DATA DASAR RENCANA DI LAPANGAN

PENGASPALAN JALAN
DESA ......................KECAMATAN..................
KABUPATEN BATANG

Lapis penetrasi (Lapen)


PANJANG JALAN = 500 M
LEBAR JALAN = 3 M
LEBAR BAHU JALAN = 0.5 M

Tabur Dua (Burda)


PANJANG JALAN = 0 M
LEBAR JALAN = 0 M
LEBAR BAHU JALAN = 0 M

Latasir (Sandsheet)
PANJANG JALAN = 500 M
LEBAR JALAN = 3 M
LEBAR BAHU JALAN = 0 M
DAFTAR HARGA SATUAN BAHAN DAN ALAT

NO MATERIAL SATUAN HARGA+PAJAK HARGA KETERANGAN

1 Batu Pecah 3-5 M3


Rp 207,500.00 Rp 183,600.00
2 Batu Pecah 2-3 M3 Rp 207,500.00 Rp 183,600.00
3 Batu Pecah 1-2 M3 Rp 207,500.00 Rp 183,600.00
4 Batu Pecah / Ciping 0,5 M3 Rp 207,500.00 Rp 183,600.00
5 Abu Batu M3 Rp 207,500.00 Rp 183,600.00
6 Aspal Penetrasi 60/70 155kg Drum Rp 1,700,000.00 Rp 1,504,400.00 Rp 10,967.74 /KG
7 Kayu Bakar M3 Rp 200,000.00 Rp 200,000.00
8 Pasir Beton M3 Rp 340,000.00 Rp 340,000.00

ALAT ADMINISTRASI

1 Prasasti 1 Rp 350,000.00
2 Papan Informasi 1 Rp 150,000.00
3 Papan Proyek 1 Rp 200,000.00

ALAT PROYEK

1 Keranjang Bh Rp 10,000.00
2 Benang Kg Rp 2,500.00
3 Selang timbangan M Rp 2,500.00
4 Wals Jam Rp 550,000.00
5 Mobilisasi Walls Ls Rp 1,500,000.00
6 Sprayer Jam Rp 38,500.00
7 Dump Truk Jam Rp 55,000.00
8 Paku kg Rp 15,000.00
9 Ompreng bh Rp 50,000.00
10 arco bh Rp 250,000.00

DAFTAR HARGA SATUAN UPAH TENAGA

NO TENAGA SATUAN UPAH KETERANGAN


1 Mandor Hari Rp 72,000.00
2 Operator Terlatih Hari Rp 132,000.00
3 Pekerja Hari Rp 54,000.00
4 Buruh Terlatih ( Tenaga Aspal ) Hari Rp 78,000.00
5 Sopir Hari Rp 72,000.00
6 Juru Godog Hari Rp 78,000.00
PERHITUNGAN VOLUME PEKERJAAN / TAKE OFF SHEET
DESA ........................

Perkerasan Jalan Aspal

No Uraian Panjang Lebar Tinggi Luas koef. Loss Volume

1 LUAS JALAN Lapen 500.00 3.00 1,500.00 1,500.00 m2


1,500.00 m2
Tabur dua - - - - m2
- m2
Latasir (sandsheet) 500.00 3.00 1,500.00 1,500.00 m2
1,500.00 m2

DI HITUNG OLEH

.........................
360
60
120.00
100
48.00

688
ANALISA PERHITUNGAN JALAN ASPAL
Desa :
5
Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.

K.618 Pekerjaan LAPEN 5 cm


Batu pecah 5-3 cm 0.0400 1,500.00 m2 60.00 m3 207,500 12,450,000 12,450,000
Batu pecah 2-3 cm 0.0221 1,500.00 m2 33.21 m3 207,500 6,891,075 6,891,075
Batu pecah 1-2 cm 0.0111 1,500.00 m2 16.61 m3 207,500 3,446,575 3,446,575
Batu pecah 0,5 cm 0.0051 1,500.00 m2 7.64 m3 207,500 1,585,300 1,585,300
Abu batu 0.0025 1,500.00 m2 3.75 m3 207,500 778,125 778,125
Aspal 4.0000 1,500.00 m2 6,000.00 kg 10,968 65,806,452 65,806,452
Kayu Bakar 0.0100 1,500.00 m2 15.00 M3 200,000 3,000,000 3,000,000
Operator Terlatih 0.0114 1,500.00 m2 17.14 HOK 132,000 2,262,480 2,262,480
Juru Godok 0.0057 1,500.00 m2 8.60 HOK 78,000 670,800 670,800
Buruh terlatih 0.0114 1,500.00 m2 17.14 HOK 78,000 1,336,920 1,336,920
Buruh tak terlatih 0.0707 1,500.00 m2 106.07 HOK 54,000 5,727,780 5,727,780
Mesin Gilas 3 roda 6T 0.0286 1,500.00 m2 43.00 jam 550,000 23,650,000 23,650,000
127,605,507
K.615 Pekerjaan Burtu
Batu pecah 1-2 cm 0.006666667 - m2 - m3 207,500 - -
Batu pecah 0,5 cm 0.006666667 - m2 - m3 207,500 - -
Abu batu 0.006666667 - m2 - m3 207,500 - -
Aspal 2.100000 - m2 - kg 10,968 - -
Kayu Bakar 0.0100 - m2 - M3 200,000 - -
Operator Terlatih 0.0133 - m2 - HOK 132,000 - -
Juru Godok 0.0089 - m2 - HOK 78,000 - -
Buruh terlatih 0.0089 - m2 - HOK 78,000 - -
Buruh tak terlatih 0.0444 - m2 - HOK 54,000 - -
Mesin Gilas 3 roda 6T 0.0222 - m2 - jam 550,000 - -

K.612 Pekerjaan Buras


Abu batu 0.017916667 m2 - m3 207,500 - -
Aspal 1.21 m2 - kg 10,968 - -
Kayu Bakar 0.0100 m2 - M3 200,000 - -
Operator Terlatih 0.0067 m2 - HOK 132,000 - -
Juru Godok 0.0067 m2 - HOK 78,000 - -
Buruh terlatih 0.0067 m2 - HOK 78,000 - -
Buruh tak terlatih 0.0333 m2 - HOK 54,000 - -
Mesin Gilas 3 roda 6T 0.0167 m2 - jam 550,000 - -

K.617 Pekerjaan Burda


Batu pecah 2-3cm 0.0075 - m2 - m3 207,500 - -
Batu pecah 1-2 cm 0.0075 - m2 - m3 207,500 - -
Batu pecah 0,5 cm 0.0075 - m2 - m3 207,500 - -
Abu batu 0.0075 - m2 - m3 207,500 - -
Aspal 2.5000 - m2 - kg 10,968 - -
Kayu Bakar 0.0100 - m2 - M3 200,000 - -
Operator Terlatih 0.0133 - m2 - HOK 132,000 - -
Juru Godok 0.0089 - m2 - HOK 78,000 - -
Buruh terlatih 0.0089 - m2 - HOK 78,000 - -
Buruh tak terlatih 0.0444 - m2 - HOK 54,000 - -
Mesin Gilas 3 roda 6T 0.0296 - m2 - jam 550,000 - -

KPUT. MPekerjaan Latasir (sandsheet) M2


Pasir Beton 0.0200 1,500.00 m2 30.00 m3 250,000 7,500,000 7,500,000
Aspal 1.2500 1,500.00 m2 1,875.00 kg 10,968 20,564,516 20,564,516
Kayu Bakar 0.0180 1,500.00 m2 27.00 M3 200,000 5,400,000 5,400,000
Operator Terlatih 0.0200 1,500.00 m2 30.00 HOK 132,000 3,960,000 3,960,000
Juru Godok 0.0067 1,500.00 m2 10.00 HOK 78,000 780,000 780,000
Buruh terlatih 0.0067 1,500.00 m2 10.00 HOK 78,000 780,000 780,000
Buruh tak terlatih 0.0333 1,500.00 m2 50.00 HOK 54,000 2,700,000 2,700,000
Mesin Gilas 3 roda 6T 0.0222 1,500.00 m2 33.33 jam 550,000 18,331,500 18,331,500

Kebutuhan
Batu pecah 5-3 cm = 60.00 = 60.00 m3
Batu pecah 2-3 cm = 33.21 = 33.00 m3
Batu pecah 1-2 cm = 16.61 = 16.00 m3
Batu pecah 0,5 cm = 7.64 = 7.00 m3
Abu batu = 3.75 = 3.00 m3
Pasir Beton = 30.00 = 30.00 m3
Aspal = 7,875.00 = 51 drum
Kayu Bakar = 42.00 = 42 M3
Operator Terlatih = 47.14 = 47 HOK
Juru Godok = 18.60 = 18 HOK
Buruh terlatih = 67.14 = 67 HOK
Buruh tak terlatih = 156.07 = 156 HOK
Mesin Gilas 3 roda 6T = 76.33 = 9 hr
RENCANA ANGGARAN BIAYA
DESA SIDALANG KECAMATAN TERSONO
TAHUN ANGGARAN 2015

1. Bidang : 2.2 ( Pelaksanaan Pembangunan Desa )


2. Kegiatan : 2.2.1.4 ( Pembangunan Pengaspalan Jalan Latasir(sandsheet) )
3. Lokasi : JL DUKUH BONJOR
3. Waktu Pelaksanaan :
4. Volume :P 0 L 0
5. Rincian Pendanaan Rp 160,219,000.00

HARGA SATUAN JUMLAH


NO. URAIAN VOLUME SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
I Belanja Barang Dan Jasa
1 Honor Panitia
- Honor Penanggung Jawab 1 Orang 400,000 400,000
- Honor Ketua 1 Orang 250,000 250,000
- Honor Sekretaris 1 Orang 150,000 150,000
- Honor Anggota 3 Orang 100,000 300,000
Jumlah 1 1,100,000
2 Honor Perencanaan Swakelola
- Surveyor 1 Orang 150,000 150,000
- Juru Gambar 1 Orang 160,000 160,000
- Penbuatan Desain RAB 1 Orang 160,000 160,000
Jumlah 1 470,000

3 Upah Tenaga Kerja


- Mandor - HOK 72,000 -
- Operator Terlatih 47 HOK 132,000 6,204,000
- Pekerja 156 HOK 54,000 8,424,000
- Buruh Terlatih ( Tenaga Aspal ) 67 HOK 78,000 5,226,000
- Juru godog 18 HOK 78,000 1,404,000
- Sopir - HOK 72,000 -
Jumlah 3 21,258,000
4 ATK
-Hvs 70 gr 1 Rim 36,000 36,000
-Kalkulator 1 Bh 30,000 30,000
-Bolpoint 1 Pak 15,500 15,500
-Buku Kwitansi 9 Bk 5,000 45,000
-Materai 6000 10 Lbr 6,000 60,000
-Materai 3000 10 Lbr 3,000 30,000
-Buku Kwarto 2 Bh 15,000 30,000
-Tinta Printer 1 Btl 33,000 33,000
-Foto Copy 115 Lbr 200 23,000
-Stopmap Plastik 7 Bh 3,000 21,000
-Cetak Foto Kegiatan 15 Lbr 3,000 45,000
-Pelaporan 4 Bk 20,000 80,000
-Papan Proyek 1 Bh 150,000 150,000
-Prasasti 1 Bh 350,000 350,000
Jumlah 4 948,500
Jumlah Barang dan Jasa ( 1-4 ) 23,776,500
II
1 Material bahan
-Batu pecah 5-3 cm 60.00 m3 207,500 12,450,000
-Batu pecah 2-3 cm 33 m3 207,500 6,847,500
-Batu pecah 1-2 cm 16 m3 207,500 3,320,000
-Batu pecah 0,5 cm 7 M3 207,500 1,452,500
-Abu batu 3 M3 207,500 622,500
-Aspal 51 drum 1,700,000 86,700,000
-Pasir Beton 30 m3 340,000 10,200,000
-Kayu Bakar 42 m3 200,000 8,400,000
Jumlah 1 129,992,500
2 Alat
-Mesin Gilas 3 roda 6T 9 hr 550,000 4,950,000
-Mobilisasi Mesin Gilas 3 roda 6T 1 ls 1,500,000 1,500,000
Jumlah 2 6,450,000
Jumlah Belanja Modal 136,442,500
JUMLAH TOTAL ( I-II ) 160,219,000
Terbilang

................., ....September 2016


Disetujui / Mengesahkan Pelaksana Kegiatan
Kepala Desa .....................
................................ .......................................
PETA LOKASI PERENCANAAN PENGASPALAN JALAN
PATOK JARAK
0+000

0+050

0+100
0 PROPINSI JAWA TENGAH
0+150
0
0+200 KABUPATEN BATANG

0+250
KECAMATAN .....................
0+300
DESA
0+350 SIDALANG

0+400 JENIS PRASARANA


PENINGKATAN JALAN ASPAL
0+450
JUDUL GAMBAR
0+500 DENAH LOKASI KEGIATAN

0+550 DIBUAT OLEH


TPK
0+600

0+650 .............................
0
0+700 MENGETAHUI
0 KADES ...............
0+750 0

0+800 ...................................

0 0+850 MENGETAHUI
KASI. PMD
0+900

0+950 ..................................
NIP..................................
0+956,3
0 0
PROPINSI JAWA TENGAH
......m ......m

KABUPATEN BATANG
POTONGAN PERKERASAN LAPENSHEET

KECAMATAN .....................
SANDSHEET 1CM ( 1,25 KG ASPAL)
ASPAL 1 KG DESA
BATU PECAH 1/2 0.02
ASPAL 1,75KG 0.02 SIDALANG

BATU PECAH 3/5 kunci 2/3 0.03


JENIS PRASARANA
ASPAL 1,25 KG
PENINGKATAN JALAN ASPAL

JUDUL GAMBAR
DENAH LOKASI KEGIATAN

DIBUAT OLEH
TPK

.............................

MENGETAHUI
......m ......m KADES ...............

POTONGAN PERKERASAN LAPEN


...................................
ABU BATU
ASPAL 1 KG MENGETAHUI
BATU PECAH 1/2 0.01 KASI. PMD
ASPAL1,75KG 0.02
BATU PECAH 3/5 kunci 2/3 0.03
ASPAL 1,25 KG ..................................
NIP..................................