Catatan :
Harga Upah Minimum Kota th. 2014 adalah Rp. 1.400.000/bln
DAFTAR HARGA SATUAN BAHAN BANGUNAN
I Bahan Bangunan
1 Tanah dan Pasir
Pasir Urug M3 99,000.00
Pasir Pasang M3 99,000.00
Pasir Beton/Cor M3 99,000.00
Sirtu M3 126,500.00
Pasir Plester M3 99,000.00
Tanah Urug M3 82,500.00
2 Kerikil
Kerikil Split M3 261,250.00
Kerikil Sungai/Koral M3 140,000.00
3 Batu Batuan
Batu Utuh, Batu Kali, Batu Gunung M3 125,000.00
Batu Pecah M3 215,000.00
4 Batu Cetak
Batu Bata Bh 1,045.00
Batako 20 x 40 x 11 Bh 2,500.00
Loster Beton 20 x 40 Bh 25,000.00
5 Kapur
Kapur Pasang (Mil) Kg 1,980.00
6 Semen
Semen Tonasa 1 zak = 50 kg Zak 65,000.00
Semen Putih Kg 1,640.00
Semen Warna Kg 22,000.00
7 Bahan Atap
Seng Gelombang kecil BJLS 0,20 Lbr 55,000.00
Seng Gelombang besar BJLS 0,20 Lbr 54,000.00
Seng Plat / Seng Talang lebar 45 cm M 19,500.00
Seng Plat BJLS 0,20 Lbr 43,500.00
Seng Plastik gelombang kecil Lbr 59,000.00
Seng Plastik gelombang besar Lbr 98,000.00
Seng "Soka Jempol" BJLS 0,22 Lbr 57,000.00
Genteng Metal ex sakura merpati uk. 80 x 77, t=0,25mm Lbr 54,000.00
Genteng Metal ex sakura merpati uk. 80 x 77, t=0,25mm (1,8 lbr / m2) M2 97,200.00
Genteng Metal Nok ex putri sakura p = 100 cm Bh 31,000.00
Lisplank GRC lebar = 20 cm, p = 4 m Lbr 76,500.00
Lisplank GRC lebar = 30 cm, p = 3,66 m Lbr 81,000.00
Talang PVC Profil U p = 4m Btg 52,000.00
Tutup talang PVC Bh 3,000.00
Gantungan besi utk talang PVC Bh 5,500.00
Corong untuk talang PVC Bh 7,500.00
Knee utk talang PVC Bh 7,500.00
Main Truss (75.75) ex taso , 1 btg = 6 m Btg 87,500.00
Reng (U Type) ex taso , 1 btg = 6 m Btg 52,500.00
Screw Truss Bh 500.00
Screw Reng Bh 500.00
No Uraian Spesifikasi Satuan Harga Satuan (Rp)
8 Bahan Kayu
Kayu Kelas I M3 3,300,000.00
Kayu Kelas II M3 1,925,000.00
Kayu Kelas III M3 1,595,000.00
Dolken (Tiang Perancah) Btg 8,000.00
Minyak bekisting Ltr 2,500.00
10 Bahan Langit-Langit
Tripleks Uk. 120x240x3,0 mm Lbr 53,900.00
Multipleks Uk. 120x240x9 mm Lbr 153,000.00
Gypsum Board Uk. 120x240 t = 9mm, ex Jayaboard Lbr 91,000.00
Lis Plafon kayu 5/5 P=4m Btg 25,000.00
Teakwood t = 3mm Lbr 128,000.00
Teakwood t = 4mm Lbr 111,000.00
11 Bahan Finishing
Cat Kayu/besi ex Ftalit Kg 60,500.00
Cat Kayu Dasar Kg 60,500.00
Dempul Besi ex Isamu Kg 57,500.00
Dempul Kayu ex Sanpolac Kg 20,000.00
Tiner ex Sakura Ltr 37,500.00
Tiner ex Impala Ltr 37,500.00
Kuas 4" Bh 15,000.00
Kuas 2" Bh 7,000.00
Kertas Pasir Lbr 4,000.00
Lem Kayu Klg 39,000.00
Sealent 1 tabung = 380 ml Tabung 37,500.00
Sealent ltr 98,600.00
Cat Tembok Finished ex Catylac, 1 Klg = 5 kg Pail 112,250.00
Cat Tembok Dasar ex Catylac, 1 Klg = 5 kg Pail 112,250.00
Plamur Tembok ex Matek, 1 galon = 4 kg Galon 50,000.00
Cat Meni ex Kansai Kg 19,800.00
Cat Residu Ltr 20,000.00
13 Bahan Penggantung
Kunci Pintu 2 Slaag ex Bremen Set 130,000.00
Engsel (utk pintu) ex Bremen, 4cm x 3cm x 2mm Psg 17,500.00
Engsel (utk jendela) ex Bremen, 3cm x 2,5cm x 2mm Psg 10,500.00
Grendel Pintu Tanam Psg 90,000.00
Grandel (kunci) jendela ex Solid Bh 7,500.00
Grandel (kunci) jendela ex Dekson Bh 7,500.00
12 Paku-Pakuan
Paku Beton Dos 13,750.00
No Uraian Spesifikasi Satuan Harga Satuan (Rp)
13 Bahan Listrik
Kabel NYM 3 x 2,5 mm Eterna, 1 Roll = 50 m Roll 387,500.00
Kabel NYA 2,5 mm Eterna, 1 Roll = 100 m Roll 275,000.00
Pipa Listrik dia 5/8 p = 4m Btg 6,000.00
Pipa Listrik dia 5/8 ex Clipsal, p = 2,4m Btg 14,000.00
Saklar Single tanam ex Broco Bh 12,350.00
Saklar Double tanam ex Broco Bh 18,350.00
Kotak imbowdus ex schneider Bh 2,000.00
Stop Kontak ex Broco Bh 20,000.00
Lampu 18 watt ex Phillips Essential Bh 45,000.00
Lampu 14 watt ex Phillips Essential Bh 35,000.00
Fitting lampu ex Broco Bh 15,000.00
MCB 6A Schnelder Bh 50,000.00
Box MCB (8 modul) ex Broco Bh 52,500.00
Penangkal Petir Bh 1,150,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
A. 2.3.1.9 Pengurugan kembali 1 m3 galian tanah (dihitung dari 1/3 kali dari koefisien pekerjaan galian)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L. 01 OH 0.2500 75,000.00 18,750.00
Mandor L. 04 OH 0.0083 100,000.00 833.33
JUMLAH TENAGA KERJA 19,583.33
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
A. 4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm, w/c = 0,78
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L. 01 OH 1.6500 75,000.00 123,750.00
Tukang batu L. 02 OH 0.2750 95,000.00 26,125.00
Kepala tukang L. 03 OH 0.0280 135,000.00 3,780.00
Mandor L. 04 OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 161,955.00
B BAHAN
Semen portland Kg 276.0000 1,300.00 358,800.00
Pasir beton m3 0.5914 99,000.00 58,551.43
Kerikil (Maks 30 mm) m3 0.7496 140,000.00 104,948.15
Air Liter 215.0000 -
JUMLAH HARGA BAHAN 522,299.58
C PERALATAN
-
JUMLAH HARGA ALAT -
A. 4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L. 01 OH 0.0200 75,000.00 1,500.00
Tukang cat L. 02 OH 0.0630 95,000.00 5,985.00
Kepala tukang L. 03 OH 0.0063 135,000.00 850.50
Mandor L. 04 OH 0.0030 100,000.00 300.00
JUMLAH TENAGA KERJA 8,635.50
B BAHAN
Plamuur Kg 0.1000 12,500.00 1,250.00
Cat dasar Kg 0.1000 22,450.00 2,245.00
Cat penutup Kg 0.2600 22,450.00 5,837.00
JUMLAH HARGA BAHAN 9,332.00
C PERALATAN
-
JUMLAH HARGA ALAT -
A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 100), slump (12 ± 2) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L. 01 OH 1.6500 75,000.00 123,750.00
Tukang batu L. 02 OH 0.2750 95,000.00 26,125.00
Kepala tukang L. 03 OH 0.0280 135,000.00 3,780.00
Mandor L. 04 OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 161,955.00
B BAHAN
Semen portland Kg 247.0000 1,300.00 321,100.00
Pasir beton m3 0.6207 99,000.00 61,450.71
Kerikil m3 0.7400 140,000.00 103,600.00
Air Liter 215.0000 -
JUMLAH HARGA BAHAN 486,150.71
C PERALATAN
-
JUMLAH HARGA ALAT -
A. 4.1.1.5 Membuat 1 m3 beton mutu f'c = 14,5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L. 01 OH 1.6500 75,000.00 123,750.00
Tukang batu L. 02 OH 0.2750 95,000.00 26,125.00
Kepala tukang L. 03 OH 0.0280 135,000.00 3,780.00
Mandor L. 04 OH 0.0830 100,000.00 8,300.00
JUMLAH TENAGA KERJA 161,955.00
B BAHAN
Semen portland Kg 326.0000 1,300.00 423,800.00
Pasir beton m3 0.5429 99,000.00 53,742.86
Kerikil m3 0.7622 140,000.00 106,711.11
Air Liter 215.0000 -
JUMLAH HARGA BAHAN 584,253.97
C PERALATAN
-
JUMLAH HARGA ALAT -
TOTAL
NO URAIAN PEKERJAAN JUMLAH BIAYA
(RP.)
A. PEKERJAAN FISIK
A. PEKERJAAN PERSIAPAN 500,000.00
B. PEKERJAAN GALIAN & URUGAN 4,001,550.00
C. PEKERJAAN PLESTERAN 4,448,820.00
D. PEKERJAAN BETON 17,466,028.65
E. PEKERJAAN AKHIR 1,000,000.00
JUMLAH TOTAL 27,416,398.65
PPn ( 11,5%) 3,152,885.85
JUMLAH 30,569,284.50
DIBULATKAN 30,569,000.00
RINCIAN
RENCANA ANGGARAN BIAYA
SATUAN KERJA : DINAS PERTANIAN PROVINSI SULAWESI TENGAH
KEGIATAN : 0
PEKERJAAN : PEMBANGUNAN LANTAI JEMUR
LOKASI : 0
TAHUN ANGGARAN : 2016
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(RP.) (RP.)
A. PEKERJAAN PERSIAPAN
1 Pek. Pasang Bouwplank & Pengukuran 1.00 Ls 500,000.00 500,000.00
TOTAL JUMLAH - A 500,000.00
B. PEKERJAAN GALIAN & URUGAN
1 Pek. Galian Tanah Kanstin Beton 3.60 m³ 34,000.00 122,400.00
2 Pek. Urugan Kembali Bekas Galian 1.08 m³ 19,583.33 21,150.00
3 Pek.Urugan Pasir bawah Lantai Jemur 9.60 m³ 142,300.00 1,366,080.00
4 Pek.Urugan Sirtu bawah Lantai Jemur 14.40 m³ 173,050.00 2,491,920.00
TOTAL JUMLAH - B 4,001,550.00
C. PEKERJAAN PLESTERAN
1 Pek. Plester Kanstin Beton 1 : 3 24.00 m2 42,580.00 1,021,920.00
2 Pek. Acian Kanstin Beton 24.00 m2 28,557.50 685,380.00
3 Pek. Acian Permukaan Lantai 96.00 m2 28,557.50 2,741,520.00
TOTAL JUMLAH - C 4,448,820.00
D. PEKERJAAN BETON
1 Pek. Cor Beton Tumbuk Untuk Lantai, t= 7 cm 13.51 m³ 572,141.00 7,730,769.19
2 Pekerjaan Kastin Beton, Mutu Beton K-175
a. Pekerjaan Pengecoran Kanstin Beton K-175 4.40 m³ 746,208.97 3,283,319.46
b. Pekerjaan Cetakan (Begisting ) 44.00 m2 146,635.00 6,451,940.00
TOTAL JUMLAH - D 17,466,028.65
E. PEKERJAAN AKHIR
1 Finishing dan Pembersihan Akhir 1.00 Ls 500,000.00 500,000.00
2 Dokumentasi dan Administrasi 1.00 Ls 500,000.00 500,000.00
TOTAL JUMLAH - E 1,000,000.00
30,569,000.00
#REF!
#REF!
#REF!
#REF!
#REF!
30,569,000.00
#REF!
B. PEKERJAAN GALIAN & URUGAN
C. PEKERJAAN PLESTERAN
7 Pek. Plester Kanstin Beton 1 : 3
Luas = 40.00 x 0.60 = 24.00 m2
24.00 m2
E. PEKERJAAN BETON
1 Pek. Cor Beton Tumbuk Untuk Lantai, t= 7 cm
= 1.13 x 12.00 = 13.51 m3
13.51 m3
F. PEKERJAAN ATAP
1 Err:509 4.00 Bh
balok tarik = 6.15 x 0.08 x 0.12 = 0.06 m3 0.02
Tiang Raja = 2.00 x 0.08 x 0.12 = 0.02 m3
Kaki Kuda2 = 9.00 x 0.08 x 0.12 = 0.09 m3 0.03
Balok Sokong = 2.40 x 0.08 x 0.12 = 0.02 m3
Balok Gapit = 4.80 x 0.06 x 0.10 = 0.03 m3 0.01
0.22 m3 0.07
0.93 m3
1 Err:509 4.00 Bh
Nok = 10.80 x 0.06 x 0.12 = 0.08 m3
Gording = 129.60 x 0.06 x 0.12 = 0.93 m3
Gording = 9.00 x 0.06 x 0.12 = 0.06 m3
1.08 m3
2 Err:509
Luas Atap = 9.00 x 10.80 = 97.20 m2
= 3.00 x 1.70 = 5.10 m2
102.30 m2
3 Pek. Pasang Bubungan Metal
Panjang Bumbungan = 11.00 m
J. PEKERJAAN PENGECATAN
1 Err:509 Listplank = Err:509 x 0.30 = Err:509 m2
Daun Pintu = 14.00 m2
Kusen = 2.24 m2
Err:509 m2
m3
m3
=
=
108.53 kg
57.60 kg
166.14 kg
12 Saluran Air Hujan = 84.50
volume per m' meliputi :
Galian Tanah = 0.25
Plesteran = 1.00
Kerikil = 0.35
Plesteran = 1.75
= 1.75
= 1.60
= 0.40
m'
bh
BERAT/6m BERAT/6m
UKURAN UKURAN
kg kg
50.36.5 mm 33.50 60.30.10.1,2 7.44
65.42.5,5 mm 42.50 60.30.10.2,3
75.40.5 mm 41.50 75.35.10.1,6 13.90
80.45.5 mm 47.00 75.45.15.2,3 19.50
100.50.5 mm 56.20 100.50.20.2,3 24.40
120.55.6 mm 75.00 100.50.20.3,2 33.00
125.55.6 mm 80.40 125.50.20.2,3 27.10
140.60.7 mm 96.00 125.50.20.3,2 36.80
150.75.6,5 mm 112.00 150.50.20.2,3 30.00
160.66.7 mm 115.50 150.50.20.3,2 40.60
180.75.7 mm 132.00 150.65.20.2,3 33.00
200.80.7,5 mm 152.00 150.65.20.3,2 45.10
220.80.9 mm 187.50 200.75.20.3,2 56.00
240.85.9,5 mm 205.00
250.80.7,1 mm 182.50
250.90.9 mm 208.00
260.90.10 mm 114.00
300.90.9 mm 229.00
300.100.10 mm 278.00
380.100.10,5 mm 337.50
PIPA PERSEGI
UKURAN ( mm ) TEBAL ( mm )
BESI BETON ( P = 12 m )
BESI W.F