32
Overhead 10% Rp. 6,631.03
Jumlah Rp. 72,941.35
Dibulatkan Rp. 72,941.00

14 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK UKURAN (20X25) CM


21.5000 Bh Keramik Rp. 3,847.50 Rp. 82,721.25
9.3000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,224.35
0.0180 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,026.70
1.9400 Kg Semen Warna Rp. 15,675.00 Rp. 30,409.50

0.9000 Pekerja Rp. 101,000.00 Rp. 90,900.00


0.4500 Tukang Batu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 163,440.00 Rp. 130,381.80 Rp. 293,821.80
Overhead 10% Rp. 29,382.18
Jumlah Rp. 323,203.98
Dibulatkan Rp. 323,203.00

15 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK BERMOTIF UKURAN (20X25) CM


21.5000 Bh Keramik Rp. 3,906.88 Rp. 83,997.81
9.3000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,224.35
0.0180 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,026.70
1.9400 Kg Semen Warna Rp. 15,675.00 Rp. 30,409.50

0.9000 Pekerja Rp. 101,000.00 Rp. 90,900.00


0.4500 Tukang Batu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 163,440.00 Rp. 131,658.36 Rp. 295,098.36
Overhead 10% Rp. 29,509.84
Jumlah Rp. 324,608.20
Dibulatkan Rp. 324,608.00

16 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK UKURAN (25X40) CM


10.5000 Bh Keramik Rp. 10,117.50 Rp. 106,233.75
9.3000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,224.35
0.0180 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,026.70
1.9400 Kg Semen Warna Rp. 15,675.00 Rp. 30,409.50

0.9000 Pekerja Rp. 101,000.00 Rp. 90,900.00


0.4500 Tukang Batu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 163,440.00 Rp. 153,894.30 Rp. 317,334.30
Overhead 10% Rp. 31,733.43
Jumlah Rp. 349,067.73
Dibulatkan Rp. 349,067.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 53 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
17 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK BERMOTIF UKURAN (25X40) CM
10.5000 Bh Keramik Rp. 7,148.75 Rp. 75,061.88
9.3000 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 14,224.35
0.0180 M3 Pasir Pasang Rp. 168,150.00 Rp. 3,026.70
1.9400 Kg Semen Warna Rp. 15,675.00 Rp. 30,409.50

0.9000 Pekerja Rp. 101,000.00 Rp. 90,900.00


0.4500 Tukang Batu Rp. 131,000.00 Rp. 58,950.00
0.0450 Kepala Tukang Rp. 161,000.00 Rp. 7,245.00
0.0450 Mandor Rp. 141,000.00 Rp. 6,345.00
Rp. 163,440.00 Rp. 122,722.43 Rp. 286,162.43
Overhead 10% Rp. 28,616.24
Jumlah Rp. 314,778.67
Dibulatkan Rp. 314,778.00

18 A.4.4.3.58. 1 M2 PEMASANGAN DINDING BATU ALAM ANDESIT


1.1000 M2 Batu Alam Andesit Rp. 197,505.00 Rp. 217,255.50
11.7500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 17,971.63
0.0350 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,885.25

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 241,112.38 Rp. 368,232.38
Overhead 10% Rp. 36,823.24
Jumlah Rp. 405,055.61
Dibulatkan Rp. 405,055.00

19 1 M2 PEMASANGAN DINDING GRANIT


1.1000 M2 Granit uk. 40 x 40 cm Rp. 172,187.50 Rp. 189,406.25
11.7500 Kg Semen Portland (PCC) Rp. 1,529.50 Rp. 17,971.63
0.0350 M3 Pasir Pasang Rp. 168,150.00 Rp. 5,885.25

0.7000 Pekerja Rp. 101,000.00 Rp. 70,700.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.0350 Mandor Rp. 141,000.00 Rp. 4,935.00
Rp. 127,120.00 Rp. 213,263.13 Rp. 340,383.13
Overhead 10% Rp. 34,038.31
Jumlah Rp. 374,421.44
Dibulatkan Rp. 374,421.00

20 A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM ( 10 X 20 )


50.000 Bh Paving Block Natural Tebal 6 cm Rp. 4,275.00 Rp. 213,750.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 98,983.30 Rp. 222,870.00 Rp. 321,853.30
Overhead 10% Rp. 32,185.33
Jumlah Rp. 354,038.63
Dibulatkan Rp. 354,038.00

21 A.4.4.3.65. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 8 CM ( 10 X 20 )


50.000 Bh Paving Block Natural Tebal 8 cm Rp. 4,750.00 Rp. 237,500.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 124,233.30 Rp. 246,620.00 Rp. 370,853.30
Overhead 10% Rp. 37,085.33
Jumlah Rp. 407,938.63
Dibulatkan Rp. 407,938.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 54 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
22 A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( 10 X 20 )
50.000 Bh Paving Block Berwarna Tebal 6 cm Rp. 5,225.00 Rp. 261,250.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 98,983.30 Rp. 270,370.00 Rp. 369,353.30
Overhead 10% Rp. 36,935.33
Jumlah Rp. 406,288.63
Dibulatkan Rp. 406,288.00

23 A.4.4.3.67. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 8 CM ( 10 X 20 )


50.000 Bh Paving Block Berwarna Tebal 8 cm Rp. 5,225.00 Rp. 261,250.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 124,233.30 Rp. 270,370.00 Rp. 394,603.30
Overhead 10% Rp. 39,460.33
Jumlah Rp. 434,063.63
Dibulatkan Rp. 434,063.00

24 A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM ( HEXAGON )


36.000 Bh Paving Block Natural Tebal 6 cm Rp. 11,875.00 Rp. 427,500.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 98,983.30 Rp. 436,620.00 Rp. 535,603.30
Overhead 10% Rp. 53,560.33
Jumlah Rp. 589,163.63
Dibulatkan Rp. 589,163.00

25 A.4.4.3.65. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 8 CM ( HEXAGON )


36.000 Bh Paving Block Natural Tebal 8 cm Rp. 12,587.50 Rp. 453,150.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 124,233.30 Rp. 462,270.00 Rp. 586,503.30
Overhead 10% Rp. 58,650.33
Jumlah Rp. 645,153.63
Dibulatkan Rp. 645,153.00

26 A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( HEXAGON )


36.000 Bh Paving Block Berwarna Tebal 6 cm Rp. 11,875.00 Rp. 427,500.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 98,983.30 Rp. 436,620.00 Rp. 535,603.30
Overhead 10% Rp. 53,560.33
Jumlah Rp. 589,163.63
Dibulatkan Rp. 589,163.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 55 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
27 A.4.4.3.67. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 8 CM ( HEXAGON )
36.000 Bh Paving Block Berwarna Tebal 8 cm Rp. 12,587.50 Rp. 453,150.00
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.5000 Pekerja Rp. 101,000.00 Rp. 50,500.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 124,233.30 Rp. 462,270.00 Rp. 586,503.30
Overhead 10% Rp. 58,650.33
Jumlah Rp. 645,153.63
Dibulatkan Rp. 645,153.00

28 PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( 30x30 ) CISANGKAN


11.000 Bh Paving Block Berwarna Tebal 6 cm Rp. 5,937.50 Rp. 65,312.50
0.0500 M3 Pasir Beton Rp. 182,400.00 Rp. 9,120.00

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.5000 Tukang Batu Rp. 131,000.00 Rp. 65,500.00
0.0500 Kepala Tukang Rp. 161,000.00 Rp. 8,050.00
0.0013 Mandor Rp. 141,000.00 Rp. 183.30
Rp. 98,983.30 Rp. 74,432.50 Rp. 173,415.80
Overhead 10% Rp. 17,341.58
Jumlah Rp. 190,757.38
Dibulatkan Rp. 190,757.00

XIV PEKERJAAN PENGECATAN


1 A.4.7.1.1. 1 1 M2 PENGIKISAN/PENGEROKAN PERMUKAAN CAT LAMA
0.0500 Kg Soda Api Rp. 70,553.18 Rp. 3,527.66

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 15,573.00 Rp. 3,527.66 Rp. 19,100.66
Overhead 10% Rp. 1,910.07
Jumlah Rp. 21,010.72
Dibulatkan Rp. 21,010.00

2 A.4.7.1.2. 1 1 M2 PENCUCIAN BIDANG PERMUKAAN TEMBOK YANG PERNAH DICAT


0.0500 Kg Sabun Rp. 50,540.00 Rp. 2,527.00

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 15,573.00 Rp. 2,527.00 Rp. 18,100.00
Overhead 10% Rp. 1,810.00
Jumlah Rp. 19,910.00
Dibulatkan Rp. 19,910.00

3 A.4.7.1.3. 1 1 M2 PENGEROKAN KARAT PADA PERMUKAAN BAJA CARA MANUAL


0.0500 Kg Sabun Rp. 50,540.00 Rp. 2,527.00

0.1500 Pekerja Rp. 101,000.00 Rp. 15,150.00


0.0080 Mandor Rp. 141,000.00 Rp. 1,128.00
Rp. 16,278.00 Rp. 2,527.00 Rp. 18,805.00
Overhead 10% Rp. 1,880.50
Jumlah Rp. 20,685.50
Dibulatkan Rp. 20,685.00

4 1 M2 PENGECATAN BIDANG KAYU LAMA


0.1500 Kg Plamir Rp. 38,000.00 Rp. 5,700.00
0.1700 Kg Cat Dasar Rp. 33,250.00 Rp. 5,652.50
0.1700 Kg Cat Penutup Rp. 51,300.00 Rp. 8,721.00

0.0700 Pekerja Rp. 101,000.00 Rp. 7,070.00


0.0075 Tukang Cat Rp. 131,000.00 Rp. 982.50
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0025 Mandor Rp. 141,000.00 Rp. 352.50
Rp. 9,371.00 Rp. 20,073.50 Rp. 29,444.50
Overhead 10% Rp. 2,944.45
Jumlah Rp. 32,388.95
Dibulatkan Rp. 32,388.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 56 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
5 A.4.7.1.4. 1 1 M2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir, 1 Lapis
Cat Dasar, 2 lapis Cat Penutup)
0.2000 Kg Cat Meni Rp. 33,250.00 Rp. 6,650.00
0.1500 Kg Plamir Rp. 38,000.00 Rp. 5,700.00
0.1700 Kg Cat Dasar Rp. 33,250.00 Rp. 5,652.50
0.2600 Kg Cat Penutup 2 Kali Rp. 51,300.00 Rp. 13,338.00
0.0100 Bh Kuas Rp. 21,422.50 Rp. 214.23
0.0300 Kg Pengencer Rp. 18,715.00 Rp. 561.45
0.2000 Lbr Ampelas Rp. 7,942.00 Rp. 1,588.40

0.0700 Pekerja Rp. 101,000.00 Rp. 7,070.00


0.0090 Tukang Cat Rp. 131,000.00 Rp. 1,179.00
0.0060 Kepala Tukang Rp. 161,000.00 Rp. 966.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 9,638.00 Rp. 33,704.58 Rp. 43,342.58
Overhead 10% Rp. 4,334.26
Jumlah Rp. 47,676.83
Dibulatkan Rp. 47,676.00

6 A.4.7.1.5. 1 M2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir, 1 Lapis


Cat Dasar, 3 Lapis Cat Penutup)
0.2000 Kg Cat Meni Rp. 33,250.00 Rp. 6,650.00
0.1500 Kg Plamir Rp. 38,000.00 Rp. 5,700.00
0.1700 Kg Cat Dasar Rp. 33,250.00 Rp. 5,652.50
0.3500 Kg Cat Penutup 3 Kali Rp. 51,300.00 Rp. 17,955.00
0.0100 Bh Kuas Rp. 21,422.50 Rp. 214.23
0.0300 Kg Pengencer Rp. 18,715.00 Rp. 561.45
0.2000 Lbr Ampelas Rp. 7,942.00 Rp. 1,588.40

0.0700 Pekerja Rp. 101,000.00 Rp. 7,070.00


0.1050 Tukang Cat Rp. 131,000.00 Rp. 13,755.00
0.0040 Kepala Tukang Rp. 161,000.00 Rp. 644.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 21,892.00 Rp. 38,321.58 Rp. 60,213.58
Overhead 10% Rp. 6,021.36
Jumlah Rp. 66,234.93
Dibulatkan Rp. 66,234.00

7 A.4.7.1.10 1 M2 PENGECATAN TEMBOK BARU (1 Lapis Plamir, 1 Lapis


Cat Dasar, 2 Lapis Cat Penutup)
0.1000 Kg Plamir Rp. 23,750.00 Rp. 2,375.00
0.1000 Kg Cat Dasar Rp. 33,250.00 Rp. 3,325.00
0.2600 Kg Cat Penutup 2 Kali Rp. 19,000.00 Rp. 4,940.00

0.0200 Pekerja Rp. 101,000.00 Rp. 2,020.00


0.0630 Tukang Cat Rp. 131,000.00 Rp. 8,253.00
0.0063 Kepala Tukang Rp. 161,000.00 Rp. 1,014.30
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 11,710.30 Rp. 10,640.00 Rp. 22,350.30
Overhead 10% Rp. 2,235.03
Jumlah Rp. 24,585.33
Dibulatkan Rp. 24,585.00

8 A.4.7.1.10 1 M2 PENGECATAN TEMBOK BARU (EXTERIOR) DENGAN


DULUX WEATHERSHEALD
0.1250 Kg Alkali Rp. 24,700.00 Rp. 3,087.50
0.2600 Kg Cat Dulux Weathersheald (Exterior) Rp. 106,400.00 Rp. 27,664.00

0.0200 Pekerja Rp. 101,000.00 Rp. 2,020.00


0.0630 Tukang Cat Rp. 131,000.00 Rp. 8,253.00
0.0063 Kepala Tukang Rp. 161,000.00 Rp. 1,014.30
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 11,710.30 Rp. 30,751.50 Rp. 42,461.80
Overhead 10% Rp. 4,246.18
Jumlah Rp. 46,707.98
Dibulatkan Rp. 46,707.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 57 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
9 A.4.7.1.11. 1 M2 PENGECATAN TEMBOK LAMA (1 Lapis Cat dasar, 2 Lapis
Cat Penutup)
0.1200 Kg Cat Dasar Rp. 33,250.00 Rp. 3,990.00
0.1800 Kg Cat Penutup 2 Kali Rp. 19,000.00 Rp. 3,420.00

0.0280 Pekerja Rp. 101,000.00 Rp. 2,828.00


0.0420 Tukang Cat Rp. 131,000.00 Rp. 5,502.00
0.0042 Kepala Tukang Rp. 161,000.00 Rp. 676.20
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 9,429.20 Rp. 7,410.00 Rp. 16,839.20
Overhead 10% Rp. 1,683.92
Jumlah Rp. 18,523.12
Dibulatkan Rp. 18,523.00

10 1 M2 PENGECATAN PLAFOND TRIPLEK (2 Lapis Cat Penutup)

0.0120 Kg Cat Dasar Rp. 33,250.00 Rp. 399.00


0.1800 Kg Cat Penutup 2 Kali Rp. 19,000.00 Rp. 3,420.00

0.0280 Pekerja Rp. 101,000.00 Rp. 2,828.00


0.0420 Tukang Cat Rp. 131,000.00 Rp. 5,502.00
0.0042 Kepala Tukang Rp. 161,000.00 Rp. 676.20
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 9,429.20 Rp. 3,819.00 Rp. 13,248.20
Overhead 10% Rp. 1,324.82
Jumlah Rp. 14,573.02
Dibulatkan Rp. 14,573.00

11 A.4.7.1.7. 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR


0.1500 Ltr Politur Rp. 61,655.00 Rp. 9,248.25
0.3720 Ltr Politur Jadi Rp. 61,655.00 Rp. 22,935.66
2.0000 Lbr Ampelas Rp. 7,942.00 Rp. 15,884.00

0.0400 Pekerja Rp. 101,000.00 Rp. 4,040.00


0.0600 Tukang Cat Rp. 131,000.00 Rp. 7,860.00
0.0160 Kepala Tukang Rp. 161,000.00 Rp. 2,576.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 14,899.00 Rp. 48,067.91 Rp. 62,966.91
Overhead 10% Rp. 6,296.69
Jumlah Rp. 69,263.60
Dibulatkan Rp. 69,263.00

12 A.4.7.1.9. 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS


0.1500 Ltr Vernis Rp. 22,325.00 Rp. 3,348.75
0.0500 Kg Dempul Rp. 38,000.00 Rp. 1,900.00
0.1000 Lbr Ampelas Rp. 7,942.00 Rp. 794.20

0.1600 Pekerja Rp. 101,000.00 Rp. 16,160.00


0.1600 Tukang Cat Rp. 131,000.00 Rp. 20,960.00
0.0160 Kepala Tukang Rp. 161,000.00 Rp. 2,576.00
0.0030 Mandor Rp. 141,000.00 Rp. 423.00
Rp. 40,119.00 Rp. 6,042.95 Rp. 46,161.95
Overhead 10% Rp. 4,616.20
Jumlah Rp. 50,778.15
Dibulatkan Rp. 50,778.00

13 A.4.7.1.16. 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


0.1000 Kg Meni Besi Rp. 33,568.25 Rp. 3,356.83
0.0100 Bh Kuas Rp. 21,422.50 Rp. 214.23

0.0200 Pekerja Rp. 101,000.00 Rp. 2,020.00


0.2000 Tukang Cat Rp. 131,000.00 Rp. 26,200.00
0.0200 Kepala Tukang Rp. 161,000.00 Rp. 3,220.00
0.0025 Mandor Rp. 141,000.00 Rp. 352.50
Rp. 31,792.50 Rp. 3,571.05 Rp. 35,363.55
Overhead 10% Rp. 3,536.36
Jumlah Rp. 38,899.91
Dibulatkan Rp. 38,899.00

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 58 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
14 A.4.7.1.17. 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH
0.1000 Kg Meni Besi Rp. 33,568.25 Rp. 3,356.83
0.0100 Ltr Pengencer Rp. 18,715.00 Rp. 187.15
0.0100 Bh Kuas Rp. 21,422.50 Rp. 214.23
0.0020 M3 Perancah Kayu Rp. 1,840,720.00 Rp. 3,681.44

0.2500 Pekerja Rp. 101,000.00 Rp. 25,250.00


0.2250 Tukang Cat Rp. 131,000.00 Rp. 29,475.00
0.0225 Kepala Tukang Rp. 161,000.00 Rp. 3,622.50
0.0075 Mandor Rp. 141,000.00 Rp. 1,057.50
Rp. 59,405.00 Rp. 7,439.64 Rp. 66,844.64
Overhead 10% Rp. 6,684.46
Jumlah Rp. 73,529.10
Dibulatkan Rp. 73,529.00

Arosuka, Januari 2020

Kepala Dinas Pekerjaan Umum dan Penataan Ruang


Kabupaten Solok

SYAIFUL. SY, ST, MT


NIP. 19650110 199403 1 006

Daftar Analisa Harga Satuan Pekerjaan Wil III Bidang CK T.A 2020 Hal. 59 dari 73
REKAPITULASI DAFTAR ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2020
KATEGORI WILAYAH III BERAT

NO URAIAN HARGA SATUAN (Rp.)


SATUAN
1 2 3 4

I PEKERJAAN PERSIAPAN
1 A. 2.2.1.9. 1 M2 PEMBERSIHAN LAPANGAN DAN PERATAAN M2 18,865.00
2 A. 2.2.1.13. 1 M3 PEMBONGKARAN BETON BERTULANG M3 1,584,704.00
3 A. 2.2.1.14. 1 M3 PEMBONGKARAN DINDING TEMBOK BATA M3 745,868.00
4 A. 2.2.1.4. 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK M' 53,247.00
5 A. 2.2.1.2 1 M' PEMBUATAN PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M M' 322,742.00
6 A. 2.2.1.15. PEMASANGAN 1 M2 PAGAR KAWAT JARING GALVANIS M2 82,477.00

II PEKERJAAN TANAH
1 A.2.3.1.1. 1 M3 PENGGALIAN TANAH BIASA SEDALAM 1 METER M3 87,202.00
2 A.2.3.1.2 1 M3 PENGGALIAN TANAH BIASA SEDALAM 2 METER M3 106,969.00
3 A.2.3.1.3 1 M3 PENGGALIAN TANAH BIASA SEDALAM 3 METER M3 127,046.00
4 A.2.3.1.4. 1 M3 PENGGALIAN TANAH KERAS SEDALAM 1 METER M3 116,063.00
5 A.2.3.1.5. 1 M3 PENGGALIAN TANAH CADAS SEDALAM 1 METER M3 175,956.00
6 A.2.3.1.61 M3 PENGGALIAN TANAH LUMPUR SEDALAM 1 METER M3 140,299.00
7 1 M3 PENGGALIAN TANAH BERBATU SEDALAM ≤ 1 METER M3 171,050.00
8 1 M3 PENGGALIAN TANAH BERBATU SEDALAM > 1 S.D 2 METER M3 189,915.00
9 1 M3 PENGGALIAN TANAH BERBATU SEDALAM > 2 S.D 3 METER M3 208,906.00
10 A.2.3.1.7. 1 M2 PENGERJAAN STRIPPING TEBING SETINGGI 1 METER M3 6,330.00
11 A.2.3.1.8. 1 M3 PEMBUANGAN TANAH SEJAUH 30 M' M3 38,214.00
12 A.2.3.1.9. 1 M3 PENGURUGAN KEMBALI GALIAN TANAH M3 63,305.00
13 A.2.3.1.10. 1 M3 PEMADATAN TANAH (PER 20 CM) M3 63,305.00
14 A.2.3.1.11 1 M3 PENGURUGAN DENGAN PASIR URUG M3 150,249.00
15 A.2.3.1.14 1 M3 PENGURUGAN SIRTU PADAT M3 228,530.00
16 A.2.3.1.14 1 M3 PENGURUGAN CADAS PADAT M3 147,020.00
17 1 M3 PENGURUGAN TANAH TIMBUNAN M3 128,210.00
18 PEMASANGAN RUMPUT LEMPENG / 1 M2 M3 66,324.00
19 PEMASANGAN RUMPUT GAJAH MINI / 1 M2 M3 80,233.00

III PEKERJAAN PONDASI


1 A.3.2.1.1 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 3 PP M3 944,890.00
2 A.3.2.1.2 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 4 PP M3 885,749.00
3 A.3.2.1.3. 1 M3 PEMASANGAN PONDASI BATU BELAH, CAMPURAN 1 PC : 5 PP M3 844,762.00
4 A.3.2.1.9. 1 M3 PEMASANGAN BATU KOSONG (ANSTAMPING) M3 413,033.00
5 A.3.2.1.10. 1 M3 PEMASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR M3 1,125,487.00
6 A.3.2.1.11. 1 M3 PEMASANGAN PONDASI SUMURAN DIAMETER 100 CM M3 992,994.00
7 1 M2 MEMASANG CETAKAN CINCIN SUMURAN M2 294,440.00
8 A.3.2.1.11. PEMANSANGAN 1 M3 PONDASI SUMURAN, DIAMETER 100 cm M3 992,994.00

IV PEKERJAAN PASANGAN DINDING


1 A. 4.4.1.1. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU M2 352,588.00
CAMPURAN SPESI 1 PC : 2 PP
2 A. 4.4.1.2. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU M2 336,873.00
CAMPURAN SPESI 1 PC : 3 PP
3 A. 4.4.1.3. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU M2 326,475.00
CAMPURAN SPESI 1 PC : 4 PP
4 A. 4.4.1.4. 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU M2 320,821.00
CAMPURAN SPESI 1 PC : 5 PP
5 A. 4.4.1.5 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1 BATU M2 318,296.00
CAMPURAN SPESI 1 PC : 6 PP
6 A. 4.4.1.7 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU M2 171,213.00
CAMPURAN SPESI 1 PC : 2 PP
7 A. 4.4.1.8 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU M2 163,877.00
CAMPURAN SPESI 1 PC : 3 PP
8 A.4.4.1.9 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU M2 159,604.00
CAMPURAN SPESI 1 PC : 4 PP

Harga Satuan Pekerjaan Konstruksi Wil III Bidang C.K T.A 2020
NO URAIAN HARGA SATUAN (Rp.)
SATUAN
9 A. 4.4.1.10 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU M2 156,912.00
CAMPURAN SPESI 1 PC : 5 PP
10 A. 4.4.1.11 1 M2 PEMASANGAN DINDING BATA MERAH (5X11X22) CM TEBAL 1/2 BATU M2 155,363.00
CAMPURAN SPESI 1 PC : 6 PP
11 A. 4.4.1.8 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 20, CAMPURAN SPESI 1 PC : 3 PP M2 254,284.00
12 A. 4.4.1.19 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 20, CAMPURAN SPESI 1 PC : 4 PP M2 252,564.00
13 A. 4.4.1.20 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 10, CAMPURAN SPESI 1 PC : 3 PP M2 208,045.00
14 A. 4.4.1.21 1 M2 PEMASANGAN DINDING HOLLOWBLOCK (HB) 10, CAMPURAN SPESI 1 PC : 4 PP M2 207,387.00
15 A. 4.4.1.22 1 M2 PEMASANGAN DINDING TERAWANG (ROOSTER) 12X11X24 CM M2 111,303.00
CAMPURAN SPESI 1 PC : 3 PP
16 A. 4.4.1.23 1 M2 PEMASANGAN DINDING TERAWANG (ROOSTER) 12X11X24 CM M2 111,303.00
CAMPURAN SPESI 1 PC : 4 PP
17 1 M2 PEMASANGAN DINDING BATAKO, CAMPURAN SPESI 1 PC : 4 PP M2 143,058.00

V PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 M2 PEMASANGAN PLESTERAN 1 PC : 1 PP, TEBAL 15 mm M2 88,972.00
2 A.4.4.2.2. 1 M2 PEMASANGAN PLESTERAN 1 PC : 2 PP, TEBAL 15 mm M2 80,828.00
3 A.4.4.2.3. 1 M2 PEMASANGAN PLESTERAN 1 PC : 3 PP, TEBAL 15 mm M2 77,264.00
4 A.4.4.2.4. 1 M2 PEMASANGAN PLESTERAN 1 PC : 4 PP, TEBAL 15 mm M2 74,865.00
5 A.4.4.2.5. 1 M2 PEMASANGAN PLESTERAN 1 PC : 5 PP, TEBAL 15 mm M2 73,458.00
6 A.4.4.2.6. 1 M2 PEMASANGAN PLESTERAN 1 PC : 6 PP, TEBAL 15 mm M2 72,351.00
7 A.4.4.2.13. 1 M2 PEMASANGAN PLESTERAN 1 PC : 1 PP, TEBAL 20 mm M2 108,143.00
8 A.4.4.2.14. 1 M2 PEMASANGAN PLESTERAN 1 PC : 3 PP, TEBAL 20 mm M2 101,995.00
9 A.4.4.2.15. 1 M2 PEMASANGAN PLESTERAN 1 PC : 4 PP, TEBAL 20 mm M2 100,131.00
10 A.4.4.2.16. 1 M2 PEMASANGAN PLESTERAN 1 PC : 5 PP, TEBAL 20 mm M2 98,317.00
11 A.4.4.2.17. 1 M2 PEMASANGAN PLESTERAN 1 PC : 6 PP, TEBAL 20 mm M2 96,779.00
12 A.4.4.2.19. 1 M2 PEMASANGAN BERAPEN 1 PC : 5 PP, TEBAL 15 mm M2 43,661.00
13 A.4.4.2.20. 1 M PEMASANGAN PLESTERAN SKONING 1 PC : 3 PP, LEBAR 10 mm M 77,478.00
14 A.4.4.2.23. 1 M2 PEMASANGAN PLESTERAN CIPRAT 1 PC : 2 PP M2 60,215.00
15 A.4.4.2.24 1 M2 PEMASANGAN FINISHING SIAR PASANGAN BATA MERAH M2 35,359.00
16 A.4.4.2.25 1 M2 PEMASANGAN FINISHING SIAR PASANGAN CONBLOCK EKSPOSE M2 16,841.00
17 A.4.4.2.26. 1 M2 PEMASANGAN FINISHING SIAR PASANGAN BATU KALI ADUKAN 1 PC : 2 PP M2 72,814.00
18 A.4.4.2.27. 1 M2 PEMASANGAN ACIAN M2 45,419.00

VI PEKERJAAN KAYU
1 A.4.6.1.1. 1 M3 PEMBUATAN DAN PEMASANGAN KUSEN PINTU DAN JENDELA, KAYU KLAS I M3 8,310,863.00
2 A.4.6.1.2 1 M3 PEMBUATAN DAN PEMASANGAN KUSEN PINTU DAN JENDELA, KAYU KLAS II M3 7,562,616.00
3 A.4.6.1.3. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU KLAMP STANDAR, KAYU KLAS II M2 348,373.00
4 A.4.6.1.4. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU KLAMP SEDERHANA, KAYU KLAS III M2 339,189.00
5 A.4.6.1.5. 1 M2 PEMBUATAN DAN PEMASANGAN DAUN PINTU PANEL KAYU KLAS I M2 770,925.00
6 A.4.6.1.5. 1 M2 PEMBUATAN DAN PEMASANGAN DAUN PINTU PANEL KAYU KLAS II M2 748,552.00
7 A.4.6.1.6. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA KACA, KAYU KLAS I M2 583,412.00
8 A.4.6.1.6. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA KACA, KAYU KLAS II M2 569,988.00
9 A.4.6.1.7. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA JALUSI KAYU KLAS I M2 865,910.00
10 A.4.6.1.7. 1 M2 PEMBUATAN DAN PEMASANGAN PINTU & JENDELA JALUSI KAYU KLAS II M2 830,112.00
11 A.4.6.1.8. 1 M2 PEMBUATAN DAUN PINTU KAYU LAPIS (PLYWOOD) RANGKAP, M2 603,544.00
RANGKA TERTUTUP KAYU KLAS II (LEBAR SAMPAI 90 CM)
12 A.4.6.1.9. 1 M2 PEMBUATAN PINTU PLYWOOD RANGKAP,RANGKA EXPOSE KAYU KLAS I M2 680,330.00
13 A.4.6.1.9. 1 M2 PEMBUATAN PINTU PLYWOOD RANGKAP,RANGKA EXPOSE KAYU KLAS II M2 666,011.00
14 A.4.6.1.10. 1 M2 PEMASANGAN JALUSI KUSEN, KAYU KLAS I M2 690,062.00
15 A.4.6.1.10. 1 M2 PEMASANGAN JALUSI KUSEN, KAYU KLAS II M2 656,502.00
16 A.4.6.1.11. 1 M2 PEMASANGAN TEAKWOOD RANGKAP, RANGKA EXPOSE KAYU KLAS I M2 814,861.00
17 A.4.6.1.12. 1 M2 PEMASANGAN TEAKWOOD RANGKAP LAPIS FORMIKA, RANGKA EXPOSE KAYU KLAS II M2 899,852.00
18 A.4.6.1.13. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KLAS I BENTANG 6 METER M3 6,802,443.00
19 A.4.6.1.13. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KLAS II BENTANG 6 METER M3 6,333,591.00
20 A.4.6.1.14. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KLAS I M3 8,801,526.00
21 A.4.6.1.14. 1 M3 PEMASANGAN KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KLAS II M3 8,290,051.00
22 A.4.6.1.15. 1 M3 PEMASANGAN KONSTRUKSI GORDENG, KAYU KLAS II M3 7,920,330.00
23 A.4.6.1.16. 1 M2 PEMASANGAN RANGKA ATAP GENTENG KERAMIK, KAYU KLAS II M2 194,822.00
24 A.4.6.1.17. 1 M2 PEMASANGAN RANGKA ATAP GENTENG BETON, KAYU KLAS II M2 263,049.00
25 A.4.6.1.18. 1 M2 PEMASANGAN RANGKA ATAP SIRAP, KAYU KLAS II M2 80,147.00
26 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (60X120) CM, KAYU KLAS II M2 122,418.00

Harga Satuan Pekerjaan Konstruksi Wil III Bidang C.K T.A 2020
NO URAIAN HARGA SATUAN (Rp.)
SATUAN
27 A.4.6.1.19. 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (50X100) CM, KAYU KLAS II M2 130,322.00
28 A.4.6.1.20. 1 M2 PEMASANGAN RANGKA LANGIT-LANGIT (60x60) CM, KAYU KLAS II M2 129,581.00
29 A.4.6.1.21. 1 M PEMASANGAN LISTPLANK UKURAN (3x20) CM, KAYU KLAS II M 82,673.00
30 A.4.6.1.22. 1 M PEMASANGAN LISTPLANK UKURAN (3x30) CM, KAYU KLAS II M 82,491.00
31 A.4.6.1.23. 1 M2 PEMASANGAN RANGKA DINDING PEMISAH (60x120) CM, KAYU KLAS II M2 184,276.00
32 1 M2 PEMASANGAN DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KLAS II M2 388,807.00
33 A.4.6.1.25. 1 M2 PEMASANGAN DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KLAS II M2 298,338.00
34 A.4.6.1.26. 1 M2 PEMASANGAN DINDING LAMBRIZIRING DARI PAPAN KAYU KLAS II M2 391,688.00

VII PEKERJAAN BETON


1 A.4.1.1.1 1 M3 MEMBUAT BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (12 + 2) CM, W/C = 0,87 M3 975,019.00
2 A.4.1.1.2 1 M3 MEMBUAT BETON MUTU fc' = 9,8 MPa (K 125), SLUMP (12 + 2) CM, W/C = 0,78 M3 1,020,169.00
3 A.4.1.1.3 1 M3 MEMBUAT BETON MUTU fc' = 12,2 MPa (K 150), SLUMP (12 + 2) CM, W/C = 0,72 M3 1,055,568.00
4 A.A.4.1.1.4 1 M3 MEMBUAT LANTAI KERJA BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (3-6) CM, W/C = 0,87 M3 887,315.00
5 A. A.4.1.1.5 1 M3 MEMBUAT BETON MUTU fc' = 14,5 MPa (K 175), SLUMP (12 + 2) CM, W/C = 0,66 M3 1,097,467.00
6 A.4.1.1.6 1 M3 MEMBUAT BETON MUTU fc' = 16,9 MPa (K 200), SLUMP (12 + 2) CM, W/C = 0,61 M3 1,137,398.00
7 A.4.1.1.7. 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58 M3 1,245,760.00
8 A.4.1.1.8. 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56 M3 1,265,397.00
9 A.4.1.1.9 1 M3 MEMBUAT BETON MUTU fc' = 24,0 MPa (K 275), SLUMP (12 + 2) CM, W/C = 0,53 M3 1,299,031.00
10 A.4.1.1.10. 1 M3 MEMBUAT BETON MUTU fc' = 26,4 MPa (K 300), SLUMP (12 + 2) CM, W/C = 0,52 M3 1,309,519.00
11 A.4.1.1.11. 1 M3 MEMBUAT BETON MUTU fc' = 28,8 MPa (K 325), SLUMP (12 + 2) CM, W/C = 0,49 M3 1,414,563.00
12 A.4.1.1.12. 1 M3 MEMBUAT BETON MUTU fc' = 31,2 MPa (K 350), SLUMP (12 + 2) CM, W/C = 0,48 M3 1,428,244.00
13 A.4.1.1.7. 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58 ( Stone Cruiser ) M3 1,298,440.00
14 A.4.1.1.8. 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56 ( Stone Cruiser ) M3 1,317,674.00
15 1 M3 MENGGUNAKAN READY MIXED K-225 M3 1,512,228.00
16 1 M3 MENGGUNAKAN READY MIXED K-250 M3 1,562,325.00
17 1 M3 MENGGUNAKAN READY MIXED K-300 M3 1,719,279.00
18 MEMASANG GORONG - GORONG PIPA BETON BERTULANG, Ø 60 cm / M1 M1 669,959.00
19 MEMASANG GORONG - GORONG PIPA BETON BERTULANG, Ø 30 cm / M1 M1 296,526.00
20 MEMASANG GORONG - GORONG PIPA BETON TANPA TULANGAN, Ø 60 cm / M1 M1 440,634.00
21 MEMASANG GORONG - GORONG PIPA BETON TANPA TULANGAN, Ø 30 cm / M1 M1 163,539.00
22 A.4.1.1.17 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Kg 19,465.00
23 A.4.1.1.18 1 Kg PEMASANGAN KABEL PRESSTRESSED POLOS/STRANDS Kg 303,442.00
24 A.4.1.1.19 1 Kg PEMASANGAN JARING KAWAT BAJA/WIRE MESH Kg 18,346.00
25 A.4.1.1.20 1 M2 PEMASANGAN BEKISTING UNTUK PONDASI M2 170,526.00
26 A.4.1.1.21 1 M2 PEMASANGAN BEKISTING UNTUK SLOOF, KOLOM PRAKTIS, BALOK PRAKTIS, PET BETON M2 178,448.00
27 A.4.1.1.22 1 M2 PEMASANGAN BEKISTING UNTUK KOLOM M2 304,852.00
28 A.4.1.1.23 1 M2 PEMASANGAN BEKISTING UNTUK BALOK M2 308,905.00
29 A.4.1.1.24 1 M2 PEMASANGAN BEKISTING UNTUK LANTAI M2 424,191.00
30 1 M2 PEMASANGAN BEKISTING UNTUK LANTAI PLAT DUIKER M2 227,203.00
31 A.4.1.1.25 1 M2 PEMASANGAN BEKISTING UNTUK DINDING M2 327,166.00
32 A.4.1.1.26 1 M2 PEMASANGAN BEKISTING UNTUK TANGGA M2 288,663.00
33 1 M2 PEMASANGAN BEKISTING COR BETON JALAN M2 127,417.00

VIII PEKERJAAN PENUTUP ATAP


1 A.4.5.2.32. 1 M2 PEMASANGAN ATAP GENTENG METAL M2 123,828.00
2 A.4.5.2.37. 1 M' PEMASANGAN NOK GENTENG METAL M' 108,157.00
3 A.4.5.2.39 1 M2 PEMASANGAN ATAP SENG GELOMBANG M2 82,800.00
4 A.4.5.2.39 1 M2 PEMASANGAN ATAP SENG GELOMBANG WARNA M2 77,976.00
5 A.4.5.2.40. 1 M' PEMASANGAN ATAP NOK SENG M2 37,815.00

IX PEKERJAAN LANGIT-LANGIT (FLAFOND)


1 A.4.5.1.5. 1 M2 PEMASANGAN LANGIT-LANGIT TRIPLEKS UKURAN (120x240) cm, tebal 3 mm M2 88,744.43
2 A.4.5.1.5. 1 M2 PEMASANGAN LANGIT-LANGIT TRIPLEKS UKURAN (120x240) cm, tebal 4 mm M2 74,334.00
3 A.4.5.1.6. 1 M2 PEMASANGAN LANGIT-LANGIT LAMBRIZIRING KAYU, TEBAL 9 MM M2 275,747.00
4 A.4.5.1.9. 1 M' PEMASANGAN LIST LANGIT-LANGIT KAYU PROFIL M 33,046.00
5 A.4.5.1.7. 1 M2 PEMASANGAN LANGIT-LANGIT GYPSUM BOARD UKURAN (120X240X9) MM M2 69,847.00
6 1 M2 PEMASANGAN LIST PLAFOND GYPSUM PROFIL M' 40,509.00
7 1 M2 PEMASANGAN LANGIT-LANGIT PLAFOND PVC, RANGKA FURING CHANNEL ZINCALUME M2 309,289.00

Harga Satuan Pekerjaan Konstruksi Wil III Bidang C.K T.A 2020
NO URAIAN HARGA SATUAN (Rp.)
SATUAN
X PEKERJAAN SANITASI GEDUNG
1 A.5.1.1 2. PEMASANGAN 1 BUAH CLOSET JONGKOK PORSLEN Bh 542,804.00
2 A.5.1.1.1. PEMASANGAN 1 BUAH CLOSET DUDUK/MONOBLOK Bh 2,551,125.00
3 A.5.1.1 4. PEMASANGAN 1 BUAH URINOIR Bh 5,660,042.00
4 A.5.1.1 5. PEMASANGAN 1 BUAH WASTAFEL Bh 1,592,503.00
5 A.5.1.1 7. PEMASANGAN 1 BUAH BAK AIR FIBREGLASS VOLUME 1 M3 Bh 676,349.00
6 A.5.1.1 15. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 30X30 CM TINGGI 35 CM Bh 545,668.00
7 A.5.1.1 16. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 45x45 CM TINGGI 50 CM Bh 825,078.00
8 A.5.1.1 17. PEMASANGAN 1 BUAH BAK KONTROL PASANGAN BATU BATA UK. 60x60 CM TINGGI 65 CM Bh 1,018,600.00
9 A.5.1.1 18. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1/2" M 90,349.00
10 A.5.1.1 20. PEMASANGAN 1 M' PIPA GALVANIS DIA. 3/4" M 106,547.00
11 A.5.1.1 21. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1" M 138,942.00
12 A.5.1.1 22. PEMASANGAN 1 M' PIPA GALVANIS DIA. 1 1/2" M 221,692.00
13 A.5.1.1 23. PEMASANGAN 1 M' PIPA GALVANIS DIA. 3" M 442,939.00
14 A.5.1.1 24. PEMASANGAN 1 M' PIPA GALVANIS DIA. 4" M 613,013.00
15 A.5.1.1 25. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 1/2" M 25,356.00
16 A.5.1.1 26. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 3/4" M 28,596.00
17 A.5.1.1 27. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 1" M 35,075.00
18 A.5.1.1 29. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 2" M 62,331.00
19 A.5.1.1 31. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 3' M 113,261.00
20 A.5.1.1 32. PEMASANGAN 1 M' PIPA PVC TIPE AW DIA. 4' M 178,051.00
21 A.5.1.1 19 PEMASANGAN 1 BUAH KRAN DIA. 3/4" ATAU 1/2" Bh 130,499.00
22 MEMBUAT 1 UNIT SEPTICK TANK KAP. 15 ORG LENGKAP DENGAN RESAPAN (Uk.1.00M x 2.00M x 1.40 M) Unit 5,002,712.00

XI PEKERJAAN BESI DAN ALUMUNIUM


1 A.4.2.1.1. 1 Kg PEMASANGAN BESI PROFIL Kg 37,870.00
2 A.4.2.1.2 . 1 Kg PEMASANGAN RANGKA KUDA-KUDA BAJA IWF Kg 37,870.00
3 A.4.2.1.3. 1 Kg PENGERJAAN PEKERJAAN PERAKITAN Kg 758.00
4 A.4.2.1.5. 1 Cm PENGERJAAN PENGELASAN DENGAN LAS LISTRIK Cm 3,502.00
5 A.4.2.1.15. 1 M2 PEMASANGAN TERALI BESI STRIP (2x3) mm M2 674,293.00
6 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (SILVER) M' 185,886.00
7 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (HITAM/COKLAT) M' 200,829.00
8 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 4" (COATING POWDER) M' 250,143.00
9 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (SILVER) M' 145,653.00
10 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (HITAM/COKLAT) M' 156,573.00
11 A.4.2.1.11. 1 M' PEMASANGAN KUZEN PINTU ALLUMINIUM 3" (COATING POWDER) M' 192,610.00
12 A.4.2.1.20 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1x40x40x2 MM, MODUL 60x120 CM, DINDING PARTISI M2 209,908.00
13 A.4.2.1.21. 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1x40x40x2 MM, MODUL 60x60 CM, FLAFON M2 253,492.00
14 1 M2 PEKERJAAN KUDA-KUDA BAJA RINGAN M2 273,614.00
15 A.4.2.1.8. 1 M2 PEMASANGAN PINTU FOLDING GATE M2 1,119,377.00
16 A.4.2.1.13. PEMASANGAN 1 M2 PINTU KACA RANGKA ALUMUNIUM M2 1,147,781.00

XII PEKERJAAN KUNCI DAN KACA


1 A.4.6.2.1. 1 BUAH PEMASANGAN KUNCI TANAM SES ASLI Bh 471,012.00
2 A.4.6.2.2. 1 BUAH PEMASANGAN KUNCI TANAM BIASA Bh 322,828.00
3 A.4.6.2.5. 1 BUAH PEMASANGAN ENGSEL PINTU Bh 44,349.00
4 A.4.6.2.5. 1 BUAH PEMASANGAN ENGSEL JENDELA Bh 33,567.00
5 1 BUAH PEMASANGAN GRENDEL JENDELA Bh 28,342.00
6 A.4.6.2.9. PEMASANGAN 1 BH KAIT ANGIN Bh 40,241.00
7 1 BH TANGAN - TANGAN JENDELA Bh 33,567.00
8 A.4.6.2.19. 1 M2 PEMASANGAN KACA, TEBAL 12 mm ( Biru ) M2 1,309,031.00
9 A.4.6.2.18.. 1 M2 PEMASANGAN KACA, TEBAL 8 mm M2 398,399.00
10 A.4.6.2.17. 1 M2 PEMASANGAN KACA, TEBAL 5 mm M2 165,151.00
11 A.4.6.2.16. 1 M2 PEMASANGAN KACA, TEBAL 3 mm M2 139,854.00
12 A.4.6.2.18. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 8 mm M2 509,993.00
13 A.4.6.2.17. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 5 mm M2 182,386.00
14 A.4.6.2.16. 1 M2 PEMASANGAN KACA RAYBAN, TEBAL 3 mm M2 162,844.00

XIII PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


1 A.4.4.3.34. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (40X40) CM M2 269,096.00
2 A.4.4.3.34. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (40X40) CM M2 275,806.00
3 A.4.4.3.35. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (30X30) CM M2 266,632.00

Harga Satuan Pekerjaan Konstruksi Wil III Bidang C.K T.A 2020
NO URAIAN HARGA SATUAN (Rp.)
SATUAN
4 A.4.4.3.35. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (30X30) CM M2 273,116.00
5 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (20X20) CM M2 261,782.00
6 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (20X20) CM M2 267,874.00
7 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK UKURAN (20X25) CM M2 263,151.00
8 A.4.4.3.36. 1 M2 PEMASANGAN LANTAI KERAMIK BERMOTIF UKURAN (25X25) CM M2 263,151.00
9 A.4.4.3.13. 1 M2 PEMASANGAN LANTAI GRANITE UKURAN (60X60) CM M2 255,199.00
10 A.4.4.3.9. PEMASANGAN 1 M2 LANTAI UBIN GRANIT UKURAN 40 X 40 CM M2 298,254.00
11 A.4.4.3.39. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (10X20) CM M' 63,307.00
12 A.4.4.3.40. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (10X10) CM M' 69,831.00
13 A.4.4.3.41. 1 M' PEMASANGAN PLINT KERAMIK UKURAN (5x20) CM M' 72,941.00
14 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK UKURAN (20X25) CM M2 323,203.00
15 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK BERMOTIF UKURAN (20X25) CM M2 324,608.00
16 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK UKURAN (25X40) CM M2 349,067.00
17 A.4.4.3.54. 1 M2 PEMASANGAN DINDING KERAMIK BERMOTIF UKURAN (25X40) CM M2 314,778.00
18 A.4.4.3.58. 1 M2 PEMASANGAN DINDING BATU ALAM ANDESIT M2 405,055.00
19 1 M2 PEMASANGAN DINDING GRANIT M2 374,421.00
20 A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM ( 10 X 20 ) M2 354,038.00
21 A.4.4.3.65. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 8 CM ( 10 X 20 ) M2 407,938.00
22 A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( 10 X 20 ) M2 406,288.00
23 A.4.4.3.67. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 8 CM ( 10 X 20 ) M2 434,063.00
24 A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM ( HEXAGON ) M2 589,163.00
25 A.4.4.3.65. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 8 CM ( HEXAGON ) M2 645,153.00
26 A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( HEXAGON ) M2 589,163.00
27 A.4.4.3.67. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 8 CM ( HEXAGON ) M2 645,153.00
28 PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM ( 30x30 ) CISANGKAN M2 190,757.00

XIV PEKERJAAN PENGECATAN


1 A.4.7.1.1. 1 1 M2 PENGIKISAN/PENGEROKAN PERMUKAAN CAT LAMA M2 21,010.00
2 A.4.7.1.2. 1 1 M2 PENCUCIAN BIDANG PERMUKAAN TEMBOK YANG PERNAH DICAT M2 19,910.00
3 A.4.7.1.3. 1 1 M2 PENGEROKAN KARAT PADA PERMUKAAN BAJA CARA MANUAL M2 20,685.00
4 1 M2 PENGECATAN BIDANG KAYU LAMA M2 32,388.00
5 A.4.7.1.4. 1 1 M2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir, 1 LapisCat Dasar, 2 lapis Cat Penutup) M2 47,676.00
6 A.4.7.1.5. 1 M2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir, 1 LapisCat Dasar, 3 Lapis Cat Penutup) M2 66,234.00
7 A.4.7.1.10 1 M2 PENGECATAN TEMBOK BARU (1 Lapis Plamir, 1 LapisCat Dasar, 2 Lapis Cat Penutup) M2 24,585.00
8 A.4.7.1.10 1 M2 PENGECATAN TEMBOK BARU (EXTERIOR) DENGANDULUX WEATHERSHEALD M2 46,707.00
9 A.4.7.1.11. 1 M2 PENGECATAN TEMBOK LAMA (1 Lapis Cat dasar, 2 LapisCat Penutup) M2 18,523.00
10 1 M2 PENGECATAN PLAFOND TRIPLEK (2 Lapis Cat Penutup) M2 14,573.00
11 A.4.7.1.7. 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR M2 69,263.00
12 A.4.7.1.9. 1 M2 PELABURAN BIDANG KAYU DENGAN VERNIS M2 50,778.00
13 A.4.7.1.16. 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI M2 38,899.00
14 A.4.7.1.17. 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH M2 73,529.00

Arosuka, Januari 2020


Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kabupaten Solok

SYAIFUL. SY, ST, MT


NIP. 19650110 199403 1 006

Harga Satuan Pekerjaan Konstruksi Wil III Bidang C.K T.A 2020
PEMERINTAH KABUPATEN SOLOK
DINAS PEKERJAAN UMUM DAN PENATAAN
RUANG
BIDANG PERUMAHAN
Komplek Perkantoran Aro Suka Telp./Fax. (0755) 31566

HARGA SATUAN UPAH, BAHAN DAN


ANALISA HARGA SATUAN PEKERJAAN

KATEGORI WILAYAH III BERAT

Kec. Tigo Lurah (Simanau dan Rangkiang Luluih)


Kec. IX Koto Sungai Lasi (Indudur, Pianggu Atas, Koto Laweh, Bukit Bais, Tauang-Taruang)
Kec. Payung Sekaki (Aia Luo)
Kec. X Koto Diatas (Pakarohan, Ganting Balai Selasa, Pasilihan)
Kec. Hiliran Gumanti (Sungai Abu)
Dan Lokasi-Lokasi lainnya yang kondisinya setara wilayah III ( Tiga )

TAHUN ANGGARAN
2020

HARGA SATUAN PEKERJAAN BERDASARKAN PERATURAN MENTERI PEKERJAAN UMUM DAN PERUMAHAN
RAKYAT REPUBLIK INDONESIA NOMOR 28/PRT/M/2016 TENTANG PEDOMAN ANALISIS HARGA SATUAN
PEKERJAAN BIDANG KECIPTAKARYAAN
DAFTAR PENETAPAN HARGA BAHAN / MATERIAL
PERHITUNGAN RENCANA ANGGARAN BIAYA ( RAB )
DINAS PERUMAHAN RAKYAT, KAWASAN PERMUKIMAN DAN PERTANAHAN KABUPATEN SOLOK
TAHUN ANGGARAN 2018

NAMA BAHAN

No. URAIAN
Beton Ready Mix Pasir Beton Semen Baja IWF Besi Beton Ulir Besi Beton Polos Sirtu

1 2. 3.
KATEGORI JARAK DEKAT
1 Kec. IX Koto Sungai Lasi Bawah
Kec. Kubung
Kec. Bukit Sundi (Kecuali Dilam) K-175 1,035,000.00 150,000.00 61,300.00 12,000.00 12,000.00 10,000.00 100,000.00
Kec. Junjung Sirih K-225 1,080,000.00
Kec. X Koto Singkarak Bawah K-250 1,125,000.00
Kec. Gunung Talang K-300 1,265,000.00
Kec. Danau Kembar K-350 1,450,000.00

KATEGORI JARAK SEDANG


2 Kec. Lembang Jaya K-175 1,075,000.00 153,000.00 62,000.00 13,000.00 13,000.00 10,600.00 120,000.00
Kec. Lembah Gumanti K-225 1,120,000.00
Kec. Pantai Cermin K-250 1,165,000.00
Kec. X Koto Singkarak Atas K-300 1,305,000.00
Kec. X Koto Diatas (Keuali Pabusuik ,
Sibarambang ) K-350 1,490,000.00
Kec. Payung Sekaki ( Kecuali Aie Luo )
Kec. Hiliran Gumanti (Kecuali Sariak dan
Sungai Abu)
Kec. Bukit Sundi (Dilam)
KATEGORI JARAK JAUH
3 Kec. IX Koto Sungai Lasi Atas K-175 1,115,000.00 155,000.00 63,000.00 14,000.00 14,000.00 11,600.00 130,000.00
Koto Laweh K-225 1,160,000.00
Indudur K-250 1,205,000.00
Pianggu Atas K-300 1,345,000.00
Bukit Bais K-350 1,530,000.00
Sungai Durian
Taruang-Taruang
Kec. Payung Sekaki ( Aie Luo )
Kec. X Koto Diatas ( Sibarambang )
Kec. Tigo Lurah ( Simanau )
Kec. Hiliran Gumanti ( Sariak dan Sungai Abu )

KATEGORI JARAK SANGAT JAUH


4 Kec. Tigo Lurah ( Kecuali Simanau ) K-175 1,155,000.00 157,000.00 64,000.00 15,000.00 15,000.00 12,600.00 140,000.00
Kec. Payung Sekaki ( Kipek ) K-225 1,200,000.00
Kec. X Koto Diatas ( Pabusuik ) K-250 1,245,000.00
K-300 1,385,000.00
K-350 1,570,000.00
)
AN KABUPATEN SOLOK

Kerikil Beton Kerikil Beton Ket


Tanah Cadas Tanah Urug Agregat halus Agregat Kasar Abu Batu / Filler
( Alam ) ( Pecah Mesin )

75,000.00 64,000.00 228,000.00 223,000.00 150,000.00 223,000.00 228,000.00

75,000.00 64,000.00 244,000.00 239,000.00 153,000.00 239,000.00 244,000.00

75,000.00 64,000.00 260,000.00 255,000.00 155,000.00 255,000.00 260,000.00

75,000.00 64,000.00 284,000.00 279,000.00 157,000.00 279,000.00 284,000.00


DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN ANGGARAN 2018

HARGA
NO URAIAN SATUAN Harga Survey Harga Survey
SATUAN (Rp.)
1 2 3 4 Lapangan Tahun 2017

II BAHAN
A BAHAN BATU - BATUAN
1 Batu Kali / Gunung / Belah M3 147,000.00 150,000
2 Batu Pecah Alam ukr 5/10 M3 157,500.00 150,000
3 Batu Pecah Alam ukr 5/7 M3 157,500.00 150,000
4 Batu Pecah Alam ukr 3/4 M3 248,745.00 236,900
5 Batu Pecah Alam ukr 2/3 M3 248,745.00 236,900
6 Batu Pecah mesin ukr 1/2 M3 228,000.00 210,000

B BAHAN KERIKIL / KORAL


1 Kerikil Beton ( Alam ) M3 150,000.00 150,000.00
2 Split (Batu pecah 0,5-1 cm/mesin) M3 228,000.00 210,000.00
3 Krekel Timbunan (Sirtu) M3 100,000.00
4 Agregat Kasar ( Stone Cruiser ) M3 223,000.00
5 Agregat halus ( Stone Cruiser ) M3 228,000.00

C BAHAN PASIR
1 Pasir Pasang M3 150,000.00 150,000.00
2 Pasir Beton M3 150,000.00 150,000.00
3 Pasir Urug M3 150,000.00 150,000.00
6 Sirtu M3 100,000.00 105,200.00
7 Abu Batu / Filler M3 228,000.00 220,500.00
E BAHAN SEMEN
1 Semen Portland / PC Kg 1,226.00
2 Semen Warna (Tepung Alfa) Kg 9,900.00
11 Gypsum Board tebal 9 mm Lbr 75,000.00 72,000
12 Gypsum Board tebal 6 mm Lbr 47,000.00 44,000
13 Formika Lbr 105,000.00 100,300
14 GRC Board tebal 4 mm Lbr 67,000.00 64,375
15 GRC Board tebal 6 mm Lbr 110,000.00 92,700
16 GRC Board tebal 9 mm Lbr 147,000.00
17 List Profil Gypsum M' 15,000.00 15,000
18 Compound Gypsum Kg 4,920.00 4,920
19 Compound GRC Kg 4,800.00 4,800
21 Plafond PVC Board 6 mm (putih) M' 11,250.00 11,250
22 Plafond PVC Board 8 mm (putih) M' 17,625.00 17,625
23 Plafond PVC Board 8 mm (motif) M' 18,625.00 18,625
24 Kalsi Board tebal 4 mm Lbr 70,000.00 70,000
25 Kalsi Board tebal 8 mm Lbr 180,000.00 180,000
26 Papan Listplank GRC M' 30,000.00 30,000

3 Besi Beton Polos Kg 10,000.00


4 Besi Beton Ulir ks Kg 12,000.00
5 Besi Profil IWF Kg 12,000.00
6 Besi Strip kg 15,862.00
12 Besi Plat Baja tebal 2 mm Lbr 493,500.00
13 Pagar BRC (tinggi 0,90 m) Lbr 185,000.00
14 Pagar BRC (tinggi 1,20 m) Lbr 220,000.00
15 Truss C-75, 0.75 M' 20,000.00
16 Truss C-75, 0.60 M' 18,000.00

Daftar Harga Satuan Upah dan Bahan Jarak Dekat TA. 2017 Hal. 68 dari 73
HARGA
NO URAIAN SATUAN Harga Survey Harga Survey
SATUAN (Rp.)
17 Reng R.33-0.45 M' 10,000.00
18 Baut (Screw Driver) Canal dan Reng Bh 340.00
19 Baut (Screw Driver) Atap 45 Bh 475.00
20 Baut (Screw Driver) Atap 40 Bh 420.00
21 Baut (Screw Driver) Atap 35 Bh 360.00
22 Dynabolt Bh 2,640.00
23 Profil Alluminium 4" (Ex. Alexindo) warna Silver M' 58,000.00
24 Profil Alluminium 3" (Ex. Alexindo) warna Silver M' 50,000.00
25 Profil Alluminium 4" (Ex. Alexindo) warna Hitam/Coklat M' 65,000.00
26 Profil Alluminium 3" (Ex. Alexindo) warna Hitam/Coklat M' 55,000.00
27 Profil Alluminium 4" (Ex. Alexindo) warna Coating Powder M' 76,000.00
28 Profil Alluminium 3" (Ex. Alexindo) warna Coating Powder M' 67,000.00
29 Skrup Fixer Bh 400.00
30 Sealant Tube 31,000.00
31 Karet Kaca M' 2,100.00
32 Sandblash M' 65,000.00
33 Furing Channel Zincalume M' 3,600.00
34 Hollow Zincalume 40x40x400 Btg 34,000.00
35 Hollow Zincalume 20x40x400 Btg 22,000.00
36 Hollow Zincalume 30x30x400 Btg 31,000.00
37 Besi Hollow 1,6x20x40x600 Btg 84,000.00
38 Besi Hollow 1,8x20x40x600 Btg 97,500.00
39 Besi Hollow 1,6x40x40x600 Btg 148,000.00 148,000
40 Besi Hollow 2x40x40x600 Btg 169,470.00 161,400
43 Pintu Folding Gate tebal 0,8 mm M2 600,000.00
44 Pintu Folding Gate tebal 1 mm M2 997,500.00

L BAHAN PELAPIS LANTAI DAN DINDING


1 Keramik Lantai uk. 40 x 40 cm ( ikad ) Kotak 73,500.00 90,000
2 Keramik Lantai uk. 30 x 30 cm (ikad) Kotak 73,500.00 88,000
3 Keramik Lantai uk. 20 x 20 cm (ikad) Kotak 70,350.00 87,000
4 Keramik Lantai uk. 25 x 25 cm (ikad) Kotak 67,000.00 67,000
5 Keramik Dinding uk. 20 x 25 cm Kotak 68,250.00 95,000
6 Keramik Dinding uk. 25 x 40 cm Kotak 95,000.00 95,000
7 Granite uk. 60 x 60 cm Bh 47,439.00 67,500
8 Granit Lantai 40 x 40 cm Bh 34,545.00 28,143
9 Plint kramik 10 x 20 Bh 6,300.00 6,000
10 Plint kramik 10 x 10 Bh 2,835.00 2,700
11 Plint kramik 5 x 20 Bh 5,775.00 5,500
12 Bon-bon kramik m' 5,250.00 5,250
13 Paving Blok Tebal 6 Natural (10 x 20 ) Bh 2,410.00 2,000
14 Paving Blok Tebal 6 Warna (10 x 20 ) Bh 2,600.00 2,400
15 Paving Blok Tebal 8 Natural ( 10 x 20 ) Bh 2,625.00 2,600
16 Paving Blok Tebal 8 Warna ( 10 x 20 ) Bh 2,825.00 3,100
17 Paving Blok Tebal 6 Natural Hexagon Bh 2,625.00 2,100
18 Paving Blok Tebal 6 Warna Hexagon Bh 2,825.00 2,500
19 Paving Blok Tebal 8 Natural Hexagon Bh 2,800.00 2,700
20 Paving Blok Tebal 8 Warna Hexagon Bh 3,150.00 3,200
8 Kaca Tempered Tebal 8 mm M2 715,000.00 715,000.00
9 Kaca Tempered Tebal 12 mm M2 1,100,000.00 1,100,000.00
10 Cat Tembok Weathershield Exterior (dulux) Kg 118,965.00 90,000
12 Cat Melanin (Clear) Kg 57,000.00 57,000
15 Wood Filler Ltr 43,200.00 43,200
16 Sanding Siller Ltr 62,500.00 62,500

Daftar Harga Satuan Upah dan Bahan Jarak Dekat TA. 2017 Hal. 69 dari 73
HARGA
NO URAIAN SATUAN Harga Survey Harga Survey
SATUAN (Rp.)
17 Wood Stain Ltr 60,000.00 60,000
18 Dempul Impra Kg 33,600.00 33,600
4 Aspal 60/70 drum Kg 16,223.00 13,000

Q BAHAN SANITAIR
9 Tangki Air Fibre Kap. 1000 L (Tedmond) Bh 1,330,000.00 1,330,000
11 Pelampung Otomatis 1/2 Bh 100,000.00 100,000
12 Pompa Air Otomatis Bh 500,000.00 500,000

S BETON READY MIX


1 Beton Ready Mix K-175 M3 1,035,000.00 850,000
2 Beton Ready Mix K-200 M3 1,057,500.00 875,000
3 Beton Ready Mix K-225 M3 1,080,000.00 900,000
4 Beton Ready Mix K-250 M3 1,125,000.00 950,000
5 Beton Ready Mix K-275 M3 1,195,000.00 1,000,000
6 Beton Ready Mix K-300 M3 1,265,000.00 1,050,000
7 Concrete Pump / Pengecoran < 30 M3 3,475,000.00 3,475,000
8 Concrete Pump / Pengecoran (Penambahan / m3) > 31 M3 46,250.00 46,250
9 Concrete Pump / Pengecoran < 40 M3 4,000,000.00 4,000,000
10 Concrete Pump / Pengecoran > 40 M3 50,000.00 50,000
11 Sewa Concrete Mixer / Molen Hari 300,000.00 300,000

Daftar Harga Satuan Upah dan Bahan Jarak Dekat TA. 2017 Hal. 70 dari 73
DAFTAR ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
TAHUN ANGGARAN 2013

No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f

I PEKERJAAN BETON (SNI 7394:2008)

1 1 M3 MEMBUAT BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (12 + 2) CM, W/C = 0,87
247.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.6200 M3 Pasir Beton Rp. 182,400.00 Rp. 113,088.00
0.7400 M3 Split Rp. 272,650.00 Rp. 201,761.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

2 1 M3 MEMBUAT BETON MUTU fc' = 9,8 MPa (K 125), SLUMP (12 + 2) CM, W/C = 0,78
276.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.5900 M3 Pasir Beton Rp. 182,400.00 Rp. 107,616.00
0.7500 M3 Kerikil Beton Rp. 272,650.00 Rp. 204,487.50
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

3 1 M3 MEMBUAT BETON MUTU fc' = 12,2 MPa (K 150), SLUMP (12 + 2) CM, W/C = 0,72
299.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.5700 M3 Pasir Beton Rp. 182,400.00 Rp. 103,968.00
0.7500 M3 Kerikil Beton Rp. 272,650.00 Rp. 204,487.50
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

4 1 M3 MEMBUAT BETON MUTU fc' = 14,5 MPa (K 175), SLUMP (12 + 2) CM, W/C = 0,66
326.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.5400 M3 Pasir Beton Rp. 182,400.00 Rp. 98,496.00
0.7600 M3 Kerikil Beton Rp. 272,650.00 Rp. 207,214.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 71 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f

5 1 M3 MEMBUAT BETON MUTU fc' = 16,9 MPa (K 200), SLUMP (12 + 2) CM, W/C = 0,61
352.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.5200 M3 Pasir Beton Rp. 182,400.00 Rp. 94,848.00
0.7600 M3 Kerikil Beton Rp. 272,650.00 Rp. 207,214.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

6 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58
371.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4900 M3 Pasir Beton Rp. 182,400.00 Rp. 89,376.00
0.7700 M3 Kerikil Beton Rp. 272,650.00 Rp. 209,940.50
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

7 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56
384.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4900 M3 Pasir Beton Rp. 182,400.00 Rp. 89,376.00
0.7600 M3 Kerikil Beton Rp. 272,650.00 Rp. 207,214.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

8 1 M3 MEMBUAT BETON MUTU fc' = 24,0 MPa (K 275), SLUMP (12 + 2) CM, W/C = 0,53
406.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4800 M3 Pasir Beton Rp. 182,400.00 Rp. 87,552.00
0.7600 M3 Kerikil Beton Rp. 272,650.00 Rp. 207,214.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

9 1 M3 MEMBUAT BETON MUTU fc' = 26,4 MPa (K 300), SLUMP (12 + 2) CM, W/C = 0,52
413.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4800 M3 Pasir Beton Rp. 182,400.00 Rp. 87,552.00
0.7500 M3 Kerikil Beton Rp. 272,650.00 Rp. 204,487.50

Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 72 dari 73
No URAIAN H. SATUAN UPAH BAHAN JUMLAH

a b c d e f
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

1.6500 Pekerja Rp. 101,000.00 Rp. 166,650.00


0.2750 Tukang Batu Rp. 131,000.00 Rp. 36,025.00
0.0280 Kepala Tukang Rp. 161,000.00 Rp. 4,508.00
0.0830 Mandor Rp. 141,000.00 Rp. 11,703.00
Rp. 218,886.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

10 1 M3 MEMBUAT BETON MUTU fc' = 28,8 MPa (K 325), SLUMP (12 + 2) CM, W/C = 0,49
439.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4700 M3 Pasir Beton Rp. 182,400.00 Rp. 85,728.00
0.7400 M3 Kerikil Beton Rp. 272,650.00 Rp. 201,761.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

2.1000 Pekerja Rp. 101,000.00 Rp. 212,100.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.1050 Mandor Rp. 141,000.00 Rp. 14,805.00
Rp. 278,390.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

11 1 M3 MEMBUAT BETON MUTU fc' = 31,2 MPa (K 350), SLUMP (12 + 2) CM, W/C = 0,48
448.0000 Kg Semen Portland Rp. #REF! Rp. #REF!
0.4700 M3 Pasir Beton Rp. 182,400.00 Rp. 85,728.00
0.7400 M3 Kerikil Beton Rp. 272,650.00 Rp. 201,761.00
215.0000 Ltr Air Rp. 95.00 Rp. 20,425.00
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00

2.1000 Pekerja Rp. 101,000.00 Rp. 212,100.00


0.3500 Tukang Batu Rp. 131,000.00 Rp. 45,850.00
0.0350 Kepala Tukang Rp. 161,000.00 Rp. 5,635.00
0.1050 Mandor Rp. 141,000.00 Rp. 14,805.00
Rp. 278,390.00 Rp. #REF! Rp. #REF!
Overhead 5% Rp. #REF!
Jumlah Rp. #REF!
Dibulatkan Rp. #REF!

Solok, Januari 2013


Kepala Dinas Pekerjaan Umum Kabid Cipta Karya Kabid Bina Program dan Pengawasan
Kota Solok Dinas Pekerjaan Umum Kota Solok Dinas Pekerjaan Umum Kota Solok

Ir. Ardy Syafwan Warfendi Boy, S.T. Ir. Nofi Hendri, M.T.
NIP. 19570513 198901 1 001 NIP. 19570831 198103 1 003 NIP. 19661115 199308 1 001

Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 73 dari 73

Anda mungkin juga menyukai