# PEKERJAAN PERSIAPAN
1 1 M² Pembersihan Lokasi
~ Pekerja 0.1000 H/ 150,000.00 15,000.00
~ Mandor 0.0500 o 352,000.00 17,600.00
H/o
JUMLAH (Belum PPn) 32,600.00
JASA 15% 4,890.00
JUMLAH 37,490.00
TOTAL 37,490.00
DIBULATKAN
# PEKERJAAN TANAH
11 1 M² Plesteran Tebal 15 mm
Campuran 1 Pc : 3 Psr
~ Sement PC 7.7760 Kg 46,000.00 357,696.00
~ Pasir Pasang 0.0230 M³ 1,500,000.00 34,500.00
~ Pekerja 0.3000 H/ 150,000.00 45,000.00
~ Tukang 0.1500 o 250,000.00 37,500.00
~ Kepala Tukang 0.0150 H/ 300,000.00 4,500.00
~ Mandor 0.0150 o 352,000.00 5,280.00
H/o
H/o
JUMLAH (Belum PPn) 484,476.00
JASA 15% 72,671.40
JUMLAH 557,147.40
TOTAL 557,140.00
DIBULATKAN
HARGA JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6
I. PEKERJAAN PENDAHULUAN
1. Papan Nama Kegiatan 1.00 Ls 500,000.00 500,000.00
3. Pengukuran dan Pemasangan Bouwplank 1.00 Ls 2,000,000.00 2,000,000.00
2. Pembersihan Lokasi 1.00 Ls 1,500,000.00 1,500,000.00
4,000,000.00
II. PEKERJAAN TANAH DAN PASIR
1. Pekerjaan Galian Tanah Pondasi 14.88 M³ 139,490.00 2,074,913.75
2. Urugan Tanah Kembali 4.96 M³ 106,490.00 528,012.92
3. Urugan Tanah Humus 16.80 M³ 688,290.00 11,563,272.00
4. Urugan Pasir Bawah Pondasi 1.45 M³ 1,780,790.00 2,582,145.50
5. Urugan Pasir Dibawah Lantai 5.60 M³ 1,780,790.00 9,972,424.00
26,720,768.17
III. PEKERJAAN BETON DAN PASANGAN
1. Pas. Anstamping Batu Kosong 4.35 M³ 2,401,110.00 10,444,828.50
2. Pas. Pondasi Batu Kali 1:4 7.29 M³ 11,430,310.00 83,326,959.90
3. Cor lantai Beton Tumbuk 3.36 M³ 15,308,350.00 51,436,056.00
4. Cor Sloof 10/15 Meja 0.24 M³ 19,270,880.00 4,625,011.20
5. Cor Kolom Praktis 10/10 Meja 0.13 M³ 18,392,280.00 2,354,211.84
6. Cor Balok 10/15 Meja 0.24 M³ 20,265,990.00 4,863,837.60
7. Cor Meja Beton Bertulang T : 10 cm 2.56 M³ 20,049,570.00 51,326,899.20
8. Pas. Dinding Bt Tela 1 : 4 14.90 M² 2,077,640.00 30,957,874.82
9. Pek. Plesteran 1 : 3 25.60 M² 557,140.00 14,262,784.00
253,598,463.06
IV. PEKERJAAN BESI
1. Pek. Tiang Besi Gip dia.2" 49.50 M¹ 542,050.00 26,831,475.00
2. Pek. Rangka Kuda - Kuda Besi Hollow 40.40.2 mm 195.92 M¹ 250,010.00 48,980,709.15
3. Pek. Gording Besi Hollow 40.40.2 mm 168.00 M¹ 250,010.00 42,001,680.00
4. Pek. Rangka Dinding Besi Hollow 40.40.2 mm 127.90 M¹ 250,010.00 31,976,279.00
5. Pek. Kusen Besi Hollow 40.40.2 mm 5.50 M¹ 250,010.00 1,375,055.00
6. Pas. Pintu Rangka Besi Hollow 40.40.2 mm 12.64 M¹ 250,010.00 3,160,126.40
7. Pas. Kawat Ram Pintu 1.08 M² 250,010.00 270,010.80
8. Pas. Agronet 132.21 M² 15,000.00 1,983,150.00
9. Pas. Penutup Atap Plastik UV 122.90 M² 18,500.00 2,273,650.00
158,852,135.35
V. PEKERJAAN SANITAIR
1. Pipa Pemasukan PVC Ø 1" 22.00 M¹ 152,310.00 3,350,820.00
2. Pas. Pipa Pembuangan PVC 2" AW 37.54 M¹ 138,120.00 5,185,024.80
3. Kran Air Ø 1" 2.00 Bh 142,000.00 284,000.00
4. Pas. Floar Drain 12.00 Bh 72,740.00 872,880.00
9,692,724.80
VI. PEKERJAAN AKHIR
1. Pek. Pembersihan Akhir 1.00 Ls 1,500,000.00 1,500,000.00
1,500,000.00
Alamat : Kantor Dinas - Dinas Otonom Provinsi Papua Gedung B Lantai 3 Jl. Raya Kotaraja - Jayapura Telp : (0967) 583156
Faxs ; (0967) 585501
Terbilang : Empat ratus sembilan puluh sembilan juta delapan ratus ribu rupiah.