2. Kerikil
Kerikil Sungai Pilihan/ Koral M3 230,000.00 170.37
Kerikil Sungai Tersaring M3 228,400.00
Kerikil Sungai Tak Tersaring M3 228,400.00
Batu Pecah 0,5 - 1 Cm (Spilt) M3 354,500.00 262.593
Batu Pecah 1 - 2 (Spilt) M3 354,500.00 262.593
Batu Pecah 2 - 3 (Spilt) M3 354,500.00 262.593
Batu Pecah 3 - 5 (Spilt) M3 354,500.00 262.593
Batu Pecah 5 - 7 (Spilt) M3 354,500.00 262.593
3. Batu - Batuan
Batu Utuh, Batu Kali, Batu Gunung M3 230,000.00
Batu Karang M3 200,000.00
Batu Andesit Bintik 30 x 30 cm M2 220,000.00
Batu Andesit Bintik 20 x 40 cm M2 220,000.00
Batu Sikat Motif Kecil Ktg 70,000.00
Batu Sikat Motif Besar Ktg 80,000.00
4. Batu Cetak :
Batu Bata Ukuran 5 x 11 x 22 cm Bh 800.00
Batu Bata Ukuran 5 x 9 x 22 cm Bh 700.00
Batu Bata Ukuran 5 x 7 x 22 cm Bh 500.00
Batako 9 cm Bh 3,433.33
Batako 10 cm Bh 3,919.17 700 Bh
2. Semen
Semen Pc (50 Kg) Zak 78,000.00 1,560 /Kg
Semen Warna/ Putih Kg 2,500.00 88,367 /Zak
Halaman - 02
HARGA
NO. UPAH KERJA / BAHAN SATUAN KETERANGAN
(Rp)
1 2 3 4 5
3. Bahan Atap
Seng Gelombang BJLS 0.20 Lbr 47,000.00
Seng Gelombang BJLS 0.18 Lbr 39,783.00
Genteng Metal (Multi Roof) T= 0,3 mm, 2 Susun Lbr 78,800.00 0,800 x 0,770
Genteng Metal (Sakura Roof) T= 0,3 mm, 2 Susun Lbr 31,500.00
Seng Plat BJLS 0.20 Lbr 44,600.00
Atap Zincalume 80 x 170 cm, T= 0,25 mm Lbr 84,000.00
5. Bahan Kayu
Balok 6/16 x 4 m (Kayu Kelas I), Kayu Lasi M3 3,500,000.00
Balok 6/16 x 4 m (Kayu Kelas II) M3 2,050,000.00
Balok 8/12 x 4 m (Kayu Kelas II) M3 2,050,000.00
Balok 6/10 x 4 m (Kayu Kelas II) M3 2,050,000.00
Balok 5/7 x 4 m (Kayu Kelas II) M3 2,050,000.00
Balok 5/7 x 4 m (Kayu Kelas III) M3 1,700,000.00
Kayu Bakesting (Kayu Kelas III) M3 1,600,000.00
Papan Palapi M3 2,050,000.00
Papan (Kayu Kelas II) M3 2,050,000.00
Papan Mall (Kayu Kelas III) M3 1,600,000.00
Dolken Kayu Galam Ø 8 -10 Cm/ 4 M' Btg 6,000.00
6. Bahan Bambu
Bambu Besar 15 - 20 Cm Btg 15,000.00
Bambu Sedang 10 - 15 Cm Btg 10,400.00
Bambu Kecil 5 - 10 Cm Btg 8,000.00
Bahan Alumunium :
Kusen Alumunium Open Back 4" x 1,3/4" M1 79,166.67 475,000.00
Kusen Alumunium Tutup Polos 4" x 1,3/4" M1 33,333.33 200,000.00
Profil Alumunium Curtain Wall 4,5 x 10 cm, Coating Putih M1 134,750.00 808,500.00
Profil Alumunium Curtain Wall 5 x 10 cm, Coating Putih M1 162,250.00 973,500.00
Profil Alumunium (Tutup Curtain Wall) 2 x 5 cm, Coating Putih M1 75,000.00 450,000.00
Daun Pintu Aluminium Rangka Kecil M2 1,000,000.00
Daun Pintu Aluminium Rangka Besar M2 1,800,000.00
Slimar Alumunium 3/8 M1 58,000.00 untuk jendela
Slimar Alumunium 3/10 M1 74,000.00 untuk pintu
Allumunium Strip Lebar 8 cm M1 25,000.00
Allumunium Strip Lebar 10 cm M1 31,000.00
Cord - Kanal C Tebal = 1 mm Btg 120,000.00 20,000.00
Reng - Kanal U Tebal = 0,6 mm Btg 115,000.00 19,166.67
Braket L Bh 2,000.00
Alcopanel (Alumunium Composite Panel), Seven Type PPDF M2 368,500.00
Jendela Nako Unit 150,000.00
9. Bahan Kawat
Kawat Ikat Beton/ Bendrat Kg 25,000.00
Kawat Duri (50 m) 4 Kg Roll 156,250.00 3,125.00
Kawat Las Dos 150,000.00
Kawat Las LB (5 Kg) Kg 128,000.00 640,000.00 /5 Kg
Kawat Las Listrik Kg 40,000.00
Kawat Las RB (5 Kg) Kg 60,000.00 460,000.00 /5 Kg
Pipa Gip :
Diameter 1/2" Btg 44,365.00 7,394.17 /M1
Diameter 3/4" Btg 66,607.00 10,633.33 /M1
Diameter 1" Btg 126,000.00 15,491.67 /M1
Diameter 1,5" Btg 135,000.00 22,500.00 /M1
Diameter 3" Btg 155,000.00 25,833.33 /M1
Knie Gip 1/2" Bh 9,500.00 1,583.33 /M1
Double Niple 1" Bh 8,900.00 1,483.33 /M1
Clame Sadle 1/2"-3" Bh 51,500.00 8,583.33 /M1
Tee Gip 1/2" Bh 5,900.00 1,475.00
Socket Drat Gip 1/2" Bh 4,700.00 783.33 /M1
Hanger + Support Pipa GIP 4" Set 140,000.00 23,333.33
Hanger + Support Pipa GIP 3" Set 120,000.00 20,000.00
Hanger + Support Pipa GIP 2" Set 100,000.00 16,666.67
Hanger + Support Pipa GIP 3/4" Set 85,000.00 14,166.67
Hanger + Support Pipa GIP 1/2" Set 65,000.00 10,833.33
Cat Tembok :
Cat Tembok & Plafond (Interior) Kg 61,600.00
Cat Tembok Wathersield (Exterior) Kg 97,650.00
Cat Tembok Metrolait Kg 27,900.00 102,500.00
Cat Tembok Paragon (20 Kg) Kg 25,800.00 357,000.00 Pail
Cat Tembok Cathylac Kg 21,600.00
Plamur Tembok Kg 12,800.00 30,500.00 Klg
Dempul Tembok Kg 32,650.00
Polimer Mortar Kg 30,000.00
EAL Water Proofing Epoxy (02) Kg 160,000.00
Cat Besi :
Meny Seng Kg 57,000.00
Meny Besi Kg 57,000.00
Cat Besi Kg 55,000.00
Cat Coating Clear (Glotex) Kg 28,000.00
Cat Dicco Kg 58,800.00
Cat Atap Seng Kg 87,000.00
Cat Atap dan Genting Kg 26,250.00 87,500.00 Klg
Cat Vernis Kg 35,100.00 87,500.00 Klg
Cat Politur Kg 32,000.00 87,500.00 Klg
Politur Jadi Kg 34,500.00 87,500.00 Klg
Pipa Listrik :
Pipa listrik 5/8" Btg 4,500.00 1,125.00
Pipa Conduit Hight Impact Ø 20 mm Btg 4,650.00 1,162.50
Fleksible 20 mm M1 6,000.00
Saklar/ Sekring :
Saklar tunggal, 10 A, 250 VAC (Setara Panasonic) Bh 28,750.00
Saklar Seri, 10 A, 250 VAC (Setara Panasonic) Bh 38,500.00
Saklar Triple, 10 A, 250 VAC (Setara Panasonic) Bh 44,000.00
Stop Kontak 2 Phase, 16 A Bh 30,800.00
Stop Kontak 1 Phase, 13 A Bh 24,200.00
Switch Socket AC + Indikator Lamp 16 A Bh 25,850.00
Exhaust Fan Set 250,000.00
Fitting Tempel Kotak Bh 10,385.00
Box Sekring 1 Fase Bh 20,350.00
Box Sekring 2 Fase Bh 27,600.00
Sekring Kas Kosong DN 2 G Bh 41,250.00
Sekring Kas Kosong DN 3 G Bh 60,000.00
Sekring Kas Kosong DN 4 G Bh 63,250.00
T Duss Bh 4,200.00
Elbow Bh 420.00
Las dop Bh 1,200.00
Inbow Does Bh 5,000.00
Mangkok Saklar/ Stop Kontak Bh 1,500.00
Klem Biasa Bh 120.00
Lampu Pijar :
Lampu 25 Watt Bh 6,750.00
10 - 40 Watt Bh 12,000.00
60 - 100 Watt Bh 13,500.00
Lampu SL 23 Watt Bh 44,550.00
Lampu SL 20 Watt Bh 44,550.00
Lampu SL 18 Watt Bh 40,825.00
Lampu SL 15 Watt Bh 34,500.00
Lampu SL 10 Watt Bh 32,200.00
Lampu SL 11 Watt Bh 32,200.00
Lampu SL 8 Watt Bh 35,075.00
Lampu SL 5 Watt Bh 11,500.00
Balon Lampu TL :
TL Biasa 20 Watt Philips Bh 47,250.00
TL Biasa 40 Watt Philips Bh 78,750.00
TL Blok Bambu 20 Watt Set 105,000.00
TL Blok Bambu 40 Watt Set 153,268.50
Lampu TL (Perset) :
10 - 20 Watt (Model keranjang) Set 45,000.00
20 - 40 Watt (Model keranjang) Set 75,000.00
40 - 60 Watt (Model keranjang) Set 125,000.00
Lampu RM (Perset) :
Lampu RMI TL 2 x 18 Watt, Stainlees Grill Set 350,000.00
Lampu RM TL 2 x 20 Watt Komplit, Stainlees Grill Set 395,000.00
Lampu RM TL 2 x 18 Watt Komplit, Glass ALML Set 375,000.00
Kran Air :
Kran Air 1/2 " Bh 40,625.00
Kran Leher Angsa Unit 325,000.00
Kran Shower Panas dan Dingin Bh 437,500.00
Kran Wudhu Unit 275,000.00
19 Sewa Peralatan
Sewa Welding Hari 200,000.00
Concrete Mixer Hari 300,000.00
Concrete Vibrator Hari 225,000.00
Stamper Hari 55,000.00
Peralatan/ Alat Bantu Set 39,000.00
#REF!
Dibuat Oleh
#REF!
#REF!
#REF!
#REF!
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-12
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-13
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-14
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-15
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-16
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.200 80,000.00 16,000.00
Tukang Batu L.02 Org/Hari 0.100 125,000.00 12,500.00
Kepala Tukang L.03 Org/Hari 0.010 148,000.00 1,480.00
Mandor L.04 Org/Hari 0.010 115,000.00 1,150.00
JUMLAH TENAGA KERJA 31,130.00
B. BAHAN :
Semen Portland - Kg 3.250 1,560.00 5,070.00
JUMLAH HARGA BAHAN 5,070.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 36,200.00
E. Overhead & Profit 10% x D 3,620.00
F. Harga Satuan Pekerjaan(D + E) 39,820.00
Halaman-17
VIII. AHSP - A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
Halaman-18
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-19
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-20
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-21
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-22
A. TENAGA :
Pekerja L.01 Org/Hari 0.040 80,000.00 3,200.00
Tukang Kayu L.02 Org/Hari 0.060 125,000.00 7,500.00
Kepala Tukang L.03 Org/Hari 0.016 148,000.00 2,368.00
Mandor L.04 Org/Hari 0.003 115,000.00 345.00
JUMLAH TENAGA KERJA 13,413.00
B. BAHAN :
Politur - Ltr 0.150 32,000.00 4,800.00
Politur Jadi - Ltr 0.372 34,500.00 12,834.00
Ampelas - Lbr 2.000 4,875.00 9,750.00
JUMLAH HARGA BAHAN 27,384.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 40,797.00
E. Overhead & Profit 10% x D 4,079.70
F. Harga Satuan Pekerjaan(D + E) 44,876.70
Halaman-23
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-24
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-25
JUMLAH TENAGA KERJA 10,752.40
B. BAHAN :
Cat Dasar - Kg 0.100 25,800.00 2,580.00
Cat Penutup - Kg 0.260 25,800.00 6,708.00
JUMLAH HARGA BAHAN 9,288.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 20,040.40
E. Overhead & Profit 10% x D 2,004.04
F. Harga Satuan Pekerjaan(D + E) 22,044.44
Halaman-26
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-27
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-28
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-29
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-30
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-31
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-32
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-33
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-34
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-35
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-36
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-37
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-38
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-39
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-40
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-41
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-42
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-43
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-44
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-45
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-46
B. BAHAN :
Rumput Jepang (Rumput Lokal) - M2 1.100 60,500.00 66,550.00
JUMLAH HARGA BAHAN 66,550.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 71,700.00
E. Overhead & Profit 10% x D 7,170.00
F. Harga Satuan Pekerjaan(D + E) 78,870.00
Halaman-47
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-48
JUMLAH HARGA BAHAN -
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 14,230.00
E. Overhead & Profit 10% x D 1,423.00
F. Harga Satuan Pekerjaan(D + E) 15,653.00
SYALDI, ST
Direktur
Halaman-49
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
IV.2 AHSP - A.4.1.1 HARGA SATUAN PEKERJAAN BETON (Pembesian dan Bekisting)
Halaman-50
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 10 mm - Kg 10.500 12,830.90 134,724.47
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 138,474.47
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 154,320.47
E. Overhead & Profit 10% x D 15,432.05
F. Harga Satuan Pekerjaan(D + E) 169,752.52
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 10 mm (Harga Satuan Pekerjaan / 10) 16,975.25
4. Besi Beton (Polos/ Ulir) Ǿ 12 mm
A. TENAGA :
Pekerja L.01 Org/Hari 0.070 80,000.00 5,600.00
Tukang Besi L.02 Org/Hari 0.070 125,000.00 8,750.00
Kepala Tukang L.03 Org/Hari 0.007 148,000.00 1,036.00
Mandor L.04 Org/Hari 0.004 115,000.00 460.00
JUMLAH TENAGA KERJA 15,846.00
B. BAHAN :
a. Besi Beton (Polos/ Ulir) Ǿ 12 mm - Kg 10.500 11,273.96 118,376.55
b. Kawat Beton - Kg 0.150 25,000.00 3,750.00
JUMLAH HARGA BAHAN 122,126.55
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 137,972.55
E. Overhead & Profit 10% x D 13,797.26
F. Harga Satuan Pekerjaan(D + E) 151,769.81
Untuk Pembesian 1 Kg dengan Besi Polos atau Besi Ulir Ǿ 12 mm (Harga Satuan Pekerjaan / 10) 15,176.98
Halaman-51
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-52
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-53
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-54
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-55
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-56
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-57
B. BAHAN :
Tanah Hitam (Tanah Subur) - M3 1.200 120,000.00 144,000.00
JUMLAH HARGA BAHAN 144,000.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 166,875.00
E. Overhead & Profit 10% x D 16,687.50
F. Harga Satuan Pekerjaan(D + E) 183,562.50
Halaman-58
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-59
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-60
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-61
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-62
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-63
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-64
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-65
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.135 80,000.00 10,800.00
Tukang Pipa L.02 Org/Hari 0.225 125,000.00 28,125.00
Kepala Tukang L.03 Org/Hari 0.023 148,000.00 3,404.00
Mandor L.04 Org/Hari 0.007 115,000.00 805.00
JUMLAH TENAGA KERJA 43,134.00
B. BAHAN :
Pipa GIP 3" - M1 1.200 25,833.33 31,000.00
Perlengkapan 35% Harga Pipa - Ls 0.350 10,850.00 3,797.50
JUMLAH HARGA BAHAN 34,797.50
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 77,931.50
E. Overhead & Profit 10% x D 7,793.15
F. Harga Satuan Pekerjaan(D + E) 85,724.65
Halaman-66
B. BAHAN :
Pipa PVC 2,5" - M1 1.200 15,625.00 18,750.00
Perlengkapan 35% Harga Pipa - Ls 0.350 6,562.50 2,296.88
JUMLAH HARGA BAHAN 21,046.88
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 46,859.88
E. Overhead & Profit 10% x D 4,685.99
F. Harga Satuan Pekerjaan(D + E) 51,545.86
Halaman-67
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-68
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-69
F. Harga Satuan Pekerjaan(D + E) 214,802.50
Halaman-70
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-71
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-72
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-73
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-74
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-75
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-76
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-77
X. AHSP - A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
Halaman-78
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-79
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-80
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-81
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.150 80,000.00 12,000.00
Tukang Alumunium L.02 Org/Hari 0.070 125,000.00 8,750.00
Kepala Tukang L.03 Org/Hari 0.007 148,000.00 1,036.00
Mandor L.04 Org/Hari 0.006 115,000.00 690.00
JUMLAH TENAGA KERJA 22,476.00
B. BAHAN :
Nok Zincalume, Tebal 0,25 mm - M1 1.100 51,370.00 56,507.00
Paku Seng Kepala Kecil - Kg 0.040 25,000.00 1,000.00
JUMLAH HARGA BAHAN 57,507.00
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 79,983.00
E. Overhead & Profit 10% x D 7,998.30
F. Harga Satuan Pekerjaan(D + E) 87,981.30
Halaman-82
XI. AHSP - A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
Halaman-83
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-84
HARGA SATUAN JUMLAH HARGA
No. URAIAN KODE SATUAN KOEFISIEN
(Rp). (Rp).
1 2 3 4 5 6 7 = (5x6)
A. TENAGA :
Pekerja L.01 Org/Hari 0.700 80,000.00 56,000.00
Tukang Kayu L.02 Org/Hari 2.100 125,000.00 262,500.00
Kepala Tukang L.03 Org/Hari 0.210 148,000.00 31,080.00
Mandor L.04 Org/Hari 0.035 115,000.00 4,025.00
JUMLAH TENAGA KERJA 353,605.00
B. BAHAN :
Papan Kayu Kelas II - M3 0.025 2,050,000.00 51,250.00
Paku 1 cm - 2,5 cm - Kg 0.030 20,000.00 600.00
Lem Kayu - Kg 0.500 15,491.00 7,745.50
Playwood 122 Cm x 244 Cm x 4 mm - Lembar 1.000 101,000.00 101,000.00
JUMLAH HARGA BAHAN 160,595.50
C. PERALATAN :
- - - - -
JUMLAH HARGA ALAT -
D. Jumlah (A+B+C) 514,200.50
E. Overhead & Profit 10% x D 51,420.05
F. Harga Satuan Pekerjaan(D + E) 565,620.55
Halaman-85
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-86
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-87
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-88
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-89
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-90
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-91
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-92
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-93
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA 0
KEGIATAN 0
PEKERJAAN 0
LOKASI 0
SUMBER DANA 0
TAHUN ANGGARAN 0
Halaman-94
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-95
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-96
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-97
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA
KEGIATAN
PEKERJAAN
LOKASI
SUMBER DANA
TAHUN ANGGARAN
Halaman-98
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-99
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Halaman-100
Mandor L.04 Org/Hari 0.167 115,000.00 19,147.50
JUMLAH TENAGA KERJA 374,720.83
B. BAHAN :
Halaman-101
1. LUAS LANTAI 1 :
- 36 x 46.2 = 1,663.20
- 21 x 3 = 63.00
- 36 x 6 = 216.00
- Lingkaran Ø 12 m 0,25*3,14*12*12 113.040 = 56.520
1,998.72
2. LUAS LANTAI 2 :
- 36 x 46.2 = 1,663.20
- 21 x 3 = 63.00
- 36 x 6 = 216.00
- Lingkaran Ø 12 m 0,25*3,14*12*12 113.040 = 56.520
1,998.72
3. LUAS LANTAI 3 :
- 36 x 46.2 = 1,663.20
- 21 x 3 = 63.00
- 36 x 6 = 216.00
- Lingkaran Ø 12 m 0,25*3,14*12*12 113.040 = 56.520
1,998.72
4. LUAS VOID :
- 18 x 32.1 = 577.80
- 6 x 6 = 36.00
613.80
M2 TENGAH
M2 DEPAN
M2 BELAKANG
M2 BUNDARAN
M2
M2 TENGAH
M2 DEPAN
M2 BELAKANG
M2 BUNDARAN
M2
M2 TENGAH
M2 TENGAH
M2
- 613.80
M2 5,000,000
26,911,800,000 kali 5 juta per m2
M2