HARGA BAHAN DAN UPAH KERJA

PEKERJAAN : PERENCANAAN PEMBANGUNAN SCREEN HOUSE UNTUKSAYURAN DATARAN TINGGI DI


KABUPATEN PUNCAK JAYA
INSTANSI : DINAS TANAMAN PANGAN DAN HORTIKULTURA PROVINSI PAPUA
LOKASI : KAB. PUNCAK JAYA
T. ANGGARA : 2018

A. HARGA BAHAN

NO NAMA BAHAN Satuan Harga di Lokasi


1 2 3 4
I. HARGA BAHAN LOKAL

A. KELOMPOK BAHAN BATU, PASIR, DAN TANAH


1. Batu Kali M³ 1,200,000.00
2. Batu Kerikil M³ 1,500,000.00
3. Batu Tela Bh 22,500.00
M³ 1,500,000.00
4. Sirtu
0.00
5. Batu Pecah : M³ 2,000,000.00
a. Ukuran 1 - 2 cm M³ 0.00
b. Ukuran 2 - 3 cm M³ 0.00
c. Ukuran 3 - 5 cm M³ 0.00
d. Ukuran 5 - 7 cm M³ 1,500,000.00
6. Pasir Pasang M³ 1,500,000.00
7. Pasir Beton M³ 1,500,000.00
8. Pasir Urug M³ 550,000.00
9. Tanah Timbunan/Urugan Pilihan M³ 550,000.00
10. Karang Timbunan M³ 550,000.00
11. Urugan Tanah Humus
II. HARGA BAHAN NON LOKAL
A. KELOMPOK BAHAN SEMEN
1. Semen PC 50 Kg Kg 46,000.00

B. KELOMPOK BAHAN ATAP


1. Agronet M2 15,000.00
C. KELOMPOK BAHAN BESI
1. Besi Hollow 40.40.2 mm Btg 375,000.00
2. Besi Hollow 20.40.1,60 mm Btg 329,000.00
3. Kawat Harmonika T. 150 cm M¹ 88,000.00
4. Pengelasan Cm 8,000.00

D. KELOMPOK BAHAN PIPA


1. PIPA GIP MEDIUM
a. Pipa GIP dia. 1/2" - 6 M Btg 633,000.00
c. Pipa GIP dia. 1" - 6 M Btg 1,018,000.00
d. Pipa GIP dia. 2" - 6 M Btg 2,001,000.00
2. PIPA PVC AW
a. Pipa PVC dia. ½" Btg 62,950.00
b. Pipa PVC dia. 1" Btg 97,800.00
d. Pipa PVC dia. 2" Btg 265,995.00

E. KELOMPOK BAHAN PENGUNCI/PENGGANTUNG


1. Engsel Pintu Stainless Bh 117,300.00

F. KELOMPOK BAHAN SANITAIR


1. Kran Air Kepala Putih Bh 92,000.00
2. Stop Kran Bh 143,000.00
3. Floor Drain Stainlees Bh 112,000.00
4. Mesin Pompa Air Sanyo + Asesories 450 Watt Unit 3,760,000.00
5. Shell Tape Bh 9,000.00

B UPAH KERJA

NO URAIAN TENAGA Satuan UPAH KERJA


1 2 3 4

1 Pekerja OH 150,000.00
2 Tukang OH 250,000.00
3 kepala Tukang OH 300,000.00
4 Mandor OH 352,000.00
ANALISA HARGA SATUAN
PEKERJAAN : PERENCANAAN PEMBANGUNAN SCREEN HOUSE UNTUKSAYURAN DATARAN TINGGI DI
KABUPATEN PUNCAK JAYA
INSTANSI : DINAS TANAMAN PANGAN DAN HORTIKULTURA PROVINSI PAPUA
LOKASI : KAB. PUNCAK JAYA
T. ANGGARAN : 2018

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6

# PEKERJAAN PERSIAPAN

1 1 M² Pembersihan Lokasi
~ Pekerja 0.1000 H/ 150,000.00 15,000.00
~ Mandor 0.0500 o 352,000.00 17,600.00
H/o
JUMLAH (Belum PPn) 32,600.00
JASA 15% 4,890.00
JUMLAH 37,490.00
TOTAL 37,490.00
DIBULATKAN
# PEKERJAAN TANAH

3 1 M³ Galian Tanah Biasa sedalam 1 M


~ Pekerja 0.7500 H/ 150,000.00 112,500.00
~ Mandor 0.0250 o 352,000.00 8,800.00
H/o
JUMLAH (Belum PPn) 121,300.00
JASA 15% 18,195.00
JUMLAH 139,495.00
TOTAL 139,490.00
DIBULATKAN
4 1 M³ Urugan Kembali Galian Tanah
~ Pekerja 0.5000 H/ 150,000.00 75,000.00
~ Mandor 0.0500 o 352,000.00 17,600.00
H/o
JUMLAH (Belum PPn) 92,600.00
JASA 15% 13,890.00
JUMLAH 106,490.00
TOTAL 106,490.00
DIBULATKAN
5 1 M³ Urugan Pasir
~ Pasir Urug 1.0000 M³ 1,500,000.00 1,500,000.00
~ Pekerja 0.3000 H/ 150,000.00 45,000.00
~ Mandor 0.0100 o 352,000.00 3,520.00
H/
o
JUMLAH (Belum PPn) 1,548,520.00
JASA 15% 232,278.00
JUMLAH 1,780,798.00
TOTAL 1,780,790.00
DIBULATKAN
7 1 M³ Urugan Tanah Humus
~ Urugan Tanah Humus 1.0000 M³ 550,000.00 550,000.00
~ Pekerja 0.3000 H/ 150,000.00 45,000.00
~ Mandor 0.0100 o 352,000.00 3,520.00
H/
o
JUMLAH (Belum PPn) 598,520.00
JASA 15% 89,778.00
JUMLAH 688,298.00
TOTAL 688,290.00
DIBULATKAN
# PEKERJAAN PASANGAN PONDASI

8 1 M³ Pasangan Pondasi Batu Kosong (Aanstamping)


~ Batu Belah 15/20 cm 1.0000 M³ 1,200,000.00 1,200,000.00
~ Pasir Urug 0.4320 M³ 1,500,000.00 648,000.00
~ Pekerja 0.7800 H/ 150,000.00 117,000.00
~ Tukang 0.3900 o 250,000.00 97,500.00
~ Kepala Tukang 0.0390 H/ 300,000.00 11,700.00
~ Mandor 0.0390 o 352,000.00 13,728.00
H/
o
H/
o
JUMLAH (Belum PPn) 2,087,928.00
JASA 15% 313,189.20
JUMLAH 2,401,117.20
TOTAL 2,401,110.00
DIBULATKAN
9 1 M³ Pasangan Pondasi Batu Kali
Campuran 1 Pc : 4 Psr
~ Batu Belah 15/20 cm 1.0000 M³ 1,200,000.00 1,200,000.00
~ Sement PC 163.0000 Kg 46,000.00 7,498,000.00
~ Pasir Pasang 0.5200 M³ 1,500,000.00 780,000.00
~ Pekerja 1.5000 H/ 150,000.00 225,000.00
~ Tukang 0.7500 o 250,000.00 187,500.00
~ Kepala Tukang 0.0750 H/ 300,000.00 22,500.00
~ Mandor 0.0750 o 352,000.00 26,400.00
H/
o
H/
o
JUMLAH (Belum PPn) 9,939,400.00
JASA 15% 1,490,910.00
JUMLAH 11,430,310.00
TOTAL 11,430,310.00
DIBULATKAN
# PEKERJAAN PASANGAN DINDING

10 1 M² Pasangan Dinding Batu Tela


Campuran 1 Pc : 3 Psr
~ Batu Tela 16.667 Bh 22,500.00 375,007.50
~ Sement PC 26.5500 Kg 46,000.00 1,221,300.00
~ Pasir Pasang 0.073 M³ 1,500,000.00 109,500.00
~ Pekerja 0.350 H/ 150,000.00 52,500.00
~ Tukang 0.150 o 250,000.00 37,500.00
~ Kepala Tukang 0.015 H/ 300,000.00 4,500.00
~ Mandor 0.018 o 352,000.00 6,336.00
H/
o
H/
o
JUMLAH (Belum PPn) 1,806,643.50
JASA 15% 270,996.53
JUMLAH TOTAL 2,077,640.03
DIBULATKAN 2,077,640.00

11 1 M² Plesteran Tebal 15 mm
Campuran 1 Pc : 3 Psr
~ Sement PC 7.7760 Kg 46,000.00 357,696.00
~ Pasir Pasang 0.0230 M³ 1,500,000.00 34,500.00
~ Pekerja 0.3000 H/ 150,000.00 45,000.00
~ Tukang 0.1500 o 250,000.00 37,500.00
~ Kepala Tukang 0.0150 H/ 300,000.00 4,500.00
~ Mandor 0.0150 o 352,000.00 5,280.00
H/o
H/o
JUMLAH (Belum PPn) 484,476.00
JASA 15% 72,671.40
JUMLAH 557,147.40
TOTAL 557,140.00
DIBULATKAN

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6

12 1 M² Acian Dinding Batu Tela


~ Sement PC 3.2500 Kg 46,000.00 149,500.00
~ Pekerja 0.2000 H/ 150,000.00 30,000.00
~ Tukang 0.1000 o 250,000.00 25,000.00
~ Kepala Tukang 0.0100 H/ 300,000.00 3,000.00
~ Mandor 0.0100 o 352,000.00 3,520.00
H/ (Belum PPn)
JUMLAH 211,020.00
JASA 15% 31,653.00
JUMLAH 242,673.00
TOTAL 242,670.00
DIBULATKAN
# PEKERJAAN BETON

10. 1 M³ COR BETON BERTULANG


Camp. 1 Pc : 2 Ps : 3 Krl
Kolom, Balok bebas tinggi s/d 4 M¹,
Plat lantai, Dak,Level setinggi 3 M1.
A. 1 M³ Beton Mutu f'c : 7,4 Mpa (K100)
~ Semen PC (50 Kg) 247.0000 Kg 46,000.00 11,362,000.00
~ Pasir Pasang 0.4340 M³ 1,500,000.00 651,000.00
~ Kerikil 0.5940 M³ 1,500,000.00 891,000.00
~ Pekerja 1.6500 H/ 150,000.00 247,500.00
~ Tukang 0.2750 o 250,000.00 68,750.00
~ Kepala Tukang 0.0280 H/ 300,000.00 8,400.00
~ Mandor 0.0830 o 352,000.00 29,216.00
H/ 13,257,866.00
B. 1 Kg Pembesian Beton Bertulang o
~ Besi beton Polos 1.0500 H/o 13,750.00 14,437.50
~ Kawat Ikat 0.0150 78,800.00 1,182.00
~ Pekerja 0.0070 150,000.00 1,050.00
~ Tukang Besi 0.0070 Kg 250,000.00 1,750.00
~ Kepala Tukang 0.0007 Kg 300,000.00 210.00
~ Mandor 0.0004 H/ 352,000.00 140.80
o 18,770.30
C. 10 M² Bekisting Beton (Bentuk Sederhana) H/
~ Kayu bekisting 0.0400 o 6,750,000.00 270,000.00
~ Paku 0.4000 H/ 75,000.00 30,000.00
~ Pekerja 0.6600 o 150,000.00 99,000.00
~ Tukang Kayu 0.3300 H/o 250,000.00 82,500.00
~ Kepala Tukang 0.0330 300,000.00 9,900.00
~ Mandor 0.0330 352,000.00 11,616.00
M³ 503,016.00
Per 1 M² Bekisting beton Kg 50,301.60
D. 10 M² Pembongkaran Bekisting H/
~ Pekerja 2.0000 o 150,000.00 300,000.00
~ Mandor 1.0000 H/ 352,000.00 352,000.00
o 652,000.00
Per 1 M² Pembongkaran Bekisting H/ 65,200.00
o
1 M³ COR BETON BERTULANG 1 : 2 : 3 H/o
~ Cor Beton 1 Pc : 2 Ps : 3 Kr 1.0000 13,257,866.00 13,257,866.00
~ Pembesian 110.0000 18,770.30 2,064,733.00
~ Bekisting 6.6000 50,301.60 331,990.56
~ Pembongkaran Bekisting 6.6000 H/o 65,200.00 430,320.00
16,084,909.56
1 M³ Cor Kolom Praktis 15 x 15 (K175) H/o
11 ~ Beton K100 1.0000 M 13,257,866.00 13,257,866.00
~ Pembesian 110.0000 ³ 18,770.30 2,064,733.00
~ Begisting Kolom 13.3333 Kg 50,301.60 670,688.00
M (Belum PPn)
JUMLAH 15,993,287.00
JASA 15% 2,398,993.05
JUMLAH 18,392,280.05
TOTAL 18,392,280.00
1 M³ Cor Beton Rinkbalk 15 x 20 (K225) DIBULATKAN
12 ~ Beton K100 1.0000 M 13,257,866.00 13,257,866.00
~ Pembesian 196.8119 ³ 18,770.30 3,694,217.50
~ Begisting Balok 13.3300 Kg 50,301.60 670,520.33
JUMLAH
M (Belum PPn) 17,622,603.83
JASA 15% 2,643,390.57
JUMLAH 20,265,994.41
TOTAL 20,265,990.00
1 M³ Cor Sloof (K225) DIBULATKAN
13 ~ Beton K100 1.0000 M³ 13,257,866.00 13,257,866.00
~ Pembesian 167.1851 Kg 18,770.30 3,138,113.99
~ Begisting Sloof 7.1829 M² 50,301.60 361,310.90
JUMLAH (Belum PPn) 16,757,290.89
JASA 15% 2,513,593.63
JUMLAH 19,270,884.53
TOTAL 19,270,880.00
DIBULATKAN
14 1 M³ Cor Plat Lantai T. 12 cm (K225)
~ Beton K225 1.0000 M 13,257,866.00 13,257,866.00
~ Pembesian 197.7634 ³ 18,770.30 3,712,078.62
~ Begisting 9.2336 Kg 50,301.60 464,465.37
M
²
JUMLAH (Belum PPn) 17,434,409.99
JASA 15% 2,615,161.50
JUMLAH 20,049,571.49
TOTAL 20,049,570.00
DIBULATKAN
15 1 M³ Membuat Beton Mutu f'c : 7,4 Mpa (K100)
~ Sement PC 247.0000 Kg 46,000.00 11,362,000.00
~ Pasir Beton 0.4340 M³ 1,500,000.00 651,000.00
~ Kerikil Beton 0.5940 M³ 1,500,000.00 891,000.00
~ Air 215.000 Ltr 250.00 53,750.00
~ Pekerja 1.6500 H/ 150,000.00 247,500.00
~ Tukang 0.2750 o 250,000.00 68,750.00
~ Kepalla Tukang 0.0280 H/ 300,000.00 8,400.00
~ Mandor 0.0830 o 352,000.00 29,216.00
H/o
H/o
JUMLAH (Belum PPn) 13,311,616.00
JASA 15% 1,996,742.40
JUMLAH 15,308,358.40
TOTAL 15,308,350.00
DIBULATKAN

HARGA SATUAN JUMLAH


No. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
16 1 M³ Membuat Beton Mutu f'c : 19,3 Mpa (K225)
~ Sement PC 371.0000 Kg 46,000.00 17,066,000.00
~ Pasir Beton 0.3490 M³ 1,500,000.00 523,500.00
~ Kerikil/Batu Pecah uk. 2 - 3 cm 0.6220 M³ 1,500,000.00 933,000.00
~ Air 215.000 Ltr 250.00 53,750.00
~ Pekerja 1.6500 H/ 150,000.00 247,500.00
~ Tukang 0.2750 o 250,000.00 68,750.00
~ Kepalla Tukang 0.0280 H/ 300,000.00 8,400.00
~ Mandor 0.0830 o 352,000.00 29,216.00
H/o
H/o
JUMLAH (Belum PPn) 18,930,116.00
JASA 15% 2,839,517.40
JUMLAH 21,769,633.40
TOTAL 21,769,630.00
DIBULATKAN
17 1 M¹ PEKERJAAN RANGKA BESI HOLOW 40.40.2 mm
~ Besi Hollow 40 x 40 mm 0.1400 M1 375,000.00 52,500.00
~ Pengelasan 16.0000 cm 4,500.00 72,000.00
~ Pekerja 0.1000 H/ 150,000.00 15,000.00
~ Tukang 0.1100 o 250,000.00 27,500.00
~ Kepala Tukang 0.0800 H/o 300,000.00 24,000.00
~ Mandor 0.0750 H/o 352,000.00 26,400.00
H/o
JUMLAH (Belum PPn) 217,400.00
JASA 15% 32,610.00
JUMLAH 250,010.00
TOTAL 250,010.00
DIBULATKAN
18 1 M¹ PEKERJAAN RANGKA BESI HOLOW 40.20.2 mm
~ Besi Hollow 20 x 40 mm 0.1400 M1 329,000.00 46,060.00
~ Pengelasan 12.0000 cm 4,500.00 54,000.00
~ Pekerja 0.1000 H/ 150,000.00 15,000.00
~ Tukang 0.1100 o 250,000.00 27,500.00
~ Kepala Tukang 0.0800 H/ 300,000.00 24,000.00
~ Mandor 0.0750 o 352,000.00 26,400.00
H/o
H/o
JUMLAH (Belum PPn) 192,960.00
JASA 15% 28,944.00
JUMLAH 221,904.00
TOTAL 221,900.00
DIBULATKAN
19 1 M¹ PEKERJAAN TIANG BESI GIP dia 2 "
~ Besi Gip 2" 0.1400 btg 2,001,000.00 280,140.00
~ Pengelasan 16.0000 cm 4,500.00 72,000.00
~ Pekerja 0.1500 H/ 150,000.00 22,500.00
~ Tukang 0.1500 o 250,000.00 37,500.00
~ Kepala Tukang 0.1000 H/o 300,000.00 30,000.00
~ Mandor 0.0830 H/o 352,000.00 29,216.00
H/o
JUMLAH (Belum PPn) 471,356.00
JASA 15% 70,703.40
JUMLAH 542,059.40
TOTAL 542,050.00
DIBULATKAN
20 1 M² Kawat Harmonika
~ Kawat Harmonikai 1.1000 Lbr 88,000.00 96,800.00
~ Pekerja 0.1000 H/ 150,000.00 15,000.00
~ Tukang Kayu 0.1000 o 250,000.00 25,000.00
~ Kepala Tukang Kayu 0.0300 H/ 300,000.00 9,000.00
~ Mandor 0.0500 o 352,000.00 17,600.00
~ Pengelasan 12.0000 H/o 4,500.00 54,000.00
H/o
cm
JUMLAH (Belum PPn) 217,400.00
JASA 15% 32,610.00
JUMLAH 250,010.00
TOTAL 250,010.00
DIBULATKAN
# PEKERJAAN SANITAIR
21 1 Bh Memasang Kran Air Ø ½"
~ Kran Air Ø ½" 1.0000 Bh 92,000.00 92,000.00
~ Seal Tape 0.0250 Bh 9,000.00 225.00
~ Pekerja 0.0100 H/ 150,000.00 1,500.00
o
~ Tukang 0.1000 H/o 250,000.00 25,000.00
~ Kepala Tukang 0.0100 H/o 300,000.00 3,000.00
~ Mandor 0.0050 H/o 352,000.00 1,760.00
JUMLAH (Belum PPn) 123,485.00
JASA 15% 18,522.75
JUMLAH 142,007.75
TOTAL 142,000.00
DIBULATKAN
22 1 Bh Memasang Floor Drain
~ Floor Drain 1.0000 Bh 32,000.00 32,000.00
~ Pekerja 0.0100 H/ 150,000.00 1,500.00
~ Tukang 0.1000 o 250,000.00 25,000.00
~ Kepala Tukang 0.0100 H/ 300,000.00 3,000.00
~ Mandor 0.0050 o 352,000.00 1,760.00
H/
o
H/o
JUMLAH (Belum PPn) 63,260.00
JASA 15% 9,489.00
JUMLAH 72,749.00
TOTAL 72,740.00
DIBULATKAN
23 1 M¹ Memasang Pipa PVC Ø 2" AW
~ Pipa PVC Ø 2 AW 1.2000 Bh 44,332.50 53,199.00
~ Perlengkapan (35% Harga Pipa) 15,516.38
~ Pekerja 0.0810 H/ 150,000.00 12,150.00
~ Tukang 0.1350 o 250,000.00 33,750.00
~ Kepala Tukang 0.0135 H/ 300,000.00 4,050.00
~ Mandor 0.0041 o 352,000.00 1,443.20
H/
o
H/o
JUMLAH (Belum PPn) 120,108.58
JASA 15% 18,016.29
JUMLAH 138,124.86
TOTAL 138,120.00
DIBULATKAN
24 1 M¹ MEMASANG PIPA PVC Ø 1" AW
~ Pipa PVC Ø 1" AW 1.2000 M¹ 16,300.00 19,560.00
~ Perlengkapan (35% Harga Pipa) 5,705.00
~ Pekerja 0.1350 H/ 150,000.00 20,250.00
~ Tukang 0.2250 o 250,000.00 56,250.00
~ Kepala Tukang 0.0225 H/ 300,000.00 6,750.00
~ Mandor 0.0680 o 352,000.00 23,936.00
H/
o
H/o
JUMLAH (Belum PPn) 132,451.00
JASA 15% 19,867.65
JUMLAH TOTAL 152,318.65
DIBULATKAN 152,310.00
RENCANA ANGGARAN BIAYA
PEKERJAAN : PERENCANAAN PEMBANGUNAN SCREEN HOUSE UNTUKSAYURAN DATARAN TINGGI
DI KABUPATEN PUNCAK JAYA
INSTANSI : DINAS TANAMAN PANGAN DAN HORTIKULTURA PROVINSI
PAPUA LOKASI : KAB. PUNCAK JAYA
T. ANGGARAN 2018

HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6

I. PEKERJAAN PENDAHULUAN
1. Papan Nama Kegiatan 1.00 Ls 500,000.00 500,000.00
3. Pengukuran dan Pemasangan Bouwplank 1.00 Ls 2,000,000.00 2,000,000.00
2. Pembersihan Lokasi 1.00 Ls 1,500,000.00 1,500,000.00
4,000,000.00
II. PEKERJAAN TANAH DAN PASIR
1. Pekerjaan Galian Tanah Pondasi 14.88 M³ 139,490.00 2,074,913.75
2. Urugan Tanah Kembali 4.96 M³ 106,490.00 528,012.92
3. Urugan Tanah Humus 16.80 M³ 688,290.00 11,563,272.00
4. Urugan Pasir Bawah Pondasi 1.45 M³ 1,780,790.00 2,582,145.50
5. Urugan Pasir Dibawah Lantai 5.60 M³ 1,780,790.00 9,972,424.00
26,720,768.17
III. PEKERJAAN BETON DAN PASANGAN
1. Pas. Anstamping Batu Kosong 4.35 M³ 2,401,110.00 10,444,828.50
2. Pas. Pondasi Batu Kali 1:4 7.29 M³ 11,430,310.00 83,326,959.90
3. Cor lantai Beton Tumbuk 3.36 M³ 15,308,350.00 51,436,056.00
4. Cor Sloof 10/15 Meja 0.24 M³ 19,270,880.00 4,625,011.20
5. Cor Kolom Praktis 10/10 Meja 0.13 M³ 18,392,280.00 2,354,211.84
6. Cor Balok 10/15 Meja 0.24 M³ 20,265,990.00 4,863,837.60
7. Cor Meja Beton Bertulang T : 10 cm 2.56 M³ 20,049,570.00 51,326,899.20
8. Pas. Dinding Bt Tela 1 : 4 14.90 M² 2,077,640.00 30,957,874.82
9. Pek. Plesteran 1 : 3 25.60 M² 557,140.00 14,262,784.00
253,598,463.06
IV. PEKERJAAN BESI
1. Pek. Tiang Besi Gip dia.2" 49.50 M¹ 542,050.00 26,831,475.00
2. Pek. Rangka Kuda - Kuda Besi Hollow 40.40.2 mm 195.92 M¹ 250,010.00 48,980,709.15
3. Pek. Gording Besi Hollow 40.40.2 mm 168.00 M¹ 250,010.00 42,001,680.00
4. Pek. Rangka Dinding Besi Hollow 40.40.2 mm 127.90 M¹ 250,010.00 31,976,279.00
5. Pek. Kusen Besi Hollow 40.40.2 mm 5.50 M¹ 250,010.00 1,375,055.00
6. Pas. Pintu Rangka Besi Hollow 40.40.2 mm 12.64 M¹ 250,010.00 3,160,126.40
7. Pas. Kawat Ram Pintu 1.08 M² 250,010.00 270,010.80
8. Pas. Agronet 132.21 M² 15,000.00 1,983,150.00
9. Pas. Penutup Atap Plastik UV 122.90 M² 18,500.00 2,273,650.00
158,852,135.35
V. PEKERJAAN SANITAIR
1. Pipa Pemasukan PVC Ø 1" 22.00 M¹ 152,310.00 3,350,820.00
2. Pas. Pipa Pembuangan PVC 2" AW 37.54 M¹ 138,120.00 5,185,024.80
3. Kran Air Ø 1" 2.00 Bh 142,000.00 284,000.00
4. Pas. Floar Drain 12.00 Bh 72,740.00 872,880.00
9,692,724.80
VI. PEKERJAAN AKHIR
1. Pek. Pembersihan Akhir 1.00 Ls 1,500,000.00 1,500,000.00
1,500,000.00
Alamat : Kantor Dinas - Dinas Otonom Provinsi Papua Gedung B Lantai 3 Jl. Raya Kotaraja - Jayapura Telp : (0967) 583156
Faxs ; (0967) 585501

"REKAPITULASI ANGGARAN BIAYA"


PEKERJAAN : PERENCANAAN PEMBANGUNAN SCREEN HOUSE UNTUKSAYURAN DATARAN TINGGI DI
KABUPATEN PUNCAK JAYA
INSTANSI : DINAS TANAMAN PANGAN DAN HORTIKULTURA PROVINSI PAPUA
LOKASI : KAB. PUNCAK JAYA
T. ANGGARAN : 2018

NO URAIAN PEKERJAAN JUMLAH HARGA


I. PEKERJAAN PENDAHULUAN Rp. 4,000,000.00
II. PEKERJAAN TANAH DAN PASIR Rp. 26,720,768.17
III. PEKERJAAN BETON DAN PASANGAN Rp. 253,598,463.06
IV. PEKERJAAN BESI Rp. 158,852,135.35
V. PEKERJAAN SANITAIR Rp. 9,692,724.80
VI. PEKERJAAN AKHIR Rp. 1,500,000.00

REAL COST : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 454,364,091.38


PAJAK (PPn 10%) : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 45,436,409.14
TOTAL COST : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 499,800,500.51

PEMBULATAN : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp. 499,800,000.00

Terbilang : Empat ratus sembilan puluh sembilan juta delapan ratus ribu rupiah.

Jayapura,..................................2018

KEPALA DINAS
PEJABAT PELAKSANA TEKNIS KEGIATAN TANAMAN PANGAN DAN HORTIKULTURA
(PPTK) PROVINSI PAPUA

SALMON TELENGGEN, SP Ir. SEMUEL SIRIWA, M.Si


Nip. 19800621 200312 1 004 Nip. 19650707 198903 1 015