1 2 3 4 5
I UPAH
1 Pekerja Hari 110,000.00
2 Mandor Hari 145,000.00
3 Kepala Tukang Hari 145,000.00
4 Tukang Kayu Hari 130,000.00
5 Tukang Batu Hari 130,000.00
6 Tukang Cat Hari 130,000.00
8 Tukang Besi Hari 130,000.00
II BAHAN
A BAHAN BATU KALI BELAH / BATU PECAH
1 Batu Belah 15/20 / Batu Gunung M3 140,000.00
C BAHAN PASIR
1 Pasir Pasang M3 160,150.00
2 Pasir Beton M3 165,000.00
4 Cadas M3 52,400.00
6 Sirtu M3 123,300.00
E BAHAN SEMEN
2 Semen Portland (PCC) Kg 1,290.00
F BAHAN KAYU
1 Kayu Papan Klas III M3 2,200,000.00 62.50
2 Kayu Balok Klas III M3 2,200,000.00
3 Kayu Papan Klas IV M3 1,900,000.00
4 Kayu Bekisting M3 1,900,000.00
5 Dolken Kayu Galam dia. 8-10/4 m Btg 12,930.00
G BAHAN PAKU
1 Paku Biasa 1/2"-5" Kg 20,000.00
2 Paku Triplek Kg 21,000.00
H BAHAN PIPA
I BAHAN PLAFOND
2 Multiplek Tebal 9 mm Lbr 125,500.00
III PERALATAN
9 Sewa Concrete Mixer / Molen Hari 200,000.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
DINAS PERUMAHAN DAN KAWASAN PERMUKIMAN KOTA SOLOK
TAHUN ANGGARAN 2021
II PEKERJAAN TANAH
V PEKERJAAN PLESTERAN
4 1 M2 PEMASANGAN PLESTERAN 1 PC : 4 PP, TEBAL 15 mm
6.2400 Kg Semen Portland (PCC) Rp. 1,290.00 Rp. 8,049.60
0.0240 M3 Pasir Pasang Rp. 160,150.00 Rp. 3,843.60
18 1 M2 PEMASANGAN ACIAN
3.2500 Kg Semen Portland (PCC) Rp. 1,290.00 Rp. 4,192.50
18 1 M2 PEMASANGAN BEKISTING UNTUK SLOOF, KOLOM PRAKTIS, BALOK PRAKTIS, PET BETON
0.0450 M3 Kayu Klas III Rp. 2,200,000.00 Rp. 99,000.00
0.3000 Kg Paku 5 cm - 10 cm Rp. 20,000.00 Rp. 6,000.00
0.1000 Lt Minyak Bekisting Rp. 2,500.00 Rp. 250.00
1 2 3 4
II PEKERJAAN TANAH
1 Penggalian Tanah Biasa Sedalam 1 Meter M3 94,737.00
2 Penggalian Tanah Biasa Sedalam 2 Meter M3 116,077.00
3 Penggalian Tanah Biasa Sedalam 3 Meter M3 137,736.00
4 Penggalian Tanah Keras Sedalam 1 Meter M3 126,104.00
5 Penggalian Tanah Cadas Sedalam 1 Meter M3 191,070.00
6 Penggalian Tanah Lumpur Sedalam 1 Meter M3 152,377.00
7 Pengerjaan Stripping Tebing Setinggi 1 Meter M3 6,847.00
8 Pembuangan Tanah Sejauh 30 Meter M3 41,525.00
9 Pengurungan Kembali Galian Tanah M3 68,475.00
10 Pemadatan Tanah (Per 20 cm) M3 68,475.00
11 Pengurugan dengan Pasir Urug M3 218,867.00
12 Pengurugan Sirtu Padat M3 196,993.00
13 Pengurugan Cadas Padat M3 107,063.00
Campuran Spesi 1 Pc : 4 Pp
NO URAIAN SATUAN HARGA SATUAN (Rp.)
9 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1/2 Batu M2 137,850.00
Campuran Spesi 1 Pc : 5 Pp
10 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1/2 Batu M2 136,625.00
Campuran Spesi 1 Pc : 6 Pp
11 Pemasangan Dinding Conblock HB15, Campuran Spesi 1 Pc : 3 Pp M2 223,604.00
12 Pemasangan Dinding Conblock HB15, Campuran Spesi 1 Pc : 4 Pp M2 222,799.00
13 Pemasangan Dinding Conblock HB10, Campuran Spesi 1 Pc : 3 Pp M2 171,573.00
14 Pemasangan Dinding Conblock HB10, Campuran Spesi 1 Pc : 4 Pp M2 171,501.00
15 Pemasangan Dinding Terawang (Roster) Ukuran 12x11x24 cm M2 353,033.00
Campuran Spesi 1 Pc : 3 Pp
16 Pemasangan Dinding Terawang (Roster) Ukuran 12x11x24 cm M2 353,562.00
Campuran Spesi 1 Pc : 4 Pp
17 Pemasangan Dinding Batako, Campuran Spesi 1 Pc : 4 Pp M2 135,241.00
V PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1 Pc : 1 Pp, Tebal 15 mm M2 87,353.00
2 Pemasangan Plesteran 1 Pc : 2 Pp, Tebal 15 mm M2 80,566.00
3 Pemasangan Plesteran 1 Pc : 3 Pp, Tebal 15 mm M2 77,620.00
4 Pemasangan Plesteran 1 Pc : 4 Pp, Tebal 15 mm M2 75,617.00
5 Pemasangan Plesteran 1 Pc : 5 Pp, Tebal 15 mm M2 74,471.00
6 Pemasangan Plesteran 1 Pc : 6 Pp, Tebal 15 mm M2 73,557.00
7 Pemasangan Plesteran 1 Pc : 2 Pp, Tebal 20 mm M2 107,799.00
8 Pemasangan Plesteran 1 Pc : 3 Pp, Tebal 20 mm M2 103,872.00
9 Pemasangan Plesteran 1 Pc : 4 Pp, Tebal 20 mm M2 101,142.00
10 Pemasangan Plesteran 1 Pc : 5 Pp, Tebal 20 mm M2 99,672.00
11 Pemasangan Plesteran 1 Pc : 6 Pp, Tebal 20 mm M2 98,396.00
12 Pemasangan Berapen 1 Pc : 5 Pp, Tebal 15 mm M2 43,363.00
13 Pemasangan Plesteran Skoning 1 Pc : 2 Pp, Lebar 10 mm M 76,897.00
14 Pemasangan Plesteran Ciprat 1 Pc : 2 Pp M2 61,774.00
15 Pemasangan Finishing Siar Pemasanganan Dinding Bata Merah M2 35,837.00
16 Pemasangan Finishing Siar Pemasanganan Dinding Conblock Ekspose M2 17,021.00
17 Pemasangan Finishing Siar Pemasanganan Batu Kali Campuran 1 Pc : 2 Pp M2 73,645.00
18 Pemasangan Acian M2 46,301.00
VI PEKERJAAN KAYU
1 Pembuatan dan Pemasangan Kuzen Pintu dan Jendela, Kayu Klas I M3 8,764,745.00
2 Pembuatan dan Pemasangan Kuzen Pintu dan Jendela, Kayu Klas II M3 7,443,920.00
3 Pembuatan dan Pemasangan Pintu Klamp Standar. Kayu Klas II M2 336,418.00
4 Pembuatan dan Pemasangan Pintu Klamp Sederhana. Kayu Klas III M2 310,018.00
5 Pembuatan dan Pemasangan Daun Pintu Panel, Kayu Klas I M2 780,560.00
6 Pembuatan dan Pemasangan Daun Pintu Panel, Kayu Klas II M2 738,760.00
7 Pembuatan dan Pemasangan Pintu dan Jendela Kaca, Kayu Klas I M2 589,501.00
8 Pembuatan dan Pemasangan Pintu dan Jendela Kaca, Kayu Klas II M2 564,421.00
9 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi, Kayu Klas I M2 879,560.00
10 Pembuatan dan Pemasangan Pintu dan Jendela Jalusi, Kayu Klas II M2 812,680.00
11 Pembuatan Daun Pintu Kayu Lapis (Plywood) Rangkap, M2 587,372.00
Rangka Tertutup Kayu Klas II (Lebar Sampai 90 cm)
12 Pembuatan Pintu Plywood Rangkap, Rangka Expose Kayu Klas I M2 676,555.00
13 Pembuatan Pintu Plywood Rangkap, Rangka Expose Kayu Klas II M2 649,803.00
14 Pemasangan Jalusi Kuzen, Kayu Klas I M2 703,202.00
15 Pemasangan Jalusi Kuzen, Kayu Klas II M2 640,502.00
16 Pemasangan Teakwood Rangkap, Rangka Expose Kayu Klas I M2 726,286.00
17 Pemasangan Teakwood Rangkap Lapis Formika, Rangka Expose Kayu Klas II M2 787,017.00
18 Pemasangan Konstruksi Kuda-Kuda Konvensional, Kayu Klas I Bentang 6 M M3 7,261,100.00
NO URAIAN SATUAN HARGA SATUAN (Rp.)
II PEKERJAAN PASANGAN
1 Bongkar Pasnagan Batu dan Pembersihan Batu (Manual) M3 204,006.00
2 Bongkar Pemasanganan Batu (Manual) M3 174,262.00
3 Bongkar Pemasanganan Batu dengan Jack Hammer M3 95,920.00
4 Membersihkan Bongkaran Pemasanganan Batu untuk Pemanfaatan Kembali Material Batu M3 29,744.00
7 Beton Mutu fc' = 16,9 MPa (K200), Slump (12+2) CM, w/c=0.61
a. Manual M3 986,624.00
b. Menggunakan Molen M3 995,106.00
8 Beton Mutu fc' = 19,3 MPa (K225), Slump (12+2) CM, w/c=0.58
a. Manual M3 1,092,412.00
b. Menggunakan Molen M3 1,098,825.00
9 Beton Mutu fc' = 21,7 MPa (K250) Kedap Air, Slump (12+2) CM, w/c=0.56
a. Manual M3 1,108,432.00
b. Menggunakan Molen M3 1,114,489.00
10 Beton Mutu fc' = 24,0 MPa (K275) Kedap Air, Slump (12+2) CM, w/c=0.53
a. Manual M3 1,135,933.00
b. Menggunakan Molen M3 1,143,892.00
11 Beton Mutu fc' = 26,4 MPa (K300) Kedap Air, Slump (12+2) CM, w/c=0.52 (Kedap Air)
a. Manual M3 1,144,446.00
b. Menggunakan Molen M3 1,151,042.00
12 Beton Mutu fc' = 28,8 MPa (K325) Kedap Air, Slump (12+2) CM, w/c=0.49 (Kedap Air)
a. Manual M3 1,246,623.00
b. Menggunakan Molen M3 1,243,367.00
13 Beton Mutu fc' = 31,2 MPa (K350) Kedap Air, Slump (12+2) CM, w/c=0.48 (Kedap Air)
a. Manual M3 1,257,768.00
b. Menggunakan Molen M3 1,254,512.00
14 Beton Menggunakan Ready Mixed K225 M3 1,646,507.00
JUSMARDI, S.Pd
NIP. 19641211 198910 1 002
DAFTAR ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
TAHUN ANGGARAN 2013
a b c d e f
1 1 M3 MEMBUAT BETON MUTU fc' = 7,4 MPa (K 100), SLUMP (12 + 2) CM, W/C = 0,87
247.0000 Kg Semen Portland Rp. 1,350.00 Rp. 333,450.00
0.6200 M3 Pasir Beton Rp. 165,000.00 Rp. 102,300.00
0.7400 M3 Split Rp. 253,000.00 Rp. 187,220.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
2 1 M3 MEMBUAT BETON MUTU fc' = 9,8 MPa (K 125), SLUMP (12 + 2) CM, W/C = 0,78
276.0000 Kg Semen Portland Rp. 1,350.00 Rp. 372,600.00
0.5900 M3 Pasir Beton Rp. 165,000.00 Rp. 97,350.00
0.7500 M3 Kerikil Beton Rp. 253,000.00 Rp. 189,750.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
3 1 M3 MEMBUAT BETON MUTU fc' = 12,2 MPa (K 150), SLUMP (12 + 2) CM, W/C = 0,72
299.0000 Kg Semen Portland Rp. 1,350.00 Rp. 403,650.00
0.5700 M3 Pasir Beton Rp. 165,000.00 Rp. 94,050.00
0.7500 M3 Kerikil Beton Rp. 253,000.00 Rp. 189,750.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
4 1 M3 MEMBUAT BETON MUTU fc' = 14,5 MPa (K 175), SLUMP (12 + 2) CM, W/C = 0,66
326.0000 Kg Semen Portland Rp. 1,350.00 Rp. 440,100.00
0.5400 M3 Pasir Beton Rp. 165,000.00 Rp. 89,100.00
0.7600 M3 Kerikil Beton Rp. 253,000.00 Rp. 192,280.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 14 dari 29
No URAIAN H. SATUAN UPAH BAHAN JUMLAH
a b c d e f
5 1 M3 MEMBUAT BETON MUTU fc' = 16,9 MPa (K 200), SLUMP (12 + 2) CM, W/C = 0,61
352.0000 Kg Semen Portland Rp. 1,350.00 Rp. 475,200.00
0.5200 M3 Pasir Beton Rp. 165,000.00 Rp. 85,800.00
0.7600 M3 Kerikil Beton Rp. 253,000.00 Rp. 192,280.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
6 1 M3 MEMBUAT BETON MUTU fc' = 19,3 MPa (K 225), SLUMP (12 + 2) CM, W/C = 0,58
371.0000 Kg Semen Portland Rp. 1,350.00 Rp. 500,850.00
0.4900 M3 Pasir Beton Rp. 165,000.00 Rp. 80,850.00
0.7700 M3 Kerikil Beton Rp. 253,000.00 Rp. 194,810.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
7 1 M3 MEMBUAT BETON MUTU fc' = 21,7 MPa (K 250), SLUMP (12 + 2) CM, W/C = 0,56
384.0000 Kg Semen Portland Rp. 1,350.00 Rp. 518,400.00
0.4900 M3 Pasir Beton Rp. 165,000.00 Rp. 80,850.00
0.7600 M3 Kerikil Beton Rp. 253,000.00 Rp. 192,280.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
8 1 M3 MEMBUAT BETON MUTU fc' = 24,0 MPa (K 275), SLUMP (12 + 2) CM, W/C = 0,53
406.0000 Kg Semen Portland Rp. 1,350.00 Rp. 548,100.00
0.4800 M3 Pasir Beton Rp. 165,000.00 Rp. 79,200.00
0.7600 M3 Kerikil Beton Rp. 253,000.00 Rp. 192,280.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
9 1 M3 MEMBUAT BETON MUTU fc' = 26,4 MPa (K 300), SLUMP (12 + 2) CM, W/C = 0,52
413.0000 Kg Semen Portland Rp. 1,350.00 Rp. 557,550.00
0.4800 M3 Pasir Beton Rp. 165,000.00 Rp. 79,200.00
0.7500 M3 Kerikil Beton Rp. 253,000.00 Rp. 189,750.00
Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 15 dari 29
No URAIAN H. SATUAN UPAH BAHAN JUMLAH
a b c d e f
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
10 1 M3 MEMBUAT BETON MUTU fc' = 28,8 MPa (K 325), SLUMP (12 + 2) CM, W/C = 0,49
439.0000 Kg Semen Portland Rp. 1,350.00 Rp. 592,650.00
0.4700 M3 Pasir Beton Rp. 165,000.00 Rp. 77,550.00
0.7400 M3 Kerikil Beton Rp. 253,000.00 Rp. 187,220.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
11 1 M3 MEMBUAT BETON MUTU fc' = 31,2 MPa (K 350), SLUMP (12 + 2) CM, W/C = 0,48
448.0000 Kg Semen Portland Rp. 1,350.00 Rp. 604,800.00
0.4700 M3 Pasir Beton Rp. 165,000.00 Rp. 77,550.00
0.7400 M3 Kerikil Beton Rp. 253,000.00 Rp. 187,220.00
215.0000 Ltr Air Rp. 12.50 Rp. 2,687.50
1.0000 Ls Sewa Pompa Rp. 41,000.00 Rp. 41,000.00
Ir. Ardy Syafwan Warfendi Boy, S.T. Ir. Nofi Hendri, M.T.
NIP. 19570513 198901 1 001 NIP. 19570831 198103 1 003 NIP. 19661115 199308 1 001
Daftar Analisa Harga Satuan Pekerjaan Konstruksi Kota Solok Tahun 2012 Hal. 16 dari 29
Rencana Anggaran Biaya (RAB)
REKAPITULASI
JUMLAH
NO URAIAN PEKERJAAN HARGA
( Rp )
a b c
A Biaya Umum
I Biaya K3 Konstruksi 3,987,500.00
B Pekerjaan Jalan Lingkungan
I Pekerjaan Pendahuluan 685,358.61
II Pekerjaan Jalan 220,611,006.15
C Pekerjaan Saluran
I Pekerjaan Pendahuluan 7,471,747.28
II Pekerjaan Drainase 449,058,065.30
Jumlah Pekerjaan 681,813,677.34
Ppn 10% 68,181,367.73
Jumlah Total 749,995,045.08
Dibulatkan 749,995,000.00
Terbilang : Tujuh Ratus Empat Puluh Sembilan Juta Sembilan Ratus Sembilan Puluh Lima Ribu Rupiah
Diketahui Oleh
Kepala Dinas
Dinas Perumahan dan Kawasan Permukiman
JUSMARDI, S.Pd
Nip. 19641211 198910 1 002
RENCANA ANGGARAN BIAYA
HARGA JUMLAH
NO URAIAN PEKERJAAN STN VOLUME SATUAN HARGA
( Rp ) ( Rp )
a b c d e f
A Biaya Umum
I Biaya K3 Konstruksi Ls 1.00 3,987,500.00 3,987,500.00
Jumlah 3,987,500.00
B Pekerjaan Jalan Lingkungan
I Pekerjaan Pendahuluan
1 Pembersihan Lapangan dan Perataan M² 83.41 8,217.00 685,358.61
Jumlah 685,358.61
II Pekerjaan Jalan
1 Pas. Bekisting Jalan M² 117.76 160,231.00 18,869,276.84
2 Pas. Plastik Cor M² 606.19 3,500.00 2,121,673.93
Pek. Cor Jalan Beton Mutu K-225, t = 20cm (Ready
3 Mix) M³ 121.24 1,646,507.00 199,620,055.38
Jumlah 220,611,006.15
C Pekerjaan Saluran
I Pekerjaan Pendahuluan
1 Pek. Bowplank M¹ 46.80 68,678.00 3,214,130.40
2 Pek. Pembongkaran Saluran Lama M³ 9.36 173,767.00 1,626,459.12
3 Pek. Pembongkaran Pelat Beton M³ 4.54 579,040.00 2,631,157.76
Jumlah 7,471,747.28
II Pekerjaan Drainase
1 Pek. Galian Tanah M³ 281.00 94,737.00 26,621,097.00
2 Pasangan Batu kali ad 1:4 M³ 228.76 820,377.00 187,669,442.52
3 Pek. Plesteran ad 1:4 M² 772.10 75,617.00 58,383,885.70
4 Pek. Acian M² 772.10 46,301.00 35,749,002.10
5 Pek. Saluran Tertutup (Beton Bertulang)
Bekisting Dinding M² 98.40 160,231.00 15,766,730.40
Bekisting Plat (Floordeck t=7 mm) M² 13.94 176,957.00 2,466,780.58
Pembesian Kg 1,144.49 16,790.00 19,216,025.73
Pek. Beton Mutu K-225, (Ready Mix) M³ 15.20 1,646,507.00 25,031,516.62
6 Pek. Pelat Duiker
Bekisting Plat (Floordeck t=7 mm) M² 87.00 176,957.00 15,395,259.00
Pembesian Kg 1,733.71 16,790.00 29,108,932.20
Pek. Beton Mutu K-225, t = 15cm (Ready Mix) M³ 13.35 1,646,507.00 21,980,868.45
7 Pek. Pembuangan Hasil Galian M³ 281.00 41,525.00 11,668,525.00
Jumlah 449,058,065.30
Jumlah Total Pekerjaan 681,813,677.34
A Biaya Umum
I Biaya K3 Konstruksi
1 Helm Buah 9.00 40,000.00 360,000.00
2 Rompi Buah 9.00 30,000.00 270,000.00
3 Sepatu Pasang 9.00 110,000.00 990,000.00
4 Sarung Tangan Pasang 9.00 2,500.00 22,500.00
5 Masker Buah 9.00 5,000.00 45,000.00
6 Kaca Mata Pelindung Buah 4.00 30,000.00 120,000.00
7 Kotak P3K Buah 1.00 100,000.00 100,000.00
II Petugas K3
1 Personil K3 dan Laporan RK3K Ls 1.00 1,980,000.00 1,980,000.00
III Rambu Rambu
1 Rambu Rambu Peringatan Ls 1.00 100,000.00 100,000.00
Jumlah 3,987,500.00
PERHITUNGAN VOLUME PEKERJAAN
II Pekerjaan Jalan
4 Pas. Bekisting Jalan Lihat Lampiran Tabel Volume Jalan 117.76 M²
5 Pas. Plastik Cor Lihat Lampiran Tabel Volume Jalan 606.19 M²
6 Pek. Cor Jalan Beton Mutu K-225, t = 20cm (Read Lihat Lampiran Tabel Volume Jalan 121.24 M³
C Pekerjaan Saluran
Pekerjaan Pendahuluan
1 Pek. Bowplank P : 10.00 x 1.00 46.80 M¹
468.00 : 10.00 x 1.00 = 46.80
> Ruas 2
Sta, 0,00 s/d Sta, 25.00 25.00 2.00 1.00 1.50 37.50 6.00 6.00 6.00 - 0.20 30.00 0.20 2 10.00 150.00
Sta, 25.00 s/d Sta, 50.00 25.00 1.00 1.00 1.00 25.00 6.00 5.50 5.75 - 0.20 28.75 0.20 2 10.00 143.75
Sta, 50.00 s/d Sta, 63.41 13.41 1.00 1.00 1.00 13.41 5.50 6.00 5.75 - 0.20 15.42 0.20 2 5.36 77.09
> Ruas 3
Sta, 0,00 s/d Sta, 25.00 25.00 0.60 - 0.30 7.50 4.35 4.00 4.18 - 0.20 20.88 0.20 2 10.00 104.38
Sta, 25.00 s/d Sta, 56.00 31.00 - - - - 4.00 4.45 4.23 - 0.20 26.20 0.20 2 12.40 130.98
1 > Ruas 1
Sta, 0,00 s/d Sta, 25.00 25.00 0.75 1.40 53.75
Sta, 25.00 s/d Sta, 175.00 150.00 1.30 0.80 156.00 1.30 0.20 0.25 0.40 0.60 2.00 97.50 0.90 1.20 315.00
2 > Ruas 2
Sta, 0,00 s/d Sta, 39.00 39.00 1.00 0.60 23.40 1.00 0.20 0.25 0.35 0.50 2.00 19.50 0.55 1.00 60.45
3 > Ruas 3
Kiri
Sta, 0,00 s/d Sta, 25.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 25.00 s/d Sta, 56.00 31.00 1.00 0.40 12.40 1.00 0.20 0.25 0.35 0.40 2.00 13.64 0.55 0.80 41.85
Sta, 75.00 s/d Sta, 100.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 100.00 s/d Sta, 119.00 19.00 1.00 0.40 7.60 1.00 0.20 0.25 0.35 0.40 2.00 8.36 0.55 0.80 25.65
Kanan
Sta, 0,00 s/d Sta, 25.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 25.00 s/d Sta, 50.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 50.00 s/d Sta, 75.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 75.00 s/d Sta, 100.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 100.00 s/d Sta, 125.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 125.00 s/d Sta, 150.00 25.00 1.00 0.40 10.00 1.00 0.20 0.25 0.35 0.40 2.00 11.00 0.55 0.80 33.75
Sta, 150.00 s/d Sta, 154.00 4.00 1.00 0.40 1.60 1.00 0.20 0.25 0.35 0.40 2.00 1.76 0.55 0.80 5.40
ket Kolom
a Nomor l Jumlah Panjang besi total arah memanjang
b Type pelat yang di kerjakan 2 x ((d - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
c Jumlah dalam pekerjaan m Jarak Pembesian arah memanjang
d Panjang pelat n Jumlah besi dalam arah memanjang
e Lebar pelat yang di cor (e / m) + 1
f Tinggi Pelat yang di cor o Diameter besi arah melintang
g Volume Cor Beton p Berat Besi "o" per meter
exfxdxc q Jumlah Panjang besi total arah melintang
h Lebar Bersih bekisting 2 x ((e - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
e - 0,25 - 0,25 r Jarak Pembesian arah melintang
i Volume Bekisting (d / m) + 1
hxdxc s Jumlah besi dalam arah melintang
j Diameter besi arah memanjang t
Total Volume berat besi arah memanjang dan arah melintang
k Berat Besi "j" per meter
((k x l x n)+(p x q x s)) x c
Tabel Saluran Beton Bertulang
ket Kolom
a Nomor l Jumlah Panjang besi total arah memanjang
b Type pelat yang di kerjakan 2 x ((d - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
c Jumlah dalam pekerjaan m Jarak Pembesian arah memanjang
d Panjang pelat n Jumlah besi dalam arah memanjang
e Lebar pelat yang di cor (e / m) + 1
f Tinggi Pelat yang di cor o Diameter besi arah melintang
g Volume Cor Beton p Berat Besi "o" per meter
exfxdxc q Jumlah Panjang besi total arah melintang
h Lebar Bersih bekisting 2 x ((e - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
e - 0,25 - 0,25 r Jarak Pembesian arah melintang
i Volume Bekisting (d / m) + 1
hxdxc s Jumlah besi dalam arah melintang
j Diameter besi arah memanjang t
Total Volume berat besi arah memanjang dan arah melintang
k Berat Besi "j" per meter
((k x l x n)+(p x q x s)) x c
Tabel Pelat Duiker
1 Type 3 9 3.00 1.00 0.15 4.05 1.00 27.00 12.00 0.888 5.99 0.20 6.00 12.00 0.888 2.08 0.20 15.00 536.44 -
2 Type 4 11 4.00 1.00 0.15 6.60 1.00 44.00 12.00 0.888 7.99 0.20 6.00 12.00 0.888 2.08 0.20 20.00 874.39 - 6
3 Type 5 2 5.00 1.00 0.15 1.50 1.00 10.00 12.00 0.888 9.99 0.20 6.00 12.00 0.888 2.08 0.20 25.00 198.75 -
4 Type 6 1 6.00 1.00 0.20 1.20 1.00 6.00 12.00 0.888 12.04 0.20 6.00 12.00 0.888 2.18 0.20 31.00 124.13 -
ket Kolom
a Nomor l Jumlah Panjang besi total arah memanjang
b Type pelat yang di kerjakan 2 x ((d - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
c Jumlah dalam pekerjaan m Jarak Pembesian arah memanjang
d Panjang pelat n Jumlah besi dalam arah memanjang
e Lebar pelat yang di cor (e / m) + 1
f Tinggi Pelat yang di cor o Diameter besi arah melintang
g Volume Cor Beton p Berat Besi "o" per meter
exfxdxc q Jumlah Panjang besi total arah melintang
h Lebar Bersih bekisting 2 x ((e - 0,05 - 0,05)+(f - 0,03 - 0,03)) + 0,05 + 0,05
e - 0,25 - 0,25 r Jarak Pembesian arah melintang
i Volume Bekisting (d / m) + 1
hxdxc s Jumlah besi dalam arah melintang
j Diameter besi arah memanjang t
Total Volume berat besi arah memanjang dan arah melintang
k Berat Besi "j" per meter
((k x l x n)+(p x q x s)) x c
Tabel Perhitungan Tembok Penahan Jalan
1 > Ruas 4
Sta, 0,00 s/d Sta, 12.10 - 0.50 0.64 - 0.50 0.20 0.15 0.40 0.70 1.00 -
Jumlah - - - -
Tabel Perhitungan Saluran Gendong
Jumlah - - - -
TIME SCHEDULE
A - 100%
I Biaya K3 Konstruksi 0.585 0.585
II Pekerjaan Jalan 32.356 4.622 4.622 4.622 4.622 4.622 4.622 4.622
C Pekerjaan Saluran
I Pekerjaan Pendahuluan 1.096 0.183 0.183 0.183 0.183 0.183 0.183 0%
Jumlah (%) 34.138 0.686 4.622 4.622 4.805 4.805 4.805 4.805 4.805 0.183
Rencana
Kumulatif (%) - 0.686 5.308 9.931 14.736 19.540 24.345 29.150 33.955 34.138
Jumlah (%)
Realisasi
Jumlah (%)
Deviasi
Solok,
Juni 2021
Dibuat Oleh
Konsultan Perencana
PT. Multikarya Interplan Konsultan