DAFTAR HARGA SATUAN BAHAN DAN UPAH

KEC. TULUNG SELAPAN KAB. OKI

NO. SATUAN HARGA

I. UPAH

1 Pekerja Orang/hari 62,400.00


2 Mandor Orang/hari 119,600.00
3 Kepala Tukang Orang/hari 109,590.00
4 Tukang Kayu/batu Orang/hari 99,580.00

II. BAHAN BANGUNAN


1 Air ltr 200.00
2 Alat bantu set 100,000.00
3 Aspal Bitumen Kg 17,550.00
4 Batu pecah 2-3 (split) M3 548,375.00
5 Batu pecah 5-7 (split) M3 564,125.00
6 Batu Kali M3 570,000.00
7 Batu bata merah uk. 8 x 8 x 16 cm Bh 850.00
8 Batu bata bolong Bh 1,150.00
9 Batu krokos/gravel M3 490,875.00
10 Besi beton polos 8 mm Kg 26,500.00
11 Kayu dolken dia. 8-10/4m Btg 15,200.00
12 Kayu papan kelas II M3 3,650,000.00
13 Kayu papan kelas III M3 2,950,000.00
14 Kayu papan kelas IV M3 2,100,000.00
15 Kayu balok kelas IV M3 2,115,000.00
16 Kawat ikat beton Kg 24,850.00
17 Kawat bronjong 4 mm Kg 27,500.00
18 Koral cor M3 550,000.00
19 Koral cor Kg 1,100.00
20 Minyak aspal Liter 4,550.00
21 Minyak pengencer Liter 6,750.00
22 Plastik cor M2 4,000.00
23 Pasir beton M3 145,000.00
24 Pasir beton Kg 96.67
25 Pasir Urug M3 135,000.00
26 Paku beton Kg 22,000.00
27 Plywood 4 mm M2 31,000.00
28 Plywood 4 mm Lembar 62,000.00
29 Plywood 6 mm M2 55,000.00
30 Plywood 6 mm Lembar 110,000.00
31 Plywood 9 mm M2 72,750.00
32 Plywood 9 mm Lembar 145,500.00
33 Semen portland (PC) / 50 kg Zak 88,600.00
34 Semen portland (PC) Kg 1,772.00
35 Tanah timbunan biasa M3 165,000.00
36 Tanah timbunan pilihan M3 165,000.00
DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

PEKERJAAN PERSIAPAN
DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE
PROVINSI SUMATERA SELATAN 1M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN TANAH 1

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.100 1 0.100 62,400.000 6,240.000


2 Mandor 0.050 1 0.050 119,600.000 5,980.000
PEKERJA 12,220.000
SUB TOTAL 12,220.000
OVER HEAD+PROFIT (15%) 1,833.000
TOTAL 14,053.000

VOLUME / QUANTITY 1.00 SATUAN M2 HARGA SATUAN (Rp.) 14,053.000

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PENGUKURAN DAN PEMASANGAN BOUWPLANK 1.1

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.100 1 0.100 62,400.000 6,240.000


2 Mandor 0.050 1 0.050 119,600.000 5,980.000
PEKERJA 12,220.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Kayu Balok IV 0.012 M3 2,115,000.000 25,380.000


2 Kayu Papan IV 0.007 M3 2,100,000.000 14,700.000
3 Paku Biasa 0.020 Kg 22,000.000 440.000
MATERIAL 40,520.000
SUB TOTAL 52,740.000
OVER HEAD+PROFIT (15%) 7,911.000
TOTAL 60,651.000

VOLUME / QUANTITY 1.00 SATUAN M' HARGA SATUAN (Rp.) 60,651.000

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PEMASANGAN CERUCUK GELAM DIA. 6-8 1.2

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.100 1 0.100 62,400.000 6,240.000


2 Mandor 0.005 1 0.005 119,600.000 598.000
PEKERJA 6,838.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Gelam (dia.8-10) 3.000 Btg 15,200.000 45,600.000


MATERIAL 45,600.000
SUB TOTAL 52,438.000
OVER HEAD+PROFIT (15%) 7,865.700
TOTAL 60,303.700

VOLUME / QUANTITY 1.00 SATUAN M' HARGA SATUAN (Rp.) 60,303.700


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN BEKISTING KAYU CETAKAN ( 10 M2 ) 1.3

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.150 1 0.150 62,400.000 9,360.000


2 Tukang Kayu 0.100 1 0.100 99,580.000 9,958.000
3 Mandor 0.003 1 0.003 119,600.000 358.800
PEKERJA 19,676.800
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Paku 0.200 Kg 22,000.000 4,400.000


2 Papan Kelas IV 0.008 M3 2,100,000.000 16,800.000
3 Gelam dia. 8-10 3.000 Btg 15,200.000 45,600.000
4 Minyak Bekisting 0.200 Ltr 6,750.000 1,350.000

MATERIAL 68,150.000
SUB TOTAL 87,826.800
OVER HEAD+PROFIT (15%) 13,174.020
TOTAL 101,000.820

VOLUME / QUANTITY 10.00 SATUAN M2 HARGA SATUAN (Rp.) 10,100.082

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN BEKISTING CETAKAN PLAT BETON (M3) 1.4

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 62,400.000 18,720.000


2 Tukang Kayu 0.330 1 0.330 99,580.000 32,861.400
3 Mandor 0.100 1 0.100 119,600.000 11,960.000
PEKERJA 63,541.400
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Paku 0.400 Kg 22,000.000 8,800.000


2 Gelam 1.000 btg 15,200.000 15,200.000
3 Papan Kelas IV 0.040 M3 2,100,000.000 84,000.000
4 Minyak Bekisting 0.200 Ltr 6,750.000 1,350.000

MATERIAL 109,350.000
SUB TOTAL 172,891.400
OVER HEAD+PROFIT (15%) 25,933.710
TOTAL 198,825.110

VOLUME / QUANTITY 1.00 SATUAN M2 HARGA SATUAN (Rp.) 198,825.110

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN GALIAN TANAH BIASA ( DALAM 1 M ) 1.5

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.400 1 0.400 62,400.000 24,960.000


2 Mandor 0.040 1 0.040 119,600.000 4,784.000
PEKERJA 29,744.000
SUB TOTAL 29,744.000
OVER HEAD+PROFIT (15%) 4,461.600
TOTAL 34,205.600

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 34,205.600


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN GALIAN TANAH KERAS ( DALAM 1 M ) 1.6

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.000 1 1.000 62,400.000 62,400.000


2 Mandor 0.032 1 0.032 119,600.000 3,827.200
PEKERJA 66,227.200
SUB TOTAL 66,227.200
OVER HEAD+PROFIT (15%) 9,934.080
TOTAL 76,161.280

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 76,161.280

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN URUGAN / PERATAAN DAN PEMADATAN TANAH 1.7

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.500 1 0.500 62,400.000 31,200.000


2 Mandor 0.050 1 0.050 119,600.000 5,980.000
PEKERJA 37,180.000
SUB TOTAL 37,180.000
OVER HEAD+PROFIT (15%) 5,577.000
TOTAL 42,757.000

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 42,757.000

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PEKERJAAN STRIPING TANAH TEBING 1M2 ( SETINGGI 1 METER) 1.8

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.050 1 0.050 62,400.000 3,120.000


2 Mandor 0.005 1 0.005 119,600.000 598.000
PEKERJA 3,718.000
SUB TOTAL 3,718.000
OVER HEAD+PROFIT (15%) 557.700
TOTAL 4,275.700

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 4,275.700


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PEMBONGKARAN EXISTING 1.9

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 2.000 1 2.000 62,400.000 124,800.000


2 Mandor 0.100 1 0.100 119,600.000 11,960.000
PEKERJA 136,760.000
SUB TOTAL 136,760.000
OVER HEAD+PROFIT (15%) 20,514.000
TOTAL 157,274.000

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 157,274.000

PEKERJAAN KONSTRUKSI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN URUGAN PASIR DI PADATKAN 2

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 62,400.000 18,720.000


2 Mandor 0.010 1 0.010 119,600.000 1,196.000
PEKERJA 19,916.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Pasir Urug 1.200 M3 135,000.000 162,000.000


MATERIAL 162,000.000
SUB TOTAL 181,916.000
OVER HEAD+PROFIT (15%) 27,287.400
TOTAL 209,203.400

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 209,203.400

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN URUGAN KROKOS DI PADATKAN 2.1

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 62,400.000 18,720.000


2 Mandor 0.010 1 0.010 119,600.000 1,196.000
PEKERJA 19,916.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Koral 1.200 M3 550,000.000 660,000.000


MATERIAL 660,000.000
SUB TOTAL 679,916.000
OVER HEAD+PROFIT (15%) 101,987.400
TOTAL 781,903.400

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 781,903.400


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN URUGAN KROKOS DI PADATKAN 2.2

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 62,400.000 18,720.000


2 Mandor 0.010 1 0.010 119,600.000 1,196.000
PEKERJA 19,916.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Koral 1.200 M3 550,000.000 660,000.000


MATERIAL 660,000.000
SUB TOTAL 679,916.000
OVER HEAD+PROFIT (15%) 101,987.400
TOTAL 781,903.400

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 781,903.400

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PEMASANGAN PLASTIK COR 2.3

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.008 1 0.008 62,400.000 499.200


2 Mandor 0.0008 1 0.001 119,600.000 95.680
PEKERJA 594.880
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Plastik Cor 1.050 M2 4,000.000 4,200.000


MATERIAL 4,200.000
SUB TOTAL 4,794.880
OVER HEAD+PROFIT (15%) 719.232
TOTAL 5,514.112

VOLUME / QUANTITY 1.00 SATUAN M2 HARGA SATUAN (Rp.) 5,514.112

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN 1 M3 BETON TAK BERTULANG K. 175 MENGGUNAKAN MOLEN 2.4

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.650 1 1.650 62,400.000 102,960.000


2 Mandor 0.083 1 0.083 119,600.000 9,926.800
3 Tukang Batu 0.275 1 0.275 99,580.000 27,384.500
4 Kepala Tukang 0.028 1 0.028 109,590.000 3,068.520
PEKERJA 143,339.820
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Koral 0.762 M3 550,000.000 419,100.000


2 Semen 326.000 Kg 1,772.000 577,672.000
3 Pasir Beton 0.540 M3 145,000.000 78,300.000
4 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 1,118,072.000
SUB TOTAL 1,261,411.820
OVER HEAD+PROFIT (15%) 189,211.773
TOTAL 1,450,623.593

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,450,623.593


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN LANTAI KERJA / (BETON MUTU K 100) 2.5

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.650 1 1.650 62,400.000 102,960.000


2 Mandor 0.080 1 0.080 119,600.000 9,568.000
3 Tukang Batu 0.350 1 0.350 99,580.000 34,853.000
4 Kepala Tukang 0.025 1 0.025 109,590.000 2,739.750
PEKERJA 150,120.750
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Koral Cor 0.870 M3 550,000.000 478,500.000


2 Semen 218.000 Kg 1,772.000 386,296.000
3 Pasir Beton 0.520 M3 145,000.000 75,400.000
4 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 983,196.000
SUB TOTAL 1,133,316.750
OVER HEAD+PROFIT (15%) 169,997.513
TOTAL 1,303,314.263

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,303,314.263

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PONDASI BETON BERTULANG 2.6

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 3.900 1 3.900 62,400.000 243,360.000


2 Tukang batu 0.350 1 0.350 99,580.000 34,853.000
3 Tukang Kayu 1.040 1 1.040 99,580.000 103,563.200
4 Tukang Besi 1.050 1 1.050 99,580.000 104,559.000
5 Kapala Tukang 0.245 1 0.245 109,590.000 26,849.550
6 Mandor 0.165 1 0.165 119,600.000 19,734.000
PEKERJA 532,918.750
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Kayu Kelas IV 0.200 m3 2,100,000.000 420,000.000


2 Paku 5cm - 12 cm 1.500 kg 22,000.000 33,000.000
3 Minyak Bekisting 0.400 Ltr 6,750.000 2,700.000
4 Besi Beton Polos 120.000 kg 26,500.000 3,180,000.000
5 Kawat Beton 2.250 kg 24,850.000 55,912.500
6 Semen Portland 323.000 kg 1,772.000 572,356.000
7 Pasir Beton 0.520 m3 145,000.000 75,400.000
8 Koral Cor 0.780 m3 550,000.000 429,000.000
9 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 4,811,368.500
SUB TOTAL 5,344,287.250
OVER HEAD+PROFIT (15%) 801,643.088
TOTAL 6,145,930.338

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 6,145,930.338


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN KOLOM BETON BERTULANG 2.7

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 7.300 1 7.300 62,400.000 455,520.000


2 Tukang batu 0.350 1 0.350 99,580.000 34,853.000
3 Tukang Kayu 3.300 1 3.300 99,580.000 328,614.000
4 Tukang Besi 2.100 1 2.100 99,580.000 209,118.000
5 Kapala Tukang 0.570 1 0.570 109,590.000 62,466.300
6 Mandor 0.250 1 0.250 119,600.000 29,900.000
PEKERJA 1,120,471.300
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Kayu Kelas IV 0.400 m3 2,100,000.000 840,000.000


2 Paku 5cm - 12 cm 4.000 kg 22,000.000 88,000.000
3 Minyak Bekisting 2.000 Ltr 6,750.000 13,500.000
4 Besi Beton Polos 120.000 kg 26,500.000 3,180,000.000
5 Kawat Beton 3.000 kg 24,850.000 74,550.000
6 Semen Portland 323.000 kg 1,772.000 572,356.000
7 Pasir Beton 0.520 m3 145,000.000 75,400.000
8 Koral Cor 0.780 m3 550,000.000 429,000.000
9 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 5,315,806.000
SUB TOTAL 6,436,277.300
OVER HEAD+PROFIT (15%) 965,441.595
TOTAL 7,401,718.895

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 7,401,718.895

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN BALOK BETON BERTULANG 2.8

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 5.960 1 5.960 62,400.000 371,904.000


2 Tukang batu 0.350 1 0.350 99,580.000 34,853.000
3 Tukang Kayu 2.800 1 2.800 99,580.000 278,824.000
4 Tukang Besi 1.400 1 1.400 99,580.000 139,412.000
5 Kapala Tukang 0.455 1 0.455 109,590.000 49,863.450
6 Mandor 0.208 1 0.208 119,600.000 24,876.800
PEKERJA 899,733.250
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Kayu Kelas IV 0.320 m3 2,100,000.000 672,000.000


2 Paku 5cm - 12 cm 3.200 kg 22,000.000 70,400.000
3 Minyak Bekisting 1.600 Ltr 6,750.000 10,800.000
4 Besi Beton Polos 125.000 kg 26,500.000 3,312,500.000
5 Kawat Beton 3.000 kg 24,850.000 74,550.000
6 Semen Portland 323.000 kg 1,772.000 572,356.000
7 Pasir Beton 0.520 m3 145,000.000 75,400.000
8 Koral Cor 0.780 m3 550,000.000 429,000.000
9 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 5,260,006.000
SUB TOTAL 6,159,739.250
OVER HEAD+PROFIT (15%) 923,960.888
TOTAL 7,083,700.138

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 7,083,700.138


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PLAT BETON BERTULANG 2.9

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 5.600 1 5.600 62,400.000 349,440.000


2 Tukang batu 0.350 1 0.350 99,580.000 34,853.000
3 Tukang Kayu 2.640 1 2.640 99,580.000 262,891.200
4 Tukang Besi 1.050 1 1.050 99,580.000 104,559.000
5 Kapala Tukang 0.400 1 0.400 109,590.000 43,836.000
6 Mandor 0.193 1 0.193 119,600.000 23,082.800
PEKERJA 818,662.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Kayu Kelas IV 0.240 m3 2,100,000.000 504,000.000


2 Paku 5cm - 12 cm 3.200 kg 22,000.000 70,400.000
3 Minyak Bekisting 1.600 Ltr 6,750.000 10,800.000
4 Besi Beton Polos 80.000 kg 26,500.000 2,120,000.000
5 Kawat Beton 2.000 kg 24,850.000 49,700.000
6 Semen Portland 323.000 kg 1,772.000 572,356.000
7 Pasir Beton 0.520 m3 145,000.000 75,400.000
8 Koral Cor 0.780 m3 550,000.000 429,000.000
9 Kayu Kelas IV Balok 0.160 m3 2,115,000.000 338,400.000
10 Plywoodkayu
Dolken 9 mmφ (8-10) 2.800 Lbr 145,500.000 407,400.000
11 cm, panjang 4 m 24.000 Btg 15,200.000 364,800.000
12 Air 215.000 Ltr 200.000 43,000.000
MATERIAL 4,985,256.000
SUB TOTAL 5,803,918.000
OVER HEAD+PROFIT (15%) 870,587.700
TOTAL 6,674,505.700

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 6,674,505.700

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PEMBESIAN BETON 2.91

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.007 1 0.007 62,400.000 436.800


2 Tukang Besi 0.007 1 0.007 99,580.000 697.060
3 Kepala Tukang 0.0007 1 0.0007 109,590.000 76.713
4 Mandor 0.0003 1 0.0003 119,600.000 35.880
PEKERJA 1,246.453
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Besi Beton 1.050 Kg 26,500.000 27,825.000


2 Kawat Beton 0.015 Kg 24,850.000 372.750
MATERIAL 28,197.750
SUB TOTAL 29,444.203
OVER HEAD+PROFIT (15%) 4,416.630
TOTAL 33,860.833

VOLUME / QUANTITY 1.00 SATUAN Kg HARGA SATUAN (Rp.) 33,860.833


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN BETON BERTULANG ( 110 KG) 2.92

NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL


SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Membuat Beton K.175 1.000 M3 1,450,623.593 1,450,623.593


2 Tulangan Besi 110.000 Kg 33,860.833 3,724,691.680
3 Pasangan Bekisting Kayu Cetakan 1.000 M2 198,825.110 198,825.110
4 Pembongkaran Bekisting 1.000 set 3,420.560 3,420.560
MATERIAL 5,377,560.943
SUB TOTAL 5,377,560.943
OVER HEAD+PROFIT (15%) 806,634.141
TOTAL 6,184,195.084

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 6,184,195.084

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PASANGAN BATU BATA AD. 1:3 2.93

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.500 1 1.500 62,400.000 93,600.000


2 Tukang Batu 0.600 1 0.600 99,580.000 59,748.000
3 Kepala Tukang 0.060 1 0.060 109,590.000 6,575.400
4 Mandor 0.075 1 0.075 119,600.000 8,970.000
PEKERJA 168,893.400
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Batu Bata Lobang 686.000 Bh 1,150.000 788,900.000


2 Semen ( Portland Cement) 3.954 Zak 88,600.000 350,324.400
3 Pasir Beton 0.546 M3 145,000.000 79,170.000
MATERIAL 1,218,394.400
SUB TOTAL 1,387,287.800
OVER HEAD+PROFIT (15%) 208,093.170
TOTAL 1,595,380.970

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,595,380.970

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PASANGAN BATU BATA AD. 1:4 2.94

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.500 1 1.500 62,400.000 93,600.000


2 Tukang Batu 0.600 1 0.600 99,580.000 59,748.000
3 Kepala Tukang 0.060 1 0.060 109,590.000 6,575.400
4 Mandor 0.075 1 0.075 119,600.000 8,970.000
PEKERJA 168,893.400
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Batu bata Lobang 686.000 Bh 1,150.000 788,900.000


2 Semen ( Portland Cement) 0.230 Zak 88,600.000 20,378.000
3 Pasir Beton 0.258 M3 145,000.000 37,410.000
MATERIAL 846,688.000
SUB TOTAL 1,015,581.400
OVER HEAD+PROFIT (15%) 152,337.210
TOTAL 1,167,918.610

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,167,918.610


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PASANGAN BATU KALI 2.95

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 1.500 1 1.500 62,400.000 93,600.000


2 Tukang Batu 0.600 1 0.600 99,580.000 59,748.000
3 Kepala Tukang 0.060 1 0.060 109,590.000 6,575.400
4 Mandor 0.075 1 0.075 119,600.000 8,970.000
PEKERJA 168,893.400
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Batu kali 1.200 Bh 570,000.000 684,000.000


2 Semen ( Portland Cement) 202.000 Kg 1,772.000 357,944.000
3 Pasir Beton 0.485 M3 145,000.000 70,325.000
MATERIAL 1,112,269.000
SUB TOTAL 1,281,162.400
OVER HEAD+PROFIT (15%) 192,174.360
TOTAL 1,473,336.760

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,473,336.760

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN HAMPARAN BATU SPLIT 5-7 DAN DI IKAT 2-3 2.96

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 88,600.000 26,580.000


2 Mandor 0.010 1 0.010 145,000.000 1,450.000
PEKERJA 28,030.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Batu Pecah 5-7 1.200 M3 564,125.000 676,950.000


2 Batu Pecah Pengikat 2-3 0.400 M3 548,375.000 219,350.000
MATERIAL 896,300.000
SUB TOTAL 924,330.000
OVER HEAD+PROFIT (15%) 138,649.500
TOTAL 1,062,979.500

VOLUME / QUANTITY 1.00 SATUAN M3 HARGA SATUAN (Rp.) 1,062,979.500

PEKERJAAN PENYELESAIAN

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PLESTERAN AD. 1:3 ( TEBAL 15 CM ) 3

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.200 1 0.200 62,400.000 12,480.000


2 Kepala Tukang 0.015 1 0.015 109,590.000 1,643.850
3 Tukang 0.150 1 0.150 109,590.000 16,438.500
4 Mandor 0.010 1 0.010 119,600.000 1,196.000
PEKERJA 31,758.350
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Semen ( Portland Cement) 6.480 Kg 1,772.000 11,482.560


2 Pasir Beton 0.019 M3 145,000.000 2,755.000
MATERIAL 14,237.560
SUB TOTAL 45,995.910
OVER HEAD+PROFIT (15%) 6,899.387
TOTAL 52,895.297

VOLUME / QUANTITY 1.00 SATUAN M2 HARGA SATUAN (Rp.) 52,895.297


DAFTAR ANALISA PEKERJAAN
KEC. TULUNG SELAPAN KAB. OKI

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN PLESTERAN AD. 1:4 ( TEBAL 15 CM ) 3.1

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.300 1 0.300 62,400.000 18,720.000


2 Kepala Tukang 0.015 1 0.015 109,590.000 1,643.850
3 Tukang 0.150 1 0.150 109,590.000 16,438.500
4 Mandor 0.015 1 0.015 119,600.000 1,794.000
PEKERJA 38,596.350
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Semen ( Portland Cement) 0.125 Zak 1,772.000 221.146


2 Pasir Beton 0.024 M3 145,000.000 3,480.000
MATERIAL 3,701.146
SUB TOTAL 42,297.496
OVER HEAD+PROFIT (15%) 6,344.624
TOTAL 48,642.120

VOLUME / QUANTITY 1.00 SATUAN M2 HARGA SATUAN (Rp.) 48,642.120

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN LABURAN ASPAL 1,8 Kg/m2 + TABUR PASIR 3.2

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 10.000 1 10.000 62,400.000 624,000.000


2 Mandor 1.000 1 1.000 119,600.000 119,600.000
PEKERJA 743,600.000
NO MATERIAL JUMLAH VOLUME HARGA SAT. BIAYA SUB TOTAL
SATUAN (Rp/Unit) (Rp.) (Rp.)

1 Pasir Pasang 43.000 M3 145,000.000 6,235,000.000


2 Aspal 2,900.000 Kg 17,550.000 50,895,000.000
3 Alat Bantu 1.000 Ls 100,000.000 100,000.000
4 Minyak Aspal 300.000 M3 4,550.000 1,365,000.000
MATERIAL 58,595,000.000
UNTUK 2400 M2 SUB TOTAL 59,338,600.000
UNTUK /M2 SUB TOTAL 24,724.417
OVER HEAD+PROFIT (15%) 3,708.663
TOTAL 28,433.079

VOLUME / QUANTITY 1 SATUAN M2 HARGA SATUAN (Rp.) 28,433.079

DINAS PEKERJAAN UMUM CIPTA KARYA ANALISA HARGA SATUAN KODE


PROVINSI SUMATERA SELATAN BONGKAR 1M2 BEKISTING DAN MEMBERSIHKAN PUING 3.4

NO PEKERJA VOL HARI JUMLAH UPAH BIAYA SUB TOTAL


(Hari -Orang) (Rp/Org/Hari) (Rp.) (Rp.)

1 Pekerja 0.040 1 0.040 62,400.000 2,496.000


2 Mandor 0.004 1 0.004 119,600.000 478.400
PEKERJA 2,974.400
SUB TOTAL 2,974.400
OVER HEAD+PROFIT (15%) 446.160
TOTAL 3,420.560

VOLUME / QUANTITY 1 SATUAN M2 HARGA SATUAN (Rp.) 3,420.560


DAFTAR HARGA SATUAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN SALURAN DRAINASE DESA PETALING KEC. TULUNG SELAPAN


KAB. OGAN KOMERING ILIR
LOKASI : DESA PETALING KEC.TULUNG SELAPAN
TH. ANGGARAN : 2016

HARGA
NO JENIS PEKERJAAN SATUAN
( RP )
1 2 3 4

1 Pekerjaan galian tanah m3 76,161.28


2 Urugan tanah kembali m3 42,757.00
3 Pengurugan 1 m3 dengan pasir urug m3 209,203.40
4 Pekerjaan pasangan batu kali ad.1:4 m3 1,473,336.76
5 Pekerjaan plesteran ad.1:4 m2 48,642.12
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT
( RP ) ( RP )
1 2 3 4 5 6

I PEKERJAAN DRAINASE
1 Pekerjaan galian tanah 138.00 m3 35,000.00 4,830,000.00
2 Urugan tanah kembali 46.00 m3 22,000.00 1,012,000.00
3 Pengurugan 1 m3 dengan pasir urug 6.00 m3 100,000.00 600,000.00
4 Pekerjaan pasangan batu bata ad.1:4 78.00 m3 850,000.00 66,300,000.00
5 Pekerjaan plesteran ad.1:4 296.00 m2 50,000.00 14,800,000.00

Jumlah 87,542,000.00
SALURAN BATU BATA
1.2

0.8
0.2 0.2

0.9

I I
1.1

0.6

0.2 II
0.05
0.3 0.3

PEKERJAAN SALURAN PAS. BATU BATA

Pekerjaan Saluran M2 M1
PANJANG
1. Pas. Batu Bata 0.780 100 78.00 M3
100 x 1,4 x 1,2
DIMENSI 1 0.27 2.00
0.54
DIMENSI 2 0.24
0.78 M2 `

2. Urugan pasir 0.05 1.20 100 6.00 M3


3. Galian tanah 1.15 1.20 100 138.00 M3
4. Plesteran
SISI ATAS 0.18 2.00
0.36
SISI SAMPING 1.00 2.00
2.00
SISI TENGAH 0.60 1.00
0.60
2.96 M3 100 296.00 M2
5. Urugan tanah kembali 46.00 M3
6. Pemasangan Bouwplank 2.00 100 50.00 M1