Anda di halaman 1dari 140

Err:522

Err:522
STANDAR HARGA SATUAN UPAH DAN BAHAN BANGUNAN

1. DAFTAR HARGA SATUAN UPAH


NO. JENIS UPAH SATUAN HARGA KET.
(Rp.)

1 2 3 4 5
1 Mandor OH 174,800.00
2 Pekerja OH 110,700.00
3 Pekerja Terlatih OH
4 Pekerja di Hutan OH
5 Pemasak Aspal OH
6 Tukang OH 151,500.00
7 Kepala Tukang OH -
8 Tukang OH 151,500.00
9 Kepala Tukang OH -
10 Tukang OH 151,500.00
11 Kepala Tukang OH -
12 Tukang Las OH 151,500.00
13 Kepala Tukang Las OH
14 Tukang Pelitur OH 151,500.00
15 Tukang Cat OH 151,500.00
16 Kepala Tukang OH -
17 Tukang Pipa OH 151,500.00
2. DAFTAR HARGA SATUAN BAHAN
2.1. Bahan Pasangan
NO. JENIS BAHAN / BARANG SATUAN HARGA KET.
(Rp.)
1 2 3 4 5
1 Batu Kali Alam M3 210,700.00
2 Batu Gunung W = 500 - 700 Kg M3
3 Krikil Sungai/Royalty (MR 012) M3
Batu Pecah (Manual) -
Batu Belah M3 185,000.00
4 Batu Pecah 5-7 cm M3 153,000.00
5 Batu Pecah 3-5 cm M3 428,300.00
6 Batu pecah 2 - 3 cm M3 400,000.00 1,400,000.00
7 Batu Pecah 1-2 cm M3 445,800.00
8 Batu Pecah 0.5-1 cm M3 360,000.00
Batu Pecah (menggunakan Mesin) -
9 Kerikil Pecah 3-5 cm M3
10 Batu Pecah 2-3 cm M3 -
11 Batu Pecah 1-2 cm M3
12 Batu Pecah 0.5-1 cm M3
13 Batu Kali Utuh M3
14 Batu Kali Belah M3
15 Filler (abu batu) M3
16 Kerikil alam 5-7 cm M3
17 Kerikil alam 3-5 cm M3
18 Kerikil alam 2-3 cm M3
19 Kerikil alam 1-2 cm M3
20 Kerikil alam 0.5-1 cm M3
20 Kerikil/koral 0.5-1 cm M3
21 Pasir cor M3 214,800.00 751,800.00
22 Pasir pasangan M3 207,500.00 726,250.00
23 Pasir urug M3 188,900.00 661,150.00
24 Sirtu M3 187,600.00 656,600.00
25 Tanah Urug M3 67,300.00 235,550.00
26 Tanah Urug Pilihan M3 187,600.00 656,600.00
27 Bata Merah Buah 1,500.00
28 Kapur Pasangan M3 500.00
29 Kapur Gamping Kg 6,200.00
30 Aspal (Aspal Concrete/AC) Kg 12,000.00
31 Aspal (Medium Curring/MC) Kg 10,000.00
32 Aspal emulsi Liter 10,000.00
33 Aditif 113,000.00
34 Grevel M3 155,000.00
35 Button Granular Asphalt (BUTAS) Kg
36 Box Culvert W 1 Standar Bina Marga (K 300) bh 4,343,000.00
P= 1,3 m

37 Box Culvert W 1,5 Standar Bina Marga (K bh 8,437,000.00


300) P= 1,3 m

2.2. Bahan Pasangan ( material non Gal. C ) -


1 Semen Warna Kg 16,000.00
2 Semen Warna Kwalitas Baik Kg 27,000.00
3 Portland Pozzoland Cement (Tiga Roda) 40 Zak 55,000.00
Kg

4 Portland Pozzoland Cement (Geresik) 40 Kg Zak 55,000.00


5 Semen Zak 60,000.00
6 Bentonit Zak 250,000.00

2.3. Bahan Atap


1 Genteng Kaca Pejaten 3 mm buah
2 Genteng Kaca Pejaten 5 mm buah
3 Genteng Kaca Kodok 3 mm buah
4 Genteng Kaca Kodok 5 mm buah
5 Genteng Pejaten Lokal buah
6 Bubungan Genteng Pejaten Lokal buah
7 Genteng Pejaten Non Lokal buah
8 Bubungan Genteng Pejaten Non Lokal buah
9 Genteng Silang/Kodok Lokal buah
10 Bubungan Genteng Silang/Kodok Lokal buah

11 Genteng Silang/Kodok Non Lokal buah


12 Bubungan Genteng Silang/Kodok Non Lokal buah

13 Genteng Beton manual buah


14 Bubungan Genteng Beton Manual buah
15 Genteng Pres Beton buah
16 Bubungan Genteng Pres Beton buah
17 Genteng Keramik buah
18 Bubungan Genteng Keramik buah
19 Asbes Gelombang 1,80 x 0,80 x 4 mm lembar
20 Asbes Gelombang 2,10 x 0,80 x 4 mm lembar
21 Bubungan Asbes Gelombang 1,8 x 0,4 x 4 set
mm

22 Seng Gelombang BJLS 18 lembar 47,000.00


23 Seng Gelombang BJLS 20 lembar 60,000.00
24 Seng Gelombang BJLS 25 lembar 80,000.00
25 Seng Gelombang BJLS 30 lembar 95,000.00
26 Seng Plat BJLS 18 lembar 64,000.00
27 Seng Plat BJLS 20 lembar 74,000.00
28 Seng Plat BJLS 25 lembar 61,000.00
29 Seng Plat BJLS 30 lembar 79,000.00
30 Genteng Multiroof M2 47,000.00
31 Rangka Atap Baja Ringan M2 71,000.00
32 Spandek 3 mm lebar 70 cm meter 37,000.00
33 Spandek 3,5 mm lebar 70 cm meter 58,000.00
34 Spandek 4 mm lebar 70 cm meter 63,000.00
2.4. Baja Ringan -
RANGKA C75, RENG B30 DAN TALANG -
GALVALUM
Polos (Colour) -
1 Reng B-30 T=0,45 Galv (P= 6 meter) Batang
2 Reng B-30 T=0,40 Galv (P= 6 meter) Batang
3 Rangka C-7575 Galv (P= 7 meter) Batang
4 Rangka C-7565 Galv (P= 6 meter) Batang
5 Rangka C-75100 Galv (P= 7 meter) Batang
BAUT-BAUT BAJA RINGAN -
1 Skrew # 12 (baut kuda-kuda) @ 800 Pc Pc
2 Skrew # 10 (baut reng) @ 1.000 Pc Pc
3 Baut Listplang 12 # T1 x 1/2 @ 200 Pc Pc

4 Fisher (S10) @ 400 Pc Pc


5 Taping (Pasangan Fisher S 10) @ 400 Pc Pc

6 Dinabolt 10 x 65 @ 150 Pc Pc
7 Baut SDS 12 x 50 (Baut spandek) @ 200 Pc Pc 2,200.00

7 Baut spandek Kg 30,000.00


8 Ripet 440 @ 1000 Pc Pc
9 Ripet 550 @ 1000 Pc Pc
ALAT KERJA BAJA RINGAN -
1 Bor Maktek type 601 Unit
2 Bor Beton Merk Makita type HR 2020 Unit
3 Srew Driver M10 bh
4 Mata Bor Beton Dia. 10 mm SDS Unit
5 Gunting Baja Ringan (Domax) bh
RANGKA C85, RENG B41 GALVALUM -
(Eceran Khusus)
1 Rangka C8585 Panjang @ 9 meter Batang
2 Rangka C8565 Panjang @ 9 meter Batang
3 Reng B41 Panjang @ 9 meter Batang
4 Upah Pasang M2
2.5. Bahan Kayu -
1 Papan Kayu Klas I m3
2 Balok Kayu Klas I m3
3 Papan Kayu Klas II m3 4,312,400.00
4 Balok Kayu Klas II m3 4,312,400.00
5 Papan Kayu Klas III m3 5,501,200.00
6 Balok Kayu Kelas III m3 5,501,200.00
7 Papan kayu Begisting m3 5,501,200.00
8 Dolken diamater 8-10cm P=4m Batang 26,200.00
2.6. Bahan Bambu
1 Bambu Besar >= 012,5 cm - 6 cm batang 63,000.00
2 Bambu Sedang >= 010 cm - 6 cm batang 47,000.00
3 Bambu Kecil>=7cm - 6m batang 31,000.00
4 Bambu Petung Ø 14 Cm Batang 332,000.00
5 Bambu Tutul Batang 33,000.00
6 Bedek Kulitan M2 55,000.00
7 Bedek 1/2 Kulitan M2 14,000.00
8 Bedek biasa M2 10,000.00
9 Bedek Pagar M2 22,000.00
10 Bambu Batang 40,000.00
2.7. Bahan Cetak -
1 Loster Beton 10x30cm Buah 26,000.00
2 Loster Beton 20x20cm Buah 16,000.00
3 Loster Beton 30x30cm Buah 26,000.00
4 Loster Pres 10x20cm Buah 26,000.00
5 Loster Pres 20x20cm Buah 31,000.00
6 Loster Keramik 20x20cm Buah
7 Loster Keramik 20x40cm Buah
8 Loster Keramik 30x30cm Buah
9 Loster Keramik 30x45cm Buah
10 Loster Keramik 40x40cm Buah
11 Loster Kaca (Glass Block ) 19x19 cm. Buah
12 Loster Batu Alam 20x20cm Buah
13 Loster Batu Alam 25x25cm Buah
14 Loster Batu Alam 30x30cm Buah
15 Loster Batu Alam 40x40cm Buah
16 Loster Batu Alam 50x50cm Buah
17 Loster Batu Alam 20x40cm Buah
18 Loster Batu Alam 30x60cm Buah
19 Loster Batu Alam Model Bundar diamater Buah
30cm

20 Loster Batu Alam Model Bundar diamater Buah


40cm

21 Batu Alam Tempel Kualitas Baik M2


22 Batu Alam Tempel Kualitas Sedang (standar) M2

23 Batu Alam Tempel Kualitas Biasa M2


24 Batu Sikat ( telah dicetak atau siap pasang) M2

25 Batu Coral kualitas baik Kg.


26 Batu Coral kualitas sedang Kg.
27 Batu Coral kualitas biasa Kg.
28 Lampion Batu Alam ukuran 20x 20cm Buah
29 Lampion Batu Alam ukuran 25cm x 25cm Buah

30 Lampion Batu Alam ukuran 30cm x 30cm Buah

31 Ornamen Relief Batu Alam M2


32 Batu Granit M2
33 Buis Beton 1/2 Lingkaran Ø 20 panjang 1 m Buah 21,000.00

34 Buis Beton 1/2 Lingkaran Ø 30 panjang 1 m Buah 31,000.00

35 Buis Beton 1/2 Lingkaran Ø 40 panjang 1 m Buah 42,000.00

36 Buis Beton Ø 20 Cm panjang 1 m Buah 52,000.00


37 Buis Beton Ø 30 Cm panjang 1 m Buah 72,000.00
38 Buis Beton Ø 40 Cm panjang 0,50 m Buah 47,000.00
39 Buis Beton Ø 50 Cm panjang 0,50 m Buah 57,000.00
40 Buis Beton Ø 60 Cm panjang 0,50 m Buah 62,000.00
41 Buis Beton Ø 80 Cm panjang 0,50 m Buah 250,000.00
42 Buis Beton Ø 90 Cm panjang 0,50 m Buah 95,000.00
43 Buis Beton Ø 100 Cm panjang 0,50 m Buah 110,000.00
44 Buis Beton Ø 30 Cm panjang 0,50 m Buah 128,000.00
(Konstruksi)

45 Buis Beton Ø 40 Cm panjang 0,50 m Buah 157,000.00


(Konstruksi)

46 Buis Beton Ø 50 Cm panjang 0,50 m Buah 184,000.00


(Konstruksi)

47 Buis Beton Ø 60 Cm panjang 0,50 m Buah 220,000.00


(Konstruksi)

48 Buis Beton Ø 70 Cm panjang 0,50 m Buah 240,000.00


(Konstruksi)

49 Buis Beton Ø 80 Cm panjang 0,50 m Buah 270,000.00


(Konstruksi)

50 Buis Beton Ø 90 Cm panjang 0,50 m Buah 300,000.00


(Konstruksi)

51 Buis Beton Ø100 Cm panjang 0,50 m Buah 325,000.00


(Konstruksi)
52 Batako ukuran 32 x 15 cm Buah 2,000.00
53 Batako ukuran 35 x 15 cm Buah 2,100.00
54 Batako ukuran 30 x 14 cm Buah 1,700.00
55 Paving Blok Cetak Presh T = 8 cm Buah 1,200.00
56 Paving Blok Bata T = 6 cm Buah 1,000.00
57 Paving Blok Biasa T = 6 cm Buah 800.00
Tutup buis Ø 60 cm Buah 57,000.00
Tutup buis Ø 80 cm Buah 250,000.00

2.8. Bahan Lantai -


1 Keramik Dinding Kwalitas Sedang M2 79,000.00
2 Keramik Dinding KM 20x25 Kwalitas Baik M2 90,000.00

3 Keramik Lantai KM 20x20 Kwalitas Sedang M2 69,000.00

4 Keramik Lantai KM 20x20 Kwalitas Baik M2 79,000.00

5 Keramik Lantai Kwalitas Sedang M2 74,000.00


6 Keramik Lantai 30x30 Kwalitas Baik M2 79,000.00
7 Keramik Lantai 40x40 Kwalitas Sedang M2 74,000.00

8 Keramik Lantai 40x40 Kwalitas Baik M2 102,000.00


9 Keramik Dinding 20x40 Kwalitas Sedang M2 164,000.00

10 Keramik Lantai 25x40 Kwalitas Baik M2 79,000.00


11 Keramik Lantai 50 x 50 kwalitas baik M2 79,000.00
12 Keramik Lantai 50 x 50 kwalitas sedang M2 84,000.00

13 Keramik Lantai 60x60 Kwalitas Sedang M2

14 Keramik Lantai 60x60 Kwalitas Baik M2


15 Keramik Lantai 30x60 Kwalitas Sedang M2

16 Keramik Lantai 30x60 Kwalitas Baik M2


17 Keramik Lantai 25x25 Kwalitas Sedang M2

18 Keramik Lantai 25x40 Kwalitas Baik M2


19 Keramik Motif Batu/Bata ukuran 40/40 M2
kwalitas baik

20 Keramik Motif Batu/Bata ukuran 40/40 M2


kwalitas sedang

21 Keramik Motif Batu/Bata ukuran 20/40 M2


kwalitas baik

22 Keramik Motif Batu/Bata ukuran 20/40 M2


kwalitas sedang

23 Keramik Motif Batu/Bata ukuran 30/60 M2


kwalitas baik

24 Keramik Motif Batu/Bata ukuran 30/60 M2


kwalitas sedang

25 List Keramik ukuran 2 x 20 kwalitas baik Buah 5,000.00

26 List Keramik ukuran 2 x 20 kwalitas sedang Buah 2,000.00

27 List Keramik ukuran 6 x 20 kwalitas baik Buah 12,000.00


28 List Keramik ukuran 6 x 20 kwalitas sedang Buah 7,000.00

29 List Keramik ukuran 6 x 25 kwalitas baik Buah 13,000.00

30 List Keramik ukuran 6 x 25 kwalitas sedang Buah 9,000.00

31 List Keramik ukuran 7x20 kwalitas baik Buah 18,000.00

32 List Keramik ukuran 7x20 kwalitas sedang Buah

33 List Keramik ukuran 7x25 kwalitas baik Buah

34 List Keramik ukuran 7x25 kwalitas sedang Buah

35 List Keramik ukuran 8 x 20 kwalitas baik Buah

36 List Keramik ukuran 8 x 20 kwalitas sedang Buah

37 List Keramik ukuran 8 x 25 kwalitas baik Buah

38 List Keramik ukuran 8 x 25 kwalitas sedang Buah

39 List Keramik ukuran 10x40 kwalitas baik Buah

40 List Keramik ukuran 10x40 kwalitas sedang Buah

41 Granit ukuran 40x40 M2


42 Granit ukuran 60x60 kualitas sedang M2
43 Granit ukuran 60x60 kualitas baik M2 isi 3
44 Granit ukuran 80x80 kualitas baik M2 isi 3
45 Granit ukuran 80x80 kualitas sedang M2 isi 3
46 Pasangan Batu Palimanan M2
2.9. Bahan Besi -
1 Besi Beton Ulir Kg 20,000.00
2 Besi Beton Polos Kg 20,050.00
3 Besi Siku 20x20x600 Lonjor
4 Besi Siku 30x30x600 Lonjor
5 Besi Siku 40x40x600 Lonjor
6 Besi Siku 50x50x600 Lonjor
7 Besi Siku 60x60x600 Lonjor
8 Besi Siku 70x70x600 Lonjor
9 Besi Siku 90x90x600 Lonjor
10 Besi Plat 0,8x122x244 Lembar
11 Besi Plat 1x122x244 Lembar
12 Besi Plat 1,2x122x244 Lembar
13 Besi Plat 1,6x1,22x244 Lembar
14 Besi Plat 2x122x244 Lembar
15 Besi Plat 3x122x244 Lembar
16 Besi Plat 4x122x244 Lembar
17 Plat Bordas (Kembang) 2x122x244 Lembar
Besi strip tebal 5 mm
18 Plat Baja Lembar 399,094.00
19 Baja Canal IWF 100 Kg
20 Baja Canal IWF 150-300 Impor Kg
21 Baja Canal IWF 100 Impor Lonjor
22 Plat Eyser 4 x 8 x 10 mm Lembar
23 Kanal UNP 100 Lonjor
24 GIP Med SNI Spindo 1" 3.2 mm Lonjor
25 BSP Med 1" x 2.5 mm Lonjor
26 BSP SCH40 Spindo 1" x 3.2 mm Lonjor
27 UNP 5 X 6 meter Lonjor
28 UNP 6,5 X 6 meter Lonjor
29 UNP 8 X 6 meter Lonjor
30 UNP 10 X 6 meter Lonjor
31 UNP 12 X 6 meter Lonjor
32 UNP 15 X 6 meter Lonjor
33 CNP 75 x 1.6 mm x 6 meter Lonjor
34 CNP 75 x 2 mm x 6 meter Lonjor
35 CNP 75 x 2.4 mm x 6 meter Lonjor
36 CNP 100 x 1.6 mm x 6 meter Lonjor
37 CNP 100 x 2 mm x 6 meter Lonjor
38 CNP 100 x 2.4 mm x 6 meter Lonjor
39 CNP 125 x 1.6 mm x 6 meter Lonjor
40 CNP 125 x 2 mm x 6 meter Lonjor
41 CNP 125 x 2.4 mm x 6 meter Lonjor
42 CNP 150 x 1.6 mm x 6 meter Lonjor
43 CNP 150 x 2 mm x 6 meter Lonjor
44 CNP 150 x 2.4 mm x 6 meter Lonjor
45 Elastomer Jenis 1 Buah
46 Elastomer Jenis 2 Buah
47 Elastomer Jenis 3 Buah
48 Expantion Tipe Join Asphaltic Plug meter
49 Expantion Join Tipe Rubber meter
50 Expantion Join Baja Siku meter
51 Kawat Ikat Beton Kg 35,000.00
52 Kawat Nyamuk Besi M2
53 Kawat Nyamuk Plastik M2
54 Kawat saringan pasir M2
55 Kawat Duri Rol
56 Pagar BRC 120x240cm. Buah
57 Tiang BRC 1,5"x120cm. Buah
58 Knop Tiang BRC 1,5" Buah
59 Kawat Bronjong digalvanisir (Kawat BWG) Kg

60 Kawat Gulungan 0,1 - 0,9 mm (Tembaga) Kg

61 Kawat Gulungan 1 - 4 mm (Tembaga) Kg


62 Kawat Bronjong pabrikasi lubang 8 x 10 Unit
Heavy Galv. Uk. 2.0 x 1.0 x 0.5 Ø 2.7
mm

63 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 2.0 x 1.0 x 0.5 Ø 3 mm

64 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 2.0 x 1.0 x 0.5
Ø 2.7 mm
65 Kawat Bronjong pabrikasi lubang 8 x 10 Unit
Heavy Galv. Uk. 3.0 x 1.0 x 0.5 Ø 2.7
mm

66 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 3.0 x 1.0 x 0.5 Ø 3 mm

67 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 3.0 x 1.0 x 0.5
Ø 2.7 mm

68 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 3.0 x 1.0 x 1.5 Ø 2.7
mm

69 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 3.0 x 1.0 x 1.5 Ø 3 mm

70 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 3.0 x 1.0 x 1.5
Ø 2.7 mm

71 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 4.0 x 1.0 x 0.5 Ø 2.7
mm

72 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 4.0 x 1.0 x 0.5 Ø 3 mm

73 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 4.0 x 1.0 x 0.5
Ø 2.7 mm

74 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 1.5 x 1.0 x 1.0 Ø 2.7
mm

75 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 1.5 x 1.0 x 1.0 Ø 3 mm

76 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 1.5 x 1.0 x 0.5
Ø 2.7 mm

77 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 2.0 x 1.0 x 1.0 Ø 2.7
mm

78 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 2.0 x 1.0 x 1.0 Ø 3 mm
79 Kawat Bronjong pabrikasi lubang 8 x 10 Unit
Heavy Galv & PVC Uk. 2.0 x 1.0 x 1.0
Ø 2.7 mm

80 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 3.0 x 1.0 x 1.0 Ø 2.7
mm

81 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv Uk. 3.0 x 1.0 x 1.0 Ø 3 mm

82 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 3.0 x 1.0 x 1.0
Ø 2.7 mm

83 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 4.0 x 1.0 x 1.0 Ø 2.7 mm

84 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv. Uk. 4.0 x 1.0 x 1.0 Ø 3 mm

85 Kawat Bronjong pabrikasi lubang 8 x 10 Unit


Heavy Galv & PVC Uk. 4.0 x 1.0 x 1.0
Ø 2.7 mm

86 Kawat Bronjong pabrikasi Heavy Galv. Ø 4 kg


mm

87 Kusen Aluminium tebal 1,2mm. Buah 170,000.00


88 Sekop Buah 90,000.00
89 Linggis Buah 196,000.00
90 Cangkul Buah 106,000.00
91 Cepang Buah 41,000.00
92 Palu Kecil Buah 35,875.00
93 Palu Sedang Buah 51,250.00
94 Palu Besar Buah 76,875.00
95 Hummer Kecil Buah 92,250.00
96 Hummer Sedang Buah 153,750.00
97 Hummer Besar Buah 290,075.00
96
Ember Buah 12,000.00
Ember kapasitas 25 liter Buah 75,000.00
97 Ganco Buah
98 Kunci Pipa Dia 2 " x 1/2 " Buah
99 Kunci Pipa Dia 3 " x 1/2 " Buah
100 Kunci Pipa Dia 4 " x 1/2 " Buah
101 Kunci Pipa Dia 6 " x 1/2 " Buah
102 Mata Gergaji Besi Kwalitas Baik Buah
103 Stang Gergaji Besi Kwalitas Baik Buah
104 Betel Besar Buah
105 Betel Kecil Buah
106 Gergaji Kayu Kwalitas Sedang Buah
107 Gergaji Kayu Kwalitas Baik Buah
108 Water Pass Tukang Kwalitas Sedang Buah
109 Water Pass Tukang Kwalitas Baik Buah
2.10. Bahan Plapon -
1 Eternit 100 x 100 Cm lembar 26,000.00
2 Kalsiboard 122 x 240 x 4 mm lembar 63,000.00
3 Kalsiboard 122 x 244 x 4 mm lembar 63,000.00
4 Triplek 122x244x2 mm lembar 65,000.00
5 Triplek 122x244x3 mm lembar 68,000.00
6 Triflek 90x210x3 mm lembar 62,000.00
7 Triplek besar 122x242 cm tebal 6 mm lembar 79,000.00
8 Triplek 122x244x9 mm lembar 120,000.00
9 Triplek 122x244x12 mm lembar
10 Teakwood 122x244x3 mm lembar
11 Teackwood 90x210x3 mm lembar
12 Blockwood 122x244x18 mm lembar
13 Teackblock 122x144x18 mm lembar
14 Playwood 122x244x3 mm lembar
15 Playwood 90x210x3 mm lembar
16 Milamin 122x244x3 mm lembar
17 Triplek Lapis Aluminium lembar 100,000.00
18 Gypsum Polos M2
19 Gypsum Susun M2
20 List Gypsum Meter
21 List Plapon Rata 1,5x4 Meter
22 List Plapon Profil Rata 2x4 Meter
23 List Plapond Profil 3/3 Meter
24 List Plapond Profil 4/4 Meter
25 Lem Kayu Kg 41,000.00
26 Lem Pipa Tube 55,000.00
27 Lem Pipa Kualitas baik kaleng 55,000.00
27 Sealtipe BH 10,000.00
Kalsiplank ukuran (8X20) cm Meter 15,000.00
27 Pilox kaleng 35,000.00

2.11. Bahan Pipa


PIPA GI -
PIPA GI Biasa -
1 Ø 1/2" Meter 15,000.00
2 Ø 3/4" Meter 21,000.00
3 Ø 1" Meter 26,000.00
4 Ø 11/4" Meter 31,000.00
5 Ø 11/2 Meter 37,000.00
6 Ø 2" Meter 42,000.00
7 Ø 3" Meter 69,000.00
8 Ø 4" Meter 103,000.00
9 Ø 6" Meter 289,000.00
PIPA GI Medium B -
1 Ø 1/2" Meter 18,000.00
2 Ø 3/4" Meter 21,000.00
3 PIPA GI Medium B Ø 1" Meter 49,150.00 294,900.00
4 PIPA GI Medium B Ø 11/4" Meter 49,150.00 294,900.00
5 PIPA GI Medium B Ø 1,5" Meter 77,483.00 464,898.00
6 PIPA GI Medium B Ø 2" Meter 159,000.00 954,000.00
7 Ø 3" Meter 106,000.00
8 Ø 4" Meter 122,000.00
9 Ø 6" Meter 323,000.00
PIPA GI Medium A
1 PIPA Galpanis (GI Medium A) Ø 1/2" Meter 32,000.00
2 PIPA Galpanis (GI Medium A) Ø 3/4" Meter 40,000.00
3 PIPA Galpanis (GI Medium A) Ø 1" Meter 56,000.00
4 PIPA Galpanis (GI Medium A) Ø 1,25" Meter 60,000.00
4 PIPA Galpanis (GI Medium A) Ø 1,5" Meter 135,000.00 810,000.00
5 PIPA Galpanis (GI Medium A) Ø 2" Meter 150,000.00 900,000.00
5 PIPA Galpanis (GI Medium A) Ø 2,5" Meter 160,000.00 960,000.00
6 PIPA Galpanis (GI Medium A) Ø 3" Meter 265,700.00 1,594,200.00
7 PIPA Galpanis (GI Medium A) Ø 4" Meter 250,000.00 1,500,000.00
8 PIPA Galpanis (GI Medium A) Ø 6" Meter 478,000.00
9 PIPA Galpanis (GI Medium A) Ø 8" Meter 690,000.00
10 PIPA Galpanis (GI Medium A) Ø 10" Meter 970,000.00
11 PIPA Galpanis (GI Medium A) Ø 12" Meter 1,500,000.00

PIPA Satinlisstill
Pipa Stailisetill Ø 1 1/4" Meter 80,000.00
Pipa Stailisetill Ø 1" Meter 65,000.00

PIPA PVC
Pipa PVC tidak bertekanan (Kwalitas C)
2 Pipa Listrik Ø (5/8) Meter 2,000.00
3 Ø 1/2" Meter 2,500.00
4 Ø 3/4" Meter 3,500.00
5 Ø 1" Meter 5,000.00
6 Ø 11/4" Meter 6,000.00
7 Ø 11/2 Meter 7,000.00
8 Ø 2" Meter 9,000.00
9 Ø 2 ½" Meter 11,000.00
10 Ø 3" Meter 15,000.00
Ø 4" Meter 20,000.00
Pipa PVC tidak bertekanan (Kwalitas D) -

2 Ø 1/2" Meter 3,000.00


3 Ø 3/4" Meter 4,500.00
4 Ø 1" Meter 5,700.00
5 Ø 11/4" Meter 8,900.00
6 Ø 11/2 Meter 12,000.00
7 Pipa PVC (Kwalitas D) Ø 2" Meter 18,000.00 72,000.00
8 Ø 2 ½" Meter 22,000.00
9 Pipa PVC (Kwalitas D) Ø 3" Meter 35,000.00 140,000.00
10 Ø 4" Meter 35,000.00
Ø 6" Meter 71,000.00
Pipa PVC bertekanan (AW)
2 Pipa PVC bertekanan (AW) Ø 1/2" Meter 7,000.00 28,000.00
3 Ø 3/4" Meter 8,500.00
4 Ø 1" Meter 10,000.00
5 Pipa PVC bertekanan (AW) Ø 1.25" Meter 16,000.00 64,000.00
6 Pipa PVC bertekanan (AW) Ø 11/2 Meter 18,000.00 72,000.00
7 Ø 2" Meter 20,000.00
8 Ø 2 ½" Meter 29,000.00
9 Ø 3" Meter 41,000.00
10 Ø 4" Meter 66,000.00
11 Pipa PVC bertekanan (AW) Ø 6" Meter 165,000.00
12 Ø 8" Meter 250,000.00
13 Ø 10" Meter 410,000.00
Ø 12" Meter 560,000.00
Pipa S 6.3 & 10 SNI
1 Pipa S 6.3 SNI Ø 1/2" Meter 10,000.00
2 Pipa S 6.3 SNI Ø 3/4" Meter 12,000.00
3 Pipa S 10 SNIØ 1" Meter 15,000.00
4 Pipa S 10 SNI Ø 6" Meter 236,600.00

Pipa S 12,5 SNI


1 Pipa S 12,5 SNI Ø 11/4 " Meter 20,000.00 120,000.00
2 Pipa S 12,5 SNI Ø 1,5" Meter 25,000.00 150,000.00
3 Pipa S 12,5 SNI Ø 2" Meter 25,666.00 153,996.00
4 Pipa S 12,5 SNI Ø 2,5" Meter 44,000.00 264,000.00
5 Pipa S 12,5 SNI Ø 3" Meter 55,000.00 330,000.00
6 Pipa S 12,5 SNI Ø 4" Meter 90,000.00
7 Pipa S 12,5 SNI Ø 6" Meter 192,000.00
8 Pipa S 12,5 SNI Ø 8" Meter
9 Pipa S 12,5 SNI Ø 10" Meter
10 Pipa S 12,5 SNI Ø 12" Meter
11 Pipa S 12,5 SNI Ø 14" Meter
12 Pipa S 12,5 SNI Ø 16" Meter
13 Pipa S 12,5 SNI Ø 20" Meter

Pipa HDPE -
1 Pipa HDPE Ø 1/2" Meter 12,000.00 PN 16 SDR 11
2 Pipa HDPE Ø 3/4" Meter 13,000.00 PN 16 SDR 11
3 Pipa HDPE Ø 1" Meter 19,000.00 PN 16 SDR 11
4 Pipa HDPE Ø 11/4" Meter 30,000.00 PN 16 SDR 11
5 Pipa HDPE Ø 1,5" Meter 29,000.00 PN 10 SDR 17
6 Pipa HDPE Ø 2" Meter 62,000.00 PN 10 SDR 17
7 Pipa HDPE Ø 2,5" Meter 65,000.00 PN 10 SDR 17
8 Pipa HDPE Ø 3" Meter 110,000.00 PN 10 SDR 17
9 Pipa HDPE Ø 4" Meter 135,000.00 PN 10 SDR 17
10 Pipa HDPE Ø 4 1/2" Meter
11 Pipa HDPE Ø 5" Meter 172,000.00 PN 10 SDR 17
12 Pipa HDPE Ø 6" Meter 282,000.00 PN 10 SDR 17
13 Ø 7" Meter
14 Ø 8" Meter
15 Ø 9" Meter
16 Ø 10" Meter
17 Ø 11" Meter
18 Ø 12" Meter
19 Ø 14" Meter
20 Ø 16" Meter
21 Ø 18" Meter
22 Ø 20" Meter
23 Ø 22" Meter
24 Coupler HDPE 2" Buah 317,200.00
25 Coupler HDPE 1" Buah 182,200.00
26 Reducer Coupler 2"x1" Buah 174,200.00
-
ACSSESORIS PIPA -
Stop Kran -
1 Stop Kran Ø 1/2" Buah 79,000.00
2 Stop Kran Ø 3/4" Buah 98,000.00
3 Stop Kran Ø 1" Buah 163,000.00
4 Stop Kran Ø 11/2 Buah 327,000.00
5 Stop Kran Ø 2" Buah 444,000.00
6 Stop Kran Ø 2.5" Buah 950,000.00
7 Stop Kran Ø 3" Buah 1,400,000.00
8 Stop Kran Ø 4" Buah 2,000,000.00

Kran
1 Kran Ø 1/2" Buah 20,000.00
2 Ø 3/4" Buah 92,000.00
3 Ø 1" Buah 128,000.00

Knee GI -
1 Knee GI Ø 1/2" Buah 9,000.00
2 Knee GI Ø 3/4" Buah 10,000.00
3 Knee GI Ø 1" Buah 11,000.00
4 Knee GI Ø 11/2 Buah 35,000.00
5 Knee GI Ø 2" Buah 55,000.00
5 Knee GI Ø 2.5" Buah
6 Knee GI Ø 3" Buah 130,000.00
7 Knee GI Ø 4" Buah 150,000.00
8 Band GI Ø 1,5" x 45 Buah 80,000.00
9 Band GI Ø 2" x 45 Buah 133,000.00
10 Band GI Ø 2,5" x 45 Buah 133,000.00
11 Band GI Ø 3" x 45 Buah 216,000.00
12 Band GI Ø 4" x 46 Buah 374,000.00
13 Band GI Ø 6" x 47 Buah 646,000.00

Dop GI (Drat Dalam) -


1 Ø 1/2" Buah 5,000.00
2 Ø 3/4" Buah 7,000.00
3 Ø 1" Buah 9,000.00
4 Ø 11/2 Buah 19,000.00
5 Ø 2" Buah 27,000.00
6 Ø 2 1 /2" Buah 30,000.00
7 Ø 3" Buah 80,000.00
8 Ø 4" Buah 93,000.00
9 Ø 6" Buah 230,000.00
Dop GI (Drat Luar) -
1 Ø 1/2" Buah 5,500.00
2 Ø 3/4" Buah 7,000.00
3 Ø 1" Buah 9,000.00
4 Ø 11/2 Buah 19,000.00
5 Ø 2" Buah 36,000.00
6 Ø 2 1/2" Buah 58,000.00
7 Ø 3" Buah 79,000.00
8 Ø 4" Buah 106,000.00
9 Ø 6" Buah 133,000.00
Tee GI -
1 Ø 1/2" Buah 7,000.00
2 Ø 3/4" Buah 9,000.00
3 Ø 1" Buah 15,000.00
4 Ø 11/2 Buah 25,000.00
5 Ø 2" Buah 36,000.00
6 Ø 2 1/2" Buah 85,000.00
7 Ø 3" Buah 100,000.00
8 Ø 4" Buah 230,000.00
9 Ø 6" Buah 600,000.00
Gate Valve -
1 Ø 1.25" Buah 400,000.00
2 Gate Valve Ø 2" Buah 750,000.00
3 Ø 2 1/2" Buah 710,000.00
4 Gate Valve Ø 3" Buah 1,300,000.00
5 Gate Valve Ø 4" Buah 1,750,000.00
6 Ø 6" Buah 2,800,000.00
7 Ø 8" Buah 3,000,000.00
8 Ø 10" Buah 7,000,000.00
9 Ø 12" Buah 11,000,000.00
10 Ø 14" Buah 17,000,000.00
11 Ø 16" Buah 21,000,000.00
Gibolt Joint PVC -
1 Ø 2" Buah 116,000.00
2 Ø 2 1/2" Buah 160,000.00
3 Ø 3" Buah 187,000.00
4 Ø 4" Buah 230,000.00
5 Ø 6" Buah 460,000.00
6 Ø 8" Buah 600,000.00
7 Ø 10" Buah
8 Ø 12" Buah
9 Ø 14" Buah
10 Ø 16" Buah
Clamp Sadle -
1 Ø6x1 Buah 230,000.00
2 Ø 6 x 1/2 Buah 230,000.00
3 Ø4x1 Buah 75,000.00
4 Ø 4 x 1/2 Buah 70,000.00
5 Ø3x1 Buah 55,000.00
6 Ø 3 x 1/2 Buah 50,000.00
7 Ø2x1 Buah 50,000.00
8 Ø 2 x 1/2 Buah 44,000.00
9 Ø 11/2 x 1 Buah 42,000.00
10 Ø 11/2 x 1/2 Buah 28,000.00

Bend PVC 90 (Knee) SNI -


1 Bend PVC 90 (Knee) Ø 1/2" Buah 70,000.00
2 Bend PVC 90 (Knee) SNI Ø 3/4" Buah 90,000.00
3 Bend PVC 90 (Knee) SNI Ø 1" Buah 100,000.00
4 Bend PVC 90 (Knee) SNI Ø 11/2 Buah 122,000.00
5 Bend PVC 90 (Knee) SNI Ø 2" Buah 148,000.00
6 Bend PVC 90 (Knee) SNI Ø 2 1/2" Buah 180,000.00
7 Bend PVC 90 (Knee) SNI Ø 3" Buah 200,000.00
8 Bend PVC 90 (Knee) SNI Ø 4" Buah 330,000.00
9 Bend PVC 90 (Knee) SNI Ø 6" Buah 560,000.00
10 Ø 8" Buah 970,000.00
11 Ø 10" Buah 1,600,000.00

Bend PVC 45 SNI -


1 Bend PVC 45 SNI Ø 1,5" Buah 153,000.00
2 Bend PVC 45 SNI Ø 2" Buah 179,000.00
3 Bend PVC 45 SNI Ø 2,5" Buah 230,000.00
4 Bend PVC 45 SNI Ø 3" Buah 276,000.00
5 Bend PVC 45 SNI Ø 4" Buah 358,000.00
6 Bend PVC 45 SNI Ø 6" Buah 624,000.00
7 Ø 8" Buah 1,000,000.00
8 Ø 10" Buah 1,500,000.00

Long Bend PVC 90 SNI -


1 Long Bend PVC 90 Ø 1" Buah 75,000.00
1 Long Bend PVC 90 Ø 2" Buah 100,000.00
2 Long Bend PVC 90 Ø 2 1/2" Buah 130,000.00
3 Long Bend PVC 90 Ø 3" Buah 150,000.00
4 Long Bend PVC 90 Ø 4" Buah 245,000.00
5 Long Bend PVC 90 Ø 6" Buah 420,000.00
6 Ø 8" Buah 700,000.00
7 Ø 10" Buah 1,220,000.00
8 Ø 12" Buah 2,000,000.00
9 Ø 14" Buah 5,000,000.00
10 Ø 16" Buah 7,000,000.00

Tee PVC
1 Tee PVC Ø 1/2" Buah 30,000.00
2 Tee PVC Ø 3/4" Buah 40,000.00
3 Tee PVC Ø 1" Buah 50,000.00
4 Tee PVC Ø 11/2 Buah 70,000.00
5 Tee PVC Ø 2" Buah 85,000.00
6 Tee PVC Ø 2.5" Buah 120,000.00
6 Tee PVC Ø 3" Buah 150,000.00
7 Tee PVC Ø 4" Buah 200,000.00
8 Tee PVC Ø 6" Buah 330,000.00

Reducer Tee All Socket PVC


1 Ø 3/4 x 1/2" Buah 50,000.00
2 Ø 1 x 1/2" Buah 70,000.00
3 Ø 1 x 3/4" Buah 80,000.00
4 Ø 1 1/2" x 1" Buah 95,000.00
5 Ø 1 1/2" x 3/4" Buah 100,000.00
6 Reducer Tee All Socket PVC Ø 2" x 1" Buah 110,000.00
7 Reducer Tee All Socket PVC Ø 2" x 1.5" Buah 125,000.00

8 Ø 3" x 1/2" Buah 140,000.00


8 Reducer Tee All Socket PVC Ø 2.5" x 1" Buah 140,000.00

9 Reducer Tee All Socket PVC Ø 2.5" x 2" Buah 140,000.00

10 Ø 3" x 2" Buah 160,000.00


11 Ø 4" x 1" Buah 230,000.00
12 Ø 6" x 3" Buah 380,000.00
13 Ø 4" x 3" Buah 250,000.00
14 Ø 6" x 2" Buah 380,000.00
15 Ø 6" x 3" Buah 430,000.00
16 Ø 6" x 4" Buah 480,000.00
Reducer Socket PVC -
1 Reducer Socket PVC Ø 1 x 3/4" Buah 50,000.00
2 Reducer Socket PVC Ø 1 1/2" x 1" Buah 65,000.00
3 Ø 1 1/2" x 3/4" Buah 75,000.00
4 Reducer Socket PVC Ø 2" x 1" Buah 80,000.00
5 Ø 2" x 11/2" Buah 90,000.00
6 Ø 21/2" x 11/2" Buah 110,000.00
7 Reducer Socket PVC Ø 2.5" x 2" Buah 115,000.00
8 Reducer Socket PVC Ø 3" x 2" Buah 122,000.00
9 Ø 3" x 21/2" Buah 120,000.00
10 Ø 4" x 2" Buah 110,000.00
11 Ø 4" x 21/2" Buah 140,000.00
12 Ø 4" x 3" Buah 149,000.00
13 Ø 6" x 3" Buah 300,000.00
14 Ø 6" x 4" Buah 272,000.00
End cop (Dop PVC) -
1 End cop (Dop PVC) Ø 1/2" Buah 10,000.00
2 End cop (Dop PVC)Ø 3/4" Buah 15,000.00
3 End cop (Dop PVC) Ø 1" Buah 25,000.00
4 End cop (Dop PVC) Ø 1.5 Buah 35,000.00
5 End cop (Dop PVC) Ø 2" Buah 50,000.00
6 End cop (Dop PVC) Ø 2 1/2" Buah 55,000.00
7 End cop (Dop PVC) Ø 3" Buah 65,000.00
8 End cop (Dop PVC) Ø 4" Buah 93,000.00
9 End cop (Dop PVC) Ø 6" Buah 156,000.00
Single Air Valve (Ventil) -
1 Ø 1/2" Buah 210,000.00
2 Ø 3/4" Buah 250,000.00
3 Ø 1" Buah 350,000.00
4 Ø 11/2 Buah 590,000.00
5 Ø 2" Buah 610,000.00
6 Ø 3" Buah 29,000.00
7 Ø 4" Buah 1,300,000.00

1 Double Neple GI Dia 1/2" Buah 13,000.00


2 Double Neple GI Dia 3/4" Buah 14,000.00
3 Double Neple GI Dia 1" Buah 66,000.00
4 Double Neple GI Dia 1,5" Buah 112,000.00
5 Double Neple GI Dia 2" Buah 123,000.00
6 Double Neple GI Dia 3" Buah 143,500.00
7 Socket Gl Dia. 1/2" Buah 13,000.00
8 Socket Gl Dia. 3/4" Buah 14,000.00
9 Socket Gl Dia. 1" Buah 37,000.00
10 Socket Gl Dia. 1,5" Buah 37,000.00
11 Socket Gl Dia. 2" Buah 56,000.00
12 Socket Gl Dia. 2,5" Buah 76,000.00
13 Socket Gl Dia. 3" Buah 96,000.00
14 Socket Gl Dia. 4" Buah 123,000.00
15 Socket Gl Dia. 6" Buah 224,000.00
16 Walter Mour Dia. 4" Buah 143,000.00
17 Walter Mour Dia. 3" Buah 92,000.00
18 Walter Mour Dia. 2" Buah 51,000.00
19 Gibolt Joint GIP Dia. 10" Buah 1,900,000.00
20 Gibolt Joint GIP Dia. 8" Buah 1,230,000.00
21 Gibolt Joint GIP Dia. 6" Buah 910,000.00
22 Gibolt Joint GIP Dia. 4" Buah 652,000.00
23 Tee All Plange Dia. 2" Buah 179,000.00
24 Tee All Flange Dia. 3" Buah 314,000.00
25 Tee All Flange Dia. 4" Buah 432,000.00
26 Tee All Flange Dia. 6" Buah 584,000.00
27 Tee GIP All Flange. Dia. 2" x 2" Buah 470,000.00
28 Tee GIP Flange Dia. 3" x 2" Buah 538,000.00
29 Tee GIP All Flange Dia. 3" x 3" Buah 612,000.00
30 Tee GIP All Flange Dia. 4" x 2" Buah 794,000.00
31 Tee GIP All Flange Dia. 4" x 3" Buah 794,000.00
32 Tee GIP All Flange Dia. 4" x 4" Buah 848,000.00
33 Tee GIP All Flange Dia. 6" x 2" Buah 1,199,000.00
34 Tee GIP All Flange Dia. 6" x 3" Buah 1,199,000.00
35 Tee GIP All Flange Dia. 6" x 4" Buah 1,204,000.00
36 Tee GIP All Flange Dia. 6" x 6" Buah 1,226,000.00
37 Elbow GI Ø 4" Buah 210,000.00
38 Elbow GI Ø 3" Buah 130,000.00
39 Elbow GI Ø 2" Buah 93,000.00
40 Elbow GI Ø 11/2" Buah 47,000.00
41 Elbow GI Ø 1" Buah 36,000.00
42 Elbow GI Ø 1/2" Buah 26,000.00
43 Elbow GI Ø 3/4" Buah 21,000.00
44 Valve Socket Ø 1/2" Buah 13,000.00
45 Valve Socket Ø 3/4" Buah 17,000.00
46 Valve Socket Ø 1" Buah 30,000.00
47 Valve Socket Ø 1.5" Buah 31,000.00
48 Valve Socket Ø 2" Buah 50,000.00
49 Valve Socket Ø 21/5" Buah 58,000.00
50 Valve Socket Ø 3" Buah 74,000.00
51 Valve Socket Ø 4" Buah 120,000.00
52 Valve Socket Ø 6" Buah 125,000.00
53 Flange Socket PVC Ø 1.5" Buah 31,000.00
54 Flange Socket PVC Ø 2" Buah 158,000.00
55 Flange Socket PVC Ø 21/2" Buah 96,000.00
56 Flange Socket PVC Ø 3" Buah 257,000.00
57 Flange Socket PVC Ø 4" Buah 400,000.00
58 Flange Socket PVC Ø 6" Buah 550,000.00
59 Flange Spigol PVC Ø 2" Buah 175,000.00
60 Flange Spigol PVC Ø 21/2" Buah 280,000.00
61 Flange Spigol PVC Ø 3" Buah 300,000.00
62 Flange Spigol PVC Ø 4" Buah 420,000.00
63 Flange Spigol PVC Ø 6" Buah 560,000.00
Air Valve -
1 Ø 4" Buah 3,500,000.00
2 Ø 3" Buah 2,000,000.00
3 Ø 2" Buah 800,000.00
4 Ø 11/2" Buah 500,000.00
5 Ø 1" Buah 350,000.00
6 Ø 3/4" Buah 280,000.00
7 Ø 1/2" Buah 210,000.00
Check Valve -
1 Ø 4" Buah 1,700,000.00
2 Ø 3" Buah 1,400,000.00
3 Ø 2" Buah 1,100,000.00
4 Ø 1 /2" Buah 75,000.00
Valve Socket PVC -
1 Ø 6" Buah 200,000.00
2 Ø 4" Buah 160,000.00
3 Ø 3" Buah 100,000.00
4 Ø 2" Buah 60,000.00
5 Ø 11/2" Buah 50,000.00
6 Ø 1" Buah 35,000.00
7 Ø 3/4" Buah 20,000.00
8 Ø 1/2" Buah 13,000.00
Atap Kran -
1 Ø 1" Buah 130,000.00
2 Ø 3/4" Buah 100,000.00
3 Ø 1/2" Buah 75,000.00
Band PVC 45° -
1 Ø 10" Buah 1,720,000.00
2 Ø 8" Buah 1,100,000.00
3 Ø 6" Buah 600,000.00
4 Ø 4" Buah 350,000.00
5 Ø 3" Buah 200,000.00
6 Ø 2" Buah 130,000.00
7 Ø 11/2" Buah 79,000.00
Knee PVC SNI
1 Ø 4" Buah 116,000.00
2 Ø 3" Buah 70,000.00
3 Ø 2" Buah 33,000.00
4 Ø 11/2" Buah 22,000.00
5 Ø 1" Buah 18,000.00
6 Ø 3/4" Buah 11,000.00
7 Ø 1/2" Buah 3,000.00
Knee GIP SNI
1 Ø 4" Buah 170,000.00
2 Ø 3" Buah 140,000.00
3 Ø 2" Buah 90,000.00
4 Ø 11/2" Buah 62,000.00
5 Ø 1" Buah 21,000.00
6 Ø 3/4" Buah 16,000.00
7 Ø 1/2" Buah 12,000.00
Tee PVC -
1 Ø6x6 Buah 750,000.00
2 Ø6x4 Buah 720,000.00
3 Ø6x3 Buah 700,000.00
4 Ø6x2 Buah 700,000.00
5 Ø4x4 Buah 450,000.00
6 Ø4x3 Buah 450,000.00
7 Ø4x2 Buah 410,000.00
8 Ø4x1 Buah 410,000.00
9 Ø3x3 Buah 390,000.00
10 Ø3x2 Buah 390,000.00
11 Ø3x1 Buah 285,000.00
12 Ø2x2 Buah 210,000.00
13 Ø2x1 Buah 210,000.00
14 Ø1x1 Buah 87,000.00
15 Ø 1 x 1/2 Buah 87,000.00
16 Ø 1/2 x 1/2 Buah 50,000.00
Flens Las GIP -
1 Ø 8" Buah 510,000.00
2 Ø 6" Buah 410,000.00
3 Ø 4" Buah 277,000.00
4 Ø 3" Buah 135,000.00
5 Ø 2" Buah 100,000.00
Flens Socket GIP -
1 Ø 4" Buah 500,000.00
2 Ø 3" Buah 400,000.00
3 Ø 2" Buah 300,000.00
4 Ø1.5" Buah 260,000.00
Packing Flens -
1 Ø 6" Buah 81,000.00
2 Ø 4" Buah 62,000.00
3 Ø 3" Buah 43,000.00
4 Ø 2" Buah 36,000.00
Flens Spigot -
1 Ø 6" Buah 720,000.00
2 Ø 4" Buah 520,000.00
3 Ø 3" Buah 450,000.00
4 Ø 2" Buah 260,000.00
Flug Kran Buah 56,000.00
Mur + baut Buah 10,000.00
Sealtafe 10 m Buah 10,000.00
Box Meter Set 100,000.00
Water Meter 1/2" Set 150,000.00
Slang Air Plastik 1/2" Meter 6,000.00
Slang Air Plastik 3/4" Meter 11,000.00
Slang Air Plastik 1" Meter 21,000.00
Pipa Gas 1/2" Meter 65,000.00
Pipa Gas 3/4" Meter 80,000.00
Pipa Gas 1" Meter 105,000.00
Shock Drat luar PVC Ø1/2" Buah 15,000.00
Shock Drat luar PVC Ø1" Buah 20,000.00
Shock Drat luar PVC Ø1.5" Buah 25,000.00
Shock Drat luar PVC Ø2" Buah 30,000.00
Shock Drat luar PVC Ø2.5" Buah 40,000.00
Shock Drat luar PVC Ø3" Buah 50,000.00
Shock Drat Dalam PVC Ø1/2" Buah 15,000.00
Mesin Jet Pump Kap. 250 watt unit 1,650,000.00
Msein Pompa tekan Kap. 150 watt unit 500,000.00
2.12. Bahan Kaca -
1 Kaca Polos 2 mm M2 75,000.00
2 Kaca Polos 3 mm M2 150,000.00
3 Kaca Polos 5 mm M2 190,000.00
4 Kaca Riben Tebal 3 mm M2 185,000.00
5 Kaca Riben Tebal 5 mm M2 250,000.00
6 Glas Blok Polos Buah 35,000.00
7 Glas Blok Warna Buah 37,500.00
2.13. Bahan Finishing -
1 Ampelas lembar 30,000.00
2 Plamir Kayu kg 40,000.00
3 Spirtus Liter 32,000.00
4 Minyak Cat biasa Liter 40,000.00
5 Thiner A Biasa 1/2 Liter Kaleng 36,000.00
6 Thiner A Biasa 1 Liter Kaleng 41,000.00
7 Thiner A Biasa 5 Liter Kaleng 133,000.00
8 Thiner A Spesial 1/2 Liter Kaleng 36,000.00
9 Thiner A Spesial 1 Liter Kaleng 46,000.00
10 Thiner A Spesial 5 Liter Kaleng 195,000.00
11 Meni Besi kg 56,000.00
12 Wood Filter kg 62,000.00
13 Meni Kayu kg 56,000.00
14 Politur Kwalitas Sedang Liter 62,000.00
15 Politur Kwalitas Baik Liter 88,000.00
16 Cat Kayu Mutu Sedang kg 62,000.00
17 Cat Kayu Mutu Baik kg 102,000.00
18 Cat Tembok Kwalitas Premium kg 102,000.00
19 Cat Tembok Mutu Standar/Sedang kg 41,000.00
20 Cat Tembok Kwalitas Ekonomis/Biasa kg 35,000.00
21 Cat tembok kg 35,000.00
22 Cat Genteng kg 53,000.00
23 Cat Marka kg 61,000.00
24 Kuas 1" Buah 15,000.00
25 Kuas 11/2" Buah 10,000.00
26 Kuas 2" Buah 10,000.00
27 Kuas 21/2" Buah 15,000.00
28 Kuas 3" Buah 18,000.00
29 Kuas 4" Buah 22,000.00
30 Kuas Lukis Buah 8,000.00
31 Kuas Rol Buah 62,000.00
32 Plamir Tembok kg 47,000.00
33 Teer Arang kg 10,000.00
34 Cat Anti Bocor kg 70,000.00
35 Mil kg 1,000.00
2.14. Bahan Pengunci -
1 Kunci Union 2 Slag Buah 70,000.00
2 Kunci Jangkar 2 Slag Buah 95,000.00
3 Kunci Pintu Buah 120,000.00
Engsel Pintu Set 92,000.00
4 Kunci Pintu + Handle ukuran kecil kualitas Set 205,000.00
baik

5 Kunci Pintu + Handle ukuran kecil kualitas Set 143,000.00


sedang

6 Kunci Pintu + Handle ukuran kecil kualitas Set 190,000.00


biasa

7 Kunci Pintu + Handle ukuran sedang Set 230,000.00


kualitas baik

8 Kunci Pintu + Handle ukurang sedang Set 169,000.00


kualitas sedang

9 Kunci Pintu + Handle ukurang sedang Set 87,000.00


kualitas biasa

10 Kunci Pintu + Handle ukurang besar Set 545,000.00


kualitas baik

11 Kunci Pintu + Handle ukurang besar Set 397,000.00


kualitas sedang

12 Kunci Pintu + Handle ukurang besar Set 169,000.00


kualitas biasa

13 Kunci Pintu Mutu Sedang Buah 82,000.00


14 Kuda Terbang 2 Slag Besar Buah 69,000.00
15 Kuda Terbang 2 Slag Kecil Buah 61,000.00
16 Haag Angin ukuran kecil kwalitas baik stel 92,000.00
17 Haag Angin ukuran kecil kwalitas sedang stel 51,000.00

18 Haag Angin ukuran kecil kwalitas biasa stel 20,000.00


19 Haag Angin ukuran sedang kwalitas baik stel 256,000.00

20 Haag Angin ukuran sedang kwalitas sedang stel 92,000.00

21 Haag Angin ukuran sedang kwalitas biasa stel 51,000.00

22 Haag Angin ukuran besar kwalitas baik stel 307,000.00

23 Haag Angin ukuran besar kwalitas sedang stel 112,000.00

24 Haag Angin ukuran besar kwalitas biasa stel 66,000.00

25 Grendel Besar kwalitas Sedang Buah 15,000.00


26 Grendel Besar kwalitas Baik Buah 30,000.00
27 Grendel Kecil Kwalitas Sedang Buah 8,000.00
28 Grendel Kecil Kwalitas Baik Buah 15,000.00
29 Grendel Tanam ukuran besar kwalitas baik Set 666,000.00

30 Grendel Tanam ukuran besar kwalitas Set 486,000.00


sedang

31 Grendel Tanam ukuran besar kwalitas biasa Set 256,000.00

32 Grendel Tanam ukuran kecil kwalitas baik Set 410,000.00

33 Grendel Tanam ukuran kecil kwalitas sedang Set 205,000.00

34 Grendel Tanam ukuran kecil kwalitas biasa Set 102,000.00

35 Engsel Pintu 3 Lubang kwalitas baik Pasang 123,000.00


36 Engsel Pintu 3 Lubang kwalitas sedang Pasang 87,000.00

37 Engsel Pintu 3 Lubang kwalitas biasa Pasang 36,000.00


38 Engsel Pintu 4 Lubang kwalitas baik Pasang 177,000.00
39 Engsel Pintu 4 Lubang kwalitas sedang Pasang 92,000.00

40 Engsel Pintu 4 Lubang kwalitas biasa Pasang 52,000.00


41 Engsel Pintu 5 Lubang kwalitas baik Pasang 209,000.00
42 Engsel Pintu 5 Lubang kwalitas sedang Pasang 108,000.00

43 Engsel Pintu 5 Lubang kwalitas biasa Pasang 62,000.00


44 Handle Pintu ukuran kecil kwalitas baik Pasang 635,000.00

45 Handle Pintu ukuran kecil kwalitas sedang Pasang 348,000.00

46 Handle Pintu ukuran kecil kwalitas biasa Pasang 128,000.00

47 Handle Pintu ukuran sedang kwalitas baik Pasang 1,039,000.00

48 Handle Pintu ukuran sedang kwalitas Pasang 717,000.00


sedang

49 Handle Pintu ukuran sedang kwalitas biasa Pasang 385,000.00

50 Handle Pintu ukuran besar kwalitas baik Pasang 1,332,000.00

51 Handle Pintu ukuran besar kwalitas sedang Pasang 1,127,000.00


52 Handle Pintu ukuran besar kwalitas biasa Pasang 600,000.00

53 Engsel H Besar Pasang 15,000.00


54 Engsel H Kecil Pasang 10,000.00
55 Selinder Buah 51,000.00
56 Door Stoper Buah 43,000.00
57 Door Closer Buah 288,000.00
58 Slot Tanam Buah 41,000.00
59 Bergel Plat Set 25,000.00
60 Besi Beugel U Beton Set 30,000.00
61 Besi Beugel U Plat Set 35,000.00
2.15. Bahan Sanitaire
1 Closet Duduk Lengkap Kwalitas Sedang Set 2,000,000.00

2 Closet Duduk Lengkap Kwalitas Baik Set 4,700,000.00


3 Closet Duduk Mono Kwalitas Sedang Set 2,000,000.00
4 Closet Duduk Mono Kwalitas Baik Set 2,900,000.00
5 Closet Jongkok Porselin Kwalitas Sedang Buah 310,000.00

6 Closet Jongkok Porselin Kwalitas Baik Buah 370,000.00


7 Wastafel Kwalitas Sedang Set 700,000.00
8 Wastafel Kwalitas Baik Set 2,000,000.00
9 Saringan air Besi Croom Buah 60,000.00
10 Saringan Air Staenlist Buah 45,000.00
11 Saringan Air Plastik tebal Buah 256,000.00
12 Bak Air Fibreglass Segi Empat 40 L Buah 230,000.00
570x370x300

13 Bak Air Fibreglass Segi Empat 100 L Buah 307,000.00


530x530x500

14 Bak Air Fibreglass Segi Empat 120 L Buah 256,000.00


530x530x600

15 Bak Air Fibreglass Segi Empat 220 L Buah 486,000.00


690x690x700

16 Bak Air Fibreglass Oval 120 L 550x550x700 Buah 483,000.00

17 Bak Air Fibreglass Oval 220 L 660x660x700 Buah 646,000.00

18 Tower Stainlis steel 750 Liter Buah 2,562,000.00


19 Tower Stainlis steel 1100 Liter Buah 3,075,000.00
20 Tower Fibreglass 250 Liter Buah 461,000.00
21 Tower Fibreglass 320 Liter Buah 512,000.00
22 Tower Fibreglass 550 Liter Buah 691,000.00
23 Tower Fibreglass 650 Liter Buah 809,000.00
24 Tower Fibreglass 750 Liter Buah 1,660,000.00
25 Tower Fibreglass 1100 Liter Buah 1,900,000.00
26 Tower Fibreglass 1200 Liter Buah 2,900,000.00
27 Tower Fibreglass 2200 Liter Buah 4,100,000.00
28 Tower Fibreglass 3300 Liter Buah 5,000,000.00
29 Tower Fibreglass 5200 Liter Buah 7,500,000.00
30 Watter Hitter 15 Ltr Unit 3,400,000.00
31 Watter Hitter 30 Ltr Unit 4,000,000.00
32 Watter Hitter 50 Ltr Unit 5,000,000.00
33 Urinoir Unit 1,350,000.00
34 Shower Spray Unit 950,000.00
35 Shower Set Unit 470,000.00
36 Flood drain Buah 370,000.00
37 Tempat Sabun Buah 53,000.00
38 Kran Zink Buah 531,000.00
39 Kitchenzink Unit 180,000.00
40 Kran dinding Buah 250,000.00
41 Badhub Unit 4,000,000.00
42 Kusen dan Pintu PVC Kamar Mandi Unit 1,500,000.00
43 Bak Porseelin 50x50x80 cm Unit 2,000,000.00
44 Sikat Closet Unit 15,000.00
45 Air liter 100.00
Waterdrain Buah 50,000.00
2.16. Bahan Paku -
1 Paku kg 20,000.00
2 Paku Nomor 2,5", 3", 4", 5", dan 6" kg 20,000.00
3 Paku Nomor 2" kg 23,000.00
4 Paku Nomor 1,5" kg 23,000.00
5 Paku Nomor 3/4" dan 1" kg 25,000.00
6 Paku Eternit kg 31,000.00
7 Paku Payung kg 31,000.00
8 Paku Giv kg 31,000.00
9 Baut Mur 10 Cm Buah 6,000.00
10 Baut Mur 15 Cm Buah 7,000.00
11 Baut Mur 20 Cm Buah 8,000.00
12 Baut Mur 25 Cm Buah 10,000.00
13 Baut Mur 30 Cm Buah 12,000.00
14 Skrup/Piles 5/8 Inci dooz kecil 12,000.00
15 Skrup/Piles 3/4 Inci dooz kecil 12,000.00
16 Skrup/Piles 1 Inci dooz kecil 18,000.00
17 Skrup/Piles 11/4 Inci dooz kecil 16,000.00
18 Skrup/Piles 11/2 Inci dooz kecil 16,000.00
19 Skrup/Piles 2 Inci dooz kecil 21,000.00
20 Paku Baja Kg 26,000.00
21 Paku Beton Kg 57,000.00
2.17. Bahan Instalasi Listrik -
1 Titik Lampu Buah 15,000.00
2 Zekering Boxes 1 Group Buah 18,000.00
3 Zekering Boxes 2 Group Buah 18,000.00
4 Zekering Boxes 3 Group Buah 31,000.00
5 MCB 1A - 25A Buah 75,000.00
6 MCB 32/60A Buah 43,000.00
7 Sekering Otomatis Kwalitas Sedang Buah 31,000.00
8 Sekering Otomatis Kwalitas Baik Buah 81,000.00
9 Stop Kontak Tanam Kwalitas Sedang Buah 15,000.00
10 Stop Kontak Tanam Kwalitas Baik Buah 22,000.00
11 Stop Kontak Tempel Kwalitas Sedang Buah 12,000.00
12 Stop Kontak Tempel Kwalitas Baik Buah 18,000.00
13 Saklar Tunggal Kwalitas Sedang Buah 125,000.00
14 Saklar Tunggal Kwalitas Baik Buah 20,000.00
15 Saklar Seri Kwalitas Sedang Buah 18,000.00
16 Saklar Seri Kwalitas Baik Buah 28,000.00
17 Saklar+Stop Kontak Kwalitas Sedang Buah 22,000.00
18 Saklar+Stop Kontak Kwalitas Baik Buah 25,000.00
19 Lampu Mercury 160 Watt Buah 56,000.00
20 Lampu Mercury 250 Watt Buah 84,000.00
21 Kabel NYM 2 x 2,5 mm, SNI Roll 1,000,000.00
22 Kabel Twister 2 x 10 mm m 9,000.00
23 Time Swith 110-230 V, f=45-60 Hz, Time 24 Buah 568,000.00
Jam

24 Konektor Kedap Air, D Cengkraman = 25-75 Buah 12,000.00


mm

25 Isolasi Buah 12,000.00


26 Piting Kecil 100-250 Volt 100/200 W Roll 15,000.00
27 Piting Besar 100-250 Volt 100/200 W Buah 27,000.00
28 Kap Kecil D = 2 mm Buah 34,000.00
29 Fhoto Cell 110 - 230 V/ 45 - 60 Hz Buah 87,000.00
30 Tangkai Ornamen D= 3/4 Inc, 1,25 M Buah 81,000.00
31 Kap Lampu Taman Buah 299,000.00
32 Kabel Listrik NYY 2 x 1.5 mm 100 m Roll 660,000.00
33 Kabel Listrik NYY 2 x 2.5 mm 100 m Roll 1,127,000.00
34 Kabel Listrik NYY 2 x 4 mm 100 m Roll 1,537,000.00
35 Kabel Listrik NYY 2 x 6 mm 100 m Roll 1,742,000.00
36 Kabel Listrik NYY 3 x 1.5 mm 100 m Roll 1,011,000.00
37 Kabel Listrik NYY 3 x 2.5 mm 100 m M 15,000.00
38 Kabel Listrik NYY 3 x 4 mm 100 m Roll 1,588,000.00
39 Kabel Listrik NYY 3 x 6 mm 100 m Roll 1,793,000.00
40 Kabel Listrik NYY 4 x 1.5 mm 100 m Roll 1,255,000.00
41 Kabel Listrik NYY 4 x 2.5 mm 100 m Roll 1,764,000.00
42 Kabel Listrik NYY 4 x 4 mm 100 m Roll 2,669,000.00
43 Kabel Listrik NYY 4 x 6 mm 100 m Roll 666,000.00
44 Kabel Listrik NYM 2 x 1.5 mm 100 m Roll 871,000.00
45 Kabel Listrik NYM 3 x 1.5 mm 100 m Roll 1,030,000.00 10,000.00
46 Kabel Listrik NYM 4 x 1.5 mm 100 m Roll 973,000.00
47 Kabel Listrik NYM 2 x 2.5 mm 100 m Roll 1,178,000.00
48 Kabel Listrik NYM 3 x 2.5 mm 100 m Roll 2,000,000.00 20,000.00
49 Kabel Listrik NYM 4 x 2.5 mm 100 m Roll 2,000,000.00
50 Kabel Listrik NYM 2 x 4 mm 100 m Roll 1,450,000.00
51 Kabel Listrik NYM 2 x 6 mm 100 m Roll 2,000,000.00
52 Kabel Listrik NYM 3 x 4 mm 100 m Roll 2,000,000.00
53 Kabel Listrik NYM 3 x 6 mm 100 m Roll 2,800,000.00
54 Kabel Listrik NYM 4 x 4 mm 100 m Roll 2,500,000.00
55 Kabel Listrik NYM 4 x 6 mm 100 m Roll 3,500,000.00
56 Kabel Listrik NYA 1.5 mm 100 m Roll 217,000.00
57 Kabel Listrik NYA 2.5 mm 100 m Roll 350,000.00
58 Kabel Listrik NYA 4 mm 100 m Roll
59 Kabel Listrik NYA 5 mm 100 m Roll
60 Kabel Telepon 4x0,5 mm M
61 Outlet TV Buah
62 Outlet Telepon Buah
63 Isolasi Buah
64 Lampu Pijar (Gelas)115/125 -
65 5 Watt Clear Buah 6,000.00
66 10 Watt Clear Buah 6,000.00
67 15 Watt Clear Buah 8,000.00
68 25 Watt Clear Buah 11,000.00
69 40 Watt Clear Buah 11,000.00
70 60 Watt Clear Buah 11,000.00
71 75 Watt Clear Buah 12,000.00
72 100 Watt Clear Buah 25,000.00
73 150 Watt Clear Buah
74 200 Watt Clear Buah
75 25 Watt Septum Buah
76 40 Watt Septum Buah
77 60 Watt Septum Buah
78 75 Watt Septum Buah
79 100 Watt Septum Buah
80 Lampu Essential 220-240 V E27 -
81 3 Watt Buah 33,000.00
82 5 Watt Buah 45,000.00
83 8 Watt Buah 47,000.00
84 11 Watt Buah 47,000.00
85 14 Watt Buah 47,000.00
86 18 Watt Buah 49,000.00
87 23 Watt Buah 51,000.00
88 35 Watt Buah 70,000.00
89 50 Watt Buah 114,000.00
90 70 Watt Buah 129,000.00
91 PJUTS LED 2 X 25 W, 100 - 120 WP Double Unit 32,742,000.00
Wing
Ornamen dengan Tiang Octogonal 7 m
Galvanis

92 PJUTS LED 2 X 25 W, 100 - 120 WP Double Unit 30,854,960.00


Wing
Ornamen dengan Tiang Octogonal 7 m
Galvanis

2.18. Bahan Bakar, Pelumas dan Peralatan Kerja


1 BBM (Premium) liter 6,450.00
2 BBM (Solar) liter 5,150.00
3 Bahan bakar minyak liter 5,150.00
4 Minyak pelumas (lubricants) liter 27,265.00
5 Minyak bekisting liter 15,000.00
6 Grease compound [Tube] kg 105,000.00
7 Bentonite - klas API/eqvl. zak 267,500.00
8 STPP (Mud Dispersant) kg 100,000.00
9 Biopolymer (Mud Additive) kg 150,000.00
10 Hexametaposphate kg 115,000.00
11 Jetting tools unit 6,750,000.00
12 Pelumas mesin Liter 58,500.00
13 Pelumas gardan Liter 58,500.00
14 Pelumas transmisi Liter 58,500.00
15 Oli SAE 40 Liter 43,750.00
16 Oli SAE 30 Liter 33,750.00
17 Oli SAE 10 Liter 35,875.00
18 Oli SAE 90 Liter 58,500.00
19 Oli SAE 140 Liter 58,500.00
20 Oli Hydrolis Liter 35,875.00
21 Gemuk Liter 62,500.00
22 Minyak Rim Liter 34,375.00
23 Air Accu Liter 10,875.00
24 Accu 12 V/60 A Buah 999,000.00
25 Ban 750/15 Buah 1,281,250.00
26 Ban 750/16 Buah 1,750,000.00
27 Ban 640/13 Buah 563,000.00
28 Ban 12.5/80 - 18 Buah 149,650.00
29 Ban 2.50 - 17 Buah 147,292.50
30 Ban 2.75 - 17 Buah 185,730.00
31 Ban 750/14 Buah 691,875.00
32 Ban Dalam 750/15 Buah 172,917.50
33 Ban Dalam 750/16 Buah 249,792.50
34 Ban Dalam 640/13 Buah 134,480.00
35 Ban Dalam 12,5/80-15 Buah 115,312.50
36 Ban Dalam 750/14 Buah 128,125.00
37 Ban Dalam 2,50/17 Buah 31,980.00
38 Saringan Udara Buah 85,000.00
39 Oil Filter Buah 85,000.00
40 Sewa Tripot/Tackel & handle crane 2 T 5,000,000.00

41 Manhole plat besi 70X70 cm Buah 500,000.00

Keterangan:
Ø = Diameter
Catatan :
Harga bahan (Mineral Batuan Bukan Logam) tersebut di atas belum termasuk :
1 Biaya Angkut dari Lokasi (Quary) ke Lokasi Proyek = Rp. 3.870/km/m3
2 Biaya lansiran 100 s/d 250 m = Rp. 20.000/M3.
3 Biaya lansiran 250 m s/d 500 m = Rp. 30.000/M3.
4 Biaya lansiran 500 m s/d 750 m = Rp. 40.000/M3.
5 Biaya lansiran 750 m s/d 1.000 m = Rp. 50.000/M3.
6 Pajak Daerah Mineral Batuan Bukan Logam (sesuai dengan peraturan dan ketentuan yang berlaku).
7 Apabila terdapat daftar barang yang tidak tercantum dalam Standar Harga Kabupaten Lombok Timur, maka dapat
PROGRAM PENYEDIAAN AIR MINUM DAN SANITASI BERBASIS MASYARAKAT
TAHUN ANGGARAN 2021

DAFTAR ANALISA HARGA SATUAN

A.2.3.1 ANALISA PEKERJAAN TANAH DAN PASIR

1 M3 PEK.GALIAN TANAH BIASA SEDALAM 1M A.2.3.1.1 83,025.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pekerja 0.750 OH 110,700.00 83,025.00
Tenaga
Mandor 0.025 OH - -
JUMLAH 83,025.00
Overhead 10% = -
Jumlah Total = 83,025.00

1 M3 PEK.GALIAN TANAH BIASA SEDALAM 2M A.2.3.1.2 99,630.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pekerja 0.900 OH 110,700.00 99,630.00
Tenaga
Mandor 0.045 OH - -
JUMLAH 99,630.00
Overhead 10% = -
Jumlah Total = 99,630.00

1 M3 URUGAN TANAH KEMBALI A.2.3.1.9 29,073.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pekerja 0.250 OH 110,700.00 27,675.00
Tenaga
Mandor 0.008 OH 174,800.00 1,398.40
JUMLAH 29,073.40
Overhead 10% = -
Jumlah Total = 29,073.40

1 M3 PEK.URUGAN PASIR A.2.3.1.11 261,638.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bahan Pasir urug 1.200 M3 188,900.00 226,680.00
Pekerja 0.300 OH 110,700.00 33,210.00
Tenaga
Mandor 0.010 OH 174,800.00 1,748.00
JUMLAH 261,638.00
Overhead 10% = -
Jumlah Total = 261,638.00

1 M3 PEK.URUGAN TANAH A.2.3.1.11a 115,718.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bahan Tanah Urug 1.200 M3 67,300.00 80,760.00
Pekerja 0.300 OH 110,700.00 33,210.00
Tenaga
Mandor 0.010 OH 174,800.00 1,748.00
JUMLAH 115,718.00
Overhead 10% = -
Jumlah Total = 115,718.00

1 M2 PEK. MEMBERSIHKAN LAPANGAN DAN PERATAAN A.2.2.1.9 19,810.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pekerja 0.100 OH 110,700.00 11,070.00
Tenaga
Mandor 0.050 OH 174,800.00 8,740.00
JUMLAH 19,810.00
Overhead 10% = -
Jumlah Total = 19,810.00
A.3.2.1 ANALISA BIAYA KONSTRUKSI PEKERJAAN PONDASI

1 M3 PEK.PEMASANGAN BATU KOSONG ( AANSTAMPING ) A.3.2.1.9 486,693.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Batu Kali Alam 1.200 M3 210,700.00 252,840.00
Bahan
Pasir urug 0.432 M3 188,900.00 81,604.80
Pekerja 0.780 OH 110,700.00 86,346.00
Tukang 0.390 OH 151,500.00 59,085.00
Tenaga
Kepala Tukang 0.039 OH - -
Mandor 0.039 OH 174,800.00 6,817.20
JUMLAH 486,693.00
Overhead 10% = -
Jumlah Total = 486,693.00

1 M3 PEK. PONDASI BATU BELAH, CAMPURAN 1PC : 4PS A.3.2.1.2 849,125.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Batu Kali Alam 1.200 M3 210,700.00 252,840.00
Bahan Semen 3.260 Zak 60,000.00 195,600.00
Pasir pasangan 0.520 M3 207,500.00 107,900.00
Pekerja 1.500 OH 110,700.00 166,050.00
Tukang 0.750 OH 151,500.00 113,625.00
Tenaga
Kepala Tukang 0.075 OH - -
Mandor 0.075 OH 174,800.00 13,110.00
JUMLAH 849,125.00
Overhead 10% = -
Jumlah Total = 849,125.00

1 M3 PEK. PONDASI BATU BELAH, CAMPURAN 1PC : 5PS A.3.2.1.3 821,705.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Batu Kali Alam 1.200 M3 210,700.00 252,840.00
Bahan Semen 2.720 Zak 60,000.00 163,200.00
Pasir pasangan 0.544 M3 207,500.00 112,880.00
Pekerja 1.500 OH 110,700.00 166,050.00
Tukang 0.750 OH 151,500.00 113,625.00
Tenaga
Kepala Tukang 0.075 OH - -
Mandor 0.075 OH 174,800.00 13,110.00
JUMLAH 821,705.00
Overhead 10% = -
Jumlah Total = 821,705.00

A.4.1.1 ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON

1 M3 BETON MUTU f 'c = 7,4 MPa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87 A.4.1.1.1 986,055.33
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 4.94 Zak 60,000.00 296,400.00
Pasir cor 0.6207 M3 214,800.00 133,329.43
Bahan
Batu pecah 2 - 3 cm 0.7400 M3 400,000.00 296,000.00
Air 215.00 liter 100.00 21,500.00
Pekerja 1.6500 OH 110,700.00 182,655.00
Tukang 0.2750 OH 151,500.00 41,662.50
Tenaga
Kepala Tukang 0.0280 OH - -
Mandor 0.0830 OH 174,800.00 14,508.40
JUMLAH 986,055.33
Overhead 10% = -
Jumlah Total = 986,055.33
1 M3 BETON MUTU f 'c = 14,5 MPa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66 A.4.1.1.5 768,131.61
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 6.52 Zak 60,000.00 391,200.00
Pasir cor 0.5429 M3 214,800.00 116,605.71
Bahan
Batu Pecah 2-3 cm 0.7622 M3 -
Air 215.00 liter 100.00 21,500.00
Pekerja 1.6500 OH 110,700.00 182,655.00
Tukang 0.2750 OH 151,500.00 41,662.50
Tenaga
Kepala Tukang 0.0280 OH - -
Mandor 0.0830 OH 174,800.00 14,508.40
768,131.61
Overhead 10% = -
Jumlah Total = 768,131.61

1 Kg PEK. PEMBESIAN DENGAN BESI POLOS/ULIR A.4.1.1.17 23,482.82


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Besi Beton Polos 1.0500 Kg 20,050.00 21,052.50
Bahan
Kawat Ikat Beton 0.0150 Kg 35,000.00 525.00
Pekerja 0.0070 OH 110,700.00 774.90
Tukang 0.0070 OH 151,500.00 1,060.50
Tenaga
Kepala Tukang 0.0007 OH - -
Mandor 0.0004 OH 174,800.00 69.92
JUMLAH 23,482.82
Overhead 10% = -
Jumlah Total = 23,482.82

1 M2 PEK. BEKISTING UNTUK PONDASI A.4.1.1.20 329,046.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0400 m3 5,501,200.00 220,048.00
Bahan Paku 0.3000 kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 15,000.00 1,500.00
Pekerja 0.5200 OH 110,700.00 57,564.00
Tukang 0.2600 OH 151,500.00 39,390.00
Tenaga
Kepala Tukang 0.0260 OH - -
Mandor 0.0260 OH 174,800.00 4,544.80
JUMLAH 329,046.80
Overhead 10% = -
Jumlah Total = 329,046.80

1 M2 PEK. BEKISTING UNTUK SLOOF A.4.1.1.21 356,552.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0450 m3 5,501,200.00 247,554.00
Bahan Paku 0.3000 kg 20,000.00 6,000.00
Minyak Bekisting 0.1000 liter 15,000.00 1,500.00
Pekerja 0.5200 OH 110,700.00 57,564.00
Tukang 0.2600 OH 151,500.00 39,390.00
Tenaga
Kepala Tukang 0.0260 OH - -
Mandor 0.0260 OH 174,800.00 4,544.80
JUMLAH 356,552.80
Overhead 10% = -
Jumlah Total = 356,552.80
1 M2 PEK. BEKISTING UNTUK KOLOM A.4.1.1.22 550,041.40
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0400 m3 5,501,200.00 220,048.00
Paku 0.4000 kg 20,000.00 8,000.00
Minyak bekisting 0.2000 liter 15,000.00 3,000.00
Bahan
Balok Kayu Kelas III 0.0150 m3 5,501,200.00 82,518.00
Triplek besar 122x242 cm tebal 6 mm 0.3500 lembar 79,000.00 27,650.00
Bambu 2.0000 Batang 40,000.00 80,000.00
Pekerja 0.6600 OH 110,700.00 73,062.00
Tukang 0.3300 OH 151,500.00 49,995.00
Tenaga
Kepala Tukang 0.0330 OH - -
Mandor 0.0330 OH 174,800.00 5,768.40
JUMLAH 550,041.40
Overhead 10% = -
Jumlah Total = 550,041.40

1 M2 PEK. BEKISTING UNTUK BALOK A.4.1.1.23 566,545.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0400 m3 5,501,200.00 220,048.00
Paku 0.4000 kg 20,000.00 8,000.00
Minyak bekisting 0.2000 liter 15,000.00 3,000.00
Bahan
Balok Kayu Kelas III 0.0180 m3 5,501,200.00 99,021.60
Triplek besar 122x242 cm tebal 6 mm 0.3500 lembar 79,000.00 27,650.00
Bambu 2.0000 Batang 40,000.00 80,000.00
Pekerja 0.6600 OH 110,700.00 73,062.00
Tukang 0.3300 OH 151,500.00 49,995.00
Tenaga
Kepala Tukang 0.0330 OH - -
Mandor 0.0330 OH 174,800.00 5,768.40
JUMLAH 566,545.00
Overhead 10% = -
Jumlah Total = 566,545.00

1 M2 PEK. BEKISTING UNTUK PLAT LANTAI A.4.1.1.24 710,041.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0400 m3 5,501,200.00 220,048.00
Paku 0.4000 kg 20,000.00 8,000.00
Minyak bekisting 0.2000 liter 15,000.00 3,000.00
Bahan
Balok Kayu Kelas III 0.0150 m3 5,501,200.00 82,518.00
Triplek besar 122x242 cm tebal 6 mm 0.3500 lembar 79,000.00 27,650.00
Bambu 6.0000 Batang 40,000.00 240,000.00
Pekerja 0.6600 OH 110,700.00 73,062.00
Tukang 0.3300 OH 151,500.00 49,995.00
Tenaga
Kepala Tukang 0.0330 OH - -
Mandor 0.0330 OH 174,800.00 5,768.40
JUMLAH 710,041.40
Overhead 10% = -
Jumlah Total = 710,041.40

1 M2 PEK. BEKISTING UNTUK PLAT DINDING A.4.1.1.25 562,535.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0300 m3 5,501,200.00 165,036.00
Paku 0.4000 kg 20,000.00 8,000.00
Minyak bekisting 0.2000 liter 15,000.00 3,000.00
Bahan
Balok Kayu Kelas III 0.0200 m3 5,501,200.00 110,024.00
Triplek besar 122x242 cm tebal 6 mm 0.3500 lembar 79,000.00 27,650.00
Bambu 3.0000 Batang 40,000.00 120,000.00
Pekerja 0.6600 OH 110,700.00 73,062.00
Tukang 0.3300 OH 151,500.00 49,995.00
Tenaga
Kepala Tukang 0.0330 OH - -
Mandor 0.0330 OH 174,800.00 5,768.40
JUMLAH 562,535.40
Overhead 10% = -
Jumlah Total = 562,535.40
1 M3 PEK. BETON KOLOM PRAKTIS 11X11 CM (Besi 4Ø10 ; Bg. Ø6-15) - Type A A.4.1.1.35 109,605.40
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0020 m3 5,501,200.00 11,002.40
Paku 0.0100 kg 20,000.00 200.00
Minyak bekisting 0.0000 liter 15,000.00 -
Besi beton polos 3.0000 Kg 20,050.00 60,150.00
Bahan
Kawat Ikat Beton 0.0450 Kg 35,000.00 1,575.00
Semen 0.0800 Zak 60,000.00 4,800.00
Pasir cor 0.0060 M3 214,800.00 1,288.80
Batu Pecah 2-3 cm 0.0090 M3 -
Pekerja 0.1800 OH 110,700.00 19,926.00
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0090 OH 174,800.00 1,573.20
JUMLAH 109,605.40
Overhead 10% = -
Jumlah Total = 109,605.40

1 M1 PEK. BETON BALOK BERTULANG 10X15CM (Besi 4Ø10 ; Bg. Ø6-15) A.4.1.1.36 149,865.20
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Begisting 0.0030 m3 5,501,200.00 16,503.60
Paku 0.0200 kg 20,000.00 400.00
Minyak bekisting 0.0000 liter 15,000.00 -
Besi beton polos 3.6000 Kg 20,050.00 72,180.00
Bahan
Kawat Ikat Beton 0.0500 Kg 35,000.00 1,750.00
Semen 0.1100 Zak 60,000.00 6,600.00
Pasir cor 0.0090 M3 214,800.00 1,933.20
Batu Pecah 2-3 cm 0.0150 M3 -
Pekerja 0.2970 OH 110,700.00 32,877.90
Tukang 0.0990 OH 151,500.00 14,998.50
Tenaga
Kepala Tukang 0.0100 OH - -
Mandor 0.0150 OH 174,800.00 2,622.00
JUMLAH 149,865.20
Overhead 10% = -
Jumlah Total = 149,865.20

A.4.4.1 ANALISA PEKERJAAN DINDING

1 M2 PEK. DINDING UK.( 5 X 11 X 22 ) CM TEBAL 1 BATA, CAMP. 1C : 3PS A.4.4.1.2 370,386.50


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bata merah 140.000 Buah 1,500.00 210,000.00
Bahan Semen 0.659 Zak 60,000.00 39,540.00
Pasir pasangan 0.091 M3 207,500.00 18,882.50
Pekerja 0.600 OH 110,700.00 66,420.00
Tukang 0.200 OH 151,500.00 30,300.00
Tenaga
Kepala Tukang 0.020 OH - -
Mandor 0.030 OH 174,800.00 5,244.00
JUMLAH 370,386.50
Overhead 10% = -
Jumlah Total = 370,386.50
1 M2 PEK. DINDING UK.( 5 X 11 X 22 ) CM TEBAL 1 BATA, CAMP. 1C : 5PS A.4.4.1.4 359,769.00
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bata merah 140.000 Buah 1,500.00 210,000.00
Bahan Semen 0.444 Zak 60,000.00 26,640.00
Pasir pasangan 0.102 M3 207,500.00 21,165.00
Pekerja 0.600 OH 110,700.00 66,420.00
Tukang 0.200 OH 151,500.00 30,300.00
Tenaga
Kepala Tukang 0.020 OH - -
Mandor 0.030 OH 174,800.00 5,244.00
JUMLAH 359,769.00
Overhead 10% = -
Jumlah Total = 359,769.00

1 M2 PEK. DINDING UK.( 5 X 11 X 22 ) CM TEBAL 1/2 BATA, CAMP. 1C : 3PS A.4.4.1.8 181,526.00
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bata merah 70.000 Buah 1,500.00 105,000.00
Bahan Semen 0.287 Zak 60,000.00 17,244.00
Pasir pasangan 0.040 M3 207,500.00 8,300.00
Pekerja 0.300 OH 110,700.00 33,210.00
Tukang 0.100 OH 151,500.00 15,150.00
Tenaga
Kepala Tukang 0.010 OH - -
Mandor 0.015 OH 174,800.00 2,622.00
JUMLAH 181,526.00
Overhead 10% = -
Jumlah Total = 181,526.00

1 M2 PEK. DINDING UK.( 5 X 11 X 22 ) CM TEBAL 1/2 BATA, CAMP. 1C : 5PS A.4.4.1.10 176,935.50
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bata merah 70.000 Buah 1,500.00 105,000.00
Bahan Semen 0.194 Zak 60,000.00 11,616.00
Pasir pasangan 0.045 M3 207,500.00 9,337.50
Pekerja 0.300 OH 110,700.00 33,210.00
Tukang 0.100 OH 151,500.00 15,150.00
Tenaga
Kepala Tukang 0.010 OH - -
Mandor 0.015 OH 174,800.00 2,622.00
JUMLAH 176,935.50
Overhead 10% = -
Jumlah Total = 176,935.50

A.4.4.2 ANALISA PEKERJAAN PLESTERAN


1 M2 PLESTERAN 1PC : 3PS TEBAL 15 mm A.4.4.2.3 72,660.70
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 0.1555 Zak 60,000.00 9,331.20
Bahan
Pasir pasangan 0.0230 M3 207,500.00 4,772.50
Pekerja 0.3000 OH 110,700.00 33,210.00
Tukang 0.1500 OH 151,500.00 22,725.00
Tenaga
Kepala Tukang 0.0150 OH - -
Mandor 0.0150 OH 174,800.00 2,622.00
JUMLAH 72,660.70
Overhead 10% = -
Jumlah Total = 72,660.70

1 M2 PLESTERAN 1PC : 5PS TEBAL 15 mm A.4.4.2.5 70,172.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 0.1037 Zak 60,000.00 6,220.80
Bahan
Pasir pasangan 0.0260 M3 207,500.00 5,395.00
Pekerja 0.3000 OH 110,700.00 33,210.00
Tukang 0.1500 OH 151,500.00 22,725.00
Tenaga
Kepala Tukang 0.0150 OH - -
Mandor 0.0150 OH 174,800.00 2,622.00
JUMLAH 70,172.80
Overhead 10% = -
Jumlah Total = 70,172.80

1 M2 ACIAN PC A.4.4.2.27 42,938.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bahan Semen 0.0650 Zak 60,000.00 3,900.00
Pekerja 0.2000 OH 110,700.00 22,140.00
Tukang 0.1000 OH 151,500.00 15,150.00
Tenaga
Kepala Tukang 0.0100 OH - -
Mandor 0.0100 OH 174,800.00 1,748.00
JUMLAH 42,938.00
Overhead 10% = -
Jumlah Total = 42,938.00

1 M2 ACIAN PC + Mill A.4.4.2.27a 42,504.60


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 0.0217 Zak 60,000.00 1,299.60
Bahan
Mil 2.1670 kg 1,000.00 2,167.00
Pekerja 0.2000 OH 110,700.00 22,140.00
Tukang 0.1000 OH 151,500.00 15,150.00
Tenaga
Kepala Tukang 0.0100 OH - -
Mandor 0.0100 OH 174,800.00 1,748.00
JUMLAH 42,504.60
Overhead 10% = -
Jumlah Total = 42,504.60
1 M2 SIARAN DG MORTAR PC-PP TYPE M (un. mutu PP tertentu setara dg camp. 1 PC:2 PP) P.03a 71,277.00
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Semen 0.1268 Zak 60,000.00 7,608.00
Bahan
Pasir pasangan 0.0120 M3 207,500.00 2,490.00
Pekerja 0.3000 OH 110,700.00 33,210.00
Tukang 0.1500 OH 151,500.00 22,725.00
Tenaga
Kepala Tukang 0.0150 OH - -
Mandor 0.0300 OH 174,800.00 5,244.00
JUMLAH 71,277.00
Overhead 10% = -
Jumlah Total = 71,277.00

ANALISA BIAYA PEKERJAAN PENUTUP LANTAI DAN DINDING

1 M2 LANTAI KERAMIK (20X20) CM A.4.4.3.36 253,370.50


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Keramik Lantai KM 20x20 Kwalitas Sedang 1.0000 M2 69,000.00 69,000.00
Semen 0.2080 Zak 60,000.00 12,480.00
Bahan
Pasir pasangan 0.0450 M3 207,500.00 9,337.50
Semen warna 1.6200 Kg 16,000.00 25,920.00
Pekerja 0.7000 OH 110,700.00 77,490.00
Tukang 0.3500 OH 151,500.00 53,025.00
Tenaga
Kepala Tukang 0.0350 OH - -
Mandor 0.0350 OH 174,800.00 6,118.00
JUMLAH 253,370.50
Overhead 10% = -
Jumlah Total = 253,370.50

1 M2 DINDING KERAMIK (20X25) CM A.4.4.3.54 #N/A


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Keramik Dinding KM 20x25 Kwalitas Sedang 1.0000 #N/A #N/A #N/A
Semen 0.1860 Zak 60,000.00 11,160.00
Bahan
Pasir pasangan 0.0180 M3 207,500.00 3,735.00
Semen warna 1.9400 Kg 16,000.00 31,040.00
Pekerja 0.9000 OH 110,700.00 99,630.00
Tukang 0.4500 OH 151,500.00 68,175.00
Tenaga
Kepala Tukang 0.0450 OH - -
Mandor 0.0450 OH 174,800.00 7,866.00
JUMLAH #N/A
Overhead 10% = #N/A
Jumlah Total = #N/A

A.4.5.1. ANALISA BIAYA PEKERJAAN LANGIT-LANGIT (PLAFOND)

1 M2 LANGIT-LANGIT CALSIBOARD 120X240X3 MM A.4.5.1.7a 45,861.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Kalsiboard 122 x 240 x 4 mm 0.3640 lembar 63,000.00 22,932.00
Bahan
Paku Eternit 0.1100 kg 31,000.00 3,410.00
Pekerja 0.1000 OH 110,700.00 11,070.00
Tukang 0.0500 OH 151,500.00 7,575.00
Tenaga
Kepala Tukang 0.0050 OH - -
Mandor 0.0050 OH 174,800.00 874.00
JUMLAH 45,861.00
Overhead 10% = -
Jumlah Total = 45,861.00
A.4.5.2. ANALISA BIAYA PEKERJAAN PENUTUP ATAP

1 M2 PEKERJAAN ATAP SENG GELOMBANG BJLS.25 A.4.5.2.38 49,722.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Spandek 3 mm lebar 70 cm 0.7000 meter 37,000.00 25,900.00
Bahan
Paku 0.0200 kg 20,000.00 400.00
Pekerja 0.1200 OH 110,700.00 13,284.00
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0060 OH 174,800.00 1,048.80
JUMLAH 49,722.80
Overhead 10% = -
Jumlah Total = 49,722.80

1 M2 PEKERJAAN ATAP SPANDEK 3 MM A.4.5.2.38a 49,922.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Spandek 3 mm lebar 70 cm 0.7000 meter 37,000.00 25,900.00
Bahan
Baut spandek 0.0200 Kg 30,000.00 600.00
Pekerja 0.1200 OH 110,700.00 13,284.00
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0060 OH 174,800.00 1,048.80
JUMLAH 49,922.80
Overhead 10% = -
Jumlah Total = 49,922.80

1 M' PEKERJAAN NOK ATAP SENG A.4.5.2.39 90,058.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Seng Plat BJLS 25 1.0000 lembar 61,000.00 61,000.00
Bahan
Paku 0.0400 kg 20,000.00 800.00
Pekerja 0.1500 OH 110,700.00 16,605.00
Tukang 0.0700 OH 151,500.00 10,605.00
Tenaga
Kepala Tukang 0.0070 OH - -
Mandor 0.0060 OH 174,800.00 1,048.80
JUMLAH 90,058.80
Overhead 10% = -
Jumlah Total = 90,058.80

1 M' PEKERJAAN NOK ATAP SENG A.4.5.2.39 90,058.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Seng Plat BJLS 25 1.0000 lembar 61,000.00 61,000.00
Bahan
Paku 0.0400 kg 20,000.00 800.00
Pekerja 0.1500 OH 110,700.00 16,605.00
Tukang 0.0700 OH 151,500.00 10,605.00
Tenaga
Kepala Tukang 0.0070 OH - -
Mandor 0.0060 OH 174,800.00 1,048.80
JUMLAH 90,058.80
Overhead 10% = -
Jumlah Total = 90,058.80

A.4.6.1. ANALISA BIAYA PEKERJAAN KAYU

1 M3 KUSEN PINTU/JENDELA KAYU KELAS II A.4.6.1.2 8,684,520.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Balok Kayu Klas II 1.2000 m3 4,312,400.00 5,174,880.00
Bahan Paku 1.2500 kg 20,000.00 25,000.00
Lem kayu 1.0000 Kg 41,000.00 41,000.00
Pekerja 6.0000 OH 110,700.00 664,200.00
Tukang 18.0000 OH 151,500.00 2,727,000.00
Tenaga
Kepala Tukang 1.8000 OH - -
Mandor 0.3000 OH 174,800.00 52,440.00
JUMLAH 8,684,520.00
Overhead 10% = -
Jumlah Total = 8,684,520.00
1 M2 DAUN PINTU PANIL KAYU KELAS II A.4.6.1.5 766,936.00
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Papan Kayu Klas II 0.0400 m3 4,312,400.00 172,496.00
Bahan
Lem kayu 0.5000 Kg 41,000.00 20,500.00
Pekerja 1.0000 OH 110,700.00 110,700.00
Tukang 3.0000 OH 151,500.00 454,500.00
Tenaga
Kepala Tukang 0.3000 OH - -
Mandor 0.0500 OH 174,800.00 8,740.00
JUMLAH 766,936.00
Overhead 10% = -
Jumlah Total = 766,936.00

1 M2 DAUN PINTU PLAYWOOD RANGKAP, KAYU KELAS II A.4.6.1.8 650,668.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Balok Kayu Klas II 0.0250 m3 4,312,400.00 107,810.00
Paku 0.0300 kg 20,000.00 600.00
Bahan
Lem kayu 0.5000 Kg 41,000.00 20,500.00
Triplek 122x244x9 mm 1.0000 lembar 120,000.00 120,000.00
Pekerja 0.7000 OH 110,700.00 77,490.00
Tukang 2.1000 OH 151,500.00 318,150.00
Tenaga
Kepala Tukang 0.2100 OH - -
Mandor 0.0350 OH 174,800.00 6,118.00
JUMLAH 650,668.00
Overhead 10% = -
Jumlah Total = 650,668.00

1 UNIT KUSEN PINTU FIBERGLASS KM/WC A.4.6.1.8a #REF!


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Bahan Pintu Fiberglass KM/WC 1.000 #REF! #REF! #REF!
Pekerja 0.1750 #REF! #REF! #REF!
Tukang 0.5250 #REF! #REF! #REF!
Tenaga
Kepala Tukang 0.0525 #REF! - -
Mandor 0.0088 #REF! #REF! #REF!
JUMLAH #REF!
Overhead 10% = #REF!
Jumlah Total = #REF!

1 M3 KONSTRUKSI GORDENG, KAYU KELAS II A.4.6.1.15 5,965,476.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Balok Kayu Klas II 1.0500 m3 4,312,400.00 4,528,020.00
Bahan Besi strip tebal 5 mm 15.0000 -
Paku 3.0000 kg 20,000.00 60,000.00
Pekerja 2.4000 OH 110,700.00 265,680.00
Tukang 7.2000 OH 151,500.00 1,090,800.00
Tenaga
Kepala Tukang 0.7200 OH - -
Mandor 0.1200 OH 174,800.00 20,976.00
JUMLAH 5,965,476.00
Overhead 10% = -
Jumlah Total = 5,965,476.00

1 M2 RANGKA LANGIT-LANGIT (60X60) CM KAYU KLAS II A.4.6.1.20 144,630.12


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Balok Kayu Klas II 0.0163 m3 4,312,400.00 70,292.12
Bahan
Paku 0.2500 kg 20,000.00 5,000.00
Pekerja 0.2000 OH 110,700.00 22,140.00
Tukang 0.3000 OH 151,500.00 45,450.00
Tenaga
Kepala Tukang 0.0300 OH - -
Mandor 0.0100 OH 174,800.00 1,748.00
JUMLAH 144,630.12
Overhead 10% = -
Jumlah Total = 144,630.12

1 M1 PASANGAN LISPLANK KALSIPLANK 8MM-20CM A.4.6.1.21a 38,019.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Kalsiplank ukuran (8X20) cm 1.1000 Meter 15,000.00 16,500.00
Bahan
Paku 0.1000 kg 20,000.00 2,000.00
Pekerja 0.1000 OH 110,700.00 11,070.00
Tukang 0.0500 OH 151,500.00 7,575.00
Tenaga
Kepala Tukang 0.0200 OH - -
Mandor 0.0050 OH 174,800.00 874.00
JUMLAH 38,019.00
Overhead 10% = -
Jumlah Total = 38,019.00
A.4.7.1 ANALISA PEKERJAAN PENGECATAN

1 M2 CAT TEMBOK - (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.10 35,582.90
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Plamir Tembok 0.1000 kg 47,000.00 4,700.00
Cat tembok 0.3600 kg 35,000.00 12,600.00
Bahan Ampelas 0.2000 lembar 30,000.00 6,000.00
Kape 0.0100 -
Kuas 0.0100 -
Pekerja 0.0200 OH 110,700.00 2,214.00
Tukang 0.0630 OH 151,500.00 9,544.50
Tenaga
Kepala Tukang 0.0063 OH - -
Mandor 0.0030 OH 174,800.00 524.40
JUMLAH 35,582.90
Overhead 10% = -
Jumlah Total = 35,582.90

1 M2 CAT KAYU - (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup) A.4.7.1.4 44,726.90
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Meni Kayu 0.2000 kg 56,000.00 11,200.00
Plamir kayu 0.1500 kg 40,000.00 6,000.00
Cat Kayu Mutu Sedang 0.1700 kg 62,000.00 10,540.00
Bahan
Kuas 1" 0.0100 Buah 15,000.00 150.00
Minyak Cat biasa 0.0300 Liter 40,000.00 1,200.00
Ampelas 0.2000 lembar 30,000.00 6,000.00
Pekerja 0.0700 OH 110,700.00 7,749.00
Tukang 0.0090 OH 151,500.00 1,363.50
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0030 OH 174,800.00 524.40
JUMLAH 44,726.90
Overhead 10% = -
Jumlah Total = 44,726.90

1 M2 PENGECATAN PERMUKAAN BAJA GALVANIS SEC. MANUAL 3 LAPIS A.4.7.1.20 #REF!


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Cat Besi 0.3600 #REF! #REF! #REF!
Bahan Minyak Cat 0.0100 #REF! #REF! #REF!
Kuas 0.0100 #REF! #REF! #REF!
Pekerja 0.0400 #REF! #REF! #REF!
Tukang 0.0800 #REF! #REF! #REF!
Tenaga
Kepala Tukang 0.0080 #REF! #REF! #REF!
Mandor 0.0020 #REF! #REF! #REF!
JUMLAH #REF!
Overhead 10% = #REF!
Jumlah Total = #REF!

1 M2 CAT GENTENG A.4.7.1.20a 36,127.60


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Cat Genteng 0.3600 kg 53,000.00 19,080.00
Bahan
Kuas 1" 0.0100 Buah 15,000.00 150.00
Pekerja 0.0400 OH 110,700.00 4,428.00
Tukang 0.0800 OH 151,500.00 12,120.00
Tenaga
Kepala Tukang 0.0080 OH - -
Mandor 0.0020 OH 174,800.00 349.60
JUMLAH 36,127.60
Overhead 10% = -
Jumlah Total = 36,127.60
A.5.1.1. ANALISA BIAYA PEKERJAAN SANITASI

1 UNIT CLOSET DUDUK A.5.1.1.1 2,679,928.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Closet Duduk Lengkap Kwalitas Sedang 1.0000 Set 2,000,000.00 2,000,000.00
Bahan Perlengkapan (6 x harga kloset) 6.0000 % 120,000.00

Pekerja 3.3000 OH 110,700.00 365,310.00


Tukang 1.1000 OH 151,500.00 166,650.00
Tenaga
Kepala Tukang 0.0100 OH - -
Mandor 0.1600 OH 174,800.00 27,968.00
JUMLAH 2,679,928.00
Overhead 10% = -
Jumlah Total = 2,679,928.00

1 UNIT CLOSET JONGKOK PORSELIN A.5.1.1.2 2,051,810.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Closet Duduk Lengkap Kwalitas Sedang 1.0000 Set 2,000,000.00 2,000,000.00
Bahan Semen 0.1200 Zak 60,000.00 7,200.00
Pasir pasangan 0.0100 M3 207,500.00 2,075.00
Pekerja 0.1000 OH 110,700.00 11,070.00
Tukang 0.1500 OH 151,500.00 22,725.00
Tenaga
Kepala Tukang 0.0150 OH - -
Mandor 0.0500 OH 174,800.00 8,740.00
JUMLAH 2,051,810.00
Overhead 10% = -
Jumlah Total = 2,051,810.00

1 UNIT WESTAFEL A.5.1.1.12 798,771.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Wastafel Kwalitas Sedang 1.0000 Set 700,000.00 700,000.00
Bahan Waterdrain 1.0000 Buah 50,000.00 50,000.00

Pekerja 0.0300 OH 110,700.00 3,321.00


Tukang 0.3000 OH 151,500.00 45,450.00
Tenaga
Kepala Tukang OH - -
Mandor OH 174,800.00 -
JUMLAH 798,771.00
Overhead 10% = -
Jumlah Total = 798,771.00

A.5.1.1. ANALISA BIAYA PEKERJAAN PEMASANGAN PIPA

1 M' PIPA GI DIAMETER 1/2" A.5.1.1.1 56,332.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 1/2" 1.0000 Meter 32,000.00 32,000.00
Bahan
Perlengkapan 0.0000 % 11,200.00 -
Pekerja 0.0540 OH 110,700.00 5,977.80
Tukang 0.0900 OH 151,500.00 13,635.00
Tenaga
Kepala Tukang 0.0090 OH - -
Mandor 0.0270 OH 174,800.00 4,719.60
JUMLAH 56,332.40
Overhead 10% = -
Jumlah Total = 56,332.40

1 M' PIPA GI DIAMETER 1" A.5.1.1.21 80,332.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 1" 1.0000 Meter 56,000.00 56,000.00
Bahan
Perlengkapan % -
Pekerja 0.0540 OH 110,700.00 5,977.80
Tukang 0.0900 OH 151,500.00 13,635.00
Tenaga
Kepala Tukang 0.0090 OH - -
Mandor 0.0270 OH 174,800.00 4,719.60
JUMLAH 80,332.40
Overhead 10% = -
Jumlah Total = 80,332.40
1 M' PIPA GI DIAMETER 1,5" A.5.1.1.22 175,099.60
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 1,5" 1.0000 Meter 135,000.00 135,000.00
Bahan
Perlengkapan % -
Pekerja 0.1080 OH 110,700.00 11,955.60
Tukang 0.1800 OH 151,500.00 27,270.00
Tenaga
Kepala Tukang 0.0180 OH - -
Mandor 0.0050 OH 174,800.00 874.00
JUMLAH 175,099.60
Overhead 10% = -
Jumlah Total = 175,099.60

1 M' PIPA GI DIAMETER 3" A.5.1.1.23 315,955.60


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 3" 1.0000 Meter 265,700.00 265,700.00
Bahan
Perlengkapan % -
Pekerja 0.1350 OH 110,700.00 14,944.50
Tukang 0.2250 OH 151,500.00 34,087.50
Tenaga
Kepala Tukang 0.0230 OH - -
Mandor 0.0070 OH 174,800.00 1,223.60
JUMLAH 315,955.60
Overhead 10% = -
Jumlah Total = 315,955.60

1 M' PIPA GI DIAMETER 4" A.5.1.1.23 300,255.60


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 4" 1.0000 Meter 250,000.00 250,000.00
Bahan
Perlengkapan % -
Pekerja 0.1350 OH 110,700.00 14,944.50
Tukang 0.2250 OH 151,500.00 34,087.50
Tenaga
Kepala Tukang 0.0230 OH - -
Mandor 0.0070 OH 174,800.00 1,223.60
JUMLAH 300,255.60
Overhead 10% = -
Jumlah Total = 300,255.60

1 M' PIPA GI DIAMETER 6" A.5.1.1.23 573,567.30


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
PIPA Galpanis (GI Medium A) Ø 6" 1.0000 Meter 478,000.00 478,000.00
Bahan
Perlengkapan % -
Pekerja 0.5060 OH 110,700.00 56,014.20
Tukang 0.2530 OH 151,500.00 38,329.50
Tenaga
Kepala Tukang 0.0230 OH - -
Mandor 0.0070 OH 174,800.00 1,223.60
JUMLAH 573,567.30
Overhead 10% = -
Jumlah Total = 573,567.30

1 M' KRAN DIAMETER 1/2" A.5.1.1.19 141,581.00


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Stop Kran Ø 1/2" 1.0000 Buah 79,000.00 79,000.00
Bahan
Perlengkapan % -
Pekerja 0.0100 OH 110,700.00 1,107.00
Tukang 0.4000 OH 151,500.00 60,600.00
Tenaga
Kepala Tukang 0.0400 OH - -
Mandor 0.0050 OH 174,800.00 874.00
JUMLAH 141,581.00
Overhead 10% = -
Jumlah Total = 141,581.00
1 M' PIPA PVC DIAMETER 1/2" A.5.1.1.25 20,424.80
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa PVC bertekanan (AW) Ø 1/2" 1.0000 Meter 7,000.00 7,000.00
Bahan
Perlengkapan % -
Pekerja 0.0360 OH 110,700.00 3,985.20
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0020 OH 174,800.00 349.60
JUMLAH 20,424.80
Overhead 10% = -
Jumlah Total = 20,424.80

1 M' PIPA PVC DIAMETER 3/4" A.5.1.1.26 25,424.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 6.3 SNI Ø 3/4" 1.0000 Meter 12,000.00 12,000.00
Bahan
Perlengkapan % -
Pekerja 0.0360 OH 110,700.00 3,985.20
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0020 OH 174,800.00 349.60
JUMLAH 25,424.80
Overhead 10% = -
Jumlah Total = 25,424.80

1 M' PIPA PVC DIAMETER 1" A.5.1.1.27 28,424.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 10 SNIØ 1" 1.0000 Meter 15,000.00 15,000.00
Bahan
Perlengkapan % -
Pekerja 0.0360 OH 110,700.00 3,985.20
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0020 OH 174,800.00 349.60
JUMLAH 28,424.80
Overhead 10% = -
Jumlah Total = 28,424.80

1 M' PIPA PVC DIAMETER 1 1/2" A.5.1.1.28 38,424.80


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 1,5" 1.0000 Meter 25,000.00 25,000.00
Bahan
Perlengkapan % -
Pekerja 0.0360 OH 110,700.00 3,985.20
Tukang 0.0600 OH 151,500.00 9,090.00
Tenaga
Kepala Tukang 0.0060 OH - -
Mandor 0.0020 OH 174,800.00 349.60
JUMLAH 38,424.80
Overhead 10% = -
Jumlah Total = 38,424.80
1 M' PIPA PVC DIAMETER 2" A.5.1.1.29 42,417.76
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 2" 1.0000 Meter 25,666.00 25,666.00
Bahan
Perlengkapan % - -
Pekerja 0.0540 OH 110,700.00 5,977.80
Tukang 0.0680 OH 151,500.00 10,302.00
Tenaga
Kepala Tukang 0.0068 OH - -
Mandor 0.0027 OH 174,800.00 471.96
JUMLAH 42,417.76
Overhead 10% = -
Jumlah Total = 42,417.76

1 M' PIPA PVC DIAMETER 2 1/2" A.5.1.1.30 60,751.76


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 2,5" 1.0000 Meter 44,000.00 44,000.00
Bahan
Perlengkapan % -
Pekerja 0.0540 OH 110,700.00 5,977.80
Tukang 0.0680 OH 151,500.00 10,302.00
Tenaga
Kepala Tukang 0.0068 OH - -
Mandor 0.0027 OH 174,800.00 471.96
JUMLAH 60,751.76
Overhead 10% = -
Jumlah Total = 60,751.76

1 M' PIPA PVC DIAMETER 3" A.5.1.1.31 85,118.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 3" 1.0000 Meter 55,000.00 55,000.00
Bahan
Perlengkapan % - -
Pekerja 0.0810 OH 110,700.00 8,966.70
Tukang 0.1350 OH 151,500.00 20,452.50
Tenaga
Kepala Tukang 0.0135 OH - -
Mandor 0.0040 OH 174,800.00 699.20
JUMLAH 85,118.40
Overhead 10% = -
Jumlah Total = 85,118.40
1 M' PIPA PVC DIAMETER 4" A.5.1.1.32 120,118.40
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 4" 1.0000 Meter 90,000.00 90,000.00
Bahan
Perlengkapan % -
Pekerja 0.0810 OH 110,700.00 8,966.70
Tukang 0.1350 OH 151,500.00 20,452.50
Tenaga
Kepala Tukang 0.0135 OH - -
Mandor 0.0040 OH 174,800.00 699.20
JUMLAH 120,118.40
Overhead 10% = -
Jumlah Total = 120,118.40

1 M' PIPA PVC DIAMETER 6" A.5.1.1.33 222,118.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa S 12,5 SNI Ø 6" 1.0000 Meter 192,000.00 192,000.00
Bahan
Perlengkapan % -
Pekerja 0.0810 OH 110,700.00 8,966.70
Tukang 0.1350 OH 151,500.00 20,452.50
Tenaga
Kepala Tukang 0.0135 OH - -
Mandor 0.0040 OH 174,800.00 699.20
JUMLAH 222,118.40
Overhead 10% = -
Jumlah Total = 222,118.40

1 M' PIPA HDPE DIAMETER 63" A.8.4.1.17 68,974.40


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa HDPE Ø 2" 1.0000 Meter 62,000.00 62,000.00
Bahan
Perlengkapan % -
Alat Sewa Tripot/Tackel & handle crane 2 T 0.0190 #N/A - -
Pekerja 0.0350 OH 110,700.00 3,874.50
Tukang 0.0170 OH 151,500.00 2,575.50
Tenaga
Kepala Tukang 0.0000 OH - -
Mandor 0.0030 OH 174,800.00 524.40
JUMLAH 68,974.40
Overhead 10% = -
Jumlah Total = 68,974.40
1 M' PIPA HDPE DIAMETER 100" A.8.4.1.18 143,157.20
Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa HDPE Ø 4" 1.0000 Meter 135,000.00 135,000.00
Bahan
Perlengkapan % -
Alat Sewa Tripot/Tackel & handle crane 2 T 0.0190 #N/A - -
Pekerja 0.0400 OH 110,700.00 4,428.00
Tukang 0.0200 OH 151,500.00 3,030.00
Tenaga
Kepala Tukang 0.0000 OH - -
Mandor 0.0040 OH 174,800.00 699.20
JUMLAH 143,157.20
Overhead 10% = -
Jumlah Total = 143,157.20

1 M' PIPA HDPE DIAMETER 150" A.8.4.1.19 294,433.90


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Pipa HDPE Ø 6" 1.0000 Meter 282,000.00 282,000.00
Bahan
Perlengkapan % -
Alat Sewa Tripot/Tackel & handle crane 2 T 0.0190 #N/A - -
Pekerja 0.0620 OH 110,700.00 6,863.40
Tukang 0.0310 OH 151,500.00 4,696.50
Tenaga
Kepala Tukang 0.0000 OH - -
Mandor 0.0050 OH 174,800.00 874.00
JUMLAH 294,433.90
Overhead 10% = -
Jumlah Total = 294,433.90

1 M' BUIS BETON DIA. 80 CM RSNI T - 15 - 2002 (6.10) 555,806.60


Harga Satuan Jumlah
Kebutuhan Indeks Satuan
Bahan / Upah (Rp.) (Rp.)
Buis Beton Ø 80 Cm panjang 0,50 m 1.0000 Buah 250,000.00 250,000.00
Bata Merah 18.9000 Buah 1,500.00 28,350.00
Bahan Semen 3.9200 Zak 60,000.00 235,200.00
Pasir Pasangan 0.0560 M3 207,500.00 11,620.00
Pasir urug 0.0240 M3 188,900.00 4,533.60
Pekerja 0.1400 OH 110,700.00 15,498.00
Tukang 0.0700 OH 151,500.00 10,605.00
Tenaga
Kepala Tukang 0.0000 OH - -
Mandor 0.0000 OH 174,800.00 -
JUMLAH 555,806.60
Overhead 10% = -
Jumlah Total = 555,806.60

Batas analisa

A.5.1.1.Ls.SP.1 MEMASANG /MEMBUAT 1 UNIT SEPTICTANK BUIS 80 cm


Harga Satuan Jumlah Harga
No. Uraian Satuan Koefisien
(Rp.) (Rp.)
A BAHAN
1 Galian tanah (dalam 1m) m³ 0.7850 110,700.00 86,899.50
2 Urugan Pasir T.10cm m³ Harga Satuan - -
3 Pas. Buis beton Ø 80cm Panjang 0,5 m bh 2.0000 250,000.00 500,000.00
4 Pipa hawa PVC Ø 2'' m' - - -
5 Pekerjaan plat beton T. 10cm m³ - - -
6 Pipa PVC Ø 4'' (plat dan dari resapan) m' - - -
7 Dop Pipa Ø 4'' bh - - -
JUMLAH HARGA BAHAN/TENAGA 586,899.50
B JUMLAH 586,899.50
Titik 1titik Tapping Pipa Kode Analisa : TP.2
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 4.0000 110,700.00 442,800.00

2. Tukang Pipa OH 2.0000 151,500.00 303,000.00


3. Kepala tukang pipa OH 0.2000 - -

B. BAHAN
1. Pemasangan Accessories ls 1.0000 55,000.00 55,000.00
2. Galian Tanah Campuran m3 0.2700 51,480.00 13,899.60
3. Timbunan Tanah Kembali dipa m3 0.1080 21,395.00 2,310.66

C. PERALATAN
Alat Bantu (0,5 % x (UP+BHN) ls 1.0000 2,738.05 2,738.05

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 819,748.31


OVER HEAD DAN KEUNTUNGA10% -
HARGA SATUAN DILUAR PPN 819,748.31

M' 6 M Pemasangan Pipa GI Ø 100 mm (4") Kode Analisa : Pg.4


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 1.2150 110,700.00 134,500.50

3. Tukang Pipa OH 2.2050 151,500.00 334,057.50


4. Kepala tukang pipa OH 0.2026 0.00 -

B. BAHAN
Seal tape Buah 8.0000 9,000.00 72,000.00

C. PERALATAN
Alat bantu 0,05 % x (A+B) -

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 540,558.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 540,558.00
HARGA SATUAN DILUAR PPN / METER 90,093.00
M' 6 M Pemasangan Pipa GI Ø 75 mm (3") Kode Analisa : Pg.3
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.6075 110,700.00 67,250.25

3. Tukang Pipa OH 1.1025 151,500.00 167,028.75


4. Kepala tukang pipa OH 0.1013 0.00 -

B. BAHAN
Seal tape Buah 4.0000 9,000.00 36,000.00

C. PERALATAN
Alat bantu 0,05 % x (A+B) -

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 270,279.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 270,279.00
HARGA SATUAN DILUAR PPN / METER 45,046.50

M' 6 M Pemasangan Pipa PVC Ø 150 mm (6") Kode Analisa : Pp. 6


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.6075 110,700.00 67,250.25

3. Tukang Pipa OH 1.0125 151,500.00 153,393.75


4. Kepala tukang pipa OH 0.1013 0.00 -

B. BAHAN
1. Pelicin/Lubrican Kg 0.0386 0.00 -

C. PERALATAN
1. Alat Bantu 0,05 % x (A+B) Ls 1.0000 5,282.72 5,282.72

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 225,926.72


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 225,926.72
HARGA SATUAN DILUAR PPN / METER 37,654.45
M' 6 M Pemasangan Pipa PVC Ø 100 mm (4") Kode Analisa : Pp. 4
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.4860 110,700.00 53,800.20

3. Tukang Pipa OH 0.8100 151,500.00 122,715.00


4. Kepala tukang pipa OH 0.0810 0.00 -

B. BAHAN
1. Pelicin/Lubrican Kg 0.0222 0.00 -

C. PERALATAN
1. Alat Bantu 0,5 % x (A+B) Ls 1.0000 88,257.60 88,257.60

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 264,772.80


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 264,772.80
HARGA SATUAN DILUAR PPN / METER 44,128.80

M' 6 M Pemasangan Pipa PVC Ø 75 mm (3") Kode Analisa : Pp.3


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.4050 110,700.00 44,833.50

3. Tukang Pipa OH 0.6750 151,500.00 102,262.50


4. Kepala tukang pipa OH 0.0675 0.00 -

B. BAHAN
Lem PVC Kg 0.0125 0.00 -

C. PERALATAN

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 147,096.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 147,096.00
HARGA SATUAN DILUAR PPN / METER 24,516.00
M' 6 M Pemasangan Pipa PVC Ø 50 mm (2") Kode Analisa : Pp.2
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.3240 110,700.00 35,866.80

3. Tukang Pipa OH 0.5400 151,500.00 81,810.00


4. Kepala tukang pipa OH 0.0540 0.00 -

B. BAHAN
Lem PVC Kg 0.0080 0.00 -

C. PERALATAN

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 117,676.80


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 117,676.80
HARGA SATUAN DILUAR PPN / METER 19,612.80

M' 6 M Pemasangan Pipa PVC Ø 40 mm (1 1/2") Kode Analisa : Pp.1


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.2160 110,700.00 23,911.20

3. Tukang Pipa OH 0.3600 151,500.00 54,540.00


4. Kepala tukang pipa OH 0.0360 0.00 -

B. BAHAN
1. Lem PVC Kg 0.0067 0.00 -

C. PERALATAN

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 78,451.20


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 78,451.20
HARGA SATUAN DILUAR PPN / METER 13,075.20
M' 6 M Pemasangan Pipa PVC Ø 25 mm (1") Kode Analisa : Pp.1.a
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.0960 110,700.00 10,627.20

3. Tukang Pipa OH 0.1600 151,500.00 24,240.00


4. Kepala tukang pipa OH 0.0160 0.00 -

B. BAHAN
1. Lem PVC Kg 0.0040 0.00 -

C. PERALATAN

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 34,867.20


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 34,867.20
HARGA SATUAN DILUAR PPN / METER 5,811.20

M' 100 M Pengetesan pipa Ø 150 mm (6") Kode Analisa : Tp. 6


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.6000 110,700.00 66,420.00

3. Tukang Pipa OH 0.1998 151,500.00 30,269.70


4. Kepala tukang pipa OH 0.0200 0.00 -
5. Operator Pompa OH 0.2000 80,000.00 16,000.00

B. BAHAN
1. Volume Air Terpakai m3 2.6494 1,200.00 3,179.28

C. PERALATAN
1. Mesin Pengetesan Hari 0.2000 150,000.00 30,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 145,868.98


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 145,868.98
HARGA SATUAN DILUAR PPN / METER 1,458.69
M' 100 M Pengetesan pipa Ø 100 mm (4") Kode Analisa : Tp. 4
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.4000 110,700.00 44,280.00

3. Tukang Pipa OH 0.1332 151,500.00 20,179.80


4. Kepala tukang pipa OH 0.0133 0.00 -
5. Operator Pompa OH 0.1333 80,000.00 10,666.67

B. BAHAN
1. Volume Air Terpakai m3 0.0000 1,200.00 -

C. PERALATAN
1. Mesin Pengetesan Hari 0.1333 150,000.00 20,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 95,126.47


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 95,126.47
HARGA SATUAN DILUAR PPN / METER 951.26

M' 100 M Pengetesan pipa Ø 75 mm (3") Kode Analisa : Tp. 3


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.3000 110,700.00 33,210.00

3. Tukang Pipa OH 0.0999 151,500.00 15,134.85


4. Kepala tukang pipa OH 0.0100 0.00 -
5. Operator Pompa OH 0.1000 80,000.00 8,000.00

B. BAHAN
1. Volume Air Terpakai m3 0.6623 1,200.00 794.76

C. PERALATAN
1. Mesin Pengetesan Hari 0.1000 150,000.00 15,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 72,139.61


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 72,139.61
HARGA SATUAN DILUAR PPN / METER 721.40
M' 100 M Pengetesan pipa Ø 50 mm (2") Kode Analisa : Tp. 2
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.2000 110,700.00 22,140.00

3. Tukang Pipa OH 0.0666 151,500.00 10,089.90


4. Kepala tukang pipa OH 0.0067 0.00 -
5. Operator Pompa OH 0.0670 80,000.00 5,360.00

B. BAHAN
1. Volume Air Terpakai m3 0.2940 1,200.00 352.80

C. PERALATAN
1. Mesin Pengetesan Hari 0.0670 150,000.00 10,050.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 47,992.70


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 47,992.70
HARGA SATUAN DILUAR PPN / METER 479.93

M' 100 M Pengetesan pipa Ø 40 mm (1.5") Kode Analisa : Tp. 1


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.2000 110,700.00 22,140.00

3. Tukang Pipa OH 0.0666 151,500.00 10,089.90


4. Kepala tukang pipa OH 0.007 0.00 -
5. Operator Pompa OH 0.053 80,000.00 4,266.67

B. BAHAN
1. Volume Air Terpakai m3 0.000 1,200.00 -

C. PERALATAN
1. Mesin Pengetesan Hari 0.0533 150,000.00 8,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 44,496.57


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 44,496.57
HARGA SATUAN DILUAR PPN / METER 444.97
M' 100 M Pengurasan/flusing pipa Ø 150 mm (6") Kode Analisa : Fp. 6
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 2.2278 110,700.00 246,617.46

3. Tukang Pipa OH 0.4458 151,500.00 67,538.70


4. Kepala tukang pipa OH 0.0446 0.00 -
5. Operator Pompa OH 0.2000 80,000.00 16,000.00

B. BAHAN
1. Volume Air Terpakai m3 3.5325 1,200.00 4,239.00
2. Kaporit 60 % gram 17.6625 7,000.00 123,637.50

C. PERALATAN
1. Mesin Pompa Hari 0.2000 100,000.00 20,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 478,032.66


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 478,032.66
HARGA SATUAN DILUAR PPN / METER 4,780.33

M' 100 M Pengurasan/flusing pipa Ø 100 mm (4") Kode Analisa : Fp. 4


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 1.4852 110,700.00 164,411.64

3. Tukang Pipa OH 0.2972 151,500.00 45,025.80


4. Kepala tukang pipa OH 0.0297 0.00 -
5. Operator Pompa OH 0.1333 80,000.00 10,666.67

B. BAHAN
1. Volume Air Terpakai m3 0.0000 1,200.00 -
2. Kaporit 60 % gram 0.0000 7,000.00 -

C. PERALATAN
1. Mesin Pompa Hari 0.1333 100,000.00 13,333.33

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 233,437.44


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 233,437.44
HARGA SATUAN DILUAR PPN / METER 2,334.37
M' 100 M Pengurasan/flusing pipa Ø 75 mm (3") Kode Analisa : Fp. 3
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 1.1139 110,700.00 123,308.73

3. Tukang Pipa OH 0.2229 151,500.00 33,769.35


4. Kepala tukang pipa OH 0.0223 0.00 -
5. Operator Pompa OH 0.1000 80,000.00 8,000.00

B. BAHAN
1. Volume Air Terpakai m3 0.8831 1,200.00 1,059.72
2. Kaporit 60 % gram 4.4156 7,000.00 30,909.20

C. PERALATAN
1. Mesin Pompa Hari 0.1000 100,000.00 10,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 207,047.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 207,047.00
HARGA SATUAN DILUAR PPN / METER 2,070.47

M' 100 M Pengurasan/flusing pipa Ø 50 mm (2") Kode Analisa : Fp. 2


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.7426 110,700.00 82,205.82

3. Tukang Pipa OH 0.1486 151,500.00 22,512.90


4. Kepala tukang pipa OH 0.0149 0.00 -
5. Operator Pompa OH 0.0667 80,000.00 5,336.00

B. BAHAN
1. Volume Air Terpakai m3 0.3930 1,200.00 471.60
2. Kaporit 60 % gram 1.9630 7,000.00 13,741.00

C. PERALATAN
1. Mesin Pompa Hari 0.0667 100,000.00 6,670.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 130,937.32


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 130,937.32
HARGA SATUAN DILUAR PPN / METER 1,309.37
M' 100 M Pengurasan/Flushing pipa Ø 40 mm (1.5") Kode Analisa : Fp. 1
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.5941 110,700.00 65,764.66

3. Tukang Pipa OH 0.1189 151,500.00 18,010.32


4. Kepala tukang pipa OH 0.0119 0.00 -
5. Operator Pompa OH 0.0533 80,000.00 4,266.67

B. BAHAN
1. Volume Air Terpakai m3 0.000 1,200.00 -
2. Kaporit 60 % grm 0.000 7,000.00 -

C. PERALATAN
1. Mesin Pompa Hari 0.0533 100,000.00 5,333.33

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 93,374.98


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 93,374.98
HARGA SATUAN DILUAR PPN / METER 933.75

M' 1 M' Crossing Jalan (Boring) Ø 100 mm (4") Kode Analisa : Bp. 4
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 1.5000 110,700.00 166,050.00
2. Tukang Bor OH 0.1500 0.00 -
3. Mandor OH 0.0750 0.00 -

B. BAHAN
1. Pasir Urug m3 0.0090 85,000.00 765.00

C. PERALATAN
1. Alat Bor Hari 0.0375 100,000.00 3,750.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 170,565.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 170,565.00
M' 1 M' Crossing Jalan (Boring) Ø 75 mm (3") Kode Analisa : Bp. 3
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 1.0000 110,700.00 110,700.00
2. Tukang Bor OH 0.1000 0.00 -

B. BAHAN
1. Pasir Urug m3 0.0060 85,000.00 510.00

C. PERALATAN
1. Alat Bor Hari 0.0250 100,000.00 2,500.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 113,710.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 113,710.00

Unit 1 Unit Mobilisasi dan Demobilisasi Peralatan Pengeboran ter Kode Analisa : SB,01
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. PERALATAN PENGEBORAN
Mesin Bor, menara stang Bor, Meliputi :
Mesin Las, Kompresor,
Generator, Pompa Pumping
Test, dan Selang Pemberat
dengan berat peralatan 20
Ton/Unit
a. Biaya Mobilisasi 1 bh Truk 6 s unit truk 1.0000 500,000.00 500,000.00
b. Pekerja Untuk bongkar muat P OH 4.0000 110,700.00 442,800.00
c. Pekerja Untuk bongkar muat P OH 5.0000 110,700.00 553,500.00

B. MOBILISASI MATERIAL
Pipa Chasing, Screen,SUMUR
Pipa Meliputi :
Sonding, Bentonite, Additive
beton dll.
a. Biaya Transportasi dari Kabup unit truk 1.0000 500,000.00 500,000.00
b. Pekerja Untuk bongkar muat OH 3.0000 110,700.00 332,100.00

C. PEKERJAAN PERSIAPAN ERICTION PERALATAN


a. Pembuatan/penyempurnaan j unit 1.0000 400,000.00 400,000.00
b.c.Pembersihan
Pemasangan,lokasi & pengga
Pemindahan unit 1.0000 250,000.00 250,000.00
dan Pembongkaran Mesin Bor
dan Alat Bantu unit 1.0000 2,528,400.00 2,528,400.00
d. Galian Tanah untuk kolam lu m3 8.0000 51,480.00 411,840.00

4,422,340.00
TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 5,918,640.00
OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 5,918,640.00
- Operasional mesin Bor Kode Analisa : SB,02
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Pengeboran diperhitungkan 1 hari = 8 jam
OPERATIONAL MESIN BOR
Merk : Standar Isi Oli Transmisi : 60 Liter
Hp. : 78 PK Isi Oli Hidraulis : 200 Liter
Isi Oli Mesin : 18 Liter Harga Pokok Mesin : Rp. 990.000.000,-
Isi Oli Gardan : 18 Liter Jam Kerja : 2.000 Jam

A. UPAH
1. Penanggung Jawab Pengebor hari 1.000 - -
2. Tukang Bor hari 1.000 - -
3. Mekanik hari 1.000 - -
4. Pekerja hari 1.000 110,700.00 110,700.00

B. BAHAN
1. Bahan Bakar Minyak Liter 38.640 6,000.00 231,840.00
2. Pelumas Mesin Liter 0.140 39,000.00 5,460.00
3. Pelumas Gardan Liter 0.200 44,500.00 8,900.00
4. Pelumas Transmisi Liter 0.080 44,500.00 3,560.00
5. Pelumas Hidraulis Liter 2.560 44,500.00 113,920.00
6. Gemuk Kg 2.000 15,000.00 30,000.00
7. Biaya Perbaikan % 0.0128 - -
8. Penyusutan Mesin dan Perala % 0.080 - -

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 504,380.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 504,380.00

- Operasional Pompa Lumpur Kode Analisa : SB,03


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Pengeboran diperhitungkan 1 hari = 8 jam
OPERATIONAL POMPA LUMPUR
Merk : Standar
Hp. : 40 PK
Isi Oli Mesin : 18 Liter Harga Pokok Mesin : Rp. 330.000.000,-
Isi Oli Gardan : 26 Liter Jam Kerja : 2.000 Jam

A. UPAH
1. Tukang Bor hari 1.000 - -
2. Pekerja hari 1.000 110,700.00 110,700.00

B. BAHAN
1. Bahan Bakar Minyak Liter 35.200 6,000.00 211,200.00
2. Pelumas Mesin Liter 0.070 39,000.00 2,730.00
3. Pelumas Gardan Liter 0.330 44,500.00 14,685.00
4. Gemuk Kg 2.000 15,000.00 30,000.00
5. Biaya Perbaikan % 0.0200 330,000,000.00 66,000.00
6. Penyusutan Mesin dan Perala % 0.010 330,000,000.00 33,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 468,315.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 468,315.00
- Pemakaian bahan MudPit/Kolam Lumpur Kode Analisa : SB,04
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
A. UPAH
1. Pekerja hari 2.000 110,700.00 221,400.00

B. BAHAN
1. Bentonite kg 110.000 15,000.00 1,650,000.00
2. Additive kg 0.070 48,000.00 3,360.00
3. Air untuk Sirkulasi Liter 0.330 150.00 49.50

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 1,874,809.50


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 1,874,809.50

M' 1 m' Lubang Bor diameter 150 mm (6") Kode Analisa SB,05
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
A. UPAH, BAHAN DAN ALAT
Diperkirakan kecepatan
Pengeboran dengan Segala
Formasi rata-rata 8 m'/hari

Biaya Pengeboran / meter m' 0.3333 504,380.00 168,126.67

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 168,126.67


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 168,126.67

M' 1 m' Pelebaran Lubang Bor (reaming) dari dia 150 mm ke 300 mm Kode Analisa SB,06
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
A. UPAH, BAHAN DAN ALAT
Diperkirakan kecepatan
Pengeboran dengan Segala
Formasi rata-rata 12 m'/hari

Biaya Pengeboran / meter m' 0.2222 504,380.00 112,084.44

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 112,084.44


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 112,084.44
M' 1 m' Electrical Loging Kode Analisa SB,07
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Biaya untuk 100 meter Logging

A. UPAH
1. Operator Logging hari 7.000 - -
2. Pembantu Operator Loging hari 7.000 80,000.00 560,000.00
3. Pekerja hari 10.000 110,700.00 1,107,000.00

B. BAHAN
1. Kertas Logging Set 1.000 250,000.00 250,000.00
2. Tinta dan Pen Logging Unit 1.000 75,000.00 75,000.00
3. Batterai dan Kabel Unit 1.000 400,000.00 400,000.00
4. Biaya Penyusutan Alat Unit 1.000 70,000.00 70,000.00
5. Akomodasi Operator Ls 1.000 200,000.00 200,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 2,662,000.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 2,662,000.00
BIAYA PER METER LOGING 26,620.00

M' 1 m' Pemasangan Pipa Chasing dia 150 mm Kode Analisa SB,08
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Biaya untuk 100 meter Logging

A. UPAH
1. Operational Mesin Bor unit/hari 0.500 - -

B. BAHAN
1. Pipa PVC diameter 150 mm m' 1.000 170,000.00 170,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 170,000.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 170,000.00

M' 1 m' Pemasangan Pipa Screen dia 150 mm Kode Analisa SB,09
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Biaya untuk 100 meter Logging

A. UPAH
1. Pemasangan Pipa Screen di unit/hari 0.333 - -

B. BAHAN
1. Pipa Screen diameter 150 mm m' 1.000 170,000.00 170,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 170,000.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 170,000.00
- Pemompaan Uji Bertahap, Menerus dan Uji Kambuh Kode Analisa SB,011
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
BIAYA OPERATIONAL GENERATOR
Merk : Standar
Hp. : 30 PK
Isi Oli Mesin : 20 Liter
Harga Pokok Mesin : Rp. 100.000.000.-

A. UPAH
1. Penanggung Jawab Pengebor hari 1.000 - -
2. Tukang Bor hari 1.000 - -
3. Pekerja hari 3.000 110,700.00 332,100.00

B. BAHAN
1. Bahan Bakar Minyak Liter 26.400 6,000.00 158,400.00
2. Pelumas Mesin Liter 0.100 39,000.00 3,900.00

BIAYA OPERATIONAL POMPA


Merk : Standar
Kapasitas : 10 l/dt Head = 110 m
Jam Kerja : 2.000 jam
Harga Pokok Mesin : Rp. 86.500.000.-
1. Biaya Operational Pompa unit 0.0022 100,000,000.00 220,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 714,400.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 714,400.00
BIAYA PEMOMPAAN UJI BERTAHAP / JAM 71,440.00

M3 1 M³ Kerikil terayak Kode Analisa : SB,012


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
Di perkirakan per m³ kerikil
setelah di ayak dan di bersihkan
menghasilkan 60% kerikil
sesuai ukuran dan seragam
dengan kecepatan pemasangan
A. BIAYA DAN UPAH
1. Operational Mesin Bor hari 0.067 504,380.00 33,625.33
2. Operational Pompa Lumpur hari 0.067 1,874,809.50 124,987.30

B. BAHAN
1. Kerikil m³ 1.670 445,800.00 744,486.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 903,098.63


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 903,098.63
- Water Jetting 1 Lokasi Sumur Kode Analisa SB,014
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. BIAYA
1. Operasional Mesin Bor Unit 0.500 504,380.00 252,190.00
2. Operasional Pompa Lumpur Unit 1.143 1,874,809.50 2,143,094.74

B. BAHAN
1. Air untuk Sirkulasi m³ 12.000 100.00 1,200.00
2. Bahan Kimia STTP kg 40.000 18,500.00 740,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 3,136,484.74


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 3,136,484.74

- Air Jetting 1 Lokasi Kode Analisa : SB,015


BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.
BIAYA OPERASIONAL MESIN BOR
Merk : Standar
Hp. : 100 PK
Isi Oli Mesin : 24 Liter
Isi Oli Hidroulis : 150 Liter
Harga Pokok Mesin : Rp. 200.000.000.-
1. Biaya Operasional Mesin Bor Unit 0.500 504,380.00 252,190.00

A. UPAH
1. Tukang Bor hari 1.000 - -
2. Pekerja hari 1.000 110,700.00 110,700.00

B. BAHAN
1. Bahan Bakar Minyak Liter 35.200 6,000.00 211,200.00
2. Pelumas Mesin Liter 0.070 39,000.00 2,730.00
3. Pelumas Gardan Liter 0.330 44,500.00 14,685.00
4. Biaya Perbaikan % 0.030 200,000,000.00 60,000.00
5. Penyusutan Mesin dan perala % 0.190 200,000,000.00 380,000.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 1,031,505.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 1,031,505.00
- Analisa Kualitas Air Kode Analisa SB,016
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. UPAH
1. Teknisi Pumping Test hari 0.100 - -
2. Analisa Laboratorium Sample 1.000 375,000.00 375,000.00

B. BAHAN
1. Jerigen m³ 1.000 11,250.00 11,250.00

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 386,250.00


OVER HEAD DAN KEUNTUNGAN 10% -
HARGA SATUAN DILUAR PPN 386,250.00

- 1 Unit Pembuatan Box Valve/ Air Valve (Analisa sendiri) Kode Analisa : TP.3
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 2.0000 110,700.00 221,400.00
3. Tukang Pipa OH 1.0000 151,500.00 151,500.00
4. Kepala tukang pipa OH 0.1000 - -

B. BAHAN
1. Pemasangan Accessories ls 1.0000 61,000.00 61,000.00
2. Galian Tanah Campuran m3 0.2700 51,480.00 13,899.60
3. Timbunan Tanah Kembali dipa m3 0.0602 21,395.00 1,288.41

C. PERALATAN
Alat Bantu (0,5 % x (UP+BHN) ls 1.0000 2,245.44 2,245.44

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 451,333.45


OVER HEAD DAN KEUNTUNGA10% -
HARGA SATUAN DILUAR PPN 451,333.45

- 1 Unit Pembuatan Box Valve/ Air Valve (Analisa sendiri) Kode Analisa : TP.3
BIAYA JUMLAH
NO. URAIAN SATUAN KUANTITAS SATUAN HARGA
Rp. Rp.

A. TENAGA KERJA
1. Pekerja OH 0.2000 110,700.00 22,140.00
3. Tukang OH 0.0175 151,500.00 2,651.25
3. Mandor OH 0.0070 - -

B. BAHAN
1. Pemasangan Accessories ls - 61,000.00 -
2. Galian Tanah Campuran m3 - - -
3. Timbunan Tanah Kembali dipa m3 - 9,000.00 -

C. PERALATAN
Truck Crane + perlengkapan ls 0.3500 60,266.98 21,093.44

TOTAL UNTUK BURUH, MATERIAL DAN PERALATAN 45,884.69


OVER HEAD DAN KEUNTUNGA10% -
HARGA SATUAN DILUAR PPN 45,884.69
Kabupaten : Lombok Timur Jenis Prasarana : Sumur Bor
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 80 Meter
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
I PEMBERSIHAN LOKASI
4 Ls a. Pekerja = 4 x 1.00 = 4.00 Ls 110,700 442,800
TOTAL I 442,800
II MOBILISASI DAN DEMOBILISASI

a. Biaya mobilisasi dan demobilisasi 2 Unit Truk a. Transportasi = 2.00 Unit/hari 1,000,000 2,000,000

TOTAL II 2,000,000

III PEKERJAAN PERSIAPAN ERICTION a. Pemasangan, Pemindahan, 1 Ls Upah


PERALATAN Pembongkaran Mesin Bor dan Alat Bantu a. Pekerja = 1 x 5.00 = 5.00 HOK 110,700 553,500

b. Galian tanah kolam lumpur


= P x L x t Upah
= 2 x 2 x 0.5 2 m³ a. Pekerja = 2 x 0.75 = 1.50 HOK 110,700 166,050
= 2 m³

TOTAL III 719,550

IV PENGERJAAN PENGEBORAN

a. Penyediaan air sirkulasi pengeboran


air sirkulasi pengeboran 80 m Bahan
Air = 80 x 30.000 = 2,400 ltr 100 240,000
b. Pengadaan Bentonit untuk Lumpur pengeboran
Bentonit untuk Lumpur pengeboran Bahan
80 m Bentonit = 80 x 0.030 = 2.40 Sak 250,000 600,000

Pengeboran sumur diameter 150 mm (6 inchi) 80 m 1. Bahan


c. Pekerjaan Pengeboran Kedalaman = 80 m a. Bahan bakar minyak = 80 x 12.88 = 1,030.40 Liter 5,150 5,306,560
b. Pelumas mesin = 80 x 0.05 = 3.73 Liter 58,500 218,400
c. Pelumas gardan = 80 x 0.07 = 5.33 Liter 58,500 312,000
d. Pelumas transmisi = 80 x 0.03 = 2.13 Liter 58,500 124,800
e. Oli Hydrolis = 80 x 0.85 = 68.27 Liter 35,875 2,449,067
f. Gemuk = 80 x 0.67 = 53.33 Kg 62,500 3,333,333

2. Upah
a. Mekanik = 80 x 0.33 = 26.67 HOK -
b. Pekerja = 80 x 0.33 = 26.67 HOK 110,700 2,952,000
c. Operator Alat bor = 80 x 0.33 = 26.67 HOK -

Operasional Pompa Lumpur 80 m 1. Bahan


Kedalaman = 80 m a. Bahan bakar minyak = 80 x 11.73 = 938 Liter 5,150 4,832,760
b. Pelumas mesin = 80 x 0.02 = 1.60 Liter 58,500 93,600
c. Pelumas gardan = 80 x 0.11 = 8.80 Liter 58,500 514,800
d. Pelumas transmisi = 80 x = - Liter 58,500 -
e. Oli Hydrolis = 80 x = - Liter 35,875 -
f. Gemuk = 80 x 0.67 = 53.60 Kg 62,500 3,350,000

2. Upah

a. Pekerja = 80 x 0.33 = 26.67 HOK 110,700 2,952,000


b. Operator Alat bor = 80 x 0.33 = 26.67 HOK -
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

Reaming sumur dari dia. 150 mm ke 250 mm 80 m Biaya


c. Kedalaman = 80 m a. Bahan bakar minyak = 80 x 6.44 = 515.20 Liter 5,150 2,653,280
b. Pelumas mesin = 80 x 0.02 = 1.87 Liter 58,500 109,200
c. Pelumas gardan = 80 x 0.03 = 2.67 Liter 58,500 156,000
d. Pelumas transmisi = 80 x 0.01 = 1.07 Liter 58,500 62,400
e. Oli Hydrolis = 80 x 0.43 = 34.13 Liter 35,875 1,224,533
f. Gemuk = 80 x 0.33 = 26.67 Kg 62,500 1,666,667

2. Upah
a. Mekanik = 80 x 0.17 = 13.33 HOK -
b. Pekerja = 80 x 0.17 = 13.33 HOK 110,700 1,476,000
c. Operator Alat bor = 80 x 0.17 = 13.33 HOK -

Electrical Logging (per 100 m Logging) 0.8 m 1. Bahan


= 80 : 100 m a. Kertas Logging = 1 x 1.00 = 0.80 Set 250,000 200,000
= 0.8 m b. Tinta & Pen Logging = 1 x 1.00 = 0.80 Unit 75,000 60,000
c. Baterai dan Kabel = 1 x 1.00 = 0.80 Unit 400,000 320,000

2. Upah
a. Operator Logging = 1 x 7.00 = 5.60 HOK -
b. Pembantu operator = 1 x 7.00 = 5.60 HOK -
c. Pekerja = 1 x 10.00 = 8.00 HOK 110,700 885,600

b. Pekerjaan Perpipaan Pengadaan dan pemasangan cassing pipa PVC (AW) 64 m 1. Bahan
Pipa PVC bertekanan 64 165,000
dia 150 mm (6") a. (AW) Ø 6" = x 1.00 = 64.00 m 10,560,000
b. End cop (Dop PVC) Ø 6" = 1 x 1.00 = 1.00 Buah 156,000 156,000

2. Upah
a. Pekerja = 64 x 0.50 = 32.00 HOK 110,700 3,542,400
b. Operator Alat bor = 64 x 0.50 = 32.00 HOK -

Pengadaan dan pemasangan screen 16 m 1. Bahan


Pipa PVC bertekanan 16 165,000
pipa PVC (AW) dia. 150 mm a. (AW) Ø 6" = x 1.00 = 16.00 m 2,640,000

2. Upah
a. Pekerja = 16 x 0.50 = 8.00 HOK 110,700 885,600
b. Operator Alat bor = 16 x 0.50 = 8.00 HOK -

c. Pekerjaan Sipil Pasangan gravel Kerikil/koral 0.5-1 cm 1.57 m³ 1. Bahan


= D x x T Kerikil/koral 0.5-1 cm = 2 x 1.20 = 1.89 m³ -
= 0.25 x x 50 m
= 2.455 m³ 2 Upah
a. Pekerja = 2 x 0.76 = 1.20 HOK 110,700 132,538
= D x x T b. Operator Alat bor = 2 x 0.19 = 0.30 HOK -
= 0.15 x x 50 m
= 0.884 m³
= 1.57

Grouting Beton Cor 1 pc : 2 ps : 3 krkl 0.94 m³ 1. Bahan


= p + l = V a. Semen = 1 x 5.52 = 5.17 Zak 60,000 310,169
= 0.5 + 0.4 = 0.94 b. Batu Pecah 1-2 cm = 1 x 0.83 = 0.78 m³ 445,800 345,683
c. Pasir Cor = 1 x 1.01 = 0.95 m³ 214,800 203,574

2. Upah
a. Pekerja = 1 x 1.65 = 1.55 HOK 110,700 171,056
b. Tukang = 1 x 0.28 = 0.26 HOK 151,500 39,017
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

e. Pekerjaan Penyelesaian Pembersihan dengan air jetting 1 Titik a Air jetting test = 1 x 1.00 = 1.00 Titik 3,136,485 3,136,485

Pembersihan dengan water jetting Titik b Water jetting = - x 1.00 = - Titik 1,031,505 -

Pemompaan Uji sumur/Pumping Test 72 Jam 1. Bahan


24 Jam Uji Pendahuluan (Pre-Test) a. Bahan bakar minyak = 72 x 13.20 = 950.40 Liter 5,150 4,894,560
18 Jam Uji Susut Bertahap (Step Drowdown Test) b. Pelumas mesin = 72 x 0.05 = 3.60 Liter 58,500 210,600
18 Jam Uji Debet Tetap (Continuos Test)
12 Jam Uji Pemulihan (Recovery Test) 2. Upah
72 a. Pekerja = 6 x 3.00 = 18.00 HOK 110,700 1,992,600
Tukang = 6 x 1.00 = 6.00 HOK 151,500 909,000

TOTAL IV 66,222,282

V PEMBUATAN BAK SUMUR BOR Volume Galian

Upah
Pasangan Buis Dia. 80 cm 0.5 Pekerja = 0.5 X 0.14 = 0.07 OH 110,700 7,749
Tukang = 0.5 X 0.07 = 0.04 OH 151,500 5,303
Bahan -
Buis Beton Ø 80 Cm panja = 0.5 X 2 = 1.00 Buah 250,000 250,000
Bata Merah = 0.5 X 0 = - Buah 1,500 -
Semen = 0.5 X 0.0784 = 0.04 Zak 60,000 2,352
Pasir Pasangan = 0.5 X 0.056 = 0.03 M3 207,500 5,810
Pasir urug = 0.5 X 0.024 = 0.01 M3 188,900 2,267

Penutup buis beton Dia. 80 cm 1 Bahan


a. Tutup buis Ø 80 cm = 1.00 X 1.00 = 1.00 Buah 250,000 250,000

TOTAL V 523,480
VI ALAT PELINDUNG DIRI
1 Masker Kain 12.0 Bh Masker Kain 12.00 Bh 10,000 120,000
2 Sabun Cuci Tangan Cair 1.0 Btl Sabun Cuci Tangan Cair 1.00 Btl 50,000 50,000
3 Ember dan Keran 1.0 Bh Ember dan Keran 1.00 Bh 85,000 85,000
TOTAL VI 255,000
GRAND TOTAL 70,163,112
DIBULATKAN 70,163,000
RENCANA ANGGARAN BIAYA

Nomor RAB : 0.1 Sub Pekerjaan/Kegiatan : Sumur Bor


Pekerjaan / Kegiat : Sarana Air Minum Ukuran/Dimensi : 80 Meter

Volume Biaya (Rp)


Harga Satuan
URAIAN Kontribusi Masy. Satuan Kontribusi Masyarakat
Total APBDes BLM Total APBDes BLM
inCash inKind Rp inCash inKind
1 2=3+4+5 3 4 5 6 7 8 9=2x8 10=3x8 11=4x8 12=5x8 13=6x8
I BAHAN
1 Bahan bakar minyak - - - - - liter 5,150 - - - - -
2 Pelumas mesin - - - - - Liter 58,500 - - - - -
3 Pelumas gardan - - - - - Liter 58,500 - - - - -
4 Pelumas transmisi - - - - - Liter 58,500 - - - - -
5 Air - - liter 100 - -
6 Bentonit - - Zak 250,000 - -
7 Oli Hydrolis - - - - - Liter 35,875 - - - - -
8 Gemuk - - Liter 62,500 - -
9 Kertas Logging - - Set 250,000 - -
10 Tinta & Pen Logging - - Unit 75,000 - -
11 Baterai dan Kabel - - Unit 400,000 - -
12 Pipa PVC bertekanan (AW) Ø 6" - - Meter 165,000 - -
13 End cop (Dop PVC) Ø 6" - - Buah 156,000 - -
14 Kerikil/koral 0.5-1 cm - - - - - M3 - - - - - -
15 Semen - - - - - Zak 60,000 - - - - -
16 Batu Pecah 1-2 cm - - M3 445,800 - -
17 Pasir Cor - - M3 214,800 - -
18 Bata merah - - - - - Buah 1,500 - - - - -
19 Pasir pasangan - - - - - M3 207,500 - - - - -
20 Air jetting test - - - - - Titik 3,136,485 - - - - -
21 Water jetting - - Titik 1,031,505 - -
22 Buis Beton Ø 80 Cm panjang 0,50 m - - Bh 250,000 - -
23 Tutup buis Ø 80 cm - - Bh 250,000 - -

II ALAT
Transportasi - - - - - Unit Truk 1,000,000.00 - - - - -

III UPAH
Pekerja - - OH 110,700.00 - - - - -
Tukang - - OH 151,500.00 - - - - -
Mekanik - - OH - - - - - -
Operator Logging - - OH - - - - - -
Pembantu operator - - OH - - - - - -
Operator Alat bor - - OH - - - - - -
Teknisi Pumping test - - - - - OH - - - - - -

IV ALAT PELINDUNG DIRI


Masker Kain - - - - - Bh 10,000.00 - - - - -
Sabun Cuci Tangan Cair - - - - - Btl 50,000.00 - - - - -
Ember dan Keran - - - - - Bh 85,000.00 - - - - -

JUMLAH TOTAL - - - - -
DIBULATKAN - - - - -
Kabupaten : …..... Jenis Prasarana : Panel, Pompa dan Aksesoris
Kecamatan : …………. Take Of Sheet Lokasi : …………..
Desa : ………….. Volume : 1.00 Unit
Sketsa Kasar Perhitungan Volume Vol. Sat. Analisa Kebutuhan Sat. harga satuan Biaya
I PEKERJAAN INSTALASI LISTRIK
a. Pemasangan Baru 1 UPAH
a. Instalasi dan Setting Pump = 1.00 X 1.00 = 1.00 Ls 8,362,500.00 8,362,500.00
2 BAHAN
a. Panel Kontrol Solar Inverter = 1.00 X 1.00 = 1.00 Unit 16,725,000.00 16,725,000.00
b. Solar Panel = 8.00 X 1.00 = 8.00 Lbr 2,230,000.00 17,840,000.00
c. Suport Panel dan Aksesoris = 1.00 X 1.00 = 1.00 Set 11,150,000.00 11,150,000.00
d. Kabel Power = 0.25 X 1.00 = 0.25 Roll 5,017,500.00 1,254,375.00
e. Kabel WLC = 0.50 X 1.00 = 0.50 Roll 2,787,500.00 1,393,750.00
f. Pompa Celup DC 12V = 1.00 X 1.00 = 1.00 Unit 1,000,000.00 1,000,000.00

57,725,625.00

GRAND TOTAL 57,725,625.00


RENCANA ANGGARAN BIAYA

Nomor RAB : 03
Pekerjaan / Kegiatan : Sarana Air Minum

Volume Biaya (Rp)


Harga Satuan
URAIAN Satuan
Total Total
Rp
1 2 3 4 5
A BAHAN
1 Panel Kontrol Solar Inverter 1.00 Ls 16,725,000 16,725,000
2 Solar Panel 8.00 Bh 2,230,000 17,840,000
3 Suport Panel dan Aksesoris 1.00 Ls 11,150,000 11,150,000
4 Kabel Power 0.25 Ls 5,017,500 1,254,375
5 Kabel WLC 0.50 Ls 2,787,500 1,393,750
6 Pompa Celup DC 12V 1.00 Ls 1,000,000 1,000,000

Sub Total A 49,363,125

Sub Total 2) -
B UPAH
1 Instalasi dan Setting Pump 1.00 Ls 8,362,500 8,362,500

Sub Total B 8,362,500


JUMLAH TOTAL 57,725,625
DIBULATKAN 57,725,000
Pekerjaan : SARANA AIR MINUM

Perhitungan
Persegi Panjang Trapesium Lingkaran Vol.
Jml
No. Uraian Pekerjaan Lb Pj Tg S. Bwh S. Ats Tg Pj Ø1 Ø2 Tg
Sat
m m m m m m m m m Bh
V=LbxPjxTg V=((1/2(S.Bwh+S.Atas))xTg)xPj
2.1 PEK. SUMUR BOR 1 (UNIT)
1 Toren 10000L 1 1.00 Unit

2.2 PEK. TOWER AIR


1 Pek. Pembersihan Lokasi 5 5.00 25.00 m2
2 Galian Tanah Pondasi
1.6 1.60 1.6 4 16.38
Total Galian Tanah 16.38 m3
3 Urugan tanah kembali
1/3 Galian tanah 5.46 m3
4 Urugan tanah peniggian 5 5.00 0.15 3.75 m3
5 Urugan pasir dibawah lantai
Pondasi 1.6 1.60 0.05 0.13
Lantai 5 5.00 0.05 1.25
Total urugan pasir 1.38 m3
6 Pek. Pondasi rolag
Teras 20.00 0.4 8.00
Total Pondasi rolag 8.00 m2
7 Pasangan dinding bata 12.00 2.5 30.00 m2
Total Pasangan bata 30.00 m2
8 Pek. Kusen Pintu Kayu Kls. II 0.06 5.10 0.12 1 0.04 m3
9 Pek. Daun Pintu Panil 0.8 2 1 1.60 m2
10 Pekerjaan Beton Lantai Kerja K-100 1.6 1.60 0.2 4 1.28 m2
11 Pekerjaan Beton K-175
Footplat (100x100) cm 1.4 1.40 0.25 4 1.96 m3
Beton sloof 20/30 cm 0.2 12.00 0.3 0.72 m3
Beton Kolom 30x30 cm 0.3 0.30 14.6 1.314 m3
Beton Kolom 15x15 cm 0.15 0.15 8 0.18 m3
Beton Balok 15/20 cm 0 - 0 2 0 m3
Beton Balok 20/40 cm 0.2 12.00 0.4 0.96 m3
Beton Balok silang 20/30 cm 0.2 7.00 0.3 0.42 m3
Beton Plat Lantai 12 cm 3.5 3.50 0.12 1 1.47 m3
Beton Plat Penutup Gudang t 8 cm 0 - 0 1 0 m3
Beton Plat Dinding 15 cm - m3
Beton Plat Penutup t = 8 cm - m3
Total Beton K-175 7.02 m3
12 Pekerjaan Pembesian
Footplat (140x140) cm
Besi Pokok D.12 mm X,Y 1.40 1.4 Jrk X 0.15 Jrk Y 0.15 Dim 12 2 253.87 225.48 Kg
Beton sloof 20/30 cm
Besi Pokok D.12 mm Pj tul 12.00 Jml Tul 6 Dim 12 72 63.95 Kg
Besi Gelang D.8 mm Pj. Bgl 1.40 Jml bgl 82 Jrk 0.15 Dim 6 114.8 25.49 Kg
Beton Kolom 30x30 cm
Besi Pokok D.12 mm Pj tul 14.60 Jml Tul 8 Dim 12 116.8 103.74 Kg
Besi Gelang D.8 mm Pj. Bgl 1.40 Jml bgl 99.3333 Jrk 0.15 Dim 6 139.07 30.88 Kg
Beton Kolom 15x15 cm
Besi Pokok D.10 mm Pj tul 8.00 Jml Tul 4 Dim 10 32 19.74 Kg
Besi Gelang D.8 mm Pj. Bgl 0.90 Jml bgl 4.66667 Jrk 0.15 Dim 6 4.2 0.93 Kg
Beton Balok 15/20 cm
Besi Pokok D.12 mm Pj tul - Jml Tul 6 Dim 12 0 - Kg
Besi Gelang D.8 mm Pj. Bgl - Jml bgl 2 Jrk 0.15 Dim 6 0 - Kg
Beton Balok 20/40 cm
Besi Pokok D.12 mm Pj tul 12.00 Jml Tul 8 Dim 12 96 85.26 Kg
Besi Gelang D.8 mm Pj. Bgl 1.30 Jml bgl 2 Jrk 0.15 Dim 6 2.6 0.58 Kg
Beton Balok silang 20/30 cm
Besi Pokok D.12 mm Pj tul 7.00 Jml Tul 6 Dim 12 42 37.30 Kg
Besi Gelang D.8 mm Pj. Bgl 1.30 Jml bgl 2 Jrk 0.15 Dim 6 2.6 0.58 Kg
Beton Plat Lantai 12 cm
Besi Pokok D.10 mm X,Y 3.50 3.5 Jrk X 0.1 Jrk Y 0.1 Dim 10 1 259 159.75 Kg
Beton Plat Penutup Gudang t 8 cm
Besi Pokok D.10 mm X,Y - 0 Jrk X 0.1 Jrk Y 0.1 Dim 10 1 0 - Kg
Beton Plat Dinding t =15 cm
Besi Pokok D.10 mm X,Y Jrk X 0.15 Jrk Y 0.15 Dim 10 2 0 - Kg
Besi Pokok D.10 mm X,Y Jrk X 0.15 Jrk Y 0.15 Dim 8 2 0 - Kg
Beton Plat Dak t = 8 cm
Besi Pokok D.10 mm X,Y - 0 Jrk X 0.15 Jrk Y 0.15 Dim 10 1 0 - Kg
Total Pembesian 753.67 Kg
Kabupaten : Jenis Prasarana : TOWER AIR
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 3X3 Meter
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
P x L x T = JMLH
I PEMBERSIHAN LOKASI

Pembersihan Lokasi 1.00 Ls a. Pekerja = 1 x 1 = 1.00 Ls 110,700 110,700

TOTAL I 110,700
II PEKERJAAN TANAH dan PASIR

a. Galian Tanah pondasi 15.36 m3 Pekerja 0.75 x 15.36 = 11.52 OH 110,700 1,275,264
= 1.6 x 1.60 x 1.5 = 4
= 15.36 m3

b. Timbunan Kembali Tanah Galian x 1/3 galian 5.12 m3 Pekerja 0.25 x 5.12 = 1.28 OH 110,700 141,696

c. Urugan Tanah Peniggian Lantai - m3 Tanah Urug 1.2 x 0 = - M3 67,300 -


= 0x - x 0 = 1 Pekerja 0.3 x 0 = - OH 110,700 -
= 0 m3

d. Urugan pasir dibawah lantai dan pondasi 0.93 m3 Pasir urug 1.2 x 0.932 = 1.12 M3 188,900 211,266
- Pondasi Pekerja 0.3 x 0.932 = 0.28 OH 110,700 30,952
= 1.6 x 2 x 0.05 = 4
= 0.512 m3
- Lantai
= 0x 0 x 0.05 = 1
= 0 m3
- Pondasi batu kali
= 0.7 x 12 x 0.05 = 1
= 0.42 m3
TOTAL II 1,659,177

III PEKERJAAN PASANGAN


a. Pek. Pondasi batu 1 : 4 3.60 m3 Batu Kali Alam 1.2 x 3.6 = 4.32 M3 210,700 910,224
- Teras Semen 2.72 x 3.6 = 9.79 Zak 60,000 587,520
L atas L bawah Tinggi Kelilling Pasir pasangan 0.544 x 3.6 = 1.96 M3 207,500 406,368
= 0.4 + 0.6 x 0.6 x 12
= 3.6 m3 Pekerja 1.5 x 3.6 = 5.40 OH 110,700 597,780
Tukang 0.75 x 3.6 = 2.70 OH 151,500 409,050

b. Pasangan 1/2 Bata 1pc:4ps 23.32 m2 Bata merah 70 x 23.32 = 1,632.40 buah 1,500 2,448,600
= 2.5 x 1 x 2.5 = 4 Semen 0.194 x 23.32 = 4.51 Zak 60,000 270,885
= 25 m2 Pasir pasangan 0.045 x 23.32 = 1.05 M3 207,500 217,750
Lubang kusen
= 0.8 x 2.10 = 1.68 Pekerja 0.3 x 23.32 = 7.00 OH 110,700 774,457
Tukang 0.1 x 23.32 = 2.33 OH 151,500 353,298

TOTAL III 6,975,933

IV PEKERJAAN BETON BERTULANG


1 Pekerjaan Beton Lantai Kerja K-100 2.05 m3 Semen 4.94 x 2.048 = 10.12 Zak 60,000 607,027
= 1.6 x 1.6 x 0.2 = 4.0 Pasir Cor 0.621 x 2.048 = 1.27 M3 214,800 273,059
= 2.0 m2 Kerikil Pecah 3-5 cm 0.74 x 2.048 = 1.52 M3 428,300 649,097
Air 215 x 2.048 = 440.32 Ltr 100 44,032
Pekerja 1.65 x 2.048 = 3.38 OH 110,700 374,077
Tukang 0.275 x 2.048 = 0.56 OH 151,500 85,325

-
2 Pekerjaan Beton Bertulang K-175 7.02 m3 Semen 6.52 x 7.024 = 45.80 Zak 60,000 2,747,789
Footplat (100x100) cm Pasir Cor 0.543 x 7.024 = 3.81 M3 214,800 819,039
= 1.4 x 1.4 x 0.25 = 4 Batu Pecah 2-3 cm 0.762 x 7.024 = 5.35 M3 400,000 2,141,540
= 1.96 M3 Air 215 x 7.024 = 1,510.16 Ltr 100 151,016
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
Beton sloof 20/30 cm Pekerja 1.65 x 7.024 = 11.59 OH 110,700 1,282,969
= 12 x 0.2 x 0.3 = 1 Tukang 0.275 x 7.024 = 1.93 OH 151,500 292,637
= 0.72 M3
Beton Kolom 30x30 cm
= 0.30 x 0.30 x 14.60 = 1
= 1.31 M3
Beton Kolom 15x15 cm
= 0.15 x 0.15 x 2 = 4
= 0.18 M3
Beton Balok 15/20 cm
= 0 x 0 x 0 = 1
= 0 M3
Beton Balok 20/40 cm
= 0.2 x 12 x 0.4 = 1
= 0.96 M3
Beton Balok Silang 20/30 cm
= 0.2 x 7 x 0.3 = 1
= 0.42 M3
Beton Plat Lantai 12 cm
= 3.5 x 3.5 x 0.12 = 1
= 1.47 M3
Beton Plat Penutup Gudang t 8 cm
= 0 x 0 x 0 = 1
= 0 M3
Beton Plat Dinding 10 cm
= 0 x 0 x 0 = 1
= 0 M3
Beton Plat Penutup t = 8 cm
= 0 x 0 x 0 = 1
= 0 M3

2 Pekerjaaan Pembesian 753.67

Footplat (140x140) cm Besi Beton Polos 1.05 x 753.673 = 791.36 kg 20,050 15,866,694
= 225.48 kg Kawat Ikat Beton 0.015 x 753.673 = 11.31 kg 35,000 395,678

Beton sloof 20/30 cm Pekerja 0.007 x 753.673 = 5.28 OH 110,700 584,021


= 89.44 kg Tukang 0.007 x 753.673 = 5.28 OH 151,500 799,270

Beton Kolom 30x30 cm


= 134.62 kg

Beton Kolom 15x15 cm


= 20.67 kg

Beton Balok 15/20 cm


= - kg

Beton Balok 20/40 cm


= 85.84 kg

Beton Balok silang 20/30 cm


= 37.88 kg
Beton Plat Lantai 12 cm
= 159.75 kg
Beton Plat Penutup Gudang t 8 cm
= - kg
Beton Plat Dinding 10 cm
= - kg

Beton Plat Dak t = 8 cm


= - kg

TOTAL IV 27,113,269
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

V PENGERJAAN BEGISTING M2 Sloof


Papan Kayu Begisting 0.045 x 0.30 = 0.01 M3 5,501,200 74,266
Begisting pondasi Pekerjaan Bekisting pondasi - M2 Paku 0.3 x 0.30 = 0.09 kg 20,000 1,800
= 0 x 0 x 0.4 = 4 Pekerja 0.52 x 0.30 = 0.16 OH 110,700 17,269
= 0 M2 Tukang 0.26 x 0.30 = 0.08 OH 151,500 11,817

Begisting Beton sloof 20/30 cm Pekerjaan Bekisting Sloof 0.30 m2


= 0.2 x 0.3 x 12 =
= 6 M2
= 0.3 m3
Kolom/Balok
Papan Kayu Begisting 0.04 x 3.95 = 0.16 M3 5,501,200 869,190
Begisting Beton Kolom 30x30 cm Pekerjaan Bekisting Kolom 1.92 m2 Paku 0.4 x 3.95 = 1.58 kg 20,000 31,600
= 0.3 x 0.3 x 4 = 8 Minyak bekisting 0 x 3.95 = - Ltr 15,000 -
= 38.4 M2 Balok Kayu Kelas III 0.015 x 3.95 = 0.06 M3 5,501,200 325,946
= 1.92 m3 Triplek 122x244x9 mm 0.35 x 79.00 = 27.65 lembar 120,000 3,318,000
Bambu 2 x 3.95 = 7.90 btg 40,000 316,000
Begisting Beton Kolom 15x15 cm Pekerjaan Bekisting Kolom 0.96 m2
= 0.15 x 0.15 x 8 = 4 Pekerja 0.66 x 3.95 = 2.61 OH 110,700 288,595
= 19.2 M2 Tukang 0.33 x 3.95 = 1.30 OH 151,500 197,480
= 0.96 m3

Begisting Beton Balok 15x20 cm Pekerjaan Bekisting Balok 0 m2


= 0 x 0 x 0 = 1
= 0 M2
= 0 m3

Begisting Beton Balok 20x40 cm Pekerjaan Bekisting Balok 0.72 m2


= 0.2 x 0.4 x 12 = 1
= 14.4 M2
= 0.72 m3

Begisting Beton Silang 20/30 cm Pekerjaan Bekisting Balok 0.35 m2


= 0.2 x 0.3 x 7 = 1
= 7 M2
= 0.35 m3
Plat
Begisting Beton Plat Lantai 12 cm Pekerjaan Bekisting Plat 1.47 M2 Papan Kayu Begisting 0.04 x 1.47 = 0.06 M3 5,501,200 323,471
= 3.5 x 3.5 x 0.12 = 1 Paku 0.4 x 1.47 = 0.59 kg 20,000 11,760
= 12.25 M2 Minyak bekisting 0 x 1.47 = - Ltr 15,000 -
= 1.47 m3 Balok Kayu Kelas III 0.015 x 1.47 = 0.02 M3 5,501,200 121,301
Bekisting Beton Plat Penutup t = 8 cm Triplek 122x244x9 mm 0.35 x 12.25 = 4.29 lembar 120,000 514,500
= 0 x 0 x 0 = 1 Bambu 2 x 1.47 = 2.94 btg 40,000 117,600
= 0 M2 -
= 0 m3 Pekerja 0.66 x 1.47 = 0.97 OH 110,700 107,401
Tukang 0.33 x 1.47 = 0.49 OH 151,500 73,493
-
Begisting Beton Plat Dinding 12 cm Pekerjaan Bekisting Dinding - M2
= 0 x 2 x 0.15 = 2
= 0 M2
= 0 m3

TOTAL V 6,721,489
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
VI PEKERJAAN PLESTERAN
Plesteran dinding 1pc:4ps 48.00 m2 Semen 0.156 x 48 = 7.46 Zak 60,000 447,898
dinding gudang kontrol Pasir pasangan 0.023 x 48 = 1.10 M3 207,500 229,080
= 0 + 0 x 2.5 = 2
= 0 m2 Pekerja 0.3 x 48 = 14.40 OH 110,700 1,594,080
dinding tower Beton Tukang 0.15 x 48 = 7.20 OH 151,500 1,090,800
= 3 + 3 x 2 = 2
= 48 m2

Plesteran lantai 1pc:3ps 9.00 m2 Semen 0.156 x 9.00 = 1.40 Zak 60,000 83,981
gudang kontrol Pasir pasangan 0.023 x 9.00 = 0.21 M3 207,500 42,953
= 0 x 3 x 1 = 1
= 0 m2 Pekerja 0.3 x 9.00 = 2.70 OH 110,700 298,890
lantai tower Tukang 0.15 x 9.00 = 1.35 OH 151,500 204,525
= 3 x 3 x 1 = 1
= 9 m2

Acian + Mill 24.00 m2 Semen 0.065 x 24 = 1.56 Zak 60,000 93,600


dinding gudang kontrol
= 0 + 0 x 2.5 = 2 Pekerja 0.2 x 24 = 4.80 OH 110,700 531,360
= 0 m2 Tukang 0.1 x 24 = 2.40 OH 151,500 363,600
dinding tower Beton
= 3 + 3 x 2 = 1
= 24 m2
TOTAL IV 4,980,766

VII PEKERJAAN KAYU dan KUNCI


a. Pek. Kusen Pintu Kayu Kls. II - m3 Balok Kayu Klas II 1.2 x 0 = - M3 4,312,400 -
= 0 x 0.14 x 0.06 = 1 Paku 1.25 x 0 = - kg 20,000 -
= 0 m3 Lem kayu 1 x 0 = - kg 41,000 -

Pekerja 6 x 0 = - OH 110,700 -
Tukang 18 x 0 = - OH 151,500 -

b. Pek. Daun Pintu Panil - m2 Papan Kayu Klas II 0.04 x 0 = - M3 4,312,400 -


= 0 x 0.9 x 2.1 = 1 Lem kayu 0.5 x 0 = - kg 41,000 -
= 0 m2 Pekerja 1 x 0 = - OH 110,700 -
Tukang 3 x 0 = - OH 151,500 -

c. Kunci Pintu - bh Kunci Pintu 1 x - = - M3 120,000 -

d. Engsel pintu - bh Engsel pintu 1 x - = - M3 92,000 -

TOTAL IV -

VIII PEKERJAAN PIPA DAN ASESIORIS


Pipa GI Ø 1.5" (inlet/masuk) m PIPA Galpanis (GI Medium A) Ø 1,5" = - m 135,000 -
Pekerja 0.11 x - = - M3 110,700 -
= 6 + 0 x 0 = 0 Tukang 0.18 x - = - M3 151,500 -
= 6 m

Pipa GI Ø 2" (Outlet dan Penguras) m PIPA Galpanis (GI Medium A) Ø 2" = - m 150,000 -
= 6 + 0 x 0 = 0 Pekerja 0.11 x - = - M3 110,700 -
= 6 m2 Tukang 0.18 x - = - M3 151,500 -
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
Pipa GI Ø 3" (outlet/keluar dan pengiras) - m PIPA Galpanis (GI Medium A) Ø 3" = - m 265,700 -
= 6 + 0 x 0 = 0 Pekerja 0.14 x - = - OH 110,700 -
= m2 Tukang 0.23 x - = - OH 151,500 -

Knee GI dia. 1.5" = 2 Bh Knee GI Ø 11/2 = - Bh 35,000 -


Knee GI dia. 3" = Bh Knee GI Ø 3" = - Bh 130,000 -
Knee GI dia. 2" = 2 Bh Knee GI Ø 2" = - Bh 55,000 -
Sock drat dalam Pipa GI dia. 1.5' = 1 Bh Shock Drat luar PVC Ø1.5" = - Bh 25,000 -
Sock drat luar Pipa GI dia. 3' = Bh Shock Drat luar GI Ø3" = - Bh 96,000 -
Sock drat luar Pipa GI dia. 2' = 1 Bh Shock Drat luar GI Ø2" = - Bh 56,000 -

Tangga Besi (GI dia. 1.5" dan GI dia. 1")


Tangga PIPA GI Medium B Ø 1,5" - m PIPA GI Medium B Ø 1,5" 1 x 0 = - m 77,483 -
= 0 + + 0.3 = 1 m PIPA GI Medium B Ø 1" 1 x 0 = - m 49,150 -
= 0 m
Pekerja 0.108 x 0 = - OH 110,700 -
Tangga PIPA GI Medium B Ø 1" - m Tukang 0.18 x 0 = - OH 151,500 -
= + 0 + 0.4 = 1
= 0 m

Gate Valve 3" Bh Gate Valve 3" - Bh 1,300,000 -


Gate Valve 2" Bh Gate Valve 2" - Bh 750,000 -
Gate Valve 1,5" - Bh Gate Valve 1,5" - Bh 550,000 -
Flank Socket PVC 3" Bh Flank Socket PVC 3" - Bh 100,000 -
Flank last 3" Bh Flank last 3" - Bh 100,000 -
Karet pak 3" Bh Karet pak 3" - Bh 25,000 -
Flank Socket PVC 2" Bh Flank Socket PVC 2" - Bh 60,000 -
Flank last 2" Bh Flank last 2" - Bh 80,000 -
Karet pak 2" Bh Karet pak 2" - Bh 20,000 -
Flank Socket PVC 1,5" Bh Flank Socket PVC 1,5" - Bh 50,000 -
Flank last 1,5" Bh Flank last 1,5" - Bh 60,000 -
Karet pak 1,5" Bh Karet pak 1,5" - Bh 15,000 -
-
Menhol 70 x 70 cm = Bh Manhole plat besi 70X70 cm = - bh 500,000 -

TOTAL II -
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

IX PENGERJAAN PENGECATAN Cat tembok 41.04 M2 Plamir Tembok 0.1 x 41.04 = 4.10 kg 47,000 192,888
Dinding ruangan Cat tembok 0.36 x 41.04 = 14.77 Kg 41,000 605,750
= 0 x x 0 = 8 Ampelas 0 x 41.04 = - m' 30,000 -
= 0 M2 Kape 0 x 41.04 = - Buah - -
Beton Kolom 30x30 cm Kuas 3" 0 x 41.04 = - Buah 18,000 -
= 0.3 x 0.3 x 4 = 4
= 19.2 M2 Pekerja 0.02 x 41.04 = 0.82 OH 110,700 90,863
Beton Balok 15/20 cm Tukang 0.063 x 41.04 = 2.59 OH 151,500 391,706
= 0.15 x 0.2 x 3 = 4
= 6.6 M2
Beton Balok 20/40 cm
= 0.4 0.4 x 3 = 4
= 14.4 M2
Beton Plat Lantai 12 cm
= 3.5 x 3.5 x 0.12 = 2
= 0.84 M2
Beton Plat Dinding 15 cm
= x x =
= M2
Beton Plat Penutup t = 8 cm
= 0 x 0 x 1 = 1
= 0 M2

Cat kayu - Meni Kayu 0.20 x - = - ltr 56,000 -


Pek. Kusen Pintu Kayu Kls. II Plamir kayu 0.15 x - = - ltr 40,000 -
= 0 x 0.14 + 0.06 = 0 Cat Kayu Mutu Sedang 0.17 x - = - ltr 62,000 -
= 0 m3 Kuas 1" - x - = - Bh 15,000 -
Minyak Cat biasa 0.03 x - = - ltr 40,000 -
Ampelas - x - = - Bh 30,000 -
Pekerja 0.07 x - = - OH 110,700 -
Tukang 0.01 x - = - OH 151,500 -
Pek. Daun Pintu Panil
= 0 x 0.9 = 1
= 0 m2

TOTAL IV 1,281,207
V BAK
Toren 5000 L 1.00 Bh Toren 5000 L 1.00 Bh 7,800,000 7,800,000
Toren 2500 L 1.00 Bh Toren 2500 L 1.00 Bh 5,000,000 5,000,000
-

TOTAL V 12,800,000
a. Pek. Pondasi batu 1 : 4 4.00 m3 Batu Kali Alam 1.2 x 3.6 = 4.32 M3 210,700 910,224
- penyangga toren di kampung Semen 2.72 x 3.6 = 9.79 Zak 60,000 587,520
L atas L bawah Tinggi Kelilling Pasir pasangan 0.544 x 3.6 = 1.96 M3 207,500 406,368
= 2+ 2 x 1 x 2
= 4 m3 Pekerja 1.5 x 3.6 = 5.40 OH 110,700 597,780
Tukang 0.75 x 3.6 = 2.70 OH 151,500 409,050

GRAND TOTAL 61,642,542


DIBULATKAN 61,642,000
RENCANA ANGGARAN BIAYA

Nomor RAB : 0.2


Pekerjaan / Kegiatan : Sarana Air Minum

Volume Biaya (Rp)


Harga Satuan
URAIAN Satuan
Total Total
Rp
1 2=3+4+5 7 8 9=2x8
1 BAHAN
- Pasir urug 1.12 m3 188,900.00 211,266
- Batu Kali Alam 4.32 m3 210,700.00 910,224
- Pasir pasangan 4.32 m3 207,500.00 896,151
- Pasir Cor 5.08 m3 214,800.00 1,092,097
- Bata merah 1,632.40 Bh 1,500.00 2,448,600
- Kerikil Pecah 3-5 cm 1.52 m3 428,300.00 649,097
- Batu Pecah 2-3 cm 5.35 m3 400,000.00 2,141,540
- Papan Kayu Begisting 0.23 m3 5,501,200.00 1,266,926
- Balok Kayu Kelas III 0.08 m3 5,501,200.00 447,248
- Bambu 10.84 Bh 40,000.00 433,600
- Paku 2.26 kg 20,000.00 45,160
- Semen 80.64 zak 60,000.00 4,838,700
- Besi Beton Polos 791.36 kg 20,050.00 15,866,694
- Kawat Ikat Beton 11.31 kg 35,000.00 395,678
- Triplek 122x244x9 mm 31.94 Lbr 120,000.00 3,832,500
- Air 1,950.48 ltr 100.00 195,048
- Plamir Tembok 4.10 kg 47,000.00 192,888
- Cat Tembok Mutu Standar/Sedang 14.77 Kg 41,000.00 605,750

Sub Total 1) 36,469,167


Volume Biaya (Rp)
Harga Satuan
URAIAN Satuan
Total Total
Rp
1 2=3+4+5 7 8 9=2x8
2 UPAH
- Pekerja 36.59 OH 110,700 4,050,187
- Tukang 14.10 OH 151,500 2,136,501

Sub Total 2) 6,186,688


3 Tandon Air
- Toren 5000 L 1.00 Bh 7,800,000.00 7,800,000
- Toren 2500 L 1.00 Bh 5,000,000.00 5,000,000
- - - - - -

Sub Total 3) 12,800,000


JUMLAH TOTAL 55,455,854
JUMLAH TOTAL DIBULATKAN 55,455,000
Kabupaten : Lombok Timur Jenis Prasarana : Pompa & Aksesories
Kecamatan : …………. Take Of Sheet Lokasi : …………..
Desa : ………….. Volume : 1.00 Unit
Sketsa Kasar Perhitungan Volume Vol. Sat. Analisa Kebutuhan Sat. harga satuan Biaya
Pemasangan 1 Unit Pompa Submersible
a. 1 UPAH
dan Aksesories
a. Pemasangan Instalasi Pompa = 1.00 X 1.00 = 1.00 Ls 2,000,000.00 2,000,000.00
2 BAHAN
Pompa Submersible Head 102 m
a. = 1.00 X 1.00 = 1.00 Bh 26,500,000.00 26,500,000.00
(Outlet 1,5" & Debit 1,5 l/dt)
b. Panel Kontrol Doubel WLC = 1.00 X 1.00 = 1.00 Paket 3,500,000.00 3,500,000.00
c. Kabel WLC NYY-HY 3x0.75mm = 750.00 X 1.00 = 750.00 m 10,000.00 7,500,000.00
d. Kabel Elektroda 3x2.5mm = 50.00 X 1.00 = 50.00 m 20,000.00 1,000,000.00
e. Watermoor GI 1.5" = 1.00 X 1.00 = 1.00 Bh 13,000.00 13,000.00
f. Check Valve 1.5" = 1.00 X 1.00 = 1.00 Bh 50,000.00 50,000.00
Pipa PVC bertekanan (AW) Ø
g. = 4.00 X 1.00 = 4.00 m 16,000.00 64,000.00
1.5"
h. Sock drat luar PVC 1.5" = - X 1.00 = - Bh 25,000.00 -
i. Sock drat dalam PVC 1.5" = - X 1.00 = - Bh 15,000.00 -
j. Knee GI 1.5" = - X 1.00 = - Bh 35,000.00 -
k. Ball Valve = - X 1.00 = - Bh 400,000.00 -
l. Stabilisher = 1.00 x 1.00 = 1.00 Bh 6,500,000.00 6,500,000.00
m. Tali nilon = 10.00 x 1.00 = 10.00 meter 7,500.00 75,000.00
n. Knee PVC (AW) Ø 1.5" = 2.00 X 1.00 = 2.00 Bh 22,000.00 44,000.00
o. Pipa (AW) Ø 6" = 4.00 X 1.00 = 4.00 m 165,000.00 660,000.00
p. Knee (AW) Ø 6" = 1.00 X 1.00 = 1.00 Bh 160,000.00 160,000.00
q. Dop (AW) Ø 6" = 1.00 X 1.00 = 1.00 Bh 156,000.00 156,000.00
j. Masker Kain = 1.00 x 1.00 = 1.00 Bh #REF! #REF!
Total I #REF!
GRAND TOTAL #REF!
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan
I. PEKERJAAN GALIAN
1 Galian Tanah 113.25 M3 2 Upah
P L d = Vol (m3) a. Pekerja = 57 X 0.75 = 42.47 Hok 110,700
Pipa GI dia. 6 " = = -
Pipa GI dia. 4 " = = -
Pipa GI dia. 3 " = = -
Pipa GI dia. 2.5" = = -
Pipa GI dia. 2" = = -
Pipa GI dia. 1.5" = = -
Pipa GI dia. 1" = = -
Pipa GI dia. 3/4" = = -
Pipa GI dia. 0.5" = = -
Pipa HDPE dia. 6 " = 0.35 0.53 = -
Pipa HDPE dia. 4 " = 0.30 0.47 = -
Pipa HDPE dia. 3 " = 0.30 0.44 = -
Pipa HDPE dia. 2.5" = 0.30 0.41 = -
Pipa HDPE dia. 2" = 300 0.25 0.39 = 29
Pipa HDPE dia. 1.5" = 0.20 0.38 = -
Pipa HDPE dia. 1" = 1200 0.20 0.35 = 84
Pipa HDPE dia. 3/4" = 0.15 0.2 = -
Pipa HDPE dia. 0.5" = 0.15 0.2 = -
Pipa PVC dia. 6" = 0.35 0.53 = -
Pipa PVC dia. 4" = 0.30 0.47 = -
Pipa PVC dia. 3" = 0.30 0.44 = -
Pipa PVC dia. 2.5" = 0.30 0.41 = - -
Pipa PVC dia. 2" = 0 0.25 0.39 = - -
Pipa PVC dia. 1.5" = 0 0.20 0.38 = - -
Pipa PVC dia. 1.5" = 0.17 0.35 = - -
Pipa PVC dia. 3/4" = 0.15 0.2 = - -
Pipa PVC dia. 0.5" = 0.15 0.2 = - -
= 1500 = 113 M3
Upah
2 Timbunan bekas galian 38 37.75 a. Pekerja = 38 X 0.25 = 9.44 Hok 110,700
1/3 x galian

Total I
II. PEKERJAAN PASANGAN
PIPA
1 Pasangan Pipa GI (GALVANIS)
a. Pipa GI dia. 6 " - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 6" = - X 1 = - m 478,000

2 Upah
a. Pekerja = - X 0.51 = - Hok 110,700
b. Tukang = - X 0.25 = - Hok 151,500

a. Pipa GI dia. 4 " - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 4" = - X 1 = - m 250,000


Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan

2 Upah
a. Pekerja = - X 0.14 = - Hok 110,700
b. Tukang = - X 0.23 = - Hok 151,500

a. Pipa GI dia. 3 " - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 3" = - X 1 = - m 265,700

2 Upah
a. Pekerja = - X 0.14 = - Hok 110,700
b. Tukang = - X 0.23 = - Hok 151,500

a. Pasangan Pipa GI 2.5" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 2,5" = - X 1 = - m 160,000

2 Upah
a. Pekerja = - X 0.11 = - Hok 110,700
b. Tukang = - X 0.18 = - Hok 151,500

a. Pasangan Pipa GI 2" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 2" = - X 1 = - m 150,000

2 Upah
a. Pekerja = - X 0.11 = - Hok 110,700
b. Tukang = - X 0.18 = - Hok 151,500

a. Pasangan Pipa GI 1.5" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 1,5" = - X 1 = - m 135,000

2 Upah
a. Pekerja = - X 0.11 = - Hok 110,700
b. Tukang = - X 0.18 = - Hok 151,500

a. Pasangan Pipa GI 1" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 1" = - X 1 = - m 56,000


Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan

2 Upah
a. Pekerja = - X 0.05 = - Hok 110,700
b. Tukang = - X 0.09 = - Hok 151,500

a. Pasangan Pipa GI Dia. 3/4" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 3/4" = - X 1 = - m 40,000

2 Upah
a. Pekerja = - X 0.05 = - Hok 110,700
b. Tukang = - X 0.09 = - Hok 151,500

a. Pasangan Pipa GI Dia. 1/2" - M 1 Bahan

Panjang = 0m a. PIPA Galpanis (GI Medium A) Ø 1/2" = - X 1 = - m 32,000

2 Upah
a. Pekerja = - X 0.05 = - Hok 110,700
b. Tukang = - X 0.09 = - Hok 151,500

a. Pasangan Pipa HDPE Dia. 6" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 6" = - X 1 = - 282,000

2 Upah
a. Pekerja = - X 0.06 = - 110,700
b. Tukang = - X 0.03 = - 151,500

a. Pasangan Pipa HDPE Dia. 4" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 4" = - X 1 = - 135,000

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

a. Pasangan Pipa HDPE Dia. 3" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 3" = - X 1 = - 110,000

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

a. Pasangan Pipa HDPE Dia. 2,5" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 2,5" = - X 1 = - 65,000
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

a. Pasangan Pipa HDPE Dia. 2" 300.00 M 1 Bahan


Panjang = 300 m 300.00 M a. Pipa HDPE Ø 2" = 300 X 1 = 300.00 62,000

2 Upah
a. Pekerja = 300 X 0.04 = 5.25 110,700
b. Tukang = 300 X 0.02 = 2.55 151,500

a. Pasangan Pipa HDPE Dia. 1,5" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 1,5" = - X 1 = - 29,000

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

a. Pasangan Pipa HDPE Dia. 1" 1,200.00 M 1 Bahan


Panjang = 1200 1,200.00 M a. Pipa HDPE Ø 1" = 1,200 X 1 = 1,200.00 19,000

2 Upah
a. Pekerja = 1,200 X 0.04 = 21.00 110,700
b. Tukang = 1,200 X 0.02 = 10.20 151,500

a. Pasangan Pipa HDPE Dia. 3/4" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 3/4" = - X 1 = - 13,000

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

a. Pasangan Pipa HDPE Dia. 1/2" - M 1 Bahan


Panjang = 0 - M a. Pipa HDPE Ø 1/2" = - X 1 = - 12,000

2 Upah
a. Pekerja = - X 0.04 = - 110,700
b. Tukang = - X 0.02 = - 151,500

b Pasangan Pipa PVC Dia. 6" - M 1 Bahan


Panjang = 0m a. Pipa S 12,5 SNI Ø 6" = - X 1 = - m 192,000
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan

2 Upah
a. Pekerja = - X 0.08 = - Hok 110,700
b. Tukang = - X 0.14 = - Hok 151,500

b Pasangan Pipa PVC Dia. 4" - M 1 Bahan


Panjang = 0m a. Pipa S 12,5 SNI Ø 4" = - X 1 = - m 90,000

2 Upah
a. Pekerja = - X 0.08 = - Hok 110,700
b. Tukang = - X 0.14 = - Hok 151,500

a. Pasangan Pipa PVC Dia. 3" - M 1 Bahan


Panjang = 0m a. Pipa S 12,5 SNI Ø 3" = - X 1 = - m 55,000

2 Upah
a. Pekerja = - X 0.08 = - Hok 110,700
b. Tukang = - X 0.14 = - Hok 151,500

b. Pasangan Pipa PVC Dia. 2,5" - M 1 Bahan


Panjang = - m a. Pipa S 12,5 SNI Ø 2,5" = - X 1 = - m 44,000

2 Upah
a. Pekerja = - X 0.05 = - Hok 110,700
b. Tukang = - X 0.07 = - Hok 151,500

b. Pasangan Pipa PVC Dia. 2" - M 1 Bahan


Panjang = - m a. Pipa S 12,5 SNI Ø 2" = - X 1 = - m 25,666

2 Upah
a. Pekerja = - X 0.05 = - Hok 110,700
b. Tukang = - X 0.07 = - Hok 151,500
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan
c. Pasangan Pipa PVC Dia. 1,5" - M 1 Bahan
Panjang = 0m a. Pipa S 12,5 SNI Ø 1,5" = - X 1 = - m 25,000

2 Upah
a. Pekerja = - X 0.04 = - Hok 110,700
b. Tukang = - X 0.06 = - Hok 151,500

e. Pasangan Pipa PVC Dia. 1" - M 1 Bahan


Panjang = 0m M a. Pipa S 10 SNIØ 1" = - X 1.000 = - m 15,000

2 Upah
a. Pekerja = - X 0.0360 = - Hok 110,700
b. Tukang = - X 0.0600 = - Hok 151,500

f. Pasangan Pipa PVC Dia. 3/4" - M 1 Bahan


Panjang = 0 M a. Pipa S 6.3 SNI Ø 3/4" = - X 1.000 = - m 12,000

2 Upah
a. Pekerja = - X 0.036 = - Hok 110,700
b. Tukang = - X 0.060 = - Hok 151,500

g. Pasangan Pipa PVC Dia. 1/2" - M 1 Bahan


Panjang = 0 M a. Pipa S 6.3 SNI Ø 1/2" = - X 1.000 = - m 10,000

2 Upah
a. Pekerja = - X 0.081 = - Hok 110,700
b. Tukang = - X 0.135 = - Hok 151,500

Total II
II. PERLENGKAPAN DAN
ACCESORIS PIPA Dimensi
1 Coupler HDPE 2" 2" 5.00 Bh Coupler HDPE 2" 5.00 Bh 317,200
2 Coupler HDPE 1" 1" 10.00 Bh Coupler HDPE 1" 10.00 Bh 182,200
3 Reducer Coupler 2"x1" 2'x1" 1.00 Bh Reducer Coupler 2"x1" 1.00 Bh 174,200
4" - Bh Tee PVC Ø 4" - Bh 200,000
3" - Bh Tee PVC Ø 3" - Bh 150,000
2" - Bh Tee PVC Ø 2" - Bh 85,000
1,5" - Bh Tee PVC Ø 1,5" - Bh 75,000
1" - Bh Tee PVC Ø 1" - Bh 50,000
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan
3 Long Bend 90 6" - Bh Long Bend PVC 90 Ø 6" - Bh 140,000
4" - Bh Long Bend PVC 90 Ø 4" - Bh 140,000
3" - Bh Long Bend PVC 90 Ø 3" - Bh 140,000
2" - Bh Long Bend PVC 90 Ø 2" - Bh 110,000
1,5" - Bh Long Bend PVC 90 Ø 1,5" - Bh 80,000

4 Stop Kran 6" - Bh Stop Kran PVC Ø 6" - Bh 1,250,000


4" - Bh Stop Kran PVC Ø 4" - Bh 1,000,000
3" - Bh Stop Kran PVC Ø 3" - Bh 700,000
2,5" - Bh Stop Kran PVC Ø 2,5" - Bh 475,000
2" 1.00 Bh Stop Kran PVC Ø 2" 1.00 Bh 222,000
1,5" - Bh Stop Kran PVC Ø 1,5" - Bh 163,500

5 Dop/Endcop PVC 2" 1.00 Bh End cop (Dop PVC) Ø 2" 1.00 Bh 50,000
1,5" - Bh End cop (Dop PVC) Ø 1.5 - Bh 35,000
1" - Bh End cop (Dop PVC) Ø 1" - Bh 25,000
3/4" - Bh End cop (Dop PVC) Ø 3/4" - Bh 76,000

6 Gibolt Joint 3" - Bh Gibot Joint PVC Ø 3" - Bh -

7 Tee 3" x 2" - Bh Reducer Tee All Socket PVC Ø 3" x 2" - Bh 160,000
2,5" x 1" - Bh Reducer Tee All Socket PVC Ø 2,5" x 1" - Bh 35,000
2" x 1" - Bh Reducer Tee All Socket PVC Ø 2" x 1" - Bh 110,000
1.5" x 1" - Bh Reducer Tee All Socket PVC Ø 1,5" x 1" - Bh 272,000

8 Shock Drat Luar 6" - Bh Shock Drat Luar PVC Ø 6" - Bh 75,000
4" - Bh Shock Drat Luar PVC Ø 4" - Bh 60,000
3" - Bh Shock Drat Luar PVC Ø 3" - Bh 62,000
2" - Bh Shock Drat Luar PVC Ø 2" - Bh 62,000
1,5" - Bh Shock Drat Luar PVC Ø 1,5" - Bh 56,000
1" - Bh Shock Drat Luar PVC Ø 1" - Bh 62,000

9 Rejucer Socket PVC 6"x4" - Bh Reducer Socket PVC Ø 6" x 4" - Bh 272,000
4" x 3" - Bh Reducer Socket PVC Ø 4" x 3" - Bh 149,000
3" x 2" - Bh Reducer Socket PVC Ø 3" x 2" - Bh 122,000
2.5" x 2" - Bh Reducer Socket PVC Ø 2.5" x 2" - Bh 115,000
2" x 1,5" - Bh Reducer Socket PVC Ø 2" x 1,5" - Bh 90,000
2" x 1" - Bh Reducer Socket PVC Ø 2" x 1" - Bh 80,000
1,5" x 1" - Bh Reducer Socket PVC Ø 1,5" x 1" - Bh 65,000

10 Knee 6" - Bh Knee PVC Ø 6" - Bh 200,000


4" - Bh Knee PVC Ø 4" - Bh 210,000
3" - Bh Knee PVC Ø 3" - Bh 70,000
2" - Bh Knee PVC Ø 2" - Bh 33,000
1,5" - Bh Knee PVC Ø 1,5" - Bh 22,000
1" - Bh Knee PVC Ø 1" - Bh 18,000

11 Clamp Saddle 3" x 1" - Bh Clamp Saddle PVC Ø 3" x 1" - Bh 55,000
2" x 1" - Bh Clamp Saddle PVC Ø 2" x 1" - Bh 50,000
2" x 3/4" - Bh Clamp Saddle PVC Ø 2" x 3/4" - Bh 35,000
1" x 3/4" - Bh Clamp Saddle PVC Ø 1" x 3/4" - Bh 30,000
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan

12 Bend 45 1" - Bh Bend 45 Ø 1" - Bh 76,500

12 Flang Spigot HDPE 6" - Bh Flang Spigot HDPE Ø 6" - Bh 185,000


13 Flang Spigot PVC 6" - Bh Flang Spigot PVC Ø 6" - Bh 650,000
-
14 Coupler HDPE 6" Bh Coupler HDPE Ø 6" - Bh 300,000
15 Lem Pipa 1.00 Bh Lem Pipa Kualitas baik 1.00 Bh 55,000
16 Seal Tape 4.00 Bh Sealtipe 4.00 Bh 10,000
17 Crosing - m Crosing - m 250,000
Total III

GRAND TOTAL
III. PEKERJAAN BETON IIIPEKERJAAN BETON BERTULANG 1 : 2 : 3
1 Pekerjaan Cor Plat Beton Penutup (15 Cm) Lantai 1: 2: 3
= P X L * T
= 4 X 1.00 * 0.15
= 0.6 M3
Kebutuhan Besi Memanjang
- Besi Ǿ ### Jarak = 0
Banyaknya beugel = P +
0
= 7 →
Panjang per Besi = 4
= P X Byk
###
= 4.4 X 0
###
= 0 Lonjor
Untuk 2 Lapis
= 0 Lonjor

Kebutuhan Besi Melintang


- Besi Ǿ ### Jarak = 0
Banyaknya beugel = P +
0
= 28 →
Panjang per Besi = 1
= P X Byk
###
= 1.4 X 0
###
= 0 Lonjor
Untuk 2 Lapis
= 0 Lonjor

Total Kebutuhan Besi


= 0
Berat Besi ( Dia 12 per m' = 0.88 kg) 11 kg/ljr
= 0
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan
Kabupaten : Jenis Prasarana : Instalasi Pipa
Kecamatan :
Desa/Kelurahan :
Take Of Sheet Lokasi
Volume
:
: 1,500

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan
sumur a. Pas. Buis beton Ø 80cm Panjang 0,5 m 15.00 M 1 Bahan

a. Pas. Buis beton Ø 80cm Panjang 0,5 m = 15 X 1 = 15.00 m 500,000

2 Upah
a. Pekerja = 15 X 0.79 = 11.78 Hok 110,700
b. Tukang = - X 0.09 = - Hok 151,500
m

Biaya

4,701,291

1,044,731

5,746,022

-
-

-
m

Biaya

-
-

-
-

-
-

-
-

-
-

-
m

Biaya

-
-

-
-

-
-

-
-

-
-

-
-

-
m

Biaya

-
-

18,600,000

581,175
386,325

-
-

22,800,000

2,324,700
1,545,300

-
-

-
-

-
m

Biaya

-
-

-
-

-
-

-
-

-
-
m

Biaya

-
-

-
-

-
-

-
-

46,237,500

1,586,000
1,822,000
174,200
-
-
-
-
-
m

Biaya
-
-
-
-
-

-
-
-
-
222,000
-

50,000
-
-
-

-
-
-
-

-
-
-
-
-
-

-
-
-
-
-
-
-

-
-
-
-
-
-

-
-
-
-
m

Biaya

-
-

-
55,000
40,000
-
3,949,200

55,932,722
m

Biaya

7,500,000

1,303,493
-
RENCANA ANGGARAN BIAYA

Nomor RAB : B.02


Pekerjaan / Kegiatan : Jaringan Perpipaan

Volume
Harga Satuan
URAIAN Satuan
Total BLM
Rp
1 2=3+4+5 7 8 13=6x8

1 BAHAN

1 Pipa HDPE Ø 2" 300 Meter 62,000 18,600,000

2 Pipa HDPE Ø 1" 1,200 Meter 19,000 22,800,000

3 Coupler HDPE 2" 5 Buah 317,200 1,586,000

4 Coupler HDPE 1" 10 Buah 182,200 1,822,000

5 Reducer Coupler 2"x1" 1 Buah 174,200 174,200

6 Stop Kran PVC Ø 2" 1 Buah 222,000 222,000

7 End cop (Dop PVC) Ø 2" 1 Buah 50,000 50,000

8 Lem Pipa Kualitas baik 1 Buah 55,000 55,000

9 Sealtipe 4 Buah 10,000 40,000

Sub Total 1) 45,349,200

2 UPAH

1 Pekerja 75 HOK 110,700 8,331,144

2 Tukang 13 HOK 151,500 1,931,625

Sub Total 2) 10,262,769

Sub Total 3) -

JUMLAH TOTAL 55,611,969

JUMLAH TOTAL DIBULATKAN 55,611,000


Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya
I PEKERJAAN PENDAHULUAN
a Pekerjaan Pembersihan 0 Ls 0 Ls 50,000.00 -

b Pasangan Bouplank = L x T x P 0m 1 Bahan


= 4 x 0 x 3.5 a Balok Kayu Kelas III = 0 X 0.012 = 0 m3 5,501,200.00 -
= 15 m' b Paku = 0 X 0.02 = 0 kg 20,000.00 -
c Papan kayu Begisting = 0 X 0.007 = 0 m3 5,501,200.00 -

2 Upah
a Pekerja = 0 X 0.1 = 0 Hok 110,700.00 -
b Tukang = 0 X 0.1 = 0 Hok 151,500.00 -

Total I -
II PEKERJAAN GALIAN DAN URUGAN
L x T x P =
a Galian Tanah Pondasi 0.35 x 1 x 16 = 2.8 2.8 m3 1 Upah
a Pekerja = 2.8 X 0.75 = 2.1 Hok 110,700.00 232,470.00

b Timbunan Kembali Tanah Galian 1 0.9333 m3 1 Upah


2 Pekerja = 0.9333 X 0.25 = 0.2333 Hok 110,700.00 25,830.00
= 0.93

P x L x T = V
c Urugan Tanah Peniggian Lantai 1 selasar 4 x 1 x 0.2 = 0.8 2.4 m3 1 Bahan
2 Ruangan 4 x 2 x 0.2 = 1.6 a Tanah Urug = 2.4 X 1.2 = 2.88 m3 67,300.00 193,824.00
= 2.4
2 Upah
a Pekerja = 2.4 X 0.30 = 0.72 Hok 110,700.00 79,704.00

P x L x T = V
d Urugan pasir dibawah lantai 1 selasar 4 x 1 x 0.05 = 0.2 0.6 m3 1 Bahan
2 Ruangan 4 x 2 x 0.05 = 0.4 a Pasir Urug = 0.6 X 1.2 = 0.72 m3 188,900.00 136,008.00
= 0.6
2 Upah
a Pekerja = 0.6 X 0.30 = 0.18 Hok 110,700.00 19,926.00

Total II 687,762.00
III PEKERJAAN PASANGAN Panjang Total
a Pasangan Batu Kosong 0.84 m3
Volume P L t = 1 Upah
16 0 0.15 = 0.84 a. Pekerja = 0.84 X 1.50 = 1.26 hok 110,700.00 139,482.00
b. Tukang = 0.84 X 0.60 = 0.504 hok 151,500.00 76,356.00
2 Bahan
a. Batu Kali Alam = 0.84 X 1.20 = 1.008 m3 210,700.00 212,385.60
b. Pasir urug = 0.84 X 0.43 = 0.3629 m3 188,900.00 68,548.03
-
Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya
a Pasangan Batu Kali 1pc : 4Ps Volume 1.68 m3
P L t = 1 Upah
16 0 0.35 = 1.68 a. Pekerja = 1.68 X 1.50 = 2.52 hok 110,700.00 278,964.00
b. Tukang = 1.68 X 0.60 = 1.008 hok 151,500.00 152,712.00
2 Bahan
a. Batu Kali Alam = 1.68 X 1.10 = 1.848 m3 210,700.00 389,373.60
b. Semen 1.68 2.72 = 4.5696 sak 60,000.00 274,176.00
c Pasir pasangan 1.68 0.54 = 0.9139 m3 207,500.00 189,638.40

b Pas. Pondasi Rolag 1 pc : 5 ps Panjang Total m2


1 Vertikal 1 Upah
3 x 2 = 6 m a. Pekerja = 0.00 X 0.65 = 0 hok 110,700.00 -
2 Horizontal b. Tukang = 0.00 X 0.20 = 0 ok 151,500.00 -
1 x 2 = 2 m 2 Bahan 0 -
= 8m a. Bata merah = 0.00 X 140.00 = 0 m3 1,500.00 -
b. Semen 0.00 0.66 = 0 sak 60,000.00 -
P x T c Pasir pasangan 0.00 0.09 = 0 m3 207,500.00 -
8 x 0 = 1.6
c Pasangan 1/2 Bata 1pc:4ps Panjang Total 32.34 m2
1 Vertikal 1 Upah
4 x 2 = 8 m a. Pekerja = 32.34 X 0.32 = 10.349 hok 110,700.00 1,145,612.16
2 Horizontal b. Tukang = 32.34 X 0.10 = 3.234 ok 151,500.00 489,951.00
2 x 3 = 6 m 2 Bahan -
= 14 m a. Bata merah = 32.34 X 72.00 = 2328.5 m3 1,500.00 3,492,720.00
b. Semen 32.34 0.05 = 1.6817 sak 60,000.00 100,900.80
P x T c Pasir pasangan 32.34 0.02 = 0.4851 m3 207,500.00 100,658.25
14 x 3 = 35

lubang
0.7 2 2 2.66
d Plesteran 32.3 64.68 m2 1 Upah
1 Plesteran Trasram 1Pc: 3 Ps dinding a. Pekerja = 64.68 X 0.30 = 19.404 hok 110,700.00 2,148,022.80
P x T sisi b. Tukang = 64.68 X 0.15 = 9.702 ok 151,500.00 1,469,853.00
= 14 x 3 x 2 2 Bahan
= 70 a. Semen = 64.68 X 0.10 = 6.706 sak 60,000.00 402,361.34
= 64.68 b. Pasir pasangan = 64.68 X 0.03 = 1.6817 m3 207,500.00 348,948.60
Lantai
P x T sisi
= 4 x 4 x 1
= 14

Acian + Mill Luas Bidang 49 m2 1 Upah


Acian P x T sisi a. Pekerja = 49.00 X 0.20 = 9.8 hok 110,700.00 1,084,860.00
= 14 x 3 x 2 b. Tukang = 49.00 X 0.10 = 4.9 ok 151,500.00 742,350.00
= 70 2 Bahan
a. Semen = 49.00 X 0.02 = 1.0613 sak 60,000.00 63,680.40
= 14 x 2 x 1 b. Mil = 49.00 x 2.17 = 106.18 m3 1,000.00 106,183.00
= 21
49
Total II 13,477,736.99
Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya
IV PEKERJAAN LANTAI
a Rabat Lantai Beton 1:2:3. t=10 cm P x L x T m3
3 x 3 x 0.1 1 Upah
a. Pekerja = 0.00 X 1.65 = 0 hok 110,700.00 -
b. Tukang = 0.00 X 0.25 = 0 ok 151,500.00 -
2 Bahan
a. Semen = 0.00 X 6.46 = 0 m3 60,000.00 -
b. Pasir cor = 0.00 X 0.52 = 0 sak 214,800.00 -
c Kerikul pecah 2 - 3 cm = 0.00 X 0.78 = 0 m3 400,000.00 -
b Acian P x L
3 x 3 m2 1 Upah
a. Pekerja = 0.00 X 0.16 = 0 hok 110,700.00 -
b. Tukang = 0.00 X 0.08 = 0 hok 151,500.00 -
2 Bahan
a. Semen = 0.00 X 0.07 = 0 Sak 60,000.00 -

P x L
b Keramik Lantai 4 x 4 14 14 m2 Upah
a. Pekerja = 14.00 X 0.7 = 9.8 hok 110,700.00 1,084,860.00
b. Tukang = 14.00 X 0.35 = 4.9 hok 151,500.00 742,350.00
Bahan
a. Keramik Lantai Kwalitas Seda = 14.00 X 1.00 = 14 m2 74,000.00 1,036,000.00
b. Semen = 14.00 X 0.21 = 2.912 Zak 60,000.00 174,720.00
c Pasir pasangan = 14.00 X 0.05 = 0.63 m3 207,500.00 130,725.00

P x T
b Keramik dinding 7 x 2 x 2 21 m2 Upah
a. Pekerja = 21.00 X 0.90 = 18.9 hok 110,700.00 2,092,230.00
= 21 b. Tukang = 21.00 X 0.45 = 9.45 hok 151,500.00 1,431,675.00
Bahan
a. Keramik Dinding Kwalitas Sed = 21.00 X 1.00 = 21 m2 79,000.00 1,659,000.00
b. Semen = 21.00 X 0.19 = 3.906 Zak 60,000.00 234,360.00
c Pasir pasangan = 21.00 X 0.02 = 0.378 m3 207,500.00 78,435.00

Total IV 8,664,355.00
V PEKERJAAN BETON
Sloof 15/20 cm
P x L x T
14 x 0x 0.2 = 0.42
Kolom Praktis 10/10 cm
P x L x T x Jlh
0.1 x 0.1 x 2.7 x 6 0.16
Ring Balok 10/10 cm
P x L x T
14 x 0x 0.1 0.14
Total 0.72 0.722 M3 BETON
Pekerjaan Beton Bertulang K-175 0.722 M3 1 Bahan
a Semen 0.722 x 6.520 = 4.7074 Sak 60,000.00 282,446.40
b Pasir cor 0.722 x 0.543 = 0.3919 m3 214,800.00 84,189.33
c Kerikil pecah 2 - 3 cm 0.722 x 0.762 = 0.5503 m3 400,000.00 220,129.78
d Air 0.722 x 215.000 = 155.23 Ltr 100.00 15,523.00

2 Upah
a Pekerja 0.722 x 1.650 = 1.1913 Hok 110,700.00 131,876.91
b Tukang 0.722 x 0.275 = 0.1986 Hok 151,500.00 30,080.33
Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya

Pekerjaaan Pembesian #REF! Kg BESI


1 Bahan
= 0.722 X ### = ### a Besi Beton Polos #REF! x 1.050 = #REF! Kg 20,050.00 #REF!
b Kawat Ikat Beton #REF! x 0.015 = #REF! Kg 35,000.00 #REF!

2 Upah
a Pekerja #REF! x 0.007 = #REF! Hok 110,700.00 #REF!
b Tukang #REF! x 0.007 = #REF! Hok 151,500.00 #REF!
Pekerjaan Bekisting Sloof #REF! M2
Pekerjaan Bekisting Kolom #REF! M2 BEGISTING SLOOF
Pekerjaan Bekisting Ring balok #REF! M2 1 Bahan
a Papan Kayu Begisting #REF! x 0.045 = #REF! m3 5,501,200.00 #REF!
b Paku #REF! x 0.300 = #REF! kg 20,000.00 #REF!
c Minyak Bekisting #REF! x 0.100 = #REF! Ltr - #REF!
2 Upah
a Pekerja #REF! x 0.520 = #REF! Hok 110,700.00 #REF!
b Tukang #REF! x 0.260 = #REF! Hok 151,500.00 #REF!

BEGISTING KOLOM
1 Bahan
a Papan Kayu Begisting #REF! x 0.040 = #REF! m3 5,501,200.00 #REF!
b Paku #REF! x 0.400 = #REF! kg 20,000.00 #REF!
c Minyak bekisting #REF! x 0.200 = #REF! Ltr - #REF!
Balok Kayu Kelas III #REF! x 0.015 = #REF! Ltr 5,501,200.00 #REF!
Triplek besar 122x242 cm tebal #REF! x 0.350 = #REF! Ltr 79,000.00 #REF!
Dolken diamater 8-10cm P=4m #REF! x 2.000 = #REF! Ltr 26,200.00 #REF!
2 Upah
a Pekerja #REF! x 0.660 = #REF! Hok 110,700.00 #REF!
b Tukang #REF! x 0.330 = #REF! Hok 151,500.00 #REF!

BEGISTING RINGBALK
1 Bahan
a Papan Kayu Begisting #REF! x 0.040 = #REF! m3 5,501,200.00 #REF!
b Paku #REF! x 0.400 = #REF! kg 20,000.00 #REF!
c Minyak bekisting #REF! x 0.200 = #REF! Ltr - #REF!
Balok Kayu Kelas III #REF! x 0.018 = #REF! Ltr 5,501,200.00 #REF!
Triplek besar 122x242 cm tebal #REF! x 0.350 = #REF! Ltr 79,000.00 #REF!
Dolken diamater 8-10cm P=4m #REF! x 2.000 = #REF! Ltr 26,200.00 #REF!
2 Upah
a Pekerja #REF! x 0.660 = #REF! Hok 110,700.00 #REF!
b Tukang #REF! x 0.330 = #REF! Hok 151,500.00 #REF!

Total V #REF!
VI Pekerjaan Rangka atap
1 Rangka Atap Kayu Klas. II 1 Atap Induk 2.1 m2 1 Upah
P x L a. Pekerja = 2.10 X 0.10 = 0.21 hok 110,700.00 23,247.00
20 x 0.07 x 0.05 = 1.4 m2 b. Tukang = 2.10 X 0.10 = 0.21 hok 151,500.00 31,815.00
2 Bahan 0
2 Atap Konsol a. Balok Kayu Klas II = 2.10 X 0.01 = 0.0252 m3 4,312,400.00 108,672.48
P x L b. Paku = 2.10 0.05 = 0.0945 Kg 20,000.00 1,890.00
10 x 0.07 x 0.05 = 0.7 m2
2.1 m2
Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya
2 Atap Spandek 0,30 mm 1 Atap Induk 25 M2 1 Upah
P x L a. Pekerja = 25.00 X 0.12 = 3 hok 110,700.00 332,100.00
5 x 2.7 x = 13.5 m2 b. Tukang = 25.00 X 0.06 = 1.5 Hok 151,500.00 227,250.00
2 Bahan
2 Atap Konsol a. Spandek 3 mm lebar 70 cm = 25.00 X 0.70 = 17.5 Lbr 37,000.00 647,500.00
P x L b. Baut spandek = 25.00 0.02 = 0.5 Kg 30,000.00 15,000.00
5 x 2.3 = 11.5 m2
25 m2

3 Kalsiplank ukuran (1 x 20) cm 15 + 10 = 25 25 m' 1 Upah


a. Pekerja = 25.00 X 0.10 = 2.5 hok 110,700.00 276,750.00
b. Tukang = 25.00 X 0.05 = 1.25 Hok 151,500.00 189,375.00
2 Bahan
a. Kalsiplank ukuran (8X20) cm = 25.00 X 1.10 = 27.5 M3 15,000.00 412,500.00
b. Paku = 25.00 X 0.10 = 2.5 Kg 20,000.00 50,000.00

Total VI 2,316,099.48
VII Pekerjaan Kusen Dan Pintu
1 Pek. Kusen Pintu Kayu Kls. II Volume 0.0619
Panjang a b Titik 1 Upah
4.3 x 0 x 0.06 2 m3 a. Pekerja = 0.06 X 14.40 = 0.8916 hok 110,700.00 98,705.43
b. Tukang = 0.06 X 4.80 = 0.2972 Hok 151,500.00 45,028.22
2 Bahan
2 Pek. Daun Pintu Panil Luas a. Balok Kayu Klas II = 0.06 X 1.20 = 0.0743 M3 4,312,400.00 320,428.57
P L Titik
1.7 x 1 x 2 2.38 m2 1 Upah
a. Pekerja = 2.38 X 0.80 = 1.904 hok 110,700.00 210,772.80
b. Tukang = 2.38 X 2.40 = 5.712 Hok 151,500.00 865,368.00
2 Bahan
a. Papan Kayu Klas II = 2.38 X 0.04 = 0.0952 M3 4,312,400.00 410,540.48

3 Pasangan Kunci Tanam 2x slag 2 Titik 1 Upah


a. Pekerja = 2.00 X 0.08 = 0.16 hok 110,700.00 17,712.00
b. Tukang = 2.00 X 0.08 = 0.16 Hok 151,500.00 24,240.00
2 Bahan
a. Kunci Pintu Mutu Sedang = 2.00 X 1.00 = 2 M3 82,000.00 164,000.00
a. Engsel Pintu 3 Lubang kwalita = 4.00 X 1.00 = 4 M3 36,000.00 144,000.00
Total VII 2,300,795.51
VIII Pekerjaan Pengecatan
1 Cat Dinding 113.68 m2 1 Upah
a. Pekerja = 113.68 X 0.02 = 2.2736 hok 110,700.00 251,687.52
b. Tukang = 113.68 X 0.06 = 7.1618 Hok 151,500.00 1,085,018.76
2 Bahan
a. Plamir tembok = 113.68 X 0.15 = 17.052 kg 47,000.00 801,444.00
b Cat Tembok Mutu Standar/Se = 113.68 x 0.20 = 22.736 kg 41,000.00 932,176.00
c Cat Tembok Mutu Standar/Se = 113.68 x 0.22 = 24.555 kg 41,000.00 1,006,750.08
a b Titik 0
2 Cat Kusen 1 Kusren 0.24 x 4 x 2 2.064 m2 2 m2 1 Upah
2 Pintu 2.38 m2 a. Pekerja = 2.00 X 0.02 = 0.04 hok 110,700.00 4,428.00
2.00 m2 b. Tukang = 2.00 X 0.06 = 0.126 Hok 151,500.00 19,089.00
2 Bahan
a. Plamir Kayu = 2.00 X 0.15 = 0.3 kg 40,000.00 12,000.00
b Meni Kayu = 2.00 X 0.20 = 0.4 kg 56,000.00 22,400.00
c Minyak Cat biasa = 2.00 x 0.22 = 0.432 kg 40,000.00 17,280.00
d Cat Kayu Mutu Sedang = 2.00 x 0.26 = 0.52 kg 62,000.00 32,240.00

Total VIII 4,184,513.36


Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya
IX Pasangan Kloset Jongkok+Acc 2 Titik 1 Upah
a. Pekerja = 2.00 X 1.00 = 2.00 hok 110,700.00 221,400.00
b. Tukang = 2.00 X 1.50 = 3.00 Hok 151,500.00 454,500.00
2 Bahan
a. Closet Duduk Lengkap Kwalit = 2.00 X 1.00 = 2.00 Bh 2,000,000.00 4,000,000.00
b Semen = 2.00 x 0.12 = 0.24 Sak 60,000.00 14,400.00
c Pasir pasangan = 2.00 x 0.01 = 0.02 m3 207,500.00 4,150.00

ACC 1 Ember kapasitas 25 ltr 2 Bh Ember kapasitas 25 liter 2 Bh 75,000.00 150,000.00


2 Sikat Kloset 2 Bh Sikat Closet 2 Bh 15,000.00 30,000.00
Total IX 4,874,450.00
X Instalasi PIPA, Kran, Floor Drain
1 Pipa 1/2 " 36 m Pipa PVC bertekanan (AW) Ø 1/2" 36.00 m 7,000.00 252,000.00
2 Knee PVC 1/2" 3 bh Bend PVC 90 (Knee) Ø 1/2" 3.00 bh 70,000.00 210,000.00
3 Tee PVC 1/2" 2 bh Tee PVC Ø 1/2" 2.00 bh 30,000.00 60,000.00
4 Kran 1/2 2 bh Kran Ø 1/2" 2.00 bh 20,000.00 40,000.00
5 Water Meter 1 bh Water Meter 1/2" 1.00 bh 150,000.00 150,000.00
6 Stop Kran 1/2 1 bh Stop Kran Ø 1/2" 1.00 bh 79,000.00 79,000.00
7 Saringan Air Plastik tebal 2 bh Saringan Air Staenlist 2.00 bh 45,000.00 90,000.00
8 Shock Drat Dalam 1/2" 2 bh Shock Drat Dalam PVC Ø1/2" 2.00 bh 15,000.00 30,000.00
9 Sal tape 4 bh Sealtipe 4.00 bh 10,000.00 40,000.00
10 Pipa Galpanis dia. 1 1/4" (relling stainlis) 6 m Pipa Stailisetill Ø 1 1/4" 6.00 m 80,000.00 480,000.00
Box Meter 1 bh Box Meter 1.00 bh 100,000.00 100,000.00

Total X 1,531,000.00
XI SEPTIC TANK
1 Galian Tanah D x L x T =
1.2 x 1 x 1.5 = 3.3912 m3 1 Upah
a Pekerja = 3.3912 X 0.75 = 2.54 Hok 110,700.00 281,554.38

P T
2 Pasangan Buis Dia. 80 cm 2 3 M 1 Upah
a. Pekerja = 3.00 X 0.14 = 0.42 hok 110,700.00 46,494.00
b. Tukang = 3.00 X 0.07 = 0.21 ok 151,500.00 31,815.00
2 Bahan
a. Buis Beton Ø 80 Cm panjang = 3.00 X 2.00 = 6.00 Bh 250,000.00 1,500,000.00
b. Bata Merah 3.00 X 18.90 = 56.70 sak 1,500.00 85,050.00
c Semen 3.00 X 3.92 = 11.76 m3 60,000.00 705,600.00
d. Pasir Pasangan 3.00 X 0.06 0.17 m4 207,500.00 34,860.00
e Pasir urug 3.00 X 0.02 0.07 m5 188,900.00 13,600.80

3 Penutup buis beton Dia. 80 cm 2 m2 1 Upah


a. Pekerja = X 0.20 = 0.00 hok 110,700.00 -
b. Tukang = X 0.15 = 0.00 ok 151,500.00 -
2 Bahan
a. Tutup buis Ø 80 cm = 2.00 X 1.00 = 2.00 Sak 250,000.00 500,000.00
Kabupaten : Lombok Timur Jenis Prasarana : JAMBAN SEKOLAH
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 1 unit

Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. harga satuan Biaya

4 Inst. pipa Buangan Pipa D 3" 10 m 1 Bahan


a. Pipa PVC (Kwalitas D) Ø 3" = 10 X 1 = 10.00 m 35,000.00 350,000.00
2 Upah
a. Pekerja = 10 X 0.08 = 0.81 Hok 110,700.00 89,667.00
b. Tukang = 10 X 0.14 = 1.35 Hok 151,500.00 204,525.00

3,843,166.18
X ALAT PELINDUNG DIRI
1 Masker Kain 12 Bh 1 Masker Kain 12 Bh 10,000.00 120,000.00
2 Ember dan Keran 1 Bh 2 Ember dan Keran 1 Bh 85,000.00 85,000.00
3 Sabun Cuci Tangan Cair 2 Btl 3 Sabun Cuci Tangan Cair 2 Btl 50,000.00 100,000.00
305,000.00
TOTAL BIAYA MCK #REF!
RENCANA ANGGARAN BIAYA

Nomor RAB : B.02 Sub Pekerjaan/Kegiatan : Jamban


Pekerjaan / Kegiatan : Sanitasi Ukuran/Dimensi : 4x2 M

Volume Biaya (Rp)


Kontribusi Harga Satuan
URAIAN Satuan Kontribusi Masyarakat
Total Masyarakat APBDes APBN Total APBDes APBN
inCash Inkind Rp inCash Inkind
1 2=3+4+5 3 4 5 6 7 8 9=2x8 10=3x8 11=4x8 12=5x8 13=6x8

1 BAHAN

1 Balok Kayu Klas II - - - - m3 4,312,400 - - - - -

2 Papan Kayu Klas II - - - - m3 4,312,400 - - - - -

3 Balok Kayu Kelas III - - - - m3 5,501,200 - - - - -

4 Papan kayu Begisting - - - - m3 5,501,200 - - - - -

5 Dolken diamater 8-10cm P=4m - - - - Batang 26,200 - - - - -

6 Tanah Urug - - - - m3 67,300 - - - - -

7 Pasir Urug - - - - m3 188,900 - - - - -

8 Batu Kali Alam - - - - m3 210,700 - - - - -

9 Pasir pasangan - - - - m3 207,500 - - - - -

10 Pasir cor - - - - m3 214,800 - - - - -

11 Kerikil pecah 2 - 3 cm - - - - m3 400,000 - - - - -

12 Air - - - - liter 100 - - - - -

13 Bata merah - - - - Buah 1,500 - - - - -

14 Semen - - - - Zak 60,000 - - - - -

15 Keramik Lantai Kwalitas Sedang - - - - m2 74,000 - - - - -

16 Keramik Dinding Kwalitas Sedang - - - - m2 79,000 - - - - -

17 Paku - - - - kg 20,000 - - - - -

18 Besi Beton Polos - - - - Kg 20,050 - - - - -

19 Kawat Ikat Beton - - - - Kg 35,000 - - - - -

20 Spandek 3 mm lebar 70 cm - - - - m 37,000 - - - - -

21 Baut spandek - - - - Kg 30,000 - - - - -

22 Kalsiplank ukuran (8X20) cm - - - - m 15,000 - - - - -

23 Triplek besar 122x242 cm tebal 6 mm - - - - lembar 79,000 - - - - -

24 Kunci Pintu Mutu Sedang - - - - Buah 82,000 - - - - -

25 Engsel Pintu 3 Lubang kwalitas biasa - - - - Pasang 36,000 - - - - -

26 Closet Duduk Lengkap Kwalitas Sedang - - - - Set 2,000,000 - - - - -

27 Ember kapasitas 25 liter - - - - Buah 75,000 - - - - -

28 Sikat Closet - - - - Unit 15,000 - - - - -

29 Pipa PVC bertekanan (AW) Ø 1/2" - - - - m 7,000 - - - - -

30 Bend PVC 90 (Knee) Ø 1/2" - - - - Buah 70,000 - - - - -

31 Tee PVC Ø 1/2" - - - - Buah 30,000 - - - - -

32 Kran Ø 1/2" - - - - Buah 20,000 - - - - -

33 Water Meter 1/2" - - - - Set 150,000 - - - - -

34 Stop Kran Ø 1/2" - - - - Buah 79,000 - - - - -

35 Saringan Air Staenlist - - - - Buah 45,000 - - - - -

36 Shock Drat Dalam PVC Ø1/2" - - - - Buah 15,000 - - - - -

37 Sealtipe - - - - BH 10,000 - - - - -

38 Pipa Stailisetill Ø 1 1/4" - - - - m 80,000 - - - - -

39 Box Meter - - - - Set 100,000 - - - - -

40 Pipa PVC (Kwalitas D) Ø 3" - - - - m 35,000 - - - - -

41 Plamir tembok - - - - kg 47,000 - - - - -

42 Cat Tembok Mutu Standar/Sedang - - - - kg 41,000 - - - - -

43 Plamir Kayu - - - - kg 40,000 - - - - -

44 Meni Kayu - - - - kg 56,000 - - - - -

45 Minyak Cat biasa - - - - Liter 40,000 - - - - -

46 Cat Kayu Mutu Sedang - - - - kg 62,000 - - - - -

47 Mil - - - - kg 1,000 - - - - -

48 Buis Beton Ø 80 Cm panjang 0,50 m - - - - Buah 250,000 - - - - -

49 Tutup buis Ø 80 cm - - - - Buah 250,000 - - - - -

Sub Total 1) - - - - -

2 UPAH

1 Pekerja - - - - - OH 110,700 - - - - -

2 Tukang - - - - - OH 151,500 - - - - -

Sub Total 2) - - - - -
3 ALAT PELINDUNG DIRI

1 Masker Kain - - - - - Bh 10,000.00 - - - - -

2 Ember dan Keran - - - - - Bh 85,000.00 - - - - -

3 Sabun Cuci Tangan Cair - - - - - Btl 50,000.00 - - - - -


Sub Total 3) - - - - -

JUMLAH TOTAL - - - - -

JUMLAH TOTAL DIBULATKAN - - - - -


RENCANA ANGGARAN BIAYA (RAB)
(Sarana Air Minum dan Sanitasi)

Program : Program Penyediaan Air Minum dan Sanitasi Berbasis Masyarakat (Pamsimas) III
Pekerjaan : Sarana Air Minum dan Sanitasi Masyarakat
Lokasi : Desa …………………….
Tahun Anggaran : 2021

KODE HARGA JUMLAH


NO. URAIAN PEKERJAAN ANALISA VOLUME SAT. SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7
I. KEGIATAN SARANA AIR MINUM
I,1 PEK. PENGEBORAN #REF!
+ PEKERJAAN PERSIAPAN 442,800.00
- Pembersihan Lokasi Ls 1.00 Unit 442,800.00 442,800.00
- - -

PEKERJAAN PERSIAPAN ERICTION


PERALATAN, MOBILISASI DAN
+ DEMOBILISASI - - 2,719,550.00
- Pemasangan, Pemindahan, Pembongkaran Ls 1.00 Unit 2,553,500.00 2,553,500.00
- Galian tanah kolam lumpur A.2.3.1.1 2.00 M3 83,025.00 166,050.00
-
+ PENGERJAAN PENGEBORAN - #REF!
- Penyediaan air sirkulasi pengeboran Ls #REF! Liter 100.00 #REF!
- Pengadaan Bentonit untuk Lumpur penge Ls 2.40 Sak 250,000.00 600,000.00
- Pekerjaan Pengeboran dia. 6 " SB,05 80.00 m 183,702.00 14,696,160.00
- Pekerjaan Operasional Pompa Lumpur SB,04 80.00 m 146,789.50 11,743,160.00
- Reaming sumur dari dia. 150 mm ke 250 SB,06 80.00 m 91,851.00 7,348,080.00
- Electrical Logging (per 100 m Logging) SB,07 80.00 m 18,320.00 1,465,600.00
- Pengadaan dan pemasangan cassing pipa SB,08 64.00 m 222,787.50 14,258,400.00
- Pengadaan dan pemasangan screen ipa PV SB,09 16.00 m 220,350.00 3,525,600.00
- Pasangan gravel Kerikil/koral 0.5-1 cm Ls 1.57 M3 84,342.33 132,537.95
Grouting Beton Cor ( K175) A.4.1.1.5 0.94 M3 1,142,017.50 1,069,499.39
Pembersihan dengan air jetting Ls 1.00 Kali 3,136,484.74 3,136,484.74
- Pembersihan dengan water jetting Ls - Kali 1,031,505.00 -
- Pemompaan Uji sumur/Pumping Test SB,10 72.00 Jam 111,205.00 8,006,760.00
- - Uji Pendahuluan (Pre-Test) 24 Jam - - -
- - Uji Susut Bertahap (Step Drowdown Test - - -
- - Uji Debet Tetap (Continuos Test) 18 Jam - - -
- - Uji Pemulihan (Recovery Test) 12 Jam - - -
-
- PEMBUATAN BAK SUMUR BOR - - 523,480.30
- - -
- Pasangan Buis Dia. 80 cm Ls 1.00 Bh 273,480.30 273,480.30
Penutup buis beton Dia. 80 cm Ls 1.00 Bh 250,000.00 250,000.00

I,2 PEK. TOWER AIR #N/A


+ PEKERJAAN PERSIAPAN 198,100.00
- Pembersihan Lokasi A.2.2.1.9 10.00 m2 19,810.00 198,100.00

+ PEKERJAAN TANAH 1,667,966.42


- Galian Tanah pondasi A.2.3.1.1 15.36 m3 83,025.00 1,275,264.00
- Timbunan Kembali Tanah Galian A.2.3.1.9 5.12 m3 29,073.40 148,855.81
- Urugan Tanah Peniggian Lantai A.2.3.1.11a - m3 115,718.00 -
- Urugan pasir dibawah lantai dan pondasi A.2.3.1.11 0.93 m3 261,638.00 243,846.62

+ PEKERJAAN PASANGAN dan PLESTERAN 9,168,486.96


- Pek. Pondasi batu 1 : 4 A.4.4.1.4 3.60 m2 359,769.00 1,295,168.40
- Pas. Pondasi Rolag A.4.4.1.4 - m2 359,769.00 -
- Pasangan 1/2 Bata 1pc:4ps A.4.4.1.10 23.32 m2 176,935.50 4,126,135.86
- Plesteran lantai 1pc:3ps A.4.4.2.3 9.00 m2 72,660.70 653,946.30
- Plesteran dinding 1pc:4ps A.4.4.2.5 48.00 m2 70,172.80 3,368,294.40
- Acian + Mill A.4.4.2.27a 24.00 m2 42,504.60 1,020,110.40

+ PEKERJAAN BETON (1pc:2ps:3kr) 25,300,522.26


- Pekerjaan Beton Lantai Kerja K-100 0.00 2.05 m3 - -
- Pekerjaan Beton Bertulang K-175 A.4.1.1.5 7.02 m3 768,131.61 5,395,356.46
- Pekerjaaan Pembesian A.4.1.1.17 753.67 Kg 23,482.82 17,698,359.61
- Pekerjaan Bekisting pondasi A.4.1.1.20 - m2 329,046.80 -
- Pekerjaan Bekisting Sloof A.4.1.1.21 0.30 m2 356,552.80 106,965.84
- Pekerjaan Bekisting Kolom A.4.1.1.22 1.92 m2 550,041.40 1,056,079.49
- Pekerjaan Bekisting Balok A.4.1.1.23 - m2 566,545.00 -
- Pekerjaan Bekisting Plat A.4.1.1.24 1.47 m2 710,041.40 1,043,760.86
- Pekerjaan Bekisting Dinding A.4.1.1.25 - m2 562,535.40 -

+ PEK. PIPA dan ASESIORIS #N/A


- Pipa GI Ø 1.5" (inlet/masuk) Ls m' 135,000.00 -
- Pipa GI Ø 2" (Limpasan dan Penguras) Ls #N/A m' 150,000.00 #N/A
- Pipa GI Ø 3" (outlet/keluar) Ls #N/A m' 265,700.00 #N/A
- Knee GI dia. 1.5" Bh 35,000.00 -
- Knee GI dia. 3" Bh 130,000.00 -
- Sock drat dalam Pipa GI dia. 1.5' Bh 25,000.00 -
- Sock drat luar Pipa PVC dia. 1.5' #N/A Bh 96,000.00 #N/A
- Sock drat luar Pipa PVC dia. 3' #N/A Bh 56,000.00 #N/A
- Tangga Besi
Tangga PIPA GI Medium B Ø 1,5" - m' 77,483.00 -
Tangga PIPA GI Medium B Ø 1" - m' 49,150.00 -
Biaya Pasang dan Las Ls 1.00 Unit - -
Gate Valve 3" Ls Bh 1,300,000.00 -
Flank Socket PVC 3" Ls Bh 100,000.00 -
Flank last 3" Ls Bh 100,000.00 -
Karet pak 3" Ls Bh 25,000.00 -
- Menhol 70 x 70 cm Ls Bh 500,000.00 -

+ PEK. KAYU dan KUNCI -


- Pek. Kusen Pintu Kayu Kls. II A.4.6.1.2 - m3 8,684,520.00 -
- Pek. Daun Pintu Panil A.4.6.1.5 - m2 766,936.00 -
- Kunci Pintu Ls - buah 120,000.00 -
- Engsel Pintu Ls - buah 87,000.00 -

+ PEK. FINISHING 1,460,322.22


- Cat tembok A.4.7.1.10 41.04 m2 35,582.90 1,460,322.22
- Cat kayu A.4.7.1.4 - m2 44,726.90 -

I,3 PEK. JARINGAN PERPIPAAN 1,000.00


+ PEKERJAAN PERSIAPAN -
- Pembersihan Lokasi A.2.2.1.9 - m2 19,810.00 -

+ PEKERJAAN TANAH -
- Galian tanah A.2.3.1.1 - m3 83,025.00 -
- Timbunan Kembali Tanah Galian A.2.3.1.9 - m3 29,073.40 -

+ PEKERJAAN PEMASANGAN PIPA -


- Pasangan Pipa PVC 6" (S-12.5) A.5.1.1.33 - m' 222,118.40 -
- Pasangan Pipa PVC 4" (S-12.5) A.5.1.1.32 - m' 120,118.40 -
- Pasangan Pipa PVC 3" (S-12.5) A.5.1.1.31 - m' 85,118.40 -
- Pasangan Pipa PVC 2" (S-12.5) A.5.1.1.29 - m' 42,417.76 -
- Pasangan Pipa PVC 1" (S-12.5) A.5.1.1.27 - m' 28,424.80 -

+ PEKERJAAN ACCESSORIES PIPA -


- Tee PVC Ø 2.5" Ls - Bh 120,000.00 -
- Tee PVC Ø 2" Ls - Bh 85,000.00 -
- Long Bend PVC 90 Ø 2" Ls - Bh 100,000.00 -
- Long Bend PVC 90 Ø 1" Ls - Bh 75,000.00 -
- Stop Kran Ø 3" Ls - Bh 1,400,000.00 -
- Stop Kran Ø 2.5" Ls - Bh 950,000.00 -
- End cop (Dop PVC) Ø 2" Ls - Bh 50,000.00 -
- End cop (Dop PVC) Ø 1.5 Ls - Bh 35,000.00 -
- End cop (Dop PVC) Ø 1" Ls - Bh 25,000.00 -
- Reducer Tee All Socket PVC Ø 2.5" x 1" Ls - Bh 140,000.00 -
Reducer Tee All Socket PVC Ø 2.5" x 2" Ls - Bh 140,000.00 -
Reducer Tee All Socket PVC Ø 2" x 1" Ls - Bh 110,000.00 -
Reducer Socket PVC Ø 2.5" x 2" Ls - Bh 115,000.00 -
Reducer Socket PVC Ø 2" x 1" Ls - Bh 80,000.00 -
Lem Pipa Kualitas baik Ls - Bh 55,000.00 -
Sealtipe Ls - Bh 10,000.00 -

I,4 PEK. PENGADAAN DAN PEMASANGAN PELENGKAP LAINNYA #REF!

- Pompa & Aksesories Ls 1.00 Paket 57,725,625.00 57,725,625.00


- Panel, Pompa dan Aksesoris Ls #REF! Paket #REF! #REF!

II. KEGIATAN SARANA AIR SANITASI #REF!


II.1 PEK. JAMBAN SEHAT SISWA - X 1 UNIT #REF!
PEK. JAMBAN SEHAT SISWA #REF!
+ PEKERJAAN PERSIAPAN -
- Pekerjaan Pembersihan A.2.2.1.9 - m2 19,810.00 -
- Pasangan Bouplank -

+ PEKERJAAN GALIAN DAN URUGAN 510,193.20


- Galian Tanah Pondasi A.2.3.1.1 2.80 m3 83,025.00 232,470.00
- Timbunan Kembali Tanah Galian A.2.3.1.9 - m3 29,073.40 -
- Urugan Tanah Peniggian Lantai A.2.3.1.11a 2.40 m3 115,718.00 277,723.20
- Urugan pasir dibawah lantai A.2.3.1.11 - m3 261,638.00 -

+ PEKERJAAN PASANGAN 8,095,191.67


- Pasangan Batu Kosong A.3.2.1.9 0.84 m3 486,693.00 408,822.12
- Pasangan Batu Kali 1pc : 4Ps A.3.2.1.2 1.68 m3 849,125.00 1,426,530.00
- Pas. Pondasi Rolag 1 pc : 5 ps A.4.4.1.4 m2 359,769.00 -
- Pasangan 1/2 Bata 1pc:4ps A.4.4.1.10 32.34 m2 176,935.50 5,722,094.07
- Pek. Kusen Pintu Kayu Kls. II A.4.6.1.2 0.06 m3 8,684,520.00 537,745.48
- Pek. Daun Pintu Panil A.4.6.1.5 m2 766,936.00 -

+ PEKERJAAN BETON (1pc:2ps:3kr) #REF!


- Pekerjaan Beton Bertulang K-175 A.4.1.1.5 0.72 m3 768,131.61 554,591.03
- Pekerjaaan Pembesian A.4.1.1.17 #REF! Kg 23,482.82 #REF!
- Pekerjaan Bekisting Sloof A.4.1.1.21 #REF! m2 356,552.80 #REF!
- Pekerjaan Bekisting Kolom A.4.1.1.22 #REF! m2 550,041.40 #REF!
- Pekerjaan Bekisting Ring balok A.4.1.1.23 #REF! m2 566,545.00 #REF!

+ PEKERJAAN PLESTERAN & PENUTUP #N/A


- Plesteran A.4.4.2.5 64.68 m2 70,172.80 4,538,776.70
- Acian + Mill A.4.4.2.27a 49.00 m2 42,504.60 2,082,725.40
Keramik Lantai A.4.4.3.36 14.00 m2 253,370.50 3,547,187.00
Keramik dinding A.4.4.3.54 21.00 m2 #N/A #N/A

+ PEKERJAAN ATAP 14,721,044.60


- Rangka Atap Kayu Klas. II A.4.6.1.15 2.10 m3 5,965,476.00 12,527,499.60
- Atap Spandek 0,30 mm A.4.5.2.38 25.00 m2 49,722.80 1,243,070.00
- Kalsiplank ukuran (1 x 20) cm A.4.6.1.21a 25.00 m' 38,019.00 950,475.00

+ PEKERJAAN SANITASI #N/A


- Closet Jongkok Porselin A.5.1.1.2 #N/A bh 2,051,810.00 #N/A
- Pipa PVC Ø ½" Ls #N/A m' #REF! #REF!
- Pipa PVC Ø 2" Ls #N/A m' #REF! #REF!
- Pipa PVC Ø 3" Ls #N/A m' #REF! #REF!
- Kran Dia ½" Ls #N/A bh #REF! #REF!
- Floor drain Ls #N/A bh #REF! #REF!
- Bak Mandi Fiberglass Ls #N/A bh #REF! #REF!
- Septiktank Kap. 1 m3 Ls #N/A Unit #REF! #REF!

+ PEKERJAAN FINISHING #REF!


- Kunci Pintu Ls #N/A bh #REF! #REF!
- Engsel Pintu Ls #N/A bh #REF! #REF!
- Cat Dinding A.4.7.1.10 113.68 m2 35,582.90 4,045,064.07
- Cat Kayu A.4.7.1.4 #N/A m2 44,726.90 #N/A

3.3 PEK. SARANA CUCI TANGAN (CTPS) - X 3 UNIT #REF!


PEK. SARANA CUCI TANGAN (CTPS) #REF!
+ PEKERJAAN PERSIAPAN #REF!
- Pembersihan Lokasi A.2.2.1.9 #REF! m2 19,810.00 #REF!

+ PEKERJAAN TANAH #REF!


- Galian tanah A.2.3.1.1 #REF! m3 83,025.00 #REF!
- Timbunan Kembali Tanah Galian A.2.3.1.9 #REF! m3 29,073.40 #REF!
- Urugan Tanah Peniggian Lantai A.2.3.1.11a #REF! m3 115,718.00 #REF!
- Urugan pasir dibawah lantai A.2.3.1.11 #REF! m3 261,638.00 #REF!

+ PEKERJAAN PASANGAN #REF!


- Pas. Pondasi Rolag A.4.4.1.4 #REF! m2 359,769.00 #REF!
Pasangan 1/2 Bata 1pc:4ps A.4.4.1.10 #REF! m2 176,935.50 #REF!
- Plesteran lantai A.4.4.2.3 #REF! m2 72,660.70 #REF!

+ PEKERJAAN BETON (1pc:2ps:3kr) #REF!


- Pekerjaan Beton Bertulang K-175 A.4.1.1.5 #REF! m3 768,131.61 #REF!
- Pekerjaaan Pembesian A.4.1.1.17 #REF! Kg 23,482.82 #REF!
- Pekerjaan Bekisting Kolom A.4.1.1.22 #REF! m2 550,041.40 #REF!

+ PEKERJAAN SANITASI #REF!


- Buis Beton Ø 60 Cm. Ls #REF! bh #REF! #REF!
- Beton Penutup Buis Ø 60 Cm. Ls #REF! bh #REF! #REF!
- Pipa PVC Ø ½" Ls #REF! m' #REF! #REF!
- Pipa PVC Ø 2" Ls #REF! m' #REF! #REF!
- Tee PVC 1/2" Ls #REF! bh #REF! #REF!
- Knee PVC 1/2" Ls #REF! bh #REF! #REF!
- Shock drat dalam 1/2" Ls #REF! bh #REF! #REF!
- Seal tape Ls #REF! bh #REF! #REF!
- Kran Dia ½" Ls #REF! bh #REF! #REF!

+ PEKERJAAN FINISHING #REF!


- Cat Genteng A.4.7.1.20a #REF! m2 36,127.60 #REF!
REKAPITULASI RENCANA ANGGARAN BIAYA
(RAB STANDAR PU CIPTA KARYA)

Program : Program Penyediaan Air Minum dan Sanitasi Berbasis Masyarakat (Pamsimas) III
Pekerjaan : Sarana Air Minum dan Sanitasi Masyarakat
Lokasi : Desa …………………….
Tahun Anggaran : 2021

NO URAIAN PEKERJAAN JUMLAH

I. KEGIATAN PELATIHAN MASYARAKAT Rp 3,800,000.00


1.1 PELATIHAN KKM DAN SATLAK Rp 2,100,000.00
1.2 PELATIHAN KKM DAN BPSPAM Rp 1,700,000.00

II. KEGIATAN SARANA AIR MINUM #REF!


2.1 PEK. SUMUR BOR #REF!
2.2 PEK. TOWER AIR #N/A
2.3 PEK. JARINGAN PERPIPAAN Rp 1,000.00
2.4 #REF! #REF!

III. KEGIATAN SARANA SANITASI #REF!


3.1 PEK. JAMBAN SEHAT SISWA - X 1 UNIT #REF!
3.2 PEK. SARANA CUCI TANGAN (CTPS) - X 3 UNIT #REF!

IV. KEGIATAN PENINGKATAN PHBS Rp 5,797,500.00


4.1 PHBS & CLTS MASYARAKAT Rp 1,626,000.00
4.2 PHBS & CLTS SEKOLAH Rp 688,500.00
4.3 PELATIHAN STBM Rp 1,833,000.00
4.4 MEDIA PROMOSI KESEHATAN Rp 1,250,000.00
4.5 PENGAMBILAN SAMPLE AIR Rp 400,000.00

V. BIAYA OPERASIONAL KKM & SATLAK Rp 13,870,000.00


5.1 ATK, INFORMASI, KONSUMSI, TRANSPORTASI, LAPORAN DAN DOKUMEN Rp 13,870,000.00

JUMLAH #REF!
JUMLAH DIBULATKAN #REF!
Terbilang : Err:522

Form ini sebagai acuan pembuatan RAB Masyarakat


Pekerjaan : SARANA AIR MINUM

Perhitungan
Persegi Panjang Trapesium Lingkaran Vol.
Jml
No. Uraian Pekerjaan Lb Pj Tg S. Bwh S. Ats Tg Pj Ø1 Ø2 Tg
Sat
m m m m m m m m m Bh
V=LbxPjxTg V=((1/2(S.Bwh+S.Atas))xTg)xPj
2.1 PEK. SUMUR BOR 1 (UNIT)
1 Sumur Bor - 0.00 m

2.2 PEK. TOWER AIR


1 Pek. Pembersihan Lokasi 0 - - m2
2 Galian Tanah Pondasi
0 - 0 4 -
Total Galian Tanah - m3
3 Urugan tanah kembali
1/3 Galian tanah - m3
4 Urugan tanah peniggian 0 - 0 - m3
5 Urugan pasir dibawah lantai
Pondasi 0 - 0 -
Lantai 0 - 0 -
Total urugan pasir - m3
6 Pek. Pondasi rolag
Teras - 0 -
Total Pondasi rolag - m2
7 Pasangan dinding bata - 0 - m2
Total Pasangan bata - m2
8 Pek. Kusen Pintu Kayu Kls. II 0 0 0 1 - m3
9 Pek. Daun Pintu Panil 0 0 0 1 - m2
10 Pekerjaan Beton Lantai Kerja K-100 0 0 0 4 - m2
11 Pekerjaan Beton K-175
Footplat (100x100) cm 0 - 0 4 - m3
Beton sloof 20/20 cm 0.2 14.00 0.2 0.56 m3
Beton Kolom 20x20 cm 0.2 0.20 6 0.24 m3
Beton Kolom 15x15 cm 0 - 8 - m3
Ring Balok 15/15 cm 0.15 14.00 0.15 1 0.32 m3
Beton Balok 20/40 cm 0 - 0 - m3
Beton Balok silang 20/30 cm 0 - - - m3
Beton Plat Lantai 12 cm 3.5 3.50 0.12 1 1.47 m3
Beton Plat Penutup Gudang t 8 cm 0 - - 1 - m3
Beton Dinding 20 cm 0.2 14.00 1.5 4.20 m3
Beton Plat Penutup t = 8 cm 3.5 3.50 0.08 1 0.98 m3
Total Beton K-175 7.77 m3
12 Pekerjaan Pembesian
Footplat (140x140) cm
Besi Pokok D.12 mm X,Y - 0 Jrk X 0.15 Jrk Y 0.15 Dim 12 2 0 - Kg
Beton sloof 20/20 cm
Besi Pokok D.12 mm Pj tul 14.00 Jml Tul 6 Dim 12 84 74.61 Kg
Besi Gelang D.8 mm Pj. Bgl 1.20 Jml bgl 95.3333 Jrk 0.15 Dim 6 114.4 25.40 Kg
Beton Kolom 20x20 cm
Besi Pokok D.12 mm Pj tul 6.00 Jml Tul 8 Dim 12 48 42.63 Kg
Besi Gelang D.8 mm Pj. Bgl 1.00 Jml bgl 42 Jrk 0.15 Dim 6 42 9.33 Kg
Beton Kolom 15x15 cm
Besi Pokok D.10 mm Pj tul - Jml Tul 4 Dim 10 0 - Kg
Besi Gelang D.8 mm Pj. Bgl - Jml bgl 2 Jrk 0.15 Dim 6 0 - Kg
Ring Balok 15/15 cm
Besi Pokok D.12 mm Pj tul 14.00 Jml Tul 6 Dim 12 84 74.61 Kg
Besi Gelang D.8 mm Pj. Bgl 1.00 Jml bgl 95.3333 Jrk 0.15 Dim 6 95.333 21.17 Kg
Beton Balok 20/40 cm
Besi Pokok D.12 mm Pj tul - Jml Tul 8 Dim 12 0 - Kg
Besi Gelang D.8 mm Pj. Bgl - Jml bgl 95.3333 Jrk 0.15 Dim 6 0 - Kg
Beton Balok silang 20/30 cm
Besi Pokok D.12 mm Pj tul - Jml Tul 6 Dim 12 0 - Kg
Besi Gelang D.8 mm Pj. Bgl - Jml bgl 2 Jrk 0.15 Dim 6 0 - Kg
Beton Plat Lantai 12 cm
Besi Pokok D.10 mm X,Y 3.50 3.5 Jrk X 0.1 Jrk Y 0.1 Dim 10 1 259 159.75 Kg
Beton Plat Penutup Gudang t 8 cm
Besi Pokok D.10 mm X,Y - 0 Jrk X 0.1 Jrk Y 0.1 Dim 10 1 0 - Kg
Beton Dinding 20 cm
Besi Pokok D.10 mm X,Y 3.50 2 Jrk X 0.15 Jrk Y 0.15 Dim 10 2 417.33 257.41 Kg
Besi Pokok D.10 mm X,Y 1.50 2 Jrk X 0.15 Jrk Y 0.15 Dim 8 2 188 74.21 Kg
Beton Plat Dak t = 8 cm
Besi Pokok D.10 mm X,Y 3.50 3.5 Jrk X 0.15 Jrk Y 0.15 Dim 10 1 177.33 109.38 Kg
Total Pembesian 848.48 Kg
Kabupaten : Jenis Prasarana : RESERVOIR
Kecamatan : Take Of Sheet Lokasi :
Desa/Kelurahan : Volume : 2x2x2 Meter
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
P x L x T = JMLH
I PEMBERSIHAN LOKASI

Pembersihan Lokasi 1.00 Ls a. Pekerja = 1 x 1 = 1.00 Ls 110,700 110,700

TOTAL I 110,700
II PEKERJAAN TANAH dan PASIR

a. Galian Tanah pondasi - m3 Pekerja 0.75 x 0 = - OH 110,700 -


= 0x 1.60 x 1.5 = 4
= 0 m3

b. Timbunan Kembali Tanah Galian x 1/3 galian - m3 Pekerja 0.25 x 0 = - OH 110,700 -

c. Urugan Tanah Peniggian Lantai - m3 Tanah Urug 1.2 x 0 = - M3 67,300 -


= 0x - x 0 = 1 Pekerja 0.3 x 0 = - OH 110,700 -
= 0 m3

d. Urugan pasir dibawah lantai dan pondasi - m3 Pasir urug 1.2 x 0 = - M3 188,900 -
- Pondasi Pekerja 0.3 x 0 = - OH 110,700 -
= 0x 2 x 0.05 = 4
= 0 m3
- Lantai
= 0x 0 x 0.05 = 1
= 0 m3
- Pondasi batu kali
= 0x - x 0.05 = 1
= 0 m3
TOTAL II -

III PEKERJAAN PASANGAN


a. Pek. Pondasi batu 1 : 4 3.52 m3 Batu Kali Alam 1.2 x 3.52 = 4.22 M3 210,700 889,997
Semen 2.72 x 3.52 = 9.57 Zak 60,000 574,464
L atas L bawah Tinggi Kelilling Pasir pasangan 0.544 x 3.52 = 1.91 M3 207,500 397,338
= 0.3 + 0.8 0.8 x 8
= 3.52 m3 Pekerja 1.5 x 3.52 = 5.28 OH 110,700 584,496
Tukang 0.75 x 3.52 = 2.64 OH 151,500 399,960

b. Pasangan 1/2 Bata 1pc:4ps - m2 Bata merah 70 x 0 = - buah 1,500 -


= 0x 1 x 2.5 = 4 Semen 0.194 x 0 = - Zak 60,000 -
= 0 m2 Pasir pasangan 0.045 x 0 = - M3 207,500 -
Lubang kusen
= 0 x 2.10 = 0 Pekerja 0.3 x 0 = - OH 110,700 -
Tukang 0.1 x 0 = - OH 151,500 -

TOTAL III 2,846,254

IV PEKERJAAN BETON BERTULANG


1 Pekerjaan Beton Lantai Kerja K-100 - m3 Semen 4.94 x 0 = - Zak 60,000 -
= 0.0 x 0.0 x 0.2 = 4.0 Pasir Cor 0.621 x 0 = - M3 214,800 -
= 0.0 m2 Kerikil Pecah 3-5 cm 0.74 x 0 = - M3 428,300 -
Air 215 x 0 = - Ltr 100 -
Pekerja 1.65 x 0 = - OH 110,700 -
Tukang 0.275 x 0 = - OH 151,500 -

-
2 Pekerjaan Beton Bertulang K-175 7.77 m3 Semen 6.52 x 7.765 = 50.63 Zak 60,000 3,037,668
Footplat (100x100) cm Pasir Cor 0.543 x 7.765 = 4.22 M3 214,800 905,443
= 0 x 1.4 x 0.25 = 4 Batu Pecah 2-3 cm 0.762 x 7.765 = 5.92 M3 400,000 2,367,462
= 0 M3 Air 215 x 7.765 = 1,669.48 Ltr 100 166,948
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
Beton sloof 20/20 cm Pekerja 1.65 x 7.765 = 12.81 OH 110,700 1,418,316
= 14 x 0.2 x 0.2 = 1 Tukang 0.275 x 7.765 = 2.14 OH 151,500 323,509
= 0.56 M3
Beton Kolom 20x20 cm
= 0.20 x 0.20 x 6.00 = 1
= 0.24 M3
Ring Balok 15/15 cm
= 0.15 x 0.15 x 14 = 1
= 0.315 M3
Beton Plat Lantai 12 cm
= 3.5 x 3.5 x 0.12 = 1
= 1.47 M3
Beton Dinding 20 cm
= 0.2 x 14 x 1.5 = 1
= 4.2 M3
Beton Plat Penutup t = 8 cm
= 3.5 x 3.5 x 0.08 = 1
= 0.98 M3

2 Pekerjaaan Pembesian 516.86

Footplat (140x140) cm Besi Beton Polos 1.05 x 516.865 = 542.71 kg 20,050 10,881,296
= - kg Kawat Ikat Beton 0.015 x 516.865 = 7.75 kg 35,000 271,354

Beton sloof 20/20 cm Pekerja 0.007 x 516.865 = 3.62 OH 110,700 400,519


= 100.01 kg Tukang 0.007 x 516.865 = 3.62 OH 151,500 548,135

Beton Kolom 20x20 cm


= 51.96 kg

Ring Balok 15/15 cm


= 95.77 kg

Beton Plat Lantai 12 cm


= 159.75 kg

Beton Plat Dak t = 8 cm


= 109.38 kg

TOTAL IV 20,320,650
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

V PENGERJAAN BEGISTING M2 Sloof


Papan Kayu Begisting 0.045 x 0.28 = 0.01 M3 5,501,200 69,315
Begisting pondasi Pekerjaan Bekisting pondasi - M2 Paku 0.3 x 0.28 = 0.08 kg 20,000 1,680
= 0 x 0 x 0.4 = 4 Pekerja 0.52 x 0.28 = 0.15 OH 110,700 16,118
= 0 M2 Tukang 0.26 x 0.28 = 0.07 OH 151,500 11,029

Begisting Beton sloof 20/20 cm Pekerjaan Bekisting Sloof 0.28 m2


= 0.2 x 0.2 x 14 =
= 5.6 M2
= 0.28 m3
Kolom/Balok
Papan Kayu Begisting 0.04 x 3.84 = 0.15 M3 5,501,200 844,984
Begisting Beton Kolom 20x20 cm Pekerjaan Bekisting Kolom 0.48 m2 Paku 0.4 x 3.84 = 1.54 kg 20,000 30,720
= 0.2 x 0.2 x 1.5 = 8 Minyak bekisting 0 x 3.84 = - Ltr 15,000 -
= 9.6 M2 Balok Kayu Kelas III 0.015 x 3.84 = 0.06 M3 5,501,200 316,869
= 0.48 m3 Triplek 122x244x9 mm 0.35 x 76.80 = 26.88 lembar 120,000 3,225,600
Bambu 2 x 3.84 = 7.68 btg 40,000 307,200
Begisting Ring Baalok 15x15 cm Pekerjaan Bekisting Kolom 3.36 m2
= 0.15 x 0.15 x 14 = 8 Pekerja 0.66 x 3.84 = 2.53 OH 110,700 280,558
= 67.2 M2 Tukang 0.33 x 3.84 = 1.27 OH 151,500 191,981
= 3.36 m3

Plat
Begisting Beton Plat Lantai 12 cm Pekerjaan Bekisting Plat 1.47 M2 Papan Kayu Begisting 0.04 x 1.47 = 0.06 M3 5,501,200 323,471
= 3.5 x 3.5 x 0.12 = 1 Paku 0.4 x 1.47 = 0.59 kg 20,000 11,760
= 12.25 M2 Minyak bekisting 0 x 1.47 = - Ltr 15,000 -
= 1.47 m3 Balok Kayu Kelas III 0.015 x 1.47 = 0.02 M3 5,501,200 121,301
Bekisting Beton Plat Penutup t = 8 cm Triplek 122x244x9 mm 0.35 x 24.50 = 8.58 lembar 120,000 1,029,000
= 3.5 x 3.5 x 0 = 1 Bambu 2 x 1.47 = 2.94 btg 40,000 117,600
= 12.25 M2 -
= 0 m3 Pekerja 0.66 x 1.47 = 0.97 OH 110,700 107,401
Tukang 0.33 x 1.47 = 0.49 OH 151,500 73,493
-

TOTAL V 7,080,080
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
VI PEKERJAAN PLESTERAN
Plesteran dinding 1pc:4ps 42.00 m2 Semen 0.156 x 42 = 6.53 Zak 60,000 391,910
dinding gudang kontrol Pasir pasangan 0.023 x 42 = 0.97 M3 207,500 200,445
= 0 + 0 x 2.5 = 2
= 0 m2 Pekerja 0.3 x 42 = 12.60 OH 110,700 1,394,820
dinding Bronkep Tukang 0.15 x 42 = 6.30 OH 151,500 954,450
= 3.5 + 3.5 x 1.5 = 2
= 42 m2

Plesteran lantai 1pc:3ps - m2 Semen 0.156 x - = - Zak 60,000 -


gudang kontrol Pasir pasangan 0.023 x - = - M3 207,500 -
= 0 x 3 x 1 = 1
= 0 m2 Pekerja 0.3 x - = - OH 110,700 -
lantai tower Tukang 0.15 x - = - OH 151,500 -
= 0 x 3 x 1 = 1
= 0 m2

Acian + Mill - m2 Semen 0.065 x 0 = - Zak 60,000 -


dinding gudang kontrol
= 0 + 0 x 2.5 = 2 Pekerja 0.2 x 0 = - OH 110,700 -
= 0 m2 Tukang 0.1 x 0 = - OH 151,500 -
dinding tower Beton
= 0 + 0 x 2 = 1
= 0 m2
TOTAL IV 2,941,625

VII PEKERJAAN KAYU dan KUNCI


a. Pek. Kusen Pintu Kayu Kls. II - m3 Balok Kayu Klas II 1.2 x 0 = - M3 4,312,400 -
= 0 x 0.14 x 0.06 = 1 Paku 1.25 x 0 = - kg 20,000 -
= 0 m3 Lem kayu 1 x 0 = - kg 41,000 -

Pekerja 6 x 0 = - OH 110,700 -
Tukang 18 x 0 = - OH 151,500 -

b. Pek. Daun Pintu Panil - m2 Papan Kayu Klas II 0.04 x 0 = - M3 4,312,400 -


= 0 x 0.9 x 2.1 = 1 Lem kayu 0.5 x 0 = - kg 41,000 -
= 0 m2 Pekerja 1 x 0 = - OH 110,700 -
Tukang 3 x 0 = - OH 151,500 -

c. Kunci Pintu - bh Kunci Pintu 1 x - = - M3 120,000 -

d. Engsel pintu - bh Engsel pintu 1 x - = - M3 92,000 -

TOTAL IV -

VIII PEKERJAAN PIPA DAN ASESIORIS


Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya
-
Menhol 70 x 70 cm = 1 1.00 Bh Manhole plat besi 70X70 cm = 1.00 bh 500,000 500,000
Pembuatan Logo Pamsimas dan Balai = 1 1.00 Ls Pembuatan Logo Pamsimas dan Balai = 1.00 bh 500,000 500,000

TOTAL II 1,000,000
Sketsa Kasar Perhitungan Volume Vol. Sat. ANALISA KEBUTUHAN Sat. Harga satuan Biaya

IX PENGERJAAN PENGECATAN Cat tembok 33.35 M2 Plamir Tembok 0.1 x 33.35 = 3.34 kg 47,000 156,745
Dinding ruangan Cat tembok 0.36 x 33.35 = 12.01 Kg 41,000 492,246
= 0 x x 0 = 8 Ampelas 0 x 33.35 = - m' 30,000 -
= 0 M2 Kape 0 x 33.35 = - Buah - -
Beton sloof 20/20 cm Kuas 3" 0 x 33.35 = - Buah 18,000 -
= 0.2 x 0.2 x 3.5 = 4
= 11.2 M2 Pekerja 0.02 x 33.35 = 0.67 OH 110,700 73,837
Beton Kolom 20x20 cm Tukang 0.063 x 33.35 = 2.10 OH 151,500 318,309
= 0.2 x 0.2 x 1.5 = 4
= 3.6 M2
Ring Balok 15/15 cm
= 0.15 0.15 x 3.5 = 4
= 6.3 M2
Beton Plat Penutup t = 8 cm
= 3.5 x 3.5 x 1 = 1
= 12.25 M2

Cat kayu - Meni Kayu 0.20 x - = - ltr 56,000 -


Pek. Kusen Pintu Kayu Kls. II Plamir kayu 0.15 x - = - ltr 40,000 -
= 0 x 0.14 + 0.06 = 0 Cat Kayu Mutu Sedang 0.17 x - = - ltr 62,000 -
= 0 m3 Kuas 1" - x - = - Bh 15,000 -
Minyak Cat biasa 0.03 x - = - ltr 40,000 -
Ampelas - x - = - Bh 30,000 -
Pekerja 0.07 x - = - OH 110,700 -
Tukang 0.01 x - = - OH 151,500 -
Pek. Daun Pintu Panil
= 0 x 0.9 = 1
= 0 m2

TOTAL IV 1,041,137
V ALAT PELINDUNG DIRI
Masker Kain 16.00 Bh Masker Kain 16.00 Bh 10,000 160,000
Sabun Cuci Tangan Cair 2.00 Btl Sabun Cuci Tangan Cair 2.00 Btl 50,000 100,000
Ember dan Keran - Bh Ember dan Keran - Bh 85,000 -

TOTAL V 260,000

GRAND TOTAL 35,600,447


DIBULATKAN 35,600,000
RENCANA ANGGARAN BIAYA

Nomor RAB : 0.2 Sub Pekerjaan/Kegiatan : Tower Air


Pekerjaan / Kegiatan : Sarana Air Minum Ukuran/Dimensi : 1 Unit

Volume Biaya (Rp)


Harga Satuan
URAIAN Kontribusi Masy. Satuan Kontribusi Masyarakat
Total APBDes BLM Total APBDes BLM
inCash inKind Rp inCash inKind
1 2=3+4+5 3 4 5 6 7 8 9=2x8 10=3x8 11=4x8 12=5x8 13=6x8
1 BAHAN
- Tanah Urug - - - - - m3 67,300.00 - - - - -
- Pasir urug - - - - - m3 188,900.00 - - - - -
- Batu Kali Alam 4.22 - 2.22 - 2.00 m3 210,700.00 889,997 - 468,597 - 421,400
- Pasir pasangan 2.88 - 2.88 - - m3 207,500.00 597,783 - 597,783 - -
- Pasir Cor 4.22 - 1.22 - 3.00 m3 214,800.00 905,443 - 261,043 - 644,400
- Bata merah - - - - - Bh 1,500.00 - - - - -
- Kerikil Pecah 3-5 cm - - - - - m3 428,300.00 - - - - -
- Batu Pecah 2-3 cm 5.92 - 1.92 - 4.00 m3 400,000.00 2,367,462 - 767,462 - 1,600,000
- Papan Kayu Begisting 0.23 - - - 0.23 m3 5,501,200.00 1,237,770 - - - 1,237,770
- Balok Kayu Klas II - - - - - m3 4,312,400.00 - - - - -
- Balok Kayu Kelas III 0.08 - 0.04 - 0.04 m3 5,501,200.00 438,171 - 238,171 - 200,000
- Papan Kayu Klas II - - - - - m3 4,312,400.00 - - - - -
- Bambu 10.62 - 10.62 - - Bh 40,000.00 424,800 - 424,800 - -
- PIPA Galpanis (GI Medium A) Ø 1,5" - - - - - m' 135,000.00 - - - - -
- PIPA Galpanis (GI Medium A) Ø 2" - - - - - m' 150,000.00 - - - - -
- PIPA Galpanis (GI Medium A) Ø 3" - - - - - m' 265,700.00 - - - - -
- Knee GI Ø 11/2 - - - - - Bh 35,000.00 - - - - -
- Knee GI Ø 3" - - - - - Bh 130,000.00 - - - - -
- Knee GI Ø 2" - - - - - Bh 55,000.00 - - - - -
- Shock Drat luar PVC Ø1.5" - - - - - Bh 25,000.00 - - - - -
- Shock Drat luar GI Ø3" - - - - - Bh 96,000.00 - - - - -
- Shock Drat luar GI Ø2" - - - - - Bh 56,000.00 - - - - -
- PIPA GI Medium B Ø 1,5" - - - - - m' 77,483.00 - - - - -
- PIPA GI Medium B Ø 1" - - - - - m' 49,150.00 - - - - -
- Gate Valve 3" - - - - - Bh 1,300,000.00 - - - - -
- Gate Valve 2" - - - - - Bh 750,000.00 - - - - -
- Gate Valve 1,5" - - - - - Bh 550,000.00 - - - - -
- Flank Socket PVC 3" - - - - - Bh 100,000.00 - - - - -
- Flank last 3" - - - - - Bh 100,000.00 - - - - -
- Karet pak 3" - - - - - Bh 25,000.00 - - - - -
- Flank Socket PVC 2" - - - - - Bh 60,000.00 - - - - -
- Flank last 2" - - - - - Bh 80,000.00 - - - - -
- Karet pak 2" - - - - - Bh 20,000.00 - - - - -
- Flank Socket PVC 1,5" - - - - - Bh 50,000.00 - - - - -
- Flank last 1,5" - - - - - Bh 60,000.00 - - - - -
- Karet pak 1,5" - - - - - Bh 15,000.00 - - - - -
- Kunci Pintu - - - - - Bh 120,000.00 - - - - -
- Engsel pintu - - - - - Bh 92,000.00 - - - - -
- Paku 2.21 - - - 2.21 kg 20,000.00 44,160 - - - 44,160
- Lem kayu - - - - - kg 41,000.00 - - - - -
- Semen 66.73 - 6.73 - 60.00 zak 60,000.00 4,004,042 - 404,042 - 3,600,000
- Besi Beton Polos 542.71 - 43.95 - 498.75 kg 20,050.00 10,881,296 - 881,296 - 10,000,000
- Kawat Ikat Beton 7.75 - 1.75 - 6.00 kg 35,000.00 271,354 - 61,354 - 210,000
- Minyak bekisting - - - - - Ltr 15,000.00 - - - - -
- Triplek 122x244x9 mm 35.46 - 5.45 - 30.00 Lbr 120,000.00 4,254,600 - 654,600 - 3,600,000
- Meni Kayu - - - - - ltr 56,000.00 - - - - -
- Plamir kayu - - - - - ltr 40,000.00 - - - - -
- Cat Kayu Mutu Sedang - - - - - ltr 62,000.00 - - - - -
- Kuas 1" - - - - - Bh 15,000.00 - - - - -
- Minyak Cat biasa - - - - - ltr 40,000.00 - - - - -
- Ampelas - - - - - m 30,000.00 - - - - -
- Air 1,669.48 - 1,669.48 - - ltr 100.00 166,948 - 166,948 - -
- Plamir Tembok 3.34 - 1.34 - 2.00 kg 47,000.00 156,745 - 62,745 - 94,000
- Cat Tembok Mutu Standar/Sedang 12.01 - 2.01 - 10.00 Kg 41,000.00 492,246 - 82,246 - 410,000
- Manhole plat besi 70X70 cm 1.00 - - - 1.00 Bh 500,000.00 500,000 - - - 500,000
- Pembuatan Logo Pamsimas dan Balai 1.00 - - - 1.00 Ls 500,000.00 500,000 - - - 500,000

Sub Total 1) 28,132,816 - 5,071,086 - 23,061,730


2 UPAH
- Pekerja 39.63 - 39.63 - - OH 110,700 4,386,765 - 4,386,765 - -
- Tukang 18.62 - 18.62 - - OH 151,500 2,820,866 - 2,820,866 - -

Sub Total 2) 7,207,631 - 7,207,631 - -


3 ALAT PELINDUNG DIRI
- Masker Kain 16.00 - - 16.00 Bh 10,000.00 160,000 - - - 160,000
- Sabun Cuci Tangan Cair 2.00 - - 2.00 Bh 50,000.00 100,000 - - - 100,000
- Ember dan Keran - - - - Bh 85,000.00 - - - - -

Sub Total 3) 260,000 - - - 260,000


JUMLAH TOTAL 35,600,447 - 12,278,717 - 23,061,730
JUMLAH TOTAL DIBULATKAN 35,600,000 - 12,279,000 - 23,061,000
RINCIAN BIAYA PENGAMBILAN DAN PEMERIKSAAN SAMPLE AIR
Pra Konstruksi (1 sample)
Uraian Volume Satuan Harga Satuan Jumlah Harga
I BIAYA PEMERIKSAAN
1 Retribusi :
Uji Laboratorium
- Bakteriologi 1 Sapel 40,000.00 40,000.00
- Kimia dan Fisika 1 Sapel 70,000.00 70,000.00
2 Bahan habis pakai (kapas, alkohol,
spritus, bahan desifektan, kertas
coklat, masker, sarung tangan) 1 Paket 25,000.00 25,000.00
Jumlah I 135,000.00
II BIAYA PENGAMBILAN SAMPEL
1 Transportasi pengambilan sampel 2
org x Rp. 50.000 x 1 hari 2 HO 50,000.00 100,000.00
2 konsumsi 2 org x Rp. 50.000 x 1 hari 2 HO 50,000.00 100,000.00
Jumlah II 200,000.00
Total I + II 335,000.00

RINCIAN BIAYA PENGAMBILAN DAN PEMERIKSAAN SAMPLE AIR


Pasca Konstruksi (3 sample)
Uraian Volume Satuan Harga Satuan Jumlah Harga
I BIAYA PEMERIKSAAN
1 Retribusi :
Uji Laboratorium
- Bakteriologi 2 Sapel 40,000.00 80,000.00
- Kimia dan Fisika 0 Sapel 70,000.00 -
2 Bahan habis pakai (kapas, alkohol,
spritus, bahan desifektan, kertas
coklat, masker, sarung tangan) 1 Paket 25,000.00 25,000.00
Jumlah I 105,000.00
II BIAYA PENGAMBILAN SAMPEL
1 Transportasi pengambilan sampel 2
org x Rp. 50.000 x 1 hari 2 HO 50,000.00 100,000.00
2 konsumsi 2 org x Rp. 50.000 x 1 hari 2 HO 50,000.00 100,000.00
Jumlah II 200,000.00
Total I + II 305,000.00
REKAP
Propinsi :
Kabupaten :
Kecamatan :
Desa :

No Uraian Satuan Volume Harga Satuan Total Biaya

I Pembangunan Sarana Air Minum


1.1 PEK. SUMUR GALI 15 m Paket 1.00 8,803,493 8,803,493
2.1 PEK. DAN PENGADAAN POMPA & INSTALASI PANEL Unit 1.00 57,725,000 57,725,000
3.1 PEK. TOWER DAN RUMAH PANEL Unit 1.00 55,455,000 55,455,000
4.1 PEK. JARINGAN PERPIPAAN meter 1,500.00 55,611,000 55,611,000
Sub Total I 177,594,493
III Pembangunan Sarana Sanitasi
3.1 PEK. JAMBAN SEHAT SISWA - X 1 UNIT Unit - - #REF!
3.2 PEK. SARANA CUCI TANGAN (CTPS)SEKOLAH Unit 2.00 #REF! #REF!
3.3 PEK. SARANA CUCI TANGAN (CTPS) MASYARAKAT Unit 1.00 #REF! #REF!
Sub Total III #REF!
IV Peningkatan PHBS
4.1 PHBS & CLTS MASYARAKAT Paket 1.00 1,040,000 #REF!
4.2 PHBS & CLTS SEKOLAH Paket 1.00 320,000 #REF!
4.3 MEDIA PROMOSI KESEHATAN Paket 1.00 375,000 #REF!
4.4 PENAGAMBILAN SAMPLE AIR
- Pra Konstruksi (1 sample) Ls 1.00 335,000 #REF!
- Pasca Konstruksi (3 sample) Ls 1.00 305,000 #REF!

Sub Total IV #REF!


V Operasional KKM
5.1 ATK, INFORMASI, KONSUMSI, TRANSPORTASI, LAPORAN DAN Paket 1 10,000,000 #REF!
DOKUMEN
Sub Total V #REF!
Total Pembiayaan RKM Err:522
RENCANA ANGGARAN BIAYA

Nomor RAB : -
Pekerjaan / Kegiatan : Sumur gali 15 m

Volume
Harga Satuan
URAIAN Satuan TOTAL
Total
Rp
1 2=3+4+5 7 8 13=6x8

1 BAHAN

1 Buis beton Ø 80cm Panjang 0,5 m 30 Bh 250,000 7,500,000

Sub Total 1) 7,500,000

2 UPAH

1 Upah Pekerja Galian Sumur 15 m' 86,900 1,303,493

Sub Total 2) 1,303,493


JUMLAH TOTAL 8,803,493

JUMLAH TOTAL DIBULATKAN 8,803,000


REKAPITULASI
RENCANA ANGGARAN BIAYA
(RAB)

PEKERJAAN :
LOKASI :
TAHUN ANGGARAN :

NO JENIS PEKERJAAN JUMLAH

1 2 3

I. PEK. SUMUR GALI 15 m Rp. 8,803,492.50


II. PEK. DAN PENGADAAN POMPA & INSTALASI PANEL Rp. 57,725,000.00
III. PEK. TOWER DAN RUMAH PANEL Rp. 55,455,000.00
IV. PEK. JARINGAN PERPIPAAN Rp. 55,611,000.00

JUMLAH BIAYA KONSTRUKSI Rp. 177,594,492.50


PEMBULATAN Rp. 177,594,000.00

TERBILANG : SERATUS TUJUH PULUH TUJUH JUTA LIMA RATUS SEMBILAN PULUH EMPAT RIBU RUPIAH
BAB 4. REKAPITULASI KEGIATAN DAN BIAYA RKM

Masyarakat
`Uraian Satuan Volume Harga Satuan Total Biaya In Cash (4%) Inkind (16 %) APBDes (10 %) APBD 70%
Peningkatan PHBS
1.1 PHBS&CLTS Masyarakat Paket 1 1,040,000 1,040,000 #REF! #REF! #REF!
1.2 PHBS&CLTS Sekolah Paket 1 320,000 320,000 #REF! #REF! 320,000
1.3 Pelatihan STBM Ting. Desa Paket 1 #REF! #REF! #REF! #REF! #REF!
1.4 Media Promkes Paket 1 375,000 375,000 #REF! #REF! -
1.5 Pengambilan sample air kali 2 - - #REF! #REF! 400000

#REF! #REF! #REF! - #REF!


Peningkatan Kapasitas KKM,Satlak
2.1 Pelatihan KKM dan SATLAK Paket 1 #REF! #REF! #REF! #REF! #REF!
2.2 Pelatihan BPSPAMS Paket 1 #REF! #REF! #REF! #REF! #REF!
Sub Total I #REF! #REF! - - #REF!
Pelayanan Air Minum
3.1 Pemb Sumur BOR Unit 1 #REF! #REF! #REF! #REF! #REF!
3.2 Pembangunan Tower Unit 1 55,455,000 55,455,000 #REF! #REF! #REF! #REF!
3.3 Pembangunan Hidran Umur Unit 1 0 0 #REF! #REF! #REF! #REF!
3.4 Instalasi Perpipaan Paket 1 55,611,000 55,611,000 #REF! #REF! #REF! #REF!
Sub Total III #REF! #REF! #REF! #REF! #REF!
Pembangunan Sarana Sanitasi
4.1 Sarana WC Sekolah Unit 1 0 0 #REF! #REF! #REF! #REF!
4.2 CTPS Unit 3 #REF! #REF! #REF! #REF! #REF! #REF!
-
Sub Total IV #REF! #REF! #REF! #REF! #REF!
Operasional KKM
5.1 Operasional KKM unit 1 10,000,000 10,000,000 #REF! #REF! #REF! -
Sub Total V 10,000,000 10,000,000 #REF! -
Total Pembiayaan RKM #REF! #REF! #REF! #REF! #REF!
RINGKASAN KEGIATAN DAN BIAYA RKM
Propinsi : Nusa Tenggara Barat Proyek : Pamsimas III
Kabupaten : Lombok Timur Tahun : 2018/2019
Kecamatan : SAKRA TIMUR KKM :
Desa : SURABAYA UTARA

No Uraian Satuan Volume Harga Satuan BLM APBDes Masyarakat Total Biaya
70% 10% In Cash (4%) In Kind(16%)
I Kegiatan Pelatihan Masyarakat
1.1 PELATIHAN KKM DAN SATLAK Kegiatan 1.00 2,000,000 - 2,000,000 2,000,000
1.2 PELATIHAN STBM Paket 1.00 1,300,000 1,300,000 1,300,000
1.3 PELATIHAN DISABELITAS Paket 1.00 1,250,000 1,250,000 1,250,000
1.4 PELATIHAN KKM DAN BPSPAM Kegiatan 1.00 1,250,000 1,250,000 1,250,000
Sub Total I 3,800,000 - 2,000,000 - 5,800,000
II Pembangunan Sarana Air Minum
2.1 PEK. SUMUR BOR Paket 1.00 - - - - - -
2.2 PEK. DAN PENGADAAN INSTALASI LISTRIK Unit 1.00 57,725,000 #REF! - #REF! #REF! #REF!
2.3 PEK. DAN PENGADAAN POMPA & INSTALASI Unit 1.00 #REF! #REF! - #REF! #REF! #REF!
2.4 PEK. TOWER AIR Unit 1.00 55,455,000 #REF! #REF! #REF! #REF! #REF!
2.5 PEK. JARINGAN PERPIPAAN meter #REF! #REF! 55,611,000 #REF! #REF! #REF! #REF!
Sub Total II #REF! #REF! #REF! #REF! #REF!
III Pembangunan Sarana Sanitasi
3.1 PEK. JAMBAN SEHAT SISWA - X 1 UNIT Unit 1.00 - - - - - -
3.2 PEK. SARANA CUCI TANGAN (CTPS) - X 3 UNIT Unit 3.00 #REF! #REF! #REF! #REF! #REF! #REF!
Sub Total III #REF! #REF! #REF! #REF! #REF!
IV Peningkatan PHBS
4.1 PHBS & CLTS MASYARAKAT Paket 1.00 1,500,000 1,500,000 - 1,500,000
4.2 PHBS & CLTS SEKOLAH Paket 1.00 750,000 750,000 750,000
4.3 MEDIA PROMOSI KESEHATAN Paket 1.00 1,000,000 1,000,000 1,000,000
4.4 PENAGAMBILAN SAMPLE AIR
- Pra Konstruksi (1 sample) Ls - - - -
- Pasca Konstruksi (3 sample) Ls 1.00 305,000 305,000 305,000

Sub Total IV 3,555,000 - - - 3,555,000


V Operasional KKM
5.1 ATK, INFORMASI, KONSUMSI, TRANSPORTASI, LAPORAN DAN DOKUMEN Paket 1 11,000,000 - - 11,000,000 - 11,000,000
Sub Total V - - 11,000,000 - 11,000,000
Total Pembiayaan RKM #REF! #REF! #REF! #REF! #REF!

Menyetujui/Mengetahui, Diverifikasi Oleh : Mengetahui, Dibuat Oleh


Koordinator Kabupaten Fasilitator Senior Fasilitator Masy. ( WSS) Kepala Desa Koordinator KKM Ketua Satlak

(SYAMSUL HADY M, ST
) (HAMDANI) (ARMAWAN, ST) (AHMAD RUSDAN) (ABDUL MUHID) (MASNULLAH)
REKAPITULASI BIAYA UPAH DAN BAHAN

Program : PAMSIMAS
Provinsi : NTB
Kabupaten : Lombok Timur
Kecamatan : Rarang Selatan
Desa : Terara

No. URAIAN VOL. SATUAN Harga Satuan Total Harga


IN-CASH IN - KIND
A KEGIATAN FISIK (SAM & SAN)
1 Material Pipa dan accessories
Pipa S 12,5 SNI Ø 2,5" - - - - - Meter 44,000 -
Pipa S 12,5 SNI Ø 2" - - - - - Meter 25,666 -
Pipa S 12,5 SNI Ø 1,5" - - - - - Meter 25,000 -
Pipa S 10 SNIØ 1" - - - - - Meter 15,000 -
Tee PVC Ø 2.5" - - - - - Buah 120,000 -
Tee PVC Ø 2" - - - - - Buah 85,000 -
Long Bend PVC 90 Ø 2" - - - - - Buah 100,000 -
Stop Kran Ø 2.5" - - - - - Buah 950,000 -
End cop (Dop PVC) Ø 2" 1.00 - - - 1.00 Buah 50,000 50,000
End cop (Dop PVC) Ø 1.5 - - - - - Buah 35,000 -
End cop (Dop PVC) Ø 1" - - - - - Buah 25,000 -
Reducer Tee All Socket PVC Ø 2.5" x 1" - - - - - Buah 140,000 -
Reducer Tee All Socket PVC Ø 2.5" x 2" - - - - - Buah 140,000 -
Reducer Socket PVC Ø 2.5" x 2" - - - - - Buah 115,000 -
PIPA Galpanis (GI Medium A) Ø 1,5" - - #REF! #REF! #REF! Meter 135,000 -
PIPA Galpanis (GI Medium A) Ø 2" - - #REF! #REF! #REF! Meter 150,000 -
PIPA GI Medium B Ø 1,5" - - #REF! #REF! #REF! Meter 77,483 -
PIPA GI Medium B Ø 1" - - #REF! #REF! #REF! Meter 49,150 -
Knee GI Ø 2.5" - - - - - Buah -
Pipa PVC tidak bertekanan (Kwalitas C) Ø 3" - - - - - #N/A #N/A #N/A
Pipa PVC tidak bertekanan (Kwalitas C) Ø 2" - - - - - #N/A #N/A #N/A
Lem Pipa Kualitas baik - - - - - kaleng 55,000 -
-
-
-
-
-
-
-
No. URAIAN VOL. SATUAN Harga Satuan Total Harga
IN-CASH IN - KIND
-
-
-
-

2
Semen 80.64 - #REF! #REF! #REF! Zak 60,000 4,838,700
Paku - - - - - kg 20,000 -
Besi Beton Polos 791.36 - #REF! #REF! #REF! Kg 20,050 15,866,694
Kawat Ikat Beton 11.31 - #REF! #REF! #REF! Kg 35,000 395,678
Minyak bekisting - - #REF! #REF! #REF! liter 15,000 -
Plamir Tembok - - - - - kg 47,000 -
Plamir Kayu - - #REF! #REF! #REF! kg 40,000 -
Meni Kayu - - #REF! #REF! #REF! kg 56,000 -
Cat Tembok Mutu Standar/Sedang - - - - - kg 41,000 -
Mil - - - - - kg 1,000 -
Minyak Cat biasa - - - - - Liter 40,000 -
Cat Kayu Mutu Sedang - - - - - kg 62,000 -
Lem kayu - - - - - Kg 41,000 -
Triplek 122x244x6 mm - - - - - #N/A #N/A #N/A
Triplek 122x244x9 mm 31.94 - #REF! #REF! #REF! lembar 120,000 3,832,500
3 Keramik Lantai KM 20x20 Kwalitas Sedang - - - - - M2 69,000 -
Keramik Dinding KM 20x25 Kwalitas Sedang - - - - - #N/A #N/A #N/A
Seng gelombang BJLS 25 - - - - - lembar 80,000 -
Kunci Pintu Mutu Sedang - - - - - Buah 82,000 -
Engsel Pintu 3 Lubang kwalitas biasa - - - - - Pasang 36,000 -
Closet Duduk Lengkap Kwalitas Sedang - - - - - Set 2,000,000 -
Pilox - - - - - kaleng 35,000 -
Pipa Stailisetill Ø 1" - - - - - Meter 65,000 -
Tee PVC Ø 1/2" - - - - - Buah 30,000 -
Kran Ø 1/2" - - - - - Buah 20,000 -
Stop Kran Ø 1/2" - - - - - Buah 79,000 -
Saringan Air Staenlist - - - - - Buah 45,000 -
Shock Drat Dalam PVC Ø1/2" - - - - - Buah 15,000 -
Pipa PVC tidak bertekanan (Kwalitas C) Ø 3" - - - - - #N/A #N/A #N/A
Pipa PVC bertekanan (AW) Ø 1/2" - - - - - Meter 7,000 -
3 Bend PVC 90 (Knee) Ø 1/2" - - Buah 70,000 -
Box Meter - - - - - Set 100,000 -
Water Meter 1/2" - - - - - Set 150,000 -
No. URAIAN VOL. SATUAN Harga Satuan Total Harga
IN-CASH IN - KIND
Sealtipe - - - - - BH 10,000 -
Ember kapasitas 25 liter - - - - - Buah 75,000 -
Sikat Closet - - - - - Unit 15,000 -
Manhole plat besi 70X70 cm - - - - - Buah 500,000 -

Pasir pasangan 4.32 - #REF! #REF! #REF! M3 207,500 896,151


Pasir Cor 5.08 - #REF! #REF! #REF! M3 214,800 1,092,097
Bata merah 1,632.40 - #REF! #REF! #REF! Buah 1,500 2,448,600
Batu Pecah 3-5 cm - - - - - M3 428,300 -
Kerikil alam 2-3 cm - - - - - M3 -
Papan Kayu Begisting 0.23 - #REF! #REF! #REF! m3 5,501,200 1,266,926
4 Balok Kayu Klas II - - #REF! #REF! #REF! m3 4,312,400 -
Balok Kayu Klas III - - - - - #N/A #N/A #N/A
Papan Kayu Klas II - - #REF! #REF! #REF! m3 4,312,400 -
Dolken diamater 8-10cm P=4m - - - - - Batang 26,200 -
Bambu 10.84 - #REF! #REF! #REF! Batang 40,000 433,600
Tanah Urug - - #REF! #REF! #REF! M3 67,300 -
Pasir urug 1.12 - #REF! #REF! #REF! M3 188,900 211,266
Batu Kali Alam 4.32 - #REF! #REF! #REF! M3 210,700 910,224
Air - - - - - liter 100 -
-
-

Pekerja 111.85 #REF! #REF! #REF! #REF! OH 110,700 12,381,331


Tukang 26.85 #REF! #REF! #REF! #REF! OH 151,500 4,068,126

Penyambungan Daya 3500 VA - - - - - #N/A #N/A


Materai - - - - - #N/A #N/A
Uang Jaminan Langganan untuk 3 Phase - - - - - #N/A #N/A
Token Perdana - - - - - #N/A #N/A
Sertifikat Laik Operasi 3500 VA - - - - - #N/A #N/A
Kabel Twisted - - - - - #N/A #N/A
Kabel WLC NYY-HY 3x2.5mm - - - - - #N/A #N/A
Saklar Seri Outbow - - - - - #N/A #N/A
Stop Kontak Outbow - - - - - #N/A #N/A
No. URAIAN VOL. SATUAN Harga Satuan Total Harga
IN-CASH IN - KIND
Fitting Gantung - - - - - #N/A #N/A
Lampu Essential 8 watt - - - - - #N/A #N/A
Isolasi - - - - - #N/A #N/A
Pipa GI 1.25" - - - - - #N/A #N/A
Pompa Submersible Head 60 m (Outlet 1,25" & Deb - - - - - #N/A #N/A
Panel Kontrol Doubel WLC 1.00 - - - 1.00 3,500,000.00 3,500,000
Kabel Elektroda 3x2.5mm 50.00 - - - 50.00 20,000.00 1,000,000
Watermoor GI 1.25" - - - - - #N/A #N/A
Check Valve 1.25" - - - - - #N/A #N/A
Sock drat luar PVC 1.25" - - - - - #N/A #N/A
Knee GI 1.25" - - - - - #N/A #N/A
Ball Valve - - - - - #N/A #N/A
Stabilisher - - - - - #N/A #N/A
Kawat seling lapis pelastik - - - - - #N/A #N/A
Pemasangan Instalasi listrik - - - - - #N/A #N/A
Pemasangan Instalasi Pompa 1.00 - - - 1.00 2,000,000.00 2,000,000
-
Bahan bakar minyak liter 5,150.00
Pelumas mesin Liter 58,500.00
Pelumas gardan Liter 58,500.00
Pelumas transmisi Liter 58,500.00
Air liter 100.00
Bentonit Zak 250,000.00
Oli Hydrolis Liter 35,875.00
Gemuk Liter 62,500.00
Kertas Logging Set 250,000.00
Tinta & Pen Logging Unit 75,000.00
Baterai dan Kabel Unit 400,000.00
Pipa PVC bertekanan (AW) Ø 6" Meter 165,000.00
End cop (Dop PVC) Ø 6" Buah 156,000.00
Kerikil/koral 0.5-1 cm M3 -
Semen Zak 60,000.00
Batu Pecah 1-2 cm M3 445,800.00
Pasir Cor M3 214,800.00
Bata merah Buah 1,500.00
Pasir pasangan M3 207,500.00
Air jetting test Titik 3,136,484.74
Water jetting Titik 1,031,505.00
Mekanik OH -
No. URAIAN VOL. SATUAN Harga Satuan Total Harga
IN-CASH IN - KIND
Operator Logging OH -
Pembantu operator OH -
Operator Alat bor OH -
Teknisi Pumping test OH -
DANA MASYARAKAT APBDes BLM
IN-CASH (Rp.) IN - KIND (Rp.)

- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - 50,000.00
- - - -
- - - -
- - - -
- - - -
- - - -
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- - - -
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
- - - -
DANA MASYARAKAT APBDes BLM
IN-CASH (Rp.) IN - KIND (Rp.)

- #REF! #REF! #REF!


- - - -
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- - - -
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- - - -
- - - -
- - - -
- - - -
- - - -
#N/A #N/A #N/A #N/A
- #REF! #REF! #REF!
- - - -
#N/A #N/A #N/A #N/A
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
#N/A #N/A #N/A #N/A
- - - -
- - - -
- - - -
- - - -
DANA MASYARAKAT APBDes BLM
IN-CASH (Rp.) IN - KIND (Rp.)
- - - -
- - - -
- - - -
- - - -

- #REF! #REF! #REF!


- #REF! #REF! #REF!
- #REF! #REF! #REF!
- - - -
- - - -
- #REF! #REF! #REF!
- #REF! #REF! #REF!
#N/A #N/A #N/A #N/A
- #REF! #REF! #REF!
- - - -
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- #REF! #REF! #REF!
- - - -

#REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF!

- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
- - - #N/A
DANA MASYARAKAT APBDes BLM
IN-CASH (Rp.) IN - KIND (Rp.)
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
- - - 3,500,000.00
- - - 1,000,000.00
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
#N/A #N/A #N/A #N/A
- - - 2,000,000.00
TIME SCHEDULE
Desa -
Kecamatan -
Kabupaten -
Propinsi -

BULAN & MINGGU KE :


NO URAIAN PEKERJAAN BIAYA BOBOT Bulan 1 Bulan 2 KET.
(Rp.) (%)
1 2 3 4 5 6 7 8
100%
I PEK. SUMUR GALI 15 m 8,803,493 4.96 0.30 0.62 0.62 0.94 0.94 0.94 0.40 0.20

AN PENGADAAN
II. POMPA & INSTALASI PANEL 57,725,000 32.50 1.50 3.00 6.24 5.62 6.01 4.06 4.06 2.00

III. PEK. TOWER DAN RUMAH PANEL 55,455,000 31.23 1.01 3.50 5.00 5.30 6.00 6.00 3.90 0.51

IV. PEK. JARINGAN PERPIPAAN 55,611,000 31.31 2.00 3.50 5.00 7.09 5.00 4.00 3.91 0.81

JUMLAH BOBOT 177,594,493 100.00 4.81 10.62 16.86 18.95 17.96 15.01 12.28 3.52
TOTAL BOBOT RENCANA 4.81 15.43 32.29 51.24 69.20 84.20 96.48 100.00
REALISASI PROGRES
DEVIASI PROGRES
TIME SCHEDULE PROGRAM PAMSIMAS III
Desa : Batu Putik
Kecamatan : Keruak Jenis Kegiatan : Pembangunan Sarana Air Bersih & Sanitasi
Kabupaten : Lombok Timur Proyek : PAMSIMAS III 2020
Propinsi : NTB KKM :

BULAN & MINGGU KE :


NO URAIAN PEKERJAAN BIAYA BOBOT Bulan 1 Bulan 2 Bulan 3 Bulan 4 KET.
(Rp.) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

I KEGIATAN PELATIHAN MASYARAKAT


100%
1.1 PELATIHAN KKM DAN SATLAK #REF! #REF! #REF!
1.2 PELATIHAN STBM #REF! #REF! #REF!
1.3 PELATIHAN DISABELITAS #REF! #REF! #REF!
1.4 PELATIHAN KKM DAN BPSPAM #REF! #REF! #REF!

KEGIATAN
II.SARANA AIR MINUM
2.1 PEK. SUMUR GALI 15 m 8,803,493 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2.2 PEK. DAN PENGADAAN POMPA & INSTALASI PANEL 57,725,000 #REF! #REF! #REF!
2.3 #REF! #REF! #REF! #REF!
2.4 PEK. TOWER DAN RUMAH PANEL 55,455,000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2.5 PEK. JARINGAN PERPIPAAN 55,611,000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

III. KEGIATAN SARANA SANITASI


3.1 PEK. JAMBAN SEHAT SISWA - X 1 UNIT - #REF!
3.2 PEK. SARANA CUCI TANGAN (CTPS)SEKOLAH #REF! #REF! #REF! #REF! #REF!
3.3 PEK. SARANA CUCI TANGAN (CTPS) MASYARAKAT #REF! #REF! #REF!

IV. KEGIATAN PENINGKATAN PHBS


4.1 PHBS & CLTS MASYARAKAT 1,040,000 #REF! #REF!
4.2 PHBS & CLTS SEKOLAH 320,000 #REF! #REF!
4.3 MEDIA PROMOSI KESEHATAN 375,000 #REF! #REF!
4.4 PENAGAMBILAN SAMPLE AIR 305,000 #REF! #REF!

V. BIAYA OPERASIONAL KKM & SATLAK


5.1 ATK, INFORMASI, KONSUMSI, TRANSPORTASI, LAPORAN DAN 10,000,000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
DOKUMEN

JUMLAH BOBOT #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
TOTAL BOBOT RENCANA #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
REALISASI PROGRES
DEVIASI PROGRES
40 % APBD + In-cash TERMIN II 60 %
PROSES PENCAIRAN TERMIN
TOTAL TERMIN 40 % TOTAL TERMIN 100%
BAB 5. RENCANA PENGADAAN BARANG DAN JASA DI TINGKAT
MASYARAKAT
Daftar Rencana Pengadaan Barang dan Jasa
Metoda Waktu
No. Paket Pekerjaan Uraian/ Material Volume Satuan Harga Satuan Jumlah Biaya (Rp) Pengadaan Pelaksanaan
1 PAKET
Material Pipa PIPA Galpanis (GI Medium A) Ø 1,5" #REF! m' 135,000.00 #REF!
PIPA Galpanis (GI Medium A) Ø 2" #REF! m' 150,000.00 #REF!
PIPA Galpanis (GI Medium A) Ø 3" #REF! m' 265,700.00 #REF!
Knee GI Ø 11/2 #REF! Bh 35,000.00 #REF!
Knee GI Ø 3" #REF! Bh 130,000.00 #REF!
Knee GI Ø 2" #REF! Bh 55,000.00 #REF!
Shock Drat luar PVC Ø1.5" #REF! Bh 25,000.00 #REF!
Shock Drat luar GI Ø3" #REF! Bh 96,000.00 #REF!
Shock Drat luar GI Ø2" #REF! Bh 56,000.00 #REF!
Gate Valve 3" #REF! Bh 1,300,000.00 #REF!
Gate Valve 2" #REF! Bh 750,000.00 #REF!
Flank Socket PVC 3" #REF! Bh 100,000.00 #REF!
Flank last 3" #REF! Bh 100,000.00 #REF!
Karet pak 3" #REF! Bh 25,000.00 #REF!
Flank Socket PVC 2" #REF! Bh 60,000.00 #REF!
Flank last 2" #REF! Bh 80,000.00 #REF!
Karet pak 2" #REF! Bh 20,000.00 #REF!
Flank Socket PVC 1,5" #REF! Bh 50,000.00 #REF!
Flank last 1,5" #REF! Bh 60,000.00 #REF!
Karet pak 1,5" #REF! Bh 15,000.00 #REF!
Pipa HDPE Ø 2" #REF! Meter 62000 #REF!
Pipa HDPE Ø 1" #REF! Meter 19,000.00 #REF!
Coupler HDPE 2" #REF! Buah 317,200.00 #REF!
Stop Kran PVC Ø 2" #REF! Buah 222,000.00 #REF!
End cop (Dop PVC) Ø 2" #REF! Buah 50,000.00 #REF!
Lem Pipa Kualitas baik #REF! Buah 55,000.00 #REF!
Sealtipe #REF! Buah 10,000.00 #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
Setelah
#REF! #REF! #REF! #REF! #REF! Perbandingan Penandatangan
#REF! #REF! #REF! #REF! #REF! Harga
PKS
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
TOTAL #REF!
Metoda Waktu
No. Paket Pekerjaan Uraian/ Material Volume Satuan Harga Satuan Jumlah Biaya (Rp) Pengadaan Pelaksanaan
2 PAKET
Bahan Toko Semen Err:522 Zak 60000 Err:522
Paku Err:522 kg 20,000.00 Err:522
Besi Beton Polos Err:522 Kg 20,050.00 Err:522
Kawat Ikat Beton Err:522 Kg 35,000.00 Err:522
Minyak bekisting #REF! liter 15,000.00 #REF!
Plamir Tembok Err:522 kg 47,000.00 Err:522
Plamir Kayu Err:522 kg 40,000.00 Err:522
Meni Kayu Err:522 kg 56,000.00 Err:522
Cat Tembok Mutu Standar/Sedang Err:522 kg 41,000.00 Err:522
Mil - kg 1,000.00 -
Minyak Cat biasa Err:522 Liter 40,000.00 Err:522
Cat Kayu Mutu Sedang Err:522 kg 62,000.00 Err:522
Lem kayu #REF! Kg 41,000.00 #REF!
Triplek 122x244x6 mm - lembar 79,000.00 -
Triplek 122x244x9 mm #REF! lembar 120,000.00 #REF!
PIPA GI Medium B Ø 1,5" #REF! m' 77,483.00 #REF!
PIPA GI Medium B Ø 1" #REF! m' 49,150.00 #REF!
Keramik Lantai Kwalitas Sedang - M2 74,000.00 -
Keramik Dinding Kwalitas Sedang - M2 79,000.00 -
Spandek 3 mm lebar 70 cm - m 37,000.00 -
Setelah
Baut spandek - Kg 30,000.00 - Perbandingan Penandatangan
Kalsiplank ukuran (8X20) cm - m 15,000.00 - Harga PKS
Kunci Pintu Mutu Sedang Err:522 Buah 82,000.00 Err:522
Engsel Pintu 3 Lubang kwalitas biasa Err:522 Pasang 36,000.00 Err:522
Closet Duduk Lengkap Kwalitas Sedang - Set 2,000,000.00 -
Pilox Err:522 kaleng 35,000.00 Err:522
Pipa Stailisetill Ø 1 1/4" Err:522 Meter 80,000.00 Err:522
Tee PVC Ø 1/2" Err:522 Buah 30,000.00 Err:522
Kran Ø 1/2" Err:522 Buah 20,000.00 Err:522
Stop Kran Ø 1/2" - Buah 79,000.00 -
Saringan Air Staenlist - Buah 45,000.00 -
Shock Drat Dalam PVC Ø1/2" Err:522 Buah 15,000.00 Err:522
Pipa PVC tidak bertekanan (Kwalitas C) Ø - m 35,000.00 -
3"
Pipa PVC bertekanan (AW) Ø 1/2" Err:522 Meter 7,000.00 Err:522
Bend PVC 90 (Knee) Ø 1/2" Err:522 Buah 70,000.00 Err:522
Box Meter Err:522 Set 100,000.00 Err:522
Water Meter 1/2" Err:522 Set 150,000.00 Err:522
Sealtipe Err:522 BH 10,000.00 Err:522
Ember kapasitas 25 liter - Buah 75,000.00 -
Sikat Closet - Unit 15,000.00 -
Manhole plat besi 70X70 cm #REF! Buah 500,000.00 #REF!
TOTAL Err:522
3 PAKET
Material alam Pasir pasangan Err:522 m3 207,500.00 Err:522
Pasir Cor Err:522 m3 214,800.00 Err:522
Bata merah Err:522 Buah 1,500.00 Err:522
Kerikil Pecah 3-5 cm #REF! m3 428,300.00 #REF!
Kerikil alam 2-3 cm Err:522 m3 #REF! #REF!
Papan Kayu Begisting Err:522 m3 5,501,200.00 Err:522
Balok Kayu Klas II Err:522 m3 4,312,400.00 Err:522
Balok Kayu Klas III Err:522 m3 5,501,200.00 Err:522
Papan Kayu Klas II Err:522 m3 4,312,400.00 Err:522 Setelah
Perbandingan
Dolken diamater 8-10cm P=4m - Batang 26,200.00 - Harga Penandatangan
Bambu #REF! Batang 40,000.00 #REF! PKS
Tanah Urug Err:522 M3 67,300.00 Err:522
Pasir urug Err:522 M3 188,900.00 Err:522
Batu Kali Alam Err:522 M3 210,700.00 Err:522
Air Err:522 liter 100.00 Err:522
Buis Beton Ø 80 Cm panjang 0,50 m - Buah 250,000.00 -
Tutup buis Ø 80 cm - Buah 250,000.00 -
#REF! Err:522 #REF! #REF! #REF!
#REF! Err:522 #REF! #REF! #REF!
TOTAL Err:522
Metoda Waktu
No. Paket Pekerjaan Uraian/ Material Volume Satuan Harga Satuan Jumlah Biaya (Rp) Pengadaan Pelaksanaan
4 PAKET
Bahan bakar minyak - liter 5,150.00 -
Jasa pengurasan Sumur
Pelumas mesin - Liter 58,500.00 -
Pelumas gardan - Liter 58,500.00 -
Pelumas transmisi - Liter 58,500.00 -
Air - liter 100.00 -
Bentonit - Zak 250,000.00 -
Oli Hydrolis - Liter 35,875.00 -
Gemuk - Liter 62,500.00 -
Kertas Logging - Set 250,000.00 -
Tinta & Pen Logging - Unit 75,000.00 -
Baterai dan Kabel - Unit 400,000.00 -
Pipa PVC bertekanan (AW) Ø 6" - Meter 165,000.00 -
End cop (Dop PVC) Ø 6" - Buah 156,000.00 -
Kerikil/koral 0.5-1 cm - M3 - -
Semen - Zak 60,000.00 -
Batu Pecah 1-2 cm - M3 445,800.00 -
Pasir Cor - M3 214,800.00 - Setelah
Bata merah - Buah 1,500.00 - Penandatangan
PKS
Pasir pasangan - M3 207,500.00 -
Air jetting test - Titik 3,136,484.74 -
Water jetting - Titik 1,031,505.00 -
Buis Beton Ø 80 Cm panjang 0,50 m - Bh 250,000.00 -
Tutup buis Ø 80 cm - Bh 250,000.00 -
- - - - -
ALAT - - - -
Transportasi - Unit Truk 1,000,000.00 -
- - - - -
UPAH - - - -
Pekerja - OH 110,700.00 -
Tukang - OH 151,500.00 -
Mekanik - OH - -
Operator Logging - OH - -
Pembantu operator - OH - -
Operator Alat bor - OH - -
Teknisi Pumping test - OH - -

TOTAL - Pemilihan Lan


5 PAKET Panel Kontrol Solar Inverter #REF! Ls 16,725,000.00 #REF!
Solar Panel
Jasa Pemasangan Instalasi #REF! Bh 2,230,000.00 #REF!
Suport Panel dan Aksesoris #REF! Ls 11,150,000.00 #REF!
Kabel Power #REF! Ls 5,017,500.00 #REF!
Kabel WLC #REF! Ls 2,787,500.00 #REF!
- #REF! - - #REF!
#REF! #REF! #REF! #REF! #REF! Setelah
Perbandingan Penandatangan
#REF! #REF! #REF! #REF! #REF! Harga
#REF! #REF! #REF! #REF! #REF! PKS
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
Instalasi dan Setting Pump #REF! Ls 8,362,500.00 #REF!
TOTAL #REF!
6 Pompa Submersible Head 102 m (Outlet 1.00 Bh 26,500,000.00 26,500,000.00
1,5" & Debit 1,5 l/dt)
PAKET
Pompa dan Aksesoris Panel Kontrol Doubel WLC 1.00 Paket 3,500,000.00 3,500,000.00
Kabel WLC NYY-HY 3x0.75mm 750.00 m 10,000.00 7,500,000.00
Kabel Elektroda 3x2.5mm 50.00 m 20,000.00 1,000,000.00
Watermoor GI 1.5" 1.00 Bh 13,000.00 13,000.00
Check Valve 1.5" 1.00 Bh 50,000.00 50,000.00 Perbandingan Setelah
Pipa PVC bertekanan (AW) Ø 1.5" 4.00 m 16,000.00 64,000.00 Harga Penandatangan
PKS
Sock drat luar PVC 1.5" - Bh 25,000.00 -
Masker Kain 1.00 Bh #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
Pemasangan Instalasi Pompa 1.00 Ls 2,000,000.00 2,000,000.00
TOTAL #REF!
7 PAKET - #REF! Ls - #REF!
Setelah
Perbandingan Penandatangan
Pembuatan Logo Harga PKS
TOTAL #REF!
8 Panel Kontrol Solar Inverter #REF! Ls 16,725,000.00 #REF!
PAKET
Instalasi Listrik Solar Panel #REF! Bh 2,230,000.00 #REF!
Suport Panel dan Aksesoris #REF! Ls 11,150,000.00 #REF!
Kabel Power #REF! Ls 5,017,500.00 #REF!
Kabel WLC #REF! Ls 2,787,500.00 #REF!
- #REF! - - #REF! Perbandingan Setelah
#REF! #REF! #REF! #REF! #REF! Harga Penandatangan
PKS
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
Perbandingan Setelah
Harga Penandatangan
PKS
Metoda Waktu
No. Paket Pekerjaan Uraian/ Material Volume Satuan Harga Satuan Jumlah Biaya (Rp) Pengadaan Pelaksanaan
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF!
TOTAL #REF!
9 #REF! Err:522 #REF! #REF! #REF!
PAKET
APD #REF! #REF! #REF! #REF! #REF!
Setelah
#REF! Err:522 #REF! #REF! #REF! Perbandingan Penandatangan
Harga
#REF! #REF! #REF! #REF! #REF! PKS
#REF! Err:522 #REF! #REF! #REF!
- #REF! - - #REF!
TOTAL #REF!
10 PAKET Coupler HDPE 2" #REF! Buah 317,200.00 #REF!
APBDes Stop Kran PVC Ø 2" #REF! Buah 222,000.00 #REF!
End cop (Dop PVC) Ø 2" #REF! Buah 50,000.00 #REF!
Lem Pipa Kualitas baik #REF! Buah 55,000.00 #REF!
Sealtipe #REF! Buah 10,000.00 #REF!
TOTAL #REF!

Anda mungkin juga menyukai